DraftRev12 SKV12

ID Task Name Duration Start Finish 2017 2018


Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 SKV12MainProjectDesignPhases 192days Wed180117 Fri280717
2 SSRApprovalUnitMix,No.ofFloors,FltoFlheightsTypicalFloors 16days Wed180117 Thu020217 SSR Approval
3 SSRApprovalStackingPlan 1day Tue070217 Tue070217 SSR Approval
4 CVP75%SchematicDesign 24days Fri030217 Sun260217 75% Schematic
5 W&A,Infra,ShmaFinalSchematicBIMissuetoCVP 0days Mon060317 Mon060317 06-03
6 CVP100%SchematicDesign 57days Fri030217 Fri310317 100% Schematic
7 HandoverBIMSchematicDesign 0days Fri310317 Fri310317 31-03
8 SSRReviewandApproval 10days Sat010417 Mon100417 SSR Approval
9 CVPDesignDevelopment50% 40days Tue110417 Sat200517 50% DD
10 SSRReviewandApproval 10days Sun210517 Tue300517 SSR Approval
11 CVPPilingBIMPreparation 10days Sun210517 Tue300517 Piling BIM Preparation
12 CVPHandoverofPilingBIM 1day Wed310517 Wed310517 Piling BIM Handover
13 CVPDesignDevelopment80% 35days Wed310517 Tue040717 80% DD
14 SSRReviewandApproval 10days Wed050717 Fri140717 SSR Approval
15 W&A,Infra,ShmaFinalDDBIMissuetoCVP 0days Fri140717 Fri140717 14-07
16 CVPFinalBIMPreparation 14days Sat150717 Fri280717 Final BIM Preparation
17 CVPHandoverofBIM100%DD 0days Fri280717 Fri280717 28-07
18
19 Piling 226days Thu010617 Fri120118
20 InfraPilingTenderPackage 35days Thu010617 Wed050717 Piling Tender Docs
21 InfraPilingConstructionDrawings 30days Thu060717 Fri040817 Piling For Con Docs
22 SSRQSPilingTenderDocumentation 30days Thu060717 Fri040817 Piling BOQ
23 PilingTenderandNegotiation 45days Sat050817 Mon180917 Piling Tender
24 AwardofPilingContract 1day Tue190917 Tue190917 Award Piling Contractor
25 PilingContractorMobilization 30days Thu141217 Fri120118 Mobilization
26 StartofPilingWorks 0days Fri120118 Fri120118 12-01
27
28 Architecture&StructureCore&Shell 136days Sat290717 Mon111217
29 QTX&InfraTenderDrawings&Spec' 60days Sat290717 Tue260917 Core & Shell Tender Docs
30 QTX&InfraConstructionDrawings 60days Wed270917 Sat251117 Core & Shell For Con Docs
31 SSRQSCore&ShellTenderDocumentation 30days Wed270917 Thu261017 Core & Shell BOQ
32 Core&ShellTenderandNegotiation 45days Fri271017 Sun101217 Core & Shell Tender
33 AwardofMainContractor 1day Mon111217 Mon111217 Award Main Contractor
34
35 MEPBaseBuilding 136days Sat290717 Mon111217
36 WABaseBuildingMEPTenderDrawings 60days Sat290717 Tue260917 MEP Tender Docs
37 WABaseBuildingMEPConstructionDrawings 60days Wed270917 Sat251117 MEP For Con Docs
38 SSRQSBaseBuildingMEPTenderDoc's 30days Wed270917 Thu261017 MEP BOQ
39 BaseBuildingMEPTender&Negotiation 45days Fri271017 Sun101217 MEP Tender
40 AwardofMEPContract 1day Mon111217 Mon111217 Award MEP Contractor
41
42 DesignDevelopmentID,Lighting,MEP 277days Mon270217 Thu301117
43 CVPPublicSpacesPresentation 1day Thu160317 Thu160317
44 InverseLightingConcept&Schematic 60days Fri170317 Mon150517 Lighting Concept & Schematic
