ID Task Task Name Duration Start Finish 2016 2017 2018

Mode Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
1 1.0 Land Ownership Transfer 40 days Mon 4/4/16 Fri 27/5/16
2 MS1 Commencement of Project 0 days Fri 27/5/16 Fri 27/5/16 27/5
3 2.0 Preliminaries Works 40 days Mon 30/5/16 Fri 22/7/16
4 2.1 Site Inspection and 7 days Mon 30/5/16 Tue 7/6/16
Investigation
5 2.2 Liaise with Authorities 14 days Wed 8/6/16 Mon 27/6/16
6 2.3 Pre Development Cost 7 days Tue 28/6/16 Wed 6/7/16
7 2.4 QA/QC Programme 7 days Wed 8/6/16 Thu 16/6/16
8 2.5 Safety Measurement and 7 days Wed 8/6/16 Thu 16/6/16
Precaution
9 2.6 Site Commencement and 0 days Wed 6/7/16 Wed 6/7/16 6/7
Possession
10 2.7 Mobilization of Plants and 7 days Thu 7/7/16 Fri 15/7/16
Equipments
11 2.7.1 Resource planning 7 days Thu 7/7/16 Fri 15/7/16
12 2.8 Soil Investigation 7 days Thu 7/7/16 Fri 15/7/16
13 2.9 Site Survey and Setting Out 5 days Mon 18/7/16 Fri 22/7/16
Works
14 2.9.1 Section A (Terrace 5 days Mon 18/7/16 Fri 22/7/16
houses)
15 2.9.2 Section B (Shophouses) 5 days Mon 18/7/16 Fri 22/7/16
16 3.0 Site Clearance and Earthwork 25 days Mon 25/7/16 Fri 26/8/16
17 3.1 Site Clearing 5 days Mon 25/7/16 Fri 29/7/16
18 3.2 Excavate of topsoil and 4 days Mon 1/8/16 Thu 4/8/16
remove surplus from site
19 3.3 Excavation to formation level 4 days Fri 5/8/16 Wed 10/8/16
20 3.4 Earthfilling with surplus 4 days Thu 11/8/16 Tue 16/8/16
excavated soil
21 3.5 Earthfilling with imported 4 days Wed 17/8/16 Mon 22/8/16
materials
22 3.6 Sand blanket 4 days Tue 23/8/16 Fri 26/8/16
23 4.0 Site Utilities 15 days Mon 29/8/16 Fri 16/9/16
24 4.1 Install temporary power 3 days Mon 29/8/16 Wed 31/8/16
service
25 4.2 Install exterior fire line and 3 days Thu 1/9/16 Mon 5/9/16
building fire riser
26 4.3 Erect building batter boards 2 days Tue 6/9/16 Wed 7/9/16
and layout building
27 4.4 Temporary Facilities 7 days Thu 8/9/16 Fri 16/9/16
28 4.4.1 Site Office 7 days Thu 8/9/16 Fri 16/9/16
29 4.4.2 Worker Quarters 7 days Thu 8/9/16 Fri 16/9/16
30 4.4.3 Guard house 3 days Thu 8/9/16 Mon 12/9/16
31 4.4.4 Material Warehouse 3 days Thu 8/9/16 Mon 12/9/16
32 5.0 Geotextile 47 days Tue 13/9/16 Wed 16/11/16
33 5.1 Piling works 21 days Tue 13/9/16 Tue 11/10/16
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline
Project: ARMAJAYA LAND BERH Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 19/12/15 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Task Name Duration Start Finish 2016 2017 2018
Mode Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
34 5.2 Work below lower floor (Pile 21 days Wed 12/10/16 Wed 9/11/16
cap, Pile stump)
35 5.3 Supply non-woven textile 5 days Thu 10/11/16 Wed 16/11/16
36 6.0 Structural Works (Terrace 290 days Thu 17/11/16 Wed
houses) 27/12/17
37 6.1 Ground beam 55 days Thu 17/11/16 Wed 1/2/17

38 6.1.1 Formwork 25 days Thu 17/11/16 Wed 21/12/16


39 6.1.2 Bar bending & Inserting RC20bars
days Thu 17/11/16 Wed 14/12/16
40 6.1.3 Concreting 15 days Thu 22/12/16 Wed 11/1/17
41 6.1.4 Backfilling 15 days Thu 12/1/17 Wed 1/2/17
42 6.2 Slab 35 days Thu 17/11/16 Wed 4/1/17
43 6.2.1 Formwork 20 days Thu 17/11/16 Wed 14/12/16
44 6.2.2 Inserting BRC bars 14 days Thu 17/11/16 Tue 6/12/16
45 6.2.3 Concreting 15 days Thu 15/12/16 Wed 4/1/17
46 6.3 Columns 33 days Thu 12/1/17 Mon 27/2/17
47 6.3.1 Formwork 20 days Thu 12/1/17 Wed 8/2/17
48 6.3.2 Bar bending & Inserting RC20bars
days Thu 12/1/17 Wed 8/2/17
49 6.3.3 Concreting 10 days Thu 9/2/17 Wed 22/2/17
50 6.3.4 Erection of Scalfolding 3 days Thu 23/2/17 Mon 27/2/17
and False Work for next level
51 6.4 1st Floor Beams 50 days Tue 28/2/17 Mon 8/5/17
52 6.4.1 Formwork 30 days Tue 28/2/17 Mon 10/4/17
53 6.4.2 Bar bending & Inserting RC
20 bars
days Tue 28/2/17 Mon 27/3/17
54 6.4.3 Concreting 20 days Tue 11/4/17 Mon 8/5/17
55 6.5 1st Floor Slab 40 days Tue 9/5/17 Mon 3/7/17
56 6.5.1 Formwork 15 days Tue 9/5/17 Mon 29/5/17
57 6.5.2 Bar bending & Inserting RC
20 bars
days Tue 9/5/17 Mon 5/6/17
58 6.5.3 Concreting 20 days Tue 6/6/17 Mon 3/7/17
59 6.6 1st Floor Columns 40 days Tue 4/7/17 Mon 28/8/17
60 6.6.1 Formwork 15 days Tue 4/7/17 Mon 24/7/17
61 6.6.2 Bar bending & Inserting RC
20 bars
days Tue 4/7/17 Mon 31/7/17
62 6.6.3 Concreting 20 days Tue 1/8/17 Mon 28/8/17
63 6.7 Roof beam 42 days Tue 29/8/17 Wed 25/10/17
64 6.7.1 Formwork 22 days Tue 29/8/17 Wed 27/9/17
65 6.7.2 Bar bending & Inserting RC20bars
days Tue 29/8/17 Mon 25/9/17
66 6.7.3 Concreting 20 days Thu 28/9/17 Wed 25/10/17
67 6.8 Roofing 45 days Thu 26/10/17 Wed 27/12/17
68 6.8.1 Roof trusses 15 days Thu 26/10/17 Wed 15/11/17
69 6.8.2 Roof purlins 15 days Thu 16/11/17 Wed 6/12/17
70 6.8.3 Roof sheathing 15 days Thu 7/12/17 Wed 27/12/17
71 7.0 Structural Works (Shopoffice) 320 days Thu 17/11/16 Wed 7/2/18
72 7.1 Ground beam 44 days Thu 17/11/16 Tue 17/1/17
73 7.1.1 Formwork 20 days Thu 17/11/16 Wed 14/12/16

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: ARMAJAYA LAND BERH Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 19/12/15 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task Task Name Duration Start Finish 2016 2017 2018
Mode Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
74 7.1.2 Bar bending & Inserting RC
20bars
days Thu 17/11/16 Wed 14/12/16
75 7.1.3 Concreting 14 days Thu 15/12/16 Tue 3/1/17
76 7.1.4 Backfilling 10 days Wed 4/1/17 Tue 17/1/17
77 7.2 Slab 39 days Thu 17/11/16 Tue 10/1/17
78 7.2.1 Formwork 25 days Thu 17/11/16 Wed 21/12/16
79 7.2.2 Bar bending & Inserting RC
25bars
days Thu 17/11/16 Wed 21/12/16
80 7.2.3 Concreting 14 days Thu 22/12/16 Tue 10/1/17
81 7.3 Columns 37 days Wed 11/1/17 Thu 2/3/17
82 7.3.1 Formwork 20 days Wed 11/1/17 Tue 7/2/17
83 7.3.2 Bar bending & Inserting RC
20bars
days Wed 11/1/17 Tue 7/2/17
84 7.3.3 Concreting 14 days Wed 8/2/17 Mon 27/2/17
85 7.3.4 Erection of Scalfolding 3 days Tue 28/2/17 Thu 2/3/17
and False Work for next level
86 7.4 1st Floor Beams 34 days Fri 3/3/17 Wed 19/4/17
87 7.4.1 Formwork 10 days Fri 3/3/17 Thu 16/3/17
88 7.4.2 Bar bending & Inserting RC
20bars
days Fri 3/3/17 Thu 30/3/17
89 7.4.3 Concreting 14 days Fri 31/3/17 Wed 19/4/17
90 7.5 1st Floor Slab 34 days Thu 20/4/17 Tue 6/6/17
91 7.5.1 Formwork 10 days Thu 20/4/17 Wed 3/5/17
92 7.5.2 Bar bending & Inserting RC
20bars
days Thu 20/4/17 Wed 17/5/17
93 7.5.3 Concreting 14 days Thu 18/5/17 Tue 6/6/17
94 7.6 1st Floor Columns 28 days Wed 7/6/17 Fri 14/7/17
95 7.6.1 Formwork 10 days Wed 7/6/17 Tue 20/6/17
96 7.6.2 Bar bending & Inserting RC
14bars
days Wed 7/6/17 Mon 26/6/17
97 7.6.3 Concreting 14 days Tue 27/6/17 Fri 14/7/17
98 7.7 Roof beam 28 days Mon 17/7/17 Wed 23/8/17
99 7.7.1 Formwork 10 days Mon 17/7/17 Fri 28/7/17
100 7.7.2 Bar bending & Inserting RC
14bars
days Mon 17/7/17 Thu 3/8/17
101 7.7.3 Concreting 14 days Fri 4/8/17 Wed 23/8/17
102 7.8 Roofing 30 days Thu 28/12/17 Wed 7/2/18
103 7.8.1 Roof trusses 10 days Thu 28/12/17 Wed 10/1/18
104 7.8.2 Roof purlins 10 days Thu 11/1/18 Wed 24/1/18
105 7.8.3 Roof sheathing 10 days Thu 25/1/18 Wed 7/2/18
106 8.0 Architectural Works (Terrace 278 days Tue 28/2/17 Thu 22/3/18
houses)
107 8.1 Ground floor 130 days Tue 28/2/17 Mon 28/8/17
108 8.1.1 Brickwall Construction 60 days Tue 28/2/17 Mon 22/5/17
109 8.1.2 Plastering Work 25 days Tue 23/5/17 Mon 26/6/17
110 8.1.3 Installation of Doors, 14 days Tue 23/5/17 Fri 9/6/17
Windows, And Ironmogery
111 8.1.4 Celling Finishes 15 days Tue 27/6/17 Mon 17/7/17
112 8.1.5 Wall Finishes 21 days Tue 27/6/17 Tue 25/7/17
113 8.1.6 Floor Finishes 16 days Tue 18/7/17 Tue 8/8/17
114 8.1.7 Sanitary Fitting 20 days Tue 27/6/17 Mon 24/7/17

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: ARMAJAYA LAND BERH Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 19/12/15 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 3
ID Task Task Name Duration Start Finish 2016 2017 2018
