Você está na página 1de 7

Eng.

Kareem Adel SEA - HUB 03-Apr-17 23:31

Activity ID Activity Name Original Start Finish April 2017 May 2017 June 2017
Duration 25
09 16 23 30 07 14 21 28 04 11 18

Total 50day 15-Apr-17 11-Jun-17 11-Jun-17, Total

SEA - HUB
HU 50day 15-Apr-17 11-Jun-17 11-Jun-17, SEA -
SE1000 Project Start 0day 15-Apr-17 Project Start
SE1010 Project Finish 0day 10-Jun-17 Project Finish
Phase One 50day 15-Apr-17 11-Jun-17 11-Jun-17, Phase
Ph.1 Block A 50day 15-Apr-17 11-Jun-17 11-Jun-17, Ph.1 B
Sub_ Structure
Stru Works 25day 15-Apr-17 13-May-17 13-May-17, Sub_ Structure Works
Soil Works
Work 25day 15-Apr-17 13-May-17 13-May-17, Soil Works
SE1280 Excavation 3day 15-Apr-17 17-Apr-17 Excavation
SE1290 Back filling 1day 13-May-17 13-May-17 Back filling
SE1300 Bitumen &insulation 1day 11-May-17 11-May-17 Bitumen &insulation
Concrete Works 14day 18-Apr-17 03-May-17 03-May-17, Concrete Works
SE1310 Shuttering P.C Footings 3day 18-Apr-17 20-Apr-17 Shuttering P.C Footings
SE1320 Placing P.C Footing 1day 22-Apr-17 22-Apr-17 Placing P.C Footing
SE1330 De shuttering P.C Footing 2day 23-Apr-17 24-Apr-17 De shuttering P.C Footing
SE1340 Shuttering R.C Footings and Tie Beams 5day 25-Apr-17 30-Apr-17 Shuttering R.C Footings and Tie Beams
SE1350 Steel Fixing R.C Footings and Tie Beams 3day 25-Apr-17 27-Apr-17 Steel Fixing R.C Footings and Tie Beams
SE1360 Placing R.C Footings and Tie Beams 1day 01-May-17 01-May-17 Placing R.C Footings and Tie Beams
SE1370 De shuttering R.C Footings and Tie Beams 2day 02-May-17 03-May-17 De shuttering R.C Footings and Tie Beams
Super _ Structure
St Works 33day 04-May-17 11-Jun-17 11-Jun-17, Super
Concrete Works 24day 04-May-17 31-May-17 31-May-17, Concrete Works
SE1380 Shuttering Ground Floor R.C Columns 4day 04-May-17 08-May-17 Shuttering Ground Floor R.C Columns
SE1390 Steel Fixing Ground Floor R.C Columns 3day 04-May-17 07-May-17 Steel Fixing Ground Floor R.C Columns
SE1400 Placing Ground Floor R.C Columns 1day 09-May-17 09-May-17 Placing Ground Floor R.C Columns
SE1410 De shuttering Ground Floor R.C Columns 1day 10-May-17 10-May-17 De shuttering Ground Floor R.C Columns
SE1420 Shuttering Ground Floor R.C Slab and Beams 5day 20-May-17 24-May-17 Shuttering Ground Floor R.C Slab and Be
SE1430 Steel Fixing Ground Floor R.C Slab and 3day 25-May-17 28-May-17 Steel Fixing Ground Floor R.C Slab
B
SE1440 Placing Ground Floor R.C Slab and Beams 1day 29-May-17 29-May-17 Placing Ground Floor R.C Slab and
SE1450 De shuttering Ground Floor R.C Slab and 2day 30-May-17 31-May-17 De shuttering Ground Floor R.C
B
SE1500 Shuttering Ground Floor Slab on Grade 1day 14-May-17 14-May-17 Shuttering Ground Floor Slab on Grade
SE1510 Steel Fixing Ground Floor Slab on Grade 2day 15-May-17 16-May-17 Steel Fixing Ground Floor Slab on Grade
SE1520 Placing Ground Floor Slab on Grade 1day 17-May-17 17-May-17 Placing Ground Floor Slab on Grade
SE1530 DeShuttering Ground Floor Slab on Grade 1day 18-May-17 18-May-17 DeShuttering Ground Floor Slab on Grade
Finishing Works 9day 01-Jun-17 11-Jun-17 11-Jun-17, Finishi

Actual Work Critical Remaining ... Page 1 of 7 TASK filter: All Activities
Remaining Work Milestone Oracle Corporation
Eng. Kareem Adel SEA - HUB 03-Apr-17 23:31

Activity ID Activity Name Original Start Finish April 2017 May 2017 June 2017
Duration 25
09 16 23 30 07 14 21 28 04 11 18
SE1460 Ground Floor Brick Works 5day 01-Jun-17 06-Jun-17 Ground Floor Brick Wor
SE1470 Facade cladding 4day 07-Jun-17 11-Jun-17 Facade cladding
SE1480 Roof Insulation 2day 01-Jun-17 03-Jun-17 Roof Insulation
SE1490 Roof Flooring 3day 07-Jun-17 10-Jun-17 Roof Flooring
Ph.1 Block B 50day 15-Apr-17 11-Jun-17 11-Jun-17, Ph.1 B
Sub_ Structure
Stru Works 25day 15-Apr-17 13-May-17 13-May-17, Sub_ Structure Works
Soil Works
Work 25day 15-Apr-17 13-May-17 13-May-17, Soil Works
SE1540 Excavation 3day 15-Apr-17 17-Apr-17 Excavation
SE1550 Back filling 1day 13-May-17 13-May-17 Back filling
SE1560 Bitumen &insulation 1day 11-May-17 11-May-17 Bitumen &insulation
Concrete Works 14day 18-Apr-17 03-May-17 03-May-17, Concrete Works
SE1570 Shuttering P.C Footings 3day 18-Apr-17 20-Apr-17 Shuttering P.C Footings
SE1580 Placing P.C Footing 1day 22-Apr-17 22-Apr-17 Placing P.C Footing
SE1590 De shuttering P.C Footing 2day 23-Apr-17 24-Apr-17 De shuttering P.C Footing
SE1600 Shuttering R.C Footings and Tie Beams 5day 25-Apr-17 30-Apr-17 Shuttering R.C Footings and Tie Beams
SE1610 Steel Fixing R.C Footings and Tie Beams 3day 25-Apr-17 27-Apr-17 Steel Fixing R.C Footings and Tie Beams
SE1620 Placing R.C Footings and Tie Beams 1day 01-May-17 01-May-17 Placing R.C Footings and Tie Beams
SE1630 De shuttering R.C Footings and Tie Beams 2day 02-May-17 03-May-17 De shuttering R.C Footings and Tie Beams
Super _ Structure
St Works 33day 04-May-17 11-Jun-17 11-Jun-17, Super
Concrete Works 24day 04-May-17 31-May-17 31-May-17, Concrete Works
SE1640 Shuttering Ground Floor R.C Columns 4day 04-May-17 08-May-17 Shuttering Ground Floor R.C Columns
SE1650 Steel Fixing Ground Floor R.C Columns 3day 04-May-17 07-May-17 Steel Fixing Ground Floor R.C Columns
SE1660 Placing Ground Floor R.C Columns 1day 09-May-17 09-May-17 Placing Ground Floor R.C Columns
SE1670 De shuttering Ground Floor R.C Columns 1day 10-May-17 10-May-17 De shuttering Ground Floor R.C Columns
SE1680 Shuttering Ground Floor R.C Slab and Beams 5day 20-May-17 24-May-17 Shuttering Ground Floor R.C Slab and Be
SE1690 Steel Fixing Ground Floor R.C Slab and 3day 25-May-17 28-May-17 Steel Fixing Ground Floor R.C Slab
B
SE1700 Placing Ground Floor R.C Slab and Beams 1day 29-May-17 29-May-17 Placing Ground Floor R.C Slab and
SE1710 De shuttering Ground Floor R.C Slab and 2day 30-May-17 31-May-17 De shuttering Ground Floor R.C
B
SE1760 Shuttering Ground Floor Slab on Grade 1day 14-May-17 14-May-17 Shuttering Ground Floor Slab on Grade
SE1770 Steel Fixing Ground Floor Slab on Grade 2day 15-May-17 16-May-17 Steel Fixing Ground Floor Slab on Grade
SE1780 Placing Ground Floor Slab on Grade 1day 17-May-17 17-May-17 Placing Ground Floor Slab on Grade
SE1790 DeShuttering Ground Floor Slab on Grade 1day 18-May-17 18-May-17 DeShuttering Ground Floor Slab on Grade
Finishing Works 9day 01-Jun-17 11-Jun-17 11-Jun-17, Finishi
SE1720 Ground Floor Brick Works 5day 01-Jun-17 06-Jun-17 Ground Floor Brick Wor
SE1730 Facade cladding 4day 07-Jun-17 11-Jun-17 Facade cladding

Actual Work Critical Remaining ... Page 2 of 7 TASK filter: All Activities
Remaining Work Milestone Oracle Corporation
Eng. Kareem Adel SEA - HUB 03-Apr-17 23:31

Activity ID Activity Name Original Start Finish April 2017 May 2017 June 2017
Duration 25
09 16 23 30 07 14 21 28 04 11 18
SE1740 Roof Insulation 2day 01-Jun-17 03-Jun-17 Roof Insulation
SE1750 Roof Flooring 3day 07-Jun-17 10-Jun-17 Roof Flooring
Ph.1 Block C 34day 15-Apr-17 23-May-17 23-May-17, Ph.1 Block C
Sub_ Structure
Stru Works 16day 15-Apr-17 02-May-17 02-May-17, Sub_ Structure Works
Soil Works
Work 16day 15-Apr-17 02-May-17 02-May-17, Soil Works
SE1020 Excavation 1day 15-Apr-17 15-Apr-17 Excavation
SE1030 Back filling 1day 02-May-17 02-May-17 Back filling
SE1040 Bitumen &insulation 1day 01-May-17 01-May-17 Bitumen &insulation
Concrete Works 9day 16-Apr-17 25-Apr-17 25-Apr-17, Concrete Works
SE1050 Shuttering P.C Footings 2day 16-Apr-17 17-Apr-17 Shuttering P.C Footings
SE1060 Placing P.C Footing 1day 18-Apr-17 18-Apr-17 Placing P.C Footing
SE1070 De shuttering P.C Footing 1day 19-Apr-17 19-Apr-17 De shuttering P.C Footing
SE1080 Shuttering R.C Footings and Tie Beams 3day 20-Apr-17 23-Apr-17 Shuttering R.C Footings and Tie Beams
SE1090 Steel Fixing R.C Footings and Tie Beams 2day 20-Apr-17 22-Apr-17 Steel Fixing R.C Footings and Tie Beams
SE1100 Placing R.C Footings and Tie Beams 1day 24-Apr-17 24-Apr-17 Placing R.C Footings and Tie Beams
SE1110 De shuttering R.C Footings and Tie Beams 1day 25-Apr-17 25-Apr-17 De shuttering R.C Footings and Tie Beams
Super _ Structure
St Works 24day 26-Apr-17 23-May-17 23-May-17, Super _ Structure Works
Concrete Works 19day 26-Apr-17 17-May-17 17-May-17, Concrete Works
SE1120 Shuttering Ground Floor R.C Columns 2day 26-Apr-17 27-Apr-17 Shuttering Ground Floor R.C Columns
SE1130 Steel Fixing Ground Floor R.C Columns 2day 26-Apr-17 27-Apr-17 Steel Fixing Ground Floor R.C Columns
SE1140 Placing Ground Floor R.C Columns 1day 29-Apr-17 29-Apr-17 Placing Ground Floor R.C Columns
SE1150 De shuttering Ground Floor R.C Columns 1day 30-Apr-17 30-Apr-17 De shuttering Ground Floor R.C Columns
SE1160 Shuttering Ground Floor R.C Slab and Beams 3day 09-May-17 11-May-17 Shuttering Ground Floor R.C Slab and Beams
SE1170 Steel Fixing Ground Floor R.C Slab and 2day 13-May-17 14-May-17 Steel Fixing Ground Floor R.C Slab and Beams
B
SE1180 Placing Ground Floor R.C Slab and Beams 1day 15-May-17 15-May-17 Placing Ground Floor R.C Slab and Beams
SE1190 De shuttering Ground Floor R.C Slab and 2day 16-May-17 17-May-17 De shuttering Ground Floor R.C Slab and Beams
B
SE1240 Shuttering Ground Floor Slab on Grade 1day 03-May-17 03-May-17 Shuttering Ground Floor Slab on Grade
SE1250 Steel Fixing Ground Floor Slab on Grade 2day 04-May-17 06-May-17 Steel Fixing Ground Floor Slab on Grade
SE1260 Placing Ground Floor Slab on Grade 1day 07-May-17 07-May-17 Placing Ground Floor Slab on Grade
SE1270 DeShuttering Ground Floor Slab on Grade 1day 08-May-17 08-May-17 DeShuttering Ground Floor Slab on Grade
Finishing Works 5day 18-May-17 23-May-17 23-May-17, Finishing Works
SE1200 Ground Floor Brick Works 3day 18-May-17 21-May-17 Ground Floor Brick Works
SE1210 Facade cladding 2day 22-May-17 23-May-17 Facade cladding
SE1220 Roof Insulation 1day 18-May-17 18-May-17 Roof Insulation
SE1230 Roof Flooring 2day 22-May-17 23-May-17 Roof Flooring

Actual Work Critical Remaining ... Page 3 of 7 TASK filter: All Activities
Remaining Work Milestone Oracle Corporation
Eng. Kareem Adel SEA - HUB 03-Apr-17 23:31

Activity ID Activity Name Original Start Finish April 2017 May 2017 June 2017
Duration 25
09 16 23 30 07 14 21 28 04 11 18
Ph.1 Block D 34day 15-Apr-17 23-May-17 23-May-17, Ph.1 Block D
Sub_ Structure
Stru Works 16day 15-Apr-17 02-May-17 02-May-17, Sub_ Structure Works
Soil Works
Work 16day 15-Apr-17 02-May-17 02-May-17, Soil Works
SE1800 Excavation 1day 15-Apr-17 15-Apr-17 Excavation
SE1810 Back filling 1day 02-May-17 02-May-17 Back filling
SE1820 Bitumen &insulation 1day 01-May-17 01-May-17 Bitumen &insulation
Concrete Works 9day 16-Apr-17 25-Apr-17 25-Apr-17, Concrete Works
SE1830 Shuttering P.C Footings 2day 16-Apr-17 17-Apr-17 Shuttering P.C Footings
SE1840 Placing P.C Footing 1day 18-Apr-17 18-Apr-17 Placing P.C Footing
SE1850 De shuttering P.C Footing 1day 19-Apr-17 19-Apr-17 De shuttering P.C Footing
SE1860 Shuttering R.C Footings and Tie Beams 3day 20-Apr-17 23-Apr-17 Shuttering R.C Footings and Tie Beams
SE1870 Steel Fixing R.C Footings and Tie Beams 2day 20-Apr-17 22-Apr-17 Steel Fixing R.C Footings and Tie Beams
SE1880 Placing R.C Footings and Tie Beams 1day 24-Apr-17 24-Apr-17 Placing R.C Footings and Tie Beams
SE1890 De shuttering R.C Footings and Tie Beams 1day 25-Apr-17 25-Apr-17 De shuttering R.C Footings and Tie Beams
Super _ Structure
St Works 24day 26-Apr-17 23-May-17 23-May-17, Super _ Structure Works
Concrete Works 19day 26-Apr-17 17-May-17 17-May-17, Concrete Works
SE1900 Shuttering Ground Floor R.C Columns 2day 26-Apr-17 27-Apr-17 Shuttering Ground Floor R.C Columns
SE1910 Steel Fixing Ground Floor R.C Columns 2day 26-Apr-17 27-Apr-17 Steel Fixing Ground Floor R.C Columns
SE1920 Placing Ground Floor R.C Columns 1day 29-Apr-17 29-Apr-17 Placing Ground Floor R.C Columns
SE1930 De shuttering Ground Floor R.C Columns 1day 30-Apr-17 30-Apr-17 De shuttering Ground Floor R.C Columns
SE1940 Shuttering Ground Floor R.C Slab and Beams 3day 09-May-17 11-May-17 Shuttering Ground Floor R.C Slab and Beams
SE1950 Steel Fixing Ground Floor R.C Slab and 2day 13-May-17 14-May-17 Steel Fixing Ground Floor R.C Slab and Beams
Beams
SE1960 Placing Ground Floor R.C Slab and Beams 1day 15-May-17 15-May-17 Placing Ground Floor R.C Slab and Beams
SE1970 De shuttering Ground Floor R.C Slab and 2day 16-May-17 17-May-17 De shuttering Ground Floor R.C Slab and Beams
B
SE2020 Shuttering Ground Floor Slab on Grade 1day 03-May-17 03-May-17 Shuttering Ground Floor Slab on Grade
SE2030 Steel Fixing Ground Floor Slab on Grade 2day 04-May-17 06-May-17 Steel Fixing Ground Floor Slab on Grade
SE2040 Placing Ground Floor Slab on Grade 1day 07-May-17 07-May-17 Placing Ground Floor Slab on Grade
SE2050 DeShuttering Ground Floor Slab on Grade 1day 08-May-17 08-May-17 DeShuttering Ground Floor Slab on Grade
Finishing Works 5day 18-May-17 23-May-17 23-May-17, Finishing Works
SE1980 Ground Floor Brick Works 3day 18-May-17 21-May-17 Ground Floor Brick Works
SE1990 Facade cladding 2day 22-May-17 23-May-17 Facade cladding
SE2000 Roof Insulation 1day 18-May-17 18-May-17 Roof Insulation
SE2010 Roof Flooring 2day 22-May-17 23-May-17 Roof Flooring
Ph.1 Block E 32day 15-Apr-17 21-May-17 21-May-17, Ph.1 Block E
Sub_ Structure
Stru Works 15day 15-Apr-17 01-May-17 01-May-17, Sub_ Structure Works

Actual Work Critical Remaining ... Page 4 of 7 TASK filter: All Activities
Remaining Work Milestone Oracle Corporation
Eng. Kareem Adel SEA - HUB 03-Apr-17 23:31

