PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO: ' AMPLIACI'ON Y MEJORAMIENTO DE LAS CONDICIONES BASICAS DEL SERVICIO EDUCATIVO EN LA I.E. N DEPARTAMENTO :SAN MARTN
0233 MONTECRISTO - SHUNTE - TOCAHE - SAN MART'IN'' PROVINCIA TOCACHE
FECHA : JUNIO DEL 2012 DISTRITO SHUNTE

ITEM DESCRIPCION UND CAN ELEM. L A H PARCIAL SUB TOTAL TOTAL OBSERVACIONES

METRADO DE ESTRUCTURAS
01 MODULO I
01.01 TRABAJOS PRELIMINARES
01.01.01 LIMPIEZA DE TERRENO MANUAL M2 185.30
MODULO I M2 1.00 1.00 17.00 10.90 185.30 185.30 LAMINA E-01, E-02, E-03

01.01.02 TRAZO Y REPLANTEO M2 185.30


MODULO I M2 1.00 1.00 17.00 10.90 185.30 185.30 LAMINA E-01, E-02, E-03

01.02 MOVIMIENTO DE TIERRAS


01.02.01 EXCAVACIN DE ZANJAS M3 117.26
MODULO I 117.26
EJE W / CORTE C-C / TRAMO 22-31 M3 1 1.00 17.00 1.80 1.50 45.90 LAMINA E-01, E-02, E-03
EJE S / CORTE D-D, CORTE E-E / TRAMO 22-31 M3 1 1.00 17.00 1.20 1.50 30.60 LAMINA E-01, E-02, E-03
EJE 31 Y 22 /CORTE A'-A' Y A-A M3 2 1.00 5.90 1.20 1.50 21.24 LAMINA E-01, E-02, E-03
EJE 26-26 / CORTE B-B / TRAMO W-S M3 1 1.00 5.90 1.80 1.50 15.93 LAMINA E-01, E-02, E-03
EJE 28-28 / CORTE F-F / TRAMO W-S M3 1 1.00 2.94 0.80 0.70 1.65 LAMINA E-01, E-02, E-03
EJE U /CORTE G-G / TRAMO 28 - 31 M3 1 1.00 2.65 0.60 0.70 1.11 LAMINA E-01, E-02, E-03
M3 1 1.00 1.19 0.60 0.70 0.50 LAMINA E-01, E-02, E-03
M3 1 1.00 0.78 0.60 0.70 0.33 LAMINA E-01, E-02, E-03

01.02.02 RELLENO Y APISONADO CON MATERIAL DE PRSTAMO M3 51.28


MODULO I 41.62 LAMINA E-01
EJE W / CORTE C-C / TRAMO 22-31 M3 1 1.00 17.00 0.65 0.75 8.29 LAMINA E-01, E-02, E-03
M3 1 1.00 15.65 0.90 0.75 10.56 LAMINA E-01, E-02, E-03
M3 1 1.00 0.65 0.30 0.75 0.15 LAMINA E-01, E-02, E-03
EJE S / CORTE D-D, CORTE E-E / TRAMO 22-31 M3 1 1.00 17.00 0.35 0.75 4.46 LAMINA E-01, E-02, E-03
M3 1 1.00 15.65 0.60 0.75 7.04 LAMINA E-01, E-02, E-03
M3 1 1.00 0.35 0.30 0.75 0.08 LAMINA E-01, E-02, E-03
EJE 31 Y 22 /CORTE A'-A' Y A-A M3 2 1.00 5.50 0.95 0.75 7.84 LAMINA E-01, E-02, E-03
EJE 26-26 / CORTE B-B / TRAMO W-S M3 1 1.00 5.50 0.78 0.75 3.20 LAMINA E-01, E-02, E-03

Excavacin para falso piso 9.67 LAMINA E-01


M3 1.00 6.40 5.50 0.15 5.28 LAMINA E-01, E-02, E-03
M3 1.00 5.50 2.95 0.15 2.43 LAMINA E-01, E-02, E-03
M3 1.00 2.65 2.53 0.15 1.01 LAMINA E-01, E-02, E-03
M3 1.00 2.65 2.38 0.15 0.95 LAMINA E-01, E-02, E-03

01.02.03 RELLENO Y APISONADO CON MATERIAL AFIRMADO M3 16.68


MODULO I 16.68 LAMINA E-01
AULA 01 M3 1.00 8.13 7.00 0.15 8.54 LAMINA E-01, E-02, E-03
SALA DE PROFESORES M3 1.00 7.00 3.97 0.15 4.17 LAMINA E-01, E-02, E-03
DIRECCION M3 1.00 3.87 3.65 0.15 2.12 LAMINA E-01, E-02, E-03
SECRETARIA M4 1.00 3.87 3.20 0.15 1.86 LAMINA E-01, E-02, E-03

VOLUMEN EXACAVADO: 117.26 LAMINA E-01, E-02, E-03


ESPONJAMIENTO: 1.25 LAMINA E-01, E-02, E-03
VOLUMEN EXCAVADO CON ESPONJAMIENTO: 146.57 LAMINA E-01, E-02, E-03

Pgina 1
PLANILLA DE METRADOS DE ESTRUCTURAS
PROYECTO: ' AMPLIACI'ON Y MEJORAMIENTO DE LAS CONDICIONES BASICAS DEL SERVICIO EDUCATIVO EN LA I.E. N DEPARTAMENTO :SAN MARTN
0233 MONTECRISTO - SHUNTE - TOCAHE - SAN MART'IN'' PROVINCIA TOCACHE
FECHA : JUNIO DEL 2012 DISTRITO SHUNTE

ITEM DESCRIPCION UND CAN ELEM. L A H PARCIAL SUB TOTAL TOTAL OBSERVACIONES

01.02.04 ELIMINACIN DE MATERIAL EXCEDENTE M3 146.57


. VOLUMEN DE MATERIAL EXCEDENTE : M3 146.57 146.57 LAMINA E-01, E-02, E-03

01.03 OBRAS DE CONCRETO SIMPLE M3


01.03.01 CIMIENTOS CORRIDOS - CONCRETO 1:10 + 30% P.G. M3 2.56
EJE 28-28 / CORTE F-F / TRAMO W-S M3 1 1.00 2.94 0.80 0.50 1.18 2.56 LAMINA E-01, E-02, E-03
EJE U /CORTE G-G / TRAMO 28 - 31 M3 1 1.00 2.65 0.60 0.50 0.80 LAMINA E-01, E-02, E-03
M3 1 1.00 1.19 0.60 0.50 0.36 LAMINA E-01, E-02, E-03
M3 1 1.00 0.78 0.60 0.50 0.23 LAMINA E-01, E-02, E-03

01.03.02 SOLADO PARA CIMIENTOS CORRIDOS (e=0.10) M2 5.12


MODULO I 5.12 LAMINA E-01
EJE 28-28 / CORTE F-F / TRAMO W-S M2 1 1.00 2.94 0.80 2.35 LAMINA E-01, E-02, E-03
EJE U /CORTE G-G / TRAMO 28 - 31 M2 1 1.00 2.65 0.60 1.59 LAMINA E-01, E-02, E-03
M2 1 1.00 1.19 0.60 0.71 LAMINA E-01, E-02, E-03
M2 1 1.00 0.78 0.60 0.47 LAMINA E-01, E-02, E-03

01.03.03 SOLADO PARA CIMIENTOS ARMADOS (e=0.10) M2 75.78


MODULO I 75.78 LAMINA E-01
EJE W / CORTE C-C / TRAMO 22-31 M2 1 1.00 17.00 1.80 30.60 LAMINA E-01, E-02, E-03
EJE S / CORTE D-D, CORTE E-E / TRAMO 22-31 M2 1 1.00 17.00 1.20 20.40 LAMINA E-01, E-02, E-03
EJE 31 Y 22 /CORTE A'-A' Y A-A M2 2 1.00 5.90 1.20 14.16 LAMINA E-01, E-02, E-03
EJE 26-26 / CORTE B-B / TRAMO W-S M2 1 1.00 5.90 1.80 10.62 LAMINA E-01, E-02, E-03

