Welcome to this presentation.

It is part of a suite of Engineering training modules.

It shows the activities and deliverables of the Plant Layout


discipline.

Comments are most welcome (herve.baron@gmail.com),


which I will incorporate for the benefit of all.

Please download this file so that you can see my trainers


notes in the top left corner latest Acrobat Pro feature.

2015 Herv Baron


Herv
HERVE Engineering disciplines: activities and deliverables
BARON

PROCESS

PLANT LAYOUT

EQUIPMENT

SAFETY & ENVIRONMENT

CIVIL

PIPING

PIPELINE

2015 Herv Baron


INSTRUMENTATION

ELECTRICAL
HERVE Piping discipline
BARON

Plant Layout &


Piping discipline

Piping Piping Piping stress


Plant Layout
installation materials analysis

2015 Herv Baron


HERVE Plant layout
BARON

What has to be considered in


the layout of a plant?

2015 Herv Baron


HERVE Layout/principles
BARON

From which direction comes the prevailing wind?

2015 Herv Baron


HERVE Layout/principles
BARON

The wind rose shows the frequency of winds blowing from particular directions.

The length of each "spoke" around the circle is related to the frequency that the wind blows from a

2015 Herv Baron


particular direction per unit time, emanating from zero at the center to increasing frequencies at
the outer circles.
HERVE Plant layout
BARON

The first step of Plant layout is to divide


the Plant area into separate blocks and
units.

Why is this done? How?

2015 Herv Baron


HERVE The Block Flow Diagram (BFD)
BARON

2015 Herv Baron


HERVE Plant layout
BARON

Minimum distances between Process Units


are determined according to GE GAP
2.5.2/2A

Classify Units in terms of Fire and


Explosion Hazard into 3 categories:

Moderate Hazard (MH)


Intermediate Hazard (IH)
High Hazard (HH)

Apply the following minimum distances


between units of various hazard category:

2015 Herv Baron


HERVE Plant layout
BARON

The first step of Plant layout is to divide


the Plant area into separate blocks and
units.

The second step of Plant layout is to


locate Equipment within each unit.

Which document are used as starting


points by Plant Layout?

2015 Herv Baron


2015 Herv Baron
Plot Plan
BARON
HERVE
HERVE Plant layout
BARON

What else shall be taken into account


to locate equipment?

2015 Herv Baron


HERVE Layout
BARON
Requirements from Process

REFLUX
CONDENSER What shall be the respective elevation
REFLUX of these equipment?
ACCUMULATOR

COLUMN

REFLUX
PUMP

2015 Herv Baron


HERVE Layout
BARON
Requirements from Process

REFLUX
CONDENSER What shall be the respective elevation
REFLUX of these equipment?
ACCUMULATOR

COLUMN

REFLUX
PUMP

2015 Herv Baron


HERVE On-shore plant: Equipment spacing recommendations
BARON
as per GE GAP Guidelines .2.5.2

Clear horizontal distance, in meters, between adjacent edges of equipment

2015 Herv Baron


HERVE Layout
BARON
Requirements from Process

What shall be the respective elevation


of the column and reboiler?

COLUMN

REBOILER

2015 Herv Baron


HERVE Layout
BARON
Requirements from Process

COLUMN

REBOILER

2015 Herv Baron


HERVE Layout/principles
BARON
Accesses

2015 Herv Baron


HERVE Layout principles: provision for piping flexibility
BARON

2015 Herv Baron


HERVE Layout principles: typical Unit Layout
BARON

2015 Herv Baron


HERVE Structured-mounted vertical vs grade-mounted horizontal
BARON
Equipment arrangement

2015 Herv Baron


HERVE Layout principles: typical Unit Layout
BARON

2015 Herv Baron


HERVE Unit Layout
BARON

2015 Herv Baron


What type of equipment has a large impact on the layout?
HERVE Layout / Equipment size by vendors
BARON

Duty spec

Waste
Heat
Boiler

2015 Herv Baron


14 meters

8 meters
HERVE Layout / package arrangement
BARON

2015 Herv Baron


HERVE Layout principles: pipe routing
BARON

There are 2 ways to run pipes. Name them.

2015 Herv Baron


HERVE Layout principles: typical Unit Layout
BARON

C/L of
Road

2015 Herv Baron


B/L(Battery
R limit)

Min. 7.5 m
HERVE Layout principles: typical Unit Layout
BARON

What is the purpose of leaving 3


meters distance between the 2

2015 Herv Baron


vessels??
HERVE Layout principles: typical Unit Layout
BARON

2015 Herv Baron


HERVE Layout principles: typical Arrangement of Air-coolers
BARON

2015 Herv Baron


HERVE Plant Layout
BARON
Job specification for design / Plant layout guidelines

Site elevation (s)

Minimum distances between units, equipment, buildings:


applicable code + supplementary information
C/L of Road
Clearance around equipment

Road width, clearance R


B/L(Battery limit)

Headroom clearance Min. 7.5 m


Pipe Rack of Structure

Min. 3 m

2015 Herv Baron


Line Up C/L of
Equipment
A
HERVE Interfaces between Engineering disciplines
BARON
Equipment
Plot Plan
Process eqt Eqt sizing
by vendors dimensions
specs

Process
design & Process eqt
simulations sizing

Process Flow
diagrams

Plot Plan
Piping routing

Fire water network routing

2015 Herv Baron


Instrument JB & cable routing

Electrical distribution & cable routing

Sewage sizing & layout


HERVE Overall Site plan
BARON

2015 Herv Baron


HERVE General plot plan
BARON

2015 Herv Baron


HERVE Unit plot plan
BARON

2015 Herv Baron


HERVE Unit plot plan
BARON
Elevation view

2015 Herv Baron


HERVE Unit plot plan
BARON
Plan view

2015 Herv Baron


HERVE 3D modelling
BARON

2015 Herv Baron


HERVE 3D model clash check
BARON

2015 Herv Baron


HERVE 3D model review
BARON

3 model reviews are usually done

2015 Herv Baron


HERVE 3D model review
BARON

3 model reviews are usually done:

What is the scope of the first model


review?

2015 Herv Baron


HERVE 3D model review
BARON

First model review:

Scope: finalize the Plot Plan

Content: Equipment + 30% of piping is modelled, i.e. all ines on PFDs

Outcome: after incorporation of COMPANYs comments, the Plot plan is released as the
base for the design (IFD).

Aspects reviewed:
Unit location, equipment location, main access and escape routes to facilities, major
piping routes indicated on PFDs, arrangement around LLI, location of main manifolds,
space around equipment for maintenance, platforms for main operation access

2015 Herv Baron


HERVE 30% model review
BARON

2015 Herv Baron


HERVE Air-Cooled Heat Exchangers
BARON
In which case would you install the ACHE at grade vs on pipe-rack?

2015 Herv Baron


HERVE Air-Cooled Heat Exchangers
BARON
In the case of installation on top of pipe-rack, what extra access shall be provided?

2015 Herv Baron


HERVE Plot Plan review
BARON
Hands-on exercise

Please review and


comment the Plot Plan

2015 Herv Baron


HERVE Piping Layout
BARON
Modular plants
In which cases is a modular plant preferable vs a stick built?

2015 Herv Baron


HERVE Design development
BARON

This is the Plot at FEED stage. Which parts of it do you expect will change at EPC stage?

2015 Herv Baron


HERVE Design development
BARON
Incinerator Package

FEED stage EPC Stage

2015 Herv Baron


HERVE Plant layout evolution
BARON
Combustion Air blowers + heater

FEED EPC - IFD EPC - IFC

2015 Herv Baron


HERVE The Oil & Gas Engineering Guide
BARON
2nd edition
Do you want to know more... Much more?

2015 Herv Baron


HERVE The Oil & Gas Engineering Guide - 2nd edition
BARON
Table of Contents

2015 Herv Baron


HERVE The Oil & Gas Engineering Guide
BARON
2nd edition

Order direct from the publisher:

http://www.editionstechnip.com/en/catalogu
e-detail/1111/oil-gas-engineering-guide-
the.html

2015 Herv Baron