Escolar Documentos
Profissional Documentos
Cultura Documentos
INCORPORATING:
SRAS DESCRIPTION
VERSION: 1.0
STATUS: FINAL
IMPORTANT NOTICE:
These SRAS Guidelines are made under the National Electricity Rules and have effect only for the purposes set out in
those Rules. The National Electricity Rules and the National Electricity Law prevail over this document to the extent of
any inconsistency.
CONTENTS
Contents
1 COMMENCEMENT .................................................................................................. 6
Figures
Figure 6.1: Electrical sub-networks within Queensland ................................................................. 20
Figure 6.2: Electrical sub-networks within New South Wales ........................................................ 21
Figure 6.3: Electrical sub-network within Victoria .......................................................................... 22
Figure 6.4: Electrical sub-network within South Australia .............................................................. 23
Figure 6.5: Electrical sub-network within Tasmania....................................................................... 24
Figure 7.1: Procurement Process for SRAS .................................................................................. 26
1 COMMENCEMENT
Glossary
In this document, a word or phrase in this style has the same meaning as given to that term in the National
Electricity Rules (NER).
In this document, capitalised words or phrases or acronyms have the meaning set out opposite those words,
phrases, or acronyms in the table below.
Unless the context otherwise requires, this document will be interpreted in accordance with Schedule 2 of the
National Electricity Law.
Boundaries of Electrical Sub-Networks The boundaries of electrical sub-networks determined by AEMO under clause 3.11.4B(b) of the NER,
and set out in Section 6 of this document.
Delivery Point The transmission network connection point to which a generating unit forming part of SRAS
Equipment is assigned in the NEM.
Generator Modelling Data The data to be provided by an SRAS Provider to AEMO under the SRAS Assessment Guidelines
(Schedule 4.2).
Multiple Site SRAS An SRAS that is delivered using SRAS Equipment located at two or more sites linked via a
transmission network or distribution network.
SRAS Assessment Guidelines The SRAS assessment guidelines referred to in clause 3.11.4A(e) of the NER, and set out in Section
4 of this document.
SRAS Description The SRAS description referred to in clause 3.11.4A(d) of the NER, and set out in Section 3 of this
document.
SRAS Equipment One or more identified generating units and other facilities to be used to provide an SRAS.
SRAS Guidelines This document, comprising the SRAS Description, SRAS Assessment Guidelines, SRAS Quantity
Guidelines, Boundaries of Electrical Sub-networks and SRAS Tender Guidelines.
SRAS Objective The SRAS objective referred to in clause 3.11.4A(a) of the NER
SRAS Procurement Objectives The SRAS procurement objectives referred to in clause 3.11.4A(c) of the NER.
SRAS Provider A Generator with whom AEMO contracts to provide SRAS, or who submits an expression of interest
or tender to provide SRAS to AEMO.
SRAS Quantity Guidelines The SRAS quantity guidelines referred to in clause 3.11.4A(f) of the NER, set out in Section 5 of this
document.
SRAS Tender Guidelines The guidelines set out in Section 7 of this document, forming part of the NMAS tender guidelines
referred to in clause 3.11.5(a) of the NER.
SRAS Test A physical test of the capability of SRAS Equipment to provide the SRAS, in accordance with the
SRAS Assessment Guidelines (Section 4.4 and Schedule 4.1)
SRS The system restart standard determined by the Reliability Panel under the NER.
Test Report A report prepared by an SRAS Provider following an SRAS Test, in accordance with the SRAS
Assessment Guidelines.
Trip to house load (or TTHL) An electrical islanding scheme using generating units that can disconnect from the transmission
network following a major supply disruption and continue to supply their own auxiliaries or an isolated
segment of system load.
1 COMMENCEMENT
1 COMMENCEMENT
These SRAS Guidelines have been prepared by AEMO in accordance with the following clauses of the NER,
with an effective date of 5 September 2014.
3 SRAS DESCRIPTION
3 SRAS DESCRIPTION
3.1 INTRODUCTION
This Section 3 is the SRAS Description under clause 3.11.4A(d) of the NER. The SRAS Description:
(a) describes each type of SRAS, identifying it as a primary restart service or a secondary restart service;
(b) describes the technical and availability requirements of each type of SRAS.
3.3.1 TIMEFRAMES
In accordance with the SRAS Procurement Objectives, AEMO seeks to procure SRAS to ensure the SRS is
met. The current standard specifies the following timeframe for the energisation and restoration of supply in
each electrical sub-network following a major supply disruption:
(a) re-supply and energise the auxiliaries of power stations within 1.5 hours to provide sufficient capacity to
meet 40% of peak demand in that sub-network; and
(b) restore generation and transmission such that 40% of peak demand in that sub-network could be
supplied within 4 hours.
In accordance with the SRAS Assessment Guidelines and the SRAS Tender Guidelines, AEMO will select the
SRAS, or combination of SRAS, that enables the SRS to be met in each electrical sub-network in the most
efficient manner. Accordingly, potential SRAS Providers will be required to indicate a timeframe within which the
SRAS Equipment can provide the tendered MW capacity at the Delivery Point.
1 The tripping schemes must be able to be activated by sustained excessive high or low frequency excursions,
and where required by AEMO; frequency rate-of-change and/or loss of synchronisation or sustained excessive
low voltage excursions, with all settings specified or approved by AEMO.
2The reason for this demonstrated ability is to ensure that there are no interlocks that would prevent closing
onto a de-energised busbar.
3 SRAS DESCRIPTION
(e) A demonstrated ability to control network voltage within limits to meet the minimum requirements
specified by AEMO.
(f) A demonstrated ability to control power system frequency within limits to meet the minimum
requirements specified by AEMO.
(g) The service must be capable of operating in a stable manner and have no adverse effects on power
system security during network switching and load restoration.
The references in this Section 3.3.2 to a demonstrated ability mean that the relevant ability must be
demonstrated in accordance with the SRAS Assessment Guidelines.
4.1 INTRODUCTION
This Section 4 contains the SRAS Assessment Guidelines under clause 3.11.4A(e) of the NER. The SRAS
Assessment Guidelines set out:
(a) how AEMO will model and assess the technical capabilities of SRAS proposed under an EOI or Tender
(Sections 4.2 and 4.3);
(b) the physical testing requirements for SRAS proposed under an EOI or Tender, or contracted under an
ancillary services agreement (Sections 4.4 and 4.5 and Schedule 4.1); and
(c) the data, models and parameters of relevant plant and supplementary information that AEMO requires
for assessment purposes (Schedules 4.1 and 4.2).
For development projects or reconfigurations where proposed SRAS Equipment is not yet built or configured,
physical testing is not required, but the assessment process and data requirements are otherwise the same as
for proposed SRAS using existing SRAS Equipment.
The SRAS Assessment Guidelines apply to both primary restart services and secondary restart services3. The
assessments are the same for both types of SRAS, with some variations for trip to house load (TTHL) schemes.
3A primary restart service has a reliability of 90% or more, a secondary restart service has a reliability of 60% or
more.
If the SRAS Provider is unable to give AEMO all Generator Modelling Data relevant to its offered SRAS, it must
give AEMO:
(a) a list of the missing data and the reasons why it could not be provided; and
(b) any alternative data or assumptions the SRAS Provider considers could be substituted for the missing
data, and their source.
AEMO will endeavour to substitute the missing data, either as proposed by the SRAS Provider or using data or
assumptions that AEMO considers to be more reliable. However, AEMO will take into account the reliability of
the substituted data in assessing the results of the power system studies conducted under Section 4.3.
4.3.1 OBJECTIVES
AEMO will conduct power system studies in relation to proposed SRAS to:
(a) verify the capacity of the SRAS to start and supply auxiliaries of other power stations, facilitating a
rebuild of the power system.
(b) determine which other power stations can be energised subsequent to the SRAS rebuilding sections of
the power system.
(c) determine the preferred paths to allow energisation of the required sections of the power system.
(d) confirm the ability to restore load blocks.
(e) qualify the security of the restoration path during credible contingency events.
(f) determine potential changes to operating modes and/or control system settings of the SRAS Equipment.
(g) determine necessary changes to the settings of protective relays for the SRAS Equipment and
transmission network in the energisation path.
The power system studies will be based on modelling of the SRAS Equipment, its control systems and
protection systems, and relevant network elements including transmission lines, loads, protection systems,
dynamic and static reactive support plant and transformers, under black system conditions.
(a) Verify integrity of the restoration path for credible contingency events.
(b) Verify appropriateness of protective relays settings during contingency events.
(c) Verify appropriateness of the settings applied to excitation system control and associated limiters.
(b) address any deviation from the approved test procedure where applicable;
(c) state whether the contracted levels of performance and minimum technical requirements were achieved;
and
(d) state reasons for any failure to establish any required item under Schedule 4.1 and the remedial actions
taken to resolve those matters.
1b Trip to House Load Trip to house load from at least 80% Demonstrate trip operation of TTHL relay to disconnect SRAS 3. SRAS remains operational at house load provide output trends of SRAS unit.
of its registered capacity (as from power system.
registered with AEMO).
2 Timeframes Provide SRAS in specified Time to be ready to commence sending out electricity from the Record the time at the following milestones over the duration of the SRAS test:
timeframe. SRAS Equipment. 4. Start of the SRAS test.
Time to reach specified electricity export capability. 5. Time at stable operation - ready to energise a de-energised busbar.
6. Time of commencement of the zero export load ability.
7. Times of completion of the zero export load ability.
8. Time of connection to isolated busbar.
9. Time commenced loading.
10. Time at contracted level of performance.
11. Time end of SRAS test.
3 Zero Export Operate in a stable manner at zero Run at zero export load for at least 30 minutes. 12. Frequency and voltage trends (and/or other) to demonstrate the SRAS operated in
export load. a stable manner at zero export load for at least 30 minutes.
4 Voltage Control Control SRAS voltage. Change SRAS output voltage by 5% above and below nominal 13. Provide output voltage trend for the duration of the SRAS test.
output voltage and hold each change for 5 minutes (measured at
generator terminals or other agreed point). Can be done
concurrently with item 3.
5 Frequency control Control SRAS frequency. Change SRAS output frequency by 0.5 Hz above and below 50 14. Provide output frequency trend for the duration of the SRAS test.
Hz and hold each change for 5 minutes (measured at generator
terminals or other agreed point). Can be done concurrently with
item 3.
6 Energise De-energised Close onto a de-energised busbar. SRAS to close onto a de-energised busbar (or other de- 15. Provide voltage trend of for the busbar for the duration of the SRAS test.
Busbar energised electrical equipment agreed by AEMO).
Supplementary Information
8 Start-up performance Performance over previous 12 - Provide evidence of the number of successful starts or TTHL trips in the most recent 12-month
months. period out of the total number of attempted starts or trips.
9 Reliability4 Availability over previous 12 months. - Demonstrate that SRAS Equipment meets or exceeds the minimum reliability percentage for
the proposed service specified in the SRS, determined in accordance with the SRAS
Description for the most recent 12-month period.
If the SRAS requires multiple generating units to deliver the service, evidence of reliability for
each of the units is required.
10 TTHL Relay TTHL relay operation. - Demonstrate and record the TTHL relay functions by injecting signals representing each (all) of
the trip conditions - with the outputs of the TTHL relay disabled. The TTHL generating unit is not
required to trip for this test.
11 Networks within SRAS Use of external network between - Demonstrate how the SRAS Provider will manage the use of an external network to provide the
(Multiple Site SRAS) SRAS sites. SRAS provide procedure or equivalent documentation endorsed by NSP.
5.1 INTRODUCTION
This Section 5 contains the SRAS Quantity Guidelines under clause 3.11.4A(f) of the NER. These Guidelines
describe the procedure for determining the number, type, and location of SRAS required to be procured for each
electrical sub-network, consistent with the SRS.
5.5 PROCEDURE
AEMO will follow an iterative procedure to determine and allocate the appropriate number, type, and location of
SRAS for each electrical sub-network. AEMO will:
(a) Determine and allocate the best SRAS available to restore and energise the electrical sub-network
following a major supply disruption (considering, size, timeframes, location and other relevant
characteristics of the SRAS).
(b) If the selected SRAS is not sufficient to meet the SRS for that electrical sub-network, select the next best
SRAS available (and so on) until a sufficient quantity is procured.
(c) Review the outcome in each electrical sub-network against the diversity and strategic location guidelines
in the SRS and adjust as far as reasonably practicable to meet those guidelines while still ensuring that
sufficient SRAS is procured to meet the SRS.
6.1 INTRODUCTION
This Section 6 contains the Boundaries of Electrical Sub-networks under clause 3.11.4B of the NER. AEMO is
required to determine the boundaries of the electrical sub-networks into which the power system is to be divided
for the purpose of acquiring SRAS and determining and implementing the system restart plan. The boundaries
must be determined in accordance with the guidelines set out in the SRS.
