1071001
HEARING
BEFORE THE
COMMITTEE ON
ENVIRONMENT AND PUBLIC WORKS
UNITED STATES SENATE
ONE HUNDRED SEVENTH CONGRESS
SECOND SESSION
ON
Printed for the use of the Committee on Environment and Public Works
(
U.S. GOVERNMENT PRINTING OFFICE
83697 PDF WASHINGTON : 2004
(II)
C O N T E N T S
Page
OPENING STATEMENTS
Bond, Hon. Christopher S., U.S. Senator from the State of Missouri ................. 5
Letter, Corps of Engineers reforms ................................................................. 6
Chafee, Hon. Lincoln, U.S. Senator from the State of Rhode Island .................. 18
Corzine, Hon. Jon S., U.S. Senator from the State of New Jersey ...................... 13
Inhofe, Hon. James M., U.S. Senator from the State of Oklahoma .................... 10
Jeffords, Hon. James M., U.S. Senator from the State of Vermont .................... 1
Reid, Hon. Harry, U.S. Senator from the State of Nevada .................................. 8
Smith, Hon. Bob, U.S. Senator from the State of New Hampshire ..................... 2
Voinovich, Hon. George V., U.S. Senator from the State of Ohio ........................ 14
Warner, Hon. John W., U.S. Senator from the Commonwealth of Virginia ....... 19
WITNESSES
Brescia, Christopher, president, MARC 2000 ....................................................... 47
Prepared statement .......................................................................................... 122
Brownlee, Hon. R.L., Acting Assistant Secretary of the Army (Civil Works),
Department of the Army ..................................................................................... 22
Prepared statement .......................................................................................... 60
Chase, Tom, director of environmental affairs, American Association of Port
Authorities ............................................................................................................ 38
Prepared statement .......................................................................................... 63
Responses to additional questions from:
Senator Jeffords ......................................................................................... 82
Senator Smith ............................................................................................ 84
Dickey, Ph.D., Edward ............................................................................................ 44
Prepared statement .......................................................................................... 112
Responses to additional questions from:
Senator Jeffords ......................................................................................... 118
Senator Smith ............................................................................................ 117
Ellis, Steve, director of water resources, Taxpayers for Common Sense ............ 42
Article, Taxpayers for Common Sense, The Construction Backlog .............. 109
Prepared statement .......................................................................................... 100
Report, The Distribution of Shore Protection Benefits, Draft Army Corps
of Engineers, November 2001, Comments of the Office of Management
and Budget .................................................................................................... 110
Feingold, Hon. Russell D., U.S. Senator from the State of Wisconsin ................ 19
Prepared statement .......................................................................................... 58
Fischer, Montgomery, director of water policy, National Wildlife Federation ... 40
Letter from several organizations to the chair, Council on Environmental
Quality and Director, Office of Management and Budget ......................... 96
Prepared statement .......................................................................................... 85
Responses to additional questions from Senator Smith ................................ 98
Summary, The State of the Nations Aquatic Resources .............................. 94
Flowers, Lieutenant General Robert B., Chief of Engineers, U.S. Army Corps
of Engineers .......................................................................................................... 23
Prepared statement .......................................................................................... 61
(III)
IV
Page
Holland, Lisa, state coordinator, Flood Mitigation Programs, South Carolina
Department of Natural Resources ...................................................................... 45
Prepared statement .......................................................................................... 119
MacDonald, Tony, executive director, Coastal States Organization ................... 49
Prepared statement .......................................................................................... 128
Robinson, Jr., Jim, Pinhook, MO ............................................................................ 51
Prepared statement .......................................................................................... 134
ADDITIONAL MATERIAL
Letters from:
Blehm, Kathleen K., project liaison officer, Yellowstone River Conserva-
tion Forum to Senator Jeffords dated July 28, 2002 ................................. 154
Yoder, Barbara, coordinator, Yellowstone River Conservation District
Council to Senator Jeffords dated July 26, 2002 ........................................ 153
Statements:
Daschle, Hon. Tom, U.S. Senator from the State of South Dakota .............. 56
Draper, Eric, director of policy, Audubon of Florida ..................................... 136
National Association of Flood and Stormwater Management Agencies ....... 150
Perciasepe, Bob, senior vice president for policy, National Audubon Soci-
ety ................................................................................................................... 138
Samet, Melissa, senior director of water resources, American Rivers ......... 141
Sepp, Peter J., vice president for Communications, National Taxpayer
Union ............................................................................................................. 135
WATER RESOURCES DEVELOPMENT ISSUES
AND CORPS REFORMS
U.S. SENATE,
COMMITTEE ON ENVIRONMENT AND PUBLIC WORKS,
Washington, DC.
The committee met, pursuant to notice, at 2:30 p.m. in room 406,
Senate Dirksen Building, Hon. James Jeffords (chairman of the
committee) presiding.
Present: Senators Jeffords, Bond, Chafee, Corzine, Inhofe, Reid,
Smith, Voinovich, and Warner.
Also present: Senator Feingold.
OPENING STATEMENT OF HON. JAMES M. JEFFORDS,
U.S. SENATOR FROM THE STATE OF VERMONT
Senator JEFFORDS. The committee will come to order. Good after-
noon and welcome. I would like to thank our witnesses for being
here. Today, we are going to hear from the Administration and a
panel of witnesses on the Army Corps of Engineers Water Resource
Program.
Since the passage of the Water Resources Development Act of
1986, every Administration has submitted a biennial legislative
proposal to the Congress containing project authorizations and pol-
icy initiatives. I understand a proposal from the Acting Assistant
Secretary is at the Office of Management and Budget. However, we
have not received a proposal yet. There is very little time remain-
ing in this legislative session, and if we want to act this year we
are going to have to have something to move on.
Working with Senator Smith and members of this committee, I
hope to introduce a legislative proposal before the July 4 work pe-
riod. Many want the legislative proposal that this committee con-
siders to include what is being referred to as Corps reform. There
have been press reports and GAO reports suggesting that the
Corps needs and overhaul. One of the reasons we are here today
is to get input from other witnesses on possible changes to the
Corps Water Resources Programshow the Corps could be more ef-
fective and efficient.
Senator Smith and Senator Feingold, who is joining us this after-
noon and is here, have introduced legislation that would make sev-
eral changes in the way the Corps does business. I intend to con-
sider all views and work to develop legislation that will keep the
Corps on its biennial planning schedule and help the Corps deliver
their much-needed services of storm damage reduction, navigation
and environmental restoration.
(1)
2
worked a long time on this issue, and we were able to join forces
and I am pleased that we were able to do that. I know he will be
instrumental in helping us to usher Corps reform through, what-
ever the vehicle might be ultimately.
Finally, Mr. Chairman, one theme repeated in the written testi-
mony of those opposed to Corps reform is that independent review
will delay the study process. I would like to just say for the record,
peer review would apply to every project, only a handful that merit
such review. The review would be conducted concurrently with
headquarters review, not in any other methodology. It is ridiculous
to think that a 180-day concurrent review is going to add years to
a study process. That is not going to be the case. How is it going
to add any more years than the 30 years we have been sitting
watching projects lay on the books accumulating $52 billion in back
dollars?
Some have said, why havent you waited for the recommenda-
tions of the National Academy of Science, which is due to issue its
report this summer? I understand enough about the issue to formu-
late a meaningful procedure. If NAS comes out with a dramatically
different recommendation, then it will have my serious consider-
ation. Finally, this issue is important enough to move forward im-
mediately.
In closing, again, I really feel strongly that there should be no
WRDA bill in 2002 without Corps reform. Lets not add insult to
injury. But I look forward to what the witnesses have to say, and
thank you, Mr. Chairman.
[The prepared statement of Senator Smith follows.]
STATEMENT OF HON. BOB SMITH, U.S. SENATOR FROM THE
STATE OF NEW HAMPSHIRE
Good afternoon. I would like to thank everyone for coming today to discuss issues
pertaining to the water resources development program within the Corps of Engi-
neers. Specifically, I hope to see this hearing highlight an issue of great importance
to me: Corps Reform. I expect Corps Reform to be an integral component of the
Water Resources Development Act of 2002.
I would like to take a moment to state for the record: contrary to what has been
said about me, I am not opposed to the Corps of Engineers. The Corps certainly has
an important role to play in both the national security of our country and in its mis-
sion areas of navigation, flood damage reduction, and environmental restoration.
However, I think we have a unique opportunity to help the Corps address some of
its internal problems that have resulted in a loss of confidence in this agency. Inci-
dent after incident of flawed analyses, overstatement of benefits, flat out miscalcula-
tions whether intentional or accidental are not only difficult to ignore, but outright
intolerable.
Initially, I wanted to give the benefit of the doubt to the Corps. Id like to quote
my friend Senator Voinovich, who at a Corps budget hearing last year said, fool
me once, shame on you. Fool me twice, shame on me. Enough chances have been
given to the Corps to take meaningful steps internally to address concerns.
One cannot overlook reports in 1999, 2000, 2001, and most recently, last week,
issued by such impartial, non-partisan institutions such as the National Academy
of Sciences, the General Accounting Office, the Army Inspector General, all of which
contain the same message: something is not right in the Corps. Something is bro-
ken. And it needs fixing.
It is clear to me now that legislation is necessary to help the Corps fix whats bro-
ken. I want to work with the Administration and my colleagues on the Committee
to negotiate something meaningful, yet effective. I am sure you all know by now
that I introduced legislation, the Corps Modernization and Improvement Act to re-
form the Corps. In fact, I would like to thank my colleague and co-sponsor, Senator
Feingold, for joining us here today to give his views on the issue. I have to credit
him with first bringing the issue to my attention 2 years ago when we were on the
5
Senate floor considering the 2000 WRDA bill. I look forward to working with him
to usher Corps Reform through this committee and the Senate.
One theme repeated in the written testimony of those who are opposed to reform-
ing the Corps is that the Independent Peer Review process will unnecessarily delay
the study process and will raise project costs. I would like to quickly address those
concerns.
First of all, Peer Review would not apply to each and every project that the Corps
constructs. I view this as only applying to a small handful of projects that for some
reason or another merit further external review. Also, the way the provision is
structured in my bill, the review would be conducted concurrently with head-
quarters review. It is ridiculous to think that a 180-day concurrent review is going
to add years to the study process. Unless of course, that review reveals major flaws
in the project analysis, in which case, the project should not go forward until the
study is revised anyway.
Many have asked me why I am not waiting for recommendations from the Na-
tional Academy of Sciences, which is due to issue a report this summer on Inde-
pendent Review. For one, I think I understand enough about the issue to formulate
a meaningful procedure. Second, if the Academy comes out with a recommendation
that is dramatically different than what I have in my bill, I will look at revising
my provision as the WRDA bill moves through the legislative process. Finally, I
think this issue is important enough that it is worth moving forward now.
In closing, let me make my intentions clear: there will be no WRDA 2002 without
Corps Reform. In case you didnt hear that, I repeat: NO WRDA WITHOUT CORPS
REFORM. With that said, for those who are opposed, instead of issuing threats to
hold up any WRDA bill that includes reform, work with me, and work with the com-
munity that supports Corps Reform to resolve our issues so that we can attempt
to reach a workable compromise.
With that said, I look forward to the discourse we are about to hear.
Senator JEFFORDS. Senator Bond.
Sand Lake, OK was studied in 1950s and 1960s and found to be in the Federal
interest. A proposed dam would have been located at the river mile 19.1 on Sand
Creek near Bartlesville, Oklahoma. The project was authorized by the Flood Control
Act of 1962 for flood control, water supply, water quality control, recreation and fish
and wildlife. However the project was place in deferred status in 1984 pending reso-
lution of conflict with the Osage Indian Nation regarding mineral rights subordina-
tion. The project was eventually deauthorized in 1999.
Since then, it has become clear that the city of Bartlesville must find a second
water source. Currently the City gets all of its water out of Lake Hulah which be-
came dangerously low this past spring. The community is interested in exploring
again the feasibility of Sand Lake. Preliminary discussions with the Osage tribe in-
dicate the tribe is willing to negotiate on the mineral rights.
TECHNICAL CHANGE TO A LAND TRANSFER AUTHORIZED IN WRDA99
The city of Edmond became a cost share partner with the Corps in 1979 for rec-
reational development and water storage facilities on Arcadia Lake. In 1987 a dis-
pute arose with the Corps over cost overruns on the recreation facilities. That dis-
pute was settled in 1992 through a Consent Decree. Included in that Consent De-
cree was a provision that the city of Edmond thought would clarify a potential fu-
ture dispute regarding the requirement to pay storage on future water use. Per the
terms of the Consent Decree, the City was not liable for payment of future use
water until such time that City decided to actually use the water. The cost of the
future use water was set at $27 million, which the City paid in October 1999.
In November 1996, the City was notified by the Corps that they had to beginning
paying interest on the future use water storage because the 10-year interest free
period following the projects completion had expired (projected was completed in
1986). However, the City believes that the Consent Decree clearly stated that they
were not liable for the future water until such time as they made use of it which
occurred in 1999 when the City paid $27 million. The Corps continues to charge the
City interest from November 1996 to present. I will be requesting WRDA02 clarify
that City is not liable for the interest from November 1996 to October 1999.
TECHNICAL CORRECTION TO THE DEFINITION OF INDIAN LANDS
Because Oklahoma does not have any Indian reservations, we need to make a
clarification in the law with the respect to the definition of Indian lands. I will pro-
pose that the definition of Indian lands in Oklahoma for Corps of Engineers pur-
poses be modified to be consistent that the definition for Indian lands in the High-
way program.
13
TRANSFER OF FLOW EASEMENTS ON GRAND LAKE, OKLAHOMA TO GRAND RIVER DAM
AUTHORITY
I am working with both the Tulsa District Corps office and the Grand River Dam
Authority (GRDA) to transfer Flow Easements on Grand Lake to the GRDA. Grand
Lake is not a Corps lake and there is no logical reason for the Corps to be involved
in the lake. Both parties are interested in seeing this transfer accomplished.
AUTHORIZATION OF 12-FOOT DEPTH ON THE ARKANSAS RIVER NAVIGATION CHANNEL
working relationship with the Detroit, Rock Island and St. Paul
District Offices that service Wisconsin. So let me be clear, as many
of the members of the committee have, I want the fiscal and man-
agement cloud over the Corps to dissipate so that the Corps can
continue to contribute to our environment and our economy.
The two reforms bills now before the committee grew in part
from my experience in two legislative efforts. First, as the com-
mittee knows, I sought to offer an amendment to the Water Re-
sources Development Act of 2000 to create an independent review
of Army Corps of Engineers projects. In response to the initiative,
the bills managers adopted an amendment as part of their man-
agers package that should help this committee the additional infor-
mation it needs to develop and refine legislation in this issue
through a study on peer review by the National Academy of
Sciences.
Second, I also learned of the need for additional technical input
into the Corps projects through my efforts in working with Senator
Bond on the reauthorization of the Environmental Management
Program in the Upper Mississippi, which was the only permanent
authorization in WRDA 1999. Included in the final EMP provisions
is a requirement that the Corps create an independent Technical
Advisory Committee to review EMP projects, monitoring plans and
habitat and natural resource needs assessments.
Mr. Chairman, I have been deeply concerned that this provision
has not been fully implemented by the Corps and I feel that as this
committee has been historically concerned about the need to secure
outside technical advice in Corps habitat restoration programs like
the EMP, it should also be concerned about getting similar input
for other Corps construction activities.
Early this Congress, I introduced the Corps of Engineers Reform
Act of 2001, S. 646, and then as Senator Smith indicated, I joined
with him and Senator McCain and introduced the Corps of Engi-
neers Modernization and Improvement Act of 2002, S. 1987. S.
1987 includes many provisions that were included in my original
bill, and it codifies the idea of independent review of the Corps,
about which Senator Smith and I agreed in the 2000 Water Re-
sources bill.
It also provides a mechanism to speed up completion of construc-
tion for good Corps projects with large public benefits by
deauthorizing low-priority and economically wasteful projects. Fur-
ther, it streamlines the existing WRDA 8060 authorization process.
Under Senate bill 1987, a project authorized for construction but
never started is deauthorized if it is denied appropriations funds
toward completion of construction for five straight years. In addi-
tion, a project that has begun construction, but denied appropria-
tion funds toward completion for three straight years, is also de-
authorized.
The bill also preserves congressional prerogatives over setting
the Corps construction priorities by allowing Congress the chance
to reauthorize any of these projects before they are automatically
deauthorized. This process will then be transparent to all interests,
because the bill requires the Corps to make an annual list of
projects in the construction backlog available to Congress and the
public at large via the Internet. The bill also allows a point of order
21
feelyou may feel that it is in the sense of who it might be, whose
district it is, whose State it is, or whatever. If we had independent
review, and I would say to you that my objective on any kind of
independent review is not to add another level of bureaucracy. On
the contrary, it would be to expedite, rather than delay. But if we
had some type of independent review, if it would be done in a way
that did not lengthen the process, perhaps maybe, say, 6 months
while the draft feasibility is being prepared, something along those
lines. Would that remove some of the political concerns that you
might feel in addressing a problem in somebodys State or district?
General FLOWERS. Sir, I do not know if it would remove political
concerns. I think the Corps is not afraid of independent review. I
testified last year that any type of external review or independent
review that might be done, as long as it did not appreciably add
time or expense to a project, would be welcomed by the Corps. We
have had a number of our projects reviewed.
But I must state that as an organization, what we do is try to
provide the best engineering and science that is available, and base
our commendations on that. I was questioned in testimony last
yearyou know, General, did you receive political pressure when
you put this budget together? The answer is yes. But if the ques-
tion is, did it cause you to change any of your recommendations,
the answer is absolutely not. They must be based on the best engi-
neering and science available. That is why some of the things that
have come up are so troubling, and I understand. We need to work
together to get that fixed.
What I am saying, sir, I think is, I will make sure that the
things we do are done right, but I need some help in making sure
that we are working on the right things.
Senator SMITH. At least if there is independent review, you have
got a little cover if they tend to agree with you. Right?
Let me ask you this, and maybe Secretary Brownlee could an-
swer this, in the situation where you have very little traffic on a
waterway, and then you see proposals to dredge it deeper or to do
more with that waterway, is it unfair to ask those who use that
waterway, that very limited waterway, is it unfair to ask them to
increase their burden for the usage of it?
Mr. BROWNLEE. Senator, the decision on those kinds of projects
of course are made here. Generally, the projects get authorized and
appropriated and then the Corps ends up doing them. The issue of
fairness with respect to the expenditure of Federal funds is one
that is probably a lot bigger than I am, but I do not know and I
listened very intently to your example. I also listened very intently
when Senator Voinovich made some of the points he made, to make
a note to go back and look into those things. Senator, the fairness
of that, I do not know. We spend a lot of money on a lot of things
in this countryon national security and economic development.
As I indicated, those decisions are usually made here by commit-
tees like this and on the floor of the Congress. The responsibility
does lie here.
Senator SMITH. General Flowers, I mentioned it, and I think
somebody else mentioned it in their remarks, the example of the
118 projects, the economic analysis that came back. Some have said
it was 80, not 118but whether it is 80 or 118, came back in 17
28
days. Can you just shed some light on that? Is there a reason why
it was only 17 days? Could you enlighten the committee a little bit
on that?
General FLOWERS. Yes, sir. As a result of an out-briefing we re-
ceived from the Government Accounting Office, it indicated to me
that for good governance, I needed to initiate a stop on any projects
that had economics over 5 years old, because essentially what was
found was economics that had been done over 10 years ago and had
not been properly validated or updated. I wanted to make sure,
very embarrassing, but essentially there was no audit trail to the
original benefits that were derived for this project. So I wanted to
make sure that we did not have same situation occurring in
projects where we had done economics that were over 5 years old.
There were some 171 projects that were reviewed. Of those 171,
there were eight projects that were going to require some addi-
tional analysis. In other words, those remaining projects, the eco-
nomics did have an audit trail and were verifiable by the people
who had done the work.
Senator SMITH. Is it possible for you to provide the committee
with the economic analyses on those projects? How much of an ef-
fort does that require?
General FLOWERS. Sir, yes, sir. In fact, the economic analyses on
all of those projects is public record. So absolutely.
Senator SMITH. It would be helpful to me just to see the process,
to see if we are being unfair in terms of saying you came back in
17 days with 80 or 118 or somewhere between number of projects.
I would like to just have the opportunity just to review that to see
what your process is so that I can understand it better. So I would
appreciate it if you could provide that for the record at some point.
General FLOWERS. Yes, sir.
Senator SMITH. Thank you, Mr. Chairman.
Mr. BROWNLEE. If I could just add, sir. When this information
came to light, I would just like to point out to the committee that
General Flowers and his people came to see me on this. They were
extremely embarrassed and frustrated by this kind of a report. Cer-
tainly, in the discussions I have had with them they are extremely
conscientious about this sort of thing and it is horribly embar-
rassing to them that this happened. But they have already taken
steps to consolidate some of their expertise in these areas to help
improve. As has been indicated before, hopefully the recommenda-
tions of the National Academy of Sciences that this committee put
in motion will help also.
Senator SMITH. Thank you very much.
Senator JEFFORDS. Senator Bond.
Senator BOND. Thank you, Mr. Chairman.
General Flowers, you have a lot of projects on your plate. These
are not projects you stay up late at night and dream up. They are
local and regional projects. Who brings these ideas to you and
where do you get them from?
General FLOWERS. Sir, you are making a great point, and that
is the Corps does not dream up any of its projects on our own. All
of these projects come forward based on some public request, either
from elected officials, local entities. Many of them come about as
a result of studies that are conducted into the feasibility of accom-
29
one way or the oil people going the other way, whether or not they
are going to be able to get all the way down to the Mississippi.
These things are justwe have to get some way we can get these
things done. I know that is not the purpose of this hearing, but it
is one that I hope that the general public can look at the charts
that Senator Voinovich held up and be concerned with them.
Now, General Flowers, we are really dealing here with three
things. You have got your national security. Youve got economic
development and environmental protectionthree things. How do
you do all three things?
General FLOWERS. Sir, I think the Corps is a great contributor
in all three areas. National securitymany of the ports that we
maintain are our strategic deployable ports for this country. I think
the inland waterway system gives us an agility to move within our
borders that is the envy of most of the rest of the world.
Senator INHOFE. I might add in moving our National Guard
around from place to place, that has ended up being the most cost-
effective way of doing it, and has saved a lot of money to other
areas of defense, hasnt it, Secretary Brownlee?
Secretary BROWNLEE. Yes, sir.
General FLOWERS. We have been able to use the expertise we
have gained. We have set up an infrastructure security partner-
ship. It is an association of associations, several Federal agencies,
many national associations such as the American Society of Civil
Engineers, the architects, the contractors, to come together and
share information on how to better protect the Nations built envi-
ronment. So we are making a contribution there.
I think when you look at the economy, money that is put into in-
frastructure that has a positive benefit-cost ratio does in two
waysshort-term, there is an infusion of money into the local
economies through the contracts that are done; and then longer
term to the treasury in terms of benefits realized. So I think we
contribute that way economically. So national defense and the
economy are two things that I think the Corps is a great contrib-
utor in.
Senator INHOFE. There is a phrase that I had not seen before,
but I saw in your written statement. You said, scenario-based com-
prehensive planning. So I will go ahead and add that to a question
I am going to ask. What legislative tools and financing changes do
you need to pursue this scenario-based comprehensive planning,
enhance public participation, increase roles for peers and technical
experts in streamlining of your economic planning and engineering
processes?
General FLOWERS. Sir, I think what we would ask for would be
the authority to do comprehensive basin-wide studies, using an
interagency process and apply more macroeconomic and larger-
scale scenarios to take a look at outcomes. I think the engineering
and science is good enough today, sir, to do very models that have
great fidelity, using the automation, the digital terrain data and so
forth that we have, and to provide better options to the decision-
makers for prioritizing and making sure that we are in fact accom-
plishing the right work.
Senator INHOFE. Mr. Chairman, I heard Senator Corzine talk
about oversight, and I kind of whispered to Senator Smith, isnt
33
sionalism of it. All of the people that I have met within the Corps
of Engineers, I believe, are striving for that.
So certainly we want to improve the methods by which the Corps
does its business. I also believe, as I indicated in my statement,
that we need to work hard to try to develop a national consensus
on what our policies ought to be with respect to our water re-
sources. I think we are beginning to realize that these water re-
sources that we may have taken for granted over the years are not
infinite.
So anyway, I know this committee knows a lot more about these
matters than I do, but I do have to say that I have been impressed
by the efforts I have seen in the Corps thus far, and their ability
to do what they do with what they have.
Senator CHAFEE. Thank you, Mr. Secretary.
General Flowers, Senator Feingold was, I believe, talking about
specific legislation that he and Senator McCain are introducing rel-
evant to the Corps. Do you have a position on that legislation?
Senator JEFFORDS. Are you aware of the legislation? Have you
seen it?
General FLOWERS. Sir, I have not reviewed in detail the legisla-
tion. I am aware of some of the provisions.
Senator CHAFEE. That is fair enough.
Senator JEFFORDS. Can we ask you to take a look and give us
your recommendations or any comments that you have? We would
appreciate that.
General FLOWERS. Yes, sir.
Mr. BROWNLEE. Senator, I did read through the side-by-sides of
the legislation as near as I could, and those of you who have done
that know that is kind of an agonizing process, but I forced myself
to do it. The last thing I would want to do is be critical of some-
bodys efforts to make something better, because I know Senator
Smith and I worked for him many years on Armed Services Com-
mittee, and everything I saw him do was characterized by his dedi-
cation and desire to make things better, and tireless efforts in that
regard, I might add.
But as I looked at this legislation, I just kind of jotted down some
questions that came to my mind. I might just kind of track through
those questions, if you would like, for the committees benefit. The
first one was, how will the National Academy of Sciences rec-
ommendations on independent review, which is expected to be re-
ceived later this summer, be factored into this bill? I know Senator
Smith said he was certainly willing to consider that, and I sure he
will. I just do not know how that would be factored in.