Activity ID Activity Name Original Start Finish April 2017 May 2017 June 2017
Duration 25
09 16 23 30 07 14 21 28 04 11 18
Soil Works
Work 15day 15-Apr-17 01-May-17 01-May-17, Soil Works
SE2060 Excavation 1day 15-Apr-17 15-Apr-17 Excavation
SE2070 Back filling 1day 01-May-17 01-May-17 Back filling
SE2080 Bitumen &insulation 1day 30-Apr-17 30-Apr-17 Bitumen &insulation
Concrete Works 8day 16-Apr-17 24-Apr-17 24-Apr-17, Concrete Works
SE2090 Shuttering P.C Footings 2day 16-Apr-17 17-Apr-17 Shuttering P.C Footings
SE2100 Placing P.C Footing 1day 18-Apr-17 18-Apr-17 Placing P.C Footing
SE2110 De shuttering P.C Footing 1day 19-Apr-17 19-Apr-17 De shuttering P.C Footing
SE2120 Shuttering R.C Footings and Tie Beams 2day 20-Apr-17 22-Apr-17 Shuttering R.C Footings and Tie Beams
SE2130 Steel Fixing R.C Footings and Tie Beams 1day 20-Apr-17 20-Apr-17 Steel Fixing R.C Footings and Tie Beams
SE2140 Placing R.C Footings and Tie Beams 1day 23-Apr-17 23-Apr-17 Placing R.C Footings and Tie Beams
SE2150 De shuttering R.C Footings and Tie Beams 1day 24-Apr-17 24-Apr-17 De shuttering R.C Footings and Tie Beams
Super _ Structure
St Works 23day 25-Apr-17 21-May-17 21-May-17, Super _ Structure Works
Concrete Works 18day 25-Apr-17 15-May-17 15-May-17, Concrete Works
SE2160 Shuttering Ground Floor R.C Columns 2day 25-Apr-17 26-Apr-17 Shuttering Ground Floor R.C Columns
SE2170 Steel Fixing Ground Floor R.C Columns 1day 25-Apr-17 25-Apr-17 Steel Fixing Ground Floor R.C Columns
SE2180 Placing Ground Floor R.C Columns 1day 27-Apr-17 27-Apr-17 Placing Ground Floor R.C Columns
SE2190 De shuttering Ground Floor R.C Columns 1day 29-Apr-17 29-Apr-17 De shuttering Ground Floor R.C Columns
SE2200 Shuttering Ground Floor R.C Slab and Beams 2day 08-May-17 09-May-17 Shuttering Ground Floor R.C Slab and Beams
SE2210 Steel Fixing Ground Floor R.C Slab and 2day 10-May-17 11-May-17 Steel Fixing Ground Floor R.C Slab and Beams
B
SE2220 Placing Ground Floor R.C Slab and Beams 1day 13-May-17 13-May-17 Placing Ground Floor R.C Slab and Beams
SE2230 De shuttering Ground Floor R.C Slab and 2day 14-May-17 15-May-17 De shuttering Ground Floor R.C Slab and Beams
Beams
SE2280 Shuttering Ground Floor Slab on Grade 1day 02-May-17 02-May-17 Shuttering Ground Floor Slab on Grade
SE2290 Steel Fixing Ground Floor Slab on Grade 2day 03-May-17 04-May-17 Steel Fixing Ground Floor Slab on Grade
SE2300 Placing Ground Floor Slab on Grade 1day 06-May-17 06-May-17 Placing Ground Floor Slab on Grade
SE2310 DeShuttering Ground Floor Slab on Grade 1day 07-May-17 07-May-17 DeShuttering Ground Floor Slab on Grade
Finishing Works 5day 16-May-17 21-May-17 21-May-17, Finishing Works
SE2240 Ground Floor Brick Works 3day 16-May-17 18-May-17 Ground Floor Brick Works
SE2250 Facade cladding 2day 20-May-17 21-May-17 Facade cladding
SE2260 Roof Insulation 1day 16-May-17 16-May-17 Roof Insulation
SE2270 Roof Flooring 2day 20-May-17 21-May-17 Roof Flooring
Phase Two 50day 15-Apr-17 11-Jun-17 11-Jun-17, Phase
Ph.2 Block F including Toilets 50day 15-Apr-17 11-Jun-17 11-Jun-17, Ph.2 B
Sub_ Structure
Stru Works 25day 15-Apr-17 13-May-17 13-May-17, Sub_ Structure Works
Soil Works
Work 25day 15-Apr-17 13-May-17 13-May-17, Soil Works

Actual Work Critical Remaining ... Page 5 of 7 TASK filter: All Activities
Remaining Work Milestone Oracle Corporation
Eng. Kareem Adel SEA - HUB 03-Apr-17 23:31

Activity ID Activity Name Original Start Finish April 2017 May 2017 June 2017
Duration 25
09 16 23 30 07 14 21 28 04 11 18
SE2320 Excavation 3day 15-Apr-17 17-Apr-17 Excavation
SE2330 Back filling 1day 13-May-17 13-May-17 Back filling
SE2340 Bitumen &insulation 1day 11-May-17 11-May-17 Bitumen &insulation
Concrete Works 14day 18-Apr-17 03-May-17 03-May-17, Concrete Works
SE2350 Shuttering P.C Footings 3day 18-Apr-17 20-Apr-17 Shuttering P.C Footings
SE2360 Placing P.C Footing 1day 22-Apr-17 22-Apr-17 Placing P.C Footing
SE2370 De shuttering P.C Footing 2day 23-Apr-17 24-Apr-17 De shuttering P.C Footing
SE2380 Shuttering R.C Footings and Tie Beams 5day 25-Apr-17 30-Apr-17 Shuttering R.C Footings and Tie Beams
SE2390 Steel Fixing R.C Footings and Tie Beams 3day 25-Apr-17 27-Apr-17 Steel Fixing R.C Footings and Tie Beams
SE2400 Placing R.C Footings and Tie Beams 1day 01-May-17 01-May-17 Placing R.C Footings and Tie Beams
SE2410 De shuttering R.C Footings and Tie Beams 2day 02-May-17 03-May-17 De shuttering R.C Footings and Tie Beams
Super _ Structure
St Works 33day 04-May-17 11-Jun-17 11-Jun-17, Super
Concrete Works 24day 04-May-17 31-May-17 31-May-17, Concrete Works
SE2420 Shuttering Ground Floor R.C Columns 4day 04-May-17 08-May-17 Shuttering Ground Floor R.C Columns
SE2430 Steel Fixing Ground Floor R.C Columns 3day 04-May-17 07-May-17 Steel Fixing Ground Floor R.C Columns
SE2440 Placing Ground Floor R.C Columns 1day 09-May-17 09-May-17 Placing Ground Floor R.C Columns
SE2450 De shuttering Ground Floor R.C Columns 1day 10-May-17 10-May-17 De shuttering Ground Floor R.C Columns
SE2460 Shuttering Ground Floor R.C Slab and Beams 5day 20-May-17 24-May-17 Shuttering Ground Floor R.C Slab and Be
SE2470 Steel Fixing Ground Floor R.C Slab and 3day 25-May-17 28-May-17 Steel Fixing Ground Floor R.C Slab
B
SE2480 Placing Ground Floor R.C Slab and Beams 1day 29-May-17 29-May-17 Placing Ground Floor R.C Slab and
SE2490 De shuttering Ground Floor R.C Slab and 2day 30-May-17 31-May-17 De shuttering Ground Floor R.C
B
SE2540 Shuttering Ground Floor Slab on Grade 1day 14-May-17 14-May-17 Shuttering Ground Floor Slab on Grade
SE2550 Steel Fixing Ground Floor Slab on Grade 2day 15-May-17 16-May-17 Steel Fixing Ground Floor Slab on Grade
SE2560 Placing Ground Floor Slab on Grade 1day 17-May-17 17-May-17 Placing Ground Floor Slab on Grade
SE2570 DeShuttering Ground Floor Slab on Grade 1day 18-May-17 18-May-17 DeShuttering Ground Floor Slab on Grade
Finishing Works 9day 01-Jun-17 11-Jun-17 11-Jun-17, Finishi
SE2500 Ground Floor Brick Works 5day 01-Jun-17 06-Jun-17 Ground Floor Brick Wor
SE2510 Facade cladding 4day 07-Jun-17 11-Jun-17 Facade cladding
SE2520 Roof Insulation 2day 01-Jun-17 03-Jun-17 Roof Insulation
SE2530 Roof Flooring 3day 07-Jun-17 10-Jun-17 Roof Flooring
Phase Three
Thre 31day 15-Apr-17 20-May-17 20-May-17, Phase Three
Ph.1 Block G 31day 15-Apr-17 20-May-17 20-May-17, Ph.1 Block G
Sub_ Structure
Stru Works 15day 15-Apr-17 01-May-17 01-May-17, Sub_ Structure Works
Soil Works
Work 15day 15-Apr-17 01-May-17 01-May-17, Soil Works
SE2580 Excavation 1day 15-Apr-17 15-Apr-17 Excavation

Actual Work Critical Remaining ... Page 6 of 7 TASK filter: All Activities
Remaining Work Milestone Oracle Corporation
Eng. Kareem Adel SEA - HUB 03-Apr-17 23:31

Activity ID Activity Name Original Start Finish April 2017 May 2017 June 2017
Duration 25
09 16 23 30 07 14 21 28 04 11 18
SE2590 Back filling 1day 01-May-17 01-May-17 Back filling
SE2600 Bitumen &insulation 1day 30-Apr-17 30-Apr-17 Bitumen &insulation
Concrete Works 8day 16-Apr-17 24-Apr-17 24-Apr-17, Concrete Works
SE2610 Shuttering P.C Footings 2day 16-Apr-17 17-Apr-17 Shuttering P.C Footings
SE2620 Placing P.C Footing 1day 18-Apr-17 18-Apr-17 Placing P.C Footing
SE2630 De shuttering P.C Footing 1day 19-Apr-17 19-Apr-17 De shuttering P.C Footing
SE2640 Shuttering R.C Footings and Tie Beams 2day 20-Apr-17 22-Apr-17 Shuttering R.C Footings and Tie Beams
SE2650 Steel Fixing R.C Footings and Tie Beams 1day 20-Apr-17 20-Apr-17 Steel Fixing R.C Footings and Tie Beams
SE2660 Placing R.C Footings and Tie Beams 1day 23-Apr-17 23-Apr-17 Placing R.C Footings and Tie Beams
SE2670 De shuttering R.C Footings and Tie Beams 1day 24-Apr-17 24-Apr-17 De shuttering R.C Footings and Tie Beams
Super _ Structure
St Works 22day 25-Apr-17 20-May-17 20-May-17, Super _ Structure Works
Concrete Works 18day 25-Apr-17 15-May-17 15-May-17, Concrete Works
SE2680 Shuttering Ground Floor R.C Columns 2day 25-Apr-17 26-Apr-17 Shuttering Ground Floor R.C Columns
SE2690 Steel Fixing Ground Floor R.C Columns 1day 25-Apr-17 25-Apr-17 Steel Fixing Ground Floor R.C Columns
SE2700 Placing Ground Floor R.C Columns 1day 27-Apr-17 27-Apr-17 Placing Ground Floor R.C Columns
SE2710 De shuttering Ground Floor R.C Columns 1day 29-Apr-17 29-Apr-17 De shuttering Ground Floor R.C Columns
SE2720 Shuttering Ground Floor R.C Slab and Beams 2day 08-May-17 09-May-17 Shuttering Ground Floor R.C Slab and Beams
SE2730 Steel Fixing Ground Floor R.C Slab and 2day 10-May-17 11-May-17 Steel Fixing Ground Floor R.C Slab and Beams
B
SE2740 Placing Ground Floor R.C Slab and Beams 1day 13-May-17 13-May-17 Placing Ground Floor R.C Slab and Beams
SE2750 De shuttering Ground Floor R.C Slab and 2day 14-May-17 15-May-17 De shuttering Ground Floor R.C Slab and Beams
B
SE2800 Shuttering Ground Floor Slab on Grade 1day 02-May-17 02-May-17 Shuttering Ground Floor Slab on Grade
SE2810 Steel Fixing Ground Floor Slab on Grade 2day 03-May-17 04-May-17 Steel Fixing Ground Floor Slab on Grade
SE2820 Placing Ground Floor Slab on Grade 1day 06-May-17 06-May-17 Placing Ground Floor Slab on Grade
SE2830 DeShuttering Ground Floor Slab on Grade 1day 07-May-17 07-May-17 DeShuttering Ground Floor Slab on Grade
Finishing Works 4day 16-May-17 20-May-17 20-May-17, Finishing Works
SE2760 Ground Floor Brick Works 2day 16-May-17 17-May-17 Ground Floor Brick Works
SE2770 Facade cladding 2day 18-May-17 20-May-17 Facade cladding
SE2780 Roof Insulation 1day 16-May-17 16-May-17 Roof Insulation
SE2790 Roof Flooring 2day 18-May-17 20-May-17 Roof Flooring

Actual Work Critical Remaining ... Page 7 of 7 TASK filter: All Activities
Remaining Work Milestone Oracle Corporation

Você também pode gostar