Você está na página 1de 24

Bill No.

1 - General Items

Rate
Item Description Quantity Unit
RM
1.0 Preliminaries
Allow for the provision of -

a) Performance Bond amounting to 5% of Lump Sum 3,000.00


Contract Sum

b) All Insurance in accordance to Preamble to Lump Sum 5,000.00


Bill of Quantity
1.1 Contractor's Superintendence

Provide all necessary superintendence during Lump Sum 15,000.00


the execution of the works including
appointment of a site agent
1.2 Setting out and survey works
Allow for the services of Licensed Surveyor, Lump Sum 5,000.00
approved by the S.O. for setting out of the
works and other survey works in accordance
with the Specification
1.3 Office Accomodation for Superintending
Office and his staff
Provide and maintain a site office for the S.O.'s Lump Sum
supervision staff inclusive of furniture and
fitting and all in accordance with drawings and
specification.

1.4 Contractor's Office and Accommodation


Provide and maintain Contractor's office, store, Lump Sum 5,000.00
workshop, workmen's accommodation necessary
fencing and their removal or reinstatement on
completion of the Works

1.5 Services
a) Allow for the provision or water, lighting power Lump Sum 1,500.00
for the works and for S.O.'s and Contractor's
offices and accommodation of the contractor's
staff

b) Allow for the provision of water, lighting and Lump Sum


power for office accommodation for
Superintending Officer and his staff
c) Allow for the provision of First Aid Box, Helmet, Lump Sum 500.00
Boots and all necessary services, guards,
watching and pay all charges as required.
1.6 Telephone for S.O.'s Staff
Allow for the installation of a handphone system Lump Sum 1,000.00
for the exclusive use of S.O.'s representative
and payment for all monthly charges including
the bills for the telephone calls
1.7 Sign Boards
Supply, erect and maintain sign boards in Lump Sum 1,500.00
accordance with the Specification and
drawing

Total Carried Forward


Amount
RM

3,000.00

5,000.00

15,000.00

5,000.00

5,000.00

1,500.00

500.00

1,000.00

1,500.00

37,500.00
Rate Amount
Item Description Quantity Unit
RM RM

Brought Forward : 37,500.00

1.8 Progress Photographs


Provide colour progress photographs to be Lump Sum 1,000.00 1,000.00
taken when directed by the S.O. Each set shall
consist of eight colour prints of postcard size.
6 sets of the photograph shall be submitted at
forthnightly interval.

1.9 Temporary Works


Allow for the provision and maintenance of all Lump Sum 5,000.00 5,000.00
temporary works including temporary drains,
access road for both contractors and other
contractors, temporary diversion and all others
as specified by S.O.'s or as shown in the drawing.
1.10 Plants

Allow for mobilisation and demobilisation Lump Sum 15,000.00 15,000.00


of all plants
1.11 Working Hours for S.O.'s Supervisory's Staff

Allow for the compliance of working hours for Lump Sum 1,000.00 1,000.00
Superintending Officer's site representatives
1.12 Clearing up site

Allow for clearing up site during progress and on Lump Sum 5,000.00 5,000.00
completion of works

1.13 As-Built Drawings


Allow for the preparation of as built drawings
with Engineer and Licensed Surveyor Lump Sum 1,500.00 1,500.00
endorsement and all attendance of the
Superintending Officer to verify the accuracy of
the drawings.
The as-built drawings shall be prepared using

Autocad or compatible computer software.


3 sets of paper prints and one set of diskette
containing the file shall be submitted to the
Engineer.
1.14 Traffic Control

Allow for the provision and maintenance of temporary Lump Sum 3,000.00 3,000.00
road diversion, all traffic or warning sign, signals,
barricades, road barriers and blinking lamps as
compliance with requirement of JKR and other
relevant authorities in connection with the works
1.15 Co-ordination
Allow for co-ordination with other contractors Lump Sum 2,000.00 3,000.00
working on the site
1.16 Compliance to Specification and Conditions of
Contract
Allow for the compliance of Specification and Lump Sum 500.00 500.00
conditions of Contract which are not specifically
mentioned in the Bill
Total Carried To Summary 72,500.00
Bill No. 2 - PILING (SPUN CONCRETE PILE)

Rate Amount
Item Description Quantity Unit
RM RM
For desription of Materials and Workmanship applicable to this
Bill, see Section 'B' Materials, Workmanship and Preambles to all
Trades

INFORMATION

The work in this section comprises :

A Installation of spun concrete piles as per Engineering drawings

B The paylength for the supply of piles shall be measured from toe
of pile to cut-off level of pile. Unless otherwise shown, cut-off level
of pile shall mean 75mm above the underside level of the pile
cap. This will apply to all piles used in the Works. In the case of
test piles, the Contractor shall allow in this rates for supplying the
excess lengths of pile required above the cut-off levels to
whatever level above the ground for the necessary pile testing.

D The paylength for driving of each pile shall be the actual


penetration of each pile into the ground.

E The rates for driving of piles shall include for driving through
whatever material encountered

F The supply or casting of the spun piles shall only commence upon
the Architects instruction which will be issued soon after
preliminary pile test. The contractor's attention is drawn to the
condition that piles cast shall not be driven until they are at least 4
weeks old. use of rapid hardening cement for casting of piles shall
be subject to the approval of the Architect and Contractor's rates
for the supply of the piles shall be deemed to include for the uise
of such material. The Contractor shall be deemed to have allowed
in the stipulated completion period or in his nominated completion
period all the time he requires to cast and install the piles for
testing, carry out the preliminary pile test and to wait for the
Architect's instruction to commence with the piling works.

G The rates for spun piling shall include for the setting out of all
piles by an approved Licensed Surveyor and the preparation of
as-built pile position plans.

Temporary Works :

H Allow for providing, maintaining, altering and adapting (as when


necessary) all temporary works in connection with taking over the
site i.e slope protection and reinstatement of slopes, temporary
drainage, pumping, any additional excavation required in
conjunction with piling and working space and any additional
excavation and hiling required in conjunction with formation of
platforms for piling and be responsible for their adequacy and all
liabilities arising.

Total Carried Forward


Bill No. 2 - PILING (SPUN PILE)

Rate Amount
Item Description Quantity Unit
RM RM
PILING PLANT AND EQUIPMENT

A Allow for the provision of all necessary piling equipment, plant,


tools and ancillary equipment and for their transportation to site,
handling, assembling, erecting, dismantling and removal on
completion

B Allow for moving, handling and maintaining piling equipment,


plant tools and anciDary equipment about the site as often and
whenever necessary for the execution of the whole piling
operation including any excavation and filling required for moving
the plant, tools and ancillary equipment from differing levels of the
site, erection of any staging required, installing piles on
embankments or slopes and dismantling and removal on
completion and all idling time

SPUN CONCRETE PILES

Spun concrete piles Grade. As described including all


necessary formwork, reinforcement and lifting toggles all as per
engineer's drawings

250 diameter piles 21


300 diameter piles
500 diameter piles

Total Carried Forward 37,500.00


Bill No. 3 - FOUNDATION (INCLUDING GROUND BEAMS)

Rate Amount
Item Description Quantity Unit
RM RM
For description of Materials and Workmanship applicable to
this Bill, see Section B-" Materials, Workmanship and
Preambles to all Trades"

EXCAVATION

A Excavating pit for foundation including backfilling with 3014 m 45,208.00


approved excavated material : compaction in layers and
disposal of surplus excavated material to Employer's pit not
exceeding 1 km from site including depositing, levelling and
compacting in layers:

LEAN CONCRETE

B Reinforced Grade 15 Concrete as described


Foundation 9 m 24.50 221.00

IN-SITU CONCRETE
Reinforced Grade 25 Concrete as described

C Foundation 173 m 43,147.00

D RC Wall 106 m 26,490.00

E Column 278 m 69,476.00

F Beam 9965 m 163,746.00


G Slab 605 m 144,618.00
Formwork

H Foundation 363 m 10,878.00


I RC Wall 1302 m 39,072.00
J Column 2761 m 78,230.00
K Beam 5223 m 156,692.00
L Slab 4034 m 121,021.00
High Tensile Reinforcement Bars including cutting,
bending, binding wires and all necessary spacer blocks.
(Provisional)

M 32mm diameter kg
N 25mm diameter kg
O 20mm diameter kg
P 16mm diameter kg
Q 12mm diameter 26184 kg
R 10mm diameter 97101 kg 242,754.00

