Escolar Documentos
Profissional Documentos
Cultura Documentos
by
Julio Baldeón
Carlos Jácome
Juan Francisco Romero
Stephen C. Welty
A Masters Degree Project submitted to the Faculty of Graduate Studies in Partial Fulfillment of
the Requirements for the Degree of Master of Science in Energy and Environment
Quito, Ecuador
August, 2003
Approval Page
The undersigned certifies that she has read, and recommends to the Faculty of Graduate Studies
for acceptance, the Group Project Report entitled “Electrical Generation Using Wind for
Francisco Romero, and Stephen C. Welty in partial fulfillment of the requirements for the degree
____________________________ ____________________________
Supervisor: Dr. Julie Rowney Date
ii
ABSTRACT
This project introduces an alternative for a marginalized community in the north of Ecudor to face
its economic problems. The district of Mira has suffered a prolongued drought for years. Thus,
agriculture, the region’s main economic activity, has decreased significantly. Unemployment,
poverty and migration are consequences.
Based on the availability of wind resource in the region and the applicable legal framework, this
project assesses the technical and economical feassibility of generating electricity at large scale for
the Ecuadorian wholesale market. A community based cooperative could share the revenues with
an interested investor. The cooperative could either use directly generated electricity for pumping,
or use the economic gains to invest in an irrigation program. Additionally, the project analyses the
convenience of different funding options and participation schemes for implementation, including
CDMs and public-private partnerships. It was found that a 14.4 MW wind farm is feasible under
the mentioned premises.
iii
ACKNOWLEDGMENTS
We appreciate the support of our families; without it, this project would have not been possible.
We acknowledge also to Dr. July Rowney and Norm Althouse because their teachings on Team
Building were essential for the success of this project.
Our special recognition is also for the Mayor of the District of Mira, Mr. Fausto Ruiz, for his
cooperation with the project; and for Eng. Ernesto Clavijo, Public Works Director of the District,
because of the information he contributed with.
iv
TABLE OF CONTENTS
v
4.1.1 Wind Power Density ___________________________________________24
4.1.2 Air Density___________________________________________________24
4.1.3 Wind Velocity ________________________________________________24
4.1.4 Surface Roughness_____________________________________________25
4.1.5 Weibull Distribution ____________________________________________26
4.1.6 Betz’ Law ___________________________________________________27
4.1.7 Power Density Function_________________________________________27
4.2 Wind Turbines___________________________________________________28
4.2.1 Power Curves ________________________________________________28
4.2.2 Annual Energy output of a wind turbine______________________________29
4.2.3 Wind Turbine Types____________________________________________30
4.2.4 Wind Turbine Components_______________________________________30
4.2.5 Size of Wind Turbines __________________________________________31
4.3 Wind Prospecting & Site Selection __________________________________32
4.3.1 Macro Siting Considerations______________________________________32
4.3.2 Micro Siting Considerations ______________________________________34
4.3.3 Wind Potential Assessment_______________________________________34
4.3.4 Measurement Equipment ________________________________________36
4.4 Site of the Project and Review of Available Data _______________________37
4.5 Preliminary Wind farm Design______________________________________40
4.6 Calculation of the energy production _________________________________42
CHAPTER 5: ECONOMIC EVALUATION ________________________________45
5.1 Optimization of Capacity and Cost___________________________________45
5.2 Breakdown Costs into Major Proje ct Activities ________________________46
5.2.1 Feasibility Phase Costs__________________________________________46
5.2.2 Construction Phase Costs________________________________________46
5.2.3 Operation and Maintenance Costs _________________________________48
5.3 Determination of the Unitary Cost of Electricity________________________49
5.3.1 Determining the Annualized Cost of Electricity ACE ____________________49
5.3.2 Determining the Annual Electricity Production AEP _____________________50
5.4 Determination of the Profits ________________________________________51
5.5 Sensitivity Analysis _______________________________________________51
5.5.1 Interest Rate _________________________________________________51
5.5.2 CDM_______________________________________________________51
5.5.3 Wind farm Arrangement _________________________________________52
5.5.4 Cost of each kW Installed. _______________________________________52
CHAPTER 6: PRELIMINARY DISCUSSION OF ENVIRONMENTAL IMPACTS54
6.1 Spatial and Temporal Boundaries ___________________________________54
vi
6.2 Issues of Concern ________________________________________________55
6.2.1 Visual Impact_________________________________________________55
6.2.2 Noise pollution________________________________________________56
6.2.3 Bird strike ___________________________________________________57
6.2.4 Construction impacts ___________________________________________58
6.2.5 Electric and Magnetic Fields (EMF) ________________________________58
6.2.6 Access roads _________________________________________________59
6.2.7 Cumulative Effects _____________________________________________59
6.2.8 Positive impacts _______________________________________________59
6.3 Description of the Environment _____________________________________60
CHAPTER 7: LEGAL FEASIBILITY ANALYSIS ___________________________62
7.1 Legislation for Renewable Energy___________________________________62
7.2 Construction and Operation Permits _________________________________64
7.3 The Concession Contract __________________________________________64
7.4 Land Leasing Contract ____________________________________________65
7.5 Environmental protection __________________________________________65
7.5.1 Chapter I General _____________________________________________66
7.5.2 Chapter II Environmental Administrative Responsibilities for the Electrical Sector66
7.5.3 Chapter III Environmental Protection _______________________________67
7.5.4 Chapter IV Instruments for Environmental Control _____________________67
7.5.5 Chapter V Environmental procedures and Requirements to Obtain Concessions,
Permits or Licenses ____________________________________________________67
7.6 Brief Overview of Private Enterprise Laws ____________________________68
7.6.1 General _____________________________________________________68
7.6.2 Specific to the Community _______________________________________69
CHAPTER 8: FINANCING MECHANISMS AND IMPLEMENTATION
SCHEMES 70
8.1 Private Funding and Implementation_________________________________71
8.2 Public/Private Partnerships_________________________________________72
8.2.1 Transfer of Plant vs. Transfer of Ownership in BOOT schemes ____________73
8.2.2 The BOOT Consortium _________________________________________74
8.2.3 Requirements for the successful packaging of a BOOT project ____________74
8.2.4 Allocation of Risks_____________________________________________75
8.3 Public Funding and Implementation__________________________________77
8.4 Agencies, Institutions and Companies ________________________________77
8.4.1 Government Agencies __________________________________________78
8.4.2 Lending Banks________________________________________________78
8.4.3 Investors ____________________________________________________80
vii
8.4.4 Constructors/Suppliers (Wind Energy Companies) _____________________80
8.4.5 Bi-Lateral and Multi-Lateral Agencies ______________________________82
8.5 Economic Instruments for Sustainable Development ____________________83
8.5.1 Clean Development Mechanism ___________________________________83
8.5.2 Small and Medium Scale Enterprise Program (SME) ___________________86
CHAPTER 9: CONCLUSIONS AND RECOMMENDATIONS ________________87
9.1 Social Aspects ___________________________________________________87
9.2 Technical Feasibility ______________________________________________88
9.3 Financing and Economics __________________________________________90
9.4 Environmental Impacts ____________________________________________91
CHAPTER 10: REFERENCES __________________________________________93
viii
List of Tables
Table 3.1 Educational Level in Mira......................................................................................... 8
Table 3.2: Age Distribution of the active economic population. ................................................. 8
Table 3.3: Main Economic Activities of Mira’s citizens ............................................................. 9
Table 3.4: Migration of Mira’s citizens................................................................................... 15
Table 3.5. Job generation for the Zafarana wind project. ........................................................ 17
Table 4.1: Roughness Class and Roughness Length (m) for different landscape types.............. 26
Table 4.2: Wind Distribution.................................................................................................. 38
Table 4.3: Approximate Weibull distribution parameters derived from the .............................. 39
Table 4.4: Selected turbine’s specifications ............................................................................ 43
Table 4.5: Results of the WTPC for a single NEG MICON 600/48 working at the site........... 43
Table 4.6: Main Features of the wind farm according to the preliminary design........................ 44
Table 5.1: Investment required in the Feasibility Phase............................................................ 46
Table 5.2: Investment required in the Construction Phase ....................................................... 48
Table 5.3: Operational and maintenance costs........................................................................ 48
Table 5.4: UCE, IRR and payback periods working with different interests rates. ................... 52
Table 5.5: Economic indexes varying the number of turbines of 600 kW................................. 52
Table 5.6: Economic indexes considering no sales of CRES varying the Cost of kW installed.. 53
Table 5.7: Economic indexes considering purchase of CRES varying the Cost of kW installed. 53
Table 6.1: Noise levels for different activities.......................................................................... 57
Table 6.2: Principal Native Species of Flora........................................................................... 60
Table 6.3: Principal native fauna species................................................................................. 61
Table 7.1: Current Environmental Regulations in Ecuador....................................................... 67
Table 8.1: BOOT Project risks divided into stages................................................................ 76
Table 8.2: World Bank Programs for Sustainable Energy. ...................................................... 78
Table 8.3: Firms involved in the Wind Energy Industry........................................................... 81
Table 8.4: GEF and World Bank Investment in Renewable Energy......................................... 83
ix
List of Figures
Figure 3-1: Location of the district of Mira............................................................................... 7
Figure 3-2: Agriculture activities of the Concepción’s citizens. ................................................ 10
Figure 4-1: Typical Weibull distribution with mean velocity of 7 m/s........................................ 26
Figure 4-2: Power Density of the Weibull Distribution in Figure 4-1....................................... 28
Figure 4-3: Power curve for a typical Danish 600 kw wind turbine. ........................................ 28
Figure 4-4: Most favorable wind resource areas in Dominican Republic.................................. 33
Figure 4-5: Example of a Wind Rose..................................................................................... 36
Figure 4-6: Approximate Weibull Distribution for Site #50 ..................................................... 40
Figure 4-7: Power Curve for the selected NEG MICON 600/48 turbine ................................ 43
Figure 6.1: Location of the project Area, near to Mira Town.................................................. 54
Figure 6.2: Probable Location for the Wind Farm................................................................. 56
Figure 8-1: Typical BOOT Consortium................................................................................. 74
x
1
CHAPTER 1: INTRODUCTION
Poverty is a major problem both for society as a whole and for the environment that society
depends upon, but in order to alleviate poverty, clear plans and mechanisms must be developed
such as opening different sectors of the economy so that marginalized communities can participate.
It may be possible to integrate the rural poor or marginalized communities into the electrical
generation sector using wind energy from wind farms and otherwise unproductive land.
To evaluate the feasibility for such a plan, a community in the Andean highlands of Ecuador
has been chosen. The results of this project may lead to a conclusion that the best way to
proceed on the project is the “No Action” option due to technical, social, legal or economic
factors. In order to reduce the risk of having such a conclusion, a number of measures have been
taken at the onset of the project and they include:
• Selection of community based on cohesiveness and self help attitude,
• Selection of an area close to meteorological stations with some wind data,
• Selection of the site with an annual average of at least 5 m/s at 10m.
The reasons for selecting the first two constraints are obvious and will be referred to
throughout the paper. The third reason is based on information that projects the cost of electricity
at sites with 5 m/s at a height of 10 meters to be on the order of US$0.04/kWh (Cavallo et. al,
1993), which from early evaluations seems to be a competitive price for energy in Ecuador
especially considering that non-conventional energy sources are given preference in the law and
have a guaranteed price of 10.05 cents per kWh.
The area chosen is the district of Mira located in the northern mountainous region of Ecuador.
The district is the newest canton in the province of Carchi, it was founded in 1980. The district
consists of one urban parish and three rural parishes Juan Montalvo, Jijón y Camaño and
Concepción. The last one is a community of black people. Studies of the current organization of
the communities and legal constitution are required. In addition, a Local Development Plan would
be useful but according to the Mayor of the district and the Association of Ecuadorian
2
Municipalities, that document will be prepared this year and is not available for this work. This
plan will provide information on the programs that will be implemented in the district in order to
improve the quality of life of the citizens.
The district, led by its Mayor, has worked with some NGOs to deal with irrigation programs
in order to deal with the draught problem of the zone. In April, 2002 the municipality and 14
others undertook a program called 3D (Decentralization- Democracy – Development) with ARD,
a NGO that works together with national and international consultants to comply with the USAID
requirements in Ecuador. This program seeks to strengthen the municipality and public
participation (Municipality of Mira, 2002).
There are 12,919 people living in the district; 2890 live in the urban area while about 10,029
live in the rural area (INEC, 2002). The main economic activity of the people in the district is
agriculture; however, draught, dollarization and the Plan Colombia have limited the activity. There
are no industries in the district and due to this, some people, especially young people, had to
emigrate to other provinces and countries (INEC, 2003). The professional people from the region
study in other cities but they usually do not go back to work in the district due to the lack of
opportunities (Clavijo, 2003).
Wind Energy is a relatively new economic activity in Ecuador. There are plans to build a of 10.8
MW wind farm in Salinas, in the province or Imbabura. The feasibility studies from this project
have finished and currently the project sponsors are looking for financing (Electroviento, 2002).
Although, there is no development of non-traditional renewables, CONELEC has a policy of
purchasing renewable energy (not including large scale hydropower) at higher rates and
guaranteeing a market for such energy provided a reasonable cost of electricity can be achieved
(CONELEC, 2002).
the country and abroad trying to improve their well being and strive to pull themselves out of their
poverty.
The project has as its objective to take advantage of the wind resource and build a wind
farm according to the results of the technical, economic, financial and legal feasibility analyses. The
use of wind energy based on its sustainability to produce electricity has increased drastically in the
last years due to its competitive prices. According to Renewable Energy World (Jul- Aug 2002)
there is even a goal that aims to generate 12% of the world’s electricity in the year 2020 from
wind energy.
Based on international and national experiences it is proposed to generate electricity using
wind for the development of the community. A good illustration of wind generation for community
development in Ecuador is what is happening in the Province of Loja, which is working in the
feasibility phase of a project for electricity generation using wind energy to pump water for
irrigation purposes. This program started as an initiative to deal with the draught problem of the
region that caused the citizens of Loja to emigrate but it was determined that the best alternative
was to provide electricity for water pumping and other uses. The site conditions indicate that the
best alternative for electricity generation is using wind energy. It is clear that the problems in the
district of Mira have some similarities with the problems in Loja; however, the conditions in terms
of government organization and administration resources are different.
