Você está na página 1de 46

Safety Guidelines for Design,

Construction and Operation of Tugs

July 2014

Guidance Note
NI 617 DT R00 E

Marine & Offshore Division


92571 Neuilly sur Seine Cedex France
Tel: + 33 (0)1 55 24 70 00 Fax: + 33 (0)1 55 24 70 25
Marine website: http://www.veristar.com
Email: veristarinfo@bureauveritas.com
2014 Bureau Veritas - All rights reserved
MARINE & OFFSHORE DIVISION
GENERAL CONDITIONS

ARTICLE 1 ARTICLE 6
1.1. - BUREAU VERITAS is a Society the purpose of whose Marine & Offshore Division (the "Society") is 6.1. - The Society accepts no responsibility for the use of information related to its Services which was not
the classification (" Classification ") of any ship or vessel or offshore unit or structure of any type or part of provided for the purpose by the Society or with its assistance.
it or system therein collectively hereinafter referred to as a "Unit" whether linked to shore, river bed or sea 6.2. - If the Services of the Society or their omission cause to the Client a damage which is proved
bed or not, whether operated or located at sea or in inland waters or partly on land, including submarines, to be the direct and reasonably foreseeable consequence of an error or omission of the Society,
hovercrafts, drilling rigs, offshore installations of any type and of any purpose, their related and ancillary its liability towards the Client is limited to ten times the amount of fee paid for the Service having
equipment, subsea or not, such as well head and pipelines, mooring legs and mooring points or otherwise caused the damage, provided however that this limit shall be subject to a minimum of eight thou-
as decided by the Society. sand (8,000) Euro, and to a maximum which is the greater of eight hundred thousand (800,000)
The Society: Euro and one and a half times the above mentioned fee. These limits apply regardless of fault in-
"prepares and publishes Rules for classification, Guidance Notes and other documents (" Rules "); cluding breach of contract, breach of warranty, tort, strict liability, breach of statute, etc.
"issues Certificates, Attestations and Reports following its interventions (" Certificates "); The Society bears no liability for indirect or consequential loss whether arising naturally or not as
a consequence of the Services or their omission such as loss of revenue, loss of profit, loss of pro-
"publishes Registers.
duction, loss relative to other contracts and indemnities for termination of other agreements.
1.2. - The Society also participates in the application of National and International Regulations or Stand-
6.3. - All claims are to be presented to the Society in writing within three months of the date when the Serv-
ards, in particular by delegation from different Governments. Those activities are hereafter collectively re-
ices were supplied or (if later) the date when the events which are relied on of were first known to the Client,
ferred to as " Certification ".
and any claim which is not so presented shall be deemed waived and absolutely barred. Time is to be in-
1.3. - The Society can also provide services related to Classification and Certification such as ship and terrupted thereafter with the same periodicity.
company safety management certification; ship and port security certification, training activities; all activi-
ARTICLE 7
ties and duties incidental thereto such as documentation on any supporting means, software, instrumen-
tation, measurements, tests and trials on board. 7.1. - Requests for Services are to be in writing.
1.4. - The interventions mentioned in 1.1., 1.2. and 1.3. are referred to as " Services ". The party and/or its 7.2. - Either the Client or the Society can terminate as of right the requested Services after giving
representative requesting the services is hereinafter referred to as the " Client ". The Services are pre- the other party thirty days' written notice, for convenience, and without prejudice to the provisions
pared and carried out on the assumption that the Clients are aware of the International Maritime in Article 8 hereunder.
and/or Offshore Industry (the "Industry") practices. 7.3. - The class granted to the concerned Units and the previously issued certificates remain valid until the
1.5. - The Society is neither and may not be considered as an Underwriter, Broker in ship's sale or char- date of effect of the notice issued according to 7.2. here above subject to compliance with 2.3. here above
tering, Expert in Unit's valuation, Consulting Engineer, Controller, Naval Architect, Manufacturer, Ship- and Article 8 hereunder.
builder, Repair yard, Charterer or Shipowner who are not relieved of any of their expressed or implied 7.4. - The contract for classification and/or certification of a Unit cannot be transferred neither assigned.
obligations by the interventions of the Society. ARTICLE 8
ARTICLE 2 8.1. - The Services of the Society, whether completed or not, involve, for the part carried out, the payment
2.1. - Classification is the appraisement given by the Society for its Client, at a certain date, following sur- of fee upon receipt of the invoice and the reimbursement of the expenses incurred.
veys by its Surveyors along the lines specified in Articles 3 and 4 hereafter on the level of compliance of 8.2. - Overdue amounts are increased as of right by interest in accordance with the applicable leg-
a Unit to its Rules or part of them. This appraisement is represented by a class entered on the Certificates islation.
and periodically transcribed in the Society's Register.
8.3. - The class of a Unit may be suspended in the event of non-payment of fee after a first unfruitful
2.2. - Certification is carried out by the Society along the same lines as set out in Articles 3 and 4 hereafter notification to pay.
and with reference to the applicable National and International Regulations or Standards.
ARTICLE 9
2.3. - It is incumbent upon the Client to maintain the condition of the Unit after surveys, to present
9.1. - The documents and data provided to or prepared by the Society for its Services, and the information
the Unit for surveys and to inform the Society without delay of circumstances which may affect the
available to the Society, are treated as confidential. However:
given appraisement or cause to modify its scope.
"Clients have access to the data they have provided to the Society and, during the period of classifica-
2.4. - The Client is to give to the Society all access and information necessary for the safe and efficient
tion of the Unit for them, to the classification file consisting of survey reports and certificates which
performance of the requested Services. The Client is the sole responsible for the conditions of presenta-
have been prepared at any time by the Society for the classification of the Unit ;
tion of the Unit for tests, trials and surveys and the conditions under which tests and trials are carried out.
"copy of the documents made available for the classification of the Unit and of available survey reports
ARTICLE 3
can be handed over to another Classification Society, where appropriate, in case of the Unit's transfer
3.1. - The Rules, procedures and instructions of the Society take into account at the date of their of class;
preparation the state of currently available and proven technical knowledge of the Industry. They
"the data relative to the evolution of the Register, to the class suspension and to the survey status of
are a collection of minimum requirements but not a standard or a code of construction neither a
the Units, as well as general technical information related to hull and equipment damages, may be
guide for maintenance, a safety handbook or a guide of professional practices, all of which are
passed on to IACS (International Association of Classification Societies) according to the association
assumed to be known in detail and carefully followed at all times by the Client.
working rules;
Committees consisting of personalities from the Industry contribute to the development of those docu-
"the certificates, documents and information relative to the Units classed with the Society may be
ments.
reviewed during certificating bodies audits and are disclosed upon order of the concerned governmen-
3.2. - The Society only is qualified to apply its Rules and to interpret them. Any reference to them tal or inter-governmental authorities or of a Court having jurisdiction.
has no effect unless it involves the Society's intervention.
The documents and data are subject to a file management plan.
3.3. - The Services of the Society are carried out by professional Surveyors according to the applicable
ARTICLE 10
Rules and to the Code of Ethics of the Society. Surveyors have authority to decide locally on matters re-
lated to classification and certification of the Units, unless the Rules provide otherwise. 10.1. - Any delay or shortcoming in the performance of its Services by the Society arising from an event
not reasonably foreseeable by or beyond the control of the Society shall be deemed not to be a breach of
3.4. - The operations of the Society in providing its Services are exclusively conducted by way of ran-
contract.
dom inspections and do not in any circumstances involve monitoring or exhaustive verification.
ARTICLE 11
ARTICLE 4
11.1. - In case of diverging opinions during surveys between the Client and the Society's surveyor, the So-
4.1. - The Society, acting by reference to its Rules:
ciety may designate another of its surveyors at the request of the Client.
"reviews the construction arrangements of the Units as shown on the documents presented by the Cli-
11.2. - Disagreements of a technical nature between the Client and the Society can be submitted by the
ent;
Society to the advice of its Marine Advisory Committee.
"conducts surveys at the place of their construction;
ARTICLE 12
"classes Units and enters their class in its Register;
12.1. - Disputes over the Services carried out by delegation of Governments are assessed within the
"surveys periodically the Units in service to note that the requirements for the maintenance of class are framework of the applicable agreements with the States, international Conventions and national rules.
met.
12.2. - Disputes arising out of the payment of the Society's invoices by the Client are submitted to the Court
The Client is to inform the Society without delay of circumstances which may cause the date or the of Nanterre, France, or to another Court as deemed fit by the Society.
extent of the surveys to be changed.
12.3. - Other disputes over the present General Conditions or over the Services of the Society are
ARTICLE 5 exclusively submitted to arbitration, by three arbitrators, in London according to the Arbitration
5.1. - The Society acts as a provider of services. This cannot be construed as an obligation bearing Act 1996 or any statutory modification or re-enactment thereof. The contract between the Society
on the Society to obtain a result or as a warranty. and the Client shall be governed by English law.
5.2. - The certificates issued by the Society pursuant to 5.1. here above are a statement on the level ARTICLE 13
of compliance of the Unit to its Rules or to the documents of reference for the Services provided for. 13.1. - These General Conditions constitute the sole contractual obligations binding together the
In particular, the Society does not engage in any work relating to the design, building, production Society and the Client, to the exclusion of all other representation, statements, terms, conditions
or repair checks, neither in the operation of the Units or in their trade, neither in any advisory serv- whether express or implied. They may be varied in writing by mutual agreement. They are not var-
ices, and cannot be held liable on those accounts. Its certificates cannot be construed as an im- ied by any purchase order or other document of the Client serving similar purpose.
plied or express warranty of safety, fitness for the purpose, seaworthiness of the Unit or of its value 13.2. - The invalidity of one or more stipulations of the present General Conditions does not affect the va-
for sale, insurance or chartering. lidity of the remaining provisions.
5.3. - The Society does not declare the acceptance or commissioning of a Unit, nor of its construc- 13.3. - The definitions herein take precedence over any definitions serving the same purpose which may
tion in conformity with its design, that being the exclusive responsibility of its owner or builder. appear in other documents issued by the Society.
5.4. - The Services of the Society cannot create any obligation bearing on the Society or constitute any
warranty of proper operation, beyond any representation set forth in the Rules, of any Unit, equipment or BV Mod. Ad. ME 545 L - 7 January 2013
machinery, computer software of any sort or other comparable concepts that has been subject to any sur-
vey by the Society.
GUIDANCE NOTE NI 617

NI 617
Safety Guidelines for Design,
Construction and Operation of Tugs

SECTION 1 GENERAL

SECTION 2 STABILITY

SECTION 3 TOWING EQUIPMENT

SECTION 4 FIRE SAFETY FOR TUGS OF LESS THAN 500 GT

SECTION 5 LIFE SAVING APPLIANCES FOR TUGS OF LESS THAN 500 GT

SECTION 6 RADIO INSTALLATIONS FOR TUGS OF LESS THAN 300 GT

SECTION 7 NAVIGATION EQUIPMENT FOR TUGS OF LESS THAN 500 GT


SECTION 8 HULL OUTFITTING

SECTION 9 ASSISTED SHIP

July 2014
Section 1 General
1 Foreword 7
1.1
2 Introduction 7
2.1 General
2.2 Typical operational profiles
2.3 Typical design arrangements
2.4 Other design arrangements
3 General 8
3.1 Scope of application
3.2 Service notations and additional service feature
3.3 Specific considerations for escort tugs
4 Definitions 10
4.1 Bollard Pull
4.2 Escort forces and speed
4.3 Reference towline force
4.4 Design Load
4.5 Winch Brake Holding Load
4.6 Towline breaking strength

Section 2 Stability
1 General 12
1.1 Scope of application
2 Openings 12
2.1 General
2.2 Ventilation openings of machinery space and emergency generator room
3 Intact stability 12
3.1 Loading conditions
3.2 Stability criteria
3.3 Additional stability criteria for service notations harbour tug and tug
3.4 Additional stability criteria for service notation escort tug
3.5 Escort performance simulations
3.6 Escort performance trials
3.7 Operating information for service notation escort tug
3.8 Icing considerations
3.9 Elements reducing stability
3.10 Alterations

Section 3 Towing Equipment


1 Towing equipment for service notations harbour tug and tug 18
1.1 General
1.2 Documents to be submitted
1.3 Design Load
1.4 Design requirements for towing winches
1.5 Design requirements for towing hooks
1.6 Design requirements for towlines

2 Bureau Veritas July 2014


1.7 Design requirements for towline guiding fittings
1.8 Design requirements for towing equipment supporting structures
1.9 Fendering
1.10 Testing requirements
2 Towing equipment for service notation escort tug 21
2.1 General
2.2 Documents to be submitted
2.3 Design Load
2.4 Design requirements for escort winches
2.5 Design requirements for towlines
2.6 Design requirements for towline guiding fittings
2.7 Design requirements for towing equipment supporting structures
2.8 Testing requirements
2.9 Inclinometer

Section 4 Fire Safety for Tugs of less than 500 GT


1 General 25
1.1 Scope of application
1.2 Fire safety objectives
1.3 Requirements for fire safety equipment
2 Fire pumps and fire main systems 25
2.1 Purpose
2.2 Capacity
2.3 Fire pumps
2.4 Portable fire pumps
2.5 Fire main
2.6 Pressure in the fire main
2.7 Fire Hydrants
2.8 Fire-hoses
2.9 Nozzles
3 Fire safety measures 28
3.1 Purpose
3.2 Structural fire protection
3.3 Materials
3.4 Surface of insulation
3.5 Ventilation systems
3.6 Oil fuel arrangements
3.7 Special arrangements in Category A machinery spaces and where necessary
other machinery spaces
3.8 Arrangements for gaseous fuel for domestic purposes
3.9 Space heating
3.10 Means of escape
4 Fixed fire detection and fire-alarm systems 31
4.1 General
5 Fire-extinguishing arrangements 31
5.1 Purpose
5.2 Fixed fire-extinguishing arrangements in Category A machinery spaces
5.3 Fixed fire-extinguishing systems
5.4 Protection of paint lockers and flammable liquid lockers
5.5 Fixed fire-extinguishing systems not required by this section
5.6 Portable Fire-extinguishers

July 2014 Bureau Veritas 3


6 Fire-fighting equipment 32
6.1 General
6.2 Fire-fighters outfit (which includes an axe)
6.3 Description of fire control plans
7 Alternative design and arrangements for fire safety 32
7.1 Purpose
7.2 General
7.3 Engineering analysis
7.4 Evaluation of the alternative design and arrangements
7.5 Re-evaluation due to change of conditions

Section 5 Life Saving Appliances for Tugs of less than 500 GT

1 General 34
1.1 Scope of application
1.2 Requirements for life saving appliances

Section 6 Radio Installations for Tugs of less than 300 GT

1 General 36
1.1 Scope of application
1.2 Requirements for radio installations

Section 7 Navigation Equipment for Tugs of less than 500 GT

1 General 37
1.1 Scope of application
1.2 Requirements for navigation equipment

Section 8 Hull Outfitting

1 Anchoring equipment 38
1.1 Equipment number
1.2 Wire ropes
1.3 Tugs of less than 500 GT
1.4 Number of anchors
1.5 Anchors
1.6 High holding power anchors
1.7 Chain cables
1.8 Water depths greater than 82,5 m

