Escolar Documentos
Profissional Documentos
Cultura Documentos
Project Name:
TABLE OF CONTENTS
1. GENERAL
2. REFERENCE DOCUMENTS
3. RESOURCES
5. NIGHT WORKS
7. CLOSING OUT
8. QUALITY ISSUES
This Work Method Statement will describe the successive steps and the
technical details set forth for the preparation and laying of the concrete
masonry units, the preparation and installation of the reinforcement needed,
the concreting of lintel beams, the vertical and horizontal stiffeners and the
inspections to be carried out during and after the execution of the works.
Setting
out of wall
Placemen
t of
reinforce
ment
Laying of concrete masonry units
Concrete lintel beams, vertical and horizontal stiffeners
2. REFERENCE DOCUMENTS
3. RESOURCES
3.1 Human resource man power
The human resources deployed for the execution of the task in
Main Site and Substation Area are detailed as follows (Typical
Team):
Resources for the
general attendance
Site Engineer - 1
General
Foreman - 1
Surveyor
(when
required) - 1
Crane Operator (when required) 1
Forklift Operator
(when required) - 1
Mason Foreman - 1
Masons- 5
Helpers - 5
Steel Fixers / Scaffolds - 2
3.2 Materials
3.3 Equipment
The building wall should be located with reference to the dimensioned setting
out drawings, which may be on a grid system and building lines.
The height of masonry walls and partitions shall be as per the approved
shop drawings. All movement joints and control joints shall be established
and will be based in the approved shop drawing before the work proceeds.
Packing of Masonry
Unit
Lifting block bv the
Truck Mounted
Crane
When the forklift is used, ensure that the pallet is properly hooked and balanced before the lift,
secure the balanced of the load and must be guided with the competent banks man. Areas shall
be barricaded and equipped with safety precaution for the workers awareness. All equipment
operation shall be carried out as per manufacturer instruction
The location and the reinforcement of the stiffeners columns and bond
beams shall be in accordance with the approved shop drawings.
The delivery of the reinforcement bars will be as per site
requirements. They will be hoisted directly to the working area.
Wooden beams shall be placed to support the bars and to provide
a gap from the floor.
To install the stiffener column's starter bars on the floor slab, drill holes
and place the starter bars with approved mortar grout materials, the
whole depth shall be in accordance with grouting manufacturers
recommendations
Once the starter bars of a stiffener column have been doweled to the floor slab, splice
the vertical reinforcement w h tie wires at minimum of 40 bar diameter or as indicated
as per approved shop drawings.
The stiffener columns will be poured in 2 times. The first pour will be up to 2 meters high.
The second pour will be up to the top of the wall or up to 4 meters high, whichever is the
highest. Please note that there will be a 20mm gap between the top of the stiffener column
and the slab soffit. This gap will be filled w h the fire proofing complex.
Prior to pouring, ensure that the steel reinforcement is clean, free of loose flaky crust,
oil or other coatings that will destroy and reduce the bond. The pouring of the stiffeners
columns will be done once the surrounding blocks partitions are higher than the height
of pouring. The 2 faces of the wooden shutters shall be closed and the pouring of
concrete will be done using the plastic pail and compacted by wooden rod. Concrete
shaII be as per the approved mix design
For the bond beam, the reinforcement shall be installed as per approved shop
drawings directly on the top of the blocks. The 2 faces of the wooden shutters shall
be closed and the pouring of concrete will be done using the plastic pail and
compacted by wooden rod. Concrete shall be as per the approved mix design
The surveyor will establish the layout of the wall /partition location.
The maximum permitted/acceptable deviation shall be in
accordance with the Project specification:
Lay out walls in advance for accurate spacing of surface bond patterns
with uniform joint thickness and for accurate location of openings,
movement-type joints, returns and offsets, all shall be carried out as per
the approved shop drawings.
Laying of blocks
CASCADED
WALLOPENING
Clean the surface of masonry wall as the work progresses by
dry brushing to remove mortar fins and smears.
During laying of block, mortar joints shaII be observed as follows:
4.4 Curing
Keep walls wet with dampened hessian or water spray for three days
after building.
masonry walls
50 - 75 1,000 40
75 - 100 800 40
100-150 500 40
Notes
4.11Mortar
Mortar preparation
4.12 Cleaning
6- CLOSING OUT
Not Applicable.
7- QUALITY ISSUES
iii. Environment