This project will deal with different funding agencies and wind energy enterprises possibly
interested in investing in a wind farm. One possibility is to use a Build-Operate-Transfer (BOT)
contract so that after the turn over period, a legal enterprise made of community members could
manage the company. By doing this, barren lands will have a good use and the rate of
unemployment and emigration may decrease for the citizens of Mira.
Due to the fact that community members could work in the management and O&M of the
legal electricity enterprise and that they will manage a service that allows them to be more
productive and provide more opportunities to work inside their community, migration,
unemployment and poverty will decrease. As a note, according to UN studies the rate of poverty
4
for Ecuadorians in 2002 was 60% in spite of the rate of unemployment and underemployment
decreasing to 8.7% and 32.5% respectively according to INEC.
The project incorporates different fields covered in the master program courses resulting in
a truly multidisciplinary work. Technical background is useful to determine a proper design that
can tap the resource potential to generate electricity but this must be inside the selling capacity
framework according to the Ecuadorian legislation. Preliminary Environmental studies have
considered possible impacts produced by the construction and operation of the project.
An economic analysis is required so not only investors but also funding agencies will be
interested in investing in the project. CDMs will be analyzed as a complement to other funding due
to the CO2 emissions offset by the use of a renewable energy.
5
CHAPTER 2: METHODOLOGY
This project has been broken down into six parts including: Problem Identification and Social
Feasibility Analysis, Technical Feasibility Analysis, Environmental Impacts, Legal Analysis,
Funding Mechanisms, and Economic Evaluation. There is really no good sequential order that
these parts can be done in due to the interaction between them. For example, the legal
framework may put limits on the size of the wind farm or the Funding Mechanisms will only
contemplate funding a project larger than a certain size. For this reason, the different sections
were completed by a team in tandem to offer timely feedback in the elaboration of the other
sections.
The Problem Identification and Social Analysis were done based on data from earlier census
from the INEC and conversations with the district mayor and other people in the area. The
demographic situation was analyzed as well as the social and economic situation of the area. The
current status of cooperatives in the area were also reviewed to understand how they are
organized and if it would be possible to use such a system with the wind park project.
The Technical Feasibility Analysis was done based on the international literature. It is difficult
to do the technical analysis before knowing the size constraints of the project, which require inputs
from the Legal Analysis, the Funding Mechanism survey and the economic evaluation. For this
reason the outcome of the technical feasibility analysis was to develop parameters which could be
used to optimize the wind farm design using constraints from the other sections. Typically, when
an electrical generation station is designed, a demand analysis must also be carried out to
determine the market. This is not necessary for the current project since the idea is to build a base
load plant from which all of the generated energy will be purchased by the state transmission
company. However, other issues such as substation distance and capacity are also considered in
this section for connecting to the electricity grid.
The economic evaluation is closely tied with the technical analysis and is an important input
for the funding mechanisms section. The project will be analyzed from a number of different
perspectives including return on investment (ROI), present value (PV), and pay back period
6
(PBP). A unified cost of electricity (UCE) is calculated based on the initial cost, the cost of
capital (interest rate), and the operation and maintenance costs. This UCE will then be compared
to both the regular price paid by the state transmission company for energy and any preferential
price that the state may pay for renewable energies. The technical analysis will determine the life
of the wind farm for calculating economic gains that can be achieved after the project is paid off.
The environmental impacts are roughly the same independent of the size of turbines or the
extent of the wind farm. The only factor that changes in the environmental impact with a changing
scale is the magnitude of impact. Since the environmental impact section is not meant to be a
complete site specific EIA (Environmental Impact Assessment) only a broad overview is given of
the potential impacts.
The Legal Analysis comprises a broad overview of the legal framework in Ecuador. This
analysis includes a review of the Electric Sector Laws, company laws, cooperative laws as well as
other bodies of law. The objective of this section is to determine the actors that are legally
permitted to own and operate an electrical generation station in the country as well as to determine
any preferential treatment for renewable energy.
The Funding Mechanism section was done to evaluate the financial arena with respect to wind
farms in developing countries. The idea of private implementation was considered as well as
public implementation. A number of different contractual types were analyzed for Private/Public
Partnerships as well. The goal of this section was to have an idea of how best to fund such a
development and identify some agencies, institutions or companies that could be used to carry out
the project.
7
The Table shows that there are professionals from the district; however, due to the lack of
opportunities of employment in the region most of them do not work there. They prefer to
emigrate to other cities and to other countries (Clavijo, 2003).
The active economic population consists of 4,925 people divided in 3,519 working in the
primary sector, 398 in the secondary sector, 855 in the tertiary sector, while 146 are not
identified and 7 are new workers (INEC, July 2002). The total number of houses is 4,055.
Table3.2 shows the age distribution of the active economic population by area.
Table 3.2: Age Distribution of the active economic population.
Age Group Area
[years] Urban Rural Total
From 5 to 9 13 13
From 10 to 14 5 247 252
From 15 to 19 49 511 560
From 20 to 24 107 436 543
From 25 to 29 105 381 486
From 30 to 34 75 360 435
From 35 to 39 123 296 419
9
Table 3.3 shows the main economic activities that the citizens of Mira are dedicated to. As
can be seen in the table, the most important activity is agriculture. The active economic population
refers to the people from the district that work in certain areas without necessarily working in the
same place. According to the mayor of Mira, 95% of the population work in agriculture while the
others are dedicated to hand weaving and sell their products in the market in Otavalo each
Saturday. He also mentioned that there is no industry in the district; therefore the job opportunities
are limited to agriculture, commerce and handicrafts.
Table 3.3: Main Economic Activities of Mira’s citizens
Economic Activity Area
Urban Rural Total
Agriculture, cattle, hunting 371 3098 3469
Forestry, timber 2 35 37
Fishing 1 1
Oil, Natural gas, coal 7 7
Mining pitting 1 4 5
Beverage and Food Processing 10 52 62
Textiles Production 9 110 119
Tanning and clothing 23 19 42
Wood processing 7 14 21
10
Construction 47 72 119
Wholesale Commerce 1 5 6
Retail Commerce 70 83 153
Transportation 67 29 96
Economic Activity Area
Urban Rural Total
Informatics and communications 1 3 4
Public Administration, National defense 63 36 99
Teaching 163 51 214
International Organizations 75 71 146
Others 236 82 318
Source: INEC, 2003
Among the common products harvested in Mira are corn, beans (kidney bean, pea), oat,
wheat, barley, tomatoes, peach, grape, plums and sugar cane and the kind of products depends
on the parish. People from El Hato and Juan Montalvo communities are milk producers and cattle
breeders.
The district has multicultural variety and that can be seen in the activities performed by each
of these groups. For instance, citizens from Jacinto Jijon y Camaño and Juan Montalvo are half-
caste and are dedicated to agriculture and cattle raising (breeding), while citizens from La
Concepción are black people dedicated to growing tomatoes, beans, plums and sugar cane.
Figure 3.2 shows women from La Concepción dedicated to classifying and selling tomatoes.
Figure 3-2: Agriculture activities of the Concepción’s citizens.
In El Hato, which is considered as an area that has wind resource potential, a great deal of
eucalyptus trees are present. People that live along the road make fired bricks using the local
11
eucalyptus as firewood in their furnaces. There is a clear sign of deforestation in the area. In
addition, there is corn, wheat, blackberries crops, and cows. In El Hato there is a small cheese
factory called Quesinor, that produces 120-130 cheeses per day using 450 litres of milk per day.
Quesinor clusters 13 milk producers along the highlands. They are trained by technicians from the
Belgium Commission, who supported the Quesinor Project with technical background, to produce
different kinds of cheeses. The cheeses are sold in delicatessens in big cities. The plant operates
under a cooperative arrangement and has 25 members (6 de Julio Co-operative). According to
Miguel Leon, a Plant worker, there are 4 workers in the plant. There are about 40 milk suppliers
that belong to the region who used to sell milk at very low prices to the intermediaries and they
had to do so otherwise the milk spoiled. Nowadays, they sell the milk to the plant and receive a
fair price. He agreed that the sector had a substantial wind resource. The shape of the trees
provide evidence of strong winds in the region.
The Cooperative El Hato includes families from the region, approximately 120. This
cooperative is led by a President, Manuel Castro, who is responsible for coordinating the
meetings. The cooperative members are accustomed to having frequent meetings in order to
discuss the communities’ necessities. The most common problems identified are a lack of water
for irrigation purposes, migration, lack of industrial development and job opportunities. There are
no programs to preserve the crops that they grow nor to process these products and give them an
added value. The citizens also complain that the technical support that they get comes from
international organizations such as the Belgium Commission rather than national institutions.
For the wind electricity generation program there is the possibility that the community will be
involved in part of the program. They could have the opportunity of acquiring some shares of the
project, which could be real if there is a contract that stipulates share benefits for land possession,
for instance. As it can be seen in the case of El Hato, its members have experience in dealing with
community organization; however, more technical background is required, which could be
12
obtained from training from a multinational company or from those that are citizens of Mira and
have a university education but have had to emigrate because of the lack of opportunities.
3.3 Description of the Basic Services in the Areas that have Wind
Potential
As mentioned before, there are three different places in Mira that have a substantial wind
resource; therefore, it is useful to mention the current conditions, in terms of basic services, of the
people that live in these places.
El Hato.- It has 392 people, 151 of them work. There are 101 homes divided in 91
houses, 1 room, 1 department, and 8 makeshift structures. All of the housing has electricity
service, 99 do not have telephone service, 84 have public sewer service, 89 get water from public
service, and the rest get it from a brook. The garbage collection system only provides its service
to 19 homes, 5 families incinerate it and the rest throw it into a gorge or empty terrain (INEC,
2003).
Pisguer.- It has a population of 218, 89 of them work. There are 31 homes divided in 23
houses, 3 rooms, 4 makeshift structures, and 1 hut. Six of the homes do not have electricity
service, 31 do not have telephone service and 3 have public sewer service. Seventeen homes get
water from public service while 4 get water from a well and the rest from a brook. The garbage
collection system does not provide its service to this sector, 31 families incinerate it and the rest
throw it into a gorge or an empty terrain (INEC, 2003).
El Mirador.- It has a population of 363, 145 of them work. There are 110 houses divided
into 93 homes, 1 room, and 16 makeshift structures. Three homes do not have electricity service,
108 do not have telephone service and 33 have public sewer service. From all the houses, 108
homes get water from public service while only 1 gets it from a well and the rest from a brook.
13
The garbage collection system provide its service to 31 homes, 7 families incinerate it and the rest
throw it into a gorge or an empty terrain (INEC, 2003).
3.4.1 Poverty
Seventy eight percent of the population of Mira is considered to live in poverty and 19.5%
of its citizens live in extreme poverty (Larrea, 1996). There are several reasons why people live in
poverty and one of them can be said to be the lack of industrial infrastructure in the region.
According to the town Mayor, Fausto Ruiz (2003), there is no industry in the district; therefore
the job opportunities are limited. In addition, the main economic activity, agriculture, has
decreased due to the period of drought that the region has and is facing. This has limited the
agricultural potential of the zone. Furthermore, the economic situation of the country has intensified
the problem, because Mira’s farmers used to export their products to Colombia. When Ecuador
started the process of dollarization, the cost of crops that were sold in Colombia became more
expensive making the business unattractive for Colombians. Another cause that worsened Mira’s
economic situation was the Plan Colombia, as there was more control on commerce and it was
limited to certain hours in the day making the transportation costs more expensive; therefore, the
prices for the Colombian consumer of Ecuadorian products increased (Clavijo, 2003).
As a consequence of poverty, children from rural areas withdraw from school in order to
help their parents in their agricultural activities. Children do that because their older brothers have
migrated to other cities looking for a better future. Therefore the level of education in rural areas is
very low.
14
“There is little water resource to have good agricultural practices, this problem has made
people abandon their lands and emigrate” (Ruiz, 2003). According to Ernesto Clavijo (2003),
emigration and drought produced mainly by deforestation of eucalyptus trees and the lack of a
good irrigation service are the main problems that Mira citizens face everyday. There are serious
troubles of bad water distribution. The Provincial Prefect has said , “There is no award and
technical concession from the irrigation water, which should be according to the population’s
needs” (Yandún, 2003).
As a consequence of indiscriminate deforestation of the eucalyptus forest that surrounded
the city, drought has intensified in the last years creating problems to agriculture mainly. Eucalyptus
wood is used as firewood for cooking and brick making. There are plans to develop irrigation
programs from El Angel river basin, which is being carried out by an NGO (ARD). Citizens from
San Isidro were against the construction of an irrigation channel due to their own interest (Clavijo,
2003).
In Ecuador, the irrigation water system only covers 500,000 hectares, which represents
30% of the cultivated land in Ecuador (1,850,000 ha). In the district of Mira, the irrigation water
comes from the El Angel river basin; however, the distribution system favors those with economic
and political power in the zone, which is a clear evidence of inequality (Proaño, Poats, 2000).
The Municipality of Mira organized and launched a seminar called Decentralization-
Democracy – Development ARD 3D whose objectives are to strengthen the municipal capacity in
service areas, local planning, financing, administration, environmental management and
identification of priorities for community development. Furthermore, it aims for public participation
to build policies and democratic mechanisms. Finally, the project seeks an effective
decentralization (Municipality of Mira, 2002). Eight different projects were identified that focused
on the current problems of the district. However, of the eight projects only one will be executed
and will help to improve the development of the district. The different projects presented were:
irrigation management program, development and route equipment, optimization of the economic
15
resources of the district, public training, popular housing, integral strategic plan, environment unit
creation, and implementation of the public health programs.
From the different proposals, the different stakeholders at the seminar decided that the
irrigation management program was a priority for the district because its implementation will
promote agricultural development, will reduce emigration and poverty and will benefit the majority
of citizens (Municipality of Mira, 2002).
3.4.3 Emigration
According to the Mayor of Mira, people abandoned the district after dollarization started.
As a consequence of migration there are few young in the district devoted to agricultural practices.
People have gone to work in flower plantations, kitchen farms located in Tabacundo, Cayambe
and Salinas and even others have gone to other countries as table 3.4 indicates. In addition, “The
majority of professionals do not come back to the town because they do not have opportunities to
apply what they learned in their universities” (Clavijo, 2003).
Table 3.4: Migration of Mira’s citizens.
