Escolar Documentos
Profissional Documentos
Cultura Documentos
June 2013
Prepared for
GIZ
Germany
Prepared By
Varun Gaur
Masters Student (2011-2013)
Post Graduate Program in Renewable Energy (PPRE)
University of Oldenburg, Germany
Email: varungaur.engg@gmail.com
Besides my main supervisors, I will also like to thank the entire team at Project Development
Program (PEP) of GIZ for their support.
Last but not the least, I would like to thank my family for supporting me throughout the life
1.1 Background
The Philippines is a large archipelago nation with more than 7000 islands. The uneven
spread of population makes decentralized electricity a favorable choice for off grid
electrification. The Government has already been encouraging Diesel (and bunker oil)
Genset based Mini Grids in the country. There is an estimated 374.5MW 1(aggregated
capacity) Diesel Mini Grids in Philippines. However, there exists, many problems
associated with such Mini Grids, for example:
High cost of electricity production (transportation cost to islands make Diesel very
costly); cost of Diesel can be more than 1Euro per liter on a Filipino island
Pollution from Diesel Gensets (more than 750 grams of CO2 per kWh of electricity
production) and it can be worse for Bunker Oil based Mini Grids
Problems associated with partial load operation of Diesel Gensets [Reduced fuel
efficiency, higher GHG emissions and increased maintenance cost of Diesel
Genset]
Problems with the logistics; fuel shortage can lead to power interruptions which
may result in social unrest in the region
Because of the above mentioned reasons, I thought that there could be a great scope of
standalone or solar-Diesel hybrid Mini Grids in Philippines. With this background, I
1 Source: Geographic, Technological and Economic Analysis of isolated Diesel grids by Paul Bertheau, year 2012
1.3 Methodology
I carried out my thesis under the supervision of
Dr Detlev Heinemann (my Professor at the University of Oldenburg, Germany)
Mr Tobias Cossen (Project Manager, PEP- GIZ (German Agency for International
Cooperation))
I started my thesis with the literature survey of Electricity Sector in Philippines, with the
focus on OffGrid Electricity. With the support of GIZ, I also attended a high level talk by
Philippine delegation to Germany that helped me in getting deeper insights into the
electricity sector of Philippines.
Activity 2: Assessment of Solar/ Solar Diesel Hybrid Mini Grids elsewhere in the
world
Simultaneous to Activity 1, I also studied existing Solar/ Solar-Diesel Hybrid Mini Grids
all across the world. For this, I utilized literature on the internet and various publications
at the library of Technical University, Berlin. GIZ also helped me in undergoing relevant
trainings at SMA Solar Academi (Kassel Germany) where I learnt Island System of SMA.
I later utilized the knowledge of SMA Sunny Island system to model the Hybrid Power
System. I also participated in various Renewable Energy workshops in Germany and
took regular guidance from the Experts in the field of Decentralized Energy.
Activity 1 and Activity 2 prepared me with the broad picture of Philippine OffGrid
Electricity Sector and the possible Renewable Energy options. Thereafter, I undertook a
scoping mission to Philippines with the objective to understand the electricity load
pattern, electricity supply system and electricity costs in the selected islands. This
mission was supported by GIZ and I was locally assisted by the GIZs local partner
Powersource Philippines Inc (PSPI). This mission was a part of collaboration between
GIZ and PSPI and therefore some information will be kept confidential in the thesis
report.
During the mission, I surveyed 3 islands (I will call them as Island A, Island B and Island
C) with the focus on Island A. As a part of my mission, I carried out a household survey
and the interviews of mini grid operators in the Island A, whereas for Island B and Island
C, I only carried out preliminary assessment of their Mini Grids.
Activity 4: Modelling the power supply system for the Solar/ Solar-Diesel Hybrid
Mini Grids in the selected island
Activity 3 helped me in getting precise information on the electricity load pattern and the
electricity generation system of the selected island. After coming back to Germany, I
utilized this information to model the Solar/ Solar Diesel Hybrid Mini Grid in the selected
island. By modelling, I mean re-producing different system configurations (power system
sizes) and the associated costs (investment costs and electricity generation costs),
based on different input parameters (such as Electric Load, Solar Insolation, Solar
penetration, etc).
I utilized the technical configuration of Hybrid System on the lines of SMA Island
System
I developed an excel application which inputs local parameters (such as Electric
Load curve, Solar Insolation, Diesel costs, required solar penetration etc) and
provides the required Power supply system configuration and the associated
costs (system costs and electricity generation costs)
Island B is a tourist island with a large number of resorts. During my survey, I was also
advised to do an indicative assessment of possible Rooftop Solar PV potential of the
resorts.
There are 8 chapters in the report including the current chapter on Introduction.
The next Chapter (Chapter 2) presents a general overview of Philippines and its
electricity sector. Chapter 3 focuses on the OffGrid electricity Sector in Philippines. It will
talk about the current government strategy and schemes for the offgrid electricity.
Chapter 4 presents the execution of my Scoping Mission and the results of the survey.
Chapter 5 details out my methodology and the resultant excel application which I have
utilized to model the Solar/ Solar Diesel Hybrid Power System. The results of system
modelling and various sensitivity analyses are discussed in Chapter 6. The focus of
modelling is Island A. Chapter 7 presents the results of Roof Top PV assessment at
Island B.
Philippines is the 12th most populous country in the world with a population of around 92
million (Census 2010, source-Wikipedia). In addition, there are around 12 million
Filipinos which live overseas. Manila is its capital with a population of around 1.6 million.
Philippines is the 43rd largest economy in the world where contribution of agriculture,
industry and Service sector are 13.8%, 30% and 56.2% respectively (source: Wikipedia).
Visayas
Luzon
Manila
Mindanao
Manila (Capital) depicted as Red dot in the picture, lies in the Luzon region. Luzon
region has the highest share of Philippine economy followed by Visayas and Mindanao.
