REF: SB032/BLD/HYGC/WR03

CONSTRUCTION PROGRESS REPORT

PROJECT TITLE : CONSTRUCTION AND COMPLETION OF 1 UNIT OF WATCH TOWER AT K3D2, SIBU
CLIENT : BINTULU LUMBER DEVELOPMENT SDN BHD
CONTRACTOR : HY GENERAL CONTRACTOR
CONTRACT PERIOD : 16.02.2017 - 15.07.2017

WEEKLY REPORT
% Complete
NO SCOPE OF WORKS
Last Week 06/03-10/03/17
1 PILING 100% 100%
2 PILE CAP/FOOTING 100% 100%
3 GROUND BEAM 100% 100%
4 GROUND SLAB 50% 100%
5 FENCING + GATE 0% 0%
6 TRUSSES/BRACING 5% 30%
7 LADDER 0% 0%
8 ROOFING WORK 0% 0%
9 BOLT & NUT/PAINTING/WELDING WORK 0% 0%
10 LIGHTNING ARRESTER 0% 0%
OVERALL COMPLETION 35.5% 43.0%

PREPARED BY,

(WILLIAM TING)
PROJECT ENGINEER, KTS PD3

Page 1 of 3
REF: SB032/BLD/HYGC/WR03

Slab done. Slab.

Distance to side edge. Distance to side edge.

Bolt length. Bolt length.

Trusses welding in progress. 8 trusses done.

Page 2 of 3
REF: SB032/BLD/HYGC/WR03

Site Diary
1. Work on welding at the trusses not yet completed. Length of the weld must be in 5 inches long.
2. 8 trusses are built.
3. Follow up and discuss with Yii about the problem on the cast-in bolts.