1. Latar Belakang

Proposal teknis ini dibuat sebagai bahan penyusunan harga dan teknis pelaksanaan
pekerjaan Survey Topografi dan Soil Investigation CPP Area, jalur Pipeline dan Lokasi
Jetty Daerah Matindok Pertamina-Sulawesi Tengah.

2. Tujuan

Pekerjaan Survey Topografi dan Soil Investigation CPP Area, jalur Pipeline dan
Lokasi Jetty Daerah Matindok Pertamina-Sulawesi Tengah untuk mendapatkan
gambaran topografi, daya dukung dan karakterisik tanah, kondisi geologi, hidrologi,
potensi daerah rawan bencana dan informasi pendukung lainnya (administrasi,
kependudukan, tataguna lahan, infrastruktur daerah).
Pekerjaan tersebut dibutuhkan dalam menunjang kegiatan pembangunan Surface
Facility di wilayah Pertamina Matindok, terutama untuk CPP area, ROW flowline dan
pipeline serta sarana pelabuhan Jetty.

3. Lokasi

Daerah Matindok Pertamina -Sulawesi Tengah (Gbr.1 dan Gbr.2).

Gbr.1

Topografi dan Soil Investigation Survey -1-


SURVEYOR INDONESIA Proposal Teknis

Peta WKP Pertamina dimana Daerah Matindok terdapat di dalamnya

Daerah Matindok Pertamina

Gbr.2
Peta Daerah Matindok Pertamina

4. Tahapan Pekerjaan

Tahapan pekerjaan mengikuti bagan alir (flowchart) sebagaimana Gbr.3.

Gbr.3

Topografi dan Soil Investigation Survey -2-


SURVEYOR INDONESIA Proposal Teknis

Bagan alir (flowchart) pekerjaan


5. Lingkup Pekerjaan

Lingkup pekerjaan mengacu pada tahapan pekerjaan sebagaimana Gbr.3 dimana pelaksana
menerapkan sistem manajemen dan prosedur yang telah ditetapkan. Standar dan hasil
pekerjaan menjadi penilaian pihak Pertamina baik dari segi teknis maupun biaya pekerjaan.

Kegiatan pekerjaan Survey Topografi dan Soil Investigation CPP Area, jalur Pipeline dan
Lokasi Jetty Daerah Matindok Pertamina-Sulawesi Tengah, meliputi :
1. Desk Study dan Survey Tinjau (Preliminary Survey)
2. Survey Lapangan Pendahuluan (Pre Survey)
3. Pekerjaan Lapangan
a. Topografi Detail Lokasi CPP
b. Topografi Detail Lokasi Jetty
c. Bathymetry survey Lokasi Jetty
d. Topografi Detail ROW Flowline/Pipeline
e. Soil Investigation dan Geotechnical Analysis
4. Final Step berupa penyusunan Laporan Akhir (Comprehensive Report and
Recommendation)

Kegiatan pekerjaan Survey Topografi dan Soil Investigation CPP Area, jalur Pipeline dan
Lokasi Jetty Daerah Matindok Pertamina-Sulawesi Tengah, meliputi :

1. Desk Study dan Survey Tinjau (Preliminary Survey)


Desk Study berupa pengumpulan data dan informasi (previous data) untuk
mendapatkan gambaran posisi, luas dan cakupan lokasi. Kegitan ini dilanjutkan dengan
Survey Tinjau untuk mengetahui gambaran aktual dan permasalahan yang ada di
lapangan.

2. Survey Lapangan Pendahuluan (Pre Survey)


Pada tahap ini dilakukan:
1. Gathering data (curah hujan, kelembaban, tekanan udara, angin, seismisitas).
2. Pemesanan dan Processing Citra Satelit

Topografi dan Soil Investigation Survey -3-


SURVEYOR INDONESIA Proposal Teknis

Tujuan pekerjaan ini adalah untuk mendapatkan gambaran aktual lokasi untuk
keperluan jalur flowline/pipeline dan surface facility. Citra harus
menggambarkan land use, river crossing, elevation dan informasi daerah terkait
lainnya.

Proccesing citra menghasilkan Digital Elevation Model yang akan ditransfer


menjadi 3D modeling image. Spesifikasi teknis pekerjaan sebagaimana Tabel 1
dan Tabel 2.

Tabel 1.

