1 Fire Water Pump Room B2 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0%
2 Fan Rooms- 12 nos B1& B2 100% 100% 0% 100% 100% 0% 100% 100% 0% 95% 95% 0% - - -
5 Generator Room B1 100% 100% 0% 100% 100% 0% 95% 95% 0% 100% 100% 0% 100% 100% 0%
6 Garbage Chute L1- L8 - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0%
7 Water Meter Room B L1- L8 - - - 100% 100% 0% - - - 100% 100% 0% 100% 100% 0%
8 Water Meter Room D L1- L8 - - - 100% 100% 0% - - - 100% 100% 0% 100% 100% 0%
9 Fire Hose Cabinet (68 nos) L1- L8 100% 100% 0% 100% 100% 0% - - - - - - - - -
12 Telecome Room L1- L8 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% - - -
15 FAN Foundations (3 nos) U. ROOF 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% 100% 100% 0%
16 Lift Machine Room ROOF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% - - -
17 FAHU Foundations (3 nos) ROOF 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% 100% 100% 0%
18 VRF Foundation (170 Nos) ROOF 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% - - -
19 LPG Foundation ROOF 100% 100% 0% 100% 100% 0% - - - 100% 100% 0% 100% 100% 0%
21 BOOSTER PUMPS (2 Nos) ROOF 100% 100% 0% - - - - - - 100% 100% 0% 100% 100% 0%
22 VRF Foundation (62 Nos) L8 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% - - -
24 FAHU foundation (1 no) L5 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% 100% 100% 0%
23 VRF Foundation (79 Nos) L5 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% - - -
26 BOOSTER PUMPS (1 Nos) L5 100% 100% 0% 100% 100% 0% - - - 100% 100% 0% 100% 100% 0%
MISCELLANEOUS
31 Swimming Pool Pump Room L6 - - - - - - 100% 100% 0% 100% 100% 0% 100% 100% 0%
1 OTS 1 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 2- Feb - 2017
2 OTS 2 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 10-Jan - 2017
3 OTS 3 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 10-Jan - 2017
4 OTS 4 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 20- Dec - 2017
5 OTS 5 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 10-Jan - 2017
6 OTS 6 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 2- Feb - 2017
7 OTS 7 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 10-Jan - 2017
8 OTS 8 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 23- Oct - 2016
9 OTS 9 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 09- Oct - 2016
10 OTS 10 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 29- Dec - 2016
AL MAKTOUM HOSPITAL RE-DEVELOPMENT PROJECT 25-May-17
SERVICE ROOMS
1 Fire Water, Irrigation Pump Room B2 80% 80% 80% 0% 85% 85% 0% 0% 0% 0% 25% 25% 0% 0% 0% 0% 53% 52.8% 0%
2 Fan Rooms (B2) B2 80% 100% 100% 0% 95% 95% 0% 35% 35% 0% 40% 40% 0% 74% 74.3% 0%
3 Fan Rooms (B1) B1 65% 100% 100% 0% 95% 95% 0% 45% 45% 0% 40% 40% 0% 77% 76.8% 0%
5 Generator Room 55% 100% 100% 0% 0% 0% 0% 0% 0% 0% 70% 70% 0% 65% 65% 0% 61% 60.5% 0%
6 Garbage Chute up to 12th floor (02 Nos) GF-12F 65% 95% 95% 0% 95% 95% 0% 20% 20% 0% 82% 82% 0% 78% 78.1% 0%
7 Water Meter Room up to 12th floor GF-12F 65% 40% 40% 0% 75% 75% 0% 70% 69.8% 0%
8 Fire Hose Cabinet up to 12th floor GF-12F 0% 16% 80% 64% 30% 30% 0% 20% 65.0% 45%
9 Electrical Room up to 12th floor GF-12F 65% 60% 90% 30% 50% 50% 0% 45% 45% 0% 55% 72.5% 18%
10 Telephone Room up to 12th floor GF-12F 65% 10% 15% 5% 0% 0% 0% 10% 10% 0% 9% 12.0% 3%
12 Lift Machine Room 85% 100% 100% 0% 0% 0% 0% 20% 30% 10% 60% 74.5% 15%
14 Swimming Pool Pump Room 65% 70% 70% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 44% 43.5% 0%
ROOF WORKS
15 FAHU (03 Nos) RF 100% 100% 100% 0% 80% 80% 0% 0% 0% 0% 70% 70.0% 0%
17 FAN Foundations RF 85% 90% 5% 85% 85% 0% 0% 0% 0% 72% 75.0% 3% No Clearance By SPML
18 Staircase Presurisation Fans RF 75% 75% 0% 70% 70% 0% 0% 0% 0% 62% 62.3% 0% No Clearance By SPML
19 GRP Water Tank (4 Nos) RF 100% 100% 100% 0% 30% 35% 5% 76% 77.3% 2%
20 VRF Units LRF 100% 100% 100% 0% 60% 65% 5% 0% 0% 0% 70% 71.3% 1%
24 Condensing Units LRF 50% 100% 100% 0% 95% 95% 0% 0% 0% 0% 79% 78.8% 0%
25 Condensing Units URF 100% 100% 0% 95% 95% 0% 0% 0% 0% 79% 78.8% 0% No Clearance By SPML
33 OTS 8 GF-RF 20% 90% 90% 0% 0% 0% 0% 3% 3% 0% 0% 0% 0% 10% 9.6% 0% Clearance Received on 13-May-2017
SERVICE ROOM TARGET COMPLETION WITH STATUS 25-May-17 AL MAKTOUM HOSPITAL RE-DEVELOPMENT PROJECT
BuildingC
CIVIL
MEPStatus
STATUS REMARK
S.N SERVICEROOM LEVEL
EquipmentInstallation FireFighting HVAC Electrical Plumbing OverallMEP
STATUS
18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE
BASEMENT01
1 ExhaustFanroom1 B1 80.0% 100% 100% 0% 95% 95% 0% 15% 20% 5% 0% 0% 0% 58% 59.5% 1%
4 ExhaustFanRoom2 B1 100.0% 10% 20% 10% 30% 30% 0% 0% 0% 0% 20% 20% 0% 11% 15% 4%
7 DirtyLINEN B1 100.0% 100% 100% 0% 90% 90% 0% 55% 55% 0% 0% 0% 0% 0% 0% 0% 58% 58% 0%
9 BMSRoom B1 60.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 5% 5% 0% 2% 2%
10 Boiler/SteamRoom B1 65.0% 100% 100% 0% 95% 95% 0% 20% 20% 0% 0% 0% 0% 90% 90% 3% 79% 79% 0%
11 Freshairfanroom B1 90.0% 60% 70% 10% 50% 50% 0% 20% 20% 0% 0% 0% 0% 37% 42% 5%
15 GeneratorRoom B1 100.0% 95% 95% 0% 0% 0% 0% 0% 0% 0% 70% 70% 0% 50% 50% 0% 62% 62% 0%
16 FuelRoom B1 30.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
17 GeneralStore B1 100.0% 0% 0% 0% 95% 95% 0% 10% 10% 0% 30% 30% 0% 20% 20% 0%
18 StorageRoom B1 100.0% 0% 0% 0% 95% 95% 0% 30% 30% 0% 30% 30% 0% 26% 26% 0%
18 UniformExchangeRoom B1 100.0% 50% 50% 0% 95% 95% 0% 30% 30% 0% 30% 30% 0% 44% 44% 0%
BASEMENT02 0% 0% 0%
18 ExhaustFanRoom2 B2 100.0% 50% 60% 10% 20% 20% 0% 35% 35% 0% 25% 25% 0% 38% 43% 5%
20 LouveredPlenum1 B2 100.0% 0% 0% 0% 50% 50% 0% 20% 20% 0% 20% 20% 0% 5% 5% 0% 15% 15% 0%
21 Electricalroom B2 100.0% 10% 10% 0% 20% 20% 0% 40% 40% 0% 22% 22% 0%
22 LCRoom B2 100.0% 15% 15% 0% 20% 20% 0% 30% 30% 0% 21% 21% 0%
23 LCStore B2 100.0% 0% 0% 0% 95% 95% 0% 20% 20% 0% 20% 20% 0% 20% 20% 0%
29 Irrigation+Fire+Domestic+PumpRoom B2 100.0% 100% 100% 0% 95% 95% 0% 20% 20% 0% 20% 20% 0% 85% 85% 0% 76% 76% 0%
32 EtisalatTelecom GF 35.0% 0% 0% 0% 0% 0% 0% 5% 5% 0% 2% 2% 0%
33 GSM GF 25.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 5% 5% 0% 2% 2% 0%
44 MEPRoomHotelSide 1F12F 35.0% 0% 0% 0% 95% 95% 0% 25% 25% 0% 10% 10% 0% 0% 0% 0% 17% 17% 0%
58 ELECTRICALROOM LR 70.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
ROOFMEPWORKS 0% 0% 0%
61 FAHU+SMOKEFAN(02Nos) 14F 100.0% 100% 100% 0% 0% 0% 0% 70% 70% 0% 75% 75% 0% 0% 0% 0% 66% 66% 0%
62 FAHU+SMOKEFAN(03NOS) L.ROOF 70.0% 80% 80% 0% 0% 0% 0% 20% 20% 0% 50% 50% 0% 0% 0% 0% 40% 40% 0%
64 CHILLER(04NOS) L.ROOF 100.0% 100% 100% 0% 80% 80% 0% 0% 0% 0% 10% 10% 0% 65% 65% 0%
66 GSMROOM L.ROOF 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
67 SMATVROOM L.ROOF 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
68 ELECTRICALROOM L.ROOF 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
70 FAHU+Fan U.ROOF 80% 85% 5% 0% 0% 0% 60% 75% 15% 0% 0% 0% 10% 10% 0% 43% 49% 6%