DESIGN CRITERIA
HANDBOOK
VOLUME I
DIRECTORATE OF FACILITIES
DECAH 20-1
WITH JUNE 2011 UPDATES
(Complete Reissue)
Division 03 - Concrete
03 30 00 Cast-In-Place Concrete
Design Criteria
Guide Specification
03 30 50 Insulated Freezer Floors
Design Criteria
Division 04 - Masonry
04 20 00 Unit Masonry
Design Criteria
Guide Specification
Division 05 - Metals
05 12 00 Structural Steel Framing
Design Criteria
Guide Specification
05 21 00 Steel Joist Framing
Design Criteria
Guide Specification
05 30 00 Steel Decking
Design Criteria
Guide Specification
05 40 00 Cold-Formed Metal Framing
Design Criteria
Guide Specification
05 50 13 Metal Fabrications
Design Criteria
Guide Specification
Design Plates
055013-01 Bumper Post
055013-02 Above Cooler Access - Isometric and Plan View
055013-03 Above Cooler Access - Elevations
05 51 00 Metal Stairs
Design Criteria
Guide Specification
05 52 00 Pipe Railings
Design Criteria
Guide Specification
Division 09 - Finishes
09 24 23 Portland Cement Plaster
Design Criteria
Guide Specification
09 29 00 Gypsum Board
Design Criteria
Guide Specification
09 30 00 Tiling
Design Criteria
Guide Specification
09 51 00 Acoustical Ceilings
Division 10 - Specialties
10 08 00 Commissioning of Specialties
10 10 00 Visual Display Surfaces
Design Criteria
Guide Specification
10 14 00 Signage
Design Criteria
Guide Specification
Design Plates
101400-01 Store Hours Sign
101400-02 Storage Height Restriction Sign
10 15 00 Interior Decor Specialties
Design Criteria
Guide Specification
10 21 13 Toilet Compartments
Design Criteria
Guide Specification
10 22 13 Wire Mesh Partitions
Design Criteria
Guide Specification
10 26 00 Wall and Equipment Protection
Design Criteria
Guide Specification
Design Plates
102600-01 Wood Bumper Rail
102600-02 Stainless Steel Bumper
10 28 13 Toilet Accessories
Design Criteria
Guide Specification
10 44 00 Fire Protection Specialties
Design Criteria
Guide Specification
10 51 13 Metal Lockers
Design Criteria
Guide Specification
10 56 23 Rotating Modular System
Design Criteria
Guide Specification
10 56 29 Storage Racks
Design Criteria
Guide Specification
Division 12 - Furnishings
12 21 13 Horizontal Louver Blinds
Design Criteria
Guide Specification
12 48 00 Entrance Mats and Grilles
Design Criteria
12 48 13.13 Surface Floor Mats
12 48 13.16 Recessed Floor Mats and Frames
12 48 16 Entrance Floor Grilles
Division 22 - Plumbing
22 05 00 Common Work Results for Plumbing
Design Criteria
Guide Specification
Design Plates
220500-01 Walk-In Box Floor Drain FD6 for Condensate From Unit Coolers
220500-03 Refrigerated Case Hub Drain Detail
220500-04 Grease Trap
Division 26 - Electrical
26 05 00 Common Work Results for Electrical
Design Criteria
Guide Specification
26 05 13 Medium-Voltage Cables
26 05 19 Low-Voltage Electrical Power Conductors and Cables
Design Criteria
Guide Specification
26 05 26 Grounding and Bonding for Electrical Systems
26 05 33 Raceways and Boxes for Electrical Systems
Design Criteria
Guide Specification
26 05 33.33 Tele-Power Poles
26 05 36 Cable Trays for Electrical Systems
Design Criteria
Guide Specification
26 05 48 Vibration and Seismic Controls for Electrical Systems
26 05 53 Identification for Electrical Systems
Design Criteria
Guide Specification
26 08 00 Commissioning for Electrical Systems
26 09 23 Lighting Control Devices
26 12 19 Medium-Voltage Transformers
26 22 00 Low-Voltage Transformers
Design Criteria
Guide Specification
26 23 00 Switchboards
Design Criteria
Guide Specification
26 24 16 Panelboards
Design Criteria
Guide Specification
26 24 19 Motor-Control Centers
Design Criteria
Guide Specification
26 25 00 Enclosed Bus Assemblies
26 27 26 Wiring Devices
Division 27 - Communications
27 08 00 Commissioning of Communication Equipment
27 15 00 Communications Horizontal Cabling
27 20 00 Datacom and Point-of-Sale Provisions
Design Criteria
Design Plates
272000-01 Emergency Generator Detail
272000-02 Point of Sale (POS) System Electrical Support 1
272000-03 Typical Under Floor Duct Arrangement
272000-05 Power Pole at Checkstand
272000-06 Data and Telephone Schematic
272000-07 POS Data Connectors
272000-08 CISIC Room Layout-Small
272000-09 CISIC Room Layout Med-Large
272000-10 Sub-Hub Room Layout
272000-11 Universal Paystation
272000-12 Self-Checkout Model 171
272000-13 Self-Checkouts Models 151 and 153
272000-14 Self-Checkouts Models 131 and 152
27 51 16 Public Address and Music System
27 80 00 Processing Area Signaling Systems
Division 31 - Earthwork
31 00 00 Earthwork
31 10 00 Site Clearing
31 31 16 Termite Control
Design Criteria
Guide Specification
Termite Map
Division 33 - Utilities
33 08 00 Commissioning of Utilities
33 11 00 Water Distribution
Design Criteria
Guide Specification
33 30 00 Sanitary Sewers
Design Criteria
Guide Specification
33 40 00 Storm Drainage Utilities
Appendices
Appendix A - Schedule and Tables
Standard Commissary Room and Finish Schedule
Commissary Door Schedule
Appendix B - Product Data Sheets
1A03-N Workstation General Office, Low Profile
1A03-R Workstation General Office, Stand alone
1B00 Bread Slice, Table Model
1B10-A Reach-In Freezer
1B10-B Freezer, Reach-In
1B11-B Refrigerator, Reach-In
1B12-A Rotating Single Rack Oven-Electric
1B12-B Rotating Single Rack Oven-Gas
1B13-A Rotating Double Rack Oven-Electric
1B15 Mini-Rotating Rack Convection Oven-Electric
1B20-A Single Wide Proof Box
1B20-B Double Wide Proof Box
1B22-B Retarder Roll-In Two-Door
1B28 Refrigerated Self-Service Case with Cake Decorator Station
1B29-A Self-Service Acrylic Door Merchandiser
1B29-B Self-Service Non-Refrigerated Bakery Display Case
1B30-B Self-Service Refrigerated Bakery Display Case
1B30-C Self-Service Refrigerated Bakery Display Case
1D04-B Refrigerator, Reach-In, 79 Cubic Feet
1D05 Prep and Display Case
1D09 Hot Foods, Single Section, Rotisserie Oven, 32 Chicken, Countertop
1D12 Hot Foods, Heated, Display Case
1D13 Prepared Foods, Refrigerated Display Case
1D14-A Case, Hot Foods, Heated, Self-Service Island, 3 Wells
1D14-B Case, Hot Foods, Heated, Self Service Island, 5 Wells
1D17 Preparation and Display Case for Pizza and Sandwiches
1D21 Deli Slicer Table
1E06-A Queuing System, Checkout, Traffic Control
1E06-B Queuing System, Checkout, Electronic Directional System with Flashing Light
1E06-C Queuing System, Checkout, Electronic Checkstand Light
1E08 Safe, 22 Cubic Feet Capacity
1E10 Safe, 39 Cubic Feet Capacity
1E12 Key Control Cabinet
1G06/07 Frozen Food Wide Island Display Cases
1M00 Scale, Platform, Mobile
1M10 Conveyor, Meat-Loaf, Electric - Product Data
1M14 Chopper, Meat, 8 lbs Per Minute
A. SUMMARY
1. The June 2011 Updates consisted of a complete and total revision & reissue of the DeCA
Design Criteria and Guide Specifications.
a. Everything:
1) Design Criteria
2) Guide Specifications
3) Design Plates
4) Appendices
J.T. KINSEY
Director, HQ Operations
Kendra S. Warren
Director, Information Technology
DRAFT
AUTHORITY: Defense Commissary Agency Directives Management Program is established in
compliance with DoD Directive 5105.55, Defense Commissary Agency (DeCA), November 1990, and
the Federal Information Resources Management Regulations (FIRMR).
MANAGEMENT CONTROLS: This handbook does not contain Management Control provisions that
are subject to evaluation and testing as required by DeCAD 70-2 and as scheduled in DeCAD 70-3.
APPLICABILITY: This directive applies to the Defense Commissary Agency (DeCA) activities.
HOW TO SUPPLEMENT: This handbook may not be supplemented; however, suggested changes may
be submitted to DeCA/CIED.
HOW TO OBTAIN COPIES: Copies may be read or downloaded from the DeCA Intranet at
http://www.decadcpmac.com
SUMMARY: This handbook contains guidance that will be used for design and construction of all
DeCA commissary construction, addition/alteration, renovation, maintenance and repair and/or
improvement projects.
Facilities Program Management is responsible for managing, coordinating and executing the design and
construction of commissary facilities. Our mission is to deliver a quality product on time and within cost. In addition
to customer requirements for operating and merchandising efficiency, commissary facilities are constructed
according to federal, state, and local laws, codes and standards, DoD policies, congressional guidance and standard
commercial construction practices.
The attached Design Criteria Handbook is intended to guide design and construction practices for
commissary facilities. Although it is intended primarily to guide architects and engineers in the design of new
commissary facilities or major additions and alterations to existing facilities, it also applies to design and
DRAFT
construction activities managed by other agents and minor projects managed through DeCAs region engineers. We
intend the criteria be used to guide all commissary design and construction efforts. Exceptions to this criteria should
be specifically requested in writing.
This document should never replace common sense, good engineering practice or ingenuity. We encourage
each project manager, architect and engineer to consider value engineering initiatives to help improve on quality and
lower life cycle costs to provide best value to the Government. Please document recommendations and Please
submit recommended changes electronically to the Lessons Learned feature on the following website:
http://www.decadcpmac.com.
This handbook is a living document that changes as design and construction methods change, new
materials and equipment are introduced and marketing strategies are adjusted. Revisions will be published live on
the Internet at http://www.decadcpmac.com/deca/. All Criteria Handbook subscribers will be notified via e-mail of
changes made to the document as they occur. Each e-mail will contain an attachment with the updated file. Changes
will be highlighted in yellow so users can easily determine which item was updated. In addition to the updates
published throughout the year, a formal submission of revisions will be posted each year in May. The next formal
update will be May 2006. All changes adopted throughout the year will be incorporated into this formal update and a
new baseline criteria will be established. Please submit recommended changes electronically to the Lessons Learned
feature on the following website: http://www.decadcpmac.com/deca/.
BOYCE BOURLAND
Facilities Program Manager
DeCA DESIGN CRITERIA HANDBOOK
1. GENERAL
1.1. These criteria are intended for use during the design and construction of commissary facilities.
1.2. These criteria also set basic facilities standards for use in the identification of deficiencies in existing
facilities for planning and programming purposes.
2. ORGANIZATION
2.1. This handbook consists of the following parts:
2.1.1. Requirements and Guidance.
2.1.2. As Applicable for Each Section in Division 01 through 33.
a. Design Criteria Guidance.
b. Guide Specification.
c. Design Standard Plates.
2.1.3. Appendix A - Schedules and Tables.
2.1.4. Appendix B - Product Data Sheets.
2.1.5. Appendix C - Commissioning.
2.1.6 Appendix D - Uniform Dcor Package.
3. INTENT
3.1. The intent of this Design Criteria Handbook is to have Architect-Engineers (A/E) include all items
necessary for the proper execution and completion of the Work by the Contractor awarded the Work.
3.2. The various parts of this handbook, including any graphical representations, are complementary, and
what is required by one part shall be as binding as if required by all.
3.3. A/E shall edit all UFGS format guide specifications as applicable to the project and incorporate them
into the contract documents.
4. CONVENTION OF MEANING
4.1. In general, this Design Criteria Handbook is written in the imperative mood.
4.2. DeCA Design Criteria is updated quarterly, with the baseline design criteria updated each year in
June; at which time Design Criteria, Guide Specifications, and Design Standard Plates will be reviewed for
applicability and documents will be re-dated to reflect the current year. Manufacturer product data will be
updated as necessary to remain current.
A summary of revisions for each quarterly Design Criteria Update will be posted on the DeCA Design
Criteria website.
4.3. In the interest of brevity, this handbook frequently omits modifying words such as "all and "any" and
articles such as "the" and "an", but the fact that a modifier or an article is absent from one statement and
June 2011 1
DeCA DESIGN CRITERIA HANDBOOK
5. DESIGN REQUIREMENTS
5.1. GENERAL
5.1.1. Design a completely functional and operational facility within the parameters of the cost and
scope constraints of the project. Should the designer anticipate impending cost overruns, make
recommendations to bring the scope and cost within the authorized limitations of the project. Include
this information in the design analysis and bring it to the DeCA Project Managers attention in writing.
5.1.2. Make every effort to reduce utility runs and site preparation requirements through proper design.
Include in the bid package identification of support costs outside the 5'-0" line.
5.1.3. Do not use deductive bid items in the bid schedule. Use additive bid items discriminately. DeCA
will approve and prioritize any additives.
5.1.4. Add/ Alter Projects shall be designed to indicate a logical sequence of site and building
construction phasing. The phasing design shall be clearly delineated to allow the Contractor to
develop accurate bid pricing and to understand the relationships of the integrated construction work
allowing the Contractor to develop a complete Project Phasing Schedule. Make certain the
construction activities will allow for use of the existing facilities maintaining continuous store operation
throughout the construction period. Phasing shall be reviewed during the design phases to ensure that
the needs of the installation, and store management are being met and as approved by DeCA
management. Refer to the Add/ Alter Construction Phasing Checklist attachment. Refer to section
013216 Construction Progress Documentation.
5.2. ARCHITECTURAL DESIGN
5.2.1. Design excellence ranks equally with economy of construction and functional efficiency in
importance. Recognize that good design does not imply added expense.
5.2.2. Front entrance canopies provide an important architectural element of a store's main facade.
The canopy can provide architectural accent to entrance and exit locations and protection from the
weather. While DeCA recognizes the importance of canopies to overall design, use them sparingly
and primarily to cover entry and exit locations and to enhance the architectural expression of the
function within. Avoid excessive lengths and depths. The architectural solution should define a clean
front entry/exit area compatible with other installation architecture and nearby community facilities.
5.2.3. The design solution should emphasize compatibility with installation architectural guidelines
without unnecessary embellishment. The primary focus for premium building materials, such as brick
masonry, should be on the front elevation and others that are prominent to the customer. DeCA
encourages the use of CMU block and precast panels. Stucco, EIF systems or other similar materials
may be appropriate for less prominent elevations and locations not subject to damages from carts and
daily operations. Balance maintainability and durability of exterior building materials with cost regional
climatic considerations.
5.2.4. Include the DeCA exterior signage per Section 101400 Signage and Appendix D Uniform
Dcor Package Building Sign.
5.3. INTERIOR DESIGN
5.3.1. The interior design should complement the exterior design philosophy in terms of economy and
restraint without sacrificing creativity and a pleasing store environment. Provide the commissary
customer with the same standard of quality found in modern commercial food retail operations. The
focus should be the product using the interior environment design to strengthen that focus, or act as a
June 2011 2
DeCA DESIGN CRITERIA HANDBOOK
backdrop to the product. Customers look for value to their dollar and the interior design should
strengthen that image. To the extent practicable, achieve the objectives without embellishment, the
perception of extravagance or added expense.
5.3.2. Give professional attention to the selection of colors and finishes. Use accent colors and
colored wall fabrics and materials to add interest and/or satisfy specialized requirements such as
acoustical control, etc.
5.3.3. Include the DeCA Uniform Dcor Package within customer areas per Section101500 Interior
Dcor Specialties and Appendix D Uniform Dcor Package. Adapt the Uniform Dcor Package
components to fit the scale, layout, and ceiling height of the specific existing Store condition for Add/
Alter Contracts.
5.3.4. Provide a comprehensive interior design that reflects contemporary design technologies for a
commercial retail shopping environment. Specifically, design and integrate the colors, materials and
finishes, graphics, signage and lighting considering the following:
a. Methods of merchandising the product and define the sales area envelope.
b. Scale and proportion of space.
c. Integration of lighting systems including, utilization of accent, task and ambient lighting. Use
lighting to establish comfortable light levels in the sales area; to highlight specialty areas and
product display cases; to supplement materials used for surface enrichment; as a decorative
or functional design element over checkout counters; and to illuminate signage. Refer to
Section 265100 for required lighting fixtures and illumination level requirements.
d. Development of a customer information system.
e. Maintenance of surface finishes.
f. Color and finishes of equipment.
g. Consumer behavior/shopping patterns.
h. Store environmental systems.
i. Community influences/characteristics.
j. Ease of cleaning.
k. Use construction materials to enhance architectural design and details and to enrich building
surfaces, graphics, and the color scheme.
l. Use graphics as a system of visual arts using color, line, pattern, and texture for the purpose
of decoration and communication in the shopping environment.
m. Use customer information systems as a method of organizing and communicating displays
and products in the shopping environment. Customer information will include, but not be
limited to, the following (Refer to section 101500 for specific details on design requirements):
1. Product information.
2. Department identification.
3. Aisle markers.
5.4. SITE DESIGN
5.4.1. Provide for all necessary site work. Include in site plans grading, drainage, roads, parking,
service area, walks, utilities, area lighting, screened/bermed service areas, lawn, planting, and
required underground sprinkler and drip irrigation system. Site building to avoid excessive grading
and balance site work. Consider berms only when excess cut is present. Carefully evaluate site
drainage, runoff and irrigation requirements with sustainability and LEED certification planning goals.
Refer to section 5.11 below.
June 2011 3
DeCA DESIGN CRITERIA HANDBOOK
5.4.2. Design access drives and internal site roads to provide convenient and safe access and
circulation (including collections, deliveries, and fire protection) within the areas and to discourage
through traffic.
5.4.3. Relate pedestrian circulation to parking and facilities. Design the site to facilitate safe and
efficient pedestrian movement to and from the parking lot and commissary. Do not site large utility
elements such as transformers and cooling towers in areas where they become prominent and conflict
with design features.
5.4.4. Refer to Section 320000 for paving and surfacing accessibility requirements.
5.4.5. Study roadways, exits, and parking areas to determine the most efficient traffic flow for
customers, employees, and trucks. Separate delivery traffic from customer traffic on the site.
5.5. OTHER DESIGN CONSIDERATIONS
5.5.1. Carefully evaluate air-conditioning design considerations for the building, such as siting,
orientation, the relative values of insulation, reflective glass coatings, in order to reduce the heat load
and the resulting total capacity of the air-conditioning plant and its subsequent operating cost. Make
studies to establish an optimum balance between costs of these design details in the building structure
and savings in the first cost of the mechanical installation and its operating cost during the planned life
of the building.
5.5.2. Generally, display cases, refrigeration systems, material-handling equipment (MHE),
staging/receiving and storage room racks, and modular furniture will be contractor-furnished,
contractor-installed. Specify refrigerated display cases as a single system with associated compressor
systems, condensers, power wiring, piping and controls.
5.5.3. Should the designer locate roof drain downspouts in the sales area, enclose them within walls or
furring to render them not visible. When located in the staging/receiving area or adjacent to the
receiving aisle, design them to not impede full use of racks or locate them where material-handling
equipment cannot damage them.
5.5.4. Consider the use of insulated daylighting panels, passive dome skylights, and similar products
in commissary designs. Where appropriate, consider passive solar design. Consider clerestory
windows for use in appropriate areas. With appropriate justification, also consider skylights in
staging/receiving area. Analyze skylights with respect to the following criteria: additional construction
costs, roof system detailing, structural deck reinforcements, anticipated electricity consumption
savings for lighting, anticipated additional heating and air-conditioning requirements, costs associated
with additional controls such as photocells and anticipated maintenance costs (if any). Address side
benefits such as safety during electrical power outages and aesthetics. Describe passive solar design
features that present a more expensive construction technique in the design analysis with appropriate
costs, comparisons, and alternatives. All such systems and alternatives contemplated shall align with
established sustainability requirements and LEED certification planning goals identified for each
Commissary during the Charrette or Investigative phases.
5.5.5. Determine the regional soil treatment requirements for termite protection if required, and specify
chemical treatment. Specify full compliance with all local, state and Federal regulations on toxic
chemicals and handling, removal and disposal of hazardous materials. Work closely with the
installation environmental authorities to ensure all requirements and methods are identified and
specified for design and bidding purposes.
5.5.6. Standards of workmanship and selection of materials must achieve the maximum degree of pest
exclusion. Place particular emphasis around doors, refrigeration, electrical, heating and air-
conditioning duct or conduits particularly where openings are created in outside walls and utility rooms.
Require doors fit to tolerances less than 1/4" and that exterior doors be fitted with durable weather
stripping appropriate to the location and relevant pest considerations. Require sealing utility ducts,
piping, and other wall penetrations with caps, metal flashing, masonry grout, escutcheon or other
suitable material to exclude rodents. Design of systems should result in minimum interior pest
harborage.
June 2011 4
DeCA DESIGN CRITERIA HANDBOOK
June 2011 5
DeCA DESIGN CRITERIA HANDBOOK
recommended modifications to the affected existing installation roadways, but do not conduct an
installation roads study.
5.8.3. Field Reconnaissance and Surveying: Make a complete survey of the project site recording
existing topography, terrain features, location of all utilities above and below ground including sizes
and elevations; width of adjacent streets, pavements, sidewalks, curbs and ditches; locations of
existing trees, hedges, and other obstructions such as catch basins, manholes, utility poles and fire
hydrants. Coordinate with the installation engineer and utility shops to locate and identify all
underground utilities in the project site area. Present data as a comprehensive site topographic
survey and include in the contract documents.
5.8.4. Engineering Information and Design Data:
a. Obtain geotechnical engineering services from a qualified geotechnical engineer. The
geotechnical engineer should determine the extent and type of investigative studies required.
Authorize those investigations that the geotechnical engineer recommends and assume
responsibility for areas overlooked by the geotechnical engineer. Provide the geotechnical
engineer all information he may require to recommend services, investigate soils conditions,
and recommend soils related influences on the project design and specifications.
b. The geotechnical engineer shall prepare a soils investigation report in a form suitable for
inclusion in the bid documents for each general contract bidder.
c. The soils investigation report shall include the geotechnical engineer's recommendations for
building foundations, paving design, corrosive soil conditions, and other soil related
construction problems that the geotechnical engineer has identified and recommended for
investigation.
d. The soils investigation report shall include the geotechnical engineer's recommended clearing
and earthwork specifications for both materials and workmanship for site work, structure, and
below grade utilities suitable for incorporation into the project specifications by reference.
e. The geotechnical engineer shall prepare an addendum to the soils investigation report
following completion of structural and civil engineering. This addendum shall reflect the
completed engineering and any modifications developed with the structural or civil engineers
during their work. The addendum shall eliminate options contained in the initial report that are
no longer available in the context of the completed engineering, so that construction bidders
have no confusion on options no longer appropriate.
f. The soils investigation report shall include detailed recommendations for follow-up and
confirmation of soils engineering recommendations to include all tests, observations, and
services to be performed during construction and presented in a form suitable for inclusion in
the construction contract. In the project specifications, require the contractor to provide these
services with his own qualified geotechnical engineer.
g. Ensure the data results in a complete and comprehensive geotechnical report for inclusion in
the contract documents. Prepare other specifications as needed for architectural earthwork
not reasonably part of the geotechnical engineer's study.
5.9. REFERENCE STANDARDS
5.9.1. DeCA will provide guidance for program development, design, and construction of a
commissary facility which will include but not be limited to the following:
a. DeCA Definitive Floor Plan.
b. DeCA Design Criteria.
c. DeCA Guide Specifications.
d. DeCA Design Standard Plates.
e. Applicable DoD standards.
June 2011 6
DeCA DESIGN CRITERIA HANDBOOK
June 2011 7
DeCA DESIGN CRITERIA HANDBOOK
5.10.2. Additional guidance about the EPA Environmentally Preferable Purchasing Program is
available in the Publication Greening the Government, which can be downloaded at the office of
Federal Environmental Executive web site www.ofee.gov, or by telephone at (202) 260-1297. Other
guidance and direction is available at the EPAs Environmentally Preferable Purchasing Program web
site at www.epa.gov/opptintr/epp or by calling the EPAs Pollution Prevention Information
Clearinghouse (PPIC) at (202) 260-1023 or FAX at (202) 260-4659.
June 2011 8
DeCA DESIGN CRITERIA HANDBOOK
pre-requisites and minimum program requirements (MPRs). At the end of the project the design team
shall submit to DeCA a report showing compliance with the targeted LEED credits.
5.12. ENVIRONMENTAL DESIGN CONSIDERATIONS
5.12.1. Environmental Considerations. Give special attention to the environmental factors in the
design and construction of DOD facilities to eliminate or minimize degradation of the environment IAW
Public Law 91-190, National Environment Policy Act; PL 92-500, Federal Water Pollution Control Act;
PL 94-580, Resource Conservation and Recovery Act; PL 95-95, Clean Air Act 1977; PL 93-523, Safe
Drinking Water Act; Executive Order 11514; and to meet the Federal, State, and local environmental
quality standards, particularly with regard to air and water pollution. For projects having pollution
abatement features, obtain necessary Environmental Protection Agency (EPA) and other State agency
coordination and concurrence, and permits for construction.
5.12.2. Air and Water.
5.12.2.1. Water Pollution Abatement Facilities - Design of waste water treatment facilities shall
ensure compliance with the Environmental Protection Agency's National Pollution Discharge
Elimination System (NPDES) permits. Industrial waste treatment facilities to be connected to the
sanitary systems shall meet current EPA pretreatment standards and comply with requirements of
DOD regulations. Address secondary containment and other requirements for fuel storage tanks.
5.12.2.2. Water Quality Permits - The installation will obtain a Permit to Construct, when required
by State or local authority. Evaluate water treatment projects to determine permit requirements.
5.12.2.3. Assemblage of Permit Data - Assemble the necessary data to enable the construction
contractor, working in coordination with the installation, to apply for a Clean Water Act Authority to
Construct Permit. Include instructions and drafts of the proposed project's necessary permit
applicable documents. Meet with the applicable permitting authority (State and/or local) to
determine the specific requirements for the project. Advise the installation and DeCA of all
meetings to allow both to establish their need to attend. The Clean Air lists specific procedures.
5.12.2.4. Clean Air Act Amendments of 1977 - The 1977 amended Clean Air Act (CAA) requires
DOD facilities to comply with State procedural requirements concerning permits for military
construction projects. Evaluate the project to determine whether or not permits are required
pursuant to the Clean Air Act Amendments of 1977. If required, provide instructions to the
Contractor on how to coordinate with the installation to obtain permits, where required, to
construct facilities that emit pollutants.
a. Assembly of Permit Data: Assemble the necessary permitting application data to enable
the Contractor to submit draft documents to the installation to apply for a CAA Authority to
Construct Permit. This includes the review of the proposed project against the governing
air quality regulation and preparation of the necessary permit application documents. To
accomplish this, meet with applicable permitting authority (EPA, State, and/or local) to
determine the specific requirements for this project. Advise the installation and DeCA of
all meetings to allow both to establish their need to attend. The construction contractor
will submit a rough draft of the permit data to the installation for review and coordination.
After approval, prepare the final package, including any draft letters of transmittal and a
summary of the permit costs. If a permit is not required, so indicate.
b. Filing of the Application - The installation will file the application with the permitting
authorities.
c. Specific Procedures:
1. Ensure the contract specifications identify that the installation will sign and transmit all
correspondence to permitting agencies.
2. Provide the following information and data with the Early Preliminary Design submittal
at the 30% design stage where the final design only is authorized, or as early in the
design as possible.
June 2011 9
DeCA DESIGN CRITERIA HANDBOOK
June 2011 10
DeCA DESIGN CRITERIA HANDBOOK
removal is a remedy, in many cases management alternatives (such as encapsulation) within the
building are acceptable and cost-effective methods of managing asbestos in-place. The key to
dealing with asbestos is knowledge of its location and condition and having a management plan to
prevent asbestos-containing materials that continue to serve their intended purpose from
becoming a health hazard. There is no alternative to such management, because DeCA does not
have the resources to remove and dispose of all asbestos in all the facilities under its
management. Most asbestos is not now nor will it become a health hazard if it is properly
managed. Statutory or regulatory requirements that result in removal or management of asbestos
are based on human exposure or the potential for human exposure (i.e., National Emission
Standards for Hazardous Air Pollutants (NESHAP) = no visible emissions, OSHA = number of
airborne fibers per cc). Professional judgment based on exposure levels or potential exposure
levels must be the primary determinant of what should be done with asbestos. Asbestos
containing materials must be analyzed to determine the most prudent course in terms of removal
or management in-place and cost that will be incurred as a result:
5.12.5.2. It is DeCA policy that whenever Commissary facilities or other facilities are demolished
as part of construction, or components of a facility are removed during construction, an inspection
and survey must be performed to determine the amount of asbestos containing materials, lead-
based paints, and PCB containing electrical components that may be present.
5.12.5.3. The following specific policies apply to asbestos containing materials:
a. Asbestos will be removed if the protection of human health, as determined by a qualified
professional, requires removal (e.g., exposed friable asbestos within a building) in
accordance with applicable health laws, regulations, and standards.
b. When asbestos is present but no immediate action is planned, a plan for managing the
asbestos in-place using commonly accepted standards, criteria, and procedures to assure
sufficient protection of human health and the environment, in accordance with applicable
and developing health standards, will be developed.
c. A thorough survey for asbestos (including review of facility records, visual inspection, and
where appropriate as determined by the Bio-environmental Engineer and the installation
engineer, (intrusive inspection) will be conducted prior to any major construction on
commissary facilities.
d. Encapsulated asbestos in a building structure, friable or not, is not regarded as hazardous
waste, nor does encapsulation within the structure of a building constitute "storing" or
"disposing of" hazardous waste. However, it is not DeCA's policy to use encapsulation as
a form of abatement, unless specifically approved in advance.
e. Friable asbestos, or asbestos that will probably become friable, will be properly disposed
of in a landfill or other disposal facility property permitted for friable asbestos disposal.
f. The final determination regarding the disposition of asbestos will be dependent on the
plan for disposal and any planned continued use of the building.
5.12.6. A-E Services for Hazardous Materials Survey/Inspection and Abatement Design:
5.12.6.1. If required by AE SOW, provide an environmental investigation and abatement design for
hazardous materials impacted by the proposed construction to include but not be limited to
Asbestos Containing Materials, lead based paints, and existing fluorescent light fixtures for PCB in
ballasts. Provide a written detailed report of findings along with recommended design for
abatement.
5.12.6.2. Part A - Investigative: Provide environmental survey services to determine the existence
of hazardous materials within the limits of the proposed construction project. This survey shall
include field reconnaissance by a licensed and accredited inspector qualified to inspect the facility
and site for asbestos materials, lead contaminated paint, and PCB contaminated light ballasts. It
will begin by the contractor reviewing available documents, including as-built construction
documents, prior surveys by the installation, lab results, prior management actions, and briefing
June 2011 11
DeCA DESIGN CRITERIA HANDBOOK
key personnel before commencing work. It will also include records of communications with state
and local regulatory agencies to clarify the nature and scope of required coordination, approval,
permitting, and licensing actions required for work to be performed. AE assumes all responsibility
for payment of any fees to state and local agencies associated with the investigation/survey and/or
design of abatement actions. Conduct survey in a manner to avoid any conflict with on-going
store operations and coordinate in advance with the contracting officer. Sample and test any
materials found to be suspect of containing asbestos and lead to determine levels of
contamination. Test a minimum of three samples of each homogeneous material suspected of
containing asbestos. Bulk samples will be analyzed by an independent, licensed and accredited
testing laboratory which participates in the National Voluntary Laboratory Accreditation Program
(NVLAP) administered by the National Institute of Standards and Technology (NIST). Once a
sample tests positive for hazardous components in a specific homogeneous area, further testing
of other samples of the same material from that homogeneous area is not required. Identify
locations of samples to depict the specific location at the building or site. Base any determination
of potential PCB containing light ballasts on name plate data and serial numbers cross-referenced
against manufacturer's information.
5.12.6.3. Part B - Analysis and Reporting: After all field inspection, sampling, and testing have
been completed, prepare a comprehensive report indicating the results of inspection and
laboratory tests. Include in the written report of findings a table of asbestos containing materials
(materials containing more than 1% asbestos), if present, sample analysis results and a floor plan
and photographs to show sample locations. At the discretion of the Government, retest lab results
indicating the presence of asbestos material in levels of 5% or less using more accurate point
counting methods. Upon completion and acceptance of the inspector's report, address appropriate
design actions including an analysis of the potential risk of hazardous material that may be
encountered during the renovation phase of the project and a recommended method of abatement
of these materials. Have an experienced Licensed Asbestos Consultant prepare the report.
Finally, include in the report recommended procedures and required actions and a detailed cost
estimate for required abatement actions.
5.12.6.4. Part C - Abatement Design: Prepare an abatement design for all materials identified for
removal or disposal in the survey report described above. Have a person licensed and accredited
to perform such work in the state where the work is to be performed prepare the design.
Coordinate the results of this abatement design into the demolition work associated with
construction or renovations to the commissary. Consider phasing of the abatement work an
integral part of the phasing of construction so to not disrupt commissary operations. Include in the
abatement plan drawings, details, and specifications defining and delineating the physical quantity
of the work. Additionally, describe in the contract specifications the technical and qualitative
aspects of the work to meet and/or exceed minimum regulatory requirements. Include in the
design documents a requirement that the abatement contractor's submittal show proof of
insurance, licenses, training, medical certificates, and worker protection measures necessary to
comply with federal, state, and local laws and regulations. Require the abatement contractor to
identify a competent person responsible for overseeing all work. Require that a licensed and
accredited air monitoring technician provide independent air monitoring as part of the asbestos
abatement procedures. Clearly state in the design documents will that the contractor assumes all
responsibility for regulatory permits, fees and fines levied as a result of his work. Final completion
of all work shall be contingent upon government acceptance of the procedures for abatement and
documentation of approved disposal of all hazardous waste materials. Require that a final
government walk-through be scheduled at the completion of all abatement work to assure work
has been performed according to plans and applicable federal, state and local laws and
regulations. Require the contractor provide statements certifying this before undertaking to apply
lock-down or other materials that cover or encapsulate any remaining residue (see Attachment 5).
Upon completion and acceptance of all work, require the contractor provide the government's
representative with a complete record of all abatement actions as a permanent record file to be
maintained by the installation.
5.12.6.5. Include in the design specifications for all new work, provisions requiring the construction
June 2011 12
DeCA DESIGN CRITERIA HANDBOOK
contractor to verify that the new construction does not contain asbestos materials or lead-based
paints. See sample certification form.
5.12.7. Minimum Requirements for Design of Asbestos Abatement Projects for Commissary Facilities:
See the attached provisions which outline the minimum requirements for protection of public health
and safety required for acceptable design of asbestos abatement work associated with commissary
construction projects. This outline does not constitute complete and sufficient specifications for an
asbestos abatement project and is intended only as an aid to design. The more detailed requirements
stipulated in the plan and specifications for a particular abatement project shall take precedence over
these limited provisions.
ARCHITECT-ENGINEER
STATEMENT OF WORK
ADD/ALTER COMMISSARY
INSTALLATION NAME
ENVIRONMENTAL PERMITTING
1. Environmental Considerations: Pay special attention to the environmental factors in the design and
construction of DoD facilities to eliminate or minimize degradation of the environment in accordance with
Public Law and to meet all federal, state and local environmental quality standards, particularly with
regard to air and water pollution.
2. A-E Requirements.
2.1. Determine what environmental permits are required, if any. If applicable, also provide to the
installation the name, address and a point of contact for each of the various agencies required. For
the permitting authorities to accomplish this, meet with the applicable permitting authorities (EPA,
state and/or local) to determine the specific requirements for this project.
2.2. Identify necessary data for the installation to file with the permitting authorities. This will include
the review of the proposed project against the governing regulation and preparation of the necessary
permit application documents. To accomplish this, you may have to meet with the applicable
permitting authority (EPA, State and/or Local) to determine the specific requirements for this project.
Advise the installation of all scheduled meetings to allow it to establish its need to attend. Submit a
rough draft of the permit data to the installation for review and coordination. After approval, prepare
a list of required actions, identifying appropriate authorities, and providing projected submittal and
approval events and estimated lead times. Also prepare a summary of the projected permit costs,
including procedural costs as well as additional construction costs. If a permit is not required, so
indicate.
June 2011 13
DeCA DESIGN CRITERIA HANDBOOK
PERMIT TYPE PERMIT PERMIT LOCAL JURISDICTION SUBMITTAL IF YES, TIME PERMIT
REQUIRED Y/N FOR CONTACTED AND REQUIREMENTS REQUIRED FOR FEE
AND NUMBER DATE PERMIT
AIR QUALITY
WATER QUALITY
SOLID WASTE
HAZARDOUS WASTE
1/
STORM WATER
EROSION CONTROL
PLAN
COASTAL ZONE
MANAGEMENT
FLOOD PLAIN/
DREDGE AND FILL
OTHER 2/
1/ Include underground tank permits for fuels and other hazardous materials.
2/ Includes any permitting requirements not specifically categorized in the matrix, such as FAA coordination, etc.
June 2011 14
DeCA DESIGN CRITERIA HANDBOOK
As authorized representative of the contractor, I hereby certify and attest that I have completed abatement
work on project _____________________________________________
Description
At _________________________________, Contract Number __________________________
Location Number
In accordance with the contract provisions, federal, state and local regulations and have disposed of all waste
and debris associated with this work at a landfill or disposal site authorized and licensed to accept such wastes.
Copies of project logs and documents, landfill receipts and waste manifests are attached. At completion of all
work, the work area was visually inspected and found to be free and clear of all visual signs of asbestos
materials and that clearance air quality monitoring and sample analysis under aggressive air disturbance
conditions was found to be within permissible levels for space re-occupancy.
The contractor's representative further accepts and acknowledges that the contractor assumes all
responsibilities for latent defects attributable to his failure to follow prescribed procedures or failure to properly
abate the required conditions as described in the contract.
by: ______________________________________________________________________
Signature, Contractor or Authorized Representative Date
_______________________________________________________________________
Printed Name
_______________________________________________________________________
Printed Title and Firm
The Government's Inspector hereby certifies that he has accompanied the Contractor's Representative on
his visual inspection and reviewed the results of his final clearance air quality monitoring and verifies that, to the
best of his knowledge and belief, the above representations by the Contractor's Representative are true and
correct.
By: ______________________________________________________________________
Signature Date
_______________________________________________________________________
Printed Name
_______________________________________________________________________
Printed Title and Firm
June 2011 15
DeCA DESIGN CRITERIA HANDBOOK
ENVIRONMENTAL CERTIFICATION
ACCOMPANYING COMPLETION OF NEW CONSTRUCTION
As authorized representative of the Contractor, I hereby certify and attest, to the best of my knowledge that
the construction completed under the contract (Government Contract No.____________________ is free and
clear of building materials and products containing regulated quantities of asbestos and/or lead-based paints. I
have determined the above based on product labels, manufacturer's information, submittal documents for
specified materials, and other information available to me. The Contractor's representative further
acknowledges and accepts that if it is later found that the Contractor has intentionally defrauded or
misrepresented these facts, and then the Contractor assumes total and complete liability for fines, penalties
and/or abatement and removal of these materials at the direction of the Government.
by: ______________________________________________________________________
Signature, Contractor or Authorized Representative Date
_______________________________________________________________________
Printed Name
_______________________________________________________________________
Printed Title and Firm
The Government's Inspector hereby certifies and attests that, to the best of knowledge and belief, the above
representations by the Contractor's representative are true and correct.
by: ______________________________________________________________________
Signature Date
_______________________________________________________________________
Printed Name
_______________________________________________________________________
Printed Title and Firm
June 2011 16
DeCA DESIGN CRITERIA HANDBOOK
SAMPLE OUTLINE COVERING MINIMUM REQUIREMENTS FOR INVESTIGATIVE SURVEY AND DESIGN
OF ASBESTOS ABATEMENT PROJECTS FOR COMMISSARY FACILITIES
SAMPLE OUTLINE
June 2011 18
DeCA DESIGN CRITERIA HANDBOOK
Construction Free and Clear of Asbestos for Materials or Lead-Based Paints: The contractor
shall be prohibited from use of any asbestos construction materials or lead-based paints in
completing this project as determined by the manufacturer's labels or submittal literature. At
the conclusion of this project, the contractor shall provide the Government with written
certification that this is true and correct.
END OF SECTION
June 2011 20
DeCA DESIGN CRITERIA HANDBOOK
Note: Use the checklist as a general review for the design of addition/alteration projects to assure the design
gives adequate care and concern to phasing issues.
1. ____ Will the contractor be responsible for providing a detailed project phasing schedule that he is required
to follow during construction (e.g., CPM with two step phasing - overall phasing at the outset plus specific
phasing schedules due at the start of each progress period)?
2. ____ Are important milestones specifically identified for the contractor to include in his project phasing
schedule? Is the contractor provided guidance on a minimal number of significant construction milestones to
include on his phasing schedule or is a specific list of milestones provided?
3 ____ Is the contractor responsible for providing a safety plan specifically addressing contractor safety
measures to insure the safety and protection of his work force as well as for commissary customers and
employees from construction activity?
4. ____ Have the contractor's work and storage areas been specifically identified and confined only to areas
required for efficient and effective construction?
5. ____ Are there stringent provisions for daily clean up of all work and storage areas, inclusive of weed and
grass control within the construction limits?
6. ____ Are construction work and materials storage areas sufficiently barricaded, screened or partitioned off at
all times to preclude mingling of patron and construction activities?
7. ____ Are there definite provisions to allow for continuation of vehicular traffic throughout the area of
construction in a safe and efficient manner?
7.1. ____ Are there adequate barriers and markings for smooth vehicular flow?
7.2. ____ Is there space for vehicular turn around between parking and contractor's work area?
7.3. ____ Is proper traffic control signage for safe movement of vehicles being maintained at all times?
7.4. ____ Are there provisions to maintain handicapped and VIP reserved parking spaces during
construction?
8. ____ Can service and product deliveries be maintained throughout the period of construction?
9. ____ Do the temporary entrance-ways offer safe and efficient patron movement, including:
10.1. ____ Handicapped access
10.2. ____ Protection from the weather?
10.3. ____ Cart storage?
10.4. ____ Obstruction-free corridors?
10. ____ Are there adequate provisions to insure safe movement of pedestrians and shopping carts from
available parking areas into and out of the store throughout the period of construction?
10.1. ____ Are barriers and protected corridors provided to isolate patrons from construction activities?
10.2. ____ If utility trenches and pavement cuts are required in pedestrian and vehicular areas, do the
design documents require immediate resurfacing to prevent any hazard to pedestrians and motorists?
11. ____ Will there be adequate fire egress from the store throughout construction?
12. ____ Will there be adequate provisions to insure store security throughout the period of construction,
including temporary barriers?
13. ____ Do temporary partitions and enclosures provide sufficient protection against weather and dust to
prevent damage to store interiors and product, and is the contractor made responsible for any damages that
June 2011 21
DeCA DESIGN CRITERIA HANDBOOK
may occur?
14. ____ Are alarms and switches being relocated, as necessary, to temporary walls?
15. ____ Is the contractor required to maintain Heating Ventilating and Air conditioning (HVAC) in the sales and
administrative areas throughout construction?
16. ____ Is the time sequence for contractor installation of government-furnished equipment specifically
identified and phased to coordinate with government acquisition schedules?
17. ____ Will manufacturer's representatives be available for the initial start up, calibration and testing of
contractor-furnished equipment?
18. ____ Are there provisions to ensure a safe can be located, installed and secured in the cashier's office?
19. ____ Is the sequencing of equipment replacement, sales area remodeling, and processing area remodeling
consistent with efficient store operations?
19.1. ____ Can perishable processing and storage activities be maintained throughout the period of
construction?
19.2. ____ What provisions will insure the minimum amount of time required to change-out or relocate
refrigerated display equipment? Is this work being accomplished without disruption of service to other
refrigerated equipment areas?
20. ____ Are refrigerated storage areas being constructed or modified with minimal impact on other refrigerated
storage areas?
21. ____ If down time is required in refrigerated storage and display areas to accomplish work, is the store to be
provided adequate notice (10 days minimum) to adjust product deliveries?
22. ____ What provisions have been identified for partial inspection, acceptance, and warranty of completed
work?
22.1. ____ How much time is the contractor allotted to correct punch list items?
22.2. ____ Are there provisions to control future payments until punch list items are corrected?
22.3. ____ Do the contract documents clearly indicate when warranty periods begin?
22.4. ____ What is the procedure specified for turnover of equipment operating manuals, warranties,
and servicing information?
22.5. ____ What procedures have been identified for base real property acceptance (DD 1354
preparation) of completed work?
23. ____ Are utility modifications and site work phased in such a manner to insure minimal disruption to present
service?
24. ____ Does the design and construction process ensure total coordination on all pertinent aspects of
phasing with:
24.1. ____ The installation engineer?
24.2. ____ The installation fire department?
24.3. ____ The installation security (military) police?
24.4. ____ The store manager?
24.5. ____ The DeCA Region?
24.6. ____ DeCA/FOA-END and Equipment office?
25. ____ Is the disposition of removed equipment specifically addressed and consistent with GFE acquisition
plans? Does this equipment become the property of the contractor? The following is a partial list of some of the
more frequent equipment items that need to be addressed:
June 2011 22
DeCA DESIGN CRITERIA HANDBOOK
June 2011 23
DeCA DESIGN CRITERIA HANDBOOK
assurance plan.
41. ____ Ensure that all phasing elements, to include temporary moves, are included in the network analysis
system.
June 2011 24
DeCA DESIGN CRITERIA HANDBOOK
GENERAL DESIGN REQUIREMENTS
A. Commissary facilities are Department of Defense (DoD) projects, and as such must be
constructed in accordance with the following criteria, codes, and standards.
B. Project design shall conform to Department of Defense (DoD) criteria and other applicable DoD
regulations, manuals, and pamphlets; (latest edition shall be used) including but not limited to the
following:
2. Unified Facilities Criteria Design: Fire Protection Engineering for Facilities (UFC 3-600-01).
3. Unified Facilities Criteria DoD Minimum Anti-Terrorism Standards for Buildings (UFC 4-010-
01).
4. Project location "Installation Design Guide" (IDG), "Base Exterior Architectural Plan" (BEAP),
"Architectural Compatibility Guidelines" (ACG), or other general design guide at the project
location.
C. Project design shall conform to national codes and regulations for building construction and
safety, including but not limited to the following:
7. OSHA Regulations.
8. ASHRAE Standards.
10. ABA Accessibility Standard for Department of Defense Facilities as adopted by the Deputy
Secretary of Defense memorandum dated October 31, 2008.
A. Sales Area layout shall be in accordance with the latest DeCA approved definitive floor plan.
Deviations from the approved definitive floor plan shall be identified during the design charrette
process and documented in the Final Project Definition Package that is developed for a particular
project.
Maintain these minimum aisle widths unless approved otherwise by DeCA during the design
charrette process.
Note that unobstructed exit aisle widths, equivalent to exit width provided at front of Sales Area, shall
be provided as required by NFPA 101 Life Safety Code. Space between checkout counters may not
be used to satisfy this requirement, unless a dedicated exit path through checkout counters is
provided.
C. Sales Floor interior volume shall be maintained at a minimum of 18'-0" clear AFF to bottom of all
obstructions including ductwork, lights, refrigeration lines, etc. exclusive of dcor elements and
specialty lighting.
D. A natural color polished concrete floor is to be used in all customer areas of new facilities.
Requirements for this system are identified in Section 03 35 43 Polished Concrete Finishing.
E. Resilient floor tile is typically used in customer areas of addition / alteration projects, as this
product can better conceal patched or otherwise damaged existing concrete floor slabs. Basis-
of-Design for single color vinyl composition floor tile to be used throughout shall be as indicated
in the DeCA Uniform Dcor 2010, "Adaptive Uniform Dcor Package". Documents shall indicate
that floor tile shall be installed with grain running in one direction, with joints in straight line.
F. Interior dcor shall comply with requirements of the DeCA Uniform Dcor 2010, "Adaptive
Uniform Dcor Package". Refer to Section 10 15 00 Interior Dcor Specialties Design Criteria for
further guidance. Typically, new stores should have an exposed structure ceiling and incorporate
an 18'-0" high standard dcor package. Addition / Alteration projects typically have acoustical
panel ceiling system with either a 12'-0" and 14'-0" high standard dcor package requiring an
adaptation of the Uniform Dcor Package criteria components to fit the scale of the specific Store
environment.
G. Gypsum wallboard soffits (i.e., fur-downs) are typically provided at 8'-0" AFF around the
perimeter of the Sales Area to accommodate interior dcor elements and conceal HVAC return
air ductwork, refrigeration piping, etc. A soffit height of 10'-0" AFF is typically provided at the front
of the checkout area to accommodate automatic entrance door packages with glass transoms
above. The face of these, roof structure suspended, soffits should be offset from (i.e., extend in
front of) the face of, floor-supported, walls below with control joints allowing for movement. This
also provides a uniform horizontal banding around the sales area for the interior dcor elements.
H. Provide gypsum wallboard partitions (i.e., wingwalls) at the ends of all display case line-ups along
perimeter walls, and between cases with different profiles (i.e., widths, depths, heights, etc.). This
is necessary to properly close-off spaces above and at sides of display cases as identified in
Design Standard Plates 07 92 00-01 and 07 92 00-02, so that HVAC return air is drawn from the
June 2011
2
DeCA DESIGN CRITERIA HANDBOOK
GENERAL DESIGN REQUIREMENTS
floor. Additionally, if these spaces are left open to the sales area they must have a fire sprinkler
system with coverage densities matching that used in the sales area.
I. Overhead HVAC return air and refrigeration piping vertical drops at island refrigerated display
cases shall also be concealed within roof structure supported gypsum wallboard enclosures.
These enclosures should have dcor elements matching that used throughout the sales area.
J. In new stores with high bay exposed structure in customer areas, the preferred method of
illumination is continuous rows of fluorescent light fixtures, mounted at dcor height and running
perpendicular to shopping aisles (refer to Division 26 for required foot-candle levels). Consider
fluorescent light fixtures above checkout counters, mounted at a lower height, to provide even
illumination with less glare for cashier functions. Refer to Section 10 15 00 Interior Dcor
Specialties Design Criteria for additional guidance regarding painting of exposed utilities in
customer areas.
K. On addition / alteration projects, acoustical panel ceiling systems are typically used in lieu of
exposed structure. This is usually necessary to conceal existing ductwork, piping, conduits, etc
that were previously installed. Run recessed continuous strip fluorescent lighting rows
perpendicular to shopping aisles.
L. Coordinate placement of dcor banners so that they are not located directly beneath light
fixtures. Arrange dcor banners so that the same color banners are not placed next to each
other.
M. Do not locate light switches in areas accessible to customers. If necessary to do so, provide
lockable switch covers.
N. Do not locate HVAC thermostats or hose bibs in areas accessible to customers. If necessary to
do so, provide lockable covers.
O. All wall surfaces accessible to impact damage from shopping carts shall have wood bumper rails
and protection posts. Corners of island refrigerated display cases shall be protected with display
case corner guards. Automatic entrance door shall be protected with protection posts at door
jambs and protection plates on impact side of sliding doors. Floor mounted storefront systems
shall be protected with cart bumpers. Refer to Section 10 26 00 Design Criteria for additional
information and Design Standard Plate 10 26 00-01 and Door Types Legend in Appendix A .
P. Coordinate mounting height of electrical receptacles on walls with wood bumper rail protection.
Refer to Design Standard Plate 10 26 00-01.
Q. Janitor Closets with doors opening directly into customer areas shall have door closers.
R. Fire extinguishers shall be located throughout the commissary in accordance with NFPA 10.
Extinguishers located in customer and admin areas shall be contained within fully recessed or
semi-recessed cabinets. Extinguishers located in warehouse and other related storage areas
shall be exposed with manufacturer's standard surface mounting bracket. Refer to Section
10 44 00 Fire Protection Specialties Design Criteria for additional guidance.
A. Wall surfaces facing the staging / receiving / MHE areas shall be full height CMU, sealed air tight
to roof structure and at all wall penetrations. This is necessary to minimize infiltration of warm
humid air in the warehouse area from entering the open space above cold storage rooms,
allowing condensation to form on refrigeration piping and cold storage room ceilings. At project
locations with normally high humidity, the interior CMU walls facing the warehouse areas should
be painted with an interior vapor barrier primer/sealer. In low volume small stores, if discussed,
June 2011
3
DeCA DESIGN CRITERIA HANDBOOK
GENERAL DESIGN REQUIREMENTS
approved, and documented during the Final Project Definition Package, these walls may be
constructed of gypsum wallboard with 8'-0" high fiberglass reinforced plastic (FRP) panels and
single wood bumper rail system.
B. Stair towers for roof access, using 3'-0" wide by 7'-0" high insulated standard steel doors, shall be
provided in facilities with roof mounted refrigeration mechanical centers and HVAC systems.
Refer to Division 08 Hollow Metal Doors and Frames for roof access door criteria.
C. Provide HM access doors to allow access from warehouse area to space above cold storage
rooms as required for service access and maintenance. Provide service lighting (minimal
footcandle required) above cold storage rooms controlled by light switch (with pilot light) located
immediately adjacent to the access door, with switch facing the warehouse area. At a minimum,
position access door so that a ladder or movable stair can be positioned directly in front of the
opening, against the wall. If access door can be located with clear floor space below, provide
permanent fixed ladder with access platform at each access door location. Refer to Design
Standard Plates 05 50 13-02, 05 50 13-03, and Guide Specification, Division 05, Section Metal
Fabrications for information on "Above-Cooler-Access Ladder and Platform".
D. Design freezer in accordance with Section 03 30 50 Insulated Freezer Floors Design Criteria,
Section 13 21 26 Cold Storage Rooms Design Criteria, and related Design Standard Plates
03 30 50-01, 03 30 50-02, 03 30 50-03, and 13 21 26-01 through 13 21 26-18. Provide adequate
air space between freezer wall panels and adjacent non-refrigerated wall surfaces, with positive
mechanical ventilation of air space. This is necessary to prevent condensation from occurring
within air space, possibly causing mold growth and damage to adjacent wall surfaces. Provide
heater cable within concrete curbs on exterior sides of freezer walls to prevent condensation and
ice from forming on curbs and adjacent floor surfaces.
E. Provide stainless steel closures to seal air spaces between cold storage room walls and adjacent
partitions. This is necessary for sanitation and rodent control. Refer to Design Standard Plate
13 21 26-05.
F. When locating sliding cold storage room doors, verify that adequate space is available for the
sliding portion of the door. Minimum space requirements are 8" on the latch side of door
opening, actual door width, and door width plus 15" on the sliding side of door opening (8" + 6'-0"
+ 7'-3" = 13'-11" minimum).
G. It is undesirable to locate electrical panels within janitor closets. These rooms are frequently
locked, have maintenance equipment stored within that often block access to panels, and are
also subject to contact with water from mop basin faucet hose, which is a safety concern. When
multiple panels are required in one area, consider providing a separate electrical room. If only a
random single electrical panel is required, locate on wall in non-customer areas (i.e., vestibule
between sales and warehouse, or warehouse area).
H. All restrooms and employee locker rooms shall meet as a minimum, the applicable codes stated
above. Also, the rooms shall follow the specific Specification Criteria within the specification
Divisions 10 21 13 Toilet Compartments, 10 51 13 Metal Lockers, 10 28 13 Toilet Accessories for
specific features and components and the general guidelines as stated below for general design
intent.
1. Provide a 3/2 women to men ratio of toilets in which no more than 50% of men's toilets
can be urinals. Generally, commissaries have more women shopping than men and
often have small children with them.
2. A single user family restroom should be included with the separate gender multi-stall
patron toilet facilities. Family, unisex, or single-user restrooms offer flexibility. Males or
June 2011
4
DeCA DESIGN CRITERIA HANDBOOK
GENERAL DESIGN REQUIREMENTS
females can use them, and one or more individuals, of the same or opposite sex, can use
them.
3. Provide sufficient double tier lockers in both the men's and women's employee locker
rooms as determined in the charrette design process, Provide single tier lockers equal to
no more than 20% of all lockers provided.
I. Solid waste management and recycling requirements shall be coordinated with sustainable
design goals including the requirements to achieve LEED certification. Each Store shall
determine the goals at the Charrette and investigative phases of every project. The goals shall be
coordinated with existing Installation contracted waste services as well as current force protection
standards. Trash and waste handling and storage concerns affect store layout and processes as
well as site planning concerns. The climatic conditions associated with installation regions will
impact design decisions. Generally a waste holding area at the building requires secure fencing
around the containers including tops of areas. Alternatives make use of remote facilities used in
heightened security conditions however access and use of remote facilities is not convenient or
prudent in certain climates.
1. Generally a waste holding area at the building requires secure fencing around the
containers including tops of areas. Alternatives make use of remote facilities used in
heightened security conditions however access and use of remote facilities is not
convenient or prudent in certain climates.
END OF SECTION
June 2011
5
Compliance with Unified Facilities Criteria (UFC 4-010-01) DoD MINIMUM
ANTITERRORISM STANDARDS FOR BUILDINGS is required on all
commissary facilities. The following is a summary of this document as it relates
to commissary facilities, and includes a checklist that the design A/E shall
complete as part of the design process. Any deviations from UFC 4-010-01 shall
be identified during the design charrette process and documented in the Design
Charrette Final Project Definition Package.
The glazing provisions of these standards are mandatory for existing inhabited
buildings within any planned window or door glazing replacement project. Such
replacements may require window frame modification or replacement.
Additions to existing inhabited buildings shall comply with the minimum standards
for new buildings. If the addition is 50% or more of the gross area of the existing
building, the existing building shall comply with the minimum standards for
existing buildings.
Implementation of these standards is mandatory for all facilities leased for DoD
use and for those buildings in which DoD receives a space assignment from
another government agency except as established below. This requirement is
intended to cover all situations, including General Services Administration space,
privatized buildings, and host-nation and other foreign government buildings.
This requirement is applicable for all new leases executed on or after 1 October
2005 and to renewal or extension of any existing lease on or after 1 October
2009. Leases executed prior to the above fiscal years will comply with these
standards where possible.
Partial Occupancy. These standards only apply where DoD personnel occupy
leased or assigned space constituting at least 25% of the net interior useable
area or the area as defined in the lease, and they only apply to that portion of the
building that is occupied by DoD personnel.
New Buildings. Buildings that are built to lease to DoD as of the effective date
established above shall comply with the standards for new construction.
INFORMATION SENSITIVITY
Posting To The Internet. This document may be posted freely to the Internet;
however, because the tables (Tables 1 and 2) in UFC 4-010-02 are For Official
Use Only they cannot be posted to any web site that is accessible to the general
public. In addition, other documents that include information from these
standards that are identified as For Official Use Only cannot be posted to web
sites accessible to the general public. For Official Use Only information may be
posted to protected, non-publicly accessible web sites that comply with standards
established by DoD for administration of web sites.
Plans and Specifications. The explosive weights from UFC 4-010-02 upon which
these standards are based shall not be entered into the plans and specifications
unless the plans and specifications are properly safeguarded. Plans and
specifications may be posted to the Internet in accordance with existing DoD
Component guidance, but such documents will not include For Official Use Only
information. All plans and specifications for inhabited buildings shall include an
annotation that cites the version of these standards that was used for design.
Glazing. The part of a window, skylight, or door assembly that is transparent and
transmits light, but not air.
The application of the standards are based on the premise that the warehouse,
staging, storage, and processing areas do not meet the definition of inhabited
space defined as occupied by 11 or more DoD personnel and with a population
density of greater than one person per 40 gross square meters (430 gross
square feet) and that the sales area (i. e. all spaces forward of the
storage/processing rooms including front offices, cashiers office, baggers break
room, and other administrative spaces at the front of the commissary), and break
room/employees restrooms is primary gathering space since it is routinely
occupied by 50 or more DoD personnel. (The break room/employees restrooms
meet the number and population densities of inhabited space. Thus must be
included in the primary gathering space.)
STANDARDS CHECKLIST
(1) Even with analysis, standoff distances less than those in this column are not allowed for new buildings, but are allowed for
existing buildings if constructed/retrofitted to provide the required level of protection at the reduced standoff distance.
(2) See UFC 4-010-2, for the specific explosive weights (kg/pounds of TNT) associated with designations I, II, III. UFC 4-010-2 is
For Official Use Only (FOUO)
(3) Explosive for building separation is an indirect fire (mortar) round at a standoff distance of half the separation distance.
(4) For existing buildings, see paragraph B-1.1.2.2.
(5) For existing family housing, see paragraph B-1.1.2.2.3.
Figure B-1 Standoff Distances and Building Separation Controlled Perimeter
Trash
Containers
25 m
45 m
45 m = 148 ft
25 m = 82 ft
Controlled Perimeter
10 m = 33 ft
10 m 10 m Uninhabited Note: Standoff
Portion of distances are from
Parking
25 m
Building Conventional
Construction
10 m
Inhabited Standoff Distance
Buildings column of Table B-1
10 m
25 m
10 m
Primary Gathering
Buildings or Billeting
Unobstructed Space Uninhabited
Building
Roadways
Parking
Parking Roadways
45 m = 148 ft
Trash
45 m
25 m = 82 ft
25 m
Containers
10 m = 33 ft
10 m Uninhabited
10 m Portion of
Uninhabited Building
25 m
Building
10 m
Inhabited
45 m Buildings
10 m
10 m
Note: Standoff distances Primary Gathering
are from Conventional Buildings or Billeting
Construction Standoff
Distance column of Unobstructed Space
Table B-1
Table 2-1 Levels of Protection New Buildings
Level of Potential Structural Potential Door and Potential Injury
Protection Damage Glazing
Hazards
Below AT Severely damaged. Doors and windows fail Majority of
standards Frame collapse/massive and result in lethal personnel suffer
destruction. Little left hazards fatalities.
standing.
Very Low Heavily damaged - onset Glazing will break and is Majority of
of structural collapse: likely to be propelled into personnel suffer
Major deformation of the building, resulting in serious injuries.
primary and secondary serious glazing fragment There are likely to
structural members, but injuries, but fragments be a limited
progressive collapse is will be reduced. Doors number (10% to
unlikely. Collapse of non-may be propelled into 25%) of fatalities.
structural elements. rooms, presenting
serious hazards.
Low Damaged unrepairable. Glazing will break, but fall Majority of
Major deformation of non- within 1 meter of the wall personnel suffer
structural elements and or otherwise not present significant injuries.
secondary structural a significant fragment There may be a
few (<10%)
members and minor hazard. Doors may fail,
fatalities.
deformation of primary but they will rebound out
structural members, but of their frames,
progressive collapse is presenting minimal
unlikely. hazards.
Medium Damaged repairable. Glazing will break, but will Some minor
Minor deformations of remain in the window injuries, but
non-structural elements frame. Doors will stay in fatalities are
and secondary structural frames, but will not be unlikely.
members and no reusable.
permanent deformation in
primary structural
members.
High Superficially damaged. Glazing will not break. Only superficial
No permanent Doors will be reusable. injuries are likely.
deformation of primary
and secondary structural
members or non-
structural elements.
Table 2-2 Levels of Protection Existing Buildings
Level of Potential Structural Potential Door and Potential Injury
Protection Damage Glazing
Hazards
Below AT Severely damaged. Doors and windows fail Majority of
standards Frame collapse/massive and result in lethal personnel suffer
destruction. Little left hazards fatalities.
standing.
Very Low Heavily damaged - onset Glazing will break and is Majority of
of structural collapse: likely to be propelled into personnel suffer
Major deformation of the building, resulting in serious injuries.
primary structural serious glazing fragment There are likely to
members, but injuries, but fragments be a limited
progressive collapse is will be reduced. Doors number (10% to
unlikely. Collapse of may be propelled into 25%) of fatalities.
secondary structural rooms, presenting
members and non- serious hazards.
structural elements.
Low Damaged unrepairable. Glazing will break and is Majority of
Major deformation of likely to be propelled into personnel suffer
secondary structural the building, but should significant
members and minor result in survivable injuries. There
deformation of primary glazing fragment injuries. may be a few
structural members, but
Doors may fail, but they (<10%) fatalities.
progressive collapse is
unlikely. Collapse of non-
will rebound out of their
structural elements. frames, presenting
minimal hazards.
Medium Damaged repairable. Glazing will break, but will Some minor
Minor deformations of remain in the window injuries, but
secondary structural frame. Doors will stay in fatalities are
members and no frames, but will not be unlikely.
permanent deformation in reusable.
primary structural
members. Major
deformation of non-
structural elements.
High Superficially damaged. Glazing will not break. Only superficial
No permanent Doors will be reusable. injuries are likely.
deformation of primary
and secondary structural
members or non-
structural elements.
CODE ANALYSIS - TYPICAL DECA COMMISSARY FACILITY
02 FEB 2011
1.3 CONFLICTS IN IF CONFLICT EXISTS BETWEEN THE UFC AND ANY OTHER UFC 1-3 1
CRITERIA DoD DOCUMENT, REFERENCED CODE, STANDARD OR
PUBLICATION THEN THE UFC TAKES PRECEDENCE.
2.2 ANTITERRORISM ANTITERRORISM REQUIREMENTS MUST NOT PRECLUDE ANY UFC 3-3.1 7
STANDARDS FIRE PROTECTION REQUIREMENTS.
2.3 DESIGN ANALYSIS FIRE PROTECTION DESIGN ANALYSIS IS REQUIRED. UFC 1-4 6
2.2 BASIC CRITERIA FIRE RESISTANCE REQUIREMENTS, ALLOWABLE FLOOR UFC 2-1 9
AREA, BUILDING HEIGHT LIMITATIONS, AND SEPARATION
DISTANCE REQUIREMENTS SHALL CONFORM TO IBC.
1
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
3 USE AND USE CHAPTER 3 OF IBC AND UFC 3-600-01. IF ANY 2-3 2
OCCUPANCY CONFLICTS OCCUR, THE REQUIREMENTS OF UFC 3-600-01
CLASSIFICATION TAKE PRECEDENCE.
2
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
3.5 INCIDENTAL USE SPACES/ AREAS WHICH ARE INCIDENTAL TO THE MAIN IBC 508.2.5 85
AREAS OCCUPANCY SHALL BE SEPARATED OR PROTECTED IN C5-34
ACCORDANCE WITH TABLE 508.2.5 AND SHALL BE
CLASSIFIED IN ACCORDANCE WITH THE MAIN OCCUPANCY
OF THE PORTION OF THE BUILDING IN WHICH THE
INCIDENTAL USE AREA IS LOCATED.
3
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
3.6 SEPARATED EACH PORTION OF THE BUILDING SHALL BE INDIVIDUALLY IBC 508.4 86
OCCUPANCIES CLASSIFIED AS TO USE AND SHALL BE COMPLETELY C5-39
SEPARATED FROM ADJACENT AREAS BY FIRE BARRIER
WALLS OR HORIZONTAL ASSEMBLIES OR BOTH HAVING A
FIRE-RESISTANCE RATING DETERMINED IN ACCORDANCE
WITH TABLE 508.4 FOR THE USES BEING SEPARATED.
3.7 NONSEPARATED EACH PORTION OF THE BUILDING SHALL BE INDIVIDUALLY IBC 508.3 86
OCCUPANCIES CLASSIFIED AS TO USE. THE REQUIRED TYPE OF C5-36
CONSTRUCTION FOR THE BUILDING SHALL BE DETERMINED
BY APPLYING THE HEIGHT AND AREA LIMITATIONS FOR
EACH OF THE APPLICABLE OCCUPANCIES TO THE ENTIRE
BUILDING. THE MOST RESTRICTIVE TYPE OF
CONSTRUCTION, SO DETERMINED, SHALL APPLY TO THE
ENTIRE BUILDING. OTHER CODE REQUIREMENTS SHALL
APPLY TO EACH PORTION OF THE BUILDING BASED ON THE
USE OF THAT SPACE EXCEPT THE MOST RESTRICTIVE
APPLICABLE PROVISIONS OF SECTION 403 AND CHAPTER 9
SHALL APPLY TO THESE NON-SEPARATED USES. FIRE
SEPARATIONS ARE NOT REQUIRED BETWEEN USES,
EXCEPT AS REQUIRED BY OTHER PROVISIONS.
4
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
5.1 DEFINITION OF BUILDING AREA IS THAT AREA INCLUDED WITHIN IBC 502.1 79
BUILDING AREA SURROUNDING EXTERIOR WALLS AND AREAS WITHIN THE C5-2
HORIZONTAL PROJECTION OF THE ROOF OR FLOOR ABOVE.
5.2 HEIGHT AND AREA THE HEIGHT AND AREA FOR BUILDINGS OF DIFFERENT IBC 503.1 79
LIMITATIONS CONSTRUCTION TYPES SHALL BE GOVERNED BY THE C5-7
INTENDED USE AND SHALL NOT EXCEED THE LIMITS IN
TABLE 503 EXCEPT AS MODIFIED HEREAFTER.
5
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
5.3 HEIGHT AND STORY BUILDINGS PROTECTED THROUGHOUT WITH AUTOMATIC IBC 504.2 81
INCREASES SPRINKLER SYSTEM THE MAXIMUM HEIGHT MAY BE C5-12
INCREASED BY 20 FEET AND MAXIMUM NUMBER OF STORIES
INCREASED BY ONE STORY.
5.4 ALLOWABLE AREA 12,500 S.F. ALLOWABLE AREA ( MERCANTILE ) BASE AREA. IBC Table 503 80
BASED ON USE PRIOR TO MODIFICATIONS. & 506.4.1 82
GROUP
5.4 AREA AREA LIMITS OF TABLE 503 SHALL BE INCREASED DUE TO IBC 506.1 78
MODIFICATIONS FRONTAGE (If) AND AUTOMATIC SPRINKLER PROTECTION (Is)
PER THE FOLLOWING FORMULA.
Aa = { At + [ At x If ] + [ At x Is ] } ( Equation 5-1 )
Aa = ALLOWABLE AREA
At = AREA OF MOST RESTRICTIVE OCCUPANCY =
MERCANTILE = 12,500 S.F.
Is = INCREASE DUE TO INCLUSION OF FIRE SPRINKLER
= 3 ( I STORY BLDG OR AIR FORCE FACILITY( PER -
UFC 3-600-01) OR
= 2 ( 2 STORY BLDG ) OR
= 0 IF NOT SPRINKLERED UFC 2-5 2
If = INCREASE DUE TO BUILDING FRONTAGE
6
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
5.5 UNLIMITED AREA I-STORY BUILDINGS ALLOWED TO BE UNLIMITED IN AREA IF IBC 507.3 83
BUILDING EQUIPPED WITH AUTO SPRINKLER AND PER IBC 507.3 AND
INCLUDING A 60' CLEAR, OPEN AREA AROUND BUILDING.
EXCEPTIONS:
1. MEZZANINE AREA ENCLOSED BY AN OCCUPANT LOAD OF
NOT MORE THAN 10.
( FOR EXAMPLE, CAN ENCLOSE A MECHANICAL AREA OF UP
TO 3,000 S.F WITH AN OCCUPANT LOAD OF 1/300 = 10.)
7
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
5.61 DEFINITION AND AGGREGATE AREA OF MEZZANINE(S) WITHIN A ROOM SHALL IBC 505.2 81
LIMITS NOT EXCEED ONE-THIRD OF THE ROOM OR SPACE IN WHICH C5-13
THEY ARE LOCATED IF EQUIPPED THROUGHOUT WITH A
SPRINKLER SYSTEM AND AN EMERGENCY VOICE/ALARM
COMMUNICATION SYSTEM.
5.62 ENCLOSURE REQ'S MEZZANINE SHALL BE OPEN AND UNOBSTRUCTED TO THE IBC 505.4 81
ROOM IN WHICH MEZZANINE IS LOCATED. C5-15
EXCEPTIONS:
1. MAY BE ENCLOSED IF OCCUPANT LOAD OF ENCLOSED
MEZZANINE SPACE DOES NOT EXCEED 10.
2. MEZZANINE HAS TWO OR MORE MEANS OF EGRESS WITH
ONE PROVIDING DIRECT ACCESS TO AN EXIT FROM THE
MEZZANINE.
3. AGGREGATE FLOOR AREA OF ENCLOSED SPACE DOES
NOT EXCEED 10% OF MEZZANINE AREA.
5.63 MEZZANINE MEANS TWO INDEPENDENT MEANS OF EGRESS REQUIRED FROM 505.3 81
OF EGRESS MEZZANINE UNLESS MEZZANINE IS OPEN (NOT ENCLOSED)
AND MEETS ALL REQ'S OF IBC 1015.1.
1. OCCUPANT LOAD IS NO MORE THAN 49 AND IBC 1015.1 238
2. COMMON PATH OF TRAVEL DOES NOT EXCEED BUILDING
TRAVEL DISTANCE AND
3. PER IBC SECTIONS 1015.3, 1015.4 & 1015.5.
8
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
6.3 FIRE-RESISTIVE NO FIRE RESISTANCE RATING REQUIRED ON STRUCTURAL IBC Table 601 89
RATINGS FRAME, BEARING WALLS, FLOOR, & ROOF.
EXTERIOR BEARING WALLS PER IBC Table 601. IBC Table 602 90
- FRT PLYWOOD MUST NOT BE USED IN ANY PART OF THE UFC 2-13.1 16
ROOF OR ROOFING SYSTEM.
9
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
4. INTERIOR FLOOR FINISH AND INTERIOR FINISH, TRIM, AND IBC 603.1.4 91
MILLWORK SUCH AS DOORS, DOOR FRAMES, WINDOW C6-15
SASHES, AND FRAMES.
7 FIRE-RESISTANT USE CHAPTER 7 OF IBC AND UFC 3-600-01. IF ANY CONFLICT 2-7 2
RATED OCCURS BETWEEN CHAPTER 7 AND UFC 3-600-01, THE
CONSTRUCTION REQUIREMENTS OF UFC 3-600-01 TAKE PRECEDENCE.
7.1 PROJECTIONS CORNICES, EAVE OVERHANGS AND SIMILAR IBC 705.2 & 97
ARCHITECTURAL APPENDAGES EXTENDING BEYOND THE 705.2.1 C7-22
FLOOR AREA IN TYPE II CONSTRUCTION SHALL BE OF
NONCOMBUSTIBLE MATERIALS.
7.2 PARAPETS PARAPETS NOT REQUIRED BY ANY OF THE EXCEPTIONS, 704.11 100
1. 0 HR. RATED WALLS OR
3. NONCOMBUSTIBLE CONSTRUCTION.
7.3 FIRE WALLS NOT TYPICAL ON DeCA COMMISSARIES UNLESS BUILDING IS IBC 706 101
DIRECTLY ATTACHED TO ANOTHER.
7.4 FIRE BARRIERS FOR BUILDINGS WITH A SECOND FLOOR: IBC 707.3 & 103
-SHAFTS : TYP. I HOUR RATED CONSTRUCTION PER IBC 707. 708 104
-STAIRWELLS: CONSIDERED EXIT ENCLOSURES AND
REQUIRE 1 HR. RATED CONSTRUCTION AND PER IBC 1020.
10
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
7.5 OPENING OPENINGS IN FIRE RATED CONSTRUCTION ARE REQUIRED IBC 715 113
PROTECTIVES PER IBC 715.
7.7 INSULATING USE ASTM E84 OR UL 723 FOR SMOKE AND FLAME RATINGS. IBC 719.1 124
MATERIALS
11
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
8.1 CLASSIFICATION WALL AND CEILING INTERIOR FINISHES SHALL BE TESTED IN NFPA 101 101-95
RATINGS ACCORDANCE WITH NFPA 255, ASTM E 84, OR UL 723 AND BE 10.2.3.4
CLASSIFIED AS FOLLOWS:
CLASS A: FLAME 0-25; SMOKE 0-450.
CLASS B: FLAME 26-75; SMOKE 0-450.
CLASS C: FLAME 76-200; SMOKE 0-450.
8.2 WALLS AND CEILING INTERIOR WALL AND CEILING FINISHES SHALL BE CLASS A NFPA 101 101-282
FINISHES OR CLASS B. 36.3.3.2
8.3 FLOOR FINISHES INTERIOR FLOOR FINISHES SHALL COMPLY WITH NFPA 101 101-282
10.2.7.1 ( CARPET) OR 10.2.7.2 ( MATERIALS OTHER THAN 36.3.3.3.3
CARPET).
0.1 W / cm (squared ) MIN. RADIANT FLUX REQUIRED FOR NFPA 101 101-97
FLOORING OTHER THAN CARPET. 10.2.7.2
8.4 TRIM AND CLASS "C" WALL AND CEILING TRIM AND INCIDENTAL NFPA 101 101-97
INCIDENTAL FINISH FINISHES ( SUCH AS BULLETIN BOARDS) ALLOWED IF LESS 10.2.5
THAN 10% OF AGGREGATE WALL AND CEILING AREA.
10 MEANS OF EGRESS USE UFC 3-600-01 IN LIEU OF IBC CHAPTER 10. 2-10 2
12
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
10.2 LIFE SAFETY - MIXED THE ENTIRE BUILDING SHALL COMPLY WITH THE MOST NFPA 101
OCCUPANCIES RESTRICTIVE FIRE AND LIFE SAFETY REQUIREMENTS OF 6.1.14.3.2 101-43
THE PREDOMINANT OCCUPANCIES INVOLVED WHICH IS
CLASS "A" MERCANTILE WITH ORDINARY HAZARD STORAGE.
13
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
10.5 MINIMUM NO. OF NOT LESS THAN 2 SEPARATE EXITS SHALL BE PROVIDED ON NFPA 101
MEANS OF EGRESS EVERY STORY - SEE MECHANICAL EXCEPTION BELOW. 36.2.4.1 (2) 101-280
- BUILDING
EXCEPTION : STORIES USED EXCLUSIVELY FOR NFPA 101
MECHANICAL EQUIPMENT, FURNACES, OR BOILERS SHALL 7.12.2 101-79
BE PERMITTED TO HAVE A SINGLE MEANS OF EGRESS
WHERE THE TRAVEL DISTANCE TO AN EXIT ON THAT STORY
IS NOT IN EXCESS OF THE COMMON PATH OF TRAVEL.
10.6 MINIMUM NO. OF A SINGLE MEANS OF EGRESS IS ALLOWED FROM A NFPA 101
MEANS OF EGRESS MEZZANINE PROVIDED THE COMMON PATH OF TRAVEL 36.2.4.5 101-281
- MEZZANINE ( TO AN EXIT ) DOES NOT EXCEED MAX. COMMON PATH
( 100' W/ SPRINKLER ).
10.7 EGRESS FROM MECHANICAL EQUIPMENT ROOMS, BOILER ROOMS AND NFPA 101 101-79
SPECIAL USE FURNACE ROOMS. 7.12
ROOMS
COMMON PATH OF TRAVEL NOT EXCEEDING 100' FOR NEW NFPA 101 101-79
AND 150' FOR EXISTING BUILDINGS WITH AN APPROVED , 7.12.1 (1) (a)
SUPERVISED AUTO SPRINKLER. 7.12.1 (2) (a)
NOTE: THE INTERNATIONAL BUILDING CODE (IBC) DENOTES IBC 1015.3 & 239
SPECIAL SECOND MEANS OF EGRESS REQUIREMENTS FOR 1015.4 &
BOILER, FURNACE AND REFRIGERATION MACHINERY ROOMS 1015.5
WHICH HAVE BEEN A PART OF COMMISSARY DESIGN FOR MANY
YEARS. HOWEVER, PER UFC, THE IBC MEANS OF EGRESS CODE
IS SUPERSEDED WITH THE NFPA MEANS OF EGRESS CODE WHICH
HAS NO SUCH SIMILAR REQUIREMENTS.
10.9 DEAD END DEAD ENDS CORRIDORS SHALL NOT EXCEED 50 FEET NFPA 101 101
CORRIDORS (WITH APPROVED, SUPERVISED AUTO. SPRINKLER 36.2.5.2.1
SYSTEM).
14
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
10.10 COMMON PATH OF COMMON PATH OF TRAVEL SHALL NOT EXCEED 100 FEET NFPA 101 101-294
TRAVEL (WITH APPROVED, SUPERVISED AUTO. SPRINKLER SYSTEM). 36.2.5.31
10.11 TRAVEL DISTANCE TRAVEL DISTANCE SHALL NOT EXCEED 250' IN ORDINARY NFPA 101 101-281
HAZARD, MERCANTILE OCCUPANCIES WITH AN APPROVED, 36.2.6.2
SUPERVISED AUTO. SPRINKLER SYSTEM.
10.12 EGRESS CAPACITY LEVEL COMPONENTS AND RAMPS = .2" / OCCUPANT. NFPA 101 101-72
AND WIDTH STAIRWAYS = .3 " / OCCUPANT. Table 7.3.3.1
36" MIN. EXIT ACCESS WIDTH IN NEW BUILDINGS. NFPA 101 101-72
7.3.4.1
28" MIN. EXIT ACCESS WIDTH IN EXISTING BUILDINGS. NFPA 101 101-72
7.3.4.1.2
10.13 MERCANTILE FRONT WALL EXITING: NFPA 101 101-281
SPECIFIC EGRESS IF THE ONLY MEANS OF CUSTOMER ENTRANCE IS THROUGH 36.2.5.7
REQUIREMENTS ONE EXTERIOR WALL OF THE BUILDING, A MINIMUM OF ONE-
HALF OF THE REQUIRED EGRESS WIDTH FROM STREET
FLOOR SHALL BE LOCATED IN SUCH WALL.
REQUIRED AISLES SHALL NOT BE LESS THAN 36" IN WIDTH. NFPA 101 101-281
36.2.5.5
15
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
10.15 EMERGENCY CLASS "A" MERCANTILE OCCUPANCIES SHALL HAVE NFPA 101 101-281
LIGHTING OF MEANS EMERGENCY LIGHTING IN ACCORDANCE WITH SECTION 7.9. 36.2.9
OF EGRESS
10.16 MARKING OF MEANS WHERE AN EXIT IS NOT IMMEDIATELY APPARENT FROM ALL NFPA 101 101-281
OF EGRESS PORTIONS OF THE SALES AREA, MEANS OF EGRESS SHALL 36.2.10
HAVE SIGNS IN ACCORDANCE WITH SECTION 7.10.
16
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
LOCKS :
LOCKS COMPLYING WITH 7.2.1.5.4 SHALL BE PERMITTED NFPA 101 101-280
ONLY ON PRINCIPLE ENTRANCE EXIT DOORS. 36.2.2.2.2
POWERED DOORS :
WHERE MEANS OF EGRESS DOORS ARE OPERATED BY NFPA 101 101-52
POWER, THE DESIGN SHALL BE SUCH THAT, IN THE EVENT 7.2.1.9.1
OF POWER FAILURE, THE DOORS OPEN MANUALLY TO
ALLOW EGRESS TRAVEL.
17
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
11.1 APPLICATION ALL AREAS OF NEWLY DESIGNED AND CONSTRUCTED ABA F201.1
BUILDINGS AND FACILITIES, AND ALTERED PORTIONS OF
EXISTING BUILDINGS SHALL COMPLY WITH THESE
REQUIREMENTS.
11.3 ACCESSIBLE EACH SITE ARRIVAL POINT MUST BE CONNECTED BY AN ABA F206.2.1
ROUTES ACCESSIBLE ROUTE TO THE ACCESSIBLE ENTRANCE(S)
SERVED.
18
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
11.4 ACCESSIBLE PARKING LOT IS NOW REFERENCED AS 'FACILITY' WHICH ABA F208.2
PARKING SPACES INDICATES BOTH PARKING LOTS AND PARKING ADVISORY
STRUCTURES.
WHERE MORE THAN ONE PARKING FACILITY ( LOT ) EXISTS ABA F208.2
ON A SITE, CALCULATE MINIMUM NUMBER OF SPACES ADVISORY
WITHIN EACH FACILITY BASED ON PARKING TOTAL OF CARS
WITHIN EACH FACILITY - NOT BASED ON TOTAL NUMBER OF
SPACES FROM ALL FACILITIES ON A SITE.
PROVIDE A MINIMUM OF 1 VAN PARKING SPACE PER 502 AND ABA F208.2.4
NOT LESS THAN ONE VAN PARKING SPACE FOR EVERY 6
PARKING SPACES REQUIRED OR FRACTION THEREOF.
19
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
STANDARD PARKING STALL: PROVIDE MINIMUM 8' WIDE ABA F502.2 &
STALL WITH A MINIMUM 5' WIDE ( FULL LENGTH) ACCESS F502.3
AISLE WHICH IS MARKED TO DISCOURAGE PARKING ( CROSS
STRIPE ) AND IS CONNECTED TO ACCESSIBLE ROUTE.
ACCESS AISLES MAY BE SHARED BETWEEN ACCESSIBLE
STALLS.
VAN PARKING STALL : 11' WIDE WITH ACCESS AISLE ABA F502.2 &
SIMILAR TO STANDARD ABOVE. MAY RECONFIGURE VAN F502.3
SPACE TO 8' WIDE STALL WITH 8' WIDE ACCESS AISLE.
- BOTH CONFIGURATIONS ARE A 16' WIDE VAN SPACE.
- NOT REQ'D BUT BEST TO CONFIGURE ACCESS AISLE ON
RIGHT SIDE OF VAN PARKING.
PARKING SHALL BE LOCATED WITHIN ONE LOT AND ON THE ABA F208..3.1
SHORTEST ROUTE TO AN ACCESSIBLE ENTRANCE. WHERE
THERE IS MORE THAN ONE ACCESSIBLE ENTRANCE,
ACCESSIBLE STALLS MAY BE DISPERSED IN DIFFERENT
LOTS AND LOCATED ON SHORTEST ROUTES TO EACH DOOR
IF THAT IS A BENEFIT - SEE ADVISORY F208.3.1.
11.5 PASSENGER MINIMUM 8' WIDE X 20' LONG VEHICULAR PULL-UP SPACE. ABA F503.2
LOADING ZONE
ADJACENT TO PULL-UP SPACE, PROVIDE 5' WIDE ACCESS
AISLE X LENGTH OF PULL-UP, FOR LOADING OF
PASSENGERS. ACCESS AISLE SHALL BE SLOPED < = 1:48, AT
SAME LEVEL AS PULL-UP AISLE AND MARKED TO
DISCOURAGE PARKING.
HANDRAILS :
- PROVIDE ON BOTH SIDES OF STAIRS AND RAMPS. ABA 505.2
- 34-38" ABOVE NOSINGS, RAMPS AND LANDINGS. ABA 505.4
- EXTEND SLOPING HANDRAIL 1 TREAD DEPTH AT BOTTOM ABA
OF STAIRS, 1'-0" HORIZ. AT TOP OF STAIRS AND 1'-0" HORIZ. 505.10.1 - 3
AT TOP AND BOTTOM OF RAMPS.
20
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
- 56" DEEP X 60" WIDE MIN. ACCESSIBLE TOILET STALL SIZE ABA 604.8.1.1
( WITH WALL-HUNG TOILET ).
21
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
11.9 FIRE ALARM PERMANENTLY INSTALLED AUDIBLE AND VISIBLE ALARMS ABA 702
SYSTEMS COMPLYING WITH NFPA 72 ( 2002) WITH EXCEPTIONS.
11.11 SALES AND SERVICE PROVIDE AT LEAST ONE ACCESSIBLE COUNTER AREA: ABA 904.4.1 &
COUNTERS FRONT APPROACH: 30" WIDE X 36" MAX. HIGH COUNTER. 904.4.2
SIDE APPROACH: 36" LONG X 36" MAX. HIGH COUNTER.
11.12 CHECK-OUT AISLES, ALL SHALL COMPLY WITH 904 - ABA F227.1
QUEUES (ON AN ACCESSIBLE ROUTE ).
22
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
12.1 FLOORS TOILET ROOM FLOORS SHALL HAVE A SMOOTH, HARD, NON- IBC 1210.1 274
ABSORBENT SURFACE THAT EXTENDS WITH A 4" MINIMUM C12-16
HIGH WALL BASE.
12.2 WALLS WALLS WITHIN 2 FEET OF URINALS AND TOILETS SHALL IBC 1210.2 274
HAVE A SMOOTH, HARD, NON-ABSORBENT SURFACE TO A C12-16
HEIGHT OF 4 FEET ABOVE THE FLOOR AND WALL MATERIALS
SHALL BE OF A MATERIAL THAT IS NOT ADVERSELY
AFFECTED BY MOISTURE.
13 ENERGY EFFICIENCY USE UFC 3-400-01 IN LIEU OF IBC CHAPTER 13. 2-13 3
15.1 LOW-SLOPE FULLY ADHERED ROOF SYSTEMS . . . SHALL BE TESTED IN IBC 1504.3.1 288
ROOFING ACCORDANCE WITH FM4450, FM4470, UL 580 OR UL 1879. C15-5
23
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
15.2 HIGH-SLOPE ROOF SYSTEMS SHALL BE TESTED IN ACCORDANCE WITH IBC 1504.3.2 288
ROOFING UL 580 OR ASTM E 1592. C15-5
15.3 METAL FASCIAS AND LOW-SLOPE ROOF SYSTEM METAL EDGE SECUREMENT , IBC 1504.3.2 288
COPINGS EXCEPT GUTTERS, SHALL BE ANSI/SPRI ES-1, -03 TESTED. C15-5
16 STRUCTURAL USE IBC CHAPTER 16 AND UFC 3-310-01 FOR STRUCTURAL 2-16 3
DESIGN LOADING DATA AND USE UFC 3-310-04 TOGETHER WITH IBC
CHAPTER 16 FOR SEISMIC DESIGN.
18 SOILS AND USE IBC CHAPTER 18 AS MODIFIED BY UFC 3-301-01. FOR 2-18 4
FOUNDATIONS NAVY AND MARINE CORPS FACILITIES, ALSO USE UFC 3-220-
01N.
24
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
21.1 MATERIALS LOAD-BEARING CMU SHALL CONFORM TO ASTM C 90. IBC 2103 432
C21-14
24.1 SAFETY GLAZING THE FOLLOWING GLAZED AREAS SHALL BE CONSIDERED IBC 2406.3 524
HAZARDOUS LOCATIONS REQUIRING SAFETY GLAZING C24-14
MATERIALS:
1. ALUMINUM & GLASS SWINGING DOORS.
2. FIXED AND SLIDING PANELS OF AUTOMATIC SLIDING
ENTRY/EXIT DOORS.
3. GLAZING WITHIN 24" HORIZONTAL OF A DOOR JAMB AND
WHERE BOTTOM OF PANE IS LESS THAN 60" ABOVE FLOOR.
(CURTAIN WALLS AND STOREFRONT ADJACENT TO ENTRY
DOORS).
4. GLAZING IN A WINDOW PANE > 9 S.F. AND EXPOSED
BOTTOM EDGE < 18 " A.F.F. AND EXPOSED TOP EDGE > 36"
AND WITHIN 3' HORIZONTAL OF A WALKING SURFACE.
25
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
26.1 FOAM PLASTIC NOTE : THE FOAM PLASTIC NOTED IN THE FOLLOWING SECTIONS
INSULATION WOULD ENCOMPASS THE RIGID INSULATION TYPICALLY USED
WITHIN DECA COMMISSARY ROOFING AND MASONRY CAVITY
WALLS AS WELL AS THE INSULATION MATERIAL WITHIN COOLER
AND FREEZER WALL PANELS.
26.2 FOAM PLASTIC FOAM PLASTIC INSTALLED AS INTERIOR TRIM MUST MEET IBC 2604.2 539
FINISH AND TRIM SECTIONS 2604.2.1 - 4 WHICH INCLUDES DENSITY, C26-13
THICKNESS, AREA LIMITATION AND FLAME SPREAD.
26
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
28 MECHANICAL 2-28-1 USE IBC CHAPTER 28 AND UFC 3-400-10N FOR NAVY 2-28 4&5
SYSTEMS AND MARINE CORPS FACILITIES.
2-28.2 USE UFC 3-410-01FA IN LIEU OF IBC CHAPTER 28 FOR
ARMY AND AIR FORCE FACILITIES.
2-28.3 USE UFC 3-400-02 TO ACCESS CLIMATOLOGICAL DATA
FOR USE IN DESIGNING MECHANICAL SYSTEMS.
29.1 MINIMUM NUMBER NUMBER OF FIXTURES SHALL FOLLOW TABLE 2902.1 AND BE IBC 2902.1 549
BASED ON NUMBER OF OCCUPANTS. THE NUMBER OF C29-3
OCCUPANTS SHALL BE DETERMINED THE SAME AS FOR
MEANS OF EGRESS OCCUPANT LOAD (UFC REPLACES IBC
CHAPTER 7 WITH NFPA CHAPTER 7).
WATER CLOSET LAVATORY DRINKING FOUNTAIN IBC TABLE 550 & 551
/ OCCUPANT / OCCUPANT / OCCUPANT 2902.1 C29-4 & 5
27
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
ADDITIONAL NOTES:
- ADD TOTALS AND DIVIDE WATER CLOSETS AND
LAVATORIES BY 2. PROVIDE THIS NEW NUMBER
(ROUNDED UP IF IT IS A FRACTION) FOR EACH SEX.
- PROVIDE A MINIMUM OF 1 SERVICE SINK OR FLOOR SINK
TOTAL PER FLOOR (STORY) WHERE ACCESSIBLE BY ALL
OCCUPANCIES.
- URINALS ( NON-NAVY ) URINALS CAN REPLACE A MAXIMUM
OF 2/3 OF THE TOILETS. EACH TOILET ROOM MUST HAVE AT
LEAST ONE WATER CLOSET.
- URINALS (NAVY ONLY) URINALS CAN REPLACE A MAXIMUM UFC 3-420-01 A-4
OF 1/3 THE TOILETS RATHER THAN THE TYP. 2/3. 403 D.
30 ELEVATOR AND USE IBC CHAPTER 30 AND UFC 3-600-01, AND ITG 01-01. 2-30 5
CONVEYING WHEN UFC 3-490-06 IS PUBLISHED, USE IBC CHAPTER 30,
SYSTEMS UFC 3-600-01 AND UFC 3-490-06.
30.1 GENERAL PASSENGER ELEVATORS SHALL CONFORM TO ICC A117.1. IBC 3001.3 C30-2
REQUIREMENTS - ICC A117.1 CONTAINS REQ'S FOR OPERATIONS, CLEARANCES,
CALLS, BUTTONS, MARKINGS ETC.
30.2 FIRE-RATING HOISTWAY ENCLOSURE SHALL BE A SHAFT ENCLOSURE IBC 3002.1.1 553
AND SHALL FOLLOW REQ'S OF IBC CHAPTER 7. C30-2
1-HR. RATED ENCLOSURE ( LESS THAN 4 STORIES ). IBC 707.4 103
C7-47
- EXCEPTION : NAVY PROJECTS REQUIRE A UFC 3-600-01 83
2-HOUR FIRE RESISTANT CONSTRUCTION FOR ALL 6-30.1
ELEVATOR HOISTWAYS.
28
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
30.3 EMERGENCY SIGNS PROVIDE "IN FIRE EMERGENCY, DO NOT USE ELEVATOR. IBC 3002.3 553
USE EXIT STAIRS." PICTOGRAPH. C3-2
30.4 ELEVATOR AND AN ELEVATOR CANNOT BE IN THE SAME ENCLOSURE AS A IBC 3002.7 553
STAIRS STAIR. C30-6
30.5 SECONDARY POWER WHERE A BUILDING HAS ONLY ONE ELEVATOR, THE IBC 3003.1.2 554
ELEVATOR SHALL AUTOMATICALLY TRANSFER TO STANDBY C30-7
POWER WITHIN 60 SECONDS AFTER NORMAL POWER
FAILURE.
30.6 EMERGENCY ELEVATORS SHALL BE EQUIPPED WITH PHASE 1 ( IBC 3003.2 554
OPERATIONS EMERGENCY RECALL) AND PHASE II ( IN-CAR OPERATION) C30-7
OPERATIONS.
30.7 MACHINE ROOMS 1-HR FIRE RATED FIRE BARRIER WALLS WITH 1-HR FIRE IBC 3006.4 555
RATED DOORS. C30-12
- IBC DOES NOT SPECIFICALLY NOTE WALL RATING FOR
MACHINE ROOMS BUT REQ. CAN BE INFERRED FROM TEXT.
33 SAFEGUARDS USE IBC CHAPTER 33 AND UFC 3-600-01. IF ANY CONFLICT 2-33 5
DURING OCCURS BETWEEN IBC CHAPTER 33 AND UFC 3-600-01, THE
CONSTRUCTION REQUIREMENTS OF UFC 3-600-01 TAKE PRECEDENCE.
29
CODE ANALYZED : UNIFIED FACILITIES CRITERIA UFC 1-200-01, 16 AUG 2010
35 REFERENCE USE IBC CHAPTER 35 AND APPENDIX "A" IN UFC 1-200-01. 2-35 6
STANDARDS
30
DESIGN A/E NOTE - GUIDE SPECIFICATION CONVENTIONS
Color-highlighted text
Yellow: Editors Notes. Comments inserted into the text are addressed to the A/E, not the
Contractor. Editors Notes are formatted as hidden text. Editors Notes are not identified with an
update. Do not print Editors Notes in issue for distribution to Bidders/Contractors.
Tip: To not print Editors Notes (hidden text) in document choose Tools on Menu bar, click Options, Print
tab, under Include with document, uncheck Hidden text (check to print text), click OK. Save.
Tip: To view Editors Notes (hidden text) in a document choose Tools on Menu bar, click Options, View
tab, under Formatting marks, check Hidden text (uncheck to hide text), click OK. Save.
Text Editing
Select options [in brackets] and edit <notes> before issuing specifications for distribution to
Bidders/Contractors.
Tip: To delete strikethrough text, choose Edit on Menu bar, click Find, Find tab, More (Search Options
opens), select All, click Format, Font, check Strikethrough, OK.
Click Replace tab, Replace All, OK, Close. Save.
Tip: To delete highlighting, locate cursor at beginning of Section and block all text in Section,
press Shift + Control + End, click No Highlight icon on Formatting toolbar. Save.
IMPORTANT: Retain month and year in footer indicating updated Guide Specification
Section issue used. Actually this now is located at the beginning of the section right
below the section title!
Note: This page will not print when Hidden text is unchecked as indicated in Editors Notes Tip.
FOR MICROSOFT WORD 2000 and 2003, CLICK ON SHOW/HIDE ICON IN MENU BAR OR CHOOSE
TOOLS IN MENU BAR. THEN CLICK OPTIONS, VIEW TAB, UNDER FORMATTING MARKS, CHECK
HIDDEN TEXT.
FOR MICROSOFT WORD 2007, CLICK ON MICROSOFT OFFICE ICON LOCATED IN UPPER LEFT
CORNER OF MENU BAR. CLICK ON WORD OPTIONS AT BOTTOM OF DROP DOWN. THEN CLICK
ON DISPLAY. CHECK THE HIDDEN TEXT BOX.
FOR MICROSOFT OFFICE 2010, CLICK ON FILE BUTTON LOCATED IN UPPER LEFT CORNER OF
MENU BAR. IN THE DROP DOWN, CLICK ON OPTIONS, AND A WORD OPTIONS BOX WILL
APPEAR. CLICK ON DISPLAY. CHECK THE HIDDEN TEXT BOX.
SECTION 01 45 00
QUALITY CONTROL
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
SECTION 01 11 00
SUMMARY OF WORK
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Miscellaneous provisions.
B. Related Requirements:
1.2 PROJECT
A. The Work performed under this Contract consists of providing all plant, labor, appliances,
equipment, materials, permits, bonds, insurance, and performing all operations necessary and
incidental to the work, in accordance with the Contract Drawings and Specifications to complete
the following project:
1. Project Name: <Enter project name as it appears on the drawings. (i.e., Additions /
Alterations Commissary Facility>.
2. Project Location: <Enter project location as it appears on the drawings>.
3. Project Number: <Enter project number. Note: This is not a solicitation number or
contract number>.
4. Project Type: [New Store] [Add/Alter].
5. Design Loads: [As indicated on drawings].
A. The primary function of the facility is to provide sales and processing of miscellaneous
commodities and grocery items for the military community of the installation. The paragraphs
below depict the general nature of the work. The work includes, but is not limited to, the items
listed in the paragraphs.
The following are examples for a new store. Edit for Project.
The following are examples for an existing store. Edit for Project.
B. Existing Store: An existing structure with continued commissary operations during construction
operations. Commissary operations remain in complete and full operation during the contract
duration.
1. Expansion of existing building to the rear (southeast). Exterior architectural features are
site cast concrete tilt-up wall panels matching existing. Interior finishes of panels are
metal studs, batt insulation and gypsum board except at warehouse area where interior
finish is concrete masonry units.
2. Front of existing commissary has canopy extended across front. Administration area
entrance has similar canopy.
3. Provide three new vestibules (one for entry and two for exit/bagger return) by enclosing
areas under existing canopy with aluminum/glass storefront system and sliding automatic
entrance doors.
D. The addition shall have an insulated single-ply fully adhered EPDM roofing system over metal
decking.
1. Interior alterations include: Prefabricated insulated coolers and freezers; floor finishes of
sealed concrete, terrazzo, vinyl composition tile, carpeting, ceramic tile, and resinous
flooring; wall finishes of paint, ceramic tile, and fiberglass reinforced panels; and ceiling
finishes of suspended acoustical panels and gypsum wallboard.
2. Replace all display cases throughout Sales Area and update decor in the Sales and
Checkout Area. New decors includes wall, floor, and ceiling finishes, lighting systems,
department signage, accent graphics, aisle directory signs, and slot boards.
3. Rework existing Entry/I.D. Check Area: Include new I.D. Desk located closer to entry
doors and rework floral alcove directly behind it.
4. Rework Checkout Area: Eliminate 5 of 21 checkstands and provide Mass Display Areas
on north and south sides of Checkstands. Enclose Mass Display Area with low partitions
on three sides of south end.
5. Rework Administration Area to make it more efficient for use of staff and vendors.
Provide updated decor in reworked rooms.
6. Replace Meat Storage Freezer and west wall of Frozen Food Storage Freezer. Provide
new cooler wall/ceiling system for Produce Processing. Provide new concrete curbs in
Meat Processing.
7. Additional work includes repair/replacement of existing deficiencies throughout the
Commissary Facility.
8. Remove existing roof system and replace with new E.P.D.M. single-ply membrane roof
system.
F. Site Work:
1. Site construction includes parking areas, sidewalks and landscape improvements around
the facility.
2. Benches, trash receptacles, and a bicycle rack are required.
A. Mount overhead mounted architectural features weighing 31 lbs or more (excluding distributed
systems such as suspended ceilings that collectively exceed that weight) in accordance with the
following to minimize the likelihood they will fall and injure building occupants:
1. Mount such systems so they resist forces of 0.5 times the component weight in any
horizontal direction and 1.5 times the component weight in the downward direction.
2. This requirement does not preclude the need to design architectural feature mountings
for forces required by other criteria such as seismic requirements.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Notice to Proceed.
B. Related Sections:
1.2 SUBMITTALS
A. Submittal List:
A. The Contracting Officer will issue the Notice to Proceed only after Government receipt of
Performance and Payment Bonds.
B. Contract Completion:
1. The Notice to Proceed sets the Contractor's Contract start and completion date.
1. The activities listed are all included in the time period set forth to complete the Project.
2. Within ten (10) calendar days after receipt of Notice to Proceed, generate and submit all
items listed for Government review and/or approval. Government acknowledgement of
their approval of these items is a condition-precedent to the Contractors commencement
of any building construction[ or demolition] activity. Allow for Government review time
of 21 calendar days for the first submission and an additional 14 calendar days for any
re-submittals, if required.
D. Construction[/Demolition]:
1. Notify the Contracting Officer upon 100 percent completion of the items listed under
Mobilization and Submittal Processing and then commence construction[/demolition]
activities.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. Use of the Site: Limit use of the premises to work in areas indicated in the Contract
Documents. Confine operations to areas within contract limits indicated. Do not disturb
portions of the site beyond the indicated work areas. Utilize the lay down area identified in the
Contract Drawings for all materials and supplies.
B. Driveways and Entrances: Unless otherwise indicated, keep driveways and entrances serving
the premises clear and available to the government, government employees, store patrons,
truck traffic, and emergency vehicles at all times. Do not use these areas for parking or storage
of material. Schedule deliveries to minimize space and time requirements for storage of
materials and equipment on site.
D. Assume full responsibility for protection and safekeeping of material, equipment, and products
stored on premises.
E. Keep temporary office, yard, and material storage (staging) areas arranged in orderly manner,
clean, and mowed. Repair areas damaged during construction operations.
F. Use of Existing Building: Maintain existing building in a weather tight condition throughout
construction period. Repair damage caused by construction operations. Protect building and its
occupants during construction period.
H. Obtain and pay for use of additional storage or work areas as needed for Contractor operations.
I. Provide signage and physical barriers to control, direct, and maintain vehicular and pedestrian traffic
during the construction process.
A. Use of the Site: Limit use of the premises to work in areas indicated in the contract documents.
Confine operations to areas within contract limits indicated. Do not disturb portions of the site
beyond the indicated work areas. Utilize the lay down area identified in the Contract Drawings
for all materials and supplies.
B. Government Occupancy: Allow for government occupancy. Do not disrupt operations of the
existing facility. Coordinate use of premises under direction of the Contracting Officer. Provide
and maintain signage and barriers to prevent patrons and DeCA store employees access into
construction areas.
D. Relocate stored construction materials or equipment that interferes with commissary operations.
E. Schedule deliveries to minimize space and time requirements for storage of materials and
equipment on-site. Do not unreasonably encumber site with materials or equipment.
F. Assume full responsibility for protection and safekeeping of material, equipment, and products
stored on premises.
G. Keep temporary office yard and material storage (staging) areas arranged in orderly manner,
clean and mowed. Repair areas damaged during construction operations.
H. Use of Existing Building: Maintain existing building in a weather tight condition throughout
construction period. Repair damage caused by construction operations. Secure and protect
building and its occupants during construction period.
I. Provide temporary chain link fence enclosure (gated and locked) around material storage area
as indicated and as specified in Division 01 Section Temporary Facilities and Controls. The
temporary construction fence remains in place until final acceptance of the Project. Provide
temporary barriers around site work areas to keep pedestrians out of the construction areas.
J. Obtain and pay for use of additional storage or work areas as needed for Contractor operations.
K. Provide signage and physical barriers to control, direct, and maintain vehicular and pedestrian
traffic during the construction process.
L. Do not impact/disturb surfaces that are known to contain hazardous materials until properly
trained workers and systems are established to prevent release, transport, and disposal. If
unknown/suspect hazardous materials are scheduled to be disturbed, Contractor to cease work,
notify Contracting Officer, and allow confirmation by CIH prior to proceeding.
A. Partial Government Occupancy: The government reserves the right to occupy and to place and
install equipment in areas of the facility under construction prior to construction completion,
provided such occupancy does not interfere with completion of the work.
A. Full Government Occupancy: The government will occupy the site and existing facility during
the entire construction period. Cooperate with the government during construction operations to
minimize conflicts, store disruptions, and facilitate government usage. Perform the work so as
not to interfere with the government's operation.
B. Contractor Occupancy: [Seven] calendar days prior to Contractor occupancy of any phase or
subphase of construction, submit a written request to the Contracting Officer for approval to
move and work in the area. Approval of said request will depend on Contractor's satisfactorily
completing other contract requirements, such as but not limited to, returning other phases to the
Commissary in a condition ready for occupancy.
C. Partial Government Occupancy: The government reserves the right to occupy and to place and
install equipment in areas of the facility under construction prior to construction completion,
provided such occupancy does not interfere with completion of the work.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Funding.
2. Construction versus equipment elements.
3. Modification procedures.
B. Related Sections:
1. Division 01 Section Notice to Proceed.
2. Division 01 Section Administrative Requirements.
3. Division 01 Section Construction Progress Documentation.
4. Division 01 Section Project Web Site.
5. Division 01 Section Quality Control.
6. Division 01 Section Temporary Facilities and Controls.
7. Division 01 Section Closeout Procedures.
1.2 SUBMITTALS
B. Submittal List:
1.3 FUNDING
A. Elements of Work: The Government may fund different elements of the Work from different
funding sources. Identify and segregate costs of the different elements of the Work when
preparing the Critical Path Method (CPM) Construction Schedule and Contract modification
proposals.
A. Refer to the attachment at the end of this Section for identification of building components and
process equipment.
A. Supplemental Instructions:
1. From time to time during progress of the Work the Contracting Officer may issue
supplemental instructions which interpret the Contract Documents or order minor
changes in the Work without change in Contract Sum or Contract Time.
2. Should the Contractor consider that these instructions or minor changes require a change
in the Contract Sum or Contract Time, he shall comply with F.A.R. notice requirements,
and then submit an itemized proposal to the Contracting Officer prior to proceeding with
the Work. If the government agrees to entitlement and the proposal is satisfactory and in
proper order, a Contract Modification for that event will supersede the supplemental
instructions.
B. Proposal Requests:
1. From time to time during progress of the Work, the Contracting Officer may issue a
proposal request for an itemized quotation for a potential change in the work that affects
the Contract Sum or Contract Time.
2. This is not a direction to proceed with the changes described therein.
D. Modification Requests:
1. Government-initiated Proposal Requests: The Contracting Officer will issue a detailed
description of proposed changes in the work that will require adjustment to the Contract
um or Contract Time. If necessary, the description will include supplemental or revised
Drawings and Specifications. Proposal requests issued by the Contracting Officer are for
information only. Do not consider them an instruction either to accelerate or stop work in
progress or to execute the proposed change.
2. Contractor-initiated Proposals: When differing or unforeseen conditions require
modifications to the Contract, the Contractor may propose changes by submitting a
request for change to the Contracting Officer. Comply with F.A.R. notice requirements.
Include a statement outlining the reasons for the change and the effect of the change on
the Work. Provide a complete description of the proposed change. Indicate the effect of
the proposed change on the Contract sum or schedule by including a detailed cost
proposal and the CPM Construction Schedule depicting affected critical path changes.
E. Allowances:
1. Allowance Adjustment: For unit cost allowance adjustment, base each modification
proposal on the difference between the actual unit purchase amount and the unit
allowance, multiplied by the final measurement of work-in-place. Where applicable,
include reasonable allowances for cutting losses, tolerances, mixing wastes, normal
product imperfections, and similar margins.
2. Unless specifically directed otherwise, include furnishing and installing the allowance
item, inclusive of any testing or start-up requirements, in the allowance cost.
G. Errors or Omissions:
1. Promptly, and substantially before work scheduled on such conditions (except in an
emergency), notify the Contracting Officer in writing of:
a. The discovery of an error, omission, or some other conflict with the Contract
Documents that materially affect the intended use of the facility.
2. The Governments Designated Inspector will promptly investigate the conditions and will
notify the Contracting Officer who will provide the Contractor with instruction.
H. Proposal Preparation:
1. Include a detailed list of quantities of required products, labor, hours, rates, and unit
costs, with the total amount of purchases.
a. State proposed change in the Contract Sum, if any.
b. State proposed change in the Contract Time of completion supported by a fragnet.
c. Clearly describe other changes in the Work, if any, required by the proposed
change.
d. Include full backup data such as subcontractors letter of proposal or similar
information.
2. List and include applicable taxes, delivery charges, equipment rental, and amounts of
trade discounts.
3. Comply with paragraphs of this Contract that address substitution.
4. Within 10 days of receipt of a proposal request, on AF 3052, submit the proposal of cost
necessary to execute the change, including time impact related costs, to the
Governments Designated Inspector for review.
5. Refer to Division 01 Section Construction Progress Documentation for required schedule
related attachments to the proposal.
6. The Contracting Officer will negotiate maximum mark-ups allowed in proposal cost
estimates.
CONSTRUCTION
BUILDING SITE WORK
normal architectural finishes, both interior and Improvements for parking, circulation, walks,
exterior. and receiving areas, including lighting more
than 5' outside building lines.
plumbing, including sinks, toilets, and other
fixtures Traffic safety devices, controls and other
improvements.
utility meters.
landscaping.
fire protection and alarm systems.
retention ponds, environmental mitigation.
electrical power & lighting to the building and
equipment, including power to all equipment site demolition.
such as balers, material handling equipment,
charger units, processing equipment, etc. (but utilities more than 5' outside building lines and
NOT to refrigerated equipment). associated costs of extending utilities to the
site.
fire extinguisher cabinets
berms and force protection barriers
toilet partitions
exterior protective bollards and guard rails
toilet and bath accessories fencing and other screening
DAIRY DEPARTMENT
PROCESSING AREAS
roll-in dairy milk bossy carts
ice machines.
work tables
PRODUCT REFRIGERATION SYSTEMS
scales.
walk-in coolers and freezer enclosures.
refrigerated unit doors, seals, strips, and heater
elements. OTHER
electrical power tie-in to all refrigerated telephone, intercom, public address and other
systems. in-store communications systems.
blowers and exhaust systems. sales area marketing dcor, including all
departmental and store signage
refrigeration system controls and monitoring
devices. lockers
END OF SECTION
1.1 SUMMARY
A. Section Includes:
1. Project coordination.
2. Submittal procedures.
3. Shop Drawings.
4. Product data.
5. Quality Assurance submittals.
6. Samples.
7. Substitutions.
8. Requests for information procedures.
9. Project Register.
10. Contractor Production Report.
11. Record photographs.
B. Related Sections:
1.2 SUBMITTALS
A. Submittal Schedule:
1. Provide the indicated quantity. Note that the Government will retain three copies and the
pdf file.
B. Submittal List:
A. Comply with the Governments procedures for intra-project communications; submittals, report
and records, schedules, coordination drawings, and recommendations; and resolution of
ambiguities and conflicts.
1. Sequence construction operations where installation of one part of the work depends on
installation of other components, before or after its own installation.
2. Sequence construction operations to ensure that completed or work in progress is not
subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the
construction period.
3. Coordinate installation of different components to ensure maximum accessibility for
required maintenance, service, and repair.
4. Make provisions to accommodate items scheduled for later installation.
C. Where necessary, prepare memoranda for distribution to each party involved, outlining special
procedures required for coordination. Include such items as required notices, reports, and
attendance at meetings.
1. Prepare similar memoranda for the government and outside contractors where required
for coordination of work.
1. Inspection of Conditions: Require the installer of each major component to inspect the
substrate and conditions for compatibility with manufacturer's installation requirements.
Do not proceed until the remedy of the unsatisfactory conditions.
2. Coordinate required inspections and tests to minimize the necessity of uncovering
completed construction.
1. Clean and protect construction in progress and adjoining materials in place, during
handling and installation. Apply protective covering where required to ensure protection
from damage or deterioration at substantial completion.
A. Definitions:
1. Field samples are full size physical examples erected on site to illustrate finishes,
coatings, or finish materials. Field samples will establish the standard by which the
Contracting Officer will judge the work.
2. Delegated-Design:
1) Indicate that products and systems comply with performance and design
criteria in the Contract Documents. Include list of codes, loads, and other
factors used in performing these services.
B. Send all material submittals for review to the Contracting Officer or Governments Designated
Inspector.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals,
and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related elements of work so
processing does not delay by the need to review submittals concurrently for coordination.
3. Processing: To avoid the need to delay installation as a result of the time required to
process submittals:
a. Allow 21 calendar days for initial review. Allow additional time if the reviewer must
delay processing to permit coordination with subsequent submittals.
b. If an intermediate submittal is necessary, process the same as the initial submittal.
c. Allow 14 calendar days for reprocessing each submittal.
d. Contracting Officer will not extend contract time because of failure to transmit
submittals to the reviewer sufficiently in advance of the work to permit processing.
E. Quantity of Submittals: Unless otherwise noted, provide four originals and 1 PDF version. The
Government will retain three copies and the pdf. To obtain additional reviewed sets, submit
additional sets over these requirements. The pdf file is not required for physical samples.
F. Submittal Preparation: Place a permanent label or title block on each submittal for
identification. Indicate the name of the entity that prepared each submittal on the label or title
block.
a. Include the following information on the label for processing and recording action
taken.
b. Project name.
c. Date.
d. Name and address of the reviewer.
e. Name and address of the Contractor.
f. Name and address of the subcontractor.
g. Name and address of the supplier.
h. Name of the manufacturer.
i. Number and title of appropriate Specification Section.
j. Drawing number and detail references, as appropriate.
G. Submittal Transmittal: Package each submittal appropriately for transmittal and handling.
Transmit each submittal from the contractor to the reviewer using the Government transmittal
form. The reviewer will not accept submittals received from sources other than the Contractor.
1. On the transmittal, record relevant information and requests for data. Comply with
paragraphs entitled "Substitutions," for deviations from contract document requirements,
including variations and limitations. Include Contractor's certification that information
complies with contract documents requirements.
2. Transmittal Form: Use Government Form Number AF 3000, "Material Approval
Submittal."
4. Distribution: Following response to the initial submittal, print and distribute copies to the
reviewer, subcontractors, and other parties required to comply with submittal dates
indicated. Post copies in the project meeting room and field office.
a. When Contractor makes revisions, distribute to the same parties and post in the
same locations. Delete parties from distribution when they have completed their
assigned portion of the work.
1. Action Submittals: Written and graphic information and physical samples that require
Contracting Officer's responsive action. Action submittals are those submittals indicated
in individual Specification Sections as follows:
2. Informational Submittals: Written and graphic information and physical samples that do
not require Contracting Officer's responsive action. Submittals may be rejected for not
complying with requirements. Informational submittals are those submittals indicated in
individual Specification Sections as follows:
A. Submit newly prepared information drawn accurately to scale. Highlight, encircle, or otherwise
indicate deviations from the Contract Documents. Do not reproduce contract documents or
copy standard information as the basis of Shop Drawings. Standard information prepared
without specific references to the Project is not a Shop Drawing.
B. Shop Drawings include fabrication and installation drawings, setting diagrams, schedules,
patterns, templates, and similar drawings. Include the following information:
1. Dimensions.
2. Identification of products and materials included by sheet and detail number.
3. Compliance with specific standards.
4. Notation of coordination requirements.
5. Notation of dimensions established by field measurements.
6. Sheet size: Except for templates, patterns, and similar full-size drawings, submit Shop
Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 42 inches.
7. Submittal: Submit blue or black line prints for review.
8. Do not use Shop Drawings without an appropriate final stamp indicating action taken.
9. Do not submit Shop Drawings until Contractor confirms compliance with requirements of
the contract documents.
10. Distribution: Furnish copies of final submittal to installer, subcontractors, suppliers,
manufacturer, fabricators, and others required for performance of construction activities.
Show distribution on transmittal form.
A. Collect product data into a single submittal for each element of construction or system. Product
data includes printed information, such as manufacturer's installation instructions, catalog cuts,
standard color charts, rough-in diagrams, templates, standard wiring diagrams, and
performance curves.
1. Mark each copy to show applicable choices and options. Where printed product data
includes information on several products that are not required, mark copies to indicate
the applicable information. Include the following information:
2. Do not submit product data until Contractor confirms compliance with requirements of the
Contract Documents.
3. Distribution: Furnish copies of final submittal to installer, subcontractors, suppliers,
manufacturer, fabricators, and others required for performance of construction activities.
Show distribution on transmittal form.
a. Do not proceed with installation until a copy of the approved product data is in the
Installer's possession.
b. Do not permit use of unmarked copies of product data for construction.
B. Bind each group of manufacturer's data and catalog cuts in a heavy paper binder such as "Duo-
tang" binder or an "Accopress" press board binder.
1.7 SAMPLES
A. Submit full-size fully fabricated samples cured and finished as specified and physically identified
with the material or product proposed. Samples include partial sections of manufactured or
fabricated components, cuts or containers of materials, color range sets, and swatches showing
color, texture, and pattern.
3. Preliminary Submittals: Submit a full set of choices where Contractor submits samples
for selection of color, pattern, texture, or similar characteristics from a range of standard
choices.
a. The reviewer will review and return preliminary submittals with the reviewer's
notations, indicating selection and other action. Do not proceed with installation
until a copy of the approved sample is in the Installer's possession.
4. Maintain sets of samples, as returned, at the project site, for quality comparisons
throughout construction.
a. Field samples are full size examples erected on site to illustrate finishes, coatings,
or finish materials, and to establish the project standard.
1. Review of submittal is to determine approval for general conformance with the design
concept and Contract Documents. Reviewer's approval is not an approval of any
deviation from the requirements of the Contract Documents. If the reviewer takes no
exceptions or comments or marks on or attaches to the submittal, it does not relieve the
Contractor from compliance with the Contract Documents. It does not construe
4. Action Stamp: The reviewer will stamp each submittal with a uniform action stamp. The
reviewer will mark the stamp appropriately to indicate the action taken as follows:
a. Final Unrestricted Release: When the reviewer marks a submittal "Approved" the
work covered by the submittal may proceed provided it complies with requirements
of the Contract Documents.
b. Final-but-Restricted Release: When the reviewer marks a submittal "Approved as
Noted," the work covered by the submittal may proceed provided it complies with
notations or corrections on the submittal and requirements of the Contract
Documents.
c. Returned for Re-submittal: When the reviewer marks a submittal "Not approved,
Revise and Resubmit," do not proceed with work covered by the submittal,
including purchasing, fabrication, delivery, or other activity. Revise or prepare a
new submittal according to the notations; resubmit without delay. Repeat if
necessary to obtain a different action mark.
5. Unsolicited Submittals: The reviewer will return unsolicited submittals to the sender
without action.
1.9 SUBSTITUTIONS
A. General:
1. The Contracting Officer will receive and consider the Contractor's request for substitution
when Contractor satisfies a, b, and c of the following conditions and one or more of the
items in d through k of the following conditions, as determined by the Contracting Officer.
If the Contractor does not satisfy these conditions, the Contracting Officer will return the
request without action except to record noncompliance with these requirements.
2. The contractor's submittal and the Contracting Officer's acceptance of Shop Drawings.
Shop drawings, product data or samples for construction activities not complying with the
Contract Documents do not constitute an acceptable or valid request for substitutions,
nor do they constitute approval.
C. Submittals:
1. Substitution Request Submittal: The Contracting Officer will consider requests for
substitution if received within 60 days after commencement of the Work. Contracting
Officer will reject requests received more than 60 days after commencement of the Work
at his discretion.
2. Contracting Officer's Action: If necessary, the Contracting Officer will request additional
information or documentation for evaluation for a request for substitution. The
Contracting Officer will notify of acceptance or rejection of the substitution within 20
calendar days after receipt, or 7 calendar days after receipt of additional information or
documentation. Acceptance will be in the form of a change to the Contract.
3. Use the product specified if the Contracting Officer cannot make a decision on the use of
a proposed substitute within the time allocated.
A. General:
1. Submit a Request for Information (RFI) when questions arise concerning interpretation,
conflicts, omissions, errors, or regulatory violations within the Contract Documents.
B. Review:
3. For RFIs determined as reasonable and a change to the contract price or time is not
involved, submit to the government using the transmittal processes described hereafter.
C. Transmittal:
D. Response:
1. Response Time:
a. Allow 14 calendar days for government review of the RFI. The Government will
respond to all RFI's on the Project website only. The Contractor will be able to
print out a hardcopy of the response from the website for its files.
2. If the response to the RFI does not involve a change to the contract, after receipt of the
government response, proceed as if the answer to the RFI existed within the Contract
Documents.
E. Changes to Contract:
1. For RFIs where the government determines a change to the Contract price or time is
appropriate, officially close the RFI and refer thereafter as a pending modification.
Comply with the modification requirements of Division 01 Section Contract Modification
Procedures.
F. Refer to Division 01 Section Project Web Site for project website related requirements.
A. Pre-Performance Conference:
3. Minutes: Entity responsible for conducting meeting will record and distribute meeting
minutes.
C. Progress Meetings:
a. Review the present and future needs of each entity present, including the
following:
1) Interface requirements.
2) Time.
3) Sequences.
4) Status of submittals.
3. Reporting: Provide minutes for the prior weeks progress meeting prior to each new
weekly meeting. No later than 3 days after each meeting, distribute minutes of the
meeting to each party present and to parties who should have been present. Include a
brief summary, in narrative form, of progress since the previous meeting and report.
1. An initial Red Zone meeting will be held to build a schedule of events necessary to
achieve project and fiscal completion within 120 days of the Project Beneficial Occupancy
Date (BOD). The initial meeting identifies key project milestones, responsibilities, and
target task completion dates. Particular attention must be given to the BOD and Grand
Opening (or Re-Opening) dates. The initial Red Zone meeting is held approximately 60
days prior to BOD.
2. The objective of each follow on weekly meeting is to discuss and record actual progress
of each task. If a specific task appears to be slipping or occurs earlier than the completion
date; means methods and resources will be discussed, identified, and committed to
maintain the Red Zone Schedule. The impact to related activities is determined and
discussed. The entire team is notified of the potential impact to the remaining work.
3. Attendees: At a minimum, the following attendees shall participate in the initial Red Zone
Meeting.
a. DeCA Project Manager: Chair of the Red Zone Meeting, Responsible for Design
and Construction of the Project.
b. DeCA Operations Monitor: Responsible for the operations activities related to the
Project.
c. DeCA Store Director: Responsible for Operational aspects of the Project.
d. DeCA Zone Manager.
e. DeCA Region Engineer.
f. DeCA Communications.
g. CARTS-DeCA POSM Personnel.
h. DeCA Equipment Personnel.
i. DeCA Contacting Branch/AMDF Contracting Officer: Authority for Construction
Contract.
j. Construction Contractor:
1) Superintendent.
2) Quality Control Manager.
3) Major Sub-Contractor Representatives.
4) Installation Personnel:
6) Commissioning Agent.
7) Architect of Record (As required per specific project requirements).
4. At a minimum, the following attendees shall participate in the follow on weekly Red Zone
Meetings. All other attendees from the initial meeting that are not listed below will attend
as required and shall receive copies of all weekly red zone meeting discussions.
1) Superintendent.
2) Quality Control Manager.
3) Major Sub-Contractor Representatives.
a. Initial Red Zone Meeting Date: The PMAC technical inspector will notify the DeCA
Project Manager of an estimated initial Red Zone Meeting date. This date will be
based on the construction Contractors CPM schedule and shall be estimated as
approximately 60 days prior to the construction Contractors scheduled BOD date.
The DeCA Project Manager will coordinate with the DeCA Operations Monitor and
a final date will be determined.
b. The DeCA PM; in conjunction with the PMAC TI will invite attendees related to the
construction portion of the Project to the meeting and the DeCA Operations
Monitor will invite the required attendees related to the operational activities of the
Project. Invitations to the meeting shall be distributed no later than 30 days prior to
the established initial Red Zone meeting date.
c. The DeCA PM chairs the initial Red Zone Meeting. The meeting discussions will
focus on the following three major areas:
6. Initial Red Zone Meeting Discussions: The group discusses remaining construction
activities and reaches a consensus on percent complete and remaining durations
required for each to include the agreed completion date. Operational activities are
identified and estimated durations and responsibilities are assigned to include the agreed
completion date. Participants build a schedule for completing each task in a logical
sequence, and assign responsibility for actions to reach financial completion. The
technical inspector records key project milestones, responsibilities and dates and
provides distribution to all team members prior to the close of the meeting. The TI shall
prepare minutes of the meeting to include all agreed dates, milestones, durations and
represented attendees. The team shall:
7. Follow on Weekly Red Zone Meeting Process: The PMAC technical inspector holds a
weekly construction meeting. Following the initial red zone meeting, the inspector will add
the red zone update to the weekly meeting agenda. Each member identified as a
mandatory attendee will provide input as to the status of each Red Zone
activity/milestone. The technical inspector will update the red zone schedule template
during the meeting. If any activity/milestone duration is different than originally planned,
the TI will identify the impact to remaining activities through the schedule software tool.
The TI will discuss with the Construction Contractor available options to maintain the
original agreed upon schedule. Emphasis shall be placed on maintaining the original
schedule. The TI shall review each impact and record the new status in the minutes. The
minutes shall be distributed to all responsible parties with specific attention brought to
any critical changes to the agreed upon schedule. If required, the DeCA PM will establish
a special meeting to help mitigate any problem that has the potential to extend the
Project end date and determine measures required to recover any lost time and bring the
activities back on schedule.
8. Suggested Activities/Milestones Listed by Responsibility:
CONSTRUCTION ACTIVITIES/MILESTONES
General Contractor
Communication System PA/Sound Beneficial Occupancy Date (BOD)
Installation As-Built Delivery
Lock and Key Plan Warranty Documents
Landscaping Complete Government Punchlist Complete
Test and Balance Systems User Training
Commissioning O & M Manual Submittal
GC Punchlist Complete DD 1354
Final Cleaning Construction Contract Complete
Pre-Final Inspection Release of Claims
Commissioning Agent
Commissioning
Installation
Fire System Inspection Installation Fire Department
Safety Inspection Installation Safety Department
Security Inspection Installation Security Department
PMAC
Run Weekly Meetings with Red Zone
Discussion PMAC TI
Update Red Zone Schedule PMAC TI
Photographer PMAC and/or Government
PMAC TI leaves site
Operations Monitor
Order GFGI
Order Vendor Contracts
Store Director
Furniture Installation/GFGI Installation
Store Set
Final Cleaning for Opening
User Move-in
Grand Opening
Government Contractor
Communication Phone System Installation
POS Installation
A. Register:
A. Submit reports for each day that Contractor performs work to the Governments Designated
Inspector by 10 AM (local) the following workday. Account for each calendar day throughout the
life of the Contract. Use the same terminology used in the construction schedule. The project
superintendent must prepare, sign, and date the Contractor Production Reports and include the
following information:
1. Date of report, report number, name of Contractor, Contract number, title and location of
contract and superintendent present.
C. Provide electronically via the project website. Refer to Division 01 Section Project Web Site, for
other requirements.
D. Record Photographs:
END OF SECTION
CONTRACTOR SUPERINTENDENT
WAS A JOB SAFETY MEETING HELD THIS DATE? oYES oNO TOTAL WORK HOURS ON JOB SITE
(If YES attach a copy of the meeting minutes) THIS DATE
WERE THERE ANY LOST TIME ACCIDENTS THIS DATE? oYES oNO
(If YES attach copy of completed OSHA report)
WAS TRENCHING/SCAFFOLD/HV ELECTRICAL/HIGH WORK DONE? oYES oNO CUMULATIVE TOTAL OF WORK
PART 1 - JOB
(If YES attach statement or checklist showing inspection performed) HOURS FROM PREVIOUS REPORT
WAS HAZARDOUS MATERIALS/WASTE RELEASED INTO THE ENVIRONMENT
(If YES attach description of incident and proposed action) oYES oNO
TOTAL WORK HOURS FROM START OF
CONSTRUCTION
LIST SAFETY ACTIONS TAKEN TODAY/SAFETY INSPECTIONS CONDUCTED SAFETY REQUIREMENTS HAVE BEEN MET
CONSTRUCTION AND PLANT EQUIPMENT ON JOB SITE TODAY. INCLUDE NUMBER OF HOURS USED TODAY
REMARKS
CONTRACTOR/SUPERINTENDENT DATE
FORM 01400-1 6/91
SHEET OF
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. General reference.
2. Related requirements.
3. Space reference.
4. Standards, laws, ordinances.
5. Operation and maintenance of equipment.
6. Wiring.
7. Grounding.
8. Access panels.
9. Operation and Maintenance Manuals.
10. Excavation and backfill.
11. Painting.
12. Vandal proofing.
13. Protective covering.
14. Interruption of service.
15. Demolition and remodeling.
16. Disposition of salvaged equipment and material.
17. Cleaning.
B. Related Sections:
1.2 SUBMITTALS
B. Submittal Schedule:
1. Provide the indicated quantity. Unless otherwise stated, Provide four originals and 1 PDF
version. The Government will retain three copies and the pdf file.
2. Submittal action by reviewer: Review each submittal, mark to indicate action taken, and
return.
1. Coordination Drawings.
2. Access panels.
1.3 GENERAL
A. Coordinate with other trades regarding the location and size of pipes, equipment, fixtures,
conduit, ducts, openings, switches, outlets, etc., so that there may be no interference between
the installation or the progress of the work of any Contractor or subcontractor on the Project.
B. The Mechanical and Electrical Drawings are diagrammatic. Follow as closely as actual
construction of the building and the work of other trades will permit. Where the Contractor
provided Shop Drawings approved by the Contracting Officer; follow the Shop Drawings.
Formally advise the Contracting Officer's Representative of any required changes from the
approved Shop Drawings, and record variances in Record Drawings.
C. The Contracting Officers Representative may change the location of any equipment 5-feet and
any piping, ductwork, conduit, etc., up to 10-feet in any direction without incurring extra charge
from the Contractor, provided such changes occur before installation.
D. Unless specified otherwise, furnish and install each item of equipment or material complete with
all necessary fittings, supports, trim, piping (supply, discharge, and drain), valves, switches,
relays, disconnects, cable, cords, conduit, overcurrent and overload protection, interfaces or
contacts, insulation, connection to power supply or source pipe, etc., as required for a complete
and operating installation in accordance with applicable codes and regulations.
E. Install all equipment and material according to the manufacturer's written instruction unless
otherwise specified.
A. Review the Architectural, Civil, Structural, Demolition, and any special Drawings to ensure the
inclusion of mechanical, electrical, and plumbing included in those drawings but omitted in the
Mechanical, Electrical, and Plumbing Drawings. Distribute such information to the appropriate
subcontractor(s) for inclusion in the Work.
B. Carefully verify and coordinate the location and level of all pipes, ducts, etc. Run preliminary
levels and coordinate with all other contractors to avoid conflicts in other locations.
C. Plumbing lines below plumbing fixtures and electrical conduits above or below electric
switchgear and panels have precedence over ductwork or heating mains. Do not install piping
or ductwork directly over, under or within code required frontal clearances of the electrical
equipment.
D. In spaces with high concentrations of inter-related equipment, piping, conduit, and ductwork
(spaces like Mechanical Rooms), provide coordination drawings clearly depicting the layout
(both plan and elevation, or perspective). Clearly define in advance of construction the
A. Where laws require, obtain written approval of systems (such as fire alarm, sprinklers) from
proper authorities before ordering equipment.
B. Supplementing the requirements of the General Conditions for compliance with laws and
ordinances, meet or exceed the requirements of the following:
A. Be responsible for the operation, maintenance, and safety of all equipment furnished, make all
necessary repairs, and do all necessary maintenance required to maintain the equipment in first
class condition until acceptance by the government.
B. Unless otherwise stated in this or other Specifications, where other contractors operate such
equipment, the other Contractor is solely responsible for the operation and safety of such
equipment.
1. Lubrication.
2. Adjustments.
3. Filter replacements.
4. Chemical treatment.
A. Furnish and install all conduit, wiring, disconnects, starters, thermal overload heaters, holding
coils, remote push buttons stations, "hand-off-auto," multi-speed switches, and pilot lights for all
electrically operated mechanical equipment, including the final connections for ready operation,
as specified and shown on the Drawings.
B. Where motor starters come as an integral part of the equipment, comply with the Contract
Documents including, but not limited to, overload protection on all phases. Install "hand-auto-
off" switches on all heating, ventilating, air conditioning and temperature control starters.
D. Furnish and install all required control and interlock wiring for all automatic control devices,
alarms, accessories, etc. Install on the holding coils of the starters or in the grounded load side
of TT switches unless otherwise specifically shown on the Electrical Drawings or specified
elsewhere.
E. Perform all electrical work in accordance with the Contract Documents. Install control wiring at
120 volt or less. Install all control wiring in conduit.
F. Consult with the electrical subcontractors before ordering or installing equipment. Coordinate
the motor type, voltage, and sizes with starter type, voltage and sizes, holding coil voltage,
thermal overload capacities, interlocks, etc. Each trade is equally responsible to ensure that the
equipment installed is of proper size and type.
G. Electrical subcontractor(s) shall consult with all other contractors furnishing motors that require
starters by the electrical subcontractor(s) to verify the exact type of starter required (e.g., part
winding, across the line, two speed, etc.) for each motor before ordering starters.
H. After the electrical subcontractor(s) completes the wiring, have each Contractor inspect the
wiring before operating their respective motors. The Contractor who furnished the motor is
completely responsible for the motors protection during the warranty period, including initial
startup of each motor, unless specifically shown otherwise in the Contract Documents.
1.8 GROUNDING
1. Ground all electrically powered equipment per electrical specifications and NFPA 70.
See specifically Sections 250-1, 42, 43, 44, 50, 70, and 90.
2. Non-electrical powered roof-mounted equipment such as roof hoods, chimneys, vents,
etc.: Ground as required by NFPA 70.
A. Where control valves, shut-off valves, drip traps, air vents, heating coils, pull boxes, or other
mechanical or electrical equipment are above inaccessible furred ceilings or back of masonry or
furred walls, provide access panels. The Drawings indicate the location of many, but not
necessarily all locations requiring access panels.
B. Size access panels of sufficient size for adequate servicing, adjustment, removal, and
replacement of concealed equipment through the opening provided. Size panels as shown on
the Drawings. Size panels not dimensioned a minimum of 16 inches by 24 inches in walls and
24 inches by 24 inches in ceilings.
D. Division 08 Section Access Doors and Frames (if applicable) specify panels.
1. Install Panels:
Bilco Milcor Karp
Drywall B DW 214P
Masonry C M 214M
Acoustical tile D AT 210
Plaster A K 214P
A. Submit all Mechanical, Electrical, and Plumbing operation and maintenance (O&M) manuals
with the initial submittals. Prior to completion of the Contract, provide inserts for the O&M
manuals containing testing documentation related to the performance testing for each piece of
equipment tested.
A. Each Contractor performs all excavation, sheathing, bracing, and backfill required for the
installation of his respective work.
B. Bed piping, conduit, etc., firmly and continuously on undisturbed earth (or sand or pea gravel
where specified or required). Where piping has bells, excavate deeper at same.
C. Where the excavation is in rock, ashes, cinders, refuse or other unsuitable materials, make the
trench 6 inches deeper and 12 inches wider than required for the piping and backfill with sand
or pea gravel 6 inches deep. In these areas, provide 6 inches of sand or pea gravel backfill
around the entire perimeter of pipe, conduit, etc. The intent is to have a minimum of 6 inches of
the appropriate fill below, on both sides, and atop the pipe, conduit, etc.
D. Maintain trenches and excavations free of standing water. Do not backfill trench until pressure
tests are complete, joints and pipe are watertight and the installation inspected. Backfill
trenches in 6-inch layers. Compact by tamping and puddling. Do not install frozen backfill
material.
E. Place backfill for the first 12 inches over piping, etc., by hand and carefully tamp.
F. Use sand or pea gravel fill for trench backfill under floors, parking areas, streets, walks, drives,
etc. Backfill over excavation with sand or pea gravel in 8-inch layers, dampen (do not soak) and
mechanically tamp to 95 percent minimum of maximum density per ASTM D 1557-78. Where
G. Surplus earth is acceptable for backfill in yards and seeded areas of the Project only upon
approval. The backfill cannot contain cinders, ashes, wood, large rocks, concrete, or debris.
Promptly remove (from the site) surplus excavation material not needed for backfill or elsewhere
on the site.
H. Provide adequate barricades, construction signs, torches, red lanterns, guards, etc., as required
during the progress of the excavation, installation, and backfill work. Observe all applicable
regulations respecting safety provisions, sheathing, and barricades.
I. For excavations made through streets, lawns, sidewalks, curbs, parking areas or other finished
surfaces, replace surfaces with material to match existing surfaces as approved by proper
authorities, including reinforced steel, where required. Neatly perform all cuts with saws, etc.
J. Protect utilities, trees, shrubbery, fences, poles, sidewalks, curbs and all other property and
surface structures from damage. Restore all disturbed by construction.
K. Before beginning excavation work, contact utility companies or, if applicable, responsible host
installation shops and request they locate and stake buried piping, wiring, etc. Expose such
piping, wiring, etc., by hand excavation prior to the use of power equipment.
L. The minimum cover over buried water pipe is frost depth plus 12 inches.
1.12 PAINTING
A. Clean, prepare, and paint the following with rust inhibitor followed by enamel paint at the time of
fabrication to stop rusting, whether exposed or concealed, insulated or un-insulated:
B. Paint all surfaces visible through grilles of fin tube radiation, cabinet unit heaters, etc., with flat
black paint.
A. Reduce the number of exposed screws, bolts, etc., used in the occupied areas of the building to
a minimum.
B. Where screws, bolts, etc. is unavoidable, provide a flat-span vandal proof type or Allen wrench
type.
A. Furnish and install suitable covering and protection for all equipment, devices, and materials,
etc., stored or set-in-place on the Project.
B. Prevent damage from mortar, plaster, paint, or other construction procedures or debris to
coverings.
C. A 6 mil polyethylene covering securely attached is acceptable in most cases. In cases where
daily temperature fluctuations will cause condensation inside the wrappings, provide a lamp or
other heat source to prevent formation of corrosion on controls, contacts, etc.
A. Arrange work to minimize the period of interruption or outages in the various services.
1. No extra payment is due if it is necessary to do this work after normal business hours on
premium time to minimize inconvenience to the occupants.
2. No less than 21 days before interruption of any service, notify the Contracting Office of
such necessity, including the extent of the work required during the outage, the probable
length of time required for that phase of the work, and the desired time at which the
outage will begin.
3. The Contracting Officer dictates the beginning time and other regulations governing each
particular outage to minimize inconveniences to the occupants.
A. Remove existing equipment and materials pertaining to this Contract as specified and as
required to prepare for the new work of all contracts.
C. Report to the Contracting Officer's Representative; any existing receptacles, light fixtures,
switches, panels, mechanical, plumbing, etc., rendered inoperable in areas outside the
construction zone and caused by work under this Contract.
D. Cap all abandoned or terminated piping, conduit, etc., below floor, behind wall surfaces, above
ceiling, etc., as required to completely conceal before new work is complete. Properly caulk,
seal, and provide an appropriate and appropriately sized pre-manufactured cap, escutcheon, or
faceplate to penetrations through walls, ceilings, and floors.
E. Most mechanical and electrical remodeling work is shown on the Mechanical and Electrical
Drawings. Carefully study all Drawings (all contracts) for "demolition" and "remodeling" work in
the existing building and field check to verify locations where such is underway to determine the
exact extent of work required.
F. The electrical subcontractor(s) shall test all new and existing electrical panels for new work and
verify their adequacy before and after connecting new loads. Report any inadequacies
immediately.
G. See Division 21 Section Fire-Suppression Sprinkler Systems, Division 22 Section Hangers and
Supports for Plumbing Piping and Equipment, Division 23 Section Hangers and Supports for
HVAC Piping and Equipment, and Division 26 Section Common Work Results for Electrical for
additional requirements.
H. NOTE! IMPORTANT! Do not remove existing equipment, systems, or etc. scheduled for
replacement by new equipment, systems, etc. from service until the installation and make ready
of the new equipment, materials, systems, etc. is complete. Provide temporary feeds to the
existing devices so they remain in service while GC is performing new work. Deviation from this
requirement requires specific written approval.
A. Where the Contract Documents specify removal of existing materials or equipment from service,
unless otherwise noted as items to be retained by the government, take possession and remove
them from the Project site promptly, except as specified below or unless otherwise noted in the
Contract Documents.
B. Prior to disposal of commissary operational equipment, fill out the appropriate form, provided by
the commissary store director (CSD), including, but not limited to a list of the itemized
equipment with name, model #, part number, and value. Return the completed form to the
Contracting Officer Representative with a copy to the CSD.
C. Coordinate removal of old salvageable equipment with the CSD prior to removal. Failure to do
so might result in GC compensating the government for lost sales due to premature equipment
removal.
A. Keep the premises free from accumulations of waste materials or rubbish caused by contractor
operations. At completion of each days work, remove rubbish from the construction area. At
the completion of the Project, remove all rubbish, tools, scaffolding, surplus materials, etc.
B. At completion, clean all surfaces of all paint, plaster, mortar, stains, paper labels, stickers, dust,
grime, etc. Do not mar or damage surfaces while cleaning.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating and reporting construction operations
on Project Web Site.
B. Related Sections:
A. General: The Government will provide the Contractor access to a web based application
"FACTSdocs," which will be utilized in submitting, transmitting, reporting, and uploading project
documents and data as indicated in the Contract Documents. The project management
software will be accessible to the project team members designated by the Contractor and the
Government. The Government will provide training in the use of this project management
software to the designated project team.
B. Manage forms, submissions, and correspondence as set forth below to assist the Government
in its monitoring and administration of this Contract. Use this system to record, maintain, and
submit information throughout the contract period. This joint Government-Contractor use will
facilitate electronic exchange of information and overall management of the Contract. This
approach provides the means for the Contractor to input, track, and electronically submit and or
share information with the Government in the following areas:
1. Administration.
2. Finances.
3. Requests for information (Project Website).
4. Price proposals and background data.
5. Quality control.
6. Submittal monitoring (Project Website).
7. Transmittals (Project Website).
8. Scheduling.
9. Import/export of data.
C. The primary function of the project management software is to ensure timely processing and
approval of all documentation in coordination with the project schedule. The Contractor shall
use the "FACTSdocs" software to complete, submit, update and upload the following data.
Request for Information (RFIs), Daily Construction Quality Control and Contractor Production
Reports Submittals, Transmittals, Weekly, Schedules to include Preliminary, Baseline,
Progress, Weekly Short Interval, Phasing Plans, Submittal Register, Project Register, Test
Reports, QCM Meeting Minutes, Safety Meeting Minutes and all other documentation and
correspondence specified in the Contract Documents and as deemed necessary by the
Government.
D. The Government will require the following naming convention format be used for all files
uploaded: Project Name-YY-MO-DD-File Name and/or description. Example: Keesler 08-06-16
Submittal 001 Quality Control Plan.
E. Project RFIs: The Contractor shall enter and transmit all Requests for Information (RFIs)
through the Project Management software. The Government will then answer the RFIs through
the Project Management software only. The project team will be able to print record copies of
the RFIs from the Project Management software.
F. Project Submittals: The Contractor shall enter submittals into the FACTSdocs software. Copies
of the product data and Shop Drawings shall be hand delivered to the Technical Inspector as
required and entered and/or uploaded into the project management software as a PDF file
and/or native format as required and/or indicated in this document.
G. Daily Quality Control Reports and Daily Contractor Production Reports: The Contractor shall
submit these reports daily into the Project Management software and sign them electronically
The Technical Inspector will then add any comments and sign electronically. The daily reports
may be printed as separate files or in "Log Format" as a report for use by the "Project Team."
H. Application for Payment: In addition to submittal requirements and in accordance with the
Contract Documents, the Contractor shall enter and/or upload all documents as listed in
Division 01 Section Contract Modification Procedures for progress payment, and final payment
and as deemed necessary by the Government in PDF format into the Project Management
software.
I. Transmittals: The Contractor shall log the transmittal of all documentation and correspondence
to the Government using the Project Management software. Likewise, the Government will log
the transmittal of all correspondence and documentation to the Contractor into the Project
Management software.
J. Weekly Progress Meeting Minutes: The Technical Inspector will chair the Weekly Progress
Meeting and will upload the meeting minutes in the Project Management Software where they
can be viewed / printed by the project team.
K. Quality Control and Safety Meeting Minutes: In accordance with the Contract Documents, the
Contractor shall enter and/or unload Quality Control and Safety Meeting Minutes into the Project
Management software.
N. Phasing Plans and Phasing Schedules: In addition to submittal requirements and in accordance
with the Contract Documents, the Contractor shall upload Phasing Plans, Schedules, and
Coordination Drawings into the Project Management software in both PDF and their native
formats.
P. Test Reports, Rework Logs and Punchlists: In addition to submittal requirements and in
accordance with the Contract Documents, the Contractor shall enter and/or upload all required
test reports, outstanding rework items, and Punchlists into the Project Management software.
R. Training: The Government shall provide training on use of the Project Management software to
the entire project team as soon as practical and or the construction trailers are in place and a
broadband internet connection is established. The FACTSdocs Administrator offers training via
web and teleconference formats for the convenience of the project team members. Scheduling
of these sessions should occur at the pre-performance conference. Initial training sessions may
be performed onsite by a competent person. The FACTSdocs Administrator will provide
additional sessions and/or follow-up training and/or training for any team member unable to
attend the onsite session via teleconference, webex, and or webinar style meeting. The
Contractor must provide the following information to the Government for each person requesting
access to the FACTSdocs software. Employee Name, Company they Represent, Contact
Phone Number, and Company Email Address.
S. Printing: All components-RFIs, submittals, daily quality control reports, transmittals, weekly
meeting minutes, modification information, project logs etc., shall be available in print through
the FACTSdocs software.
T. There is no separate payment or line item for establishing and maintaining these requirements.
Include all associated costs within the Contract pricing for the Work.
A. For ease and speed of communications, both the Government and Contractor shall exchange
correspondence and other documents in electronic format. As required by the Contracting
Officer, the Contractor shall provide correspondence, pay requests, requests for information,
and other documents comprising the official contract record in paper format, with original
signatures and dates. Paper documents shall govern, in the event of discrepancy with the
B. Format and File Naming Convention for Electronic Files: The government requires use of the
following file naming convention for all electronic file uploads. Project Name-Date-File Name-
version.
C. Start file name with abbreviated job name. For example, abbreviate Ord Military Community to
"Ord," abbreviate Dyess AFB to Dyess, and Camp Pendleton MCB to Pendleton. Do not use
special characters in the filename (e.g. ! @ # $ % ^ & *) . Follow the name with the date YY-
MM-DD. Always use two digits. Always use one space between the name and the date. A
good example is as follows 08-08-13. Follow the date with a brief description such as this
example, "Bakery-Deli Floor Tile."
D. Use the following sequencing when uploading photos of the same subject: add a space then a
number such as 1, 2, or 3, etc. after the description. A good example is "West Point 08-05-12,
Produce 1.jpg" and "West Point 08-05-12 Produce 2.jpg". Always use one space between the
date and the description.
E. Submit all correspondence and document attachments in Adobe Acrobats - Portable Document
Format (PDF) and schedules in native formats as well as PDF.
G. Provide fillable PDF data blocks where appropriate on all forms and correspondence requiring
further action by the Government.
H. When specifically requested by the Contracting Officer, provide additional data files in native
formats, e.g. spreadsheet (Microsoft Excel (.xls)) and word processing (Microsoft Word (.doc))
files.
I. Identification: Identify all Contractor correspondence to the Government with a serial number.
Prefix correspondence initiated by the Contractor's site office separately from that initiated by
the Contractors home office. Start serial numbering format from 0001.
A. The FACTSdocs software shall be available during all normal working hours in all CONUS time
zones. Expect only minimum downtime of the FACTSdocs software for maintenance and or
repairs.
B. FACTSdocs Software Maintenance: Performance of all periodic maintenance shall occur during
non- working hours for the Project.
C. The name and contact information of the FACTSdocs Administrator will be provided by the
Government at the pre-performance conference. This person will issue passwords and access
rights to all Project participants, resolve site maintenance issues, and act as primary point of
contact for the duration of the Project. This person shall be available to respond to technical or
functional questions or issues with the site operations during all normal business hours or a
minimum of 40 hours per week Mondays through Fridays.
E. The Project Website shall be accessible via the internet by all Project members.
F. The Project data maintained by the FACTSdocs software shall be accessible to the Government
for a period of five years after the Date of Beneficial Occupancy (BOD).
G. The Government will determine Access to specific data fields and reports in the FACTSdocs
software.
A. Whenever possible the Contractor is to provide all electronic file submissions in Adobe Acrobat
.PDF format and unless otherwise specified only .PDF format.
1. Where electronic files are required to be delivered on data disk use the following:
minimum 750 MB CR-R capable of running Microsoft Windows XP or newer.
Alternatively, DVD-ROMs may be used. As an option 210MB CD-R medium may be
used for small files. Ensure they conform to industry standards used in the United States.
Provide all data in English.
B. Disk or CD/DVD-ROM Labels: Affix a permanent exterior label to each diskette and CD/DVD-
ROM submitted. Indicate in English the file name(s), full Contract number, Project name, Project
location, data date, name and telephone number of person responsible for the data.
1.6 IMPLEMENTATION
A. Contractor shall use electronic format as described in the preceding paragraphs. Contractor
shall ensure that sufficient resources are available to maintain supporting data and databases.
END OF SECTION
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
B. Submittal List:
1.3 DEFINITIONS
A. Non-excusable Delay: Any delay caused by events within the control of the Contractor.
B. Excusable Delay: Any delay beyond the control of the Contractor or Government, caused by
events such as strikes, acts of God, unusually severe weather, fires, floods, acts of
Government, etc.
C. Critical (Prejudicial) Delay: a delay to any activity that impacts the project completion date (a
delay to the critical path).
D. Non-Critical (Non-prejudicial) Delay: a delay to any activity that does not exceed the available
float time, and thus, does not impact the project completion date (a delay to non-critical work).
F. Concurrent Delay: Two or more delays that occur simultaneously or overlap in some way.
A. All schedules provided for herein shall be based on the Contract Time and shall show Beneficial
Occupancy within the Contract Time, measured in calendar days after the effective date of the
Notice to Proceed.
B. Furnish such manpower, materials, facilities, and equipment and work hours, including night
shifts, overtime operations, to include Sundays and holidays as necessary to ensure completion
of the Work in accordance with the approved Project Schedule. If the Contractor through non-
excusable delay, misses a scheduled milestone by 14 days, a critical path activity start or
completion date, or forecasts a delay to the overall project, the Contracting Officer may require
the Contractor to take the following recovery actions:
4. Submit a revised Project Schedule demonstrating the Contractors proposed plan to make
up the lag in schedule progress and to ensure completion of work within the Contract
time. Refer to paragraph 1.7N.
A. Submit within 20 calendar days from the Notice to Proceed a preliminary computer generated
network defining the Contractor's planned operations during the first 120 calendar days.
Indicate the general approach for the balance of the project. Include cost of activities expected
to be complete or partially complete before submission and approval of the project schedule.
B. The Government will provide the Contractor with a Primavera or a Suretrak schedule template
with all default program settings, codes, etc. Use the approved preliminary schedule for
payment purposes not to exceed (120) calendar days.
A. Occupancy Requirements:
1. The commissary will remain in operation throughout the duration of this Contract.
2. Cooperate with the Contracting Officer in phasing and coordinating the work to minimize
disruptions and interference with commissary daily operations.
B. Scheduling:
1. Submit a detailed schedule of work in accordance with this Section that conform to the
priority and sequence of work shown on the Construction Phasing Plan indicated in the
Contract Documents. Notify the Contracting Officer 14 days in advance of anticipated
changes in the phasing plan or work schedule to permit the Contracting Officers
consideration of approval and for adjustment of store operations without adversely
affecting the ability of the commissary to function as necessary. Obtain written notice to
proceed before commencing phase changes or work that affects store operations.
C. Government Phasing Plan: The Government phasing plan is a floor plan of the store that
shows areas the Contractor will be allowed to have at any one time. Combined with the Project
Schedule, the Government can view what part of the store is being worked on at any given time.
By definition, the Phasing Plan is not the same as the Project Schedule. The Government
Phasing Plan indicated in the documents is a minimum guideline for developing detail in the
Contractor's Project Schedule required by this Section. Any proposed change to the
Government Phasing Plan must be approved by the Government. The Government Phasing
Plan is intended to explain a potential phasing sequence. Some requirements must be adhered
to for practical, operational, safety, or other reasons.
D. Contractor's Phasing Plan: The Contractor will develop a revised phasing plan (if it deviates
from the Government phasing plan) from information gathered in a formal meeting, scheduled
by the Contractor within 45 days from Notice to Proceed. Mandatory attendees are the Store
Director (or authorized representative), the DeCA Project Manager, the Contracting Officer, the
Governments Designated Inspector, key management of the Contractor, major Sub-
Contractors and Suppliers. Submit the revised phasing plan to the Contracting Officer for
approval at least 10 days prior to the meeting. Do not proceed onto future phases until the
Contracting Officer approves the revised phasing plan. Once approved, the revised phasing
plan will be the contractual 'Phasing Plan'. Use of the approved Phasing Plan in the
Contractor's Project Schedule is required.
1. The Government Phasing Plan does not address all of the situations encountered in the
construction process, nor does it address the Contractor's specific capabilities, means, or
methods. It generally addresses Commissary operations and is to serve as a guidance
document and as a basis for the Contractor to develop a detailed Phasing Plan. In
developing the detailed Phasing Plan, prioritize Commissary operations as implied by the
Government Phasing Plan. The Contractor shall take into account his and his
E. Phase Turnover and conditions for proceeding to subsequent Phases: Comply with Division 01
Section Closeout Procedures.
F. Subsequent revisions to the Phasing Plan: If the Contractor deems revision to the Phasing plan
to be prudent, the Contractor shall request permission from the Contracting Officer to revise it
and the make the corresponding changes to the Project Schedule. Prior to submission for
approval, concurrence for the changes shall be obtained from the Governments Designated
Inspector and the Store Director. Only after gaining the Contracting Officer's approval shall the
Contractor proceed with instituting the revised Phasing Plan and Project Schedule.
1. Work areas inside the commissary are normally available during hours the commissary
closes to customers. Note that commissary operations personnel regularly work hours
over and above those hours open to customers. Coordinate access and request
approval from the Contracting Officer seven days in advance of the need to schedule
after hours work.
2. Perform some work tasks during the commissary's normally closed hours. Potential
tasks required for performance during those hours include, but are not limited to,
painting, tasks involving disconnecting or rerouting electrical power, some demolition
items, items of work which create excessive noise or generate fumes which irritate the
customers, commissary employees, or put them at risk. Closely coordinate with the
Contracting Officer, the Commissary Store Director and Base Security to identify these
tasks and schedule them.
3. Schedule construction inside the commissary so interference to daily operations is
minimal. Restrict operations that create dust, noise, and fumes inside an open-for-
business commissary to its normally closed hours.
4. It is the intent of the Contract that the commissary does not close any days other than
those it would normally. However, should the Contractor identify accomplishment of a
task in a time period not to exceed 48 hours, and should this result in a benefit to the
commissary in its operations, a one day closing is an option on either side of a normally
closed day. The Contracting Officer is under no obligation to grant such a closing, but
may consider if it would result in an enhancement to the overall project. Provide a
minimum 30-day notice to the Contracting Officer and receive written notice to proceed
before commencing work on the premise of a closed store.
5. Maintain utilities to all adjacent facilities at all times except as required during scheduled
change over periods. Schedule outages and interruptions with, and obtain written
approvals from, the Contracting Officer.
6. Coordinate the installation of the mechanical, fire detection and suppression, and
electrical systems to maintain the existing building at its current levels while the new
systems and new areas become on line.
A. Contract Time: Warrant and represent that the Work shall be complete within the Contract
Time. Perform all work in an orderly and closely coordinated sequence and in conformance
with the Contract Milestones and the Project Schedule. The Contract Time includes allowances
B. Effect of Schedules. Acknowledge that no Progress Schedule or any other update of any
schedule (whether accepted by the Contracting Officer or not) shall extend the Contract Time,
adjust the Contract Milestones or modify the Project Schedule unless and until such change is
approved by the Contracting Officer in a written Contract Modification. If the Contracting Officer
determines that the Contractor is not entitled to an extension of Contract Time or an adjustment
of the Contract Milestones, comply with the then current Contract Milestones and achieve
Beneficial Occupancy within the Contract Time. Take such action as necessary to bring the
general progress of the Work into compliance with the Project Schedule. Bear entirely the cost
and expense of such overtime, or any additional measures, including any costs or damages
incurred by the Government; such as the Governments Designated Inspector, or Government
Contractors.
C. General Format:
1. Base schedules on the critical path method using the Precedence Diagram Method
format ("PDM").
a. For Contracts Greater Than $7,500,000 in Value: Use Primavera Project Planner
(P3) Software, Version 3.01 or later for Windows Operating Systems.
b. For Contracts $7,500,000 or Lower in Value: Use P3 or Suretrak Project Manager
(current Version) for Windows Operating Systems.
2. Use the schedule template provided, including all default program settings, codes,
calendars, etc. during all Project Schedule[/Phasing Plan] development.
3. The schedule is a requirement to assure adequate planning and execution of the work
and to assist the Government in appraising the reasonableness of the schedule and
evaluating progress of the work both before and during construction.