Item Code Satellite Imaging and Image Processing

New Satellite Imaging


SP/1
Tools : Satellite services (Ikonos, SPOT 5, QuickBird, ASTER, etc),
CONTRACTOR shall offer each satellite services as below:
QuickBird satellite (SP/1-3)

Scope :The Satelite image output shall cover all target area with cloud
percentage not more than 20%. The object of the image shall shown
clear with not covered by cloud or other weather factor,
CONTRACTOR shall guarantee the clearance of the object,
CONTRACTOR shall get written approval from OWNER
representative before do further image processing. The image
processing shall be transferred the satellite image into DEM (Digital
Elevation Model) to make comprehensive level interpretation.
CONTRACTOR shall have minimum 3 accountable reference point
with GPS verification within the
image object. Every step of this work shall approved by OWNER
representative before do next step, all work conducted with no
OWNER approval will not considered as a progress.
The minimum resolution shall 1 m
Soft copy result shall in GeoTiff format in CD ROM
Hard copy result shall on glossy with 1 : 10,000 scale
2 disks Soft Copy (CD ROM)
2 sheet Hard copy
Unit : per 1 scene (The size of scene shall be mentioned by
OWNER)

Deliverables:
Satellite image in soft copy ard hard copy

Topografi dan Soil Investigation Survey -4-


SURVEYOR INDONESIA Proposal Teknis

Tabel 2.

Item Code Satellite Imaging and Image Processing


Acquisition Existing Satellite Imaging

Tools : Satellite services (Ikonos, SPOT 5, QuickBird, ASTER, etc),


CONTRACTOR shall offer each satellite services as below:
QuickBird satellite (SP/1-3)

Scope :The Satelite image output shall cover all target area with cloud
percentage not more than 20%. The object of the image shall shown
clear with not covered by cloud or other weather factor,
CONTRACTOR shall guarantee the clearance of the object,
CONTRACTOR shall get written approval from OWNER
representative before do further image processing.
The image processing shall be transferred the satellite image into
DEM (Digital Elevation Model) to make comprehensive level
interpretation. CONTRACTOR shall have minimum 3 accountable
reference point with GPS verification within the
image object.
Every step of this work shall approved by OWNER representative
before do next step, all work conducted with no OWNER approval
will not considered as a progress.
The minimum resolution shall 1 m
Soft copy result shall in GeoTiff format in CD ROM
Hard copy result shall on glossy with 1 : 10,000 scale
2 disks Soft Copy (CD ROM)
2 sheet Hard copy
Unit : per 1 scene (The size of scene shall be mentioned by COMPANY)

Deliverables:
Satellite image in soft copy and hard copy

Topografi dan Soil Investigation Survey -5-


SURVEYOR INDONESIA Proposal Teknis

Item Code Satellite Imaging and Image Processing


SP/3 Image Processing

Scope : This service shall conduct processing of established image (in SP/1
contract) into 3D modeling image with 25 m interval from Digital
Elevation Model data.

CONTRACTOR shall conduct


The result shall provide in digital map with ArcView / Mapinfo
format.
The scale of image shall 1 : 5,000
Hard copy output shall on high glossy paper
2 disks Soft Copy (CD ROM)
2 sheet Hard copy

Unit : per 1 established scene (from SP/1 contract)

Deliverables:
3D image with longitudinal section in soft copy and hard
copy (Sectional Image).
Pipeline route recommendation

3. Pemasangan Benckmark dan Premark untuk kerangka pengukuran

Tabel 3.

Item Code Benchmark Establishment

Tools : Trimble GPS Total Station or equal


Scope : The benchmark control stations will consist of benchmarks
constructed permanently. The marks will be located such that
they are not likely to be disturbed during the onstruction phase of
the project.

The benchmark shall be made to an existing primary Bakosurtanal


government GPS control benchmark with WGS 84 spheroid base.

CONTRACTOR shall provide the detail explanation include in


TS/1 technical and administration document. Vertical datum shall be in
Mean Sea Level which shall be derived from Bakosurtanal GPS
Control with WGS 84 spheroid base.

All survey data shall be presented in the Universal Transverse


Mercator (UTM) projection

Unit : 1 points per package


Deliverables :
Permanent benchmark point on site, with sufficient code
Benchmark layout drawings

Topografi dan Soil Investigation Survey -6-


SURVEYOR INDONESIA Proposal Teknis

4. Penyusunan jalur terbang untuk Foto Udara

Tabel 4.
Item Code Aerial Photograph / Aerial Survey

SP/4
Scope : This service shall conduct aerial photograph from airplane or other
air vehicles.
CONTRACTOR shall conduct
The result shall conduct aerial photograph image with
1 : 2,000 scale
Hard copy output shall on plain paper
2 disks Soft Copy (CD ROM)
2 set Hard copy

Unit : per 1 km 2 or equal with 1 km 2

Deliverables:
Aerial photograph ( with air plane / air transporter )
Pipeline route recommendation

3. Pekerjaan Lapangan
Pekerjaan lapangan terbagi menjadi 2 bagian besar yaitu Pekerjaan
Topografi/Bathymetri dan Pekerjaan Soil Investigation dan Geotechnical Analysis.
Informasi awal menyebutkan bahwa rencana lokasi CPP adalah daerah Kini-kini dan
Jetty berlokasi di Nonong.

