PPIP TAHUN 2013

ANALISA PEKERJAAN
PEKERJAAN : TALUD 1 (Panjang 9,8m' : Tinggi 2,75 m )

Desa : Gandu
Kecamatan : Tembarak

Satua Koefisie Harga


No Uraian Volume Jumlah Harga
n an Satuan
A Pekerjaan Persiapan/Galian
Galian Pondasi (m3) 12 m3
0,70
Pekerja oh 0.400 40,000 4.80 192,000.00
Sub Total A) 1,00
192,000.00
B Pas. Batu belah 1:4 30.03 m3
0,30
1 Batu belah m3 1.100 140,000 33.03 4,624,620.00
2 Pasir m3 0.485 140,000 14.56 2,039,037.00
3 Semen sak 3.200 63,000 96.10 6,054,048.00
4 Pekerja oh 1.500 40,000 45.05 1,801,800.00
5 Tukang oh 0.700 50,000 21.02 1,051,050.00
0,3
Sub Total B) ###
0
C Plesteran 1PC:4Psr:Tbl 15mm 6.00 m2
1 Pasir m3 0.020 140,000 0.12 16,800.00
2 Semen sak 0.136 63,000 0.82 51,408.00
3 Pekerja oh 0.200 40,000 1.20 48,000.00
4 Tukang oh 0.150 50,000 0.90 45,000.00
Sub Total E) 161,208.00
TOTAL BIAYA ###

Estimasi Kebutuhan:
Harga
No Uraian Kebutuhan Satuan Vol Jumlah
Satuan
1 Batu belah m3 33.03 140,000 4,624,620
2 Pasir m3 14.68 140,000 2,055,837
3 Semen sak 96.91 63,000 6,105,456
4 Pekerja hok 51.05 40,000 2,041,800
5 Tukang hok 21.92 50,000 1,096,050
Jumlah 15,923,763.00
-
0,2
0
PPIP TAHUN 2013

ANALISA PEKERJAAN
PEKERJAAN : TALUD 2 (Panjang 22 m' : Tinggi 1 m )

Desa : Gandu
Kecamatan : Tembarak

Satua Koefisie Harga Jumlah


No Uraian Volume
n an Satuan Harga
A Pekerjaan Persiapan/Galian
Galian Pondasi (m3) 7.7 m3
Pekerja oh 0.400 40,000 3.08 123,200.00
Sub Total A) 123,200.00
B Pas. Batu belah 1:4 11.4 m3
1 Batu belah m3 1.100 ### 12.54 ###
2 Pasir m3 0.485 ### 5.53 774,060.00
3 Semen sak 3.200 63,000 36.48 ###
4 Pekerja oh 1.500 40,000 17.10 684,000.00
5 Tukang oh 0.700 50,000 7.98 399,000.00
Sub Total B) ###
C Plesteran 1PC:4Psr:Tbl ### m2
1 Pasir m3 0.020 ### 0.22 30,800.00
2 Semen sak 0.136 63,000 1.50 94,248.00
3 Pekerja oh 0.200 40,000 2.20 88,000.00
4 Tukang oh 0.150 50,000 1.65 82,500.00
Sub Total E) 295,548.00
TOTAL BIAYA ###

Estimasi Kebutuhan:
Harga
No Uraian Kebutuhan Satuan Vol Jumlah
Satuan
1 Batu belah m3 12.54 ### 1,755,600
2 Pasir m 3
5.75 ### 804,860
3 Semen sak 37.98 63,000 2,392,488
4 Pekerja hok 22.38 40,000 895,200
5 Tukang hok 9.63 50,000 481,500
Jumlah 6,329,648.00
-
PPIP TAHUN 2013

ANALISA PEKERJAAN

PEKERJAAN : JALAN RABAT BETON

Desa : GANDU
Kecamatan : Tembarak

Koefisie Harga
No Uraian Satuan Volume Jumlah Harga
an Satuan
1 2 3 4 5 6 7
A Pekerjaan Persiapan/Galian
Galian Tanah 229.5 m3
1 Pekerja oh 0.400 40,000 91.80 3,672,000.00
2 Tukang oh 0.090 50,000 20.66 1,032,750.00
Sub Total A) 4,704,750.00
B Pekerjaan Bagesting /Pemasangan Cetakan
1 Kayu Papan 2/12/200 ptg - 10,000 200.00 2,000,000.00
2 Usuk 5/6/200 ptg - 10,000 100.00 1,000,000.00
3 Paku kg - 18,000 8.00 144,000.00
4 Pekerja oh - 40,000 26.00 1,040,000.00
5 Tukang oh - 50,000 13.00 650,000.00
Sub Total B) 4,834,000.00
C Urugan Pasir 42.5 m3
1 Pasir m3 1.100 140,000 46.75 6,545,000.00
2 Pekerja oh 0.750 40,000 31.88 1,275,000.00
3 Tukang oh 0.250 50,000 10.63 531,250.00
Sub Total C) 8,351,250.00
D Pekerjaan Cor = Camp: 1
229.5 m3
1 Pasir m3 0.520 140,000 119.34 16,707,600.00
2 Batu Pecah 2/3 m 3
0.820 195,000 188.19 36,697,050.00
3 Semen sak 6.800 63,000 1,560.60 98,317,800.00
4 Pekerja oh 1.650 40,000 378.68 15,147,000.00
5 Tukang oh 0.450 50,000 103.28 5,163,750.00
Sub Total D) ###
E Pekerjaan Tlasah 57.38 m2
1 Batu belah 20/15 468 m3 0.180 - -
2 Pasir Urug 468 m 3
0.050 - -
3 Pekerja 468 oh 0.255 40,000 119.34 4,773,600.00
4 Tukang 468 oh 0.195 50,000 91.26 4,563,000.00
Sub Total E) 9,336,600.00
TOTAL BIAYA ###

Estimasi Kebutuhan:
No Uraian Kebutuhan Satuan Vol Harga Satuan Jumlah
1 Kayu Papan 3/20/200 ptg 200.00 10,000 2,000,000
2 Usuk 5/6/200 ptg 100.00 10,000 1,000,000
3 Paku kg 8.00 18,000 144,000
4 Pasir m3 166.09 140,000 23,252,600
5 Batu Pecah 2/3 m3 188.19 195,000 36,697,050
6 Semen sak 1,560.60 63,000 98,317,800
7 Pekerja oh 647.69 40,000 25,907,600
8 Tukang oh 238.82 50,000 11,940,750

Jumlah 199,259,800.00 -
PNPM - MD 2014

ANALISA PEKERJAAN

PEKERJAAN : DUEKER PLAT TYPE-1

Desa :GANDU
Kecamatan : Tembarak

Satua Koefisie Harga


No Uraian Volume Jumlah Harga
n an Satuan

1 2 3 4 5 6 7
A Pekerjaan Persiapan/Galian
1 Galian Tanah Keras 3 m3
Pekerja oh 0.625 40,000 1.88 75,000.00
Sub Total A) 75,000.00
B Pas. Batu belah 1:4 6.5 m3
1 Batu belah m3 1.100 140,000 7.15 1,001,000.00
2 Pasir m3 0.485 140,000 3.15 441,350.00
3 Semen sak 3.200 63,000 20.80 1,310,400.00
4 Pekerja oh 1.500 40,000 9.75 390,000.00
5 Tukang oh 0.700 50,000 4.55 227,500.00
Sub Total B) ###
C Pas. Batu onderlagh 0.3 m 3

1 Batu belah m3 1.100 140,000 0.33 46,200.00


2 Pekerja oh 0.250 40,000 0.08 3,000.00
3 Tukang oh 0.100 50,000 0.03 1,500.00
Sub Total C) 50,700.00
D Pek. Cor beton lapisan onderlagh = 1PC 0.3 m3
Tebal : 0,05 m
1 Pasir m3 0.480 140,000 0.14 20,160.00
2 Batu Pecah 2/3 m3 0.960 195,000 0.29 56,160.00
3 Semen sak 5.970 63,000 1.79 112,833.00
4 Pekerja oh 6.000 40,000 1.80 72,000.00
5 Tukang oh 1.000 50,000 0.30 15,000.00
Sub Total D) 276,153.00
E Pek. Plat Cor Beton Bertulang
E.1. Cor Beton 1PC:2Psr:4Krl (vol. 5,76 m
0.75
3
) m3
1 Pasir m3 0.480 140,000 0.36 50,400.00
2 Batu Pecah 2/3 m 3
0.960 195,000 0.72 140,400.00
3 Semen sak 5.970 63,000 4.48 282,082.50
4 Pekerja oh 6.000 40,000 4.50 180,000.00
5 Tukang oh 1.000 50,000 0.75 37,500.00
E.2. Tulangan 10 mm
10m x 1.1m : jarak 10cm 5 m2
1 Besi beton 10mm m' 20.00 6,000 100.00 600,000.00
2 Kawat Bendrat kg 17,000 4.00 68,000.00
3 Pekerja oh 40,000 24.00 960,000.00
4 Tukang oh 50,000 12.00 600,000.00
Sub Total E) ###
F Pekerjaan Bagesting : P: 10 x L: 0.50 5 m2
1 Kayu Papan 2/20/200 ptg 10,000 15.00 150,000.00
2 Paku kg 16,000 2.00 32,000.00
3 Usuk 5/6/200 ptg 10,000 10.00 100,000.00
4 Pekerja oh 40,000 4.00 160,000.00
5 Tukang oh 50,000 2.00 100,000.00
Sub Total F) 542,000.00

1 2 3 4 5 6 7
G Pekerjaan Dueker : P:1,10mxT:0,70mx2unit
Pas. Batu Bata / 1PC:4Psr:Tbl 1bata 1
1 Batu Bata m2 140.00 800 140.00 112,000.00
2 Semen sak 1.100 63,000 1.10 69,300.00
3 Pasir m3 0.093 140,000 0.09 13,020.00
4 Pekerja oh 0.850 40,000 0.85 34,000.00
5 Tukang oh 0.350 50,000 0.35 17,500.00
Sub Total G) 245,820.00
H Plesteran 1PC:4Psr:Tbl 15mm 5.00 m2
1. Plesteran Dinding dalam saluran m2
2. Plesteran Dueker m2
1 Pasir m3 0.020 140,000 0.10 14,000.00
2 Semen sak 0.136 63,000 0.68 42,840.00
3 Pekerja oh 0.200 40,000 1.00 40,000.00
4 Tukang oh 0.150 50,000 0.75 37,500.00
Sub Total H) 134,340.00
TOTAL BIAYA ###

Estimasi Kebutuhan:
Harga
No Uraian Kebutuhan Satuan Vol Jumlah
Satuan
1 Batu belah m3 7.48 140,000 1,047,200
2 Pasir m 3
3.85 140,000 538,930
3 Batu Pecah 2/3 1.01 195,000 196,560
4 Semen sak 28.85 63,000 1,817,456
5 Besi beton 10mm / 12m m 100.00 6,000 600,000
6 Bendrat kg 4.00 17,000 68,000
7 Batu bata bh 140.00 800 112,000
8 Papan 2/20/200 ptg 15.00 18,000 270,000
9 Usuk 5/6/200 ptg 10.00 16,000 160,000
10 Bambu ptg 15,000 -
11 Paku kg 2.00 18,000 36,000
12 Pekerja hok 47.85 35,000 1,674,750
13 Tukang hok 20.73 50,000 1,036,500
Jumlah 7,612,645.50 -
RENCANA ANGGARAN BIAYA
Provinsi : Jawa Tengah No.RAB
Kabupaten :Temanggung Program
Kecamatan :Tembarak Jenis Kegiatan
Desa :Gandu Ukuran

VOLUME
URAIAN Sat Harga Satuan (Rp)
Total Dari swadaya Dari Dana PPIP
BAHAN
Batu belah 38.84 38.84 m3 140,000
Pasir 18.17 18.17 m3 140,000
Semen 120.10 120.10 sak 63,000
sub total
ALAT
Cangkul 5.00 5.00 bh 60,000
Centong Semen 10.00 10.00 bh 15,000
benang 1.00 1.00 pak 25,000
ember 20.00 20.00 bh 6,000
Papan Spasi 8.00 8.00 bh 10,000
Gerobak Dorong 2.00 2.00 unit 450,000
sub total
UPAH
Tukang 31.55 31.55 hok 50,000
Pekerja 73.43 73.43 hok 40,000
sub total
TOTAL
Dana BLM PPIP
Sumber Dana
Swadaya Masyarakat

Diperiksa Oleh : Dibuat Oleh :


Fasilitator Masyarakat Ketua OMS

Agus WR, S.Pd

Rizki Oktarinda, ST SURIP

Diverifikasi Oleh :
TAMK

(...................................)
: PPIP Tahun 2013
: Talud
: P :12m L:0,77m : T:2,75m
: P : 22m L: 0,55m : T : 1m

Jumlah Total (Rp)

5,437,740
2,543,849
7,566,174
15,547,763
0
300,000
150,000
25,000
120,000
80,000
900,000
1,575,000
0
1,577,500
2,937,200
4,514,700
21,637,463
21,637,463
0

Dibuat Oleh :
Kader Desa

GAMPANG
RENCANA ANGGARAN BIAYA
Provinsi : Jawa Tengah No.RAB
Kabupaten :Temanggung Program
Kecamatan :Tembarak Jenis Kegiatan
Desa :Gandu Ukuran
VOLUME
URAIAN Sat Harga Satuan (Rp)
Total Dari swadaya Dari Dana PPIP
BAHAN
Kayu Papan 3/20/200 200.00 200.00 lbr 10,000
Usuk 5/6/200 100.00 100.00 lbr 10,000
Paku 8.00 8.00 kg 18,000
Pasir 166.09 166.09 m3 140,000
Batu Pecah 2/3 188.19 188.19 m3 195,000
plastik cor 1,700.00 1,700.00 m2 700
Semen 1,560.60 1,560.60 sak 63,000
sub total
ALAT
ember 50 50 bh 6000
benang 3 3 pak 25000
Cangkul 10.00 10.00 bh 60,000
Centong Semen 5.00 5.00 bh 15,000
Sewa 2 Molen +solar 80.00 80.00 hr 200,000
Gerobak Dorong 3.00 3.00 unit 450,000
sub total
UPAH
Tukang 238.82 20.66 218.16 hok 50,000
Pekerja 647.49 91.8 555.69 hok 40,000
sub total
TOTAL
Dana BLM PPIP
Sumber Dana
Swadaya Masyarakat

Diperiksa Oleh : Dibuat Oleh :


Fasilitator Masyarakat Ketua OMS

Agus WR, S.Pd

Rizki Oktarinda, ST SURIP

Diverifikasi Oleh :
TAMK

(...................................)
: PPIP Tahun 2013
: Rabat Beton
: P : 850m L: 2m : T : 0,135m
Jumlah Total (Rp)

2,000,000 2,000,000
1,000,000 1,000,000
144,000 144,000
23,252,600 66.436 23,252,600 9301040
36,697,050 75.276 36,697,050 14678820
1,190,000 1,190,000
98,317,800 575 98,317,800 36225000
162,601,450
0
300,000
75,000
600,000
75,000
16,000,000
1,350,000
18,400,000 18,400,000
0
11,941,000 87.264
25,899,600 222.276
37,840,600 15136240
218,842,050 98,075,100
214,137,050
4705000

Dibuat Oleh :
Kader Desa

GAMPANG
RENCANA ANGGARAN BIAYA
Provinsi : Jawa Tengah No.RAB
Kabupaten :Temanggung Program
Kecamatan : Tembarak Jenis Kegiatan
Desa : Gandu Ukuran
VOLUME
URAIAN Sat Harga Satuan (Rp)
Total Dari swadaya Dari Dana PPIP
BAHAN
Batu Belah 7.48 2.07 m3 140,000
Pasir 3.85 1.60 m3 140,000
Batu Pecah 2/2 1.10 0.84 kg 195,000
Semen 28.85 14.03 m3 63,000
Besi Beton 10mm/12mm 220.00 220.00 m3 6,000
Bendrat 4.00 4.00 sak 17,000
Batu Bata 280.00 280.00 bh 800
Papan 2/20/200 15.00 15.00 bh 10,000
Usuk 5/6/200 10.00 10.00 bh 10,000
Bambu 3.00 3.00 bh 15,000
Paku 2.00 2.00 kg 18,000
sub total
ALAT
Cangkul 3.00 3.00 bh 60,000
benang 1.00 1.00 pak 25,000
ember 10.00 10.00 bh 6,000
Centong Semen 4.00 4.00 bh 15,000
Gerobak Dorong 1.00 1.00 unit 450,000
sub total
UPAH
Tukang 20.73 20.73 hok 50,000
Pekerja 47.85 47.85 hok 40,000
sub total
TOTAL
Dana BLM PPIP
Sumber Dana
Swadaya Masyarakat

Diperiksa Oleh : Dibuat Oleh :


Fasilitator Masyarakat Ketua OMS

Agus WR, S.Pd

Rizki Oktarinda, ST SURIP

Diverifikasi Oleh :
TAMK

(...................................)
: PPIP Tahun 2013
Decker Plat
: P : 5m L:1m : T : 1,75m
Jumlah Total (Rp)

1,047,200
539,000
214,500
1,817,550
1,320,000
68,000
224,000
150,000
100,000
45,000
36,000
5,561,250
0
180,000
25,000
60,000
60,000
450,000
775,000
0
1,036,500
1,914,000
2,950,500
9,286,750
9,286,750
0

Dibuat Oleh :
Kader Desa

GAMPANG
REKAP RENCANA ANGGARAN BIAYA

Provinsi : Jawa Tengah No. RAB


Kabupaten : Temanggung Program PPIP APBN-P 2013
Kecamatan : Tembarak Jenis Kegiatan Betonisasi Dusun Gandon
Desa : Gandu Ukuran/Dimensi Beton, 850x0,135x2
Decker, 1x5x1
talud, 3,25x34x0,7
No Uraian Pekerjaan Volume Satuan Harga Satuan (Rp) Jumlah Biaya (Rp)
I Pekerjaan Jalan Beton
1 Pekerjaan persiapan/galian 230 m3 20,500 4,704,750
2 Pekerjaan begesting 230 m3 21,063 4,834,000
3 Urugan pasir 43 m3 196,500 8,351,250
4 Pekerjaan cor 230 m3 749,600 172,033,200
5 Pekerjaan Tlasah 57 m3 162,715 9,336,600
sub total 199,259,800
II Pekerjaan Talud
1 Pekerjaan Persiapan/Galian 20 m3 16,000 315,200
2 Pas. Bt. Belah 1:4 41 m3 518,500 21,481,455
3 Plesteran 17 m2 26,868 456,756
sub total 22,253,411
III Pekerjaan Decker Plat
1 Pekerjaan Persiapan/galian 3 m3 25,000 75,000
2 Pas Bt. Belah 7 m3 518,500 3,370,250
3 Pas. Bt. Onderlagh 0 m3 169,000 50,700
4 Pek Cor Beton Lap Onderlagh 0 m3 920,510 276,153
5 Pek Plat Cor Beton Bertulang 1 m3 3,891,176 2,918,382
6 Pek. Begesting 5 m3 108,400 542,000
7 Pek. Decker 1 m3 245,820 245,820
8 Plesteran 5 m3 26,868 134,340
sub total 7,612,645
IV Alat
centong semen 19 bh 15,000 285,000
cangkul 18 bh 60,000 1,080,000
benang 12 pak 25,000 300,000
ember 80 bh 6,000 480,000
papan spasi 8 bh 10,000 80,000
grobag dorong 6 bh 450,000 2,700,000
sewa 2 molen +solar 80 hr 200,000 16,000,000
sub total 20,925,000

v Operasional 5000000
TOTAL 255,050,856
Dana BLM PPIP 250000000
Sumber Dana
Swadaya Masyarakat 5,050,856

