Você está na página 1de 34

Work: Construciton and Upgradation of Road and other structures from Phulwaria ghat at Lalbakiya River to Bahar (Bahera)

Village in Sitamarhi District under INDO-NEPAL Border Road Project for the Year 2

Agreement No. 27/SBD/2012-13


Ageny: M/s Aarpee Infraprojects Pvt. Ltd. (M/s Rajesh Kumar Garg)
Programme of Work
Sl. QNT No. of EXECUTION TIME
ACTIVITY UNIT
No. Y Days October-2013 November-2013 December-2013 January-2014 February-2014 March-2014 April-2014
1 Selection of Site for Casting Yard
Setting up Casting Yardincluding Cement
2 Godown, Site office, Site Lab i/c Fencing etc.
Job 1
3 Procurement of Shuttering material like MS
Sheet, Angle Iron, I Section, etc. Job 1
4 Fabrication of Shuttering
5 Pile Liner nos 6 15.10.13 to 20.07.14
6 Pile Cap
Size 900x1200 = 108.00 sqm
600x900 = 63.00 sqm sqm ### 15.11.13 to 15.12.13
300x1200 =21.60 sqm
300x900mm =16.20 sqm

7 Pier i/c Pier Cap set 1 15.11.13 to 15.12.13


8 Abutment i/c Cap set 1 15.11.13 to 15.12.13
9 I-Beams i/c intermediate cross Girders etc. set 3 20.12.13 to 14.01.14
10 Wing Wall, Retain Wall, Deck Slab, etc.
Size 900x1200 = 108.00 sqm
600x900 = 63.00 sqm
sqm ### 15.12.13 to 15.01.14
300x1200= 21.60 sqm
300x900mm= 16.20 sqm

11 Crash Barrier & Railing, Shuttering etc. = 5 mtr. set 1


12 Length
Piling i/c setting out on ground, boring, using
Bentonite Slurry & Temporary liner, preparing
Reinforcement Cage i/c Cutting, Bending,
Binding, Lowering the Cage in the Bore hole, nos 88
lowering tremmi pipe in the bore hole,
concreting & removal of Temp. Liner etc
complete.

13 Piles of Abutment 'A1' (Bhangaha Side) - Rig No.1 nos 12 36 15.11.13 to 21.12.13
14 Pile of Pier P1 - Rig No.1 nos 10 30 22.12.13 to 22.01.14
15 Pile of Pier P2 - Rig No.1 nos 10 30 23.01.14 to 23.02.14
16 Pile of Pier P3 - Rig No.1 nos 10 30 24.02.14 to 26.03.14
17 Pile of Pier P4 - Rig No.1 nos 10 30 27.03.14 to 26.04.14
18 Pile of Abutment 'A2' - Rig No.2 nos 12 36 15.11.13 to 21.12.13
19 Pile of Pier P7 - Rig No.2 nos 10 30 22.12.13 to 22.01.14
20 Pile of Pier P6 - Rig No.2 nos 10 30 23.01.14 to 23.02.14
21 Pile of Pier P5 - Rig No.2 nos 10 30 24.02.14 to 26.03.14

22 Pile Cap for Abutment A1 including from next


day of completion of Piling work i.e. S.No.5 no. 1 21 22.12.13 to 11.01.13
23 Breacking Pile head, Excavation upto founding
level & P/L PCC, levelling bed etc. complete.
24 Reinforcement i/c Cutting, binding& bending etc.
25 Shuttering i/c shuttering & proping etc.
26 Concreting i/c compaction, curing etc.
27 Deshuttering i/c shifting of material to the other location
28 Pile Cap for
Breacking Pier
Pile P1 Excavation upto founding
head, no. 1 21 23.01.14 to 12.02.14
29 level & P/L PCC, levelling bed etc. complete.
30 Reinforcement i/c Cutting, binding& bending etc.
31 Shuttering i/c shuttering & proping etc.
32 Concreting i/c compaction, curing etc.
33 Deshuttering i/c shifting of material to the other location
34 Pile Cap for
Breacking Pier
Pile P2 Excavation upto founding
head, 21 24.02.14 to 16.03.14
35 level & P/L PCC, levelling bed etc. complete.
36 Reinforcement i/c Cutting, binding& bending etc. nos
37 Shuttering i/c shuttering & proping etc.
38 Concreting i/c compaction, curing etc. nos 1
39 Deshuttering i/c shifting of material to the other locat nos 1
40 Pile Cap for
Breacking Pier
Pile P3 Excavation upto founding
head, 21 27.03.14 to 16.04.14
41 level & P/L PCC, levelling bed etc. complete.
42 Reinforcement i/c Cutting, binding& bending etc.
43 Shuttering i/c shuttering & proping etc.
44 Concreting i/c compaction, curing etc. nos 1
45 Deshuttering i/c shifting of material to the other locat nos 1
46 Pile Cap for
Breacking Pier
Pile P4 Excavation upto founding
head, 21 11.04.14 to 31.04.14
47 level & P/L PCC, levelling bed etc. complete.
48 Reinforcement i/c Cutting, binding& bending etc.
49 Shuttering i/c shuttering & proping etc.
50 Concreting i/c compaction, curing etc. nos 1
51 Deshuttering i/c shifting of material to the other locat nos 1
52
53 Pile Cap for
Breacking Abutment
Pile A2
head, Excavation upto founding nos 1 21 22.12.13 to 11.01.14
54 level & P/L PCC, levelling bed etc. complete. nos 1
55 Reinforcement i/c Cutting, binding& bending etc.
56 Shuttering i/c shuttering & proping etc.
57 Concreting i/c compaction, curing etc.
58 Deshuttering i/c shifting of material to the other location
59 Pile Cap for Pier P7 21 23.01.14 to 12.02.14
60 Breacking Pile head, Excavation upto founding
level & P/L PCC, levelling bed etc. complete.
61 Reinforcement i/c Cutting, binding& bending etc.
62 Shuttering i/c shuttering & proping etc.
63 Concreting i/c compaction, curing etc.
64 Deshuttering i/c shifting of material to the other location
65 Pile Cap for Pier P6 21 24.02.14 to 16.03.14
66 Breacking Pile head, Excavation upto founding
level & P/L PCC, levelling bed etc. complete.
67 Reinforcement i/c Cutting, binding& bending etc.
68 Shuttering i/c shuttering & proping etc.
69 Concreting i/c compaction, curing etc.
70 Deshuttering i/c shifting of material to the other location
71 Pile Cap for Pier P5 21 27.03.14 to 16.04.14
72 Breacking Pile head, Excavation upto founding
level & P/L PCC, levelling bed etc. complete.
73 Reinforcement i/c Cutting, binding& bending etc.
74 Shuttering i/c shuttering & proping etc.
75 Concreting i/c compaction, curing etc.
76 Deshuttering i/c shifting of material to the other location
77
78 Concreting of Abutment A1 including Cap 15 12.01.14 to 27.01.14
79 Reinforcement i/c Cutting, binding& bending etc.
80 Shuttering i/c shuttering & proping etc.
81 Concreting i/c compaction, curing etc.
82 Deshuttering i/c shifting of material to the other location
83 Concreting of Pier P1 including Cap 15 13.02.14 to 28.02.2014
84 Reinforcement i/c Cutting, binding& bending etc.
85 Shuttering i/c shuttering & proping etc.
86 Concreting i/c compaction, curing etc.
87 Deshuttering i/c shifting of material to the other location
88 Concreting of Pier P2 including Cap 15 17.03.14 to 31.03.14
89 Reinforcement i/c Cutting, binding& bending etc.
90 Shuttering i/c shuttering & proping etc.
91 Concreting i/c compaction, curing etc.
92 Deshuttering i/c shifting of material to the other location
93 Concreting of Pier P3 including Cap 15 17.04.14 to 01.05.14
94 Reinforcement i/c Cutting, binding& bending etc.
95 Shuttering i/c shuttering & proping etc.
96 Concreting i/c compaction, curing etc.
97 Deshuttering i/c shifting of material to the other location
98 Concreting of Pier P4 including Cap 15 01.05.14 to 15.05.14
99 Reinforcement i/c Cutting, binding& bending etc.
100 Shuttering i/c shuttering & proping etc.
101 Concreting i/c compaction, curing etc.
102 Deshuttering i/c shifting of material to the other location
103 Concreting of Abutment A2 including Cap 15 12.01.14 to 27.01.14
104 Reinforcement i/c Cutting, binding& bending etc.
105 Shuttering i/c shuttering & proping etc.
106 Concreting i/c compaction, curing etc.
107 Deshuttering i/c shifting of material to the other location
108 Concreting of Pier P7 including Cap 15 13.02.14 to 28.02.2014
109 Reinforcement i/c Cutting, binding& bending etc.
110 Shuttering i/c shuttering & proping etc.
111 Concreting i/c compaction, curing etc.
112 Deshuttering i/c shifting of material to the other location
113 Concreting of Pier P6 including Cap 15 17.03.14 to 31.03.14
114 Reinforcement i/c Cutting, binding& bending etc.
115 Shuttering i/c shuttering & proping etc.
116 Concreting i/c compaction, curing etc.
117 Deshuttering i/c shifting of material to the other location
118 Concreting of Pier P5 including Cap 15 17.04.14 to 01.05.14
119 Reinforcement i/c Cutting, binding& bending etc.
120 Shuttering i/c shuttering & proping etc.
121 Concreting i/c compaction, curing etc.
122 Deshuttering i/c shifting of material to the other location
123
124 Concreting of Bearing Pedastal i/c Centring,
Shuttering, Proping & Deshuttering etc nos. 6
125 complete.
Abutment A1 no. 1 28.01.14
126 Pier P1 no. 1 29.02.14
127 Pier P2 no 1 01.04.14
128 Pier P3 no. 1 02.05.14
129 Pier P4 no. 1 16.05.14
130 Abutment A2 no. 1 28.01.14
131 Pier P7 no 1 29.02.14
132 Pier P6 no. 1 01.04.14
133 Pier P5 no. 1 02.05.14
134
135 Pre-casting of I-Beam on Casting Bed i/c
Prestressing, Shifting to the stacking bed &
erction thereof in nos 4
136 Span between Abutment A1- & Pier P1 including 45 01.01.14 to 15.02.14
137 Concreting i/c Shuttering, proping & reinforcement
i/c cutting, bending, binding etc.
138 Shifting of I-Beam from Casting Bed to Stacking Bed
139 Prestressing of I-Beam
140 Placing Elastomaric Bearings over Abutment & Pier
141 Erection of prestressed I-Beam in the respective Span
142
Span between Pier P1- & Pier P2 including 45 16.01.14 to 01.03.14
143 Concreting i/c Shuttering, proping & reinforcement
i/c cutting, bending, binding etc.
144 Shifting of I-Beam from Casting Bed to Stacking Bed
145 Prestressing of I-Beam
146 Placing Elastomaric Bearings over Abutment & Pier
147 Erection of prestressed I-Beam in the respective Span
148
Span between Pier P2- & Pier P3 including 45 31.01.14 to 17.03.14
149 Concreting i/c Shuttering, proping & reinforcement
i/c cutting, bending, binding etc.
150 Shifting of I-Beam from Casting Bed to Stacking Bed
151 Prestressing of I-Beam
152 Placing Elastomaric Bearings over Abutment & Pier
153 Erection of prestressed I-Beam in the respective Span
154
Span between Pier P3- & Pier P4 including 45 16.02.14 to 01.04.14
155 Concreting i/c Shuttering, proping & reinforcement
i/c cutting, bending, binding etc.
156 Shifting of I-Beam from Casting Bed to Stacking Bed
157 Prestressing of I-Beam
158 Placing Elastomaric Bearings over Abutment & Pier
159 Erection of prestressed I-Beam in the respective Span
160 Span between Abutment A2- & Pier P7 including 45 03.03.14 to 17.04.14
161 Concreting i/c Shuttering, proping & reinforcement
i/c cutting, bending, binding etc.
162 Shifting of I-Beam from Casting Bed to Stacking Bed
163 Prestressing of I-Beam
164 Placing Elastomaric Bearings over Abutment & Pie
165 Erection of prestressed I-Beam in the respective Span
166
Span between Pier P7- & Pier P6 including 45 18.03.14 to 01.05.14
167 Concreting i/c Shuttering, proping & reinforcement
i/c cutting, bending, binding etc.
168 Shifting of I-Beam from Casting Bed to Stacking Bed
169 Prestressing of I-Beam
170 Placing Elastomaric Bearings over Abutment & Pie
171 Erection of prestressed I-Beam in the respective Span
172
Span between Pier P6- & Pier P5 including 45 02.04.14 to 17.05.14
173 Concreting i/c Shuttering, proping & reinforcement
i/c cutting, bending, binding etc.
174 Shifting of I-Beam from Casting Bed to Stacking Bed
175 Prestressing of I-Beam
176 Placing Elastomaric Bearings over Abutment & Pie
177 Erection of prestressed I-Beam in the respective Span
178
Span between Pier P5- & Pier P4 including 45 17.04.14 to 01.06.14
179 Concreting i/c Shuttering, proping & reinforcement
i/c cutting, bending, binding etc.
180 Shifting of I-Beam from Casting Bed to Stacking Bed
181 Prestressing of I-Beam
182 Placing Elastomaric Bearings over Abutment & Pie
183 Erection of prestressed I-Beam in the respective Span
184
185 Concreting of Intermediate Cross Girders
186 Between Span Abutment A1 & Pier P1 including nos 15 21 16.02.14 to 08.03.14
187 Reinforcement i/c Cutting, binding& bending etc.
188 Shuttering i/c shuttering & proping etc.
189 Concreting i/c compaction, curing etc.
190 Deshuttering i/c shifting of material to the other location
191 Between Span Pier P1 & Pier P2 including nos 15 21 02.03.14 to 23.03.14
192 Reinforcement i/c Cutting, binding& bending etc.
193 Shuttering i/c shuttering & proping etc.
194 Concreting i/c compaction, curing etc.
195 Deshuttering i/c shifting of material to the other location
196 Between Span Pier P2 & Pier P3 including nos 15 21 18.03.14 to 08.04.14
197 Reinforcement i/c Cutting, binding& bending etc.
198 Shuttering i/c shuttering & proping etc.
199 Concreting i/c compaction, curing etc.
200 Deshuttering i/c shifting of material to the other location
201 Between Span Pier P3 & Pier P4 including nos 15 21 02.04.14 to 22.04.14
202 Reinforcement i/c Cutting, binding& bending etc.
203 Shuttering i/c shuttering & proping etc.
204 Concreting i/c compaction, curing etc.
205 Deshuttering i/c shifting of material to the other location
206 Between Span Abutment A2 & Pier P7 including
nos. 15 21 18.04.14 to 09.05.14
207 Reinforcement i/c Cutting, binding& bending etc.
208 Shuttering i/c shuttering & proping etc.
209 Concreting i/c compaction, curing etc.
210 Deshuttering i/c shifting of material to the other location
211 Between Span Pier P7 & Pier P6 including nos. 15 21 02.05.14 to 22.05.14
212 Reinforcement i/c Cutting, binding& bending etc.
213 Shuttering i/c shuttering & proping etc.
214 Concreting i/c compaction, curing etc.
215 Deshuttering i/c shifting of material to the other location
216 Between Span Pier P6 & Pier P5 including nos. 15 21 18.05.14 to 08.06.14
217 Reinforcement i/c Cutting, binding& bending etc.
218 Shuttering i/c shuttering & proping etc.
219 Concreting i/c compaction, curing etc.
220 Deshuttering i/c shifting of material to the other location
221 Between Span Pier P5 & Pier P4 including nos 15 21 02.06.14 to 22.06.14
222 Reinforcement i/c Cutting, binding& bending etc.
223 Shuttering i/c shuttering & proping etc.
224 Concreting i/c compaction, curing etc.
225 Deshuttering i/c shifting of material to the other location
226
227 Deck Slab Concreting cum
228 Of Span between Abutment A1 & Pier P1 including 10 05.03.14 to 15.03.14
229 Reinforcement i/c Cutting, bending & binding etc.
230 Shuttering i/c shuttering & proping etc.
231 Concreting i/c compaction, curing etc.
232 Deshuttering i/c shifting of material to the other location
233 Of Span between Pier P1 & Pier P2 including cum 10 20.03.14 to 30.03.14
234 Reinforcement i/c Cutting, bending & binding etc.
235 Shuttering i/c shuttering & proping etc.
236 Concreting i/c compaction, curing etc.
237 Deshuttering i/c shifting of material to the other location
238 Of Span between Pier P2 & Pier P3 including cum 10 05.04.14 to 15.04.14
239 Reinforcement i/c Cutting, bending & binding etc.
240 Shuttering i/c shuttering & proping etc.
241 Concreting i/c compaction, curing etc.
242 Deshuttering i/c shifting of material to the other location
243 Of Span between Pier P3 & Pier P4 including cum 10 19.04.14 to 29.04.14
244 Reinforcement i/c Cutting, bending & binding etc.
245 Shuttering i/c shuttering & proping etc.
246 Concreting i/c compaction, curing etc.
247 Deshuttering i/c shifting of material to the other location
248 Of Span between Abutment A2 & Pier P7 includin cum 10 06.05.14 to 16.05.14
249 Reinforcement i/c Cutting, bending & binding etc.
250 Shuttering i/c shuttering & proping etc.
251 Concreting i/c compaction, curing etc.
252 Deshuttering i/c shifting of material to the other location
253 Of Span between Pier P7 & Pier P6 including cum 10 19.05.14 to 29.05.14
254 Reinforcement i/c Cutting, bending & binding etc.
255 Shuttering i/c shuttering & proping etc.
256 Concreting i/c compaction, curing etc.
257 Deshuttering i/c shifting of material to the other location
258 Of Span between Pier P6 & Pier P5 including cum 10 05.06.14 to 15.06.14
259 Reinforcement i/c Cutting, bending & binding etc.
260 Shuttering i/c shuttering & proping etc.
261 Concreting i/c compaction, curing etc.
262 Deshuttering i/c shifting of material to the other location
263 Of Span between Pier P5 & Pier P4 including cum 10 19.06.14 to 29.06.14
264 Reinforcement i/c Cutting, bending & binding etc.
265 Shuttering i/c shuttering & proping etc.
266 Concreting i/c compaction, curing etc.
267 Deshuttering i/c shifting of material to the other location
268
269 Consolidation of Sub Grade i/c Levelling &
Dressing and placing PCC for Aproach Slab.
270 Bhangaha Side 10 15.04.14 to 25.04.14
271 Kanuali Side 10 01.05.14 to 15.05.14
272 Concreting of Approach slab i/c cutting,
bending, binding of Reinforcement, Providing &
Placing Centring & Shuttering i/c Proping &
Deshuttering etc. as required.

273 Bhangaha Side 7 26.04.14 to 03.05.14


274 Kanuali Side 7 16.05.14 to 22.05.14
275 Provding & Fixing Expansion Joint
276 Over Abutment A1 7 28.04.14 to 04.05.14
277 Over Pier P1 7 04.05.14 to 11.05.14
278 Over Pier P2 7 11.05.14 to 18.05.14
279 Over Pier P3 7 18.05.14 to 25.05.14
280 Over Abutment A2 7 25.05.14 to 31.05.14
281 Over Pier P7 7 31.05.14 to 06.06.14
282 Over Pier P6 7 06.06.14 to 13.06.14
283 Over Pier P5 7 13.06.14 to 20.06.14
284 Over Pier P4 7 20.06.14 to 27.06.14
285 Concreting of Crash Barrier & Footpath etc.
286 Unstream side Mtr. 180 50 15.04.14 to 04.06.14
287 Downstream side Mtr. 180 50 03.05.14 to 23.06.14
288 Bituminous work on Deck slab
289 DBC 7 27.06.14 to 04.07.14
290 Mastic 10 04.07.14 to 14.07.14
291 Misc. & Finishin Work
292 Rain water spout & down take pipe 15 01.06.14 to 15.06.14
293 GI Pipe Railing 15 26.05.14 to 10.06.14
294 Painting & Road Marking 4 15.07.14 to 19.07.14
295 Opening the Bridge for Traffic 1 20.07.14
der INDO-NEPAL Border Road Project for the Year 2012-13.

EXECUTION TIME
May-2014 June-2014 July-2014 July-2014 August-2014 September-2014 October-2014 November-2014 December-2014
Work: Construciton and Upgradation of Road and other structures from Phulwaria ghat at Lalbakiya River to Bahar (Bahera) Village in Sitamarhi District under INDO-NEPAL

Agreement No. 27/SBD/2012-13


Ageny: M/s Aarpee Infraprojects Pvt. Ltd. (M/s Rajesh Kumar Garg)
Programme of Work
Sl. EXECUTION
ACTIVITY UNIT QNTY
No. October-2013 November-2013 December-2013 January-2014 February-2014 March-2014 April-2014
1 Selection of Site for Casting Yard
Setting up Casting Yardincluding Cement Godown, Site
2 office, Site Lab i/c Fencing etc.
Job 1
3 Procurement of Shuttering material like MS Sheet,
Angle Iron, I Section, etc. Job 1
4 Fabrication of Shuttering
5 Pile Liner nos 6
6 Pile Cap
Size 900x1200 = 108.00 sqm
600x900 = 63.00 sqm sqm 208.80 01.10.13 to 31.10.13
300x1200 =21.60 sqm
300x900mm =16.20 sqm

7 Pier i/c Pier Cap set 1 01.10.13 to 31.10.13


8 Abutment i/c Cap set 1 01.10.13 to 31.10.13
9 I-Beams i/c intermediate cross Girders etc. set 3 15.11.13 to 14.12.13
10 Wing Wall, Retain Wall, Deck Slab, etc.
Size 900x1200 = 108.00 sqm
600x900 = 63.00 sqm
300x1200= 21.60 sqm
300x900mm= 16.20 sqn
sqm 400.00 01.11.13 to 30.11.13
11 Crash Barrier & Railing, Shuttering etc. = 5 mtr. Length set 1
12 Piling i/c setting out on ground, boring, using Bentonite
Slurry, Temporary liner, preparing Reinforcement Cage
i/c Cutting, Bending, Binding, Lowering the Case in the
Bore hole, concreting & Removal of Temp. Liner.

nos 88
13 Abutment 'A1' (Bhangaha Side) nos 12
14 Pile Cap Group Pier P1 nos 16
15 Pile Cap Group Pier P2 nos 16
16 Abutment 'A2' nos 12
17 Pile Cap Group Pier P3 nos 16
18 Pile Cap Group Pier P4 nos 16
19 Pile Cap for Abutment A1 no. 1
Excavation upto founding level & P/L PCC, levelling bed
etc. complete.
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
7 Pile Cap forupto
Excavation Abutment
founding A2level & P/L PCC, levelling bed nos 1
etc. complete. nos 1
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
8 Concreting of Abutment A1
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
9 Concreting of Abutment A2
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
Concreting of Bearing Pedastal i/c Centring, Shuttering
10 & Proping etc. nos. 6
Abutment A1 no. 1
Abutment A2 no. 1
11 Pre-casting of I-Beam on Casting Bed i/c Prestressing,
Shifting to the stacking bed & erction thereof in the
Span 'A1-A2' nos 4
Concreting i/c Shuttering, proping & reinforcement i/c
cutting, bending, binding etc.
Shifting of I-Beam from Casting Bed to Stacking Bed
Prestressing of I-Beam
Erection of prestressed I-Beam in the respective Span
12 Concreting of Intermediate Cross Girders of Span A1-
A2 nos 15
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
13 Deck Slab Concreting of Span A1-A2 cum
Reinforcement i/c Cutting, bending & binding etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
14 Concreting of Crash Barrier & Footpath
Unstream side Mtr. 180
Downstream side Mtr. 180
15 Bituminous work on Deck slab
DBC
Mastic
Fancing GI Pipe Railing
Painting & Road Marking
der INDO-NEPAL Border Road Project for the Year 2012-13.

EXECUTION TIME
May-2014 June-2014 July-2014 July-2014 August-2014 September-2014 October-2014 November-2014 December-2014
Work: Construciton and Upgradation of Road and other structures from Phulwaria ghat at Lalbakiya River to Bahar (Bahera) Village in Sitamarhi District under INDO-NEPAL
Agreement No. 27/SBD/2012-13
Ageny: M/s Aarpee Infraprojects Pvt. Ltd. (M/s Rajesh Kumar Garg)
Programme of Work
Sl. EXECUTION
ACTIVITY UNIT QNTY
No. October-2013 November-2013 December-2013 January-2014 February-2014 March-2014 April-2014
1 Selection of Site for Casting Yard
Setting up Casting Yard i.e. Cement Godown, Site
2 office, Site Lab i/c Fencing etc.
Job 1
3 Procurement of Shuttering material like MS Sheet,
Angle Iron, I Section, etc. Job 1
4 Fabrication of Shuttering
Pile Liner nos 4
Pile Cap (Size 900x1200, 600x900, 300x1200 &
300x900mm ) nos
Pier i/c Pier Cap set 1
Abutment i/c Cap set 1
I-Beams i/c intermediate cross Girders etc. set 3
Wing Wall, Retain Wall, Deck Slab, etc. (Size 900x1200,
600x900, 300x1200 & 300x900mm ) sqm 400.00
5 Piling i/c boring, using Bentonite Slurry, Temporary
liner, preparing Reinforcement Cage i/c Cutting,
Bending, Binding, Lowering the Case in the Bore hole,
concreting & Removal of Temp. Liner.

nos 88
Abutment 'A1' (Bhangaha Side) nos 12
Pile Cap Group Pier P1 nos 16
Pile Cap Group Pier P2 nos 16
Abutment 'A2' nos 12
Pile Cap Group Pier P3 nos 16
Pile Cap Group Pier P4 nos 16
6 Pile Cap for Abutment A1 no. 1
Excavation upto founding level & P/L PCC, levelling bed
etc. complete.
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
7 Pile Cap forupto
Excavation Abutment
founding A2level & P/L PCC, levelling bed nos 1
etc. complete. nos 1
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
8 Concreting of Abutment A1
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
9 Concreting of Abutment A2
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
Concreting of Bearing Pedastal i/c Centring, Shuttering
10 & Proping etc. nos. 6
Abutment A1 no. 1
Abutment A2 no. 1
11 Pre-casting of I-Beam on Casting Bed i/c Prestressing,
Shifting to the stacking bed & erction thereof in the
Span 'A1-A2' nos 4
Concreting i/c Shuttering, proping & reinforcement i/c
cutting, bending, binding etc.
Shifting of I-Beam from Casting Bed to Stacking Bed
Prestressing of I-Beam
Erection of prestressed I-Beam in the respective Span
12 Concreting of Intermediate Cross Girders of Span A1-
A2 nos 15
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
13 Deck Slab Concreting of Span A1-A2 cum
Reinforcement i/c Cutting, bending & binding etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
14 Concreting of Crash Barrier & Footpath
Unstream side Mtr. 180
Downstream side Mtr. 180
15 Bituminous work on Deck slab
DBC
Mastic
Fancing GI Pipe Railing
Painting & Road Marking
der INDO-NEPAL Border Road Project for the Year 2012-13.

EXECUTION TIME
May-2014 June-2014 July-2014 July-2014 August-2014 September-2014 October-2014 November-2014 December-2014

Você também pode gostar