Total Carried Forward 996,935.00


Rate Amount
Item Description Quantity Unit
RM RM
Precast Drain
2.1 Excavate and construct precast drain (brickwall to be
paid separately) including lean concrete, mesh fabric,
Grade 20 concrete bedding with X-distance as shown
on drawing , jointing and stepping where required .
(a) 300mm half round drain 2,491 lin. m. 80.00 199,280.00

(b) 450mm half round drain R.O lin. m. 120.00


Brickwork
2.2 Construct cement sand brickwall to sides of half
round drain inclusive of R.C. Struts, crusher run,
weep holes complete with geotextile wrapping to the
thickness as shown on the drawings, cement mortar
rendering and backfilling complete as shown on the
drawing.
(a) 225mm thick 3,186 sq.m. 47.00 149,742.00
(b) 345mm thick 390 sq.m. 65.00 25,350.00
(c) 450mm thick 55 sq.m. 85.00 4,675.00
Pipe Culvert
2.3 Supply and construct precast pipe culvert Class "Y"
to road crossing including spigot, socket, rubber ring
and all necessary joint. Rate to include excavation,
lean concrete, Grade 20 concrete bedding and
surround, mesh fabric reinforcement, jointing and
backfilling complete as shown on drawings : (Bakau
piling to be paid separately)
(a) 750 mm dia. (with concrete surround) 34 lin.m 260.00 8,840.00
(b) 900 mm dia. (with concrete surround) R.O lin.m 320.00
(c) 1050 mm dia. (with concrete surround) R.O lin.m 395.00
Culvert Sump For Pipe Culvert
2.4 Excavate, supply and construct cement sand brick
sump at inlet and outlet of culvert to the thickness as
shown in drawings. Rate to include lean concrete,
Grade 20 concrete bedding, mesh fabric reinforcement,
cement rendering, R.C strut, stainless steel steps and M.S
grating complete as shown on drawing and excavation
stabilisation measure during construction include
sheet piling. (Bakau piling to be paid seperately).
(a) Internal size 1050mm x 900mm, depth
not exceeding 1.5m 5 no. 850.00 4,250.00
(b) Internal size 1050mm x 900mm, depth exceeding
1.5m, not exceeding 2.0m 1 no. 1,100.00 1,100.00
(c) Internal size 1200mm x 900mm, depth exceeding
1.5m, not exceeding 2.0m R.O no. 1,350.00
(d) Internal size 1200mm x 900mm, depth exceeding
2m, not exceeding 2.5m R.O no. 1,600.00
(e) Internal size 1350mm x 900mm, depth exceeding
2m, not exceeding 2.5m R.O no. 1,850.00

House Entrance Slab

2.5 Excavate, supply and construct house entrance


slab over the drain and headwall complete
as detailed as shown in the drawing.
(a) 3600 mm x 1050mm x 100mm thick R.O no. 350.00

(b) 8720 mm x 1050mm x 100mm thick R.O no. 670.00

Total Carried Forward 393,237.00


Rate Amount
Item Description Quantity Unit
RM RM
Br 393,237.00
2.5 Excavate and construct 230 mm high x 230 mm ou
thick brickwork head wall to sides of entrance gh
slab inclusive of cement mortar plastering complete t
as shown on the drawing. R.O no. 35.00
Fo
M.S Grating rw
ar
2.6 Supply and lay 600mm x 600mm m.s grating d
to house entrance slab complete as detailed
as shown in the drawing. R.O no. 95.00
Slab Culvert
2.70 Supply and construct 100mm thk. grade 20 concrete slab
culvert over drain completed as shown on drawing R.O no. 350.00
PC slab over drain
2.80 Supply and install 750 x 900 mm (w x L) grade 20 precast
concrete slab over drain at backlane for each individual house R.O no. 38.00
completed as shown on drawing

Bakau Piling

2.12 (a) Mobilisation, transport and set up all necessary


bakau piling plant and equipment at sites, dismantle and
remove them on completion of all bakau piling work 1 Lump 1,000.00 1,000.00
(b) Supply, handle, pitch and drive 100mm diameter Sum
bakau piles (initial/ extension) including cutting off pile
head 4,900 lin.m 2.50 12,250.00
(c) Supply and fix 100mm dia. M.S Sleeve for jointing bakau p 490 no. 8.00 3,920.00
M.S Sleve shall be of size 450mm long x 3mm thk.