4. Schedule activity durations to allow for normal weather conditions such as precipitation,
high or low temperature, wind, etc. Any activity duration, potentially impacted by normally
anticipated weather shall include an adjustment for the anticipated weather effect. The
Contractor shall anticipate the weather effect by referring to the governments projected
number of days the Contractor will be affected by weather delays. The projected average
number non-work weather delays for <insert specific installation location here>,
based on the National Oceanic and Atmospheric Association's (NOAA) historical monthly
averages for the NOAA location for this site, is <insert average number of historical
non-work weather days based on NOAA Station closest to the project site -
typically the military installations flight-line>. Using this data, the Contractor will
reflect the number of anticipated weather delays allocated to an activity in the activity's
calendar. A lost workday caused by weather, is defined as a day in which the
Contractor's workforce cannot work at least 50 percent of the day on the impacted
activity(s) because of weather. The Contractor shall immediately notify the Contracting
Officer when a lost day has occurred due to weather and will record on the Daily Reports
the occurrence of the weather and the resultant impact to the normally scheduled work. If
the number of actual lost workdays caused by weather exceeds the number of days
anticipated, the Contracting Officer will convert any qualifying lost workdays to calendar
days, giving full consideration for equivalent fair weather workdays and issue a
modification in accordance with the Contract clauses.
a. Each electronic file shall contain the Project Schedule (initial submittal), or the
latest updated Progress Schedule (subsequent monthly submittals).
b. Properly label each electronic file identifying the project, Contractor's name,
filename, and the data date.
E. Contractors Scheduling Representative: Before starting the Work, designate, in writing to the
Contracting Officer, an individual, with previous experience of at least five (5) years creating and
reviewing construction schedules, as the Contractors Scheduling Representative. This
representative shall monitor and maintain the Project Schedule and scheduling as defined in
this Section and shall be able to revise, update, and recommend logic revisions to the Project
Schedule as necessary for closely monitoring progress of the work. Include in the written
designation the name, qualifications and experience of the individual and request the
Government's acceptance, which will not be unreasonably withheld. The Scheduling
Representative shall be responsible for the coordination and implementation of all Contractor
activities and responsibilities relating to the Project Schedule and scheduling as set forth in the
Contract Documents.
F. Proposed Baseline Project Schedule: Within ninety (90) calendar days after the effective date
of the Notice to Proceed, provide the Contracting Officer with a schedule to cover the entire
Contract Time (Project Schedule). Prepare schedule in detail and format required by the items
set forth below. The Project Schedule shall show the order, interdependence of activities, and
the sequence of the plan to accomplish the work.
1. Review of Project Schedule: All submitted Schedule(s) shall be subject to the review by
the Contracting Officer, and when accepted by the Contracting Officer, shall be identified
as the Baseline Project Schedule. Allow the Contracting Officer fourteen (14) calendar
days for review of each submittal. Within twenty-one (21) calendar days of the Project
Schedule submittal, the Contracting Officer will conduct a teleconference with the DeCA
PM, Governments Designated Inspector, Government Scheduler, and Contractor to
discuss any review comments issued. The Government will provide an advance set of
comments to the Contractor three calendar days prior to the meeting. The PCO will return
the disposition of the schedule to the Contractor on an AF Form 3000 one calendar day
prior to the teleconference. If the Project Schedule is approved as submitted, a
teleconference is not required.
2. By accepting the submitted Schedule(s) as the Baseline Project Schedule, the
Contracting Officer is not assuming any of the Contractor's responsibility for the timely
and orderly completion of the Work or the coordination of the performance of the
Contractor's Work or its subcontractors with that of other Contractors. Any adjustments
made in the Project Schedule necessitated by any error or inconsistency, or by reason of
the requirements for the orderly performance of the Work, shall be made and the Work
performed by the Contractor without additional compensation or extension of time.
3. The final proposed Project Schedule accepted by the Contracting Officer shall be
identified as the Project Schedule and shall be the Project Schedule used by the
Contractor and Government for monitoring progress of the work.
4. Clearly indicate any special sequencing, predetermined use of multiple shifts or overtime,
all costs of which deemed included in the Contract Sum. Unless otherwise indicated,
work hours shall be Monday through Friday, 8 hours per day (day shift). Schedule the
c. Government Activities: Show Government and other agency activities that could
impact progress. These activities include, but are not limited to: approvals,
inspections, utility tie-ins, Government Furnished Equipment (GFE)[, each phase
start and phase completion dates]. "Logically link" government activities to the
schedule.
d. Contract Milestones: In addition to any Contract Milestones set out in the Bid
Documents, indicate on the Project Schedule no fewer than three and no more
than eighteen Contract Milestones for the completion of various components of the
Work. The Contract Milestones shall be confirmed by Contract Modification and
cannot thereafter be changed except by Contract Modification.
e. Suggested Milestones:
1) HVAC start-up.
2) [Phase Start to include Sub-Phase start].
3) [Phase Completion to include Sub-Phase completion].
4) Telecommunications and IT systems installation.
5) POSM/Data installation [by phase].
6) Refrigeration 100 percent ready for inspection.
7) Security system complete.
8) Fire Alarm system complete.
9) Government Furnished Equipment (GFE).
5. Provide a coding system that clearly identifies (as a minimum) the following items per
each activity:
6. All construction activities in the Project Schedule shall be cost loaded. The assigned
dollar values for all activities shall cumulatively equal the total Contract Price and include
the costs for mobilization, bonds and insurance. General requirements, overhead and
profit, and other costs not attributable to specific activities shall be prorated throughout all
construction activities shown in the Project Schedule.
7. Tabular reports shall contain the following: All reports in this paragraph shall contain
activity identification, the original duration, remaining duration, percent completion,
activity description, early dates, late dates, total float, added or deleted activities, and
changes to logic and durations. An exception is the cost report which shall have the
activity identification, activity description, original duration, remaining duration, the
percent completion, values, total budget value, previous total value, this month value and
remaining values per each item. This cost report total shall be the contract amount
8. Graphic diagrams of the following: All reports in this paragraph shall contain an activity
identification, the original duration, remaining duration, percent completion, activity
description, early dates, late dates and total float for each activity.
a. A logic diagram showing a continuous activity flow from left to right (11 inches by
17 inches and 30 inches by 42 inches). Show activity numbers, description,
duration, and total float on the diagram. Graphically and clearly identify contract
milestones and critical path.
b. A short interval schedule (3-week look ahead) chart as described in paragraph 1.8.
G. Monthly Reports: Contractor shall submit monthly, those reports detailed in paragraphs F.6 and
1.8 with the exception of the logic diagrams. These diagrams shall be submitted for approval
when major logic changes are made to the Project Schedule or when the Contracting Officer
deems necessary.
H. Revisions to Project Schedule: If Contractor requires major changes to the Project Schedule,
by no fault of the Government, Contracting Officer or Governments Designated Inspector, the
Contractor shall submit those changes for review and acceptance by the Contracting Officer,
and shall follow the procedures outlined in the Articles above, at no cost to the Government.
Contractor shall allow the Contracting Officer fourteen (14) calendar days for review. No
changes to the Project Schedule or out-of-sequence work are allowed without a written
authorization from the Contracting Officer.
I. Progress Schedules: On the 25th of each month, the Governments Designated Inspector and
the Contractor shall inspect the work to determine percent complete for each activity in the
Project Schedule. Generate the monthly Progress Schedule from the current month's accepted
Project Schedule, in the retained logic mode, and shall show the actual progress of the Work
(through the end of the current month). Throughout the term of the Contract, deliver a monthly
Progress Schedule to the Contracting Officer on or before the 1st of the following month or as
otherwise required by Contracting Officer. Record progress for each activity by entering the
actual start and finish dates and, the percent complete for all activities worked for that period.
In the event that the Contracting Officer and Contractor cannot agree on the monthly update,
the Contracting Officer will direct the Contractor, at no cost to the Government, to update the
J. Set the software's calculation method so that percent complete will determine remaining
duration is not automatically calculated from the reported percent complete. All approved
Contract Modifications shall be incorporated into the monthly update of the Progress Schedule.
The latest accepted Progress Schedule shall become the current Project Schedule. Allow 5
calendar days for Government review of the Project Schedule Update. Sequentially number
each monthly Progress Schedule and date for identification, in the form and substance
requested by the Contracting Officer. The monthly Progress Schedule shall include all tabular
and graphic reports and electronic media indicated above.
K. Progress Payment: At the discretion of the Contracting Officer, payment may be withheld
without an approved Project Schedule. Use the Project Schedule to generate the monthly
payment application based on actual work installed (percent complete). Base progress and
earned value on work-in-place and project through the end of the month. Use this information to
generate a Progress Payment Application. Submit the payment application no later than the 1st
day of each month. Activities that do not have an approved budget line item are not payable.
L. Monthly Schedule Meetings: Cooperate with the Contracting Officer in all matters concerning
the Project and/or Progress Schedules, and attend a monthly schedule review meeting with the
Contracting Officer or Governments Designated Inspector. In the meeting describe on an
activity-by-activity basis the following:
1. All proposed revisions and adjustments to the Project Schedule reflecting the status of
the Project.
2. Actual start and actual finish dates for all activities in progress or completed, as
appropriate.
3. The estimated percent complete for each activity in progress.
4. All logic changes pertaining to Project Modification activities sequencing or durations, and
corrections to schedule logic to avoid out of sequence progress.
5. The purpose of this meeting is for evaluating the updated Progress Schedule and not for
modifying previously reviewed durations or percentages. Do not make any changes to
the schedule without a written acceptance by the Contracting Officer.
6. The monthly meeting described in this paragraph is in addition to the "weekly progress
meetings" described in Division 01 Section Administrative Requirements.
M. Changes:
1. When changes in the work are necessary, submit for review by the Government a fragnet
analysis along with a proposal for each individual change.
2. Illustrate in the fragnet how the Contractor proposes to incorporate the changed work and
the time impact of the change into the overall completion date.
3. Additionally, demonstrate in the fragnet the time impact (based on the forecast Notice to
Proceed date provided by the government and the status of construction at that point in
time) and the event time computation of all affected activities using the latest approved
Progress Schedule.
4. In cases where the Contractor does not submit a fragnet for a specific change or alleged
delay then it is mutually agreed that the particular change or alleged delay has no time
impact on the Contract completion date and no time extension is required.
5. In the event that the Contractor and the Contracting Officer cannot agree on the
extension or reduction of time for a particular change, the Contracting Officer will have
the option to provide suggested logic and/or duration times in all subsequent reports.
a. If the Contractor has any objections to the data furnished by Contracting Officer, so
advise the Contracting Officer, in writing, fully supporting the objections with an
alternate plan no later than 10 calendar days after receiving the information from
the Contracting Officer.
b. Use the data provided by the Contracting Officer until the alternate plan is
reviewed and accepted by the Contracting Officer.
c. If the Contractor does not submit an alternate plan in the stipulated time, the
Contracting Officer will deem that the Contractor has concurred with the
Contracting Officers suggested logic/duration time changes to the Project
Schedule.
6. The approved fragnet shall be the basis of time performance of the work.
7. Include only Contract Modifications approved by the Contracting Officer in the Project
Schedule submission.
8. The Monthly Progress Payment Narrative, as required in Division 01 Section Contract
Modification Procedures, shall specifically reference, on an activity-by-activity basis, all
changes made since the previous period and relate each change to documented,
approved Project Schedule changes.
N. Schedule Delays:
1. If the Contractor determines that it will not be able to perform the Work in accordance
with the Contract Milestones and achieve Beneficial Occupancy within the Contract Time,
and:
2. Promptly submit to the Contracting Officer a plan (no later than seven (7) calendar days
after such determination), including proposed adjustments to the Progress Schedule, if
any, showing how the Contractor plans.
a. to mitigate impact upon other portions of the Work and the Project
b. and how it plans to bring the Project back on the Project Schedule
3. If the Contracting Officer finds the proposed plan is not acceptable, submit a new plan. If
the actions taken by the Contractor on the second proposed plan are not satisfactory to
the Contracting Officer, take the actions set forth in paragraph 1.4.B without additional
costs to the Government, to make up the lag in schedule progress.
4. If the Contractor feels that it is necessary to revise its critical path logic in order to
achieve the Contract Milestones and Beneficial Occupancy within the Contract Time,
submit a revised recovery plan for approval prior to commencing Work on said activities.
5. Unapproved out-of-sequence Work in the critical path is not allowed. The Government
will not make payment for unapproved out-of sequence Work on the critical path. DO
NOT start work until such alternate plan is approved by the Contracting Officer.
6. The Contracting Officer has the right to immediately order the Contractor to finish
completion of late activities, and any activities which have been delayed by the late
activities, by whatever means necessary, without any additional cost to the Government.
Comply with the order.
O. Schedule Float: The Contractor and Contracting Officer agree that float available in the
schedule, at any time, is not for the exclusive use of either the Government or the Contractor.
Use of Zero Free Float and Zero Total Float constraints is not allowed. Negative float is not
allowed without a recovery plan to bring the project back to the current contract completion
date. Use of float suppression techniques, such as; preferential sequencing (arranging critical
path through activities more susceptible to Government caused delay), lag logic restraints, zero
total or free float constraints, extended activity times, or imposing constraint dates other than as
required by the contract, shall be cause for rejection of the project schedule or its updates. The
use of Resource Leveling (or similar software features) used for the purpose of artificially
adjusting activity durations to consume float and influence the critical path is expressly
prohibited.
P. Expedited Work: The Government may request the Contractor to work overtime to expedite the
completion of the Work or a portion of the Work at a time when the Contractor is otherwise in
conformance with the Contract Documents and the Project Schedule. If such a situation should
occur, a price for the expedited work shall be negotiated prior to commencement and covered in
a contract modification.
Q. Time Extensions: For consideration of a time extension, the following criteria must occur:
A. Short Interval Schedules: Submit Short Interval Scheduling (SIS) or 3-week look-a-head for
each Weekly Construction Meeting. Generate these reports using Primavera Filter, or the
Tabular Report function from the current approved Progress Schedule.
B. The interval is a three-week projection that includes the week submitted and the following two
weeks thereafter.
C. Provide sufficient detail to evaluate milestones and identify/tie into the current schedule. Detail
this schedule to include all activities scheduled for the 3-week period. The short interval
schedule shall reflect actual work planned for the three week time.
D. Submit in bar chart format on a daily scale, sorted by early start and responsibility, covering all
activity work for the following 3 weeks.
END OF SECTION
BACKGROUND
Executive Order 13514 Federal Leadership in Environmental, Energy, and Economic Performance,
signed October 5th 2009. This document contains numerous requirements on greenhouse gas and
energy reduction, water use efficiency, pollution prevention and waste reduction, sustainable acquisition,
electronic stewardship, and other sustainability aspects. EO 13514 builds on the requirements contained
in EO 13423 described below. EO 13514 makes mandatory the five Guiding Principles of the
memorandum of understanding for all new construction and major renovations and sets an aggressive
goal for applying these practices to our existing capital assets over the next decade.
In addition to meeting the requirements of the executive orders described above, design and administer
construction for all New and Add / Alt Projects to meet the requirements of LEED Silver with an initial
design target of 55 points. Do not register the Project through LEED. The design team shall submit to
DeCA a completed LEED scorecard during the early design phase of the project indicating the credits to
be pursued as part of the design process in addition to the required pre-requisites and minimum program
requirements (MPRs). At the end of the project the design team shall submit to DeCA a report showing
compliance with the targeted LEED credits.
IMPLEMENTATON PLANNING
DeCA facilities will implement EO 13423 and 13514 using the DeCA Design Criteria Handbook, as the
basis of all commissary designs. All current sustainable design requirements for compliance with the
executive orders reference above are available to all users on the DeCA Facilities website and can be
accessed at www.decafacilities.com.
DESIGN CRITERIA
with the above, Executive Orders 13514 and 13423 direct Federal Agencies to ensure that
new construction and major renovation of federal facilities comply with the Guiding Principles
for Federal Leadership in High Performance and Sustainable Buildings. These principles
require designers to incorporate the following goals during project design:
These principles are to be followed for the goals of reducing the total ownership cost of
facilities; improving the energy efficiency and water conservation; provide safe, healthy, and
productively built environments; and, to promote sustainable environmental stewardship. The
Executive Orders can be viewed at www.fedcenter.gov under the Program Area menu to the
left hand side of the screen.
B. As an Agency of the Department of Defense, DeCA fully recognizes the economic and
environmental benefits of sustainable design and construction practices. The Agency also
recognizes that certain objectives for the sustainable goals in commissary projects may be
harder to achieve than others. The designer of commissary facilities is to identify the
sustainable design features and requirements early in the design process so that these
features can be incorporated into the design at the lowest possible cost. As required by EO
13513 a 30% energy reduction over ASHRAE 90.1-2004 must be achieved in all new building
projects. LEED Silver Design requirements will require comparison with ASHRAE 90.1-2007
for energy savings results, since ASHRAE 90.1-2007 is more stringent on energy design
requirements, the energy reduction over ASHRAE 90.1-2007 may be less than 30%. Design
team will need to provide DeCA with predicted energy savings thresholds from an energy
model compared to both the ASHRAE 90.1-2004 and 2007 baselines for the building to
validate compliance.
C. Designers are to review the following Guiding Principles and incorporate them in the design.
These outlines are intended to provide an example guide in implementation of the goals of the
authority Executive Order 13423. Designers are requested to review these principles at
http://www.wbdg.org/sustainableEO/ .
D. Guiding Principles for Federal Leadership in High Performance and Sustainable Buildings.
The following outline issues are to be addressed during the design stages.
June 2011 01 33 29 2
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
GUIDING PRINCIPLES
FOR
FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND
SUSTAINABLE BUILDINGS
Federal Agencies are required to incorporate the Guiding Principles for New Construction and Major
Renovations into all new construction, major renovation, or repair and alternation of Federal
Buildings. This set of Guiding Principles is linked below, with additional links to technical guidance on
specific topics covered in the WBDG.
http://www.wbdg.org/references/fhpsb_new.php
June 2011 01 33 29 3
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
Application: Project development team will maintain the same senior management from the
beginning programming and charrette through completion of construction. The team will not only
comply with all relevant codes and laws, but will incorporate into the project the essence and
intensions of Executive Order 13423-Strengthening Federal Environmental, Energy, and
Transportation Management and Executive Order 13514-Federal Leadership in Environmental,
Energy, and Economic Performance. The team will develop and implement an overall strategic plan
to implement to the highest degree possible, the goals of these E.O.'s.
Suggested Steps:
1. Address and provide a strategic plan to establish performance goals early in the planning
and design stages
2. Develop and incorporate team strategies for the implementation of goals and define
areas of responsibility.
I.B - Commissioning
Reference: Appendix C - COMMISSIONING. The referenced source will be the guide for
completing this requirement.
June 2011 01 33 29 4
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
Heating, ventilating, air conditioning, and refrigeration (HVAC &R) systems (mechanical
and passive) and associated controls.
Lighting controls, including day lighting.
Domestic hot water systems.
Renewable energy systems (PV, wind, solar, etc.).
Application: A formal building commissioning program for commissary construction will provide
considerable benefits as stated above. DeCA has adopted a policy to require a formal building
commissioning process during design and construction. An independent commissioning authority will
be designated to lead the commissioning process. Appendix C provides guidance on how the
commissioning process must be structured.
Suggested Steps:
1. Designate a Facility Commissioning Authority to lead facility commissioning activities.
The commissioning agent must be independent of the designer or construction manager
and qualified to serve as the owners commissioning representative.
3. In conjunction with the architect-engineer and DeCA, the Commissioning Agent will
ensure that the Owners project requirements have been document and addressed in the
design documents.
4. Require the commissioning agent to coordinate with the architect-engineer designers and
DeCA on specific commissioning goals for sustainable design and energy conservation.
5. Incorporate a review of the buildings energy related systems into the commissioning
process.
6. Have the commissioning agent review and comment on the design documents and
design energy model.
7. Develop and coordinate a commissioning report after the commissioning activities have
been completed.
8. Plan for and schedule a Post Occupancy Survey to assess building performance with
O&M staff and operators within one year of final acceptance and develop a plan for
addressing lessons learned, operational issues and outstanding commissioning issues.
June 2011 01 33 29 5
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
Requirements: Reduce the proposed building performance rating compared to the baseline building
performance rating per ASHRAE/IESNA Standard 90.1-2007 (without amendments), for the total
energy consumption within and associated with the building project, as demonstrated by a whole
building project simulation using the Building Performance Rating Method in Appendix G of the
Standard.
All building energy loads associated with the project must be included in the energy simulation model.
Improvements to non-regulated loads must be documented as described below. Regulated energy
systems include HVAC (heating, cooling, fans, and pumps), service water heating, and general
interior lighting. Process loads for retail may include display lighting, refrigeration equipment, cooking
and food preparation, and other major support appliances. Merchandise for sale that is plugged in,
and small moveable appliances are not candidates for improved energy performance.
Appendix G of Standard 90.1-2007 requires that the energy analysis done for the Building
Performance Rating Method include ALL of the energy consumption within and associated with the
building project.
Must comply with the mandatory provisions (Sections 5.4, 6.4, 7.4, 8.4, 9.4, and 10.4) in
Standard 90.1-2007 (without amendments);
Must include all the energy consumption within and associated with the building project;
and
Must be compared against a baseline building that complies with Appendix G to Standard
90.1-2007 (without amendments).
For the purpose of this analysis, process energy is considered to include, but is not limited to, office
and general miscellaneous equipment, computers, elevators and escalators, kitchen cooking and
refrigeration, laundry washing and drying, lighting exempt from the lighting power allowance (e.g.
lighting integral to medical equipment) and other (e.g. waterfall pumps). Process energy does not
include any lighting (such as for the interior, parking garage, surface parking, faade, or building
grounds, except as noted above), nor any HVAC (such as for space heating, space cooling, fans,
pumps, toilet exhaust, parking garage ventilation, kitchen hood exhaust, etc.), nor any service water
heating for domestic or space heating purposes.
For Process Loads provide cut sheets or other documentation demonstrating budget and proposed
equipment. A clear baseline must be described and documented to compare to proposed
improvements in process load categories. The baseline and improvements must be documented in
the following ways:
Appliances & Equipment: For appliances and equipment, provide cut sheets of typical
budget and proposed equipment that indicates hourly energy use. Provide a
spreadsheet calculation estimating the daily use hours for each piece of equipment
listed. Use the total estimated energy use in the energy simulation model as a plug load.
Reduced use time (schedule change) is not a category of energy improvement in this
June 2011 01 33 29 6
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
credit. Energy star ratings and evaluations are a valid basis for performing this
calculation.
Display Lighting: For display lighting, the space by space method of determining allowed
lighting power under ASHRAE 90.1-2001 must be used to determine the appropriate
baseline for both the general building space and the display lighting. Section 9.3.1.2 of
ASHRAE 90.1-2001 describes the methodology for determining a baseline that includes
display lighting. Installed lighting in the proposed building, including display lighting is
compared to this baseline in the simulation.
Refrigeration: For hard-wired refrigeration loads, the impact of energy performance
improvements must be modeled with a simulation program specifically designed to
account for refrigeration equipment. For example, eQUEST has a refrigeration module
that can be used to simulate performance improvements in refrigeration equipment. An
energy simulation template for DeCA using the eQUEST Refrigeration Model is currently
being developed and will be available soon. Included with the template will be
spreadsheet tools that are designed to provide an easy means to transfer information
from design plans and specifications into a format for ease of inputting into eQUEST.
The template will include specific modeling guidelines for commissaries, including how to
determine infiltration loads through customer doors, DHW loads and sources for
determining appropriate utility rates to apply in the model.
Application: The intent of these MOU performance standards is to ensure that Commissaries
facilities are being designed to maximize energy performance of the building envelope and building
systems. It is within DeCAs best interest to ensure that facilities are being designed and constructed
to maximize energy performance. These objectives provide a good target of opportunity and some
results could be achieved without significantly impacting overall project costs above baseline. Other
factors to consider:
Passive solar features should also be considered for potential commissary application.
Not only can these features contribute to the overall reduction of energy use, but they
also can have an impact on customer sales. Studies have demonstrated a positive
contribution to sales from implementing these features. Use of solar light tubes in the
sales area and warehouse could offer a significant contribution to overall energy
reduction.
High efficiency HVAC systems, refrigeration equipment and various other process and
equipment loads and lighting will have the greatest incremental impact on overall energy
consumption in commissaries. The greatest amount of design effort should be devoted
to improving these systems. The refrigeration process loads are the expected to be the
biggest energy use in commissary stores. DeCA typically utilizes heat recovery and heat
rejection strategies, high efficiency motors, high efficiency ballasts and high efficiency
lamps in display cases to lower total energy use. Designers should coordinate with
equipment manufacturers to improve energy efficiency, particularly for volume build
applications.
The designer should look at all equipment and systems that use energy and identify
strategies to reduce energy use. Consider first cost verses life cycle cost, maintenance,
replacement costs, and any potential benefit or detriment to staff or customers when
selecting strategies. Design the building envelope and building systems to maximize
energy performance. Use a computer simulation model to assess the energy
performance and identify the most cost-effective energy efficiency measures. Quantify
June 2011 01 33 29 7
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
energy performance as compared to the baseline benchmark. The designer should use
historic utility bills from similar stores, generic retail energy use data, data from their local
utility, or computer modeling to assess typical and projected loads. Regardless of the
methodology used in setting the energy budget, the credit narrative should include a
description of the methodology used and assumptions made.
The U.S. Environmental Protection Agencys Energy Star Program is working to establish
retail energy benchmarks. Benchmark data is available for grocery stores. Beta testing is
underway to compile benchmark data for convenience stores and warehouses.
Designers should use Energy Star data when determining their energy budget. In the
absence of established retail benchmarks, the retailer-specific, relative energy savings
credit will meet the intent of increasing energy performance as well as generate retail
energy usage data.
DeCA commissaries are required under the Federal Energy Management Program
(FEMP) to provide energy reductions. Consistent with this guidance, DeCA has
established a goal to achieve an Energy Use Index (EUI) for commissaries of 137 by
2010 (137,000 BTU/SF/YR). Typical commissary facility project designs are currently
rated with a Design Energy Use (DEU) Index in the range of 150 to 200 (150,000 to
200,000 BTU/SF/YR). This is more than the required EUI goal, so additional
improvements will be required to meet the Guiding Principles goal of a 30% reduction for
new facilities and a 20% reduction for major renovations.
The following table describes average building and process loads for several categories of retail
types. This table provides a guideline as to the anticipated significance of process energy categories
in retail projects. (The data is assembled from several national studies and data provided by the
R
LEED -NC Retail Committee.)
Suggested Steps:
June 2011 01 33 29 8
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
3. Review and assess cost and benefits of identified cost saving opportunities.
Requirements
Develop and implement a Measurement and Verification plan consistent with Option D:
Calibrated Simulation (Savings Estimation Method 2), or Option B: ECM Isolation, as
specified in the International Performance Measurement & Verification Protocol (IPMVP)
Volume III: Concepts and Options for Determining Energy Savings in New Construction,
April, 2003.
OR
Develop and implement a Measurement and Verification plan consistent with Option C:
Whole Building, as specified in the International Performance Measurement &
Verification Protocol (IPMVP) Volume I: Concepts and Options for Determining Energy
and Water Savings, 2001.
The option selected shall be appropriate for the size and nature of the building.
The M&V period shall cover a period of no less than one year of post-construction
occupancy.
Application: DeCA provides for substantial metering and verification of energy consumption over
time through its refrigeration monitoring and alarm contracts. As an integral part of the facility
commissioning and post validation assessment surveys, DeCA can include provisions in these
contracted efforts to demonstrate thru measurement and verification that the objectives for reduced
building energy consumption over time have been achieved. Other factors to consider:
DeCAs current metering policy does not include sub-metering to identify discrete
elements of energy performance. In the early stages of the design, sub-metering needs
to be discussed and made part of the overall design appropriate to the scope of the
project.
June 2011 01 33 29 9
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
Sub-metering capabilities, their potential benefits and costs, need to be discussed during
the design process.
In interpreting the intent of this requirement, it may be assumed that DeCA would not
have to implement metering down to individual components. Instead metering would be
implemented at the aggregate component portion of load. In other words, load
components, such as refrigeration case load, sales area lighting, process energy loads,
exterior lighting and other key components would be each be measured in aggregate and
provide opportunity to assess load contribution and potential energy reduction strategies
for each component.
Suggested Steps:
II. D - Benchmarking
Requirements: Maximize water efficiency within buildings to reduce the burden on municipal water
supply and wastewater systems. Employ strategies that in aggregate result in 20% less water use
than the water use baseline for the building after meeting the Energy Policy Act of 2005 (EPACT 05)
Uniform Plumbing Code 2006 and International Plumbing Code 2006 (not including outdoor irrigation
for site landscaping). For equipment not addressed by EPACT 05 additional equipment performance
requirements may be proposed provided documentation supporting the proposed benchmark or
industry standard is submitted. The installation of water meters is encouraged to allow for the
June 2011 01 33 29 10
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
management of water use during occupancy. The use of harvested rainwater, treated wastewater,
and air conditioner condensate should also be considered and used where feasible for nonpotable
use and potable use where allowed.
Application: Commissary facilities are typically large consumers of potable water as a result of
patron and employee sanitation demands and water demands associated with food preparation,
processing and sanitation. DeCA has already established target guidelines to reduce water
consumption in new and existing facilities. There is a general trend in the food industry toward
reduction in the amount of food preparation and processing that occurs on-site in a retail grocery
facility. The trend is toward more centralized preparation and processing of food items such as
meats, produce and bakery products. Consequently, the process loads in commissaries will be
decreasing significantly over the next few years, thus reducing water demand. Preliminary design
considerations should examine the potential impact of these trends on store potable water needs and
how those needs might be further reduced. Other design considerations include:
As with many similar retailing operations, process water (water used to provide a product
or service) far outweighs the water used for toilets and hand sinks. Process water also
includes water used in cooling systems or any other equipment not directly regulated by
the Energy Policy Act of 2005 (which covers faucets, toilets, urinals and showerheads).
To address process water use, the water calculation spreadsheet template has been
expanded for retail projects to include commercial fixtures not covered by EPACT 2005.
In addition to specifying water efficient fixtures and appliances, consider reuse of grey-
water for non-potable applications such as toilet flushing, mechanical systems, cleaning,
plant irrigation (for plants that are for sale and not part of site landscaping), hosing of
dock or processing areas, or other applications that do not require potable water.
Specify only high-efficiency fixtures for plumbing consistent with DeCAs Design Criteria
Handbook Section 22 05 00. The fixtures reduce potable water intake and wastewater
generation.
Consider reuse of clean wastewater for flushing systems. Identify any potential health
risks and coordinate with Food Health Safety Office.
Treated water can be used for boiler and HVAC system make-up water.
A wide variety of fixtures for sinks, lavatories and hose valves are also available in high-
efficiency models. Specify only water-conserving fixtures, with electronic operational
sensors for hand sinks.
Specify high efficiency Ice Makers, pre rinse spray valves, and other processing
equipment consistent with water efficiency criteria, including EPACT 92.
Suggested Steps:
1. Review current water consumption records and identify water reduction goals.
2. Identify fixturing and equipment requirements and assess application of water reduction
methodologies to these fixtures and equipment.
3. Research and identify high-efficiency fixtures and equipment and document life cycle
cost features as part of design analysis.
June 2011 01 33 29 11
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
4. Identify installation and local code requirements regarding specification and use of low-
flow or dry fixtures, or reuse of storm-water or grey- water volumes.
5. Separate water consumption into domestic and process loads and calculate the energy
savings contribution of each. Extra reductions over and above those needed to receive
the credit may be applied to Innovation and Design credit.
Submittal: Provide appropriate documentation in design documents to substantiate that the design
meets the required reduction in potable water demand to satisfy Guiding Principle criteria. Include
appropriate documentation and drawings to verify use of high-efficiency fixtures, and provide a
spreadsheet to demonstrate a reduction in water demand by at least 20 percent, compared to
baseline conditions. Provide cut sheets and other manufacturers data to demonstrate high efficiency
equipment. For additional equipment for which no benchmark is provided in EPACT 05, provide the
following:
2. Benchmarking data that compares these flow rates with industry averages or the industry
standard for that particular equipment type (water research organization study, industry
audit data, etc.).
Requirements: Use high-efficiency irrigation technology OR use water collected on site that would
otherwise be released from the site, such as captured rain, or recycled water, or use water treated
and conveyed by a public agency specifically for non-potable uses, or use as a combination of water
from these sources to reduce potable water consumption for irrigation by 50% over conventional
means. The installation of water meters for locations with significant outdoor water use is
encouraged.
Application: Commissary landscape features are usually identified during the early design stages of
commissaries and integrated into the civil site design. DeCA encourages the use of natural
landscape materials in site design and minimizes the area requiring landscaping to key areas in the
front of the store. The use of natural materials and Xeriscape should make this credit achievable
under normal circumstances. If irrigation is provided, use high efficiency irrigation technology or use
water collected on the site that would otherwise be released. Other design considerations include:
Maximize the extent of surfaces excluding the building footprint with native or adaptive
vegetation areas.
The architect-engineers selection of landscape materials requires coordination with the
installation to assure selection of native materials.
Drip irrigation systems afford opportunities to dramatically reduce water consumption
over conventional means of irrigation.
June 2011 01 33 29 12
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
Consider integration of water collection and storage features into the landscape design.
If irrigation systems are used, use only high efficiency irrigation systems. Although there
is a cost premium for micro-irrigation systems, the payback can be quick, due to lower
water use and less maintenance.
Suggested Steps:
1. Review installation landscaping plans and guidelines along with site constraints to
identify opportunities for water efficient landscaping.
2. Require the architect-engineer designers to perform a soil and climate analysis and
consider Xeriscape and water-efficient irrigation technologies, including high-efficiency
irrigation systems and/or grey-water systems for irrigation.
3. Document collaborative decisions in the project agreements with the installation prior to
commencing final design.
Submittal: Provide appropriate documentation in design that necessary analysis has occurred to
determine that the project site meets the criteria. Include appropriate documentation and drawings to
depict natural areas and landscape areas. Identify irrigation areas and types of systems used.
Intent: Eliminate the use of potable water, or other natural surface or subsurface water resources
available on or near the project site, for landscape irrigation.
Requirements: Use only water collected on site that would otherwise be released from the site,
such as captured rain, or recycled water, or use water treated and conveyed by a public agency
specifically for nonpotable uses, or in a combination of water from these sources to eliminate all
potable water use for site irrigation (except for initial watering to established plants) OR do not install
permanent landscape irrigation systems.
As applied to: Commissary landscape features are usually identified during the early
Commissaries design stages and integrated into the civil site design. DeCA encourages the use of
natural landscape materials in site design and minimizes the area requiring landscaping to key areas
in the front of the store. The use of only natural materials and Xeriscape could make this credit
achievable under normal circumstances. Other design considerations include:
Rely solely on native or adaptive vegetation areas to provide landscape features to the
site.
The architect-engineers selection of landscape materials requires coordination with the
installation to assure selection of native materials.
If water is collected and released on the site for storm water retention, consider
incorporating these features into the landscape plan.
June 2011 01 33 29 13
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
Eliminating a permanent irrigation system altogether reduces first costs and life-cycle
costs.
Irrigation systems that capture and reuse stormwater runoff, greywater or rainwater are
more costly to design and may require code variances.
Suggested Steps:
1. Review installation landscaping plans and guidelines along with site constraints to
identify opportunities for water efficient landscaping.
2. Require the architect-engineer designers to perform a soil and climate analysis and
consider Xeriscape and water-efficient irrigation technologies.
3. Document collaborative decisions in the project agreements with the installation prior to
commencing final design.
4. Provide analysis of the sustainability of the landscape design without permanent irrigation
systems.
Requirement: Per EPAct 2005 Section 109, when potable water is used to improve a buildings
energy efficiency, deploy life cycle cost effective water conservation measures.
Requirement: Specify EPAs WaterSense labeled products or other water conserving products
where available. Choose irrigation contractors who are certified through a WaterSense labeled
program. For further detail go to www.epa.gov/watersense.
1 - Thermal Comfort
Requirements: Provide a thermally comfortable environment that supports the productivity and well-
being of building occupants. Comply with ASHRAE Standard 55-2004, Thermal Comfort Conditions
for to Human Occupancy.
Application: This goal should be readily achievable in commissary construction by the specification
of materials and procedures that comply with the goal requirements. Consistent with DeCAs Design
Criteria, typical commissary design provides efficient thermal comfort for human occupancy. The
June 2011 01 33 29 14
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
DeCA Design Criteria has established efficient operating and patron comfort criteria for the design
building envelope and HVAC system to provide and maintain comfort ranges for human occupancy
that comply with ASHRAE Standard 55-2004.
Suggested Steps:
3. Review architect and engineer design for compliance with these requirements.
Requirements: Establish minimum indoor air quality (IAQ) performance to enhance indoor air
quality in buildings, thus contributing to the comfort and well-being of the occupants. Meet the
minimum requirements of voluntary consensus standard ASHRAE 62.1-2007, Ventilation for
Acceptable Indoor Air Quality. Mechanical ventilation systems shall be designed using the Ventilation
Rate Procedure. Naturally ventilated buildings must comply with ASHRAE 62.1-2007, paragraph 5.1.
Application: Commissary ventilation designs conform to ASHRAE standards for Acceptable Indoor
Air Quality. Mechanical Ventilation systems are designed using the Ventilation Rate Procedure.
Facilities must be designed to conform to Sections 4, 5, 6, and 7 of the referenced standard. Other
factors to consider:
1. It is important to consider the potential adverse effects on Indoor Air Quality caused by
improper maintenance procedures. As an example, use of toxic lubricants on HVAC
system dampers may affect indoor air quality. These procedures should be avoided.
2. Include proactive design details that will eliminate some of the common causes of indoor
air quality in buildings.
3. Ensure ventilation system outdoor air capacity can meet standards in all modes of
operation.
4. Locate building outdoor air intakes (including operable windows) away from potential
pollutant/contamination sources such as dock receiving and loading areas, building
exhaust fans, cooling towers, sanitary vents, dumpsters, vehicle exhausts, runway
activities, and other potential sources of air pollution.
June 2011 01 33 29 15
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
5. Include measures to control and mitigate radon build-up in areas where this is prevalent.
6. Commissary projects limit environmental humidity in the sales area to minimize impact on
refrigeration systems. This also minimizes mold growth and promotes respiratory health.
Suggested Steps:
1. Target opportunities to enhance indoor Air Quality during the early stages of design.
3. Obtain necessary baseline information from the installation on potential Radon gas
residual levels and required mitigation measures.
4. Review design and location of all proposed and/or existing air intake structures for
potential impact on indoor air quality.
Submittal: Provide documentation by a responsible design professional declaring that the project is
fully compliant with Sections 4, 5, 6 and 7 of ASHRAE 62.1-2007. Include a summary of calculations
in the project Design Analysis, including all assumptions, assumed occupant densities, zone air
distribution effectiveness, and ventilation system efficiency.
3 - Thermal Comfort Monitoring
Requirements Provide a permanent monitoring system and process for corrective action to
ensure building performance to the desired comfort criteria as determined by Guiding Principle
IV.A.1-Compliance.
Suggested Steps
June 2011 01 33 29 16
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
3. Review architect and engineer design for compliance with these requirements.
Application: If a balance between wetting and drying is maintained, moisture will not accumulate
over time and moisture-related problems are unlikely. The extent and duration of wetting, storage
and drying must always be considered when assessing and designing moisture risk in buildings. The
judicious design, assembly and material choices is the most practical approach for designing
buildings and conditioning systems. There are four primary sources of moisture in building. They
are:
Water vapor from the exterior and from activities and processes with-in the building.
Moisture built-in with the materials of construction or brought in with goods and people.
Moisture moves under different mechanisms. Primarily the transport processes to be considered in
design are:
Liquid gravity flow, including hydrostatic pressure, through cracks, openings, and
macropores.
Suggested Steps:
June 2011 01 33 29 17
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
3. Review architect and engineer design for inclusion of the moisture control concepts
in buildings.
4. Include verification of technical compliance with these concepts as part of the facility
commissioning process.
Submittal: Provide documentation by a responsible design professional demonstrating and stating
the criteria for reasonable moisture control in buildings has been complied with in the design.
IV.C - Daylighting
Requirements Provide for the building occupants a connection between indoor spaces and the
outdoors through the introduction of daylight and views into the regularly occupied areas of the
building. Achieve a minimum Daylight Factor of 2% (excluding all direct sunlight penetrations) or
achieve at least 25 foot-candles using a computer simulation model in 75% of all sales and customer
service areas and any employee administration spaces occupied for critical visual tasks. Provide
daylight redirection and/or glare control devices to ensure daylight effectiveness. Exceptions for
areas where tasks would be hindered by the use of daylight will be considered on their merits.
Requirements:
Operationally, DeCA has opposed use of daylight features based on three arguments:
1. The first argument addresses the perceived non-uniformity of light caused by the
introduction of daylight into the operating areas of the store. Without control devices, the
natural light can introduce glare and heat into the operating space and create bright
spots and dark spots throughout the sales space. Provision of daylight redirection and/or
glare control devices can overcome this objection and ensure daylight effectiveness.
2. Additionally, there is also operational concern over the extra heat generated and how
this heat might affect refrigerated products such as produce. DeCA studies have
demonstrated the heat gain on product to be negligible.
3. Finally, there are concerns about maintenance and housekeeping requirements for
operative light and glare control devices.
June 2011 01 33 29 18
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
Clerestory windows in the produce area provide a distinguishable architectural element of the
store design. Designers are to investigate methods that are employed to reduce the amount of
light leaving the building.
Use of extensive storefront glazing, skylights and other light features need to be reconciled with
force protection entry and blast resistance standards.
Strategies to consider include building orientation, shallow floor plates, increased building
perimeter, exterior and interior permanent shading devices, high performance glazing and photo
integrated light sensors.
Predict daylight factors via manual calculations or model daylight strategies with a physical or
computer model to assess foot-candle levels and daylight factors achieved. Modeling must
demonstrate 25 horizontal foot-candles under clear sky conditions, at noon, on the equinox, at
30" above the floor. Any portion of a room achieving the requirements can qualify for this credit.
Many retail applications may not be able to use perimeter windows for day-lighting, due to display
or other security concerns. Skylights, clerestories and light wells may provide more feasible retail
alternatives. Depending on the design of a skylight (vertical monitor, horizontal/domed skylight,
saw-tooth) and the transmittance of the glazing, providing skylights at approximately 3-6% of the
applicable roof area may achieve this goal. For any project, glazing performance must be
carefully balanced for optimum daylight, heat loss and solar heat gain performance.
Suggested Steps
3. Review architect and engineer design for compliance with these requirements.
Submittal: Provide documentation demonstrating that the criteria for day-lighting has been
achieved. Provide area calculations that define the daylight zones and provide a summary of daylight
factor prediction calculations through manual methods or in a summary of computer simulations
illustrating that the foot-candle levels have been achieved.
Requirements Reduce the quantity of indoor air contaminants that are odorous, potentially
irritating and/or harmful to the comfort and well-being of installers and occupants. All materials listed
below that are used inside the exterior weatherproofing system must not exceed the following
requirements:
Adhesives, Sealants and Sealant Primers: South Coast Air Quality Management District
(SCAQMD) Rule #1168 requirements in effect on January 1, 2003 and rule amendment
date of October 3, 2003.
Aerosol Adhesives: Green Seal Standard GC-36 requirements in effect on October 19,
2000.
June 2011 01 33 29 19
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
Suggested Steps
2. Provide specification requirements for this plan consistent with the credit requirements
stipulated above.
3. Specify low-VOC materials and require contractors to provide product cut sheets, MSDS
data, and other documentation from the manufacturers that clearly demonstrate that
materials qualify as low VOC materials in construction documents.
4. Assure the contractors quality control procedures address review and monitoring of
materials for compliance.
5. Require the PMAC construction manager to document with the contractors adherence
with the credit requirements.
Requirements: Reduce the quantity of indoor air contaminants that are odorous, potentially irritating
and/or harmful to the comfort and well-being of installers and occupants. Paints and coating used on
the interior of the building and applied on-site must not exceed the VOC limits and must not include
any of the chemical components limited or restricted by the following standards:
Topcoat Paints: Green Seal Standard GS-11, Paints, First Edition, May 20, 1993.
Anti-Corrosive and Anti-Rust Paints: Green Seal Standard GS-03, Anti-Corrosive Paints,
Second Edition, January 7, 1997. (For applications on ferrous metal substrates)
All other Architectural Coatings, Primers and Undercoats: South Coast Air Quality
Management District (SCAQMD) Rule 1113, Architectural Coatings, rules in effect on
January 1, 2004.
Application: This goal should be achievable in commissary construction by the specification of low-
VOC materials in the construction documents. Particular attention should be given to the selection of
resilient paints and coatings used in commissary construction. Selection of oil-based paints should
June 2011 01 33 29 20
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
be carefully reviewed and avoided, if possible. Varnishes and finishes to doors should be applied in
well-ventilated space, outside of the sales and administrative areas. Selection of coatings used for
seamless flooring and terrazzo need to be carefully reviewed to ensure the products selected have
low-VOC ratings.
Suggested Steps
2. Provide specification requirements for this plan consistent with the credit requirements
stipulated above.
3. Specify low-VOC materials and require contractors to provide product cut sheets, MSDS
data, and other documentation from the manufacturers that clearly demonstrate that
materials qualify as low VOC materials in construction documents.
4. Assure the contractors quality control procedures address review and monitoring of
materials for compliance.
5. Require the PMAC construction manager to document with the contractors adherence
with the credit requirements.
Requirements Reduce the quantity of indoor air contaminants that are odorous, potentially irritating
and/or harmful to the comfort and well-being of installers and occupants. Carpets systems must not
exceed the target emissions factors of the Carpet and Rug Institutes:
Carpet: Green Label Plus Program and Testing Procedures.
Carpet Cushion: Green Label Program and Testing Procedure
Carpet Adhesive: Green Label Program and Testing Procedure.
OR
Carpets systems must not exceed the maximum target emission factors and testing
requirements identified below in a 24-hour chamber test. For carpets only, 14-day
chamber testing may be used in lieu of the 24-hour testing at the discretion of the product
manufacturer. Test results must be current within 12 months of product installation in the
building.
June 2011 01 33 29 21
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
Testing Procedures: Each manufactured product must meet the testing requirements identified
below. Testing data for individual materials used to fabricate a product cannot be used to
determine compliance with the established emissions criteria:
Product Sample Collection: Test specimens shall be selected or cut at random directly
from normal material production runs, for roll goods, carpet tile and cushion. Test
specimens for adhesives shall be collected from unopened manufacturers containers.
Specimens shall be packaged at the factory and shipped directly to testing laboratory by
the manufacturer within 24-hours of production. Packaging shall preserve the chemical
integrity of the specimen. Wrap the specimen in a manner that will eliminate direct
contact with air or absorbent packaging materials other than an inert air barrier such as
aluminum foil. A chain-of-custody form must accompany each test specimen.
June 2011 01 33 29 22
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
http://www.dhs.ca.gov/ps/deodc/ehlb/iaq/VOCS/Section_01350_07_15_2004_FINAL.pdf.
Chronic reference exposure levels (CRELs) are concentrations at or below which serious
non-cancer systemic health effects are unlikely to occur among a diverse human
population (including sensitive individuals) continuously exposed over ten years or more.
For further information about CRELS check with the California Environmental Protection
Agency (Cal/EPA) at:
www.calepa.ca.gov/air/chronic_rels/index.html
The Building Materials Emissions Study (Nov 2003) for the State of California is an
excellent guide on building materials emissions. It can be found on the state of California
website at:
(www.ciwmb.ca.gov/publications/greenbuilding/43303015.pdf)
The one exception to using CREL is for formaldehyde which is set to a higher emissions
level to address issues related to the ability of meeting the emissions criteria based on
current industry practices. Use accepted testing method criteria such as The Test
Method For Determining Total Volatile Organic Compound Emission Factors From
Carpet and Associated Materials Under Defined Test Conditions Using Small
Environmental Chambers from the EPA Carpet Policy Dialogue Compendium Report,
September 1991, EPA/560/2-91-002. This document is available from www.ntis.gov.
Suggested Steps
2. Provide specification requirements for this plan consistent with the requirements
stipulated above.
3. Specify low-VOC carpet materials and require contractors to provide product cut sheets,
MSDS data, and other documentation from the manufacturers that clearly demonstrate
that materials qualify as low VOC materials in construction documents.
June 2011 01 33 29 23
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
4. Assure the contractors quality control procedures address review and monitoring of
materials for compliance.
5. Require the PMAC construction manager to document with the contractors adherence
with the credit requirements.
Requirements: Reduce the quantity of indoor air contaminants that are odorous, potentially
irritating and/or harmful to the comfort and well-being of installers and occupants. Composite wood
and agrifiber products, including core materials, must contain no added urea formaldehyde resins.
Adhesives used in field- and shop-fabricated assemblies containing these products must contain no
urea-formaldehyde.
Application: This goal should be achievable in commissary construction by the specification of low-
VOC composite wood and laminate adhesive materials. The most likely use of this type of material
would be in fire-rated plywood used in the warehouse as a wall protection, installation of laminate
boards such as Fire Resistant Panel (FRP) with adhesives, dcor elements and signs, telephone and
communications boards, and millwork for cabinetry and in bakery deli areas. Particular attention
should be given to the specification of wood and agrifiber products that contain no added urea-
formaldehyde resins. Specify laminating adhesives for field and shop applied assemblies including
adhesives and veneers that contain no urea-formaldehydes. Review product cut sheets, MSDS data
sheets, signed submittals or other official literature from the contractor and manufacturer that clearly
demonstrate the products used do not contain urea formaldehyde resins. Contractor submittals
must clearly demonstrate compliance.
Suggested Steps:
2. Provide specification requirements for this plan consistent with the requirements
stipulated above.
3. Specify low-emitting composite woods and laminate adhesives and require contractors to
provide product cut sheets, MSDS data, and other documentation from the
June 2011 01 33 29 24
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
manufacturers that clearly demonstrate that materials do not contain urea formaldehyde
resins.
4. Assure the contractors quality control procedures address review and monitoring of
materials for compliance.
5. Require the PMAC construction manager to document with the contractors adherence
with the credit requirements.
June 2011 01 33 29 25
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
air handling units processing both return air and outside supply air. Ensure that air-handling units
can accommodate required filter sizes. Typically, commissary filtration media is 2" or less in
thickness. To comply with the stated MERV 13 value, filtration media will have to be 4" thick or more.
Suggested Steps:
2. Provide specification requirements for this plan consistent with the requirements
stipulated above.
3. Evaluate potential chemical gas and liquid pollution when designing mechanical rooms,
battery charging areas, and wash down operations.
4. Review architect and engineer design for compliance with these procedures.
1. Permanent entryway systems (grilles, grates, etc.) to capture dirt, particulates, etc. are
provided at all high volume entryways.
2. Chemical use areas and copy rooms have been physically separated with deck-to-deck
partitions; independent exhaust ventilation has been installed at the required exhaust rate
and negative pressure differential.
3. Drains in facility cleaning and maintenance areas are plumbed for environmentally
appropriate disposal of hazardous liquid wastes.
4. Filters used meet the MERV requirements with new media installed prior to occupancy.
Provide a listing of each filter installed including the MERV value, manufacturer name
and model number.
Goal: Protect Indoor Air Quality during Construction. Follow the recommended approach of the
Sheet Metal and Air Conditioning Contractor's National Association Indoor Air Quality Guidelines for
Occupied Buildings under Construction, 1995. After construction and prior to occupancy, conduct a
minimum 72-hour flush-out with maximum outdoor air consistent with achieving relative humidity no
greater than 60 percent. After occupancy, continue flush-out as necessary to minimize exposure to
contaminants from new building materials.
Requirements: Prevent indoor air quality problems resulting from the construction/renovation
process in order to help sustain the comfort and well-being of construction workers and building
June 2011 01 33 29 26
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
occupants. Develop and implement an Indoor Air Quality (IAQ) Management Plan for the
construction and pre-occupancy phases of the building as follows:
During construction meet or exceed the recommended Design Approaches of the Sheet
Metal and Air Conditioning National Contractors Association (SMACNA) IAQ Guideline
for Occupied Buildings under Construction, 1995, Chapter 3.
Protect stored on-site or installed absorptive materials from moisture damage.
If air handlers must be used during construction, filtration media with a Minimum
Efficiency Reporting Value (MERV) of 8 must be used at each return air grill, as
determined by ASHRAE 52.2-1999.
Replace all filtration media immediately prior to occupancy.
Application: This goal requires the construction contractor to adopt and implement an indoor air
quality plan during construction, control pollutant sources and interrupt contamination pathways.
Sequence the installation of materials to avoid contamination of absorptive materials such as
insulation, carpeting, ceiling tile, and gypsum wallboard. Coordinate with IV.E.2-Construction IAQ
Management Plan Before Occupancy and IV.D.5-Indoor Chemical and Pollutant Source Control and
install only a single set of final filtration media. Other factors to consider:
2. Specifications to comply with these requirements will have to be clearly covered with the
contractor at the outset, during the preconstruction conference. Measures to assure
compliance would have to be incorporated into the contractors Quality Control Plan.
Suggested Steps
2. Provide specification requirements for this plan consistent with requirements stipulated
above.
3. Require the PMAC construction manager to document with photographs and weekly
progress reports, the contractors adherence with the credit requirements.
OR
June 2011 01 33 29 27
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
2. Declare the five design Approaches of SMACNA IAQ Guideline for Occupied Buildings
under Construction, 1995, Chapter 3, which were used during building construction.
Include a brief description of some of the important design approaches that were
employed.
2 - Construction IAQ Management Plan Before Occupancy
Requirements: Reduce indoor air quality problems resulting from the construction/renovation
process in order to help sustain the comfort and well-being of construction workers and building
occupants. Develop and implement an Indoor Air Quality (IAQ) Management Plan for the pre-
occupancy phase as follows:
After construction ends and with all interior finishes installed, as described in the
Reference Guide, install new filtration media and flush-out the building by supplying a
total air volume of 14,000 ft3 of outdoor air per ft2 of floor area while maintaining an
internal temperature of at least 60o F and, where mechanical cooling is operated, relative
humidity no higher than 60%.
The space may only be occupied following delivery of a minimum of 3,500 ft3 of outdoor
air per ft2 of floor area to the space, and provided the space is ventilated at minimum rate
of 0.30 cfm/ft2 of outside air or the design minimum outside air rate, whichever is greater,
a minimum of three hours prior to occupancy and during occupancy, until the total of
14,000 ft3/ft2 of outside air has been delivered to the space.
OR
Conduct baseline IAQ testing, after construction ends and prior to occupancy, using
testing protocols consistent with the United States Environmental Protection Agency
Compendium of Methods for the Determination of Air Pollutants in Indoor Air and as
additionally detailed in the Reference Guide.
Demonstrate that the contaminants concentration levels listed below are not exceeded:
CONTAMINATE MAXIMUM
CONCENTRATION
Formaldehyde 50 parts per billion
Particulates (PM10) 50 micrograms per cubic meter
Total Volatile Organic Compounds (TVOC) 500 micrograms per cubic meter
* 4-Phenylcyclohexene (4-PCH) 6.5 micrograms per cubic meter
Carbon Monoxide (CO) 9 part per million and no greater
than 2 parts per million above
outdoor levels
* This test is only required only if carpets and fabrics with Styrene Butadiene (SB) latex
backing material are installed as part of the base building systems.
For each sampling point where the maximum concentration limits are exceeded conduct
additional flush-out with outside air and retest the specific parameter(s) that were
exceeded to indicate the requirements are achieved. Repeat procedure until all
requirements have been met. When retesting non-complying building areas take samples
from the same locations as in the first test.
The air sample testing shall be conducted as follows:
June 2011 01 33 29 28
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
2. The building shall have all interior finishes installed, including but not limited
to millwork, doors, paint, carpet, and acoustic tiles. Non-fixed furnishings
such as workstations and partitions are encouraged, but not required, to be
in place for the testing.
3. The number of sampling locations will vary depending upon the size of the
building and number of ventilation systems. For each portion of the building
served by a separate ventilation system, the number of sampling points shall
not be less than one per 25,000 ft2, or for each contiguous floor area,
whichever is larger, and include areas with the least ventilation and greatest
presumed source strength.
4. Air samples are shall be collected between 4' and 7' from the floor to
represent the breathing zone of occupants and over a minimum 4-hour
period.
Application: This goal requires the construction contractor to adopt and implement an indoor air
quality plan during construction, control inside air pollution, and provide for a two week building flush
out or test of the contamination levels of the building prior to occupancy. Other factors to consider:
2. For IAQ testing, consider using a recognized measurement protocol similar to the EPA
Compendium of Methods for the Determination of Air Pollutants in Indoor Air. If
alternate testing protocols are used, provide justification that the measured test results
meet the intent of the EPA testing methods.
3. Copies of the IAQ testing results should describe the contaminant sampling and
analytical methods, the locations and duration of the contaminant samples, the field
sampling log sheets and laboratory analytical data and the methods and results utilized
to determine that the ventilation system was started at the normal daily start time and
operated at the minimum outside air flow rate for the occupied mode through the duration
of the air testing.
4. The potential impact of outside air flushing of the store environment for two weeks on the
operation and calibration of the sales area refrigeration systems has to be considered
during the design stages. The design engineers will need to evaluate the impact of an
extended period of flush with outside air on refrigerated display cases just prior to
occupancy. Introduction of moisture laden air may contribute to frost build up and require
extended defrost cycles. Operationally, it would also be difficult to preclude occupancy of
the store for extended periods of air flushing. It may be more feasible for DeCA to
require air sampling as part of facility commissioning rather than the extended flushing.
June 2011 01 33 29 29
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
Suggested Steps:
2. Provide specification requirements for this plan consistent with the requirements
stipulated above.
3. Specify contaminant control strategies including protecting the HVAC system, controlling
pollutant sources, interrupting pathways for contamination, enforcing proper
housekeeping and coordinating schedules to minimize disruption.
4. Specify the construction sequencing to install absorptive materials after the prescribed
dry or cure time of wet finishes to minimize the adverse effects on indoor air quality.
5. Specify that contractor will avoid practices that subject absorptive building materials
direct exposure to moisture, such as through precipitation, plumbing leaks or
condensation to avoid possible microbial contamination. Absorptive materials to be
protected include insulation, carpeting, ceiling tiles and gypsum products.
6. As part of the IAQ Plan, require the contractor to appoint an IAQ monitor to observe
construction practices for compliance
7. If air testing protocols are used in lieu of building flush-out, the IAQ testing procedures
should describe the contaminant sampling and analytical methods, the location and
duration of samples, the field sampling log sheets and laboratory analysis protocols
used. The methodologies should demonstrate that the systems were started at normal
daily start times and operated at minimum outside air flow rates for the occupied mode
for the duration of the testing.
8. With the contractors coordination require the PMAC construction manager to document
the contractors adherence with the requirements.
1. Documentation demonstrating the required flush out period, including dates and
procedures. Provide calculations that demonstrate the required total air volumes and
minimum ventilation volumes and rates have been delivered.
OR
2. Documentation that the required air quality testing procedure has been conducted and
that all areas tested were found to be below the maximum allowable concentration limits.
Provide a copy of the IAQ testing results that includes documentation of the results and
the identifying EPA testing method used. If alternative testing protocols are used,
June 2011 01 33 29 30
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
provide documentation and rationale justifying that the measured results meet the intent
of the EPA testing methods.
Requirement: Implement a policy and post signage indicating that smoking is prohibited within the building
and within 25' of all building entrances, operable windows and building ventilation intakes during building
occupancy.
Requirements: Increase demand for building products that incorporate recycled content materials,
therefore reducing impacts resulting from extraction and processing of new virgin materials. Use
materials with recycled content such that the sum of post-consumer recycled content plus one-half of
the pre-consumer content constitutes at least 10% of the total value of the materials in the project.
The value of the recycled content portion of a material or furnishing shall be determined by dividing
the weight of recycled content in the item by the total weight of all material in the item, then
multiplying the resulting percentage by the total value of the item. Mechanical and electrical
components shall not be included in this calculation. Recycled content materials shall be defined in
accordance with the International Organization of Standards document, ISO 14021 - Environmental
labels and declarations - Self-declared environmental claims (Type II environmental labeling.)
Application: The specification of recycled content material may be somewhat easier to achieve and
incorporate into new construction than reuse of building products and materials. Recycled content
materials have undergone some form of manufacture process to produce products that can be
labeled as new with recycled content. This category of materials may find greater acceptability than
resource reuse, because the perception to the customer is that the product is new. A list of EPA
designated items with Recovered Material Content is included in the DeCA Design Criteria
Handbook. Additional guidance about the EPA Environmentally Preferred Purchasing Program is
available through EPA. Comprehensive Procurement Guidelines for Construction and Landscaping
and the latest list of designated items can be downloaded at the EPA website
http://www.epa.gov/cpg/index.htm. It is Department of Defense Policy that 100% of the purchases of
these designated items meet or exceeds the EPA guidelines. Through compliance with these
provisions, the objectives of this goal should be achievable.
Suggested Steps:
1. Target opportunities for selection of recyclable content materials early during the project
planning and design stages. Investigate the latest EPA list of designated items at the
EPA website listed above.
2. Include appropriate investigative studies to confirm the suitability of the materials their
intended use.
3. Estimate material quantities by material types that will be required during construction.
June 2011 01 33 29 31
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
4. Identify the recycled content building materials that will be designated and specified as
part of the procurement.
5. Include requirements for recyclable content materials in the contract specifications. Even
if no specific materials are identified, the contractor should be encouraged to consider
reuse by indicating a government preference for materials of equal performance
characteristics and life expectancy.
7. Include provisions that require verification from the construction contractor that the
designated materials have been obtained and used in construction.
8. Have the contractor specify material types, quantities and source of recyclable content
material. Specify whether pre-consumer or post-consumer materials.
Submittal: Provide documentation that the goal requirements have been met. Include a listing of the
total supplied building materials and products, and list the materials and quantities of the materials
and products designated as recyclable content and identify their costs and the total costs of materials
and products for the project. Provide copies of specifications and contractor submittals to verify that
the identified recyclable content materials and products have been purchased and used on the
project.
Requirements: Reduce the use and depletion of finite raw materials by replacing them with
renewable, bio-based materials. Use rapidly renewable building materials and products (made from
plants that are typically harvested within a ten-year cycle or shorter.
Application: Specification of renewable bio-based materials may be difficult because of the nature
of commissary construction. The predominant materials of commissary construction projects are
contained in steel, concrete, roofing, manufactured equipment, walk-in refrigerated rooms, metal
doors, glazing, and architectural finishes. Opportunities to use bio-based materials such as bamboo
flooring, wool carpets, strawboard, cotton batt insulation, linoleum flooring, poplar OSB, sunflower
seed board, wheatgrass cabinetry, cork, agricultural fibers and other materials may be limited for this
goal. The most likely candidates of bio-based materials in commissary construction would be in trim
and finishes, insulation and limited application of suitable materials in dcor elements. It is also noted
that the list of qualifying materials excludes materials such as hardwoods. Also excluded from the
calculation are materials such as formwork, shoring, temporary partitions and other temporary
construction elements that are not a permanent part of the finished building. It may also be difficult to
assure these materials were actually used. For a more complete list, see the U.S. Green Building
Council website. Other factors to consider:
June 2011 01 33 29 32
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
3. Many of the materials designated as rapidly renewable carry a first cost premium, and as
percentage of total cost, it is not likely the percentages can be achieved without added
investment.
Suggested Steps:
1. Target opportunities for selection of bio-based materials early during the project planning
and design stages.
2. Include appropriate investigation in A-E design contracts to confirm the availability and
suitability of identified products.
3. Estimate material quantities by material types and values that will be required during
construction.
4. Identify bio-based materials that will be designated and specified as part of the
procurement.
7. Include provisions that require verification from the construction contractor that bio-based
materials have been obtained and used in construction.
Submittal: Provide documentation that the requirements have been met. Include a listing of the total
supplied building materials and products, and list the materials and quantities of the materials and
products designated as bio-based. Include calculations demonstrating that the project incorporates the
requirement. Identify their costs and the total costs of materials and products for the project. Include
manufacturers cut sheets or other submittal information to verify bio-based product characteristics.
Requirements: Divert construction and demolition debris from disposal in landfills and incinerators.
Redirect recyclable recovered resources back to the manufacturing process. Redirect reusable
materials to appropriate sites. Develop and implement a construction waste management plan,
quantifying material goals for diversion. Recycle and/or salvage at least 50% of non-hazardous
construction and demolition debris. Land clearing debris and excavated soil do not contribute to this
goal. Calculations must be done by weight.
June 2011 01 33 29 33
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
1. The contractor may achieve the objectives of this requirement by diverting wastes to
charitable organizations, such as Habitat for Humanity. Diversion to these organizations
is included under this goal.
2. Include appropriate investigative studies to confirm the suitability of the materials for
diversion.
3. Exclude hazardous materials from being diverted to other uses or other construction
sites.
Suggested Steps
1. Target opportunities for waste diversion should be identified early during the project
planning and design stages.
2. Estimate waste quantities by material types that will be generated during construction.
3. Identify potential construction haulers and recyclers that could handle the designated
materials and include requirements in the criteria.
4. Include provisions that require verification for the construction contractor that materials
have been diverted. Have the contractor specify material types, quantities and final
disposition.
Submittal: Provide certification that requirements have been met. Include tabulations of the
estimated total non-hazardous materials, the quantities diverted, and the means of diversion. Provide
copies of specifications and contractor submittals to verify that wastes have been diverted to other
uses.
Requirement: Reduce ozone depletion. Zero use of CFC-based refrigerants in new base building
HVAC&R systems. When reusing existing base building HVAC equipment, complete a
comprehensive CFC phase-out conversion.
June 2011 01 33 29 34
DeCA DESIGN CRITERIA HANDBOOK
01 33 29 SUSTAINABLE DESIGN REPORTING
Application: DeCA converted from CFC-based refrigerants for new construction and facility
renovation projects several years ago and had completed retrofits in CONUS and the Pacific by 1999.
By law, new HVAC and refrigeration equipment cannot contain CFCs. In response, DeCA
underwent an extensive program to replace all of its existing CFC-based refrigerant systems with
non-CFC refrigerants. Currently DeCA specifications do not allow CFC-based refrigerants and has
completely transitioned to alternative replacements (HFC). Initially the primary focus was to eliminate
R-12 and R-502 refrigerants and then begin replacing the HCFC-22, as equipment is replaced. The
HCFC-22 began phase out starting in 2003 and the phase out period extends for several years.
Other factors to consider:
Clearly identify required refrigerants as part of the design.
Verify during design reviews that no CFCs and HCFCs have been specified.
Document refrigerant types as part of facility commissioning.
Suggested Steps:
Submittal: Provide certification by the a licensed professional engineer or architect confirming that
no CFC-based refrigerants were used and that any pre-existing CFC-based refrigerant conditions
have been corrected.
END OF SECTION
June 2011 01 33 29 35
SECTION 01 33 29
SUSTAINABLE DESIGN REPORTING
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1. General requirements and procedures for compliance with Executive Order (EO) 13423 -
Strengthening Federal Environmental, Energy, and Transportation Management, as
identified in the Guiding Principles for Federal Leadership in High Performance and
Sustainable Buildings Memorandum of Understanding and Executive Order (EO) 13514 -
Federal Leadership in Environmental, Energy and Economic Performance.
2. A LEED Silver design target of 55 points under the LEED for Retail NC Rating System is
required for all new DeCA facilities. Design teams will not be required to register and
certify the building through USGBC. However, design teams will need to present DeCA
with a completed LEED scorecard during the early design phases of the project
demonstrating compliance with a LEED silver target. The scorecard shall indicate the
credits they would pursue as part of the design process, in addition to meeting the
required pre-requisites and minimum program requirements (MPRs) set forth by the
LEED rating system. At the end of the project the design team will be expected to provide
DeCA with a report showing they have complied with the requirements of all LEED
credits they elected to pursue at the beginning of the Project.
B. Related Sections:
1.2 DEFINITIONS
B. EPA:
1. Materials made from plants that are typically harvested within a 10-year or shorter cycle.
Rapidly renewable materials include products made from bamboo, cotton, flax, jute,
straw, sunflower seed hulls, vegetable oils, or wool. For a more complete list, see the
U.S. Green Building Council website, www.usgbc.org.
E. Recycled Content:
F. Bio-Based Content:
1.3 SUBMITTALS
B. Submittal Schedule:
C. Submittal List:
1. Solid Waste, Construction, and Demolition Debris Waste Management plan complying
with Division 01 Section Environmental Management. (LEED Credit MR 2.1)
2. Construction indoor-air-quality management plan complying with requirements of Division
23. (LEED Credit IEQ 3.1)
1. Solid waste disposal progress reports complying with Part 7 - Waste Management and
Disposal of Division 01 Section Environmental Management. (LEED Credit MR 2.1)
2. Recycled Content: Provide a listing of the total supplied building materials and products,
and list the materials and quantities of the materials and products designated as
recyclable content and identify their costs and the total costs of materials and products
for the Project. Provide documentation verifying that the identified recyclable content
materials and products have been purchased and used on the Project. (LEED
Credit MR 4)
3. Construction Indoor Air Quality Management (IAQ) During Construction. Comply with
sustainable design submittal requirements of Division 23 (LEED Credit IEQ 3.1)
5. Documentation listing the adhesives, sealants, sealant primers, and aerosol adhesives
used inside the weatherproofing system. For each listed product, state the VOC level, the
applicable standard, the classification of material and the VOC limit. (LEED
Credit IEQ 4.1) Indicate they do not exceed the following requirements.
a. Adhesives, Sealants, and Sealant Primers: South Coast Air Quality Management
District (SCAQMD) Rule #1168 requirements in effect on January 1, 2003 and rule
amendment date of October 3, 2003.
b. Aerosol Adhesives: Green Seal Standard GC-36 requirements in effect on
October 19, 2000.
6. Documentation listing all paints and coatings used inside the weatherproofing system.
For each product, state the VOC level, the applicable standard, the classification of
material and the VOC limit. (LEED Credit IEQ 4.2) Indicate they do not exceed the VOC
limits and do not include any of the chemical components limited or restricted by the
following standards.
a. Topcoat Paints: Green Seal Standard GS-11, Paints, First Edition, May, 20 1993.
b. Anti-Corrosive and Anti-Rust Paints: Green Seal Standard GS-03, Anti-Corrosive
Paints, Second Edition, January 7, 1997. (For applications on ferrous metal
substrates.)
c. All other Architectural Coatings, Primers, and Undercoats: South Coast Air Quality
Management District (SCAQMD) Rule 1113, Architectural Coatings, rules in effect
on January 1, 2004.
7. Documentation listing all composite wood products used in the building and state that
they contain no added urea formaldehyde resins and list all the laminating adhesives
used in construction and state that they contain no urea formaldehydes. Provide the
documentation for all core and adhesive products used on the Project indicating that the
products used contain no added urea formaldehydes. (Credit IEQ 4.4)
PART 2 - PRODUCTS
A. General:
A. General:
1. Provide a minimum of 50 percent (by cost) of wood-based materials that are produced
from wood obtained from forests certified by an FSC-accredited certification body to
comply with FSC STD-01-001, "FSC Principles and Criteria for Forest Stewardship."
(LEED Credit MR 7).
a. Wood-based materials include, but are not limited to, the following materials when
made from wood, engineered wood products, or wood-based panel products:
1) Miscellaneous carpentry.
2) Finish carpentry.
3) Architectural woodwork.
4) Wood cabinets.
1. For field applications that are inside the weatherproofing system, use adhesives and
sealants that comply with the following limits for VOC content when calculated according
to 40 CFR 59, Subpart D (LEED Credit IEQ 4.1):
1. For field applications that are inside the weatherproofing system, use paints and coatings
that comply with the following limits for VOC content when calculated according to
40 CFR 59, Subpart D (LEED Credit IEQ 4.2):
a. Flat Paints, Coatings, and Primers: VOC not more than 50 g/L.
b. Nonflat Paints, Coatings, and Primers: VOC not more than 150 g/L.
c. Anticorrosive and Antirust Paints Applied to Ferrous Metals: VOC not more than
250 g/L.
d. Stains: VOC not more than 250 g/L.
e. Primers, Sealers, and Undercoaters: VOC not more than 200 g/L.
f. Dry-Fog Coatings: VOC not more than 400 g/L.
g. Zinc-Rich Industrial Maintenance Primers: VOC not more than 340 g/L.
h. Pretreatment Wash Primers: VOC not more than 420 g/L.
i. Aromatic Compounds: Paints and coatings shall not contain more than 1.0
percent by weight total aromatic compounds (hydrocarbon compounds containing
one or more benzene rings).
PART 3 - EXECUTION
A. General:
A. General:
1. Implement measurement and verification plan consistent with (LEED Credit EA 5):
OR
2. If not already in place, install metering equipment to measure energy usage. Monitor,
record, and trend log measurements.
3. Evaluate energy performance and efficiency by comparing actual to predicted
performance.
4. Measurement and verification period shall cover at least one year of post-construction
occupancy.
A. Comply with Part 7 - Waste Management and Disposal of Division 01 Section Environmental
Management. (LEED Credit MR 2)
A. General:
2. Comply with SMACNA's "SMACNA IAQ Guideline for Occupied Buildings under
Construction," 1995, Chapter 3. (LEED Credit EQ 3.1)
a. After construction ends, prior to occupancy and with all interior finishes installed,
as described in the USGBC Reference Guide, install new filtration media and
perform a 72-hour building flush-out by supplying a total volume of 14000 cu. ft.of
outdoor air per sq. ft.of floor area while maintaining an internal temperature of at
least 60 deg Fand, where mechanical cooling is operated, a relative humidity no
higher than 60 percent.
b. The space may only be occupied following delivery of a minimum of 3500 cu. ft.of
outdoor air per sq. ft.of floor area to the space and provided the space is ventilated
at a minimum rate of 0.30 cfm per sq. ft.of outside air or the design minimum
outside air rate, whichever is greater, a minimum of three hours prior to occupancy
and continue during occupancy until a total of 14000 cu. ft./sq. ft.of outside air has
been delivered to the space.
OR
a. Formaldehyde: 50 ppb.
b. Particulates (PM10): 50-micrograms/cu. m.
c. Total Volatile Organic Compounds (TVOC): 500-micrograms/cu. m.
d. *4-Phenylcyclohexene (4-PH): 6.5-micrograms/cu. m.
e. Carbon Monoxide: 9 ppm and no greater than 2 ppm above outdoor levels.
*This test is only required only if carpets and fabrics with Styrene Butadiene (SB) latex
backing material are installed as part of the base building systems.
6. For each sampling point where the maximum concentration limits are exceeded, conduct
additional flush-out with outside air and retest the specific parameter(s) exceeded to
8. Air samples shall be collected between 4 and 7 feet from the floor to represent the
breathing zone of occupants, and over a minimum four-hour period.
END OF SECTION
GENERAL
1.02. Summary. The computer analysis predicts energy consumption and energy system performance.
It can optimize electrical and mechanical system operations and architectural alternatives such
as building orientation, building length and width, number of building stories, wall and roof
construction, thickness of insulation, window size and type, and solar and shading applications.
Base optimization on a life cycle cost study. Normally, designers will choose the least life cycle
cost alternatives taking into account building aesthetics. Perform analysis at the 30% Design
Stage. BLAST 3.0, DOE-2.2, Trane TRACE 700, Carrier HAP-E20, EnergyPlus, or other similar
computer programs which perform transient thermal analyses are acceptable.
1.03. Compliance. Compliance with energy targets shown in Table 1 (from 1991 Corps of Engineers
Design Criteria) are mandatory and are predicated on Title 10 CFR, Subpart F, Part 434 "Energy
Conservation Voluntary Performance Standards for New Commercial and Multifamily High Rise
Residential Buildings, Mandatory for New Federal Buildings," Section 434.601. See attached
Figures 1 and 2 for compliance.
A. Base on the National Bureau of Standards (NBS) handbook 135, "Life-cycle Costing Manual for
the Federal Energy Management Program," the current edition.
B. Analysis shall result in the least building energy use, consistent with least life cycle cost.
C. The HVAC system to be considered will be packaged rooftop DX cooling, indirect gas fired
heating equipment as this equipment has been demonstrated to have the lowest life cycle costs
in most instances. Where rooftop equipment is prohibited by Base or post policy, consider split
system DX cooling and heat pump heating. Where electric or gas utilities are abnormally high or
climatic conditions are extreme, the use of boilers, desiccant dehumidifiers or other strategies
may be considered. In these cases, provide a life-cycle cost economic analysis to evaluate
alternative fuel sources and other energy reduction strategies. See paragraph this section entitled
Guidelines.
1.05. Definitions:
A. Energy Use Budget (EUB). The energy KCAL that is consumed within the 5'-0 line of a building
per year over a 24 hour/day, 365 days/year period and specified operating hours. This energy
consists of space heating, space cooling, ventilation and lighting loads, excluding process loads.
See Tables 1 and 1A attached.
B. Process Loads. Non-real property installed equipment or user equipment loads (typewriters,
copiers, merchandise display cases, commissary refrigeration systems, computer systems,
industrial equipment, training systems, etc.) and their cooling requirements, meat department
wash down, and hot water heating requirements for commissaries. Do not include specialized
ventilation systems, such as exhaust hoods or those required by OSHA standards, in the
calculation of the EUB. People are not considered process loads. Therefore, include their
contribution to the EUB in the energy calculations and base such calculations on expected or
actual operating times. Combine them with other EUB elements which are calculated at the
expected or actual operating times to provide the total EUB.
C. Design Energy Usage (DEU). Sum of energy figures for heating, cooling, ventilation, domestic
hot water (DHW), and lighting, which the designer calculates as part of the design. Make DEU
computations based on normal operating hours over a period of one year.
D. Total DEU (TDEU). Similar to DEU, except, its basis is expected or actual operating hours over a
one year period. It not only includes the sum of five energy consumption components (heating,
cooling, lighting, and ventilation), but also includes process load energy figures.
June 2011 01 33 29.51 1
DeCA DESIGN CRITERIA HANDBOOK
01 33 29.51 - COMPUTER ENERGY ANALYSIS
E. EUB. Target energy figure which represents maximum allowable energy consumption in
KCAL/m2/YR (BTU/SF/YR) over a 24 hour/day, 365 days/year period with the operating hours
specified.
F. Heating Energy Figure. Calculated energy figure for heating building environment based on the
required operating time.
G. Cooling Energy Figure. Calculated energy figure for cooling the building environment based on
the required operating time.
H. Ventilation Energy Figure. Calculated energy figure for ventilating building environment based on
required operating time. This figure is the fan energy for circulating air during the economizer
cycle, if used, and conditioned air when the heating or cooling system is not on.
I. Lighting Energy Figure. Calculated energy figure for lighting the building based on the required
operating time.
J. Domestic Hot Water (DHW) Energy Figure. Calculated energy figure for heating domestic hot
water based on the operating hours. This energy figure does not include the process load for
meat department wash down operation.
K. Process Load Energy Figure. Calculated energy figure for process loads based on the actual or
anticipated hours/day and days per week.
1.06. Guidelines:
A. DEUs apply only to building loads and to energy consumed within the 5'-0" line of a building
except for the following cases:
1. Where a packaged chiller, cooling tower, air-cooled refrigeration condenser, transformer or
substation, or heating plant is located outside the 5'-0 line but serves only one building,
charge the energy required to operate these facilities to the building.
2. Where equipment in paragraph 1.6.A.1. above serves two to four buildings, pro-rate the
energy requirements among the buildings. Where such facilities serve five or more buildings,
consider these facilities in the category of central plants.
B. Losses from steam, chilled water, high temperature water or hot water distribution lines beyond
the 5'-0" line are not chargeable to the building energy consumption except as provided in
paragraph 1.6.A.2. above.
C. Exterior lighting beyond the 5'-0" line is not chargeable to the building energy consumption.
D. For the purposes of calculating energy budget figures, use the fuel conversion factors indicated in
Table 2 attached.
E. At specific installations where the energy source KCAL (BTU) content varies significantly from the
value presented in Table 2 above, then the local value may be used provided:
1. There is adequate data on permanent file covering a period of at least two years to support
the different value, and
2. There is a fully documented basis to expect that different value to remain in effect for the
foreseeable future with the documentation to remain in a permanent file.
F. Measure energy in the form of steam, high temperature water, medium temperature water or
chilled water which is supplied from a central plant, at the building boundary with proper credit
given to the energy in the condensate return or water return. Do not charge distribution line
losses beyond the building 5'-0) line against the building consumption.
G. Consider hot water requirements, with the exception of domestic hot water (hand washing,
restrooms, etc.) as process load in commissaries. Accordingly, do not include them in the EUB
requirements.
H. Clearly identify the calculated TDEU in the summary analysis of the energy report. Calculated
TDEU should be in the range of 131,000 to 160,000 BTU/SF/YR.
1.07. Energy Budget Analysis Requirements shall include but not be limited to the following
information:
A. The space heating, cooling, ventilation, lighting, and DHW energy figures based on the operating
hours, plus the DEU based on the actual or expected operating hours per day and days per
week, not including process loads.
B. Comments on the ease or difficulty of meeting the EUB, if the DEU varies from the EUB by 10 to
14.9% (+ or -).
C. A detailed summary of the heat gain/loss analysis at the 30% design stage.
D. A computer generated printout of DEUs that are calculated after all optimized, cost effective and
practicable energy efficient applications, or techniques are included in the envelope of the
building and building non-process loads. Design the facility to an optimum EUB, and do not
consider the EUB as a convenient stopping point for determining the building energy efficiency.
Likely, the calculated DEU will be less, and in some cases much less, than the EUB, depending
on the incorporation of other forms of energy efficient applications.
E. Provide certification of mandatory compliance with Section 435.112 of Title 10 CFR, Part 435,
Subpart A, "Energy Conservation voluntary Performance Standards for New Commercial and
Multifamily High Rise Residential Buildings, Mandatory for Federal Buildings," published January
30, 1989, for each design. Provide the statement below on the first sheet of the design
documents.
"We certify that these design documents comply with the requirements of Section
435.112 of Title 10 CFR, Part 435, Subpart A."
END OF SECTION
TABLE 1
1 2 3 4 5 6 7 8 9 10 11
ADMIN/ 45 45 40 40 35 40 40 35 35 40 40 10 5
OPERATIO
NS
BUILDINGS:
OVER 740
SM
(8,000 SF)
UNDER 50 50 40 40 40 45 45 35 30 35 35 10 5
740 SM
(8,000 SF)
COMMISSA 90 80 70 60 55 60 70 55 55 55 65 122 62
RY
BUILDINGS
NOTE 1: If more than one distinct function such as warehousing is being performed in an area which
comprises more than 10% of the building's floor area, the EUB will be normalized using the
following formula:
EUB=EUB 1 (Area 1/Area Total) + EUB 2 (Area 2/Area Total) + EUBN (Area N/Area
Total)
Where: EUB is for the mixed use building, EUBN is for one of the distinct functional areas,
Area N is the gross floor area devoted to function N, and Area Total is the total gross floor
area of the building.
NOTE 2: Occupancy hours per day and days per week may vary. Tabulated EUB values are based
on 12 hours per day and 6 days per week.
TABLE 1A
\1 The data published in TM 5-785/AFM 88-29/NAFAC P-89 (Engineering Weather Data) will be
used to select the appropriate weather regions.
\2 Weather Regions 1, 2 and 3 are determined by the Heating Degree Day Range independent of the
Cooling Degree Day.
\3 Weather Regions 4, 5, 6, 7, 8 and 9 are determined by the Cooling Degree Days being less than
2000 and then by the appropriate range bracket of Heating Degree Day.
\4 Weather Regions 10 and 11 are determined by the Cooling Degree Days being greater than 2000
and then by the appropriate range bracket of Heating Degree Day.
TABLE 2
\1 High temperature, Medium temperature, or Chilled Water from a Central Plant will use the heat value
of fluid based on the actual temperature and pressure delivered to the 5' line.
\2 The EUB values assume that no electric resistive heating will be used in the building (except auxiliary
electric resistive heating used with heat pump systems). When 10% or more of a building's annual
heating consumption will be derived from electric resistive heating, the electric resistive portion will be
multiplied by 2.2 to reflect additional conversion losses.
\3 At specific installations where the energy source cal/Kg (BTU) content is known to vary consistently by
10% or more from the values given above the local value may be used provided there is adequate
data on file for two years or more to justify the revision and that this value is expected to hold true for
at least five years following building occupancy.
Figure 2
A-E SUMMARY OF ENERGY CONSUMPTION FOR EUB VALUE
INSTALLATION: HOST
PDC NO.: PROJECT
A-E FIRM:
DESIGN
I. BUILDING ENVELOPE LOSS PER DEGREE HOUR (DH)
KW/DH
GLASS N OR NE "U" FACTOR
(BTU/DH)
KW/DH
GLASS E OR SE "U" FACTOR
(BTU/DH)
KW/DH
GLASS S OR SW "U" FACTOR
(BTU/DH)
KW/DH
GLASS W OR NW "U" FACTOR
(BTU/DH)
KW/DH
TOTAL GLASS LOSS:
(BTU/DH)
KW/DH
INFILTRATION LOSS:
(BTU/DH)
KW/DH
ROUND FLOOR LOSS:
(BTU/DH)
KW/DH
TOTAL LOSS THROUGH BUILDING ENVELOPE:
(BTU/DH)
Figure 2
A-E SUMMARY OF ENERGY CONSUMPTION FOR EUB VALUE
KW/H
TOTAL INTERNAL HEAT GAINS (WINTER):
(BTUH)
KW/H
TOTAL GAIN TO THE INTERIOR (WINTER):
(BTUH)
(ENVELOPE + INTERNAL GAINS)
Figure 2
A-E SUMMARY OF ENERGY CONSUMPTION FOR EUB VALUE (CONT.)
HEATING: KW/m2/YR
(BTU/SF/YR)
COOLING: KW/m2/YR
(BTU/SF/YR)
LIGHTING: KW/m2/YR
(BTU/SF/YR)
VENTILATION: KW/m2/YR
(BTU/SF/YR)
DHW HEATING: KW/m2/YR
(BTU/SF/YR)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Fire Prevention.
2. Safety.
3. Security.
1.2 SUBMITTALS
B. Submittal Schedule:
1. Provide the indicated quantity. Note that the Government will retain three copies and the
pdf file.
D. Submittal List:
Reference Submittal Item Quantity Action
1.4B Fire Prevention Plan X R
1.5C Safety Plan X R
1.6 Security Plan X R
1.3 MANAGEMENT
A. The Contractor shall be responsible for initiating, maintaining and supervising all fire prevention,
safety, and security precautions and programs in connection with the performance of the
Contract.
A. Standards: Comply with the requirements of the Installation's Fire Prevention Standards.
Comply with NFPA 241 "Standards for Safeguarding Construction, Alterations, and Demolition
Operations."
B. Submittals: Provide a Fire Prevention Plan which contains, but is not limited to, procedures for
the following:
a. The proper availability, operation and location of fire protection equipment and
general supervision of safeguards.
b. Coordination with installation fire chief on all matters of special permits such as
burning or welding permits, fire prevention, fire reporting, and fire fighting.
2. Safeguards:
a. Fire-resistant construction for offices, shops, and sheds located within the
construction area and within 30 feet of building lines. Comply with the
requirements of NFPA 241.
b. Prohibition of smoking in the commissary and in the vicinity of hazardous
operations and locations.
c. Access for fire fighting vehicles to the immediate job site throughout the
construction period.
d. Vehicle parking control measures so as not to conflict with emergency vehicle site
access.
e. Control measures for combustion powered construction equipment (compressors,
hoists, derricks, pumps, etc., dealing with both fire prevention and exhaust fumes.
f. Temporary Fire protection: Until permanent fire protection is operational, install
and maintain temporary fire protection facilities (including alarm and all
suppression systems) of the types required to protect against reasonably
predictable and controllable fire losses. Comply with NFPA 10 "Standard for
Portable Fire Extinguishers" and NFPA 241 "Standard for Safeguarding
Construction, Alterations, and Demolition Operations."
g. Changes to exits or exits related to temporary construction. Inform and gain the
approval of the Installation Safety and Fire Officers for the maintenance of exit
requirements (both travel distance and exit numbers).
1.5 SAFETY
A. Standards: Comply with ANSI A10 Series standards for "Safety Requirements for Construction
and Demolition." Comply with OSHA 1910 and 1926. Comply with USACE EM 385-1-1 Health
and Safety Manual.
B. The Contractor shall take reasonable precautions for safety of, and shall provide reasonable
protection to prevent damage, injury or loss to:
1. Employees on the Work and other persons who may be affected thereby;
2. The Work and materials and equipment to be incorporated therein, whether in storage on
or off the site, under care, custody or control of the Contractor or the Contractor's
Subcontractors or Sub-subcontractors; and
C. Submittals: Provide a Safety Plan and accident prevention policy for all personnel during the
performance of the work. Requirements: The plan shall contain, but is not limited to,
procedures for the following:
a. Did Contractor hold job safety meeting? (If YES, attach a copy of the meeting
minutes.)
b. Were there any lost time accidents? (If YES, attach a copy of the completed
OSHA report.)
c. Were there any non-lost time accidents? (If YES, attach a copy of the completed
OSHA report.)
d. Was trenching/scaffold/high voltage electrical work done? (If YES, attach a
statement or checklist showing inspection performed.)
e. Equipment Inspections: Attach a list of safety inspections on any equipment
delivered to the site for construction purposes stating the equipment meets all
OSHA operating requirements (e.g., fire extinguishers, back up alarms, etc.).
Perform weekly inspections for compliance.
18. Confined Space Entry and Access Plan: <insert name of installation> has designated
the [entire crawl space] [access tunnel to refrigerated display cases] under the
existing Commissary building as a "CONFINED SPACE, PERMIT REQUIRED FOR
ENTRY." <insert name of installation>s Ground Safety Office has indicated the OSHA
29 CFR 1926 requirements for "ENTER BY PERMIT ONLY CONFINED SPACE" will be
required for entry into and work in the existing [crawl space] [tunnel], including, but not
limited to, the following:
a. Personnel that enter the [crawl space] [tunnel] shall be trained accordingly.
b. A Confined Space Access Plan shall be prepared.
c. A Confined Space Permit shall be prepared.
d. An attendant shall be stationed outside the confined space access.
D. Comply with all applicable requirements stipulated by the Occupational Safety and Health Act
and General Provisions clause titled Accident Prevention for method of operation, work
conditions, procedures, and equipment.
E. The Contractor shall not load or permit any part of the construction or site to be loaded so as to
endanger its safety.
1.6 SECURITY
A. Submittals: Provide a Security Plan for persons and property during the performance of the
Work.
B. Requirements: The Plan shall contain, but is not limited to, procedures for the following:
1. Security Clearances: Information for security clearances and compliance with security
regulations as imposed by both the military installation and the buildings occupying
agency for all Contractor employees.
2. The Governments reservation of right to exclude or remove from the site or building any
employee of the Contractor or Subcontractor whom the Government deems incompetent,
careless, insubordinate, otherwise objectionable, or whose continued employment on the
work is deemed by the Government to be contrary to public interest.
3. Identification Pass: While on the Installation, each employee of the Contractor and
subcontractors shall have in his possession, an approved identification pass. Indicate the
individuals name, and bear a picture of the individual. Coordinate with the Commissary
Store Director for individual requirements regarding security badges while within the
confines of the commissary building.
4. Security Enclosure and Lockup: Install substantial temporary enclosure of partially
completed areas of construction unless otherwise directed by the Contracting Officer.
Provide locking entrances to prevent unauthorized entrance, vandalism, theft, and similar
violations of security.
5. Storage: For storage of materials and equipment that are of value or attractive for theft,
provide a secure lockup. Enforce discipline in connection with the installation and
release of material to minimize the opportunity for theft and vandalism. As alterations or
construction on buildings progress, provide temporary security enclosures, doors and
locks necessary to prevent unauthorized entrance.
6. Restricted Areas: Do not permit workers in restricted areas (as designated by the
Contracting Officer).
7. Do not change over from use of temporary security to permanent security until the
Contracting Officer accepts the work.
8. Restrictions on photographs at sensitive areas of the installation.
END OF SECTION
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 DEFINITIONS
A. Acronyms:
B. Certified Industrial Hygienist (CIH): An individual certified the American Board of Industrial
Hygiene (ABIH) to have met ABIH requirements for education and experience, and through
examination, has demonstrated the required level of knowledge in industrial hygiene.
C. Containment: The act of stopping the spread or propagation of hazardous substances spilled or
released into the environment.
E. Cleanup: The act of removing hazardous substances from the scene of a spill release or
stabilizing or neutralizing hazardous substances to non-hazardous concentrations in
accordance with established federal, state, local, and Installation procedures.
I. Disposal: The thermal or chemical destruction or permanent land filling of hazardous waste.
K. Environmental Service Provider: Environmental Consulting Firm contracted by the A/E or A/E
Firm if environmental professionals are in-house.
M. Generator: Any person or agency that produces, creates, or discovers hazardous waste.
1. Any item or chemical that is a "health hazard" or "physical hazard" as defined by OSHA
in 29 CFR 1910.1200 or by the EPA at 40 CFR 370, 372, and 100-180, including the
following:
a. Chemicals which are carcinogens, toxic or highly toxic agents, reproductive toxins,
irritants, corrosives, sensitizers, hepatotoxins, nephrotoxins, neurotoxins, agents
which act on the hematopoietic system, and agents which damage the lungs, skin,
eyes, or mucous membranes;
b. Chemicals which are combustible liquids, compressed gases, explosives,
flammable liquids, flammable solids, organic peroxides, oxidizers, pyrophorics,
unstable (reactive) or water reactive;
c. Chemicals which in the course of normal handling, use, or storage operations may
produce or release dusts, gases, fumes, vapors, mists or smoke which may have
any of the above characteristics;
d. Any item or chemical which is reportable or potentially reportable as inventory
under the reporting requirements of the hazardous chemical reporting section of 40
CFR (40 CFR part 370), or as an environmental release under the reporting of the
toxic chemical release reporting community right-to-know (40 CFR part 372),
including chemicals with special characteristics which in the opinion of the
manufacturer can cause harm to people, plants, or animals when released by
spilling, leaking, pumping, pouring, emitting, emptying, discharging, injecting,
escaping, leaching, dumping, or disposing into the environment (including the
abandonment or discarding of barrels, containers, and other receptacles).
e. Any item or chemical which, when being transported or moved, is a risk to public
safety or is an environmental hazard and is regulated as such by one or more of
the following:
P. Hazardous Substance: A material and its mixtures or solutions that is identified by the letter "E"
in column (1) of the Hazardous Materials Table, 49 CFR Sec. 172.101 or as identified herein:
1. When offered for transportation in one package, or in a transport vehicle if not packaged,
and when the quantity of the material therein equals the reportable quantity;
Q. Hazardous Waste: Any HAZMAT or hazardous chemical that has been used, contaminated,
spilled, and recovered, and is impossible to reuse, recycle or treat. This term also refers to
residues generated as a result of recycling activities and empty containers whose previous
contents were hazardous.
R. Incompatible: Any two materials, which create a violent reaction when combined.
S. Installation: The military base, post, depot, etc. on which the Project is located.
U. Material Safety Data Sheet: A report detailing the hazardous characteristics and dangers of a
specific material.
V. NAF Work Force: NAF employees or their Contractors who perform projects on the Installation.
W. Permitted: An activity approved by an authority with official control over the activity.
AA. Resource Conservation and Recovery Act (RCRA: The Federal Act, which gives the EPA
environmental protection regulation and enforcement authority concerning hazardous waste
(HW) and associated activities.
EE. Training: Formal instruction, in addition to existing job knowledge, designed to protect human
health and the environment by increased awareness and improved job proficiency.
A. DOD Instructions, Policies, Guidance Documents, Memoranda, and Regulations: Comply with
the following:
B. United States Environmental Protection Agency(EPA) Regulations: Comply with the following:
C. Occupational Safety and Health Administration (OSHA) Regulations: Comply with the following:
F. [Other State, Regional, Local and Installation Plans, Policies, Regulations, and Permitting
Procedures: Comply with the following:
2. State Regulations:
PART 3 - EXECUTION
A. Protection of natural resources: Comply with applicable regulations and these specifications.
Preserve the natural resources within the Project boundaries and outside the limits of
permanent Work performed under this Contract in their existing condition or restore to an
equivalent or improved condition as approved by Owner.
B. Provide protection, operate temporary facilities, and conduct construction in ways and by
methods that comply with environmental regulations, and minimize the possibility of
contamination, pollution, or other undesirable effects.
B. Contractors shall ensure all company-owned and employee owned gasoline and diesel vehicles
driven on the Installation comply with the emissions inspection requirements of the Department
of Public Health and Environment (DPHE) Motor Vehicle Emissions Inspection Program and
Reduction of Diesel Vehicle Emissions.
C. The Contractor shall restrict emissions of all smoke and fugitive particulates, to levels less than
20 percent opacity at the point of emission, and to levels that do not visibly disperse beyond the
Installations property boundaries unless exempt.
D. The Contractor shall ensure any equipment containing ozone-depleting chemicals (ODC) are
operated and maintained in accordance with States Control of Emission of Ozone-Depleting
Compounds requirements. Train and certify all contractors and subcontractor employees
servicing ODC containing equipment.
E. The Contractor shall take active steps to prevent evaporation of all solid or liquid materials that
have potential to become airborne including but not limited to fuels, solvents, paints, and other
volatile chemicals under the Contractors control. Close all containers holding solid or liquid
materials that have potential to become airborne at all times, except when adding product to or
removing product from the container.
F. The Contractor shall fully comply with the conditions of all applicable air quality permits and
applicable air quality requirements. Local and State Regulations of Air Pollution Prevention and
Control Act.
G. The Contractor shall comply with all requirements of Fugitive Particulate Control Plans required
by and prepared for DPHE.
I. The Contractor shall maintain a daily log of fugitive particulate emissions that exceed 20 percent
opacity or that cause visible emissions crossing the Installations property boundaries. The
Contractor shall maintain a copy of this log on site at all times and shall make it available for
review to the Installation upon request.
J. The Contractor shall not utilize cutback asphalt or any coating included in the definition of
cutback asphalt during the months of March through September unless the cutback asphalt is
used solely as a penetrating prime coat or if the user can demonstrate to DPHE Air Pollution
Control Division that under the conditions of its intended use, there shall be no emissions of
volatile organic compounds to the ambient air.
K. Contractors shall not apply sand or gravel to Installation roads without obtaining prior written
approval from the Contracting Officer.
L. The Contractor shall submit copies of all fugitive particulate emission logs, and any other logs
required by Fugitive Particulate Control Plans, to the Contracting Officer no later than seven
working days after completion of work.
M. The Contractor shall properly re-vegetate all disturbed land to prevent fugitive particulate
emissions following the completion of work.
A. Comply with regulations including but not limited to 40 CFR 122.26 (EPA NPDES Permit
Regulations), state and local wastewater regulations, COE document EO 1165-2-304 (1976
Flood Plain Regulations for Flood Plain Management), EPA document 832-R-92-005 (Storm
Water Management for Construction Activities), state and local Stormwater regulations, the
County Drainage Plan and the City/County Drainage Criteria Manual.
1. Be familiar with all relevant requirements of permits held by the Installation. Applicable
Installation permits include <INSERT TITLE & NUMBER>. These permits are available
for review at <INSERT LOCATION>.
2. Not discharge wastewater or water (including surface discharges and underground
injection) that could impact the quality of the surface water or groundwater of the state
without prior approval of the Installation Environmental Office.
3. Implement basic housekeeping provisions of the applicable wastewater discharge permit
including monitoring and sampling, inspections, reporting, and record keeping.
4. Dispose of sewage through existing connections to the Installation sanitary sewage
system. Where such connections are not available, use chemical toilets or comparably
effective units; periodically, have these toilets serviced by a licensed contractor in
accordance with all applicable regulations. Do not dispose of sanitary waste into the
sewage system without approval of the Installation.
C. Concerning construction projects that shall disturb greater than or equal to one (1) acres,
Contractor shall:
7. Once approved by the Installation, the NOT shall be co-signed by the Installation and the
Contractor, and the Installation shall submit it to the EPA or state permit authority.
D. Concerning construction projects that shall disturb less than one acre, the Contractor shall:
E. Regardless of the size of the project, storm water runoff from the Project site shall be restricted
to historical flows during and after construction. The Contractor shall submit for approval
devices/designs to comply with this condition to the Contracting Officer. Structural BMPs may
include but are not limited to mulch, grass, stockpile covers, silt fences, inlet protection, check
dams, stabilized construction entrances, and sediment traps. Non-structural BMPs may include
but are not limited to minimizing disturbances, preserving natural vegetation, and good
housekeeping practices.
1. Following each storm event of 0.1 inch or greater or at least weekly, the Contractor shall
inspect erosion and pollution control devices and correct any deficiencies immediately.
Record these inspections and records maintained onsite.
2. To ensure compliance with other Clean Water Act requirements, the Construction
Contractor:
A. All hazardous materials brought on-site by the Construction Contractor shall be subject to pre-
approval by the Installation. The Installation reserves the right to prohibit the use of hazardous
materials it deems to be especially hazardous to human health or the environment. The
Installation also reserves the right to prohibit the use of hazardous materials due to the type
and/or quantity of hazardous wastes potentially generated from the materials. In the event of
disapproval of a hazardous material for use on the Installation, the Installation may provide the
Construction Contractor a list of suitable substitutes; however, the Construction Contractor shall
retain responsibility for finding an acceptable substitute. The Installation promotes waste
minimization and pollution prevention practices and all contractors shall take appropriate actions
to comply with this policy.
B. Hazardous materials requirements are designed to ensure the Installation meets and maintains
compliance with:
C. Current Conditions:
1. Review of Installation documentation has identified that the following hazardous material
conditions are currently present at the Project location: <INSERT CONDITIONS>.
1. A minimum of ten working days prior to commencement of work on site, submit to the
Contracting Officer a listing of hazardous materials on site during the performance of the
Contract. Include estimated usage and estimated quantities for each hazardous material.
The Contractor shall identify any "extremely hazardous substances" (40 CFR Part 355,
1. Contracts with a performance period of less than or equal to ninety (90) days:
Construction Contractors shall immediately report hazardous materials used at any time
during the execution of the Contract to the Contracting Officer. The report shall include a
listing of the total amount hazardous materials used while performing work on site and a
description of the disposition of each hazardous material (e.g., fully consumed during
Contract/Project execution, saved for future use, or disposed of as hazardous waste in
accordance with state and local hazardous waste regulations for generators,
transporters, and treatment, storage, and disposal facilities).
2. Contracts with a performance period of greater than ninety (90) days: Every 90 days
from the start of work on site, the Construction Contractor shall report to the Contracting
Officer hazardous materials used in the previous 90 day period. The report, submitted ten
(10) working days after the end of each ninety (90) day period, shall include a listing of all
hazardous materials used while performing work on site, the total amount of each
hazardous material used, and a description of the disposition of each hazardous material
(e.g., fully consumed during Contract/Project execution, saved for future use, or disposed
of as hazardous waste in accordance with state hazardous waste regulations for
generators, transporters, and treatment, storage, and disposal facilities).
F. Final Report:
1. The Construction Contractor shall submit a final inventory of all hazardous materials used
since the last hazardous usage report no later than ten working days after completion of
work. The final inventory shall list all hazardous materials used, total amount of each
used, and a description of the disposition of any remaining hazardous materials (e.g.,
fully consumed during Contract/Project execution, saved for future use, or disposed of as
hazardous waste in accordance with state hazardous waste regulations for generators,
transporters, and treatment, storage, and disposal facilities).
1. Construction Contractors shall transport and store all known or potentially hazardous
materials in original containers with manufacturer labels meeting the OSHA Hazard
Communication requirements (29 CFR 1910.1200). Repackage or place bulk materials
and materials into different containers at the job site and clearly label in accordance with
OSHA Hazard Communication requirements (29 CFR 1910.1200). Do not bring
materials without proper, legible labeling to the Installation.
2. The Construction Contractor shall only use and store hazardous materials in areas that
are free from obstructions or hazards such as tripping hazards, fire, standing water, or
pests. All hazardous materials shall be separated in accordance with OSHA Material
Handling requirements (29 CFR 1910.176[c]) and OSHA Hazard Communication
requirements (1910.1200[b], and 1910.1200[f]).
3. The Construction Contractor shall store hazardous materials in containers that are in
good condition, with no leaks or rust.
A. Construction and demolition debris consists of the materials generated during the construction,
renovation, and demolition of buildings, roads, and bridges. Construction and demolition debris
often contains bulky, heavy materials that include:
1. Concrete,
2. wood (from buildings),
3. asphalt (from roads and roofing shingles),
4. gypsum (the main component of drywall),
5. metals,
6. bricks,
7. glass,
8. plastics,
9. salvaged building components (i.e. doors, windows, and plumbing fixtures)
10. trees, stumps, earth, and rock from clearing sites.
B. Reducing and recycling construction and demolition debris conserves landfill space, reduces
the environmental impact of producing new materials, creates jobs, and can reduce overall
building Project expenses through avoided purchase/disposal costs. The overall intent of the
recycling content of the Project shall be reconciled with the specific sustainable design
requirements of the Project.
C. The waste requirements are designed to ensure the Installation meets and maintains
compliance with:
D. If the Construction Contractor generates solid wastes during the execution of a Contract, the
Construction Contractor shall prepare a Solid Waste, Construction, and Demolition Debris
Waste Management plan utilizing an outline provided by CEV and provide this plan to the
Contracting Officer ten (10) working days before commencement of construction activities.
Among other things, this plan shall document the extent to which waste materials can be
recycled and identify the disposal/recycling pathway. In-house and troop forces shall comply
with all the requirements contained in the Installation Solid Waste, Construction, and Demolition
1. Integrate generated solid waste into the Installation recycling process as appropriate. The
Construction Contractor shall utilize local sources for recycling as much as possible.
2. Provide, as applicable, Installation with a plan for the disposal of medical waste.
3. Prepare and submit to the Contracting Officer a "Solid Waste Disposal Report" on a
quarterly basis. This report shall itemize the type and amount of solid waste, by disposal
category (e.g., recycled, land filled, reused) that was disposed of during the previous
quarter.
4. Dispose of bulky wastes and demolition debris properly (e.g., automobile bodies,
furniture, and appliances are required to be salvaged or crushed so as to minimum the
volume of waste). Scrap tires may only be disposed of at approved solid waste disposal
facilities.
5. Place all solid waste in a solid waste dumpster or roll-off provided by the Construction
Contractor.
6. Place contaminated reusable sharps and other regulated wastes in puncture resistant,
color coded, leak proof containers, as soon as possible after use and until properly
reprocessed. Place specimens of blood or other potentially infectious materials in a
container that prevents leakage during collection, handling, processing, storage,
transport, or shipping. Specific labeling and handling requirements are to be followed (29
CFR 1910.1030[d]). The Construction Contractor shall also comply with the packaging,
storage and labeling requirements specified in States solid waste regulation if the
Contractor generates infectious wastes.
7. To the extent practicable and as applicable, collect compost materials (organics,
vegetation, grass, wood debris, etc.) and arrange with the Installation to utilize the
material in its composting program. To the extent practicable and as applicable and if
economically feasible, sort and recycle wood debris by three categories: painted,
pressure treated, or creosote treated.
8. Dispose of sewage through existing connections to the Installation sanitary sewage
system. Where such connections are not available, use chemical toilets or comparably
effective units; periodically, have these toilets serviced by a licensed Contractor in
accordance with all applicable regulations. Do not dispose of sanitary waste into the
sewage system without approval of the Installation.
9. For projects requiring offsite disposal of solid waste, disposal shall be to land fills holding
a valid State Waste Disposal Permit.
10. The Installation has the following disposal facilities available for use by the Construction
Contractor: <INSERT FACILITY LOCATION, USE, RESTRICTIONS, AND CONTACT
INFORMATION>.
A. The National Historic Preservation Act of 1966 (NHPA) Title 16 United States Code (U.S.C.)
Section 470, establishes the role of the Federal government, in cooperation with other nations
and in partnership with the States, local governments, Indian tribes, and private organizations
and individuals regarding significant cultural resources. These specific roles are outlined in
Sections 402, 110, 111, and 106. Among these are standing architectural features (districts,
buildings, structures, and objects) and archaeological sites.
B. The Installation has determined that historic or cultural resources exist within the Project site.
The following activities and precautionary measures shall be conducted to prevent harm to
these resources: <INSERT PROTECTIVE MEASURES>.
A. General:
1. Construction activities impacting wildlife habitat shall be planned outside of the primary
breeding and nesting periods whenever possible. Impacts to aquatic resources shall be
planned during low flow periods and outside of primary spawning seasons.
2. Workers shall not harm or harass any wildlife species.
3. Pesticide use shall be in accordance with the Installations Pesticide Management Plan
and according to all product labels. The Pesticide Management Plan may have
restrictions not found on labels that protect sensitive habitats or endangered species.
4. The Construction Contractor shall return the staging area to its original condition upon
completion of the work. Returning the staging area to its original condition may require,
among other things, revegetation and remediation. Perform the work at the Construction
Contractors expense.
5. Construction Contractors shall minimize, to the extent possible, the creation of new roads
and trails around Project areas. Any such trails/roads shall be rehabilitated and re-
vegetated by the Construction Contractor when the Project is completed.
1. Section 404 and Section 10 of the Clean Water Act regulate dredge and fill operations
within Waters of the United States. The United States Army Corps of Engineers
(USACE) has jurisdiction over activities affecting Waters of the United States including
special aquatic areas such as wetlands.
2. USACE Permit Number <INSERT PERMIT NUMBER> has been obtained for
construction activities and is presented <INSERT ATTACHMENT OR APPENDIX
IDENTIFIER>. The Construction Contractor will adhere to the conditions set forth in this
permit.
3. All water crossings and wetland impacts shall be limited to the least amount possible.
4. Mats shall be used for large equipment working in wetlands. This will limit vegetation and
soil disturbances.
5. Construction areas and staging areas near wetlands and streams shall contain ample
storm water controls to avoid sediment or other pollutants from reaching these waters.
6. Construction within a designated 100-year floodplain is required to adhere to any local
floodplain permits or ordinances.
1. The Endangered Species Act of 1973, as amended, requires all federal actions be
assessed for potential impacts to species designated as threatened or endangered by the
Department of the Interior.
2. The Installation has identified that the following protected species may be present within
the Project area: <INSERT SPECIES NAMES>. The following restrictions and protective
measures shall be taken to ensure that construction activities do not affect these species
<INSERT RESTRICTIONS AND PROTECTIVE MEASURES>.
a. All site personnel shall be instructed by the Installation as to the reason for, and
importance of, limiting impacts to vegetated habitat outside the work area.
D. Construction Timber:
1. All projects on the Installation for which removal of trees is a requirement shall be
coordinated with and approved by the Installations Natural Resource POC. In
accordance with Department of Defense Instruction (DODI) 4715.3, DODI 7310.1, and
AFI 32-7064 Section 8.3, forest products shall not be given away, abandoned, destroyed,
or used to offset Contract costs.
2. All merchantable wood products [i.e. stems and limb wood equal to or greater than 4
(four) inches in diameter] that result from projects on the Installation proper shall have all
limbs removed and be delivered to the Installations wood yard if one exists. Such
deliveries shall be coordinated with the Installations Natural Resource POC to allow
access to the wood yard. Leaving wood outside the wood yard fence is strictly
prohibited.
3. All limb wood (to include stem wood) less than four inches in diameter produced in the
completion of projects on Installation shall be delivered to the Installations compost yard.
Responsible parties shall contact the Installations Natural Resource POC to coordinate
delivery. Leaving limb wood outside of the compost yard fence is strictly prohibited.
However, projects involving small amounts of limb wood may dispose of the wood by
broadcasting it at the site if prior coordination has been made with the Natural Resource
POC. In such cases, the limbs shall be lopped so as not to exceed twelve inches above
ground level.
4. If no compost or wood yard exists on the Installation, the Contractor shall coordinate
proposed off-site disposal methods and locations with the Installations Natural Resource
POC.
5. Any and all stumps that are to remain on site shall be cut as close to ground level as
practical, not to exceed six (6) inches above ground level. Tree branches that obstruct
the movement of equipment shall be cut flush to the trunk. The remaining portions of
limbs broken by the passage of equipment shall be cut back flush to the trunk.
6. Any and all stumps with attached root masses shall be disposed of off Installation
property to an approved landfill unless specifically authorized by the Installations Natural
Resource POS. Proper disposal of such stumps is the exclusive responsibility of the
Contractor responsible for the Project.
7. In the event of a bona fide emergency outside of normal duty hours, trees may be
removed if absolutely necessary without consulting the Installations Natural Resource
POC. All other provisions, however, remain in effect with regard to disposal of wood
products at the earliest opportunity.
8. Removal of forest products without a permit from the Installation constitutes theft of
government property.
1. Consult the Installations Vegetation Management Plan and Integrated Natural Resource
Management Plan for seed mixes for re-vegetating disturbed areas. Construction
a. Seeding Dates: The type of seed mixtures to be used will be affected by the
planting season. Normal seeding shall occur during seasons with ample rainfall
and temperature to promote growth. If planting during the dry season supplemental
irrigation of 0.5 inches/week shall be provided during the first growing season to
promote seedling survival, unless otherwise stated by the Installation.
b. Seeding Methods: Drill seeding or broadcast seeding shall be used depending on
the slope of the disturbed site and the size of the area.
1) Slopes less than 3:1: Seed shall be drilled using a rangeland or grass drill
with a small seed/legume box and an agitator box for fluffy or bulky seed.
Seed rows shall be spaced 7-10 inches apart, and planted 0.5 to 0.75
inches deep. The drill shall have double disk furrow openers with depth
bands and packer wheels. Seeding shall be accomplished by following the
contour of the slope. The drill shall be calibrated each day or whenever
changing seed mixes to ensure even seed distribution.
2) Slopes greater than 3:1 and areas less than 0.5 acre: Seed shall be
broadcast by hand, mechanical spreader, or hydraulic equipment.
Broadcast seeded areas shall be raked or harrowed to incorporate the seed
into the soil at a depth not exceeding 0.75 inches. Seed shall not be mixed
in a tank with hydromulch and broadcast.
3) Mulching: Weed-free native hay, weed-free straw, virgin wood fiber
hydromulch, or erosion control blankets shall be used to promote
germination and seedling establishment. Native hay, straw, or hydromulch
shall be applied at 2000 pounds/acre on slopes less than 3:1. Native hay or
straw shall be crimped into the soil to a depth of 3-4 inches, and shall
protrude above the ground 3-4 inches. Hydromulch shall be applied using
the recommended rate of an organic tackifier. Erosion control blankets shall
a. Protection: Protect existing trees which are to remain from injury, bruise, defacing,
or other damage from construction operations. Remove displaced rocks. By
approved excavation, remove trees with 30 percent or more of their root systems
destroyed.
b. Replacement: Remove trees and other landscape features scarred or damaged
by construction operations, and replace with equivalent, undamaged trees and
landscape features. Obtain Contracting Officer's approval before replacement.
c. On February 3, 1999, the President issued Executive Order 13112 to prevent the
introduction of invasive species and provide for their control, and to minimize the
economic, ecological, and human health impacts. All landscaping shall consist of
native, non-invasive species.
A. Polychlorinated Biphenyls (PCBs) are mixtures of synthetic organic chemicals with the same
basic chemical structure and similar physical properties ranging from oily liquids to waxy solids.
Due to their non-flammability, chemical stability, high boiling point and electrical insulating
properties, PCBs were used in hundreds of industrial and commercial applications including
electrical, heat transfer, and hydraulic equipment; as plasticizers in paints, plastics and rubber
products; in pigments, dyes and carbonless copy paper and many other applications. More than
1.5 billion pounds of PCBs were manufactured in the United States prior to cessation of
production in 1977.
B. Concern over the toxicity and persistence in the environment of PCBs led Congress in 1976 to
enact 6(e) of the Toxic Substances Control Act (TSCA) that included among other things,
prohibitions on the manufacture, processing, and distribution in commerce of PCBs. Thus,
TSCA legislated true "cradle to grave" (i.e., from manufacture to disposal) management of
PCBs in the United States.
C. Provide certification that all persons or entities under Contractor control have had awareness
training to recognize the potential presence of PCBs that may be encountered during conduct of
service or construction Contracts.
D. Contractor and all subcontractors shall prepare a written procedure outlining the notification
process between their employees/subcontractors/agents and Contractor management and to
the Contracting Officer informing of the presence of PCBs not identified beforehand. All
construction workers that handle the PCBs and/or PCB wastes shall be trained of PCBs and
hazards associated with PCBs and also trained in accordance with OSHA 40-hour
HAZWOPER.
F. Should the Contractor encounter previously unidentified or unanticipated suspect PCB items,
that must be disturbed, the Contractor shall cease that work which would disturb the suspect
items and shall immediately notify the Contracting Officer. The Installation shall evaluate the
extent to which there are cost impacts to abatement and disposal and take steps as necessary
to resolve the issue.
3.9 RADON
A. Radon (chemical symbol Rn) is a naturally occurring radioactive gas found in soils, rock, and
water throughout the U.S. It has numerous different isotopes, but radon-220, and -222 are the
most common. Radon causes lung cancer, and is a threat to health because it tends to collect
in homes, sometimes to very high concentrations. As a result, radon is the largest source of
exposure to naturally occurring radiation.
B. The Radon requirements are designed to ensure the Installation meets and maintains
compliance with 40 CFR Part 61, Subpart I.
C. The Project site <DOES OR DOES NOT> have Radon concerns. The following measures will
be taken to ensure public and worker safety: <INSERT MEASURES TO ENSURE PUBLIC AND
WORKER SAFETY DURING CONSTRUCTION, AND POTENTIAL LONG-TERM MITIGATION
MEASURES TO BE INCORPORATED INTO THE DESIGN>.
A. The Hazardous Material Assessment for the Project indicates Lead Based Paint / Paint with
Lead requiring remediation. Comply with Division 02 Section Lead Remediation.
B. The Hazardous Material Assessment for the Project indicates no Lead Based Paint / Paint with
Lead (LBP/PWL) requiring remediation encountered in the investigation. Notify Governments
Designated Representative immediately if LBP/PWL or suspected LBP/PWL is encountered.
3.11 ASBESTOS
A. The Hazardous Material Assessment for the Project indicates Asbestos Containing Material
requiring remediation. Comply with Division 02 Section Asbestos Remediation.
B. The Hazardous Material Assessment for the Project indicates no Asbestos Containing Material
(ACM) requiring remediation encountered in the investigation. Notify Governments Designated
Representative immediately if ACM or suspected ACM is encountered.
A. General:
1. Spill prevention and response requirements are designed to ensure the Installation meets
and maintains compliance with:
2. Spill response and reporting procedures and liability requirements are designed to ensure
the Installation meets and maintains compliance with:
3. The Requirements for Petroleum, Oil, & Lubricants are designed to ensure the
Installation meets and maintains compliance with:
B. Responsibility:
1) Contractor name.
2) Mailing address.
3) Primary and alternate contacts.
4) Contacts phone numbers (land line plus mobile if available).
5) Contacts pagers.
6) Contacts fax number.
2. Submit the completed SPRP plan to the Contracting Officer a minimum of ten working
days prior to commencement of work for review and approval. The Installation will make
a copy of its SPRP plan available to the Construction Contractor, upon request, to use as
a guide in preparing their SPRP. The Construction Contractor may not adopt the
Installations SPRP as the Construction Contractors SPRP without the addition of
Construction Contractor specific information as outlined above.
1. The Construction Contractor shall manage, store, and use all hazardous materials
(including fuels) in accordance with good engineering practices and implement best
management practices in order to prevent spills and releases. The Construction
Contractor shall report spills to the Installation and execute timely and appropriate actions
to contain and cleanup all spills in accordance with the Contractor SPRP plan and the
Installation SPRP. The Installation does not authorize the Construction Contractor
employees to provide emergency response nor clean up actions beyond the level of
training of their employees. Once a spill or release of a hazardous material managed,
used, or stored by the Construction Contractor has been contained, the Installation shall
determine if additional cleanup is required and the extent of the Contractors
responsibility. The Construction Contractor shall be liable for any direct and indirect
costs incurred during spill response and clean-up, including but not limited to
administrative costs, materials, labor, equipment, shipping, packaging, testing,
replacement equipment and materials, and disposal.
2. Construction Contractor-owned tanks used for vehicle or equipment refueling shall only
be allowed to exist at the Installation if approved by the Contracting Officer. Construction
Contractors requesting permission to stage a fuel tank on the Installation shall do so in
writing to the Contracting Officer. Construction Contractors shall prepare a Spill
Prevention Control and Countermeasure Plan (SPCC) and submit it with their request to
stage a fuel tank. The Construction Contractor shall not use aboveground tanks with an
individual capacity of greater than 660 gallons.
3. During fuel transfers, the Contractor shall utilize spill containment devices and have spill
containment materials available.
4. The Construction Contractor is prohibited from performing routine servicing of vehicles
such as oil changes or brake fluid changes on Installation property.
5. The Construction Contractor is prohibited from using oil on roadways or other surface
areas for dust suppression.
6. The Construction Contractor shall not release secondary containment water when oil
sheen is present. The Contractor shall collect contaminated containment water and make
arrangements with the Installation Environmental Office for its proper disposition.
10. The Construction Contractor managing POLs at the Installation is subject to local and
state oil and petroleum spill prevention requirements including but not limited to the
following reporting requirements:
11. The Construction Contractor shall report a release of oil that enters or may enter "waters
of the state" including surface waters, groundwater, dry gullies, or storm sewers leading
to surface waters to Local and State Department of Public Health and Environment
(DPHE) immediately, the Installation Environmental Office shall also be notified.
12. The Construction Contractor shall report releases of oil to land greater than 25 gallons to
the state immediately and notify the Installation Environmental Office.
13. The Construction Contractor shall not mix used oil with characteristic hazardous waste
(e.g. gasoline) since the mixing constitutes hazardous waste treatment and requires a
permit.
END OF SECTION
his visual inspection and reviewed the results of his final clearance air quality monitoring and verifies that,
to the best of his knowledge and belief, the above representations by the Contractor's Representative are
by: _______________________________________________________________________________
Signature Date
____________________________________________________________________________
Printed Name
____________________________________________________________________________
Printed Title and Firm
that the construction completed under the contract (Government Contract No.____________________ )
is free and clear of building materials and products containing regulated quantities of asbestos and/or
lead-based paints. I have determined the above based on product labels, manufacturer's information,
submittal documents for specified materials, and other information available to me. The Contractor's
representative further acknowledges and accepts that if it is later found that the Contractor has
intentionally defrauded or misrepresented these facts, then the Contractor assumes total and complete
liability for fines, penalties and/or abatement and removal of these materials at the direction of the
Government.
by: _________________________________________________________________________________
Signature, Contractor or Authorized Representative Date
______________________________________________________________________________
Printed Name
______________________________________________________________________________
Printed Title and Firm
GOVERNMENT INSPECTOR'S CERTIFICATION
The Government's Inspector hereby certifies and attests that, to the best of knowledge and belief, the
above representations by the Contractor's representative are true and correct.
by: _________________________________________________________________________________
Signature Date
______________________________________________________________________________
Printed Name
______________________________________________________________________________
Printed Title and Firm
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Installation of refrigerant.
2. [Removal of refrigerant.]
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
1.3 SUBMITTALS
1.4 QUALIFICATIONS
A. Installer: Company specializing in performing the work of this Section with minimum three years
documented experience.
A. Conform to IMC.
1. The Contractor is responsible for safe handling, dismantling, removal, and disposal of all
refrigeration equipment identified for removal as part of the Contract Documents unless
otherwise specified. Prior to dismantling and removal of refrigeration equipment, the
Contractor will recover all refrigerants for recycling by transferring to an approved
external vessel or certified recycling or recovery machine.
1. Furnish and maintain a refrigerant log book for recording refrigerant transfers.
2. In the log book itemize services performed, actions taken, and amount of refrigerant
added to or removed from each system installed, or affected, or removed by this Project.
3. The Refrigerant Log Book is a three-ring loose leaf binder containing a table of contents
and a separate Refrigerant logging form for each piece of refrigeration and HVAC
equipment (see sample form).
1. Duration: Establish the Refrigerant Log Book at the start of construction and
continuously maintain and keep current until completion of the warranty portion of the
Contract.
2. Location of Refrigerant Log Book: During the construction period, keep the log book in
the possession of the Contractor at the construction site. After construction is completed,
keep the log book in the Commissary Store Directors Office.
3. Project Close-out: Upon completion of the construction portion of the Project, furnish two
updated copies of the log book to DeCA/PM/FM. Then, turn the original log book over to
the Commissary Store Director.
END OF SECTION
Date installed:
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for additional indoor air quality
requirements.
2. Division 01 Section Environmental Management for definitions and general requirements.
3. Division 23 Section Testing, Adjusting, and Balancing for HVAC for baseline testing for
Indoor Air Quality.
1.2 DEFINITIONS
A. Type 1 Finishes: Materials and finishes which have a potential for short-term levels of off
gassing from chemicals inherent in their manufacturing process, or which are applied in a form
requiring vehicles or carriers for spreading which release a high level of particulate matter in the
process of installation and/or curing. Type 1 Finishes include, but are not limited to the
following:
1. Composite wood products, specifically including particleboard from which millwork, wood
paneling, doors or furniture may be fabricated.
2. Adhesives, sealants, and glazing compounds, specifically those with petrochemical
vehicles or carriers.
3. Wood preservatives, finishes, and paint.
4. Control and/or expansion joint fillers.
5. All hard finishes requiring adhesive installation.
6. Gypsum board and associated finish processes.
B. Type 2 Finishes: "Fuzzy" materials and finishes which are woven, fibrous, or porous in nature
and tend to adsorb chemicals off gassed by Type 1 finishes or may be adversely affected by
particulates. These materials become chemical binder for organic/aromatic compounds which
may be released much later, or collectors of contaminants that may promote subsequent
bacterial growth. The chemicals off gassed by Type 1 finishes may combine with chemicals in
Type 2 finishes to alter both chemical constituents or even polymerize. Type 2 Finishes include,
but are not limited to the following:
C. Materials that can be categorized as both Type 1 and Type 2 materials shall be considered to
be Type 1 materials.
1.3 SUBMITTALS
1. Show sequence of finishes applications and allowances for curing times. Within each air
zone identify finishes, indicating their type classifications.
a. An air zone is that part of any floor area served by a single air handling unit.
2. Indicate and schedule types and durations of temporary ventilations proposed. Show
schedule for commissioning procedures and all temporary usages of building mechanical
systems, identifying types of filtration used and schedule of filter replacement and
changeouts.
B. Material Safety Data Sheets (MSDSs): Requirements for submittal of MSDSs are specified in
the individual specification sections of this Project Manual as required.
A. General: Perform the work of this Section as a supplement to and in accordance with applicable
requirements of Division 01 Section Quality Control.
PART 3 - EXECUTION
3.1 PREPARATION
A. Certify in writing to the Governments Designated Inspector that interior environmental control
has been implemented as specified below and that required conditions are being maintained,
B. Coordination: Schedule and coordinate the work of all finishes installers to assure compliance
with the requirements of this Specification Section.
A. Provide and maintain controlled interior environment in accordance with the following
requirements before beginning installation of interior finish materials in order to dilute and
exhaust vapors produced by solvents and other carriers from liquid applied materials, and
particulate matter from residual manufacturing chemicals contained in solid products.
B. Implement guidelines as identified in the Sheet Metal and Air Conditioning Contractors National
Association, Inc. (SMACNA) "IAQ Guidelines for Occupied Buildings Under Construction"
Current Edition. The intent is to prevent any indoor air quality problems to building occupants
during construction. Isolate all areas of construction from Commissary operations. Remove all
hazardous materials prior to starting work. If hazardous materials are found, identified, or
suspect, cease work and mitigate the hazardous material concern. Do not continue with
contract work until the space has been cleared by a PE or Certified Industrial Hygienist for
occupancy.
C. Supply 100 percent outside air 24 hours a day. Supply airflow at 6 air changes per hour when
outside temperature is between 55 deg F and 85 deg F and humidity is between 30 percent and
60 percent.
1. Supply a minimum of 1.5 air changes per hour when outside conditions are not within the
range above. To meet desired volumetric air changes for dilution ventilation, Contractor
may use the exhaust air as makeup air if the following requirements are met:
2. The supply air system shall have filters in place. Maintain filtration efficiency of 30
percent unless higher efficiency is required by other Contract Documents.
3. The HVAC system may be used to move both supply and return air if the following
requirements are met:
a. Permanent return air ductwork and heating and cooling coils shall be cleaned per
National Air Duct Cleaners Association standards upon completion of all
construction and finish installation work and before beneficial occupancy of the
Project or Phase by the Government.
E. Pre-commissioning and commissioning procedures for HVAC systems, including duct cleaning
and filter replacement prior to release of the Project or Phase to the Government for occupancy,
are specified in Division 23 Sections and by reference above to SMACNA "IAQ Guidelines for
Occupied Buildings Under Construction" - Current Edition.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Definitions.
2. Specification format and content explanation.
3. Industry standards.
1.2 DEFINITIONS
A. "Indicated": The term "indicated" refers to graphic representations, notes, or schedules on the
drawings, or paragraphs or schedules in the Specifications and similar requirements in the
contract documents. The use of terms such as "shown," "noted," "schedule," and "specified"
help the reader locate the reference. Location does not limit.
C. "Approved": The term "approved" when used in conjunction with the Contracting Officer's action
on the contractor's submittals, applications, and requests, refers only to the Contracting Officer's
duties and responsibilities as stated in the Conditions of the Contract.
D. "Regulations": The term "regulations" include laws, ordinances, statutes, and lawful orders
issued by authorities having jurisdiction, as well as rules, conventions, and agreements within
the construction industry that control performance of the work.
E. "Furnish": The term "furnish" means supply and deliver to the project site, ready for unloading,
inspection, inventory, unpacking, assembly, installation, and similar operations.
F. "Install": The term "install" describes operations at the project site including the actual
unloading, temporary storage, unpacking, assembly, erecting, placing, anchoring, applying,
working dimension, finishing, curing, protecting, cleaning, and similar operations.
G. "Provide": The term "provide" means to furnish and install, complete and ready for the intended
use.
H. "Installer": An installer is the contractor or another entity engaged by the contractor, either as
an employee, subcontractor, or contractor of lower tier, to perform a particular construction
activity, including purchasing, installation, erection, application, or similar operations. Installers
must possess experience in the operations they perform.
1. The term "experience" when used with the term "installer" means having a minimum of 5
previous projects similar in size and scope to this project, being familiar with the special
I. "Project Site": The space available to the contractor for performing construction activities, either
exclusively or in conjunction with others performing work as part of the project.
M. Products: Items purchased for incorporating into the work. The term "product" includes the
terms "material," "equipment," "system," and terms of similar intent.
A. Specification Format: The organization of these specifications into Divisions and Sections
follow CSI's 48-Division format and Master Format numbering system.
B. Specification Content: This specification uses certain conventions regarding the style of
language and the intended meaning of certain terms, words, and phrases when used in
particular situations or circumstances. These conventions are as follows:
a. Imply the words "shall be" where a colon (:) is within a sentence or phrase.
A. Applicability of Standard: Except where the contract documents include more stringent
requirements, applicable construction industry standards have the same force and effect as if
bound or copied directly into the contract documents to the extent referenced. Such standards
are a part of the contract documents by reference.
B. Publication Dates: Comply with the standards in effect as of the issue date of the Solicitation
except comply with standards having different revision dates as referenced in the Building Code
indicated in Division 01 Section Summary of Work.
C. Conflicting Requirements: Where the contract documents specify compliance with 2 or more
standards and the standards establishes different or conflicting requirements for minimum
quantities or quality levels, comply with the most stringent requirement. Before commencing,
refer to the Contracting Officer for a decision on requirements that are different but apparently
equal, and where it is uncertain which requirements are the most stringent.
1. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified is
the minimum acceptable. The actual installation may comply exactly with the minimum
quantity or quality specified, or it may exceed the minimum within reasonable limits. To
comply with these requirements, indicated numeric values are minimum or maximum, as
appropriate, for the context of the requirements. Refer uncertainties to the Contracting
Officer for a decision before proceeding.
D. Copies of Standards: Require each entity engaged in construction on the project to be familiar
with industry standards applicable to its construction activity. The contract documents do not
contain bound copies of applicable standards.
E. Abbreviations and Names: Abbreviations frequently occur in trade association's names and
titles of general standards. The use of such acronyms or abbreviations in the specifications or
other contract documents, mean the recognized name of the trade association, standard-
generating organization, authorities having jurisdiction, or other entity applicable to the context
of the text provision. Refer to Thompson Gales "Encyclopedia of Associations" or Columbia
Books "National Trade & Professional Associations of the U.S."
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Quality control.
2. Field engineering.
3. Sample forms and reports.
1.2 REFERENCES
A. The publications listed below form a part of this Specification to the extent referenced. The
publications refer to the text by the basic designation only.
1.3 SUBMITTALS
B. Submittal Schedule:
C. Submittal List:
A. QC Program Requirements:
B. QC Organization:
1. QC Manager:
1. Requirements: Within ten (10) from Notice to Proceed, provide for approval by the
Contracting Officer, a QC plan that covers both on-site and off-site work and includes the
following:
2. Preliminary Work Authorized Prior to Approval: The only work authorized to proceed
prior to the approval of the QC Plan is mobilization of storage and office trailers and
surveying subject to Division 01 Section Temporary Facilities and Controls.
3. Approval: Obtain approval of the QC Plan prior to the start of construction. The
Contracting Officer reserves the right to require changes in the QC Plan and operations
as necessary to ensure the specified quality of work. The Contracting Officer reserves
the right to interview any member of the QC organization at any time to verify his/her
submitted qualifications.
4. Notification of Changes: Notify the Contracting Officer, in writing, of any proposed
changes, including changes in the QC organization personnel, a minimum of seven
calendar days prior to a proposed change. The Contracting Officer must approve
proposed changes and reserves the right to deny the proposed change.
1. Participate in the development of a Construction Management Plan, which will aid all
project participants by detailing the communication and administrative procedures used
to implement this contract.
1. After submission of the QC Plan, but prior to the start of construction, meet with the
Contracting Officer to discuss the QC program required by this contract. The purpose of
this meeting is to develop a mutual understanding of the QC details. This includes forms
used for documentation, administration for on-site and off-site work, and the coordination
of the contractor's management, production, and QC personnel with the Contracting
Officer. As a minimum, the contractor's personnel required to attend include the Project
Manager, Project Superintendent, QC Manager, Assistant QC Manager, and QC
Specialist. The QC Manager prepares the minutes of the meeting, and both the
Contractor and the Contracting Officer signs this document.
F. QC Meetings:
1. After the start of construction, the QC Manager conducts weekly QC meetings at the
work site with the project superintendent. The QC Manager prepares minutes of the
meeting. Provide a copy to the Contracting Officer within 2 working days after the
meeting. The Contracting Officer or Governments Designated Inspector may attend
these meetings. Notify the Contracting Officer at least 48 hours before each meeting.
This meeting requirement is solely for quality control and is in addition to the weekly
construction meeting held by the Governments Designated Inspector or Contracting
Officer and the QC managers preparatory meetings. As a minimum, accomplish the
following at each meeting:
c. Review the work scheduled in the next week and documentation required.
Schedule the three phases of control and testing:
G. Three Phases of Control: The QC Manager performs the three phases of control to ensure that
work complies with contract requirements. The three phases of control cover both on-site and
off-site work and include the following for each definable feature of work:
1. Preparatory Phase: Notify the Contracting Officer at least 2 work days before each
preparatory phase meeting. Conduct the meeting with the QC specialist, the
Superintendent, the foreman responsible for the definable feature of work, and
representatives of manufacturers and fabricators involved in or affected by the installation
and its coordination or integration with other materials. The Contracting Officer or
Governments Designated Inspector may attend. The QC Manager prepares minutes of
the meeting. Provide a copy to the Contracting Officer within 2 working days after the
meeting. This meeting requirement is solely for quality control and is in addition to other
quality meetings. Perform the following prior to beginning work on each definable feature
of work:
a. Review the progress of other construction activities and preparations for the
particular activity under consideration at each meeting, including requirements for
the following:
1) Contract documents.
2) Options.
3) Related changes to the contract.
4) Interface requirements.
5) Sequences.
6) Status of submittals.
7) Off-site fabrication issues.
8) Housekeeping.
9) Status of RFIs.
10) Purchases.
11) Deliveries.
12) Shop drawings, product data, and quality-control samples.
13) Possible conflicts.
14) Compatibility problems.
15) Time schedules.
16) Approved construction schedules
17) Weather limitations.
18) Manufacturer's recommendations.
19) Warranty requirements.
20) Compatibility of materials.
21) Acceptability of substrates.
22) Temporary facilities.
23) Space and access limitations.
24) Governing regulations.
25) Inspecting and testing requirements.
26) Required performance results.
27) Recording requirements.
28) Protection.
2. Initial Phase: Notify the Contracting Officer at least 2 work days before each initial
phase. When construction crews are ready to start work on a definable feature of work,
conduct the initial phase with the QC specialist, the superintendent, and the foreman
responsible for that definable feature of work. Observe the initial segment of the
definable feature of work to ensure that the work complies with contract requirements.
Document the results of the initial phase in the daily Contractor Quality Control Report.
Repeat the initial phase for each new crew to work on site, or when specified quality is
below acceptable levels. Perform the following for each definable feature of work:
3. Follow-up Phase: Perform the following for on-going work daily, or more frequently as
necessary until the completion of each definable feature of work and document in the
daily Contractor Quality Control Report:
4. Notification of three phases of control for off-site work: Notify the Contracting Officer at
least two weeks before the start of the preparatory and initial phases.
1. Except as stated otherwise in the specification sections, perform sampling and testing
required under this contract.
I. Special Inspections:
1. Retain third-party quality assurance agencies to conduct the special inspections required
by the Project Building Code indicated in Division 01 Section Summary of Work. The
inspecting agency shall provide reports of the special inspections directly to the
Contracting Officer. These inspections are in addition to the inspections specified
elsewhere in the Contract Documents.
a. The quality assurance agencies shall supervise qualified personal that are
Registered Professional Engineers and demonstrate competence, to the
satisfaction of the Contracting Officer, for inspection of the particular type of
construction or operation requiring special inspection. Quality assurance agencies
and professional engineers are subject to written approval of the Contracting
Officer.
b. Quality assurance agencies shall conduct special inspections indicated in
Statement of Special Inspections as indicated on Drawings and in individual
Specification Sections, and as follows:
J. QC Certifications:
1. Contractor Quality Control Report Certification: Each Contractor Quality Control Report
must contain the following statement: "On behalf of the Contractor, I certify that this
report is complete and correct and equipment and material used and work performed
during this reporting period is in compliance with the contract drawings and specifications
to the best of my knowledge, except as noted in this report."
2. Invoice Certification: Furnish a certificate to the Contracting Officer with each payment
request, signed by the QC Manager, attesting that as-built drawings are current and
attesting that the work for which Contractor requests payment, including stored material,
is in compliance with contract requirements.
3. Completion Certification: Upon completion of work under this contract, furnish a
certificate to the Contracting Officer signed by the QC Manager attesting that "Contractor
has completed, inspected, tested the work and is in compliance with the contract."
K. Documentation:
1. Contractor Quality Control Report: Provide reports for each day of work and for every
seven consecutive calendar days of no-work and on the last day of a no-work period.
2. Testing Plan and Log: As Contractor performs tests, record on the "Testing Plan and
Log" the date the test results sent to the Contracting Officer. Include remarks and
acknowledgment of use of an accredited or approved testing laboratory. Attach a copy of
the updated "Testing Plan and Log" to the last daily Contractor Quality Control Report of
each month.
3. Rework Items List: Maintain a list of work that does not comply with the contract,
identifying what items Contractor needs to rework, the date the item discovered, and the
date Contractor corrected the item. There is no requirement to report a rework item
corrected on the same day of discovery. Attach a copy of the "Contractor Rework Items
List" to the last daily Contractor Quality Control Report of each month. Take
responsibility for items on this list needing rework including those identified by the
Contracting Officer.
4. Record ("As-Built") Drawings: The QC Manager shall review the as-built drawings as
required by Division 01 Section Closeout Procedures. Ensure as-built drawings are kept
current on a daily basis and marked to show deviations made from the contract drawings.
Initial each deviation and each revision. Upon completion of work, furnish a certificate
A. Summary:
1. This Article specifies administrative and procedural requirements for field engineering
services.
B. Examination:
1. Verify layout information shown on the drawings, with existing benchmarks, before
proceeding to lay out the work. Locate and protect existing benchmarks and control
points. Preserve permanent reference points during construction.
2. Existing Utilities and Equipment: The existence and location of underground and other
utilities and construction indicated as existing are not guaranteed. Before beginning
work, investigate and verify the existence and location of underground utilities and other
construction.
3. Coordinate between trades.
C. Performance:
1. Work from lines and levels established by the drawings. Establish benchmarks and
markers to set lines and levels at each story of construction and elsewhere as needed to
locate each element of the project. Calculate and measure required dimensions within
indicated or recognized tolerances. Do not scale drawings to determine dimensions.
2. Building Lines and Levels: Locate and lay out batter boards for structures, building
foundations, column grids, and locations, and control lines and levels required for
mechanical and electrical work.
3. Existing Utilities: Furnish information necessary to adjust, move, or relocate existing
structures, utility poles, lines, service, or other appurtenances located in or affected by
construction. Coordinate with local authorities having jurisdiction.
END OF SECTION
CONTRACTOR SUPERINTENDENT
WAS A JOB SAFETY MEETING HELD THIS DATE? oYES TOTAL WORK HOURS ON JOB SITE
oNO THIS DATE
(If YES attach a copy of the meeting minutes)
JOB SAFETY
WERE THERE ANY LOST TIME ACCIDENTS THIS DATE? oYES oNO
(If YES attach copy of completed OSHA report) CUMULATIVE TOTAL OF WORK
WAS TRENCHING/SCAFFOLD/HV ELECTRICAL/HIGH WORK DONE? oYES oNO HOURS FROM PREVIOUS REPORT
(If YES attach statement or checklist showing inspection performed)
WAS HAZARDOUS MATERIALS/WASTE RELEASED INTO THE ENVIRONMENT
(If YES attach description of incident and proposed action) oYES TOTAL WORK HOURS FROM START
oNO OF CONSTRUCTION
LIST SAFETY ACTIONS TAKEN TODAY/SAFETY INSPECTIONS CONDUCTED SAFETY REQUIREMENTS HAVE
BEEN MET
CONSTRUCTION AND PLANT EQUIPMENT ON JOB SITE TODAY. INCLUDE NUMBER OF HOURS USED TODAY
REMARKS
CONTRACTOR/SUPERINTENDENT DATE
FORM 01400-1 6/91
SHEET OF
WORK COMPLIES WITH CONTRACT TESTING PERFORMED & WHO PERFORMED TEST
AS APPROVED IN INITIAL PHASE.
F
O
L
L
O
W
-
U
P
REWORK ITEMS IDENTIFIED TODAY (NOT CORRECTED BY CLOSE OF BUSINESS) REWORK ITEMS CORRECTED TODAY (FROM REWORK ITEMS
LIST)
REMARKS
On behalf of the contractor, I certify that this report is complete and
correct and equipment and materials used and work perfomed during the
reporting period is in compliance with the contract drawings and
specifications to the best of my knowledge, except as noted in this report.
DATE
GOVERNMENT QUALITY ASSURANCE REPORT
QUALITY ASURANCE REPRESENTATIVE'S REMARKS AND/OR EXCEPTIONS TO THE REPORT
TEST REPORT
DESCRIPTION OF TEST:
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________
NAME: _______________________________________
TITLE: ________________________________________
SIGNATURE: ___________________________________
I HEREBY CERTIFY THAT THE ABOVE DESCRIBED ITEM, SYSTEM, OR PART OF SYSTEM HAS BEEN TESTED AS
INDICATED ABOVE AND FOUND TO BE ENTIRELY SATISFACTORY AS REQUIRED IN THE CONTRACT
SPECIFICATIONS.
SIGNATURE OF CONTRACTOR
QUALITY CONTROL INSPECTOR: _______________________________
DATE: ________________________________
REMARKS:
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________________________________________________________________________________________
__________________________________________________________________________________________________
------- Field Water Content and Density Tests, Data Field density tests and respective moisture
Sheet contents.
------- Field Density and Grading Analysis Test Field density tests and gradation.
(Washington Dens-o-Meter Method)
DD 1206 Sieve Analysis Data Sieve analysis data sheet for soils.
------- Mechanical Analysis Test Data Sieve analysis data sheet and hydrometer data
sheet for soils.
------- Gradation Curves Gradation graph for soils and aggregates. (To
include specification limits)
------- Soil Moisture Content Moisture content sheet for soils and/or
aggregates.
------- Specific Gravity and Absorption Test Data Sheet Specific gravity and absorption test for soil and
aggregates.
Atterberg Limits Determinations
DD 1209 Test and graph for Atterberg limits tests.
Gradations of Blended Aggregate
------- Aggregate blending computation work sheet.
Bituminous Mix Design - Aggregate Blending Aggregate blending sheet for asphaltic concrete.
DD 1217
Asphaltic Concrete Mix Design Report
Asphaltic mix design and aggregate grading.
-------
Extraction Text, Hot Mix Asphalt and Concrete Extraction test and grading sheet (include fracture
face tests if specified).
------- Marshall Method - Computation of Properties of
Asphalt Mixtures Marshall Test form.
DD 1218
Daily Plant Inspection Report - Asphalt
Test Data on Absorption and Moisture Condition of Absorption and moisture condition tests of
Masonry Blocks. masonry units.
-------
Backfill for foundations and walls, Gradation1 1 every 380 m3 (500 CY) or 1 per
trenches, streets, roads, and day for quantities exceeding 20 m 3
sidewalks (25 CY)/lift.
2/12 3
In-Place Density 1 every 380 m (500 CY) or 1 per
day for quantities exceeding 20 m 3
(25 CY).
Mix Design (by Contractor) Submittal Design Mix (include test results)4:
Blended
Aggregate: 45 kg (100 lbs.)
Asphalt: 3.9 L (1 gal.)
Mineral Filler: 4.5 kg (10 lbs.)
Asphalt (including and prime and Sample and certification. Submit a 1 quart sample material
tack coat) (viscosity, flash point, penetration) certification with test results for
each shipment or lot of asphalt.
Retain a duplicate 1 quart sample
until completion of Work.
Aggregates (from bins or source not Gradation 1 test prior to start of paving
to exceed 1/2") operation and every 360 t (1500
tons) or 750 m3 (1000 CY).
Asphaltic concrete (including Marshall Method Test 1 test (set of 2 specimens) per day
asphalt treated base) for more than 90 t (100 tons) and 1
per 2720 t (3000 tons) thereafter.
Mix Design (by Contractor) Submittal Mix design for each class of
concrete in accordance with ACI
211. Include all material, tests, and
certifications below. Also, include
proportions, slump, air content, and
water cement ratio (include
certification of compatibility for more
than one admixture).
Portland Cement and Pozzolan Chemical and Physical tests Manufacturer's certificate of
compliance with a test report for
each delivery or lot. Submit a
4.5 kg (10 lb.) sample for every
other certification.
Fine Aggregate7 Gradation and fineness modules 1 every 190 m3 (250 CY) of
concrete.
Unit weight, yield, and water Conduct with strength tests. Check
cement ratio unit weight and adjust aggregate
weights to insure proper yield.
Batching and mixing equipment Contract Compliance Contractor compliance with ASTM
tests C 94 "Standard Specifications for
Ready Mix Concrete", with
documentation, reports, and
certification of compliance.
Masonry
Concrete Masonry Units9 Dry shrinkage10 1 set of 3 per 10,000 units and
manufacturer's certification and test
report.
11
Airdry condition Same as dry shrinkage.
NOTES:
1
All acceptance tests shall be conducted from in-place samples.
2
Additional tests shall be conducted when variations occur due to the contractors operations, weather conditions,
site conditions, etc.
3
Classification (ASTM D-2487), moisture contents, Atterberg limits and specific gravity tests shall be conducted for
each compaction test if applicable.
4
Materials to be submitted only upon request by the Contracting Officer.
5
Tests can substitute for same tests required under "Aggregates" (from bins or source), although gradations will be
required when blending aggregates.
6
Increase quantities by 50 percent for Paving mixes and by 100 percent for Government testing of admixtures.
Include standard deviation for similar mixes from the intended batch plant and data from a minimum of 30 tests, if
available. Refer to ACI 214.
7
A petrographic report for aggregate is required with the sample for source approval. If the total amount of all types
of concrete is less than 150 m 3 (200 CY), service records from three separate structures in similar environments
which used the aggregates may substitute for the petrographic.
8
Aggregate moisture tests are to be conducted in conjunction with concrete strength tests for w/c calculations.
9
For less than 1,000 units, the above test may be waived at the discretion of the Contracting Officer and acceptance
based on manufacturers certification and test report.
10
Additional tests shall be performed when changes are made either in the manufacturing processes or in materials
used in the production of the masonry units.
11
If adequate storage protection is not provided at the jobsite, additional tests shall be made to determine that the
allowable moisture condition has not been exceeded before the blocks can be placed in the structure.
12
THE NUCLEAR DENSIMETER, IF PROPERLY CALIBRATED, MAY BE USED BUT ONLY TO SUPPLEMENT
THE REQUIRED TESTING FREQUENCY AND PROCEDURES. THE DENSIMETER SHALL BE CALIBRATED
AND IS RECOMMENDED FOR USE WHEN THE TIME FOR COMPLETE RESULTS BECOMES CRITICAL.
This Section does not specify requirements for planning and design
which are addressed in the DeCA Design Criteria Handbook
Division 01 Section 01 33 29, Sustainable Design Reporting, that are
the responsibility of the A/E.
1.1 SUMMARY
A. Section includes requirements for construction facilities and temporary controls, including
temporary utilities, support facilities, and security and protection.
B. Related Sections:
1.2 SUBMITTALS
B. Submittal Schedule:
C. Submittal List:
Reference Submittal Item Quantity Action
1.4D.1 Temporary Utilities Plan X R
1.5B Temporary Support Facilities Plan X R
1.5C.4 Temporary Administration Trailer X R
1.6B Temporary Security and Protection Facilities Plan X R
X Submit quantity specified in Division 01 Section Administrative Requirements.
R Review each submittal, mark to indicate action taken, and return.
A. Provide new materials. Provide new equipment. If acceptable to the Contracting Officer, the
contractor may use undamaged, previously used equipment in serviceable condition for
temporary use. Provide equipment suitable for use intended.
B. Use qualified personnel for installation of temporary facilities. Coordinate with the Contracting
Officer on locating facilities where they will serve the project adequately and result in minimum
interference with performance of the work.
C. Provide each facility ready for use to avoid delays. Maintain and modify as required. Do not
remove until facilities are no longer necessary or replaced by authorized use of completed
permanent facilities.
D. Protection of Property Markers and Official Datum Points: Protect from damage during
construction. Remove only if necessary for construction and with approval of the Contracting
Officer.
E. Conditions of Use: Keep temporary services and facilities clean and neat in appearance.
Operate in a safe and efficient manner. Relocate temporary services and facilities as the work
progresses. Do not overload facilities or permit them to interfere with progress. Take
necessary fire prevention measures. Do not allow hazardous, dangerous, unsanitary
conditions, or public nuisances to develop or persist on-site or off-site.
a. Protect on-site and off-site facilities, utilities, streets, and curbs from damage, dust,
and dirt. Restore affected areas to original state or better at no expense to the
Government.
b. Protect and preserve, in operating condition, active utility services that traverse or
border the project site. Repair damage resulting from this work at no expense to
the Government.
F. Verify areas available for access, parking, and material storage before starting work.
G. Use of alternative construction facilities and temporary controls is contractor's option, subject to
Contracting Officer's acceptance.
A. Temporary utilities include, but are not limited to, the following:
B. General: Where only part of utility services is available, provide the remainder with matching,
compatible materials and equipment. Comply with installation recommendations.
1. Arrange with the Contracting Officer for service interruptions and connections for
temporary services.
2. Use Charges: The contractor is responsible for all temporary utility fees and their
connection, removal, and restoration (e.g., electricity, gas, telephone, and water).
Provide metering devices with programmable use rates, appropriate for the utility being
used, and acceptable to the Contracting Officer.
3. Use Charges: Subject to the approval of the Contracting Officer, reasonable amounts of
utilities (exclusive of telephone) are available from the Government for use without
metering and without payment of use charges. Provide connections and extensions of
services as required for construction operations.
C. Regulations: Comply with industry standards and applicable laws and installation regulations
and authorities having jurisdiction.
1. Standards: Comply with NEC Electrical Design Library "Temporary Electrical Facilities."
2. Inspections: Arrange for authorities having jurisdiction to inspect and test each
temporary utility before use. Obtain required certifications and permits.
1. Provide a Temporary Utilities plan which identifies, but is not limited to, plans and
procedures for the following:
1. Water Service: Install distribution piping of sizes and pressures adequate for
construction operations.
b. For new construction maintain a minimum of 10 foot candles (or more if required
by regulatory agencies) in all areas. Increase the lighting levels to a minimum of
75 foot candles when drywall, painting, and other finish operations begin.
G. Temporary Heat:
a. Prohibit the use of open flame, salamander, or burning space heating units.
H. Ventilation:
I. Telephone Service:
1. Sanitary facilities include temporary toilets, wash facilities, and drinking water fixtures.
Comply with regulations and health codes for the type, number, location, operation, and
maintenance of fixtures and facilities. Install where facilities will best serve the project
needs (verify locations acceptable to the Contracting Officer before proceeding).
A. Provide any other equipment, facilities, or materials necessary to house office operations and
protect stored construction materials or building equipment from the elements. This includes,
but is not limited to: storage trailers, crating, etc. Support facilities include, but are not limited to,
the following:
B. Submittals:
1. Provide a Temporary Support Facilities plan which identifies, but is not limited to, plans
and procedures for the following:
1. Provide a temporary office trailer (new or like new condition) for the use of the
Governments Designated Inspector that is physically detached from the contractor's
structure.
2. Install the office complete with utilities within three weeks after Notice to Proceed (NTP)
in a location and orientation approved by the Governments Designated Inspector. Strap
down the office to prevent shifting or dislocation by wind. Maintain office, including
utilities and sanitary facilities, until completion of all punch list work at the end of the
contract. This may require relocation, at contractors expense, of the office and utilities to
allow completion of the project. Place utilities to support office occupancy at any time of
the day or night. Field office shall be "Williams Scottsman" model 46 feet by 10 feet,
model 44 feet by 12 feet, "GE Capital" model GS-1260, or equal. Furnish and equip the
office as follows:
a. Furnish with:
1) Two each 60 inch by 30 inch double pedestal desks with lockable drawers.
2) One each 72 inch by 36 inch plan table.
3) Two each legal size 4 drawer metal lockable file cabinets.
4) Two desk type swivel chairs with arm rests.
5) One stool to match plan table height.
6) One waste basket.
7) Electric water cooler including scheduled delivery of bottled drinking water
and drinking cups, quantities on an as-needed basis.
8) Twelve inch wide shelving and a minimum of 20 LF for reference books
(installed by contractor at direction of the Governments Designated
Inspector).
9) Small conference table (minimum of 30 by 96 inches) and four chairs.
10) One plan storage rack (Minimum capacity of six sets of full size project
plans).
11) Outside security light operated by photocell.
b. Equip with:
1) Fluorescent lighting with minimum of 550 lux at desk tops and plan table,
incandescent lighting acceptable in restroom.
c. Meet all contract codes. All furnishings new or like new condition.
1. Provide temporary administration trailer(s) (new or like new condition) for the use of store
administration personnel during phased construction.
2. Install the trailer(s) complete with utilities in the location and orientation indicated. Strap
down the trailer to prevent shifting or dislocation by wind. Provide support of trailer that
do not distort or mar paving surface. Maintain trailer, including utilities, sanitary facilities,
and cleaning, until completion of phased construction. Provide utilities to support trailers
occupancy at any time of the day or night. Temporary administration trailer shall be
"Williams Scottsman" Sales Office trailer, size 48 feet by 24 feet (actual size 44 feet by
23 feet-6 inches), or equal. 1-800-782-1500 or www.willscot.com. Equip each office area
in trailer as follows:
1. Field Offices: Within 21 days from notice to proceed, provide insulated, weather tight
temporary offices of sufficient size to accommodate required office personnel at the
project site. Keep the office clean and orderly for use for small progress meetings, etc.
2. Locate field offices, storage sheds, and other temporary construction and support
facilities for easy access.
a. Coordinate and obtain approval of location of field offices and storage sheds with
the Contracting Officer.
1. Implement guidelines as identified in the Sheet Metal and Air Conditioning Contractors
National Association, Inc. (SMACNA) - "IAQ Guidelines for Occupied Buildings Under
Construction" - Current Edition. The intent is to prevent any indoor air quality problems to
building occupants during construction. Isolate all areas of construction from
Commissary operations. Remove all hazardous materials prior to starting work. If
hazardous materials are found, identified, or suspect, cease work and mitigate the
hazardous material concern. Do not continue with contract work until the space has been
cleared by a PE or Certified Industrial Hygienist for occupancy.
2. Provide temporary enclosures to seal operational portions of the commissary from areas
of construction and for protection of construction in progress and completed, from
exposure, foul weather, other construction operations, and similar activities. Construct
temporary enclosures to withstand typical loading conditions, such as impact from carts,
wind loads, and commissary operations.
3. Doors in Barriers: Provide gates in barriers for the contractor's access to the work, of
similar construction to the barrier in which it occurs. Provide gates with hinges, braces,
and locks.
4. Customer Access Protection Through Construction Areas: Provide patron access
protection through the construction area consisting of temporary enclosures, walkways,
and when required, roofs. Comply with ADA guidelines for accessibility by individuals
with disabilities. Construct walkways a minimum of 8 feet wide and with a hard walking
surface, smooth enough for the easy passage of shopping carts. Do not install steps and
vertical offsets of greater than 1/4 inch and excessive inclines. Construct these barriers of
2 inch by 4 inch wood or metal stud, adequately braced, and covered with 1/2 inch
plywood on the exterior side. When work is overhead, provide adequately braced roofs
of 2 inch by 4 inch wood or metal studs with 1/2 inch plywood on the exterior side for
patron protection. Relocate or rebuild temporary facilities throughout the construction
period to provide safe patron access to the commissary.
a. The commissary will remain in operation during the construction period; therefore,
construct barriers by the contractor as work progresses. Provide barriers as
specified and in locations as required, from floor to ceiling or from floor to
underside of the roof deck, to seal the operational portions of the commissary from
the area of construction.
b. Construct barriers of wood or metal studs with finished surfaces. Determine the
stud sizes and the spacing of the studs (2 feet maximum). Construct barriers to
withstand typical loading conditions such as impact loading from carts, wind loads,
commissary operations, and construction operations.
c. Provide adequate lighting.
d. Construct barriers of single length members. If splicing is necessary due to the
height of the wall, design the splice to provide adequate strength to withstand
typical loading conditions.
1. Project Identification and Temporary Signs: Prepare project identification and other signs
of size indicated. Install signs where indicated to inform the public and persons seeking
entrance to the project. Support on posts or framing of preservative-treated wood or
steel. Do not permit installation of unauthorized signs.
2. Plywood: For signs and directory boards, provide exterior-type, Grade B-B high density
concrete form overlay plywood, unless otherwise indicated, of size and thickness
indicated.
3. Paint: For sign panels and applying graphics, provide exterior-grade alkyd gloss enamel
over exterior primer unless otherwise indicated.
1. Collection and Disposal of Waste: Collect waste from the construction areas and
elsewhere on a daily basis.
1. Rodent and Pest Control: Retain a local exterminator or pest control company to
recommend practices to minimize attraction and harboring of rodents, roaches, and other
pests. Employ this service to perform extermination and control procedures at regular
intervals so the project will be free of pests and their residues at completion of the
project. Perform control operations lawfully, using environmentally safe materials.
J. Grounds Maintenance:
A. Security and protection facilities include, but are not limited to, the following:
B. Submittals:
1. Provide a Temporary Security and Protection Facilities plan which identifies, but is not
limited to, procedures for the following:
1. Fire Extinguishers: Provide hand carried, portable, UL rated, Class A fire extinguishers
for temporary offices and similar spaces. In other locations, provide hand carried,
portable, Ul rated, Class ABC, dry chemical extinguishers or a combination of
extinguishers of NFPA recommended classes for the exposure.
a. Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and
size required by location and class of fire exposure.
1. Tarpaulins: Provide waterproof, fire resistant, UL labeled tarpaulins with a flame spread
rating of 15 or less. For temporary enclosures, provide translucent, nylon reinforced,
laminated polyethylene or polyvinyl chloride, fire retardant tarpaulins.
2. Lumber and Plywood:
a. For vision barriers, provide minimum 3/8 inch thick exterior plywood.
b. For safety barriers, sidewalk bridges, and similar uses, provide minimum 5/8 inch
thick exterior plywood. Paint sides facing sales area two coats gloss white.
3. Wind Damage Control: Provide properly designed and constructed temporary bracing of
adequate strength to prevent damage to project and component parts due to normal and
excessive wind forces. Replace or repair damaged portions of project and component
parts at no additional cost to the Government.
1. Site Limit Barrier: Provide a site limit barrier constructed of a temporary chain link fence,
at least 6 feet high, on steel posts with a steel top rail and bottom tension wires.