01.04 OBRAS DE CONCRETO ARMANDO


01.04.01 CIMIENTOS REFORZADOS
01.04.01.01 CIMIENTO REFORZADO - concreto f'c = 210 Kg/cm M3 37.89
MODULO II - BLOQUE A 37.89 LAMINA E-01
EJE W / CORTE C-C / TRAMO 22-31 M2 1 1.00 17.00 1.80 0.50 15.30 LAMINA E-01, E-02, E-03
EJE S / CORTE D-D, CORTE E-E / TRAMO 22-31 M2 1 1.00 17.00 1.20 0.50 10.20 LAMINA E-01, E-02, E-03
EJE 31 Y 22 /CORTE A'-A' Y A-A M2 2 1.00 5.90 1.20 0.50 7.08 LAMINA E-01, E-02, E-03
EJE 26-26 / CORTE B-B / TRAMO W-S M2 1 1.00 5.90 1.80 0.50 5.31 LAMINA E-01, E-02, E-03

01.04.01.02 ACERO ESTRUCTURAL - F'y=4200 Kg/cm KG 1,111.44


MODULO I KG 1.00 1,111.44 1,111.44 LAMINA E-01, E-02, E-03

01.04.02 VIGAS DE CONEXIN


01.04.02.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS DE CONEXION M3 3.41
MODULO I 3.41 LAMINA E-01
VCo-01 EJE W-W / TRAMO 31 - 22 M3 2.00 3.25 0.25 0.70 1.14 LAMINA E-01, E-02, E-03
VCo-01 EJE S-S / TRAMO 31 - 22 M3 4.00 3.25 0.25 0.70 2.28 LAMINA E-01, E-02, E-03

01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL M2 36.40


MODULO I 36.40 LAMINA E-01
VCo-01 EJE W-W / TRAMO 22-31 M2 4.00 2.00 3.25 0.70 18.20 LAMINA E-01, E-02, E-03
VCo-01 EJE S-S / TRAMO 31 - 22 M2 4.00 2.00 3.25 0.70 18.20 LAMINA E-01, E-02, E-03

01.04.02.03 ACERO ESTRUCTURAL FY=4200kg/cm2 KG 575.94


MODULO I KG 1.00 575.94 575.94 LAMINA E-01, E-02, E-03

Pgina 2
PLANILLA DE METRADOS DE ESTRUCTURAS
PROYECTO: ' AMPLIACI'ON Y MEJORAMIENTO DE LAS CONDICIONES BASICAS DEL SERVICIO EDUCATIVO EN LA I.E. N DEPARTAMENTO :SAN MARTN
0233 MONTECRISTO - SHUNTE - TOCAHE - SAN MART'IN'' PROVINCIA TOCACHE
FECHA : JUNIO DEL 2012 DISTRITO SHUNTE

ITEM DESCRIPCION UND CAN ELEM. L A H PARCIAL SUB TOTAL TOTAL OBSERVACIONES

01.04.03 VIGAS DE CIMENTACION


01.04.03.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS DE CIMENTACION M3 3.10
MODULO I 3.10 LAMINA E-01
VCI-31 EJE 31-31/ TRAMO W-S M3 2.00 2.95 0.25 0.70 1.03 LAMINA E-01, E-02, E-03
VCI-26 EJE 31-31/ TRAMO W-S M3 2.00 2.95 0.25 0.70 1.03 LAMINA E-01, E-02, E-03
VCI-22 EJE 31-31/ TRAMO W-S M3 2.00 2.95 0.25 0.70 1.03 LAMINA E-01, E-02, E-03

01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL M2 16.52


MODULO I 16.52 LAMINA E-01
VCI-31 EJE 31-31/ TRAMO W-S M2 1.00 2.00 2.95 0.70 4.13 LAMINA E-01, E-02, E-03
VCI-26 EJE 31-31/ TRAMO W-S M2 2.00 2.00 2.95 0.70 8.26 LAMINA E-01, E-02, E-03
VCI-22 EJE 31-31/ TRAMO W-S M2 1.00 2.00 2.95 0.70 4.13 LAMINA E-01, E-02, E-03

01.04.03.03 ACERO ESTRUCTURAL FY=4200kg/cm2 KG 600.48


MODULO I KG 1.00 600.48 600.48 LAMINA E-01, E-02, E-03

01.04.04 FALSO PISO M2


01.04.04.01 FALSO PISO DE 4" DE CONCRETO 1:10
MODULO I 111.21
AULA 01 M2 1.00 8.13 7.00 56.91 LAMINA E-01, E-02, E-03
SALA DE PROFESORES M2 1.00 7.00 3.97 27.79 LAMINA E-01, E-02, E-03
DIRECCION M2 1.00 3.87 3.65 14.13 LAMINA E-01, E-02, E-03
SECRETARIA M2 1.00 3.87 3.20 12.38 LAMINA E-01, E-02, E-03

01.04.04.02 ACERO ESTRUCTURAL FY=4200kg/cm2 KG 431.73


MODULO I KG 1.00 431.73 431.73 LAMINA E-01, E-02, E-03

01.04.05 SOBRECIMIENTO REFORZADO


01.04.05.01 CONCRETO F'C= 210 KG/CM2. PARA SOBRECIMIENTO REFORZA M3 8.81
MODULO I 8.81 LAMINA E-01
EJE W / CORTE C-C / TRAMO 22-31 M3 1 1.00 13.00 0.15 0.65 1.27 LAMINA E-01, E-02, E-03
EJE S / CORTE D / TRAMO 22-31 M3 1 1.00 2.35 0.15 0.65 0.23 LAMINA E-01, E-02, E-03
EJE S / CORTE E-E / TRAMO 22-31 M3 3 1.00 2.23 0.15 0.65 0.65 LAMINA E-01, E-02, E-03
M3 3 1.00 1.00 0.15 0.30 0.14 LAMINA E-01, E-02, E-03
EJE 31 Y 22 /CORTE A'-A' Y A-A M3 2 1.00 5.90 0.25 1.60 4.72 LAMINA E-01, E-02, E-03
EJE 26-26 / CORTE B-B / TRAMO W-S M3 1 1.00 5.90 0.25 0.65 0.96 LAMINA E-01, E-02, E-03
EJE 28-28 / CORTE F-F / TRAMO W-S M3 1 1.00 6.45 0.15 0.55 0.53 LAMINA E-01, E-02, E-03
EJE U /CORTE G-G / TRAMO 28 - 31 M3 1 1.00 2.65 0.15 0.55 0.22 LAMINA E-01, E-02, E-03
M3 1 1.00 1.19 0.15 0.55 0.10 LAMINA E-01, E-02, E-03

Pgina 3
PLANILLA DE METRADOS DE ESTRUCTURAS
PROYECTO: ' AMPLIACI'ON Y MEJORAMIENTO DE LAS CONDICIONES BASICAS DEL SERVICIO EDUCATIVO EN LA I.E. N DEPARTAMENTO :SAN MARTN
0233 MONTECRISTO - SHUNTE - TOCAHE - SAN MART'IN'' PROVINCIA TOCACHE
FECHA : JUNIO DEL 2012 DISTRITO SHUNTE

ITEM DESCRIPCION UND CAN ELEM. L A H PARCIAL SUB TOTAL TOTAL OBSERVACIONES

01.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL M2 17.62


MODULO I 17.62 LAMINA E-01
EJE W / CORTE C-C / TRAMO 22-31 M3 1 2.00 13.00 0.15 0.65 2.54 LAMINA E-01, E-02, E-03
EJE S / CORTE D / TRAMO 22-31 M3 1 2.00 2.35 0.15 0.65 0.46 LAMINA E-01, E-02, E-03
EJE S / CORTE E-E / TRAMO 22-31 M3 3 2.00 2.23 0.15 0.65 1.30 LAMINA E-01, E-02, E-03
M3 3 2.00 1.00 0.15 0.30 0.27 LAMINA E-01, E-02, E-03
EJE 31 Y 22 /CORTE A'-A' Y A-A M3 2 2.00 5.90 0.25 1.60 9.44 LAMINA E-01, E-02, E-03
EJE 26-26 / CORTE B-B / TRAMO W-S M3 1 2.00 5.90 0.25 0.65 1.92 LAMINA E-01, E-02, E-03
EJE 28-28 / CORTE F-F / TRAMO W-S M3 1 2.00 6.45 0.15 0.55 1.06 LAMINA E-01, E-02, E-03
EJE U /CORTE G-G / TRAMO 28 - 31 M3 1 2.00 2.65 0.15 0.55 0.44 LAMINA E-01, E-02, E-03
M3 1 2.00 1.19 0.15 0.55 0.20 LAMINA E-01, E-02, E-03