Country of Destiny Men Women Total
Spain 31 29 60
Brazil 1 1
United States 5 1 6
Russia 1 1
Chile 1 1
Colombia 5 2 7
Honduras 1 1
Guatemala 2 2
Czech Republic 1 1
Belgium 1 1
Italy 2 2
United Kingdom 3 2 5
Cuba 1 1
Sweden 1 1
Costa Rica 1 1
Austria 1 1 2
Total 51 42 93
Source: INEC, 2003
16
One of the main benefit that the implementation of an electricity generation program in a
rural area that does not have opportunities for industrial development is the improvement of the
economy in the region due to capital movement and job generation. One of the biggest problems
that Ecuador has is unemployment. According to UN studies the rate of poverty for Ecuadorians
in 2002 was 60% despite the fact that the rate of unemployment and underemployment decreased
to 8.7% and 32.5% respectively (INEC, 2003). The wind electricity generation program could
contribute to the people from Mira with employment; therefore, it would reduce the
unemployment at least in the district.
17
In the feasibility, construction and operational phase of the project, there is a requirement
of skilled and unskilled people. In addition, it provides opportunities for local shopkeepers, hotels,
restaurants and car rentals because workers from the electric company will live in Mira and this
will increase the average income of its citizens. However, this economic component of the project
is difficult to estimate. In the feasibility and in the construction phase local people could be
involved in the civil works, erection of mills, transportation, measurement of wind velocities and
directions and the construction of monitoring towers.
Mira has professional people that could join to the construction and operational phases of
the projects but previously they should receive training in wind energy management because it is a
new field. Moreover, it will increase the opportunity of constructing factories or increasing the
capacity of the milk and cheese industries from the region that nowadays do not have refrigeration
systems that allow product conservation.
18
By having integration between the electric company and the local community members, the
wind electricity program provides economic gains for Mira’s citizens. This is without taking into
account the option for community members to acquire some shares of the wind electricity
program.
One of the main difficulties that the area has is the lack of good irrigation programs to deal
with the drought of the region. There are water bodies that flow in and near the district. One is the
Angel basin and the other the Mira River. There is a water basin by a creek in Juan Montalvo that
could be used to provide water, however it needs to be pumped (Clavijo, 2003). It is clear that
the incorporation of a sustainable electricity program will assure that electricity is available for
water pumping and will help to irrigate barren lands. A good example of interconnection between
irrigation programs and electricity generation using wind energy is the Aerogeneration for the
sustainability of the pumping systems in the Province of Loja in Ecuador, as was mentioned before
(H. Consejo Provincila de Loja, 2003).
By implementing such a program the main economic activity, agriculture, will flourish again.
This will allow the district to become the agricultural hot spot that it was in the past, and it will also
allow for emigration and poverty reduction.
A reforestation program could also be incorporated as the bad practice of cutting trees
has destroyed the forest belt that the district had. Deforestation practices produces erosion and
then drought (Bouchart, 2003). By incorporating a reforestation program, which may eventually
be incorporated into a CDM program, the drought problem could decrease and this would make
the irrigation problem less critical.
19
Mira citizens have potable water (97% of the district, INEC, 2003). The piping system
was changed from asbestos to PVC. Clavijo (2003) emphasized that “The problem appears in the
irrigation water for agricultural purposes”. There is a water basin by a creek in Juan Montalvo that
could be used to provide water, however it would require a pumping system.
Based on the experience that Mira’s citizens have in organizing cooperatives such as El
Hato, it would be a good initiative that the owners of the land where the windmills will be built
organize some sort of cooperative. A strategic alliance between the investors of the wind project
with the community members could be done as in the case of Honduras, where a group of farmers
20
with land properties containing rivers became shareholders of the hydro electric plants on their
property (OLADE, 2003). One disadvantage of such an initiative is that in most of the cases the
main beneficiaries are the richest people from the region because they are the ones who own the
maximum amount of land in the district and the probabilities that the windmill is built in their land is
high. Therefore, the problem of poor wealth distribution would continue.
For this reason, it would be good to create a cooperative where most of the citizens will
benefit. It is necessary that a commitment exists among the citizens to contribute to the creation of
a cooperative where a fair welfare distribution exists. The cooperative must be representative of
the district that means it should include small, medium and large scale farmers, milk producers, and
merchants. Some of the difficulties with applying this method based on the other stakeholders in
the projects will be discussed in the financial chapter.
Another option to manage the project could be that the Municipality administrates the
income of the electricity program because it has a complete overview of the district needs and if it
works well it will maximize the welfare and the equity throughout the district. One benefit of is to
undertake projects that will promote the development of the region such as those mentioned in the
3-D seminar.
Nonetheless, there are some disadvantages of such a proposal and one of those is the
duration of a particular administration in the Municipality. In Ecuador the Mayor of the district
lasts 4 years and in most cases they are accustomed to developing short term projects rather than
long term projects like this one. For this reason the continuity of the project in hands of the
Municipality is not guaranteed. Furthermore, inside a government organization with good profits
comes the issue of corruption could destroy any benefits. This has been very common in Ecuador
and needs to be considered.
The selection of the right shareholders for the electric utility company will guarantee the
sustainability of the project. For this reason it is very important to analyze all the pros and cons of
both proposals.
21
One problem that has plagued Ecuador for many years is the poor banking sector (Saltos &
Vázques, 1999). With the bank holidays and money lost in the banks during the administration of
Jamil Mahuad, very few people have confidence in putting their money in banks. One way that
this project could be carried out is by looking for national investors in the project. Developing
infrastructure programs in developing countries should not only have the goal of providing services
to the citizens but it should also help to develop local capital markets where nationals can invest
and earn a reasonable return on their investment with a low risk (Churchill, 1991). The obvious
difficulty with this method is that it would once again favor those who have money to invest in such
a project and would do nothing for the people that are considered to be poor.
receive the benefits. These benefits are related to improvements in the economic income and the
execution of public works that are vital for the community’s development. This could be achieved
if the wind energy project becomes a reality in Mira.
23
The energy flux, or wind power density, of a stream of air of density ρ [kg/m3] moving with
velocity v [m/s] is given by: (Cavallo, Hock, Smith.,1993)
(Pw)dens = ρv3/2 [watts/m2]
A wind turbine obtains its power input by converting the force of the wind into a torque (turning
force) acting on the rotor blades. Then, the amount of energy transferred from the wind to the
rotor depends on the density of the air, the rotor area A (m2), and the wind speed (DWIA, 2002).
The power (Pw) of a wind turbine is given by the expression: (Barriga, 2002)
Pw = ρAv3/2 [watts]
The "heavier" the air, the more energy is captured by the turbine. At normal atmospheric
pressure at 15° Celsius air weighs about 1.225 kilogrammes per cubic metre, but the density
decreases slightly with increasing humidity. Also, the air is denser when it is cold than when it is
warm. At high altitudes, (in mountains) the air pressure is lower, and the air is less dense
(DWIA,2002). Therefore, air density is one of the characteristics making wind power extremely
site specific.
The energy content of the wind varies with the cube (the third power) of the average wind
speed, as derived from the last expression. Wind velocity is inherently variable in both magnitude
and direction. In fact, wind velocity may fluctuate from second to second. Wind patterns vary also
seasonally and may vary from year to year for a given location (DWIA,2002). These
characteristics necessitate a long period of wind characterization to gather reliable data for a
specific place within an area of interest for a wind farm. However, the strong winds usually come
25
from a particular direction and this should be evident in the data collected over time
(DWIA,2002).
Wind velocity up to 100 meters is very much influenced by the ground surface. The wind
will be slowed down by the earth's surface roughness and obstacles. In general, the more
pronounced the roughness of the earth's surface, the more the wind will be slowed down. Forests
and large cities obviously slow the wind down considerably, while concrete runways in airports
will only slow the wind down a little. Water surfaces are even smoother than concrete runways,
and will have even less influence on the wind, while long grass and shrubs and bushes will slow the
wind down considerably. A high roughness class of 3 to 4 refers to landscapes with many trees
and buildings, while a sea surface is in roughness class of 0.
Roughness lengths and roughness classes are used in the wind industry to quantify the
influence of the ground surface. The term roughness length refers to the distance above ground
level where the wind speed theoretically should be zero because of the influence of the surface
roughness. The European Wind Atlas defines the roughness class on the basis of the roughness
through the following logarithmic function (DWIA,2002):
Table 4.1 provides values for roughness class and roughness length for different landscape
types, in accordance to definitions of the European Wind Atlas (Troen & Lundtang, 1991). Those
values are important for the determination of velocities at different heights away from the
measurement height (for which wind speed measurement was taken).
26
Table 4.1: Roughness Class and Roughness Length (m) for different landscape types
Landscape Type Rough- Roughness
ness Class Length (m)
Water surface 0 0.0002
Open terrain with a smooth surface (e.g. runways, in airports, 0.5 0.0024
mowed grass, etc)
Open agricultural area without fences and hedgerows and very 1 0.03
scattered buildings. Only softly rounded hills
Landscape Type Rough- Roughness
ness Class Length (m)
Agricultural land with some houses and 8 metre tall sheltering 1.5 0.055
hedgerows with a distance of approx. 250 mts
Agricultural land with some houses and 8 metre tall sheltering 2 0.1
hedgerows with a distance of approx. 500 metres
Agricultural land with many houses, shrubs and plants, or 8 metre 2.5 0.2
tall sheltering hedgerows with a distance of approx. 250 metres
Villages, small towns, agricultural land with many or tall sheltering 3 0.4
hedgerows, forests and very rough and uneven terrain
Larger cities with tall buildings 3.5 0.8
Very large cities with tall buildings and skyscrapers 4 1.6
Source: DWIA, 2002
Weibull distribution describes the wind variation for a typical site. Normally, the
measurements are carried out during 1 year. The graph of the distribution shows the number of
hours a year in which the velocity is within each different class or range of velocities i.e. the
probability density distribution. Therefore, the probability of occurrence of any velocity may be
derived from this distribution. A Weibull distribution is defined by two parameters: mean velocity
and shape parameter. Figure 4.1 (DWIA,2002) is a typical Weibull distribution in which the mean
velocity is 7 m/s and the shape parameter is 2.
Figure 4-1: Typical Weibull distribution with mean velocity of 7 m/s
If each tiny wind speed interval is multiplied by its probability of occurrence, and those
values are added up, the result is the mean wind speed. In other words, the mean wind speed is
the average of the wind speed measurements for the site. The most common wind speed is called
the modal value of the distribution; in the case of the figure it is 5.5 m/s. The statistical distributions
of wind speeds are not symmetrical. The shape factor describes how the distribution is skewed. If
the shape parameter is exactly 2, as in the graph, the distribution is known as a Rayleigh
distribution. Turbine manufacturers often use this distribution to give standard performance figures
for their machines.
When wind passes through turbines, it is slowed down. Aerodynamics of this energy
transmission process explains that an ideal turbine would slow the wind down by 2/3 of its original
speed. Derived from this fact, the Betz law expresses that any turbine can only convert less than
16/27 (or 59%) of the kinetic energy in the wind to mechanical energy. This generalization applies
for any turbine with a disc-like rotor (DWIA,2002).
The power density function is derived from the Weibull Distribution, by multiplying the
power of each wind speed with the correspondent probability of that speed. If average wind
velocities were used instead of the power density function, the power calculation will be
underestimating wind resources by nearly 100%, provided that high wind speeds although rare,
account for a big share of the harvested energy (DWIA,2002).
Also as a consequence of this, the Weibull curve changes shape. The resulting power
density function derived from the previous Weibull distribution is shown in the Figure 4.2.
28
The power curve is a graphical register of the electrical power output for a given turbine at
different wind speeds. Power curves are obtained from field measurements, and are provided by
the turbine’s manufacturer. This data allows building the turbine power output curve in the
29
previous graph. Figure 4.3 shows a power curve for a typical Danish 600 kw wind turbine
(DWIA,2002).
Given the continuous fluctuation of wind velocity it is difficult to get accurate data for the
power curve. It results in the possibility of errors up to plus or minus 10 percent even in certified
power curves (DWIA,2002). Additionally, power curves are registered at standard air pressure
and temperature, (1 atm, 298 K); consequently it is necessary to make corrections for changes in
air density.
The turbines, also called aero-generators are the devices used to capture and convert the
wind energy into electrical energy. Those devices are designed to start running at a certain wind
speed called the cut in speed, which is usually somewhere around 3 to 5 m/s (DWIA,2002).
Similarly, there is a cut out speed at which the wind turbine is programmed to stop. It occurs at
high wind speeds, around 25 m/s, in order to protect the turbine from excessive loads and the
surroundings.
The energy output in kWh per year, tells how much electrical energy the wind turbine will
produce in an average year and is one of the features that is used to calculate the unit cost of
electricity on an annual basis as will be described later. In order to calculate the energy output of
a wind turbine, it is necessary to combine the site’s meteorological data, the site’s Weibull
Distribution and the selected turbine’s power curve. If the probability of each velocity on the
Weibull Distribution is multiplied by that velocity and its corresponding power value from the
turbine’s power curve (adjusted for the meteorological conditions) and all of these partial products
are summed up, the result is the average power output for that turbine. If this value is multiplied by
365 day/year and 24 hour/day, the total energy output for an average year is obtained. It must be
noted that power curves are obtained empirically by the manufacturer for standard conditions (1
atm and air pressure 1,225 kg/m3). Upon this calculation, site meteorological conditions are also
used to determine the theoretical maximum output, and then, the turbine’s capacity factor. It is the
30
actual annual energy output divided by the theoretical maximum output, if the machine were
running at its rated (maximum) power all along the year (DWIA,2002).
As regards to axis orientation, two types of wind turbines exist: horizontal axis or vertical
axis. However, “all grid-connected commercial wind turbines today are built with a propeller-type
rotor on a horizontal axis (i.e. a horizontal main shaft)” (DWIA,2002). Additionally, there are
Upwind and Downwind Machines. Upwind machines have the rotor facing the wind. The basic
advantage of upwind designs is that one avoids the wind shade behind the tower. By far the vast
majority of wind turbines have this design (DWIA,2002). Finally, wind turbines may also differ in
the number of rotor blades. Most modern wind turbines are three-bladed designs with the rotor
position maintained upwind (on the windy side of the tower) using electrical motors in their yaw
mechanism. This design is usually called the classical Danish concept and the vast majority of
turbines sold in world markets have this design (DWIA,2002). For the purposes of this research,
and given the scope of the technical feasibility analysis, only typical Danish wind turbines are
considered for selection. A required further analysis of the technical design may explore other
possibilities.
