Escolar Documentos
Profissional Documentos
Cultura Documentos
CONSTRUCTION PHASE TO
OPERATIONAL PHASE
A Chapman
K Gormley
K Lutz
D Turner
C Clarke
D Phipps
Contents:
Introduction
Contract Conditions
Engineering Perspective
Appendices:
2
Introduction
The handover process of a construction project to the Owner, and hence the transfer of risk
from the construction insurances to the operational insurances, should be a relatively simple
affair.
All that needs to be done is for pre-agreed criteria in the Contract Conditions to be met, such
as pre-agreed performance levels between the manufacturer/supplier and the principle,
followed by a continuous test run for an agreed time, normally 72 hours ultimately resulting
in the approval of the principle and/or his representatives/consultants, and the signing of the
appropriate handover certificate.
However, the handover process is rarely simple. Disputes often arise over whether the
performance criteria have been reached, whether all equipment is operating correctly, and
many others. Too often a snag list or punch list of items to be resolved remains. The
project can often be transferred to the principle and the operational programme before the
handover criteria have been achieved. On other occasions the risk remains completely or
partially insured under the construction insurance policy, with the majority of equipment
operating while the disputed items are fixed
Obviously the handover process is vitally important to both construction and operational
insurers. The purpose of this study is not to prepare a clause or wording, but to examine the
handover process and highlight some of the issues that can occur. A team of senior
underwriters have formed to carry out this study. To this group was added Kevin Gormley,
Engineering Manager of QBE Marine and Energy Syndicate 1036, who has already prepared
and delivered a presentation to OPERA on the Engineering aspects of handover, together
with Adam Chapman, Vice President of Marsh Energy, who has extensive knowledge of
contract conditions.
This study is divided into three sections, the first being a review of contractual structures and
their bearing on the handover process; engineering perspectives of the handover process and
some examples of handover clauses in current use.
Contractual Structures
3
The purpose of this section is to provide a background as to the various contractual structures
that might be used in a construction project, and examine how they might influence handover
to an operational policy
Contract Structures
There are a number of different ways that a construction project maybe structured from a
contractual viewpoint. The list below is suggested to be the main structures typically
encountered.
Types of Contract
4
Design Build and Operate
This is a variant where the contract is responsible for designing, building and then operating
the plant. This is more applicable to projects where the construction contractor takes the role
of the operations and maintenance contract after completion.
Installation Contractors
This is a variant where the contractor is responsible solely for the installation of the works,
i.e. the design is carried out by another party, as is the purchase of the equipment. In this
variant the contractors responsibility typically ceases at MC.
Vendors
For specialist items of equipment, for instance gas turbines / compressors etc, the vendors
will produce onsite assistance during the commissioning activities.
Licensors
In certain cases in which the process is licensed there will be representatives of the licensor
providing advice to the commissioning team. Under the license arrangement there may also be
separate obligations in terms of performance / reliability testing and financial commitments.
Types of Reimbursement
There are various ways in which a contractor can be reimbursed for his contract, and these
are sometimes referred to when specifying the type of contract. The main arrangements are:
Lump Sum (LS) or Lump Sum Turn Key (LSTK), where an all in price is agreed for
the execution of the contract. Turn Key contracts imply that the plant is commissioned by
the contractor, and then turned over in an operating state.
Cost Reimbursable are contracts whereby there is a predetermined formula for arriving at
the contractors remuneration based on the cost expended. (Variants of this type are for
instance open book contracts, cost plus etc.)
Target Price contracts are similar to cost reimbursable but where a target price is agreed
and remuneration is based around the target price.
5
Common Features
Definitions
All contracts will typically contain a definitions section. Whilst this paper contains
suggestion as to the meanings of a particular term and its use within this paper, it should be
noted that all contracts vary and therefore the definitions section of a particular contract
should be referred to, to determine the meaning of a particular term in context.
Mechanical Completion
Whilst the specifics vary from contract to contract, generically this is the point at which a
system or the plant as a whole is mechanically complete, and ready for pre-commissioning.
Precommissioning
Commissioning / testing prior to the introduction of feedstock. This is typcially done on a
system or subsystem level and may involve the energisation of the system, cold dynamic
testing etc. Typically it does not involve the introduction of feedstock, although from an
insurance viewpoint it may involve the introduction of hydrocarbons for the drying out of
refractory linings, preloading of reactors etc.
Performance Test
A test of the plant performance, usually for a short duration such as 72 hours during which
nameplate capacity has to be achieved and maintained. However it should be noted that this
test also typically includes a number of other criteria that need to be met as well as
production:-
6
Reliability Test
Some type of plants also have reliability tests. These are longer in duration than the
performance testing being typically 30 90 days, and monitor availability and consumption
typically rather than maximum output.
Contract Forms
The vast majority of construction contracts for major projects are bespoke contract forms, and
a couple of examples of these are included in Appendix 2 to this paper. However there are
also several standard contracts such as FIDIC and IChemE that form the basis of contract for
smaller projects and are in widespread use.
Bespoke Forms
Unfortunately these tend to be tailored to the particular project and therefore it is difficult to
generalise regarding such. However most detail the transition to completion via a series of
steps of mechanical completion, pre-commissioning leading to ready for start up,
commissioning leading to the performance test and issuance of a provisional acceptance
certificate.
FIDIC
FIDIC contracts have four main types of contract:-
Conditions of Contract for Construction for Building and Engineering Works Designed
by the Employer: The Construction Contract (the new Red Book)
7
Conditions of Contract for Plant and Design-Build for Electrical and Mechanical Plant
and for Building and Engineering Works, Designed by the Contractor The Plant and
Design/Build Contract (the new Yellow Book)
Conditions of Contract for EPC/Turnkey Projects: the EPC Turnkey Contract (the Silver
Book)
A short form of contract (the Green Book).
