Você está na página 1de 3

TATA HOUSING

(ON LETTER HEAD OF CONTRACTOR)

DECLARATION BY CONTRACTOR

I___________________________________________________________(Name) authorized

representative of ________________________________________________________

(Contractor) had read and understood the EHS Requirements Ready Reckoner and other

documents mentioned therein. I fully agree to these and commit to abide by the same.

Also, I will accept penalty in case of failure to fulfil these requirements.

Date: Signature

Place: Seal of Company

Declaration Page 1
TATA HOUSING

EHS OFFENCES PENALTY MATRIX

Non-compliance or non-conformance with EHS Requirements stated (refer Ready Reckoner


A and Ready Reckoner B) or implied shall be treated as offence. Contractor, its staff and
workers will be penalized for each offence as per the EHS PENALTY MATRIX given below:

Penalty shall be imposed to individual as well as contracting company as per the conditions
stipulated in the matrix. However, the amount of penalty accrued shall be deducted from
the payment due to the contracting company. If offence is repeated in spite of the penalty,
Contractor shall be disbanded based on the recommendation of Project Head or corporate
EHS Head.
Sr. No. Definition of Offence Amount of Penalty
1 Failure to provide ID Card to workers Rs. 200/- per person
2 Failure to provide requisite amenities in the Labour Rs. 5,000/- per amenity
Camp.
4 Smoking in the construction zone and/or working under Rs. 500/- per violation
influence of alcohol/prohibited drugs.
5 Burning of waste or smouldering of combustible Rs. 500/-
materials on site without written permission.
6 Failure to wear Personal Protective Equipment (PPE) or Rs. 500/- per individual if PPE
its improper use. supplied but not worn by personal;
Rs. 1,000/- per individual if PPE not
provided by the contractor
7 Working without EHS Induction Rs. 500/- per personal and working
day to be dismissed
8 Not attending EHS Meetings or any other EHS Rs. 1,000/- per individual
Programme/Function
9 Failure to Implement TATA Housings EHS Documents Rs. 10,000/- each instance
(EHS Plan, Work Method Statement, Emergency Plan)
10 Failure to submit report on incident , Rs. 5,000/- each instance
accidents and near misses with in the
stipulated time
11 Failure to comply with infringement notice Rs. 2,000/- each instance
12 Misuse/damage to property/equipment/ infrastructure Rs. 1,000/-; in addition contractor to
pay for the cost of items damaged
13 Unsafe work (act/condition) not covered otherwise Rs. 2,000/-; & immediate
rectification
14 Poor Housekeeping and stacking of materials Rs. 2,000/- & cessation of work till
satisfactory rectification
15 Obstruction of passageways, entrances, doorways, stairs, Rs. 2,000/- & immediate rectification
access to Fire Fighting Equipment etc.
16 Use of equipment without Inspection tag or its Rs. 1,000/-& immediate rectification
unauthorized use and alterations
17 Use of damaged or uncertified lifting tackles Rs. 2,000/- & confiscation of such
items
18 Unsafe lifting method Rs. 2,000/- & cessation of work till
satisfactory rectification

Declaration Page 2
TATA HOUSING

19 Failure to provide for and use unsafe working platforms, Rs. 2,000/-& cessation of work till
means of access to the work place, where work is satisfactory rectification
required to be carried out beyond a persons normal
reach
20 Permitting/Forcing personal to work unsafe manner Rs. 5,000/- each instance to
supervisor/work Incharge
21 Failure to provide EHS signage Rs. 5,000/-
22 Not providing collective fall protection Rs. 5,000/- & cessation of work till
satisfactory rectification
23 Allowing fall of materials from height or throwing Rs. 5,000/-
materials from height or not barricading dangerous zone
on ground or not providing signage to warn the
possibility of falling materials.
24 Violation of Work Method Statement or Violation of Rs. 5,000/-
Permit to Work or Violation of Work Instructions
26 Lack of pre & post-employment health screening Rs.5,000/-
27 Failure to implement Height Pass for height work Rs. 5,000/-
28 Statutory non-compliance Rs. 10,000/- and any fine imposed by
the authority
29 Unauthorized use of any safety appliances/equipments Rs. 10,000/-

30 Adopting unsafe tapping/connections/termination of Rs. 10,000/- & cessation of work till


electrical lines or use of defective electrical fittings , satisfactory rectification
cables and electrical tools or allowing cables /
equipment to be submerged in water or
not providing Earth Leakage Circuit Breaker/not
maintaining Earthing
31 Failure to comply with an order (written or otherwise) Rs.10,000/-
issued by the THDC Project Manager or representative,
or EHS In-charge in regard to EHS matter

32 Threatening EHS personnel, misbehaving, fighting or Rs. 10,000/- and


intentionally causing harm to any person Personal to be banned from the site
and a report will be made to the
police
33 Failure to deploy competent EHS Personnel in adequate Rs. 10,000/- per incidence
number (ref. EHSP-01 & 02 : EHS Requirement Ready
Reckoner)
34 Lost Time Injury as a result of negligence as established Rs. 25,000/- each incidence
by Accident Investigation Report
35 Fatality Rs. 100,000/- each case
36 Environmental incidence ( major spillage/persistent high Rs, 25,000/- each incidence
noise/unabated dust in work environment)
37 Failure to constitute and run Safety Committee or non- Rs. 25,000/-
representation of workers in the committee
38 Failure to constitute Emergency Response Team Rs. 25,000/-
39 Use of Mobile Phone in any form while on work Rs. 500/- per person per incidence

Declaration Page 3

Você também pode gostar