Diperiksa Oleh Dibuat Oleh


Fasilitator Masyarakat Ketua OMS Kader Desa

Agus W R, S.Pd

Rizki Oktarinda, ST Surip Gampang

Diverivikasi Oleh
TAMK
Ali Murtadho, ST
etonisasi Dusun Gandon
RENCANA PENGGUNAAN DANA TAHAP I

PROVINSI : JAWA TENGAH DESA :GANDU


KABUPATEN : TEMANGGUNG PROGRAM :PPIP 2013
KECAMATAN : TEMBARAK JENIS KEGIATAN :BETONISASI JALAN

NO JENIS BAHAN VOLUME HARGA SATUAN JUMLAH


1 2 3
A ALAT DAN BAHAN
1 Kayu Papan 3/20/200 200.00 Rp. 10,000 / m3 Rp. 2,000,000.00
2 Usuk 5/6/200 100.00 Rp. 10,000 / m3 Rp. 1,000,000.00
3 Paku 8.00 Rp. 18,000 / m3 Rp. 144,000.00
4 Pasir 66.436 Rp. 140,000 / kg Rp. 9,301,040.00
5 Batu Pecah 2/2 75.276 Rp. 195,000 / Zak Rp. 14,678,820.00
6 plastik cor 1,700.00 Rp. 700 / m3 Rp. 1,190,000.00
7 semen 604 Rp. 63,000 / kg Rp. 38,052,000.00
8 ember 50 Rp. 6000 / kg Rp. 300,000.00
9 benang 3 Rp. 25000 / ltr Rp. 75,000.00
10 centong semen 5.00 Rp. 15,000.00 / bh Rp. 75,000.00
11 gerobak dorong 3.00 Rp. 450,000.00 / bh Rp. 1,350,000.00
12 molen 80.00 Rp. 200,000.00 / hr Rp. 16,000,000.00
13 cangkul 10.00 Rp. 60,000.00 / m3 Rp. 600,000.00
SUB TOTAL Rp. 84,765,860.00
B UPAH
Tukang 87.264 50,000.00 Rp. 4,363,200.00
Pekerja 222.276 40,000.00 Rp. 8,891,040.00
SUB TOTAL Rp. 13,254,240.00
C OPERASIONAL
1 Administrasi Rp. 700,000.00
2 Dokumentasi Rp. 250,000.00
3 biaya untuk musyawarah Rp. 750,000.00
4 Transportasi Rp. 300,000.00
SUB TOTAL Rp. 2,000,000.00
JUMLAH TOTAL Rp. 100,020,100.00
Terbilang : Seratus Juta Rupiah

GANDU, 20 NOVEMBER 2013


KETUA OMS DESA GANDU

(SURIP)
hanya rabat beton
DIKURANGI RPD1 total buat rpd RPD 2
Kayu Papan 3 200.00 200.00 10,000
Usuk 5/6/200 100.00 100.00 10,000
Paku 8.00 8.00 18,000
99.65 Pasir 166.09 66.436 140,000 50 7000000
112.91 Batu Pecah 2 188.19 75.276 195,000 70 13650000
0.00 plastik cor 1,700.00 1,700.00 700
956.60 Semen 1,560.60 604 63,000 185.6484 11,695,849.20
0.00 ember 50 50 6000
0.00 benang 3 3 25000
0.00 Cangkul 10.00 10 60,000
0.00 Centong Sem 5.00 5 15,000
0.00 Sewa 2 Molen 80.00 80 200,000
0.00 Gerobak Dor 3.00 3 450,000

130.90 Tukang 218.16 87.264 50000 65 3,250,000.00


333.41 Pekerja 555.69 222.276 40000 162 6,480,000.00

0
RPD 3

49.65 6951560
42.91 8368230
0.00 0
770.95 48569951
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
0.00 0
65.90 3294800
171.41 6856560
74041101
RENCANA PENGGUNAAN DANA TAHAP II