Mode Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
115 8.1.8 Painting 45 days Tue 27/6/17 Mon 28/8/17
116 8.2 First floor 148 days Tue 29/8/17 Thu 22/3/18
117 8.2.1 Brickwall Construction 60 days Thu 26/10/17 Wed 17/1/18
118 8.2.2 Plastering Work 25 days Thu 18/1/18 Wed 21/2/18
119 8.2.3 Installation of Doors, 14 days Thu 18/1/18 Tue 6/2/18
Windows, And Ironmogery
120 8.2.4 Celling Finishes 15 days Thu 22/2/18 Wed 14/3/18
121 8.2.5 Wall Finishes 21 days Thu 22/2/18 Thu 22/3/18
122 8.2.6 Floor Finishes 16 days Wed 7/2/18 Wed 28/2/18
123 8.2.7 Sanitary Fitting 20 days Thu 22/2/18 Wed 21/3/18
124 8.2.8 Painting 45 days Tue 29/8/17 Mon 30/10/17
125 9.0 Architectural Works (Shopoffice)157 days Wed 7/6/17 Thu 11/1/18
126 9.1 Ground floor 112 days Wed 7/6/17 Thu 9/11/17
127 9.1.1 Brickwall Construction 42 days Wed 7/6/17 Thu 3/8/17
128 9.1.2 Plastering Work 30 days Fri 4/8/17 Thu 14/9/17
129 9.1.3 Installation of Doors, 7 days Fri 4/8/17 Mon 14/8/17
Windows, And Ironmogery
130 9.1.4 Celling Finishes 14 days Fri 15/9/17 Wed 4/10/17
131 9.1.5 Wall Finishes 18 days Fri 15/9/17 Tue 10/10/17
132 9.1.6 Floor Finishes 15 days Thu 5/10/17 Wed 25/10/17
133 9.1.7 Sanitary Fitting 10 days Fri 15/9/17 Thu 28/9/17
134 9.1.8 Painting 40 days Fri 15/9/17 Thu 9/11/17
135 9.2 First floor 101 days Thu 24/8/17 Thu 11/1/18
136 9.2.1 Brickwall Construction 42 days Thu 24/8/17 Fri 20/10/17
137 9.2.2 Plastering Work 30 days Mon 23/10/17 Fri 1/12/17
138 9.2.3 Installation of Doors, 7 days Mon 23/10/17 Tue 31/10/17
Windows, And Ironmogery
139 9.2.4 Celling Finishes 14 days Mon 4/12/17 Thu 21/12/17
140 9.2.5 Wall Finishes 18 days Mon 4/12/17 Wed 27/12/17
141 9.2.6 Floor Finishes 15 days Fri 22/12/17 Thu 11/1/18
142 9.2.7 Sanitary Fitting 10 days Mon 4/12/17 Fri 15/12/17
143 9.2.8 Painting 40 days Fri 10/11/17 Thu 4/1/18
144 10.0 Mechanical & Electrical 20 days Tue 23/5/17 Mon 19/6/17
(Terrace houses)
145 10.1 Plumbing 20 days Tue 23/5/17 Mon 19/6/17
146 10.2 Wiring 20 days Tue 23/5/17 Mon 19/6/17
147 11.0 Mechanical & Electrical 15 days Mon 23/10/17 Fri 10/11/17
(Shophouses)
148 11.1 Plumbing 15 days Mon 23/10/17 Fri 10/11/17
149 11.2 Wiring 15 days Mon 23/10/17 Fri 10/11/17
150 MS2 Section 1 completed Section 2 0 days Thu 22/3/18 Thu 22/3/18 22/3
started
151 12.0 Drainage work 70 days Fri 23/3/18 Thu 28/6/18
152 12.1 Setting out 7 days Fri 23/3/18 Mon 2/4/18
153 12.2 Excavation and base 14 days Tue 3/4/18 Fri 20/4/18
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline
Project: ARMAJAYA LAND BERH Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 19/12/15 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 4
ID Task Task Name Duration Start Finish 2016 2017 2018
Mode Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
154 12.3 Laying p.c drain 14 days Mon 23/4/18 Thu 10/5/18
155 12.4 Caping beam 14 days Fri 11/5/18 Wed 30/5/18
156 12.5 Slab cover 7 days Thu 31/5/18 Fri 8/6/18
157 12.6 Box Culvert 7 days Mon 11/6/18 Tue 19/6/18
158 12.7 Cast in place main drain 7 days Wed 20/6/18 Thu 28/6/18
159 13.0 Water Supply work 45 days Fri 23/3/18 Thu 24/5/18
160 13.1 Excavate pipe trenchs 7 days Fri 23/3/18 Mon 2/4/18
161 13.2 150mm dia HDPE pipe 4 days Tue 3/4/18 Fri 6/4/18
162 13.3 Supply, Lay & Test piping 4 days Mon 9/4/18 Thu 12/4/18
163 13.4 Precast concrete 10 days Fri 13/4/18 Thu 26/4/18
164 13.5 Sluice valve chamber 2 days Fri 27/4/18 Mon 30/4/18
165 13.6 Hydrant indicator post 2 days Tue 1/5/18 Wed 2/5/18
166 13.7 Sluice valve indicator post 2 days Thu 3/5/18 Fri 4/5/18
167 13.8 Valve 2 days Mon 7/5/18 Tue 8/5/18
168 13.9 Fire Hydrant 2 days Wed 9/5/18 Thu 10/5/18
169 13.10 Tapping to main supply pipe2 days Fri 11/5/18 Mon 14/5/18
170 13.11 Flushing & Disinfecting the 2 days Tue 15/5/18 Wed 16/5/18
tested pipeline with chlorine
171 13.12 Elevated Water Tank 2 days Thu 17/5/18 Fri 18/5/18
172 13.13 Testing and commisioning 4 days Mon 21/5/18 Thu 24/5/18
173 14.0 Sewerage work 38 days Fri 23/3/18 Tue 15/5/18
174 14.1 Excavate trench 10 days Fri 23/3/18 Thu 5/4/18
175 14.2 Pipe Installation 7 days Fri 6/4/18 Mon 16/4/18
176 14.3 Precast Reinforced Concrete 7 days Tue 17/4/18 Wed 25/4/18
Manhole
177 14.4 Normal type 7 days Thu 26/4/18 Fri 4/5/18
178 14.5 1200mm dia manhole 7 days Mon 7/5/18 Tue 15/5/18
179 15.0 Road work and Carparks 54 days Fri 23/3/18 Wed 6/6/18
180 15.1 Subgrade 7 days Fri 23/3/18 Mon 2/4/18
181 15.2 Subbase 5 days Tue 3/4/18 Mon 9/4/18
182 15.3 Roadbase 2 days Tue 10/4/18 Wed 11/4/18
183 15.4 Coating 1 day Thu 12/4/18 Thu 12/4/18
184 15.5 Premix Course 10 days Fri 13/4/18 Thu 26/4/18
185 15.6 Ramp 12 days Fri 27/4/18 Mon 14/5/18
186 15.7 Road Kerb 9 days Tue 15/5/18 Fri 25/5/18
187 15.8 Road Demarcation Line 5 days Mon 28/5/18 Fri 1/6/18
188 15.9 Road Signage 3 days Mon 4/6/18 Wed 6/6/18
189 16.0 Ancillary Building 7 days Fri 23/3/18 Mon 2/4/18
190 16.1 Bin Center 7 days Fri 23/3/18 Mon 2/4/18
191 16.2 Sub station 7 days Fri 23/3/18 Mon 2/4/18
192 MS3 Project Closed and Hand-Over 0 days Thu 28/6/18 Thu 28/6/18 28/6

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: ARMAJAYA LAND BERH Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 19/12/15 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only