It shows that fossil fuels form around 65% of the total installed capacity. There is also a
significant proportion of Oil based electricity generation. Renewables are dominated by
Geothermal (Quasi Renewable), which forms 12% of the mix. Other Renewable such as
solar and wind are present in a very small proportions.
The Following picture 2.e presents the Electricity mix in different regions of Philippines.
Visayas:
Luzon: Electricity Mix dominated
Electricity mix by Geothermal and Oil
dominated by
Coal and Gas
Mindanao:
Electricity mix
dominated by Coal and
Hydro
2.4 Need for Renewable Energy and trends in the Fossil Fuel mix of Grid
Philippine has a significant proportion of Oil in its grid connected installed power
capacity. However, there is a strong need to find its substitute. I found that within 8 years
(between 2001 and 2009), the R/P ratio of Oil in Philippines fell down by a factor of 10.
Please see figures 2.f below
Figure 2.f: Proven Oil Reserves-Philippines, Source: Figure 2.f: Oil Production-Philippines, Source: US-
US- EIA EIA
The above figures show that within year 2001 and 2009, Oil Reserves in Philippines
have come down by a factor of 2 and Oil production has climbed up by a factor of 5. This
implies that R/P ratio has come down by a factor of 10.
This alarming decline rate has surely made the Philippine Government to review their
policies and figure below shows the change of generation type in Electricity generation
mix in the last few years.
The figure shows that within 2001-2009, Oil based electrification has reduced
significantly, however, still the expenditures on Oil imports in 2011 was 5.7% of GDP
(source Geographic, Technological and Economic analysis of isolated Diesel Grids by
Paul Bertheau, Year 2012).
Thus, we saw that there has been a strong reliance on Oil for the Grid Connected
Electricity Sector, and there is a strong need for its substitute. In the next chapter, we will
try to understand the Off Grid Electricity Sector in Philippines.
As per the data from NPC SPUG, 11% of island Mini Grids (of NPC-SPUG) operate for
24 hours while remaining provide electricity for less than 24 hours, with majority of them
operating for 6-8 hours. Presented below is the classification of Diesel Mini Grids based
on their hours of operation.
10-15 hours 36
16-20 hours 11
24 hours 25
Total 221
Table 3.a: Classification of Mini Grids as per the hours of operations; Source: NPC SPUG
Presented next is the classification of Mini Grids based on the installed power capacity.
2
Geographic, Technological and Economic analysis of isolated Diesel Grids by Paul Bertheau, Year 2012
Government has classified different Offgrid areas as per the respective gross electricity
generations in year 2011. These classifications are then used to decide which area is to
be operated by NPC-SPUG or NPP or QTP. Following table presents the classifications:
So, the areas where electricity generations in 2011 were more than 10GWh, will
continue to be under NPC SPUG. Areas with smaller electricity generations will go to
NPPs and QTPs.
Power Sector
Management and NPPs
Liability Corporation OBI (Output Regulates rates
based Subsidy) and services
Power
Revenue
OBI= TCGR-SAGR
SAGR (Subsidized
Acceptable
Distribution Generation Rate)
Companies
Figure 3.a: Off Grid Electrification Scheme; Source: Alliance for Rural Electrification
2. Carbon Emissions with Diesel Genset: A Diesel Genset generally emits 750
Grams of CO2 with production of 1 KWh of electricity. This emission rate can go
higher in case of Bunker Oil based electricity generation.
This figure shows that how the fuel efficiency drops at partial load operation. It
shows that for example: a 20 KW generator running at full load requires 1.6
Gallons of fuel for generating 20 KWh, however, at load, it requires 0.6 Gallons
of fuel for generating 5 KWh (1/4 of 20 KW) ie 2.4 Gallons for generating 20
KWh.
Further, the carbon emissions also increase with partial load operation. Partial
load operation also increases wear and tear of the Genset.
4. Fuel Shortage also cause power interruption and anger amongst people
However, it is unclear whether this OBI will be over and above the OBI as given in
Diesel based electrification where OBI= 100% (TCGR-SAGR)* KWh of electricity
produced
Fiscal Benefits
In addition to OBI, there was a mention of following extra benefits for RE
Income tax holiday for 7 years
Duty free importation of RE machinery
Exemption from universal charge
RPS ( Renewable Portfolio Standard) which is the bindings on Distribution
companies to buy certain % of electricity from RE sources.
It is unclear whether these benefits are only for Grid Connected Renewables or also
for Offgrid Renewables.
Thus, in this chapter, we saw that Offgrid Electrification in Philippines is majorly based
on Diesel and this Diesel based electrification is highly subsidized. High cost of Diesel
makes the electricity cost very high and a huge financial burden. This brings in a strong
case of Renewable Energy based Offgrid electrification.
In the previous chapters, I presented a broad picture of Philippines and its Off Grid
electricity sector. This was primarily based on my Literature survey. After getting a broad
picture of Filipino Off Grid Electrification Sector, I undertook a scoping mission to
selected Islands in Philippines. The objective was to understand the electrification
scenario in the selected islands and utilize the information to model the Solar/ Solar
Diesel hybrid Mini Grids for the same. Now on, I will present you my findings and
assessment from the selected islands. Chapter 4 will present the findings from the
scoping mission and in the following chapters, I will utilize the information to model the
PV system.
My mission was supported by GIZ and the same has asked to keep some select
information confidential. During the mission, I surveyed 3 islands and will refer them as
Island A, Island B and Island C. It is to be noted that the focus of my mission is Island A,
however, I will also present crucial learnings from Island B and Island C.
Located in the Visayas sea, Island A is around 2.5 hours boat ride from nearest port.
With around 600 households, it has a population of around 3000.
In the survey, I was assisted by 2 employees of Power Source Philippines Inc (PSPI),
which is our local partner in the project. The names of the PSPI officials are: 1) Mr Erwin
Tindoc and 2) Mr Romy Alvarez. PSPI also hired 6 Resource Persons for assistance in
household survey.
I started my assessment with a Focused Group Discussion (FGD) with the local council
(Barangay council). This helped me in getting a broad picture of the village. In the FGD, I
got to know that the island is divided into 6 clusters (Sitios) of households. It has 2
Primary schools, 1 high school and 1 small health center.
Island Council also mentioned that the main electric load in the island is Light and TV.
The source of electricity in the island is a large number of small Diesel Gensets typically
5 KVA, each serving to a small cluster of households. They reported around 40 such
Diesel Gensets in the island. Shown below is the indicative map of the island with the 6
Cluster of Households.
After getting a broad picture of the island, I started my survey. I broke the survey into 2
parts.
Part 1: To understand the electric load in the island and the cost of electricity. For
this, I interviewed around 50% households. The questionnaire used for this survey is
attached as Annexure 1
Part 2: To understand the electricity supply system, the cost of electricity generation
and the electricity distribution system. For this, I interviewed around 10% of Diesel
mini grid operators. The questionnaire is attached as Annexure 2
In the household survey, we tried to cover equal percentage of households in all the
six clusters. Shops were mostly part of the households.
Figure 4.f: Household Survey Figure 4.g: Typical Light bulb in Households
Figure 4.h: Survey of Shop cum Household Figure 4.i: Survey of Primary School
From the data, it is clear that the most common load in the island is Light bulb
(CFL) and the TV (along with DVD player). Few households (mostly Genset
owners) also had Audio Amplifiers, Fans, Laptops and Refrigerators.
The households get around 3.5 hours of electricity every day (6 pm to around
9.30 pm). They pay a fixed price of electricity per gadget, which is mentioned
below:
Considering the case of light point, it means that for 63 Whs, consumers are
paying 0.15 Euros. This translates into the cost of electricity as 2.3 Euros/ kWh
For lighting requirements beyond 9.30 pm, people use kerosene lanterns. The
cost of kerosene in village is 1.4 Euros/ liter of kerosene
People showed a great aspiration for having Refrigerators and TVs in the near
future
People mentioned that the supply of electricity is very erratic and they also
encounter frequent flickering of lights
People have the willingness to pay for electricity services
The load curve of Island A can therefore be interpreted as figure 4.j
The typical capacity of the Genset was 3 KVA to 5 KVA and each serving to a
cluster of households.
All interviewed Mini Grids were running at partial load (typically around 20-
30% load factor)
The Gensets were very old (no make visible on the Genset)
The fuel consumption rate was significantly higher (around 1 liter of Diesel/
kWh of electricity), as mentioned by the operators.
The cost of Diesel was very high in the island compared to mainland. It was
54 Pesos (~1 Euro) / Liter compared to 43 Pesos/ Liter in the mainland city
High cost of generation of electricity, as calculated in the case study below
Frequent breaking down of Genset was a common problem
Running Genset was a burden on mini grid operator
Main Points
Size of the Genset: 5KVA
Number of customers: 12
Electric Load: 12 houses with 1 light point (18W each); 6 of
these households also had a TV with DVD player DVD
player; So total ~0.9KW load
Fuel Consumption: 3 liters to run the above load for 3.5
hours in night
This means that 3 liters of Diesel is used to produce 3.15
kWh of electricity. This implies that 162 pesos (3.05 Euros)
for 3.15 kWh of electricity.
This translates to the cost of electricity generation to be
around 1 Euro/ kWh. This cost of generation only includes
fuel cost and maintenance; capital cost etc will be extra.
External Wire
Link
Households hook
their internal wire to
the external wire link
During my assessment in Island A, I came across some ruins of an Old Mini Grid, which
was established in 1996. I questioned few of the Office Bearers of the local Island
Council. Following are the main findings:
When, I was returning from Island A, I managed to get the appointment of General
Manager of the concerned Electric Cooperative. I asked him about their plans for the
electrification of Island A. He told that there could be 2 possibilities
Island B is around 1 hour boat ride from Island A. It has around 1000 households with
around 5000 population. It is a tourist island and has around 30 resorts. Although my
focus of study was island A, however I also tried to study the electrification scenario for
Island B because of the following reasons:
It has a big Diesel Genset Mini grid operated by a Private Company. This gave me
an opportunity to see the operations by a big private player.
It is famous for Tourism and has a number of Resorts, so it has an unconventional
Electric Load.
It is close to Island A, so there might be some resemblance in the electric load
pattern, and there might be some learnings for Island A
My intention with the study of Island B was only to understand the execution of Mini Grid,
not the household survey. During my survey of the mini grid, I also found a big number
of Island resorts in the Island. The Resorts had significant electric load in the day time
and the roof tops of these resorts also provide a good opportunity of Roof Top PV.
Therefore, I also utilized my visit to Island B for assessing the amount of Solar PV that
can be put on the rooftop of the resorts. Some snapshots of my survey at Island B are
given next.
The following are the major findings from the Mini Grid at Island B
The total capacity of Mini Grid is around 1,050 KW comprising of three 350 KVA
Generators. Only one generator is used at a time. All the Generators are of Chinese
Make: Ningbo CSI Power & Machinery Group Co. Ltd
The generation, transmission and distribution is managed by PowerSource
Philippines Inc
It provides 24 hours of electricity
A typical daily load curve is shown in figure below (a day in December 2012) It
shows a peak load of around 180 KW at 1900 hours and Minimum load of 93 KW at
around 0600 hours
It serves around 1000 households, 30 resorts and a Telecom Tower
All consumers were paying electricity at the rate of ~0.55 Euros/ KWh
Island C is further around 1 hour boat ride from Island B. It has a population of
around 7,000 with fishing as the main source of income. Again, Island C was not
my focus of study and my intention with Island C, was only to assess the working
of its mini grid. The reasons which made interested to study the electrification for
Island B are:
It has a big Diesel Genset Mini Grid where
o Generation of Electricity is managed by a Government Company
(NPC-SPUG)
o Transmission and Distribution is managed by an Electric Cooperative
So, this gave me an opportunity to study a mini grid operated by a
government agency
Like Island A, it has only residential load, so there might be some
resemblance in the electric load pattern, and there might be some learnings
for Island A
Following are the main findings from the interview with the Mini grid Operator
The generation is done through 2 generators viz 220 KVA and 125 KVA alternately.