Qld South and NSW One 330 kV double circuit transmission corridor and a DC Direct Link between Qld South and NSW (i.e.: Terranora Qld South:
The boundary between Qld South and NSW cuts across the Mudgeeraba). These transmission corridors link Qld South and NSW. Generation: 7,120 MW
interconnectors between Qld and NSW: The major generation centre in Qld South electrical sub-network is in South West Qld. Load: 5,650 MW
QNI Bulli Creek Dumaresq 330 kV lines (8L & 8M) and Direct NSW:
link Terranora Mudgeeraba 132 kV DC lines (DC1, DC2 &
DC3). Generation: 17,775 MW
Refer to Figure 6.1 and Figure 6.2 for regional view Load: 14,750 MW
NSW and Vic One 330 kV double circuit transmission corridor, another 330 kV single circuit transmission corridor and a weak 220 kV NSW:
The boundary between NSW and Vic cuts across Murray single circuit transmission corridor connection between Redcliffs and Buronga. Generation: 17,775 MW
Dederang 330 kV lines (67, 68), WodongaJindera 330 kV line The major generation centres in NSW electrical sub-network are in Hunter Valley and Snowy Mountains area. Load: 14,750 MW
(060) and a BurongaRedcliffs 220 kV line (0X1).
Vic:
Refer to Figure 6.2 and Figure 6.3 for regional view
Generation: 12,620 MW
Load: 10,580 MW
BOUNDARIES BETWEEN ELECTRICAL SUB- FACTORS CONSIDERED IN DETERMINING BOUNDARIES GENERATION AND LOAD IN ELECTRICAL
NETWORKS SUB-NETWORK
NUMBER AND STRENGTH OF TRANSMISSION CORRIDORS CONNECTING TO REMAINDER OF
THE POWER SYSTEM (APPROXIMATE FIGURES)
AND ELECTRICAL DISTANCE (LENGTH OF TRANSMISSION LINES) BETWEEN GENERATION
CENTRES
Vic and SA One 275 kV double circuit transmission corridor and a DC link between Vic and SA. Vic:
The boundary between Vic and SA cuts across Heywood The major generation centre in Vic electrical sub-network is in Latrobe Valley. Generation: 12,620 MW
South-East 275 kV lines (1 & 2) and a DC Murraylink The major generation centre in SA electrical sub-network is in Adelaide. Load: 10,580 MW
Refer to Figure 6.3 and Figure 6.4 for regional view SA:
Generation: 5,140 MW
Load: 3,400 MW
Note: Any reference to a figure in this schedule refers to that figure in Schedule 6.2.
Qld North
Qld South
7.1 INTRODUCTION
This Section 7 contains the SRAS Tender Guidelines, which form part of the NMAS tender guidelines defined in clause
3.11.5(a) of the NER. As contemplated in clause 3.11.5(b) of the NER, AEMO has prepared separate NMAS tender
guidelines for SRAS and for network support and control ancillary services. The SRAS Guidelines must contain the
following (the numbering below corresponds with applicable subclauses in clause 3.11.5(b) of the NER):
(1) a requirement for AEMO to call for expressions of interest before issuing an invitation to tender in relation to any
required SRAS;
(2) a requirement that a person who is required to provide SRAS under an ancillary services agreement has the
facility tested in accordance with:
(i) the SRAS Assessment Guidelines; and
(ii) the timeframes for physical testing referred to in subparagraph (5);
(4) a requirement for an NSP or other Registered Participant to assist a prospective tenderer in identifying and, if
possible, resolving issues that would prevent the delivery of effective SRAS proposed by a prospective tenderer;
(5) the timeframes over which AEMOs assessment of SRAS expressions of interest, SRAS tenders and physical
testing of selected SRAS will occur;
(7) a requirement for a tenderer to provide data, models and parameters of relevant plant, sufficient to facilitate a
thorough assessment of the network impacts and power station impacts of the use of the relevant SRAS;
(8) the terms and conditions of the ancillary services agreement that a successful tenderer would be expected to
enter into with AEMO;
(9) the principles AEMO will apply in assessing SRAS expressions of interest and SRAS tenders; and
(10) any other matter considered appropriate by AEMO.
Issue request
4 Weeks for EOI
EOIs Close
Review EOIs
YES
Issue ITT
4 Weeks
ITTs Close
Review ITTs
YES
YES
NO
YES
AEMO chooses
Preferred Tenderers
In accordance with clause 3.11.5(f)(2) of the NER, if it would not be reasonable and practicable for an NSP to participate
in, or facilitate testing of a proposed SRAS, the SRAS Provider might need to redefine the proposed SRAS so that its
testing does not require NSP participation or facilitation.
7.5 DISPUTES
A dispute concerning any aspect (other than price) of a Tender for SRAS must be dealt with in accordance with clause
8.2 of the NER.