01.04.05.03 ACERO ESTRUCTURAL FY=4200kg/cm2 KG 218.06


MODULO I KG 1.00 218.06 218.06 LAMINA E-01, E-02, E-03

01.04.06 COLUMNAS
01.04.06.01 CONCRETO F'C= 210 KG/CM2. PARA COLUMNAS M3 28.75
MODULO I 28.75 LAMINA E-01, E-02, E-03
PRIMER NIVEL
C-1 M3 4.00 AREA 0.33 5.25 6.83 LAMINA E-01, E-02, E-03
C-2 M3 2.00 AREA 0.31 5.25 3.28 LAMINA E-01, E-02, E-03
C-3 M3 4.00 AREA 0.19 5.25 3.94 LAMINA E-01, E-02, E-03
C-4 M3 3.00 0.60 0.25 5.25 2.36 LAMINA E-01, E-02, E-03
SEGUNDO NIVEL
C-1 M3 4.00 AREA 0.33 3.80 4.94 LAMINA E-01, E-02, E-03
C-2 M3 2.00 AREA 0.31 3.80 2.38 LAMINA E-01, E-02, E-03
C-3 M3 4.00 AREA 0.19 3.80 2.85 LAMINA E-01, E-02, E-03
C-4 M3 3.00 0.60 0.25 4.85 2.18 LAMINA E-01, E-02, E-03

01.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL M2 229.28


MODULO I 229.28
PRIMER NIVEL LAMINA E-01
C-1 M2 4.00 Perimetro 3.00 4.35 52.20 LAMINA E-01, E-02, E-03
C-2 M2 2.00 Perimetro 3.00 4.35 26.10 LAMINA E-01, E-02, E-03
C-3 M2 2.00 Perimetro 1.75 4.35 15.23 LAMINA E-01, E-02, E-03
M2 2.00 Perimetro 1.50 4.35 13.05 LAMINA E-01, E-02, E-03
C-4 M2 3.00 Perimetro 1.70 4.35 22.19 LAMINA E-01, E-02, E-03
SEGUNDO NIVEL LAMINA E-02
C-1 M2 4.00 Perimetro 3.00 3.20 38.40 LAMINA E-01, E-02, E-03
C-2 M2 2.00 Perimetro 3.00 3.20 19.20 LAMINA E-01, E-02, E-03
C-3 M2 3.00 Perimetro 1.75 3.20 16.80 LAMINA E-01, E-02, E-03
M2 1.00 Perimetro 1.50 3.20 4.80 LAMINA E-01, E-02, E-03
C-4 M2 3.00 Perimetro 1.70 4.18 21.32 LAMINA E-01, E-02, E-03

01.04.07.03 ACERO ESTRUCTURAL FY=4200kg/cm2 Kg 3,848.29


MODULO I Kg 1.00 3,848.29 3,848.29 LAMINA E-01, E-02, E-03

Pgina 4
PLANILLA DE METRADOS DE ESTRUCTURAS
PROYECTO: ' AMPLIACI'ON Y MEJORAMIENTO DE LAS CONDICIONES BASICAS DEL SERVICIO EDUCATIVO EN LA I.E. N DEPARTAMENTO :SAN MARTN
0233 MONTECRISTO - SHUNTE - TOCAHE - SAN MART'IN'' PROVINCIA TOCACHE
FECHA : JUNIO DEL 2012 DISTRITO SHUNTE

ITEM DESCRIPCION UND CAN ELEM. L A H PARCIAL SUB TOTAL TOTAL OBSERVACIONES

01.04.07 COLUMNETAS
01.04.07.01 CONCRETO F'C= 210 KG/CM2. M3 1.97
MODULO I 1.97
PRIMER NIVEL LAMINA E-01
C-A EJE W - W M3 7.00 0.25 0.15 1.20 0.32 LAMINA E-01, E-02, E-03
M3 1.00 0.25 0.15 1.80 0.07 LAMINA E-01, E-02, E-03
M3 1.00 0.25 0.15 3.00 0.11 LAMINA E-01, E-02, E-03
C-A EJE S-S M3 6.00 0.25 0.15 1.50 0.34 LAMINA E-01, E-02, E-03

SEGUNDO NIVEL LAMINA E-02


C-A EJE W - W M3 8.00 0.25 0.15 1.20 0.36 LAMINA E-01, E-02, E-03
C-A EJE S-S M3 8.00 0.25 0.15 1.50 0.45 LAMINA E-01, E-02, E-03
C-A EN PARAPETO M3 8.00 0.25 0.15 1.10 0.33 LAMINA E-01, E-02, E-03

01.04.07.02 ENCOFRADO Y DESENCOFRADO NORMAL M2 31.36


MODULO I 31.36
PRIMER NIVEL LAMINA E-01
C-A EJE W - W M2 7.00 0.50 1.20 4.20 LAMINA E-01, E-02, E-03
M2 1.00 0.50 1.80 0.90 LAMINA E-01, E-02, E-03
M2 1.00 0.15 3.00 0.45 LAMINA E-01, E-02, E-03
C-A EJE S-S M2 5.00 0.50 1.50 3.75 LAMINA E-01, E-02, E-03
M2 3.00 0.65 1.50 2.93 LAMINA E-01, E-02, E-03
SEGUNDO NIVEL LAMINA E-02
C-A EJE W - W M2 8.00 0.80 1.20 7.68 LAMINA E-01, E-02, E-03
C-A EJE S-S M2 6.00 0.50 1.50 4.50 LAMINA E-01, E-02, E-03
M2 2.00 0.65 1.50 1.95 LAMINA E-01, E-02, E-03
C-A EN PARAPETO M2 14.00 0.25 1.10 3.85 LAMINA E-01, E-02, E-03
M2 7.00 0.15 1.10 1.16 LAMINA E-01, E-02, E-03

01.04.07.03 ACERO ESTRUCTURAL FY=4200kg/cm2 Kg 366.89 LAMINA E-01


MODULO I Kg 1.00 366.89 366.89 LAMINA E-01, E-02, E-03

01.04.08 VIGAS
01.04.08.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS M3 58.47
MODULO I 58.47 LAMINA E-01, E-02, E-03
PRIMER PISO LAMINA E-02
V 101 (30 X 60) M3 2.00 1.00 8.75 0.30 0.60 3.15 LAMINA E-01, E-02, E-03
V 102 (25 X 40) M3 3.00 1.00 2.95 0.25 0.40 0.89 LAMINA E-01, E-02, E-03
M3 3.00 1.00 2.25 0.25 0.40 0.68 LAMINA E-01, E-02, E-03
V 103 (25 X 40) M3 2.00 4.00 3.25 0.25 0.55 3.58 LAMINA E-01, E-02, E-03
V 104 (15X20) M3 1.00 1.00 15.06 0.15 0.20 0.45 LAMINA E-01, E-02, E-03

Pgina 5
PLANILLA DE METRADOS DE ESTRUCTURAS
PROYECTO: ' AMPLIACI'ON Y MEJORAMIENTO DE LAS CONDICIONES BASICAS DEL SERVICIO EDUCATIVO EN LA I.E. N DEPARTAMENTO :SAN MARTN
0233 MONTECRISTO - SHUNTE - TOCAHE - SAN MART'IN'' PROVINCIA TOCACHE
FECHA : JUNIO DEL 2012 DISTRITO SHUNTE