220 KVA generator was of USA make: Dale and 125 KVA generator was of
Japanese make
As already mentioned, generation of electricity was done by NPC SPUG, whereas, a
local Electric Cooperative (EC) was responsible for transmission and distribution.
Mini Grid operates from 5 pm to 1 am; The load profile of a typical day is shown in
the figure 4.o below
NPC SPUG sells electricity to EC @ 0.094 Euros/ KWh) and EC sells electricity to
households @ 0.22 Euros/ KWh
Mini Grid operator also mentioned that there are around 15% of households who do
not pay electricity bill
He also mentioned that government had tried to give electricity also in the morning
time, but electric load was not sufficient to run the generator, so morning hours of
operation was discontinued.
The fuel efficiency on 14-12-2012 was around 420 ml of Diesel/ KWh
So, The Chapter 4 gave us the electric load profiles of selected Islands. These will be
further utilized to develop the configuration of Solar/ Solar-Diesel hybrid system for the
islands
In the previous chapter, I explained the findings from my scoping mission to Island A,
Island B and Island C. This scoping mission had helped me to gather the Load profile
(Electric Demand pattern) of these islands. In this chapter, I will utilize the load profile to
model the Solar-Diesel Hybrid Power System for these islands.
The focal point of my study is Island A for which I will also consider different scenarios
for sensitivity analysis. I will also present the modeling for Island B.
Section 5.1 of this chapter will present my indicative technical configuration of the
proposed Solar-Diesel Hybrid System. For this, I utilized learnings from my recent
training program at SMA Solar Academi, Kassel and my learnings at University of
Oldenburg.
Section 5.2 will present my methodology for developing the excel sheet tool that can
model the Solar-Diesel Hybrid Power System, based on different input parameters. For
developing this tool, I utilized learnings from my University of Oldenburg and my
experience at TERI India.
Based on this methodology, Chapter 6 will present the models for Island A and Island B.
A Hybrid Power system is that power supply system which utilizes two or more power
sources. This helps in improving the reliability of the system as there is less reliance on
one method of power production. Solar Diesel Hybrid System utilizes solar and Diesel as
the power supply and battery as the power backup. A Power converter system is an
important component of Hybrid System that controls the power supply and power
backup system in the most efficient manner.
The Figure 5.a below shows the indicative configuration of the proposed Solar-Diesel
Hybrid Power system. This is on the lines of SMA Sunny Island System.
Solar
Solar Inverter
PV
Loads (Non Critical)
Power Converter
(Master)
Charge
Controller
Solar PV Battery
The heart of the system is the Power Converter which will form the Grid and will be the
Master of the system. On DC power supply side, it will have connection to the battery
and the Solar PV (through a charge controller). DC side is depicted by blue line. On AC
Power supply side, it is connected to Diesel Genset and it can also be connected to an
external solar inverter. Diesel Genset is connected through a switch which can be made
ON and OFF as per the system requirement. AC side is depicted by red line. The Grid
Master will keep an eye on the frequency of the system with the following logic:
If frequency > 50 hz, this means that the Supply is more than Demand
If frequency <50 Hz, this will mean that Demand is more than Supply
According to frequency values, Master will regulate the Diesel Genset and the Loads.
Solar PV will be designed in such a way that it will never be more then demand.
The above system is modular in nature. With any possible future load growth, system
size can be increased by adding extra modules. For example, there can be an additional
power converter in parallel to Master, however this additional module will be
synchronized with the frequency of Master.
Section 5.1 presented the indicative technical configuration of the power system. Now
the next step is to model the power system as per the load and other input conditions.
Described below is my methodology for modeling the system.
The first step is to gather the hourly load profile. Presented below is the typical load
profile for Island A and Island B (Corresponding excel sheets are attached as Annexure
4 and Annexure 5 respectively. This data is from the scoping mission.
Figure 5.c presents the typical load curve for Island B. It shows the maximum load of
180KW between 7 pm to 8 pm and minimum load is around 100 KW between 6 pm to 7
pm.
I received 3 major parameters from Step 1, which I will use later for my modeling of
power system:
Energy requirement for each hour (Eh): Hourly Load (KW) multiplied by 1 hour
is the energy requirement for each hour
Daily Electricity Requirement (Ed): This is calculated by adding hourly energy
requirements (Eh) for a complete day
Maximum Power requirement at any point of the day (Pmax): This is the
highest load value at any hour
It is to be noted that I have not considered any effect of inductive load in my calculations.
The second step is to consolidate the Solar Insolation data. I got the Average Monthly
Solar Insolation data for Philippines from the report Assessment of Solar Resources in
Philippines under the project Philippine Renewable Energy Project submitted by
NREL. Figure below presents the data in the form of graph. This data is based on
NRELs Climatological Solar Radiation (CSR) model.
This graph shows that April is the month of maximum solar insolation where insolation
can reach 6KWh/m2/day. December-January is the period of minimum solar insolation.
The average yearly Solar Insolation was around 5.03 KWh/ m2/day
The graph below presents the Hourly Solar Irradiance for a day in April (which
represents the month of maximum sun). This data is based on the information from
HOMER for 12degree North latitude and 122 degree East longitude (coordinated for
Philippines). It is to be noted that there is very little variation on the number of sun hours
in any day of the year.
So, I got 3 major parameters from Step2, which will be utilized in the later section and
they are:
Average Daily Solar Insolation for the month with maximum sun (Sdmax):
This is the daily average value of Solar Insolation for the month of maximum sun.