o Topografi Detail Lokasi CPP


Tabel 5.
Item Code Topography Survey CPP Location

Tools : Complete Total Station Theodolith or equal


Scope : Conduct topography drawing. Data result is gathered in electronic
format and stored on board the instrument for later downloading
and processing on a computer. This data is shall be processed and
reduced to easting, northing, elevation, point code, and point
number for modeling in the survey DTM software. All survey data
TS/2 shall be presented in the Universal Transverse Mercator (UTM)

Unit : 1 Ha per package (flexible sheep of the polygon)


Deliverables:
Topography drawings complete with minimum 2 nearest
benchmark point (scale 1 : 100)

Topografi dan Soil Investigation Survey -7-


SURVEYOR INDONESIA Proposal Teknis

o Topografi Detail Lokasi Jetty


Tabel 6.
Item Code Topography Survey Jetty Location

Tools : Complete Total Station Theodolith or equal


Scope : Conduct topography drawing. Data result is gathered in electronic
format and stored on board the instrument for later downloading
and processing on a computer. This data is shall be processed and
reduced to easting, northing, elevation, point code, and point
number for modeling in the survey DTM software. All survey data
TS/2 shall be presented in the Universal Transverse Mercator (UTM)

Unit : 1 Ha per package (flexible sheep of the polygon)


Deliverables:
Topography drawings complete with minimum 2 nearest
benchmark point (scale 1 : 100)

o Bathymetry survey Lokasi Jetty


Tujuan bathymetric surveys untuk mendapatkan data yang komprehensif
mengenai kedalaman air yang digambarkan dalam bentuk kontur seabed untuk
keperluan desain Jetty atau sub sea construction lainnya.

Tabel 7.

Item Code Bathymetry Survey Jetty Location

Topografi dan Soil Investigation Survey -8-


SURVEYOR INDONESIA Proposal Teknis

Tools : Ceeducer Digital Echo Sounder (mounted on boat)


Scope : The bathymetric surveys shall be carried out using the Ceeducer
Digital Echo Sounder mounted on a locally sourced boat or similar
of minimum length of 5 metres. Horizontal positioning will be by
RTK GPS (Trimble 4700) which is integrated into the sounding
system. The sounder collects and logs depth and position data in
digital form (depth data at the rate of 6 soundings per second and
position data at the rate of 1 RTK GPS corrected position fix every
2 seconds) and displays it in real time on a laptop computer, via
BS/1 priority software. The onboard computer display is used to
navigate the survey vessel along predetermined run lines. A 'bar
check' will be carried out at the start and finish of each days work.
This enables calibration of the echo sounder for 'speed of sound'
through the water. The depth data shall corrected to Mean Sea
Level derived by TS/1 scope.

Units : 100 m x 100 m per package or equal to 10,000 m2

Deliverables:
Sea bed contour drawings with 5 m survey interval

o Topografi Detail ROW Flowline/Pipeline


Tabel 8.

Item Code Topography Survey for ROW Flowline/Pipeline

Tools : Total Station Theodolith (Sokia or equal)


Scope : Data result is gathered in electronic format and stored on board the
instrument for later downloading and processing on a computer.
Thisdata is shall be processed and reduced to easting, northing,
TS/3 elevation, point code, and point number for modeling in the survey
DTM software
Unit : 1,000 m x 40 m (RoW width 40 m per 1 km)
Deliverables:
Topography drawings with maximum 1 m interval along the
pipeline route (scale 1 : 100)

o Soil Investigation dan Geotechnical Analysis

Tujuan pekerjaan ini untuk mendapatkan analisis komprehensif mengenai kondisi dan
daya dukung tanah, tipe dan parameter mekanis tanah, geologi dan hidrologi. Pada
tabel di bawah ini disebutkan item pekerjaan, alat, metoda dan hasil masing-masing
item pekerjaan Soil Investigation dan Geotechnical Analysis.
.

Topografi dan Soil Investigation Survey -9-


SURVEYOR INDONESIA Proposal Teknis

Masing-masing item pekerjaan Soil Investigation dan Geotechnical Analysis


tersebut harus dapat diterapkan dengan jumlah volume bervariasi untuk lokasi :
CPP, lokasi Jetty dan sepanjang ROW flowline/pipeline yang ditentukan.

Tabel 9.

Item Code Hand Auger Drilling (5 m average depth)

Tools : Hand Auger Drilling shall consist of light weight aluminum


component
Scope : The soils and groundwater levels encountered during the drilling
will be logged by a geotechnical engineer onsite; and samples
representative of the main soil types will be recovered for
subsequent laboratory testing.
SG/1 Unit : 3 points per package
Deliverables :
Bore log with soil type, soil parameters from each undisturbed
samples, water table level.
Geological analysis and recommendation for pipeline route and or
shallow foundation
Soil investigation report

Tabel 10.

Item Code On Shore Deep boring

Tools : Portable Boring Machine (with mini rig)


Scope : Testing and sampling within the boreholes at a nominal 1.5
m vertical interval and would comprise SPT in non-cohesive or
stiff to hard soils and undisturbed sampling in soft to firm
cohesive soils. Each sample of cohesive soil shall be tested for
undrained shear strength using a pocket penetrometer and hand
held vane shear device immediately after recovery. The undisturbed
samples will be sealed with wax in the field. NQ3 coring shall be
SG/2-1 used for rock layer.

Unit : 3 points per package


Deliverables:
Bore Log with soil type and soil parameters undisturbed samples,
water table level
N value for SPT schedule
Soil investigation report and recommendation for foundation
(pilling). Recommendation of Piling Work.

Tabel 11.

Topografi dan Soil Investigation Survey - 10 -


SURVEYOR INDONESIA Proposal Teknis

Item Code Off Shore Deep boring

Tools : Portable Boring Machine (with mini rig)


Scope : Testing and sampling within the boreholes at a nominal 1.5 m
vertical interval and would comprise SPT in non-cohesive or stiff
to hard soils and undisturbed sampling in soft to firm cohesive
soils. Each sample of cohesive soil shall be tested for undrained
shear strength using a pocket penetrometer and hand held vane
shear device immediately after recovery. The undisturbed samples
will be sealed with wax in the field. NQ3 coring shall be used for
rock layer. CONTRACTOR shall be prepared all equipment for
SG/2-2 OFF SHORE operation

Unit : 3 points per package


Deliverables:
Bore Log with soil type and soil parameters undisturbed samples,
water table level
N value for SPT schedule
Soil investigation report and recommendation for foundation
(pilling). Recommendation of Piling Work.

Tabel 12.

Item Code Dutch Cone Penetration / DCP

Tools : Dutch Cone Penetration with minimum 2.5 T cap


Scope : To define soil strength characteristic and soil cohesion within
soil layers.
SG/3 Unit : 3 points per package
Deliverables:
DCP/CPT graphic & schedule of friction and cohesion
Soil investigation report with complete analysis of soil condition,
including recommendation of deep foundation

Tabel 13.

Item Code Soil Resistivity Test

Topografi dan Soil Investigation Survey - 11 -


SURVEYOR INDONESIA Proposal Teknis

Tools : Mega Earth testing in a Wenner array


Scope : Conduct test using a spacing (a-value) of 2.5, 5, 10 and 15 m; to
determines the average ground resistivity to those depths

Unit : 3 points per package


SG/5 Deliverables :
Soil resistivity graphic
Soil investigation report with those recommendation of ground
resistivity average
Soil Chemistry and Physical Properties (including acidity)

4. Final Step berupa penyusunan Laporan Akhir (Comprehensive Report and


Recommendation)

Penyusunan Laporan Akhir (Comprehensive Report and Recommendation) merupakan


Final Step keseluruhan pekerjaan. Pada setiap tahapan pekerjaan, Laporan Kemajuan
Pekerjaan (Progress Report) harus dibuat.

Laporan Akhir Soil Investigation (Comprehensive Report and Recommendation) dibuat


untuk 3 lokasi yaitu CPP Area, Flowline/Pipeline and Jetty, setelah item work berikut
selesai dalam bentuk final drawing.:
a. Topographic Map for CPP
b. Topographic Map for ROW Flowline/Pipeline
c. Topographic Map for Jetty
d. Bathimetric Map for Jetty

Geotechnical Analysis dibuat secara komprehensif dengan memperhatikan data


lapangan, hasil test laboratorium dan data pendukung lainnya. Analisis dan
rekomendasi menyangkut hal-hal sebagai berikut :

o GROUND CONDTTIONS
Stratigraphy
Soil Profile Based
Groundwater Conditions
Engineering Properties of Ground
Index Properties

Topografi dan Soil Investigation Survey - 12 -


SURVEYOR INDONESIA Proposal Teknis

Shear Strength Properties


Deformation Properties
Dynamic Shear Modulus
Consolidation Characteristics
Compaction Properties
o SETTLEMENT PREDICTION AND SLOPE STABILITY
Settlements Due to Fill Material
Slope Stability of Embankment
o PILE FOUNDATIONS
Axial Compressive Capacity
Pile driving Criteria
Uplift Capacity
Lateral Load capacity
Pile Group Efficiency
Dynamic Capacity
Settlement of Piles
Pile Spring and Damping Constants
SHALLOW FOUNDATIONS
LIQUEFACTION POTENTIAL
CORROSIVE POTENTIAL and SOIL RESISTIVITY

Topografi dan Soil Investigation Survey - 13 -