2. Open-Mesh Fencing 6 Foot High: Provide 0.120 inch thick, galvanized 2 inch chain link
fabric fencing and galvanized steel pipe posts, 1-1.2 inch I.D. for line posts and 2 inch
I.D. for corner posts. Provide gates of similar construction.
F. Covered Walkways:
1. Provide walkway roofs with adequately braced 2 inch by 4 inch wood or metal studs with
5/8 inch plywood on the exterior side.
1. Security Dust Barriers: Provide security dust barriers as required, similar in all respects
to the dust barrier, except that the security dust barrier has, in addition to the tarpaulin, a
layer of 5/8 inch plywood attached full height to the opposite side of the studs from the
tarpaulin.
2. Security Weather tight Temporary Enclosure: Where security weather tight temporary
enclosures are required, provide a temporary framework with 5/8 inch plywood on the
exterior side and 5/8 inch gypsum wallboard or plywood on the interior. Install a tarpaulin
over exterior surfaces subject to the weather, taped and secured to provide a weather
tight enclosure. Construct to comply with wind load requirements. Maintain weather tight
throughout the time in use.
3. Provide doors in temporary enclosures for access to the work, of similar construction to
the temporary enclosure in which it occurs. Provide doors with hinges, braces, and locks.
a. Security Weather tight Barriers: Where security Weather tight barriers are
required, provide a temporary framework with 5/8 inch plywood on the exterior side
and 5/8 inch gypsum board or plywood on the interior side. Provide one layer of
polyethylene fiberglass reinforced film on exterior surfaces subject to the weather.
Tape and secured to provide a weather tight enclosure. Maintain weather tight
throughout the construction period.
B. Maintenance: Maintain facilities in good operating condition until removal. Protect from
damage by the elements.
C. Maintain support facilities until near project final acceptance. Remove prior to project final
acceptance.
D. Termination and Removal: Unless the Contracting Officer requests longer maintenance,
remove each temporary facility when the need ends or when replaced by authorized use of a
permanent facility. Complete or, if necessary, restore permanent construction delayed because
1. Materials and facilities that constitute temporary facilities are the contractor's property.
The government reserves the right to take possession of project identification signs.
2. For areas intended for landscape development, remove soil and aggregate fill that do not
comply with requirements for fill or subsoil in the area. Remove materials contaminated
with road oil, asphalt and other petrochemical compounds, and other substances that
might impair growth of plant materials or lawns.
END OF SECTION
DESIGN CRITERIA
2. This section specifies project requirements for the Contractor to employ the services of a
qualified arborist to ensure that the tree protection and trimming work is completed in accordance
with accepted standards and practices. This cost shall be included in the construction contract
amount.
3. Contract Documents shall clearly indicate which trees are to remain, which trees are to be
removed, and which trees are to be transplanted.
END OF SECTION
June 2011 01 56 39 1
SECTION 01 56 39
TEMPORARY TREE AND PLANT PROTECTION
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. The protection and trimming of existing trees that interfere with, or are affected by,
execution of the Work, whether temporary or permanent construction.
1.2 DEFINITIONS
A. Tree Protection Zone: Area surrounding individual trees or groups of trees to remain during
construction, and defined by the drip line of individual trees or the perimeter drip line of groups
of trees, unless otherwise indicated.
1.3 SUBMITTALS
A. Product Data:
1. Tree Pruning Schedule: Written schedule from arborist detailing scope and extent of
pruning of trees to remain that interfere with or are affected by construction.
B. Qualification Data:
C. Certification:
1. From arborist, certifying that trees indicated to remain have been protected during
construction according to recognized standards and that trees were promptly and
properly treated and repaired when damaged.
D. Maintenance Recommendations:
1. From arborist, for care and protection of trees affected by construction during and after
completing the Work.
E. Submittal List:
1. An experienced tree service firm that has successfully completed tree protection and
trimming work similar to that required for this Project and that will assign an experienced,
qualified arborist to Project site during execution of tree protection and trimming.
B. Arborist Qualifications:
1. Comply with ANSI A300 (Part 1), "Tree, Shrub, and Other Woody Plant Maintenance--
Standard Practices (Pruning)."
D. Preinstallation Conference:
a. Before tree protection and trimming operations begin, meet with representatives of
the Installation, consultants, and other concerned entities to review tree protection
and trimming procedures and responsibilities.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Drainage Fill:
1. Selected crushed stone, or crushed or uncrushed gravel, washed, ASTM D 448, Size 24,
with 90 to 100 percent passing a 2-1/2-inch sieve and not more than 10 percent passing
a 3/4-inch sieve.
B. Topsoil:
1. Natural or cultivated surface-soil layer containing organic matter and sand, silt, and clay
particles; friable, pervious, and black or a darker shade of brown, gray, or red than
underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more
than 2 inches in diameter; and free of weeds, roots, and toxic and other nonsoil materials.
2. Obtain topsoil only from well-drained sites where topsoil is 4 inches deep or more; do not
obtain from bogs or marshes.
C. Filter Fabric:
PART 3 - EXECUTION
3.1 PREPARATION
A. General:
1. Temporary Fencing: Install temporary fencing around tree protection zones to protect
remaining trees and vegetation from construction damage. Maintain temporary fence
and remove when construction is complete.
2. Protect tree root systems from damage caused by runoff or spillage of noxious materials
while mixing, placing, or storing construction materials. Protect root systems from
ponding, eroding, or excessive wetting caused by dewatering operations.
3. Do not store construction materials, debris, or excavated material inside tree protection
zones. Do not permit vehicles or foot traffic within tree protection zones; prevent soil
compaction over root systems.
4. Maintain tree protection zones free of weeds and trash.
5. Do not allow fires within tree protection zones.
3.2 EXCAVATION
A. General:
a. Redirect roots in backfill areas where possible. If encountering large, main lateral
roots, expose roots beyond excavation limits as required to bend and redirect them
without breaking. If encountered immediately adjacent to location of new
construction and redirection is not practical, cut roots approximately 3 inches back
from new construction.
b. Do not allow exposed roots to dry out before placing permanent backfill. Provide
temporary earth cover or pack with peat moss and wrap with burlap. Water and
maintain in a moist condition. Temporarily support and protect roots from damage
until they are permanently relocated and covered with soil.
4. Where utility trenches are required within tree protection zones, tunnel under or around
roots by drilling, auger boring, pipe jacking, or digging by hand.
a. Root Pruning: Do not cut main lateral roots or taproots; cut only smaller roots that
interfere with installation of utilities. Cut roots with sharp pruning instruments; do
not break or chop.
A. Grade Lowering:
1. Where new finish grade is indicated below existing grade around trees, slope grade
beyond tree protection zones. Maintain existing grades within tree protection zones.
B. Grade Lowering:
1. Where new finish grade is indicated below existing grade around trees, slope grade away
from trees as recommended by arborist, unless otherwise indicated.
a. Root Pruning: Prune tree roots exposed during grade lowering. Do not cut main
lateral roots or taproots; cut only smaller roots. Cut roots with sharp pruning
instruments; do not break or chop.
C. Minor Fill:
1. Where existing grade is 6 inches or less below elevation of finish grade, fill with topsoil.
Place topsoil in a single uncompacted layer and hand grade to required finish elevations.
D. Moderate Fill:
1. Where existing grade is more than 6 inches but less than 12 inches below elevation of
finish grade, place drainage fill, filter fabric, and topsoil on existing grade as follows:
a. Carefully place drainage fill against tree trunk approximately 2 inches above
elevation of finish grade and extend not less than 18 inches from tree trunk on all
sides. For balance of area within drip-line perimeter, place drainage fill up to 6
inches below elevation of grade.
b. Place filter fabric with edges overlapping 6 inches minimum.
c. Place fill layer of topsoil to finish grade. Do not compact drainage fill or topsoil.
Hand grade to required finish elevations.
A. General:
1. Prune trees to remain that are affected by temporary and permanent construction.
2. Prune trees to remain to compensate for root loss caused by damaging or cutting root
system. Provide subsequent maintenance during Contract period as recommended by
arborist.
3. Pruning Standards: Prune trees according to ANSI A300
4. Cut branches with sharp pruning instruments; do not break or chop.
5. Chip removed tree branches and dispose of off-site.
A. General:
a. Provide new trees of same size and species as those being replaced; plant and
maintain as specified in Division 32 Section Planting.
b. Provide new trees of 6-inch caliper size and of a species selected by
Government's Designated Representative when damaged trees more than 6
inches in caliper size, measured 12 inches above grade, are required to be
replaced. Plant and maintain new trees as specified in Division 32 Section
Planting.
3. Aerate surface soil, compacted during construction, 10 feet beyond drip line and no
closer than 36 inches to tree trunk. Drill 2-inch- diameter holes a minimum of 12 inches
deep at 24 inches o.c. Backfill holes with an equal mix of augured soil and sand.
A. Burning is not permitted. Remove excess excavated material and displaced trees from
Government's property.
END OF SECTION
GOVERNMENT-FURNISHED PRODUCTS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The Drawings indicate government equipment requiring relocation. The work includes providing
support systems (including mechanical and electrical connections) for the government's
relocated equipment.
1. Identify relocation dates of items requiring relocation in the Contractor's CPM Schedule.
2. Remove, relocate, and erect items as required.
3. Protect items from damage, including damage from exposure to the elements to include
rain, heat and/or cold. Repair or replace items damaged as a result of construction
operations.
B. Quality Assurance:
D. Inspection: Verify that substrates are sound and free of irregularities interfering with installation.
Correct unsatisfactory conditions prior to installation.
E. Installation: Securely attach relocated products to resist required earthquake and product use
loads.
1. The government will provide necessary manufacturers product data to the contractor,
upon request.
2. The government will arrange for delivery of Government-Furnished items.
3. Identify delivery dates of Government-Furnished items in the Contractor's Construction
Schedule per Division 01 Section Administrative Requirements.
a. Notify the Government one-month prior to any delay affecting the delivery date of
Government-Furnished items. Notify the Government two months prior to any
acceleration affecting the delivery date of Government-Furnished items. After
providing the Government with the initial delivery dates, and to which the
Government agrees, the Government will attempt to meet, but is not obligated to
change the delivery dates as requested by the Contractor.
4. Review shop drawings, product data, and samples and return them to the Contracting
Officer noting discrepancies or problems anticipated in the use of the product.
B. Protect Government-Furnished items from damage, including damage from exposure to the
elements to include rain, heat and/or cold. Repair or replace, as determined by the Contracting
Officer, items damaged as a result of construction operations.
A. The government will furnish and install items indicated on the drawings as Government-
Furnished, Government Installed (GFGI). Unless otherwise indicated, GFGI operations will
occur simultaneously with work under this Contract. The Contractors work includes preparation
of areas and providing support systems, as indicated, to receive GFGI equipment.
1. The government will provide necessary manufacturers product data to the contractor,
upon request.
2. The government will arrange for delivery of GFGI items.
3. Delete option below if no project phasing required.
a. Notify the Government one-month prior to any delay affecting the delivery date of
Government-Furnished items. Notify the Government two months prior to any
acceleration affecting the delivery date of Government-Furnished items. After
providing the Government with the initial delivery dates, and to which the
Government agrees, the Government will attempt to meet, but is not obligated to
change the delivery dates as requested by the Contractor.
5. Prior to installation of GFGI items and [phase turnover or ]contract close-out, examine
areas that are to receive GFGI items with the Government Installer.
6. Protect GFGI items from damage, including damage from exposure to the elements to
include rain, heat and/or cold. Repair or replace, as determined by the Contracting
Officer, items damaged as a result of construction operations. All GFGI equipment shall
be stored in a storage enclosure or trailer in accordance with Division 01 Section
Temporary Facilities and Controls.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
A. Requirements for Structural Work: Do not cut and patch structural elements in a manner that
would change their load-carrying capacity or load-deflection ratio.
B. Operational Limitations: Do not cut and patch operating elements or related components in a
manner that would result in reducing their capacity to perform as intended. Do not cut and
patch operating elements or related components in a manner that would result in increased
maintenance or decrease operational life or safety. Maintain fire resistance ratings of members
and systems.
D. Cutting and Patching Roofs: Determine from the government which roofing manufacturer is
responsible for the roof bond or guarantee. Subcontract all cutting and patching to the roofing
manufacturer's approved local contractor. Provide the government with a letter confirming his
authority to perform such work prior to commencing the work.
E. Exterior Building Enclosure: Close openings in exterior surfaces to protect existing work from
weather and extremes of temperature and humidity. Insulate ductwork and piping to prevent
condensation in exposed areas. Maintain the security system and secure openings nightly.
F. Visual Requirements: Do not cut and patch construction exposed on the exterior or in occupied
spaces in a manner that would, in the Contracting Officer's opinion, reduce the buildings
aesthetic qualities. Do not cut and patch construction in a manner that would result in visual
evidence of cutting and patching. Remove and replace construction cut and patched in a
visually satisfactory manner.
A. Existing Warranties: Replace, patch, and repair material and surfaces cut or damaged by
methods and with materials in such a manner as not to void warranties required or existing.
1.4 MATERIALS
A. Use materials identical to existing materials. For exposed surfaces, use materials that visually
match existing adjacent surfaces to the fullest extent possible. If identical materials are
unavailable or Contractor cannot find, use materials whose installed performance will equal or
surpass that of existing materials.
1. New Materials: As specified on product Sections; match existing products for patching
and extending work. Install work according to manufacturer and special standards.
2. Type and quality of existing products; determine by inspection and testing products
where necessary, install work according standards.
1.5 INSPECTION
A. Examine surfaces Contractor will cut and patch and conditions under which Contractor will cut
and patch before cutting. If unsafe or unsatisfactory conditions exist, take corrective action
before proceeding.
B. Verify demolition is complete and areas are ready for installation of new work.
1.6 PREPARATION
C. Protection: Protect existing construction during cutting and patching to prevent damage.
Provide protection from adverse weather for portions of the project exposed during cutting and
patching operations.
D. Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.
E. Verify and identify the existence of underground or hidden conduits, plumbing, or voice/data
circuits.
F. Do not cut active pipe, conduit, or ductwork scheduled for removal or relocation and serving an
occupied building until Contractor either bypasses them or provides alternate services to the
affected areas of the building.
G. Examine surfaces to be cut and patched and conditions under which cutting and patching are to
be performed.
I. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.
J. Cut, move or remove items as necessary for access to alterations and renovation work.
Replace and restore at completion.
K. Remove unsuitable material not marked for salvage, such as rotted wood, corroded metals, and
deteriorated masonry and concrete. Replace materials as specified for finished work.
L. Prepare surface and remove surface finishes to provide for proper installation of new work and
finishes.
1.7 PERFORMANCE
A. General: Employ skilled workmen to perform cutting and patching. Proceed with cutting and
patching at the earliest feasible time and complete without delay.
1.8 CUTTING
A. Verify underground or hidden electrical conduits, piping etc. have been identified before cutting.
B. Cut existing construction using methods least likely to damage elements retained or adjoining
construction. Where possible, review proposed procedures with the original installer; comply
with the original installer's recommendations.
C. When cutting, use hand or small power tools designed for sawing or grinding, not hammering
and chopping. Cut holes and slots as small as possible, neatly to size required, and with
minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
D. To avoid marring existing finished surfaces, cut or drill from exposed or finished side into
concealed surfaces.
E. Cut through concrete and masonry using a cutting machine, such as a carborundum saw or a
diamond-core drill.
F. Comply with requirements of applicable Division 31 Section Earthwork where cutting and
patching requires excavating and backfilling.
G. Except as otherwise indicated in Divisions 23 and 26, comply with the following:
1. Cut-off pipe or conduit in floors, walls or partitions to be removed. Cap, valve, or plug
and seal the remaining portion of pipe or conduit to prevent entrance of moisture or other
foreign matter after by-passing and cutting.
A. Patch with durable seams that are as invisible as possible. Comply with specific tolerances.
B. Where feasible, inspect and test patched areas to demonstrate integrity of the installation.
C. Patch construction by filling, repairing, refinishing, closing up, and similar operations following
performance of other Work. Patch with durable seams that are as invisible as possible.
Provide materials and comply with installation requirements specified in other Sections of these
Specifications.
D. Restore exposed finishes of patched areas and extend finish restoration into retained adjoining
construction in a manner that will eliminate evidence of patching and refinishing.
E. Where removing walls or where partitions extends one finished area into another, patch and
repair floor and wall surfaces in the new space. Provide an even surface of uniform color and
appearance. Remove existing floor and wall coverings and replace with new materials as
required by the contract documents to achieve uniform color and appearance.
1. Where patching occurs in a smooth painted surface, extend final paint coat over entire
unbroken surface containing the patch after the area has received primer and second
coat.
2. Where new work abuts or aligns with existing, perform a smooth and even transition.
Patch work to match existing adjacent work in texture and appearance.
3. When finished surfaces are cut so that a smooth transition with new work is not possible,
terminate existing surface along a straight line at a natural line of division. Make
corrective action recommendations to the Contracting Officer.
G. Plaster Installation: Comply with the manufacturer's instructions and installation thickness and
coats as indicated.
1.10 FINISHES
B. Finish patches to uniform finish and texture over entire area. When Contractor cannot match
finish, refinish entire surface to nearest intersections.
1. Remove debris and abandoned items from the area and from concealed spaces.
2. Clean areas and spaces where cutting and patching are performed. Completely remove
paint, oils, putty, and similar items. Thoroughly clean piping, conduit, and similar features
before applying paint or other finishing materials. Restore damaged pipe covering to its
original condition.
END OF SECTION
CLOSEOUT PROCEDURES
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1. Administrative and procedural requirements for contract close-out, including but not
limited to:
1.2 SUBMITTALS
B. Submittal Schedule:
C. Submittal List:
Reference Submittal Item Quantity Action
A. Prior to request for phase inspection, perform all necessary quality control and final clean
actions. This includes working off all QC program punch list items and cleaning areas to a
condition suitable for government occupancy.
B. Employ experienced workers for final cleaning. Clean each surface to the condition expected in
a commercial building cleaning and maintenance program. Complete the following before
requesting a phase inspection.
A. Prior to turn over of any phase to the Government, submit a written request for an acceptance
inspection to the Government. Do not submit request less than two weeks prior to the proposed
inspection date. The Government will not accept a phase unless all construction, finishes,
equipment, and systems are fully operational and there are no limits to the intended use of the
area and systems in that phase or previously accepted phases. At their discretion, the
Government may accept a phase with minor incomplete punch list items. If so, complete all
punch list items in each phase accepted within two weeks of the date of acceptance.
B. At the conclusion of each phases QC and final clean actions, submit, in writing, to the
Contracting Officer, a request for phase inspection and turnover.
C. Commensurate with the request for phase inspection and turnover, provide the Contracting
Officer with the following:
1. The CQC punch list and its current status. Include on a separate punch list all
outstanding administration items required to complete the Work. The CQC punch list
submitted in conjunction with the request for final inspection of a completed phase of the
Work may list incomplete construction items as well as those completed construction
items requiring minor adjustment or correction. However, the government will not perform
the actual formal inspection until all construction items are complete and only minor
adjustments or corrections remain to finish the Work.
2. Warranty dates.
D. A government team will inspect the areas, verify the Contractors CQC punch list, and make any
necessary corrections or additions to it. The punch list as modified by the government team
shall represent a conformed punch list. The Contracting Officer will determine the Work to be
complete only after the contractor completes all punch list items to the Contracting Officers
satisfaction.
E. Do not proceed with a subsequent phase until completion of all punch list and administration
items on this current phase.
A. Maintenance Manuals: Furnish for approval six complete maintenance manuals for all materials
and equipment. Organize maintenance data into sets of manageable size. Make each manual
8-1/2 inches by 11 inches, heavy-duty vinyl hard cover, 3 ring, loose leaf style, with pocket
folders for folded sheet information and divider leafs with index tabs; be fully labeled in large,
KROY or MERLIN letters on edge and front, etc. Insert master Index and tab by section in each
binder. Mark identification on front and spine of each binder. Include the following information:
1. Part 1:
a) Architect.
b) Engineer.
c) Contractor.
d) Subcontractor.
2. Part 2:
1) Copies of warranties.
2) Appropriate design criteria.
3) Listing of equipment.
4) Parts list.
5) Spare parts list.
6) Operating instructions.
7) Manufacturer letters of certification.
8) Maintenance instructions - equipment.
9) Maintenance instructions - finishes.
10) Shop drawings and product data (government's copy of all accepted
submittals).
11) Wiring diagrams.
a) Water purity.
b) Test and Balance report.
c) Water treatment.
d) Sound system.
e) Fire alarm system.
f) Sprinkler system.
B. Notify the Governments Designated Inspector seven days prior to instruction sessions so he
may be present.
C. Submit an Instruction Certification Letter prepared by the contractor and signed by the
Contracting Officer and the contractor certifying that the below instruction is satisfactorily
complete.
D. After the systems are fully operational and Government approval for O&M manual distribution
and completed HVAC test and balance reports have been received, instruct the government's
representatives in the operation and maintenance of the systems. The approximate number of
trainees will typically number about 20. Coordinate with the Governments Designated
Inspector. Provide trainers with at least 5 years experience in training operators and technical
persons on the same system. Provide instructional material as handouts for each of these
classes. This service includes:
1. Arrange for the installer of equipment that requires regular maintenance to meet with the
Government's personnel to provide instruction in proper operation and maintenance.
Include a detailed review of the following:
a. Maintenance manuals.
b. Spare parts and materials.
c. Tools.
d. Lubricants.
e. Control sequences.
f. Hazards.
g. Warranties and bonds.
Discipline
Minimum number of trips to Minimum hours of instruction
project
Plumbing 2 4
HVAC 2 4
Electrical 2 4
Fire Protection 2 4
Refrigeration & RMCS Comply with Division 23 Sections Comply with Division 23 Sections
Product Refrigeration Systems, Product Refrigeration Systems,
Refrigeration Monitoring and Refrigeration Monitoring and
Control Systems (RMCS), and Control Systems (RMCS), and
others as applicable others as applicable
F. See Division 01 Section Demonstration and Training for additional operational and training
requirements.
A. Warranty Dates:
1. Add/Alter Projects: The warranty periods for Add/Alter projects begin the date the
government begins beneficial occupancy of that phase. Warranties for items such as
refrigeration racks and piping, mechanical, and other electrical systems begin the day of
beneficial occupancy (not component installation date) and acceptance of the last part of
the system as a whole. The warranty period remains in effect for not less than one year.
Refer to other sections of the specifications for particular items requiring warranty
duration in excess of one year.
2. New Stores: The warranty periods begin on the date of beneficial occupancy (not
component installation date) of the entire building. The warranty period remains in effect
for not less than one year. Refer to other sections of the specifications for particular
items requiring warranty duration in excess of one year.
B. Warranty Inspection:
1. Approximately nine months after the date acceptance, return to the Project with the
Contracting Officer or Governments Designated Inspector, to conduct an inspection to
determine whether the work completed by the Contractor is performing according to the
requirements of the Contract Documents. Work not conforming to these requirements
may be considered defective. The Contracting Officer or Governments Designated
Inspector will prepare a comprehensive list of items for correction and, in cooperation
with the Contractor, fix the time to correct or furnish all items on the list. Proceed
promptly to correct items on the list.
E. Definitions:
F. Warranty Requirements:
G. Warranty Process:
1. Instruct and train the commissary staff on the warranty and notification process.
a. Should the commissary require warranty service, the commissary will list in writing
the symptom then Fax to the general contractor and the appropriate trade or
supplier (if ascertainable by the commissary).
H. Submittals:
1. Submit written warranties to the Contracting Officer prior to the final inspection.
a. When a designated portion of the Work is complete and occupied or used by the
Government, by separate agreement with the Contractor during the construction
period, submit properly executed warranties to the Contracting Officer within 15
days of completion of that designated portion of the Work.
b. When the Contract Documents require the Contractor, or the Contractor and a
subcontractor, supplier or manufacturer to execute a special warranty, prepare a
written document that contains appropriate terms and identification, ready for
execution by the required parties. Submit a draft to the Government, through the
Contracting Officer, for approval prior to final execution.
c. Refer to Divisions 02 through 33 Sections for specific content requirements and
particular requirements for submitting special warranties.
d. Upon completion of construction, ownership of the building will be transferred to
the Installation upon which the facility is located, via DD Form 1354 "Transfer and
Acceptance of Military Real Property". Special warranties shall be issued to the
Installation as identified in this Section, under paragraph "Real Property Records".
e. Form of Submittal: At final completion, compile each required warranty properly
executed by the Contractor, or by the Contractor, subcontractor, supplier, or
manufacturer. Organize the warranty documents into an orderly sequence based
on the table of contents of the project manual. Include extended Warranties (for
specific equipment with more than one year guarantee) such as:
1) Heat exchangers.
2) Refrigeration compressors.
3) Battery units.
4) Roof.
1) Provide heavy paper dividers with tabs for each separate warranty. Mark
the tab to identify the product or installation. Provide a typed description of
the product or installation, including the name of the product, and the name,
address, and telephone number of the installer.
2) Identify each binder on the front and spine with the typed or printed title
"WARRANTIES," Project title or name, and name of the Contractor.
3) List in each binder a master list of the General Contractor and installing
firms points of contract, including firm names, contact person, address,
telephone, and FAX number.
4) When warranted construction requires operation and maintenance manuals,
provide additional copies of each required warranty, as necessary, for
inclusion in each required manual.
A. General: Do not use record documents for construction purposes; protect from loss in a secure
location; provide access to record documents for the Contracting Officer's reference.
B. As-Built (Record) Drawings: Maintain one clean, undamaged set of blue or black line prints of
Contract Drawings and Shop Drawings at the job-site. Using red ink, mark up these drawings to
show the actual installation. Mark whichever drawing is most capable of showing conditions
accurately. Give particular attention to concealed elements that would be difficult to measure
and record later.
1. Update the set each month with all changes taking place during the previous period.
2. The Construction Contract Inspector will review the status of the Record Field Data
monthly, prior to processing the Contractor's invoice for progress payment. The
Contracting Officer may hold retention against any invoice should the data not be current
at the time of the invoice.
3. At final completion of the work, submit for approval, record documents reflecting all
additions, and revisions which vary from the Contract Documents.
4. Show all deviations in actual construction from the Contract Drawings, and note the type
of material used whenever a material option is specified. Show these deviations in the
same general detail utilized in the Contract Drawings.
5. Maintain full size marked-up drawings, survey notes, sketches, nameplate data,
description, and serial numbers of all installed equipment. Maintain this information in a
current condition at all times until completion of the work. The resulting field marked
prints shall be referred to and marked as "Record Field Data," and shall be used for no
other purpose.
6. Make set available for inspection by the Construction Contract Inspector whenever
requested during construction, and submit them for approval at the completion of
construction.
7. Delineate and locate dimensionally on the prints features not already shown on the
Contract Drawings which are encountered by the Contractor during construction and
which might interfere with future construction, such as pipes, conduits, electrical cables,
or the like buried in the ground, in concrete, or otherwise hidden. Specifically record the
following information:
a. Locations of all Work buried under or outside each building, such as plumbing and
electrical lines and conduits, points of connection with existing utilities, changes in
direction, valves, manholes, catch basins, capped stub outs, invert elevations, etc
b. Actual numbering of each electrical circuit.
c. Locations of significant Work concealed inside each building whose general
locations change from those shown on the Contract.
d. Locations of all items, not necessarily concealed, which vary from the Contract
Documents.
e. Installed location of all cathodic protection anodes.
f. Deviations from the sizes, locations, and other features of installations shown in
the Contract Documents.
g. Sufficient information to locate Work concealed in each building with reasonable
ease and accuracy. In some instances, this may be by dimension, in others it may
be in relation to the nearby building.
D. Record Specifications:
E. Record Document Deliverable: Contractor shall provide the project records, specifications, and
As-built Drawings in AutoCAD format on CD. Contractor shall ask the Contracting Officer what
version of AutoCAD is acceptable prior to developing electronic version of As-Built Drawings.
A. Employ experienced workers for final cleaning. Clean each surface to the condition expected in
a commercial building cleaning and maintenance program. Use cleaning products
recommended by the manufacturer of the surface to be cleaned that comply with Green Seals
GS-37, or if GS-37 is not applicable use products that comply with California Code of
Regulations maximum allowable VOC levels. Complete the following before requesting final
inspection.
1. Restore permanent facilities consumed during the construction period including, but not
limited to, the following:
2. Generate a QC management team punch list, submit the list to the Governments
Designated Inspector, and then work off the list in its entirety.
3. Submit specific warranties, maintenance agreements, final certifications and similar
documents.
4. Submit record drawings, maintenance manuals, equipment brochures, warranties and
bonds, and similar final record information.
5. Change over permanent locks and transmit keys to the Contracting Officer.
6. Complete start-up testing of systems, commissioning, and Government's personnel
training. Remove temporary facilities from the site, along with construction tools, mock-
ups, and similar elements.
7. Complete final clean. Touch up, repair, and restore marred exposed finishes.
B. Inspection Procedures:
2. Attach the written certification to a request for final inspection and forward to the
Contracting Officer.
3. The Contracting Officer will arrange for Government inspection personnel to perform the
inspection. After the inspection, the Contracting Officer will advise the contractor of the
work necessary before the Government can accept the project and the work remaining
for the contractor to complete the project.
C. Results of the completed inspection will form the basis of requirements for final acceptance.
A. 30 Days prior to Beneficial Occupancy and under the direction of the Real Property Accounting
Officer from the military installation of the project site, prepare the DD Form 1354, "Transfer and
Acceptance of Military Real Property" and submit to the Contracting Officer.
2. List items including but not necessarily limited to, the following:
a. DD Form 1354 Preparation File. This file contains a link to a fillable PDF 1354
form. Instructions on how to fill out each block of the form and a DD Form 1354
Check list.
1.12 PARTS
A. Provide written receipt signed by Commissary Store Director for all "loose" items turned over
such as:
A. Before requesting inspection for certification of final acceptance and final payment, submit a
copy of the final inspection list stating that each item is complete or otherwise resolved for
acceptance.
B. Re-inspection Procedure: The Contracting Officer will re-inspect the Work upon receipt of
notice that the Work is complete, except items whose completion delayed because of
circumstances acceptable to the Contracting Officer.
C. Upon completion of re-inspection, the Contracting Officer will prepare a certificate of final
acceptance, or advise the Contractor of Work that is incomplete or obligations unfulfilled.
END OF SECTION
1. Building:
1.1. Outside dimensions: SM
A. Main building: SM
B. Wings SM
C. Offsets SM
1.2. Number of floors:
1.3. Construction:
A. Foundations (such as concrete) TYPE
B. Floors (such as wood, concrete) TYPE
C. Walls (such as wood siding) TYPE
D. Roof (such as built-up, shingle) TYPE
1.4. Utilities entering building:
A. Water (size of pipe)
B. Gas (size of pipe)
C. Sewer (size of pipe)
D. Electric (phase, voltage, wire, connected load)
1.5. Landscape:
2. Systems in building:
2.1. Fire Protection:
Category Nomenclature Unit of Quantity Cost
Code Measure
880-211 Clsd Hd Auto Spklers SM
Number of Sprinkler Heads EA N/A
880-212 Open Hd Deluge Sys SM
Number of Sprinkler Heads EA N/A
880-221 Auto Fire Detection Sys SM
(Heat Detectors) EA
(Horns) EA
(Alarm Bells) EA
(Smoke Detectors) ( ) EA
(Manual Pull Station) EA
880-222 Manual Fire Alarm Sys EA
880-231 CO2 Fire Sys EA
880-232 Foam Fire Sys EA
880-233 Other Fire Sys EA
(Smoke Detectors) ( )
(Standpipe Connections) ( )
(Dry Chemical Sys) ( )
9. Cost of construction management activities, other than in-house efforts, to provide construction
surveillance and oversight management during construction.
Nomenclature Unit of Amount Cost
Measure
Demolition cost SF
Addition or Deletion of SF
Related Facilities SF
INSTRUCTIONS TO PREPARE DD FORM 1354 DATA FIELDS. The page number and the total number of pages
comprising each 1354 project or transaction shall be shown in the space provided at the top right-hand corner of the
form. When two or more pages are required to describe the information required for blocks 1 through 23, then blocks
24 through 26 (signatures and voucher number) shall be completed only on the first or signature page. Signing
officials should initial subsequent or unsigned pages and line through the Property Voucher Number block on all
except the signed page. The remainder of this chapter explains in detail what the data are and where data come from
to complete the individual data element blocks on the DD Form 1354. A single example is used for all the example
entries to the DD Form 1354 data fields in the remainder of this chapter. The example is a Military Construction, Army
(MCA) project to construct a new battalion headquarters and classroom, and associated structures and utilities. A
summary of these instructions is provided as Appendix C for quick reference and for publishing in the next update of
the FMR.
Block 1. [FROM]. Enter in block 1 Defense Commissary Agency (DeCA). You should include the full address and zip
code.
Example: Defense Commissary Agency (DeCA)
2250 Foulois Street
Lackland AFB, TX 78236
Block 2. [DATE PREPARED]. Enter the date the DD Form 1354 is prepared. Use the DoD standard YYYYMMDD
format for all dates. This is the date used to track different editions when revisions are necessary. The form is
considered prepared when it is ready for signatures in blocks 24 and 25.
Example: Use 20040115 for date: 15 JAN 2004
Block 3. [PROJECT/JOB NUMBER]. Enter the project number assigned to identify the project on a DD Form 1391
for new military construction (MILCON) or the job order number for other projects.
Examples: DD Form 1391 project number might be EA01MP01.
Block 4. [SERIAL NUMBER]. This is the document number assigned to the 1354 by DeCA/ PMFM. This shall be left
blank by the construction contractor and PMAC.
Block 5. [TO]. Enter the name of the receiving organization or agency to which the transfer will be made. This
receiving organization could be the DPW/FacMgr/BCE/DIS on a DoD installation that has been assigned the
responsibility for accounting for the real property. Always include the address, zip code, and installation number the
unique identifier of the installation - which the RPAO represents. Installation numbers are available from individual
service databases of installations or can be provided by the gaining installation Realty Specialist.
Example: Engineering Plans & Services Division
Directorate of Public Works
Fort Riley, KS 66442-6000
INSNO 20605
Block 6. [SITE/INSNO/NAME]. Site number or installation number of the actual facility physical location is one of the
first points of entry into the database. Enter in block 6 the site number identifier or installation number (INSNO) and
site name where the facility being transferred/accepted is physically located. Enter this number and name regardless
of whether it is the same or different from the location of the RPAO (which is identified in block 5).
Example: 20605/Riley (In this example it happens to be the same as the
identifier in block 5).
ITEM 4 SERIAL NUMBER Serial number assigned in sequence by the preparing organization.
Identify the fiscal year, and sequence number; for example, 2004-0001,
2004-0002, etc.
ITEM 5 TO Name and address of the receiving installation, activity, and service.
Include zip code and installation number (INSNO) of receiving installation,
which the RPAO
represents.
ITEM 6 SITE/INSNO/ Site or installation number and site name where the
NAME facility being constructed/transferred/accepted is located.
ITEM 7 CONTRACT Contract number(s) if any project work is performed
NUMBER(S) under a contract.
ITEM 8 DRAWING Enter the drawing number(s) or CAD identifier(s) for the
NUMBER(S) project components.
ITEM 9 TRANSACTION Has four subparts
DETAILS
SUBPART TYPE of Checkbox to indicate whether the DD Form 1354 applies
9A TRANSACTION to acceptance of new construction, transfer of existing
facilities, a capital improvement to existing facilities, or
other. Enter remarks in block 28 "Project Remarks" if "other" is specified.
Mark only one box.
TOTAL QUANTITY- The total area for the measure identified in Item 15. Use negative
ITEM 16
UM1 numbers for demolition.
ITEM 17 OTHER: UNIT OF The Unit of Measure 2 for capacity or other measurement unit. Use
MEAS-2 abbreviations, such as "MB" for millions of BTU, found in DODI 4165.3.
ITEM 20 FUND SOURCE Fund source for this Item. Use the Item Remarks (column 23) to explain
funding for this item if necessary. See Appendix E.
ITEM 21 FUNDING The organization responsible for replacing this facility at the end of its
ORGANIZATION useful life (e.g., Army, Air Force, Navy, Marine Corps (specify component
for each service), DLA, DeCA, TMA, etc.). See Appendix F.
ITEM 22 INTEREST CODE Indicator of the governments interest or ownership in the facility (e.g.,
DoD owned, leased, State owned, privately owned, etc.). See Appendix
G.
ITEM 23 ITEM REMARKS Include any clarifying remarks pertaining only to the item number
identified in column 10. Also summarize any cost sharing or prorating
logic that would document how you derived the item cost.
ITEM 24 STATEMENT OF Name, signature, title and date of signature by the individual responsible
COMPLETION for the transfer of the properties.
ITEM 25 ACCEPTED BY Name, signature, title and date of signature by the RPAO or delegated
individual responsible for accepting the property.
ITEM 26 PROPERTY Next sequential number assigned by the RPAO in the Register of
VOUCHER NUMBER Vouchers to a Stock Record Account (e.g., DA Form 272 or Navy system
assigned number).
ITEM 27 CONSTRUCTION All construction deficiencies in the project known or identified during the
DEFICIENCIES construction contractor turnover inspection.
ITEM 28 PROJECT REMARKS Any information to explain "other" entries in blocks 9A or 9B and other
information that would be helpful in understanding the transaction. Also
used for project level remarks and continuation where more space is
needed.
Facility Number of
Number Building Name Floors Gross SF Net SF
Main Building
Wings
Offsets
Basement
Attic
Porches, covered
Roof
Foundation
Other Building Data Feet
Ceiling Height Main Bldg
Ceiling Height Basement
Door Height
Door Width
Code
Fire Rating Code
Pile or Foundation
Foundation Form Material
Available or
Number of Diameter of Capacity of all Connected?
Utility Connections (Yes/No)
pipes each pipe inlet pipes
Water
Gas
Sewer Pipe
Storm Sewer
Pipe
Steam
Condensate
Communications
Heating
Air Conditioning
Hot Water
Steam
Electrical
UFC 1-300-08
30 JUNE 2004
Security System
Security Alarm System EA
Heating System
Heating Plant MB
Storage Tank for Heating Fuel GA
Electrical System
Emergency Electric Power KW/KV
Generator A
Storage Tank for Generator Fuel GA
Hot Water
Theater-type Seats,
bolted to floor
PN
Other (SPECIFY)
Gas Mains LF
Septic Systems KG
Sanitary Sewer LF
Water Dist Mains LF
Fire Hydrants EA
Telephone Duct LF
Telephone Pole LF
FUND SOURCE
Choose the correct Fund Source for block 20 from Appendix E.
APPENDIX
Abbreviation Fund Source Full Name
E Code
04 RDTE
Research, Development, Test, and
Evaluation
08 PROCURE Procurement
12 PRIVATE Private/Donation
02 Owned by Federal Government Federal Government-owned real property facilities (other than DoD)
(Non-DoD) that are licensed or permitted to the DoD. Example: Laboratory facility
at the National Institutes of Health occupied by TRICARE Management
Activity. Do not include facilities acquired from the General Services
Administration (GSA) under this code. See Code 3 below.
03 Owned by Private Sector-Leased A lease is a written agreement that conveys an interest, based on
to DoD Component possession, in real property, usually exclusive, for a period of time for a
specified consideration. Include under this code all General Services
Administration (GSA) leases for use by DoD. Example: Office of the
Secretary of Defense at 400 Army-Navy Drive
04 Owned by Other Than DoD - An easement is a real estate instrument that grants the right to use
Land Easement property (land only) for a specific purpose. It may be temporary or
permanent. Example: permission for an Air Force installation to cross
private property and/or public domain property with a utility line either
underground or overhead.
05 Owned by Foreign Government Foreign Government-owned real property facilities that are licensed or
permitted to DoD. Example: US Army barracks in Heidelberg, Germany
or Navy NATO facilities in Italy.
06 Owned by Other Foreign Source Real property facilities leased from a foreign private sector for use by
DoD. Example: US Marine Corps apartment complex located in
Okinawa, Japan, and leased from a private realtor.
07 Privately Owned and Operated Real property facilities on DoD sites that are owned and operated by
the private sector. Examples: Burger King Restaurant or a privatized
utility.
08 Owned by State or Local Real property facilities owned by a state or local government or other
Government public entity. Examples: Army National Guard maintenance facility at
Camp Blanding, FL, a state owned military site.
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 SUBMITTALS
A. Instruction Program: Submit two copies of outline of instructional program for demonstration
and training, including a schedule of proposed dates, times, length of instruction time, and
instructors' names for each training module. Include learning objective and outline for each
training module.
1. At completion of training, submit one complete training manual(s) for Government's use.
C. Attendance Record: For each training module, submit list of participants and length of
instruction time.
D. Evaluations: For each participant and for each training module, submit results and
documentation of performance-based test.
E. Demonstration and Training Videotapes: Submit two copies within seven days of end of each
training module.
a. Name of Project.
b. Name and address of photographer.
c. Name of DeCA Program Management Assistance Contract Inspector (PMAC).
d. Name of Contractor.
e. Date videotape was recorded.
f. Description of vantage point, indicating location, direction (by compass point), and
elevation or story of construction.
1. Review and finalize instruction schedule and verify availability of educational materials,
instructors' personnel, audiovisual equipment, and facilities needed to avoid delays.
2. Review required content of instruction.
3. For instruction that must occur outside, review weather and forecasted weather
conditions and procedures to follow if conditions are unfavorable.
1.4 COORDINATION
A. Coordinate instruction schedule with PMAC and Store Director. Adjust schedule as required to
minimize disrupting Government's operations.
B. Coordinate instructors, including providing notification of dates, times, length of instruction time,
and course content.
C. Coordinate content of training modules with content of approved emergency, operation, and
maintenance manuals. Do not submit instruction program until operation and maintenance data
has been reviewed and approved by PMAC.
A. Program Structure: Develop an instruction program that includes individual training modules for
each system and equipment not part of a system, as required by individual Specification
Sections, and as follows:
1. Motorized doors, including overhead coiling doors and automatic entrance doors.
2. Equipment, including loading dock equipment, grease hoods and food-service
equipment.
3. Fire-protection systems, including fire alarm and fire-extinguishing systems.
4. Intrusion detection systems.
5. Conveying systems, including elevators.
6. HVAC systems, including air-handling equipment, air distribution systems and terminal
equipment and devices.
7. HVAC instrumentation and controls.
8. Electrical service and distribution, including transformers, switchboards, panelboards,
uninterruptible power supplies and motor controls.
9. Packaged engine generators, including transfer switches.
10. Lighting equipment and controls.
11. Communication systems, including intercommunication, surveillance, clocks and
programming, voice and data, and television equipment.
B. Training Modules: Develop a learning objective and teaching outline for each module. Include
a description of specific skills and knowledge that participant is expected to master. For each
module, include instruction for the following:
1. Basis of System Design, Operational Requirements, and Criteria: Include the following:
a. Emergency manuals.
b. Operations manuals.
c. Maintenance manuals.
d. Project Record Documents.
e. Identification systems.
f. Warranties and bonds.
g. Maintenance service agreements and similar continuing commitments.
a. Startup procedures.
b. Equipment or system break-in procedures.
c. Routine and normal operating instructions.
d. Regulation and control procedures.
e. Control sequences.
f. Safety procedures.
g. Instructions on stopping.
h. Normal shutdown instructions.
i. Operating procedures for emergencies.
j. Operating procedures for system, subsystem, or equipment failure.
k. Seasonal, weekend and unoccupied modes of operation operating instructions.
l. Required sequences for electric or electronic systems.
m. Special operating instructions and procedures.
a. Alignments.
b. Checking adjustments.
c. Noise and vibration adjustments.
d. Economy and efficiency adjustments.
a. Diagnostic instructions.
b. Test and inspection procedures for collecting specific performance data.
a. Inspection procedures.
b. Types of cleaning agents to be used and methods of cleaning.
c. List of cleaning agents and methods of cleaning detrimental to product.
d. Procedures for routine cleaning.
e. Procedures for preventive maintenance.
f. Procedures for routine maintenance.
g. Instruction on use of special tools.
a. Diagnosis instructions.
b. Repair instructions.
c. Disassembly; component removal, repair, and replacement; and reassembly
instructions.
d. Instructions for identifying parts and components.
e. Review of spare parts needed for operation and maintenance.
3.1 PREPARATION
A. Assemble educational materials necessary for instruction, including documentation and training
module. Assemble training modules into a combined training manual.
3.2 INSTRUCTION
A. Engage qualified instructors to instruct Government's personnel to adjust, operate, and maintain
systems, subsystems, and equipment not part of a system.
1. PMAC and Store Director will furnish Contractor with names and positions of participants.
B. Scheduling: Provide instruction at mutually agreed on times. For equipment that requires
seasonal operation, provide similar instruction at start of each season.
1. Schedule training with PMAC and Store Director with at least seven days' advance
notice.
C. Evaluation: At conclusion of each training module, assess and document each participant's
mastery of module by use of a written performance-based test.
D. Cleanup: Collect used and leftover educational materials and give to PMAC and Store Director.
Remove instructional equipment. Restore systems and equipment to condition existing before
initial training use.
1. At beginning of each training module, record each chart containing learning objective and
lesson outline.
C. Recording: Mount camera on tripod before starting recording, unless otherwise necessary to
show area of demonstration and training. Display continuous running time.
E. Transcript: Provide a typewritten transcript of the narration. Display images and running time
captured from videotape opposite the corresponding narration segment.
***********************************************************
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 DESCRIPTION
A. Commissioning:
1. This project will have selected building systems commissioned. The commissioning
process will be directed by the Contractor and monitored by the Government
Commissioning Representative (GCR) whose services will be provided by the
Government.
2. Commissioning is a systematic process of ensuring that all building systems perform
interactively according to the design intent and the Governments operational needs.
This is achieved by actual verification of performance. The commissioning process
encompasses and coordinates the functions of system documentation, equipment
startup, control system calibration, testing and balancing, performance testing and
training. Commissioning during the construction phase is intended to achieve the
following specific objectives according to the Contract Documents:
a. Verify that applicable equipment and systems are installed according to the
manufacturers recommendations and to industry accepted minimum standards
and that they receive adequate operational checkout by installing contractors.
b. Verify and document proper performance of equipment and systems.
c. Verify that O&M documentation is complete.
d. Verify that the Governments operating personnel are adequately trained.
C. Abbreviations. The following are common abbreviations used in the Specifications and in the
Commissioning Plan.
B. Provision of a fully commissioned system of all materials required under the construction
contract is the responsibility of the General Contractor. Therefore, Contractor Group members
of the Systems Commissioning Team, through participation in the planning, management, and
oversight of all construction activities related to equipment approvals, performance testing, and
commissioning of the systems identified herein must be able to assure the Government that all
systems have been properly tested and commissioned. The Government and User members
are intended to participate fully as adjuncts to the Contractor Group Team members. It is
intended that through this participation, the Contractor Group Team members will be provided
timely access to all design information necessary to resolve questions as to intended
performance of the systems specified. In addition, the Government will be sufficiently involved in
the development of commissioning and performance testing programs to assure timely review
of plans and procedures submitted by the Contractor. The purpose of this process will be to
provide fully functional systems which interact to meet all contract performance requirements.
The participation of the Government Commissioning Team members shall not relieve the
General Contractor of any responsibility for compliance with the requirements of the contract.
D. Scheduling:
1. The GCR will work with GC according to established protocols to schedule the
commissioning activities. The GCR will review the Construction Schedule and verify that
prefunctional and functional testing is properly scheduled. The GC will integrate all
commissioning activities into the master schedule.
2. Commissioning inspections and testing will be accomplished in the presence of a
representative of the Contracting Officer.
A. Commissioning Plan:
1. An initial Commissioning Plan has been developed for this project and is included
elsewhere in the Bid Documents. The commissioning plan provides guidance and further
details the requirements in the execution of the commissioning process. The
Specifications take precedence over the Commissioning Plan in the event of a conflict.
The Contractor shall ensure that the initial commissioning plan is complete. Any missing
or incomplete Pre-functional Checklists or Functional Checklists shall be provided or
completed by the construction contractor.
B. Commissioning Process: The following narrative provides a brief overview of the typical
commissioning tasks during construction and the general order in which they occur.
7. The Subs, under their own direction, execute and document the Functional checklists
with the QC verifying and the TI monitoring conformance.
8. Items of non-compliance in material, installation or setup are noted for the Contractor to
correct. Non-complying systems will then be retested and functional performance verified
by the QC and monitored by the TI.
9. All functional performance tests are completed before Beneficial Occupancy Date.
10. The QC and TI review the O&M documentation for completeness.
11. The QC and TI review the training plan provided by the Subs. The QC and TI will witness
training session(s) to verify that acceptable training was provided.
A. Duties and responsibilities of the GCR are set forth in the Commissioning Plan.
1.6 DEFINITIONS
Acceptance Phase - phase of construction after startup and initial checkout when functional
performance tests, O&M documentation review and training occurs.
Commissioning Plan - an overall plan, developed before bidding, that provides the structure,
schedule, and coordination planning for the commissioning process.
Datalogging - monitoring flows, currents, status, pressures, etc. of equipment using stand-alone
dataloggers separate from the control system.
Deferred Functional Tests - FTs that are performed later, after substantial completion, due to
partial occupancy, equipment, seasonal requirements, design or other site conditions that
disallow the test from being performed.
Functional Performance Test (FT) - test of the dynamic function and operation of equipment
and systems using manual (direct observation) or monitoring methods. Functional testing is the
dynamic testing of systems (rather than just components) under full operation (e.g., the chiller
pump is tested interactively with the chiller functions to see if the pump ramps up and down to
maintain the differential pressure setpoint). Systems are tested under various modes, such as
during low cooling or heating loads, high loads, component failures, unoccupied, varying
outside air temperatures, fire alarm, power failure, etc. The systems are run through all the
control systems sequences of operation and components are verified to be responding as the
sequences state. Traditional air or water test and balancing (TAB) is not functional testing.
TABs primary work is setting up the system flows and pressures as specified, while functional
testing is verifying that which has already been set up. The Government Commissioning
Representative develops the functional test procedures in a sequential written form,
coordinates, oversees and documents the actual testing, which is usually performed by the
installing contractor or vendor. FTs are performed after prefunctional checklists and startups
are complete.
Manual Test - using hand-held instruments, immediate control system readouts or direct
observation to verify performance (contrasted to analyzing monitored data taken over time to
make the "observation").
Monitoring - the recording of parameters (flow, current, status, pressure, etc.) of equipment
operation using dataloggers or the trending capabilities of control systems.
Over-written Value - writing over a sensor value in the control system to see the response of a
system (e.g., changing the outside air temperature value from 50F to 75F to verify economizer
operation). See also "Simulated Signal."
Phased Commissioning - commissioning that is completed in phases due to the size of the
structure or other scheduling issues, in order to minimize the total construction time.
Prefunctional Checklist (PC) - a list of items to inspect and elementary component tests to
conduct to verify proper installation of equipment, provided by the GCR to the Sub.
Prefunctional checklists are primarily static inspections and procedures to prepare the
equipment or system for initial operation (e.g., belt tension, oil levels OK, labels affixed, gages
in place, sensors calibrated, etc.).
Sampling - functionally testing only a fraction of the total number of identical or near identical
pieces of equipment.
Seasonal Performance Tests - FT that are deferred until the system(s) will experience
conditions closer to their design conditions.
Simulated Condition - condition that is created for the purpose of testing the response of a
system (e.g., applying a hair blower to a space sensor to see the response in a VAV box).
Simulated Signal - disconnecting a sensor and using a signal generator to send an amperage,
resistance or pressure to the transducer and DDC system to simulate a sensor value.
Test Procedures - the step-by-step process which must be executed to fulfill the test
requirements. The test procedures are developed by the GCR.
Test Requirements - requirements specifying what modes and functions, etc. shall be tested.
The test requirements are not the detailed test procedures. The test requirements are specified
in the Contract Documents.
PART 2 - PRODUCTS
A. All testing equipment required to perform startup and initial checkout and required functional
performance testing shall be provided by the construction contractor for the equipment being
tested.
B. Special equipment, tools and instruments (only available from vendor, specific to a piece of
equipment) required for testing equipment, according to these Contract Documents shall be
included in the base bid price to the Contractor and shall be left on site for use by the
Government.
C. All testing equipment shall be of sufficient quality and accuracy to test and/or measure system
performance with the tolerances specified in the Specifications.
A. Provide utilities necessary to execute testing and commissioning, including water, fuels,
chemicals, batteries and other similar expendable items.
B. Provide any equipment or device required for access, such as ladders, and platforms.
PART 3 - EXECUTION
3.1 MEETINGS
A. During regular contractor meetings, the QC and TI will be available to answer questions about
the Commissioning process and assist subcontractors in the completion of prefunctional and
functional test sheets.
1. The Government Commissioning Representative will review submittals during regular site
visits. The Government Commissioning Representative will review the final approved
submittal located in the GC's trailer on site. The GC will maintain this filing system.
2. The Government Commissioning Representative will review normal Contractor submittals
applicable to systems being commissioned and adjust prefunctional and functional test
sheets as appropriate based on equipment being supplied.
A. General: Prefunctional checklists ensure that the equipment and systems are properly installed
and operational. They ensure that functional performance testing (in-depth system checkout)
may proceed without unnecessary delays. Each piece of equipment receives full prefunctional
checkout. The prefunctional testing for a given system must be successfully completed prior to
formal functional performance testing of equipment or subsystems of the given system.
1. The Subs and vendors shall execute startup and provide the TI, through the QC, with a
signed and dated copy of the completed start-up and prefunctional tests and checklists.
2. Only individuals that have direct knowledge and witnessed that a line item task on the
prefunctional checklist was actually performed shall initial or check that item off.
3. The QC and TI shall witness prefunctional tests and checklist completion by reviewing
prefunctional checklist reports and by selected site observation.
C. Deficiencies:
1. List any outstanding items of the initial start-up and prefunctional procedures that were
not completed successfully, at the bottom of the procedures form or on an attached
sheet. The procedures form and any outstanding deficiencies shall be provided to the TI
through the QC within two days of test completion. The QC will review and the TI will
monitor outstanding deficiencies.
A. When startup and initial checkout are required to be executed in phases, this phasing will be
planned and scheduled in a coordination meeting of the GCR, mechanical, plumbing, TAB and
1. Documentation: The QC and TI will witness and the QC will document the results of all
functional performance tests using the specific procedural forms developed for that
purpose.
2. Non-Conformance:
a. The QC will record the results of the functional test on the procedure or test form.
The TI will witness the test. All deficiencies or non-conformance issues shall be
noted.
b. Corrections of minor deficiencies identified may be made during the tests. In such
cases the deficiency and resolution will be documented on the procedure form.
c. Every effort will be made to expedite the testing process and minimize
unnecessary delays, while not compromising the integrity of the procedures.
d. Any required retesting shall not be considered a justified reason for a claim of
delay or for a time extension.
A. O&M Manuals:
1. The specific content requirements for O&M manuals are described elsewhere in Division
01. Special requirements for the controls contractor and TAB contractor are found in
Division 23 Section Commissioning of HVAC.
2. The QC will verify and the TI will witness that O&M Manuals have been provided. The
QC will review and the TI will verify O&M Manuals to ensure they meet the requirements
of the Specifications.
1. Compile, organize and index commissioning data into labeled, indexed and tabbed,
three-ring binders and deliver two copies to the GCR for review.
2. Final Report Details:
A. The GC shall coordinate the operator training. Training requirements are shown in each
Section specifying commissioning and in Sections specifying items or systems to be
commissioned.
B. The GCR will review the content of the training plan and adequacy of the training of
Government personnel for commissioned equipment.
1. Each Sub and vendor responsible for training shall submit a written training plan to the
GCR for review prior to training. The plan shall cover the following elements:
2. For the primary HVAC equipment, the Controls Contractor shall provide a short
discussion of the control of the equipment during the mechanical or electrical training
conducted by others.
3. Video taping of the training sessions will be provided by the subcontractor with tapes
cataloged by the subcontractor and added to the O&M manuals. The QC and TI will
witness the taped sessions and the GCR will review the cataloged tapes.
4. The mechanical design engineer shall, at the first training session, present the overall
system design concept and the design concept of each equipment section.
A. Unforeseen Deferred Tests. If any check or test cannot be completed due to the building
structure, required occupancy condition or other deficiency, execution of checklists and
functional testing may be delayed upon approval of the Contracting Officer.
B. Seasonal Testing. During the warranty period, seasonal testing (tests delayed until weather
conditions are closer to the systems design) shall be completed as part of this contract. The GC
shall coordinate this activity. Tests shall be executed, documented and deficiencies corrected
by the appropriate Subs, with facilities staff and the GCR witnessing. Make any final
adjustments to the O&M manuals and as-builts due to the testing.
A. The commissioning must be complete, except for training, prior to Beneficial Occupancy Date,
unless approved in writing by the Contracting Officer.
A. The above systems will be commissioned and associated Prefunctional Testing Checklists and
Functional Testing Checklists are provided in the Commissioning Manual.
B. Depending upon the phasing of construction, checklists may be copied and completed for that
section of the work. Portions of the systems may be commissioned in stages. Once an entire
system is completed all test sheets for that system shall be submitted for review by the QC and
TI. Only when the entire system is completed shall the functional test of the entire system be
completed.
3.11 CHECKLISTS
A. The following table lists checklists for each item and system to be commissioned, and
corresponds to the table found in the Commissioning Plan. In case of conflict or discrepancy,
the table in the Commissioning Plan takes precedence.
Division 11 - Equipment
Battery Equipment
Refrigerated Display Cases PC-110000 -1 None
Equipment, Generic PC-110000 -2 None
Bakery Equipment PC-114000-13 None
Loading Dock Equipment PC-111300 None
Pedestrian Control Equipment PC-111400 FT-111400
Safes PC-111616 None
Grocery Equipment PC-114000.16 None
Meat Department Equipment PC-114000.23 None
Produce Department Equipment PC-114000.26 None
Seafood Department Equipment PC-114000.29 None
Baler PC-118236 None
Division 27 - Communication
Voice and Data Communications PC-271000-1 None
Cabling
Boxes, Panels And Control Centers PC-271116 None
Data Communication Systems PC-272000 FT-272000
Voice Communications Systems PC-273000 FT-273000
Division 33 - Utilities
Storm Drainage PC-334000 None
Electric Utility Services PC-337100 None
END OF SECTION
DESIGN CRITERIA
1. Related Sections: Division 03 Sections; Insulated Freezer Floors, Polished Concrete Finishing and Tilt-
Up Concrete, and Division 09 Sections for floor finishes requiring special preparation of concrete floor
slabs.
2. This Section specifies cast-in-place, normal-weight concrete for general building construction
including related formwork, reinforcement, concrete materials and admixtures, vapor retarders,
concrete mixture requirements, placement, as-cast and applied finishes, curing, repairs, and field
quality control.
A. This Section does not specify structural lightweight concrete, tilt-up concrete, post-tensioned
concrete, precast concrete, grouts, metallic and nonmetallic floor toppings, cement concrete
pavement, or decorative cement concrete pavements.
B. DeCA Guide Specifications require that floor slabs not be placed until building spaces are
enclosed and weathertight, as recommended by the Portland Cement Association (PCA) and the
National Ready Mixed Concrete Association (NRMCA).
A. ACI 301 is incorporated by reference and applies to cast-in-place structural concrete construction
for any Commissary building project.
B. ACI 318 is adopted by IBC and establishes minimum requirements for acceptance of design and
construction of structural concrete.
4. Design concrete in accordance with the Concrete Mixture Schedule at the end of Part 3 of the
specifications and the following unless project conditions require alternatives:
1. ACI 302.1R indicates that concrete slab reinforcement can be furnished in the form of
deformed steel bars, welded wire reinforcing, steel fibers, synthetic fibers, or post-tensioning
tendons. ACI 302.1R discusses the attributes of various types of reinforcing. It is left to the
A/E of record to specify the type of reinforcing most appropriate for each project. Regardless
of the reinforcement selected special attention must be given to the spacing and kind of
support provided for each type of reinforcement.
2. While both wire mesh reinforcing and deformed steel bar reinforcing provide suitable crack
control in floor slabs, quality control during construction has a significant impact on actual
crack control. If reinforcing is not maintained within the upper third of slab thickness or 2"
below the slab surface (whichever is closer to the slab surface), its crack control qualities are
reduced. When wire mesh reinforcing is used, its larger flexibility dictates that the Contractor
pay close attention to establishing and maintaining adequate support of the reinforcement
during concrete placing operations. Wire mesh reinforcing should not be placed on the
ground and pulled up after placement of the concrete, nor should the mats be walked in after
placing the concrete.
3. ACI Committee 302 "Strategic Development Council Task Group on Moisture" indicates that
for the best crack control, reinforcing steel should be placed as close to the surface as
June 2011 03 30 00 1
DeCA DESIGN CRITERIA HANDBOOK
03 30 00 CAST-IN-PLACE CONCRETE
possible and adequately supported so the location doesnt change during floor construction.
They further state that designers should consider using supported deformed bars no smaller
than #4 instead of light gauge mesh. Smaller-diameter bars are too limber, requiring too
many bar supports, and light-gauge mesh is difficult to keep in the correct location. For a 5"
thick floor slab, consider using #4 or #5 bars near the top with 1" of clear cover. Typically, #4
bars spaced at 12" to 18" on center both ways are used. This amount of steel holds crack
faces together tightly enough for non-rigid floor coverings by maintaining aggregate interlock
and significantly reducing slab curling. In some instances, closer spacing or larger diameter
bars may be needed. Constructability becomes an issue when bar spacing is so close that
workers cant step into openings between the bars. Larger-diameter bars may be the better
choice in this case.
4. Considering the above, DeCA Design Standard shall be to reinforce concrete slab-on-grade
floors using properly supported deformed steel bars.
D. Floor Slopes in Food Storage and Processing Areas: Slope to drains approximately 1/8 in/ft.
Locate drains so that maximum overall slope is approximately 1". Coordinate floor drain rim
elevations with plumbing.
E. Floor Loads: Abide by the most stringent of the IBC, local codes, or the following DeCA criteria:
4. Staging/receiving and dock areas: 1300 psf, unless loads at point of contact of shelving
uprights or material handling equipment wheel loads dictate greater.
F. The mixes indicated in the Schedule are based on Type I Portland cement without supplements.
1. Concrete and cement products containing fly ash are included in the current list of EPA
designated guideline items. Specify cementitious materials in accordance with Article 5.10 -
Specification of Preferential Recyclable Items of the Design Criteria Handbook Guidance
except where project conditions exclude their use.
G. Slump Limit: A 4" slump is indicated in the Schedule for all the Mix Uses listed. This in
accordance with ACI 301, 4.2.2.2, and allows a tolerance of 1" in accordance with ACI 117.
This slump also agrees with ACI 302.1R, Table 6.2.1, for floors. Modify slumps as required by
project conditions.
H. Air Content: The air content indicated in the Schedule for the Mix Uses listed are in accordance
with ACI 301, Table 4.2.2.4, ACI 201.2R, Table 1.4.3, and ACI 318/318R, 4.2.1, based on
relationship of air content of concrete and size of coarse aggregate. Modify air content
percentages in accordance with project conditions. Entrained air is not recommended for
concrete to be given a smooth, dense, hard troweled finish (ACI 302.1R, 8.3.11).
June 2011 03 30 00 2
DeCA DESIGN CRITERIA HANDBOOK
03 30 00 CAST-IN-PLACE CONCRETE
1. Consider omitting air entrainment if project will not be exposed to freeze/thaw conditions.
I. Footings and Foundation Walls Not Subject to Freezing and Thawing: The Maximum water-
cementitious materials ratio indicated in the Schedule for this Mix Use is in accordance with the
w/c ratio of ACI 211.1, Table 6.3.4 (a), for concrete containing Type I Portland cement, non-air-
entrained concrete, not subject to special exposure conditions or sulfate exposure, and for
compressive strength indicated. If Type of cement, exposure or compressive strength is changed,
change w/c ratio accordingly.
J. Foundation Walls Subject to Freezing and Thawing, i.e., Retaining Walls: The Maximum water-
cementitious materials ratio indicated in the Schedule for this Mix Use is in accordance with the
w/c ratio of ACI 201.2R, 1.4.2, ACI 318 Table 4.2.2, and ACI 211.1, Table 6.3.4 (a), for concrete
containing Type I Portland cement, air-entrained concrete, subject to freezing and thawing, not
subject to sulfate exposure, and for compressive strength indicated. If Type of cement, exposure
or compressive strength is changed, change w/c ratio accordingly.
K. Concrete Floor Finishing: DeCA has determined ACI 302.1R, Table 2.1, Class 5, with hard steel-
troweled final finish as the standard concrete floor finish for Commissaries. Because of the
impracticality of preparing small isolated floor areas for different finish floor surface materials, a
hard-troweled concrete floor finish is specified for all interior floor slabs. Where distinctive
concrete floor surfaces are required, the preparation of the concrete floor slab to receive the floor
covering is specified as the responsibility of the finish flooring installer.
L. Water-Cement Ratio: ACI 302.1R indicates that the total water content can have a major impact
on the bleeding characteristics of the concrete, as well as the potential for shrinkage, so use of
the lowest practical quantity of water in the concrete mixture is recommended. Typically, the
higher the w/cm ratios, the lower the compressive strength of the concrete. ACI 302.1R further
indicates that w/cm ratios in the range of 0.47 to 0.53 are applicable for most interior floors with
Floor Classification 4 and higher. A typical Commissary Sales Area floor slab will have a Floor
Classification 9. Other areas within a Commissary will have a Floor Classification 5. Interior floor
slabs subject to freezing will have a w/cm ratio of 0.45 as recommended by ACI 302.1R. Refer to
table at end of Section 03 30 00 Cast-in-place Concrete Guide Specification for recommended
w/cm ratios.
M. Concrete Floor Flatness: Provide minimum overall and local area F Flatness and minimum
overall area and local F Levelness for appropriate slab construction, building usage, and slab
finishing technique per ASTM E 1155 Determining Floor Flatness and Levelness Using the F-
Number System. Test for flatness per ASTM E 1155.
5. Vapor Retarders for Concrete Slabs on Grade: The following information was derived from ASTM E
1643-98, "Standard Practice for Installation of Water Vapor Retarders Used in Contact with Earth or
Granular Fill Under Concrete Slabs" and ACI 302.1R-04 "Guide for Concrete Floor and Slab
Construction".
A. Although both ACI and ASTM identify applications where vapor retarders may not be necessary,
all new commissary facilities shall have vapor retarders installed beneath slab-on-grade
construction. ACI 302.1R indicates that a vapor retarder should be provided if the project is
required to have a humidity controlled environment, which all commissary facilities are required to
have. Additionally, the O & M life of a commissary facility will typically include multiple
renovations. While current DeCA Design Criteria establishes an exposed concrete floor
throughout most of the facility; this may not be criteria in the future. Providing a vapor retarder
will accommodate moisture sensitive floor finishes possibly required at a later date.
June 2011 03 30 00 3
DeCA DESIGN CRITERIA HANDBOOK
03 30 00 CAST-IN-PLACE CONCRETE
1. ACI 302.1R, paragraph 3.2.3 addresses placement of vapor retarders. The decision to locate
the vapor retarder in direct contact with the slab or beneath a layer of granular fill should be
made on a case-by-case basis. Concerns identified in paragraph 3.2.3 are as follows:
a. Placing concrete in direct contact with the vapor retarder eliminates the potential for
water from sources such as rain, saw-cutting, curing, cleaning, or compaction to become
trapped within the fill course. Wet or saturated fill above the vapor retarder can
significantly increase the time required for a slab to dry to levels required by the
manufacturers of floor coverings, adhesives, and coatings.
b. Placing concrete in direct contact with the vapor retarder requires additional
consideration if potential slab-related problems are to be avoided. When compared with
identical concrete cast on a draining base, concrete placed in direct contact with a vapor
retarder has been shown to exhibit significantly larger length change in the first hour after
casting, during drying shrinkage, and when subject to environmental change. Bleed time
is also longer which can result in aggregate moving out of suspension.
c. Concrete that does not lose water to the base does not stiffen as rapidly as concrete that
does loose part of its excess water to the base. If rapid surface drying conditions are
present, the surface of the concrete placed directly on a vapor retarder will have a
tendency to dry and crust over while the concrete below the top fraction of an inch
remains relatively less stiff or unhardened. When this occurs, it may be necessary to
begin machine operations on the concrete surface before the concrete below the top
surface is sufficiently set. Under such conditions, a reduction in surface flatness and
some blistering or delamination can occur as air, water, or both become trapped below
the finish surface.
d. A granular course placed over the vapor retarder is intended to balance release of water
from top and bottom of the slab-on-grade during curing.
e. ACI Committee 302.1R now recommends concrete be placed directly on vapor retarder
when slab will receive vapor-sensitive floor coverings and directly on dry granular
material when slabs are in humidity controlled areas.
2. If drainage fill is placed over the vapor retarder, indicate types, thickness, and location(s) of
granular course materials on structural engineers foundation Drawings.
3. Considering concerns identified above, placement of the vapor retarder beneath the drainage
base shall be the DeCA Design Standard whenever project conditions do not specifically
require placement of the vapor retarder directly beneath the slab.
4. In the case that the Vapor Barrier/Retarder is placed directly below the slab, follow
recommendations in ACI 302.2R related to w/c ratio, aggregate gradation, and curing. These
factors, w/c ratio, gradation, and curing have the greatest effect on remedying the ill effects
of the slab in direct contact with the vapor barrier.
6. Joint Filler: Provide semi-rigid polyurea joint filler specified in this Section only in joints of concrete
floor slabs that are required to remain exposed. Division 03 Section Polished Concrete Finishing and
Division 09 Sections that specify applied floor finishes shall specify joint filler in joints of concrete floor
slabs as work of those individual Sections.
June 2011 03 30 00 4
DeCA DESIGN CRITERIA HANDBOOK
03 30 00 CAST-IN-PLACE CONCRETE
A. Floor Sealing: Provide for the application of two coats of sealer on floors indicated to be left
exposed. The first coat, applied after the concrete has cured, is intended to protect the concrete
from stains during construction operations. The second coat, applied just before completion of
project, dresses-up the floor for the Commissary opening. Do not indicate a sealer on floors
receiving a polished concrete finish specified in Division 03 Section Polished Concrete Finishing.
B. Floor Hardeners: Liquid surface treatments designed to reduce dusting and create a denser,
harder surface, are not intended to provide additional wear resistance in new, well designed, well
constructed and cured floors, nor to permit the use of lower quality concrete. Therefore, floor
hardeners are not specified. Add/Alter projects exhibiting floors with low wear resistance or
dusting may require remediation with a floor hardener.
8. Testing and Inspection: Although the IBC requires special inspections be performed by special
inspectors who are engaged by the Government or the design professional, this Section specifies the
Contractor shall perform these duties.
END OF SECTION
June 2011 03 30 00 5
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
a. Footings.
b. Foundation walls.
c. Slabs-on-grade. (Do not place floor slabs until building spaces are enclosed and
weathertight).
d. Concrete floor on metal deck.
e. Procedures and timing for saw cutting contraction joints in slabs-on-grade.
f. Procedures and timing for application of liquid floor treatments.
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of steel products.
2. Division 03 Section Polished Concrete Finishing for concrete floor slabs receiving a
polished finish.
3. Division 09 Sections for floor finishes requiring specially finished cast-in place concrete
floor slabs.
1.2 REFERENCES
A. NRMCA:
1. National Ready Mixed Concrete Association: Concrete In Practice, Technical Series, 900
Spring Street, Silver Spring, Maryland 20910, (301) 587-1400, ext.101, www.nrmca.org.
B. PCA:
1.3 DEFINITIONS
A. Cementitious Materials:
B. Drainage Course:
1. Course supporting the slab-on-grade that also minimizes upward capillary flow of pore
water.
1.4 SUBMITTALS
A. Product Data:
1. Admixtures.
2. Vapor retarders.
3. Floor slab treatments.
B. LEED Submittals:
1. Product Data for Credit MR 4.1[ and Credit MR 4.2]: For products having recycled
content, documentation indicating percentages by weight of postconsumer and
preconsumer recycled content.
a. Include statement indicating costs for each product having recycled content.
2. Design Mixtures for Credit ID 1.1: For each concrete mixture containing fly ash as a
replacement for portland cement or other portland cement replacements, and for
equivalent concrete mixtures that do not contain portland cement replacements.
C. Design Mixtures:
1. For each concrete mixture. Submit data and test documentation on materials and mixture
proportions. Submit alternate design mixtures when characteristics of materials, Project
conditions, weather, test results, or other circumstances warrant adjustments.
D. Ready-Mixed Concrete:
1. Furnish batch ticket information, prepared and distributed in accordance with ASTM C 94.
2. Statement of Material Content and Proportions Selected: Prior to actual delivery of
concrete, furnish a statement giving the dry masses of cement and saturated surface-dry-
E. Shop Drawings:
1. Shop and placing Drawings that detail fabrication, bending, and placement of steel
reinforcement. Include bar sizes, lengths, material, grade, bar schedules, stirrup spacing,
bent bar diagrams, bar arrangement, splices and laps, mechanical connections, tie
spacing, hoop spacing, and supports for concrete reinforcement.
F. Samples:
1. Vapor retarder.
1. Product Data:
L. Submittal List:
Reference Submittal Item Quantity Action
A. Manufacturer Qualifications:
B. Concrete Testing Service: Engage a qualified independent testing agency to perform material
evaluation tests and to design concrete mixtures.
1. An independent agency, qualified according to ASTM C 1077 and ASTM E 329 for
testing indicated, as documented according to ASTM E 548.
a. Personnel conducting field tests shall be qualified as ACI certified Concrete Field
Testing Technician, Grade 1, according to ACI CP-01 or an equivalent certification
program.
b. Personnel performing laboratory tests shall be ACI-certified Concrete Strength
Testing Technician and Concrete Laboratory Testing Technician - Grade I.
Testing Agency laboratory supervisor shall be an ACI-certified Concrete
Laboratory Testing Technician - Grade II.
D. Source Limitations:
1. Obtain each type or class of cementitious material of the same brand from the same
manufacturer's plant, obtain aggregate from one source, and obtain admixtures through
one source from a single manufacturer.
E. ACI Publications (other applicable construction industry standards indicated throughout this
Section have the same force and effect as if listed below):
1. Comply with the following unless modified by requirements in the Contract Documents:
F. ASTM Publications:
1. Comply with the following unless modified by requirements in the Contract Documents
(other applicable construction industry standards indicated throughout this Section have
the same force and effect as if listed below):
1. Special inspections for reinforced concrete shall be performed under the direct
supervision of a Professional Engineer registered in the State in which the project is
located. The personnel performing the inspections shall be ICC-certified Reinforced
Concrete Special Inspector or an equivalent certification program.
1. The concrete floor finishing subcontractor, Lead Finisher and two additional members of
the finishing crew, shall be certified under the Concrete Flatwork Finisher Training and
Certification Program as granted by the American Concrete Institute.
2. The concrete floor finisher subcontractor shall have experience in finishing interior floors
of similar size and scope in at least 5 previous projects.
I. Preinstallation Conference:
a. Before submitting design mixtures, review concrete design mixture and examine
procedures for ensuring quality of concrete materials. Require representatives of
each entity directly concerned with cast-in-place concrete to attend, including the
following:
1) Contractor's superintendent.
2) Independent testing agency responsible for concrete design mixtures.
3) Ready-mix concrete manufacturer.
4) Concrete subcontractor.
5) Concrete floor finishing subcontractor.
6) Special concrete floor finish installer (attendance may be telephonically).
7) Special concrete floor finish system manufacturer (attendance may be
telephonically).
b. Review special inspection and testing and inspecting agency procedures for field
quality control, concrete finishes and finishing, cold- and hot-weather concreting
procedures, curing procedures, construction contraction and isolation joints, joint-
filler strips, semirigid joint fillers, forms and form removal limitations, shoring and
reshoring procedures, vapor-retarder installation, anchor rod and anchorage
device installation tolerances, steel reinforcement installation, floor and slab
flatness and levelness measurement, concrete repair procedures, and concrete
protection. Unacceptable floor slab finishes include blisters, cracking, crazing,
curling, delamination, surface discoloration, dusting, efflorescence, popouts,
scaling, and spalling. Sources available to the Contractor identifying causes,
prevention, and repair of concrete slab surface defects are available from the
Portland Cement Association and the National Ready Mix Concrete Association as
identified in Paragraph 1.2 "References".
c. Review protection precautions relating to the special concrete floor finish system
as specified in Division 03 Section Polished Concrete Finishing including, but not
limited to, the following:
A. Deliver, store, and handle steel reinforcement to prevent bending and damage.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Form-facing panels that will provide continuous, true, and smooth concrete surfaces.
Furnish in largest practicable sizes to minimize number of joints.
C. Form-Release Agent:
a. Formulate form-release agent with rust inhibitor for steel form-facing materials.
D. Form Ties:
A. Reinforcing Bars:
B. Plain-Steel Wire:
A. Cementitious Material:
1. Portland Cement: ASTM C 150, Type I, of the same type, brand, and source, throughout
Project:
B. Normal-Weight Aggregates:
1. ASTM C 33, Class 3S coarse aggregate or better, graded. Provide aggregates from a
single source.
2. Maximum Coarse-Aggregate Size: As indicated.
3. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.
C. Water:
D. Fly Ash:
2.6 ADMIXTURES
A. General:
B. Air-Entraining Admixture:
A. Vapor Retarder:
1. Vapor Retarder: ASTM E 1745, Class B or A, with the following minimum criteria:
B. Accessories:
1. Seam Tape: Minimum 4-inch width, of high density polyethylene with pressure sensitive
adhesive on one side, or as recommended by the product manufacturer.
2. Barrier Penetration Boots: Constructed of the vapor retarder product or as recommended
by the product manufacturer.
1. Waterborne solution, VOC compliant, 15 percent to 20 percent total solids, that dries to
form a clear, glossy, protective film that seals concrete surfaces.
2. Basis-of-Design Products:
A. Evaporation Retarder:
1. AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9
oz./sq. yd. when dry.
C. Moisture-Retaining Cover:
D. Potable Water.
1. Rapid setting, 100 percent solids, flexible, two part polyurea joint filler with a Type A
Shore durometer hardness of at least 85 per ASTM D 2240 when cured. Designed to fill
and protect joints in industrial floors that are subject to traffic such as trucks, forklifts or
steel wheeled carts.
2. Color: Manufacturers standard gray.
3. Basis-of-Design Product: Advanced Floor Products, Inc.; Crete-Fill Pro 85; (773) 622-
2444 and www.retroplatesystem.com.
4. Performance Criteria:
C. Saw-cutting System:
1. Power saw equipped with shatter-proof abrasive or diamond-rimmed blades. Cut 1/8-
inch-wide joints into concrete when cutting action will not tear, abrade, or otherwise
damage surface before concrete develops random contraction cracks. Use the following
saw cutting system appropriate to procedures and timing for saw cutting contraction joints
in slabs-on-grade.
A. Repair Underlayment:
1. Where repair material for concrete floor and slab areas is required beneath floor
coverings, provide cement-based, polymer-modified, self-leveling product that can be
applied in thicknesses from 1/8 inch and that can be feathered at edges to match
adjacent floor elevations in accordance with the following:
B. Repair Overlayment:
1. Where repair material for concrete floor or slab areas is required to remain exposed and
not receive floor coverings, provide cement-based, polymer-modified, self-leveling
product that can be applied in thicknesses from 1/8 inch and that can be feathered at
edges to match adjacent floor elevations in accordance with the following:
1. Prepare design mixtures for each type and strength of concrete, proportioned on the
basis of laboratory trial mixture or field test data, or both, according to ACI 301.
B. Cementitious Materials:
1. Limit percent by weight of cementitious materials other than Portland cement in concrete
as follows:
a. Fly Ash; 5 percent maximum in floors receiving special concrete floor finish, 15
percent maximum elsewhere.
C. Concrete Mixtures:
D. Chloride-Ion Content:
E. Admixtures:
A. Ready-Mixed Concrete:
1. Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M, and furnish
batch ticket information.
a. When air temperature is between 85 and 90 deg F, reduce mixing and delivery
time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F,
reduce mixing and delivery time to 60 minutes.
3.1 FORMWORK
A. General:
1. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support
vertical, lateral, static, and dynamic loads, and construction loads that might be applied,
until structure can support such loads.
2. Construct formwork so concrete members and structures are of size, shape, alignment,
elevation, and position indicated, within tolerance limits of ACI 117 and ACI 301 except
as specified herein.
3. Limit concrete surface irregularities, designated by ACI 347R as abrupt or gradual, as
follows:
a. Install keyways, reglets, recesses, and the like, for easy removal.
b. Do not use rust-stained steel form-facing material.
6. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required
elevations and slopes in finished concrete surfaces. Provide and secure units to support
screed strips; use strike-off templates or compacting-type screeds.
7. Provide temporary openings for cleanouts and inspection ports where interior area of
formwork is inaccessible. Close openings with panels tightly fitted to forms and securely
braced to prevent loss of concrete mortar. Locate temporary openings in forms at
inconspicuous locations.
8. Chamfer exterior corners and edges of permanently exposed concrete.
9. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and
bulkheads required in the Work. Determine sizes and locations from trades providing
such items.
10. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust,
dirt, and other debris just before placing concrete.
11. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks
and maintain proper alignment.
12. Coat contact surfaces of forms with form-release agent, according to manufacturer's
written instructions, before placing reinforcement.
13. Provide slab side forms, of form materials specified, full depth, with beveled, level, and
smooth top surface for all slabs where SOV is greater than FF 35 / FL 25.
14. Provide slab side forms such that by placing a 10-foot straightedge, form does not
exceed 1/8 inch variation.
A. General:
1. Place and secure anchorage devices and other embedded items required for adjoining
work that is attached to or supported by cast-in-place concrete. Use setting Drawings,
templates, diagrams, instructions, and directions furnished with items to be embedded.
a. Install anchor rods, accurately located, to elevations required and complying with
tolerances in Section 7.5 of AISC's "Code of Standard Practice for Steel Buildings
and Bridges."
b. Install loading dock leveler pit framing angles and anchors in accordance with dock
leveler manufacturer's written instructions.
A. General:
1. Formwork for sides of beams, walls, columns, and similar parts of the Work that does not
support weight of concrete may be removed after cumulatively curing at not less than 50
deg F for 24 hours after placing concrete, if concrete is hard enough to not be damaged
by form-removal operations and curing and protection operations are maintained.
2. Remove forms only if shores have been arranged to permit removal of forms without
loosening or disturbing shores.
B. Reused Forms:
1. Clean and repair surfaces of forms to be reused in the Work. Split, frayed, delaminated,
or otherwise damaged form-facing material will not be acceptable for exposed surfaces.
Apply new form-release agent.
a. When forms are reused, clean surfaces, remove fins and laitance, and tighten to
close joints. Align and secure joints to avoid offsets.
1. Place, protect, and repair vapor-retarders over the prepared subgrade in accordance with
ACI 302.1R and ASTM E 1643, as applicable.
2. Place the vapor retarder sheeting over the prepared base with the longest dimension
parallel with the direction of the concrete slab.
3. Lap joints 6 inches and seal with seam tape (or manufacturer's recommended adhesive).
4. Lap vapor retarder over footings or onto foundation walls, or both, and seal around all
penetrations such as utilities and columns in order to create a monolithic membrane
between the moisture source below the slab and the slab.
1. Take precautions to protect vapor retarder from damage during installation of utilities, and
during drainage course placement.
2. Avoid use of stakes driven through the retarder.
A. Inspect and repair all punctures, damage or opened seams in the membrane retarder
immediately prior to drainage course placement.
B. Place drainage course on vapor retarder free of mud, frost, snow, or ice.
a. Compact each layer of drainage course to required cross sections and thicknesses
to not less than 95 percent of maximum dry unit weight according to ASTM D 698.
A. General:
a. For slabs-on-grade space reinforcing bar supports not to exceed 4 feet on center
in each direction.
6. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.
3.7 JOINTS
A. General:
1. Construct joints true to line with faces perpendicular to surface plane of concrete.
2. Provide construction, isolation and contraction joints as indicated on Drawings and as
noted below.
3. Bulkheads for construction joints shall be 1-1/2 inch minimum lumber. Do not use
permanent preformed metal bulkheads.
4. Provide bulkheads full depth of member.
7. Unless otherwise shown on the Drawings, do not extend reinforcement, corner protection
angles, bars or other fixed metal items through construction joints in slabs on grade or
pavements or through joints between slabs on grade and vertical surfaces.
B. Construction Joints:
1. Install so strength and appearance of concrete are not impaired, at locations indicated or
as approved by Contracting Officer.
2. Do not use keyed joints in floors.
a. Sawed Joints: Form contraction joints with power saws equipped with shatterproof
abrasive or diamond-rimmed blades. Cut 1/8-inch- wide joints into concrete before
concrete starts to cool, when cutting action will not tear, abrade, or otherwise
damage surface, and before concrete develops random contraction cracks.
1) Early-Entry Dry-Cut Saw Cutting: Saw cut slab within 1 hour in hot weather
to 2 hours in cold weather after completing finishing of the slab in that joint
location. Minimum saw cut depth of 1 inch within time limits. Clean out joints
with a diamond impregnated saw blade equipped with a dustless vacuum
system to ensure sides of joint walls are clean so that joint filler can bond
with them.
2) Conventional Saw Cutting: Saw cut slab within 4 hours in hot weather to 12
hours in cold weather after the slab has been finished in an area. Depth of
saw cut using conventional saw shall be at least one-quarter of slab depth
or minimum of 1 inch, whichever is greater.
1. After removing formwork, install joint-filler strips at slab junctions with vertical surfaces,
such as column pedestals, foundation walls, grade beams, and other locations, as
indicated.
2. Extend joint-filler strips full width and depth of joint, terminating top of strip below finished
concrete surface as indicated.
3. Install joint-filler strips in lengths as long as practicable. Where more than one length is
required, lace or clip sections together.
4. Form isolation joints of preformed joint-filler strips (PMEJ) where indicated.
a. Place top of joint filler flush with finished concrete surface if joint sealant is not
indicated.
b. Protect top edge of joint filler during concrete placement with metal, plastic, or
other temporary preformed cap. Remove protective cap after concrete has been
placed on both sides of joint.
A. General:
4. Deposit and consolidate concrete for floors and slabs in a continuous operation, within
limits of construction joints, until placement of a panel or section is complete.
a. Slab on Grade Thickness: Plus (+) as required to conform to slab finished surface
flatness and levelness tolerances specified, and minus (-) 1/4 inch, with the
average of all thickness samples equal to or greater than the specified slab
thickness.
b. Where floor slab is to be used as casting bed for tilt-up concrete, provide materials
and methods compatible with those specified for tilt-up concrete work.
c. Consolidate concrete during placement operations so concrete is thoroughly
worked around reinforcement and other embedded items and into corners.
d. Maintain reinforcement in position on chairs during concrete placement.
e. Screed slab surfaces with a straightedge and strike off to correct elevations.
f. Slope surfaces uniformly to drains where required.
g. Begin initial floating using bull floats or darbies to form a uniform and open-
textured surface plane, before excess bleedwater appears on the surface. Do not
further disturb slab surfaces before starting finishing operations.
B. Cold-Weather Placement:
1. Comply with ACI 306.1. Protect concrete work from physical damage or reduced
strength that could be caused by frost, freezing actions, or low temperatures.
2. When average high and low temperature is expected to fall below 40 deg F for three
successive days, maintain delivered concrete mixture temperature within the temperature
range required by ACI 301.
C. Hot-Weather Placement:
1) When the concrete's rate of evaporation exceeds 0.2 pounds per square
foot per hour, as determined by analysis, or any combination of concrete
materials and weather conditions are favorable for the formation of plastic
shrinkage cracks, the Contractor shall employ all necessary precautions to
avoid cracking.
2) Maintain an accurate reading thermometer at the job site to check
temperature of concrete.
3) Reject concrete based on following criteria: For slabs, reject concrete if its
temperature before placement is 95 deg F or above unless otherwise
approved by Contracting Officer. During hot weather, mixing and delivery
(discharge) time shall be shorter than specified in ASTM C94 as follows
unless otherwise approved by the Contracting Officer:
D. Precipitation Protection: Protect surfaces of exposed concrete from precipitation until adequate
strength is gained to prevent damage.
A. Rough-Formed Finish:
1. As-cast concrete texture imparted by form-facing material with tie holes and defects
repaired and patched. Remove fins and other projections that exceed specified limits on
formed-surface irregularities.
B. Smooth-Formed Finish:
1. At tops of walls, horizontal offsets, and similar unformed surfaces adjacent to formed
surfaces, strike off smooth and finish with a texture matching adjacent formed surfaces.
Continue final surface treatment of formed surfaces uniformly across adjacent unformed
surfaces, unless otherwise indicated.
A. General:
1. Comply with ACI 302.1R recommendations for screeding, restraightening, and finishing
operations for concrete surfaces.
2. Do not place floor slabs until building spaces are enclosed and weathertight.
3. Do not add water to slab surface during finishing operations.
4. Do not add cement to slab surface during finishing operations.
5. Perform no finishing operation while water is present on slab surface.
a. Fans or blower heaters, provided that the airflow does not dry, dust, or crust the
surface or cause cracking.
b. If concrete surface is stiff enough to not be damaged, rubber hose may be dragged
slowly over surface one time without disturbing surface.
7. Initial Leveling: Complete bull floating, darbying and straight-edging before any bleed
water is present on slab surface.
8. Hand and Power Floating:
1) Bleeding is finished.
2) Bleed water is gone, including water sheen on slab surface.
3) Concrete will sustain the weight of finishers without creating more than 1/8
to 1/4 inch indentations.
4) Mortar is not thrown by rotating blades of power float.
c. Float three times minimum with each floating at right angles to previous floating,
and final pass at 45 deg to previous pass.
1) Do not ride trowels on existing slabs. Trowels shall be carried off of slab
surfaces. When parking power trowels on fresh concrete, place on top of
plywood or spray area with evaporation retarder before placing trowel on top
of slab.
1. After applying normal trowel finish, apply hard trowel finish by hand and power-driven
trowel. Power trowel a minimum of three times and finally hand trowel to render finished
surface essentially free of trowel marks and uniform in texture and appearance. Grind
smooth any surface defects that would telegraph through applied coatings or floor
coverings. Unless otherwise indicated follow the finishing operations described in ACI
302.1R, for Floor Classification, Class 5.
b. Where "Special Concrete Floor Finish" is indicated follow the finishing operations
described in ACI 302.1R, for Floor Classification, Class 9 and as follows:
1. Finish surfaces to the following tolerances, according to ASTM E 1155, for a randomly
trafficked floor surface:
a. Unless otherwise indicated: Specified Overall Values (SOV) of flatness, F(F) 35;
and of levelness, F(L) 25; with Minimum Local Values (MLV) of flatness, F(F) 26;
and of levelness, F(L) 19 tolerance for troweled floors in accordance with ACI 117.
An ACI certified Flatwork Finisher will not be required for finishing of these floors.
D. Broom Finish:
1. Apply a broom finish to exterior concrete platforms, steps, and ramps, and elsewhere as
indicated.
2. Immediately after float finishing, slightly roughen trafficked surface by brooming with
fiber-bristle broom perpendicular to main traffic route.
A. Filling In:
1. Fill in holes and openings left in concrete structures, unless otherwise indicated, after
work of other trades is in place. Mix, place, and cure concrete, as specified, to blend with
in-place construction. Provide other miscellaneous concrete filling indicated or required
to complete the Work.
B. Curbs:
1. Provide monolithic finish to interior curbs by stripping forms while concrete is still green
and by steel-troweling surfaces to a hard, dense finish with corners, intersections, and
terminations slightly rounded.
1. Provide machine and equipment bases and foundations as shown on Drawings. Set
anchor bolts for machines and equipment at correct elevations, complying with diagrams
or templates from manufacturer furnishing machines and equipment.
A. General:
1. Protect freshly placed concrete from premature drying and excessive cold or hot
temperatures. Comply with ACI 306.1 for cold-weather protection and ACI 301 for hot-
weather protection during curing.
2. Start curing as soon as concrete surface will not be damaged by curing operations.
3. Continuously cure concrete for at least 7 consecutive days.
4. During curing period, do not allow any part of the concrete to become dry.
5. Do not use polyethylene sheets on exposed interior floors.
B. Evaporation Retarder:
1. Apply evaporation retarder to unformed concrete surfaces if hot, dry, or windy conditions
cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing operations.
Apply according to manufacturers written instructions after placing, screeding, and bull
floating or darbying concrete, but before float finishing.
2. Do not use evaporation retarder on floor slabs receiving floor finish specified in Division
03 Section Polished Concrete Finishing unless approved by special concrete floor finish
manufacturer
C. Formed Surfaces:
1. Cure formed concrete surfaces. Keep forms in contact with concrete wet during curing
period unless type of form is impervious to water, such as metal or fiberglass. If forms
remain during curing period, moist cure after loosening forms. If removing forms before
end of curing period, continue curing for the remainder of the curing period with other
approved methods.
1. Begin curing immediately after finishing concrete. Cure unformed surfaces, including
floors and slabs, and other surfaces.
E. Curing:
1. Cure concrete according to ACI 308.1, by one or a combination of the following methods:
a. Moisture Curing: Keep surfaces continuously moist for not less than seven days
with the following materials:
1) Water.
2) Continuous water-fog spray.
3) Absorptive cover, water saturated, and kept continuously wet. Cover
concrete surfaces and edges with 12-inch lap over adjacent absorptive
covers.
A. General:
1. Install semirigid polyurea joint filler only in joints of concrete slab-on-grade floors that are
indicated to remain exposed. Do not fill joints of floors receiving [special concrete floor
finish, refer to Division 03 Section Polished Concrete Finishing, or] finished flooring,
refer to Division 09 Sections for floor finishes.
2. Prepare, clean, and install semirigid joint filler according to manufacturer's written
instructions.
3. Defer joint filling until concrete has aged for time period recommended by joint filler
manufacturer. Do not fill joints until construction traffic has permanently ceased.
4. Remove all foreign material from joint substrates that could interfere with adhesion of
joint filler, including dust, paints (except for permanent, protective coatings tested and
approved for filler adhesion and compatibility by joint filler manufacturer), old joint
sealants and fillers, grease, dirt, debris, saw cuttings, and sealers from joints; leave
contact faces of joint clean and dry.
B. Installation:
1. Install semirigid joint filler full depth in saw-cut joints and at least 2 inches deep in formed
joints in accordance with manufacturers written recommendations. Overfill joint and trim
joint filler flush with top of joint after hardening.
A. Defective Concrete:
1. Repair and patch defective areas when approved by Contracting Officer. Remove and
replace concrete that cannot be repaired and patched to Contracting Officers approval.
B. Patching Mortar:
1. Mix dry-pack patching mortar, consisting of one part portland cement to two and one-half
parts fine aggregate passing a No. 16 sieve, using only enough water for handling and
placing.
1. Surface defects include color and texture irregularities, cracks, spalls, air bubbles,
honeycombs, rock pockets, fins and other projections on the surface, and stains and
other discolorations that cannot be removed by cleaning.
a. Immediately after form removal, cut out honeycombs, rock pockets, and voids
more than 1/2 inch in any dimension in solid concrete, but not less than 1 inch in
depth. Make edges of cuts perpendicular to concrete surface. Clean, dampen
with water, and brush-coat holes and voids with bonding agent. Fill and compact
with patching mortar before bonding agent has dried. Fill form-tie voids with
patching mortar or cone plugs secured in place with bonding agent.
b. Repair defects on surfaces exposed to view by blending white portland cement
and standard portland cement so that, when dry, patching mortar will match
surrounding color. Patch a test area at inconspicuous locations to verify mixture
and color match before proceeding with patching. Compact mortar in place and
strike off slightly higher than surrounding surface.
c. Repair defects on concealed formed surfaces that affect concrete's durability and
structural performance as determined by Contracting Officer.
1. Test unformed surfaces, such as floors and slabs, for finish and verify surface tolerances
specified for each surface. Correct low and high areas. Test surfaces sloped to drain for
trueness of slope and smoothness; use a sloped template.
B. Inspections:
1. The inspection program by the Special Inspector shall comply with Table 1704.4 of the
2009 International Building Code.
C. Concrete Tests:
1. Testing of composite samples of fresh concrete obtained according to ASTM C 172 shall
be performed according to the following requirements:
2. Testing Frequency: Obtain at least one composite sample for each 100 cu. yd. or
fraction thereof of each concrete mixture placed each day.
3. When frequency of testing will provide fewer than five compressive-strength tests for
each concrete mixture, testing shall be conducted from at least five randomly selected
batches or from each batch if fewer than five are used.
a. Cast and laboratory cure two sets of two standard cylinder specimens for each
composite sample.
7. Compressive-Strength Tests: ASTM C 39/C 39M; test one set of two laboratory-cured
specimens at 7 days and one set of two specimens at 28 days.
a. Test one set of two field-cured specimens at 7 days and one set of two specimens
at 28 days.
b. A compressive-strength test shall be the average compressive strength from a set
of two specimens obtained from same composite sample and tested at age
indicated.
8. Strength of each concrete mixture will be satisfactory if every average of any three
consecutive compressive-strength tests equals or exceeds specified compressive
strength and no compressive-strength test value falls below specified compressive
strength by more than 500 psi.
9. Test results shall be reported in writing to Contracting Officer, concrete manufacturer,
and Contractor within 48 hours of testing. Reports of compressive-strength tests shall
contain Project identification name and number, date of concrete placement, name of
concrete testing and inspecting agency, location of concrete batch in Work, design
compressive strength at 28 days, concrete mixture proportions and materials,
compressive breaking strength, and type of break for both 7- and 28-day tests.
10. Additional Tests: Testing and inspecting agency shall make additional tests of concrete
when test results indicate that slump, air entrainment, compressive strengths, or other
requirements have not been met, as directed by Contracting Officer. Testing and
inspecting agency may conduct tests to determine adequacy of concrete by cored
cylinders complying with ASTM C 42/C 42M or by other methods as directed by
Contracting Officer.
11. Additional testing and inspecting, at Contractor's expense, will be performed to determine
compliance of replaced or additional work with specified requirements.
a. Correct deficiencies in the Work that test reports and inspections indicate dos not
comply with the Contract Documents.
1. Test floor slab finished surface areas for flatness and levelness in accordance with ASTM
E 1155 within 72 hours of finishing.
2. F-Number requirements shall be as follows for all interior floor slabs.
c. Complete testing, identify defective areas, and submit written report within 24
hours after testing.
END OF SECTION
Mix Use fc Agg Size Slump Limit, w/c Air Content, Floor/Slab
Type Min at 28 Days, Maxa inches Ratio percent Final Finish
psi inches Max
Footings 3000 1-1/2 4 0.68 None NA
Foundation Walls Not Subject to Freezing 3000 1-1/2 4 0.68 None NA
and Thawing
Foundation Walls Subject to Freezing and 4000 1-1/2 4 0.48 5.5 NA
Thawing - Retaining Walls
Interior Slabs-on-Grade Unless Otherwise 4000 1 4 0.47 to 0.53 None Hard trowel finish
Indicated, Floor Classification 5
Interior Slabs-on-Grade Slab Special Con- 4000 1 4 0.47 to 0.53 None Hard trowel finish
crete Floor Finish, Floor Classification 9
Freezer Floor 4000 1 4 0.45 None Hard trowel finish
Interior Concrete Floor on Metal Deck, Ex- 3500 1/2 4 0.47 to 0.53 None Hard trowel finish
posed Surface
Interior Miscellaneous Concrete, Non- 2500 1 4 0.47 to 0.53 None Hard trowel finish
Structural, Exposed Surface
Interior Equipment Pads, Non-Structural, 2500 1 4 0.47 to 0.53 None Hard trowel finish
Exposed Surface
Exterior Miscellaneous Concrete, Exposed 4000 1 4 0.40 6 Broom finish
Surface
Exterior Equipment Pads, Exposed Surface 4000 1 4 0.40 6 Broom finish
DESIGN CRITERIA
1. Related Sections: See Division 03 Section Cast-In-Place Concrete, Division 13 Section Cold Storage
Rooms and related Design Standard Plates.
2. Provide insulating concrete freezer floors at freezer locations indicated on Concept Floor Plan and as
follows:
A. Low temperature cold storage rooms 200 SF in size, and larger, shall have insulated concrete
freezer floors with positive underfloor ventilation for prevention of frost heave. Construct
insulated concrete freezer floors systems consisting of:
1. 36" deep drainage fill layer containing PVC ventilation piping.
2. 10 mil vapor retarder directly on top of drainage fill.
3. Concrete sub-slab.
4. Three 2" layers of polystyrene insulation.
5. Perimeter wood thermal break (preservative treated or redwood) around freezer slab recess.
6. 10 mil vapor retarder set directly on top of insulation and wrapping-up and over exposed face
of perimeter wood thermal break (note that purpose of this is to minimize possibility of excess
concrete mix water from seeping down between joints in insulation).
7. Concrete top slab designed to accommodate a 250 psf live load.
8. Concrete top slab shall be level with hard trowel surface. Provide floor hardening treatment
and floor sealing treatment. Refer to related Section indicated above for additional
information.
9. Provide block-out at all door openings to accommodate heater cable and stainless steel
threshold furnished as part of low temperature insulated cold storage room.
B. On new construction projects, low temperature cold storage rooms (less than 200 SF in size)
shall be constructed similarly, except that an underfloor ventilation system is not required.
C. On alteration projects utilizing existing concrete floor slabs, low temperature cold storage rooms
(less than 200 SF in size) shall be constructed using 4" thick prefabricated insulated aluminum
floor panels with 1/4" thick aluminum diamond tread plate wearing surface. Refer to related
section indicated above for additional information on this floor system.
END OF SECTION
June 2011 03 30 50 1
SECTION 03 30 50
INSULATED FREEZER FLOORS
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1. Cast-in-place concrete floor systems on grade under cold storage room freezers.
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of steel products.
2. Division 03 Section Cast-in-Place Concrete for vapor retarders.
3. Division 13 Section Cold Storage Rooms for freezer room requirements.
1.2 SUBMITTALS
B. Product Data:
1. Provide data on insulation materials. Provide manufacturers product type data and
performance properties.
2. Provide data on vent piping materials. Provide manufacturers product type grading
quality.
C. Submittal List:
A. Comply with quality assurance provisions of Division 03 Section Cast-In-Place Concrete for
cast-in-place concrete.
2.1 MATERIALS
A. Drainage Fill:
1. Rigid, cellular polystyrene thermal insulation formed from polystyrene base resin by an
extrusion process using hydrochlorofluorocarbons as blowing agent to comply with
ASTM C 578 for type and with other requirements indicated below:
a. Type IV, 1.60-lb/cu. Ft. minimum density; 5.00 R-value of 1 inch thickness at mean
temperature of 75 deg F; 25 psi compressive resistance, unless otherwise
indicated.
C. Wood Blocking:
1. For perforated-wall pipes and fittings 4 inches in diameter: PVC sewer pipe, ASTM D
2729, bell-and-spigot ends, for loose joints.
2. For solid-wall pipes and fittings: PVC sewer pipe, ASTM D 3034, SDR 35, bell-and-
spigot ends, for gasketed joints.
E. Wire Cloth:
1. Plain weave, No. 4 square mesh (1/4 inch center to center of wires), 0.120 inch (11 ga.)
diameter wire, stainless steel, Type 304, mill finish.
PART 3 - EXECUTION
A. General:
1. Excavate for underfloor vent system after subgrade material has been compacted. Grade
bottom of excavation to required elevation and compact to a firm, solid bed for vent
system.
2. Install drainage fill to elevations indicated.
A. General:
1. Place drainage fill material under concrete slabs and around vent pipes.
2. Install vapor retarder over drainage fill material. Place, protect, and repair vapor-retarder
sheets according to ASTM E 1643 and manufacturer's written instructions. Maintain
continuity of retarder. Fully seal all seams and membrane penetrations. Repair rips and
tears that occur prior to placing concrete.
3. Install concrete sub-slab over vapor retarder. Float finish sub-slab in accordance with
requirements under Division 03 Section Cast-In-Place Concrete for interior sub-slabs on
grade.
4. Install wood blocking at perimeter of freezer floor as indicated.
5. Install insulation over sub-slab in multiple layers of 2 inches thick each; stagger joints.
6. Install vapor retarder over insulation and up face of wood blocking as indicated. Place,
protect, and repair vapor-retarder sheets according to ASTM E 1643 and manufacturer's
written instructions. Maintain continuity of retarder. Fully seal all seams and membrane
penetrations. Repair rips and tears that occur prior to placing concrete.
7. Install concrete freezer floor slab over vapor retarder. Trowel finish freezer floor slab and
cure in accordance with requirements under Division 03 Section Cast-In-Place Concrete
for freezer floor slab.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 03 Design Criteria and Standard Commissary Room and Finish
Schedule in Appendix A.
2. Exposed concrete floors (of various types) are becoming more popular in retail facilities, as they are
not subject to bond failure between the floor finish system and the concrete floor slab, commonly
caused by moisture vapor transmission (from below the slab) and surface moisture (from above the
slab). Surface moisture caused by refrigerated display case condensation, wet product displays
(such as produce), and daily floor cleaning allow water to puddle which seeps into joints of applied
floor finish systems causing bond failure.
3. Shrinkage cracking, differential settlement, slab curling / cupping, or any other surface defects will be
visible in exposed concrete floors. Repairs are difficult to mask (i.e., conceal). Specifications will
need to be carefully prepared, with emphasis placed on quality control for both material and
installation. Guide Specification Division 03 Section Cast-In-Place Concrete has established floor
flatness and floor levelness values at F(F) 50 F(L) 40 to minimize the appearance of waviness in a
highly polished floor. Control joint spacing should be carefully planned to minimize (and hopefully
eliminate) uncontrolled cracking.
4. The exposed concrete floor specified in Division 03 Section Polished Concrete Finishing is a natural
concrete floor with polished finish, consisting of:
5. The concrete polishing system is a chemical re-active concrete stabilizer that enhances concrete
density and hardness allowing concrete to be finished to a high cosmetic marble-like sheen. This is a
floor polishing system that has three standard finishes including a Level 1 hard-shell satin finish,
Level 2 hard-shell medium sheen, and Level 3 light reflective mirror finish. A Level 3 light reflective
mirror finish is to be provided in commissary facilities, unless directed otherwise by the DeCA Project
Manager. Once polished, this is a permanent integrally sealed, hardened, and dust proof finish. The
finish will never require re-application, waxing, or re-polishing. It will not peel or flake, and is not
affected by moisture vapor transmission (from below the slab) or surface moisture (from above the
slab). All levels of finish exceed OSHA and ADA recommendations for coefficient of friction (ASTM
1028) for both wet and dry hard surfaces. The product is non-flammable, water based, non-toxic,
meeting USDA and VOC compliance. The basis-of-design manufacturer for the concrete polishing
system is Advanced Floor Products "Retro Plate System."
The Retro Plate System works in conjunction with integrally colored concrete, dry-shake color
hardeners and acid stains to provide floor color, performance, and shine.
6. The joint filler used with polished concrete floors is a rapid setting, 100% solids, flexible, two part
polyurea joint filler designed to fill and protect joints in industrial floors that are subject to traffic such
as trucks, forklifts or steel wheeled carts. Joint filler is installed the full depth of saw-cut joints and at
least 2" deep in formed joints. Overfill joints and trim joint filler flush with floor surface after
hardening. The basis-of-design manufacturer for the joint filler is Advanced Floor Products, Inc.
Crete-Fill Pro 85.
7. Other types of exposed polished concrete floors that are suitable for retail use include:
June 2011 03 35 43 1
DeCA DESIGN CRITERIA HANDBOOK
03 35 43 POLISHED CONCRETE FINISHING
END OF SECTION
June 2011 03 35 43 2
SECTION 03 35 43
PART 1 - GENERAL
1.1 SUMMARY
A. General:
1. Work in this Section applies to the mechanical polishing of interior concrete floor
surfaces. Verify flatness and levelness of concrete slabs meet or exceed Specified
Overall Values (SOV) of flatness, F(F) 50 and of levelness, F(L) 40; with Minimum Local
Values (MLV) of flatness, F(F) 38; and of levelness, F(L) 26. Do not proceed until
unsatisfactory conditions are corrected. Floor grinding and polishing shall be started
using a metal disc, as needed to remove all low spots and trowel marks. No low spots or
trowel marks are to be left in the slab. A concrete grinding machine with planetary or
counter-rotating heads must be used.
B. Section Includes:
a. Surface preparation.
b. Densifying agent.
c. Polishing System.
d. Stain Protection.
e. Joint filler.
C. Related Sections:
1.2 SUBMITTALS
A. Product Data:
d. Submit technical data sheet giving descriptive data, curing time, and application
requirements.
e. Submit recommended maintenance and repair instructions for the installed floor
system.
C. Submittal List:
A. Repair Materials:
1. Furnish 5 gallons of the stain blocker and repair instructions to the technical inspector for
future repair by the Government. Furnish extra materials that match products installed
and that are packaged with protective covering for storage and identified with labels
describing contents.
A. Manufacturer Qualifications:
B. Installer Qualifications:
1. A firm that is regularly engaged in the installation of polished concrete floor system with a
minimum of 3 years experience with proposed system. Furnish documentation of
successful completion of a minimum of five projects with proposed system on projects of
similar magnitude and complexity. The installer shall have been certified in writing by the
special concrete floor finish manufacturer within 12 months prior to start of this project,
certifying that the installer is:
a. Current on the latest application means and methods of special concrete floor
finish.
2. The special concrete finish manufacturer shall certify, in writing, that the installer
designated for this project is qualified for the scope of this project and has qualified
personnel to perform the work.
C. Source Limitations:
1. Obtain each type of material for Special Concrete Floor Finish System from one source
approved by Special Concrete Floor Finish System manufacturer with resources to
provide materials of consistent quality in appearance and physical properties.
D. Mockups:
1. Provide benchmark sample of Special Concrete Floor Finish System to verify finish
indicated and to demonstrate aesthetic effects and set quality standards for materials and
execution, i.e., typical joints, surface finish, color variation (if any), and standard of
workmanship.
1. The Installer shall participate telephonically before the placement of the concrete slab
related to this Section with the General Contractor, and technical inspector to review
requirements necessary for a successful polished floor surface.
2. The Installer shall conduct a conference at the Project site to comply with requirements in
Division 01 Section Administrative Requirements.
A. Deliver materials in original containers, with seals unbroken, bearing manufacturer labels
indicating brand name and directions for storage. Dispense special concrete finish material from
factory numbered and sealed containers. Maintain record of container numbers.
A. General:
1. Close spaces to traffic during Special Concrete Floor Finish System application.
B. Environmental Limitations:
1. Comply with Special Concrete Floor Finish System manufacturer's written instructions for
substrate temperature, ambient temperature, moisture, ventilation, and other conditions
affecting Special Concrete Floor Finish System application.
C. Grinding Operations:
1. Planetary or counter rotating 3 head and 4 head variable speed floor grinder. Minimum
size of grinding head shall be 32-inch diameter. Tilt-back machines shall be used for
grinding and polishing operations.
2. Dust extraction system for above grinders incorporating HEPA filters.
3. Protect adjacent construction from detrimental effects of grinding operations.
4. Hand or edge grinders with dust extraction or dust suppression attachment.
5. Grinding heads must include both metal bonded diamonds and resin bonded diamonds
using a flexible head system.
6. High speed burnisher with minimum 2500 RMN and minimum 20-inch diameter head.
7. Diamond impregnated burnishing pads.
8. Provide dustproof partitions and temporary enclosures to limit dust migration and to
isolate areas from noise.
9. All grinding diamonds used shall be approved by concrete polishing system
manufacturer.
A. Special Warranty:
a. Special warranty includes penetrating liquid concrete floor densifying agent, joint
filler, finish, and other components of Special Concrete Floor Finish System.
b. Warranty Period: 10 years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
a. Basis-of-Design Products:
1. Patented process of metal bond diamond grinding and polishing in graduated grits from
coarse to fine.
2. Basis-of-Design Systems:
a. Advanced Floor Products, Inc.; Retro-Plate Concrete Polishing System; (773) 622-
2444 and www.retroplatesystem.com.
b. Finish: Level 3 light reflective mirror finish. Standing on the floor, looking directly
down, the floor shall have depth and clarity. Overhead light fixtures shall be clearly
visible and defined and the reflection shall appear to be 8 to 12 feet deep.
1. Non-film forming, water-based, penetrating stain repellent specifically formulated for the
protection of polished concrete from oil and water-based stains.
2. Basis-of-Design Products:
1. Rapid setting, 100 percent solids, flexible, two part polyurea joint filler with a Type A
Shore durometer hardness of at least 85 per ASTM D 2240 when cured. Designed to fill
and protect joints in industrial floors that are subject to traffic such as trucks, forklifts or
steel wheeled carts.
2. Color: Manufacturers standard gray.
3. Basis-of-Design Product: Advanced Floor Products, Inc.; Crete-Fill Pro 85; (773) 622-
2444 and www.retroplatesystem.com.
4. Performance Criteria:
PART 3 - EXECUTION
3.1 GENERAL
A. Comply with manufacturers written instructions for substrate temperature and moisture content,
ambient temperature and humidity, ventilation, and other conditions affecting performance.
C. Apply Special Concrete Floor Finish System prior to installation of equipment; provide a
complete, uninhibited concrete slab for application.
D. Close areas to traffic during floor application and for 2 hours after application.
A. Examine substrate, with special floor finish installer present, for conditions affecting
performance of finish. Correct conditions detrimental to timely and proper work. Do not proceed
until unsatisfactory conditions are corrected.
1. Verify flatness and levelness of concrete slabs meet or exceed Specified Overall Values
(SOV) of flatness, F (F) 50 and of levelness, F(L) 40; with Minimum Local Values (MLV)
of flatness, F(F) 38; and of levelness, F(L) 26. Do not proceed until unsatisfactory
conditions are corrected.
B. Verify that concrete floor slab meet finish and surface profile requirements in Division 03
Section Cast-In-Place Concrete.
C. Prior to application, verify that floor surfaces are free of construction laitance.
A. General:
a. Only a certified applicator shall apply the penetrating liquid densifying agent.
Applicable procedures shall be followed as recommended by the product
manufacturer and as required to match approved benchmark sample.
b. Achieve waterproofing, hardening, dust-proofing, and abrasion resistance of the
surface without changing the natural appearance of the concrete, except for the
sheen.
c. Polish to required sheen level.
C. Start the process with the appropriate metal diamond grinding head (for example: 40, 80, 120
grit) depending on condition of concrete floor slab. Continue with additional grinding steps as
necessary to achieve a consistent and uniform salt and pepper concrete slab appearance
(showing sand aggregate only) and void of random scratches. All metal bond grinding shall be
performed wet.
E. Begin the polishing process with a 100 grit resin bonded diamond grinding head followed in
succession with a 200, 400, 800, and finally a 1500 grit resin bonded diamond grinding head as
necessary, to achieve specified sheen. Complete final polishing prior to installation of
refrigerated display cases and gondolas shelving.
F. Use hand grinders and burnishers along edges and other areas of floor slab, exposed to view,
that are not reachable using a planetary floor grinder.
A. Preparation:
1. Complete all densification, grinding, and polishing before application of stain repellent.
2. Clean substrate of substances that might interfere with penetration or performance of
stain repellent. Check surface for water, according to stain repellent manufacturer's
written instructions, to ensure that surface is totally dry.
3. Install per manufacturer requirements.
a. Remove oil, laitance, and other substances that could prevent adhesion or
penetration of stain repellent.
4. Proceed with installation only after unsatisfactory conditions have been corrected.
B. Application:
A. General:
1. Prepare, clean, and install joint filler according to manufacturers written instructions and
the following requirements.
a. Defer joint filling until after concrete floor polishing and application of stain
protection are completed. Do not fill joints until construction traffic has permanently
ceased in areas receiving joint filler.
b. Remove all foreign material from joint substrates that could interfere with adhesion
of joint filler, including dust, paints (except for permanent, protective coatings
2. Install joint filler full depth in saw-cut joints and at least 2 inches deep in formed joints.
Overfill joint and trim joint filler flush with floor surface after hardening.
A. General:
3.8 PROTECTION
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 03 Sections Cast-In-Place Concrete and Tilt-Up Concrete and Division
04 Section Unit Masonry for precast concrete trim units.
2. This Section specifies architectural precast, conventionally reinforced normal-weight concrete units
with conventional form-liner and abrasive-blast exposed-aggregate finishes.
A. This Section does not specify structural precast concrete, pretensioned or post-tensioned
architectural precast, prestressed concrete units, insulated or sandwich wall panels, cast stone,
autoclaved aerated concrete, glass-fiber-reinforced concrete, panels with applied brick or stone
facings, or site-cast tilt-up concrete.
A. ACI 318 is adopted by IBC and establishes minimum requirements for acceptance of design and
construction of precast concrete.
C. PCI MNL 117, "Manual for Quality Control for Plants and Production of Architectural Precast
Concrete Products."
E. Testing and Inspection: Although the IBC requires special inspections be performed by special
inspectors who are engaged by the Government or the design professional, this Section specifies
the Contractor shall perform these duties.
4. Design Considerations:
A. Consult with local architectural precast concrete fabricators. Frequently, such factors as the
weight and transport of units, handling and erection stresses, and standard fabrication techniques
govern the design of architectural precast concrete units.
B. The precast concrete fabricator is specified in this Section to assume engineering responsibility
of the architectural precast concrete units to comply with Project performance requirements.
C. Be sensitive to the environmental factors causing out of plane panel bow during panel to panel
connection design.
END OF SECTION
June 2011 03 45 00 1
SECTION 03 45 00
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of steel products.
2. Division 03 Section Cast-In-Place Concrete for installing connection anchors in concrete.
1.2 DEFINITIONS
A. Face-down Surface:
B. Face-up Surface:
B. Structural Performance:
a. Wind Load:
1) Wind loads for the in-plane sheet wall design have been indicated on the
drawings. Wind loads for the out-of-plane design shall be determined by the
Precast Manufacturer.
b. Seismic Loads:
1) Seismic loads for the in-plane shear wall design have been indicated on the
drawings. Seismic loads for the out-of-plane design shall be determined by
the Precast Manufacturer.
2) Provide precast architectural concrete assemblies capable of resisting the
effects of earthquake motions.
3) Refer to Division 01 Section Summary of Work for seismic-load design
criteria.
4) Determine seismic loads using the appropriate exposure coefficient for the
precast architectural concrete assemblies.
C. Thermal Movements:
1. Provide systems that allows for thermal movements resulting from the following
maximum change (range) in ambient and surface temperatures by preventing
displacement of stone, opening of joints, overstressing of components, failure of joint
sealants and connections, and other detrimental effects. Base engineering calculation on
surface temperatures of materials due to both solar heat gain and nighttime sky heat
loss.
a. Temperature Change (Range): 110 deg F, ambient; 170 deg F, material surfaces.
1.4 SUBMITTALS
A. Product Data:
B. LEED Submittal:
1. Product Data for Credit MR 4.1[ and Credit MR 4.2]: For products having recycled
content, documentation indicating percentages by weight of postconsumer and
preconsumer recycled content.
C. Design Mixes:
1. For each concrete mix. Include compressive strength and water-absorption tests.
D. Shop Drawings:
1. Detail fabrication and installation of precast architectural concrete units. Indicate member
locations, plans, elevations, dimensions, shapes, cross sections, limits of each finish, and
types of reinforcement, including special reinforcement.
a. Indicate welded connections by AWS standard symbols. Detail loose and cast-in
hardware, inserts, connections, and joints, including accessories.
b. Indicate locations and details of anchorage devices to be embedded in or attached
to structure or other construction.
c. Indicate plans and elevations showing unit location and sequence of erection for
special conditions.
d. Comprehensive engineering analysis signed and sealed by the qualified
professional engineer responsible for its preparation and registered in the State in
which the project is located.
E. Samples:
1. For each type of finish indicated on exposed surfaces of precast architectural concrete
units, in sets of 3, illustrating full range of finish, color, and texture variations expected;
approximately 12 by 12 by 2 inches.
F. Welding Certificates:
G. Material Certificates:
1. Signed by manufacturers certifying that each of the following items complies with
requirements:
a. Concrete materials.
b. Reinforcing materials.
H. Installer qualifications.
I. Fabricator qualifications.
K. Test reports.
1. Product Data:
M. Submittal List:
A. Installer Qualifications:
1. A precast concrete erector who has retained a "PCI-certified Field Auditor" to conduct a
field audit of a project in same category as this Project before erection of precast
concrete and who can produce an Erectors Post-Audit Declaration, according to PCI
MNL 127, "PCI Erectors Manual - Standards and Guidelines for the Erection of Precast
Concrete Products."
B. Fabricator Qualifications:
1. A firm that complies with the following requirements and is experienced in manufacturing
precast architectural concrete units similar to those indicated for this Project and with a
record of successful in-service performance.
1. An independent testing agency qualified according to ASTM C 1077 and ASTM E 329 to
conduct the testing indicated, as documented according to ASTM E 548.
D. Design Standards:
1. Comply with ACI 318 and the design recommendations of PCI MNL 120, "PCI Design
Handbook--Precast and Prestressed Concrete."
E. Quality-Control Standard:
F. Welding:
1. Qualify procedures and personnel according to AWS D1.1, "Structural Welding Code--
Steel"; and AWS D1.4, "Structural Welding Code--Reinforcing Steel."
A. Deliver precast architectural concrete units to Project site in such quantities and at such times to
ensure continuity of installation. Store units at Project site to prevent cracking, distorting,
warping, staining, or other physical damage, and so markings are visible. Lift and support units
only at designated lifting and supporting points as shown on Shop Drawings.
1.7 SEQUENCING
A. Molds:
1. Provide molds and, where required, form-facing materials of metal, plastic, wood, or
another material that is nonreactive with concrete and dimensionally stable to produce
continuous and true precast concrete surfaces within fabrication tolerances and suitable
for required finishes.
B. Form Liners:
A. Reinforcing Bars:
B. Plain-Steel Wire:
1. ASTM A 185, fabricated from as-drawn steel wire into flat sheets.
E. Supports:
1. Manufacturer's bolsters, chairs, spacers, and other devices for spacing, supporting, and
fastening reinforcing bars and welded wire fabric in place according to CRSI's "Manual of
Standard Practice," PCI MNL 117, and as follows:
A. Portland Cement:
1. ASTM C 150, Type I, or Type III, of same type, brand, and source.
1. Except as modified by PCI MNL 117, ASTM C 33, with coarse aggregates complying with
Class 5S.
C. Coloring Admixture:
a. Color: As indicated.
D. Water:
1. Potable; free from deleterious material that may affect color stability, setting, or strength
of concrete and complying with chemical limits of PCI MNL 117.
E. Air-Entraining Admixture:
F. Chemical Admixtures:
1. ASTM A 108, AISI 1018 through AISI 1020, cold finished; AWS D1.1, Type A or B, with
arc shields.
C. Carbon-Steel Plate:
1. ASTM A 47.
1. ASTM A 307, Grade A; carbon-steel, hex-head bolts and studs; carbon-steel nuts; and
flat, unhardened steel washers.
K. Finish:
1. For exterior steel items, steel in exterior walls, and items indicated for galvanizing, apply
zinc coating by hot-dip process according to ASTM A 123/A 123M, after fabrication, and
ASTM A 153/A 153M, as applicable.
a. Galvanizing Repair Paint: High-zinc-dust-content paint with dry film containing not
less than 94 percent zinc dust by weight, and complying with DOD-P-21035A or
SSPC-Paint 20.
L. Shop-Primed Finish:
a. Primer: MPI#79, "Alkyd Anti-Corrosive Metal Primer" or MPI#76, "Quick Dry Alkyd
Metal Primer."
M. Welding Electrodes:
N. Accessories:
1. Provide clips, hangers, plastic shims, and other accessories required to install precast
architectural concrete units.
A. General:
1. Proportion mixes by either laboratory trial batch or field test data methods according to
ACI 211.1, with materials to be used on Project, to provide normal-weight concrete with
the following properties:
C. Admixtures:
A. Molds:
1. Accurately construct molds, mortar tight, of sufficient strength to withstand pressures due
to concrete-placement operations and temperature changes.
a. Place form liners accurately to provide finished surface texture indicated. Provide
solid backing and supports to maintain stability of liners during concreting. Coat
form liner with form-release agent.
2. Maintain molds to provide completed precast architectural concrete units of shapes, lines,
and dimensions indicated, within fabrication tolerances specified.
1. Uniformly chamfered.
2.8 FABRICATION
1. Fabricate anchorage hardware with sufficient anchorage and embedment to comply with
design requirements. Accurately position for attachment of loose hardware, and secure
in place during precasting operations. Locate anchorage hardware where it does not
affect position of main reinforcement or concrete placement.
2. Furnish loose steel plates, clip angles, seat angles, anchors, dowels, cramps, hangers,
and other hardware shapes for securing precast architectural concrete units to supporting
and adjacent construction.
3. Cast-in reglets, slots, holes, and other accessories in precast architectural concrete units
to receive windows, cramps, dowels, reglets, waterstops, flashings, and other similar
work as indicated.
4. Cast-in openings larger than 10 inches in any dimension.
B. Reinforcement:
1. Mix concrete according to PCI MNL 117 and requirements in this Section. After concrete
batching, no additional water may be added.
2. Place concrete in a continuous operation to prevent seams or planes of weakness from
forming in precast concrete units. Comply with requirements in PCI MNL 117 for
measuring, mixing, transporting, and placing concrete.
3. Thoroughly consolidate placed concrete by internal and external vibration without
dislocating or damaging reinforcement and built-in items. Use equipment and procedures
complying with PCI MNL 117.
4. Comply with ACI 306.1 procedures for cold-weather concrete placement.
5. Comply with ACI 305R recommendations for hot-weather concrete placement.
1. Identify pickup points of precast architectural concrete units and orientation in structure
with permanent markings, complying with markings indicated on Shop Drawings. Imprint
or permanently mark casting date on each precast architectural concrete unit on a
surface that will not show in finished structure.
E. Curing:
1. Cure concrete, according to requirements in PCI MNL 117, by moisture retention without
heat or by accelerated heat curing using low-pressure live steam or radiant heat and
moisture.
F. Defective Units:
1. Discard precast architectural concrete units that are warped, cracked, broken, spalled,
stained, or otherwise defective unless repairs are approved by Contracting Officer.
A. General:
1. Fabricate precast architectural concrete units straight and true to size and shape with
exposed edges and corners precise and true so each finished panel complies with
PCI MNL 117 product tolerances as well as position tolerances for cast-in items.
B. Position Tolerances:
1. For cast-in items measured from datum line location, as indicated on Shop Drawings.
2.10 FINISHES
A. Quality-Control Testing:
1. Test and inspect precast concrete according to PCI MNL 117 requirements.
2. Strength of precast concrete units will be considered deficient if units fail to comply with
ACI 318 requirements.
B. Testing:
1. If there is evidence that the strength of precast concrete units may be deficient or may
not comply with ACI 318 requirements, employ an independent testing agency to obtain,
prepare, and test cores drilled from hardened concrete to determine compressive
strength according to ASTM C 42.
C. Patching:
1. If core test results are satisfactory and precast concrete units comply with requirements,
clean and dampen core holes and solidly fill with precast concrete mix that has no coarse
aggregate, and finish to match adjacent precast concrete surfaces.
D. Defective work.
1. Precast architectural concrete units that do not comply with requirements, including
strength, manufacturing tolerances, and finishes, are unacceptable. Replace with
precast concrete units that comply with requirements.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions for compliance with requirements for installation tolerances,
true and level bearing surfaces, and other conditions affecting performance. Proceed with
installation only after unsatisfactory conditions have been corrected. Do not install precast
concrete units until supporting concrete has attained minimum design compressive strength.
3.2 INSTALLATION
A. General:
1. Install clips, hangers, and other accessories required for connecting precast architectural
concrete units to supporting members and backup materials.
2. Install precast architectural concrete. Provide temporary supports and bracing as
required to maintain position, stability, and alignment as units are being permanently
connected.
3. Install bearing pads as precast concrete units are being erected.
4. Maintain horizontal and vertical joint alignment and uniform joint width as erection
progresses.
5. Remove projecting hoisting devices and use sand-cement grout to fill voids within
recessed hoisting devices flush with surface of concrete.
a. Protect precast architectural concrete units and bearing pads from damage by field
welding or cutting operations and provide noncombustible shields as required.
b. Repair damaged galvanized steel surfaces by cleaning and applying a coat of
galvanizing repair paint to galvanized surfaces.
c. Repair damaged primed steel surfaces by cleaning and repriming damaged
painted surfaces.
8. At bolted connections, use lock washers or other acceptable means to prevent loosening
of nuts.
9. Grouting Connections: Grout connections where required or indicated. Retain grout in
place until hard enough to support itself. Pack spaces with stiff grout material, tamping
until voids are completely filled. Place grout to finish smooth, level, and plumb with
adjacent concrete surfaces. Keep grouted joints damp for not less than 24 hours after
initial set. Promptly remove grout material from exposed surfaces before it affects
finishes or hardens.
10. All welded connections shall be painted with galvanized repair paint.
11. All connections exposed to earth or weather shall be covered with asphaltic based paint.
A. Install precast architectural concrete units level, plumb, square, true, and in alignment without
exceeding the noncumulative erection tolerances of PCI MNL 117, Appendix I.
A. Special Inspections:
1. Contractor shall engage a Special Inspector to perform special inspections for erection of
precast concrete members and as follows:
a. The inspection program by the Special Inspector shall comply with Table 1704.4 of
the 2009 International Building Code.
B. Testing:
1. Engage a qualified independent testing and inspecting agency to perform field tests and
inspections.
2. Test and inspect field welds and connections using high-strength bolts.
3. Testing agency shall report test results promptly and in writing to Contractor and
Contracting Officer.
4. Remove and replace work that does not comply with specified requirements.
5. Additional testing and inspecting, at Contractor's expense, shall be performed to
determine compliance of corrected work with specified requirements.
A. Repair exposed exterior surfaces of precast architectural concrete units to match color, texture,
and uniformity of surrounding precast architectural concrete if permitted by Contracting Officer.
Remove and replace damaged precast architectural concrete units if repairs do not comply with
requirements.
3.6 CLEANING
A. Clean exposed surfaces of precast concrete units after erection to remove weld marks, other
markings, dirt, and stains. Wash and rinse according to precast concrete fabricator's written
recommendations. Protect other work from staining or damage due to cleaning operations. Do
not use cleaning materials or processes that could change the appearance of exposed concrete
finishes.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 03 Sections Cast-In-Place Concrete and Precast Architectural
Concrete.
A. Where the casting slab is the building's permanent concrete slab-on-grade insure that the depth
of floor brace anchors or the length of drilled-in anchors do not puncture the vapor retarder under
the slab-on-grade; insure that the strength and thickness of the slab-on-grade will withstand
temporary bracing loads and the combined weight of the crane and the lifted tilt-up panel;
consider the effect of contraction joints and isolation joints on finishes; verify the compatibility of
curing compounds with bondbreakers; and verify the suitability of the slab-on-grade finish.
2. This Section specifies tilt-up concrete wall panels that are cast, finished, and tilted into place on-site.
This Section also specifies related formwork, reinforcement, concrete materials and admixtures,
concrete mixture requirements, placement, as-cast and conventional form-liner and abrasive-blast
exposed-aggregate finishes, bondbreakers, curing, repairs, and field quality control.
A. This Section does not specify cast-in-place architectural concrete or precast architectural
concrete.
A. ACI 301 is incorporated by reference and applies to tilt-up load bearing-concrete construction.
B. ACI 551 Tilt up construction Guide provides further information for the A/E.
D. Testing and Inspection: Although the IBC requires special inspections be performed by special
inspectors who are engaged by the Government or the design professional, this Section specifies
the Contractor shall perform these duties.
4. Design Considerations:
1. The primary structural design of tilt-up panels is with the A/E. This includes a review of design
analyses, building stability, structural systems, and permanent connections.
2. The tilt-up concrete fabricator is specified in this Section to assume engineering responsibility of
lifting inserts and devices, provide professional engineering services and take design
responsibility for tilting and erection stresses; and also determines insert locations, selects lifting
devices, and develops bracing designs for the tilt-up panels.
END OF SECTION
June 2011 03 47 13 1
SECTION 03 47 13
TILT-UP CONCRETE
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of steel products.
1.2 DEFINITIONS
A. Face-Down Surface:
1. Concealed surface of as-cast, tilt-up panel formed against the casting slab.
B. Face-Up Surface:
C. Reveal:
1.3 SUBMITTALS
A. Product Data:
B. LEED Submittals:
1. Product Data for Credit MR 4.1[ and Credit MR 4.2]: For products having recycled
content, documentation indicating percentages by weight of postconsumer and
2. Design Mixtures for Credit ID 1.1: For each concrete mixture containing fly ash as a
replacement for portland cement or other portland cement replacements and for
equivalent concrete mixtures that do not contain portland cement replacements.
C. Design Mixtures:
1. For each concrete mixture. Submit alternate design mixtures when characteristics of
materials, Project conditions, weather, test results, or other circumstances warrant
adjustments.
D. Shop Drawings:
1. Detail fabrication and installation of tilt-up concrete units. Indicate panel locations, plans,
elevations, dimensions, shapes, cross sections, and details of steel embedments.
2. Include steel reinforcement, detailing fabrication, bending, and placing. Include material,
grade, bar schedules, stirrup spacing, bent-bar diagrams, arrangement, and supports of
concrete reinforcement.
3. Include additional steel reinforcement to resist hoisting and erection stresses.
4. Include locations and details of hoisting points and lifting devices for handling and
erection.
5. Include engineering analysis data of additional steel reinforcement and hoisting and
erection details, signed and sealed by the qualified professional engineer responsible for
their preparation.
6. Indicate welded connections by AWS standard symbols. Detail cast-in inserts,
connections, and joints, including accessories.
E. Material Certificates:
a. Cementitious materials.
b. Steel reinforcement and accessories.
1. Product Data:
A. Manufacturer Qualifications:
1. An independent agency, qualified according to ASTM C 1077 and ASTM E 329 for
testing indicated, as documented according to ASTM E 548.
a. Personnel conducting field tests shall be qualified as ACI Concrete Field Testing
Technician, Grade I, according to ACI CP-01 or an equivalent certification
program.
b. Personnel performing laboratory tests shall be an ACI-certified Concrete Strength
Testing Technician and Concrete Laboratory Testing Technician - Grade I.
Testing agency laboratory supervisor shall be an ACI-certified Concrete Laboratory
Testing Technician - Grade II.
C. Source Limitations:
1. Obtain each type or class of cementitious material of the same brand from the same
manufacturer's plant, obtain aggregate from one source, and obtain admixtures through
one source from a single manufacturer.
D. ACI Publications:
1. Comply with ACI 301, "Specification for Structural Concrete," Sections 1 through 5,
unless modified by requirements in the Contract Documents.
1. Engage a qualified independent testing agency to perform material evaluation tests and
to design concrete mixtures.
PART 2 - PRODUCTS
A. Forms:
1. Metal, dressed lumber, or other approved materials that are nonreactive with concrete
and that will provide continuous, true, and smooth concrete surfaces.
B. Chamfer Strips:
C. Form Liners:
1. Units of face design, texture, arrangement, and configuration indicated. Furnish with
manufacturer's recommended liquid-release agent that will not bond with, stain, or
adversely affect concrete surfaces and will not impair subsequent surface treatments of
concrete.
D. Reveal Strips:
1. Metal, PVC, rubber, straight dressed wood, or plywood; with sides kerfed.
E. Sealer:
B. Reinforcing Bars:
C. Plain-Steel Wire:
1. ASTM A 185, fabricated from as-drawn steel wire into flat sheets.
F. Bar Supports:
A. Cementitious Material:
1. Use the following cementitious materials, of the same type, brand, and source,
throughout the Project:
B. Coarse Aggregate:
1. ASTM C 33, Class 4S coarse aggregate or better, graded. Provide aggregates from a
single source.
C. Fine Aggregate:
1. ASTM C 33, manufactured or natural sand, from same source for Project, free of
materials with deleterious reactivity to alkali in cement.
2.5 ADMIXTURES
A. Air-Entraining Admixture:
1. ASTM C 260.
B. Chemical Admixtures:
C. Color Pigment:
a. Color: As indicated.
2.6 BONDBREAKERS
A. Evaporation Retarder:
1. AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9
oz./sq. yd. when dry.
C. Moisture-Retaining Cover:
1. ASTM A 307, Grade A; carbon-steel, hex-head bolts and studs; carbon-steel nuts; and
flat, unhardened steel washers.
F. Welding Electrodes:
H. Shop-Primed Finish:
A. General:
1. Furnish inserts, dowels, bolts, nuts, washers, and other items to be cast in panels for
tilting and lifting.
a. Manufacture inserts with feet of plastic, galvanized steel wire, plastic-tipped steel
wire, or stainless-steel-tipped steel wire.
2. Furnish brace anchors and other accessories to be cast in panels and in casting slab for
attaching bracing.
a. Manufacture wall brace anchors and accessories with feet of galvanized steel wire,
plastic-tipped steel wire, or stainless-steel-tipped steel wire.
b. Manufacture floor brace anchors that will not penetrate vapor retarder under slab-
on-grade.
A. Elastomeric Pads:
1. Preformed, randomly oriented synthetic fibers set in elastomer with a Type A Shore
durometer hardness of 70 to 90, ASTM D 2240.
2.11 GROUT
1. Mill galvanized steel sheet, not less than 0.0269 inch (22 gage) thick, 1-inch wide by 1-
inch deep by 5/8 inch throat. Temporarily fill or cover face opening of slots to prevent
intrusion of concrete or debris.
1. Hot-dipped galvanized steel sheet, not less than 0.0528 inch (16 gage) thick, compatible
with dovetail anchor slot throat opening. Provide seismic anchors with a lip, hook, or clip
on the extended leg that will engage or enclose W2.8 or 0.188-inch diameter hot-dipped
galvanized horizontal joint reinforcement wire.
A. Bonding Agent:
B. Patching Mortar:
1. Dry-pack mix consisting of 1 part portland cement to 2-1/2 parts fine aggregate passing
No. 16 sieve, using only enough water for handling and placing.
A. General.
1. Prepare design mixtures for each type and strength of concrete, proportioned on basis of
laboratory trial mixture or field test data, or both, according to ACI 301.
2. Use a qualified independent testing agency for preparing and reporting proposed
concrete design mixtures based on laboratory trial mixtures.
D. Admixtures:
E. Color Pigment:
A. Ready-Mixed Concrete:
1. Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M, and furnish
batch ticket information.
2. When air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes.
3. When air temperature is between 85 and 90 deg F reduce mixing and delivery time from
90 to 75 minutes.
PART 3 - EXECUTION
3.1 FORMS
A. General:
1. Construct and brace formwork so tilt-up concrete panels are of size, shape, alignment,
elevation, and position indicated.
2. Construct forms on slab-on-grade or on temporary casting slab, at Contractor's option.
3. Provide for openings, offsets, recesses, reveals, rustications, reglets, and blockouts.
4. Place form liners accurately to provide finished surface texture indicated. Provide solid
backing and supports to maintain stability of liners during concreting. Coat form liner with
form-release agent.
5. Fabricate forms for easy removal without hammering or prying against concrete surfaces.
Use kerfed inserts, such as those forming reglets, rustications, and recesses, for easy
removal.
6. Set edge forms for panels to achieve required panel thickness.
7. Chamfer exposed corners and edges, unless otherwise indicated, using chamfer strips
fabricated to produce uniform, smooth lines and tight edge joints.
8. Coat contact surfaces of wood forms and chamfers with sealer before placing
reinforcement.
3.2 BONDBREAKERS
A. Uniformly and continuously apply two coats of bondbreaker to casting-slab surfaces by power
spray or roller according to manufacturer's written instructions, before placing steel
A. General:
1. Comply with CRSI's "Manual of Standard Practice" for fabricating and placing
reinforcement.
2. Accurately position, support, and secure reinforcement against displacement. Locate
and support reinforcement with bar supports to maintain minimum concrete cover.
3. Install welded wire reinforcement in longest practicable lengths on bar supports spaced to
minimize sagging. Lap edges and ends of adjoining sheets at least one mesh spacing.
Offset laps of adjoining sheet widths to prevent continuous laps in either direction. Lace
overlaps with wire.
4. Accurately place and securely support embedded items, anchorages, inserts, cramps,
retainers, bar chords and sleeves, and other items to be built into panels. Coordinate
with other trades for installing cast-in items.
A. General:
1. Comply with ACI 301 for handling, placing, and consolidating concrete.
2. Maintain position of steel reinforcement, inserts, and anchors during concrete placement,
consolidation, and finishing.
3. Screed panel surfaces to correct level with a straightedge and strike off.
a. Begin initial floating before excess moisture or bleedwater appears on the surface.
Use bull floats or darbies to form a uniform and open-textured surface plane free of
humps or hollows. Do not disturb panel surfaces before beginning finishing
operations.
4. Form chamfers at top edges of panel perimeters, openings, and similar locations not
formed by chamfer strips, unless otherwise indicated.
5. Surface Defects: Limit visible surface defects to those permitted by TCA's "Tilt-up
Concrete Association's Guideline Specifications" for Grade A, Architectural panel
surfaces.
5. Deviation of Steel Reinforcement Cover: Maintain minimum cover required by ACI 301.
A. General:
1. Provide face-up finish of panels on inside of a building with float finish followed with
trowel finish.
B. Float Finish:
C. Trowel Finish:
1. After applying float finish, apply first trowel finish and consolidate plastic concrete by
hand trowel or power-driven trowel. Continue troweling passes and restraighten until
surface is free of trowel marks and is uniform in texture and appearance.
1. Where panel face is smooth, cast panel to produce a surface free of pockets, sand
streaks, and honeycombs. Produce a surface appearance of uniform color and texture.
B. Form-Liner Finish:
1. Where panel face is fluted texture, cast panel over form liners placed, secured, and
sealed over casting slab to produce a textured surface free of pockets, streaks, and
honeycombs. Produce a surface appearance of uniform color and texture.
A. General:
1. Protect freshly placed concrete from premature drying and excessive cold or hot
temperatures according to ACI 301.
2. Apply evaporation retarder in hot, dry, or windy weather to protect concrete from rapid
moisture loss before and during finishing operations. Apply according to manufacturer's
written instructions after screeding and bull floating concrete, but before float finishing.
3. Begin curing immediately after finishing concrete. Cure by one or a combination of the
following methods according to ACI 308.1:
a. Moisture Curing: Keep surfaces continuously moist for not less than seven days
with the following materials:
1) Water.
2) Continuous water-fog spray.
3) Absorptive cover, water saturated and kept continuously wet. Cover
concrete surfaces and edges with 12-inch lap over adjacent absorptive
covers.
3.9 ERECTION
A. General:
1. Use erection equipment with care to prevent damage to floor slabs and panels.
2. Lift, support, and erect panels only at designated lifting or supporting points indicated on
Shop Drawings.
3. Do not erect panels until 75 percent of 28-day compressive strength of concrete has
been verified.
4. Install tilt-up concrete panels level, plumb, square, and true. Place panels on leveled
grout-setting pads or shims in correct position. Maintain joint width of 1/2 inch between
panels.
5. Temporarily brace and support panels securely in position against loads comparable in
intensity to those for which structure was designed. Maintain braces and supports in
place, undisturbed, until entire integrated supporting structure has been completed and
permanent connections to panels are secured.
6. Anchor panels in place and, if indicated, to one another.
A. Special Inspections:
1. Contractor shall engage a Special Inspector to perform special inspections for erection of
precast concrete members and as follows:
B. The inspection program by the Special Inspector shall comply with Table 1704.4 of the 2009
International Building Code.
C. Testing:
1. Engage a qualified testing and inspecting agency to perform tests and inspections and to
submit reports.
D. Testing Services:
A. General:
1. Install tilt-up concrete panels without exceeding the following erection tolerances:
a. Joint Width Variation (Exterior Face): Without decreasing or increasing more than
50 percent from specified joint width, maintain joint width as follows:
b. Joint Taper: Maximum 3/8 inch over length, but not greater than the following:
c. Panel Alignment:
A. General:
1. Patch holes and voids left by erecting and bracing inserts on tilt-up panels and slabs-on-
grade. Cut or chip edges of voids perpendicular to concrete surface. Fill blockouts
where indicated.
a. Clean, dampen with water, and brush-coat holes, voids, and blockouts with
bonding agent. Fill and compact with patching mortar of a stiff consistency before
bonding agent has dried.
b. Finish surfaces of fills and repairs to Contracting Officer's approval, with materials
of same colors and textures as finishes on surrounding surfaces.
2. Repair damaged galvanized steel surfaces of connectors by cleaning and applying a coat
of zinc repair paint.
3. Repair damage to tilt-up panels and slabs-on-grade resulting from tilt-up work, as
directed by Contracting Officer.
4. Remove and replace tilt-up panels that do not comply with requirements in this Section.
5. Demolish and remove temporary concrete casting slabs.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 03 Section Tilt-Up Concrete for masonry veneer inserts, Division 05
Sections Metal Fabrications for loose lintels and Cold-Formed Metal Framing for metal stud supported
masonry veneer.
2. This Section specifies clay and concrete masonry for engineered and empirically designed
applications. Masonry units in this Section include ordinary concrete masonry units, decorative
concrete masonry units, face brick made from clay, and precast concrete trim units.
A. This Section does not specify brick or concrete pavers, brick flooring, thin brick applications,
glass block, stone masonry, or masonry restoration and cleaning.
A. Building Code Requirements for Masonry Structures (ACI 530/ASCE 5-05/TMS 402-05) is
adopted, with amendments, by IBC and establishes minimum requirements for acceptance of
design of unit masonry assemblies.
B. Specification for Masonry Structures (ACI 530.1/ASCE 6/TMS 602) is adopted, with
amendments, by IBC and establishes minimum requirements for acceptance of construction of
unit masonry assemblies.
4. Design Considerations:
A. The Guide Specifications specify a minimum average net area compressive strength for each
type of unit masonry in Part 1 "Performance Requirements." A mortar type is specified in Part 2
"Mortar And Grout Mixes." These requirements establish the basis of the unit masonry net-area
compressive strengths (f'm) and functional performance of the masonry assemblies. Revise
these requirements in accordance with project conditions requiring assemblies of different
compressive strengths or more functional properties. Coordinate with the drawings the extent of
each type of engineered designed masonry required.
B. Indicate and coordinate face brick size, color, texture, etc. on drawings for each specific project
location.
C. Masonry Joint Reinforcement, Ties, and Anchors in Exterior Walls: Use only hot-dip galvanized,
carbon steel. Laboratory tests and field experience indicate that portland cement-lime mortars
provide better resistance to water leakage and higher flexural strengths than masonry cement
mortars. Because both of these attributes are important in exterior wall construction and walls
requiring resistance to seismic forces Portland cement-lime mortars and mortar cement mortars
are specified in this Section. Where project conditions do not require resistance to water leakage
or seismic forces the specification allows masonry cement to be used.
D. Indicate masonry anchored directly to structural steel members without gaps unless movement of
structural member abutting masonry is anticipated, i.e., rigid frames, wind bents, etc. Where
movement is anticipated provide an open space not less than 1/2" to 1" in width between
masonry and structural member. Keep open space free of mortar and other rigid materials to
avoid stress on masonry assembly.
E. Indicate an impermeable flashing material in all exterior unit masonry assemblies to provide
water drainage and prevent water penetration through the assembly.
June 2011 04 20 00 1
DeCA DESIGN CRITERIA HANDBOOK
04 20 00 UNIT MASONRY
F. Expansion, Control, and Isolation Joints: Analyze each Project and show the locations of control
joints on Drawings based on visual and functional requirements.
1. Clay Face Brick: Refer to The Brick Industry Associations (BIA) Technical Notes 18 and 18A
for detailed analyses of differential movement, expansion joints, flexible anchorage of clay
masonry construction, and the proper location of joints.
2. Concrete Masonry Units: Refer to The National Concrete Masonry Associations (NCMA)
TEK 10 Series for crack control in concrete masonry walls and the proper location of joints.
G. In accordance with the IBC all projects are assigned to a Seismic Design Category. Where
required by project location, add applicable requirements of the IBC and referenced codes and
standards.
H. Exterior masonry walls shall be designed for security protection in accordance with UFC 4-010-
01 DoD Minimum Antiterrorism Standards For Buildings, October 08, 2003, including change 1,
22 January 2007, Standard 9, as follows:
1. Unreinforced masonry walls are prohibited for the exterior walls of new buildings.
2. A minimum of 0.05% vertical reinforcement with a maximum spacing of 48"shall be provided
with reinforcement within 1.3' of the ends of walls. The horizontal reinforcement must be at
least 0.025%, consisting of either joint reinforcement spaced no more than 1.3', or bond
beam reinforcement spaced no more than 4', with reinforcement within 1.3' of the top and
bottom of the wall.
3. For existing Buildings, implement mitigating measures to provide an equivalent level of
protection.
4. This requirement shall not preclude the need to design masonry assemblies for forces
required by other criteria such as seismic requirements.
5. Testing and Inspection: Although the IBC requires special inspections be performed by special
inspectors who are engaged by the Government or the design professional, this Section specifies the
Contractor shall perform these duties.
END OF SECTION
June 2011 04 20 00 2
SECTION 04 20 00
UNIT MASONRY
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 REFERENCES
A. Specification for Masonry Structures: ACI 530.1-08 /ASCE 6-08 /TMS 602-08.
1.3 DEFINITIONS
1. Provide units with minimum average net area compressive strengths as follows:
2. For Concrete Masonry Units: 1900 psi.
B. Determine net-area compressive strength (f'm) of masonry from average net-area compressive
strengths of masonry units and mortar types (unit-strength method) according to Tables 1 and 2
in ACI 530.1/ASCE 6/TMS 602. Provide Type S mortar at all locations.
1.5 SUBMITTALS
A. Shop Drawings:
B. LEED Submittals:
1. Product Certificates for Credit MR 5.1[ and Credit MR 5.2]: For products and materials
required to comply with requirements for regional materials indicating location and
distance from Project of material manufacturer and point of extraction, harvest, or
recovery for each raw material. Include statement indicating cost for each regional
material and the fraction by weight that is considered regional.
C. Material Certificates:
a. Masonry Units:
b. Face Brick:
E. Mix Designs:
1. For each combination of masonry unit type and mortar type, provide statement of
average net-area compressive strength of masonry units, mortar type, and resulting net-
area compressive strength of masonry determined according to Tables 1 and 2 in
ACI 530.1/ASCE 6/TMS 602.
I. Sustainability Submittals:
1. Product Certificates: Comply with requirements for LEED NC Credit MR 5. For products
and materials required to comply with requirements for regional materials indicating
location and distance form Project of material manufacturer and point of extraction,
harvest, or recovery for each raw material. Include statement indicating cost for each
regional material and the fraction by weight that is considered regional.
J. Submittal List:
1. Obtain exposed masonry units of a uniform texture and color, or a uniform blend within
the ranges accepted for these characteristics, through one source from a single
manufacturer for each product required.
1. Obtain mortar ingredients of a uniform quality, including color for exposed masonry, from
a single manufacturer for each cementitious component and from one source or producer
for each aggregate.
1. Where indicated, provide materials and construction identical to those of assemblies with
fire-resistance ratings determined per ASTM E 119 by a testing and inspecting agency,
by equivalent concrete masonry thickness, or by other means, as acceptable to
authorities having jurisdiction.
D. Mockup:
1. Build mockup to verify selections made under sample submittals and to demonstrate
aesthetic effects and set quality standards for materials and execution.
2. Build mockup to include each type of typical exterior wall in sizes approximately 48
inches long by 48 inches high by full thickness, including face and backup wythes,
precast concrete trim, and accessories.
1. Special inspections for structural masonry shall be performed under the direct
supervision of a Professional Structural Engineer registered in the state in which the
project is located. The personnel performing the inspections shall be ICC-certified
Structural Masonry Special Inspector or an equivalent certification program.
A. Storage:
1. Store masonry units on elevated platforms in a dry location. If units are not stored in an
enclosed location, cover tops and sides of stacks with waterproof sheeting, securely tied.
If units become wet, do not install until they are dry.
2. Store cementitious materials on elevated platforms, under cover, and in a dry location.
Do not use cementitious materials that have become damp.
1. Deliver preblended, dry mortar mix in moisture-resistant containers designed for lifting
and emptying into dispensing silo. Store preblended, dry mortar mix in delivery
containers on elevated platforms, under cover, and in a dry location or in a metal
dispensing silo with weatherproof cover.
A. Protection of Masonry:
1. During construction, cover tops of walls, projections, and sills exposed to weather with
waterproof sheeting at end of each day's work. Cover partially completed masonry when
construction is not in progress.
2. Extend cover a minimum of 24 inches down both sides and hold cover securely in place.
B. Applied Loads:
1. Do not apply uniform floor or roof loads for at least 12 hours and concentrated loads for
at least 3 days after building masonry walls.
C. Stain Prevention:
1. Prevent grout, mortar, and soil from staining the face of masonry to be left exposed or
painted. Immediately remove grout, mortar, and soil that come in contact with such
masonry.
2. Protect base of walls from rain-splashed mud and from mortar splatter by spreading
coverings on ground and over wall surface.
3. Protect sills, ledges, and projections from mortar droppings.
4. Protect surfaces of window and door frames, as well as similar products with painted and
integral finishes, from mortar droppings.
5. Turn scaffold boards near the wall on edge at the end of each day to prevent rain from
splashing mortar and dirt onto completed masonry.
D. Cold-Weather Requirements:
1. Do not use frozen materials or materials mixed or coated with ice or frost. Do not build
on frozen substrates. Remove and replace unit masonry damaged by frost or by freezing
conditions. Comply with cold-weather construction requirements contained in
ACI 530.1/ASCE 6/TMS 602.
E. Cold-Weather Cleaning:
1. Use liquid cleaning methods only when air temperature is 40 deg F and above and will
remain so until masonry has dried, but not less than 7 days after completing cleaning.
F. Hot-Weather Requirements
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Defective Units: Referenced masonry unit standards may allow a certain percentage of units to
exceed tolerances and to contain chips, cracks, or other defects exceeding limits stated in the
standard. Do not uses units where such defects, including dimensions that vary from specified
dimensions by more than stated tolerances, will be exposed in the completed Work or will
impair the quality of completed masonry.
A. Shapes:
D. Integral Water Repellent: Provide decorative units made with liquid polymeric, integral water-
repellent admixture that does not reduce flexural bond strength. Units made with integral water
repellent, when tested as a wall assembly made with mortar containing integral water-repellent
manufacturer's mortar additive according to ASTM E 514, with test period extended to 24 hours,
show no visible water or leaks on the back of the test specimen.
1. Basis-of Design Product: Dry-Block; W. R. Grace & Co., Construction Products Division.
2.4 BRICK
A. General:
B. Face Brick:
A. Materials:
a. Color: As indicated.
2. Aggregates: ASTM C 33. Provide aggregates that are hard, durable, selected, and
graded; free of material that causes staining or reacting with cement.
3. Pigments:
4. Nonfading, resistant to lime and other alkalis. Natural and synthetic iron oxides and
chromium oxides, compounded for use in concrete mixes. Use only pigments with record
of satisfactory performance in concrete.
a. Stainless steel shapes: AISI Type 302/304.Anchor bolts: ASTM A 307, low
carbon steel bolts, regular hexagon nuts and carbon steel washers; hot-dipped
galvanized.
B. Concrete:
1. Minimum 3000 psi, unless otherwise indicated, 28 day strength, air entrained in
accordance with ACI 301.
C. Fabrication:
1. Use rigid molds, constructed to maintain precast unit uniform in shape, size, and finish.
2. Reinforce sills and lintels with not less than two No. 4 bars.
3. Reinforce sills and lintels for full length and a sufficient length beyond ends to allow
splicing or tying to building reinforcement, if any.
4. Maintain 3/4 inch minimum clearance between reinforcement and unit face.
5. Place and embed flashing reglets continuous and straight.
6. Provide drip grooves on underside where units overhang walls.
7. Provide sills with washes. Fabricate sills for windows and mullions in sections with head
joints at mullions and a 1/4 inch allowance for mortar joints. The ends, except at exposed
surfaces, shall be roughened for bond.
8. Finish: Provide smooth, dense finish on exposed-to-view surfaces. Exposed surfaces
shall be free of surface voids, spalls, cracks, and chipped and broken edges.
A. Built-in-place horizontal grouted masonry element made from concrete masonry units with
reinforcing bars placed as indicated and filled with coarse grout. Temporarily support built-in-
place element until cured.
A. Portland Cement:
1. ASTM C 150, Type I or II, except Type III may be used for cold-weather construction.
1. Packaged blend of portland cement complying with ASTM C 150, Type I or Type III, and
hydrated lime complying with ASTM C 207. Mix proportions shall be per ASTM C270,
proportion specification based on volume.
1. ASTM C 144; except for joints less than 1/4 inch thick, use aggregate graded with 100
percent passing the No. 16 sieve.
1. ASTM C 404.
F. Cold-Weather Admixture:
G. Water-Repellent Admixture:
1. Liquid water-repellent mortar admixture intended for use with decorative concrete
masonry units, containing integral water repellent by same manufacturer.
2. Basis-of Design Product: Dry-Block; W. R. Grace & Co., Construction Products Division.
H. Water: Potable.
I. Colored Cement Product: Packaged blend made from portland cement and lime or mortar
cement and mortar pigments, all complying with specified requirements, and containing no other
ingredients.
1. Formulate blend as required to produce color indicated or, if not indicated, as selected
from manufacturer's standard colors.
2. Premix cement and pigment at plant. Do not mix cement and pigment at job site.
3. Pigments shall not exceed 10 percent of portland cement by weight.
4. Pigments shall not exceed 5 percent of mortar cement by weight.
5. Products:
b. Colored Mortar Cement: Lafarge North America Inc.; Magnolia Superbond Mortar
Cement.
2.8 REINFORCEMENT
1. ASTM A 951.
2. Interior Walls: Mill-galvanized, carbon steel wire.
3. Exterior Walls (including backup wythes): Hot-dip galvanized, carbon steel wire.
4. Wire Size for Side, Cross, and Veneer Rods: W1.7 or 0.148-inch (9 gage) diameter.
5. Spacing of Cross Rods, Tabs, and Cross Ties: Not more than 16 inches o.c.
6. Provide in lengths of not less than 10 feet, with prefabricated corner and tee units.
Adjustable (two-piece) type, ladder design, with one side rod at each face shell of backing wythe and with
separate ties (pintles) that extend into facing wythe. Ties have two hooks that engage eyes or slots in
reinforcement and resist movement perpendicular to wall. Ties extend at least halfway through facing
wythe but with at least 5/8-inch cover on outside face.
a. Wire size for veneer ties (pintles): W2.8 or 0.188-inch3/16 inch diameter.
b. Basis-of-design product for ladder type with adjustable ties:
Dayton Superior Corporation, Dur-O-Wal Division; DA3600 I.L.E. Ladur-Eye, including pintles.
A. Materials:
1. Provide ties and anchors specified in subsequent paragraphs that are made from
materials that comply with subparagraphs below, unless otherwise indicated.
2. Interior Walls: Mill-Galvanized, Carbon-Steel Wire: ASTM A 82; with
ASTM A 641/A 641M, Class 1 coating.
3. Exterior Walls: Hot-Dip Galvanized, Carbon-Steel Wire: ASTM A 82; with
ASTM A 153/A 153M, Class B-2 coating.
4. Galvanized Steel Sheet: ASTM A 653/A 653M, Commercial Steel, G60 zinc coating.
1. Unless otherwise indicated, size wire ties to extend at least halfway through veneer but
with at least 5/8-inch cover on outside face. Outer ends of wires are bent 90 degrees and
extend 2 inches parallel to face of veneer.
C. Adjustable Anchors for Connecting to Structure: Provide anchors that allow vertical or
horizontal adjustment but resist tension and compression forces perpendicular to plane of wall.
D. Rigid Anchors:
1. Fabricate from steel bars 1-1/2 inches wide by 1/4 inch thick by 24 inches long, with ends
turned up 2 inches or with cross pins, unless otherwise indicated. Connect T-
intersections of CMU shear walls with rigid anchors in lieu of masonry bonding or bond
beams, unless otherwise indicated.
2. Corrosion Protection: Hot-dip galvanized to comply with ASTM A 153/A 153M.
1. General: Provide anchors that allow vertical adjustment but resist tension and
compression forces perpendicular to plane of wall, for attachment over sheathing to metal
studs, and as follows:
a. Anchor Section: Sheet metal plate, 1-1/2 incheswide by 6 incheslong, with screw
holes top and bottom and with raised rib-stiffened strap stamped into center to
provide a slot between strap and plate for inserting wire tie.
b. Fabricate sheet metal anchor sections and other sheet metal parts from 0.067-
inch-nominal 14 gage thick, steel sheet, galvanized after fabrication.
c. Fabricate Triangular wire ties from 0.187-inch-diameter, hot-dip galvanized steel
wire.
d. Basis-of-Design Product: Dayton Superior Corporation, Dur-O-Wal Division;
DA210 Veneer Anchor Screw On Plate with DA700 Series Triangular Ties.