Once the load requirement is sized, this value will be used to size the Solar PV.
Solar PV is sized for maximum sun because if the Solar PV is sized with any
other lesser Solar Insolation and Solar Fraction in the system is 100%, then Solar
electricity will be wasted in the month of maximum sun. In this case, Sdmax is
6KWh/ m2/ day in the month of April.
Average Daily Solar Insolation for each month (Sd): Once the Solar PV is
sized, this parameter will suggest that how much solar electricity will be
generated in a day of a particular month.
Average Hourly Solar Irradiance for the month with maximum sun (Sh): This
parameter will be utilized to size the battery of the system. Once the Solar PV is
sized, this parameter will help in calculating the amount of solar electricity
generated each hour. Solar electricity which will not be consumed by load, will
have to be absorbed in battery.
Once we have Load data and Solar Insolation data, next step is to size the required
Solar PV. For sizing Solar PV, I used the very simple formula as mentioned below:
The size of the Diesel Genset should be equal to the maximum power requirement of
load (Pmax) at any point of time. If the Solar fraction is between 0 and 0.5, I have
considered Size of Diesel Genset to be Pmax. In case, solar fraction is 0.5 or more then
I have considered size of Genset as 50% of the Pmax. The size will have a flexibility of
5% over capacity.
It is to be noted that I have not considered any effect of Power Factor in my calculations.
Battery Bank absorbs the electricity from Solar in day time and provides to load during
night time. The size of the battery bank can be calculated by the below mentioned
formula:
Energy to be stored in battery: Step 3 gave us the Size of Solar PV (PV). Step 2
gave us the Sh (hourly solar insolation during the day of maximum sun). Sh will
give us the hourly Yield from PV. Hourly Yield will be: Size of Solar PV * Sh.
For example, if size of Solar PV is 1KW and the Sh at 1pm to 2 pm is 700 W/m2,
then it means that 1KW of PV can generate 0.7KWh during 1 pm to 2 pm.
Similarly, we can get solar electricity for the entire day. This is further matched
with the hourly load requirements. The Solar electricity which is not consumed by
load is fed to the battery. For example, if the solar electricity generation between
1 pm to 2 pm is 0.7KWh and load requirement is 0.4KWh, and then 0.3KWh will
be fed to battery. Similarly, calculation of the entire day is carried out.
The number of Autonomy days is the number of days that battery must support
the load without starting the generator. In our case, if the Solar fraction is 100%,
then the battery can support the entire load for 1 day (in the month of maximum
solar insolation)
Battery Efficiency is considered to be 0.9
DoD (Depth of Discharge of the battery): DoD is the amount of charge that can
be taken out from battery in one cycle. For example, if the battery is 100Ah and
DoD is 70%, then 70Ah can be consumed from the battery in one cycle. In our
Step 3 gave us the size of PV. Step 2 gave us the Sd (average daily solar insolation in
each month). Daily Solar Electricity Yield can be calculated as: Size of Solar PV *Sd.
This was further matched with the daily load requirement. The leftover electricity
requirement is expected to be fed by Diesel Genset. Once we have sized the required
electricity units from Diesel Genset, amount of required Diesel will be calculated by using
the thumb rule that 350 ml of Diesel is used to generate 1 KWh of electricity.
Savings in CO2 emissions were calculated as: CO2 emissions in the existing scenario
CO2 emissions for Hybrid System
In the above eight steps, we were able to size the Power Supply System. Now, in this
step, I will explain my strategy to model the Levelized Cost of electricity generation.
o Cost of Diesel Genset= Size of Diesel Genset (from step 5)* 800Euros/ KW
[Assumptions:
- Source: This figure of 800 Euros/KW is based on the report Best Energy
Practices for remote facilities, Artic Energy Alliance
-life of the system is assumed to be 15 years, so this investment cost will be
repeated in the 16th year]
o Cost of battery= Size of Battery bank (from step 6)* 135 Euro/ KWh
[Assumptions
-life of battery bank is 5 years, so this investment cost will be repeated in 6th
year, 11th year, 16th year and 21st year and DoD is taken as 70%
- Source: the pricing is based on the current market prices of battery in
Philippines (Motoma AGM Lead Acid batteries (deep cycle)]
o Cost of Power Convertor= Size of Power Convertor (from step 4)* 0.75Euro/
W
[Assumptions:
-life of power converter is 20 years, so this investment cost will be repeated in
20th year
- Source: This figure of 0.75 Euro/ W is based on the offer of SMA Sunny
Island system on the website of TCK Solar Shop, Australia]
o O&M of Solar PV= (1% of investment cost)/ year [this figure is based on the
learnings of a similar study of Hybrid System by Center for Engineering
Research in Saudi Arabia]
o O&M of Battery= (1% of investment cost)/ year [this is based on the learnings
of a similar study of Hybrid System by Center for Engineering Research in
Saudi Arabia]
o O&M of Diesel Genset= (2 Euro)/KW/ year [this is based on the learnings of a
similar study of Hybrid System by Center for Engineering Research in Saudi
Arabia]
Fuel cost in year t = Diesel requirement in a year t (from Step7) * Diesel cost
SDR- It is the System Degradation Rate owing to the losses due to ageing of
Solar PV modules and generators. It is considered 0.5% in my model.
r is the Discount rate: Discount rate is a factor by which a future value must be
multiplied in order to obtain the present value. This includes interest rate as well
as other financial risks involved with the investment. In my modeling, I will
consider different discount rates between 6% to 13%
5.3: Resultant Excel Tool for modelling the Hybrid Power System
Making use of the methodology as mentioned in Section 5.1 and 5.2, I have developed
an application (tool) in excel. I had developed this application during my tenure at TERI
(India), however, I strengthened it further during my thesis. A snapshot of the user
interface of the application is presented below.
Figure 5.e: A snapshot of the User Interface of the developed Modeling Tool
This application is attached to the load curve which can be changed as per the
requirements.
On the left side (Yellow colour) are the input system parameters such as
Solar Fraction
On the basis of input parameters and the load curve, it calculates and displays:
System Sizes (Size of Solar PV, Diesel Genset, Power Converter, Diesel
Requirement)
Initial Investment Cost
Levelized Cost of Electricity
Carbon Credits
The above mentioned methodology and the excel application will be utilized to
model Solar/ Solar-Diesel Hybrid Systems for Island A and Island B. The results of
the modeling are discussed in next Chapter (Chapter 6).
The focus of my study is Island A, for which I have considered different scenarios . I will
start by describing different load scenarios for Island A
Based on the household survey, I got the electric load pattern in the island A (discussed
in Chapter 4). I utilized this load pattern to size the solar-Diesel hybrid mini grid. Further,
I felt that there can be some changes in the load pattern in the near future and I made 2
two extra scenarios.
Scenario1: System is sized as per the existing load requirement (as per the load curve
generated from the household survey- Annexure 7)
Island A- Scenario 1
Timings Load Assumption
6 pm to 10 pm 76KW Load as per the
S survey results
Table 6.1: Island A- Scenario 1 Load Profile
c
Scenario2: In my load survey, I had found that there were around 50% households
which did not have TV. However, these households showed a great aspiration of having
TVs in the near future. Further, a few percentage of households also showed the
aspiration of having refrigerators in the near future. Scenario 2 assumes these
aspirations as realities in near future. Scenario 2 also includes the possibility of
extending the mini grid operation till 12 am in the night with basic load such as lights,
TVs and Refrigerators (this feature was also prominent in Island B and Island C where
Island A-Scenario 2
Timings Load Assumption
6 pm to 10 pm 170KW Load as per the survey
results + TVs in all the
remaining households+
Refrigerators in 20%
households
Scenario3: In this scenario, I assumed a situation where we can extend the hours of
operation of mini grid in the day time and we can shift some of the existing night time
loads to the day time. Some percentage of loads such as TVs, Audio Players, Cell
Phones, Laptops etc may be shifted to day time. In scenario 3, I have assumed that we
have been able to shift 30% of existing night time load (of Scenario 2) to the day time
(i.e. between 12 pm to 6 pm). Please see Annexure 7.
Island A-Scenario 3
Timings Load Assumption
12 pm to 6 pm 51KW 30% of the night time
load shifted to this time
The figure gives the actual load profile of Island A. It shows a load of 76KW between 6
pm to 10 pm.
Now, I put this load profile into my excel sheet application. Shown below is the snapshot
of my results (on the same excel application). On the left hand side (yellow color), is the
input values and on the right side are the results (green color).
The above snapshot shows that for Island A- Scenario1 load profile: for example: When I
input the required Solar Fraction to be 80%, then the Levelized cost of electricity
generation (LC) will be 0.357 Euros/ KWh. It also gives the values for the required
system sizes and also the carbon emission values. Similarly, by changing input
parameters, resultant values can be obtained. Please see Figure 4.g above for the
assumptions and the results.
Effect of different Solar Fractions (SF) on the Levelized Cost of Electricity (LC)
Figure 6.h below shows the impact of different Solar Fractions on the Levelized Cost of
Electricity Generation (LC). By keeping all the input parameters constant and changing
the Solar Fractions, I got different values for LC. These values are projected in the graph
below.
Figure 6.h Levelized Cost of Electricity (LC) versus Solar Fraction for Island A -Scenario1
The graph below presents the Levelized Cost of Electricity (LC) at different Discount
Rates
Figure 6.i: Island A- Scenario1- Levelized Cost (LC) versus Discount Rates at different Solar Fractions (SF)
The graph below shows the impact of different PV costs on the Levelized Cost of
Electricity. The discount rate is kept constant at 10%.
Figure 6.j: LC for different Solar PV costs (at different Solar Fractions and 10% Discount Rate)
One observation is quiet clear. If the cost of Solar PV is between 2-2.5 Euro/ Wp, then
LC at SF=0 is infact the best case and any Solar PV penetration in the system will be
undesirable.
Shown below is the Island A - Scenario2 Load curve (Scenario 2 has already been
explained above). It shows the load of 170KW between 6 pm to 10pm and load of
145KW between 10 pm and 12 am.
Now applying the Scenario2-Load profile to my excel application, I got the below
mentioned results.
Applying exactly the same input parameters, the Levelized cost of electricity in scenario
2 is 0.335 Euro/ KWh as compared to 0.357 Euro/ KWh in scenario 1. Thus we see that
as the load grows (almost double as of Scenario 1), the Levelized Cost of
electricity will come down, however, the drop is not significant.
Effect of different Solar Fractions (SF) on the Levelized Cost of Electricity (LC) and
the comparison with Scenario1
Figure 6m: Levelized Cost vs Solar Fractions (Comparison between Scenario 1 and Scenario 2)
The graph above indicates that although the pattern of decrease of LC with SF in
Scenario 2 is same as of Scenario 1, however there is an overall decrease of LC at all
SFs in scenario 2. This decrease is almost uniform for all the Solar Fractions, however
the drop is not significant, despite of that fact that Scenario 2 needs more than double
amount of investment.
As depicted in the above graph, the pattern of change of LC with Discount Rate is similar
to as of Scenario 1, however, there is one minor observation. In scenario 1, LC at
SF=0% and LC at SF=60% collided at Discount Rate of 12%, whereas, in scenario 2,
they will overlap at Discount Rate of 13% or more. This means that in scenario1, Solar
fraction of 60% wouldnt have given any benefit over Solar Fraction of 0% at 12%
discount rate. Now, in scenario 2, this cutoff interest rate has slightly improved.
However, this improvement is not significant.
In Scenario 1, we found that for the cost of PV greater than 2 Euro/Wp, solar penetration
was not proving economically desirable (with regard to Levelized Cost of Electricity).
However, in scenario 2, there is an improvement on the cutoff Solar PV price. However,
there is no significant improvement.
The objective of Scenario 3 is to understand the impact of shifting nighttime load to the
day time. Figure below presents the Load Profile for Island A Scenario 3.
Putting the load profile into my Excel Application yielded the following results
Effect of different Solar Fractions (SF) on the Levelized Cost of Electricity (LC) and
the comparison with Scenario2
Figure 6.r: Levelized Cost vs Solar PV Price for Island A- Scenario3 (and comparison with Scenario2
In scenario 2, we found that at 13% Discount Rate, Levelized cost at Solar Fraction of
0% was similar to Solar Fraction of 60%, but in this scenario this situation will come at
much higher discount rates.
This show that even at much higher discount rates, Solar penetration will be desirable in
Scenario 3.
In Scenario 2, we found that any solar penetration was not feasible at Euro 2.5 / Wp,
however, in this scenario, solar penetration will be viable at rates even much higher than
Euro 2.5 Euro/Wp
Island B has a bigger Electric Load, with a significant Load in the day time. System
modeling for Island B will also help us in understanding the impact of solar penetration in
the above mentioned scenario.
Putting this load profile in my excel application, I got the following results (snapshot)
It is clearly visible from the graph below that in island B, there is further reduction of
around 5 Euros cents in all solar penetrations.
Although, there is no relation between Load of Island A-Scenario 3 and Load of Island B,
however, this sensitivity shows that with the growth of load in the day time, there will be
significant reduction of LC.
The figure below shows the effect of different Discount Rates on Levelized Cost of
Electricity
Any Solar Penetration will be better then SF=0% (ie Diesel ONLY case)
Diesel Only case (SF=0%) has no influence to the changing discount Rates
There is a reduction of upto 40% in the LC between SF=1 and SF=0
During my survey in Island B, I realized that there is a vast potential of utilizing roof tops
of Resorts for PV installation, because of the following reasons:
Resorts have a significant day time load which will match the Solar PV
generation
There is a good amount of Roof tops available on the resorts
The Price of electricity is already very high in island B and Resort owners
showed an inclination of Roof Top Solar in their resorts.
Further, as seen in chapter 6, we found that any penetration of solar in Island B Grid is
much economical then Only Diesel Option. Therefore, there is a strong case of putting
solar on the rooftop of the resorts.
After my discussions with PSPI staff, I did an indicative assessment of the Rooftop Solar
PV potential of the resorts. I was assisted by a PSPI staff, Mr Ian, who helped me in
seeing around all the relevant resorts.
Section 7.1 of this chapter presents my methodology of the roof top PV assessment.
Section 7.2 presents the rough sketches of the relevant resorts. Section 7.3 presents the
possible Solar PV installation on the roof tops of the resorts and the methodology of
calculation.
I. Rooftop Area
For its rated performance, Solar PV panels should always be facing South
direction, at an inclination which should be equivalent to the latitude of the place
of installation. There should off course be no hindrance to the sunlight. Rooftops
should therefore be accordingly chosen.
II. Structural strength of Rooftop: The roof of the building should be capable of
handling the mechanical stress of Solar PV. Solar PV installation would also
require mounting structure to be drilled and fastened into the roof, so rooftop
should be accordingly capable.
It is to be noted that there were few resorts/ resort buildings whose roofs were neither
concrete, nor semi concrete, nor Tin, so we did not include them in our assessment.
Further, there were some resorts who were either surrounded by buildings or dense
trees, so we did not include them either. Section 7.2 presents all the rough sketches
along with the dimensions and directions.
In Section 7.3, I have presented the amount of Solar PV that can be mounted on the
roofs of the resorts and the methodology of calculating the amount of Solar PV that can
be installed.
Presented below are the Resorts along with their roof tops and the relevant roof top
areas for Solar PV Installation
1)Resort A
I found 3 types of roof tops in the resort. These are shown below. Rooftops are marked
in Alphabets in the following pictures.
I am naming this Roof Top as Roof Top A. There were 3 such cottages in resort A with
the same orientations. The side facing South can be utilized for Solar PV installation.
The relevant area is 48m2(12m*4 m). Since, there were 3 such cottages, so total area of
144 m2. It is to be noted that there were few trees in front these cottages, which can be
trimmed regularly.
Roof Top C is a roof top of another type of Cottage in the resort. The side of the roof top
with orientation towards South is shown above. The relevant area is around 60m2
(10m*6m)
Total Relevant Roof Top Area in the resort is 700 m2 (Rooftop A+ Rooftop B+
Rooftop C)
The relevant roof top facing south has an area of 100 m2 (30 m *5m Area of Windows).
There were few trees near the building which can be trimmed regularly.
3) Resort C
Resort C had 2 relevant roof tops (Roof Top F and Roof Top G). Roof Top G could
be utilized for Solar PV installation
4) Resort D
It is a perfect Area for Solar PV installation with roof facing South and no obstruction
from trees. Total relevant Area is 160 m2 (2 times of 16m*5m)
Area of the South facing roof is 80 m2 and there are 2 such buildings, So Total relevant
Area of 160 m2
6) Resort F
7) Resort G
Shown below is the rooftop of Resort G, however, it might not be very suitable for Solar
PV installation because rooftop is of Tin and its orientation is not South facing.
8) Resort H
Shown below is the roof top of Resort H, however, its orientation is not fit for Solar PV
installation
In Section 7.2, I found the relevant Roof Top Areas (of Resorts) in Island B. In this
section, I present the amount of Solar PV that can be installed on the roofs.