ITEM DESCRIPCION UND CAN ELEM. L A H PARCIAL SUB TOTAL TOTAL OBSERVACIONES

SEGUNDO PISO LAMINA E-03


V 201 30 X 60 M3 2.00 14.30 0.30 0.60 5.15 LAMINA E-01, E-02, E-03
V 201 M3 1.00 1.04 0.30 0.20 0.06 LAMINA E-01, E-02, E-03
V 201 M3 1.00 2.35 0.30 0.20 0.14 LAMINA E-01, E-02, E-03
V 202 25 X 60 M3 3.00 2.00 Area 13.23 0.25 19.85 LAMINA E-01, E-02, E-03
V 202 M3 3.00 1.04 0.30 0.20 0.19 LAMINA E-01, E-02, E-03
V 202 M3 3.00 2.35 0.30 0.20 0.42 LAMINA E-01, E-02, E-03
M3 3.00 Area 0.66 0.25 0.50 LAMINA E-01, E-02, E-03
V 203 (25 X 60) M3 2.00 4.00 3.25 0.25 0.55 3.58 LAMINA E-01, E-02, E-03
M3 2.00 1.00 0.45 0.25 0.55 0.12 LAMINA E-01, E-02, E-03
V T 30X70 M3 1.00 1.00 Area 1.16 15.66 18.20 LAMINA E-01, E-02, E-03
M3 1.00 1.00 Area 0.51 0.45 0.23 LAMINA E-01, E-02, E-03
V B 15X20 M3 2.00 16.11 0.15 0.20 0.97 LAMINA E-01, E-02, E-03
M3 1.00 10.75 0.15 0.20 0.32 LAMINA E-01, E-02, E-03

01.04.08.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS M2 435.31


MODULO I 435.31 LAMINA E-01, E-02, E-03
PRIMER PISO LAMINA E-02
V 101 (30 X 60) M3 2.00 2.00 8.75 0.60 21.00 LAMINA E-01, E-02, E-03
M3 2.00 1.00 8.75 0.30 5.25 LAMINA E-01, E-02, E-03
V 102 (25 X 40) M3 3.00 4.00 2.95 0.40 14.16 LAMINA E-01, E-02, E-03
M3 3.00 2.00 2.95 0.25 4.43 LAMINA E-01, E-02, E-03
V 102 (25 X 40) M3 3.00 2.00 2.25 0.40 5.40 LAMINA E-01, E-02, E-03
M3 3.00 1.00 2.25 0.25 1.69 LAMINA E-01, E-02, E-03
V 103 (25 X 40) M3 2.00 8.00 3.25 0.55 28.60 LAMINA E-01, E-02, E-03
M3 2.00 4.00 3.25 0.25 6.50 LAMINA E-01, E-02, E-03
V 104 (15X20) M3 1.00 2.00 15.06 0.20 6.02 LAMINA E-01, E-02, E-03
M3 1.00 1.00 15.06 0.15 2.26 LAMINA E-01, E-02, E-03

SEGUNDO PISO LAMINA E-03


V 201 30 X 60 M3 2.00 2.00 14.30 0.60 34.32 LAMINA E-01, E-02, E-03
M3 2.00 1.00 14.30 0.30 8.58 LAMINA E-01, E-02, E-03
V 201 M3 1.00 2.00 1.04 0.20 0.42 LAMINA E-01, E-02, E-03
M3 1.00 1.00 1.04 0.30 0.31 LAMINA E-01, E-02, E-03
V 201 M3 1.00 2.00 2.35 0.20 0.94 LAMINA E-01, E-02, E-03
M3 1.00 1.00 2.35 0.30 0.71 LAMINA E-01, E-02, E-03
V 202 25 X 60 M3 3.00 4.00 Area 13.23 158.81 LAMINA E-01, E-02, E-03
M3 3.00 2.00 1.04 0.25 1.56 LAMINA E-01, E-02, E-03
V 202 M3 3.00 2.00 1.04 0.20 1.25 LAMINA E-01, E-02, E-03
M3 3.00 1.00 1.04 0.30 0.94 LAMINA E-01, E-02, E-03
V 202 M3 3.00 2.00 2.35 0.20 2.82 LAMINA E-01, E-02, E-03
M3 3.00 1.00 2.35 0.30 2.12 LAMINA E-01, E-02, E-03
V 202 M3 3.00 2.00 Area 0.66 3.96 LAMINA E-01, E-02, E-03
M3 3.00 1.00 0.25 0.75 LAMINA E-01, E-02, E-03
V 203 (25 X 60) M3 2.00 8.00 3.25 0.55 28.60 LAMINA E-01, E-02, E-03
M3 2.00 4.00 3.25 0.25 6.50 LAMINA E-01, E-02, E-03
V 203 M3 2.00 2.00 0.45 0.55 0.99 LAMINA E-01, E-02, E-03
M3 2.00 1.00 0.45 0.25 0.23 LAMINA E-01, E-02, E-03
V T 30X70 M3 1.00 1.00 perimetro 3.94 15.66 61.70 LAMINA E-01, E-02, E-03
VT M3 1.00 1.00 perimetro 1.96 0.45 0.88 LAMINA E-01, E-02, E-03
V B 15X20 M3 2.00 2.00 16.11 0.20 12.89 LAMINA E-01, E-02, E-03
M3 2.00 1.00 16.11 0.15 4.83 LAMINA E-01, E-02, E-03
VB M3 1.00 2.00 10.75 0.20 4.30 LAMINA E-01, E-02, E-03
M3 1.00 1.00 10.75 0.15 1.61 LAMINA E-01, E-02, E-03

01.04.08.03 ACERO ESTRUCTURAL FY=4200kg/cm2 Kg 3,754.00


MODULO I Kg 1.00 3,754.00 3,754.00 LAMINA E-01, E-02, E-03

Pgina 6
PLANILLA DE METRADOS DE ESTRUCTURAS
PROYECTO: ' AMPLIACI'ON Y MEJORAMIENTO DE LAS CONDICIONES BASICAS DEL SERVICIO EDUCATIVO EN LA I.E. N DEPARTAMENTO :SAN MARTN
0233 MONTECRISTO - SHUNTE - TOCAHE - SAN MART'IN'' PROVINCIA TOCACHE
FECHA : JUNIO DEL 2012 DISTRITO SHUNTE

ITEM DESCRIPCION UND CAN ELEM. L A H PARCIAL SUB TOTAL TOTAL OBSERVACIONES

01.04.09 VIGUETAS
01.04.09.01 CONCRETO F'C= 210 KG/CM2. M3 0.28
MODULO I 0.28
PRIMER PISO LAMINA E-02
EJE W-W/ TRAMO 22-24 / 26 - 24 M3 2.00 1.00 2.70 0.15 0.10 0.08 LAMINA E-01, E-02, E-03
EJE W-W/ TRAMO 28-26 M3 1.00 1.00 2.70 0.15 0.10 0.04 LAMINA E-01, E-02, E-03
EJE W-W/ TRAMO 28-31 M3 1.00 1.00 1.90 0.15 0.10 0.03 LAMINA E-01, E-02, E-03
M3 1.00 1.00 0.62 0.15 0.10 0.01 LAMINA E-01, E-02, E-03
EJE S-S/ TRAMO 22-24 M3 1.00 1.00 2.70 0.15 0.10 0.04 LAMINA E-01, E-02, E-03
EJE S-S/ TRAMO 24-31 M3 3.00 1.00 1.72 0.15 0.10 0.08 LAMINA E-01, E-02, E-03

SEGUNDO PISO LAMINA E-03


EJE W-W / TRAMO 22-31 M3 1.00 4.00 2.70 0.15 0.10 0.16 LAMINA E-01, E-02, E-03
EJE S-S / TRAMO 22-24 / 26-28 M3 1.00 1.00 2.70 0.15 0.10 0.04 LAMINA E-01, E-02, E-03
EJE S-S / TRAMO 24-26 / 28-31 M3 2.00 1.00 2.70 0.15 0.10 0.08 LAMINA E-01, E-02, E-03
EJE S-S / TRAMO E'-C' M3 2.00 1.00 1.72 0.15 0.10 0.05 LAMINA E-01, E-02, E-03
VIGUETAS EN PARAPETOS M3 1.00 1.00 15.06 0.15 0.10 0.23 LAMINA E-01, E-02, E-03

01.04.09.02 ENCOFRADO Y DESENCOFRADO NORMAL M2 16.76


MODULO I 16.76
PRIMER PISO LAMINA E-02
EJE W-W/ TRAMO 22-24 / 26 - 24 M2 2.00 2.00 2.70 0.15 1.62 LAMINA E-01, E-02, E-03
EJE W-W/ TRAMO 28-26 M2 1.00 2.00 2.70 0.15 0.81 LAMINA E-01, E-02, E-03
EJE W-W/ TRAMO 28-31 M2 1.00 2.00 1.90 0.15 0.57 LAMINA E-01, E-02, E-03
M2 1.00 2.00 0.62 0.15 0.19 LAMINA E-01, E-02, E-03
EJE S-S/ TRAMO 22-24 M2 1.00 2.00 2.70 0.15 0.81 LAMINA E-01, E-02, E-03
EJE S-S/ TRAMO 24-31 M2 3.00 2.00 1.72 0.15 1.55 LAMINA E-01, E-02, E-03

SEGUNDO PISO LAMINA E-03


EJE W-W / TRAMO 22-31 M2 4.00 2.00 2.70 0.15 3.24 LAMINA E-01, E-02, E-03
EJE S-S / TRAMO 22-24 / 26-28 M2 1.00 2.00 2.70 0.15 0.81 LAMINA E-01, E-02, E-03
EJE S-S / TRAMO 24-26 / 28-31 M2 2.00 2.00 2.70 0.15 1.62 LAMINA E-01, E-02, E-03
EJE S-S / TRAMO E'-C' M2 2.00 2.00 1.72 0.15 1.03 LAMINA E-01, E-02, E-03
VIGUETAS EN PARAPETOS M2 1.00 2.00 15.06 0.15 4.52 LAMINA E-01, E-02, E-03

01.04.09.03 ACERO ESTRUCTURAL FY=4200kg/cm2 Kg 42.11


MODULO I Kg 1.00 42.11 42.11 LAMINA E-01, E-02, E-03

Pgina 7
PLANILLA DE METRADOS DE ESTRUCTURAS
PROYECTO: ' AMPLIACI'ON Y MEJORAMIENTO DE LAS CONDICIONES BASICAS DEL SERVICIO EDUCATIVO EN LA I.E. N DEPARTAMENTO :SAN MARTN
0233 MONTECRISTO - SHUNTE - TOCAHE - SAN MART'IN'' PROVINCIA TOCACHE
FECHA : JUNIO DEL 2012 DISTRITO SHUNTE

ITEM DESCRIPCION UND CAN ELEM. L A H PARCIAL SUB TOTAL TOTAL OBSERVACIONES

01.04.10 ALIGERADO M3 27.92


01.04.10.01 CONCRETO F'C= 210 KG/CM2. EN LOSA ALIGERADA 27.92
MODULO I
PRIMER NIVEL M3 2.00 Area= 26.95 factor 0.09 4.85 LAMINA E-01, E-02, E-03
M3 2.00 Area= 27.82 factor 0.09 5.01 LAMINA E-01, E-02, E-03
VOLADIZO M3 2.00 Area= 8.10 factor 0.09 1.46 LAMINA E-01, E-02, E-03
M3 2.00 Area= 8.36 factor 0.09 1.50 LAMINA E-01, E-02, E-03

SEGUNDO NIVEL M3 2.00 Area= 28.18 factor 0.09 5.07 LAMINA E-01, E-02, E-03
M3 2.00 Area= 29.13 factor 0.09 5.24 LAMINA E-01, E-02, E-03
VOLADIZO M3 2.00 Area= 4.00 factor 0.09 0.72 LAMINA E-01, E-02, E-03
M3 2.00 Area= 4.14 factor 0.09 0.75 LAMINA E-01, E-02, E-03
M3 2.00 Area= 9.05 factor 0.09 1.63 LAMINA E-01, E-02, E-03
M3 2.00 Area= 9.35 factor 0.09 1.68 LAMINA E-01, E-02, E-03

01.04.10.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERAD M2 310.18


MODULO I 310.18
PRIMER NIVEL M2 2.00 Area= 26.95 53.90 LAMINA E-01, E-02, E-03
M2 2.00 Area= 27.82 55.64 LAMINA E-01, E-02, E-03
VOLADIZO M2 2.00 Area= 8.10 16.20 LAMINA E-01, E-02, E-03
M2 2.00 Area= 8.36 16.72 LAMINA E-01, E-02, E-03

SEGUNDO NIVEL M2 2.00 Area= 28.18 56.36 LAMINA E-01, E-02, E-03
M2 2.00 Area= 29.13 58.27 LAMINA E-01, E-02, E-03
VOLADIZO M2 2.00 Area= 4.00 8.01 LAMINA E-01, E-02, E-03
M2 2.00 Area= 4.14 8.28 LAMINA E-01, E-02, E-03
M2 2.00 Area= 9.05 18.10 LAMINA E-01, E-02, E-03
M2 2.00 Area= 9.35 18.71 LAMINA E-01, E-02, E-03

01.04.10.03 LADRILLO DE ARCILLA HUECO 15X30X30 Und 2,583.79


factor
MODULO I Und 8.33 310.18 2,584 LAMINA E-01, E-02, E-03

01.04.10.04 ACERO ESTRUCTURAL FY=4200kg/cm2 KG 1,607.51


MODULO I KG 1.00 1,607.51 LAMINA E-01, E-02, E-03

Pgina 8
CONCRETO PARA LOSA ALIGERADA BLOQUE 5

OBRAS DE CONCRETO ARMADO UNIDAD


CONCRETO PARA LOSA ALIGERADA PRIMER PISO m3

DESCRIPCION Nro. LOSA (m2) LADRILLO (m) SUB TOTAL TOTAL


VECES AREA ESPESOR LARGO ANCHO ESPESOR (m3) (m3)
1 115.21 0.2 0.3 0.3 0.15 10.086059

VOLUMEN . = VOLUMEN. DE _ VOLUMEN. DE


DE CONCRETO LOSA ALIGERADA LADRILLOS

10.086059
TENIENDO EN CUENTA LOS DESPERDICIOS AGREGAREMOS UN 5% 0.504303 10.590362

OBRAS DE CONCRETO ARMADO UNIDAD


CONCRETO PARA LOSA ALIGERADA SEGUNDO PISO m3

DESCRIPCION Nro. LOSA (m2) LADRILLO (m) SUB TOTAL TOTAL


VECES AREA ESPESOR LARGO ANCHO ESPESOR (m3) (m3)
1 163.4304 0.2 0.3 0.3 0.15 14.307514
SE TIENE EN
CUENTA LA
INCLINACION DEL
TECHO

VOLUMEN . = VOLUMEN. DE _ VOLUMEN. DE


DE CONCRETO LOSA ALIGERADA LADRILLOS

14.307514
TENIENDO EN CUENTA LOS DESPERDICIOS AGREGAREMOS UN 5% 0.7153757 15.02289
METRADO DE ACERO - CIMIENTO ARMADO

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1
01.04.01.02 CIMIENTO ARMADO MODULO I
CA-1
ACERO FY=4200 KG/CM2 L=17.00 x 1.20 1/2" @ 0.15
L= 17.00
A= 1.20 16.85
1/2 16.85 8.00 1.00 134.80
1.05
1/2 1.05 113.00 1.00 118.65

CA-2 L=17.00 x 1.80 1/2" @ 0.15


ACERO FY=4200 KG/CM2 L= 17.00
A= 1.80 16.85
1/2 16.85 12.00 1.00 202.20
1.65
1/2 1.65 113.00 1.00 186.45

CA-3
ACERO FY=4200 KG/CM2 L=8.50 x 1.20 1/2" @ 0.15
L= 8.50
A= 1.20 8.35
1/2 8.35 8.00 2.00 133.60
1.05
1/2 1.05 57.00 2.00 119.70

CA-4 L=8.50 x 1.80 1/2" @ 0.15


ACERO FY=4200 KG/CM2 L= 8.50
A= 1.80 8.35
1/2 8.35 12.00 1.00 100.20
1.65
1/2 1.65 57.00 1.00 94.05

Peso en kilogramos por metro lineal 0.25 0.58 1.02 1.69 2.86 4.04 Total en kg
Longitud total por dimetro, en metros lineales - - 1,089.65 - - -
Total en kilogramos por dimetro - - 1,111.44 - - - 1,111.44
METRADO DE ACERO - VIGAS DE CIMENTACION

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de E LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1
01.04.02.03 VIGAS DE CONEXIN MODULO I
ACERO FY=4200 KG/CM2 L=17.00 EJE "W" Y "S"
Vco-01
4 5/8" + 2 1/2"
L= 17.00
16.92
0.3 0.30 5/8 18.42 4.00 2.00 147.36

REFUERZOS 16.92
1/2 16.92 2.00 2.00 67.68

ESTRIBOS 3/8", 1@ 0.05 ,2@ 0.10


,1@ 0.15 resto @ 0.25
0.17
H= 0.70
A= 0.25 3/8 1.73 32.00 2.00 110.72
Ltotal= 0.62 3/8 1.73 32.00 2.00 110.72
3.25 3/8 1.73 32.00 2.00 110.72
3.25 3/8 1.73 32.00 2.00 110.72
3.25
3.25

Peso en kilogramos por metro lineal 0.25 0.58 1.02 1.69 2.86 4.04 Total en kg
Longitud total por dimetro, en metros lineales - 442.88 67.68 147.36 - -
Total en kilogramos por dimetro - 256.87 69.03 249.04 - - 574.94

01.04.03.03 VIGAS DE CIMENTACION


ACERO FY=4200 KG/CM2 L=7.50 EJE "22' ", "26' " Y "31"
VCI-01
6 5/8" + 2 1/2"
L= 7.50
7.42
0.3 0.30 5/8 8.92 6.00 3.00 160.56

REFUERZOS
7.42 1/2 7.42 2.00 3.00 44.52

ESTRIBOS 3/8", 1@ 0.05 ,2@ 0.10


,1@ 0.15 resto @ 0.25
0.17
H= 1.15
A= 0.25 3/8 2.63 31.00 3.00 244.59
Ltotal= 1.07 3/8 2.63 31.00 3.00 244.59
2.95
2.95

Peso en kilogramos por metro lineal 0.25 0.58 1.02 1.69 2.86 4.04 Total en kg
Longitud total por dimetro, en metros lineales - 489.18 44.52 160.56 - -
Total en kilogramos por dimetro - 283.72 45.41 271.35 - - 600.48
METRADO DE AC

N de Descripcin del Diseo de Acero


Partida Elemento Estructural en el elemento estructural
01.04.04.02 FALSO PISO REFORZADO MODULO I - AULA
ACERO FY=4200 KG/CM2 L=8.13 x 7.00 3/8" @ 0.30
L= 8.13
A= 7.00 7.98

6.85

SALA DE PROFESORES
ACERO FY=4200 KG/CM2 L=7.00 x 3.95 3/8" @ 0.30
L= 7.00
A= 3.95 6.85

3.8

DEIRECCION
ACERO FY=4200 KG/CM2 L=3.85 x 3.65 3/8" @ 0.30
L= 3.85
A= 3.65 3.70

3.5

SECRETARIA
ACERO FY=4200 KG/CM2 L=3.850 x 3.20 3/8" @ 0.30
L= 3.85
A= 3.20 3.70

3.05
METRADO DE ACERO - FALSO PISO REFORZADO

Dimetro Longitud por Repeticiones Cantidad de LONGITUD POR DIAMETRO DE VARILLA E


varilla diseo del diseo Estructurales 1/4 3/8 1/2

3/8 7.98 24.00 1.00 191.52

3/8 6.85 28.00 1.00 191.80

3/8 6.85 14.00 1.00 95.90

3/8 3.80 24.00 1.00 91.20

3/8 3.70 13.00 1.00 48.10

3/8 3.50 13.00 1.00 45.50

3/8 3.70 11.00 1.00 40.70

3/8 3.05 13.00 1.00 39.65

Peso en kilogramos por metro lineal 0.25 0.58 1.02


Longitud total por dimetro, en metros lineales - 744.37 -
Total en kilogramos por dimetro - 431.73 -
OR DIAMETRO DE VARILLA EN ML.
5/8 3/4 1

1.69 2.86 4.04 Total en kg


- - -
- - - 431.73
METRADO DE ACERO - SOBRECIMIENTOS ARMADOS

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de E LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1
01.04.05.03 SOBRECIMIENTOS ARMADOS MODULO I
ACERO FY=4200 KG/CM2 CORTE A-A / EJE 31, 26 Y 22
3/8" @ 0.3
L= 7.50
7.42
3/8 7.42 3.00 3.00 66.78
3/8 1.05 20.00 3.00 63.00
H= 0.95
L ESTRIBOS= 5.90

0.95

0.10
CORTE F-F / EJE 28
3/8" @ 0.3
L= 6.45
6.37
3/8 6.37 3.00 1.00 19.11
3/8 0.90 4.00 1.00 3.60
H= 0.80 3/8 0.90 6.00 1.00 5.40
L ESTRIBOS= 1.25 1.79 2.78 3/8 0.90 9.00 1.00 8.10

0.80

0.10

CORTE C-C / EJE W


3/8" @ 0.3
L= 17.00
16.92
3/8 17.22 3.00 1.00 51.66
3/8 1.05 11.00 4.00 46.20
H= 0.95
L ESTRIBOS=
3.20

0.95

0.10

CORTE E-E Y D-D / EJE S


3/8" @ 0.3
L= 17.00
16.92
3/8 16.92 2.00 1.00 33.84
13.92 3/8 13.92 1.00 1.00 13.92
3/8 1.05 7.00 3.00 22.05
3/8 0.45 11.00 1.00 4.95
H= 0.95 3/8 0.45 3.00 3.00 4.05
L ESTRIBOS= 2.23
L ESTRIBOS= 3.20
1.00

0.95

0.35

0.10 0.10
METRADO DE ACERO - SOBRECIMIENTOS ARMADOS

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de E LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1

CORTE G-G / EJE 28


3/8" @ 0.3
L= 3.23
3.15
3/8 3.15 3.00 2.00 18.90
3/8 0.90 8.00 1.00 7.20
H= 0.80 3/8 0.90 8.00 1.00 7.20
L ESTRIBOS= 2.50
2.50

0.80

0.10

Peso en kilogramos por metro lineal 0.25 0.58 1.02 1.69 2.86 4.04 Total en kg
Longitud total por dimetro, en metros lineales - 375.96 - - - -
Total en kilogramos por dimetro - 218.06 - - - - 218.06
METRADO DE ACERO - COLUMNAS

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de E LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1
01.04.07.03 COLUMNAS MODULO I
ACERO FY=4200 KG/CM2 COLUMNA C1
8 3/4" + 4 5/8"
H1= 9.05
L1= 8.94 3/4 9.54 8.00 4.00 305.12
0.3 0.30
5/8 9.54 4.00 4.00 152.56

ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.1 ,2@ 0.15


1,@ 0.2 resto @ 0.25
0.17 3/8 2.33 20.00 4.00 186.40
L= 1.00 3/8 2.33 20.00 4.00 186.40
A= 0.25
Ltotal= 0.92
3.16
3.21
ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.1 ,2@ 0.15 3/8 1.43 20.00 4.00 114.40
1,@ 0.2 resto @ 0.25 3/8 1.43 20.00 4.00 114.40
0.22
L= 0.50
A= 0.30
Ltotal= 0.42
3.16
3.21

ACERO FY=4200 KG/CM2 COLUMNA C2


8 3/4" + 4 5/8"
H1= 9.05
L1= 8.94 3/4 9.54 8.00 2.00 152.56
0.3 0.30
5/8 9.54 4.00 2.00 76.28

ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.1 ,2@ 0.15


1,@ 0.2 resto @ 0.25
0.17 3/8 2.33 20.00 2.00 93.20
L= 1.00 3/8 2.33 20.00 2.00 93.20
A= 0.25
Ltotal= 0.92
3.16
3.21
ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.1 ,2@ 0.15 3/8 1.33 20.00 2.00 53.20
1,@ 0.2 resto @ 0.25 3/8 1.33 20.00 2.00 53.20
0.17
L= 0.50
A= 0.25
Ltotal= 0.42
3.16
3.21
METRADO DE ACERO - COLUMNAS

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de E LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1
ACERO FY=4200 KG/CM2 COLUMNA C3
6 3/4" + 2 5/8"
H1= 9.05
L1= 8.94 3/4 9.54 6.00 4.00 228.84
0.3 0.30
5/8 9.54 2.00 4.00 76.28

ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.1 ,2@ 0.15


1,@ 0.2 resto @ 0.25
0.17 3/8 1.33 20.00 4.00 106.40
L= 0.50 3/8 1.33 20.00 4.00 106.40
A= 0.25
Ltotal= 0.42
3.16
3.21
ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.1 ,2@ 0.15 3/8 1.33 20.00 4.00 106.40
1,@ 0.2 resto @ 0.25 3/8 1.33 20.00 4.00 106.40
0.17
L= 0.50
A= 0.25
Ltotal= 0.42
3.16
3.21

ACERO FY=4200 KG/CM2 COLUMNA C4


8 5/8"
H1= 10.13
L1= 10.02
0.3 0.30
5/8 10.62 8.00 3.00 254.76

ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.1 ,2@ 0.15


1,@ 0.2 resto @ 0.25
0.17 3/8 1.17 20.00 3.00 70.20
L= 0.42 3/8 1.17 20.00 3.00 70.20
A= 0.25
Ltotal= 0.34
3.16
3.21
ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.1 ,2@ 0.15 3/8 1.17 20.00 3.00 70.20
1,@ 0.2 resto @ 0.25 3/8 1.17 25.00 3.00 87.75
0.17
L= 0.42
A= 0.25
Ltotal= 0.34
3.16
4.23

Peso en kilogramos por metro lineal 0.25 0.58 1.02 1.69 2.86 4.04 Total en kg
Longitud total por dimetro, en metros lineales - 1,618.35 - 559.88 686.52 -
Total en kilogramos por dimetro - 938.64 - 946.20 1,963.45 - 3,848.29
METRADO DE ACERO - COLUMNAS

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de E LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1
01.04.07.03 COLUMNETAS MODULO I

COLUMNETAS
4 3/8"
H1= 2.45
H2= 2.15
H3= 1.85 L1= 2.34 L2= 1.77 L2= 1.77 3/8 2.74 4.00 12.00 131.28
0.2 0.20 3/8 2.17 4.00 16.00 138.88
3/8 2.17 4.00 16.00 138.88

ESTRIBOS 1/4", 1@ 0.05 ,3@ 0.1


resto @ 0.25
0.07 1/4 0.63 13.00 12.00 98.28
L= 0.25 1/4 0.63 12.00 16.00 120.96
A= 0.15 1/4 0.63 11.00 16.00 110.88
Ltotal= 0.17
2.05
1.70
1.40

PARAPETOS
4 3/8"
H1= 1.10
L1= 1.02 3/8 1.42 4.00 10.00 56.80
0.2 0.20

ESTRIBOS 1/4", 1@ 0.05 ,3@ 0.1


resto @ 0.25
0.07 1/4 0.63 9.00 10.00 56.70
L= 0.25
A= 0.15
Ltotal= 0.17
1.00

Peso en kilogramos por metro lineal 0.25 0.58 1.02 1.69 2.86 4.04 Total en kg
Longitud total por dimetro, en metros lineales 386.82 465.84 - - - -
Total en kilogramos por dimetro 96.71 270.19 - - - - 366.89
METRADO DE ACERO - VIGAS PERALTADAS

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1
01.04.08.03 VIGAS PERALTADAS MODULO I
PRIMER NIVEL
VIGA VP-101, EJES 24 y 28
L= 9.75
9.67
0.3 0.1 3/4 10.07 2.00 2.00 40.28
5/8 2.76 2.00 2.00 11.04
0.3 2.46 4.71 0.1 5/8 4.81 2.00 2.00 19.24
1/2 9.11 2.00 2.00 36.44
9.11 3/4 10.07 3.00 2.00 60.42

0.3 7.42 2.25 0.10

ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.20 ,2@ 0.15


resto @ 0.25
0.22
H= 0.60
A= 0.30 3/8 1.63 32.00 2.00 104.32
Ltotal= 0.52
6.50 3/8 1.23 15.00 2.00 36.90

ESTRIBOS 3/8", 1@ 0.05 ,7@ 0.1


resto @ 0.2
0.22
H= 0.40
A= 0.30
Ltotal= 0.32
2.25

VIGA VP-102, EJES 22 Y 31


L= 9.75
9.67
0.3 0.30 5/8 11.17 2.00 3.00 67.02
3.45 5/8 3.55 2.00 3.00 21.30
0.1 5/8 8.90 2.00 3.00 53.40
0.3 8.6 5/8 3.35 2.00 3.00 20.10

0.55 2.7 0.1

ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.10


resto @ 0.2
0.17
H= 0.40
A= 0.25 3/8 1.13 29.00 3.00 98.31
Ltotal= 0.32 3/8 0.15 29.00 3.00 13.05
2.95 3/8 0.93 13.00 3.00 36.27
2.95

ESTRIBOS 3/8", 1@ 0.05 ,7@ 0.1


resto @ 0.2
0.17
H= 0.30
A= 0.25
Ltotal= 0.22
2.10
METRADO DE ACERO - VIGAS PERALTADAS

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1

VIGA VP-103/ EJE W Y S


L= 17.00
16.92
0.3 0.30 5/8 19.32 4.00 2.00 154.56

ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.10


resto @ 0.25
0.17
H= 0.40
A= 0.25 3/8 1.13 31.00 2.00 70.06
Ltotal= 0.32 3/8 1.13 31.00 2.00 70.06
3.25 3/8 1.13 31.00 2.00 70.06
3.25 3/8 1.13 31.00 2.00 70.06
3.25
3.25

76 VIGA 104 (.15 X .20)


L= 17.00
16.92
0.1 0.10 3/8 18.92 4.00 1.00 75.68

ESTRIBOS 1/4", @ 0.2

0.07
H= 0.20
A= 0.15 0.12 1/4 0.53 17.00 1.00 9.01
Ltotal= 1/4 0.53 17.00 1.00 9.01
3.25 1/4 0.53 17.00 1.00 9.01
3.25 1/4 0.53 17.00 1.00 9.01
3.25
3.25

SEGUNDO NIVEL
VIGA V-201, EJES 24 - 28

4.95 6.24 3/4 11.45 3.00 2.00 68.70


1/2 2.43 2.00 2.00 9.72
0.13 0.13 1/2 3.73 2.00 2.00 14.92
3/8 8.80 2.00 2.00 35.20
0.13 2.3 3.60 0.13 3/4 1.85 2.00 2.00 7.40
3/4 1.85 2.00 2.00 7.40
4.4 4.40 3/4 8.53 3.00 2.00 51.18
3/4 8.53 3.00 2.00 51.18

0.5 0.50
1.35 1.35

4.28 4.25 4.28


4.25

ESTRIBOS 3/8", 1@ 0.05 ,8@ 0.10


resto @ 0.2
0.22
H= 0.60
A= 0.30 3/8 1.63 26.00 2.00 84.76
Ltotal= 0.52 3/8 1.63 26.00 2.00 84.76
3.35 3/8 0.83 18.00 2.00 29.88
3.35 3/8 0.83 26.00 2.00 43.16

ESTRIBOS 3/8", 1@ 0.05 ,5@ 0.1


resto @ 0.15
0.22
H= 0.20
A= 0.30
Ltotal= 0.12
1.05
2.35
METRADO DE ACERO - VIGAS PERALTADAS

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1

VIGA V-202, EJES 22 Y 31

4.92 6.24
5/8 11.42 2.00 3.00 68.52
1/2 2.40 2.00 3.00 14.40
0.13 2.27 3.58 0.13 1/2 3.71 2.00 3.00 22.26
0.13 0.13 5/8 8.50 2.00 3.00 51.00
8.5 3/8 7.45 2.00 3.00 44.70
3/8 7.11 2.00 3.00 42.66
L1= L1= L1= L1= 3/8 5.45 1.00 3.00 16.35
7.45 7.11 5.45 3.78 3/8 3.78 2.00 3.00 22.68

ESTRIBOS 3/8", 1@ 0.25

0.17 3/8 2.13 12.00 3.00 76.68


HP= 0.90 3/8 2.13 16.00 3.00 102.24
A= 0.25
Ltotal= 0.82
2.95
2.95

ESTRIBOS 3/8", 1@ 0.05, 8@.10, RESTO @.15

0.17 3/8 0.73 27.00 3.00 59.13


H= 0.20
A= 0.25
0.12

VIGA V-203 / EJE W - S


L= 17.60
L= 17.00
17.52
0.1 0.30 5/8 19.72 2.00 2.00 78.88
5/8 2.15 2.00 2.00 8.60
0.1 2.05 1/2 19.12 2.00 2.00
5/8 19.12 2.00 2.00
16.92 76.48
0.2 0.20 76.48

ESTRIBOS 3/8", 1@ 0.05 ,7@ 0.10


resto @ 0.2
0.17
H= 0.60
A= 0.25 3/8 1.53 31.00 2.00 94.86
Ltotal= 0.52 3/8 1.53 31.00 2.00 94.86
3.25 3/8 1.53 31.00 2.00 94.86
3.25 3/8 1.53 31.00 2.00 94.86
3.25
3.25

ESTRIBOS 3/8", 1@ 0.05, 7@.10, RESTO @.20

0.17 3/8 0.73 5.00 2.00 7.30


H= 0.20
A= 0.25
0.12

VIGA VT-02 / EJE U


L= 17.60

17.52
0.30 0.3
1.4 5/8 18.12 4.00 1.00 72.48
1/2 18.12 6.00 1.00 108.72
5/8 18.12 3.00 1.00 54.36
1/2 1.40 4.00 1.00 5.60
ESTRIBOS 3/8", 1@ 0.05 ,12@ 0.10
resto @ 0.2
0.22 3/8 1.83 25.00 1.00 45.75
H= 0.70 3/8 1.83 25.00 1.00 45.75
A= 0.30 3/8 1.83 25.00 1.00 45.75
Ltotal= 0.62 3/8 1.83 25.00 1.00 45.75
3.85
3.97
3.98
3.85
METRADO DE ACERO - VIGAS PERALTADAS

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1
ESTRIBOS 3/8", @ 0.20

3/8 2.26 19.00 1.00 42.94


Ltotal= 0.33 0.33 3/8 2.26 20.00 1.00 45.20
3.85 0.10 0.1 3/8 2.26 20.00 1.00 45.20
3.97 0.10 3/8 2.26 20.00 1.00 45.20
3.98 0.10
3.85 0.60 0.60

VIGA V-B
L= 17.60
L= 10.75 17.52
0.1 0.10 3/8 19.52 4.00 2.00 156.16
3/8 12.67 4.00 1.00 50.68
0.10 10.67 0.10

ESTRIBOS 3/8", 1@ 0.05 ,4@ 0.10


resto @ 0.2
0.07
H= 0.20
A= 0.15 0.12 1/4 0.53 37.00 2.00 39.22
Ltotal= 1/4 0.53 37.00 2.00 39.22
3.85 1/4 0.53 37.00 2.00 39.22
3.97 1/4 0.53 37.00 2.00 39.22
3.98 1/4 0.53 32.00 1.00 16.96
3.85 1/4 0.53 32.00 1.00 16.96
2.95 1/4 0.53 28.00 1.00 14.84
2.95
2.10

Peso en kilogramos por metro lineal 0.25 0.58 1.02 1.69 2.86 4.04 Total en kg
Longitud total por dimetro, en metros lineales 241.68 2,242.09 288.54 756.98 286.56 -
Total en kilogramos por dimetro 60.42 1,300.41 294.31 1,279.30 819.56 - 3,754.00
N de Descripcin del Diseo de Acero
Partida Elemento Estructural en el elemento estructural
01.04.09.03 PRIMER NIVEL
VIGUETAS V . S1
L= 3.20
L= 2.22

L
0.10

ESTRIBOS 1/4", @ 0.05 resto @

0.07
H= 0.10
A= 0.15
Ltotal= 0.02
2.15
1.95
SEGUNDO NIVEL
V . S1
L= 3.20
L= 1.95

L
0.10

ESTRIBOS 1/4", @ 0.05 resto @

0.07
H= 0.10
A= 0.15
Ltotal= 0.02
2.15
1.95
Dimetro Longitud por Repeticiones Cantidad de LONGITUD POR DIAMETRO DE V
al varilla diseo del diseo Estructurales 1/4 3/8

3/8 4.52 2.00 5.00 45.20


3/8 3.54 2.00 3.00 21.24

0.10

0.2

1/4 0.14 12.00 3.00 5.04


1/4 0.14 11.00 6.00 9.24

3/8 4.52 2.00 4.00 36.16


3/8 3.27 2.00 6.00 39.24

0.10

0.2

1/4 0.14 12.00 3.00 5.04


1/4 0.14 11.00 6.00 9.24

Peso en kilogramos por metro lineal 0.25 0.58


Longitud total por dimetro, en metros lineales 14.28 66.44
Total en kilogramos por dimetro 3.57 38.54
LONGITUD POR DIAMETRO DE VARILLA EN ML.
1/2 5/8 3/4 1

1.02 1.69 2.86 4.04 Total en kg


- - - -
- - - - 42.11
METRADO DE ACERO - LOSA ALIGERADA

N de Descripcin del Diseo de Acero Dimetro Longitud por Repeticiones Cantidad de Elementos LONGITUD POR DIAMETRO DE VARILLA EN ML.
Partida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8 3/4 1
01.04.10.04 LOSA ALIGERADA MODULO I
PRIMER NIVEL
PAOS L=17.00
L= 17.00

16.96
1/2 17.36 19.00 1.00 329.84

1/2 2.90 19.00 1.00 55.10


2.90 1/2 2.90 19.00 1.00 55.10
2.90 1/2 2.90 19.00 1.00 55.10
2.90

3/8 1.48 19.00 2.00 56.24


L= 1.25 3/8 1.48 19.00 2.00 56.24
L= 1.25 1.23 0.25
1.23
PAOS L=17.00 - PASADIZOS
L= 17.00

16.96
1/2 16.96 5.00 1.00 84.80

2.90 1/2 2.90 5.00 1.00 14.50


2.90 1/2 2.90 5.00 1.00 14.50
2.90 1/2 2.90 5.00 1.00 14.50

3/8 1.33 5.00 2.00 13.30


L= 1.25 3/8 1.33 5.00 2.00 13.30
L= 1.25 1.23 0.10
1.23

ACERO TEMPERATURA
L= 9.75

9.71
1/4 9.71 64.00 2.00 1,242.88

SEGUNDO NIVEL
PAOS L=7.50
L= 7.50
0.25
5.31
1/2 5.56 10.00 2.00 111.20

2.22 0.25 1/2 2.47 10.00 2.00 49.40


1/2 2.50 10.00 1.00 25.00
1.25 1.25

ACERO TEMPERATURA
L= 26.10

26.06
1/4 26.06 30.00 2.00 1,563.60

Peso en kilogramos por metro lineal 0.25 0.58 1.02 1.69 2.86 4.04 Total en kg
Longitud total por dimetro, en metros lineales 2,806.48 139.08 809.04 - - -
Total en kilogramos por dimetro 701.62 80.67 825.22 - - - 1,607.51