01 EXCAVATION AND EARTHWORK

Rate for Excavation and Earthwork shall include for :

a. Trimming sides, keeping clean and consolidating bottom of


base and trenches etc. leveling consolidating where required
under slabs or sub floor layers.

b. Back filling with selected excavated materials or with borrowed


materials and disposl of surplus excavated materials from site as
specified and directed.

c. Any necessary additional excavation for working space.

BASIC MATERIALS PRICES

Skilled Labour Rs. 1,200.00 per day


Un Skilled Labour Rs. 1,000.00 per day

Dry hard earth Rs. 2,300.00 per cube

1 " thick plank Rs. 120.00 s. ft.


( class 11 )

2" x 4" joist Rs. 60.00 L. ft.


( class 11 )

2" x 6" joist Rs. 85.00 L. ft.


( class 11 )

Wire nails Rs. 165.00 kg.

Tractor Rs. 2,500.00 per day

Overheads & Profit 32% %

Rock Blasting Powder Rs. ### Kg


Rock Blastingfuse Rs. 50 Lft
Jumper Steel 500 Kg
A EXCAVATION AND EARTHWORK
RATE
WITH
SITE CLEARING PROFIT

A. 01 Clearing site and grubbing up all small trees not


exceeding 500mm girth and including bushes,
scrubs,undergrowth hedges etc. sqr. Rs. 679.80

EXCAVATION

A. 02 Excavation of top soil of average depth of 6" and


carting away surplus soil. sqr. Rs. 1,359.60

A. 03 Excavation over site to reduce level in any material


except level, in any material except rock requiring
blasting including depositing and leveling as directed
up to a distance not exceeding 30'-0" cube. Rs. 2,209.35

A. 04 Excavation in trenchaes for wall / column pits in soft


/ loose soil from 0' to 5'-0" depth and depositing
excavated material to a distance not exceeding
30'-0" (Earth work suopport to be paid separately
where necessary) cube. Rs. 1,359.60

A. 05 Excavate trench for wall foundation/ Column pits in


Ordinary soil depth n.e 5'-0" and depoisting excavated
material N.E-30'-0"( not exceeding 5' 0" deep ) cube. Rs. 3,059.10

A. 06 Excavate trench for walls foundation / Columns pits in


Hard /dense soil up to a depth of 5'-0" and
depositing excavated meterial up to a destance N.E
30'-0" ( Not exceeding 5' 0" deep ) cube. Rs. 4,758.60

A. 07 Excavation in trench for walls foundation / Columns


pits in Mud/Wet soil up to a depth of 5'-0" and
depositing excavated meterial to destance N.E 30'-0"
(Earth work suopport to be paid separately where cube, Rs. 4,078.80
necessary)

A. 08 Excavate trench for walls foundation / Columns pits in


Distintegrated Rock (Not Requaring Blasting ) up to a
depth of 5'-0" and depositing excavated meterial to
destance N.E 30'-0"( Not exceeding 5' 0" deep ) cube, Rs. 3,399.00

A. 09 Excavation trench for walls foundation / Columns pits


in Hard Rock Requaring Blasting up to a depth of 5'-0"
and depositing excavated meterial to destance N.E
30'-0"( Not exceeding 5' 0" deep ) cube, Rs. 11,874.72

A. 10 Excavation in levlling site in any material except rock


requiring blasting, including transporting up to 1/4 mile
depositing and levelling. cube, Rs. 3,949.00

EARTH FILLING

A. 11 Earth work Backfilling and Compacting cube, Rs. 1,359.60

A. 09 Filling under floors with gravel or other approved quality


of filling, spread, watered and well rammed in 3" thick
layers. ( earth available at site ) cube. Rs. 1,549.94

A. 10 Filling under floors with gravel or other approved quality


of filling, spread, watered and well rammed in 3" thick
layers. ( earth not available at site ) cube. Rs. 4,664.88

A. 11 Filling under floors with gravel or other approved quality


of filling, spread, watered and well rammed in 3" thick
layers. ( within Colombo Municipal limits ) cube. Rs. 4,664.88

EARTH WORK SUPPORT


A. 12 Earth work support in trenches up to 5' 0" deep
( oping planking ) sqr. Rs. 3,246.81
A. 13 Earth work support in trenches up to 5' 0" deep
( close planking ) sqr. Rs. 7,025.03

A. 14 Earth work support in trenches up to 10' 0" deep


( close planking ) sqr. Rs. 7,404.86

A. 01 Clearing site and grubbing up all small trees not exceeding 500mm girth SSR(PS)-A-1
and including bushes, scrubs,undergrowth hedges etc.

Per square

0.50 day Un skilled labour @ Rs. 1,000.00 500.00

Add. 3% for Small tools for lobour cost 15.00


Rs. 515.00

Add.
Overheads & Profit Rs. 164.80

Unite Rate Rs. 679.80

A. 02 Removeing of top soil of average depth not exceeding 6" and carting SSR(PS)-A-2
and depositing as directed witing site BSR-01
Per square

Labour

1.00 day Un skilled labour @ Rs. 1,000.00 Rs. 1,000.00

Add 3% for Tools of Labour cost


Rs. 30.00
Rs. 1,030.00
Add Overheads & Profit Rs. 329.60

Unite Rate Rs. 1,359.60

A. 03 Excavation over site to reduce level in any material except level, in any SSR(PS)-A-3
material except rock requiring blasting including depositing and leveling BSR-02
as directed up to a distance not exceeding 30'-0"

Per Cube

Labour

1 5/8 day Un skilled labour @ Rs. 1,000.00 Rs. 1,625.00


Add 3% for Tools of Labour cost
Rs. 48.75
Rs. 1,673.75
Add Overheads & Profit Rs. 535.60

Unite Rate Rs. 2,209.35

A. 04 Excavation in trenchaes for wall / column pits in soft / loose soil from
SSR(PS)-A-4
5'-0" depth and depositing excavated material to a distance not exce BSR-03
30'-0" (Earth work suopport to be paid separately where necessary)
Per Cube

Labour

1.00 days Un skilled labour @ Rs. 1,000.00 Rs. 1,000.00

Add. 3% for tools of Labour cost Rs. 30.00


Rs. 1,030.00

Add. Overheads & Profit Rs. 329.60

Unite Rate Rs. 1,359.60

A. 05 Excavate trench for wall foundation/ Column pits in Ordinary soil depthSSR(PS)-A-5
n.e 5'-0" and depoisting excavated material N.E-30'-0"( not exceeding 5' BSR-04
deep )
Per Cube
Labour

2.25 days Un skilled labour @ Rs. 1,000.00 2,250.00

Add. 3% for tools of Labour cost Rs. 67.50


Rs. 2,317.50
Add.
Overheads & Profit Rs. 741.60

Cost for one cube with overheads and profit Rs. 3,059.10

A. 06 Excavate trench for walls foundation / Columns pits in Hard dense soil SSR(PS)-A-6
up to a depth of 5'-0" and depositing excavated meterial to BSR-05
destance N.E 30'-0"( Not exceeding 5' 0" deep )

Per Cube

Labour

3 1/2 days Un skilled labour @ Rs. 1,000.00 Rs. 3,500.00

Add. 3% for tools of Labour cost @ Rs. Rs. 105.00


Basic Rte per Cube 3,605.00

Add.
Overheads & Profit 1,153.60

Unite Rate per Cube 4,758.60


A. 07 Excavation in trench for walls foundation / Columns pits in Mud/Wet soil SSR(PS)-A-7
up to a depth of 5'-0" and depositing excavated meterial to BSR-06
destance N.E 30'-0" (Earth work suopport to be paid separately where necessary)
( Not exceeding 5' 0" deep )
Per Cube

Labour

3.0 days Un skilled labour @ Rs. 1,000.00 Rs. 3,000.00

Add. 3% for tools of Labour cost @ Rs. Rs. 90.00


Basic Rte per Cube 3,090.00

Add.
Overheads & Profit Rs. 988.80

Unite Rate per Cube Rs. 4,078.80

A. 08 Excavation trench for walls foundation / Columns pits in Distintegrated Rock


(Not Requaring Blasting ) up to a depth of 5'-0" and depositing excavated
meterial to destance N.E 30'-0"( Not exceeding 5' 0" deep )

Per Cube

Labour

2.5 day Un skilled labour @ Rs. 1,000.00 Rs. 2,500.00

Add. 3% for tools of Labour cost Rs. 75.00


Basic Rte per Cube Rs. 2,575.00

Add.
Overheads & Profit Rs. 824.00

Unite Rate Rs. 3,399.00

A. 09 Excavation trench for walls foundation / Columns pits in Hard Rock


Requaring Blasting up to a depth of 5'-0" and depositing excavated
meterial to destance N.E 30'-0"( Not exceeding 5' 0" deep )

Per Cube

0.75 Lbs Blasting Powder @ Rs ### ###


### Lft Fuse @ Rs 50 500.00
1.00 Lb Jumper Steel @ Rs 500 500.00
for fuel and Rs 4,750.00
Compresher, forge
Add
20% Meterial cost @ Rs 950.00

Total metirial cost Rs 5,700.00


Labour

1.00 day skilled labour @ Rs. 1,200.00 1,200.00


2.00 day Un skilled labour @ Rs. 1,000.00 2,000.00
Rs 3,200.00

Add. 3% tools of Labour cost Rs 96.00


Basic cost per cube 8,996.00
Add.
Overheads & Profit 2,878.72
Cost for one cube with overheads and profit 11,874.72

A. 10 Cutting and levlling site in any material except rock


requiring blasting, including transporting up to 1/4 mile
depositing and levelling.
Per cube,

Labour

Cutting and loading earth to tractor

2 1/2 days Un skilled labour @ Rs. 1,000.00 Rs. 2,500.00

Transporting earth

1/6 day tractor @ Rs. 2,500.00 Rs. 416.67

Add. 3% tools of Labour cost Rs. 75.00


Rs. 2,991.67
Add.
Overheads & Profit Rs. 957.33

Unite rate per cube Rs. 3,949.00

A. 11 Earth work Backfilling and Compacting

Back filling to trenches wit selected earth available at site


Per Cube

Labour

1.00 day Un skilled labour @ Rs. 1,000.00 Rs. 1,000.00

Add. 3% for tools of Labour cost Rs. 30.00


Basic Rte per Cube Rs. 1,030.00

Add.
Overheads & Profit Rs. 329.60

Unite Rate Rs. 1,359.60


A. 09 Filling under floors with gravel or other approved quality
of filling, spread, watered and well rammed in 3" thick
layers. ( earth available at site ) 1 cube.

Labour

1.5 day Un skilled labour at. Rs. 1,000.00 1,500.00

Add. tools
3 % of Labour cost 45.00
1,545.00
Add.
Overheads & Profit 4.94

Cost for one cube with overheads and profit 1,549.94

A. 10 Filling under floors with gravel or other approved quality


of filling, spread, watered and well rammed in 3" thick
layers. ( earth not available at site ) 1 cube.

Materials

1.35 cube Earth with transport cost at. Rs. 2,300.00 3,105.00

Labour

1.5 day Un skilled labour at. Rs. 1,000.00 1,500.00

Add. tools
3% of Labour cost 45.00
4,650.00
Add.
Overheads & Profit 14.88

Cost for one cube with overheads and profit 4,664.88

A. 11 Filling under floors with gravel or other approved quality


of filling, spread, watered and well rammed in 3" thick
layers. ( within Colombo Municipal limits ) 1 cube.

Materials

1.35 cube Earth with transport cost at. Rs. 2,300.00 3,105.00

Labour
1.5 day Un skilled labour at. Rs. 1,000.00 1,500.00

Add. tools
3% of Labour cost 45.00
4,650.00
Add.
Overheads & Profit 14.88

Cost for one cube with overheads and profit 4,664.88

A. 12 Earth work support in trenches up to 5' 0" deep


( open planking ) 1.20 sqr.

Note
Consider trench 12' 0" long 3' 0" wide and 5' 0" deep
open planking to both side. ( Class 11 timber )

Materials

40.00 s. ft. 1 1/2" thick planks at Rs. 120.00 4,800.00

40.00 l. ft. 2" x 6" joist at Rs. 85.00 3,400.00

40.00 l. ft. 2" x 4" joist at Rs. 60.00 2,400.00

0.50 kg. wire nails at Rs. 165.00 82.50

###
3% Westege 320.48
cost for 4 uses Rs. 11,002.98

for single use 2,750.74


Rs. 2,750.74
Labour
0.50 Skilled labour at Rs. 1,200.00 600.00

0.50 Un skilled labour at Rs. 1,000.00 500.00


Rs. 1,100.00
tools
3% of labour cost Rs. 33.00
Rs. 3,883.74
Overheads & Profit Rs. 12.43

Rs. 3,896.17

Cost for one sqr. with overheads and profit


( open planking ) Rs. 3,246.81

A. 13 Earth work support in trenches up to 5' 0" deep


( close planking ) 1 sqr.

Note
Consider trench 10' 0" long 3' 0" wide and 5' 0" deep
close planking to both side. ( class 11 timber )

Materials

110.00 s. ft. 11/2" thick planks at Rs. 120.00 ###

40.00 ft, 2" x 6" joist at Rs. 85.00 3,400.00

24.00 ft, 2" x 4" joist at Rs. 60.00 1,440.00

0.5 kg. wire nails at Rs. 165.00 82.50

Cost for 4 uses Rs. 18,122.50

For single use Rs. 4,530.63

Labour

0.75 day Skilled labour at Rs. 1,200.00 900.00

0.75 day 2 Un skilled labour at Rs. 1,000.00 1,500.00


Rs. 2,400.00

Add
tools
3% of labour cost Rs. 72.00
Rs. 7,002.63

Overheads & Profit Rs. 22.41

Cost for one sqr. with overheads and profit


( close planking ) Rs. 7,025.03

A. 14 Earth work support in trenches up to 10' 0" deep


( close planking ) 2 sqr.

Note
Consider trench 10' 0" long 4' 0" wide and 10' 0" deep
close planking to both side.

Materials

220.00 s. ft. 11/2" thick planks at Rs. 120.00 ###

6.00 no 12' 0" long joist 2" x 6" at Rs. 1,020.00 6,120.00

12.00 no 4' 0" long props 2" x 4" at Rs. 240.00 2,880.00

2.00 kg. Wire nails at Rs. 165.00 330.00


###

Westege 3% 1,071.90
Cost for 4 uses ###

For single use Rs. 9,200.48

Labour

1 day 2.00 Skilled labour at Rs. 1,200.00 2,400.00

1 day 3.00 Un skilled labour at Rs. 1,000.00 3,000.00


Rs. 5,400.00

tools

3% of labour cost Rs. 162.00

Rs. 14,762.48

Overheads & Profit Rs. 47.24

Rs. 14,809.71

Cost for one sqr. with overheads and profit Rs. 7,404.86
( close planking )