HAIL SURFACE FACILITIES

EPS PROJECT
ABU DHABI OIL CO. LTD (JAPAN)
ITR (DAILY) FOR TARGET ENGINEERING
Daily ITR No. HSF-TAR-ITR-18/MAY Date of Issue - 17-MAY-17
Intervention
Point
RFI
Reference Inspecti Refere
Sl. Internal Ref. RFI Rev Date for Time for Description of work / Item to be Reference Activity Applicable Checklist
Discipline Drawing ITP Title Location on nce TR Remarks
No. No. . Inspection Inspection Inspected Project ITP No. No. Report No.

Target

ADOC
No. Status RFI

TPI
TR
No.

RFI-HSF- INSPECTION AND TEST HSF-ITP-TEC-MOG-


09.00 AM TO Foundation leveling pad elevation & HD-EC-CM-
1 Structure TARGET-TF- 0 18-May-17 - PLAN FOR 3.2 W W - W Mubarraz - - 0004, F- Civil
05.00 PM location checking-Area 500 ZQXS-5011
STRUCT-0012 MODULE INSTALLATION 06

Transfer of foundations /basements /


pedestals from Civil. Verify that all
RFI-HSF- foundations, foundation bolts and INSPECTION AND TEST
2
09.00 AM TO HD-EC-CM- Release note / Hand
Module TARGET-TF- 0 18-May-17 other PLAN FOR 3.1 H W - W Mubarraz - - Civil
05.00 PM ZQXS-5011 over note
STRUCT-0017 supports for steel works are suitably MODULE INSTALLATION
prepared to receive the steel
structure:

Weld Visual
RFI-HSF- Inspection
09.00 AM TO HD-EC-CM-
3 Module Piping TARGET-TF- 0 18-May-17 Weld Visual Examination - ITP for Module Installation 4.6 W W W Mubarraz - - Report:HSFITP- Mechanical
05.00 PM ZQXS-5011
MEC-0089 TEC-MOG-0006, F-
01

RFI-HSF-
4
Radiographic Film Interpretation for HD-EC-CM-
Module Piping TARGET-TF- 0 18-May-17 10.00 AM - ITP for Module Installation 4.8 W W W W Mubarraz - - Intertek Format Mechanical
Module Piping ZQXS-5011
MEC-0085

RFI-HSF-
Radiographic Film Interpretation for HD-EC-CM-
5 Pipeline TARGET-TF- 0 18-May-17 10.00 AM - ITP for Pipeline 6.3 W W W W Mubarraz - - Intertek Format Mechanical
Pipeline ZQXS-5003
MEC-0090

RFI-HSF-
6
Cathodic Protection Installation and HD-EC-CM-
Pipeline TARGET-TF- 0 18-May-17 10.00 AM - ITP for Pipeline 9.4 W W S Mubarraz - - Holiday Test Report Mechanical
testing ZQXS-5003
MEC-0088

DISCIPLINE SUBCONTRACTOR CONTRACTOR COMPANY

NAME Vipin Unnikrishnan

DESIGNATION QA/QC
SIGNATURE
DATE 13-May-17

Page 1 of 1 LEGEND : A - ACCEPTED; R -REJECED; C - CANCELLED; P-PENDING; H - HOLD