Design a gravity dam for the following data:

Maximum allowable compressive stress in concrete= 3000kN/m2


GRAVITY DAM Maximum Reservoir level=200.0m
R.L. of bottom of dam=100.0m
Specific gravity of concrete=2.4
Unit weight of water=10 kN/m2

Solution: Use freeboard of 3m.


RL OF TOP= 203.0m R.L. of the top of the dam=200+3=203m
Height of low gravity dam=H1=f/ (Sc+1)
51,8
30

R.L. 200 Putting the values, H1=88.2m, <Height of the Dam


Therefore it is high gravity dam.
161

Hence the dam from RL 200 to RL 111.8 designed as low gravity dam. And the dam from RL 111.8 to 100 shall
110,44
249

be designed as high gravity dam.


88

Design of low dam from RL 200m to RL 11.8m


Top width=a=5.18m (from calculation)
Base width required=56.8m
882

Upstream projection from vertical face required=a/16=0.33m


Total base width=56.8+.33= 57.13m
633

U/S batter provided at a depth of =2a(Sc)1/2=16.1m from below M.W.L.


and it ends at a depth of 3.1a(Sc)1/2=24.9m

Design of the dam from RL 111.8m to RL 100m

R.L.118.1 Designed in three strips.


Strip1 (After Calculation)
38

571,3
R.L. 108.0m 29
3,7
40

604
R.L.104.0m
4,5
31,5
y1=3.8m ; B1=57.13m ; B2=60.4m ; X2=0.37m
40

640
R.L.100m
6,2
33,8

Strip 2 (After Calculation) Topic: GRAVITY DAM


Base of Dam
y2=4m ; B2=60.4m ; B3=64m ; X3=0.45m Name: Chandrajyoti Kumar
Strip 3 (After Calculation) Roll: 13114904
y3=4m ; B3=64m ; B4=68m ; X4=0.62m Branch: Civil, 8th Semester