A. Anchor Bolts:
1. Headed or L-shaped steel bolts complying with ASTM A 307, Grade A; with ASTM A 563
hex nuts and, where indicated, flat washers; hot-dip galvanized to comply with
ASTM A 153/A 153M, Class C; of dimensions indicated.
B. Post-Installed Anchors:
A. Flexible Flashing: For flashing not exposed to the exterior, use one of the following, unless
otherwise indicated:
1. Copper-Laminated Flashing: 5-oz./sq. ft. copper sheet bonded with asphalt between 2
layers of glass-fiber cloth. Use only where flashing is fully concealed in masonry.
a. Available Products:
a. Available Products:
a. Available Products:
1. Provide metal drip edge, where flashing is exposed or partly exposed and where
indicated, complying with SMACNA's "Architectural Sheet Metal Manual."
2. Stainless Steel: ASTM A 240/A 240M, Type 304, 0.016 inch thick.
3. Fabricate continuous flashings in sections 96 inches long minimum, but not exceeding 12
feet. Provide splice plates at joints of formed, smooth metal flashing.
4. Extend at least 3 inches into wall and 1/2 inch out from wall, with outer edge bent down
30 degrees and hemmed.
C. Adhesives, Primers, and Seam Tapes for Flashings: Flashing manufacturer's standard
products or products recommended by flashing manufacturer for bonding flashing sheets to
each other and to substrates.
A. Compressible Filler:
C. Bond-Breaker Strips:
1. Asphalt-saturated, organic roofing felt complying with ASTM D 226, Type I (No. 15
asphalt felt).
1. Wire units designed to fit into mortar bed joints spanning masonry unit cells with loops for
holding reinforcing bars in center of cells. Units are formed from 0.142-inch steel wire,
hot-dip galvanized after fabrication. Provide units with either two loops or four loops as
needed for number of bars indicated.
2. Basis-of-Design Product: Dayton Superior Corporation, Dur-O-Wal Division; D/A 810,
D/A 812 or D/A 817.
E. Weeps:
1. Wicking Material: Absorbent rope, made from cotton or UV-resistant synthetic fiber, 1/4
to 3/8 inch in diameter, in length required to produce 2-inch exposure on exterior and 18
inches in cavity between wythes.
F. Pea Gravel:
1. ASTM C 578, Type IV, closed-cell product extruded with an integral skin.
B. Adhesive:
A. Cleaning Solutions:
1. Not harmful to masonry work or adjacent materials; expressly approved for intended use
by manufacturers of masonry units and mortar being cleaned.
A. General:
1. Furnish dry mortar ingredients in form of a preblended mix. Measure quantities by weight
to ensure accurate proportions, and thoroughly blend ingredients before delivering to
Project site.
1. Comply with ASTM C 270, Proportion Specification. Provide Type S mortar unless
another type is indicated or needed to provide required compressive strength of masonry.
D. Pigmented Mortar:
1. Comply with ASTM C 476, delete reference to mix proportion per compressive strength in
Paragraph 5.2 of ASTM C476.
2. Use grout of type indicated or, if not otherwise indicated, of type (fine or coarse) that will
comply with Table 1.15.2 in ACI 530.1/ASCE 6/TMS 602 for dimensions of grout spaces
and pour height.
3. Provide grout with a slump of 8 to 11 inches as measured according to
ASTM C 143/C 143M.
PART 3 - EXECUTION
3.1 EXAMINATION
A. General:
1. Examine conditions, with Installer present, for compliance with requirements for
installation tolerances and other conditions affecting performance of work.
2. Verify that foundations are within tolerances specified.
3. Verify that reinforcing dowels are properly placed.
4. Before installation, examine rough-in and built-in construction for piping systems to verify
actual locations of piping connections.
5. Proceed with installation only after unsatisfactory conditions have been corrected.
A. Thickness:
1. Build masonry construction to full thickness shown. Build single-wythe walls to actual
widths of masonry units, using units of widths indicated.
1. Build chases and recesses to accommodate items specified in this and other Sections.
1. Leave openings for equipment to be installed before completing masonry. After installing
equipment, complete masonry to match the construction immediately adjacent to
opening.
D. Cutting of Units:
1. Use full-size units without cutting if possible. If cutting is required to provide a continuous
pattern or to fit adjoining construction, cut units with motor-driven saws; provide clean,
sharp, unchipped edges. Allow units to dry before laying unless wetting of units is
specified. Install cut units with cut surfaces and, where possible, cut edges concealed.
1. Select and arrange units for exposed unit masonry to produce a uniform blend of colors
and textures.
2. Mix units from several pallets or cubes as they are placed.
3. Face Brick Color Range: Lay face brick with color range evenly distributed throughout.
Do not install brick so that colors are concentrated in wall areas that result in an uneven,
blotchy color distribution.
1. Wet brick before laying if initial rate of absorption exceeds 30 g/30 sq. in. per minute
when tested per ASTM C 67. Allow units to absorb water so they are damp but not wet
at time of laying.
1. Do not retemper colored mortar unless samples of retempered colored mortar have been
made and no significant change in appearance of the color of the mortar is evident, as
acceptable to the Contracting Officer.
H. Tolerances:
1. Comply with construction tolerances in ACI 530.1/ASCE 6/TMS 602 and with the
following:
a. For conspicuous vertical lines, such as external corners, door jambs, reveals, and
control joints, do not vary from plumb by more than 1/8 inch in 10 feet, 1/4 inch in
20 feet, or 1/2 inch maximum.
A. General:
1. Lay out walls in advance for accurate spacing of surface bond patterns with uniform joint
thicknesses and for accurate location of openings, movement-type joints, returns, and
offsets. Avoid using less-than-half-size units, particularly at corners, jambs, and, where
possible, at other locations.
1. Unless otherwise indicated, lay exposed masonry in running bond; do not use units with
less than nominal 4-inch horizontal face dimensions at corners or jambs.
C. Concealed Masonry:
1. Lay concealed masonry with all units in a wythe in running bond or bonded by lapping not
less than 4-inches. Bond and interlock each course of each wythe at corners. Do not
use units with less than nominal 4-inch horizontal face dimensions at corners or jambs.
1. Stop work by racking back units in each course from those in course below; do not tooth.
When resuming work, clean masonry surfaces that are to receive mortar, remove loose
masonry units and mortar, and wet brick if required before laying fresh masonry.
E. Built-in Work:
1. As construction progresses, build in items specified in this and other Sections. Fill in
solidly with masonry around built-in items.
F. Steel Frames:
1. Fill space between steel frames and masonry solidly with mortar, unless otherwise
indicated.
2. If additives are used in mortar, field coat steel door frames in contact with mortar with a
bituminous compound to prevent corrosion.
G. Built-In Items:
1. Where built-in items are to be embedded in cores of hollow masonry units, place a layer
of metal lath, wire mesh, or plastic mesh in the joint below and rod mortar or grout into
core.
H. Grouting of CMUs:
I. Interior Partitions:
1. Build non-load-bearing interior partitions full height of story to underside of solid floor or
roof structure above, unless otherwise indicated.
2. Install compressible filler in joint between top of partition and underside of structure
above.
3. At fire-rated partitions, treat joint between top of partition and underside of structure
above to comply with Division 07 Section Firestopping.
1. With face shells fully bedded in mortar and with head joints of depth equal to bed joints.
2. With webs fully bedded in mortar in all courses of piers, columns, and pilasters.
3. With webs fully bedded in mortar in grouted masonry, including starting course on
footings.
4. With entire units, including areas under cells, fully bedded in mortar at starting course on
footings where cells are not grouted.
1. Lay solid masonry units with completely filled bed and head joints; butter ends with
sufficient mortar to fill head joints and shove into place. Do not deeply furrow bed joints
or slush head joints.
1. Set precast concrete trim units in full bed of mortar with full vertical joints. Fill dowel,
anchor, and similar holes.
D. Joints:
1. Tool exposed joints slightly concave when thumbprint hard, using a jointer larger than
joint thickness, unless otherwise indicated.
2. Rake out mortar in preparation for application of sealants where sealants are indicated in
mortar joints.
A. Corners: Provide interlocking masonry unit bond in each wythe and course at corners, unless
otherwise indicated.
a. General:
A. Bond:
1. Face brick veneer on concrete masonry-unit back-up. Bond wythes of cavity walls
together using cavity wall joint reinforcement.
a. Adjustable (two-piece) type, ladder design, with one side rod at each face shell of
backing wythe and with separate ties that extend into facing wythe. Provide ties
installed in horizontal joints, but not less than one metal tie for 1.77 sq. ft. of wall
area spaced not to exceed 16 inches o.c. horizontally and 16 inches o.c. vertically.
Provide additional ties around openings larger than 16 inches in either dimension.
Place anchors within 12 inches of openings.
B. Cavities:
1. Keep cavities clean of mortar droppings and other materials during construction. Bevel
beds away from cavity, to minimize mortar protrusions into cavity. Do not attempt to
trowel or remove mortar fins protruding into cavity.
1. Place small dabs of adhesive, spaced approximately 12 inches o.c. both ways, on inside
face of insulation boards, or attach with plastic fasteners designed for this purpose. Fit
courses of insulation between wall ties and other confining obstructions in cavity, with
edges butted tightly both ways. Press units firmly against inside wythe of masonry or
other construction as shown.
2. Fill cracks and open gaps in insulation with crack sealer compatible with insulation and
masonry.
A. General:
1. Fasten screw-attached anchors through sheathing to wall framing with metal fasteners of
type indicated. Use two fasteners unless anchor design only uses one fastener.
2. Insert anchor sections in metal studs as sheathing is installed. Provide one anchor at
each stud in each horizontal joint between sheathing boards.
3. Locate anchor sections to allow maximum vertical differential movement of ties up and
down.
4. Space anchors not more than 16 inches o.c. vertically and 16 inches o.c. horizontally with
not less than 1 anchor for each 1.77 sq. ft. of wall area. Install additional anchors within
12 inches of openings and at intervals, not exceeding, 16 inches around perimeter.
A. General:
1. Install control and expansion joint materials in unit masonry as masonry progresses. Do
not allow materials to span control and expansion joints without provision to allow for in-
plane wall or partition movement. If locations of vertical expansion and control joints are
not shown, locate as follows:
2. Form control joints in concrete masonry using one of the following methods unless
otherwise indicated:
3. Form expansion joints in brick made from clay or shale as follows unless otherwise
indicated:
a. Build flanges of metal expansion strips into masonry. Lap each joint 4 inches in
direction of water flow. Seal joints below grade and at junctures with horizontal
expansion joints if any.
b. Build flanges of factory-fabricated, expansion-joint units into masonry.
c. Build in compressible joint fillers where indicated.
d. Form open joint full depth of brick wythe and of width indicated, but not less than 1
inch for installation of sealant and backer rod specified in Division 07 Section Joint
Sealants.
3.11 LINTELS
A. Steel Lintels:
1. Provide steel lintels where indicated and where openings of more than 12 inches for brick
size units and 24 inches for block size units are shown without structural steel or other
supporting lintels.
2. Steel Lintel Angles Per Masonry Wythe: 3-1/2 inches by 3-1/2 inches by 1/4 inch. Verify
size of angles with Contracting Officer before proceeding.
3. Provide minimum bearing of 8 inches at each jamb, unless otherwise indicated.
B. Masonry Lintels:
1. In concrete masonry walls provide masonry lintels where shown and where openings of
more than 8 inches for brick-size units and 16 inches for block-size units are shown
without structural steel or other supporting lintels. Match color and texture of adjacent
units.
A. General:
1. Install embedded flashing and weep holes in masonry at shelf angles, lintels, ledges,
other obstructions to downward flow of water in wall, and where indicated.
1. Prepare masonry surfaces so they are smooth and free from projections that could
puncture flashing. Where flashing is within mortar joint, place through-wall flashing on
sloping bed of mortar and cover with mortar. Before covering with mortar, seal
penetrations in flashing with adhesive, sealant, or tape as recommended by flashing
manufacturer.
a. Install metal drip edge beneath flashing at exterior face of wall. Adhere flashing to
top of metal.
b. Lap ends of flashing a minimum of 6 inches. Seal flashing lap with mastic or
adhesive compatible with flashing material if flashing is not self-adhering.
2. Cavity Walls:
a. Install concealed through-wall flexible flashing 1/2 inch back from exterior face of
outer wythe of masonry, over metal drip edge, through outer wythe, and turn up a
minimum of 8 inches.
1) Where interior face of masonry wall is exposed to building interior and is not
scheduled to be concealed, extend flexible flashing through inner wythe to
within 1/2 inch of the interior face of the wall.
2) Where interior face of inner wythe is not exposed to building interior and is
scheduled to be concealed, extend flexible flashing completely through inner
wythe and turn flashing up approximately 2 inches.
3) For support of pea gravel place through-wall flashing on sloping bed of
mortar conforming to the curve of the flashing.
3. Masonry-veneer Walls:
a. Install concealed flexible flashing 1/2 inch back from exterior face of veneer, over
metal drip edge, through veneer, across air space behind veneer, and up face of
sheathing at least 8 inches, with upper edge tucked under building paper or
building wrap lapping at least 4 inches.
4. Below wall openings in masonry, extend flexible flashing under sills 1/2 inch back from
exterior face of masonry, over metal drip edge, and turn up flashing as specified for type
of wall construction.
5. At lintels install metal drip edge beneath flashing at exterior face of wall in continuous bed
of adhesive applied directly to steel lintels. Turn up flashing over lintel and as specified
for type of wall construction.
C. Weeps:
1. Install weep holes in head joints in exterior wythes of first course of masonry immediately
above embedded flashing and as follows:
D. Cavity Drainage:
1. Place pea gravel in cavities as soon as practical to a height equal to height of first course
above top of flashing, but not less than 2 inches, to maintain drainage.
A. Basic Requirement:
1. Reinforce concrete masonry unit cores with reinforcement bars and grout.
C. Placing Reinforcement:
D. Keying:
1. To form key for subsequent lift, terminate grout lift 1-1/2 inches below top course.
E. Grouting:
1. Do not place grout until entire height of masonry to be grouted has attained enough
strength to resist grout pressure.
2. Comply with requirements in ACI 530.1/ASCE 6/TMS 602 for cleanouts and for grout
placement, including minimum grout space and maximum pour height.
3. Limit height of vertical grout pours to not more than 60 inches.
4. Consolidate pours by mechanical vibration and reconsolidate by mechanical vibration
after initial water loss and settlement has occurred.
A. Use specially formed U-shaped bond beam units. Place horizontal reinforcement in bond
beams; lap at corners and intersections. Fill bond beam course with grout or concrete as
indicated.
a. Inspections:
1) The inspection program by the Special Inspector shall comply with Table
1704.5.1 of the 2009 International Building Code.
1) Mortar and grout samples shall be secured from field mixed materials. Do
not use retempered mortar.
4) Test results will be reported in writing on same day that tests are made.
Reports of compressive strength tests will contain the project identification
name and number, date of material placement, name of testing service,
location of material in structure, design compressive strength at 28 days,
material mix proportions and materials; compressive breaking strength for
both seven-day and 28-day tests.
5) If testing service reports and inspections indicated specified material
strengths and other characteristics have not been attained in the structure,
the testing service will make additional tests of in-place mortar or grout, as
directed by the Contracting Officer. Contractor shall pay for such tests
conducted, and any other additional testing as may be required, when
unacceptable material is verified.
A. General:
1. Remove and replace masonry units that are loose, chipped, broken, stained, or otherwise
damaged or that do not match adjoining units. Install new units to match adjoining units;
install in fresh mortar, pointed to eliminate evidence of replacement.
B. Pointing:
1. During the tooling of joints, enlarge voids and holes, except weep holes, and completely
fill with mortar. Point up joints, including corners, openings, and adjacent construction, to
provide a neat, uniform appearance. Prepare joints for sealant application, where
indicated.
C. In-Progress Cleaning:
1. Clean unit masonry as work progresses by dry brushing to remove mortar fins and
smears before tooling joints.
D. Final Cleaning:
1. After mortar is thoroughly set and cured, clean exposed masonry as follows:
END OF SECTION
DESIGN CRITERIA
2. This Section specifies the fabrication and erection of structural steel for building construction,
including miscellaneous sub-framing units that may be part of the structural-steel framing system.
3. All structural steel shall be shop prime painted with a non-asphaltic primer. Do not allow the use of
red oxide primers. This is necessary to develop bond for field applied paint finish.
5. All structural steel exposed to the building exterior shall be hot-dipped galvanized before priming or
shop primed with an anti-corrosion primer that prevents or inhibits corrosion or rusting of steel.
6. In accordance with the IBC all projects are assigned to a Seismic Design Category. Where required
by project location, add applicable requirements of the IBC and referenced codes and standards.
ANSI/AISC 341s1 provisions apply when the seismic response modification factor R, as specified in
the applicable building code, is taken greater than 3, regardless of the seismic design category.
7. Testing and Inspection: Although the IBC requires special inspections be performed by special
inspectors who are engaged by the Government or the design professional, this Section specifies the
Contractor shall perform these duties.
END OF SECTION
June 2011 05 12 00 1
SECTION 05 12 00
STRUCTURAL STEEL FRAMING
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1. Structural steel.
2. Grout.
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of steel products.
A. Structural Performance:
1.3 SUBMITTALS
A. Product Data:
B. LEED Submittal:
1. Product Data for Credit MR 4.1[ and Credit MR 4.2]: For products having recycled
content, documentation indicating percentages by weight of postconsumer and
preconsumer recycled content. Include statement indicating costs for each product
having recycled content.
a. Include details of cuts, connections, splices, camber, holes, and other pertinent
data.
b. Indicate welds by standard AWS symbols, distinguishing between shop and field
welds, and show size, length, and type of each weld.
c. Indicate type, size, and length of bolts, distinguishing between shop and field bolts.
Identify high-strength bolted slip-critical, direct-tension, or tensioned shear/bearing
connections.
d. Include Shop Drawings signed and sealed by a qualified professional engineer
responsible for their preparation when connections are required to be designed by
the fabricator.
e. Identify members and connections of the seismic-load-resisting system.
f. Identify locations and dimensions of protected zones.
g. Identify demand critical welds.
D. Welding Certificates.
F. Special Inspection reports on shop and field bolted connections, and welded connections.
1. Product Data:
H. Submittal List:
A. Installer Qualifications:
1. Engage an experienced Installer who has completed structural steel work similar in
material, design, and extent to that indicated for this Project and with a record of
successful in-service performance.
B. Fabricator Qualifications:
1. Engage a qualified fabricator that participates in the AISC Quality Certification Program
and is designated an AISC-Certified Plant, Category STD.
E. Welding: Qualifications:
1. Qualify procedures and personnel according to AWS D1.1 "Structural Welding Code-
Steel."
1. Special Inspections for bolted and welded connections and steel details shall be
performed under the direct supervision of a Professional Engineer registered in the State
in which the project is located. The personnel performing the inspections shall be ICC-
certified Structural Steel and Welding Special Inspection or an equivalent certification
program.
A. Delivery:
1. Deliver structural steel to Project site in such quantities and at such times to ensure
continuity of installation.
1. Store materials to permit easy access for inspection and identification. Keep steel
members off ground by using pallets, platforms, or other supports. Protect steel
members and packaged materials from erosion and deterioration.
2. Store fasteners in a protected place. Clean and relubricate bolts and nuts that become
dry or rusty before use. Comply with manufacturers written recommendations for
cleaning and lubricating ASM F 1852 fasteners and for retesting fasteners after
lubrication.
3. Do not store materials on structure in a manner that might cause distortion or damage to
members or supporting structures. Repair or replace damaged materials or structures as
directed.
1.6 SEQUENCING
PART 2 - PRODUCTS
1. Finish: Black.
G. Welding Electrodes:
D. Non-High-Strength Bolts, Anchor Bolts, Nuts, and Washers: ASTM A 307, Grade A.
1. Carbon-steel, hex-head bolts; carbon-steel nuts; and flat, unhardened steel washers.
2. Finish: Plain, uncoated.
1. Heavy hex steel structural bolts, heavy hex carbon-steel nuts, ASTM A 563, Grade C,
and hardened carbon-steel washers, ASTM F 436 Type 1.
2. Direct-Tension Indicators: ASTM F 959, Type 325 compressible-washer type with plain
finish.
3. Finish: Plain, uncoated.
4. Tension-Control, High Strength Bolt-Nut-Washer Assemblies: ASTM 1852, Type 1,
Heavy Hex head assemblies consisting of steel structural bolts with splined ends, heavy-
hex carbon-steel nuts, and hardened carbon-steel washers.
2.3 PRIMER
1. Lead- and chromate-free, rust inhibiting primer compatible with field applied topcoat
indicated.
2. Where field applied topcoat is not indicated provide fabricators standard lead- and
chromate-free, rust inhibiting primer.
3. Do not use asphaltic primers or primers containing red oxide.
4. Color: Gray.
2.4 GROUT
A. General:
A. General:
1. Fabricate and assemble structural steel in shop to greatest extent possible. Fabricate
structural steel according to AISC specifications referenced in this Section and in Shop
Drawings.
B. Thermal Cutting:
C. Finishing:
1. Accurately mill ends of columns and other members transmitting loads in bearing.
D. Holes:
1. Provide holes required for securing other work to structural steel framing and for passage
of other work through steel framing members, as shown on Shop Drawings.
2. Cut, drill, or punch holes perpendicular to metal surfaces. Do not flame-cut holes or
enlarge holes by burning. Drill holes in bearing plates.
3. Weld threaded nuts to framing and other specialty items as indicated to receive other
work.
A. General:
1. Shop install and tighten non-high-strength bolts, except where high-strength bolts are
indicated.
2. Shop install and tighten high-strength bolts according to RCSC's "Specification for
Structural Joints Using ASTM A 325 or A 490 Bolts."
1. Comply with AWS D1.1 for procedures, appearance and quality of welds, and methods
used in correcting welding work.
2. Assemble and weld built-up sections by methods that will maintain true alignment of axes
without warp.
3. Verify that weld sizes, fabrication sequence, and equipment used for architecturally
exposed structural steel will limit distortions to allowable tolerances. Prevent surface
bleeding of back-side welding on exposed steel surfaces. Grind smooth exposed fillet
welds 1/2 inch and larger. Grind flush butt welds. Dress exposed welds.
C. Beam Connections:
1. Unless otherwise indicated, beam connections shall develop one-half of the maximum
shear capacity of the beam.
B. Surface Preparation:
1. Clean surfaces to be painted. Remove loose rust and mill scale and spatter, slag, or flux
deposits. Prepare surfaces according to SSPC-PS Guide 7.00, "Painting System
Guide 7.00: Guide for Selecting One-Coat Shop Painting Systems."
C. Primer Application:
1. Apply 1-coat primer in accordance with SSPC-PS Guide 7.00, "Painting System
Guide 7.00: Guide for Selecting One-Coat Shop Painting Systems," to provide a dry film
thickness of not less than 1.5 mils.
D. Painting:
1. Indicate protected zone by applying contrasting color on all surfaces of protected zone
excluding surfaces to be field welded. Stencil "Protected Zone - No cutting, welding,
attachments or modifications permitted" within the zone.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Before erection proceeds, and with the steel erector present, verify elevations of concrete and
masonry bearing surfaces and locations of anchorages for compliance with requirements. Do
not proceed with erection until unsatisfactory conditions have been corrected.
A. Provide temporary shores, guys, braces, and other supports during erection to keep structural
steel secure, plumb, and in alignment against temporary construction loads and loads equal in
intensity to design loads. Remove temporary supports when permanent structural steel,
connections, and bracing are in place, unless otherwise indicated.
3.3 ERECTION
A. General:
1. Set structural steel accurately in locations and to elevations indicated and according to
AISC specifications referenced in this Section.
1. Clean concrete and masonry bearing surfaces of bond-reducing materials and roughen
surfaces prior to setting base and bearing plates. Clean bottom surface of base and
bearing plates.
a. Set base and bearing plates for structural members on wedges, shims, or setting
nuts as required.
b. Tighten anchor bolts after supported members have been positioned and plumbed.
Do not remove wedges or shims but, if protruding, cut off flush with edge of base
or bearing plate prior to packing with grout.
c. Pack grout solidly between bearing surfaces and plates so no voids remain. Finish
exposed surfaces, protect installed materials, and allow to cure.
C. Erection Tolerances:
1. Maintain erection tolerances of structural steel within AISC's "Code of Standard Practice
for Steel Buildings and Bridges."
D. Alignment:
1. Align and adjust various members forming part of complete frame or structure before
permanently fastening. Before assembly, clean bearing surfaces and other surfaces that
will be in permanent contact. Perform necessary adjustments to compensate for
discrepancies in elevations and alignment.
2. Level and plumb individual members of structure.
3. Establish required leveling and plumbing measurements on mean operating temperature
of structure. Make allowances for difference between temperature at time of erection and
mean temperature at which structure will be when completed and in service.
E. Modifications:
A. General:
1. Install and tighten non-high-strength bolts, except where high-strength bolts are
indicated.
2. Install and tighten high-strength bolts according to RCSC's "Specification for Structural
Joints Using ASTM A 325 or A 490 Bolts."
B. Weld Connections:
1. Comply with AWS D1.1 for procedures, appearance and quality of welds, and methods
used in correcting welding work.
2. Comply with AISC specifications referenced in this Section for bearing, adequacy of
temporary connections, alignment, and removal of paint on surfaces adjacent to field
welds.
3. Assemble and weld built-up sections by methods that will maintain true alignment of axes
without warp.
4. Verify that weld sizes, fabrication sequence, and equipment used for architecturally
exposed structural steel will limit distortions to allowable tolerances. Prevent surface
bleeding of back-side welding on exposed steel surfaces. Grind smooth exposed fillet
welds 1/2 inch and larger. Grind flush butt welds. Dress exposed welds.
5. Remove backing bars or runoff tabs where indicated, back gouge, and grind steel
smooth.
6. Welds designated as demand critical shall be made with a filler metal capable of
providing a minimum Charpy V-Notch (CVN) toughness of 20 ft-lb at -20 deg F as
determined by AWS classification test or manufacturer certification and 40 ft-lb at 70 deg
F when the steel frame is normally enclosed and maintained above 49 deg F.
1. Field quality control shall be in accordance with the Quality Control Plan.
1. Engage a special Inspector to perform field inspections and tests and to prepare test
reports.
2. Testing agency will conduct and interpret tests and state in each report whether tested
Work complies with or deviates from requirements.
3. Correct deficiencies in or remove and replace structural steel that inspections and test
reports indicate do not comply with specified requirements.
4. Additional testing, at Contractor's expense, will be performed to determine compliance of
corrected Work with specified requirements.
5. Field-bolted connections will be tested and inspected according to RCSC's "Specification
for Structural Joints Using ASTM A 325 or A 490 Bolts."
a. Direct-tension indicator gaps will be verified to comply with ASTM F 959, Table 2.
7. In addition to visual inspection, shear connector stud welds will be tested and inspected
according to requirements in AWS D1.1 for stud welding and as follows:
3.6 CLEANING
A. Touchup Painting:
1. Immediately after erection, clean field welds, bolted connections, and abraded areas of
shop paint. Apply paint to exposed areas using same material as used for shop painting.
2. Apply by brush or spray to provide a minimum dry film thickness of 1.5 mils.
END OF SECTION
DESIGN CRITERIA
2. This Section specifies manufactured, open-web, K-series and KCS-type K-series steel joists, and
steel joist girders as defined by the Steel Joist Institute.
3. All steel joists shall be shop prime painted with a non-asphaltic primer. Do not allow the use of red
oxide primers, as this will prohibit the possibility of finish painting as part of the current project or at
some future date.
5. All steel joists exposed to the building exterior shall be hot-dipped galvanized before priming or shop
primed with an anti-corrosion primer that prevents or inhibits corrosion or rusting of steel.
6. In accordance with the IBC all projects are assigned to a Seismic Design Category. Where required
by project location, add applicable requirements of the IBC and referenced codes and standards.
7. Testing and Inspection: Although the IBC requires special inspections be performed by special
inspectors who are engaged by the Government or the design professional, this Section specifies the
Contractor shall perform these duties.
END OF SECTION
June 2011 05 21 00 1
SECTION 05 21 00
STEEL JOIST FRAMING
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of steel products.
1.2 SUBMITTALS
A. Product Data:
B. LEED Submittals:
1. Product Data for Credit MR 4: For products having recycled content, documentation
indicating percentages by weight of postconsumer and preconsumer recycled content.
Include statement indicating cost for each product having recycled content.
C. Shop Drawings:
1. Show layout, mark, number, type, location, and spacings of joists. Include joining and
anchorage details, bracing, bridging, accessories; splice and connection locations and
details; and attachments to other construction.
D. Mill Certificates:
1. Signed by manufacturers of bolts certifying that their products comply with specified
requirements.
1. Product Data:
G. Include statement indicating costs for each product having recycled content.
H. Submittal List:
A. Manufacturer Qualifications:
1. A firm experienced in manufacturing joists similar to those indicated for this Project and
with a record of successful in-service performance.
2. Manufacturer must be certified by SJI to manufacture joists complying with SJI standard
specifications and load tables.
B. SJI Specifications:
1. Comply with SJI's "Standard Specifications Load Tables and Weight Tables for Steel
Joists and Joist Girders" (hereafter, "Specifications"), applicable to types of joists
indicated.
1. Qualify procedures and personnel according to AWS D1.1, "Structural Welding Code-
Steel;" and AWS D1.3 "Structural Welding Code-Sheet Steel."
1. Special inspections for bolted and welded connections and steel details shall be
performed under the direct supervision of a Professional Engineer registered in the State
in which the project is located. The personnel performing the inspections shall be ICC-
certified Structural Steel and Welding Special Inspector or an equivalent certification
program.
A. Deliver, store, and handle joists as recommended in SJI's "Specifications." Protect joists from
corrosion, deformation, and other damage during delivery, storage, and handling.
1.5 SEQUENCING
A. Deliver steel bearing plates and other devices to be built into concrete and masonry
construction.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Steel:
1. ASTM A 307, Grade A, carbon-steel, hex-head bolts and threaded fasteners; carbon-
steel nuts; and flat, unhardened steel washers.
2. Finish: Plain, uncoated.
1. ASTM A 325, Type 1, heavy hex steel structural bolts, heavy hex carbon-steel nuts, and
hardened carbon-steel washers.
2. Finish: Plain, uncoated.
E. Welding Electrodes:
A. Primer:
1. Lead- and chromate-free, rust inhibiting primer compatible with field applied topcoat
indicated.
2. Where field applied topcoat is not indicated provide fabricators standard lead- and
chromate-free, rust inhibiting primer.
3. Do not use asphaltic primers or primers containing red oxide.
4. Color: Gray.
A. General:
1. Manufacture steel joists according to "Standard Specifications for Open Web Steel Joists,
K-Series," in SJI's "Specifications," with steel-angle top- and bottom-chord members,
underslung ends, and parallel top chord; of joist type indicated.
2. Joist Type: K-series steel joists and KCS-type K-series steel joists.
3. Comply with AWS requirements and procedures for shop welding, appearance, quality of
welds, and methods used in correcting welding work.
4. Provide holes in chord members for connecting and securing other construction to joists.
5. Top-Chord Extensions: Extend top chords of joists with SJI's Type S top-chord
extensions where indicated, complying with SJI's "Specifications."
6. Extended Ends: Extend bearing ends of joists with SJI's Type R extended ends where
indicated, complying with SJI's "Specifications."
7. Camber joists according to SJIs "Specifications."
8. Equip bearing ends of joists with manufacturer's standard beveled ends or sloped shoes
if joist slope exceeds 1/4 inch per 12 inches.
A. General:
A. General:
1. Manufacture joist girders according to "Standard Specifications for Joist Girders" in SJI's
"Specifications," with steel-angle top- and bottom-chord members; with end and top-
chord arrangements as indicated.
2. Comply with AWS requirements and procedures for shop welding, appearance, quality of
welds, and methods used in correcting welding work.
3. Provide holes in chord members for connecting and securing other construction to joist
girders.
4. Camber joist girders according to SJI's "Specifications."
5. Equip bearing ends of joists with manufacturer's standard beveled ends or sloped shoes
if joist slope exceeds 1/4 inch per 12 inches (1:48).
A. Bridging:
B. Bearing Plates:
1. Fabricate steel bearing plates with integral anchorages of sizes and thicknesses
indicated. Shop prime paint.
2. Steel bearing plates with integral anchorages are specified in Division 05 Section Metal
Fabrications.
C. Ceiling Extensions:
D. Miscellaneous Accessories:
1. Supply miscellaneous accessories, including splice plates and bolts required by joist
manufacturer to complete joist installation.
A. Cleaning:
1. Clean and remove loose scale, heavy rust, and other foreign materials from fabricated
joists and accessories to be primed by hand-tool cleaning, SSPC-SP 2 or power-tool
cleaning, SSPC-SP 3.
1. Clean surfaces to be painted. Remove loose rust and mill scale and spatter, slag, or flux
deposits. Prepare surfaces according to SSPC-PS Guide 7.00, "Painting System
Guide 7.00: Guide for Selecting One-Coat Shop Painting Systems."
C. Primer Application:
1. Apply 1-coat primer in accordance with SSPC-PS Guide 7.00, "Painting System
Guide 7.00: Guide for Selecting One-Coat Shop Painting Systems," to provide a dry film
thickness of not less than 1.5 mils.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine supporting substrates, embedded bearing plates, and abutting structural framing, with
Installer present, for compliance with requirements for installation tolerances and other
conditions affecting performance. Proceed with installation only after unsatisfactory conditions
have been corrected.
3.2 INSTALLATION
A. General:
a. Before installation, splice joists delivered to Project site in more than one piece.
b. Space, adjust, and align joists accurately in location before permanently fastening.
c. Install temporary bracing and erection bridging, connections, and anchors to
ensure that joists are stabilized during construction.
d. Delay rigidly connecting bottom-chord extensions to columns or supports until
dead loads have been applied.
3. Field weld joists to supporting steel bearing plates. Coordinate welding sequence and
procedure with placement of joists. Comply with AWS requirements and procedures for
welding, appearance and quality of welds, and methods used in correcting welding work.
4. Bolt joists to supporting steel framework using high-strength structural bolts, unless
otherwise indicated. Comply with RCSC's "Allowable Stress Design Specification for
Structural Joints Using ASTM A 325 or ASTM A 490 Bolts" for high-strength structural
bolt installation and tightening requirements.
5. Install and connect bridging concurrently with joist erection, before construction loads are
applied. Anchor ends of bridging lines at top and bottom chords if terminating at walls or
beams.
A. General:
1. Field quality control shall be in accordance with the Quality Control Plan.
2. Contractor shall engage a Special Inspector to inspect field welds and high-strength
bolted connections.
3. Field welds shall be visually inspected according to AWS D1.1
4. Bolted connections shall be visually inspected.
5. High-strength, field-bolted connections shall be tested and verified according to
procedures in RCSC's "Allowable Stress Design Specification for Structural Joints Using
ASTM A 325 or ASTM A 490 Bolts."
6. Correct deficiencies in Work that inspections and test reports have indicated are not in
compliance with specified requirements.
7. Additional testing shall be performed to determine compliance of corrected Work with
specified requirements.
A. Touchup Painting:
1. After installation, promptly clean, prepare, and prime or reprime field connections, rust
spots, and abraded surfaces of prime-painted joists and accessories, bearing plates and
abutting structural steel.
2. Clean and prepare surfaces by hand-tool cleaning, SSPC-SP 2, or power-tool cleaning,
SSPC-SP 3.
3. Apply a compatible primer of the same type as the shop primer used on adjacent
surfaces.
B. Protection:
END OF SECTION
DESIGN CRITERIA
2. This Section specifies steel floor deck classified as composite floor deck and steel roof deck.
3. All steel deck shall have hot-dip galvanized finish prepared for field painting.
5. Verify that Contract Documents do not graphically show or indicate anything suspended from steel
deck.
6. Locations of large roof mounted equipment (i.e., refrigeration mechanical centers, HVAC units, etc.)
need to be accurately shown on structural drawings, with allowable openings in steel roof deck
clearly identified. If actual deck opening sizes cannot be identified during design, the approximate
size and location along with criteria establishing maximum opening sizes and required reinforcing for
steel deck shall be noted on the structural drawings. This large roof mounted equipment typically
has numerous penetrations through the steel roof deck (for HVAC ductwork, pipes, conduits,
etc. that enter the building from the underside of these units) and ideally should be located
above the cold storage rooms, not above the sales area. This location will provide maximum
space for coordination of these items and keep it out of the view of customers. Leaks (roof or
condensation) are also less of a nuisance in these areas. This location will also minimize noise
transmission from the roof-mounted equipment into customer areas. Coordinate location of
equipment and placement of sound attenuation insulation (on top of the steel roof deck) directly
beneath the roof top equipment with Division 23 Design Criteria.
7. If the project requirements dictate a FM approved roof system, evaluate the metal deck fastening,
deck properties and fastener approvals as indicated by Factory Mutual Guidelines.
8. In accordance with the IBC all projects are assigned to a Seismic Design Category. Where required
by project location, add applicable requirements of the IBC and referenced codes and standards.
9. Testing and Inspection: Although the IBC requires special inspections be performed by special
inspectors who are engaged by the Government or the design professional, this Section specifies the
Contractor shall perform these duties.
10. The Guide specifications indicate decking is to be fastened by welding. Mechanical fastening may be
used if acceptable to the project A/E.
END OF SECTION
June 2011 05 30 00 1
SECTION 05 30 00
STEEL DECKING
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1. Roof deck.
2. Composite floor deck.
3. Noncomposite form deck.
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of steel products.
1.2 SUBMITTALS
A. Product Data:
B. LEED Submittals:
1. Product Data for Credit MR 4: For products having recycled content, documentation
indicating percentages by weight of postconsumer and preconsumer recycled content.
Include statement indicating cost for each product having recycled content.
C. Shop Drawings:
1. Show layout and types of deck panels, anchorage details, reinforcing channels, pans,
deck openings, special jointing, accessories, and attachments to other construction.
E. Welding certificates.
1. Product Data:
G. Submittal List:
A. Installer Qualifications:
1. An experienced installer who has completed steel deck similar in material, design, and
extent to that indicated for this Project and whose work has resulted in construction with a
record of successful in-service performance.
C. Special inspections for welding shall be performed under the direct supervision of a
Professional Engineer registered in the State in which the project is located. The personnel
performing the inspections shall be ICC-certified Structural Steel and Welding Special Inspector
or an equivalent certification program.
D. Welding:
1. Qualify procedures and personnel according to AWS D1.1, "Structural Welding Code-
Steel," and AWS D1.3, "Structural Welding Code-Sheet Steel."
E. AISI Specifications:
1. Calculate structural characteristics of steel deck according to AISI's "Specification for the
Design of Cold-Formed Steel Structural Members."
A. Protect steel deck from corrosion, deformation, and other damage during delivery, storage, and
handling. Stack steel deck on platforms or pallets and slope to provide drainage. Protect with a
waterproof covering and ventilate to avoid condensation.
1. Fabricate panels, without top-flange stiffening grooves, to comply with "SDI Specifications
and Commentary for Steel Roof Deck," in SDI Publication No31, and the following:
1. Fabricate panels, with integrally embossed or raised pattern ribs and interlocking side
laps, to comply with "SDI Specifications and Commentary for Composite Steel Floor
Deck," in SDI Publication No. 30, the minimum section properties indicated, and the
following:
2. Hot-Dipped Galvanized and Pretreated Steel Sheet: ASTM A 653/A 653M, Structural
Steel (SS), Grade 33, G60zinc coating; cleaned, and pretreated for field painting.
3. Profile Depth: 1-1/2 inches.
4. Design Uncoated-Steel Thickness: 0.0358 inch (20 gage).
5. Span Condition: Triple span or more.
A. General:
1. Provide manufacturer's standard accessory materials for deck that comply with
requirements indicated.
2. Mechanical Fasteners: Corrosion-resistant, low-velocity, power-actuated or
pneumatically driven carbon-steel fasteners; or self-drilling, self-threading screws.
3. Side-Lap Fasteners: Corrosion-resistant, hexagonal washer head; self-drilling, carbon-
steel screws, No. 10 minimum diameter.
4. Miscellaneous Sheet Metal Deck Accessories: Steel sheet, minimum yield strength of
33,000 psi, not less than 0.0359-inch design uncoated thickness, of same material and
finish as deck; of profile indicated or required for application.
5. Steel Sheet Accessories: Steel sheet, of same material, finish, and thickness as deck,
unless otherwise indicated.
6. Pour Stops and Girder Fillers: Steel sheet, minimum yield strength of 33,000 psi, of
same material and finish as deck, and of thickness and profile recommended by SDI
Publication No. 30 for overhang and slab depth.
7. Column Closures, End Closures, Z-Closures, and Cover Plates: Steel sheet, of same
material, finish, and thickness as deck, unless otherwise indicated.
8. Weld Washers: Uncoated steel sheet, shaped to fit deck rib, 0.0598 inch thick, with
factory-punched hole of 5/8-inch minimum diameter.
9. Roof Sump Receiver (Flat Sump Plate): Single-piece steel sheet, 0.0747 inch thick, of
same material and finish as deck. For drains, cut holes in the field. Exclude roof sump
receiver if specified with drains under work of Division 22.
10. Galvanizing Repair Paint: ASTM A 780.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine supporting frame and field conditions for compliance with requirements for installation
tolerances and other conditions affecting performance.
3.2 INSTALLATION
A. General:
1. Fasten roof deck panels to steel supporting members by arc spot (puddle) welds of the
surface diameter indicated or arc seam welds with an equal perimeter, but not less than
1-1/2 inches long, and as follows:
2. Side-Lap and Perimeter Edge Fastening: Fasten side laps and perimeter edges of
panels between supports, at intervals not exceeding the lesser of 1/2 of the span or 36
inches, and as follows:
3. End Bearing: Install deck ends over supporting frame with a minimum end bearing of 1-
1/2 inches, with end joints as follows:
4. Roof Plates: Install over openings provided in roof decking and weld flanges to top of
deck. Space welds not more than 12 inches apart with at least 1 weld at each corner.
5. Miscellaneous Roof Deck Accessories: Install ridge and valley plates, finish strips, cover
plates, end closures, and reinforcing channels according to deck manufacturer's written
instructions. Weld to substrate to provide a complete deck installation.
1. Fasten floor deck panels to steel supporting members by arc spot (puddle) welds of the
surface diameter indicated and as follows:
2. Side-Lap and Perimeter Edge Fastening: Fasten side laps and perimeter edges of
panels between supports, and as follows:
3. End Bearing: Install deck ends over supporting frame with a minimum end bearing of 1-
1/2 inches, with end joints as follows:
4. Shear Connectors: Weld shear connectors through deck to supporting frame according
to AWS D1.1 and manufacturer's written instructions. Butt end joints of deck panels; do
not overlap. Remove and discard arc shields after welding shear connectors.
A. General:
1. Field quality control shall be in accordance with the Quality Control Plan.
2. Contractor shall engage a Special Inspector to inspect field welds and all deck
connections.
3. Field welds shall be subject to inspection.
a. In addition to visual inspection, shear connector stud welds shall be tested and
inspected according to requirements in AWS D1.1 for stud welding and as follows:
4. Special Inspector shall report test results promptly and in writing to Contractor and
Contracting Officer.
5. Remove and replace work that does not comply with specified requirements.
6. Additional testing and inspecting, at Contractor's expense, shall be performed to
determine compliance of corrected work with specified requirements.
A. Galvanizing Repairs:
1. Prepare and repair damaged galvanized coatings on both surfaces of deck with
galvanized repair paint according to ASTM A 780 and manufacturer's written instructions.
B. Protection:
1. Provide final protection and maintain conditions to ensure that steel deck is without
damage or deterioration at time of final acceptance.
END OF SECTION
DESIGN CRITERIA
2. This Section specifies cold-formed steel framing including exterior and interior load-bearing and
exterior non-load-bearing wall studs; floor joists; roof rafters and ceiling joists.
4. Consideration should be given to structural supports to resist wind uplift on exterior suspended soffit
systems.
5. In accordance with the IBC all projects are assigned to a Seismic Design Category. Where required
by project location, add applicable requirements of the IBC and referenced codes and standards.
6. Testing and Inspection: Although the IBC requires special inspections be performed by special
inspectors who are engaged by the Government or the design professional, this Section specifies the
Contractor shall perform these duties.
END OF SECTION
June 2011 05 40 00 1
SECTION 05 40 00
COLD-FORMED METAL FRAMING
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1. Wall framing.
2. Roof rafter framing.
3. Ceiling joist framing.
4. Metal supports for exterior soffits.
5. Z-furring for exterior of walls.
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of steel products.
2. Division 09 Section Portland Cement Plaster for metal furring that support lath and
portland cement plaster.
3. Division 09 Section Gypsum Board for interior non-load-bearing, metal-stud framing and
ceiling-suspension assemblies.
1.2 DEFINITIONS
A. Producer:
1. Entity that produces steel sheet coil fabricated into cold-formed members.
3. Design framing systems to provide for movement of framing members without damage or
overstressing, sheathing failure, connection failure, undue strain on fasteners and
anchors, or other detrimental effects when subject to a maximum ambient temperature
change of 120 deg F.
B. Cold-Formed Steel Framing, General: Design according to AISI's "Standard for Cold-Formed
Steel Framing - General Provisions."
1. Headers: Design according to AISI's "Standard for Cold-Formed Steel Framing - Header
Design."
1. Minimum uncoated thickness of cold-formed framing delivered to the Project site shall be
not less than 95 percent of the thickness used in the cold-formed framing design. Lesser
thicknesses shall be permitted at bends due to cold forming.
1.4 SUBMITTALS
A. Product Data:
1. For each type of cold-formed metal framing product and accessory indicated.
B. LEED Submittal:
1. Product Data for Credit MR 4.1[ and Credit MR 4.2]: For products having recycled
content, documentation indicating percentages by weight of postconsumer and
preconsumer recycled content.
a. Include statement indicating costs for each product having recycled content.
C. Welding Certificates.
D. Special Inspection reports on shop and field bolted connections, and welded connections.
1. Product Data:
1) Include statement indicating costs for each product having recycled content.
F. Submittal List:
A. Installer Qualifications:
B. Welding:
1. Qualify procedures and personnel according to AWS D1.1, "Structural Welding Code--
Steel," and AWS D1.3, "Structural Welding Code--Sheet Steel."
C. AISI Specifications:
1. Comply with AISI's "Specification for the Design of Cold-Formed Steel Structural
Members" for calculating structural characteristics of cold-formed metal framing.
1. Special Inspections, for bolted and welded connections, and steel details shall be
performed under the direct supervision of a Professional Engineer registered in the State
in which the project is located. The personnel performing the inspections shall be ICC-
certified Structural Steel and Welding Special Inspection or an equivalent certification
program.
A. Protect cold-formed metal framing from corrosion, deformation, and other damage during
delivery, storage, and handling. Store cold-formed metal framing, protect with a waterproof
covering, and ventilate to avoid condensation.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Steel Sheet:
1. ASTM A 1003, structural steel, Type H, metallic coated, of grade and coating as follows:
a. Grade: ST33H for minimum uncoated steel thickness of 0.0428 inch (SSMA
designation 43, nominal 18 gage) and less; ST50H for minimum uncoated steel
thickness of 0.0538 inch (SSMA designation 54, nominal 16 gage) and greater.
b. Coating: G60, hot-dip galvanized, unless otherwise indicated.
c. Coating: G90, hot-dip galvanized for exterior masonry backup framing, unless
otherwise indicated.
A. Channels:
1. Cold-rolled steel, minimum 0.0598-inch- thick base (uncoated) metal, and as follows:
a. Carrying Channels: 1-1/2 inches deep, 475 lb/1000 feet and minimum 7/16-inch-
wide flanges.
b. Channel Hangers: 3/4 inch deep, 300 lb/1000 feet and minimum 7/16-inch- wide
flanges.
A. Steel Studs:
1. Manufacturer's standard C-shaped steel studs, of web depths indicated, punched, with
stiffened flanges, complying with ASTM A 1003, and as follows:
A. Steel Rafters:
2.6 Z-FURRING
A. Z-Shaped Furring:
1. With nonslotted web, face flange of 1-1/4 inches, wall attachment flange of 7/8 inch,
minimum bare metal thickness of 0.0179 inch, and depth required to fit insulation
thickness indicated.
A. General:
1. Fabricate steel-framing accessories of the same material and finish used for framing
members, with a minimum yield strength of 33,000 psi.
2. Provide accessories of manufacturer's standard thickness and configuration, unless
otherwise indicated, as follows:
a. Supplementary framing.
b. Bracing, bridging, and solid blocking.
c. Web stiffeners.
d. End clips.
e. Foundation clips.
f. Gusset plates.
g. Stud kickers, knee braces, and girts.
h. Hole reinforcing plates.
i. Backer plates.
1. ASTM A 36/A 36M, zinc coated by hot-dip process according to ASTM A 123.
B. Power-Actuated Anchors:
1. Fastener system of type suitable for application indicated, fabricated from corrosion-
resistant materials, with capability to sustain, without failure, a load equal to 10 times
C. Mechanical Fasteners:
D. Welding Electrodes:
1. SSPC-Paint 20 or DOD-P-21035.
2.10 FABRICATION
A. Fabricate cold-formed metal framing and accessories plumb, square, and true to line, and with
connections securely fastened, according to manufacturer's written recommendations and
requirements in this Section.
a. Comply with AWS D1.3 requirements and procedures for welding, appearance and
quality of welds, and methods used in correcting welding work.
b. Locate mechanical fasteners and install with screws penetrating joined members
by not less than three exposed screw threads.
c. Fasten other materials to cold-formed metal framing by welding, bolting, or screw
fastening.
4. Reinforce, stiffen, and brace framing assemblies to withstand handling, delivery, and
erection stresses. Lift fabricated assemblies to prevent damage or permanent distortion.
5. Fabrication Tolerances: Fabricate assemblies level, plumb, and true to line to a
maximum allowable tolerance variation of 1/8 inch in 10 feet and as follows:
a. Spacing: Space individual framing members no more than plus or minus 1/8 inch
from plan location. Cumulative error shall not exceed minimum fastening
requirements of sheathing or other finishing materials.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine supporting substrates and abutting structural framing for compliance with requirements
for installation tolerances and other conditions affecting performance. Proceed with installation
only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Grout bearing surfaces uniform and level to ensure full contact of bearing flanges or track webs
on supporting concrete or masonry construction.
3.3 INSTALLATION
A. General:
1. Cold-formed metal framing may be shop or field fabricated for installation, or it may be
field assembled.
2. Install cold-formed metal framing according to ASTM C 1007, unless more stringent
requirements are indicated.
3. Install shop- or field-fabricated, cold-formed framing and securely anchor to supporting
structure.
a. Bolt or weld wall panels at horizontal and vertical junctures to produce flush, even,
true-to-line joints with maximum variation in plane and true position between
fabricated panels not exceeding 1/16 inch.
4. Install cold-formed metal framing and accessories plumb, square, and true to line, and
with connections securely fastened, according to manufacturer's written
recommendations and requirements in this Section.
5. Install framing members in one-piece lengths, unless splice connections are indicated for
track or tension members.
6. Install temporary bracing and supports to secure framing and support loads comparable
in intensity to those for which structure was designed. Maintain braces and supports in
a. Space individual framing members no more than plus or minus 1/8 inch from plan
location. Cumulative error shall not exceed minimum fastening requirements of
sheathing or other finishing materials.
3. Install hangers and members supported by hangers at spacings indicated, but not greater
than that required by the following:
a. Hangers: Space hangers not over 36 inches o.c., parallel with and not over 36
inches perpendicular to direction of carrying channels, unless otherwise indicated,
and within 6 inches of carrying channel ends.
b. Carrying Channels: Space carrying channels not over 36 inches o.c.
1. Install continuous tracks sized to match studs. Align tracks accurately and securely
anchor to supporting structure. Space studs as indicated; set plumb, align, and fasten
both flanges of studs to track, unless otherwise indicated.
b. Install single-leg deflection tracks and anchor to building structure. Do not fasten
studs to deflection track.
c. Install horizontal bridging in studs, spaced in rows not more than 54 inches apart.
Fasten at each stud intersection.
d. Install miscellaneous framing and connections, including stud kickers, web
stiffeners, clip angles, continuous angles, anchors, fasteners, and stud girts, to
provide a complete and stable wall-framing system.
1. Install perimeter joist track sized to match joists. Align and securely anchor or fasten
track to supporting structure at corners, ends, and spacings indicated on Shop Drawings.
2. Install joists bearing on supporting frame, level, straight, and plumb; adjust to final
position, brace, and reinforce. Fasten joists to both flanges of joist track.
a. Install joists over supporting frame with a minimum end bearing of 1-1/2 inches.
b. Reinforce ends and bearing points of joists with web stiffeners, end clips, joist
hangers, steel clip angles, or steel-stud sections as indicated on Shop Drawings.
3. Space joists not more than 2 inches from abutting walls, and as follows:
4. Frame openings with built-up joist headers consisting of joist and joist track, nesting
joists, or another combination of connected joists if indicated.
5. Install bridging at each end of joists and at intervals not exceeding 4 feet. Fasten
bridging at each joist intersection in accordance with one of the following:
6. Install miscellaneous joist framing and connections, including web stiffeners, closure
pieces, clip angles, continuous angles, hold-down angles, anchors, and fasteners, to
provide a complete and stable joist-framing assembly.
E. Z-Furring:
1. Erect insulation vertically and hold in place with Z-furring members spaced 24 inches o.c.
2. Except at exterior corners, securely attach narrow flanges of furring members to wall with
concrete stub nails, screws designed for masonry attachment, or powder-driven fasteners
spaced 24 inches o.c.
3. At exterior corners, attach wide flange of furring members to wall with short flange
extending beyond corner; on adjacent wall surface, screw-attach short flange of furring
channel to web of attached channel. At interior corners, space second member no more
than 12 inches from corner and cut insulation to fit.
A. Galvanizing Repairs:
1. Prepare and repair damaged galvanized coatings on fabricated and installed cold-formed
metal framing with galvanized repair paint according to ASTM A 780 and manufacturer's
written instructions.
1. Field quality control shall be in accordance with the Quality Control Plan.
1. Engage a special Inspector to perform field inspections and tests and to prepare test
reports.
2. Field and shop welds will be subject to testing and inspecting.
3. Testing agency will report test results promptly and in writing to Contractor and
Contracting Officer.
4. Remove and replace work where test results indicate that it does not comply with
specified requirements.
5. Additional testing and inspecting, at Contractor's expense, will be performed to determine
compliance of replaced or additional work with specified requirements.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 05 and Division 08 Design Criteria, and related Design Standard
Plates.
2. Metal fabrications are used for numerous applications in commissary construction, including steel
framing for support of operable partitions, mechanical and electrical equipment, and miscellaneous
steel trim such as wall mounted steel angle corner guards, dock leveler pit frames, and loading dock
edge angles. Metal fabrications considered operational necessities in commissary facilities, include
the following:
A. Structural Steel Door Frames: Provide at overhead receiving doors and interior traffic doors (in
CMU walls) between the sales area and warehouse area. Traffic doors are subject to heavy use
and the traffic door manufacturer recommends the use of structural steel door frames. Traffic
doors installed in gypsum wallboard partitions facing Sales Area shall have 14 gage flush
galvanized steel security frames, with 1/4" steel reinforcement plates at hardware attachment
locations. Refer to Division 08 Section Hollow Metal Doors and Frames for further information.
C. Metal Ships Ladders: Provide at roof access hatch location in existing stores for replacement
only. Ships ladder shall be at an angle of 50 to 60 degrees, width shall be 24", and stair tread
depth shall not be less than 6".
D. Metal Bollards (Bumper Posts): Provide 8" diameter concrete filled steel bumper posts at jambs
of all receiving doors to protect door tracks. Provide 4" diameter concrete filled steel bumper
posts at jambs of all traffic doors between the sales area and warehouse area (not exposed to
sales area). Provide 8" diameter concrete filled steel bumper posts at exterior locations to protect
jambs of grade level receiving doors, leading edges of guardrails and handrails, corners of
receiving platforms and ramps, and grade/pad mounted mechanical and electrical equipment.
Provide polyethylene thermoplastic sleeves over interior bumper posts (located in non-customer
areas). Coordinate with Installation Design Guideline (IDG) or other Installation criteria controlling
exterior architectural design for required appearance of exterior bumper posts. Default color shall
be safety yellow.
E. Safety Chains: Provide across mezzanine door openings providing forklift access to mezzanine
storage or mechanical spaces.
F. Metal Column Covers: Provide 6'-0" high stainless steel covers on all exposed columns within
customer areas, including those located within gondola shelving.
G. Stainless Steel Wall Panel: Provide quilted stainless steel wall panel in Deli, directly behind
counter mounted chicken rotisserie, from top of counter or stainless steel table to underside of
ceiling. Nominal size: 60" wide by 84" high.
H. Testing and Inspection: Although the IBC requires special inspections be performed by special
inspectors who are engaged by the Government or the design professional, this Section specifies
the Contractor shall perform these duties.
END OF SECTION
June 2011 05 50 13 1
SECTION 05 50 13
METAL FABRICATIONS
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Products furnished, but not installed, under this Section include the following:
C. Related Sections:
A. Thermal Movements:
a. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces.
B. Delegated Design:
1. Provide ladders (including ships ladders, if any) capable of withstanding the effects of
loads and stresses within limits and under conditions specified in ANSI A14.3.
1.3 SUBMITTALS
A. Shop Drawings:
a. Include plans, elevations, sections, and details of metal fabrications and their
connections. Show anchorage and accessory items.
b. Provide templates for anchors and bolts specified for installation under other
Sections.
B. Samples:
C. Welding Certificates.
D. Special Inspection reports on shop and field bolted connections, and welded connections.
E. Product Data:
F. Delegated-Design Submittal:
1. For installed products indicated to comply with performance requirements and design
criteria, including analysis data signed and sealed by the qualified professional engineer
responsible for their preparation.
1. Product Data:
I. Submittal List:
A. Welding:
1. Qualify procedures and personnel according to AWS D1.1, "Structural Welding Code--
Steel."
1. Special Inspections for bolted and welded connections and steel details shall be
performed under the direct supervision of a Professional Engineer registered in the State
in which the project is located. The personnel performing the inspections shall be ICC-
certified Structural Steel and Welding Special Inspection or an equivalent certification
program.
A. Field Measurements:
1. Verify actual locations of walls and other construction contiguous with metal fabrications
by field measurements before fabrication and indicate measurements on Shop Drawings.
1.6 COORDINATION
PART 2 - PRODUCTS
A. Metal Surfaces:
1. Provide materials with smooth, flat surfaces, unless otherwise indicated. For metal
fabrications exposed to view in the completed Work, provide materials without seam
marks, roller marks, rolled trade names, or blemishes.
A. Recycled Content of Steel Products: Provide products with average recycled content of steel
products so postconsumer recycled content plus one-half of preconsumer recycled content is
not less than [25] <Insert number> percent. Steel Plates, Shapes, and Bars
ASTM A 36/A 36M.
C. Stainless-Steel Sheet, Strip, and Plate: ASTM A 240/A 240M or ASTM A 666.
2.3 FASTENERS
A. General:
1. Unless otherwise indicated, provide Type 304 stainless-steel fasteners for exterior use
and zinc-plated fasteners with coating complying with ASTM B 633, Class Fe/Zn 5, at
exterior walls. Provide stainless-steel fasteners for fastening aluminum. Select fasteners
for type, grade, and class required.
B. Shop Primers:
D. Zinc-Rich Primer:
F. Bituminous Paint:
A. Shop Assembly:
1. Preassemble items in the shop to greatest extent possible. Disassemble units only as
necessary for shipping and handling limitations. Use connections that maintain structural
value of joined pieces. Clearly mark units for reassembly and coordinated installation.
2. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a
radius of approximately 1/32 inch, unless otherwise indicated. Remove sharp or rough
areas on exposed surfaces.
3. Form bent-metal corners to smallest radius possible without causing grain separation or
otherwise impairing work.
4. Form exposed work true to line and level with accurate angles and surfaces and straight
edges.
5. Weld corners and seams continuously to comply with the following:
a. Use materials and methods that minimize distortion and develop strength and
corrosion resistance of base metals.
6. Form exposed connections with hairline joints, flush and smooth, using concealed
fasteners where possible. Where exposed fasteners are required, use Phillips flat-head
(countersunk) screws or bolts, unless otherwise indicated. Locate joints where least
conspicuous.
7. Fabricate seams and other connections that will be exposed to weather in a manner to
exclude water. Provide weep holes where water may accumulate.
8. Cut, reinforce, drill, and tap metal fabrications as indicated to receive finish hardware,
screws, and similar items.
9. Provide for anchorage of type indicated; coordinate with supporting structure. Space
anchoring devices to secure metal fabrications rigidly in place and to support indicated
loads.
a. Where units are indicated to be cast into concrete or built into masonry, equip with
integrally welded steel strap anchors, 1/8 by 1-1/2 inches, with a minimum 6-inch
embedment and 2-inch hook, not less than 8 inches from ends and corners of units
and 24 inches o.c., unless otherwise indicated.
A. General:
1. Provide steel framing and supports not specified in other Sections as needed to complete
the Work.
2. Fabricate units from steel shapes, plates, and bars of welded construction, unless
otherwise indicated. Fabricate to sizes, shapes, and profiles indicated and as necessary
to receive adjacent construction retained by framing and supports. Cut, drill, and tap
units to receive hardware, hangers, and similar items.
3. Furnish inserts if units are installed after concrete is placed.
4. Galvanize miscellaneous framing and supports where indicated.
1. Fabricate supports for operable partitions from continuous steel members of sizes
indicated with attached bearing plates, anchors, and braces as indicated. Drill bottom
flanges of beams to receive partition track hanger rods; locate holes where indicated on
operable partition Shop Drawings.
2. Unless otherwise indicated, provide supplementary supports for operable partitions as
follows:
A. Fabrication:
1. Fabricate loose steel lintels from steel angles and shapes of size indicated for openings
and recesses in masonry walls and partitions at locations indicated. Weld adjoining
members together to form a single unit where indicated.
2. Size loose lintels to provide bearing length at each side of openings equal to 1/12 of clear
span but not less than 8 inches, unless otherwise indicated.
3. Galvanize loose steel lintels located in exterior walls.
A. Fabrication:
1. Fabricate shelf angles from steel angles of sizes indicated and for attachment to concrete
framing. Provide horizontally slotted holes to receive 3/4-inch bolts, spaced not more
than 6 inches from ends and 24 inches o.c., unless otherwise indicated.
2. Provide mitered and welded units at corners.
3. Provide open joints in shelf angles at expansion and control joints. Make open joint
approximately 2 inches larger than expansion or control joint.
4. Galvanize shelf angles located in exterior walls.
A. Provide loose bearing and leveling plates for steel items bearing on masonry or concrete
construction. Drill plates to receive anchor bolts and for grouting. Prime plates with zinc-rich
primer.
A. Provide steel weld plates and angles not specified in other Sections, for items supported from
concrete construction as needed to complete the Work. Provide each unit with not less than
two integrally welded steel strap anchors for embedding in concrete.
A. Fabrication, General:
1. Fabricate structural-steel door frames from steel shapes, plates, and bars of size and to
dimensions indicated, fully welded together unless otherwise indicated. Plug-weld built-
up members and continuously weld exposed joints. Reinforce frames and drill and tap as
necessary to accept finish hardware.
2. Provide with integrally welded steel strap anchors for securing door frames into adjoining
concrete or masonry.
3. Unless otherwise indicated provide anchors 1/8 thick by 2 inches wide, with a minimum
6-inch embedment and 2-inch hook for securing door frames into adjoining concrete or
masonry. Weld anchors to frame jambs no more than 12 inches from both bottom and
head of frame, and space anchors not more than 30 inches apart.
1. Structural steel jambs and head of sizes and shapes as indicated; provide steel plates
where indicated on overhead door Shop Drawings for support of tracks, counterbalance
system, and operators.
D. Finish:
A. General:
1. Unless otherwise indicated, fabricate units from steel shapes, plates, and bars of profiles
shown with continuously welded joints and smooth exposed edges. Miter corners and
use concealed field splices where possible.
B. Fabrication:
E. Finish:
A. General:
B. Steel Ladders:
1. Siderails: Continuous, 3/8-by-2-1/2-inch steel flat bars, with eased edges, unless
otherwise indicated.
2. Rungs: 3/4-inch- diameter steel bars, unless otherwise indicated.
3. Fit rungs in centerline of siderails; plug-weld and grind smooth on outer rail faces.
4. Provide nonslip surfaces on top of each rung, either by coating rung with aluminum-oxide
granules set in epoxy-resin adhesive or by using a type of manufactured rung filled with
aluminum-oxide grout.
5. Galvanize exterior ladders and interior ladders, where indicated, including brackets and
fasteners.
6. Prime interior ladders, including brackets and fasteners.
C. Aluminum Ladders:
1. Provide metal ships' ladders where indicated. Fabricate of open-type construction with
channel or plate stringers, pipe and tube railings, and bar grating treads, unless
otherwise indicated. Provide brackets and fittings for installation.
2. Fabricate ships' ladders, including treads and railings from steel.
3. Comply with applicable requirements in Division 05 Sections Metal Stairs and Pipe
Railings.
4. Prime steel ships' ladders, including treads, railings, brackets, and fasteners.
A. Fabrication:
1. Basis-of-Design Product: Ideal Shield, Standard Bumper Post Sleeve, 2525 Clark Street,
Detroit, MI 48209-1355. Telephone: (877)323-0769.
2. Low-density polyethylene thermoplastic (LDPE) tubes having ultra-violet resistance and
anti static properties, nominal thickness 0.250 inch. OSHA yellow color unless otherwise
indicated.
A. Stainless Steel: 20 gage, Type 304 stainless steel sheet metal with #4 finish.
A. Chain:
1. Galvanized wrought iron, straight link style, 3/16-inch diameter, minimum 12 links per foot
and with boat type snap hooks on each end.
1. Galvanized 3/8-inch diameter bolts with 3/4-inch eye, anchored to frame opening.
C. Installation:
A. 18 gage (0.0500 inch) thick, Type 304 stainless steel with #4 finish, 4-inch by 4-inch quilted
pattern. Perimeter edges of panel shall be turned-in against wall with 15 degree break, to
increase rigidity of panel and provide tight fit against wall. Secure to ceramic wall tile with
construction adhesive.
A. Metal Finishes
1. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
2. Finish metal fabrications after assembly.
A. Galvanizing:
1. Hot-dip galvanize items as indicated to comply with applicable standard listed below:
2. ASTM A 123/A 123M, for galvanizing steel and iron products.
3. ASTM A 153/A 153M, for galvanizing steel and iron hardware.
C. Shop Priming:
1. Apply shop primer to uncoated surfaces of ferrous-metal fabrications, except those with
galvanized finishes and those to be embedded in concrete, sprayed-on fireproofing, or
masonry, unless otherwise indicated. Comply with SSPC-PA 1, "Paint Application
Specification No. 1: Shop, Field, and Maintenance Painting of Steel," for shop painting.
2. Stripe paint corners, crevices, bolts, welds, and sharp edges.
A. General:
1. Provide stainless steel free from surface blemishes where exposed to view in the finished
unit. Exposed-to-view surfaces exhibiting pitting, seam marks, roller marks, stains,
discolorations, or other imperfections on finished units are not acceptable.
2. Remove tool and die marks and stretch lines or blend into finish.
3. Grind and polish surfaces to produce uniform, directionally textured, polished finish
indicated, free of cross scratches. Run grain with long dimension of each piece.
B. Finish:
PART 3 - EXECUTION
3.1 INSTALLATION
A. General:
1. Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required for installing
metal fabrications. Set metal fabrications accurately in location, alignment, and elevation;
with edges and surfaces level, plumb, true, and free of rack; and measured from
established lines and levels.
2. Fit exposed connections accurately together to form hairline joints. Weld connections
that are not to be left as exposed joints but cannot be shop welded because of shipping
size limitations. Do not weld, cut, or abrade surfaces of exterior units that have been hot-
dip galvanized after fabrication and are for bolted or screwed field connections.
B. Field Welding:
1. Provide anchorage devices and fasteners where metal fabrications are required to be
fastened to in-place construction. Provide threaded fasteners for use with concrete and
masonry inserts, toggle bolts, through bolts, lag bolts, wood screws, and other
connectors.
D. Built-In Construction:
1. Provide temporary bracing or anchors in formwork for items that are to be built into
concrete, masonry, or similar construction.
A. General:
1. Install framing and supports to comply with requirements of items being supported,
including manufacturers' written instructions and requirements indicated on Shop
Drawings.
2. Anchor supports for operable partitions securely to and rigidly brace from building
structure.
A. Preparation:
1. Clean concrete and masonry bearing surfaces of bond-reducing materials, and roughen
to improve bond to surfaces. Clean bottom surface of plates.
B. Setting:
1. Set bearing and leveling plates on wedges, shims, or leveling nuts. After bearing
members have been positioned and plumbed, tighten anchor bolts. Do not remove
wedges or shims but, if protruding, cut off flush with edge of bearing plate before packing
with grout. Pack grout solidly between bearing surfaces and plates to ensure that no
voids remain.
A. Concrete Embedment:
1. Anchor bollards in place with concrete footings. Center bollards in holes and set bottom
end of bollard 3 inches above bottom of excavation. Place concrete and vibrate or tamp
for consolidation. Support and brace bollards in position until concrete has cured. Slope
concrete up approximately 1/8 inch toward bollard.
B. Pipe Fill:
1. Fill bollards solidly with concrete, mounding top surface to shed water.
A. Location:
1. Install bumper post sleeves over interior pipe bollards (bumper posts) located in non-
customer areas and where indicated on Drawings.
2. Secure sleeve to pipe with manufacturers neoprene adhesive tape in accordance with
manufacturers installation guidelines. Do not use screws, glue, or clamps.
A. General:
1. Field quality control shall be in accordance with the Quality Control Plan.
1. Engage a special Inspector to perform field inspections and tests and to prepare test
reports.
2. Field and shop welds will be subject to testing and inspecting.
3. Testing agency will report test results promptly and in writing to Contractor and
Contracting Officer.
4. Remove and replace work where test results indicate that it does not comply with
specified requirements.
5. Additional testing and inspecting, at Contractor's expense, will be performed to determine
compliance of replaced or additional work with specified requirements.
A. Touchup Painting:
1. Immediately after erection, clean field welds, bolted connections, and abraded areas.
Paint uncoated and abraded areas with the same material as used for shop painting to
comply with SSPC-PA 1 for touching up shop-painted surfaces. Apply by brush or spray
to provide a minimum 2 mil dry film thickness.
B. Galvanized Surfaces:
1. Clean field welds, bolted connections, and abraded areas and repair galvanizing to
comply with ASTM A 780.
END OF SECTION
DESIGN CRITERIA
2. This Section specifies straight-run, steel-framed industrial stairs with steel floor plate treads, risers,
and landings. Stairs are typically provided for interior access to non-customer areas such as
mechanical equipment mezzanines and roof access stair towers. The guide specification indicates
shop primed steel that will require field painting. Clearly identify on the Contract Drawings required
dimensional layout and section of stairs, including requirement for field painting.
3. If conditions require exterior steel stairs, specify and detail hot-dipped galvanized steel bar grating
construction.
4. If conditions require interior steel stairs to administration and customer accessible mezzanine or
second floor spaces, specify and detail painted concrete filled steel pan construction.
5. In accordance with the IBC all projects are assigned to a Seismic Design Category. Where required
by project location, add applicable requirements of the IBC and referenced codes and standards.
6. Testing and Inspection: Although the IBC requires special inspections be performed by special
inspectors who are engaged by the Government or the design professional, this Section specifies the
Contractor shall perform these duties.
END OF SECTION
June 2011 05 51 00 1
SECTION 05 51 00
METAL STAIRS
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1. Industrial-type stairs and landings with steel floor plate treads, unless otherwise
indicated.
2. Industrial-type landing with steel grating, where indicated.
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of steel products.
2. Division 05 Section Pipe Railings for pipe railings.
1. Provide metal stairs capable of withstanding the effects of gravity loads and the following
loads and stresses within limits and under conditions indicated:
B. Seismic Performance:
A. LEED Submittals:
1. Product Data for Credit MR 4.1[ and Credit MR 4.2]: Indicating percentages by weight of
postconsumer and preconsumer recycled content for products having recycled content.
Include statement indicating costs for each product having recycled content.
B. Shop Drawings:
a. For installed products indicated to comply with design loads, include structural
analysis data signed and sealed by the qualified professional engineer responsible
for their preparation.
C. Welding Certificates.
D. Special Inspection reports on shop and field bolted connections, and welded connections.
E. Delegated-Design Submittal:
1. For installed products indicated to comply with performance requirements and design
criteria, including analysis data signed and sealed by the qualified professional engineer
responsible for their preparation.
1. Product Data:
G. Submittal List:
A. Installer Qualifications:
1. Fabricator of products.
1. Comply with "Recommended Voluntary Minimum Standards for Fixed Metal Stairs" in
NAAMM AMP 510, "Metal Stairs Manual," for class of stair designated, unless more
stringent requirements are indicated.
C. Welding:
1. Special Inspections for bolted and welded connections and steel details shall be
performed under the direct supervision of a Professional Engineer registered in the State
in which the project is located. The personnel performing the inspections shall be ICC-
certified Structural Steel and Welding Special Inspection or an equivalent certification
program.
1.5 COORDINATION
A. Coordinate installation of anchorages for metal stairs. Furnish setting Drawings, templates, and
directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items
with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to
Project site in time for installation.
PART 2 - PRODUCTS
A. Metal Surfaces, General: Provide materials with smooth, flat surfaces, unless otherwise
indicated. For components exposed to view in the completed Work, provide materials without
seam marks, roller marks, rolled trade names, or blemishes.
1. Rolled from plate complying with ASTM A 36/A 36M or ASTM A 283/A 283M, Grade C or
D.
1. Either commercial steel, Type B, or structural steel, Grade 30, unless another grade is
required by design loads.
2.3 FASTENERS
B. Shop Primer:
A. Provide complete stair assemblies, including metal framing, hangers, struts, clips, brackets,
bearing plates, and other components necessary to support and anchor stairs and platforms on
supporting structure.
D. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius
of approximately 1/32 inch, unless otherwise indicated. Remove sharp or rough areas on
exposed surfaces.
E. Form bent-metal corners to smallest radius possible without causing grain separation or
otherwise impairing work.
F. Form exposed work true to line and level with accurate angles and surfaces and straight edges.
1. Use materials and methods that minimize distortion and develop strength and corrosion
resistance of base metals.
2. Obtain fusion without undercut or overlap.
3. Remove welding flux immediately.
4. Weld exposed corners and seams continuously, unless otherwise indicated.
5. At exposed connections, finish exposed welds and surfaces smooth and blended so no
roughness shows after finishing and contour of welded surface matches that of adjacent
surface.
H. Form exposed connections with hairline joints, flush and smooth, using concealed fasteners
where possible. Where exposed fasteners are required, use Phillips flat-head (countersunk)
screws or bolts unless otherwise indicated. Locate joints where least conspicuous.
A. Stair Framing:
1. Form treads and platforms to configurations shown from raised-pattern rolled-steel floor
plate of thickness needed to comply with performance requirements but not less than 1/4
inch (of flat plate, exclusive of height of the raised pattern).
2. Form treads with integral nosing and back edge stiffener. Form risers from steel sheet
not less than 0.0966 inch thick, welded to tread nosings, to stiffeners, and to platforms.
3. Weld steel supporting brackets to stringers and weld treads to brackets.
4. Fabricate platforms with integral nosings matching treads and weld to platform framing.
1. Where Indicated: Form platforms to configurations shown from metal bar grating;
fabricate to comply with NAAMM MBG 531, "Metal Bar Grating Manual."
2. Platforms: Provide patterns, spacing, and bar sizes in accordance with performance
requirements; fabricate to comply with NAAMM MBG 531 "Metal Bar Grating Manual."
a. Fabricate platforms from welded steel grating with openings in gratings no more
than 3/4 inch in least dimension.
b. Surface: Serrated.
c. Finish: Shop primed.
d. Fabricate grating platforms with nosing matching that on treads. Provide toeplates
at open-sided edges of grating platforms. Weld grating to platform framing.
A. Reference Standard:
1. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
2. Finish metal stairs after assembly.
B. Shop Priming:
PART 3 - EXECUTION
1. Provide anchorage devices and fasteners where necessary for securing metal stairs to
in-place construction. Include threaded fasteners for concrete and masonry inserts,
through-bolts, lag bolts, and other connectors.
1. Perform cutting, drilling, and fitting required for installing metal stairs. Set units
accurately in location, alignment, and elevation, measured from established lines and
levels and free of rack.
2. Provide temporary bracing or anchors in formwork for items that are to be built into
concrete, masonry, or similar construction.
3. Fit exposed connections accurately together to form hairline joints. Weld connections
that are not to be left as exposed joints but cannot be shop welded because of shipping
size limitations.
4. Field Welding: Comply with requirements for welding in "Fabrication, General" Article.
1. Field quality control shall be in accordance with the Quality Control Plan.
1. Engage a special Inspector to perform field inspections and tests and to prepare test
reports.
2. Field and shop welds will be subject to testing and inspecting.
3. Testing agency will report test results promptly and in writing to Contractor and
Contracting Officer.
4. Remove and replace work where test results indicate that it does not comply with
specified requirements.
5. Additional testing and inspecting, at Contractor's expense, will be performed to determine
compliance of replaced or additional work with specified requirements.
A. Touchup Painting:
1. Immediately after erection, clean field welds, bolted connections, and abraded areas of
shop paint, and paint exposed areas with the same material as used for shop painting to
comply with SSPC-PA 1 for touching up shop-painted surfaces.
2. Apply by brush or spray to provide a minimum 2.0-mil dry film thickness.
END OF SECTION
DESIGN CRITERIA
3. Exterior pipe railings are required at receiving area retaining walls, raised trash platforms, and stairs.
Roof mounted pipe railings are required adjacent to mechanical equipment located within 10' from the
edge of the building or raised equipment platform. DeCA standard requires exterior pipe railings to be
hot-dip galvanized and not painted, for reduced maintenance. Some military installations require that
exterior pipe railings be painted in accordance with the IDG and other Base standards. Provide
painted finish if required by installation.
4. Interior pipe railings are required at mezzanines open to a floor below and at stairs. Interior pipe
railings are prime painted immediately following fabrication and finish painted immediately following
installation. Indicate primer and finish paint in accordance with Division 09 Section Painting and
Coating.
5. In addition to the above locations indicate guards along open-sided walking surfaces, mezzanines,
equipment platforms, stairways, ramps, and landings which are located more than 30" above the floor
or grade below.
6. Where severe corrosion conditions exist, such as heavy industrial atmospheres or marine (salt water)
environments, specify Type 316 or Type 317 stainless steel. Refer to designer handbooks Design
Guidelines for the Selection and Use of Stainless Steel and Stainless Steel Architectural Facts
available from the Specialty Steel Industry of North America.
7. The design of pipe railings shall comply with applicable building/life safety codes and OSHA
requirements. Because commissary receiving areas are not open to the public, the 2009 IBC
(Paragraph 1012.3) only requires that balusters, horizontal intermediate rails or other construction be
designed so that a sphere with a diameter of 21 cannot pass through any opening.
8. In accordance with the IBC all projects are assigned to a Seismic Design Category. Where required
by project location, add applicable requirements of the IBC and referenced codes and standards.
9. Testing and Inspection: Although the IBC requires special inspections be performed by special
inspectors who are engaged by the Owner or the design professional, this Section specifies the
Contractor shall perform these duties.
END OF SECTION
June 2011 05 52 00 1
SECTION 05 52 00
PIPE RAILINGS
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of steel products.
A. General:
B. Structural Performance:
1. Provide railings capable of withstanding the effects of gravity loads and the following
loads and stresses within limits and under conditions indicated:
2. Handrails and Top Rails of Guards:
3. Infill of Guards:
C. Thermal Movements:
1. Allow for thermal movements from ambient and surface temperatures acting on exterior
railings by preventing buckling, opening of joints, overstressing of components, failure of
connections, and other detrimental effects.
a. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces.
1. Prevent galvanic action and other forms of corrosion by insulating metals and other
materials from direct contact with incompatible materials.
E. Delegated Design:
1.3 SUBMITTALS
A. LEED Submittals:
1. Product Data for Credit MR 4.1[ and Credit MR 4.2]: Indicating percentages by weight of
postconsumer and preconsumer recycled content for products having recycled content.
Include statement indicating costs for each product having recycled content.
B. Shop Drawings:
a. For installed products indicated to comply with design loads, include structural
analysis data signed and sealed by the qualified professional engineer responsible
for their preparation.
C. Welding Certificates.
D. Special Inspection reports on shop and field bolted connections, and welded connections.
E. Delegated-Design Submittal:
1. For installed products indicated to comply with performance requirements and design
criteria, including analysis data signed and sealed by the qualified professional engineer
responsible for their preparation.
1. Product Data:
A. Source Limitations:
1. Obtain each type of railing through one source from a single manufacturer.
B. Welding Qualifications:
1. Special Inspections for bolted and welded connections and steel details shall be
performed under the direct supervision of a Professional Engineer registered in the State
in which the project is located. The personnel performing the inspections shall be ICC-
certified Structural Steel and Welding Special Inspection or an equivalent certification
program.
A. Field Measurements:
1. Verify actual locations of walls and other construction contiguous with railings by field
measurements before fabrication.
1. Furnish setting Drawings, templates, and directions for installing anchorages, including
sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be
embedded in concrete or masonry. Deliver such items to Project site in time for
installation.
1. Schedule installation so wall attachments are made only to completed walls. Do not
support railings temporarily by any means that do not satisfy structural performance
requirements.
PART 2 - PRODUCTS
1. Provide materials with smooth surfaces, without seam marks, roller marks, rolled trade
names, stains, discolorations, or blemishes.
1. Cast or formed metal of same type of material and finish as supported rails, unless
otherwise indicated.
2.2 STEEL
1. Type F or Type S, Grade A, Standard Weight (Schedule 40), unless another grade and
weight are required by structural loads.
2. Provide galvanized finish for exterior installations.
2.3 FASTENERS
A. Steel Railings:
1. Select fasteners of type, grade, and class required to produce connections suitable for
anchoring railings to other types of construction indicated and capable of withstanding
design loads.
1. Provide concealed fasteners for interconnecting railing components and for attaching
them to other work, unless exposed fasteners are unavoidable or are the standard
fastening method for railings indicated.
D. Anchors:
B. Shop Primers:
E. Anchoring Cement:
A. General:
1. Fabricate railings to comply with requirements indicated for design, dimensions, member
sizes and spacing, details, finish, and anchorage, but not less than that required to
support structural loads.
2. Assemble railings in the shop to greatest extent possible to minimize field splicing and
assembly. Disassemble units only as necessary for shipping and handling limitations.
Clearly mark units for reassembly and coordinated installation. Use connections that
maintain structural value of joined pieces.
3. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a
radius of approximately 1/32 inch, unless otherwise indicated. Remove sharp or rough
areas on exposed surfaces.
4. Form work true to line and level with accurate angles and surfaces.
5. Fabricate connections that will be exposed to weather in a manner to exclude water.
Provide weep holes where water may accumulate.
6. Cut, reinforce, drill, and tap as indicated to receive finish hardware, screws, and similar
items.
7. Connections: Fabricate railings with welded connections, unless otherwise indicated.
8. Welded Connections: Cope components at connections to provide close fit, or use
fittings designed for this purpose. Weld all around at connections, including at fittings.
a. Use materials and methods that minimize distortion and develop strength and
corrosion resistance of base metals.
b. Obtain fusion without undercut or overlap.
c. Remove flux immediately.
d. At exposed connections, finish exposed surfaces smooth and blended so no
roughness shows after finishing and welded surface matches contours of adjoining
surfaces.
a. At brackets and fittings fastened to gypsum board partitions, provide fillers made
from crush-resistant material, or other means to transfer wall loads through wall
finishes to structural supports and prevent bracket or fitting rotation and crushing of
substrate.
13. Provide inserts and other anchorage devices for connecting railings to concrete or
masonry work. Fabricate anchorage devices capable of withstanding loads imposed by
railings. Coordinate anchorage devices with supporting structure.
14. For railing posts set in concrete, provide steel sleeves not less than 6 inches long with
inside dimensions not less than 1/2 inch greater than outside dimensions of post, with
steel plate forming bottom closure.
A. Galvanized Railings:
B. General:
1. Fill vent and drain holes that will be exposed in the finished Work, unless indicated to
remain as weep holes, by plugging with zinc solder and filing off smooth.
2. For galvanized railings, provide hot-dip galvanized fittings, brackets, fasteners, sleeves,
and other ferrous components.
3. For nongalvanized steel railings, provide nongalvanized ferrous-metal fittings, brackets,
fasteners, and sleeves.
4. Preparation for Shop Priming: Prepare uncoated ferrous-metal surfaces to comply with
SSPC-SP 3, "Power Tool Cleaning."
5. Apply shop primer to prepared surfaces of railings, unless otherwise indicated. Comply
with requirements in SSPC-PA 1, "Paint Application Specification No. 1: Shop, Field, and
Maintenance Painting of Steel," for shop painting. Primer need not be applied to surfaces
to be embedded in concrete or masonry.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine gypsum board assemblies, where reinforced to receive anchors, to verify that locations
of concealed reinforcements have been clearly marked for Installer. Locate reinforcements and
mark locations if not already done.
3.2 INSTALLATION
A. General:
a. Do not weld, cut, or abrade surfaces of railing components that have been coated
or finished after fabrication and that are intended for field connection by
mechanical or other means without further cutting or fitting.
b. Set posts plumb within a tolerance of 1/16 inch in 3 feet.
c. Align rails so variations from level for horizontal members and variations from
parallel with rake of steps and ramps for sloping members do not exceed 1/4 inch
in 12 feet.
A. Welded Connections:
1. Use fully welded joints for permanently connecting railing components. Comply with
requirements for welded connections in Part 2 "Fabrication" Article whether welding is
performed in the shop or in the field.
B. Expansion Joints:
1. Install expansion joints at locations indicated but not farther apart than required to
accommodate thermal movement. Provide slip-joint internal sleeve extending 2 inches
beyond joint on either side, fasten internal sleeve securely to 1 side, and locate joint
within 6 inches of post.
A. General:
1. Use steel pipe sleeves preset and anchored into concrete for installing posts. After posts
have been inserted into sleeves, fill annular space between post and sleeve with
nonshrink, nonmetallic grout or anchoring cement, mixed and placed to comply with
anchoring material manufacturer's written instructions.
2. Form or core-drill holes not less than 5 inches deep and 3/4 inch larger than OD of post
for installing posts in concrete. Clean holes of loose material, insert posts, and fill
annular space between post and concrete with nonshrink, nonmetallic grout or anchoring
cement, mixed and placed to comply with anchoring material manufacturer's written
instructions.
3. Leave anchorage joint exposed; wipe off surplus anchoring material; and leave 1/8-inch
buildup, sloped away from post.
A. General:
1. Anchor railing ends to concrete and masonry with round flanges connected to railing
ends and anchored to wall construction with anchors and bolts.
2. Anchor railing ends to metal surfaces with flanges bolted to metal surfaces and welded to
railing ends or connected to railing ends using nonwelded connections.
A. General:
1. Attach handrails to wall with wall brackets. Provide brackets with 1-1/2-inch clearance
from inside face of handrail and finished wall surface.
a. For concrete and solid masonry anchorage, use drilled-in expansion shields and
hanger or lag bolts.
b. For hollow masonry anchorage, use toggle bolts.
4. For steel-framed gypsum board partitions, fasten brackets directly to steel framing or
concealed steel reinforcements using self-tapping screws of size and type required to
support structural loads.
1. Field quality control shall be in accordance with the Quality Control Plan.
1. Engage a special Inspector to perform field inspections and tests and to prepare test
reports.
2. Field and shop welds will be subject to testing and inspecting.
3. Testing agency will report test results promptly and in writing to Contractor and
Contracting Officer.
4. Remove and replace work where test results indicate that it does not comply with
specified requirements.
5. Additional testing and inspecting, at Contractor's expense, will be performed to determine
compliance of replaced or additional work with specified requirements.
A. Touchup Painting:
1. Immediately after erection, clean field welds, bolted connections, and abraded areas of
shop paint, and paint exposed areas with same material as used for shop painting to
comply with SSPC-PA 1 for touching up shop-painted surfaces.
B. Galvanized Surfaces:
1. Clean field welds, bolted connections, and abraded areas and repair galvanizing to
comply with ASTM A 780.
3.9 PROTECTION
A. Protection:
1. Protect finishes of railings from damage during construction period with temporary
protective coverings approved by railing manufacturer. Remove protective coverings at
time of final acceptance.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 06 Sections Sheathing and Interior Architectural Woodwork.
2. This Section specifies miscellaneous wood framing, incidental rough carpentry required for the
support or attachment of other construction. It is intended for projects that do not require wood
framing as the primary structural system or extensive use of other carpentry items. The Section
includes pressure-preservative-treated and fire-retardant-treated wood.
3. Design Considerations:
B. In accordance with UFC 3-600-01, paragraph 2-13.1 (14 JUL 2009), fire-retardant plywood is not
to be used in any part of a roof or roofing system.
END OF SECTION
June 2011 06 10 00 1
SECTION 06 10 00
ROUGH CARPENTRY
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
A. General:
1. Keep materials under cover and dry. Protect from weather and contact with damp or wet
surfaces. Stack lumber, plywood, and other panels. Provide for air circulation within and
around stacks and under temporary coverings.
2. For lumber and plywood pressure treated with waterborne chemicals, place spacers
between each bundle to provide air circulation.
1.3 SUBMITTALS
A. Product Data:
B. LEED Submittals:
2. Product Data for Credit EQ 4.1: For adhesives, documentation including printed
statement of VOC content.
3. Product Data for Credit EQ 4.4: For composite wood products, documentation indicating
that product contains no urea formaldehyde.
C. Submittal List:
PART 2 - PRODUCTS
A. Lumber Standards:
1. Comply with DOC PS 20, "American Softwood Lumber Standard," and with applicable
grading rules of inspection agencies certified by American Lumber Standards
Committee's (ALSC) Board of Review.
B. Sizes:
1. Where nominal sizes are indicated, provide actual sizes required by DOC PS 20 for
moisture content specified. Where actual sizes are indicated, they are minimum dressed
sizes for dry lumber.
2. Provide dressed lumber, S4S, unless otherwise indicated.
3. Provide dry lumber with 19 percent maximum moisture content at time of dressing for 2-
inch nominal thickness or less, unless otherwise indicated.
1. Allowable Design Stresses: Provide engineered wood products with allowable design
stresses, as published by manufacturer, that meet or exceed those indicated.
Manufacturer's published values shall be determined from empirical data or by rational
engineering analysis and demonstrated by comprehensive testing performed by a
qualified independent testing agency.
A. General:
B. Pressure Treatment:
a. Wood cants, nailers, curbs, equipment support bases, blocking, stripping, and
similar members in connection with roofing.
b. Wood blocking, furring, stripping, and similar concealed members in contact with
masonry or concrete.
1. Wood cants, nailers, curbs, equipment support bases, blocking, stripping, and similar
members in connection with roofing, flashing, vapor barriers, and waterproofing.
2. Wood blocking, and similar concealed members in contact with masonry or concrete.
3. Wood framing and furring attached directly to the interior of below-grade exterior masonry
or concrete walls.
4. Wood framing members that are less than 18 inches above the ground in crawl spaces or
unexcavated areas.
5. Wood floor plates that are installed over concrete slabs-on-grade.
A. General:
a. Concealed blocking.
b. Plywood backing panels.
C. See Design Criteria and UFC for restrictions on fire treated plywood in roof systems
A. General:
B. Trademark:
1. Factory mark structural-use panels with APA trademark evidencing compliance with
grade requirements.
1. C-C Plugged Exterior, thickness as indicated but not less than 1/2 inch.
1. A-D Interior, thickness as indicated but not less than 1/2 inch.
2.6 FASTENERS
A. General:
1. Provide fasteners of size and type indicated that comply with requirements specified in
this Article for material and manufacture.
F. Bolts: Steel bolts complying with ASTM A 307, Grade A; with ASTM A 563 hex nuts and, where
indicated, flat washers.
G. Expansion Anchors: Anchor bolt and sleeve assembly of material indicated below with
capability to sustain, without failure, a load equal to 6 times the load imposed when installed in
unit masonry assemblies and equal to 4 times the load imposed when installed in concrete as
determined by testing per ASTM E 488 conducted by a qualified independent testing and
inspecting agency.
3.1 INSTALLATION
A. General:
1. Discard units of material with defects that impair quality of carpentry and that are too
small to use with minimum number of joints or optimum joint arrangement.
2. Set carpentry to required levels and lines, with members plumb, true to line, cut, and
fitted.
3. Fit carpentry to other construction; scribe and cope as required for accurate fit. Correlate
location of furring, nailers, blocking, grounds, and similar supports to allow attachment of
other construction.
4. Where wood-preservative-treated lumber is installed adjacent to metal decking, install
continuous flexible flashing separator between wood and metal decking.
5. Apply field treatment complying with AWPA M4 to cut surfaces of preservative-treated
lumber and plywood.
6. Securely attach carpentry work as indicated and according to applicable codes and
recognized standards.
7. Countersink nail heads on exposed carpentry work and fill holes with wood filler.
8. Use fasteners of appropriate type and length. Predrill members when necessary to avoid
splitting wood.
A. General:
1. Install where shown and where required for screeding or attaching other work. Cut and
shape to required size. Coordinate locations with other work involved.
2. Attach to substrates to support applied loading. Recess bolts and nuts flush with
surfaces, unless otherwise indicated.
3. Anchor wood nailers for roofing system work as follows:
a. Wood nailer to concrete masonry units: Provide 1/2 inch diameter steel bolt by
length required for 8-inch embedment into concrete filled core. Space anchors 4
feet 0 inches on center, staggered, except at corners space anchors 2 feet 0
inches on center from corner for a distance of 8 feet 0 inches.
b. Wood nailer to concrete masonry unit bond beam: Provide 1/2 inch diameter steel
bolt with 2-inch hook with embedment length of 5 inches into concrete filled
concrete masonry unit bond beam. Space anchors 4 feet 0 inches on center,
staggered, except at corners space anchors 2 feet 0 inches on center from corner
for a distance of 8 feet 0 inches.
c. Wood nailer to metal deck: Provide No. 10 cadmium plated sheet metal screws
with 5/8 inch diameter galvanized washers. Install in two rows. Space 2 feet 0
inches on center in each row except at corners space screws 1 foot 0 inches on
center from corner for a distance of 8 feet 0 inches. Stagger spacing between
rows.
d. Wood member to wood nailer: Provide 10d threaded nail by length required for 1-
1/2 inches penetration into nailer. Install in two rows. Space 2 feet 0 inches on
center in each row except at corners space nails 1 foot 0 inches on center from
corner for a distance of 8 feet 0 inches. Stagger spacing between rows.
A. General:
1. Install plumb and level with closure strips at edges and openings. Shim with wood as
required for tolerance of finish work.
2. Furring to Receive Plywood Paneling: Install 1-by-3-inch nominal- size furring at 24
inches o.c., horizontally and vertically. Select furring with no knots capable of producing
bent-over nails and damage to paneling.
A. General:
1. Comply with applicable recommendations contained in APA Form No. E30K, "APA
Design/Construction Guide: Residential & Commercial," for types of structural-use
panels and applications indicated.
B. Fastening Methods:
3.5 PROTECTION
A. Protect wood that has been treated with inorganic boron (SBX) from weather. If, despite
protection, inorganic boron-treated wood becomes wet, apply EPA-registered borate treatment.
Apply borate solution by spraying to comply with EPA-registered label.
B. Protect rough carpentry from weather. Replace rough carpentry if, despite protection, rough
carpentry becomes sufficiently wet that moisture content exceeds that specified, apply EPA-
registered borate treatment. Apply borate solution by spraying to comply with EPA-registered
label.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 07 Section Metal Panels for metal sheathing roof panels.
2. This Section specifies paper-surfaced gypsum wall sheathing, glass-mat gypsum sheathing board,
and building paper.
3. Design Considerations:
A. Use glass-mat gypsum sheathing board on walls receiving plaster or exterior insulation finish
systems.
B. Use paper-surfaced gypsum wall sheathing on walls receiving exterior finishes other than above,
i.e., masonry veneer, metal wall panels, etc.
END OF SECTION
June 2011 06 16 00 1
SECTION 06 16 00
SHEATHING
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Wall sheathing.
2. Building paper.
3. Building wrap.
4. Sheathing joint-and-penetration treatment.
5. Flexible flashing at openings in sheathing.
1.2 SUBMITTALS
A. Product Data:
1. For each type of process and factory-fabricated product. Indicate component materials
and dimensions and include construction and application details.
B. LEED Submittals:
C. Submittal List:
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. ASTM C 79/C 79M or ASTM C 1396/C 1396M, gypsum sheathing; with water-resistant-
treated core and with water-repellent paper bonded to core's face, back, and long edges.
2. Type: Regular, 1/2 inch thick.
3. Edge and End Configuration: V-shaped, tongue-and-groove long edges; square ends.
4. Size: 24 by 96 inches for horizontal installation.
A. Building Paper: ASTM D 226, Type 1 (No. 15 asphalt-saturated organic felt), unperforated.
B. Building Wrap: ASTM E 1677, Type I air retarder; with flame-spread and smoke-developed
indexes of less than 25 and 450, respectively, when tested according to ASTM E 84; UV
stabilized; and acceptable to authorities having jurisdiction.
2. Water-Vapor Permeance: Not less than 28 Perms when tested per ASTM E 96,
Desiccant Method (Procedure B).
A. Sealant for Paper-Surfaced and Glass-Mat Gypsum Sheathing Board: Silicone emulsion
sealant complying with ASTM C 834, and recommended by tape and sheathing manufacturers.
B. Sheathing Tape for Glass-Mat Gypsum Sheathing Board: Self-adhering glass-fiber tape, of
type recommended by sheathing and tape manufacturers.
2.5 FASTENERS
A. General:
1. Provide fasteners of size and type indicated that comply with requirements specified in
this Article for material and manufacture.
2. For wall sheathing, provide fasteners with hot-dip zinc coating complying with
ASTM A 153/A 153M.
a. For steel framing less than 0.0329 inch thick, attach sheathing to comply with
ASTM C 1002.
b. For steel framing from 0.033 to 0.112 inch thick, attach sheathing to comply with
ASTM C 954.
3.1 INSTALLATION
A. General:
1. Do not use materials with defects that impair quality of sheathing or pieces that are too
small to use with minimum number of joints or optimum joint arrangement.
2. Cut panels at penetrations, edges, and other obstructions of work; fit tightly against
abutting construction, unless otherwise indicated.
3. Securely attach to substrate by fastening as indicated.
4. Coordinate wall sheathing installation with flashing and joint-sealant installation so these
materials are installed in sequence and manner that prevent exterior moisture from
passing through completed assembly.
5. Do not bridge building expansion joints; cut and space edges of panels to match spacing
of structural support elements.
6. Coordinate sheathing installation with installation of materials installed over sheathing so
sheathing is not exposed to precipitation or left exposed at end of the workday when rain
is forecast.
A. General:
B. Horizontal Installation:
1. Install sheathing with V-grooved edge down and tongue edge up. Interlock tongue with
groove to bring long edges in contact with edges of adjacent boards without forcing. Abut
ends of boards over centers of studs, and stagger end joints of adjacent boards not less
than one stud spacing. Attach boards at perimeter and within field of board to each steel
stud.
2. Space fasteners approximately 8 inches o.c. and set back a minimum of 3/8 inch from
edges and ends of boards.
C. Vertical Installation:
1. Install board vertical edges centered over studs. Abut ends and edges of each board
with those of adjacent boards. Attach boards at perimeter and within field of board to
each stud.
2. Space fasteners approximately 8 inches o.c. and set back a minimum of 3/8 inch from
edges and ends of boards.
A. General:
a. Cut back barrier 1/2 inch on each side of the break in supporting members at
expansion- or control-joint locations.
b. Apply barrier to cover vertical flashing with a minimum 4-inch overlap, unless
otherwise indicated.
B. Building Paper:
1. Apply horizontally with a 2-inch overlap and a 6-inch end lap; fasten to sheathing with
galvanized staples or roofing nails.
A. Apply glass-fiber sheathing tape to glass-mat gypsum sheathing board joints, and apply and
trowel silicone emulsion sealant to embed tape in sealant. Apply sealant to exposed fasteners.
Seal other penetrations and openings.
A. Apply flexible flashing where indicated to comply with manufacturers written instructions.
1. Lap seams and junctures with other materials at least 4 inches, except that at flashing
flanges of other construction, laps need not exceed flange width.
2. Lap flashing over weather-resistant building paper at bottom and sides of openings.
3. Lap weather-resistant building paper over flashing at heads of openings.
4. After flashing has been applied, roll surfaces with a hard rubber or metal roller.
3.6 PROTECTION
END OF SECTION
DESIGN CRITERIA
1. This Section specifies fabricated wood and plastic laminate cabinetry, plastic laminate counter tops,
solid surface counter tops and materials and miscellaneous accessories items.
2. Design Considerations:
B. Coordinate details from Design plates and modify for the project.
C. Including point of sale transitions and floor clearances, comply with ABA Accessibility Standard
for Department of Defense Facilities as adopted by the Deputy Secretary of defense
memorandum dated October 31, 2008.
END OF SECTION
June 2011 06 40 23 1
SECTION 06 40 23
1.1 SUMMARY
A. Section Includes:
1. Plastic-laminate-faced cabinets.
2. Plastic-laminate-faced countertops.
3. Solid-surfacing-material countertops.
4. Hardware and accessory materials.
5. Articulating key board tray.
6. Utility shelving.
7. Silver paracube grid.
8. Plastic sheet.
B. Related Sections:
3. Division 6 Section "Rough Carpentry" for wood furring, blocking, shims, and hanging
strips required for installing cabinets and concealed within other construction before
cabinet installation.
1.2 DEFINITIONS
A. Interior architectural woodwork includes wood furring, blocking, shims, and hanging strips for
installing woodwork items unless concealed within other construction prior to woodwork
installation.
A. Product Data:
1. For each type of product indicated, including cabinet hardware and accessories, and
finishing materials and processes.
B. LEED Submittals:
1. Product Data for Credit MR 4: For products having recycled content, documentation
indicating percentages by weight of postconsumer and preconsumer recycled content.
Include statement indicating cost for each product having recycled content.
3. Product Data for Credit IEQ 4.1: For installation adhesives, documentation including
printed statement of VOC content.
4. Product Data for Credit IEQ 4.4: For composite wood products and adhesives,
documentation indicating that product contains no urea formaldehyde.
5. Laboratory Test Reports for Credit IEQ 4: For [adhesives] [composite wood products]
[and] [finishing materials], documentation indicating that products comply with the
testing and product requirements of the California Department of Health Services'
"Standard Practice for the Testing of Volatile Organic Emissions from Various Sources
Using Small-Scale Environmental Chambers."
C. Shop Drawings:
1. Dimensioned plans, elevations, and large scale details showing location of each cabinet,
attachment devices, and other components.
1. Standing and running trim with transparent finish, 12 inches long, for each species and
cut, finished on one side and one edge.
2. Plastic-laminate and solid-surfacing material color, pattern, and texture selected.
A. Fabricator Qualifications:
1. Firm experienced in producing architectural woodwork that employs skilled workers who
custom fabricate products similar to that indicated for this Project and with a record of
successful in-service performance, as well as sufficient production capacity to produce
required units without delaying the Work.
B. Installer Qualifications:
1. Arrange for interior architectural woodwork installation by a firm that can demonstrate
successful experience in installing architectural woodwork items similar in type and
quality to those required for this Project.
C. Quality Standard:
A. Protect woodwork during transit, delivery, storage, and handling to prevent damage, soilage,
and deterioration. Do not deliver woodwork until painting and similar operations that could
damage, soil, or deteriorate woodwork have been completed in installation areas. If woodwork
must be stored in other than installation areas, store only in areas whose environmental
conditions meet requirements specified in "Project Conditions."
A. Environmental Limitations:
1. Do not deliver or install woodwork until building is enclosed, wet-work is completed, and
HVAC system is operating and will maintain temperature and relative humidity at
occupancy levels during the remainder of the construction period.
1.7 COORDINATION
A. General:
1. Coordinate sizes and locations of framing, blocking, furring, reinforcements, and other
related units of Work specified in other Sections to ensure that interior architectural
woodwork can be supported and installed as indicated.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
2.2 MATERIALS
A. General:
1. Provide materials that comply with requirements of referenced quality standard for each
type of woodwork and quality grade specified unless otherwise indicated and, where the
following products are part of interior woodwork, with requirements of the referenced
product standards that apply to product characteristics indicated:
A. General:
B. Hardware Standard:
1. Comply with BHMA A156.9 for items indicated by reference to BHMA numbers or
referenced to this standard.
1. For exposed hardware, provide finish that complies with BHMA A156.18 for BHMA code
number indicated.
1. For concealed hardware provide manufacturer's standard finish that complies with
product class requirements of BHMA A156.9.
E. Hardware:
1. Softwood or hardwood lumber, kiln dried to less than 15 percent moisture content.
B. Screws:
1. Select material, type, size, and finish required for each use. Comply with ASME B18.6.1
for applicable requirements. For metal framing supports, provide screws as
recommended by metal-framing manufacturer.
C. Nails:
1. Select material, type, size, and finish required for each use. Comply with FS FF-N-105
for applicable requirements.
D. Anchors:
1. Select material, type, size, and finish required for each substrate for secure anchorage.
Provide nonferrous metal or hot-dip galvanized anchors and inserts on inside face of
exterior walls and elsewhere as required for corrosion resistance. Provide toothed steel
or lead expansion bolt devices for drilled-in-place anchors.
1. Provide interior woodwork complying with the referenced quality standard and of the
following grade:
a. Grade: Premium.
1. Comply with requirements of referenced quality standard for wood moisture content in
relation to relative humidity conditions existing during time of fabrication and in installation
areas.
C. Fabrication:
1. Fabricate woodwork to dimensions, profiles, and details indicated. Ease edges to radius
indicated for the following:
a. Corners of cabinets and edges of solid-wood (lumber) members 3/4 inch thick or
less: 1/16 inch.
b. Edges of rails and similar members more than 3/4 inch thick: 1/8 inch.
A. Quality Standard:
B. Grade:
1. Premium.
1. Provide materials and products that result in colors and textures of exposed laminate
surfaces complying with the following requirements:
H. Drawer Construction
1. Fabricate with exposed fronts fastened to subfront with mounting screws from interior of
body.
a. Join subfronts, backs, and sides with glued rabbeted joints supplemented by
mechanical fasteners or glued dovetail joints
A. Quality Standard:
B. Fabrication
A. Quality Standard:
1. Fabricate tops in one piece with shop-applied backsplashes and edges, unless otherwise
indicated. Comply with solid-surfacing-material manufacturer's written recommendations
for adhesives, sealers, fabrication, and finishing.
1) Ergonomic design.
2) Slides fully concealed from view.
3) No rough edges or pinch points.
4) Accommodates any size keyboard by removing palm rest.
5) Large tray width provides unhanded mouse surface.
6) Foam mouse pad and removable full-length gel palm rest.
7) Cable management fixtures incorporated in rear of tray.
8) Slides silenced in the open and closed positions.
9) Detent in the full open, typing, and closed positions.
10) Rear storage compartments for office supplies.
1. 2-inch OD, black, molded-plastic grommets and matching plastic caps with slot for wire
passage.
2. Basis-of-Design Products: "SG series," Doug Mockett and Co., Inc.
2.10 SHELVING
A. Utility Shelving:
1. Softwood Boards: Eastern white, Idaho white, lodgepole, ponderosa, radiata, or sugar
pine; C Select (Choice), D Select (Quality), Finish or 1 Common (Colonial), Premium or
2 Common (Sterling); NeLMA, NLGA, or WWPA; kiln dried.
a. 3/4 inch by 1-1/2-inch solid lumber dropped edge, glued and nailed to shelf.
b. Shelf Width: As indicated.
4. Shelf Rest:
a. Mount shelves to brackets with two shelf rests per bracket. Fasten with 2-No. 10
wood screws per shelf rest.
b. Knape & Vogt Mfg. Co., No. 106.
A. Basis-of-Design Products:
A. Polycarbonate Sheet:
1. Plastic compound, clear; ultraviolet stabilized; silicone abrasion resistant coating for
scratch resistance.
B. Attachment Accessories:
1. Plastic rosettes placed at top and bottom of sheet, 24 inches on center maximum.
3.1 PREPARATION
A. General:
3.2 INSTALLATION
A. General:
1. Quality Standard: Install interior architectural woodwork to comply with referenced quality
standard for the same grade specified in Part 2 of this Section for type of woodwork
involved.
2. Install woodwork plumb, level, true, and straight with no distortions. Shim as required
with concealed shims. Install to a tolerance of 1/8 inch in 96 inches for plumb and level
(including tops).
3. Scribe and cut woodwork to fit adjoining work and refinish cut surfaces or repair damaged
finish at cuts.
4. Anchor woodwork to anchors or blocking built in or directly attached to substrates.
5. Secure to grounds, stripping, and blocking with countersunk, concealed fasteners and
blind nailing as required for complete installation. Use fine finishing nails or finishing
screws for exposed nailing, countersunk and filled flush with woodwork and matching
final finish.
6. Cabinets: Install without distortion so that doors and drawers fit openings properly and
are accurately aligned. Adjust hardware to center doors and drawers in openings and to
provide unencumbered operation. Complete the installation of hardware and accessory
items as indicated.
a. Install cabinets with no more than 1/8 inch in 96-inch sag, bow, or other variation
from a straight line.
b. Fasten wall cabinets through back, near top and bottom, and at ends not more
than 16 inches o.c. as follows:
1) No. 10 wafer-head screws sized for not less than 1-1/2-inch penetration into
wood framing, blocking, or hanging strips.
2) No. 10 wafer-head sheet metal screws or toggle bolts through metal backing
or metal framing behind wall finish.
c. Tops: Anchor securely to base units and other support systems as indicated. Calk
space between backsplash and wall with clear single-component mildew-resistant
acid-curing silicone sealant.
1) Install countertops with no more than 1/8 inch in 96-inch sag, bow, or other
variation from a straight line.
A. General:
1. Repair damaged and defective woodwork where possible to eliminate functional and
visual defects; where not possible to repair, replace woodwork. Adjust joinery for uniform
appearance.
2. Clean, lubricate, and adjust hardware.
3. Clean woodwork on exposed and semiexposed surfaces. Touch up shop-applied
finishes to restore damaged or soiled areas.
3.4 PROTECTION
A. Provide final protection and maintain conditions in a manner acceptable to fabricator and
Installer that ensures that woodwork is without damage or deterioration at the time of final
acceptance.
END OF SECTION
DESIGN CRITERIA
2. This Section specifies semi-rigid, impact-resistant, washable. sheet wall panels for protection of cold
storage room wall panels and gypsum wallboard partitions in high traffic, high abuse areas, including:
B. Cold Storage Room walls facing Receiving/Staging and other storage areas.
D. Janitors Closets.
3. Refer to Standard Commissary Room and Finish Schedule in Appendix A for specific application
requirements.
4. Codes and Standards: NFPA Class A interior finish in accordance with ASTM E 84.
5. Plastic sheet wall coverings have a high level of thermal elasticity, therefore, use edge trim and
moldings to accommodate the resulting expansion and contraction. Install panels with adhesive
except where fasteners are required for additional support. Do not use metal fasteners on cold
storage room wall panels.
END OF SECTION
June 2011 06 83 16 1
SECTION 068316
FIBERGLASS REINFORCED PANELING
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
1. Product Data:
a. For adhesives and sealants, including printed statement of VOC content and
chemical components (Credit EQ 4.1).
C. Submittal List:
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design Product:
B. Materials:
1. Fiberglass reinforced polyester plastic sheets: Sheets shall comply with fire-test-
response characteristics specified, be chemical and stain resistant, and be USDA
acceptable for incidental food contact. Provide manufacturer's standard matching
moldings and trim as indicated.
2. Size: 4 feet by 8 feet, minimum.
3. Thickness: 0.09 inch.
4. Do not furnish material in roll form.
C. Fire Classification:
D. Panel Finish:
E. Accessories:
a. VOC Content: 50 g/L or less when calculated according to 40 CFR 59, Subpart D
(EPA Method 24).
a. VOC Content: 250 g/L or less when calculated according to 40 CFR 59, Subpart D
(EPA Method 24).
3.1 INSPECTION
A. General:
1. Ensure surfaces to receive wall paneling are clean, true and free of irregularities.
2. Clean substrates of substances that could impair bond of adhesive, including oil, grease,
dirt, and dust.
3. Ensure wall surface flatness tolerance do not vary more than 1/8 inch in 10 feet.
4. Schedule installation of panels as late as possible to prevent damage during construction
and movement of materials.
A. General:
1. Handle and apply wall panels in accordance with manufacturer's written instructions.
2. Install panels in a full spread of adhesive.
3. Where fasteners are required for additional support use noncorroding fasteners where
concealed and Nylon drive rivets where exposed. Install in accordance with
manufacturers written instructions allowing for expansion and contraction of panels.
4. Install with edges inserted into moldings. Allow clearance for expansion and contraction
of panels when fitting into moldings.
5. Install trim accessories with adhesive. Do not fasten through panels.
6. Apply a continuous bead of sealant into molding slots prior to insertion of panels.
3.3 CLEANING
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 04 Section Unit Masonry for integral water-repellent admixture for unit
masonry assemblies.
2. This Section specifies liquid-applied, clear, penetrating water repellents for vertical and horizontal
surfaces of concrete unit masonry.
3. Design Considerations:
A. Indicate a water repellent where concrete unit masonry is exposed to moisture that will be
absorbed through pores, capillaries, or cracks in its exterior surfaces. Water repellents limit the
penetration of liquid water that is not under pressure, but they permit vapor transmission. They
cannot be used below grade.
B. Verify that field-applied water repellent is compatible with the integral water-repellent admixture
provided by the CMU manufacturer per Division 04.
END OF SECTION
June 2011 07 19 00 1
SECTION 07 19 00
WATER REPELLENTS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Penetrating water-repellent coatings for the following vertical and horizontal surfaces:
B. Related Sections:
1. Division 04 Section Unit Masonry for integral water-repellent admixture for unit masonry.
A. Performance Testing: Provide water repellents that comply with test-performance requirements
indicated, as evidenced by reports of tests performed by manufacturer by a qualified
independent testing agency on manufacturer's standard products applied to substrates
simulating those on Project using same application methods to be used for Project.
1.3 SUBMITTALS
A. Product Data:
D. Special warranty.
F. Submittal List:
1.5 WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer and Applicator agree(s)
to repair or replace materials that fail to maintain water repellency specified in Part 1
"Performance Requirements" Article within Five years from date of final acceptance.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.1 PREPARATION
A. General:
a. Water-repellent work may precede sealant application only if sealant adhesion and
compatibility have been tested and verified using substrate, water repellent, and
sealant materials identical to those used in the Work.
5. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 APPLICATION
B. First Application:
C. Second Application:
1. Apply a second saturation spray coating, repeating first application. Comply with
manufacturer's written instructions for limitations on drying time between coats and after
rainstorm wetting of surfaces between coats. Consult manufacturer's technical
representative if written instructions are not applicable to Project conditions.
A. Coverage Test: In the presence of Governments Designated Representative, hose down a dry,
repellent-treated surface to verify complete and uniform product application. A change in
surface color will indicate incomplete application.
1. Notify Governments Designated Representative seven days in advance of the dates and
times when surfaces will be tested.
2. Reapply water repellent until coverage test indicates complete coverage.
3.4 CLEANING
A. Immediately clean water repellent from adjoining surfaces and surfaces soiled or damaged by
water-repellent application as work progresses. Repair damage caused by water-repellent
application. Comply with manufacturer's written cleaning instructions.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 09 painting Sections for general field painting.
2. This Section specifies surface preparation and the application of concrete stains to exterior concrete
surfaces.
3. When selecting an exterior concrete stain system, evaluate the substrate, the severity of the
environment, and the actual cost of stain system, including maintenance programs necessary to
protect the systems integrity.
4. Ensure products selected meet all federal, state, and local VOC requirements.
5. Require a full-coat field benchmark finish sample for each type of stain required, duplicating the finish
of approved samples, for approval by the Contracting Officer.
END OF SECTION
June 2011 07 19 13 1
SECTION 07 19 13
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Surface preparation and the application of concrete stains to exterior concrete surfaces.
1.2 SUBMITTALS
A. Product Data:
a. Material List: An inclusive list of required stain materials. Indicate each material
and cross-reference the specific stain system and application. Identify each
exterior concrete stain material by manufacturer's catalog number and general
classification.
b. Manufacturer's Information: Manufacturer's technical information, including label
analysis and instructions for handling, storing, and applying each exterior concrete
stain.
1. For each color and stain material to be applied, with texture to simulate actual conditions,
on representative Samples of actual substrates.
a. Use representative colors when preparing Samples for review. Resubmit until
required color and texture are achieved.
b. Provide list of materials and applications for each coat of each Sample. Label
each Sample for location and application.
c. Submit Samples on the following substrates for Contracting Officer's review of
color and texture only:
C. Submittal List:
A. Applicator Qualifications:
1. Provide a full-coat benchmark finish sample for each type of stain and substrate required.
Duplicate finish of approved sample Submittals.
a. Location: Apply each type of stain where indicated on Drawings, for each color.
1) After finishes are accepted, Contracting Officer will use benchmark samples
to evaluate stain systems of a similar nature.
A. Delivery:
a. Protect from freezing. Keep storage area neat and orderly. Remove oily rags and
waste daily.
A. Temperature Limitations:
1. Apply stains only when temperatures of surfaces to be stained and the surrounding air
are between 50 deg F and 90 deg F for latex-based stain.
B. Weather Limitations:
1. Do not apply stain in snow, rain, fog, or mist; when relative humidity exceeds 85 percent;
when temperatures are less than 5 deg F above the dew point; or to damp or wet
surfaces.
a. Allow wet surfaces to dry thoroughly and attain temperature and conditions
specified before starting or continuing with coating operation.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Stain-Material Quality:
1. Provide manufacturer's best-quality stain material of the various stain types specified that
are factory formulated and recommended by manufacturer for application indicated.
Stain-material containers not displaying manufacturer's product identification will not be
acceptable.
B. Proprietary Names:
PART 3 - EXECUTION
3.1 EXAMINATION
A. General:
1. Examine substrates, areas, and conditions, with Applicator present, for compliance with
requirements for stain application. Surfaces to be stained must be thoroughly dry before
stains are applied.
a. Proceed with stain application only after unsatisfactory conditions have been
corrected.
b. Stain application may precede sealant application only if sealant adhesion and
compatibility have been tested and verified using substrate, stain, and sealant
materials identical to those used in the Work.
c. Start of application will be construed as Applicator's acceptance of surfaces and
conditions.
B. Coordination of Work:
1. Review other Sections in which coatings are provided to ensure compatibility of the total
system for various substrates.
3.2 PREPARATION
A. General:
a. After completing staining operations, reinstall items removed using workers skilled
in trades involved.
B. Surface Preparation:
a. Prepare concrete surfaces to be stained. Remove dust, dirt, grease, oils, and
release agents. Roughen as required to remove glaze. If hardeners or sealers
have been used to improve curing, use mechanical methods of surface
preparation.
C. Mixing:
1. Mix and prepare stains according to manufacturer's written instructions. Stir stain
thoroughly before applying and frequently during application to maintain color
consistency.
3.3 APPLICATION
a. Do not apply stain on surfaces that are not sufficiently dry. Ensure that each coat
is dry before applying succeeding coat.
A. Coverage Test: In the presence of Governments Designated Representative, hose down a dry,
repellent-treated surface to verify complete and uniform product application. A change in
surface color will indicate incomplete application.
1. Notify Governments Designated Representative seven days in advance of the dates and
times when surfaces will be tested.
2. Reapply water repellent until coverage test indicates complete coverage.
3.5 CLEANING
A. Cleanup:
1. At the end of each workday, remove empty cans, rags, rubbish, and other discarded
materials from Project site.
3.6 PROTECTION
A. General:
1. Protect work of other trades, whether being stained or not, against damage from staining.
Correct damage by cleaning, repairing or replacing, and restaining as approved by
Contracting Officer.
2. Provide "Wet Paint" signs to protect newly stained finishes. After completing staining
operations, remove temporary protective wrappings provided by others to protect their
work.
a. After work of other trades is complete, touch up and restore damaged or defaced
stained surfaces.
A. Exterior Concrete:
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 03 Section Insulated Freezer Floors, Division 04 Section Unit Masonry,
Division 07 Section Exterior Insulation and Finish Systems (EIFS), and Division 07 Sections Ethylene-
Propylene-Diene-Monomer Roofing and Thermoplastic Membrane Roofing, and Division 09 Section
Gypsum Board for sound attenuation insulation.
2. This Section specifies common types of general building insulation installed in commissary facilities
as separate elements rather than as components of prefabricated or field-assembled systems.
3. Insulate above grade exterior wall systems to achieve an "R" of 10 minimum, unless climatic
conditions or the local Installation energy code requirements dictate otherwise. Current Federal
Energy Reduction Mandates may require the use of increased insulation thicknesses. This will be
determined through energy usage calculations prepared as part of project development.
4. If climatic conditions warrant below slab foundation insulation, a geotechnical report will typically
indicate this requirement. Design foundation insulation in full compliance with the recommendations
contained in the Project Geotechnical Report. If climatic conditions indicate that foundation insulation
would be appropriate and the geotechnical report does not indicate same, consult with engineer
responsible for preparation of report.
5. Moisture Protection:
A. As a constituent part of the atmosphere, water vapor migrates by diffusion through air and
materials according to its own pressure differentials. Accordingly, the control of diffusion is more
important with improved construction techniques controlling air leakage in commissaries. Overall
control of moisture within a pressurized building envelope requires a vapor retarder.
1. Where summer design dew point is above 70 degrees locate vapor retarder on outside of
wall insulation.
2. Where winter design temperature is below 65 degrees locate vapor retarder on inside of wall
insulation.
B. A commissary has a pressurized building envelope with specific temperature and humidity
requirements for refrigeration systems to function properly.
2. Cold storage rooms are maintained at various temperatures required for proper storage and
processing of food products.
3. Staging and receiving areas, as well as other non-refrigerated storage areas, typically have
heat and ventilation only.
C. It is important that walls surrounding the staging and receiving areas extend to the
underside of the roof deck, and that all penetrations through these walls are sealed air
tight. This is necessary to prevent warm humid air from entering into the temperature and
humidity controlled sales area and attic spaces above sales area and cold storage rooms. If
warm humid air is allowed to enter these spaces, condensation can occur that will damage other
construction and impact proper operation of mechanical systems.
D. In particularly warm and humid locations it may be appropriate to insulate the full height wall
surrounding the staging and receiving area, in addition to sealing penetrations air tight.
June 2011 07 21 00 1
DeCA DESIGN CRITERIA HANDBOOK
07 21 00 THERMAL INSULATION
E. In facilities with exposed roof structure in sales area, the perimeter walls / soffits shall
extend to the underside of the roof deck with all penetrations sealed air tight. This is
necessary maintain proper temperature and humidity control of sales area, eliminate requirement
for sprinklers in attic space above cold storage rooms and other adjacent areas, and aesthetic
appearance.
END OF SECTION
June 2011 07 21 00 2
SECTION 07 21 00
THERMAL INSULATION
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of glass and slag-
wool-fiber/rock-wool-fiber insulation products.
2. Division 03 Section Insulated Freezer Floors for freezer floor slab rigid board insulation.
3. Division 04 Section Unit Masonry for cavity-wall rigid board insulation.
4. Division 07 Section Ethylene-Propylene-Diene-Monomer Roofing for insulation specified
as part of roofing construction.
5. Division 07 Section Thermoplastic Membrane Roofing for insulation specified as part of
roofing construction.
6. Division 07 Section Exterior Insulation and Finish Systems (EIFS) for insulation specified
as part of EIFS finish systems.
7. Division 09 Section Gypsum Board for sound attenuation blankets.
1.2 SUBMITTALS
A. Product Data:
B. LEED Submittals:
1. Product Data for Credit MR 4.1[ and Credit MR 4.2]: For products having recycled
content, documentation indicating percentages by weight of postconsumer and
preconsumer recycled content. Include statement indicating costs for each product
having recycled content.
C. Submittal List:
1. Obtain each type of building insulation from a single source with resources to provide
products complying with requirements indicated without delaying the Work.
A. Protect insulation materials from physical damage and from deterioration by moisture, soiling,
and other sources. Store inside and in a dry location. Comply with manufacturer's written
instructions for handling, storing, and protecting during installation.
1. Protect Plastic Insulation: Do not expose to sunlight, except to extent necessary for
period of installation and concealment.
2. Protect against ignition at all times. Do not deliver plastic insulating materials to Project
site before installation time.
3. Complete installation and concealment of plastic materials as rapidly as possible in each
area of construction.
PART 2 - PRODUCTS
A. General:
1. Provide insulating materials that comply with requirements and with referenced
standards.
B. Preformed Units:
1. ASTM C 578, of type and density indicated below, with maximum flame-spread and
smoke-developed indexes of 75 and 450, respectively:
a. ASTM C 665, Type III (blankets with reflective membrane facing), Class A
(membrane-faced surface with a flame spread index of 25 or less); Category 1
(membrane is a vapor barrier), faced with foil-scrim-kraft, foil-scrim, or foil-scrim-
polyethylene vapor-retarder membrane on 1 face.
A. General
1. Two-component polyurethane spray froth foam air seal utilizing non-ozone depleting,
non-flammable, HFC propellant blowing agent dispensed through a two-component
dispensing unit.
A. Adhesive for Bonding Insulation: Product with demonstrated capability to bond insulation
securely to substrates indicated without damaging insulation and substrates.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions, with Installer present, for compliance with requirements of
Sections in which substrates and related work are specified and to determine if other conditions
affecting performance of insulation are satisfactory. Do not proceed with installation until
unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. General:
A. General:
a. Use blanket widths and lengths that fill cavities formed by framing members.
Where more than one length is required to fill cavity, provide lengths that will
produce a snug fit between ends.
b. Place blankets in cavities formed by framing members to produce a friction fit
between edges of insulation and adjoining framing members.
6. Install appropriate type insulation in cavities created in exterior walls and other typically
insulated areas resulting from construction operations during alterations. Stuff Type 2,
unfaced mineral fiber blanket, insulation into miscellaneous voids and cavity spaces
where required for thermal protection and air-infiltration reduction in exterior walls.
Compact to approximately 40 percent of normal maximum volume equaling a density of
approximately 2.5 lb/cu. ft. Completely fill voids and cavity spaces.
A. General
1. Install air seal at roof deck ribs at top of walls and where indicated.
2. Apply air seal to substrates by spray method indicated, complying with manufacturer's
written instructions.
3. Fill and seal voids to prevent air infiltration.
3.7 PROTECTION
A. Protect installed insulation, air seal, and vapor retarders from damage due to harmful weather
exposures, physical abuse, and other causes. Provide temporary coverings or enclosures
where insulation is subject to abuse and cannot be concealed and protected by permanent
construction immediately after installation.
END OF SECTION
1.1 SUMMARY
A. Section Includes:
1. Walls: Water-drainage exterior insulation and finish system (EIFS) applied over water-
resistive coating over [glass-mat gypsum sheathing] [and] [masonry].
2. Soffits: Exterior insulation and finish system (EIFS) applied over glass-mat gypsum
sheathing.
B. Related Sections:
A. Class PB EIFS:
B. Water-Drainage EIFS:
1. EIFS with a means that allows water entering into an EIFS assembly to drain to the
exterior.
A. Class PB EIFS: Physical properties and structural performance that comply with the
acceptance criteria of ICC-ES AC235.
B. Water-Drainage EIFS: Physical properties, structural performance, and drainage that comply
with ICC-ES AC235.
1.4 SUBMITTALS
A. Product Data:
1. Product Data for Credit EQ 4.1: For adhesives and sealants used inside the
weatherproofing system, including printed statement of VOC content.
1. 24-inch- square panels for each type of finish-coat color and texture indicated, prepared
using same tools and techniques intended for actual work including a typical control joint
filled with sealant of color selected.
2. Include sealant samples to verify color selected.
D. Manufacturer Certificates:
1. Signed by manufacturers certifying that EIFS and joint sealants comply with
requirements.
a. Materials forming joint substrates and joint-sealant backings have been tested for
compatibility and adhesion with joint sealants.
b. Interpretation of test results and written recommendations for primers and
substrate preparation needed for adhesion.
F. Evaluation Reports: For water-resistive coating, code compliance, and EIFS systems (including
insulation), from ICC Evaluation Services, LLC.
H. Submittal List:
A. Installer Qualifications:
B. Source Limitations:
1. Obtain EIFS through one source from a single EIFS manufacturer and from sources
approved by EIFS manufacturer as compatible with system components.
A. Delivery and Handling: Deliver materials in original, unopened packages with manufacturers'
labels intact and clearly identifying products.
B. Storage: Store materials inside and under cover; keep them dry and protected from weather,
direct sunlight, surface contamination, aging, corrosion, damaging temperatures, construction
traffic, and other causes.
1.8 COORDINATION
A. Coordinate installation of EIFS with related Work specified in other Sections to ensure that
assemblies, including sheathing, flashing, trim, joint sealants, windows, and doors, are
protected against damage from the effects of weather, age, corrosion, moisture, and other
causes. Do not allow water to penetrate behind flashing and drainage plane that is behind
water-drainage EIFS.
2.1 MANUFACTURERS
B. Basis-of-Design EIFS Systems: Subject to compliance with requirements, provide one of the
following wall systems:
C. Subject to compliance with requirements, provide one of the following soffit systems:
1. Soffit System:
2.2 MATERIALS
1. Job-mixed formulation of portland cement complying with ASTM C 150, Type I, and
polymer-based adhesive specified for base coat.
2. Factory-blended dry formulation of portland cement, dry polymer admixture, and fillers
specified for base coat.
3. VOC Content of Coatings Used as Insulation Adhesive: 50 g/L or less when calculated
according to 40 CFR 59, Subpart D (EPA Method 24).
E. Molded, Rigid Cellular Polystyrene Board Insulation: Comply with ASTM C 578, Type I; EIFS
manufacturer's requirements; and EIMA's "EIMA Guideline Specification for Expanded
Polystyrene (EPS) Insulation Board" for most stringent requirements for material performance
and qualities of insulation, including dimensions and permissible variations, and the following:
1. Aging: Before cutting and shipping, age insulation in block form by air drying for not less
than six weeks or by another method approved by EIMA that produces equivalent results.
2. Flame-Spread and Smoke-Developed Indexes: 25 and 450 or less, respectively, per
ASTM E 84.
3. Dimensions: Provide insulation boards not more than 24 by 48 inches and in thickness
indicated but not more than 4 inches thick.
4. Channeled Board Insulation: EIFS manufacturer's standard factory-fabricated profile with
linear, vertical drainage channels, slots, or waves on the back side of board.
5. Foam Shapes: Provide with profiles and dimensions indicated on Drawings.
G. Base-Coat Materials:
1. Standard mixture.
2. Job-mixed formulation of portland cement complying with ASTM C 150, Type I, white or
natural color; and manufacturer's standard polymer-emulsion adhesive designed for use
with portland cement.
J. Water: Potable.
K. Trim Accessories:
1. Type as designated or required to suit conditions indicated and to comply with EIFS
manufacturer's written requirements; manufactured from UV-stabilized PVC; and
complying with ASTM D 1784, manufacturer's standard Cell Class for use intended, and
ASTM C 1063.
2. Soffit Trim:
B. Sealant Color:
A. General: Comply with EIFS manufacturer's requirements for combining and mixing materials.
Do not introduce admixtures, water, or other materials except as recommended by EIFS
manufacturer. Mix materials in clean containers. Use materials within time period specified by
EIFS manufacturer or discard.
PART 3 - EXECUTION
3.1 EXAMINATION
A. General:
1. Examine substrates, areas, and conditions, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting performance of
EIFS.
2. Examine roof edges, wall framing, flashings, openings, substrates, and junctures at other
construction for suitable conditions where EIFS will be installed.
3. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. General:
1. Protect contiguous work from moisture deterioration and soiling caused by application of
EIFS. Provide temporary covering and other protection needed to prevent spattering of
exterior finish coats on other work.
2. Protect EIFS, substrates, and wall construction behind them from inclement weather
during installation. Prevent penetration of moisture behind drainage plane of EIFS and
deterioration of substrates.
3. Prepare and clean substrates to comply with EIFS manufacturer's written requirements to
obtain optimum bond between substrate and adhesive for insulation.
A. Comply with EIFS manufacturer's written instructions for installation of EIFS as applicable to
each type of substrate indicated.
B. Water-Resistive Coatings: Apply over substrates of wall systems to protect substrates from
degradation and to provide water-/weather-resistive barrier.
C. Flexible-Membrane Flashing: Install over weather-resistive barrier, applied and lapped to shed
water; seal at openings, penetrations, terminations, and where indicated by EIFS
manufacturer's written instructions to protect wall assembly from degradation. Prime
substrates, if required, and install flashing to comply with EIFS manufacturer's written
instructions and details.
A. Trim: Apply trim accessories at perimeter of EIFS, at expansion joints, and elsewhere as
indicated, according to EIFS manufacturer's written instructions. Coordinate with installation of
insulation.
1. Weep Screed/Track: Use at bottom termination edges, at window and door heads of
water-drainage EIFS unless otherwise indicated.
2. Window Sill Flashing: Use at windows unless otherwise indicated.
3. Expansion Joint: Use where indicated on Drawings.
4. Casing Bead: Use at other locations.
5. Parapet Cap Flashing: Use where indicated on Drawings.
1. Soffit System:
a. Install insulation boards over sheathing with long dimension at right angles to stud
faming.
b. Place channeled insulation with channels aligned in the vertical position for
drainage; align drainage channels with channels in insulation boards above and
below.
c. Apply adhesive to insulation by notched-trowel method resulting in approximately
1/2 by 1/2 inch ribbons 2 inches apart.
d. Apply adhesive ribbons parallel to the short dimension of the insulation board so
that when the board is applied to the sheathing the adhesive ribbons run vertically
creating vertical drainage channels between the water/weather-resistive barrier
and the insulation boards to provide water drainage from behind the insulation
board.
e. Apply adhesive ribbons between the channels on channeled insulation boards.
f. Where trim is not indicated begin first course of insulation from a level base line
and work upward.
g. Where trim is indicated begin first course of insulation from screed/track and work
upward. Work from perimeter casing beads toward interior of panels if possible.
h. Stagger vertical joints of insulation boards in successive courses to produce
running bond pattern. Locate joints so no piece of insulation is less than 12 inches
wide or 6 inches high. Offset joints not less than 6 inches from corners of window
and door openings and not less than 4 inches from aesthetic reveals.
i. Interlock ends at internal and external corners.
j. Coordinate installation of flashing and insulation to produce wall assembly that
does not allow water to penetrate behind flashing and water-/weather-resistive
barrier.
3. Abut insulation tightly at joints within and between each course to produce flush,
continuously even surfaces without gaps or raised edges between boards. If gaps
greater than 1/16 inch occur, fill with insulation cut to fit gaps exactly; insert insulation
without using adhesive or other material.
4. Cut insulation to fit openings, corners, and projections precisely and to produce edges
and shapes complying with details indicated.
5. Rasp or sand flush entire surface of insulation to remove irregularities projecting more
than 1/16 inch from surface of insulation and to remove yellowed areas due to sun
exposure; do not create depressions deeper than 1/16 inch.
6. Cut aesthetic reveals in outside face of insulation with high-speed router and bit
configured to produce grooves, rabbets, and other features that comply with profiles and
locations indicated. Do not reduce insulation thickness at aesthetic reveals to less than
3/4 inch.
7. Install foam shapes and attach to supporting substrate.
8. Interrupt insulation for expansion joints where indicated.
9. Joint-sealant application to base coat: Form joints for sealant application by leaving
gaps between adjoining insulation edges and between insulation edges and dissimilar
adjoining surfaces. Make gaps wide enough to produce joint widths indicated after
encapsulating joint substrates with base coat and reinforcing mesh.
10. Joint-sealant application to casing beads: Form joints for sealant application with back-
to-back casing beads for joints within EIFS and with perimeter casing beads at dissimilar
adjoining surfaces. Make gaps between casing beads and between perimeter casing
beads and adjoining surfaces of width indicated.
11. After installing insulation and before applying field-applied reinforcing mesh, fully wrap
board edges. Cover edges of board and extend encapsulating mesh not less than 2-1/2
a. Except for edges forming substrates of sealant joints, encapsulate with base coat,
reinforcing mesh, and finish coat.
b. Encapsulate edges forming substrates of sealant joints within EIFS or between
EIFS and other work with base coat and reinforcing mesh.
c. At edges trimmed by accessories, extend base coat, reinforcing mesh, and finish
coat over face leg of accessories.
B. Expansion Joints: Install at locations indicated, where required by EIFS manufacturer, and as
follows:
A. General:
B. Reinforcing Mesh: Embed type indicated below in wet base coat to produce wrinkle-free
installation with mesh continuous at corners and overlapped not less than 2-1/2 inches or
otherwise treated at joints to comply with EIFS manufacturer's written instructions. Do not lap
reinforcing mesh within 8 inches of corners. Completely embed mesh, applying additional base-
coat material if necessary, so reinforcing-mesh color and pattern are not visible
C. Additional Reinforcing Mesh: Apply strip reinforcing mesh around openings extending 4 inches
beyond perimeter. Apply additional 9-by-12-inch strip reinforcing mesh diagonally at corners of
openings (re-entrant corners). Apply 8-inch- wide strip reinforcing mesh at both inside and
outside corners unless base layer of mesh is lapped not less than 4 inches on each side of
corners.
1. At aesthetic reveals, apply strip reinforcing mesh not less than 8 inches wide.
2. Embed strip reinforcing mesh in base coat before applying first layer of reinforcing mesh.
E. Double Base-Coat Application: Where indicated, apply second base coat in same manner and
thickness as first application except without reinforcing mesh. Do not apply until first base coat
has cured.
A. Primer: Apply over dry base coat according to EIFS manufacturer's written instructions.
B. Finish Coat: Apply over dry primed base coat, maintaining a wet edge at all times for uniform
appearance, in thickness required by EIFS manufacturer to produce a uniform finish of color
and texture matching approved sample and free of cold joints, shadow lines, and texture
variations
A. Prepare joints and apply sealants, of kind and at locations indicated, to comply with applicable
requirements in Division 07 Section Joint Sealants and in ASTM C 1481
1. Unless otherwise required by EIFS manufacturer, apply joint sealants after base coat has
cured but before applying finish coat. Unless otherwise required by EIFS manufacturer,
provide recessed joint configuration per Figure 3 in ASTM C 1481. If casing beads are
used to form joints install sealant after applying finish coat.
2. Clean surfaces to receive sealants to comply with indicated requirements and EIFS
manufacturer's written instructions.
3. Apply primer recommended in writing by sealant manufacturer for surfaces to be sealed.
4. Install sealant backing to control depth and configuration of sealant joint and to prevent
sealant from adhering to back of joint.
5. Apply masking tape to protect areas adjacent to sealant joints. Remove tape
immediately after tooling joints, without disturbing joint seal.
6. Recess sealant sufficiently from surface of EIFS so an additional sealant application,
including cylindrical sealant backing, can be installed without protruding beyond EIFS
surface.
A. General
1. Field quality control shall be in accordance with the Quality Control Plan.
2. Special Inspections: Engage a qualified special inspector to perform special inspections
of the water-resistive barrier coating [except at masonry walls].
1. Perform special inspections of the water-resistive barrier coating to ensure that ambient
conditions at time of installation of water-resistive barrier coating were within acceptable
range, installation sequences were followed, and coating meets requirements.
C. Remove and replace water-resistive barrier coating where inspection results indicate that the
water-resistive barrier coating does not comply with specified requirements.
A. Remove temporary covering and protection of other work. Promptly remove coating materials
from window and door frames and other surfaces outside areas indicated to receive EIFS
coatings.
END OF SECTION
DESIGN CRITERIA
2. This Section specifies Class PB water-drainage exterior insulation and finish system (EIFS) for walls
consisting of an inner layer of rigid cellular thermal board insulation, an integrally reinforced base
coat, and a textured protective finish coat. EIFS shall be applied over glass-mat gypsum sheathing or
masonry with moisture protection barrier. Provide additional base coat impact resistant reinforcing
on wall surfaces below 8'-0" A.F.F.
A. Where high wind-load capacity is a design consideration, consult the product manufacturer for
limitations of product specified and recommendations for alternative systems.
3. This Section includes Class PB exterior insulation and finish system (EIFS) for soffits. Where both
water drainage wall systems and soffit systems are used in the design, channeled board insulation
may be used in soffit systems if acceptable, in writing, to the EIFS manufacturer.
4. This Section does not specify direct-applied exterior finish systems (DEFS), i.e., EIFS without an
insulation component.
5. It is recommended that EIFS not be used on exterior wall surfaces in receiving areas. Solid masonry
and concrete wall surfaces should be considered for attachment of loading dock equipment (i.e., dock
seals, dock hoods, etc.) and overhead receiving doors. Durability of wall surfaces is a major concern
in these areas.
A. Before retaining manufactures names, verify that their systems comply with project building
codes and other requirements. Manufacturers and/or system evaluation reports may prohibit
their use as soffit panels.
END OF SECTION
June 2011 07 24 00 1
DeCA DESIGN CRITERIA HANDBOOK
07 40 00 METAL PANELS
DESIGN CRITERIA
1. Related Sections: See Division 05 Section Cold-Formed Metal Framing for secondary support
framing, including roof rafters, purlins, and ceiling joists. See Division 07 Section Sheet Metal Flashing
And Trim for flashing and other sheet metal work that is not part of metal roof or wall panel
assemblies.
2. This Section specifies factory-formed and field-assembled standing-seam metal roof panels, glass-
mat gypsum sheathing panels, concealed-fastener, metal wall panels, and concealed-fastener, metal
soffit panels.
3. UFC 3-600-01 does not allow the use of fire retardant treated plywood as part of a roof or roofing
system. Guide specification Division 07 Section Metal Panels requires the use of glass-mat gypsum
sheathing panels for metal panel assemblies.
END OF SECTION
June 2011 07 40 00 1
SECTION 07 40 00
METAL PANELS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 05 Section Steel Decking for steel roof deck supporting metal roof panels.
2. Division 05 Section Cold-Formed Metal Framing for cold-formed metal framing supporting
metal panels.
3. Division 07 Section Sheet Metal Flashing and Trim for field-formed roof drainage
systems, and other sheet metal work not part of metal roof panel assemblies.
A. General:
1. Provide metal roof panel assemblies that comply with performance requirements
specified as determined by testing manufacturers' standard assemblies similar to those
indicated for this Project, by a qualified testing and inspecting agency.
B. Water Penetration:
1. No water penetration of standing seam metal roof panels when tested according to
ASTM E 1646 at the following test-pressure difference:
C. Wind-Uplift Resistance:
1. Provide metal roof panel assemblies that comply with UL 580 for wind-uplift resistance
class indicated.
D. FMG Listing:
1. Provide metal roof panels and component materials that comply with requirements in
FMG 4471 as part of a panel roofing system and that are listed in FMG's "Approval
Guide" for Class 1 or noncombustible construction, as applicable. Identify materials with
FMG markings.
E. Structural Performance:
1. Provide metal roof panel assemblies (including sheathing) capable of withstanding the
effects of gravity loads and the following loads and stresses within limits and under
conditions indicated, based on testing according to ASTM E 1592.
a. Wind Loads: Refer to Division 01 Section Summary of Work for wind loading
design criteria.
F. Seismic Performance:
1. Provide metal panel assemblies capable of resisting the effects of earthquake motions.
2. Refer to Division 01 Section Summary of Work for seismic-load design criteria.
3. Determine seismic loads using the appropriate exposure coefficient for the metal panel
assemblies.
G. Thermal Movements:
1. Provide metal panel assemblies that allow for thermal movements resulting from the
following maximum change (range) in ambient and surface temperatures by preventing
buckling, opening of joints, overstressing of components, failure of joint sealants, failure
of connections, and other detrimental effects. Base engineering calculation on surface
temperatures of materials due to both solar heat gain and nighttime-sky heat loss.
a. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces.
1.3 SUBMITTALS
A. Product Data:
1. Show layouts of metal panels, including plans, elevations, sections, details, and
attachments to other work.
2. Include details of edge conditions, joints, panel profiles, corners, anchorages, trim,
flashings, closures, and accessories.
C. Samples:
D. Submittal List:
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Aluminum Sheet: Coil-coated sheet, ASTM B 209, alloy as standard with manufacturer, with
temper as required to suit forming operations and structural performance required.
B. Panel Sealants:
1. Joint Sealant: ASTM C 920; elastomeric silicone sealant; of type, grade, class, and use
classifications required to seal joints in metal roof panels and remain weathertight; and as
recommended in writing by metal roof panel manufacturer.
B. Substrate-Board Fasteners:
1. Factory-coated steel fasteners and metal or plastic plates complying with corrosion-
resistance provisions in FMG 4470, designed for fastening substrate board to substrate.
A. General:
1. Complying with ASTM C 645 requirements for metal and with ASTM A 653/A 653M, G60,
hot-dip galvanized zinc coating.
1. ASTM C 645.
2. Minimum Base Metal Thickness: 0.0312 inch.
3. Depth: 7/8 inch.
1. Of type, material, size, corrosion resistance, holding power, and other properties required
to fasten steel members to substrates.
1. Self-tapping screws, bolts, nuts, self-locking rivets and bolts, end-welded studs, and other
suitable fasteners designed to withstand design loads. Provide exposed fasteners with
heads matching color of metal panels by means of plastic caps or factory-applied coating.
B. Bituminous Coating:
1. Cold-applied asphalt mastic, SSPC-Paint 12, compounded for 15-mil dry film thickness
per coat. Provide inert-type noncorrosive compound free of asbestos fibers, sulfur
components, and other deleterious impurities.
1. Provide components required for a complete metal roof panel assembly including trim,
fasciae, corner units, clips, flashings, sealants, gaskets, fillers, closure strips, and similar
items. Match material and finish of metal roof panels, unless otherwise indicated.
2. Closures: Provide closures at eaves fabricated of same metal as metal roof panels.
3. Clips: Floating to accommodate thermal movement. Manufacturers standard panel clips
designed to withstand negative-load requirements.
4. Cleats: Mechanically seamed cleats formed from minimum 0.0250-inch- thick, stainless-
steel or nylon-coated aluminum sheet.
1. Factory-formed, with vertical panel edges and flat pan between panel edges; with flush
joint between panels designed to be field assembled by lapping and interconnecting side
edges of adjacent panels and mechanically attaching through panel to supports using
concealed fasteners. Include accessories required for weathertight installation.
2. Basis-of-Design Product: Peterson Aluminum Corporation, "Flush Panel."
3. Material: Aluminum-zinc alloy-coated steel sheet, 0.032-inchnominal thickness.
1. Provide components required for a complete metal wall panel assembly including trim,
fasciae, corner units, clips, flashings, sealants, gaskets, fillers, and similar items. Match
material and finish of metal wall panels, unless otherwise indicated.
2. Closures: Provide closures at eaves, fabricated of same metal as metal wall panels.
1. Perforated panels formed with vertical panel edges and flat pan between panel edges;
with V-groove joint between panels.
2. Basis-of-Design Product: Peterson Aluminum Corporation, "PAC-850."
2.10 FABRICATION
1. Fabricate and finish metal panels and accessories at the factory to greatest extent
possible, by manufacturer's standard procedures and processes, as necessary to fulfill
indicated performance requirements demonstrated by laboratory testing. Comply with
indicated profiles and with dimensional and structural requirements.
2. Provide panel profile, including major ribs and intermediate stiffening ribs, if any, for full
length of panel.
3. Where indicated, fabricate metal panel joints with factory-installed captive gaskets or
separator strips that provide a tight seal and prevent metal-to-metal contact, in a manner
that will minimize noise from movements within panel assembly.
4. Sheet Metal Accessories: Fabricate flashing and trim to comply with recommendations in
SMACNA's "Architectural Sheet Metal Manual" that apply to the design, dimensions,
metal, and other characteristics of item indicated.
5. Protect mechanical and painted finishes on exposed surfaces from damage by applying a
strippable, temporary protective covering before shipping.
PART 3 - EXECUTION
3.1 EXAMINATION
A. General:
1. Examine substrates, areas, and conditions, with Installer present, for compliance with
requirements for installation tolerances, metal roof panel supports, and other conditions
affecting performance of the Work.
2. Examine roughing-in for components and systems penetrating metal roof panels to verify
actual locations of penetrations relative to seam locations of metal roof panels before
metal roof panel installation.
3. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. General:
a. Install substrate board with long joints in continuous straight lines, perpendicular to
roof slopes with end joints staggered between rows. Tightly butt substrate boards
together.
3. Miscellaneous Framing: Install eave angles, furring, and other miscellaneous panel
support members and anchorage according to manufacturer's written instructions.
a. Soffit Framing: Wire tie or clip furring channels to supports, as required to comply
with requirements for assemblies indicated.
A. Felt Underlayment:
1. Install felt underlayment on substrate boards. Use adhesive for temporary anchorage.
Apply in shingle fashion to shed water, with lapped joints of not less than 2 inches.
1. Fasten metal roof panels to supports with concealed clips at each standing-seam joint at
location, spacing, and with fasteners recommended by manufacturer.
2. Install clips to supports with self-tapping fasteners.
3. Snap Joint: Nest standing seams and fasten together by interlocking and completely
engaging factory-applied sealant.
4. Provide metal roof panels of full length from eave to wall. Anchor metal roof panels and
other components of the Work securely in place, with provisions for thermal and
structural movement.
1. Fasten metal wall panels to supports with fasteners at each lapped joint at location and
spacing recommended by manufacturer.
2. Provide sealant tape at lapped joints of metal wall panels and between panels and
protruding equipment, vents, and accessories.
5. Apply elastomeric sealant continuously between metal base channel (sill angle) and
concrete, and elsewhere as indicated or, if not indicated, as necessary for waterproofing.
6. Provide weatherproof escutcheons for pipe and conduit penetrating exterior walls.
1. Provide metal soffit panels full width of soffits. Install panels perpendicular to support
framing.
2. Flash and seal panels with weather closures where metal soffit panels meet walls and at
perimeter of all openings.
D. Fasteners:
1. Use stainless-steel fasteners for surfaces exposed to the exterior and galvanized steel
fasteners for surfaces exposed to the interior.
E. Metal Protection:
1. Where dissimilar metals will contact each other or corrosive substrates, protect against
galvanic action by painting contact surfaces with bituminous coating, by applying
rubberized-asphalt underlayment to each contact surface, or by other permanent
separation as recommended by metal roof panel manufacturer.
F. Joint Sealers:
1. Install gaskets, joint fillers, and sealants where indicated and where required for
weatherproof performance of metal roof panel assemblies.
2. Prepare joints and apply sealants to comply with requirements in Division 07 Section
Joint Sealants.
A. Install accessories with positive anchorage to building and weathertight mounting and provide
for thermal expansion. Coordinate installation with flashings and other components.
B. Install components required for a complete metal panel assembly including trim, seam covers,
flashings, sealants, gaskets, fillers, closure strips, and similar items.
A. Remove temporary protective coverings and strippable films, if any, as metal panels are
installed, unless otherwise indicated in manufacturer's written installation instructions. On
completion of metal panel installation, clean finished surfaces as recommended by metal panel
manufacturer. Maintain in a clean condition during construction. After metal wall panel
installation, clear weep holes and drainage channels of obstructions, dirt, and sealant.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 07 Section Sheet Metal Flashing and Trim for shop- or field-fabricated
sheet metal copings, fasciae, gravel stops, flashing receivers, equipment support flashings, roof
penetration flashings, and counter-flashings.
2. This Section specifies fully adhered EPDM black membrane roofing systems including roof insulation,
base flashings, walkways, and auxiliary roofing materials.
A. The basis-of-design system specified is for installation over metal decking mechanically
fastened through a top layer of roof insulation and secured to the metal decking for buildings
and other structures located where the basic design wind speed (3-second gust) does not
exceed 90 mph as indicated in Table C, Appendix C, UFC 3-310-01, 25 May, 2005 including
Change 2, 5 December 2007.
B. For locations where the design wind speed is greater than 90 mph, a top layer of cover board
membrane underlayment is required in accordance with the membrane roofing system
manufacturer. The membrane underlayment shall not be fire retardant treated (FRT) plywood
(article 2-13, UFC 3-600-01, 14 July 2009).
3. Provide insulation materials with a total minimum Long Term Thermal Resistance (LTTR) R-value of
20, unless climatic conditions or local Installation energy code requirements dictate a higher R-value.
Current Federal Energy Reduction Mandates may require the use of increased insulation
thicknesses. This will be determined through energy usage calculations prepared as part of project
development.
4. Design roof slope in accordance with roofing manufacturer's recommendations, but no less than 1/4"
per foot to interior drains using roof structure for slopes. Achieving roof slope with insulation is not
acceptable, except at drainage crickets, preformed saddles, tapered edge strips, and perimeter edge
strips.
5. Keep interior vertical drops from roof drains to a minimum, combining when practical and locating
them in concealed void spaces and storage areas. Do not locate exposed within customer areas.
6. If appropriate, locate overflow roof drains adjacent to normal roof drains with overflow outlets
exposed on exterior wall of building.
7. Provide access to roof for equipment maintenance via ships ladder and roof hatch from mechanical
equipment mezzanine, or stair tower from ground floor of building with standard steel door and frame
roof access to roof.
8. Indicate roof walkways necessary to access roof mounted equipment requiring maintenance.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 07 Section Sheet Metal Flashing and Trim for sheet metal flashing and trim
integral with membrane roofing.
2. Division 07 Section Roof Specialties for wind resistive metal flashing and trim integral
with membrane roofing.
1.2 DEFINITIONS
A. Roofing Terminology: Refer to ASTM D 1079 and glossary of NRCA's "The NRCA Roofing and
Waterproofing Manual" for definition of terms related to roofing work in this Section.
A. General:
1. Provide installed roofing membrane and base flashings that remain watertight; do not
permit the passage of water; and resist specified uplift pressures, thermally induced
movement, and exposure to weather without failure.
B. Material Compatibility:
1. Provide roofing materials that are compatible with one another under conditions of
service and application required, as demonstrated by roofing membrane manufacturer
based on testing and field experience.
1. Provide a membrane roofing system that is identical to systems that have been
successfully tested by a qualified testing and inspecting agency to either resist uplift
pressure calculated according to ASCE/SEI 7 or in accordance with membrane
manufactures written fastening density instructions, whichever is more resistive to wind
load indicated.
1.4 SUBMITTALS
A. Product Data:
B. LEED Submittals:
1. Product Test Reports for Credit SS 7.2: For roof materials, documentation indicating that
roof materials comply with Solar Reflectance Index requirement.
C. Shop Drawings:
1. For roofing system. Include plans, elevations, sections, details, and attachments to other
Work.
2. Base flashings and membrane terminations.
3. Tapered insulation, including slopes.
4. Insulation fastening patterns.
D. Installer Certificates:
E. Manufacturer Certificates:
1. Signed by roofing manufacturer certifying that roofing system complies with requirements
specified in "Performance Requirements" Article.
2. Submit evidence of meeting performance requirements. Include the following roofing
system design considerations:
G. Maintenance Data:
H. Warranties:
I. Inspection Report:
J. Submittal List:
A. Installer Qualifications:
B. Manufacturer Qualifications:
1. A qualified manufacturer that has UL listing approval for membrane roofing system
identical to that used for this Project.
C. Source Limitations:
1. Obtain components for membrane roofing system from same manufacturer as roofing
membrane.
a. Exterior Fire-Test Exposure: Class A; ASTM E 108, for application and roof slopes
indicated.
1. Before starting roof deck construction, conduct conference at Project site. Comply with
requirements for preinstallation conferences in Division 01 Section Administrative
Requirements. Review methods and procedures related to roof deck construction and
roofing system including, but not limited to, the following:
F. Preinstallation Conference:
A. Delivery:
1. Deliver roofing materials to Project site in original containers with seals unbroken and
labeled with manufacturer's name, product brand name and type, date of manufacture,
and directions for storing and mixing with other components.
1. Store liquid materials in their original undamaged containers in a clean, dry, protected
location and within the temperature range required by roofing system manufacturer.
Protect stored liquid material from direct sunlight.
2. Discard and legally dispose of liquid material that cannot be applied within its stated shelf
life.
3. Protect roof insulation materials from physical damage and from deterioration by sunlight,
moisture, soiling, and other sources. Store in a dry location. Comply with insulation
manufacturer's written instructions for handling, storing, and protecting during installation.
4. Handle and store roofing materials and place equipment in a manner to avoid permanent
deflection of deck.
A. Weather Limitations:
1. Proceed with installation only when existing and forecasted weather conditions permit
roofing system to be installed according to manufacturer's written instructions and
warranty requirements.
1.8 WARRANTY
A. Special Warranty:
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Membrane Materials:
1. ASTM D 4637, Type I, nonreinforced uniform, flexible sheet made from EPDM, and as
follows:
A. General:
a. Insulation/underlayment.
b. Insulation attachment materials and method.
c. Membrane bonding adhesive.
2. Liquid-type auxiliary materials shall meet VOC limits of authorities having jurisdiction.
B. Sheet Flashing:
E. Lap Sealant:
H. Fasteners:
I. Miscellaneous Accessories:
1. Provide pourable sealers, preformed cone and vent sheet flashings, preformed inside
and outside corner sheet flashings, reinforced EPDM securement strips, T-joint covers,
in-seam sealants, termination reglets, cover strips, and other accessories.
A. General:
1. Provide preformed roof insulation boards that comply with requirements and referenced
standards, selected from manufacturer's standard sizes and of thicknesses indicated.
2. Provide insulation materials complying with a total minimum Long Term Thermac
Resistance (LTTR) R-value of 30 minimum, per ASTM C 1289 and CAN/ULC.
1. ASTM C 1289, Type II, Class 1, Grade 2 or 3, felt or glass-fiber mat facer on both major
surfaces.
C. Tapered Insulation:
1. Provide preformed saddles, crickets, tapered edge strips, and other insulation shapes
where indicated for sloping to drain. Provide factory-tapered insulation boards fabricated
to slope of 1/4 inch per 12 inches unless otherwise indicated.
1. Provide preformed saddles, crickets, tapered edge strips, and other insulation shapes
where indicated for sloping to drain. Fabricate to slopes indicated.
A. General:
B. Fasteners:
1. Factory-coated steel fasteners and metal or plastic plates complying with corrosion-
resistance provisions in FM Approvals 4470, designed for fastening roof insulation[ and
cover boards] to substrate, and acceptable to roofing system manufacturer.
C. Cover Board:
D. Insulation Adhesive:
2.6 WALKWAYS
A. Flexible Walkways:
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with the
following requirements and other conditions affecting performance of roofing system:
1. Verify that roof openings and penetrations are in place and set and braced and that roof
drains are securely clamped in place.
2. Verify that wood blocking, curbs, and nailers are securely anchored to roof deck at
penetrations and terminations and that nailers match thicknesses of insulation.
3. Verify that surface plane flatness and fastening of steel roof deck complies with
requirements in Division 05 Section Steel Decking.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. General:
1. Clean substrate of dust, debris, moisture, and other substances detrimental to roofing
installation according to roofing system manufacturer's written instructions. Remove
sharp projections.
2. Prevent materials from entering and clogging roof drains and conductors and from spilling
or migrating onto surfaces of other construction. Remove roof-drain plugs when no work
is taking place or when rain is forecast.
3. Complete terminations and base flashings and provide temporary seals to prevent water
from entering completed sections of roofing system at the end of the workday or when
rain is forecast. Remove and discard temporary seals before beginning work on
adjoining roofing.
A. General:
B. Adhered Insulation:
1. Install each layer of insulation and adhere to substrate in lieu of membrane roofing
system manufacturers mechanical fasteners when approved in writing by membrane
roofing system manufacturer.
C. Cover Boards:
1. Install cover boards over insulation with long joints in continuous straight lines with end
joints staggered between rows. Offset joints of insulation below a minimum of 6 inches in
each direction. Loosely butt cover boards together.
1. Install and secure insulation [and cover boards] to deck in accordance with warranty
requirements using mechanical fasteners specifically designed and sized for fastening
specified board-type roof insulation to deck type.
2. Fasten insulation [and cover boards] to resist uplift pressure at corners, perimeter, and
field of roof in accordance with performance and warranty requirements.
A. General:
1. Install roofing membrane over area to receive roofing according to membrane roofing
system manufacturer's written instructions. Unroll roofing membrane and allow to relax
before installing.
2. Start installation of roofing membrane in presence of membrane roofing system
manufacturer's technical personnel.
3. Accurately align roofing membrane and maintain uniform side and end laps of minimum
dimensions required by manufacturer. Stagger end laps.
4. Bonding Adhesive: Apply bonding adhesive to substrate and underside of roofing
membrane at rate required by manufacturer and allow to partially dry before installing
roofing membrane. Do not apply bonding adhesive to splice area of roofing membrane.
5. Mechanically or adhesively fasten roofing membrane securely at terminations,
penetrations, and perimeter of roofing.
6. Apply roofing membrane with side laps shingled with slope of roof deck where possible.
7. Tape Seam Installation: Clean and prime both faces of splice areas, apply splice tape,
and firmly roll side and end laps of overlapping roofing membranes according to
A. General:
1. Install sheet flashings and preformed flashing accessories and adhere to substrates
according to membrane roofing system manufacturer's written instructions.
2. Apply bonding adhesive to substrate and underside of sheet flashing at required rate and
allow to partially dry. Do not apply bonding adhesive to seam area of flashing.
3. Flash penetrations and field-formed inside and outside corners with cured or uncured
sheet flashing.
4. Clean splice areas, apply splicing cement, and firmly roll side and end laps of overlapping
sheets to ensure a watertight seam installation. Apply lap sealant and seal exposed
edges of sheet flashing terminations.
5. Terminate and seal top of sheet flashings and mechanically anchor to substrate through
termination bars.
A. Flexible Walkways: Install walkway products in locations indicated or, if not indicated, from roof
access indicated to and around roof-mounted mechanical equipment. Adhere walkway
products to substrate according to roofing system manufacturer's written instructions. Space
walkway pads one-inch apart to permit drainage. Discontinue walkways over all field splices to
provide a minimum one-inch gap over the seam edge.
2. Repair or remove and replace components of membrane roofing system where test
results or inspections indicate that they do not comply with specified requirements.
3. Additional testing and inspecting, at Contractor's expense, will be performed to determine
compliance of replaced or additional work with specified requirements.
A. Protection:
1. Protect membrane roofing system from damage and wear during remainder of
construction period. When remaining construction will not affect or endanger roofing,
B. Correction:
1. Correct deficiencies in or remove membrane roofing system that does not comply with
requirements, repair substrates and repair or reinstall membrane roofing system to a
condition free of damage and deterioration at time of final acceptance and according to
warranty requirements.
C. Cleaning:
1. Clean overspray and spillage from adjacent construction using cleaning agents and
procedures recommended by manufacturer of affected construction.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 07 Section Sheet Metal Flashing and Trim for shop- or field-fabricated
sheet metal copings, fasciae, gravel stops, flashing receivers, equipment support flashings, roof
penetration flashings, and counter-flashings.
2. This Section specifies fully adhered EPDM white membrane roofing systems including roof insulation,
base flashings, walkways, and auxiliary roofing materials.
A. The basis-of-design system specified is for installation over metal decking mechanically
fastened through a top layer of roof insulation and secured to the metal decking for buildings
and other structures located where the basic design wind speed (3-second gust) does not
exceed 90 mph as indicated in Table C, Appendix C, UFC 3-310-01, 25 May, 2005 including
Change 2, 5 December 2007.
B. For locations where the design wind speed is greater than 90 mph, a top layer of cover board
membrane underlayment is required in accordance with the membrane roofing system
manufacturer. The membrane underlayment shall not be fire retardant treated (FRT) plywood
(article 2-13, UFC 3-600-01, 14 July 2009).
3. Provide insulation materials with a total minimum Long Term Thermal Resistance (LTTR) R-value of
20, unless climatic conditions or local Installation energy code requirements dictate a higher R-value.
Current Federal Energy Reduction Mandates may require the use of increased insulation
thicknesses. This will be determined through energy usage calculations prepared as part of project
development.
4. Design roof slope in accordance with roofing manufacturer's recommendations, but no less than 1/4"
per foot to interior drains using roof structure for slopes. Achieving roof slope with insulation is not
acceptable, except at drainage crickets, preformed saddles, tapered edge strips, and perimeter edge
strips.
5. Keep interior vertical drops from roof drains to a minimum, combining when practical and locating
them in concealed void spaces and storage areas. Do not locate exposed within customer areas.
6. If appropriate, locate overflow roof drains adjacent to normal roof drains with overflow outlets
exposed on exterior wall of building.
7. Provide access to roof for equipment maintenance via ships ladder and roof hatch from mechanical
equipment mezzanine, or stair tower from ground floor of building with standard steel door and frame
roof access to roof.
8. Indicate roof walkways necessary to access roof mounted equipment requiring maintenance.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 07 Section Sheet Metal Flashing and Trim for sheet metal flashing and trim
integral with membrane roofing.
2. Division 07 Section Roof Specialties for wind resistive metal flashing and trim integral
with membrane roofing.
1.2 DEFINITIONS
A. Roofing Terminology: Refer to ASTM D 1079 and glossary of NRCA's "The NRCA Roofing and
Waterproofing Manual" for definition of terms related to roofing work in this Section.
A. General:
1. Provide installed roofing membrane and base flashings that remain watertight; do not
permit the passage of water; and resist specified uplift pressures, thermally induced
movement, and exposure to weather without failure.
B. Material Compatibility:
1. Provide roofing materials that are compatible with one another under conditions of
service and application required, as demonstrated by roofing membrane manufacturer
based on testing and field experience.
1. Provide a membrane roofing system that is identical to systems that have been
successfully tested by a qualified testing and inspecting agency to either resist uplift
pressure calculated according to ASCE/SEI 7 or in accordance with membrane
manufactures written fastening density instructions, whichever is more resistive to wind
load indicated.
1.4 SUBMITTALS
A. Product Data:
B. LEED Submittals:
1. Product Test Reports for Credit SS 7.2: For roof materials, documentation indicating that
roof materials comply with Solar Reflectance Index requirement.
C. Shop Drawings:
1. For roofing system. Include plans, elevations, sections, details, and attachments to other
Work.
2. Base flashings and membrane terminations.
3. Tapered insulation, including slopes.
4. Insulation fastening patterns.
D. Installer Certificates:
E. Manufacturer Certificates:
1. Signed by roofing manufacturer certifying that roofing system complies with requirements
specified in "Performance Requirements" Article.
2. Submit evidence of meeting performance requirements. Include the following roofing
system design considerations:
G. Maintenance Data:
H. Warranties:
I. Inspection Report:
J. Submittal List:
A. Installer Qualifications:
B. Manufacturer Qualifications:
1. A qualified manufacturer that has UL listing approval for membrane roofing system
identical to that used for this Project.
C. Source Limitations:
1. Obtain components for membrane roofing system from same manufacturer as roofing
membrane.
a. Exterior Fire-Test Exposure: Class A; ASTM E 108, for application and roof slopes
indicated.
1. Before starting roof deck construction, conduct conference at Project site. Comply with
requirements for preinstallation conferences in Division 01 Section Administrative
Requirements. Review methods and procedures related to roof deck construction and
roofing system including, but not limited to, the following:
F. Preinstallation Conference:
A. Delivery:
1. Deliver roofing materials to Project site in original containers with seals unbroken and
labeled with manufacturer's name, product brand name and type, date of manufacture,
and directions for storing and mixing with other components.
1. Store liquid materials in their original undamaged containers in a clean, dry, protected
location and within the temperature range required by roofing system manufacturer.
Protect stored liquid material from direct sunlight.
2. Discard and legally dispose of liquid material that cannot be applied within its stated shelf
life.
3. Protect roof insulation materials from physical damage and from deterioration by sunlight,
moisture, soiling, and other sources. Store in a dry location. Comply with insulation
manufacturer's written instructions for handling, storing, and protecting during installation.
4. Handle and store roofing materials and place equipment in a manner to avoid permanent
deflection of deck.
A. Weather Limitations:
1. Proceed with installation only when existing and forecasted weather conditions permit
roofing system to be installed according to manufacturer's written instructions and
warranty requirements.
1.8 WARRANTY
A. Special Warranty:
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Membrane Materials:
1. ASTM D 4637, Type I, nonreinforced uniform, flexible sheet made from EPDM, and as
follows:
A. General:
a. Insulation/underlayment.
b. Insulation attachment materials and method.
c. Membrane bonding adhesive.
2. Liquid-type auxiliary materials shall meet VOC limits of authorities having jurisdiction.
B. Sheet Flashing:
E. Lap Sealant:
H. Fasteners:
I. Miscellaneous Accessories:
1. Provide pourable sealers, preformed cone and vent sheet flashings, preformed inside
and outside corner sheet flashings, reinforced EPDM securement strips, T-joint covers,
in-seam sealants, termination reglets, cover strips, and other accessories.
A. General:
1. Provide preformed roof insulation boards that comply with requirements and referenced
standards, selected from manufacturer's standard sizes and of thicknesses indicated.
2. Provide insulation materials complying with a total minimum Long Term Thermac
Resistance (LTTR) R-value of 20 minimum, per CAN/ULC test method.
1. ASTM C 1289, Type II, Class 1, Grade 2 or 3, felt or glass-fiber mat facer on both major
surfaces.
C. Tapered Insulation:
1. Provide preformed saddles, crickets, tapered edge strips, and other insulation shapes
where indicated for sloping to drain. Provide factory-tapered insulation boards fabricated
to slope of 1/4 inch per 12 inchesunless otherwise indicated.
1. Provide preformed saddles, crickets, tapered edge strips, and other insulation shapes
where indicated for sloping to drain. Fabricate to slopes indicated.
A. General:
B. Fasteners:
1. Factory-coated steel fasteners and metal or plastic plates complying with corrosion-
resistance provisions in FM Approvals 4470, designed for fastening roof insulation[ and
cover boards] to substrate, and acceptable to roofing system manufacturer.
C. Cover Board:
D. Insulation Adhesive:
2.6 WALKWAYS
A. Flexible Walkways:
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with the
following requirements and other conditions affecting performance of roofing system:
1. Verify that roof openings and penetrations are in place and set and braced and that roof
drains are securely clamped in place.
2. Verify that wood blocking, curbs, and nailers are securely anchored to roof deck at
penetrations and terminations and that nailers match thicknesses of insulation.
3. Verify that surface plane flatness and fastening of steel roof deck complies with
requirements in Division 05 Section Steel Decking.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. General:
1. Clean substrate of dust, debris, moisture, and other substances detrimental to roofing
installation according to roofing system manufacturer's written instructions. Remove
sharp projections.
2. Prevent materials from entering and clogging roof drains and conductors and from spilling
or migrating onto surfaces of other construction. Remove roof-drain plugs when no work
is taking place or when rain is forecast.
3. Complete terminations and base flashings and provide temporary seals to prevent water
from entering completed sections of roofing system at the end of the workday or when
rain is forecast. Remove and discard temporary seals before beginning work on
adjoining roofing.
A. General:
B. Adhered Insulation:
1. Install each layer of insulation and adhere to substrate in lieu of membrane roofing
system manufacturers mechanical fasteners when approved in writing by membrane
roofing system manufacturer.
C. Cover Boards:
1. Install cover boards over insulation with long joints in continuous straight lines with end
joints staggered between rows. Offset joints of insulation below a minimum of 6 inches in
each direction. Loosely butt cover boards together.
1. Install and secure insulation [and cover boards] to deck in accordance with warranty
requirements using mechanical fasteners specifically designed and sized for fastening
specified board-type roof insulation to deck type.
2. Fasten insulation [and cover boards] to resist uplift pressure at corners, perimeter, and
field of roof in accordance with performance and warranty requirements.
A. General:
1. Install roofing membrane over area to receive roofing according to membrane roofing
system manufacturer's written instructions. Unroll roofing membrane and allow to relax
before installing.
2. Start installation of roofing membrane in presence of membrane roofing system
manufacturer's technical personnel.
3. Accurately align roofing membrane and maintain uniform side and end laps of minimum
dimensions required by manufacturer. Stagger end laps.
4. Bonding Adhesive: Apply bonding adhesive to substrate and underside of roofing
membrane at rate required by manufacturer and allow to partially dry before installing
roofing membrane. Do not apply bonding adhesive to splice area of roofing membrane.
5. Mechanically or adhesively fasten roofing membrane securely at terminations,
penetrations, and perimeter of roofing.
6. Apply roofing membrane with side laps shingled with slope of roof deck where possible.
7. Tape Seam Installation: Clean and prime both faces of splice areas, apply splice tape,
and firmly roll side and end laps of overlapping roofing membranes according to
A. General:
1. Install sheet flashings and preformed flashing accessories and adhere to substrates
according to membrane roofing system manufacturer's written instructions.
2. Apply bonding adhesive to substrate and underside of sheet flashing at required rate and
allow to partially dry. Do not apply bonding adhesive to seam area of flashing.
3. Flash penetrations and field-formed inside and outside corners with cured or uncured
sheet flashing.
4. Clean splice areas, apply splicing cement, and firmly roll side and end laps of overlapping
sheets to ensure a watertight seam installation. Apply lap sealant and seal exposed
edges of sheet flashing terminations.
5. Terminate and seal top of sheet flashings and mechanically anchor to substrate through
termination bars.
A. Flexible Walkways: Install walkway products in locations indicated or, if not indicated, from roof
access indicated to and around roof-mounted mechanical equipment. Adhere walkway
products to substrate according to roofing system manufacturer's written instructions. Space
walkway pads one-inch apart to permit drainage. Discontinue walkways over all field splices to
provide a minimum one-inch gap over the seam edge.
2. Repair or remove and replace components of membrane roofing system where test
results or inspections indicate that they do not comply with specified requirements.
3. Additional testing and inspecting, at Contractor's expense, will be performed to determine
compliance of replaced or additional work with specified requirements.
A. Protection:
1. Protect membrane roofing system from damage and wear during remainder of
construction period. When remaining construction will not affect or endanger roofing,
B. Correction:
1. Correct deficiencies in or remove membrane roofing system that does not comply with
requirements, repair substrates and repair or reinstall membrane roofing system to a
condition free of damage and deterioration at time of final acceptance and according to
warranty requirements.
C. Cleaning:
1. Clean overspray and spillage from adjacent construction using cleaning agents and
procedures recommended by manufacturer of affected construction.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 07 Section Sheet Metal Flashing and Trim for shop- or field-fabricated
sheet metal roof drainage systems, low slope roof flashing and wall flashing. See Division 07 Section
Roof Specialties for manufactured copings and roof-edge flashings which have been wind-uplift
tested.
2. This Section specifies fully adhered TPO (thermoplastic polyolefin) membrane roofing systems
including roof insulation, base flashings, walkways, and auxiliary roofing materials.
A. The basis-of-design system specified is for installation over metal decking mechanically fastened
through a top layer of cover board or composite board (when required due to project design wind
speed conditions), through the roof insulation, and secured to the metal decking for buildings and
other structures located where the basic design wind speed (3-second gust) does not exceed 90
mph as indicated in Table C, Appendix C, UFC 3-310-01, 25 May, 2005 including Change 2, 5
December 2007.
B. For locations where the design wind speed is greater than 90 mph, a top layer of cover board or
composite board membrane underlayment is required in accordance with the membrane roofing
system manufacturer. The membrane underlayment shall not be fire retardant treated (FRT)
plywood (article 2-13, UFC 3-600-01, 14 July 2009).
C. The TPO white membrane specified is LEED compliant in accordance with Energy Star
compliance for roofing materials having a Solar Reflectance Index of 78 when applied over at
least 75 percent of the roof surface.
3. Provide insulation materials with a total minimum Long Term Thermal Resistance (LTTR) R-value of
20, unless climatic conditions or local Installation energy code requirements dictate a higher R-value.
Current Federal Energy Reduction Mandates may require the use of increased insulation
thicknesses. This will be determined through energy usage calculations prepared as part of project
development.
4. Design roof slope in accordance with roofing manufacturer's recommendations, but no less than 1/4"
per foot to interior drains using roof structure for slopes. Achieving roof slope with insulation is not
acceptable, except at drainage crickets, preformed saddles, tapered edge strips, and perimeter edge
strips.
5. Keep interior vertical drops from roof drains to a minimum, combining when practical and locating
them in concealed void spaces and storage areas. Do not locate exposed within customer areas.
6. If appropriate, locate overflow roof drains adjacent to normal roof drains with overflow outlets
exposed on exterior wall of building.
7. Provide access to roof for equipment maintenance via ships ladder and roof hatch from mechanical
equipment mezzanine, or stair tower from ground floor of building with standard steel door and frame
roof access to roof.
8. Indicate roof walkways necessary to access roof mounted equipment requiring maintenance.
END OF SECTION
June 2011 07 54 00 1
SECTION 07 54 00
THERMOPLASTIC MEMBRANE ROOFING
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 07 Section Sheet Metal Flashing and Trim for sheet metal flashing and trim
integral with membrane roofing.
2. Division 07 Section Roof Specialties for wind resistive metal flashing and trim integral
with membrane roofing.
1.2 DEFINITIONS
A. Roofing Terminology:
1. Refer to ASTM D 1079 and glossary of NRCA's "The NRCA Roofing and Waterproofing
Manual" for definition of terms related to roofing work in this Section.
A. General:
1. Provide installed roofing membrane and base flashings that remain watertight; do not
permit the passage of water; and resist specified uplift pressures, thermally induced
movement, and exposure to weather without failure.
B. Material Compatibility:
1. Provide roofing materials that are compatible with one another under conditions of
service and application required, as demonstrated by roofing membrane manufacturer
based on testing and field experience.
1. Provide a membrane roofing system that is identical to systems that have been
successfully tested by a qualified testing and inspecting agency to resist uplift pressure
D. Energy Performance: Provide roofing system that is listed on the DOE's ENERGY STAR "Roof
Products Qualified Product List" for low-slope roof products.
1.4 SUBMITTALS
A. Product Data:
B. Shop Drawings:
1. For roofing system. Include plans, elevations, sections, details, and attachments to other
Work.
C. Installer Certificates:
D. Manufacturer Certificates:
1. Signed by roofing manufacturer certifying that roofing system complies with requirements
specified in "Performance Requirements" Article.
2. Submit evidence of meeting performance requirements. Include the following roofing
system design considerations:
F. Maintenance Data:
H. Inspection Report:
1. Product Data for roofing materials indicating that roof materials comply with initial Solar
Reflectance Index (SRI) not less than 78 for a minimum of 75 percent of the roof surface
when calculated according to ASTM E 1980, based on testing identical products by a
qualified testing agency. (Heat Island Effect - Roof, SS Credit 7.2)
J. Submittal List:
A. Installer Qualifications:
B. Manufacturer Qualifications:
1. A qualified manufacturer that has UL listing for membrane roofing system identical to that
used for this Project.
C. Source Limitations:
1. Obtain components for membrane roofing system from roofing membrane manufacturer.
D. Fire-Test-Response Characteristics:
1. Before starting roof deck construction, conduct conference at Project site. Comply with
requirements for preinstallation conferences in Division 01 Section Administrative
Requirements. Review methods and procedures related to roof deck construction and
roofing system including, but not limited to, the following:
F. Preinstallation Conference:
A. Delivery:
1. Deliver roofing materials to Project site in original containers with seals unbroken and
labeled with manufacturer's name, product brand name and type, date of manufacture,
and directions for storing and mixing with other components.
B. Storage:
1. Store liquid materials in their original undamaged containers in a clean, dry, protected
location and within the temperature range required by roofing system manufacturer.
Protect stored liquid material from direct sunlight.
a. Discard and legally dispose of liquid material that cannot be applied within its
stated shelf life.
C. Protection:
1. Protect roof insulation materials from physical damage and from deterioration by sunlight,
moisture, soiling, and other sources. Store in a dry location. Comply with insulation
manufacturer's written instructions for handling, storing, and protecting during installation.
D. Handling:
1. Handle and store roofing materials and place equipment in a manner to avoid permanent
deflection of deck.
A. Weather Limitations:
1. Proceed with installation only when existing and forecasted weather conditions permit
roofing system to be installed according to manufacturer's written instructions and
warranty requirements.
1.8 WARRANTY
A. Special Warranty:
Insert wind speed limit that is appropriate for warranty period and
deck/membrane underlayment specified.
c. Warranty shall include roofing damage resulting from wind speeds up to and
including <Insert number> mph (3-second gust speed at 33 feet above ground for
exposure category indicated).
d. Evidence of manufacturers warranty reserve shall be in included as part of project
submittals.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Uniform, flexible sheet formed from a thermoplastic polyolefin, internally fabric or scrim
reinforced, ASTM D 6878, and as follows:
A. General:
2. Liquid-type auxiliary materials shall meet VOC limits of authorities having jurisdiction.
3. Liquid-type auxiliary materials shall meet VOC limits of authorities having jurisdiction.
4. Sheet Flashing: Manufacturer's standard unreinforced thermoplastic polyolefin sheet
flashing, 55 mils thick, minimum, of same color as sheet membrane.
5. Bonding Adhesive: Manufacturer's standard solvent-based low VOC bonding adhesive
for membrane, and solvent-based low VOC bonding adhesive for base flashings.
6. Metal Termination Bars: Manufacturer's standard predrilled stainless-steel or aluminum
bars, approximately 1 by 1/8 inch thick; with anchors.
7. Fasteners: Factory-coated steel fasteners and metal or plastic plates meeting corrosion-
resistance provisions in FMG 4470, designed for fastening membrane to substrate, and
acceptable to membrane roofing system manufacturer.
8. Miscellaneous Accessories: Provide pourable sealers, preformed cone and vent sheet
flashings, preformed inside and outside corner sheet flashings, T-joint covers, termination
reglets, cover strips, and other accessories.
A. General:
1. Provide preformed roof insulation boards that comply with requirements and referenced
standards, selected from manufacturer's standard sizes and of thicknesses indicated.
1. ASTM C 1289, Type II, Class 1, Grade 2 or 3, felt or glass-fiber mat facer on both major
surfaces approved by roofing system manufacturer for intended use in accordance with
warranty requirements.
2. Tapered Insulation: Provide factory-tapered insulation boards fabricated to slope of 1/4
inch per 12 inches, unless otherwise indicated.
3. Other Insulation Shapes: Provide preformed saddles, crickets, tapered edge strips, and
other insulation shapes where indicated for sloping to drain. Fabricate to slopes
indicated.
A. General:
A. Membrane Underlayment:
2.7 WALKWAYS
a. Color: White.
PART 3 - EXECUTION
3.1 EXAMINATION
A. General:
1. Examine substrates, areas, and conditions, with Installer present, for compliance with the
following requirements and other conditions affecting performance of roofing system:
a. Verify that roof openings and penetrations are in place and set and braced and
that roof drains are securely clamped in place.
b. Verify that wood blocking, curbs, and nailers are securely anchored to roof deck at
penetrations and terminations and that nailers match thicknesses of insulation.
c. Verify that surface plane flatness and fastening of steel roof deck comply with
requirements in Division 05 Section Steel Decking.
d. Proceed with installation only after unsatisfactory conditions have been corrected.
A. General:
1. Clean substrate of dust, debris, moisture, and other substances detrimental to roofing
installation according to roofing system manufacturer's written instructions. Remove
sharp projections.
2. Prevent materials from entering and clogging roof drains and conductors and from spilling
or migrating onto surfaces of other construction. Remove roof-drain plugs when no work
is taking place or when rain is forecast.
3. Complete terminations and base flashings and provide temporary seals to prevent water
from entering completed sections of roofing system at the end of the workday or when
rain is forecast. Remove and discard temporary seals before beginning work on
adjoining roofing.
A. General:
a. Install insulation so that all roof surfaces slope to drains, whether or not slope is
explicitly indicated.
4. Install insulation so completed surface is flush with surface of contiguous wood nailers;
adjust thickness of nailers to maintain surfaces flush.
5. Install insulation under area of roofing to achieve required thickness. Install 2 or more
layers with joints of each succeeding layer staggered from joints of previous layer a
minimum of 6 inches in each direction.
6. Trim surface of insulation where necessary at roof drains so completed surface is flush
and does not restrict flow of water.
7. Install insulation with long joints of insulation in a continuous straight line with end joints
staggered between rows, abutting edges and ends between boards. Fill gaps exceeding
1/4 inch with insulation.
a. Cut and fit insulation within 1/4 inch of nailers, projections, and penetrations.
B. Membrane Underlayment:
A. General:
1. Install roofing membrane over area to receive roofing according to membrane roofing
system manufacturer's written instructions. Unroll roofing membrane and allow to relax
before installing.
2. Start installation of roofing membrane in presence of membrane roofing system
manufacturer's technical personnel.
3. Accurately align roofing membrane and maintain uniform side and end laps of minimum
dimensions required by manufacturer. Stagger end laps.
4. Bonding Adhesive: Apply solvent-based low VOC bonding adhesive to substrate and
underside of roofing membrane at rate required by manufacturer and allow to partially dry
before installing roofing membrane. Do not apply bonding adhesive to splice area of
roofing membrane.
5. Mechanically or adhesively fasten roofing membrane securely at terminations,
penetrations, and perimeter of roofing.
6. Apply roofing membrane with side laps shingled with slope of roof deck where possible.
7. Seams: Clean seam areas, overlap roofing membrane, and hot-air weld side and end
laps of roofing membrane according to manufacturer's written instructions to ensure a
watertight seam installation.
a. Test lap edges with probe to verify seam weld continuity. Apply lap sealant to seal
cut edges of roofing membrane.
b. Verify field strength of seams a minimum of twice and repair seam sample areas.
1) Conduct initial probe after membrane has had sufficient time to cool and set.
2) Conduct a second probe after the membrane has experienced at least one
complete thermal cycle (i.e., daily solar heating with nighttime cooling).
c. Repair tears, voids, and lapped seams in roofing membrane that does not meet
requirements.
8. Spread sealant or mastic bed over deck drain flange at deck drains and securely seal
roofing membrane in place with clamping ring.
A. General:
1. Install sheet flashings and preformed flashing accessories and adhere to substrates
according to membrane roofing system manufacturer's written instructions.
B. Install walkway products in locations indicated or, if not indicated, from roof access indicated to
and around roof-mounted mechanical equipment. Cut walkway rolls into maximum 10-foot
lengths and position with a minimum 1 inch gap between adjacent pieces to allow for water
drainage. Cut walkway so a 4-inch minimum gap is created over field splices. Heat weld to
substrate according to roofing system manufacturer's written instructions.
A. General:
1. Final Roof Inspection: Arrange for roofing system manufacturer's technical personnel to
inspect roofing installation on completion and submit report to Contracting Officer.
2. Repair or remove and replace components of membrane roofing system where test
results or inspections indicate that they do not comply with specified requirements.
3. Additional testing and inspecting, at Contractor's expense, will be performed to determine
compliance of replaced or additional work with specified requirements.
A. General:
1. Protect membrane roofing system from damage and wear during remainder of
construction period. When remaining construction will not affect or endanger roofing,
inspect roofing for deterioration and damage, describing its nature and extent in a written
report, with copies to Contracting Officer.
2. Correct deficiencies in or remove membrane roofing system that does not comply with
requirements, repair substrates, and repair or reinstall membrane roofing system to a
condition free of damage and deterioration at time of final acceptance and according to
warranty requirements.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 04 Section Unit Masonry for manufactured and formed through-wall
flashing, reglets, and other sheet metal flashing and trim included with unit masonry assemblies. See
Division 07 Section Metal Panels for sheet metal flashing and trim associated with those assemblies.
See Division 07 Section Roof Specialties for manufactured copings and roof-edge flashings which
have been wind-uplift tested.
2. This Section specifies shop and field-formed sheet metal roof drainage systems, low-slope roof
flashing, steep-slope roof flashing, and wall flashing.
3. Graphically indicate location and size of metal gutters and downspouts on drawings. Exterior building
elevations shall locate exposed vertical downspouts with metal downspout boots. Select and identify
types of metal downspout boots required on Project:
A. 48" high metal downspout boot with vertical discharge directly into buried storm pipe.
B. 48" high metal downspout boot with discharge at 35 degrees from horizontal onto splash block or
pavement.
4. Do not discharge downspouts at grade in customer walk areas, or small landscape areas near
customer areas that may be subject to flooding during heavy rainfall. Discharge directly into buried
storm pipe systems.
END OF SECTION
June 2011 07 60 00 1
SECTION 07 60 00
SHEET METAL FLASHING AND TRIM
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 06 Section Rough Carpentry for wood nailers, curbs, and blocking.
2. Division 07 Section Roof Specialties for manufactured roof specialties not part of sheet
metal flashing and trim.
3. Division 07 Section Metal panels for metal roof system components not part of sheet
metal flashing and trim.
4. Division 07 Section Ethylene-Propylene-Diene-Monomer Roofing for roof system
components.
5. Division 07 Section Thermoplastic Membrane Roofing for roof system components.
A. General:
1. Install sheet metal flashing and trim to withstand wind loads, structural movement,
thermally induced movement, and exposure to weather without failing, rattling, leaking,
and fastener disengagement.
B. Thermal Movements:
1. Provide sheet metal flashing and trim that allow for thermal movements resulting from the
following maximum change (range) in ambient and surface temperatures by preventing
buckling, opening of joints, hole elongation, overstressing of components, failure of joint
sealants, failure of connections, and other detrimental effects. Provide clips that resist
rotation and avoid shear stress as a result of sheet metal and trim thermal movements.
Base engineering calculation on surface temperatures of materials due to both solar heat
gain and nighttime-sky heat loss.
a. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces.
1. Provide sheet metal flashing and trim that do not allow water infiltration to building
interior.
1.3 SUBMITTALS
A. Shop Drawings:
1. Show layouts of sheet metal flashing and trim, including plans and elevations.
Distinguish between shop- and field-assembled work. Include the following:
a. Identify material, thickness, weight, and finish for each item and location in Project.
b. Details for forming sheet metal flashing and trim, including profiles, shapes,
seams, and dimensions.
c. Details for fastening, joining, supporting, and anchoring sheet metal flashing and
trim, including fasteners, clips, cleats, and attachments to adjoining work.
d. Details of expansion-joint covers, including showing direction of expansion and
contraction.
1. For each type of exposed finish required, prepared on Samples of size indicated below:
a. Sheet Metal Flashing: 12 inches long. Include fasteners, cleats, closures, and
other attachments.
b. Trim: 12 inches long. Include fasteners and other exposed accessories.
C. Submittal List:
A. Sheet Metal Flashing and Trim Standard: Comply with SMACNA's "Architectural Sheet Metal
Manual." Conform to dimensions and profiles shown unless more stringent requirements are
indicated.
A. Delivery:
1. Deliver sheet metal flashing materials and fabrications undamaged. Protect sheet metal
flashing and trim materials and fabrications during transportation and handling.
1. Unload, store, and install sheet metal flashing materials and fabrications in a manner to
prevent bending, warping, twisting, and surface damage.
C. Handling:
1. Stack materials on platforms or pallets, covered with suitable weathertight and ventilated
covering. Do not store sheet metal flashing and trim materials in contact with other
materials that might cause staining, denting, or other surface damage.
1.6 COORDINATION
A. Coordinate installation of sheet metal flashing and trim with interfacing and adjoining
construction to provide a leakproof, secure, and noncorrosive installation.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design Products: Subject to compliance with requirements, provide either the named
products or equal products. Refer to Division 01 Section References.
A. Aluminum Sheet: ASTM B 209, alloy as standard with manufacturer for finish required, with
temper as required to suit forming operations and performance required.
B. Exposed Finishes:
1. High-Performance Organic Finish: Prepare, pretreat, and apply coating to exposed metal
surfaces to comply with coating and resin manufacturers' written instructions.
C. Lead Sheet:
A. General:
1. Provide materials and types of fasteners, solder, welding rods, protective coatings,
separators, sealants, and other miscellaneous items as required for complete sheet metal
flashing and trim installation.
B. Fasteners:
1. Wood screws, annular threaded nails, self-tapping screws, self-locking rivets and bolts,
and other suitable fasteners designed to withstand design loads.
2. Exposed Fasteners: Heads matching color of sheet metal by means of plastic caps or
factory-applied coating.
3. Fasteners for Flashing and Trim: Blind fasteners or self-drilling screws, gasketed, with
hex washer head.
4. Blind Fasteners: High-strength aluminum or stainless-steel rivets.
5. Spikes and Ferrules: Same material as gutter; with spike with ferrule matching internal
gutter width.
E. Elastomeric Sealant:
1. ASTM C 920, elastomeric silicone polymer sealant; of type, grade, class, and use
classifications required to seal joints in sheet metal flashing and trim and remain
watertight.
G. Bituminous Coating:
1. Cold-applied asphalt mastic, SSPC-Paint 12, compounded for 15-mil dry film thickness
per coat. Provide inert-type noncorrosive compound free of asbestos fibers, sulfur
components, and other deleterious impurities.
A. Custom fabricate sheet metal flashing and trim to comply with recommendations in SMACNA's
"Architectural Sheet Metal Manual" that apply to design, dimensions, metal, and other
characteristics of item indicated. Shop fabricate items where practicable. Obtain field
measurements for accurate fit before shop fabrication.
C. Fabricate sheet metal flashing and trim without excessive oil canning, buckling, and tool marks
and true to line and levels indicated, with exposed edges folded back to form hems.
1. Seams for Other Than Aluminum: Fabricate nonmoving seams in accessories with flat-
lock seams. Tin edges to be seamed, form seams, and solder.
D. Sealed Joints: Form nonexpansion but movable joints in metal to accommodate elastomeric
sealant to comply with SMACNA recommendations.
E. Expansion Provisions: Where lapped or bayonet-type expansion provisions in the Work cannot
be used, form expansion joints of intermeshing hooked flanges, not less than 1 inch deep, filled
with elastomeric sealant concealed within joints.
F. Conceal fasteners and expansion provisions where possible on exposed-to-view sheet metal
flashing and trim, unless otherwise indicated.
G. Fabricate cleats and attachment devices from same material as accessory being anchored or
from compatible, noncorrosive metal.
A. Hanging Gutters:
1. Fabricate to cross section indicated, complete with end pieces, outlet tubes, and other
accessories as required. Fabricate in minimum 96-inch- long sections. Furnish flat-stock
gutter spacers and gutter brackets fabricated from same metal as gutters, of size
recommended by SMACNA but not less than twice the gutter thickness. Fabricate
expansion joints, expansion-joint covers, and gutter accessories from same metal as
gutters.
2. Expansion Joints: Butt type.
3. Gutters with Girth up to 15 Inches: Fabricate from the following material:
B. Downspouts:
1. Fabricate rectangular downspouts complete with mitered elbows. Furnish with metal
hangers, from same material as downspouts, and anchors.
2. Fabricate downspouts from the following materials:
A. Counterflashing:
2.7 FINISHES
A. General:
1. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
2. Protect mechanical and painted finishes on exposed surfaces from damage by applying a
strippable, temporary protective covering before shipping.
3. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces
are acceptable if they are within one-half of the range of approved Samples. Noticeable
variations in the same piece are not acceptable. Variations in appearance of other
components are acceptable if they are within the range of approved Samples and are
assembled or installed to minimize contrast.
A. Precast concrete type, of size and profile indicated on drawings; if not indicated, provide
minimum 12-inch wide by 18-inch long with center depression.
A. Provide downspout boots made from cast gray iron in heights indicated with inlets of size and
shape to suit downspouts.
1. Basis-of-Design Products:
a. Barry Pattern & Foundry Company, Inc., Catalog Number B25A. (800) 524-1809.
b. McKinley Iron Works, Inc., Type DS4. (800) 433-2303.
1. Basis-of-Design Product:
a. Barry Pattern & Foundry Company, Inc., Catalog Number B25D. (800) 524-1809.
b. McKinley Iron Works, Inc., Type DS8. (800) 433-2303.
3.1 EXAMINATION
A. General:
1. Examine substrates, areas, and conditions, with Installer present, to verify actual
locations, dimensions and other conditions affecting performance of work.
2. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and securely
anchored.
3. Proceed with installation only after unsatisfactory conditions have been corrected.
A. Anchor sheet metal flashing and trim and other components of the Work securely in place, with
provisions for thermal and structural movement. Use fasteners, solder, welding rods, protective
coatings, separators, sealants, and other miscellaneous items as required to complete sheet
metal flashing and trim system.
D. Metal Protection:
1. Where dissimilar metals will contact each other or corrosive substrates, protect against
galvanic action by painting contact surfaces with bituminous coating or by other
permanent separation as recommended by fabricator or manufacturers of dissimilar
metals.
E. Install exposed sheet metal flashing and trim without excessive oil canning, buckling, and tool
marks.
F. Install sheet metal flashing and trim true to line and levels indicated. Provide uniform, neat
seams with minimum exposure of solder, welds, and elastomeric sealant.
G. Install sheet metal flashing and trim to fit substrates and to result in watertight performance.
Verify shapes and dimensions of surfaces to be covered before fabricating sheet metal.
1. Space cleats not more than 12 inches apart. Anchor each cleat with two fasteners. Bend
tabs over fasteners.
I. Fasteners: Use fasteners of sizes that will penetrate substrate not less than 1-1/4 inches for
nails and not less than 3/4 inch for wood screws.
1. Where sealant-filled joints are used, embed hooked flanges of joint members not less
than 1 inch into sealant. Form joints to completely conceal sealant. When ambient
temperature at time of installation is moderate, between 40 and 70 deg F, set joint
members for 50 percent movement either way. Adjust setting proportionately for
installation at higher ambient temperatures. Do not install sealant-type joints at
temperatures below 40 deg F.
2. Prepare joints and apply sealants to comply with requirements in Division 07 Section
Joint Sealants.
K. Soldered Joints: Clean surfaces to be soldered, removing oils and foreign matter. Pretin edges
of sheets to be soldered to a width of 1-1/2 inches except where pretinned surface would show
in finished Work.
1. Do not use open-flame torches for soldering. Heat surfaces to receive solder and flow
solder into joints. Fill joints completely. Completely remove flux and spatter from
exposed surfaces.
A. General:
1. Install sheet metal roof drainage items to produce complete roof drainage system
according to SMACNA recommendations and as indicated. Coordinate installation of
roof perimeter flashing with installation of roof drainage system.
B. Hanging Gutters:
1. Join sections with riveted and soldered joints or with lapped joints sealed with elastomeric
sealant. Provide for thermal expansion. Attach gutters at eave or fascia to firmly
anchored straps spaced not more than 36 inches apart. Provide end closures and seal
watertight with sealant. Slope to downspouts.
1. Join sections with 1-1/2-inch telescoping joints. Provide fasteners designed to hold
downspouts securely 1 inch away from walls; locate fasteners at top and bottom and at
approximately 60 inches o.c. in between.
a. Provide elbows at base of downspout to direct water away from building and,
where indicated, onto splashblocks.
b. Connect downspouts to underground drainage system where indicated.
D. Expansion-Joint Covers:
1. Install where downspouts discharge on low-sloped roofs. Set units on roof in method
approved by primary roofing manufacturer and compatible with roofing membrane.
A. General:
1. Install sheet metal roof flashing and trim to comply with performance requirements and
SMACNA's "Architectural Sheet Metal Manual." Provide concealed fasteners where
possible, set units true to line, and level as indicated. Install work with laps, joints, and
seams that will be permanently watertight.
B. Counterflashing:
C. Roof-Penetration Flashing:
a. Turn lead flashing down inside vent piping, being careful not to block vent piping
with flashing.
b. Seal with elastomeric sealant and clamp flashing to pipes penetrating roof except
for lead flashing on vent piping.
A. Cleaning:
1. Clean exposed metal surfaces of substances that interfere with uniform oxidation and
weathering.
1. Replace sheet metal flashing and trim that have been damaged or that have deteriorated
beyond successful repair by finish touchup or similar minor repair procedures.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 07 Section Sheet Metal Flashing And Trim for site-fabricated sheet
metal flashing and trim and for roof-edge drainage-system components. See Division 07 Section
Metal Panels for sheet metal flashing and trim associated with those assemblies.
2. This Section specifies manufactured copings and roof-edge flashings which have been wind-uplift
tested.
3. Roof specialties are plant manufactured and distinguished from sheet metal flashing and trim
components that are also linear in nature, but which are formed or fabricated in the field or at the
fabricator's shop.
4. Graphically indicate location and size of manufactured copings and roof-edge flashings on drawings.
END OF SECTION
June 2011 07 71 00 1
SECTION 07 71 00
ROOF SPECIALTIES
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Copings.
2. Roof-edge flashings.
B. Related Sections:
1. Division 06 Section Rough Carpentry for wood nailers, curbs, and blocking.
2. Division 07 Section Sheet Metal Flashing and Trim for site-fabricated sheet metal flashing
and trim and for roof-edge drainage-system components.
3. Division 07 Section [Ethylene-Propylene-Diene-Monomer Roofing] [Thermoplastic
Membrane Roofing] for metal edging specified as part of roofing system special
warranty.
A. General Performance:
1. Roof specialties shall withstand exposure to weather and resist thermally induced
movement without failure, rattling, leaking, or fastener disengagement due to defective
manufacture, fabrication, installation, or other defects in construction.
2. ANSI/SPRI Wind Design Standard: Manufacture and install copings and roof-edge
flashings tested according to ANSI/SPRI ES-1 and capable of resisting the following
design pressures:
a. Refer to Division 01 Section Summary of Work for wind loading design criteria.
3. Thermal Movements: Allow for thermal movements from ambient and surface
temperature changes to prevent buckling, opening of joints, hole elongation,
overstressing of components, failure of joint sealants, failure of connections, and other
detrimental effects. Provide clips that resist rotation and avoid shear stress as a result of
thermal movements. Base calculations on surface temperatures of materials due to both
solar heat gain and nighttime-sky heat loss.
a. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces.
A. Product Data:
1. For each type of product indicated. Include construction details, material descriptions,
dimensions of individual components and profiles, and finishes.
B. Shop Drawings:
1. For roof specialties. Include plans, elevations, expansion-joint locations, keyed details,
and attachments to other work. Distinguish between plant- and field-assembled work.
Include the following:
1. For copings and roof-edge flashings made from 12-inch lengths of full-size components
including fasteners, cover joints, accessories, and attachments.
F. Submittal List:
A. Mockups:
1. Build mockups to verify selections made under sample submittals and to demonstrate
aesthetic effects and set quality standards for fabrication and installation.
a. Approval of mockups does not constitute approval of deviations from the Contract
Documents contained in mockups.
A. Storage:
1. Do not store roof specialties in contact with other materials that might cause staining,
denting, or other surface damage. Store roof specialties away from uncured concrete
and masonry.
B. Protection:
1. Protect strippable protective covering on roof specialties from exposure to sunlight and
high humidity, except to extent necessary for the period of roof specialties installation.
1.6 WARRANTY
a. Fluoropolymer Finish: Deterioration includes, but is not limited to, the following:
1.7 COORDINATION
PART 2 - PRODUCTS
A. Aluminum Sheet:
1. ASTM B 209, alloy as standard with manufacturer for finish required, with temper to suit
forming operations and performance required.
A. Aluminum Extrusions:
1. ASTM B 221, alloy and temper recommended by manufacturer for type of use and
structural performance indicated, mill finished.
A. General:
1. Provide materials and types of fasteners, protective coatings, sealants, and other
miscellaneous items required by manufacturer for a complete installation.
2. Fasteners: Manufacturer's recommended fasteners, suitable for application and
designed to meet performance requirements. Furnish the following unless otherwise
indicated:
3. Elastomeric Sealant: ASTM C 920, elastomeric polymer sealant of type, grade, class,
and use classifications required by roofing-specialty manufacturer for each application.
4. Bituminous Coating: Cold-applied asphalt emulsion complying with ASTM D 1187.
B. Asphalt Roofing Cement: ASTM D 4586, asbestos free, of consistency required for application.
A. Copings:
1. Manufactured coping system consisting of formed-metal coping cap in section lengths not
exceeding 12 feet, concealed anchorage; corner units, end cap units, and concealed
splice plates with same finish as coping caps.
Where the Project wind speed exceeds 100 mph and requires 15-
year or greater warranty, delete below and insert product that meets
performance and warranty requirements acceptable to membrane
manufacturer specified in related Division 7 EPDM or TPO
membrane roofing Section.
A. Roof-Edge Fascia:
Where the Project wind speed exceeds 120 mph and requires 15-
year or greater warranty, delete below and insert product that meets
performance and warranty requirements acceptable to membrane
manufacturer specified in related Division 7 EPDM or TPO
membrane roofing Section.
b. SecurEdge 2000 Fascia.
Where the Project wind speed exceeds 155 mph and requires 15-
year or greater warranty, delete below and insert product that meets
A. General:
1. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
2. Protect mechanical and painted finishes on exposed surfaces from damage by applying a
strippable, temporary protective covering before shipping.
3. Appearance of Finished Work: Noticeable variations in same piece are not acceptable.
Variations in appearance of adjoining components are acceptable if they are within the
range of approved Samples and are assembled or installed to minimize contrast.
PART 3 - EXECUTION
3.1 EXAMINATION
A. General:
1. Examine substrates, areas, and conditions, with Installer present, to verify actual
locations, dimensions, and other conditions affecting performance of the Work.
2. Examine walls, roof edges, and parapets for suitable conditions for roof specialties.
3. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and securely
anchored.
4. Proceed with installation only after unsatisfactory conditions have been corrected.
A. General:
B. Metal Protection:
1. Protect metals against galvanic action by separating dissimilar metals from contact with
each other or with corrosive substrates by painting contact surfaces with bituminous
coating or by other permanent separation as recommended by manufacturer.
C. Expansion Provisions:
D. Fastener Sizes:
1. Use fasteners of sizes that will penetrate substrate not less than recommended by
fastener manufacturer to achieve maximum pull-out resistance.
E. Joint Seal:
A. General:
1. Install cleats, anchor plates, and other anchoring and attachment accessories and
devices with concealed fasteners.
2. Anchor copings to meet performance requirements.
A. General:
1. Install cleats, cants, and other anchoring and attachment accessories and devices with
concealed fasteners.
2. Anchor roof edgings with manufacturer's required devices, fasteners, and fastener
spacing to meet performance requirements.
A. General:
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 05, Division 07, and Division 08 Design Criteria.
2. Roof hatches shall be provided in facilities with minimal roof top equipment (i.e., air cooled condensing
units, air intake and exhaust fans, small prepackaged HVAC units, etc.).
3. Stair towers for roof access, using 3' 0" wide by 7' 0" high insulated standard steel doors, shall be
provided in facilities with roof mounted refrigeration mechanical centers and HVAC systems. Refer to
Division 08 Hollow Metal Doors and Frames for roof access door criteria.
4. Roof hatch shall be single leaf-type with minimum opening size of 2' 6" by 4' 6" and typically accessed
by a ships ladder from the mechanical equipment mezzanine. Refer to Division 05 Metal Fabrications
for ship ladder design criteria.
5. Locate roof hatch parallel with roof framing and position to avoid overhead clearance conflicts with
intermediate framing / bridging and ships ladder.
6. Verify intended roof surface drainage patterns are maintained around hatch installation. Provide crickets
where required to direct surface runoff around units and not cause ponding.
8. Do not locate roof hatch or any equipment requiring maintenance within ten feet of a roof edge, unless
safety railings are provided.
9. Provide roof walkway pads from roof hatch access point to all roof top equipment requiring
maintenance. Location of walkway pads shall be indicated on roof plan.
10. Verify that a security alarm contact is provided at roof hatch, as well as padlock.
END OF SECTION
June 2011 07 72 33 1
SECTION 07 72 33
ROOF HATCHES
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Roof hatches.
2. Safety railing system.
1.2 SUBMITTALS
A. Product Data:
1. For each type of roof accessory indicated. Include construction details, material
descriptions, dimensions of individual components and profiles, and finishes.
B. Submittal List:
A. Pack, handle, and ship roof hatches properly labeled in heavy-duty packaging to prevent
damage.
1.5 COORDINATION
A. Coordinate layout and installation of roof hatches with roofing membrane and base flashing
and interfacing and adjoining construction to provide a leakproof, weathertight, secure, and
noncorrosive installation.
2.1 MANUFACTURERS
A. Roof Hatches:
1. Fabricate roof hatches with insulated double-wall lids and insulated double-wall curb
frame with integral deck mounting flange and lid frame counterflashing. Fabricate with
welded or mechanically fastened and sealed corner joints. Provide continuous
weathertight perimeter gasketing and equip with corrosion-resistant or hot-dip galvanized
hardware.
a. Basis-of-Design Products: Bilco Company (The), Type NB for ship stair access.
2. Loads: Fabricate roof hatches to withstand 40-lbf/sq. ft. external and 20-lbf/sq. ft. internal
loads.
3. Type and Size: Single-leaf lid, 30 by 54 inches.
4. Curb and Lid Material: Galvanized steel sheet, 0.079 inch thick.
2. Hatch rail system shall satisfy the requirements of OSHA 29 CFR 1910.23 and shall meet
OSHA strength requirements with a factor of safety of two, and the following:
5. Self-Latching Gate: Fabricated of same materials and rail spacing as safety railing
system. Provide manufacturer's standard hinges and self-latching mechanism.
6. Pipe Ends and Tops: Covered or plugged with weather-resistant material.
7. Provide weep holes or another means to drain entrapped water in hollow sections of
handrail and railing members that are exposed to exterior or to moisture from
condensation or other sources.
8. Fabricate joints that will be exposed to weather in a watertight manner.
9. Close exposed ends of handrail and railing members with prefabricated end fittings.
10. Hardware:
3.1 EXAMINATION
A. General:
1. Examine substrates, areas, and conditions, with Installer present, to verify actual
locations, dimensions, and other conditions affecting performance of work.
2. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and securely
anchored and is ready to receive roof accessories.
3. Verify dimensions of roof openings for roof hatches.
4. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. General:
a. Coat concealed side of roof hatches with bituminous coating where in contact with
wood, ferrous metal, or cementitious construction.
b. Underlayment: Where installing exposed-to-view components of roof hatches
directly on cementitious or wood substrates, install a course of felt underlayment
and cover with a slip sheet, or install a course of polyethylene underlayment.
c. Bed flanges in thick coat of asphalt roofing cement where required by roof
accessory manufacturers for waterproof performance.
4. Install roof accessories level, plumb, true to line and elevation, and without warping, jogs
in alignment, excessive oil canning, buckling, or tool marks.
5. Roof Hatch Installation: Check roof hatch for proper operation. Adjust operating
mechanism as required. Clean and lubricate joints and hardware.
6. Safety Railing System Installation: Attach hatch rail system to the cap flashing of roof
hatch; do not penetrate any roofing material.
7. Seal joints with elastomeric sealant as required by manufacturer of roof hatches.
3.3 TOUCH UP
A. Factory-Primed Surfaces:
1. Touch up factory-primed surfaces with compatible primer ready for field painting in
accordance with Division 09 painting Sections.
1. Clean field welds, bolted connections, and abraded areas and repair galvanizing to
comply with ASTM A 780.
3.4 CLEANING
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Divisions 21, 22, 23, 26, 27 and 28 Sections to ensure that systems required
under in this Section fit the types of mechanical and electrical penetrating items and the types of fire-
rated construction penetrated.
2. This Section specifies through-penetration firestop systems and fire-resistive joint systems for head-
of-wall joints installed in fire-resistance-rated construction.
3. This Section does not specify fire-resistive joint systems for floor-to-floor, floor-to-wall, and wall-to-
wall joints, and perimeter fire-containment systems (often called fire-safing insulation) for perimeter
joints between curtain-wall assemblies and fire-resistance-rated floor assemblies.
4. This Section makes the Contractor responsible for selecting, furnishing, and installing through-
penetration firestop systems and fire-resistive joint systems for head-of-wall joints appropriate for the
fire-resistance-rated construction indicated on the drawings.
END OF SECTION
June 2011 07 84 00 1
SECTION 07 84 00
FIRESTOPPING
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
3. For through-penetration firestop systems exposed to view, traffic, moisture, and physical
damage, provide products that, after curing, do not deteriorate when exposed to these
conditions both during and after construction.
a. For piping penetrations for plumbing and wet-pipe sprinkler systems, provide
moisture-resistant through-penetration firestop systems.
b. For penetrations involving insulated piping, provide through-penetration firestop
systems not requiring removal of insulation.
1. General: Provide fire-resistive joint systems that are produced and installed to resist
spread of fire according to requirements for joints, resist passage of smoke and other
gases, and maintain original fire-resistance rating of assembly in which fire-resistive joint
systems are installed.
2. Joint Systems in and between Fire-Resistance-Rated Constructions: Provide systems
with assembly ratings equaling or exceeding the fire-resistance ratings of construction
indicated as determined by UL 2079.
1. Where firestop systems are required to have same Class A finish rating as wall and
ceiling finishes in which firestop systems are installed provide products with flame-spread
and smoke-developed indexes of less than 25 and 450, respectively, as determined per
ASTM E 84.
1.3 SUBMITTALS
A. Product Data:
B. LEED Submittal:
1. Product Data for Credit EQ 4.1: For penetration firestopping, including printed statement
of VOC content and chemical components.
C. Shop Drawings:
E. Submittal List:
A. Installer Qualifications:
1. A firm that has been approved by FMG according to FMG 4991, "Approval of Firestop
Contractors."
B. Installation Responsibility:
C. Fire-Test-Response Characteristics:
1. Provide firestop systems that comply with the following requirements and those specified
in Part 1 "Performance Requirements" Article.
D. Coordination:
1. Coordinate construction of joints, openings and penetrating items to ensure that firestop
systems are installed according to requirements specified by firestop system
manufacturer.
E. Concealed Installations:
1. Do not cover up firestop systems installations that will become concealed behind other
construction until inspecting agency and building inspector of authorities having
jurisdiction have examined each installation.
2.1 FIRESTOPPING
A. Products:
1. Subject to compliance with requirements, select and provide firestopping products for
each fire-resistance-rated construction indicated on Drawings in accordance with "Part 1
Performance Requirements" Article.
B. Compatibility:
1. Provide firestop systems that are compatible with one another; with joint substrates, with
the substrates forming openings; and with the items, if any, penetrating through-
penetration firestop systems, under conditions of service and application, as
demonstrated by through-penetration firestop system manufacturer based on testing and
field experience.
C. Accessories:
1. Provide components for each firestop system, including primers and forming materials,
that are needed to install fill materials and to comply with Part 1 "Performance
Requirements" Article. Use only components specified by firestop system manufacturer
and approved by qualified testing and inspecting agency for firestop systems required.
D. VOC Content:
1. Provide penetration firestopping that complies with the following limits for VOC content
when calculated according to 40 CFR 59, Subpart D (EPA Method 24):
PART 3 - EXECUTION
3.1 INSTALLATION
a. After installing fill materials and allowing them to fully cure, remove combustible
forming materials and other accessories not indicated as permanent components
of firestop systems.
a. Fill voids and cavities formed by openings, forming materials, accessories, and
penetrating items as required to achieve fire-resistance ratings indicated.
b. Apply materials so they contact and adhere to substrates formed by openings and
penetrating items.
c. For fill materials that will remain exposed after completing Work, finish to produce
smooth, uniform surfaces that are flush with adjoining finishes.
A. Inspecting Agency:
B. Testing Services:
a. Inspecting agency shall state in each report whether inspected firestop systems
comply with or deviate from requirements.
2. Remove and replace firestop systems where inspections indicate that they do not comply
with specified requirements.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 32 Section Concrete Paving Joint Sealants; Division 03 Section Cast-
in-Place Concrete for joint fillers; Division 04 Section Unit Masonry for joint fillers and gaskets for
control and expansion joints in unit masonry; Division 07 Section Firestopping; Division 08 Section
Glazing for glazing sealants; Division 09 Section Resilient Tile Flooring for joint fillers in concrete floor
slab; and Division 09 Section Gypsum Board for sealing perimeter joints of gypsum board partitions
to reduce sound transmission.
2. This Section specifies elastomeric and latex joint sealants for applications indicated at beginning of
Section, and continuous foam compression seals to fill voids between refrigerated display cases and
adjacent wall surfaces. Refer to Design Standard Plate 07 92 00 - 1 and 07 92 00 - 2.
3. Control / contraction joints in exposed concrete floor slabs shall be filled with joint filler as specified in
Division 03 Section Cast-In-Place Concrete.
4. Control / contraction joints in concrete floor surfaces receiving resilient floor tile covering shall be
filled with latex patching or underlayment compound recommended by resilient flooring manufacturer.
END OF SECTION
June 2011 07 92 00 1
SECTION 07 92 00
JOINT SEALANTS
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1. Joint sealants for the following applications, including those specified by reference to this
Section:
d. Interior perimeter joints between food equipment cases and Between Surfaces
Indicated and Food Equipment Cases: Foam compression seals.
e. Joint-sealant applications not indicated will be selected by the Contracting Officer
from elastomeric products indicated in Part 2.
B. Related Sections:
1. Division 03 Section Cast-In-Place Concrete for filling joints in interior floor slabs.
2. Division 04 Section Unit Masonry for masonry control and expansion joint fillers and
gaskets.
3. Division 07 Section Exterior Insulation and Finish Systems (EIFS) for sealing joints in
EIFS with elastomeric joint sealants.
4. Division 08 Section Glazing for glazing sealants.
5. Division 09 Section Gypsum Board for sealing perimeter joints of gypsum board partitions
to reduce sound transmission.
6. Division 32 Section Concrete Paving Joint Sealants for sealing joints in exterior
pavements, walkways, and curbing.
a. Use ASTM C 1087 to determine whether priming and other specific joint
preparation techniques are required to obtain rapid, optimum adhesion of joint
sealants to joint substrates.
b. Submit not fewer than eight pieces of each type of material, including joint
substrates, shims, joint-sealant backings, secondary seals, and miscellaneous
materials.
c. Schedule sufficient time for testing and analyzing results to prevent delaying the
Work.
d. For materials failing tests, obtain joint-sealant manufacturer's written instructions
for corrective measures including use of specially formulated primers.
1. Before installing elastomeric sealants, field test their adhesion to Project joint substrates
as follows:
a. Locate test joints where indicated on Project or, if not indicated, as directed by
Contracting Officer.
b. Conduct field tests for each application indicated below:
c. Notify Contracting Officer seven days in advance of dates and times when test
joints will be erected.
d. Arrange for tests to take place with joint-sealant manufacturer's technical
representative present.
1.3 SUBMITTALS
A. Product Data:
B. LEED Submittal:
1. Product Data for Credit EQ 4.1: For sealants and sealant primers used inside the
weatherproofing system, including printed statement of VOC content.
1. For each kind and color of joint sealant required, provide Samples with joint sealants in
1/2-inch- wide joints formed between two 6-inch- long strips of material matching the
appearance of exposed surfaces adjacent to joint sealants.
a. Materials forming joint substrates and joint-sealant backings have been tested for
compatibility and adhesion with joint sealants.
b. Interpretation of test results and written recommendations for primers and
substrate preparation needed for adhesion.
1. Indicate which sealants and joint preparation methods resulted in optimum adhesion to
joint substrates based on testing specified in "Preconstruction Testing" Article.
H. Submittal List:
A. Source Limitations:
1. Obtain each kind of joint sealant through one source from a single manufacturer.
B. Product Testing:
A. General:
1. Do not proceed with installation of joint sealants under the following conditions:
a. When ambient and substrate temperature conditions are outside limits permitted
by joint-sealant manufacturer.
b. When joint substrates are wet.
c. Where joint widths are less than those allowed by joint-sealant manufacturer for
applications indicated.
d. Where Contaminants capable of interfering with adhesion have not yet been
removed from joint substrates.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Compatibility:
1. Provide joint sealants, backings, and other related materials that are compatible with one
another and with joint substrates under conditions of service and application, as
demonstrated by sealant manufacturer, based on testing and field experience.
1. Provide sealants and sealant primers for use inside the weatherproofing system that
comply with the following limits for VOC content when calculated according to
40 CFR 59, Part 59, Subpart D (EPA Method 24):
A. Elastomeric Sealants:
1. Comply with ASTM C 920 and other requirements indicated for each liquid-applied
chemically curing sealant specified, including those referencing ASTM C 920
classifications for type, grade, class, and uses related to exposure and joint substrates.
B. Stain-Test-Response Characteristics:
1. Where elastomeric sealants are indicated for joints that will come in repeated contact with
food, provide products that comply with 21 CFR 177.2600.
D. ES-S1 Single-Component Nonsag Neutral-Curing Surface Modified Silicone Sealant (Low dirt
pick-up):
B. Basis-of-Design Products:
A. General:
1. Provide sealant backings of material that are nonstaining; are compatible with joint
substrates, sealants, primers, and other joint fillers; and are approved for applications
indicated by sealant manufacturer based on field experience and laboratory testing.
1. ASTM C 1330, Type C (closed-cell material with a surface skin), O (open-cell material), B
(bicellular material with a surface skin), or any of the preceding types, as approved in
writing by joint-sealant manufacturer for joint application indicated, and of size and
density to control sealant depth and otherwise contribute to producing optimum sealant
performance:
C. Bond-Breaker Tape:
A. Manufacturer's standard preformed continuous foam compression seals to fill voids between
refrigerated display cases and adjacent wall surfaces.
1. Meets requirements for resistance to mold growth (UL181), fungi (ASTM G 21 / C 1338),
and bacteria (ASTM G 22).
2. Properties: Permanently elastic, mildew resistant, nonmigratory, nonstaining, and
compatible with joint substrates and other joint sealants.
3. Flame spread and smoke developed index: 25/50, ASTM E 84.
4. Density: 3.0 to 6.0 lb/cu. ft.
A. Primer:
C. Masking Tape:
1. Nonstaining, nonabsorbent material compatible with joint sealants and surfaces adjacent
to joints.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with
requirements for joint configuration, installation tolerances, and other conditions affecting joint-
sealant performance. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.2 PREPARATION
1. Clean out joints immediately before installing joint sealants to comply with joint-sealant
manufacturer's written instructions and the following requirements:
a. Remove all foreign material from joint substrates that could interfere with adhesion
of joint sealant, including dust, paints (except for permanent, protective coatings
tested and approved for sealant adhesion and compatibility by sealant
1) Concrete.
2) Masonry.
3) Unglazed surfaces of ceramic tile.
1) Metal.
2) Glass.
3) Porcelain enamel.
4) Glazed surfaces of ceramic tile.
A. General:
1. Comply with joint-sealant manufacturer's written installation instructions for products and
applications indicated, unless more stringent requirements apply.
1. Comply with recommendations in ASTM C 1193 for use of joint sealants as applicable to
materials, applications, and conditions indicated.
C. Sealant Backings:
1. Install sealant backings of kind indicated to support sealants during application and at
position required to produce cross-sectional shapes and depths of installed sealants
relative to joint widths that allow optimum sealant movement capability.
D. Bond-Breakers:
1. Install bond-breaker tape behind sealants where sealant backings are not used between
sealants and backs of joints.
E. Sealant Installation:
1. Install sealants using proven techniques that comply with the following and at the same
time backings are installed:
a. Place sealants so they directly contact and fully wet joint substrates.
b. Completely fill recesses in each joint configuration.
c. Produce uniform, cross-sectional shapes and depths relative to joint widths that
allow optimum sealant movement capability.
1. Immediately after sealant application and before skinning or curing begins, tool sealants
according to requirements specified in subparagraphs below to form smooth, uniform
beads of configuration indicated; to eliminate air pockets; and to ensure contact and
adhesion of sealant with sides of joint.
1. Neatly cut 48-inch wide rolls of foam compression seal material into strips of appropriate
width to insure force fit between refrigerated display cases and adjacent wall surfaces.
2. Secure foam compression seals in place with adhesive sealant as indicated on drawings.
3.4 CLEANING
A. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by
methods and with cleaning materials approved in writing by manufacturers of joint sealants and
of products in which joints occur.
3.5 PROTECTION
A. Protect joint sealants during and after curing period from contact with contaminating substances
and from damage resulting from construction operations or other causes so sealants are without
END OF SECTION
***********************************************************
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 DEFINITIONS
1.3 DESCRIPTION
B. Conform to commissioning requirements and the commissioning plan issued by the CA.
1. Schedules.
2. Instructions for operation of each piece of equipment for emergencies.
3. Seasonal adjustment.
4. Instructions for energy savings operations and descriptions of the energy savings
strategies in the facility (from O&M Manuals).
C. Warranty Period:
PART 3 - EXECUTION
3.1 STARTUP
A. Contractors shall follow the start-up and initial checkout procedures listed in the Responsibilities
list in this Section and in Division 01 Section General Commissioning Requirements. Division
08 has start-up responsibility and is required to complete systems and sub-systems so they are
fully functional, meeting the design objectives of the Contract Documents. The commissioning
procedures and functional testing do not relieve or lessen this responsibility or shift that
responsibility partially to the commissioning agent, technical inspector, or Government.
B. Functional testing will generally begin upon completion of a system. Functional testing may
proceed prior to the completion of systems or sub-systems at the discretion of the CO.
Beginning system testing before full completion does not relieve the Contractor from fully
completing the system, including all prefunctional checklists.
A. The following O&M manual requirements are in addition to O&M manual documentation
requirements elsewhere in these Specifications.
B. Division 08 shall compile and prepare documentation for all commissioned systems covered in
Division 08 and deliver this documentation to the GC for inclusion in the O&M manuals prior to
the training of Government personnel.
A. The GC shall be responsible for training coordination and scheduling to ensure that training is
completed.
B. The QC shall be responsible for reviewing the content and adequacy of the training of
Government personnel for commissioned equipment or systems. TI will verify compliance.
C. The Division 08 Contractor shall have the following training responsibilities for the
commissioned systems:
1. Provide the TI with a training plan four weeks before the planned training.
2. Provide designated Government personnel with comprehensive orientation and training
in the understanding of the systems and the operation and maintenance of each piece of
commissioned equipment.
3. Training shall start with classroom sessions followed by hands-on training on each piece
of equipment.
4. During any demonstration, should the system fail to perform in accordance with the
requirements of the O&M manual or sequence of operations, the system will be repaired
or adjusted as necessary and the demonstration repeated.
5. The appropriate trade or manufacturer's representative shall provide the instructions on
each major piece of equipment. This person may be the start-up technician for the piece
of equipment, the installing contractor or manufacturer's representative. Practical
8. Hands-on training shall include start-up, operation in all modes possible, including
manual, shut-down and any emergency procedures and preventative maintenance for all
pieces of equipment.
9. Training shall occur after functional testing is complete, unless approved otherwise by the
Contracting Officer.
10. Minimum Duration of Training. Contractor shall meet for 8 hours with facility staff after
completion of the work and instruct them as indicated above.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 05 and Division 08 Design Criteria, Commissary Door Schedule
in Appendix "A", and related Design Standard Plates.
2. Typically, hollow metal doors and frames are used at office / storage areas in non-customer areas, and
customer areas requiring increased durability. Hollow metal door frames with stained solid core wood
doors are typically used in administrative office areas and office / storage areas facing customer areas.
3. Select all hollow metal doors and frames for high use, heavy traffic applications. Design doors and
frames in accordance with ANSI/SDI A250.8, SDI-100 "Recommended Specifications for Standard Steel
Doors and Frames" as Published by the Steel Door Institute.
A. Exterior frames shall be 0.067" minimum base metal thickness (nominal 14 gage) galvanized steel
with reinforcement and grout guards at hardware locations. Frames shall be shop fabricated with
mitered and welded face corners and seamless face joints. Do not use knockdown frames. Secure
frames in masonry construction using adjustable galvanized strap-and-stirrup or T-shaped anchors.
Do not use wire anchors. Grout frames solid.
B. Interior frames shall be 0.053" minimum base metal thickness (nominal 16 gage) (shop primed steel
except where frames are exposed to a refrigerated space and where project conditions require
galvanized steel) with reinforcement and grout guards at hardware locations, except where 0.067"
minimum base metal thickness (nominal 14 gage) galvanized steel security frames are required.
Refer to Commissary Door Schedule in Appendix "A". Frames shall be shop fabricated with mitered
and welded face corners and seamless face joints. Do not use knockdown door frames. Secure
door frames in masonry construction using adjustable galvanized strap-and-stirrup or T-shaped
anchors. Do not use wire anchors. Grout frames solid. Secure door frames in steel stud framed
partitions with stud-wall type anchors welded to steel studs. Spot grout frames at jamb anchor
locations in accordance with Division 09 Section Gypsum Board.
1. Traffic doors located in steel stud framed partitions shall have 0.067" minimum base metal
thickness (nominal 14 gage) flush galvanized steel security frames with 1/4" steel plate at all
hardware attachment points. Reinforcing shall be welded to concealed face of frame.
2. Traffic doors located in concrete masonry unit (CMU) partitions shall have steel channel frames.
Refer to Division 05 Metal Fabrications for further information.
A. Exterior doors shall be thermally insulated 0.053" minimum base metal thickness (nominal 16 gage)
galvanized steel. Fabricate in accordance with ANSI/SDI A250.8 Level 3 and Physical Security
Level A (Extra Heavy Duty), Model 2 (Seamless).
B. Interior doors shall be 0.053" minimum base metal thickness (nominal 16 gage) shop primed steel
except where doors are exposed to a refrigerated space and where project conditions require
galvanized steel. Provide thermally insulated doors at locations where doors are exposed to a
refrigerated space. Fabricate in accordance with ANSI/SDI A250.8 Level 3 and Physical Security
Level A (Extra Heavy Duty), Model 1 (Full Flush).
C. Interior security doors shall be 0.067" minimum base metal thickness (nominal 14 gage) shop
primed steel. Fabricate in accordance with ANSI/SDI A250.8 Level 4 and Physical Security Level A
(Extra Heavy Duty), Model 1 (Full Flush).
June 2011 08 11 13 1
DeCA DESIGN CRITERIA HANDBOOK
08 11 13 HOLLOW METAL DOORS AND
FRAMES
D. Glass vision panels in exterior doors shall be laminated glass. Glass vision panels in interior doors
shall be tempered glass, except at security door locations where laminated glass shall be provided.
Refer to Design Standard Plates for Commissary Door Types in Appendix "A", for vision panel
sizes. Note that vision panel in Cashier's Office security door shall not exceed 24" by 24" in size.
E. Access through wall surfaces above cold storage rooms is frequently required and must be easily
accessible. Provide access via a standard steel door and frame, with passage latch set, in lieu of
conventional access openings as specified in Section 08 31 13 Access Doors and Frames. No
locks are to be provided on these access door openings. Provide HM access doors (2' 8" wide by
3' 8" high) in these walls, allowing access from warehouse area to space above cold storage
rooms as required for service access and maintenance. Locate bottom of access doors
immediately above cold storage room ceilings at 11' 4 " AFF. Standard hollow metal frame, and
stop, shall be continuous on all four sides of door opening.
F. Facilities with roof mounted refrigeration mechanical centers and HVAC systems shall be designed
with a stair tower for roof access. Provide an insulated standard hollow metal door in the stair tower
at roof with appropriate security grade hardware and security alarm contact.
6. Exterior swinging doors shall be designed for security protection in accordance with UFC 4-010-01
DoD Minimum Antiterrorism Standards For Buildings, October 08, 2003, Standard 12, as follows:
A. Ensure that all exterior doors into inhabited areas open outwards. By doing so, the doors will seat
into the door frames in response to an explosive blast, increasing the likelihood that the doors will
not enter the buildings as hazardous debris. Alternatively, position doors such that they will not
be propelled into rooms if they fail in response to a blast or provide other means to ensure they
do not become hazards to building occupants.
END OF SECTION
June 2011 08 11 13 2
SECTION 08 11 13
HOLLOW METAL DOORS AND FRAMES
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 DEFINITIONS
1.3 SUBMITTALS
A. Product Data:
B. Shop Drawings:
1. In addition to requirements below, provide a schedule of standard steel doors and frames
using same reference numbers for details and openings as those on Drawings:
2. Elevations of each door design.
3. Details of doors, including vertical and horizontal edge details.
4. Frame details for each frame type, including dimensioned profiles.
5. Details and locations of reinforcement and preparations for hardware.
6. Details of each different wall opening condition.
7. Details of anchorages, accessories, joints, and connections.
8. Details of glazing frames and stops showing glazing.
9. Details of conduit and preparations for electrified door hardware and controls.
C. Coordination Drawings:
1. Drawings of each opening, including door and frame, drawn to scale and coordinating
door hardware. Show elevations of each door design type, showing dimensions,
locations of door hardware, and preparations for power, signal, and electrified control
systems.
A. Installer Qualifications:
B. Source Limitations:
1. Obtain standard steel doors and frames through one source from a single manufacturer.
1. Assemblies complying with NFPA 80 that are listed and labeled by a qualified testing
agency, for fire-protection ratings indicated, based on testing at as close to neutral
pressure as possible according to NFPA 252 or UL 10C.
A. Delivery:
1. Deliver doors and frames palletized, wrapped, or crated to provide protection during
transit and Project-site storage. Do not use nonvented plastic.
2. Deliver welded frames with two removable spreader bars across bottom of frames, tack
welded to jambs and mullions.
B. Storage:
1. Store doors and frames under cover at Project site. Place units in a vertical position with
heads up, spaced by blocking, on minimum 4-inch- high wood blocking. Avoid using
nonvented plastic or canvas shelters that could create a humidity chamber.
A. Field Measurements: Verify openings by field measurements before fabrication and indicate
measurements on Shop Drawings.
A. Coordinate installation of anchorages for standard steel frames. Furnish setting drawings,
templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor
bolts, and items with integral anchors, that are to be embedded in masonry. Deliver such items
to Project site in time for installation.
PART 2 - PRODUCTS
2.1 MATERIALS
1. ASTM A 1008/A 1008M, Commercial Steel (CS), Type B; suitable for exposed
applications.
1. ASTM A 653/A 653M, Commercial Steel (CS), Type B; with minimum A40 zinc-iron-alloy
(galvannealed) coating designation.
C. Frame Anchors:
1. Interior Frame Anchors: ASTM A 591/A 591M, Commercial Steel (CS), 40Z coating
designation; mill phosphatized.
a. Exterior Frame Anchors: Steel sheet complying with ASTM A 1008/A 1008M or
ASTM A 1011/A 1011M. After fabricating, hot-dip galvanize units to be built into
exterior walls according to ASTM A 153/A 153M, Class B.
1. Fastener system of type suitable for application indicated, fabricated from corrosion-
resistant materials, with clips or other accessory devices for attaching standard steel door
frames of type indicated.
F. Grout:
1. Comply with ASTM C 476, with a slump of 4 inches for standard steel door frames built
into concrete or masonry, as measured according to ASTM C 143/C 143M.
G. Mineral-Fiber Insulation:
I. Bituminous Coating:
1. Cold-applied asphalt mastic, SSPC-Paint 12, compounded for 15-mil dry film thickness
per coat. Provide inert-type noncorrosive compound free of asbestos fibers, sulfur
components, and other deleterious impurities.
A. General:
1. Provide doors of design indicated, not less than thickness indicated; fabricated with
smooth surfaces, without visible joints or seams on exposed faces unless otherwise
indicated. Comply with ANSI/SDI A250.8.
2. Design: Flush panel.
3. Core Construction: Manufacturer's standard core indicated that produces doors
complying with ANSI/SDI A250.8.
4. Vertical Edges for Single-Acting Doors: Edge profile in accordance with manufacturers
standard for the Model specified.
5. Top and Bottom Edges: Closed with flush or inverted 0.042-inch- thick end closures or
channels of same material as face sheets.
6. Tolerances: Comply with SDI 117, "Manufacturing Tolerances for Standard Steel Doors
and Frames."
B. Exterior Doors:
1. Face sheets fabricated from metallic-coated steel sheet. Provide doors complying with
requirements indicated below by referencing ANSI/SDI A250.8 for level and model and
ANSI/SDI A250.4 for physical-endurance level:
C. Interior Doors:
1. Face sheets fabricated from cold-rolled steel sheet. Provide doors complying with
requirements indicated below by referencing ANSI/SDI A250.8for level and model and
ANSI/SDI A250.4 for physical-endurance level:
D. Hardware Reinforcement:
1. Fabricate according to ANSI/SDI A250.6 with reinforcement plates from same material as
door face sheets
1. Fabricate concealed stiffeners and hardware reinforcement from either cold- or hot-rolled
steel sheet.
A. General:
1. Comply with ANSI/SDI A250.8 and with details indicated for type and profile.
2. Fabricate frames with mitered or coped corners. Fabricate frames as full profile welded
frames.
3. Fabricate from metallic-coated steel sheet.
B. Exterior Frames:
C. Interior Frames:
D. Hardware Reinforcement:
1. Fabricate according to ANSI/SDI A250.6 with reinforcement plates from same material as
frames and to comply with the following:
1. Masonry Type: Adjustable strap-and-stirrup or T-shaped anchors to suit frame size, not
less than 0.042 inch thick, with corrugated or perforated straps not less than 2 inches
wide by 10 inches long. Do not use wire anchors.
2. Stud-Wall Type: Designed to engage stud, welded to back of frames; not less than 0.042
inch thick.
3. Postinstalled Expansion Type for In-Place Masonry: Minimum 3/8-inch- diameter bolts
with expansion shields or inserts. Provide pipe spacer from frame to wall, with throat
reinforcement plate, welded to frame at each anchor location.
F. Floor Anchors:
1. Formed from same material as frames, not less than 0.042 inch thick, and as follows:
a. Monolithic Concrete Slabs: Clip-type anchors, with two holes to receive fasteners.
b. Separate Topping Concrete Slabs: Adjustable-type anchors with extension clips,
allowing not less than 2-inch height adjustment. Terminate bottom of frames at
finish floor surface.
G. Hardware Reinforcement:
1. Fabricate according to ANSI/SDI A250.6 with reinforcement plates from same material as
frames.
H. Ceiling Struts:
I. Grout Guards:
1. Formed from same material as frames, not less than 0.016-inch thick.
J. Mullions and Transom Bars: Join to adjacent members by welding or rigid mechanical anchors.
1. Minimum 0.032 inch thick, fabricated from same material as door face sheet in which
they are installed.
1. Formed integral with standard steel frames, minimum 5/8 inch high, unless otherwise
indicated.
1. Minimum 0.032 inch thick, fabricated from same material as frames in which they are
installed.
A. Interior Doors:
1. Provide louvers where indicated, that comply with SDI 111C, with blades or baffles
formed of 0.020-inch- thick, cold-rolled steel sheet set into 0.032-inch-thick steel frame.
2.6 FABRICATION
A. General:
1. Fabricate standard steel doors and frames to be rigid and free of defects, warp, or
buckle. Accurately form metal to required sizes and profiles, with minimum radius for
thickness of metal. Where practical, fit and assemble units in manufacturer's plant. To
ensure proper assembly at Project site, clearly identify work that cannot be permanently
factory assembled before shipment.
B. Tolerances:
1. Where frames are fabricated in sections due to shipping or handling limitations, provide
alignment plates or angles at each joint, fabricated of same thickness metal as frames.
This does not permit knockdown frames or slip-on drywall frames to be substituted for full
profile welded frames.
2. Full Profile Welded Frames: Weld flush face joints continuously; grind, fill, dress, and
make smooth, flush, and invisible.
3. Sidelight and Transom Bar Frames: Provide closed tubular members with no visible face
seams or joints; fabricated from same material as door frame. Fasten members at
crossings and to jambs by butt welding.
4. Provide countersunk, flat- or oval-head exposed screws and bolts for exposed fasteners,
unless otherwise indicated.
5. Grout Guards: Weld guards to frame at back of hardware mortises in frames to be
grouted.
6. Floor Anchors: Weld anchors to bottom of jambs and mullions with at least four spot
welds per anchor.
a. Masonry Type: Locate anchors not more than 18 inches from top and bottom of
frame. Space anchors not more than 32 inches o.c. and as follows:
b. Stud-Wall Type: Locate anchors not more than 18 inches from top and bottom of
frame. Space anchors not more than 32 inches o.c. and as follows:
c. Postinstalled Expansion Type: Locate anchors not more than 6 inches from top
and bottom of frame. Space anchors not more than 26 inches o.c.
8. Door Silencers: Except on weather-stripped doors, drill stops to receive door silencers as
follows. Keep holes clear during construction.
a. Single-Door Frames: Drill stop in strike jamb to receive three door silencers.
b. Double-Door Frames: Drill stop in head jamb to receive two door silencers.
E. Hardware Preparation:
1. Factory prepare standard steel doors and frames to receive templated mortised
hardware; include cutouts, reinforcement, mortising, drilling, and tapping, according to the
Door Hardware Schedule and templates furnished as specified in Division 08 Section
Door Hardware.
2. Reinforce doors and frames to receive nontemplated mortised and surface-mounted door
hardware.
3. Comply with applicable requirements in ANSI/SDI A250.6 and ANSI/DHI A115 Series
specifications for door and frame preparation for hardware. Locate hardware as
indicated on Shop Drawings or, if not indicated, according to ANSI/SDI A250.8.
1. Provide stops and moldings around glazed lites where indicated. Form corners of stops
and moldings with butted or mitered hairline joints.
2. Single Glazed Lites: Provide fixed stops and moldings welded on secure side of door or
frame.
3. Multiple Glazed Lites: Provide fixed and removable stops and moldings such that each
glazed lite is capable of being removed independently.
4. Provide fixed frame moldings on outside of exterior and on secure side of interior doors
and frames.
5. Provide loose stops and moldings on inside of doors and frames.
1. Apply shop primer specified below immediately after surface preparation and
pretreatment.
PART 3 - EXECUTION
3.1 EXAMINATION
1. Examine substrates, areas, and conditions, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting performance of
standard steel doors and frames.
2. Examine roughing-in for embedded and built-in anchors to verify actual locations of
standard steel frame connections before frame installation.
3. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Remove Spreaders:
1. Prior to installation and with installation spreaders in place, adjust and securely brace
standard steel door frames for squareness, alignment, twist, and plumb:
1. Drill and tap doors and frames to receive nontemplated mortised and surface-mounted
door hardware.
A. General:
1. Provide doors and frames of sizes, thicknesses, and designs indicated. Install standard
steel doors and frames plumb, rigid, properly aligned, and securely fastened in place;
comply with Drawings and manufacturer's written instructions.
1. Install standard steel frames for doors, sidelights, transoms, borrowed lights, and other
openings, of size and profile indicated. Comply with ANSI/SDI A250.11.
2. Set frames accurately in position; plumbed, aligned, and braced securely until permanent
anchors are set. After wall construction is complete, remove temporary braces, leaving
surfaces smooth and undamaged.
3. Floor Anchors: Provide floor anchors for each jamb and mullion that extends to floor and
secure with postinstalled expansion anchors.
1. Fit hollow-metal doors accurately in frames, within clearances specified below. Shim as
necessary.
2. Non-Fire-Rated Standard Steel Doors:
D. Glazing:
1. Comply with installation requirements in Division 08 Section Glazing and with standard
steel door and frame manufacturer's written instructions.
2. Secure stops with countersunk flat- or oval-head machine screws spaced uniformly not
more than 9 inches o.c., and not more than 2 inches o.c. from each corner.
A. Final Adjustments:
1. Check and readjust operating hardware items immediately before final inspection. Leave
work in complete and proper operating condition. Remove and replace defective work,
including standard steel doors or frames that are warped, bowed, or otherwise
unacceptable.
B. Clean:
1. Remove grout and other bonding material off standard steel doors and frames
immediately after installation.
C. Prime-Coat Touchup:
1. Immediately after erection, sand smooth rusted or damaged areas of prime coat and
apply touchup of compatible air-drying primer.
D. Metallic-Coated Surfaces:
1. Clean abraded areas and repair with galvanizing repair paint according to manufacturer's
written instructions.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 08 Design Criteria, Commissary Door Schedule in Appendix
'"A"', and related Design Standard Plates.
2. Typically, solid core flush wood doors are used throughout administrative office areas and office/storage
areas facing customer areas.
4. Doors shall be Custom Grade in accordance with the "Architectural Woodwork Standards." A
structural composite lumber core (SCLC) is used for durability and so that minimum stile widths at
glazed doors may be provided in accordance with specified warranty requirements.
5. Wood veneer shall be plain sliced red oak with factory applied transparent finish. Doors shall be
factory fit to suit frame-opening sizes and factory machined for hardware that is not surface applied.
6. Where required, doors shall have wood louvers and wood frames for glass vision panels, matching
wood veneer on door.
END OF SECTION
June 2011 08 14 16 1
SECTION 08 14 16
FLUSH WOOD DOORS
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
1. For each type of door. Include details of core and edge construction, louvers, and trim for
openings. Include factory-finishing specifications.
B. LEED Submittals:
1. Certificates for Credit MR 7: Chain-of-custody certificates certifying that flush wood doors
comply with forest certification requirements.[ Include evidence that manufacturer is
certified for chain of custody by an FSC-accredited certification body.]
C. Shop Drawings:
1. Indicate location, size, and hand of each door; elevation of each kind of door;
construction details not covered in Product Data; location and extent of hardware
blocking; and other pertinent data.
1. Factory finishes applied to actual door face materials, approximately 8 by 10 inches, for
each material and finish. For each wood species and transparent finish, provide set of
three samples showing typical range of color and grain to be expected in the finished
work.
2. Corner sections of doors, approximately 8 by 10 inches, with door faces and edgings
representing typical range of color and grain for each species of veneer and solid lumber
required. Finish sample with same materials proposed for factory-finished doors.
3. Louver blade and frame sections, 6 inches long, for each material and finish specified.
4. Frames for light openings, 6 inches long, for each material, type, and finish required.
E. Submittal List:
A. Source Limitations:
1. Obtain flush wood doors through one source from a single manufacturer.
B. Quality Standard:
C. Manufacturer Qualifications:
A. Requirements:
1.5 WARRANTY
A. Special Warranty:
PART 2 - PRODUCTS
B. Low-Emitting Materials:
1. Provide doors made with adhesives and composite wood products that do not contain
urea formaldehyde.
A. Wood Louvers:
B. Beads:
2.3 FABRICATION
A. Factory Fabrication:
B. Factory Machining:
1. Factory machine doors for hardware that is not surface applied. Locate hardware to
comply with DHI-WDHS-3. Comply with final hardware schedules, door frame Shop
Drawings, BHMA-156.115-W, and hardware templates.
2. Coordinate measurements of hardware mortises in metal frames to verify dimensions and
alignment before factory machining.
C. Openings:
a. Light Openings: Trim openings with moldings of material and profile indicated.
b. Louvers: Factory install louvers in prepared openings.
A. General:
a. Finish faces, all four edges, edges of cutouts, and mortises. Stains and fillers may
be omitted on top and bottom edges, edges of cutouts, and mortises.
B. Transparent Finish:
1. Grade: Premium.
2. Finish: System-11, catalyzed polyurethane.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine Doors and Installed Door Frames, with Installer Present, Before Hanging Doors:
1. Verify that installed frames comply with indicated requirements for type, size, location,
and swing characteristics and have been installed with level heads and plumb jambs.
2. Reject doors with defects.
3. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Hardware:
B. Installation Instructions:
C. Factory-Fitted Doors:
D. Factory-Finished Doors:
3.3 ADJUSTING
A. Operation:
B. Finished Doors:
1. Replace doors that are damaged or do not comply with requirements. Doors may be
repaired or refinished if work complies with requirements and shows no evidence of
repair or refinishing.
DESIGN CRITERIA
1. Related Sections: See related Division 08 Design Criteria, Commissary Door Schedule in Appendix A,
and related Design Standard Plates.
2. Provide access through finished walls and ceilings for concealed mechanical and electrical items, such
as transformers, mixing valves, shut-off valves, and any other items requiring maintenance or access.
Provide adequate general notes on contract documents requiring this access.
3. Typically, screwdriver-operated cam latches shall be provided on access doors, except at locations
requiring frequent access / inspection and sized for passage of maintenance personnel. Locations
requiring frequent access / inspection shall be identified (both size and location) on the drawings, and
shall be self-latching bolt operated by an integral knurled knob turn.
4. Access through wall surfaces above cold storage rooms is frequently required and must be easily
accessible. Provide access via a standard hollow metal door and frame in accordance with Section
08 11 13 Hollow Metal Doors and Frames.
END OF SECTION
June 2011 08 31 13 1
SECTION 08 31 13
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
1. For each type of access door assembly specified, including details of construction relative
to materials, individual components, profiles, and finishes.
B. Submittal List:
A. Single-Source Responsibility:
1. Obtain access doors for entire Project from one source and by a single manufacturer.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Steel Sheet:
1. Uncoated or electrolytic zinc coated, ASTM A 879/A 879M, with cold-rolled steel sheet
substrate complying with ASTM A 1008/A 1008M, Commercial Steel, exposed.
3. Frame: Minimum 0.060-inch- thick sheet metal with 1-inch- wide, surface-mounted trim.
4. Hinges: Concealed spring pin or continuous type.
5. Latch: Screwdriver- operated cam latch unless otherwise indicated.
2.3 FABRICATION
A. General:
1. Manufacture each access door assembly as an integral unit ready for installation.
1. Continuous welded construction. Grind welds smooth and flush with adjacent surfaces.
Furnish attachment devices and fasteners of type required to secure access panels to
types of supports indicated.
C. Locking Devices:
1. Furnish number required to hold door in flush, smooth plane when closed.
PART 3 - EXECUTION
3.1 PREPARATION
A. Coordination:
1. Advise Installers of other work about specific requirements relating to access door
installation, including sizes of openings to receive access door and frame, as well as
locations of supports, inserts, and anchoring devices. Furnish inserts and anchoring
devices for access doors that must be built into other construction. Coordinate delivery
with other work to avoid delay.
3.2 INSTALLATION
A. General:
A. Adjust hardware and panels after installation for proper operation. Remove and replace panels
or frames that are warped, bowed, or otherwise damaged.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 08 Design Criteria, Commissary Door Schedule in Appendix A,
and related Design Standard Plates.
2. Both sectional overhead doors and overhead coiling doors are used in commissary facilities. The type
to be used on a specific project should be verified by the DeCA Project Manager at the start of design.
Refer to Section 08 36 13 Sectional Doors for additional information.
3. Four different types of overhead coiling doors are typically used in commissary facilities.
A. Type OCD-1: Manually operated insulated exterior coiling service door in combination with manually
operated ventilating security door. This door type is typically used at grade level receiving doors to
permit fresh air ventilation while at the same time maintain security and rodent control.
B. Type OCD-2: Manually operated insulated exterior coiling service door. This door type is typically
used at dock height receiving doors. It is also used sometimes when multiple grade level receiving
doors are present.
C. Type OCD-3: Manually operated non-insulated interior coiling counter doors. This door type is
typically used where a service window and counter is provided in the administrative office area.
D. Type OCD-4: Manually operated non-insulated interior coiling service doors. This door type is
typically used at service opening between refrigeration equipment mezzanine and receiving area in
warehouse. Forklift trucks are used to lift commercial refrigeration and other equipment up to
mezzanine. Safety chains are required at this door opening as specified in Section 055013 Metal
Fabrications. This requirement needs to be coordinated with door schedule.
E. If hurricane resistant sectional overhead doors are required for Project, add performance
requirements to specification section.
END OF SECTION
June 2011 08 33 23 1
SECTION 08 33 23
OVERHEAD COILING DOORS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Type OCD 1: Manual operated insulated exterior coiling service doors in combination
with manual operated coiling ventilation doors.
2. Type OCD 2: Manual operated insulated exterior coiling service doors.
3. Type OCD 3: Manual operated non-insulated interior coiling counter doors.
4. Type OCD 4: Manual operated non-insulated interior coiling service doors.
1.2 DEFINITIONS
A. Operation Cycle: One complete cycle of a door begins with the door in the closed position. The
door is then moved to the open position and back to the closed position.
A. General Performance:
1. Exterior overhead coiling doors shall meet performance requirements specified without
failure due to defective manufacture, fabrication, installation, or other defects in
construction and without requiring temporary installation of reinforcing components.
2. Delegated Design overhead coiling doors, including comprehensive engineering analysis
by a qualified professional engineer, using performance requirements and design criteria
indicated.
B. Structural Performance:
1. Provide overhead coiling doors capable of withstanding the effects of gravity loads, wind
loads and the following loads and stresses without evidencing permanent deformation of
door components according to SEI/ASCE 7:
a. Wind Load:
1) Provide exterior overhead coiling door assemblies, including anchorage,
capable of withstanding wind pressures acting inward and outward normal
to the plane of the wall.
2) Refer to Division 01 Section Summary of Work for wind loading design
criteria.
3) Determine design loads using the appropriate coefficients for the exterior
overhead coiling door assembly configurations indicated.
C. Operation-Cycle Requirements:
1. Design overhead coiling exterior service and ventilation door components and operator to
operate for not less than 100,000 cycles.
2. Provide interior service door components and operators capable of operating for not less
than 20,000 cycles.
1.4 SUBMITTALS
A. Product Data:
1. For each type and size of overhead coiling door and accessory. Include details of
construction relative to materials, dimensions of individual components, profiles, and
finishes. Provide roughing-in diagrams, operating instructions, and maintenance
information. Include the following:
B. Delegated-Design Submittal:
1. For overhead coiling doors indicated to comply with performance requirements and
design criteria, including analysis data signed and sealed by the qualified professional
engineer responsible for their preparation.
C. Submittal List:
A. Installer Qualifications:
B. Source Limitations:
1. Obtain overhead coiling doors through one source from a single manufacturer.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Door Curtain:
a. Exterior Service Door Steel Door Curtain Exterior (Front) Slats: Structural-quality,
cold-rolled galvanized steel sheets complying with ASTM A 653/A 653M, with G90
zinc coating. Provide manufacturer's standard flat-profile slats. 0.033 inch (20
gage) minimum base-metal (uncoated) thickness.
b. Interior Service Door Steel Door Curtain Slats: Structural-quality, cold-rolled
galvanized steel sheets complying with ASTM A 653/A 653M. Provide
manufacturer's standard flat-profile slats. 0.027 inch (22 gage) minimum base-
metal (uncoated) thickness.
1. Manufacturer's standard locks on not less than alternate curtain slats for curtain
alignment and resistance against lateral movement.
1. Consisting of 2 angles, each not less than 1-1/2 by 1-1/2 by 1/8 inch thick, either
galvanized or stainless-steel or aluminum extrusions to suit type of curtain slats.
F. Astragal for Interior Doors: Equip each door bottom bar with a replaceable, adjustable,
continuous, compressible gasket of flexible vinyl, rubber, or neoprene as a cushion bumper.
1. Fabricate curtain jamb guides of steel angles, or channels and angles, with sufficient
depth and strength to retain curtain, to allow curtain to operate smoothly, and to
withstand loading. Build up units with not less than 3/16-inch- thick, galvanized steel
sections complying with ASTM A 36, and ASTM A 123. Slot bolt holes for guide
adjustment. Provide removable stops on guides to prevent overtravel of curtain and a
continuous bar for holding windlocks.
1. Fabricate curtain jamb guides of angles, or channels and angles of material and finish to
match curtain slats, with sufficient depth and strength to retain curtain, to allow curtain to
A. Door Curtains:
a. Perforated Aluminum Door Curtain Slats: ASTM B 209 sheet or ASTM B 221
extrusions, alloy and temper standard with manufacturer for type of use and finish
indicated; thickness of 0.050 inch and as required to meet requirements.
B. Endlocks:
C. Bottom Bar:
1. Consisting of two angles, each not less than 1-1/2 by 1-1/2 by 1/8 inch thick; fabricated
from aluminum extrusions to match curtain slats and finish.
D. Astragal:
1. Equip each door bottom bar with a replaceable, adjustable, continuous, compressible
gasket of flexible vinyl, rubber, or neoprene as a cushion bumper.
1. Fabricate curtain jamb guides of steel angles, or channels and angles, with sufficient
depth and strength to retain curtain and to allow curtain to operate smoothly. Build up
units with not less than 3/16-inch- thick, galvanized steel sections complying with ASTM
A 36, and ASTM A 123. Slot bolt holes for guide adjustment. Provide removable stops
on guides to prevent overtravel of curtain.
1. Provide a separate duel track mounted behind the exterior coiling service door to allow
independent door operation.
2. Separate hood from that of service door.
3. Fabricate and install ventilation door separate from service door so that each door may
be removed and serviced independent of the other.
A. Hood:
B. Weatherseals:
C. Vision-Panel Glazing:
1. Manufacturer's standard clear glazing, fabricated from transparent acrylic sheet; set in
glazing channel secured to curtain slats.
1. Provide galvanized steel lifting handles on each side of door. Provide pull-down straps for
doors more than 84 inches high.
1. Fabricate with side locking bolts to engage through slots in tracks for locking by padlock,
located on both left and right jamb sides, operable from coil side.
1. Fabricate locking device assembly with lock, spring-loaded dead bolt, operating handle,
cam plate, and adjustable locking bar to engage through slots in tracks.
2. Locking Bars: Full-disc Cremone type, both jamb sides, operable from inside only.
3. Lock cylinder is specified in Division 08 Section Door Hardware.
A. General:
C. Spring Balance:
1. Provide spring balance of one or more oil-tempered, heat-treated steel helical torsion
springs. Size springs to counterbalance weight of curtain, with uniform adjustment
accessible from outside barrel. Provide cast-steel barrel plugs to secure ends of springs
to barrel and shaft.
1. Fabricate torsion rod for counterbalance shaft of cold-rolled steel, sized to hold fixed
spring ends and carry torsional load.
E. Brackets:
1. Provide manual chain-hoist operator consisting of endless steel hand chain, chain pocket
wheel and guard, and gear-reduction unit with a maximum 35-lbf force for door operation.
Provide alloy steel hand chain with chain holder secured to operator guide.
B. Push-up Operation for Non-Insulated Service Doors, Ventilation Doors, and Counter Doors:
1. Design counterbalance mechanism so required lift or pull for door operation does not
exceed 25 lbf.
A. General:
1. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
1. Variations in appearance of abutting or adjacent pieces are acceptable if they are within
one-half of the range of approved Samples. Noticeable variations in the same piece are
not acceptable. Variations in appearance of other components are acceptable if they are
within the range of approved Samples and are assembled or installed to minimize
contrast.
A. Finish Designation:
1. Finish designations prefixed by AA comply with the system established by the Aluminum
Association for designating aluminum finishes.
A. General:
1. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
B. Contractors Option:
1. At Contractors option provide factory primer for field finish specified in Division 09
Section Painting and Coating, baked finish, or powder-coat finish.
a. Factory Primer for Field Finish: Manufacturer's standard primer, compatible with
field-applied finish according to coating manufacturer's written instructions for
cleaning, pretreatment, application, and minimum dry film thickness.
b. Baked Finish: Baked finish consisting of primer and topcoat according to coating
manufacturer's written instructions for cleaning, pretreatment, application,
thermosetting, and minimum dry film thickness.
c. Powder-Coat Finish: Powder-coat finish consisting of primer and topcoat
according to coating manufacturer's written instructions for cleaning, pretreatment,
application, thermosetting, and minimum dry film thickness.
C. Color:
PART 3 - EXECUTION
3.1 INSTALLATION
A. General:
1. Install door and operating equipment complete with necessary hardware, jamb and head
mold strips, anchors, inserts, hangers, and equipment supports according to Shop
Drawings, manufacturer's written instructions, and as specified.
2. Do not install overhead coiling door components with through-bolts to wall.
1. Lubricate bearings and sliding parts; adjust doors to operate easily, free from warp, twist,
or distortion and fitting weathertight for entire perimeter.
2. Adjust seals to provide weathertight fit around entire perimeter.
3.3 DEMONSTRATION
A. Startup Services:
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 08 Design Criteria, Commissary Door Schedule in Appendix A,
and related Design Standard Plates.
2. Both sectional overhead doors and overhead coiling doors are used in commissary facilities. The type
to be used on a specific project should be verified by the DeCA Project Manager at the start of design.
Refer to Section 08 33 23 Overhead Coiling Doors for additional information.
3. Two different types of sectional overhead doors are typically used in commissary facilities.
A. Type 1: Manually operated insulated exterior sectional door in combination with manually operated
ventilating security door. This door type is typically used at grade level receiving doors to permit
fresh air ventilation while at the same time maintain security and rodent control.
B. Type 2: Manually operated insulated exterior sectional door. This door type is typically used at dock
height receiving doors. It is also used when multiple grade level receiving doors are present.
4. If hurricane resistant sectional overhead doors are required for Project, add performance
requirements to Specification Section.
END OF SECTION
June 2011 08 36 13 1
SECTION 08 36 13
SECTIONAL DOORS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Type SOD-1: Manual operated insulated exterior sectional doors in combination with
manual operated ventilation doors.
2. Type SOD-2: Manual operated insulated exterior sectional doors.
1.2 DEFINITIONS
A. Operation Cycle: One cycle of a door is complete when it is moved from the closed position to
the fully open position and returned to the closed position.
A. General Performance:
1. Sectional doors shall meet performance requirements specified without failure due to
defective manufacture, fabrication, installation, or other defects in construction and
without requiring temporary installation of reinforcing components.
B. Delegated Design:
C. Structural Performance:
1. Provide sectional overhead doors capable of withstanding the effects of gravity loads and
the following loads and stresses without evidencing permanent deformation of door
components according to ASCE/SEI 7:
a. Wind Loads:
D. Operation-Cycle Requirements:
1. Provide sectional door components and operators capable of operating for not less than
100,000 cycles.
2. Provide ventilation door components and operators capable of operating for not less than
15,000 cycles.
1.4 SUBMITTALS
A. Product Data:
1. For each type and size of sectional overhead door and accessory. Include the following:
B. LEED Submittal:
1. Certificates for Credit MR 7: Chain-of-custody certificates certifying that flush wood doors
comply with forest certification requirements.[ Include evidence that manufacturer is
certified for chain of custody by an FSC-accredited certification body.] Include
statement indicating costs for each certified wood product.
C. Delegated-Design Submittal:
1. For sectional doors indicated to comply with performance requirements and design
criteria, including analysis data signed and sealed by the qualified professional engineer
responsible for their preparation.
D. Submittal List:
Reference Submittal Item Quantity Action
A. Installer Qualifications:
B. Source Limitations:
1. Obtain sectional overhead doors through one source from a single manufacturer.
1. Fabricate sectional doors to comply with DASMA 102 unless otherwise indicated.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Materials:
1. Construct door sections including face sheets and frames from zinc-coated (galvanized),
cold-rolled, commercial steel (CS) sheet, complying with ASTM A 653/A 653M, G60
coating designation.
2. Minimum Base-Metal (Uncoated) Thickness for Exterior-Section Faces: 0.033 inch (20
gage).
3. Exterior-Section Face: Manufacturer's standard grooved, ribbed, or fluted.
1. Fabricate door panels from a single sheet to provide sections not more than 24 inches
high and nominally 2 inches deep. Roll horizontal meeting edges to a continuous,
interlocking, keyed, rabbeted, shiplap, or tongue-in-groove weathertight seal, with a
reinforcing flange return.
2. For insulated doors, provide door sections with continuous thermal-break construction,
separating faces of door.
C. Stiles:
1. Enclose open sections with channel end stiles formed from not less than 0.064-inch- thick
galvanized steel sheet and weld end stiles to door section in place. Provide intermediate
stiles formed from not less than 0.064-inch- thick galvanized steel sheet, cut to door
section profile, and welded in place.
2. Stile Spacing: Not more than 48 inches apart.
1. Reinforce bottom section with a continuous channel or angle complying with bottom-
section profile and allowing installation of astragal.
E. Section Reinforcement:
F. Hardware Reinforcement:
G. Thermal Insulation:
1. Insulate inner core of steel sections with door manufacturer's standard CFC-free
polyurethane insulation, foamed in place to completely fill inner core of section and
pressure bonded to face sheets to prevent delamination under wind load, and with
maximum flame-spread and smoke-developed indexes of 75 and 450, respectively,
according to ASTM E 84. Enclose insulation completely within steel sections that
incorporate the following inside facing material, with no exposed insulation material
evident:
1. Fabricate sections so finished door assembly is rigid and aligned, with tight hairline joints
and free of warp, twist, and deformation.
1. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
2. Surface Preparation: Clean galvanized surfaces with nonpetroleum solvent so surfaces
are free of oil and other contaminants.
a. Pretreat zinc-coated steel, after cleaning, with a conversion coating of type suited
to organic coating applied over it.
3. Apply manufacturer's standard primer to both door faces after forming, according to
coating manufacturer's written instructions for application and minimum dry film
thickness.
4. At Contractors option provide factory primer for field finish specified in Division 09
Section Painting and Coating, baked finish, or powder-coat finish.
a. Factory Primer for Field Finish: Manufacturer's standard primer, compatible with
field-applied finish according to coating manufacturer's written instructions for
cleaning, pretreatment, application, and minimum dry film thickness.
b. Baked Finish: Baked finish consisting of primer and topcoat according to coating
manufacturer's written instructions for cleaning, pretreatment, application,
thermosetting, and minimum dry film thickness.
c. Powder-Coat Finish: Powder-coat finish consisting of primer and topcoat
according to coating manufacturer's written instructions for cleaning, pretreatment,
application, thermosetting, and minimum dry film thickness.
A. Door Frame:
1. Construct door sections with extruded-aluminum shapes, complying with ASTM B 221,
alloy and temper recommended by aluminum producer and finisher for type of use and
finish indicated, with wall thickness not less than 0.065 inch. Join stiles and rails by
welding or with concealed, 1/4-inch- minimum-diameter, aluminum or nonmagnetic
stainless-steel through bolts, full height of door section. Provide reinforcement for
hardware attachment.
B. Screen:
1. Fabricate screen of stainless steel woven wire cloth, complying with ASTM E 437.
2. Insect Screen Wire Cloth: B Medium, 30 by 30 mesh, 0.011-inch) wire diameter, 0.0223-
inch-square) opening size, 44.8 percent free area.
3. Weave type: Manufacturer's standard for wire cloth indicated.
4. Metal composition: Type 304 stainless steel.
1. Lift Type: Vertical lift except where clearances limit type to high lift. Do not provide
standard or low lift types unless specifically indicated.
2. Mounting hardware shall be standard commercial grade 2- or 3-inch ten ball rollers, track,
galvanized steel 11 gage hinges.
3. Provide a separate duel track mounted behind the sectional door to allow independent
door operation.
4. Provide manufacturers standard torsion spring kit.
5. Provide pull brackets at the bottom of each side of the door.
6. Locking Device: Fabricate with hasps for locking by padlock, located on both-jambs,
operable from inside only.
7. Separate hood from that of section door.
8. Fabricate and install ventilation door separate from service door so that each door may
be removed and serviced independent of the other.
A. Tracks:
1. Manufacturer's standard, galvanized steel track system, sized for door size and weight,
designed for vertical lift except where clearances limit type to high lift, and complying with
ASTM A 653/A 653M for minimum G60 zinc coating. Do not provide standard or low lift
types unless specifically indicated. Provide complete track assembly including brackets,
bracing, and reinforcement for rigid support of ball-bearing roller guides for required door
type and size. Slot vertical sections of track spaced at 2 inches apart for door-drop safety
device. Slope tracks at proper angle from vertical or design to ensure tight closure at
jambs when door unit is closed. Weld or bolt to track supports.
C. Weatherseals:
D. Windows:
1. Type and size indicated and in arrangement shown. Set glazing in vinyl, rubber, or
neoprene glazing channel for metal-framed doors and elastic glazing compound for wood
doors, as required. Provide removable stops of same material as door-section frames.
A. General:
B. Hinges:
1. Heavy-duty galvanized steel hinges of not less than 0.0747-inch- thick, uncoated steel at
each end stile and at each intermediate stile, according to manufacturer's written
recommendations for door size. Attach hinges to door sections through stiles and rails
with bolts and lock nuts or lock washers and nuts. Use rivets or self-tapping fasteners
where access to nuts is not possible. Provide double-end hinges where required, for
doors exceeding 16 feet in width, unless otherwise recommended by door manufacturer.
C. Rollers:
1. Heavy-duty rollers with steel ball bearings in case-hardened steel races, mounted with
varying projections to suit slope of track. Extend roller shaft through both hinges where
double hinges are required. Provide 3-inch- diameter roller tires for 3-inch- wide track
and 2-inch- diameter roller tires for 2-inch- wide track.
2. Tire Material: Case-hardened steel.
D. Push/Pull Handles:
E. Locking Device:
1. Fabricate with hasps for locking by padlock, located on both-jambs, operable from inside
only.
A. Torsion Spring:
B. Cable Drums:
1. Include a spring-loaded, steel or bronze cam mounted to bottom door roller assembly on
each side and designed to automatically stop door if either cable breaks.
D. Bracket:
1. Provide anchor support bracket as required to connect stationary end of spring to the wall
and to level shaft and prevent sag.
E. Spring Bumper:
1. Provide a spring bumper at each horizontal track to cushion door at end of opening
operation.
A. Push-up Operation:
1. Lift handles and pull rope for raising and lowering doors, operating with a maximum 25-lbf
lift or pull.
PART 3 - EXECUTION
3.1 INSTALLATION
A. General:
1. Install door, track, and operating equipment complete with necessary hardware, jamb and
head molding strips, anchors, inserts, hangers, and equipment supports according to
Shop Drawings, manufacturer's written instructions, and as specified.
2. Do not through-bolt exterior door supports or operating equipment to wall.
B. Track Installation:
1. Fasten vertical track assembly to framing, spaced not less than 24 inches apart. Hang
horizontal track from structural overhead framing with angle or channel hangers fastened
to framing by welding or bolting or both. Provide sway bracing, diagonal bracing, and
reinforcement as required for rigid installation of track and door-operating equipment.
3.2 ADJUSTING
A. General:
1. Adjust hardware and moving parts to function smoothly so that doors operate easily, free
of warp, twist, or distortion
B. Touch-up Painting:
1. Immediately after welding galvanized track to track supports, clean field welds and
abraded galvanized surfaces and repair galvanizing to comply with ASTM A 780.
3.3 DEMONSTRATION
A. Training:
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 05, Division 08, and Division 13 Design Criteria, Commissary
Door Schedule in Appendix "A", and related Design Standard Plates.
2. This Section includes double action, self-closing, lightweight, impact resistant doors (i.e., traffic doors)
and flexible vertical strip barrier doors (i.e., plastic strip curtains).
A. Type "FF" non-sealed traffic doors are typically used at air-lock vestibules located between
conditioned sales areas and non-conditioned storage areas. This door type also provided at bakery
/deli service entrance, with padlock brackets so doors can be secured during non-business hours.
Coordinate with door schedule.
B. Type "GG" sealed traffic doors are typically used at cold storage room door openings with frequent
pedestrian, as well as forklift traffic, that do not have sliding or swinging cold storage doors.
C. Type "O" plastic strip curtains are used at cold storage room door openings that have either sliding
or swinging cold storage doors, to minimize loss of refrigeration cooling when cold storage doors
are open.
3. Color of traffic doors shall be indicated in the Contract Documents. Standard color shall be "black."
4. Traffic doors are subject to heavy usage. It is imperative that structurally adequate door frames be
provided at all traffic door locations.
A. Cold storage room wall panels have built-in structural framing to accommodate traffic doors.
Stainless steel frames (18 gauge) shall wrap head and both jambs of door opening to provide
additional rigidity and impact protection.
B. Structural steel channels (6" minimum face width) shall be used as door frames at concrete
masonry unit (CMU) partitions. Channels shall be securely anchored to CMU construction and
grouted solid.
C. Reinforced 14 gauge flush galvanized steel security frames shall be used at gypsum wallboard
(GWB) partitions. Frames shall be securely anchored to partition framing and floor. Reinforce
frames with 1/4"steel plate at all hardware attachment locations. Reinforcing shall be welded to
concealed face of frame.
END OF SECTIO
June 2011 08 38 00 1
SECTION 08 38 00
TRAFFIC DOORS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Double action, self-closing, lightweight, impact resistant doors of the following types:
1.2 SUBMITTALS
A. Product Data:
B. Submittal List:
A. Protect doors during transit, storage and handling to prevent damage, soiling and deterioration.
Store products in manufacturers unopened packages until ready for installation. Do not lay flat.
2.1 MANUFACTURERS
6. Jamb Guards: Welded assembly of 1/4 inch stainless steel; 18 inches high by 5 inches
deep. Provide with floor and wall anchors. Secure bottom pin assembly to top of jamb
guard.
7. Color: Black.
8. Provide manufacturer's standard brackets on doors for application of padlocks.
9. Full perimeter gasket seal, adjustable at bottom.
A. General:
1. Door curtains consisting of overlapping strips to form a sealed door curtain. Provide
strips of length required to suit opening height and with sufficient number in unit to close
opening width with 4 to 6 inches overlap on each jamb.
2. Basis-of-Design Product: American Floor Products Company, Inc., Vista-Curtain
Flexible, Transparent Strip Doors (VC-5050), Style PF-808.
B. Strip Material: Curved, clear, transparent, extruded PVC. Fabricate strips for manufacturer's
standard method of attachment to overhead mounting system indicated.
1. Strip width and thickness: Minimum 8 inches wide and 0.08 inch thick.
2. Strip overlap: Overlap strips 2/3 width of strips.
PART 3 - EXECUTION
3.1 INSPECTION
A. Verify openings are prepared with headers level, jambs plumb, floor level, without projections,
and are correctly dimensioned to receive traffic doors. Begin installation of doors only when
conditions are satisfactory.
3.2 INSTALLATION
A. General:
1. Install doors, complete with accessories and hardware, in strict accordance with shop
drawings and manufacturer's installation instructions.
1. Mount strip doors so operation of doors or other apparatus in same opening are not
obstructed.
a. Wall Surface Mounting: Consisting of a steel plate bolted to side of interior face of
wall above door opening; equip plate with permanently attached, threaded,
mounting pins and steel-angle or -plate retaining strip attached to plate with wing
nuts.
b. Wall Surface Mounting: Consisting of a rigid, vinyl wall-mounting unit bolted to
interior face of wall above opening; equip unit with a similarly formed, rigid, vinyl
retainer attached to unit with wing nuts.
c. At Contractors option, mount strip doors using either of the above systems.
A. General:
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 08 Sections Sliding Automatic Entrances and Glazing.
2. This Section specifies standard exterior and interior aluminum-framed entrance and storefront
systems.
A. Entrance systems include manual-swing aluminum doors, door frames, vestibule enclosures,
transoms, and sidelights.
3. Glazing within exterior aluminum framed systems shall be laminated type and secured using structural
sealant to comply with current force protection requirements.
4. Exterior aluminum framed systems shall be designed for security protection in accordance with UFC
4-010-01 DoD Minimum Antiterrorism Standards For Buildings, (latest issue), Standard 10. The
specific requirements in the following subparagraphs comply with Standard 10 in accordance with
Standard 1, Table B-1, Standoff Distances for New and Existing Buildings, i.e., Parking and
Roadways Located within a Controlled Perimeter, Building Category is a Primary Gathering Building,
Applicable Level of Protection is Low, Standoff Distance For Conventional Construction is 25 m, and
Applicable Explosive Weight is II. Where project conditions, including existing buildings, are different
from the preceding, additional and alternative requirements indicated in UFC 4-010-01 shall be
followed.
A. Frames, connections to their surroundings, and supporting structural elements shall be designed
in accordance with ASTM F 2248 based on the explosive weight and standoff distance indicated
above.
1. Dynamic analysis may be used as an alternative to the design approach described above.
2. Dynamic testing may be done as an alternative to the provisions of Standard 10.
B. Except where more stringent requirements are dictated by project conditions, restrict deflections
of edges of the blast resistant glazing the frames support to 1/160 of the length of the supported
edge at allowable stress levels determined in accordance with ASTM F 2248.
1. The supported edge length of a punched window shall be equal to the span of the glass,
regardless of any intermediate support connections. For multi-panel glazing systems, the
supported edge length shall be equal to the span of a single glass panel and the deflection
shall be calculated based on simple support conditions for that length.
C. Structural glazing is the installation of glass with structural silicone sealant applied between the
glass and glass stops creating a bond between the two materials to resist expulsion of the glass
under pressure from the exterior. Generally, standard window and door glass stops can
accommodate a 3/8" bite and not a 1" bite. Select window and glazed door systems that will
accommodate bite requirement.
1. Glazing shall have a minimum frame bite of 3/8" for structurally glazed systems.
2. Glazing shall have a minimum frame bite of 1" for systems that are not structurally glazed.
D. Coordinate glass unit thickness with width of frame rabbet holding glass.
June 2011 08 41 13 1
DeCA DESIGN CRITERIA HANDBOOK
08 41 13 ALUMINUM-FRAMED ENTRANCES
AND STOREFRONTS
5. Exterior swinging doors shall be designed for security protection in accordance with UFC 4-010-01
DoD Minimum Antiterrorism Standards For Buildings, (latest issue), Standard 12, as follows:
A. Ensure that all exterior doors into inhabited areas open outwards. By doing so, the doors will seat
into the door frames in response to an explosive blast, increasing the likelihood that the doors will
not enter the buildings as hazardous debris. Alternatively, position doors such that they will not
be propelled into rooms if they fail in response to a blast or provide other means to ensure they
do not become hazards to building occupants.
6. If project requires no exterior framing systems, edit Specification Section deleting requirements for
security protection.
7. If hurricane resistant aluminum framed systems are required for Project, add performance
requirements to Specification Section.
END OF SECTION
June 2011 08 41 13 2
SECTION 08 41 13
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for adhesives and sealants used inside
of the weatherproofing system.
A. General:
a. Blast loads.
b. Structural loads.
c. Deflection of framing members:
d. Thermal movements.
e. Movements of supporting structure indicated on Drawings including, but not limited
to, deflection from uniformly distributed and concentrated live loads.
f. Dimensional tolerances of building frame and other adjacent construction.
g. Failure includes the following:
B. Blast Loads:
a. Once the contract is awarded, the successful contractor will be eligible to receive
UFC 4-010-02 for use in the development of the final exterior aluminum-framed
design package under conditions dictated by the Government.
b. Alternatives to the design approach above: Any or all aluminum-framed systems,
including connections and supporting structural elements:
C. Structural Loads:
1. Wind Loads:
2. Seismic Loads:
3. Security Protection:
1. Deflection Normal to Wall Plane at Design Wind Pressure: Limited to 1/175 of clear span
for spans up to 13 feet 6 inches and to 1/240 of clear span plus 1/4 inch for spans greater
than 13 feet 6 inches or an amount that restricts edge deflection of individual glazing lites
to 3/4 inch, whichever is less.
2. Deflection Parallel to Glazing Plane: Limited to amount not exceeding that which reduces
glazing bite to less than 75 percent of design dimension and that which reduces edge
clearance between framing members and glazing or other fixed components directly
below them to less than 1/8 inch and clearance between members and operable units
directly below them to less than 1/16 inch.
3. Deflection Normal to Wall Plane at Design Blast Pressure: Except where more stringent
requirements are dictated by project conditions, restrict deflections of edges of blast
resistant glazing the frames support to 1/160 of the length of the supported edge at
allowable stress levels determined in accordance with ASTM F 2248.
a. The supported edge length of punched windows shall be equal to the span of the
glass, regardless of any intermediate support connections. For multi-panel glazing
systems, the supported edge length shall be equal to the span of a single glass
panel and the deflection shall be calculated based on simple support conditions for
that length.
E. Structural-Test Performance:
1. Preconstruction Testing Service: Provide aluminum framed systems that comply with
test-performance requirements indicated, as evidenced by reports based on Project-
specific preconstruction testing or of tests performed on manufacturer's standard
assemblies by a qualified testing agency.
2. Provide exterior aluminum-framed systems tested according to ASTM E 330 as follows:
a. When tested at positive and negative wind-load design pressures, systems do not
evidence deflection exceeding specified limits.
b. When tested at 150 percent of positive and negative wind-load design pressures,
systems, including anchorage, do not evidence material failures, structural
distress, and permanent deformation of main framing members exceeding 0.2
percent of span.
3. Test Durations: As required by design wind velocity but not less than 10 seconds.
F. Thermal Movements:
1. Provide aluminum-framed systems that allow for thermal movements resulting from the
following maximum change (range) in ambient and surface temperatures. Base
engineering calculation on surface temperatures of materials due to both solar heat gain
and nighttime-sky heat loss.
G. Air Infiltration:
1. Provide aluminum-framed systems with maximum air leakage through fixed glazing and
framing areas of 0.06 cfm/sq. ft. of fixed wall area when tested according to ASTM E 283
at a minimum static-air-pressure difference of 6.24 lbf/sq. ft.
1. Provide aluminum-framed systems that do not evidence water penetration through fixed
glazing and framing areas when tested according to ASTM E 331 at a minimum static-air-
pressure difference of 20 percent of positive wind-load design pressure, but not less than
6.24 lbf/sq. ft.
1.3 SUBMITTALS
A. Product Data:
B. LEED Submittals:
1. Product Data for Credit EQ 4.1: For adhesives and sealants used inside of the
weatherproofing system, including printed statement of VOC content.
C. Shop Drawings:
a. Show minimum frame bite for glazing exterior window and door systems.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
F. Submittal List:
Reference Submittal Item Quantity Action
A. Installer Qualifications:
C. Product Options:
a. Do not modify door stile width. Do not modify other intended aesthetic effects, as
judged solely by Contracting Officer, except with Contracting Officer's approval. If
modifications are proposed, submit comprehensive explanatory data to
Contracting Officer for review.
1. Comply with applicable provisions in the U.S. Architectural & Transportation Barriers
Compliance Board's ABA Accessibility Guidelines and ICC/ANSI A117.1.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design:
a. Basis-of-Design Products:
2.2 MATERIALS
A. Aluminum:
1. Alloy and temper recommended by manufacturer for type of use and finish indicated.
2. Sheet and Plate: ASTM B 209/ASTM B 209M.
3. Extruded Bars, Rods, Profiles, and Tubes: ASTM B 221/ASTM B 221M.
4. Extruded Structural Pipe and Tubes: ASTM B 429.
5. Structural Profiles: ASTM B 308/B 308M.
6. Welding Rods and Bare Electrodes: AWS A5.10/A5.10M.
B. Steel Reinforcement:
A. General:
A. Framing Members:
E. Flashing:
A. Glazing:
B. Glazing Gaskets:
2.6 DOORS
A. General:
B. Door Hardware:
A. Joint Sealants:
B. Bituminous Paint:
A. General:
1. Include accommodations for using temporary support device (dutchman) to retain glazing
in place while structural sealant cures.
D. Door Frames:
1. Reinforce as required to support loads imposed by door operation and for installing
hardware.
2. At exterior doors, provide compression weather stripping at fixed stops.
3. At interior doors, provide silencers at stops to prevent metal-to-metal contact. Install
three silencers on strike jamb of single-door frames and two silencers on head of frames
for pairs of doors.
E. Doors:
F. After Fabrication:
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas, with Installer present, for compliance with requirements for installation
tolerances and other conditions affecting performance of work. Proceed with installation only
after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. General:
4. Metal Protection:
a. Where aluminum will contact dissimilar metals, protect against galvanic action by
painting contact surfaces with primer or by applying sealant or tape or installing
nonconductive spacers as recommended by manufacturer for this purpose.
b. Where aluminum will contact concrete or masonry, protect against corrosion by
painting contact surfaces with bituminous paint.
5. Install components to drain water passing joints, condensation occurring within framing
members, and moisture migrating within the system to exterior.
6. Set continuous sill members and flashing in full sealant bed as specified in Division 07
Section Joint Sealants and to produce weathertight installation.
7. Install components plumb and true in alignment with established lines and grades,
without warp or rack.
8. Install glazing as specified in Division 08 Section Glazing.
D. Erection Tolerances:
a. Location and Plane: Limit variation from true location and plane to 1/8 inch in 12
feet; 1/4 inch over total length.
b. Alignment:
1) Where surfaces abut in line, limit offset from true alignment to 1/16 inch.
2) Where surfaces meet at corners, limit offset from true alignment to 1/32
inch.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 08 Design Criteria, Commissary Door Schedule in Appendix A,
and related Design Standard Plates.
2. Sliding automatic entrance doors are typically provided at all customer entrances and exits. Depending
on egress requirements, either full-breakout or fixed sidelight door packages shall be provided. Perform
an exiting analysis to determine which type is required.
3. Provide sliding automatic door packages with transom panels, unless conditions prevent the use of
transom panels. Standard door package size, with transom, is 10' 0" wide by 10' 0" high.
4. In new facilities with polished concrete floors, equip doors with recessed roller track guide system at
sidelights that are set flush with concrete floor surface. No threshold is required across actual door
opening.
5. On addition / alteration projects and new facilities with applied floor finishes (i.e., VCT, terrazzo, etc.) a
threshold is required at exterior door openings to prevent wind driven rainwater from seeping into the
vestibules causing floor finish adhesive failures. The manufacturers standard single bevel surface
mounted roller track guide system shall be provided at sidelights with single bevel surface mounted
threshold across door opening
6. Exterior sliding automatic door package glazing shall be laminated type and secured using structural
sealant to comply with current force protection requirements.
7. Exterior sliding automatic door systems, including sidelight frames and transoms, shall be designed for
security protection in accordance with UFC 4-010-01 DoD Minimum Antiterrorism Standards For
Buildings, (latest issue), Appendix B, Standard 12.
DeCA standard is to design commissary facilities so that exterior sliding automatic entrance door
systems (operable doors, sidelights, and transoms) are positioned in accordance with the "Alternative
Designs" method identified in Appendix "B", Standard 12 of UFC 4-010-01; and are not required to be
secured for blast resistance. This alternative design method requires that sliding automatic entrance
door systems be positioned such that they will not be propelled into rooms if they fail in response to a
blast, or provide other means to ensure they do not become hazards to building occupants. Sliding
automatic entrance door systems glazing must comply with glass type and minimum frame bite
provisions of Appendix "B", Standard 10.
DeCA Guide Specifications are based on design compliance with this alternative design method.
Should sitting of a particular commissary facility not permit compliance with this alternative design
method, it will be necessary to design the sliding automatic entrance door systems in compliance with
the base requirements of Appendix "B", Standard 12 of UFC 4-010-01. Doing so will require the use of
blast rated single slide automatic entrance doors with reduced egress width and fixed sidelights. Modify
DeCA Guide Specifications accordingly. Supplementary exit doors will be necessary to comply with
building egress requirements.
8. Drawings shall graphically indicate the direction of travel at sliding automatic doors. Customer
entrance and carry-out return doors shall have motion detectors that will activate doors allowing one-
way only traffic flow into the commissary, when doors are in the closed position. Customer exit doors
shall have motion detectors that will activate doors allowing one-way only traffic flow out of the
commissary, when doors are in the closed position. Deviations from the above requirements shall be
discussed during project design and documented in the Project Design Analysis. An exception to the
above requirements would be at facilities sharing a common entrance from an adjacent exchange
mall or possibly at a commissary with only one customer entrance, where two-way traffic flow is
desired.
9. Provide door signage on both sides of each sliding automatic door package, identifying intended use of
door (i.e., entrance, exit, emergency exit, carry-out return) based on which direction a person is
approaching the door. Locate signage on center horizontal muntin.
10. Provide stainless steel protection plates on traffic side of exit doors/sidelight panels and carry-out return
doors/sidelight panels to protect against impact damage from shopping carts. Do not provide stainless
steel protection plates at entrance doors, unless shopping carts are stored on exterior of commissary.
In addition to stainless steel protection plates, provide protection posts to guard leading edge of all
sliding automatic doors (Note that regardless of direction of travel through door opening, protection
posts can only be installed on interior side of doors).
11. Provide 10" high door bottoms on automatic sliding doors and sidelights, to match that required by ANSI
A117.1 on manual swing doors and storefront systems.
12. Indicate maintenance proximity from Installer's place of business to Project site to suit Project
location.
13. If project requires no exterior sliding automatic door systems, edit specification section deleting
requirements for security protection.
14. If hurricane resistant sliding automatic door systems are required for Project, add performance
requirements to specification section.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 DEFINITIONS
A. Activation Device:
1. Device that, when actuated, sends an electrical signal to the door operator to open the
door.
B. Safety Device:
A. General:
1. Provide automatic entrance door assemblies capable of withstanding structural loads and
thermal movements based on testing manufacturer's standard units in assemblies similar
to those indicated for this Project.
1. Wind Loads:
2. Seismic Loads:
C. Thermal Movements:
1. Provide automatic entrance doors that allow for thermal movements resulting from the
following maximum change (range) in ambient and surface temperatures by preventing
buckling, opening of joints, overstressing of components, failure of joint sealants, failure
of connections, and other detrimental effects. Base engineering calculation on surface
temperatures of materials due to both solar heat gain and nighttime-sky heat loss.
a. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces.
1. Provide automatic entrance door operators capable of operating between minus 20 deg F
and plus 130 deg F.
E. Air Infiltration:
1. Maximum air leakage through fixed glazing and framing areas of 1.25 cfm/sq. ft. of fixed
entrance system area when tested according to ASTM E 283 at a minimum static-air-
pressure difference of 1.57 lbf/sq. ft.
1. Egress Doors: Not more than 50 lbf required to manually set door in motion if power
fails, and not more than 15 lbf required to open door to minimum required width.
2. Accessible Interior Doors: Not more than 5 lbf.
3. Breakaway Device for Power-Operated Doors: Not more than 50 lbf required for a
breakaway door or panel to open.
1.4 SUBMITTALS
A. Product Data:
B. Shop Drawings:
1. Include plans, elevations, sections, details, hardware mounting heights, and attachments
to other Work.
2. For systems indicated to comply with performance requirements and design criteria,
include structural analysis data signed and sealed by the qualified professional engineer
responsible for their preparation.
a. Show minimum frame bite for glazing exterior door, sidelight, and transom
systems.
3. Wiring Diagrams: Detail wiring for power, signal, and control systems and differentiate
between manufacturer-installed and field-installed wiring.
E. Maintenance Data:
F. Submittal List:
A. Installer Qualifications:
C. Manufacturer Qualifications:
1. A firm experienced in manufacturing systems similar to those indicated for this Project
and with a record of successful in-service performance. A manufacturer with company
certificate issued by AAADM
E. Source Limitations:
1. Obtain automatic entrance doors through one source from a single manufacturer.
F. Product Options:
a. Do not modify door stile width. Do not modify other intended aesthetic effects, as
judged solely by Contracting Officer, except with Contracting Officers approval. If
modifications are proposed, submit comprehensive explanatory data to
Contracting Officer for review.
G. Welding Standards:
I. UL Standard:
1. Comply with requirements of authorities having jurisdiction for automatic entrance doors
serving as a required means of egress.
2. Emergency Break Away: Provide in accordance with ANSI A156.10 and NFPA 101.
A. Field Measurements:
1. Verify automatic entrance door openings by field measurements before fabrication and
indicate measurements on Shop Drawings. Coordinate fabrication schedule with
construction progress to avoid delaying the Work.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
2.2 MATERIALS
A. Aluminum:
1. Alloy and temper recommended by manufacturer for type of use and finish indicated,
complying with standards indicated below:
1. Refer to Division 07 Section Joint Sealants for joints at perimeter of entrance framing
system.
E. Bituminous Paint:
A. General:
1. Provide manufacturer's standard automatic entrance door system, complete with doors,
sidelite and transom framing, operators, controls, activation devices, safety devices, and
accessories as indicated. Comply with the following:
B. Activation Device:
1. Motion detectors mounted on each side of door header to detect pedestrians in activating
zone and to open door.
C. Safety Devices:
1. Presence detector mounted to underside of door header and two photoelectric beams
mounted in sidelite jambs to detect pedestrians in presence zone and to prevent door
from closing.
2.4 COMPONENTS
A. General:
1. Exterior Assemblies: At the Contractors option, exterior sliding automatic entrance door
system glazing may be retained by structural sealant, or mechanically with gaskets, or a
combination of both in compliance with performance requirements.
B. Doors:
1. Provide manufacturer's standard 1-3/4-inch- thick glazed doors with minimum 0.125-inch-
thick, extruded tubular stile and rail members. Fabricate corners with mechanically
fastened reinforcing brackets or by welding. Incorporate concealed tie-rods that span full
length of top and bottom rails.
2. Glazing Stops and Gaskets:
C. Framing Members:
D. Headers:
F. Sills:
1. Manufacturer's standard sill members and bottom guide system, with stainless-steel ball-
bearing-center roller wheels, and threshold and configuration indicated below:
I. Signage:
A. General:
1) Adjustable speed, including opening, closing, back check, and latch check.
2) Door speed (not the checking speed): Minimum two feet per second
opening, one foot per second closing; adjustable speed control for opening
and closing cycles.
3) Adjustable time delay for length of time door remains open.
d. Microprocessor Control: System that automatically defines and sets opening and
closing parameters.
e. On/Off Feature: Provide on/off/hold-open switch to control electric power to
operator.
B. Electromechanical Operators:
1. Self-contained overhead units, with power opening and closing mechanism indicated
below and with checking in both opening and closing cycles. Provide safety-release
clutch for obstructed closing. Provide for manual sliding when power is off. Provide
operator action as indicated.
A. Control Systems:
E. Electrical Interlocks:
1. Unless units are equipped with self-protecting devices or circuits, provide electrical
interlocks to prevent activation of operator when door is locked, latched, or bolted.
2.7 HARDWARE
A. General:
1. Refer to Division 08 Section Door Hardware for requirements for hardware items other
than those indicated to be provided by automatic entrance door manufacturer.
B. Heavy-Duty Hardware:
1. Provide units as indicated in size, number, and type recommended by manufacturer for
entrances required. Finish exposed parts to match door finish, unless otherwise
indicated.
1. Provide release hardware that allows panel to swing out in the direction of egress to a full
90 degrees from any position in the sliding mode. Maximum force to open panel shall be
50 lbf according to ANSI/BHMA A156.10. Interrupt operation of panel operator while in
the breakaway mode.
1. Provide security hooking devices at top and bottom of meeting stiles of sliding doors and
sidelights. Hooks shall automatically secure sliding doors and sidelights together when
sliding doors reach fully closed position and shall prevent break out when sliding door is
locked.
2. Provide 2-point night locks at meeting stiles of sliding doors. 2-point locks shall consist of
a hook bolt at meeting stiles of bi-parting leafs and a head bolt simultaneously thrown or
retracted by cylinder operation.
3. Cylinders: On door exterior and interior, as specified in Division 08 Section Door
Hardware.
2.8 FABRICATION
A. General:
B. Prefabrication:
C. Welding:
1. Weld components to comply with referenced AWS standard. Weld before finishing
components to greatest extent possible. Weld in concealed locations to greatest extent
possible to minimize distortion or discoloration of finish. Remove weld spatter and
welding oxides from exposed surfaces by descaling or grinding.
D. Glazing Channels:
1. Provide minimum clearances for thickness and type of glass indicated according to
GANA's "Glazing Manual."
E. Metal Protection:
1. Where aluminum will contact dissimilar metals, protect against galvanic action by painting
contact surfaces with primer or by applying sealant or tape recommended by
manufacturer for this purpose.
F. Hardware:
a. Hardware Preparation:
G. Doors:
1. Fabricate doors in profiles indicated. Reinforce as required to support imposed loads and
for installing hardware. Factory assemble door and frame units.
2. Exterior Doors: Provide compression weather stripping at fixed stops. At locations
without fixed stops, provide sliding weather stripping retained in adjustable strip mortised
into door edge.
H. Framing:
1. Fabricate tubular and channel frame assemblies in configuration indicated, with welded
or mechanical joints according to manufacturer's standards. Provide subframes and
reinforcement of types indicated or, if not indicated, as needed for a complete system to
support required loads.
2. Exterior Framing: Fabricate components to drain water passing joints and condensation
and moisture occurring or migrating within the system to the exterior. Provide anchorage
and alignment brackets for concealed support of assembly from the building structure.
Allow for thermal expansion of exterior units.
A. Performance:
1. The access security system shall detect sliding condition and panic breakout condition of
automatic sliding entrance doors when doors are locked and security system is activated.
B. Wiring:
1. System shall be factory wired within the automatic sliding entrance door components; all
equipment shall be concealed within door operator housing.
C. Operation:
1. System shall electrically transmit a signal to a remote alarm when sliding condition and
panic condition occur. Wiring from automatic sliding entrance doors and the alarm
system are specified in Division 26. Provide disconnect switch and wire terminal
connection points on terminal block for interface connections to remote alarm.
A. Finish aluminum automatic entrance door system components to match finish of aluminum
framed systems.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Existing Conditions:
1. Examine conditions, with Installer present, for compliance with requirements for
installation tolerances, header support, and other conditions affecting performance of
automatic entrance doors. Proceed with installation only after unsatisfactory conditions
have been corrected.
3.2 PREPARATION
A. Templates and Diagrams: Furnish templates, diagrams, and other data to fabricators and
installers of related work, as necessary for coordinating automatic entrance door installation.
3.3 INSTALLATION
A. General:
B. Metal Protection:
1. Where aluminum will contact dissimilar metals, protect against galvanic action by painting
contact surfaces with primer or by applying sealant or tape recommended by
manufacturer for this purpose. Where aluminum will contact concrete or masonry,
protect against corrosion by painting contact surfaces with bituminous paint.
C. Entrances:
1. Install entrances plumb and true in alignment with established lines and grades without
warp or rack of framing members and doors. Anchor securely in place. Lubricate
operating hardware and other moving parts.
2. Install surface-mounted hardware using concealed fasteners to greatest extent possible.
3. Set tracks, header assemblies, operating brackets, and guides level and true to location
with anchorage for permanent support.
D. Door Operators:
1. Install control devices and wiring, including connections to door operators, as follows:
F. Glazing:
G. Sealants:
1. Comply with requirements in Division 07 Section Joint Sealants for installing perimeter
sealants, fillers, and gaskets.
2. Seal threshold perimeter between metal and concrete with sealant.
3. Seal frame perimeter with sealant to provide weathertight construction, unless otherwise
indicated.
3.4 ADJUSTING
A. Components:
1. Adjust door operators, controls, and hardware for smooth and safe operation and for
weathertight closure.
B. Operation:
1. Readjust door operators and controls after repeated operation of completed installation
equivalent to three days' use by normal traffic (100 to 300 cycles). Lubricate hardware,
operating equipment, and other moving parts.
A. Cleaning:
1. Clean glass and aluminum surfaces promptly after installation. Remove excess glazing
and sealant compounds, dirt, and other substances. Repair damaged finish to match
original finish.
2. Comply with requirements in Division 08 Section Glazing for cleaning and maintaining
glass.
B. Protection:
1. Provide final protection and maintain conditions, including limiting construction traffic, that
ensure automatic entrance doors are without damage or deterioration at time of final
acceptance.
3.6 DEMONSTRATION
A. Training:
END OF SECTION
UNIT SKYLIGHTS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Test Performance Criteria: Provide unit skylights capable of complying with performance
requirements indicated, based on testing manufacturer's unit skylights that are representative of
those specified.
1. Structural Performance: Provide unit skylights, including glazing and anchorage, capable
of withstanding the effects of the following design loads:
2. Wind Loads: Refer to Division 01 Section Summary of Work for design wind velocity and
building exposure factor.
3. Air Infiltration: ASTM E283 shall be less than 0.01 CFM/ Cu. Ft. at 6.25-psf negative
pressure.
4. Water Penetration: ASTM E331 shall pass at a negative pressure of 15-psf.
1.3 SUBMITTALS
A. Product Data:
1. For each type of unit skylight indicated. Include construction details, material
descriptions, dimensions of individual components and profiles, and finishes for unit
skylights.
B. Shop Drawings:
1. For unit skylight work. Include plans, elevations, sections, details, and connections to
supporting structure and other adjoining work.
1. Based on evaluation of comprehensive tests performed within the last four years by a
qualified testing agency for each type, performance class, performance grade, and size
of unit skylight. Test results based on use of downsized test units will not be accepted.
D. Submittal List:
A. Manufacturer Qualifications:
B. Installer Qualifications:
1. An installer acceptable to unit skylight manufacturer for installation of units required for
this Project.
C. Source Limitations:
1. Provide plastic glazing sheets identical to those tested for fire-exposure behavior per test
method indicated below by a testing and inspecting agency acceptable to authorities
having jurisdiction. Identify materials with appropriate markings of applicable testing and
inspecting agency.
1.5 COORDINATION
A. General:
1.6 WARRANTY
A. Special Warranty:
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design Products:
2.2 MATERIALS
A. Aluminum Components:
1. Sheets: ASTM B 209, alloy and temper to suit forming operations and finish
requirements but with not less than the strength and durability of alclad Alloy 3005-H25.
2. Extruded Shapes: ASTM B 221, alloy and temper to suit structural and finish
requirements but with not less than the strength and durability of Alloy 6063-T52.
B. Fasteners:
1. Same metal as metal being fastened, nonmagnetic stainless steel, or other noncorrosive
metal as recommended by manufacturer. Finish exposed fasteners to match material
being fastened.
2.3 GLAZING
A. Polycarbonate Glazing:
A. General:
1. Factory assembled self-flashing units consisting of impact modified plastic domes, 0.062
inch extruded aluminum curb frame, 0.062 inch extruded aluminum retaining angle,
double wall insulated curb. Skylight frame shall have an integral condensate gutter with
weep slots. Weep slots shall be protected from weather and air-borne debris. Insulated
curbs shall be constructed with an aluminum inner and outer wall isolated at the top and
bottom by PVC thermal barriers. Insulation material between walls is to be
polyisocyanurate. No breakage or disengagement of dome from frame shall occur upon
impact of up to 1000 ft. lbs.
2. Type: Model FPNTLA thermalized sealed pyramid double dome.
3. Integral Curb: Extruded-aluminum, self-flashing type.
1) Height: 12 inches.
2) Construction: Double wall.
3) Insulation: Manufacturer's standard rigid or semirigid type.
A. Mill Finish:
1. Manufacturer's standard.
PART 3 - EXECUTION
3.1 EXAMINATION
A. General:
A. General:
1. Coordinate installation of unit skylight with installation of substrates, vapor retarders, roof
insulation, roofing membrane, and flashing as required to ensure that each element of the
Work performs properly and that combined elements are waterproof and weathertight.
2. Comply with recommendations in AAMA 1607 and with manufacturer's written
instructions for installing unit skylights.
3. Install unit skylights level, plumb, and true to line, without distortion.
4. Anchor unit skylights securely to supporting substrates.
5. Where metal surfaces of unit skylights will contact incompatible metal or corrosive
substrates, including preservative-treated wood, apply bituminous coating on concealed
metal surfaces, or provide other permanent separation recommended in writing by unit
skylight manufacturer.
6. Set unit skylight flanges in thick bed of roofing cement to form a seal unless otherwise
indicated.
7. Where cap flashing is indicated, install to produce waterproof overlap with roofing or roof
flashing. Seal with thick bead of mastic sealant except where overlap is indicated to be
left open for ventilation.
3.3 CLEANING
A. General:
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 08 Sections Hollow Metal Doors and Frames and Aluminum-Framed
Entrances and Storefronts for door and frame preparation, and reinforcement provided as part of
doors and frames. See Division 08 Section Flush Wood Doors for factory pre-fitting and machining of
wood doors for door hardware. See Division 08 Section Key Storage Equipment for key
management system.
2. This Section specifies hardware, also known as finish hardware, builders' hardware, or architectural
finish hardware, applied to doors. The Section uses manufacturers' product names and references to
Builders Hardware Manufacturers Association standards in Part 3 "Door Hardware Schedule" Article
to indicate door hardware requirements. Also included are hardware items essential to the operation,
control, and weather stripping of doors, and electrified door hardware.
3. Guide specification Division 08 Section Door Hardware includes typical hardware sets required in
Commissary facilities. Select hardware sets from descriptive names of rooms indicated in
specification. If necessary, adjust to suit project requirements. General guidelines for door locking is
as follows:
A. Automatic entrance doors are specified with all required operational door hardware, except
cylinder locks. Indicate cylinder locks that are key operated from exterior side and thumb turn
operated from interior side.
B. Exterior aluminum framed glass door at Administrative Office entrance requires a two-point
deadlatch, cylinder lock (key operated from exterior side and paddle from interior side), closer,
and pull hardware.
C. Exterior employee entrance / exit doors in warehouse area require exit device, door closer, and
local day alarm. Day alarm shall be the type where de-activation will be accomplished only by
key access. Day alarm must be hard wired, with battery back-up. Any time receiving is not
taking place these doors must be under surveillance by a DeCA employee or monitored by a
local alarm to afford protection against unauthorized entry or exit. The local day alarm will
typically be activated so that security can be controlled during the time when the store is closed
to customers, but still occupied by cleaning, maintenance, and stocking personnel. The purpose
of the local alarm is to serve as a deterrent and immediately notify management if unauthorized
use of a particular door occurs. It does not replace the intrusion detection (IDS) that is monitored
by Installation police, and typically activated when the building is unoccupied. IDS does not
annunciate in the store.
D. Exterior emergency exit only doors require delayed egress lock with local day alarm. It is
intended that these doors will only be used in an emergency. Day alarm shall be the type where
de-activation will be accomplished only by key access or fire alarm signal. Day alarm must be
hard wired, with battery back-up, and will typically be activated 24 hours per day. The purpose of
the local alarm is to serve as a deterrent and immediately notify management if unauthorized use
of a particular door occurs. It does not replace the intrusion detection (IDS) that is monitored by
Installation police, and typically activated when the building is unoccupied. IDS does not
annunciate in the store.
E. Exterior overhead receiving doors require a padlock at both jambs of door opening.
F. Interior aluminum framed glass door at Administrative Office entrance requires a closer and
push/pull hardware. No lockset is required on this door.
June 2011 08 71 00 1
DeCA DESIGN CRITERIA HANDBOOK
08 71 00 DOOR HARDWARE
H. Cashiers Office and Cash Counting Room doors require mortise locks (storeroom function with a
3/4" throw). The Cash Counting Room door also requires an electric door strike with operator
located in Cashiers Office.
I. Communications Room and Communications Closet require mortise locks (storeroom function
with a 3/4" throw).
J. Administrative Office Corridor doors, Employee Break Room, Toilet Rooms, Locker Rooms, and
Training Rooms require push/pull hardware and door closers. Some locations require deadbolt
locks to secure these rooms during non-business hours, to prohibit access to room by
employees, stockers, and vendors after rooms have been cleaned. Verify requirement for
deadbolt locks with the DeCA Project Manager.
K. Janitors Closets, mechanical rooms, and Storage Room doors require storeroom function
locksets. Provide closers on doors opening to customer areas.
4. Assure that door hardware selected complies with ABA Accessibility Standard for Department of
Defense Facilities as adopted by the Deputy Secretary of Defense memorandum dated October 31,
2008.
5. Guide specification indicates lever handles on all doors in accordance with accessibility
requirements. Cast construction. Commercial plain design. Lever handles for exit devices shall meet
test requirements of ANSI/BHMA A156.13 for mortise locks. Lever handle locks shall have
breakaway feature (such as weakened spindle or shear key) to prevent irreparable damage to lock
when force in excess of that specified in ANSI/BHMA A156.13 is applied to the lever handle. Lever
handles shall return to within 1/8" of door face.
6. Indicate all high use interior personnel doors with kick plates on push side of door.
A. Exterior Doors.
B. Administration offices.
C. Cashier's Office - dead bolt lockset required.
8. Indicate Type 1 Operational Grade 1 locksets at all storage and utility rooms.
9. Indicate door closers complying with ANSI/BHMA A156.4, Series C02000, Grade 1. Use closers
Type C02011 with optional feature PT 4C (adjustable closing force at least 50% over minimum value
for closer) for surface applications, except use parallel arm closers, C02021, on out-swinging exterior
doors.
10. Indicate heavy-duty wall mounted or floor mounted door stops. Provide as necessary to preclude
damage to door, hardware, and adjacent walls.
11. Locate building key box (KNOX-BOX) on exterior building wall adjacent to main customer entrance
for use by Fire Department in an emergency. Verify with Fire Department that building key box
specified is compatible with that used at Installation. Modify accordingly.
A. In accordance with UFC 4-010-01, Standard 21, indicate methods of controlling access to crawl
spaces, utility tunnels, and other means of under building access.
June 2011 08 71 00 2
DeCA DESIGN CRITERIA HANDBOOK
08 71 00 DOOR HARDWARE
B. Verify with Installation safety authorities if under building access is to conform to OSHA
requirements for confined spaces.
END OF SECTION
June 2011 08 71 00 3
SECTION 08 71 00
DOOR HARDWARE
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
a. Swinging doors.
b. Sliding doors.
c. Other doors to the extent indicated.
B. Related Sections:
1.2 SUBMITTALS
A. Product Data:
1. Manufacturer's technical product data for each item of door hardware, installation
instructions, maintenance of operating parts and finish, and other information necessary
to show compliance with requirements.
1. Certify that locksets approved for use complies with "Buy American Act."
C. Hardware Schedule:
3. Submittal Sequence: Submit final schedule at earliest possible date particularly where
acceptance of hardware schedule must precede fabrication of other work that is critical in
the Project construction schedule. Include with schedule the product data, samples,
shop drawings of other work affected by door hardware, and other information essential
to the coordinated review of schedule.
D. Keying Schedule:
E. AHC Report:
1. Upon completion of the installation, and as a condition of its acceptance, deliver a report
signed by the AHC stating that his inspection was made, that all adjustments
recommended by him have been completed, that all finish hardware furnished under this
Section has been installed and is in optimum working condition, and that finish hardware
conforms to commissioning requirements.
Retain door hardware items below specified for project that are
required to meet accessibility requirements.
G. Submittal List:
1. Obtain each type of hardware (latch and lock sets, hinges, closers, etc.) from a single
manufacturer.
C. Installer Qualifications:
A. Furnish a complete set of specialized tools and maintenance instructions as needed for
Governments continued adjustment, maintenance and removal and replacement of door
hardware.
1.5 COORDINATION
A. Templates:
1. Distribute door hardware templates for doors, frames, and other work specified to be
factory prepared for installing door hardware. Check Shop Drawings of other work to
confirm that adequate provisions are made for locating and installing door hardware to
comply with indicated requirements.
1. Coordinate layout and installation of electrified door hardware with connections to power
supplies, fire alarm system and detection devices, access control system, security
system, and building control system, as applicable to project.
2. Conduct conference at Project site to comply with requirements in Division 01 Section
Administrative Requirements. Review methods and procedures related to electrified door
hardware including, but not limited to, the following:
a. Inspect and discuss electrical roughing-in and other preparatory work performed
by other trades.
b. Review sequence of operation for each type of electrified door hardware.
c. Review and finalize construction schedule and verify availability of materials,
Installer's personnel, equipment, and facilities needed to make progress and avoid
delays.
d. Review required testing, inspecting, and certifying procedures.
A. Accessibility Requirements:
1. Comply with applicable provisions in the U.S. Architectural & Transportation Barriers
Compliance Board's "Architectural Barriers Act (ABA) Accessibility Guidelines for
Buildings and Facilities" and ICC/ANSI A117.1 as follows:
a. Provide operating devices that do not require tight grasping, pinching, or twisting of
the wrist and that operate with a force of not more than 5 lbf.
b. Comply with the following maximum opening-force requirements:
A. General:
1. Inventory door hardware on receipt and provide secure lock-up for door hardware
delivered to Project site.
2. Tag each item or package separately with identification related to the final door hardware
sets, and include basic installation instructions, templates, and necessary fasteners with
each item or package.
3. Deliver keys and replacement cores to manufacturer of key control system for
subsequent delivery to Contracting Officer.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Do not use manufacturers' products that have manufacturer's name or trade name
displayed in a visible location (omit removable nameplates) except in conjunction with
required fire-rated labels and as otherwise acceptable to Contracting Officer.
2. Manufacturer's identification will be permitted on rim of lock cylinders only.
B. Base Metals:
1. Produce hardware units of basic metal and forming method indicated, using
manufacturer's standard metal alloy, composition, temper and hardness, but in no case
of lesser (commercially recognized) quality than specified for applicable hardware units
by applicable ANSI/BHMA A156 series standards for each type of hardware item and
with ANSI/BHMA A156.18 for finish designations indicated. Do not furnish "optional"
materials or forming methods for those indicated, except as otherwise specified.
C. Fasteners:
2.3 HINGES
A. Templates:
1. Except for hinges to be installed entirely (both leaves) into wood doors and frames,
provide only template-produced units.
B. Screws:
a. For metal doors and frames, install machine screws into drilled and tapped holes.
b. For wood doors, install wood screws.
c. Finish screw heads to match surface of hinges or pivots.
C. Hinge Pins:
D. Number of Hinges:
1. Provide number of hinges indicated but not less than 2 hinges per door leaf for doors 60
inches or less in height and one additional hinge for each 30 inches, or fraction thereof, of
additional height.
E. Butts:
1. 5 knuckle, full mortise hinges with ball bearings conforming to ANSI/BHMA A156.1 and
as follows:
a. Exterior Door Hinges: Stainless steel base metal, A5111, 4-1/2 by 4-1/2 by 0.180
inches, with 4 ball bearings.
b. Interior Door Hinges: Cold rolled steel base metal, A8112, 4-1/2 by 4-1/2 by 0.134
inches, with 2 ball bearings.
c. Provide doors greater than 3 feet in width with hinges 5 inches high.
A. General:
1. Provide cylinders for each hardware device requiring cylinder operation. Cylinders and
the locks in which they are used shall be functionally compatible.
2. Coordinate preparation of doors receiving cylinders with door manufacturer to assure
their compatibility.
B. Cylinders:
1. Equip locks with cylinders that comply with performance requirements for Grade 1
cylinders as listed in ANSI/BHMA A 156.5.
2. Equip locks with cylinders for interchangeable-core pin tumbler inserts, compatible with
Installations locking system. Provide temporary inserts for the construction period, and
remove these when directed. Provide key control for removal and insertion of cores.
3. Furnish final cores (complete with materials to combinate) and keys for installation by
Government. After final acceptance and keying, Government will return construction
cores to Contractor.
4. Metals: Construct lock cylinder parts from brass or bronze, stainless steel or nickel silver.
5. Furnish replacement cores in the quantity of 10 percent of total locks with
interchangeable core pin tumbler inserts.
1. Installer shall meet with Contracting Officer at Project site to finalize keying requirements
and obtain final instructions in writing.
2. Keying System: Factory registered, complying with guidelines in ANSI/BHMA A156.28,
Appendix A. Except as otherwise indicated, provide new master key system for Project.
Review the keying system with the Contracting Officer and provide the type required
(master, grandmaster or great-grandmaster), either new or integrated with Governments
existing system.
3. Comply with Contracting Officers instructions for master keying and, except as otherwise
indicated, provide individual change key for each lock that is not designated to be keyed
alike with a group of related locks.
a. Key Type: Verify with Installation if a special key section is required to match
existing.
D. Delivery:
A. General:
1. Provide surface mounted building key box to contain key for emergency access to
building. Install in location indicated.
A. General:
1. Keyed locks shall conform to general requirements and cylinder requirements specified
under "LOCK CYLINDERS AND KEYING."
1. Provide a textured surface on the door handle, knob, pull, and other operating hardware
of doors that lead to areas that might prove dangerous to a blind person, i.e., doors to
loading platforms, boiler rooms, mechanical equipment rooms, electrical equipment
rooms, and janitors closets.
C. Strikes:
1. Provide manufacturer's standard wrought box strike for each latch and lock bolt, with
curved lip extended to protect frame, finished to match hardware set, unless otherwise
indicated.
2. Mortise-type locks and latches for doors 1-3/4 inches thick and over: Provide adjustable
bevel fronts or otherwise conform to the shape of the door edge.
3. Provide mortise locks with armored fronts.
4. Provide flat lip strikes for locks with 3-piece, antifriction latchbolts as recommended by
manufacturer.
5. Provide recess type top strikes for bolts locking into head frames, unless otherwise
indicated.
1. Mortise type locks shall be listed under Category F in BHMA's "Certified Product
Directory."
E. Mortise Type:
1. Stamped steel case with steel or brass parts; ANSI/BHMA A156.13;Series 1000. Provide
mortise locks and latches with escutcheon, minimum 7 by 1-3/4 inches.
2. Lever Handle: Cast lever handle and cast shank. Breakaway feature on lock functions
(such as weakened spindle or shear key) to prevent irreparable damage to lock when
force in excess of that specified in reference standard is applied to the lever handle.
Lever handles shall return to within 1/2 inch of door face.
3. Type 1: Operational Grade 1.
4. Type 2: Security Grade 1; meet both operational and security criteria.
5. Manufacturers: Subject to compliance with requirements, provide products by one of the
following:
F. Bored Type:
2. Lock Trim:
G. Latch Guard:
1. Provide stainless steel latchguards appropriate for the type of lock and strike used;
concealed, through-bolt fasteners.
1. Conform to ANSI/BHMA A156.31, US32D, Grade 1. Provide appropriate strike for use
with type of lock specified, i.e., rim latch, mortise lock, deadlatch.
2. Intermittent action; fail secure; audible operations.
3. Provide appropriate rectifier, current limiter, and transformer.
4. Provide concealed conduit and wiring in door frame and building construction to remote
electric power supply junction box and strike release switch junction box.
A. General:
1. Keyed auxiliary locks shall conform to general requirements and cylinder requirements
specified under "LOCK CYLINDERS AND KEYING."
2. Keyed auxiliary locks shall conform to requirements for strikes and rabbeted doors
specified under "LOCKS, LATCHES, AND BOLTS."
3. Locate centerline of deadlock and deadlatch strikes 48 inches above finished floor.
B. Deadlocks:
1. Bored auxiliary deadlock; Type 1, ANSI/BHMA A156.5, keyed both sides, E2141. Where
indicated in Hardware Schedule provide sign "THIS DOOR TO REMAIN UNLOCKED
WHEN THE BUILDING IS OCCUPIED" in line with lock. Letters shall be not less than 1
inch high in a contrasting background.
2. Bored auxiliary deadlock; Type 2, ANSI/BHMA A156.5, keyed inside, mounting plate on
out side, E5161.
3. Mortise deadlock; ANSI/BHMA A156.5, dead bolt operated by key from inside only, 1-
inch throw, E06082.
C. Deadlatches:
D. Flush Bolts:
1. Manual flush bolt, ANSI/BHMA A156.16; L04081; provide extension at head and
dustproof strike, L04011 or L04021 as applicable, at floor.
E. Padlocks:
1. Padlock; ASTM F 883, Grade 1, Type P01 (key operated), 6 pin deadlock, option E
(corrosion resistant), 4-inch shackle, sash chain with clevis on each end of chain. Secure
chain to padlock and frame. Option B (removable cylinder).
A. General:
1. Local sound alarm produced by a high decibel horn; armed and disarmed by control key;
cylinders as specified under "LOCK CYLINDERS AND KEYING" automatic rearming
after authorized use; sign stating "EMERGENCY EXIT/ALARM WILL SOUND"
2. Basis-of-Design Product: Detex Corporation, EAX 2500S surface mount on wall.
A. General:
B. Exit Device:
C. Delayed-Egress Lock:
1. Exit Device: Depressing push pad for more than 2 seconds initiates irreversible alarm
and 15-second delay for egress. Fire alarm voids 15-second delay. Comply with the
following:
A. General:
1. Type 1: Push/Pull set; J304/J407; 1/8 inch by 4-inch by 16-inch push plate with beveled
edges and 3/4 inch round bar by 8-inch center-to-center pull.
2. Type 2: Push/Pull set; push bar J501, 1 inch round bar by door width; pull J402, 90
degree offset, 1 inch round bar by 9 inches center-to-center.
3. Type 3: Pull; J402, 90 degree offset; 1 inch round bar by 9 inches center-to-center.
4. Type 4: Pull; J303 1/8-inch thick plate, with cylinder hole and pull.
5. Type 5: Pull; J501, 3/4 inch round bar by 24 inches center-to-center. Mount horizontally
on center of pull side of door.
2.11 CLOSERS
A. General:
B. Size of Units:
C. Overhead Closers:
a. C02011 surface mounted on pull side, regular arm with closing power adjustment
at least 50 percent more than minimum tested value.
b. C02021 surface mounted on push side, parallel arm with closing power adjustment
at least 50 percent more than minimum tested value and spring stop function in
soffit shoe set at approximately 90 degrees to 110 degrees.
A. General:
1. Provide manufacturer's standard exposed fasteners for door trim units consisting of either
machine screws or self-tapping screws.
2. Fabricate protection plates not more than 1- 1/2 inches less than door width on pull side
and not more than 1/2 inch less than door width on pull side by height indicated.
3. Stainless steel, 0.050 inch thick (U.S. 18 gage).
4. Bevel plate top and 2 sides.
5. Provide kickplates on both sides of door leaf unless otherwise indicated.
B. Types:
A. Types:
1. Type 1: Steel, 2 inches wide by 1/8 inch thick minimum, prime coat. Provide overlapping
astragal on one leaf of pairs of doors where required by NFPA 80 for fire-performance
rating or where indicated. Extend minimum 3/4 inch beyond edge of door on which
astragal is mounted. Paint finish to match doors. Provide with tamperproof fasteners.
Basis-of-Design Products:
A. General:
1. Conform to ANSI/BHMA A156.8 for overhead stops and ANSI/BHMA A156.16 for floor
and wall stops.
2. Provide stops at all doors except where closers with integral stops are indicated or no
stops are indicated.
3. Provide wall stops except where floor stops are more appropriate or overhead stops are
indicated.
4. Place door stops in such a position that they permit maximum door swing but do not
present hazard or obstruction.
5. Provide floor stops with risers at carpeted floors, at undercut doors, and at thresholds, as
required for at least 1/2 inch contact with door bottom.
6. Size overhead stops in accordance with manufacturer's printed instructions for each door
opening.
7. Set overhead stops for 110 degree opening, unless limited by building construction or
equipment.
