Escolar Documentos
Profissional Documentos
Cultura Documentos
14,551.77
AZOTEA ( H = 1.00 m)
Elemento Carga Longitud Ancho Alto Area Cantidad TOTAL
Aligerado (H=20 cm) 300.00 1.00 0.00
Viga Principal 2,400.00 1.00 0.00
Viga Secundaria 2,400.00 1.00 0.00
Columna 2,400.00 0.35 0.30 1.00 1.00 252.00
Tabiqueria 1,800.00 1.00 0.00
Acabados 100.00 1.00 0.00
S/C (Viviendas) 200.00 12.90 1.00 2,580.00
2,832.00
RESUMEN:
CM CV TOTAL
PRIMER PISO : 11,971.77 2,580.00 14,551.77
SEGUNDO PISO : 10,933.44 2,580.00 13,513.44
TERCER PISO : 10,933.44 2,580.00 13,513.44
CUARTO PISO : 10,933.44 2,580.00 13,513.44
AZOTEA : 252.00 2,580.00 2,832.00
45,024.09 12,900.00 57,924.09
1.10 PG
C1 bxD =
0.30 x fc
bxD = 30 x 34 cm2
AZOTEA ( H = 1.00 m)
Elemento Carga Longitud Ancho Alto Area Cantidad TOTAL
Aligerado (H=20 cm) 300.00 1.00 0.00
Viga Principal 2,400.00 1.00 0.00
Viga Secundaria 2,400.00 1.00 0.00
Columna 2,400.00 0.30 0.40 1.00 1.00 288.00
Tabiqueria 1,800.00 1.00 0.00
Acabados 100.00 1.00 0.00
S/C (Viviendas) 200.00 7.48 1.00 1,496.00
1,784.00
RESUMEN:
CM CV TOTAL
PRIMER PISO : 9,827.32 1,496.00 11,323.32
SEGUNDO PISO : 9,299.56 1,496.00 10,795.56
TERCER PISO : 9,299.56 1,496.00 10,795.56
CUARTO PISO : 9,299.56 1,496.00 10,795.56
AZOTEA : 288.00 1,496.00 1,784.00
38,014.00 7,480.00 45,494.00
1.25 PG
C2 bxD =
0.25 x fc
bxD = 30 x 36 cm2
AZOTEA ( H = 1.00 m)
Elemento Carga Longitud Ancho Alto Area Cantidad TOTAL
Aligerado (H=20 cm) 300.00 1.00 0.00
Viga Principal 2,400.00 1.00 0.00
Viga Secundaria 2,400.00 1.00 0.00
Columna 2,400.00 0.30 0.30 1.00 1.00 216.00
Tabiqueria 1,800.00 1.00 0.00
Acabados 100.00 1.00 0.00
S/C (Viviendas) 200.00 6.94 1.00 1,388.00
1,604.00
RESUMEN:
CM CV TOTAL
PRIMER PISO : 7,806.55 1,388.00 9,194.55
SEGUNDO PISO : 6,271.33 1,388.00 7,659.33
TERCER PISO : 6,271.33 1,388.00 7,659.33
CUARTO PISO : 6,271.33 1,388.00 7,659.33
AZOTEA : 216.00 1,388.00 1,604.00
26,836.54 6,940.00 33,776.54
1.25 PG
C2 bxD =
0.25 x fc
bxD = 30 x 27 cm2
AZOTEA ( H = 1.00 m)
Elemento Carga Longitud Ancho Alto Area Cantidad TOTAL
Aligerado (H=20 cm) 300.00 1.00 0.00
Viga Principal 2,400.00 1.00 0.00
Viga Secundaria 2,400.00 1.00 0.00
Columna 2,400.00 0.30 0.30 1.00 1.00 216.00
Tabiqueria 1,800.00 1.00 0.00
Acabados 100.00 1.00 0.00
S/C (Viviendas) 200.00 4.03 1.00 806.00
1,022.00
RESUMEN:
CM CV TOTAL
PRIMER PISO : 4,816.54 806.00 5,622.54
SEGUNDO PISO : 4,486.33 806.00 5,292.33
TERCER PISO : 4,486.33 806.00 5,292.33
CUARTO PISO : 4,486.33 806.00 5,292.33
AZOTEA : 216.00 806.00 1,022.00
18,491.53 4,030.00 22,521.53
1.50 PG
C2 bxD =
0.20 x fc
bxD = 30 x 27 cm2
9,699.93
AZOTEA ( H = 1.00 m)
Elemento Carga Longitud Ancho Alto Area Cantidad TOTAL
Aligerado (H=20 cm) 300.00 1.00 0.00
Viga Principal 2,400.00 1.00 0.00
Viga Secundaria 2,400.00 1.00 0.00
Columna 2,400.00 0.35 0.30 1.00 1.00 252.00
Tabiqueria 1,800.00 1.00 0.00
Acabados 100.00 1.00 0.00
S/C (Viviendas) 200.00 8.51 1.00 1,702.00
1,954.00
RESUMEN:
CM CV TOTAL
PRIMER PISO : 7,997.93 1,702.00 9,699.93
SEGUNDO PISO : 7,855.10 1,702.00 9,557.10
TERCER PISO : 7,855.10 1,702.00 9,557.10
CUARTO PISO : 7,855.10 1,702.00 9,557.10
AZOTEA : 252.00 1,702.00 1,954.00
31,815.23 8,510.00 40,325.23
1.10 PG
C1 bxD =
0.30 x fc
bxD = 30 x 23 cm2
AZOTEA ( H = 1.00 m)
Elemento Carga Longitud Ancho Alto Area Cantidad TOTAL
Aligerado (H=20 cm) 300.00 1.00 0.00
Viga Principal 2,400.00 1.00 0.00
Viga Secundaria 2,400.00 1.00 0.00
Columna 2,400.00 0.30 0.40 1.00 1.00 288.00
Tabiqueria 1,800.00 1.00 0.00
Acabados 100.00 1.00 0.00
S/C (Viviendas) 200.00 7.48 1.00 1,496.00
1,784.00
RESUMEN:
CM CV TOTAL
PRIMER PISO : 9,827.32 1,496.00 11,323.32
SEGUNDO PISO : 9,299.56 1,496.00 10,795.56
TERCER PISO : 9,299.56 1,496.00 10,795.56
CUARTO PISO : 9,299.56 1,496.00 10,795.56
AZOTEA : 288.00 1,496.00 1,784.00
38,014.00 7,480.00 45,494.00
1.25 PG
C2 bxD =
0.25 x fc
bxD = 30 x 36 cm2
AZOTEA ( H = 1.00 m)
Elemento Carga Longitud Ancho Alto Area Cantidad TOTAL
Aligerado (H=20 cm) 300.00 1.00 0.00
Viga Principal 2,400.00 1.00 0.00
Viga Secundaria 2,400.00 1.00 0.00
Columna 2,400.00 0.30 0.30 1.00 1.00 216.00
Tabiqueria 1,800.00 1.00 0.00
Acabados 100.00 1.00 0.00
S/C (Viviendas) 200.00 6.94 1.00 1,388.00
1,604.00
RESUMEN:
CM CV TOTAL
PRIMER PISO : 7,806.55 1,388.00 9,194.55
SEGUNDO PISO : 6,271.33 1,388.00 7,659.33
TERCER PISO : 6,271.33 1,388.00 7,659.33
CUARTO PISO : 6,271.33 1,388.00 7,659.33
AZOTEA : 216.00 1,388.00 1,604.00
26,836.54 6,940.00 33,776.54
1.25 PG
C2 bxD =
0.25 x fc
bxD = 30 x 27 cm2
AZOTEA ( H = 1.00 m)
Elemento Carga Longitud Ancho Alto Area Cantidad TOTAL
Aligerado (H=20 cm) 300.00 1.00 0.00
Viga Principal 2,400.00 1.00 0.00
Viga Secundaria 2,400.00 1.00 0.00
Columna 2,400.00 0.30 0.30 1.00 1.00 216.00
Tabiqueria 1,800.00 1.00 0.00
Acabados 100.00 1.00 0.00
S/C (Viviendas) 200.00 4.03 1.00 806.00
1,022.00
RESUMEN:
CM CV TOTAL
PRIMER PISO : 4,816.54 806.00 5,622.54
SEGUNDO PISO : 4,486.33 806.00 5,292.33
TERCER PISO : 4,486.33 806.00 5,292.33
CUARTO PISO : 4,486.33 806.00 5,292.33
AZOTEA : 216.00 806.00 1,022.00
18,491.53 4,030.00 22,521.53
1.50 PG
C2 bxD =
0.20 x fc
bxD = 30 x 27 cm2