PROVINSI : JAWA TENGAH DESA :GANDU


KABUPATEN : TEMANGGUNG PROGRAM :PPIP 2013
KECAMATAN : TEMBARAK JENIS KEGIATAN :BETONISASI JALAN
: TALUD
: DECKER PLAT
NO JENIS BAHAN VOLUME HARGA SATUAN JUMLAH
1 2 3
A ALAT DAN BAHAN
1 Batu Belah 46.32 Rp. 140,000.00 Rp. 6,484,800.00
2 Pasir 72.02 Rp. 140,000.00 Rp. 10,082,800.00
3 Semen 334.60 Rp. 63,000.00 Rp. 21,079,800.00
4 Batu Pecah 2/3 71.1 Rp. 195,000.00 Rp. 13,864,500.00
5 Besi Beton 10mm 220 Rp. 6,000.00 Rp. 1,320,000.00
6 Bendrat 4.00 Rp. 17,000.00 Rp. 68,000.00
7 Batu Bata 280 Rp. 800.00 Rp. 224,000.00
8 Papan 2/20/200 15 Rp. 10,000.00 Rp. 150,000.00
9 Usuk 5/6/200 10 Rp. 10,000.00 Rp. 100,000.00
10 Bambu 3.00 Rp. 15,000.00 Rp. 45,000.00
11 Paku 2.00 Rp. 18,000.00 Rp. 36,000.00
12 cangkul 8.00 Rp. 60,000.00 Rp. 480,000.00
13 centong semen 14.00 Rp. 15,000.00 Rp. 210,000.00
14 benang 2.00 Rp. 25,000.00 Rp. 50,000.00
15 ember 30.00 Rp. 6,000.00 Rp. 180,000.00
16 papan spasi 8.00 Rp. 10,000.00 Rp. 80,000.00
17 gerobak dorong 3.00 Rp. 450,000.00 Rp. 1,350,000.00
SUB TOTAL Rp. 55,804,900.00
B UPAH
Tukang 117.28 50,000.00 Rp. 5,864,000.00
Pekerja 283.28 40,000.00 Rp. 11,331,200.00
SUB TOTAL Rp. 17,195,200.00
C OPERASIONAL
1 Administrasi Rp. 700,000.00
2 Dokumentasi Rp. 250,000.00
3 biaya untuk musyawarah Rp. 750,000.00
4 Transportasi Rp. 300,000.00
SUB TOTAL Rp. 2,000,000.00
JUMLAH TOTAL Rp. 75,000,100.00
Terbilang : Tujuh Puluh Lima Juta Rupiah

GANDU, 1 DESEMBER 2013


KETUA OMS DESA GANDU

(SURIP)
RENCANA PENGGUNAAN DANA TAHAP III

PROVINSI : JAWA TENGAH DESA :GANDU


KABUPATEN : TEMANGGUNG PROGRAM :PPIP 2013
KECAMATAN : TEMBARAK JENIS KEGIATAN :BETONISASI JALAN

NO JENIS BAHAN VOLUME HARGA SATUAN JUMLAH


1 2 3
A ALAT DAN BAHAN
4 Pasir 49.65 Rp. 140,000 Rp. 6,951,000.00
5 Batu Pecah 2/2 42.91 Rp. 195,000 Rp. 8,367,450.00
7 semen 770.95 Rp. 63,000 Rp. 48,569,850.00
SUB TOTAL Rp. 63,888,300.00
B UPAH
Tukang 65.9 50,000.00 Rp. 3,295,000.00
Pekerja 170.42 40,000.00 Rp. 6,816,800.00
SUB TOTAL Rp. 10,111,800.00
C OPERASIONAL
1 Administrasi Rp. 250,000.00
2 Dokumentasi Rp. 100,000.00
3 biaya untuk musyawarah Rp. 500,000.00
4 Transportasi Rp. 150,000.00
SUB TOTAL Rp. 1,000,000.00
JUMLAH TOTAL Rp. 75,000,100.00
Terbilang : Tujuh Puluh Lima Juta Rupiah

gandu,
KETUA OMS DESA GANDU

(SURIP)