B. Stop Types:
A. General:
1. Provide continuous jamb, head and sill seals on exterior doors and on interior doors
where indicated or scheduled. Provide noncorrosive fasteners for exterior applications
and elsewhere as indicated.
2. Provide only those units where resilient or flexible seal strip is easily replaceable and
readily available from stocks maintained by manufacturer.
1. ANSI/BHMA 156.22, R3B196; bumper-type resilient insert and metal retainer strips,
surface applied to stop, screw fastened, slotted holes for adjustment.
a. Metal and finish: Extruded aluminum with natural anodized finish, 0.062-inch
minimum thickness of main walls and flanges.
b. Bumper material: Solid neoprene conforming to ASTM D 2000 and
AAMA 701/702.
1. ANSI/BHMA 156.22, R3D536; door bottom consisting of contact-type resilient insert and
metal housing, applied to door face, screw fastened, slotted holes for adjustment, as
follows:
a. Metal and finish: Extruded aluminum rain drip type sweep retainer with natural
anodized finish, 0.062-inch minimum thickness of main walls and flanges.
b. Resilient seal strip: Flexible vinyl wiper or sweep seal strip.
2.16 THRESHOLDS
A. Extruded aluminum drip, 0.59 inch minimum projection, 0.082 inch minimum thickness, applied
to frame face, screw fastened.
A. Conform to ANSI/BHMA A156.16. L03011 for metal frames. Provide 3 silencers at strike jamb of
single doors and 2 silencers at tops of frames of double doors. Install silencers on all door
frames except frames receiving weatherstripping or gaskets.
1. US 26D, satin chromium except hardware exposed to the weather shall be US 32D, satin
stainless steel.
2. Provide finishes that match those established by BHMA.
2.20 FASTENERS
A. General:
1. Furnish door hardware with necessary screws, bolts and other fasteners of suitable size
and type to anchor the hardware in position for long life under hard use.
2. Furnish fastenings where necessary with expansion shields, toggle bolts, sex bolts, and
other approved anchors according to material which the hardware is to be applied and
instructions of the hardware manufacturer.
3. Fasteners exposed to weather shall be stainless steel, and shall match the finish of the
trim.
4. Design: All fastenings shall harmonize with hardware as to material and finish.
A. All other materials, such as brackets, fasteners, back-up plates and other accessories not
specifically described but required for a complete operable finish hardware installation, shall be
as provided by the Contractor and subject to approval.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Mounting Heights:
B. General:
1. Install each hardware item in compliance with the manufacturer's instructions and
recommendations. Where cutting and fitting is required to install hardware onto or into
surfaces that are later to be painted or finished in another way, coordinate removal,
storage, and reinstallation or application of surface protection with finishing work
specified in the Division 09 Sections. Do not install surface-mounted items until finishes
have been completed on the substrates involved.
2. Set units level, plumb, and true to line and location. Adjust and reinforce the attachment
substrate as necessary for proper installation and operation.
A. Adjusting:
1. Adjust and check each operating item of hardware and each door to ensure proper
operation or function of every unit. Replace units that cannot be adjusted to operate
freely and smoothly or as intended for the application made.
2. Where door hardware is installed more than one month prior to acceptance or occupancy
of a space or area, return to the installation during the week prior to acceptance or
occupancy and make final check and adjustment of all hardware items in such space or
area. Clean operating items as necessary to restore proper function and finish of
hardware and doors. Adjust door control devices to compensate for final operation of
heating and ventilating equipment.
B. Cleaning:
C. Demonstrating:
A. General:
1. Provide finish hardware in sets according to the following schedule. Unless otherwise
modified in the hardware sets, provide hardware as previously specified in this Section.
Hardware indicated is for each door leaf in an opening except where a single item serves
a pair of doors, and unless additional items are indicated.
Cashiers Office
HDW SET 2:
Butts
Storeroom Lock F07, Type 2
Closer C02011
Kickplate
Stop
Private Offices (Customer Service Office/ Medical Food Inspection Office/Region Management
Support, etc.)
HDW SET 4:
Butts
Entrance Lock F04, Type 2
Kickplate
Stop
Administrative Corridor
Omit sign if opening is not a required means of egress.
HDW SET 5:
Butts
Bored Auxiliary Deadlock Type 1 with Sign
Push/Pull Set Type 1
Closer C02011
Kickplate
Stop
Roof Hatch, Exterior Chain Link Gates, and Overhead Door at Mechanical Mezzanine
HDW SET 12:
Padlock
Electrical Utility Room containing equipment rated 1200 amperes or more and over 6 feet wide -
Single Exterior Door
HDW SET 14
Butts
Exit Device
Overhead Stop
Kickplate, 32 inches high
Threshold Type 2
Door Bottom Protection
Weatherstripping
Head Drip
Communications Room(CISIC)
HDW SET 21:
Butts
Storeroom Lock F07, Type 1
Closer C02011
Kickplate
Stop
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each product specification is current. Provide written notification to the DeCA
Project Manager when this verification has been completed.
B. The key control cabinet is a key management system designed to control key access and
accountability in commissary facilities. One or more key control cabinets may be required,
depending on size of the building. Locations and sizes of cabinets should be determined during
the design charrette process. They are typically located in areas accessible to employees at all
times when the building is occupied, such as the administrative office vestibule and warehouse
staging and receiving area. Coordinate required utility connections as specified. All utility
connections (power, data, etc) shall be hardwired internal to the key control cabinet.
C. Sizes are as follows:
1. 1E12-A - Key Control Cabinet, 16 key set.
2. 1E12-B - Key Control Cabinet, 32 key set.
3. 1E12-C - Key Control Cabinet, 48 key set.
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
3. CONTRACT DOCUMENT PHASE RESPONSIBILITIES.
A. The Contract Documents shall include the equipment list developed during the design charrette
process, clearly identifying responsibility for all equipment. To facilitate and expedite technical
review by DeCA, the contract documents shall use DeCA equipment item numbers to key both
the contractor-furnished and government-furnished equipment to the drawings.
B. If applicable, DeCA will provide the A/E with a list of existing government-owned equipment to be
re-used in the new or renovated facility. The A/E shall evaluate the identified equipment to
determine suitability, and confirm utility requirements for removal and relocation into the new or
renovated facility. If applicable, list or note on the contract specifications/drawings any
equipment to be salvaged or relocated by the construction contractor.
C. On addition / alteration projects, provide specific guidance on the Contract Documents regarding
disposition of salvaged equipment (i.e., will it become the property of the contractor or turned
over to DRMO). Turn-in of salvaged equipment is the responsibility of the Commissary Store
Director or designated Government representative. When the contractor is required to remove
and/or otherwise dispose of commissary equipment such as display and storage shelving, display
cases, refrigeration equipment and walk-in-boxes, the contractor will be required to sign DD Form
1348-1 Receipt Release Documents prepared by the Commissary Store Director or designated
Government representative. The A/E shall clearly identify any equipment that will become the
June 2011 08 79 13 1
DeCA DESIGN CRITERIA HANDBOOK
08 79 13 KEY STORAGE EQUIPMENT
property of the contractor for salvage, and clearly identify that all other operational equipment
shall remain the property of DeCA.
D. Verify that adequate space is available (both floor space and ceiling clearance) for all specified
equipment.
END OF SECTION
June 2011 08 79 13 2
SECTION 08 79 13
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
1. Commercial warranty.
2. Installation and operating instructions.
3. Parts list.
1. Submit copies of outline of instructional program for demonstration and training, including
a schedule of proposed dates, times, length of instruction time, and instructors' names for
each training module. Include learning objective and outline for each training module.
C. Submittal List:
2.1 MANUFACTURERS
A. General:
1. Design key management system to control key access and accountability in store and
warehouse operations:
2. Provide a stand-alone system with software and hardware for programming via built-in
keypad and LCD display, and report generation via integrated printer with capability to
generate management reports for audit trail, employee use, overdue keys, and keys in
use.
3. Cabinet dimensions: 20-1/2 inches wide by 34 inches long by -9-3/4 inches deep.
B. Operational:
1. Construct of minimum 18 gauge steel cabinet and 13 gauge steel door. Locate mounting
screws/bolts, electrical connections, and communication connections within the cabinet.
2. Equip with tamper alarms provided for keypad, door, and keys. Equip with internal relays
that automatically activates remote alarms or intrusion detection system (IDS) for
unauthorized key removal, non-returned keys, door left open, AC power outage, and
keypad tampering.
3. Provide with integrated battery back-up for 24 hour operation in event of power outage.
4. System shall control a minimum of 2000 each 4-8 digit individual user codes/PINS that
allow door and key access. Each user PIN can be assigned a minimum of four
programmable time zones to control key use times.
5. Key control functions:
a. Door access PIN allows key removal for user without additional code entry.
b. Minimum of four time zones per user per key. Programmable to release to users
only within certain time zones.
c. During entry of a user, key sets not authorized shall remain individually entrapped
to deny user access.
d. System shall have key control capability as specified below.
6. Internal memory shall be non-volatile and remain intact during a power outage. Internal
memory shall retain the latest 4000 transactions at all times. Minimum data shall include
all events by date, time, and user code, and all programmed functions.
7. Provide with RS-232 serial port and an integrated serial server device to allow PC
communication and report printing through Local Area Network via TCP/IP. Management
reports shall include: access audit trail (key movement by user, time, date), alarm events,
employee use, overdue keys, and keys in use.
A. General:
1. Design key management system to control key access and accountability in store and
warehouse operations:
2. Provide a stand-alone system with software and hardware for programming via built-in
keypad and LCD display, and report generation via integrated printer with capability to
generate management reports for audit trail, employee use, overdue keys, and keys in
use.
3. Cabinet dimensions: 20-1/2 inches wide by 34 inches long by 9-3/4 inches deep.
B. Operational:
1. Construct of minimum 18 gauge steel cabinet and 13 gauge steel door. Locate mounting
screws/bolts, electrical connections, and communication connections within the cabinet.
2. Equip with tamper alarms provided for keypad, door, and keys. Equip with internal relays
that automatically activates remote alarms or intrusion detection system (IDS) for
unauthorized key removal, non-returned keys, door left open, AC power outage, and
keypad tampering.
3. Provide with integrated battery back-up for 24 hour operation in event of power outage.
4. System shall control a minimum of 2000 each 4-8 digit individual user codes/PINS that
allow door and key access. Each user PIN can be assigned a minimum of four
programmable time zones to control key use times.
5. Key control functions:
a. Door access PIN allows key removal for user without additional code entry.
b. Minimum of four time zones per user per key. Programmable to release to users
only within certain time zones.
c. During entry of a user, key sets not authorized shall remain individually entrapped
to deny user access.
d. System shall have key control capability as specified below.
6. Internal memory shall be non-volatile and remain intact during a power outage. Internal
memory shall retain the latest 4000 transactions at all times. Minimum data shall include
all events by date, time, and user code, and all programmed functions.
7. Provide with RS-232 serial port and an integrated serial server device to allow PC
communication and report printing through Local Area Network via TCP/IP. Management
reports shall include: access audit trail (key movement by user, time, date), alarm events,
employee use, overdue keys, and keys in use.
A. General:
1. Design key management system to control key access and accountability in store and
warehouse operations:
2. Provide a stand-alone system with software and hardware for programming via built-in
keypad and LCD display, and report generation via integrated printer with capability to
generate management reports for audit trail, employee use, overdue keys, and keys in
use.
3. Cabinet dimensions: 20-1/2 inches wide by 34 inches long by 9-3/4 inches deep.
B. Operational:
1. Construct of minimum 18 gauge steel cabinet and 13 gauge steel door. Locate mounting
screws/bolts, electrical connections, and communication connections within the cabinet.
2. Equip with tamper alarms provided for keypad, door, and keys. Equip with internal relays
that automatically activates remote alarms or intrusion detection system (IDS) for
unauthorized key removal, non-returned keys, door left open, AC power outage, and
keypad tampering.
3. Provide with integrated battery back-up for 24 hour operation in event of power outage.
4. System shall control a minimum of 2000 each 4-8 digit individual user codes/PINS that
allow door and key access. Each user PIN can be assigned a minimum of four
programmable time zones to control key use times.
5. Key control functions:
a. Door access PIN allows key removal for user without additional code entry.
b. Minimum of four time zones per user per key. Programmable to release to users
only within certain time zones.
c. During entry of a user, key sets not authorized shall remain individually entrapped
to deny user access.
d. System shall have key control capability as specified below.
6. Internal memory shall be non-volatile and remain intact during a power outage. Internal
memory shall retain the latest 4000 transactions at all times. Minimum data shall include
all events by date, time, and user code, and all programmed functions.
7. Provide with RS-232 serial port and an integrated serial server device to allow PC
communication and report printing through Local Area Network via TCP/IP. Management
reports shall include: access audit trail (key movement by user, time, date), alarm events,
employee use, overdue keys, and keys in use.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine roughing-in for electrical systems to verify actual locations of connections before key
control cabinet installation. Proceed with installation only after unsatisfactory conditions have
been corrected.
3.2 INSTALLATION
A. General:
1. Comply with key control cabinet manufacturer's written installation instructions, unless
more stringent requirements are indicated.
2. Install key control cabinet where indicated on Drawings and where not indicated install
key control cabinet where directed by Contracting Officer.
B. Anchorage:
C. Clearances:
1. Verify that clearances are adequate to properly and freely operate key control cabinet.
D. Connections:
1. Connect key control cabinet to electrical systems, hardwired, not plugged-in to an outlet.
A. Testing:
1. Test, adjust, and verify operation of key control cabinet. Repair or replace any item found
to be defective or operating below rated capacity.
A. Adjust equipment for proper operation. After completion of installation, clean and polish all
exposed surfaces.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See other Division 08 Sections for doors and windows for glazing requirements
specified by reference to this Section.
2. This Section specifies uncoated float glass for monolithic, laminated, and insulating-glass units along
with the glazing materials required for their installation.
3. Individual glazed areas in hazardous locations shall comply with the 2009 International Building Code
for safety glazing.
4. Glazing within exterior door and window systems shall be laminated type and secured using structural
sealant to comply with current force protection requirements.
5. Exterior door and window systems shall be designed for security protection in accordance with UFC
4-010-01 DoD Minimum Antiterrorism Standards for Buildings (latest issue), Standard 10 and
Standard 12. The specific requirements in the following subparagraphs comply with Standard 10 and
Standard 12 in accordance with Standard 1, Table B-1, Standoff Distances for New and Existing
Buildings, i.e., Parking and Roadways Located within a Controlled Perimeter, Building Category is a
Primary Gathering Building, Applicable Level of Protection is Low, Standoff Distance For
Conventional Construction is 25 m, and Applicable Explosive Weight is II; and are also based on
application of ASTM F 2248 and ASTM E 1300 referenced standards resulting in glass and interlayer
thicknesses indicated in Tables B-2 and B-3. Where project conditions, including existing buildings,
are different from the preceding, additional and alternative requirements indicated in UFC 4-010-01
shall be followed.
A. Glazing shall be designed in accordance with ASTM F 2248 and ASTM E 1300 based on the
explosive weight and standoff distance indicated above.
1. Minimum laminated glass thickness and interlayer thickness shall be 6 mm (1/4") and 0.030"
respectively.
2. Dynamic analysis may be used as an alternative to the design approach described above.
3. Dynamic testing may be done as an alternative to the provisions of Standard 10.
B. Except where more stringent requirements are dictated by project conditions, restrict deflections
of edges of the blast resistant glazing the frames support to 1/160 of the length of the supported
edge at allowable stress levels determined in accordance with ASTM F 2248.
1. The supported edge length of a punched window shall be equal to the span of the glass,
regardless of any intermediate support connections. For multi-panel glazing systems, the
supported edge length shall be equal to the span of a single glass panel and the deflection
shall be calculated based on simple support conditions for that length.
C. Structural glazing is the installation of glass with structural silicone sealant applied between the
glass and glass-stops creating a bond between the two materials to resist expulsion of the glass
under pressure from the exterior. Generally, standard window and door glass stops can
accommodate a 3/8" bite and not a 1" bite. Ensure window and glazed door systems will
accommodate bite requirement.
1. Glazing shall have a minimum frame bite of 3/8" for structurally glazed systems.
2. Glazing shall have a minimum frame bite of 1" for systems that are not structurally glazed.
D. Coordinate glass unit thickness with width of frame rabbet holding glass.
June 2011 08 81 00 1
DeCA DESIGN CRITERIA HANDBOOK
08 81 00 GLAZING
6. If project requires no exterior glazing systems, edit specification section deleting requirements for
security protection.
7. If hurricane resistant glazing systems are required for Project, add performance requirements to
Specification Section.
END OF SECTION
June 2011 08 81 00 2
SECTION 08 81 00
GLAZING
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1. Glazing for the following products and applications, including those specified in other
Sections where glazing requirements are specified by reference to this Section:
a. Windows.
b. Doors.
c. Glazed entrances.
d. Interior borrowed lites.
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for glazing sealants used inside of the
weatherproofing system.
2. Division 08 Section Automatic Entrances.
3. Division 08 Section Aluminum-Framed Entrances and Storefronts
1.2 DEFINITIONS
A. Manufacturer:
1. A firm that produces primary glass or fabricated glass as defined in referenced glazing
publications.
B. Interspace:
1. Defects developed from normal use that is attributed to the manufacturing process and
not to causes other than glass breakage and practices for maintaining and cleaning
laminated glass contrary to manufacturer's written instructions. Defects include edge
separation, delamination materially obstructing vision through glass, and blemishes
exceeding those allowed by referenced laminated-glass standard.
1. Failure of the hermetic seal under normal use that is attributed to the manufacturing
process and not to causes other than glass breakage and practices for maintaining and
cleaning insulating glass contrary to manufacturer's written instructions. Evidence of
failure is the obstruction of vision by dust, moisture, or film on interior surfaces of glass.
A. General:
1. Provide glazing systems capable of withstanding normal thermal movement and wind
and impact loads (where applicable) without failure, including loss or glass breakage
attributable to the following: defective manufacture, fabrication, and installation; failure of
sealants or gaskets to remain watertight and airtight; deterioration of glazing materials; or
other defects in construction.
B. Glass Design:
1. Glass thicknesses indicated are minimums and are for detailing only. Confirm glass
thicknesses by analyzing Project loads and in-service conditions. Provide glass lites for
various size openings in nominal thicknesses indicated, but not less than thicknesses and
in strengths (annealed or heat treated) required to meet or exceed the following criteria:
c. Probability of Breakage for Vertical Glazing at Design Wind Pressure: 8 lites per
1000 for lites set vertically or not more than 15 degrees off vertical and under wind
action.
d. Glass Deflection:
2. Deflection Normal to Wall Plane At Design Blast Pressure: Except where more stringent
requirements are dictated by project conditions, restrict deflections of edges of blast
resistant glazing the frames support to 1/160 of the length of the supported edge at
allowable stress levels determined in accordance with ASTM F 2248.
a. The supported edge length of punched windows shall be equal to the span of the
glass, regardless of any intermediate support connections. For multi-panel glazing
systems, the supported edge length shall be equal to the span of a single glass
panel and the deflection shall be calculated based on simple support conditions for
that length.
3. Minimum Glass Thickness for Exterior Lites: Not less than 1/4 inch.
C. Thermal Movements:
1. Provide glazing that allows for thermal movements resulting from the following maximum
change (range) in ambient and surface temperatures acting on glass framing members
and glazing components. Base engineering calculation on surface temperatures of
materials due to both solar heat gain and nighttime-sky heat loss.
a. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces.
D. Structural Sealant:
1. Capable of withstanding tensile and shear stresses imposed by window and door
systems without failing adhesively or cohesively. Provide sealant that fails cohesively
before sealant releases from substrate when tested for adhesive compatibility with each
substrate and joint condition required.
a. Adhesive failure occurs when sealant pulls away from substrate cleanly, leaving no
sealant material behind.
b. Cohesive failure occurs when sealant breaks or tears within itself but does not
separate from each substrate because sealant-to-substrate bond strength exceeds
sealant's internal strength.
1. Test a minimum five production-run samples each of metal, glazing, and other material.
2. Prepare samples using techniques and primers required for installed assemblies.
3. Perform tests under environmental conditions that duplicate those under which
assemblies will be installed.
1.5 SUBMITTALS
A. Product Data:
B. LEED Submittals:
1. Product Data for Credit EQ 4.1: For glazing sealants used inside of the weatherproofing
system, including printed statement of VOC content.
C. Glazing Schedule:
D. Product Certificates:
1. Signed by manufacturers of glass and glazing products certifying that products furnished
comply with requirements.
1. From glazing structural-sealant manufacturer indicating glazing sealants were tested for
adhesion to glass and glazing channel substrates and for compatibility with glass and
other glazing materials.
G. Submittal List:
Reference Submittal Item Quantity Action
A. Installer Qualifications:
1. An experienced installer who has completed glazing similar in material, design, and
extent to that indicated for Project and whose work has resulted in construction with a
record of successful in-service performance.
1. Obtain insulating-glass units from one manufacturer using the same type of glass and
other components for each type of unit indicated.
1. Obtain laminated-glass units from one manufacturer using the same type of glass lites
and interlayers for each type of unit indicated.
1. Obtain glazing accessories from one source for each product and installation method
indicated.
E. Safety Glass:
F. Glazing Publications:
1. Permanently marked either on spacers or on at least one component lite of units with
appropriate certification label of the following inspecting and testing agency:
A. General:
A. Environmental Limitations:
1. Do not proceed with glazing when ambient and substrate temperature conditions are
outside limits permitted by glazing material manufacturers and when glazing channel
substrates are wet from rain, frost, condensation, or other causes.
2. Do not install liquid glazing sealants when ambient and substrate temperature conditions
are outside limits permitted by glazing sealant manufacturer or below 40 deg F.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. ASTM C 1036, Type I (transparent flat glass), Quality Q3 (glazing select); class indicated.
1. ASTM C 1048; Type I (transparent flat glass); Quality Q3 (glazing select); class, kind, and
condition indicated.
A. Laminated Glass:
B. Interlayer:
C. Laminating Process:
1. Fabricate laminated glass to meet ASTM C 1172, and complying with testing
requirements in 16 CFR 1201 for Category II materials, and with other requirements
specified. Use materials that have a proven record of no tendency to bubble, discolor, or
lose physical and mechanical properties after fabrication and installation:
a. Laminate lites with polyvinyl butyral interlayer in autoclave with heat plus pressure.
A. Insulating-Glass Units:
1. Dimensions indicated are nominal and the overall thicknesses of units are measured
perpendicularly from outer surfaces of glass lites at unit's edge.
C. Sealing System:
D. Spacer Specifications:
1. Manufacturer's standard spacer material and construction complying with the following
requirements:
A. General:
a. Compatibility: Select glazing sealants that are compatible with one another and
with other materials they will contact, including glass products, seals of insulating-
glass units, and glazing channel substrates, under conditions of service and
application, as demonstrated by sealant manufacturer based on testing and field
experience.
b. Suitability: Comply with sealant and glass manufacturers' written instructions for
selecting glazing sealants suitable for applications indicated and for conditions
existing at time of installation.
1. Comply with ASTM C 920 and other requirements indicated for each liquid-applied,
chemically curing sealant in the Glazing Sealant Schedule at the end of Part 3, including
those referencing ASTM C 920 classifications for type, grade, class, and uses.
C. Structural Sealants:
1. Closed-cell, PVC foam tape; factory coated with adhesive on both surfaces; packaged on
rolls with release liner protecting adhesive; and complying with AAMA 800 for the
following types:
a. EPDM.
b. Silicone.
c. Thermoplastic polyolefin rubber.
d. Any material indicated above.
A. General:
1. Provide products of material, size, and shape complying with referenced glazing
standard, requirements of manufacturers of glass and other glazing materials for
application indicated, and with a proven record of compatibility with surfaces contacted in
installation.
C. Setting Blocks:
D. Spacers:
1. Elastomeric material of hardness needed to limit glass lateral movement (side walking).
A. General:
1. Fabricate glass and other glazing products in sizes required to glaze openings indicated
for Project, with edge and face clearances, edge and surface conditions, and unless
otherwise indicated glass bite complying with written instructions of product manufacturer
and referenced glazing standard, to comply with system performance requirements.
a. Glass shall have a minimum frame bite of 3/8 inch for structurally glazed systems.
b. Glass shall have a minimum frame bite of 1 inch for systems that are not
structurally glazed.
PART 3 - EXECUTION
3.1 EXAMINATION
A. General:
1. Examine framing glazing, with Installer present, for compliance with the following:
2. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Clean glazing channels and other framing members receiving glass immediately before glazing.
Remove coatings not firmly bonded to substrates.
3.3 GLAZING
A. General:
a. Locate spacers directly opposite each other on both inside and outside faces of
glass. Install correct size and spacing to preserve required face clearances,
unless gaskets and glazing tapes are used that have demonstrated ability to
maintain required face clearances and to comply with system performance
requirements.
b. Provide 1/8-inch minimum bite of spacers on glass and use thickness equal to
sealant width. With glazing tape, use thickness slightly less than final compressed
thickness of tape.
8. Provide edge blocking where indicated or needed to prevent glass lites from moving
sideways in glazing channel, as recommended in writing by glass manufacturer and
according to requirements in referenced glazing publications.
9. Set glass lites in each series with uniform pattern, draw, bow, and similar characteristics.
10. Where wedge-shaped gaskets are driven into one side of channel to pressurize sealant
or gasket on opposite side, provide adequate anchorage so gasket cannot walk out when
installation is subjected to movement.
11. Square cut wedge-shaped gaskets at corners and install gaskets in a manner
recommended by gasket manufacturer to prevent corners from pulling away; seal corner
joints and butt joints with sealant recommended by gasket manufacturer.
A. General:
1. Position tapes on fixed stops so that, when compressed by glass, their exposed edges
are flush with or protrude slightly above sightline of stops.
2. Install tapes continuously, but not necessarily in one continuous length. Do not stretch
tapes to make them fit opening.
3. Where framing joints are vertical, cover these joints by applying tapes to heads and sills
first and then to jambs. Where framing joints are horizontal, cover these joints by
applying tapes to jambs and then to heads and sills.
4. Place joints in tapes at corners of opening with adjoining lengths butted together, not
lapped. Seal joints in tapes with compatible sealant approved by tape manufacturer.
5. Do not remove release paper from tape until just before each glazing unit is installed.
6. Center glass lites in openings on setting blocks and press firmly against tape by inserting
dense compression gaskets formed and installed to lock in place against faces of
A. General:
1. Install glass with structural silicone sealant applied between glass and metal window
frame creating a bond between the two materials to resist expulsion of the glass under
pressure from the exterior, in accordance with performance requirements.
a. Apply the structural silicone sealant bead to both sides of the glass panel for single
pane glazing but only to the inboard side for insulating glass units.
b. Install continuous spacers, or spacers combined with cylindrical sealant backing,
between glass lites and glazing stops to maintain glass face clearances and to
prevent sealant from extruding into glass channel and blocking weep systems until
sealants cure. Secure spacers or spacers and backings in place and in position to
control depth of installed sealant relative to edge clearance for optimum sealant
performance.
c. Force sealants into glazing channels to eliminate voids and to ensure complete
wetting or bond of sealant to glass and channel surfaces.
d. Tool exposed surfaces of sealants to provide a substantial wash away from glass.
A. Testing Agency:
B. Testing Services:
C. Structural-sealant-glazed windows and doors will be considered defective if they do not pass
tests.
A. General:
1. Protect exterior glass from damage immediately after installation by attaching crossed
streamers to framing held away from glass. Do not apply markers to glass surface.
Remove nonpermanent labels, and clean surfaces.
2. Protect glass from contact with contaminating substances resulting from construction
operations, including weld splatter. If, despite such protection, contaminating substances
do come into contact with glass, remove them immediately as recommended by glass
manufacturer.
3. Examine glass surfaces adjacent to or below exterior concrete and other masonry
surfaces at frequent intervals during construction, but not less than once a month, for
build-up of dirt, scum, alkaline deposits, or stains; remove as recommended by glass
manufacturer.
4. Remove and replace glass that is broken, chipped, cracked, abraded, or damaged in any
way, including natural causes, accidents, and vandalism, during construction period.
5. Wash glass on both exposed surfaces in each area of Project not more than four days
before date scheduled for inspections that establish date of Substantial Completion.
Wash glass as recommended by glass manufacturer.
A. Type 1 - Security Protection Uncoated Clear Insulating Heat-Treated and Laminated Float
Glass Unit:
1. Outdoor Lite:
1. Outdoor Lite:
2. Indoor Lite: Kind LA, consisting of two lites of annealed float glass.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 10 Section Toilet Accessories for factory-assembled framed and
backed mirror units.
2. This Section specifies unframed silvered flat glass mirrors for mounting on walls.
3. Use mechanical devices (brackets, frames, bolts, clips, etc.) on all mirrors, except for very small
mirrors, in addition to mastic to support the weight of the mirror. Mechanical support needs to be used
to support not only the weight of the mirror but also to prevent the top edge of the mirror from pulling
away from the substrates to which the mirror is attached.
4. Mirrors in hazardous locations shall comply with the 2009 International Building Code for safety
glazing.
END OF SECTION
June 2011 08 83 00 1
SECTION 08 83 00
MIRRORS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
1. From mirror manufacturer indicating that mirror mastic was tested for compatibility and
adhesion with mirror backing and substrates on which mirrors are installed.
C. Submittal List:
A. Installer Qualifications:
1. A qualified installer who employs glass installers for this Project who are certified under
the National Glass Association's Certified Glass Installer Program.
1. Obtain mirrors from one source for each type of mirror indicated.
1. Obtain mirror glazing accessories from one source for each type of accessory indicated.
a. GANA's "Glazing Manual" unless more stringent requirements are indicated. Refer
to this publication for definitions of glass and glazing terms not otherwise defined in
this Section or in referenced standards.
b. GANA Mirror Division's "Mirrors, Handle with Extreme Care: Tips for the
Professional on the Care and Handling of Mirrors."
A. Mirror Protection:
1. Comply with mirror manufacturer's written instructions for shipping, storing, and handling
mirrors as needed to prevent deterioration of silvering, damage to edges, and abrasion of
glass surfaces and applied coatings. Store indoors, protected from moisture including
condensation.
A. Environmental Limitations: Do not install mirrors until ambient temperature and humidity
conditions are maintained at levels indicated for final occupancy.
1.6 WARRANTY
A. Special Warranty:
1. Manufacturer's standard form in which mirror manufacturer agrees to replace mirrors that
deteriorate within specified warranty period. Deterioration of mirrors is defined as defects
developed from normal use that are not attributed to mirror breakage or to maintaining
and cleaning mirrors contrary to manufacturer's written instructions. Defects include
discoloration, black spots, and clouding of the silver film.
2.1 MANUFACTURERS
1. ASTM C 1503, Mirror Glazing Quality manufactured using copper-free, low-lead mirror
coating process.
2. [Ultraclear (low-iron) float glass with a minimum 91 percent visible light
transmission].
3. Nominal Thickness: 6.0 mm.
1. Tempered Clear Glass: Mirror Glazing Quality, for blemish requirements; and comply
with ASTM C 1048 for Kind FT, Condition A, tempered float glass before silver coating is
applied.
2. Nominal Thickness: 6.0 mm
A. Setting Blocks: Elastomeric material with a Type A Shore durometer hardness of 85, plus or
minus 5.
B. Edge Sealer: Coating compatible with glass coating and approved by mirror manufacturer for
use in protecting against silver deterioration at mirrored glass edges.
C. Mirror Mastic: An adhesive setting compound, produced specifically for setting mirrors and
certified by both mirror manufacturer and mastic manufacturer as compatible with glass coating
and substrates on which mirrors will be installed.
a. Bottom Trim: J-channels formed with front leg and back leg not less than 3/8 and
7/8 inch in height, respectively, and a thickness of not less than 0.04 inch.
B. Outside Corners:
1. Extruded aluminum, anodized clear. Provide 4 inch long setting blocks in channel at
quarter points and 1/4 inch weeps at channel bottom. Provide felt or plastic pads
between mirror and metal.
2. Basis-of-Design Product: The Engineered Products Co. (EPCO),Architectural &
Functional Hardware Products. Model No. 2015A.
C. Fasteners:
1. Fabricated of same basic metal and alloy as fastened metal and matching it in finished
color and texture where fasteners are exposed.
1. Provide devices as required for mirror hardware installation. Provide toothed or lead-
shield expansion-bolt devices for drilled-in-place anchors. Provide galvanized anchors
and inserts for applications on inside face of exterior walls and where indicated.
2.5 FABRICATION
A. Mirror Sizes:
B. Cutouts:
1. Fabricate cutouts for notches and holes in mirrors without marring visible surfaces.
Locate and size cutouts so they fit closely around penetrations in mirrors.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, over which mirrors are to be mounted, with Installer present, for
compliance with installation tolerances, substrate preparation, and other conditions affecting
performance. Verify compatibility with and suitability of substrates, including compatibility of
mirror mastic with existing finishes or primers. Proceed with mirror installation only after
unsatisfactory conditions have been corrected and surfaces are dry.
A. Comply with mastic manufacturer's written installation instructions for preparation of substrates,
including coating surfaces with mastic manufacturer's special bond coating where applicable.
3.3 INSTALLATION
A. General:
1. Install mirrors to comply with mirror manufacturer's written instructions and with
referenced GANA publications. Mount mirrors accurately in place in a manner that
avoids distorting reflected images.
2. Provide a minimum air space of 1/8 inch between back of mirrors and mounting surface
for air circulation between back of mirrors and face of mounting surface.
B. Mounting:
1. For wall-mounted mirrors, install mirrors with mastic and mirror hardware.
2. Attach mirror hardware securely to mounting surfaces with mechanical fasteners installed
with anchors or inserts as applicable. Install fasteners so heads do not impose point
loads on backs of mirrors.
3. For mirror hardware in the form of continuous J-channels at bottom, provide setting
blocks 1/8 inch thick by 4 inches long at quarter points. To prevent trapping water,
provide, between setting blocks, 2 slotted weeps not less than 1/4 inches 20 wide by 3/8
inch long.
4. Install mastic as follows:
5. Install column-mounted mirrors similar to wall-mounted mirrors except install with outside
corner channels.
A. Protect mirrors from breakage and contaminating substances resulting from construction
operations.
C. Maintain environmental conditions that will prevent mirrors from being exposed to moisture from
condensation or other sources for continuous periods of time.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 07 Section Thermal Insulation for thermal insulations and vapor
retarders required in portland cement plaster soffit assemblies. See Division 05 Section Cold-Formed
Metal Framing for metal framing that support furring, lath, and portland cement plaster.
2. This Section specifies portland cement plasterwork on metal lath exterior soffit applications. This
Section also specifies furring that supports metal lath.
B. Indicate metal accessories as zinc except where aluminum vented moldings are required.
3. Consideration should be given to structural supports to resist wind uplift on exterior suspended soffit
systems.
4. Isolate plaster assemblies from abutting structural elements at points of contact. Because structural
systems are subject to creep, settlement, deflection, thermal movement, and wind-load strains,
consider the effect of these forces on assemblies and detail isolation requirements on the Drawings.
5. Locate control joints at natural lines of weakness to prevent cracking. Show the location of and detail
control joints on the Drawings.
A. Delineate plaster soffits into areas (panels) of 100 sq. ft. maximum.
B. Locate distances between control joints of not more than 18' o.c.
C. Delineate plaster soffits into areas (panels) with length-to-width ratios of not greater than 2-1/2:1.
D. Locate control joints where plaster soffit framing or furring changes direction.
E. Where plaster soffit areas change dimensions, control joints should be located to delineate
rectangular-shaped areas (panels) to relieve the stress that occurs at the corner formed by the
dimension change.
6. Provide float finish, as opposed to a smooth finish, to receive a painted finish, because of the
inevitability of fine, random shrinkage cracks or fissures occurring during curing.
END OF SECTION
June 2011 09 24 23 1
SECTION 09 24 23
PORTLAND CEMENT PLASTER
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for recycled content of steel products.
2. Division 05 Section Cold-Formed Metal Framing for metal framing that support furring,
lath, and portland cement plaster.
1.2 SUBMITTALS
A. Product Data:
B. LEED Submittals:
1. Product Data for Credit MR 4.1[ and Credit MR 4.2]: For products having recycled
content, documentation indicating percentages by weight of postconsumer and
preconsumer recycled content.
a. Include statement indicating costs for each product having recycled content.
2. Product Data for Credit EQ 4.1: For sealants, including printed statement of VOC
content.
C. Shop Drawings:
1. Show locations and installation of control and expansion joints including plans,
elevations, sections, details of components, and attachments to other work.
1. For each type of finish coat indicated; 12 by 12 inches, and prepared on rigid backing.
E. Submittal List:
A. Store materials inside under cover and keep them dry and protected against damage from
weather, direct sunlight, surface contamination, corrosion, construction traffic, and other causes.
A. Reference Standard:
1. Apply and cure plaster to prevent plaster drying out during curing period. Use
procedures required by climatic conditions, including moist curing, providing coverings,
and providing barriers to deflect sunlight and wind.
2. Apply plaster when ambient temperature is greater than 40 deg F.
3. Protect plaster coats from freezing for not less than 48 hours after set of plaster coat has
occurred.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Components, General:
1. Comply with ASTM C 1063. For steel sheet components not included in ASTM C 1063,
comply with ASTM C 645 requirements for metal, unless otherwise indicated.
B. Cold-Rolled Channels:
1. Base metal thickness of 0.0538 inch with ASTM A 653/A 653M, G60, hot-dip galvanized
zinc coating.
C. Wire:
1. ASTM A 641/A 641M, Class 1 zinc coating, soft temper, not less than 0.0475-inch
diameter, unless otherwise indicated.
A. Direct Furring:
B. Tie Wire:
1. For saddle tying cross furring to main runners use 0.0625-inch- diameter wire or double
strand of 0.0475-inch- diameter wire.
A. Expanded-Metal Lath:
1. ASTM C 847 with ASTM A 653/A 653M, G60, hot-dip galvanized zinc coating.
2. 3/8-Inch Rib Lath.
3. Weight: 4 lb/sq. yd.
2.5 ACCESSORIES
A. General:
1. Comply with ASTM C 1063 and coordinate depth of trim and accessories with
thicknesses and number of plaster coats required.
B. Zinc Accessories:
1. Casing Beads: Fabricated from zinc; square-edged style; with expanded flanges.
2. Control Joints: Fabricated from zinc; one-piece-type, folded pair of unperforated screeds
in M-shaped configuration; with perforated flanges and removable protective tape on
plaster face of control joint.
1. Potable and free of substances capable of affecting plaster set or of damaging plaster,
lath, or accessories.
a. Fasteners for Attaching Metal Lath to Substrates: Complying with ASTM C 1063.
A. General:
1) Scratch Coat: For cementitious material, mix 1 part portland cement and 0
to 3/4 parts lime. Use 2-1/2 to 4 parts aggregate per part of cementitious
material (sum of separate volumes of each component material).
2) Brown Coat: For cementitious material, mix 1 part portland cement and 0 to
3/4 parts lime. Use 3 to 5 parts aggregate per part of cementitious material
(sum of separate volumes of each component material).
1. Portland Cement Mix: For cementitious materials, mix 1 part portland cement and 3/4 to
1-1/2 parts lime. Use 1-1/2 to 3 parts aggregate per part of cementitious material (sum of
separate volumes of each component material).
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and substrates, with Installer present, including structural framing, for
compliance with requirements and other conditions affecting performance. Proceed with
installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Protect adjacent work from soiling, spattering, moisture deterioration, and other harmful effects
caused by plastering.
A. General:
a. Comply with ASTM C 754 for installation of items not addressed in ASTM C 1063.
a. Isolate soffit assemblies where they abut or are penetrated by building structure.
3. Do not bridge building control joints with furring members. Frame both sides of joints
independently.
A. Installation Tolerances:
1. Install steel furring components for soffits so members are level to within 1/4 inch in 10
feet measured lengthwise on each member and transversely between parallel members.
2. Install steel furring components for soffits in sizes and spacings indicated but not less
than that required by the referenced steel framing and installation standards.
B. Furring Spacing:
A. Expanded-Metal Lath:
A. General:
A. General:
1. Comply with ASTM C 926 except nominal thickness of plaster shall be 3/4-inch.
a. Do not deviate more than plus or minus 1/4 inch in 10 feet from a true plane in
finished plaster surfaces, as measured by a 10-foot straightedge placed on
surface.
b. Finish plaster flush with metal frames and other built-in metal items or accessories
that act as a plaster ground, unless otherwise indicated. Where casing bead does
not terminate plaster at metal frame, cut base coat free from metal frame before
plaster sets and groove finish coat at junctures with metal.
c. Provide plaster surfaces that are ready to receive field-applied finishes indicated.
1. Scratch and brown coats for three-coat plasterwork; 1/2 inch thick.
A. Cut, patch, replace, and repair plaster as necessary to accommodate other work and to restore
cracks, dents, and imperfections. Repair or replace work to eliminate blisters, buckles, crazing
and check cracking, dry outs, efflorescence, sweat outs, and similar defects and where bond to
substrate has failed.
A. Remove temporary protection and enclosure of other work. Promptly remove plaster from other
surfaces not indicated to be plastered. Repair floors, walls, and other surfaces stained, marred,
or otherwise damaged during plastering.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 06 Section Rough Carpentry for plywood backing panels at
communications equipment, Division 06 Section Sheathing for gypsum sheathing, and Standard
Commissary Room and Finish Schedule in Appendix "A".
2. This Section specifies gypsum board assemblies, non-load bearing metal framing support systems,
and sound attenuation blankets and acoustical sealants.
3. Provide water-resistant gypsum backing board at ceramic tile, wet walls, and high humidity areas.
4. Provide sound attenuation in partitions surrounding training rooms, administration offices, restrooms,
and break rooms and at mechanical rooms. If partition stops at underside of acoustical panel ceiling,
install sound attenuation above ceiling of room.
5. Provide fire retardant treated plywood as part of gypsum wallboard construction at locations identified
in Standard Commissary Room and Finish Schedule. Fire-Retardant-Treated plywood is covered in
Division 06 Section Rough Carpentry.
END OF SECTION
June 2011 09 29 00 1
SECTION 09 29 00
GYPSUM BOARD
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for sealants and recycled content of
products.
2. Division 05 Section Cold-Formed Metal Framing for exterior and interior load-bearing and
exterior non-load-bearing wall studs; floor joists; roof rafters and ceiling joists; and roof
trusses.
3. Division 06 Section Sheathing for gypsum sheathing at exterior walls.
1.2 SUBMITTALS
B. LEED Submittals:
1. Product Data for Credit MR 4.1[ and Credit MR 4.2]: For products having recycled
content, documentation indicating percentages by weight of postconsumer and
preconsumer recycled content. Include statement indicating cost for each product having
recycled content.
4. Product Data for Credit EQ 4.1: For adhesives used to laminate gypsum board panels to
substrates, documentation including printed statement of VOC content.
C. Submittal List:
1.3 DEFINITIONS
A. Gypsum Board Construction Terminology: Refer to ASTM C 11 and GA-505 for definitions of
terms for gypsum board assemblies not defined in this Section or in other referenced standards.
A. Deliver materials in original packages, containers, or bundles bearing brand name and
identification of manufacturer or supplier. Store materials inside under cover and keep them dry
1. Establish and maintain environmental conditions for applying and finishing gypsum board
to comply with ASTM C 840 requirements or gypsum board manufacturer's
recommendations, whichever are more stringent.
B. Room Temperatures:
1. For nonadhesive attachment of gypsum board to framing, maintain not less than 40 F.
Do not exceed 95 deg F when using temporary heat sources.
C. Ventilation:
1. Ventilate building spaces as required to dry joint treatment materials. Avoid drafts during
hot, dry weather to prevent finishing materials from drying too rapidly.
PART 2 - PRODUCTS
a. Steel Sheet Components: Comply with ASTM C 645 requirements for metal
unless otherwise indicated.
b. Protective Coating: Manufacturer's standard rust-inhibiting coating.
A. General:
1. Provide components complying with ASTM C 754 for materials and sizes unless
otherwise indicated.
1. Cold-rolled steel, 0.053 inch minimum thickness of base (uncoated) metal and 1/2 inch
wide flanges, and as follows:
1. ASTM C 645, hat-shaped, depth of 7/8 inch, and minimum thickness of base (uncoated)
metal of 0.018 inch.
A. General:
a. Component Sizes and Spacings: As indicated but not less than that required to
comply with ASTM C 754.
1. ASTM C 645.
1. Where indicated, provide steel sheet top runner manufactured to prevent cracking of
finishes applied to interior partition framing resulting from deflection of structure above; in
thickness not less than indicated for studs and in width to accommodate depth of studs.
1. Provide fasteners of type, material, size, corrosion resistance, holding power, and other
properties required to fasten steel framing to substrates.
A. General:
C. Types:
1. Regular type.
2. Type X.
3. Type C: Thickness as required by fire-resistance-rated assembly indicated on Drawings.
4. Ceiling Type: Manufactured to have more sag resistance than regular-type gypsum
board
1. Corner beads, edge trim, and control joints complying with ASTM C 1047 and
requirements indicated below:
a. Material: Formed metal, or metal combined with paper, with metal complying with
the following requirement:
A. General:
A. General:
1. Provide auxiliary materials for gypsum board construction that comply with referenced
standards and recommendations of gypsum board manufacturer.
1. Complying with ASTM C 1002 for fastening gypsum board to steel members less than
0.033 inch (22 gage) thick.
2. Complying with ASTM C 954 for fastening gypsum board to steel members from 0.033 to
0.112 inch thick.
D. Sound-Attenuation Blankets:
E. Acoustical Joint Sealant: Manufacturer's standard nonsag, paintable, nonstaining latex sealant
complying with ASTM C 834. Product effectively reduces airborne sound transmission through
perimeter joints and openings in building construction as demonstrated by testing representative
assemblies according to ASTM E 90.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates to which gypsum board assemblies attach or abut, installed hollow metal
frames, cast-in-anchors, and structural framing, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting performance of
assemblies specified in this Section. Do not proceed with installation until unsatisfactory
conditions have been corrected.
3.2 PREPARATION
1. Install steel framing to comply with ASTM C 754 and with ASTM C 840 requirements that
apply to framing installation.
1) Install deflection track top runner to attain lateral support and avoid axial
loading.
4. Do not bridge building control and expansion joints with steel framing or furring members.
Independently frame both sides of joints with framing or furring members as indicated.
1. Install hangers plumb and free from contact with insulation or other objects within ceiling
plenum that are not part of supporting structural or ceiling suspension system. Splay
hangers only where required to miss obstructions and offset resulting horizontal forces by
bracing, countersplaying, or other equally effective means.
2. Where width of ducts and other construction within ceiling plenum produces hanger
spacings that interfere with the location of hangers required to support standard
suspension system members, install supplemental suspension members and hangers in
form of trapezes or equivalent devices. Size supplemental suspension members and
hangers to support ceiling loads within performance limits established by referenced
standards.
3. Secure wire hangers by looping and wire-tying, either directly to structures or to inserts,
eyescrews, or other devices and fasteners that are secure and appropriate for substrate,
and in a manner that will not cause them to deteriorate or otherwise fail.
4. Do not attach hangers to steel deck tabs.
5. Do not attach hangers to steel roof deck. Attach hangers to structural members.
8. Installation Tolerances: Install steel framing components for suspended ceilings so that
cross-furring or grid suspension members are level to within 1/8 inch in 12 feet as
measured both lengthwise on each member and transversely between parallel members.
9. Wire-tie or clip furring members to main runners and to other structural supports as
indicated.
A. General:
1. Install runners (tracks) at floors, ceilings, and structural walls and columns where gypsum
board stud assemblies abut other construction.
a. Where studs are installed directly against exterior walls, install asphalt felt strips
between studs and wall.
2. Extend partition framing full height to structural supports or substrates above suspended
ceilings, except where otherwise indicated. Continue framing over frames for doors and
openings and frame around ducts penetrating partitions above ceiling to provide support
for gypsum board.
3. Install steel studs and furring in sizes and at spacings indicated.
4. Install steel studs so flanges point in the same direction and leading edge or end of each
gypsum board panel can be attached to open (unsupported) edges of stud flanges first.
7. Frame openings other than door openings to comply with details indicated or, if none
indicated, as required for door openings. Install framing below sills of openings to match
framing required above door heads.
1. Install and finish gypsum panels to comply with ASTM C 840 and GA-216.
2. Install sound-attenuation blankets, where indicated, prior to installing gypsum panels
unless blankets are readily installed after panels have been installed on one side.
a. Except where concealed application is indicated or required for sound, fire, air, or
smoke ratings, coverage may be accomplished with scraps of not less than 8 sq.
ft. in area.
b. Fit gypsum panels around ducts, pipes, and conduits.
c. Where partitions intersect structural members projecting below underside of
floor/roof slabs and decks, cut gypsum panels to fit profile formed by structural
members; allow 1/4- to 3/8-inch-wide joints to install sealant.
A. Single-Layer Application:
1. For substrates indicated to receive thin-set ceramic tile and similar rigid applied wall
finishes, comply with the following:
A. General:
1. For trim accessories with back flanges, fasten to framing with the same fasteners used to
fasten gypsum board. Otherwise, fasten trim accessories according to accessory
manufacturer's directions for type, length, and spacing of fasteners.
2. Install cornerbead at external corners.
3. Install edge trim where edge of gypsum panels would otherwise be exposed. Provide
edge trim type with face flange formed to receive joint compound, except where other
types are indicated.
a. Install LC-bead where gypsum panels are tightly abutted to other construction and
back flange can be attached to framing or supporting substrate.
b. Install L-bead where edge trim can only be installed after gypsum panels are
installed.
c. Install U-bead where indicated.
A. General:
1. Treat gypsum board joints, interior angles, flanges of cornerbead, edge trim, control
joints, penetrations, fastener heads, surface defects, and elsewhere as required to
prepare gypsum board surfaces for decoration.
2. Prefill open joints, rounded or beveled edges, and damaged areas using setting-type joint
compound.
3. Apply joint tape over gypsum board joints, except those with trim accessories having
flanges not requiring tape.
4. Levels of Gypsum Board Finish: Provide the following levels of gypsum board finish per
GA-214.
a. Level 1 for ceiling plenum areas and concealed areas, unless a higher level of
finish is required for fire-resistance-rated assemblies and sound-rated assemblies.
1) At joints and angles, embed tape in joint compound. Finish panel surfaces
free of excess joint compound, but tool marks and ridges are acceptable.
1) At joints and angles, embed tape in joint compound and apply one separate
coat of joint compound over tape, fastener heads, and flanges of trim
accessories. Joint compound applied on the face of the tape when the tape
is embedded is considered a separate coat. Finish panel surfaces free of
excess joint compound, but tool marks and ridges are acceptable.
c. Level 4 for all gypsum board exposed surfaces, unless otherwise indicated.
1) At joints and angles, embed tape in joint compound and apply three
separate coats of joint compound over joints, angles, fastener heads, and
flanges of trim accessories. Finish panel surfaces and joint compound
smooth and free of tool marks and ridges.
5. Use the following joint compound combination as applicable to the finish levels specified:
6. For Level 4 gypsum board finish, embed tape in joint compound and apply first, fill
(second), and finish (third) coats of joint compound over joints, angles, fastener heads,
and accessories. Touch up and sand between coats and after last coat as needed to
produce a surface free of visual defects and ready for decoration.
7. Where Level 2 gypsum board finish is indicated, embed tape in joint compound and apply
first coat of joint compound.
8. Where Level 1 gypsum board finish is indicated, embed tape in joint compound.
9. Finish water-resistant gypsum backing board forming base for ceramic tile to comply with
ASTM C 840 and gypsum board manufacturer's directions for treatment of joints behind
tile.
A. Install unfaced-fiber blanket insulation over suspended ceilings so that insulation extends over
entire ceiling.
A. Acoustical Assemblies: Seal construction at perimeters, behind control joints, and at openings
and penetrations with a continuous bead of acoustical sealant. Install acoustical sealant at both
faces of partitions at perimeters and through penetrations. Comply with ASTM C 919 and with
manufacturer's written recommendations for locating edge trim and closing off sound-flanking
paths around or through assemblies, including sealing partitions above acoustical ceilings.
A. Promptly remove any residual joint compound from adjacent surfaces. Provide final protection
and maintain conditions, in a manner acceptable to Installer, that ensure gypsum board
assemblies are without damage or deterioration at the time of final acceptance.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: Division 07 Section Joint Sealants for sealing of expansion, contraction, control,
and isolation joints in tile surfaces; and Division 09 Section Gypsum Board for ceramic wall tile
substrate.
2. This Section specifies thin-set unglazed and glazed ceramic tile, including pavers, wall tile, stone
thresholds, tile setting, grouting materials, accessories, and installation requirements.
3. TCA Handbook, 2009, installation methods for F113, F116, F131, F132, F133, and F134 indicate
concrete receiving tile be steel troweled and fine broom finished. The General Requirements:
Subsurfaces and Preparations by Other Trades 2005 [New] in the ANSI tile installation specification
booklet (ANSI A108 series) suggests particular specifications for related trades regarding preparation
for tile work that is not a part of the ANSI specifications. This Section specifies requirements to
prepare the concrete slab in accordance with ANSI A108 series and roughen slab where required to
assure bond.
4. Indicate expansion joints and other sealant-filled joints including control, contraction, and isolation
joints on Drawings.
A. Indicate sealant-filled control joints at perimeter of floor tiles where abutting walls and columns.
A. Provide tile that is classified in ANSI A137.1 as Vitreous Tile, based on water absorption of 0.5 to
3.0 percent.
B. Provide epoxy grout in food handling and food processing areas where quarry tile is required.
END OF SECTION
June 2011 09 30 00 1
SECTION 09 30 00
TILING
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 DEFINITIONS
A. General: Definitions in the ANSI A108 series of tile installation standards and in ANSI A137.1
apply to Work of this Section unless otherwise specified.
B. ANSI A108 Series: ANSI A108.01, ANSI A108.02, ANSI A108.1A, ANSI A108.1B,
ANSI A108.1C, ANSI A108.4, ANSI A108.5, ANSI A108.6, ANSI A108.8, ANSI A108.9,
ANSI A108.10, ANSI A108.11, ANSI A108.12, ANSI A108.13, ANSI A108.14, ANSI A108.15,
ANSI A108.16, and ANSI A108.17, which are contained in "American National Standard
Specifications for Installation of Ceramic Tile."
1.3 SUBMITTALS
B. LEED Submittals:
2. Product Data for Credit IEQ 4.3: For [adhesives] [and] [grouts], documentation
including printed statement of VOC content.
3. Product Data for Credit IEQ 4.3: For tile floors, documentation from an independent
testing agency indicating compliance with the FloorScore Standard.
4. Laboratory Test Reports for Credit IEQ 4: For [adhesives] [sealants] [and] [tile flooring
systems], documentation indicating that products comply with the testing and product
requirements of the California Department of Health Services' "Standard Practice for the
Testing of Volatile Organic Emissions from Various Sources Using Small-Scale
Environmental Chambers."
1. Assembled samples with grouted joints for each type and composition of tile and for each
color and finish required, at least 12 inches square and mounted on rigid panel. Use
grout of type and in color or colors approved for completed work.
D. Submittal List:
A. Source Limitations for Tile: Obtain all tile of same type and color or finish from one source or
producer.
1. Obtain tile from same production run and of consistent quality in appearance and
physical properties for each contiguous area.
C. Source Limitations for Other Products: Obtain each of the following products specified in this
Section from a single manufacturer for each product:
1. Stone thresholds.
2. Joint sealants.
3. Cementitious backer units.
4. Metal edge strips.
A. Deliver and store packaged materials in original containers with seals unbroken and labels
intact until time of use. Comply with requirement in ANSI A137.1 for labeling sealed tile
packages.
B. Store tile and cementitious materials on elevated platforms, under cover, and in a dry location.
C. Store aggregates where grading and other required characteristics can be maintained and
contamination avoided.
D. Store liquid latexes and emulsion adhesives in unopened containers and protected from
freezing.
E. Handle tile that has temporary protective coating on exposed surfaces to prevent coated
surfaces from contacting backs or edges of other units. If coating does contact bonding
surfaces of tile, remove coating from bonding surfaces before setting tile.
A. Environmental Limitations: Do not install tile until construction in spaces is complete and
ambient temperature and humidity conditions are maintained at the levels indicated in
referenced standards and manufacturer's written instructions.
A. Furnish extra materials that match and are from same production runs as products installed and
that are packaged with protective covering for storage and identified with labels describing
contents.
1. Tile and Trim Units: Furnish quantity of full-size units equal to 2 percent of amount
installed, for each type, composition, color, pattern, and size indicated. Extra stock shall
be from the same production run as installed materials.
2. Grout: Furnish quantity of grout equal to 3 percent of amount installed for each type,
composition, and color indicated.
A. ANSI Ceramic Tile Standard: Provide tile that complies with ANSI A137.1, "Specifications for
Ceramic Tile," for types, compositions, and other characteristics indicated.
1. Provide tile complying with Standard grade requirements, unless otherwise indicated.
2. Provide Vitreous type tile complying with ASTM C373-88 for water absorption in Food
Processing areas, whether new or to match or replace existing tiles.
B. ANSI Standards for Tile Installation Materials: Provide materials complying with ANSI A108.02,
ANSI standards referenced in other Part 2 articles, ANSI standards referenced by TCA
installation methods specified in tile installation schedules, and other requirements specified.
C. Factory Blending: For tile exhibiting color variations within ranges selected during Sample
submittals, blend tile in factory and package so tile units taken from one package show same
range in colors as those taken from other packages and match approved Samples.
D. Mounting: For factory-mounted tile, provide back- or edge-mounted tile assemblies as standard
with manufacturer, unless otherwise indicated.
1. Where tile is indicated for installation in food processing areas, do not use back- or edge-
mounted tile assemblies unless tile manufacturer specifies in writing that this type of
mounting is suitable for installation indicated and has a record of successful in-service
performance.
E. Factory-Applied Temporary Protective Coating: Where indicated under tile type, protect
exposed surfaces of tile against adherence of mortar and grout by precoating with continuous
film of petroleum paraffin wax, applied hot. Do not coat unexposed tile surfaces.
F. Colors, Textures, and Patterns: Where manufacturer's standard products are indicated for tile,
grout, and other products requiring selection of colors, surface textures, patterns, and other
appearance characteristics, provide specific products or materials complying with the following
requirements:
2.2 MANUFACTURERS
a. External Corners: Surface bullnose, module size 4-1/4 by 4-1/4 inches No. S-
4449.
b. Internal Corners: Surface coved internal angle, module size 4-1/4 by 4-1/4 inches,
No. A-3401.
c. Base: Sanitary cove:
1) Square top unless otherwise indicated, module size 4-1/4 by 4-1/4 inches,
No. A-3401.
2) Internal corners: Field-butted square corners except with coved base
designed to fit with stretcher shapes, module size 4-1/4 by 4-1/4 inches, No.
A-3401.
3) External corners: Unless otherwise indicated, surface bullnose, square top,
module size 4-1/4 by 4-1/4 inches, No. SCR-L-3401.
a. Base: Coved.
b. Bullnose top, size 8 by 6 inches, No. S-3689T.
c. Internal corners: Bullnose top designed to fit with stretcher shapes, No. SB-3689T.
d. External corners: Bullnose top designed to fit with stretcher shapes, No. SC-
3689T.
A. Fabricate to sizes and profiles indicated or required to provide transition between adjacent floor
finishes.
1. Bevel edges at 1:2 slope, aligning lower edge of bevel with adjacent floor finish. Limit
height of bevel to 1/2 inch or less, and finish bevel to match face of threshold.
B. Marble Thresholds: ASTM C 503 with a minimum abrasion resistance of 10 per ASTM C 1353
or ASTM C 241 and with honed finish.
1. Polymer Type: Acrylic resin or styrene-butadiene rubber in liquid-latex form for addition
to prepackaged dry-grout mix.
a. Unsanded grout mixture for joints 1/8 inch and narrower. Color as indicated.
b. Sanded grout mixture for joints 1/8 inch and wider. Color as indicated.
A. General: Provide sealants, primers, backer rods, and other sealant accessories that comply
with the following requirements and with the applicable requirements in Division 07 Section
Joint Sealants.
1. Use sealants that have a VOC content of 250 g/L or less when calculated according to
40 CFR 59, Subpart D (EPA Method 24).
2. Use primers, backer rods, and sealant accessories recommended by sealant
manufacturer.
B. Temporary Protective Coating: Either product indicated below that is formulated to protect
exposed surfaces of tile against adherence of mortar and grout; compatible with tile, mortar, and
grout products; and easily removable after grouting is completed without damaging grout or tile.
1. Petroleum paraffin wax, fully refined and odorless, containing at least 0.5 percent oil with
a melting point of 120 to 140 deg F per ASTM D 87.
2. Grout release in form of manufacturer's standard proprietary liquid coating that is
specially formulated and recommended for use as temporary protective coating for tile.
C. Tile Cleaner: A neutral cleaner capable of removing soil and residue without harming tile and
grout surfaces, specifically approved for materials and installations indicated by tile and grout
manufacturers.
D. Metal Edge Strips: Angle or L-shape, height to match tile and setting-bed thickness, metallic or
combination of metal and PVC or neoprene base, designed specifically for flooring applications;
stainless-steel, ASTM A 666, 300 Series exposed-edge material.
E. Grout Sealer: Manufacturer's standard[ silicone] product for sealing grout joints and that does
not change color or appearance of grout.
A. Mix mortars and grouts to comply with referenced standards and mortar and grout
manufacturers' written instructions.
C. Obtain and use type of mixing equipment, mixer speeds, mixing containers, mixing time, and
other procedures to produce mortars and grouts of uniform quality with optimum performance
characteristics for installations indicated.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions where tile will be installed, with Installer present, for
compliance with requirements for installation tolerances and other conditions affecting
performance of installed tile.
1. Verify that substrates for setting tile are firm, dry, clean, free of coatings that are
incompatible with tile-setting materials including curing compounds and other substances
a. Verify that surfaces that received a steel trowel finish have been mechanically
scarified.
b. Verify that protrusions, bumps, and ridges have been removed by sanding or
grinding.
3. Verify that installation of grounds, anchors, recessed frames, electrical and mechanical
units of work, and similar items located in or behind tile has been completed before
installing tile.
4. Verify that joints and cracks in tile substrates are coordinated with tile joint locations; if
not coordinated, adjust joint locations in consultation with Contracting Officer.
3.2 PREPARATION
A. Fill cracks, holes, and depressions in concrete substrates for tile floors installed with adhesives
or thin-set mortar with trowelable leveling and patching compound specifically recommended by
tile-setting material manufacturer.
B. Blending: For tile exhibiting color variations within ranges selected during Sample submittals,
verify that tile has been factory blended and packaged so tile units taken from one package
show same range of colors as those taken from other packages and match approved Samples.
If not factory blended, either return to manufacturer or blend tiles at Project site before installing.
C. Field-Applied Temporary Protective Coating: Where indicated under tile type or needed to
prevent grout from staining or adhering to exposed tile surfaces, precoat them with continuous
film of temporary protective coating, taking care not to coat unexposed tile surfaces.
A. Comply with TCA's "Handbook for Ceramic Tile Installation" for TCA installation methods
specified in tile installation schedules. Comply with parts of the ANSI A108 Series
"Specifications for Installation of Ceramic Tile" that are referenced in TCA installation methods,
specified in tile installation schedules, and apply to types of setting and grouting materials used.
1. For the following installations, follow procedures in the ANSI A108 Series of tile
installation standards for providing 95 percent mortar coverage:
B. Extend tile work into recesses and under or behind equipment and fixtures to form complete
covering without interruptions, unless otherwise indicated. Terminate work neatly at
obstructions, edges, and corners without disrupting pattern or joint alignments.
D. Jointing Pattern: Lay tile in grid pattern, unless otherwise indicated. Lay out tile work and
center tile fields in both directions in each space or on each wall area. Adjust to minimize tile
cutting and the use of pieces that are less than half of a tile. Provide uniform joint widths,
unless otherwise indicated.
1. For tile mounted in sheets, make joints between tile sheets same width as joints within
tile sheets so joints between sheets are not apparent in finished work.
2. Where adjoining tiles on floor, base, walls, or trim are specified or indicated to be same
size, align joints.
3. Where tiles are specified or indicated to be whole integer multiples of adjoining tiles on
loor, base, walls, or trim, align joints unless otherwise indicated.
E. Joint Widths: Unless otherwise indicated, install tile with the following joint widths:
F. Expansion Joints: Provide expansion joints and other sealant-filled joints, including control,
contraction, and isolation joints, where indicated. Form joints during installation of setting
materials, mortar beds, and tile. Do not saw-cut joints after installing tiles.
1. Where joints occur in concrete substrates, locate joints in tile surfaces directly above
them.
2. Prepare joints and apply sealants to comply with requirements in Division 07 Section
"Joint Sealants."
3. Indicate expansion joints and other sealant filled joints at perimeter of floor tiles where
abutting walls and columns, including control, contraction, and isolation joints, on
Drawings.
G. Lay out tile wainscots to dimensions indicated or to next full tile beyond dimensions indicated.
H. Stone Thresholds: Install stone thresholds at locations indicated, in same type of setting bed as
adjacent floor unless otherwise indicated.
1. Set thresholds in latex-portland cement mortar (thin set) for locations where mortar bed
would otherwise be exposed above adjacent nontile floor finish.
I. Metal Edge Strips: Install [at locations indicated] [where exposed edge of tile flooring meets
carpet, wood, or other flooring that finishes flush with top of tile] [where exposed edge of tile
flooring meets carpet, wood, or other flooring that finishes flush with or below top of tile and no
threshold is indicated].
K. Grouting Standards: Grout tile to comply with requirements of the following tile installation
standards:
1. For ceramic tile grouts (latex-portland cement grouts), comply with ANSI A108.10.
A. Cleaning: On completion of placement and grouting, clean all ceramic tile surfaces so they are
free of foreign matter.
B. Protect installed tile work with kraft paper or other heavy covering during construction period to
prevent staining, damage, and wear. If recommended by tile manufacturer, apply coat of
neutral protective cleaner to completed tile walls and floors.
C. Prohibit foot and wheel traffic from tiled floors for at least seven days after grouting is
completed.
D. Before final inspection, remove protective coverings and rinse neutral protective cleaner from
tile surfaces.
1. Tile Installation F113: Thin-set mortar; TCA F113 and ANSI A108.5.
1. Tile Installation W243: Thin-set mortar on gypsum board; TCA W243 and ANSI A108.5.
2. Tile Type: Glazed wall tile.
3. Thin-Set Mortar: Latex- portland cement mortar.
4. Grout: Polymer-modified unsanded grout. Color as indicated.
DESIGN CRITERIA
1. Related Sections: See related Division 9 Design Criteria and Commissary Standard Room and
Finish Schedule in Appendix "A."
2. This Section specifies acoustical panels and exposed metal suspension systems for ceilings.
3. The DeCA standard for customer areas with ceilings is 24" by 24", white, tegular edge, acoustical
ceiling panels. The specifications indicate a panel manufactured with built-in humidity guard to resist
panel warping and an anti-bacterial coating to resist mold growth (both common problems in
commissary facilities).
4. Provide a detail on contract drawings indicating proper suspension of ceiling system. Verify that
Contract Drawings do not graphically show or indicate ceiling hangers suspended from steel roof
deck or utilities (i.e., ductwork, sprinkler piping, conduits, etc.). Splayed hanger wires shall have offset
splayed wires.
5. Design Considerations:
A. In accordance with the IBC all projects are assigned to a Seismic Design Category. Where
required by project location, add applicable requirements of the IBC and referenced codes and
standards.
B. Overhead mounted architectural features shall be designed for security protection in accordance
with UFC 4-010-01 DoD Minimum Antiterrorism Standards For Buildings, October 08, 2003
(including change 1, dated 22 January 2007), Standard 15, as follows:
1. Indicate overhead mounted features weighing 14 kilograms (31 pounds) or more (excluding
distributed systems such as suspended ceilings that collectively exceed that weight) are
mounted to minimize the likelihood that they will fall and injure building occupants.
2. Mount such systems so they resist forces of 0.5 times the component weight in any
horizontal direction and 1.5 times the component weight in the downward direction.
3. This requirement shall not preclude the need to design architectural feature mountings for
forces required by other criteria such as seismic requirements.
END OF SECTION
June 2011 09 51 00 1
SECTION 09 51 00
ACOUSTICAL CEILINGS
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. Seismic Performance:
1. Acoustical ceiling system shall withstand the effects of earthquake motions determined
according to ASCE/SEI 7-05, Chapter 13 as referenced by the International Building
Code (IBC), Chapter 16. Specific seismic requirements for suspended ceiling are
indicated in ASCE section 13.5.6.
B. Delegated Design:
a. Refer to Division 1 Section "Description of Work" for seismic design load data.
1.3 SUBMITTALS
A. Product Data:
1. Product Data for Credit MR 4: For products having recycled content, documentation
indicating percentages by weight of postconsumer and preconsumer recycled content.
Include statement indicating costs for each product having recycled content.
2. Product Data for Credit EQ 4.1: For sealants, documentation including printed statement
of VOC content.
3. Laboratory Test Reports for Credit EQ 4: For [ceiling systems] [and] [sealants],
documentation indicating that products comply with the testing and product requirements
of the California Department of Health Services' "Standard Practice for the Testing of
Volatile Organic Emissions from Various Sources Using Small-Scale Environmental
Chambers."
C. Delegated-Design Submittal:
1. For design of acoustical ceiling system withstanding the effects of earthquake motions.
E. Qualification Data:
1. For each acoustical panel ceiling, for tests performed by a qualified testing agency.
G. Evaluation Reports:
1. For each acoustical panel ceiling suspension system[ and anchor and fastener type],
from ICC-ES.
I. Submittal List:
A. Installer Qualifications:
1. Engage an experienced Installer who has completed acoustical panel ceilings similar in
material, design, and extent to that indicated for this Project and with a record of
successful in-service performance.
1. Obtain acoustical ceiling panel and suspension system from a single source with
resources to provide products of consistent quality in appearance and physical properties
without delaying the Work.
C. Fire-Test-Response Characteristics:
1. Provide acoustical panel ceilings that comply with the following requirements:
D. Seismic Standard:
1. Provide acoustical panel ceilings designed and installed to withstand the effects of
earthquake motions indicated in Division 01 Section Summary of Work, according to
ASCE 7-05, "Minimum Design Loads for Buildings and Other Structures," Section 13,
"Seismic Design Requirements for Nonstructural Components."
A. Deliver acoustical panels and suspension system components to Project site in original,
unopened packages and store them in a fully enclosed space where they will be protected
against damage from moisture, direct sunlight, surface contamination, and other causes. Before
installing acoustical panels, permit them to reach room temperature and a stabilized moisture
content. Handle acoustical panels carefully to avoid chipping edges or damaging units in any
way.
A. Space Enclosure and Environmental Limitations: Do not install acoustical panel ceilings until
spaces are enclosed and weatherproof, wet-work in spaces is completed and dry, ambient
temperature and humidity conditions are being maintained at the levels indicated for Project
when occupied for its intended use, and work above ceilings is complete and accepted by
Government.
1.7 COORDINATION
A. Coordinate layout and installation of acoustical panels and suspension system components with
other construction that penetrates ceilings or is supported by them, including light fixtures,
HVAC equipment, fire-suppression system components (if any), and partition assemblies (if
any).
A. General:
1. Furnish extra materials described below that match products installed and that are
packaged with protective covering for storage and identified with labels describing
contents.
D. Seismic Clips:
A. General Warranty:
1. The special warranties specified in this Article shall not deprive the Government of other
rights the Government may have under other provisions of the Contract Documents and
shall be in addition to, and run concurrent with, other warranties made by the Contractor
under requirements of the Contract Documents.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Provide panels complying with ASTM E 1264 and Basis-Of-Design Product for
characteristics described below:
c. Colors: White.
d. NRC (Noise Reduction Coefficient): 0.55.
e. CAC (Ceiling Attenuation Class): 35.
f. LR (Light Reflectance): 0,85.
g. Edge/Joint Detail: Angled Tegular for interface with basis-of-design exposed tee
grid system.
h. Thickness: 5/8 inch.
i. Modular Size: 24- by 24-inches.
j. Sag resistant.
k. Broad Spectrum Antimicrobial Fungicide and Bactericide Treatment: Provide
acoustical panels treated, on surface and back of panels, with manufacturer's
standard antimicrobial formulation that inhibits fungus, mold, mildew, and gram-
positive and gram-negative bacteria and showing no mold, mildew, or bacterial
growth when tested according to ASTM D 3273.
B. Basis-of-Design Product:
B. Attachment Devices:
1. Size for five times design load indicated in ASTM C 635, Table 1, Direct Hung unless
otherwise indicated. Comply with seismic design requirements.
a. Zinc-Coated, Carbon-Steel Wire: ASTM A 641, Class 1 zinc coating, soft temper.
b. Size: Select wire diameter so its stress at three times hanger design load (ASTM
C 635, Table 1, Direct-Hung), will be less than yield stress of wire, but provide not
less than 0.106-inch diameter wire.
1. Main and cross-runners roll-formed from commercial-quality hot dipped galvanized steel
coating. Exposed surfaces chemically cleansed, capping prefinished galvanized steel in
baked polyester. 15/16-inch wide metal caps on flanges; other characteristics as follows:
B. Basis-of-Design Product:
A. Roll-Formed, Sheet-Metal Edge Moldings and Trim: Type and profile indicated or, if not
indicated, manufacturer's standard moldings for edges and penetrations that comply with
seismic design requirements; formed from sheet metal of same material, finish, and color as
that used for exposed flanges of suspension-system runners.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and structural framing to which acoustical panel ceilings attach or abut, with
Installer present, for compliance with requirements specified in this and other Sections that
affect ceiling installation and anchorage. Do not proceed with installation until unsatisfactory
conditions have been corrected.
3.2 PREPARATION
A. Measure each ceiling area and establish the layout of acoustical panels to balance border
widths at opposite edges of each ceiling. Avoid using less-than-half-width panels at borders,
and conform to the layout shown on reflected ceiling plans.
3.3 INSTALLATION
A. General:
1. Install acoustical panel ceilings to comply with publications referenced below and per
manufacturer's written instructions.
a. Standard for Ceiling Suspension System Installations: Comply with ASTM C 636
and seismic design requirements indicated[, according to CISCA's "Ceiling
Systems Handbook."][.].
a. Install hangers plumb and free from contact with insulation or other objects within
ceiling plenum that are not part of the supporting structure or of the ceiling
suspension system.
b. Splay hangers only where required to miss obstructions; offset resulting horizontal
forces by bracing, countersplaying, or other equally effective means.
c. Where width of ducts and other construction within ceiling plenum produces
hanger spacings that interfere with the location of hangers at spacings required to
support standard suspension system members, install supplemental suspension
members and hangers in the form of trapezes or equivalent devices. Size
supplemental suspension members and hangers to support ceiling loads within
performance limits established by referenced standards and publications.
d. Secure wire hangers to ceiling suspension members and to supports above with a
minimum of three tight turns. Connect hangers either directly to structures or to
3. Install edge moldings and trim of type indicated at perimeter of acoustical ceiling area
and where necessary to conceal edges of acoustical panels.
a. Attach moldings to substrate with screws at intervals not over 16 inches o.c. and
not more than 3 inches from ends, leveling with ceiling suspension system to a
tolerance of 1/8 inch in 12 feet. Miter corners accurately and connect securely.
4. Install suspension system runners so they are square and securely interlocked with one
another. Remove and replace dented, bent, or kinked members.
5. Install acoustical panels with undamaged edges and fitted accurately into suspension
system runners and edge moldings. Scribe and cut panels at borders and penetrations
to provide neat, precise fit.
a. For reveal-edged panels on suspension system runners, install panels with bottom
of reveal in firm contact with top surface of runner flanges.
b. Paint the cut panel edges remaining exposed after installation; match color of
exposed panel surfaces using coating recommended for this purpose by acoustical
panel manufacturer.
B. Special Inspections:
C. Defective Work:
1. Acoustical panel ceiling hangers, anchors, and fasteners will be considered defective if
they do not pass inspections.
3.5 CLEANING
A. Clean exposed surfaces of acoustical panel ceilings, including trim, edge moldings, and
suspension system members. Comply with manufacturer's instructions for cleaning and
touchup of minor finish damage. Remove and replace ceiling components that cannot be
successfully cleaned and repaired to permanently eliminate evidence of damage.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 03 Section Cast-In-Place Concrete and Cast-In-Place Concrete
Design Criteria for slab finishes in spaces to receive resilient floor tile and for vapor retarder and
granular base below slabs-on-grade.
2. This Section specifies vinyl composition tile (VCT), and resilient wall base and accessories typically
installed with resilient floor tile. This Section also specifies accessories typically installed with
carpets.
3. Resilient floor tile is required in administrative office areas, training rooms, and break rooms as
indicated in Appendix "B" Standard Commissary Room and Finish Schedule. On projects where
resilient floor tile is required in sales and other customer areas, extend tile completely under checkout
counters, shelving, and display cases.
4. Graphically indicate all floor finish transitions on drawings. Transitions should occur beneath doors
when in the closed position, and other locations as indicated on Drawings.
5. Where resilient flooring terminates at corridors leading to Staging and Receiving Areas, extend tile 3-
0 into corridor. Indicate transition strips fabricated of solid stainless steel 2" x 1/4" bars with tapered
edges and secured to floor with countersunk fasteners. Do not use resilient edge strips.
END OF SECTION
June 2011 09 65 19 1
SECTION 09 65 19
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 SUBMITTALS
B. LEED Submittals:
1. Product Data for Credit EQ 4.1: For [adhesives] [sealants] [and] [chemical-bonding
compounds], including printed statement of VOC content.
1. Full-size units of each color and pattern of resilient floor tile required.
2. Resilient Wall Base and Accessories: Manufacturer's standard-size Samples, but not
less than 12 inches long, of each resilient product color and pattern required.
D. Maintenance Data: For each type of floor tile to include in maintenance manuals.
A. Installer Qualifications: A qualified installer who employs workers for this Project who are
competent in techniques required by manufacturer for floor tile installation indicate.
A. Store resilient products and installation materials in dry spaces protected from the weather, with
ambient temperatures maintained within range recommended by manufacturer, but not less
than 50 deg F or more than 90 deg F. Store tiles on flat surfaces.
A. Maintain temperatures within range recommended by manufacturer, but not less than 70 deg F
or more than 95 deg F, in spaces to receive floor tile during the following time periods:
E. Install resilient products after other finishing operations, including painting, have been
completed.
A. Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents. Furnish extra
materials from the same production run as installed materials.
1. Furnish not less than one percent of each type, color, pattern, class, wearing surface,
and size of resilient tile flooring, accessory, and wall base installed.
PART 2 - PRODUCTS
B. Basis-of-Design Product:
2.2 RESILIENT WALL BASE (RB) Coordinate below with Drawings and Interior Finishes Legend.
B. Basis-of-Design Product:
I. Finish: Smooth.
1. Johnsonite.
2. Roppe Corporation, USA.
3. VPI, LLC; Floor Products Division.
1. Description: Carpet edge and joiner for tile and carpet for glue-down applications.
2. Material: Extruded or molded heavy-duty vinyl.
3. Profile and Dimensions: Provide moldings with undercut appropriate for carpet thickness.
2 inches wide, minimum, anchorage flange.
4. Provide edge, transition, and other flooring accessory materials that comply with
accessibility requirements of authorities having jurisdiction.
5. Color: To coordinate with carpet.
1. Material Requirement:
a. Rubber: Composition A.
b. Vinyl: Composition B.
C. Nosing Height: 1-1/2 inches.Thickness: 1/4 inch and tapered to back edge.
E. Size: Lengths and depths to fit each stair tread in one piece one or, for treads exceeding
maximum lengths manufactured, in equal-length units.
A. Basis-of-Design Products: Provide either the named products or products provided or approved
by resilient tile flooring manufacturer for applications indicated.
B. Concrete Sealer:
C. Concrete Primer:
E. Adhesives (Cements):
1. Basis-of-Design Product: The W.W. Henry Company, Henry 530 TilePro High-
Performance "Fast Tack" Adhesive.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, with Installer present, for compliance with requirements for maximum
moisture content and other conditions affecting performance of the Work.
B. Verify that finishes of substrates comply with tolerances and other requirements specified in
other Sections and that substrates are free of cracks, ridges, depressions, scale, and foreign
deposits that might interfere with adhesion of floor tile.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
B. Concrete Substrates for Resilient Stair Nosings and Accessories. Prepare according to ASTM
F 710.
C. Concrete Sealing:
a. Contract completion time will not be extended due to time interval between sealer
application and flooring installation.
1. Use trowelable leveling and patching compound to fill cracks, holes, and depressions in
substrates.
a. Fill and smooth surface cracks, grooves, depressions, control joints and other non-
moving joints, and other irregularities with latex patching or underlayment
compound recommended by the resilient flooring manufacturer.
E. Material Preconditioning:
1. Move resilient products and installation materials into spaces where they will be installed
at least 48 hours in advance of installation.
2. Do not install resilient products until they are same temperature as space where they are
to be installed.
F. Substrate Preparation:
C. Match tiles for color and pattern by selecting tiles from cartons in the same sequence as
manufactured and packaged, if so numbered. Discard broken, cracked, chipped, or deformed
tiles.
1. Lay tiles with grain running in one direction, in pattern of colors and sizes indicated, and
with joints in straight line.
D. Scribe, cut, and fit tiles to butt neatly and tightly to vertical surfaces and permanent fixtures
including built-in furniture, cabinets, pipes, outlets, edgings, door frames, thresholds, and
nosings.
1. Where a visible gap occurs between joints of vertical surfaces and edge of resilient
flooring, install clear elastomeric joint sealant ES-3 as specified in Division 07 Section
Joint Sealants to form a waterproof seal.
E. Extend tiles into toe spaces, door reveals, closets, and similar openings, except in Sales Areas;
Extend flooring completely under checkstands, shelving, and display cases.
1. Install stair nosing where tile terminates at trench edge under display cases.
F. Maintain reference markers, holes, and openings that are in place or marked for future cutting
by repeating on floor tiles as marked on substrates. Use chalk or other nonpermanent,
nonstaining marking device.
G. Install tiles on covers for telephone and electrical ducts and similar items in finished floor areas.
Maintain overall continuity of color and pattern with pieces of tile installed on covers. Tightly
adhere tile edges to substrates that abut covers and to cover perimeters.
H. Adhere tiles to flooring substrates using a full spread of adhesive applied to substrate to
produce a completed installation without open cracks, voids, raising and puckering at joints,
telegraphing of adhesive spreader marks, and other surface imperfections.
I. Hand roll tiles immediately after installation according to tile manufacturer's written instructions,
except if rolling is not required for products specified.
B. Apply resilient base to walls, columns, pilasters, casework and cabinets in toe spaces, and
other permanent fixtures in rooms and areas where base is required.
D. Tightly adhere resilient base to substrate throughout length of each piece, with base in
continuous contact with horizontal and vertical substrates.
F. On masonry surfaces or other similar irregular substrates, fill voids along top edge of resilient
base with manufacturer's recommended adhesive filler material.
1. Use stair-tread-nose filler to fill nosing substrates that do not conform to tread contours.
2. Tightly adhere to substrates throughout length of each piece.
C. Resilient Molding Accessories: Butt to adjacent materials and tightly adhere to substrates
throughout length of each piece. Install reducer strips at edges of carpet, resilient floor covering
that would otherwise be exposed.
D. Install expansion joint insert strip in isolation joints around columns in slabs on grade to allow
movement of tile below cap and keep tile from cracking; miter corners.
A. Install transition edge strips at edges of flooring as indicated. Anchor edge strips with No. 10 or
larger flat head, countersunk, machine screws (MS) at spacings not to exceed 12 inches. Use
lead shield for anchoring to concrete.
A. Comply with manufacturer's written instructions for cleaning and protection of resilient products.
B. Perform the following operations immediately after completing resilient product installation:
D. Floor Polish: Remove soil, visible adhesive, and surface blemishes from resilient stair treads
before applying liquid floor polish.
E. Cover products installed on horizontal surfaces with undyed, untreated building paper until final
acceptance. Coordinate with manufacturers' written recommendations for products used.
F. F. Do not move heavy and sharp objects directly over surfaces. Place hardboard or plywood
panels over flooring and under objects while they are being moved. Slide or roll objects over
panels without moving panels.
1. When required by flooring manufacturer, allow a minimum of 72 hours after resilient tile
installation before moving and installing equipment on flooring.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 03 Section Cast-In-Place Concrete and Cast-In-Place Concrete
Design Criteria for concrete substrates to receive resinous flooring.
2. Resinous flooring systems are required in food processing areas, both refrigerated and non-
refrigerated, as indicated in Appendix "A" Standard Commissary Room and Finish Schedule.
3. This Section specifies two types of trowel applied resinous flooring systems.
1. This system is used in refrigerated food preparation and storage areas. Resinous floors in
these areas are subject to thermal shock from daily cleaning of room. The refrigerated
spaces, with maintained temperatures of 50 degrees, are washed down with 140 degrees
water and then immediately returned to normal operating temperature. Resinous floor color
is "Brick Red", with "Light Texture" finish.
1. This system is used in non-refrigerated food preparation areas (Bakery / Deli). Resinous
floor color is "Beechwood", with "Texture #2" finish.
4. Specifications require that concrete surfaces receiving resinous flooring be shot-blasted, with an
apparatus that abrades the concrete surface, prior to application.
5. Concrete surfaces must be uniform and free of curing and sealing compounds, underlayments,
leveling compounds, or other substances capable of impairing resinous flooring bond.
6. Crack Control:
A. Where RES-1 flooring is installed, saw cut resinous flooring where substrate joints occur and
apply joint sealant.
B. Where RES-2 flooring is installed, apply crack and joint membrane at substrate joints to bridge
non-moving joints with resinous flooring. At substrate isolation joints subject to movement, saw
cut resinous flooring and apply joint sealant.
END OF SECTION
June 2011 09 67 23 1
SECTION 09 67 23
RESINOUS FLOORING
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. Unit Price: Provide a unit price per square foot, with initial bid, for osmotic resistant grout
application in the event concrete floor slab moisture tests indicate the need for same.
B. Procedures:
1. Unit price includes all necessary material, plus cost for delivery, installation, insurance,
applicable taxes, overhead, and profit.
1.3 SUBMITTALS
A. Product Data: For each type of product specified. Include manufacturer's technical data,
installation instructions, and recommendations for each resinous flooring component required.
B. LEED Submittals:
1. Product Data for Credit IEQ 4.2: For liquid-applied flooring components, documentation
including printed statement of VOC content.
2. Laboratory Test Reports for Credit IEQ 4: For flooring systems, documentation indicating
that products comply with the testing and product requirements of the California
Department of Health Services' "Standard Practice for the Testing of Volatile Organic
Emissions from Various Sources Using Small-Scale Environmental Chambers."
C. Samples for Verification: Of each resinous flooring system required, 6 inches square, applied
by Installer for this Project to a rigid backing, in color, texture, and finish indicated. Where
finishes involve normal color and texture variations, include Sample sets showing the full range
of variations expected.
D. Submittal List:
A. Installer Qualifications:
B. Source Limitations: Obtain primary resinous flooring materials, including primers, resins,
hardening agents, and sealing or finish coats, through one source from a single manufacturer.
Provide secondary materials including patching and fill material, joint sealant, and repair
materials from manufacturer of primary materials.
1. Review methods and procedures related to resinous flooring including, but not limited to,
the following:
1. Critical Radiant Flux Classification: Class I, not less than 0.45 W/sq. cm.
A. Delivery: Deliver materials in original packages and containers, with seals unbroken, bearing
manufacturer's labels indicating brand name and directions for storage and mixing with other
components.
A. Environmental Limitations: Comply with resinous flooring manufacturer's written instructions for
substrate temperature, ambient temperature, moisture, ventilation, and other conditions
affecting resinous flooring installation.
B. Lighting: Provide permanent lighting or, if permanent lighting is not in place, simulate
permanent lighting conditions during resinous flooring installation.
1. Provide side lighting focused horizontally across work area during installation to aid
installers in eliminating trowel marks.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
2.2 MATERIALS
A. VOC Content of Resinous Flooring: Provide resinous flooring systems, for use inside the
weatherproofing system, that comply with the following limits for VOC content when calculated
according to 40 CFR 59, Subpart D (EPA Method 24):
A. Resinous Flooring: RES-1 - Chemical and Thermal-Shock Resistant Urethane Mortar Resinous
Flooring consisting of a high performance, four-component polyurethane mortar system
including urethane-urea binder, pigments, powders and quartz aggregates; sealant and seal
coats. Comply with requirements indicated in the Resinous Flooring Schedule located at end of
this Section.
8. Cure Rate allow (at 77 deg F): 6 hours for foot traffic, 24 hours for normal operations.
9. System Chemical Resistance: As indicated by system designation and components
indicated above.
B. RES-2 - Trowel-Applied Epoxy Mortar Resinous flooring includes penetrating, moisture tolerant,
two-component epoxy primer, a high performance, three-component mortar consisting of epoxy
resin, curing agent and selected, graded aggregates blended with inorganic pigments and a
two-component, chemical resistant, epoxy coating. Comply with requirements indicated in the
Resinous Flooring Schedule located at end of this Section.
2. Color: Beechwood.
3. Total Thickness of Body Coat(s): 1/4 inch.
4. Wearing Surface: Texture #2 finish.
5. Base: 4-inch- high integral cove base.
6. Physical Properties: Provide resinous flooring system with the following minimum
physical property requirements when tested according to standard test methods
indicated:
2.4 ACCESSORIES
A. Crack and Joint Isolation Membrane: Manufacturer's recommended flexible resin formulation
for crack isolation to help prevent substrate cracks from reflecting through RES-2 trowel-applied
epoxy mortar flooring system.
C. Patching and Fill Material: Resinous product manufactured by resinous flooring manufacturer
and recommended by manufacturer for application indicated.
D. Joint Sealant: Type manufactured by resinous flooring manufacturer for type of service and
joint condition indicated. Match resinous flooring color.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and areas, with Installer present, for compliance with requirements for
installation tolerances and other conditions affecting performance of resinous flooring. Do not
proceed with installation until unsatisfactory conditions, including levelness tolerances, have
been corrected.
A. General: Prepare and clean substrate according to resinous flooring manufacturer's written
instructions for substrate indicated. Provide clean, dry, and neutral Ph substrate for resinous
flooring application.
1. At the juncture of resinous flooring with other floor finishes, saw cut and chase concrete
as indicated on drawings for a flush transition of flooring surfaces.
B. Concrete Substrates: Provide sound concrete surfaces free of laitance, glaze, efflorescence,
curing compounds, form-release agents, dust, dirt, grease, oil, and other contaminates
incompatible with resinous flooring.
4. Verify that concrete substrates have neutral Ph and that resinous flooring will adhere to
them. Perform tests recommended by manufacturer. Proceed with application only after
substrates pass testing.
5. Where RES-1 flooring is installed, saw cut resinous flooring where substrate joints occur
and apply joint sealant according to manufacturer's written recommendations.
6. Where RES-2 flooring is installed apply crack and joint membrane at substrate joints to
bridge non-moving joints with resinous flooring. At substrate isolation joints subject to
movement, saw cut resinous flooring and apply joint sealant according to manufacturer's
written recommendations.
8. For both RES-1 and RES-2 locations: Apply osmotic resistant grout over areas indicated
to receive resinous flooring, bridging all joints except isolation joints. At substrate
isolation joints, saw cut resinous flooring and apply joint sealant to comply with
manufacturer's written recommendations.
A. Protection: Protect resinous flooring from damage and wear during the remainder of
construction period. Use protective methods and materials, including temporary covering,
recommended in writing by resinous flooring manufacturer.
B. Cleaning: Clean resinous flooring not more than 4 days before dates scheduled for inspections
intended to establish date of final acceptance in each Project area. Use cleaning materials and
procedures recommended in writing by resinous flooring manufacturer.
END OF SECTION
WALL COVERINGS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 SUBMITTALS
A. Product Data:
1. For each type of product indicated. Include data on physical characteristics, durability,
fade resistance, and flame-resistance characteristics.
B. LEED Submittals:
2. Product Data for Credit EQ 4.1: For adhesives, including printed statement of VOC
content.
3. Product Data for Credit EQ 4.2: For paints and coatings, including printed statement of
VOC content[ and chemical components].
1. Show location and extent of each wall-covering type. Indicate pattern placement, seams
and termination points.
D. Samples:
1. For each type of wall covering and for each color, texture, and pattern required.
2. Sample from same print run or dye lot to be used for the Work, with specified treatments
applied. Show complete pattern repeat. Mark top and face of fabric.
E. Submittal List:
A. Fire-Test-Response Characteristics:
1. Provide wall coverings and adhesives with the following fire-test-response characteristics
as determined by testing identical products applied with identical adhesives to substrates
per test method indicated below by UL or another testing and inspecting agency
acceptable to authorities having jurisdiction.
A. Environmental Limitations: Do not deliver or install wall coverings until spaces are enclosed
and weathertight, wet work in spaces is complete and dry, work above ceilings is complete, and
temporary HVAC system is operating and maintaining ambient temperature and humidity
conditions at occupancy levels during the remainder of the construction period.
B. Lighting: Do not install wall covering until a permanent level of lighting is provided on the
surfaces to receive wall covering.
C. Ventilation: Provide continuous ventilation during installation and for not less than the time
recommended by wall-covering manufacturer for full drying or curing.
A. Furnish extra materials that match products installed and that are packaged with protective
covering for storage and identified with labels describing contents.
1. Wall-Covering Materials: For each type, full-size units equal to 5 percent of amount
installed.
PART 2 - PRODUCTS
A. General:
1. Provide rolls of each type of wall covering from the same run number or dye lot.
2.2 ACCESSORIES
A. Adhesive.
B. Mildew-resistant, nonstaining, strippable adhesive, for use with specific wall covering and
substrate application, as recommended in writing by wall-covering manufacturer and with a
VOC content of 50 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA
Method 24).
C. Primer/Sealer:
D. Seam Tape:
3.1 EXAMINATION
A. Examine substrates and conditions, with Installer present, for compliance with requirements for
levelness, wall plumbness, maximum moisture content, and other conditions affecting
performance of the Work.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
B. Clean substrates of substances that could impair bond of wall covering, including dirt, oil,
grease, mold, mildew, and incompatible primers.
C. Prepare substrates to achieve a smooth, dry, clean, structurally sound surface free of flaking,
unsound coatings, cracks, and defects.
D. Check painted surfaces for pigment bleeding. Sand gloss, semigloss, and eggshell finish with
fine sandpaper.
E. Remove hardware and hardware accessories, electrical plates and covers, light fixture trims,
and similar items.
F. Acclimatize wall-covering materials by removing them from packaging in the installation areas
not less than 24 hours before installation.
3.3 INSTALLATION
B. Cut wall-covering strips in roll number sequence. Change roll numbers at partition breaks and
corners.
E. Install wall covering with no gaps or overlaps, no lifted or curling edges, and no visible
shrinkage.
G. Install seams vertical and plumb at least 6 inches from outside corners and 6 inches from inside
corners unless a change of pattern or color exists at corner. No horizontal seams are permitted.
H. Fully bond wall covering to substrate. Remove air bubbles, wrinkles, blisters, and other defects.
I. Trim edges and seams for color uniformity, pattern match, and tight closure. Butt seams
without any overlay or spacing between strips.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 05 Sections for shop priming of metal substrates with primers; see
Division 08 Sections for factory priming hollow metal windows and doors with primers, see Division
08 Section Flush Wood Doors for factory applied stains and transparent finishes applied to interior
wood doors.
2. This Section specifies surface preparation and the application of standard paint systems on exterior
and interior substrates.
3. This Section specifies generic paint systems in accordance with MPI Architectural Painting
Specification Manual, (hereafter, MPI Manual) which categorizes coating systems by location
(exterior and interior) and by substrate.
4. Ensure products selected meet all federal, state, and local VOC requirements.
5. Select colors harmonizing with Commissary interior and interior dcor. Indicate on the drawings
colors from a major paint manufacturer as the basis of color selection.
6. Exterior and interior painting schedules are placed at the end of Part 3 of this Section and are
representative of typical Commissary finishes used, including level of gloss.
END OF SECTION
June 2011 09 90 00 1
SECTION 09 90 00
1.1 SUMMARY
A. Section Includes:
1. Surface preparation and the application of paint systems on the following substrates:
a. Exterior Painting:
1) Plaster substrates.
2) Steel substrates.
3) Galvanized-metal substrates.
b. Interior Painting:
2. Customer Area Exposed Structure: Where areas above the Sales Area are not otherwise
concealed by ceilings, soffits, or the like, apply dry-fall paint finishes indicated in the
"Room Finish and Color Schedule."
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for field applications of paints that are
inside the weatherproofing system.
2. Division 05 Sections for shop priming of metal substrates with primers specified in this
Section.
3. Division 08 Section Flush Wood Doors for stains and transparent finishes applied to
interior wood doors.
4. Division 08 Sections for factory priming hollow metal windows and doors with primers
specified in this Section.
1.2 SUBMITTALS
1. Product Data for Credit EQ 4.2: For paints and coatings, including printed statement of
VOC content.
2. Laboratory Test Reports for Credit EQ 4: For paints and coatings, documentation
indicating that they meet the testing and product requirements of the California
Department of Health Services' "Standard Practice for the Testing of Volatile Organic
Emissions from Various Sources Using Small-Scale Environmental Chambers."
C. Samples: For each finish and for each color and texture required.
1. Printout of current "MPI Approved Products List" for each product category specified in
Part 2, with the proposed product highlighted.
E. Submittal List:
A. MPI Standards:
1. Products: Complying with MPI standards indicated and listed in "MPI Approved Products
List."
2. Preparation and Workmanship: Comply with requirements in "MPI Architectural Painting
Specification Manual" for products and paint systems indicated.
A. A. Furnish extra materials, from the same product run, that match products installed and that are
packaged with protective covering for storage and identified with labels describing contents.
1. Paint: [5] <Insert number> percent, but not less than [1 gal.] <Insert number> of each
material and color applied.
A. Store materials not in use in tightly covered containers in well-ventilated areas with ambient
temperatures continuously maintained at not less than 45 deg F.
A. Apply paints only when temperature of surfaces to be painted and ambient air temperatures are
between 50 and 95 deg F.
B. Do not apply paints in snow, rain, fog, or mist; when relative humidity exceeds 85 percent; at
temperatures less than 5 deg F above the dew point; or to damp or wet surfaces.
PART 2 - PRODUCTS
2.1 MANUFACTURERS:
B. Products: Subject to compliance with requirements, [provide product] [provide one of the
products] [available products that may be incorporated into the Work include, but are not
limited to products] listed in other Part 2 articles for the paint category indicated.
A. MPI Standards: Provide products that comply with MPI standards indicated and that are listed
in its "MPI Approved Products List."
B. Material Compatibility:
1. Provide materials for use within each paint system that are compatible with one another
and substrates indicated, under conditions of service and application as demonstrated by
manufacturer, based on testing and field experience.
2. For each coat in a paint system, provide products recommended in writing by
manufacturers of topcoat for use in paint system and on substrate indicated.
C. VOC Content: Products shall comply with VOC limits of authorities having jurisdiction and, for
interior paints and coatings applied at Project site, the following VOC limits, exclusive of
D. Chemical Components of Field-Applied Interior Paints and Coatings: Provide products that
comply with the following chemical restrictions; these requirements do not apply to primers or
finishes that are applied in a fabrication or finishing shop:
1. Aromatic Compounds: Paints and coatings shall not contain more than 1.0 percent by
weight of total aromatic compounds (hydrocarbon compounds containing one or more
benzene rings).
2. Restricted Components: Paints and coatings shall not contain any of the following:
a. Acrolein.
b. Acrylonitrile.
c. Antimony.
d. Benzene.
e. Butyl benzyl phthalate.
f. Cadmium.
g. Di (2-ethylhexyl) phthalate.
h. Di-n-butyl phthalate.
i. Di-n-octyl phthalate.
j. 1,2-dichlorobenzene.
k. Diethyl phthalate.
l. Dimethyl phthalate.
m. Ethylbenzene.
n. Formaldehyde.
o. Hexavalent chromium.
p. Isophorone.
q. Lead.
r. Mercury.
s. Methyl ethyl ketone.
t. Methyl isobutyl ketone.
u. Methylene chloride.
v. Naphthalene.
w. Toluene (methylbenzene).
x. 1,1,1-trichloroethane.
y. Vinyl chloride.
1. Duron, Block Kote Latex Block Filler, 08-126: Applied at a dry film thickness of not less
than 10.2 mils.
1. Benjamin Moore; Super Spec Latex Vapor Barrier Primer Sealer 260.
1. Dry Fall Waterborne for Galvanized Steel, Flat: MPI #133. (Gloss Level 1).
G. Interior Stains:
1. Varnish, Interior, Oil-Modified, Clear Polyurethane Satin: MPI #57, (Gloss Level 4).
a. Sherwin-Williams Co. Setfast Fast Dry Acrylic Waterborne Traffic Marking Paint,
8.5 mils dft.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions, with Applicator present, for compliance with requirements
for maximum moisture content and other conditions affecting performance of work.
B. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter
as follows:
1. Wood: 15 percent.
2. Gypsum Board: 12 percent.
3. Concrete: 12 percent
4. Masonry (Clay and CMU): 12 percent.
5. Portland Cement Plaster: 12 percent.
C. Verify suitability of substrates, including surface conditions and compatibility with existing
finishes and primers.
D. Primer is not required on shop-primed items that are compatible with system subsequent
applied coats.
G. Exterior Gypsum Board Substrates: Verify that finishing compound is sanded smooth.
3.2 PREPARATION
B. Clean substrates of substances that could impair bond of paints, including dirt, oil, grease, and
incompatible paints and encapsulants.
1. Remove incompatible primers and reprime substrate with compatible primers as required
to produce paint systems indicated.
C. Remove hardware, covers, plates, and similar items already in place that are removable and
are not to be painted. If removal is impractical or impossible because of size or weight of item,
provide surface-applied protection before surface preparation and painting.
D. After completing painting operations, use workers skilled in the trades involved to reinstall items
that were removed. Remove surface-applied protection.
E. Concrete Substrates: Remove release agents, curing compounds, efflorescence, and chalk.
Do not paint surfaces if moisture content or alkalinity of surfaces to be painted exceeds that
permitted in manufacturer's written instructions.
F. Masonry Substrates: Remove efflorescence and chalk. Do not paint surfaces if moisture
content or alkalinity of surfaces or mortar joints exceeds that permitted in manufacturer's written
instructions.
G. Steel Substrates: Remove rust, loose mill scale, and shop primer if any. Clean using methods
recommended in writing by paint manufacturer[.] [ but not less than the following:]
H. Shop-Primed Steel Substrates: Clean field welds, bolted connections, and abraded areas of
shop paint, and paint exposed areas with the same material as used for shop priming to comply
with SSPC-PA 1 for touching up shop-primed surfaces.
I. Galvanized-Metal Substrates: Remove grease and oil residue from galvanized sheet metal by
mechanical methods to produce clean, lightly etched surfaces that promote adhesion of
subsequently applied paints.
1. Scrape and clean knots. Before applying primer, apply coat of knot sealer recommended
in writing by topcoat manufacturer for exterior use in paint system indicated.
2. Sand surfaces that will be exposed to view, and dust off.
3. Prime edges, ends, faces, undersides, and backsides of wood.
4. After priming, fill holes and imperfections in the finish surfaces with putty or plastic wood
filler. Sand smooth when dried.
K. Cotton or Canvas Insulation Covering Substrates: Remove dust, dirt, and other foreign material
that might impair bond of paints to substrates.
3.3 APPLICATION
1. Use applicators and techniques suited for paint and substrate indicated.
2. Paint surfaces behind movable items same as similar exposed surfaces. Before final
installation, paint surfaces behind permanently fixed items with prime coat only.
3. Paint both sides and edges of exterior doors and entire exposed surface of exterior door
frames.
B. Tint undercoats same color as topcoat, but tint each undercoat a lighter shade to facilitate
identification of each coat if multiple coats of same material are to be applied. Provide sufficient
difference in shade of undercoats to distinguish each separate coat.
C. If undercoats or other conditions show through topcoat, apply additional coats until cured film
has a uniform paint finish, color, and appearance.
D. Apply paints to produce surface films without cloudiness, spotting, holidays, laps, brush marks,
roller tracking, runs, sags, ropiness, or other surface imperfections. Cut in sharp lines and color
breaks.
1. Paint items exposed in customer areas including, but not limited to, the following:
a. Mechanical Work:
b. Electrical Work:
1) Switchgear.
2) Panelboards.
3) Conduit.
4) Cable trays.
A. At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from
Project site.
B. After completing paint application, clean spattered surfaces. Remove spattered paints by
washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces.
C. Protect work of other trades against damage from paint application. Correct damage to work of
other trades by cleaning, repairing, replacing, and refinishing, as approved by Architect, and
leave in an undamaged condition.
A. Steel Substrates:
B. Galvanized-Metal Substrates:
C. Plaster Substrates:
a. Block Filler: Concrete unit masonry block filler under vapor barrier finish.
b. Finish Coats: Latex Vapor Barrier Primer/Sealer.
1) Ceilings: Flat.
2) Walls and Soffits: Eggshell.
END OF SECTION
***********************************************************
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 DEFINITIONS
1.3 DESCRIPTION
1.4 RESPONSIBILITIES
1. Schedules.
2. Instructions for operation of each piece of equipment for emergencies.
3. Seasonal adjustment.
4. Instructions for energy savings operations and descriptions of the energy savings
strategies in the facility (from O&M Manuals).
C. Warranty Period:
PART 3 - EXECUTION
3.1 STARTUP
A. Contractors shall follow the start-up and initial checkout procedures listed in the Responsibilities
list in this Section and in Division 01 Section General Commissioning Requirements. Division
10 has start-up responsibility and is required to complete systems and sub-systems so they are
fully functional, meeting the design objectives of the Contract Documents. The commissioning
procedures and functional testing do not relieve or lessen this responsibility or shift that
responsibility partially to the Commissioning Agent, technical inspector, or Government.
B. Functional testing will generally begin upon completion of a system. Functional testing may
proceed prior to the completion of systems or sub-systems at the discretion of the CO.
Beginning system testing before full completion does not relieve the Contractor from fully
completing the system, including all prefunctional checklists.
A. The following O&M manual requirements are in addition to O&M manual documentation
requirements elsewhere in these specifications.
B. Division 10 shall compile and prepare documentation for all commissioned systems covered in
Division 10 and deliver this documentation to the GC for inclusion in the O&M manuals prior to
the training of Government personnel.
A. The GC shall be responsible for training coordination and scheduling to ensure that training is
completed.
B. The QC shall be responsible for reviewing the content and adequacy of the training of
Government personnel for commissioned equipment or systems. TI will verify compliance.
C. The Division 10 Contractor shall have the following training responsibilities for the
commissioned systems:
1. Provide the TI with a training plan four weeks before the planned training.
2. Provide designated Government personnel with comprehensive orientation and training
in the understanding of the systems and the operation and maintenance of each piece of
commissioned equipment.
3. Training shall start with classroom sessions followed by hands-on training on each piece
of equipment.
4. During any demonstration, should the system fail to perform in accordance with the
requirements of the O&M manual or sequence of operations, the system will be repaired
or adjusted as necessary and the demonstration repeated.
5. The appropriate trade or manufacturer's representative shall provide the instructions on
each major piece of equipment. This person may be the start-up technician for the piece
of equipment, the installing contractor or manufacturer's representative. Practical
8. Hands-on training shall include start-up, operation in all modes possible, including
manual, shut-down and any emergency procedures and preventative maintenance for all
pieces of equipment.
9. Training shall occur after functional testing is complete, unless approved otherwise by the
Contracting Officer.
10. Minimum Duration of Training. Contractor shall meet for 8 hours with facility staff after
completion of the work and instruct them as indicated above.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Design Standard Plates.
2. This Section includes markerboards and tack boards used in Commissary Training Rooms.
Markerboards are low gloss finished porcelain enamel steel laminated to a medium density fiberboard
(MDF) backing. Tack boards are polyester fabric faced cork sheets laminated to a particle board
backing.
3. Design of markerboards and tack boards shall comply with Design Standard Plate for Training Room
Cabinets.
4. Coordinate markerboard and tack board locations with other design disciplines (i.e., electrical
receptacles, wall thermostats, etc.). Contract Documents shall clearly identify requirement for wood
blocking (or other material) within metal stud framed walls for proper attachment and support of
markerboards and tack boards.
END OF SECTION
June 2011 10 10 00 1
SECTION 10 10 00
1.1 SUMMARY
A. Section Includes:
1. Markerboards.
2. Tackboards.
B. Related Sections:
1.2 SUBMITTALS
A. Product Data:
B. Samples:
1. Product Data: For adhesives, including printed statement of VOC content and chemical
components (Credit EQ 4.1).
D. Submittal List:
A. Deliver factory-built visual display boards, including factory-applied trim where indicated,
completely assembled in one piece without joints, where possible. If dimensions exceed
maximum manufactured panel size, provide two or more pieces of equal length as acceptable to
Architect. When overall dimensions require delivery in separate units, prefit components at the
factory, disassemble for delivery, and make final joints at the site.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
B. Particleboard:
C. Cork Sheet:
D. Polyester Fabric:
1. Nondirectional weave, 100 percent polyester; weighing not less than 15 oz./sq. yd.; with
surface-burning characteristics indicated.
F. Laminating Adhesive:
A. Porcelain-Enamel Markerboards:
a. Basis-of Design Product: Claridge Products & Equipment, Inc.; Designer Series
fabric.
1. Fabricated from not less than 0.062-inch- thick, extruded aluminum; of size and shape
indicated.
2. Factory-Applied Trim:
1. Manufacturer's standard, continuous, extruded aluminum, solid type with ribbed section
and end closures. Match color of frame.
2.6 FABRICATION
A. General:
1. Laminate porcelain-enamel face sheet and backing sheet to core material under heat and
pressure with manufacturer's standard flexible, waterproof adhesive.
1. Class II, clear anodic coating complying with AAMA 611, AA-M12C22A31, Class II, 0.010
mm or thicker.
PART 3 - EXECUTION
3.1 INSTALLATION
A. General:
1. Install visual display surfaces in locations and at mounting heights indicated on Drawings.
Keep perimeter lines straight, level, and plumb. Provide grounds, clips, backing
materials, adhesives, brackets, anchors, trim, and accessories necessary for complete
installation.
1. Attach concealed clips, hangers, and grounds to wall surfaces and to visual display
boards with fasteners at not more than 16 inches o.c. Secure both top and bottom of
boards to walls.
1. Attach trim over edges of visual display boards and conceal grounds and clips. Attach
trim to boards with fasteners at not more than 24 inches o.c.
1. Attach one cleaning label to visual display surface in each room. Cover and protect
visual display surfaces after installation and cleaning.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: Refer to related Division 10 and Division 26 Design Criteria, Commissary Door
Schedule in Appendix "A", and related Design Standard Plates. Refer to Division 10 Section Storage
Racks to coordinate storage height restrictions sign with height of storage racks.
2. Provide interior and exterior signage as follows:
A. Construction Sign.
B. Traffic and Parking Signs.
C. Exterior Illuminated Building Sign.
D. Store Hours Sign.
E. Automatic Entrance Door Signage.
F. Restroom Door Identification Signage.
G. Interior Door Identification Signage.
H. Receiving Door Identification Signage.
I. Exterior Door Identification Signage.
J. Customer Service Signage.
K. Traffic Door Identification Signage.
L. Storage Height Restriction Sign.
M. Surcharge Plaque.
3. All signage shall be graphically shown on the Drawings with location and mounting heights clearly
identified.
4. Signage requirements are as follows:
A. Construction Sign: Immediately after issuance of Notice to Proceed with construction, Contractor
shall furnish and erect a construction sign similar to that illustrated at the end of the sign Guide
Specification. The location of the sign should be determined during preparation of Contract
Documents with location clearly identified on Drawings. The electronic artwork necessary to print
the construction sign will be obtained by the design A/E from DeCA and made available to the
Contractor after the award of construction. The design A/E shall edit the DeCA electronic artwork
files to include Project name, location, project type (i.e., New Construction, Add/Alter, Architectural
and Refrigeration Upgrade), and architectural rendering; and be included in sign Guide
Specification. Specifications will require Contractor to furnish completion date and construction cost.
Traffic and Parking Signs: Signage shall be in accordance with the U.S. Department of
Transportation, Manual on Uniform Traffic Control Devices.
1. Accessible parking shall have post-mounted parking signs with the international accessibility
symbol, in addition to having the international accessibility symbol painted on the pavement.
Determine number of required spaces per code/regulation requirements. It is recommended
that all accessible spaces be designed as van accessible spaces.
2. When a separate parking area is provided for commissary employees, provide permanent post
mounted signs at each entrance clearly stating "COMMISSARY EMPLOYEE PARKING ONLY".
B. Exterior Illuminated Building Sign: Provide DeCA standard sign. A standard size has been
developed for use on commissary facilities. Refer to DeCA Uniform Decor 2010, "Adaptive Uniform
Dcor Package" Exterior Wall Mounted Sign standard drawings. These are available in AutoCAD
electronic format for use in Contract Documents. Sign location and sizing adaptation requirements
should be determined during the initial design charrette process. Coordinate electrical connection
rough-in with Division 26 Electrical.
June 2011 10 14 00 1
DeCA DESIGN CRITERIA HANDBOOK
10 14 00 SIGNAGE
C. Store Hours Sign: Provide DeCA standard grade mounted store hours sign. Refer to Design
Standard Plate 10 14 00-01. Sign shall be internally illuminated with removable back panel and
changeable store hour panel inserts. Design sign base with appropriate foundation for support of
store hours sign. Materials used for base shall be compatible with that used on the commissary
building. Location of store hours sign should be determined during design and clearly indicated on
Contract Documents. Coordinate electrical connection rough-in with Division 26 Electrical. Provide
note on sign detail requiring Contractor to verify store hours at time of sign fabrication.
D. Automatic Entrance Door Signage: Provide pressure sensitive lettering on automatic entrance and
exit doors that identify intended function of door opening. Signage color shall contrast with door
color. Typically white pressure sensitive lettering is applied to dark bronze doors. Lettering is
typically located on center muntin of automatic doors, except at carryout return door opening where
lettering is applied to vision lites. Required signage is "ENTRANCE", "EXIT","EXIT ONLY",
"EMERGENCY EXIT ONLY" and "CARRY OUT RETURN ONLY". Identify required signage on
Door Schedule.
1. Vestibule RM. 1 - Entrance Vestibule: At exterior door provide signage "ENTRANCE" on
exterior side of door opening and "EXIT" on vestibule side of door opening. At interior vestibule
door provide signage "ENTRANCE" on vestibule side of door opening and "EXIT" on sales area
side of door opening.
2. Vestibule RM. 2 - Exit Vestibule: At exterior door provide signage "EXIT ONLY" on exterior side
of door opening and "EXIT" on vestibule side of door opening. At interior vestibule door provide
signage "EXIT ONLY" on vestibule side of door opening and "EXIT" on checkout area side of
door opening.
3. Vestibule RM. 3 - Carry Out Return: At exterior door provide signage "CARRYOUT RETURN
ONLY" on exterior side of door opening and "EMERGENCY EXIT ONLY" on vestibule side of
door opening. At interior vestibule door provide signage "CARRY OUT RETURN ONLY" on
vestibule side of door opening and "EMERGENCY EXIT ONLY" on checkout area side of door
opening.
E. Restroom Door Identification Signage: Melamine plastic with raised text, Braille, border, and
symbols. Locate at entrance to customer and employee restrooms, and employee locker rooms.
Permanently mount sign on wall adjacent to latch side of door with the centerline of the sign 5'-0"
AFF. Signs shall read "MEN" or "WOMEN" as appropriate and include appropriate silhouette
symbol and international accessibility symbol. If an additional sign is required for identification,
mount directly below restroom door identification sign with centerline of the sign 48" AFF. Locate a
sign reading "EMPLOYEES MUST WASH HANDS BEFORE RETURNING TO WORK" 15' -0"
above finished floor on the inside of each door in the employees restrooms.
F. Interior Door Identification Signage: Melamine plastic with raised text, Braille, border, and symbols.
Provide interior door identification signage for all rooms (i.e., offices, break rooms, training rooms,
storage rooms, mechanical rooms, etc.) other than cold storage rooms, identifying occupancy /
function of room. Permanently mount sign on wall adjacent to latch side of door with the centerline
of the sign 5' -0" AFF. Signs may have both identification text (i.e., Cashiers Office, etc.) and
direction text (Authorized Personnel Only). Requirements for signage text shall be clearly indicated
in Door Schedule.
1. Training Room shall have removable "Conference in Session" signage in conjunction with
identification text "Training Room".
2. Doors leading to utility tunnels under store shall have identification text "Underfloor Tunnel" with
direction text "Danger Permit Required Confined Space Authorized Personnel Only".
G. Receiving Door Identification Signage: Fiberglass sign with raised text (6" high numerals) and
border. Provide signs at all overhead receiving doors. Locate signs 4' -6" above each dock level
receiving door and centered on door opening. Locate signs 8' -0" above finish floor at grade level
receiving doors, adjacent to either left or right jamb of door opening. Doors shall be numbered,
starting with numeral "1" at the first door approached upon entering the commissary receiving area.
June 2011 10 14 00 2
DeCA DESIGN CRITERIA HANDBOOK
10 14 00 SIGNAGE
H. Exterior Door Identification Signage: Fiberglass sign with raised text, Braille, and border.
Permanently mount sign on wall adjacent to latch side of door with the centerline of the sign 5' -0"
AFF. If an additional sign is required for identification, mount directly below door identification sign
with centerline of the sign 48" AFF.
1. Provide at exterior access mechanical / electrical room doors. Signs shall have both
identification text (i.e., Fire Sprinkler Riser Room, etc.) and direction text (Authorized Personnel
Only). Requirements for signage text shall be clearly indicated in Door Schedule.
2. Provide at exterior entrance to commissary administrative office. Sign shall have both
identification text (i.e., Commissary Administrative Office) and direction text (Authorized
Personnel Only). Requirements for signage text shall be clearly indicated in Door Schedule.
3. Provide at receiving area personnel doors that have door buzzer push buttons for delivery
personnel to signal when deliveries are occurring. Push button shall be located directly beneath
sign. Signs shall have both identification text (i.e., Meat Department, etc.) and direction text
(Push Button for Deliveries). If multiple push buttons are located at one door opening, provide
detail clarifying signage and push button placement. Requirements for signage text shall be
clearly indicated in Door Schedule. Coordinate push button locations with Division 26 Electrical.
4. Provide international "NO SMOKING" signs at all exterior personnel doors. This will typically
be an additional sign located directly beneath the primary door identification sign. Provide
international "NO SMOKING" two sided decal at automatic entrance doors (customer entrance
and carryout return doors) and exterior administrative office entrance glass door(s).
I. Customer Service Signage: Melamine plastic with raised text, Braille, border, and symbols. Provide
in commissary sales area for customers to signal Meat Department and Produce Department
personnel for customer service. Locate signs at closest entrance to these service support areas.
Permanently mount sign on wall near door, with the centerline of the sign 5'-0" AFF. Push button
shall be located directly beneath sign. Sign shall have both identification text (i.e., Meat Department,
etc.) and direction text (Push Button for Customer Service). Requirements for signage text shall be
clearly indicated in Door Schedule. Coordinate push button locations with Division 26 Electrical.
J. Traffic Door Identification Signage: Provide pressure sensitive lettering applied to each door leaf of
traffic doors that identify intended use of door opening (i.e., EMPLOYEES ONLY). Signage color
shall contrast with door color. Typically white color pressure sensitive lettering is applied to black
color doors. Align (i.e., justify) lettering with edge of vision window closest to the middle of the door
opening on pairs of doors and closest to strike jamb on single leaf traffic doors.
K. Storage Height Restriction Sign: DeCA Design Criteria does not permit storage above 12'-0" in
staging and receiving areas (i.e. high piled stock or rack storage). Contract Documents shall require
that a continuous painted 6" wide red color stripe, at 12' -0" above floor slab, be provided on all walls
facing staging and receiving areas. Provide one plastic sign centered on each wall and immediately
above the stripe that reads "DO NOT STACK MERCHANDISE ABOVE THIS LINE". Refer to
Design Standard Plate 10 14 00-02.
L. Surcharge Plaque: The Government will furnish a 12" high by 18" wide, cast bronze surcharge
plaque for installation by the Contractor. Plaque shall be permanently installed in a prominent
location at the front customer entrance to the commissary. Location of surcharge plaque shall be
determined during design of project and clearly indicated on Contract Documents.
END OF SECTION
June 2011 10 14 00 3
SECTION 10 14 00
SIGNAGE
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Construction sign.
2. Traffic and parking signs.
3. Exterior illuminated building sign.
4. Commissary store hours sign.
5. Automatic entrance door signage.
6. Restroom door identification signage.
7. Interior door identification signage.
8. Receiving door identification signage.
9. Exterior door identification signage.
10. Customer service signage.
11. Traffic door identification signage.
12. Storage height restriction sign.
13. Surcharge plaque.
A. Wind Loading:
B. Seismic Performance:
1. Seismic Loads:
A. Product Data:
1. For each type of sign specified, including details of construction relative to materials,
dimensions of individual components, profiles, and finishes.
B. Shop Drawings:
1. Showing fabrication and erection of signs. Include plans, elevations, and large-scale
sections of typical members and other components. Show anchors, grounds, layout,
reinforcement, accessories, and installation details.
2. Provide message list for each sign required, including large-scale details of wording and
lettering layout.
3. For signs supported by or anchored to permanent construction, provide setting Drawings,
templates, and directions for installation of anchor bolts and other anchors to be installed
as a unit of Work in other Sections.
4. Templates: Furnish full-size spacing templates for individually mounted dimensional
letters and numbers.
1. Prior to sign fabrication, submit a list indicating the text required for each sign, including
store hours where applicable, for verification by the Contracting Officer.
D. Submittal List:
1. Firm experienced in producing signs similar to those indicated for this Project, with a
record of successful in-service performance, and sufficient production capacity to
produce sign units required without causing delay in the Work.
1. Provide lighting fixtures and electrical components for illuminated signs that are labeled
and listed by UL and comply with applicable NEMA standards.
C. Regulatory Requirements:
1. Comply with applicable provisions in ABA Accessibility Guidelines and ICC/ANSI A117.1.
1. For each separate sign type required, obtain signs from one source of a single
manufacturer.
A. Field Measurements: Take field measurements prior to preparation of shop Drawings and
fabrication to ensure proper fitting. Show recorded measurements on final shop Drawings.
Coordinate fabrication schedule with construction progress to avoid delay.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
2.2 MATERIALS
A. Plastic Laminate:
1. Provide high-pressure plastic laminate engraving stock with face and core plies in
contrasting colors, in finishes and color combinations indicated or, if not indicated, as
selected from the manufacturer's standards.
B. Aluminum Sheet:
1. Provide aluminum sheet of alloy and temper recommended by the sign manufacturer for
the type of use and finish indicated, and with not less than the strength and durability
properties specified in ASTM B 209 for 5005- H32.
C. Aluminum Extrusions:
1. Provide aluminum extrusions of alloy and temper recommended by the sign manufacturer
for the type of use and finish indicated, and with not less than the strength and durability
properties specified in ASTM B 221 for 6063-T5.
D. Vinyl Film:
1. Use concealed fasteners, unless otherwise indicated, fabricated from metals that are not
corrosive to the sign material and mounting surface.
2. Exposed fasteners are permitted for construction sign and traffic signs.
1. Use nonferrous metal or hot-dipped galvanized anchors and inserts for exterior
installations and elsewhere as required for corrosion resistance. Use toothed steel or
lead expansion bolt devices for drilled-in-place anchors. Furnish inserts, as required, to
be set into concrete or masonry work.
1. Use colored coatings, including inks and paints for copy and background colors, that are
recommended by acrylic manufacturers for optimum adherence to acrylic surface and are
nonfading for the application intended.
H. Brackets:
1. Fabricate brackets and fittings for bracket-mounted signs from extruded aluminum to suit
sign panel construction and mounting conditions indicated. Factory-paint brackets in a
color matching the background color of the sign panel.
PART 3 - EXECUTION
3.1 INSTALLATION
A. General:
1. Locate sign units and accessories where indicated, using mounting methods of the type
described and in compliance with the manufacturer's instructions.
2. Install signs level, plumb, and at the height indicated, with sign surfaces free from
distortion or other defects in appearance.
B. Construction Sign:
1. Immediately upon issuance of Notice to Proceed with construction, furnish, install, and
maintain a Construction Sign capable of withstanding normal winds encountered in
Project Area.
2. Locate sign where indicated, if not indicated locate as directed by Contracting Officer.
3. Sign shall remain the property of the Contractor, and upon completion of the Work shall
be removed from Project site.
1. Install where indicated. Where not indicated, install on wall adjacent to latch side of door.
Where there is no wall space to latch side of door, place signs on nearest adjacent wall
or center on door. Locate signage so that a person may approach within 3 inches of
signage without standing within swing of door.
2. Employee Notice Sign: Install where indicated. Where not indicated, install on center of
restroom side of door 60 inches above finished floor to centerline of sign.
1. Install where indicated. Where not indicated, install on wall adjacent to latch side of door.
Where there is no wall space to latch side of door, including double leaf doors, place
signs on nearest adjacent wall.
2. Locate signage so that a person may approach within 3 inches of signage without
standing within swing of door.
3. Install interior and exterior door identification signage 60 inches above finished floor to
centerline of sign.
4. Install receiving door identification signage centered above overhead door, at recessed
docks, and adjacent to overhead door at grade level receiving doors.
1. Unless otherwise indicated mount customer service sign at height above finished floor to
centerline of pushbutton as follows:
1. Attach panel signs to wall surfaces using the methods indicated below:
A. After installation, clean soiled sign surfaces according to the manufacturer's instructions.
Protect units from damage until final acceptance.
a. Construction Cost.
b. Completion Date.
8. Refer to construction sign details and artwork images attached at end of this Section.
a. Construction Cost.
b. Completion Date.
8. Refer to construction sign details and artwork images attached at end of this Section.
3. Faces:
a. G.E. Lexan, 0.15 inch thick, clear and white, with first and second surface 3M
Brand Translucent film applications and custom logo of 3M Brand Translucent
Scotch print Digital Graphic in high resolution.
b. Colors shall match codes and descriptions for DeCA Commissary as indicated.
4. Electrical:
a. Single face.
b. Size of uppercase letters: As indicated.
11. Internal post supports and bracing in accordance with system performance requirements.
12. Aluminum skirt to conceal post supports.
13. Basis-of-Design Product: I-5 Design & Manufacture (800) 459-2967 or
www.i5design.com.
1. No Smoking sign: Minimum 6-inch by 3-inch vinyl stick-on 2-sided decal transfer
indicating international no smoking symbol and text "NO SMOKING." Red circle, black
cigarette, with red diagonal.
2. Exit, Emergency Exit Only, Entrance, Exit Only, and Carry-Out Return Only signs:
a. Applied Copy: Die-cut characters from vinyl film with pressure-sensitive adhesive
backing, pre-spaced and pre-aligned.
b. Lower case Helvetica medium.
c. Color: As indicated.
3. Sliding Door Emergency Breakaway Sign: BHMA A156.10; red background with 1-inch-
high contrasting letters with the words "IN EMERGENCY PUSH TO OPEN."
4. Sliding Door Caution Sign: BHMA A156.10; minimum 1/2-inch- high, lettering with the
words "AUTOMATIC DOOR."
a. Men's restroom verbal and silhouette symbol identification sign with international
accessibility symbol. Text in uppercase.
b. Women's restroom verbal and silhouette symbol identification sign with
international accessibility symbol. Text in uppercase.
c. Familys restroom verbal and silhouette symbol identification sign with international
accessibility symbol. Text in uppercase.
d. "Employees Must Wash Hands Before Returning To Work" sign.
1) Title text case: Lower case with first letter of each word in uppercase.
5. Colors:
7. Mounting: Vinyl-tape.
8. Basis-of-Design Product: I-5 Design & Manufacture (800) 459-2967 or
www.i5design.com.
3. Colors:
4. Mounting: Vinyl-tape.
5. Basis-of-Design Product: I-5 Design & Manufacture (800) 459-2967 or
www.i5design.com.
1. Panel:
4. Characters (lettering):
1) Helvetica medium.
2) Lowercase with an uppercase first letter of each word.
c. Character Height (measured using an upper case X): Approximately 3/4 inch.
5. Mounting: Vinyl-tape.
6. Basis-of-Design Product: I-5 Design & Manufacture (800) 459-2967 or
www.i5design.com.
7. Traffic Door Identification Signage:
8. Unless otherwise indicated provide pressure sensitive lettering in accordance with the
following:
a. Applied Copy: Die-cut characters from vinyl film with pressure-sensitive adhesive
backing, pre-spaced and pre-aligned.
b. Letter Color: As indicated.
c. Letter Style: Helvetica Medium.
1. Panel:
2. Colors:
3. Characters (lettering):
1) Helvetica medium.
2) Uppercase.
M. Surcharge Plaque:
1. The Government will furnish a cast bronze surcharge plaque for installation by the
Contractor. Permanently mount the plaque in a prominent location at the front entrance.
The Contracting Officer will determine the exact location.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 10 and Division 26 Design Criteria, related Design Standard
Plates, and electronic AutoCAD files of the DeCA Uniform Decor 2010.
2. Provide a state-of-the-art integrated supermarket merchandising interior decor package in
accordance with the DeCA "Adaptive Uniform Decor Package".
A. Refer to the DeCA "Adaptive Uniform Decor Package" for recommended placement of all interior
decor components and fabrication requirements. Adapt recommended placements as required to
accommodate specific store layout and to accommodate store ceiling heights less than the
recommended new store height guidelines indicated.
B. Electronic AutoCAD (.dwg) files of the "Adaptive Uniform Decor Package" are available for A/E
use in preparation of Contract Documents. Edit files as required to accommodate specific project
requirements and incorporate all applicable details into the contract documents.
C. Decor packages are designed for 18" -0" clear heights with decorative suspended components.
Decor packages for Add/ Alter Projects typically have suspended grid with acoustical tile ceilings
at lower elevations requiring adaptations of the dcor standards.
D. On exposed structure facilities, it is important that suspended lighting and HVAC diffusers are set
at the same elevation as the top of the interior decor package. All other utilities (HVAC ductwork,
refrigeration piping, sprinkler piping, conduits, etc.) should be above the decor package. Set roof
structure height, including roof drainage slope, accordingly. Provide flat oval or multiple HVAC
supply air ducts to reduce building height.
E. The following interior decor specialties are included in the Guide Specification:
1. Aisle Directory Signs
2. Department Decor Elements
3. Tagline Lettering
4. Banners
5. Checkstand Markers
6. Department Blade Signs
7. Frozen Food Identifier
8. Frozen Food Valance
9. Produce Decor Grid
10. Soffit Trim
F. Electronic artwork of all printed decor elements is available for use by the interior decor
fabricator.
END OF SECTION
June 2011 10 15 00 1
SECTION 10 15 00
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 01 Section Sustainable Design Reporting for adhesives and composite wood
products documentation indicating that products contain no urea formaldehyde. Chain-
of-custody certificates indicating that products specified to be made from certified wood
comply with forest certification and chain-of-custody requirements.
2. Division 06 Section Rough Carpentry for wood furring, blocking, shims, and hanging
strips required for installation.
3. Division 06 Section Interior Architectural Woodwork for interior carpentry exposed to view
that is not specified in this Section.
1.2 DEFINITIONS
A. ABA Accessibility Guidelines: U.S. Architectural & Transportation Barriers Compliance Board's
"Architectural Barriers Act (ABA) Accessibility Guidelines."
1.3 SUBMITTALS
A. Product Data: For each type of interior decor specialty specified, including details of
construction relative to materials, dimensions of individual components, profiles, and finishes.
1. Show fabrication and erection of interior decor specialties. Include plans, elevations, and
large-scale sections of typical members and other components. Show anchors, grounds,
layout, reinforcement, accessories, and installation details.
2. Provide message list for each sign required, including large-scale details of wording and
lettering layout.
3. Show details of anchors supporting banners.
C. Samples:
1. Provide digitally printed color sample, 2 inch by 2 inch minimum size for color matching
with paint chip control samples. Submit paint chip color control samples with digitally
printed color sample submittal.
2. Provide 2 foot by 2 foot banner sample.
3. Provide sample of anchors supporting banners.
A. Interior Decor Specialty Fabricator Qualifications: Firm experienced in producing interior decor
specialties similar to those indicated for this Project, with a record of successful in-service
performance, and sufficient production capacity to produce interior decor specialty units
required without causing delay in the Work.
A. Field Measurements: Obtain field measurements prior to preparation of Shop Drawings and
fabrication to ensure proper fitting. Show recorded measurements on final shop Drawings.
Coordinate fabrication schedule with construction progress to avoid delay.
B. Environmental Limitations: Do not deliver or install directories until spaces are enclosed and
weathertight, wet work in spaces is complete and dry, work above ceilings is complete, and
temporary HVAC system is operating and maintaining ambient temperature and humidity
conditions at occupancy levels during the remainder of the construction period.
2.1 MANUFACTURERS
B. Basis of Design Interior Decor Specialties Fabricator: I-5 Design & Manufacture Inc, Contact:
Joe Hier (800) 459-2967 x 105 or e-mail jhier@i5design.com.
2.2 MATERIALS
1. Extruded polystyrene foam board bonded on both sides with laminated facing materials.
Lightweight structural panels of rigid polystyrene foam core faced on both sides with
smooth, moisture resistant man-made wood fiber veneers. Foam and veneers are
permanently bonded together in a sandwich construction. Face laminates specially
developed to provide excellent surface for painting, silk screening, laminating, and photo
mounting.
2. Fire-Test-Response Characteristics:
a. Flame-spread index of not greater than 25 when tested according to ASTM E 84.
b. Smoke-developed index of not greater than 450 when tested according to ASTM
E 84.
c. Rapid heat release rate of not greater than 150 kilowatts when tested according to
UL 1975.
B. Foamed Core Board Type 2: Rigid, foamed, closed-cell poly vinyl chloride (PVC) board bonded
on both sides with laminated facing materials.
1. Fire-Test-Response Characteristics:
a. Flame-spread index of not greater than 25 when tested according to ASTM E 84.
b. Smoke-developed index of not greater than 450 when tested according to ASTM E
84.
c. Rapid heat release rate of not greater than 150 kilowatts when tested according to
UL 1975.
C. Aluminum: Alloy and temper recommended by aluminum producer and finisher for type of use
and finish indicated, and with not less than the strength and durability properties of alloy and
temper designated below for each aluminum form required.
1. ANSI A208.2, Grade MD. [, made with binder containing no urea formaldehyde].
2. Basis-Of-Design Product: "Medite 3D" Sierra Pine Composite Solutions, (800) 676-3339,
www.sierrapine.com.
A. Colors and Surface Textures: For exposed interior decor specialty material that requires
selection of materials with integral or applied colors, surface textures or other characteristics
related to appearance, provide color matches indicated.
B. Metal Finishes: Comply with NAAMMs "Metal Finishes Manual for Architectural and Metal
Products"for finish designations and applications recommendations.
C. Appearance of Finished Work: Noticeable variations in same piece are not acceptable.
Variations in appearance of adjoining components are acceptable if they are within the range of
approved Samples and are assembled or installed to minimize contrast.
NHLA does not define any maximum moisture content values for
kiln-dried hardwood lumber; purchaser must specify the value.
Maximum moisture content values in first subparagraph below are
based on ranges given for optimum moisture content in AWI's
"Architectural Woodwork Quality Standards Illustrated." First
option applies to damp coastal areas of the southern U.S. and the
Maritime Provinces. Second option applies to Ontario, Quebec, and
most of the U.S. Third option applies to the dry southwestern U.S.
and to Alberta, Manitoba, and Saskatchewan.
PART 3 - EXECUTION
3.1 INSTALLATION
A. General:
1. Locate interior decor components where indicated, using mounting methods of the type
described and in compliance with the manufacturer's instructions.
2. Install interior decor components level, plumb, and at the height indicated, with surfaces
free from distortion or other defects in appearance.
B. Wall-Mounted Foamed Core Board Interior Decor Components: Attach foamed core board
interior decor components to wall surfaces using the methods indicated below:
A. After installation, clean soiled interior decor specialty surfaces according to the manufacturer's
instructions. Protect units from damage until final acceptance.
A. Aisle Directory Signs: Custom fabricated of Foamed Core Board Type 2 and MDF (Medite 3D)
as detailed on Drawings.
1. Colors: As indicated.
2. Numbers:
a. Thickness: As indicated.
b. Face style: As indicated.
c. Size: As indicated.
3. Mounting: As indicated.
B. Department Decor Elements: Custom fabricated of Foamed Core Board Type 2, Aluminum,
MDF (Medite 3D) and LED Lighting as detailed on Drawings.
1. Colors: As indicated.
2. Letters: As indicated.
a. Thickness: As indicated.
b. Face style: As indicated.
c. Size: As indicated.
d. Profiles: As indicated.
3. Mounting: As indicated.
4. Valance:
a. Thickness: As indicated.
b. Face style: As indicated.
c. Size: As indicated.
d. Mounting: As indicated.
a. Size: As indicated.
b. Color: As indicated.
1. Colors: As indicated.
2. Profiles: As indicated.
3. Size: As indicated.
4. Mounting: Silicone adhesive and 3M VHB.
D. Banners: Custom fabricated of styrene, MDF (Medite 3D) and aluminum as detailed on
Drawings. Electronic artwork provided by Government.
F. Department Blade Signs: Custom fabricated of MDF (Medite 3D) and aluminum as indicated
and detailed on Drawings.
1. Colors: As indicated.
2. Profiles: As indicated.
3. Size: As indicated.
4. Mounting: As Indicated.
G. Frozen Food Identifiers: Custom fabricated of MDF (Medite 3D) and aluminum as indicated and
detailed on Drawings.
1. Colors: As indicated.
2. Profiles: As indicated.
3. Size: As indicated.
4. Mounting: As Indicated.
H. Frozen Food Valance: Custom fabricated of aluminum as indicated and detailed on Drawings.
1. Colors: As indicated.
2. Profiles: As indicated.
3. Size: As indicated.
4. Mounting: As Indicated.
I. Produce Decor Grid: Custom fabricated of Hemlock wood and aluminum as detailed on
Drawings.
1. Framing:
J. Soffit Trim.
END OF SECTION
DESIGN CRITERIA
2. This Section includes floor mounted, overhead braced, textured stainless steel toilet compartments. If
required in plan layout, provide matching wall mounted urinal screens. Size of urinal screens shall be
18" deep x 42" high, with top of screen set 58" above finish floor.
3. Layout of toilet compartments shall be in accordance with applicable provisions in the U.S.
Architectural & Transportation Barriers Compliance Board's "Architectural Barriers Act (ABA)
Accessibility Guidelines for Buildings and Facilities" and ICC/ANSI A117.1 guidelines.
4. Layout of room shall not permit direct view (or mirror reflected view) into toilet rooms. Current DeCA
criteria requires that all multiple-use restroom doors (and locker room doors if connected) swing outward
from the restroom or locker room for sanitation reasons. Single-use family restroom doors may swing
into the rooms as these doors have locksets with handles.
5. Coordinate placement of toilet accessories, both partition mounted and wall mounted, to avoid conflicts
with toilet compartment door swings.
6. Coordinate toilet compartment locations with other design disciplines (i.e., electrical receptacles, wall
thermostats, radiant heaters, etc.). Contract Documents shall clearly identify requirement for wood
blocking (or other material) within metal stud framed walls for proper attachment and support of toilet
compartments.
7. Show dimensioned elevations on drawings. Indicate accessory locations where cutouts and
reinforcements are required. Indicate pilaster, door, panel, and screen heights.
END OF SECTION
June 2011 10 21 13 1
SECTION 10 21 13
TOILET COMPARTMENTS
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 SUBMITTALS
A. Product Data: For each type of product indicated. Include construction details, material
descriptions, dimensions of individual components and profiles, and finishes.
C. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work.
D. Submittal List:
B. Regulatory Requirements: Comply with applicable provisions in the U.S. Architectural &
Transportation Barriers Compliance Board's "Architectural Barriers Act (ABA) Accessibility
Guidelines for Buildings and Facilities" and ICC/ANSI A117.1 for toilet compartments
designated as accessible.
A. Field Measurements: Verify actual locations of walls, columns, ceilings, and other construction
contiguous with toilet compartments by field measurements before fabrication and indicate
measurements on Shop Drawings.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Steel Sheet: Commercial steel sheet for exposed applications; mill phosphatized and selected
for smoothness.
2.2 MANUFACTURERS
B. Toilet Enclosure Style: Floor and Ceiling anchored: Manufacturer's standard thickness, but not
less than 0.0375 inch.
D. Door, Panel, and Pilaster Construction: Seamless, metal facing sheets pressure laminated to
core material; with continuous, interlocking molding strip or lapped-and-formed edge closures;
corners secured by welding or clips and exposed welds ground smooth Exposed surfaces shall
be free of pitting, seam marks, roller marks, stains, discolorations, telegraphing of core material,
or other imperfections.
E. Urinal-Screen Construction:
1. Integral-Flange, Wall-Hung Urinal Screen: Similar to panel construction, with integral full-
height flanges for wall attachment, and maximum 1-1/4 inches thick.
F. Facing Sheets and Closures: Fabricated from ASTM A 666, Type 304, stainless-steel sheet,
leveled to stretcher-leveled flatness. Stainless-steel sheet of nominal thicknesses as follows:
1. Pilasters, Braced at Both Ends: Manufacturer's standard thickness, but not less than
0.038 inch.
2. Panels: Manufacturer's standard thickness, but not less than 0.031 inch.
3. Doors: Manufacturer's standard thickness, but not less than 0.031 inch.
4. Integral-Flange, Wall-Hung Urinal Screens: Manufacturer's standard thickness, but not
less than 0.031 inch.
G. Pilaster Shoes and Sleeves (Caps): ASTM A 666, Type 302 or 304. Stainless-steel sheet, not
less than 0.031-inch nominal thickness and 3 inches high, finished to match hardware.
I. Stainless Steel Finish: Manufacturers standard textured finish on exposed faces. Protect
exposed surfaces from damage by application of strippable, temporary protective covering
before shipment.
2.4 ACCESSORIES
2.5 FABRICATION
B. Door Size and Swings: Unless otherwise indicated, provide 24 inch wide in-swinging doors for
standard toilet compartments and 36 inch wide out-swinging doors with a minimum 32 inch wide
clear opening for compartments indicated to be accessible to people with disabilities.
PART 3 - EXECUTION
3.1 INSTALLATION
A. General: Comply with manufacturer's written installation instructions. Install units rigid, straight,
level, and plumb. Secure units in position with manufacturer's recommended anchoring
devices.
1. Maximum Clearances:
2. Stirrup Brackets: Secure panels to walls and to pilasters with not less than two brackets
attached near top and bottom of panel.
a. Locate wall brackets so holes for wall anchors occur in masonry or tile joints.
b. Align brackets at pilasters with brackets at walls.
C. Urinal Screens: Attach with anchoring devices to suit supporting structure. Set units level and
plumb, rigid, and secured to resist lateral impact.
D. Floor Seal: Seal tight at all floor connections with single or multi-component silicone sealant
appropriate for application.
3.2 ADJUSTING
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 08 Design Criteria and Standard Commissary Room and Finish
Schedule in Appendix "A".
2. Wire mesh partitions are intended for building interior use. Refer to Division 32 Design Criteria for Chain
link Fences and Gates intended for exterior use.
3. Wire mesh partitions may be used to provide lockable secure enclosures for Contract Stocker Storage
(RM. 30), Sensitive Storage (RM. 32), and Operational Supply Storage (RM. 33 and 47).
4. Enclosures shall be full height galvanized steel wire mesh and secured to metal roof deck and adjacent
partitions. Wire mesh partitions are not painted. Depending on location within the commissary, other
durable building materials may be more practical and cost effective.
END OF SECTION
June 2011 10 22 13 1
SECTION 10 22 13
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 DEFINITIONS
1. Intermediate Crimp: Wires pass over one and under the next adjacent wire in both
directions, with wires crimped before weaving and with extra crimps between the
intersections.
2. Lock Crimp: Deep crimps at points of intersection that lock wires securely in place.
A. Seismic Performance:
1. Provide wire mesh partition assemblies capable of resisting the effects of earthquake
motions.
2. Refer to Division 01 Section Summary of Work for seismic-load design criteria.
3. Determine seismic loads using the appropriate exposure coefficient for the wire mesh
partition assemblies.
1.4 SUBMITTALS
A. Product Data:
B. Shop Drawings:
1. Include plans, elevations, sections, details, and attachments to other work necessary for
fabrication and installation.
2. For installed products indicated to comply with design loads, include structural analysis
data signed and sealed by the qualified professional engineer responsible for their
preparation.
D. Submittal List:
A. Installer Qualifications:
B. Source Limitations:
1. Obtain wire mesh items through one source from a single manufacturer.
C. Welding:
A. Field Measurements:
1. Verify actual locations of construction contiguous with wire mesh items by field
measurements before fabrication and indicate measurements on Shop Drawings.
A. General:
1. Deliver wire mesh items palleted or crated to provide protection during transit and
Project-site storage. Use vented plastic.
2. Inventory wire mesh partition door hardware on receipt and provide secure lockup for
wire mesh partition door hardware delivered to Project site.
1.8 COORDINATION
A. Coordinate installation of anchorages for wire mesh items supported or anchored to permanent
construction. Furnish setting drawings, templates, and directions for installing anchorages,
including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be
embedded in concrete or masonry. Deliver such items to Project site in time for installation.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design Products:
2.2 MATERIALS
1. Commercial Steel (CS), Type B; with G60 zinc (galvanized) or A60 zinc-iron-alloy
(galvannealed) coating designation.
F. Panel-to-Panel Fasteners:
1. With capability to sustain, without failure, load imposed within factors of safety indicated,
as determined by testing per ASTM E 488, conducted by a qualified independent testing
agency.
2. Corrosion Protection: Carbon-steel components zinc plated to comply with ASTM B 633,
Class Fe/Zn 5 for Class SC 1 service condition (mild).
3. For Post installed Anchors in Concrete: Capability to sustain, without failure, a load equal
to four times the loads imposed.
4. For Post installed Anchors in Grouted Masonry Units: Capability to sustain, without
failure, a load equal to six times the loads imposed.
1. Fastener system of type suitable for application indicated and fabricated from corrosion-
resistant materials; with clips or other accessory devices for attaching hangers of type
indicated, and with capability to sustain, without failure, a load equal to 10 times that
imposed by wire mesh construction, as determined by testing per ASTM E 1190,
conducted by a qualified testing and inspecting agency.
I. Seismic Bracing:
1. Angles with legs not less than 1-1/4 inch wide, formed from 0.04-inch- thick, metallic-
coated steel sheet; with bolted connections and 1/4-inch- diameter bolts.
A. Mesh:
1. 0.135-inch- diameter, intermediate-crimp steel wire woven into 1-1/2-inch diamond mesh.
1. 1-by-1/2-by-1/8-inch cold-rolled steel channels with wire woven through, or two 1-by-3/8-
by-1/8-inch cold-rolled steel channels bolted or riveted toe to toe through mesh.
1. 1-1/4-by-1-1/4-by-1/8-inch steel angles with 1/4-inch- diameter bolt holes aligning with
bolt holes in vertical framing; with floor anchor clips.
1. Two, manufacturer's standard steel pipe or tubing posts connected by steel hinges at 36
inches o.c. attached to posts; with 1/4-inch- diameter bolt holes aligning with bolt holes in
vertical framing.
H. Line Posts:
I. Floor Shoes:
1. Steel, cast iron, or cast aluminum, 2 inches high; sized to suit vertical framing, drilled for
attachment to floor, and with set screws for leveling adjustment.
J. Swinging Doors:
1. Fabricated from same mesh as partitions, with framing fabricated from 1-1/4-by-1/2-by-
1/8-inch steel channels or C-channels, banded with 1-1/4-by-1/8-inch flat steel bar cover
plates on 3 sides, and with 1/8-inch- thick angle strike bar and cover on strike jamb.
2. Hinges: Full-surface type, 3-by-3-inch steel, 1-1/2 pairs per door; bolted, riveted, or
welded to door and jamb framing.
3. Cylinder Lock: Mortise type with cylinder specified in Division 08 Section Door Hardware;
operated by key outside and lever inside.
4. Inactive Leaf Hardware: Cane bolt at bottom and chain bolt at top.
5. Door Frames: Fabricated from same size and shape as vertical panel framing for the
mesh panels.
K. Accessories:
2.4 FABRICATION
A. General:
1. Fabricate wire mesh items from components of sizes not less than those indicated. Use
larger-size components as recommended by wire mesh item manufacturer. Provide
bolts, hardware, and accessories as required for complete installation.
2. Fabricate wire mesh items to be readily disassembled.
3. Welding: Weld corner joints of framing and leave as applied.
1. Fabricate wire mesh partitions with cutouts for pipes, ducts, beams, and other items
indicated. Finish edges of cutouts to provide a neat, protective edge.
2. Mesh: Securely clinch mesh to framing.
4. Fabricate wire mesh partitions with 3 inches of clear space between finished floor and
bottom horizontal framing.
5. Doors: Align bottom of door with bottom of adjacent panels.
a. For doors that do not extend full height of partition, provide transom over door,
fabricated from same mesh and framing as partition panels.
6. Hardware Preparation: Mortise, reinforce, drill, and tap doors and framing as required to
install hardware.
2.5 FINISHES
A. General:
1. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
2. Finish wire mesh items after assembly.
3. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces
are acceptable if they are within one-half of the range of approved Samples. Noticeable
variations in the same piece are not acceptable. Variations in appearance of other
components are acceptable if they are within the range of approved Samples and are
assembled or installed to minimize contrast.
B. Galvanizing:
1. Hot-dip galvanize wire mesh items to comply with ASTM A 123/A 123M. Hot-dip
galvanize hardware for hot-dip galvanized wire mesh items to comply with
ASTM A 153/A 153M.
PART 3 - EXECUTION
3.1 EXAMINATION
A. General:
1. Examine areas, with Installer present, for compliance with requirements for installation
tolerances and other conditions affecting performance of work.
2. Examine floors for suitable conditions where wire mesh items will be installed.
3. Examine walls and ceilings to which wire mesh items will be attached for properly located
blocking, grounds, and other solid backing for attachment of support fasteners.
4. Proceed with installation only after unsatisfactory conditions have been corrected.
1. Anchor wire mesh partitions to floor with 3/8-inch- diameter, post installed expansion
anchors at 12 inches o.c. through floor shoes located at each post and corner. Adjust
wire mesh partition posts in floor shoes to achieve level and plumb installation.
2. Anchor wire mesh partitions to walls at 12 inches o.c. through back corner panel framing
and as follows:
3. Secure top capping bars to top framing channels with 1/4-inch- diameter "U" bolts spaced
not more than 28 inches o.c.
4. Provide line posts at locations indicated or, if not indicated, as follows:
a. For partitions that are more than 12 feet high, located between each panel.
5. Provide seismic supports and bracing as indicated or, if not indicated, as recommended
by manufacturer and as required for stability, extending and fastening members to
supporting structure.
6. Where standard-width wire mesh partition panels do not fill entire length of run, provide
adjustable filler panels to fill openings.
7. Install doors complete with door hardware.
8. Bolt accessories to wire mesh partition framing.
A. Adjusting:
B. Cleaning:
1. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas; repair
galvanizing to comply with ASTM A 780.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 05 Design Criteria and related Design Standard Plates.
2. Wall and equipment guards are required at numerous locations throughout commissary facilities, and
are considered operational necessities.
A. Protection Posts: Provide at all exposed corners within sales area and other customer areas.
Protection posts are stock-manufactured chrome plated steel, expansion bolted to the finish floor.
Protection posts shall also be provided to guard leading edges of automatic entrance doors.
B. Cart Rails: Provide at shopping cart storage areas, mass display areas adjacent to customer
checkout areas, and at end checkout counters as required to identify checkout aisle width.
Provide double rail system at end checkout counters. Provide triple rail system at shopping cart
storage areas and mass display areas. Cart rails are stock-manufactured chrome plated steel,
expansion bolted to the finish floor.
C. Cart Bumper: Provide spring type floor mounted cart bumpers to protect sliding doors at walk-in
cold storage rooms, and wall surfaces at cart storage areas subject to contact by shopping carts.
Cart bumpers are stock-manufactured chrome plated steel, expansion bolted to the finish floor.
D. Case Corner Guards: Provide at exposed corners of all refrigerated display cases in sales area.
Not required at movable refrigerated display cases. Case corner guards are stock-manufactured
chrome plated steel, expansion bolted to the finish floor.
E. Stainless Steel Bumper Rails: Provide at display cases as identified in Design Standard Plate
10 26 00-02. Bumper rails are stock-manufactured in stainless steel and removable for daily floor
cleaning. Provide detailed information on contract documents identifying bumper rail layout and
required spacing at each display case line-up required to have bumper rail protection.
F. Wood Bumper Rails: Provide double wood bumper rails at all locations within customer areas
that are subject to impact damage from shopping carts. Clearly identify extent of wood bumper
rails on floor plans and interior elevations of sales area. Refer to Design standard Plate 10 26 00-
01 for additional information. Coordinate mounting/rough-in height of utilities (electrical
receptacles, hose bibs, etc.) on walls with double wood bumper rails.
G. Rigid Wall Covering: Provide rigid wall covering on all walls that have double wood bumper rails
and on employee breakroom walls as indicated in Appendix "A" Standard Commissary Room and
Finish Schedule. Refer to Design Standard Plate 10 26 00-01 for additional information.
END OF SECTION
June 2011 10 26 00 1
SECTION 10 26 00
1.1 SUMMARY
A. Section Includes:
a. Protection posts.
b. Cart rails.
c. Cart bumpers.
d. Case corner guards.
e. Stainless steel bumper rail system.
f. Wood bumper rail.
g. Impact resistant wall covering.
B. Related Sections:
1.2 SUBMITTALS
A. Product Data: Product Data: Include construction details, material descriptions, impact
strength, dimensions of individual components and profiles, and finishes for each type of
product indicated.
B. Sustainable Design Submittals: Product Data: For adhesives, including printed statement of
VOC content (credit EQ 4.1).
C. Submittal List:
A. Source Limitations: Obtain each type of wall and equipment guard unit through one source
from a single manufacturer.
A. Store impact-resistant wall protection units in original undamaged packages and containers
inside well-ventilated area protected from weather, moisture, soiling, extreme temperatures, and
humidity.
B. Maintain room temperature within storage area at not less than 70 deg F during the period
plastic materials are stored.
A. Environmental Limitations: Do not deliver or install wall and equipment guards until building is
enclosed and weatherproof, wet work is complete and dry, and HVAC system is operating and
maintaining temperature at 70 deg F for not less than 72 hours before beginning installation and
for the remainder of the construction period.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
2.2 MATERIALS
A. Metal Surfaces: Provide materials with smooth, flat surfaces, unless otherwise indicated. For
metal fabrications exposed to view in the completed Work, provide materials without seam
marks, roller marks, rolled trade names, or blemishes.
B. PVC Plastic: ASTM D 1784, Class 1, textured, chemical- and stain-resistant, high-impact-
resistant PVC or acrylic-modified vinyl plastic with integral color throughout; sheet material,
thickness as indicated.
C. Solid Wood: Clear hardwood lumber of species indicated, free of appearance defects, and
selected for compatible grain and color.
A. Galvanizing Repair Paint: High-zinc-dust-content paint for re-galvanizing steel, complying with
SSPC-Paint 20.
1. Post: 3-inch O.D. tube made from 11 gage cold rolled steel with a 5-1/2 inch diameter
steel flange at the base containing four (4) anchor holes. The top of the post shall be
sealed with a fully welded 3 inch diameter cold rolled steel post cap.
2. Post height 36 inches.
3. Anchor post to floor with expansion anchor bolts. Anchor Package consists of four (4)
each SB anchors with 3/8 - 16 by 2-1/2 inch HHCS and washers. Each SB anchor is a 1-
1/2 inch long by 5/8 inch diameter single-expansion system that expands to lock the
anchor bolt securely in place.
4. 16 gage steel form-fit cover plate for covering post base anchors.
5. Finish: All external fabricated materials are composed of cold rolled chrome plated steel
and mirror polished.
6. Basis-of-Design Products: Alvarado Mfg. Co., Inc., 3 Inch Diameter Safety Bollard with
Anchor Package. 800-423-4143 or www.alvaradomfg.com.
7. See Drawings for locations and details.
1. Post: 2-1/4-inch O.D. by 16 gage steel tubing welded to 1/4-inch thick by 5-1/2 inch
diameter steel base plate, include post cap and railing outlets.
2. Rail: 1-3/4-inch O.D. by 16 gage steel tubing.
3. Anchor each post to floor with expansion anchor bolts. Anchor Package for each post
consists of four (4) each SB anchors with 3/8 - 16 by 2-1/2 inch HHCS and washers.
Each SB anchor is a 1-1/2 inch long by 5/8 inch diameter single-expansion system that
expands to lock the anchor bolt securely in place.
4. Anchor rail to post with a vibration resistant self-locking bolt and railing setscrews.
5. 16 gage steel form-fit cover plate for covering post base anchors.
6. Polished chrome post, post cap, rails, and cover plate.
9. Basis-of-Design Products: Alvarado Mfg. Co., Inc., Vogue Post - Type V and Rail with
Anchor Package. 800-423-4143 or www.alvaradomfg.com.
10. See Drawings for locations and details.
1. 4-inch wide, 11 gage, steel channel with capped ends and, where required,
interconnecting bolt-together assembly and angle ends.
2. 4.5-inch wide spring post support, 0.180 inch thick spring steel treated to RC40 to RC50
that forms a half-circle at its base.
3. Anchor cart bumper to floor with double Keystone expansion anchor bolts. Anchor
Package consists of one (1) type SA anchors with 5/8 - 11 by 3-1/4 inch HHCS and
washer at each support foot. Each SA anchor is a 2-3/4 inch long by 1 inch diameter
double-expansion system that expands to lock the anchor bolt securely in place.
4. Where cart bumper is used to protect sliding doors provide bumper of length not less
than door width.
5. Polished chrome finish.
6. Basis-of-Design Products: Alvarado Mfg. Co., Inc., Model CB, Cart Bumper System and
Model SA floor anchors. 800-423-4143 or www.alvaradomfg.com.
7. See Drawings for locations and details.
1. Rail: 1.75-inch diameter by 16 gage stainless steel tubing capped at each end with force
fit, impact resistant plastic end caps designed to fit and adhere tightly into the rail.
2. Stem assembly supporting rail: Fully welded assembly constructed of tapered 2-inch by
4-inch long stainless steel tube welded at 90 degrees to a 0.75-inch diameter by 7.5-inch
long stainless steel rod for insertion into floor socket. Grind welds smooth.
a. Provide two 1/4-20 set screws on the underside of each tube to secure stem
assembly to rail.
b. Provide 2 stems with each 2-foot, 4-foot, and 6-foot bumper rail length; 3 stems
with each 8-foot and 10-foot bumper rail length; and 4 stems with each 12-foot
bumper rail length.
3. Floor Socket: 0.765-inch I.D. by 2.8-inch long stainless steel tube with a 1.7-inch
diameter flange at top end. Socket tube is sealed at bottom end.
4. Stainless Steel: Type 304 with No.4 polished satin finish.
5. Install bumper rail system with top of rail 6.75 inches above floor in accordance with
manufacturers written directions and instructions.
6. See Drawings for locations and details.
B. Basis-of-Design Products: Alvarado Mfg. Co., Inc., Stainless Steel Bumper, Model SSB. 800-
423-4143 or www.alvaradomfg.com.
A. Salient Characteristics:
5. Finish: Transparent finish over stain as specified in Division 09 Section Painting and
color as indicated on drawings.
6. See Drawings for locations and details.
A. Salient Characteristics:
2.11 FABRICATION
A. Fabricate impact-resistant wall protection units to comply with requirements indicated for
design, dimensions, and member sizes, including thicknesses of components.
A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
1. Remove tool and die marks and stretch lines, or blend into finish.
2. Grind and polish surfaces to produce uniform finish, free of cross scratches.
3. Run grain of directional finishes with long dimension of each piece.
4. When polishing is completed, passivate and rinse surfaces. Remove embedded foreign
matter and leave surfaces chemically clean.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and wall areas, with Installer present, for compliance with requirements for
installation tolerances and other conditions affecting performance of work.
1. For impact-resistant wall protection units attached with adhesive, verify compatibility with
and suitability of substrates, including compatibility with existing finishes or primers.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Complete finishing operations, before installing wall and equipment guards, including painting,
before installing impact-resistant wall protection system components.
B. Before installation, clean substrate to remove dust, debris, and loose particles.
3.3 INSTALLATION
A. General
1. Install wall and equipment guard units level, plumb, and true to line without distortions.
Do not use materials with chips, cracks, voids, stains, or other defects that might be
visible in the finished Work.