Are the bills current provisions expected to be consistent with
the Academys recommendations? I am not sure if any of us know
that at this point in time. How do provisions of the bill directly con-
tribute to improving the technical capability and competence of the
Corps of Engineers? Is the primary goal of the bill to shift the em-
phasis of the Corps away from economic development and more to-
ward environmental restoration, or at least to make it more dif-
ficult to justify economic development projects? What would be the
effect of the bill on the Nations marine transportation system and
the resulting impact on international trade and competitiveness? In
37
general, how does this legislation equip the Nation to better deal
with growing water resources challenges of all kinds?
I just submit those, not to anybody specifically, justI think that
. . .
Senator CHAFEE. You do not have a firm position on the bill
just some questions?
Mr. BROWNLEE. As I indicated, Senator, the Administration, the
Corps, myselfwe are all willing to workI have talked to Senator
Smiths staffto work with the members of this committee, the in-
terested members. Senator Bond mentioned a letter that had been
signed which I have seen. I would certainly expect that we work
with a group, that it could include members of that group. If there
is a way to do a Corps reform bill in that regard, we are certainly
willing to pitch in and help.
Senator JEFFORDS. Thank you very much, and thank you for
very, very excellent testimony. It gives us confidence when we lis-
ten to you that we will be able to make some improvements and
have it work a little bit better.
Senator SMITH. I might just say, Mr. Chairman, while they are
getting prepared to leave the table, that I take those questions in
the spirit they are intended. The objective is to work together to
hear your input, and we will go back and review those topics that
you brought up. It is also obvious that you are not quite ready to
go to heaven yet.
[Laughter.]
Senator JEFFORDS. Thank you very much.
We do have another panel. Obviously, we have a number of peo-
ple hereall very good, excellent witnesses. But if you want to im-
press the members that are left, if you can keep your statements
to around 3 minutes, that would be appreciated. Under the rules,
you are allowed five, so I will not interrupt you, but we would be
grateful if you can do that.
Senator SMITH. We will just ask you nasty questions after it is
over.
[Laughter.]
Senator JEFFORDS. We will start with Mr. Chase.
Senator BOND. Mr. Chairman, as I mentioned to you, I was ready
to make a Faustian bargain with you to give up my right to ask
questions if you would let me give a very brief introduction to two
good friends who are here. I have a longstanding appointment that
I have to make.
Senator JEFFORDS. You have a deal. You have a deal.
Senator BOND. I figured that this would be a good deal. This
would save you about three and a half minutes.
Senator JEFFORDS. That is right.
Senator BOND. Chris Brescia has been an expert on river trans-
portation issues. I hope that you will read very carefully his very
thoughtful statement. I have read it, and it will be submitted in
full for the record. It really gives an idea of the importance of this
water transportation issue.
My second friend is Mr. Jim Robinson of Pinhook, MO. He has
been working on closing a hole in a levee for 26 years. They first
testified before this body, the first testimony was by Senator Eagle-
ton. He has come up here time and time again. Back in 1999, 2000,
38
he came up after the President flew into the delta and said we
were going to protect the delta. The Vice Presidents office came
out, look at itAlvin Brown of the USDA came out and look at it.
They were assured by the Council of Environmental Quality that
they were going to get it done. After the election, it was sent back
to the Corps for its supplemental, supplemental, supplemental,
supplemental study.
Mr. Robinson, it is a real pleasure to welcome you and Mrs.
Aretha Robinson. When you testify, I hope you will tell us why
your family settled where you did and why you stay. Tell us why
you, your families and your neighbors do not just do what all the
smart people have done and move to Washington, DC. to get a job
where the wetlands are already permanently destroyed, and you do
not have to worry about little issues like stopping floods. I think
that the testimony that you have given will be very, very compel-
ling. If anybody misses it, I will be repeating it frequently.
I thank you, Mr. Chairman, and Senator Smith, and I thank all
of our witnesses.
Senator JEFFORDS. The first witness is Mr. Chase.
STATEMENT OF TOM CHASE, DIRECTOR OF ENVIRONMENTAL
AFFAIRS, AMERICAN ASSOCIATION OF PORT AUTHORITIES
Mr. CHASE. Thank you, Mr. Chairman.
I have been going through my testimony trying to cut it back,
and I will do my best.
On behalf of the 85 public seaport members of the American As-
sociation of Port Authorities, we thank the committee for the op-
portunity to discuss the importance of the Corps of Engineers pro-
grams.
There are two points I want to leave with the committee today.
First, the Nations marine transportation system is highly decen-
tralized, market-driven, and returns untold benefits to U.S. busi-
nesses and consumers. Second, the Congress needs to fully fund the
Corps of Engineers Civil Works Program and authorize new navi-
gation projects and policies that meet the needs of the Nations
businesses and consumers. We urge the Congress to seriously re-
view the impacts of any proposed changes to the procedures used
to evaluate navigation projects to avoid needlessly increasing the
cost or further delaying the construction of deep-draft navigation
projects.
The deep-draft commercial ports of the United States handle over
95 percent of the volume and 75 percent of the value of cargo mov-
ing into and out of the Nation. All commercial ports and navigation
channels serve multistate needs. On average, each State relies on
between 13 to 15 ports to handle its imports and exports. For ex-
ample, 14 ports handle more than 1 percent of Vermonts foreign
trade. Four ports are on the West Coast, four ports are on the Gulf
Coast, and six are on the Atlantic Coast.
Between 1993 and 1997, U.S.-foreign waterborne grade grew by
4.6 percent per year to over one billion metric tons, and now ac-
counts for about 20 percent of global waterborne trade and almost
30 percent of U.S. gross domestic product. The number of con-
tainers moving through U.S. ports doubled between 1990 and 2000,
from 15.3 to 30.4 million TEUsthe unit of a 20-foot equivalent
39
ered. The model does not consider the impact that long-term dam-
ages will have on the Federal budget as it is related to disaster
payments. NED has a role in the decisionmaking process, but it
needs to be balanced with other planning objectives. The complex-
ities of this problem cannot be solved in a limited testimony and
should not be crafted on the fly through the legislative process.
What should be done, however, is to direct the Administration to
develop revisions to P&G to reflect the current realities, broaden
the approach such as the NED as part of the decisionmaking proc-
ess, and finally, directs the Administration to consider the project
formulation and delivery process.
In closing, the Association of State Floodplain Managers urges
you to act swiftly and judiciously in modernizing the policies of the
U.S. Army Corps of Engineers in the areas of cost-sharing and re-
vising the outdated principles and guidelines.
Thank you, Mr. Chairman.
Senator JEFFORDS. Thank you. Very good work.
Mr. Brescia.
STATEMENT OF CHRISTOPHER BRESCIA, PRESIDENT,
MARC 2000
Mr. BRESCIA. Thank you, Chairman Jeffords, members of the
committee. My name is Chris Brescia. I am President of MARC
2000. MARC 2000 is composed of leading agricultural, industrial
and labor groups in the Midwest, and I am pleased to appear here
to address Water Resource Development Act of 2002 proposals.
We have a proposal of our own that we are putting forward that
urges Congress to support the authorization and construction of an
initial group of seven new 1,200-foot locksfive on the Upper Mis-
sissippi, two on the Illinoisguidewall extensions and appropriate
mooring cells. That proposal is in more detail in my written text.
However, I want to emphasize that this proposal is limited to the
placement of new locks at only 7 out of 37 possible locations at the
lower portion of the river system just north of the confluence of the
Upper Mississippi and the Illinois Rivers. We are not advocating
new locks on the entire 1,202 miles of the basin system.
We also strongly support an enhanced environmental restoration
effort for our basin, with a reliable and consistent funding mecha-
nism. Our proposals third element calls for timely completion of a
WRDA 1999-authorized comprehensive plan designed to develop an
integrated flood control system in our basin. According to the U.S.
Department of Transportation, maritime trade is expected to dou-
ble in less than 25 years. Freight in the United States is expected
to clog the Nations highways and our rails. Experts project grain
trade will increase two-thirds or more by 2020.
The Corps of Engineers has documented an anticipated 60 per-
cent increase in likely tonnage movements on the Upper Mis-
sissippi and Illinois Rivers. Our waterway system is a logical
means by which we can accommodate growth, reduce incidence of
spills, air pollution accidents, and deaths to our population. Water
traffic options save more than $700 million a year to our Nation
directly, and another $900 million in our basin alone.
But todays river system is operating at 75 percent capacity, with
antiquated infrastructure. There is no way to meet these future de-
48
nomic needs of this country and the coastal States, as well as the
environmental baseline on which we must rely.
But policyI think I was very encouraged to hear General Flow-
ers remarks regarding broader regional and watershed planning.
That is something the States strongly support. However, I have to
say that the policy must be supported by enhanced partnerships
with the States and a greater reliance on the expertise of States
and other local project sponsors and coastal, watershed, and basin-
wide management. This committee has a lot of experience with
those things, I think, and the expertise of other parties, and I think
the Corps could benefit from sharing some of its expertise with us,
and us with them.
There needs to be in any effort for reform for the Corps must
take into account these multi-purpose, multi-stakeholder efforts
that get beyond rigid national economic benefits formulae and in-
clude the value of economic, cultural and social inputs.
You have already heard a lot today about the significant eco-
nomic and environmental importance of the Corps water resources
mission, as well as the substantial economic return to the Federal
treasury that results from Corps projects. That is all true and we
strongly support that. As recently observed by a 2001 Federal Re-
serve Bank of Kansas City report, the United States is a coastal
nation. It says, quote, The coastal concentration of U.S. economic
activity reflects a productivity effect of access to navigable waters.
That has been true historically. That is true today. I think it will
be true for our future as well, so that is why this is important.
However, controversy over port development projects in places
like the Delaware River, Charleston, South Carolina, and the Co-
lumbia River clearly demonstrate the importance of incorporating
more local and regional concerns into the Corps planning processes,
along with the consideration of national benefits and the Federal
standard of the least-cost environmentally acceptable alternative.
As has been mentioned many times, historically Corps projects,
some of them, have undermined the integrity and function of nat-
ural littoral systems, and the natural flow of sand and other sedi-
ment material, resulting in sediment starvation and erosions along
the shoreline. Shoreline erosion and sea-level rise and lake-level
change will pose increasing challenges for States and the Nation in
the years ahead. It is very important that we consider these things
now.
Coastal States strongly support continuation of the Federal-State
partnership in coastal storm protection and beach nourishment
projects. Beaches are magnets for international as well as domestic
tourism and provide readily accessible recreation and respite for
millions of families from very diverse urban and rural areas that
may not have other options. The same beaches serve, as previously
alluded to, as natural barriers for flooding, waves, and storm
surges and provide cost-efficient and environmentally preferable al-
ternatives for protection of life and property. A recent Corps of En-
gineers study of six coastal communities in North Carolina show
that the communities with shore protection projects suffered sig-
nificantly less from Hurricane Fran. Shore protection projects can
protect lives and save money in the long run.
51
Senator SMITH. Thank you very much, Mr. Robinson. As you can
see, the Chairman had to leave to go vote, and he is going to come
back and then I will leave. Senator Chafee, do you want to ask a
quick question? We apologize to the witnesses for that, but we are
trying to keep from inconveniencing you so we can keep things
flowing.
Let me just ask a quick question. Mr. Dickey, on the legislative
benefits, and we accept your comments in the spirit they were in-
tended and we will try to see if we can improve what we are trying
to do as a result of your expertise, but you use the term legislative
benefits. Were you referring specifically to us saying that it ought
to be 1.5 as opposed to 1.1 return for the dollar? Is that where you
were coming from? What specifically were you . . .
Mr. DICKEY. Senator, I have in mind that the supervision, and
I do not remember the exact language, but to the effect it says
that, you know, you cannot count any benefit that somehow is a
private versus a private benefit. As an economist, I have a hard
time understanding what that means, since benefits are based on
the willingness of individuals to pay. The situationthere is an-
other example, too, of where, say, dont count any benefits if they
result from draining or altering a wetland. To me, that says, gee,
they have said wetlands are infinitely valuable. They do not care,
you know, what the tradeoff is. The essence of good water planning
is to have tradeoffs and tradeoffs that are informed on the basis
of analysis. So that is why I really want the analysis.
Senator SMITH. I think that is right. I would also say, too, there
could be benefits derived from something that are not necessarily
monetary. There may be a national security benefit. There may be
an environmental benefit. There may be some other benefit. That
is not necessarily to say we have to get 1.5 dollars back for every
dollar invested. Let me, Mr. Fischer, on theif I asked you to just
give me one location anywhere in the country that would have the
lowest economic priority and the greatest negative environmental
impactin other words, someplace we ought to fix, where would
that be in all of the waterways that we have?
Mr. FISCHER. The lowest economic priority, if you are talking
about a Corps project?
Senator SMITH. Yes. A project out there that does not yield very
much economically in return for the dollar, but impacts negatively
on the environment.
Mr. FISCHER. I would say the Yazoo Pump Project would be the
ones that we have focused on over the years as having probably
if you measure the environmental impact on that, along with the
economic cost-benefits, that is one that we have targeted for years
as being one that just absolutely is at the top of our list of ones
that we would prefer to have just go away.
Senator SMITH. Any others? I did not mean to put you on the
spot, but any others?
Mr. FISCHER. There is a whole list of them in the Troubled Wa-
ters Report that we did over the recent years, and that American
Rivers has come out with as well. I would think that the situation
in the Missouri River also, where we are trying to go through with
a suggestion of having a better flow regime to more adequately ad-
dress natural conditions, rather than a more limited situation there
54
more tools and resources that are not necessarily financial, but just
options to the local governments and States.
Senator JEFFORDS. Mr. Brescia.
Mr. BRESCIA. Mr. Chairman, we think that many of the concerns
that have been articulated over project purpose, benefit-cost anal-
ysis, cost-sharing are really reflective of the lack of a national con-
sensus about water resource development priorities. I think the
single-most thing that Congress can do and this committee can
take leadership in is defining that, clarifying that, to really bring
into clarity the Corps job and what their roles are and what their
objectives are. I think that the rest will follow.
Senator JEFFORDS. Mr. MacDonald.
Mr. MACDONALD. I think making the individual purpose projects,
put them in the broader context of regional sediment planning and
regional management planning. So how does your navigation
project fit your use of dredge material and beneficial use and flood
control for the watershed? So I think getting beyond the single-pur-
pose projects to broader regional and watershed planning.
Senator JEFFORDS. Mr. Robinson.
Mr. ROBINSON. Mr. Chairman, after being in this thing as long
as I have, I think they need to be let to do the things that they
have on-line to do all along, not just bypass a certain area like my
Pinhook that I speak about, for some unknown reason.
Senator JEFFORDS. Thank you all. We, of course, always leave
the record open and allow ourselves time to bludgeon you by more
questions through the mail or otherwise. I want to warn you about
that, and for other members. But with that, I just want to thank
you, for I know all the work that went into preparing your testi-
mony, and I deeply appreciate it.
But I would say right now, we are adjourned.
[Whereupon, at 5:15 p.m., the committee was adjourned, to re-
convene at the call of the chair.]
[Additional statements submitted for the record follow.]
STATEMENT OF HON. TOM DASCHLE, U.S. SENATOR FROM THE
STATE OF SOUTH DAKOTA
Mr. Chairman, thank you for inviting me to testify today at this hearing. I am
here to express my strong belief that fundamental reform of the Corps of Engineers
is necessary not only to protect the nations environment, but also to protect the in-
tegrity of the process by which Congress authorizes Corps projects and to restore
the severely damaged credibility of the Corps itself.
In that regard, I want to commend the Committee for taking up the Water Re-
sources Development Act, and for recognizing that passage of any new authorizing
legislation for the Corps of Engineers should be accompanied by meaningful reform
legislation. I also want to encourage the Committee to include many of the provi-
sions of S. 1987 in the next Water Resources Development Act. This bill is a
thoughtful and justifiable response to the ongoing problems associated with the
Corps of Engineers, and I will cosponsor it today.
My one reservation about the bill is the establishment of a benefit-to-cost ratio
of 1.5. It has been my experience that some projects with lesser benefit-to-cost ratios
are defensible, while some with higher benefit-to-cost ratios may not be justified. I
think it is important that Congress establish a more sensitive metric for evaluating
projects than simply increasing the minimum benefit-to-cost ratio, and I would like
to explore this issue further with the Committee.
Mr. Chairman, I have advocated reform of the Corps of Engineers for years. In
fact, in March of 2000, I introduced S. 2309, the Corps of Engineers Civil Works
Independent Investigation and Review Act, calling for an independent review of the
Corps of Engineers. That bill established an independent commission to take a hard
look at the Corps.
57
At the time, I was extremely concerned by evidence that the Corps was neglecting
its responsibilities to comply with the nations environmental laws and was system-
atically engaged in producing fraudulent analyses of proposed projects to manufac-
ture economic justifications in cases where factual analyses could not have sup-
ported their authorization by Congress.
Two years ago the Washington Post published a number of very troubling articles
about the operations of the U.S. Army Corps of Engineers. Those stories exposed
the existence of independent agendas within the Corps. They suggested cost-benefit
analyses rigged to justify billion dollar projects, disregard for environmental laws,
and a pattern of catering to special interests.
The actions described in the Post articles raise serious questions about the ac-
countability of the Corps and present a compelling case for a thorough review of the
agencys operations and management. And it is not only the Post articles that cause
me to believe this.
The Corps current effort to update the Missouri River Master Control Manual
the policy document that governs the Corps management of the river from Montana
to Missouriillustrates not only that the Corps can be indifferent to the environ-
ment. It also demonstrates that the close relationship of the Corps to the barge in-
dustry often drives the Corps willingness to manipulate and falsify data and anal-
yses to protect those special interests and justify the work of the Corps in sup-
porting those activities.
On the Missouri River, for example, the Corps has taken pains to protect the $7
million barge industry at the expense of public recreational opportunities and fish
and wildlife. One important factor that motivates the Corps actions is its ongoing
program to maintain the barge channela Corps jobs program that costs taxpayers
over $7 million per yearmore than the value of the barge industry itself.
This example ought to be a concern to all Americans. It is a deep concern to South
Dakotans. The Missouri runs down the center of our state and is a major source
of income, recreation and pride for us. More than 40 years ago, the Corps built dams
up and down the Missouri River in order to harness hydroelectric power. In return,
it was expected to manage the river wisely, and in compliance with the nations
laws.
The Corps has not kept that trust. The Missouri river is dying a slow death. And
the Corps continues to bend over backward to ensure that the management changes
necessary to meet the requirements of the Endangered Species Act and recover the
health of the river are not made.
In recent years, studies have been done to determine how to restore the river to
health. An overwhelming amount of scientific and technical data all point to the
same conclusion. The flow of the river needs to more closely mimic nature. Flows
should be higher in the spring, and lower in the summerjust as they are in na-
ture.
Yet, if and when the Corps ever releases its plan for managing the riverand
after 12 years of study, that is still in doubtobservers expect that it will propose
to continue doing largely what it has been doing all these years. That is what most
expect, despite knowing exactly what the practices have produced now for the last
40-plus years. The agencys refusal to change will further jeopardize endangered
species. And, it will continue to erode the natural beauty and recreational value of
the river.
The Washington Post series suggested that the Corps handling of the Missouri
River Master Manual is not an isolated case. The Post articles contained allegations
by a Corps whistleblower who says that a study of proposed upper-Mississippi lock
expansions was rigged to provide an economic justification for that billion-dollar
project. In response to these allegations, the Corps own Office of Special Counsel
concluded that the agency probably broke laws and engaged in a gross waste of
funds.
In my own dealings with the Corps of Engineers, I, too, have experienced the in-
stitutional problems recorded so starkly in the Post series. In South Dakota, where
the Corps operates four hydroelectric dams, we have fought for more than 40 years
to force the agency to meet its responsibilities under the 1958 Fish and Wildlife Co-
ordination Act and mitigate the loss of wildlife habitat resulting from the construc-
tion of those dams.
For 40 years, the Corps has failed to meet those responsibilities. That is why I
have worked closely with the Governor of my state, Bill Janklow, and with many
other South Dakotans, to come up with a plan to transfer Corps lands back to the
state of South Dakota and two Indian tribes. Unfortunately, instead of attempting
to work with us, the Corps fought us for yearshoping to prevent us from rein-
forcing the precedent that the Corps is responsible for mitigating the environmental
damage caused by its projects.
58
Just last week, the Post described a new General Accounting Office report on a
project in Delaware, where once again fraudulent analysis was performed to justify
moving forward when it appears an objective analysis would have concluded the op-
posite. When considered in the context of the litany of problems that have come to
light in the Post, Congress has no choice but to enact serious reforms prior to pro-
viding the agency with any new authority.
In a democracy, institutions of government must be held accountable by rep-
resentatives of the people. That is the job of Congressto hold that agency respon-
sible and make sure it follows the nations laws and provides lawmakers with accu-
rate information upon which million- and billion-dollar decisions are made.
Contempt for environmental laws and self-serving economic analyses simply can-
not be tolerated if Congress is to make well-informed decisions regarding the au-
thorization of expensive projects, and if the American taxpayer is to be assured that
Federal moneys are being spent wisely.
The Corps of Engineers provides a valuable national service. It constructs and
manages needed projects throughout the country. The size and scope of the biannual
Water Resources Development Act is clear evidence of the importance of the Corps
civil works mission. Because the Corps work is so critical, it is essential that steps
be taken immediately to determine the extent of the problems within the agency
and to design meaningful and lasting reforms to correct them. Our Nation needs a
civil works program we can depend on. We need a Corps of Engineers that conducts
credible analysis.
We need a Corps that balances economic development and environmental protec-
tion as required by its mandatenot one that ignores environmental laws as it
chooses. History does not offer much room for confidence that the Army Corps of
Engineers can meet these standards under its current management system.
Consequently, I urge this committee to take a hard and systematic look at the
Corps and include reforms in the next Water Resources Development Act to address
these obvious problems. In particular, I hope the Committee will look at the Corps
compliance with environmental laws, the quality and objectivity of the agencys sci-
entific and economic analysis, the extent to which the Corps coordinates and cooper-
ates with other state and Federal agencies in designing and implementing projects,
and the appropriateness of the agencys size, budget and personnel.
It is my hope that all those who care about the integrity of the Army Corps of
Engineers and its mission will support an effort by this committee to identify and
implement whatever reforms are necessary to rebuild public support for its work.
I look forward to working with all members of the Committee to help craft respon-
sible reform legislation, and I encourage you to look to the provisions of S. 1987 as
a basis for needed reform in this years Water Resources Development Act.
Our water highways are national assets that serve a broad range of economic and
strategic interests. The United States has the most extensive, complex and decen-
tralized marine transportation system in the world; it is an appropriate asset for
the worlds largest trading country and sole superpower. A large measure of this
countrys unprecedented economic growth is due to the increased productivity of the
American economy and foreign trade. To remain competitive in the global market-
place, U.S. businesses must have an efficient and reliable transportation system.
This section of my testimony discusses the many benefits provided by the nations
system of deep-draft navigation channels. The structure of the broader marine
transportation system and its relation ship to deep-draft navigation channels is also
discussed. Finally, a number of challenges facing the Corps of Engineers and its
non-Federal partners on deep-draft navigation projectsthe nations public port au-
thoritiesare also highlighted.
Benefits of Deep-Draft Navigation Projects
Economic Benefits: Ports activities link every community in our Nation to the
world marketplace, enabling us to create export opportunities and to deliver im-
ported goods more inexpensively to consumers across the Nation. The deep-draft
commercial ports of the U.S. handle over 95 percent of the volume and 75 percent
of the value of cargo moving in and out of the Nation.
The marine transportation system has helped American exporters from every
state develop and maintain markets around the world for a variety of commodities,
ranging from paper, forest and agricultural products, to plastics, chemicals and
pharmaceuticals; from fruits and vegetables to poultry, beef and cotton; and, from
machinery and automobile parts to frozen fish.
The industry has also provided American consumers and businesses with inexpen-
sive access to a vast array of goods from around the world, including more than half
of the petroleum used, 75 percent of the apparel and 95 percent of the footwear
worn in this country, food products, beverages such as coffee and beer from around
the world, flowers, kitchenware, household appliances, furniture and bicycles, mar-
ble and tile, automobiles, auto parts and tires, machinery and tools, electronic goods,
computer equipment and copiers, manufacturing components and supplies, and
thousands of other goods.
All ports serve multi-state needs. The foreign trade activities of each state are
supported by a variety of ports both within and, more often, outside the state. On
average, each state relies on between 13 to 15 ports to handle 95 percent of its im-
ports and exports. The goods from 27 states leave the country through the ports in
Louisiana alone. Midwestern grain supplies the Pacific rim market through ports
in the Pacific Northwest. Imported crude oil refined in New Jersey and Pennsyl-
vania reaches consumers on the entire East Coast, from Maine to Florida. Steel that
travels to major Midwestern industrial centers is delivered cheaply and efficiently
through Great Lakes ports. Ports on the West Coast handle goods such as cars, com-
puters, and clothing, which are destined for consumers throughout the country.
World trade increased by 3.8 percent annually (on a tonnage basis) between 1993
and 1997 to a total of 5.3 billion metric tons. In that same period, U.S. foreign wa-
terborne trade grew by 4.6 percent per year to 1,071 million metric tons and ac-
counted for about 20 percent of global waterborne trade and almost 30 percent of
U.S. Gross Domestic Product.3 By 2020, U.S. foreign maritime trade is expected to
more than double over 1996 tonnage levels, with total tonnage projected to grow 3.5
percent annually. Figures 1 and 2 illustrate the range and scope of import and ex-
port cargos, respectively, moving through U.S. ports in 2000.
65
The nations system of ports and harbors provides the nations shippersimport-
ers and exporterswith a range of choices that allow them to minimize transpor-
tation costs, and, thus, deliver goods to the consumer more cheaply and compete
more effectively in international markets. As a result of the proliferation of just-in-
time manufacturing practices, time definite delivery, and vendor managed inventory
in our manufacturing and retail sectors, an interruption of only four to five business
days can have devastating consequences for our global supply chain, as evidenced
by the impact of September 11 on our land border crossings.
