Escolar Documentos
Profissional Documentos
Cultura Documentos
ASSIGNMENT-I
Submitted by:
Submitted to:
April 6, 2017
1. Background
a) Introduction
Hydrodealkyation forms an integral process of chemical industries for manufacturing of Benzene
which is an important constituent for various chemical processes across the plants and labs. A
hydrodealkylation plant in general uses Toluene and Hydrogen as feed and producing various
fuels, most importantly being methane and butane which are burnt for obtaining the calorific value
and generating steam for electricity production.
A hydrodealkylation plant was modelled and simulated using Aspen Plus and economic analysis
was carried out using Aspen Economic Analyzer in order to obtain project feasibility. The plant
consisted of a reactor carrying out hydrodealkylation reaction at 922K, followed by a flash vessel
(334 kPa) in order to separate liquid benzene product from methane fuel. This is followed by a
distillation train operating at varying temperatures and pressure ultimately giving benzene product
of purity of 74.4%. In order to achieve benzene product of high purity optimization and sensitivity
analysis need to be carried out which shall be scope of future work.
Figure 1.1: Process flow sheet of Hydrodealkylation plant simulation on Aspen Plus [1]
2. Economic analysis
i) Operations
Operating Weeks/years: 52 (1 Week: 7 days, 1 day: 24 hours.)
Economic life of Project: 10 years.
For flowsheeting, 43056 kg/hr (95860lb/hr) of overall process feed containing Toluene 41.3% by
mole (11442.4 kg/hr ) and hydrogen 58.7% by mol (357.12 kg/hr) in excess was considered with
stream prices respectively $3.2/gal[1] and $2.9/kg[1]. From process plant analyzer overall raw
material costs obtained are tabulated as follows:
Cooling
Water Water 0.149503 MMGAL/H 17.94036 US$/H
Total 53.01/hr US$/hr
v) Overall Capital and Operating Cost Analysis
Table 2.4 Overall Cost analysis
S.No Quantity Percent of Total initial Cost (US$)
. Investment(T.I.)
Capital Costs
1. Total Initial Investment (T.I.) - $187285800
2. Total Project Cost - $ 8918370
3. Initial Working Capital Cost 5% $ 9364290
Operating Costs
1. Operating Charges 25% $ 46821450
2. Plant Overhead 50% $ 93642900
3. Total Operating Labor Cost 0.44% $ 832700
4. Total Maintenance Cost 0.05% $ 78346
5. General and Administrative 8% $ 911116
Expenses(G&A Expenses)
vi) Depreciation
Method: Straight Line Depreciation
Initial investment (V): 187285800
Salvage Value (Vs): 40% of Initial Working Capital Cost = $3745716
Service Life (n): 10 years
Depreciation: = = $18354008.4
4.) Conclusions
After suitable modifications in the conventional process flow sheet by introducing a recycle stream
of diphenyl benzene and replacing distillation column by flash drum it was observed that the
payout period decreased from 10.23 years to 8.3157 years. At the same time the operating cost of
the plant decreased from $48767543 to $46821450 (3.99%), and the Benzene yield increased from
0.0308 kmol/sec to 0.0334 kmol/sec(8.44%). Thus the obtained results confirms well with
suggested literature results [6].
5.) References
[1]. Jana, A.K. (2014). Process simulation and control using Aspen. New Delhi: PHI Learning.
[2]. Peters, M.S., Timmerhaus, K.D., & West, R.E. (2006). Plant design and economics for
chemical engineers. Boston: McGraw-Hill
[3]. Seider, W.D., Lewin, D.R., Seader, J.D., Widagdo, S., Gani, R., & Ng, K.M. (2017).
Product and process design principles: synthesis, analysis and evaluation. Hoboken, NJ:
Wiley.
[4]. Douglas, J.M. (2012). Conceptual design of chemical processes. Massachusetts: McGraw-
Hill.
[5]. Morales, M. (2013, July 19). Aspen Plus V8.0 Tutorial - Sensitivity Analysis. Retrieved
April 04, 2017, from https://www.youtube.com/watch?v=L8inROJ10Jw.
[6]. Hoo, K. (2015). A Modified Hierarchy for Designing Chemical Processes, (June 2006),
50375043. https://doi.org/10.1021/ie051443k