Escolar Documentos
Profissional Documentos
Cultura Documentos
WHY BOTHER?
1.
Can
we
Win?
2.
Can
we
deliver?
3.
Will
we
make
a
prot?
An
enthusiasIc
bid
team
will
always
answer
YES
to
all
3.
3.
What
%
condence
do
you
have
achieving
target
margin?
3a.
Show
me
how
you
came
to
that
gure
Copyright
@
2011.
All
rights
reserved
ObservaIons
o Bidding
stage
is
o]en
the
Ime
we
are
most
uncertain
about
a
projects
nal
cost
n Li`le
structured
Ime
is
o]en
devoted
to
understanding
this
uncertainty
n OrganisaIons
lose
money
because
of
this.
o ConIngency
is
o]en
removed
because
we
cant
defend
it
n Bid
Reviews
n Customer
intervenIon
o Key
to
defending
conIngency
n High
quality
risk
descripIons
and
esImates
n A
well
thought
out
and
logical
cost
risk
model
n Clear
understanding
of
risk
ownership
JUBILEE LINE
Original Cost Estimate (1.5Bn)
Final Cost (3.5Bn)
2 years late
GETTING IT RIGHT
? No of Data Fields
100+
Risks
A default assumption that overall risk is equal to the sum of the risk in the risk
register is usually irrational
In practice, this approach may help win a project or get it started, but only at the
expense of significant downstream difficulties
60
PMO
50
development
40
supplier
cost
30
PLANNED
20
10
0
0.0
2000.0
4000.0
6000.0
8000.0
10000.0
12000.0
14000.0
Cost
k
Mutually
Exclusive
Select
Company
A 30 0
Select
Company
B 70 1
Total
Contractor
Price
() 8544.54
Other
Costs
Development
100 1 1050 1400 1900 1500 1500
PMO
Costs
100 1 1100 1220 1800 1100 1100
Trails 100 1 200 450 600 500 500
Training 100 1 0 250 300 260 260
TOTAL 11904.54
80
70
60
Condence
50
40
1st
pass
Output
30
PLANNED
20
2nd
Pass
Monte
Carlo
Output
10
0
5000.0
6000.0
7000.0
8000.0
9000.0
10000.0
11000.0
12000.0
13000.0
14000.0
15000.0
Cost
k
o Less
risk
than
rst
pass
(note
the
angle
of
the
curve)
o Key
Drivers
n Material
uctuaIon
n Exchange
Rate
(mulIplicaIve
eect)
o PotenIally
dramaIc
eects
n P80
First
pass
=
12.3M
n P80
Second
pass
=
11.2M
o 2nd
pass
uses
a
more
detailed
and
representaIve
model
o 3rd
pass
and
so
on.
RISK DESCRIPTIONS
Impact
Delay to the commencement of Electrical
systems integration
RISK ESTIMATES
Heuristics
Probability density
Multiplicative effects
Copyright
@
2011.
All
rights
reserved
CONTEXT
AND
SOURCES
OF
UNCERTAINTY
n InvesIgaIon
into
sources
of
uncertainty
o Baseline
assumes
100
cables
per
vehicle,
where
as
it
could
be
between
80
and
150
o Up
to
100%
of
cables
might
need
screening,
+500
per
cable
o Average
unit
costs
historically
vary
from
700
1300
for
cables
n WORST
CASE
ESTIMATE
COULD
BE
o 270,000
per
vehicle
n BEST
CASE
COULD
BE
o 56,000
per
vehicle
n FLEET
COST
o 5.6M
and
27M
Copyright
@
2011.
All
rights
reserved
Improved
Three-Point
EsImates
1. Develop a sound description of the risk involved,
identifying all significant sources of uncertainty
2. Clarify with the estimator the implications of
Context using extreme points or confidence points
(Relevant Facts)
3. Make the Worst case estimate, based on how
sources of uncertainty could combine
4. Make the Best case estimate, combining
Source(s) of optimistic estimates for each factor
uncertainty
5. Make a realistic Most Likely (Mode) estimate
based on a balanced judgement
RISK OWNERSHIP
Source Risk
of risk owner
Agreement Risk-bearing
e.g. contract organisation