The forms use terms such as Tests on Completion, Performance Test and Taking Over
Certificates. Tests on Completion are divided into three categories, being:-
Pre-commissioning
Commissioning
Trial Operations
Taking Over Certificates are typically issued upon completion of the Test on Completion for
a particular element, however it may also be issued due to failure to perform either by the
contractor or by the principal the tests within a designated timeframe. The Performance
Certificate is issued upon expiry of the Defects Notification Period.
8
Also requires
Official acceptance by Insured.
Plant handed over without reservation or waiver of guarantee
No equipment faults or punchlist items affecting operational integrity
No temporary structures or start-up modifications
72 hours run
Official Acceptance
Most operational insurers determine official acceptance as the issuance of the provisional
acceptance certificate. However as mentioned above this can happen for reasons other than
those intended by the operational insurers. Furthermore it should be noted that typically it is
only a provisional acceptance certificate that it is used following the performance test, the
final acceptance certificate only being issued after the defect liability period.
9
Without reservation
From a contractual compliance viewpoint this is very difficult to comply with, since in the
vast majority of cases the Principal will retain certain rights against the contractor following
acceptance, even if it is only that of the remedying of defects during the defects liability
period, and completion of the outstanding punchlist items (see below).
Punchlists
In the vast majority of cases in order to move from mechanical completion to ready for start
up the more serious of the punchlist items (typically called Category A and B items) will
need to be resolved. Category C items (i.e. those that remain whilst the plant moves into a
commissioning phase) are typically items such as painting, making good, and removal of
items from site. Therefore from a contractual viewpoint this can generally be complied with.
Engineering Perspective
The handover process involves two teams of engineers, both working towards the same goal,
but from different perspectives. On the one hand, there are the engineering designers,
manufacturers and contractors who are trying to ensure that the plant perfumes adequately to
match the handover criteria; and then there are those of the owner, who are monotoiring
performance to ensure that the plant performs to the required criteria.
10
From the engineering perspective (and insurers and reinsurers too) the testing and
commissioning period is the most difficult and potentially hazardous part f the construction
phase. It comes at the end of a hectic construction programme with intense pressure to bring
plant and equipment to operation as quickly as possible. It brings a disparate mix of
equipment from their as-built state into operation as a dynamic process, operated by human
beings and producing saleable products. The presence of feedstock also increase risk
exposure levels.
Precommissioning/Cold Testing encompasses all static and non-energised checking and test
work, necessary to ensure that a given system is built according to project specifications and
documents
Diagram to be inserted
Diagram to be inserted
11
Testing and Commissioning Typical Time line
Diagram to be inserted
Diagram to be inserted
12
Testing and Commissioning Example of Workload
140 sub-systems
6,500instrument loops
Introduction of hydrocarbons
13
Introduction of Feed
Most construction projects are commissioned and start operation with only minor problems,
resolved in the normal course of operation.
Some construction projects suffer damage and delays that can be related to one or more of the
following:
Poor planning
Rushed installation
Poor QA / QC
Inadequate design
14
Testing and Commissioning Typical Incidents
15
Insufficient feed to test at 100% capacity
Batch operation, not all plant run and tested for 72 hours before handover and transfer
to operational insurances
Phased handover, again not all plant run and tested before handover and transfer to
operational insurances
Design issues prevented 100% operation before handover and transfer to operational
insurances
When a plant cannot strictly comply with the contract criteria for handover,
underwriters should require an engineering review consisting of:
Reasons why Testing and Commissioning clause in the operational insurance policy
cannot be complied with
The Insureds plan to test and commission the rest of the plant
These clauses are current examples and are not deemed to be approved or recommended by
LEG.
16
Property and Plant Testing and Commissioning Clause
This clause was originally drafted by IOI and CIGNA in the 1990s following a number of
incidents that followed handover from the construction phase to the operational phase without
he achievement of the handover criteria. It is still very much in general use.
It is hereby noted and agreed that this insurance does not cover destruction of or damage to
property in course of construction or erection, dismantling, revamp or undergoing testing or
commissioning including mechanical performance testing and any business interruption
resulting therefrom.
It is further noted and agreed that the above provisions do not apply to normal routine
maintenance activities and schedule turnarounds.
Some other clauses supplied by LEG members are also currently in usage:
Handover
Notwithstanding that phases or sections of the Project will be completed and/or handed over
prior to completion of commissioning of the last phase or section of the Project the cover
provided by this Policy shall continue for the benefit of the Principal in full force and effect
with respect to all the lnsured Property until the completion of commissioning of the last
phase or section of the Project but excluding any such completed and/or handed over phase(s)
17
or section(s) in full commercial operation other than in connection with the completion or
ramp up of the Project.
Notwithstanding that sections of the insured contract will be completed prior to completion of
commissioning of the last section of the contract the cover provided by this Policy shall
continue in full force and effect for all of the lnsured Property until the completion of
commissioning of the last section of the contract but excluding any handed over section(s)
that have reached the contractually agreed specification and are in full commercial operation.
Conclusions
This exercise has taken a considerable time to prepare, and hopefully manages to convey the
problems and pitfalls that can be encountered in the handover process.
There is still a considerable amount of research that is left to be done, and it is hoped that this
Study Group can continue to work on this subject and take this report to a more detailed
level.
18
October 2009
19