4 Bureau Veritas July 2014


Section 9 Assisted Ship

1 Towing fittings 43
1.1 General
2 Side structure 43
2.1 General
3 Making fast 44
3.1 General

July 2014 Bureau Veritas 5


6 Bureau Veritas July 2014
NI 617, Sec 1

SECTION 1 GENERAL

1 Foreword 2.1.4 A general and indicative description of typical tug


design arrangements for towing and pushing operations is
provided in [2.3]. It is recognised that other, specialised tug
1.1 design arrangements exist in addition to the ones specified
in [2.3]. The guidelines are applicable to the specific design
1.1.1 This Guidance Note has been developed on the basis arrangements mentioned in [2.3.1], [2.3.2] and [2.3.3], but
of cooperative research and development work performed may also be applied to other design arrangements, as far as
deemed reasonable and practicable (refer to [2.4]).
within the scope of the SafeTug Joint Industry Project and
through bilateral cooperation with industry stakeholders.
2.2 Typical operational profiles
The purpose of the Guidance Note is to provide recom-
mended criteria for the design, construction and operation
of tugs. 2.2.1 Harbour tugs
Harbour tugs are considered to be tugs specially equipped
The recommended criteria are to be used in conjunction
to assist ships and/or floating offshore units while entering
with the Bureau Veritas Rules for The Classification of Steel or leaving port and during berthing and unberthing opera-
Ships (NR 467) and may be applied as an alternative to tions. Harbour tugs are considered to navigate in calm
and/or in addition to the requirements of NR 467, Pt D, stretches of water (sheltered area). Usually harbour tugs
Ch 14 as applicable for the service notations tug and escort work from a fixed port; the crew is familiar with the operat-
tug defined in NR 467, Pt A, Ch 1, Sec 2. ing area and shore side facilities for maintenance, repairs,
spare parts, etc., are directly available. In case of emergency
Application of the recommended criteria of this Guidance shore side assistance is directly available.
Note as alternative to the requirements of NR 467, Pt D, Ch 14
is subject to agreement by the Society on a case by case basis.
2.2.2 Seagoing tugs
Seagoing tugs are considered to be tugs specially equipped
2 Introduction to assist ships and/or floating offshore units at sea, but may
also be involved in harbour towage operations. Seagoing
tugs can either operate without any restriction (deep sea
2.1 General towage, in any sea area and any period of the year), within
short distance from shore (coastal towage), or at a specified
2.1.1 Tugs are considered to be ships specially equipped location (offshore terminal tugs). Salvage tugs are consid-
for towing and/or pushing other (generally larger) ships ered as seagoing tugs having specific equipment for salvage
and/or floating offshore units. Both the tasks assigned to operations.
tugs as well as the operational profiles show a broad varia-
tion. Therefore, differences between tugs can be very signif- For coastal towage and offshore terminal tugs the crew is
icant in terms of general arrangement design, hull lines, considered to be generally familiar with the operating area
and shore side facilities for maintenance, repairs, spare
structural reinforcements, machinery and electrical systems,
parts, etc., are readily available. It is also considered that in
deck and towing equipment and safety systems.
case of emergency shore side assistance is readily available
if the tug does not proceed in the course of the voyage more
2.1.2 In order to provide the industry with adequate guide- than four hours at operational speed from a place of safe
lines and rules, the class requirements for tugs should take sheltered anchorage.
this variation into account. A logical way of doing so is to
define a set of different service notations for tugs, which For deep sea towage the crew is not necessarily familiar
reflect the nature of operation of the tug as well as the opera- with the operating area and shore side facilities for mainte-
tional profile. The class requirements for each type of tug are nance, repairs, spare parts, etc., are generally not readily
then defined as a function of the selected service notation. available. It is also considered that in case of emergency
shore side assistance is not readily available.
2.1.3 An overview of typical operational profiles for which Salvage tugs, due to the nature of their operations, are to be
tugs are designed and equipped is provided in [2.2]. The able to operate fully autonomously under all conditions.
operational profile is to be considered as a combination of Consequently, even if the crew may be familiar with the
the function (type of operation) and service (operating area) operating area, it is considered that shore side facilities and
of the tug. emergency assistance are not readily available.

July 2014 Bureau Veritas 7


NI 617, Sec 1

2.2.3 Escort tugs 2.4 Other design arrangements


Escort tugs are considered to be tugs specially equipped for
2.4.1 Other tug design arrangements, having towing and
escorting ships during navigation. Escorting is considered to
propulsion configurations different from the design arrange-
include active (emergency) steering, braking and otherwise
ments described in [2.3.1], [2.3.2] and [2.3.3], have been
controlling of the assisted ship while approaching a port or developed and built:
terminal, or, while navigating in confined waters. Typically
escorting involves indirect towage at speeds in excess of Reference is made to tugs, other than the tractor tugs
6 kn. Escort tugs are considered to operate in open sea and ASD tugs as described in [2.3.2] and [2.3.3],
areas and/or in sheltered (confined) waters (e.g. in ports). respectively, which are equipped with omnidirectional
thrusters installed at a single location along the length,
If escort tugs operate from a fixed station, the crew is gener- effectively mixing the characteristics of both design con-
ally familiar with the operating area and shore side facilities cepts.
for maintenance, repairs, spare parts, etc. are readily availa- The guidelines provide specific recommendations
ble. It is considered that in case of emergency shore side regarding the anticipated effective towline forces acting
assistance is readily available if the escort tug does not pro- in the transverse direction and the associated heeling
ceed in the course of the voyage more than four hours at moments in relation to the towing and/or escorting sta-
operational speed from a place of safe sheltered anchorage. bility requirements.
Reference is also made to tugs which are equipped with
2.3 Typical design arrangements multiple omnidirectional thrusters distributed along the
length. Such tugs have the capability to generate rela-
tively high transverse thrust compared to tugs with
2.3.1 Conventional tugs omnidirectional thrusters installed at a single location
Conventional tugs have fixed single or multiple shaft along the length described above.
arrangement. The propeller(s) can be of fixed pitch or con- This aspect needs to be specially considered when
trollable pitch type, normally fitted with Kort nozzle(s). applying these Guidelines. Particular attention is to be
Steering is done by means of rudder(s) or steerable noz- paid to the anticipated effective towline forces acting in
zle(s). The towing point is normally located slightly aft of the transverse direction and the associated heeling
the centre of lateral resistance for towing over the stern with moments in relation to the towing and/or escorting sta-
a towing hook and/or towing winch. bility requirements.

Conventional tugs may also be equipped to perform push-


ing operations.
3 General

2.3.2 Tractor tugs 3.1 Scope of application


Tractor tugs are fitted with omnidirectional thrusters (typi- 3.1.1 These Guidelines is applicable to tugs having a (free-
cally two steerable propellers or Voith-Schneider type board) length LLL, as defined in the International Convention
cycloidal propulsion units), which are located forward of on Load Lines (ICLL) in force, of not more than 100 m and
the towing point (usually not more than 30% of the length to which one or more of the service notations specified in
from the forward end). A skeg or vertical fin is fitted aft. [3.2] are assigned.
Towing is performed over the stern with a towing winch
and/or towing hook. 3.1.2 These Guidelines may also be applied to other ships
engaged in towing, such as anchor handling tugs, anchor
Tractor tugs may also be equipped to perform pushing oper- handling tug supply vessels, salvage tugs and standby res-
ations. cue vessels, as far as deemed practicable by the Society.

2.3.3 Azimuth Stern Drive tugs 3.2 Service notations and additional service
Azimuth Stern Drive (ASD) tugs are fitted with multiple feature
steerable propellers located near the aft end. Typically, ASD
tugs can perform towing operations over the bow with the 3.2.1 On the basis of the typical operational profiles of
forward towing winch (towing operation similar to a tractor tugs, as described in [2.2], the following service notations
tug) and over the stern with a towing hook and/or second are defined:
towing winch (towing operation similar to a conventional harbour tug for tugs specially equipped for towing
tug). In both cases the towing point is located forward of the and/or pushing within the limits of a port,
thrusters. ASD tugs may be fitted with a skeg, the size and
tug for tugs specially equipped for towing and/or push-
location depending on the intended function). ing at sea, as well as in port
Azimuth Stern Drive tugs may also be equipped to perform escort tug for tugs specially equipped for escorting ships
pushing operations. during navigation.

8 Bureau Veritas July 2014


NI 617, Sec 1

3.2.2 The service notations harbour tug and tug are to be hydrodynamic lift and drag forces acting on the hull and
completed by the design performance limit as follows: appendices of the tug advancing through the water at a drift
(Bollard Pull = [TBP/9,81] t) angle relative to the water flow, the thrust vector and the
towline force.
where TBP is defined in [4.1.1].
Note 1: In direct towing mode the trust is directly applied to gener-
Example: tug (Bollard Pull = 60 t) ate the towline force, whereby hydrodynamic lift and drag forces
play no significant role.
3.2.3 The service notation escort tug is to be completed by
the design performance limits as follows: 3.3.3 Escort tugs may work in different indirect towing
(maximum steering force = [TY,MAX/9,81] t, maximum modes, depending on the required action towards the
braking force = [TX,MAX/9.81] t, maximum escort speed escorted ship (e.g. steering, braking). The main indirect tow-
= [Vmax] kn) ing modes relevant for escort tugs are schematically shown
in Fig 1.
where TY,MAX and TX,MAX are defined in [4.2.6], while VMAX is
Where reference is made to indirect steering the objective
defined in [4.2.4].
is to maximise the steering force in indirect towing mode.
Example: escort tug (maximum steering force = 65 t, maxi-
Where reference is made to indirect braking the objective
mum braking force = 90 t, maximum escort speed = 10 kn)
is to maximise the braking force in indirect towing mode.
3.2.4 The service notations tug and escort tug may be
completed by the following additional service feature: 3.3.4 In (basic) indirect mode the towline force is gener-
ated primarily by the hydrodynamic forces acting on the
sailing time 4 h from a safe sheltered anchorage
hull and skeg, with the thrust used solely to maintain the
for tugs which do not proceed in the course of their voyage desired drift angle (also referred to as yaw angle).
more than four hours at operational speed from a place of
refuge. 3.3.5 In powered indirect mode (indirect steering) the
transverse component of thrust is used to maintain the
3.2.5 Multiple service notations may be assigned. desired drift angle, while a significant longitudinal compo-
nent of thrust is applied in forward direction of the tug.
3.3 Specific considerations for escort tugs Compared to the (basic) indirect mode, the tug is operating
more sideways of the escorted ship with a relatively large
3.3.1 For the purpose of these Guidelines escorting is con- towline angle, generating a higher steering force.
sidered to include active (emergency) steering, braking and
otherwise controlling of the escorted ship by the tug operat- 3.3.6 In combination mode (indirect braking) the same
ing in indirect towing mode, whereby the ahead speed of principle as for the indirect steering mode is applied, except
the escorted ship is within a typical speed range of 6 to that the longitudinal component of thrust is applied in aft-
10 kn. ward rather than forward direction.
3.3.2 In indirect towing mode the towline force is the Compared to the (basic) indirect mode, the tug is operating
resulting from the (quasi-static) equilibrium condition more behind the escorted ship with a relatively small tow-
reached between the forces and moments arising from the line angle, generating a higher braking force.

Figure 1 : Schematic overview of indirect towing modes (escort tug)

July 2014 Bureau Veritas 9


NI 617, Sec 1

3.3.7 For indirect towing modes it is recommended to Figure 2 : Typical escort configuration
design the tug to generate high (indirect) towline forces with
minimal propulsion thrust, while respecting the limits
imposed by stability and strength considerations (towing
equipment, general hull structure).

3.3.8 The propulsion engines are to ensure sufficient thrust


for manoeuvring the tug quickly for any drift angle (refer to
angle as defined in [4.2.2]).

3.3.9 In the case of loss of propulsion, the heeling moment


due to the remaining forces is to lead to a safe equilibrium
position of the tug with reduced heeling angle.

4 Definitions

4.1 Bollard Pull

4.1.1 The Bollard Pull TBP, in kN, is the maximum sustained 4.2.2 The following angles are defined in relation to escort
towline force the tug is capable of generating at zero for- operations (see Fig 2):
ward speed, to be initially specified by the Designer and to
The towline angle , in deg, is the angle between the
be verified by a full scale test, generally referred to as Bol-
towline and the centreline of the escorted ship, and
lard Pull test.
The drift angle , in deg, is the angle between the cen-
4.1.2 The Bollard Pull is to be verified by means of a Bol- treline of the tug and the centreline of the escorted ship
lard Pull test performed in accordance with a recognised (also referred to as yaw angle).
standard.
4.2.3 The steady towline force TESC can be decomposed
For tugs capable of towing over the stern (ahead towing) as into a steering force TY and a braking force TX (see Fig 2):
well as over the bow (astern towing), the Bollard Pull test is
to be performed for towing over the stern (ahead towing) The steering force TY, in kN, is the transverse compo-
and for towing over the bow (astern towing). nent of the steady towline force TESC with respect to the
escorted ship
The maximum measured Bollard Pull is to be referenced in
the service notation, see [3.2]. The braking force TX, in kN, is the longitudinal compo-
nent of the steady towline force TESC with respect to the
4.1.3 Where the value of the Bollard Pull is not provided, escorted ship.
the following default values may be used for preliminary
design review: 4.2.4 The maximum escort speed VMAX, in kn, is the highest
escort speed V for which the escort tug is considered to per-
TBP = 0,204 N PS form escort operations, to be specified by the Designer and
for conventional tugs with propellers fitted with nozzles; not to be taken higher than 10 kn.
Note 1: For high powered escort tugs with a free running speed of
TBP = 0,176 N PS more than 15 kn the Society may, on a case-by-case basis, accept a
for tractor tugs and ASD tugs with steerable propellers maximum escort speed of 12 kn.
fitted with nozzles.
4.2.5 For the purpose of these Guidelines the following
where: rated values of the above defined escort forces are speci-
fied:
N : Number of propellers
The rated steady towline force TESC,R, in kN, is the high-
PS : Maximum continuous power per propeller est anticipated steady towline force TESC, as obtained
shaft, in kW. from the evaluation of the escort forces for a particular
loading condition and escort speed, taking into account
4.2 Escort forces and speed the applicable stability and strength criteria of these
Guidelines
4.2.1 The steady towline force during escorting, TESC, in kN, The rated steering force TY,R, in kN, is the m highest
is the towline force associated with the considered (quasi- anticipated steering force TY, as obtained from the eval-
static) equilibrium in indirect towing mode, excluding short uation of the escort forces for a particular loading condi-
time-duration dynamic effects, for a given loading condition tion and escort speed, taking into account the
and escort speed V, see Fig 2. The steady towline force is applicable stability and strength criteria of these Guide-
applied by the tug on the stern of the escorted ship. lines

10 Bureau Veritas July 2014


NI 617, Sec 1

The rated maximum braking force TX,R, in kN, is the 4.3 Reference towline force
highest anticipated braking force TX, as obtained from
the evaluation of the escort forces for a particular load- 4.3.1 The reference (quasi-static) towline force T, in kN, is
ing condition and escort speed, taking into account the considered to represent:
applicable stability and strength criteria of these Guide-
the Bollard Pull TBP for service notations harbour tug
lines.
and tug, see [4.1]
4.2.6 For the purpose of these Guidelines the following the maximum steady towline force TESC,MAX for service
maximum values of the above defined rated escort forces notation escort tug, see [4.2].
are specified:
The maximum steady towline force TESC,MAX, in kN, is the
4.4 Design Load
highest rated steady towline force TESC,R over the appli-
cable range of loading conditions and escort speeds
4.4.1 The Design Load DL, in kN, is the force taken into
The maximum steering force TY,MAX, in kN, is the m high- consideration for the strength assessment and testing of the
est rated steering force TY,R over the applicable range of towing equipment and the associated supporting structures,
loading conditions and escort speeds and is to be taken as not less than:
The maximum braking force TX,MAX, in kN, is the m high- DL = DAF T
est rated braking force TX,R over the applicable range of
loading conditions and escort speeds. where,
DAF : Dynamic Amplification Factor
4.2.7 The matrix of rated steady towline forces TESC,R, steer-
ing forces TY,R and braking forces TX,R is to be initially speci- The DAF takes into consideration dynamic effects. Refer-
fied by the Designer and to be verified by the Society on the ence values for the DAF are given in Sec 3, [1.3] for service
basis of the results of: notations harbour tug and tug, and in Sec 3, [2.3] for serv-
full scale trials, or ice notation escort tug.
model testing, or
a computer simulation programme accepted by the 4.5 Winch Brake Holding Load
Society.
4.5.1 The winch Brake Holding Load BHL, in kN, is the
4.2.8 Full scale trials, where applicable, should be per- maximum towline force the towing winch can withstand
formed in accordance with a procedure agreed with the without slipping of the (activated) brake, considering the
Society before prior to commencement of the trials and towline at the first layer.
comply with the requirements of Sec 2, [3.6].
4.5.2 The BHL is a reference for the strength assessment
4.2.9 Model testing, where applicable, should be per- and testing of towing winches and associated towing fittings
formed in accordance with a procedure agreed with the (e.g. fairlead, staple, gob-eye) as well as their supporting
Society before prior to commencement of the tests and structures.
comply with the requirements of Sec 2, [3.6]. Special atten-
tion is to be paid to scale effects when processing the meas-
urement result to create predictions at full scale. 4.6 Towline breaking strength

4.2.10 Computer simulation programmes for predicting 4.6.1 The towline breaking strength, in kN, is the tension
escort performance are to comply with the requirements of required to cause failure of the towline (parting of the tow-
Sec 2, [3.5]. line).

July 2014 Bureau Veritas 11


NI 617, Sec 2

SECTION 2 STABILITY

1 General 3 Intact stability

1.1 Scope of application 3.1 Loading conditions


1.1.1 All tugs having a Load Line length LLL equal to or 3.1.1 Standard loading conditions
greater than 24 m may be assigned class only after it has
Standard loading conditions are to be included in the stabil-
been demonstrated that their intact stability is adequate.
ity booklet:
Adequate intact stability means compliance with standards
laid down by the relevant Administration or with the lightship condition
requirements specified in this section taking into account tug in lightest anticipated loading condition, with full
the tugs size and type. stores and fuel
In any case, the level of intact stability is not to be less than same condition as above, but with 10% stores, provi-
that provided by the Guidelines. sions and consumables

1.1.2 The Guidelines also apply to tugs with a load line tug in the departure condition at the waterline corre-
length LLL of less than 24 m in length. sponding to the maximum draught, with full stores, pro-
visions and consumables

2 Openings same condition as above, but with 10% stores, provi-


sions and consumables.

2.1 General For the lightship condition, not being an operational load-
ing condition, the Society may accept that part of the men-
2.1.1 Openings in the hull, superstructures or deckhouses tioned criteria is not fulfilled.
which cannot be closed weathertight are to be considered
as unprotected openings and, consequently, as down-flood- 3.1.2 In case a tug is fitted with water ballast tanks the
ing points for the purpose of stability calculations (the lower lightest anticipated loading condition may be a ballast con-
edge of such openings is to be taken into account). dition (in particular for larger tugs).

2.2 Ventilation openings of machinery 3.1.3 When a tropical freeboard is to be assigned to the
space and emergency generator room tug, the corresponding loading conditions are also to be
included.
2.2.1 It is recognised that for tugs, due to their size and
arrangement, compliance with the requirements of ICLL 3.1.4 For the loading condition corresponding to the maxi-
Reg. 17(3) for ventilators necessary to continuously supply mum draught, when necessary, deck cargo may be applied
the machinery space and the emergency generator room to arrive at the required draught. Attention is to be paid to
may not be practicable. Lesser heights of the coamings of the associated wind profile for verification of the severe
these particular openings may be accepted if the openings: wind and rolling criterion, refer to part A, 2.3 of the Interna-
tional Code on Intact Stability, 2008.
are positioned as close to the centreline and as high
above the deck as practicable in order to maximise the 3.1.5 Additional loading conditions to be included
down-flooding angle and to minimise exposure to green in the stability booklet
water
Additional loading conditions are to be included in the sta-
are provided with weathertight closing appliances in bility booklet:
combination with suitable arrangements, such as sepa-
rators fitted with drains tug in the worst anticipated operating conditions for
towing, covering the relevant range of draughts, for serv-
are equipped with efficient protective louvers and mist
ice notations harbour tug and tug
eliminators
tug in the worst anticipated operating conditions for
have a coaming height of not less than 900 mm above
escorting, covering the relevant range of draughts, for
the deck
service notation escort tug.
are considered as unprotected openings and, conse-
quently, as down-flooding points for the purpose of sta- Further loading conditions may be included when deemed
bility calculations. necessary or useful.

12 Bureau Veritas July 2014


NI 617, Sec 2

3.2 Stability criteria 3.3.6 A harbour tug or tug may be considered as having
sufficient stability to withstand the heeling moment arising
3.2.1 The intact stability of tugs should comply with the from the towline if the following condition is complied with
provisions given in part A, 2.2 and 2.3 of the International (see Fig 1):
Code on Intact Stability, 2008, except that the alternative AB
criteria given in part B, 2.4.5, which apply to offshore sup-
ply vessels, may be used for tugs of similar design and char- where:
acteristics.
A : Area, in m.rad, contained between the righting
arm and the heeling arm curves, measured from
3.2.2 With reference to Part B, 5.1.4 of the International the heeling angle C to the heeling angle D
Code on Intact Stability, 2008, tugs should possess an ade-
quate reserve of stability to withstand the anticipated heel- B : Area, in m.rad, contained between the heeling
ing moment arising from the towline. It is considered that arm and the righting arm curves, measured from
this requirement is complied with in case a tug meets the zero heel ( = 0) to the heeling angle C
additional stability criteria as specified in [3.3] and/or [3.4], C : Heeling angle of equilibrium, corresponding to
as applicable. the first intersection between heeling and right-
ing arm curves
3.3 Additional stability criteria for service D : Heeling angle, to be taken as the lesser of:
notations harbour tug and tug
heeling angle corresponding to the second
3.3.1 All the loading conditions reported in the trim and intersection between heeling and righting
arms heeling and righting arm curves
stability booklet which are intended for towing operations
are also to be checked in order to investigate the tugs capa- angle of downflooding.
bility to withstand the effect of the transverse heeling
moment induced by the combined action of the towline Figure 1 : Heeling and righting arm curves
force and the thrust vector.

3.3.2 The stability calculations are to be performed on the


basis of the Bollard Pull, as defined in Sec 1, [4.1].

3.3.3 For tugs capable of towing over the stern as well as


over the bow, this check is to be performed for both towing
situations, duly taking into account the location of the asso-
ciated towing points. If different values of the ahead and
astern Bollard Pull are available, it is acceptable to consider
the ahead Bollard Pull for towing over the stern and the
astern Bollard Pull for towing over the bow.

3.3.4 The values of the ahead and astern Bollard Pull, as


applicable, are to be specified by the Designer in the stabil-
ity booklet. In addition, an arrangement drawing with the
3.3.7 The heeling arm curve is to be calculated as follows:
location of the towing point(s) and propulsion unit(s) is to
be included in the stability booklet. In this drawing the lon- T BP hc
b H = ----------------
- cos
gitudinal and vertical distance, in m, from each of the tow- 9, 81
ing points to the relevant centrelines of the propulsion
unit(s) and the baseline, respectively, are to be specified. where:

bH : Heeling arm, in m
3.3.5 Preliminary stability calculations on the basis of esti-
mated Bollard Pull values may be submitted for (prelimi- TBP : Bollard Pull, in kN, as relevant for the consid-
nary) examination. If after completion of the Bollard Pull ered towing situation
test the measured Bollard Pull values exceed the estimated h : Vertical distance, in m, between the towing
values, the stability calculations have to be updated for the point (fairlead, staple, towing hook or equiva-
measured Bollard Pull values. It is recommended to include lent fitting) and the horizontal centreline of the
a reasonable margin in the estimated values (on the basis of propulsion unit(s), as relevant for the considered
design experience). towing situation

July 2014 Bureau Veritas 13


NI 617, Sec 2

c : Coefficient to be taken equal to: 3.4.5 The value of the highest anticipated heeling moment
is to be specified by the Designer in the stability calcula-
c = 0,50 for tugs with non-azimuth propul- tions. In addition, an arrangement drawing with the loca-
sion (conventional tug, see Sec 1, [2.3.1]) tion of the towing points and propulsion units is to be
included in the stability booklet. In this drawing the longitu-
c = 0,90 / (1 + d / LLL) for tugs with azimuth-
dinal and vertical distance, in m, from the towing point to
ing thrusters installed at a single point along the relevant centrelines of the propulsion units and the
the length (tractor tug and ASD tug, see Sec baseline, respectively, are to be specified.
1, [2.3.2] and Sec 1, [2.3.3], respectively, as
well as similar tug designs), as relevant for 3.4.6 Preliminary stability calculations on the basis of esti-
the considered towing situation, but is in no mated highest heeling moment and associated heeling arm
case to be taken as less than 0,70 for ASD values may be submitted for (preliminary) examination. If
tugs towing over the stern and tractor tugs after verification of the heeling arm values on the basis of
towing over the bow and 0,50 for ASD tugs the results of escort performance trials, model tests or a
towing over the bow and tractor tugs towing computer simulation programme accepted by the Society
over the stern, respectively (refer to [3.5]) the final values exceed the estimated values,
the stability calculations have to be updated for the final
: Loading condition displacement, in t heeling moment and heeling arm values. It is recommended
to include a reasonable margin in the estimated values (on
: Angle of heel, in deg the basis of design experience).
d : Longitudinal distance, in m, between the tow-
ing point (fairlead, staple, towing hook or equiv- 3.4.7 An escort tug may be considered as having sufficient
alent fitting) and the vertical centreline of the stability to withstand the heeling moment arising from the
propulsion unit(s), as relevant for the considered towline, if the three following conditions are complied
with:
towing situation.
A 1,25 B
3.4 Additional stability criteria for service C 1,40 D
notation escort tug
C 15 deg
3.4.1 All the loading conditions reported in the trim and sta- where:
bility booklet which are intended for escorting operations are
also to be checked in order to investigate the tugs capability A : Righting arm curve area, in m.rad, measured
to withstand the effect of the transverse heeling moment from the heeling angle C to a heeling angle of
20 deg (see Fig 2)
induced by the combined action of the following forces:
B : Heeling arm curve area, in m.rad, measured
hydrodynamic forces acting on the hull and appendices
from the heeling angle C to a heeling angle 20
thrust forces deg (see Fig 2)

steady towline force. C : Righting arm curve area, in m.rad, measured


from the zero heel ( = 0) to the heeling angle
D (see Fig 3)
3.4.2 The stability calculations are to be performed on the
basis of the highest anticipated heeling moment for the con- D : Heeling arm curve area, in m.rad, measured
sidered loading condition, which is to be obtained from the from zero heel ( = 0) to the heeling angle D
results of full scale tests, model tests, or, alternatively, the (see Fig 3)
results of a computer simulation programme accepted by
C : Heeling angle of equilibrium corresponding to
the Society (refer to [3.5]).
the first intersection between heeling arm and
righting arm curve, to be obtained when the
3.4.3 For each relevant loading condition the evaluation of highest anticipated heeling moment resulting
the highest anticipated heeling moment is to be performed for from the steady towline force TESC as defined in
the applicable range of speeds and towline angles, as defined Sec 1, Fig 2, is applied to the escort tug.
in the escort towing arrangement plan (see Sec 3, [2.2]). As a
minimum, the conditions corresponding to the highest rated D : Heeling angle, to be taken as the lesser of:
steering force, TY,R, and highest rated braking force, TX,R, as the angle of down-flooding
defined in Sec 1, [4.2], are to be included in the evaluation.
40 deg
3.4.4 The highest anticipated heeling moment is to be the heeling angle corresponding to the sec-
assumed constant for the purpose of the stability calcula- ond intersection between heeling and right-
tions. ing arms heeling and righting arm curves.

14 Bureau Veritas July 2014


NI 617, Sec 2

Figure 2 : Definition of areas A and B Figure 3 : Definition of areas C and D

3.5 Escort performance simulations


3.5.4 As a minimum, for each relevant loading condition
(see [3.4]) the following set of results is to be provided in
3.5.1 Where the highest anticipated heeling moment is tabular form as function of the escort speed for the rated
obtained from the results of a computer simulation pro- values of the steering force TY,R and the braking force TX,R:
gramme, the basic assumptions and theoretical models
underlying the software are to be presented in detail to the Rated steering force TY,R or steering force TY correspond-
ing to rated braking force TX,R, as applicable
Society. Items to be addressed include:
Rated braking force TX,R or braking force TX correspond-
hydrodynamic lift and drag computation (hull and
ing to rated steering force TY,R, as applicable
appendices)
Corresponding towline force TESC
modelling of thrust forces
All corresponding forces acting in transverse direction
interaction effects between hull, skeg and (steerable)
(hydrodynamic, thrust and towline)
propulsion units
Corresponding heeling angle
flow separation effects
Corresponding heeling moment
water pile-up effects
Corresponding towline angle relative to the escorted
effects of waves and/or swell ship (refer to in Sec 1, Fig 2);
dynamic effects before a steady state is reached (e.g. Corresponding drift angle of the escort tug (refer to in
during initiation and turning manoeuvres) and scaling Sec 1, Fig 2).
effects (if any).
Note 1: The highest anticipated values of the steering force, braking
force, towline force and heeling moment do not normally all occur
3.5.2 A validation report, containing comparisons between
in the same condition (defined by the position of escort tug relative
simulation results and full scale and/or model test results, is to the escorted ship and the drift angle), although more than one
to be presented to the Society. parameter may have its highest value in a particular condition.
Hence it is necessary to consider at least two conditions: one for
the highest anticipated steering force and one for the highest antic-
3.5.3 A clear description of the input and output data is to
ipated braking force. In case the highest anticipated heeling
be provided, along with explanations on how the output moment and/or towline force do not occur in either one of these
data are obtained/calculated by the software. two conditions, the relevant conditions are to be added.

July 2014 Bureau Veritas 15


NI 617, Sec 2

3.5.5 It is recommended that the results of the escort per- 3.6.6 As a minimum, the following data is to be collected
formance simulations are presented in the form of diagrams during testing for post-processing and analysis:
showing the envelope of the (steady state) combinations of Towline force (tension) TESC
steering and braking forces obtained from the simulations.
Towline angle , as defined in Sec 1, Fig 2
Such diagrams should cover the applicable escort speed
range, with a recommended step of 2 kn. Drift angle , as defined in Sec 1, Fig 2
Heeling angle of the escort tug
3.6 Escort performance trials Towline length and angle of towline with the horizontal
plane.
3.6.1 Escort performance trials at full scale or model scale
3.6.7 It is also recommended to measure the following
may be carried out in order to obtain the characteristics of
data:
escort tugs defined in Sec 1, [4.2].
Power setting and orientation angle of rudder(s) (propel-
3.6.2 The trials are to cover the applicable range of loading lers) of the escort tug
conditions and escort speeds. Time needed to perform swing the tug from the equilib-
rium position to its mirror position (see Sec 1, Fig 2).
3.6.3 The following documents are to be submitted for
information prior to testing: 3.6.8 For each combination of loading condition and test
speed:
Relevant loading conditions, defined by draught (or dis-
placement) and trim, for which the tug is designed to The rated steering force TY,R and rated braking force TX,R
perform escort services and are to be calculated on the basis of the correspond-
ing measured steady towline force TESC and the associ-
Applicable range of test speeds of the escorted ship: the
ated measured towline angle, drift angle and the angle
speed is defined as the relative speed with respect to the
between the towline and the horizontal plane
sea, taking into account current effects
The maximum heeling arm is to be calculated on the
Main propulsion characteristics, in particular power and basis of the corresponding measured steady towline
maximum orientation angle of the rudder(s) (propellers); force TESC, as defined in Sec 1, [4.2], the associated
Preliminary calculation of the rated steering force TY,R, measured heeling angle and the GZ curve applicable to
rated braking force TX,R and rated steady towline force the loading condition considered.
TESC,R as defined in Sec 1, [4.2], as well as the corre-
Note 1: The GZ curve is to be based on the escort tug in upright
sponding heeling moments and heeling angles, for the position before commencing the escort operation
range of test speeds
Calculation of the route deviation of the escorted ship 3.6.9 As a minimum, for each tested loading condition the
(for testing purposes the escorted ship is to be selected following set of results is to be provided in tabular form as
so that the route deviation induced by the tug is kept function of the escort speed for the rated values of the steer-
reasonably small ing force TY,R and the braking force TX,R:

Preliminary stability calculations for the above men- Rated steering force TY,R or steering force TY correspond-
tioned conditions ing to rated braking force TX,R, as applicable
Rated braking force TX,R or braking force TX correspond-
Escort towing arrangement plan, including the load cell
and specification of the components ing to rated steering force TY,R, as applicable
Corresponding towline force TESC,R
Documentation relevant to the Bollard Pull test, see Sec
1, [4.1]. Corresponding heeling angle
Corresponding heeling moment
3.6.4 Prior to commencing the escort performance trials Corresponding towline angle relative to the escorted
the following data are to be recorded: ship (refer to in Sec 1, Fig 2)
Wind speed and direction Corresponding drift angle of the escort tug (refer to in
Sea state, including significant wave height and peak Sec 1, Fig 2).
period Note 1: The highest anticipated values of the steering force, braking
Current speed and direction force, towline force and heeling moment do not normally all occur
in the same condition (defined by the position of escort tug relative
Water depth to the escorted ship and the drift angle), although more than one
Loading condition of the escort tug: draught (or dis- parameter may have its highest value in a particular condition.
placement) and trim Hence it is necessary to consider at least two conditions: one for
the highest anticipated steering force and one for the highest antic-
Loading condition of the escorted ship. ipated braking force. In case the highest anticipated heeling
moment and/or towline force do not occur in either one of these
3.6.5 Testing is to be performed over the applicable range two conditions, the relevant conditions are to be added.
of towline angles as defined in the escort towing arrange-
ment plan. The length of the towline and the angle of the 3.6.10 For model testing due consideration is to be paid to
towline with the horizontal plane are is to represent a typi- scale effects for establishing the escort tug characteristics at
cal operating condition. full scale from the model test results.

16 Bureau Veritas July 2014


NI 617, Sec 2

3.7 Operating information for service nota- 3.8 Icing considerations


tion escort tug
3.8.1 For tugs operating in areas where ice accretion is
3.7.1 Additional operating information is to be provided in
expected due consideration is to be given to the stability
the stability booklet in relation to the design limitations
affecting effect of added weight due to ice accretion.
related to the assignment of the service notation escort tug .
Note 1: Reference is made to Pt B, Ch 3.8 of the International Code To this end relevant loading conditions, including ice accre-
on Intact Stability, 2008. tion are to be included in the stability booklet, together with
detailed calculations of the expected ice accretion.
3.7.2 As a minimum, the following information is to be
included: Note 1: Reference is made to Pt B, Ch 6 of the International Code
Design operating area and environmental conditions for on Intact Stability, 2008.
performing escort operations (refer to Sec 1, [2.2.3])
The maximum escort speed VMAX (refer to Sec 1, [4.2]) 3.9 Elements reducing stability
A table with permissible values of heeling angle and
steady towline force as function of loading condition
3.9.1 Provisions are to be made for a safe margin of stabil-
and escort speed (based on the rated steering and brak-
ity at all stages of the voyage, regard being given to addi-
ing forces as obtained from [3.5] or [3.6], as applicable)
tions of weight, such as those due to absorption of water
Instructions to the master regarding the handling of the and icing and to losses of weight such as those due to con-
escort tug and the associated towing equipment, dem- sumption of fuel and stores.
onstrating the implementation of effective means to lim-
iting the steady towline force and heeling angle within
the permissible limits and the use of the emergency 3.10 Alterations
quick-release device.
Note 1: Adjustable audible or visible alarms, providing a warning 3.10.1 Where any alterations are made to a tug or its tow-
to the master when the heeling angle and/or steady towline force ing equipment so as to materially affect the stability infor-
exceeds the permissible value(s) applicable to the relevant loading mation supplied to the master, amended stability
condition and escort speed, in combination with appropriate han- information shall be provided.
dling instructions are as effective means.
Note 1: While in service life it may be considered to carry out
3.7.3 The table with permissible values of heeling angle (periodical) lightweight surveys to verify any changes in lightship
and steady towline force as function of loading condition displacement and longitudinal centre of gravity. In case significant
and escort speed is to be displayed in the wheelhouse next deviations are found in comparison with the approved stability
to the control desk or another appropriate location. information, it may be necessary to (re-)incline the tug.

July 2014 Bureau Veritas 17


NI 617, Sec 3

SECTION 3 TOWING EQUIPMENT

1 Towing equipment for service Design load of towing hook and towline guiding fittings
notations harbour tug and tug Design calculations of the towline guiding fittings and
the supporting structures of towing equipment, includ-
ing detailed analysis reports in case three dimensional
1.1 General finite element models have been used.

1.1.1 Towing winches, towing hooks and towline guiding 1.2.2 The following documents are to be submitted for
fittings (fairleads, staples, gob-eyes, towing pins, etc.) are approval:
normally to be arranged in way of the tugs centreline, in
such a position as to minimise heeling moment exerted by Detailed drawings of towing winches, including winch
the towline force. drums, main shaft, load carrying non-rotating structures
(support frame), winch brakes, gears and clutches
Effective means are to be provided to lead and restrain the
towline within the designed limits of its sweep. Hydraulic, electrical and control system diagrams of the
towing winch, as applicable
1.1.2 Materials used in towing equipment are to comply Detailed drawings of towing hook and towline guiding
with the applicable class requirements for materials. Class fittings
certificates are required for the materials used for winch
drums, drum shafts, winch brake components, winch sup- Supporting structures of towing equipment.
porting frames, towing hooks and towline guiding fittings.
1.3 Design Load
1.1.3 Reliable emergency quick-release arrangements,
capable of releasing the towline under the maximum antici- 1.3.1 The Design Load DL to be considered for the strength
pated load regardless of the angle of the towline and the assessment of the towing equipment and the associated
tugs trim and heel, are to be provided. supporting structures is given in Tab 1.
The emergency quick-release devices shall be operable in
case of failure of the main power supply. Table 1 : Design Loads for harbour tug and tug

TBP [kN] DL [kN]


1.2 Documents to be submitted
T 200 2T
1.2.1 The following documents are to be submitted for 200 < T < 800 2600 T
information: Harbour tug ---------------------- T
1200
Towing arrangement plan, showing the location and T 800 1,5 T
general lay-out of the towing equipment, the range of
anticipated lines of action of the towlines with the asso- T 400 2,5 T
ciated maximum steady towline forces and the corre- 400 < T < 1000 3400 T
sponding points of application of the towline forces on Tug ---------------------- T
1200
the towing equipment
T 1000 2T
Note 1: The steady towline force is the towline force without
dynamic amplification effects (also called quasi-static towline Note 1: The DL takes into consideration dynamic effects
force). through the application of the Dynamic Amplification Factor
(DAF) (see also Sec 1, [4.4]).
Detail arrangement drawings of towing winches, towing
hooks and towline guiding fittings (fairleads, staples,
gob-eyes, towing pins, stern roller, etc.) 1.4 Design requirements for towing winches
Design information of towing winches, including maxi-
1.4.1 The winch brake shall normally act directly on the
mum rated line pull, winch brake holding force, render-
drum and shall be operable in case of failure in the primary
ing load and specification of emergency quick-release
power supply system (either manually or otherwise
arrangements
arranged).
Design calculations of towing winches, including winch
drums, main shaft, load carrying non-rotating structures 1.4.2 The towline attachment to the winch drum shall be
(support frame) and braking capacity provided by means of a weak link or equivalent.

18 Bureau Veritas July 2014


NI 617, Sec 3

1.4.3 Towing winches shall be provided with an emer- 1.5 Design requirements for towing hooks
gency quick-release device operable from a position on the
bridge with full view and control of the towing operation. 1.5.1 Towing hooks and their load carrying attachments
Means of control for the emergency quick-release device (connecting the towing hook to the hull structure) shall be
shall be protected against unintentional use. able to sustain the DL, as specified in [1.3], without exceed-
The time delay between the initiation and actual start of the ing an equivalent stress level (based on Von Mises criterion)
emergency quick-release (pay-out of the towline) should be of 0,80 ReH.
as short as reasonably practicable. Towing hooks shall be provided with an emergency quick-
release device operable from a position on the bridge with
The speed of paying out shall be such that the tension in the
full view and control of the towing operation, as well as at a
towline is reduced as fast as reasonably possible, taking into
location near the hook where the device can be safely oper-
consideration that paying out is to be done in a controlled
ated. Identical means of control for the emergency quick-
manner. Spinning (free, uncontrolled rotation) of the winch
release devices shall be provided at each control station
drum is to be avoided, as this could cause the towline to get
and are to be protected against unintentional use.
stuck and disable the release function of the winch.
The force necessary to open the hook under load is to be
1.4.4 After a quick-release event the winch brakes shall not greater than 150 N.
directly be able to operate normally (automatically), while The applicable procedures for the emergency quick-release
the winch motor shall be engaged manually (not automati- device shall be communicated to the crew and vital infor-
cally). mation shall be displayed next to the control desk or
The applicable procedures for the emergency quick-release another appropriate location.
device, including time delays and release speed, shall be
communicated to the crew and vital information shall be 1.6 Design requirements for towlines
displayed next to the control desk or another appropriate
location. 1.6.1 The breaking strength of towlines is not to be less
than the DL, as specified in [1.3].
1.4.5 The dimensioning of the winch drum is to take into In addition, the breaking strength of towlines used on a tow-
account the rope bending specifications provided by the ing winch is not to be less than the BHL of the associated
towline manufacturer. winch (see Sec 1, [4.5]).
Due consideration is to be given to the proper spooling of
The towline shall be protected from being damaged by
the towline on the winch drum, as well as preventing the
chafing and abrasion. To this end cargo rails, bulwarks, and
towline to slip over the flanges of the drum.
other elements, supporting the towline should be suffi-
1.4.6 Towing winches (in particular the components which ciently rounded with consideration to the bend radius limit
are exposed to the tension in the towline, such as the winch of the towline in order to ensure that the towline breaking
drums, drum shafts, brakes, support frame and connection strength is maintained.
to the hull structure) shall be able to: It is recommended that the total length of the towline
sustain the DL, as specified in [1.3] without permanent applied on a towing winch is to be such that under normal
deformation, and operation at least half a layer remains on the drum. In no
case less than three turns shall remain on the drum in under
sustain the BHL, as defined in Sec 1, [4.5], without normal operation.
exceeding an equivalent stress level (based on Von
Mises criterion) of 0,80 ReH.
1.7 Design requirements for towline guiding
where: fittings
ReH : Minimum specified yield stress of material,
in N/mm2. 1.7.1 Towline guiding fittings, such as fairleads, staples,
gob-eyes, towing pins, stern rollers and equivalent compo-
1.4.7 Where deemed necessary by the Society, buckling nents which guide the towline, shall be able to sustain the
and/or fatigue analysis, performed in accordance with a force exerted by the towline loaded under a tension equal
standard or code of practice recognised by the Society, may to the DL, as specified in [1.3], in the most unfavourable
be required to be submitted for information. anticipated position of the towline without exceeding the
following stress level criteria:
1.4.8 Towing winches may be equipped with an active pay- Normal stress 0,75 Rref
out and haul-in system automatic adjustment of towline. In
that case the relevant requirements of [2.4] and [2.8] are to Shear stress 0,47 Rref
be complied with. Equivalent stress VM 0,85 Rref

1.4.9 It is recommended that the towing winch should be where:


fitted with equipment to continuously measure the tension Rref : Reference stress of the material, in N/mm2, nor-
in the towline. mally to be taken as 235/k, but may be taken as
In case a towline measurement system is installed on board, ReH for fittings not made of welded construction.
the measured data are to be displayed in the wheelhouse k : Material factor, defined as function of the mini-
next to the control desk or another appropriate location. mum guaranteed yield stress ReH, see Tab 2.

July 2014 Bureau Veritas 19


NI 617, Sec 3

Table 2 : Material factor k 1.9 Fendering

ReH, in N/mm2 k 1.9.1 A robust and efficient fendering system is to be fitted


235 1 in areas intended for pushing. The fendering system pur-
pose is to distribute the pushing force and limit its dynamic
315 0,78 component on the hull structure of both the tug (and the
355 0,72 assisted ship).

390 0,68 The design of the fendering system, in particular the contact
area and stiffness distribution, is to result in an acceptable
1.7.2 Towline guiding fittings used for guiding the towline pressure distribution on the supporting structure of the tug
when towing on a towing winch shall be able to sustain the (and the assisted ship) under the maximum anticipated
force exerted by the towline loaded under a tension equal loads during pushing operations.
to the BHL of the associated winch, as specified in Sec 1,
[4.5], in the most unfavourable anticipated position of the Within the context of these guidelines it is considered that
towline without exceeding the above mentioned stress level during pushing operations the contact between the tug and
criteria. assisted ship is maintained and that no bouncing (e.g. under
wave action) is taking place. Forces resulting from bouncing
1.7.3 Where a towline guiding fitting (e.g. fairlead or guide loads are not taken into consideration, as it is understood
pin) has been designed for a specific Safe Working Load that pushing operations (in waves) are normally halted
SWL, defined as the maximum static working load, the fit- when bouncing starts taking place (due to operational diffi-
ting shall be able to sustain a force equal to 2 times the SWL culties to keep position within the pushing area of the
without exceeding the above mentioned the above men- assisted ship as well as to control the associated impact type
tioned stress level criteria. loads).

1.7.4 In case the yielding check of the towline guiding fit- 1.9.2 The Design Load DL to be considered for the strength
tings is carried out by means of a three dimensional finite assessment of the fender supporting structure may be taken
element model, the permissible stress levels given above as follows:
may be increased by 10 per cent (compared to a beam
model). DL = 1,5 TBP

where:
1.8 Design requirements for towing equip-
ment supporting structures TBP : Bollard Pull, as defined in Sec 1, [4.1].

The DL takes into consideration anticipated dynamic effects


1.8.1 The supporting structures of towing equipment shall
through the application of the Dynamic Amplification Fac-
be able to sustain the load exerted on the supporting struc-
tor (DAF) (see also Sec 1, [4.4]), but not bouncing effects
ture under the action of the towline loaded under a tension
(see above).
equal to the DL, as specified in [1.3], in the most unfavour-
able anticipated position of the towline, without exceeding The fender supporting structure shall be able to sustain the
the stress level criteria specified in [1.7].
DL, as specified above, without exceeding the stress level
criteria specified in [1.7].
1.8.2 Supporting structures of towing equipment engaged
when towing on a towing winch shall be able to sustain the
load exerted on the supporting structure under the action of 1.10 Testing requirements
the towline loaded under a tension equal to the BHL of the
associated winch, as specified in Sec 1, [4.5], in the most
1.10.1 Towing winches, including the associated emer-
unfavourable anticipated position of the towline without
gency quick-release devices are normally to be load tested
exceeding the stress level criteria specified in [1.7].
at the DL, as defined in [1.3], or the BHL, as defined in Sec
1, [4.5], whichever is the greatest. Generally, load testing is
1.8.3 Where a towline guiding fitting has been designed for
to be conducted at a special facility equipped to generate
a specific Safe Working Load SWL, defined as the maxi-
the required line tension (e.g. makers premises) and to be
mum static working load, the associated supporting struc-
ture shall be able to sustain a force equal to 2 times the witnessed by the Society.
SWL without exceeding the stress level criteria specified in In case a towing winch is of conventional, proven design,
[1.7]. for which load testing has been previously performed in a
deemed acceptable by the Society, it is sufficient to perform
1.8.4 In case the yielding check of the towing equipment on board function testing in accordance with the require-
supporting structures is carried out by means of a three
ments specified below.
dimensional finite element model, the permissible stress
levels given above may be increased by 10 per cent (com- Note 1: The Society may request the winch manufacturer to supply
pared to a beam model). records of the load tests performed.

20 Bureau Veritas July 2014


NI 617, Sec 3

1.10.2 Towing hooks, including the associated emergency 1.10.7 Operational tests are to be performed by the crew in
quick-release devices, are normally to be load tested at the order to ensure the satisfactory operation of the towing
DL, as defined in [1.3]. Generally, load testing is to be con- equipment, in particular the emergency quick-release sys-
ducted at a special facility equipped to generate the tems, as requested by the operating manual.
required line tension (e.g. makers premises) and to be wit- Records of operational tests are to be kept on board and
nessed by the Society. made available to the Society upon request.
For novel or particular designs the emergency quick-release
devices is also to be load tested with the towline at an 2 Towing equipment for service
upward angle of 45 degrees with the horizontal plane at a notation escort tug
towline force of not less than 50 per cent of the Bollard Pull,
as defined Sec 1, [4.1].
2.1 General
In case a towing hook is of conventional, proven design, for
which load testing has been previously performed in a 2.1.1 The requirements of [1] are to be complied with in
deemed acceptable by the Society, it is sufficient to perform relation to normal towing services.
on board function testing in accordance with the require- Note 1: Normal towing services are to be understood to include
ments specified below. towing and pushing operations other than escorting as defined in
Sec 1, [2.2.3].
Note 1: The Society may request the winch manufacturer to supply
records of the load tests performed. 2.1.2 Towing winches and towline guiding fittings (fair-
leads, staples, etc.) used for escort services are normally to
1.10.3 In general, the proper functioning of the towing be arranged in way of the tugs centreline, in such a position
equipment is to be verified by on board testing and to be as to minimise heeling moment.
witnessed by the Society. Function testing is to be per-
2.1.3 Materials used in towing equipment are to comply
formed both for normal operating conditions and in accord-
with the applicable class requirements for materials. Class
ance with the towing arrangement plan, see [1.2], as well as
certificates are required for the materials used for winch
in emergency conditions (emergency quick-release, failure
drums, drum shafts, winch brake components, winch sup-
of main power supply). The safe operation of the towing
porting frames and towline guiding fittings.
winch from all control stations is to be demonstrated.
2.1.4 Reliable emergency quick-release arrangements,
1.10.4 Towing winches are to be function tested on board. capable of releasing the towline under the maximum antici-
The correct functioning of the winch brake, the load carry- pated load regardless of the angle of the towline and the
ing winch components and the associated supporting struc- tugs trim and heel, are to be provided.
ture is to be demonstrated at a towline force equal to the The emergency quick-release devices shall be operable in
Bollard Pull, as defined in Sec 1, [4.1]. The emergency case of failure of the main power supply.
quick-release is to be function tested under normal power
supply with a towline force corresponding to the minimum
thrust (engine(s) clutched in and running at idle speed), as 2.2 Documents to be submitted
well as in dead-ship condition (without strain in the tow-
2.2.1 The following documents are to be submitted for
line).
information:
Winch operating modes to be function tested include haul- Escort towing arrangement plan, showing the location
ing in and paying out of the towline, as well as braking. and general lay-out of the towing equipment used for
escorting, the range of anticipated lines of action of the
Hydraulic and electrical systems shall be function tested on towlines with the associated maximum steady towline
board in accordance with the Societys requirements for forces and the corresponding points of application of
machinery and electrical systems. the towline forces on the towing equipment
Note 1: The steady towline force is the towline force without
1.10.5 Towing hooks are to be function tested on board. dynamic amplification effects (also called quasi-static towline
The correct functioning of the hook and the associated sup- force).
porting structure is to be demonstrated at a towline force Summary tables of maximum steering force TY, in kN,
equal to the Bollard Pull, as defined in Sec 1, [4.1]. The and maximum braking force TX, in kN, for the intended
emergency quick-release is to be function tested under nor-
range of speeds VY, in kn, as obtained from the results of
mal power supply with a towline force corresponding to the
full scale tests or model tests, or alternatively, the results
minimum thrust (engine(s) clutched in and running at idle
of a computer simulation program accepted by the Soci-
speed), as well as in dead-ship condition (without strain in
ety, refer to Sec 2, [3.5]
the towline).
Note 2: In case the final values are not yet available, estimated val-
ues may be submitted as preliminary information for the pur-
1.10.6 Where deemed necessary by the Society towline pose drawing review. In case the final values are significantly
guiding fittings may be required to be function tested under higher than the preliminary values, the drawings are to be
specified conditions. reviewed against the final values.

July 2014 Bureau Veritas 21


NI 617, Sec 3

Detail arrangement drawings of the escort winch and This system is to automatically and reliably pay-out the tow-
towline guiding fittings used for escorting (fairlead, sta- line in a controlled manner when the towline force exceeds
ple) a pre-set (adjustable) level equal to 110 per cent of the rated
Design information of escort winch, including maxi- towline force TESC,R and, as the towline force is reduced,
mum rated line pull, winch brake holding force, render- actively haul-in the towline to prevent slack-line events and
ing and recovering loads and specification of maintain a pre-set or adjustable towline force consistent
emergency quick-release arrangement with the rated towline force.
Design calculations of escort winch, including winch Pay-out and haul-in speeds and pull capability shall be cho-
drums, main shaft, load carrying non-rotating structures sen taking into account the anticipated escort services and
(support frame) and braking capacity the dynamic characteristics of the escort tug.
Design load of towline guiding fittings used for escort- Escort operations in conditions where dynamic oscillations
ing of the towline are likely to occur may not be based on the
Design calculations of the towline guiding fittings and use of the brakes of the winch drum.
the supporting structures of towing equipment used for
2.4.2 Escort operations in calm water conditions, such as in
escorting, including detailed analysis reports in case
ports and sheltered (confined) waters, may be based on the
three dimensional finite element models have been
use of the brakes of the winch drum. As a minimum, the
used.
winch brake holding load BHL is to be equal to or greater
2.2.2 The following documents are to be submitted for than two times the maximum steady towline force TESC,MAX.
approval:
2.4.3 Escort winches are to be fitted with equipment to
Detailed drawings of the escort winch, including winch continuously measure the tension in the towline.
drums, main shaft, load carrying non-rotating structures
(support frame), winch brakes, gears and clutches The measured data are to be displayed in the wheelhouse
next to the control desk or another appropriate location.
Hydraulic, electrical and control system diagrams of the
escort winch, as applicable 2.4.4 The escort towing system is to be designed so as to
Detailed drawings of the towline guiding fittings used enable the proper spooling of the towline on the winch
for escorting drum when hauling in. Generally this can be achieved by a
Supporting structures of towing equipment used for suitable design of the fairlead or staple guiding the towline
escorting. between the escort winch and the assisted ship.
Where a spooling device is fitted, this device should be
2.3 Design Load designed for the same Design Load and stress criteria as the
towline guiding fittings, see [2.6].
2.3.1 The Design Load DL to be considered for the strength
assessment of the towing equipment used for escort services 2.4.5 Winches shall be provided with an emergency quick-
and the associated supporting structures is given in Tab 3. release device operable from a position on the bridge with
full view and control of the towing operation. Means of
Table 3 : Design Loads for escort tug control for the emergency quick-release device shall be
protected against unintentional use.
TESC,MAX [kN] DL [kN] The time delay between the initiation and actual start of the
TESC,MAX 500 3T emergency quick-release (pay-out of the towline) should be
as short as reasonably practicable.
500 < TESC,MAX < 1000 2000 T
---------------------- T The speed of paying out shall be such that the tension in the
500
towline is reduced as fast as reasonably possible, taking into
TESC,MAX 1000 2T consideration that paying out is to be done in a controlled
manner. To that end effective means to prevent spinning
Note 1: The DL takes into consideration dynamic effects
(free, uncontrolled rotation) of the winch drum are to be
through the application of the Dynamic Amplification Factor
provided.
(DAF) (see also Sec 1, [4.4]).
After a quick-release event the winch brakes shall directly
2.4 Design requirements for escort winches be able to operate normally (automatically), while the
winch motor shall be engaged manually (not automati-
2.4.1 The winch brake shall normally act directly on the cally).
drum and shall be operable in case of failure in the primary Note 1: Spinning of the winch drum could cause the towline to get
power supply system (either manually or otherwise stuck and disable the release function of the winch
arranged). The applicable procedures for the emergency quick-release
Escort winches intended to be used in conditions where device, including time delays and release speed, shall be
dynamic oscillations of the towline are likely to occur, such communicated to the crew and vital information shall be
as in open sea areas or other areas exposed to waves, are to displayed next to the control desk or another appropriate
be equipped with an active pay-out and haul-in system. location.

22 Bureau Veritas July 2014


NI 617, Sec 3

The dimensioning of the winch drum is to take into account 2.6.3 Where a towline guiding fitting has been designed for
the rope bending specifications provided by the towline a specific Safe Working Load SWL, defined as the maxi-
manufacturer. mum static working load, the fitting shall be able to sustain
a force equal to 2 times the SWL without exceeding the
Due consideration is to be given to preventing the towline
stress level criteria specified in [1.7].
to slip over the flanges of the drum.

2.4.6 Escort winches (in particular the components which 2.6.4 In case the yielding check of the towline guiding fit-
are exposed to the tension in the towline, such as the winch tings is carried out by means of a three dimensional finite
drums, drum shafts, brakes, support frame and connection element model, the permissible stress levels given above
to the hull structure) shall be able to: may be increased by 10 per cent (compared to a beam
model).
sustain the DL, as specified in [2.3] without permanent
deformation, and
sustain the BHL, as defined in Sec 1, [4.5], without
2.7 Design requirements for towing equip-
exceeding an equivalent stress level (based on Von ment supporting structures
Mises criterion) of 0,80 ReH
2.7.1 The supporting structures of towing equipment used
where: for escort services shall be able to sustain the load exerted
ReH : Minimum specified yield stress of material, on the supporting structure under the action of the towline
in N/mm2. loaded under a tension equal to the DL, as specified in
[2.3], in the most unfavourable anticipated position of the
2.4.7 Where deemed necessary by the Society, buckling towline, without exceeding the stress level criteria specified
and/or fatigue analysis, performed in accordance with a in [1.7].
standard or code of practice recognised by the Society, may
be required to be submitted for information. 2.7.2 In addition, supporting structures of towing equip-
ment used for escort services shall be able to sustain the
2.5 Design requirements for towlines load exerted on the supporting structure under the action of
the towline loaded under a tension equal to the BHL of the
2.5.1 The breaking strength of towlines used for escort serv- associated winch, as specified in Sec 1, [4.5], in the most
ices is not to be less than the DL, as specified in [2.3]. unfavourable anticipated position of the towline without
exceeding the stress level criteria specified in [1.7].
In addition, the breaking strength for towlines used for
escort services on an escort winch is not to be less than the
2.7.3 Where a towline guiding fitting has been designed for
BHL of the associated escort winch (see Sec 1, [4.5]).
a specific Safe Working Load SWL, defined as the maxi-
2.5.2 The towline shall be protected from being damaged mum static working load, the associated supporting struc-
by chafing and abrasion. To this end cargo rails, bulwarks, ture shall be able to sustain a force equal to 2 times the
and other elements, supporting the towline should be ade- SWL without exceeding the stress level criteria specified in
quately rounded. [1.7].

2.5.3 It is recommended that the total length of the towline 2.7.4 In case the yielding check of the towing equipment
applied on a towing winch is to be such that under normal supporting structures is carried out by means of a three
operation at least half a layer remains on the drum. In no dimensional finite element model, the permissible stress
case less than three turns shall remain on the drum in under levels given above may be increased by 10 per cent (com-
normal operation. pared to a beam model).

2.6 Design requirements for towline guiding 2.8 Testing requirements


fittings
2.8.1 Escort winches, including the associated emergency
2.6.1 Towline guiding fittings used for escort services, such quick-release device are normally to be load tested at the
as fairleads, staples and equivalent components which DL, as defined in [2.3], or the BHL, as defined in Sec 1,
guide the towline, shall be able to sustain the force exerted [4.5], whichever is the greatest. Generally, load testing is to
by the towline loaded under a tension equal to the DL, as be conducted at a special facility equipped to generate the
specified in [2.3], in the most unfavourable anticipated required line tension (e.g. makers premises) and to be wit-
position of the towline without exceeding the stress level nessed by the Society.
criteria specified in [1.7].
In case an escort winch is of conventional, proven design,
2.6.2 In addition, towline guiding fittings shall be able to for which load testing has been previously performed in a
sustain the force exerted by the towline loaded under a ten- deemed acceptable by the Society, it is sufficient to perform
sion equal to the BHL of the associated winch, as specified on board function testing in accordance with the require-
in Sec 1, [4.5], in the most unfavourable anticipated posi- ments specified below.
tion of the towline without exceeding the stress level criteria Note 1: The Society may request the winch manufacturer to supply
specified in [1.7]. records of the load tests performed.

July 2014 Bureau Veritas 23


NI 617, Sec 3

2.8.2 In general, the proper functioning of the towing Hydraulic and electrical systems shall be function tested on
equipment used for escort services is to be verified by on board in accordance with the Societys requirements for
board testing and to be witnessed by the Society. Function machinery and electrical systems.
testing is to be performed both for normal operating condi-
tions and in accordance with the escort towing arrangement 2.8.3 Where deemed necessary by the Society towline
plan, see [2.2], as well as in emergency conditions (emer- guiding fittings used for escort services may be required to
gency quick-release, failure of main power supply). The safe be function tested under specified conditions.
operation of the escort winch from all control stations is to 2.8.4 Operational tests are to be performed by the crew in
be demonstrated. order to ensure the satisfactory operation of the towing
Escort winches are to be function tested on board. The cor- equipment used for escort services, in particular the emer-
rect functioning of the winch brake, the load carrying winch gency quick-release systems, as requested by the operating
manual.
components and the associated supporting structure is to be
demonstrated at a towline force equal to the Bollard Pull, as Records of operational tests are to be kept on board and
defined in Sec 1, [4.1]. The emergency quick-release is to made available to the Society upon request.
be function tested under normal power with a towline force
corresponding to the minimum thrust (engine(s) clutched in 2.9 Inclinometer
and running at idle speed), as well as in dead-ship condi-
tion (without strain in the towline). 2.9.1 Escort tugs are to be equipped with a calibrated heel-
ing angle measurement system (inclinometer).
Winch operating modes to be function tested include haul- The measured heeling angle is to be displayed in the wheel-
ing in and paying out of the towline, braking and the active house next to the control desk or another appropriate loca-
pay-out and haul-in system when fitted (see [2.4]). tion.

24 Bureau Veritas July 2014


NI 617, Sec 4

SECTION 4 FIRE SAFETY FOR TUGS OF LESS THAN 500 GT

1 General Fixed fire extinguishing systems should be installed, as


applicable, having due regard to the fire growth poten-
tial of the protected spaces; and
1.1 Scope of application
Fire extinguishing appliances should be readily availa-
1.1.1 This section applies to tugs of less than 500 GT. ble.

1.2 Fire safety objectives 2.2 Capacity

1.2.1 The fire safety objectives of this section are to: 2.2.1 The total capacity Q, in m3/hour, of the main fire
pump(s) is not to be less than:
Prevent the occurrence of fire and explosion
2
Q = ( 0,145 L ( B + D ) + 2,170 )
Reduce the risk to life caused by fire

Reduce the risk of damage caused by fire to the tug and but need not exceed 25 m3/hour,
the environment
where:
Contain, control and suppress fire and explosion in the
L : Freeboard Length, in m
compartment of origin; and
B : Greatest moulded breadth of tug, in m
Provide adequate and readily accessible means of
escape for crew. D : Moulded depth to bulkhead deck, in m.

1.2.2 The fire safety objectives set out above could be


achieved by ensuring compliance with [2] to [7], or by 2.3 Fire pumps
alternative design and arrangements which comply with [7].
A tug could be considered to achieve the fire safety objec- 2.3.1 Generally one main power pump and one portable
tives set out in first paragraph when either: fire pump should be provided as specified below:
The tug's designs and arrangements, as a whole, comply a) Sanitary, ballast, bilge or general service pumps may be
with [2] to [6], as applicable accepted as fire pumps, provided that they are not nor-
The tug's designs and arrangements, as a whole, have mally used for pumping oil, and that, if they are subject
been reviewed and approved in accordance with [7]; or to occasional duty for the transfer or pumping of fuel
oil, suitable changeover arrangements are fitted
Part(s) of the tug's designs and arrangements have been
reviewed and approved in accordance with [7] and the b) A power pump is a fixed pump driven by a power
remaining parts of the tug comply with the relevant Rec- source other than by hand. An independently driven
ommendations in [2] to [6]. power pump is independent from the main engine(s)

c) Provisions are to be made for clearing sea inlet gratings


1.3 Requirements for fire safety equipment of fire pump sea inlet valves. Special attention is to be
paid to ice clearing arrangements for tugs intended for
1.3.1 Requirements for fire safety equipment are defined in navigation in ice (e.g. air blowing, heating)
Tab 1.
d) Relief valves should be provided in conjunction with
any fire pump if the pump is capable of developing a
2 Fire pumps and fire main systems pressure exceeding the design pressure of the water
service pipes, hydrants and hoses. These valves should
be so placed and adjusted as to prevent excessive pres-
2.1 Purpose sure in any part of the fire main system

2.1.1 The purpose of this requirement is to suppress and e) Where a centrifugal pump is provided in order to com-
swiftly extinguish a fire in the space of origin. For this pur- ply with this sub-section, a non-return valve should be
pose, the following functional requirements should be met: fitted in the pipe connecting the pump to the fire main.

July 2014 Bureau Veritas 25


NI 617, Sec 4

Table 1 : Fire safety requirements

tug / escort tug harbour tug


sailing time 4h from a
(unrestricted) (in port)
safe sheltered anchorage
fire pumps
150 gt independently driven power pumps 1 1 1
power pumps 1 1 1
hand pumps
< 150 gt independently driven power pumps
power pumps 1 1 1
hand pumps 1 1
portable or fixed emergency fire pump 1 (1) (2) 1 (1) (2)
fire hydrants
150 gt Sufficient number and so located that at least 2 2 2
the number of powerful water jets can reach any
normally accessible part of tug
< 150 gt Sufficient number and so located that at least 1 1 1
the number of powerful water jets can reach any
normally accessible part of tug
number of hydrants number of hydrants number of hydrants
fire hoses (length) (3)
+ 1 spare hose + 1 spare hose + 1 spare hose
with coupling and nozzles X X X
hose nozzles
dual purpose (spray/jet) with 12 mm jet and integral shut- X X X
off; jet may be reduced to 10 mm and shut-off omitted for
hand pump hoses
portable fire extinguishers
machinery spaces (one extinguisher per 375 kW of internal 2 2 2
combustion engine power (4) (capacity 45 l fluid or equiv- 6 6 6
alent)
fixed fire extinguishing systems
150 gt Category A machinery spaces X X
fixed fire detection system (Category A spaces) X X X

firemans outfit
complete outfit 1 1
firemans axe 1 1 1
150 gt fire control plan 1 1 1
means of escape
accommodation and service spaces 2 2 2
machinery spaces (5) 2 2 2
(1) For tugs of less than 150 GT fitted with an approved fixed fire-fighting system in the engine room, portable pumps may be omit-
ted.
(2) When a portable / emergency firepump is fitted, (independent) power pump may be omitted.
(3) Sufficient in length to project a jet of water to any of the spaces in which they may be required to be used.
(4) Alternatives may be proposed taking into consideration the size of the tug and the installed power.
(5) Unless when the small size of the machinery space makes it unpractical.

26 Bureau Veritas July 2014


NI 617, Sec 4

2.4 Portable fire pumps d) Pump is required to supply water for a fixed fire-extin-
guishing system in the space there the main fire pump is
2.4.1 Portable fire pumps should comply with the follow- situated, it should be capable of simultaneously supply-
ing: ing water to this system and the fire main at the required
rates
a) The pump should be self-priming
e) The pump may also be used for other suitable purposes,
b) The total suction head and the net positive suction head subject to the approval in each case
of the pump should be determined taking account of
actual operation, i.e. pump location when used f) Pressure and quantity of water delivered by the pump
Note 1: Net positive suction head of the pump is to be realised
being sufficient to produce a jet of water, at any nozzle,
from the deck where the pump is fitted (in practical cases on of not less than 12 m in length. For tugs of less than 150
tugs this is typically the maindeck). GT, the jet of water may be specially considered.

c) The portable fire pump, when fitted with its length of 2.4.3 For tugs of less than 150 GT fitted with an approved
discharge hose and nozzle, should be capable of main- fixed fire-fighting system in the engine room, portable
taining a pressure sufficient to produce a jet throw of at pumps may be omitted.
least 12 m, or that required to enable a jet of water to be
directed on any part of the engine room or the exterior
2.4.4 Means to illuminate the stowage area of the portable
boundary of the engine room and casing, whichever is
pump and its necessary areas of operation should be pro-
the greater
vided from the emergency source of electrical power.
d) Except for electric pumps, the pump set should have its
own fuel tank of sufficient capacity to operate the pump 2.5 Fire main
for three hours. For electric pumps, their batteries
should have sufficient capacity for three hours
2.5.1 The diameter of the fire main should be based on the
e) Except for electric pumps, details of the fuel type and required capacity of the fixed main fire pump(s) and the
storage location should be carefully considered. If the diameter of the water service pipes should be sufficient to
fuel type has a flashpoint below 60C, further consider- ensure an adequate supply of water for the operation of at
ation to the fire safety aspects should be given least one fire hose.
f) The pump set should be stored in a secure, safe and
2.5.2 The wash deck line may be used as a fire main pro-
enclosed space, accessible from open deck and clear of
vided that the requirements of this sub-section are satisfied.
the Category A machinery space
g) The pump set should be easily moved and operated by 2.5.3 All exposed water pipes for fire-extinguishing should
two persons and be readily available for immediate use be provided with drain valves for use in frosty weather. The
valves should be located where they will not be damaged
h) Arrangements should be provided to secure the pump at
by tug operations.
its anticipated operating position(s)
i) The overboard suction hose should be non-collapsible
2.6 Pressure in the fire main
and of sufficient length, to ensure suction under all
operating conditions. A suitable strainer should be fitted
2.6.1 When the main fire pump is delivering the quantity of
at the inlet end of the hose
water required by [2.2], or the fire pump described in
j) Any diesel-driven power source for the pump should be [2.4.2], through the fire main, fire hoses and nozzles, the
capable of being readily started in its cold condition by pressure maintained at any hydrant should be sufficient to
hand (manual) cranking. If this is impracticable, consid- produce a jet throw at any nozzle of not less than 12 m in
eration should be given to the provision and mainte- length. (For tugs of less than 150 GT, the jet of water may be
nance of heating arrangements, so that readily starting specially considered).
can be ensured.

2.4.2 Alternatively to the requirements of [2.4.1], a fixed


2.7 Fire Hydrants
fire pump may be fitted, which should comply with the fol-
lowing: 2.7.1 Number and position of hydrants
For tugs of less than 150 GT the number and position of
a) The pump, its source of power and sea connection
the hydrants should be such that at least one jet of water
should be located in accessible positions, outside the
may reach any part normally accessible to the crew,
compartment housing the main fire pump
while the tug is being navigated and any part of any
b) The sea valve should be capable of being operated from deck space when empty.
a position near the pump
Furthermore, such hydrants should be positioned near
c) The room where the fire pump prime mover is located the accesses to the protected spaces. At least one
should be illuminated from the emergency source of hydrant should be provided in each Category A
electrical power, and should be well ventilated machinery space.

July 2014 Bureau Veritas 27


NI 617, Sec 4

For tug equal to or greater than 150 GT the number and 2.9.2 For accommodation and service spaces, the nozzle
position of hydrants should be such that at least two jets size need not exceed 12 mm.
of water not emanating from the same hydrant, one of
which should be from a single length of hose, may reach 2.9.3 The size of nozzles used in conjunction with a porta-
any part of the tug normally accessible to the crew ble fire pump need not exceed 12 mm.
while the tug is being navigated and any part of any
cargo spaces when empty. 2.9.4 All nozzles should be of an approved dual purpose
Furthermore, such hydrants should be positioned near type (i.e. spray/jet type) incorporating a shut-off.
the accesses to the protected spaces. Other Require-
ments specified by the Administration may be consid- 3 Fire safety measures
ered.

2.7.2 Pipes and hydrants 3.1 Purpose


a) Materials readily rendered ineffective by heat should not
be used for fire mains. Where steel pipes are used, they 3.1.1 The purpose of this regulation should contain a fire in
should be galvanized internally and externally. Cast iron the space of origin. For this purpose, the following func-
pipes are not acceptable. The pipes and hydrants should tional requirements should be met:
be so placed that the fire-hoses may be easily coupled The tug should be subdivided by thermal and structural
to them. The arrangement of pipes and hydrants should boundaries;
be such as to avoid the possibility of freezing. In tugs
where deck cargo may be carried, the positions of the Thermal insulation of boundaries should have due
hydrants should be such that they are always readily regard to the fire risk of the space and adjacent spaces;
accessible and the pipes should be arranged, as far as The fire integrity of the divisions should be maintained
practicable, to avoid risk of damage by such cargo. at openings and penetrations.
There should be complete interchange ability of hose
couplings and nozzles
3.2 Structural fire protection
b) A valve should be fitted at each fire hydrant so that any
fire-hose may be removed while the fire pump is at work
3.2.1 The minimum fire integrity of bulkheads and decks
c) Where a fixed fire pump is fitted outside the engine should be as prescribed in Tab 2.
room, in accordance with [2.4.2]:
1) an isolating valve should be fitted in the fire main so Table 2 : Minimum fire integrity of bulkheads and
that all the hydrants in the tug, except those in the decks
Category A machinery space, can be supplied with
water. The isolating valve should be located in an Item Space Separation by From space
easily accessible and tenable position outside the 1 Machinery Space A-60 Accommodation
Category A machinery space; and Class A Control stations
2) the fire main should not re-enter the machinery Corridors
space downstream of the isolating valve. Staircases
Service spaces of
high fire risk
2.8 Fire-hoses
2 Machinery Space A-0 Other than above
2.8.1 Fire-hoses should be of approved non-perishable Class A (Item 1)
material. The hoses should be sufficient in length to project 3 Galley A-0 Unless specified
a jet of water to any of the spaces in which they may be otherwise
required to be used. Their length, in general, is not to 4 Service space of B-15 Unless specified
exceed 18 m. Each hose should be provided with a nozzle high fire risk above (Item 1)
and the necessary couplings. Fire-hoses, together with any other than galley
necessary fittings and tools, should be kept ready for use in
conspicuous positions near the water service hydrants or 5 Corridor A-0 Unless specified
Staircase / escape above (Item 1)
connections.
route
2.8.2 One hose should be provided for each hydrant. In Note 1: The divisions used to separate spaces not mentioned
addition one spare hose should be provided on board. above should be of non-combustible material.

2.9 Nozzles 3.2.2 The hull, superstructure, structural bulkheads, decks


and deckhouses should be constructed of steel or other
2.9.1 For the purpose of this section, standard nozzle sizes equivalent material. For the purpose of applying the defini-
are 12 mm, 16 mm or 19 mm, or as near thereto as possi- tion of steel or other equivalent material, as given in SOLAS,
ble, so as to make full use of the maximum discharge the applicable fire exposure should be one hour. Tugs built
capacity of the fire pump(s). of materials other than steel should be specially considered.

28 Bureau Veritas July 2014


NI 617, Sec 4

3.2.3 Stairways should be enclosed, at least at one level, by 3.3.7 Materials used for insulating pipes, etc., in machinery
divisions and doors or hatches, in order to restrict the free spaces and other compartments containing high fire risks
flow of smoke to other decks in the tug and the supply of air should be non-combustible. Vapour barriers and adhesives
to the fire. Doors forming such enclosures should be self- used in conjunction with insulation, as well as the insula-
closing. tion of pipe fittings, for cold service systems need not be of
non-combustible materials, but they should be kept to the
3.2.4 Openings in A Class divisions should be provided minimum quantity practicable and their exposed surfaces
with permanently attached means of closing which should should have low flame spread characteristics.
be at least as effective for resisting fires as the divisions in
which they are fitted. 3.4 Surface of insulation
3.2.5 Interior stairways serving machinery spaces, accom- 3.4.1 In spaces where penetration of oil products is possi-
modation spaces, service spaces or control stations should ble, the surface of the insulation should be impervious to oil
be of steel or other equivalent material. or oil vapours. Insulation boundaries should be arranged to
avoid immersion in oil spillage.
3.2.6 Doors should be self-closing in way of Category A
machinery spaces and galleys, except where they are nor- 3.5 Ventilation systems
mally kept closed.
3.5.1 Ventilation fans should be capable of being stopped
3.2.7 Where A Class divisions are penetrated for the pas- and main inlets and outlets of ventilation systems closed
sage of electric cables, pipes, trunks, ducts, etc., or for gird- from outside the spaces being served.
ers, beams or other structural members, arrangements
should be made to ensure that the fire resistance is not 3.5.2 Ventilation ducts for Category A machinery spaces
impaired. Arrangements should also prevent the transmis- should not pass through accommodation spaces, galleys,
sion of heat to un-insulated boundaries at the intersections service spaces or control stations, unless the ducts are con-
and terminal points of the divisions and penetrations by structed of steel and arranged to preserve the integrity of the
insulating the horizontal and vertical boundaries or penetra- division.
tions for a distance of 450 mm.
3.5.3 Ventilation ducts for accommodation spaces, service
spaces or control stations should not pass through Category
3.3 Materials A machinery spaces or galleys unless the ducts are con-
structed of steel and arranged to preserve the integrity of the
3.3.1 Paints, varnishes and other finishes used on exposed division.
interior surfaces should not be capable of producing exces-
sive quantities of smoke, toxic gases or vapours and should 3.5.4 Ventilation arrangement for store rooms containing
be of the low flame spread type in accordance with the highly flammable products should be specially considered.
IMO FTP Code, Annex 1, Parts 2 and 5.
3.5.5 Ventilation systems serving Category A machinery
3.3.2 Except in cargo spaces or refrigerated compartments spaces and galley exhaust ducts should be independent of
of service spaces, insulating materials should be non-com- systems serving other spaces.
bustible.
3.5.6 Ventilation should be provided to prevent the accu-
mulation of gases that may be emitted from batteries.
3.3.3 Where pipes penetrate A or B Class divisions, the
pipes or their penetration pieces should be of steel or other 3.5.7 Ventilation openings may be fitted in and under the
approved materials having regard to the temperature and lower parts of cabin, mess and dayroom doors in corridor
integrity Recommendations such divisions are required to bulkheads. The total net area of any such openings is not to
withstand. exceed 0.05 m2. Balancing ducts should not be permitted in
fire divisions.
3.3.4 Pipes conveying oil or combustible liquids through
accommodation and service spaces should be of steel or
other approved materials having regard to the fire risk. 3.6 Oil fuel arrangements
3.6.1 In a tug in which oil fuel is used, the arrangements for
3.3.5 Materials readily rendered ineffective by heat should
the storage, distribution and utilization of the oil fuel should
not be used for overboard scuppers, sanitary discharges and
be such as to ensure the safety of the tug and persons on
other outlets which are close to the waterline, and where
board.
the failure of the material in the event of fire would give rise
to the danger of flooding. 3.6.2 Oil fuel tanks situated within the boundaries of Cate-
gory A machinery spaces should not contain oil fuel hav-
3.3.6 Primary deck coverings within accommodation ing a flashpoint of less than 60C.
spaces, service spaces and control stations should be of a
type which will not readily ignite, or give rise to toxic or 3.6.3 Oil fuel, lubricating oil and other flammable oils
explosive hazards at elevated temperatures in accordance should not be carried in a forepeak tank or a tank forward of
with the IMO FTP Code, Annex 1, Parts 2 and 6. the collision bulkhead.

July 2014 Bureau Veritas 29


NI 617, Sec 4

3.6.4 As far as practicable: 3.7.5 The controls required in [3.7.4] should be located
outside the space concerned, where they will not be cut off
a) oil fuel lines shall be arranged far apart from hot sur- in the event of fire in the space they serve. Such controls
faces, electrical installations or other sources of ignition and the controls for any required fire-extinguishing system
and shall be screened or otherwise suitably protected to should be situated at one control position or grouped in as
avoid oil spray or oil leakage onto the sources of igni- few positions as possible. Such positions should have a safe
tion. The number of joints in such piping systems shall access from the open deck.
be kept to a minimum.

b) surfaces with temperatures above 220C which may be 3.8 Arrangements for gaseous fuel for
impinged as a result of a fuel and/or hydraulic oil system domestic purposes
failure shall be properly insulated. Precautions shall be
3.8.1 Where gaseous fuel is used for domestic purposes,
taken to prevent any oil that may escape under pressure
the arrangements for the storage, distribution and utilization
from any pump, filter or heater from coming into con-
of the fuel should be specially considered.
tact with heated surfaces.

c) external high-pressure fuel delivery lines between the 3.9 Space heating
high pressure fuel pumps and fuel injectors shall be pro-
tected with a jacketed piping system capable of contain- 3.9.1 Space heaters, if used, should be fixed in position
ing fuel from a high-pressure line failure. A suitable and so constructed as to reduce fire risks to a minimum. The
enclosure on engines having an output of 375 kW or design and location of these units should be such that cloth-
less having fuel injection pumps serving more than one ing, curtains or other similar materials cannot be scorched
injector may be used as an alternative to the jacketed or set on fire by heat from the unit.
piping system.
3.10 Means of escape
3.7 Special arrangements in Category A 3.10.1 The purpose of this requirement is to provide means
machinery spaces and where necessary of escape so that persons on board can safely and swiftly
other machinery spaces escape to the lifeboat and liferaft embarkation deck. For this
purpose, the following functional requirements should be
3.7.1 The number of skylights, doors, ventilators, openings met:
in funnels to permit exhaust ventilation and other openings Safe escape routes should be provided;
to machinery spaces should be reduced to a minimum con- Escape routes should be maintained in a safe condition,
sistent with the needs of ventilation and the proper and safe clear of obstacles; and
working of the tug. Additional aids for escape should be provided as neces-
sary to ensure accessibility, clear marking, and adequate
3.7.2 Skylights should be constructed with steel frames and design for emergency situations.
are not to contain glass panels, unless fire-retardant glass
equivalent to steel is applied. Suitable arrangements should 3.10.2 Stairways, ladders and corridors serving crew
be made to permit the release of smoke, in the event of fire, spaces and other spaces to which the crew normally have
from the space to be protected. access should be arranged so as to provide ready means of
escape to a deck from which embarkation into survival craft
may be effected.
3.7.3 Windows should not be fitted in machinery space
boundaries. This does not preclude the use of glass in con- 3.10.3 There should be at least two means of escape, as
trol rooms within the machinery spaces. widely separated as possible, from each section of accom-
modation and service spaces and control stations.
3.7.4 Means of control should be provided for:
a) The normal means of access to the accommodation and
a) opening and closure of skylights, closure of openings in service spaces below the open deck should be arranged
funnels which normally allow exhaust ventilation, and so that it is possible to reach the open deck without
closure of ventilator dampers; passing through spaces containing a possible source of
fire (e.g. machinery spaces, storage spaces of flammable
permitting the release of smoke; liquids).
b) The second means of escape may be through portholes
b) closing power-operated doors or actuating release
or hatches of adequate size and preferably leading
mechanism on doors other than power-operated water-
directly to the open deck.
tight doors;
c) Dead-end corridors having a length of more than 7 m
c) stopping ventilating fans; and should not be accepted.
Note 1: The escapes should be positioned either both at centerline,
d) stopping forced and induced draught fans, oil fuel trans- at centreline and at port side, at centreline and at starboard side or
fer pumps, oil fuel unit pumps and other similar fuel at starboard side and at port side. Having both escapes on one side
pumps. of the tug should be avoided.

30 Bureau Veritas July 2014


NI 617, Sec 4

3.10.4 At least two means of escape should be provided from Table 3 : Portable Fire-extinguishers
machinery spaces, except where the small size of a machinery
space makes it impracticable. Escape should be by steel lad- Accommodation and service spaces
ders that should be as widely separated as possible. tugs greater than or equal to 150 GT 3
tugs of less than 150 GT (see [5.6.7]) 1
4 Fixed fire detection and fire-alarm Machinery spaces (one extinguisher per every 375 kW 2
systems of internal combustion engine power) 6

4.1 General 5.6.2 Approved types


All fire-extinguishers should be of approved types and
4.1.1 An approved and fixed fire detection system should be
designs.
installed in all Category A machinery spaces. Manual activat-
ing units should be positioned near each emergency exit.
5.6.3 Extinguishing medium
Note 1: Upon special consideration, taking into account the size
and arrangement (general layout and number of deckhouse tiers) of a) The extinguishing media employed should be suitable
the tug, approved fire detectors may be connected to a group alarm for extinguishing fires in the compartments in which
system. they are intended to be used.
b) The extinguishers required for use in the machinery
5 Fire-extinguishing arrangements spaces of tugs using oil as fuel should be of a type dis-
charging foam, carbon dioxide gas, dry powder or other
5.1 Purpose approved media suitable for extinguishing oil fires.

5.1.1 The purpose of this requirement should suppress and 5.6.4 Capacity
swiftly extinguish a fire in the space of origin. For this pur-
pose, the following functional requirements should be met: a) The capacity of required portable fluid extinguishers
should not exceed more than 13,5 litres but not less
Fixed fire-extinguishing systems should be installed, as
than 9 litres. Other extinguishers should be at least as
applicable, having due regard to the fire growth poten-
portable as the 13,5 litre fluid extinguishers, and should
tial of the protected spaces; and
have a fire-extinguishing capability at least equivalent to
Fire-extinguishing appliances should be readily availa- a 9 litre fluid extinguisher.
ble.
b) The following capacities may be taken as equivalents:
5.2 Fixed fire-extinguishing arrangements 9 litre fluid extinguisher (water or foam);
in Category A machinery spaces 5 kg dry powder;
5.2.1 Machinery spaces of Category A on tugs with GT 5 kg carbon dioxide.
greater than or equal to 150 except for harbour tugs, should
be provided with an approved fixed fire extinguishing sys- 5.6.5 Spare charges
tem, as specified in [5.2]. A spare charge should be provided for each required porta-
ble fire-extinguisher that can be readily recharged on board.
5.3 Fixed fire-extinguishing systems If this cannot be done, duplicate extinguishers should be
provided.
5.3.1 Fixed fire-fighting systems where required, should be
in accordance with the requirements of the IMO FSS Code. 5.6.6 Location
a) The extinguishers should be stowed in readily accessi-
5.4 Protection of paint lockers and flamma- ble positions and should be spread as widely as possible
ble liquid lockers and not be grouped.
5.4.1 The Recommendations for the protection of paint b) One of the portable fire-extinguishers intended for use
lockers and flammable liquids lockers should be specially in any space should be stowed near the entrance to that
considered. space.

5.5 Fixed fire-extinguishing systems not 5.6.7 Portable fire-extinguishers in accommodation


spaces, service spaces and control stations
required by this section
Accommodation spaces, service spaces and control stations
5.5.1 If such a system is installed, it should be of an should be provided with a sufficient number of portable fire-
approved type. extinguishers to ensure that at least one extinguisher will be
readily available for use in every compartment of the crew
5.6 Portable Fire-extinguishers spaces. In any case, their number should be not less than
three, except where this is impractical for very small tugs, in
5.6.1 Number of portable fire-extinguishers which case one extinguisher should be available at each deck
The number of portable fire-extinguisher is defined in Tab 3. having accommodation or service spaces, or control stations.

July 2014 Bureau Veritas 31


NI 617, Sec 4

6 Fire-fighting equipment Table 4 : Language in fire control plan

Service notations Language


6.1 General tug, escort tug (unrestricted) English
harbour tug Official language(s) of the
6.1.1 The fire-fighting equipment should comply with the tug, escort tug with addi- Administration(s) concerned
minimum requirements as specified below: tional service feature sailing with the tugs service, or lan-
time 4 h from safe shel- guage(s) recognized by such
tered anchorage Administration(s) (possibly
6.2 Fire-fighters outfit (which includes an English).
axe) However, description in such
plans and booklets for tugs
engaged in domestic service
6.2.1 Except for harbour tugs, at least one fire-fighters out-
only may be in the official
fit complying with the Requirements of the IMO FSS Code, language of the Flag State
should be provided on board. only.

6.3.4 In general, on all tugs greater than or equal to 150


6.3 Description of fire control plans GT, a duplicate set of fire-control plans or a booklet con-
taining such plans should be permanently stored in a prom-
6.3.1 In all tugs, general arrangement plans should be per- inently marked weather tight enclosure outside the
manently exhibited for the guidance of the tug's officers, deckhouse for the assistance of shoreside fire fighting per-
using graphical symbols that are in accordance with IMO sonnel.
Resolution A.952(23), which show clearly for each deck the
6.3.5 For service notation harbour tug a duplicate set of the
control stations, the various fire sections enclosed by steel
fire-control plan may be stored at a shore side facility.
or A Class divisions, together with particulars of:

The fire detection and fire-alarm systems 7 Alternative design and arrangements
Fixed fire-fighting system for fire safety
The fire-extinguishing appliances 7.1 Purpose
The means of access to different compartments, decks,
7.1.1 The purpose of this recommendation should provide
etc. a methodology for alternative design and arrangements for
The position of the fireman's outfits fire safety.

The ventilating system, including particulars of the fan 7.2 General


control positions, the position of dampers and identifi-
cation numbers of the ventilating fans serving each sec- 7.2.1 Fire safety design and arrangements may deviate from
tion, and [2] to [7] of this section, provided that the design and
arrangements meet the fire safety objectives and the func-
The location and arrangement of the emergency stop for tional Recommendations.
the oil fuel unit pumps and for closing the valves on the
pipes from oil fuel tanks. 7.2.2 When fire safety design or arrangements deviate from
the requirements of this section, engineering analysis, eval-
uation and approval of the alternative design and arrange-
6.3.2 Alternatively, the details required by [6.3.1] may be
ments should be carried out in accordance with this
set out in a booklet, a copy of which should be supplied to regulation.
each officer, and one copy is at all times to be available on
Note 1: Reference can be made to MSC/Circ.1002 "Guidelines on
board in an accessible position. alternative design and arrangements for fire safety".

6.3.3 The plans and booklets should be kept up to date, 7.3 Engineering analysis
any alterations being recorded thereon as soon as practica-
ble. Description in such plans and booklets should be in the 7.3.1 The engineering analysis should be prepared and
official language of the Flag State and in the language as submitted to the Society, based on the guidelines developed
shown in the following Tab 4. In addition, instructions con- by the International Maritime Organization and should
include, as a minimum, the following elements:
cerning the maintenance and operation of all the equip-
ment and installations on board for the fighting and a) determination of the tug type and space(s) concerned
containment of fire should be kept under one cover, readily b) identification of recommendation(s) with which the tug
available in an accessible position. or the space(s) will not comply

32 Bureau Veritas July 2014


NI 617, Sec 4

c) identification of the fire and explosion hazards of the f) technical justification demonstrating that the alternative
tug or the space(s) concerned: design and arrangements meet the required fire safety
identification of the possible ignition sources performance criteria.
identification of the fire growth potential of each
space concerned 7.4 Evaluation of the alternative design and
identification of the smoke and toxic effluent gener- arrangements
ation potential for each space concerned
identification of the potential for the spread of fire, 7.4.1 The engineering analysis required in [7.3] should be
smoke or of toxic effluents from the space(s) con- evaluated and approved by the Society taking into account
cerned to other spaces the guidelines developed by the International Maritime
Organization.
d) determination of the required fire safety performance
criteria for the tug or the space(s) concerned: 7.4.2 A copy of the documentation, as approved by the
performance criteria should be based on the fire Society, indicating that the alternative design and arrange-
safety objectives and on the functional Recommen- ments comply with this regulation should be carried on
dations of this section board the tug.
performance criteria should provide a degree of
safety not less than that achieved the recommenda- 7.5 Re-evaluation due to change of condi-
tion in [2] to [7], and
tions
performance criteria should be quantifiable and
measurable 7.5.1 If the assumptions, and operational restrictions that
e) detailed description of the alternative design and were stipulated in the alternative design and arrangements
arrangements, including a list of the assumptions used are changed, the engineering analysis should be carried out
in the design and any proposed operational restrictions under the changed condition and should be approved by
or conditions, and the Society.

July 2014 Bureau Veritas 33


NI 617, Sec 5

SECTION 5 LIFE SAVING APPLIANCES FOR TUGS OF LESS


THAN 500 GT

1 General 1.2 Requirements for life saving appliances


1.2.1 Requirements for life saving appliances are defined in
1.1 Scope of application Tab 1.
1.1.1 This section applies to tugs of less than 500 GT. 1.2.2 The equipment specified in Tab 1 should comply
with the IMO Life Saving Appliances Code or specified oth-
erwise by the Administration.

Table 1 : Life saving appliances

tug / escort tug harbour tug


sailing time 4h from a
(unrestricted) (in port)
safe sheltered anchorage
life rafts
100% capacity on each side / easy side to side transfer,
or X X (1)
150% capacity on each side
hydrostatic releases X X (1)
Illumination and operating instructions X X (1)
MOB arrangement
rescue boat X (2) X (2)
Jasons cradle X X X
search light X X X
Lifebuoys
with smoke/light 2 1 1
with light 1 1 1
with lifeline 1 1 1
lifejackets with lights
each person on board X X X
immersion suit
each person on board X (3) X (3)
other equipment
rocket parachute flares 12 6
red hand flares 6 2 2
smoke signals 2 buoyant 2 2
line throwing apparatus 1 1
general alarm X X X
(1) A float free buoyant apparatus is to be provided.
(2) The tugs operational working area, manoeuvrability, size, freeboard and propulsion arrangement may be taken into considera-
tion for the evaluation of the applicability of the requirement for a rescue boat.
(3) If the tug is constantly engaged in warm climates (refer to MSC Circ.1046) where, in the opinion of the Administration thermal
protection is unnecessary, immersion suits need not be carried on board.
(4) An illustrated table describing the life saving signals shall be readily available to the officer of the watch of every tug to all tugs
on all voyages. The signals shall be used by tugs or persons in distress when communicating with life-saving stations, maritime
rescue units and aircraft engaged in search and rescue operations.

34 Bureau Veritas July 2014


NI 617, Sec 5

tug / escort tug harbour tug


sailing time 4h from a
(unrestricted) (in port)
safe sheltered anchorage
communication system
to engine room / accommodation / deck X X X
documentation on board
fire and safety plan X X X
training and instruction manual X X X
SOLAS life saving table (4) X X X
muster list and emergency instructions X X X
(1) A float free buoyant apparatus is to be provided.
(2) The tugs operational working area, manoeuvrability, size, freeboard and propulsion arrangement may be taken into considera-
tion for the evaluation of the applicability of the requirement for a rescue boat.
(3) If the tug is constantly engaged in warm climates (refer to MSC Circ.1046) where, in the opinion of the Administration thermal
protection is unnecessary, immersion suits need not be carried on board.
(4) An illustrated table describing the life saving signals shall be readily available to the officer of the watch of every tug to all tugs
on all voyages. The signals shall be used by tugs or persons in distress when communicating with life-saving stations, maritime
rescue units and aircraft engaged in search and rescue operations.

July 2014 Bureau Veritas 35


NI 617, Sec 6

SECTION 6 RADIO INSTALLATIONS FOR TUGS OF LESS THAN


300 GT

1 General 1.2 Requirements for radio installations


1.2.1 Requirements for radio installations are defined in
1.1 Scope of application Tab 1.
1.1.1 This section applies to tugs of less than 300 GT.

Table 1 : Radio installations

tug / escort tug harbour tug


sailing time 4h from a
(unrestricted) (in port)
safe sheltered anchorage
general requirements
300 gt SOLAS (A1+A2+A3+A4, as applicable) X X X
< 300 gt no duplication of equipment required X X X
specific requirements
VHF / DSC 1 1 1
SART (1) 1 1 1
EPIRB / satellite 1 1 (A2+A3)
EPIRB / VHF 1 (A1)
NAVTEX 1 1
MF / DSC 1 (2)
INMARSAT C 1 (2)
GMDSS porto 1 1
electrical power supply 1 1 1
(1) SART is not required if the 406 MHZ EPIRB provided has a 121.5 MHz frequency transmitting capability and is of the non-float
free type for placing in a life raft.
(2) MF / DSC or INMARSAT C depending on region.

36 Bureau Veritas July 2014


NI 617, Sec 7

SECTION 7 NAVIGATION EQUIPMENT FOR TUGS OF LESS


THAN 500 GT

1 General 1.2 Requirements for navigation equipment


1.2.1 Requirements for navigation equipment are defined
1.1 Scope of application in Tab 1.
1.1.1 This section applies to tugs of less than 500 GT.

Table 1 : Navigation equipment

tug / escort tug harbour tug


sailing time 4h from a
(unrestricted) (in port)
safe sheltered anchorage
general requirements
SOLAS Ch V is to be taken into account for all tugs on all voyages
The administration shall determine to what extent the provisions of
SOLAS Ch V do not apply to the following tugs: X X X
tugs below 150 gt on any voyage
tugs below 150 gt not engaged on international voyages (1)
specific requirements
radar 1 1
magnetic compass 1 (2) 1 (2) 1
gyro compass 1 (2) 1 (2)
GPS compass 1 (2) 1 (2)
GPS 2 1 1
AIS 1 1 1
nautical charts / ECDIS 1 1 1
daylight signalling lamp 1 1 1
echo sounding 1 1 1
IAMSAR 1 1 1
code of signals 1 1 1
(1) International voyage: voyage from a country to which the SOLAS Convention applies to a port outside such country, or conversely.
(2) Optional 2 out of 3

July 2014 Bureau Veritas 37


NI 617, Sec 8

SECTION 8 HULL OUTFITTING

1 Anchoring equipment where:


a : Distance, in m, from the summer
1.1 Equipment number load waterline amidships to the
upper deck
1.1.1 The Equipment Number EN is to be obtained from
the following formula: hi : Height, in m, on the centreline of
23
each tier of houses having a breadth
EN = + 2, 0 hB + A 10 greater than B/4.
where:
: Moulded displacement of the tug, in t, to the 1.1.2 The equipment length, in m, is the length between
summer load waterline perpendiculars but is not to be less than 96% nor greater
B : Moulded breadth, in m than 97% of the extreme length on the summer load water-
line (measured from the forward end of the waterline).
A : Area, in m2, in profile view, of the hull, super-
structures and houses above the summer load
waterline which are within the equipment 1.1.3 All tugs are to be provided with equipment in
length of the tug and also have a breadth greater anchors and chain cables, or wire ropes according to [1.2],
than B/4 to be obtained from Tab 1 and Tab 2, as applicable, based
on their Equipment Number EN. For tugs with restricted
h : Effective height, in m, from the summer load
navigation the equipment in anchors and chain cables may
waterline to the top of the uppermost house; for
be reduced. For tugs with navigation notation coastal area
the lowest tier h is to be measured at cen-
the reduction comprises of entering in Tab 1 and Tab 2, as
treline from the upper deck or from a notional
applicable, one line higher, while for tugs with navigation
deck line where there is local discontinuity in
notation sheltered area the reduction comprises of entering
the upper deck.
in Tab 1and Tab 2, as applicable, two lines higher, as based
h = a + h i on their calculated Equipment Number EN

Table 1 : Equipment for EN 205

Stockless bower anchors Stud link chain cable for bower anchors
Minimum diameter
E.N Total length (m)
No Mass per anchor (kg) Mild steel Special quality Extra special quality
(1)
Gr. 1 (mm) Gr. 2 (mm) Gr. 3 (mm)
205-240 3 660 302,5 26 22 20,5
240-280 3 780 330 28 24 22
280-320 3 900 357,5 30 26 24
320-360 3 1020 357,5 32 28 24
360-400 3 1140 385 34 30 26
400-450 3 1290 385 36 32 28
450-500 3 1440 412,5 38 34 30
500-550 3 1590 412,5 40 34 30
550-600 3 1740 440 42 36 32
600-660 3 1920 440 44 38 34
660-720 3 2100 440 46 40 36
720-780 3 2280 467,5 48 42 36
780-840 3 2460 467,5 50 44 38
840-910 3 2640 467,5 52 46 40
910-980 3 2850 495 54 48 42
980-1060 3 3060 495 56 50 44
1060-1140 3 3300 495 58 50 46
1140-1220 3 3540 522,5 60 52 46

38 Bureau Veritas July 2014


NI 617, Sec 8

Stockless bower anchors Stud link chain cable for bower anchors
Minimum diameter
E.N Total length (m)
No Mass per anchor (kg) Mild steel Special quality Extra special quality
(1)
Gr. 1 (mm) Gr. 2 (mm) Gr. 3 (mm)
1220-1300 3 3780 522,5 62 54 48
1300-1390 3 4050 522,5 64 56 50
1390-1480 3 4320 550 66 58 50
1480-1570 3 4590 550 68 60 52
1570-1670 3 4890 550 70 62 54
1670-1790 3 5250 577,5 73 64 56
1790-1930 3 5610 577,5 76 66 58
1930-2080 3 6000 577,5 78 68 60
2080-2230 3 6450 605 81 70 62
2230-2380 3 6900 605 84 73 64
2380-2530 3 7350 605 87 76 66
2530-2700 3 7800 632,5 90 78 68
2700-2870 3 8300 632,5 92 81 70
2870-3040 3 8700 632,5 95 84 73
3040-3210 3 9300 660 97 84 76
3210-3400 3 9900 660 100 87 78
3400-3600 3 10500 660 102 90 78
3600-3800 3 11100 687,5 105 92 81
3800-4000 3 11700 687,5 107 95 84
4000-4200 3 12300 687,5 111 97 87
4200-4400 3 12900 715 114 100 87
4400-4600 3 13500 715 117 102 90
4600-4800 3 14100 715 120 105 92
4800-5000 3 14700 742,5 122 107 95
5000-5200 3 15400 742,5 124 111 97
5200-5500 3 16100 742,5 127 111 97
5500-5800 3 16900 742,5 130 114 100
5800-6100 3 17800 742,5 132 117 102
6100-6500 3 18800 742,5 120 107
6500-6900 3 20000 770 124 111
6900-7400 3 21500 770 127 114
7400-7900 3 23000 770 132 117
7900-8400 3 24500 770 137 122
8400-8900 3 26000 770 142 127
8900-9400 3 27500 770 147 132
9400-10000 3 29000 770 152 132
10000-10700 3 31000 770 137
10700-11500 3 33000 770 142
11500-12400 3 35500 770 147
12400-13400 3 38500 770 152
13400-14600 3 42000 770 157
14600-16000 3 46000 770 162
(1) The total length of chain is to be divided in approximately equal parts between the two bower anchors.
Note 1: Two bower anchors of the three bower anchors under col. 2 of Tab 1 are to be connected to their cables and positioned on
board ready for use while the third anchor is intended as a spare bower anchor. Installation of the spare bower anchor on board is not
compulsorily required.

July 2014 Bureau Veritas 39


NI 617, Sec 8

Table 2 : Equipment for EN < 205

Stockless bower anchors Stud link chain cable for bower anchors Stream wire or chain
Minimum diameter
E.N Mass per anchor Stock-less stream Total length Length Breaking
No Mild steel Special quality
(kg) anchor (kg) (m) (1) (m) strength (kN)
Gr. 1 (mm) Gr. 2 or 3 (mm)
50-70 2 180 60 220 14,0 12,5 80 65
70-90 2 240 80 220 16,0 14,0 85 75
90-110 2 300 100 247,5 17,5 16,0 85 80
110-130 2 360 120 247,5 19,0 17,5 90 90
130-150 2 420 140 275 20,5 17,5 90 100
150-175 2 480 165 275 22,0 19,0 90 110
175-205 2 570 190 302,5 24,0 20,5 90 120
(1) The total length of chain is to be divided in approximately equal parts between the two bower anchors.

1.2 Wire ropes K : Coefficient depending on the service notation


and optional additional service feature, as
1.2.1 Wire ropes may be used as an alternative two chain shown in Tab 3.
cables as follows:
Table 3 : Equipment coefficient K
Where L < 30 m, may be replaced with wire ropes of
equal minimum breaking strength, which should:
service notation additional service feature K
Have a length 1.5 times that for chain cable required
by Tab 1, and harbour tug - 1.20

Have a short length of Grade 2/1 chain cable is to be tug sailing time 4 h from safe 1.20
fitted between the wire rope and the anchor, having sheltered anchorage
a length equal to 12.5 m or the distance from the tug - 1.30
anchor in the stowed position to the winch, which-
ever is the lesser escort tug sailing time 4 h from safe 1.20
sheltered anchorage
Where 30 m L 40 m one chain cable may be
replaced with wire rope meeting the requirements of L > escort tug - 1.30
40 m, while the other chain cable may be replaced with
wire rope meeting the requirements of L < 30 m 1.4 Number of anchors
Where 40 m < L 90 m, both chain cables may be 1.4.1 Tugs are to be provided with equipment in stockless
replaced with wire rope of equal minimum breaking anchors, chain cables and/or wire ropes. This equipment is
strength which should: to be obtained as a function of the Equipment Number EN.
Have a length 1.5 times that for chain cable required The number of anchors, as obtained from the equipment
by Tab 1, and table depends on the service notation and optional addi-
Have a minimum mass per unit length of 30% that tional service feature, the propulsion arrangement and the
of Grade 2 chain cable required by Tab 1, and application of a fixed fire fighting installation. In general,
the recommended number of anchors and chain cables is
Have a short length of chain cable is to be fitted shown in Tab 4.
between the wire rope and the anchor, having a
length equal to 12,5 m or the distance from the Table 4 : Number of anchors and chain cables
anchor in the stowed position to the winch, which-
ever is the lesser. service notation additional service feature Nr
harbour tug - 1
1.3 Tugs of less than 500 GT
tug sailing time 4 h from safe 2
1.3.1 For tugs of less than 500 GT, the EN may be obtained sheltered anchorage
from the following simplified formula: tug - 2
23
EN = K ( LBD ) escort tug sailing time 4 h from safe 2
sheltered anchorage
where:
D : Moulded depth, in m escort tug - 2

40 Bureau Veritas July 2014


NI 617, Sec 8

1.4.2 A reduction of the number of anchors and chain 1.5.4 The mass of the head, including pins and fittings, of
cables can be accepted as depicted in Tab 5 if the following an ordinary stockless anchor is to be not less than 60 per
conditions, based on redundancy principles, are complied cent of the total mass of the anchor.
with:
The tug is equipped with at least twin propulsion, of 1.5.5 When stocked bower or stream anchors are to be
which each main engine can maintain sufficient propul- used, the mass ex-stock is to be not less than 80 per cent
sion power to safely return to berth. For this purpose, of the mass given in Tab 1 and Tab 2, as applicable, for ordi-
the main engines should be able to run self-supporting, nary stockless bower anchors. The mass of the stock is to be
i.e. independent of generator sets intended for auxiliary 25 per cent of the total mass of the anchor, including the
power, unless these are able to run parallel and, in case shackle, etc., but excluding the stock.
of black-out, have automatic starting and connecting to
switchboard within 45 seconds
1.6 High holding power anchors
A single failure, except fire, should not cause total pro-
pulsion failure 1.6.1 Anchors of designs for which approval is sought as
A fixed fire fighting installation is provided. high holding power anchors are to be tested at sea to show
that they have holding powers of at least twice those of
1.4.3 It may be considered by the tug builder and operator approved standard stockless anchors of the same mass.
to apply a spare anchor as an alternative to a second bower
anchor. In such case special provisions, such as a crane and 1.6.2 If approval is sought for a range of sizes, then at least
suitable storage space for the spare anchor, are to be two sizes are to be tested. The smaller of the two anchors is
present on board and the weight and dimensions of the to have a mass not less than one-tenth of that of the larger
anchor are to be such that it can be handled swiftly. For tugs anchor, and the larger of the two anchors tested is to have a
with the additional service features sailing time 4 h from a mass not less than one tenth of that of the largest anchor for
safe sheltered anchorage, effectively operating in a fixed which approval is sought.
and limited area, the spare anchor may be stored ashore.
1.6.3 The tests are to be conducted on not less than three
Table 5 : Reduced number of anchors and chain different types of bottom, which should normally be soft
cables based on redundancy principles mud or silt, sand or gravel, and hard clay or similarly com-
pacted material.
service notation additional service feature Nr
harbour tug - 0 1.6.4 The test should normally be carried out from a tug,
tug sailing time 4 h from safe shel- 1 and the pull measured by dynamometer or derived from
tered anchorage recently verified curves of tug rev/min against bollard pull.
A scope of 10 is recommended for the anchor cable, which
tug (unrestricted) 2
may be wire rope for this test, but in no case should a scope
escort tug sailing time 4 h from safe shel- 1 of less than 6 be used. The same scope is to be used for the
tered anchorage anchor for which approval is sought and the anchor that is
escort tug (unrestricted) 2 being used for comparison purposes.

1.5 Anchors 1.6.5 High holding power anchors are to be of a design


that will ensure that the anchors will take effective hold of
1.5.1 Anchors are to be of an approved design. The design the sea bed without undue delay and will remain stable, for
of all anchor heads is to be such as to minimize stress con- holding forces up to those required in this section, irrespec-
centrations, and in particular, the radii on all parts of cast tive of the angle or position at which they first settle on the
anchor heads are to be as large as possible, especially sea bed when dropped from a normal type of hawse pipe.
where there is considerable change of section. In case of doubt, a demonstration of these abilities may be
required.
1.5.2 Anchors which must be specially laid the right way
up, or which require the fluke angle or profile to be 1.6.6 When high holding power anchors are used as bower
adjusted for varying types of sea bed, will not generally be anchors, the mass of each such anchor may be 75 per cent
approved for normal ship use, but may be accepted for off- of the mass given in the Tab 1 and Tab 2, as applicable, for
shore units, floating cranes, etc. In such cases suitable tests ordinary stockless bower anchors.
may be required.

1.5.3 The mass of each bower anchor given in Tab 1 and 1.7 Chain cables
Tab 2, as applicable, is for anchors of equal mass. The
masses of individual anchors may vary by 7 per cent of 1.7.1 Chain cables may be of mild steel, special quality
the masses given in the Table, provided that the total mass steel or extra quality steel in accordance with the require-
of the anchors is not less than would have been required for ments of Rules for Materials and are to be graded in accord-
anchors of equal mass. ance with Tab 6.

July 2014 Bureau Veritas 41


NI 617, Sec 8

Table 6 : Grades of chain cables ing power anchors. Grade 3 material is to be used only for
chain 20,5 mm or more in diameter.
Range of UTS
Material Grade 1.7.4 Where stream anchors are used in association with
(N/mm2)
chain cable, this cable may be either stud link or short link.
Mild steel 1 300 to 490
Special quality steel 2 460 to 690 1.7.5 The form and proportion of links and shackles are to
be in accordance with the Rules for Materials.
Extra special quality steel 3 > 690

1.7.2 The designation Grade 1 may be replaced, at dis- 1.8 Water depths greater than 82,5 m
cretion of the Society, by Grade 1a where UTS is greater
than but not exceeding 400 N/mm2 or by Grade 1b where 1.8.1 Where Owners require equipment for anchoring at
UTS is greater than 400 but not exceeding 490 N/mm2. depths greater than 82,5 m, it is their responsibility to spec-
ify the appropriate total length of the chain cable required
1.7.3 Grade 1 material having a tensile stress of less than for this purpose. In such cases, consideration can be given
400 N/mm2 is not to be used in association with high hold- to dividing the chain cable into two unequal lengths.

42 Bureau Veritas July 2014


NI 617, Sec 9

SECTION 9 ASSISTED SHIP

1 Towing fittings 1.1.7 Given the scope of application of IACS UR A2, care-
ful consideration is to be given to towing fittings to be used
for offshore towage and escorting operations.
1.1 General
Note 1: In accordance with IACS UR A1, A1.1.1, the anchoring
equipment required herewith is intended for temporary mooring of
1.1.1 The assisted ship towing equipment is regulated by a vessel within a harbour or sheltered area when the vessel is
the following documents: awaiting berth, tide, etc. In accordance with A1.1.2, the equipment
is therefore not designed to hold a ship off fully exposed coasts in
SOLAS Regulation II-1/3-8 Towing and mooring equip- rough weather or to stop a ship which is moving or drifting. In this
ment condition the loads on the anchoring equipment increase to such a
degree that its components may be damaged or lost owing to the
IACS UR A2 Requirement concerning mooring, anchor- high energy forces generated, particularly in large ships
ing and towing
For towing operations in waves, due to dynamic effects, the
Classification Society Rules maximum towline force may be expected to exceed the
maximum (static) bollard pull by more than 25 per cent (as
OCIMF Mooring Equipment Guidelines (can be used for considered in the UR A2), in which case a higher SWL of
design purposes). the towing fittings on the assisted ship would be required.
For offshore escort operations similar considerations apply
1.1.2 For emergency towing arrangements, ships subjected with respect to dynamic effects.
to SOLAS Regulation II-1/3-4 are to comply with that regu-
lation and resolution MSC.35(63). In case offshore towing and escort operations are envis-
aged, it is recommended to apply the Design Load (DL)
specified in Sec 3, Tab 1 and Sec 3, Tab 3, as applicable, for
1.1.3 Reference is made to IACS UR A2 "Shipboard fittings the towing fittings on the assisted ship.
and supporting hull structures associated with towing and
mooring on conventional vessels".
2 Side structure
1.1.4 For towage and manoeuvring in port the Design Load
(DL) for towing fittings on the assisted ship is the load
2.1 General
exerted on the considered fitting under the action of the
towline loaded under a tension equal to 1.25 times the
maximum Bollard Pull (BP), as defined in Sec 1, [4.1], in 2.1.1 To ensure the integrity of the assisted ship side struc-
the most unfavourable anticipated position of the towline. ture during pushing operations, it is recommended that the
pushing forces exerted by the tug are applied on a locally
Note 1: Reference is made to IACS UR A2, Sec A.2.1.3. reinforced side structure of the assisted ship (towing push
point or area).
1.1.5 The associated Safe Working Load (SWL) is not to The maximum applied load (in terms of force and pressure)
exceed 80 per cent of the Design Load (DL). by the tug on the assisted ship side structure is to be less
Note 1: Reference is made to IACS UR A2, Sec A.2.1.6.
than the design load for that part of the structure.

The strength and size of the reinforced areas of the assisted


1.1.6 For escort towage the Design Load (DL) for towing fit- ships side structure should be designed to take in account
tings on the assisted ship is the load exerted on the consid- tug motions.
ered fitting under the action of the towline loaded under a
tension equal to towline breaking strength according to the It is recommended to consider the Design Load (DL) speci-
IACS Recommendation No 10 "Equipment" for the ships fied in Sec 3, [1.9] for the design of the push points/area of
corresponding EN is to be applied, in the most unfavourable the assisted ship (in combination with a suitable contact
anticipated position of the towline. area).

Note 1: Reference is made to IACS UR A2, Sec A.2.1.3. 2.1.2 Tug push points/areas should be clearly marked.
The associated Safe Working Load (SWL) is not to exceed
the Design Load (DL). 2.1.3 The strength characteristics of the assisted ship side
structure (maximum pushing force and pressure) should be
Note 2: Reference is made to IACS UR A2, Sec A.2.1.6. communicated between the tug and the assisted ship.

July 2014 Bureau Veritas 43


NI 617, Sec 9

3 Making fast no (or limited) reserve power, which reduces the tugs abil-
ity to escape from a critical situation.
3.1 General It is recommended to explicitly address during the design
stage (of the assisted ship) the minimum speed through the
3.1.1 It is recognised that large and fast ships, in particular
water (propulsion configuration) as well as the proper loca-
container ships, with high main engine power enter ports at
tion and strength of the towing fittings (bollards, fairleads,
relatively high minimum speeds of 6 up to 11 kn through
etc.) in relation to connecting to a tug.
the water and, consequently, that making fast by tugs would
have to be performed at speeds close to the tugs maximum Tug owners/operators and port authorities are recom-
speed (typically 11 to 12 kn). mended to specify an appropriate maximum speed for mer-
It is also recognised that making fast at high speed incorpo- chant ships in relation to making fast of tugs.
rates risk for the tug and its crew. Increased ships speed
leads to stronger water flows between and around the ships 3.1.2 The maximum speed and procedure for making fast
and hence increases the risk of collision. In addition, at should be communicated between the tug(s) and assisted
speeds close to the tugs maximum speed the engines have ship.

44 Bureau Veritas July 2014

Você também pode gostar