Você está na página 1de 5

AL MAKTOUM HOSPITAL RE-DEVELOPMENT PROJECT 25-May-17

SERVICE ROOM TARGET COMPLETION WITH STATUS BUILDING BD


MEPStatus
S.NO ROOMDESCRIPTION LEVEL EquipmentInstallation FireFighting HVAC Electrical Plumbing REMARK
18-May 25-May VARIANCE 18-May 25-May VARIANCE 18-May 25-May VARIANCE 18-May 25-May VARIANCE 18-May 25-May VARIANCE
SERVICE ROOMS

1 Fire Water Pump Room B2 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0%

2 Fan Rooms- 12 nos B1& B2 100% 100% 0% 100% 100% 0% 100% 100% 0% 95% 95% 0% - - -

3 LV Room - B B2 100% 100% 0% 100% 100% 0% 95% 95% 0% 100% 100% 0% - - -

4 LV Room - D B2 100% 100% 0% 100% 100% 0% 95% 95% 0% 100% 100% 0% - - -

5 Generator Room B1 100% 100% 0% 100% 100% 0% 95% 95% 0% 100% 100% 0% 100% 100% 0%

6 Garbage Chute L1- L8 - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0%

7 Water Meter Room B L1- L8 - - - 100% 100% 0% - - - 100% 100% 0% 100% 100% 0%

8 Water Meter Room D L1- L8 - - - 100% 100% 0% - - - 100% 100% 0% 100% 100% 0%

9 Fire Hose Cabinet (68 nos) L1- L8 100% 100% 0% 100% 100% 0% - - - - - - - - -

10 Electrical Rooms L1- L8 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% - - -

11 LC Room L1- L8 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% - - -

12 Telecome Room L1- L8 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% - - -

13 Busbar B1- L8 100% 100% 0% - - - - - - - - - - - -

UPPER ROOF MEP WORKS

14 SMATV Founadtion (7 nos) U. ROOF 100% 100% 0% - - - - - - 100% 100% 0% - - -

15 FAN Foundations (3 nos) U. ROOF 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% 100% 100% 0%

MAIN ROOF MEP WORKS

16 Lift Machine Room ROOF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% - - -

17 FAHU Foundations (3 nos) ROOF 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% 100% 100% 0%

18 VRF Foundation (170 Nos) ROOF 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% - - -

19 LPG Foundation ROOF 100% 100% 0% 100% 100% 0% - - - 100% 100% 0% 100% 100% 0%

20 GRP Water Tanks (4 Nos) ROOF 100% 100% 0% - - - - - - - - - 100% 100% 0%

21 BOOSTER PUMPS (2 Nos) ROOF 100% 100% 0% - - - - - - 100% 100% 0% 100% 100% 0%

8TH FLOOR ROOF MEP WORKS

22 VRF Foundation (62 Nos) L8 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% - - -

23 FAN Foundations (1 nos) L8 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% - - -

5TH FLOOR ROOF MEP WORKS

24 FAHU foundation (1 no) L5 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% 100% 100% 0%

23 VRF Foundation (79 Nos) L5 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% - - -

26 BOOSTER PUMPS (1 Nos) L5 100% 100% 0% 100% 100% 0% - - - 100% 100% 0% 100% 100% 0%

27 GRP Water Tanks (2 Nos) L5 100% 100% 0% - - - - - - - - - 100% 100% 0%

28 FAN Foundations (4 nos) L5 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% - - -

29 LC ROOM L5 100% 100% 0% - - - 100% 100% 0% 100% 100% 0% - - -

MISCELLANEOUS

30 Swimming Pool L6 - - - - - - 100% 100% 0% 100% 100% 0% 100% 100% 0%

31 Swimming Pool Pump Room L6 - - - - - - 100% 100% 0% 100% 100% 0% 100% 100% 0%

32 Irrigation Pump Room B1 - - - - - - - - - 100% 100% 0% 100% 100% 0%

OTS SHAFT WORKS EquipmentInstallation LPGPiping HVAC Electrical Plumbing

1 OTS 1 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 2- Feb - 2017

2 OTS 2 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 10-Jan - 2017

3 OTS 3 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 10-Jan - 2017

4 OTS 4 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 20- Dec - 2017

5 OTS 5 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 10-Jan - 2017

6 OTS 6 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 2- Feb - 2017

7 OTS 7 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 10-Jan - 2017

8 OTS 8 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 23- Oct - 2016

9 OTS 9 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 09- Oct - 2016

10 OTS 10 GF-RF - - - 100% 100% 0% 100% 100% 0% 100% 100% 0% 100% 100% 0% Civil Clearance Received on 29- Dec - 2016
AL MAKTOUM HOSPITAL RE-DEVELOPMENT PROJECT 25-May-17

SERVICE ROOM TARGET COMPLETION WITH STATUS BUILDING A


CIVIL
Level/ MEPStatus
STATUS REMARK
S.N ROOMDESCRIPTION Equipment FireFighting HVAC Electrical Plumbing OverallMEP
Area
18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE

SERVICE ROOMS

1 Fire Water, Irrigation Pump Room B2 80% 80% 80% 0% 85% 85% 0% 0% 0% 0% 25% 25% 0% 0% 0% 0% 53% 52.8% 0%

2 Fan Rooms (B2) B2 80% 100% 100% 0% 95% 95% 0% 35% 35% 0% 40% 40% 0% 74% 74.3% 0%

3 Fan Rooms (B1) B1 65% 100% 100% 0% 95% 95% 0% 45% 45% 0% 40% 40% 0% 77% 76.8% 0%

4 LV Room GF 100% 80% 80% 0% 0% 0% 0% 90% 90% 0% 76% 75.5% 0%

5 Generator Room 55% 100% 100% 0% 0% 0% 0% 0% 0% 0% 70% 70% 0% 65% 65% 0% 61% 60.5% 0%

6 Garbage Chute up to 12th floor (02 Nos) GF-12F 65% 95% 95% 0% 95% 95% 0% 20% 20% 0% 82% 82% 0% 78% 78.1% 0%

7 Water Meter Room up to 12th floor GF-12F 65% 40% 40% 0% 75% 75% 0% 70% 69.8% 0%

8 Fire Hose Cabinet up to 12th floor GF-12F 0% 16% 80% 64% 30% 30% 0% 20% 65.0% 45%

9 Electrical Room up to 12th floor GF-12F 65% 60% 90% 30% 50% 50% 0% 45% 45% 0% 55% 72.5% 18%

10 Telephone Room up to 12th floor GF-12F 65% 10% 15% 5% 0% 0% 0% 10% 10% 0% 9% 12.0% 3%

11 Busbar B2-12F 65% 50% 60% 10% 50% 60.0% 10%

12 Lift Machine Room 85% 100% 100% 0% 0% 0% 0% 20% 30% 10% 60% 74.5% 15%

13 Swimming Pool 12F 80% 70% 70% 0% 0% 0% 0% 42% 42.0% 0%

14 Swimming Pool Pump Room 65% 70% 70% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 44% 43.5% 0%

ROOF WORKS

15 FAHU (03 Nos) RF 100% 100% 100% 0% 80% 80% 0% 0% 0% 0% 70% 70.0% 0%

16 Mechnical Room(Fans) RF 0% 5% 5% 85% 85% 0% 0% 0% 0% 26% 28.3% 3% No Clearance By SPML

17 FAN Foundations RF 85% 90% 5% 85% 85% 0% 0% 0% 0% 72% 75.0% 3% No Clearance By SPML

18 Staircase Presurisation Fans RF 75% 75% 0% 70% 70% 0% 0% 0% 0% 62% 62.3% 0% No Clearance By SPML

19 GRP Water Tank (4 Nos) RF 100% 100% 100% 0% 30% 35% 5% 76% 77.3% 2%

20 VRF Units LRF 100% 100% 100% 0% 60% 65% 5% 0% 0% 0% 70% 71.3% 1%

21 VRF Units URF 100% 100% 0% 20% 25% 5% 0% 0% 0% 60% 61.3% 1%

22 LPG Tank RF 100% 100% 100% 0% 0% 0% 0% 10% 15% 5% 63% 63.8% 1%

23 Booster Pump (2 Nos) RF 100% 15% 20% 5% 0% 0% 0% 0% 0% 0% 8% 10.0% 3% No Clearance By SPML

24 Condensing Units LRF 50% 100% 100% 0% 95% 95% 0% 0% 0% 0% 79% 78.8% 0%

25 Condensing Units URF 100% 100% 0% 95% 95% 0% 0% 0% 0% 79% 78.8% 0% No Clearance By SPML

OTS SHAFT Equipment LPG HVAC Electrical Plumbing


Clearance Received on 30-April-2017 (Without
26 OTS 1 GF-RF 80% 85% 90% 5% 35% 39% 4% 60% 60% 0% 61% 88% 26% 53% 62.8% 10%
Extension Scaffolding)
Clearance Received on 24-April-2017 (Without
27 OTS 2 GF-RF 80% 90% 100% 10% 47% 56% 9% 60% 60% 0% 53% 83% 30% 56% 69.3% 14%
Extension Scaffolding)
Clearance Received on 24-April-2017 (Without
28 OTS 3 GF-RF 15% 90% 90% 0% 47% 52% 5% 60% 60% 0% 53% 83% 30% 56% 66.5% 11%
Extension Scaffolding)
Clearance Received on 24-April-2017 (Without
29 OTS 4 GF-RF 30% 90% 90% 0% 50% 56% 6% 60% 60% 0% 61% 88% 26% 59% 69.7% 10%
Extension Scaffolding)

30 OTS 5 GF-RF 30% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0% 0% No Clearance By SPML

31 OTS 6 GF-RF 15% 90% 90% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 9% 9.0% 0% No Clearance By SPML

32 OTS 7 GF-RF 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0% 0% No Clearance By SPML

33 OTS 8 GF-RF 20% 90% 90% 0% 0% 0% 0% 3% 3% 0% 0% 0% 0% 10% 9.6% 0% Clearance Received on 13-May-2017
SERVICE ROOM TARGET COMPLETION WITH STATUS 25-May-17 AL MAKTOUM HOSPITAL RE-DEVELOPMENT PROJECT
BuildingC
CIVIL
MEPStatus
STATUS REMARK
S.N SERVICEROOM LEVEL
EquipmentInstallation FireFighting HVAC Electrical Plumbing OverallMEP
STATUS
18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE 18May 25May VARIANCE

BASEMENT01

1 ExhaustFanroom1 B1 80.0% 100% 100% 0% 95% 95% 0% 15% 20% 5% 0% 0% 0% 58% 59.5% 1%

2 MainLVroom B1 100.0% 95% 95% 0% 0% 0% 0% 80% 80% 0% 63% 63% 0%

3 TransformerRoom B1 100.0% 100% 100% 0% 95% 95% 0% 79% 89% 10%

4 ExhaustFanRoom2 B1 100.0% 10% 20% 10% 30% 30% 0% 0% 0% 0% 20% 20% 0% 11% 15% 4%

5 Electricalroom B1 100.0% 30% 40% 10% 0% 0% 0% 40% 40% 0% 29% 34% 5%

6 LCRoom B1 100.0% 30% 35% 5% 0% 0% 0% 20% 20% 0% 24% 26% 3%

7 DirtyLINEN B1 100.0% 100% 100% 0% 90% 90% 0% 55% 55% 0% 0% 0% 0% 0% 0% 0% 58% 58% 0%

8 UPS B1 100.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 10% 10% 0% 3% 3% 0%

9 BMSRoom B1 60.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 5% 5% 0% 2% 2%

10 Boiler/SteamRoom B1 65.0% 100% 100% 0% 95% 95% 0% 20% 20% 0% 0% 0% 0% 90% 90% 3% 79% 79% 0%

11 Freshairfanroom B1 90.0% 60% 70% 10% 50% 50% 0% 20% 20% 0% 0% 0% 0% 37% 42% 5%

12 260cumFire+RawWaterTank B1 65.0% 0% 0% 0% 10% 10% 0% 0% 0% 0% 0% 0% 0% 50% 50% 0% 14% 14% 0%

13 PlantRoomStore B1 25.0% 0% 0% 0% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 10% 10% 0%

14 LouveredPlenum B1 100.0% 0% 0% 0% 95% 95% 0% 0% 0% 0% 20% 20% 0% 0% 0% 0% 14% 14% 0%

15 GeneratorRoom B1 100.0% 95% 95% 0% 0% 0% 0% 0% 0% 0% 70% 70% 0% 50% 50% 0% 62% 62% 0%

16 FuelRoom B1 30.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

17 GeneralStore B1 100.0% 0% 0% 0% 95% 95% 0% 10% 10% 0% 30% 30% 0% 20% 20% 0%

18 StorageRoom B1 100.0% 0% 0% 0% 95% 95% 0% 30% 30% 0% 30% 30% 0% 26% 26% 0%

18 UniformExchangeRoom B1 100.0% 50% 50% 0% 95% 95% 0% 30% 30% 0% 30% 30% 0% 44% 44% 0%

BASEMENT02 0% 0% 0%

17 ExhaustFanRoom1 B2 40.0% 50% 60% 10% 20% 20% 0% 0% 0% 0% 0% 0% 0% 25% 29% 5%

18 ExhaustFanRoom2 B2 100.0% 50% 60% 10% 20% 20% 0% 35% 35% 0% 25% 25% 0% 38% 43% 5%

19 StoreRoom B2 0% 0% 0% 100% 100% 0% 20% 20% 0% 0% 0% 0% 16% 16% 0%

20 LouveredPlenum1 B2 100.0% 0% 0% 0% 50% 50% 0% 20% 20% 0% 20% 20% 0% 5% 5% 0% 15% 15% 0%

21 Electricalroom B2 100.0% 10% 10% 0% 20% 20% 0% 40% 40% 0% 22% 22% 0%

22 LCRoom B2 100.0% 15% 15% 0% 20% 20% 0% 30% 30% 0% 21% 21% 0%

23 LCStore B2 100.0% 0% 0% 0% 95% 95% 0% 20% 20% 0% 20% 20% 0% 20% 20% 0%

24 SumppitRoom B2 0% 0% 0% 20% 20% 0% 0% 0% 0% 0% 0% 0% 2% 2% 0%

25 Freshairfanroom1 B2 100.0% 0% 0% 0% 0% 0% 0% 20% 20% 0% 20% 20% 0% 9% 9% 0%


BuildingC
CIVIL
MEPStatus
STATUS REMARK
S.N SERVICEROOM LEVEL
EquipmentInstallation FireFighting HVAC Electrical Plumbing OverallMEP
STATUS
26 Electrical/MechanicalStore B2 100.0% 0% 0% 0% 90% 90% 0% 20% 20% 0% 20% 20% 0% 20% 20% 0%

27 Freshairfanroom2 B2 85.0% 0% 0% 0% 20% 20% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 2% 2% 0%

28 LouveredPlenum2 B2 100.0% 0% 0% 0% 20% 20% 0% 0% 0% 0% 20% 20% 0% 6% 6% 0%

29 Irrigation+Fire+Domestic+PumpRoom B2 100.0% 100% 100% 0% 95% 95% 0% 20% 20% 0% 20% 20% 0% 85% 85% 0% 76% 76% 0%

30 MCCRoom B2 40.0% 0% 0% 0% 0% 0% 0% 20% 20% 0% 0% 0% 0% 2% 2% 0%

31 260cumFire+RawWaterTank B2 0% 0% 0% 0% 0% 0% 0% 0% 0% 5% 5% 0% 50% 50% 0% 13% 13% 0%

32 EtisalatTelecom GF 35.0% 0% 0% 0% 0% 0% 0% 5% 5% 0% 2% 2% 0%

33 GSM GF 25.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 5% 5% 0% 2% 2% 0%

34 LuggageStore&Scanning GF 25.0% 0% 0% 0% 0% 0% 0% 25% 25% 0% 5% 5% 0% 0% 0% 0% 6% 6% 0%

35 FreezerStorageRoom GF 25.0% 0% 0% 0% 0% 0% 0% 25% 25% 0% 5% 5% 0% 0% 0% 0% 6% 6% 0%

36 Electricalroom GF 35.0% 0% 0% 0% 0% 0% 0% 35% 35% 0% 12% 12% 0%

37 LCRoom GF 35.0% 10% 10% 0% 0% 0% 0% 5% 5% 0% 7% 7% 0%

38 GarbageChute 1F12F 45.0% 90% 90% 0% 60% 60% 0% 0% 0% 0% 0% 0% 0% 41% 41% 0%

39 FireHoseCabinet 1F12F 35.0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 18% 18% 0%

40 ElectricalRoomApartment 1F12F 45.0% 20% 20% 0% 0% 0% 0% 30% 30% 0% 21% 21% 0%

41 LCRoomApartment 1F12F 38.0% 0% 0% 0% 0% 0% 0% 20% 20% 0% 7% 7% 0%

42 ElectricalRoomHotel 1F12F 38.0% 50% 50% 0% 0% 0% 0% 50% 50% 0% 43% 43% 0%

43 LCRoomHotel 1F12F 38.0% 15% 15% 0% 0% 0% 0% 20% 20% 0% 15% 15% 0%

44 MEPRoomHotelSide 1F12F 35.0% 0% 0% 0% 95% 95% 0% 25% 25% 0% 10% 10% 0% 0% 0% 0% 17% 17% 0%

45 ElectricalRoomApartment 13F 50.0% 12% 12% 0% 0% 0% 0% 35% 35% 0% 18% 18% 0%

46 LCRoomApartment 13F 50.0% 10% 10% 0% 0% 0% 0% 10% 10% 0% 9% 9% 0%

47 MEPRoomHotelSide 13F 50.0% 0% 0% 0% 95% 95% 0% 10% 10% 0% 0% 0% 0% 0% 0% 0% 12% 12% 0%

48 ElectricalRoomHotelSide 13F 50.0% 15% 15% 0% 0% 0% 0% 10% 10% 0% 11% 11% 0%

49 LCRoomHotelSide 13F 50.0% 2% 2% 0% 0% 0% 0% 10% 10% 0% 5% 5% 0%

50 SwimmingPoolPumpRoom/TankRoom 13F 50.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

51 ElectricalRoom1 14F 50.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

52 ElectricalRoom2 14F 50.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

53 LCRoom 14F 60.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

54 CentralHotWaterCylinderwithBackupGasBoiler 14F 30.0% 65% 65% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 26% 26% 0%

55 SwimmingPool 14F 100.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

56 FAHU+SMOKEFANROOM LR 60.0% 60% 60% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 18% 18% 0%


BuildingC
CIVIL
MEPStatus
STATUS REMARK
S.N SERVICEROOM LEVEL
EquipmentInstallation FireFighting HVAC Electrical Plumbing OverallMEP
STATUS
57 CHWPUMPROOM LR 80.0% 100% 100% 0% 75% 75% 0% 0% 0% 0% 50% 50% 0% 68% 68% 0%

58 ELECTRICALROOM LR 70.0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

59 PUMPROOM LR 80.0% 100% 100% 0% 0% 0% 0% 0% 0% 0% 70% 70% 0% 61% 61% 0%

ROOFMEPWORKS 0% 0% 0%

60 CENTRALGASSYSTEM 14F 100.0% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 40% 40% 0%

61 FAHU+SMOKEFAN(02Nos) 14F 100.0% 100% 100% 0% 0% 0% 0% 70% 70% 0% 75% 75% 0% 0% 0% 0% 66% 66% 0%

62 FAHU+SMOKEFAN(03NOS) L.ROOF 70.0% 80% 80% 0% 0% 0% 0% 20% 20% 0% 50% 50% 0% 0% 0% 0% 40% 40% 0%

63 GRPTANK(2NOS) L.ROOF 100.0% 100% 100% 0% 45% 45% 0% 81% 81% 0%

64 CHILLER(04NOS) L.ROOF 100.0% 100% 100% 0% 80% 80% 0% 0% 0% 0% 10% 10% 0% 65% 65% 0%

65 HOT&COLDWATERPUMP L.ROOF 30.0% 100% 100% 0% 0% 0% 0% 0% 0% 0% 50% 50% 0% 55% 55% 0%

66 GSMROOM L.ROOF 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

67 SMATVROOM L.ROOF 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

68 ELECTRICALROOM L.ROOF 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

69 HOTWATERSOLARPANEL U.ROOF 100% 100% 0% 0% 0% 0% 95% 95% 0% 79% 79% 0%

70 FAHU+Fan U.ROOF 80% 85% 5% 0% 0% 0% 60% 75% 15% 0% 0% 0% 10% 10% 0% 43% 49% 6%