Você está na página 1de 3

Tech 101

How Offshore Capping Stacks Work


Mauricio Madrid and Antony Matson, Trendsetter Engineering, Inc.

Expectations and requirements for that is placed over the blown-out well as
subsea-well emergency response a cap. Its purpose is to stop or redirect
preparedness were stepped up as a the flow of hydrocarbonsand to buy time
result of the Macondo blowout and oil for engineers to permanently seal the
spill that began 20 April 2010 in the US well. It is massive and can weigh as much
Gulf of Mexico. A key change is the as 50 to 100 tons, presenting logistical
requirement to have subsea capping challenges in quickly transporting it to
stacks ready to be deployed that are the emergency occurring at the blown-
capable of handling the specific blowout out offshore well.
scenarios projected for each GOM well, Before the capping stack arrives,
no matter how challenging. a remotely operated vehicle (ROV)
It is very important to distinguish inspects the seabed site and
between a subsea blowout preventer engineerszero in on precisely what
(BOP) and a subsea capping stack. The equipment is needed. Then debris is
name of each piece of equipment gives removed and the wellhead is prepared.
some useful clues. As the names implies, After the equipment arrives, the capping
a BOP is a safety device meant to prevent stack is carefully maneuvered into place
a blowout from occurringthat is, to over thewellhead.
prevent an uncontrolled flow of liquids Once fully operational, the capping Fig. 1Macondo capping stack
and gases from reaching the surface. The stack provides a dual barrier for onboard Discover Inspiration
BOP is always present when drilling, and containmenta BOP ram, plus a 11July2010.
any time the drilling team suspects fluids containment cap. The stacks valves can
and/or gases could be released from be closed to cap the well (cap only) or, still leaking, other ways of containing the flow
the wellbore in an uncontrolled manner, if necessary, the flow can be redirected of oil were triedincluding a containment
they can activate the BOP to prevent such to surface vessels throughflexible pipes dome (7 May), top kill and junk shot (26
anoutcome. and risers (cap and flow). May), a cap for funneling oil and gas to a
A capping stack is not needed surface ship (3 June)all of which failed.
when drilling. It is the centerpiece of a Macondo Changed Requirements Meanwhile, the first capping stack
containment system kept in readiness at for Offshore Blowout Intervention specifically designed for the leaking
an onshore location. It is only deployed A capping stack had never been Macondo well (Fig. 1) was being put
after the BOP has failed to serve its developed for or used before 2010 together. It was a basic design consisting
purpose and a blowout has occurred. A specifically to contain a deepwater of three rams, a wellhead connector, a
capping stack is a piece of equipment blowout. In 2010, while the Macondo well was mandrel on top, a couple of double-block
drilling valves on the choke-and-kill
outlets of the middle ram, and associated
Mauricio Madrid is director of projects at Trendsetter ROV panels. It was installed on the lower
Engineering, Inc. In addition to being responsible for overall marine riser package on 12 July.
project management oversight, he also manages multiple This system did successfully cap
project teams with technical and commercial disciplines to the well, and provided the opportunity
develop, register, and commercialize multiple high quality, for engineers to perform a static kill
differentiated, and proprietary products for the company. (3August), drill a relief well during
Madrid serves Trendsetter Engineering in overall project August, and finally complete a bottom
coordination, planning and execution, cost and schedule kill, which led to the US federal
management, and design management, ensuring the company meets its government declaring the well dead
commitment to quality and safety. Beginning his career at ExxonMobil Development (September 21).
Company, he has worked exclusively in the oil and gas industry as a subsea One of the immediate deficiencies
engineer/project manager. Madrid earned a BS degree in mechanical engineering noted was the lack of a readily available
from Texas A&M University. backup capping stack for use should the

