No. URAIAN SAT VOLUME HARGASAT HARGA


(Rp) (Rp)
M01 1BuahClosetjongkokPorselenStandar
Closetjongkok bh 1.00 188,200.00 188,200.00
P.C(50gk) Kg 6.00 1,406.00 8,436.00
Pasirpasang m3 0.01 233,400.00 2,334.00
Pekerja org 1.0000 42,000.00 42,000.00
Tukangbatu org 1.5000 65,000.00 97,500.00
KepalaTukang org 1.5000 75,000.00 112,500.00
Mandor org 0.1600 80,000.00 12,800.00
Jumlah 463,770.00
Dibulatkan 463,770.00
M02 1BuahUrinoir
Urinoir bh 1.00 1,773,400.00 1,773,400.00
P.C(50gk) Kg 6.00 1,406.00 8,436.00
Pasirpasang m3 0.01 233,400.00 2,334.00
Pekerja org 1.0000 42,000.00 42,000.00
Tukangbatu org 1.0000 65,000.00 65,000.00
KepalaTukang org 0.1000 75,000.00 7,500.00
Mandor org 0.0010 80,000.00 80.00
Perlengkapan30%hargaurinoir lot 0.3000 1,773,400.00 532,020.00
Jumlah 2,430,770.00
Dibulatkan 2,430,770.00
M03 1BuahWastafel
wastafelstandar unit 1.00 1,012,700.00 1,012,700.00
P.C(50gk) Kg 6.00 1,406.00 8,436.00
Pasirpasang m3 0.01 233,400.00 2,334.00
Pekerja org 1.2000 42,000.00 50,400.00
Tukangbatu org 1.4500 65,000.00 94,250.00
KepalaTukang org 0.1500 75,000.00 11,250.00
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm 1/7
5/28/2017 AnalisaHargaSatuanPekerjaanSanitasiSoftwareRAB

Mandor org 0.1000 80,000.00 8,000.00


Perlengkapan12%hargawastafel lot 0.1200 1,773,400.00 212,808.00
Jumlah 1,400,178.00
Dibulatkan 1,400,178.00
M04 1BuahbakMandiFibreglassVolume0,30m3
Bakfibreglass0.60mx0.60m bh 1.00 255,300.00 255,300.00
Pekerja org 1.8000 42,000.00 75,600.00
Tukangbatu org 2.7000 65,000.00 175,500.00
KepalaTukang org 0.5400 75,000.00 40,500.00
Mandor org 0.1100 80,000.00 8,800.00
Perlengkapan18%hargabak lot 0.1800 255,300.00 45,954.00
Jumlah 601,654.00
Dibulatkan 601,654.00
M05 1M'SaluranAirLimbahBuisbetond=30cm60cm
Buisbeton30cm bh 1.10 61,700.00 67,870.00
Batamerah bh 25.00 775.00 19,375.00
P.C(50gk) Kg 10.300 1,406.00 14,481.80
Pasirpasang m3 0.061 233,400.00 14,237.40
Pasirurug m3 0.069 175,300.00 12,095.70
Pekerja org 0.3800 42,000.00 15,960.00
Tukangbatu org 0.1900 65,000.00 12,350.00
KepalaTukang org 0.0190 75,000.00 1,425.00
Mandor org 0.0190 80,000.00 1,520.00
Jumlah 159,314.90
Dibulatkan 159,315.00
M06 1BuahBakKontrolPasBataMerahUk(60x60)cm
Batamerah bh 186.00 775.00 144,150.00
P.C(50gk) Kg 114.000 1,406.00 160,284.00
Pasirpasang m3 0.184 233,400.00 42,945.60
Batupecah2/3 m3 0.033 211,100.00 6,966.30
Besibeton m3 4.850 16,500.00 80,025.00
Pasirbeton m3 0.120 255,400.00 30,648.00
Pekerja org 2.1600 42,000.00 90,720.00
Tukangbatu org 0.7200 65,000.00 46,800.00
KepalaTukang org 0.0720 75,000.00 5,400.00
Mandor org 0.1080 80,000.00 8,640.00
Tukanggali org 0.1000 42,000.00 4,200.00
Jumlah 620,778.90
Dibulatkan 620,779.00
M07 1BuahBakKontrolPasBataMerahUk(30x30)cm
Batamerah bh 53.00 775.00 41,075.00
P.C(50gk) Kg 44.000 1,406.00 61,864.00
Pasirpasang m3 0.070 233,400.00 16,338.00
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm 2/7
5/28/2017 AnalisaHargaSatuanPekerjaanSanitasiSoftwareRAB

Batupecah2/3 m3 0.070 211,100.00 14,777.00


Besibeton m3 1.600 16,500.00 26,400.00
Pasirbeton m3 0.060 255,400.00 15,324.00
Pekerja org 3.2000 42,000.00 134,400.00
Tukangbatu org 1.0150 65,000.00 65,975.00
KepalaTukang org 0.0015 75,000.00 112.50
Mandor org 0.0160 80,000.00 1,280.00
Jumlah 377,545.50
Dibulatkan 377,546.00
M08 1M'PipaPVC1/2"(AW)
Pipapvc1/2" m' 1.2000 10,025.00 12,030.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukangbatu org 0.0600 65,000.00 3,900.00
KepalaTukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan35%hargapipa lot 0.3500 12,030.00 4,210.50
Jumlah 22,246.50
Dibulatkan 22,247.00
M09 1M'PipaPVC1"(AW)
Pipapvc1" m' 1.2000 15,800.00 18,960.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukangbatu org 0.0600 65,000.00 3,900.00
KepalaTukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan35%hargapipa lot 0.3500 18,960.00 6,636.00
Jumlah 31,602.00
Dibulatkan 31,602.00
M10 1M'PipaPVC11/2"(AW)
Pipapvc11/2" m' 1.2000 26,475.00 31,770.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukangbatu org 0.0600 65,000.00 3,900.00
KepalaTukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan35%hargapipa lot 0.3500 31,770.00 11,119.50
Jumlah 48,895.50
Dibulatkan 48,896.00
M11 1M'PipaPVC2"(AW)
Pipapvc2" m' 1.2000 27,675.00 33,210.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukangbatu org 0.0600 65,000.00 3,900.00
KepalaTukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan35%hargapipa lot 0.3500 31,770.00 11,119.50
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm 3/7
5/28/2017 AnalisaHargaSatuanPekerjaanSanitasiSoftwareRAB

Jumlah 50,335.50
Dibulatkan 50,336.00
M12 1M'PipaPVC4"(AW)
Pipapvc4" m' 1.2000 86,975.00 104,370.00
Pekerja org 0.0810 42,000.00 3,402.00
Tukangbatu org 0.1350 65,000.00 8,775.00
KepalaTukang org 0.0135 75,000.00 1,012.50
Mandor org 0.0041 80,000.00 328.00
Perlengkapan35%hargapipa lot 0.3500 104,370.00 36,529.50
Jumlah 154,417.00
Dibulatkan 154,417.00
M13 1M'PipaPVC3/4"(AW)
Pipapvc3/4" m' 1.2000 13,050.00 15,660.00
Pekerja org 0.0810 42,000.00 3,402.00
Tukangbatu org 0.1350 65,000.00 8,775.00
KepalaTukang org 0.0135 75,000.00 1,012.50
Mandor org 0.0041 80,000.00 328.00
Perlengkapan35%hargapipa lot 0.3500 15,660.00 5,481.00
Jumlah 34,658.50
Dibulatkan 34,659.00
M14 1BuahBakCucipiringStainlesssteel
Bakcucistainlesssteel+asesoris
bh 1.0000 397,800.00 397,800.00
lengkap
Pekerja org 0.0300 42,000.00 1,260.00
Tukangbatu org 0.3000 65,000.00 19,500.00
KepalaTukang org 0.0300 75,000.00 2,250.00
Mandor org 0.0015 80,000.00 120.00
Jumlah 420,930.00
Dibulatkan 420,930.00
M15 1BuahKran1/2"3/4"
Kranair bh 1.0000 40,900.00 40,900.00
Sealtape bh 0.0250 4,200.00 105.00
Pekerja org 0.0100 42,000.00 420.00
Tukangbatu org 0.1000 65,000.00 6,500.00
KepalaTukang org 0.0100 75,000.00 750.00
Mandor org 0.0050 80,000.00 400.00
Jumlah 49,075.00
Dibulatkan 49,075.00
M16 1BuahFloorDrain
Floordrain bh 1.0000 66,600.00 66,600.00
Pekerja org 0.0100 42,000.00 420.00
Tukangbatu org 0.1000 65,000.00 6,500.00
KepalaTukang org 0.0100 75,000.00 750.00
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm 4/7
5/28/2017 AnalisaHargaSatuanPekerjaanSanitasiSoftwareRAB

Mandor org 0.0050 80,000.00 400.00


Jumlah 74,670.00
Dibulatkan 74,670.00
M17 1M'GrafelbetonU20cm60cm
PipabetonU bh 1.1000 44,300.00 48,730.00
Batamerah bh 12.0000 775.00 9,300.00
P.C(50gk) zak 0.1030 1,406.00 144.82
Pasirpasang m3 0.0305 233,400.00 7,118.70
Pasirurug m3 0.0345 175,300.00 6,047.85
Pekerja org 0.0100 42,000.00 420.00
Tukangbatu org 0.1000 65,000.00 6,500.00
KepalaTukang org 0.0100 75,000.00 750.00
Mandor org 0.0050 80,000.00 400.00
Jumlah 79,411.37
Dibulatkan 79,411.00
M18 1M'PasangTalangPlastikPVCU15cm(AW)
TalangplastikPVC m' 1.05000 60,000.00 63,000.00
Perlengkapan35%hargatalang lot 0.3500 63,000.00 22,050.00
Pekerja org 0.1500 42,000.00 6,300.00
Tukangbatu org 0.4000 65,000.00 26,000.00
KepalaTukang org 0.0250 75,000.00 1,875.00
Mandor org 0.0013 80,000.00 100.00
Jumlah 119,325.00
Dibulatkan 119,325.00
M19 1M'SaluranAirLimbahBuisBeton60cm
Buisbeton60cm bh 1.10 130,900.00 143,990.00
Batamerah bh 25.00 775.00 19,375.00
P.C(50gk) zak 0.206 1,406.00 289.64
Pasirpasang m3 0.061 233,400.00 14,237.40
Pasirurug m3 0.069 175,300.00 12,095.70
Pekerja org 0.3800 42,000.00 15,960.00
Tukangbatu org 0.1900 65,000.00 12,350.00
KepalaTukang org 0.0190 75,000.00 1,425.00
Mandor org 0.0190 80,000.00 1,520.00
Jumlah 221,242.74
Dibulatkan 221,243.00
M20 1M'PasangTalangSengDatar
Sengpelat3"x6" lbr 0.50000 20,801.00 10,400.50
Paku kg 0.01500 23,400.00 351.00
KayukelasII m3 0.00960 2,850,000.00 27,360.00
Menibesi kg 0.2500 30,400.00 7,600.00
Pekerja org 0.1500 42,000.00 6,300.00
Tukangbatu org 0.4000 65,000.00 26,000.00
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm 5/7
5/28/2017 AnalisaHargaSatuanPekerjaanSanitasiSoftwareRAB

KepalaTukang org 0.0250 75,000.00 1,875.00


Mandor org 0.0013 80,000.00 100.00
Jumlah 79,986.50
Dibulatkan 79,987.00
M21 1BuahClosetDuduk
Closetduduk bh 1.00 1,724,700.00 1,724,700.00
Pekerja org 3.3000 42,000.00 138,600.00
Tukangbatu org 1.1000 65,000.00 71,500.00
KepalaTukang org 0.0010 75,000.00 75.00
Mandor org 0.1600 80,000.00 12,800.00
Perlengkapan6%hargacloset lot 0.0600 1,724,700.00 103,482.00
Jumlah 2,051,157.00
Dibulatkan 2,051,157.00
M22 1BuahTangkiAirfibreglassVolume1m3
Bakfibreglasskapasitas1m3 bh 1.00 1,316,400.00 1,316,400.00
Pekerja org 3.3000 42,000.00 138,600.00
Tukangbatu org 1.1000 65,000.00 71,500.00
KepalaTukang org 0.0010 75,000.00 75.00
Mandor org 0.1600 80,000.00 12,800.00
Perlengkapan6%hargabak lot 0.0600 1,316,400.00 78,984.00
Jumlah 1,618,359.00
Dibulatkan 1,618,359.00
M23 1UnitSeptictank2x1,50x1,50m+Rembesan
Galiantanah m3 4.500 26,252.00 118,134.00
Pasirurug m3 0.214 175,300.00 37,514.20
lantaikerja m3 2.250 716,798.00 1,612,795.50
Pasbataadk1pc:3ps m2 15.000 220,267.10 3,304,006.50
PelatbetonK225 m3 0.300 6,438,864.00 1,931,659.20
Plesteranadk1pc:3ps m2 15.000 41,301.82 619,527.30
PipaPVC4"jenisAW m' 5.400 256,800.00 1,386,720.00
PipaGIP11/2" m' 5.000 46,750.00 233,750.00
Galiantanahuntukrembesan m3 3.375 20,000.00 67,500.00
Pasijuk kg 5.400 23,400.00 126,360.00
Urugankerikil3/5 m3 1.050 205,000.00 215,250.00
PipaPVC4"berlubangjenisAW m' 9.000 36,700.00 330,300.00
Urugandanperataantanah m3 1.125 34,584.00 38,907.00
Jumlah 10,022,423.70
Dibulatkan 10,022,424.00
M24 1UnitSeptictank1x1,50x1,50m+Rembesan
Galiantanah m3 2.250 20,000.00 45,000.00
Pasirurug m3 0.107 175,300.00 18,757.10
lantaikerja m3 1.125 716,798.00 806,397.75
Pasbataadk1pc:3ps m2 7.500 220,267.10 1,652,003.25
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm 6/7
5/28/2017 AnalisaHargaSatuanPekerjaanSanitasiSoftwareRAB

PelatbetonK225 m3 0.150 6,438,864.00 965,829.60


Plesteranadk1pc:3ps m2 7.500 41,301.82 309,763.65
PipaPVC4"jenisAW m' 9.000 256,800.00 2,311,200.00
PipaGIP11/2" m' 2.500 46,750.00 116,875.00
Galiantanahuntukrembesan m3 1.688 20,000.00 33,760.00
Pasijuk kg 2.700 23,400.00 63,180.00
Urugankerikil3/5 m3 0.525 205,000.00 107,625.00
PipaPVC4"berlubangjenisAW m' 9.000 36,700.00 330,300.00
Urugandanperataantanah m3 0.563 34,584.00 19,470.79
Jumlah 6,780,162.14
Dibulatkan 6,780,162.00
KembalikeAnalisaSNI

Copyright2015SoftwareRABRumah|XHTML|G1|G2|ValidRSS|PrivacyPolicy|Disclaimer|Contact

www.softwarerab.com

http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm 7/7

Você também pode gostar