The basic elements in typical wind turbines are: nacelle, rotor blades, hub, tower, gearbox,
electrical generator. Additionally modern wind turbines include other mechanisms that make
possible their operation such as: low speed shaft, high speed shaft with its mechanical brake yaw
mechanism, electronic controller, hydraulics system, cooling unit, tower, anemometer, and wind
vane. The nacelle contains key components of the wind turbine, including the gearbox and the
electrical generator. The turbine rotor includes both the rotor blades and the motor hub. Rotor
blades capture the wind and transfer its power to the rotor hub. This hub is attached to the low
speed shaft of the turbine which goes into the gearbox. On a modern 600 kW wind turbine the
rotor rotates slowly, about 19 to 30 revolutions per minute (rpm) (DWIA,2002). The high speed
31
shaft at the gearbox output rotates 50 times faster than the low speed shaft. It is nearly 1500 rpm,
and drives the electrical generator. It is equipped with an emergency mechanical disc brake. The
electrical generator is usually an induction or asynchronous generator. On modern wind turbines
electric power ranges between 500 and 3000 (kw). The tower of the wind turbine holds the
nacelle and the rotor. Towers may be either tubular towers or lattice towers. Modern turbines
include an electronic controller consisting of a computer continuously monitoring the condition of
the wind turbine and controlling its operation. The electronic controller also senses the wind
direction, and operates the yaw mechanism which turns the nacelle and the rotor to keep it against
the wind when its direction changes. The anemometer and the wind vane measure the speed and
direction of the wind and send their signals to the electronic controller.
Higher towers have the advantage that wind speeds increase farther away from the
ground. A typical modern 600 kW turbine will have a tower of 40 to 60 meters (DWIA,2002).
Longer rotor blades implies a higher capacity of capturing energy from the wind, since power is
proportional to the area swept by the rotor (i.e. the square of the rotor blade length), as seen in
the expression of the power of a wind turbine. Nevertheless, large rotor turbines and generators
require also large wind power to be moved. On the other hand smaller generators in low wind
areas provide more electrical power output, because they will be running more hours during a year
(DWIA,2002).
The Danish Wind Industry Association exposes economies of scale and efficiency in the use
of wind resource as reason to select large turbines instead of smaller ones. Other advantages of
large turbines are that they are more suited for weak electric grids while the electricity output of a
wind farm of smaller turbines fluctuates. On the other hand, the costs of transportation and
mounting of smaller components are frequently lower and the risk of temporary failure is spread in
several small units rather than in a few large ones (DWIA,2002). All of these factors must be
32
balanced in attention to local conditions in order to select the most convenient turbine arrangement
for a wind farm.
For the initial site selection, there are a number of methods to identify regions with a
significant wind resource. Most countries have a national meteorological institute for predicting the
weather in order to warn their citizens of imminent natural disasters or for general weather
forecasting. Measurements are also taken for aviation purposes. While this data can be helpful in
getting a general idea of where there is a considerable wind resource, they are usually very local as
is the case for airport data or are measurements of upper wind speeds using weather balloons
which are not very helpful for knowing the surface wind speed. The area of Mira in this project
was chosen based on information from INAMHI, which has a wind station in the town of Mira.
Another way to identify areas of considerable wind resources is to use upper air pressure/
wind data and combine it with high resolution surface topology information to estimate surface
wind potential (Hamlin, 2001). The United Nations Environment Program (UNEP) is carrying out
a project called Solar and Wind Energy Resource Assessment (SWERA), which uses this
approach to characterize the wind resource in 13 developing countries. The resource information
collected through SWERA will be widely available as a user friendly Geographical Information
Systems (GIS) tool including geospatial information such as proximity to grid substations,
population density, roads and non-electrified areas (UNEP, 2002). Unfortunately, Ecuador is not
one of the 13 countries to have had the wind resource map developed for it during the initial
phases of the SWERA program. This informational tool will give a considerable advantage for
foreign investment to those nations that have it.
33
SWERA uses a number of wind mapping models including WRAMS, which is a model
developed by the US National Renewable Energy Laboratory (NREL) that selects the most
favourable topology for wind and calculates the wind power from upper air data and then
calibrates that to ground data (Hamlin, 2001). WAsP is another model developed by the Riso
National Laboratory in Denmark and predicts wind power from wind data measured at weather
stations in the same region, taking into account topology and obstructions (WAsP, 2003). Figure
4-4 shows the wind resource map for the Dominican Republic.
Figure 4-4: Most favorable wind resource areas in Dominican Republic.
Skewed trees and shrubs as well as traces of erosion may show evidence of intense winds
and their prevailing direction at the site. Likewise, topographic characteristics give an idea of the
better places for locating wind turbines. Two speed up effects are known: Tunnel effect and Hill
effect. The first occurs due to the compression experienced by the wind when passing between
two mountains or gulch walls (DWIA,2002). Turbines are commonly placed on hills overlooking
the surrounding landscape. The wind becomes compressed on the windy side of the hill, what is
known as the Hill effect (DWIA,2002). Therefore, both tunnels and hills are places likely to have
higher wind speeds than in other areas. Nevertheless, if the tunnel walls or the hill are uneven and
are not softly embedded in the landscape, it may cause turbulence and consequently cancel the
advantages of those speed-up effects. In general, desirable characteristics for a site to place wind
turbines include wide and open spaces as possible in the prevailing wind direction, few obstacles
and low roughness in that same direction.
Other issues to take into account for defining the location of a wind farm are: the availability
of the appropriate electrical facilities to transport the electricity, the feasibility of building
foundations of the turbines, and road construction to reach the site with heavy trucks transporting
the equipment (DWIA,2002).
According to the World Bank Industry and Energy Department (1986), the principal
descriptive parameter of a wind regime is the annual average wind speed. Wind resource
assessment, also known as anemometry, is commonly carried out for aviation or weather
forecasting purposes, consisting quantifying the amount, variability and other characteristics of the
wind. However, those aviation and meteorological data are not sufficiently reliable for assessment
of wind energy potential, given the cube relationship existing between wind power and wind
speed. Consequently, small differences in wind speed can have significant effects on the total
power available (The World Bank Industry and Energy Department, 1986). As stated before,
(Section: Power Density Function), if average speed values were used in wind power calculation,
35
the outcome would underestimate wind potential by nearly 100% (DWIA,2002). The World
Bank guidelines for assessing wind potential asserts “Before any wind energy system can be
seriously contemplated, good wind regime data must be available” (The World Bank Industry and
Energy Department, 1986), and then describes “good” in terms of accuracy and range of data
collected as well as length of time over which measurements take place. As regards to length of
time the WB Guidelines estimate that 5 years would be “highly desirable”, 2 years would be
“sufficient to have a reasonable certainty of the distribution”, and a 1 year period would be the “a
bare minimum”.
The devices used to measure the wind speed over a given period of time, or averaging
time period are called anemometers. “The ideal averaging period for any situation is the longest
one which still permits one to capture the type of oscillations in the wind pattern which are deemed
relevant for the application in question” (The World Bank Industry and Energy Department,
1986). Finally, the Danish Wind Industry Association as well as the WB guidelines endorse that a
10 minutes averaging period is suitable for wind potential prospection purposes (DWIA,2002).
In this way, conventional anemometers (10 minute average period) allow 144 observations per
day and 52,560 per year. All of that data is sorted into bins or ranges of velocity to obtain a
frequency distribution or Weibull Distribution, described before. WB Guidelines presents, as
example, ranges or bins of 1m/s.
Another resource used to characterize the wind of a site is a Wind rose. It is a graph used
to illustrate the relative energy content of the wind coming from the varying wind directions, at a
specific measurement site. Wind roses are extremely useful to locate wind turbines, and for the
general wind farm layout, if a large share of the energy in the wind comes from a particular
direction, it would be desirable to have as few obstacles as possible in that direction. The next
figure shows an example (DWIA,2002).
36
Standard Wind Roses have 12 sectors, one for each degree of the horizon. The radius of
the outermost wide wedges gives the relative frequency of each of the 12 wind directions. The
next wedge provides the same information but multiplied by the average wind speed in the
correspondent direction, normalized and expressed as percentage. It shows how much each
sector contributes to the average wind speed at our particular location. Finally, the innermost
wedge gives the energy content of wind coming from the diverse directions expressed as a
percentage, by taking into account the cube of the respective wind speed.
As supported by the Danish Wind Industry Association as regards to wind rose graphs,
“Planners of large wind parks will usually rely on one year of local measurements, and then use
long-term meteorological observations from nearby weather stations to adjust their measurements
to obtain a reliable long term average” (DWIA,2002).
Wind speeds are usually measured using “cup anemometers”. Those devices have a
vertical axis and three cups which capture the wind, its revolutions per minute (rpm) are
electronically registered. Additionally, typically used anemometers include a vane to detect the
37
wind direction. Other types of anemometers may include propellers, ultrasonic laser devices,
however those are less common, and the analysis of its convenience goes beyond the scope of this
research. What is important to know about anemometers is that, professional and well calibrated
anemometers are required for purposes of wind potential assessment. Poorly calibrated
anemometers available in the market for meteorological purposes may include errors of 5 to 10
percent that could cause a disaster in economic terms if used for wind prospection (DWIA,2002).
The anemometer’s data of wind speeds and directions is registered and collected on a data
logger, a battery operated electronic chip or a small computer (DWIA,2002).
At a prospective wind turbine site, anemometers are placed at the top of a mast in the
prevailing direction of the wind. In order to minimize the uncertainty involved in recalculating the
wind speeds at a different height, the best is to have the anemometer at the same height as the
expected hub height of the turbine to be used (DWIA,2002). The log Relationship is used to
calculate the wind mean velocity at a given height when wind prospection data is available for
other heights at which prospection took place (The World Bank Industry and Energy Department,
1986) as shown through the following expression:
V ( h2 ) ln( h2 / R)
=
V ( h1 ) ln( h1 / R)
Where: V(x) represents the average wind speed at height x, h1 and h2 are the two respective
heights in meters and R is a surface roughness constant.
(DWIA,2002). However, more of those lands are untilled. The presence of high winds was also
verified by visual inspection of the site where the skew of the trees and shrubs gives an idea of
strong winds in a given direction towards the Salinas valley. In addition, the zone has the highest
hills in the surrounding landscape, where turbines could be placed to take advantage of the hill
effect, explained before.
As discussed, the necessary wind resource characterization for a project of large scale electricity
generation implies a long period of measurements at specific points where the power density of
wind is suspected to be considerable. In the face of the absence of this data, available data for
the Salinas Valley is used referentially as explained before. The characterization has been carried
out by the company PROVIENTO in three sites from 1997 to 1999. PROVIENTO denominated
the sites: #40, #50 and #21. The measurement height for all of them is 40 meters. It is important to
note that PROVIENTO changed its name to ELECTROVIENTO by the year 2002 and the
project studies done by the latter company have changed the features with respect to those of the
former.
Given the scope for the present technical feasibility study, it is assumed that the District of
Mira has available a number of points with similar wind potential in which wind turbines may be
placed. This wind potential is represented by the Weibull Distribution given for a test measurement
point upon the PROVIENTO’s wind distribution data in the Salinas Project. The two first rows in
table 4.2 present such information.
Table 4.2: Wind Distribution
Speed Hours/year Probability Prob*Speed Weibull Absolute
(m/s) (h) Deviation
0 86 0.0098 0.0000 0.0000 0.0098
1 457 0.0522 0.0522 0.0645 0.0123
2 668 0.0763 0.1525 0.0907 0.0145
3 792 0.0904 0.2712 0.1035 0.0131
4 858 0.0979 0.3918 0.1069 0.0090
5 854 0.0975 0.4874 0.1035 0.0060
6 818 0.0934 0.5603 0.0956 0.0022
7 744 0.0849 0.5945 0.0849 0.0000
8 656 0.0749 0.5991 0.0731 0.0018
39
The ELECTROVIENTO data does not reflect exactly a Weibull distribution. However,
by using the SOLVER tool of MICROSOFT EXCEL, different values of shape parameter were
tested with the WEIBULL DISTRIBUTION function (in EXCEL too) with the series mean
velocity to find the shape parameter for which the difference between the sum of absolute
deviations is the minimum. Where absolute deviation is the absolute value of the difference
(Weibull calculated probability – Measured probability). This way, an approximate Weibull
distribution given by the mean velocity of the series and the obtained shape parameter was found
for each measurement point. Those parameters are shown in table 4.3. Figure 4.6 shows the
ELECTROVIENTO Site data and the approximated Weibull Distribution.
Table 4.3: Approximate Weibull distribution parameters derived from the
Measurement Sites #40
Mean velocity 7.150
Shape parameter 1.617
Source: ELECTROVIENTO Report , 2002
40
0.1200
0.1000
0.0800
Probability
0.0600
0.0400
0.0200
0.0000
0 5 10 15 20 25 30
Wind Speed
Basically the objective of this section is to determine the annual energy output of the wind farm
and main components of investment required for the farm to be installed and generating. Those
results will be used for the economic feasibility evaluation.
All of the parameters for the design of the wind farm are somehow related to each other.
Then, it is necessary to start from certain restrictions or even assumptions to simplify the problem
in order to narrow it down and come up with referential results according to the scope of the
41
present research. However, parameters of optimization of the wind farm design will be identified
along the process of design.
First, with regard to installed power there are several factors to take into account such as:
economies of scale of wind farms, size of the investment, investment’s period of return and the
availability of physical space and others. However, the Ecuadorian legislation ensures preferential
dispatch for electricity coming from alternative sources including wind energy up to 2% of the
installed capacity of the generators of the Wholesale Electricity Market, which is around 65 MW
since the total capacity in Ecuador is 3247 MW (CONELEC, 2002). However, in order to get
preferential treatment for non-conventional renewable energies, a single plant can be no bigger
than 15 MW. The installed capacity for the ELECTROVIENTO’s project at the Salinas Valley is
10.8 MW: and this project has been demonstrated to be feasible (ELECTROVIENTO, 2002).
Different arrangements of turbines as regards to size and number may result in the desired
installed capacity, in such a way that those variables are parameters of optimization for the design
of the wind farm. The referred (PROVIENTO, 2000) project also selected 24 600-kw turbines,
for the feasibility study of their farm. In consequence, as a first approximation it looks like a good
option to define the same to achieve an installed capacity lower than the preferential dispatch limit.
Naturally, a site specific analysis carried out on the basis of the presented theoretical principles
would allow the determination of optimal values for installed power, number and size of turbines.
However, it does not make sense here, since no site specific data is available.
As for wind farm layout, it largely depends on the available area in the proximity of the points
where the resource has been characterized and found adequate for commercial generation of
electricity. For spacing wind turbines the wind park effect that occurs when more than one turbine
is located facing the wind in a column must be considered, since each turbine will slow down the
wind behind as it dissipates energy. Although at a smaller scale, perturbation takes place also
perpendicular to the direction of the wind, when the turbine intercepts the flow. As a rule of
thumb, turbines in wind parks should be spaced somewhere between 5 and 9 rotor diameters in
42
the prevailing direction of the wind and between 3 and 5 rotor diameter in the transversal direction
(DWIA, 2002).
For the present calculations it is assumed that the available area is not restrictive for placing
approximately twenty four 600KW turbines in the district of Mira, as supported by Mira’s Mayor
in an interview. He mentioned that the Municipality had the authority to expropriate terrains if it is
considered necessary for a project in the public interest, and the availability of the resource is
given as explained in the section “Site of the project and review of available data”.
typical Danish turbines, whose parameters and power curves are predefined by the manufacturer.
For the present calculations NEG MICON 600/48 turbines were selected. The aero-generators
have the specifications shown in Table 4.4.
Table 4.4: Selected turbine’s specifications
Turbine NEG MICON 600/48
Nominal Power 600 kw
Rotor Diameter 48 meters
Hub Height 46 meters
Cut in wind speed 4 m/s
Cut out wind speed 25 m/s
Manufacturer NEG
Source: DWIA , 2002
The manufacturer’s power curve for the selected turbine is shown in Figure 4-7. The data
also comes from the WPTC, (DWIA,2002).
Figure 4-7: Power Curve for the selected NEG MICON 600/48 turbine
Finally, the WTPC displays the power calculation results for the selected turbine working
with the entered wind distribution and at the selected site. Table 4.5 presents those results for the
present calculation.
Table 4.5: Results of the WTPC for a single NEG MICON 600/48 working at the site
Mean Velocity Shape Power Density Turbine’s Capacity
[m/s] Parameter [W/m2] Energy output Factor
[kWh/year]
7.15 1.62 82 1300732 24.7%
Source: DWIA , 2002
44
By taking into account the recommendation for spacing wind turbines, the number of
turbines and their rotor diameter the wind farm area could be nearly 2 square Kms. However, in
the real case the layout would be determined by the wind potential at specific points.
Table 4.6: Main Features of the wind farm according to the preliminary design
Turbines NEG MICON 600/48
Number of turbines 24
Installed Capacity 14.4 MW
Annual Energy Output 31217568 kwh/year
Source: DWIA , 2002
45
After using the wind power calculator the turbines NEG MICON 600/48 were chosen.
Twenty four turbines were selected for the farm in order to decrease the transportation cost,
consultants wages and maximize the energy output and work inside investment values for Energy
Projetcs common in Ecuador (H. Consejo Provincial de Loja, 2003). The available area for the
wind energy is not known but is not considered to be a limiting factor for reasons explained in the
technical analysis.
For the feasibility phase the amount of money varies with the number of turbines placed in
the region with possible wind potential. According to José Aguirre (2003), Renewable Energy
Coordinator from the Loja Project, the cost of 50 m high towers that support the anemometers, in
the country is around 4000 USD. Moreover, the price of the anemometer, wind direction meter,
barometer, and data logger for each tower varies from 10,000 to 13,000 USD according to the
manufacturer. The rest of the investment is required in labor.
Table 5.1: Investment required in the Feasibility Phase
Description Units USD/unit Total
Tower construction 6 4000 24000
Equipment 6 13000 78000
Labor 1 16000 16000
Total 118000
For the construction phase the investment costs increase drastically. For instance, for the
construction of a 10.8 MW- project in Salinas, Electroviento (2002) estimated that the total
47
required investment was 14.3 M USD. The investment distribution is the following: turbines
(65.1%) custom duties (3.3%), marine transportation (4.7%), land transportation (3.3%), civil
works(2.5%), grid connection (14.4%), permissions (0.3%) and studies ( 7.2%) (PROVIENTO,
2000).
On the other hand, according to the Beurskens and Hjuler (2001) article for onshore wind
farms up to 8 MW the cost distribution is the following: turbine manufacture 80%, transportation,
installation and infrastructure 15%, project development that includes permits, insurance, land
property 5%. It is important to know the cost of each kW installed in situ. A good illustration of
this is the wind energy program carried out in Costa Rica that has an installed capacity of 20 MW
and had a cost of 18 M USD (International Development and Energy Associates, 1992) . In other
words the cost of each kW installed was 900 USD. Nevertheless, according to the Electroviento
(2002) information, the installation cost is 1324 USD/ kW installed, which is expensive, especially
the description of studies, which has a high percentage in the investment cost.
Additionally the report of Vicky Pollard (2000), in the Renewable Energy magazine
analyses the cost of each kW installed. For instance, in the year 2000 the cost is 925 Euro/kW
and for the year 2010 it is forecasted to be 700 Euro/ kW. For these arguments, it is difficult to
believe that the cost of each kW installed in Salinas would be 1324 USD/kW taking into account
that the analysis was carried out at the end of 2002. For the Loja project, located in Ecuador the
expected investment is 15 M USD approximately for a 15 MW project. This means that the cost
of each kW in another Ecuadorian place is around 1000 USD/kW installed.( Consejo Provincial
de Loja, 2003)
Based on the information of one of Costa Rica’s wind energy projects, the Ecuadorian
Loja project and Pollard’s projections, some modifications have been made to the cost presented
by Electroviento. The reference for establishing the costs will be the unitary cost of each kW
installed. By doing this analysis for the case of Mira that will have an installed capacity of 14.4
MW, the investment cost for the feasibility phase for the setting of 6 towers and all the electronic
equipment, and the labor cost is 11.800 USD. For the construction phase, the investment is
48
14,070,460 USD, which produces an installed cost of 977.1 USD/ kW but it is still higher than
the Costa Rica’s project; however, it is lower than the one proposed by Electroviento.
For the Mira project the cost distribution for the feasibility phase is shown in Table 5.1.
For the construction phase the cost distribution is presented in Table 5.2, this table does not
include the cost of studies but it includes the interconnection to the substation located in the Chota
valley at about 20 Km from Mira (ELECTROVIENTO, 2002).
Table 5.2: Investment required in the Construction Phase
Description Units USD/unit Total
Turbines 600 [kW] 24 420000 10080000
Custon Duties* 24 21000 504000
Sea Transportation 1 787260 787260
Land Transportation 24 18200,0 436800
Income tax 0% 0
Cementation 24 10000 240000
Access road 24 5000 120000
Grid Connection 1 1800000 1800000
Permissions, Consultants 1 52400 52400
Crane 10 5000 50000
Studies, Supervision 24 0 0
Total Investment 14070460
* Considering a duty rate of 5%
Estimated life span of the project: 20 years.
Salvage value: 40,000 USD for each turbine after the life span of the project.
In addition to the investment cost there are recurrent expenses that will be presented
throughout the life time of the project, and are related to operational and maintenance costs. These
costs are presented in Table 5.3.
Table 5.3: Operational and maintenance costs
Description Units USD/unit Total
Maintenance 3000 24 72000
Spare parts & material 100800
Insurance 4000 24 96000
Reduced insurance 0
Management 40000
49
Accountancy 10000
Rent of landuse(1) 10000
Rent of landuse(2) 8000
Miscellaneous costs 10000
Reserves for removal 3000
Total 349800
In order to determine ACE it is required to work on a yearly base, which can be the first
year once the project enters into operation. It is required to translate the feasibility investment, the
construction investment and the salvage value to the base year by using the following formula.
FV = PV * (1 + i )
t
Where:
FV means money after a time t (future value)
PV means money in the time t = 0 (present value)
i = the loan interest rate. There are different cases presented in this chapter as a function of this
value.
By doing this and using an interest rate of 7% the value of investments and the salvage
value (TIS) in the base year is equal to 13,004,946 USD. A life span of 20 years is assumed,
which is common for wind energy projects (Ringius at al, 2002). The annualized value (AV) of the
total investments and the salvage value are calculated by using the following formula:
50
i
AV = TIS *
1
1−
(1 + i )
t
Where:
i = the loan interest rate.
t = the life time of the project, 20 years.
By using data AV = 1227575 USD/ year
ACE is equal to AV plus the cost of operation and maintenance. Therefore:
ACE = 1227575 + 349800
ACE = 1577375 USD /year
The outputs from NEG MICON 600/48 wind turbines subjected to a mean wind velocity of
7.15 m/s and a shape parameter of 1.62 are the following:
• Energy output =1364182 kwh / year /turbine
• Capacity factor = 25.93%
• Number of Selected turbines = 24
• Considering a Technical availability1 of 95%
• Total energy production = Number of turbines* Output of each turbine* technical
availability
TEP = 31103349,6 kW - h / year
1577375 [USD]
UCE = = 0.0507 USD / kWh
31103349.6 [kW − h ]
1 A technical availability of 95% means the turbines will work the whole year except for 5% due to maintenance or other
factors.
51
Other Outputs
Internal Rate of Return = 12.28%
Net Present Value =6,410,429 USD (In the year of the construction phase)
Payback period = 10.77 years
There are always uncertainties with regard to the interest rate whose value makes the
project more or less attractive. Table 5.4 presents the changes in the UCE, internal rate of return,
net present value and payback period if the interest rate changes.
5.5.2 CDM
In addition, Table 5.4 includes the changes in the economic analysis output if the project is
subjected to CDM negotiations, that means the selling of Carbon Emission Reductions (CREs).
For this analysis, it is considered that the wind power plant will substitute a thermal plant that
works with diesel with an efficiency of 33%. Therefore, the generation of each MWh of electricity
using wind energy will avoid the production of 0.785-ton CO2/ MWh. According to David Neira,
representative of CORDELIM (Corporation for Clean Development in Ecuador), the price of
52
each credit or ton of CO2 reduced is 3 USD. In other words for the 14.4 MW project considered
the CO2 selling would increase the profits by 73,249 USD yearly.
Table 5.4: UCE, IRR and payback periods working with different interests rates.
Interest rate 5,0% 5,0% 7,0% 7, 0% 9,0% 9,0% 11,0%
CO2 sales NO YES NO YES NO YES YES
UCE 0,0452 0,0452 0,0507 0,0507 0,0565 0,0565 0,0623
IRR 13,68% 14,27% 12,28% 12,88% 10,79% 11,40% 9,85%
NPV 12269374 13182218 6410429 7186430 1884284 2552941 -1072728
Pay back period 8,5 8,1 10,8 10,2 15,3 14,1 22,2
On the other hand, table 5.5 presents the changes in the investment required and the cost
of each kW installed by changing the number of 600 kW-turbines. All of this is made considering
no carbon credits sales, and using an interest rate of 7%. As table 5.5 shows the investment is
proportional to the number of installed turbines. However, the cost of each kW installed increases
while the number of turbine decreases, this is due to the economics of scale of wind farms mainly
related to overhead and transportation costs. By having a wind farm of an installed capacity lower
than 7.2 MW, the project does not become attractive, economically speaking.
Table 5.5: Economic indexes varying the number of turbines of 600 kW
Number of Turbines 24 20 16 12 10 8
Installed Capacity [MW] 14,4 12,0 9,6 7,2 6,0 4,8
UCE 0,0507 0,0528 0,0560 0,0613 0,0655 0,0718
IRR 12,28% 11,14% 9,53% 7,09% 5,29% 2,76%
NPV 6410429 4293558 2176686 59814 -998622 -2057058
Cost kW installed 977.1 1014.5 1070.5 1163.9 1238.6 1350.7
Investment 14,070,460 12,173,660 10,276,860 8,380,060 7,431,660 6,483,260
The Cost of kW installed is an important variable that affects the economic feasibility of
the project. If this value is high, that means a high investment, the project does not become
economically attractive. Table 5.7 includes an analysis considering purchase of CREs.
53
Table 5.6: Economic indexes considering no sales of CRES varying the Cost of kW installed
Cost kW installed 977 1000 1100 1200 1300
UCE 0,051 0,052 0,056 0,061 0,065
Price kWh 0,113 0,113 0,113 0,113 0,113
Price ton CO2 0 0 0 0 0
Interest rate 7,0% 7,0% 7,0% 7,0% 7,0%
IRR 12,3% 11,7% 9,1% 6,9% 4,9%
NPV 6410429 5739504 2809593 -123396 -3053307
Cost kW installed 977 1000 1100 1200 1300
Pay back period 10,77 11,40 14,43 18,00 22,25
CO2 avoid t/ year 24416 24416 24416 24416 24416
CO2 selling 0 0 0 0 0
Income 1921752 1889535 1748843 1608004 1467313
Table 5.7: Economic indexes considering purchase of CRES varying the Cost of kW installed
Cost kW installed 977 1000 1100 1200 1300
UCE 0,051 0,052 0,056 6,08% 6,53%
Price kWh 0,113 0,113 0,113 0,1 0,1
Price ton CO2 3 3 3 3 3
Interest rate 7,0% 7,0% 7,0% 7,0% 7,0%
IRR 12,9% 12,2% 9,7% 7,5% 5,4%
NPV 7186430 6515505 3585594 652605 -2277306
Pay back period 10,19 10,79 13,66 17,00879 20,96564
CO2 avoid t/ year 24416 24416 24416 24416 24416
CO2 selling 73249 73249 73249 73249 73249
Income without CRE 1921752 1889535 1748843 1608004 1467313
Income with CRE 1995001 1962784 1822092 1681253 1540562
54
Mira
55
The temporal boundary will be taken to be 3 years for the construction phase, 20 years for the
operational phase, and 2 years for decommissioning. All of these values are estimates and based
on the literature including the Nai Kun Wind Farm EIA Study Design (Pottinger Gaherty Group,
2002).