Vol. 10 // No. 1 // 2014 25


Tech 101

H4 Upper Mandrel One type is a connector designated


H4 with a large-bore perforated pipe
section or open pipe section that allows
Retrievable Chokes
the same through-flow as one single
Guidance Saddle for 18-in. bore. The second type is a
Running Tool (not pictured)
spreader bar that attaches to a frame
TEI Vertical Connection System with the bore completelyunimpeded.
c/w/ gasket change-out, softland
Acoustic Modem x2 The stack can be installed with the
and drawdown tooling
outlets open or closed, but each blowout
Dual 18 15K Ram scenario has to be analyzed to determine
with Blind Rams what will handle flow best.
Chemical Injection
Panel For example, in some cases, having
the outlets open could cause a Venturi
Dual Gate Valves ROV Control Panel
effecta jet effect that results in a
4 diverter legs reduction in fluid pressure and could
create hydrate formation problems in
Diverter Spool
deepwater scenarios as seawater is
TEI 24 channel cobra head Steel Flying Lead inadvertently sucked into the bore. If
possible, it is preferred that the bores are
HCH4 or H4 Multicore Hydraulic
Wellhead Connector Flying Lead opened when installing the stack because
this reduces the number of subsea
Fig. 2UK-based Oil Spill Response Limiteds Subsea Well Intervention Services operations that must be performed by
15,000-psi capping stack designed to cap a well in up to 10,000 ft water depth. the ROV to cap a well, thereby reducing
overall responsetime.
On at least two outlets there is also a
first one fail. Fortunately, it didnt fail, but circumstances, a crossover transition subsea connector with a choke package.
until the well was declareddead, several spool can be installed for interface to the The chokes are used to soft shut in the
alternative designs for capping stacks capping stack, similar to what was done well, meaning that the chokes slowly
were quickly generated. to install the Macondo capping stack. constrict flow from the well by gradually
On 22 July 2010, four major GOM The running tool for the stack must restricting the outlet bore size such that
oil and gas operators committed to take into account the flow coming from the flow gradually reduces to near zero.
establish a nonprofit company devoted to the blown-out well. Computational As chokes are wear items and take the
providing always-ready state-of-the-art fluid dynamic (CFD) studies have full differential pressure of shutting in
emergency well containment services been conducted showing that when the well, they are placed on subsea
and technology to all operators in the installing a capping stack in deep water connectors such that they are removable
USGOM. The resulting company, the on a high flow rate blowout well, as the and serviceable with the stack in place.
Marine Well Containment Company stackis positioned over the plume and Each choke is individually shut in
(MWCC) consortium, was created 10 as it approaches the wellhead interface, by the ROV. Since a closed choke is not
December 2010 and by 31 March 2011, a water post-effect occurs allowing considered a barrier, once the choke is
consisted of 10 member companies. stability and centralization of the stack shut in, the gate valve in line with it will
Today, consortia such as the MWCC, in relation to the wellhead. This is also be shut. As a result, erosion wear on
the Helix Well Containment Group in the veryconvenient! the valve sealing surfaces is minimized
US, and the Emergency Preparedness In fact, Bernoullis principle helps since there is little to zero flow and
Offshore Liaison Group in the UK explain the water post-effect in that pressure drop through the valve during
continue to advance their capabilities the fluid flow out the top of the well actuation, providing a recognized sealing
so their members can go on safely and through the capping stack bore barrier on eachoutlet.
exploring for new sources of oil. creates a force-centering effect on
the stack when it is being landed, thus More Capping Stack Capabilities
Offshore Deployment aiding in the make-up of the stack to the During the capping operation, chemicals
The basic operational need of the stack is wellheadmandrel. can be injected into the well through
to attach and seal on a subsea well during several strategically placed chemical
an active blowout, then shut in safely. Running to Depth and Installation injection ports (Fig. 2). These ports are
To achieve this, first a mandrel or hub There are typically two types of running located upstream of all sealing devices
profile must be exposed (either at the tools available for use with capping in the diverter spool central bore, and on
wellhead or on top of the BOP). In special stacks to date. the four outlets on the stack. This allows