These global business trends are interrelated to the demand of cargo shippers for
increasing reliability, reduced damage, and decreasing cost. All of these demands
drive the transportation provider to improve service and find efficiencies at each
link in the transportation chain. This is especially true for the ocean carrier who
transports large volumes of cargo over relatively long distances. The drive to satisfy
cargo shippers in ocean transportation has led to the building of larger ships and
to the increasing containerization of cargo. Figure 3 illustrates the trend in the con-
tainerized cargo segment of U.S. foreign trade. The number of containers moving
though U.S. ports doubled between 1990 and 2000, from 15.3 to 30.4 million 20-foot
equivalent units (TEUs) and the volume is expected to double again over the current
decade. Relative increases were consistent on the Atlantic, Gulf and Pacific Coasts
with volumes in 2000 of 13, 1.7, and 15.7 million TEUs, respectively.
Recent testimony by the World Shipping Council discusses trends in freight rates
for containerized cargo moving in U.S. international trade.1 Table 1 summarizes the
changes in average rates for moving containerized cargo in the major U.S. foreign
trade routes from 1978 through 1998. Significantly, rates in real terms have de-
clined by between 52 and 72 percent, during this period of rapid expansion in the
use of containers for shipping cargo. It has been an unrecognized success that all
segments of the maritime transportation system have made the investments nec-
essary to sustain, and in turn foster, the explosive growth in global trade.
According to a semi-annual survey conducted by the U.S. Department of Agri-
culture, American shippers of containerized agricultural goods have reported that
they are able to obtain cost-efficient ocean transportation. Specifically, the USDAs
December 2001 report on Agricultural Ocean Transportation Trends states that:
1 Testimony of Christopher Koch, President & CEO of the World Shipping Council Before the
House Committee on the Judiciary Hearing on International Liner Shipping Regulatory Policy,
June 5, 2002.
66
The rates for U.S. outbound dry containers, particularly westbound transpacific
rates, are approaching historically low levels. Virtually all U.S. agricultural export-
ers are paying less for transportation than they were in early 2001 when rates were
already perceived to be extraordinarily low . . . It is remarkable that commodities
are reportedly moving in certain transpacific, westbound trades at $225 per 40-foot
equivalent unit . . . Rates are so uniformly low, they are no longer the primary de-
termining factor for carrier selection. There is a presumption that rates will hit
rock bottom, so, while agricultural shippers continue to keep an eye on the overall
rates (the base rate plus the surcharges), carriers are now primarily selected accord-
ing to service capabilities.2
Trans-Pacific
Eastbound .......................................................................................................... 32.1 72.1
Westbound .......................................................................................................... 20.8 67.5
Trans-Atlantic
Eastbound .......................................................................................................... 4.6 60.9
Westbound .......................................................................................................... 18.2 51.5
Besides providing cost savings to the countrys businesses and consumers through
more efficient transportation, the U.S. marine transportation system, including the
nations deep-draft navigation channels, creates substantial economic and trade ben-
efits for the Nation, as well as for the local port community and regional economies.
The following statistics highlight how critical ports are in facilitating national eco-
nomic activity:3
U.S. Customs duty revenues totaling approximately $15.6 billion were paid into
the general treasury in fiscal year 1996 on cargo moved through ports.
Our nations commercial deep draft ports annually handle in excess of $600 bil-
lion in inter national trade.
Foreign trade is an increasingly important part of the U.S. economy, currently
accounting for almost 30 percent of our Gross Domestic Product. U.S. exports and
imports are projected to increase in value from $454 billion in 1990 to $1.6 trillion
in 2010. The volume of cargo is projected to increase from 875 million to 1.5 billion
metric tons in 2010.
The overall national economic impact of port activities in 1996 generated:
3 million jobs;
$743 billion to the Gross Domestic Product; and
$200 billion in taxes at all levels of government.
National Defense Benefits: We should also not lose sight of the fact that the ports
continue to play a very critical role in our nations defense. That role has never been
more apparent than during the loadouts of military cargo and personnel during Op-
eration Desert Shield/Desert Storm. The huge buildup of U.S. forces in and around
the Persian Gulf would have been impossible without the modern facilities and
strong support provided by Americas ports. According to the U.S. Military Traffic
Management Command (MTMC), between August 1990 and March 1991, MTMC
loaded 312 vessels and more than 4.2 million measurement tons of cargo in 18 U.S.
ports for delivery to the Persian Gulf in support of Desert Shield/Desert Storm.
More than 50 ports have agreements with the Federal Government to provide ready
access for national emergency purposes.
Environmental Benefits: Several navigation projects that have substantial envi-
ronmental features, including the creation of thousands of acres of wildlife habitat
using dredged material, would not proceed under the proposed funding levels. For
example, the Port of Oakland is currently building a project to expand its container
handling capability that will redevelop a former military facility, create 120 acres
of shallow-water habitat, restore 3200 acres of wetlands, provide 30 acres of new
public parkland, and reduce vehicle emissions by 40 tons per year. In addition, the
larger, more efficient ships that will be able to call at the port will result in reduced
volumes of ballast water discharged and air pollutants emitted. Similar multi-objec-
4 An Assessment of the U.S. Marine Transportation SystemA Report to Congress. U.S. De-
partment of Transportation, Washington, DC 104 pp., September 1999 (www.dot.gov/mts/report/
).
5 United States Port Development Expenditure Report, December 2001, U.S. Department of
Transportation Maritime Administration, Office of Ports and Domestic Shipping, Washington,
DC.
68
facilities, and handling equipment. Infrastructure expenditures cover improvements,
such as roadways, rail, and utilities that are located on or off terminal property.
Dredging consists of local port expenditures associated with the dredging deepening
and/or maintenance of Federal and non-Federal channels and berths as well as the
local costs for land, easements, rights-of-way, and disposal areas. The other cat-
egory includes those structures and fixtures not directly related to the movement
of cargo, such as maintenance and administrative facilities.
Table 2.Comparison of Annual Capital Expenditures by Type of Facility for 19922000 and
Projected Capital Expenditures for 20012005
Special-
General Liquid On Ter- Off Ter- Total Ex-
ized Dry Bulk Passenger Other Dredging
Cargo Bulk minal minal penditure
Year Cargo [In Per- [In Per- [In Per- [In Per-
[In Per- [In Per- [In Per- [In Per- [millions
[In Per- cent] cent] cent] cent]
cent] cent] cent] cent] of dollars]
cent]
2001
2005 9.8 44.4 1.5 0.6 4.3 8.0 8.5 6.3 16.6 $9,434
2000 ... 22.8 31.2 3.5 0.8 5.7 8.2 8.0 8.7 11.1 1,058
1999 ... 11.5 39.2 5.2 1.4 6.4 9.0 8.8 8.6 9.9 1,116
1998 ... 10.9 35.8 8.3 0.2 1.9 8.5 7.1 11.2 10.8 1,414
1997 ... 14.8 35.5 8.3 0.1 3.8 8.5 14.0 6.7 8.3 1,542
1996 ... 14.7 41.0 5.9 0.5 2.7 4.8 10.7 8.8 10.9 1,301
1995 ... 22.2 28.8 3.0 0.9 4.7 8.2 18.0 3.1 11.1 1,203
1994 ... 22.8 34.8 5.6 0.3 4.7 7.3 15.1 6.0 3.4 687
1993 ... 24.5 27.6 4.5 1.7 5.6 11.9 11.6 3.6 9.0 654
1992 ... 23.9 31.8 4.8 0.2 7.5 9.5 9.0 3.8 9.5 680
Table 3 presents information on the methods used by the U.S. public port authori-
ties to finance their capital expenditure programs. The table identifies six funding
categories to classify the financing sources: port revenues, general obligation bonds
(GO bonds), revenue bonds, loans, grants, and other. The other funding category
includes all financing sources that were not described above, such as state transpor-
tation trust funds, state and local appropriations, taxes (property, sales), and lease
revenue. As the table illustrates, public ports are relying on either direct revenue
or revenue-backed bonds for a greater percentage of the financing needs, and this
trend is expected to continue with revenue-based financing expected to reach almost
78 percent of capital financing needs in 20012005. (Note: Total financing and total
expenditure levels from Table 2 may not agree because of incomplete survey re-
sponses.).
Table 3.Comparison of Annual Capital Financing by Method for 19962000 and Projected
Capital Financing for 20012005
1996 [In Per- 1997 [In Per- 1998 [In Per- 1999 [In Per- 2000 [In Per- 20012005
Method cent] cent] cent] cent] cent] [In Percent]
Vessels: The worlds ocean cargo vessels enter the market offering a wide variety
of shipping services and trade routes from a variety of ownership patterns rep-
resenting large global integrated logistics companies to national entities to niche
carriers. Because the majority of ocean carriers are non-U.S. owned, some critics of
Federal investment in navigation channels have charged that the benefits of such
investments only accrue to foreigners and, therefore, such investments are some-
how defective. There are several reasons why this is otherwise.
First, the ocean carrier industry is highly competitive. There are no barriers to
entry in international shipping as there are in other industries, such as inter-
national commercial aviation. In the liner industry, which is often the focus of this
criticism, the shipping public has a wide array of carriers and variety of shipping
services from which to choose. For example, as illustrated in Table 4, only one car-
69
rier has a market share above 10 percent, and the top ten carriers combined account
for only 57.5 percent of the total containerized cargo carried (exports and imports
combined) in U.S. trades.
Second, as discussed above, freight rates for the shipment of containers in the
liner industry have declined substantially over the last 15 years due to, among other
reasons, the increased efficiencies resulting from larger vessels and deeper naviga-
tion channels.
Table 4.Market Share In U.S. Liner Trade in the First Quarter 2002 (Source: JoC/PIERS)
Jan.-March Combined
2002 Market
Lines TEUs Carried Market Share
Share [In Percent]
[In Percent]
Third, vessel owners have made huge investments in new equipment, information
technology, and larger vessels to achieve economies of scale, developed alliances
with other vessel owners to take advantage of these economies of scale and scope
that made possible significant cost savings. To keep pace with the expected doubling
of trade by 2020, the liner industry expects that it will need to invest an estimated
$100 billion in new vessels and containers alone. Those efficiency gains and cost re-
ductions resulting from these investments are passed on to shippers in lower rates
and improved service.
Some critics have pointed out that the liner industry enjoys anti-trust immunity
as proof that these foreign companies enjoy a benefit that is detrimental to U.S.
businesses, consumers and, in the case of Federal investments in navigation chan-
nels, to the American taxpayer. Again, a closer examination of this issue dem-
onstrates that this is not the case.
The anti-trust immunity provided to the liner industry is limited and highly regu-
lated. The protection to the industry was established by the U.S. Congress, not some
foreign, unaccountable entity. In fact, Congress most recently reviewed and reau-
thorized this protection in 1998 with passage of the Ocean Shipping Reform Act of
1998. Carriers may operate under agreements filed with and overseen by the Fed-
eral Maritime Commission that promote and enable operational cooperation and ef-
ficiencies. Under this system, carriers, among other things:
May not operate under an agreement that unreasonably increases rates or de-
creases service;
May not engage in unjust or unfair or predatory practices;
May not retaliate against any shipper;
May not drive competitors out of a trade; and,
May not impose any unreasonable prejudice or disadvantage with respect to any
port.
Given the highly competitive marketplace for transporting U.S. foreign trade evi-
denced by the large number of companies engaged in this business and the dramatic
reduction in rates that have occurred over the last 15 years, it is clear that there
is no monolithic foreigner dictating the terms of the trade to U.S. businesses and
consumers. Instead, these companies are continually making investments in their
operations to reduce costs and provide better service to users of the nations marine
transportation system U.S. businesses and consumers.
Navigation Channels: Since its beginning, the U.S. Congress has authorized and
funded activities to ensure free and open access of the nations waterways to naviga-
tion. The General Survey Act of 1824 established the U.S. Army Corps of Engineers
(USACE) as the agency responsible for the nations navigation system.1 Since that
time, the Federal Government has consistently exercised its power to develop and
maintain a navigation system for the benefit of the whole nation. Today, there are
70
approximately 1,000 Federal navigation channel projects spanning over 25,000 miles
of inland, intracoastal, and coastal waterways.6
Prior to the Water Resources Development Act of 1986, the Federal Government
paid 100 percent of general navigation features (GNFs) of harbor projects that con-
sisted primarily of harbor dredging.7 Lands, easements, rights of way and reloca-
tions (LERRs), and dredging for berthing areas were a local or private responsi-
bility, as were all landside improvements including terminals and equipment. All
maintenance dredging was federally funded out of general revenue. With the pas-
sage of WRDA 1986, cost-sharing for general navigation features changed to include
a local or non-Federal share as shown in Table 5. Maintenance dredging remained
100 percent federally funded; however, today Federal costs may be recovered 100
percent from deposits of the Harbor Maintenance Tax to the Harbor Maintenance
Trust Fund.
Figure 4 illustrates the volume of material dredged and the cost of dredging for
new work and maintenance dredging from Federal navigation channels between
1965 and 1999.8 Annual construction costs have averaged about $125 million for the
period between 19771996 and average annual maintenance costs have averaged
about $450 million. Average Federal investment in new channels increased since
1996 to a level $271.4 million in fiscal year 2002. Maintenance dredging volumes
range annually between 250 and 300 million cubic yards.
Individual navigation channel improvements must be demonstrated to be in the
Federal interest before becoming eligible for Federal funding. Congress established
that the Federal interests in water resources projects are as follows:
It is the intent of Congress that the objectives of enhancing regional economic
development, the quality of the total environment, including its protection and
improvement, the well-being of the people of the United States, and the na-
tional economic development are the objectives to be included in federally fi-
nanced water resource projects (including shore protection projects such as
projects for beach nourishment, including the replacement of sand), and in the
evaluation of benefits and cost attributable thereto, giving due consideration to
the most feasible alternative means of accomplishing these objectives.(42USCx
19622)
Congress also authorized the establishment of a Water Resources Council com-
posed of the Secretaries of the Interior, Agriculture, Army, Commerce, Housing and
Urban Development, and Transportation and the Administrator of EPA. In 1983,
the Council adopted The Federal Principles and Guidelines for Water and Related
Land Resources Implementation Studies, which continues today as the benchmark
against which Federal water resources projects are measured. The P&G, as the pol-
icy document is informally called, applies to all water and land-related resources
projects undertaken by the Federal Government, including projects by the Corps of
Engineers, the Bureau of Reclamation, and the Department of Agriculture. Despite
Congress intent that Federal water resources should also take into account regional
economic development benefits, the P&G sets the maximization of national economic
development (NED) benefits as the definitive threshold for Federal involvement in
such projects.9 This policy continues even after non-Federal interests became re-
6 Civil
Works Program1998. U.S. Army Corps of Engineers, Washington, DC, 54 pp., 1998.
7 Cost sharing requirements are contained in Section 101 of the Water Resources Development
Act of 1986, Public Law 99662, November 17, 1986, 33 U.S.C. 2211.
8 Actual Dredging Cost Data for 19631999, Long-Term Continuing Cost Analysis data. U.S.
Army Corps of Engineers Dredging Program. Navigation Data Center, U.S. Army Corps of Engi-
neers, Fort Belvoir, VA (www.wrsc.usace.army.mil/ndc/ddhisbth.htm).
9 Principles and Guidelines for Water and Related Land Resources Implementation Studies.
U.S. Army Corps of Engineers, Washington, DC, 1983. (www.wrsc.usace.army.mil/iwr/pdf/
p&g.pdf)
71
sponsible for cost-sharing projects. Thus, non-Federal interests are required to share
up to 60 percent of the cost of Federal navigation projects, but any regional benefits
derived from these projects may not be included in justifying the project.
The Corps of Engineers project planning process is divided into two stages, a re-
connaissance study and feasibility study, which together require an average of 5.6
years to complete. Corps reconnaissance studies, which are conducted by the Corps
district offices, are today required to be completed with 12 months. There is then
often a lag between the end of reconnaissance and the start of feasibility. Between
1985 and 1996, the average length of this gap was roughly 1 year. Feasibility stud-
ies during the same period averaged 3.6 years.10
The basic economic benefits from navigation plans are the reduction in the value
of resources required to transport commodities and the increase in the value of out-
put for goods and services. Specific transportation savings may result from the use
of larger vessels, more efficient use of large vessels, more efficient use of existing
vessels, reductions in transit time, lower cargo handling and tug assistance costs,
reduced interest and storage costs such as from an extended navigation season, and
the use of water transportation rather than an alternative land mode.
Corps of Engineers navigation improvement studies examine the transportation
costs of an identified set of commodity flows both with and without the proposed
project over the planning period, usually 50 years. Elements of analysis of current
tonnage include: size and type of vessel, annual volume of movements, frequency of
movements, volume of individual shipments, adequacy of existing harbor and trans-
portation facilities, rail and truck connections, and service considerations. Generally
this prospective traffic is the aggregate of a large number of movements (origin-des-
tination pairs) of many commodities; the benefit from the navigation project is the
savings on the aggregate of these prospective movements.
Next, the analysis evaluates the vessel fleet composition and cost. Key compo-
nents in the study are the size and characteristics of the current and future fleet
that would use the harbor both with and without the proposed improvement. Vessel
characteristics are often dependent on trade route, type of commodity, volume of
traffic, waterway restrictions, foreign port depths, and lengths of haul. Vessel costs
include the full origin-to-destination cost, including necessary handling, transfer,
storage, and other accessory charges. The without-project condition is based on costs
and conditions prevailing at the time of the study. Transportation costs with a plan
reflect any efficiencies that can be reasonably expected, such as use of larger ves-
sels, increased loads, reduction in transit time and delays (tides), etc. In evaluating
these cargo flow assessments, the Corps conducts a systematic determination of al-
ternative routing possibilities, regional port analyses, and intermodal networks.
10 New Directions in Water Resources Planning for the U.S. Army Corps of Engineers. Na-
tional Academy of Sciences, Washington, DC, 120 pp., 1999.
72
Benefits may not be claimed for cargo that may be diverted from another port be-
cause of a Federal navigation project.
Challenges
There are a variety of challenges that threaten the ability of the MTS to meet
the growing demands of the nations businesses and consumers for transportation
services. These challenges include:
Growing Levels of Demand.As discussed above, the volume of trade is ex-
pected to double over the next 20 years and the movement of cargo in containers
is expected to double in the next 10 years. The business environment in which
American companies must operate has become more competitive. They must be lean
and capable of effectively serving larger, more demanding markets. Ports and other
MTS service providers must meet increasingly stringent requirements to success-
fully meet the needs of American business and consumers. Everything must be ac-
complished faster and less expensively, while maintaining dependable, secure, and
safe movement of goods. Consequently, the need to provide investment in improved
MTS facilities and services is great.
Increasing National Security Needs.The attacks of September 11 have dra-
matically heightened everyones awareness of the threat to the U.S. from rogue
states and terrorists. Ports and other MTS service providers are, and will continue,
spending substantial resources to improve the security at their facilities. These re-
sources, however, are being diverted from other investments that would have been
made in improving the efficiency of the system.
Minimizing conflicts among land uses along the waterfront and intermodal con-
nections.Many of our nations port cities are trying to revitalize their communities
through waterfront re development that has focused on residential, commercial, and
tourist-related uses, leaving less land available for port development. Intermodal
connections at ports, such as roads and railroads, also experience land constraints
because of zoning and environmental regulations that restrict expansion, particu-
larly in densely populated areas. Proposals for port expansion, largely for projects
handling cargo that will move far outside the local port area, are facing increasing
public opposition due to concerns about local environmental impact. Many port com-
munities are reluctant to bear the environmental and social costs for projects that
largely benefit people outside of their region.
Ensuring Adequate Navigation Channels.Larger vessels are increasingly car-
rying the cargos of U.S. international trade because they provide the cost efficiency
and level of service that U.S. businesses and consumers are demanding. These larg-
er vessels require deeper waterways. The nations public port authorities are work-
ing closely with the Corps of Engineers and the Congress to ensure that appropriate
investment in the nations system of navigation channels is made. In addition to the
need for adequate Federal funding of studies and construction of navigation im-
provement projects, we have also identified several areas in the partnership be-
tween the Federal Government and non-Federal sponsors of navigation projects that
should be improved so we can improve the timeliness and cost effective delivery of
these projects. A summary of these recommended improvements are discussed in the
next section.
NEED TO ENACT WRDA 2002
1 Port Development in the United States, Panel on Future Port Requirements of the United
States, Marine Transportation Research Board, National Research Council, National Academy
of Science, Washington, DC, 1976.
83
puter modeling techniques. The data needed for such a determination are often dif-
ficult to obtain; therefore, interviews with knowledgeable experts will often have to
be relied upon. (p. 65)
In practice, because of the complexity of conducting these studies, the Corps of
Engineers often limits the types of potential benefits it considers for a navigation
project to only those which are unlikely to induce cargo diversions from other ports
in order to avoid the need for a comprehensive multiport analysis. Provided these
benefits are sufficient to justify a project, most local sponsors agree to this approach
to avoid the expense and delays resulting from such a study, even though it may
seriously understate the actual benefits of the project.
With regard to the specific proposal for regional port analysis contained in S. 1987
(Section 5(b)), AAPA has a number of concerns. This section establishes a require-
ment for the detailed and thorough consideration of three highly complex assess-
ments of potential regional effects of individual navigation improvement projects.
Because of their complexity, these assessments will almost always be expensive to
undertake and contain substantial uncertainty. Ultimately, these assessments are
unlikely to provide additional value to the decisionmaking process, will likely in-
crease the cost and time to formulate projects, and do little to reduce the level of
controversy around projects because of the additional complicated and uncertain
studies that will be produced.
We also have the following concerns with each of the three assessments called for
in S. 1987. First, the requirement for an assessment of the economic impacts of a
project on other ports within a region appears to be unnecessary in light of the cur-
rent requirement for multiport analysis under the P&G. Second, we are unclear
about what would be required for a detailed and thorough consideration of cumu-
lative environmental impacts of a project within the region. Given the expansive
definition of a region within this section, would a port in Florida, for example, be
required to consider the environmental effects of its project in addition to the effects
of all activities on the entire U.S. Atlantic seaboard.
Finally, we are concerned with the requirement for an assessment of the cumu-
lative impacts of the project on overcapacity in the region. The NAS report reviewed
the issue of over capacity, and found:
The panel has concluded that it cannot quantitatively determine the existence of
redundancy. Redundancy implies excess capacity, and it is impossible to provide an
adequate measure for the capacity of a port. There are many reasons for this meas-
urement problem: One is that the nature of cargo ships and productivity of facilities
will vary greatly through time. Cargoes are not uniform. Peakingthe concentration
of demand during limited periods of timeoccurs in port operations as in all other
aspects of transportation. It is economical [sic] and, in some instances, physically
impossible to provide for the maximum peaks. At the same time, it is undesirable
that undue waiting time, leading to costly delays to vessels and cargo, occur because
of failure to provide for periodic peaks. Such delays, in common, would result in
traffic being diverted to competing ports or, in some instances, not moving at all.
Excess capacity, in one sense, does not exist even though a port or terminal may
have 100 per cent utilization of its capacity for only short periods of time, if ever.
Consideration of peak activities, other than for very infrequent occasions, is an im-
portant element of port planning. Capacity must be supplied in order to provide ade-
quate service to the shipping public as well as to anticipate possible national emer-
gencies, when even the largest ports may be crowded.
Another important reason, in the judgment of the panel, for providing capacity in
excess of normal demand is to create competition among various ports and port
services to the advantage of the shipping public. That is, the public can be reason-
ably assured not only of continued availability of port services in the event of acci-
dents or other closures or reductions but also of competitive rates and services.
Thus, the shipper receives a series of options that would not be available unless
interport competition continued (p. 128).
We believe that assessments of overcapacity are unlikely to provide additional
value to the decisionmaking process for navigation projects, will likely increase the
cost and time to formulate projects, and do little to reduce the level of controversy
around projects because of the additional complicated and uncertain studies that
will be produced.
Question 2. Do you believe that such analyses could significantly improve the
planning of navigation in the United States port system and result in more eco-
nomic and financial efficiencies in port development for the country?
Response. For the reasons stated in response to Question 1., above, we are con-
cerned that the complexity and uncertainty inherent in such analyses are unlikely
to provide additional value to the decisionmaking process for navigation projects,
84
will likely increase the cost and time to formulate projects, and do little to reduce
the level of controversy around projects because of the additional complicated and
uncertain studies that will be produced.
AAPA again agrees with the observation made in the NAS report that the future
port requirements of the United States are subject to an almost infinite variety of
conditions and forces, many of which are nonquantifiable and unpredictable (p.
125). We believe the current decentralized, market-driven approach to port develop-
ment has, and can continue, to serve the country well.
New York Harbor Channels .............................................. Authorized in WRDA 2000. No Contracts Have Been Awarded to
date.
Norfolk, VA ........................................................................ WRDA 86 authorized a 50-foot project; to date, the out-bound
lane has been constructed.
Mobile, AL ......................................................................... WRDA 86 authorized a 55-foot project; to date, a portion of the
project has been deepened to 45-feet.
Mississippi River, LA ........................................................ WRDA 86 authorized a 55-foot project; to date, the project has
been deepened to 45-feet.
Savannah, GA ................................................................... Authorized in WRDA 1999. No Contracts Have Been Awarded to
date.
Los Angeles, CA ............................................................... Authorized in WRDA 2000. No Contracts Awarded to Date.
Oakland, CA ..................................................................... Authorized in WRDA 1999. First Contract Awarded: ???