The visual impact is one of the most notable environmental impacts of wind turbines. There
are no mitigation possibilities for visual impacts so the configuration and layout of the farm must be
considered from the very beginning of the project so that this factor can be taken into account and
minimized. The Irish Energy Centre (2003) recommends the following guidelines for minimizing
the visual impact:
• Areas of unique scenic beauty are not recommended as wind farm sites
• Turbine layout should avoid turbines appearing one behind the other from main visibility
points
• Consider local screening (e.g. with tree plantings) from some local points of visibility within
1 – 2 km of wind farm
• Turbines should be painted off-white or light gray with a matt finish
• Blades should be left to spin when the turbines are off
• The number of machines should reflect the landscape of the site
• Non-linear layouts may be more suitable where the topography is uneven
• All the turbines should be of similar size and design, with blades rotating in the same
direction
56
While the area is not a heavily trafficked area in terms of tourism, the hot springs in the near
vicinity could eventually draw visitors, especially if the armed conflict near the Colombian border
can be resolved. It is important to keep in mind the visibility of the wind farm from the tourist
centers so as to avoid adverse visual impact.
Figure 6.2: Probable Location for the Wind Farm
There are two types of noise generated by wind turbines: aerodynamic (the movement of the
blades in the wind) and mechanical (noise generated by the turning of gears or other parts).
Mechanical noise can be reduced to a negligible level using proven engineering techniques and a
number of turbines on the market have imperceptible levels of mechanical noise when compared
to the aerodynamic noise. The aerodynamic noise is more difficult to mitigate but improved
aerodynamic designs have been done that reduce the noise to reasonable levels. The table below
shows the noise levels for different activities including wind turbines.
57
Threshold of hearing 0
Rural night-time background 30-40
Quiet bedroom 35
Wind farm at 350m 35-45
Car at 40mph at 100m 55
Busy general office 60
Truck at 30mph at 100m 65
Pneumatic drill at 7m 95
Source: Irish Energy Centre, 2003
According to the Irish Energy Centre (2003), the noise level at the center of a wind farm is
from 50 to 60 dB and the single greatest factor in determining the impact of noise is distance. It is
estimated that beyond 400m there is unlikely to be any significant effect.
The threat to birds due to bird strike is generally considered to be quite small in properly
sited wind farms (DTI, 2003). Studies carried out at operational wind farms in the UK indicate
that in general, birds live in harmony with wind turbines (DTI, 2003). Additionally, a number of
studies have been carried out in America and Europe with the following situation being sited in one
study: “At a near-shore Danish wind farm, which borders a sensitive, protected site for Eider
Ducks, it was found that approximately 1% of bird deaths were due to collision with wind
turbines. This was a three year study, followed by a further two year monitoring study, which
confirmed its findings.” (Irish Energy Centre, 2003).
Wind farms have been found to pose little or no threat to other wildlife or fauna since they
occupy only 2 to 3% of the land area of the farm. In a number of cases livestock have been found
to graze right up to the towers. However, for a new project, the impact on the flora and fauna
should be analyzed by a qualified ecologist especially in terms of the access roads and
construction activities.
58
The construction phase will be the phase of highest environmental and social impact. The
social impact of having outsider workers in the area could be great and if not planned and
controlled, it could be very negative. Likewise, it will be the time of greatest earth moving in terms
of access roads and foundation building for the towers. But the construction phase is temporary
and if proper mitigating strategies and remedial measures are taken, there is no reason why lasting
adverse effects should be produced.
Wind turbines generate electric-magnetic fields (EMF) on the same scale as a diesel
generator and would have a very minor impact on humans especially since the turbines are high
above the ground and further from the potential receptor. All European and American electrical
equipment is required to meet strict standards for electro-magnetic radiation and most of the wind
turbines sold today are fit to enter those markets.
Of more concern is the effect wind turbines could have on electro-magnetic signals emitted
elsewhere. This occurs due to the physical blocking of the signal by the blades or by the blades
acting as an unwanted relay transmitter. This is highly unlikely and according to the Irish Energy
Center (2003), this effect has not been found in any of the 22 wind farms in Ireland. The kinds of
signals potentially affected include microwave signals, mobile phone signals, radar and air traffic
control signals, and UHF or VHF television signals.
Despite the low probability of impact, this potential impact should not be overlooked
especially if an airport is nearby. Figure 6.1 shows that the nearest airport to the district of Mira is
in the city of Ibarra, which is more than 50km away and according to the figures from the Irish
Energy Centre (2003) that is a safe distance since the effects described here usually only happen
at a maximum of 2km.
59
During the installation phase, the turbines and towers can be transported by sea to the
ports of Guayaquil or Esmeraldas. The road connecting Esmeraldas, San Lorenzo, and Ibarra will
facilitate transportation from the coast to the Project site because it is shorter than the road to
Guayaquil. In the immediate area where the project will be installed there is a need to build access
roads and platforms for the cranes and cement trucks and small storage buildings for supplies and
materials.
The access roads will be constructed prior to the construction phase but will remain in use
for the life of the wind farm. The access roads have the highest potential for negative
environmental impact and a similarly high potential for positive socio-economic impact. The roads
must be constructed with careful attention being paid to erosion, waterways and potential positive
social impacts that could be created.
Based on the fact that a conventional thermoelectric power plant consumes one gallon of
diesel fuel to generate 10 kWh, the project will avoid the use of more than 3.1 million gallons per
year at the 31 GWh/year energy production calculated in the economic analysis section. Since at
present Ecuador imports part of its diesel the project will save not only valuable natural resources
but also foreign currencies which would have been spent in the importation of diesel. The project,
60
due to its special curve of daily production will replace in first degree the cost of expensive and
contaminating thermoelectric power plants operating in Ecuador’s national energy grid system.
Studies performed by CONELEC indicate that the mean contamination level of the power
plants working in Ecuador is 0,775 ton of CO2/MWh per year. The project will therefore avoid a
contamination of 24,025 tons of CO2 per year. Over the lifetime of the project, this will mean
avoidance of 480,500 tons of CO2.
The Project will offer many temporary jobs during the construction phase, as well as a
range of permanent jobs during its 20-year life span (very important in this rural area).
In addition, aesthetically, a wind turbine array (with 48 m diameter blades turning silently at
a height of 40 meters), is nothing short of spectacular. Considering that there are no equivalent
projects in Colombia or Peru, the area may become a tourist site bringing many additional dollars
into the economy of the district of Mira.
A large number of non-native plants were seeded in cultivatable lands and became part of
the flora diversity of the region. Among the most common crops are potatoes (Solanum
tuberosum, Solanaceae), melloco (Ullucus tuberosus, Basellaceae), oca (Oxalis tuberosa,
Oxalidaceae). Other crops are corn (Zea mays, Poaceae), la quinoa (Chenopodium quinoa,
Chenopodiaceae) and different varieties of beans with commercial value.
The native fauna of the region can comprise the following species which are common in the
High Andean Grasslands Areas (Paramos).
Table 6.3: Principal native fauna species.
Community Name Scientific Name
Lobo de páramo* Psudalopex culpaeus
Curiquingue Phaalcoenus carunculatus
Conejo silvestre* Syilvilagus brasiliensis
Ligle Vanellus resplendens
Zorro
Fucungo
Mirlo
Raposa
Chucuri
Rana
Sapo
Guamanito
Perdíz
Solitario
Source: UNORIG (1999). *in danger of extinction
However, the situation in the area is highly changed from its natural state with the inhabitants in the
area relying on a wide variety of introduced species (cattle, poultry, dogs, cats, etc) which
displaced the native fauna.
62
Article 63.-
“The State will foment the development and use of non conventional energy
resources through the public organisms, development banking, universities and
private institutions.”
Article 64.-
“The National Council of Electricity (CONELEC) will dictate norms that can be
applied for the dispatch of electricity produced with non-conventional energies
looking for its utilization and priority.”
Moreover, in the Regulation for the Ecuadorian Wholesale Electricity Market, article 21 states:
Article 21
“The preferring dispatch of power plants that use non-conventional renewable
energies, by the National Centre for Control of Energy (CENACE), could not exceed
2% of the installed capacity of the generators of the Electricity Market.”
All the energy coming from renewable non-conventional sources given to the
National Interconnected System (SNI) will not be a part of the economic dispatch;
this is, its costs will not be taken into account for fixing the marginal cost.
“CONELEC will establish the prices that CENACE will use to assess the production
of each one of the power plants, on the basis of international references, which total
63
“...The preferring and obligatory dispatch will be made by the power plant and the
prices of energy will not be taken into account to determine the marginal cost per
hour in the Wholesale Electricity Market.”
Price of Energy
The prices to be considered for the energy measured at the point of delivery,
expressed in cents of USA dollars per kWh, for wind power energy is of 10.05
cUSD/kWh. In order to stabilize the income of the energy delivered, these prices will
be valid for a ten-year period, starting at present date of the regulation, for the
power plants entering into operation until the year 2004. After this timeframe, the
prices fixed by CONELEC for the next years will prevail. No payment will be
considered for the power to the production of non-conventional power plants.
Additional Payment for Transportation
An additional payment is established for transportation, in the case that a line of
transmission will be required from the Generation Power Plant to the point of
64
connection to the SNI, this payment is of 0.06 cUSD/kWh/km, with a maximum limit
of 1.5 cUSD/kwh.
• To transfer or to remit abroad of its utilities, previous the compliance with the pertinent
legal norms.
• The concession contract shall give in some of its clauses security to the investors for future
changes in the laws or rules, maintaining the economic and financial stability of the project.
• Legal mechanisms for resolution of controversies.
Article 3 of the Electric Sector Law states that energy generators, transmitters and
distributors of electricity will obey the legal regulations pertaining to environmental protection. To
comply with this edict each sector of the industry should prepare an independent environmental
impact evaluation study to determine the environmental impacts during the construction, operation
and abandonment of electric projects. These studies must include mitigation and/or recovery plans
of affected areas and a cost analysis.
The definition of an EIA is described in the:
• Regulation of the Electric Sector Law, Chapter III
• Regulation of Concessions and Permits, section IV, art. 35
The Environmental Regulation for electric activities is the legal document that establishes
and regulates the content, reach and development of an EIA. This regulation includes the following
sections:
This chapter defines the areas of competence of CONELEC (art. 7). The administrative
relationship between CONELEC and other State organizations to establish areas of coordination,
cooperation and competence. (arts. 8,9,10,11).
67
Section 3 establishes the obligations of concession holders, permit owners etc. (art. 13).
This chapter is the most important regarding environmental issues as it establishes norms
for different parameters within the project (arts. 14, 15). It also establishes the required prevention
and mitigation techniques to reduce the environmental impacts.
This chapter establishes the characteristics and content of EIA’s and environmental
management plans (arts. 17, 18, 19, 20, 21, 22, 23, 24, 25). It also defines the type and
characteristics of environmental audits (arts. 26, 27, 28, 29, 30).
This section describes the procedures required for companies who wish to obtain
concessions, permits and licenses.
The following table provides a brief outline of the current environmental regulations in
Ecuador:
Table 7.1: Current Environmental Regulations in Ecuador.
Law or regulation Document
Security and Health Regulations for workers RO 565 November 17, 1986
and the improvement of the working
environment
Regulation for the prevention of pollution to RO 204 June 5, 1989
water resources
Regulation for prevention and control of the RO 560, November 12, 1990
environmental pollution by noise.
Regulation of Air Quality and measurement RO 726, July 15, 1991
methods
Regulation for Solid Waste disposal RO 991, August 3, 1992
Regulation on general norms of emission for Supplement of the RO 303, October 25, 1993
fixed sources of combustion and general
measurement methods
Regulation for collection and transport of RO 360, January 17, 1994
recyclable paper
Basic Environmental Policies of Ecuador DE 1802, June 1, 1994, published in the RO
456, June 7, 1994
Environmental Management Law RO 245, July 30 1999
Source: Ministry of Environment
7.6.1 General
The Constitution guarantees the investments of foreign or national firms especially when
they are destined for production of goods to be consumed nationally and those to be exported
(Article 244). It also gives special guarantees to investments made in less developed areas or
areas of national interest.
The Law of Companies establishes the different kinds of companies that can be formed
and puts forth the requirement for foreign companies operating within the national territory. There
are a number of opportunities for private companies in Ecuador in terms of the legislation and the
69
continual opening of the economy based on the Law of Modernization of the State and the
TROLE I (Law of Economic Transformation) & TROLE II (Law for the promotion of investment
and public participation).
Article 246 of the Constitution states that the government will promote community
companies such as cooperatives, craft workshops, councils to administer potable water whose
property and management belongs to the community or the people who work permanently in
them. The Law of Cooperatives governs how cooperatives are formed and how they operate.
The Ministry of Social Welfare is assigned the responsibility to study and approve proposals for
the formation of Cooperatives (Article 7, Law of Cooperatives). Depending on the activity that
the cooperative is going to carry out, it must belong to one of the following categories: production,
consumption, savings and loans or services.
Article 102 of the Law of Cooperatives provides for the free development and autonomy of
cooperatives based on the fact that the state views these organizations as positive for economic,
social and moral development of the country. Based on that, cooperatives are given the following
benefits: (1) exemption from fiscal, municipal, or any other tax on immovable estates purchased by
the cooperative, (2) preference in bidding on projects from state, municipal or other organisms,
(3) liberalization from taxes on tools, machinery or other inputs to the cooperative, (4) exemption
from export taxes on goods produced by artistic or craft based cooperatives, and (5) preference
in expropriation of land in favor of cooperatives formed by peasants.
70
the state and of external pressures in terms of possibilities for funding. In the next sections the
different implementation mechanisms will be discussed.
importance of the training process in BOOT projects in developing countries to develop local
capabilities and to make the transfer process feasible. It is probably safe to discount the
possibility of using DBO since for the case of the wind farm in question, this contractual type is not
advisable because there is not the sufficient experience and know-how in the government or
community to take on full responsibility of the wind farm upon commissioning.
Since the different contractual types are similar in most respects with the only differences
being whether or not the assets are transferred and if so when in the process that happens, the
following discussion will focus on the BOOT mechanism and its variants will be discussed where
appropriate.
There is some debate in the literature about whether a BOO is preferable over a BOOT
contract. Mathrani (1990) argues that the transfer requirement often complicates the contract and
makes financing more difficult and reduces the number of potential genuine long-term investors.
