Jumlah 50,335.50
Dibulatkan 50,336.00
M12 1M'PipaPVC4"(AW)
Pipapvc4" m' 1.2000 86,975.00 104,370.00
Pekerja org 0.0810 42,000.00 3,402.00
Tukangbatu org 0.1350 65,000.00 8,775.00
KepalaTukang org 0.0135 75,000.00 1,012.50
Mandor org 0.0041 80,000.00 328.00
Perlengkapan35%hargapipa lot 0.3500 104,370.00 36,529.50
Jumlah 154,417.00
Dibulatkan 154,417.00
M13 1M'PipaPVC3/4"(AW)
Pipapvc3/4" m' 1.2000 13,050.00 15,660.00
Pekerja org 0.0810 42,000.00 3,402.00
Tukangbatu org 0.1350 65,000.00 8,775.00
KepalaTukang org 0.0135 75,000.00 1,012.50
Mandor org 0.0041 80,000.00 328.00
Perlengkapan35%hargapipa lot 0.3500 15,660.00 5,481.00
Jumlah 34,658.50
Dibulatkan 34,659.00
M14 1BuahBakCucipiringStainlesssteel
Bakcucistainlesssteel+asesoris
bh 1.0000 397,800.00 397,800.00
lengkap
Pekerja org 0.0300 42,000.00 1,260.00
Tukangbatu org 0.3000 65,000.00 19,500.00
KepalaTukang org 0.0300 75,000.00 2,250.00
Mandor org 0.0015 80,000.00 120.00
Jumlah 420,930.00
Dibulatkan 420,930.00
M15 1BuahKran1/2"3/4"
Kranair bh 1.0000 40,900.00 40,900.00
Sealtape bh 0.0250 4,200.00 105.00
Pekerja org 0.0100 42,000.00 420.00
Tukangbatu org 0.1000 65,000.00 6,500.00
KepalaTukang org 0.0100 75,000.00 750.00
Mandor org 0.0050 80,000.00 400.00
Jumlah 49,075.00
Dibulatkan 49,075.00
M16 1BuahFloorDrain
Floordrain bh 1.0000 66,600.00 66,600.00
Pekerja org 0.0100 42,000.00 420.00
Tukangbatu org 0.1000 65,000.00 6,500.00
KepalaTukang org 0.0100 75,000.00 750.00
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm 4/7
5/28/2017 AnalisaHargaSatuanPekerjaanSanitasiSoftwareRAB
Copyright2015SoftwareRABRumah|XHTML|G1|G2|ValidRSS|PrivacyPolicy|Disclaimer|Contact
www.softwarerab.com
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm 7/7