Escolar Documentos
Profissional Documentos
Cultura Documentos
Q: What is a Contract?
7
Contracts involve a process from conception to grave
8
Q: Is it true (or fair) to say that a bad
contract is the fault of those involved
at the tender stage?
A: No. Why?
A: No. Why?
9 9
Q: Who is involved in managing a contract?
10
FIDIC Contracts Workshop Objectives
12
FIDIC
(Fdration Internationale des
Ingnieurs-Conseils)
Federation of national associations of consulting engineers
Based in Geneva
Founded in 1913 with original founding members from France,
Belgium and Switzerland
UK joined 1949, USA joined 1958
Seen as international from 1970s and members from about 70
counties
Amongst other things, FIDIC produces Standard Forms of
Contract
General principles of FIDIC Standard Forms
of Contract - 1
16
Current FIDIC Main Standard Forms of Contract
Yellow book.
Plant and
Design-Build
Contract
Gold book.
DBO Contract
Silver book.
EPC/Turnkey
Contract
When do you use which standard form?
22
An overview - 1
31
Wikinger Offshore Wind Farm Conditions
Contractor to design and construct the Works so they are fit for
the purposes for which the Works are intended as defined in
the Contract (sub-clause 4.1).
The obligation for fitness for purpose is more onerous that
designing with due skill and care
i.e. Suitability of end product versus design process
Responsibility for fitness for purpose cannot be passed to
anyone else or insured
41
Do you?
43
Employers role Yellow Book
47
Some of the obligations Yellow Book
50
Exercise
51
Exercise - answers
The things that the Contractor should expect to receive from the
Employer and/or his representative within say 28 days of Contract
Award:
56
Time and planning
59
Rate of progress 2
Unless the Engineer notifies otherwise, the Contractor shall adopt these
revised methods, which may require increases in the working hours and /
or in the numbers of Contractors Personnel or Goods, at the risk and cost
of the Contractor
If these revised methods cause the Employer to incur additional costs, the
Contractor shall subject to Sub-Clause 2.5 [Employers Claims] pay these
costs to the Employer, in addition to delay damages (if any) under Sub-
Clause 8.7 below.
60
Valuation &
Payments
Contract Price and Payments
62
Payment Procedure
Clause 14.5 - Payment for plant and materials may apply certain
conditions attached
Clause 14.6 Engineer issues Interim Payment Certificate within 28
days of receipt of Statement
Certificate does not indicate acceptance or approval
Clause 14.7 Employer pays within 56 days of receipt of Statement
(different for advance payment)
Clause 14.8 - Contractor entitled to interest for late payments without
giving notice
Clause 16.1 Engineer failure to certify or Employer failure to pay also
gives rights for Contractor to slow down and / or suspend Works
(notice needed)
63
Payment Procedure
Only the Engineer (or delegated assistants) can vary the Works
(sub-clause 13.1).
Variations is a defined term and a change to the Employers
Requirements.
A Contractors proposal to be requested prior to an variation
being instructed (sub-clause 13.1)
Contractor shall comply with instructions from the Engineer
(sub-clause 3.3)
Contractor has limited rights to object to a variation, but
can be over ruled (sub-clause 13.1)
Contractor is entitled to recover the time and money effects of
a Variation
Adjustments to the Contract Price are to be agreed or
determined by the Engineer
Reasonable profit is to be included
Contractors Claims
Notice
69
Procedure - Engineer
71
Completion and
Taking Over
72
Tests and Taking Over
74
Upon Taking Over 2
75
End of the Defects Notification
78
Yellow Book typical sequence of dispute
events envisaged in clause 20
81
Photograph credits to FreeDigitalPhoto.net & David Castilo Dominici