The National Wildlife Federation strongly supports both S. 1987 and S. 646 be-
cause these bills contain critically needed reforms to improve and modernize the
way the Corps responds to the nations water resources development needs and to
ensure every project the Corps undertakes represents a sound, environmentally sus-
tainable investment. The bills improve the Corps accountability, modernize its prin-
ciples and practices, improve mitigation of wetlands, pull the plug on projects that
no longer make sense, keep Federal costs down, and stop the race to the bottom
among ports and harbors.
Improve Accountability. S. 1987 and S. 646 would make the Corps more account-
able to help restore the publics confidence in this agency by:
requiring independent peer review for costly projects and controversial projects;
enhancing the publics ability to participate in the Corps planning process; and
increasing the publics access to information.
Modernize the Corps. S. 1987 and S. 646 would modernize the Corps basic ap-
proach to developing and planning water resources projects by:
directing that the Principles & Guidelines be revised and updated to define en-
vironmental protection and restoration as a co-equal goal with economic develop-
ment, and to incorporate other changes that ensure this goal is carried out; and
modernizing the basic criteria used by the Corps to justify moving forward with
a project.
Wetlands Mitigation Improvement.
S. 646 would improve the way the Corps mitigates for wetlands impacted by
Corps projects; and
both S. 646 and S. 1987 would exclude from economic justification analyses ben-
efits derived from draining wetlands.
Pull the Plug on Outdated Projects. S. 1987 would help prioritize the Corps efforts
by:
expediting the automatic deauthorization process to reduce the Corps bur-
geoning backlog; and
updating the Corps benefit-to-cost ratios to ensure taxpayers get a better re-
turn on their investment.
Keep Federal Costs Down. S. 1987 would reduce the Federal Governments burden
for sand pumping projects.
Stop the Race to the Bottom. S. 1987 would improve the way the Corps plans to
deepen ports and harbors by requiring regional port planning.
Given the record of problems that has amassed over the past several years, the
Corps should not be allowed to continue with business as usual. The problems are
87
so grave, a WRDA should not move forward without these reforms. I will now spend
a few minutes discussing some of the problems that have plagued the Corps and
that the bills seek to address.
CORPS CRISIS IN PUBLIC CONFIDENCE
1 See Working Group 1, Intergovernmental Panel on Climate Change, Climate Change 1995:
The Science of Climate Change, at 6 (estimating that IPCCs best estimate is that global sea
level will rise 49 cm from 19902100). See also James G. Titus & Vijay K. Narayanan, U.S.
Environmental Protection Agency, The Probability of Sea Level Rise iii, 14546
(1995)(explaining that along much of the U.S. coast sea level is likely to rise about 10 cm more
than the global average).
93
sight and a much more thoughtful, scientifically based response than we have seen
to date to help guide a rational approach to erosion.
Reduce the Federal Governments Burden for Sand Pumping Projects
While there are instances where sand pumping may be either economically justi-
fied or can serve as temporary measures to allow communities that face erosion
problems to make permanent adjustments, such as relocating at-risk buildings, a
fundamental concern is that many believe this should not be largely a Federal re-
sponsibility, given the range of demands on the Federal budget. NWF strongly urges
the Committee to seriously consider supporting a substantial reduction in the Fed-
eral cost-share for beach nourishment activities, such as proposed by S. 1987 and
the Presidents fiscal year 2002 budget recommendation. In addition, we urge the
Committee to resist attempts to allow more of these types of projects that are pri-
marily for recreation rather than storm damage prevention. Until a much clearer
picture can be gained of the ecological impacts that may be represented by expand-
ing Federal beach nourishment activities, the Committee should resist new author-
izations.
A Race To The Bottom Among Ports and Harbors Is Bad for Taxpayers and the En-
vironment
Our nations ports and harbors are critically valuable resources for our economy
and our environment and they must be managed in a manner that continues to sup-
port both. NWF has previously expressed our severe concern to the Committee that
a number of ports and harbors are engaged in a race to deepen their channels in
order to accommodate many of the largest and deepest draft ships operating on the
trans-oceanic routes. At the same time, port authorities have sought to increase
Federal subsidies for deep draft harbor dredging by modifying current cost-share
formulas to treat ports from 45 to 55 feet in depth the same as 45-foot depth or
less general cargo ports. This would amount to a 25 percent increase in Federal
costs for deep draft dredging. The Corps is not currently dredging any commercial
U.S. port deeper than 55 feet.
We also caution the Committee about relying on generalized future growth in
trade predictions as a rationale for an across the board effort to deepen our ports.
For instance, just 2 years ago at the time predictions were made that trade would
double over the next 20 years, eastbound trans-Pacific trade grew at very high rates
of 12 percent to 14 percent per year. Since then, trade traffic has seen far less sig-
nificant growth. According to recent reports in the Journal of Commerce, cargo vol-
umes in the eastbound Pacific increased by only 2 percent last year, and despite the
nations recovering economy, volumes are expected to grow by single digit rates
through next year. See, e.g., Bill Mongelluzzo, The Dire TransPacific, Journal of
Commerce, March 18, 2002. The uncertainties associated with port and harbor
needs argue even more strongly for the development of regional port planning to in-
tegrate the Corps program with national transportation policy.
The Corps Should Strive to Focus Deep Draft Port Dredging Activities to the Most
Efficient, Environmentally Sound Ports
We must invest in our ports wisely. Growth tends to be concentrated in a few
major U.S. ports. More than half is concentrated in 20 ports and more than a quar-
ter is handled by just five ports. In 1997, 25 ports handled 98 percent of the foreign
container cargo, and the leading 10 ports accounted for 80 percent with the Los-An-
geles-Long Beach port complex responsible for one-third of all container traffic. The
50 leading U.S. ports handle nearly 90 percent of all waterborne commerce. (NAS,
Applying Information Systems to Ports and Waterways Management, 1999).
NWF supports provisions from S. 1987 that would require the Corps to conduct
comprehensive coordinated planning to look regionally at shipping needs and the
economic and environmental cumulative impacts of deepening ports and harbors. In
WRDA 1986, Congress wisely established a cost sharing formula requiring that the
very deepest portsthose with channels dredged deeper than 45 feetpay a higher
share of the costs for dredging than those below 45 feet. We believe any decision
to increase the Federal subsidy, such as the proposal sought by the port authorities
to increase the subsidy by 25 percent, would unnecessarily fuel major expansions
of capacity at too many locations that would have dire long-term environmental con-
sequences. There is no reason to believe that the current formula will not allow the
necessary capacity to meet the nations transportation needs where the business ex-
ists. We strongly oppose this cost-sharing change because it will undoubtedly fuel
the race to the bottom, thereby unnecessarily wasting taxpayer resources and
threatening further harm to the nations bays, rivers and estuaries. Instead, we
urge the Committee to require regional port planning as an element of helping to
94
guide the Federal interest in ensuring U.S. ports can meet national transportation
needs, consistent with protecting the environment.
21ST CENTURY VISION FOR THE CORPS: THE PREMIER ECOSYSTEM RESTORATION AND
PROTECTION AGENCY
In sum, the Corps of Engineers has a vital role to play in managing the nations
water resources. Continuing business as usual, however, is not acceptable. Several
new reports by the National Academy of Sciences and others, the results of exten-
sive audits and investigations, as well as much thoughtful legislation, have provided
critically important recommendations for long-needed reforms. We applaud the
Corps of Engineers for taking a first step in signaling its commitment to a sustain-
able environment by formalizing a set of Environmental Operating Principles ap-
plicable to its decisionmaking and programs. These principles were recently articu-
lated by the Chief of Engineers, Lt. General Flowers, at the dedication of the Davis
Pond Fresh Water Diversion Project in Louisiana. We urge the Environment and
Public Works Committee to directly address the Corps crisis in confidence by in-
cluding important legislative reforms in the next WRDA. These reforms would pro-
vide critical direction for all Corps programs, including direction for what may be
among the Corps most important functions in the twenty-first centuryecosystem
restoration and protection.
Chairman Jeffords and Ranking Member Smith, once again, thank you for the op-
portunity to present our views. We look forward to working with you and the other
members of the Committee to help bring the Corps into the 21st Century by incor-
porating critically needed reforms in the next WRDA legislation. I am happy to re-
spond to any questions the Committee Members may have.
APPENDIX
Agriculture .............. 38 40 57 42 33 63 45 56 64 35
Commercial Devel-
opment ............... 35 30 42 33 56 44 16 67 29 13
Water Development 30 47 66 22 28 63 91 21 99 48
Outdoor Recreation 27 16 19 15 31 25 9 41 4 26
Livestock Grazing .... 22 17 10 20 8 19 16 15 1 9
Pollutants ................ 20 27 66 10 21 25 55 26 97 48
Infrastructure Devel-
opment ............... 17 16 12 8 28 38 17 23 6 9
Percentage of Federal endangered, threatened, and proposed species harmed by types of habitat destruction and degradation.
96
June 12, 2002.
Hon. JAMES CONNAUGHTON,
Chair, Council on Environmental Quality
Washington, DC.
Hon. MITCHELL E. DANIELS, Jr.,
Director, Office of Management and Budget,
Washington, DC.
Subject: U.S. Army Corps of Engineers
DEAR MESSRS. CONNAUGHTON AND DANIELS: We are writing to urge the Adminis-
tration to work with Members of Congress and with our conservation, taxpayer, and
professional organizations to support legislation that will reform the way the Corps
of Engineers (Corps) plans, evaluates, and implements water resources projects. The
Corps failure to address the contemporary needs of communities in an environ-
mentally sound and cost-efficient manner is taking a tremendous toll on the nations
natural and financial resources. Your leadership in this effort is critical.
The Corps implementation of its much touted nationwide project pause starkly
underscores the need for the Bush Administration and Congress to act now to re-
form the Corps. We had hoped that the project pause was a genuine sign of the
Corps interest in ensuring that its water resource projects were economically and
environmentally sound. Unfortunately, the review appears to have been little more
than a charade, and the Corps has made it abundantly clear that it is either unwill-
ing or unable to reform itself.
First, less than 3 weeks after announcing the pause, the Corps announced that
it had reviewed 172 projects and cleared 118 to move forward. Only eight projects
were flagged for additional review as a result of this process (with the remainder
already undergoing reevaluation due to previously identified problems). That
timeline made it abundantly clear that General Griffins direction to conduct a new
economic analysis for projects approved prior to fiscal year 99 was not followed.
Second, just a few days later, the Corps released a corrected list that deviated
in significant ways from the first list. The second list identifies only 164 projects
as having been reviewed, clearing 80 to proceed (with the remainder already under-
going reevaluation due to previously identified problems). Again, only eight projects
were said to require additional review as a result of the project pause directive.
With no explanation, the Corps completely removed from the second list some of
the worst projects that were identified on the original list with the nomenclature
review complete. These projects include the Grand Prairie Irrigation Demonstra-
tion Project in Arkansas, the Yazoo Pumps Project in Mississippi, St. Johns Bayou
Project in Missouri and the Inner Harbor Navigation Canal (Industrial Canal)
Project in Louisiana. In addition to being costly, these projects are highly controver-
sial and would destroy some of Americas most valuable wetlands and aquatic habi-
tat. Because the Corps has left the public completely in the dark on the process used
in its review, the only conclusion we can reach is that although the Corps originally
announced to Congress and the public that these projects had in fact been reviewed,
the reviews never occurred. If the Corps review and reevaluation process is to have
any credibility, these projects must be fully and openly re-evaluated.
Third, in addition to the Corps apparent inability to be able to accurately identify
projects that were reviewed, the list contains glaring omissions of projects that most
certainly should have been reevaluated. For example, the list does not include the
Dallas Floodway Extension project in Texas an authorized project for which con-
struction has not begun. Not only did the Office of Management and Budget inform
the Corps that they had failed to comply with their own planning guidance for this
project, but a U.S. District Court also ordered the Corps to reevaluate the projects
cumulative environmental impacts.
Finally, the project reevaluation was conducted behind closed doors with no in-
volvement from the public, other Federal and state agencies, or apparently the Ad-
ministration. The Corps has not identified or described the information reviewed,
the results of each review, or the documentation supporting its conclusions. The fact
that the Corps originally cleared more than 100 projects in less than 3 weeks includ-
ing some of the most highly questionable and controversial Corps projects and then
substantially revised the list of projects reviewed and their status (once again all
behind closed doors), gives the public no confidence that the cleared projects rep-
resent a sound and environmentally sustainable investment.
Instead, the Corps actions have increased the publics lack of confidence in the
Corps ability to plan water resource projects in an objective and reliable manner.
Now more than ever, Congress must enact meaningful Corps reforms to improve the
broken process and help restore faith in this scandal-plagued agency. The Corps re-
form bills introduced in the Senate and House (S. 1987, S. 646, H.R. 1310 and H.R.
97
2353) contain crucial reforms that cannot be postponed. We urge the Administration
to actively support these legislative proposals as Congress considers authorizing
even more water resource projects during debate over the Water Resource Develop-
ment Act.
We very much appreciate the leadership of the Bush Administration in proposing
a more environmentally responsible budget for the Corps of Engineers for fiscal year
03, and hope that you will fight to keep this years budget from growing as it moves
through Congress. We also hope that the Administration will work to make the
Corps entire program more environmentally and fiscally responsible by actively
supporting the important legislative proposals directed at reforming the Corps of
Engineers.
Sincerely,
Bradford T. McLane, Executive Director, Alabama Rivers Alliance; Kathy
Andria, President, American Bottom Conservancy; S. Elizabeth
Birnbaum, Director of Government Affairs, American Rivers; David
McLain, Executive Director, Apalachicola Bay and Riverkeeper;
David Gowdey, Executive Director, Arizona Wildlife Federation; Dan-
iel DeVun, Vice President, Arkansas Nature Alliance; Jim Wood,
Representative, Arkansas Wildlife Federation; Rob Fisher, Conserva-
tion Director, Audubon Arkansas; Sidney Maddock, Environmental
Analyst, Biodiversity Legal Foundation; John Koeferl, Founding
Board Member, Citizens Against Widening the Industrial Canal;
Jamie Matera, Outreach Coordinator, Coast Alliance; Peter Huhtala,
Executive Director, Columbia Deepening Opposition Group; Matthew
Van Ess, Director, Columbia River Estuary Study Taskforce; Patricia
A. Pendergrast, President, Connecticut Ornithological Association;
Karen Blue, Executive Director, Conservation Council for Hawaii;
Michael E. Riska, Executive Director, Delaware Nature Society;
Maya K. van Rossum, Delaware Riverkeeper, Delaware Riverkeeper
Network; Val Washington, Executive Director, Environmental Advo-
cates of New York; Mona Shoup, Chair, Friends of Clear Creek; Erich
Pica, Director, Green Scissors Campaign, Friends of the Earth;
Manley K. Fuller III, President, Florida Wildlife Federation; Jim
Blackburn, Chair, Galveston Bay Conservation and Preservation As-
sociation; Jerry L. McCollum, President and CEO, Georgia Wildlife
Federation; Margaret Wooster, Executive Director, Great Lakes
United; Cyn Sarthou, Executive Director, Gulf Restoration Network;
Marilyn Blackwell, President, Help Save The Apalachicola River
Group; Pamela Dashiell, President, Holy Cross Neighborhood Asso-
ciation; Steven G. Sorensen, Past President, Kansas Wildlife Federa-
tion; Tom Fitzgerald, Director, Kentucky Resources Council, Inc.;
Judy Petersen, Executive Director, Kentucky Waterways Alliance,
Inc.; Cam Davis, Executive Director, Lake Michigan Federation;
Larry Mitchell, President, League of Ohio Sportsmen; Mark F. Ten
Eyck, Advocacy Director, Minnesota Center for Environmental Advo-
cacy; Kenneth Hiemenz, President, Minnesota Conservation Federa-
tion; Tim Sullivan, Executive Director, Mississippi River Basin Alli-
ance; Bea Covington, Executive Director, Missouri Coalition for the
Environment; Perry Plumart, Director of Government Relations, Na-
tional Audubon Society; Jamie Rappaport Clark, Senior Vice Presi-
dent, National Wildlife Federation; Marian Maas, Ph.D., Conserva-
tion Programs Chair, Nebraska Wildlife Federation; Jim Stephenson,
Program Analyst, North Carolina Coastal Federation; Chuck Rice,
Executive Director, North Carolina Wildlife Federation; Nina Bell,
J.D., Executive Director, Northwest Environmental Advocates; Vicki
Deisner, Executive Director, Ohio Environmental Council; Ella F.
Filippone, Executive Administrator, Passaic River Coalition; Jim Ste-
vens, President, People to Save the Sheyenne; Gerald H. Meral,
Ph.D., Executive Director, Planning and Conservation League; Clark
Bullard, Member of the Board, Prairie Rivers Network; Magi Sha-
piro, Member of the Board, Public Employees for Environmental Re-
sponsibility; Todd Ambs, Executive Director, River Alliance of Wis-
consin; Mike Fremont, President, Rivers Unlimited; Angela Viney,
Executive Director, South Carolina Wildlife Federation; Chris Hesla,
Executive Director, South Dakota Wildlife Federation; Gwen Griffith,
DVM, MS, Program Director, Tennessee Environmental Council; Mi-
chael Utt, President, The Ohio Smallmouth Alliance; Melanie Winter,
Director, The River Project; Wilfred Cwikiel, Water Resource Pro-
98
gram Director, Tip of the Mitt Watershed Council; Kelly D. Lowry,
Esq., General Counsel and Water Program Director, Vermont Nat-
ural Resources Council; Larry Baesler, Executive Director, Wyoming
Wildlife Federation
The need for more accountability in the Corps becomes more apparent by the
month, as a growing list of project studies have been found to have been manipu-
lated or contain egregious errors:
In December 2000, the Army Inspector General reprimanded three senior Corps
officialsincluding the second-ranking general in the agencyfor manipulating
studies of a billion dollar expansion of seven locks on the Upper Mississippi and Illi-
nois River.
In January 2001, the Corps suspended all work on the $90 million Chesapeake
and Delaware Canal deepening project after four Eastern Maryland retirees dem-
onstrated basic math errors and fundamentally flawed assumptions that erro-
neously showed the project to be justified.
In March 2002, the Portland Oregonian concluded an extensive investigation
that found the Corps had overstated the benefits of a $190 million deepening project
for the Columbia River by more than 125 percent, and that in fact there was no
economic justification for proceeding with the project.
A few days later a National Academy of Sciences panel harshly criticized a
Corps of Engineers model of the carrying capacity of the Florida Keys to accommo-
date future development: Incomplete and outdated information, coupled with inac-
curate assumptions, makes the modelas it stands nowinappropriate for drawing
conclusions about the impact of future development.
Also in March, a U.S. District Court judge in Ft. Worth, Texas issued an injunc-
tion against proceeding with the $127 million Dallas Floodway Extension project.
The judge ruled the Corps had failed to consider smaller-scale alternativessuch
as a simple levee raiseto re-engineering the whole Trinity River. Most of the bene-
fits of the re-engineering project could be achieved through the smaller project at
less than one-third of the cost.
And just last week, the General Accounting Office issued a scathing report on
the lack of economic justification for the $420 million Delaware River deepening
project. The report found that the Corps had made an appalling series of material
errors citing miscalculations, invalid assumptions, and reliance upon outdated in-
formation that led the Corps to overestimate benefits by more than 200 percent.
Dozens of other examples of problematic and controversial projects could also be
cited that together account for billions more dollars in wasteful spending.
A key way to restore some credibility to the Corps project planning process is to
implement a system of independent peer review for costly and controversial projects.
A workable and faithful independent peer review process should include the fol-
lowing elements:
True independence from the Corps we suggest locating the Director of Inde-
pendent Review in the Office of the Army Inspector General.
102
Integration into the existing public comment period so as not to unnecessarily
delay completion of project studies.
Capped review costs at $250,000 or no more than half of 1 percent of total
project costs for more expensive projects.
The need for independent review has now been endorsed by the National Academy
of Sciences, the General Accounting Office, President Bush and many Members of
Congress, and dozens of public interest groups across the Nation.
RESTORING INTEGRITY TO THE AUTHORIZATION PROCESS
There are growing external pressures placed on the Corps to green-light projects
lacking true economic justification. Congress will contingently authorize a project
based upon a favorable finding by the Corps prior to the necessary feasibility stud-
ies being completed. There is a correlation between contingent authorizations and
later findings that a project study had been poorly conducted on an unjustified
project. For example, two of the projects listed earlier in this testimony, the Colum-
bia River deepening project and C&D Canal deepening project in Eastern Maryland,
were both contingent authorizations.
The Smith-Feingold-McCain reform bill would address this problem by allowing
Senators to raise a point of order when controversial projects are included in author-
izing legislation without the Corps first completing the mandatory feasibility studies
and approval from the Chief of Engineers. S. 1987 would take significant steps to-
ward restoring integrity to the authorization process.
We are also very concerned that there are efforts underway to seek a contingent
authorization of the billion-dollar Upper Mississippi and Illinois Rivers lock expan-
sion project in the hopes of beginning Pre-construction, Engineering, and Design.
The Corps has only prepared an Interim Report introducing various scenarios, but
has still not done any in-depth re-evaluation of alternatives that would lead to a
recommendation to Congress.
One of the best arguments for not proceeding with authorization of any Upper
Mississippi navigation project in this WRDA comes from the Inland Waterways
Users Board themselves, an industry advisory committee for the Army Corps of En-
gineers. A construction schedule for inland waterways projects posted on its website
lists the Upper Mississippi lock expansion as not being able to start construction
until 2020and this is the optimistic scenario. A limiting factor is that despite a
current surplus in the Inland Waterways Trust Fund, so many waterways expan-
sion projects are being sought by the navigation industry that the pace of construc-
tion will be limited by the availability of money from this fund, which is generated
from a tax on diesel fuel used for barges.
NEED FOR CLEAR PRIORITIES
A more recent, but growing, pressure on the backlog is mission creep within the
Corps of Engineers. The Corps has three congressionally mandated primary mis-
sions: navigation, flood damage reduction, and environmental protection. Other ac-
tivities such as hydropower, recreation management, and water supply are per-
mitted when associated with a multi-purpose project. However, the Corps has
sought and Congress has authorized to extend its tentacles into irrigation, munic-
ipal water supply, wastewater treatment, and even construction of public schools.
Each of these areas has traditionally been carried out by the private sector or
through other government programs.
The Corps does not have extensive experience in cross-basin water transfer
projects, for example, but is seeking to build more than a billion dollars worth of
pump and distribution infrastructure in Eastern Arkansas to assist rice irrigation.
A lack of experience led the Corps to only look at structural solutions to long-term
groundwater depletion concerns. After the release of the Corps initial design for the
$319 million Grand Prairie Area demonstration plan, hundreds of farmersthe very
people the Corps was trying to help withheld support for the project because they
prefer cheaper and more effective non-structural conservation alternatives that
would minimize water taxes slated to be assessed on them to pay for the project.
In the case of municipal water supply and wastewater treatment, or what has also
been called environmental infrastructure, Corps involvement in these projects is
a redundantand wastefulsubstitute for the Environmental Protection Agencys
Drinking Water and Clean Water State Revolving Funds. The only difference is that
projects obtained through the Corps effectively receive grants as opposed to loans,
and the allocation of funds to projects under the Corps budget is driven almost ex-
clusively by politics.
In Los Angeles and Washington, DC, the Corps has entered into billion dollar and
hundred million dollar contracts, respectively, to build and renovate public schools.
But they have done a poor job at that too, while at the same time crowding out con-
struction management firms in the private sector that could have performed the
work faster and at less cost.
President Bush has sought to limit mission creep by not requesting funds for
these types of projects. His fiscal 2003 budget request outlines the impacts of mis-
sion creep:
104
Congress periodically directs the Corps to work in other areas that duplicate
existing Federal programs or are activities that should be carried out by non-
Federal interests. This mission creep diverts the Corps from its primary busi-
ness lines, slows down completion of higher priority construction projects, and
postpones the benefits that completing these projects would bring.
The reform to check mission creep is simple: deauthorize all of the unconstructed
irrigation, municipal water supply and wastewater projects, and stop the Corps from
entering into contracts with local school districts to build schools.
OUTDATED PROJECTS
The Corps of Engineers recently announced that it would pause more than 150
authorized projects in order to resolve questions over the accuracy and currency
of economic analyses, the validity of plan formulation decisions, and the rigor of the
review process. This was a significant acknowledgement that the agency too often
relies upon outdated economic information, as well as other problems with the
project planning process.
For example, the Delaware River deepening project was justified in 1992 pri-
marily upon projections of increased oil imports and scrap metal exports. However,
we now have the benefit of 10 years of actual data, which reveals that the Corps
predictions were overly optimistic. None of the area refineries have significantly in-
creased their oil imports, mostly because they have not, nor plan to, make any ex-
pansion of plant capacity in order to avoid having to install expensive pollution con-
trol technology if they did expand. By 2000, scrap metal was no longer being ex-
ported from the Port of Philadelphia because the former Soviet states replaced the
U.S. as the main provider of scrap to Turkey.
Both of these trends were apparent during the early and mid1990s, but the
Corps never updated its project studies to reflect these real world market changes,
even though they did revise cost estimates downward during that time. In fact, the
Corps continually denied the economic reality of the project and continually sought
construction funds for this project despite knowing its benefits analysis was woefully
out of date. Only after the General Accounting Office examined the project has the
Corps acknowledged these errors and sought to update their feasibility report.
Although we hoped the Corps pause represented a real effort to change the way
the agency did business, the Corps did not follow through with an honest evaluation
of the 150 projects. In fact, only eight projects will be subjected to further analysis.
Although the Corps cited that dozens of projects were already undergoing further
re-evaluation before the launch of the nationwide review, the Corps failed to correct
its studies on dozens of other boondoggle projects like the Dallas Floodway and
Grand Prairie irrigation projects.
The Corps review fiasco is yet another indication the agency is incapable of re-
forming itself and that real reform must be passed into law this year by Congress.