26
an operator the option of injecting into continue to inject chemicals as needed Capping solutions have also been
multiple locations on the stack. and can continue to monitor pressure developed for tension leg platforms
For example, dispersant could be and temperature. that have a forest of risers underneath
injected into any or all of the ports to It is an industry-recommended them, with some risers no farther apart
minimize the environmental impact practice that two barriers (e.g., rams than 15 ft, requiring a very compact
of the oil flowing out of the blown-out and gate valves) exist between capping stack that can be maneuvered
well thereby minimizing the oil sheen hydrocarbons and the environment. and installed in close proximity to
on the surface. Methanol or glycol To achieve this once the stack is shut otherwells.
could also be injected to mitigate the in, the running tool is removed and a International communities of
formationof hydrates in deepwater secondary cap is installed to seal the operators, such as UK-based Oil Spill
cappingscenarios. bore with a metal VX-type seal on the Response Ltd. (OSRL), formed in 1985,
In addition to the ports, sensors are upper H4 mandrel instead of relying on now have specific efforts devoted to
placed on the diverter spool to monitor the rams rubber seal. Also, the subsea emergency subsea well intervention
pressure and temperature during all connectors with chokes are removed services and technology. OSRLs Subsea
shut-in operations. To transmit this and replaced by connectors with blind Well Intervention Service stores and
information to the surface, an acoustic rams to provide the secondary barrier maintains capping stack equipment
system is fitted on the stack that transmits on all the outlets. across four regions, with locations
pressure and temperature readings In some well control cases, it may in Norway, Singapore, South Africa,
through acoustic signals. The signals are make sense to pump kill fluids down the andBrazil.
picked up at the surface by a computer stack. In that scenario, the subsea con- In addition, emergency offshore
and a dunker that contains a surface- nectors with chokes can be replaced containment companies have evolved
deployed directional acoustic transducer by subsea connectors with flowlines the containment system approach to
and the transceiver electronics. The running to the surface for pumping address the time and vast amount of
acoustic system is powered by a local down kill fluids such as mud or cement. resources it takes to mobilize a capping
replaceable battery on the capping stack, The idea is that the capping stack will stack after an incident has occurred.
eliminating the need to run a cable or only be shut in long enough to drill the Since a capping stacks immensity
subsea umbilical during capping stack relief well to kill the well at its source and and weight present time-consuming
installation operations. cement it in. logistical challenges, the next step in
subsea source control hardware is to
Offshore Capping Stack Controls The Future of Well Containment bring response capability closer to
All controls on the stack are direct Today, specialized service companies the drilling operation. The Mudline
hydraulic from an ROV stab or have built a portfolio of capping stacks Containment Device (MCD) is a type
operated by an ROV torque tool. This for every offshore scenario, including of capping stack that provides direct
control philosophy is robust, and easy systems uniquely designed for shallow- capping and containment capability in a
to understand and operate under water Arctic drilling operations, for drill-through package.
emergency capping scenarios. Once which glory holes (also known as Having an MCD in place in lieu of or
all gate valves on the outlets and the well cellars) are excavated below the while waiting for the arrival of a capping
BOP are shut in, the well is considered seafloor to protect well equipment stack could greatly reduce emergency
capped, though the operator can such as BOPs from ice ridge scouring. containment response time should a
well control incident arise. The MCD is
installed directly on the wellhead and
Tony Matson, project manager, is responsible for the features an independent control system
execution and delivery of multiple projects at Trendsetter and power supply to act as a backup to
Engineering, Inc., including managing their commercial and traditional drilling controlsystems.
technical aspects. He has an extensive background in project Regardless of the type, subsea
controls disciplines. Since joining Trendsetter Engineering, capping stacks existence and
Matson has developed and implemented fundamental project deployment-readiness are now the
controls processes enabling improved project performance. norm. As the subsea drilling industry
Responsibilities include project planning, coordination and continues to evolve, more solutions
execution, cost and schedule management, and design management. Matson joined are emerging for subsea blowout
Trendsetter Engineering in 2012 after working in downstream petrochemical containment. Subsea capping stacks
construction for a major engineering, procurement, and construction contractor. are undoubtedly here to stay and have
Before working in oil and gas, he worked in automotive manufacturing and earned a added greatly to the offshore oil and gas
BS degree in management from Kettering University in Flint, Michigan. industrys emergency preparedness and
responsecapabilities. TWA

Vol. 10 // No. 1 // 2014 27

Você também pode gostar