According to him “The need to value and transfer the assets at the end of the concession period
exacerbates the problem, because it tends to decrease the value of the assets and thus the
attractiveness of BOOT projects” (Mathrani, 1990, pg 2-3). Both Mathrani (1990) and Churchill
(1991) argue the importance of bringing projects to capital markets so that local investors can
invest in them. Churchill offers an alternative to transferring the project that will assist in
developing capital markets. He states “Rather than transferring a plant back to the public
monopoly, which has done so poorly in running that type of plant in the past, the foreign
shareholders in the plant would be expected to divest themselves of their stock, up to some
negotiated percentage.” (Churchill, 1991, pg 86). In this way, ownership is transferred rather than
the plant, which helps develop the local capital market. In his opinion, the primary objective of
these contracts should not be to build another plant but to develop capital markets. He points out
that typically, in the highly indebted Latin American countries, there is a savings rate of 18% of the
GNP compared to only 8% in the United States. These savings are not being mobilized for
development purposes but could be if legitimate investment opportunities were available.
74
According to Arndt (1999), in BOOT projects there is usually no one single entity looking
to take on the project so a consortium of different companies is developed. Figure 1 below
shows the general arrangement of such a consortium. The sponsor is usually a lead participant
and may often be a construction company seeking work. Debt and Equity providers also become
part of the consortium with the debt provider being banks or other purchasers of capital market
instruments such as bonds. The sponsors and contractors are often times equity providers but
other investors may also take part as pure equity investors. The operators, contractors and
advisers also form part of the consortium. It is important to recognize that these consortia
members are far from homogeneous which can complicate negotiations with the public sector.
Figure 8-1: Typical BOOT Consortium
The other contractual types, namely BOO and DBO, would have a similar structure. For
the case of DBO, the asset would be transferred to the government before commissioning for an
agreed upon price.
Ferrigno defines successful packaging of this type of project as “getting all of the political,
technical, commercial and financial elements of a project together so that adequate funds have
75
been committed and advanced to the project company and construction has started.” (Ferrigno,
1990, pg 3-1). The prerequisites that he claims are necessary are the following:
• There must be a high need for the project which has been perceived for years by
government officials
• There are inadequate government funds available and there is sufficient political will to
utilize the private sector
• There are highly credible contractors and suppliers that are willing to enter into a turnkey
design/construction contract with firm prices and completion terms;
• It is believed that the private sector possesses all of the technical expertise to design, build
and operate the project;
• The project is considered financeable on a limited-recourse basis.
Another question that needs to be answered is how big should the project be before it
qualifies for a BOOT contract? According to Moore (1990) the minimum investment that Asea-
Brown-Boveri (ABB) will make in a project is half a million to three quarters of a million dollars
whether it is a 50 MW hydro station or a 1000MW coal fired station. This is from the equipment
manufacturer or developers viewpoint but the investors or suppliers have a different perspective.
According to Strzelecki (1990, pg 6-25), from the view point of the investor or supplier, “the
minimum size of BOOT project that is worthwhile developing in the international market is about
150 MW”. He claims that anything smaller is a dilution of resources and larger projects can more
easily carry the overhead costs. But he acknowledges that the minimum size that will attract
interest depends on the options available. However, he is speaking of thermoelectric plants that
have a much higher operating cost due to the expenses related to fuel and the accompanying
supply risks. These issues were discussed in more depth in the economic analysis section.
For all of the parties to be satisfied with the contract, they must feel that they are not taking
on a disproportionate share of the risk. For this reason, the allocation of risks is a crucial element
in developing a successful BOOT project (Phillips, 1991). The main risks in a BOOT project are
76
1) there is a finite concession or franchise period in which to recover costs, 2) there are political
and economic risks due to a single buyer – the state owned electric utility, 3) foreign exchange and
convertibility risks, and 4) few OECD countries have domestic private sector power companies
so there are few private players interested in those concessions (Mathrani, 1990). The fourth risk
is no longer as much of a problem as it was in 1990 when Mathrani published that article and a
number of countries have privatized their energy sectors; the situation for wind energy is especially
exempt from this problem since most developers are private companies. For the case of Ecuador,
the third risk is non-existent due to the change of national currency to the dollar in the year 2000.
The second risk will continue to be a risk due to the fact that the electric transmission
infrastructure is a natural monopoly. The first risk of the finite concession period could be averted
by using a BOO contract instead of a BOOT contract and requiring the initial investors to divest a
certain percentage of their shares to local capital markets, the government or a community
cooperative after an agreed period.
The risks associated with the project can be further broken down into the following periods:
pre-commissioning, post-commissioning, and project lifetime risks. The risks associated with
each period are shown in the table below.
Table 8.1: BOOT Project risks divided into stages.
Pre-Commissioning Risks Post-Commissioning Risks Project Lifetime Risks
Abortion of project by shareholders Output Shortfalls due to: Foreign exchange rates
Late start-up - Physical Damage Increased interest rates
Cost overruns - Strikes Nationalization
Delays from Force Majeure - General operational reasons Expropriation
Damage - Inadequate fuel supply Delays in commissioning
Bankruptcy of shareholders or Lower offtake than desired Shareholders do not fulfill their
suppliers joint venture responsibilities
Fuel supply infrastructure problemsPower prices lower than forecasted General political risks – change in
taxation conditions,
Gov. requirements – customs, Inflation and operational costs higher - abrogation of foreign
procurement and construction labor than forecasted purchase agreements
Gov. action – import restrictions, tax - Changes in requirements for
regime, safety or environmental indigenous involvement.
regulations, fuel supply arrangements
Source: Mathanri, 1990.
Moore (1990) discusses how the risks should be allocated to the different partners from the
developers perspective. He divides the risks into market risks, sovereign risks, project risks, and
77
commercial risks. He states “ABB is, without hesitation, willing to take the risks of plant
availability, output and performance, but is unwilling to take the risks of expropriation and any of
the components of sovereign risk, unless sufficient benefits are offered to offset such risks” (
Moore, 1990, pg 7-6). For ABB, a private power company, the optimal distribution of the risks
is as follows: the utility should take the market risk, the multi-lateral agencies and bi-lateral
agencies should take the sovereign risks, the lenders should take the project risks and the private
power company should take the commercial risks.
Some of the government agencies in Ecuador that need to be involved, by law, in the
development of this project have been identified in the Legal Framework section of this report. In
general, CONELEC is responsible for granting concessions to generation plants, signing purchase
agreements for the energy from non-conventional power plants and setting prices that the
generators and distributors will be paid (CONELEC, 2001). CONELEC is also responsible for
dividing and selling the state owned generators. The state, however, does maintain ownership in a
number of generators and there may be interest for the state to purchase shares in the new
development with the shares going into the Fondo de Solidaridad. TRANSELECTRIC is the
state owned transmission company but all agreements and contracts are signed through
CONELEC.
The World Bank has been motivated into new partnerships such as the GEF-World Bank
Group Strategic Partnership for Renewable Energy, which uses Adaptable Program Loans
(APL) to permit flexible project support over periods of up to 10 years (Saghir, 2002). Another
such partnership is the Renewable Energy and Energy Efficiency Fund, which is the first global
private equity fund dedicated entirely to investments in renewable energy and energy efficiency
(Saghir, 2002). Some of the World Bank programs specifically geared towards sustainable
energy are shown in Table 8.2.
Table 8.2: World Bank Programs for Sustainable Energy.
Entity Implementing Agency Geographic Focus
IBRD/IDA Lending WB Global
GEF WB UNDP UNEP Global
ESMAP WB UNDP Global
ASTAE WB Asia
AFFREI/RPTES WB Africa
SDC WB IFC Foundations Global
IFC – REEF PVMTI RE Financing WB Commercial banks Fund/Project Dependant
SME Foundations
Prototype Carbon Fund WB Global
Source: Saupin, 2000
79
The International Development Bank has set aside a family of untied trust funds to support
the preparation of Sustainable Energy and Urban Transportation projects in Latin America called
the Hemispheric Sustainable Energy and Transportation Funds (HSET) (IDB, 2003). In
order for a project to be eligible for these trust funds, it must meet the following criteria:
• Sited in a borrowing member country of IDB
• Well developed in structure and location
• Strong emphasis on a role for the private sector
• Clear support from private and public partners
• Consistent with the countries priorities and the Banks investment priorities.
The institutions eligible for receiving these funds are national governments and their political
subdivisions, NGO’s, and private entities with the legal authority to borrow such funds.
According to Saupin (2000), “The IFC's Renewable Energy and Energy Efficiency Fund
(REEF) is expected to be the first global fund dedicated to investing in private sector renewable
energy and energy efficiency in developing countries.” The fund provides from 150 million to 210
million USD of IFC and private capital for financing projects of less than 50 MW.
National Banks within the country of development can also be approached for funding but
the project developer must be careful to negotiate a reasonable interest rate since some of these
banks often times require high interests for repayment of the loan.
Other private banks in other nations such as Fortis Bank in England provide specialized
services for wind energy developments and may be able to offer loans with interest rates lower
than national banks.
A number of countries also have Export Credit Agencies (ECA) with the mission of
helping their national companies expand their markets abroad through the provision of credits for
the purchase of their equipment. This mechanism has been used extensively in technology transfer
and could be used in this case as well.
80
8.4.3 Investors
In many projects, the project participants themselves may invest in the project as indicated
in section 8.2.2. Some of the wind energy companies discussed in the next section provide
financial services as well as technical and managerial services.
If the project is placed under the responsibility of a publicly traded company or
consortium, funding can be raised through a stock market by selling shares in the company. This
would help to develop capital markets in the nation as discussed earlier. Ecuador does have a
stock market but its effectiveness is not clear. Their web site is not developed and there appears
to be very little information on it. However, it may not be necessary to have a functional stock
market to divide shares in a corporation, using Over The Counter (OTC) traded shares instead
(Howstuffworks, 2003). In this model, the community, individuals or the municipality could be
part owner in the project depending on their ability to contribute funds or buy shares. This,
however, has the obvious difficulty of giving more opportunities to those who already have
resources to invest.
Additionally, there are a number of Social Funds in developed nations that offer
opportunities for people to invest in ecological funds. One such fund is a Green Loan Fund that
supports environmental enterprises in Latin America offered through EcoLogic Enterprise Funds.
This fund provides small business loans to firms in Latin America whose business activities support
biodiversity conservation and equitable development (SocialFunds.com, 2003).
The manufacturers of Wind Turbines frequently offer installation and other services related
to a wind farm project. The list of companies involved in the wind industry from data logging to
training includes over 1000 entries in the Renewable Energy World Directory of Suppliers
(REW, 2001). The world’s top ten manufacturers, in terms of megawatts sold, include Vestas (in
the lead with 17.9% of market), Bonus, Nordex, Gamesa, Ecotecnia, DeWind, Suzlon, NEG
Micon, Enron Wind Corporation, and MADE (BTM Consult, 2001). In 2001, these companies
had 91.8% of the market.
81
The table above lists some of the firms involved in Wind Energy and their services.
The small selection of firms shown in Table 8.2 demonstrates the diversity of services
offered by different companies in the wind industry. It is clear that the wind industry opens a wide
array of opportunities for the private sector and depending on the competencies of the firm or
agency executing the wind farm, different levels of services can be sought from a wide range of
firms in the industry. For example, if it was determined that the government were going to develop
the wind farm, they could purchase a turnkey wind farm from firms such as Nordex or SeaWest.
82
There are a number of bi-lateral and multi-lateral agencies that could contribute to this
project. For example, the German government has a wind energy program called TERNA. It is
administered through GTZ and is aimed at helping to develop and fund wind park programs in
developing nations. They will either work through the Energy Ministries in a given country or
directly with private industries to develop wind energy capacity in developing nations (GTZ,
2003). Alongside the TERNA program, GTZ also offers risk sharing in Public-Private
Partnership projects through its PPP program (GTZ, 2003). The risk sharing service works like
an insurance that only gets paid out if something goes wrong.
The United States government also offers support for development through its USAID
agency. There is a specific program called “Ecuador Northern Border Development” with a
strategic objective of improving the quality of life of the population living along the northern border
of Ecuador. USAID uses Andean Counterdrug Initiative (ACI) funds and Economic Support
Funds (ESF) to develop projects related to water and sanitation systems, roads, bridges, irrigation
and small energy projects (USAID, 2003).
The Global Environmental Facility (GEF) is a financial mechanism for providing grants and
concessional funding for projects in developing countries that contribute to protecting the worlds
environment (Saupin, 2000). The GEF has a mandate to link its efforts with national sustainable
development efforts and complement regular development assistance funding, not replace it. As
indicated in section 8.4.2, GEF works closely with the World Bank and Table 8.4 shows some of
the investments made by GEF and the WB in Renewable Energy Throughout the World.
83
The Danish International Development Cooperation Agency has helped to fund wind
power developments in India (Terim, 2003). Other national development agencies that might
contribute to wind power developments are the Canadian International Development Agency
(CIDA) and the Swedish International Development Agency. However, to secure funds from
these agencies one of the criteria is often that a private sector company from that nation must be
involved in the project.
Unfortunately, there is no such scheme in place in Ecuador for SO2 and NOx but a new
development stemming from the activities of the UNFCCC and the countries that have ratified the
84
Kyoto Protocol could offer opportunities for emissions trading related to CO2. While Ecuador is
a non-Annex I country with no obligation to reduce its CO2 emissions, the Kyoto Protocol allows
for a flexibility mechanisms called the Clean Development Mechanism (CDM) that could yield
opportunities for developing countries to access funds for sustainable development and clean
energy technologies (Thompson, 2002).
The Annex I signatory countries to the Kyoto Protocol have an obligation to reduce their
greenhouse gas (GHG) emissions to a certain percentage below 1990 levels depending on the
country. In order to meet this obligation they can increase efficiency, substitute fuels, or implement
renewable energies in their own countries or use the flexibility mechanisms such as Joint
Implementation (JI), emissions trading or the CDM (Thompson, 2002). The reasons a nation
would want to use a flexibility mechanism instead of reducing all of the emissions within its own
countries are economic reasons. A certain amount of reduction could be achieved at a reasonable
cost within the nation but the costs increase as the most economically viable projects are carried
out. For that reason, CDM presents significant opportunities for the Annex-I country as well as
the developing nation where the project will be carried out.
In the European Union (EU) governments are going through the process of distributing
GHG emission allowances throughout the industries. While there is some controversy in this
process and concerns over fairness, once the allowances have been distributed the companies will
actively be seeking CDM projects for which they can claim Certified Emissions Reductions
(Nicholls, 2003). Despite a lack in structure and some ambiguities about how CDM will work, a
number of companies have already begun selling carbon credits such as the company
EcoSecurities that sold between 2.6 million and 5 million tones of carbon dioxide emissions to the
Dutch Government (Nicholls, 2003). The credits for that sale were generated from the
NovaGerar Brazilian landfill gas project.
Even in countries that did not ratify the Kyoto Protocol, there is increasing activity in
relation to GHG emission trading. In Australia, a great deal of time and effort is being devoted to
GHG policy and the development of a national system of GHG emissions reductions (Griffin,
85
2003). This climate of increased activity in GHG policy among countries that have ratified the
Kyoto Protocol and those that have not gives some reason to be optimistic of the opportunities for
CDM projects in developing nations.
According to David Neira (2003) (CORDELIM official) the current price being paid for
Certified Emissions Reductions (CERs) in CDM projects is between $3 and $5 depending on the
quality of the project. The quality of the project is related to aspects of the project like added
benefits or consequent disadvantages. A project that offers renewable energy, provides local
economic development and biodiversity conservation is a high quality project. On the other hand
a large hydro-electric dam that displaces a population and floods land with endangered species
would be considered a low quality project. With the current price for CERs, a project developer
could not expect to finance a significant portion of a project with a CDM deal but the CERs could
make the difference between a marginal project and a profitable project.
The Dutch government is one of the worlds largest buyers of carbon credits and it is
learning important lessons that could be applied in future projects (de Jonge, 2003). Senter
International of the Dutch government has set up a website at www.carboncredits.nl through
which it purchases carbon credits that projects in renewable energy and energy efficiency
generate. However, only carbon credits generated through JI can be sold through this site under
the first tender called the Emissions Reduction Unit Procurement Tender (ERUPT) (Senter
International, 2003). ERUPT formed the basis for the CERUPT tender for credits from CDM
projects which was launched in late 2001. Through the CERUPT tender, the Dutch government
has purchased carbon credits from Wind projects in China, India, and Jamaica (de Jonge, 2003).
One of the most ambiguous and controversial subjects in CDM projects is the baseline
from which CERs are calculated. “A baseline should reasonably represent the anthropogenic
emissions of GHGs that would occur in the absence of the proposed project ” (paragraph 44 of
the Marrakech Accords). CERUPT has developed a baseline methodology based on key factors
such as financing, economics, local legislation and others (de Jonge, 2003). One key factor used
86
by CERUPT that has received criticism from NGO’s is the financial additionality (Mathias, 2003).
According to de Jonge (2003), head of the CDM division in the Dutch environment ministry,
financial additionality does not need to be proved since it was not included in the 2001 Marrakech
Accords. But CDM Watch, an NGO that monitors CDM projects, says that the purchases made
by CERUPT “will merely make already profitable projects more profitable - they will not achieve
additional reductions in GHGs”(Mathias, 2003). But it is clear from the analysis in this report, that
CDM deals will not significantly change the economics of projects and it would be very difficult to
apply the financial additionality requirement.
The World Bank has prepared the Prototype Carbon Fund which has as its objectives to
show how project based GHG emissions reductions can contribute to sustainable development
and reduce costs of compliance with Kyoto, to disseminate knowledge on CDM and JI, and to
demonstrate how the world bank can work with public and private partnerships to mobilize
resources for development (Prototype Carbon Fund, 2003). Carbon Credits can also be sold
through this fund.
Another climate change initiative, separate from Kyoto, that can be used to finance climate
change projects is the Small and Medium Scale Enterprise Program (SME) through the
International Finance Corporation (IFC). It is a $21 million activity of IFC supported by GEF. It
is geared toward financing climate change projects carried out by small and medium scale
enterprises in GEF-eligible countries (Saupin, 2002). Contingent, concessional loans are provided
to financial intermediaries (FIs) including NGOs and commercial enterprises. These FIs then
finance the SMEs.
87
The integration of the municipality into the project is an option that needs to be
considered, taking into account that this institution is responsible for the execution of public works
that are vital for the community’s development but that have not been prioritized due to the lack of
budget.
Most of the social benefits mentioned until now are secondary or minimal since the
quantity of human resources needed from the district is small and the specific expertise for a
number of the jobs is not available within the district. The scheme that would most benefit the
population of the district is the operation and management of the wind farm under a cooperative
structure so that benefits and profits are shared equally by the members. The citizens of Mira
have shown the ability to work well in cooperatives. While most of the cooperative experience in
the area is based on low skilled work, there is a very good example of complex work being done
under a cooperative structure in the Basque region of Spain called the Mondragon Group of
Cooperatives. Mondragon is the umbrella organization for a group of separate cooperatives that
engage in activities ranging from agriculture to the production of domestic appliances (Whyte,
1988). All of the cooperatives support each other under a policy of import substitution. While
the cooperatives also produce for markets outside the cooperative group, many of the inputs for
the different activities come from suppliers within the group. A similar idea could be used in a
community such as Mira starting with the base cooperatives of agriculturalists and cheese
producers already existing in the area. However, one main limitation to using a cooperative
scheme for the wind farm is that funding will be difficult to find.
landscape clues, such as skewing of trees or wind erosion. In addition, two speed-up effects: hill
effect and tunnel effect should be considered for those purposes. The chosen location, the district
of Mira, presents several places where the aero-generators could take advantage of the hill effect,
especially the site called El Mirador .
As for the selection of aero-generators, it was based on its capacity factor working at the site.
However, on the basis of a site specific reliable wind resource characterization, the turbines, the
number of turbines, its size (height of the hub and rotor’s diameter), the generator size and the
costs associated to those variables, in addition to the capacity factor, constitute parameters for
economic optimization. Economic optimization basically consists of obtaining as much energy
production as possible with the minimum investment cost, which is the driving figure of the
calculation.
In this particular project, other issues such as availability of road accesses, proximity of
electrical facilities, and transport of equipment do not constitute major barriers for the
development.
For the layout of the wind farm, in addition to the availability of the wind resource, the minimal
spacing between windmills and other obstacles causing wind shade both in the wind’s direction
and the transversal direction must be taken into account. Given the current agricultural activities of
the district of Mira, the presence of scattered wind turbines, based on the recommendations, will
have a minimal effect on the current use of land.
Although the Danish, German, and US based Industries lead the field of Windmill
Manufacture, by providing the most efficient and sophisticated equipment, the possibility of
involving local design and manufacture could be surveyed in terms of its economic convenience
and opportunities for funding as it would constitute a local project for technical development in
renewable energy. It might be in the interest of international funding agencies. However, it is best
to use proven technology in this type of project.
90
borrow money or get grants from development agencies and then receive dividends from
ownership in the project. Obviously, the dividends received would have to be significantly higher
than any debt servicing that would be required. Alternatively, individuals in the region or nation
could invest in the project as shareholders. This would have the effect of expanding local capital
markets and give legitimate investing opportunities to those that wish to do something other than
put their money in banks or invest in foreign markets.
The options for financing include private funding, public funding and private/public
partnerships. If a BOOT scheme is selected, it gives the opportunity for local government to
obtain ownership in the plant after a certain period of time. But it also has the effect of making the
project less attractive to private investors since the period in which they can recover their
investment is limited.
Other opportunities include using credit from export credit agencies or leveraging funding
from the Clean Development Mechanism (CDM) of the Kyoto Protocol to sell carbon credits to
developed nations. Another sustainable development mechanism that could be leveraged is the
Small and Medium Enterprise (SME) fund offered through the International Finance Corporation
(IFC) that provides loans for small-scale sustainable energy generation.
problem if proper equipment is selected that is certified by the competent authorities in the USA
and Europe, however there could be some effect due to the blades blocking signals or acting as
unwanted relay transmitters. With proper siting precautions these problems can easily be avoided.
The visual impact should also be considered for any wind farm development but since there are no
major tourist destinations in the area, there is likely to be little if any problems caused by this
impact. The positive environmental impacts include the offsetting of 480,500 tons of CO2 over
the lifetime of the project and the offsetting of any NOx or SOx emissions that would result from
an equivalently sized thermal power plant.
93
Griffin, M. (2003). Australia Eyes Emissions Trading – Again. In: Environmental Finance
April, 2003. London. Fulton Publishing.
GTZ. (2003). TERNA Wind Energy Program: Industry as Partner. Retrieved on May 21, 2003
from URL: http://www.gtz.de/wind/english/wirtschart.html.
H. Consejo Provincial de Loja (2003). Aerogeneración de Energía para la Sostenibilidad de los
Sistemas de Bombeo de la Provincia de Loja.
Hamlin, T. (2001). Solar and Wind Energy Resource Assessment (SWERA): a UNEP/GEF
project. Retrieved on May 19, 2003 from URL:
http://www.uneptie.org/energy/act/re/fs/docs/swera.pdf
Hegmann, G., C. Cocklin, R. Creasey, S. Dupuis, A. Kennedy, L. Kingsley, W. Ross, H. Spaling
and D. Stalker. (1999). Cumulative Effects Assessment Practitioners Guide. Prepared
by AXYS Environmental Consulting Ltd. and the CEA Working Group for the Canadian
Environmental Assessment Agency, Hull, Quebec.
Howstuffworks. (2003). How Stocks and the Stock Market Work. Retreived on May 21, 2003
from URL: http://www.howstuffworks.com/stock.htm
IDEA. (1992). Phase One Feasibility Study of a 20 MW Wind Electric Power Plant in Costa
Rica. Washington D.C.
Instituto Nacional de Estadísticas y Censos (INEC), 2002. Difusión de Resultados Definitivos del
VI Censo de Población and V de Vivienda. Provincia del Carchi.
Instituto Nacional de Estadísticas y Censos (INEC), 2003. Datos Socio-Econónmicos del
Cantón Mira basados en el VI Censo de Población and V de Vivienda.
International Development Bank (IDB). (2003). The Hemispheric Sustainable Energy and
Transportation (HSET) Funds. Retrieved on May 21, 2003 from URL:
http://www.iadb.org/sds/hset/hset_e.htm.
Irish Energy Center (2003). Environmental (and Other) Impacts of Wind Turbines. Retrieved on
January 14, 2003 from URL: http://www.irish-energy.ie/reio.htm.
Lam, E.Y. (1988). The Build-Operate-Transfer (BOT) Concept. Presented at Seminar on
Private Power Generation Through Build-Operate-Transfer. Manila.
Larrea, Carlos. (1996). La Geografía de la Pobreza en el Ecuador. Secretaría Técnica del Frente
Social. Quito.
Mathias, A. (2003). NGOs slam Dutch on CDM. In: Environmental Finance April, 2003.
London. Fulton Publishing.
Mathrani, R. (1990). The Financial Equation. In: Private Sector Participation in Power Through
BOOT Schemes edited by John E. Besant-Jones. The World Bank. Washington, D.C.
McCowa, A. and Mohamed, S. (----). Evaluation of Build-Operate-Transfer (BOT) Project
Opportunities in Developing Countries.
95
Ministry of Energy and Mines from Ecuador. (2002). Sector Energético Ecuatoriano. Brochure.
Quito, Ecuador.
Ministry of Environment from Ecuador. Retrieved on February 2003 from URL:
http://www.mambiente.gov.ec
Mitchell, R.K., Bradley, R.A, & Wood, D.J. (1997). Toward a Theory of Stakeholder
Identification and Salience: Defining the Principle of Who and What Really Counts.
Academy of Management Review, Vol. 22, No 4. 853-886.
Moore, J. (1990). An Equipment Manufacturer’s/Developer’s Perspective of BOOT. In: Private
Sector Participation in Power Through BOOT Schemes edited by John E. Besant-Jones.
The World Bank. Washington, D.C.
Municipality of Mira (2002). Proyecto Descentralización-Democracia-Desarrollo. Presented at
Seminar on Community Development Program. Mira.
Neira, D. (2003). Personal Interview with Official of CORDELIM. Ecuador
Nicholls, M. (2003). EcoSecurities Sells Carbon Credits on own Account. In: Environmental
Finance April, 2003. London. Fulton Publishing.
Nicholls, M. (2003). The Devil in the Allocation. In: Environmental Finance April, 2003.
London. Fulton Publishing.
OLADE. (2003). Information from the Masters Degree Program Field Trip to Honduras.
Phillips, R. J. (1990). The Questions Which Need to be Asked to Identify Viability. In: Private
Sector Participation in Power Through BOOT Schemes edited by John E. Besant-Jones.
The World Bank. Washington, D.C.
Phillips, R. J. (1991). BOOT: The Overview and the Questions Which Need to be Asked to
Identify Viability. In: Energy Magazine Year 15, Number 1. OLADE. Quito, Ecuador.
Pollard V. (2000). How Wind Power can Reduce Emissions of CO2. Renewable Energy World.
November/ December 2000. London: James & James Ltd.
Pottinger Gaherty Group (2002). Nai Kun Wind Farm Environmental Impact Assessment Study
Design. Retrieved on January 13, 2003 from URL:
http://www.uniterre.ca/Nai_Kun_Wind_Farm_rep.pdf
Proaño, M. and Poats, S. (2000). Abundancia o Escacez Concesiones, manejos y políticas en el
Manejo de la Cuenca del río El Angel. MANRECUR, FUNDAGRO, CIDD. Retrieved
on April 14, 2003 from URL: ww.condesan.org/memoria/ECU0200.PDF
Prototype Carbon Fund. (2003). Overview I. Retrieved on May 20, 2003 from URL:
http://www.prototypecarbonfund.org.
96
USAID. (2003). Ecuador: Program Data Sheet 518-013. Retrieved on April 5, 2003 from
URL: http://www.usaid.gov/country/lac/ec/518-013.html.
WAsP. (2003). Wind Atlas Analysis and Application Program. Retrieved on May 19, 2003
from URL: http://www.wasp.dk.
Yandún, René (2003). Provincial Prefect, Personal Interview.
Whyte, W. (1988). Making Mondragon: The Growth and Dynamic of Worker Cooperative
Compex. New York. ILR Press.