Total Carried to Summary 410,407.00


Rate Amount
Item Description Quantity Unit
RM RM
Preparation of Pavement Formation
3.1 Excavate and shape the road subgrade to the correct
alignment, levels and gradients as shown on the
drawings, including boxing out and consolidating by a
10 ton smooth-wheeled roller ; part return of
excavated material to shoulder and medium including
fill-in, ram and compact to the required formation level
and gradient; removal of excess excavated material
to filling ground designated by S.O. including filling in,
ram and compaction. 15,301 sq.m. 2.50 38,252.50

Sub-Base

3.2 Supply, spread and compact sand to the 50mm


compacted thickness as shown in the drawings
ram and compaction. 15,301 sq.m. 2.50 38,252.50

Road-Base

3.3 Supply, spread and compact approved crushed


rock road base to the compacted thickness as
shown in the drawings
(a) 225 mm thick 15,301 sq.m. 11.20 171,371.20

Asphaltic Concrete Surfacing

3.4 Supply and apply emulsified bituminous prime coat to


surface of crushed rock road base 15,301 sq.m. 0.70 10,710.70

3.5 Supply and apply bituminous tack coat to binder


course surface prior to laying of wearing course 14,919 sq.m. 0.70 10,443.30

3.6 Supply , lay and compact asphaltic concrete


surfacing to the compacted thickness as shown in
the drawing
(a) wearing course - 50 mm thick 14,919 sq.m. 12.50 186,487.50

(b) binder course - 60 mm thick 14,919 sq.m. 13.50 201,406.50

Turfing

3.7 Supply and lay spot turfing to road median, road


shoulder and at location as specified in the drawing,
including 50mm of selected topsoil, pegging, watering 3,963 sq.m. 2.50 9,907.50
and tendering to ensure growth of turf planted.
Pavement Marking and Road Sign

3.8 Supply and install "BERHENTI" sign and 300mm


wide stop lines pavement marking with Thermoplastic
paint at all junction to JKR standard. 11 no. 450.00 4,950.00

Total Carried Forward 671,781.70


Rate Amount
Item Description Quantity Unit
RM RM
Brought 671,781.70
Forward :
To supply and install all road signage complete at all the
road junction governed under area as
shown on the drawings to JKR satisfaction. 2 no. 450.00 900.00
3.9
3.10 To mark the pavement of the junction, accerelation and
deceleration lane at all the road junction governed under
Phase 1 as shown in the drawings or as directed by S.O.
and to JKR satisfaction.
(a) 100mm wide broken centre lines 1,759 lin.m 2.50 4,397.50

(b) 150mm wide pavement edge lines 3,449 lin.m 3.50 12,071.50
(d) Straight through direction arrow 5 no. 80.00 400.00
(e) Left and right turn direction arrow R.O no. 100.00
(g) Straight through, left and right turn direction arrow 1 no. 120.00 120.00
(f) Left or right turn direction arrow R.O no. 90.00
Kerb

3.11 Excavate, supply and construct precast kerb Type


M1 including 1:3:6 concrete base and haunching,
reinforcement and formwork, where required and
painting complete as shown on drawing 225 lin.m 27.00 6,061.50

Scupper Drain

3.13 Excavate, supply and lay 225mm dia earthened


ware pipe including 100mm thick 1:3:6 concrete
foundation, backfilling to required level complete
as shown in the drawing 178 lin.m. 38.00 6,764.00

Guardrail

3.14 Supply and construct new G.I gaurd rail next to main drain 200 lin.m. 105.00 21,000.00

at location as shown in the drawing

Replacement of Unsuitable Material

3.15 Excavate and remove from site unsuitable material below R.O m
3 ###
road formation level up to 600 mm deep and replace with
compacted suitable material from contractor own source

Total Carried To Summary 723,496.20


Rate
Item Description Quantity Unit
RM
Trench Excavation
4.1 (i) Trench excavation of sewer pipe for depth exceeding
1.5 m but not exceeding 2.0 m including part backfill
on completion, compaction, removal of surplus,
shoring and/or sheet pile where necessary:-
(a) 225mm dia V.C. pipe 601 lin.m 20.00
(b) 300mm dia V.C. pipe R.O lin.m 20.00
(ii) -ditto- exceeding 2.0m but not exceeding 3.0m
(a) 225mm dia V.C. pipe 596 lin.m 26.00
(b) 300mm dia V.C. pipe 105 lin.m 20.00
(iii) -ditto- exceeding 3.0m but not exceeding 4.0m
(a) 225mm dia V.C. pipe 224 lin.m 55.00
(b) 300mm dia V.C. pipe 113 lin.m 20.00
(iv) -ditto- exceeding 3.0m but not exceeding 4.0m
(a) 225mm dia D.I.(Ductile Iron). Pipe R.O lin.m 80.00
(b) 300mm dia V.C. pipe 211 lin.m 20.00
4.2 Extra over item 4.1 for trench excavation in mettalled road. R.O lin.m 75.00
Rate to include cutting of mettalled pavement with diamond
cutter, reinstatement of mettalled road with 50mm thick sand
blanket, 300mm thick crusher run, 50mm thick binder
course and 60mm thick wearing coarse.
4.3 Ditto ~ for trench excavation under existing road side drains. R.O Lump Sum 2,000.00
Rate to include reinstatement of road side drain.
4.4 Ditto ~ for trench excavation under existing main drains. R.O Lump Sum 1,000.00
Rate to include reinstatement of pudu cut main drain.
Pipe Laying

Notes : -
All sewer with diameter less than 450mm shall be
vitrified clay pipe (VCP) with flexible joint and comply
with M.S 881 Part 1 1991, M.S. 1061;1986.
Foundation base of sewer must be compacted with
crushed run.
All sewer with diameter 450mm and above shall be
centrifugal spun reinforced concrete pipe (RCP) of
class Z. All RCP shall be internally line with 12mm
thick high alumina cement mortar. All pipe joints with
flexible rubble rings joints.
4.5 Supply and lay sewer pipes complete including
jointing, concrete/granular bedding, haunching all as
specified
(a) 225mm dia V.C. pipe (Class A bedding) 1,421 lin.m 105.00
(b) 300mm dia V.C. pipe (Class A bedding) 429 lin.m 100.00

4.6 Connection to Existing Mainhole

Allow for connection of VCP pipe to existing manhole. Lump Sum 1,000.00
Rate to include reinstatement and make good of
existing manhole.
Carried Forward
Bill No. 4 - Sewerage Reticulation

Rate
Item Description Quantity Unit
RM
Brought Forward :
Precast Concrete Manhole

4.7 Excavate, supply and construct precast concrete


manholes complete including lean concrete, Grade
20 cast in-situ concrete ring base, building in pipes,
benching, precast r.c. chamber, Grade 20 mass
concrete surround, formwork, stainless steel steps,
precast r.c. cover slab complete as detailed and
shoring and/or sheet pile where necessary
during construction.
(manhole cover and frames to be paid separately)
(i) Manhole type 1 with chamber diameter 1200mm
(for sewer pipe 225mm & 300mm)
(a) below ground level to invert level not exceeding 2.0m 14 no 2,000.00
(b) ditto exceeding 2.0m but not exceeding 3.0m 11 no 2,800.00
(c) ditto exceeding 3.0m but not exceeding 4.0m 5 no 3,300.00
(d) ditto exceeding 4.0m but not exceeding 5.0m 4 no 3,301.00
4.8 Supply and fix the following for manhole
backdrop including excavation:
(a) D.I. Tee 225mm x 225mm dia including N/A no 150.00
M.S. cover plate
(c) 90 degree medium D.I. Bend 225mm dia. N/A no 20.00

(e) D.I. Straights 225mm dia N/A lin.m 60.00

(g) concrete grade 15 mix including formwork N/A cu.m 70.00

4.9 Supply and fix Heavy Duty ductile iron manhole 34 no 440.00

covers and frames as specified

Carried Forward
Amount
RM

12,026.00

15,485.60
2,104.00

12,325.50
2,256.00

4,220.00

149,205.00
42,900.00

1,000.00

241,522.10
Amount
RM
241,522.10

28,000.00
30,800.00
16,500.00
13,204.00

14,960.00

344,986.10
Rate
Item Description Quantity Unit
RM
Brought Forward :
Testing of Sewer Line

4.6 (a) Carry out test for straightness and obstruction on all 1 Lump Sum 2,000.00
sewer lines as specified in Clause 4.3(a) of Section 5 of
Specification
(b) Carry out water testing on all sewer lines as specified in 1 Lump Sum 2,000.00
Clause 4.3(b) of Section 5 of Specification
(c) Carry out air testing on all sewer lines as specified in N/A
Clause 4.3(c) of Section 5 of Specification
(d) Carry out C.C.T.V. Test and submission of test report for
sewer lines as directed by S.O. representative or IWK/JPP
(i) 225mm dia. V.C. pipe 278 lin.m 25.00

4.7 Excavate beyond foundation level as directed by the


S.O. and backfill with selected material (Provisional) Rate only cu.m
Service Connection

4.8 (a) Excavate, supply and lay 150mm dia. V.C.


service pipe in class A bedding, 225mm dia. x
150mm dia. v.c. 'Y' junction including concrete
thrust block, 150mm dia. x 45 degree v.c. short
bend, end cap at location as directed by S.O. (Provisional)
complete as shown on the drawings 91 no 450.00
(b) Supply and install Marker complete as shown on the Rate Only no 50.00
drawings
(c) To excavate, supply and construct last manhole within Rate Only no
housing lot at the depth of 1.35m as shown on the
drawings
d) To supply and install end cap and install marker to D.I pipe 1 L.s 165.00
for future connection to last manhole of P.S.No.4
IWK Inspection

4.9 Allow for liasing with IWK/JPP for interim inspection 1 Lump Sum 4,000.00
during construction and final inspection for
handing over

Total Carried To Summary


Amount
RM
344,986.10

2,000.00

2,000.00

6,937.50

40,950.00

4,000.00

400,873.60
Rate Amount
Item Description Quantity Unit
RM RM

TRENCH EXCAVATION

Excavate in all material below completed platform level

Trench excavation shall be measured once only to


the full depth of the trench.

5.1 Excavation trench not exceeding 1.5 m deep for


water mains. Rate to include backfilling,compaction,
dewatering, timbering and removal of surplus
excavated material for :
(a) 150mm dia. pipe 2,005 lin.m 8.00 16,040.00
(b) 200mm dia. pipe R.O lin.m 10.00
(c) 300mm dia. pipe R.O lin.m 15.00
(d) 450mm dia. pipe 356 lin.m 20.00 7,120.00

5.2 -ditto- exceeding 1.5m

(a) 150mm dia pipe R.O lin.m 15.00


(b) 200mm dia. pipe R.O lin.m 20.00
(c) 300mm dia. pipe R.O lin.m 30.00
(d) 450mm dia. pipe R.O lin.m 40.00

5.3 Remove unsuitable materials beyond nominal 10 cu.m 15.00 150.00

limits of trench excavations as orded by the S.O.


and backfill with selected materials; rate to
include disposal material to spoil pit as
directed (provisional)

5.4 Supply, fill, spread and compact approved sand 109 cu.m 35.00 3,815.00

in pipe trenches and at road crossing. Rate to


include transportation of sand.

5.5 Import selected earth from borrow site, rate to 10 cu.m 15.00 150.00

include excavation, backfilling, ramming and


compaction (provisional)

PIPE LAYING

Notes:
(a) All spigot and socket ended pipes and specials
shall be suitable for internally & externally
welded slip joints
(b) All steel pipe shall be concrete lined internally
and bitumen coated externally. All exposed steel
pipes and specials shall be externally painted.
(c) The rate for joining pipe, special or fitting shall
be deemed to include the supply and installation
of all joint coupling or mechanical coupling and
jointing material complete
(d) All flanges shall be suitable for a rating of 16
bars unless specified otherwise

Total Carried To Forward 27,275.00


Rate Amount
Item Description Quantity Unit
RM RM
Brought 27,275.00
Forward
(e) The thickness of steel shells and concrete lining
shall be as stated in the specifications
(f) Plain ended pipes shall be suitable for
mechanical coupling or internally and externally
welded collar joints
(g) all pipe diameters mentioned refer to
nominal diameter.
P/E means plain ended
B/F means both end flanged
F/PE means one flanged end and one plain ended
5.6 Supply, lay and join spigot and socket ended
standard or sized steel water pipe; Rate to
include loading, transport, handle, repair lining
and coating where required, cutting, internally &
externally welding and protection to welded
joints and painting as specified.

(a) 150mm dia. pipe 2,005 lin.m 88.00 176,440.00

(b) 200mm dia. pipe R.O lin.m 126.00


(b) 300mm dia. pipe R.O lin.m 200.00
(d) 450mm dia. pipe 356 lin.m 300.00 106,800.00

Culvert Crossing

5.7 Supply, lay and join steel pipe and special

for crossing over culvert or sump rate to


include 1 No. flanged off-take tee for air
valve connection, welding, jointing 4
nos. steel gusseted bends and 75mm x 6mm
thk. M.S. steel strap as shown on drawing -

(a) 150mm dia. pipe 7 no 2,800.00 19,600.00

STEEL SPECIALS

Supply and fix steel specials P/E. Rate to include VA

Dresser joint or mechanical coupling and jointing


material complete

5.8 150mm dia. P/E bend

(a) up to 30 degree 11 no 210.00 2,310.00


(b) more than 60 degree 7 no 220.00 1,540.00

5.9 Tee barrel plain ended and with flanged branch

(a) 150mm x 150mm dia 12 no 240.00 2,880.00


5.10 Hydrant tee, barrel plain ended with flanged
concentric branch
(a) 150mm x 100mm dia 11 no 210.00 2,310.00
TAPERS
5.11 Supply and fix cross P/E
(a) 200mm x 150mm 2 no 450.00 900.00
(b) 300mm x 200 mm R.O no 900.00
Total Carried Forward 340,055.00
Rate Amount
Item Description Quantity Unit
RM RM
Brought 340,055.00
END CAPS Forward :
5.12 Supply and fix end caps
(a) 150mm dia 1 no 220.00 220.00
(b) 200mm dia R.O no 253.00
(c) 300mm dia R.O no 710.00
(d) 450mm dia 1 no 850.00 850.00
Short piece

5.13 short piece x 600mm long P/E for sluice valve


connection
(a) 150mm dia. 8 no. 52.80 422.40
(b) 200mm dia. Rate Only no. 77.00
(c) 300mm dia. Rate Only no. 132.00
(d) 450mm dia 2 no 250.00 500.00

5.14 600mm long flanged and plain ended short piece

for sluice valve connection


(a) 150mm dia. 8 no. 660.00 5,280.00
(b) 200mm dia. Rate Only no. 1,210.00
(c) 300mm dia. Rate Only no. 1,870.00
(d) 450mm dia 2 no 2,000.00 4,000.00
Flanged Adaptor

5.15 Supply and fix flanged adaptor for sluice valve


connection
(a) 150mm dia. 8 no. 300.00 2,400.00
(b) 200mm dia. Rate Only no. 500.00
(c) 300mm dia. Rate Only no. 800.00
(d) 450mm dia 2 no 900.00 1,800.00
Valves

Supply and fix cast iron fittings and specials for


air valve, sluive valve and Hydrant. Rate to include
mechanical coupling and jointing material
5.16 Air Valves
a) 50mm dia. double orifice air valve complete
with isolating stopcock 7 no 650.00 4,550.00

Sluice Valves

5.17 a) 150mm dia. double flanged sluice valves


suitable for a working pressure of 16 bars 8 no 700.00 5,600.00
b) 200mm dia. ditto - Rate Only no 960.00
c) 300mm dia. ditto - Rate Only no 2,000.00
(d) 450mm dia 2 no 3,500.00 7,000.00
Double oulet pillar hydrant

5.18 (a) 100mm dia. x 300mm B/F ductile iron


lengthening piece 11 no 110.00 1,210.00
(b) 100mm dia. x 500mm B/F ductile iron
lengthening piece 11 no 132.00 1,452.00
(c) 100mm dia. x 1000mm B/F ductile iron
lengthening piece 11 no 187.00 2,057.00
(d) 100mm dia. sluice valve, P.N. 16 rating, B/F 11 no 412.50 4,537.50

(e) 100mm dia. Ductile iron duckfoot bend 11 no 9.00 99.00

(f) Ductile iron double outlet pillar and painted as


directed by the S.O., rate to include concrete
base 11 no 305.00 3,355.00
Total Carried Forward 385,387.90

RM RM
Item Description Quantity Unit 385,387.90
Scour valve
5.19 Scour valve including 100 mm dia. sluice
valve, ductile iron lengthening piece, flanged
spigot, gibault coupling and short length
of 100mm dia. uPVC Pipe class D to drain
complete as shown on drawing. Rate to
include reinstatement of drains to its
original state ( excluding tee) 3 no 1,200.00 3,600.00

5.20 Washout

Washout at dead end including 100mm 3 no. 1,200.00 3,600.00


dia. sluice valve, brick chamber and
short length of uPVC pipe class D
to drain complete as shown on Drawing.
Rate to include reinstatement of drains to
its original state

P.C Markers and Chambers

5.21 Supply and fix precast concrete marker,


including painting as directed for
(a) sluice valve 10 no 75.00 750.00
(b) air valve 7 no 75.00 525.00
(c) scour valve/ washout 3 no 75.00 225.00
(e) pipe 5 no 75.00 375.00

5.22 Supply and construct precast concrete

chamber as detailed on drawing; rate to


include excavation, sand bedding, complete
with covers requirement
(a) hydrant valve 11 no 300.00 3,300.00
(b) sluice valve 10 no 300.00 3,000.00
(c) air valve 7 no 300.00 2,100.00

5.23 Supply and construct brickwork chamber as

detailed on drawing; rate to include


excavation, sand bedding , complete with
covers to JBA requirement
(a) scour valve 3 no 650.00 1,950.00

Thrust and Anchor Blocks

5.24 Supply and construct thrust, diaphram

and anchor blocks. Rate to include


excavation backfilling, compaction, concrete
mix as specified, formwork, steel reinforcement
and all as shown on the drawings. 10 cu.m 260.00 2,600.00

Total Carried Forward 407,412.90


Rate Amount
Item Description Quantity Unit
RM RM
Brought 407,412.90
Forward :
Miscellaneous

5.25 Allow for pressure and leakage test

including supply of water and instruments. Lump Sum 3,500.00 0.00

5.26 Allow for disinfection and flushing of pipe

including supply for chemicals, sampling


and chemical analysis Lump Sum 2,000.00 0.00

Service Connection

5.27 Excavate and provide 25mm dia service

connection at the following M.S pipe


rate to include malleable D.I. Clamp
saddle, ferrul, tapping complete
(a) 150mm dia 91 no 120.00 10,920.00

5.28 Excavate, supply and lay 25mm dia S.S. pipe

from tapping point up to the meter


position rate to include bends, laying
through drain and all reinstatement back to
its original conditions, Supplying and laying
sand or quarry dush to S.Steel service connection
pipe at road crossing and all as shown
on the drawings. 382 lin.m 55.00 21,021.00

5.29 Supply and fix (all fitting shall be of Stainless Steel)

(a) 15mm dia ball cock 91 no 9.00 819.00

(b) 25mm x 15mm Elbow 91 no 17.00 1,547.00


(c) 20mm Nipple 91 no 7.50 682.50
(d) 20mm Integrated Lockable Valve (ILV) 91 no 40.00 3,640.00
(e) 25mm x 20mm Bush 91 no 5.30 482.30
(f) 25mm x 20mm Reducer 91 no 18.00 1,638.00
(g) 15mm Nipple 91 no 6.00 546.00

Zone Meter (District Metering)

5.3 Supply and install a zone meter complete with Rate Only no 15,000.00

by pass and all necessary fitting, bends, felxible


coupling,flange adapter, valves and bulk meter
(provisional)

Sampling Box

5.31 Supply and install a PUAS approved sampling box. Rate Only no 5,000.00
Location to be reconfirmed by PUAS.

Total Carried to Summary 448,708.70


SUMMARY OF TENDER

Contract For Construction And Completion of Road & Drainage Works,


Sewer Reticulation, Water Reticulation And Ancillary Work For Bungalow lots
at Phase 3 For Cadangan Pembangunan Perumahan Di Atas Lot 707,
Mukim Tanjung Duabelas, Daerah Kuala Langat Selangor Darul Ehsan

\\vboxsrv\conversion_tmp\scratch_1\
[153888056.xls.ms_office.xls]BQ5

Bill No Description

1 General Items

2 Major Drainage Works & Internal Drainage System

3 Road Work

4 Sewerage Reticulation

5 Water Reticulation

Sub-Total Amount

Add Levy as required by The Construction Industry Development


Board = Sub-Total Amount x ( /
0.125%
)
99.875%

Total carried forward to Form of Tender

Summary
(REV.1)
w lots

nversion_tmp\scratch_1\
xls.ms_office.xls]BQ5

Amount
RM

72,500.00

410,407.00

723,496.20

400,873.60

448,708.70

2,055,985.50