MINUTES OF MEETING

ProgramforStudying,Designing&SupervisionProjectsofTheMinistryofHousinginTheKingdomofSaudi
ProgramTitle
Arabia
Project/SiteTitle DammamSouth Chairedby SamerElfiky
MeetingTitle WorkshopforRoadandElectricalItems
Dateofmeeting 20January2014 Starttime 11:00AM
Location(s) DammamSouthSiteOffice Endtime 16:00PM
Reference MOME009P143480013 Dateofnextmeeting

Attendees:

Name Job Title Company Mobile Email Signature

Engineering
SamerSaeedElfiky SAPL 0540609339 Samer.Elfiky@saudiparsons.com
Coordinator
SeniorRoads
KazimBangash SAPL Kazim.Bangash@saudiparsons.com
Engineer
Senior Electrical
ReyFerrer SAPL Rey.ferrer@saudiparsons.com
Engineer
Construction Al
AshrafAlKhalili
manager YAMAMAH
Al
SyedJafarBasha Technicalmanager syedjafar@yc.com.sa
YAMAMAH








Page1of4

MinutesofMeeting:
Status
SN Item/Discussions Action(s)tobetaken Actionby DueDate
(C/IP/D)*
1. ElectricalIssues






Advised the Contractor to
include the requirements of
Direct buried fiber optic cables
on Shop drawings as per SDCS-
02, PART-6. SEC specifications
FIBER OPTICS FOR MV to be provided to contractor
NETWORKS AS PER SEC
1.1 officially.

Commercial issue regarding
the requirements will be
under authority having
jurisdiction.








Currently , there is no design
drawing related to fiber optics for
LV network which requires the
50 mm HDPE duct with
routing of HDPE duct from each
rope for fiber optics
substation up to each Kw-hr meter.
1.2 cable for LV network as
Options are to be finalized whether
per SEC
we will provide separate design
drawings for the requirements or to
be included on shop drawings.


Calculations for building Apartments
to be provided in detail specifying
1.3 ElectricalCalculations
the number of floors and the Built up

area for each floor. If any

Page2of4

discrepancies arises between the


BOQ, SLD and the calculations. The
current calculation shall be followed.



Discrepancies between SLD and
layout for Potable water. Advised
1.4 Discrepancies contractor to submit an RFI.


The Contractor has not been aware
about the Service reservation layout
provided to them. It was until the
meeting they have found out that
there are Service reservation layout
provided to them. With this respect,
we advise the contractor to follow
the service reservation layout in
1.5 Service reservation layout terms of the location and routing of
MV, LV, street lighting,
Telecommunication cables.
Furthermore, it is the designer scope
of works that this service reservation
layout has been coordinated and
approved by all authority having
jurisdiction.


The Contractor has been advised
with some SEC requirements
regarding the location acceptable
location of Substation,
1.6 SECRequirements
Distribution Pillars, routing of
MV and LV cables, etc. , to be
implemented on their shop
drawings
Telecommunication network layout
to be checked in accordance with the
latest specifications and
requirements by STC. We will
1.7 Telecoms inform the contractor if the current
layout can adopt the latest STC
requirements otherwise changes
from layout may be required.


The option of redesigning
1.8 ServiceReservation
Dammam South according to

Page3of4

change in masterplan utilizing the


contractor is not an option
anymore since they raised their
hands of not doing so
2. RoadIssues



Contractor will be producing shop
drawings as per the latest MP
except profiles because their site SAPL/AL
team has limited capacity to YAMAMA
2.1
redesign profiles and they wont be
getting any assistance from their
design office. SAPL will redesign
profiles.



3. GeneralIssues
Contractor will submit workshop AL
drawings according to the new YAMAMA
3.1 StormDrainage
masterplan.

Contractor will submit workshop
drawings according to the new AL
3.2 Sewer
masterplan. YAMAMA


Note*:C:forcompletedaction,IP:InProgressandD:forDelayedAction(inthiscasedelayedperiodindayshastobe
mentioned)

MinutesofMeetingPreparedBy

Name SamerElfiky
Designation Engineeringcoordinator
Organization SaudiParsons

AnyadditionoromissionmustbebroughttotheattentionofSaudiArabianParsonsLtd.within2workingdaysof
thedateofissuanceofdraftminutesotherwisetheseminuteswillbeconsideredfinal.