BARON
PROCESS
PLANT LAYOUT
EQUIPMENT
CIVIL
PIPING
PIPELINE
ELECTRICAL
HERVE Piping discipline
BARON
The wind rose shows the frequency of winds blowing from particular directions.
The length of each "spoke" around the circle is related to the frequency that the wind blows from a
REFLUX
CONDENSER What shall be the respective elevation
REFLUX of these equipment?
ACCUMULATOR
COLUMN
REFLUX
PUMP
REFLUX
CONDENSER What shall be the respective elevation
REFLUX of these equipment?
ACCUMULATOR
COLUMN
REFLUX
PUMP
COLUMN
REBOILER
COLUMN
REBOILER
Duty spec
Waste
Heat
Boiler
8 meters
HERVE Layout / package arrangement
BARON
C/L of
Road
Min. 7.5 m
HERVE Layout principles: typical Unit Layout
BARON
Min. 3 m
Process
design & Process eqt
simulations sizing
Process Flow
diagrams
Plot Plan
Piping routing
Outcome: after incorporation of COMPANYs comments, the Plot plan is released as the
base for the design (IFD).
Aspects reviewed:
Unit location, equipment location, main access and escape routes to facilities, major
piping routes indicated on PFDs, arrangement around LLI, location of main manifolds,
space around equipment for maintenance, platforms for main operation access
This is the Plot at FEED stage. Which parts of it do you expect will change at EPC stage?