Escolar Documentos
Profissional Documentos
Cultura Documentos
A 245-m long high level arch bridge across river Beas, which main arch is curved in plan. On the right bank, the viaduct
provides bypass to Kullu town in Himachal Pradesh, was comprises of a three-span continuous unit, curved in plan of
recently completed. The contract stipulated that a 100-m long 41-m length.
main arch span be constructed using stay cable system. Site
conditions in typical hilly terrain imposed many constraints The foundations of the viaduct spans are of open type,
founded at about 3 to 4 m below the bed level. The
on construction The paper discusses various constructional
substructure comprises of three circular columns with
aspects of this project, involving the use of cantilever
common capping beam at top, Figure 2. The decking comprises
segmental construction with stay cable system. of twin cell box in reinforced concrete. Since the approaches are
on curves, the deck width varies between 11 and 12 m and is
Keywords: Arch bridge, stay cable system, cantilever segmental
also provided with super elevation.
construction
The main constraint in the construction of the superstructure
The national highway NH-21 leading to the popular hillstation
was the existing roads on both sides. On the right bank, the
of Manali, passes through congested Kullu town. This often
viaduct spans are located over national highway leading to
results in frequent traffic jams. Also, only suspension
Manali with heavy traffic. Staging system of trusses/beams
pedestrian bridges connect portions of Kullu town on left and
supported over trestles was provided allowing for
right banks of river Beas. Thus, vehicular traffic in the town
uninterrupted traffic below. Similar arrangements were
had to take a detour of about 40 km just to cross from one bank
to another. A high level bridge, on road bye-passing Kullu
town, was therefore necessary for overcoming the above
problems.
General arrangement
The project consists of 104-m long viaduct on left bank
followed by 100-m long arch span and 41-m long viaduct
portion on right bank, forming an overall length of 245 m.
Detailed discussion on conceptualisation, general
arrangement, design aspects, etc of the project is covered in a
companion paper1. The general site layout plan is shown in
Figure 1.
CONCRETE BRIDGES 1
provided on the left bank over the small village road with
moderate traffic.
Since the wells were located right on the highway, placing the cast using ground-supported arrangement, Figure 4. The
towers above them would have caused a major obstacle in the general arrangement of the supporting system consisting of
traffic diversion trestles and steel joists has
arrangements planned been shown in Figure 5.
during the construction of
arch. The RC arch, with 4.75-m wide solid The location of trestles
section of varying depth, was built by supporting initial segments
In view of the above, towers had to be carefully decided
had to be located in front of cantilever construction simultaneously so as to control the stresses in
the arch and also to
the foundations, within the from both ends
arch span. The tower accommodate form traveller
configuration was modified for further segments. Sand
to girdle around the arch jacks were provided on the
section. The backstays could main trestles to facilitate
now be anchored in the well cap, Figure 3. With this smooth transfer of supporting system for the arch from ground
arrangement proper traffic diversion and satisfactory stay supported arrangement to stay cables.
cable system could be ensured.
Form traveller
Initial segments The balance portion of arch was cast in segments of 4-m each. A
The RC arch, with 4.75-m wide solid section of varying depth, specially designed form traveller was used for in-situ casting
was built by cantilever construction simultaneously from both of segments, Figure 6. A total of nine segments on either side
ends. Initial portion of about 15 m length on either side was were cast using a pair of such form travellers. As the initial
2 ICJ COMPILATION
Figure 6. A view of the specially-designed form traveller
Figure 5. General arrangement of the support system backstay cables, were stressed. Figure 7 shows a view during
portion of arch was sloping steeply, timber skids with proper segmental construction of arch with stay cable system.
locking arrangements and two 20-tonne capacity hydraulic
jacks were used for moving the form traveller forward for Monitoring during arch construction
casting next segment. The form traveller was equipped with a Geometry of the arch, cable forces and tower deflections were
system of hydraulic jacks, to be used for alignment of the form monitored during each casting cycle. Cable forces and camber
traveller in vertical and horizontal planes and camber for the next segment were reviewed to maintain the profile of
adjustments. the arch and to ensure that the stresses in arch are within
permissible limits. Special formats were devised for reporting
Stay cable arrangement various parameters to design offices. After studying the arch
Stay cables were made from 12.7-mm strands of varying profile and cable forces, the necessary feedback regarding
numbers. Freyssinet's 12K13 system of anchorages and K-200 camber adjustment and adjustments of forces in the stay-
jacks were used for stressing. The back-stay and fore-stay cables stressed earlier were sent from the design office to the
cables converged at two levels of the tower. Fore-stay cables site.
were threaded from bottom of the arch through MS ducts left
in the arch segments. Back-stay cables were threaded from top The closing segment was cast using supporting arrangement
of the tower through ducts left in the well cap. suspended from adjoining portion of arch cast already. On
completion of the arch, stay cables were de-stressed as per
To limit the tower size, stressing of fore-stay cables was done predetermined sequence.
within the space provided in the anchorage zone of tower. The
back-stay cables were stressed
from the lower end anchored
in the well cap. Since the crew
had to be below the ground
level during stressing
operations, special protective
barriers had to be provided to
guard against landslides from
adjoining hills. Kentledge had
to be provided above the
anchorage zone of back-stay
cables to limit tensile stresses
in the steining due to vertical
component of force in the
cables.
Segmental
construction with
stay cable system
After casting each segment, a
pair of forestay cables and
corresponding pair of Figure 7. Segmental construction of arch in progress from both ends
CONCRETE BRIDGES 3
Due to the possibility of
unseasonal floods with heavy
current, the alternative of
providing staging system resting
on riverbed for casting the main
arch was ruled out. Instead, stay
cable system for supporting cast-
in-situ segments of arch was
adopted.
4 ICJ COMPILATION