45 InverseLightingDesignDevelopment 59days Tue160517 Thu130717 Lighting DD
46 InverseLightingTenderDrawings&Spec' 60days Fri140717 Mon110917 Lighting Tender Docs
47 WAMEPDesignDevelopment 109days Mon270317 Thu130717 MEP DD
48 WAMEPTenderDrawings 50days Fri140717 Fri010917 MEP Tender Docs
49 WAMEPConstructionDrawings 60days Mon021017 Thu301117 MEP For Con Docs
50 SSRQSMEPTenderDoc's 30days Mon021017 Tue311017 MEP BOQ
51 Interior(PublicAreas&Units)DD 70days Mon270317 Sun040617 Public Area & Unit Interior DD
52 SSRReviewandApproval 10days Mon050617 Wed140617 SSR Approval
53 InteriorTenderDrawings(PublicAreas&Units) 60days Thu150617 Sun130817 Public Area & Unit Interior Tender Docs
54 InteriorConstructionDrawings(PublicAreas&Units) 42days Mon140817 Sun240917 ID For Con
55 SSRQSInteriorTenderDoc's&BOQ 30days Mon140817 Tue120917 Public Area & Unit Interior BOQ
56 LandscapeConceptandSchematicDesign 63days Mon270217 Sun300417 Landscape Concept & Schematic
57 LandscapeDesignDevelopment 67days Mon010517 Thu060717 Landscape DD
58 LandscapeTenderDrawingsandDoc's 45days Fri070717 Sun200817 Landscape Tender Docs
59 LandscapeConstructionDrawings 45days Mon210817 Wed041017 Landscape For Con
60 SSRQSLandscapeTenderDoc's 30days Mon210817 Tue190917 Landscape BOQ
61
62 ProjectInformationforSalesTools 62days Thu150617 Wed160817
63 Plans 30days Thu150617 Fri140717 Plans
64 Perspectives 30days Thu150617 Fri140717 Perspectives
65 Model 61days Thu150617 Mon140817 Model
66 MarketingMaterial 62days Thu150617 Tue150817 Marketing Material
67 ProjectLaunch(PreSale) 0days Wed160817 Wed160817 16-08
68
69 SalesOffice 193days Sun210517 Wed291117
70 SalesOfficeDesign 70days Sun210517 Sat290717 Design
71 SSRReviewandApproval 10days Sun300717 Tue080817
72 SalesOfficeConstruction 90days Wed090817 Mon061117 Construction
73 FurnitureOrdering 15days Wed090817 Wed230817 Order
74 FurnitureProduction 45days Thu240817 Sat071017 Production
75 FurnitureShipping 45days Sun081017 Tue211117 Shipping
76 FurnitureandPropsSetUp 7days Wed221117 Tue281117 Set Up
77 OpentoProspectiveClients 1day Wed291117 Wed291117 Open
78
79 EIASubmission&AuthorityApproval 275days Mon270217 Tue281117
80 EIADrawingsandDocumentationQTX 45days Mon270217 Wed120417 EIA Docs - QTX
81 EIADrawingsandDocumentationW&A 30days Tue140317 Wed120417 EIA Docs - W&A
82 PrepareEIAReport 45days Wed050417 Fri190517 EIA Report
83 EIAReportSubmission 1day Fri190517 Fri190517 EIA Submission
84 EIAReviewandApprovalProcess 180days Fri190517 Tue141117 EIA Process
85 BuildingPermitT39Documentation 30days Mon161017 Tue141117 T39 Docs
86 BuildingPermitT39Approval 14days Wed151117 Tue281117 T39 Submission

Task Project Summary Manual Task Start-only Deadline

Project: 17-02-17 SKV12 - Draf Split Inactive Task Duration-only Finish-only Progress
Date: Fri 17-03-17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone