Escolar Documentos
Profissional Documentos
Cultura Documentos
Chapter 4 - Manual Mine Clearance 30 Jun 07
Chapter 4 - Manual Mine Clearance 30 Jun 07
1.1 Humanitarian demining techniques used during each project may differ
according to equipment, the terrain, type of mines / UXO, etc. All procedures used
in clearance operations are to be fully explained in step-by-step detail in the mine
action organisations SOP. The following are established humanitarian demining
clearance procedures and although, certain techniques may vary between mine
action organisations, these shall be recognised as the minimum standard required
by the UNMAO in Sudan.
Page 1 of 9
NTSG, Part 1, Edition 8, Version 2
Chapter 4
Page 2 of 9
NTSG, Part 1, Edition 8, Version 2
Chapter 4
Cleared Max 50 cm
Max 40cm
1m Uncleared
Area
Progression
of lane
10-50cm
Overlap
Page 3 of 9
NTSG, Part 1, Edition 8, Version 2
Chapter 4
Detector
Signal
Isolation Maximum 50 cm
Markers
Signal
Marker
1m Uncleared
Area
Progression
of lane
h. Prodding & Excavation: Once the precise location of the signal has
been identified using the metal detector, the source of the signal shall be
investigated to identify it. This shall be done by prodding and/or excavating
(1) Prodding shall commence a minimum of ten centimetres back
from the nearest point of the signal and to the required width, which, is
dependent on the size of the signal. All prodding is to be at an angle
</> than thirty degrees and at maximum intervals of two point five
centimetres. The prodder is to be used with an even motion, avoiding
any excessive force or stabbing. The depth prodded shall be
dependent on the ground conditions, search depth and tool design. If it
is not possible to conduct prodding from the surface of the ground to
the required search depth, then a certain amount of excavation shall be
conducted in order to achieve the required prodding depth.
Alternatively, the prodding procedure may be replaced with excavation
(sapping) only. In hard ground, resulting from extremely dry conditions,
water could be used to soften the ground before prodding commences.
(2) Excavation (Sapping) is used to reveal the identity/source of the
signal. A hole is dug a minimum of ten centimetres back from the
nearest point of the signal to a minimum depth of fifteen centimetres.
The trowel (or similar tool) is used to slowly remove the soil towards
the location of the source of the signal. Any excessive pressure and
Page 4 of 9
NTSG, Part 1, Edition 8, Version 2
Chapter 4
abrupt movements with the trowel shall be avoided. The prodder may
also be used in conjunction with the excavation process.
If an object is not located after using the prodder and excavation to the
required depth, the Supervisor will decide whether further investigation is
required.
i. Action on Locating Metal The metal shall be carefully removed from the
ground and placed it in the metal contamination pit. The area where the
metal was removed from shall be checked visually and with the metal
detector for additional signals, prior to moving forward.
j. Action on Locating Mines/UXO The deminer shall stop mine clearance
activities, place a mine marker a minimum ten centimetres before the
mine/UXO and notify the supervisor through the chain of command. The
supervisor is responsible for ensuring all actions relating to the removal or
destruction of the mine/UXO in situ are carried out correctly and by a
qualified EOD operator. The lane may be cordoned and mine clearance
activities started in a new lane. No personnel shall be allowed past a located
mine/UXO in a one metre wide clearance lane. In circumstances where the
mine/UXO is not destroyed or removed immediately, the deminer shall be
moved to an alternative lane or clearance shall be conducted to safely by-
pass the mine/UXO. No mine clearance should be conducted within fifty
metres of a located mine/UXO.
Min 10 cm
Mine Marker
Where mines/UXO are not destroyed on the day that they are found,
they are to be accurately reported in the organisations daily clearance
log and destroyed as soon as possible. If they are not destroyed by the
end of the working week, the organisation is to ensure they are
included on the weekly progress report for the task submitted to the
UNRMAO and an explanation given.
l. Action on Locating a Tripwire The deminer shall stop mine clearance
activity and place 3 x small red stones a minimum of ten centimetres before
and in the direction of the trip wire (see Figure 4.4) and then notify the
supervisor. The supervisor is responsible for ensuring that both ends of the
tripwire are located and appropriate action is taken depending on what is
found at each end. It is stressed that the method employed in tracing the
tripwire should at all times ensure that deminers tasked do not become
isolated. Conditions should always allow for swift, safe and effective
Casevac to be conducted should an accident occur. Whilst tracing a tripwire
there shall be no other activities within fifty metres.
10cm
Page 6 of 9
NTSG, Part 1, Edition 8, Version 2
Chapter 4
Page 7 of 9
NTSG, Part 1, Edition 8, Version 2
Chapter 4
n. High Metallic Areas In areas where the metallic content of the soil is
high, the metal detector may be ineffective. The detector procedure shall be
replaced with a complete prodding and/or excavating procedure to ensure
that all mines/UXO are located to the required depth. The minimum depth to
be excavated is 15 centimetres and the complete width of the one metre
wide lane shall be investigated to this depth. The detector should be used
to regularly check the soil contamination level and confirm whether the
complete prodding and excavation process can be replaced with the
detector procedure. Alternatively, mark the boundary of the high metallic
area for clearance by MDD or mechanical means. The size of the area, type
of terrain and the availability of alternative clearance assets will determine
the most efficient method of clearance to use.
o. Mountainous and Rocky Terrain In areas where the ground is
mountainous and rocky, there may be a requirement to remove rocks (E.g.,
physical hazard, suspicion that a mine/UXO is beneath the rocks, ghost
signal). Therefore, the Supervisor shall make a decision on the best
clearance method(s) (E.g., lifting, detector search, prodding and/or
excavation, pulling drill). When removing rocks by hand, caution shall be
made so as to avoid disturbing the ground and the rocks should be lifted
vertically.
p. Clearance of Obstacles During the clearance of minefields, obstacles
should be identified and special clearance drills adopted as required. (E.g.,
sapping, pulling, EOD).Those obstacles that cannot be cleared immediately
are to be marked and if necessary fenced for future clearance operations.
The supervisor on site must give consideration to the approach and
clearance method used for each type of obstacle encountered.
q. Burning of Vegetation in Unclear Areas Burning of unclear areas may
be conducted in order to remove vegetation to facilitate mine clearance
operations. Prior to commencing burning, the organisation concerned shall
liaise with the UNMAO and local authorities. Caution must be exercised by
the organisation and the burning must be controlled in order to prevent the
undesired burning of other areas and cause an unacceptable risk to the
local population. The results from burning must be considered, such as, the
altered state and instability of mines and UXO. Any demining organisation
conduct burning of unclear areas is to ensure that the following precautions
are adhered to:
(1) Inform the UNMAO and local authorities.
(2) If possible, inform the local emergency fire services.
(3) If necessary, construct a firebreak to prevent the fire from
spreading.
(4) Ensure that adequate precautions are taken to extinguish any
small fires in cleared areas. (eg, fire extinguishers, sand).
(5) Calculate the blast / fragmentation safety distance depending on
the threat (eg, mines/UXO) and post sentries accordingly.
(6) Inform the UNMAO and relevant authorities on completion of
burning.
(7) Allow a 24 hour soak time, from the last signs of smoke before
conducting demining operations in the burned area.
Page 8 of 9
NTSG, Part 1, Edition 8, Version 2
Chapter 4
r. Working Hours A manual mine clearance deminer shall not work for
longer than sixty (60) minutes before taking a break of at least ten (10)
minutes. The working time may vary between organisations and specific
situations (eg, climate), however, the aforementioned times shall be
adhered to. A normal working day for a manual mine clearance deminer
shall not exceed 6 hours actual mine clearance work a day. In excessive
climatic conditions, the working hours may be reduced or the daily routine
changed. A safe and sensible approach shall be made by the demining
organisation supervisor in order to achieve the best possible mine clearance
results without compromising the safety of demining personnel.
Page 9 of 9
NTSG, Part 1, Edition 8, Version 2