For calculating amount of Solar PV that can be installed on the roof, I have utilized the
following thumb rule:
# It is to be noted that different Thin film technologies have different Area requirements.
In my calculations, I considered Copper Indium Diselenide. If thin film technology is
Amorphous Silicon, then the area requirement will be even bigger: 18m2/ KWp
Based on the above thumb rule, following table presents the amount of Solar PV that
can be installed on the respective Resorts.
A
B
C
D
E
F
The table presents that for example, resort As rooftop can host 100KW p of Mono
Crystalline PV or 78KW p of Polycrystalline PV or 54KW p of Thinfilm PV.
Combining all the resorts, there is a possibility of putting 223KWp of Mono Crystalline
PV OR 173KWp of Polycrystalline PV OR 120KWp of Thinfilm PV in the entire island.
In addition to this, there could also be possibility of putting Solar PV on the grounds or
on the roof tops of some households.
General:
There is a vast scope of solarizing existing Diesel Mini Grids/ establishing stand
alone Solar Mini Grids in Philippines [400 MW and above]
Government is pumping significant subsidies on Diesel Mini Grids and it is a
huge burden
The policies related to Off grid Renewable Energy are unclear in Philippines,
however, the same has a vast scope in the country
Specific to Island A:
In the existing scenario, where several small Diesel Gensets are serving to
several small clusters of households, people are paying a very high cost of
electricity (~2 Euros/ KWh); Also the cost of electricity generation is very high to
individual Genset owner (~1 Euro/ KWh)
I had then proposed a Solar-Diesel Hybrid Mini Grid where a Central Power
Converter (Master Inverter on the lines of SMA Sunny Island) plays the role of
Master with power inputs from Solar, Diesel and Battery BackUp. Following were the
main findings
In Scenario 2 (where the existing load is assumed to get increased at the same
night timings), it was observed that the Levelized cost of Electricity will come
down only slightly as compared to Scenario 1, however, the drop is not
significant. This is despite of the fact that investment cost will become almost
double in Scenario2.
In both Scenario 1 and Scenario 2, if the cost of Solar PV is higher than 2.5 Euro/
Wp, then any solar penetration will be undesirable.
Note: It is to be noted that in the entire analysis, the cost of battery is taken to be
135Euro/ KWh with 70% DoD. This is as per the market prices in Philippines for
AGM Lead Acid batteries. If the cost of batteries is higher, then solar penetration
in Island A-Scenario 1 and Scenario 2 will be undesirable (because of big night
time loads and large battery bank requirements).
In Scenario 3, solar penetration will be viable even at higher discount rates (13%)
Specific to Island B
Applying the same model to Island B, it was observed that LC will decrease with
increasing Solar Fraction and any solar penetration will give better LC as
compared to Diesel ONLY option.
Although there is no direct relation between Island A and Island B, however
Island B has a significant load in the day time compared to Island A-Scenario 3.
While comparing the two, Island B shows more drop in LC compared to Island A-
Scenario3. This means that as the load will grow in day time, LC will decrease
significantly.
It was also observed that there is a strong case of putting Solar PV on the
rooftops of Island Resorts. An estimated 173 KWp of Polycrytalline Solar PV
can be put on the roof tops of the selected Island Resorts. Open grounds in
island B provides further opportunity of Solar PV installation in the island.
Visit to Island C, was utilized to understand the execution of Diesel Mini Grids by
NPC-SPUG and it also helped in developing Scenarios for Island A. No modeling
was done for Island C.
ANNEXURES
Annexure 1
There were 2 different forms used for household survey (one developed by me
and the other developed by PSPI)
Household Survey form (No 1)
Location: _______________________________________________________________
(Sitio) (Barangay) (Municipality) (Province)
I. SOCIO-ECONOMIC DATA
3. Household Size: _______ (Number of household members living in your house at least 6
months within a year).
4. Housing conditions
Expenditure on electricity
Expenditure on rest
1.1 What are your sources of energy for lighting and operating home appliances? (Please
check, household can have more than one sources)
Kerosene
Drycell/Battery
Car battery (powered by some minigrid or Genset)
Personal Diesel Genset
Connection to Diesel Genset MiniGrid
Gas Light
Solar system
1.2 What are the uses of the sources of energy mentioned above? (Appliance Details)
Frequency of
S.No Type of Energy Cost per purchase/charge Cost per
Source purchase per month for year
lighting/ other
electricity use
2.1 Kerosene P_____ per
liter
2.2 Drycell batteries P_____ per
pc.
Cont..
2.5.2 Total number of households connected to the same Genset? _____________ households
2.5.6 How much is the charge per light/bulb (Indicate the cost opposite each bulb)
10 Watts P __________ 40 Watts P __________
20 Watts P __________ Others, specify _________ P __________
2.5.7 How much is the charge per appliance? (Indicate the cost opposite each appliance)
B&W TV P __________ VCD P __________
Karaoke P __________ VHS P __________
Others, specify ____________________ P __________
2.7 Solar System (Do you have Solar Home System in your house)
1.1 What time of the day do you think electricity is most needed? (Please check)
Whole day (24 hrs.) From 6pm to 6am
From 6pm until 10pm Others, pls. specify __________________
1.4 Based on your estimates, your household spends about P ____________ per month of
lighting. If electricity were to be improved, how much more are you willing to pay per
month?
P ____________
1.5 Which of the following electrical appliances do you plan to acquire within the next 6
months if electricity would be improved? (Please check)
Radio/Cassette Refrigerator
TV black/white Electric flat iron
TV colored Computer
Electric fan Electric machinery or tools
Washing machine Others, pls. specify ____________________
NOTES:
..
I. Technical Questions
c) Distribution network
What is the typical length of distribution network? What are the
specifications of wires? [ mini-grid operator can atleast give some idea]
What is the operating voltage and frequency of the system and what are
their typical deviations?
How is electricity metering done?
Any idea on distribution losses
Annexure 3
Result of Household Survey (Electric Load)
Scenario 1 Load
Scenario 2 Load
For executing my Master thesis, I utilized information from the following references: