Appendix A: Crane Pre-Lift Inspection Checklist

Crane Pre-Lift Inspection Checklist

Operating Group : SMO KLO GPO-I GPO-P


Location : Date:

The Crane Pre-Lift Inspection will include, but not be limited to, the following: Y N N/A

1 Visually inspect boom and lattice for any sign of damage

2 Visually inspect crane, rigging and hooks for missing nuts, bolts, pins or keepers

3 Ensure the area around the base of the crane is free from all obstructions

4 Check fluid levels in the engine fuel, water and oil, also check the hydraulic oil level

5 Ensure the engine safety devices, i.e., controls are set

6 Visually inspect all wire rope for damage and correct spooling

7 Check all controls for correct operation, control levers are spring loaded and must return
to the center or neutral position when released

8 Check weight and radius indicator are functioning properly, load chart

9 Start engine and run at idle speed for 3 to 5 minutes to allow the engine to warm up.
While warming up the engine, check around for any sign of water, oil or hydraulic leaks

10 Raise the boom, test the anti-two block and boom kick out functions

11 Lower the boom and check boom tip sheaves, and ensure the wire rope is on the
sheave

12 Report any abnormalities and DO NOT operate the crane

13 On completion of crane operations, lay the boom in the boom rest or away from the
helideck, set all controls to off or neutral, and set the swing lock

Note: Y = yes, N/A = not


applicable
Appendix B: Monthly Crane Inspection Checklist
Monthly Crane Inspection Checklist

Operating Group : SMO KLO GPO-I GPO-P

Location : Date:

This inspection will be performed once per month for all cranes assigned a heavy usage category. This inspection will be
performed by a Qualified Crane Operator or a Qualified Crane Inspector and shall be recorded.
Monthly inspections will include, but not be limited, to the following:

No Object To Inspect Y N N/A


1 Check all ladders and cages
2 Check boom rest
3 Inspect crane structure
4 Inspect boom
5 Sheaves and Drums
a. Sheaves shall not have excessive wear on shoulders, grooving or gouging in the
cradle
b. Check sheave bushing and bearings for excessive wear
c. Drums shall be free of gouges and excessive wear
6 Wire rope
Check for excessive wear or damage such as broken strands, reduction in
diameter, kinks, corrosion etc
7 Check condition of cab
8 Inspect load block, head ache ball, & hooks
a. Check hoist block body for cracks, breaks, excessive wear or missing parts
b. Check hook for bends, cracks, corrosion, and enlarged throat opening, free swivel
Action, and operational safety latch
9 All pins
a. Shall be lubricated as needed
b. Retainer shall be in place and operational
c. Pins should not be excessively worn
10 Inspect electrical system
11 Check anti-two block system
12 Check boom hi-angle kick out
13 Lubricate boom foot pins
14 Lubricate ball ring and pinion
15 Lubricate all pins
16 Inspect wedge sockets
a. Main
b. Auxiliary
c. Boom
17 Engine (check for any irregularities or power losses. Gages must be operational and
legible)
a. Oil pressure & level
b. Coolant level
c. Fuel level
d. Drive belts
e. Hoses
f. Exhaust system
g. Starter
h. Emergency Shut Down (ESD)
i. Battery and Charging System
18 Hydraulic System
a. Hydraulic oil level (fluid level shall be maintained and reasonably clean)
b. Hoses and fittings (lines shall be free of nicks, bulges, abrasions, or leaks)
19 Load Limit and Safety Devices
20 Control station
a. Check all controls for proper labels
b. Check all controls for proper operation (hoisting, swing, travel, & boom)
c. Check boom angle/radius indicator
d. Check drains and drip pans
21 Winches, cylinders and gear boxes
a. Check for exterior leaks or damage
b. Check winch oil level
c. Check all mounting bolts
d. Ensure wire rope is lubricated
e. Check hydraulic cylinder operation
22 Clutches
a. All bands and plates shall be properly lined and in good condition
b. The operation shall be smooth with no grabbing
23 Outriggers
a. Outriggers shall extend and retract completely, with pins and retainers in good
operational condition
b. Check valves shall be protected where required
c. All leveling devices must be operational and legible
24 Fire Extinguisher
a. An all purpose fire extinguisher shall be fully charged and properly mounted
25 Audible Warning Device
Note: The above guide will vary according to crane type and model Y = yes, N = No, N/A= not
applicable
Appendix C: Semi/Annual Crane Inspection Checklist

TDI
Annual Crane Inspection

Location : Date :
Crane Model : Crane Serial :

Safety YES
1 Perform JSA prior to beginning inspection
2 Perform Pre-use Inspection NO NA
Engine
1 Drain sludge/water from fuel tank
2 Check emergency shutdown at idle speed
3 Check condition of drains and drip pans
4 Change oil in all gearboxes
5 Check air box drain tubes
6 Check security of engine hold down bolts
7 Check condition of hydraulic system
8 Inspect/lubricate throttle linkage
9 Inspect/lubricate tach. drive
10 Lubricate fan shaft bearing
11 Replace fuel filters
12 Clean/replace air filter
13 Change crankcase oil and filter
14 Clean breather cap
15 Inspect/replace hydraulic starter fluid
16 Clean blower screen
17 Inspect exhaust system
Hydraulic System
1 Change hydraulic oil filters
2 Inspect hydraulic oil
3 Drain sludge/water from hydraulic reservoir
Upper Revolving Structure
1 Check and lubricate chain and sprocket
2 Lubricate ring gear and pinion
3 Lubricate ball ring
4 Inspect ball ring grease for metal content
5 Check ball ring bolts
6 Rotate crane 360 and check smoothness of rotation
7 Change oil in swing gearbox
Boom, Sheaves, and Winches
1 Check boom foot pin clearance and lubricate
2 Inspect boom for damage
3 Inspect and lubricate sheaves
4 Inspect/lubricate boom stops
5 Lubricate retractable booms
6 Inspect boom angle/radius indicator
7 Ensure cable is properly secured in winch(s)
8 Visually inspect open brakes
9 Inspect drums and flanges for cracks/wear
10 Check hydraulic cylinder(s) operation
Take oil sample on all winches for analysis and change
11
oil.
12 Test winch brakes
13 Test static swing brake
14 Check the boom high angle kick-out setting
Wire Rope and Hooks
1 Ensure load block/headache ball is painted
2 Ensure load block is drilled to drain water
3 Dye penetrate test all hooks
4 Remove and inspect headache ball pin
5 Cut 36 off ends of all cable
6 Inspect and lubricate all wire rope
General
1 Check condition of cab
2 Inspect electrical system
3 Inspect crane structure for cracks/corrosion
4 Visually inspect general condition of welds
5 Inspect/calibrate weight indicator
6 Review crane files for proper documentation
Inspection Readings Reading Measurement (1) Reading Measurement (2)
1 Record Accumulator Pressure
2 Record Engine Hour Reading
3 Record Hydraulic Return Pressure
Hydraulic Pressure Settings
1 Boom Winch Relief Valve Pressure Settings
2 Main Winch Relief Valve Pressure Settings
3 Auxiliary Winch Relief Valve Pressure Settings
4 Operator System Pressure Setting
Cable and Hook Measurement
1 O.D. Measurement Boom Cable
2 O.D. Measurement Main Cable
3 O.D. Measurement Auxiliary Cable
4 O.D. Measurement Left Pendant Cable
5 O.D. Measurement Right Pendant Cable
6 Main Hook Throat Measurement
7 Auxiliary Hook Throat Measurement
Cable Certification Manufactured Date Certification Number
1 Boom Cable
2 Main Cable
3 Auxiliary Cable
4 Left Pendant Cable
5 Right Pendant Cable
Winch Identification Date Installed Winch Model # Winch Serial #
1 Boom Winch
2 Main Winch
3 Auxiliary Winch
Anti-Two Block & Boom Kick-Out Ident. Manufacture Model #
1 Boom Kick-Out Valve
2 Main Block Anti-Two Valve
3 Auxiliary Ball Anti-Two Valve
Upper Revolving Structure OK NOT OK
1 Ball Ring (Record 4 observed Readings)
NORTH SOUTH EAST WEST

2 Check Boom Sheave Groove Diameter
3 Check Gantry Sheave Groove Diameter
4 Check Load Block Sheave Groove Diameter
5 Check Boom Foot Pin Clearance
6 Check Gantry Pin Clearance
7 Verify Accuracy of Angle / Radius Indicator
Pull Test Data
Load Line
1 Boom Angle
2 Radius (FT.)
3 Rated Capacity (Lbs.)
4 Load Pulled (Lbs.)
5 % Rated Capacity (%)
Auxiliary Line
1 Boom Angle
2 Radius (FT.)
3 Rated Capacity (Lbs.)
4 Load Pulled (Lbs.)
5 % Rated Capacity (%)

Inspector Signature: Date: