Você está na página 1de 5

Product Installation Instructions

KHVT-3/C

High Voltage Termination


for 3/C Shielded
and Non-Shielded Power Cable

Raychem Korea Corporation


Electrical Products Division
General Instructions
Suggested Installation Equipment (not supplied with kit)
Cable preparation tools Clean, lint-free cloths Connector(s) and installation tools
Raychem P63 cable preparation kit or Non-conducting abrasive cloth, 120 Raychem recommended torch
cable manufacturer approved solvent grit or finer
Electrician's tape
Recommended Raychem Torches
Install heat-shrinkable cable accessories Clean burning torches include the
with a "clean burning" torch, i.e., a Raychem FH-2629 (uses refillable
propane torch that does not deposit propane cylinders) and FH-2616A1
conductive contaminants on the product. (uses disposable cylinder).
Safety Instructions
Warning: When installing electrical To avoid risk of accidental fire or As Raychem has no control over field
power system accessories, failure to explosion when using gas torches, conditions which influence product
follow applicable personal safety always check all connections for leaks installation, it is understood that the
requirements and written installation before igniting the torch and follow the user must take this into account and
instructions could result in fire or torch manufacturer's safety instructions. apply his own experience and
explosion and serious or fatal injuries. expertise when installing product.
To minimize any effect of fumes
produced during installation, always
provide good ventilation of confined
work spaces.
Adjusting the Torch Regulator Pressure
Adjust regulator and torch as required to torches will have a 3- to 4-inch yellow FH-2616A1 Full pressure
provide an overall 12- inch bushy flame. tip. Use the yellow tip for shrinking. FH-2629 15 psig
The FH-2629 will be all blue, the other
Cleaning the Cable
Use an approved solvent, such as the Some newer solvents do not evaporate Please follow the manufacturer's
one supplied in the P63 Cable Prep Kit, quickly and need to be removed with a instructions carefully.
to clean the cable. Be sure to follow the clean, lint-free cloth. Failure to do so
manufacturer's instructions. Failure to could change the volume resistivity of
follow these instructions could lead to the substrate or leave a residue on the
product failure. surface.
General Shrinking Instructions
Apply outer 3- to 4-inch tip of the To determine if a tube has completely Note: When installing multiple tubes,
flame to heat-shrinkable material with a recovered, look for the following, make sure that the surface of the last
rapid brushing motion. especially on the back and underside of tube is still warm before positioning and
Keep flame moving to avoid the tube: shrinking the next tube. If installed tube
scorching. 1. Uniform wall thickness. has cooled, re-heat the entire surface.
Unless otherwise instructed, start 2. Conformance to substrate.
shrinking tube at center, working flame 3. No flat spots or chill marks.
around all sides of the tube to apply 4. Visible sealant flow if the tube is
uniform heat. coated.

2
Installation Instructions
1. Determine jacket cutback; mark cable.

Cutback must be long enough to allow positioning of insulated conductors


without violating the bend radius (usually 10 times the diameter of the
cable) and fit within the min/max dimensions shown in Table 1.

*Note: If a sealing boot is to be used, at least 4" (102mm) of jacket must be Measure
visible extending from the conduit opening. Jacket
Table 1: Jacket Cutback Cutback
Indoor Outdoor
Conduct Size Minimum Normal Normal **
UPTO 38sqmm 400mm 600mm 700mm
50-250sqmm 450mm 650mm 800mm *Note
300-600sqmm 550mm 700mm 900mm

**If greater length is required, order bulk tubing. 592

2. Remove outer jacket.

Remove the outer jacket (and/or armor) and any filler or bedding tapes
around all three phases to the mark made in Step 1.

Note: Do not cut into the shielding layer or phase insulation. Phase Shield

Cable Jacket

3. Position rejacketing tubes.

If using UniShield cable, discard rejacketing tubes and go to Step 6.

Place one rejacketing tube (larger diameter) over each phase. Bottom of
tube should be within 1" (25mm) of the jacket cutback. Rejacketing
Tubes

Cable Jacket

4. Shrink rejacketing tubes in place.

Shrink in place beginning at the cable jacket end. Work the torch around
each tube and to the end of the phase with a smooth brushing motion to
ensure even shrinkage.

3
Installation Instructions
5. Trim rejacketing tubes.

Allow the tubes to cool enough to touch. Trim excess tubing from the end of
each phase.

6. Clean jacket.

Using an approved solvent, clean the cable jacket for 4" (102mm) below the
jacket cutback.

Clean 4"
(102mm)
7. Position sealing boot.

Thread the three phases and ground wire(s) through the sealing boot. The
phases go through the large holes; grounds go through the small holes.

Slide the boot over the cable jacket (or jacket shim) as far as it will go.
Insert the plugs into any unused ground holes. Hang the plugs by locks as
shown.

Sealing Boot

8. Shrink boot in place.

Begin shrinking boot fingers. Shrink down over body onto cable jacket.

4
Installation Instructions
9. Remove rejacketing tuber jacket.

* Remove the Treat rejacketing tube as each phases' cable jacket.

Note: Do not cut into the shielding layer or phase insulation. L Jacket
Cutback
Conduct Jacket Cutback
Size (sqmm) L (mm)

UP TO 38 190
50-100 210
120-250 230
300-500 250
OVER 500 290

10. Outdoor modification is complete.

*Refer to 1/C KHVT instructions to complete the 3/C termination.