ID Task Name Duration Start Finish

k -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20
T T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S
0 SCLBH-ACCOMODATION BLOCK 122.75 Thu 3/28/13 Fri 8/9/13
days

1 MOBILISATION 2 days Thu 3/28/13 Fri 3/29/13

2 Mobilisation and site clearance 2 days Thu 3/28/13 Fri 3/29/13 Mobilisation and site clearance

3 SUBSTRUCTURE 26.56 days Thu 3/28/13 Thu 4/25/13

4 Trench excavation 5 days Thu 3/28/13 Tue 4/2/13 Trench excavation

5 Strip Concreting 2 days Tue 4/2/13 Thu 4/4/13 Strip Concreting

6 Plith Walling 5 days Mon 4/8/13 Fri 4/12/13 plinth Walling

7 Back and Murrum filling 4 days Fri 4/12/13 Wed 4/17/13 Murrum filling and compaction

8 Hardcore placement 4 days Wed 4/17/13 Mon 4/22/13 Hardcore placement

9 Blinding and laying DPM & Slab formwork 1 day Mon 4/22/13 Tue 4/23/13 Blinding & DPM & Slab formwork

10 Casting slab concrete 3 days Tue 4/23/13 Thu 4/25/13 Concrete slab casting

11 WALLING AND FRAME 22.13 days Tue 4/30/13 Thu 5/23/13

12 General walling 15 days Tue 4/30/13 Thu 5/16/13 General Walling

13 Beam steel work 5 days Mon 5/6/13 Fri 5/10/13 Beam steel work

14 Beam form work 4 days Thu 5/9/13 Mon 5/13/13 Beam form work

15 Casting beam concrete 4 days Mon 5/13/13 Fri 5/17/13 Casting beam Concrete

16 walling above beam 3 days Tue 5/21/13 Thu 5/23/13 Walling above beam

17 ROOF CONSTRUCTION 21 days Thu 5/16/13 Fri 6/7/13

18 Roofing 21 days Thu 5/16/13 Fri 6/7/13 Roofing

19 WINDOWS AND DOORS 32.63 days Tue 4/30/13 Tue 6/4/13

20 Fabrication of windows abd doors 21 days Tue 4/30/13 Wed 5/22/13 Fabrication of windows and doors

21 Fitting Windows 4 days Mon 5/27/13 Thu 5/30/13 Fitting Windows

22 Fitting Doors 5 days Thu 5/30/13 Tue 6/4/13 Fitting Doors

23 MECHANICAL INSTALLATIONS 86.06 days Tue 4/16/13 Thu 7/18/13

24 Plumbing & mechanical installations 20 days Tue 4/16/13 Wed 7/17/13 Plumbing & mech Installations

25 Electrical installations 9.56 days Fri 5/31/13 Thu 7/18/13 Electrical Installations

26 PLASTERING 8 days Fri 6/7/13 Mon 6/17/13

27 Internal plaster 8 days Fri 6/7/13 Mon 6/17/13 Internal plaster

28 External finishes 4 days Wed 6/12/13 Sat 6/15/13 External finishes

29 CEILING 20 days Mon 6/17/13 Tue 7/9/13

30 Ceiling timber framing & fixing boards 20 days Mon 6/17/13 Tue 7/9/13 Ceiling timber framing

31 Floor 5 days Tue 7/9/13 Sat 7/13/13 Floor Screeding

32 Painting 21 days Sat 7/13/13 Tue 8/6/13 Painting

33 SITE CLEANING 2 days Tue 8/6/13 Thu 8/8/13 SITE CLEANING

34 HAND OVER 1 day Thu 8/8/13 Fri 8/9/13 HAND OVER

Project: SCLBH-ACCOMODATION BL Task Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Deadline
Date: Fri 4/12/13