MODERNIZING THE PROJECT PLANNING PROCESS
The Smith-Feingold-McCain bill would also require the Corps to work with the
National Academy of Sciences in modernizing the planning guidelines. For example,
the guidelines should be updated to ensure full accounting of costs of projectsin-
cluding adverse economic impacts to other interestsincorporating new techniques
in risk and uncertainty analysis, eliminating biases and disincentives for non-
structural flood damage reduction projects, incorporate new analytical techniques,
and ensuring projects are justified upon benefits to the public interest rather than
a few private firms or individuals.
A full revision of the Corps planning guidelines was recommended by the National
Academy of Sciences itself in a 1999 report on the Corps project planning process.
The Principles and Guidelines, the Corps planning documents, was last updated in
1983, and with the exception of a few minor revisions, has basically been frozen in
time for nearly two decades.
Many of the Corps problems stem from an increasingly obsolete planning process
that was developed at a time when water projects were seen as more of a job cre-
ation program than a national investment.
Our Nation and thinking certainly have changed since the New Deal Era, but the
Corps still relies on the 1936 Flood Control Acts standards to call a billion dollar
project economically justified if the benefits outweigh the costs by even one dollar.
No business would ever make an investment knowing that they would get no return
on their dollar, and we deserve no less from our investment of tax dollars.
The Smith-Feingold-McCain bills proposal to require project benefits be 1.5 times
the total estimated costs in order to qualify as economically justified makes strong
fiscal sense, by ensuring at least a modicum of a return to the Federal taxpayer.
105
An additional benefit is that this reform will help break the backlog by
deauthorizing marginal projects that have yet to start construction.
Another problem with the Corps is that it studies and plans projects in a vacuum.
The Corps assumes there are no budget or other constraints when developing a con-
struction schedule. For example, the Corps benefit-cost analysis for the $420 million
Delaware River deepening project, anticipated construction over a 4-year period.
There was virtually no chance of this ever happening, as the project would have to
receive more than $90 million5 percent of the agencys overall construction budg-
eteach year for four straight years. The actual construction appropriations for the
project have not exceeded $20 millionwith none of those funds ever being spent
on actual constructionbut by optimistically scheduling construction over only 4
years, the Corps was able to reduce estimated costs by maximizing scales of effi-
ciency. In fact, this problem was cited by the General Accounting Office as another
factor that led the Corps to overestimate the true benefits of the project.
Although being able to construct large-scale projects quickly is ideal and preferred
because it minimizes construction costs while quickly returning benefits to tax-
payers. However, such scheduling does not reflect the harsh reality of a massive
backlog and growing budget constraints. S. 1987 requires the Corps to devise more
realistic construction schedules for projects and reflect the impacts on project costs.
The Corps tunnel vision is also apparent in its planning of port development
projects. Currently, there is a race to the bottom amongst major U.S. ports, includ-
ing 12 major Corps deepening projects along the East Coast that together will cost
taxpayers $2.4 billion to complete. This phenomenon is stoked by a shift amongst
the shipping lines to larger and deeper-draft container ships and a fear among ports
that they may be left behind.
The problem is that few of these ports will be successful in alluring these larger
ships to their docks. With significant deregulation of the shipping industry in the
1990s and other factors, shipping lines have consolidated and begun to rely more
heavily upon hub ports like New York/New Jersey Harbor and the Ports of Los An-
geles and Long Beach. The result is these larger ships will carry more cargo, but
to fewer ports. Medium-sized ports are poised to become feeder ports in this system,
similar to the way the airport network has evolved. These ports will also find advan-
tages in specializing in niche cargos, like the Port of Wilmington, Delawares suc-
cessful makeover into one of the nations premier ports for refrigerated produce.
Certain ports like those in New York and Los Angeles are logical choices for hubs
due to the tens of millions of consumers within a relatively few miles of the piers.
Other ports have natural advantages like the Port of Seattle that requires very little
dredging to maintain its deep berths, or Hampton Roads, Virginia, which already
is maintained at a deep draft and is well positioned only a few miles from the Atlan-
tic Ocean.
On the other hand, the Ports of Philadelphia and Portland, Oregon are more than
100 miles inland, and the cost of maintaining deep access channels is inherently ex-
pensive. Furthermore, it is more difficult and much slower to navigate up 100 hun-
dred miles of a restricted channel, consequently it takes much longer for ships to
traverse those rivers to deliver their goods than it would to a port near the open
ocean.
The Corps continues to pursue many more deepening projects than the Nation
needs. This is because the Corps evaluates a particular deepening project without
any consideration of potential adverse economic affect upon its competitor ports.
These studies do not take into account the potential impacts of other nearby port
development projects in the works, but not yet completed, that can affect the ability
of the port under study to ultimately attract more ships.
Also, the Corps expertise and mandate generally limit it to only consider deep-
ening a ports access channels when studying port improvements. However, a ports
depth is only one of many factors that determine its competitiveness. The amount
of dockside land available to store containers, intermodal connections to rail and
highways, crane equipment, labor conditions, geography and many other factors are
just as important.
On April 15, the Alameda Corridor project opened, connecting the Ports of Los An-
geles and Long Beach to downtown L.A.s rail and highway nexus, 20 miles inland.
The $2.4 billion collaborative project was on time, on budget, had almost no public
opposition, and used only a moderate amount of Federal funds22 percent of the
total cost plus a $400 million loan. The loan and the rest of the costs of the project
are being borne by the ports, Los Angeles County, and revenue bonds to be paid
off over time by a $15 user fee on each loaded container that uses the corridor.
Port experts are predicting that the efficiencies gained from the corridor by facili-
tating the quick transfer of containers from ships to the highways and rail lines
leading out of L.A. will solidify Los Angeles and Long Beachs position as the Nation
106
top two ports for decades to come. Transportation Secretary Norman Mineta at the
corridor dedication ceremony called the project, a powerful example of what we
want to encourage throughout the country.
We urge Congress to require the Corps to institute rational port planning to con-
sider what investments are in the best national interest on a regional basis. In fact,
the Department of Transportation is already ahead of the Corps on this issue, and
is currently funding a project at the University of Rhode Island Transportation Cen-
ter to develop a comprehensive framework for sustainable container port develop-
ment.
S. 1987 would require the Corps to work with the National Academy of Sciences
in revising its project planning guidelines include rational port planning. Unfortu-
nately, in recent years some port interests have pushed for increasing the Federal
subsidy of dredging ports deeper than 45-feet from 40 percent to 65 percent. If such
a change were applied to the New York/New Jersey Harbor project to deepen to 50-
feet, taxpayers would be fleeced for more than $375 million. There is no need for
the U.S. to subsidize port overcapacity through the dredging of dozens of ports past
45-feet. A few select ports with depths of 45-feet or more can serve the whole Nation
well as hubs.
We strongly urge Congress to reject any attempt this year to increase the Federal
subsidy for dredging deep draft ports past 45-feet.
ENSURING EVERYONE PAYS THEIR FAIR SHARE
Some have concerns over whether cost sharing and even other reforms could nega-
tively affect underprivileged communities. However, most likely the reforms in the
Smith-Feingold-McCain bill would be a net benefit to poor and minority commu-
nities.
In the case of cost sharing reforms, Section 103(m) of the Water Resources Devel-
opment Act of 1986 allows for cost sharing reductions on flood damage reduction
projects down to as little as 5 percent for qualifying poor communities. In WRDA
2000, Congress extended the ability to pay rules to all Corps projects and directed
the Corps to rewrite the qualifying rules and formulas. The Corps has not completed
revision of these rules, and concerns regarding the impact of cost sharing upon fi-
nancially strapped communities are best addressed through that process.
A significant benefit to disadvantaged communities and all stakeholders are the
reforms in S. 1987 that call for greater public involvement in the project planning
process, inclusion of adverse economic impacts of a project on a community in the
benefit-to-cost analysis. Additionally, independent peer review would ensure that
the voices of all communities are better heard and listened to by the Corps.
One of the worst cases of the Corps failing to take into account a projects effect
on a poor, minority community is the $715 million Inner Harbor Navigation Canal
in New Orleans. This project lacks economic justification. In addition, there is evi-
dence that the Corps used Enron-style accounting and cost-apportionment to add-
on a hundreds of million dollar deepening element of the project, to benefit just one
shipyard.
This lock replacement and canal-deepening project was first authorized in 1956
and has been vigorously fought by the surrounding poor African-American neighbor-
hoods ever since. Concern over the Corps ignorance of the local residents in plan-
ning the project came to a head in 1991, when Congress directed the Corps to create
a stakeholder advisory committee composed of local citizens from affected neighbor-
hoods and to establish a mitigation fund to compensate those in the neighborhood
who would have to suffer the extremely disruptive effects of seven straight years
of construction.
However, despite this congressional directive, the Corps has in many ways treated
the local residents even worse by hiding critical facts from them about various as-
pects of the project.
In an off-hand remark to residents at a public meeting about the project, a Corps
engineer mentioned that the canal was going to be dredged to 40-ft. The plan Con-
gress approved only included designs for a 36-ft deep lock. Testing has shown that
between 36 and 40-ft levels there are tons of toxic sediments, which now will be
flushed out to Lake Pontchartrain, a popular swimming area for the children of the
nearby neighborhoods. This additional dredging would also add tens of millions or
more costs to the project to only accommodate a handful of additional ships.
The Corps also claimed for years that the project would actually reduce traffic
congestion at the bridges that cross the canal because barges and ships would be
able to move through the new lock faster. After close examination of the Corps
plans, a local retired engineer discovered that the construction process would fre-
quently cause several mile long backups for 45 minutes or more each day, creating
a traffic nightmare for thousands of commuters trying to get to their jobs in the
heart of New Orleans. Only recently at a public meeting did the Corps acknowledge
that these traffic problems would be created and now pledge to investigate solutions.
New solutions that could add another hundred million dollars or more to the cost
of this already unjustified, over-budget project.
There are dozens of other cases where the Corps has ill-treated or just flat out
ignored citizens who are not considered their project clients such as:
The poor African-American Cadillac Heights neighborhood of Dallas, which pre-
fers a non-structural flood control alternative. The Corps plan is designed specifi-
cally to accommodate new toll highways inside existing levees that would actually
reduce the flood capacity of the river channel;
Rice farmers on the Grand Prairie of Arkansas who are being forced to swallow
higher taxes and a gold-plated project just to get the smaller-scale on farm assist-
ance that they really desire;
Crab fishermen who are the greatest economic engine of struggling Clatsop
County, Oregon and Pacific County, Washington whose fishery will be at risk from
the Corps plan to dump tens of millions tons of dredged material onto their fishing
grounds.
109
TIME FOR CHANGE
The Corps of Engineers has a vast influence over our nations waters, and its
work affects millions of Americans. Many projects have had a positive effect, pro-
tecting countless lives from floods and bringing the fruits of midwestern farmers
labor to the rest of the world. But there are also many projects that have had a
significant negative effect on peoples lives, have harmed other industries and users
of the nations waters who are not the Corps traditional clients, and most out-
rageously squandered taxpayer dollars on these activities.
At the root of so many of the agencys problems is the belief that the local sponsor
of a project is Corps sole client. What agency officials lose sight of when they pro-
mote a wasteful project is that the Federal taxpayer is the primary client, and the
majority shareholder of virtually all Corps projects.
The Army Inspector General went out of his way to highlight these concerns in
his December 2000 report on the Upper Mississippi River project scandal:
Although this investigation focused on one study, the testimony and evidence
presented strong indications that institutional bias might extend throughout the
Corps. Advocacy, growth, the customer service model, and the Corps reliance on
external funding combined to create an atmosphere where objectivity in its
analysis was placed in jeopardy The overall impression conveyed by testimony
of Corps employees was that some of them had no confidence in the integrity
of the Corps study process.
The Corps has certain expertise and resources that can greatly assist local com-
munities in building something they would not be able to do on their own. But the
agency is accountable to the Nation as a whole, and its mandate is to pursue a civil
works program that will benefit the overall national economy and welfare of its citi-
zens.
Unfortunately, the Corps has failed to remember that it serves the American tax-
payer. Therefore, it is imperative upon Congress to enact real Corps reform this
year. In fact, no Water Resources Development Act should pass without reform. At
risk is the publics confidence in the Army Corps of Engineers and any hope that
Congress can restrain itself from ever-escalating pork barrel spending, even in the
midst of the a very expensive and important war on terrorism.
There are 285 projects in the known active construction backlogthose projects
that are funded in the Construction General account of the Presidents budget re-
questwhich still require $28.1 billion to complete.
The typical project in the known active construction backlog is only 24 percent
complete (based on median rate of completion).
190 projects in the known active construction backlog are less than 50 percent
complete and will require $22.3 billion more of taxpayer funds to complete.
PROJECTS WITH A BENEFIT-TO-COST RATIO OF LESS THAN 1.5 TO 1.0
1 Projects by the Corps Northwestern Division were not included in this analysis because
Budget Justification Statements for this division were not available on the Internet.
2 Based upon $28 billion of the known active construction backlog (those projects listed in the
Corps FY02 Budget Justification Statements, not including the Northwestern Division), $8 bil-
lion of inactive projects (those that even the Corps has determined are no longer economically
justified, are no longer in the Federal interest, or are no longer supported by a local sponsor),
approximately $16 billion in additional projects that have been authorized by Congress and
projects in the Pre-construction Engineering and Design (PED) phase.
110
39 of these projects ($4.3 billion remaining balance) are less than 50 percent
completed, with the typical project being 24 percent complete (based on median rate
of completion).
The Dare County Beach replacement project will cost $1.8 billion to maintain
15 miles of wide beach in front of four booming beach towns for the next 50 years.
The Corps has estimated only a 27 percent return in net benefits (1.27 to 1.0 ben-
efit-to-cost ratio), despite much uncertainty about the cost and ability of the beach
to hold the sand for very long.
PROJECTS WITH OUTDATED ECONOMIC ANALYSES
In recent years the Administration has budgeted a modest amount for sand
pumping projects only to see Congress dramatically increase funding for beaches. In
the last 3 years, beach funding has increased 60 percent while the overall Corps
budget increased 9 percent.
35 projectsrepresenting $6.3 billion of the known active construction back-
logwere budgeted for in President Bushs Fiscal Year 2002 Budget.
Congress subsequently funded a total of 58 beach projects for construction and
48 studies of new beach projects, which if all are continued through to completion
over the next several decades would cost taxpayers well over $10 billion.
The analysis of the hypothetical scenario in the draft report relies upon two key
assumptions that lead to a substantial understatement of the benefits that accrue
locally.
It uses an inappropriate measurethe place of principal residence of the peo-
ple who own local property or who use the beachto allocate the benefits of a
project to the beach region (local) or to the rest of the nation (national). The
issue here is not who benefits, but whether the way in which the benefits accrue
enable the State or local authorities to support a non-Federal cost-share. That
depends largely upon where the benefits will occur, not on where the people
who receive the benefits reside most of the year.
111
Although the report views some national and some regional economic develop-
ment benefits as local, it limits the local area to the county or counties in which
the shore protection project physically is located. Coastal States typically pay
much of the non-Federal costs of these projects. e.g., between 50 percent and
100 percent in the five States that the Corps surveyed. Therefore, we believe
the report should have viewed as local all benefits that flow to any resident or
business in the State or should have attempted, at a minimum, to estimate the
benefits that accrue in-State beyond the county line. Instead, it simply includes
them on the national side of the ledger.
STORM DAMAGE REDUCTION
All storm damage reduction effects redound to the benefit of the local community.
By reducing damages to structures and their contents and to local infrastructure,
a shore protection project raises local property values compared to the without
project condition. Since real property is a fixed asset, most of this added value re-
mains within the reach of local authorities and augments their ability to contribute
towards the projects construction costs, for example, through property or occupancy
taxes. It does not matter that some property owners may reside elsewhere. The
project reduces storm damages only locally, for those who live elsewhere, it reduces
damages to their second home, rental property, or business; its contents; and the
surrounding land.
RECREATION
Shore protection projects that support recreation can add significantly to the abil-
ity of the State and local sponsor to contribute to the costs of construction. The anal-
ysis of the hypothetical scenario in the report underestimates these local benefits
in several ways:
In limiting the beach region to the county, the report understates the local compo-
nent of the regional economic development benefits. The people who travel farther
to reach the beach are more likely to stay overnight nearby in a hotel or rental unit
and to spend money when they get there. Their beach-trip spending beyond the
county line is likely to occur mostly in-State, but the report allocates the associated
benefits to the rest of the nation.
Although spending by foreign tourists in the coastal State is new spending from
a national perspective, the added value that it contributes to the national economy
primarily benefits the local coastal community and the State.
The intangibles, subjective value of the beach experience generally exceeds the fi-
nancial costs that beach users incur. For beach users who live within the State ei-
ther part-time or full-time, all of this consumer surplus is local.
The State or local authorities can access only a part of this consumer surplus via
a user fee without significantly affecting overall tourist spending. Since the amount
that they could so collect from out-of-State and foreign visitors is potentially avail-
able to help pay for the project, it is a local benefit as well.
The report treats the Federal tax revenue from spending in the beach region as
a benefit that occurs outside the beach region. However, the net effect of a project
on Treasury receipts probably is insignificant. In the absence of the project, it is
likely that: (1) spending by recreation users (perhaps elsewhere) would generate a
similar level of tax revenue and (2) the alternative Federal investment (same
amount spent elsewhere) would produce a comparable level of tax revenue.
PUBLIC FINANCE CAPABILITIES
The draft report does not sufficiently explore a complex question that is central
to determining an appropriate non-Federal coat-share. To what extent will the pre-
dicted benefits of a shore protection project occur within the reach of local or State
authorities and therefore potentially be available to support a non-Federal cost-
share?
The draft report assumes that local authorities can support a portion of the
projects costs only through belt tightening or by developing an additional source of
recreation-based revenue. However, a shore protection project chiefly benefits homes
and businesses in the local coastal community. By preserving existing property
value and facilitating further coastal development in that community, a project in
affect augments the long-term local tax base. The draft report did not examine the
extent to which this effect of a project on private property values, under a range
of property tax rates that now prevail, contributes to the revenues that coastal com-
munities now are collecting.
112
The report also should have examined the option of charging existing users of the
beach a fee or a higher fee. It focuses only on the ability of local authorities to raise
additional funds from new visitors or a sales tax increase.
In calculating the fiscal capability of State and local interests, the report also
makes two significant computational errors:
It does not represent the stream of payments property. Beach replenishment oc-
curs periodically over a projects lifetime. The report assumes the local sponsor
would issue a bond at the outset of a project that is large enough to pay all future
costs up front, years and decades before much of the work actually will occur.
It also overestimates the up-front gum that non-Federal interests would need to
borrow when it multiplies average annual costs by 50. The amount that a local
sponsor would borrow is equivalent to the principal of the loan; average annual
costs include both the principal and a substantial interest component.
ENVIRONMENTAL IMPACTS
According to the draft report, shore protection projects can benefit species that use
the beach such as shorebirds, but cause short-term damage to habitat in the marine
subtidal zone. The draft report does not try to assess the relevance, if any, of these
benefits to possible changes to the cost-sharing formula.
Project opponents claim that shore protection projects also can lead to more seri-
ous long-term impacts, e.g., to fishery habitat areas of particular concern, new estu-
aries, and in shallow areas that are less subject to littoral drift such as a bay. By
facilitating the further development of certain coastal communities and adjacent
areas, projects may have other adverse environmental impacts as well. Since the
early 1970s, the Corps has recommended dozens of projects that involve periodic
beach replenishment, covering major stretches of the New Jersey, Florida, and
North Carolina coastlines and significant segments in a few other States. It is in-
volved in a multi-year effort to monitor the biological impact of six projects in New
Jersey, but has not examined the cumulative environmental impacts of: (1) the
Corps program as a whole; (2) the many other such projects that local authorities
and States now fund on their own; and (3) related Federal disaster relief and Fed-
eral flood insurance efforts that affect coastal development. The draft report does
not address such concerns.
1 Circular A94, Guidelines and Discount Rates for Benefit-Cost Analysis of Federal Programs,
page 7.
115
ory. In Section 7(a) of the Department of Transportation Act (P.L. 89670), Congress
defines the primary navigation benefits in terms of rate savings to shippers rather
than resource cost savings. In Section 219 of WRDA 1999 (P.L 10653), Congress
requires to Corps to . . . calculate the benefits of the nonstructural project using
methods similar to those used for calculating the benefits of structural projects, in-
cluding similar treatment in calculating the benefits from losses avoided.despite
the fact that the economic impacts of structural and non-structural alternatives are
quite different.
The executive branch develops implementation guidance that allows the best esti-
mate of economic benefits within the constraints imposed by law, but benefit-defin-
ing legislation signals that Congress seeks outcomes different from those that would
be produced by objective economic analysis. Unfortunately, S. 1987 would move fur-
ther toward legislating benefit procedures for the executive branch. Congress should
affirm its commitment to using the best analytical techniques in every Civil Works
project study by abrogating past benefit-defining provisions and by avoiding new
constraints on objective benefit and cost measurements.
Review is an essential part of the recommendation development process
Sound water project planning requires not only a clear policy framework in which
to conduct analyses, it requires timetime to develop a plan and time for review
of the plan so that national as a well as local perspectives can be brought to the
attention of decisionmakers. During the last decade, the quality of the internal exec-
utive branch review processes has declined; one major reason for this decline is that
Congress has authorized many projects that had not received the full benefit of ex-
ecutive branch review. The executive branch project review culminates when the
Secretary of the Army transmits a report of the Chief of Engineers to Congress. In
the last decade, Congress has authorized dozens of projects without waiting for com-
pletion of the report development and review process. Many of these authorizations
were conditioned on favorable report of the Chief of Engineers by a future specific
date.
Conditional authorizations create enormous pressures on the Corps review staff.
In the interest of time and to avoid disappointing Members of Congress who sup-
ported conditional congressional approval, problems are glossed over and reviewers
concerns are ignored. In any case, even if the Chief of Engineers report is completed
by the deadline, the Secretary and the other Departments of Government may not
have even initiated their final policy-level review.
It is not surprising that projects that have been found deficient in one way or an-
other in recent times Delaware River Deepening, The Chesapeake and Delaware
Canal and the Dallas Floodway Project were authorized without a report trans-
mitted by the Secretary of the Army. In the case of the Upper Mississippi River
Navigation study, Congress specifically authorized the Corps to proceed with engi-
neering and design on expanded locks before even a draft report was released. Is
it surprising that the Corps was eager to find expansion projects justified? Except
in the most extraordinary circumstances, Congress should authorize only those
projects that have completed the executive branch review process.
COST SHARING AND IMPROVED RESOURCE ALLOCATION
The Corps of Engineers is uniquely qualified by its professional resources and its
adherence to the Principles and Guidelines to address the full spectrum of the na-
tions water problems. I believe that the best opportunity for the Nation to integrate
the management of all water quality and quantity problems is through the Civil
Works planning process under the existing Principles and up-dated Guidelines.
Congress and the President must work together to take full advantage of the
Corps potential to develop solutions to the nations water and related land resource
problems and to recommend productive, cost-effective public investments. Congress
can best ensure that the Corps consistently pursues sound water resources develop-
ment and management by taking these actions: (1) direct the U.S. Water Resource
Council to review and update executive branch planning guidance, (2) remove obsta-
cles to unbiased analysis created by past legislation, (3) authorize only those
projects that have completed the executive branch study and review process, (4) re-
institute substantial cost sharing for all projects without exception, (5) clarify the
kinds of studies it expects and modify study cost sharing to support those studies,
and (6) require demand management be an integral part of the delivery of project
services when it can increase project benefits. Finally Congress should support the
Department of the Army and Corps in strengthening the Civil Works planning and
review capabilities and require use of outside experts to guide and review important
studies.
In general the ASFPM believes that the US Army Corps of Engineers has a long
proud tradition of providing water resource projects to the Nation. However, we also
believe that the model being used today best served the Nation in a past era, and
that it is time reshape the Corps based on modern domestic policies.
Current policy and process have resulted in disagreement over the economic and
environmental viability of many projects; a huge backlog of controversial projects;
division among the nations policymakers on how to invest in projects; and a situa-
tion where the cost of operating and maintaining existing projects is becoming ex-
cessive.
The policy and process model that we are currently working under:
1. Assumes that national return on investment (NED) is our focus for water re-
sources, yet we never consider the opportunity cost of this investment.
2. Assumes that environmental or social benefits are of a lesser value than eco-
nomic benefits, in spite of congressional actions to the contrary.
3. Has led to many non-Federal sponsors wasting time and money on projects that
are not justified, or will not be funded.
4. Has attempted to meet national objectives through an altruistic planning proc-
ess that is prone to manipulation to meet pre-conceived project outcomes.
5. Has failed to expand from a Federal investment mentality to one that embraces
and supports a broader array of domestic policies, most notably the lack of focus
on actions that reduce future disaster expenditures.
In order to address these issues and others, we will focus our testimony on the
following areas:
120
Trends in Flood damagesGrowing disaster expenditures
Despite the expenditure of over 100 billion dollars and years of efforts in Federal
programs to reduce flood damages and encourage sound floodplain management
flooding costs are now approaching $5-$8 billion per year. On one hand this may
be surprising, but on the other hand it was predictable. Our policies and practices
have tended to encourage people to occupy areas that are marginally protected from
flooding, or to take actions in the floodplain that have transferred their problem
onto others. The economist would suggest that these occasional damages are re-
flected in the economic models, and as long as benefits exceed cost, that escalating
flood damages is a rational outcome. For this model to work however, based on cur-
rent policies, it would needs to assume that there is virtually an unlimited supply
of money to pay for the disaster costs, and that other programs of domestic policy
would not suffer because of the transfer of dollars to pay for disasters.
The fact is that there is not an unlimited supply of cash, and that other domestic
programs do suffer from escalating disaster costs. To break this cycle the Corps
must begin to modify its model such that it leads to solutions that provide perma-
nent flood protection with an eye toward reducing disaster costs. Many times these
solutions may be the least cost solution, but may not satisfy the NED criteria. Rec-
ognizing the regional economic development goals of many local sponsors, we would
suggest that Congress encourage the ability to link Corps projects with other pro-
grams of economic development outside of flood hazard areas.
Principles and Guidelines (P&G)
The P&G have been used since 1983, when they replaced the Principles and
Standards. In spite of their shortcomings, in theory they provide a reasonable ap-
proach to justify an investment mentality for project alternatives. In reality, they
are a maze which both Federal and non-Federal sponsors navigate to justify a pre-
conceived outcome. The P&G alone fall short of supporting the domestic policies of
the Nation. At a minimum the P&G need to be reissued with the environmental
quality account being a required input to the process.
For P&G to be effective, the Congress must mandate the Corps to develop and
adopt methods for quantifying the economic value of environmental, cultural, and
social inputs. For the expenditures of the Corps to be effective, the P&G must be
augmented with decisionmaking criteria that reflect current domestic policies and
programs. In essence they need more than tweaking. The P&G do not reflect the
way planning is done today, by any level of government, let alone the Corps. Forcing
Corps staff to use these guidelines sets up an instant conflict in the project alter-
natives. The Principles and Guidelines need to reflect a collaborative, multi-objective
approach in the beginning, rather than attempting that collaboration at the end of
the process. The list of Environmental operating principles put forth by General
Flowers provides some excellent ideas for incorporation.
We would urge that the Principles and Guidelines be revised in collaboration with
a group of Corps partners, who work with the Corps and other programs in devel-
oping projects for flood loss reduction and environmental restoration. Incorporating
the ability to coordinate project implementation with other programs will provide
an opportunity to leverage dollars.
Benefit/Cost analysis.There is broad support of the need for modifications in the
approach for determining the cost effectiveness of projects. Much of this focus is
misplaced due to the emphasis in the process that results in selection of the NED
plan. Better to spend our efforts re-thinking the process to select the alternative,
so we end up with a project appropriate to the multiple needs of the local partner.
Incentives in cost sharing
There has been considerable discussion about the Federal/non-Federal cost share
formula. We offer no preference on a specific cost share, and suggest that formula
is a policy decision of Congress. We urge Congress to base their decisions on inde-
pendent studies, which carefully assess where the true interests of the nations tax-
payers lies.
What we do urge is a sliding cost share for non-Federal partners, which would
provide incentives for those partners to take responsibility for reducing flood risk
in their community.
There are communities in the Nation that are aggressively implementing pro-
grams that reduce the need for Federal project expenditures or for disaster relief.
Yet, we have likewise heard concerns from our members as to why should they con-
tinue to proactively fight future flood damages, when they can take the easy polit-
ical route, do nothing and simply wait for Federal projects and disaster relief. The
current system makes no sense, and does nothing to encourage local accountability
and responsibility for combating disaster expenditures.
121
It is time to Congress to communicate to those States and Communities that are
taking proactive steps to combat future flood losses, that they are doing the right
thing for their community and for the Nation. We would argue that by providing
a more favorable cost share to those communities that are proactively dealing with
future losses, that in the long run Federal expenditures for projects and disasters
will decrease.
Some might argue that this may be quite complex, but we would like to remind
these individuals that in the mid90s Corps Staff had developed the details for im-
plementing a similar plan, and that FEMA has over a decade of experience in a
similar program called the Community Rating System. These positive actions would
demonstrate a commitment that will save the Federal taxpayers money on disaster
relief, thus justifying the investment in the sliding cost share. A list of low cost in-
centives is attached.
The Federal role
The Federal Government has a key role to play in helping to reduce flood damage,
but that role has changed and evolved from what it was 30 to 60 years ago. It has
become apparent that federally developed solutions often yield single purpose
projects which tend to address specific flooding problems, but may pay insufficient
attention to other critical local considerations such as economic development, hous-
ing, water quality, watershed planning, natural resources, recreation and quality of
life. Without those considerations, local buy-in is often razor thin.
We have learned that some structural solutions to specific flooding problems can
inadvertently create new flooding problems downstream. Some generate higher op-
eration and maintenance costs than can realistically be supported by the local spon-
sor. Current programs tend to promote that flooding and flood protection is a Fed-
eral and not a local issue. Local governments and citizens grow to believe the Fed-
eral Government will bail them out if flooded or if the problem gets worse.
Structural flood control projects are necessary in many instances and are often
advocated by our members. Unfortunately, without the ability to offer various solu-
tions or a mix of approaches, structural policies and programs can provide incen-
tives to pursue solutions, which may not be the best choice for building hazard re-
sistance in some communities. It is important to recognize that current Federal
flood policy rewards those communities and states, which do the least to prevent
and solve their flooding problems. Those rewards come in the form of Federal dis-
aster assistance, Federal flood control projects and cost sharing for these actions.
The Corps cost-sharing formula needs to evolve in order to be consistent with the
evolution to new approaches in flood loss reduction in the Nation.
Independent Peer Review
The ASFPM understands the cry for independent review, in light of the revela-
tions during recent years. The problem with the independent peer review proposal
is that peer review is necessary for two reasons. The first is to introduce a level
of quality control, the second is to safeguard against what some might see as abuses
to the process. If the peer review is meant to implement a level of quality control,
than one needs to question why this is not already being accounted for within the
planning and design process. If it is to safeguard against abuses, than one needs
to question whether the problem is so severe within the Corps that the entire pro-
gram needs to be reorganized with new management. While clearly there is always
room for improved quality, the evidence would suggest that cleaning house is NOT
necessary.
What we do believe is necessary however is the following:
1. A renewed commitment by the Corps to quality Control measures and plans.
2. Occasional GAO audits of projects.
3. A zero tolerance policy for those found to be directing the manipulation of
project results.
4. Independent peer groups that are formed to evaluate the assumptions used in
the planning guidance.
While some direct abuses have been alleged, for the most part what we have
heard about tends to indicate planning guidance that is out of touch with real world
situations and current domestic policy. If independent project review comes about,
we suggest a streamlined process and a logical funding threshold is considered.
Surely a $25 million project is not reasonable. We see some individual homes being
built in the Nation with costs approaching that. Perhaps something 8 to 10 times
that amount might make more sense.
Backlog and de-authorization
There is a need to address review of the huge backlog of projects, with an eye
toward either re-authorizing or de-authorizing the projects. The experience of our
122
members suggests this backlog creates many problems. A common example occurs
immediately after a flood disaster. The community wants to do something because
of the damages it received, and the first thing they think of is some Corps project
that was looked at in the past, which sits on the shelf now, in an inactive state.
It may be there for a number of reasons, including being not cost effective, major
environmental harm, controversy, etc. In most instances, the project would probably
not be viable under todays circumstances, if it ever was. But the community sees
it as a quick solution and spends lots of effort and time trying to make the project
work, rather than looking at their problems and needs today, and working with all
the interests in community to identify viable and implementable solutions.
Mr. Chairman, MARC 2000 has been involved in the Upper Miss navigation study
since the inception of the feasibility study in 1993. Ten years later, we are on the
edge of our seats as the Corps of Engineers is poised to issue an Interim Report
on July 1 of this year. We believe there will be sufficient information in that report
for Congress to initiate a balanced modernization program in the Upper Mississippi
Basin that includes lock modernization and enhanced environmental restoration
programs.
This study has taken many turns and permutations over the last 10 years. One
of the most important developments in the past year has been the Chief of Engi-
neers decision to restart and restructure this study with the assistance of other
Federal and state agencies and stakeholder groups in the basin.
This Interim report should provide a fresh look at the risks we take in not mod-
ernizing the lock system in the Upper Miss Basin. It should also provide important
guidance on the risks we take as a Nation if we dont address pressing environ-
mental declines in the river. Private stakeholder groups have met and continue to
meet to find the right balance toward sustaining economic growth and protecting
the environment. The discussion has shifted from one of mutual exclusivity in in-
vestment to how we manage the future of the river for all uses without jeopardizing
the uses of future generations.
The following is clear and irrefutable:
First, this waterway system is critical to the future competitiveness of the Mid-
west agricultural economy. Without efficient waterway transportation, Midwest
grain exports will be lost at considerable expense to producers and the national
treasury;
Second, with continued and increased congestion costs on the waterway, shippers
will have to find alternatives to ship their goods or lose sales. Every modal shift
study concludes considerable economic, environmental and social benefits to keeping
freight on the waterway. Creating higher cost structures on the water through in-
vestment inaction will lead to lost economic activity, increased air emissions, in-
creased fuel consumption, increased accidents and increased fatalities in our com-
munities.
Third, continuing to show indecisiveness in modernizing the waterway infrastruc-
ture in the Midwest will continue to embolden our global competitors to increase
placing virgin lands into production and work to capture the growing share of a
world food market that will double in the next 10 years. Our inactivity is ensuring
that the U.S. may not be in a position to capitalize on these new markets.
Fourth, the environmental benefits of the waterway system, including those ini-
tially created with the construction of the lock and dam system, are declining. With-
out a high priority commitment to redressing that decline, we will continue to lose
islands, important backwaters, and other ecosystem elements critical to this rec-
reational Mecca and national flyway.
STRONG BASIN SUPPORT
Equally clear and irrefutable are the thousands of private citizens who have ex-
pressed their support for modernization of the lock system over the last 10 years,
either through direct communications to Congress, at Corps of Engineers-sponsored
public meetings and information sessions and most recently through statewide-elect-
ed officials.
The MARC 2000 coalition includes a multitude of industries, individuals, labor
groups, trade associations and community economic development groups. These con-
stituent groups know that as a region, over 151 million tons of commodities moved
on the 2,000 navigable miles of the Upper Mississippi, Illinois, and Missouri River
System in 1999. The combined value of these commodities totaled approximately
$24 billion. For the same year, 92.5 billion tons of commodities were shipped out
of our region 23rds of which consisted of corn, soybeans, wheat and other grains.
Louisiana receives 54 million tons of this grain for export to world markets, while
3 million tons went to processing facilities on the Tennessee River.
Our regions docks received more than 28 million tons from outside the system,
most of which were fertilizers and other chemicals. Another 30 million tons moved
within the basin in 1999, more than half of which consisted of gravel, sand, and
other aggregates.
125
A 39 percent majority of the shipments out of our region consisted of grain, but
many other commodities travel our river system. The Corps of Engineers figures re-
veal impressive statistics for total traffic in 1999 on the UMRS: almost 28 million
tons of coal ($1.1 B), over 10 million tons of petroleum ($1.6 B) 27 million tons of
aggregates ($943 million) over 59 million tons of grain ($8.7 B) over 9 million tons
of chemicals ($4.3 B) over 3 million tons of ores and minerals ($453million) over 6
million tons of iron and steel ($4.2 B) and over 8 million tons of other products ($2.3
B) moved on our waterways in 1999.
On a state level, shipments to and from Illinois totaled 92.3 million tons, worth
over $15 B. Shipments to and from Missouri totaled 46.1 million tons, worth over
$3.8 B. Shipments to and from Minnesota totaled over 20.2 million tons, worth over
$3.3 B. Shipments to and from Iowa totaled 18.4 million tons, worth over $2.7 B.
Shipments to and from Wisconsin totaled over 4.5 million tons, worth over $340 mil-
lion. These shipments of goods connected our five states with 17 other states in the
Nation (TX, OK, KS, NE, MI, IN, OH, KY, WV, PA, AR, MS, AL, TN, LA, FL and
GA), not to mention world markets. Copies of our state profiles can be accessed on
our web site at www.marc2000.org.
The importance of the waterway to this region has not been lost on witnesses over
the years. Our stakeholder groups have spent the last 10 years waiting for the Fed-
eral study process to produce an assessment of the navigation and environmental
needs. While the restructured study may achieve that goal, the economic and envi-
ronmental imperatives dictate action necessary this year to launch a lock mod-
ernization and enhanced restoration initiative.
Last year, the State of Minnesota started a process that has mushroomed in the
basin. Acting on its own initiative and encouraged by Rep. Jim Oberstar, the state
legislature passed House Resolution 208 and Senate Resolution 551 overwhelmingly,
expressing support for lock modernization and environmental restoration. Minnesota
rejected suggestions that they could not offer direction just because the Corps study
was not completed. Minnesota legislators recognized the economic and environ-
mental value of moving bulk commodities on the inland systemas most Americans
do when offered the choiceand chose to forge ahead with their expression of sup-
port.
This year, the Iowa, Missouri, Illinois and Wisconsin legislatures went a step fur-
ther, passing their own resolutions recognizing that:
Efficient operations of the inland system is critical to their economy and envi-
ronment;
Modern 1200-foot locks have a proven track record of alleviating congestion on
the inland waterway system; and among other things,
Its time to get on with this program and authorize funding to construct 1200-
foot locks.
Mr. Chairman, I would ask that copies of Minnesota House Resolution 208, Illi-
nois Joint Resolution 54, Iowa House Concurrent resolution 109 and Senate Concur-
rent Resolution 104, Missouri Senate Concurrent Resolution 44 and House Concur-
rent Resolution 11, and Wisconsin Assembly Resolution 56 be included in the record
with my testimony. These resolutions passed with broad bi-partisan support and
call on Congress to authorize and fund the construction of 1200-foot locks on the
Upper Mississippi and Illinois Rivers.
Testimonies at the most recent round of public meetings made it clear that the
labor community joins our industrial, agricultural, and economic development com-
munities in expressing strong support for the authorization and construction of new
locks on our inland waterway system. These projects provide a double investment
to the economic security of our region and country. First, good family wage jobs in
our Nation are supported by the efficient functioning of our transportation system
and the construction of modern locks. Second, infrastructure renewal has a proven
record of stimulating additional economic activity and more jobs. Historically, navi-
gation water project investments have returned to the national economy benefits
many times over the original dollar investment.
SMALL SCALE OPTIONS
Smaller scale investments are certainly part of the studys area of concentration.
Industry representatives have spent countless hours with engineering contractors
and the Corps of Engineers reviewing over 100 different proposals. It appears we
are revisiting some of the same alternatives, such as industry self-help and now
scheduling.
The theoretical underpinnings of scheduling promise to reduce lock congestion, re-
duce barge rates to shippers, improve equipment utilization for barge operators and
reduce operating costs for barge operators. In reality, all it will likely accomplish
126
is another layer of bureaucracy and delay solving the problem with the most effi-
ciently recognized alternative, 1200-foot locks.
Lock delays and resulting high barge rates are symptoms of a seasonal river sys-
tem that primarily operates 9 months, and inadequate lock infrastructure incapable
of meeting shipper demand. Congestion is a function of the timing of market de-
mand with the ability to move carrying capacity to the areas of the system to meet
that demand.
Scheduling will not allow the industry to increase barge supply in the spring, will
not result in increased barge supply in the fall, will not reduce shipper rates in the
spring, nor in the fall. It might minimize some lock delay costs. But, in order to
reduce carrier operating costs, equipment that otherwise would be waiting in queues
must be productively and economically employed in alternative income producing
uses. On the Upper Mississippi River system, equipment either waits in queue or
waits at an alternate location until scheduled lockage time is allocated. Mr. Chair-
man, I would like to introduce into the record a report issued by the Inland Water-
way Users Board to the Chief of Engineers outlining these key reasons why sched-
uling is not the answer to our problems on the inland waterway system.
Finally, some have suggested that small-scale measures, though not the long-term
solution to address a 60 percent growth in traffic, might be a short-term solution.
Regrettably, this thinking is what got us behind the eight ball today. History has
proven that average annual growth is not how the real world works, but only how
models can operate to project future needs. The reality of surges in grain exports
means that if we build infrastructure solely to meet average annual growth, rather
than capturing peak movements, we will continue to lose growth opportunities.
ENVIRONMENTAL PRIORITIES
This Feasibility study has already spent over $26 million reviewing biological im-
pacts of increased traffic and the cumulative impacts of navigation on the Upper
Basin system. In addition, we have invested $76 million more creating a monitoring
system under the Environmental Management Program (EMP), which has proven
invaluable in providing us with better information about the environmental status
of the rivers ecology.
In addition, the Upper Mississippi River Conservation Committee has issued a
document entitled A River that Works and a Working River, chronicling the evo-
lution of the Mississippi River sustaining multiple uses, but one whose environ-
mental values provide a mixed report. Through the EMP, our region has also pro-
duced a Habitat Needs Assessment outlining initial ideas on activities to restore lost
habitat to the rivers ecosystem. These combined efforts have helped scope a range
of opportunities for an enhanced restoration effort in the Upper Mississippi River
Basin.
The solutions to site-specific navigation improvements are well documented.
Agreement on how best to achieve environmental sustainability is still very much
the focus of our collaborative effort. MARC 2000 would urge the Committee to give
careful consideration to evaluating WRDA 2002 proposals to address the following
concerns:
The Corps traditional approach and funding of Operation and Maintenance
needs to be re-evaluated to address both the navigation system and the ecosystem.
O&M costs have been increasing as the navigation infrastructure ages and the chal-
lenge of finding environmentally acceptable approaches increases pressure on a
budget item unable to meet current needs;
Setting aside the traditional approach of addressing environmental restoration
in the Upper Miss Basin primarily through mitigation by exploring means by which
the full range of actions required for future environmental sustainability can be im-
plemented;
Establishing a viable approach for funding environmental improvements. While
the Inland Waterway Trust Fund provides cost-sharing dollars for navigation im-
provements, there is considerable question on how to finance environmental restora-
tion efforts largely needed to balance the creation of a Federal locking river whose
benefits are enjoyed by multiple users.
CONCLUSION
Mr. Chairman, our Basin is prepared to work with Congress to find a reasonable
approach to lock modernization and environmental restoration. In addition to work-
ing as part of the collaborative process with the Corps of Engineers and other Fed-
eral agencies and the Governors representatives, we are engaged in dialogs with
leading environmental groups in the Basin. We sincerely seek a balanced approach
to the Basins needs.
127
Unfortunately, the lack of resource commitment to completing navigation projects
of national significance is sapping our Nation of vital economic benefits associated
with responsible water resource development.
Lock modernization on the Upper Miss and Illinois must begin this year with au-
thorization language and pre-construction and design work if we have any hope of
staying competitive in world grain trade. It will take at least 2 years or more for
the PED process to be completed prior to construction. We believe the Interim Re-
port will provide sufficient guidance for Committee action. In order for the benefits
of U.S. Trade, Agriculture and Transportation policy to be realized in our part of
the country, we must move rapidly to protect our Achilles heel: the aging, anti-
quated, trade-limiting inland waterway system.
Many different products are transported on our waterway system. However, I
would like to close with another agricultural example of why this investment deci-
sion should be acted on immediately. In the 1999/2000 farm production year, over
270 million bushels of soybeans and 1.214 Billion bushels of corn were loaded on
barges for export from the Upper Miss Basin. Those exports were valued at over
$4 Billion. According to USDA multipliers, these exports generated a gross economic
output of over $22 Billion, personal income of over $6 Billion and supported gross
employment of over 230,000. This activity would have generated $776 million to the
U.S. treasury, or almost 60 percent of the total cost of lock modernization on the
Upper Mississippi and Illinois Rivers.
By any other standards, this investment would be a given, especially when half
the cost of modernization is paid for out of the Inland Waterway Users Trust Fund,
which is currently running a surplus of over $400 million. Modernization helps re-
dress the extensive rehabilitation costs of old structures and reduces the backlog.
The economy wins with stronger farm economies, efficient transportation systems
and a reinforced jobs base. The environment wins with slower growth of alternative
modes that consume more fuel and emit more pollutants, such as hydrocarbons, car-
bon monoxide, and nitrogen oxides into the air. Societies win with sustained quality
of life, fewer accidents and transportation-related fatalities.
It is far more likely that export growth will surge prior to completion of new locks
than construction of new locks being built prior to the next wave of export growth.
The risk to the Nation is greater if we cant meet that surge of demand than if were
meeting it head on or waiting for it to develop as food experts predict it inevitably
will.
CORPS OF ENGINEERS STUDY PROCESS
Mr. Chairman, I would like to express a few words about the Corps Feasibility
study process.
The picture of the Corps painted by certain elements of the press along with the
glib commentaries of selected opponents to water resource development are very dif-
ferent from the Corps of Engineers we work with and, yes, argue with over technical
analyses and how best to achieve congressionally authorized purposes for projects
and programs throughout this Nation. The Corps is made up of a unique blend of
civilians and military personnel who serve their Nation well. This agency was re-
cently voted as one of the two best government agencies in value produced for tax-
payer dollar received.
The people in our basin worked side-by-side with Corps personnel in 1993, 1995,
and 1997 and most recently during the 2002 floods that have resulted in minimum
loss of life and in protection of the environment. Before the long-standing policies
and procedures of the Corps of Engineers are too quickly attacked, lets reflect on
the fact that were dealing with an organization that has an unprecedented record
of civil works and emergency response accomplishments. The last thing in the world
that we need is change which makes the Corps study process more costly, time-con-
suming and burdensome.
The Upper Miss study is an example of an extremely open participative process.
The public has been involved in this study at every step of the way. There have
been over 80 open technical meetings at each step of the way. There have been
over 41 public meetings between 19932000. Some might even argue this has been
too much public participation and has perpetuated the problem of paralysis by anal-
ysis.
This study is a compilation of countless other smaller studies that have been
scoped out, conducted collaboratively with resource managers and economists
throughout the basin, and then reviewed by expert elicitations and peer reviews.
The direction of the study has evolved over these years. Additional sub-studies have
been commissioned. I cant imagine how many PhDs this study has produced over
the last 10 years. There has never been any problem with the publics access to in-
128
formation. If anything, this open, collaborative process has miscued over one impor-
tant promise and congressional desireto be expeditious, deliberative and conclu-
sive within a 6-year timeframe.
We agree with the National Academy of Sciences (NAS) that certain expectations
placed on this study, such as 50-year projections, are unrealistic. In addition, we be-
lieve the process is overwhelmed because there is a crisis of clarity over what this
nations priorities should be. Any attempts to change technical assumptions without
clear policy agreement, at this time, would be premature and likely harm and con-
fuse the Corps ability to meet congressional objectives.
Many of the concerns articulated over project purposes, benefit cost analysis and
cost sharing are reflective of a lack of National consensus about water resource de-
velopment priorities. In our basin, the citizens overwhelmingly would prefer that
barge transportation move bulk commodities on the inland waterway system, rather
than further overburdening the highways and rails that move through our commu-
nities. The national benefits of the waterways have been recognized since the incep-
tion of our Nation, and need to be re-emphasized. Water resource projects built our
basin and now support an economic structure that competes in a global market-
place. Our investment in modernizing navigation lock infrastructure and improving
the ecosystem must begin in earnest if we are to continue to provide family wage
jobs in our basin.
Thank you for the opportunity to present MARC 2000s views on WRDA 2002 lock
modernization opportunities and the Corps of Engineers study process. I would be
pleased to answer any questions.
The critical importance of the Corps Civil Works programs to the Nation should
not be lost amidst the often legitimate criticism. More than half of the nations pop-
ulation lives within 50 miles of the shore. Our ports and harbors are the nations
interface with the global economy. Ports are connected by inland waterways and
other transportation access to every state. Ninety-five percent of international trade
by volume passes through U.S. ports. In 1996, U.S. Customs revenues totaled $15.6
billion. A recent report by the Federal Reserve Bank of Kansas City, The U.S. as
a Coastal Nation, observed: . . . the coastal concentration of U.S. economic activity
reflects a productivity effect of access to navigable water. In addition, the report
examined the significant historical and cultural importance, as well as quality of life
factors that draw people to live, work and recreate along the nations coasts and
beaches.
The coast provides a staging area for fishing fleets, seafood processing, and off-
shore oil and gas production, as well as supports critical habitats for spawning fish,
shellfish and threatened and endangered species. Any visit to the beach confirms
that they are the nations premier recreation areas. Their beauty and accessibility
provide a magnet not only for international visitors, but also provide readily acces-
sible recreation and respite for millions families from diverse urban and rural areas
that may not have other options. Travel and tourism is the nations largest industry
with more than 85 percent of industry revenues being generated in coastal areas.
Federal tax revenues from beach tourism activity has been estimated to generate
$14 billion in California alone. Most importantly, these same beaches provide pro-
tection of life and property as natural barriers to flooding, waves and storm surges.
A recent Corps of Engineers study of six coastal communities in North Carolina
showed that communities with shore protection projects suffered significantly less
from Hurricane Fran.
Arcane cost-benefit ratios and budgeting exercises obscure the full range of bene-
fitsthe economic stimulus, tax revenues, environmental protection, and life and
property protectionderived from our nations coastal infrastructure. For example,
we spend billions on constructing highways and transportation corridors to enable
people to get to coastal areas and the beach. Yet, to spend several million on ensur-
ing that the beach exists protecting the natural and economic resource which justi-
fies the transit project is characterized by some as extravagant. The entire national
budget for beach nourishment projectsapproximately $135 million in fiscal year
2002would be a virtual rounding error on most significant transportation projects.
I want to dispel several myths which too often distort the debate over shore pro-
tection projects.
Shore protection projects do not simply wash away into the sea. They absorb
wave energies that typically save millions of dollars in property damages. Although
the sand is lost temporarily from the beach, many times the majority of the sand
remains in the littoral system and is either returned to the beach or deposited on
downstream beaches.
Nourishment projects are typically less expensive in current dollars than struc-
tural solutions as much of the costs are deferred well into the future while struc-
tures must be paid for at the time of initial construction.
In addition, nourishment projects are preferable to hard structures which would
undermine the natural protective features of the shoreline and would be less envi-
ronmentally acceptable and adversely impact downdrift beaches.
Finally, the Federal investment is justified based on formulating a project for
hurricane/storm damage protection and not recreation. In addition, for Federal par-
ticipation, all shore protection projects must have a benefit / cost ratio of greater
than 1.0 and more than 50 percent of that justification must be based on storm
damage reduction benefits.
In addition to the clear national interest and economic return of investment in
the coastal water resource infrastructure, many Corps Civil Works projects have
historically had, and continue to have, adverse effects upon the proper functioning
of littoral system. Dams, channelization and improvements to navigation including
130
navigational dredging and jetties often disrupt the natural flow of sand and other
sediment material resulting in sediment starvation and erosion. While it is a Fed-
eral responsibility to mitigate damages resulting from these Civil Works projects,
current Corps policies only support mitigation of damages directly induced by the
project and do not give priority to a comprehensive solution to overall shore protec-
tion problems. While it is important to remedy past errors, it is even more impor-
tant to provide a framework for planning and implementing Corps projects that en-
courages not simply mitigation but the maximization of economic and environment
benefits.
PROBLEMS IDENTIFIED WITH THE CIVIL WORKS PROGRAM
There are significant opportunities for project savings by simplifying Corps project
reviews and allowing local sponsors, working with private sector partners, to take
the lead more often in planning and implementing water resource projects. How-
ever, given the Corps continued insistence in controlling the planning process and
the uncertainties in obtaining sufficient funding to reimburse project sponsors, there
is no incentive for the Corps to take advantages of the efficiencies that could be gen-
erated by implementing these changes.
There is a catch22, which is common among all Corps project types, that results
from the gap between construction authorizations under WRDA and annual congres-
sional appropriations for the Civil Works Program. With huge project backlog within
the Civil Works Program, the Corps has allocated funding among as many projects
as it can keep going. By allocating less funding per project to sustain a greater num-
ber of projects, the Corps has lengthened the completion times and costs for projects,
and consequently for local project sponsors. Timelier project completion is one of the
primary means of reducing costs within the Civil Works Program and reducing the
project backlog.
There are fundamental problems with the Civil Works Program which should be
addressed in the Water Resources Development Act of 2002.
1. The project by project approach to project planning and authorization does not
take into account how projects affect each other, including opportunities for achiev-
ing efficiencies among projects or limiting cross-project impacts.
2. It simply takes too long to complete a project. If greater local participation in
projects is sought, projects, particularly project studies, needs to be simplified and
streamlined.
3. The Corps Districts and Divisions are effectively discouraged from finding cre-
ative ways for the beneficial uses of dredged material. The so-called Federal stand-
ard, least-cost environmentally acceptable alternative requirement, favoring open
water disposal of clean dredged material, thwarts the long-term cost savings to the
Federal Government and resource benefits resulting from keeping sand within lit-
toral systems. The effect of the least-cost alternative policy is to miss opportunities
for environmental restoration and shift costs from the Corps budget to other Federal
accounts such as disaster assistance due to the lack of protection that would other-
wise have been available from sand starved beaches.
4. The full range of benefits resulting from projects, both economic and environ-
mental, are not being credited. For example, states with comprehensive planning in
place which limits development along the shore and bans sea walls have difficulty
meeting the benefit thresholds for renourishment assistance, thereby penalizing
states for good coastal planning. Without the availability of renourishment assist-
ance, the pressure to allow sea walls or other shore protection structures can be
overwhelming. The effect of hard structures is increased erosion as wave energy is
focused at the point of impact with the wall. With the loss of the beach, the associ-
ated recreational, economic and environmental benefits are also lost.
5. The increasing pressure to reduce spending is impairing the ability of the Corps
to fulfill its service functions to support state and local efforts. In addition to assist-
ance for project planning and construction, the Corps provides much needed services
to states and coastal communities, such as technical advice and data for flood plain
management, planning assistance for state constructed projects, and research for
improved understanding of coastal littoral systems and project designs.
WRDA 2002: AN OPPORTUNITY
WRDA 2002 presents the opportunity to improve the Army Corps of Engineers
Civil Works Program through requiring more comprehensive and strategic planning,
rational project selection, effective project design, and enhancement of the cost effec-
tiveness of Civil Works projects. Making these improvements will require institu-
tional and legal changes, as well as changes in the overall approach to managing
the nations coastal infrastructure.
131
There are lessons to be learned by passage of laws like the Estuary Habitat Res-
toration Partnership Act, which was championed by this Committee. That law not
only set out a clear national policy goal of restoring one million acres of estuarine
habitat, but also called for the Corps to take the lead in development of a multi-
agency national restoration strategy to guide selection of the Corps projects funded
under the Act and to serve as guidance other Federal, state and local investment
in estuarine restoration.
In changing the overall approach to managing coastal water resources infrastruc-
ture, we recommend that Congress incorporate the following basic premises:
Our management of coastal infrastructure needs to take a systems-based ap-
proach.The entry and movement of the sediment which forms our shoreline is a
dynamic system. Man has made many alterations to the system through the erec-
tion of dams, navigational dredging, jetties and groins. While man has altered the
system in many ways, we cannot stop it. We can work with the system or against
it. The difference is found mostly in long-term project effectiveness and overall costs.
Working within the littoral system, we need to develop a strategy for meeting re-
gional and state needs.We need to move away from taking a project by project ap-
proach to the coast and develop a framework that addresses crosscutting coastal
shoreline issues along with setting priorities and strategies for meeting our Nations
coastal infrastructure protection needs including targeted needs for specific inlet
and regional management plans.
CSO RECOMMENDATIONS
The Army Corps of Engineers, through its authorized projects, has contributed to
the nations prosperity, saved lives and improved living conditions for millions of
Americans. Many of these projects have also had serious negative environmental
consequences. In Florida alone, billions of dollars are being spent to correct damage
from Corps projects.
138
It is time to reform the role and activities of the Army Corps of Engineers and
strongly supports legislation such as S. 1987, S. 646, H.R. 1310 and H.R. 2353 to
accomplish reforms. We specifically urge the passage of legislation with the fol-
lowing elements:
New tests and rules for fiscal responsibility, public accountability and environ-
mentally sustainable projects.
Full mitigation of environmental damages incurred by project construction.
Increased public participation and input at the outset of every proposed project.
Deauthorization of those projects that are shown to be economically unjustified.
New rules to prevent the Corps from basing any of a projects benefits upon any
economic value resulting from the destruction of wetlands.
Requirements that the Corps to count the cost of destroying natural resources
when calculating the economic costs and benefits of projects
Independent peer review of large and controversial projects concurrent with the
Corps current project planning process.
Increased fiscal responsibility and public accountability of the Corp activities
and projects.
APALACHICOLA-CHATTAHOOCHEE-FLINT RIVER PROJECT
In addition to the specific reforms noted above, Audubon of Florida supports de-
authorization of the nine by 100 foot channel of the Apalachicola-Chattahoochee-
Flint River Project between the Gulf Intracoastal Waterway near Apalachicola, Flor-
ida to Jim Woodruff dam near Chattahoochee, Florida as supported by the Governor
and Cabinet of the State of Florida. The maintenance dredging of this section of the
Apalachicola River, which is little used for commercial navigation, has had enor-
mous negative environmental impacts. Remarkably, this river project accounts for
30 percent of the Inland Waterways operations and maintenance budget, although
the project only amounts to 3 percent of all navigation in the Inland Waterways.
Dredging of the Apalachicola-Chattahoochee-Flint River Project is both environ-
mentally and economically irresponsible. By ending the dredging of this waterway,
the Apalachicola River may repair itself and once more become home to abundant
fish and wildlife.
Congress should enact meaningful Corps reforms to help restore faith in an agen-
cy that has suffered a significant loss of credibility. However, Congress should also
act to authorized the three aforementioned Everglades projects and deauthorize the
harmful operation of the Apalachicola River. We ask Congress to direct the Corps
to manage ecosystems in an environmentally sustainable manner and to provide
equal consideration and resources to environmental restoration as to flood control
and navigation. Audubon of Florida will continue to support efforts to reform the
U.S. Army Corps of Engineers and we look forward to working with you to ensure
that the next WRDA contains comprehensive and much-needed reforms.
We greatly appreciate this opportunity to provide the Committee with our views
for WRDA.
Again, we thank the Committee for its long-standing support for Everglades res-
toration and urge your continued support for the restoration of Americas Ever-
glades. The Everglades is a model for future Corps environmental restoration
projects. The Comprehensive Everglades Restoration Plan (CERP) is an outstanding
example of how a reformed Corps would repair damage from previous water re-
source projects while functioning in a manner that is responsive, accountable, and
fiscally responsible.
Everglades restoration embodies Corps Reform. The Corps has set about to undo
the damage wrought by a half-century of civil works projects that diked and drained
the Everglades and each day divert up to 2 billion gallons of life-giving water away
from the Everglades and out to sea. In Everglades restoration, the Corps has dem-
onstrated public accountability by conducting extensive public outreach and remain-
ing extremely open and accessible throughout the process. In some ways the Corps
is already operating the largest restoration project ever attempted in human history
in the manner that the proposed reforms intend. Everglades restoration amounts to
Corps Reform in action, on-the-ground, righting the wrongs of the past by restoring
one of the worlds most unique and diverse ecosystems.Audubon strongly urges the
Committee to include in WRDA three vital Everglades restoration projects that are
scheduled for authorization by Congress this year and contain more than half of the
total land area of the Comprehensive Everglades Restoration Plan (CERP). These
projects will deliver enormous benefits to the Everglades natural system. Like other
parts of the Everglades ecosystem, these projects are largely an attempt to repair
previous damage by Federal and state projects. The partnership between America
and Florida on these projects will contribute significant improvements to the Ever-
glades and our nations natural resources.
The proposed 2002 Water Resources Development Act (WRDA) must include au-
thorization for the Water Preserve Areas (WPAs), the Indian River Lagoon (IRL),
and the Southern Golden Gates Estates (SGGE) Hydrologic Restoration Projects in
order to accomplish significant early restoration. These projects also provide the ear-
liest ecological and economic value for the investment that Floridas and Americas
taxpayers are making in this historic restoration effort.
The Indian River Lagoon Project will reverse the deterioration and restore a na-
tionally significant and unique system connecting Lake Okeechobee to one of the
most diverse estuaries in North America. The project restores, protects and utilizes
92,900 acres of water storage and water quality treatment areas. Restoring, clean-
ing up and enhancing the areas wetlands and waterways increases the extent of
natural storage and limits the dumping of harmful stormwater into Lake Okee-
chobee, the Indian River Lagoon and the St. Lucie Estuary. These water bodies will
benefit enormously by land acquisition and improvements for stormwater retention
and water storage and by changing the current projects drainage patterns.
The Southern Golden Gates Estates Hydrologic Restoration Project will restore to
its previous natural condition 113 square miles (72,320 acres) of Southwest Florida
that was ditched and drained for a sprawling development. Efforts to restore this
areas unique ecology of cypress, wet prairie, pine, hardwood hammock and swamp
have been underway for decades. The project is connected to the Florida Panther
National Wildlife Refuge, the Belle Meade State Conservation and Recreation Lands
141
Project Area, the Fakahatchee Strand State Preserve, and will restore flows to the
Ten Thousand Island Estuaries and Aquatic Preserve through sheetflow and
flowways rerouting approximately 185,000 acre-feet of water currently discharged as
point source to the Faka Union Bay. Immediate benefits for the booming adjacent
urban area include water supply through aquifer recharge and the prevention of
saltwater intrusion while maintaining current authorized levels of flood protection
for developed areas. The State of Florida has already acquired more than 90 percent
of the 60,000 acres needed for the project. The restoration benefits of this project
are critically needed and too long overdue.
The Water Preserve Areas (WPAs) Project, (including the Bird Drive Recharge Area
and the Southern Compartment of the Hillsboro Impoundment), an integral part of
the Everglades restoration plan, is located within Palm Beach, Broward, and Miami-
Dade Counties east of the Everglades and west of existing development, creating a
13,600 acre buffer area (Recommended Plan of the Draft WPA Feasibility Study).
The WPAs are designed to increase the spatial extent of wetlands acres, improve
habitat in the Everglades Protection Area, enhance the Loxahatchee National Wild-
life Refuge, as well as store water, and safeguard wellfields. WPAs provide a critical
source of water storage for restoration by reducing undesirable losses from the nat-
ural system through seepage and providing a means of capturing stormwater runoff
that was previously wasted to tide. Further, development continues to encroach on
the remaining natural areas adjacent to the Everglades. These remaining wetlands
serve a critical role in the restoration of the Everglades by maintaining wetland spa-
tial extent. The WPAs also provide a mechanism for increased aquifer recharge and
surface water storage capacity to enhance regional water supplies for the lower east
coast urban areas, thereby reducing demands on an already degraded natural sys-
tem.
These three projects demonstrate large-scale ecosystem restoration, while main-
taining or improving water supply and flood protection. The success of these projects
hinges on timely authorization. These projects require intensive and significant ac-
quisition of land under significant development pressure delay could result in fail-
ure. If authorized in 2002, these projects will result in significant ecosystem restora-
tion early in CERP implementation the kind of early success that will be essential
to maintaining the broad support CERP now enjoys from both the public and pri-
vate sectors.
Chairman Jeffords and Ranking Member Smith, thank you for the opportunity to
present our views to the Committee. We look forward to working with you and the
other members of the Committee to ensure that the next WRDA includes com-
prehensive Corps Reform along with vital Everglades restoration projects that are
a model for future Corps restoration projects.
During the past few years, increased scrutiny of U.S. Army Corps of Engineers
(Corps) projects has revealed a disturbing pattern of flawed economic and environ-
mental analyses, biased and insupportable decisionmaking, and failed mitigation.
These problems have been identified by the Army Inspector General, the National
Academy of Sciences, the General Accounting Office, the Environmental Protection
Agency, the U.S. Fish and Wildlife Service, the media, environmental and taxpayer
organizations, and citizen activists.
Projects based on flawed analyses damage the nations rivers and wetlands, wreak
havoc on recreation, tourism, and other businesses that rely on healthy rivers, and
squander agency resources and tax dollars. When tax dollars and Corps resources
are spent on planning, defending, or constructing such projects, the Corps has less
ability to carry out environmental protection and restoration projects, or more de-
serving flood control and navigation projects.
142
To ensure that the Corps provides true benefits to the Nation, and does not cause
unnecessary and entirely avoidable environmental harm, Congress should reform
the way the Corps plans and constructs water resources projects. Importantly, these
same reforms also will save taxpayer dollars.
American Rivers opposes the passage of another Water Resources, Development
Act without these reforms. More potentially wasteful and environmentally damaging
Corps activities should not be authorized without substantially changing the way
the Corps plans, evaluates, and constructs its civil works projects.
American Rivers strongly supports congressional proposals that would change the
way the Corps does business. We believe that reforms contained in S. 646 (Corps
of Engineers Reform Act of 2001), and S. 1987 (Corps of Engineers Modernization
and Improvement Act of 2002), H.R. 1310 (Corps of Engineers Reform Act of 2001),
and H.R. 2353 (Army Corps of Engineers Reform and Community Relations Im-
provement Act of 2001), are essential to bringing about this change. In this testi-
mony I would like to highlight three critical reforms: requiring independent peer re-
view of costly or controversial Corps projects; requiring full and concurrent mitiga-
tion, and prohibiting the Corps from claiming project benefits for draining wetlands
in cost-benefit ratios.
CORPS STUDIES MUST BE REVIEWED BY AN INDEPENDENT PANEL OF EXPERTS
Study after study has shown that the Corps economic and environmental anal-
yses cannot be trusted. Indeed, the Armys own Inspector General found that many
Corps employees have no confidence in the integrity of the Corps planning process.1
Unfortunately, the impacts of flawed analyses go far beyond issues of trust and in-
tegrity. All too often, they are used to justify the construction of projects that unnec-
essarily harm the environment, and that divert tax dollars away from serving the
real needs of the Nation.2
The transformation of the nations rivers brought about by Corps levees, dams
and dredging projects are among the leading reasons that North Americas fresh-
water species are disasppearing five times faster than land based species, and as
quickly as rainforest species.3 The widespread damage has led the National Re-
search Council to call for the establishment of a national goal to restore riparian
functions along Americas rivers. The National Research Council has concluded that
protecting and restoring riparian areas will have a major influence on achieving
the goals of the Clean Water Act, the Endangered Species Act, and flood damage
control programs.4
Despite an explicit environmental protection mission, and specific environmental
restoration programs and projects, the Corps traditional flood control and naviga-
tion projects do not appear to be doing any better for the environment. To the con-
trary, agency-wide biases, institutional barriers, and faulty analyses are all contrib-
uting to the continued degradation of the nations rivers and wetlands.
Two National Academy of Sciences panels and the Army Inspector General have
concluded that the Corps has an institutional bias for approving large and environ-
mentally damaging structural projects, and that its planning process lacks adequate
environmental safeguards.5 Less environmentally damaging, less costly, non-
structural measures that would result in the same or better outcomes are routinely
ignored or given short shrift.
The National Academy of Sciences, the Army Inspector General, the General Ac-
counting Office and numerous other independent reviews also have revealed funda-
Just last week, the General Accounting Office reported that the Corps had over-
estimated the benefits of the $311 million Delaware River Deepening Project by an
incredible 300 percent. The General Accounting Office concluded that the Corps
analysis of project benefits contained or was based on miscalculations, invalid as-
sumptions, and outdated information.6 The Corps said the project would produce
$40.1 million in annual benefits. The General Accounting Office found that the
project benefits could be no more than $13.3 million a year. Unable to explain its
own analysis, the Corps blamed $4.7 million of that discrepancy on, a computer
error.7 The Corps suspended work on this project in late April 2002 when the Gen-
eral Accounting Office advised the Corps of its preliminary findings.
In one of the Corps more notorious episodes, the Army Inspector General con-
cluded that the Corps had deceptively and intentionally manipulated data in an at-
tempt to justify a $1.2 billion expansion of locks on the Upper Mississippi River.8
In short, the Corps had cooked the books.
An independent economic analysis of the Corps proposal to construct the $181
million Yazoo Backwater pumping plant in Mississippi, clearly demonstrates that
the Corps overestimated just the agricultural benefits of that project by $144 mil-
lion.9 hat study also concludes that even if all the remaining benefit calculations
were correct, those benefits could not justify construction of the project.
The U.S. Environmental Protection Agency (EPA) working with the U.S. Geo-
logical Survey also demonstrated that the Corps had grossly underestimated the
wetland impacts of the Yazoo Pumps project. EPA has concluded that the Yazoo
Pumps will drain and damage more than 200,000 acres of ecologically significant
wetlands10 times more wetlands than are destroyed in an entire year by private
developers. The Corps claims that only 23,200 acres of wetlands will be affected.10
The U.S. Fish and Wildlife Service (the Service) also conducted an extensive
analysis of the Yazoo Pumps and concluded that the Corps was claiming environ-
mental benefits that were physically impossible to obtain. The Corps told that public
that this agricultural drainage project would benefit the environment through at-
tempts to purchase conservation easements on 62,500 acres of privately owned agri-
cultural land located below the 87-foot elevation and within the project area. The
Service documented, however, that in the project area, there are fewer than 9,100
acres of agricultural land in private ownership below 87 feet. In short, the Corps
claimed environmental and economic benefits for reforesting 53,400 acres of pri-
vately owned agricultural lands that do not exist.
The U.S. Fish and Wildlife Service also conducted a detailed investigation of the
methodology used by the Corps to evaluate the relative costs of purchasing flowage
easements for the $62 million Big Sunflower River dredging project. The Service
found that the Corps significantly overestimated the costs of utilizing nonstructural
alternatives to meet the objectives of the Big Sunflower project.11 The Corps failings
on this project continue. After EPA advised the Corps that it should prepare a sup-
plemental environmental impact statement to evaluate, in part, the human health
risks associated with dredging DDT and toxaphene contaminated sediments from
104 miles of the river bottom, the Corps issued an inadequate environmental assess-
ment that does not even acknowledge the existence of the toxaphene contamination,
let alone evaluate the impacts of dredging the toxaphene contaminated sediments.
A newspapers 6-month review of the economics of the $188 million Columbia
River channel deepening project revealed that the Corps had overestimated the
projects benefits by 140 percent. The Corps told the public that the project would
12 The Oregonian, Key parts of corps analysis dont hold water, March 3, 2002.
13 The Oregonian, Digging deeper in Columbia, March 10, 2002. The Corps noticed the new
study on March 19, 2002 (67 Fed. Reg. 1246).
14 Michael Grunwald, A Race to the Bottom, The Washington Post, September 12, 2000, at
A 15.
15 For example, the General Accounting Office is currently investigating the Corps analysis
of the $108 million Oregon Inlet Jetties project.
16 Editorial, Wet Elephant, The Washington Post, January 5, 1987, at A16.
17 Memorandum from Robert H. Griffin, Major General, U.S. Army, Director of Civil Works,
April 30, 2002.
18 The Corps already battered credibility took yet another hit when just a few days later it
released a corrected list under the project pause directive that deviated in significant ways
from the first list. The second list identifies only 164 projects as having been reviewed, clearing
80 to proceed (with the remainder already undergoing reevaluation due to previously identified
problems). Again only eight projects were said to require additional review as a result of the
review process. With no explanation, the Corps completely removed from the second list some
of the worst projects that were identified on the original list with the nomenclature review com-
plete, including the Grand Prairie Irrigation Demonstration Project in Arkansas, the Yazoo
Pumps Project in Mississippi, and the St. Johns Bayou Project in Missouri. In addition to being
costly, each of these projects is highly controversial and would destroy some of Americas most
valuable wetlands and aquatic habitat. Because the Corps has left the public completely in the
145
nouncement. A legitimate economic analysis for a Corps project requires the gath-
ering of data, selection and justification of models and assumptions, and careful re-
view and evaluation. Claims that the economic analyses for 118 projects can be
redone in just 17 days is simply not believable.
As the St. Louis Post-Dispatch so aptly editorialized when the Corps announced
its agency-wide project review:
Critics still worry, and rightly so, that the Corps may be trying to preempt true
reform by making a show of falling on its sword. Congress must see to it that
doesnt happen. For years the Corps has downplayed the costs of its projects to the
environment and the taxpayers and overstated their benefits to agriculture and the
barge industry.19
Congress should stop these abuses, and restore credibility to the Corps planning
and decisionmaking process.
American Rivers urges Congress to require independent peer review as set forth
in S. 1987 and S. 646. These provisions would require independent peer review for
projects whose total costs exceed $25 million, or for projects that. are deemed to be
controversial. These provisions ensure that the review is truly independent by plac-
ing the review office outside of the Corps, and that each review is carried out by
a panel that represents a balance of expertise in the areas of biology, economics,
and engineering.
Importantly, independent review will not delay planning for projects of concern
unless, of course the review finds fundamental flaws or dishonesty, in which case
delays would be inevitable but would serve the public interest. The Corps review
of costly or controversial projects typically takes approximately 1 year from the date
the draft report is released for public comment until a final report is issued, and
can take much longer. For example:
A draft reformulation report/environmental impact statement for the Yazoo
Pumps project discussed in this testimony was issued in September 2000, and 21
months later a final study still has not been released.
A draft feasibility report for the $311 million Delaware River Deepening Project
discussed above, was issued in June 1990, and the final feasibility report was not
issued until February 1992, 20 months later.20
A draft feasibility report/environmental impact statement for the $390 million
Lower Snake River Juvenile Salmon Migration project was issued in December
1999, and a final study was not issued until February 2002, 26 months-later.21
The 180-day independent review period required under S. 1987 and S. 646 could
easily have been carried out during these time periods.
Independent review also will decrease wasteful spending by ensuring that analyt-
ical flaws are brought to light before a project is built or becomes entangled in pro-
tracted litigation. Independent review will ensure that the Corps plans, rec-
ommends, designs, and builds projects that are based on sound science and econom-
ics. Most importantly, independent review will help ensure that environ-
mental.impacts have been adequately addressed, that less environmentally dam-
aging alternatives have been fully evaluated, and that Corps projects are economi-
cally justified.
Independent peer review is a common sense solution, and a practice used rou-
tinely in the scientific community. It is a practice that is sorely needed to help re-
store the Corps battered credibility.
CONGRESS SHOULD REQUIRE THE CORPS TO FULLY MITIGATE FOR THE HARM CAUSED
BY CORPS PROJECTS AND TO IMPLEMENT THAT MITIGATION IN A TIMELY MANNER
The Corps has abjectly failed to plan and implement ecologically successful miti-
gation for the significant damage caused to rivers and wetlands by Corps projects.
The Corps generally does not even attempt to mitigate hydrologic impacts to rivers
and streams, and undertakes only limited efforts to mitigate for wetland impacts.
There are many reasons for the Corps lack of mitigation success. The Corps civil
works mitigation is not properly planned, and typically calls for the creation of non-
wetland habitat to replace wetlands harmed by Corps projects. It does not reflect
dark on the process used in its review, we can only conclude that although the Corps originally
announced to Congress and the public that these projects had in fact been reviewed, the reviews
never occurred.
19 Editorial, Backpaddling, St. Louis Post-Dispatch, May 6, 2002.
20 Environmental threats from this project include severely damage to the banks of the Dela-
ware River, its wildlife, and nearby drinking water wells and aquifers.
21 This study was prompted by National Marine Fisheries Service and U.S. Fish and Wildlife
Service Biological Opinions on the impacts of operation of the navigation dams on four federally
endangered salmon stocks.
146
contemporary science and the importance of natural systems, often is riot imple-
mented in anything remotely approaching a timely manner, and is not effectively
tracked or monitored.
In reality, the Corps imposes far more stringent mitigation requirements on pri-
vate developers than it imposes on itself And, unfortunately, even the more strin-
gent mitigation requirements under the Corps regulatory program are alarmingly
far from achieving the goal of no net loss of wetlands.22 The actual amount of wet-
land impacts offset is only about 20 percent, meaning that the section 404 permit-
ting program has been fostering an 80 percent net loss of wetlands.23
Poor Planning.When selecting a preferred project alternative for its own civil
works projects, the Corps frequently provides little more than a vague indication of
its intent to mitigate. Typically the Corps does not provide: (1) a detailed mitigation
plan that identifies specific mitigation sites; (2) evidence that proposed mitigation
will produce the promised ecological benefits; (3) evidence that the proposed mitiga-
tion can actually be implemented; (4) evidence that the proposed mitigation is eco-
logically appropriate with respect to mitigating project impacts; or (5) a detailed
monitoring plan to ensure that the mitigation produces the promised ecological re-
sults.
