Escolar Documentos
Profissional Documentos
Cultura Documentos
1 Dismatling RCC & Carting away with a lead of 1 km (By Mechanical Means)
Dismantlling & clearing away the RCC & carting the excavated material from the site within 1.0 km d
suitable site including loading, unloading, conveyance charges & dumping the carted materialat in
charges, all leads, lifts and other incidental & operational charges etc.,complete(as per MoST 2.4(ii)
Details of cost for 1.25 cu.m.
a) Labour
Mazdoor (unskilled) 0.050 day 490.00
For Pneumatic Breaker 0.660 day 490.00
Blacksmith 0.250 day 623.00
For Loading 0.250 cum 490.00
b) Machinery
Air compressor 210 / 250 cfm with pneumatic 1.00 Hour 1511.50
breaker @1.0 cum per hour
Tractor with trolley 3t 0.27 Hour 345.00
Sub Total -1
c) Overheads & Contractors Profit 14%
Sub Total-2
Total for 1.25 Cum
Rate per Cum of RCC/PSC dismantling
Ordinary rock (not requiring blasting)- out put for 180 Cum
Mechanical Means-Upto 3 m depth
a)Labour
Mate 0 Nos. 0.00
Mazdoor (Unskilled) 6.24 Nos. 490.00
b) Machinery
Hydraulic Excavator 1 cum bucket capacity 6 hours 2821.50
Sub total
c&d) Overheads & Contractors Profit 14%
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
Rate per 1 Cum excluding Dewatering
7 RCC- M 20 Grade
BLD-CSTN-3-13-(30) - A
Supply and placing of the M-20 Design Mix Concrete corresponding to IS 456 using WEIGH BATC
20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to
Seigniorage charges, sales & other taxes on all materials including all operational, incidental a
such as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding co
fabrication charges for finished item of work (APSS No. 402)with minimum cement content a
Structural Components.
l) RCC M20- Beams up to 3.66 m height with Steel Scaffolding & Centering
Basic cost of RCC M-20 1.00 Cum 6458.62
Material Hire Charges ,Pg.78 1.00 Cum 1064.00
Labour Charges, Pg.78 1.00 Cum 626.00
Add MA allowance on LC @ 25%
Sub Total
Overheads & Contractors Profit 14%
Total
Rate per One Cum
Unit : 1.0 MT
(a) Material
HYSD bars including 2.5 per cent for overlaps and 1.03 Ton 44000.00
wastage
Binding wire- 3.00 kg 70.00
Welding Electrodes @ 5# per Joint & 14 Joints per 70.00 Each 12.00
tonne
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Blacksmith / Bar bender 10.00 No 462.50
Mazdoor (Unskilled) 10.00 No 400.00
Sub Total
Over heads & Contractors profit 14%
Total per MT
Rate per Kg
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop) 13.30 sqm 16.00
Cement Mortar 1:3 for 25 mm thick 0.25 cum 3803.56
Dry Cement for making Lumps 50.00 kg 4.00
12 mm Plastering 2 coats in 1:4 & 1:2 cm both sides 21.80 sqm 138.74
A. MATERIALS:
Cement 76.80 Kg 4.00
Coursed Rubble Stone 0.94 Cum 1047.88
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum 0.16 Cum 1047.88
Fine aggregate (Sand) 0.32 Cum 1000.00
B. LABOUR:
Mason 1st class 1.50 Nos 437.50
Mazdoor (unskilled) 2.32 Nos 350.00
Total A+B
C.Overheads & Contractors Profit 14%
Grand Total
CRS Masonry CM(1:6), Rate/Cum
A. MATERIALS:
Cement 48.00 Kg 4.00
Bricks traditional size 23 x 11 x 7 cms 2nd class 512 Nos 4298.27
Fine aggregate (Sand) 0.20 Cum 800.00
B. LABOUR:
Mason 1st class 0.24 Nos. 437.50
Mason 2nd class 0.56 Nos. 400.00
Mazdoor (unskilled) 1.89 Nos. 350.00
Total A+B
c.Overheads & Contractors Profit 14%
Grand Total
Rate per One Cum
Plastering in CM(1:6) & CM(1:4) Base & Top Coats, 20mm th (16 & 4 mm)
BLD-CSTN-8-9-(84)
Plastering 20mm thick two coats with base coat of 16mm thick in C.M. (1:6) and top coat of 4mm
with dubara sponge finishing including cost & conveyance of all materials like cement, Sand , W
seigniorage charges, all operational, including charges, labour charges for mixing mortar, finishi
charges, curing , including cutting grooves where ever necessary etc., complete for finished item
surfaces of walls. (External walls)
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement 43.00 Kg 4.00
Fine aggregate (Sand) 0.18 Cum 1000.00
Top Coat in CM(1:4), 4 mm thick
Cement 14.50 Kg 4.00
Fine aggregate (Sand) 0.04 Cum 1000.00
B. LABOUR:
Mason 1st class 0.63 Nos 437.50
Mason 2nd class 1.47 Nos 400.00
Mazdoor (unskilled) 3.90 Nos 350.00
Sub Total
C.Overheads & Contractors Profit 14%
Grand Total for 10 Sq.m
Plastering 20mm, Two Coats Rate/Sq.m
A. MATERIALS:Output : 10Sq.m
Cement Mortor (1:4) 0.21 Cum 3139.67
B. LABOUR:
Mason 1st class 0.94 Nos 437.50
Mazdoor (unskilled) 1.60 Nos 400.00
Total A+B
C.Overheads & Contractors Profit 14%
Grand Total for 10 Sq.m
Plastering,CM(1:4), 20 mm Rate/Sq.m
A. MATERIALS:Output 10 Sq.m
Cement Mortor (1:3) 0.15 Cum 3803.56
B. LABOUR:
Mason 1st class 0.60 Nos 437.50
Mazdoor (unskilled) 0.96 Nos 400.00
Total A+B
C.Overheads & Contractors Profit 14%
Grand Total for 10 Sq.m
Plastering ,CM(1:3),12mm, Rate/Sq.m
Ceiling Plast.,CM(1:3),12mm Other Floors 1F 2F 3F
Basic rate per Sq.m 121.70 121.70 121.70
Hire Charges for Access Scaffolding 1.24 1.24 1.24
Labour Charges for Scaffolding 5.60 8.41 11.21
Add MA allowance on LC @ 1.40 2.10 2.80
Total 129.94 133.46 136.96
Overheads & Contractors Profit 18.19 18.68 19.17
Ceiling Plast.,CM(1:3),12mm, Rate/Sq.m 148.14 152.14 156.13
#REF! a). Painting to Walls with Oil Bound Washable Distemper Paint:
BLD-CSTN-11-10-(167)
Painting to new walls with 2 coats of ready mixed oil bound wahsable distemper of approved brand
base coat of Cement primer of approved brand, making 3 coats in all to give an even shade after th
the surface to remove all dirt and remains of loose powdered materials, including cost and
materials to work site and all operational, incidental, labour charges etc. complete for finished item
911 for internal walls
BMT-J-36: Supplying, application and finishing of Two Coats of Altek/Saicoat/Wall care , One Coat o
and Two Coats of Emulsion paint for internal Walls
Rate as per SSR 388/page 28 95.00
Over heads & Contractors Profit 14%
Unit = 10 sqm
A. MATERIALS:
Marble tiles 11.00 sqm 681.00
Cement for CM (1:8) for base coat 21.60 kg. 4.00
Cement for slurry 33.00 kg. 4.00
Cement for jointing 20.00 kg. 4.00
Sand for CM (1:8) proportion 0.12 cum 1000.00
B. LABOUR
Mason 1st class 3.10 day 437.50
Mason 2nd class 1.10 day 400.00
Mazdoor (unskiled) 0.86 day 350.00
Unit = 10 sqm
A. MATERIALS:
Glazed Ceramic Non Skid Floor Tiles of 300*300*7 10.10 sqm 397.00
mm thick of all colors
Cement for CM (1:8) for base coat 21.60 kg. 4.00
Cement for slurry 33.00 kg. 4.00
Cement for Pointing with CM (1:3) 6.000 kg. 4.00
Sand for CM (1:8) 0.12 cum 1000.00
Sand for pointing 0.020 cum 1000.00
B. LABOUR
Mason 1st class 0.96 day 437.50
Mason 2nd class 2.24 day 400.00
Mazdoor (unskiled) 3.30 day 350.00
Unit : 10 sqm
A. MATERIALS:
High Strenth CC Designer Tiles (Phoenix or 10.05 sqm 484.00
Equivalent)
Cement for CM (1:6) proportion for base coat 28.80 kg. 4.00
Cement for slurry 33.00 kg. 4.00
Cement for jointing & pointing 6.00 kg. 4.00
Pigment 2.00 kg. 32.50
Sand for CM (1:6) proportion 0.12 cum 1000.00
B. MACHINERY
Nill
C. LABOUR
Mason 1st Class 0.960 Day 437.50
Mason 2nd Class 2.240 Day 400.00
Mazdoor (unskiled) 3.30 Day 350.00
A. MATERIALS:
Polished Shahbad/Tandur 15/18mm thick Stones of 11.00 Sqm 167.66
size 0.40*0.40 m
Cement for CM (1:8) proportion for base coat 21.60 Kg 4.00
Cement for Slurry 33.00 Kg 4.00
Cement for Jointing 20.00 Kg 4.00
Sand for CM (1:8) proportion 0.12 Cum 1000.00
B. LABOUR:
Mason 1st class 3.100 Nos 437.50
Mason 2nd class 1.100 Nos 400.00
Mazdoor (unskilled) 0.86 Nos 350.00
Sub Total
Over heads & Contractors profit 14%
Total
Rate per 1 Sqm
78 Supplying and fixing of MS Grill for windows using 35x35x5 mm MS angle alround and 10mm
horizontally at 125mm centre to centre and vertically at 30cm centre to centre including fixing w
holdfasts (2 on each side) duly making cutting brick masonry, fixing and making to original s
painting grill with one coat of red oxide primer including and conveyance of all materials ,cutting
including all operational charges and all labour charges etc., complete for finished item of work.
Cost Analysis
Wt. of Grill 33.26 Kg 35.25
Labour charges for fabricating steel and fixing in 33.26 Kg 33.60
position as per SSR Item No.BMM-V.14-850 &
BMM-V.15-851.Pg- 68
Cutting Holes in Brick masonry and repiars -Labour 82.00 Each 4.00
Charges BMW-I.44 -pg.124
Sub Total
Over heads & Contractors profit 14%
Total (Cost of 2.25 Sq.m Grill)
Rate per Sq.m of Grill
Rate per 1 Sqm
Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead o
operational, incidental, labour charges such as shoring, sheeting, planking, strutting, etc. complet
of work including seigniorage excluding dewatering charges etc as per SS - 20 B (APSS 308).
a)Labour
Mate 0 Nos.
Mazdoor (Unskilled) (excluding AA ) 3.64 Nos. 490.00
Extra for foundations @ 75%
Sub total
c&d) Overheads & Contractors Profit 14%
Cost for 10 cum = a+b+c+d
Rate per cum = (a+b+c+d)/10
Rate per 1 Cum excluding Dewatering
Carting away Surplus excavated earth or other unusable material from work site within a lead of
place including loading , unloading charges etc. complete. Loading by Manual Means & Unload
Means.
Carting away Surplus excavated earth or other unusable material from work site within a lead of 5 K
place including loading , unloading charges etc. complete. Loading by Manual Means & Unloading
Means
Unit : Cum (Lead 5 Km)
Lead Charges 1.00 Cum 84.00
Loading Charges (Manual) 1.00 Cum 111.00
Unloading (Mechanical) 1.00 Cum 15.90
Add "MAA" on Labour #REF! 18.90
Total Rate per Cum
Bailing out water from the pipe line trenches with oil engine driven pump sets, including hire charg
and wages for Driver and Helper etc, complete,
Oil Engine Driven Pumpset Basic Rate Item.27(a) 1.00 Hp-Hr 38.00
PHSSR
Sub Total
Overheads & Contractors Profit 14%
Total
Rate per 1HP-Hr
Barricading, hoarding, lighting and watching etc., for water supply and sewerage works for trenche
2.0 m below G.L (As per PH Data)
Taking output 3 Rmt
Material
Bamboos of 1 dia 2.5 M long (5 ft c/c = 3 x 2.5) 7.50 Rmt 47.08
Cost of Bamboos
BLD-CSTN-2-5 - (13)
Earth work excavation in Ordinary Rock (not required blasting) for foundations and depositing on b
with an initial lead of 50m including all operational, incidental, labour charges such as shoring, s
strutting, etc. complete for finished item of work including seigniorage excluding dewatering charg
20 B (APSS 308).
Ordinary rock (not requiring blasting)-Manual
out put 10.00 Cum
Means-Upto 3 m depth
a)Labour
Mate 0 Nos.
Mazdoor (Unskilled) (excluding AA ) 5.20 Nos. 490.00
Sub total
Extra for foundations @ 75%
Sub total
c&d) Overheads & Contractors Profit 14%
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/10
Rate per 1 Cum excluding Dewatering
BLD-CSTN-2-6 - (14)
Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead o
operational, incidental, labour charges such as shoring ,sheeting, planking, strutting, etc. complet
of work including seigniorage excluding dewatering charges etc as per SS - 20 B (APSS 308).
BLD-CSTN-2-7 - (15)
Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead o
operational, incidental, labour charges such as shoring ,sheeting, planking, strutting, etc. complet
of work including seigniorage excluding dewatering charges etc as per SS - 20 B (APSS 308).
a)Labour
Mate 0.00 Nos 0.00
Mazdoor (Unskilled) 5.20 Nos 490.00
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack 6 hour 1285.40
hammers of pneumatic breaker at 1 cum per hour
Plain Cement concrete M 7.50 (1:4:8) Grade using 40mm size Hard Granite Machine Crushed Metal i
conveyance of all materials like cement, sand, coarse aggregate water etc., to site , seigniorage cha
materials, labour charges , for mixing , laying, concrete , ramming in 15 cm layers, finishing top su
required level curing etc., complete for finished item of work.for foundation and under flooring bed
RCC-M 25 Grade
Supply and placing of the M-25 Design Mix Concrete corresponding to IS 456 using WEIGH BATC
20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to
Seigniorage charges, sales & other taxes on all materials including all operational, incidental a
such as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding co
fabrication charges for finished item of work (APSS No. 402)with minimum cement content a
Structural Components.
RCC-M 30 Grade
Supply and placing of the M- 30 Design Mix Concrete corresponding to IS 456 using WEIGH BATC
20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to
Seigniorage charges, sales & other taxes on all materials including all operational, incidental a
such as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding co
fabrication charges for finished item of work (APSS No. 402)with minimum cement content a
Structural Components.
24 RCC M25 Grade COLUMNS, LINTELS(Unsupported Height of 3.66 m)- Steel Scaffolding & C
a Columns up to 3.66 m unsupported height above GL
R.C.C. M 25 Per Cum (Basic Cost) 1.00 Cum 6903.66
Centering Hire Charges ,Pg No.75 1.00 Cum 106.00
Labour charges,Pg No.75 1.00 Cum 747.00
Add MA allowance on LC @ 25%
Sub Total
Overheads & Contractors Profit 14%
Columns-M25 -Rate per One Cum
RCC M20 for Sun shades of 0.45M width, 100 mm th. at Support and 75 mm th. at edge Rate pe
(Unsupported Ht. of 3.66m) using Steel Scaffolding & Centering
a) Dome Slabs upto 3.66m unsupported Height - Steel Scaffolding & Centering
Basic cost of RCC M-20 1.00 Cum 6458.62
Centering Hire Charges ,Pg No.75 1.00 Cum 2281.00
Labour charges,Pg No.75 1.00 Cum 1152.00
Add MA allowance on LC @ 25%
Sub Total
Overheads & Contractors Profit 14%
Total
Dome Slabs-M20- Rate per One Cum
m) RCC M20 for Sun shades of 0.60M width, 100 mm th. at Support and 75 mm th. at edge Rate pe
(Unsupported Ht. of 3.66m) using Steel Scaffolding & Centering
Basic cost of RCC M-20 0.0525 Cum 6458.62
Material Hire Charges ,Pg.78 0.60 Sqm 139.00
Labour Charges, Pg.78 0.60 Sqm 82.00
Add MA allowance on LC @ 25%
Sub Total
Overheads & Contractors Profit 14%
Total
Sunshades-M20- 100/75mm-Rate per Rm
MASONRY
#REF! Fly Ash Cement / Lime Solid Block Masonry in CM (1:6), 15/20 cm thick
Fal-G masonry using Fal-G Solid Blocks of size 290x200x140 mm for super-structure on ground
Min. compressive strength of 50 Kg/Sq.cm including cost of all materials, seigniorage charge
operations and curing etc., complete for finished item of work (15/20cm thick)
A. MATERIALS:
Cement 24.00 Kg 4.00
Fal-G Bricks 290x200x140 mm - 50 Ksc 110 Nos 26.39
Fine aggregate (Sand) 0.10 Cum 1000.00
B. LABOUR:
Mason 1st class 0.60 Nos. 437.50
Mason 2nd class 0.60 Nos. 400.00
Mazdoor (unskilled) 2.75 Nos. 350.00
A. MATERIALS:
Cement 72.00 Kg 4.00
Bricks traditional size 23 x 11 x 7 cms 2nd class 512 Nos 4298.27
Fine aggregate (Sand) 0.20 Cum 800.00
B. LABOUR:
Mason 1st class 0.24 Nos. 437.50
Mason 2nd class 0.56 Nos. 400.00
Mazdoor (unskilled) 1.89 Nos. 350.00
Total A+B
c.Overheads & Contractors Profit 14%
Grand Total
Rate per One Cum
BM in CM(1:4),23cm -for Other Floors 1F 2F 3F
Basic rate per 1Cum 3639.22 3639.22 3639.22
Hire Charges for Access Scaffolding 23.01 23.01 23.01
Labour Charges for Scaffolding 123.54 185.31 247.08
Add MA allowance on LC @ 30.89 46.33 61.77
Sub Total 3816.65 3893.86 3971.08
Overheads & Contractors Profit @ 0.14 534.33 545.14 555.95
BM in CM(1:4),23cm - Rate/Cum 4350.98 4439.01 4527.03
A. MATERIALS:
Cement 24.00 Kg 4.00
Fal-G Bricks 290x200x140 mm - 50 Ksc 220 Nos 20.81
Fine aggregate (Sand) 0.10 Cum 800.00
B. LABOUR:
Mason 1st class 0.60 Nos. 623.00
Mason 2nd class 0.60 Nos. 567.00
Mazdoor (unskilled) 2.75 Nos. 490.00
A. MATERIALS:
Cement 79.20 Kg 4.00
CR Rubble Stone 0.44 Cum 1047.88
Rough Stone 0.50 Cum 781.10
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum 0.16 Cum 1047.88
Fine aggregate (Sand) 0.33 Cum 1000.00
B. LABOUR:
Mason 1st class 1.20 Nos 437.50
Mazdoor (unskilled) 2.00 Nos 400.00
Total A+B
C.Overheads & Contractors Profit 14%
Grand Total
RR Masonry,CM(1:6). Rate/Cum
A. MATERIALS:Output : 10 Sq.m
Cement 14.40 Kg 4.00
Fine aggregate (Sand) 0.03 Cum 1000.00
B. LABOUR:
Mason 2nd class 0.50 Nos 400.00
Mazdoor (unskilled) 0.74 Nos 350.00
Sub Total
C.Overheads & Contractors Profit 14%
Grand Total for 10 Sq.m
Flush Pinting,CRS Masonry, Rate/Sq.m
BLD-CSTN-12-2-(169)
Painting with Priming Coat on New Plastered Surface with Cement Primer Water base Exterior Gr-
brushing the surface to remove all dirt and remains of loose powdered materials including co
labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of w
BLD-CSTN-11-4- (161)
White washing one coat with white Cement of approved quality to give an even shade after thoro
surface to remove all dirt and remains of loose powdered materials including cost of all materials, l
incidental such as scaffolding, lift charges etc., complete for finished item of work, but excl
charges of materials. White Cement -One Coat.
BLD-CSTN-12-3-(170)
Painting Walls with 'Snowcem' or other equal and approved Water Proof Cement Paint over Primi
(All Colours) making 2 coats in all to give an even shade after thourughly brushing the surface to
remains of loose powdered materials, including cost and conveyance of all materials to work site a
incidental, labour charges etc. complete for finished item of work as per SS 912.
BMT-J-37: Supplying, application and finishing of Two Coats of Altek/Saicoat/Wall care , One Coat o
and Two Coats of Acrylic Washable Distemper for internal Walls
Rate as per SSR 389/page 28 90.00
Over heads & Contractors Profit 14%
BMT-J-38: Supplying, application and finishing of One Caot of Water base Cement Primer and Two
grade emulsion paint for exterior Walls
Rate as per SSR 390/page 28 96.00
Over heads & Contractors Profit 14%
BLD-CSTN-10-6: Painting New Wood Work with One Coat of Wood Primer
Unit: 10 sqm
Wood Primer - One Coat 0.70 Ltr 135.00
1st Class Painter 0.21 Nos. 437.50
2nd Class Painter 0.49 Nos. 400.00
BLD-CSTN-10-7: Painting New Iron Work with One Coat Red Oxide Primer
Unit: 10 sqm
Red Oxide Primer Gr-I - One Caot 0.70 Ltr 121.00
1st Class Painter 0.21 Nos. 437.50
2nd Class Painter 0.49 Nos. 400.00
Unit: 10 sqm
Wood Primer -One Coat
Synthetic Enamel Paint Gr-I - Two Coats 2.80 Ltr 230.00
1st Class Painter 0.36 Nos. 437.50
2nd Class Painter 0.84 Nos. 400.00
BLD-CSTN-10-10: Painting New Iron Work with One Coat of Red Oxide Primer and Two Coats of Sy
Paint
Unit: 10 sqm
Red Oxide Primer -One Coat
Synthetic Enamel Paint Gr-I - Two Coats 2.40 Ltr 230.00
1st Class Painter 0.36 Nos. 437.50
2nd Class Painter 0.84 Nos. 400.00
Unit: 10 Sq.m
a) Materials
Melamine Polish 0.65 Litres 299.00
Thinner for Melamine Polish 0.33 Litres 125.00
b) Labour
Painter - I Class 0.24 Day 437.50
Painter- II Class 0.56 Day 400.00
Helper 0.8 Day 350.00
Sundries for Spraying m/c etc. 1 5.00
Sub Total
c) Overheads & Contractors Profit 14% 849.60
Total cost per 10 Sq.m
Unit: 10 Sq.m
a) Materials
Poly Urethan Polish -interior Grade 0.70 Litres 608.00
Thinner for Poly urethane Polish 0.30 Litres 256.00
b) Labour
Painter - I Class 0.24 Day 437.50
Painter- II Class 0.56 Day 400.00
Helper 0.80 Day 350.00
Sundries for Spraying m/c etc. 1.00 5.00
Sub Total
c) Overheads & Contractors Profit 14% 1116.40
Total cost per 10 Sq.m
Output : 10 Sq.m
a) Materials
Plastic Emulsion Paint 0.50 Litre 244.00
b) Labour
Painter - 1st Class 0.21 Day 437.50
Painter-II Class 0.49 Day 400.00
Sundries for Brushes, Blades etc 1.00 3.00
Sub Total
c) Overheads & Contractors profit 14% 412.88
Total for 10 Sq.m
Cost per Sq.m (One Coat)-Internal
Output : 10 Sq.m
a) Materials
Synthetic /PoP Putty 9.00 Kg 26.00
b) Labour
Painter - 1st Class 0.27 Day 437.50
Painter-II Class 0.64 Day 400.00
Mazdoor 0.91 Day 350.00
Sundries for Emery paper, fillers, Knife etc 1.00 3.00
Sub Total
c) Overheads & Contractors profit 14% 929.74
Total for 10 Sq.m
Cost per Sq.m Wall Care Putty-Internal
Output : 10 Sq.m
a) Materials
Synthetic /PoP Putty 9.000 Kg 26.00
b) Labour
Painter - 1st Class 0.546 Day 437.50
Painter-II Class 1.274 Day 400.00
Mazdoor 1.820 Day 350.00
Labour for Access Scaffold 10.000 Sq.m 35.99
Sundries for Emery paper, fillers, Knife etc 1.000 3.00
Sub Total
c) Overheads & Contractors profit 14% 1982.38
Total for 10 Sq.m
Cost per Sq.m Wall Care Putty- External
54 BLD-CSTN-10-25-(148)
Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1
compound per bag of cement laid over roof when it is green including cost of all materials, se
excluding conveyance charges of materials and including all operational, incidental and labour c
mortar, laying, rendering smooth and thread lining, curing, rounding off junctions of wall and slab
finished item of work
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3 0.210 Cum 3803.56
Water proof compound 2.000 Kg 48.00
B. LABOUR
Mason 1st class 0.660 Nos 437.50
Mason 2nd class 1.540 Nos 400.00
Mazdoor (unskiled) 3.70 Nos 350.00
Sub Total
Over heads & Contractors profit 14%
Total cost for 10 sqm
Rate per 1 Sqm
FLOORING
BLD-CSTN-7-2
Flooring with 40 mm thick Rough Shahbad/Tandur stones, set over base coat of cement mortar (
over CC bed already laid or RCC roof slab, including pointing with cement mortar 1:3 duly f
including cost of all materials like flooring stone, cement, sand, and water etc., complete, inc
charges, labour charges for dressing of flooring stones etc., complete for finished item of work,
cost of conveyance of all materials.
A. MATERIALS:
Shahabad / Tandur Rough Stone slabs of minimum 10.50 Sqm 131.10
40 mm thick
Cement for CM (1:8) proportion for base coat 21.60 Kg 4.00
Cement for CM 1:3 proportion for pointing 9.60 Kg 4.00
Sand for CM (1:8) proportion 0.12 Cum 1000.00
Sand for CM (1:3) proportion 0.02 Cum 1000.00
B. LABOUR:
Mason 1st class 0.960 Nos 437.50
Mason 2nd class 2.240 Nos 400.00
Mazdoor (unskilled) 3.30 Nos 350.00
Sub Total
over heads & contractors profit 14%
Total cost for 10 sqm
Rate per 1 Sqm
BLD-CSTN-7-2
Flooring with 40 mm thick Rough Kadapa slabs, set over base coat of cement mortar (1 : 8) 12 mm
already laid or RCC roof slab, including pointing with cement mortar 1:3 duly filling joints neatly, in
materials like flooring stone, cement, sand, and water etc., complete, including seigniorage charge
for dressing of flooring stones etc., complete for finished item of work, but excluding the cost of
materials.
A. MATERIALS:
Rough Kadapa Slabs 40 mm thick of size 0.45 *0.45 10.50 Sqm 103.10
m
Cement for CM (1:8) proportion for base coat 21.60 Kg 4.00
Cement for CM 1:3 proportion for pointing 9.60 Kg 4.00
Sand for CM (1:8) proportion 0.12 Cum 1000.00
Sand for CM (1:3) proportion 0.02 Cum 1000.00
B. LABOUR:
Mason 1st class 0.960 Nos 437.50
Mason 2nd class 2.240 Nos 400.00
Mazdoor (unskilled) 3.30 Nos 350.00
Sub Total
over heads & contractors profit 14%
Total cost for 10 sqm
Rate per 1 Sqm
BLD-CSTN-7-1
with 25mm thick polished Bethemcherla (50% White & 50% black) stones of size 0.25 *0.25 m set
CM (1:8) over already laid CC bed / RCC Roof Slab, including neat cement slurry of honey like con
3.3 kgs per sqm. & Jointed with neat cement to full depth including cost of all materials like cemen
and flooring stones etc., complete, including seigniorage charges, labour charges for dressing of fl
complete for finished item of work, but excluding the cost of conveyance of all materials.
A. MATERIALS:
Polished Bethemcherla 50% White& 50 % Black 11.00 Sqm 335.44
-25mm thick and 0.25*0.25m
Cement for CM (1:8) proportion for base coat 21.60 Kg 4.00
Cement for Slurry 33.00 Kg 4.00
Cement for Jointing 20.00 Kg 4.00
Sand for CM (1:8) proportion 0.12 Cum 1000.00
B. LABOUR:
Mason 1st class 3.100 Nos 437.50
Mason 2nd class 1.100 Nos 400.00
Mazdoor (unskilled) 0.86 Nos 350.00
Sub Total
Over heads & Contractors profit 14%
Total
Rate per 1 Sqm
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size -900x90x10mm 10.10 sqm 1225.00
Cement for CM (1:8) for base coat 21.60 kg. 4.00
Cement for slurry 33.00 kg. 4.00
Cement for Pointing with CM (1:3) 6.000 kg. 4.00
Sand for CM (1:8) 0.12 cum 1000.00
Sand for pointing 0.020 cum 1000.00
B. LABOUR
Mason 1st class 0.96 day 437.50
Mason 2nd class 2.24 day 400.00
Mazdoor (unskiled) 3.30 day 350.00
A. MATERIALS:
6mm to 12 mm H.G. Metal (Machine crushed) 0.17 Cum 1576.85
Cement 120.00 Kg 4.00
Sand 0.085 Cum 1000.00
B. LABOUR:
Mason 1st class 1.25 Nos 437.50
Mason 2nd class 0.06 Nos 400.00
Mazdoor (unskiled) 3.00 Nos 350.00
Add water charges 1% 1.00%
Total
Over heads & Contractors profit 14%
Total cost for 10 sqm
Rate per 1 Sqm
Unit = 10 sqm
A. MATERIALS:
High polished Other than black Granite 16 to 18 mm 10.10 sqm 3440.66
thick slab other than black
Cement for CM (1:8) for base coat 36.00 kg. 4.00
Cement for slurry 33.00 kg. 4.00
White cement with color oxides for jointing & 6.00 kg. 32.50
pointing
Sand for CM (1:8) 0.20 cum 1000.00
B. LABOUR
Mason 1st class 3.00 day 437.50
Mason 2nd class 1.00 day 400.00
Mazdoor (unskiled) 8.00 day 350.00
Unit = 10 sqm
A. MATERIALS:
High polished black granite 16 to 18 mm thick slabs 10.10 sqm 2990.66
BLD-CSTN-7-18-(116)
Providing skirting to internal walls to 15 cm height/risers of steps with ceramic tiles 7.30 mm thi
flooring stones, set over base coat of CM (1:3) 12 mm thick with cement slurry of honey like consis
rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching s
including cost of all materials like tiles, cement, sand and water etc., complete including seignio
complete for finished item of work, but excluding the cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick 10.00 sqm 397.00
Sand for cm 1:3 base coat 0.12 cum 1000.00
Cement for cm 1:3 base coat 57.60 kgs 4.00
Cement for slurry 33.00 kgs 4.00
White cement for jointing & pointing 6.00 kgs 32.50
B. LABOUR
Mason 1st class 0.77 Nos 437.50
Mazdoor (unskiled) 0.80 Nos 350.00
Sub Total
Over heads & Contractors profit 14%
Total cost for 10 sqm
Rate per 1 Sq.m
BLD-CSTN-7-23
Providing skirting to internal walls to 15 cm height/risers of steps with 15 to 18 mm thick polishe
length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with cement sl
consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixe
matching shade to full depth, including cost of all materials like Shahabad stone, cement, san
complete including seigniorage charges, etc., complete for finished item of work, but exclu
conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
15 /18mm thick polished Shahabad stone 10.10 sqm 167.66
Sand for cm 1:3 base coat 0.12 cum 1000.00
Cement for cm 1:3 base coat 57.60 kgs 4.00
Cement for slurry 33.00 kgs 4.00
B. LABOUR
Mason Ist class 0.96 Nos 437.50
Mason 2nd class 2.24 Nos 400.00
Mazdoor (unskiled) 3.10 Nos 350.00
BLD-CSTN-7-21
Providing skirting to internal walls to 15 cm height/risers of steps with 8 mm thick mirror polished
equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with cement slurry of hone
spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of
full depth, including cost of all materials like tiles, cement, sand and water etc., complete inc
charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materi
Unit = 10 sqm
A. MATERIALS:
8 mm thick mirror polished granite tiles 10.10 sqm 1167.66
Sand for cm 1:3 base coat 0.12 cum 1000.00
Cement for cm 1:3 base coat 57.60 kgs 4.00
Cement for slurry 33.00 kgs 4.00
White cement for jointing & pointing 5.00 kgs 32.50
B. LABOUR
Mason Ist class 0.87 day 437.50
Mason 2nd Class 2.03 day 400.00
Mazdoor (unskiled) 4.90 day 350.00
Sub Total
Add water charges 1% 1.00%
Sub Total
Over heads & Contractors profit 14%
Total cost for 10 sqm
Rate per 1 Sq.m
BLD-CSTN-7-18
Providing skirting to internal walls with Glazed colour tiles of any size 1st quality set over a ba
Prop. 12mm thick and neat Gray cement slurry of Honey like consistancy sread at the rate of 3.30
One Square Meter and jointed wiyh neat White cement paste mixed with pigmant of matching sh
and conveyance of all materials like cement, sand, water, flooring Tiles etc. to site, all operatio
labour charges such as mixing of cement mortar, laying, jointing, curing, lift charges etc., comple
of work
A. MATERIALS:
Colour glazed tiles of 1st quality 10.10 Sqm 447.00
Sand for cm 1:3 base coat 0.12 cum 1000.00
Cement for cm 1:3 base coat 57.60 kgs 4.00
Cement for slurry 33.00 kgs 4.00
White cement for jointing & pointing 6.00 kgs 32.50
B. LABOUR
Mason Ist class 0.77 day 437.50
Mazdoor (unskiled) 0.80 day 350.00
Unit : 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles 30mm thick thick (Dark 10.05 sqm 266.00
Shade)
Cement for CM (1:6) proportion for base coat 28.80 kg. 4.00
Cement for slurry 33.00 kg. 4.00
Cement for jointing & pointing 6.00 kg. 4.00
Pigment 2.00 kg. 32.50
Sand for CM (1:6) proportion 0.12 cum 1000.00
B. MACHINERY
Nill
C. LABOUR
Mason 1st Class 0.96 day 437.50
Mason 2nd Class 2.24 day 400.00
Mazdoor (unskiled) 3.30 day 350.00
Unit : 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles 30mm thick thick (Dark 10.05 sqm 250.00
Shade)
Cement for CM (1:6) proportion for base coat 28.80 kg. 4.00
Cement for slurry 33.00 kg. 4.00
Cement for jointing & pointing 6.00 kg. 4.00
Pigment 2.00 kg. 32.50
Sand for CM (1:6) proportion 0.12 cum 1000.00
B. MACHINERY
Nill
C. LABOUR
Mason 1st Class 0.96 day 437.50
Mason 2nd Class 2.24 day 400.00
Mazdoor (unskiled) 3.30 day 350.00
Flooring with 60 mm thick-M30 Gr. CC Interlocking Pavers (All Colours & Pattterns) for Non Traffic
with IS_15658
Flooring with 60mm thick CC-M30 Gr. Interlocking pavers of all colours, sizes & all patterns la
sand bed to proper levels and grades including materials and labour charges etc. complete as
authorities for finished item of work excluding cost of Sand.
Unit : 10 sqm
A. MATERIALS:
60mm thick Interlocking CC Pavers(BMT-D.16) 10.05 sqm 400.00
B. MACHINERY
Nill
C. LABOUR
Mason 1st Class 0.96 Day 437.50
Mason 2nd Class 2.24 Day 400.00
Mazdoor (unskiled) 3.30 Day 350.00
Sub Total
Overheads & Contractors Profit 14.00%
Total Cost for 10 Sq.m
Rate per One Sq.m
Flooring with M15 Gr. Concrete & top Red Oxide Finish
Flooring with Cement Concrete ,M15 Gr (1:2:4) using 20 mm Graded HBG Chips, 50 mm thick and to
12 mm thick in CM(1:3) using Red oxid, with polished surface and neatly Finished to proper levels a
Unit = 10 sqm
A. MATERIALS:
PCC 1:2:4 using 20 mm Graded HBG Metal 0.50 Cum 5449.76
Plastering with CM (1:3), 12 mm thick 10.00 Sq.m 138.74
Red oxid Pigment (LR) 10.00 Kg 105.00
B. LABOUR
Mason 1 st Class for polishing 0.33 Day 437.50
Mason 2nd Class 0.77 Day 400.00
Sub Total
OH & CP @ 14% 5614.67
Total
M15 Gr.Flooring &Red Oxide: Rs/Sq.m
#REF! a). Precast RCC Door Frame with 30mm thick Flush Shutters:
Supply , Delivey and Fixing of RCC Precast Door Frame of Size 100x100 with 30mm thick solid bloc
shutters including cost of wooden reapers, butt hinges, Tower bolts, Aldrops and all other wi
complete for finished item of Work (Note: The Design of Frame shall be approved by Dept. before D
Output: 2.00 Sq.m (1.00 x2.00 m) 2.00
a) Material
Cost of Precast RCC Door Frame (LR) 6.00
30 mm thick Solid Block Board Shutter with 2.2
Commercial Ply on both sides
Sal Wood Reaper (50x30 mm) 0.007
Aluminium Butt Hinges,125 mm 6.00
Aluminium Handles,125mm 2.00
Aluminium Aldrops,250 mm 2.00
Aluminium Tower Bolts, 150 mm 2.00
MS Screws 40 mm 40
b) Labour
Carpenter-I Class 0.165
Carpenter-II Class 0.385
Mazdoor 0.55
Sub Total
#REF! Precast RCC Window Frame with Design Grill prefixed & 25 mm thick Flush Shutters
Supply , Delivey and Fixing of RCC Precast Window Frame of Size 80x80 mm with designer Grill p
thick solid block board flush door shutters including cost of wooden reapers, butt hinges, Tower
all other wind appliance ( Note: The Frame and design of Grill shall be approved by Dept. before De
BMT-P.25
NCL or Equivalent ECO 3000 SERIES WINDOWS (SUITABLE FOR RESIDENTIAL BUILDINGS WITH G
Providing and Fixing of windows made of pre-painted steel (Base steel as per IS 513 of 0.6mm thick
IS 277 with Zinc of 120 GSM). Primer coated with epoxy primer of 5-7 microns thick, finish painte
paint of 12-16 microns thick and back coated with 5-7 microns thick alkyd backer. Section for oute
of 48x50mm, centre mullion should be of 48x50mm, section for shutter should be of 47x20mm
beading section should be of 12x12mm. Outer frame and mullions to have rebate for Glazed sh
provision for Guard bars/Grills.
The Sections are to be cut to length metre jointed with corner bracket. Centre mullion is to be fixed
Seccolor Handle,seccolar stay, 2 nos of stainless steel heavy duty pivot hinges shall be provid
windows should be panelled with 5 mm thick plain float glass. Rubber gaskets are provided all aro
above frames should be fixed to the concrete/masonry wall by means of self expanding screw
square guard bars with 6" (152.4 mm) pitch etc. complete for finished item of work.
a Double shutter Window with vertical member 40 x 40 (1219.2mm x 1219.2mm) outer fram
48x50mm shutter frame section size of 47x20mm and mullion section should be of 48x50mm.
Rate as per SSR Item No. 742/62-BMT-P.25 1 Sqm 4806.00
over heads & contractors profit 14%
Total
Rate per 1 Sqm
b Centre fixed both side openable shutter window 50x40 (1524mm x1219.2mm). Outer fram
48x50mm. Shutter frame section size of 47x20mm. Mullion section size of 48x50mm. Fixed bead
12x12mm.
71 NCL or Equivalent ECO 4000 SERIES WINDOWS (SUITABLE FOR RESIDENTIAL BUILDINGS WITH
PROVISION) Providing & Fixing of windows made of pre-painted steel (Base Steel as per IS 5
galvanized as per IS 277 with zinc of 150 GSM). Primer coated with epoxy primer of 5-7 microns th
with a polyester paint of 12-16 microns thick and back coated with 5-7 microns thick alkyd backe
frame should be of 72x55mm, centre mullion should be of 72x50mm, Section for fixed glass bead
be of 12x12mm and section for shutters should be of 47x20mm. Outer frame & mullion sections
glazed shutters, fly mesh and a 20mm provision for guard bars/grills. Fly mesh shutter sec
20x40mm. The sections are to be cut to length metre joined with corner bracket. Centre mullions a
mullion cap, seccolor stay, seccolor handles, seccolor latch 2 Nos of heavy duty stainless steel piv
provided per Shutter.
The windows should be panelled with 5 mm thick plain float glass and SS Mesh for fly fly mesh shu
Rubber gaskets are provided all around the glass. The above frames should be fixed to the concret
means of self expanding screws including 10mm square guard bars with 6" (152.4 mm) pitch etc. co
finished item of work.
Centre fixed both side openable shutter window 50x40 (1524mm x1219.2mm). Outer fram
72x50mm. Shutter frame section size of 47x20mm. Mullion section size of 72x50mm. Fixed bead
12x12mm.
Rate as per SSR Item No. 748/63 BMT-P.31 1 Sqm 5719.00
over heads & contractors profit 14%
Total
Rate per 1 Sqm
NCL or Equivalent Sliding Windows Providing and Fixing Sliding Window fabricated from Roll form
of galvanized Steel colour coated/powder coated (Base Steel as per IS 513 D quality, galvanized
zinc of 120 GM/Sq.mtr) with total coated thickness of 0.60mm. Primer coat with epoxy primer of
finish painted with a polyester paint of 12-16 microns thick and back coated with Alkyd backer
powder coated with pure polyester powder up to 50-60 microns thick. Section for external frame b
79x44mm, external frame sides and top should be of 69x24mm, guide for top and bottom shou
(Stainless Steel). Section for shutter should be of 26x30mm. The windows should be panelled wi
float glass. Corner bracket for internal and external frame made of glass filled nylon. Gaskets are t
Propylene Diamine Monomer (EPDM).The sections are to be cut to length, joined and assembled b
bracket.
The above frames should be fixed to the concrete/masonry wall by means of self expanding screws
square guard bars with 6" (152.4 mm) pitch etc. complete for finished item of work.
Rate as per SSR Item No. 750/64 BMT-P.33 1 Sqm 5195.00
Over heads & Contractors profit 14%
Total
Rate per 1 Sqm
BMT-N.04
Providing and fixing 30mm thick RAJSHRI or Equivalent BRAND FACTORY MADE SOLID SINGLE SID
PVC DOOR SHUTTER consisting of frame made out of MS. Tubes of 19gauge thickness and size of 19m
and 15mmX15mm for top and bottom rails. The MS. Frame shall have a coat of steel primers of a
manufacture. MS. Frame covered with 5mm thick heat moulded Rajshri single side Prelam Pac
30mmX50mm to form stiles.5mm thick& 75mm wide single side prelim Pac sheets shall be for the top, b
Panelling of 5mm thick one side Pac sheet to be fitted in the MS. Frame and sealed to the front (prelam
(which should have a 5mm 45 bent portion as beading) and attached to the back(white/ivory) stiles an
have a 10mm 900 bent portion as beading ) using 2nos. 15mm wide X 5mm thick Pac sheet beading
beading. All stiles, rails and beadings are to be joined to the panel using solvent cement etc. an additional
of 20mm width to be stuck on the interior side of the C channel
using Pac solvent cement adhesive and 10 mm (5mmx2) thick, 20 mm wide cross pac sheet to be fitted as
and bottom rail etc. complete as per direction of Engineer in charge manufaturer specification and drawing
Rate as per SSR Item No.645, Pg 38 -BMT- 1 Sqm 2450.00
N.04
over heads & contractors profit 14%
Total
Rate per 1 Sqm
BMT-N.31
Doors Frames (Colour Coated Steel Sections) & Shutter using Cement Bonded Particle Board as p
Panel or Equivalent) : Providing and fixing of door frame made from cold roll formed sections m
(Base steel as per IS277 with zinc of 120 Gms/sqm) colour coated steel sections with total coated
primer coated with epoxy primer coat of 5-7 microns thick, finish paint with polyester paint of 1
Section for door frame is to be filled with polyurethane (P.U) form of 40kg/m3. Overall size of frame
of 50mm x 50mm. With necessary corner brackets, stiffeners, hinges, and screws. Cement Bon
shutter (Bison Panel or Equivalent) Single Leaf with all round styles U section of size 12m x 1
from 0.6 mm thick galvanized, colour coated cold rolled steel profiles with 16mm thick Cement Bon
(Bison Panel or Equivalent) with necessary screws fixed at every 1-0 (304.8mm) intervals. The co
nickel coated Aldrop of size 250mm long 2nos. 200mm long tower bolt 1no., 125mm handles 2nos.,
cost and conveyance of all materils at site and applying one coat of primer, one coat of luppum and
sythetic enamel paint as per approved design for finished item of work
Rate as per SSR Item No.673/48 BMT-N.31 1 Sqm 2558.00
over heads & contractors profit 14%
Total
Rate per 1 Sqm
75 BMT-F.30
Supplying & fixing collapsible steel shutters with vertical, double channel of 20 x10x2 mm of 100 m
with flat iron 40x40x6 mm with 38 mm dia steel pulleys, the top, bottom and side vertical frames
gate with 65x65mmx8mm MS Angle and middle guide rail at site height with 65mmx8mm MS flat
guide and fixed with necessary hold fasts, bolts, nuts, rivets, locking arrangements, stop
accessories all fixtures and painted with one coat of approved steel primer etc., complete for finish
per special spn 1105.
BMT-P.44
ELIXIR SUPER SERIES OR EQUIVALENT PRE-PAINTED STEEL WINDOWS / VENTILATORS Su
Ventilators : Top hung 4-0 X 2-0 (1219.2 x 609.6mm) outer frame section size of 46 X 52 mm
section size of 46 X 46mm and mullion section size of 46 x70 mm
Supply and fixing of pre-painted steel windows & top hung and fixed louvered ventilators made of
(base steel as per IS 513 of -0.6 mm thick 'D" quality, galvanized as per IS 277 with zinc of 120 G
with epoxy primer of 5-7 microns thick, finish painted with a polyester paint of 12-16 microns thic
with 5-7 microns thick alkyd backer, section for outer frame of 46 x 52 mm section and for shutter o
46 x 46 mm section for mullion 46 x 70 mm, and section for beading should be 18 x 25 mm and s
ventilation of 33 x57mm Box section and the windows panelled with 5 mm thick plain float glas
glass for ventilators with Ethyl propylene Diamine monomer Gasket (EPDM) and the sections c
joined with corner brocket centre mullions fixed using mullion cap and with handle made of hig
powder coated and nylon receiver, corner brackets made of CRCA with Zinc Phosphate, Mullion c
filled nylon, frames fixed to the concrete /masonry wall by means of self expanding screws includ
guard bars with 6" pitch complete for finished item of work.
77 BMS-W.16
Supply, delivery and fixing of 40mm thick Cement Jali of size 0.90x0.45 m or suitable size for Ventila
labour charges etc., complete
Cost of 50 mm thick Cement Jali -SSR Item No.876, 1 Sqm 274.00
Pg 70 - BMS-W.16
over heads & contractors profit 14%
Total
Rate per 1 Sqm
Unit : 1.0 MT
(a) Material
HYSD bars including 5 per cent for overlaps and 1.05 Ton 30246.02
wastage
Binding wire- 6.00 kg 70.00
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Blacksmith / Bar bender 10.00 Day 437.50
Mazdoor (Unskilled) 10.00 Day 350.00
Sub Total
Over heads & Contractors profit 14%
Total per MT
Rate per Kg
(c ) Extra for Supply, fixing of Corrugated , Serrated adjustable ridges and hips including necessary fas
keeping
Output : in position
20.20 Rm etc. complete
Corrugated, Serrated Ridges/Hips 21.50 Rm 174.00
Conveyance & Sundries LS
Carpenter 1st Class 0.14 day 437.50
Carpenter 2nd Class 0.55 day 400.00
Mazdoor 1.64 day 350.00
Sub Total
Total Cost per 20.20 Rm
Rate per RM
(b) Extra for Providing Wind Ties over Non Asbestos HIPP reincorced cement Corrugated Sheets
Output: 30 Rm
Cost of 40x6 mm MS Flat including Wastage 59.50 Kg 35.00
Carpenter 1st class 0.50 day 437.50
Man Mazdoor 0.50 day 350.00
Conveyance & Sundreis LS
Sub Total
Over heads & Contractors profit 14%
Total Rate for 30 Rm
Rate per RM
(c ) Extra for Supply, fixing of Non Asbestos High Impact Poly Propylene reinforced cement Corrugated
adjustable ridges
Output : 20.20 Rmand hips including necessary fasteners and keeping in position etc. complete
Non Asbestos HIPP Corrugated, Serrated 21.50 Rm 238.00
adjustable Ridges/Hips
Conveyance & Sundries LS
Carpenter 1st Class 0.14 day 437.50
Carpenter 2nd Class 0.55 day 400.00
Mazdoor 1.64 day 350.00
Sub Total
Total Cost per 20.20 Rm
Rate per Rm
Scaffolding charges 1%
Sub Total
Over heads & Contractors profit 14%
Total
Rate per 1 sqm
Unit: 1 Sq.m
A) Material requirement
1219x1829 mm Gyp Boards 1.03 sqm 232.00
GI Ceiling angle 25x10x0.55mm 0.64 RM 69.00
GI Ceiling Section 51.5x26x10.5x0.55 mm 0.84 RM 79.00
Intermediate Channel 45x15x15x0.9mm 0.84 RM 78.00
Perimeter Channel:20x27x30x0.55mm 0.40 RM 69.00
Connecting Clips 1.84 Nos 2.00
Rawl Plugs 0.64 Nos 2.00
Drywall screws-25mm 18.00 Nos 2.00
Jointing paper tape 1.46 RM 5.00
Drywall top coat 0.15 Lit 133.00
B) LABOUR CHARGES
1st Class Carpenter 0.12 day 672.00
2nd Class Carpenter 0.12 day 567.00
1st Class Painter 0.024 day 672.00
2nd Class Painter 0.024 day 567.00
Power Saw - Hand Operated - Operator 0.012 day 623.00
Power Drill - Hand Operated - Operator 0.024 day 721.00
Unskilled Mazdoor 0.072 day 350.00
C) Machinery
Power Saw - Hand Operated - Hire charges 0.32 Hrs 117.00
Power Drill - Hand Operated - Hire Charges 0.64 Hrs 108.00
Scaffolding charges 1%
Sub Total
Over heads & Contractors profit 14%
Total
Rate per 1 sqm
89 Gypboard Fine Line Grid False Ceiling-12.5 mm thick
Supplying and Fixing Gyp Board Fine Line Grid False Ceiling (GS_FLC-4.6 as per India Gypsum) in
using 12.5mm thick Gyp Board sheet tiles of 595 x 595 mm or 595x 1195 mm conforming ti IS-2095 a
steel precoated GI wall angle of size 25x25x0.7 mm thick along perimeter of and ceiling screws fixe
Brickwork/partition at 610 mm c/c and suspending the frame work using pre coated GI Tee section (
from soffit at 1220 mm c/c fixed with GI Soffit cleat, rawl plugs and steel expansion fasteners and c
the GI T-Section with 4mm dia GI Rod with Galvanized spring steel level clip of PVC universal holdin
1200 mm c/c and fixing the 12.5 mm Gypboard sheet tiles of size 595x595 or 595x1195 mm and finis
coats of drywall topcoat complete for finished item of work as per India Gypsum Ltd. specification
Unit: 1 Sq.m
A) Material requirement
12.5mm thick Gyp Board Tiles 1.00 sqm 249.00
GI Precoated angle 25x25x0.7 mm 0.40 RM 38.00
GI Precoated T-Section 24x38x0.7 mm 3.20 RM 50.00
GI Rod-4mm dia connecting Road 1.28 RM 11.00
Rawl Plugs 1.28 Nos 2.00
Soffit Cleats 1.28 Nos 2.00
Universal Holding Clips 5.36 Nos 2.00
Drywall Top Coat 0.15 Lit 133.00
B) LABOUR CHARGES
1st Class Carpenter 0.12 day 672.00
2nd Class Carpenter 0.12 day 567.00
1st Class Painter 0.024 day 672.00
2nd Class Painter 0.024 day 567.00
Power Saw - Hand Operated - Operator 0.012 day 623.00
Power Drill - Hand Operated - Operator 0.012 day 721.00
Unskilled Mazdoor 0.072 day 350.00
C) Machinery
Power Saw- Hand Operated - Hire charges 0.32 Hrs 117.00
Power Drill - Hand Operated - Hire Charges 0.32 Hrs 108.00
Scaffolding charges 1%
Sub Total
Over heads & Contractors profit 14%
Total
Rate per 1 sqm
90 Supply, Delivery, fabrication and fixing in position of MS Purlines including cost and conveyance of
fixing in position etc. complete
(a) For 25 mm NB-Medilum Class
Wt. of 25 mm NB Medium Class 1 Rmt 2.41
Add wastage @ 5% 0.12
Total weight 2.53
Cost of Mild Steel Tubes & pipes of all diameters as 2.53 Kg 57.00
per IS-1161-BMT-F.04-Sl No-130 and Pg 17
Fbarication Charges including fixing in position 2.53 Kg 33.60
Sub Total
Over heads & Contractors profit 14%
Total per Rm
Rate per RM
91 IRR-CCDW1-8 :
Providing and fixing 2.50 m long cold twisted deformed steel Anchor rods with 1.50m length dr
drilled in bed rock and remaining length embedded in concrete/ masonry including cost of all ma
labour, drilling and cleaning hole, driving Anchore rod, grouting hole with thick cement slurry etc,
to 50m and all lifts.
a Unit - 10 Nos
A) MATERIALS
25mm dia Steel (including 5% Wastage) 10 Nos 101.00 Kg 30.00
of 2.50m length
Drilling of 36mm dia holes by Pneumatic 15 RM 120.00
Compressor Sl No.143 Pg No. 19
Grouting 36mm dia holes with neat cement slurry Sl 15 RM 109.50
No.146 Pg No. 19
B) LABOUR CHARGES
Bar Bender 0.50 day 437.50
Mason 2nd class 0.50 day 567.00
Mazdoor (unskilled) 1.00 day 350.00
Sub Total
Over heads & Contractors profit 14%
Grand Total
Rate per 10 Nos.
Rate per Each 25mm Dia Anchoring
b Unit - 10 Nos
A) MATERIALS
20mm dia Steel (including 5% Wastage) 10 Nos of 65.00 Kg 30.00
2.50m length
Drilling of 25mm dia holes by Pneumatic 15 RM 105.00
Compressor Sl No.142 Pg No. 19
Grouting 25mm dia holes with neat cement slurry Sl 15 RM 89.00
No.145 Pg No. 19
B) LABOUR CHARGES
Bar Bender 0.50 day 437.50
Mason 2nd class 0.50 day 567.00
Mazdoor (unskilled) 1.00 day 350.00
Sub Total
Over heads & Contractors Profit 14%
Grand Total
Rate per 10 Nos.
Rate per Each 20mm Dia Anchoring
c Unit - 10 Nos
A) MATERIALS
16mm dia Steel (including 5% Wastage) 10 Nos of 41.50 Kg 30.00
2.50m length
Drilling of 20mm dia holes by Pneumatic 15 RM 110.00
Compressor Sl No.141 Pg No. 19
Grouting 20mm dia holes with neat cement slurry Sl 15 RM 71.00
No.144 Pg No. 19
B) LABOUR CHARGES
Bar Bender 0.50 day 437.50
Mason 2nd class 0.50 day 567.00
Mazdoor (unskilled) 1.00 day 350.00
Total
over heads & contractors profit 14%
Grand Total
Rate per 10 Nos
Rate per Each 20mm Dia Anchoring
Output: 100 RM
Materials:
Galvanised steel barbed wire IS type I weighing 15.500 Kg 77.00
0.155 kg/Rm : M-063
Carriage of barbed wire.
G.I. staples steel pins or binding wire @10% 10%
Labour :-
For fixing & stretching wire
Blacksmith, 1st Class 0.150 No 437.50
Blacksmith, 2nd Class 0.150 No 567.00
Mazdoor (male). 0.300 No 350.00
Sub Total
Over heads & Contractors profit 14%
Cost for 100 m of Fixing Barbed Wire
Rate per 1RM
Unit: 1 Rm
a) 15.90mm OD- SDR-13.50 (1/2" NB) 1 Rm 120.00
Add "MAA" @ 25% 58.00
Sub Total
OH&CP @ 14% 134.5
Total (1/2' NB) : Rate/Rm
a) 75 mm OD SWR Type"B"
Cost of 3.0m S/S Pipe 1 Rm 144.00
Add for Fittings Bends,Tees,Couplers etc 20% 144.00
Labour Charges for Fixing 1 Rm 58.00
MAA on labour 25% 58.00
Sub Total
OH&CP @ 14% 245.3
75mm OD,SWR"Type B", Rate/Rm
b) 90 mm OD SWR Type"B"
Cost of 3.0m S/S Pipe 1 Rm 232.00
Add for Fittings Bends,Tees,Couplers etc 20% 232.00
Labour Charges for Fixing 1 Rm 58.00
MAA on labour 25% 58.00
Sub Total
OH&CP @ 14% 350.9
90 mm OD,SWR"Type B", Rate/Rm
90 mm OD SWR Type"A"
Cost of 3.0m S/S Pipe 1 Rm 135.00
Add for Fittings Bends,Tees,Couplers etc 20% 135.00
Labour Charges for Fixing 1 Rm 58.00
MAA on labour 25% 58.00
Sub Total
OH&CP @ 14% 234.5
90 mm OD,SWR"Type A" Rate/Rm
1 day 24.50
1 day 323.40
1 day 155.75
1 day 122.50
1 Hour 1511.50
1 Hour 93.15
2230.80
312.31
2543.11
2543.11
Rs 2034.49
Cum
1 Each 0.00
1 Each 4076.80
1 hours 16929.00
21005.80
2940.81
23946.61
99.78
Rs 99.78
Cum
ons and depositing on bank for all lifts and
rges such as shoring, sheeting, planking,
luding dewatering charges etc as per SS -
1 Each 0.00
1 Each 3057.60
1 hours 16929.00
19986.60
2798.12
22784.72
126.58
Rs 126.58
Cum
1 Nos 0.00
1 Nos 151.90
21.27
173.17
28.86
Rs 28.86
Cum
1 Cum 4800.00
1 Nos 0.00
1 Nos 151.90
4951.90
693.27
5645.17
940.86
Rs 940.86
Cum
1.00 Kg 1217.13
1.00 Cum 1402.29
1.00 Cum 360.00
1.00 Kl 120.00
1.00 hour 303.10
1 Kg 717.00
1 Cum 1402.29
1 Cum 360.00
1 Kl 120.00
1 hour 303.10
1 Nos 72.10
1 Nos 681.10
Rs 3655.59
511.78
4167.37
Rs 4167.37
Cum
1 Cum 1418.49
1 Cum 360.00
1 Kg 1936.35
1 Each 95.89
1 Each 151.39
1 Each 1764.00
1 hour 503.90
1 hour 108.60
1 Kl 120.00
Rs 6458.62
Cum
1 Cum 6458.62
1 Cum 1441.00
1 Cum 260.00
65.00
8224.62
1151.45
9376.07
Rs 9376.07
Cum
1 Cum 6458.62
1 Cum 480.00
1 Cum 413.00
103.25
7454.87
1043.68
8498.55
Rs 8498.55
Cum
1 Cum 6458.62
1 Cum 730.00
1 Cum 626.00
156.50
7971.12
1115.96
9087.08
Rs 9087.08
Cum
1 Cum 6458.62
1 Cum 1064.00
1 Cum 626.00
156.50
Rs 8305.12
1162.72
9467.84
Rs 9467.84
Cum
4F 5F
6458.62 6458.62
1064.00 1064.00
814.00 876.00
203.50 219.00
8540.12 8617.62
1195.62 1206.47
9735.74 9824.09 Cum
1 Cum 6886.25
1 Sqm 1190.00
1 Sqm 700.00
175.00
Rs 8951.25
1253.18
10204.43
Rs 10204.43
Cum
4F 5F
6886.25 6886.25
1190.00 1190.00
910.00 980.00
227.50 245.00
9213.75 9301.25
1289.93 1302.18
10503.68 10603.43 Cum
d 75 mm th. at edge
1 Cum 339.08
1 Sqm 62.55
1 Sqm 36.90
9.23
Rs 447.75
62.69
510.44
Rs 510.44
Cum
& Centering
1 Cum 6458.62
1 Cum 703.00
1 Cum 532.00
133.00
Rs 7826.62
1095.73
8922.35
Rs 8922.35
Cum
1 Ton 45100.00
1 kg 210.00
1 Each 840.00
1 No 4625.00
1 No 4000.00
54775.00
7668.50
62443.50
Rs 62.44
Kg
1 sqm 212.80
1 cum 950.89
1 kg 200.00
1 sqm 3024.57
1 day 3500.00
1 day 400.00
1 day 3500.00
1 Hrs 606.20
Rs 12394.46
1735.22
14129.69
Rs 14129.69
Rs 1412.97
Sq.m
1 Kg 307.20
1 Cum 985.00
1 Cum 167.66
1 Cum 320.00
1 Nos 656.25
1 Nos 812.00
Rs 3248.11
454.74
3702.85
Rs 3702.85
Cum
1 Kg 192.00
1000 Nos 2200.72
1 Cum 160.00
1 Each 105.00
1 Each 224.00
1 Each 661.50
Rs 3543.22
496.05
4039.27
Rs 4039.27
Cum
4F 5F
3543.22 3543.22
23.01 23.01
308.85 370.62
77.21 92.66
3952.29 4029.50
553.32 564.13
4505.61 4593.63 Cum
1 Kg 316.00
1000 Nos 2428.52
1 Cum 220.00
1 Each 262.50
1 Each 240.00
1 Each 962.50
4429.52
44.30
4473.82
626.33
5100.15
Rs 5100.15
Cum
4F 5F
4473.82 4473.82
45.97 45.97
616.99 740.39
154.25 185.10
5291.03 5445.27
740.74 762.34
6031.77 6207.61 Cum
1 Kg 172.00
1 Cum 180.00
1 Kg 58.00
1 Cum 40.00
1 Nos 275.63
1 Nos 588.00
1 Nos 1365.00
Rs 2678.63
375.01
3053.63
Rs 305.36
Sq.m
4F 5F
267.86 267.86
0.53 0.53
7.10 8.52
1.78 2.13
277.27 279.04
38.82 39.07
316.08 318.11 Sq.m
1 Cum 659.33
1 Nos 411.25
1 Nos 640.00
1710.58
239.48
1950.06
Rs 195.01
Sq.m
4F 5F
171.06 171.06
0.53 0.53
7.10 8.52
1.78 2.13
180.46 182.24
25.26 25.51
205.73 207.75 Sq.m
1 Cum 570.53
1 Nos 262.50
1 Nos 384.00
Rs 1217.03
170.38
1387.42
Rs 138.74
Sq.m
4F 5F
121.70 121.70
1.24 1.24
14.01 16.81
3.50 4.20
140.46 143.96
19.66 20.15
160.12 164.11 Sq.m
422.62
1 Kg 137.70
1 Nos 157.50
1 Nos 336.00
Rs 1053.82
147.53
1201.35
Rs 120.14
Sq.m
1 Sq.m 95.00
13.3
Rs 108.30
Sq.m
10 sqm 7491.00
1 kg. 86.40
1 kg. 132.00
1 kg. 80.00
1 cum 120.00
1 day 1356.25
1 day 440.00
1 day 301.00
10006.65
100.07
10106.72
1414.94
11521.66
Rs 1152.17
Sq.m
1 sqm 4009.70
1 kg. 86.40
1 kg. 132.00
1 kg. 24.00
1 cum 120.00
1 cum 20.00
1 day 420.00
1 day 896.00
1 day 1155.00
6863.10
68.63
6931.73
970.44
7902.17
Rs 790.22
Sq.m
mm thick , M 40 gradeof which top 12 mm
ctive glazing set over base coat of cement
cluding near cement slurry of honey like
ll depth mixed with pigment of matching
complete, including seigniorage charges,
all materials.
1 Sq.m 4864.20
1 Kg 115.20
1 Kg 132.00
1 Kg 24.00
1 Kg 65.00
1 Cum 120.00
1 Day 420.00
1 Day 896.00
1 Day 1155.00
7791.40
77.91
7869.31
1101.70
8971.02
Rs 897.10
Sq.m
Flooring
set over base coat of CM (1:8) over already
consistency spread @ 3.3 kgs per sqm. &
ment, sand, and water and flooring stones
ing of flooring stones etc., complete for
1 Sqm 1844.29
1 Kg 86.40
1 Kg 132.00
80.00
1 Cum 120.00
1 Nos 1356.25
1 Nos 440.00
1 Nos 301.00
Rs 4359.94
610.39
4970.33
Rs 497.03
Sq.m
1 Cum 798.75
1 Kg 132.00
1 Nos 288.75
1 Nos 616.00
1 Nos 1295.00
Rs 3130.50
438.27
3568.77
Rs 356.88
Sq.m
= 2.25 Sqm
Rmt
15.60 Kg
Rmt
Rmt
Rmt 17.66 Kg
33.26 Kg
Kg 1172.28
Kg 1117.54
Nos 328.00
2617.82
366.49
Rs. 2984.31
Rs. 1326.36
Rs. 1326.36
Sq.m
1 Each 0.00
1 Each 1783.60
1783.60 1337.70
3121.30
436.98
3558.28
355.83
Rs 355.83
Cum
1 Day 9.80
1 Day 122.50
1 Day 122.50
1 Hour 1012.71
1 Hour 93.15
1360.66
190.49
1551.15
1551.15
Rs 1240.92
Cum
38.00
5.32
43.32
Rs 43.32
HP-Hr
m Hr 12.00
No Hr 6.00
18.00
Days 2.25
Rs 1102.50
Rs 367.50
m Hr 14.00
No Hr 12.00
26.00
Days 3.25
Rs 1592.50
Rs 455.00
Rs./Rm
m Hr 15.00
No Hr 8.00
23.00
Days 2.88
Rs 1408.75
Rs 469.58
Rs./Rm
m Hr 17.50
No Hr 16.00
33.50
Days 4.19
Rs 2051.88
Rs 586.25
Rs./Rm
m Hr 22.75
No Hr 24.00
m Hr 4.00
50.75
Days 6.34
Rs 3108.44
Rs 777.11
Rs./Rm
m Hr 29.75
No Hr 32.00
m Hr 10.50
72.25
Days 9.03
Rs 4425.31
Rs 983.40
Rs./Rm
m Hr 36.75
No Hr 44.00
m Hr 13.00
93.75
Days 11.72
Rs 5742.19
Rs 1276.04
Rs./Rm
870.10
174.02
1 Each 0.00
1 Each 2548.00
2548.00
1911.00
4459.00
624.26
5083.26
508.33
Rs 508.33
Cum
1 Each 0.00
1 Each 360.50
1 Each 180.25
1 Each 4091.50
1 hours 1285.40
1 Kg 2450.00
1 Nos. 168.70
8536.35
1195.09
9731.44
973.14
Rs 973.14
Cum
1 Nos 0.00
1 Nos 2548.00
1 hour 7712.40
10260.40
1436.46
11696.86
1169.69
Rs 1169.69
Cum
1.00 Kg 896.25
1.00 Cum 1402.29
1.00 Cum 360.00
1.00 Kl 120.00
1.00 hour 303.10
1 Kg 1825.70
1 Cum 1418.49
1 Cum 360.00
1 Kl 120.00
1 hour 303.10
1 Nos 72.10
1 Nos 681.10 For Design mix concrete, allow Cement as follows (for estimate purpose on
Rs 4780.49 Grade Kgs
669.27 M20 350
5449.76 M25 380
Rs 5449.76 M30 400
Cum M35 420
M40 430
1 Cum 1418.49
1 Cum 360.00
1 Kg 2102.32
1 Each 95.89
1 Each 153.26
1 Each 2041.20
1 hour 503.90
1 hour 108.60
1 Kl 120.00
Rs 6903.66
Cum
456 using WEIGH BATCHER / MIXER with
) from approved quarry including cost and
ggregate, water etc., to site and including
perational, incidental and labour charges
mplete but excluding cost of steel and its
mum cement content as per IS code for
1 Cum 1418.49
1 Cum 360.00
1 Kg 2212.97
1 Each 95.89
1 Each 0.00
1 Each 2066.40
1 hour 503.90
1 hour 108.60
1 Kl 120.00
Rs 6886.25
Cum
1 Cum 6903.66
1 Cum 49.00
1 Cum 260.00
65.00
7277.66
1018.87
8296.53
Rs 8296.53
Cum
1 Cum 6903.66
1 Cum 58.00
1 Cum 413.00
103.25
7477.91
1046.91
8524.82
Rs 8524.82
Cum
1 Cum 6903.66
1 Cum 827.00
1 Cum 626.00
156.50
8513.16
1191.84
9705.00
Rs 9705.00
Cum
1 Cum 6903.66
1 Cum 106.00
1 Cum 747.00
186.75
Rs 7943.41
1112.08
Rs 9055.49
Cum
4F 5F
6903.66 6903.66
106.00 106.00
971.00 1046.00
242.75 261.50
8223.41 8317.16
1151.28 1164.40
9374.69 9481.56 Cum
1 Cum 339.08
1 Sqm 62.55
1 Sqm 36.90
438.53
9.23
Rs 886.28
124.08
1010.36
Rs 1010.36
4F 5F
6458.62 6458.62
703.00 703.00
692.00 745.00
173.00 186.25
8026.62 8092.87
1123.73 1133.00
9150.35 9225.87 Cum
456 using WEIGH BATCHER / MIXER with
) from approved quarry including cost and
ggregate, water etc., to site and including
perational, incidental and labour charges
mplete but excluding cost of steel and its
mum cement content as per IS code from
ring, shuttering, laying concrete, vibrating,
for finished item of work. for RCC Domes,
sing Steel Scaffolding and Centering
g
1 Cum 6458.62
1 Cum 2281.00
1 Cum 1152.00
288.00
Rs 10179.62
1425.15
11604.77
Rs 11604.77
Cum
4F 5F
6458.62 6458.62
2281.00 2281.00
1498.00 1613.00
374.50 403.25
10612.12 10755.87
1485.70 1505.82
12097.82 12261.69 Cum
1 Cum 6458.62
1 Sqm 1586.27
1 Sqm 933.10
233.28
Rs 9211.26
1289.58
10500.84
Rs 10500.84
Cum
4F 5F
6458.62 6458.62
1586.27 1586.27
1213.03 1306.34
303.26 326.59
9561.18 9677.81
1338.56 1354.89
10899.74 11032.71 Cum
1 Cum 6886.25
1 Sqm 991.27
1 Sqm 583.10
145.78
Rs 8606.40
1204.90
9811.29
Rs 9811.29
Cum
4F 5F
6886.25 6886.25
991.27 991.27
758.03 816.34
189.51 204.09
8825.06 8897.95
1235.51 1245.71
10060.57 10143.66 Cum
1 Cum 6886.25
1 Sqm 952.00
1 Sqm 560.00
140.00
Rs 8538.25
1195.36
9733.61
Rs 9733.61
Cum
4F 5F
6886.25 6886.25
952.00 952.00
728.00 784.00
182.00 196.00
8748.25 8818.25
1224.76 1234.56
9973.01 10052.81 Cum
1 Cum 6886.25
1 Sqm 793.73
1 Sqm 466.90
116.73
Rs 8263.61
1156.90
9420.51
Rs 9420.51
Cum
4F 5F
6886.25 6886.25
793.73 793.73
606.97 653.66
151.74 163.42
8438.69 8497.06
1181.42 1189.59
9620.11 9686.64 Cum
1 Cum 6886.25
1 Sqm 708.04
1 Sqm 416.83
104.21
Rs 8115.33
1136.15
9251.47
Rs 9251.47
Cum
4F 5F
6886.25 6886.25
708.04 708.04
542.45 582.42
135.61 145.61
8272.35 8322.32
1158.13 1165.12
9430.48 9487.44 Cum
1 Cum 6886.25
1 Sqm 620.00
1 Sqm 365.00
91.25
Rs 7962.50
1114.75
9077.25
Rs 9077.25
Cum
4F 5F
6886.25 6886.25
620.00 620.00
475.00 510.00
118.75 127.50
8100.00 8143.75
1134.00 1140.13
9234.00 9283.88 Cum
1 Cum 6886.25
1 Sqm 550.56
1 Sqm 324.12
81.03
Rs 7841.96
1097.87
8939.84
Rs 8939.84
Cum
4F 5F
6886.25 6886.25
550.56 550.56
421.80 452.88
105.45 113.22
7964.06 8002.91
1114.97 1120.41
9079.03 9123.32
1 Cum 6886.25
1 Sqm 496.00
1 Sqm 292.00
73.00
Rs 7747.25
1084.61514
8831.87
Rs 8831.87
Cum
4F 5F
6886.25 6886.25
496.00 496.00
380.00 408.00
95.00 102.00
7857.25 7892.25
1100.02 1104.92
8957.27 8997.17 Cum
1 Cum 6886.25
1 Sqm 412.92
1 Sqm 243.09
60.77
Rs 7603.03
1064.42
8667.46
Rs 8667.46
Cum
4F 5F
6886.25 6886.25
412.92 412.92
316.35 339.66
79.09 84.92
7694.61 7723.75
1077.25 1081.32
8771.85 8805.07 Cum
1 Cum 339.08
1 Sqm 83.40
1 Sqm 49.20
12.30
Rs 483.98
67.76
551.73
Rs 551.73
Rm
4F 5F
339.08 339.08
83.40 83.40
64.20 69.00
16.05 17.25
502.73 508.73
70.38 71.22
573.11 579.95 per Rm
456 using WEIGH BATCHER / MIXER with
) from approved quarry including cost and
ggregate, water etc., to site and including
perational, incidental and labour charges
mplete but excluding cost of steel and its
mum cement content as per IS code from
ring, shuttering, laying concrete, vibrating,
for finished item of work. for RCC Domes,
sing Steel Scaffolding and Centering
1 Cum 6458.62
1 Cum 4111.00
1 Cum 1822.00
455.50
Rs 12847.12
1798.60
14645.72
Rs 14645.72
Cum
1 Cum 6458.62
1 Sqm 2865.95
1 Sqm 1479.63
369.91
Rs 11174.11
1564.37
12738.48
Rs 12738.48
Cum
1 Cum 6458.62
1 Sqm 2150.00
1 Sqm 1110.00
277.50
Rs 9996.12
1399.46
11395.58
Rs 11395.58
Cum
1 Cum 6458.62
1 Sqm 1790.95
1 Sqm 924.63
231.16
Rs 9405.36
1316.75
10722.11
Rs 10722.11
Cum
1 Cum 6458.62
1 Sqm 1720.00
1 Sqm 888.00
222.00
Rs 9288.62
1300.41
10589.03
Rs 10589.03
Cum
1 Cum 6458.62
1 Sqm 1434.05
1 Sqm 740.37
185.09
Rs 8818.13
1234.54
10052.67
Rs 10052.67
Cum
1 Cum 6458.62
1 Sqm 1227.65
1 Sqm 633.81
158.45
Rs 8478.53
1186.99
9665.53
Rs 9665.53
Cum
1 Cum 6458.62
1 Sqm 1075.00
1 Sqm 555.00
138.75
Rs 8227.37
1151.83
9379.20
Rs 9379.20
Cum
1 Cum 6458.62
1 Sqm 954.60
1 Sqm 492.84
123.21
Rs 8029.27
1124.10
9153.37
Rs 9153.37
Cum
1 Cum 6458.62
1 Sqm 860.00
1 Sqm 444.00
111.00
Rs 7873.62
1102.31
8975.93
Rs 8975.93
Cum
1 Cum 6458.62
1 Sqm 715.95
1 Sqm 369.63
92.41
Rs 7636.61
1069.12
8705.73
Rs 8705.73
Cum
ck
er-structure on ground floor in CM (1:6) of
als, seigniorage charges, labour , and all
ck)
1 Kg 96.00
1 No 2902.35
1 Cum 100.00
1 Each 262.50
1 Each 240.00
1 Each 962.50
4563.35
45.63
4608.99
645.26
5254.25
Rs 5254.25
Cum
4F 5F
4608.99 4608.99
35.28 35.28
473.57 568.28
118.39 142.07
5236.23 5354.63
733.07 749.65
5969.31 6104.28 Cum
1 Kg 288.00
1000 Nos 2200.72
1 Cum 160.00
1 Each 105.00
1 Each 224.00
1 Each 661.50
Rs 3639.22
509.49
4148.71
Rs 4148.71
Cum
4F 5F
3639.22 3639.22
23.01 23.01
308.85 370.62
77.21 92.66
4048.29 4125.50
566.76 577.57
4615.05 4703.07 Cum
1 Kg 212.00
1000 Nos 2428.52
1 Cum 220.00
1 Each 262.50
1 Each 240.00
1 Each 962.50
4325.52
43.26
4368.78
611.63
4980.41
Rs 4980.41
Cum
4F 5F
4368.78 4368.78
45.97 45.97
616.99 740.39
154.25 185.10
5185.99 5340.23
726.04 747.63
5912.02 6087.87 Cum
1 Kg 96.00
1 No 4577.87 1000000000 1771000 565
1 Cum 80.00 800.00 8120000 4060000 246
1000.00 123.15270936 9090909
1 Each 373.80 110 1.11957
1 Each 340.20 220
1 Each 1347.50
6815.37
68.15
6883.53
963.69
7847.22
Rs 7847.22
Cum
4F 5F
6883.53 6883.53
35.28 35.28
473.57 568.28
118.39 142.07
7510.77 7629.17
1051.51 1068.08
8562.28 8697.25 Cum
1 Kg 316.80
1 Cum 461.07
1 Cum 390.55
1 Cum 167.66
1 Cum 330.00
1 Nos 525.00
1 Nos 800.00
Rs 2991.08
418.75
Rs 3409.83
Cum
1 Cum 691.35
1 Nos 52.50
1 Nos 112.00
1 Nos 385.00
1 Nos 245.00
Rs 1485.85
208.02
Rs 1693.87
Cum
1 Cum 522.93
1 Nos 245.00
1 Nos 140.00
Rs 907.93
127.11
Rs 1035.04
Cum
1 Cum 342.32
1 Nos 210.00
1 Nos 448.00
1 Nos 175.00
1 Nos 630.00
Rs 1805.32
252.74
2058.07
Rs 205.81
Sq.m
uding cost and conveyance of all materials
ing and all operational, incidental, labour
omplete for finished item of work. CM
1 Cum 371.37
1 Nos 373.80
1 Nos 470.40
Rs 1215.57
170.18
1385.75
Rs 138.57
Sq.m
4F 5F
121.56 121.56
0.53 0.53
7.10 8.52
1.78 2.13
130.96 132.74
18.33 18.58
149.30 151.32 Sq.m
1 Cum 470.95
1 Nos 373.80
1 Nos 470.40
1315.15
184.12
1499.27
Rs 149.93
Sq.m
4F 5F
131.52 131.52
0.53 0.53
7.10 8.52
1.78 2.13
140.92 142.70
19.73 19.98
160.65 162.67 Sq.m
1 Cum 411.20
1 Nos 373.80
1 Nos 470.40
Rs 1255.40
175.76
1431.16
Rs 143.12
Sq.m
4F 5F
125.54 125.54
0.53 0.53
7.10 8.52
1.78 2.13
134.95 136.72
18.89 19.14
153.84 155.86 Sq.m
1 Kg 115.20
1 Cum 60.00
1 Nos 200.00
1 Nos 259.00
Rs 634.20
88.79
722.99
Rs 72.30
Sq.m
)Prop including cost & conveyance of all
plete for finished item of work
1 Kg 57.60
1 Cum 30.00
1 Nos 200.00
1 Nos 259.00
Rs 546.60
76.52
623.12
Rs 62.31
Sq.m
1 Kg 81.00
1 Nos 91.88
1 Nos 196.00
368.88
1.84
370.72
51.90
422.62
Rs 42.26
Sq.m
1 Kg 39.00
1 Nos 48.13
1 Nos 77.00
164.13
0.82
164.95
23.09
188.04
Rs 18.80
even shade after thoroughly brushing the
ng cost of all materials, labour charges and
item of work, but excluding conveyance
1 Kg 65.00
1 Nos 91.88
1 Nos 112.00
268.88
2.69
Rs 271.56
38.02
309.58
Rs 30.96
Sq.m
188.04
25 Kg 154.84
1 Nos 65.63
1 Nos 140.00
1 Nos 525.00
1073.50
10.74
1084.24
151.79
1236.03
Rs 123.60
Sq.m
188.04
25 Kg 88.48
1 Nos 39.38
1 Nos 84.00
1 Nos 525.00
924.89
9.25
934.14
130.78
1064.92
Rs 106.49
Sq.m
1 Sq.m 90.00
12.6
102.60
Sq.m
1 Sq.m 96.00
13.44
109.44
Sq.m
1 Ltr 94.50
1 Each 91.88
1 Each 196.00
382.38
3.82
Rs 386.20
54.07
440.27
Rs 44.03
Sq.m
1 Ltr 84.70
1 Each 91.88
1 Each 196.00
372.58
3.73
Rs 376.30
52.68
428.98
Rs 42.90
Sq.m
and Two Coats of Synthetic Enamel Paint
440.27
1 Ltr 644.00
1 Each 157.50
1 Each 336.00
1577.77
15.78
Rs 1593.54
223.10
1816.64
Rs 181.66
Sq.m
428.98
1 Ltr 552.00
1 Each 157.50
1 Each 336.00
1474.48
14.74
Rs 1489.23
208.49
1697.72
Rs 169.77
Sq.m
1 Litre 194.35
1 Litre 41.25
105.00
224.00
280.00
5.00
849.60
118.94
Rs 968.54
Sq.m
1 Litre 425.60
1 Litre 76.80
0.00
105.00
224.00
280.00
5.00
1116.40
156.30
Rs 1272.70
Sq.m
1 Lire 122.00
1 Day 91.88
1 Day 196.00
3.00
412.88
57.80
470.68
Rs 47.07
Sq.m
1 Lire 195.20
1 Day 157.50
1 Day 336.00
3.00
691.70
96.84
788.54
Rs 78.85
Sq.m
1 Lire 122.00
1 Day 65.63
1 Day 140.00
525.00
3.00
855.63
119.79
975.41
Rs 97.54
Sq.m
1 Lire 195.20
1 Day 91.88
1 Day 196.00
525.00
3.00
1011.08
141.55
1152.63
Rs 115.26
Sq.m
1 Kg 234.00
1 Day 119.44
1 Day 254.80
318.50
3.00
929.74
130.16
1059.90
Rs 105.99
Sq.m
1 Kg 234.00
1 Day 238.88
1 Day 509.60
637.00
1 Sq.m 359.90
3.00
1982.38
277.53
2259.91
Rs 225.99
Sq.m
1 cum 798.75
1 Kg 96.00
1 Nos 288.75
1 Nos 616.00
1 Nos 1295.00
Rs 3094.50
433.23
3527.73
Rs 352.77
Sq.m
1 Kg 86.40
1 Kg 38.40
1 Cum 120.00
1 Cum 20.00
1 Nos 420.00
1 Nos 896.00
1 Nos 1155.00
Rs 4112.35
575.73
4688.08
Rs 468.81
Sq.m
1 Sqm 1082.55
1 Kg 86.40
1 Kg 38.40
1 Cum 120.00
1 Cum 20.00
1 Nos 420.00
1 Nos 896.00
1 Nos 1155.00
Rs 3818.35
534.57
4352.92
Rs 435.29
Sq.m
Flooring
of size 0.25 *0.25 m set over base coat of
slurry of honey like consistency spread @
all materials like cement, sand, and water
harges for dressing of flooring stones etc.,
all materials.
1 Sqm 3689.81
1 Kg 86.40
1 Kg 132.00
80.00
1 Cum 120.00
1 Nos 1356.25
1 Nos 440.00
1 Nos 301.00
Rs 6205.46
868.76
7074.23
Rs 707.42
Sq.m
10 sqm 12372.50
1 kg. 86.40
1 kg. 132.00
1 kg. 24.00
1 cum 120.00
1 cum 20.00
1 day 420.00
1 day 896.00
1 day 1155.00
15225.90
152.26
15378.16
2152.94
17531.10
Rs 1753.11
Sq.m
1 Cum 268.06
1 Kg 480.00
1 Cum 85.00
1 Nos 546.88
1 Nos 24.00
1 Nos 1050.00
Rs 2453.94
24.54
2478.48
346.99
2825.47
Rs 282.55
Sq.m
1 sqm 34750.69
1 kg. 144.00
1 kg. 132.00
1 kg. 195.00
1 cum 200.00
1 day 1312.50
1 day 400.00
1 day 2800.00
39934.19
399.34
Rs 40333.53
5646.69
45980.23
Rs 4598.02
Sq.m
1 kg. 144.00
1 kg. 132.00
1 kg. 195.00
1 cum 200.00
1 day 1312.50
1 day 400.00
1 day 2800.00
35389.19
353.89
Rs 35743.08
5004.03
40747.11
Rs 4074.71
Sq.m
1 sqm 3970.00
1 cum 120.00
1 kgs 230.40
1 kgs 132.00
1 kgs 195.00
1 Nos 336.88
1 Nos 280.00
Rs 5264.28
737.00
6001.27
Rs 600.13
Sq.m
to 18 mm thick polished Shahabad stone
m thick with cement slurry of honey like
hite cement paste mixed with pigment of
bad stone, cement, sand and water etc.,
em of work, but excluding the cost of
10 sqm 1693.39
1 cum 120.00
1 kgs 230.40
1 kgs 132.00
1 Nos 420.00
1 Nos 896.00
1 Nos 1085.00
4576.79
45.77
Rs 4622.56
647.16
5269.72
Rs 526.97
Sq.m
1 sqm 11793.39
1 cum 120.00
1 kgs 230.40
1 kgs 132.00
1 kgs 162.50
1 day 380.63
1 day 812.00
1 day 1715.00
15345.91
153.46
15499.37
2169.91
17669.29
Rs 1766.93
Sq.m
1 Sqm 4514.70
1 cum 120.00
1 kg 230.40
1 kg 132.00
1 kg 195.00
0.00
1 day 336.88
1 day 280.00
5808.98
58.09
5867.06
821.39
6688.45
Rs 668.85
Sq.m
1 Sq.m 2673.30
1 Kg 115.20
1 Kg 132.00
1 Kg 24.00
1 Kg 65.00
1 Cum 120.00
1 Day 420.00
1 Day 896.00
1 Day 1155.00
5600.50
56.01
5656.51
791.91
6448.42
Rs 644.84
Sq.m
1 Sq.m 2512.50
1 Kg 115.20
1 Kg 132.00
1 Kg 24.00
1 Kg 65.00
1 Cum 120.00
1 Day 420.00
1 Day 896.00
1 Day 1155.00
5439.70
54.40
5494.10
769.17
6263.27
Rs 626.33
Sq.m
1 Day 420.00
1 Day 896.00
1 Day 1155.00
6491.00
6491.00
908.74
7399.74
Rs 739.97
Sq.m
1 Cum 4167.37
1 Sq.m 1387.42
1 Kg 1050.00
1 Day 144.38
1 Day 308.00
7057.17
988.00
8045.17
Rs 804.52
Sq.m
1 Cum 4371.72
1 Sq.m 1387.42
1 Kg 1050.00
1 Day 144.38
1 Day 308.00
7261.51
1016.61
8278.13
Rs 827.81
Sq.m
1 Cum 2724.88
1 Sq.m 1387.42
1 Kg 1050.00
1 Day 144.38
1 Day 308.00
5614.67
786.05
6400.73
Rs 640.07
Sqm
s
CRCA laths, interlocked together through
on specially designed
1 pipe shaft of2000.00
Sqm 50mm
els, stoppers, bottom locking plates and
280.00
cluding cost of hood cover and springs
earings, all accessories etcRscomplete
2280.00
for
Sq.m
Rm 250.00 1500.00
Sq.m 771.00 1696.20
#REF!
#REF!
Rs. #REF!
Sq.m
k Flush Shutters
m with designer Grill prefixed and 25 mm
ers, butt hinges, Tower bolts, Handles and
oved by Dept. before Delivery)
Sq.m
1 Sqm 4240.00
593.60
4833.60
Rs 4833.60
Sq.m
1 Sqm 5719.00
800.66
6519.66
Rs 6519.66
Sq.m
abricated from Roll formed sections made
3 D quality, galvanized as per IS 277 with
at with epoxy primer of 5-7 microns thick,
ated with Alkyd backer of 5-7 microns or
ion for external frame bottom should be of
or top and bottom should be of 69x26mm
s should be panelled with 5mm thick plain
led nylon. Gaskets are to be made of Ethyl
joined and assembled by means of corner
343.00
2793.00
Rs 2793.00
Sq.m
nded Particle Board as per IS 14276 (Bison
d roll formed sections made of galvanized
ctions with total coated thickness of 1mm,
with polyester paint of 12-16 microns. The
m3. Overall size of frame section should be
d screws. Cement Bonded particle board
section of size 12m x 18m x 12mm made
16mm thick Cement Bonded particle Board
4.8mm) intervals. The cost inclusive of MS
, 125mm handles 2nos.,
1 Sqm 2558.00
358.12
2916.12
Rs 2916.12
Sq.m
1 Sqm 2187.00
306.18
2493.18
Rs 1995.00
Sq.m
1 Sqm 4992.00
698.88
5690.88
Rs 5690.88
Sq.m
cle boards and Pre-Painted Steel Sections
el color coated sections (Base steel as per IS-
ated thickness of 0.58mm primer coated with
crons and back coated with alkyd backer of 5-
orm of 40 kg/Cum) of 60mm x 50mm, with
mm x 25 mm and another section of size 60
to length and miter jointed with plastic corner
e mullion section fixed to the frame with plastic
k CRCA electroplated provided to fix window
minated cement bonded particle board and 5
of 10 mm square rods duly welded at 150 mm
means of self expansion nylon Cap (75) and
oated fittings, A) 75mm long grip handles 1 no
ivot hinges 2 nos per shutter, D) MS Powder
1 Sqm 3413.00
477.82
3890.82
Rs 3890.82
Sq.m
1 Sqm 3838.00
537.32
4375.32
Rs 4375.32
Sq.m
1 Sqm 4226.00
591.64
4817.64
Rs 4817.64
Sq.m
1 Sqm 3900.00
546.00
4446.00
Rs 4446.00
Sq.m
1 Sqm 274.00
38.36
312.36
Rs 312.36
Sq.m
1 Ton 31758.32
1 kg 420.00
1 day 4375.00
1 Day 3500.00
40053.32
5607.46
45660.79
Rs. 45.66
Kg
1 Kg 7059.26
1 nos 239.57
1 nos 395.08
1 nos 27.54
1 nos 27.54
1 litre 24.00
1 litre 46.75
1 day 336.04
1 day 318.70
0.00
1 day 26.80
1 day 21.44
0.00
1 day 59.99
1 day 47.99
Rs 8630.70
1208.30
9839.00
Rs 983.90
Rs 983.90
Sq.m
& nuts 8 mm dia with bitumen & G.I limpet
and two coats of approved paint on over
turnover tax etc., complete, excluding the
1 Kg 5772.44
1 nos 239.57
1 nos 395.08
1 nos 27.54
1 nos 27.54
1 litre 24.00
1 litre 46.75
1 day 336.04
1 day 318.70
0.00
1 day 26.80
1 day 21.44
0.00
1 day 59.99
1 day 47.99
Rs 7343.89
1028.14
8372.03
Rs 837.20
Rs 837.20
Sq.m
1 Kg 4676.83
1 nos 239.57
1 nos 395.12
1 nos 27.54
1 nos 27.54
1 litre 24.00
1 litre 46.75
1 day 336.04
1 day 318.70
0.00
1 day 26.80
1 day 21.44
0.00
1 day 59.99
1 day 47.99
Rs 6248.32
874.76
7123.08
Rs 712.31
Rs 712.31
Sq.m
1 nos 110.13
1 nos 22.03
1 nos 6.61
1 day 172.88
1 day 189.17
Rs 2881.32
403.39
3284.71
Rs 328.47
Rs 328.47
Sq.m
1.00 Kg 2082.50
1.00 day 218.75
1.00 day 175.00
20.00
2496.25
349.48
2845.73
94.86
RM
including necessary fasteners and
1.00 Rm 3741.00
10.00
61.25
220.00
574.00
4606.25
4606.25
228.03
RM
1 nos 198.24
1 nos 22.03
1 nos 6.61
1 day 172.88
1 day 189.17
Rs 3291.43
460.80
3752.23
Rs 375.22
Rs 375.22
Sq.m
Corrugated Sheets
1.00 Kg 2082.50
1.00 day 218.75
1.00 day 175.00
20.00
2496.25
349.48
2845.73
94.86
RM
rced cement Corrugated , Serrated
osition etc. complete
1.00 Rm 5117.00
10.00
61.25
220.00
574.00
5982.25
5982.25
296.15
RM
1 Sqm 3355.00
1 nos 198.24
1 nos 22.03
1 nos 6.61
1 day 172.88
1 day 189.17
Rs 3943.93
552.15
4496.08
Rs 449.61
Rs 449.61
Sq.m
ck)
0.50 mm thick, 550 MPa, Top and Bottom
m dia, G.I plain washers complete or with
nce charges etc., complete for finished
ing structure
1 Sqm 4899.00
1 nos 198.24
1 nos 22.03
1 nos 6.61
1 day 172.88
1 day 189.17
Rs 5487.93
768.31
6256.24
Rs 625.62
Rs 625.62
Sq.m
600 mm x 600 mm using 19 mm thick
4.0 mm x 2.4 mm in grid with cross tee of
of size 24 x 24 mm fixed to periphery of the
ns using 2.0 mm thick GI Wire for finished
bour charges such as1 cutting
sqm, fixing 43.00
of of
1 RM 9.60
1 RM 102.40
1 RM 11.52
1 Nos 2.56
1 day 72.58
1 day 61.24
1 day 12.46
1 day 28.84
1 day 70.00
1 Hrs 18.72
1 Hrs 34.56
467.47
4.67
472.15
66.10
538.25
Rs 538.25
Sq.m
1 day 268.80
1 day 226.80
1 day 53.76
1 day 45.36
1 day 24.92
1 day 28.84
1 day 84.00
1 Hrs 37.44
1 Hrs 34.56
1374.95
13.75
1388.70
194.42
1583.12
Rs 1583.12
Sq.m
1 sqm 238.96
1 RM 66.36
1 RM 27.60
1 RM 1.28
1 RM 7.28
1 Nos 19.95
1 day 80.64
1 day 68.04
1 day 16.13
1 day 13.61
1 day 7.48
1 day 17.30
1 day 25.20
1 Hrs 37.44
1 Hrs 69.12
696.39
6.96
703.35
98.47
801.82
Rs 801.82
Sq.m
1 sqm 249.00
1 RM 160.00
1 RM 2.56
1 RM 10.72
1 day 80.64
1 day 68.04
1 day 16.13
1 day 13.61
1 day 7.48
1 day 8.65
1 day 25.20
1 Hrs 37.44
1 Hrs 34.56
714.02
7.14
721.16
100.96
822.13
Rs 822.13
Sq.m
cost and conveyance of all material and
1 Kg 144.24
1 Kg 85.02
229.26
32.10
261.36
261.36
RM
1 Kg 185.54
1 Kg 109.37
294.90
41.29
336.19
336.19
RM
1 Kg 213.07
1 Kg 125.60
338.66
47.41
386.08
386.08
RM
1 Kg 301.05
1 Kg 177.46
478.50
66.99
545.49
545.49
RM
1 Kg 384.24
1 Kg 226.50
610.73
85.50
696.24
696.24
RM
25 96.25
625 101.0625
1 Kg 3030.00 3.85
1 RM 1800.00
1 Nos 1642.50
1 day 218.75
1 day 283.50
1 day 350.00
Rs 7324.75
1025.47
8350.22
Rs 8350.22
Rs 835.02
Each
1 Kg 1950.00
1 RM 1575.00
1 RM 1335.00
1 day 218.75
1 day 283.50
1 day 350.00
Rs 5712.25
799.72
6511.97
Rs 6511.97
Rs 651.20
Each
1 Kg 1245.00
1 RM 1650.00
1 RM 1065.00
1 day 218.75
1 day 283.50
1 day 350.00
Rs 4812.25
673.72
5485.97
Rs 5485.97
Rs 548.60
Each
1 Rmt 1193.50
119.35
1 No 65.63
1 No 85.05
1 No 105.00
1568.53
219.59
1788.12
Rs 17.88
RM
lines including Fittings for Water Supply
refilling etc. complete as directed by Dept.
1 Rm 120
1 Rm 14.5
134.5
18.83
153.33
Rm
1 Rm 135
1 Rm 14.5
149.5
20.93
170.43
Rm
1 Rm 180
1 Rm 14.5
194.5
27.23
221.73
Rm
1 Rm 245
1 Rm 14.5
259.5
36.33
295.83
Rm
1 Rm 305
1 Rm 14.5
319.5
44.73
364.23
Rm
1 Rm 445
1 Rm 14.5
459.5
64.33
523.83
Rm
ttings like Bends, Tees, Couplers, Raised
1 Rm 144.00
28.80
1 Rm 58.00
14.50
245.30
34.34
279.64
Rm
1 Rm 232.00
46.40
1 Rm 58.00
14.50
350.90
49.13
400.03
Rm
1 Rm 276.00
55.20
1 Rm 58.00
14.50
403.70
56.52
460.22
Rm
1 Rm 85.00
17.00
1 Rm 58.00
14.50
174.50
24.43
198.93
Rm
1 Rm 135.00
27.00
1 Rm 58.00
14.50
234.50
32.83
267.33
Rm
1 Rm 161.33
32.27
1 Rm 58.00
14.50
266.10
37.25
303.35
Rm
ollows (for estimate purpose only) :
87.7192982456
87.72
12.2808
DETAILED ESTIMATE OF THE FLAT NO.11(a&b) BELONGS TO SMT. K. AR
PEARL DROP ENCLAVE', H.NO.3-6-98, BOOSAREDDYGUDA, WEST MARRE
CONTONMENT.
ABSTRACT ESTIMATE
5 RCC- M 20 Grade:
BLD-CSTN-3-13-(30) - A
Supply and placing of the M-20 Design Mix Concrete
corresponding to IS 456 using WEIGH BATCHER /
MIXER with 20mm size graded machine crushed hard
granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water
etc., to site and including Seigniorage charges, sales &
other taxes on all materials including all operational,
incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402)with minimum
cement content as per IS code for Structural
Components.
b. Columns 1.00
Under Ground Level
C1 11.00 0.23 0.45
Above Ground Level up to Stilt Beam
C1 11.00 0.23 0.45
First Floor
C1 11.00 0.23 0.45
Second Floor
C1 11.00 0.23 0.45
e. Roof 1.00
Stilt Floor Roof Slab 1.00 6.55 11.43
First Floor Roof Slab 1.00 6.55 11.43
Second Floor Roof Slab 1.00 6.55 11.43
Passage Slab 3.00 6.55 1.22
Head Room Slab 1.00 4.57 1.22
Over Head Tank 1.00 6.10 1.52
Water Sump 1.00 7.32 1.83
b R.C.C.Lintels:
RCC M20 for Lintels up to 3.66m un-supported height
above GL-Steel Scaffolding & Centering.
R.C.C.Lintels for Each DU: 1.00
Door Openings
MD: 2.00 1.22 0.23
D1: 10.00 1.06 0.12
D2: 4.00 0.91 0.12
Windows Openings
W1: 10.00 1.80 0.23
W2k: 2.00 1.50 0.23
V1: 4.00 1.10 0.23
1.00
Basement 1.00
North-South Walls 2.00 6.55 0.6
East-West Walls 2.00 11.43 0.6
10 Plastering in CM(1:6) & CM(1:4) Base & Top Coats, 20mm th (16 & 4 mm) (External)
BLD-CSTN-8-9-(84)
Plastering 20mm thick two coats with base coat of
16mm thick in C.M. (1:6) and top coat of 4mm thick in
C.M. (1:3) with dubara sponge finishing including cost &
conveyance of all materials like cement, Sand, Water,
etc., to site, seigniorage charges, all operational,
including charges, labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing, including
cutting grooves where ever necessary etc., complete for
finished item of work of uneven surfaces of walls.
(External walls)
B. Skirting:
Skirting-15/18 mm Marble Tiles: 1.00
Skirting: (First & Second Floors)
Hall 2.00 3.20 2.90
M. Bed Room 2.00 3.35 3.35
Bed Rooms 2.00 6.40 1.22
Dinning 2.00 3.35 3.35
Utility 4.00 3.20 2.90
Kitchen 2.00 2.44 2.13
Passage 2.00 2.44 0.91
Doors: 1.00
MD: 2.00 1.05 2.13
D1 10.00 1.05 1.95
D2: 4.00 0.75 1.95
Windows: 1.00
W1 10.00 1.50 1.35
W2k 2.00 1.20 0.90
V1 4.00 0.90 0.45
14 M.S. GRILL:
Supplying and fixing of MS Grill for windows using
35x35x5 mm MS angle alround and 10mm MS square
bars horizontally at 125mm centre to centre and
vertically at 30cm centre to centre including fixing with 4
Nos of MS Z holdfasts (2 on each side) duly making
cutting brick masonry, fixing and making to original
surface neatly and painting grill with one coat of red
oxide primer including and conveyance of all
materials ,cutting, bending, welding including all
operational charges and all labour charges etc.,
complete for finished item of work.
ESTIMATE
Height in Rate in
RMt. Quantity Unit Rs. Amount in Rs.
100.03 Cum
49.50 Cum
2.00 49.50 Cum
50.53 Cum
1.65 44.51 Cum
1.80 6.02 Cum
ans):
SOIL:
t:
Rs. 2,376,344.74
Rs 190,107.58
Rs 142,580.68
2,709,033.01
Area of
the
1624.00 Roof 1,668.12
812
Page 247 of 613
RATE ANALYSIS FOR THE ITEMS OF CIVIL CONSTRUCTION TO THE DUPLEX HOUSES AND
APARTMENT BLOCKS IN 'SARASWATI PEARL DROP ENCLAVE', H.NO.3-6-98, BOOSAREDDYGUDA,
WEST MARREDPALLY, SECUNDERABAD CONTONMENT.
Buildings Data
EARTH WORK EXCAVATION
Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead of 50m including all
operational, incidental, labour charges such as shoring, sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS - 20 B (APSS 308).
a)Labour
Mate 0 Nos. 1 Each 0.00
Mazdoor (Unskilled) (excluding AA ) 3.64 Nos. 350.00 1 Each 1274.00
Extra for foundations @ 75% 1274.00 955.50
Sub total 2229.50
c&d) Overheads & Contractors Profit 14% 312.13
Cost for 10 cum = a+b+c+d 2541.63
Rate per cum = (a+b+c+d)/10 254.16
Rate per 1 Cum excluding Dewatering Rs 254.16
Cum
1 BLD-CSTN-2-2(10)
Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead of 50m including all
operational, incidental, labour charges such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS - 20 B (APSS 308).
1 BLD-CSTN-2-5 - (13)
Earth work excavation in Ordinary Rock (not required blasting) for foundations and depositing on bank for all lifts and
with an initial lead of 50m including all operational, incidental, labour charges such as shoring, sheeting, planking,
strutting, etc. complete for finished item of work including seigniorage excluding dewatering charges etc as per SS -
20 B (APSS 308).
Buildings
Page 248 of 613
Buildings
Page 249 of 613
3 BLD-CSTN-2-8 (16)
Filling with Sand in trenches, sides of foundations and basement with initial lead in layers not exceeding 15 cm thick,
consolidating each deposited layer by watering and ramming including cost and conveyance of water to work site
and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work. (APSS
NO. 309 & 310)
4 Plain Cement concrete M 5 (1:5:10) Grade using 40mm size Hard Granite Machine Crushed Metal including cost and
conveyance of all materials like cement, sand, coarse aggregate water etc., to site , seigniorage charges on all
materials, labour charges , for mixing , laying, concrete , ramming in 15 cm layers, finishing top surface to the
required level curing etc., complete for finished item of work.for foundation and under flooring bed.
Buildings
Page 250 of 613
5 RCC- M 20 Grade
BLD-CSTN-3-13-(30) - A
Supply and placing of the M-20 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER / MIXER with
20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)with minimum cement content as per IS code for
Structural Components
Buildings
Page 251 of 613
Buildings
Page 252 of 613
5 Dismatling RCC & Carting away with a lead of 1 km (By Mechanical Means)
Dismantlling & clearing away the RCC & carting the excavated material from the site within 1.0 km distance to a
suitable site including loading, unloading, conveyance charges & dumping the carted materialat including all labour
charges, all leads, lifts and other incidental & operational charges etc.,complete(as per MoST 2.4(ii))
6 Carting away Surplus excavated earth or other unusable material from work site within a lead of 2 Km to a suitable
place including loading , unloading charges etc. complete. Loading by Manual Means & Unloading by Mechanical
Means
Unit : Cum (Lead 2 Km)
Lead Charges 1.00 Cum 44.10 1.00 Cum 44.10
Loading Charges (Manual) 1.00 Cum 111.00 1.00 Cum 111.00
Unloading (Mechanical) 1.00 Cum 15.90 15.90
Add "MAA" on Labour 25% 18.90 4.73
Total Rate per Cum 175.73
Cu.m
7 Carting away Surplus excavated earth or other unusable material from work site within a lead of 5 Km to a suitable
place including loading , unloading charges etc. complete. Loading by Manual Means & Unloading by Mechanical
Means
8 Bailing out water from the pipe line trenches with oil engine driven pump sets, including hire charges, fuel charges
and wages for Driver and Helper etc, complete,
Oil Engine Driven Pumpset Basic Rate Item.27(a) 1.00 Hp-Hr 38.00 1.00 Hp-Hr 38.00
PHSSR
Sub Total 38.00
Overheads & Contractors Profit 14% 5.32
Total 43.32
Rate per 1HP-Hr Rs 43.32
HP-Hr
Buildings
Page 253 of 613
Buildings
Page 254 of 613
Unit: Each
Earthe Work Excavation for Service
Connection trench: 1.2*1.2*1.2 1.73 Cum 355.83 1.00 cum 615.58
Cost of MS Clamp with Welded Coupling to suit 1.00 Each 400.00 1.00 Each 400.00
110mmOD (LR) incl Rubber Packing
12 mm GM Ferrule ISI 1.00 Nos 375.00 1.00 Each 375.00
12 mm GI Bends 2.00 Nos 32.00 1.00 Each 64.00
12mm GI Couplings 2.00 Nos 18.00 1.00 Each 36.00
12mm GI Unions 2.00 Nos 53.00 1.00 Each 106.00
20mm OD PE100 -PN 16.0 Pipe 6.00 RM 21.12 1.00 RM 126.72
Drilling & Tapping the WS main (12mm) 1.00 Each 106.85 1.00 Each 106.85
Labour Charges for Laying,Jointing& Testing the 6.00 RM 25.65 1.00 RM 153.90
HSC
Refilling the Pipe Line Trench 1.73 Cum 20.62 1.00 Cum 35.66
Sub Total 1404.14
Overheads & Contractors Profit 14% 1404.14 196.58
Total Cost for 12mm dia HSC (Each) 1600.72
Each
11 Barricading, hoarding, lighting and watching etc., for water supply and sewerage works for trenches of depths upto
2.0 m below G.L (As per PH Data)
Taking output 3 Rmt
Material
Bamboos of 1 dia 2.5 M long (5 ft c/c = 3 x 2.5) 7.50 Rmt 47.08 1.00 Rmt 353.13
Baboom of 1 dia 3.66 M long (5 ft c/c = 3x 3.66) 10.98 Rmt 47.08 1.00 Rmt 516.98
(a) Usage of Material 5 times. Thus Cost of Material 0.20 870.10 174.02
taken as 20%
(b) Labour
Man mazdoor day 0.50 350.00 1.00 Day 175.00
349.02
(c) Sundries for Coir rope, nails, @ 1% 1% 349.02 3.49
(d) Sundries for lighting and watching etc at 1% 1% 349.02 3.49
Sub Total 356.00
e)Overheads & Contractors Profit 14% 356.00 49.84
Cost for 3rmt (a+b+c+d+e) 405.84
Rate per each rmt = (a+b+c+d+e)/3 135.28
Rmt
Buildings
Page 255 of 613
BLD-CSTN-2-6 - (14)
Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead of 50m including all
operational, incidental, labour charges such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS - 20 B (APSS 308).
a)Labour
Mate 0 Nos. 0.00 1 Each 0.00
Driller 0.50 Nos. 721.00 1 Each 360.50
Blaster 0.25 Nos. 721.00 1 Each 180.25
Mazdoor (Unskilled) 8.35 Nos. 350.00 1 Each 2922.50
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack 1 hours 1285.40 1 hours 1285.40
hammers sl.5 &39/325
c) Materials
Gelatine 80 per cent -M-104/ Pg.246 3.50 Kg 700.00 1 Kg 2450.00
Electric Detonators @ 1 detonator for 2 gelatine 14 Nos. 12.05 1 Nos. 168.70
sticks of 285 gm each - Sl No.165, Pg No.21of R&B
SSR
Sub total 7367.35
d) Overheads & Contractors Profit 14% 1031.43
Total 8398.78
Cost for 10 cum = a+b+c+d 839.88
Rate per 1 Cum excluding Dewatering Rs 839.88
Cum
BLD-CSTN-2-7 - (15)
Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead of 50m including all
operational, incidental, labour charges such as shoring ,sheeting, planking, strutting, etc. complete for finished item
of work including seigniorage excluding dewatering charges etc as per SS - 20 B (APSS 308).
a)Labour
Mate 0.00 Nos 0.00 1 Nos 0.00
Mazdoor (Unskilled) 5.20 Nos 350.00 1 Nos 1820.00
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack 6 hour 1285.40 1 hour 7712.40
hammers of pneumatic breaker at 1 cum per hour
sub total ; a+b 9532.40
c&d) Overheads & Contractors Profit 14% 1334.54
Cost for 10 cum = a+b+c+d 10866.94
Rate per cum = a+b+c+d+e)/10 1086.69
Rate per 1 Cum excluding Dewatering 1086.69
Cum
Buildings
Page 256 of 613
Plain Cement concrete M 7.50 (1:4:8) Grade using 40mm size Hard Granite Machine Crushed Metal including cost and
conveyance of all materials like cement, sand, coarse aggregate water etc., to site , seigniorage charges on all
materials, labour charges , for mixing , laying, concrete , ramming in 15 cm layers, finishing top surface to the
required level curing etc., complete for finished item of work.for foundation and under flooring bed.
Plain Cement concrete M 10 (1:3:6) Grade using 40mm size Hard Granite Machine Crushed Metal including cost and
conveyance of all materials like cement, sand, coarse aggregate water etc., to site , seigniorage charges on all
materials, labour charges , for mixing , laying, concrete , ramming in 15 cm layers, finishing top surface to the
required level curing etc., complete for finished item of work for foundation and under flooring bed.
21 Plain Cement concrete M 15 Grade using 20 mm size Graded Hard Granite Machine Crushed Metal including cost
and conveyance of all materials like cement, sand, coarse aggregate water etc., to site , seigniorage charges on all
materials, labour charges , for mixing , laying, concrete , ramming in 15 cm layers, finishing top surface to the
required level curing etc., complete for finished item of work with nomonal reinforcement
B. LABOUR:
Mason 1st class 0.10 Nos 437.50 1 Nos 43.75
Mazdoor (unskilled) 1.39 Nos 350.00 1 Nos 486.50
Total Rs 4051.84
c.Overheads & Contractors Profit 14% 567.26
Grand Total 4619.10
Rate per One Cum Rs 4619.10
Cum
22 RCC-M 25 Grade
Supply and placing of the M-25 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER / MIXER with
20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)with minimum cement content as per IS code for
Structural Components.
Buildings
Page 257 of 613
23 RCC-M 30 Grade
Supply and placing of the M- 30 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER / MIXER with
20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)with minimum cement content as per IS code for
Structural Components.
Buildings
Page 258 of 613
24 RCC M25 Grade COLUMNS, LINTELS(Unsupported Height of 3.66 m)- Steel Scaffolding & Centering
RCC M20 for Sun shades of 0.45M width, 100 mm th. at Support and 75 mm th. at edge Rate per Rm
(Unsupported Ht. of 3.66m) using Steel Scaffolding & Centering
Basic cost of RCC M-20 0.0525 Cum 5335.98 1 Cum 280.14
RCC M25 Grade COLUMNS, 0.45 Sqm 139.00 1 Sqm 62.55
LINTELS(Unsupported
Columns up to 3.66 m Height of 3.66
unsupported m)- above
height Steel 0.45 Sqm 82.00 1 Sqm 36.90
Scaffolding & Centering
GL 379.59
Add MA allowance on LC @ 25% 9.23
Sub Total Rs 768.40
Overheads & Contractors Profit 14% 107.58
Total 875.98
Sunshades-M20- 100/75mm-Rate per Rm Rs 875.98
RCC M20 for Sun shades of 0.45M width, 100 mm th. at Support and 75 mm th. at edge Rate per Rm
(Unsupported Ht. of 3.66m) using Steel Scaffolding & Centering
Basic cost of RCC M-20 0.0525 Cum 5335.98 1 Cum 280.14
R.C.C. M 20 Per Cum 0.45 Sqm 139.00 1 Sqm 62.55
Centering Hire Charges ,Pg No.75 0.45 Sqm 82.00 1 Sqm 36.90
Add MA allowance on LC @ 25% 9.23
Sub Total Rs 388.81
Buildings
Page 259 of 613
Buildings
Page 260 of 613
25 Supply and placing of the M-20 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER / MIXER with
20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)with minimum cement content as per IS code from
standard suppliers approved by the department including pumping, centering, shuttering, laying concrete, vibrating,
curing etc. complete but excluding cost of steel and its fabrication charges for finished item of work. for RCC Domes,
Slabs, Beams Unsupported Height of 3.66m using Steel Scaffolding and Centering
a) Dome Slabs upto 3.66m unsupported Height - Steel Scaffolding & Centering
Basic cost of RCC M-20 1.00 Cum 5335.98 1 Cum 5335.98
Centering Hire Charges ,Pg No.75 1.00 Cum 2281.00 1 Cum 2281.00
Labour charges,Pg No.75 1.00 Cum 1152.00 1 Cum 1152.00
Add MA allowance on LC @ 25% 288.00
Sub Total Rs 9056.98
Overheads & Contractors Profit 14% 1267.98
Total 10324.95
Dome Slabs-M20- Rate per One Cum Rs 10324.95
Cum
Rate for other Floors (Domes) 1F 2F 3F 4F 5F
R.C.C. M 20 Per Cum 5335.98 5335.98 5335.98 5335.98 5335.98
Centering Hire Charges ,Pg No.75 2281.00 2281.00 2281.00 2281.00 2281.00
Labour charges,Pg No.75 1152.00 1267.00 1382.00 1498.00 1613.00
Add MA allowance on LC @ 288.00 316.75 345.50 374.50 403.25
Total 9056.98 9200.73 9344.48 9489.48 9633.23
Overheads & Contractors Profit @ 0.14 1267.98 1288.10 1308.23 1328.53 1348.65
Domes-M20 -Rate per One Cum 10324.95 10488.83 10652.70 10818.00 10981.88 Cum
Buildings
Page 261 of 613
Buildings
Page 262 of 613
Buildings
Page 263 of 613
Buildings
Page 264 of 613
l) RCC M20- Beams up to 3.66 m height with Steel Scaffolding & Centering
Basic cost of RCC M-20 1.00 Cum 5535.98 1 Cum 5535.98
Material Hire Charges ,Pg.78 1.00 Cum 1064.00 1 Cum 1064.00
Labour Charges, Pg.78 1.00 Cum 626.00 1 Cum 626.00
Add MA allowance on LC @ 25% 156.50
Sub Total Rs 7382.48
Overheads & Contractors Profit 14% 1033.55
Total 8416.02
Rate per One Cum Rs 8416.02
Cum
Beams-M20- for other Floors 1F 2F 3F 4F 5F
Basic cost of RCC M-20 5535.98 5535.98 5535.98 5535.98 5535.98
Material Hire Charges ,Pg.78 1064.00 1064.00 1064.00 1064.00 1064.00
Labour Charges, Pg.78 626.00 689.00 751.00 814.00 876.00
Add MA allowance on LC @ 156.50 172.25 187.75 203.50 219.00
Sub Total 7382.48 7461.23 7538.73 7617.48 7694.98
Overheads & Contractors Profit @ 0.14 1033.55 1044.57 1055.42 1066.45 1077.30
Rate per One Cum 8416.02 8505.80 8594.15 8683.92 8772.27 Cum
m) RCC M20 for Sun shades of 0.60M width, 100 mm th. at Support and 75 mm th. at edge Rate per Rm
(Unsupported Ht. of 3.66m) using Steel Scaffolding & Centering
Basic cost of RCC M-20 0.0525 Cum 5535.98 1 Cum 290.64
Material Hire Charges ,Pg.78 0.60 Sqm 139.00 1 Sqm 83.40
Labour Charges, Pg.78 0.60 Sqm 82.00 1 Sqm 49.20
Add MA allowance on LC @ 25% 12.30
Sub Total Rs 435.54
Overheads & Contractors Profit 14% 60.98
Total 496.51
Sunshades-M20- 100/75mm-Rate per Rm Rs 496.51
Rm
Sunshades-M20- 100/75mm-other Floors 1F 2F 3F 4F 5F
R.C.C. M 20 Per 0.0525Cum 290.64 290.64 290.64 290.64 290.64
Material Hire Charges ,Pg.78 83.40 83.40 83.40 83.40 83.40
Labour Charges, Pg.78 49.20 54.00 58.80 64.20 69.00
Add MA allowance on LC @ 12.30 13.50 14.70 16.05 17.25
Sub Total 435.54 441.54 447.54 454.29 460.29
Overheads & Contractors Profit @ 0.14 60.98 61.82 62.66 63.60 64.44
Sunshades-M20-100/75 mm-Rate/Rm 496.51 503.35 510.19 517.89 524.73 per Rm
26 Supply and placing of the M-20 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER / MIXER with
20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges
such as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)with minimum cement content as per IS code from
standard suppliers approved by the department including pumping, centering, shuttering, laying concrete, vibrating,
curing etc. complete but excluding cost of steel and its fabrication charges for finished item of work. for RCC Domes,
Slabs, Beams (Unsupported Height of 7.32m) using Steel Scaffolding and Centering
Buildings
Page 265 of 613
Buildings
Page 266 of 613
Buildings
Page 267 of 613
MASONRY
Brick Masonry in CM(1:6), 23 cm thick
27 BLD-CSTN-5-4 (42)
Brick Masonary 2nd Class Ground moulded or traditional size 23x11x7 Cm in Cement Mortor 1:6 Prop having
minimum Crushing strength 40 Kg Per Sqcm including Cost & conveyance of all Materials like Cement, Sand, Bricks,
Water, etc., to site cost of Seigniorage charges on all materials, including all labour charges like mixing Cement
Mortor, scaffoding charges lift charges , curing charges etc., complete for finished item of work (23cm thick)
A. MATERIALS:
Cement 48.00 Kg 4.00 1 Kg 192.00
Bricks traditional size 23 x 11 x 7 cms 2nd class 512 Nos 4298.27 1000 Nos 2200.72
Fine aggregate (Sand) 0.20 Cum 800.00 1 Cum 160.00
B. LABOUR:
Mason 1st class 0.24 Nos. 437.50 1 Each 105.00
Mason 2nd class 0.56 Nos. 400.00 1 Each 224.00
Mazdoor (unskilled) 1.89 Nos. 350.00 1 Each 661.50
Total A+B Rs 3543.22
c.Overheads & Contractors Profit 14% 496.05
Grand Total 4039.27
Rate per One Cum Rs 4039.27
Cum
BM in CM(1:6),23cm -for Other Floors 1F 2F 3F 4F 5F
Basic rate per 1Cum 3543.22 3543.22 3543.22 3543.22 3543.22
Hire Charges for Access Scaffolding 23.01 23.01 23.01 23.01 23.01
Labour Charges for Scaffolding 123.54 185.31 247.08 308.85 370.62
Add MA allowance on LC @ 30.89 46.33 61.77 77.21 92.66
Sub Total 3720.65 3797.86 3875.08 3952.29 4029.50
Overheads & Contractors Profit @ 0.14 520.89 531.70 542.51 553.32 564.13
BM in CM(1:6),23cm -Rate/Cum 4241.54 4329.57 4417.59 4505.61 4593.63 Cum
A. MATERIALS:
Cement 72.00 Kg 4.00 1 Kg 288.00
Bricks traditional size 23 x 11 x 7 cms 2nd class 512 Nos 4298.27 1000 Nos 2200.72
Fine aggregate (Sand) 0.20 Cum 800.00 1 Cum 160.00
B. LABOUR:
Mason 1st class 0.24 Nos. 437.50 1 Each 105.00
Mason 2nd class 0.56 Nos. 400.00 1 Each 224.00
Mazdoor (unskilled) 1.89 Nos. 350.00 1 Each 661.50
Total A+B Rs 3639.22
c.Overheads & Contractors Profit 14% 509.49
Grand Total 4148.71
Rate per One Cum Rs 4148.71
Cum
BM in CM(1:4),23cm -for Other Floors 1F 2F 3F 4F 5F
Basic rate per 1Cum 3639.22 3639.22 3639.22 3639.22 3639.22
Hire Charges for Access Scaffolding 23.01 23.01 23.01 23.01 23.01
Labour Charges for Scaffolding 123.54 185.31 247.08 308.85 370.62
Add MA allowance on LC @ 30.89 46.33 61.77 77.21 92.66
Sub Total 3816.65 3893.86 3971.08 4048.29 4125.50
Overheads & Contractors Profit @ 0.14 534.33 545.14 555.95 566.76 577.57
BM in CM(1:4),23cm - Rate/Cum 4350.98 4439.01 4527.03 4615.05 4703.07 Cum
A. MATERIALS:
Cement 53.00 Kg 4.00 1 Kg 212.00
Bricks traditional size 23 x 11 x 7 cms 2nd class 565 Nos 4298.27 1000 Nos 2428.52
Buildings
Page 268 of 613
A. MATERIALS:
Cement 79.00 Kg 4.00 1 Kg 316.00
Bricks traditional size 23 x 11 x 7 cms 2nd class 565 Nos 4298.27 1000 Nos 2428.52
Fine aggregate (Sand) 0.22 Cum 1000.00 1 Cum 220.00
B. LABOUR:
Mason 1st class 0.60 Nos. 437.50 1 Each 262.50
Mason 2nd class 0.60 Nos. 400.00 1 Each 240.00
Mazdoor (unskilled) 2.75 Nos. 350.00 1 Each 962.50
4429.52
Add Water charges@ 1% 1% 44.30
Sub Total 4473.82
c.Overheads & Contractors Profit 14% 626.33
Grand Total 5100.15
BM in CM(1:4), 11.50cm - Rate/Cum Rs 5100.15
Cum
BM in CM(1:4),11.5cm - for Other Floors 1F 2F 3F 4F 5F
Buildings
Page 269 of 613
A. MATERIALS:
Cement 24.00 Kg 4.00 1 Kg 96.00
Fal-G Bricks 290x200x140 mm - 50 Ksc 110 Nos 26.39 1 No 2902.35
Fine aggregate (Sand) 0.10 Cum 1000.00 1 Cum 100.00
B. LABOUR:
Mason 1st class 0.60 Nos. 437.50 1 Each 262.50
Mason 2nd class 0.60 Nos. 400.00 1 Each 240.00
Mazdoor (unskilled) 2.75 Nos. 350.00 1 Each 962.50
4563.35
Add Water charges@ 1% 1% 45.63
Sub Total 4608.99
c.Overheads & Contractors Profit 14% 645.26
Grand Total 5254.25
Fal-G CM(1:6), 15/20 cm - Rate/Cum Rs 5254.25
Cum
Fal-G in CM(1:6),15/20cm- Other Floors 1F 2F 3F 4F 5F
Basic rate per 1Cum 4608.99 4608.99 4608.99 4608.99 4608.99
Hire Charges for Access Scaffolding 35.28 35.28 35.28 35.28 35.28
Labour Charges for Scaffolding 189.43 284.14 378.86 473.57 568.28
Add MA allowance on LC @ 25% 47.36 71.04 94.71 118.39 142.07
Sub Total 4881.06 4999.45 5117.84 5236.23 5354.63
Overheads & Contractors Profit @ 0.14 683.35 699.92 716.50 733.07 749.65
Fal-G CM(1:6), 11.50cm - Rate/Cum 5564.41 5699.37 5834.34 5969.31 6104.28 Cum
A. MATERIALS:
Cement 24.00 Kg 4.00 1 Kg 96.00
Fal-G Bricks 290x200x140 mm - 50 Ksc 220 Nos 20.81 1 No 4577.87
Fine aggregate (Sand) 0.10 Cum 800.00 1 Cum 80.00
B. LABOUR:
Mason 1st class 0.60 Nos. 437.50 1 Each 262.50
Mason 2nd class 0.60 Nos. 400.00 1 Each 240.00
Mazdoor (unskilled) 2.75 Nos. 350.00 1 Each 962.50
6218.87
Add Water charges@ 1% 1% 62.19
Sub Total 6281.06
c.Overheads & Contractors Profit 14% 879.35
Grand Total 7160.41
Fal-G CM(1:6), 15/20 cm - Rate/Cum Rs 7160.41
Cum
Fal-G in CM(1:6),15/20cm- Other Floors 1F 2F 3F 4F 5F
Basic rate per 1Cum 6281.06 6281.06 6281.06 6281.06 6281.06
Hire Charges for Access Scaffolding 35.28 35.28 35.28 35.28 35.28
Labour Charges for Scaffolding 189.43 284.14 378.86 473.57 568.28
Add MA allowance on LC @ 25% 47.36 71.04 94.71 118.39 142.07
Sub Total 6553.13 6671.52 6789.92 6908.31 7026.70
Overheads & Contractors Profit @ 0.14 917.44 934.01 950.59 967.16 983.74
Fal-G CM(1:6), 11.50cm - Rate/Cum 7470.57 7605.54 7740.51 7875.47 8010.44 Cum
32 BLD-CSTN-6-6-(61)
Construction of CRS Masonary 2nd Sort in Cement Mortor ( 1:6 ) Prop using hard granite stone including cost &
Conveyance of all materials like Cement, Sand , Water, Granite Stones, including Seigniorage Charges on all
Materials, ,labour charges for cutting Stones to required size and shape, mixing of Cement Mortor, Construction,
Scaffolding Charges curing etc., complete for finished item of Work . CRS Masonry CM(1:6)
A. MATERIALS:
Cement 76.80 Kg 4.00 1 Kg 307.20
Buildings
Page 270 of 613
A. MATERIALS:
Cement 79.20 Kg 4.00 1 Kg 316.80
CR Rubble Stone 0.44 Cum 1047.88 1 Cum 461.07
Rough Stone 0.50 Cum 781.10 1 Cum 390.55
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum 0.16 Cum 1047.88 1 Cum 167.66
Fine aggregate (Sand) 0.33 Cum 1000.00 1 Cum 330.00
B. LABOUR:
Mason 1st class 1.20 Nos 437.50 1 Nos 525.00
Mazdoor (unskilled) 2.00 Nos 350.00 1 Nos 700.00
Total A+B Rs 2891.08
C.Overheads & Contractors Profit 14% 404.75
Grand Total 3295.83
RR Masonry,CM(1:6). Rate/Cum Rs Cum
Buildings
Page 271 of 613
Buildings
Page 272 of 613
Plastering with 12mm thick in single coat in CM (1:5) finished smooth including cost and conveyance of all materials
to site, seigniorage charges on all materials, finishing, curing, scaffolding and all operational, incidental, labour
charges etc., including cutting grooves where ever necessary etc., complete for finished item of work. CM
(1:5),12mm thickOutput: 10Sq.m
A. MATERIALS:
Cement Mortor (1:5) 0.15 Cum 2741.34 1 Cum 411.20
B. LABOUR:
Mason 1st class 0.60 Nos 437.50 1 Nos 262.50
Mazdoor (unskilled) 0.96 Nos 350.00 1 Nos 336.00
Total A+B Rs 1009.70
C.Overheads & Contractors Profit 14% 141.36
Grand Total for 10 Sqm 1151.06
Plastering,CM(1:5),12mm Rate/Sq.m Rs 115.11
Sq.m
Pastering CM(1:5), 12 mm Other Floors 1F 2F 3F 4F 5F
Basic rate per 1 sq.m 100.97 100.97 100.97 100.97 100.97
c.Overheads & Contractors Profit 0.53 0.53 0.53 0.53 0.53
Labour Charges for Scaffolding 2.84 4.26 5.68 7.10 8.52
Add MA allowance on LC @ 0.71 1.07 1.42 1.78 2.13
Total 105.05 106.83 108.60 110.38 112.15
Overheads & Contractors Profit 14.71 14.96 15.20 15.45 15.70
Plastering,CM(1:6),12mm Rate/Sq.m 119.76 121.78 123.80 125.83 127.85 Sq.m
Buildings
Page 273 of 613
A. MATERIALS:Output : 10Sq.m
Cement Mortor (1:4) 0.15 Cum 3139.67 1 Cum 470.95
B. LABOUR:
Mason 1st class 0.60 Nos 437.50 1 Nos 262.50
Mazdoor (unskilled) 0.96 Nos 350.00 1 Nos 336.00
Total A+B 1069.45
C.Overheads & Contractors Profit 14% 149.72
Grand Total for 10 Sq.m 1219.17
Plastering,CM(1:4),12mm Rate/Sq.m Rs 121.92
Sq.m
Pastering CM(1:4), 12 mm Other Floors 1F 2F 3F 4F 5F
Basic rate per 1 Sq.m 106.95 106.95 106.95 106.95 106.95
Hire Charges for Access Scaffolding 0.53 0.53 0.53 0.53 0.53
Labour Charges for Scaffolding 2.84 4.26 5.68 7.10 8.52
Add MA allowance on LC @ 25% 0.71 1.07 1.42 1.78 2.13
Total 111.03 112.80 114.58 116.35 118.13
Overheads & Contractors Profit,14% 15.54 15.79 16.04 16.29 16.54
Plastering,CM(1:4),12mm, Rate/Sq.m 126.57 128.59 130.62 132.64 134.66 Sq.m
A. MATERIALS:Output : 10Sq.m
Cement Mortor (1:4) 0.21 Cum 3139.67 1 Cum 659.33
B. LABOUR:
Mason 1st class 0.94 Nos 437.50 1 Nos 411.25
Mazdoor (unskilled) 1.60 Nos 350.00 1 Nos 560.00
Total A+B 1630.58
C.Overheads & Contractors Profit 14% 228.28
Grand Total for 10 Sq.m 1858.86
Plastering,CM(1:4), 20 mm Rate/Sq.m Rs 185.89
Sq.m
Pastering CM(1:4), 20mm Other Floors 1F 2F 3F 4F 5F
Basic rate per 1 Sq.m 163.06 163.06 163.06 163.06 163.06
Hire Charges for Access Scaffolding 0.53 0.53 0.53 0.53 0.53
Labour Charges for Scaffolding 2.84 4.26 5.68 7.10 8.52
Add MA allowance on LC @ 25% 0.71 1.07 1.42 1.78 2.13
Total 167.14 168.91 170.69 172.46 174.24
Overheads & Contractors Profit,14% 23.40 23.65 23.90 24.14 24.39
Plastering,CM(1:4),12mm, Rate/Sq.m 190.54 192.56 194.58 196.61 198.63 Sq.m
A. MATERIALS:Output 10 Sq.m
Cement Mortor (1:3) 0.15 Cum 3803.56 1 Cum 570.53
B. LABOUR:
Mason 1st class 0.60 Nos 437.50 1 Nos 262.50
Mazdoor (unskilled) 0.96 Nos 350.00 1 Nos 336.00
Total A+B Rs 1169.03
C.Overheads & Contractors Profit 14% 163.66
Grand Total for 10 Sq.m 1332.70
Plastering ,CM(1:3),12mm, Rate/Sq.m Rs 133.27
Sq.m
Buildings
Page 274 of 613
Plastering in CM(1:6) & CM(1:4) Base & Top Coats, 20mm th (16 & 4 mm)
31 BLD-CSTN-8-9-(84)
Plastering 20mm thick two coats with base coat of 16mm thick in C.M. (1:6) and top coat of 4mm thick in C.M. (1:3)
with dubara sponge finishing including cost & conveyance of all materials like cement, Sand , Water, etc., to site,
seigniorage charges, all operational, including charges, labour charges for mixing mortar, finishing, scaffolding, lift
charges, curing , including cutting grooves where ever necessary etc., complete for finished item of work of uneven
surfaces of walls. (External walls)
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement 43.00 Kg 4.00 1 Kg 172.00
Fine aggregate (Sand) 0.18 Cum 1000.00 1 Cum 180.00
Top Coat in CM(1:4), 4 mm thick
Cement 14.50 Kg 4.00 1 Kg 58.00
Fine aggregate (Sand) 0.04 Cum 1000.00 1 Cum 40.00
B. LABOUR:
Mason 1st class 0.63 Nos 437.50 1 Nos 275.63
Mason 2nd class 1.47 Nos 400.00 1 Nos 588.00
Mazdoor (unskilled) 3.90 Nos 350.00 1 Nos 1365.00
Sub Total Rs 2678.63
C.Overheads & Contractors Profit 14% 375.01
Grand Total for 10 Sq.m 3053.63
Plastering 20mm, Two Coats Rate/Sq.m Rs 305.36
Sq.m
Plastering 20mm,Two Coats,other Floors 1F 2F 3F 4F 5F
Basic rate per 1Cum 267.86 267.86 267.86 267.86 267.86
Hire Charges for Access Scaffolding 0.53 0.53 0.53 0.53 0.53
Labour Charges for Scaffolding 2.84 4.26 5.68 7.10 8.52
Add MA allowance on LC @ 0.71 1.07 1.42 1.78 2.13
Total 271.94 273.72 275.49 277.27 279.04
Overheads & Contractors Profit 38.07 38.32 38.57 38.82 39.07
Rate per One Sq.m 310.01 312.04 314.06 316.08 318.11 Sq.m
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) 0.21 Cum 3803.56 1 Cum 798.75
Water Proofing Compound 2.00 Kg 66.00 1 Kg 132.00
B. LABOUR:
Mason 1st class 0.66 Nos 437.50 1 Nos 288.75
Mason 2nd class 1.54 Nos 400.00 1 Nos 616.00
Mazdoor (unskilled) 3.70 Nos 350.00 1 Nos 1295.00
Sub Total Rs 3130.50
C.Overheads & Contractors Profit 14% 438.27
Grand Total for 10 Sq.m 3568.77
WP Plasteitn,CM(1:3),20mm Rate/Sq.m Rs 356.88
Sq.m
Buildings
Page 275 of 613
A. MATERIALS:Output : 10 Sq.m
Cement 14.40 Kg 4.00 1 Kg 57.60
Fine aggregate (Sand) 0.03 Cum 1000.00 1 Cum 30.00
B. LABOUR:
Mason 2nd class 0.50 Nos 400.00 1 Nos 200.00
Mazdoor (unskilled) 0.74 Nos 350.00 1 Nos 259.00
Sub Total Rs 546.60
C.Overheads & Contractors Profit 14% 76.52
Grand Total for 10 Sq.m 623.12
Flush Pinting,CRS Masonry, Rate/Sq.m Rs 62.31
Sq.m
34 BLD-CSTN-12-2-(169)
Painting with Priming Coat on New Plastered Surface with Cement Primer Water base Exterior Gr-2 after thoroughly
brushing the surface to remove all dirt and remains of loose powdered materials including cost of all materials,
labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of work.
Buildings
Page 276 of 613
35 BLD-CSTN-11-5-(162)
White washing two coats with white cement of approved quality to give an even shade after thoroughly brushing the
surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charges and
incidental such as scaffolding, lift charges etc., complete for finished item of work, but excluding conveyance
charges of materials Whoite Cement- Two Coats
Output : 10 Sq.m
Cement Primer-One Coat 422.62
Cost of Oil Bound Distemper-Two Coats 1.70 Kg 81.00 1 Kg 137.70
1st class painter 0.36 Nos 437.50 1 Nos 157.50
II class painter 0.84 Nos 400.00 1 Nos 336.00
Total Rs 1053.82
Over heads & contractors profit 14% 147.53
Total cost for 10 sqm 1201.35
Rate per 1 Sqm Rs 120.14
Sq.m
Buildings
Page 277 of 613
39 BMT-J-36: Supplying, application and finishing of Two Coats of Altek/Saicoat/Wall care , One Coat of Cememt Primer
and Two Coats of Emulsion paint for internal Walls
40 BMT-J-37: Supplying, application and finishing of Two Coats of Altek/Saicoat/Wall care , One Coat of Cememt Primer
and Two Coats of Acrylic Washable Distemper for internal Walls
41 BMT-J-38: Supplying, application and finishing of One Caot of Water base Cement Primer and Two Coats of exterior
grade emulsion paint for exterior Walls
42
BLD-CSTN-10-6: Painting New Wood Work with One Coat of Wood Primer
Unit: 10 sqm
Wood Primer - One Coat 0.70 Ltr 135.00 1 Ltr 94.50
1st Class Painter 0.21 Nos. 437.50 1 Each 91.88
2nd Class Painter 0.49 Nos. 400.00 1 Each 196.00
382.38
Sundries including brushes, soap, putty etc., 1.00% 3.82
Total Rs 386.20
Over heads & Contractors profit 14% 54.07
Total cost for 10 sqm 440.27
Rate per 1 Sqm Rs 44.03
Sq.m
43 BLD-CSTN-10-7: Painting New Iron Work with One Coat Red Oxide Primer
Unit: 10 sqm
Red Oxide Primer Gr-I - One Caot 0.70 Ltr 121.00 1 Ltr 84.70
1st Class Painter 0.21 Nos. 437.50 1 Each 91.88
2nd Class Painter 0.49 Nos. 400.00 1 Each 196.00
372.58
Sundries including brushes, soap, putty etc., 1.00% 3.73
Sub Total Rs 376.30
Over heads & Contractors profit 14% 52.68
Total cost for 10 sqm 428.98
Rate per 1 Sqm Rs 42.90
Sq.m
44
BLD-CSTN-10-10: Painting New Wood Work with One Coat of Wood Primer and Two Coats of Synthetic Enamel Paint
Unit: 10 sqm
Wood Primer -One Coat 440.27
Synthetic Enamel Paint Gr-I - Two Coats 2.80 Ltr 230.00 1 Ltr 644.00
1st Class Painter 0.36 Nos. 437.50 1 Each 157.50
2nd Class Painter 0.84 Nos. 400.00 1 Each 336.00
1577.77
Sundries including brushes, soap, putty etc., 1.00% 15.78
Sub Total Rs 1593.54
Over heads & Contractors profit 14% 223.10
Total cost for 10 sqm 1816.64
Rate per 1 Sqm Rs 181.66
Sq.m
45 BLD-CSTN-10-10: Painting New Iron Work with One Coat of Red Oxide Primer and Two Coats of Synthetic Enamel
Paint
Unit: 10 sqm
Red Oxide Primer -One Coat 428.98
Synthetic Enamel Paint Gr-I - Two Coats 2.40 Ltr 230.00 1 Ltr 552.00
1st Class Painter 0.36 Nos. 437.50 1 Each 157.50
2nd Class Painter 0.84 Nos. 400.00 1 Each 336.00
1474.48
Buildings
Page 278 of 613
Buildings
Page 279 of 613
Unit: 10 Sq.m
a) Materials
Melamine Polish 0.65 Litres 299.00 1 Litre 194.35
Thinner for Melamine Polish 0.33 Litres 125.00 1 Litre 41.25
b) Labour
Painter - I Class 0.24 Day 437.50 105.00
Painter- II Class 0.56 Day 400.00 224.00
Helper 0.8 Day 350.00 280.00
Sundries for Spraying m/c etc. 1 5.00 5.00
Sub Total 849.60
c) Overheads & Contractors Profit 14% 849.60 118.94
Total cost per 10 Sq.m 968.54
Sq.m
Unit: 10 Sq.m
a) Materials
Poly Urethan Polish -interior Grade 0.70 Litres 608.00 1 Litre 425.60
Thinner for Poly urethane Polish 0.30 Litres 256.00 1 Litre 76.80
b) Labour 0.00
Painter - I Class 0.24 Day 437.50 105.00
Painter- II Class 0.56 Day 400.00 224.00
Helper 0.80 Day 350.00 280.00
Sundries for Spraying m/c etc. 1.00 5.00 5.00
Sub Total 1116.40
c) Overheads & Contractors Profit 14% 1116.40 156.30
Total cost per 10 Sq.m 1272.70
Sq.m
Output : 10 Sq.m
a) Materials
Plastic Emulsion Paint 0.50 Litre 244.00 1 Lire 122.00
b) Labour
Painter - 1st Class 0.21 Day 437.50 1 Day 91.88
Painter-II Class 0.49 Day 400.00 1 Day 196.00
Sundries for Brushes, Blades etc 1.00 3.00 3.00
Sub Total 412.88
c) Overheads & Contractors profit 14% 412.88 57.80
Total for 10 Sq.m 470.68
Cost per Sq.m (One Coat)-Internal 47.07
Sq.m
Buildings
Page 280 of 613
Painting to new walls with Two Coats of plastic emusion paint of approved brand and shade after thoroughly
brushing the surface to remove all dirt and remains of loose powdered materials including cost and conveyance of all
materials to work site and all operational , incidental labour charges etc. complete for finished item of work as per SS
for internal walls
Output : 10 Sq.m
a) Materials
Plastic Emulsion Paint 0.80 Litre 244.00 1 Lire 195.20
b) Labour
Painter - 1st Class 0.36 Day 437.50 1 Day 157.50
Painter-II Class 0.84 Day 400.00 1 Day 336.00
Sundries for Brushes, Blades etc 1.00 3.00 3.00
Sub Total 691.70
c) Overheads & Contractors profit 14% 691.70 96.84
Total for 10 Sq.m 788.54
Cost per Sq.m( Two Coats)-Internal 78.85
Sq.m
Output : 10 Sq.m
a) Materials
Plastic Emulsion Paint 0.50 Litre 244.00 1 Lire 122.00
b) Labour
Painter - 1st Class 0.15 Day 437.50 1 Day 65.63
Painter-II Class 0.35 Day 400.00 1 Day 140.00
Mazdoor 1.50 Day 350.00 525.00
Sundries for Brushes, Blades etc 1.00 3.00 3.00
Sub Total 855.63
c) Overheads & Contractors profit 14% 855.63 119.79
Total for 10 Sq.m 975.41
Cost per Sq.m (One Coat)-External 97.54
Sq.m
Output : 10 Sq.m
a) Materials
Plastic Emulsion Paint 0.80 Litre 244.00 1 Lire 195.20
b) Labour
Painter - 1st Class 0.21 Day 437.50 1 Day 91.88
Painter-II Class 0.49 Day 400.00 1 Day 196.00
Mazdoor 1.50 Day 350.00 525.00
Sundries for Brushes, Blades etc 1.00 3.00 3.00
Sub Total 1011.08
c) Overheads & Contractors profit 14% 1011.08 141.55
Total for 10 Sq.m 1152.63
Cost per Sq.m( Two Coats)-External 115.26
Sq.m
Output : 10 Sq.m
a) Materials
Synthetic /PoP Putty 9.00 Kg 26.00 1 Kg 234.00
b) Labour
Painter - 1st Class 0.27 Day 437.50 1 Day 119.44
Painter-II Class 0.64 Day 400.00 1 Day 254.80
Mazdoor 0.91 Day 350.00 318.50
Sundries for Emery paper, fillers, Knife etc 1.00 3.00 3.00
Sub Total 929.74
c) Overheads & Contractors profit 14% 929.74 130.16
Buildings
Page 281 of 613
Output : 10 Sq.m
a) Materials
Synthetic /PoP Putty 9.000 Kg 26.00 1 Kg 234.00
b) Labour
Painter - 1st Class 0.546 Day 437.50 1 Day 238.88
Painter-II Class 1.274 Day 400.00 1 Day 509.60
Mazdoor 1.820 Day 350.00 637.00
Labour for Access Scaffold 10.000 Sq.m 35.99 1 Sq.m 359.90
Sundries for Emery paper, fillers, Knife etc 1.000 3.00 3.00
Sub Total 1982.38
c) Overheads & Contractors profit 14% 1982.38 277.53
Total for 10 Sq.m 2259.91
Cost per Sq.m Wall Care Putty- External 225.99
Sq.m
54 BLD-CSTN-10-25-(148)
Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg of water proof
compound per bag of cement laid over roof when it is green including cost of all materials, seigniorage charges,
excluding conveyance charges of materials and including all operational, incidental and labour charges for mixing
mortar, laying, rendering smooth and thread lining, curing, rounding off junctions of wall and slab etc,, complete for
finished item of work
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3 0.210 Cum 3803.56 1 cum 798.75
Water proof compound 2.000 Kg 48.00 1 Kg 96.00
B. LABOUR
Mason 1st class 0.660 Nos 437.50 1 Nos 288.75
Mason 2nd class 1.540 Nos 400.00 1 Nos 616.00
Mazdoor (unskiled) 3.70 Nos 350.00 1 Nos 1295.00
Sub Total Rs 3094.50
Over heads & Contractors profit 14% 433.23
Total cost for 10 sqm 3527.73
Rate per 1 Sqm Rs 352.77
Sq.m
FLOORING
55 BLD-CSTN-7-2
Flooring with 40 mm thick Rough Shahbad/Tandur stones, set over base coat of cement mortar (1 : 8) 12 mm thick
over CC bed already laid or RCC roof slab, including pointing with cement mortar 1:3 duly filling joints neatly,
including cost of all materials like flooring stone, cement, sand, and water etc., complete, including seigniorage
charges, labour charges for dressing of flooring stones etc., complete for finished item of work, but excluding the
cost of conveyance of all materials.
A. MATERIALS:
Shahabad / Tandur Rough Stone slabs of minimum 10.50 Sqm 131.10 1 Sqm 1376.55
40 mm thick
Cement for CM (1:8) proportion for base coat 21.60 Kg 4.00 1 Kg 86.40
Cement for CM 1:3 proportion for pointing 9.60 Kg 4.00 1 Kg 38.40
Sand for CM (1:8) proportion 0.12 Cum 1000.00 1 Cum 120.00
Sand for CM (1:3) proportion 0.02 Cum 1000.00 1 Cum 20.00
B. LABOUR:
Mason 1st class 0.960 Nos 437.50 1 Nos 420.00
Mason 2nd class 2.240 Nos 400.00 1 Nos 896.00
Mazdoor (unskilled) 3.30 Nos 350.00 1 Nos 1155.00
Sub Total Rs 4112.35
over heads & contractors profit 14% 575.73
Total cost for 10 sqm 4688.08
Rate per 1 Sqm Rs 468.81
Buildings
Page 282 of 613
Sq.m
56 BLD-CSTN-7-2
Flooring with 40 mm thick Rough Kadapa slabs, set over base coat of cement mortar (1 : 8) 12 mm thick over CC bed
already laid or RCC roof slab, including pointing with cement mortar 1:3 duly filling joints neatly, including cost of all
materials like flooring stone, cement, sand, and water etc., complete, including seigniorage charges, labour charges
for dressing of flooring stones etc., complete for finished item of work, but excluding the cost of conveyance of all
materials.
A. MATERIALS:
Rough Kadapa Slabs 40 mm thick of size 0.45 *0.45 10.50 Sqm 103.10 1 Sqm 1082.55
m
Cement for CM (1:8) proportion for base coat 21.60 Kg 4.00 1 Kg 86.40
Cement for CM 1:3 proportion for pointing 9.60 Kg 4.00 1 Kg 38.40
Sand for CM (1:8) proportion 0.12 Cum 1000.00 1 Cum 120.00
Sand for CM (1:3) proportion 0.02 Cum 1000.00 1 Cum 20.00
B. LABOUR:
Mason 1st class 0.960 Nos 437.50 1 Nos 420.00
Mason 2nd class 2.240 Nos 400.00 1 Nos 896.00
Mazdoor (unskilled) 3.30 Nos 350.00 1 Nos 1155.00
Sub Total Rs 3818.35
over heads & contractors profit 14% 534.57
Total cost for 10 sqm 4352.92
Rate per 1 Sqm Rs 435.29
Sq.m
57 BLD-CSTN-7-1 Flooring
with 25mm thick polished Bethemcherla (50% White & 50% black) stones of size 0.25 *0.25 m set over base coat of
CM (1:8) over already laid CC bed / RCC Roof Slab, including neat cement slurry of honey like consistency spread @
3.3 kgs per sqm. & Jointed with neat cement to full depth including cost of all materials like cement, sand, and water
and flooring stones etc., complete, including seigniorage charges, labour charges for dressing of flooring stones etc.,
complete for finished item of work, but excluding the cost of conveyance of all materials.
A. MATERIALS:
Polished Bethemcherla 50% White& 50 % Black 11.00 Sqm 335.44 1 Sqm 3689.81
-25mm thick and 0.25*0.25m
Cement for CM (1:8) proportion for base coat 21.60 Kg 4.00 1 Kg 86.40
Cement for Slurry 33.00 Kg 4.00 1 Kg 132.00
Cement for Jointing 20.00 Kg 4.00 80.00
Sand for CM (1:8) proportion 0.12 Cum 1000.00 1 Cum 120.00
B. LABOUR:
Mason 1st class 3.100 Nos 437.50 1 Nos 1356.25
Mason 2nd class 1.100 Nos 400.00 1 Nos 440.00
Mazdoor (unskilled) 0.86 Nos 350.00 1 Nos 301.00
Sub Total Rs 6205.46
Over heads & Contractors profit 14% 868.76
Total 7074.23
Rate per 1 Sqm Rs 707.42
Sq.m
A. MATERIALS:
Polished Shahbad/Tandur 15/18mm thick Stones of 11.00 Sqm 167.66 1 Sqm 1844.29
size 0.40*0.40 m
Cement for CM (1:8) proportion for base coat 21.60 Kg 4.00 1 Kg 86.40
Cement for Slurry 33.00 Kg 4.00 1 Kg 132.00
Cement for Jointing 20.00 Kg 4.00 80.00
Sand for CM (1:8) proportion 0.12 Cum 1000.00 1 Cum 120.00
B. LABOUR:
Mason 1st class 3.100 Nos 437.50 1 Nos 1356.25
Mason 2nd class 1.100 Nos 400.00 1 Nos 440.00
Mazdoor (unskilled) 0.86 Nos 350.00 1 Nos 301.00
Sub Total Rs 4359.94
Over heads & Contractors profit 14% 610.39
Buildings
Page 283 of 613
Total 4970.33
Rate per 1 Sqm Rs 497.03
Sq.m
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size -900x90x10mm 10.10 sqm 1225.00 10 sqm 12372.50
Cement for CM (1:8) for base coat 21.60 kg. 4.00 1 kg. 86.40
Cement for slurry 33.00 kg. 4.00 1 kg. 132.00
Cement for Pointing with CM (1:3) 6.000 kg. 4.00 1 kg. 24.00
Sand for CM (1:8) 0.12 cum 1000.00 1 cum 120.00
Sand for pointing 0.020 cum 1000.00 1 cum 20.00
B. LABOUR
Mason 1st class 0.96 day 437.50 1 day 420.00
Mason 2nd class 2.24 day 400.00 1 day 896.00
Mazdoor (unskiled) 3.30 day 350.00 1 day 1155.00
15225.90
Add water charges 1% 1.00% 152.26
Sub Total 15378.16
Over heads & Contractors profit 14% 2152.94
Total cost for 10 sqm 17531.10
Rate per 1 Sqm Rs 1753.11
Sq.m
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size - 600*600*8 mm 10.10 sqm 607.00 10 sqm 6130.70
Cement for CM (1:8) for base coat 21.60 kg. 4.00 1 kg. 86.40
Cement for slurry 33.00 kg. 4.00 1 kg. 132.00
Cement for Pointing with CM (1:3) 6.000 kg. 4.00 1 kg. 24.00
Sand for CM (1:8) 0.12 cum 1000.00 1 cum 120.00
Sand for pointing 0.020 cum 1000.00 1 cum 20.00
B. LABOUR
Mason 1st class 0.96 day 437.50 1 day 420.00
Mason 2nd class 2.24 day 400.00 1 day 896.00
Mazdoor (unskiled) 3.30 day 350.00 1 day 1155.00
8984.10
Add water charges 1% 1.00% 89.84
Sub Total 9073.94
Over heads & Contractors profit 14% 1270.35
Total cost for 10 sqm 10344.29
Rate per 1 Sqm Rs 1034.43
Sq.m
Unit = 10 sqm
A. MATERIALS:
Buildings
Page 284 of 613
Glazed Ceramic Non Skid Floor Tiles of 10.10 sqm 447.00 1 sqm 4514.70
400*400*7.30 mm thick of all colors
Cement for CM (1:8) for base coat 21.60 kg. 4.00 1 kg. 86.40
Cement for slurry 33.00 kg. 4.00 1 kg. 132.00
Cement for Pointing with CM (1:3) 6.000 kg. 4.00 1 kg. 24.00
Sand for CM (1:8) 0.12 cum 1000.00 1 cum 120.00
Sand for pointing 0.020 cum 1000.00 1 cum 20.00
B. LABOUR
Mason 1st class 0.96 day 437.50 1 day 420.00
Mason 2nd class 2.24 day 400.00 1 day 896.00
Mazdoor (unskiled) 3.30 day 350.00 1 day 1155.00
7368.10
Add water charges 1% 1.00% 73.68
Sub Total 7441.78
Over heads & Contractors profit 14% 1041.85
Total cost for 10 sqm 8483.63
Rate per 1 Sqm Rs 848.36
Sq.m
A. MATERIALS:
6mm to 12 mm H.G. Metal (Machine crushed) 0.17 Cum 1576.85 1 Cum 268.06
Unit = 10 sqm
A. MATERIALS:
High polished Other than black Granite 16 to 18 mm 10.10 sqm 3440.66 1 sqm 34750.69
thick slab other than black
Cement for CM (1:8) for base coat 36.00 kg. 4.00 1 kg. 144.00
Cement for slurry 33.00 kg. 4.00 1 kg. 132.00
White cement with color oxides for jointing & 6.00 kg. 32.50 1 kg. 195.00
pointing
Sand for CM (1:8) 0.20 cum 1000.00 1 cum 200.00
B. LABOUR
Mason 1st class 3.00 day 437.50 1 day 1312.50
Mason 2nd class 1.00 day 400.00 1 day 400.00
Mazdoor (unskiled) 8.00 day 350.00 1 day 2800.00
39934.19
Add water charges 1% 1.00% 399.34
Sub Total Rs 40333.53
Over heads & Contractors profit 14% 5646.69
Total cost for 10 sqm 45980.23
Rate per 1 Sqm Rs 4598.02
Sq.m
Buildings
Page 285 of 613
Unit = 10 sqm
A. MATERIALS:
High polished black granite 16 to 18 mm thick slabs 10.10 sqm 2990.66 1 sqm 30205.69
Cement for CM (1:8) for base coat 36.00 kg. 4.00 1 kg. 144.00
Cement for slurry 33.00 kg. 4.00 1 kg. 132.00
White cement with color oxides for jointing & 6.00 kg. 32.50 1 kg. 195.00
pointing
Sand for CM (1:8) 0.20 cum 1000.00 1 cum 200.00
B. LABOUR
Mason 1st class 3.00 day 437.50 1 day 1312.50
Mason 2nd class 1.00 day 400.00 1 day 400.00
Mazdoor (unskiled) 8.00 day 350.00 1 day 2800.00
35389.19
Add water charges 1% 1.00% 353.89
Sub Total Rs 35743.08
Over heads & Contractors profit 14% 5004.03
Total cost for 10 sqm 40747.11
Rate per 1 Sqm Rs 4074.71
Sq.m
65 BLD-CSTN-7-18-(116)
Providing skirting to internal walls to 15 cm height/risers of steps with ceramic tiles 7.30 mm thick length equal to
flooring stones, set over base coat of CM (1:3) 12 mm thick with cement slurry of honey like consistency spread at the
rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth,
including cost of all materials like tiles, cement, sand and water etc., complete including seigniorage charges, etc.,
complete for finished item of work, but excluding the cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick 10.00 sqm 447.00 1 sqm 4470.00
Sand for cm 1:3 base coat 0.12 cum 1000.00 1 cum 120.00
Cement for cm 1:3 base coat 57.60 kgs 4.00 1 kgs 230.40
Cement for slurry 33.00 kgs 4.00 1 kgs 132.00
White cement for jointing & pointing 6.00 kgs 32.50 1 kgs 195.00
B. LABOUR
Mason 1st class 0.77 Nos 437.50 1 Nos 336.88
Mazdoor (unskiled) 0.80 Nos 350.00 1 Nos 280.00
Sub Total Rs 5764.28
Over heads & Contractors profit 14% 807.00
Total cost for 10 sqm 6571.27
Rate per 1 Sq.m Rs 657.13
Sq.m
66 BLD-CSTN-7-23
Providing skirting to internal walls to 15 cm height/risers of steps with 15 to 18 mm thick polished Shahabad stone
length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like Shahabad stone, cement, sand and water etc.,
complete including seigniorage charges, etc., complete for finished item of work, but excluding the cost of
conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
15 /18mm thick polished Shahabad stone 10.10 sqm 167.66 10 sqm 1693.39
Sand for cm 1:3 base coat 0.12 cum 1000.00 1 cum 120.00
Cement for cm 1:3 base coat 57.60 kgs 4.00 1 kgs 230.40
Cement for slurry 33.00 kgs 4.00 1 kgs 132.00
B. LABOUR
Mason Ist class 0.96 Nos 437.50 1 Nos 420.00
Mason 2nd class 2.24 Nos 400.00 1 Nos 896.00
Mazdoor (unskiled) 3.10 Nos 350.00 1 Nos 1085.00
4576.79
Add water charges 1% 1.00% 45.77
Sub Total Rs 4622.56
Buildings
Page 286 of 613
Unit = 10 sqm
A. MATERIALS:
8 mm thick mirror polished granite tiles 10.10 sqm 1167.66 1 sqm 11793.39
Sand for cm 1:3 base coat 0.12 cum 1000.00 1 cum 120.00
Cement for cm 1:3 base coat 57.60 kgs 4.00 1 kgs 230.40
Cement for slurry 33.00 kgs 4.00 1 kgs 132.00
White cement for jointing & pointing 5.00 kgs 32.50 1 kgs 162.50
B. LABOUR
Mason Ist class 0.87 day 437.50 1 day 380.63
Mason 2nd Class 2.03 day 400.00 1 day 812.00
Mazdoor (unskiled) 4.90 day 350.00 1 day 1715.00
Sub Total 15345.91
Add water charges 1% 1.00% 153.46
Sub Total 15499.37
Over heads & Contractors profit 14% 2169.91
Total cost for 10 sqm 17669.29
Rate per 1 Sq.m Rs 1766.93
Sq.m
68 BLD-CSTN-7-18
Providing skirting to internal walls with Glazed colour tiles of any size 1st quality set over a base coat of CM(1:3)
Prop. 12mm thick and neat Gray cement slurry of Honey like consistancy sread at the rate of 3.30 Kg of cement per
One Square Meter and jointed wiyh neat White cement paste mixed with pigmant of matching shade including cost
and conveyance of all materials like cement, sand, water, flooring Tiles etc. to site, all operational, incidental and
labour charges such as mixing of cement mortar, laying, jointing, curing, lift charges etc., complete for finished item
of work
A. MATERIALS:
Colour glazed tiles of 1st quality 10.10 Sqm 447.00 1 Sqm 4514.70
Sand for cm 1:3 base coat 0.12 cum 1000.00 1 cum 120.00
Cement for cm 1:3 base coat 57.60 kgs 4.00 1 kg 230.40
Cement for slurry 33.00 kgs 4.00 1 kg 132.00
White cement for jointing & pointing 6.00 kgs 32.50 1 kg 195.00
B. LABOUR 0.00
Mason Ist class 0.77 day 437.50 1 day 336.88
Mazdoor (unskiled) 0.80 day 350.00 1 day 280.00
5808.98
Add water charges 1% 1.00% 58.09
Sub Total 5867.06
Over heads & Contractors profit 14% 821.39
Total cost for 10 sqm 6688.45
Rate per One Sqm Rs 668.85
Sq.m
Unit : 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles 30mm thick thick (Dark 10.05 sqm 266.00 1 Sq.m 2673.30
Shade)
Cement for CM (1:6) proportion for base coat 28.80 kg. 4.00 1 Kg 115.20
Cement for slurry 33.00 kg. 4.00 1 Kg 132.00
Cement for jointing & pointing 6.00 kg. 4.00 1 Kg 24.00
Pigment 2.00 kg. 32.50 1 Kg 65.00
Sand for CM (1:6) proportion 0.12 cum 1000.00 1 Cum 120.00
Buildings
Page 287 of 613
B. MACHINERY
Nill
C. LABOUR
Mason 1st Class 0.96 day 437.50 1 Day 420.00
Mason 2nd Class 2.24 day 400.00 1 Day 896.00
Mazdoor (unskiled) 3.30 day 350.00 1 Day 1155.00
5600.50
Add water charges 1% 1.00% 56.01
Sub Total 5656.51
Overheads & Contractors Profit 14.00% 791.91
Total Cost for 10 Sq.m 6448.42
Rate per One Sq.m 644.84
Sq.m
Unit : 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles 30mm thick thick (Dark 10.05 sqm 250.00 1 Sq.m 2512.50
Shade)
Cement for CM (1:6) proportion for base coat 28.80 kg. 4.00 1 Kg 115.20
Cement for slurry 33.00 kg. 4.00 1 Kg 132.00
Cement for jointing & pointing 6.00 kg. 4.00 1 Kg 24.00
Pigment 2.00 kg. 32.50 1 Kg 65.00
Sand for CM (1:6) proportion 0.12 cum 1000.00 1 Cum 120.00
B. MACHINERY
Nill
C. LABOUR
Mason 1st Class 0.96 day 437.50 1 Day 420.00
Mason 2nd Class 2.24 day 400.00 1 Day 896.00
Mazdoor (unskiled) 3.30 day 350.00 1 Day 1155.00
5439.70
Add water charges 1% 1.00% 54.40
Sub Total 5494.10
Overheads & Contractors Profit 14.00% 769.17
Total Cost for 10 Sq.m 6263.27
Rate per One Sq.m 626.33
Sq.m
Unit : 10 sqm
A. MATERIALS:
High Strenth CC Designer Tiles (Phoenix or 10.05 sqm 484.00 1 Sq.m 4864.20
Equivalent)
Cement for CM (1:6) proportion for base coat 28.80 kg. 4.00 1 Kg 115.20
Cement for slurry 33.00 kg. 4.00 1 Kg 132.00
Cement for jointing & pointing 6.00 kg. 4.00 1 Kg 24.00
Pigment 2.00 kg. 32.50 1 Kg 65.00
Sand for CM (1:6) proportion 0.12 cum 1000.00 1 Cum 120.00
B. MACHINERY
Nill
Buildings
Page 288 of 613
C. LABOUR
Mason 1st Class 0.960 Day 437.50 1 Day 420.00
Mason 2nd Class 2.240 Day 400.00 1 Day 896.00
Mazdoor (unskiled) 3.30 Day 350.00 1 Day 1155.00
7791.40
Add water charges 1% 1.00% 77.91
Sub Total 7869.31
Overheads & Contractors Profit 14.00% 1101.70
Total Cost for 10 Sq.m 8971.02
Rate per One Sq.m 897.10
Sq.m
72 Flooring with 60 mm thick-M30 Gr. CC Interlocking Pavers (All Colours & Pattterns) for Non Traffic and in conformity
with IS_15658
Flooring with 60mm thick CC-M30 Gr. Interlocking pavers of all colours, sizes & all patterns laid over compacted
sand bed to proper levels and grades including materials and labour charges etc. complete as directed by Dept
authorities for finished item of work excluding cost of Sand.
Unit : 10 sqm
A. MATERIALS:
60mm thick Interlocking CC Pavers(BMT-D.16) 10.05 sqm 400.00 1 Sq.m 4020.00
B. MACHINERY
Nill
C. LABOUR
Mason 1st Class 0.96 Day 437.50 1 Day 420.00
Mason 2nd Class 2.24 Day 400.00 1 Day 896.00
Mazdoor (unskiled) 3.30 Day 350.00 1 Day 1155.00
6491.00
Sub Total 6491.00
Overheads & Contractors Profit 14.00% 908.74
Total Cost for 10 Sq.m 7399.74
Rate per One Sq.m 739.97
Sq.m
Unit = 10 sqm
A. MATERIALS:
PCC I:4:8 using 40mm HBG Metal 1.00 Cum 3834.55 1 Cum 3834.55
Plastering with CM (1:3), 12 mm thick 10.00 Sq.m 133.27 1 Sq.m 1332.70
Red oxid Pigment (LR) 10.00 Kg 105.00 1 Kg 1050.00
B. LABOUR
Mason 1 st Class for polishing 0.33 Day 437.50 1 Day 144.38
Mason 2nd Class 0.77 Day 400.00 1 Day 308.00
Buildings
Page 289 of 613
75 Flooring with M15 Gr. Concrete & top Red Oxide Finish
Flooring with Cement Concrete ,M15 Gr (1:2:4) using 20 mm Graded HBG Chips, 50 mm thick and top plastered with
12 mm thick in CM(1:3) using Red oxid, with polished surface and neatly Finished to proper levels and Grades
Unit = 10 sqm
A. MATERIALS:
PCC 1:2:4 using 20 mm Graded HBG Metal 0.50 Cum 4619.10 1 Cum 2309.55
Plastering with CM (1:3), 12 mm thick 10.00 Sq.m 133.27 1 Sq.m 1332.70
Red oxid Pigment (LR) 10.00 Kg 105.00 1 Kg 1050.00
B. LABOUR
Mason 1 st Class for polishing 0.33 Day 437.50 1 Day 144.38
Mason 2nd Class 0.77 Day 400.00 1 Day 308.00
Sub Total 5144.62
OH & CP @ 14% 5144.62 720.25
Total 5864.87
M15 Gr.Flooring &Red Oxide: Rs/Sq.m 586.49
Sq.m
Buildings
Page 290 of 613
Rate as per SSR Item No. 155,Pg 18 -BMT-F.29 1.00 Sqm 2500.00 1 Sqm 2000.00
Over heads & Contractors profit 14% 280.00
Rate per 1 Sqm Rs 2280.00
Sq.m
70 BMT-P.25
NCL or Equivalent ECO 3000 SERIES WINDOWS (SUITABLE FOR RESIDENTIAL BUILDINGS WITH GRILL PROVISION)
Providing and Fixing of windows made of pre-painted steel (Base steel as per IS 513 of 0.6mm thick galvanized as per
IS 277 with Zinc of 120 GSM). Primer coated with epoxy primer of 5-7 microns thick, finish painted with a polyester
paint of 12-16 microns thick and back coated with 5-7 microns thick alkyd backer. Section for outer frame should be
of 48x50mm, centre mullion should be of 48x50mm, section for shutter should be of 47x20mm and Fixed glass
beading section should be of 12x12mm. Outer frame and mullions to have rebate for Glazed shutter and a 20mm
provision for Guard bars/Grills.
The Sections are to be cut to length metre jointed with corner bracket. Centre mullion is to be fixed with mullion cap.
Seccolor Handle,seccolar stay, 2 nos of stainless steel heavy duty pivot hinges shall be provided per shuter. The
windows should be panelled with 5 mm thick plain float glass. Rubber gaskets are provided all around the glass. The
above frames should be fixed to the concrete/masonry wall by means of self expanding screws including 10mm
square guard bars with 6" (152.4 mm) pitch etc. complete for finished item of work.
a Double shutter Window with vertical member 40 x 40 (1219.2mm x 1219.2mm) outer frame section size of
48x50mm shutter frame section size of 47x20mm and mullion section should be of 48x50mm.
Rate as per SSR Item No. 742/62-BMT-P.25 1 Sqm 4806.00 1 Sqm 4806.00
over heads & contractors profit 14% 672.84
Total 5478.84
Sq.m
b Centre fixed both side openable shutter window 50x40 (1524mm x1219.2mm). Outer frame section size of
48x50mm. Shutter frame section size of 47x20mm. Mullion section size of 48x50mm. Fixed beading section size of
12x12mm.
Rate as per SSR Item No. 743/62 BMT-P.26 1 Sqm 4240.00 1 Sqm 4240.00
Total 4833.60
Rate per 1 Sqm Rs 4833.60
Sq.m
71 NCL or Equivalent ECO 4000 SERIES WINDOWS (SUITABLE FOR RESIDENTIAL BUILDINGS WITH GRILL & FLYMESH
PROVISION) Providing & Fixing of windows made of pre-painted steel (Base Steel as per IS 513 of 0.6mm thick
galvanized as per IS 277 with zinc of 150 GSM). Primer coated with epoxy primer of 5-7 microns thick, finish painted
with a polyester paint of 12-16 microns thick and back coated with 5-7 microns thick alkyd backer. Section for outer
frame should be of 72x55mm, centre mullion should be of 72x50mm, Section for fixed glass beading section should
be of 12x12mm and section for shutters should be of 47x20mm. Outer frame & mullion sections to have rebate for
glazed shutters, fly mesh and a 20mm provision for guard bars/grills. Fly mesh shutter section should be of
20x40mm. The sections are to be cut to length metre joined with corner bracket. Centre mullions are to be fixed with
mullion cap, seccolor stay, seccolor handles, seccolor latch 2 Nos of heavy duty stainless steel pivot hinges shall be
provided per Shutter.
The windows should be panelled with 5 mm thick plain float glass and SS Mesh for fly fly mesh shutter (304 grade) .
Rubber gaskets are provided all around the glass. The above frames should be fixed to the concrete/masonry wall by
means of self expanding screws including 10mm square guard bars with 6" (152.4 mm) pitch etc. complete for
finished item of work.
Centre fixed both side openable shutter window 50x40 (1524mm x1219.2mm). Outer frame section size of
72x50mm. Shutter frame section size of 47x20mm. Mullion section size of 72x50mm. Fixed beading section size of
12x12mm.
Rate as per SSR Item No. 748/63 BMT-P.31 1 Sqm 5719.00 1 Sqm 5719.00
Buildings
Page 291 of 613
Sq.m
72 NCL or Equivalent Sliding Windows Providing and Fixing Sliding Window fabricated from Roll formed sections made
of galvanized Steel colour coated/powder coated (Base Steel as per IS 513 D quality, galvanized as per IS 277 with
zinc of 120 GM/Sq.mtr) with total coated thickness of 0.60mm. Primer coat with epoxy primer of 5-7 microns thick,
finish painted with a polyester paint of 12-16 microns thick and back coated with Alkyd backer of 5-7 microns or
powder coated with pure polyester powder up to 50-60 microns thick. Section for external frame bottom should be of
79x44mm, external frame sides and top should be of 69x24mm, guide for top and bottom should be of 69x26mm
(Stainless Steel). Section for shutter should be of 26x30mm. The windows should be panelled with 5mm thick plain
float glass. Corner bracket for internal and external frame made of glass filled nylon. Gaskets are to be made of Ethyl
Propylene Diamine Monomer (EPDM).The sections are to be cut to length, joined and assembled by means of corner
bracket.
The above frames should be fixed to the concrete/masonry wall by means of self expanding screws including 10mm
square guard bars with 6" (152.4 mm) pitch etc. complete for finished item of work.
Rate as per SSR Item No. 750/64 BMT-P.33 1 Sqm 5195.00 1 Sqm 5195.00
using Pac solvent cement adhesive and 10 mm (5mmx2) thick, 20 mm wide cross pac sheet to be fitted as gap insert for top
and bottom rail etc. complete as per direction of Engineer in charge manufaturer specification and drawing.
Rate as per SSR Item No.645, Pg 38 -BMT- 1 Sqm 2450.00 1 Sqm 2450.00
N.04
over heads & contractors profit 14% 343.00
Total 2793.00
Rate per 1 Sqm Rs 2793.00
Sq.m
74 BMT-N.31
Doors Frames (Colour Coated Steel Sections) & Shutter using Cement Bonded Particle Board as per IS 14276 (Bison
Panel or Equivalent) : Providing and fixing of door frame made from cold roll formed sections made of galvanized
(Base steel as per IS277 with zinc of 120 Gms/sqm) colour coated steel sections with total coated thickness of 1mm,
primer coated with epoxy primer coat of 5-7 microns thick, finish paint with polyester paint of 12-16 microns. The
Section for door frame is to be filled with polyurethane (P.U) form of 40kg/m3. Overall size of frame section should be
of 50mm x 50mm. With necessary corner brackets, stiffeners, hinges, and screws. Cement Bonded particle board
shutter (Bison Panel or Equivalent) Single Leaf with all round styles U section of size 12m x 18m x 12mm made
from 0.6 mm thick galvanized, colour coated cold rolled steel profiles with 16mm thick Cement Bonded particle Board
(Bison Panel or Equivalent) with necessary screws fixed at every 1-0 (304.8mm) intervals. The cost inclusive of MS
nickel coated Aldrop of size 250mm long 2nos. 200mm long tower bolt 1no., 125mm handles 2nos.,
cost and conveyance of all materils at site and applying one coat of primer, one coat of luppum and two coats of
sythetic enamel paint as per approved design for finished item of work
Rate as per SSR Item No.673/48 BMT-N.31 1 Sqm 2558.00 1 Sqm 2558.00
over heads & contractors profit 14% 358.12
Total 2916.12
Rate per 1 Sqm Rs 2916.12
Sq.m
75 BMT-F.30
Supplying & fixing collapsible steel shutters with vertical, double channel of 20 x10x2 mm of 100 mm centre, Bracers
with flat iron 40x40x6 mm with 38 mm dia steel pulleys, the top, bottom and side vertical frames of the collapsible
gate with 65x65mmx8mm MS Angle and middle guide rail at site height with 65mmx8mm MS flat for the pulleys to
guide and fixed with necessary hold fasts, bolts, nuts, rivets, locking arrangements, stoppers, handles, all
accessories all fixtures and painted with one coat of approved steel primer etc., complete for finished item of work as
per special spn 1105
Buildings
Page 292 of 613
Rate as per SSR Item No. 156, Pg 17 -BMT- 1 Sqm 2187.00 1 Sqm 2187.00
F.30
over heads & contractors profit 14% 306.18
Total 2493.18
Rate per 1 Sqm Rs 1995.00
Sq.m
76 BMT-P.44
ELIXIR SUPER SERIES OR EQUIVALENT PRE-PAINTED STEEL WINDOWS/VENTILATORS
Supply and fixing of Ventilators : Top hung 4-0 x 2-0 (1219.2 x 609.6mm) outer frame section size of 46 x 52 mm
and shutter frame section size of 46x46mm and mullion section size of 46 x70 mm
Rate as per SSR Item No. 756 Pg 57 -BMT-P.44 1 Sqm 4992.00 1 Sqm 4992.00
Sq.m
76 Supplying and fixing of WINDOWS with Prelaminated Cement Bonded Particle boards and Pre-Painted Steel Sections
fabricated from pre-painted Cold rolled formed sections made of galvanized steel color coated sections (Base steel as per IS-
512 D quality, galvanized as per IS-277 with Zinc of 120 gram/sqm) with total coated thickness of 0.58mm primer coated with
epoxy primer of 5- 7 microns thick, finish painted with polyester paint of 12-16 microns and back coated with alkyd backer of 5-
7 microns), sections for outer frame and centre mullion (duly filled with PU form of 40 kg/Cum) of 60mm x 50mm, with
provision for fixing glazed shutter and the section for glazed/paneled of size 48 mm x 25 mm and another section of size 60
mm x 23 mm provided for separating glazed and paneled portion, the section cut to length and miter jointed with plastic corner
brackets and with corner brackets for window outer frames of 50mm x 60mm, the mullion section fixed to the frame with plastic
mullion cap and stiffener plates of size 60 mm x 50 mm made of 1.25mm thick CRCA electroplated provided to fix window
frames to concrete/masonry, gasket for fixing glass and 10mm both sides pre-laminated cement bonded particle board and 5
mm thick colour pin headed glass provided for glazing and providing guard bars of 10 mm square rods duly welded at 150 mm
pitch to MS flat section of size 18 mm and 3 mm thick, and fixed to wall by means of self expansion nylon Cap (75) and
electroplated wooden screws of size 100 mm, together with aluminum powder coated fittings, A) 75mm long grip handles 1 no
per shutter, B) 75 mm long tower bolts 2 nos. per shutter, C) Heavy duty SS Pivot hinges 2 nos per shutter, D) MS Powder
coated telescopic stay 1 no per shutter.
Rate as per SSR Item No. 737 Pg 66 -BMT-P.05 1 Sqm 3413.00 1 Sqm 3413.00
Buildings
Page 293 of 613
Rate as per SSR Item No. 735 Pg 65 -BMT-P.03 1 Sqm 4226.00 1 Sqm 4226.00
Sq.m
78 Supplying and fixing of MS Grill for windows using 35x35x5 mm MS angle alround and 10mm MS square bars
horizontally at 125mm centre to centre and vertically at 30cm centre to centre including fixing with 4 Nos of MS Z
holdfasts (2 on each side) duly making cutting brick masonry, fixing and making to original surface neatly and
painting grill with one coat of red oxide primer including and conveyance of all materials ,cutting, bending, welding
including all operational charges and all labour charges etc., complete for finished item of work.
Cutting Holes in Brick masonry and repiars -Labour 82.00 Each 4.00 Nos 328.00
Charges BMW-I.44 -pg.124
Sub Total 2617.82
Over heads & Contractors profit 14% 366.49
Total (Cost of 2.25 Sq.m Grill) Rs. 2984.31
Rate per Sq.m of Grill Rs. 1326.36
Rate per 1 Sqm Rs. 1326.36
Sq.m
79 S&F of HYSD/TMT Reinforcemt (Lap Splicing)
Buildings
Page 294 of 613
S&F HYSD/TMT/MS steel bars (Fe 415/500 Grades) of different dias. for RCC Works including labour charges for
straightening, cutting, bending to required sizes and shapes, placing in positioin with cover blocks of approved
materials and size and tying and lap slicing with binding wire of 18 SWG , forming grills for reinforcement work as per
approved designs and drawings including cost and conveyance of steel bars, including all wastages such as
overlaps, couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks and all
incidental, operational, labour charges such as cutting, bending, placing in position, tying including sales and other
taxes on all materials etc. compete for finished item of work in all floors.
Unit : 1.0 MT
(a) Material
HYSD bars including 5 per cent for overlaps and 1.05 Ton 30246.02 1 Ton 31758.32
wastage
Binding wire- 6.00 kg 70.00 1 kg 420.00
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Blacksmith / Bar bender 10.00 Day 437.50 1 day 4375.00
Mazdoor (Unskilled) 10.00 Day 350.00 1 Day 3500.00
Sub Total 40053.32
Over heads & Contractors profit 14% 5607.46
Total per MT 45660.79
Rate per Kg 45.66
Kg
Unit : 1.0 MT
(a) Material
HYSD bars including 2.5 per cent for overlaps and 1.03 Ton 30246.02 1 Ton 31002.17
wastage
Binding wire- 3.00 kg 70.00 1 kg 210.00
Welding Electrodes @ 5# per Joint & 14 Joints per 70.00 Each 12.00 1 Each 840.00
tonne
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Blacksmith / Bar bender 10.00 No 437.50 1 No 4375.00
Mazdoor (Unskilled) 10.00 No 350.00 1 No 3500.00
Sub Total 39927.17
Over heads & Contractors profit 14% 5589.80
Total per MT 45516.97
Rate per Kg 45.52
Kg
Buildings
Page 295 of 613
Buildings
Page 296 of 613
Buildings
Page 297 of 613
B. LABOUR
Carpenter II class 0.84 day 400.00 1 day 336.04
Man mazdoor (beldar) 0.91 day 350.00 1 day 318.70
For primer painting one coat 0.00
Painter 0.06 day 437.50 1 day 26.80
Mazdoor (coolie) 0.06 day 350.00 1 day 21.44
For two coats of painting to over laps 0.00
Painter 0.14 day 437.50 1 day 59.99
Mazdor (coolie) 0.14 day 350.00 1 day 47.99
Sub Total Rs 6248.32
Over heads & Contractors profit 14% 874.76
Grand Total 7123.08
Rate per 10 sqm Rs 712.31
Rate per 1 Sq.m- 0.63 mm thick (as laid) Rs 712.31
Sq.m
Output : 20.20 Rm
Corrugated, Serrated Ridges/Hips 21.50 Rm 174.00 1.00 Rm 3741.00
Conveyance & Sundries LS 10.00
Carpenter 1st Class 0.14 day 437.50 61.25
Carpenter 2nd Class 0.55 day 400.00 220.00
Buildings
Page 298 of 613
RM
Buildings
Page 299 of 613
(a) A. MATERIALS:
6 mm thick Non Asbestos High Impact Poly 11.50 Sqm 235.00 1 Sqm 2702.50
Propylene Sheets
Polymer coated 8 mm dia J or 'L" bolts & nuts 22.03 nos 9.00 1 nos 198.24
(b) Extra for Providing Wind Ties over Non Asbestos HIPP reincorced cement Corrugated Sheets
Output: 30 Rm
Cost of 40x6 mm MS Flat including Wastage 59.50 Kg 35.00 1.00 Kg 2082.50
Carpenter 1st class 0.50 day 437.50 1.00 day 218.75
Man Mazdoor 0.50 day 350.00 1.00 day 175.00
Conveyance & Sundreis LS 20.00
Sub Total 2496.25
Over heads & Contractors profit 14% 349.48
Total Rate for 30 Rm 2845.73
Rate per RM 94.86
RM
(c ) Extra for Supply, fixing of Non Asbestos High Impact Poly Propylene reinforced cement Corrugated , Serrated
adjustable ridges and hips including necessary fasteners and keeping in position etc. complete
Output : 20.20 Rm
Non Asbestos HIPP Corrugated, Serrated 21.50 Rm 238.00 1.00 Rm 5117.00
adjustable Ridges/Hips
Conveyance & Sundries LS 10.00
Carpenter 1st Class 0.14 day 437.50 61.25
Carpenter 2nd Class 0.55 day 400.00 220.00
Polymer coated 8 mm dia J or 'L" bolts & nuts or 22.03 nos 9.00 1 nos 198.24
Self Drilling Fasteners
G.I washers- BMS-W.65 - Sl No-925,Pg 73 22.03 nos 1.00 1 nos 22.03
Bitumen washers - BMS-W.67 - Pg 73 22.03 nos 0.30 1 nos 6.61
B. LABOUR
Carpenter II class 0.43 day 400.00 1 day 172.88
Man mazdoor 0.54 day 350.00 1 day 189.17
Sub Total Rs 5487.93
Over heads & Contractors profit 14% 768.31
Grand Total 6256.24
Rate per 1 Sq.m as Laid Rs 625.62
Rate per 1 Sqm(as Laid) Rs 625.62
Sq.m
85 BLD-CSTN-8-11-(86)
RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire mesh & nominal reinforcement as directed by
Engineer-in-charge with dubara sponge finishing, including cost & conveyance of all materials to site, seigniorage
charges, sales & other taxes on all materials, operational & incidental, cost and conveyance of cement, wire mesh,
water to work site, centering, scaffolding and form work, lift charges etc., complete for finished items of work but
excluding cost of steel & its fabrication charges, for finished item of work. (APSS No.403 & 903)
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop) 13.30 sqm 16.00 1 sqm 212.80
Cement Mortar 1:3 for 25 mm thick 0.25 cum 3803.56 1 cum 950.89
Dry Cement for making Lumps 50.00 kg 4.00 1 kg 200.00
12 mm Plastering 2 coats in 1:4 & 1:2 cm both sides 21.80 sqm 133.27 1 sqm 2905.28
Buildings
Page 301 of 613
Buildings
Page 302 of 613
UNIT 1 sqm
A) Material requirement
19 mm Thermocole sheet 600 x 600 1.00 sqm 43.00 1 sqm 43.00
Alumninium Angle 24 mm x 24 mm 0.40 RM 24.00 1 RM 9.60
Anodised Aluminium T Section 3.20 RM 32.00 1 RM 102.40
GI Wire - prestraightened - 2.0 mm dia 1.28 RM 9.00 1 RM 11.52
Rawl Plugs 1.28 Nos 2.00 1 Nos 2.56
B) LABOUR CHARGES
1st Class Carpenter 0.108 day 672.00 1 day 72.58
2nd Class Carpenter 0.108 day 567.00 1 day 61.24
Power Saw - Hand Operated - Operator 0.020 day 623.00 1 day 12.46
Power Drill - Hand Operated - Operator 0.040 day 721.00 1 day 28.84
Unskilled Mazdoor 0.200 day 350.00 1 day 70.00
C) Machinery
Power Saw-- Hand Operated - Hire charges 0.16 Hrs 117.00 1 Hrs 18.72
Power Drill - Hand Operated - Hire Charges 0.32 Hrs 108.00 1 Hrs 34.56
467.47
Scaffolding charges 1% 4.67
Sub Total 472.15
Over heads & Contractors profit 14% 66.10
Total 538.25
Rate per 1 sqm Rs 538.25
Sq.m
87 Armstrong Fine Line Grid False Ceiling- 15mm thick
Providing and fixing in true horizontal level 600 mm x 600 mm 15 mm thick Arm strong false ceiling system
manufactured by M/s Arm strong world Industries using hot dipped Galvanised Steel section exposed surface with
pre-coated capping, main Tee of size 24 x 32 mm at every 1200 mm c/c maximum and rotary stiched cross tee of size
24 x 27 mm at evry 600 mm c/c and sub-cross tee of size 24 mm x 25 mm at 1200 mm c/c and wall angle of size 19 x
19 mm fixed to periphery of the wall and the above grid is suspended at every 1200 mm c/c in both directions using
2.0 mm thick pre-straightened GI Wire laying fine fissured butt edge ceiling tiles of 15 mm thick mineral fiber Board
manufactured by M/s Arm Strong World Industries Ltd., having RH 99% and for finished of size 600 x 600 mm
including Cost &conveyance of all materials and labour charges such as cutting , fixing of standing of frame work
exposing roof making complete for finished item of work
UNIT 1 sqm
A) Material requirement
15 mm - Armstrong Mineral Fiber sheet 600 x 600 1.00 sqm 479.00 1 sqm 479.91
Buildings
Page 303 of 613
Unit: 1 Sq.m
A) Material requirement
1219x1829 mm Gyp Boards 1.03 sqm 232.00 1 sqm 238.96
GI Ceiling angle 25x10x0.55mm 0.64 RM 69.00
GI Ceiling Section 51.5x26x10.5x0.55 mm 0.84 RM 79.00 1 RM 66.36
Intermediate Channel 45x15x15x0.9mm 0.84 RM 78.00
Perimeter Channel:20x27x30x0.55mm 0.40 RM 69.00 1 RM 27.60
Connecting Clips 1.84 Nos 2.00
Rawl Plugs 0.64 Nos 2.00 1 RM 1.28
Drywall screws-25mm 18.00 Nos 2.00
Jointing paper tape 1.46 RM 5.00 1 RM 7.28
Drywall top coat 0.15 Lit 133.00 1 Nos 19.95
B) LABOUR CHARGES
1st Class Carpenter 0.12 day 672.00 1 day 80.64
2nd Class Carpenter 0.12 day 567.00 1 day 68.04
1st Class Painter 0.024 day 672.00 1 day 16.13
2nd Class Painter 0.024 day 567.00 1 day 13.61
Power Saw - Hand Operated - Operator 0.012 day 623.00 1 day 7.48
Power Drill - Hand Operated - Operator 0.024 day 721.00 1 day 17.30
Unskilled Mazdoor 0.072 day 350.00 1 day 25.20
C) Machinery
Power Saw - Hand Operated - Hire charges 0.32 Hrs 117.00 1 Hrs 37.44
Power Drill - Hand Operated - Hire Charges 0.64 Hrs 108.00 1 Hrs 69.12
696.39
Scaffolding charges 1% 6.96
Sub Total 703.35
Over heads & Contractors profit 14% 98.47
Total 801.82
Rate per 1 sqm Rs 801.82
Sq.m
89 Gypboard Fine Line Grid False Ceiling-12.5 mm thick
Supplying and Fixing Gyp Board Fine Line Grid False Ceiling (GS_FLC-4.6 as per India Gypsum) in size 600 x 600 mm
using 12.5mm thick Gyp Board sheet tiles of 595 x 595 mm or 595x 1195 mm conforming ti IS-2095 and fixing to Gyp
steel precoated GI wall angle of size 25x25x0.7 mm thick along perimeter of and ceiling screws fixed to
Brickwork/partition at 610 mm c/c and suspending the frame work using pre coated GI Tee section (24x38x0.7 mm)
from soffit at 1220 mm c/c fixed with GI Soffit cleat, rawl plugs and steel expansion fasteners and connecting clip to
the GI T-Section with 4mm dia GI Rod with Galvanized spring steel level clip of PVC universal holding clip system at
1200 mm c/c and fixing the 12.5 mm Gypboard sheet tiles of size 595x595 or 595x1195 mm and finishing with two
coats of drywall topcoat complete for finished item of work as per India Gypsum Ltd. specification
Unit: 1 Sq.m
A) Material requirement
12.5mm thick Gyp Board Tiles 1.00 sqm 249.00 1 sqm 249.00
GI Precoated angle 25x25x0.7 mm 0.40 RM 38.00
GI Precoated T-Section 24x38x0.7 mm 3.20 RM 50.00 1 RM 160.00
GI Rod-4mm dia connecting Road 1.28 RM 11.00
Rawl Plugs 1.28 Nos 2.00 1 RM 2.56
Soffit Cleats 1.28 Nos 2.00
Universal Holding Clips 5.36 Nos 2.00 1 RM 10.72
Drywall Top Coat 0.15 Lit 133.00
B) LABOUR CHARGES
1st Class Carpenter 0.12 day 672.00 1 day 80.64
2nd Class Carpenter 0.12 day 567.00 1 day 68.04
1st Class Painter 0.024 day 672.00 1 day 16.13
2nd Class Painter 0.024 day 567.00 1 day 13.61
Power Saw - Hand Operated - Operator 0.012 day 623.00 1 day 7.48
Power Drill - Hand Operated - Operator 0.012 day 721.00 1 day 8.65
Unskilled Mazdoor 0.072 day 350.00 1 day 25.20
C) Machinery
Power Saw- Hand Operated - Hire charges 0.32 Hrs 117.00 1 Hrs 37.44
Power Drill - Hand Operated - Hire Charges 0.32 Hrs 108.00 1 Hrs 34.56
714.02
Buildings
Page 304 of 613
Buildings
Page 305 of 613
RM
Buildings
Page 306 of 613
91 IRR-CCDW1-8 :
Providing and fixing 2.50 m long cold twisted deformed steel Anchor rods with 1.50m length driven in to the hole
drilled in bed rock and remaining length embedded in concrete/ masonry including cost of all materials, machinary,
labour, drilling and cleaning hole, driving Anchore rod, grouting hole with thick cement slurry etc, with intial lead up
to 50m and all lifts.
a Unit - 10 Nos
A) MATERIALS
25mm dia Steel (including 5% Wastage) 10 Nos 101.00 Kg 30.00 1 Kg 3030.00
of 2.50m length
Drilling of 36mm dia holes by Pneumatic 15 RM 120.00 1 RM 1800.00
Compressor Sl No.143 Pg No. 19
Grouting 36mm dia holes with neat cement slurry Sl 15 RM 109.50 1 Nos 1642.50
No.146 Pg No. 19
B) LABOUR CHARGES
Bar Bender 0.50 day 437.50 1 day 218.75
Mason 2nd class 0.50 day 567.00 1 day 283.50
Mazdoor (unskilled) 1.00 day 350.00 1 day 350.00
Sub Total Rs 7324.75
Over heads & Contractors profit 14% 1025.47
Grand Total 8350.22
Rate per 10 Nos. Rs 8350.22
Rate per Each 25mm Dia Anchoring Rs 835.02
Each
b Unit - 10 Nos
A) MATERIALS
20mm dia Steel (including 5% Wastage) 10 Nos of 65.00 Kg 30.00 1 Kg 1950.00
2.50m length
Drilling of 25mm dia holes by Pneumatic 15 RM 105.00 1 RM 1575.00
Compressor Sl No.142 Pg No. 19
Grouting 25mm dia holes with neat cement slurry Sl 15 RM 89.00 1 RM 1335.00
No.145 Pg No. 19
B) LABOUR CHARGES
Bar Bender 0.50 day 437.50 1 day 218.75
Mason 2nd class 0.50 day 567.00 1 day 283.50
Mazdoor (unskilled) 1.00 day 350.00 1 day 350.00
Sub Total Rs 5712.25
Over heads & Contractors Profit 14% 799.72
Grand Total 6511.97
Rate per 10 Nos. Rs 6511.97
Rate per Each 20mm Dia Anchoring Rs 651.20
Each
c Unit - 10 Nos
A) MATERIALS
16mm dia Steel (including 5% Wastage) 10 Nos of 41.50 Kg 30.00 1 Kg 1245.00
2.50m length
Drilling of 20mm dia holes by Pneumatic 15 RM 110.00 1 RM 1650.00
Compressor Sl No.141 Pg No. 19
Grouting 20mm dia holes with neat cement slurry Sl 15 RM 71.00 1 RM 1065.00
No.144 Pg No. 19
B) LABOUR CHARGES
Bar Bender 0.50 day 437.50 1 day 218.75
Mason 2nd class 0.50 day 567.00 1 day 283.50
Mazdoor (unskilled) 1.00 day 350.00 1 day 350.00
Total Rs 4812.25
over heads & contractors profit 14% 673.72
Grand Total 5485.97
Rate per 10 Nos Rs 5485.97
Rate per Each 20mm Dia Anchoring Rs 548.60
Each
Buildings
Page 307 of 613
Output: 100 RM
Materials:
Galvanised steel barbed wire IS type I weighing 15.500 Kg 77.00 1 Rmt 1193.50
0.155 kg/Rm : M-063
Carriage of barbed wire.
G.I. staples steel pins or binding wire @10% 10% 119.35
Labour :-
For fixing & stretching wire
Blacksmith, 1st Class 0.150 No 437.50 1 No 65.63
Blacksmith, 2nd Class 0.150 No 567.00 1 No 85.05
Mazdoor (male). 0.300 No 350.00 1 No 105.00
Sub Total 1568.53
Over heads & Contractors profit 14% 219.59
Cost for 100 m of Fixing Barbed Wire 1788.12
Rate per 1RM Rs 17.88
RM
Buildings
Page 308 of 613
b) 90 mm OD SWR Type"B"
Cost of 3.0m S/S Pipe 1 Rm 232.00 1 Rm 232.00
Add for Fittings Bends,Tees,Couplers etc 20% 232.00 46.40
Labour Charges for Fixing 1 Rm 58.00 1 Rm 58.00
MAA on labour 25% 58.00 14.50
Sub Total 350.90
OH&CP @ 14% 350.9 49.13
90 mm OD,SWR"Type B", Rate/Rm 400.03
Rm
Buildings
DETAILED ESTIMATE OF THE DR. BR AMBEDKAR BHAVAN (PHASE - I) AT GODAVARIKHANAI,
PEDDAPALLI DISTRICT.
ABSTRACT ESTIMATE
5 RCC- M 20 Grade:
BLD-CSTN-3-13-(30) - A
Supply and placing of the M-20 Design Mix Concrete
corresponding to IS 456 using WEIGH BATCHER / MIXER with
20mm size graded machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and conveyance of
all materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour
charges such as weigh batching, machine mixing, laying concrete,
curing etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)with minimum
cement content as per IS code for Structural Components.
b R.C.C.Lintels:
RCC M20 for Lintels up to 3.66m un-supported height above GL-
Steel Scaffolding & Centering.
R.C.C.Lintels for Each DU: 1.00 47.72 Cum
7 S&F of HYSD/TMT Reinforcemt (Lap Splicing):
S&F HYSD/TMT/MS steel bars (Fe 415/500 Grades) of different
dias. for RCC Works including labour charges for straightening,
cutting, bending to required sizes and shapes, placing in positioin
with cover blocks of approved materials and size and tying and lap
slicing with binding wire of 18 SWG , forming grills for reinforcement
work as per approved designs and drawings including cost and
conveyance of steel bars, including all wastages such as overlaps,
couplings, chairs, spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental, operational, labour
charges such as cutting, bending, placing in position, tying including
sales and other taxes on all materials etc. compete for finished item
of work in all floors..
@ 120 Kgs per CMt 1.00 3141.06 1.00 120.00 376927.80 Kgs
East-West Wall
Shops 1.00 43.29 0.23 3.00 29.87 Cum
16.00 2.40 0.23 3.00 26.50 Cum
East-West Wall
Shops 1.00 43.29 0.23 2.70 26.88 Cum
16.00 2.40 0.23 2.70 23.85 Cum
East-West Wall
Shops 1.00 43.29 0.23 2.70 26.88 Cum
16.00 2.40 0.23 2.70 23.85 Cum
10 Plastering in CM(1:6) & CM(1:4) Base & Top Coats, 20mm th (16 & 4 mm) (External)
BLD-CSTN-8-9-(84)
Plastering 20mm thick two coats with base coat of 16mm thick in
C.M. (1:6) and top coat of 4mm thick in C.M. (1:3) with dubara
sponge finishing including cost & conveyance of all materials like
cement, Sand, Water, etc., to site, seigniorage charges, all
operational, including charges, labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing, including cutting grooves
where ever necessary etc., complete for finished item of work of
uneven surfaces of walls. (External walls)
East-West Wall
Shops 1.00 43.29 - 3.75 162.35 Smt
Auditorium
Auditorium Toilets 1.00 6.90 - 5.10 35.19 Smt
-1.00 1.20 - 2.10 -2.52 Smt
Auditorium Long Walls 2.00 74.70 - 5.10 761.89 Smt
Less doors -6.00 1.20 - 2.10 -15.12 Smt
-1.00 0.90 - 2.10 -1.89 Smt
Staircase walls 2.00 5.40 - 5.10 55.08 Smt
East-West Wall
Shops 1.00 43.29 - 3.45 149.36 Smt
East-West Wall
Shops 1.00 43.29 - 3.75 162.35 Smt
Auditorium
Auditorium Toilets 1.00 6.90 - 5.50 37.95 Smt
-1.00 1.20 - 2.10 -2.52 Smt
Auditorium Long Walls 2.00 74.70 - 5.50 821.65 Smt
Less doors -6.00 1.20 - 2.10 -15.12 Smt
-1.00 0.90 - 2.10 -1.89 Smt
Staircase walls 2.00 5.40 - 5.50 59.40 Smt
Auditorium
North-South Wall 2.00 25.00 - 5.25 262.50 Smt
Bride & Groom Rooms 8.00 3.89 - 5.25 163.26 Smt
Auditorium Toilets 1.00 6.10 - 5.25 32.01 Smt
1.00 2.74 - 5.25 14.41 Smt
Less Doors -1.00 1.20 - 2.10 -2.52 Smt
-1.00 0.90 - 2.10 -1.89 Smt
Dinning Hall
Kitchen & Toilet 2.00 18.29 - 5.25 192.07 Smt
Less Doors -6.00 1.20 - 2.10 -15.12 Smt
Hand Wash & Stores 2.00 5.03 - 5.25 52.82 Smt
Less Doors -4.00 1.20 - 2.10 -10.08 Smt
East-West Wall
Shops 1.00 43.29 - 3.60 155.85 Smt
32.00 2.40 - 3.60 276.48 Smt
East-West Wall
Shops 1.00 43.29 - 3.30 142.87 Smt
32.00 2.40 - 3.00 230.40 Smt
Auditorium
North-South Wall 2.00 25.00 - 5.40 270.00 Smt
Bride & Groom Rooms 8.00 3.89 - 5.40 167.93 Smt
Auditorium Toilets 1.00 6.10 - 5.40 32.93 Smt
1.00 2.74 - 5.40 14.82 Smt
Less Doors -1.00 1.20 - 2.10 -2.52 Smt
-1.00 0.90 - 2.10 -1.89 Smt
Dinning Hall
Kitchen & Toilet 2.00 18.29 - 5.40 197.56 Smt
Less Doors -6.00 1.20 - 2.10 -15.12 Smt
Hand Wash & Stores 2.00 5.03 - 5.40 54.33 Smt
Less Doors -4.00 1.20 - 2.10 -10.08 Smt
East-West Wall
Shops 1.00 43.29 - 3.30 142.87 Smt
32.00 2.40 - 3.30 253.44 Smt
Auditorium 4.00 5.40 - 5.40 116.64 Smt
Less Doors -4.00 0.90 - 2.10 -7.56 Smt
Auditorium Toilets 2.00 6.90 - 5.40 74.52 Smt
-2.00 1.20 - 2.10 -5.04 Smt
Auditorium Long Walls 1.00 74.70 - 5.40 403.35 Smt
Less doors -6.00 1.20 - 2.10 -15.12 Smt
-1.00 0.90 - 2.10 -1.89 Smt
Auditorium Kitchen walls 6.00 5.40 - 5.40 174.96 Smt
-3.00 0.90 - 2.10 -5.67 Smt
Staircase walls 2.00 5.40 - 5.40 58.32 Smt
One Coat of Cement Primer & Two Coats of Acrylic Distemper for
Internal Walls & Ceiling: 1.00 17584.35 S.Mt.
Wall Plastering: 8064.49 S.Mt.
Internal Plastering Area to be taken-Ground Floor 1.00 1.00 1.00 1.00 3270.56 S.Mt.
Internal Plastering Area to be taken-First Floor 1.00 1.00 1.00 1.00 1635.21 S.Mt.
Internal Plastering Area to be taken-Second Floor 1.00 1.00 1.00 1.00 3158.71 S.Mt.
Ceiling Plastering: 9519.86 S.Mt.
Ceiling Plastering to be taken-Ceiling Floor 1.00 1.00 1.00 1.00 3060.00 S.Mt.
Ceiling Plastering to be taken-Ground Floor 1.00 1.00 1.00 1.00 3060.00 S.Mt.
Ceiling Plastering to be taken-First Floor 1.00 1.00 1.00 1.00 811.68 S.Mt.
Ceiling Plastering to be taken-Second Floor 1.00 1.00 1.00 1.00 2736.00 S.Mt.
Less Vent Shafts 1.00 1.00 1.00 1.00 -147.82 S.Mt.
B. Skirting:
1.00 297.81 S.Mt.
Total Quantity of Skirting: (Gr.Floor) 1.00 110.65 S.Mt.
Shops 32.00 7.20 3.6 0.12 41.47 S.Mt.
32.00 1.35 1.2 0.12 9.79 S.Mt.
Corridor 2.00 10.82 52.13 0.12 15.11 S.Mt.
2.00 1.95 66.46 0.12 16.42 S.Mt.
2.00 6.00 8.00 0.12 3.36 S.Mt.
Auditorium
2.00 18.00 67.99 0.12 20.64 S.Mt.
Kitchen 2.00 10.67 5.40 0.12 3.86 S.Mt.
Flooring with High Strength CC Designer Tiles 30 mm thick 1.00 3600.00 S.Mt.
Cellar 1.00 36.00 100 1.00 3600.00 S.Mt.
First Floor
D1: 16.00 3.00 7.00 1.00 336.00 S.Mt.
Second Floor
MD: 14.00 1.95 2.10 1.00 57.33 S.Mt.
D 4.00 0.90 2.10 1.00 7.56 S.Mt.
D1: 19.00 3.00 7.00 1.00 399.00 S.Mt.
First Floor
V1 16.00 0.90 0.61 1.00 8.78 S.Mt.
Second Floor
W1 24.00 1.80 1.35 1.00 58.32 S.Mt.
W2 4.00 1.20 1.35 1.00 6.48 S.Mt.
W2k 2.00 1.20 1.35 1.00 3.24 S.Mt.
V1 26.00 0.90 0.61 1.00 14.27 S.Mt.
14 M.S. GRILL:
Supplying and fixing of MS Grill for windows using 35x35x5 mm MS
angle alround and 10mm MS square bars horizontally at 125mm
centre to centre and vertically at 30cm centre to centre including
fixing with 4 Nos of MS Z holdfasts (2 on each side) duly making
cutting brick masonry, fixing and making to original surface neatly
and painting grill with one coat of red oxide primer including and
conveyance of all materials, cutting, bending, welding including all
operational charges and all labour charges etc., complete for
finished item of work.
b R.C.C.Lintels:
RCC M20 for Lintels up to 3.66m un-supported height
above GL-Steel Scaffolding & Centering.
R.C.C.Lintels for Each DU: 47.72 Cum 8922.35
e) Granite Work:
52 mm thick cement concrete flooring with concrete
hardener topping under layer 40 mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20 mm nominal size) and top layer 12
mm thick cement hardener consisting of mix 1:2 (1
cement hardener mix : 2 graded stone aggregate 6 mm
nominal size) by volume hardening compound is mixed
@ 2 litre per 50 kg of cement or as per manufacturers
specifications. This includes cost of cement slurry but
excluding the cost of nosing of steps etc. complete.
13 a). Teak Wood Frame with 30mm thick Teak wood Shutters:
Supply , Delivey and Fixing of Teak wood Frame Size
of 100x100 with 30mm thick Teak wood door shutters
including cost of wooden reapers, butt hinges, Tower
bolts, Aldrops and all other wind appliances etc.
complete for finished item of Work.
1263.78 S.Mt. 6150.00
13 b). NCL WINDOWS:
NCL or Equivalent Sliding Windows Providing and Fixing
Sliding Window fabricated from Roll formed sections
made of galvanized Steel colour coated/powder coated
(Base Steel as per IS 513 D quality, galvanized as per
IS 277 with zinc of 120 GM/Sq.mtr) with total coated
thickness of 0.60mm. Primer coat with epoxy primer of
5-7 microns thick, finish painted with a polyester paint of
12-16 microns thick and back coated with Alkyd backer
of 5-7 microns or powder coated with pure polyester
powder up to 50-60 microns thick. Section for external
frame bottom should be of 79x44mm, external frame
sides and top should be of 69x24mm, guide for top and
bottom should be of 69x26mm (Stainless Steel). Section
for shutter should be of 26x30mm. The windows should
be panelled with 5mm thick plain float glass. Corner
bracket for internal and external frame made of glass
filled nylon. Gaskets are to be made of Ethyl Propylene
Diamine Monomer (EPDM).The sections are to be cut to
length, joined and assembled by means of corner
bracket.
ELECTRICAL WORKS @ 8% Rs
PLUMBING WORKS @ 6% Rs
Grand Total Rs
KAR BHAVAN (PHASE - I) AT
TRICT.
AMOUNT IN RUPEES
550382.94
77581.99
35377.81
228967.93
56383242.89
4435629.14
2022085.65
9035678.19
14571706.23
97185.94
425754.35
17156612.79
1112967.10
1470041.11
302037.99
811186.55
1018827.41
5283812.17
10914808.46
377614.44
1782544.86
2484000.00
187500.00
7772247.00
1026997.89
882288.58
140,447,079.42
11,235,766.35
8,426,824.77
160,109,671
Page 334 of 613
Door&Window
CEMENT MORTARS WITH OP CEMENT
Qty Rate Per Amount
a CEMENT MORTAR (1:1)
Cement 1440 Kg 5.53 1.00 Kg 7966.68
Sand 1.05 Cum 1000.00 1.00 Cum 1050.00
Man mazdoor 0.2 Day 490.00 1.00 Day 98.00
Rate per cu.m. Rs 9114.68
Cu.m
b CEMENT MORTAR (1:1.5)
Cement 960.00 Kg 5.53 1.00 Kg 5311.12
Sand 1.05 Cum 1000.00 1.00 Cum 1050.00
Man mazdoor 0.20 Day 490.00 1.00 Day 98.00
Rate per cu.m. Rs 6459.12
Cu.m
Mortars
Lead Statement
SSR- 2016-17
Steel & Cement Updated to
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
15 Agg. 5.6mm & Below incl. Seig- M-030 1 Cum Kannala 25 348.60 875.00
336 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
19 Agg.20mm Nom. Size Incl. Seig- M-053 1 Cum Kannala 25 348.60 1090.00
32 Agg. 63 to45mm (Gr.II) incl. Seig.- M-038 1 Cum Kannala 25 348.60 625.00
337 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
338 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
339 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
340 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
341 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
342 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
343 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
344 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
345 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
346 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
347 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
348 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
349 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
350 of 613
S# Description of Materials Unit SSR Ref Source of supply Lead in Km Lead Charge Basic Rate incl Taxes
458
459
351 of 613
t
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
352 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
Derived 1576.85
Derived 1576.10
353 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
350.00
98.00
6.00
4.10
354 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
30.00
30.50
18.00
31.00
114.00
480.00
730.00
1441.00
98.00
23.00
36.00
41.00
120.00
158.00
13.00
80.00
355 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
85.00
125.00
175.00
225.00
20000.00
6.00
4.00
266.00
10.00
190.00
130.00
88.00
10.27
150.00
187.00
231.00
460.00
350.00
100.00
167.80
310.20
54.70
1025.00
50.20
356 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
12.20
3.60
2.75
3.66
5.50
25.89
35.03
37.58
54.16
56.51
73.87
92.11
108.05
118.31
153.98
171.13
181.58
244.43
357 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
272.33
298.88
317.94
369.47
418.95
31.00
33.30
50.20
50.20
66.50
81.80
97.50
103.20
134.40
149.20
158.40
358 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
213.20
237.50
258.90
277.30
322.20
365.40
40.10
42.90
61.80
64.40
84.90
104.90
125.60
134.80
173.60
194.60
359 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
204.50
277.60
310.20
338.40
362.70
420.90
505.50
10.95
10.97
10.97
14.20
16.00
20.60
37.29
39.30
44.80
360 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
48.20
64.00
77.60
91.08
105.47
129.53
154.20
13.45
13.45
14.10
15.70
17.92
22.85
39.90
44.00
49.00
361 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
51.20
66.20
84.60
95.20
116.70
141.00
167.00
24.34
24.34
24.34
27.71
39.94
39.94
55.49
63.51
78.97
94.93
126.41
16.50
21.50
33.60
362 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
62.30
84.26
127.73
254.46
51.30
54.20
63.40
74.50
115.50
126.20
136.00
20.00
35.00
50.00
65.00
80.00
363 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
143.00
124.00
143.00
124.00
143.00
124.00
94.00
94.00
300.00
310.00
64.10
574.00
275.00
11.00
8.60
470.00
190.00
8.00
85.00
120.00
125.00
735.00
364 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
29.80
29.80
50.20
50.20
50.20
64.10
67.30
71.20
74.60
77.90
80.90
85.00
88.30
92.30
95.70
100.40
365 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
102.80
106.20
109.90
113.50
115.80
120.60
124.00
127.20
131.20
120.00
127.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
M-148 119.50 0.00 50.00 642.50
366 of 613
SSR Ref Page No. Loadg/ Unloadg. Charges MAA @ 40% on Loading & Unloading Seig. Total
367 of 613
Page 368 of 613
Material_Monthly
Page 369 of 613
LABOUR RATES
Labour_AA@40%
Page 370 of 613
Labour_AA@40%
Page 371 of 613
Labour_AA@40%
Statement showing the cost of Materials & Leads
Sl. Description Ref. to SSR unit Basic Rate Lead
No.
Lead in Lead Seig.
Km Charges
NATURAL FLOORING STONES (ex-quarry price - excluding cost of conveyance, loading & unloading)
36 Rough Kadapa slab-40mm thick size BMT-B.01/14 Sq.m 96.00 6 Km 7.10 103.10
0.45*0.45m
37 Rough Shabad/Tandur-25mm thick size BMT-B.03/14 Sq.m 96.00 6 Km 4.44 100.44
0.45*0.45m
38 Rough Shahbad/Tandur slab-40mm thick size BMT-B.04/14 Sq.m 124.00 6 Km 7.10 131.10
0.45*0.45m
39 Polished Shahbad/Tandur slab-15 to 18 mm BMT-B.05/14 Sq.m 165.00 6 Km 2.66 167.66
thick & of size 0.40*0.40m
40 Polished Black Kadapa slabs-15 mm thick BMT-B.06/14 Sq.m 138.00 6 Km 2.66 140.66
(0.45*0.45m)
41 Polished Bethemcherla white-25 mm thick BMT-B.07/14 Sq.m 386.00 6 Km 4.44 390.44
(0.25 *0.25m)
42 Polished Bethemcherla Colour-25 mm thick BMT-B.08/14 Sq.m 276.00 6 Km 4.44 280.44
(0.25 *0.25m)
43 High Polished Granite -Black-16/18 mm thick BMT-B.11/14 Sq.m 2988.00 6 Km 2.66 2990.66
upto 2.40m
44 High Polished Granite -Other than BMT-B.09/14 Sq.m 3438.00 6 Km 2.66 3440.66
Black/Premium Colors-16/18mm thick (2.40m)
45 Granite Stone Tiles 8 mm thick- mirror polished BMT-B.16/15 Sq.m 1165.00 6 Km 2.66 1167.66
of all shades
46 Polished Marble Slabs of any variety- 16/20 mm BMT-B.12/14 Sq.m 729.00 6 Km 2.66 731.66
thick size: 0.45 to 0.60m
1 The aggregate rates mentioned above are inclusive of seigniorage charges of Rs.50/ cum, blasting charges of
Rs.70/cum and 25% machine crushing charges. However , if the metal is obtained from hand broken , the blasting
and crushing charges shall be deducted. The aggregate shall be HB Stone of Granite, Dolamite, Dolerite and Trap.
( Quartzite and Basalt with aggregate Impact value of Less than 20)
LEAD CHARGES
Gravel 20.00 Km
up to 5.00 Km 1.00 84.00 84.00
5.00 to 30 Km 15.00 12.60 189.00
Above 30 Km 0.00 10.50 0.00
Total 273.00 Cum
Bricks 6.00 Km
up to 5.00 Km 1.00 123.50 123.50
5.00 to 30 Km 1.00 18.50 18.50
Above 30 Km 0.00 15.40 0.00
Total 142.00 Cum
Sl. Description Ref. to SSR unit Basic Rate Lead
No.
Lead in Lead Seig.
Km Charges
Sq.m per
AC Sheets, 6 mm thick 80.43
Tonne
Bitumen/Emulsion 190.00 Km
up to 5.00 Km 1.00 52.50 52.50
5.00 to 30 Km 25.00 7.90 197.50
Above 30 Km 160.00 6.60 1056.00
Total 1306.00 Tonne
Table: B
Note: Lead and Lift Charges are inlcusive of 14% Overheads & Contractors profit
(Lead) Conveyance Charges for Machinery per kilometer for Transportaion of Materilas by
tippers/trucks excluding Loading, Unloading and idle hire charges for machinery (Lead
Charges are inclusive of OH&CP of 14%)
PCC
Slabs/S
hababa
Coarse Cement/St
d
Earth/Sand/ Agg/Rubbl eel/AC Water per
slabs/C
Lead Charges Murrum per e/Stone/C Sheets/ tonne or 1000
C
Cum oarse Agg Packed per lits.
blocks/
per Cum Tonne
Wood
per
Cum
Upto 1 Km 31.50 30.40 19.00 44.70 18.80
Upto 2.0 Km 44.10 42.60 26.60 62.60 26.30
Upto 3.0 Km 58.80 58.80 36.70 86.50 35.00
Upto 4.0 Km 71.40 71.40 44.60 105.00 42.50
Upto 5.0 Km 84.00 84.00 52.50 123.50 50.00
For every Km beyond 5Km & upto 30 Km 12.60 12.60 7.90 18.50 7.50
For every Km beyond 30 Km 10.50 10.50 6.60 15.40 6.30
Sl. Description Ref. to SSR unit Basic Rate Lead
No.
Lead in Lead Seig.
Km Charges
Table:C
Rubble/C
Loading & Unloading by Manual oarse Steel
Earth/Snad Cement Brick per
Means (Excluding Idle hire charges per Cum
Agg/
per Tonne
per
1000 Nos
of trucks)- Labour Component Stone per Tonne
Cum
Table:D
Rubble/C
Loading and Unloading by Manual oarse Steel
Earth/Snad Cement Brick per
Means (Including idle hire charges of per Cum Agg/
per Tonne
per
1000 Nos
trucks) Stone Tonne
per Cum
Table:E
Rubble
Loading and Unloading by Earth/Sand/
/Size
Gravel/Murru
Mechanical means (Including idle m
Stone/
hire charges of trucks) Agg./ Lime
per Cum
Per Cum
Note: Lead and Lift Charges are inlcusive of 14% Overheads & Contractors profit
Table:A
Earth/Sand/
Shahbad
Gravel/Rubb Cement/
Slab/Wood
le/Stone/ Steel
Lead Charges by Head Loads Aggregate/ per
/CC
Blocks per
Moorum Tonne
Cum
per Cum
Toal lead upto 50 m (Covered by item rate) Initial Lead Initial Lead Initial Lead
Note:
Anti Corrosive Bitumen Black Paint 394 BMT-J.28 32 487.00 1 Litre 487.00
Aluminium Paint Gr-1 395 BMT-J.29 32 244.00 1 Litre 244.00
Wood Primer 371 BMT-J.05 31 135.00 1 Lits 135.00
Red Oxide Iron Primer Paint Grade - I 369 BMT-J.03 31 121.00 1 Lits 121.00
Zinc Chromate Yellow Oxide Iron Primer 370 BMT-J.04 31 175.00 1 Lit 175.00
Vitrified polished floor tiles of size not less 50 BMT-C.13 15 1225.00 1 Sq.m 1225.00
than 900*900*10 to 12 mm thickness
Vitrified polished floor tiles of size not less 52 BMT-C.15 15 1008.00 1 Sqm 1008.00
than 600x600 of 8 to 10 mm thickness
glossy finish premium colours
Materials_Others
Page 377 of 613
GI Chain Link mesh-SWG 8 (4mm)- 4"x4" 151 BMT-F.23 21 223.00 1Sq.m 223.00
Materials_Others
Page 378 of 613
Mild Steel Tubes & Pipes of all dia. 132 BMT-F.04 20 57.00 1 Kg 57.00
SS-204 Tubes,Sections, Plates, Pipes 133 BMT-F.05 20 187.00 1 Kg 187.00
SS-304 Tubes,Sections, Plates,Pipes 134 BMT-F.06 20 309.00 1 Kg 309.00
Galvanised Barbed Wire TypeA or B 135 BMT-F.07 20 77.00 1 Kg 77.00
conforming to IS-278 @0.155 Kg/Rm
Rolling Shutter made of 80x1.25mm 157 BMT-F.29 21 2500.00 1 Sq.m 2500.00
CRCA laths
Collapsible Gates with double Channels 158 BMT-F.30 21 2187.00 1 Sq.m 2187.00
of 20x10x2 mm with accessories
Door Closure Hyper Brand IS_6315 221 BMT-G.63 23 938.00 Each 938.00
Double Action SS Cover Plate Floor 222 BMT-G.64 23 1280.00 Each 1280.00
Spring Hyper brand IS-6315
Double Action Brass Cover Plate Floor 223 BMT-G.65 23 3037.00 Each 3037.00
Spring IS_6315 for Aluminium Dooor
Aluminium Anodized Sections for Doors , 891 BMS-W-01 86 300.00 1 Kg 300.00
Windows, Partitions, Ventilators
Flush Shutter Solid Bond Wood Block 672 BMT-N.16 52 771.00 1 Sq.m 771.00
Board type with Commercial ply on both
faces, 30 mm thick
Flush Shutter Solid Bond Wood Block 671 BMT-N.15 51 684.00 1 Sq.m 684.00
Board type with Commercial ply on both
faces, 25 mm thick
Sal Wood Scantlings any Length 123 BMT-E.15 19 48543.00 1 Cum 48543.00
Materials_Others
Page 379 of 613
Materials_Others
Page 380 of 613
Other Materials:
Water M-189 311 100.00 1 kL 100.00
Gelatin80% M-104 327 700.00 1 Kg 700.00
Electric Detonators (100 Nos. Rate) M-094 326 1205.00 100 Nos 1205.00
Bolts & Nuts with Double Washers PHSSR Table 36 102.00 1 Kg 102.00
Rubber Packing 3/6 mm PHSSR Table 36 85.00 1 Kg 85.00
Pig Lead 99.99% Pure PHSSR Table 36 264.00 1 Kg 264.00
Lead Wool PHSSR Table 36 139.00 1 Kg 139.00
Spun Yarn PHSSR Table 36 105.00 1 Kg 105.00
Oil Engine Driven Pumpset PHSSR Item # 27 38.00 HP-Hr 38.00
Cutting Open BT Road Surface PHSSR Item # 26 471.00 10 Sq.m 471.00
Cutting Open WBM Roads (upto 75mm PHSSR Item # 26 161.00 1 Cum 161.00
thick)
Cutting Open CC Roads PHSSR Item # 26 1309.00 1 Cum 1309.00
MD-10: 500mm dia Clear SFRC MH PHSSR Table 33 1427.00 Each 1427.00
Frame & Cover
HD-20 : 500 mm dia Clear SFRC MH PHSSR Table 33 1839.00 Each 1839.00
Frame & Cover
HD-20 : 560 mm dia Clear SFRC MH PHSSR Table 33 1972.00 Each 1972.00
rame & Cover
HD-35 : 560 mm dia Clear SFRC MH PHSSR Table 33 2113.00 Each 2113.00
Frame & Cover
Plastic Encapsulated Steps for MH's PHSSR Table 33 150.00 Each 150.00
Materials_Others
Page 381 of 613
Labour charges for fabricating all heavy BMM-V.16 85/882 18.00 7.20 Kg 25.20
steel works like Trusses, Stanchions,
Heavy Beams and Girders etc excluding
cost of fixing in position
Labour charges for fixing heavy iron BMM-V.17 85/883 16.00 6.40 Kg 22.40
grills, Trusses, Stanchions, Heavy Beams
and Girders.
