BUILDINGS.
EXCAVATION
Sr. Item Unit Rubble Over Size Sand in Quarry in spaul
No. in M3 metal in M3 M3 in M3
1 Providing trap M3 1.00 -- -- 0.20
rubble spoiling 15
to 20cm thick
2 Providing soiling M3 -- 1.00 0.15 --
using 80mm over
size trap metal
PILE FOUNDATION
Sr. Item Unit Cement Sand in M3
No. Bags
1 M-25 RCC Cast in Situ Bored Piles M3 7.50 0.45
3
2 M-30 RCC Cast in Situ Bored Piles M 8.00 0.45
STONE MASONARY.
Sr. Item Unit Cement Screened Trap Corner/
No. in Bags Sand in M3 Rubble Quins in
in Nos Nos
1 UCR masonary in CM 1:6 in M3 1.77 0.35 1.16 2
foundations and plinth of inner
walls/external walls
2 UCR masonary in CM 1:6 in M3 2.05 0.35 1.16 2
Super structure
3 Random rubble masonary IInd M3 2.05 0.35 1.16 2
sort in CM 1:6 in Superstructure
RCC PIPES
SR. Item Unit Cement in Sand in
No Bag Cum
1 P & L cc pipes of NP-2 class / IRC Pipes of NP-3 Class
I 450 mm dia. M 0.12 0.009
II 600 mm dia. M 0.16 0.011
III 800 mm dia. M 0.22 0.015
IV 900 mm dia M 0.22 0.0154
V 1000 mm dia M 0.24 0.017
VI 1200 mm dia. M 0.26 0.018
THEORITICAL MATERIAL REQUIREMENT
M.O.S.T. 2000 EDITION AND DATA BOOK
( Grading Material shall be as per actual job mix formula wherever applicable)
1) Primer coat over Granular base (Table :500.1 page 19)
i) Low porosity surface such as wet mix 6 to 9 kg/10 Sqm
macadam and water bound macadam
ii) Medium porosity surface such as cement stabilized soil base 9 to 12 kg/10 Sqm
iii) High porosity surface such as grave base 12 to 15 kg/10 Sqm
5) Built up Spray Grout (Excluding Primer / Tack coat) clause no. 506
A) Bitumen @ 15 kg /10m2 for each layer - 30 kg / 10m2
C) key aggregate Passing 22.4 mm 0.13 Cum /10m2 0.13 Cum / 10m2
Retained on 2.80 mm -------------------------
Total 1.13 cum /10 m2
6) Dense Graded Bituminous Macadam (Density 2.30)
Grading I ( 40 mm nominal size) with bitumen at 4.25% of total mix
(Excluding primer coat / tack coat) Clause No. 507
iii) Binder (Bitumen) for 13.20 mm chipping 9.50kg / 10m2 Total Bitumen
iv) Binder (Bitumen) for 11.2 mm chipping 5.10 kg / 10m2 14.60 kg /10 Sqm
11) Providing and applying premixed seal coat type B Clause no 513
i) Sand or grit passing 2.36 mm and 0.060 m3/10 m2
retained on 180 micron
ii) Bitumen 6.80 kg /10 m2
THEORITICAL MATERIAL REQUIREMENT
M.O.S.T. 2000 EDITION AND DATA BOOK
(REQUIREMENT OF MATERIALS SHALL BE AS PER ACTUAL JOB MIX FORMULA BRIDGES
AND CULVERTS)
b) Well Staining
C) Bottom Plug
5 a) RCC Superstructure
c) Prestressed concrete
a) M-35 grade m3 0.422 0.45 - 0.54 0.36
b) M-40 grade m3 0.430 0.45 - 0.54 0.36
SR. ITEM UNIT CEME COARSE COURSE
NO NT IN SAND IN AGGREGATE
MT M3 40 20 10
mm mm mm
in M3 in m3 in m3
RCC Wearing Course &
6 Approach slab
a) RCC M-15 grade m3 0.300 0.45 - 0.67 0.22
b) RCC M-20 grade m3 0.350 0.45 - 0.67 0.22
c) RCC M-25 grade m3 0.375 0.45 - 0.67 0.22
d) RCC M-30 grade m3 0.400 0.45 - 0.67 0.22
e) RCC M 35 grade m3 0.413 0.45 - 0.67 0.22
f) RCC M 40 grade m3 0.425 0.45 - 0.67 0.22