The lack of detailed planning leads to a variety of problems. In the case of the
Yazoo Pumps; project discussed earlier in this testimony, lack of a detailed plan led
the Corps to claim that it could implement mitigation on lands that do not exist.
Specifically, the Corps said it could purchase conservation easements on 62,500
acres of private agricultural land within the affected area to offset the projects im-
pacts, when only 9,100 acres of privately owned agricultural land exist in that area.
Where the details of mitigation are not carefully planned, the Corps has no ability
to effectively evaluate the potential for mitigation success. This leads to
unsupportable claimsmade routinely by the Corpsthat a project should proceed
because mitigation will alleviate the harms caused.
Just as importantly, where the details of a mitigation plan are not established,
the costs of mitigation also cannot be realistically established. Since the costs of
mitigation are a project cost, failure to havea detailed and realistic mitigation
plan can seriously skew the cost benefit analysis.
Out-of-Kind MitigationThe mitigation that is proposed by the Corps frequently
ignores its interim goal of no overall net loss of the Nations remaining wetlands
base, as defined by acreage and function that was established by the Water Re-
sources Development Act of 1990.24
The Corps ignores the functional replacement element of this goal by frequently
replacing rare aquatic and riparian habitat with more common terrestrial habitat.
This out-of-kind mitigation by definition cannot replace lost wetland functions. The
Corps has completely abandoned the mandate to ensure no net loss of wetland
acres by consistently requiring far less than one-to-one wetland replacement.
For example, though the Corps plan to dredge over 100 miles of the Big Sun-
flower River will adversely impact 3,631 acres of wetlands, the Corps has limited
its mitigation to planting tree seedlings on 1,912 acres of frequently flooded agricul-
tural lands.25 This is not wetlands mitigation and will not replace the wetland func-
tions that will be lost through the project. Even if this mitigation somehow miracu-
lously created 1,912 acres of wetlands, it would still result in a 47 percent loss of
wetlands.
Not Implemented In A Timely Manner.Though existing law requires the Corps
to implement mitigation prior to or concurrently with, project construction; the
Corps has exploited the somewhat vague definition of concurrent to allow decades-
long delays in the implementation of mitigation. For example, the Corps currently
is scheduled to complete the enlargement of the Mississippi River Mainline levees
in the year 2030. That project consists of hundreds of individual and completely sep-
arable construction projects (for example, some sections of levees will be raised in
Louisiana while others will be raised in northern Mississippi) each with separate
mitigation requirements. The Corps nevertheless asserts that all mitigation will
22 National Research Council, Compensating for Wetland Losses Under the Clean Water Act
2001, at 2.
23 R. Eugene Turner, et al., Count It by Acre or FunctionMitigation Adds Up to Net Loss
of Wetlands, National Wetlands Newsletter, November-December 2001.
24 33 U.S.C. 2317(a)(1).
25 Final Project Report and Supplement No. 2 to the Final Environmental Impact Statement,
Flood Control, Mississippi River and Tributaries, Yazoo Basin, Mississippi, Big Sunflower River
Maintenance Project, Volume 1, Project Report, Supplemental Environmental Impact Statement,
and Appendices A-C, July 1996, at Appendix B, U.S. Fish & Wildlife Coordination Act Report
at i. At least 443 acres of bottomland hardwood wetlands and 476 acres of farmed wetlands will
be destroyed, and an additional 2,712 acres of wetlands will be severely impacted. Id.
147
have occurred concurrently as long as it is completed when the very last portion
of levee is raised in 2030 or later, even though construction of most of the separate
components will have been completed decades earlier.
This can lead to wholesale failures in the Corps mitigation program. For example,
by its own admission, the Vicksburg District of the Corps has a mitigation backlog
of almost 30,000 acres that it is legally obligated to implement.26 Despite the fact
that much of this mitigation was to have been undertaken years ago, the Vicksburg
District has not even purchased the vast majority of the land needed to start these
efforts.
Not Tracked or Monitored.As importantly, the Corps makes little effort to track
or evaluate the ecological success of mitigation efforts for either its own civil works
program or the Clean Water Act Section 404 program. For example, it took the
Corps almost 5 months to identify the promised mitigationand the mitigation
backlogin just one of the Corps 38 domestic Districts. And despite a specific re-
quest, the Corps did not provide any data evaluating whether any mitigation that
was attempted in that District has been ecologically successful. The Corps did not
provide that information because it had none to providea response to a later Free-
dom of Information Act request revealed that no ecological monitoring had been car-
ried out.27
In another telling admission, the Corps has advised the General Accounting Office
that the Corps bases its evaluation of whether or not mitigation is complete on the
amount of money spent. According to the Corps, the point at which 50 percent of
mitigation is completed occurs in the fiscal year in which the Corps district offices
cumulative expenditures toward the mitigation plan total at least 50 percent. of the
estimated cost of these activities.28 Mitigation monitoring and ecological success ap-
parently do not come into play in the Corps determination.
The Corps also does not track implementation of mitigation required under the
Clean Water Act Section 404 regulatory program. The General Accounting Office
has concluded that many Corps districts have touted the success of wetlands mitiga-
tion required under the Corps regulatory program without having any data to sup-
port those claims and without having bothered to assess whether the mitigation ef-
forts have been ecologically successful.29 The National Academy of Sciences also has
found that the Corps is making unsupportable decisions in its Clean Water Act Sec-
tion 404 regulatory program, which are causing profound impacts on the nations
rivers, streams, and wetlands.30
Even though the Corps apparently has little idea of whether promised mitigation
is successful or even attempted, it continues to build projects and to issue Section
404 permits based on the premise that mitigation will correct all environmental
damage. To make sound decisions, both the Corps and the public must have ready
access to mitigation data.
Congress also recognized that it needed ready access to mitigation information in
the Water Resources Development Act of 1986. That Act requires the Corps to in-
clude a specific fish and wildlife mitigation plan for any project proposal submitted
to Congress for authorization after 1986, or provide Congress with a determination
that the project will have negligible adverse impacts on fish and wildlife.31 However,
the Corps often does not provide accurate mitigation information to Congress, pre-
venting Congress from honestly assessing a. projects impacts prior to authorization.
Between 1986 and 2001, the Corps advised Congress that only 47 of 150 projects
required. a fish and wildlife mitigation plan.32 It strains credulity to suggest that
26 As of June 24, 1999, the Corps Vicksburg District was legally obligated to implement com-
pensatory mitigation on well over 25,000 acres that had yet to be purchased. That backlog did
not include the mitigation required in the Vicksburg District for the Mississippi River Mainline
Levee Project that includes the purchase and reforestation of an additional 5,200 acres of fre-
quently flooded agricultural lands. Letter and Attachments from Joseph W. Westphal, Assistant
Secretary of the Army (Civil Works) to Melissa A. Samet, Attorney, Earthjustice Legal Defense
Fund (August 9, 1999).
27 Response to September 25, 2000 Freedom of Information Act Request submitted by Melissa
Samet, Earthjustice, requesting information and data on the Corps wetlands monitoring pro-
gram in the Vicksburg District.
28 General Accounting Office, U.S. Army Corps of Engineers Scientific Panels Assessment of
Fish and Wildlife Mitigation Guidance, GAO02574, May 2002 at 4 n.2.
29 General Accounting Office, Wetlands Protection, Assessments Needed to Determine Effective-
ness of In-Lieu-Fee Mitigation, 2001, at 3.
30 National Research Council, Compensating for Wetland Losses Under the Clean Water Act
at 6, 2001, (Conclusion 4: Support for regulatory decisionmaking is inadequate); at 6.
31 33 U.S.C. 2283(d).
32 General Accounting Office, U.S. Army Corps of Engineers Scientific Panels Assessment of
Fish and Wildlife Mitigation Guidance, GAO02574, May 2002 at 4. The Corps provided the
Continued
148
only 31 percent of Corps projects require mitigation. This is particularly true when
one examines some of the projects that did not include mitigation plans when pro-
posed to Congress.33
For example, the Corps did not present a fish and wildlife mitigation plan to Con-
gress for the American River Watershed Flood Plain Protection Project, which the
Environmental Protection Agency has determined will have adverse environmental
impacts that are of sufficient magnitude that EPA believes the proposed action must
riot proceed as proposed.34 The Corps also did not provide fish and wildlife mitiga-
tion plans to Congress for the Boston Harbor Navigation Improvements and Berth
Dredging Project or the John T. Myers and Greenup Lock Improvements, each of
which the Environmental Protection Agency has said will have significant environ-
mental impacts that should be avoided in order to adequately protect the environ-
ment.35
The Corps should be required to mitigate for all unavoidable harm caused by its
projects and to carry out its mitigation in a timely and ecologically sound manner.
American Rivers urges Congress to pass into law each of the mitigation provisions
in S. 646, which we believe would significantly improve the Corps mitigation suc-
cess rate.
Among other things, S. 646 would require the Corps to mitigate fully for the ad-
verse environmental harm caused by its projects, including adverse hydrologic im-
pacts. It would require the Corps toat an absolute minimumimplement one acre
of mitigation for each acre of habitat harmed by a Corps project, and to ensure that
each mitigation plan reflects contemporary science and the importance of natural
systems. It would require the Corps to develop a specific mitigation plan flat in-
cludes monitoring for each project.
S. 646 also would require the Secretary of the Army to determine that the mitiga-
tion plan has the greatest possibility of cost-effectively and successfully mitigating
the adverse impacts of a project, before the Corps can proceed with that project.
To ensure timely implementation of mitigation, S. 646 also clarifies the definition
of concurrent mitigation to require that 50 percent of mitigation be completed be-
fore project construction begins.
S. 646 further requires the Corps to set up a publicly accessible system to track
promised and implemented mitigation, both for the Corps civil works program and
its regulatory program.
Each of these mitigation reforms is critical for ensuring the protection and res-
toration of the nations rivers, streams, and wetlands. Without these provisions, the
Corps will have no hope of meeting its statutorily established goal of ensuring no
net loss of wetlands as defined by acreage and function. And the Nation will con-
tinue to lose key resources necessary to protect water quality, provide habitat for
fish and wildlife, and provide protection from flooding.
CONGRESS SHOULD ENSURE THAT THE CORPS COST BENEFIT CRITERIA COMPLY WITH
FEDERAL LAW AND LONGSTANDING FEDERAL POLICY
The Corps currently can, and does, claim project benefits for draining wetlands
an activity that undeniably harms the environment and that requires mitigation.
For example, over 83 percent of the benefits of the Yazoo Pumps project are derived
from draining wetlands to promote increased agricultural production on marginal
lands that have always flooded. As I discussed earlier, EPA has concluded that the
Yazoo Pumps will drain and damage more than 200,000 acres of ecologically signifi-
cant wetlands. Approximately 150,000 of those wetland acres are located within the
2-year floodplain.
Claiming project benefits from the draining of wetlands is directly at odds with
the mandates of the Clean Water Act Section 404(b)(1) Guidelines (which apply to
Corps projects), the implementing regulations of the National Environmental Policy
Act, and long-standing national wetlands protection policies, national farm policies,
and national floodplain policies. It also is wholly inconsistent with the Corps envi-
mitigation planning information for 150 projects that it says were authorized between the Water
Resources Development Act of 1986 and September 30, 2001 that received construction appro-
priations. Id.
33 Information supporting the GAOs May 2002 Study entitled U.S. Army Corps of Engineers
Scientific Panels Assessment of Fish and Wildlife Mitigation Guidance. The list of projects was
provided to American Rivers by the U.S. Army Corps of Engineers upon request.
34 The Environmental Protection Agency gave the Corps environmental impact statement for
this project a rating of EU2. The criteria for that rating, which includes the quote above, is de-
scribed at http://www.epa.gov/compliance/nepa/comments/ratings.html.
35 The Environmental Protection Agency gave the Corps environmental impact statements for
each of these projects a rating of E02. The criteria for that rating, which includes the quote
above, is described at http://www.epa.gov/compliance/nepa/comments/ratings.html.
149
ronmental protection mission and with the Corps statutorily mandated goal of no
net loss of the nations wetlands. Specifically:
This practice is at odds with the implementing regulations of the National Envi-
ronmental Policy Act, and the Section 404(b)(1) Guidelines, both of which require
mitigation for wetland impacts that cannot be avoided. 40 C.F.R. 1508.20; 40
C.F.R. 230.10(d).
This practice is at odds with Executive Order 11990, which since 1977 has di-
rected every Federal agency to provide leadership and take action to minimize the
destruction, loss, or degradation of wetlands, and to preserve and enhance the nat-
ural and beneficial values in carrying; out agency responsibilities. Indeed, this Exec-
utive Order specifically compels the Corps to avoid draining, dredging, and filling
wetlands.36 The courts have held that Executive Order 11990 is judicially enforce-
able and should be given the full force and effect of law.37
This practice is at odds with national farm policy and the Federal Governments
significant efforts to take excess and environmentally sensitive croplands out of pro-
duction, and to remove incentives for draining wetlands to enhance crop produc-
tion.38
For floodplain wetlands, this practice is at odds with Executive Order 11988,
which since 1977 has directed all Federal agencies to take action to restore and
preserve the natural and beneficial values served by floodplains in carrying out
their water resources activities. This Executive Order was passed to help reduce
flood damages by protecting the natural values of floodplains and reducing unwise
land use practices in the nations floodplains.
This practice is at odds with the long-standing bipartisan national policy of no net
loss of wetlands which was established under the first Bush Administration, and
which was codified as to the Corps in the Water Resources Development Act of
1990.
Congress should put a stop to this outdated practice. American Rivers strongly
urges Congress to prohibit the Corps from claiming project benefits for increased
value of privately owned property and services, or increases in the quantity of pri-
vately owned property, derived from draining wetlands, as provided in S. 1987 and
S. 646.
CONCLUSION
American Rivers respectfully urges Congress to act quickly and decisively to re-
store credibility to the Corps civil works program. The absence of meaningful re-
view, the absence; of clear requirements to ensure full and ecologically sound miti-
gation, and outdated methods of predicting project benefits, have created a climate
where abuse has flourished. Without these long overdue reforms, these abuses will
continue and the environment and the taxpayers will continue to suffer. We urge
you not to pass another Water Resources Development Act unless these reforms are
included. American Rivers would like to work with the Committee to make these
reforms a reality.
4321. As importantly, Executive Order 11990 provides that each Federal agency: shall avoid
undertaking or providing assistance for new construction located in wetlands unless the head
of the agency finds (1) that there is no practicable alternative to such construction, and (2) that
the proposed action includes all practicable measures to minimize-harm to wetlands which may
result from such use. Id. at Section 2(a). The term new construction is defined to include
draining, dredging, channelizing, filling, diking, impounding and related and any structures or
facilities begun or authorized after the effective date of the Executive Order. Id. at Section 7(b).
37 City of Carmel By-the-Sea v. United States Dept of Transportation, 123 F.3d 1142, 1166 (9th
Cir. 1997); City of Waltham v. United States Postal Service, 786 F. Supp. 105, 131 (D. Mass.
1992). The courts also have found that this Executive Order imposes duties on Federal agencies
beyond those of NEPA. It requires a specific finding that no practicable alternative to the pro-
posed action exists. City of Carmel, 123 F.3d at 1167.
38 The Food Security Act of 1985 and the Erodible Land and Wetland Conservation Program,
16 U.S.C. 3801 et seq., encourage the removal of fragile lands from production and provide var-
ious opportunities for wetland habitat protection and restoration. A special conservation provi-
sion in this Act, known as Swampbuster, removes incentives for draining wetlands by elimi-
nating most agricultural subsidies to farmers who drain wetlands to enhance crop production,
or who produce commodities on wetlands converted after 1985.
150
STATEMENT OF THE NATIONAL ASSOCIATION OF FLOOD AND STORMWATER
MANAGEMENT AGENCIES
The National Association of Flood and Stormwater Management Agencies is very
pleased to have the opportunity to submit this testimony to the committee for con-
sideration on an issue of importance to the NAFSMA membership.
BACKGROUND ON NAFSMA
NAFSMA represents more than 100 local and state flood control and stormwater
management agencies serving a total of more than 76 million citizens and has a
strong interest in this important legislation.
NAFSMAs members are public agencies whose function is the protection of lives,
property and economic activity from the adverse impacts of storm and flood waters.
NAFSMA member activities are also focused on the improvement of the health and
quality of our nations waters.
The mission of the association is to advocate public policy, encourage technologies
and conduct education programs to facilitate and enhance the achievement of the
public service functions of its members. Many of NAFSMAs members are currently
involved in ongoing water resources projects with the Corps of Engineers, including
flood management and environmental restoration projects.
Since the organization was formed in 1979, NAFSMA has worked closely with the
U.S. Army Corps of Engineers and other Federal agencies, including the U.S. Envi-
ronmental Protection Agency and the Federal Emergency Management Agency in
numerous efforts. Our members have supported the concept of cost sharing as first
authorized in WRDA 86 and a group of our members worked closely with the Corps
to redesign what is now the Project Cooperation Agreement in the early 1990s.
We have supported new initiatives such as the Corps Challenge 21 riverine res-
toration and other environmental restorations initiatives as a necessary complement
and vital tool to add to the Corps ability to meet environmental challenges in their
traditional water resource projects.
NAFSMA very much appreciates the Committees commitment to hold hearings
to keep WRDA on its biennial renewal process. NAFSMA members are on the front
line protecting their communities from loss of life and property and therefore the
organization is keenly aware that flood management measures are a necessary in-
vestment required to prevent loss of life and damages to peoples homes and busi-
nesses. Flood management is a wise investment that will pay for itself by preserving
life and property and reducing the probability of repeatedly asking the Federal Gov-
ernment for disaster assistance.
NAFSMA RELATIONSHIP WITH THE CORPS
Over the past twenty years of NAFSMAs existence, our relationship and the role
of our agencies and the Corps of Engineers has changed. Our members are dedi-
cated to looking at both non-structural and structural approaches to flood manage-
ment. Environmental restoration is a key focus of our member agency missions as
well as the Corps. Urban stream restoration and other similar projects have been
undertaken and have been quite successful.
We are proud of the commitment of our member agencies to protect and restore
the environment. The Corps is an important partner to state and local agencies in
carrying out these environmental restoration initiatives.
NAFSMA firmly believes that the Corps has the technical capabilities and exper-
tise to carry out its stated missions. The Corps must have the funding resources to
maximize the public benefits that can be obtained from the Corps capabilities and
expertise.
The Corps has strengthened and improved its partnership with the non-Federal
sponsors over recent years. This partnership can continue to be strengthened and
improved with some new policy initiatives. Changes in the Water Resources Devel-
opment Act this year will help our member agencies better carry out their evolving
missions and responsibilities. I would like to describe some of those issues for you
today.
POLICY INITIATIVES FOR WRDA 2002
NAFSMA supports the current Federal project cost sharing for flood control activi-
ties of 65 percent Federal/35 percent non-Federal. We also support the development
of incentives to implement floodplain management measures above the minimum
measures, allowing the project cost sharing to be modified upwards to 75 percent
Federal/25 percent local. Decisions as to whether local communities would qualify
for improved cost sharing could be based on the communitys rating under the Na-
tional Flood Insurance Program Community Rating System or submission of a flood-
plain management plan that substantially exceeds minimum requirements.
Such an approach has already been passed by the California state legislature and
is currently implemented at the State level for State participation with local agen-
cies in Corps-partnered projects.
We know that in the past, a number of interests have proposed that this cost
sharing be reduced to a 50/50 Federal/non-Federal approach. NAFSMA is strongly
opposed to such a move. This type of change would keep critical public safety
projects from moving forward.
CREDIT FOR IN-KIND SERVICES
Within the Water Resources Development Act, NAFSMA urges the Committee to
include language that would encourage multi-objective efforts, to include flood man-
agement, river restoration, recreation, environmental preservation and enhance-
ments. Such an approach would produce long-lasting multiple benefit projects for
communities throughout the nation.
Although we can currently do combined flood damage reduction and environ-
mental restoration, with some difficulty, under the Corps General Investigation Pro-
gram, multiple objective projects cannot be done through the more efficient Con-
tinuing Authorities Program for small projects, such as flood control projects (Sec-
tion 205), environmental restoration (Section 1135.) or, aquatic restoration (Section
206).
NAFSMA recommends combining all the continuing authority programs into a
single program that allows inclusion of any of the benefits presently provided for
in the individual continuing authority programs, or establishing anew continuing
authority program for multi-objective projects. We are learning that single purpose
projects do not meet the demands of todays society and are less efficient to imple-
ment.
REVISION OF CURRENT NED POLICIES
NAFSMA recommends the review and revision of current National Economic De-
velopment (NED) policies to encourage more environmentally sensitive, multi-objec-
tive flood management projects.
NAFSMA supports the Corps movement in this direction through their develop-
ment and use of the National Ecosystem Restoration (NER) plan process for project
formulation of ecosystem restoration projects. NAFSMA encourages the melding of
NED and NER approaches to achieve multi-objective projects.
CONTINUED SUPPORT FOR SECTION 211 INITIATIVES
NAFSMA supports policies and programs, such as Section 211 of WRDA 1996,
that allow local implementation of Federal projects where advantages and effective-
ness can be demonstrated and provide for reimbursement.
MAXIMIZE THE BENEFIT OF THE USE OF FEDERAL FUNDS
NAFSMA is concerned about some of the approaches suggested for Corps reform.
NAFSMA encourages a process and funding mechanism to maximize the benefit of
the use of Federal funds for federally authorized projects. The following items ad-
dress this issue.
152
Independent Peer Review
NAFSMA opposes efforts to add external independent peer review to the approval
process for federally partnered flood control or environmental restoration projects.
Corps projects presently go through an extensive review process that includes re-
view and involvement by the U.S. Environmental Protection Agency, Fish and Wild-
life and others. While there are constituencies promoting such reviews under the
umbrella of cost savings and better use of Federal tax dollars, the addition of such
a review process would only serve to slow down the process for much-needed flood
management projects and increase the cost of such projects at both the non-Federal
and Federal levels.
A logical sequence of events is to consider this issue after a thorough review of
the congressionally requested National Academy of Sciences study on the feasibility
of independent review panel. The study is expected to be released in July.
We understand that independent review panels are being recommended because
the Corps feasibility study and project authorization process is believed by some not
to fulfill the programs intent. That being the situation, NAFSMA suggests that first
consideration be given to a review and correction of the existing feasibility and au-
thorization process before adding an additional process such as independent review.
NAFSMA would be supportive of language to encourage partnerships that are
formed early and amongst all parties, including the regulatory agencies, whose goal
is to seek participant consensus on the recommended flood management and water-
shed enhancement projects.
Benefit Cost Ratio
NAFSMA opposes increasing the current benefit cost ratio for water resources
projects subject to benefit cost analyses. The benefit cost ratio should not be the sole
criteria for project screening. Non-Federal sponsors and the Corps are moving to-
ward multi objective environmentally sensitive projects to better address public
needs and maximize the use of Federal funds. Increasing the benefit cost would
hinder that approach. We are also concerned that disadvantaged areas would be dis-
criminated against with this higher benefit cost ratio. Non-Federal sponsors need
to be involved in any effort to examine changes to the current benefit cost ratios.
NAFSMA supports review of all laws, regulations, policies, procedures, and guid-
ance to determine what changes are required to expedite implementation of flood
management and/or watershed enhancement projects, without the project suffering
in quality. An example would be the elimination of the Preconstruction, Engineering
and Design (PED) agreement.
NAFSMA urges Congress to authorize a process and Federal funding mechanism
for nonfederal sponsor developed projects to maximize the benefit of the use of Fed-
eral funds for federally authorized projects. This would include local sponsors taking
the lead in design and/or construction in partnership with the Corps on federally
authorized projects.
Deauthorization of Backlogged Projects
Deauthorization of projects in the backlog should occur only where the Non-Fed-
eral sponsor no longer expresses desire to participate. NAFSMA believes that rev-
ocation of an authorization or commitment to the public without public support
would be inappropriate. Deauthorization efforts shouldnt apply to projects.where
non-Federal sponsors have expressed a desire to participate, such as having exe-
cuted Preconstruction, Engineering and Design (PED) agreements, Project Coopera-
tion Agreements (PCAs) or initiated actions on Lands, Easements, Rights-of-way,
Relocations, Disposal Areas (LERRDS).
Review Of Corps Projects That Have Exhausted Their Project Life
NAFSMA encourages Congress to authorize the Corps to develop Guidance and
Policy for reevaluation of Corps-constructed or federally authorized flood control
projects that have reached or surpassed their project life.
The guidance and policy should include at a minimum, an option for de-author-
izing all or portions of the project, cost shared implementation of alternatives, such
as nonstructural approaches that provide the same benefits, or cost shared recon-
struction without going through the rigors required of new projects. NAFSMA is
prepared to assist in developing such guidance.
Early Attention to Environmental Issues and Potential Benefits and Impacts
NAFSMA supports and encourages the Corps of Engineers to make personnel
available to participate early and throughout the planning, design and permitting
phases of new civil works projects to address all environmental issues and regula-
tions in order to obtain the necessary permitting in a timely and uncontested man-
ner.
153
Assessment of True Costs During Feasibility
NAFSMA advocates the Federal Government to assure the true costs and benefits
incurred by the local sponsor for Lands, Easements, Rights-of-way, Relocations, Dis-
posal Areas, construction, environmental mitigation, operation and maintenance are
considered during the feasibility phase of the project. The true costs include those
costs mandated by laws, rules, and regulations of local, state, and Federal Govern-
ments.
Full-Credit for Project Related Expenses, Including CERCLA
NAFSMA supports non-Federal sponsors receiving full credit for all legitimate
project related expenses, similar to credit received by the Corps for project related
expenses. NAFSMA members also urge Congress to make Comprehensive Environ-
mental Response, Compensation, and Liability Act (CERCLA) activities necessary
for project execution eligible for cost-sharing credit.
CONCLUSIONS