Labour Charges for Fabrication of BMM-V.19 85/885 1354.00 541.60 Sq.m 1895.60
Stainless Steel Sheet Cladding works
using Stainless Steel Welding rods
including buffing, polishing, lacquer
finishing to present seamless finish
S&F 20mm NB GI Pipe (Medium) with GI BMW-F.81 112 192.00 33.00 Rm 168.00
Fittings (20mm NB)
S&F 25mm NB GI Pipe (Medium) with GI BMW-F.83 112 252.00 33.00 Rm 220.00
Fittings (25mm NB)
S&F 32mm NB GI Pipe (Medium) with GI BMW-F.85 112 354.00 33.00 Rm 309.00
Fittings (32 mm NB)
S&F 40mm NB GI Pipe (Medium) with GI BMW-F.87 112 396.00 36.00 Rm 346.00
Fittings (40mm NB)
S&F 50 mm NB GI Pipe (Medium) with GI BMW-F.89 112 427.00 55.00 Rm 373.00
Fittings (50 mm NB)
S&F 65 mm NB GI Pipe (Medium) with BMW-F.91 112 757.00 55.00 Rm 661.00
Fittings (65 mm NB)
Cutting Holes in CC, basement & BMW-I.44 123 0.00 82.00 Each 82.00
Repaires (Labour)
S& F of CPVC Pipes conforming to IS-15450 including Fittings & Excavation upto 1.0m, Laying, fixing &
Testing, Refilling and Commissioning
Ref.# page Material Labour Unit Total
15.90mm OD- SDR-13.50 (1/2" NB) BMW-I.220 131 132.00 58.00 Rm 120.00
34.90mm OD- SDR-13.50 (1 1/4" NB) BMW-I.223 131 270.00 58.00 Rm 245.00
Materials_Others
Page 382 of 613
Labour Charges for Laying and Fixing of BMW-G.152 119 0.00 58.00 Rm 58.00
PVC Pipes and fittings with Solvent
Cement Joints
Supply of u-PVC-Type"B" SWR Pipes Conforming to IS : 13592 (Type B: Soil,Waste &Rain Water)
SWR_Type"B" _uPVC Pipes Ref.# Page Material Labour Unit Total
75mm OD- 3m Long Single Socket BMW-G.33 114 432.00 Each 432.00
90mm OD-3m Long Single Socket BMW-G.34 114 696.00 Each 696.00
110 mm OD - 3m Long Single Socket BMW-G.35 114 828.00 Each 828.00
Supply of u-PVC-Type"A" SWR Pipes Conforming to IS : 13592 (Type B: Soil,Waste &Rain Water)
SWR_Type"A" _uPVC Pipes Ref.# Page Material Labour Unit Total
75mm OD- 3m Long Single Socket BMW-G.11 113 255.00 Each 255.00
90mm OD-3m Long Single Socket BMW-G.12 113 405.00 Each 405.00
110 mm OD - 3m Long Single Socket BMW-G.13 113 484.00 Each 484.00
SWR Fittings
75mm ODx900 Plain Bend BMW-G.55 115 50.00 Each 50.00
90mm ODx900 Plain Bend BMW-G.56 115 70.00 Each 70.00
110 mm ODx90 Plain Bend
0
BMW-G.57 115 83.00 Each 83.00
75mm ODx90 Door Bend
0
BMW-G.58 115 67.00 Each 67.00
90 mm ODx90 Door Bend
0
BMW-G.59 115 95.00 Each 95.00
110 mm ODx900 Door Bend BMW-G.60 116 107.00 Each 107.00
75 mm OD Single Tee BMW-G.67 116 59.00 Each 59.00
90mm OD Single Tee BMW-G.68 116 89.00 Each 89.00
110 mm OD Single Tee BMW-G.69 116 108.00 Each 108.00
75 mm OD Single Tee w/Door BMW-G.70 102 73.00 Each 73.00
90mm OD Single Tee w/Door BMW-G.71 102 108.00 Each 108.00
110 mm OD Single Tee w/Door BMW-G.72 102 130.00 Each 130.00
Material Labour
Stone Ware Glazed Pipes
100 mm dia SWG-SP1 Pipes BMW-A.15 99 169 0 Rm 169
150 mm dia SWG-SP1 pipes BMW-A.16 99 293 0 Rm 293
200 mm dia SWG-SP1 Pipes BMW-A.17 99 453 0 Rm 453
250 mm dia SWG -SP1 Pipes BMW-A.18 99 829 0 Rm 829
300 mm dia SWG -SP1 Pipes BMW-A.19 99 1195 0 Rm 1195
350mm dia SWG-SP1 Pipes BMW-A.20 99 1626 0 Rm 1626
400mm dia SWG-SP1 Pipes BMW-A.21 100 1961 0 Rm 1961
450mm dia SWG -SP1 Pipes BMW-A.22 100 2368 0 Rm 2368
Materials_Others
0
Hire Charges
S.No Description Item./Page Unit SoRate Remarks
Air Compressor (Gen.Purpose) 12/28 Hour 499.40
Air Compressor 8.5 cmm (Diesel) 5/354 Hour 1285.40
Bitumen Pressure Distributor 15/28 Hour 940.00
Batching & Mixing Plant 30 cum/hr 30/355 Hour 2130.00
Batching Plant 0.50 cum (6 cum/hr) 9/331 Hour 503.90
Concrete Mixer 300/200 L (Diesel) 16/354 Hour 303.10
Concrete Paver Finisher with 40 HP 38/30 Hour 2360.00
Core Drilling Machine 22/405 Hour 718.80
Crane (for Lifting) 3t 33/29 Hour 280.00
Crane (for Lifting) 35 t Hour 630.00
Crane (for Lifting) 80 t Hour 950.00
Crane with Grab Bucket (0.75 cum) 33/29 Hour 1725.00
Dozer (D80) 1/28 Hour 1729.90
Drilling Equipment 47/31 Hour 1035.00
Electric Generator 125kVA 41/30 Hour 1090.00
Electric Generator 250 kVA 41/30 Hour 1550.00
Front End Loader 4/28 Hour 1320.00
Hot Mix Plant 120 TPH 17/29 Hour 23000.00
Hydraulic Excavator 3/28 Hour 1808.50
Hydraulic Chip Spreader 23/29 Hour 2070.00
39/380 Hour 226.10
Mechanical Broom Hydraulic 14/28 Hour 290.00
Motor Grader 2/28 Hour 2600.00
Paver Fisnisher (Mechanical) 100TPH 22/29 Hour 1090.00
Paver Finisher (Elec.Sensor Control) 21/29 Hour 2530.00
Planing Machine 44/380 Hour 287.30
Plate Compactor (for medians) 46/31 Hour 40.00
BRIDGES
S.No Description Unit Qty Rate Rs. Amount Rs.
1 EARTH WORK EXCAVATION
Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead of 50m
including all operational, incidental, labour charges such as shoring ,sheeting, planking, strutting, etc.
(a) complete for finished item of work including seigniorage excluding dewatering charges etc as per SS - 20
B (APSS 308).
a)Labour
Mate 0 Nos. 0.00 0.00
Mazdoor (Unskilled) 8.32 Nos. 490.00 4076.80
b) Machinery
Hydraulic Excavator 1 cum bucket capacity 6 hours 1808.50 10851.00
Sub total 14927.80
c&d) Overheads & Contractors Profit 2089.89
Cost for 240 cum = a+b+c+d 17017.69
Rate per cum = (a+b+c+d)/240 70.91
Rate per 1 Cum excluding Dewatering 70.91
Cum
Front end loader 1 cum bucket capacity @ 25 cum hour 0.200 1320.00 264.00
per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.230 588.17 135.28
Sub Total #REF!
c) Overheads & Contractors Profit 14% #REF!
Cost for 100 sqm = a+b+c #REF!
Rate per sqm = (a+b+c)/100 #REF!
Sq.m
Construction of embankment with approved material obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required slope and compacting to meet requirement of table
300-2 of MoRTH with a lead of 5 Km
Construction of embankment with approved material obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required slope and compacting to meet requirement of table
300-2 of MoRTH with a lead of 10 Km
Taking output = 100 cum
a) Labour
Mate day 0.04 #REF! #REF!
Mazdoor day 1.00 490.00 490.00
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum per
hour 1.67 1808.50 3020.20
hour
Tipper 10 tonne capacity (160*Lead) tonne.km 1600.00 4.20 6721.94
Add 10 per cent of cost of carriage to cover cost of loading
672.19
and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.50 1729.90 864.95
Motor grader for grading @ 100 cum per hour hour 1.00 2600.00 2600.00
Water tanker6 KL capacity hour 4.00 345.00 1380.00
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.00 1704.60 1704.60
c) Material
Cost of water KL 24.00 100.00 2400.00
Compensation for earth taken from private land cum 100.00 30.00 3000.00
10 Well Foundations - Island for 8.0m dia Well Foundation (4.0m depth of water)
Providing and Constructing Temporary Island 16m dia for constructing well foundation of 8.0 m dia well
as per Technical Specification of MoRTH for 4.0 m depth of water and 4.50m height of Island
11 Well Curb
Providing and Laying Cutting Edge of Mild Steel weighing 40 kg per metre for Well Foundation complete
as per Drawing and Technical Specification.
Unit = 1 MT
a) Material
Structural steel in plates, angles, etc MT 1.05 35246.02 37008.32
Nuts & bolts Kg 20.00 102.00 2040.00
b) Labour
(for cutting, bending, making holes, joining, welding and
erecting in position)
Fitter Day 5.50 672.00 3696.00
Blacksmith Day 5.50 623.00 3426.50
Welder Day 5.50 623.00 3426.50
Mazdoor Day 17.82 490.00 8731.80
Electrodes, cutting gas and other consumables @ 10 per
10% 39048.32 3904.83
cent of cost of (a) above
c) Handling, Loading and Unloading , Hire charges for
Welding equipment etc. @ 5% on (a) 5% 39048.32 1952.42
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/
vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of
screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the
required density as per Cl.404 of MoRTH
By Manual Means
Taking output = 360 cum
a) Labour
Mate day 10.08 #REF! #REF!
Mazdoor skilled day 2.00 #REF! #REF!
Mazdoor day 250.00 490.00 122500.00
b) Machinery
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm cum 97.20 0.00 0.00
OR
Crushable type such as Moorum or Gravel for grading-I @
cum 108.00 450.80 48686.40
0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for grading I
cum 28.80 450.80 12983.04
material
Cost of water KL 144.00 #REF! #REF!
Sub Total #REF!
d)Overheads & Contractors Profit 14% #REF!
Cost for 360 cum = a+b+c+d #REF!
Rate per cum = (a+b+c+d)/360 #REF!
#REF!
Cu.m
13 Water Bound Macadam - Grade II (75 mm thick Compacted)
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/
vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of
screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the
required density as per Cl.404 of MoRTH
By Manual Means
(a) +(b) (Labour + Machinery) #REF!
c)Materilas
Aggregate
Grading-II 63 mm to 45 mm @ 0.91 cum per 10 sqm for
cum 435.6 #REF! #REF!
compacted thickness of 75 mm
Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm cum 57.6 0 0.00
OR
Crushable type such as Moorum or Gravel for grading II &III
cum 105.59 450.80 47599.97
@ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.4 0 0.00
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
cum 28.8 450.80 12983.04
material
Cost of water KL 144 #REF! #REF!
Sub Total #REF!
d) Overheads & Contractors Profit 14% #REF!
Cost for 360 cum = a+b+c+d #REF!
Rate per cum = (a+b+c+d)/360 #REF!
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/
vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of
screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the
required density as per Cl.404 of MoRTH
Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.4 0 0.00
OR
Crushable type such as Moorum or Gravel for grading II &III
cum 105.59 450.80 47599.97
@ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading III
cum 28.8 450.80 12983.04
material
Cost of water KL 144 #REF! #REF!
Sub Total #REF!
d) Overheads & Contractors Profit 14% #REF!
Cost for 360 cum = a+b+c+d #REF!
Rate per cum = (a+b+c+d)/360 #REF!
#REF!
Cum
15 Granular Sub-Base with Close Graded Material (Table:- 400-1) : GSB
Plant Mix Method
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at
OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared
surface and compacting with vibratory power roller to achieve the desired density, complete as per clause
401
Water tanker 6 KL capacity 5 km lead with one trip per hour hour 4.50 345.00 1552.50
Front end loader 1 cum bucket capacity hour 6.00 1320.00 7920.00
Tipper 10 tonne (450*Lead)(Lead:21 Km) tonne.km 9450.00 4.20 39701.48
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by
tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and
compacting with vibratory roller to achieve the desired density as per Cl.406 of MoRTH
Tipper (495* lead (L) Km) (Lead:21Km) tonne.km 10395 4.20 43671.62
1. Though vibratory roller is required only for 3 hours as per norms, the same is required to be available at site for
6 hours to match with other machines. The usage rates of vibratory roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use, the same has been provided as an alternative
which can be used if the thickness of individual layer does not exceed 100 mm..
17 Prime Coat using Bitumen Emulsion RS-1
Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including
clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.
Mechanical broom @ 1250 sqm per hour hour 2.80 290.00 812.00
Air compressor 250 cfm hour 2.80 499.40 1398.32
Bitumen pressure distributor @ 1750 sqm per hour hour 2.00 940.00 1880.00
Water tanker 6 KL capacity @ 1 trip per hour hour 1.00 345.00 345.00
c) Material
Sq.m
Note: Bitumen primer has been provided @ 0.60 kg per sqm as per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between this quantity and the actual quantity approved by the Engineer
after the preliminary trials refer
Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of
0.20 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom.
a) Labour
Mate day 0.08 #REF! #REF!
Mazdoor day 2.00 490.00 980.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.80 290.00 812.00
Air compressor 250 cfm hour 2.80 499.40 1398.32
Emulsion pressure distributor @ 1750 sqm per hour hour 2.00 940.00 1880.00
c) Material
Bitumen emulsion @ 0.2 kg per sqm tonne 0.70 39224.00 27456.80
Sq.m
1. Bitumen emulsion has been provided @ 0.20 kg per sqm as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this quantity and actual quantity approved by the Engineer
after preliminary trials referred to in
2. An output of 3500 sqm has been considered in case of prime coat and tack coat which can be covered by
bituminous courses on the same day.
20 Bituminous Macadam
Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average output of
75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder,
transported to site, laid over a previously prepared surface with paver finisher to the required grade, level
and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction
Unit = cum
Skilled mazdoor for checking line & levels day 5.00 #REF! #REF!
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour actual
hour 6.00 23000.00 138000.00
output
Mechanical broom hydraulic @ 1250 sqm per hour hour 2.20 290.00 638.00
Front end loader 1 cum bucket capacity hour 6.00 1320.00 7920.00
Finish rolling with 6-8 tonnes smooth wheeled tandem roller. hour 6.00x0.65* 686.84 2678.68
Material : ( c) #REF!
Cum
Material : ( c) #REF!
Note: *1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be
available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of
450 tonnes considered in t
Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an
average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.5 per cent of mix and filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH
specification clause No. 508 complete in all respects
Unit : cum
Taking output = 195 cum (450 tonnes)
a) Labour
Skilled mazdoor for checking line & levels day 5.00 #REF! #REF!
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.00 23000.00 138000.00
Front end loader 1 cum bucket capacity hour 6.00 1320.00 7920.00
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1704.60 6647.94
Finish rolling with 6-8 tonnes smooth wheeled tandem roller hour 6.00x0.65* 686.84 2678.68
c) Material
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.25 34370.00 695992.50
ii) Aggregate
Material : (c ) #REF!
Cu.m
Grading II: 10 mm (Nominal Size) -SDBC
Bitumen @ 5.0 per cent of weight of mix tonne 22.50 34370.00 773325.00
Aggregate
*1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be available at
site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of 450 tonnes
considered in this ana
2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case SDBC is laid over freshly laid tack coat, provision of broom and 2 mazdoor shall be deleted as the same
has been included in the cost of tack coat.
5. The quantity of Bitumen to be adjusted as per job mix formula.
21 Cement Concrete Pavement - M30 Grade PQC (Without Dowels and Tie Rods)
Construction of un-reinforced M30 Grade plain cement concrete pavement over a prepared sub base with
43 grade cement @ 380 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of
coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design,
transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction, expansion, construction and longitudinal joints,
joint filler, separation membrane, sealant primer, joint sealant, debonding strip, admixtures as approved,
curing compound, finishing to lines and grades as per drawing as per Cl. 602 of MoRTH
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 #REF! #REF!
Mazdoor skilled day 15.000 #REF! #REF!
Mazdoor day 35.000 490.00 17150.00
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 290.00 812.00
Front end loader 1 cum bucket capacity hour 18.000 1320.00 23760.00
Cement concrete batch mix plant @ 175 cum per hour 6.000 2130.00 12780.00
hour (effective output)
Electric generator 250 KVA hour 6.000 1550.00 9300.00
Slip form paver with electronic sensor hour 6.000 2360.00 14160.00
Water tanker6 KL capacity hour 36.000 345.00 12420.00
Transit truck agitator 5 cum capacity.(L :21Km) t-km 2415xL 7.96 403546.50
Add 10 per cent of cost of carriage to cover cost of 40354.65
loading and unloading
Concrete joint cutting machine . hour 12.000 718.80 8625.60
Texturing machine . hour 12.000 287.30 3447.60
c) Material
Crushed stone coarse aggregates of 25mm and cum 945.000 #REF! #REF!
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4. .
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.00 #REF! #REF!
Mazdoor skilled day 15.00 #REF! #REF!
Mazdoor day 35.00 490.00 17150.00
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.80 290.00 812.00
Front end loader 1 cum bucket capacity hour 18.00 1320.00 23760.00
Sand as per IS: 383 and conforming to clause cum 473.00 #REF! #REF!
602.2.4 @ 0.45 cum/cum of concrete
Cement 43 grade @ 380 kg/cum of concrete tonne 399.00 5532.42 2207435.58
32 mm mild steel dowel bars of grade S 240 tonne 9.45 35000.00 330750.00
16 mm deformed steel tie bars of grade S 415 tonne 1.17 30000.00 35100.00
Separation Membrane of impermeable plastic sqm 3675.00 20.00 73500.00
sheeting 125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion sqm 16.33 1052.00 17179.16
joint.
Joint sealant kg 875.00 90.00 78750.00
Sealant primer kg 116.67 80.00 9333.60
Plastic sheath,1.25 mm thick for dowel bars sqm 46.67 #REF! #REF!
Curing compound Lit 1850.00 123.00 227550.00
Super plastisizer admixture IS marked as per 9103- kg 2070.00 69.00 142830.00
1999 @ 0.5 per cent by weight of cement
Cost of water KL 216.00 100.00 21600.00
Add 1 per cent of material for cost of miscellaneous #REF!
materials like tarpauline, Hessian cloth, metal cap,
cotton / compressible sponge and cradle for dowel
bars, work bridges for men to approach concrete
surface without walking over it, cutting blades an
Cum
23 Cement Concrete Pavement - M 20 Grade PQC (Without Dowels and Tie Rods)
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.00 #REF! #REF!
Mazdoor skilled day 15.00 #REF! #REF!
Mazdoor day 35.00 490.00 17150.00
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.80 290.00 812.00
Front end loader 1 cum bucket capacity hour 18.00 1320.00 23760.00
Cement concrete batch mix plant @ 175 cum per hour 6.00 2130.00 12780.00
hour (effective output)
Cum
24 Cement Concrete Pavement - M 20 Grade PQC (With Dowels and Tie Rods)
Construction of un-reinforced M 20 Grade plain cement concrete pavement over a prepared sub base with
43 grade cement @ 350 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of
coarse aggregate not exceeding 25 mm, mixed in a batchi
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.00 #REF! #REF!
Mazdoor skilled day 15.00 #REF! #REF!
Mazdoor day 35.00 490.00 17150.00
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.80 290.00 812.00
Front end loader 1 cum bucket capacity hour 18.00 1320.00 23760.00
Cement concrete batch mix plant @ 175 cum per hour 6.00 2130.00 12780.00
hour (effective output)
Electric generator 250 KVA hour 6.00 1550.00 9300.00
Slip form paver with electronic sensor hour 6.00 2360.00 14160.00
Water tanker6 KL capacity hour 36.00 345.00 12420.00
Transit truck agitator 5 cum capacity.(L :21Km) t-km 2415xL 7.96 403546.50
Add 10 per cent of cost of carriage to cover cost of 40354.65
loading and unloading
Sand as per IS: 383 and conforming to clause cum 473.00 #REF! #REF!
602.2.4 @ 0.45 cum/cum of concrete
Supply, Delivery, Lowering, Laying and Jointing of RCC Plain ended pipes with cement joints including
cost of jointing materials of the following Dia at regular intervals across the roads for facilitating the
25
crossing of utilities like Water Supply Service Connections and cables etc. inclusive of all material and
labour charges etc. complete and as directed by Dept. authorities
26
Cement Concrete Pavement - M30 Grade RMC (Without Dowels and Tie Rods)
Construction of un-reinforced M30 Grade plain cement concrete pavement Using RMC as per IS-4926-2003
over a prepared sub base with 43 grade cement @ 380 kg per cum (as per Mix design approved by the
Dep+B644t.),coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not
exceeding 20 mm, mixed in a batching and mixing plant as per approved mix design, transported to site,
laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation
including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant, debonding strip, admixtures as approved, curing compound,
finishing to lines and grades as per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 #REF! #REF!
Mazdoor skilled day 15.000 #REF! #REF!
Mazdoor day 35.000 490.00 17150.00
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 290.00 812.00
Front end loader 1 cum bucket capacity hour 18.000 1320.00 23760.00
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 2130.00 12780.00
(effective output)
Electric generator 250 KVA hour 6.000 1550.00 9300.00
Slip form paver with electronic sensor hour 6.000 2360.00 14160.00
Water tanker6 KL capacity hour 36.000 345.00 12420.00
Transit truck agitator 5 cum capacity.(L :21Km) t-km 2415xL 7.96 403546.50
Add 10 per cent of cost of carriage to cover cost of loading 40354.65
and unloading
Concrete joint cutting machine . hour 12.000 718.80 8625.60
Texturing machine . hour 12.000 287.30 3447.60
c) Material
Crushed stone coarse aggregates of 25mm and 12.5mm cum 945.000 #REF! #REF!
nominal size @ 0.90 cum/cum of concrete conforming to
clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 @ cum 473.000 #REF! #REF!
0.45 cum/cum of concrete
Cement 43 grade @ 380 kg/cum of concrete tonne 399.000 5532.42 2207435.58
32 mm mild steel dowel bars of grade S 240 tonne 9.450 0.00 0.00
16 mm deformed steel tie bars of grade S 415 tonne 1.170 0.00 0.00
Separation Membrane of impermeable plastic sheeting 125 sqm 3675.000 20.00 73500.00
micron thick
Pre moulded Joint filler, 25 mm thick for expansion joint. sqm 16.330 1052.00 17179.16
Joint sealant kg 875.000 90.00 78750.00
Sealant primer kg 116.670 80.00 9333.60
Plastic sheath,1.25 mm thick for dowel bars sqm 46.670 0.00 0.00
Curing compound Lit 1850.000 123.00 227550.00
Super plastisizer admixture IS marked as per 9103-1999 @ kg 2070.000 69.00 142830.00
0.5 per cent by weight of cement
Cost of water KL 216.000 100.00 21600.00
Add 1 per cent of material for cost of miscellaneous #REF!
materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades an
Sub Total #REF!
d) Overheads & Contractors profit 14% #REF!
Cost for 1050cum = a+b+c+d #REF!
27 Cement Concrete Pavement - M30 Grade RMC (With Dowels & Tie Rods)
Construction of un-reinforced M20 Grade plain cement concrete pavement Using RMC as per IS-4926-2003
over a prepared sub base with 43 grade cement @ 350 kg per cum (as per Mix design approved by the
Dept.),coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding
20 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and finished in a continuous operation including
provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane,
sealant primer, joint sealant, debonding strip, admixtures as approved, curing compound, finishing to
lines and grades as per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 #REF! #REF!
Mazdoor skilled day 15.000 #REF! #REF!
Mazdoor day 35.000 #REF! #REF!
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 290.00 812.00
Front end loader 1 cum bucket capacity hour 18.000 1320.00 23760.00
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 2130.00 12780.00
(effective output)
Electric generator 250 KVA hour 6.000 1550.00 9300.00
Slip form paver with electronic sensor hour 6.000 2360.00 14160.00
Water tanker6 KL capacity hour 36.000 345.00 12420.00
Transit truck agitator 5 cum capacity.(L :21Km) t-km 2415xL 7.64 387462.60
Add 10 per cent of cost of carriage to cover cost of loading 38746.26
and unloading
Concrete joint cutting machine . hour 12.000 546.20 6554.40
Texturing machine . hour 12.000 265.10 3181.20
c) Material
Crushed stone coarse aggregates of 25mm and 12.5mm cum 945.000 #REF! #REF!
nominal size @ 0.90 cum/cum of concrete conforming to
clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 @ cum 473.000 800.00 378400.00
0.45 cum/cum of concrete
Cement 43 grade @ 380 kg/cum of concrete tonne 399.000 5532.42 2207435.58
32 mm mild steel dowel bars of grade S 240 tonne 9.450 35000.00 330750.00
16 mm deformed steel tie bars of grade S 415 tonne 1.170 30000.00 35100.00
Separation Membrane of impermeable plastic sheeting 125 sqm 3675.000 #REF! #REF!
micron thick
Pre moulded Joint filler, 25 mm thick for expansion joint. sqm 16.330 915.00 14941.95
Joint sealant kg 875.000 26.00 22750.00
Sealant primer kg 116.670 45.00 5250.15
Plastic sheath,1.25 mm thick for dowel bars sqm 46.670 #REF! #REF!
Curing compound Lit 1850.000 95.00 175750.00
Super plastisizer admixture IS marked as per 9103-1999 @ kg 2070.000 50.00 103500.00
0.5 per cent by weight of cement
Cost of water KL 216.000 70.00 15120.00
Add 1 per cent of material for cost of miscellaneous #REF!
materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades an
28 Cement Concrete Pavement - M 20 Grade RMC (Without Dowels and Tie Rods)
Construction of un-reinforced M20 Grade plain cement concrete pavement Using RMC as per IS-4926-2003
over a prepared sub base with 43 grade cement @ 350 kg per cum (as per Mix design approved by the
Dept.),coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding
20 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and finished in a continuous operation including
provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane,
sealant primer, joint sealant, debonding strip, admixtures as approved, curing compound, finishing to
lines and grades as per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2 #REF! #REF!
Mazdoor skilled day 15 #REF! #REF!
Mazdoor day 35 #REF! #REF!
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.8 290 812.00
Front end loader 1 cum bucket capacity hour 18 1320 23760.00
Cement concrete batch mix plant @ 175 cum per hour
hour 6 2130 12780.00
(effective output)
Electric generator 250 KVA hour 6 1550 9300.00
Slip form paver with electronic sensor hour 6 2360 14160.00
Water tanker6 KL capacity hour 36 345 12420.00
Transit truck agitator 5 cum capacity.(L :21Km) t-km 2415xL 7.64 387462.60
Add 10 per cent of cost of carriage to cover cost of loading
38746.26
and unloading
Concrete joint cutting machine . hour 12 546.2 6554.40
Texturing machine . hour 12 265.1 3181.20
c) Material
Crushed stone coarse aggregates of 25mm and 12.5mm
nominal size @ 0.90 cum/cum of concrete conforming to cum 945 #REF! #REF!
clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 @
cum 473 800 378400.00
0.45 cum/cum of concrete
Cement 43 grade @ 350 kg/cum of concrete tonne 367.5 5532.42 2033164.35
32 mm mild steel dowel bars of grade S 240 tonne 9.45 0 0.00
16 mm deformed steel tie bars of grade S 415 tonne 1.17 0 0.00
Separation Membrane of impermeable plastic sheeting 125
sqm 3675 #REF! #REF!
micron thick
Pre moulded Joint filler, 25 mm thick for expansion joint. sqm 16.33 915 14941.95
Joint sealant kg 875 26 22750.00
Sealant primer kg 116.67 45 5250.15
Plastic sheath,1.25 mm thick for dowel bars sqm 46.67 0 0.00
Curing compound Lit 1850 95 175750.00
Super plastisizer admixture IS marked as per 9103-1999 @
kg 2070 50 103500.00
0.5 per cent by weight of cement
Cost of water KL 216 70 15120.00
29 Cement Concrete Pavement - M 20 Grade RMC (With Dowels and Tie Rods)
Construction of un-reinforced M20 Grade plain cement concrete pavement Using RMC as per IS-4926-2003
over a prepared sub base with 43 grade cement @ 350 kg per cum (as per Mix design approved by the
Dept.),coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding
20 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and finished in a continuous operation including
provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane,
sealant primer, joint sealant, debonding strip, admixtures as approved, curing compound, finishing to
lines and grades as per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2 #REF! #REF!
Mazdoor skilled day 15 #REF! #REF!
Mazdoor day 35 #REF! #REF!
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.8 290 812.00
Front end loader 1 cum bucket capacity hour 18 1320 23760.00
Cement concrete batch mix plant @ 175 cum per hour
hour 6 2130 12780.00
(effective output)
Electric generator 250 KVA hour 6 1550 9300.00
Slip form paver with electronic sensor hour 6 2360 14160.00
Water tanker6 KL capacity hour 36 345 12420.00
Transit truck agitator 5 cum capacity.(L :21Km) t-km 2415xL 7.64 387462.60
Add 10 per cent of cost of carriage to cover cost of loading
38746.26
and unloading
Concrete joint cutting machine . hour 12 546.2 6554.40
Texturing machine . hour 12 265.1 3181.20
c) Material
Crushed stone coarse aggregates of 25mm and 12.5mm
nominal size @ 0.90 cum/cum of concrete conforming to cum 945 #REF! #REF!
clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 @
cum 473 800 378400.00
0.45 cum/cum of concrete
Cement 43 grade @ 350 kg/cum of concrete tonne 367.5 5532.42 2033164.35
32 mm mild steel dowel bars of grade S 240 tonne 9.45 35000 330750.00
16 mm deformed steel tie bars of grade S 415 tonne 1.17 30000 35100.00
Separation Membrane of impermeable plastic sheeting 125
sqm 3675 #REF! #REF!
micron thick
Pre moulded Joint filler, 25 mm thick for expansion joint. sqm 16.33 915 14941.95
Joint sealant kg 875 26 22750.00
Sealant primer kg 116.67 45 5250.15
Plastic sheath,1.25 mm thick for dowel bars sqm 46.67 #REF! #REF!
Curing compound liter 1850 95 175750.00
Super plastisizer admixture IS marked as per 9103-1999 @
kg 2070 50 103500.00
0.5 per cent by weight of cement
30 Cement Concrete Pavement - M 15 Grade RMC (Without Dowels and Tie Rods)
Construction of un-reinforced M15 Grade plain cement concrete pavement Using RMC as per IS-4926-2003
over a prepared sub base with 43 grade cement @ 330 kg per cum (as per Mix design approved by the
Dept.),coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding
20 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and finished in a continuous operation including
provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane,
sealant primer, joint sealant, debonding strip, admixtures as approved, curing compound, finishing to
lines and grades as per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2 #REF! #REF!
Mazdoor skilled day 15 #REF! #REF!
Mazdoor day 35 #REF! #REF!
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.8 290 812.00
Front end loader 1 cum bucket capacity hour 18 1320 23760.00
Cement concrete batch mix plant @ 175 cum per hour
hour 6 2130 12780.00
(effective output)
Electric generator 250 KVA hour 6 1550 9300.00
Slip form paver with electronic sensor hour 6 2360 14160.00
Water tanker6 KL capacity hour 36 345 12420.00
Transit truck agitator 5 cum capacity.(L :21Km) t-km 2415xL 7.64 387462.60
Add 10 per cent of cost of carriage to cover cost of loading
38746.26
and unloading
Concrete joint cutting machine . hour 12 546.2 6554.40
Texturing machine . hour 12 265.1 3181.20
DRAINS
1 EARTH WORK EXCAVATION
Earthh work excavation for foundations and depositing on bank for all lifts and with an initial lead of
50m including all operational, incidental, labour charges such as shoring ,sheeting, planking,
strutting, etc. complete for finished item of work including seigniorage excluding dewatering charges
etc as per SS - 20 B
Drains
Page 410 of 613
Drains
Page 411 of 613
6 Laying of VCC (1:3:6) using 20 mm (SS-5) graded HBG m/c metal using OPC, coarse and fine
aggregates conforming to IS:383 including cost & conveyance of all materials, labour charges,
machine mixing, vibration, centering, laying in position, curing for 21 days to proper grades and
slopes etc. complete.
Unit: 1 Cum
a) Material
Cost of 20mm (SS5) graded HBG M/C metal cum 0.92 1576.10 1450.01
Cost of Cement OPC grade kg 220.00 5.53 1217.13
Cost of Sand cum 0.46 800.00 368.00
Water including curing kL 1.20 100.00 120.00
b) Labour:
Mason 1st class day 0.06 623.00 37.38
Mason 2nd class day 0.14 567.00 79.38
Man Mazdoor day 1.8 490.00 882.00
Women Mazdoor day 1.4 490.00 686.00
c) Machinery
Concrete Mixer 0.28 cum cap Hr 1.0 303.10 303.10
Vibrating charges Hr 1.0 120.40 120.40
Form work charges (page.75) cum 1.0 309.00 309.00
Sub Total 5572.40
Over heads and contractors profit 0.14 5572.40 780.14
Rate per 1Cum : VCC (1:3:6) for Drains 6352.54
cum
Laying of VCC (1:4:8) using 40mm m/c SS5 HBG including machine mixing, laying, compacting,
7
finishing, curing etc for foundations of CC drains and culverts including formwork and curing
Unit: 1 Cum
a) Material
Cement Kg 162.00 5.53 896.25
Coarse aggregate 40mm cum 0.90 1558.10 1402.29
Fine aggregate (sand) cum 0.45 800.00 360.00
Water including curing kL 1.20 100.00 120.00
b) Machinery
Concrete mixer 0.30 cum Hr 1.00 303.10 303.10
Plate Vibrator Hr 1.00 120.40 120.40
c) Labour
Mason 1st class day 0.10 623.00 62.30
Mazdoor unskilled day 1.39 490.00 681.10
Formwork Charges cum 1.00 0.00 0.00
Sub Total 3945.44
Overheads & Contractors profit 0.14 3945.44 552.36
Rate per Cum : VCC (1:4:8) 4497.80
Cum
Drains
Page 412 of 613
8 Construction of Drain walls using - M 10 Grade RMC - Nom. (1:3:6) PCC using 20mm Graded
Construction of un-reinforced M10 Grade plain cement concrete drain walls using RMC as per IS-
4926-2003 with OPC @ 220 kg per cum (as per Mix design approved by the Dept.),coarse and fine
aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 20 mm, mixed in a
batching and mixing plant as per approved mix design, transported to site, laid in a form work at site ,
spreading, compacted and finished in a continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler,admixtures as approved, curing compound,
finishing to lines and grades as per drawing
Drains
Page 413 of 613
Construction of un-reinforced M15 Grade plain cement concrete drain walls using RMC as per IS-
4926-2003 with OPC @ 300 kg per cum (as per Mix design approved by the Dept.),coarse and fine
aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 20 mm, mixed in a
batching and mixing plant as per approved mix design, transported to site, laid in a form work at site ,
spreading, compacted and finished in a continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler,admixtures as approved, curing compound,
finishing to lines and grades as per drawing
Drains
RATES OF HDPE PIPES -PE -80 Grade - 4.0 Ksc
Manufacture, supply, & delivery of HDPE pipes conforming to IS 4984 - 1995 including transportation to any where in A.P,including excise duty, sale tax but
excluding specials etc., complete. ( Supply upto 90 mm dia in coil & above 90 mm dia straight length in 6 M.)
Table 16 PE-80 :4.0 Ksc
Resin Rate Revised Total
Max Wt of SSR Rate SSR resin Total Cost
Pipe OD Pipe OD Min thick Av.thick Pipe ID as on Pipe Rate CED VAT OH&CP Supply Laying &
thick in pipe per Rm rate Sub-total Supply, LL
in mm in Mts in mm in mm in Mts 12/2012 per Rm Cost per Jointing
mm &Jointing
Rm
M P1 A1 A2 P2 12.36% 5.00% 14%
50mm 0.050 2.30 2.8 2.55 0.045 0.36 51.00 88610.00 112626.92 59.20 7.32 3.33 69.84 9.78 79.62 37.05 116.67
63 mm 0.063 2.50 3.00 2.75 0.058 0.49 70.00 88610.00 112626.92 81.22 10.04 4.56 95.83 13.42 109.24 41.33 150.57
75 mm 0.075 2.90 3.40 3.15 0.069 0.67 96.00 88610.00 112626.92 111.33 13.76 6.25 131.35 18.39 149.73 45.60 195.33
90 mm 0.090 3.50 4.10 3.80 0.082 0.97 138.00 88610.00 112626.92 160.19 19.80 9.00 188.99 26.46 215.44 51.30 266.74
110 mm 0.110 4.30 5.00 4.65 0.101 1.45 205.00 88610.00 112626.92 238.18 29.44 13.38 281.00 39.34 294.38 58.43 352.81
125 mm 0.125 4.90 5.60 5.25 0.115 1.87 265.00 88610.00 112626.92 307.59 38.02 17.28 362.88 50.80 413.69 71.25 484.94
140 mm 0.140 5.40 6.20 5.80 0.128 2.31 327.00 88610.00 112626.92 379.72 46.93 21.33 447.99 62.72 510.71 75.53 586.23
160 mm 0.160 6.20 7.10 6.65 0.147 3.03 428.00 88610.00 112626.92 497.08 61.44 27.93 586.44 82.10 668.54 81.23 749.77
180 mm 0.180 7.00 7.90 7.45 0.165 3.82 540.00 88610.00 112626.92 627.08 77.51 35.23 739.81 103.57 843.38 89.78 933.16
200 mm 0.200 7.70 8.70 8.20 0.184 4.67 662.00 88610.00 112626.92 768.53 94.99 43.18 906.70 126.94 1033.64 96.90 1130.54
225 mm 0.225 8.70 9.80 9.25 0.207 5.92 862.00 88610.00 112626.92 997.18 123.25 56.02 1176.45 164.70 1341.16 106.88 1448.03
250 mm 0.250 9.70 10.90 10.30 0.229 7.33 1067.00 88610.00 112626.92 1234.24 152.55 69.34 1456.13 203.86 1659.98 114.00 1773.98
280 mm 0.280 10.80 12.10 11.45 0.257 9.13 1330.00 88610.00 112626.92 1538.28 190.13 86.42 1814.84 254.08 2068.91 125.40 2194.31
315 mm 0.315 12.20 13.70 12.95 0.289 11.61 1690.00 88610.00 112626.92 1954.95 241.63 109.83 2306.42 322.90 2629.31 225.15 2854.46
355 mm 0.355 13.70 15.30 14.50 0.326 14.66 2049.00 88610.00 112626.92 2383.43 294.59 133.90 2811.93 393.67 3205.59 250.80 3456.39
400 mm 0.400 15.40 18.00 16.70 0.367 19.00 2655.00 88610.00 112626.92 3088.59 381.75 173.52 3643.86 510.14 4153.99 279.30 4433.29
450 mm 0.450 17.40 20.30 18.85 0.412 24.13 3374.00 88610.00 112626.92 3924.51 485.07 220.48 4630.05 648.21 5278.26 310.65 5588.91
500 mm 0.500 19.30 22.40 20.85 0.458 29.66 4145.00 88610.00 112626.92 4821.71 595.96 270.88 5688.55 796.40 6484.95 342.00 6826.95
560 mm 0.560 21.60 25.10 23.35 0.513 37.20 5123.00 88610.00 112626.92 5971.79 738.11 335.50 7045.40 986.36 8031.76
630 mm 0.630 24.30 28.20 26.25 0.578 47.05 6479.00 88610.00 112626.92 7552.52 933.49 424.30 8910.31 1247.44 10157.75
710 mm 0.710 27.40 31.80 29.60 0.651 59.79 8233.00 88610.00 112626.92 9597.20 1186.21 539.17 11322.59 1585.16 12907.75
800 mm 0.800 30.80 35.70 33.25 0.734 75.69 10421.00 88610.00 112626.92 12147.90 1501.48 682.47 14331.85 2006.46 16338.31
900 mm 0.900 34.70 40.20 37.45 0.825 95.90 13205.00 88610.00 112626.92 15393.06 1902.58 864.78 18160.42 2542.46 20702.88
1000 mm 1.000 38.50 44.50 41.50 0.917 118.09 16260.00 88610.00 112626.92 18954.40 2342.76 1064.86 22362.03 3130.68 25492.71
Density is taken as 943.45kg/cumt as per IS 4984 1995 PARA 5.2.1
*
414 of 613
* Resin rate exlusive of CED for the month
415 of 613
RATES OF HDPE PIPES -PE -80 Grade - 10.0 Ksc
Manufacture, supply, & delivery of HDPE pipes conforming to IS 4984 - 1995 including transportation to any where in A.P,including excise duty, sale tax but
excluding specials etc., complete. ( Supply upto 90 mm dia in coil & above 90 mm dia straight length in 6 M.)
Table 16 PE-80 : 10.00 Ksc
Resin Rate Revised
Wt of SSR Rate SSR resin Total
Max as on Pipe Rate CED VAT OH&CP Total Cost
Pipe OD Pipe OD Min thick Av.thick Pipe ID pipe per Rm rate Supply Laying &
thick in 12/2012 per Rm * Sub-total Supply, LL
in mm in Mts in mm in mm in Mts Cost per Jointing
mm &Jointing
M P1 A1 A2 P2 12.36% 5.00% 14% Rm
25 mm 0.025 2.30 2.80 2.55 0.020 0.17 0.00 0.00 0.00 26.25 3.24 1.47 30.97 4.34 35.30 29.93 65.23
32 mm 0.032 3.00 3.50 3.25 0.026 0.28 0.00 0.00 0.00 41.78 5.16 2.35 49.29 6.90 56.19 29.93 86.12
40 mm 0.040 3.70 4.30 4.00 0.032 0.43 0.00 0.00 0.00 64.43 7.96 3.62 76.01 10.64 86.66 37.05 123.71
50 mm 0.050 4.60 5.30 4.95 0.040 0.66 0.00 0.00 0.00 99.80 12.34 5.61 117.74 16.48 134.23 37.05 171.28
63 mm 0.063 4.30 5.00 4.65 0.054 0.81 0.00 0.00 0.00 157.75 19.50 8.86 186.11 26.06 194.97 41.33 236.30
75 mm 0.075 6.90 7.80 7.35 0.060 1.48 0.00 0.00 0.00 222.57 27.51 12.50 262.58 36.76 299.35 45.60 344.95
90 mm 0.090 8.20 9.30 8.75 0.073 2.11 0.00 0.00 0.00 318.28 39.34 17.88 375.50 52.57 428.07 51.30 479.37
110 mm 0.110 10.00 11.20 10.60 0.089 3.13 0.00 0.00 0.00 471.64 58.29 26.50 556.43 77.90 634.33 58.43 692.76
125 mm 0.125 11.40 12.80 12.10 0.101 4.06 0.00 0.00 0.00 627.95 77.61 35.28 740.84 103.72 844.56 71.25 915.81
140 mm 0.140 12.80 14.30 13.55 0.113 5.09 0.00 0.00 0.00 787.42 97.33 44.24 928.98 130.06 1059.04 75.53 1134.56
* Quotation Rates
416 of 613
RATES OF HDPE PIPES - PE -80 Grade - 12.50 Ksc
Manufacture, supply, & delivery of HDPE pipes conforming to IS 4984 - 1995 including transportation to any where in A.P,including excise duty, sale tax but
excluding specials etc., complete. ( Supply upto 90 mm dia in coil & above 90 mm dia straight length in 6 M.)
Table 16 PE-80 : 12.50 Ksc
Resin Rate Revised Total
Max Wt of SSR Rate SSR resin Total Cost
Pipe OD Pipe OD Min thick Av.thick Pipe ID as on Pipe Rate CED VAT OH&CP Supply Laying &
thick in pipe per Rm rate Sub-total Supply, LL
in mm in Mts in mm in mm in Mts 12/2012 per Rm Cost per Jointing
mm &Jointing
M P1 A1 A2 P2 12.36% 5.00% 14% Rm
20 mm 0.020 2.30 2.80 2.55 0.015 0.13 0.00 0.00 0.00 20.23 2.50 1.14 23.87 3.34 27.21 25.65 52.86
25 mm 0.025 2.80 3.30 3.05 0.019 0.20 0.00 0.00 0.00 30.45 3.76 1.71 35.92 5.03 40.95 29.93 70.88
32 mm 0.063 3.60 4.20 3.90 0.055 0.68 0.00 0.00 0.00 49.18 6.08 2.76 58.02 8.12 66.14 29.93 96.07
40 mm 0.075 4.50 5.20 4.85 0.065 1.01 0.00 0.00 0.00 76.29 9.43 4.29 90.01 12.60 102.61 37.05 139.66
50 mm 0.090 5.60 6.40 6.00 0.078 1.50 0.00 0.00 0.00 117.53 14.53 6.60 138.66 19.41 158.07 37.05 195.12
63 mm 0.110 7.00 7.90 7.45 0.095 2.27 0.00 0.00 0.00 185.37 22.91 10.41 218.70 30.62 229.11 41.33 270.43
75 mm 0.125 8.40 9.50 8.95 0.107 3.08 0.00 0.00 0.00 264.68 32.71 14.87 312.26 43.72 355.98 45.60 401.58
90 mm 0.140 10.00 11.20 10.60 0.119 4.07 0.00 0.00 0.00 376.75 46.57 21.17 444.48 62.23 506.71 51.30 558.01
110 mm 0.160 12.30 13.80 13.05 0.134 5.69 0.00 0.00 0.00 566.36 70.00 31.82 668.18 93.55 761.73 58.43 820.15
125 mm 0.180 13.90 15.50 14.70 0.151 7.21 0.00 0.00 0.00 745.29 92.12 41.87 879.28 123.10 1002.38 71.25 1073.63
140 mm 0.200 15.60 17.40 16.50 0.167 8.99 0.00 0.00 0.00 936.53 115.76 52.61 1104.90 154.69 1259.59 75.53 1335.11
* Quotation Rates
417 of 613
2 RATES OF HDPE PIPES - PE -100 Grade- 6.0 Ksc
Manufacture, supply, & delivery of HDPE pipes conforming to IS 4984 - 1995 including transportation to any where in A.P,including excise duty, sale tax but
excluding specials etc., complete. ( Supply upto 90 mm dia in coil & above 90 mm dia straight length in 6 M.)
Table 16 Pg.267 PE-100 : 6.0 Ksc
Resin Rate Revised
Wt of SSR resin Total
Max SSR Rate as on Pipe Rate CED VAT OH&CP Total Cost
Pipe OD pipe OD Min thick Av.thick pipe ID pipe rate Supply Laying &
thick in 12/2012 per Rm Sub-total Supply, LL
in mm in Mts in mm in mm in Mts Cost per Jointing
mm &Jointing
M P1 A1 A2 P2 12.36% 5.00% 14% Rm
50 mm 0.050 2.300 2.800 2.55 0.045 0.36 55.00 89610.00 112626.92 62.85 7.77 3.53 74.15 10.38 84.54 37.05
63 mm 0.063 2.900 3.400 3.15 0.057 0.56 83.00 89610.00 112626.92 95.24 11.77 5.35 112.36 15.73 128.09 41.33 169.42
75 mm 0.075 3.500 4.100 3.80 0.067 0.80 118.00 89610.00 112626.92 135.56 16.76 7.62 159.94 22.39 182.33 45.60 227.93
90 mm 0.090 4.100 4.800 4.45 0.081 1.13 168.00 89610.00 112626.92 192.71 23.82 10.83 227.36 31.83 259.19 51.30 310.49
110 mm 0.110 5.000 5.700 5.35 0.099 1.66 252.00 89610.00 112626.92 288.35 35.64 16.20 340.18 47.63 387.81 58.43 446.23
125 mm 0.125 5.700 6.500 6.10 0.113 2.15 322.00 89610.00 112626.92 369.08 45.62 20.74 435.44 60.96 496.40 71.25 567.65
140 mm 0.140 6.400 7.300 6.85 0.126 2.71 404.00 89610.00 112626.92 463.21 57.25 26.02 546.48 76.51 622.99 75.53 698.52
160 mm 0.160 7.300 8.300 7.80 0.144 3.52 528.00 89610.00 112626.92 605.07 74.79 33.99 713.84 99.94 813.78 81.23 895.01
180 mm 0.180 8.200 9.300 8.75 0.163 4.45 664.00 89610.00 112626.92 761.27 94.09 42.77 898.13 125.74 1023.87 89.78 1113.65
200 mm 0.200 9.100 10.300 9.70 0.181 5.48 821.00 89610.00 112626.92 940.83 116.29 52.86 1109.97 155.40 1265.37 96.90 1362.27
225 mm 0.225 10.300 11.600 10.95 0.203 6.96 1062.00 89610.00 112626.92 1214.15 150.07 68.21 1432.43 200.54 1632.97 106.88 1739.85
250 mm 0.250 11.400 12.800 12.10 0.226 8.55 1307.00 89610.00 112626.92 1493.87 184.64 83.93 1762.43 246.74 2009.18 114.00 2123.18
280 mm 0.280 12.800 14.300 13.55 0.253 10.72 1638.00 89610.00 112626.92 1872.37 231.43 105.19 2208.99 309.26 2518.25 125.40 2643.65
315 mm 0.315 14.400 16.100 15.25 0.285 13.57 2077.00 89610.00 112626.92 2373.74 293.39 133.36 2800.50 392.07 3192.56 225.15 3417.71
355 mm 0.355 16.200 18.100 17.15 0.321 17.20 2605.00 89610.00 112626.92 2981.13 368.47 167.48 3517.08 492.39 4009.47 250.80 4260.27
400 mm 0.400 18.200 21.200 19.70 0.361 22.24 3433.00 89610.00 112626.92 3919.35 484.43 220.19 4623.97 647.36 5271.32 279.30 5550.62
450 mm 0.450 20.500 23.800 22.15 0.406 28.14 4261.00 89610.00 112626.92 4876.20 602.70 273.95 5752.85 805.40 6558.24 310.65 6868.89
500 mm 0.500 22.800 26.500 24.65 0.451 34.79 5269.00 89610.00 112626.92 6029.65 745.26 338.75 7113.66 995.91 8109.57 342.00 8451.57
560 mm 0.560 25.500 29.600 27.55 0.505 43.55 6090.00 89610.00 112626.92 7042.25 870.42 395.63 8308.31 1163.16 9471.47 0.000 9471.47
630 mm 0.630 28.700 33.300 31.00 0.568 55.13 7676.00 89610.00 112626.92 8881.43 1097.74 498.96 10478.13 1466.94 11945.07 0.000 11945.07
710 mm 0.710 32.300 37.400 34.85 0.640 69.85 9766.00 89610.00 112626.92 11293.41 1395.87 634.46 13323.74 1865.32 15189.06 0.000 15189.06
800 mm 0.800 36.400 42.100 39.25 0.722 88.65 12394.00 89610.00 112626.92 14332.36 1771.48 805.19 16909.03 2367.26 19276.29 0.000 19276.29
900 mm 0.900 41.000 47.400 44.20 0.812 112.30 15701.00 89610.00 112626.92 18156.54 2244.15 1020.03 21420.72 2998.90 24419.62 0.000 24419.62
1000 mm 1.000 45.500 52.600 49.05 0.902 138.48 19362.00 89610.00 112626.92 22389.95 2767.40 1257.87 26415.22 3698.13 30113.35 0.000 30113.35
40 mm 0.040 2.40 2.90 2.65 0.035 0.29 45.00 89610.00 112626.92 51.43 6.36 2.89 60.67 8.49 69.16 37.05 106.21
50 mm 0.050 3.00 3.50 3.25 0.044 0.45 69.00 89610.00 112626.92 78.86 9.75 4.43 93.04 13.03 106.07 37.05 143.12
63 mm 0.063 3.80 4.40 4.10 0.055 0.72 106.00 89610.00 112626.92 121.68 15.04 6.84 143.55 20.10 163.65 41.33 204.97
75 mm 0.075 4.50 5.20 4.85 0.065 1.01 150.00 89610.00 112626.92 172.09 21.27 9.67 203.02 28.42 231.45 45.60 277.05
90 mm 0.090 5.40 6.20 5.80 0.078 1.45 214.00 89610.00 112626.92 245.70 30.37 13.80 289.87 40.58 330.46 51.30 381.76
110 mm 0.110 6.60 7.50 7.05 0.096 2.15 320.00 89610.00 112626.92 367.12 45.38 20.62 433.12 60.64 493.75 58.43 552.18
125 mm 0.125 7.50 8.50 8.00 0.109 2.78 412.00 89610.00 112626.92 472.76 58.43 26.56 557.75 78.09 635.84 71.25 707.09
140 mm 0.140 8.40 9.50 8.95 0.122 3.48 516.00 89610.00 112626.92 592.14 73.19 33.27 698.59 97.80 796.40 75.53 871.92
160 mm 0.160 9.60 10.80 10.20 0.140 4.54 671.00 89610.00 112626.92 770.19 95.20 43.27 908.65 127.21 1035.87 81.23 1117.09
180 mm 0.180 10.80 12.10 11.45 0.157 5.73 850.00 89610.00 112626.92 975.28 120.54 54.79 1150.62 161.09 1311.70 89.78 1401.48
200 mm 0.200 12.00 13.40 12.70 0.175 7.06 1050.00 89610.00 112626.92 1204.42 148.87 67.66 1420.95 198.93 1619.88 96.90 1716.78
225 mm 0.225 13.50 15.10 14.30 0.196 8.95 1357.00 89610.00 112626.92 1552.59 191.90 87.22 1831.72 256.44 2088.16 106.88 2195.03
250 mm 0.250 15.00 16.70 15.85 0.218 11.02 1677.00 89610.00 112626.92 1917.92 237.06 107.75 2262.73 316.78 2579.51 114.00 2693.51
280 mm 0.280 16.80 18.70 17.75 0.245 13.82 2100.00 89610.00 112626.92 2402.18 296.91 134.95 2834.04 396.77 3230.81 125.40 3356.21
315 mm 0.315 18.90 21.00 19.95 0.275 17.48 2659.00 89610.00 112626.92 3041.11 375.88 170.85 3587.84 502.30 4090.14 225.15 4315.29
355 mm 0.355 21.20 23.60 22.40 0.310 22.12 3329.00 89610.00 112626.92 3812.64 471.24 214.19 4498.08 629.73 5127.81 250.80 5378.61
400 mm 0.400 23.90 27.70 25.80 0.348 28.66 4383.00 89610.00 112626.92 5009.72 619.20 281.45 5910.37 827.45 6737.82 279.30 7017.12
450 mm 0.450 26.90 31.20 29.05 0.392 36.30 5462.00 89610.00 112626.92 6255.83 773.22 351.45 7380.51 1033.27 8413.78 310.65 8724.43
500 mm 0.500 29.90 34.60 32.25 0.436 44.78 6734.00 89610.00 112626.92 7713.26 953.36 433.33 9099.94 1273.99 10373.94 342.00 10715.94
560 mm 0.560 33.50 38.80 36.15 0.488 56.22 7788.00 89610.00 112626.92 9017.33 1114.54 506.59 10638.46 1489.38 12127.85 0.00 12127.85
630 mm 0.630 37.70 43.60 40.65 0.549 71.12 9854.00 89610.00 112626.92 11409.20 1410.18 640.97 13460.35 1884.45 15344.79 0.00 15344.79
710 mm 0.710 42.40 49.00 45.70 0.619 90.13 12487.00 89610.00 112626.92 14457.76 1786.98 812.24 17056.97 2387.98 19444.95 0.00 19444.95
800 mm 0.800 47.80 55.20 51.50 0.697 114.44 15854.00 89610.00 112626.92 18356.37 2268.85 1031.26 21656.48 3031.91 24688.39 0.00 24688.39
900 mm 0.900 53.80 62.10 57.95 0.784 144.87 20070.00 89610.00 112626.92 23237.70 2872.18 1305.49 27415.37 3838.15 31253.52 0.00 31253.52
32 mm 0.032 2.40 2.90 2.65 0.027 0.23 35.00 89610.00 112626.92 40.05 4.95 2.25 47.25 6.61 53.86 29.93 83.79
40 mm 0.040 3.00 3.50 3.25 0.034 0.35 53.00 89610.00 112626.92 60.75 7.51 3.41 71.68 10.03 81.71 37.05 118.76
50 mm 0.050 3.70 4.30 4.00 0.042 0.55 83.00 89610.00 112626.92 94.94 11.74 5.33 112.01 15.68 127.70 37.05 164.75
63 mm 0.063 4.70 5.40 5.05 0.053 0.87 128.00 89610.00 112626.92 147.00 18.17 8.26 173.42 24.28 197.70 41.33 239.03
75 mm 0.075 5.60 6.40 6.00 0.063 1.23 180.00 89610.00 112626.92 206.88 25.57 11.62 244.07 34.17 278.24 45.60 323.84
90 mm 0.090 6.70 7.60 7.15 0.076 1.76 256.00 89610.00 112626.92 294.45 36.39 16.54 347.39 48.63 396.03 51.30 447.33
110 mm 0.110 8.10 9.20 8.65 0.093 2.60 381.00 89610.00 112626.92 437.91 54.13 24.60 516.64 72.33 588.97 58.43 647.39
125 mm 0.125 9.20 10.40 9.80 0.105 3.35 495.00 89610.00 112626.92 568.29 70.24 31.93 670.45 93.86 764.32 71.25 835.57
140 mm 0.140 10.30 11.60 10.95 0.118 4.20 620.00 89610.00 112626.92 711.73 87.97 39.99 839.69 117.56 957.24 75.53 1032.77
160 mm 0.160 11.80 13.20 12.50 0.135 5.47 807.00 89610.00 112626.92 926.69 114.54 52.06 1093.29 153.06 1246.35 81.23 1327.57
180 mm 0.180 13.30 14.90 14.10 0.152 6.94 1021.00 89610.00 112626.92 1172.85 144.96 65.89 1383.71 193.72 1577.43 89.78 1667.20
200 mm 0.200 14.80 16.50 15.65 0.169 8.57 1259.00 89610.00 112626.92 1446.29 178.76 81.25 1706.30 238.88 1945.18 96.90 2042.08
225 mm 0.225 16.60 18.50 17.55 0.190 10.81 1633.00 89610.00 112626.92 1869.34 231.05 105.02 2205.41 308.76 2514.17 106.88 2621.05
250 mm 0.250 18.40 20.50 19.45 0.211 13.31 2016.00 89610.00 112626.92 2307.10 285.16 129.61 2721.87 381.06 3102.93 114.00 3216.93
280 mm 0.280 20.60 22.90 21.75 0.237 16.68 2523.00 89610.00 112626.92 2887.63 356.91 162.23 3406.77 476.95 3883.72 125.40 4009.12
315 mm 0.315 23.20 25.80 24.50 0.266 21.13 3194.00 89610.00 112626.92 3656.02 451.88 205.40 4313.30 603.86 4917.17 225.15 5142.32
355 mm 0.355 26.20 29.10 27.65 0.300 26.87 4004.00 89610.00 112626.92 4591.57 567.52 257.95 5417.04 758.39 6175.43 250.80 6426.23
400 mm 0.400 29.50 34.20 31.85 0.336 34.81 5259.00 89610.00 112626.92 6020.18 744.09 338.21 7102.49 994.35 8096.83 279.30 8376.13
450 mm 0.450 33.10 38.30 35.70 0.379 43.91 6567.00 89610.00 112626.92 7527.14 930.35 422.87 8880.37 1243.25 10123.62 310.65 10434.27
500 mm 0.500 36.80 42.60 39.70 0.421 54.25 8099.00 89610.00 112626.92 9285.27 1147.66 521.65 10954.58 1533.64 12488.22 342.00 12830.22
560 mm 0.560 41.20 47.60 44.40 0.471 67.96 9305.00 89610.00 112626.92 10791.10 1333.78 606.24 12731.13 1782.36 14513.48 0.00 14513.48
630 mm 0.630 46.40 53.60 50.00 0.530 86.10 11787.00 89610.00 112626.92 13669.57 1689.56 767.96 16127.08 2257.79 18384.87 0.00 18384.87
710 mm 0.710 52.30 60.40 56.35 0.597 109.35 14972.00 89610.00 112626.92 17363.07 2146.08 975.46 20484.60 2867.84 23352.44 0.00 23352.44
800 mm 0.800 58.90 68.00 63.45 0.673 138.74 19070.00 89610.00 112626.92 22103.80 2732.03 1241.79 26077.62 3650.87 29728.48 0.00 29728.48
421 of 613
5 RATES OF HDPE PIPES 10.0 Kg/Sqcm - PE - 100 Grade- 12.50 Ksc
Manufacture, supply, & delivery of HDPE pipes conforming to IS 4984 - 1995 including transportation to any where in A.P,including excise duty, sale tax but
excluding specials etc., complete. ( Supply upto 90 mm dia in coil & above 90 mm dia straight length in 6 M.)
Table 17 Pg.267 PE:100 - 12.50 ksc
Wt of Resin Rate Revised Total
Max SSR resin Total Cost
pipe OD in pipe OD Min thick Av.thick Avg. ID pipe SSR Rate as on Pipe Rate CED VAT OH&CP Supply Laying &
thick in rate Sub-total Supply, LL
mm in Mts in mm in mm in "m" Kg/Rm 12/2012 per Rm Cost per Jointing
mm &Jointing
Rm
M P1 A1 A2 P2 12.36% 5.00% 14%
25 mm 0.025 2.30 2.80 2.55 0.020 0.17 - 89610.00 112626.92 27.25 3.37 1.53 32.15 4.50 36.65 29.93 66.57
32 mm 0.032 2.90 3.40 3.15 0.026 0.27 46.00 89610.00 112626.92 51.90 6.41 2.92 61.23 8.57 69.80 29.93 99.73
40 mm 0.040 3.70 4.30 4.00 0.032 0.43 69.00 89610.00 112626.92 78.35 9.68 4.40 92.43 12.94 105.37 37.05 142.42
50 mm 0.050 4.60 5.30 4.95 0.040 0.66 108.00 89610.00 112626.92 122.48 15.14 6.88 144.49 20.23 164.72 37.05 201.77
63 mm 0.063 5.70 6.50 6.10 0.051 1.03 170.00 89610.00 112626.92 192.53 23.80 10.82 227.15 31.80 258.95 41.33 300.27
75 mm 0.075 6.80 7.70 7.25 0.061 1.46 242.00 89610.00 112626.92 273.89 33.85 15.39 323.13 45.24 368.36 45.60 413.96
90 mm 0.090 8.20 9.30 8.75 0.073 2.11 344.00 89610.00 112626.92 390.15 48.22 21.92 460.29 64.44 524.73 51.30 576.03
110 mm 0.110 10.00 11.20 10.60 0.089 3.13 517.00 89610.00 112626.92 585.40 72.36 32.89 690.64 96.69 787.33 58.43 845.76
125 mm 0.125 11.30 12.70 12.00 0.101 4.03 663.00 89610.00 112626.92 751.03 92.83 42.19 886.05 124.05 1010.09 71.25 1081.34
140 mm 0.140 12.70 14.20 13.45 0.113 5.05 834.00 89610.00 112626.92 944.49 116.74 53.06 1114.29 156.00 1270.30 75.53 1345.82
160 mm 0.160 14.50 16.20 15.35 0.129 6.59 1087.00 89610.00 112626.92 1231.14 152.17 69.17 1452.47 203.35 1655.82 81.23 1737.04
180 mm 0.180 16.30 18.20 17.25 0.146 8.33 1372.00 89610.00 112626.92 1554.25 192.11 87.32 1833.67 256.71 2090.38 89.78 2180.16
200 mm 0.200 18.10 20.20 19.15 0.162 10.28 1699.00 89610.00 112626.92 1923.82 237.78 108.08 2269.69 317.76 2587.44 96.90 2684.34
225 mm 0.225 20.40 22.70 21.55 0.182 13.02 2143.00 89610.00 112626.92 2427.61 300.05 136.38 2864.05 400.97 3265.02 106.88 3371.89
250 mm 0.250 22.60 25.10 23.85 0.202 16.01 2647.00 89610.00 112626.92 2997.14 370.45 168.38 3535.96 495.03 4031.00 114.00 4145.00
280 mm 0.280 25.30 28.10 26.70 0.227 20.08 3326.00 89610.00 112626.92 3765.03 465.36 211.52 4441.91 621.87 5063.78 125.40 5189.18
315 mm 0.315 28.50 28.10 28.30 0.258 24.09 4193.00 89610.00 112626.92 4719.70 583.36 265.15 5568.21 779.55 6347.76 225.15 6572.91
355 mm 0.355 32.10 31.60 31.85 0.291 30.56 5333.00 89610.00 112626.92 6001.14 741.74 337.14 7080.02 991.20 8071.23 250.80 8322.03
400 mm 0.400 36.20 41.90 39.05 0.322 41.85 6905.00 89610.00 112626.92 7820.00 966.55 439.33 9225.88 1291.62 10517.50 279.30 10796.80
450 mm 0.450 40.70 47.10 43.90 0.362 52.93 8729.00 89610.00 112626.92 9886.31 1221.95 555.41 11663.67 1632.91 13296.59 310.65 13607.24
500 mm 0.500 45.20 52.20 48.70 0.403 65.25 10783.00 89610.00 112626.92 12209.75 1509.12 685.94 14404.81 2016.67 16421.49 342.00 16763.49
560 mm 0.560 50.60 58.40 54.50 0.451 81.79 11992.00 89610.00 112626.92 13780.42 1703.26 774.18 16257.87 2276.10 18533.97 0.00 18533.97
630 mm 0.630 56.90 65.70 61.30 0.507 103.50 14138.00 89610.00 112626.92 16401.06 2027.17 921.41 19349.64 2708.95 22058.59 0.00 22058.59
422 of 613
5 RATES OF HDPE PIPES 10.0 Kg/Sqcm - PE - 100 Grade- 16.00 KSC
Manufacture, supply, & delivery of HDPE pipes conforming to IS 4984 - 1995 including transportation to any where in A.P,including excise duty, sale tax but
excluding specials etc., complete. ( Supply upto 90 mm dia in coil & above 90 mm dia straight length in 6 M.)
Table 17 Pg.267 PE:100 - 16.00 ksc
Wt of Resin Rate Revised Total
Max SSR resin Total Cost
pipe OD in pipe OD Min thick Av.thick Avg. ID pipe SSR Rate as on Pipe Rate CED VAT OH&CP Supply Laying &
thick in rate Sub-total Supply, LL
mm in Mts in mm in mm in "m" Kg/Rm 12/2012 per Rm Cost per Jointing
mm &Jointing
M P1 A1 A2 P2 10.32% 5.00% 14% Rm
25 mm 0.025 2.90 3.40 3.15 0.019 0.20 34.00 89610.00 112626.92 38.47 3.97 2.12 44.56 6.24 32.80 29.93 62.73
32 mm 0.032 3.70 4.30 4.00 0.024 0.33 56.00 89610.00 112626.92 63.27 6.53 3.49 73.29 10.26 83.55 29.93 113.48
40 mm 0.040 4.60 5.30 4.95 0.030 0.52 86.00 89610.00 112626.92 97.26 10.04 5.37 112.67 15.77 128.44 37.05 165.49
50 mm 0.050 5.70 6.50 6.10 0.038 0.80 134.00 89610.00 112626.92 151.38 15.62 8.35 175.36 24.55 199.91 37.05 236.96
63 mm 0.063 7.10 8.10 7.60 0.048 1.25 209.00 89610.00 112626.92 236.33 24.39 13.04 273.76 38.33 312.08 41.33 353.41
75 mm 0.075 8.50 9.60 9.05 0.057 1.77 237.00 89610.00 112626.92 275.75 28.46 15.21 319.41 44.72 364.13 45.60 409.73
90 mm 0.090 10.20 11.50 10.85 0.068 2.55 431.00 89610.00 112626.92 486.75 50.23 26.85 563.83 78.94 642.77 51.30 694.07
110 mm 0.110 12.40 13.90 13.15 0.084 3.78 631.00 89610.00 112626.92 713.68 73.65 39.37 826.69 115.74 942.43 58.43 1000.86
125 mm 0.125 14.10 15.80 14.95 0.095 4.88 813.00 89610.00 112626.92 919.80 94.92 50.74 1065.46 149.16 1214.63 71.25 1285.88
140 mm 0.140 15.80 17.60 16.70 0.107 6.11 1023.00 89610.00 112626.92 1156.67 119.37 63.80 1339.84 187.58 1527.42 75.53 1602.94
160 mm 0.160 18.10 20.20 19.15 0.122 8.01 1330.00 89610.00 112626.92 1505.10 155.33 83.02 1743.44 244.08 1987.53 81.23 2068.75
180 mm 0.180 20.30 22.60 21.45 0.137 10.10 1680.00 89610.00 112626.92 1900.77 196.16 104.85 2201.78 308.25 2510.03 89.78 2599.80
200 mm 0.200 22.60 25.10 23.85 0.152 12.47 2073.00 89610.00 112626.92 2345.72 242.08 129.39 2717.19 380.41 3097.60 96.90 3194.50
225 mm 0.225 25.40 28.20 26.80 0.171 15.77 2622.00 89610.00 112626.92 2966.82 306.18 163.65 3436.64 481.13 3917.77 106.88 4024.65
250 mm 0.250 28.20 31.30 29.75 0.191 19.45 3235.00 89610.00 112626.92 3660.36 377.75 201.91 4240.01 593.60 4833.62 114.00 4947.62
280 mm 0.280 31.60 35.00 33.30 0.213 24.39 4063.00 89610.00 112626.92 4596.29 474.34 253.53 5324.16 745.38 6069.54 125.40 6194.94
315 mm 0.315 35.50 39.30 37.40 0.240 30.82 5138.00 89610.00 112626.92 5811.97 599.80 320.59 6732.36 942.53 7674.89 225.15 7900.04
355 mm 0.355 40.00 44.20 42.10 0.271 39.11 6531.00 89610.00 112626.92 7386.15 762.25 407.42 8555.82 1197.81 9753.63 250.80 10004.43
400 mm 0.400 45.10 52.10 48.60 0.303 50.70 8437.00 89610.00 112626.92 9545.64 985.11 526.54 11057.29 1548.02 12605.31 279.30 12884.61
450 mm 0.450 50.80 58.70 54.75 0.341 64.24 10626.00 89610.00 112626.92 12030.78 1241.58 663.62 13935.98 1951.04 15887.01 310.65 16197.66
500 mm 0.500 56.40 65.10 60.75 0.379 79.22 12886.00 89610.00 112626.92 14618.25 1508.60 806.34 16933.20 2370.65 19303.84 342.00 19645.84
423 of 613
HDPE Specials
Manufacture, supply, & delivery of HDPE fittings conforming to IS 4984 - 1995 including
transportation to any where in A.P, Central excise duty, sale tax etc., complete
2 MS FLANGES
CED VAT OH&CP
S# Description Unit Basic Rate Total
10.32% 5.00% 14.00%
1 OD 50 mm Each 110.00 11.35 6.07 17.84 145.26
2 OD 63 mm Each 140.00 14.45 7.72 22.70 184.87
3 OD 75 mm Each 176.00 18.16 9.71 28.54 232.41
4 OD 90 mm Each 189.00 19.50 10.43 30.65 249.58
5 OD 110 mm Each 200.00 20.64 11.03 32.43 264.11
6 OD 125 mm Each 274.00 28.28 15.11 44.43 361.83
7 OD 140 mm Each 297.00 30.65 16.38 48.16 392.20
8 OD 160 mm Each 390.00 40.25 21.51 63.25 515.01
9 OD 180 mm Each 550.00 56.76 30.34 89.19 726.29
10 OD 200 mm Each 713.00 73.58 39.33 115.63 941.54
11 OD 225 mm Each 891.00 91.95 49.15 144.49 1176.59
12 OD 250 mm Each 1052.00 108.57 58.03 170.60 1389.20
13 OD 280 mm Each 1194.00 123.22 65.86 193.63 1576.71
14 OD 315 mm Each 1405.00 145.00 77.50 227.85 1855.35
15 OD 355 mm Each 2379.00 245.51 131.23 385.80 3141.54
16 OD 400 mm Each 2951.00 304.54 162.78 478.56 3896.89
17 OD 450 mm Each 3852.00 397.53 212.48 624.68 5086.68
18 OD 500 mm Each 4411.00 455.22 243.31 715.33 5824.86
424 of 613
3 HDPE END CAPS
CED VAT OH&CP
S# Description Unit Basic Rate Total
10.32% 5.00% 14.00%
1 OD 50 mm Each 41.00 4.23 2.26 6.65 54.14
2 OD 63 mm Each 50.00 5.16 2.76 8.11 66.03
3 OD 75 mm Each 63.00 6.50 3.48 10.22 83.19
4 OD 90 mm Each 83.00 8.57 4.58 13.46 109.60
5 OD 110 mm Each 95.00 9.80 5.24 15.41 125.45
6 OD 125 mm Each 131.00 13.52 7.23 21.24 172.99
7 OD 140 mm Each 153.00 15.79 8.44 24.81 202.04
8 OD 160 mm Each 234.00 24.15 12.91 37.95 309.00
9 OD 180 mm Each 380.00 39.22 20.96 61.62 501.80
10 OD 200 mm Each 415.00 42.83 22.89 67.30 548.02
11 OD 225 mm Each 433.00 44.69 23.88 70.22 571.79
12 OD 250 mm Each 615.00 63.47 33.92 99.73 812.13
13 OD 280 mm Each 629.00 64.91 34.70 102.01 830.61
14 OD 315 mm Each 861.00 88.86 47.49 139.63 1136.98
15 OD 355 mm Each 1329.00 137.15 73.31 215.52 1754.98
16 OD 400 mm Each 2321.00 239.53 128.03 376.40 3064.95
17 OD 450 mm Each 3733.00 385.25 205.91 605.38 4929.54
18 OD 500 mm Each 6879.00 709.91 379.45 1115.57 9083.93
4 HDPE REDUCERS
CED VAT OH&CP
S# Description Unit Basic Rate Total
10.32% 5.00% 14.00%
1 OD 50 mm x 63 mm Each 58.00 5.99 3.20 9.41 76.59
2 OD 63 mm x 75 mm Each 83.00 8.57 4.58 13.46 109.60
3 OD 75 mm x 90 mm Each 136.00 14.04 7.50 22.06 179.59
4 OD 90 mm x 110 mm Each 188.00 19.40 10.37 30.49 248.26
5 OD 110 mm x 125 mm Each 287.00 29.62 15.83 46.54 378.99
6 OD 125 mm x 140 mm Each 396.00 40.87 21.84 64.22 522.93
7 OD 140 mm x 160 mm Each 553.00 57.07 30.50 89.68 730.25
8 OD 160 mm x 180 mm Each 766.00 79.05 42.25 124.22 1011.53
9 OD 180 mm x 200 mm Each 990.00 102.17 54.61 160.55 1307.33
10 OD 200 mm x 225 mm Each 1215.00 125.39 67.02 197.04 1604.44
11 OD 225 mm x 250 mm Each 1657.00 171.00 91.40 268.72 2188.12
12 OD 250 mm x 280 mm Each 2353.00 242.83 129.79 381.59 3107.21
13 OD 280 mm x 315 mm Each 3327.00 343.35 183.52 539.54 4393.40
14 OD 315 mm x 355 mm Each 3815.00 393.71 210.44 618.68 5037.82
15 OD 355 mm x 400 mm Each 5384.00 555.63 296.98 873.13 7109.74
16 OD 400 mm x 450 mm Each 5585.00 576.37 308.07 905.72 7375.16
17 OD 450 mm x 500 mm Each 7161.00 739.02 395.00 1161.30 9456.32
425 of 613
5 HDPE EQUAL TEEs
CED VAT OH&CP
S# Description Unit Basic Rate Total
10.32% 5.00% 14.00%
1 OD 50 mm Each 80.00 8.26 4.41 12.97 105.64
2 OD 63 mm Each 126.00 13.00 6.95 20.43 166.39
3 OD 75 mm Each 153.00 15.79 8.44 24.81 202.04
4 OD 90 mm Each 269.00 27.76 14.84 43.62 355.22
5 OD 110 mm Each 318.00 32.82 17.54 51.57 419.93
6 OD 125 mm Each 479.00 49.43 26.42 77.68 632.53
7 OD 140 mm Each 661.00 68.22 36.46 107.19 872.87
8 OD 160 mm Each 1137.00 117.34 62.72 184.39 1501.44
9 OD 180 mm Each 1543.00 159.24 85.11 250.23 2037.58
10 OD 200 mm Each 2125.00 219.30 117.22 344.61 2806.13
11 OD 225 mm Each 3016.00 311.25 166.36 489.11 3982.72
12 OD 250 mm Each 4129.00 426.11 227.76 669.60 5452.47
13 OD 280 mm Each 5781.00 596.60 318.88 937.51 7633.99
14 OD 315 mm Each 8242.00 850.57 454.63 1336.61 10883.81
15 OD 355 mm Each 11752.00 1212.81 648.24 1905.83 15518.87
16 OD 400 mm Each 17212.00 1776.28 949.41 2791.28 22728.97
17 OD 450 mm Each 24450.00 2523.24 1348.66 3965.07 32286.97
18 OD 500 mm Each 33578.00 3465.25 1852.16 5445.36 44340.77
6 HDPE BENDS
CED VAT OH&CP
S# Description Unit Basic Rate Total
10.32% 5.00% 14.00%
1 OD 50 mm Each 50.00 5.16 2.76 8.11 66.03
2 OD 63 mm Each 111.00 11.46 6.12 18.00 146.58
3 OD 75 mm Each 144.00 14.86 7.94 23.35 190.16
4 OD 90 mm Each 248.00 25.59 13.68 40.22 327.49
5 OD 110 mm Each 327.00 33.75 18.04 53.03 431.81
6 OD 125 mm Each 481.00 49.64 26.53 78.00 635.18
7 OD 140 mm Each 634.00 65.43 34.97 102.82 837.22
8 OD 160 mm Each 946.00 97.63 52.18 153.41 1249.22
9 OD 180 mm Each 1358.00 140.15 74.91 220.23 1793.28
10 OD 200 mm Each 1840.00 189.89 101.49 298.39 2429.78
11 OD 225 mm Each 2610.00 269.35 143.97 423.26 3446.58
12 OD 250 mm Each 3578.00 369.25 197.36 580.25 4724.86
13 OD 280 mm Each 5159.00 532.41 284.57 836.64 6812.62
14 OD 315 mm Each 7134.00 736.23 393.51 1156.92 9420.66
15 OD 355 mm Each 9889.00 1020.54 545.48 1603.70 13058.73
16 OD 400 mm Each 14917.00 1539.43 822.82 2419.10 19698.35
17 OD 450 mm Each 21930.00 2263.18 1209.66 3556.40 28959.23
18 OD 500 mm Each 29731.00 3068.24 1639.96 4821.49 39260.69
426 of 613
7 HDPE Electrofusion Ferrule Tapping Saddle:
Supply, Delivery and fixing of Electrofusion Ferrule Tapping Saddle conforming to EN 12201-3 ,
manufactured from virgin resin of PE-80/PE-100 having blue/black color using food grade
compound raw material with quality assurance certifificate from quality agencies like
DVGMK/KIWA/SPGN/WRC etc. for usage in drinking water systems and having working
pressure of 10 bar. The cost is inclusive of testing all materials, labour, all taxes, inspection
charges, transportation charges upto site, insurance , loading , unloading, stacking and fixing
etc. complete and as directed by Dept. authorities
PP Saddles Prices
CED VAT OH&CP
Description Unit Basic Rate Total
10.32% 5.00% 14.00%
40 x1/2" to 3/4" Each 67.50 8.34 3.79 11.15 90.78
50x1/2" to 3/4" Each 75.00 9.27 4.21 12.39 100.87
63x1/2" to 1" Each 97.50 12.05 5.48 16.10 131.13
75x1/2" to 1 1/2" Each 127.50 15.76 7.16 21.06 171.48
90x1/2" to 1 1/2" Each 157.50 19.47 8.85 26.01 211.83
110x1/2" to 1 1/2" 187.50 23.18 10.53 30.97 252.18
427 of 613
Manufacture,supply and delivery of RCC Socket and Spigot Pipes conforming to B.I.S. 458/2003 -Rate per Meter of effective length- Excluding Transportation but
including Central Excice Duty, VAT etc.complete.
Cost of RCC S/S NP2 Pipes & Conveyance Charges :
RCC NP2 S/S Pipes: per RMT RCC NP2 S/S Pipes: per RMT
1 100 178.00 5100 5532 3.30 1.43 46000 40060 0.77 -4.57 174.85 10.00 Km 3.90 18.45 9.86 207.06 28.99 236.05
2 150 209.00 5100 5532 4.95 2.14 46000 40060 0.83 -4.93 206.21 10.00 Km 5.10 21.81 11.66 244.77 34.27 279.04
3 200 254.00 5100 5532 6.05 2.62 46000 40060 0.97 -5.76 250.85 10.00 Km 7.30 26.64 14.24 299.03 41.86 340.90
4 225 277.00 5100 5532 6.87 2.97 46000 40060 1.05 -6.24 273.74 10.00 Km 8.30 29.11 15.56 326.70 45.74 372.44
5 250 297.00 5100 5532 7.70 3.33 46000 40060 1.17 -6.95 293.38 10.00 Km 10.00 31.31 16.73 351.42 49.20 400.62
6 300 417.00 5100 5532 11.22 4.85 46000 40060 1.57 -9.33 412.52 10.00 Km 14.00 44.02 23.53 494.07 69.17 563.24
7 350 534.00 5100 5532 13.37 5.78 46000 40060 1.91 -11.34 528.44 10.00 Km 17.10 56.30 30.09 631.93 88.47 720.40
8 400 592.00 5100 5532 15.48 6.69 46000 40060 2.27 -13.48 585.21 10.00 Km 20.90 62.55 33.43 702.10 98.29 800.39
9 450 736.00 5100 5532 18.47 7.99 46000 40060 2.75 -16.33 727.65 10.00 Km 23.70 77.54 41.44 870.34 121.85 992.19
10 500 847.00 5100 5532 20.78 8.99 46000 40060 3.24 -19.24 836.74 10.00 Km 26.40 89.08 47.61 999.83 139.98 1139.81
11 600 1194.00 5100 5532 31.67 13.69 46000 40060 4.25 -25.24 1182.45 10.00 Km 36.90 125.84 67.26 1412.45 197.74 1610.19
12 700 1549.00 5100 5532 41.78 18.07 46000 40060 5.82 -34.57 1532.50 10.00 Km 43.20 162.61 86.92 1825.23 255.53 2080.76
13 800 1983.00 5100 5532 47.28 20.45 46000 40060 7.93 -47.10 1956.34 10.00 Km 61.40 208.23 111.30 2337.27 327.22 2664.49
14 900 2499.00 5100 5532 58.06 25.10 46000 40060 10.47 -62.19 2461.92 10.00 Km 96.70 264.05 141.13 2963.80 414.93 3378.73
15 1000 3027.00 5100 5532 69.93 30.24 46000 40060 12.45 -73.95 2983.29 10.00 Km 106.00 318.81 170.41 3578.51 500.99 4079.50
16 1100 3569.00 5100 5532 82.91 35.85 46000 40060 14.5 -86.12 3518.73 10.00 Km 116.40 375.15 200.51 4210.78 589.51 4800.29
17 1200 4054.00 5100 5532 98.52 42.60 46000 40060 17.23 -102.34 3994.26 10.00 Km 126.40 425.25 227.30 4773.21 668.25 5441.46
18 1400 5742.00 5100 5532 122.05 52.78 46000 40060 23.21 -137.86 5656.92 10.00 Km 149.50 599.22 320.28 6725.92 941.63 7667.55
19 1600 7100.00 5100 5532 147.78 63.90 46000 40060 28.92 -171.77 6992.13 10.00 Km 173.60 739.50 395.26 8300.50 1162.07 9462.56
20 1800 8027.00 5100 5532 188.02 81.31 46000 40060 36.26 -215.37 7892.94 10.00 Km 207.40 835.95 446.81 9383.10 1313.63 10696.74
RCC NP3 S/S Pipes: per RMT RCC NP3 S/S Pipes: per RMT
1 300 985.00 5100 5532 14.40 6.23 46000 40060 2.58 -15.32 975.90 10.00 Km 33.40 104.16 55.67 1169.14 163.68 1332.81
2 350 1278.00 5100 5532 36.00 15.57 46000 40060 3.73 -22.15 1271.41 10.00 Km 36.30 134.96 72.13 1514.80 212.07 1726.87
3 400 1416.00 5100 5532 39.60 17.12 46000 40060 4.08 -24.23 1408.89 10.00 Km 48.40 150.39 80.38 1688.07 236.33 1924.40
4 450 1564.00 5100 5532 43.20 18.68 46000 40060 4.57 -27.14 1555.54 10.00 Km 52.30 165.93 88.69 1862.45 260.74 2123.20
5 500 1788.00 5100 5532 50.40 21.79 46000 40060 5.60 -33.26 1776.53 10.00 Km 56.70 189.19 101.12 2123.54 297.30 2420.84
7 600 2506.00 5100 5532 64.80 28.02 46000 40060 8.19 -48.65 2485.38 10.00 Km 78.10 264.55 141.40 2969.43 415.72 3385.15
9 700 3195.00 5100 5532 75.60 32.69 46000 40060 11.45 -68.01 3159.68 10.00 Km 114.10 337.85 180.58 3792.22 530.91 4323.13
10 800 4226.00 5100 5532 97.20 42.03 46000 40060 15.70 -93.25 4174.78 10.00 Km 144.90 445.79 238.27 5003.74 700.52 5704.27
11 900 5310.00 5100 5532 124.00 53.62 46000 40060 20.96 -124.49 5239.13 10.00 Km 144.90 555.63 296.98 6236.64 873.13 7109.77
12 1000 6027.00 5100 5532 160.00 69.19 46000 40060 24.18 -143.62 5952.57 10.00 Km 151.10 629.90 336.68 7070.24 989.83 8060.08
13 1100 7109.00 5100 5532 176.00 76.11 46000 40060 30.65 -182.05 7003.06 10.00 Km 160.20 739.25 395.13 8297.63 1161.67 9459.30
14 1200 8384.00 5100 5532 200.00 86.48 46000 40060 37.12 -220.48 8250.01 10.00 Km 176.70 869.64 464.82 9761.16 1366.56 11127.72
15 1400 11105.00 5100 5532 260.00 112.43 46000 40060 49.76 -295.55 10921.87 10.00 Km 225.90 1150.45 614.91 12913.14 1807.84 14720.98
16 1600 14408.00 5100 5532 308.00 133.19 46000 40060 68.95 -409.54 14131.65 10.00 Km 263.30 1485.56 794.03 16674.53 2334.43 19008.97
17 1800 19084.00 5100 5532 368.00 159.13 46000 40060 96.46 -572.93 18670.20 10.00 Km 352.20 1963.11 1049.28 22034.78 3084.87 25119.65
RUBBER RINGS- RCC S/S Pipes
Manufacture,supply and delivery of Rubber rings to suit RCC Socket and Spigot
Pipes confirming to B.I.S. 5382/ 1985 (RATE PER EACH RUBBER RING) including
Transportation,Central Excice Duty, Sales Tax but Excluding VAT etc.complete.
2* 2*
6.286 6.286
NP 3 - Class Pipes NP 2 - Class Pipes
Vol. Barral
Dia of Barral Steel Qty Dia of Vol. Cement Steel Qty
Radius Cement Thickne Radius of
Sl Pipe in Thicknes in Kgs- Sl Pipe in per 1 Qty in in Kgs-
of Pipe per 1 Qty in Kg ss in Pipe
Mts s in Mts NP3 Mts Rmt Kg NP2
Rmt Mts
1 0.080 0.025 0.0525 0.00825 2.89 0.75 1 0.080 0.025 0.0525 0.008 2.89 0.75
2 0.100 0.025 0.060 0.00942 3.30 0.81 2 0.100 0.025 0.060 0.009 3.30 0.77
3 0.150 0.025 0.090 0.01414 4.95 1.05 3 0.150 0.025 0.090 0.014 4.95 0.83
4 0.200 0.030 0.120 0.02262 7.92 1.40 4 0.200 0.025 0.110 0.017 6.05 0.97
5 0.225 0.030 0.128 0.02403 8.41 1.62 5 0.225 0.025 0.125 0.020 6.87 1.05
6 0.250 0.030 0.140 0.02639 9.24 1.83 6 0.250 0.025 0.140 0.022 7.70 1.17
7 0.300 0.040 0.170 0.04273 14.95 2.58 7 0.300 0.030 0.170 0.032 11.22 1.57
8 0.350 0.075 0.210 0.09896 34.64 3.73 8 0.350 0.032 0.190 0.038 13.37 1.91
9 0.400 0.075 0.240 0.1131 39.58 4.08 9 0.400 0.032 0.220 0.044 15.48 2.27
10 0.450 0.075 0.260 0.12252 42.88 4.57 10 0.450 0.035 0.240 0.053 18.47 2.75
11 0.500 0.075 0.290 0.13666 47.83 5.60 11 0.500 0.035 0.270 0.059 20.78 3.24
12 0.600 0.085 0.340 0.18158 63.55 8.19 12 0.600 0.045 0.320 0.090 31.67 4.25
13 0.700 0.085 0.390 0.20829 72.90 11.45 13 0.700 0.050 0.380 0.119 41.78 5.82
14 0.800 0.095 0.450 0.26861 94.01 15.70 14 0.800 0.050 0.430 0.135 47.28 7.93
15 0.900 0.100 0.500 0.31416 109.96 20.96 15 0.900 0.055 0.480 0.166 58.06 10.47
16 1.000 0.115 0.560 0.40464 141.62 24.18 16 1.000 0.060 0.530 0.200 69.93 12.45
17 1.100 0.115 0.610 0.44077 154.27 30.65 17 1.100 0.065 0.580 0.237 82.91 14.50
18 1.200 0.120 0.660 0.49763 174.17 37.12 18 1.200 0.070 0.640 0.281 98.52 17.23
19 1.400 0.135 0.770 0.65314 228.60 49.76 19 1.400 0.075 0.740 0.349 122.05 23.21
20 1.600 0.140 0.870 0.76529 267.85 68.95 20 1.600 0.080 0.840 0.422 147.78 28.92
21 1.800 0.150 0.980 0.92363 323.27 96.46 21 1.800 0.090 0.950 0.537 188.02 36.26
22 2.000 0.170 1.090 1.16427 407.50 107.26 22 2.000 0.100 1.050 0.660 230.91 50.42
23 2.200 0.185 1.190 1.38324 484.14 142.66 23 2.200 0.110 1.160 0.802 280.61 61.65
24 2.400 0.200 1.300 1.63363 571.77 161.49
25 2.600 0.215 1.410 1.90475 666.66 190.64
Manufacture,supply and delivery of RCC Plain Ended Pipes conforming to B.I.S. 458/2003 -Rate per Meter of effective length- Excluding Transportation but
including Central Excice Duty, VAT etc.complete.
RCC NP2 P/E Pipes: per RMT RCC NP2 P/E Pipes: per RMT
Market
SSR Rate Market Variation Sub Total
Basic Rate Cement Variation in SSR Rate Rate of MS rods Actual Rate
of Rate of in MS Lead Lead
Dia of of Pipe required Cement of MS rods MS required of Pipe per CED VAT Cost per OH&CP
Cement/ Cement rods Km Charges
Sl # Pipes per Rmt per 1 Rmt Cost / MT rods/ per 1 Rmt Rmt Rm Total Rate
MT / MT Cost
in mm MT
1 80 129.00 5100 5532 2.89 1.25 46000 40060 0.75 -4.45 125.79 10.00 Km 2.50
2 100 149.00 5100 5532 3.30 1.43 46000 32060 0.77 -10.73 139.69 10.00 Km 2.90 14.72 7.87 165.17 23.12 188.30
3 150 176.00 5100 5532 4.95 2.14 46000 32060 0.83 -11.57 166.57 10.00 Km 4.50 17.65 9.44 198.16 27.74 225.90
4 200 209.00 5100 5532 6.05 2.62 46000 32060 0.97 -13.52 198.09 10.00 Km 5.60 21.02 11.24 235.95 33.03 268.98
5 225 227.00 5100 5532 6.87 2.97 46000 32060 1.05 -14.64 215.34 10.00 Km 6.90 22.93 12.26 257.43 36.04 293.47
6 250 243.00 5100 5532 7.70 3.33 46000 32060 1.17 -16.31 230.02 10.00 Km 7.70 24.53 13.11 275.36 38.55 313.92
7 300 348.00 5100 5532 11.22 4.85 46000 32060 1.57 -21.89 330.96 10.00 Km 11.20 35.31 18.87 396.35 55.49 451.84
8 350 433.00 5100 5532 13.37 5.78 46000 32060 1.91 -26.62 412.16 10.00 Km 15.50 44.13 23.59 495.38 69.35 564.73
9 400 499.00 5100 5532 15.48 6.69 46000 32060 2.27 -31.64 474.05 10.00 Km 17.90 50.77 27.14 569.86 79.78 649.64
10 450 612.00 5100 5532 18.47 7.99 46000 32060 2.75 -38.33 581.65 10.00 Km 22.60 62.36 33.33 699.94 97.99 797.94
11 500 673.00 5100 5532 20.78 8.99 46000 32060 3.24 -45.16 636.82 10.00 Km 25.20 68.32 36.52 766.86 107.36 874.22
12 600 995.00 5100 5532 31.67 13.69 46000 32060 4.25 -59.24 949.45 10.00 Km 36.70 101.77 54.40 1142.32 159.92 1302.24
13 700 1276.00 5100 5532 41.78 18.07 46000 32060 5.82 -81.13 1212.94 10.00 Km 47.90 130.12 69.55 1460.51 204.47 1664.98
14 800 1570.00 5100 5532 47.28 20.45 46000 32060 7.93 -110.54 1479.90 10.00 Km 54.10 158.31 84.62 1776.93 248.77 2025.70
15 900 1972.00 5100 5532 58.06 25.10 46000 32060 10.47 -145.95 1851.16 10.00 Km 60.20 197.25 105.43 2214.04 309.97 2524.01
16 1000 2390.00 5100 5532 69.93 30.24 46000 32060 12.45 -173.55 2246.69 10.00 Km 97.30 241.90 129.29 2715.19 380.13 3095.31
17 1100 2850.00 5100 5532 82.91 35.85 46000 32060 14.50 -202.12 2683.73 10.00 Km 104.20 287.71 153.78 3229.42 452.12 3681.54
18 1200 3393.00 5100 5532 98.52 42.60 46000 32060 17.23 -240.18 3195.42 10.00 Km 115.70 341.71 182.64 3835.47 536.97 4372.44
19 1400 4609.00 5100 5532 122.05 52.78 46000 32060 23.21 -323.54 4338.24 10.00 Km 134.20 461.56 246.70 5180.69 725.30 5905.99
20 1600 5357.00 5100 5532 147.78 63.90 46000 32060 28.92 -403.13 5017.77 10.00 Km 151.10 533.43 285.11 5987.41 838.24 6825.65
21 1800 7009.00 5100 5532 188.02 81.31 46000 32060 36.26 -505.45 6584.86 10.00 Km 169.50 697.05 372.57 7823.98 1095.36 8919.33
22 2000 5100 5532 230.91 99.85 46000 32060 50.42 -702.83 -602.99
23 2200 5100 5532 280.61 121.34 46000 32060 61.65 -859.38 -738.04
RCC NP3 P/E Pipes: per RMT RCC NP3 P/E Pipes: per RMT
Market
Dia of SSR Rate Market Variation Sub Total
Basic Rate Cement Variation in SSR Rate Rate of MS rods Actual Rate
of Rate of in MS Lead Lead
Sl # Pipes of Pipe
Cement/ Cement
required Cement of MS rods MS required
rods
of Pipe per
Km Charges
CED VAT Cost per OH&CP
in mm per Rmt per 1 Rmt Cost / MT rods/ per 1 Rmt Rmt Rm Total Rate
MT / MT Cost
MT
14.00%
P1 C1 C2 Wc R1 S1 S2 Ws R2 P1+R1+R2 10.32% 5.00%
300 778.00 6.47 -35.96 748.50 10.00 Km 27.20 80.05 42.79 898.54 125.80 1024.34
7 5100 5532 14.95 46000 32060 2.58
350 980.00 14.98 32060 -51.99 942.98 10.00 Km 29.60 100.37 53.65 1126.60 157.72 1284.32
8 5100 5532 34.64 46000 3.73
400 1084.00 17.12 32060 -56.87 1044.24 10.00 Km 35.80 111.46 59.58 1251.08 175.15 1426.23
9 5100 5532 39.58 46000 4.08
450 1238.00 18.54 32060 -63.70 1192.84 10.00 Km 39.80 127.21 67.99 1427.84 199.90 1627.74
10 5100 5532 42.88 46000 4.57
500 1349.00 20.68 32060 -78.06 1291.62 10.00 Km 43.00 137.73 73.62 1545.97 216.44 1762.41
11 5100 5532 47.83 46000 5.6
600 2020.00 27.48 32060 -114.17 1933.32 10.00 Km 67.90 206.53 110.39 2318.13 324.54 2642.67
12 5100 5532 63.55 46000 8.19
700 2512.00 31.52 32060 -159.61 2383.92 10.00 Km 76.50 253.91 135.72 2850.05 399.01 3249.05
13 5100 5532 72.90 46000 11.45
800 3317.00 40.65 32060 -218.85 3138.80 10.00 Km 88.80 333.09 178.03 3738.72 523.42 4262.15
14 5100 5532 94.01 46000 15.7
900 4166.00 47.55 32060 -292.17 3921.37 10.00 Km 124.90 417.58 223.19 4687.04 656.19 5343.23
15 5100 5532 109.96 46000 20.96
1000 5170.00 61.24 32060 -337.06 4894.18 10.00 Km 145.00 520.04 277.96 5837.19 817.21 6654.39
16 5100 5532 141.62 46000 24.18
1100 6098.00 66.71 32060 -427.25 5737.46 10.00 Km 156.60 608.27 325.12 6827.44 955.84 7783.29
17 5100 5532 154.27 46000 30.65
1200 7181.00 75.31 32060 -517.44 6738.88 10.00 Km 172.00 713.20 381.20 8005.28 1120.74 9126.02
18 5100 5532 174.17 46000 37.12
1400 9291.00 98.85 32060 -693.63 8696.22 10.00 Km 224.40 920.61 492.06 10333.28 1446.66 11779.94
19 5100 5532 228.60 46000 49.76
1600 12054.00 115.82 32060 -961.14 11208.69 10.00 Km 262.80 1183.86 632.77 13288.11 1860.34 15148.45
20 5100 5532 267.85 46000 68.95
21 1800 15973.00 5100 5532 323.27 139.79 46000 32060 96.46 -1344.61 14768.17 10.00 Km 352.20 1560.42 834.04 17514.84 2452.08 19966.91
RCC COLLARS
Manufacture,supply and delivery of RCC Collars confirming to B.I.S. 458/20035
(RATE PER EACH COLLAR) suitable for Plain Ended Pipes including
Transportation,Central Excice Duty, VAT etc.complete.
Table 19
pipe Min Resin
Pipe OD Max thick Av.thick Pipe ID Wt of SSR resin Actual CED VAT Sub OH&CP Total per
OD in thick in SSR Rate Rate as on
in mm in mm in mm "m" pipe rate pipe rate 12.36% 5.00% Total 14% RM
"m" mm 12/2012
M P1 A1 A2 P2
20 0.020 0.00 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
25 0.025 0.00 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
32 0.032 0.00 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
40 0.040 0.00 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
50 0.050 0.00 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
63 0.063 - - #VALUE! ### #VALUE! - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
75 0.075 - - #VALUE! ### #VALUE! - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
90 0.090 1.30 1.70 1.50 0.087 0.60 59.00 64172 77053 66.40 8.21 3.73 78.34 10.97 89.30
110 0.110 1.60 2.00 1.80 0.106 0.89 89.00 64172 77053 99.86 12.34 5.61 117.81 16.49 134.30
125 0.125 1.80 2.20 2.00 0.121 1.12 117.00 64172 77053 130.71 16.16 7.34 154.21 21.59 175.80
140 0.140 2.00 2.40 2.20 0.136 1.38 142.00 64172 77053 158.90 19.64 8.93 187.47 26.25 213.71
160 0.160 2.30 2.80 2.55 0.155 1.83 189.00 64172 77053 211.38 26.13 11.88 249.38 34.91 284.30
180 0.180 2.60 3.10 2.85 0.174 2.30 237.00 64172 77053 265.14 32.77 14.90 312.81 43.79 356.60
200 0.200 2.90 3.40 3.15 0.194 2.82 302.00 64172 77053 336.57 41.60 18.91 397.07 55.59 452.66
225 0.225 3.30 3.90 3.60 0.218 3.63 389.00 64172 77053 433.43 53.57 24.35 511.35 71.59 582.94
250 0.250 3.60 4.20 3.90 0.242 4.37 468.00 64172 77053 #REF! #REF! #REF! #REF! #REF! #REF!
280 0.280 4.10 4.80 4.45 0.271 5.59 601.00 64172 77053 #REF! #REF! #REF! #REF! #REF! #REF!
315 0.315 4.60 5.30 4.95 0.305 6.99 758.00 64172 77053 #REF! #REF! #REF! #REF! #REF! #REF!
355 0.355 5.10 5.90 5.50 0.344 8.76 - 64172 77053 #REF! #REF! #REF! #REF! #REF! #REF!
400 0.400 5.80 6.70 6.25 0.388 11.21 - 64172 77053 #REF! #REF! #REF! #REF! #REF! #REF!
450 0.450 6.50 7.50 7.00 0.436 14.13 - 64172 77053 #REF! #REF! #REF! #REF! #REF! #REF!
500 0.500 7.20 8.30 7.75 0.485 17.38 - 64172 77053 #REF! #REF! #REF! #REF! #REF! #REF!
560 0.560 8.10 9.40 8.75 0.543 21.97 - 64172 77053 #REF! #REF! #REF! #REF! #REF! #REF!
630 0.630 9.10 10.50 9.80 0.610 27.69 - 64172 77053 #REF! #REF! #REF! #REF! #REF! #REF!
S.S. RATES FOR U-PVC PIPES ( 4 Kg/Cm2 ) Class:2 uPVC: 4.0Ksc or 0.40 MPa
Manufacture, Supply and delivery of Unplasticised PVCs Pipes for potable water supplies conforming to IS : 4985/2000 (third revision) with bell ends (Socket) as per
specification in light Grey/Natural Ivory Grey/ Any other Color (except White) inclusive of transportation to the sub-divisional stores anywhere in AP including Excise
duty and Sales Tax etc.
Table 19
M P1 A1 A2 P2
Table 19
M P1 A1 A2 P2
20 0.020 - - - - - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
25 0.025 - - - - - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
40 0.040 1.40 1.80 1.60 0.037 0.28 27.00 64172 77053 30.42 3.76 1.71 35.89 5.03 40.92
50 0.050 1.70 2.10 1.90 0.046 0.42 42.00 64172 77053 47.09 5.82 2.65 55.56 7.78 63.34
63 0.063 2.20 2.70 2.45 0.058 0.68 65.00 64172 77053 73.27 9.06 4.12 86.44 12.10 98.54
75 0.075 2.60 3.10 2.85 0.069 0.94 89.00 64172 77053 100.46 12.42 5.64 118.52 16.59 135.12
90 0.090 3.10 3.70 3.40 0.083 1.34 129.00 64172 77053 145.41 17.97 8.17 171.56 24.02 195.57
110 0.110 3.70 4.30 4.00 0.102 1.93 187.00 64172 77053 210.64 26.03 11.83 248.50 34.79 283.29
125 0.125 4.30 5.00 4.65 0.116 2.55 238.00 64172 77053 269.20 33.27 15.12 317.59 44.46 362.05
140 0.140 4.80 5.50 5.15 0.130 3.16 308.00 64172 77053 346.71 42.85 19.48 409.04 57.27 466.31
160 0.160 5.40 6.20 5.80 0.148 4.07 398.00 64172 77053 447.85 55.35 25.16 528.37 73.97 602.34
180 0.180 6.10 7.10 6.60 0.167 5.21 512.00 64172 77053 575.80 71.17 32.35 679.31 95.10 774.42
200 0.200 6.80 7.90 7.35 0.185 6.45 623.00 64172 77053 701.93 86.76 39.43 828.13 115.94 944.06
225 0.225 7.60 8.80 8.20 0.209 8.10 833.00 64172 77053 932.10 115.21 52.37 1099.67 153.95 1253.63
250 0.250 8.50 9.80 9.15 0.232 10.04 1027.00 64172 77053 1149.85 142.12 64.60 1356.57 189.92 1546.49
280 0.280 9.50 11.00 10.25 0.260 12.60 1296.00 64172 77053 1450.13 179.24 81.47 1710.83 239.52 1950.35
315 0.315 10.70 12.40 11.55 0.292 15.97 1629.00 64172 77053 1824.37 225.49 102.49 2152.36 301.33 2453.69
355 0.355 12.00 13.80 12.90 0.329 20.10 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
400 0.400 13.50 15.60 14.55 0.371 25.55 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
450 0.450 15.20 17.50 16.35 0.417 32.30 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
500 0.500 16.90 19.50 18.20 0.464 39.94 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
560 0.560 18.90 21.80 20.35 0.519 50.03 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
630 0.630 21.30 24.50 22.90 0.584 63.33 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
S.S. RATES FOR UPVC PIPES ( 8.00 Kg/Cm2 ) Class:4 uPVC: 8.0 Ksc or 0.80 MPa
Manufacture, Supply and delivery of Unplasticised PVCs Pipes for potable water supplies conforming to IS : 4985/2000 (third revision) with bell ends (Socket) as per
specification in light Grey/Natural Ivory Grey/ Any other Color (except White) inclusive of transportation to the sub-divisional stores anywhere in AP including Excise
duty and Sales Tax etc.
Table 19
pipe Min Resin
Pipe OD Max thick Av.thick Wt of SSR resin Actual CED VAT Sub OH&CP Total per
OD in thick in pipe ID SSR Rate Rate as on
in mm in mm in mm pipe rate pipe rate 12.36% 5.00% Total 14% RM
Mts mm 12/2012
M P1 A1 A2 P2
20 0.020 - - - - - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
25 0.025 1.20 1.60 1.40 0.022 0.15 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
32 0.032 1.50 1.90 1.70 0.029 0.23 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
40 0.040 1.80 2.20 2.00 0.036 0.35 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
50 0.050 2.30 2.80 2.55 0.045 0.55 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
63 0.063 2.80 3.30 3.05 0.057 0.83 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
75 0.075 3.40 4.00 3.70 0.068 1.20 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
90 0.090 4.00 4.60 4.30 0.081 1.68 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
110 0.110 4.90 5.60 5.25 0.100 2.51 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
125 0.125 5.60 6.40 6.00 0.113 3.25 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
140 0.140 6.30 7.30 6.80 0.126 4.13 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
160 0.160 7.20 8.30 7.75 0.145 5.37 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
180 0.180 8.00 9.20 8.60 0.163 6.71 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
200 0.200 8.90 10.30 9.60 0.181 8.33 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
225 0.225 10.00 11.50 10.75 0.204 10.49 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
250 0.250 11.20 12.90 12.05 0.226 13.06 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
280 0.280 12.50 14.40 13.45 0.253 16.33 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
315 0.315 14.00 16.10 15.05 0.285 20.56 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
355 0.355 15.80 18.20 17.00 0.321 26.17 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
400 0.400 17.80 20.50 19.15 0.362 33.22 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
450 0.450 20.00 23.00 21.50 0.407 41.97 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
500 0.500 22.30 25.70 24.00 0.452 52.04 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
560 0.560 24.90 28.70 26.80 0.506 65.09 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
630 0.630 28.00 32.20 30.10 0.570 82.26 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
S.S. RATES FOR UPVC PIPES ( 10.00 Kg/Cm2 ) Class:5 uPVC: 10.0 Ksc or 1.0 MPa
Manufacture, Supply and delivery of Unplasticised PVCs Pipes for potable water supplies conforming to IS : 4985/2000 (third revision) with bell ends (Socket) as per
specification in light Grey/Natural Ivory Grey/ Any other Color (except White) inclusive of transportation to the sub-divisional stores anywhere in AP including Excise
duty and Sales Tax etc.
Table 19
pipe Min Resin
Pipe OD Max thick Av.thick Wt of SSR resin Actual CED VAT Sub OH&CP Total per
OD in thick in pipe ID SSR Rate Rate as on
in mm in mm in mm pipe rate pipe rate 12.36% 5.00% Total 14% RM
Mts mm 12/2012
M P1 A1 A2 P2
20 0.020 1.10 1.50 1.30 0.017 0.11 12.00 64172 77053 13.36 1.65 0.75 15.76 2.21 17.96
25 0.025 1.40 1.80 1.60 0.022 0.17 18.00 64172 77053 20.09 2.48 1.13 23.70 3.32 27.02
32 0.032 1.80 2.20 2.00 0.028 0.27 29.00 64172 77053 32.34 4.00 1.82 38.16 5.34 43.50
40 0.040 2.20 2.70 2.45 0.035 0.42 44.00 64172 77053 49.13 6.07 2.76 57.96 8.11 66.08
50 0.050 2.80 3.30 3.05 0.044 0.65 68.00 64172 77053 75.98 9.39 4.27 89.64 12.55 102.19
63 0.063 3.50 4.10 3.80 0.055 1.02 99.00 64172 77053 111.54 13.79 6.27 131.59 18.42 150.02
75 0.075 4.20 4.90 4.55 0.066 1.46 142.00 64172 77053 159.87 19.76 8.98 188.61 26.41 215.02
90 0.090 5.00 5.70 5.35 0.079 2.06 201.00 64172 77053 226.25 27.96 12.71 266.92 37.37 304.29
110 0.110 6.10 7.10 6.60 0.097 3.11 301.00 64172 77053 339.04 41.91 19.05 399.99 56.00 455.99
125 0.125 6.90 8.00 7.45 0.110 3.99 393.00 64172 77053 441.82 54.61 24.82 521.25 72.97 594.22
140 0.140 7.70 8.90 8.30 0.123 4.98 486.00 64172 77053 546.93 67.60 30.73 645.26 90.34 735.60
160 0.160 8.80 10.20 9.50 0.141 6.51 639.00 64172 77053 718.70 88.83 40.38 847.91 118.71 966.61
180 0.180 9.90 11.40 10.65 0.159 8.22 817.00 64172 77053 917.54 113.41 51.55 1082.49 151.55 1234.04
200 0.200 11.00 12.70 11.85 0.176 10.16 995.00 64172 77053 1119.28 138.34 62.88 1320.51 184.87 1505.38
225 0.225 12.40 14.30 13.35 0.198 12.87 1326.00 64172 77053 1483.51 183.36 83.34 1750.21 245.03 1995.24
250 0.250 13.80 15.90 14.85 0.220 15.91 1618.00 64172 77053 1812.66 224.04 101.83 2138.53 299.39 2437.93
280 0.280 15.40 17.80 16.60 0.247 19.92 2048.00 64172 77053 2291.74 283.26 128.75 2703.74 378.52 3082.27
315 0.315 17.30 19.90 18.60 0.278 25.11 2584.00 64172 77053 2891.32 357.37 162.43 3411.12 477.56 3888.67
355 0.355 19.60 22.60 21.10 0.313 32.09 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
400 0.400 22.00 25.30 23.65 0.353 40.55 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
450 0.450 24.80 28.60 26.70 0.397 51.48 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
500 0.500 27.50 31.70 29.60 0.441 63.43 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
560 0.560 30.80 35.50 33.15 0.494 79.56 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
630 0.630 34.70 40.00 37.35 0.555 100.83 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
S.S. RATES FOR UPVC PIPES ( 12.50 Kg/Cm2 ) Class:6 uPVC: 12.50 Ksc or 1.25 MPa
Manufacture, Supply and delivery of Unplasticised PVCs Pipes for potable water supplies conforming to IS : 4985/2000 (third revision) with bell ends (Socket) as per
specification in light Grey/Natural Ivory Grey/ Any other Color (except White) inclusive of transportation to the sub-divisional stores anywhere in AP including Excise
duty and Sales Tax etc.
Table 19
pipe Min Resin
Pipe OD Max thick Av.thick Wt of SSR resin Actual CED VAT Sub OH&CP Total per
OD in thick in pipe ID SSR Rate Rate as on
in mm in mm in mm pipe rate pipe rate 12.36% 5.00% Total 14% RM
Mts mm 12/2012
M P1 A1 A2 P2
20 0.020 1.40 1.80 1.60 0.017 0.13 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
25 0.025 1.70 2.10 1.90 0.021 0.20 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
32 0.032 2.20 2.70 2.45 0.027 0.33 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
40 0.040 2.80 3.30 3.05 0.034 0.51 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
50 0.050 3.40 4.00 3.70 0.043 0.78 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
63 0.063 4.30 5.00 4.65 0.054 1.24 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
75 0.075 5.10 5.90 5.50 0.064 1.74 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
90 0.090 6.10 7.10 6.60 0.077 2.51 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
110 0.110 7.50 8.70 8.10 0.094 3.76 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
125 0.125 8.50 9.80 9.15 0.107 4.83 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
140 0.140 9.50 11.00 10.25 0.120 6.06 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
160 0.160 10.90 12.60 11.75 0.137 7.94 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
180 0.180 12.20 14.10 13.15 0.154 9.99 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
200 0.200 13.60 15.70 14.65 0.171 12.37 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
225 0.225 15.30 17.60 16.45 0.192 15.63 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
250 0.250 17.00 19.60 18.30 0.213 19.32 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
280 0.280 19.00 21.90 20.45 0.239 24.18 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
315 0.315 21.40 24.70 23.05 0.269 30.65 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
355 0.355 24.10 27.80 25.95 0.303 38.90 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
400 0.400 27.20 31.30 29.25 0.342 49.40 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
450 0.450 30.50 35.10 32.80 0.384 62.34 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
500 0.500 33.90 39.00 36.45 0.427 76.97 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
560 0.560 38.00 43.70 40.85 0.478 96.61 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
630 0.630 42.70 49.20 45.95 0.538 122.25 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Pipe OD
in mm
20
25
32
40
50
63
75
90
110
125
140
160
180
200
225
250
280
315
355
400
450
500
560
630
Pipe OD
in mm
20
25
32
40
50
63
75
90
110
125
140
160
180
200
225
250
280
315
355
400
450
500
560
630
Pipe OD
in mm
20
25
32
40
50
63
75
90
110
125
140
160
180
200
225
250
280
315
355
400
450
500
560
630
Pipe OD
in mm
20
25
32
40
50
63
75
90
110
125
140
160
180
200
225
250
280
315
355
400
450
500
560
630
Pipe OD
in mm
20
25
32
40
50
63
75
90
110
125
140
160
180
200
225
250
280
315
355
400
450
500
560
630
Pipe OD
in mm
10.0Ksc
20
25
32
40
50
63
75
90
110
125
140
160
180
200
225
250
280
315
355
400
450
500
560
630
Table: 8
Manufacture, Supply and Delivery of AC Pressure Pipes conforming to BIS # 1592-2003 as amended from time to time (mazza Process) including cost of
Material, incidental handling, loading , packing and inclusive of transportation, unloading, stacking at Dept. stores and inclusive of all taxes and other Govt.
levies etc. complete.
3 125 279.00 5100 5532 7.99 3.45 64156 64156 1.4 0.00 282.45 28.25 34.91 15.87 361.48 50.61 412.09 125
4 150 393.00 5100 5532 11.32 4.89 64156 64156 2.0 0.00 397.89 39.79 49.18 22.35 509.22 71.29 580.51 150
5 200 651.00 5100 5532 19.08 8.25 64156 64156 3.4 0.00 659.25 65.92 81.48 37.04 843.69 118.12 961.81 200
6 250 824.00 5100 5532 24.24 10.48 64156 64156 4.3 0.00 834.48 83.45 103.14 46.88 1067.95 149.51 1217.47 250
7 300 1154.00 5100 5532 34.18 14.78 64156 64156 6.0 0.00 1168.78 116.88 144.46 65.66 1495.78 209.41 1705.19 300
8 350 1409.00 5100 5532 41.61 17.99 64156 64156 7.3 0.00 1426.99 142.70 176.38 80.17 1826.24 255.67 2081.91 350
9 400 1831.00 5100 5532 54.35 23.50 64156 64156 9.6 0.00 1854.50 185.45 229.22 104.19 2373.35 332.27 2705.62 400
10 450 2171.00 5100 5532 67.44 29.16 64156 64156 11.9 0.00 2200.16 220.02 271.94 123.61 2815.72 394.20 3209.92 450
11 500 2681.00 5100 5532 81.93 35.43 64156 64156 14.5 0.00 2716.43 271.64 335.75 152.61 3476.43 486.70 3963.13 500
12 600 3812.00 5100 5532 118.70 51.33 64156 64156 20.9 0.00 3863.33 386.33 477.51 217.04 4944.21 692.19 5636.40 600
13 700 5045.00 5100 5532 149.77 64.77 64156 64156 26.4 0.00 5109.77 510.98 631.57 287.07 6539.38 915.51 7454.89 700
14 750 5750.00 5100 5532 170.98 73.94 64156 64156 30.2 0.00 5823.94 582.39 719.84 327.19 7453.36 1043.47 8496.83 750
15 800 6578.00 5100 5532 195.96 84.74 64156 64156 34.6 0.00 6662.74 666.27 823.51 374.31 8526.84 1193.76 9720.60 800
16 850 7379.00 5100 5532 220.12 95.19 64156 64156 38.8 0.00 7474.19 747.42 923.81 419.90 9565.31 1339.14 10904.46 850
17 900 8227.00 5100 5532 245.68 106.24 64156 64156 43.4 0.00 8333.24 833.32 1029.99 468.16 10664.71 1493.06 12157.77 900
18 1000 10156.00 5100 5532 303.97 131.44 64156 64156 53.6 0.00 10287.44 1028.74 1271.53 577.95 13165.66 1843.19 15008.86 1000
455 of 613
AC-Pressure Pipes - Cl-20 - TP:20 ksc AC-Pressure Pipes - Cl-20 - TP:20 ksc
Asbestos Sub
SSR Rate Market Cement SSR Rate Market Variation Actual Transport
Basic Rate Variation in Fibre
Dia of of Pipe per of Rate of required of Rate of in Rate of ation CED @ VAT @ Total OH&CP Total Rate
Cement Required
Pipes Rmt
Cement/ Cement / per 1 Rmt
Cost
Asbestos Asbestos
per 1 Rmt
Asbestos Pipe per Cost 12.36% 5% Cost per @14% per Rm Dia in
Sl # MT MT (Kg) Fibre/MT Fibre/MT Fibre Cost Rmt @10% Rm
in (Kg) "mm"
mm
P1+R1+
P1 C1 C2 Wc R1 F1 F2 Wf R2
R2
1 80 177.00 5100 5532 5.35 2.31 64156 64156 0.9 0.00 179.31 17.93 22.16 10.07 229.48 32.13 261.61 80
2 100 100
272.00 5100 5532 8.18 3.54 64156 64156 1.4 0.00 275.54 27.55 34.06 15.48 352.63 49.37 402.00
3 125 125
348.00 5100 5532 10.39 4.49 64156 64156 1.8 0.00 352.49 35.25 43.57 19.80 451.11 63.16 514.27
4 150 150
489.00 5100 5532 14.67 6.34 64156 64156 2.6 0.00 495.34 49.53 61.22 27.83 633.93 88.75 722.68
5 200 200
833.00 5100 5532 26.08 11.28 64156 64156 4.6 0.00 844.28 84.43 104.35 47.43 1080.49 151.27 1231.76
6 250 250
1069.00 5100 5532 33.53 14.50 64156 64156 5.9 0.00 1083.50 108.35 133.92 60.87 1386.64 194.13 1580.77
7 300 300
1503.00 5100 5532 47.15 20.39 64156 64156 8.3 0.00 1523.39 152.34 188.29 85.58 1949.60 272.94 2222.55
8 350 350
1830.00 5100 5532 55.44 23.97 64156 64156 9.8 0.00 1853.97 185.40 229.15 104.16 2372.68 332.18 2704.85
9 400 400
2393.00 5100 5532 73.83 31.93 64156 64156 13.0 0.00 2424.93 242.49 299.72 136.23 3103.37 434.47 3537.84
10 450 450
2880.00 5100 5532 92.05 39.80 64156 64156 16.2 0.00 2919.80 291.98 360.89 164.03 3736.71 523.14 4259.85
11 500 500
3524.00 5100 5532 112.27 48.55 64156 64156 19.8 0.00 3572.55 357.25 441.57 200.71 4572.07 640.09 5212.16
12 600 600
4977.00 5100 5532 158.70 68.63 64156 64156 28.0 0.00 5045.63 504.56 623.64 283.46 6457.29 904.02 7361.31
13 700 700
6844.00 5100 5532 206.70 89.38 64156 64156 36.5 0.00 6933.38 693.34 856.97 389.52 8873.20 1242.25 10115.45
14 750 750
7901.00 5100 5532 236.46 102.25 64156 64156 41.7 0.00 8003.25 800.32 989.20 449.62 10242.40 1433.94 11676.34
15 800 800
8651.00 5100 5532 270.67 117.04 64156 64156 47.8 0.00 8768.04 876.80 1083.73 492.59 11221.17 1570.96 12792.13
16 850 850
10069.00 5100 5532 304.59 131.71 64156 64156 53.8 0.00 10200.71 1020.07 1260.81 573.08 13054.66 1827.65 14882.32
17 900 900
11250.00 5100 5532 340.50 147.24 64156 64156 60.1 0.00 11397.24 1139.72 1408.70 640.30 14585.96 2042.03 16627.99
18 1000 1000
13811.00 5100 5532 421.39 182.22 64156 64156 74.4 0.00 13993.22 1399.32 1729.56 786.14 17908.24 2507.15 20415.40
456 of 613
AC-Pressure Pipes - Cl-25 - TP:25 ksc AC-Pressure Pipes - Cl-25 - TP:25 ksc
Asbestos Sub
SSR Rate Market Cement SSR Rate Market Variation Actual Transport
Basic Rate Variation in Fibre
Dia of of Pipe per of Rate of required of Rate of in Rate of ation CED @ VAT @ Total OH&CP Total Rate
Cement Required
Pipes Rmt
Cement/ Cement / per 1 Rmt
Cost
Asbestos Asbestos
per 1 Rmt
Asbestos Pipe per Cost 12.36% 5% Cost per @14% per Rm Dia in
Sl # MT MT (Kg) Fibre/MT Fibre/MT Fibre Cost Rmt @10% Rm
in (Kg) "mm"
mm
P1+R1+
P1 C1 C2 Wc R1 F1 F2 Wf R2
R2
1 80 221.00 5100 5532 6.74 2.92 64156 64156 1.2 0.00 223.92 22.39 27.68 12.58 286.56 40.12 326.68 80
2 100 100
334.00 5100 5532 10.27 4.44 64156 64156 1.8 0.00 338.44 33.84 41.83 19.01 433.13 60.64 493.77
3 125 125
436.00 5100 5532 13.32 5.76 64156 64156 2.4 0.00 441.76 44.18 54.60 24.82 565.35 79.15 644.50
4 150 150
615.00 5100 5532 19.18 8.29 64156 64156 3.4 0.00 623.29 62.33 77.04 35.02 797.68 111.67 909.35
5 200 200
1057.00 5100 5532 33.41 14.45 64156 64156 5.9 0.00 1071.45 107.14 132.43 60.19 1371.22 191.97 1563.19
6 250 250
1339.00 5100 5532 42.39 18.33 64156 64156 7.5 0.00 1357.33 135.73 167.77 76.25 1737.08 243.19 1980.28
7 300 300
1920.00 5100 5532 61.63 26.65 64156 64156 10.9 0.00 1946.65 194.67 240.61 109.36 2491.29 348.78 2840.07
8 350 350
2307.00 5100 5532 71.97 31.12 64156 64156 12.7 0.00 2338.12 233.81 288.99 131.36 2992.28 418.92 3411.20
9 400 400
2970.00 5100 5532 92.72 40.09 64156 64156 16.4 0.00 3010.09 301.01 372.05 169.11 3852.26 539.32 4391.57
10 450 450
3607.00 5100 5532 116.09 50.20 64156 64156 20.5 0.00 3657.20 365.72 452.03 205.46 4680.41 655.26 5335.67
11 500 500
4424.00 5100 5532 142.07 61.44 64156 64156 25.1 0.00 4485.44 448.54 554.40 251.99 5740.37 803.65 6544.02
12 600 600
6343.00 5100 5532 203.82 88.14 64156 64156 36.0 0.00 6431.14 643.11 794.89 361.30 8230.44 1152.26 9382.70
13 700 700
8850.00 5100 5532 267.78 115.80 64156 64156 47.3 0.00 8965.80 896.58 1108.17 503.70 11474.25 1606.39 13080.64
14 750 750
10126.00 5100 5532 306.56 132.56 64156 64156 54.1 0.00 10258.56 1025.86 1267.96 576.33 13128.70 1838.02 14966.72
15 800 800
11487.00 5100 5532 350.48 151.56 64156 64156 61.9 0.00 11638.56 1163.86 1438.53 653.85 14894.79 2085.27 16980.06
16 850 850
12936.00 5100 5532 394.65 170.66 64156 64156 69.6 0.00 13106.66 1310.67 1619.98 736.33 16773.64 2348.31 19121.95
17 900 900
14469.00 5100 5532 441.44 190.89 64156 64156 77.9 0.00 14659.89 1465.99 1811.96 823.59 18761.43 2626.60 21388.03
18 1000 17793.00 5100 5532 546.05 236.12 64156 64156 96.4 0.00 18029.12 1802.91 2228.40 ### 23073.31 3230.26 26303.57 1000.00
457 of 613
BP : Bursting Pressure (BP/TP : Ranges from 1.5 to 2.0 and BP/WP : Ranges from 3 to 4)
458 of 613
Table:9 &10 : AC Couplings with RR's
Manufacture, Supply, Delivery of AC Couplings including Cost of Rubber Rings to suit AC
Couplings including cost of material, incidental handling, packing, Transportation and
unloading at Dept. stores and inclusive of all taxes and duties etc. complete
AC Couplings with RR's-Cl:15
Basic Couplin
Dia of RR's CED OH & CP Total Cost
Sl# Rate, g with VAT @5% Sub Total
Pipe Each Set @12.36% @14% , Each
Each RR's
459 of 613
AC Couplings with RR's-Cl:20
Basic Couplin
Dia of RR's CED OH & CP Total Cost
Sl# Rate, g with VAT @5% Sub Total
Pipe Each Set @12.36% @14% , Each
Each RR's
1 80 84.00 56.00 140.00 17.30 7.87 165.17 23.12 188.29
2 100 109.00 68.00 177.00 21.88 9.94 208.82 29.23 238.06
3 125 140.00 89.00 229.00 28.30 12.87 270.17 37.82 307.99
4 150 185.00 113.00 298.00 36.83 16.74 351.57 49.22 400.79
5 200 297.00 117.00 414.00 51.17 23.26 488.43 68.38 556.81
6 250 401.00 135.00 536.00 66.25 30.11 632.36 88.53 720.89
7 300 538.00 135.00 673.00 83.18 37.81 793.99 111.16 905.15
8 350 696.00 154.00 850.00 105.06 47.75 1002.81 140.39 1143.21
9 400 1084.00 188.00 1272.00 157.22 71.46 1500.68 210.10 1710.78
10 450 1311.00 221.00 1532.00 189.36 86.07 1807.42 253.04 2060.46
11 500 1584.00 255.00 1839.00 227.30 103.32 2169.62 303.75 2473.36
12 600 1821.00 289.00 2110.00 260.80 118.54 2489.34 348.51 2837.84
13 700 2585.00 601.00 3186.00 393.79 178.99 3758.78 526.23 4285.01
14 750 2961.00 624.00 3585.00 443.11 201.41 4229.51 592.13 4821.64
15 800 3332.00 670.00 4002.00 494.65 224.83 4721.48 661.01 5382.49
16 850 3727.00 747.00 4474.00 552.99 251.35 5278.34 738.97 6017.30
17 900 4142.00 785.00 4927.00 608.98 276.80 5812.78 813.79 6626.56
18 1000 5038.00 870.00 5908.00 730.23 331.91 6970.14 975.82 7945.96
460 of 613
AC Couplings with RR's-Cl:25
Basic Couplin
Dia of RR's CED OH & CP Total Cost
Sl# Rate, g with VAT @5% Sub Total
Pipe Each Set @12.36% @14% , Each
Each RR's
1 80 97.00 56.00 153.00 18.91 8.60 180.51 25.27 205.78
2 100 131.00 68.00 199.00 24.60 11.18 234.78 32.87 267.64
3 125 169.00 89.00 258.00 31.89 14.49 304.38 42.61 347.00
4 150 230.00 113.00 343.00 42.39 19.27 404.66 56.65 461.32
5 200 379.00 117.00 496.00 61.31 27.87 585.17 81.92 667.09
6 250 512.00 135.00 647.00 79.97 36.35 763.32 106.86 870.18
7 300 693.00 135.00 828.00 102.34 46.52 976.86 136.76 1113.62
8 350 889.00 154.00 1043.00 128.91 58.60 1230.51 172.27 1402.78
9 400 1389.00 188.00 1577.00 194.92 88.60 1860.51 260.47 2120.98
10 450 1683.00 221.00 1904.00 235.33 106.97 2246.30 314.48 2560.78
11 500 2024.00 255.00 2279.00 281.68 128.03 2688.72 376.42 3065.14
12 600 2329.00 289.00 2618.00 323.58 147.08 3088.66 432.41 3521.08
13 700 3361.00 601.00 3962.00 489.70 222.59 4674.29 654.40 5328.69
14 750 3821.00 624.00 4445.00 549.40 249.72 5244.12 734.18 5978.30
15 800 4312.00 670.00 4982.00 615.78 279.89 5877.66 822.87 6700.54
16 850 4832.00 747.00 5579.00 689.56 313.43 6581.99 921.48 7503.47
17 900 5379.00 785.00 6164.00 761.87 346.29 7272.16 1018.10 8290.27
18 1000 6565.00 870.00 7435.00 918.97 417.70 8771.66 1228.03 9999.70
461 of 613
Weights of AC- Pressure Pipes conforming to BIS-1592-2003
ID of
S# Pipe in Barrrel Thickness in "mm" Wt. of Pipe in Kg/m
"m"
Cl:10 Cl:15 Cl:20 Cl:25 Cl:10 Cl:15 Cl:20 Cl:25
1 0.050 9.5 9.5 11.0 13.5 3.55 3.55 4.22 5.39
2 0.060 9.5 9.5 11.0 13.5 4.15 4.15 4.91 6.23
3 0.080 9.5 9.5 11.0 13.5 5.34 5.34 6.29 7.93
4 0.100 9.5 10.0 13.5 16.5 6.54 6.91 9.63 12.08
5 0.125 9.5 11.0 14.0 17.5 8.03 9.40 12.23 15.67
6 0.150 9.5 13.0 16.5 21.0 9.52 13.31 17.26 22.56
7 0.200 16.5 22.0 27.5 0.00 22.45 30.69 39.31
8 0.250 17.0 23.0 28.5 0.00 28.52 39.45 49.87
9 0.300 20.0 27.0 34.5 0.00 40.21 55.47 72.51
10 0.350 21.0 27.5 35.0 0.00 48.95 65.23 84.67
11 0.400 24.0 32.0 39.5 0.00 63.94 86.86 109.08
12 0.450 26.5 35.5 44.0 0.00 79.34 108.29 136.57
13 0.500 29.0 39.0 48.5 0.00 96.39 132.08 167.15
14 0.600 35.0 46.0 58.0 0.00 139.64 186.71 239.79
15 0.700 38.0 51.5 65.5 0.00 176.21 243.17 315.04
16 0.750 40.5 55.0 70.0 0.00 201.16 278.19 360.65
17 0.800 43.5 59.0 75.0 0.00 230.54 318.44 412.33
18 0.850 46.0 62.5 79.5 0.00 258.97 358.34 464.30
19 0.900 48.5 66.0 84.0 0.00 289.04 400.59 519.34
20 1.000 54.0 73.5 93.5 0.00 357.61 495.76 642.41
462 of 613
S.S.RATES FOR NON- PRESSURE P.V.C_U PIPES (SEWERS) (S- 25) - SDR:51 _Conforming to IS: 15328_Solvent Cement Joints
Manufacture, supply, & delivery of Unplasticized Non-Pressure Polyvinyl Chloride(PVC-U) pipes of dark (any shade of Brown) for use in underground drainage &
sewerage system conforming to IS 15328/2003) with solvent cement jointing as per specification inclusive of transportation to the Sub-Divisional stores any where in
A.P, including Central Excise duty & VAT
Resin
pipe Min SSR
pipe OD Max thick Av.thick Wt of SSR Rate as Actual CED OH&CP Toal per
OD in thick in pipe ID Resin VAT 5% Sub Total
in mm in mm in mm pipe Rate on pipe rate 12.36% 14% RM
Mts mm rate
12/2012
M P1 A1 A2 P2
110 mm 0.110 - - #VALUE! #VALUE! #VALUE! - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
125 mm 0.125 - - #VALUE! #VALUE! #VALUE! - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
160 mm 0.160 - - 3.20 0.1536 2.29 248.00 64172 77053 275.97 34.11 15.50 325.58 45.58 371.17
200 mm 0.200 - - 3.90 0.1922 3.48 377.00 64172 77053 419.63 51.87 23.57 495.07 69.31 564.38
250 mm 0.250 - - 4.90 0.2402 5.47 584.00 64172 77053 650.95 80.46 36.57 767.97 107.52 875.49
315 mm 0.315 - - 6.20 0.3026 8.72 922.00 64172 77053 1028.72 127.15 57.79 1213.67 169.91 1383.58
400mm 0.400 - - 7.90 0.3842 14.11 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
500mm 0.500 - - 9.80 0.4804 21.88 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
630mm 0.630 - - 12.30 0.6054 34.61 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
S.S.RATES FOR NON- PRESSURE P.V.C_U PIPES (SEWERS) (S- 20) -SDR:41 _Conforming to IS: 15328_Solvent Cement Joints
Manufacture, supply, & delivery of Unplasticized Non-Pressure Polyvinyl Chloride(PVC-U) pipes of dark (any shade of Brown) for use in underground drainage &
sewerage system conforming to IS 15328/2003) with solvent cement jointing as per specification inclusive of transportation to the Sub-Divisional stores any where in
A.P, including Central Excise duty & VAT
Table 20 Solvent PVC-U S-20 SDR: 41 SN: 4
Resin
pipe Min SSR
pipe OD Max thick Av.thick Wt of SSR Rate as Actual CED OH&CP Toal per
OD in thick in pipe ID Resin VAT 5% Sub Total
in mm in mm in mm pipe Rate on pipe rate 12.36% 14% RM
Mts mm rate
12/2012
M P1 A1 A2 P2
110 mm 0.110 - - #VALUE! #VALUE! #VALUE! - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
125 mm 0.125 - - 3.20 0.1186 1.78 192.00 64172 77053 213.73 26.42 12.01 252.15 35.30 287.45
160 mm 0.160 - - 4.00 0.152 2.84 307.00 64172 77053 341.78 42.24 19.20 403.23 56.45 459.68
200 mm 0.200 - - 4.90 0.1902 4.35 466.00 64172 77053 519.29 64.18 29.17 612.65 85.77 698.42
250 mm 0.250 - - 6.20 0.2376 6.89 727.00 64172 77053 811.26 100.27 45.58 957.11 134.00 1091.10
315 mm 0.315 - - 7.70 0.2996 10.78 1141.00 64172 77053 1272.90 157.33 71.51 1501.74 210.24 1711.99
400mm 0.400 - - 9.80 0.3804 17.42 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
500mm 0.500 - - 12.30 0.4754 27.33 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
630mm 0.630 - - 15.40 0.5992 43.12 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
S.S.RATES FOR NON- PRESSURE P.V.C_U PIPES (SEWERS) (S- 16.5) - SDR:34 _Conforming to IS: 15328_Solvent Cement Joints
Manufacture, supply, & delivery of Unplasticized Non-Pressure Polyvinyl Chloride(PVC-U) pipes of dark (any shade of Brown) for use in underground drainage &
sewerage system conforming to IS 15328/2003) with solvent cement jointing as per specification inclusive of transportation to the Sub-Divisional stores any where in
A.P, including Central Excise duty & VAT
Table 20 Solvent PVC-U S-16.5 SDR: 34 SN: 8
Resin
pipe Min SSR
pipe OD Max thick Av.thick Wt of SSR Rate as Actual CED OH&CP Toal per
OD in thick in pipe ID Resin VAT 5% Sub Total
in mm in mm in mm pipe Rate on pipe rate 12.36% 14% RM
Mts mm rate
12/2012
M P1 A1 A2 P2
110 mm 0.110 - - 3.20 0.1036 1.56 169.00 64172 77053 188.05 23.24 10.56 221.86 31.06 252.92
125 mm 0.125 - - 3.70 0.1176 2.04 228.00 64172 77053 253.02 31.27 14.21 298.51 41.79 340.30
160 mm 0.160 - - 4.70 0.1506 3.32 356.00 64172 77053 396.69 49.03 22.29 468.00 65.52 533.53
200 mm 0.200 - - 5.90 0.1882 5.22 554.00 64172 77053 617.84 76.36 34.71 728.91 102.05 830.96
250 mm 0.250 - - 7.30 0.2354 8.07 858.00 64172 77053 956.76 118.26 53.75 1128.77 158.03 1286.80
315 mm 0.315 - - 9.20 0.2966 12.82 1355.00 64172 77053 1511.83 186.86 84.93 1783.62 249.71 2033.33
400mm 0.400 - - 11.70 0.3766 20.70 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
500mm 0.500 - - 14.60 0.4708 32.28 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
630mm 0.630 - - 18.40 0.5932 51.26 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
S.S.RATES FOR NON- PRESSURE P.V.C_U PIPES (SEWERS) (S- 25) -SDR:51 _Conforming to IS: 15328_Ring Tite
Manufacture, supply, & delivery of Unplasticized Non-Pressure Polyvinyl Chloride(PVC-U) pipes of dark (any shade of Brown) for use in underground drainage &
sewerage system conforming to IS 15328/2003) with Ring Tite jointing as per specification inclusive of transportation to the Sub-Divisional stores any where in A.P,
including Central Excise duty & VAT
Table 21 RRType PVC-U S-25 SDR: 51 SN: 2
Resin
pipe Min SSR
pipe OD Max thick Av.thick Wt of SSR Rate as Actual CED OH&CP Toal per
OD in thick in pipe ID Resin VAT 5% Sub Total
in mm in mm in mm pipe Rate on pipe rate 12.36% 14% RM
Mts mm rate
12/2012
M P1 A1 A2 P2
110 mm 0.110 - - #VALUE! #VALUE! #VALUE! - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
125 mm 0.125 - - #VALUE! #VALUE! #VALUE! - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
160 mm 0.160 - - 3.20 0.1536 2.29 265.00 64172 77053 292.97 36.21 16.46 345.64 48.39 394.03
200 mm 0.200 - - 3.90 0.1922 3.48 402.00 64172 77053 444.63 54.96 24.98 524.57 73.44 598.01
250 mm 0.250 - - 4.90 0.2402 5.47 625.00 64172 77053 691.95 85.52 38.87 816.35 114.29 930.63
315 mm 0.315 - - 6.20 0.3026 8.72 984.00 64172 77053 1090.72 134.81 61.28 1286.82 180.15 1466.97
400mm 0.400 - - 7.90 0.3842 14.11 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
500mm 0.500 - - 9.80 0.4804 21.88 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
630mm 0.630 - - 12.30 0.6054 34.61 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
S.S.RATES FOR NON- PRESSURE P.V.C_U PIPES (SEWERS) (S- 20) -SDR:41 _Conforming to IS: 15328_Solvent Cement Joints
Manufacture, supply, & delivery of Unplasticized Non-Pressure Polyvinyl Chloride(PVC-U) pipes of dark (any shade of Brown) for use in underground drainage &
sewerage system conforming to IS 15328/2003) with Ring Tite jointing as per specification inclusive of transportation to the Sub-Divisional stores any where in A.P,
including Central Excise duty & VAT
Table 21 RRType PVC-U S-20 SDR: 41 SN: 4
Resin
pipe Min SSR
pipe OD Max thick Av.thick Wt of SSR Rate as Actual CED OH&CP Toal per
OD in thick in pipe ID Resin VAT 5% Sub Total
in mm in mm in mm pipe Rate on pipe rate 12.36% 14% RM
Mts mm rate
12/2012
M P1 A1 A2 P2
110 mm 0.110 - - #VALUE! #VALUE! #VALUE! - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
125 mm 0.125 - - 3.20 0.1186 1.78 207.00 64172 77053 228.73 28.27 12.85 269.85 37.78 307.63
160 mm 0.160 - - 4.00 0.152 2.84 326.00 64172 77053 360.78 44.59 20.27 425.65 59.59 485.24
200 mm 0.200 - - 4.90 0.1902 4.35 495.00 64172 77053 548.29 67.77 30.80 646.86 90.56 737.42
250 mm 0.250 - - 6.20 0.2376 6.89 773.00 64172 77053 857.26 105.96 48.16 1011.38 141.59 1152.97
315 mm 0.315 - - 7.70 0.2996 10.78 1212.00 64172 77053 1343.90 166.11 75.50 1585.51 221.97 1807.48
400mm 0.400 - - 9.80 0.3804 17.42 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
500mm 0.500 - - 12.30 0.4754 27.33 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
630mm 0.630 - - 15.40 0.5992 43.12 - 64172 77053 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 0.00
S.S.RATES FOR NON- PRESSURE P.V.C_U PIPES (SEWERS) (S- 16.5) -SDR:34 _Conforming to IS: 15328_Solvent Cement Joints
Manufacture, supply, & delivery of Unplasticized Non-Pressure Polyvinyl Chloride(PVC-U) pipes of dark (any shade of Brown) for use in underground drainage &
sewerage system conforming to IS 15328/2003) with Ring Tite jointing as per specification inclusive of transportation to the Sub-Divisional stores any where in A.P,
including Central Excise duty & VAT
110 mm
125 mm
160 mm
200 mm
250 mm
315 mm
400 mm
500 mm
630 mm
OD in
mm
110 mm
125 mm
160 mm
200 mm
250 mm
315 mm
400 mm
500 mm
630 mm
OD in
mm
110 mm
125 mm
160 mm
200 mm
250 mm
315 mm
400 mm
500 mm
630 mm
OD in
mm
110 mm
125 mm
160 mm
200 mm
250 mm
315 mm
400 mm
500 mm
630 mm
OD in
mm
110 mm
125 mm
160 mm
200 mm
250 mm
315 mm
400 mm
500 mm
630 mm
OD in
mm
110 mm
125 mm
160 mm
200 mm
250 mm
315 mm
400 mm
500 mm
630 mm
K7
DI- K7-S/S Pipes of Std. Working Length Table 23
14 900 11.20 16071.00 30948.00 29500.00 227.64 16387.43 5.10 3009.00 1691.18 903.93 21991.55 3078.82 25070.36
15 1000 12.00 19056.00 30948.00 29500.00 270.88 19432.54 5.10 3009.00 2005.44 1071.90 25518.88 3572.64 29091.52
471 of 613
DI - K9 -S/S of Std. Working Length K9
Basic Rate of Market Rate
Actual Rate
Pipe per of Pig Iron SSR Pig Iron Wt. of Pipe Transport
of Pipe per Transport CED VAT
Sl Dia Thic. Rmt as per MT Rate MT Kg/Rm
Rmt Cost OH&CP Total Cost
SSR -July:2011 per Sub Total
No in mm Mm @ 14% per Rm
Km/Rm
P1 R2 R1 M P2 590 Km 10.32% 5.00%
100 6.00 1014.00 30948.00 29500.00 14.19 1033.72 0.20 118.00 106.68 57.02 1315.42 184.16 1499.58
1
150 6.00 1502.00 30948.00 29500.00 20.88 1531.02 0.30 177.00 158.00 84.45 1950.47 273.07 2223.54
2
200 6.30 2006.00 30948.00 29500.00 28.99 2046.30 0.40 236.00 211.18 112.87 2606.35 364.89 2971.24
3
250 6.80 2632.00 30948.00 29500.00 38.95 2686.14 0.50 295.00 277.21 148.17 3406.52 476.91 3883.44
4
300 7.20 3334.00 30948.00 29500.00 49.34 3402.58 0.60 354.00 351.15 187.69 4295.41 601.36 4896.77
5
350 7.70 4156.00 30948.00 29500.00 61.44 4241.40 0.80 472.00 437.71 233.96 5385.07 753.91 6138.98
6
400 8.10 5009.00 30948.00 29500.00 73.73 5111.49 0.90 531.00 527.51 281.95 6451.95 903.27 7355.22
7
450 8.60 5992.00 30948.00 29500.00 87.97 6114.29 1.10 649.00 630.99 337.26 7731.55 1082.42 8813.96
8
500 9.00 6971.00 30948.00 29500.00 102.18 7113.04 1.30 767.00 734.07 392.36 9006.46 1260.90 10267.36
9
600 9.90 9195.00 30948.00 29500.00 134.68 9382.22 1.70 1003.00 968.24 517.52 11870.98 1661.94 13532.92
10
700 10.80 11878.00 30948.00 29500.00 171.23 12116.02 2.50 1475.00 1250.37 668.32 15509.72 2171.36 17681.08
11
750 11.30 13330.00 30948.00 29500.00 191.89 13596.74 3.00 1770.00 1403.18 750.00 17519.92 2452.79 19972.70
11
13 800 11.70 14710.00 30948.00 29500.00 211.83 15004.46 5.10 3009.00 1548.46 827.65 20389.57 2854.54 23244.11
14 900 12.60 17937.00 30948.00 29500.00 256.48 18293.53 5.10 3009.00 1887.89 1009.07 24199.50 3387.93 27587.43
15 1000 13.50 21270.00 30948.00 29500.00 305.19 21694.23 5.10 3009.00 2238.84 1196.65 28138.73 3939.42 32078.16
472 of 613
RUBBER GASKETS- CI/DI Pipes
Manufacture as per bis 12820/89 with S.B.R. quality rubber confirming to BIS: 5382/85,
supply and delivery of rubber gaskets suitable for C.I/ D.I. S/S pipes anywhere in A.P.
including cost of material, loading, incidental handling with companys standard packing,
transportation, unloading & stacking, central excise duty but excluding VAT etc., complete.
S# SSR
OH&CP
CED VAT Total Cost
Dia Basic Rate Sub Total
10.32% 5.00% 14.00% Each
473 of 613
COST OF CI SPECIALS- Table 26
CI Specials
1 MANUFACTURE, SUPPLY AND DELIVERY OF CAST IRON PIPES AND FITTINGS (Spls.) CONFORMING
TO I.S. No. 7181/1986, 5531/1988, 3950/1979 AND C.I.D. JOINTS CONFORMING TO IS No.8794/1988 AT
SITE OF WORK ANYWHERE IN A.P. INCLUDING, LOADING, UNLOADING, TRANSPORTATION TO SITE
OF WORK STACKING AT SITE TRANSIT RISK AND PACKAGE, INCLUDING TAXES AND DUTIES.
Difference 1448.00
Increase for every Rs.1000/MT as per SSR 3.43 %
Coke
As per SSR 28500.00
Market Rate of Coke 29100.00
Difference 600.00
Increase for every Rs.1000/MT 0.67 %
Therefore 0.60 0.67 % 0.402 %
DI - Specials
2 Manufacture, Supply and Delivery of Ductile Iron Fittings conforming to IS:9523/2000 for fittings with
Zinc external zinc coating and inside mortar lining inclusive of all taxes , duties and transportation to
site of work anywhere in AP
474 of 613
Rate per One Kg Rs. 92.72
Add CED @ 10.32% 9.57
102.29
Add VAT @ 5.00% 5.11
Add Transportaion @ 10% 9.27
Sub Total Rs 116.68 Kg
Add OH&CP @ 14.00% 16.34
Total Rs 133.02 Kg
3 DI - Specials /Fittings
Manufacture, Supply and Delivery of Ductile Iron Fittings conforming to IS:9523/2000 for fittings with
Zinc external zinc coating and inside mortar lining inclusive of all taxes , duties and transportation to
site of work anywhere in AP for the following Sizes
Wt. in
Kg Rate/Kg Cost (Rs.)
a) DI Double Socket 90 Deg Bend
300 mm 79.8 133.02 10614.67
250 mm 57.1 133.02 7588.56
200 mm 39.2 133.02 5214.23
150 mm 25.2 133.02 3352.00
100 mm 14.7 133.02 1955.33
475 of 613
300x80 44.8 133.02 5959.12
f) DI Flanged Sockets
300 42.7 133.02 5679.78
250 32.9 133.02 4376.23
200 24.5 133.02 3258.89
150 17.2 133.02 2281.22
100 11.0 133.02 1461.85
476 of 613
4 CID Joints Conforming to IS-8794
Manufacture, Supply , Delivery of CID Joints inclusive of all taxes, transportation to
site of work etc. comple
Rate/Kg
80 mm CID Joint (Cl 5- Cl-15)
Joint Wt excluding NBW,RR 3.00 Kg 97.85 293.56
NBW- 3 # 12 dia x 100 mm 0.40 Kg 102.00 40.80
RR's 2 Nos 18.67 37.33
Sub Total 371.69
OH&CP 14% 371.69 52.04
Total Cost of Each CID Joint 423.73
Each Set
477 of 613
200 mm CID Joint :Cl 20
Joint Wt excluding NBW,RR 9.70 Kg 97.85 949.17
NBW- 4 # 16 dia x 120 mm 1.08 Kg 102.00 110.16
RR's 2 Nos 39.00 78.00
Sub Total 1137.33
OH&CP 14% 1137.33 159.23
Total Cost of Each CID Joint 1296.56
Each Set
478 of 613
OH&CP 14% 1734.63 242.85
Total Cost of Each CID Joint 1977.48
Each Set
479 of 613
Manufacture, Supply and Delivery of Cast Iron Double Flanged Pipes conforming to IS:7181 with
amendments upto date inclusive of all taxes , duties and transportation to site of work anywhere in AP
for the following Sizes
480 of 613
8) 150 mm CI D/F Pipe (2.75 m) Wt.(Kg) Rate/Kg Amount
Wt. of Barrel 2.75 41.60 97.85 11194.34
Wt. of Flanges 2.00 6.70 97.85 1311.23
Total Cost 12505.56
Each
481 of 613
Wt. of Barrel 2.00 106.10 97.85 20764.33
Wt. of Flanges 2.00 14.80 97.85 2896.44
Total Cost 23660.76
Each
482 of 613
Total Cost 4824.13
Each
483 of 613
13) 300 mm CI D/F Pipe (1.00m) Wt.(Kg) Rate/Kg Amount
Wt. of Barrel 1.00 91.40 97.85 8943.73
Wt. of Flanges 2.00 14.80 97.85 2896.44
Total Cost 11840.17
Each
484 of 613
350x250 96 97.85 9393.85
350x300 106 97.85 10372.38
400x250 109 97.85 10665.94
400x300 120 97.85 11742.31
400x350 132 97.85 12916.55
485 of 613
1 Manufacture, Supply and delivery of CI D/F Sluice valves conforming to IS 14846/2000 with
amendments ,if any, heavy duty with CI grade FG 260 as per IS: 210. Two coats of primer suitable
for EPOXY PAINTS finish shall be applied to all metal surface and two coats of Epoxy sahll be
applied. The Valves shall be tested for (Close end test) agaisnst the hydrostatic test
requirement.The rates of inclsuive of all applicable taxes and transportation. The valve shall be
supplied with Handwheel /Cap and having CML of BIS.
Table 27
a CI D/F Sluice Valves with Hand Wheel - PN 1.0
2 Manufacture, Supply and delivery of CI D/F Sluice valves conforming to IS 14846/2000 with
amendments No. 1&2 heavy duty with CI grade FG 260 as per IS: 210. Two coats of primer suitable
for EPOXY PAINTS finish shall be applied to all metal surface and fin
3 Manufacture, Supply and delivery of DI D/F Gate Valves (Soft Seated) Resilient seated soft sealing
gate valves (Sluice valves) with body bonnet of ductile cast iron of grade GGG40/ SG 400/12 or
equivalent grade as per I.S.3896-part2-1985 and subsequent
Table 32
a DI D/F Sluice Valves (Soft Seated) - PN 10 & 16
500 With By- 360067.00 44504.28 58662.84 36006.70 499240.82 69893.71 569134.53
pass & Gear
500 With By- 676818.00 83654.70 38023.64 67681.80 866178.14 121264.94 987443.08
pass & Gear
600 With By- 871547.00 107723.21 48963.51 87154.70 ### 156154.38 1271542.80
pass & Gear
4 Manufacture, supply and delivery of CI D/F Gate (Sluice) Valve (Soft Seated) according to
standards of BS5163 86 type B, also available as per DIN 3352 Part-4/AWWA C509/ISO5752 with
body bonnet of Cast Iron of grade FG 260 as per IS 210-1978 wedge fully
Table 28
CI D/F Sluice Valve (Soft Seated) PN-1.0
Table 27
CI D/F Non Return Valves - PN 1.6
Dia in mm Basic Rate CED VAT Transport Sub Total OH&CP Total
Rs.
12.36% 5.00% 10% 14%
50 mm 2348.00 290.21 131.91 234.80 3004.92 420.69 3425.61
65 mm 2935.00 362.77 164.89 293.50 3756.15 525.86 4282.02
80 mm 3523.00 435.44 197.92 352.30 4508.66 631.21 5139.88
100 mm 4696.00 580.43 263.82 469.60 6009.85 841.38 6851.23
125 mm 5870.00 725.53 329.78 587.00 7512.31 1051.72 8564.03
150 mm 8803.00 1088.05 494.55 880.30 11265.90 1577.23 12843.13
200 mm 17561.00 2170.54 986.58 1756.10 22474.22 3146.39 25620.61
250 mm 25471.00 3148.22 1430.96 2547.10 32597.28 4563.62 37160.90
300 mm 38317.00 4735.98 2152.65 3831.70 49037.33 6865.23 55902.56
350 mm 51771.00 6398.90 2908.49 5177.10 66255.49 9275.77 75531.26
400 mm 67356.00 8325.20 3784.06 6735.60 86200.86 12068.12 98268.98
450 mm 113471.00 14025.02 6374.80 11347.10 145217.92 20330.51 165548.42
500 mm 136873.00 16917.50 7689.53 13687.30 175167.33 24523.43 199690.75
600 mm 218668.00 27027.36 12284.77 21866.80 279846.93 39178.57 319025.50
6 Manufacture, Supply and delivery of CI D/F Kinetic Air Valve Heavy Duty suitable for working
pressure up to 16kg/Cm2 without isolating valve, conforming to IS 14845 excluding transportation,
Central Excise duty and sale tax etc., complete.
Table 27
CI D/F Kinetic Air Valve (Without isolating valve)_ PN 1.0
CED VAT Transport Sub Total OH&CP
Total
Dia in mm Basic Rate
12.36% 4.00% 10% 14% Rs.
8 Manufacture, Supply and delivery of CI D/F Kinetic Air Valve as per IS:14845 Heavy Duty with
isolating valve bevel gear operated as per IS 14846 including transportation, Central Excise duty
and sales tax etc., complete.
a CI D/F Kinetic Air Valve (With isolating valve)_ PN 1.0
CED VAT Transport Sub Total OH&CP Total
Dia in mm Basic Rate
12.36% 4.00% 10% 14% Rs.
10 PHE-CISV-15-
Lowering, keeping in position and fixing C.I. sluice valves (with cap / with hand wheel & Reflex
valves) excluding cost of bolts, nuts, rubber insertion, sluice valve and tail pieces.
Rates up to 750mm dia valves as per PH data sheet and above 750mm dia vide Sl.No.10, Pg.225 of final
SSR (PH items)
MA @ OH&CP @ Total
Dia in mm Unit Basic Rate
25% 14%
100 mm Each Joint 291.62 291.62
150 mm Each Joint 451.35 451.35
200 mm Each Joint 491.31 491.31
250 mm Each Joint 698.29 698.29
300 mm Each Joint 735.83 735.83
350 mm Each Joint 1049.28 1049.28
400 mm Each Joint 1457.19 1457.19
450 mm Each Joint 1700.48 1700.48
500 mm Each Joint 1964.10 1964.10
600 mm Each Joint 2712.81 2712.81
700 mm Each Joint 3439.18 3439.18
750 mm Each Joint 3685.62 3685.62
800 mm Each Joint 4528.00 633.92 5161.92
900 mm Each Joint 5325.00 745.50 6070.50
1000 mm Each Joint 6133.00 858.62 6991.62
12 Labour charges for fixing Air valves including boring the mains and threading the bore fixing
nipple etc., complete.
MA @ OH&CP
Dia in mm Unit Basic Rate Total
25% 14%
50 mm Each 124.00 31.00 21.70 176.70
65 mm Each 132.00 33.00 23.10 188.10
80 mm Each 144.00 36.00 25.20 205.20
100 mm Each 169.00 42.25 29.58 240.83
125 mm Each 264.00 66.00 46.20 376.20
150 mm Each 289.00 72.25 50.58 411.83
13 Labour charges for fixing Kinetic Air Valves with isolating Sluice valves, Double Air valves/ Air
Cushion valve excluding cost of jointing materials such as bolts, nuts and rubber insertions etc.,
complete.
MA @ CP @
Dia in mm Unit Basic Rate Total
25% 14%
40 mm Each 133.00 33.25 23.28 189.53
50 mm Each 141.00 35.25 24.68 200.93
65 mm Each 151.00 37.75 26.43 215.18
80 mm Each 165.00 41.25 28.88 235.13
100 mm Each 193.00 48.25 33.78 275.03
125 mm Each 301.00 75.25 52.68 428.93
Rates up to 750mm dia pipes as per PH data sheet and above 750mm dia vide Sl.No.8.b/254 of final SSR
(PH items)
25% 14%
a 80 mm dia per metre 42.91
b 100mm dia Per Metre 54.28
c 125 mm dia Per Metre 70.49
d 150mm dia Per Metre 88.66
e 200mm dia Per Metre 127.56
f 250mm dia Per Metre 172.71
g 300mm dia Per Metre 222.95
h 350mm dia Per Metre 281.06
i 400mm dia Per Metre 342.68
j 450mm dia Per Metre 412.60
LL&Jointing
Page 497 of 613
LL&Jointing
Page 498 of 613
25% 14%
80 mm dia Each Joint 179.23
a 100mm dia Each Joint 291.62
12mm dia Each Joint 301.32
b 150mm dia Each Joint 451.35
c 200mm dia Each Joint 491.31
d 250mm dia Each Joint 698.29
LL&Jointing
Page 499 of 613
LL&Jointing
Page 500 of 613
Rates up to 600mm dia pipes as per PH data sheet and above 600mm dia vide Sl.No.11.b, Pg.226 of final
SSR (PH items)
As Per PH Add Ma on
Dia of Pipes Unit OH &CP@
Data / SSR LC
25% 14%
a 80 mm Per Metre
b 100 mm Per Metre
c 150 mm Per Metre
d 200 mm Per Metre
e 225 mm Per Metre
f 250 mm Per Metre
g 300 mm Per Metre
h 350 mm Per Metre
i 400 mm Per Metre
j 450 mm Per Metre
k 500 mm Per Metre
l 600 mm Per Metre
m 700 mm Per Metre 241.00 60.25 42.18
n 800 mm Per Metre 289.00 72.25 50.58
o 900 mm Per Metre 347.00 86.75 60.73
p 1000 mm Per Metre 415.00 103.75 72.63
Rates up to 600mm dia pipes as per PH data sheet and above 600mm dia vide Sl.No.11.b, Pg.255 of final
SSR (PH items)
Add CP on
Rate as per Add MAon
Dia of Pipes Unit Basic Rate +
PH Data/SSR LC
LC @
25% 14%
LL&Jointing
Page 501 of 613
7 Lowering, Laying & Jointing RCC P/E Pipes with Cement Joints
Lowering the RCC Plain ended Pipes carefully into the trenches laying them true to alignment and
gradient , jointing Plain ended RCC pipes with Cement Joints including curing , cost of Jointing
materilas i.e., cement mortar (1:1.5), hemp yarn etc. but including testing with water with a water
lead of upto 500m etc. complete
LL&Jointing
Page 502 of 613
Item 15 of SoR
Add MA at OH&CP
OD of Pipe in mm Basic Rate
25% 14%
1 20 mm OD Per Metre 18.00 4.50 3.15
2 25 mm OD Per Metre 21.00 5.25 3.68
3 32 mm OD Per Metre 21.00 5.25 3.68
4 40 mm OD Per Metre 26.00 6.50 4.55
5 50 mm OD Per Metre 26.00 6.50 4.55
6 63 mm OD Per Metre 29.00 7.25 5.08
7 75 mm OD Per Metre 32.00 8.00 5.60
8 90 mm OD Per Metre 36.00 9.00 6.30
9 110 mm OD Per Metre 41.00 10.25 7.18
10 125 mm OD Per Metre 50.00 12.50 8.75
11 140 mm OD Per Metre 53.00 13.25 9.28
12 160 mm OD Per Metre 57.00 14.25 9.98
13 180 mm OD Per Metre 63.00 15.75 11.03
14 200 mm OD Per Metre 68.00 17.00 11.90
15 225 mm OD Per Metre 75.00 18.75 13.13
16 250 mm OD Per Metre 80.00 20.00 14.00
17 280 mm OD Per Metre 88.00 22.00 15.40
18 315 mm OD Per Metre 158.00 39.50 27.65
19 355 mm OD Per Metre 176.00 44.00 30.80
20 400 mm OD Per Metre 196.00 49.00 34.30
21 450 mm OD Per Metre 218.00 54.50 38.15
22 500 mm OD Per Metre 240.00 60.00 42.00
PH Data
Add MA at OH&CP
OD of Pipe in mm Basic Rate
25% 14%
1 63 mm OD Per Metre 9.70 2.43 1.70
2 75 mm OD Per Metre 11.55 2.89 2.02
3 90 mm OD Per Metre 13.86 3.47 2.43
4 110mm OD Per Metre 16.94 4.24 2.97
5 125 mm OD Per Metre 19.26 4.81 3.37
6 140 mm OD Per Metre 21.57 5.39 3.77
7 160 mm OD Per Metre 24.65 6.16 4.31
LL&Jointing
Page 503 of 613
LL&Jointing
Page 504 of 613
Table 14
Add MAA
OH&CP
DIA of Pipe in mm Basic Rate at
25% 14%
1 400 mm dia Per Metre 395.00 98.75 69.13
2 500 mm dia Per Metre 493.00 123.25 86.28
3 600 mm dia Per Metre 606.00 151.50 106.05
4 700 mm dia Per Metre 704.00 176.00 123.20
5 800 mm dia Per Metre 803.00 200.75 140.53
6 900 mm dia Per Metre 944.00 236.00 165.20
7 1000 mm dia Per Metre 1042.00 260.50 182.35
8 1100 mm dia Per Metre 1225.00 306.25 214.38
9 1200 mm dia Per Metre 1373.00 343.25 240.28
10 1300 mm dia Per Metre 1577.00 394.25 275.98
11 1400 mm dia Per Metre 1815.00 453.75 317.63
12 1500 mm dia Per Metre 2086.00 521.50 365.05
13 1600 mm dia Per Metre 2399.00 599.75 419.83
14 1700 mm dia Per Metre 2757.00 689.25 482.48
15 1800 mm dia Per Metre 3172.00 793.00 555.10
16 1900 mm dia Per Metre 3648.00 912.00 638.40
17 2000 mm dia Per Metre 4196.00 1049.00 734.30
18 2100 mm dia Per Metre 4826.00 1206.50 844.55
19 2200 mm dia Per Metre 5549.00 1387.25 971.08
20 2300 mm dia Per Metre 6381.00 1595.25 1116.68
21 2400 mm dia Per Metre 7338.00 1834.50 1284.15
22 2500 mm dia Per Metre 8439.00 2109.75 1476.83
23 2600 mm dia Per Metre 9705.00 2426.25 1698.38
LL&Jointing
Page 505 of 613
of Pipes
es &Specials
ll classes) and specials (fittings) with s/s ends carefully into trenches and
and gradient including all sundries but excluding cost and conveyance of
Ref to specifications. BIS No.3114/1994)
Total
es &Specials
l classes) and specials (fittings) with flanged ends carefully into trench
ent and gradient including all sundries but excluding cost and conveyance of
Reference to specifications. BIS No.3114/1994)
as per PH data sheet and above 750mm dia vide Sl.No.8.b/254 of final SSR
Total per Rm
42.91
54.28
70.49
88.66
127.56
172.71
222.95
281.06
342.68
412.60
LL&Jointing
Page 506 of 613
482.01
645.79
835.35
LL&Jointing
Page 507 of 613
943.39
567.15
736.73
959.03
ipes & fittings with Rubber Gasket, excluding the cost of the gasket but
th water with a water lead upto 500 m and testing to required pressure etc.,
85.
Total
156.36
219.66
269.85
300.40
349.00
391.22
528.93
653.00
710.81
783.75
928.27
1172.81
1475.58
1617.71
1865.05
2505.77
2783.26
d valves with flanged ends including cost of jointing materials such as bolts,
cluding filling with water, with lead up to 500 meters and testing to required
e to specifications. BIS No.3114/1994.)
Total
179.23
291.62
301.32
451.35
491.31
698.29
LL&Jointing
Page 508 of 613
735.83
1049.28
1457.19
LL&Jointing
Page 509 of 613
1700.48
1964.10
2712.81
3439.18
3685.62
5472.00
6435.30
7411.14
ng RCC S/S NP2 Pipes (RR's)
s carefully into the trenches laying them true to alignment and gradient,
nd testing including filling with water with a water lead up to 500 meters
gs as per BIS No. 783/1985
as per PH data sheet and above 600mm dia vide Sl.No.11.b, Pg.226 of final
Total per RM
74.95
92.50
124.66
133.52
96.40
162.99
105.94
208.23
230.96
136.22
291.15
334.84
343.43
411.83
494.48
591.38
s carefully into the trenches laying them true to alignment and gradient,
nd testing including filling with water with a water lead up to 500 meters
gs as per BIS No. 783/1985
as per PH data sheet and above 600mm dia vide Sl.No.11.b, Pg.255 of final
Total per Rm
LL&Jointing
Page 510 of 613
201.77
227.69
254.68
281.62
310.01
376.20
343.43
411.83
494.48
591.38
Total per RM
52.17
65.21
97.81
130.42
163.02
195.62
228.23
260.83
293.44
326.04
391.25
456.46
521.66
586.87
652.08
717.29
782.50
912.91
1043.33
1173.74
LL&Jointing
Page 511 of 613
Total
25.65
29.93
29.93
37.05
37.05
41.33
45.60
51.30
58.43
71.25
75.53
81.23
89.78
96.90
106.88
114.00
125.40
225.15
250.80
279.30
310.65
342.00
Cement)- uPVC
Total
13.83
16.46
19.76
24.15
27.44
30.73
35.12
LL&Jointing
Page 512 of 613
39.51
43.90
49.39
LL&Jointing
Page 513 of 613
54.88
61.46
69.15
Testing- MS Pipes
static filed test pressure, including cost of site welding jointing materials and
including emptying pipe line after completion of filed testing
Total per RM
562.88
702.53
863.55
1003.20
1144.28
1345.20
1484.85
1745.63
1956.53
2247.23
2586.38
2972.55
3418.58
3928.73
4520.10
5198.40
5979.30
6877.05
7907.33
9092.93
10456.65
12025.58
13829.63
LL&Jointing
Page 514 of 613
Index- S
code No
Description Unit Quantity Rate Rs. Amt Rs.
Sub Analysis
Lowering, Laying CI /DI Pipes ( S/S Ends)
Lowering C.I. Pipes, A class and specials with s/s ends
carefully into trench and laying them true to alignment and
Commo gradient including all sundries but excluding cost and
n Data conveyance of pipes from source of supply. (Reference to
specifications. BIS No.3114/94)
Assumtion 10 m
200 mm dia CI pipes 5m long (class A)
Weight = 2 x 257 kgs = 514 kgs = 5.14 quintal
(a) LABOUR:
Plumber 1st class day 0.10 721.00 73.54
Plumber 2nd class day 0.24 567.00 134.95
Man mazdoor day 1.33 490.00 651.70
(b) Cost for 10 metres 860.19
Rate per metre = b/10 Rm 86.02
Rate for 1 kg = b/514 Kg 1.67
1.00 Lowering C.I. / D.I. Pipes (all classes) and specials (fittings)
with s/s ends carefully into trenches and laying them true to
PHE-
alignment and gradient including all sundries but excluding
LCIS-1 cost and conveyance of pipes from source of supply (Ref to
specifications. BIS No.3114/1994)
Note : The Labour charges for cost of Lowering & Laying per 1
kg weight shall be as per sub-analysis made for 200 mm dia CI
Pipes S/s ends. Without CP
Details of cost for 5m
i 80 mm dia CI /DI S/S
Weight of 5m length = (79 +85.5 + 92)/3 = 85.5 kgs
(a) Labour charges for laying kgs 85.50 1.67 143.09
(b) Overheads & Contractors Profit 14% 143.09 20.03
(c) Cost for 5 metres = a+b 163.12
Rate per metre = c/5 32.62
Rm
ii 100 mm dia CI/ DI S/S
Weight of 5m length = (100+109+117)/3 = 108.67 kgs
(a) Labour charges for laying kgs 108.67 1.67 181.86
(b) Overheads & Contractors Profit 14% 181.86 25.46
(c) Cost for 5 metres = a+b 207.32
Rate per metre = c/5 41.46
Rm
iii 125 mm dia CI /DI S/S
Weight of 5m length = (130+141+153)/3 = 141.33 kgs
(a) Labour charges for laying kgs 141.33 1.67 236.52
(b) Overheads & Contractors Profit 14% 236.52 33.11
(c) Cost for 5 metres = a+b 269.63
Rate per metre = c/5 53.93
Rm
iv 150mm dia CI/ DI S/S
Weight of 5m length = (162+178+191)/3 = 177 kgs
(a) Labour charges for laying kgs 177.00 1.67 296.21
(b) Overheads & Contractors Profit 14% 296.21 41.47
(c) Cost for 5 metres = a+b 337.68
Rate per metre = c/5 67.54
Rm
PH data
Page 515 of 613
PH data
Page 516 of 613
PH data
Page 517 of 613
Rm
v 200 mm dia CI/DI D/F
Weight of 1m length = 60.1+(2x9.3)/2.75 = 66.86 kgs
(a) Labour charges for laying kgs 66.86 1.67 111.89
(b) Overheads & Contractors Profit 15.66
Rate per metre 127.56
Rm
vi 250 mm dia CI/DI D/F
Weight of 1m length = 81.8+(2x12)/2.75 = 90.53 kgs
(a) Labour charges for laying kgs 90.53 1.67 151.50
(b) Overheads & Contractors Profit 21.21
Rate per metre 172.71
Rm
vii 300 mm dia CI/DI D/F
Weight of 1m length = 106.1+(2x14.8)/2.75 = 116.86 kgs
(a) Labour charges for laying kgs 116.86 1.67 195.57
(b) Overheads & Contractors Profit 27.38
Rate per metre 222.95
Rm
viii 350 mm dia CI/DI D/F
Weight of 1m length = 133.5+(2x19)/2.75 = 147.32 kgs
(a) Labour charges for laying kgs 147.32 1.67 246.54
(b) Overheads & Contractors Profit 34.52
Rate per metre 281.06
Rm
ix 400 mm dia CI/DI D/F
Weight of 1m length = 162.6+(2x23.4)/2.75 = 179.62 kgs
(a) Labour charges for laying kgs 179.62 1.67 300.60
(b) Overheads & Contractors Profit 42.08
Rate per metre 342.68
Rm
x 450mm dia CI/DI D/F
Weight of 1m length = 197+(2x26.5)/2.75 = 216.27 kgs
(a) Labour charges for laying kgs 216.27 1.67 361.93
(b) Overheads & Contractors Profit 50.67
Rate per metre 412.60
Rm
xi 500 mm dia CI/DI D/F
Weight of 1m length = 229.3+(2x32.1)/2.75 = 252.65 kgs
(a) Labour charges for laying kgs 252.65 1.67 422.81
(b) Overheads & Contractors Profit 59.19
Rate per metre 482.01
Rm
xii 600 mm dia CI/DI D/F
Weight of 1m length = 306.5+(2x44)/2.75 = 338.5 kgs
(a) Labour charges for laying kgs 338.50 1.67 566.49
(b) Overheads & Contractors Profit 79.31
Rate per metre 645.79
Rm
xiii 700mm dia CI/DI D/F
Weight of 1m length = 394.3+(2x59.9)/2.75 = 437.86 kgs
(a) Labour charges for laying kgs 437.86 1.67 732.77
(b) Overheads & Contractors Profit 102.59
Rate per metre 835.35
Rm
xiv 750 mm dia CI/DI D/F
Weight of 1m length = 443.8+(2x59.7)/2.75 = 494.49 kgs
(a) Labour charges for laying kgs 494.49 1.67 827.54
(b) Overheads & Contractors Profit 115.86
Rate per metre 943.39
Rm
2A Sub Analysis : (Basic Data)
PHE- OBSERVED DATA FOR TESTING OF 450 MM DIA PSC MAIN :
LCIF- Pumping main to Hydralic field test pressure including
2A transportation of Water with minimum lead of 500 M
(Length = 500 Mts) taking out put / 500 Mts. Unit = 1 Rmt.
PH data
Page 518 of 613
Labour
Fitters (2 x 3 days)
Fitters I Class day 3.00 721.00 2163.00
Fitters II Class day 3.00 567.00 1701.00
Machinery
Hire chargers for Hydraulic field test pressure testing including days 3.00 1200.00 3600.00
transportation of water @ Rs. 1200/- (1000+200) / day
Materials
Pressure guage Nos 0.05 500.00 25.00
3/4" G.I. Pipe (20 mm) RM 3.00 146.00 438.00
Specials 1.00 500.00 500.00
Dummies No. 0.10 1500.00 150.00
Diesel (2 Lts. / Hr) 30 Hrs.(item No.4 of Pg.241) Lts. 60.00 38.50 2310.00
(T) Total Rate per 500 Mts. 10887.00
(r) Rate per 1 Rmt for 450 mm dia 21.77
(R) Rate per 1 Rmt for 10 mm dia = (10/450) x r 0.48
Per Rm per 10 mm dia
Note : Proportionate Testing Charges may be arrived,
keeping the diametre of pipe based on this analysis, for all
varities of pipes for various Dia Pipes.
PH data
Page 519 of 613
PH data
Page 520 of 613
PH data
Page 521 of 613
PH data
Page 522 of 613
PH data
Page 523 of 613
PH data
Page 524 of 613
Joint
PH data
Page 525 of 613
PH data
Page 526 of 613
ii 100mm dia
(a) Labour
Assistant fitter(plumber 2nd class) day 0.63 567.00 357.21
Man mazdoor day 4.50 490.00 2205.00
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 0.47 800.00 372.80
Kerosene oil litre 0.38 28.00 10.61
(c) Total = a+b 2945.62
(d) Overheads & Contractors Profit 0.14 2945.62 412.39
(e) Cost for 40.26 m (c+d) 3358.01
Rate per each m = e/40.26 83.41
Rm
iii 125mm dia
(a) Labour
Assistant fitter(plumber 2nd class) day 0.76 567.00 430.92
Man mazdoor day 5.00 490.00 2450.00
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 0.56 800.00 447.20
Kerosene oil litre 0.56 28.00 15.74
(c) Total = a+b 3343.86
(d) Overheads & Contractors Profit 0.14 3343.86 468.14
(e) Cost for 40.26 m (c+d) 3812.00
Rate per each m = e/40.26 94.68
Rm
iv 150mm dia
(a) Labour
Assistant fitter(plumber 2nd class) day 0.83 567.00 470.61
Man mazdoor day 5.50 490.00 2695.00
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 0.66 800.00 530.40
Kerosene oil litre 0.57 28.00 15.90
(c) Total = a+b 3711.91
(d) Overheads & Contractors Profit 0.14 3711.91 519.67
(e) Cost for 40.26 m (c+d) 4231.58
Rate per each m = e/40.26 105.11
Rm
v 200mm dia
(a) Labour
Assistant fitter(plumber 2nd class) day 1.10 567.00 623.70
Man mazdoor day 6.50 490.00 3185.00
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 0.84 800.00 672.00
Kerosene oil litre 0.76 28.00 21.20
(c) Total = a+b 4501.90
(d) Overheads & Contractors Profit 0.14 4501.90 630.27
(e) Cost for 40.26 m (c+d) 5132.16
Rate per each m = e/40.26 127.48
Rm
vi 250mm dia
(a) Labour
Assistant fitter(plumber 2nd class) day 1.30 567.00 737.10
Man mazdoor day 7.50 490.00 3675.00
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 1.03 800.00 820.80
Kerosene oil litre 1.14 28.00 31.82
(c) Total = a+b 5264.72
(d) Overheads & Contractors Profit 0.14 5264.72 737.06
(e) Cost for 40.26 m (c+d) 6001.78
Rate per each m = e/40.26 149.08
Rm
PH data
Page 527 of 613
PH data
Page 528 of 613
PH data
Page 529 of 613
PH data
Page 530 of 613
PH data
Page 531 of 613
PH data
Page 532 of 613
PH data
Page 533 of 613
PH data
Page 534 of 613
PH data
Page 535 of 613
c) Testing
Testing of Pipelines with required pressure as per relevant IS Rm 27.50 6.05 166.33
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
PH data
Page 536 of 613
PH data
Page 537 of 613
PH data
Page 538 of 613
PH data
Page 539 of 613
PH data
Page 540 of 613
Unit= 1 rmt
Taking out put 100 rmt
i 80 mm dia RCC NP2
a) Labour
Mason 1st class day 0.78 721.00 562.38
Mason 2nd class day 1.80 567.00 1020.60
Man mazdoor day 5.00 490.00 2450.00
Woman mazdoor(water carrier) day 1.30 490.00 637.00
b) Material
Rubber rings conforming BIS 5382/1985-including taxes Each 50.00 29.05 1452.58
c) Testing
Testing of Pipelines with required pressure as per relevant IS Rm 100.00 3.87 387.09
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
PH data
Page 541 of 613
c) Testing
Testing of Pipelines with required pressure as per relevant IS Rm 100.00 7.26 725.80
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
PH data
Page 542 of 613
PH data
Page 543 of 613
PH data
Page 544 of 613
PH data
Page 545 of 613
PH data
Page 546 of 613
PH data
Page 547 of 613
10702.93
(b) Material
Add for Water charges at 1% on Labour & Testing 107.03
(c) Total (a+b) 10809.96
Rate per RM =c/500 21.62
Rate per 10 mm / 1rm 1.35
PH data
Page 548 of 613
Per Rm per
10mm
A All Classes pipes :
i 63 mm dia pipe
PH data
Page 549 of 613
(a) Labour charges for laying, jointing & testing Rm 28.00 1.35 37.83
(b) Overheads & Contractors Profit 5.30
Rate per metre a+b 43.13
Rate per 1 Rmt Rs 43.13
xiii 315 mm dia pipe
Weight of 1m length = (10.682+15.723+24.732)/3 =17.046 kgs
(a) Labour charges for laying, jointing & testing Rm 31.50 1.35 42.56
(b) Overheads & Contractors Profit 5.96
Rate per metre a+b 48.52
Rate per 1 Rmt Rs 48.52
PH data
Page 550 of 613
Output: 30 Rm
A SWG -Pipes conforming to IS-651
i 100 mm dia SWG
(a) Labour
Mason 1st class day 0.600 721.00 432.60
Mason 2nd class day 1.400 567.00 793.80
Man mazdoor day 3.000 490.00 1470.00
Woman mazdoor (Water carrier) day 1.000 490.00 490.00
b) Material
100 mm dia SWG Pipe Rm 30.000 169.00 5070.00
Cement for 50 joints =0.045 cum MT 0.065 5300.00 344.50
Mortar Sand = 0.045 cum cum 0.045 1000.00 45.00
Spun yarn = 0.09x50=4.50 Kg 4.500 105.00 472.50
(c) Total = a+b 9118.40
(d) Add for water charges @ 1% on Labour & Testing 91.18
Charges
(e) Total = c+d 9209.58
(f) Overheads & Contractors Profit 1289.34
(g) Cost for 30 m (e+f) 10498.93
Rate per metre = g/30 349.96
Rate per 1 RM 349.96
Rm
ii 150 mm dia SWG
(a) Labour
Mason 1st class day 0.900 721.00 648.90
Mason 2nd class day 2.100 567.00 1190.70
Man mazdoor day 4.000 490.00 1960.00
Woman mazdoor (Water carrier) day 1.000 490.00 490.00
b) Material
150 mm dia SW pipe Rm 30.000 293.00 8790.00
Cement for 50 joints =0.045 cum MT 0.097 5300.00 514.10
Sand = 0.045 cum cum 0.068 1000.00 68.00
Spun yarn = 0.09x50=4.50 Kg 9.000 105.00 945.00
(c) Total = a+b 14606.70
(d) Add for water charges @ 1% on Labour & Testing 146.07
Charges
(e) Total = c+d 14752.77
(f) Overheads & Contractors Profit 2065.39
(g) Cost for 30 m (e+f) 16818.15
Rate per metre = g/30 560.61
Rate per 1 RM 560.61
Rm
PH data
Page 551 of 613
PH data
Page 552 of 613
PH data
Page 553 of 613
14 Sub Analysis :
Labour charges for laying in position S&S or flanged C.I.
specials such as tees, bends, collars tapers and caps etc
PH data
Page 554 of 613
PH data
Page 555 of 613
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 837.50 3.10 2597.16
valves - (775+900)/2=837.5
Overheads & Contractors Profit 363.60
Rate per each 2960.77
xii 600 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 1422.50 3.10 4411.30
valves - (1220+1625)/2=1422.5
Overheads & Contractors Profit 617.58
Rate per each 5028.88
PH data
Page 556 of 613
PH data
Page 557 of 613
PH data
Page 558 of 613
PH data
Page 559 of 613
PH data
Page 560 of 613
PH data
Page 561 of 613
PH data
Page 562 of 613
vi 250 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.25 567.00 141.75
Man mazdoor day 0.25 490.00 122.50
(b) Overheads & Contractors Profit 37.00
Rate per each Cut 301.25
vii 300 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.30 567.00 170.10
Man mazdoor day 0.30 490.00 147.00
(b) Overheads & Contractors Profit 44.39
Rate per each Cut 361.49
viii 350 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.35 567.00 198.45
Man mazdoor day 0.35 490.00 171.50
(b) Overheads & Contractors Profit 51.79
Rate per each Cut 421.74
ix 400 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.40 567.00 226.80
Man mazdoor day 0.40 490.00 196.00
(b) Overheads & Contractors Profit 59.19
Rate per each Cut 481.99
x 450 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.45 567.00 255.15
Man mazdoor day 0.45 490.00 220.50
(b) Overheads & Contractors Profit 66.59
Rate per each Cut 542.24
xi 500 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.50 567.00 283.50
Man mazdoor day 0.50 490.00 245.00
(b) Overheads & Contractors Profit 73.99
Rate per each Cut 602.49
xii 600 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.60 567.00 340.20
Man mazdoor day 0.60 490.00 294.00
(b) Overheads & Contractors Profit 88.79
Rate per each Cut 722.99
24 Drilling and tapping C.I./D.I. main and fixing brass screw
down ferrule and Plug (Labour charges only)
PH data
Page 563 of 613
PHE- 25 Shoring and strutting of trenches for water and sewer lines
SHST-
25
(A) Single staging from 0 to 8-0 ( 0 to 2.5 Metre)
Depth not exceeding 1.5 M
Details of cost for an area 30 M long and 1.5 M deep.
Area = 30 x 1.5 = 45 sqm
(a) Labour
Carpenter 2nd class day 0.57 331.80 189.13
Man mazdoor day 1.10 490.00 539.00
b) Material
Polling boards and ballies sqm
Requirement for 45 sqm :
Polling Boards of 250 mm x 35 mm (40 x 1.5 x 0.25 x 0.038) cum 0.57 14000.00 7980.00
Ballies 125 mm dia 1.5 mts long (60 x p x (0.125)2 / 4 x 1.5 cum 1.10 14000.00 15400.00
DeductCredit for materials after use @ 80% of the cost of -0.80 23380.00 -18704.00
materials =0.8 x X
c) Machinery
Nil
Sub Total 5404.13
Overheads & Contractors Profit 756.58
(d) Cost for 45 sqm (a+b+c) 6160.70
Rate per each sqm = d/45 136.90
Sq.m
(B) Double staging from 8 to 14 ( 2.5 to 4.5 Metre)
Depth not exceeding 1.5 M
Details of cost for an area 30 M long and 1.5 M deep.
Area = 30 x 1.5 = 45 Sqm
(a) Labour
Carpenter 2nd class day 0.50 331.80 165.90
Man mazdoor day 1.32 490.00 646.80
b) Material
Polling boards and ballies sqm
Requirement for 45 sqm :
Polling Boards of 250 mm x 35 mm (40 x 1.5 x 0.25 x 0.038 = cum 0.57 14000.00 7980.00
Jungle 0.57 cum)
wood
planks,it Ballies 125 mm dia 1.5 mts long (60 x p x (0.125)2 / 4 x 1.5 = cum 1.10 14000.00 15400.00
em 1.1 cum
47/Pg.1
96 Deduct Credit for materials after use @ 80% of the cost of -0.80 23380.00 -18704.00
materials = 0.8 x X
c) Machinery
Nil
Sub Total 5488.70
Overheads & Contractors Profit 768.42
(d) Cost for 45 sqm (a+b+c) 6257.12
Rate per each sqm = d/45 139.05
Sq.m
(C) Triple staging beyond 14 for every 2 meter beyond
4.5 m
Depth not exceeding 1.5 M.
Note : Add for every 2 Mts (difference of single and double
staging) for staging beyond 4.5 mts.
PH data
Page 564 of 613
(a) Usage of Material 5 times. Thus Cost of Material taken as 0.20 831.60 166.32
20%
(b) Labour
Man mazdoor day 0.50 490.00 245.00
411.32
(c) Sundries for Coir rope, nails, @ 1% 1% 411.32 4.11
(d) Sundries for lighting and watching etc at 1% 1% 411.32 4.11
Sub Total 419.55
e)Overheads & Contractors Profit 14% 419.55 58.74
Cost for 3rmt (a+b+c+d +e) 478.28
Rate per each rmt = (a+b+c+d+e)/3 159.43
Rm
26 Providing RCC spun vent shaft with cowl 140 mm and 200
mm internal and external dia respectively at top, 300 and
450 mm internal and external dia respectively at bottom and
9.10m overall length. Bottom 1.25 m below ground level
fixed in a pit 90cmx90cm x150 cm with cement concrete
1:4:8, 25cm in bed and minimum 20cm all-round with top
15cm in cement concrete 1:2:4. Junction of vent shaft and
concrete grouted with cement mortar 1:1 including making
connection with sewer manhole with 150 mm dia metre
cement concrete pipe of required length complete as per
standard design
PH data
Page 565 of 613
PH data
Page 566 of 613
Rm
PH data
Page 567 of 613
PH data
Page 568 of 613
PH data
Page 569 of 613
PH data
Page 570 of 613
MT
iii AC Pipes and Collars (load per truck = 5.40 T)
Taking Output = 10.8 MT
a)Labour
Man Mazdoor day 6.00 490.00 2940.00
Add sundries at 1% towards Nylon rope, Tyres etc 0.01 29.40
Total 2969.40
Overheads & Contractors Profit 14% 415.72
Cost for 10.8 MT 3385.12
Rate per MT 313.44
MT
iv Stone ware pipes (load per truck = 5.40 T)
Taking Output = 10.8 MT
a)Labour
Man Mazdoor day 6.00 490.00 2940.00
Add sundries at 1% towards Nylon rope, Tyres etc 0.01 29.40
Total 2969.40
Overheads & Contractors Profit 14% 415.72
Cost for 10.8 MT 3385.12
Rate per MT 313.44
MT
35 Loading or unloading materials such as C.I / D.I. Pipes, stone
PHE- ware pipes, R.C.C. pipes, A.C. Pressure pipes and specials from
LUMS- 300 mm to 600 mm dia upto 4 mts in length including
35
stacking.
PH data
Page 571 of 613
PHE-
36 Loading or unloading materials such as CI / DI Pipes, A.C.
LUGS- pressure pipes less than 300 mm dia above 4.00 M in length
36 including stacking
i C.I. / D.I. Pipes (load per truck = 8.46 T)
Taking Output = 1 MT
a)Labour
Man Mazdoor day 0.71 0.00 0.00
Add sundries at 1% towards Nylon rope, Tyres etc 0.01 0.00
Total 0.00
Overheads & Contractors Profit 14% 0.00
Cost for 1 MT 0.00
MT
ii AC Pipes (load per truck = 3.78 T)
Taking Output = 1MT
a)Labour
Man Mazdoor day 0.79 0.00 0.00
Add sundries at 1% towards Nylon rope, Tyres etc 0.01 0.00
Total 0.00
Overheads & Contractors Profit 14% 0.00
Cost for MT 0.00
MT
PHE-
37 Loading or Unloading materials such as C.I / D.I. Pipes, A.C.
LUBS- Pressure pipes from 300 to 600mm dia above 4.00 m including
37 stacking
i AC Pipes (load per truck = 4.3 T)
Taking Output = 1 MT
a)Labour
Man Mazdoor day 0.71 0.00 0.00
Add sundries at 1% towards Nylon rope, Tyres etc 0.01 0.00
Total 0.00
Overheads & Contractors Profit 14% 0.00
Cost for 1 MT 0.00
MT
ii C.I. Pipes (load per truck = 3.85 T)
Taking Output = 1MT
a)Labour
Man Mazdoor day 0.78 0.00 0.00
Add sundries at 1% towards Nylon rope, Tyres etc 0.01 0.00
Total 0.00
Overheads & Contractors Profit 14% 0.00
Cost for MT 0.00
MT
PHE- 38 Labour charges for fixing ventilating shafts in sewerage
LCVS- scheme complete with all accessories
40
Unit Each
a) Labour
Mason 1st class day 0.15 721.00 108.15
Mason 2nd class day 0.35 567.00 198.45
Plumber 2nd Class day 0.60 567.00 340.20
Man Mazdoor day 2.00 0.00 0.00
Total 646.80
Overheads & Contractors Profit 14% 90.55
Rate per Each 737.35
PH data
Page 572 of 613
WATER SUPPLY
1 Cutting open BT road surface (as well as asphalt concrete upto 75 mm thick ) including water bound macadam
and stacking of excavated materials for pipe line trench work & as directed by the departmental officers.
Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and 301.2.1 of MORT&H
In ordinary soils, by Manual means for Pipe line Trenches
up to 3.00 Mts depth below GL (Output: 10.00 Cum)
a)Labour
Mate 0 Nos. 560.00 1 Each 0.00
Mazdoor (Unskilled) 3.64 Nos. 490.00 1 Each 1783.60
1783.60
Add extra for pipe line trenches @ 75% 1783.60 1337.70
Sub Total 3121.30
c&d) Overheads & Contractors Profit @ 14% 436.98
Cost for 10 cum = a+b+c+d 3558.28
Rate per cum = (a+b+c+d)/10 355.83
WS_items
Page 573 of 613
WS_items
Page 574 of 613
WS_items
Page 575 of 613
a)Labour
Mate 0 Nos. 560.00 1 Each 0.00
Mazdoor (Unskilled) 2.08 Nos. 490.00 1 Each 1019.20
b. Hydraulic excavator 1.0 cum bucket capacity 0.17 hours 1808.50 1 hours 307.45
Tipper 5.5 cum capacity, 4 trips per hour 0.45 hours 588.17 1 hours 264.68
c. Selected earth within 1.00 Km lead 240.00 cum 30.00 1 cum 7200.00
Seigniorge for Earth 240.00 Cum 22.00 5280.00
Lead 1 Km 240.00 Cum 31.50 7560.00
Sub Total 21631.32
c&d) Overheads & Contractors Profit 14% 3028.39
Cost for 240 cum = a+b+c+d 24659.71
Rate per cum = (a+b+c+d)/10 102.75
Rate per 1 Cum excluding Dewatering Rs 102.75
Cu.m
WS_items
Page 576 of 613
Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and 301.2.1 of MORT&H
Ordinary Soils : for Sumps, Thrust Blocks and Man Holes etc,.
up to 3.00 Mts depth below GL out put 10.00 Cum
a)Labour
Mate 0 Nos. 560.00 1 Each 0.00
Mazdoor (Unskilled) 3.64 Nos. 490.00 1 Each 1783.60
Sub total 1783.60
c&d) Overheads & Contractors Profit 14% 249.70
Cost for 10 cum = a+b+c+d 2033.30
Rate per cum = (a+b+c+d)/10 203.33
Rate per 1 Cum excluding Dewatering Rs 203.33
Cum
11 Earth Work Excavation using Mechanical means :
Earthwork excavation for structures in all types of soil as per drawing and technical specifications including
setting out, construction of shoring and bracing, removal of stumps and other deleterious material and
disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable
material as per Technical Specification 305 MORD / 304 MORTH. for Sumps,Thrust blocks, Chambers and Man
Holes etc. by mechanical means,
WS_items
Page 577 of 613
12 Filling with Sand in Pipe line trenches, sides of foundations and basement with initial lead in layers not
exceeding 15 cm thick, consolidating each deposited layer by watering and ramming including cost and
conveyance of water to work site and all operational, incidental, labour charges, hire charges of T & P etc.,
complete for finished item of work. (APSS NO. 309 & 310)
15 Dismantelling & clearing away stone masonary in cement Mortar/ Brick masonry and carting the excavated
materialfrom the site within a lead of 100 m including including all labour charges, all leads, lifts and other
incidental & operational charges etc.,complete
WS_items
Page 578 of 613
Total 2753.23
Cum
18 Bailing out water from the pipe line trenches with oil engine driven pump sets, including hire charges, fuel
charges and wages for Driver and Helper etc, complete,
Oil Engine Driven Pumpset Basic Rate 1 Hp-Hr 38.00 1 Hp-Hr 38.00
Item.27(a)/258
Sub Total 38.00
Overheads & Contractors Profit 14.00% 5.32
Add Sundries 43.32
WS_items
Page 579 of 613
19 Providing temporary rider mains and pipes for water supply house service connections with ISI mark GI pipes
and fittings so as not to disturb the existing water supply connections during earth work excavation for
trenches and during laying of new mains in including cost and conveyance of all materials, labour charges and
with all incidental and operational charges etc., complete.
WS_items
Page 580 of 613
20 HYSD Reinforcement
BLD-CSTN-4-1-(34)
Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and technical
specifications for Bars below 36 mm dia including over laps and wastage, where they are not welded.
Unit = Mt
(a) Material
HYSD bars including 5 per cent for overlaps and 1.05 Ton 30000.00 1 Ton 31500.00
wastage
Binding wire- SSR (Irrigation) item No 3/233 6.00 kg 52.00 1 kg 312.00
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Blacksmith / Bar bender 10.00 No 721.00 1 No 7210.00
Mazdoor (Unskilled) 10.00 No 490.00 1 No 4900.00
Sub Total 43922.00
OH&CP @14% (c+d) 14% 6149.08
Rate per Mt = a+b+c+d 1 MT 50071.08
Rate per One MT 50071.08
Rate per One Kg Rs. 50.07
kg
21 BLD-CSTN-3-7-Using Concrete mixture all works up to Plinth Level
Plain Cement concrete nominal mix (1:5:10) prop (Cement : fine aggregate: coarse aggregate ) using 40mm size
Hard Granite Machine Crushed Metal including cost and conveyance of all materials like cement, sand, coarse
aggregate water etc., to site , seigniorage charges on all materials, labour charges , for mixing , laying, concrete ,
ramming in 15 cm layers, finishing top surface to the required level curing etc., complete for finished item of work.for
foundation and under flooring bed.
WS_items
Page 581 of 613
WS_items
Page 582 of 613
WS_items
Page 583 of 613
25 PHE-BHLW-26
Barricading, hoarding, lighting and watching etc., for water supply and sewerage works for trenches of depths
upto 6-0 (2 Meter) below G.L
WS_items
Page 584 of 613
27 PHE-URCI-19
Uprooting of C.I. pipes by melting lead, loosening the joints, separating the pipes, hoisting and keeping within
a lead of 10 metres but excluding earth work excavation and refilling
WS_items
Page 585 of 613
150mm dia CI
(a) Labour
Assistant fitter(plumber 2nd class) 0.830 day 331.80 1 day 275.39
Man mazdoor 5.500 day 490.00 1 day 2695.00
b) Material
For breacking lead coulked joints, melting lead
etc.,
Fuel wood 0.663 Qtl 800.00 1 Qtl 530.40
Kerosene oil 0.568 litre 28.00 1 litre 15.90
(c) Total = a+b 3516.70
(d) Overheads & Contractors Profit 14% 3516.70 492.34
(e) Cost for 40.26 m (c+d) 4009.04
Rate per each m = e/40.26 99.58
Rate per 1 Rmt Rs 99.58
Rm
200mm dia CI
(a) Labour
Assistant fitter(plumber 2nd class) 1.100 day 331.80 1 day 364.98
Man mazdoor 6.500 day 490.00 1 day 3185.00
b) Material
For breacking lead coulked joints, melting lead
etc.,
Fuel wood 0.840 Qtl 800.00 1 Qtl 672.00
Kerosene oil 0.757 litre 28.00 1 litre 21.20
(c) Total = a+b 4243.18
(d) Overheads & Contractors Profit 14% 4243.18 594.04
(e) Cost for 40.26 m (c+d) 4837.22
Rate per each m = e/40.26 120.15
Rate per 1 Rmt Rs 120.15
Rm
250mm dia CI
(a) Labour
Assistant fitter(plumber 2nd class) 1.300 day 331.80 1 day 431.34
Man mazdoor 7.500 day 274.40 1 day 2058.00
b) Material
For breacking lead coulked joints, melting lead
etc.,
Fuel wood 1.026 Qtl 800.00 1 Qtl 820.80
Kerosene oil 1.137 litre 28.00 1 litre 31.82
(c) Total = a+b 3341.96
(d) Overheads & Contractors Profit 14% 3341.96 467.87
(e) Cost for 40.26 m (c+d) 3809.84
Rate per each m = e/40.26 94.63
Rate per 1 Rmt Rs 94.63
Rm
WS_items
Page 586 of 613
300mm dia CI
(a) Labour
Assistant fitter(plumber 2nd class) 1.500 day 331.80 1 day 497.70
Man mazdoor 8.500 day 274.40 1 day 2332.40
b) Material
For breacking lead coulked joints, melting lead
etc.,
Fuel wood 1.120 Qtl 800.00 1 Qtl 896.00
Kerosene oil 1.515 litre 28.00 1 litre 42.42
(c) Total = a+b 3768.52
(d) Overheads & Contractors Profit 14% 3768.52 527.59
(e) Cost for 40.26 m (c+d) 4296.11
Rate per each m = e/40.26 106.71
Rate per 1 Rmt Rs 106.71
Rm
350mm dia. CI
(a) Labour
Assistant fitter(plumber 2nd class) 1.750 day 331.80 1 day 580.65
Man mazdoor 9.500 day 274.40 1 day 2606.80
b) Material
For breacking lead coulked joints, melting lead
etc.,
Fuel wood 1.231 Qtl 800.00 1 Qtl 984.80
Kerosene oil 1.515 litre 28.00 1 litre 42.42
(c) Total = a+b 4214.67
(d) Overheads & Contractors Profit 14% 4214.67 590.05
(e) Cost for 40.26 m (c+d) 4804.72
Rate per each m = e/40.26 119.34
Rate per 1 Rmt Rs 119.34
Rm
400mm dia. CI
(a) Labour
Assistant fitter(plumber 2nd class) 2.000 day 331.80 1 day 663.60
Man mazdoor 10.500 day 274.40 1 day 2881.20
b) Material
For breacking lead coulked joints, melting lead
etc.,
Fuel wood 1.306 Qtl 800.00 1 Qtl 1044.80
Kerosene oil 1.894 litre 28.00 1 litre 53.03
(c) Total = a+b 4642.63
(d) Overheads & Contractors Profit 14% 4642.63 649.97
(e) Cost for 40.26 m (c+d) 5292.60
Rate per each m = e/40.26 131.46
Rate per 1 Rmt Rs 131.46
Rm
450mm dia. CI
(a) Labour
Assistant fitter(plumber 2nd class) 2.250 day 331.80 1 day 746.55
Man mazdoor 11.500 day 274.40 1 day 3155.60
b) Material
For breacking lead coulked joints, melting lead
etc.,
Fuel wood 1.400 Qtl 800.00 1 Qtl 1120.00
Kerosene oil 2.273 litre 28.00 1 litre 63.64
(c) Total = a+b 5085.79
(d) Overheads & Contractors Profit 14% 5085.79 712.01
(e) Cost for 40.26 m (c+d) 5797.81
Rate per each m = e/40.26 144.01
Rate per 1 Rmt Rs 144.01
WS_items
Page 587 of 613
Rm
WS_items
Page 588 of 613
500mm dia. CI
(a) Labour
Assistant fitter(plumber 2nd class) 2.500 day 331.80 1 day 829.50
Man mazdoor 12.500 day 274.40 1 day 3430.00
b) Material
For breacking lead coulked joints, melting lead
etc.,
Fuel wood 1.492 Qtl 800.00 1 Qtl 1193.60
Kerosene oil 2.652 litre 28.00 1 litre 74.26
(c) Total = a+b 5527.36
(d) Overheads & Contractors Profit 14% 5527.36 773.83
(e) Cost for 40.26 m (c+d) 6301.19
Rate per each m = e/40.26 156.51
Rate per 1 Rmt Rs 156.51
Rm
600mm dia CI
(a) Labour
Assistant fitter(plumber 2nd class) 3.000 day 331.80 1 day 995.40
Man mazdoor 14.500 day 274.40 1 day 3978.80
b) Material
For breacking lead coulked joints, melting lead
etc.,
Fuel wood 1.580 Qtl 800.00 1 Qtl 1264.00
Kerosene oil 3.410 litre 28.00 1 litre 95.48
(c) Total = a+b 6333.68
(d) Overheads & Contractors Profit 14% 6333.68 886.72
(e) Cost for 40.26 m (c+d) 7220.40
Rate per each m = e/40.26 179.34
Rate per 1 Rmt Rs 179.34
Rm
28 Shifting of existing water supply mains with the following DI pipes of K7 class as per ISI with spigot and socket ends,
with all necessary fittings as per IS 3114, including cost of DI pipes and specials and rubber rings, lowering, laying,
jointing and testing to required pressure including cost and conveyance of all materials to the site, labour charges etc.,
etc. complete.
WS_items
Page 589 of 613
110mm dia PVC pipe as per data sheet 1 Rmt #VALUE! 1 Rmt #VALUE!
Lowering, Laying & Jointing 1 Rmt 16.94 1 Rmt 16.94
Sub Total #VALUE!
Overheads & Contractors Profit 14% #VALUE!
Rate per 1 Rmt including 14% CP Rs #VALUE!
Rm
b 160mm dia U- PVC 4 kg/SqCm
160mm dia PVC pipe as per data sheet 1 Rmt 87.47 1 Rmt 87.47
Lowering, Laying & Jointing 1 Rmt 24.65 1 Rmt 24.65
Sub Total 112.11
Overheads & Contractors Profit 14% 15.70
Rate per 1 Rmt including 14% CP Rs 127.81
WS_items
Page 590 of 613
Rm
WS_items
Page 591 of 613
WS_items
Page 592 of 613
33 PHE-CCIP-23
Cutting C.I./ DI Pipes without water in mains where ever required (.Dia of pipes in mm.)
Details of cost for one cutting
80 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.060 day 331.80 1 day 19.91
Man mazdoor 0.060 day 274.40 1 day 16.46
(b) Overheads & Contractors Profit 5.09
Rate per each m 41.46
Rate per each cut Rs 41.46
100 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.080 day 331.80 1 day 26.54
Man mazdoor 0.080 day 274.40 1 day 21.95
(b) Overheads & Contractors Profit 6.79
Rate per each m 55.29
Rate per each cut Rs 55.29
125 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.110 day 331.80 1 day 36.50
Man mazdoor 0.110 day 274.40 1 day 30.18
(b) Overheads & Contractors Profit 9.34
Rate per each m 76.02
Rate per each cut Rs 76.02
150 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.150 day 331.80 1 day 49.77
Man mazdoor 0.150 day 274.40 1 day 41.16
(b) Overheads & Contractors Profit 12.73
Rate per each m 103.66
Rate per each cut Rs 103.66
200 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.200 day 331.80 1 day 66.36
Man mazdoor 0.200 day 274.40 1 day 54.88
(b) Overheads & Contractors Profit 16.97
Rate per each m 138.21
Rate per each cut Rs 138.21
250 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.250 day 331.80 1 day 82.95
Man mazdoor 0.250 day 274.40 1 day 68.60
(b) Overheads & Contractors Profit
Rate per each m 151.55
Rate per each cut Rs 151.55
300 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.300 day 331.80 1 day 99.54
Man mazdoor 0.300 day 274.40 1 day 82.32
(b) Overheads & Contractors Profit 25.46
Rate per each m 207.32
Rate per each cut Rs 207.32
WS_items
Page 593 of 613
350 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.350 day 331.80 1 day 116.13
Man mazdoor 0.350 day 274.40 1 day 96.04
(b) Overheads & Contractors Profit 29.70
Rate per each m 241.87
Rate per each cut Rs 241.87
400 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.400 day 331.80 1 day 132.72
Man mazdoor 0.400 day 274.40 1 day 109.76
(b) Overheads & Contractors Profit 33.95
Rate per each m 276.43
Rate per each cut Rs 276.43
450 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.450 day 331.80 1 day 149.31
Man mazdoor 0.450 day 274.40 1 day 123.48
(b) Overheads & Contractors Profit 38.19
Rate per each m 310.98
Rate per each cut Rs 310.98
500 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.500 day 331.80 1 day 165.90
Man mazdoor 0.500 day 274.40 1 day 137.20
(b) Overheads & Contractors Profit 42.43
Rate per each m 345.53
Rate per each cut Rs 345.53
600 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class 0.600 day 331.80 1 day 199.08
Man mazdoor 0.600 day 274.40 1 day 164.64
(b) Overheads & Contractors Profit 50.92
Rate per each m 414.64
Rate per each cut Rs 414.64
WS_items
Page 594 of 613
34 Manufacturing ,Supplying and errection of air valve gaurd cabins of size 0.90 x0.90 x 0.90 m made with 4 nos
vertical and 8 nos horizontal MS flats of size 50x8 mm and 12mm dia MS round bars fixed at 10 cm c/c with
door and locking arrangements as per approved drawing and as directed by the departmental officers and
painting both sides with anti corrossive paint two coats over one coat of primery coat including cost of all
materials , fabrication ,welding , transportation to site, all taxes and duties,fixing in position duly embodying in
CC(1:4:8) prop , and all other incidental and operational charges etc complete for finished item of work.
WS_items
Page 595 of 613
Sewers & MH
1 Cutting open BT road surface (as well as asphalt concrete upto 75 mm thick ) including water bound macadam
and stacking of excavated materials for pipe line trench work & as directed by the departmental officers.
Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and 301.2.1 of MORT&H
In ordinary soils, by Manual means for Sewer line Trenches
up to 3.00 Mts depth below GL (Output: 10.00
Cum)
a)Labour
Mate 0 Nos. 567.00 1 Each 0.00
Mazdoor (Unskilled) 3.64 Nos. 490.00 1 Each 1783.60
1783.60
Add extra for Restricted Places @ 75% 1783.60 1337.70
Sub Total 3121.30
c&d) Overheads & Contractors Profit @ 14% 436.98
Cost for 10 cum = a+b+c+d 3558.28
Rate per cum = (a+b+c+d)/10 355.83
Rate per 1 Cum excluding Dewatering Rs 355.83
Cu.m
Sewer
Page 596 of 613
Sewer
Page 597 of 613
Tipper 5.5 cum capacity, 4 trips per hour 0.45 hours 686.84 1 hours 309.08
c. Selected earth within 1.00 Km lead 240.00 cum 30.00 1 cum 7200.00
Seigniorge for Earth 240.00 Cum 22.00 5280.00
Lead 1 Km 240.00 Cum 31.50 7560.00
Sub Total 21675.72
c&d) Overheads & Contractors Profit 14% 3034.60
Cost for 240 cum = a+b+c+d 24710.32
Rate per cum = (a+b+c+d)/10 102.96
Rate per 1 Cum excluding Dewatering Rs 102.96
Cu.m
9 Excavation - In hard rock require blasting:
Excavation in rocky soils by Machine require blasting : Earthwork excavation in hard rock such as sheet rock
and boulders required blasting for pipe line trenches including, cost of blasting materials, duly taking all
precautionary measures including all incidental and operational charges etc., complete.
Sewer
Page 598 of 613
Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and 301.2.1 of MORT&H
Ordinary Soils : for Sumps, Thrust Blocks and Man Holes etc,.
up to 3.00 Mts depth below GL out put 10.00 Cum
a)Labour
Mate 0 Nos. 567.00 1 Each 0.00
Mazdoor (Unskilled) 3.64 Nos. 490.00 1 Each 1783.60
Sub total 1783.60
c&d) Overheads & Contractors Profit 14% 249.70
Cost for 10 cum = a+b+c+d 2033.30
Rate per cum = (a+b+c+d)/10 203.33
Rate per 1 Cum excluding Dewatering Rs 203.33
Cum
12 Earth Work Excavation using Mechanical means :
Earthwork excavation for structures in all types of soil as per drawing and technical specifications including
setting out, construction of shoring and bracing, removal of stumps and other deleterious material and
disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable
material as per Technical Specification 305 MORD / 304 MORTH. for Sumps,Thrust blocks, Chambers and Man
Holes etc. by mechanical means,
13 Filling with Sand in Pipe line trenches, sides of foundations and basement with initial lead in layers not
exceeding 15 cm thick, consolidating each deposited layer by watering and ramming including cost and
conveyance of water to work site and all operational, incidental, labour charges, hire charges of T & P etc.,
complete for finished item of work. (APSS NO. 309 & 310)
Sewer
Page 599 of 613
14 Filling with useful & available excavated earth (excluding rock) in Pipe line trenches, sides of foundations and
basement with initial lead in layers not exceeding 15 cm thick, consolidating each deposited layer by watering
and ramming including cost and conveyance of water to work site and all operational, incidental, labour
charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)
16 Dismantelling & clearing away stone masonary in cement Mortar/ Brick masonry and carting the excavated
materialfrom the site within a lead of 100 m including including all labour charges, all leads, lifts and other
incidental & operational charges etc.,complete
Sewer
Page 600 of 613
Cum
Sewer
Page 601 of 613
18 Dismantling & clearing away Reinforced concrete material from site within a lead of 100m including all labour
charges, all leads, lifts and other incidental & operational charges etc.,complete
19 Bailing out water from the pipe line trenches with oil engine driven pump sets, including hire charges, fuel
charges and wages for Driver and Helper etc, complete,
Oil Engine Driven Pumpset Basic Rate Item.27(a)/258 1 Hp-Hr 105.00 1 Hp-Hr 105.00
Sub Total 105.00
Overheads & Contractors Profit 14.00% 14.70
20 Supply and delivery of Stoneware Glazed Pipes of ISI make conforming to ISI 651 including cost and
conveyance of pipes i.e laoding at factory, transporation, unloading at site and stacking etc, complete
Sewer
Page 602 of 613
21 Lowering and laying in ready made trench true to alignment and gradient, jointing, and testing of stone ware
pipes including cost of jointing material such as cement mortar (1:1) proportion and hemp yarn including
cost and conveyance of pipe.
Output: 30 Rm
SWG -Pipes conforming to IS-651
a 100 mm dia SWG
(a) Labour
Mason 1st class day 0.600 721.00 1 day 432.60
Mason 2nd class day 1.400 567.00 1 day 793.80
Man mazdoor day 3.000 490.00 1 day 1470.00
Woman mazdoor (Water carrier) day 1.000 490.00 1 day 490.00
b) Material
100 mm dia SWG Pipe Rm 30.000 169.00 1 Rm 5070.00
Cement for 50 joints =0.045 cum MT 0.065 5300.00 1 MT 344.50
Sand = 0.045 cum cum 0.045 1000.00 1 cum 45.00
Spun yarn = 0.09x50=4.50 Kg 4.500 105.00 1 Kg 472.50
(c) Total = a+b 9118.40
(d) Add for water charges @ 1% on Labour & Testing 1% 91.18
Charges
(e) Total = c+d 9209.58
(f) Overheads & Contractors Profit 14% 1289.34
(g) Cost for 30 m (e+f) 10498.93
Rate per metre = g/30 349.96
Rate per 1 RM 349.96
Rm
b 150 mm dia SWG
(a) Labour
Mason 1st class day 0.900 721.00 1 day 648.90
Mason 2nd class day 2.100 567.00 1 day 1190.70
Man mazdoor day 4.000 490.00 1 day 1960.00
Woman mazdoor (Water carrier) day 1.000 490.00 1 day 490.00
b) Material
150 mm dia SW pipe Rm 30.000 293.00 1 Rm 8790.00
Cement for 50 joints =0.045 cum MT 0.097 5300.00 1 MT 514.10
Sand = 0.045 cum cum 0.068 1000.00 1 cum 68.00
Spun yarn = 0.09x50=4.50 Kg 9.000 105.00 1 Kg 945.00
(c) Total = a+b 14606.70
(d) Add for water charges @ 1% on Labour & Testing 1% 146.07
Charges
(e) Total = c+d 14752.77
(f) Overheads & Contractors Profit 14% 2065.39
(g) Cost for 30 m (e+f) 16818.15
Rate per metre = g/30 560.61
Rate per 1 RM 560.61
Rm
c 200 mm dia SWG
(a) Labour
Mason 1st class day 1.050 356.25 1 day 374.06
Mason 2nd class day 2.450 325.00 1 day 796.25
Man mazdoor day 4.500 268.75 1 day 1209.38
Woman mazdoor (Water carrier) day 1.250 268.75 1 day 335.94
b) Material
200 mm dia SW pipe Rm 30.000 412.00 1 Rm 12360.00
Sewer
Page 603 of 613
Sewer
Page 604 of 613
22 Manufacture as per BIS:12592 (Part 1&2) Supply & Delivery of man hole covers and frames anywhere in A.P.,
F.O.R. destination including, loading, un-loading & stacking at site ,central excise duty,but excluding sales
tax, octroi and other Govt levies etc., as applicable.ISI mark
b H.D. -20 with 500mm dia clear opening 1 No 1839.00 1 each 1839.00
Sewer
Page 605 of 613
Sewer
Page 606 of 613
c H.D. -20 with 560mm dia clear opening 1 No 1972.00 1 each 1972.00
Add CED @ 10.32% 203.51
VAT @ 5.00% 108.78
Sub Total 2284.29
OH & CP @ 14.00% 319.80
Rate per each 2604.09
Each
d H.D. -35 with 560mm dia clear opening 1 No 2113.00 1 each 2113.00
Add CED @ 10.32% 218.06
VAT @ 5.00% 116.55
Sub Total 2447.61
OH & CP @ 14.00% 342.67
Rate per each 2790.28
Each
23 Manufacture,supply and delivery of encapsulated plastic steps for man holes including cost of materials
packing ,loading, transportation, unloading and stacking at site of work etc, complete including C.E.D but
excluding VAT
Inspection chamber 3' dia and upto 3' depth using Fal-G Blocks
Rate as per SSR item - BMW-B.01 1 No. 4648.00 Each 4648.00
Over heads and Contractors profit @ 14% 14.00% 650.72
Total 5298.72
Rate per 1 No 5298.72
Each
25 BMW-B.02
Constructing 904.0 mm (30) dia solid block masonry inspection chamber as per IS - 4111: Part-1:1986 with
cement mortar (1:6) prop using fly-ash blocks of 225 mm thick from approved source having a minimum
crushing strength of 10 N/sq.mm including plastering with cement mortar 1:3 prop; thick both inside and
outside fitted with 20 dia RCC manhole covers and frames including excavating pits up to a depth of 1524 mm
(5'-0") in all sorts of soils (excluding rock) and laying cement concrete (1:4:8) 150 mm thick using 40 mm HBG
Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard specification and including cost
and conveyance of all materials like cement, sand, bricks, water etc., to site, cost of seigniorage charges on all
materials and all incidental and operational, labour charges like mixing cement mortar, constructing masonry,
lift charges, curing etc., complete for finished item of work as per Standard specification.
Inspection chamber 3' dia and upto 5' depth Using Fal- G Blocks
Rate as per SSR item - BMW-B.02, 1 No. 7225.00 Each 7225.00
Over heads and Contractors profit @ 14% 14.00% 1011.50
Total 8236.50
Rate per 1 No 8236.50
Each
Sewer
Page 607 of 613
26 BMW-B.03
Constructing 904.0 mm (30) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with cement mortar
(1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a minimum crushing strength of
5 N/sq.mm including plastering with cement mortar 1:3 prop; thick both inside and outside fitted with 20 dia RCC
manhole covers and frames including excavating pits up to a depth of 904 mm (3'-0") in all sorts of soils (excluding
rock) and laying cement concrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and
channel 100 mm thick as per Standard specification and including cost and conveyance of all materials like cement,
sand, bricks, water etc., to site, cost of seigniorage charges on all materials and all incidental and operational, labour
charges like mixing cement mortar, constructing masonry, lift charges, curing etc., complete for finished item of work as
per Standard specification.
Inspection chamber 3' dia and upto 3' depth using Clay Bricks
Rate as per SSR item - BMW-B.03, Pg.87 1 No. 4096.00 Each 4096.00
Over heads and Contractors profit @ 14% 14.00% 14% 573.44
Total 4669.44
Rate per 1 No 4669.45
Each
27 BMW-B.04
Constructing 904.0 mm (30) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with cement mortar
(1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a minimum crushing strength of
5 N/sq.mm including plastering with cement mortar 1:3 prop; thick both inside and outside fitted with 20 dia RCC
manhole covers and frames including excavating pits up to a depth of 1524 mm (5'-0") in all sorts of soils (excluding
rock) and laying cement concrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and
channel 100 mm thick as per Standard specification and including cost and conveyance of all materials like cement,
sand, bricks, water etc., to site, cost of seigniorage charges on all materials and all incidental and operational, labour
charges like mixing cement mortar, constructing masonry, lift charges, curing etc., complete for finished item of work as
per Standard specification.
Inspection chamber 3' dia and upto 5' depth using Clay Bricks
Rate as per SSR item - BMW-B.04 1 No. 6160.00 Each 6160.00
Over heads and Contractors profit @ 14% 14.00% 14% 862.40
Total 7022.40
Rate per 1 No 7022.40
Each
28 RBR-FNDN-2
Collection ,Supply and filling of Gravel from approved quarry to work site and stacking at work site to Dept. gauge for
premeasurements including cost and convenyance of all material and all labour charges etc. complete as per
standard specifications. Clause 305.3.9 MORD & 304 MORTH
a)Labour
Mate 0.00 Nos 331.80 1 Nos 0.00
Mazdoor (Unskilled) 0.31 Nos 274.40 1 Nos 85.06
b) Material
Gravel 6.00 Cum 162.55 1 Cum 975.30
Sub total a+b 1060.36
c&d) Overheads & Contractors Profit 148.45
Rate per cum = a+b+c+d 1208.81
Rate per 1 Cum 1208.85
Rate per 6 Cum 1208.85
Rate per 1 Cum 201.50
Sewer
Page 608 of 613
0.00
1 RBR-FNDN-1
Earthwork in excavation in all types of soils for per specification drawings and as directed by the departmental
officer and protecting the walls and other structures etc.,so as not to disturb the existing utility services i.e
water spply and sewer pipe lines ,telephone,and power supply cables/ducts,strom water drains, traffic signals
etc., during the execution, taking all precautionary measures in the restricted areas including divertion of
traffic and back filling in trenches with excavated suitable material including all incidental and operational
charges etc., complete. for Sumps,Thrust blocks, Chambers and Man Holes etc. etc,
Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and 301.2.1 of
MORT&H
Ordinary Soils : for Sumps, Thrust Blocks and Man Holes etc,.
A By Manual means
up to 3.00 Mts depth below GL out put 10.00 Cum
a)Labour
Mate 0 Nos. 567.00 1 Each
Mazdoor (Unskilled) 3.64 Nos. 490.00 1 Each
Add extra for restricted places 75.00%
Sub total
c&d) Overheads & Contractors Profit 14%
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/10
Rate per 1 Cum excluding Dewatering Rs
B By Mechanical means
up to 3.00 Mts depth below GL out put 240.00 Cum
a)Labour
Mate 0 Nos. 567.00 1 Each
Mazdoor (Unskilled) 8.32 Nos. 490.00 1 Each
b) Machinery
Hydraulic Excavator 1 cum bucket capacity 6 hours 1808.50 1 hours
Sub total
c&d) Overheads & Contractors Profit 14%
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
Rate per 1 Cum excluding Dewatering Rs
data-MH
Page 609 of 613
Unit : 1cum
A. MATERIALS:
Cement 129.60 Kg 5.53 1 Kg
Coarse aggregate 40mm graded 0.90 Cum 1558.10 1 Cum
Fine aggregate (Sand) 0.45 Cum 800.00 1 Cum
Water (including for curing) 1.20 Kl 100.00 1 Kl
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.3 cum) capacity 1 hour 303.10 1 hour
C. LABOUR:
Mason 1st class 0.10 Nos 437.50 1 Nos
Mazdoor (unskilled) 1.39 Nos 350.00 1 Nos
Sub Total
Overheads & Contractors Profit 14.00%
Grand Total
Rate per cu.m. Rs
Unit : 1cum
A. MATERIALS:
Cement 324.00 Kg 5.53 1 Kg
Coarse aggregate 20mm graded 0.90 Cum 1576.10 1 Cum
Fine aggregate (Sand) 0.45 Cum 800.00 1 Cum
Water (including for curing) 1.20 Kl 100.00 1 Kl
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity 1 hour 303.10 1 hour
C. LABOUR:
Mason 1st class 0.10 Nos 437.50 1 Nos
Mazdoor (unskilled) 1.39 Nos 350.00 1 Nos
Sub Total
Overheads & Contractors Profit 14.00%
Grand Total
Rate per cu.m. Rs
data-MH
Page 610 of 613
5 BLD-CSTN-6-4
Plastering with 12mm thick in single coat in CM (1:3) finished smooth including cost and conveyance
of all materials to site, seigniorage charges on all materials, finishing, curing, scaffolding and all
operational, incidental, labour charges etc., including cutting grooves where ever necessary etc.,
complete for finished item of work. (As per SS 903). per 10 Sqm.
6 BLD-CSTN-6-4
Plastering with 12mm thick in single coat in CM (1:1) finished smooth including cost and conveyance
of all materials to site, seigniorage charges on all materials, finishing, curing, scaffolding and all
operational, incidental, labour charges etc., including cutting grooves where ever necessary etc.,
complete for finished item of work. (As per SS 903).
data-MH
Page 611 of 613
and 301.2.1 of
0.00
1783.60
1337.70
3121.30
436.98
3558.28
355.83
355.83
Cum
0.00
4076.80
10851.00
14927.80
2089.89
17017.69
70.91
70.91
Cum
data-MH
Page 612 of 613
717.00
1402.29
360.00
120.00
303.10
43.75
486.50
3432.64
480.57
3913.21
3913.21
Cum
1792.50
1418.49
360.00
120.00
303.10
43.75
486.50
4524.34
633.41
5157.75
5157.75
Cum
data-MH
Page 613 of 613
ng minimum Crushing
Materials like Cement,
, including all labour
rges etc., complete for
2902.35
265.56
80.00
262.50
340.20
962.50
4813.11
48.13
4861.24
680.57
5541.82
5541.82
Cum
570.53
262.50
336.00
1169.03
163.66
1332.70
1332.70
133.27
Sq.m
1367.20
262.50
336.00
1965.70
275.20
2240.90
224.09
data-MH