2. Provide splices, mounting hardware, anchors, and other accessories required for a
complete installation.
3. Install wall and equipment guards and impact-resistant wall protection units in locations
and at mounting heights indicated on Drawings.
4. Impact-Resistant Wall Covering: Install top and edge moldings, corners, and divider bars
as required for a complete installation.
3.4 CLEANING
A. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair
galvanizing to comply with ASTM A 780.
B. Impact Resistant Wall covering: Remove excess adhesive using methods and materials
recommended in writing by manufacturer.
END OF SECTION
DESIGN CRITERIA
2. This Section identifies toilet accessories typically used in commissary facilities. While Guide
Specifications are continually being updated to incorporate the specified manufacturers product
improvements, it is the A/Es responsibility to verify with the basis-of-design manufacturer that each
product specification is current. Provide written notification to the DeCA Project Manager when this
verification has been completed.
3. Toilet accessories are assigned Mark Numbers for coordination and identification on contract
drawings. It may be necessary to add or delete items on a project. A "Toilet Accessory Schedule"
shall be developed for each project that identifies Mark Number, Description, and Mounting Height.
Coordinate accessory locations and mounting heights with other design disciplines (i.e., electrical
receptacles, automatic flush valves, etc.). Contract documents shall clearly identify requirement for
wood blocking (or other material) within metal stud framed walls for proper attachment and support of
accessories.
NOTE: Toilet accessories listed in the guide specification do not include paper towel or toilet tissue
dispensers, within customer and employee toilet rooms, because DeCAs maintenance service
agreement requires that the service provider furnish and install these items. Provide paper towel
dispensers and soap dispensers as part of 4S00 hand wash sinks. Show locations for all accessories
including accessories provided by others on drawings.
Mark "A": Grab Bar Mounted Horizontally, Parallel to Side of Water Closet:
Mark "B": Grab Bar Mounted Horizontally, Parallel to Back of Water Closet:
Use in handicap accessible toilet compartments only.
Mark "C": Stainless Steel, Angle Framed Mirror:
Use above wall hung lavatories in both customer and employee toilet rooms. Mounting heights
shall comply with manufacturer recommendations for both standard and handicap accessible
locations.
Mark "D": Liquid Soap Dispenser, Deck Mounted:
Use at wall hung lavatories. Coordinate with lavatory specification to confirm that lavatory is
furnished with mounting hole for soap dispenser, and that spout dispenser is proper length for
lavatory specified.
Mark "E": Waste Receptacle, Semi-Recessed:
Use in toilet rooms with metal stud framed walls.
Locate on wall adjacent to lavatories. Provide a minimum of one unit for every three lavatories.
Mark "F": Waste Receptacle, Surface Mounted:
Use at CMU wall locations and other locations where semi-recessed mounting is not possible.
Locate on wall adjacent to lavatories. Provide a minimum of one unit for every three lavatories.
Mark "G": Sanitary Napkin Disposal Unit, Partition-Mounted, Dual Access Type:
Use in female toilet rooms containing two or more toilet compartments.
June 2011 10 28 13 1
DeCA DESIGN CRITERIA HANDBOOK
10 28 13 TOILET ACCESSORIES
END OF SECTION
June 2011 10 28 13 2
SECTION 10 28 13
TOILET ACCESSORIES
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 SUBMITTALS
A. Product Data: For each type of product indicated. Include the following:
B. Product Schedule: Indicating types, quantities, sizes, and installation locations by room of each
accessory required.
C. Submittal List:
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
by a qualified testing agency, and marked for intended location and application.
1.4 COORDINATION
A. Coordinate accessory locations with other work to prevent interference with clearances required
for access by disabled persons, proper installation, adjustment, operation, cleaning, and
servicing of accessories.
B. Deliver inserts and anchoring devices set into concrete or masonry as required to prevent
delaying the Work.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
2.2 MATERIALS
A. Stainless Steel: ASTM A 666, Type 304, with No. 4 finish (satin), in 0.031-inch minimum
nominal thickness, unless otherwise indicated.
B. Steel Sheet: ASTM A 1008/A 1008M, Designation CS (cold rolled, commercial steel),
0.036-inch minimum nominal thickness.
C. Galvanized Steel Sheet: ASTM A 653/A 653M, with G60 hot-dip zinc coating.
D. Mirrors: ASTM C 1503, Mirror Glazing Quality, clear-glass mirrors, nominal 0.236-inch thick.
E. Galvanized Steel Mounting Devices: ASTM A 153/A 153M, hot-dip galvanized after fabrication.
F. Fasteners: Screws, bolts, and other devices of same material as accessory unit, tamper and
theft resistant when exposed, and of galvanized steel when concealed.
2.3 FABRICATION
D. Framed Glass-Mirror Units: Fabricate frames for glass-mirror units to accommodate glass edge
protection material. Provide mirror backing and support system that permits rigid, tamper-
resistant glass installation and prevents moisture accumulation.
1. Provide galvanized steel backing sheet, not less than 0.034 inch and full mirror size, with
nonabsorptive filler material. Corrugated cardboard is not an acceptable filler material.
E. Mirror-Unit Hangers: Provide one of the following mirror-unit mounting systems that permits
rigid, tamper- and theft-resistant installation, as follows:
F. Keys: Provide universal keys for internal access to accessories for servicing and resupplying.
Provide minimum of six keys to Government's representative.
1. Where this designation is indicated on Drawings, provide mirror unit complying with the
following:
1. Where this designation is indicated on Drawings, provide soap dispenser complying with
the following:
1. Where this designation is indicated, provide stainless-steel unit complying with the
following:
1. General:
a. Warm air, rapid drying, energy efficient electric hand dryer; entire dryer internally
grounded; completely sealed control assembly and optics; automatic, activated by
infrared optical sensor; operates while hands are under blower.
2. Salient Characteristics:
C. Salient Characteristics:
PART 3 - EXECUTION
3.1 INSTALLATION
B. Secure mirrors to walls in concealed, tamper-resistant manner with special hangers, toggle
bolts, or screws. Set units level, plumb, and square at locations indicated, according to
manufacturer's written instructions for substrate indicated.
C. Install grab bars to withstand a downward load of at least 250 lbf, when tested according to
method in ASTM F 446.
A. General: Adjust accessories for unencumbered, smooth operation and verify that mechanisms
function properly. Replace damaged or defective items.
END OF SECTION
DESIGN CRITERIA
2. This Section includes portable fire extinguishers, fire extinguisher cabinets, and fire protection
accessories.
3. Design and placement of fire extinguishers shall be in accordance with NFPA 10 "Standard for Portable
Fire Extinguishers" with locations clearly identified on the Drawings.
4. Standard 10 LB A-B-C multi-purpose chemical (U/L Rating 4-A:60-B:C) extinguishers shall be located
throughout the building with a maximum 75' travel distance to each. Extinguishers located in customer
and administrative office areas shall be provided with semi-recessed cabinets. Extinguishers located in
warehouse and other similar areas shall be mounted on walls with manufacturer standard fire
extinguisher hooks.
5. Commissary facilities with Deli Departments containing 1D09 rotisserie and 1D10-B combi-steamer
ovens (one or both) require a vented hood with built-in fire suppression system. A 1.6-gal wet chemical
(U/L Rating 2-A:1-B:C:K) extinguisher is required to supplement this system, and shall be located in the
immediate vicinity of the hood.
6. Coordinate placement of extinguisher cabinets with wall mounted wood bumper rails, hose bibs, and
other concealed utilities within walls.
7. Locate fire extinguisher cabinets to comply with the guidelines of the ABA Accessibility Standard for
Department of Defense Facilities.
END OF SECTION
June 2011 10 44 00 1
SECTION 10 44 00
FIRE PROTECTION SPECIALTIES
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
B. Submittal List:
A. Source Limitations:
1. Obtain fire extinguishers and cabinets through one source from a single manufacturer.
B. NFPA Compliance:
1. Fabricate, install, and label fire extinguishers to comply with NFPA 10, "Standard for
Portable Fire Extinguishers."
1. Install fire extinguisher cabinets in compliance with the ABA Accessibility Standard for
Department of Defense Facilities.
D. Fire Extinguishers:
1. Listed and labeled for type, rating, and classification by an independent testing agency
acceptable to authorities having jurisdiction.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design Products:
c. Signage:
1) Wall surface: Decal, 11-3/4- by 3-1/2-inches, vertical, red and white, FIRE
EXTINGUISHER, #DRFA.
2) Cabinet Door: Die cut, 3/4 by 18-inches, vertical, red, FIRE
EXTINGUISHER, #FELVR.
2.2 MATERIALS
1. Provide manufacturer's standard box (tub), with trim, frame, door, and hardware to suit
cabinet type, trim style, and door style indicated. Weld joints and grind smooth. Miter
and weld perimeter door frames.
2. Cabinet Metal: Enameled-steel sheet.
3. Cabinet Type: Suitable for fire extinguisher.
4. Cabinet Mounting: Suitable for the following mounting conditions:
5. Cabinet Trim Style: Fabricate cabinet trim in one piece with corners mitered, welded, and
ground smooth.
a. Exposed Trim: One-piece combination trim and perimeter door frame overlapping
surrounding wall surface with exposed trim face and wall return at outer edge
(backbend).
b. Return trim with rolled edge.
6. Cabinet Trim Material: Manufacturer's standard, same metal and finish as door.
7. Door Material: Manufacturer's standard, steel sheet.
8. Door Style: Manufacturer's standard design, flush opaque panel, frameless, with no
exposed hinges.
9. Door Construction: Fabricate doors according to manufacturer's standards, of materials
indicated, and coordinated with cabinet types and trim styles selected.
10. Door Hardware: Provide manufacturer's standard door-operating hardware of proper
type for cabinet type, trim style, and door material and style indicated. Provide either
lever handle with cam-action latch, or exposed or concealed door pull and friction latch.
Provide concealed or continuous-type hinge permitting door to open 180 degrees.
2.5 ACCESSORIES
A. Mounting Brackets:
A. General:
1. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
2. Protect mechanical finishes on exposed surfaces from damage by applying a strippable,
temporary protective covering before shipping.
3. Finish fire protection cabinets after assembly.
1. Variations in appearance of abutting or adjacent pieces are acceptable if they are within
one-half of the range of approved Samples. Noticeable variations in the same piece are
not acceptable. Variations in appearance of other components are acceptable if they are
within the range of approved Samples and are assembled or installed to minimize
contrast.
A. Surface Preparation:
1. Clean surfaces of dirt, oil, grease, mill scale, rust, and other contaminants that could
impair paint bond using manufacturer's standard methods.
B. Baked-Enamel Finish:
a. Color:
3.1 EXAMINATION
A. General:
1. Examine walls and partitions for suitable framing depth and blocking where recessed and
semirecessed cabinets are to be installed.
2. Examine fire extinguishers for proper charging and tagging.
3. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. General:
a. Prepare recesses for cabinets as required by type and size of cabinet and trim
style.
b. Fasten mounting brackets to structure and cabinets, square and plumb.
c. Fasten cabinets to structure, square and plumb.
A. Adjust cabinet doors that do not swing or operate freely. Refinish or replace cabinets and doors
damaged during installation. Provide final protection and maintain conditions that ensure that
cabinets and doors are without damage or deterioration at the time of final acceptance.
END OF SECTION
DESIGN CRITERIA
2. While Guide Specifications are continually being updated to incorporate the specified manufacturers
product improvements, it is the A/Es responsibility to verify with the basis-of-design manufacturer that
each product specification is current. Provide written notification to the DeCA Project Manager when
this verification has been completed.
3. Metal lockers are to be provided in employee locker rooms and break rooms (employee and carry-out
return personnel). Location and quantity will be determined during the design charrette process.
Lockers are typically single tier and double tier configurations with perforated diamond mesh fronts and
sides with solid sloped metal tops. Lockers are to be set-on a raised concrete base in locker rooms and
break rooms with permanent locker configurations. Use built-up wood bases in rooms where locker
configuration could be revised. Cover exposed fronts and sides of locker bases with finish base material
matching that used in room where lockers are located. Height of bases shall match height of finish base
material.
4. The ABA Accessibility Standard for Department of Defense Facilities requires that when lockers are
provided in any room, at least 5 percent, but no fewer than one, shall be handicap accessible.
Lockers shall be equipped with shelves and hooks to accommodate both forward reach and parallel
reach wheelchair approach.
Forward Reach Requirements: All single tier lockers shall have hat/book shelf and coat hooks
located no more than 48" above the finished floor. One additional shelf shall be placed near the
bottom of the locker so that it is no lower than 15" above the finished floor.
Parallel Reach Requirements: All single tier lockers shall have hat/book shelf and coat hooks located
no more than 54" above the finished floor. One additional shelf shall be placed near the bottom of the
locker so that it is no lower than 9" above the finished floor.
An accessible bench is required wherever accessible lockers are provided. Benches shall have
seats that are 42" long minimum, 20" deep minimum (24" deep maximum), and 17" minimum (19"
maximum) above finished floor. Clear floor space shall be provided and shall be positioned at the
end of the bench seat and parallel to the short axis of the bench. The bench shall provide for back
support or shall be affixed to a wall. DeCA standard design is to provide a locker bench that is
located along a wall and secured to the floor.
5. Coordinate locker locations with other design disciplines (i.e., concrete bases, electrical receptacles,
wall thermostats, etc.). Contract documents shall clearly identify requirement for wood blocking (or
other material) within metal stud framed walls for proper attachment and support of lockers.
END OF SECTION
June 2011 10 51 13 1
SECTION 10 51 13
METAL LOCKERS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 DEFINITIONS
1.3 SUBMITTALS
A. Product Data:
B. Submittal List:
A. Installer Qualifications:
1. Obtain metal lockers, benches, and accessories through one source from a single
manufacturer.
C. Regulatory Requirements:
1. Where metal lockers and benches are indicated to comply with accessibility
requirements, comply with the ABA Accessibility Standard for Department of Defense
Facilities
A. Do not deliver metal lockers and benches until spaces to receive them are clean, dry, and ready
for metal locker and bench installation. Deliver master and control keys to Contracting Officer at
beneficial occupancy by the Government.
A. Field Measurements:
1. Verify the following by field measurements before fabrication and indicate measurements
on Shop Drawings:
a. Concealed framing, blocking, and reinforcements that support metal lockers before
they are enclosed.
1.7 COORDINATION
A. Coordinate size and location of concrete and wood bases for metal lockers. Coordinate sizes
and locations of framing, blocking, furring, reinforcements, and other related units of Work
specified in other Sections to ensure that metal lockers can be supported and installed as
indicated.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. ASTM A 1008, Commercial Steel (CS) Type B, suitable for exposed applications.
B. Fasteners:
1. Zinc-plated or nickel-plated steel, slotless-type exposed bolt heads, and self-locking nuts
or lock washers for nuts on moving parts.
C. Anchors:
1. Select material, type, size, and finish required for secure anchorage to each substrate.
2. Provide toothed-steel or lead expansion sleeves for drilled-in-place anchors.
2.3 4L01 - SINGLE TIER LOCKER, ONE DOOR, ONE LOCKER WIDE LOCKER, CLOTHING
SINGLE TIER
A. Basis-of-Design Product:
B. Locker Arrangement:
1. Single tier.
2. Size of each locker: 15 inches wide by 18 inches deep by 72 inches high.
C. Body:
1. Assembled by welding body components together. Fabricate from cold-rolled steel sheet
with thicknesses as follows:
a. Tops and Bottoms: 0.0528 inch thick, with single bend at edges.
b. Backs: 0.0528-inch- thick.
D. Perforated Sides:
1. Fabricated from 0.0528-inch- thick, cold-rolled steel sheet with manufacturer's standard
diamond perforations.
E. Frames:
1. Channel formed; fabricated from 0.0528-inch- thick, cold-rolled steel sheet or 0.0966-
inch- thick steel angles; lapped and factory welded at corners; with top and bottom main
frames factory welded into vertical main frames. Form continuous, integral door strike full
height on vertical main frames.
F. Perforated Doors:
1. One-piece, fabricated from 0.0677-inch- thick, cold-rolled steel sheet with manufacturer's
standard diamond perforations; formed into channel shape with double bend at vertical
edges and with right-angle single bend at horizontal edges.
1. Welded to door and attached to door frame with not less than 2 factory-installed rivets per
hinge that are completely concealed and tamper resistant when door is closed; fabricated
to swing 180 degrees.
a. Knuckle Hinges: Steel, full loop, 5 knuckles, tight pin; 2 inches high. Provide 3
hinges for each door.
1. Stainless-steel cup with integral door pull, recessed so locking device does not protrude
beyond face of door; pry resistant.
a. Multipoint Latching: Finger-lift latch control designed for use with padlock locking
capability; positive automatic and prelocking.
1) Latch Hooks: Equip doors with 3 latch hooks; fabricated from minimum
0.1116-inch- thick steel; welded to full-height door strikes; with resilient
silencer on each latch hook.
2) Latching Mechanism: Manufacturer's standard rattle-free latching
mechanism and moving components isolated to prevent metal-to-metal
contact, and incorporating a prelocking device that allows locker door to be
locked while door is open and then closed without unlocking or damaging
lock or latching mechanism.
I. Cylinder Locks:
1. Built-in, flush, cam locks with five-pin tumbler keyway, keyed separately and master
keyed. Furnish two change keys for each lock and five master keys.
J. Equipment:
1. Equip each metal locker with identification plate and the following, unless otherwise
indicated:
a. Shelf, one double-prong back hook and two single-prong wall hooks.
b. Hooks: Steel, formed with ball points, zinc-plated and attached with two bolts or
rivets.
c. Coat Rods: For each compartment of single-tier metal lockers.
K. Accessories:
1. Continuous Sloping Tops: Fabricated from minimum 0.0428-inch- thick, cold-rolled steel
sheet; approximately 20-degree pitch.
1. Baked enamel.
2. Color: Jet Black #94.
A. Basis-of-Design Product:
B. Locker Arrangement:
1. Single tier.
2. Size of each locker: 15 inches wide by 18 inches deep by 72 inches high.
C. Body:
1. Assembled by welding body components together. Fabricate from cold-rolled steel sheet
with thicknesses as follows:
a. Tops and Bottoms: 0.0528 inch thick, with single bend at edges.
b. Backs: 0.0528 inch thick.
D. Perforated Sides:
1. Fabricated from 0.0528-inch- thick, cold-rolled steel sheet with manufacturer's standard
diamond perforations.
E. Frames:
1. Channel formed; fabricated from 0.0528-inch- thick, cold-rolled steel sheet or 0.0966-
inch- thick steel angles; lapped and factory welded at corners; with top and bottom main
frames factory welded into vertical main frames. Form continuous, integral door strike full
height on vertical main frames.
F. Perforated Doors:
1. One-piece, fabricated from 0.0677-inch- thick, cold-rolled steel sheet with manufacturer's
standard diamond perforations; formed into channel shape with double bend at vertical
edges and with right-angle single bend at horizontal edges.
G. Hinges:
1. Welded to door and attached to door frame with not less than 2 factory-installed rivets per
hinge that are completely concealed and tamper resistant when door is closed; fabricated
to swing 180 degrees.
a. Knuckle Hinges: Steel, full loop, 5 knuckles, tight pin; 2 inches high. Provide 3
hinges for each door.
1. Stainless-steel cup with integral door pull, recessed so locking device does not protrude
beyond face of door; pry resistant.
a. Multipoint Latching: Finger-lift latch control designed for use with padlock locking
capability; positive automatic and prelocking.
1) Latch Hooks: Equip doors with 3 latch hooks; fabricated from minimum
0.1116-inch- thick steel; welded to full-height door strikes; with resilient
silencer on each latch hook.
2) Latching Mechanism: Manufacturer's standard rattle-free latching
mechanism and moving components isolated to prevent metal-to-metal
contact, and incorporating a prelocking device that allows locker door to be
locked while door is open and then closed without unlocking or damaging
lock or latching mechanism.
I. Cylinder Locks:
1. Built-in, flush, cam locks with five-pin tumbler keyway, keyed separately and master
keyed. Furnish two change keys for each lock and five master keys.
J. Equipment:
1. Equip each metal locker with identification plate and the following, unless otherwise
indicated:
a. Two hat/book shelves, one double-prong back hook and two single-prong wall
hooks.
b. Hooks: Steel, formed with ball points, zinc-plated and attached with two bolts or
rivets.
c. Height of equipment from finished floor for forward reach wheelchair approach:
d. Height of equipment from finished floor for parallel reach wheelchair approach:
K. Accessories:
1. Continuous Sloping Tops: Fabricated from minimum 0.0428-inch- thick, cold-rolled steel
sheet; approximately 20-degree pitch.
L. Finish:
1. Baked enamel.
2. Color(s): As indicated.
2.5 4L02 TWO TIER LOCKER, TWO DOORS, ONE LOCKER WIDE LOCKER, CLOTHING
DOUBLE TIER
A. Basis-of-Design Product:
B. Locker Arrangement:
1. Double tier.
2. Size of each locker: 15 inches wide by 18 inches deep by 72 inches high.
3. Size of each locker compartment: 15 inches wide by 18 inches deep by 36 inches high.
C. Body:
1. Assembled by welding body components together. Fabricate from cold-rolled steel sheet
with thicknesses as follows:
a. Tops and Bottoms: 0.0528 inch thick, with single bend at edges.
b. Backs: 0.0528-inch- thick.
D. Perforated Sides:
1. Fabricated from 0.0528-inch- thick, cold-rolled steel sheet with manufacturer's standard
diamond perforations.
E. Frames:
1. Channel formed; fabricated from 0.0528-inch- thick, cold-rolled steel sheet or 0.0966-
inch- thick steel angles; lapped and factory welded at corners; with top and bottom main
frames factory welded into vertical main frames. Form continuous, integral door strike full
height on vertical main frames.
F. Perforated Doors:
1. One-piece, fabricated from 0.0677-inch- thick, cold-rolled steel sheet with manufacturer's
standard diamond perforations; formed into channel shape with double bend at vertical
edges and with right-angle single bend at horizontal edges.
G. Hinges:
1. Welded to door and attached to door frame with not less than 2 factory-installed rivets per
hinge that are completely concealed and tamper resistant when door is closed; fabricated
to swing 180 degrees.
1. Stainless-steel cup with integral door pull, recessed so locking device does not protrude
beyond face of door; pry resistant.
a. Multipoint Latching: Finger-lift latch control designed for use with built-in cylinder
locks; positive automatic and prelocking.
1) Latch Hooks: Equip doors with 2 latch hooks; fabricated from minimum
0.1116-inch- thick steel; welded to full-height door strikes; with resilient
silencer on each latch hook.
2) Latching Mechanism: Manufacturer's standard rattle-free latching
mechanism and moving components isolated to prevent metal-to-metal
contact, and incorporating a prelocking device that allows locker door to be
locked while door is open and then closed without unlocking or damaging
lock or latching mechanism.
I. Cylinder Locks:
1. Built-in, flush, cam locks with five-pin tumbler keyway, keyed separately and master
keyed. Furnish two change keys for each lock and five master keys.
J. Equipment:
1. Equip each metal locker with identification plate and the following, unless otherwise
indicated:
a. Double-Tier Units: One double-prong back hook and two single-prong wall hooks.
b. Hooks: Steel, formed with ball points, zinc-plated and attached with two bolts or
rivets.
K. Accessories:
1. Continuous Sloping Tops: Fabricated from minimum 0.0428-inch- thick, cold-rolled steel
sheet; approximately 20-degree pitch.
L. Finish:
1. Baked enamel.
a. Color(s): As indicated.
A. Bench Height:
1. Provide bench units with overall assembly seat height of 17 inches minimum (19 inches
maximum) above finished floor.
B. Bench Tops:
1. Manufacturers standard 1-piece units with laminated maple top 24 inches wide by 1-1/4
inches thick by 48 inches long. Round all corners, sand smooth, and apply
manufacturers standard transparent sealer coating.
C. Fixed Pedestals:
1. Manufacturer's standard supports, with predrilled fastener holes for attaching bench top
and anchoring to floor, complete with fasteners and anchors, and as follows:
a. Tubular Steel: 1-1/4-inch- diameter steel tubing, with 0.1265-inch thick steel
flanges welded at top and base; with baked-enamel finish; anchored with exposed
fasteners.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine walls, floors, and support bases, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting performance of work.
Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. General:
1. Install level, plumb, and true; shim as required, using concealed shims.
2. Anchor locker runs at ends and at intervals recommended by manufacturer, but not more
than 36 inches o.c. Install anchors through backup reinforcing plates, channels, or
blocking as required to prevent metal distortion, using concealed fasteners.
3. Anchor single rows of metal lockers to walls near top and bottom of lockers.
1. Connect groups of all-welded metal lockers together with standard fasteners, with no
exposed fasteners on face frames.
1. Fit exposed connections of trim, fillers, and closures accurately together to form tight,
hairline joints, with concealed fasteners and splice plates.
1) Each locker shall have a polished aluminum number plate with black
numerals not less than 1/2 inch high. Plates shall be attached with at least
two aluminum rivets to the lower surface within the recessed handle pocket.
Number lockers in sequential order.
d. Attach filler panels with concealed fasteners. Locate fillers panels to close
openings between lockers and adjacent walls.
e. Attach sloping top units to metal lockers, with closures at exposed ends.
f. Provide perforated end panels, matching locker sides, at ends of nonrecessed
metal lockers.
D. Fixed Benches:
A. General:
1. Clean, lubricate, and adjust hardware: Adjust doors and latches to operate easily without
binding. Verify that integral locking devices operate properly.
2. Protect metal lockers from damage, abuse, dust, dirt, stain, or paint. Do not permit metal
locker use during construction.
3. Touch up marred finishes, or replace metal lockers that cannot be restored to factory-
finished appearance. Use only materials and procedures recommended or furnished by
metal locker manufacturer.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each product specification is current. Provide written notification to the DeCA
Project Manager when this verification has been completed.
B. Rotating files are used to display damaged (i.e., salvaged) merchandise that is for sale to
customers. Typically the unit is located within a cased gypsum wallboard opening between the
Damaged Merchandise Room (RM. 23) and the Damaged Merchandise Sales Niche (RM. 24).
While one side of cabinet is accessible to customers for product display, the opposite side is open to
the salvage room for re-stocking.
C. A typical damaged merchandise display case assembly consists of a single starter unit with one
add-on unit. The starter unit is 45 " wide. The add-on unit is 38 " wide. If a larger damaged
merchandise display space is available, each add-on unit will increase overall width of assembly
by 38 ". Only one starter unit is required per assembly. Locate foot pedal operator on salvage
room side of unit. Provide cased opening, allowing +/- 2 " clearance on both sides and top of
assembled unit for construction / installation tolerances. Provide closures at same matching
sales area dcor.
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
3. CONTRACT DOCUMENT PHASE RESPONSIBILITIES.
A. The Contract Documents shall include the equipment list developed during the design charrette
process, clearly identifying responsibility for all equipment. To facilitate and expedite technical
review by DeCA, the Contract Documents shall use DeCA equipment item numbers to key both
the contractor-furnished and government-furnished equipment to the Drawings.
B. If applicable, DeCA will provide the A/E with a list of existing government-owned equipment to be
re-used in the new or renovated facility. The A/E shall evaluate the identified equipment to
determine suitability, and confirm utility requirements for removal and relocation into the new or
renovated facility. If applicable, list or note on the Contract Specifications/Drawings any
equipment to be salvaged or relocated by the construction contractor.
C. On addition / alteration projects, provide specific guidance on the Contract Documents regarding
disposition of salvaged equipment (i.e., will it become the property of the contractor or turned
over to DRMO). Turn-in of salvaged equipment is the responsibility of the Commissary Store
Director or designated Government representative. When the contractor is required to remove
and/or otherwise dispose of commissary equipment such as display and storage shelving, display
cases, refrigeration equipment and walk-in-boxes, the contractor will be required to sign DD Form
1348-1 "Receipt Release Documents" prepared by the Commissary Store Director or designated
Government representative. The A/E shall clearly identify any equipment that will become the
June 2011 10 56 23 1
DeCA DESIGN CRITERIA HANDBOOK
10 56 23 ROTATING MODULAR SYSTEM
property of the contractor for salvage, and clearly identify that all other operational equipment
shall remain the property of DeCA.
D. Verify that adequate space is available (both floor space and ceiling clearance) for all specified
equipment.
END OF SECTION
June 2011 10 56 23 2
SECTION 10 56 23
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
A. Seismic:
1.3 SUBMITTALS
A. Product Data:
1. For each item of equipment required, including the manufacturer's standard details and
installation and maintenance instructions.
B. Submittal List:
A. Installer Qualifications:
1. Obtain rotating modular system through one source from a single manufacturer.
1.5 WARRANTY
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. General:
1. Rotating modular system installed through wall between salvage room and damaged
merchandise sales niche. System shall consist of one standard starter unit and standard
add-on unit(s) placed side-by-side. Each individual unit capable of being rotated
manually by use of foot pedal and locked from inside salvage room. When unlocked and
rotated 180 degrees, each unit displays merchandise to the sales area while the back
side is being restocked.
B. Salient Characteristics:
a. Adjustable reversible metal shelves: R-W No. 902 legal size. Five shelves per side
(10 shelves total) each unit.
b. 1-3/4-inch shelf height increment adjustment.
c. Closing strips to cover rotation space between unit and wall, panel and another
unit. Match unit finish.
d. Extended canopy tops over rotor top to cover the rotation space behind the unit.
e. Full length centerpanel between back-to-back shelves.
1) 12 gage steel.
2) Connect base and rotor bottom with 1/2 inch, minimum, diameter carriage
bolt.
3) Secure assembly with locknut.
4) Fabricate with an oil impregnated bronze bushing for permanent lubrication
to carriage bolt rotation.
5) Install raceways in both base and rotor bottom to capture ball bearings and
protect rotating components from excessive and unusual wear,
burnishment, and fatigue.
6) 28-inch diameter, minimum, press formed raceways for legal size units.
Smaller diameter raceways are not acceptable because they will not control
or maintain the cabinet center of gravity during unbalanced loading and
rotation.
2. Dimensions:
C. Basis-of-Design Product: Richards-Wilcox, Inc., High Density, Multi Media Rotary Filing
System. (800) 277-1699 or www.timestwo.com.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine openings and surfaces in and on which rotating modular systems are to be installed.
Do not proceed with work until unsatisfactory conditions are corrected.
3.2 INSTALLATION
A. Install items where indicated in accordance with manufacturers assembly and installation
Drawings.
A. Adjust rotating modular systems for proper operation. After completion of installation, clean and
polish all exposed surfaces.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each product specification is current. Provide written notification to the DeCA
Project Manager when this verification has been completed.
B. Storage racks typically provided in Commissary facilities include the following:
1. 2R16 - Storage Rack, Shelf, Galvanized:
Racks are hot dipped galvanized steel and used in refrigerated spaces. Upright frames are
30" deep by 96" high and spaced 8'-3" center-to-center. Load beams are 96" long.
Assembled units have three shelving levels (24", 60", and 96") with wire mesh decking on
each level.
2. 2R17 - Storage Rack, Pallet, Painted:
Racks are painted steel and used in receiving/staging areas of a commissary for storage of
palletized materials. Upright frames are 42" deep by 96" high and spaced 8'-3" center-to-
center. Load beams are 96" long. Assembled units have two shelving levels (12" and 72").
The end upright frame of each row/set of 2R17 racks is 96" high.
3. 2R19 - Storage Rack, Pallet, Painted:
Racks are painted steel and used in receiving/staging areas of a commissary for storage of
palletized materials. Upright frames are 42" deep by 120" high and spaced 8'-3" center-to-
center. Load beams are 96" long. Assembled units have two shelving levels (60" and 120")
in addition to a ground floor level. The end upright frame of each row/set of 2R19 racks is
132" high.
4. 2R24 - Shelving, Food Storage:
Racks are stainless steel and used in smaller cold storage rooms and other small storage
areas where product is typically hand stocked. Assembled units are 48" wide by 24" deep by
72" high with five shelving levels. Each rack is provided with swivel casters.
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
3. CONTRACT DOCUMENT PHASE RESPONSIBILITIES
A. The Contract Documents shall include the equipment list developed during the design charrette
process, clearly identifying responsibility for all equipment. To facilitate and expedite technical
review by DeCA, the Contract Documents shall use DeCA equipment item numbers to key both
the contractor-furnished and government-furnished equipment to the Drawings.
June 2011 10 56 29 1
DeCA DESIGN CRITERIA HANDBOOK
10 56 29 STORAGE RACKS
B. If applicable, DeCA will provide the A/E with a list of existing government-owned equipment to be
re-used in the new or renovated facility. The A/E shall evaluate the identified equipment to
determine suitability, and confirm utility requirements for removal and relocation into the new or
renovated facility. If applicable, list or note on the Contract Specifications/Drawings any
equipment to be salvaged or relocated by the Construction Contractor.
C. On addition / alteration projects, provide specific guidance on the Contract Documents regarding
disposition of salvaged equipment (i.e., will it become the property of the Contractor or turned
over to DRMO). Turn-in of salvaged equipment is the responsibility of the Commissary Store
Director or designated Government representative. When the Contractor is required to remove
and/or otherwise dispose of commissary equipment such as display and storage shelving, display
cases, refrigeration equipment and walk-in-boxes, the Contractor will be required to sign DD
Form 1348-1 Receipt Release Documents prepared by the Commissary Store Director or
designated Government representative. The A/E shall clearly identify any equipment that will
become the property of the Contractor for salvage, and clearly identify that all other operational
equipment shall remain the property of DeCA.
D. Verify that adequate space is available (both floor space and ceiling clearance) for all specified
equipment.
END OF SECTION
June 2011 10 56 29 2
SECTION 10 56 29
STORAGE RACKS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
A. Seismic:
1.3 SUBMITTALS
A. Product Data:
1. For each type of storage rack and accessory specified. Include installation methods for
each type of substrate.
2. Commercial warranty.
B. Submittal List:
2.1 MANUFACTURERS
1. Galvanized steel storage pallet shelves shall be assembled side by side in a row. The
design of all galvanized steel load bearing components, hot rolled to shape, shall be as
specified for design fabrication, and erection of structural steel for buildings, or one of the
suitable ASTM designations for structural quality sheet or strip referenced for the design
of light gauge cold-formed steel structural members. The design and construction of
each load bearing component shall assure that the component is capable of sustaining
the minimum safe load specified with a safety factor not less than 1.65. The storage
shelves shall consist of steel frame uprights, load beams with safety locks, wire mesh
decking, and leveling shims. All components shall be galvanized and designed for use in
refrigerated areas. Storage racks shall have the following salient features:
i. The upright frames and shelf units shall assemble and disassemble, throughout
the height range of the post openings, easily and freely, without the use of bolts or
tools other than a soft hammer, except for permanently fastening to the floor.
Assembled rack shall support without permanent deformation or skewing, the
stresses induced by capacity loads. The beam to post safety lock shall engage
and disengage without the use of tools. Floor plates shall be permanently
fastened to the floor.
1. Loaded pallet steel storage racks shall be assembled side by side in a row. The design
of all steel load bearing components, hot rolled to shape, shall be as specified for design
fabrication, and erection of structural steel for buildings, or one of the suitable ASTM
designations for structural quality sheet or strip referenced for the design of light gauge
cold-formed steel structural members. The design and construction of each load bearing
component shall assure that the component is capable of sustaining the minimum safe
load specified with a safety factor of not less than 1.65. The racks shall consist of steel
frame uprights, load beams, with safety locks, cross bars for front to rear supports, wall
spacers and leveling shims. The racks are intended for storing palletized loads. Color
shall be gray. Storage racks shall have the following salient features:
i. The upright frames and shelf units shall assemble and disassemble, throughout
the height range of the post openings, easily and freely, without the use of bolts or
tools other than a soft hammer, except for permanently fastening to the floor.
Assembled rack shall support without permanent deformation or skewing, the
stresses induced by capacity loads. The beam to post safety lock shall engage
and disengage without the use of tools, and shall be effective at any position.
Floor plates shall be permanently fastened to the floor.
j. Nominal dimensions in inches:
1. Loaded pallet steel storage racks shall be assembled side by side in a row. The design
of all steel load bearing components, hot rolled to shape, shall be as specified for design
fabrication, and erection of structural steel for buildings, or one of the suitable ASTM
designations for structural quality sheet or strip referenced for the design of light gauge
cold-formed steel structural members. The design and construction of each load bearing
component shall assure that the component is capable of sustaining the minimum safe
load specified with a safety factor of not less than 1.65. The racks shall consist of steel
frame uprights, load beams, with safety locks, cross bars for front to rear supports, wall
spacers and leveling shims. The racks are intended for storing palletized loads. Color
shall be gray. Storage racks shall have the following salient features:
j. The upright frames and shelf units shall assemble and disassemble, throughout
the height range of the post openings, easily and freely, without the use of bolts or
tools other than a soft hammer, except for permanently fastening to the floor.
Assembled rack shall support without permanent deformation or skewing, the
stresses induced by capacity loads. The beam to post safety lock shall engage
and disengage without the use of tools, and shall be effective at any position.
Floor plates shall be permanently fastened to the floor.
k. Nominal dimensions in inches:
1. Five adjustable open wire shelves, and swivel/brake stem casters. Shelving shall have
the following salient features:
2. Basis-of-Design Product: AMCO Corp., "AMCO II Wire Shelving PC 72". (800) 621-
4023.
1. Upright, steel wrap-around rack column corner guard. 1/4 inch thick by 24-inches high,
with 3/8 inch thick steel base plate anchored to floor with 3/4 inch diameter double
Keystone expansion anchors. Paint bright OSHA yellow. Install in close proximity to but
separate from item protected.
2. Basis-of-Design Product Manufacturer: Ridg-U-Rak, Inc.
PART 3 - EXECUTION
3.1 INSPECTION
A. General:
1. Check that surfaces to which work will be secured are sound and free of irregularities
interfering with installation.
2. Do not begin installation until unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. General:
END OF SECTION
***********************************************************
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 DEFINITIONS
1.3 DESCRIPTION
C. Warranty Period:
PART 3 - EXECUTION
3.1 STARTUP
A. Contractors shall follow the start-up and initial checkout procedures listed in the Responsibilities
list in this Section and in Division 01 Section General Commissioning Requirements. Division
11 has start-up responsibility and is required to complete systems and sub-systems so they are
fully functional, meeting the design objectives of the Contract Documents. The commissioning
procedures and functional testing do not relieve or lessen this responsibility or shift that
responsibility partially to the Commissioning Agent, Technical Inspector, or Government.
B. Functional testing will generally begin upon completion of a system. Functional testing may
proceed prior to the completion of systems or sub-systems at the discretion of the CO.
Beginning system testing before full completion does not relieve the Contractor from fully
completing the system, including all prefunctional checklists.
A. The following O&M manual requirements are in addition to O&M manual documentation
requirements elsewhere in these specifications.
B. Division 11 shall compile and prepare documentation for all commissioned items and systems
covered in Division 11 and deliver this documentation to the GC for inclusion in the O&M
manuals prior to the training of Government personnel.
A. The GC shall be responsible for training coordination and scheduling to ensure that training is
completed.
B. The QC shall be responsible for reviewing the content and adequacy of the training of
Government personnel for commissioned equipment or systems. TI will verify compliance.
C. The Subcontractor shall have the following training responsibilities for the commissioned
systems:
1. Provide the TI with a training plan four weeks before the planned training.
2. Provide designated Government personnel with comprehensive orientation and training
in the understanding of the systems and the operation and maintenance of each piece of
commissioned equipment.
3. Training shall start with classroom sessions followed by hands-on training on each piece
of equipment.
8. Hands-on training shall include start-up, operation in all modes possible, including
manual, shut-down and any emergency procedures and preventative maintenance for all
pieces of equipment.
9. Fully explain and demonstrate the operation, function and overrides of any local
packaged controls, not controlled by the central control system.
10. Training shall occur after functional testing is complete, unless approved otherwise by the
Project Manager.
11. Minimum Duration of Training. Subcontractor shall provide 8 hours of training.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 32, Division 05, and Division 26 Design Criteria and related
Design Standard Plates.
2. General:
A. Truck/Trailer to Wall Relationship: A major consideration in design of recessed receiving areas
for semi-trailer trucks is to prevent the rear top of the trailer from hitting the wall first when
docking. A vertically parallel relationship with the building wall can best be achieved by providing
a pavement surface that permits both front and rear axles to be at the same elevation when
docking. To accommodate typical semi-trailer delivery vehicles (WB-50, WB-65, and WB-67), the
pavement 50'-0" to 55'-0" from the face of the building should be approximately the same
elevation as that adjacent to the building wall. A continuous trench drain, parallel to the building
wall, should be located 26' from the building wall with a pavement slope of 2 percent to this
trench drain. Rear top of trucks on shorter trailers will then, because of slope to drain, be angled
safely away from the wall. Where this optimal dimension cannot be achieved and slopes cannot
be designed to maintain a vertically parallel relationship, thicker dock bumpers must be provided
to prevent impact damage to the building wall. In this event, however, thicker bumpers may
impose requirements for special dock levelers having deeper lip extensions to compensate for
increased bed to dock distance. Tapered dock seals shall also be provided where trailer bed
slope could exceed 2 percent. Refer to Design Standard Plates 11 13 00-01 and 11 13 00-02.
B. Dock Height: Normally, a 48" height from recessed receiving area pavement to staging/receiving
area floor level, in combination with dock leveler, will accommodate most semi-trailer bed
heights. Establish dock height at 47-1/2"; otherwise OSHA requires a guard railing across
opening heights 48" and higher. Refer to Design Standard Plate 11 13 00-03.
C. Slopes: Slopes of 1:50 are considered optimum for all paved and landscaped areas as indicated
except for ramps into recessed areas which shall have minimum slope required, up to a 10
percent maximum. Where ramp must be at or near maximum slope in northern climates, give
special consideration to providing traction for driving wheels; i.e., ribbed surface, snow/ice
melting device, etc.
D. Paving: Pavement in both the recessed and grade level areas shall be 6" minimum thickness
reinforced concrete on compacted, stabilized base, sufficient to withstand a minimum bearing
capacity of 31,900# under tandem axle.
E. Lane Markers: To facilitate accurate backing of semi-trailer vehicles, paint 6" wide guidelines on
receiving area pavement and up dock wall to finish floor level. Specify epoxy type paint that is
specially formulated for use as pavement marking.
3. Loading Dock Equipment shall include following:
A. Dock Bumpers;
B. Dock Levelers;
C. Truck Restraints;
D. Dock Seals;
E. Metal Hoods (above dock seals).
4. Receiving Areas:
A. Equip each overhead receiving door at recessed dock area of commissary with loading dock
equipment listed above. Dock lights shall also be provided at each of these receiving doors as
specified in Division 26.
June 2011 11 13 00 1
DeCA DESIGN CRITERIA HANDBOOK
11 13 00 LOADING DOCK EQUIPMENT
B. Coordinate specified interlocks between dock leveler, overhead door, and truck restraint system.
Dock leveler shall not operate if overhead door is in closed position and dock restraint is not
engaged.
C. Nominal size of dock leveler shall be 6'-0" wide by 8'-0" deep. On projects with narrow receiving
aisles, a nominal 6'-0" wide by 6'-0" deep may be used if approved by the DeCA Project
Manager.
D. Provide Interlocking control to prevent dock leveler from operating when associated door is in
closed position.
E. Laminated tire tread dock bumpers are typically 4-1/2" thick. Increase thickness of bumpers if
site constraints prevent optimal grading at receiving docks as indicated above.
F. Provide dock bumpers at receiving and trash platforms. Provide 24" long bumpers evenly
spaced (approximately 5'-0" apart) so that trash dumpsters or trucks will contact no less than two
bumpers. Refer to Design Standard Plate 11 13 00-03.
G. Provide 8" diameter concrete filled steel pipe bumper posts with domed tops at interior jambs of
overhead doors with dock levelers. Provide 8" diameter concrete filled steel pipe bumper posts
with domed tops at both interior and exterior jambs of overhead door at grade level receiving
areas. Embed posts 18" deep minimum in 18" diameter concrete foundations Depth of
foundation at interior locations shall be 24" minimum. Depth of foundation at exterior locations
shall be 24" minimum or deeper as required to accommodate frost depth.
H. Provide polyethylene thermoplastic sleeves over interior bumper posts (located in non-customer
areas). Color shall be "safety yellow". Refer to Section 05 50 00 for further guidance.
Coordinate with Installation Design Guide (IDG), or other Installation criteria controlling exterior
architectural design, for required appearance of exterior bumper posts.
I. Provide 120-volt exterior weatherproof duplex receptacle adjacent to each overhead receiving
door. Refer to Division 26 criteria for additional information.
J. Provide exterior-type weatherproof push button adjacent to receiving area personnel doors,
connected to an interior buzzer. Push buttons shall be provided to activate buzzers in Produce
Processing, Meat Processing, and Staging / Receiving Area. Provide individual push buttons at
each receiving area personnel door for each individual area, with signage identifying same.
Buzzers shall have different tones for each area. Refer to Division 26 criteria for additional
information.
K. Trash Platforms attached directly to the exterior building wall of a commissary are no longer
permitted by UFC 4-010-01, unless the area is secured (UFC 4-010-01 Standard 1). The trash
platform may be secured using a chain-link enclosure as shown in Design Standard Plate
11 13 00-03. Unsecured trash containers shall be located at least 82.02' from the building.
END OF SECTION
June 2011 11 13 00 2
SECTION 11 13 00
LOADING DOCK EQUIPMENT
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Dock bumpers.
2. Dock levelers.
3. Truck restraints.
4. Dock seals.
5. Metal hoods.
1.2 DEFINITIONS
A. Operating Range: Maximum amount of travel above and below the loading dock level.
1.3 SUBMITTALS
A. Product Data:
B. Installer Certification:
1. Submit letter from Manufacturer stating that installer is an authorized representative who
is trained and approved for installation of units required for this Project.
C. Shop Drawings:
1. Show fabrication and installation details. Include plans, elevations, sections, details, and
attachments to other work.
D. Maintenance Data:
E. Warranties:
G. Submittal List:
A. Installer Qualifications:
B. Source Limitations:
1. Obtain all loading dock equipment through one source from a single manufacturer.
1. Store and handle dock seals in a manner to avoid significant or permanent damage to
fabric or frame.
2. Comply with manufacturer's written instructions for minimum and maximum temperature
requirements for storage.
1.7 COORDINATION
1. Furnish setting Drawings, templates, and directions for installing anchorages, including
sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be
1. Coordinate size and location of pits to ensure proper clearances and operation of
equipment.
C. Electrical Requirements:
1.8 WARRANTY
1. Manufacturer agrees, in writing, to repair or replace truck restraints that fail in materials or
workmanship, including all material, labor, tax, and freight for period of 7 years from date
of shipment.
1.9 GUARANTEE
A. Special Guarantee for Truck Restraints: Manufacturer agrees, in writing, to a 24-month money
back guarantee of satisfactory truck restraint performance as determined by the Contracting
Officer.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
2.2 MATERIALS
1. ASTM A 786/A 786M, rolled from steel plate complying with ASTM A 572/A 572M,
Grade 55.
C. Steel Tubing:
A. Laminated-Tread Bumpers:
1. Fabricated from multiple, uniformly thick plies cut from fabric-reinforced rubber tires.
Laminate plies under pressure on not less than two 3/4 inch diameter, steel supporting
rods that are welded at one end to 1/4 inch thick, structural-steel end angle and secured
with a nut and angle at the other end. Fabricate angles with predrilled anchor holes and
sized to provide not less than 1 inch of tread plies extending beyond the face of closure
angles.
2. Thickness: 4-1/2 inches.
3. Horizontal Style:
B. Anchorage Devices:
1. Hot-dip galvanized steel anchor bolts, nuts, washers, bolts, sleeves, cast-in-place plates,
and other anchorage devices as required to fasten bumpers securely in place and to suit
installation type indicated.
A. General:
B. Function:
1. Dock levelers shall compensate for differences in height between truck bed and loading
platform surface in the following manner:
a. Vertical Travel: Provide operating range above platform level of sufficient height to
enable lip to extend and clear truck bed before contact.
b. Automatic Vertical Compensation: Floating travel of ramp with lip extended and
resting on truck bed shall compensate automatically for upward or downward
movement of truck bed during loading and unloading.
c. Automatic Lateral Compensation: Tilting of ramp with lip extended and resting on
truck bed shall compensate automatically for canted truck beds of up to 4 inches
over width of ramp.
d. Lip Operation: Manufacturer's standard mechanism that automatically extends
and supports hinged lip on ramp edge with lip resting on truck bed over dock
leveler's working range, allows lip to yield under impact of incoming truck, and
automatically retracts lip when truck departs.
e. Automatic Ramp Return: Automatic return of unloaded ramp, from raised or
lowered positions to stored position, level with platform, as truck departs.
D. Construction:
1. Fabricate dock-leveler frame, platform supports, and lip supports from structural- or
formed-steel shapes. Weld platform and hinged lip to supports. Fabricate entire
assembly to withstand deformation during both operating and stored phases of service.
Chamfer lip edge to minimize obstructing wheels of material-handling vehicles.
a. Hinged Lip: Full width, piano-type hinge with heavy-wall hinge tube and greased
fittings, with gussets on lip and ramp for support.
b. Toe Guards: Equip open sides of rising ramp over range indicated with metal toe
guards mounted flush with ramp edges and projecting below ramp.
E. Accessories:
1. Pit Frame: 3 by 3 by 1/4 inch galvanized steel curb angles for edge of recessed leveler
pit, with 1/2 inch diameter by 6 inch long concrete anchors welded to angle at 6 inches
o.c. Paint pit frame angles safety yellow.
2. Night Locks: Manufacturer's standard means to prevent extending lip and lowering ramp
when overhead doors are locked.
3. Side and rear seals or closures to provide rodent and weather containment.
4. Interlock: Leveler will not operate while overhead door is in closed position and truck
restraint is not engaged.
A. General:
1. Manufacturer's standard device designed to engage truck's rear-impact guard and hold
truck at loading dock. Restraint shall consist of an iron or steel restraining arm that raises
until contacting rear-impact guard. Arm shall move vertically, automatically adjusting to
varying height of truck due to loading and unloading operations.
2. Basis-of-Design Products: Rite-Hite Corporation, RHR-1000.
3. Provide a truck restraint at each recessed dock leveler.
4. Truck restraining device shall be manufactured by the same manufacturer as the dock
levelers.
5. No motors shall be required to position the restraint to reach proper engagement level for
variable rear impact guard heights. Position of rotating hook shall therefore be in the
same position in relation to variable rear impact guard heights prior to activation.
6. Large, rotating or level vertical-rising, yellow zinc dichromate steel hook for visibility.
7. Hook arrangement shall be maintained throughout every phase of loading/unloading
process, including below dock end loading.
8. Finish: Galvanized.
1. Capable of restraining total gross load of 32,000 pounds without permanent deflection or
distortion.
C. Operating Range:
E. Caution Signs:
1. Surface mounted; with black text on yellow background, and with sign copy as follows.
Provide one sign each at each truck-restraint location.
a. Exterior Sign: Copy in Forward and Reverse Text: "BACK IN OR PULL OUT ON
GREEN ONLY."
b. Interior Sign: Copy in Forward Text: "ENTER ON GREEN ONLY."
1. Red and green illuminated signal-light sets, with lens approximately 4 inches in diameter,
designed to indicate status to both dock attendant and truck driver. Equip system with
connection to master control panel that includes illuminated lights indicating status of
exterior signal lights. Provide signal-light set and connection to master control panel at
each truck restraint location. Enclose exterior signal-light sets in steel or plastic housing
with sunshade.
2. Manual Operation: System is activated by push button or switch located on interior
master control panel.
3. Light box shall have maximum projection from wall of no more than 4 inches.
G. Alarm:
1. Audible and visual system located on master control panel indicating that rear-impact
guard is not engaged, with manual reset.
2. Alarm Override: Alarm override allows communication via the lighting system and an
audible alarm when abnormal hooking position exists or no rear impact guard is present.
Override turns off audible alarm and leaves outside light red with inside lights
simultaneously red and green, indicating abnormal condition. Remote-control shall not
function until code is re-entered or key used to turn override off.
A. General:
1. Provide a control panel enclosed in NEMA ICS 6, Type 12 box, at each truck dock door,
with integral fused disconnecting means for operating dock leveler and truck restraints
and with lockout-tagout.
2. Basis-of-Design Products: Rite-Hite Corporation, Doc-Commander.
3. Dock leveler multibutton controls:
4. Truck Restraint:
A. General:
C. Construction:
a. Color: Black.
b. Pleated Protectors: Protectors on face of jamb pads of overlapping layers of black
vinyl-coated nylon or polyester with minimum total weight of 40 oz./sq. yd fabric
attached to base fabric and with 4 inch wide full length, coated, nylon yellow guide
stripes stitched to pleats. Wear exposure same width as side pad face.
A. General:
1. Dock hood designed to project over top of truck's rear opening; of type, size, and
construction indicated.
2. Basis-of-Design Product: 4 Front Engineering Solutions, W183 S8253 Racine Avenue,
Muskego, WI 53150.
3. Type: Surface mounted projected metal hood with integral gutter.
4. Projection: 18 inches.
5. Material: 18 gage galvanized steel.
6. Brackets: In addition to standard brackets, provide 1/4 inch thick by 2 inch wide
galvanized steel brackets on underside of hood extending from gutter to wall, secured to
hood and anchored to wall. Space brackets 12 inches on center.
2.9 FINISHES
A. General:
1. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
2. Finish loading dock equipment after assembly and testing.
3. Galvanizing:
1) ASTM A 123/A 123M for iron and steel loading dock equipment.
2) ASTM A 153/A 153M for iron and steel hardware for loading dock
equipment.
PART 3 - EXECUTION
3.1 EXAMINATION
A. General:
1. Examine areas and conditions, with Installer present, for compliance with requirements
for installation tolerances and other conditions affecting performance of loading dock
equipment.
2. Examine roughing-in for electrical systems for loading dock equipment to verify actual
locations of connections before equipment installation.
3.2 PREPARATION
A. General:
3.3 INSTALLATION
A. General:
1. Install loading dock equipment, including motors control stations wiring safety devices
and accessories as required for a complete installation.
2. Rough-in electrical connections according to requirements specified in Division 26.
B. Dock Bumpers:
1. Attach dock bumpers to face of loading dock and trash platform in a manner that
complies with requirements indicated for spacing, arrangement, and position relative to
top of platform and anchorage.
2. Welded Attachment: Plug-weld anchor holes in contact with steel inserts and fillet weld
at other locations.
3. Bolted Attachment: Attach dock bumpers to preset anchor bolts embedded in concrete
or to cast-in-place inserts or threaded studs welded to embedded-steel plates or angles.
If preset anchor bolts, cast-in-place inserts, or threaded studs welded to embedded-steel
plates or angles are not provided, attach dock bumpers by drilling and anchoring with
expansion anchors and bolts.
1. Attach dock levelers securely to loading dock, flush with adjacent loading dock surfaces
and square to recessed pit.
D. Truck Restraints:
1. Attach truck restraints in a manner that complies with requirements for arrangement and
height required for device to engage vehicle rear-impact guard. Interconnect control
panel and signals with dock leveler.
E. Dock Seals:
A. Mount metal hoods by securing to wall above dock seals at dock door openings. Install in
accordance with manufacturer's printed instructions.
A. Adjusting:
1. Adjust loading dock equipment for proper, safe, efficient operation and to operate
smoothly.
B. Testing:
1. Test dock levelers for vertical travel within operating range indicated.
C. Cleaning:
3.6 DEMONSTRATION
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 26 Design Criteria.
2. While Guide Specifications are continually being updated to incorporate the specified manufacturers
product improvements, it is the A/Es responsibility to verify with the basis-of-design manufacturer that
each product specification is current. Provide written notification to the DeCA Project Manager when
this verification has been completed.
3. Item 1E06-A: QUEUING SYSTEM, CHECKOUT, TRAFFIC CONTROL is a portable traffic control
system consisting of stanchions (posts), retractable tension belts, and directional signs to guide
customers into a queue for smooth and organized flow to the checkout counters. System shall be
graphically shown on drawings with quantity of stanchions clearly identified. Space stanchions 5'-0" on
center, creating 4'-0" wide queue lanes. Queue should be positioned so that customers approach start
of queue at end of normal shopping sequence and end queue at center of checkout counter line-up.
4. Item 3-2D04: DIGITAL "TAKE-A-NUMBER" SYSTEM is provided to improve customer service in an
orderly manner within a department. Provide one system at the bakery department and one system at
the deli department. Since these departments are typically co-located, position so that it is obvious to
customers which system is for the bakery and which system is for the deli. Coordinate with electrical
drawings to provide a junction box with 120V power for each LED number indicator at 96" AFF with
empty conduit concealed in wall to empty junction box at 48" AFF directly below (or other convenient
location) for clerk activated push button control of system.
END OF SECTION
June 2011 11 14 00 1
SECTION 11 14 00
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
C. Submittal List:
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Post: heavy walled T5 tempered continuous aluminum extrusion, 0.1030 inch at its
thinnest point. Post shall contain four grooves that run the length of the post. Each
groove shall contain a 35-inch by 1-5/8-inch decorative high-pressure color plastic
laminated trim strip. Each groove shall also serve as a belt attachment point allowing
connection from any of three angles. Bright chrome anodized finish.
2. Base Weight: Cast iron with an epoxy coating that fits snugly underneath a base cover.
The entire outer rim of the base cover shall contain a non-marring black rubber rim that
attaches to the cast base through the use of spru holes. Do not provide rollers.
3. Base Cover: 14 inches in diameter and fits over the base weight; 16 gage stamped steel
with a, satin chrome finish.
4. Belt: 2 inches wide woven nylon. The belt shall be able to extend up to 82 inches from
post to post center. The bottom of the belt shall be 34 inches from finished floor. Belt
color: Black. A 1.269-inch by 3.125-inch plastic belt end shall attach to the end of the belt
to allow the belt to be secured to another post. The belt end shall be able to be secured
into place with locking tabs supplied with each unit.
5. Belt Spring: Stainless steel, power-wound constant force spring that retracts the
complete length of the belt when not in use.
6. Sign Frames and Signs:
a. Two chrome trimmed sign frames 7 by 11 inches with adapters for mounting on
posts.
b. One double faced sign engraved "PLEASE ENTER HERE" each side.
c. One single faced sign engraved "PLEASE WAIT HERE FOR THE NEXT
AVAILABLE CASHIER."
d. Sign color, white letters on black background.
A. Salient Characteristics:
1. Electronic L.E.D. number indicator: Black with 2-digit number display, 12 inches long by
2-1/4 inches deep by 9-3/4 inches high.
2. Red ticket dispenser with "Please Take A Number" sign.
3. 12-volt transformer.
4. 100 feet of wire with hardware.
5. 3 push buttons.
6. Set of "Now Serving" decals in 12 languages.
7. 5-foot high portable floor stand for dispenser.
8. Tickets: Disposable, pre-cut, pre numbered, 15 rolls at 3000 tickets per roll. Provide
white tickets. If more than one system is used, provide each system with a different roll of
colored tickets.
1. Electronic number indicator kit: Model 51310, includes number display, dispenser with
sign, transformer, wire with hardware, pushbuttons, and decals.
2. Dispenser stand: Model 78118.
3. Take-A-Number tickets: Model 96272.
PART 3 - EXECUTION
3.1 INSTALLATION
A. General:
A. Testing: Test, adjust, and verify operation of each unit and component of the queuing systems.
Repair or replace any item found to be defective or operating below rated capacity.
A. Adjusting:
1. Verify that operating parts work freely and fit neatly. Adjust and lubricate hardware and
moving parts.
B. Cleaning:
C. Repair or Replace:
1. Repair or replace damaged parts, dents, buckles, abrasions, and other defects affecting
appearance or serviceability so queuing systems are in an acceptable condition at time of
final acceptance.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each product specification is current. Provide written notification to the DeCA
Project Manager when this verification has been completed.
B. Safes are typically located within the Cashiers Office of the Commissary. The size of the safe is
based on the sales volume of a commissary and will be determined during the design charrette.
DeCA Directive 30-18 "DeCA Security and Loss Prevention" requires that safes be positioned so
that the combination lock is not directly visible from windows or doors opening into the Cashiers
Office. Further, it should be positioned so that the contents of the safe are not visible to persons
outside the cashiers office when the safe door is open.
C. Sizes are as follows:
1. 1E08 - SAFE, 22 CU. FT. CAPACITY (RATED TL-30).
2. 1E10 - SAFE, 39 CU. FT. CAPACITY (RATED TL-30).
D. Refer to Section 13 25 00 for specific construction and security requirements for cashier offices.
2. DESIGN CHARRETTE PHASE RESPONSIBILITIES
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
3. CONTRACT DOCUMENT PHASE RESPONSIBILITIES.
A. The Contract Documents shall include the equipment list developed during the design charrette
process, clearly identifying responsibility for all equipment. To facilitate and expedite technical
review by DeCA, the Contract Documents shall use DeCA equipment item numbers to key both
the contractor-furnished and government-furnished equipment to the Drawings.
B. If applicable, DeCA will provide the A/E with a list of existing government-owned equipment to be
re-used in the new or renovated facility. The A/E shall evaluate the identified equipment to
determine suitability, and confirm utility requirements for removal and relocation into the new or
renovated facility. If applicable, list or note on the Contract Specifications/Drawings any
equipment to be salvaged or relocated by the construction contractor.
C. On addition / alteration projects, provide specific guidance on the Contract Documents regarding
disposition of salvaged equipment (i.e., will it become the property of the contractor or turned
over to DRMO). Turn-in of salvaged equipment is the responsibility of the Commissary Store
Director or designated Government representative. When the contractor is required to remove
and/or otherwise dispose of commissary equipment such as display and storage shelving, display
cases, refrigeration equipment and walk-in-boxes, the contractor will be required to sign DD Form
1348-1 "Receipt Release Documents" prepared by the Commissary Store Director or designated
Government representative. The A/E shall clearly identify any equipment that will become the
property of the contractor for salvage, and clearly identify that all other operational equipment
shall remain the property of DeCA.
June 2011 11 16 16 1
DeCA DESIGN CRITERIA HANDBOOK
11 16 16 SAFES
D. Verify that adequate space is available (both floor space and ceiling clearance) for all specified
equipment.
END OF SECTION
June 2011 11 16 16 2
SECTION 11 16 16
SAFES
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
B. Submittal List:
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Salient Characteristics:
1. Freestanding safe.
2. Rectangular door.
3. Hinge door as indicated on drawings.
4. UL approved group 1R anti-manipulative lock with spy-proof dial.
5. UL approved locking and re-locking devices.
6. UL Class TL-30 tool resistant rating.
7. Full-length dead bar to prevent entry into safe by removing hinges. Welded ball-bearing
hinges with adjustment screws.
8. Design safe to accommodate all standard alarm systems internally.
9. Safe to accommodate store cash register drawers (up to 40 stacked drawers) with
nominal dimensions of 14-1/2 inches wide by 13-1/2 inches deep by 2 inches high.
10. Inside dimensions: 31 inches wide by 21 inches deep by 61 inches high.
11. Capacity: 23.0 cubic feet.
12. Five heavy-duty adjustable shelves.
13. Outside dimensions: 33 inches wide by 27-3/4 inches deep by 63 inches high.
14. Standard Khaki color finish.
B. Basis-of-Design Product: Adesco Safe Co., FireKing Security Group (800) 457-2424 x 3524 or
www.fireking.com.
2.3 ITEM 1E10: SAFE - LARGE (29 MINIMUM CUBIC FOOT) CAPACITY, TL-30 RATED
A. Salient Characteristics:
1. Freestanding safe.
2. Rectangular door.
3. Hinge door as indicated on drawings.
4. UL approved group 1R, anti-manipulative lock with spy-proof dial.
5. UL approved locking and re-locking devices.
6. UL Class TL-30 tool resistant rating.
7. Full length dead bar to prevent access by removing hinges. Welded ball-bearing hinges
with adjustment screws.
8. Design safe to accommodate all standard alarm systems internally.
9. Safe to accommodate store cash register drawers (up to 50 stacked drawers) with
nominal dimensions of 14-1/2 inches wide by 13-1/2 inches deep by 2 inches high.
10. Inside dimensions: 35 inches wide by 27 inches deep by 73 inches high.
11. Capacity: 39.9 cubic feet.
12. Five heavy-duty adjustable shelves.
13. Outside dimensions: 37 inches wide by 33-1/4 inches deep by 75 inches high.
14. Standard Khaki color finish.
3.1 INSTALLATION
A. Install items where indicated on Drawings and in absence of dimension, install items where
directed by Contracting Officer. Install in accordance with approved assembly and installation
Drawings.
A. Adjust equipment for proper operation. After completion of installation, clean and polish all
exposed surfaces. Deliver keys and instruction sheets to the Contracting Officer.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. Teller and service equipment is used at the Cashiers Office of the Commissary, and is typically
limited to a cashiers window (located between customer area and cashiers office) and a cash
tray window (located between cash counting room and cashiers office). The size and location
of these windows will be determined during the design charrette. DeCA Directive 30-18 "DeCA
Security and Loss Prevention" provides glazing requirements / restrictions, and requires that
operable windows be positioned so that a person cannot unlock the entrance door into the
cashiers office by reaching through a window. Further, windows should be positioned so that the
contents of the safe are not visible to persons outside the cashiers office.
B. It is the A/Es responsibility to verify with the basis-of-design manufacturer listed in the guide
specification is current. Provide written notification to the DeCA Project Manager when this
verification has been completed.
C. Refer to Division 13 Design Criteria, Section 13 25 00 Cash Rooms and Design Standard
Plates13 25 00-01, 13 25 00-02, 13 25 00-03, and 13 25 00-04, for specific construction and
security requirements for cashier offices.
D. Refer to Design Standard Plates 11 17 00-01 and 11 17 00-02 for information on cashiers
window.
E. Refer to Design Standard Plates 11 17 00-03 and 11 17 00-04 for information on cash tray
window.
2. DESIGN CHARRETTE PHASE RESPONSIBILITIES
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
3. CONTRACT DOCUMENT PHASE RESPONSIBILITIES
A. The Contract Documents shall include the equipment list developed during the design charrette
process, clearly identifying responsibility for all equipment. To facilitate and expedite technical
review by DeCA, the Contract Documents shall use DeCA equipment item numbers to key both
the contractor-furnished and government-furnished equipment to the Drawings.
B. If applicable, DeCA will provide the A/E with a list of existing government-owned equipment to be
re-used in the new or renovated facility. The A/E shall evaluate the identified equipment to
determine suitability, and confirm utility requirements for removal and relocation into the new or
renovated facility. If applicable, list or note on the Contract Specifications/Drawings any
equipment to be salvaged or relocated by the construction contractor.
C. On addition / alteration projects, provide specific guidance on the Contract Documents regarding
disposition of salvaged equipment (i.e., will it become the property of the contractor or turned
over to DRMO). Turn-in of salvaged equipment is the responsibility of the Commissary Store
Director or designated Government representative. When the contractor is required to remove
and/or otherwise dispose of commissary equipment such as display and storage shelving, display
cases, refrigeration equipment and walk-in-boxes, the contractor will be required to sign DD Form
1348-1 "Receipt Release Documents" prepared by the Commissary Store Director or designated
June 2011 11 17 00 1
DeCA DESIGN CRITERIA HANDBOOK
11 17 00 TELLER AND SERVICE EQUIPMENT
Government representative. The A/E shall clearly identify any equipment that will become the
property of the contractor for salvage, and clearly identify that all other operational equipment
shall remain the property of DeCA.
D. Verify that adequate space is available (both floor space and ceiling clearance) for all specified
equipment.
END OF SECTION
June 2011 11 17 00 2
SECTION 11 17 00
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Cashiers window.
2. Cash tray window.
1.2 SUBMITTALS
A. Product Data:
B. Submittal List:
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Cashiers Window:
1. Speakhole:
3. Glazing Channel: Stainless steel, 18 gauge, Type 304, No. 4 fine brush finish, nominally
1/4 inch high legs by glass thickness by glass width.
4. Glass: Uncoated, clear, laminated float glass complying with ASTM C 1172, Kind LA,
Type I (transparent glass, flat), Class 1 (clear), and Quality q3 (glazing select), fabricated
of two 1/8 inch thick plies with 0.015 inch thick clear polyvinyl butyral interlayer.
5. Related Sections: The following Section contains requirements that relate to cashiers
window:
a. Division 08 Section Hollow Metal Doors and Frames for cashiers window frame
manufactured according to the Hollow Metal Manufacturers Association's
standards.
6. Fabricate framing in profiles indicated for flush glazing (without projecting stops).
7. Install glazing to comply with requirements of Division 08 Section Glazing, unless
otherwise indicated.
1. Basis-of-Design Product: Nissen & Company, Inc.; Series C, custom size as indicated.
2. Frames and Glass Channels: Type 6063-T5 extruded aluminum.
3. Glass: Uncoated, clear, laminated float glass complying with ASTM C 1172, Kind LA,
Type I (transparent glass, flat), Class 1 (clear), and Quality q3 (glazing select), fabricated
of two 1/8 inch thick plies with 0.015 inch thick clear polyvinyl butyral interlayer.
4. Metal Finish: Anodized 204R-1 clear alumite.
5. Lock: Sliding bolt type.
PART 3 - EXECUTION
3.1 INSTALLATION
A. General:
A. Testing:
1. Test each item of equipment to verify proper operation. Make necessary adjustments.
B. Accessories:
1. Verify that accessory items required have been furnished and installed.
C. Cleaning:
1. Remove packing material from equipment items and leave units in clean condition, ready
for operation.
2. Remove and replace glass that is broken, chipped, cracked, abraded, or damaged in any
way, including natural causes, accidents, and vandalism, during construction period.
3. Wash glass on both exposed surfaces in each area of Project not more than four days
before date scheduled for inspections that establish date of final acceptance. Wash
glass as recommended by glass manufacturer.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each product specification is current. Verify that equipment color is coordinated
with the current DeCA dcor and available from the manufacturer. Provide written notification to
the DeCA Project Manager when this verification has been completed.
B. The guide specification specifies equipment typically used in a commissary facility. The A/E shall
edit the guide specification, deleting equipment not required on a particular project.
C. It may be necessary to specify equipment that it not included in the guide specification. The A/E will
be responsible for developing UFGS format product specifications for insertion into the guide
specification.
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
3. CONTRACT DOCUMENT PHASE RESPONSIBILITIES
A. The Contract Documents shall include the equipment list developed during the design charrette
process, clearly identifying responsibility for all equipment. To facilitate and expedite technical
review by DeCA, the Contract Documents shall use DeCA equipment item numbers to key both
the contractor-furnished and government-furnished equipment to the Drawings.
B. If applicable, DeCA will provide the A/E with a list of existing government-owned equipment to be
re-used in the new or renovated facility. The A/E shall evaluate the identified equipment to
determine suitability, and confirm utility requirements for removal and relocation into the new or
renovated facility. If applicable, list or note on the Contract Specifications/Drawings any
equipment to be salvaged or relocated by the construction contractor.
C. On addition / alteration projects, provide specific guidance on the Contract Documents regarding
disposition of salvaged equipment (i.e., will it become the property of the contractor or turned
over to DRMO). Turn-in of salvaged equipment is the responsibility of the Commissary Store
Director or designated Government representative. When the contractor is required to remove
and/or otherwise dispose of commissary equipment such as display and storage shelving, display
cases, refrigeration equipment and walk-in-boxes, the contractor will be required to sign DD Form
1348-1 Receipt Release Documents prepared by the Commissary Store Director or designated
Government representative. The A/E shall clearly identify any equipment that will become the
property of the contractor for salvage, and clearly identify that all other operational equipment
shall remain the property of DeCA.
D. Verify that adequate space is available (both floor space and ceiling clearance) for all specified
equipment.
E. Verify that proper utility connections and mounting heights (water, drain, vent, refrigeration,
electrical, communication, etc.) are shown on Contract Documents for all specified equipment.
F. If wedge configurations are utilized in bakery display case line-up, provide a three-step custom
millwork unit with plastic laminate finish. Provide solid-surfacing material countertops for service
and transaction counter locations. Millwork units are freestanding, finished on all surfaces (except
bottom) and not attached to display cases. Do not locate any utilities within or attached to these
wedge configurations. If required, locate utilities (i.e., electrical receptacles for normal
housekeeping) in millwork counters.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
1. For each item of equipment required, including the manufacturer's standard details and
installation and maintenance instructions.
B. Submittal List:
A. Installer Qualifications: Engage an experienced installer to perform work of this Section who is
an authorized representative of the bakery equipment manufacturer, who has specialized in
installing bakery department equipment, who has completed installations similar in design and
extent to that indicated for this Project, and who has a record of successful in-service
performance.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Salient Characteristics:
1. Cabinet exterior, front, one piece sides, louver assembly, and doors constructed of heavy
gauge stainless steel with #4 finish. Cabinet interior and door liners are constructed of
anodized aluminum. Exterior cabinet top, back and bottom are constructed of heavy
gauge aluminized steel.
2. Top mounted, self-contained, balanced refrigeration system located behind a one piece
louver assembly.
3. Plenum effect blower coil, large, high humidity evaporator coil located outside the food
zone and a top mounted non-electric condensate evaporator.
4. Automatic non-electric condensate evaporator. No plumbing required to dispose of
condensation/defrost water.
5. Automatic preset time activated electric defrost.
a. 58 inches long.
b. 35 inches deep.
c. 83 inches high on 6-inch legs.
14. Electrical:
a. Refrigerant: R-404A.
b. BTU/HR H.P.: 3790 (3/4 HP).
B. Accessories:
1. Provide one full door section with chrome plated steel rod type slide assemblies to
support up to thirty-eight 18-inch by 26-inch sheet pans. This door section is the left door
when facing the unit.
2. Provide other full door section with 18 gauge stainless steel adjustable angle type shelf
brackets for full height of each door section on minimum 3-inch centers to support 18-
inch by 26-inch sheet pans.
3. Provide 12 stainless steel wire shelves with shelf clips.
1. A Series 2-Section Full Length Door Model ALT232WUT-FHS. (Energy Star Listed)
2. No. 4.Tray Slide.
3. No. 2 Tray Slide.
4. Stainless steel shelves.
A. Salient Characteristics:
1. Cabinet exterior, front, one piece sides, louver assembly, and doors constructed of heavy
gauge stainless steel with #4 finish. Cabinet interior and door liners are constructed of
a. 86 inches long.
b. 35 inches deep.
c. 83 inches high on 6-inch legs.
14. Electrical:
a. Refrigerant: R-404A.
b. BTU/HR H.P.: 4710 (1 HP).
B. Accessories:
1. Provide one full door section with chrome plated steel rod type slide assemblies to
support up to thirty-eight 18-inch by 26-inch sheet pans. This door section is the left door
when facing the unit.
2. Provide other two full door sections with 18 gauge stainless steel adjustable angle type
shelf brackets for full height of each door section on minimum 3-inch centers to support
18-inch by 26-inch sheet pans.
3. Provide 12 stainless steel wire shelves with shelf clips.
A. Salient Characteristics:
1. Cabinet exterior, front, one piece sides, louver assembly, and doors constructed of heavy
gauge stainless steel with #4 finish. Cabinet interior and door liners are constructed of
anodized aluminum. Exterior cabinet top, back and bottom are constructed of heavy
gauge aluminized steel.
2. Top mounted, self-contained, balanced refrigeration system located behind a one piece
louver assembly.
3. Plenum effect blower coil, large, high humidity evaporator coil located outside the food
zone and a top mounted non-electric condensate evaporator.
4. Automatic non-electric condensate evaporator. No plumbing required to dispose of
condensation/defrost water.
5. Digital thermometer and temperature controls. Standard operating temperature: 34 to 38
deg F.
6. Replaceable vinyl magnetic door gaskets with anti-condensate heaters located behind
each door opening.
7. Insulation: Cabinet and doors contain high density, non-CFC, foamed-in-place
polyurethane insulation.
8. Full length doors are equipped with removable plug cylinder locks and guaranteed for life
cam-lift, gravity action, self-closing metal, glide hinges with stay open feature at 120
degrees. Door handle is mounted horizontally over recess in door which limits protrusion
from door face into aisle ways.
9. Interior lighting controlled by opening and closing doors.
10. Adjustable 6-inch high stainless steel legs.
11. Capacity: 79 cu. ft.
12. Cabinet approximate overall dimensions:
a. 86 inches long.
b. 35 inches deep.
c. 83 inches high on 6-inch legs.
13. Electrical:
a. Refrigerant: R-134a.
b. BTU/HR H.P.:4900 (3/4 HP).
B. Accessories:
1. Provide one full door section with chrome plated steel rod type slide assemblies to
support up to thirty-eight 18-inch by 26-inch sheet pans. This door section is the left door
when facing the unit.
A. Salient Characteristics:
1. Electric operated.
2. Capacity: One single full-size baking rack.
3. Self-contained cast spherical steam system.
4. Stainless steel interior and exterior.
5. Flush stainless steel floor panel with extender kit.
6. Integral hood with grease filters complying with NFPA 96 for Type I (grease) installation.
7. Provide with a digital, programmable control system which incorporates: minimum of 99
menus.
8. Automatic Damper controls.
9. Single point vent connection with collar designed for connection to 8-inch diameter duct.
Hood is fully welded with grease trough, drain cup, and UL classified grease filters.
Chamber vents are factory ducted to the integral hood (690 cfm required). Refer to
Division 23 for duct and roof mounted exhaust fan. Interlock exhaust fan control signal to
oven control.
10. Rack lift rotation system.
11. Door: Positive latching door lock with heavy-duty door hinges and wide viewing glass with
triple-pane glass for reduced heat loss and cooler working area in front of oven.
12. Electrical (two supplies required):
a. Control:
b. Heating Element:
a. Water - 1/2 inch NPT. Cold water at 30 psi minimum at 3.0 GPM flow rate.
b. Drain - Choose either front or rear drain, and plug the drain connection that is not
used. Route to air-gap drain as indicated on Drawings.
a. 55 inches wide.
b. 51 inches deep (without hood or drain fittings).
c. 104 inches high.
B. Accessories:
1. Oven: OV500E1.
2. Single Oven Rack: BXSSA-20B1.
A. Salient Characteristics:
1. Gas operated.
2. Capacity: One single full-size baking rack.
3. Self-contained cast spherical steam system.
4. In-shot burner system with a heat exchanger consisting of 18 independent high-
temperature, stainless steel tubes. In-shot burners will have no moving parts.
5. Stainless steel interior and exterior.
6. Flush stainless steel floor panel with extender kit.
7. Integral hood with single-point exhaust and grease filters complying with NFPA 96 for
Type I (grease) installation. Hood is fully welded with grease trough, drain cup, and UL
classified grease filters. Refer to Division 23 for duct and roof mounted exhaust fan.
Interlock exhaust fan control signal to oven control.
8. Provide with a digital, programmable control system which incorporates: minimum of 99
menus.
9. Automatic Damper controls.
10. Rack lift rotation system.
11. Field reversible oven door with three panes of glass in the viewing window to ensure a
safe-to-the-touch exterior.
12. Electrical (two supplies required):
a. Control:
c. Gas:
d. Hood Vent:
e. Plumbing:
1) Water - 1/2 inch NPT. Cold water at 30 psi minimum at 3.0 GPM flow rate.
2) Drain - Choose either front or rear drain, and plug the drain connection that
is not used. Route to air-gap drain as indicated on Drawings.
f. Approximate Dimensions:
1) 55 inches wide.
2) 51 inches deep (without hood or drain fittings).
3) 104 inches high.
B. Accessories:
1. Oven: OV500G1.
2. Single Oven Rack: BXSSA-20B2.
A. Salient Characteristics:
1. Electric operated.
2. Capacity: One full-size double rack or two full-size single racks.
3. Self-contained cast spherical steam system.
4. Stainless steel interior and exterior.
5. Flush stainless steel floor panel with extender kit.
6. Integral hood with grease filters complying with NFPA 96 for Type I (grease) installation.
a. Control:
b. Heating Element:
13. Plumbing:
a. Water - 1/2 inch NPT. Cold water at 30 psi minimum at 3.0 GPM flow rate.
b. Drain - Choose either front or rear drain, and plug the drain connection that is not
used. Route air-gap drain as indicated on Drawings.
a. 72 inches wide.
b. 62 inches deep (without hood or drain fittings).
c. 104 inches high.
B. Accessories:
1. Oven: OV500E2.
2. Single Oven Rack: BXSSA-20B2.
3. Double Oven Rack: BXDSA-20B2.
A. Salient Characteristics:
1. Combination unit: Oven mounted on an associated proofing cabinet. Oven designed for
holding baking sheet pans on an integral rotary rack. Proofing cabinet designed for
holding and simultaneously proofing sheet pans.
2. Stainless steel construction interior and exterior.
3. Electrically operated heating system; shall NOT use gas.
4. Oven accommodates 8 each 18- by 26-inch sheet pans with 4-inch spacing.
5. Proofer accommodates 16 each 18- by 26-inch sheet pans with 3-inch spacing.
6. Overall approximate dimensions with standard trim:
7. Oven Cabinet:
a. Provide glass doors allowing view of sheet pans during the cooking process.
b. Self-contained steam injection system.
c. Digital programmable control system which incorporates 99-recipe settings; 4-step
baking, fan delay feature, automatic damper, temperature, time, steam, blower,
and venting controls.
8. Proofer Cabinet:
a. Provide for one supply circuit, separate from oven circuits: 120 V / 60 HZ / 1 PH /
16A, 1/70 H.P.
b. Provide with digital humidity and temperature controls.
c. Water connection point 1/4-inch cold water at 30 - 80 psi.
d. Drain fitting: 1/2 inch to air-gap drain.
e. Provide with four each 4-inch swivel casters (two locking) for mobility.
f. Unit minimum operating temperature range of 80 to 120 deg F for proofing.
A. Salient Characteristics:
9. Electrical:
B. Accessories:
1. Oven Racks: Aluminum side load type. Provide two single, twenty-pan capacity, roll-in
racks with oven ready casters.
2. Rack Covers: Provide vinyl rack cover for each roll-in rack.
3. Sheet Pans: Provide forty 18-inch by 26-inch sheet pans.
A. Salient Characteristics:
9. Electrical:
a. 208-204 volts, 60 hertz, three-phase. Neutral wire circuitry needed to provide 110 -
120V for miscellaneous control components.
b. Total 20.4 amps.
c. Install with permanent connection to service.
a. 62 inches wide.
b. 44 inches deep.
c. 99.5 inches high.
B. Accessories:
1. Oven Racks: Aluminum side load type. Provide two single, twenty-pan capacity, roll-in
racks with oven ready casters.
2. Rack Covers: Provide vinyl rack cover for each roll-in rack.
3. Sheet Pans: Provide forty 18-inch by 26-inch sheet pans.
A. Salient Characteristics:
1. Cabinet exterior front, one piece sides, louver assembly, and doors constructed of 20
gage stainless steel with #4 finish. Cabinet interior and door liners are constructed of
stainless steel. Exterior cabinet top, back and bottom are constructed of heavy gauge
aluminized steel. Interior floor is constructed of stainless steel and insulated with 3/4-inch
of resilient cork. Provide readily attachable stainless steel ramp to facilitate loading and
unloading.
2. Top mounted, self-contained, balanced refrigeration system located behind a one piece
louver assembly.
3. Plenum effect blower coil, large, high humidity evaporator coil located outside the food
zone and a top mounted non-electric condensate evaporator.
4. Automatic non-electric condensate evaporator. No plumbing required to dispose of
condensation/defrost water.
5. Digital thermometer and temperature controls. Standard operating temperature: 34 to 38
deg F.
6. Replaceable vinyl magnetic door gaskets with anti-condensate heaters located behind
each door opening.
a. 68 inches long.
b. 36 inches deep.
c. 89 inches high.
11. Electrical:
a. Refrigerant: R-134a.
b. BTU/HR H.P.:4200 (1/2 HP).
B. Accessories:
1. Oven Racks: Aluminum side load type. Provide two single, twenty-pan capacity, roll-in
racks with oven ready casters.
2. Rack Covers: Provide vinyl rack cover for each roll-in rack.
3. Sheet Pans: Provide forty 18-inch by 26-inch sheet pans.
2.12 ITEM 1B28: REFRIGERATED SELF-SERVICE CASE WITH CAKE DECORATOR STATION
A. Salient Characteristics:
1. Refer to Division 23 Section Refrigeration Monitoring and Control System (RMCS) for
refrigeration monitoring sensors installed by that Section.
2. Self-contained refrigeration system with R-404A refrigerant and bottom mounted air-
cooled condensing unit designed to maintain a product temperature of 30 - 34 deg F.
Condensing unit shall be designed to slide out for ease of maintenance.
3. Electrical: 208 - 230 volts, 60 hertz, 1 phase with (30 amp) NEMA L14-30 plug.
4. Electric condensate dissipator pan.
5. Electronic thermostat temperature controls.
6. Electronic temperature sensors.
7. One solar digital thermometer.
8. Energy efficient fans.
9. Off-cycle defrost.
10. On/Off light switch for case lighting with T-8 fluorescent lamps and electronic ballasts.
NOTE BELOW: Specify only one glass end panel where drawings
show this display case as an end case in a display case line-up and
physically connected with either 1D13 or 1D17.
c. Two tempered glass end panels mounted on top of insulated end panels.
a. One adjustable (height and angle) 12-inch deep shelf with undershelf light, full
length of case, stainless steel.
b. Base deck area lighted with continuous ledge light, full length of case, stainless
steel.
c. Canopy light (same profile as ledge light), full length of case, stainless steel.
d. Air dam: 3/8 inch thick clear tempered glass at front of base deck.
e. Case front nosepiece: Painted aluminum extrusion to match exterior case color.
f. Molded bumper (1 inch wide) across front of display case, centered on nosepiece.
Color: Black.
g. Stainless steel kickplate.
C. Continuity:
1. Where shown on Drawings, this display case shall physically connect with 1D13 and
1D17 display cases to form a contiguous refrigerated display area, with tempered glass
ends in clerk service area, and without intermediate divider panels in self service area.
Provide insulated end panels only at beginning and end of display case line-up and
where required between refrigerated and dry storage areas.
1. Item 1B28-4: Refrigerated Self-Service Case with Cake Decorator Station, 4 foot Case
Length.
2. Item 1B28-6: Refrigerated Self-Service Case with Cake Decorator Station, 6 foot Case
Length.
3. Item 1B28-8: Refrigerated Self-Service Case with Cake Decorator Station, 8 foot Case
Length.
4. Item 1B28-12: Refrigerated Self-Service Case with Cake Decorator Station, 12 foot Case
Length.
A. Salient Characteristics:
a. 58 inches wide.
b. 41 inches deep.
c. 51 inches high.
1. Model HVAD56SS.
A. Salient Characteristics:
a. 76 inches wide.
b. 41 inches deep.
c. 51 inches high.
13. Electrical:
1. Model HVAD74SS.
A. Salient Characteristics:
a. 50 inches wide.
b. 42 inches deep.
c. 51 inches high.
15. Electrical:
1. Model HV48RSS.
A. Salient Characteristics:
a. 58 inches wide.
b. 42 inches deep.
c. 51 inches high.
15. Electrical:
1. Model HV56RSS.
A. Salient Characteristics:
a. 76 inches wide.
b. 42 inches deep.
c. 51 inches high.
1. Model HV74RSS.
A. Salient Characteristics:
1. Integrated Scale/Printer:
2. Electrical:
A. Salient Characteristics:
9. Electrical:
PART 3 - EXECUTION
3.1 INSPECTION
A. Check that surfaces to which work will be secured are sound and free of irregularities interfering
with installation.
3.2 PREPARATION
B. Ensure that roughed-in openings, built-in anchorage, and reinforcing required for proper
installation of work of this Section are correctly sized, installed and located.
C. Obtain electrical and mechanical service characteristics and rough-in locations from site.
C. Set units plumb, square and true, securely anchored to building structure.
E. Seal spaces between built-in equipment, walls and columns with preformed foam sealants
specified in Division 07 Section Joint Sealants, shim level and rigid, use proper type anchoring
devices for materials encountered and usage expected.
F. Cut, fit and patch; coordinate with work of other Sections involved.
G. Cut and drill tops, backs, sides and bottoms for service outlets and fixtures. Install fixtures and
fittings. Make connections to services.
H. Sequence installation and erection to ensure that mechanical and electrical connections are
effected.
I. Deliver instruction sheets to Contracting Officer and instruct Government's personnel in the
proper use, adjustment, and maintenance of equipment.
A. Adjust doors, drawers, hardware fixtures, and other moving and operating parts to function
smoothly and correctly.
D. Clean equipment cases, counters, shelves, glass, legs, hardware, fittings and fixtures. Wipe
down surfaces to remove fingerprints and markings and leave in clean condition.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each product specification is current. Provide written notification to the DeCA
Project Manager when this verification has been completed. Verify that equipment color is
coordinated with DeCAs current standard dcor and available from the manufacturer. Provide
written notification to the DeCA Project Manager when this verification has been completed.
B. The guide specification specifies equipment typically used in a commissary facility. The A/E shall
edit the guide specification, deleting equipment not required on a particular project.
C. It may be necessary to specify equipment that it not included in the guide specification. The A/E will
be responsible for developing UFGS format product specifications for insertion into the guide
specification.
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
D. Verify that adequate space is available (both floor space and ceiling clearance) for all specified
equipment.
E. Verify that proper utility connections and mounting heights (water, drain, vent, refrigeration,
electrical, communication, etc.) are shown on Contract Documents for all specified equipment.
F. If wedge configurations are utilized in deli display case line-up, provide three-step custom
millwork stepped displays with plastic laminate and solid surfacing finishes as indicated in Design
Standard Plate 06 40 23-03. Stepped displays are freestanding and not attached to display
cases. Do not locate any utilities within or attached to these wedge configurations.
G. Provide customer service counter with plastic laminate and solid surfacing finishes as indicated in
Design Standard Plate 06 40 23-02. Customer service counter is freestanding and not attached
to display cases. If required, locate utilities (i.e., electrical and data receptacles) within millwork
counters using flexible connectors as permitted by code.
END OF SECTION
DELI EQUIPMENT
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
1. For each item of equipment required, including the manufacturer's standard details and
installation and maintenance instructions. In addition, submit the following, as applicable:
B. Submittal List:
Reference Submittal Item Quantity Action
A. Installer Qualifications: Engage an experienced installer to perform work of this Section who is
an authorized representative of the deli equipment manufacturer, who has specialized in
installing deli department equipment, who has completed installations similar in design and
extent to that indicated for this Project, and who has a record of successful in-service
performance.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Salient Characteristics:
1. Cabinet exterior, including front, one piece sides, louver assembly, and doors constructed
of heavy gauge stainless steel. Cabinet interior and door liners are constructed of
anodized aluminum. Exterior cabinet top, back and bottom are constructed of heavy
gauge aluminized steel.
2. Top mounted, self-contained, balanced refrigeration system located behind a one piece
louver assembly.
3. Plenum effect blower coil, large, high humidity evaporator coil located outside the food
zone and a top mounted non-electric condensate evaporator.
4. Automatic non-electric condensate evaporator. No plumbing required to dispose of
condensation/defrost water.
a. 58 inches long.
b. 35 inches deep.
c. 83 inches high on 6-inch legs.
13. Electrical:
a. Refrigerant: R-134a.
b. BTU/HR H.P.:4200 (1/2 HP).
B. Accessories:
1. Provide full door sections with 18 gauge stainless steel angle type shelf brackets for full
height of each door section on minimum 3-inch centers to support 18-inch by 26-inch
sheet pans.
2. Provide 18 stainless steel wire shelves with shelf clips.
A. Salient Characteristics:
1. Cabinet exterior, including front, one piece sides, louver assembly, and doors constructed
of heavy gauge stainless steel. Cabinet interior and door liners are constructed of
anodized aluminum. Exterior cabinet top, back and bottom are constructed of heavy
gauge aluminized steel.
a. 86 inches long.
b. 35 inches deep.
c. 83 inches high on 6-inch legs.
13. Electrical:
a. Refrigerant: R-134a.
b. BTU/HR H.P.: 4200 (1/2 HP).
B. Accessories:
1. Provide all three full door sections with 18 gauge stainless steel angle type shelf brackets
for full height of each door section on minimum 3-inch centers to support 18-inch by 26-
inch sheet pans.
A. Salient Characteristics:
1. Refer to Division 23 Section Refrigeration Monitoring and Control Systems (RMCS) for
refrigeration monitoring sensors installed by that Section.
2. Self-contained refrigeration system with R-404A or R-134A refrigerant, and bottom
mounted air-cooled condensing unit designed to maintain a product temperature of 30
34 deg F. Designed for operation at maximum of 75 deg F DB and 55 percent RH.
Condensing unit shall be designed to slide out for ease of maintenance.
3. Compressor unit with minimum 1/3 horsepower.
4. Electrical: 120 volt, 60 hertz, 1 phase with (30 amp) NEMA L5-30 plug.
5. Electric condensate dissipater pan.
6. Electronic thermostat temperature controls.
7. Electronic temperature sensors.
8. One solar digital thermometer.
9. Energy efficient fans.
10. Off-cycle defrost.
11. On/Off light switch for case lighting with T-8 fluorescent lamps and electronic ballasts.
12. Four casters, 5 inches diameter (NSF). Position locks shall be provided on the two rear
casters as a minimum.
13. CFC free foamed-in-place insulation.
14. Seamless, non-corrosive tub.
15. Copper tube aluminum finned coils.
16. Case exterior color as indicated on Drawings, with stainless steel interior.
17. Welded steel chassis.
18. Preparation Table Work Surface:
a. One adjustable (height and angle) 15-inch deep shelf with undershelf light, full
length of case, stainless steel.
b. Base deck (adjustable angle) lighted with continuous ledge light, full length of
case, stainless steel.
c. Canopy light (same profile as ledge light), full length of case, stainless steel.
d. Air dam: 3/8 inch thick clear tempered glass at front of base deck.
20. Case front nosepiece: Painted aluminum extrusion to match exterior case color.
C. Item Selection:
A. Salient Characteristics:
1. Integrated Scale/Printer:
2. Electrical:
A. Salient Characteristics:
1. Angle gravity feed type table top slicer with a 11-3/4-inch knife diameter.
2. Positive angle carriage design enabling operator to slice without manual feed.
3. Tilt back and removable carriage system for cleaning and sanitation procedures. Lift lever
for raising and propping slicer to tilted position for cleaning underneath slicer.
4. 12-1/2-inch manual carriage travel.
5. Adjustable variable speed capability: 28, 33, 38, 42, 47, 52 strokes per minute. Speed
may be changed with slicer motor on or off. Slicer may be turned off with a quick turn of
index knob to the closed position after slicing or by toggle type switch, operated by a
push-pull rod.
6. Gauge plate adjustable to cut any thickness up to 1 inch.
7. Carriage shall take food up to 12 inches in width or 7-1/2 inches in diameter.
8. Carriage can be disengaged from power whether slicer is in operation or not.
9. Automatic engagement and speed selector controls located in front of machine.
10. Home-start position of carriage to ensure it is in a convenient position before starting
slicer.
11. Automatically turns off slicer after slicing.
12. Gauge plate interlock protects knife edge when indicator is at zero.
13. Carriage system interlock shall not allow tilt away or removal if gauge plate indicator is
not closed.
14. In the event of power loss, slicer must be restarted before operation can continue.
15. A permanently mounted ring guard with integrated product deflector protects knife. No
tools shall be required for removal of deflector to clean slicer.
16. One-piece 12 gauge knife cover; spring loaded for quick removal and replacement.
17. Gauge plate protects knife edge when indicator is closed.
18. Knife cover shall be quickly removed with a quarter turn of spring loaded locking knob.
19. One lever operation with two Borazon stones to sharpen and hone knife in five seconds.
Removable and top mounted. Knife edge is shielded when sharpener is removed for
cleaning. Borazon stones have lifetime guarantee.
a. Double action setting: First revolution of index cam for precision slicing; second
revolution for thicker slicing selection.
b. Indexing cam holds true to setting during slicing operation.
23. Electroless nickel plated transport single slide rod with an oil reservoir/oil wick for slide
rod bearings.
24. Finish: Stainless steel carriage, knife, and knife cover; anodized aluminum base;
aluminum with ribbed laminated stainless steel face gauge plate.
25. Meat Grip: Thermoplastic front mounted grip swings out of way when not in use.
26. Electrical:
2.7 ITEM 1D09: HOT FOODS, SINGLE SECTION, ROTISSERIE OVEN, 32-CHICKEN,
COUNTER TOP OVEN, ROTISSERIE, COUNTER TOP MODEL, WITH BASE CABINET
A. Salient Characteristics:
1. Stainless steel construction, both interior and exterior, tempered clear glass doors,
lighted cabinet interior for point-of-sale visibility, and fully insulated cabinet with solid
back.
2. Electronic controls to permit programmable cooking cycles plus manual entry mode and
digital display to show temperature and cook/hold times.
3. Food probe provided to connect directly to control panel to display internal temperature of
food product.
4. Door sensors automatically stops/starts rotation, heaters and blowers when cabinet door
is opened.
5. Cooking process to include infrared heating with cross flow convection.
6. Spit rotation switch for easy loading.
7. Eight (8) removable angled spits.
8. Drive assembly, drip trays and drain pans easily disassembled for quick clean-up.
9. Rotisserie parts to have coated surfaces for easier clean-up.
B. Approximate Dimensions:
1. 41 inches wide.
2. 30 inches deep.
3. 44 inches high with legs.
1. Electrical:
D. Accessories:
A. Salient Characteristics:
1. Refer to Division 23 Section Refrigeration Monitoring and Control Systems (RMCS) for
refrigeration monitoring sensors installed by that Section.
2. Self-contained refrigeration system with R-404A refrigerant and bottom mounted air-
cooled condensing unit designed to maintain a product temperature of 30 - 34 deg F.
Condensing unit shall be designed to slide out for ease of maintenance.
3. Electrical: 208 - 230 volts, 60 hertz, 1 phase with (30 amp) NEMA L14-30 plug.
4. Electric condensate dissipator pan.
5. Electronic thermostat temperature controls.
6. Electronic temperature sensors.
7. One solar digital thermometer.
8. Energy efficient fans.
9. Off-cycle defrost.
10. On/Off light switch for case lighting with T-8 fluorescent lamps and electronic ballasts.
11. Leveler legs (NSF 6 inches).
12. CFC free foamed-in-place insulation.
13. Seamless, non-corrosive drain pan.
14. Copper tube aluminum finned coils.
15. Case exterior color as indicated on Drawings, with white interior.
16. Welded steel case frame.
17. Dome Service Case:
a. Upper and lower heating elements to maintain food temperature ranges consistent
with UL Sanitation standards.
b. Individually controlled radiant heaters over each well.
c. Provide a control panel with separate switches for power and lights. Provide
thermometer, and temperature control. Displays food probe temperature (digital
readout), air temperature, and individual on/off displays for radiant heat, water pan
heat and lower heat.
i. Two tempered glass end panels mounted on top of insulated end panels.
1. Model CVT-HT, Combination Case with Heated Dome Service Top And Self-Service
Front.
C. Continuity:
1. Where shown on Drawings, this display case shall physically connect with 1B28, 1D13,
and 1D17 display cases to form a contiguous refrigerated display area, with tempered
glass ends in clerk service area, and without intermediate divider panels in self service
area. Provide insulated end panels only at beginning and end of display case line-up and
where required between refrigerated and dry storage areas.
D. Item Selection:
A. Salient Characteristics:
1. Refer to Division 23 Section Refrigeration Monitoring and Control Systems (RMCS) for
refrigeration monitoring sensors installed by that Section.
2. Self-contained refrigeration system with R-404A refrigerant and bottom mounted air-
cooled condensing unit designed to maintain a product temperature of 30 - 34 deg F.
Condensing unit shall be designed to slide out for ease of maintenance.
3. Electrical: 208 - 230 volts, 60 hertz, 1 phase with (30 amp) NEMA L14-30 plug.
4. Electric condensate dissipator pan.
5. Electronic thermostat temperature controls.
6. Electronic temperature sensors.
7. One solar digital thermometer.
8. Energy efficient fans.
9. Off-cycle defrost.
10. On/Off light switch for case lighting with T-8 fluorescent lamps and electronic ballasts.
11. Leveler legs (NSF 6 inches).
12. CFC free foamed-in-place insulation.
13. Seamless, non-corrosive drain pan.
14. Copper tube aluminum finned coils.
15. Case exterior color as indicated on Drawings, with white interior.
16. Welded steel case frame.
17. Dome Service Case:
Retain above and specify only one glass end panel (below) where
drawings show this display case as an end case in a display case
line-up and physically connected with either 1B28 or 1D17.
g. Two tempered glass end panels mounted on top of insulated end panels.
a. One adjustable (height and angle) 12-inch deep shelf with undershelf light, full
length of case, stainless steel.
b. Base deck area lighted with continuous ledge light, full length of case, stainless
steel.
c. Canopy light (same profile as ledge light), full length of case, stainless steel.
d. Air dam: 3/8 inch thick clear tempered glass at front of base deck.
Note below: Provide one insulated end panel where drawings show
this display case as an end case in a display case line-up and
physically connected with 1B28 or 1D17.
h. Two insulated end panels: Laminated exterior to match case color with stainless
steel interior and stainless edge molding; fabricate top to receive glass end panel.
i. Narrow "U" channel chase at top rear of self-service case for wire service to
optional electrical outlets.
1. Model CVT-D, Combination Case with Refrigerated Dome Service Top And Self-Service
Front.
C. Continuity:
1. Where shown on Drawings, this display case shall physically connect with 1B28 and
1D17 display cases to form a contiguous refrigerated display area, with tempered glass
ends in clerk service area, and without intermediate divider panels in self service area.
Provide insulated end panels only at beginning and end of display case line-up and
where required between refrigerated and dry storage areas.
D. Item Selection:
1. ITEM 1D13-4: Prepared Foods, Refrigerated Display Case, 4 foot Case Length.
2. ITEM 1D13-6: Prepared Foods, Refrigerated Display Case, 6 foot Case Length.
3. ITEM 1D13-8: Prepared Foods, Refrigerated Display Case, 8 foot Case Length.
4. ITEM 1D13-12: Prepared Foods, Refrigerated Display Case, 12 foot Case Length.
2.10 ITEM 1D14-A: CASE, HOT FOODS, HEATED, SELF-SERVICE ISLAND, 3 WELLS
A. Salient Characteristics:
1. The heated island merchandiser/display case is designed to hold precooked hot food at
the precise temperature levels to meet health code requirements and to meet maximum
shelf-life requirements.
2.11 ITEM 1D14-B: CASE, HOT FOODS, HEATED, SELF-SERVICE ISLAND, 5 WELLS
A. Salient Characteristics:
1. The heated island merchandiser/display case is designed to hold precooked hot food at
the precise temperature levels to meet health code requirements and to meet maximum
shelf-life requirements.
2. Five-well heated island merchandiser with 2-inch depth self-service insert.
3. Designed to match profile of existing deli cases.
4. Constructed of stainless steel and clear tempered glass on both sides.
5. Tall profile curved glass case tor maximum product visibility.
6. Designed to use upper and lower heating elements to maintain food temperature ranges
consistent with UL Sanitation standards.
7. Self service from both sides.
8. Cooled landing shelf on both sides.
9. Dual black bumpers to prevent scratching and denting.
10. Provided with a control panel with power switch, light control, thermometer, and
temperature control.
11. Electrical - 120/208V; 3PH; 13 Amp; 60Hz; with cord and plug.
12. Provided with food temperature probe with digital readout.
13. Electronic controls provide food probe temperature, air temperature, individual on/off
displays for lower heat, radiant heat, and water pan heat.
14. Individual controlled radiant heaters over each well.
15. Incandescent lighting for food presentation.
16. Heated water pan for humidified environment.
2.12 ITEM 1D17: PREPARATION AND DISPLAY CASE FOR PIZZA AND SANDWICHES
A. Salient Characteristics:
1. Refer to Division 23 Section Refrigeration Monitoring and Control Systems (RMCS) for
refrigeration monitoring sensors installed by that Section.
2. Self-contained refrigeration system with R-404A refrigerant and bottom mounted air-
cooled condensing unit designed to maintain a product temperature of 30 - 34 deg F.
Condensing unit shall be designed to slide out for ease of maintenance.
3. Electrical: 208 - 230 volts, 60 hertz, 1 phase with (30 amp) NEMA L14-30 plug.
4. Electric condensate dissipator pan.
5. Electronic thermostat temperature controls.
6. Electronic temperature sensors.
7. One solar digital thermometer.
8. Energy efficient fans.
9. Off-cycle defrost.
10. On/Off light switch for case lighting with T-8 fluorescent lamps and electronic ballasts.
11. Leveler legs (NSF 6 inches).
12. CFC free foamed-in-place insulation.
13. Seamless, non-corrosive drain pan.
14. Copper tube aluminum finned coils.
15. Case exterior color as indicated on Drawings, with stainless steel interior.
16. Welded steel case frame.
17. Sandwich Preparation Station Top:
Delete above and specify only one glass end panel (below) where
drawings show this display case as an end case in a display case
line-up and physically connected with 1D13.
Two tempered glass end panels mounted on top of insulated end panels.
a. One adjustable (height and angle) 12-inch deep shelf with undershelf light, full
length of case, stainless steel.
b. Base deck area lighted with continuous ledge light, full length of case, stainless
steel.
c. Canopy light (same profile as ledge light), full length of case, stainless steel.
d. Air dam: 3/8 inch thick clear tempered glass at front of base deck.
e. Case front nosepiece: Painted aluminum extrusion to match exterior case color.
f. Molded bumper (1 inch wide) across front of display case, centered on nosepiece.
Color: Black.
g. Stainless steel kickplate.
Retain below and specify only one insulated end panel where
drawings show this display case as an end case in a display case
line-up and physically connected with 1B28 or 1D13.
h. Two insulated end panels: Laminated exterior to match case color with stainless
steel interior and stainless steel edge molding; fabricate top to receive glass end
panel.
i. Rear refrigerated storage, medium temperature, with see-through glass, NSF-7
certified sliding doors, base and adjustable height upper, lighted.
j. Narrow "U" channel chase at top rear of self-service case for wire service to
optional electrical outlets.
1. Model CVT-WC-SG-IP, Preparation And Display Case For Pizza And Sandwiches.
C. Continuity:
1. Where shown on Drawings, this display case shall physically connect with 1D13 and
1B28 display cases to form a contiguous refrigerated display area, with tempered glass
ends in clerk service area, and without intermediate divider panels in self service area.
D. Item Selection:
1. Item 1D17-4: Preparation and Display Case for Pizza and Sandwiches, 4 foot Case
Length.
2. Item 1D17-6: Preparation and Display Case for Pizza and Sandwiches, 6 foot Case
Length.
3. Item 1D17-8: Preparation and Display Case for Pizza and Sandwiches, 8 foot Case
Length.
4. Item 1D17-12: Preparation and Display Case for Pizza and Sandwiches, 12 foot Case
Length.
A. Salient Characteristics:
1. Portable deli slicing table with mounting beam and saddle for automatic slicer.
a. Provide special Hobart style saddles required for Hobart brand automatic slicers.
2. Construct of heavy gage 304 stainless steel with tubular steel frame.
3. Provide unit with the following accessories:
a. Removable, height adjustable stainless steel scale shelf with marine edges and
vibration dampening mounts for electronic weighing and labeling machine.
b. Flexible boots that cover the slicer feet and mounting saddles.
c. Concave stainless steel pan under slice mounting beam with slide out stainless
steel crumb tray.
d. 3 axis adjustable deli bag and tissue/glove holder.
e. Additional Lower side frame mounted tissue/glove box holder.
f. Frame mounted knife rack.
g. Pull out and removable lower shelf.
h. Removable polyethylene cutting board on top left side with drain slots.
i. A mid-shelf, removable, slide out Polsan cutting board with built-in cleaning bottle
holder.
j. Lower shelf with splashguard kickplate.
k. A fixed left side handle grip for use in moving the table.
l. A tall adjustable ergonomic handle on right side of the table.
A. Salient Characteristics:
9. Electrical:
A. Salient Characteristics:
1. Construct table completely of 14 gauge, type 304 stainless steel except as described
below.
2. NSF certified for contact with any type of food in commercial food preparation.
3. Reinforce top work surface and under-shelf with 14 gauge, 1-inch by 2-inch stainless
steel channel.
4. Deliver table completely set-up with all welded assembly.
a. 30 inches deep.
b. 36-inch working height.
c. 6-foot length.
11. Under-Shelf: Reinforced, one piece, 16 gauge, 304 stainless steel construction. Weld
under-shelf to the inside of the table legs and size to match table dimensions. Locate
under-shelf 12 inches above the floor.
A. Salient Characteristics:
1. Table shall be constructed entirely of type 304 stainless steel with a minimum of 14
gauge table top and frame and a minimum 16 gauge other surfaces.
2. Table shall be certified for contact with any type of food in commercial food preparation.
3. Table shall be delivered completely set-up with all welded assembly.
4. Backsplash shall be 6 inch high with 45 degree return angle to work surface.
5. Top work surface shall be provided with 1-1/2 inch rolled edge on front. Sides of table to
be provided with 90 degree bend for table line-up.
6. Table legs fitted with sanitary stainless steel bullet feet that adjust 1 inch.
7. Provided with heavy duty sliding doors that slide on stainless steel roll in track. Doors
shall be easily removable for cleaning.
8. Approximate Table Dimensions:
a. 30 inch deep.
b. 36 inch working height.
c. 6-foot length.
PART 3 - EXECUTION
3.1 INSPECTION
A. Check that surfaces to which work will be secured are sound and free of irregularities interfering
with installation. Do not begin installation until satisfactory conditions have been corrected.
B. Ensure that roughed-in openings, built-in anchorage, and reinforcing required for proper
installation of work of this Section are correctly sized, installed and located.
C. Obtain electrical and mechanical service characteristics and rough-in locations from site.
3.3 INSTALLATION
C. Set units plumb, square and true, securely anchored to building structure.
E. Seal spaces between built-in equipment, walls and columns with preformed foam sealants
specified in Division 07 Section Joint Sealants, shim level and rigid, use proper type anchoring
devices for materials encountered and usage expected.
F. Cut, fit and patch; coordinate with work of other Sections involved.
G. Cut and drill tops, backs, sides and bottoms for service outlets and fixtures. Install fixtures and
fittings. Make connections to services.
H. Sequence installation and erection to ensure that mechanical and electrical connections are
effected.
I. Deliver instruction sheets to Contracting Officer and instruct Government's personnel in the
proper use, adjustment, and maintenance of equipment.
A. Adjust doors, drawers, hardware fixtures, and other moving and operating parts to function
smoothly and correctly.
D. Clean equipment cases, counters, shelves, glass, legs, hardware, fittings and fixtures. Wipe
down surfaces to remove fingerprints and markings and leave in clean condition.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each product specification is current. Provide written notification to the DeCA
Project Manager when this verification has been completed.
B. The guide specification specifies equipment typically used in a commissary facility. The A/E shall
edit the guide specification, deleting equipment not required on a particular project.
C. It may be necessary to specify equipment that is not included in the guide specification. The A/E will
be responsible for developing UFGS format product specifications for insertion into the guide
specification.
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
E. Verify that proper utility connections and mounting heights (water, drain, vent, refrigeration,
electrical, communication, etc.) are shown on Contract Documents for all specified equipment.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
2.1 MATERIALS
B. Fasteners:
1. Conceal fasteners where possible; otherwise, locate where they will be as inconspicuous
as possible. Size fasteners to support closure panels, with fasteners spaced to prevent
buckling or waviness in finished surfaces.
2. Drill and tap holes needed for securing closure panels to other surfaces.
2.2 FABRICATION
A. General:
1. Miter or cope trim members at corners and reinforce with bent metal splice plates to form
tight joints.
2. Coordinate dimensions and attachment methods of closure panels with those of adjoining
construction to produce integrated assemblies with closely fitting joints and with edges
and surfaces aligned, unless otherwise indicated.
3. Form metal to profiles indicated, in maximum lengths to minimize joints. Produce flat,
flush surfaces without cracking or grain separation at bends. Fold back exposed edges
of unsupported sheet metal to form a 1/2-inch- wide hem on the concealed side, or ease
edges to a radius of approximately 1/32 inch and support with concealed stiffeners.
4. Increase metal thickness or reinforce with concealed stiffeners, backing materials, or
both, as needed to provide surface flatness specified for stretcher-leveled sheet metal
and sufficient strength for indicated use.
5. Support joints with concealed stiffeners as needed to hold exposed faces of adjoining
sheets in flush alignment.
6. Build in straps, plates, and brackets as needed to support and anchor fabricated items to
adjoining construction.
7. Provide support framing, mounting and attachment clips, splice sleeves, fasteners, and
accessories needed to install closure panels.
A. General:
1. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
2. Complete mechanical finishes of flat sheet metal surfaces before fabrication where
possible. After fabrication, finish all joints, bends, abrasions, and other surface blemishes
to match sheet finish.
3. Protect mechanical finishes on exposed surfaces from damage by applying a strippable,
temporary protective covering before shipping.
1. Remove tool and die marks and stretch lines or blend into finish.
2. Grind and polish surfaces to produce uniform, directionally textured, polished finish
indicated, free of cross scratches. Run grain with long dimension of each piece.
3. Bright, Directional Polish: No. 4 finish.
4. When polishing is completed rinse surfaces. Remove embedded foreign matter and
leave surfaces chemically clean.
PART 3 - EXECUTION
3.1 INSPECTION
A. Check that surfaces to which work will be secured are sound and free of irregularities interfering
with installation. Do not begin installation until satisfactory conditions have been corrected.
3.2 PREPARATION
A. Obtain dimensions from the site affecting work of this Section. Ensure that roughed-in openings,
built-in anchorage, and reinforcing required for proper installation of work of this Section are
correctly sized, installed and located.
A. General:
1. Locate and place closure panel fabrications level, plumb, and in alignment with adjacent
construction.
2. Use concealed anchorages where possible. Provide brass or lead washers fitted to
screws where needed to protect metal surfaces.
3. Form tight joints with exposed connections accurately fitted together.
B. Air Plenums:
1. Install closure panels with airtight connections to plenums using sealant or gaskets, and
to allow for service and maintenance.
A. Protect finishes of closure panels from damage during construction period. Remove temporary
protective coverings at time of final acceptance.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each product specification is current. Provide written notification to the DeCA
Project Manager when this verification has been completed.
B. The guide specification specifies equipment typically used in a commissary facility. The A/E shall
edit the guide specification, deleting equipment not required on a particular project.
C. It may be necessary to specify equipment that is not included in the guide specification. The A/E will
be responsible for developing UFGS format product specifications for insertion into the guide
specification.
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
E. Verify that proper utility connections and mounting heights (water, drain, vent, refrigeration,
electrical, communication, etc.) are shown on contract documents for all specified equipment.
F. If wedge configurations are utilized in multi-deck meat display case line-up, provide full height
gypsum wallboard on metal stud wedge shapes conforming to case configuration. Provide
adequate clear space at ends of display cases for necessary end panels and clearances required
by manufacturer.
G. If return air will be taken from beneath refrigerated display cases, provide air tight closures at
tops and sides of display cases to insure that return air is drawn from beneath display case.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product data for each item of equipment required, including the manufacturer's standard details
and installation and maintenance instructions.
B. Submittal List:
A. Installer Qualifications: Engage an experienced installer to perform work of this Section who is
an authorized representative of the meat department equipment manufacturer, who has
specialized in installing meat department equipment, who has completed installations similar in
design and extent to that indicated for this Project, and who has a record of successful
in-service performance.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Salient Characteristics:
1. Electronic digital scale and mobile stand, designed for weighing boxes of product during
the receiving process.
2. Electronic digital scale:
1) 17 inches wide.
2) 25 inches deep.
3) 30 inches high.
e. Electrical:
3. Mobile Stand:
a. Designed to allow for mobility of the scale and safe weighing of product while the
scale is on the mobile stand.
b. All steel construction, capable of supporting 500 pounds while mobile.
c. Push handle bar approximately 35 inches above floor, five inch variance.
d. Platform height 14 inches, two-inch variance.
e. Four 5-inch diameter casters (one-inch variance) or wheels, two locking.
A. Salient Characteristics:
1. Portable, motor driven, continuous, cleated belt conveyor for handling blocks of ground
meat.
2. Automatically elevates meat loaves from meat molding machine and mixer/grinder.
3. Steel conveyor bed with sanitary plated finish.
4. Adjustable legs, low end 13 inches to 16 inches, high end 33 inches to 41 inches.
5. Motor and switch shall be interchangeable for mounting on either side.
6. Nominal Dimensions:
a. 76 inches wide.
b. 21 inches deep.
c. 41 inches high.
1. Model "CB-0606."
A. Salient Characteristics:
1. Table model.
2. Grind 8 Lbs. per minute based on 1/8 inch plate.
3. Enclosed stainless steel housing with no sharp edges, projections, cracks or crevices.
a. 13 inches wide.
b. 24 inches deep.
c. 23 inches high.
12. Electrical:
A. Salient Characteristics:
1. Molding device and integral automatic paper feed unit that inserts paper separator
between each square or molded meat block.
2. Molding machine adjustable to produce 1/2-lb to 2-lb blocks with an operating rate of
2,400 to f 3,600 blocks per hour.
3. With adapter ring to fit on a #52 chopper head.
4. No-tool assembly and disassembly.
5. Nominal Dimensions:
a. Width 22 inches.
b. Depth 10 inches.
c. Height 14 inches.
A. Salient Characteristics:
1. Floor model type with adjustable feet (one inch minimum height adjustability).
2. Vertical cutting clearance 17-1/2 inches.
3. Horizontal cutting clearance 15-3/4 inches.
4. All surfaces (other than blade and pusher block) coming into contact with meat: Polished
stainless steel.
5. Movable Carriage Tray: Stainless steel, 16 inches by 24-1/4 inches, mounted on ball
bearing wheels.
6. Stationary Cutting Table: Stainless steel, 21-1/2 inches by 39-5/8 inches.
7. Gauge plate regulates cutting thickness.
A. Salient Characteristics:
3. Foot switch: Pneumatically operated foot switch for hands free operation, with 12-foot
cord.
4. Electrical:
A. Salient Characteristics:
3. Foot switch: Pneumatically operated foot switch for hands free operation, with 12-foot
cord.
4. Electrical:
A. Salient Characteristics:
1. Components include a feed tray, side notch paper feed, patty molder, and counter
stacker conveyor.
2. Designed as a tabletop model. Stainless steel construction with moving components
enclosed or shielded by guards.
3. Production rate factory set at 2100 patties per hour.
12. Electrical:
A. Salient Characteristics:
1. The machine shall have a rigid frame, electric motor drive, package conveyor, heat
sealing belt, cold film cut-off, package elevator or straight through system film roll holder.
2. Equipment shall be of the same type, capacity, and design that has been used in
successful commercial supermarket operations for a minimum of two years.
3. Equipment shall be supported by a service organization that will provide needed service
seven days a week. The response time to a service call on a normal business day will be
within four hours.
4. Master Scale Management System:
a. System shall automatically weigh, wrap, and apply label to packages at a minimum
rate of 30 packages per minute, automatically feeding, measuring, cutting,
wrapping, and heat sealing stretch plastic film.
b. The machine shall be designed to allow the operator to monitor all switches and
change package size.
c. The automatic wrapper shall accommodate one roll of 13-inch wide stretch film,
with capacity to wrap 1S to "family packs" 10- by 14-inches.
d. The film stretching mechanism shall grip and stretch the film around all sides of the
package. Sensors shall detect the required film size for the package and
economize film use.
e. The film rack shall be located within the central control area to allow the operator
full access to film roll.
f. Wrapper shall be equipped with a safety stop switch.
g. A Cold film cut-off is required; the film cutter shall not be hot-wire system.
h. Wrapper to have a rigid frame, electric motor drive, package conveyor, and film roll
holders.
i. Temperature range: 41 to 95 deg F.
j. Equipped with casters.
k. Electrical: 208/230 volt, 60 hertz, single phase 2kVa.
a. The scale, labeler and printer system shall be integrated with the wrapper for
automatic prepackaging.
b. System shall have easy access to the scale area for weighing and labeling pre-
wrapped and oversize packages.
c. Scale and printer system shall be capable of printing the USDA mandated safe
handling statement for raw or partially cooked meat, nutrifacts information,
expanded text, graphics, and special messages.
d. Labeler shall apply price labels to wrapped packages.
e. Printer Construction: Stainless steel enclosure.
f. Prints 5 label formats: 2.1, 2.4, 3.3, 3.7, 4.2.
g. Prints 30 custom formats.
h. Label capacity: 4,500.
i. The system shall have a controller that controls all weighing, labeling, and printing
functions on all manual, semi-automatic, and full automatic Prepack and Central
Pack applications.
j. Electrical:
7. Power Conveyor:
a. Power roller conveyor used to transport wrapped and labeled packages from
labeler discharge to gravity roller conveyor.
b. Conveyor dimension approximately 18 inches wide by 51-inch 180 degree wide
arc.
c. Electrical: 115 volt, 60 hertz, single phase.
8. Roller Conveyor:
a. Gravity roller conveyor used to transport wrapped and labeled packages from
power conveyor to rotary accumulator bin.
b. Conveyor dimension approximately 18 inches wide.
A. Salient Characteristics:
1. The machine shall have a rigid frame, electric motor drive, package conveyor, heat
sealing belt, cold film cut-off, package elevator or straight through system film roll holder.
2. Equipment shall be of the same type, capacity, and design that has been used in
successful commercial supermarket operations for a minimum of two years.
3. Equipment shall be supported by a service organization that will provide needed service
seven days a week. The response time to a service call on a normal business day will be
within four hours.
4. Master Scale Management System:
a. Consists of PC based software that is Windows based (98, 2000, XP, and ME) and
designed to manage satellite scales within the meat department.
b. Provide with one 3.5 inch disk with software.
c. Provide with all required hardware to connect all scales in meat department to the
scale management system.
5. Automatic Wrapper:
a. The scale, labeler and printer system shall be integrated with the wrapper for
automatic prepackaging.
b. System shall have easy access to the scale area for weighing and labeling pre-
wrapped and oversize packages.
c. Scale and printer system shall be capable of printing the USDA mandated safe
handling statement for raw or partially cooked meat, nutrifacts information,
expanded text, graphics, and special messages.
d. Labeler shall apply price labels to wrapped packages.
e. Printer Construction: Stainless steel enclosure.
f. Prints 5 label formats: 2.1, 2.4, 3.3, 3.7, 4.2.
g. Prints 30 custom formats.
h. Label capacity: 4,500.
i. The system shall have a controller that controls all weighing, labeling, and printing
functions on all manual, semi-automatic, and full automatic Prepack and Central
Pack applications.
j. Electrical:
7. Power Conveyor:
a. Power roller conveyor used to transport wrapped and labeled packages from
labeler discharge to gravity roller conveyor.
b. Conveyor dimension approximately 18 inches wide by 51-inch 180 degree wide
arc.
c. Electrical: 115 volt, 60 hertz, single phase.
8. Roller Conveyor:
a. Gravity roller conveyor used to transport wrapped and labeled packages from
power conveyor to rotary accumulator bin.
b. Conveyor dimension approximately 18 inches wide.
2.12 Item 1M30: SCALE AND PRINTER WITH 3-ROLL WRAPPER SYSTEM
A. Salient Characteristics:
1. Designed to operate in refrigerated rooms with temperature range of 41 to 104 deg F and
10 to 90 percent relative humidity, non-condensing.
2. Controller:
a. Scale Base: Die cast aluminum base with stainless steel weighing
platter/wrapping surface approximately 13.2 inches wide by 11.4 inches deep, one
inch variance.
b. 50 lb by 0.01 capacity.
c. Power provided by connection to controller.
d. Heat Seal Wrapper:
1) Sealing hot plate surface covered with non-stick Teflon, 15 inches wide by 6
inches deep.
2) Solid state electronics controlled hot rod cut-off bar.
4. Printer:
a. Automatically prints product name, unit price, total price, and weight on label, for
hand application to wrapped packages. Capable of accommodating pre-printed
labels with USDA statement and organization logo.
b. Prints a minimum of 2000 characters per label for ingredients and nutritional
information.
c. Minimum of 4000 PLU (product look-up code) memory for item file, using 1-6 digit
PLU codes.
d. Prints standard label stock widths of 1.5 inch and 2.25 inch, with label lengths from
1-6 inch minimum.
e. Digital clock automatically updates shelf life.
f. Printer Construction: Stainless steel enclosure.
g. Prints 5 label formats: 2.1, 2.4, 3.3, 3.7, 4.2.
h. Prints 30 custom formats.
i. Produces universal bar code.
j. Label capacity: 4,500.
6. Electrical:
A. Salient Characteristics:
1. Angle gravity feed type table top slicer with a 11-3/4-inch knife diameter.
2. Positive angle carriage design enabling operator to slice without manual feed.
3. Tilt back and removable carriage system for cleaning and sanitation procedures. Lift lever
for raising and propping slicer to tilted position for cleaning underneath slicer.
4. 12-1/2-inch manual carriage travel.
5. Adjustable variable speed capability: 28, 33, 38, 42, 47, 52 strokes per minute. Speed
may be changed with slicer motor on or off. Slicer may be turned off with a quick turn of
index knob to the closed position after slicing or by toggle type switch, operated by a
push-pull rod.
6. Gauge plate adjustable to cut any thickness up to 1 inch.
7. Carriage shall take food up to 12 inches in width or 7-1/2 inches in diameter.
8. Carriage can be disengaged from power whether slicer is in operation or not.
9. Automatic engagement and speed selector controls located in front of machine.
10. Home-start position of carriage to ensure it is in a convenient position before starting
slicer.
11. Automatically turns off slicer after slicing.
12. Gauge plate interlock protects knife edge when indicator is at zero.
13. Carriage system interlock shall not allow tilt away or removal if gauge plate indicator is
not closed.
14. In the event of power loss, slicer must be restarted before operation can continue.
15. A permanently mounted ring guard with integrated product deflector protects knife. No
tools shall be required for removal of deflector to clean slicer.
16. One-piece 12 gauge knife cover; spring loaded for quick removal and replacement.
17. Gauge plate protects knife edge when indicator is closed.
18. Knife cover shall be quickly removed with a quarter turn of spring loaded locking knob.
a. Double action setting: First revolution of index cam for precision slicing; second
revolution for thicker slicing selection.
b. Indexing cam holds true to setting during slicing operation.
23. Electroless nickel plated transport single slide rod with an oil reservoir/oil wick for slide
rod bearings.
24. Finish: Stainless steel carriage, knife, and knife cover; anodized aluminum base;
aluminum with ribbed laminated stainless steel face gauge plate.
25. Meat Grip: Thermoplastic front mounted grip swings out of way when not in use.
26. Electrical:
A. Salient Characteristics:
10. Electrical:
A. Salient Characteristics:
2.16 ITEM 4TMP-4: TABLE, STAINLESS STEEL, MEAT PREPARATION WITH POLY TOP AND
WITHOUT BACKSPLASH
A. Salient Characteristics:
1. Construct table completely of 16 gauge, Type 304 stainless steel except as described
below.
2. NSF certified for contact with any type of food in commercial food preparation.
3. Table shall be delivered completely set-up with all welded assembly.
4. Table shall be provided with polyethylene cutting boards, 3/4 inch thick. Poly cutting
surface shall be dishwasher safe and high-temperature safe to 180 deg F and may be
steam cleaned.
5. Table top is an open frame with the poly boards sectioned for easy removal. Removable
and replaceable clips shall d poly top secure.
6. Approximate Table Dimensions:
a. 30 inches deep.
b. 36-inch working height.
c. 4-foot length.
2.17 ITEM 4TMP-6: TABLE, STAINLESS STEEL, MEAT PREPARATION WITH POLY TOP AND
WITHOUT BACKSPLASH
A. Salient Characteristics:
1. Construct table completely of 16 gauge, Type 304 stainless steel except as described
below.
2. NSF certified for contact with any type of food in commercial food preparation.
3. Table shall be delivered completely set-up with all welded assembly.
4. Table shall be provided with polyethylene cutting boards, 3/4 inch thick. Poly cutting
surface shall be dishwasher safe and high-temperature safe to 180 deg F and may be
steam cleaned.
5. Table top is an open frame with the poly boards sectioned for easy removal. Removable
and replaceable clips shall d poly top secure.
6. Approximate Table Dimensions:
a. 30 inches deep.
b. 36-inch working height.
c. 6-foot length.
7. Under-Shelf: Reinforced, one piece, 16 gauge, 304 stainless steel construction. Weld
under-shelf to the inside of the table legs and size to match table dimensions. Locate
under-shelf 12 inches above the floor.
8. Table shall be provided with stainless steel legs fitted with bullet feet.
2.18 ITEM 4TMPBS-6: TABLE, STAINLESS STEEL, MEAT PREPARATION WITH POLY TOP AND
BACKSPLASH
A. Salient Characteristics:
1. Construct table completely of 14 gauge, Type 304 stainless steel except as described
below.
2. NSF certified for contact with any type of food in commercial food preparation.
3. Reinforce top work surface and under-shelf with 14 gauge, 1-inch by 2-inch stainless
steel channel. Provide table side edges with 90 degree bend for table line-up.
4. Deliver table completely set-up with all welded assembly.
5. Backsplash: 6 inches high with 45 degree return angle to work surface.
a. 30 inches deep.
b. 36-inch working height.
c. 6-foot length.
11. Under-Shelf: Reinforced, one piece, 16 gauge, 304 stainless steel construction. Weld
under-shelf to the inside of the table legs and size to match table dimensions. Locate
under-shelf 12 inches above the floor.
A. Salient Characteristics:
1. Construct table completely of 14 gauge, Type 304 stainless steel except as described
below.
2. NSF certified for contact with any type of food in commercial food preparation.
3. Reinforce top work surface and under-shelf with 14 gauge, 1-inch by 2-inch stainless
steel channel.
4. Deliver table completely set-up with all welded assembly.
5. Backsplash and top work surface: One piece stainless steel construction.
6. Backsplash: 6 inches high and coved to work surface.
7. Provide top work surface with 1-1/2-inch rolled edge on front and side edges and with 90
degree bend for table line-up.
8. Provide table with 1-5/8-inch diameter, 16 gauge legs fitted with 1-1/2-inch sanitary
adjustable bullet feet.
9. Provide legs fitted into stainless steel sockets and welded to underside of top.
10. Approximate Table Dimensions:
a. 30 inches deep.
b. 36-inch working height.
c. 6-foot length.
11. Under-Shelf: Reinforced, one piece, 16 gauge, 304 stainless steel construction. Weld
under-shelf to the inside of the table legs and size to match table dimensions. Locate
under-shelf 12 inches above the floor.
3.1 INSPECTION
A. Rough-In Work: Examine roughed-in mechanical and electrical services, installation of floors,
walls, columns, and ceilings, and other conditions under which meat department equipment
work is to be installed; verify dimensions of services and substrates before fabricating work.
Notify Contractor of unsatisfactory locations and dimensions of other work and of unsatisfactory
conditions for proper installation of meat department equipment. Do not proceed with
fabrication and installation until unsatisfactory dimensions and conditions have been corrected
in manner satisfactory to Installer.
A. General:
1. Set each item of nonmobile and nonportable equipment securely in place, level, and
adjust to correct height. Anchor to supporting substrate where indicated and where
required for sustained operation and use without shifting or dislocation. Conceal
anchorages where possible. Adjust countertops and other work surfaces to level
tolerance of 1/16-inch maximum offset, and maximum variation from level or indicated
slope of 1/16-inch per foot.
B. Field Joints:
C. Enclosed Spaces:
1. Treat spaces that are inaccessible after equipment installation by covering horizontal
surfaces with powdered borax at rate of 4 oz. per sq. ft.
E. Cutouts:
1. Provide cutouts in meat department equipment where required to run plumbing or electric
lines through equipment items for final connections.
1. Install all around each unit to make joints airtight, watertight, vermin-proof, and sanitary
for cleaning purposes. In general, make sealed joints not less than 1/8-inch wide, and
stuff backer rod to shape sealant bead properly, at 1/4-inch depth. Shape exposed
A. Testing:
1. Coordinate start-up of meat department equipment when service lines have been tested,
balanced, and adjusted for pressure, voltage, and similar considerations. Before testing,
lubricate each equipment item in accordance with manufacturer's recommendations.
3.4 CLEANING
A. After completion of installation and other major work in meat department areas, remove
protective coverings, if any, and clean meat department equipment, internally and externally.
Restore exposed and semiexposed finishes to remove abrasions and other damages; polish
exposed-metal surfaces and touch-up painted surfaces. Replace work that cannot be
successfully restored.
1. Prior to date of acceptance on meat department equipment work, buff exposed stainless
steel finishes lightly, using power buffer and polishing rouge or grit of No. 400 or finer.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each product specification is current. Provide written notification to the DeCA
Project Manager when this verification has been completed.
B. The guide specification specifies equipment typically used in a commissary facility. The A/E shall
edit the guide specification, deleting equipment not required on a particular project.
C. It may be necessary to specify equipment that is not included in the guide specification. The A/E will
be responsible for developing UFGS format product specifications for insertion into the guide
specification.
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
E. Verify that proper utility connections and mounting heights (water, drain, vent, refrigeration,
electrical, communication, etc.) are shown on Contract Documents for all specified equipment.
F. If wedge configurations are utilized in produce display case line-up, provide full height gypsum
wallboard on metal stud wedge shapes conforming to case configuration. Provide adequate
clear space at ends of display cases for necessary end panels and clearances required by
manufacturer.
G. If return air will be taken from beneath refrigerated display cases, provide air tight closures at
tops and sides of display cases to insure that return air is drawn from beneath display case.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
1. For each item of equipment required, including the manufacturer's standard details and
installation and maintenance instructions.
A. Installer Qualifications: Engage an experienced installer to perform work of this Section who is
an authorized representative of the produce department equipment manufacturer, who has
specialized in installing produce department equipment, who has completed installations similar
in design and extent to that indicated for this Project, and who has a record of successful in-
service performance.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Salient Characteristics:
1) 22 inches wide.
2) 24 inches deep.
3) 27 inches high.
a. In-line water filtration system for ice flaker machines with volume up to 1,500
lbs/day.
b. Equip unit with replaceable water filter and provide an additional replacement filter
cartridge.
c. Plumbing:
1) 7 inches wide.
2) 7 inches deep.
3) 29 inches high.
3. Frame Assembly:
a. Steel frame designed to support the ice flaker positioned over the portable cart to
allow for continuous flow of flaked ice into the portable cart.
b. Baked enamel (gray).
c. Nominal frame dimensions: 33-1/4 inches wide, 39-3/4 inches long, 42-3/4 inches
high.
a. Ice storage bin designed to receive flaked ice from the top mounted ice flaker
machine.
b. Capacity: 260 lbs.
c. Stainless steel bin exterior, polyethylene bin liner, and chute adapter.
d. Mobile bin with four casters and push/pull bar.
e. Plumbing Connection: 5/8 inch bin drain fitting that can be adapted to plastic or
copper drain line.
f. Nominal bin dimensions: 26-1/2 inches wide, 39-3/4 inches long, 38-1/4 inches
high.
5. Overall height of assembly when ice flaker is mounted onto the frame shall not exceed 81
inches high.
A. Salient Characteristics:
1. Modular ice flaker with storage bin and removable cart for transporting ice to sales
floor/display areas.
2. Ice Flaker Machine:
a. Self-contained refrigeration.
b. Non-ozone depleting refrigerant R-404A.
c. Air cooled condenser.
d. Volume production of ice per 24 hour period based on air/water temperatures:
h. Approximate Dimensions:
1) 30 inches wide.
2) 24 inches deep.
3) 27 inches high.
a. In-line water filtration system for ice flaker machines with volume up to 1,500
lbs/day.
b. Unit equipped with one replaceable water filter.
c. Plumbing:
d. Approximate Dimensions:
1) 7 inches wide.
2) 7 inches deep.
3) 29 inches high.
a. Elevated ice flaker storage bin and base designed to support ice flaker machine
and with mobile cart beneath to receive flaked ice.
b. Each unit standard with bin, base, cart with lid, and ice paddle.
c. Stainless steel frame base and exterior of ice storage bin.
d. Storage bin and chute adapter designed to receive flaked ice from top-mounted ice
flaker machine. Custom fabricate top of storage bin to form fit ice flaker machine.
e. Provide ice storage bin with one polyethylene snout and lift door for frontal access
to the ice product.
f. Capacity: 740 lbs.
g. Provide stationary ice cabinet and mobile cart with built-in drains.
h. Equip mobile cart with casters (two swivel locking) and push/pull bar.
i. Equip cart with 6 polyethylene ice tote accessory inserts, with capacity of 25 lbs of
ice per insert.
1) 25 inches wide.
2) 42 inches deep.
3) 35 inches high.
1) 31 inches wide.
2) 40 inches deep.
3) 60 inches high with legs.
A. Salient Characteristics:
1. Modular ice flaker with storage bin and removable carts for transporting ice to sales
floor/display areas.
2. Ice Flaker Machine:
a. Self-contained refrigeration.
b. Non-ozone depleting refrigerant R-404A.
c. Air cooled condenser.
d. Volume production of ice per 24 hour period based on air/water temperatures:
h. Approximate Dimensions:
1) 42 inches wide.
2) 24 inches deep.
3) 27 inches high without legs.
a. In-line water filtration system for high volume ice flaker machines exceeding 2,200
lbs/day.
b. Unit equipped with three replaceable water filters.
c. Plumbing:
d. Approximate Dimensions:
1) 21 inches wide.
2) 6 inches deep.
3) 30 inches high.
a. Elevated ice flaker storage bin and base designed to support ice flaker machine
and with mobile carts beneath to receive flaked ice.
b. Each unit standard with bin, base, carts with lids, and ice paddle.
c. Stainless steel frame base and exterior of ice storage bin.
d. Storage bin and chute adapter designed to receive flaked ice from top-mounted ice
flaker machine. Custom fabricate top of storage bin to form fit ice flaker machine.
e. Provide ice storage bin with one polyethylene snout and lift door for frontal access
to the ice product.
f. Capacity: 1830 lbs.
g. Provide stationary ice cabinet and mobile carts with built-in drains.
h. Equip mobile carts with casters (two swivel locking) and push/pull bar.
i. Equip each cart with 6 polyethylene ice tote accessory inserts, with capacity of 25
lbs) of ice per insert.
j. Approximate Cart Dimensions:
1) 25 inches wide.
2) 42 inches deep.
3) 35 inches high.
1) 60 inches wide.
2) 40 inches deep.
3) 75 inches high with legs.
1. Storage Bin with Base and Dual Portable Carts Model ITS1350SG-60.
A. Salient Characteristics:
1. Integrated Scale/Printer:
2. Electrical:
A. Salient Characteristics:
9. Electrical:
A. Salient Characteristics:
1) 30 inches deep.
2) 36-inch working height.
3) 6-foot length.
A. Salient Characteristics:
1. Electronic digital scale and mobile stand, designed for weighing boxes of product during
the receiving process.
1) 17 inches wide.
2) 25 inches deep.
3) 30 inches high.
4) Two-inch variance each dimension, bench style.
5) Approximately 44 inches high with scale mounted on the stand.
e. Electrical:
3. Mobile Stand:
a. Designed to allow for mobility of the scale and safe weighing of product while the
scale is on the mobile stand.
b. All steel construction, capable of supporting 500 pounds while mobile.
c. Push handle bar approximately 35 inches above floor, five inch variance.
d. Platform height 14 inches, two-inch variance.
e. Four 5-inch diameter casters (one-inch variance) or wheels, two locking.
A. Salient Characteristics:
1. Designed to operate in refrigerated rooms with temperature range of 41 to 104 deg F and
10 to 90 percent relative humidity, non-condensing.
2. Controller:
a. Scale Base: Die cast aluminum base with stainless steel weighing
platter/wrapping surface approximately 13.2 inches wide by 11.4 inches deep, one
inch variance.
b. 50 lb by 0.01 capacity.
c. Power provided by connection to controller.
d. Heat seal wrapper:
e. Sealing hot plate surface covered with non-stick Teflon, 15 inches wide by 6
inches deep.
4. Printer:
a. Automatically prints product name, unit price, total price, and weight on label, for
hand application to wrapped packages. Capable of accommodating pre-printed
labels with USDA statement and organization logo.
b. Prints a minimum of 2000 characters per label for ingredients and nutritional
information.
c. Minimum of 4000 PLU (product look-up code) memory for item file, using 1-6 digit
PLU codes.
d. Prints standard label stock widths of 1.5 inch and 2.25 inch, with label lengths from
1-6 inch minimum.
e. Digital clock automatically updates shelf life.
f. Printer Construction: Stainless steel enclosure.
g. Prints 5 label formats: 2.1, 2.4, 3.3, 3.7, 4.2.
h. Prints 30 custom formats.
i. Produces universal bar code.
j. Label capacity: 4,500.
6. Electrical:
A. Salient Characteristics:
a. 84 inches long.
b. 48 inches wide.
c. 24 inches high.
2.11 ITEM 2P08-A: TILT TOP DISPLAY TABLE, PRODUCE ITEMS, WOODEN, EURO TYPE
A. Salient Characteristics:
a. Removable Side Rails: Two each (per table) removable oak side rails complete
with mounting hardware. Rounded top to reduce product bruising. Pre-drilled and
specific length to match table tilt-top depth.
b. Front Guard: One each (per table) clear front guard (product stop) which allows
full view of product. Constructed of heavy duty 0.177 thickness plastic, without
holes. Approximate dimensions 6 inches high by 4 inches deep (L-shape) by 48
inches long or sized appropriately to match table tilt-top width.
c. Leg Ties: Four each (per table) leg ties. Constructed of black nylon straps 1/4
inches by 24 inches with locking mechanism. Designed to prevent movement of
tables when two or more tables are joined, and easily removable and reusable.
d. Horizontal Product Stop: One each (per table) oak horizontal divider (product
stop). Designed to divide table into horizontal sections and sized to match width of
table.
e. Vertical Product Stop: One each (per table) oak vertical divider (product stop).
Designed to divide the table into vertical sections and sized to match the depth of
the table.
f. Interlocking Pans: Four each (per table) interlocking pans designed to allow
merchandising of multiple items on one table. Constructed of black ABS plastic
with interlocking pans to restrict movement. Approximate dimensions 24 inches by
24 inches by 6 inches.
g. Scale Holder: One each (per four tables or fraction thereof) scale holder.
Constructed of powder coated steel and designed to fit the Euro table, black in
color. Designed to suspend a hanging scale and provided with a swivel (360
degree) top.
h. Bag Holder: One each (per four tables or fraction thereof) angled bag roll holder.
Constructed of powder coated steel and designed to fit the Euro table, black in
color. Designed to hold one roll of bags vertically.
i. Insulated Ice Pan: One each (per four tables or fraction thereof) insulated ice pan.
Constructed of black ABS plastic with polyurethane foam insulation. Ice pan has
built-in drain system with hose attachment for easy draining of water and a cut-off
valve. Four inches deep and sized (length by width) to match tilt top table.
j. Rolling Reservoir: One each (per four tables or fraction thereof) reservoir pan to
be used in conjunction with insulated ice pan. Constructed of black ABS plastic
and mounted on 2- to 3- inch non-marking heavy duty casters. Integrated pop
valve drain system. Approximate dimensions 30 inches wide by 30 inches long by
12 inches high.
k. "U" Shape Front Guard: One each (per four tables or fraction thereof) u-shape
clear front guard (product stop). Constructed of clear heavy duty plastic designed
to be used in conjunction with insulated ice pan to allow massive ice presentation
and to prevent ice spillovers. Sized to match the insulated ice pan.
a. 48 inches long.
b. Adjustable 48 to 61 inches deep.
c. Adjustable 18 to 28 inches high.
A. Salient Characteristics:
a. 48 inches long.
b. 48 inches wide.
c. 32 inches high.
1) 24 inches long.
2) 3/4 inches deep.
3) 12 inches high.
A. Salient Characteristics:
a. 48 inches long.
b. 48 inches wide.
c. 32 inches high.
1) 24 inches long.
2) 3/4 inches deep.
3) 12 inches high.
1. Model OBA-CLS IC O 4-Foot by 4-Foot Oak Orchard Bin w/Liner & Drain Pan.
2. Model CB-OB 24x12 C Composition Chalkboard w/Frame & Holder.
A. Salient Characteristics:
a. 81 inches long.
b. 30 inches deep.
c. 44 inches high.
10. Back panel: Shall extend full length of deck and 24 inches above the deck. Sloped at
both ends with a 31-1/2 inch flat top.
PART 3 - EXECUTION
3.1 INSPECTION
A. General:
1. Check that surfaces to which work will be secured are sound and free of irregularities
interfering with installation.
2. Do not begin installation until satisfactory conditions have been corrected.
3.2 PREPARATION
A. General:
A. General:
A. General:
1. Adjust doors, drawers, hardware fixtures, and other moving and operating parts to
function smoothly and correctly.
2. Restore finishes damaged during installation and construction period so no evidence
remains of correction work. Return items that cannot be refinished in the field to the
shop; make required alterations and refinish entire unit or provide new units.
3. On completion of installation, touch up all marred or abraded finished surfaces.
4. Clean equipment cases, counters, shelves, glass, legs, hardware, fittings and fixtures.
Wipe down surfaces to remove fingerprints and markings and leave in clean condition.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each product specification is current. Provide written notification to the DeCA
Project Manager when this verification has been completed.
B. The guide specification specifies equipment typically used in a commissary facility. The A/E shall
edit the guide specification, deleting equipment not required on a particular project.
C. It may be necessary to specify equipment that is not included in the guide specification. The A/E will
be responsible for developing UFGS format product specifications for insertion into the guide
specification.
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
E. Verify that proper utility connections and mounting heights (water, drain, vent, refrigeration,
electrical, communication, etc.) are shown on Contract Documents for all specified equipment.
F. If wedge configurations are utilized in deli display case line-up, provide three-step custom
millwork stepped displays with plastic laminate and solid surfacing finishes as indicated in Design
Standard Plate 06 40 23-03. Stepped displays are freestanding and not attached to display
cases. Do not locate any utilities within or attached to these wedge configurations.
G. Provide customer service counter with plastic laminate and solid surfacing finishes as indicated in
Design Standard Plate 06 40 23-02. Customer service counter is freestanding and not attached
to display cases. If required, locate utilities (i.e., electrical and data receptacles) within millwork
counters using flexible connectors as permitted by code.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
1. For each item of equipment required, including the manufacturer's standard details and
installation and maintenance instructions.
B. Submittal List:
A. Installer Qualifications: Engage an experienced installer to perform work of this Section who is
an authorized representative of the seafood equipment manufacturer, who has specialized in
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Salient Characteristics:
1) 22 inches wide.
2) 24 inches deep.
3) 27 inches high.
a. In-line water filtration system for ice flaker machines with volume up to 1,500
lbs/day.
b. Equip unit with replaceable water filter and provide an additional replacement filter
cartridge.
c. Plumbing:
1) 7 inches wide.
2) 7 inches deep.
3) 29 inches high.
a. Steel frame designed to support the ice flaker positioned over the portable cart to
allow for continuous flow of flaked ice into the portable cart.
b. Baked enamel (gray).
c. Nominal frame dimensions: 33-1/4 inches wide, 39-3/4 inches long, 42-3/4 inches
high.
a. Ice storage bin designed to receive flaked ice from the top mounted ice flaker
machine.
b. Capacity: 260 lbs.
c. Stainless steel bin exterior, polyethylene bin liner, and chute adapter.
d. Mobile bin with four casters and push/pull bar.
e. Plumbing Connection: 5/8 inch bin drain fitting that can be adapted to plastic or
copper drain line.
f. Nominal bin dimensions: 26-1/2 inches wide, 39-3/4 inches long, 38-1/4 inches
high.
5. Overall height of assembly when ice flaker is mounted onto the frame shall not exceed 81
inches high.
A. Salient Characteristics:
1. Cabinet exterior, including front, one piece sides, louver assembly, and three doors
constructed of heavy gauge stainless steel. Cabinet interior and door liners are
constructed of anodized aluminum. Exterior cabinet top, back and bottom are constructed
of heavy gauge aluminized steel.
2. Top mounted, self-contained, balanced refrigeration system located behind a one piece
louver assembly.
3. Plenum effect blower coil, large, high humidity evaporator coil located outside the food
zone and a top mounted non-electric condensate evaporator.
4. Automatic non-electric condensate evaporator. No plumbing required to dispose of
condensation/defrost water.
5. Automatic preset time activated electric defrost.
6. Digital thermometer and temperature controls. Standard operating temperature: 0 to
minus 5 deg F.
a. 86 inches long.
b. 35 inches deep.
c. 83 inches high on 6-inch legs.
14. Electrical:
a. 4-wire 208-230/115 volts, 60 hertz, single phase. Both voltages are required.
b. Full load amperes: 11.0.
c. Wattage: 1830.
d. Equipped with one 9-foot cord and NEMA L14-20P plug.
a. Refrigerant: R-404A.
b. BTU/HR H.P.: 5220 (1 HP).
B. Accessories:
1. Provide one full door section with chrome plated steel rod type slide assemblies to
support up to thirty-eight 18-inch by 26-inch sheet pans. This door section is the left door
when facing the unit.
2. Provide other two full door sections with 18 gauge stainless steel adjustable angle type
shelf brackets for full height of each door section on minimum 3-inch centers to support
18-inch by 26-inch sheet pans.
3. Provide 12 stainless steel wire shelves with shelf clips.
3.1 INSPECTION
A. Check that surfaces to which work will be secured are sound and free of irregularities interfering
with installation. Do not begin installation until unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. General:
3.3 INSTALLATION
A. General:
A. General:
1. Adjust doors, drawers, hardware fixtures, and other moving and operating parts to
function smoothly and correctly.
2. Replace damaged items with new material.
3. On completion of installation, touch up all marred or abraded finished surfaces.
4. Clean equipment cases, counters, shelves, glass, legs, hardware, fittings and fixtures.
Wipe down surfaces to remove fingerprints and markings and leave in clean condition.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each product specification is current. Provide written notification to the DeCA
Project Manager when this verification has been completed.
B. Vertical balers are typically used in commissary facilities and are located within the staging and
receiving area, usually near a door opening to grade level receiving or trash platform. Quantity,
size, and location of balers will be determined during the design charrette. Locate baler with 24"
clearance from wall behind unit (or greater clearance if recommended by manufacturer). Provide
adequate space around unit for door swing and bale removal.
C. Sizes are as follows:
1. 1R00-A: Baler, Cardboard, Vertical, Small.
2. 1R00-B: Baler, Cardboard, Vertical, Medium.
3. 1R00-C: Baler, Cardboard, Vertical, Large.
1. Wires for 1R00-A are 14'-0" in length by 14 GA. Provide a 10'-0" long, 6" diameter open-
ended PVC pipe mounted on wall directly behind baler at 48" above finish floor.
2. Wires for 1R00-B and 1R00-C are 18'-0" in length by 12 GA. Provide a 14'-0" long, 6"
diameter open-ended PVC pipe mounted on wall directly behind baler at 48" above finish
floor.
3. Secure pipe to wall with PVC pipe hangers spaced 4'-0" on center maximum. Locate pipe
with adequate clearance at each end for insertion of and removal of baling wires.
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
determine suitability, and confirm utility requirements for removal and relocation into the new or
renovated facility. If applicable, list or note on the Contract Specifications/Drawings any
equipment to be salvaged or relocated by the construction contractor.
C. On addition / alteration projects, provide specific guidance on the Contract Documents regarding
disposition of salvaged equipment (i.e., will it become the property of the contractor or turned
over to DRMO). Turn-in of salvaged equipment is the responsibility of the Commissary Store
Director or designated Government representative. When the contractor is required to remove
and/or otherwise dispose of commissary equipment such as display and storage shelving, display
cases, refrigeration equipment and walk-in-boxes, the contractor will be required to sign DD Form
1348-1 Receipt Release Documents prepared by the Commissary Store Director or designated
Government representative. The A/E shall clearly identify any equipment that will become the
property of the contractor for salvage, and clearly identify that all other operational equipment
shall remain the property of DeCA.
D. Verify that adequate space is available (both floor space and ceiling clearance) for all specified
equipment.
END OF SECTION
June 2011 11 82 36 2
SECTION 11 82 36
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data:
B. Warranty:
C. Submittal List:
Reference Submittal Item Quantity Action
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. General Characteristics:
B. Operational Characteristics:
a. Unit shall have interlocks to prevent operation with doors open and to ensure
correct sequence of operation.
b. Moving parts during baling process shall be fully enclosed.
c. Provide with a safety hydraulic relief valve.
d. All electrical circuits, including the control panel, shall be weather proofed to permit
outdoor installation.
e. Provide with a key operated start switch.
1. Model DX-60-8.
A. General Characteristics:
B. Operational Characteristics:
a. Unit shall have interlocks to prevent operation with doors open and to ensure
correct sequence of operation.
b. Moving parts during baling process shall be fully enclosed.
c. Provide with a safety hydraulic relief valve.
d. All electrical circuits, including the control panel, shall be weather proofed to permit
outdoor installation.
e. Provide with a key operated start switch.
1. Model DC-72-LU.
A. General Characteristics:
B. Operational Characteristics:
a. Unit shall have interlocks to prevent operation with doors open and to ensure
correct sequence of operation.
b. Moving parts during baling process shall be fully enclosed.
c. Provide with a safety hydraulic relief valve.
d. All electrical circuits, including the control panel, shall be weather proofed to permit
outdoor installation.
e. Provide with a key operated start switch.
1. Model DX-78-48.
3.1 INSTALLATION
A. General:
1. Items shall be installed where indicated on the Drawings and in absence of dimension,
items shall be installed where directed by Contracting Officer.
2. Installation shall be in full accordance with approved assembly and installation Drawings.
3. Deliver instruction sheets to Contracting Officer and instruct Government's personnel in
the proper use, adjustment, and maintenance of equipment.
A. Adjust equipment for proper operation. After completion of installation, clean and polish all
exposed surfaces. Deliver keys and instruction sheets to the Contracting Officer.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 08 Design Criteria, Commissary Door Schedule and
Commissary Room Finish Schedule in Appendix "A", and related Design Standard Plates.
2. Horizontal louver blinds shall be provided at all windows located in offices and cash handling areas.
Color of blinds shall match or be compatible with window frame.
3. Whenever possible, blinds shall be positioned between window frame jambs, not surface mounted to
the face of the frame or wall.
END OF SECTION
June 2011 12 21 13 1
SECTION 12 21 13
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Requirements:
1. Division 06 Section Rough Carpentry for wood blocking and grounds for mounting
horizontal louver blinds and accessories.
2. Division 08 Section Door Hardware for door hardware.
1.2 SUBMITTALS
B. Samples for Verification: For each type and color of horizontal louver blind indicated.
C. Window Treatment Schedule: For horizontal louver blinds. Use same room designations
indicated on Drawings.
D. Submittal List:
A. Source Limitations: Obtain horizontal louver blinds through one source from a single
manufacturer.
B. Product Standard: Provide horizontal louver blinds complying with WCSC A 100.1.
A. Deliver horizontal louver blinds in factory packages, marked with manufacturer and product
name, and location of installation using same designations indicated on Drawings and in a
window treatment schedule.
A. Environmental Limitations: Do not install horizontal louver blinds until construction and wet and
dirty finish work in spaces, including painting, is complete and dry and ambient temperature and
humidity conditions are maintained at the levels indicated for Project when occupied for its
intended use.
B. Field Measurements: Where horizontal louver blinds are indicated to fit to other construction,
verify dimensions of other construction by field measurements before fabrication and indicate
measurements on Shop Drawings. Allow clearances for operable glazed units' operation
hardware throughout the entire operating range. Notify Contracting Officer of discrepancies.
Coordinate fabrication schedule with construction progress to avoid delaying the Work.
PART 2 - PRODUCTS
B. Slats: Aluminum; alloy and temper recommended by producer for type of use and finish
indicated; with crowned profile and radius corners.
1. Width: 1 inch.
2. Thickness: Manufacturer's standard. Not less than 0.008 inch.
3. Spacing: Manufacturer's standard.
4. Finish: As indicated.
C. Headrail: Formed steel or extruded aluminum; long edges returned or rolled; fully enclosing
operating mechanisms on three sides and end plugs and the following:
a. Lift-Cord Lock: Variable; stops lift cord at user-selected position within blind full
operating range.
b. Operator: Extension of lift cord(s) through lift-cord lock mechanism to form cord
pull.
a. Tilt: Full.
b. Tilt Operation: Manual with clear plastic wand.
c. Tilt: Two-direction, positive stop or lockout limited at an angle of 80 degrees from
horizontal, both directions.
d. Operator: Clear-plastic wand
e. Over-Rotation Protection: Manufacturer's detachable operator or slip clutch to
prevent over rotation of gear.
5. Manual Lift Operator and Tilt Operator Length: Length required to extend to 48 inches
above floor level when blind is fully closed.
6. Manual Lift Operator and Tilt Operator Locations: Manufacturer's standard.
7. Integrated Headrail/Valance: Curved face.
D. Bottom Rail: Formed-steel or extruded-aluminum tube that secures and protects ends of
ladders and lift cords and has plastic- or metal-capped ends.
E. Ladders: Evenly spaced across headrail at spacing that prevents long-term slat sag.
1. Type: Braided Cord. For Blinds with Nominal Slat Width 1 Inch or Less.
G. Mounting Brackets: With spacers and shims required for blind placement and alignment
indicated.
1. Type: Wall, permitting easy removal and replacement without damaging blind or
adjacent surfaces and finishes; with spacers and shims required for blind placement and
alignment indicated.
2. Intermediate Support: Provide intermediate support brackets to produce support spacing
recommended by blind manufacturer for weight and size of blind.
A. Product Safety Standard: Fabricate horizontal louver blinds to comply with WCMA A 100.1
including requirements for corded, flexible, looped devices; lead content of components; and
warning labels.
D. Mounting and Intermediate Brackets: Designed for removal and reinstallation of blind without
damaging blind and adjacent surfaces, for supporting blind components, and for bracket
positions and blind placement indicated.
E. Installation Fasteners: No fewer than two fasteners per bracket, fabricated from metal
noncorrosive to brackets and adjoining construction; type designed for securing to supporting
substrate; and supporting blinds and accessories under conditions of normal use.
F. Color-Coated Finish:
1. Metal: For components exposed to view, apply manufacturer's standard baked finish
complying with manufacturer's written instructions for surface preparation including
pretreatment, application, baking, and minimum dry film thickness.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with
requirements for installation tolerances, operational clearances, and other conditions affecting
performance.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Install horizontal louver blinds level and plumb, aligned and centered on openings, and aligned
with adjacent units according to manufacturer's written instructions.
1. Locate so exterior slat edges are not closer than 2 inches from interior faces of glass and
not closer than 1/2 inch from interior faces of glazing frames through full operating ranges
of blinds.
2. Install mounting and intermediate brackets to prevent deflection of headrails.
3. Install with clearances that prevent interference with adjacent blinds, adjacent
construction, and operating hardware of glazed openings, other window treatments, and
similar building components and furnishings.
B. Jamb Mounted: Install headrail flush with face of opening jamb and head.
A. Adjust horizontal louver blinds to operate smoothly, easily, safely, and free of binding or
malfunction throughout entire operational range.
A. Cleaning: Clean horizontal louver blind surfaces after installation, according to manufacturer's
written instructions.
C. Replacement: Replace damaged horizontal louver blinds that cannot be repaired, in a manner
approved by Contracting Officer, before time of final acceptance.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 03, Division 05, and Division 22 Design Criteria.
2. Equip Customer Entry Vestibule (RM. 1), Carry-Out Return Vestibule (RM. 3), and Administrative Entry
Vestibule (RM. 13) with one of the following:
C. Section 12 48 16 - Entrance Floor Grilles (recessed pit type with floor drains)
3. The type to be used at a particular Commissary will depend on the location of the Installation and local
climatic conditions (such as annual snowfall, annual rainfall, etc.). Whether sand or salt is used for
exterior ice control should also be a consideration in selecting which system is to be used. Installations
utilizing sand for ice control have experienced problems with sanitary lines being blocked by sand.
Which entry mat system to be used should be discussed and selected during the design charrette
process, in coordination with the Installation.
4. Surface floor mat systems are roll-up surface mounted, rubber-backed, carpet-type mats with tapered
vinyl edgings. Width of mat (including edgings) is 6 '-0" minimum. Width and length shall be selected to
fit location and dimensions clearly indicated on Drawings.
5. Recessed floor mats and frames are roll-up vinyl rail hinged mats set in recessed aluminum frames that
are flush with the adjacent finish floor system. Width and length shall be as selected to fit location and
dimensions clearly indicated on Drawings.
6. Foot grilles are recessed stainless steel treads with support frame system set in a concrete pit with
sloped floor and floor drain connected to the building sanitary system. Coordinate with plumbing to
include a floor drain trap primer system and vent system.
7. In arctic climates, it may be appropriate to provide recessed foot grilles with snow pits. This should be
coordinated with DeCA and the Installation.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
B. Samples for Verification: Floor Mat: 12 inch square, sections of floor mat including perimeter
floor molding.
C. Submittal List:
A. Source Limitations: Obtain floor mats through one source from a single manufacturer.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design Product:
B. Carpet-Type Mats:
1. Manufactured from 100 percent UV resistant polypropylene fibers with a face weight of
50 oz./sq. yd. and total weight of 85 oz./sq. yd. with all-weather skid-resistant rubber
backing.
2. Heavy-Duty Vinyl Edging: 1-1/2 inch tapered vinyl edging for surface mounted
application, black color.
3. Mat Size: As indicated on Drawings.
4. Colors, Textures, and Patterns: Custom, as indicated on Drawings.
2.3 FABRICATION
A. Floor Mats: Shop fabricate units to greatest extent possible in sizes indicated. Unless
otherwise indicated, provide single unit for each mat installation; do not exceed manufacturer's
recommended maximum sizes for units that are removed for maintenance and cleaning. Where
joints in mats are necessary, space symmetrically and away from normal traffic lanes.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and floor conditions for compliance with requirements for location, sizes,
and other conditions affecting installation of floor mats.
1. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
END OF SECTION
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 03 Section Cast-in-Place Concrete for slab depression for recessed mats and
frames.
2. Division 12 Section Entrance Floor Grilles for rigid foot grilles and frames.
1.2 SUBMITTALS
D. Submittal List:
E. Maintenance Data: For floor mats and frames to include in maintenance manuals.
A. Source Limitations:
1. Obtain floor mats and frames through one source from a single manufacturer.
B. Accessibility Requirements:
1.5 COORDINATION
A. Coordinate size and location of recesses in concrete with installation of finish floors to receive
floor mats and frames.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design Product:
B. Roll-up Vinyl Rail Hinged Mats: Vinyl-acrylic tread rails 2 inch wide by 3/8 inch thick with slotted
or perforated vinyl hinges.
1. Tread Inserts: Ribbed-design-surface, resilient vinyl. 1/4 inch high, 28 oz./sq. yd. weight,
level-cut, nylon-pile, fusion-bonded carpet.
2. Color, Texture, and Patterns of Inserts: As indicated.
3. Rail Color: As indicated.
4. Mat Size: As indicated on Drawings.
1. Extruded Aluminum: ASTM B 221, Alloy 6061-T6 or Alloy 6063-T5, T6, or T52.
2. Color: Mill finish.
A. Provide concrete grout and fill equivalent in strength to cast-in-place concrete slabs for
recessed mats and frames. Use aggregate no larger than one-third fill thickness.
2.4 FABRICATION
A. Floor Mats: Shop fabricate units to greatest extent possible in sizes indicated. Unless
otherwise indicated, provide single unit for each mat installation; do not exceed manufacturer's
recommended maximum sizes for units that are removed for maintenance and cleaning. Where
joints in mats are necessary, space symmetrically and away from normal traffic lanes. Miter
corner joints in framing elements with hairline joints or provide prefabricated corner units without
joints.
B. Recessed Frames: As indicated, for permanent recessed installation, complete with corner pins
or reinforcement and anchorage devices.
1. Fabricate edge-frame members in single lengths or, where frame dimensions exceed
maximum available lengths, provide minimum number of pieces possible, with hairline
joints equally spaced and pieces spliced together by straight connecting pins.
C. Coat surfaces of aluminum frames that will contact cementitious material with manufacturer's
standard protective coating.
A. General: Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products"
for recommendations for applying and designating finishes.
1. Finish designations prefixed by AA comply with the system established by the Aluminum
Association for designating aluminum finishes.
B. Class II, Clear Anodic Finish: AA-M12C22A31 (Mechanical Finish: Nonspecular as fabricated;
Chemical Finish: etched, medium matte; Anodic Coating: Architectural Class II, clear coating
0.010 mm or thicker) complying with AAMA 611.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, floor conditions, and floor recesses for compliance with requirements for
location, sizes, minimum recess depth, and other conditions affecting installation of floor mats
and frames.
3.2 INSTALLATION
A. General: Install recessed mat frames to comply with manufacturer's written instructions. Set
mat tops at height recommended by manufacturer for most effective cleaning action; coordinate
top of mat surfaces with bottom of doors that swing across mats to provide clearance between
door and mat.
1. Install necessary shims, spacers, and anchorages for proper location and secure
attachment of frames.
2. Install grout and fill around frames and, if required to set mat tops at proper elevations, in
recesses under mats. Finish grout and fill smooth and level.
3.3 PROTECTION
A. After completing frame installation and concrete work, provide temporary filler of plywood or
fiberboard in recesses and cover frames with plywood protective flooring. Maintain protection
until construction traffic has ended and Project is near final acceptance. Defer installation of
floor mats until Project is near final acceptance.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
1. Division 03 Section Cast-in-Place Concrete for slab depression for recessed foot
grilles and frames.
A. Structural Performance: Provide foot grilles and frames capable of withstanding the following
loads and stresses:
1.3 SUBMITTALS
D. Submittal List:
A. Source Limitations: Obtain foot grilles and frames through one source from a single
manufacturer.
B. Accessibility Requirements: Provide installed foot grilles that comply with Section 302 in the
ABA Accessibility Standard for Department of Defense Facilities adopted October 31, 2008.
1.6 COORDINATION
A. Coordinate size and location of recesses in concrete to receive foot grilles and frames.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
2.2 MATERIALS
A. Extruded Aluminum: ASTM B 221, Alloy 6061-T6 or Alloy 6063-T5, T6, or T52 as standard with
manufacturer. Coat surface of frame in contact with cementitious materials with manufacturer's
standard protective coating.
B. Stainless-Steel Sheet, Strip, Plate, and Flat Bars: ASTM A 666, Type 304.
C. Stainless-Steel Angles: ASTM A 276 or ASTM A 479/A 479M, corrosion resistant, Type 304.
A. Basis-of-Design Product:
1. Surface Treads: 0.086 by 0.177 inch wire with 0.118 inch wide openings between wires.
2. Support Rods: Spaced 1 inch o.c., welded to each wire.
3. Mat Grating: 5/8 inch deep.
4. Pit Grating: 1-1/8 inches deep.
5. Stainless Steel Finish: No. 4 finish.
6. Grille Size: As indicated.
2.4 FRAMES
A. Provide manufacturer's standard frames of size and style for grille type, for permanent recessed
installation in subfloor, complete with installation anchorages and accessories. Unless
otherwise indicated, fabricate frame of same material and finish as grilles.
A. Drainage Pit Applications: Provide manufacturer's special deep-pit frame and aluminum
support extrusion system with intermediate support beams, sized and spaced as recommended
by manufacturer for indicated spans and equipped with vinyl support cushions.
A. Provide manufacturer's standard, 0.050 inch thick, stainless steel sheet drain pan with NPS 2
drain outlet for each floor grille unit. Coat bottom of pan with protective coating recommended
by manufacturer.
2.7 FABRICATION
A. Shop fabricate foot grilles to greatest extent possible in sizes as indicated. Unless otherwise
indicated, provide each grille as a single unit; do not exceed manufacturer's recommended
maximum sizes for units that are removed for maintenance and cleaning. Where joints in grilles
are necessary, space symmetrically and away from normal traffic lanes.
B. Fabricate frame members in single lengths or, where frame dimensions exceed maximum
available lengths, provide minimum number of pieces possible, with hairline joints equally
spaced and pieces spliced together by straight connecting pins.
A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
A. Finish designations prefixed by AA comply with the system established by the Aluminum
Association for designating aluminum finishes.
B. Mill Finish: AA-M10 (Mechanical Finish: as fabricated); grind and buff as required to remove
scratches, welding, or abrasions produced in fabrication process.
1. When polishing is completed rinse surfaces. Remove embedded foreign matter and
leave surfaces chemically clean.
PART 3 - EXECUTION
3.1 EXAMINATION
A. General: Examine substrates and floor conditions for compliance with requirements for
location, size, minimum recess depth, and other conditions affecting installation of foot grilles
and frames.
B. Examine roughing-in for drainage piping systems to verify actual locations of piping connections
before foot grille and frame and drain pan installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Install recessed foot grilles and frames and drain pans to comply with manufacturer's written
instructions at locations indicated and with top of foot grilles and frames in relationship to one
another and to adjoining finished flooring as recommended by manufacturer. Set foot-grille tops
at height for most effective cleaning action. Coordinate top of foot-grille surfaces with doors that
swing across grilles to provide clearance under door.
3.3 PROTECTION
A. After completing frame installations, provide temporary filler of plywood or fiberboard in foot-
grille recesses and cover frames with plywood protective flooring. Maintain protection until
construction traffic has ended and Project is near final acceptance. Defer installation of foot
grilles until Project is near final acceptance.
END OF SECTION
DESIGN CRITERIA
1. GENERAL
A. While Guide Specifications are continually being updated to incorporate the specified
manufacturers product improvements, it is the A/Es responsibility to verify with the basis-of-design
manufacturer that each specified CED is current. Provide written notification to the DeCA Project
Manager when this verification has been completed.
B. The guide specification specifies equipment typically used in a commissary facility. The A/E shall
edit the guide specification, deleting equipment not required on a particular project.
C. It may be necessary to specify equipment that is not included in the guide specification. The A/E
will be responsible for developing UFGS format product specifications for insertion into the
Project Specification.
D. CF/CI Furniture typically provided in commissary facilities is limited to modular workstations that are
located in various administrative office areas. Locations and sizes will be determined during the
design charrette.
E. Modular Work Station sizes are as follows:
1. 1A03-N - Workstation, General Office, Low Profile
2. 1A03-R - Workstation, General Office, Stand Alone
F. Workstations shall be constructed as individual stand-alone units, each with all components
necessary to function without attachment to adjacent workstations. On new construction
projects, feed electrical and communication data from recessed floor boxes located beneath each
modular workstation. Locate floor boxes in corner of modular workstation beneath corner work
surface. On addition / alteration projects with existing floors, feed electrical and communication
data from overhead power pole drops at each modular workstation. Feed all utilities into raceway
bases of units with manufacturer's standard receptacles as specified.
2. DESIGN CHARRETTE PHASE RESPONSIBILITIES
A. During the design charrette process, the A/E (working with DeCA personnel) will develop a
definitive floor plan of the commissary indicating operational equipment (drawn to scale with
required end panels and clearances, etc.); and will develop an Equipment List for same indicating
quantity, size, and description. Upon completion of this list, DeCA will review the list and
incorporate additional operational equipment necessary for a complete and functional
commissary. They will also identify responsibility for equipment as follows:
1. Government-Furnished/Government-Installed (GF/GI).
2. Government-Furnished/Contractor-Installed (GF/CI).
3. Contractor-Furnished/Contractor-Installed (CF/CI).
3. CONTRACT DOCUMENT PHASE RESPONSIBILITIES.
A. The Contract Documents shall include the equipment list developed during the design charrette
process, clearly identifying responsibility for all equipment. To facilitate and expedite technical
review by DeCA, the Contract Documents shall use DeCA equipment item numbers to key both
the contractor-furnished and government-furnished equipment to the Drawings.
B. If applicable, DeCA will provide the A/E with a list of existing government-owned equipment to be
re-used in the new or renovated facility. The A/E shall evaluate the identified equipment to
determine suitability, and confirm utility requirements for removal and relocation into the new or
renovated facility. If applicable, list or note on the Contract Specifications/Drawings any
equipment to be salvaged or relocated by the construction contractor.
C. On addition / alteration projects, provide specific guidance on the Contract Documents regarding
disposition of salvaged equipment (i.e., will it become the property of the contractor or turned
June 2011 12 59 00 1
DeCA DESIGN CRITERIA HANDBOOK
12 59 00 SYSTEMS FURNITURE
over to DRMO). Turn-in of salvaged equipment is the responsibility of the Commissary Store
Director or designated Government representative. When the contractor is required to remove
and/or otherwise dispose of commissary equipment such as display and storage shelving, display
cases, refrigeration equipment and walk-in-boxes, the contractor will be required to sign DD Form
1348-1 "Receipt Release Documents" prepared by the Commissary Store Director or designated
Government representative. The A/E shall clearly identify any equipment that will become the
property of the contractor for salvage, and clearly identify that all other operational equipment
shall remain the property of DeCA.
D. Verify that adequate space is available (both floor space and ceiling clearance) for all specified
equipment.
END OF SECTION
June 2011 12 59 00 2
SECTION 12 59 00
SYSTEMS FURNITURE
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data: For each furniture item specified, including details of construction relative to
materials, dimensions, and finishes.
B. Submittal List:
B. Store materials in original protective packaging to prevent soiling, physical damage, or wetting.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design Product:
1. Hon Company, Simplicity II Series. Provide modular work stations, nominal 74- by 99-
inches, as indicated on drawings. Provide panels with raceway bases to allow for routing
of computer, telephone, and electrical systems. Provide wire management ports on all
work surfaces with multi-outlet, pop-up receptacles. Provide one adjustable pull-out
computer keyboard drawer at each corner work surface. Each work station shall
comprise the following components.
a. Three fabric covered raceway acoustical wall panels, 30 inches high by 37 inches
wide, with connectors as necessary. Hon SR3037.
b. One fabric covered raceway acoustical wall panel, 30 inches high by 62 inches
wide, with connectors as necessary. Hon SR3062.
c. Two fabric covered raceway acoustical end wall panels, 30 inches high by 25-1/2
inches wide, with connectors as necessary. Hon SR3025.
d. One standard plastic-laminate work surface, 24 inches wide by 62 inches long,
with brackets as necessary. Hon WS2462.
e. One standard plastic-laminate work surface, 24 inches wide by 37 inches long,
with brackets as necessary. Hon WS2437.
f. One corner plastic-laminate work surface, 37 inches wide by 24 inches deep, with
brackets as necessary. Hon WS3724.
g. One mobile prefinished painted ped box/box/file, 26-7/8 inches high by 22-7/8
inches deep by 15 inches wide. Hon 23723.
h. One plastic-laminate wood center drawer, 22 inches wide by 15-3/8 inches deep,
installed under work surface WS2437. Hon 1522.
i. Two cantilever bracket SC/FS units. Hon CB1.
j. One articulating/swiveling keyboard platform. Hon 850500.
k. One data and electrical receptacle, 6 pin RJ11, of color selected. Hon H61011E6.
l. One pull-up receptacle, Hon H870300.
m. One electrical pass-thru cable 36W 3-1 & 2-2 systems, Hon H871136.
n. Two Electrical power harness 36W, 3-1 and 2-2 systems. Hon H871236.
o. One Electrical power harness 60W, 3-1 and 2-2 systems. Hon H871260.
p. One duplex receptacle circuit 1, 3-1 and 2-2 systems, of color selected. Hon
H871501.
q. One duplex receptacle circuit 2, 3-1 and 2-2 systems, of color selected. Hon
H871502.
r. One duplex receptacle circuit 4, 3-1 and 2-2 systems, of color selected. Hon
H871504.
s. One power in-feed cable, base, 3-1 and 2-2 systems. Hon H879072.
t. Raceway 90 degree corner panel connectors. Hon PB090R. (As required).
u. Raceway 180 degree straight panel connectors. Hon PB180R (As required).
v. Raceway end-of-run panel kits. Hon PB1R (As required).
w. Raceway tee (3-way) panel connectors. Hon PB3R (As required).
x. Two work surface support legs 20/24 inches deep by 28 inches high of color
selected. Hon SP2824.
y. One swivel/tilt task chair with height and back adjustment and adjustable arms, five
star base, duel wheel casters, and fabric cover. Hon 6603 (chair) and Hon 6693
(chair arms).
A. Basis-of-Design Product:
1. Hon Company, Simplicity II Series. Provide modular work stations, nominal 74- by 99-
inches, as indicated on drawings. Provide panels with raceway bases to allow for routing
of computer, telephone, and electrical systems. Provide wire management ports on all
work surfaces with multi-outlet, pop-up receptacles. Provide one adjustable pull-out
computer keyboard drawer at each corner work surface. Provide task lighting under each
overhead storage unit for the full length of the unit. Each work station shall comprise the
following components (adjacent work stations may share acoustical wall panels).
a. Three fabric covered raceway acoustical wall panels, 65 inches high by 37 inches
wide, with connectors as necessary. Hon SR6537.
b. One fabric covered raceway acoustical wall panel, 65 inches high by 62 inches
wide, with connectors as necessary. Hon SR6562.
c. Two fabric covered raceway acoustical end wall panels, 65 inches high by 25-1/2
inches wide, with connectors as necessary. Hon SR6525.
d. One 61-inch lockable prefinished painted overhead storage unit, with connectors
as necessary. Hon SC62L.
e. One 36-inch lockable prefinished painted overhead storage unit, with connectors
as necessary. Hon SC37L.
f. One connector block SC/FS units. Hon SD3137C.
g. One 36-inch prefinished painted full height open bookshelf unit, with connectors as
necessary. Hon FS37.
h. One standard plastic-laminate work surface, 24 inches wide by 62 inches long,
with brackets as necessary. Hon WS2462.
i. One standard plastic-laminate work surface, 24 inches wide by 37 inches long,
with brackets as necessary. Hon WS2437.
j. One corner plastic-laminate work surface, 37 inches wide by 24 inches deep, with
brackets as necessary. Hon WS3724.
k. Two cantilever bracket SC/FS units. Hon CB1.
l. One mobile prefinished painted ped box/box/file, 26-7/8 inches high by 22-7/8
inches deep by 15 inches wide. Hon 23723.
m. One plastic-laminate wood center drawer 22 inches wide by 15-3/8 inches deep
(installed under work surface WS2437). Hon 1522.
n. One articulating/swiveling keyboard platform. Hon 850500.
o. One data and electrical receptacle, 6 pin RJ11 of color selected. Hon H61011E6.
p. One pull-up receptacle, Hon H870300.
q. One electrical pass-thru cable 36W 3-1 & 2-2 systems, Hon H871136.
r. Three task lights 30W, Hon H870930.
s. Two Electrical power harness 36W, 3-1 and 2-2 systems. Hon H871236.
t. One Electrical power harness 60W, 3-1 and 2-2 systems. Hon H871260.
u. One duplex receptacle circuit 1, 3-1 and 2-2 systems, of color selected. Hon
H871501.
v. One duplex receptacle circuit 2, 3-1 and 2-2 systems, of color selected. Hon
H871502.
w. One duplex receptacle circuit 3, 3-1 system only, of color selected. Hon H871503.
x. One duplex receptacle circuit 4, 3-1 and 2-2 systems, of color selected. Hon
H871504.
y. One power in-feed cable, base, 3-1 and 2-2 systems. Hon H879072.
z. Raceway 90 degree corner panel connectors. Hon PB090R (As required).
aa. Raceway 180 degree straight panel connectors. Hon PB180R (As required).
bb. Raceway end-of-run panel kits. Hon PB1R (As required).
PART 3 - EXECUTION
3.1 INSTALLATION
B. Install furniture after other finishing operations, including painting, have been completed.
E. Clean and polish exposed surfaces, using materials and methods recommended by the
manufacturer.
3.2 PROTECTION
A. Protect furniture against damage during remainder of construction period, complying with
manufacturer's directions.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See related Division 32 Design Criteria for additional Site Work.
2. Provide exterior site furnishings at front of commissary, to include benches, trash receptacles, and
bicycle rack. Trash receptacle shall have built-in ash receptacle on top of unit. Clearly indicate on
Contract Documents that site furnishings shall be permanently secured in-place. All site furnishings
shall have matching design style. Select bench lengths and bicycle rack size as appropriate for
building design. Locate bicycle rack at front of commissary, but away from busy pedestrian traffic
areas.
3. The guide specification is based on powder coated steel site furnishings finished in a black color.
Coordinate site furnishing materials and colors with building design and local Installation
requirements. Consider the use of recycled materials for site furnishings if the local Installation has
no specific requirements. If alternate site furnishings are selected, select only those types requiring
no maintenance other than occasional washing.
END OF SECTION
June 2011 12 93 00 1
SECTION 12 93 00
SITE FURNISHINGS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Benches.
2. Bicycle racks.
3. Trash receptacles.
1.2 SUBMITTALS
A. Product Data: For each type of product indicated. Include construction details, material
descriptions, dimensions of individual components and profiles, finishes, field-assembly
requirements, and installation details.
C. Submittal List:
PART 2 - PRODUCTS
2.1 MANUFACTURERS
2.2 MATERIALS
2.3 BENCHES
1. Frame, Armrests and Legs: 0.120 inch thick by 1-1/2 inch square mild steel seamless
tubing.
2. Seat and Backrest Slats: 0.085 inch thick by 3/4 inch by 1-1/2-inch mild steel seamless
tubing.
3. Arms: Two, one at each end of bench.
4. Arm Height: Standard with product.
5. Seat Height: 16 inches.
6. Overall Height: 35 inches.
7. Overall Width: 23 inches.
8. Overall Length: 74 inches.
9. Seat Surface Shape: Standard with product.
10. Installation Method: Anchor to floor surface is facilitated through 5/8-inch diameter holes
in pedestal mount base of each bench leg.
11. Steel Finish: UV resistant exterior grade polyester powder coating applied to a minimum
thickness of 6 mils. Liquid, epoxy, and lead-containing powder coatings are not
acceptable. Color: Black.
1. Frame: One-piece 2-inch inside diameter Schedule 40 pipe (outside diameter 2-3/8
inches) with four hex socket screws at each end to secure frame to pedestal mounting
base.
2. Pedestal Mounting Base: 1/4-inch thick mild steel plate permanently welded to 1-1/2-inch
inside diameter Schedule 40 pipe sleeve with decorative metal base cover to conceal
pedestal mounting base and expansion anchors.
3. Style: Serpentine or ribbon.
1. Receptacle Shape, Form, and Function: Square; with ash/dome top and opening for
depositing trash in top.
2. Frame: 0.120 inch thick by 1-1/2-inch square mild steel tubing.
3. Side Slats: 0.085 inch thick by 3/4 inch by 1-1/2-inch mild steel seamless tubing.
4. Ash/Dome Tops: Fabricated from 0.125 inch thick steel plate with 13-inch diameter
center hole, 18-inch diameter 14 gage steel dome with two 6-inch radius openings, and a
6-inch top ash tray. Provide sand for ash tray.
5. Provide litter container with a hinged side door and keyed-cylinder lock.
6. Pedestal (fixed leveling) mounting with separate mounting hardware to enable leveling on
uneven surfaces. Anchor to floor surface is facilitated through 5/8-inch diameter holes in
pedestal mount base plate.
7. Style: As indicated by manufacturers designation.
8. Overall Height: 44-1/4 inches.
9. Overall Size: 23 inches square.
10. Inner Container: Plastic liner designed to be removable and reusable.
11. Capacity: 36 gal.
12. Installation Method: Anchoring to floor is facilitated through four 5/8-inch diameter holes
in pedestal mounting base.
13. Steel Finish: UV resistant exterior grade polyester powder coating applied to a minimum
thickness of 6 mils. Liquid, epoxy, and lead-containing powder coatings are not
acceptable. Color: Black.
2.6 FABRICATION
A. Metal Components: Form to required shapes and sizes with true, consistent curves, lines, and
angles. Separate metals from dissimilar materials to prevent electrolytic action.
B. Welded Connections: Weld connections continuously. Weld solid members with full-length,
full-penetration welds and hollow members with full-circumference welds. At exposed
connections, finish surfaces smooth and blended so no roughness or unevenness shows after
finishing and welded surface matches contours of adjoining surfaces.
C. Exposed Surfaces: Polished, sanded, or otherwise finished; all surfaces smooth, free of burrs,
barbs, splinters, and sharpness; all edges and ends rolled, rounded, or capped.
D. Factory Assembly: Assemble components in the factory to greatest extent possible to minimize
field assembly. Clearly mark units for assembly in the field.
A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for
recommendations for applying and designating finishes.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with requirements for
correct and level finished grade, mounting surfaces, installation tolerances, and other conditions
affecting performance.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
A. Comply with manufacturer's written installation instructions unless more stringent requirements
are indicated. Complete field assembly of site furnishings where required.
B. Unless otherwise indicated, install site furnishings after landscaping and paving have been
completed.
C. Install site furnishings level, plumb, true, and securely anchored at locations indicated on
Drawings.
D. Anchor site furnishings to floor surfaces with corrosion resistant zinc alloy expansion anchors
(bolt size 1/2-inch 16, 2-3/16-inch anchor length) and washer.
3.3 CLEANING
A. After completing site furnishing installation, inspect components. Remove spots, dirt, and
debris. Repair damaged finishes to match original finish or replace component.
END OF SECTION
***********************************************************
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 DEFINITIONS
1.3 DESCRIPTION
1. A table of all addresses, setpoints and similar information and the implications when
changing them.
2. Schedules.
3. Instructions for operation of each piece of equipment for emergencies.
4. Startup and shutdown.
5. Recommendations for recommissioning frequency by equipment type.
C. Warranty Period:
A. The responsibilities of the Fire Suppression Contractor, during construction and acceptance
phases in addition to those listed in Paragraph A, above, are:
1. Provide submittals as required by A/E and those listed on the pre-functional test sheets.
2. During the startup and initial checkout process, execute the fire suppression-related
portions of the prefunctional checklists for all commissioned equipment.
3. Perform and clearly document all completed startup and system operational checkout
procedures, providing a copy to the CA.
PART 3 - EXECUTION
3.1 STARTUP
A. Contractors shall follow the start-up and initial checkout procedures listed in the Responsibilities
list in this Section and in Division 01 Section General Commissioning Requirements. Division
13 has start-up responsibility and is required to complete systems and sub-systems so they are
fully functional, meeting the design objectives of the Contract Documents. The commissioning
procedures and functional testing do not relieve or lessen this responsibility or shift that
responsibility partially to the Commissioning Agent, Technical Inspector, or Government.
B. Functional testing is intended to begin upon completion of a system. Functional testing may
proceed prior to the completion of systems, or sub-systems at the discretion of the PM and GC.
Beginning system testing before full completion, does not relieve the Contractor from fully
completing the system, including all prefunctional checklists as soon as possible.
A. The following O&M manual requirements do not replace O&M manual documentation
requirements elsewhere in these specifications.
B. Division 13 shall compile and prepare documentation for all commissioned systems covered in
Division 13 and deliver this documentation to the GC for inclusion in the O&M manuals prior to
the training of Government personnel.
A. The GC shall be responsible for training coordination and scheduling to ensure that training is
completed.
B. The QC shall be responsible for reviewing the content and adequacy of the training of
Government personnel for commissioned equipment or systems. TI will verify compliance.
1. Provide the TI with a training plan four weeks before the planned training.
8. Hands-on training shall include start-up, operation in all modes possible, including
manual, shut-down and any emergency procedures and maintenance of all pieces of
equipment.
9. Fully explain and demonstrate the operation, function and overrides of any local
packaged controls, not controlled by the central control system.
10. Training shall occur after functional testing is complete, unless approved otherwise by the
Project Manager.
11. Minimum Duration of Training. Subcontractor shall provide 8 hours of training.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: See Division 03 Section Insulated Freezer Floors, Division 23 Section Product
Refrigeration Systems, and Division 23 Section Refrigeration Monitoring and Control Systems
(RMCS).
2. Summary: Provide cold storage rooms per Concept Floor Plan: Shop fabricated, site assembled,
walk-in room type, complete with doors and frames. Erect freezers over insulated cast-in-place
concrete floors and provide heated stainless steel threshold across door openings.
3. Doors for cold storage rooms are included in this section. Provide sliding and/or swinging cold
storage room doors as well as 1G11 Dairy Reach-in doors. Provide cart corrals and milk and egg
carts aligned with the 1G11 reach in doors in Dairy cold storage rooms. See Division 08 Section
Traffic Doors for double action and flexible vertical strip doors used in cold storage rooms.
4. Windows for cold storage rooms are included in this Specification Section.
5. General Description:
A. Prefabricated Insulated Panels: Interior and exterior aluminum panels uniformly formed with
metal dies, insulation, and panel fasteners. Maximum length: 12"-0". Maximum width: 48".
Minimum thickness: Low temperature panels shall be 5" thickness with minimum R factor of 36.
Medium temperature panels shall be 4" thickness with minimum R factor of 28. Panel joints:
Interlocking design. Wood frame panels not acceptable. Provide panel fasteners to secure
panels to each other. Provide vapor seal at panel joints when joints are assembled. Form seal
by compressing closed cell gaskets or silicon sealant at the joint. Panel gaskets: Synthetic
rubber or other manufacturer approved material. Panel skins: Minimum 0.032" thick stucco
embossed aluminum. Provide factory applied USDA accepted white baked or acrylic enamel
finish on exposed surfaces. Panels shall be UL approved, or shall be provided with an
independent testing laboratory's test certificate certifying fire retardant properties of the insulation.
Panel skins shall adhere to the insulation.
B. Insulation:
1. Insulation shall be foamed-in-place polyurethane, 2 pcf minimum density, bonded to inner
and outer metal panels.
2
2. Thermal conductivity (K) shall not exceed 0.14 (BTU) (IN) / (HR.) (FT ) (DEGREE F).
3. Insulation shall be Factory Mutual System classified Class I (per ASTM E-84) having a flame
spread of no more than 25, fuel contributed of 0, and smoke developed rating not greater
than 400 when tested in a 4" cross section.
C. Walls: Cold storage room walls shall be constructed using 10'-0" high panels. Cover exposed
surfaces of wall panels in high traffic areas with fiberglass reinforced panels (FRP) as indicated in
Room Finish Schedule.
D. Ceilings: Prefabricated insulated panels spanning width of cold storage room. Underside of
ceiling panels shall have sufficient strength to support conduit and light fixtures affixed directly to
the skin.
E. Ceiling Panel Suspension System: Provide suspension system for support of ceiling panels from
roof structural members. Do not use ceiling support columns within the cold storage rooms.
Suspension system shall consist of all members, including fasteners and attachments, required
to support ceiling panels. Provide manufacturer's standard hangers conforming to panel joint
configuration. Suspension system shall be of sufficient strength to support ceiling panels,
workmen during construction, light fixtures, and equipment supported from panels.
F. Penetrations: Provide PVC conduit sleeves and resilient gaskets for all penetrations. Seal
penetrations vapor tight with silicone sealant. Seal electrical conduits internally and externally to
prevent moisture migration through electrical conduit.
June 2011 13 21 26 1
DeCA DESIGN CRITERIA HANDBOOK
13 21 26 COLD STORAGE ROOMS
G. Temperature Monitoring: Monitor temperatures within each cold storage room with the
Refrigeration Monitoring and Control System (RMCS). Provide temperature probes to measure
temperature of return air to unit coolers and general room temperature. Do not mount
temperature probes in unit cooler discharge air or near doors.
H. Thermometers: At each cold storage room, provide a 4" flanged dial thermometer with a remote
reading capillary tube. Range of thermometer shall be within operating temperature of the cold
storage room. Locate thermometer adjacent to entrance door with capillary tube located remote
from door opening.
I. Pressure Relief Ports: Provide a pressure relief port for cold storage rooms operating at
temperatures below 20 deg F. Design port so that air can move into and out of refrigerated
space. The relief port shall be electrically heated.
J. Floors:
1. Medium temperature cold storage rooms shall be constructed directly on top of concrete floor
slabs as required by Section 03 30 00 Cast-In-Place Concrete. Cold storage rooms shall
have concrete floors sloped to drains.
2. Low temperature cold storage rooms 200 SF in size, and larger, shall have insulating
concrete freezer floors with positive underfloor ventilation for prevention of frost heave.
Construct insulating concrete freezer floor systems consisting of:
a. 36" deep drainage fill layer containing PVC ventilation piping.
b. 10 mil vapor retarder directly on top of drainage fill.
c. Concrete sub-slab.
d. Three 2" layers of polystyrene insulation.
e. Perimeter wood thermal break (preservative treated or redwood) around freezer slab
recess.
f. 10 mil vapor retarder set directly on top of insulation and wrapping-up and over
exposed face of perimeter wood thermal break (note that purpose of this is to
minimize possibility of excess concrete mix water from seeping down between joints
in insulation).
g. Concrete top slab.
3. On new construction projects, low temperature cold storage rooms (less than 200 SF in size)
shall be constructed similarly, except that an underfloor ventilation system is not required.
4. On alteration projects with existing concrete floor slabs, low temperature cold storage rooms
(less than 200 SF in size) shall be constructed using 4" thick prefabricated insulated
aluminum floor panels with 1/4" thick aluminum diamond tread plate wearing surface.
Provide removable 1/4" thick aluminum diamond tread plate exterior ramp.
K. Curbs:
1. Provide concrete curbs (secured to concrete floor slab with steel dowels) for protection of
prefabricated wall panels. Construct curbs with sloped tops for drainage, and isolated from
face of wall panels with pre-molded expansion joint filler. Seal joint between back of curb
and face of wall panel, water tight.
2. At cold storage rooms with resinous floor finish, cover exposed surfaces of curb with resinous
material to match floor. (Note that curb is installed after wall panels are complete, using pre-
molded joint filler as form against wall panel).
3. Provide heater cable within concrete curb on outside of frozen food storage. Refer to Division
13 Design Criteria and Design Standard Plates 13 21 26-04 and 13 21 26-08 for additional
information.
June 2011 13 21 26 2
DeCA DESIGN CRITERIA HANDBOOK
13 21 26 COLD STORAGE ROOMS
END OF SECTION
June 2011 13 21 26 3
SECTION 13 21 26
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
a. Cooler rooms.
b. Freezer rooms.
c. Insulated floor panels.
d. Ceiling panel supports.
e. Sliding cold storage room doors.
f. Swinging cold storage room doors.
g. Windows.
h. 1G11 Remote, Dairy, Reach-In Doors, Milk/Eggs/Juice.
B. Related Sections:
1. Division 03 Section Insulated Freezer Floors for cast-in-place insulating concrete floors.
2. Division 08 Section Traffic Doors for flexible vertical strip barrier doors.
3. Division 08 Section Traffic Doors for double action, self-closing, lightweight, impact
resistant traffic doors.
4. Division 23 Section Product Refrigeration Systems for refrigeration system.
5. Division 23 Section Refrigeration Monitoring and Control System (RMCS) for monitoring
and control system.
6. Division 26 for lighting, electrical wiring, and connections.
A. Structural Performance:
1. Provide cold storage room ceilings capable of withstanding the effects of gravity loads
and the following loads and stresses within limits and under conditions indicated:
a. Live Load: Uniform load of 10 psf or a concentrated load of 300 lbf on an area of
144 sq. in., whichever produces the greater stress. Concentrated and uniform
loads need not be assumed to act concurrently.
b. Dead Load: 4 psf or actual weight of panels, fixtures, and equipment supported,
whichever is greater.
c. Deflection: L/180.
1. Design, engineer, and provide cold storage rooms capable of withstanding the effects of
earthquake motions.
2. Refer to Division 01 Section Summary of Work for seismic-load design performance
criteria.
1.3 SUBMITTALS
A. Product Data:
1. Submit complete catalog data. Submit catalog cuts of each type of unit, as well as cuts
of hardware and accessories proposed for use.
B. Shop Drawings:
1. Provide overall layout drawing indicating location and exact dimensions of cold storage
rooms.
2. Show construction and fabrication details of each item.
3. Provide details for structural supports to be used.
a. For installed products indicated to comply with design loads, include structural
analysis data signed and sealed by the qualified professional engineer responsible
for their preparation.
C. Installation Drawings:
1. Submit complete drawings showing details of anchorage and connection, location and
method of attachment of installed equipment, method of assembling sections and
relationship to adjoining work.
2. Show complete layout of panels, connection details, setting diagrams. Number each
panel and show panel numbers on installation drawings.
D. Installation Instructions:
G. Warranties:
H. Submittal List:
A. Deliver store and handle material to prevent damage and marring of finish. Protect finished
surfaces from damage. Store units on pallets or other approved devices. Store materials inside
building, under protective covering, and protect from weather, moisture, open flames and
sparks.
A. Provide written warranty covering materials and workmanship of all work of this Section for a
period of 2 years and repair or replace all material which becomes defective during warrantee
period. The Government shall have continued use of defective equipment until replacement
equipment is delivered.
B. Special warranty shall not diminish any standard manufacturer warranty period available for any
products specified within this section that are in excess of the stated 2 year requirement.
A. General:
1. Contract Drawings indicate the extent and general arrangement of the construction. No
departures from the Contract Drawings, these Specifications or the approved shop
drawings may be made without prior written approval of the Contracting Officer. Units
shall be factory prefabricated, job assembled, commercial, walk-in, room type, complete
with doors and accessory items as specified.
2. Construction shall be as approved by the National Sanitation Foundation International
and shall bear the NSF Seal of Approval.
B. Supervision:
1. Install work of this Section, and related work specified in other Sections, under the
supervision of trained and experienced personnel.
1. Where not specified elsewhere, furnish and install equipment, parts, and fittings
necessary for the proper operation of the equipment as part of the work of this Section.
Conform to applicable requirements of Divisions 22 and 23.
D. Electrical Work:
1. Where not specified elsewhere, furnish and install manual and automatic controls and
protective or signal devices required for the operation of the equipment as part of the
work of this Section. Conform to applicable requirements of Division 26.
E. Rough-in of Utilities:
1. Install water, waste, vent, gas, electric and other mechanical and electrical work, not
included as part of the cold storage room units, in accordance with Divisions 23 and 26.
Provide rough-in information, including templates, drawings to scale, and brochures to
enable work of other sections to proceed. Contract drawings are diagrammatic. As part
of this work, provide adjustments required for the various parts and the work of the
various sections to fit together for a complete and operable system.
F. Operating Temperatures:
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Panels, General:
a. Interior and exterior metal panels uniformly formed with metal dies, insulation, and
panel fasteners.
b. Wood frame panels are not acceptable.
c. UL approved, or provided with certificate of test from independent testing
laboratory, certifying to fire retardant properties of the insulation.
6. Panel Skins: 0.032 inch thick stucco embossed aluminum. Provide factory applied USDA
acceptable white baked or acrylic enamel finish.
a. The under side of ceiling panels shall have sufficient strength to support conduit
and light fixtures riveted directly to the skin. Light fixture weight is approximately
50 pounds per 8 feet of strip light.
b. Panel skins shall adhere to the insulation.
7. Door And Window Opening Framing: Structural steel channel around perimeter of
opening, foamed-in-place with insulation. Width of steel channel shall match width of
prefabricated panel.
B. Insulation:
a. Low Temperature Panels: 5-inch thickness with a minimum "R" factor of 36.
b. Medium Temperature Panels: 4-inch thickness with a minimum "R" factor of 28.
3. Insulation shall be Factory Mutual System classified Class I (per ASTM E-84) having a
flame spread of no more than 25, fuel contributed of 0, and smoke developed rating not
greater than 400 when tested in a 4-inch cross section.
C. Floor Panels:
1. 4-inch thick prefabricated insulated aluminum floor panels with 1/4 inch thick aluminum
diamond tread plate wearing surface. Provide removable 1/4 inch thick aluminum
diamond tread plate exterior ramp.
A. General:
1. Do not use vertical support columns or posts on interior or exterior of cold storage rooms.
Interior of cold storage rooms shall be free and clear of any attachments or penetrations
from supporting members.
B. Overhead-Supported Panels:
1. Where ceiling panels cannot be self-supporting on cold storage room wall panels, provide
ceiling panel support system, including fasteners and attachments, suspended from
building overhead structural system. Do not support panels from metal decking.
C. Self-Supporting Panels:
1. Where ceiling panels are self-supporting, provide ceiling panels that bear on cold storage
wall panels and span from wall to wall.
2. Design ceiling panels in accordance with performance requirements.
A. Sliding Doors:
Door Panel Cladding: 0.032 inch thick stucco embossed aluminum with factory
applied white baked or acrylic enamel finish matching prefabricated wall
panels.
Door Panel Assembly: Internal extruded aluminum frame reinforced with heavy
gage "L" brackets, vapor sealed, and insulated with foamed-in-place
polyurethane insulation.
d. Door Hardware:
Tamper-proof, with cylinder lock and provisions, when locked, of being opened
from the inside without damage to the door assembly.
Drop track guide system, with closed hood tracking system, providing immediate
gasket clearance as door opens. Track fabricated of extruded aircraft grade
aluminum throughout profile. Support sliding door panel with twin trolley
roller assembly comprised of four nylon wheels and a solid aluminum tie
bar.
Attached track and hardware shall have a corrosion resistant coating.
Provide manufacturer's standard fiber reinforced nylon door hook and polymer
bottom door guide system to provide positive seal when door is in closed
position.
Gaskets: Provide dual wiper perimeter gasket seals on door panel that are
resistant to oil, water, fats, and sunlight. Gasket material shall be
santoprene which remains pliable to minus 40 degrees F. Mount gaskets in
an extrusion on back of door panel. Door frame mounted gaskets are not
acceptable. Door bottom gasket shall be twin sweep gasket design. The first
gasket shall be located under door panel in an extruded track. The second
gasket is an adjustable gasket mounted on interior side of door panel and
easily moved up or down with contour of floor.
Provide 18 ga. stainless steel wrap at both jambs and head of door opening.
Width of stainless steel wrap shall match overall depth of door frame
assembly and return 2-inches on both faces.
Provide 48-inch high 1/8 inch thick (measured through the body of plate, not
including the raised portion) polished aluminum diamond tread protection
plates on both faces of door panel, including 4 inches wide edges of door
panel.
B. Swing Doors:
a. Door Panel Cladding: 0.032 inch thick stucco embossed aluminum with factory
applied white baked or acrylic enamel finish matching prefabricated wall panels.
b. Door Panel Assembly: Internal extruded aluminum frame reinforced with heavy
gage "L" brackets, vapor sealed, and insulated with foamed-in-place polyurethane
insulation. Provide additional reinforcing around perimeter of the door to prevent
twisting.
c. Door overall thickness, including insulation and panel skins:
4. Door Hardware:
Provide on each door that is not wider than 3 feet-9 inches nor taller than 7 feet a
spring action or hydraulic door closer that firmly close doors that have been
closed to within 1 inch of full closure.
c. Design door latch to open door by breaking the seal or force on the door gasket.
d. Provide latch with provision for a padlock and provisions, when locked, of being
opened from the inside without damage to the door latch assembly.
e. Provide door stops for doors and an assist wheel to ensure proper closure and
seal.
f. Install door mechanism and exterior hinges with tamper-proof fasteners in doors.
g. Gaskets: Provide dual wiper perimeter gasket seals on door panel that are
resistant to oil, water, fats, and sunlight. Gasket material shall be santoprene which
remains pliable to minus 40 degrees F. Mount gaskets in an extrusion on back of
door panel. Door frame mounted gaskets are not acceptable. Door bottom gasket
shall be twin sweep gasket design. The first gasket shall be located under door
panel in an extruded track. The second gasket is an adjustable gasket mounted on
interior side of door panel and easily moved up or down with contour of floor.
h. Provide 18 ga. stainless steel wrap at both jambs and head of door opening.
Width of stainless steel wrap shall match overall depth of door frame assembly and
return 2-inches on both faces.
i. Provide 48-inch high 1/8 inch thick (measured through the body of plate, not
including the raised portion) polished aluminum diamond tread protection plates on
both faces of door panel, including 4 inches wide edges of door panel.
C. Freezer Doors:
A. Flexible vertical strip barrier doors are specified in Division 08 Section Traffic Doors.
A. Double action, self-closing, lightweight, impact resistant traffic doors are specified in Division 08
Section Traffic Doors.
1. Provide 18 ga. stainless steel wrap at both jambs and head of door opening. Width of
stainless steel frame shall match overall depth of door frame assembly and return 2
inches on both faces.
A. Salient Characteristics:
1. Doors:
a. Self-closing, lift-in/lift-out type for easy cleaning, and containing magnetic gaskets
for a positive tight seal.
b. Hardware: Concealed hinges capable of hinging on either side and an attractive
modern-styled handle.
c. Heated door and frame with humidity sensing heater controllers.
Antisweat heater with antisweat heat controls: Total door rail, glass, and frame
heater power draw of 3.0 watts per square foot of door opening. The
antisweat heat controls shall reduce the energy use of the antisweat heater
in a quantity corresponding to the relative humidity in the air outside the
door or to the condensation on the inner glass pane.
a. Milk Cart: Rigid stainless steel milk bully cart (80 one gallon capacity / 180 half-
gallon capacity) - Cannon Equipment, model no. 10841-902 (26-7/8 inch wide by
26-5/16 inch deep by 65-11/16 inches high). Five (5) upper shelves constructed of
formed wire. One bottom shelf constructed of formed sheet metal channels and
square tubing. Sides constructed of square tubing. Ladder constructed of square
tubing zinc plated. Two (2) rigid and two (2) swivel casters with 6 inch by 2 inch
phenolic wheels and roller bearings, with threadguards (dairy grade casters). 1/2
inch diameter solid rear shelf support rod penetrates side frame tubes for extra
Provide six carts for each four (4) glass display doors. Any fraction shall be
rounded to the next higher number.
b. Egg Cart: Bright zinc electroplated with lacquer dip finish (240 dozen capacity) -
Cannon Equipment, model no. 83-9922-000 (26 inch wide by 24-3/4 inch deep by
66-1/4 inches high). Side and rear frames constructed of square steel tubing.
Base and two (2) folding shelves constructed of square steel tubing and sheet,
tilted back for product retention. Two (2) swivel casters with 5 inch by 2 inch
phenolic wheels. Two (2) rigid casters with 5 inch by 2 inch phenolic wheels.
Shelves and sides fold for compact storage. Top shelf locks in an intermediate
position to allow easy access to 2nd shelf, yet not interfere with top of cooler.
Provide two carts for each four (4) glass display doors. Any fraction shall be
rounded to the next higher number.
3. Cart Corral:
Cart Corral with Add-On Units: Zinc electroplated with white powder coat finish
Cannon Equipment, model 10113-901 Cart Corral (28.56 inch wide by 23.38
inch deep by 65.69 inch high) with model no. 10114-901 Add-On units.
Provide individual cart corral with add-on units fastened together to match
quantity and alignment of 1G11 glass display doors. Assemble cart corrals
with stainless steel washers as required to maintain alignment (28-3/4 inch
on-center spacing) with individual 1G11 glass doors. Sectional glass doors
will require adjustment to cart spacing to maintain alignment of carts with the
doors due to the door sectional frame requirements. Provide 1 inch by 1.5
inch steel tube cart coral side frames. Provide movable ID channels; milk
cart requires four (4) per door and egg cart requires two (2) per door.
Stainless steel side frame straps and stainless steel floor anchor plates.
Fasten to floor with manufacturers standard hardware.
2.8 WINDOWS
A. General:
1. Provide a pressure relief port for cold storage rooms operating at temperatures below
20EF. The relief port shall equalize the difference in pressure on the exterior of the cold
storage room and the pressure on the interior caused by sudden temperature changes
due to opening of doors, loading products and the defrosting of coils. Locate the relief
port in a side panel located away from the direct air stream flowing from the evaporator
coils, or other approved location. Design the relief port so that air can move into the cold
storage room or out of it. Electrically heat the relief port.
B. Lighting:
1. Provide each room with a 3-way light switch mounted near the door, one on the interior of
the room and one on the exterior of the room. Provide at additional locations as indicated
on drawings.
2. Light switches shall include a red jewel pilot light and cover plate.
3. Lights shall be vapor proof.
C. Thermometers:
PART 3 - EXECUTION
A. Equipment:
B. Materials:
1. All items shall be installed plumb, square, level and at proper elevation, and in alignment
with other work. All work shall be arranged to suit field conditions, fitted with proper
jointing and intersections. Adjust doors to operate smoothly. At completion of work,
thoroughly clean materials and equipment, remove debris from the site, and leave work in
condition acceptable to the Contracting Officer.
C. Additional Caulking:
1. After tests have been completed and approved, all exterior freezer ceiling panel joints
and exterior freezer wall panel joints (not sharing common wall with medium temperature
cold storage room) shall be sealed with silicone sealant.
1. Where cold storage rooms abut building walls and partitions, seal-off spaces with
stainless steel sheet metal closures.
E. Thermometers:
1. Locate thermometers adjacent to cold storage room door openings with capillary tube at
least 5 feet away from door opening.
3.2 PENETRATIONS
A. General:
1. Minimize required penetrations through ceilings, floors, and walls of cold storage rooms.
2. Provide PVC conduit sleeves and resilient gaskets for penetrations as indicated on
Drawings.
3. Seal penetrations tightly with silicone sealant.
4. Internally seal electrical and communication conduits to prevent moisture migration
through conduit. Conduits shall be sealed on the warm side of the penetration to prevent
air movement via convection currents. Do not seal a single conduit at multiple locations
as this will trap condensation and result in corrosion.
A. Tests, General:
1. Perform operating and performance tests on each cold storage room. Submit a written
test procedure for approval prior to performance of tests. Furnish instruments, test
equipment and personnel required for tests. The Government will furnish necessary
water and electricity for the installed equipment to perform tests. Engage and pay for an
approved independent testing laboratory to properly calibrate the test instruments
immediately prior to performing tests. Prepare written report of tests.
B. Operating Tests:
1. Perform operating tests on each cold storage room after complete adjustment and
installation of the refrigeration systems. Operate the refrigerating system long enough at
the required control settings to determine that refrigeration, defrost, and control systems
operate and cycle properly. Operating failures include component operating failures,
system leaks, and inability of the refrigeration system to maintain walk-in cooler and
freezer temperatures. Correct failures and rerun tests.
C. Performance Tests:
1. Maintain temperatures inside cold storage rooms for a period of 24 hours. Record
temperatures and submit with test report.
END OF SECTION
DESIGN CRITERIA
In accordance with DeCA Directive 30-18, dated 01 AUG 2003, construction of the Cashiers Office shall
comply with the following:
Interior wall surfaces facing room will be constructed of 5/8" gypsum wallboard on top of 3/4" fire-
retardant-treated plywood. Opposite surface of partition may be 5/8" gypsum wallboard.
Ceiling will be constructed of 1/2" gypsum wallboard on top of 3/4" ire- retardant-treated plywood, unless
interior wall surfaces extend to underside of metal roof deck, in which case a standard suspended
gypsum wallboard or acoustical tile ceiling may be installed.
Note that it is common to have extensive quantities of HVAC ductwork above the ceiling of this room.
Security bars will be required on any large duct work penetrating this secure partition. For that reason,
constructing a secure gypsum wallboard ceiling as described above is recommended.
All windows within this room shall be constructed of shatter resistant, composite, or wire mesh reinforced
glass. Laminated glass is recommended.
Customer service and cash tray windows shall be constructed to prevent individuals outside the window
from reaching funds or door locks inside the Cashiers Office.
Customer service windows shall be designed in accordance with the ABA Accessibility Standard for
Department of Defense Facilities as adopted by the Deputy Secretary of Defense memorandum dated
October 31, 2008. Refer also to Advisory 904.6 Security Glazing for assistive listening device options to
help facilitate voice communication with patrons.
Refer to Division 11 Section 11 17 00 Teller and Service Equipment for design responsibilities and
additional requirements for equipment associated with these rooms.
Windows located in exterior walls are typically not permitted by DeCA criteria. However, should an
exterior window be required, DeCAD 30-18 requires that "Windows which open to the exterior of the
building greater than 96 square inches, where the smallest dimension is greater than six inches, e.g. 7
inches by 14", will be protected by a steel rod-and-bar grid. Grid ends should be embedded in the
structure or welded to a frame that is securely attached to the structure from the inside."
Door options identified in DeCAD 30-18 include "... a minimum 1-3/4" -thick, solid wood door with 12-
gauge metal plate securely attached to the outside face; or standard 1-3/4" -thick hollow metal industrial
type door (minimum thickness of skin plate 14-gauge)". It is recommended that a security grade 14-
gauge hollow metal door be provided.
Door shall be equipped with a viewer or window that will permit personnel to be viewed and identified
prior to entry. If a viewing window is installed, it will be no larger than 24" by 24", constructed of shatter
resistant glass, composite, or wire mesh reinforced glass. It is recommended that a 12" by 12" laminated
glass window be installed in the Cashiers Office door.
DeCAD 30-18 also requires that this door shall be equipped with an automatic, secondary latchbolt lock
which cannot be left unlocked and which cannot be opened from the outside without a key. The locking
mechanism will be installed and adjusted so that when the door is closed the latch bolt is fully extended
June 2011 13 25 00 1
DeCA DESIGN CRITERIA HANDBOOK
13 25 00 CASH ROOMS
into the strike plate and the auxiliary dead latch is fully retracted to prevent "shimming" or slipping the lock
open with a plastic card or other device. If the locking bolt is visible from outside when the door is closed,
it will be further protected with a metal shield of at least 12-gauge, extending at least one inch beyond the
edge of the door frame and three inches above and below the bolt. It is recommended that a mortise lock,
with storage room function, be provided in addition to door closer.
IMPORTANT - Width of Cashiers Office door shall be 42" (or wider as required) to allow safe to be
moved through door opening. Hinges shall be 5" ball bearing type.
IMPORTANT - Width of Cash Counting Room door shall be 42" (or wider as required) to allow safe to be
moved through door opening. Hinges shall be 5" ball bearing type. Door shall be solid core wood with no
vision window.
END OF SECTION
June 2011 13 25 00 2
SECTION 21 08 00
COMMISSIONING OF FIRE SUPPRESSION
(Edited from DeCA June 2011 Design Criteria)
***********************************************************
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 DEFINITIONS
1.3 DESCRIPTION
1.4 RESPONSIBILITIES
C. Warranty Period:
3.1 STARTUP
A. Contractors shall follow the start-up and initial checkout procedures listed in the Responsibilities
list in this Section and in Division 01 Section General Commissioning Requirements. Division
11 has start-up responsibility and is required to complete systems and sub-systems so they are
fully functional, meeting the design objectives of the Contract Documents. The commissioning
procedures and functional testing do not relieve or lessen this responsibility or shift that
responsibility partially to the Commissioning Agent, Technical Inspector, or Government.
B. Functional testing will generally begin upon completion of a system. Functional testing may
proceed prior to the completion of systems or sub-systems at the discretion of the CO.
Beginning system testing before full completion does not relieve the Contractor from fully
completing the system, including all prefunctional checklists.
A. The following O&M manual requirements are in addition to O&M manual documentation
requirements elsewhere in these specifications.
B. Division 11 shall compile and prepare documentation for all commissioned items and systems
covered in Division 11 and deliver this documentation to the GC for inclusion in the O&M
manuals prior to the training of Government personnel.
A. The GC shall be responsible for training coordination and scheduling to ensure that training is
completed.
B. The QC shall be responsible for reviewing the content and adequacy of the training of
Government personnel for commissioned equipment or systems. TI will verify compliance.
C. The Subcontractor shall have the following training responsibilities for the commissioned
systems:
1. Provide the TI with a training plan four weeks before the planned training.
2. Provide designated Government personnel with comprehensive orientation and training
in the understanding of the systems and the operation and maintenance of each piece of
commissioned equipment.
3. Training shall start with classroom sessions followed by hands-on training on each piece
of equipment.
4. During any demonstration, should the system fail to perform in accordance with the
requirements of the O&M manual or sequence of operations, the system will be repaired
or adjusted as necessary and the demonstration repeated.
5. The appropriate trade or manufacturer's representative shall provide the instructions on
each major piece of equipment. This person may be the start-up technician for the piece
of equipment, the installing Contractor or manufacturer's representative. Practical
operating expertise as well as in-depth knowledge of all modes of operation of the
specific piece of equipment are required. More than one party may be required to
execute the training.
8. Hands-on training shall include start-up, operation in all modes possible, including
manual, shut-down and any emergency procedures and preventative maintenance for all
pieces of equipment.
9. Fully explain and demonstrate the operation, function and overrides of any local
packaged controls, not controlled by the central control system.
10. Training shall occur after functional testing is complete, unless approved otherwise by the
Project Manager.
11. Minimum Duration of Training. Subcontractor shall provide 8 hours of training.
END OF SECTION
PART 1 - GENERAL
1.01 Requirements
A. General. The fire protection system shall be an automatic wet pipe sprinkler system. Fire
protection design requirements shall be per NFPA 101 (The National Fire Protection
Association's Life Safety Code) and NFPA 13, Latest Edition, except where Unified Facilities
Criteria UFC 3-600-01 is indicated. The following table shows commodity class, hazard class,
densities and areas to be used for the various parts of the building.
June 2011 21 13 00 1
DeCA DESIGN CRITERIA HANDBOOK
21 13 00 FIRE -SUPPRESSION SPRINKLER
SYSTEMS
RESIDUAL
FIRE BLDG. RESIDUAL FLOW FLOW AT
HYDRANT LOCATION STATIC kPa kPa L/s 138kPa (20psi)
[XXX] [XXX] [XXX] [XXX] [XXX] [XXX]L/s
([XXX]psi) ([XXX]psi) ([XXX]gpm) ([XXX]gpm)
1.02. New Store Concept:
A. Current marketing trend eliminates suspended ceiling in Sales Area and renders ceiling
structure visible. This impact on the fire-suppression system is immediate. The design
Engineer shall provide guidance to the design Architect for appropriate visual appearance of
the fire-suppression system. Accomplish this by camouflaging fire sprinkler systems and
paralleling structural support runs with piping runs.
1.03. Remodel Concept:
A. Incorporate new store concepts during major remodeling of existing facilities. Many will not
apply. The design Engineer shall coordinate with the design Architect on those marketing
concepts to include in the construction documents. The same requirements for new store
projects shall apply for remodel projects to the extent feasible.
B. Phasing of work to accomplish the desired changes will be an important consideration to
incorporating the changes. Clearly discuss the effect of the work on the mechanical systems
in the design analysis. Discuss any conflicts or problems with attempting to incorporate the
new marketing concept application.
1.04. Post Award Submittals. [NOTE TO SPECIFIER: Include this paragraph ONLY for Navy jobs]
Prior to purchasing any system components, submit, for approval, 2 sets each of the following to
the Navy Fire Protection Engineer listed by the paragraph entitled "Distribution of Construction
Document Progress and Final Sets" in Section 3 of Division 1:
A. Manufacturer's Descriptive Data: Annotate descriptive data to show clearly the specific
model, type, and size of each item. At a minimum, submit data for the following:
1. Piping.
2. Valves, including gate, check, and globe.
3. Electrical Alarm Valve.
4. Sprinkler heads.
5. Pressure or flow switch.
6. Pipe hangers and supports.
7. Excess pressure pump.
8. Fire department connections.
9. Low air pressure supervisory panel.
10. Dry pipe valves.
11. Air compressor.
12. Mechanical couplings/fittings.
13. Backflow Preventer.
14. Tamper Switch.
15. Hose Connections.
B. Drawings. Show details, plan view, elevations and sections of the systems supply and
piping. Show piping schematic of systems supply, devices, valves, pipe, and fittings. Provide
seal and signature on each such drawing by a registered fire protection engineer licensed to
practice in at least one of the United States, its possessions, or Puerto Rico, current at the
time of the submission. At a minimum, submit the following:
1. Sprinkler heads and piping system layout.
2. Schematic of proposed system, indicating major system components, i.e., pumps, tanks,
risers, piping, building entrance, etc.
June 2011 21 13 00 2
DeCA DESIGN CRITERIA HANDBOOK
21 13 00 FIRE -SUPPRESSION SPRINKLER
SYSTEMS
END OF SECTION
June 2011 21 13 00 3
SECTION 21 13 00
FIRE-SUPPRESSION SPRINKLER SYSTEMS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
C. System Description:
1. System to provide complete coverage for the entire building, including exterior canopies.
2. Provide system to Unified Facilities Criteria - UFC 3-600-01 and National Fire Protection
Association - NFPA 13, Latest Edition, and occupancy and hazard classifications shown
on the preliminary working plans (bid documents) completed by the Engineer Of Record.
3. Determine volume and pressure of incoming water supply from water flow test data.
Conduct new water flow tests per NFPA 291. Do not rely on data shown on preliminary
working plans. Provide new water flow test data to the Engineer of Record for evaluation
and hydraulically design system based on the evaluated data from the Engineer of
Record.
4. Interface system with building fire detection and alarm system.
5. Provide fire department connections where indicated.
1. Perform Work in accordance with NFPA 13, Latest Edition, and UFC 3-600-01.
A. The following publications form a part of this Specification to the extent they are applicable:
1.4 SUBMITTALS
4. Fire Sprinkler Contractor shall perform a two hydrant flow test in accordance with NFPA
291 at time of actual Working Plan design.
C. LEED Submittal:
1. Product Data for Credit EQ 4.1: For solvent cements and adhesive primers, including
printed statement of VOC content and chemical components.
A. Division 01 Section Quality Control: Transport, handle, store, and protect products.
C. Provide temporary end caps and closures on piping and fittings. Maintain in place until
installation.
1.6 QUALIFICATIONS
B. Installer Qualifications: Company specializing in performing the work of this Section with
minimum 5 years documented experience.
B. Perform Work in accordance with NFPA 13, Latest Edition and the Unified Facilities Criteria
UFC 3-600-01. The requirements of the UFC 3-600-01 shall take precedence over the
requirements of NFPA 13.
PART 2 - PRODUCTS
2.1 SPRINKLERS
C. The operating temperature of sprinkler heads shall be as required by the specific location of
installation.
D. Extended coverage sprinklers shall not be used unless specified in the preliminary working
plans.
E. Sprinklers shall conform to the following schedule, the requirements of NFPA 13 and as
indicated in the preliminary working plans:
a. Type: Standard type with matching flat escutcheon plate. Projection below ceiling
shall not exceed 2 inches.
b. Finish: Chrome.
c. Escutcheon Plate Finish: Chrome plated.
d. Fusible Link: Fusible solder link type or glass bulb type temperature rated for
specific area hazard.
e. Sprinkler with deflectors less than 7 feet-6 inches above finished floor shall have
listed sprinkler guards.
A. Provide flexible hose assemblies and end fittings with 100 percent Type 304 Stainless steel,
with a 175 psi maximum rated pressure. Flexible hose assemblies shall be fully welded non
mechanical fittings, braided, leak tested with minimum 1 inch true bore internal corrugated hose
diameter.
B. Flexible hose assemblies shall have G90 galvanized steel ceiling bracket, direct attachment
type, having integrated snap on clip ends positively attached to the ceiling using tamper
resistant screws. Provide flexible hose attachment with removable hub type with set screw.
D. Install flexible sprinkler hose fittings for use in commercial suspended and sheetrock ceilings.
A. Piping underground shall be Class 52 cement lined ductile iron pipe or as required by the local
utility company a minimum of 5 feet-0 inches from the building. Straight runs of pipe with no
offsets may be rubber joint with bell and spigot. All fittings shall consist of mechanical joint type.
B. All buried pipe and fittings shall be installed in a sand bedded trench, 6 inches under pipe and
filled with sand to 12 inches minimum above pipe.
C. Block or rod underground piping and fittings for static and surge pressures. Furnish and install
concrete thrust blocks and joint ties at each change in direction of all underground piping in
accordance with NFPA 13 and NFPA 24 requirements. Set screw ("Mega-Lug type") restraint
shall be used in addition to concrete thrust blocks.
D. Prior to connection to existing water line, the Water Authority having jurisdiction shall be
contacted so that they can inspect the procedures used.
E. All underground pipe, fittings, and valves shall conform to NFPA 13 and NFPA 24 requirements.
A. Interior piping for automatic sprinkler system shall conform to NFPA 13, UFC 3-600-01 and as
follows.
1. Sprinkler piping above ground with threaded fittings shall be Schedule 40 black steel pipe
with a corrosion resistance rating equal to or greater than 1.0. Threaded thinwall pipe
with a CRR less than 1.0 shall not be used.
2. Fittings for threaded and coupled pipe shall consist of cast iron or malleable threaded
fittings joined with Teflon tape thread sealing compound or pipe joint compound.
Pressure rating of fittings shall be as required for application.
3. Sprinkler piping above ground with grooved fittings for sizes 2-1/2-inch and larger shall
be roll grooved Schedule 40 black steel pipe. Pressure rating of fittings shall be as
required for application.
4. Fittings for grooved end pipe shall in accordance with NFPA 13.
5. All dry sprinkler systems piping above ground 2 inches and smaller shall be galvanized
threaded fittings and Schedule 40 pipe. Sizes 2-1/2-inch and larger shall be roll grooved
Schedule 40 galvanized pipe and galvanized or painted fittings. Grooved pipe couplings
shall be galvanized or painted.
6. All exterior copper pipe shall be type K soft or hard copper with brazed copper fittings.
7. All interior copper pipe shall be type L hard copper pipe with brazed wrought or cast
copper fittings.
8. Fittings for plain end pipe shall not be used.
9. CPVC piping and fitting shall not be used.
10. Alternate piping systems approved by NFPA 13 may be allowed with prior approval of the
Engineer of Record.
11. All piping shall be identified with pre-manufactured piping identification labels.
12. All drain and Fire Department Connection piping and fittings down-stream of valves shall
be galvanized.
A. Space pipe hangers in accordance with the requirements of NFPA. Construct hangers, hanger
rods, inserts and clamps as approved by NFPA 13.
A. Furnish and install all earthquake bracing as required by NFPA 13. Construct bracing as
approved by NFPA 13.
2.7 VALVES
A. Gate valves shall be approved indicating type as required by NFPA. Check valves shall be as
required by NFPA. Test and drain valves shall be approved brass globe, angle, or ball valves.
Locate sprinkler system isolation valves as shown on the drawings complete with a tamper
alarm.
A. Install new backflow prevention devices of the type and configuration as required by the Water
Authority having jurisdiction.
B. Double Check Valve Assemblies shall be: ANSI/ASSE 1015, AWWA C510; Bronze body with
corrosion resistant internal parts and stainless steel springs; two independently operating check
valves two os&y valves, 175 psig working pressure, drain pipe to floor drain with air gap fitting.
C. Reduced Pressure Backflow Assemblies shall be: ANSI/ASSE 1013, AWWA C511; stainless
steel body with corrosion resistant internal parts and stainless steel springs; two link operating
check valves with replaceable check disc rubber, two os&y valves, 175 psig working pressure,
pressure relief with air gap fitting.
E. All reduced pressure backflow prevention devices shall be provided with an air gap drain with
splash guard and piped to the exterior or adequate floor drain with galvanized pipe and fittings.
Drain pipe shall be sized as required by the manufacturer for full flow of the relief valve.
2.9 SPECIALTIES
A. Fire Seals:
1. Where piping passes through walls, floors or other building construction which by code
requires a fire rating, approved fire rated assemblies shall be used. Proposed protection
shall be submitted for approval. Plans shall clearly indicate details and locations of
required protection.
B. Escutcheon Plates:
1. Where exposed piping passes through finish work, chrome plated or other finish
acceptable to the Governments Designated Inspector wall plates shall be installed. Split
C. Valve Identification:
1. All valves within the building shall have permanently marked identification signs provided
in accordance with NFPA 13 standards. Signs shall be manufactured and not hand
written. Signs shall be hung with galvanized or chrome chain.
1. Furnish and install a supply of extra sprinklers of each type and degree link installed in
the project, complete with mountable box. Mount box on wall next to sprinkler entry;
provide wrenches for each type of sprinkler installed in box.
E. Piping Identification:
1. All piping shall be identified at 40 foot maximum spacing and a minimum of one
identification label per room. Labels shall be Seton wrap around style or equal.
A. Install dry pipe valve complete with necessary drain valves, pressure switches, check valves,
etc., as required by NFPA 13 where shown on the drawings. Assembly shall have pressure
switches with contacts for wiring to the fire alarm system.
B. Valve shall be check type valve with divided seat ring, rubber faced clapper to automatically
actuate water motor alarm and drain valve.
C. Provide and install air compressor, automatic air maintenance device and low air alarms as
required by NFPA 13.
A. All electrical devices shall be coordinated with Division 26 Electrical and Division 28 Fire
Detection and Alarm requirements for compatibility of voltages and manufacturer.
1. Vane type switch for mounting horizontal or vertical with retard adjustment. Switch shall
have two sets of SPDT contacts; rated 10 amps at 125 volt AC and 2.5 amps at 24 volt.
Enclosure shall be NEMA 4/IP54 rated. Flow sensitivity shall be 4-10 gpm Construction
of base and cover shall be die-cast and provided with two (2) knockouts for 1/2-inch
conduit. Switch shall be UL listed for fire protection service.
E. Air Compressor:
1. Tank mounted single unit, electric motor driven, motor starter, safety valves, check
valves, air maintenance device incorporating electric pressure switch and unloader valve.
F. Tamper Switch:
1. Tamper switch shall be suitable to monitor the open position of valves. Switch shall have
two sets of SPDT contacts; rated 10 amps at 125 volt AC and 2.5 amps at 24 volt DC.
Enclosure shall be NEMA 4 and NEMA 6(IP67) rated. Construction of base and cover
having corrosion resistant finishes and tamper resistant screws. Switch shall be UL listed
for fire protection service.
2. On each control valve, arranged to actuate alarm when valve is closed.
1. Audio/Visual units shall provide a common enclosure for the fire alarm audible and visual
alarm devices. The housing shall be designed to accommodate either horns, bells, or
chimes. The unit shall be complete with a tamper resistant, Pyramidal shaped lens with
"Fire" lettering visible from a 180 degree field of view. Integral Xenon strobe shall provide
a minimum light output of 4.5 candelas at 24VDC at a 45 flashes per minute rate. Xenon
strobes shall provide a 4-wire connection to insure properly supervised in/out system
connection. Unit shall be complete with all mounting hardware including backbox.
B. Set all hose connections 3 feet above floor or as required by the Fire Marshal.
C. Hose connections shall be rough brass globe valves with replaceable seats and discs complete
with 1-1/2 inches adapter, Cap and Chain. Valves shall be 300 PSI UL rated.
1. Fire department connection shall be flush mounted wall type with chrome plated finish.
2. Outlets: Two-way with thread size to suit fire department hardware; threaded dust cap
and chain of matching material and finish.
1. Inspectors test and drain shall be Per NFPA 13, Latest Edition, Hard piped to adequate
drain or to exterior of building.
2. Minimum of one per sprinkler system zone.
PART 3 - EXECUTION
A. Design Basis Information: Provide design, materials, equipment, installation, inspection, and
testing of the automatic sprinkler system in accordance with the requirements of NFPA 13.
Recommendations in appendices shall be treated as requirements.
4. Hydraulic Calculations: Calculated demand including hose stream requirements shall fall
no less than 20 percent (10 psi) below the available water supply curve.
5. Quick response sprinkler reductions are not allowed.
6. Flexible head assemblies shall be in hydraulic calculations using the UL listing equivalent
length of Schedule 40, nominal 1 inch diameter pipe.
7. Water Supply: See preliminary working plans.
B. The fire protection system supplier shall design the piping to supply the system. Piping shall be
laid out so as not to interfere with the installation of other piping, ductwork or light fixtures.
C. The entire sprinkler system is not shown on preliminary working plans. The intent is to provide
complete sprinkler systems as required. This Contractor shall be responsible for surveying the
site, existing construction, and new construction, and prepare working plans for the total
system.
D. All piping shall be run concealed wherever possible. Where piping is run exposed, special
notation on Contractor's working plans to that effect shall be evident and conspicuous on the
drawings. Any piping determined to be a problem shall be relocated at no cost to the
Government.
F. Meet the Seismic Restraint requirements in NFPA 13, Latest Edition, Vibration Isolation and
Seismic Restraints. Seismic coefficient to be provided or derived from Table 9.3.5.6.2, NFPA
13-2010, using site specific seismic data from Table E2, UFC 3-301-01, 27 January 2010.
G. The preparation of all working plans and hydraulic calculations shall be prepared by an FPE or
Registered Professional Engineer meeting the requirements of the UFC-600-01.
3.2 INSTALLATION
1. Systems shall be equipped with a supervised isolation valve and an approved flow alarm
connected to the building fire alarm system.
2. A Fire Department Connection shall be installed on the system side of the water supply
check valve complete with its own check valve and ball drip.
3. A main drain shall be installed on each riser or sectional zone control valve and shall
drain to the exterior or to an adequate drain connection.
4. Auxiliary drains shall be provided when a change in piping direction prevents drainage of
sections of branch lines or mains through the main drain valve.
5. A test pipe of not less than 1 inch diameter terminating in an orifice equivalent to one
sprinkler shall be provided for each system or sectional zone.
6. Exterior alarm shall be installed as near as practical to Fire Department connection with
identification sign. Exterior horn/strobe shall be wired to alarm system.
C. Installation of Piping:
1. Pipe threads to be deburred, cleaned, and made free of rust prior to installation.
2. Internally and externally cold galvanize all threaded and roll grooved ends cut in the field.
Properly clean the pipe per manufactures instruction before applying the finish.
3. Accurately cut pipe to measurements established by the installer and work into place
without springing or forcing. In any situations where bending of the pipe is required, use
a standard pipe-bending template.
4. Install concealed piping in spaces that have finished ceilings. Pipe installed near
equipment shall not block or encroach on equipment access or impede maintenance.
Where ceiling mounted equipment exists, install sprinklers so as not to obstruct the
movement or operation of the equipment or block access. Sidewall heads may need to
be utilized.
5. Locate piping in stairways as near to the ceiling as possible to prevent tampering by
unauthorized personnel, and to provide a minimum headroom clearance of seven feet-six
inches. To prevent an obstruction to egress, provide piping clearances in accordance
with NFPA 101.
E. Drains: Install adequate drains piped to floor drains or out of doors. Pipe drains to discharge at
safe points outside of the building or to sight cones attached to drains of adequate size to
F. Waterflow Alarm Switches: Install waterflow switch and adjacent valves in easily accessible
locations.
G. Inspector's Test Connection: Install and supply in conformance with NFPA 13, locate in a
secured area, and discharge to the exterior of the Building.
H. Affix cutout disks, which are created by cutting holes in the walls of pipe for flow switches and
non-threaded pipe connections to the respective waterflow switch or pipe connection near to the
pipe from where they were cut.
I. Sleeves: Provide for pipes passing through masonry or concrete schedule 40 pipe. Provide
space between the pipe and the sleeve in accordance with NFPA 13. Seal this space with a UL
Listed through penetration fire stop material per UL assembly listings.
J. Provide pressure gage at each water flow alarm switch location, at the top of each standpipe,
and at each main drain connection.
K. Securely attach identification signs to control valves, drain valves, and test valves. Locate
hydraulic placard information signs at each sectional control valve where there is a zone water
flow switch.
L. Repairs: Repair damage to the building or equipment resulting from the installation of the
sprinkler system by the installer at no additional expense to the Government.
M. Where details of installation are not given, the installation shall be made using manufacturer's
recommended practices or at the direction of the Architect/Engineer.
N. Contractor shall complete the fire protection systems ready for operation, in all respects, as
soon as possible. When system is complete and ready for continuous operation, activate the
system for its intended use. After system has been activated for continuous use, water charges
will be paid by the Government.
S. Provide approved double check valve backflow preventer assembly or reduced pressure
backflow assembly at sprinkler system water source connection. Provide means of forward flow
testing at system demand per NFPA 13.
U. Locate fire department connection with sufficient clearance from walls, obstructions, or adjacent
siamese connectors to allow full swing of fire department wrench handle. For each fire
department connection, provide the symbolic sign given in NFPA 170 and locate 8 to 10 feet
Y. Center sprinklers in one direction in ceiling tile and provide piping offsets as required.
Z. Coordinate sprinkler locations with light fixtures, structure, HVAC ducts, grilles, diffusers, etc.
Provide additional heads under ducts, equipment, etc, as per NFPA 13, Latest Edition.
AA. Apply masking tape or paper cover to ensure concealed sprinklers, cover plates, and sprinkler
escutcheons do not receive field paint finish. Remove after painting.
BB. Install and connect to fire pump system in accordance with NFPA 13, Latest Edition, and
Division 21 Section Fire Pumps.
CC. Install air compressor on vibration isolators. Refer to Division 22 Section Vibration and Seismic
Controls for Plumbing Piping and Equipment.
EE. Provide all electrical devices and wiring required but not provided under Division 26.
FF. Flush entire piping system, new and existing, of foreign matter
GG. Provide labels on all controls, valves, etc. as required by NFPA 13, Latest Edition.
HH. This Contractor shall remove from the building, all rubbish and unused materials due to or
connected with this installation.
II. The surface of all piping shall be cleaned and left ready for painting.
3.3 TESTING
A. The entire sprinkler system shall be hydrostatically tested at not less than 200 psig pressure for
a period of not less than two (2) hours with no pressure drop in the system and per NFPA 13.
B. The underground fire service main shall be hydrostatically tested at not less than 200 psig
pressure for a period of not less than two (2) hours with no pressure drop in the system and per
NFPA 13.
D. Conduct Preliminary Test in the presence of the Fire Department and the FPE. The test shall
include hydrostatic test per NFPA 13, Latest Edition, and operational tests of alarms and all
other devices. Make any corrections required. Submit a signed and dated certificate, similar to
that specified in NFPA 13, Latest Edition, to the Contracting Officer. The FPE shall prepare a
report documenting the test and results.
F. Where jurisdictional authority's standards are more stringent than the above test, they shall
prevail.
A. Ensure required devices are installed and connected as required to fire alarm system.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. Source Limitations: Obtain fire pumps, pressure-maintenance pumps, and controllers through
one source from a single manufacturer for each type of equipment.
B. Product Options: Drawings indicate size, profiles, and dimensional requirements of fire pumps,
pressure-maintenance pumps, and controllers and are based on specific systems indicated.
C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
D. Comply with standards of authorities having jurisdiction pertaining to materials, hose threads,
and installation.
E. The following publications form a part of this specification to the extent they are applicable:
A. Conform to NFPA 20, NFPA 13, and UFC 3-600-01, Latest Edition.
1.5 SUBMITTALS
A. Division 01 Section Quality Control: Transport, handle, store, and protect products.
B. Accept fire pumps and components on site in factory packing. Inspect for damage. Comply with
manufacturers rigging and installation instructions.
C. Protect fire pumps and components from physical damage including effects of weather, water,
and construction debris.
D. Provide temporary inlet and outlet caps, and maintain in place until installation.
1.7 QUALIFICATIONS:
B. Installer Qualifications: Company specializing in performing the work of this Section with
minimum 5 years documented experience approved by manufacturer.
C. Design fire pump system under direct supervision of a state licensed Professional Fire
Protection Engineer experienced in design of this Work.
A. Conform to UL.
D. Provide certificate of compliance from authority have jurisdiction indicating approval of field
acceptance tests.
B. Provide one set of gaskets, screens and seals for each pump type and model supplied.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Acceptable Manufacturers:
1. Peerless.
2. Aurora.
3. Armstrong.
4. Fairbanks Morse.
5. Other U.S. Manufacturer providing U/L listed and F.M. approved fire pumps for a
minimum of the most recent 5-year period.
A. Type: UL 448 and UL 778, vertical, single stage, close coupled, radially or horizontally split
casing, for in-line mounting, for 250 psi.
B. Casting: Cast or ductile iron, with suction and discharge gage port, casing wear ring, seal flush
connection, drain plug, flanged suction and discharge.
E. Seal: Carbon rotating against a stationary ceramic seat [viton fitted,] 225 deg F maximum
continuous operating temperature.
A. Type: UL 448 and UL 778, double suction horizontal split case design for 250 psi.
B. Cast iron casing, bronze casing wearing rings, bronze impeller, high quality steel shaft with
renewable bronze shaft sleeves through the packing boxes and grease lubricated cartridge type
anti friction bearings. The packing box glands shall be of the bronze spit type. The packing box
drainage shall not be allowed to flow down to a drip tray or drip rim. Packing box drainage shall
be collected at the bearing arms and a 1/2-inch NPT connection shall be provided for piping to
an appropriate drain.
A. Eccentric suction reducer (if required) and OS&Y gate valve on suction side of pump.
B. Concentric increaser (if required) and check valve in pump discharge and OS&Y gate or
butterfly valve on system side of check valve.
C. Fire pump bypass fitted with OS&Y gate or butterfly valves and check valve where fire pump
draws from positive pressure supply.
D. Main relief valve, UL 1478, and open type waste cone where required by NFPA 20.
E. Suction pressure gage, 4-1/2 inch diameter dial with snubber, valve cock and lever handle.
I. Hose valve manifold sized per NFPA 20 with appropriate number of 2-1/2 inch hose gate valves
with caps and chains.
A. Motor: Squirrel cage induction type; in open drip proof NEMA MG-1 enclosure. Refer to
Division 23 Section Common Motor Requirements for HVAC Equipment.
B. Fire-Pump Controllers, General: UL 218 and NFPA 20; listed for electric-drive, fire-pump
service and service entrance; combined automatic and manual operation; factory assembled
and wired; and factory tested for capacities and electrical characteristics.
1. Rate controllers for scheduled fire-pump horsepower and short-circuit withstand rating at
least equal to short-circuit current available at controller location. Take into account
cable size and distance from substation or supply transformers.
1. Finish: Manufacturer's standard color paint applied to factory-assembled and -tested unit
before shipping.
2. Nameplate: Complete with capacity, characteristics, and other pertinent data.
C. Controllers: UL 508; factory-assembled, -wired, and -tested, across-the-line type for combined
automatic and manual operation.
1. Enclosure: UL 508 and NEMA 250, Type 2, wall-mounting type for field electrical wiring.
A. Description: Fire-pump flowmeter system that indicates flow to not less than 175 percent of fire-
pump rated capacity. Include sensor of size to match pipe, tubing, flowmeter, and fittings.
A. Description: UL 393, 3-1/2 to 4-1/2 inchdiameter dial with range of [0 to 250 psig] [0 to 300
psig] minimum. Include caption "WATER" on dial face.
2.9 GROUT
3.1 INSTALLATION
A. Install and align fire pump, pressure-maintenance pump, and controller according to NFPA 20.
B. Provide access space around pumps for service; no less than minimum as recommended by
manufacturer. Maintain minimum required space around controllers. Install pumps and
controllers to provide access for periodic maintenance including removal of motors, impellers,
couplings, and accessories.
D. Provide drains for bases and seals, piped to and discharging into floor drains.
E. Mount unit on vibration isolators. Refer to Division 22 Section Vibration and Seismic Controls
for Plumbing Piping and Equipment.
F. Set base-mounting-type pumps on concrete bases. Disconnect coupling halves before setting.
Do not reconnect couplings until alignment operations have been completed.
1. Support pump baseplate on rectangular metal blocks and shims or on metal wedges
having small taper, at points near anchor bolts, to provide 3/4 to 1-1/2 inch gap between
pump base and concrete base for grouting.
2. Adjust metal supports or wedges until pump and driver shafts are level. Verify that
coupling faces and pump suction and discharge flanges are level and plumb.
G. Install suction and discharge piping equal to or greater than diameter of fire-pump nozzles.
H. Install valves that are same size as piping connecting fire pumps, bypasses, test headers, and
other piping systems.
J. Support pumps and piping separately so weight of piping does not rest on pumps.
K. Install piping accessories, hangers and supports, anchors, valves, meters and gages, and
equipment supports.
L. Install flow meters and sensors where indicated. Install flow meter-system components and
make connections according to manufacturer's written instructions.
M. Electrical Wiring: Install electrical devices furnished by equipment manufacturers but not
specified to be factory mounted. Furnish copies of manufacturers' wiring diagram submittals to
electrical Installer.
A. Install concrete bases of dimensions indicated for fire pumps, pressure-maintenance pumps,
and controllers.
1. Install dowel rods to connect concrete base to concrete floor. Unless otherwise
indicated, install dowel rods on 18 inch centers around full perimeter of base.
2. For supported equipment, install epoxy-coated anchor bolts that extend through concrete
base and anchor into structural concrete floor.
3. Place and secure anchorage devices. Use setting drawings, templates, diagrams,
instructions, and directions furnished with items to be embedded.
4. Install anchor bolts to elevations required for proper attachment to supported equipment.
3.3 ALIGNMENT
Retain this Article only for split-case and end-suction fire pumps.
A. Align [split-case] [end-suction] fire-pump and driver shafts after complete unit has been
leveled on concrete base, grout has set, and anchor bolts have been tightened.
B. After alignment is correct, tighten anchor bolts evenly. Fill base plate completely with grout,
with metal blocks and shims or wedges in place. Tighten anchor bolts after grout has hardened.
Check alignment and make required corrections.
D. Align pump and driver shafts for angular and parallel alignment according to HI 1.4 and to
tolerances specified by manufacturer.
E. Align vertically mounted, split-case pump and driver shafts after complete unit has been made
plumb on concrete base, grout has set, and anchor bolts have been tightened.
3.4 CONNECTIONS
C. Connect water supply and discharge piping to [fire pumps] [fire pumps and pressure-
maintenance pumps] [pressure-maintenance pumps][with flexible connectors]. Connect
water supply and discharge piping to pressure-maintenance pumps [with flexible connectors].
[Refer to Division 21 Section Fire-Suppression Sprinkler Systems for flexible
connectors.]
G. Connect fire-pump controllers to building fire-alarm system. Refer to Division 28 Section Fire
Detection and Alarm.
END OF SECTION
GENERAL
1.01 Summary
A. The plumbing system shall include sanitary drainage, waste, and vent piping; roof drains and
interior downspouts; domestic cold water, hot water, and hot water recirculating piping;
plumbing fixtures, special fixtures, and floor drains; and, a domestic water heater. Plumbing
work shall comply with The International Plumbing, NFPA Fuel Gas Codes 54 and 58, current
editions, and Unified Facilities Criteria (UFC).
B. Plumbing Design Analysis.
1. Provide plumbing load analysis and calculations with all design submittals.
2. In the design analysis, include the following:
3. Plumbing calculations complete with all assumptions (i.e., water supply, future
requirements, sewage estimate, etc.).
4. Provide records of available water pressures and hydrant flow tests.
5. Investigation results of the availability of heat source for heating the domestic hot water.
6. Fire protection analysis, in accordance with this design criteria and applicable codes.
7. Design calculations to verify the hot water systems capacity to provide the water required
in paragraph above will be specifically included in the design analysis.
8. Include an economic analysis on heat source in the design calculations.
June 2011 22 05 00 1
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
4. For economy, consider using point-of-use water heaters for remote store areas such as
restrooms, breakrooms, Medical Food Inspectors offices, etc. which require hot water
service.
5. Heat Reclaim:
a. Domestic water supplied to the hot water heater shall be preheated with reclaimed
waste heat from the low temperature refrigeration system(s).
b. Heat recovered from the refrigeration system for water preheating shall be 25
percent of the total heat of rejection of the compressor system.
c. For hot water systems with refrigerant heat reclaim units, see Design Standard
220500-7 Plate for piping schematic.
d. Do not credit heat recovery units to determine the required hot water heater capacity.
6. Meat Processing/Wrapping Washdown Load: In addition to normal building hot water
requirements, incorporate the following meat processing/wrapping washdown load into
the building hot water heater load:
a. [On facilities of 60,000ft2 and larger, use a meat prep washdown load of 600
gal. of 140 deg F water used during a two hour period in building hot water
load calculations.]
b. [On facilities less than 60,000ft2, use a meat prep washdown load of 400 gal.
140 deg F water used during a two hour period in building hot water load
calculations.]
7. Water heater shall be sealed or separated combustion type with ducted combustion air
and not utilizing a draft hood or barometric damper when located in refrigeration
equipment rooms.
B. Water Meter. Provide one on building service.
C. Sanitary Drainage System. Provide single grease trap outside building except that in
extremely cold climates locate indoors with the concurrence of DeCA Project Manager. Size
as indicated In the Standard details, plate 22 05 00-04. Route only discharge from plumbing
fixtures in Meat Processing / Wrapping and floor drains from Meat Department through
grease trap. Install no plumbing below freezer walk-in box(es).
D. Gas meter/: Provide on building gas service.
PRODUCTS
2.01 Fixtures and Equipment. See Division 11 for detailed equipment information.
A. Water Heater/Service
1. Provide hot and cold water service at each lavatory, sink, and service sink. Also provide
hot and cold washdown stations (WS) with hose racks, and hot and cold hose stations
(HS) with hose racks.
B. Lavatories and other areas as required below. Provide soap dispensers and paper towel
dispensers at all locations that have hand-wash sinks as contractor-furnished contractor-
installed (CF/CI) equipment.
C. Fixtures. Commercial quality and equipped with water conserving devices. Provide water
closets and urinals with automatic electronic sensor flush mechanisms. Provide lavatories
with automatic electronic sensor operated faucets (120V power, no batteries permitted), fitted
with devices to limit water discharge to 2L/s (0.5gpm). Provide work sinks with combination
hot and cold mixing faucets without flow control devices.
D. Plumbing Fixtures: The A/E shall develop fixture schedules meeting the following criteria:
1. P-1 Water Closet. Standard wall hung, elongated rim, low consumption (6.0Lpf (1.6gpf))
electronic sensor operated flushometer. Equip low voltage solenoid operated valve with
June 2011 22 05 00 2
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
override button for temporary use when sensor is inoperative. Size transformer to
operate specified number of fixtures within room. Provide standard trim.
2. P-1A Water Closet. Handicapped; same as P-1 except seat at 17" - 19" above floor.
3. P-2 Urinal. Standard, wall hung, flush valve, siphon jet at 24" above floor. Provide low
consumption (1.0gpf) electronic sensor operated flushometer with low voltage solenoid
operated valve flushometer. . Equip low voltage solenoid operated valve with override
button for temporary use when sensor is inoperative. Size transformer to operate
specified number of fixtures within room. Provide standard trim.
4. P-2A Urinal. Handicapped, same as P-2 except 16" above floor.
5. P-3 Lavatory. Standard, wall hung, slab lavatory, concealed arms, 20" by 18". Equip
lavatory with electronic sensor hand washing faucet. Low voltage solenoid operated
valve shall limit water flow to 0.5 gpm max. Provide faucet with sensor range
adjustments, variable time-out settings (3 seconds min. to 20 minutes max.), back check
valves for hot/cold mixing, mixing valve and trim plates. Size transformer to operate
specified number of fixtures within room. Provide standard trim.
6. P-3A Lavatory. Handicapped wheel chair type, same as P-3 except 27-1/4" by 20-1/2",
mount rim 34" above floor.
7. Sinks: Supply all sinks with both hot and cold water. Specific water temperature
requirements for various sinks throughout the commissary are outlined below. Provide
domestic hot water system with thermostatically controlled mixing valve(s) to provide 115
deg F hot water to hand-wash sinks and controls.
a. Medical Food Inspection Office:
1) 4CKFD sink. Two compartment, stainless steel, counter type, kitchen type sink
with one 373W (.5 hp) garbage disposal. Provide with cold and 120 deg F water.
b. Janitor Closets:
1) Floor sinks: Elkay model number 3321-C or equal, with splashguard and
manufacturers mop rack. Provide with cold and 120 deg F water.
c. Employee Breakroom:
1) 4CKFD Sink. Two compartment, stainless steel, kitchen counter type. Provide
with cold and 120 deg F water.
8. Special Sinks: Supply all sinks with both hot and cold water. Specific water temperature
requirements for various sinks throughout the commissary are outlined below. Provide
domestic hot water system with thermostatically controlled mixing valve(s) to provide 115
deg F hot water to hand-wash sinks and controls. Provide with cold and 115 deg F water.
See the Guide Specifications Section 22 05 19 Plumbing Specialties.
a. Dairy Storage Room:
1) 4S01 L or R as required (formerly 1G01) Sink. One compartment, stainless
steel, drain boards, self-standing. Provide with cold and 140 deg F water and
hose sprayer.
b. Damage Merchandise Room:
1) 4S02 D (formerly 1R01) Sink. Two compartment, stainless steel, drain boards,
self-standing, one .75 hp garbage disposal, wrist action handles. Provide with
cold and 120 deg F water and hose spray.
c. Meat Processing Room:
1) 4S03 D (formerly 1M01) Sink. Three compartment, stainless steel, drain boards,
self-standing. Provide with cold and 140 deg F water, hose spray in left
compartment and swing spout in center compartment to reach all 3
compartments.
June 2011 22 05 00 3
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
2) 4S00 (formerly 2M01) Sink. Hand wash sink, stainless steel, single
compartment, with electronic sensor controls. Provide with cold and 115 deg F
water.
d. Meat Wrapping Room:
1) 4S00 (formerly 2M01) Sink. Hand wash sink, stainless steel, single
compartment, with electronic sensor controls. Provide with cold and 115 deg F
water.
e. Produce Processing:
1) 4S03 D (formerly 1P05) Sink. Three compartment, stainless steel, drain boards,
self-standing. Provide with cold and 120 deg F water, hose spray in left
compartment and swing spout in center compartment to reach all 3
compartments. Install in building drainage system with indirect waste connection
through an air gap.
2) 4S00 (formerly 2P01) Sink. Hand wash sink, stainless steel, single
compartment, with electronic sensor controls. Provide with cold and 115 deg F
water.
f. Deli/Bakery:
1) 4S00 (formerly 2D01) Sink. Hand wash sink, stainless steel, single
compartment, with electronic sensor controls. Provide with cold and 115 deg F
water.
2) 4S03 D (formerly 1B01) Sink for bakery. Three compartment, stainless steel,
drain boards, self-standing. Provide with cold and 140 deg F water, hose spray
in left compartment and swing spout in center compartment to reach all 3
compartments.
3) 4S03 D (formerly 1D20) Sink for deli. Three compartment, stainless steel, drain
boards, self-standing with one 373W (5 hp) garbage disposal. Provide with cold
and 140 deg F water and hose spray in left or right compartment and 14" swing
spout in center compartment to reach all 3 compartments.
NOTE: Separator sink required in deli for processing chickens.
g. [Clerk Service Fish Market:]
1) 4S03 D (formerly 1F10) Sink. Three compartment, stainless steel, drain boards,
self-standing, .75 hp garbage disposal. Provide with cold and 140 deg F water
and hose spray. Install in building drainage system with indirect waste
connection through an air gap.
2) 4S00 Sink. Hand wash sink, stainless steel, single compartment, with electronic
sensor controls. Provide with cold and 115 deg F water.
E. Special Drains:
1. All processing room drains shall be extra heavy duty with hinged grates strategically
located for optimal water drainage.
2. Provide chrome finished strainer for drains at finished floors.
3. Slope all floors requiring drainage downward to floor drains with a minimum slope to
drain of 1 percent, maximum slope of 2 percent. See Design Standard 22 05 00-05 for
drain detail.
4. Slope floors in all cold storage rooms, except freezers, to allow for positive drainage.
Rim elevation of floor drains shall be set 1" to 1-1/2" below finish floor with drain spacings
to provide an approximate floor slope of 1/8" per foot. Coordinate location and rim
elevation of floor drains within each cold storage room. Provide cold storage rooms with
indirect waste piping for all floor drains. Run separate waste pipes from each cold
storage room, each with an indirect connection to the building sanitary drainage system
incorporating an air gap to preclude the backflow of sewage into food storage areas.
June 2011 22 05 00 4
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
June 2011 22 05 00 5
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
b. A.R.E. interior.
c. Anti splash strainer.
d. 8" by 6" A.R.E. bucket.
8. FD-8 Gutter Drain.
a. Zurn Z572 or equal.
9. RD-1 Roof Drain.
a. Cast iron integral gravel stop with sump and wide roof flange.
b. 9" high dome.
10. Overflow Roof Drain.
a. 2" high raised rim.
G. Locations and Specifics:
1. Meat Processing and Meat Wrapping Rooms:
a. Provide two FD5 drains with 4" waste line each.
b. Provide drain lines with adequate slope to minimize fat buildup in the lines.
c. Ensure meat processing, meat wrapping, and meat storage rooms lead to a grease
interceptor located [outside] [note to specifier: sub artic locations may require
interior grease interceptors] the building.
d. See Design Standard 22 05 00-04.
2. Poultry Storage, Bulk Meat Storage, Fat and Bone Storage, Pre-Packaged Meat Storage,
Produce Storage:
a. Provide two FD5 drains with 4" waste lines centrally located for drainage.
b. Slope floor to drains.
c. See also 2.01E.
3. Room Dairy Storage:
a. Provide two FD5 drains with 4" waste lines centrally located for drainage.
b. Provide two FD6 condensate drains for unit coolers and locate to prevent damage
to condensate lines.
c. Slope floor to drains.
4. Produce Processing:
a. Provide two FD5 drains with 4" waste lines centrally located for drainage.
b. Provide one FD1 with 3" located next to ice flaker 1P04.
c. Provide one FD7 with 4" located below the three compartment sink drain board.
5. Frozen Food Storage:
a. Provide one FD2 drain with 4" waste lines within 2' to 3' outside each door. See
Design Standard Plate 22 05 00-2.
b. Locate drain out of traffic path.
6. Unloading Aisle:
a. Do not provide drains in the Unloading Aisle.
7. Damaged Merchandise:
a. Provide one 4"FD2 centrally located.
8. MHE Pad Area:
June 2011 22 05 00 6
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
June 2011 22 05 00 7
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
B. Provide with hot and cold water supply with thermostatic mixing valve for complete mixing of
water to any desired temperature.
C. Piping to hose stations: 1/2" unless otherwise noted.
D. Provide each station with check valve on hot and cold water supply line, easily accessible
and an integral vacuum breaker at the hose connection.
E. See Design Standard [22 05 00-06] for details.
F. Provide hot and cold wash down stations (WS) with 50'-0" heavy duty hose with water gun
and hose racks.
G. Provide hot and cold hose stations (HS) with 50'-0" heavy-duty hose with water gun and hose
racks.
H. Locations and Specifics:
1. Wash down Station with Stainless Steel Hose Rack (WS):
a. Provide hot (140 deg F and cold water service at each Wash down station.
b. Provide 3/4" supply.
c. Provide quantity specified at the following locations:
1) One in Meat Processing [(55)] near door to Bulk Meat Storage [(59)].
2) One at Meat Wrapping [(56)] near door to Sales Area [69)].
d. Provide 7.5 gpm for Wash down stations (WS).
2. Hose Station with Stainless Steel Hose Rack (HS):
a. Provide hot 120 deg F and cold water service at each hose station.
b. Provide 1/2" supply.
c. Do not locate on prefabricated cooler panel walls.
d. Provide quantity specified at the following locations:
1) Provide one in Dairy Storage near glass door.
a) [For stores 70,000 ft2 and larger, provide two in Dairy Storage on
opposite walls near glass doors.]
2) Provide one at Produce Storage near door to Receiving Aisle.
3) Provide one at Produce Processing near door to Produce Storage.
e. Provide 3 gpm for hose stations (HS).
2.03 Miscellaneous:
A. HB Hose Bibbs, cold water only, except as noted, locate to provide coverage with 75' hose.
1. Provide 3gpm for cold water supply.
2. Provide at the following locations:
a. MHE Pad:
1) Provide one, cold water supply only.
b. Sales Area:
1) Provide one in recessed wall enclosure at end of type 1G02 cases (hot 120 deg
F and cold water).
2) Provide one at end of 1P02 cases (hot 120 deg F and cold water).
3) Provide one in recessed wall enclosure located to best serve the meat cases (hot
120 deg F and cold water).
June 2011 22 05 00 8
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
June 2011 22 05 00 9
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
June 2011 22 05 00 10
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
June 2011 22 05 00 11
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
5. Waste from meat wrapping, meat processing, and the Deli shall go to the grease
interceptor.
6. All sink and floor drains in the meat and deli/bakery departments including floor drains in
meat storage rooms shall go to the grease interceptor. See also 2.01.E.4 for air gap
requirements.
B. 1-1/2 " and Smaller. "ABS" plastic pipe and fittings above grade in concealed locations and
hard tempered "DWV" copper with cast brass drainage fittings in exposed locations and
below grade.
C. ABS and PVC may be used where corrosive soils are present only with the concurrence of
DeCA.
2.06 Water Meters
A. Water meters shall conform to American Water Works Association (AWWA) C700.
B. Meters shall be positive displacement, oscillating piston, or disc nutation type.
C. Features:
1. Magnetic drive with magnetic shielding.
2. Straight reading sealed register graduated in cubic feet.
3. All bronze split case.
4. Integral strainer.
5. Threaded ends.
6. Pulse switch initiator.
7. Meter shall be suitable for accurately measuring and handling water at pressure,
temperatures, and flow rates to be encountered.
8. Pulse initiator shall provide maximum number of pulses up to 500 per minute that is
obtainable from the manufacturer.
9. It shall not provide less than 1-pulse per 100-gallons.
2.07 Gas Meters:
A. Gas meters shall conform to Federal Specification GG-M-2802, Style B.
B. Meters shall be suitable for accurately measuring and handling gas at pressures,
temperatures and flow rates to be encountered.
C. Meters shall have a pulse switch initiator capable of operating up to speeds of 500-pulses per
minute with no false pulses and shall require no field adjustments.
D. Initiators shall provide the maximum number of pulses up to 500 per minute that is obtainable
from the manufacturer.
June 2011 22 05 00 12
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
GENERAL
3.01 Do not locate plumbing within pre-fabricated cooler panel walls. Provide surface-mounted
plumbing in walk-in refrigerated rooms.
3.02 Do not locate sewer, storm or water lines below slabs in following rooms:
A. Frozen Food storage.
B. Ice Cream storage.
C. Bakery Freezer storage.
3.03 Coordinate gas and water meter connections to RMCS, see Section 23 09 16.
A. At lavatories with automatic low flow faucets, the HWR piping shall connect to the HW within
18" of the faucet.
C. Do not use AGA draft hoods on water heaters unless the heater is in a room by itself with
combustion air makeup and no exhaust.
D. Coordinate roof mounted equipment mounting with Architect and Structural engineer to
assure structural adequacy and adequate detailing of structure and roof flashing.
E. Where possible in new and add/alter projects consolidate the mechanical equipment into a
single equipment room unless space availability, line length or other factors make this
impractical.
G. In replacement projects, insure that hot water will be continuously available by providing an
alternate location for the new heater and leaving the existing heater in place until the new
heater is operational.
H. Detail janitors sink to prevent water accumulation below sink and wicking up walls.
I. Water heaters shall be separated combustion type with ducted combustion air when located
in Refrigeration Equipment Rooms to satisfy codes.
J. Where load on existing under floor drains is to increase with the add/alter program, conduct
video survey of line before reusing.
L. Install water hammer arrestors at all fixtures, groups of fixtures, and quick closing valves.
N. Where sump pumps or lift stations are required, connect discharge to the building sewer
outside the building.
June 2011 22 05 00 13
DeCA DESIGN CRITERIA HANDBOOK
22 05 00 COMMON WORK RESULTS FOR
PLUMBING
END OF SECTION
June 2011 22 05 00 14
SECTION 22 05 00
COMMON WORK RESULTS FOR PLUMBING
(Edited from DeCA June 2011 Design Criteria)
GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. General Provisions of the contract, including the following, shall apply to Division 22
Specification Sections: Solicitation Documents and Division 01.
A. The following publications form a part of this Specification to the extent they are applicable.
1. All work must be performed in accordance with the requirements of current editions of
local, county, state and national codes and regulations including the requirements of the
latest editions of the following:
1. All equipment, apparatus and systems shall be rated, tested, fabricated and/or installed in
accordance with the applicable industry standard mentioned. The following list will serve
to clarify abbreviations that appear in other sections of this Specification:
1.4 DEFINITIONS
A. Furnish: The term furnish means supply and deliver to the Project Site, ready for unloading,
unpacking, assembly, installation and similar operations.
B. Install: The term install describes operations at the Project Site including the actual unloading,
unpacking, assembly, erecting, placing, anchoring, applying, working to dimension, finishing,
curing, protecting, cleaning and similar operations.
C. Provide: The term provides means to furnish and install, complete and ready for intended use.
A. See Division 01 Section Quality Control for requirements for Shop Drawings and product data.
C. See applicable Sections to this Division for items requiring Shop Drawings.
A. Materials, the style, make or quality of which is specifically designated, shall be as specified.
B. Contractor shall furnish necessary materials in ample quantities and as frequently as required to
avoid delay in the progress of the Work, and shall so store them as to prevent interference with
other work.
A. All materials or work found to be defective or not in strict conformity with the drawings or
different from requirements of the drawings and specifications or defaced or injured through
negligence of Contractor or his employees, or through action of fire or weather will be rejected
and shall be immediately removed from premises by Contractor and satisfactory materials and
work substituted without delay.
B. All defective work or imperfect work shall be corrected immediately on notice from
Government's Designated Representative. No previous inspection or certificate on account
shall be held to relieve Contractor from his obligation to furnish sound materials and to perform
good and satisfactory work.
A. Contractor shall confer with other contractors at the site before installing his work to avoid
interferences so that maximum head room and clearances may be maintained. In event that
interferences develop between work of various contractors, Government's Designated
Representative's decision will be final and no additional compensation will be allowed for
changes required.
B. Particular attention shall be paid to situations where recessed equipment, pipes and lights
occur, or where the work of several trades occurs together above suspended ceilings, in pipe
shafts or in areas where space is limited.
C. All fixtures, equipment, devices, switches, outlets, pumps, etc., shall be positioned to avoid all
interferences with and to assure proper coordination with work of all other trades, cases,
partitions, wall, floor and ceiling patterns, architectural features, etc. All recessed devices,
fixtures, etc., shall be coordinated with all wall, floor and ceiling patterns. Government's
Designated Representative will reconcile conflicts and adjustments where such adjustments are
warranted.
A. Contractor shall keep all his respective pipe openings closed by means of plugs or caps to
prevent entrance of foreign matter during construction and cover all fixtures, equipment, and
apparatus as required to protect them against dirt, water, chemical or mechanical damage both
before and after installation. Any such fixtures, equipment or apparatus damaged prior to final
acceptance of the Work shall be restored to its original condition or replaced by Contractor at no
cost to Government.
A. The layout shown on the Contract Drawings is necessarily diagrammatic but shall be followed
as closely as actual construction and as other work will allow. The dimensions of work as
shown on the Contract Drawings are not as-built dimensions. No measurements shall be
scaled from the Drawings and used as definite dimensions for laying out or fitting work in place.
B. The layout of manufactured equipment as shown on the drawings shall be checked and the
exact location shall be determined from the dimensions of equipment shop drawings approved
by the Government's Designated Representative.
A. Upon completion of the Work, Contractors shall provide the Government's Designated
Representative with three copies of maintenance manual for all equipment furnished and
installed under his Work. Manuals shall be in substantial 3-ring binders with project name and
number inscribed on face and hinged back. Manual shall include roster of all Government
training session attendees. The manual shall, however, first be approved by the Government's
Designated Representative.
B. The manual shall include manufacturer's lubricating and operating instructions and parts list and
serial numbers for all operating machinery, including drive information, and motor horsepower,
amperage, and voltage readings on all phases, valve chart, sequence of operation, index
following the order listed in the specifications, warranties in the name of the Installation, and a
list of manufacturers, service firms and subcontractors names and telephone numbers.
C. Training attendance rosters for each training session shall be included in manuals. Roster will
identify training subject, date, attendees name, job title, office symbol, grade/rank, and
telephone number.
D. All switches, controls, and safety devices shall be clearly and permanently marked with
embossed or printed plates as to purpose and as to operation and shall be tested in the
presence of the Government's Designated Representative to ensure that he understands their
function and purpose.
E. Upon completion of the Work, Contractors shall put the systems into service. Contractors shall
be entirely responsible for the equipment during all testing operations including the lubricating
and turning on and off of such apparatus.
A. Refer to the Division 01 Section Closeout Procedures for requirements. The following
paragraphs supplement the requirements of Division 01.
B. Mark Drawings to indicate revisions to piping and ductwork, size and location both exterior and
interior; including locations of coils, dampers and other control devices, filters, boxes, and
similar units requiring periodic maintenance or repair; actual equipment locations, dimensioned
for column lines; actual inverts and locations of underground piping; concealed equipment,
dimensioned to column lines; mains and branches of piping systems, with valves and control
devices located and numbered, concealed unions located, and with items requiring
maintenance located (i.e., traps, strainers, expansion compensators, tanks, etc.); Change
Orders; concealed control system devices.
A. Deliver products to project properly identified with names, model numbers, types, grades,
compliance labels, and similar information needed for distinct identifications; adequately
packaged and protected to prevent damage during shipment, storage and handling.
1.14 COMMISSIONING
A. All Plumbing shall comply with the requirements of Division 01 Section General Commissioning
Requirements and Division 22 Section Commissioning of Plumbing.
PART 3 - EXECUTION
3.1 ACCESSIBILITY
A. Install equipment and materials to provide required access for servicing and maintenance.
Coordinate the final location of concealed equipment and devices requiring access with final
location of required access panels and doors. Allow ample space for removal of all parts that
require replacement or servicing.
3.2 ROUGH-IN
A. Verify final locations for rough-ins with field measurements and with the requirements of the
actual equipment to be connected.
A. General: sequence, coordinate, and integrate the various elements of plumbing systems,
materials, and equipment. Comply with the following requirements:
A. This Article specifies the cutting and patching of plumbing equipment, components, and
materials to include removal and legal disposal of selected materials, components, and
equipment.
B. Refer to Division 01 Section Quality Control for general requirements for cutting and patching.
C. Refer to Division 26 Electrical for requirements for cutting and patching electrical equipment,
components, and materials.
D. Do not endanger or damage installed Work through procedures and processes of cutting and
patching.
E. Arrange for repairs required to restore other work, because of damage caused as a result of
plumbing installations.
F. No additional compensation will be authorized for cutting and patching Work that is necessitated
by ill-timed, defective, or non-conforming installations.
G. Perform cuttings, fittings, and patching of plumbing equipment and materials required to:
H. Provide and maintain temporary partitions or dust barriers adequate to prevent the spread of
dust and dirt to adjacent areas.
3.5 CLEANING
A. Refer to the Division 01 Section Closeout Procedures for general requirements for final
cleaning.
B. Refer to Division 23 Section Testing, Adjusting, and Balancing for HVAC for requirements for
cleaning filters, strainers, and mechanical systems prior to final acceptance.
3.6 COMMISSIONING
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
B. Related Sections:
1. Division 01 Section Mechanical, Refrigeration, Food Service Equipment and Electrical
Coordination.
2. Division 01 Section Government-Furnished Products.
3. Division 01 Section Quality Control.
4. Division 01 Section Closeout Procedures.
5. Division 07 Section Ethylene-Propylene-Diene-Monomer Roofing.
6. Division 22 Section Hangers and Supports for Plumbing Piping and Equipment.
7. Division 22 Section Vibration and Seismic Controls for Plumbing Piping and Equipment.
8. Division 22 Section Plumbing Piping.
9. Division 22 Section Plumbing Fixtures.
10. Division 22 Section Plumbing Equipment.
11. Division 23 Section Hydronic Piping.
12. Division 26 Electrical.
A. The following publications form a part of this Specification to the extent they are applicable:
1. ASME A112.21.1 - Floor Drains.
2. ASME A112.21.2 - Roof Drains.
3. ASME A112.26.1 - Water Hammer Arrestors.
4. ASME B40.1 - Gages - Pressure Indicating Dial Type - Elastic Element.
5. ASME MFC-3M - Measurement of Fluid Flow in Pipes Using Orifice, Nozzle and Venturi.
1.3 SUBMITTALS
B. Do not install instruments when areas are under construction, except for required rough-in, taps,
supports and test plugs.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. See Drawings.
A. See Drawings.
A. See Drawings.
2.5 CLEANOUTS
A. See Drawings.
A. See Drawings.
2.7 HYDRANTS
A. See Drawings.
A. ANSI A112.26.1; stainless steel construction, bellows type sized in accordance with PDI WH-
201, precharged suitable for operation in temperature range 34 to 250 deg F working pressure.
2.10 SUMPS
B. Cover: 3/8 inch plate with gasket seal frames and anchor bolts.
A. Valve: Chrome plated cast brass body, stainless steel or copper alloy bellows, integral
temperature adjustment.
B. Accessories:
1. Check valve on inlets.
2. Volume control shut-off valve on outlet.
3. Stem thermometer on outlet.
4. Strainer stop checks on inlets.
C. Cabinet: 16 gage stainless steel, for recessed mounting with keyed lock.
A. Acceptable Manufacturers:
1. Maxitrol #325-5H or #210-D.
2. Fisher #S102 or S302.
3. Rockwell.
B. Construction:
1. Synthetic rubber seating surface to provide full positive shut-off.
2. Regulators shall maintain reduced pressure under static conditions when no gas is
flowing. (lock up type).
3. 2 to 5 psi inlet pressure to 4 in. to 8 in. W.G. outlet pressure. (Verify).
A. Acceptable manufacturers:
1. Boylston Figure 88.
2. Spence.
3. Monel trim.
B. Construction:
1. Gate valve before; Gate valve after; Globe valve in bypass; 1/2 inch regulator line, with
needle valve, connected 15 feet downstream.
A. Acceptable Manufacturers:
1. Hersey.
2. Rockwell.
3. American Meter.
B. Water Meters:
1. Shall conform to American Water Works Association (AWWA) C700.
2. Meters shall be positive displacement, oscillating piston, or disc nutation type.
3. Features: Magnetic drive with magnetic shielding, straight reading sealed register
graduated in cubic feet. All bronze split case, integral strainer, threaded ends, and pulse
switch initiator.
4. Meter shall be suitable for accurately measuring and handling water at pressure,
temperatures and flow rates to be encountered.
5. Pulse initiator shall provide maximum number of pulses up to 500 per minute that is
obtainable from the manufacturer. It shall not provide less than 1-pulse per 100-gallons.
A. Acceptable Manufacturers:
1. Rockwell "Equimeter."
2. American Meter.
3. Schlumberger.
B. Gas Meters:
1. Shall conform to ANSI B109.3.
2. Meters shall be suitable for accurately measuring and handling gas at pressures,
temperatures and flow rates to be encountered.
3. Meters shall have a pulse switch initiator capable of operating up to speeds of 500-pulses
per minute with no false pulses and shall require no field adjustments.
4. Initiators shall provide the maximum number of pulses up to 500 per minute that is
obtainable from the manufacturer. It shall not provide less than 1-pulse per 100 cubic
feet of gas.
A. Gage: ASME B40.1, UL 393 [UL 404] drawn steel case, phosphor bourdon tube, rotary brass
movement, brass socket, front recalibration adjustment, black scale on white background.
B. Case: Steel with brass bourdon tube or Cast aluminum with phosphor bronze bourdon tube.
F. Scale: PSI.
A. Gage Cock:
1. Tee or lever handle, brass for maximum 150 psig.
B. Needle Valve:
C. Brass, 1/4 inch NPT for minimum [150 psig.] [300 psi.]
D. Ball Valve:
1. Brass, 1/8 inch NPT 250 psi.
E. Pulsation Damper:
1. Pressure snubber, brass with 1/4 inch NPT connections.
2.19 THERMOMETERS
A. Stem Thermometer: ASTM E1, adjustable angle, red-reading liquid, lens front tube, cast
aluminum case with enamel finish, cast aluminum adjustable joint with positive locking device.
Mercury shall not be used.
1. Size: 7 inch scale.
2. Window: Clear glass or Lexan.
C. Dial Thermometer: ASTM E1, stainless steel case, bimetallic helix actuated with silicone fluid
damping, white with black markings and black pointer hermetically sealed lens, stainless steel
stem.
1. Size: 3-1/2 inch diameter dial.
2. Lens: Clear Lexan.
3. Accuracy: 1 percent.
4. Calibration: Deg F.
A. Socket: Brass separable sockets for thermometer stems with or without extensions as required,
and with cap and chain, to be mounted in piping systems.
B. Flange: 3 inch outside diameter reversible flange, designed to fasten to sheet metal air ducts,
with brass perforated stem.
2.22 SINKS
Note: Ensure The Length And Width Of This Sink Will Fit In The
Space Available At The Store.
Note: Ensure The Length And Width Of This Sink Will Fit In The
Space Available At The Store.
***A/E Edit****
Note: Ensure The Length And Width Of This Sink Will Fit In The
Space Available At The Store.
Note: Ensure The Length And Width Of This Sink Will Fit In The
Space Available At The Store.
****A/E Edit****
Note: Ensure The Length And Width Of This Sink Will Fit In The
Space Available At The Store.
****A/E Edit****
Note: Ensure The Length And Width Of This Sink Will Fit In The
Space Available At The Store.
****A/E Edit****
Note: Ensure The Length And Width Of This Sink Will Fit In The
Space Available At The Store.
****A/E Edit****
Note: Ensure The Length And Width Of This Sink Will Fit In The
Space Available At The Store.
****A/E Edit****
Note: Ensure The Length And Width Of This Sink Will Fit In The
Space Available At The Store.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Locate devices where shown on Drawings and install in accordance with manufacturer's
instructions.
E. Install approved potable water protection devices on plumbing lines where contamination of
domestic water may occur; on boiler feed water lines, janitor rooms, fire sprinkler systems,
premise isolation, irrigation systems, flush valves, and interior and exterior hose bibs.
G. Install water hammer arrestors complete with accessible isolation valve on hot and cold water
supply piping to lavatories, sinks, washing machine outlets, and each washroom or group of
fixtures.
H. Install air chambers on hot and cold water supply piping to each fixture or group of fixtures.
Fabricate same size as supply pipe or 3/4 inch minimum, and minimum 18 inches long.
I. Install one pressure gage per pump, with taps before strainers and on suction and discharge of
pump; pipe to gage with isolating valves.
J. Install pressure gages with pulsation dampers. Provide gage cock, needle valve or ball valve to
isolate each gage. Extend nipples to allow clearance from insulation.
K. Install thermometers in piping systems in sockets in short couplings. Enlarge pipes smaller than
2-1/2 inches for installation of thermometer sockets. Ensure sockets allow clearance from
insulation.
L. Install Temperature and Pressure Stations in piping adjacent to controls systems thermostat,
transmitter, or sensor sockets.
N. Provide instruments with scale ranges selected according to service with largest appropriate
scale.
O. Install gages and thermometers in locations where they are easily read from normal operating
level. Install vertical to 45 degrees off vertical.
3.2 SCHEDULES
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications for a part of this specification to the extent they are applicable.
2.1 ACCESSORIES
A. Hanger Rods: Mild steel threaded both ends, threaded one end, or continuous threaded.
B. Beam clamps shall not be of the set screw type unless they also have a positive means of
securing the clamp against horizontal movement, i.e. horizontal j-bolt extending to the opposite
flange of the beam or joist or similar device.
C. Hanger loads of up to 300 pounds can be applied to the top or bottom chord of a bar joist using
a threaded rod between the chord angles with washer and double nuts above and below the
chord within 6 inches of a panel point. Heavier loads require coordination with the joist
manufacturer.
A. Inserts: Malleable iron case of galvanized steel shell and expander plug for threaded connection
with lateral adjustment, top slot for reinforcing rods, lugs for attaching to forms; size inserts to
suit threaded hanger rods.
B. Self drilling expansion anchors, powder driven anchors, or other similar devices shall be applied
in accord with their manufacturers published ratings and instructions.
2.4 FLASHING
A. Fabrication: Welded 18 gage galvanized steel shell and base, mitered 3 inch cant, variable step
to match roof insulation, 1-1/2 inch thick insulation, factory installed wood nailer, 14 inches
minimum height, higher where noted. Vary height of curbs and rails to compensate for roof
pitch and make top of curb level.
B. For piping penetration curbs, provide a curb cap with tapered neoprene pipe flashing sleeves
and stainless steel drawbands.
C. Construct to meet the wind loading criteria and local seismic design criteria on Structural
Drawings.
2.6 SLEEVES
A. Sleeves for Pipes Through Non-fire Rated Floors: 18 gage galvanized steel.
B. Sleeves for Pipes Through Non-fire Rated Beams, Walls, Footings, and Potentially Wet Floors:
Steel pipe or 18 gauge galvanized steel.
C. Sleeves for Pipes Through Fire Rated and Fire Resistive Floors and Walls, and Fire Proofing:
Prefabricated fire rated sleeves including seals, AWL listed.
F. Sealant: Acrylic.
A. Concrete housekeeping pads shall comply with Division 03. Concrete pads shall extend 6
inches beyond equipment and be 4 inches high.
PART 3 - EXECUTION
3.1 INSTALLATION
1. Support of all equipment, piping, etc. such that it will withstand a force of 5 times its
weight in any direction and 1.5 times its weight downward.
2. Do not attach to roof deck, connect to structural members and span between same with
structural members, Unistrut, etc.
3. Roof mounted equipment curbs and roof mounting rails shall be installed to withstand the
wind and seismic loading required by Division 01 Section Summary of Work.
3.2 INSERTS
B. Provide inserts for suspending hangers from reinforced concrete slabs and sides of reinforced
concrete beams.
C. Provide hooked rod to concrete reinforcement section for inserts carrying pipe over 4 inches.
D. Where concrete slabs form finished ceiling, locate inserts flush with slab surface.
E. Where inserts are omitted, drill through concrete slab from below and provide through-bolt with
recessed square steel plate and nut recessed into and grouted flush with slab.
B. Install hangers to provide minimum 1/2 inch space between finished covering and adjacent
work.
E. Support horizontal cast iron pipe adjacent to each hub, with 5 feet maximum spacing between
hangers.
F. Support vertical piping at every floor. Support vertical cast iron pipe at each floor at hub.
G. Where several pipes can be installed in parallel and at same elevation, provide multiple or
trapeze hangers.
I. Provide [copper plated hangers and supports for copper piping] [sheet lead packing
between hanger or support and piping].
A. Provide housekeeping pads of concrete, minimum 4 inches thick and extending 6 inches
beyond supported equipment. Refer to Division 03 Section Cast-in-Place Concrete.
B. Provide templates, anchor bolts, and accessories for mounting and anchoring equipment.
C. Construct supports of steel members. Brace and fasten with flanges or plates bolted to
structure.
D. Provide rigid anchors for pipes after vibration isolation components are installed.
3.5 FLASHING
A. Provide flexible flashing and metal counterflashing where piping and ductwork penetrate
weather or waterproofed walls, floors, and roofs.
B. Provide curbs for mechanical roof installations 14 inches high, minimum, above roofing surface.
Flash and counterflash with sheet metal; seal watertight. Attach counterflashing and
mechanical equipment, and lap base flashing on roof curbs. Flatten and solder joints.
C. Adjust storm collars tight to pipe with bolts; calk around top edge. Use storm collars above roof
jacks. Screw vertical flange section to face of curb.
3.6 SLEEVES
B. Size sleeves large enough to allow for movement due to expansion and contraction. Provide for
continuous insulation wrapping.
C. Extend sleeves through floors one inch above finished floor level. Calk sleeves.
D. Where piping or ductwork penetrates floor, ceiling, or wall, close off space between pipe or duct
and adjacent work with stuffing (fire stopping at fire walls) insulation and caulk air tight. Provide
close fitting metal collar or escutcheon covers at both sides of penetration.
A. Fasten curbs to structure and units to curb in such a way as to withstand design wind loading.
END OF SECTION
****See 1BC para. 1621 and ASCE 7.02, para 9.6 for applicability of
this section and for exceptions based on seismic design category
and importance factor. The structural engineer shall determine
these values. Include, delete or edit this section as appropriate***
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 INTENT
****See 1BC para. 1621 and ASCE 7.02, para 9.6 for exceptions
based on seismic design category and importance factor. The
structural engineer shall determine these values. Include, delete or
edit this section as appropriate***
A. It is the intent of the seismic portion of this Specification to keep all plumbing building system
components in place during a seismic or wind event required by the criteria stated on the
Structural Drawings.
D. Any variance or non-compliance with these specification requirements shall be corrected by the
Contractor in an approved manner.
E. Seismic restraints shall be designed in accordance with IBC 2009, Chapter 16 and ASCE-7.
C. OSHPD: Office of Statewide Health Planning and Development for the State of California.
A. Vibration Isolators:
1. Provide vibration isolation on motor driven equipment over 0.5 HP (0.35 kW) unless
internal isolation is specified.
2. Provide minimum static deflection of isolators for equipment as scheduled on the
Contract Drawings.
B. Seismic Restraints:
C. Wind-Restraint Loading:
1.5 SUBMITTALS
B. Shop Drawings: Indicate and locate vibration isolators, with static and dynamic load on each.
Indicate and locate seismic restraints, with load on each.
C. Product Data: Provide schedule of vibration isolator and seismic restraint type with location and
load on each. Provide manufacturers product data for each isolator and restraint.
E. Manufacturer's Certificate: Certify that seismic restraints have been selected and designed by a
licensed professional engineer, licensed to practice in the state where the restraints are being
installed, to meet or exceed specified requirements.
F. Where walls, floors, slabs or supplementary steel work are used for seismic restraint locations,
details of acceptable attachment methods for pipe must be included and approved before the
condition is accepted for installation. Restraint manufacturers' submittals must include spacing,
static loads and seismic loads at all attachment and support points.
G. Seismic restraint calculations must be provided for all connections of equipment to the structure.
Calculations must be stamped by a registered professional engineer with at least five years of
seismic design experience, licensed in the state of the job location.
H. Welding certificates.
PART 2 - PRODUCTS
A. Housekeeping pad reinforcement and monolithic pad attachment to the structure details and
design shall be prepared by the restraint vendor if not already indicated on the Drawings.
B. Housekeeping pads shall be coordinated with restraint vendor and sized to provide a minimum
edge distance of ten (10) bolt diameters all around the outermost anchor bolt to allow
development of full drill-in wedge anchor ratings. If cast-in anchors are to be used, the
housekeeping pads shall be sized to accommodate the ACI requirements for bolt coverage and
embedment.
C. Housekeeping pad anchors shall consist of a ductile iron casting that is tapered and hexagonal,
smaller at its base than at its top. The upper portion shall have holes for rebar to pass through.
The anchor shall be continuously threaded from top to bottom for the attachment of soleplates.
Housekeeping pad anchors shall be attached to the structural slab using a stud wedge anchor.
Housekeeping pad anchors shall be type HPA and stud wedge anchor shall be equal to type
SAS both as manufactured by Mason Industries, Inc or equivalent.
A. Contractor shall supply supplementary support steel for all plumbing equipment, piping, etc.
including roof mounted equipment, as required or specified. When supplementary support steel
structure is welded, the contractor shall qualify procedures and personnel according to
AWS D1.1/D1.1M, "Structural Welding Code - Steel."
2.3 ATTACHMENTS
A. Contractor shall supply restraint attachment plates cast into housekeeping pads, concrete
inserts, double sided beam clamps, etc. in accordance with the requirements of the restraint
vendor's calculations.
A. Seismic Cable Restraints shall consist of galvanized steel aircraft cables sized to resist seismic
loads with a minimum safety factor of two and arranged to provide all-directional restraint.
Cables must be pre-stretched to achieve a certified minimum modulus of elasticity. Cable end
connections shall be steel assemblies that swivel to final installation angle and utilize two
clamping bolts to provide proper cable engagement. Cables must not be allowed to bend
across sharp edges. [Cable assemblies shall have an Anchorage Preapproval "R" Number
from OSHPD in the State of California verifying the maximum certified load ratings].
Cable assemblies shall be Type SCB at the ceiling and at the clevis bolt, SCBH between the
hanger rod nut and the clevis or SCBV if clamped to a beam all as manufactured by Mason
Industries, Inc or equivalent.
B. Seismic solid braces shall consist of steel angles or channels to resist seismic loads with a
minimum safety factor of 2 and arranged to provide all directional restraint. Seismic solid brace
end connectors shall be steel assemblies that swivel to the final installation angle and utilize two
through bolts to provide proper attachment. [Seismic solid brace assembly shall have
anchorage preapproval "R" number from OSHPD in the state of California verifying the
maximum certified load ratings]. Solid seismic brace assemblies shall be equal to type SSB
as manufactured by Mason Industries, Inc or equivalent.
C. Steel angles, sized to prevent buckling, shall be clamped to pipe or equipment rods utilizing a
minimum of three ductile iron clamps at each restraint location when required. Welding of
support rods is not acceptable. [Rod clamp assemblies shall have an Anchorage
Preapproval "R" Number from OSHPD in the State of California]. Rod clamp assemblies
shall be equal to type SRC as manufactured by Mason Industries, Inc or equivalent.
D. Pipe clevis cross bolt braces are required in all restraint locations. They shall be special
purpose preformed channels deep enough to be held in place by bolts passing over the cross
bolt. [Clevis cross braces shall have an Anchorage Preapproval "R" Number from
OSHPD in the State of California]. Clevis cross brace shall be equal to type CCB as
manufactured by Mason Industries, Inc or equivalent.
F. All directional seismic snubbers shall consist of interlocking steel members restrained by shock
absorbent rubber materials compounded to bridge bearing specifications. Elastomeric materials
shall be replaceable and a minimum of 3/4 inch thick. Rated loadings shall not exceed 1000
psi. Snubbers shall be manufactured with an air gap between hard and resilient material of not
less than 1/8 inch nor more that 1/4 inch. Snubbers shall be installed with factory set
clearances. The capacity of the seismic snubber at 3/8 inch deflection shall be equal or greater
than the load assigned to the mounting grouping controlled by the snubber multiplied by the
applicable "G" force. Submittals shall include the load deflection curves up to 1/2 inch
deflection in the x, y and z planes. [Snubbers shall have an anchorage preapproval "R"
number from OSHPD in the state of California verifying the maximum certified horizontal
and vertical load ratings]. Snubbers shall be equal to series Z-1011 as manufactured by
Mason Industries, Inc or equivalent.
G. Stud wedge anchors shall be manufactured from full diameter wire, not from undersized wire
that is "rolled up" to create the thread. The stud anchor shall also have a safety shoulder which
fully supports the wedge ring under load. The stud anchors shall have an evaluation report
number from the I.C.B.O Evaluation Service, Inc. verifying its allowable loads. Drill-in stud
wedge anchors shall be equal to type SAS as manufactured by Mason Industries, Inc or
equivalent.
H. Female wedge anchors are preferred in floor locations so isolators or equipment can be slid into
place after the anchors are installed. Anchors shall be manufactured from full diameter wire,
and shall have a safety shoulder to fully support the wedge ring under load. Female wedge
anchors shall have an evaluation report number from the I.C.B.O Evaluation Service, Inc.
verifying to its allowable loads. Drill-in female wedge anchors shall be equal to type SAB as
manufactured by Mason Industries, Inc or equivalent.
PART 3 - EXECUTION
3.1 INSTALLATION
B. Installation of vibration isolators and seismic restraints must not cause any change of position of
equipment or piping resulting in stresses or misalignment.
C. Coordinate work with other trades to avoid rigid contact with the building.
D. Overstressing of the building structure must not occur because of overhead support of
equipment. Contractor must submit loads to the structural engineer of record for approval.
Generally bracing may occur from:
E. Cable restraints shall be installed slightly slack to avoid short circuiting the isolated suspended
equipment, piping or conduit.
F. Cable assemblies are installed taut on non-isolated systems. Seismic solid braces may be used
in place of cables on rigidly attached systems only.
G. At locations where cable restraints are located, the support rods must be braced when
necessary to accept compressive loads with braces.
H. At all locations where cable restraints are attached to pipe clevis's, the clevis cross bolt must be
reinforced with specification braces.
I. Equipment 400 lbs. and less mounted 4 feet or less above floor level is excepted.
1. Seismically restrain all piping listed as a, b or c below. Use cables if isolated. Rigid
restraints may be used on unisolated piping.
a. Fuel oil piping, gas piping, medical gas piping, and compressed air piping that is 1
inch I.D or larger.
b. Piping located in boiler rooms, mechanical equipment rooms, and refrigeration
equipment rooms that is 1-1/4 inch I.D. and larger.
c. All other piping 1-1/2 inch diameter and larger.
2. Transverse piping restraints shall be at 40 foot maximum spacing for all pipe sizes,
except where lesser spacing is required to limit anchorage loads.
3. Longitudinal restraints shall be at 80 foot maximum spacing for all pipe sizes, except
where lesser spacing is required to limit anchorage loads.
4. Where thermal expansion is a consideration, guides and anchors may be used as
transverse and longitudinal restraints provided they have a capacity equal to or greater
than the restraint loads in addition to the loads induced by expansion or contraction.
5. For fuel oil and all gas piping transverse restraints must be at 20 foot maximum and
longitudinal restraints at 40 foot maximum spacing.
6. Transverse restraint for one pipe section may also act as a longitudinal restraint for a
pipe section of the same size connected perpendicular to it if the restraint is installed
within 24 inches of the elbow or TEE or combined stresses are within allowable limits at
longer distances.
7. Hold down clamps must be used to attach pipe to all trapeze members before applying
restraints in a manner similar to clevis supports.
8. Branch lines may not be used to restrain main lines.
9. Cast iron pipe of all types, glass pipe and any other pipes joined with a four band shield
and clamp assembly in Zones 2B, 3 and 4 shall be braced as in T. 2 and 3 above. For
Zones 0, 1 and 2A, 2 band clamps may be used with reduced spacings of 1/2 of those
listed in T.2 and 3.
END OF SECTION
1.1 SUMMARY
A. Section Includes:
1. Nameplates.
2. Tags.
3. Stencils.
4. Pipe Markers.
B. Related Sections:
1. Division 01 Section Mechanical, Refrigeration, Food Service Equipment and Electrical
Coordination.
2. Division 01 Section Quality Control.
3. Division 01 Section Closeout Procedures.
A. The following publications form a part of this Specification to the extent they are applicable:
1. Division 01 Section Quality Control.
2. ASME A13.1 - Scheme for the Identification of Piping Systems.
PART 2 - PRODUCTS
2.1 NAMEPLATES
A. Description: Laminated three-layer plastic with engraved black letters on light contrasting
background color, 4 inch by 1-1/2 inch or larger.
2.2 TAGS
A. Plastic Tags: Laminated three-layer plastic, brass, or aluminum with engraved black letters on
light contrasting background color. Tag size minimum 1-1/2 inch.
B. Plastic Pipe Markers: Factory fabricated, flexible, semi- rigid plastic, preformed to fit around pipe
or pipe covering; minimum information indicating flow direction arrow and identification of fluid
being conveyed.
2.4 STENCILS
B. Stencil Paint: As specified in Division 09 Section Painting and Coating, semi-gloss enamel,
colors and lettering size conforming to ASME A13.1.
PART 3 - EXECUTION
3.1 PREPARATION
B. Prepare surfaces in accordance with Division 09 Section Painting and Coating for stencil
painting.
3.2 INSTALLATION
F. Install plastic tape pipe markers complete around pipe in accordance with manufacturer's
instructions.
G. Identify pumps, heat transfer equipment, tanks, and water treatment devices with plastic
nameplates. Small devices, such as in-line pumps, may be identified with tags.
H. Identify control panels and major control components outside panels with plastic nameplates.
K. Identify piping, concealed or exposed, with plastic pipe markers or plastic tape pipe markers.
Delete markers on piping 3/4 inch diameter and smaller. Identify service and flow direction.
Install in clear view and align with axis of piping. Locate identification not to exceed 50 feet on
straight runs including risers and drops, adjacent to each valve and Tee, at each side of
penetration of structure or enclosure, and at each obstruction.
L. Provide ceiling tacks to locate equipment or dampers above T-bar type panel ceilings. Locate
in corner of panel closest to equipment.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Piping insulation.
2. Jackets and accessories.
B. Related Sections:
A. Materials: Flame spread/smoke developed rating of 25/50 or less in accordance with NFPA 255
and UL 723.
B. All materials and insulating values shall comply with the International Energy Conservation
Code.
A. The following publications form a part of this specification to the extent they are applicable:
1.4 SUBMITTALS
a. Product Data for Credit EQ 4.1: For adhesives and sealants, including printed
statement of VOC content.
B. Deliver materials to site in original factory packaging, labeled with manufacturer's identification,
including product density and thickness.
F. Maintain temperature during and after installation for minimum period of 24 hours.
1.6 QUALIFICATIONS
A. Applicator: Company specializing in performing the work of this section with minimum three
years experience.
PART 2 - PRODUCTS
A. Insulation:
1. ASTM C921, white kraft paper with glass fiber yarn, bonded to aluminized film.
2. Moisture Vapor Transmission: ASTM E96; 0.02 perm-inches.
C. Tie Wire:
1. 16-gauge soft annealed stainless steel with twisted ends on maximum 12 inch centers.
2.2 JACKETS
A. PVC Plastic:
1. Jacket: ASTM D1784, One piece molded type fitting covers and sheet material, off-white
color.
B. Jacket:
1. White all serviceable jacket with evaporation holes, cap seal joints and butt strips, no
staples.
2. Permeance: 0.4 perms maximum.
C. Premolded Fittings:
A. Fiberglass insulation installed outdoors and subject to water damage shall be provided with an
additional 0.016 inch aluminum jacket with lock seam longitudinal joint and stainless steel
"Bandit" straps for butted joints as required for a water-tight installation.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that piping has been tested before applying insulation materials.
B. Verify that surfaces are clean, foreign material removed, and dry.
3.2 INSTALLATION
A. General:
B. Installation: Glass fiber insulated pipes conveying fluids below ambient temperature:
1. For hot piping conveying fluids over 140 deg F, insulate flanges and unions at equipment.
2. Glass fiber insulated pipes conveying fluids above ambient temperature:
1. All longitudinal and butt joints shall be fully glued and sealed.
1. Install in accordance with NAIMA National Insulation Standards and Knauf installation
instructions.
2. Where insulation is indicated to be replaced, remove existing insulation. Allow piping to
warm to above the dew point and to dry thoroughly before applying new insulation.
Coordinate with the Commissary Officer to schedule work for times when the
Commissary is closed.
3. Insulate fittings, joints, and valves with insulation of like material and thickness as
adjoining pipe. Finish with PVC fitting covers. Install wicking material as directed by
manufacturer.
4. Continue insulation through walls, sleeves, pipe hangers, and other pipe penetrations.
Finish at supports, protrusions, and interruptions. At fire separations, refer to Division 07
Section Firestopping.
5. Install jacket with evaporation holes aligned with wicking material at the bottom of the
pipe.
a. Shields: Galvanized steel between pipe hangers or pipe hanger rolls and inserts.
b. Insert location: Between support shield and piping and under the finish jacket.
c. Insert configuration: Minimum 6 inches long, of same thickness and contour as
adjoining insulation; may be factory fabricated.
d. Insert material: Hydrous calcium silicate insulation or other heavy density
insulating material suitable for the planned temperature range.
3.3 TOLERANCE
A. Substituted insulation materials shall provide thermal resistance within 10 percent at normal
conditions, as materials indicated.
A. Plumbing Piping:
Domestic Hot Water, Hot Recirculated: Over 2 inch 1.5 inchOver 1 inch 1.0 inch
1 inch and less 1/2 inch
A. Roof drain bodies, horizontal downspouts above grade, and vertical downspouts from drains to
horizontal downspouts:
All 1
A. Insulation installed outdoors shall be provided with an additional 0.016 inch aluminum jacket
with lock seam longitudinal joint and stainless steel "Bandit" straps for butted joints as required
for a water-tight installation.
END OF SECTION
***********************************************************
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 DEFINITIONS
1.3 DESCRIPTION
3. Warranty Period:
B. Plumbing Contractor: The responsibilities of the Plumbing Contractor, during construction and
acceptance phases in addition to those listed in Paragraph A, above, are:
1) Controlled system.
2) Point abbreviation.
3) Point description.
4) Display unit.
5) Control point or setpoint (Yes / No).
6) Monitoring point (Yes / No).
7) Intermediate point (Yes / No).
8) Calculated point (Yes / No).
9) Key:
9. An updated as-built version of the Control Drawings and sequences of operation shall be
included in the final controls O&M manual submittal.
10. Assist and cooperate with the CA in the following manner:
a. Using a skilled technician who is familiar with the installed systems in this building,
execute the functional testing of the controls system. Assist in the functional testing
of all equipment. Provide two-way radios during the testing.
b. Execute all control system trend logs.
PART 3 - EXECUTION
3.1 STARTUP
A. The Plumbing shall follow the start-up and initial checkout procedures listed in the
Responsibilities list in this Section and in Division 01 Section General Commissioning
Requirements. Division 22 has start-up responsibility and is required to complete systems and
sub-systems so they are fully functional, meeting the design objectives of the Contract
Documents. The commissioning procedures and functional testing do not relieve or lessen this
responsibility or shift that responsibility partially to the commissioning agent, technical inspector
or Government.
B. Functional testing is intended to begin upon completion of a system. Functional testing may
proceed prior to the completion of systems or sub-systems at the discretion of the CO.
Beginning system testing before full completion does not relieve the Contractor from fully
completing the system, including all prefunctional checklists as soon as possible.
A. The following O&M manual requirements do not replace O&M manual documentation
requirements elsewhere in these Specifications.
B. Division 22 shall compile and prepare documentation for all commissioned systems covered in
Division 22 and deliver this documentation to the GC for inclusion in the O&M manuals prior to
the training of Government personnel.
1. Three copies of the controls training manuals in a separate manual from the O&M
manuals.
2. Operation and Maintenance Manuals containing:
a. Specific instructions on how to perform and apply all functions, features, modes,
etc. mentioned in the controls training sections of this specification and other
features of this system. These instructions shall be step-by-step. Indexes and
clear tables of contents shall be included. The detailed technical manual for
programming and customizing control loops and algorithms shall be included.
b. Full as-built set of Control Drawings.
c. Full as-built sequence of operations for each piece of equipment.
d. Full points list: A listing of all rooms shall be provided with the following
information for each room:
1) Floor.
2) Room number.
3) Room name.
4) Reference drawing number.
e. Full print out of all schedules and set points after testing and acceptance of the
system.
f. Full as-built print out of software program.
g. Electronic copy on disk of the entire program for this facility.
h. Marking of all system sensors and thermostats on the as-built floor plan and
Mechanical Drawings with their control system designations.
i. Maintenance instructions, including sensor calibration requirements and methods
by sensor type, etc.
j. Control equipment component submittals, parts lists, etc.
k. Warranty requirements.
l. Copies of all checkout tests, other than commissioning tests, and calibrations
performed by the Contractor.
3. The manual shall be organized and subdivided with permanently labeled tabs for each of
the following data in the given order:
a. Sequences of operation.
b. Control drawings.
c. Points lists.
d. Controller / module data.
e. Thermostats and timers.
f. Sensors and DP switches.
g. Valves and valve actuators.
h. Dampers and damper actuators.
i. Program setups (software program printouts).
4. Field checkout sheets and trend logs should be provided to the GC for inclusion in the
on-site Commissioning filing system.
A. The GC shall be responsible for training coordination and scheduling and ultimately to ensure
that training is completed.
B. The QC shall be responsible for reviewing the content and adequacy of the training of
Government personnel for commissioned equipment or systems. TI will verify compliance.
C. Plumbing Contractors: The Plumbing Contractors shall have the following training
responsibilities for their respective commissioned systems:
1. Provide the TI with a training plan four weeks before the planned training.
2. Provide designated Government personnel with comprehensive orientation and training
in the understanding of the systems and the operation and maintenance of each piece of
commissioned equipment.
3. Training shall start with classroom sessions followed by hands-on training on each piece
of equipment.
4. During any demonstration, should the system fail to perform in accordance with the
requirements of the O&M manual or sequence of operations, the system shall be
repaired or adjusted as necessary and the demonstration repeated.
5. The appropriate trade or manufacturer's representative shall provide the instructions on
each major piece of equipment. This person may be the start-up technician for the piece
of equipment, the Installing Contractor or manufacturer's representative. Practical
building operating expertise as well as in-depth knowledge of all modes of operation of
the specific piece of equipment is required. More than one party may be required to
execute the training.
6. The Controls Contractor shall attend sessions other than the controls training, as
requested, to discuss the interaction of the controls system as it relates to the equipment
being discussed.
7. The training sessions shall follow the outline in the Table of Contents of the operation and
maintenance manual and illustrate whenever possible the use of the O&M manuals for
reference.
8. Training shall include:
9. Hands-on training shall include start-up, operation in all modes possible, including
manual, shut-down and any emergency procedures and preventative maintenance for all
pieces of equipment.
10. Fully explain and demonstrate the operation, function and overrides of any local
packaged controls, not controlled by the central control system.
SYSTEM HOURS
Domestic Water Systems 8
D. Controls Contractor: The Controls Contractor shall have the following training responsibilities:
1. Provide the CA with a training plan four weeks before the planned training.
2. The Controls Contractor shall provide designated Government personnel training on the
control system in this facility. The intent is to clearly and completely instruct the
Government on all the capabilities of the control system.
3. Training manuals: The standard operating manual for the system and any special
training manuals shall be provided for each trainee. In addition, copies of the system
technical manual shall be demonstrated during training. Manuals shall include detailed
description of the subject matter for each session. The manuals shall cover all control
sequences and have a definitions section that fully describes all relevant words used in
the manuals and in all software displays. Copies of audiovisuals shall be delivered to the
Government.
4. The training sessions shall be tailored to the needs and skill-level of the trainees.
5. The trainers shall be knowledgeable on the system and its use in buildings.
6. During any demonstration, should the system fail to perform in accordance with the
requirements of the O&M manual or sequence of operations, the system shall be
repaired or adjusted as necessary and the demonstration repeated.
7. The Controls Contractor shall attend sessions other than the controls training, as
requested, to discuss the interaction of the controls system as it relates to the equipment
being discussed.
8. Provide three training sessions structured as follows:
a. Training I: Control System. The first training shall consist of 8 hours of actual
training. This training may be held on-site or in the supplier's facility. If held off-
site, the training may occur prior to final completion of the system installation.
Upon completion, each student, using appropriate documentation, should be able
to perform elementary operations and describe general hardware architecture and
functionality of the system.
b. Training II: Building Systems. The second session shall be held on-site for a
period of 24 hours of actual hands-on training after the completion of system
commissioning. The session shall include instruction on:
c. Training III: The third training will be conducted on-site six months after occupancy
and consist of 16 hours of training. The session shall be structured to address
specific topics that trainees need to discuss and to answer questions concerning
operation of the system.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
a. Sanitary sewer.
b. Domestic water.
c. Storm water.
d. Natural gas.
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
C. Welding Materials and Procedures: Conform to ASME SEC IX and applicable state labor
regulations.
D. Identify pipe with marking including size, ASTM material classification, ASTM specification,
potable water certification, water pressure rating.
1.4 SUBMITTALS
A. Division 01 Section Quality Control: Transport, handle, store, and protect products.
B. Accept valves on site in shipping containers with labeling in place. Inspect for damage.
D. Provide temporary end caps and closures on piping and fittings. Maintain in place until
installation.
E. Protect piping systems from entry of foreign materials by temporary covers, completing sections
of the work, and isolating parts of completed system.
A. Perform Work in accordance with International Plumbing Code (IPC) and International Fuel Gas
Code (IFGC).
PART 2 - PRODUCTS
***ABS and PVC maybe used in corrosive soils only with the
concurrence of DeCA***
1. Cast Iron Pipe 2 Inches and Larger: CISPI 301, hubless, service weight.
a. Fittings: ABS.
b. Joints: ASTM D2235, solvent weld.
a. Fittings: PVC.
b. Joints: ASTM D2885, solvent weld with ASTM D2564 solvent cement.
a. Fittings: ASME B16.18, cast copper alloy or ASME B16.22 wrought copper and
bronze.
b. Joints: AWS A5.8, BCuP silver braze.
a. Fittings: ASME B16.18, cast copper alloy or ASME B16.22, wrought copper and
bronze.
b. Joints: ASTM B32, solder, Grade 95TA.
a. Fittings: ABS.
b. Joints: ASTM D2235, solvent weld.
a. Fittings: PVC.
b. Joints: ASTM D2855, solvent weld with ASTM D2564 solvent cement.
a. Fittings: PVC.
b. Joints: ASTM F477, elastomeric gaskets.
a. Fittings: ABS.
b. Joints: ASTM D2235, solvent weld.
a. Fittings: PVC.
b. Joints: ASTM D2855, solvent weld with ASTM D2564 solvent cement.
a. Fittings: PVC.
b. Joints: ASTM F477, elastomeric gaskets.
A. Not permitted.
1. Fittings: 2 inches and smaller - ASME B16.3, malleable iron. Larger than 2 inches -
ASTM A234/A234M, forged steel welding type.
2. Joints: NFPA 54, threaded or welded to ANSI B31.1.
1. Ferrous Pipe: Class 150 malleable iron threaded or forged steel slip-on flanges;
preformed neoprene gaskets.
2. Copper Tube and Pipe: Class 150 slip-on bronze flanges; preformed neoprene gaskets.
1. Housing: Malleable iron clamps to engage and lock, designed to permit some angular
deflection, contraction, and expansion; steel bolts, nuts, and washers; galvanized for
galvanized pipe.
2. Sealing Gasket: "C" shape composition sealing gasket.
D. Dielectric Connections: Union with galvanized or plated steel threaded end, copper solder end,
water impervious isolation barrier.
1. MSS SP-80, Class 150, bronze body, bronze trim, rising stem, handwheel, inside screw,
solid wedge disc, solder or threaded ends.
1. MSS SP-80, Class 125, bronze body, bronze trim, handwheel, bronze disc, solder or
threaded ends.
A. Construction, 4 Inches and Smaller: MSS SP-110, Class 150, bronze, two piece body, chrome
plated brass ball, regular port, Teflon seats and stuffing box ring, blow-out proof stem, lever
handle, solder or threaded ends.
A. Construction 2-1/2 Inches and Larger: MSS SP-78, 175 psi, cast iron body and plug, pressure
lubricated, Teflon or Buna N packing, flanged or grooved ends. Provide lever operator with set
screw.
A. Construction 2 inches or Less: MSS SP-67, 200 psi, bronze iron body, bronze disc, resilient
replaceable seat, extended neck, lever handle.
1. MSS SP-80, Class 125, bronze body and cap, bronze swing disc with rubber seat, solder
or threaded ends.
1. MSS SP-71, Class 125, iron body, bronze swing disc, renewable disc seal and seat,
flanged or grooved ends.
A. Pressure Relief:
1. AGA Z21.22 certified, bronze body, Teflon seat, steel stem and springs, automatic, direct
pressure actuated.
1. AGA Z21.22 certified, bronze body, Teflon seat, stainless steel stem and springs,
automatic, direct pressure actuated, temperature relief maximum 210 degrees F, capacity
ASME SEC IV certified and labeled.
2.18 STRAINERS
1. Threaded brass body for Class 150, threaded bronze body, Y pattern with 1/32 inch
stainless steel perforated screen.
1. Class 125, flanged iron body, Y pattern with 1/16 inch stainless steel perforated screen.
PART 3 - EXECUTION
3.1 EXAMINATION
3.2 PREPARATION
A. Ream pipe and tube ends. Remove burrs. Bevel plain end ferrous pipe.
3.3 INSTALLATION
C. Route piping in orderly manner and maintain gradient. Route parallel and perpendicular to
walls.
D. Install piping to maintain headroom, conserve space, and not interfere with use of space.
F. Install piping to allow for expansion and contraction without stressing pipe, joints, or connected
equipment. Refer to Division 23 Expansion Fittings and Loops for HVAC Piping.
G. Provide clearance in hangers and from structure and other equipment for installation of
insulation and access to valves and fittings. Refer to Division 22 Section Plumbing Piping
Insulation.
I. Establish elevations of buried piping outside the building to ensure not less than 5 foot of cover.
J. Install vent piping penetrating roofed areas to maintain integrity of roof assembly; refer to
Division 07 for Roofing.
K. Where pipe support members are welded to structural building framing, scrape, brush clean,
and apply one coat of zinc rich primer to welding.
L. Provide support for utility meters in accordance with requirements of utility companies.
M. Prepare exposed, unfinished pipe, fittings, supports, and accessories ready for finish painting.
Refer to Division 09 Section Painting and Coating.
N. Excavate in accordance with Division 31 Section Earthwork for work of this Section.
O. Backfill in accordance with Division 31 Section Earthwork for work of this Section.
U. Inserts:
3.4 APPLICATION
C. Install brass male adapters each side of valves in copper piped system. Solder adapters to
pipe.
D. Install gate ball or butterfly valves for shut-off and to isolate equipment, part of systems, or
vertical risers.
E. Install globe ball or butterfly valves for throttling, bypass, or manual flow control services.
B. Establish invert elevations, slopes for drainage to 1/4 inch per foot for pipe 3 inches and
smaller, 1/8 inch per foot for larger pipes. Maintain gradients.
C. Slope water piping minimum 0.25 percent and arrange to drain at low points.
B. Ensure Ph of water to be treated is between 7.4 and 7.6 by adding alkali (caustic soda or soda
ash) or acid (hydrochloric).
C. Inject disinfectant, free chlorine in liquid, powder, tablet or gas form, throughout system to
obtain 50 to 80.09 ppm residual.
D. Bleed water from outlets to ensure distribution and test for disinfectant residual at minimum 15
percent of outlets.
F. If final disinfectant residual tests less than 25.02 ppm, repeat treatment.
G. Flush disinfectant from system until residual equal to that of incoming water or 1.00 ppm.
H. Take samples no sooner than 24 hours after flushing, from 10 percent of outlets and from water
entry, and analyze in accordance with AWWA C651.
3.8 SCHEDULES
1. Metal Piping:
2. Plastic Piping:
3.9 TESTING
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Water heaters.
2. Water storage tanks.
3. Sump pumps.
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
1.3 SUBMITTALS
B. Provide pumps with manufacturer's name, model number, and rating/capacity identified.
D. Ensure pumps operate at specified system fluid temperatures without vapor binding and
cavitation, are non-overloading in parallel or individual operation; operate within 25 percent of
midpoint of published maximum efficiency curve.
1. Provide temporary inlet and outlet caps. Maintain caps in place until installation.
1.7 WARRANTY
1. Provide five year manufacturer warranty for domestic water heaters and water storage
tanks.
PART 2 - PRODUCTS
B. Tank: Glass lined welded steel; thermally insulated with minimum 2 inches, glass fiber or
polyurethane encased in corrosion-resistant steel jacket; baked-on enamel finish.
C. Controls: Automatic immersion water thermostat; externally adjustable temperature range from
60 to 180 deg F flanged or screw-in nichrome elements, high temperature limit thermostat.
D. Accessories: Brass water connections and dip tube, drain valve, magnesium anode, and
ASME rated temperature and pressure relief valve.
A. Packaged, integrated, separated combustion water heater with storage tank, controls,
circulators and local piping. See Drawings for performance.
B. Heater design shall be [copper tubes having extruded integral fins and mounted in
accessible cast iron headers with an insulated enameled steel jacket.] [condensing flue
coil, glass coated on the flue gas side.] Pressure rating shall be 160 psig. Efficiency shall be
[82 percent] [92 percent].
D. Glass lined steel tank, ASME labeled; 2 inches glass fiber, encased in corrosion-resistant steel
jacket; baked-on enamel finish; built in drain pan, floor shield and legs.
E. Accessories: Brass water connections and dip tube, drain valve, magnesium anode, and ASME
rated temperature and pressure relief valve.
F. Approval: By AGA as automatic storage water heater for operation at 180 deg F.
G. Controls: Automatic direct immersion thermostat with temperature range adjustable minimum
140 deg F differential, automatic reset high temperature limiting thermostat factory set at 195
deg F, gas pressure regulator, multi-ribbon or tabular burner, 100 percent safety shut-off pilot
and thermocouple, draft proving switch, intermittent electronic ignition monitoring pilot and main
flame, trial for re-ignition for momentary loss of flame, shut down or pilot and main burner in 2-4
seconds after loss of flame, and power venter.
A. Casing: Bronze, rated for 125 psig working pressure, with stainless steel rotor assembly.
B. Impeller: Bronze.
C. Shaft: Alloy steel with integral thrust collar and two oil lubricated bronze sleeve bearings.
B. Impeller: [Cast iron;] [Bronze;] [open non-clog,] [closed,] keyed to [corrosion resistant
alloy steel] [stainless steel] shaft.
C. Support: Cast iron pedestal motor support on steel floor plate with gas tight gaskets.
D. Bearings: [Forced grease] [oil] lubricated bronze sleeve spaced maximum 48 inches and
grease lubricated ball thrust at floor plate.
E. Drive: Flexible coupling to vertical, solid shaft ball bearing electric motor.
F. Sump: Steel cover plate [with steel curb frame for grouting into concrete sump] [on steel
sump basin] with inspection opening and cover, and alarm fittings.
G. Controls (Duplex): Float operated mechanical alternator with float rod, stops, and corrosion
resistant float to alternate operation of pumps, cut-in second pump on rising level or lead pump
failure, [separate pressure switch high level alarm with transformer, alarm bell, and
standpipe,] [and extra set of wired terminals for remote alarm circuit] [and emergency
B. Casing: [Cast iron] [Bronze] pump body and oil filled motor chamber.
C. Impeller: [Cast iron;] [Bronze;] [open non-clog,] [closed,] [stainless steel] [corrosion
resistant alloy steel] shaft.
E. Sump: Fiberglass basin with steel cover plate; [ ] inches diameter, [ ] inches
deep.
F. Accessories: Oil resistant [6 foot] [ ] foot cord and plug [with three-prong
connector] for connection to electric wiring system [including grounding connector].
G. Servicing: slide-away coupling consisting of discharge elbow secure to sump floor, movable
bracket, guide pipe system, lifting chain and chain hooks.
H. Controls: Integral [diaphragm] [mercury switch] type level controls [with separate liquid
level control high level alarm].
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install water heaters in accordance with manufacturer's instructions and to AGA requirements.
B. Coordinate with plumbing piping and related fuel piping, gas venting, and electrical work to
achieve operating system.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Water closets.
2. Urinals.
3. Lavatories.
4. Sinks.
5. Service sinks.
6. Electric water coolers.
7. Eye and face wash fountains.
8. Emergency showers.
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
B. Protect installed fixtures from damage by securing areas and by leaving factory packaging in
place to protect fixtures and prevent use.
1.5 QUALIFICATIONS
1.7 WARRANTY
B. Provide five year manufacturer warranty for electric water cooler and water heater.
Copy and edit paragraph and subparagraphs in this Article for each
type flushometer required.
A. Water Closet:
a. Kohler.
b. American Standard.
c. Eljer.
d. Crane.
Copy and edit paragraph and subparagraphs in this Article for each
type hot-water dispenser required.
Copy and edit paragraph and subparagraphs below for each type
floor-mounting, floor-outlet water closet required.
Copy and edit paragraph and subparagraphs below for each type
wall-mounting, back-outlet urinal required.
A. Urinals:
a. Type: Washout.
b. Strainer or Trapway: Integral cast strainer with integral trap.
c. Design Consumption: .5 gal./flush.
d. Color: White.
e. Trip Mechanism: Hard-wired, electric-sensor actuator with transformer, and true
mechanical override.
f. Supply Spud Size: NPS 3/4.
g. Outlet Size: NPS 1-1/2.
h. Carrier: Combination carrier designed for required mounting height of wall-
mounting, urinal fixture. Include single or double, vertical or horizontal, hub-and-
spigot or hubless waste fitting as required for piping.
Copy and edit paragraph and subparagraphs below for each type
wall-mounting, bottom-outlet urinal required.
Copy and edit paragraph and subparagraphs below for each type
wall-mounting, back-outlet dry urinal required.
2.3 LAVATORIES
Copy and edit paragraph and subparagraphs below for each type
wall-mounting lavatory required.
A. Lavatories:
Copy and edit paragraph and subparagraphs below for each type
counter-mounting lavatory required.
a. Type: Undercounter.
b. Oval Lavatory Size: 15 by 12 inches.
c. Strainer or Trapway: Integral cast strainer with integral trap.
d. Design Consumption: .5 gal./flush.
e. Color: White.
f. Trip Mechanism: Hard-wired, electric-sensor actuator with transformer, and true
mechanical override.
g. Supply Spud Size: NPS 3/4.
h. Outlet Size: NPS 1-1/2.
i. Drain: Grid.
A. Wall Mounted Combination Units: Plumbed, accessible, wall-mounted type with eye/face wash
and drench hose equipment.
1. Available Products:
a. Bradley Corporation.
b. Chicago Faucet Co.
c. Encon Safety Products.
d. Guardian Equipment Co.
e. Haws Corporation.
f. Lab Safety Supply, Inc.
g. Speakman Co.
4. Eye/Face Wash Equipment: With capacity to deliver potable water at rate not less than
3.0 gpm for at least 15 minutes.
5. Hand-Held Drench Hose: With capacity to deliver potable water at rate not less than 3.0
gpm for at least 15 minutes.
1. Available Products:
4. Eye/Face Wash Equipment: With capacity to deliver potable water at rate not less than
3.0 gpm for at least 15 minutes.
5. Hand-Held Drench Hose: With capacity to deliver potable water at rate not less than 3.0
gpm for at least 15 minutes.
Caution: Sinks in this Article are not suitable for food preparation
or for use as scullery sinks.
Copy and edit paragraph and subparagraphs below for each type
counter-mounting commercial sink required.
Copy and edit paragraph and subparagraphs below for each type
freestanding, commercial sink required.
A. Commercial Sinks:
Copy and edit paragraph and subparagraphs below for each type
handwash sink required. Delete if handwash sinks are specified in
Division 11.
a. Advance Tabco.
b. AERO Manufacturing, Inc.
c. Amtekco Industries, Inc.
d. Elkay Manufacturing Co.
e. Just Manufacturing Company.
f. Marlo Manufacturing.
a. Type: Basin with radius corners, back for faucet, and support brackets.
b. Size; Approximately 17 by 16 by 5 inches.
c. Faucet: Back-mounting, chrome-plated, solid-brass, gooseneck type with
electronic sensor with AC adaptor.
d. Supplies: NPS 1/2 chrome-plated copper with stops.
e. Skirt: Stainless steel pedestal skirt.
f. Drain: Grid.
g. Drain Piping: NPS 1-1/2 chrome-plated, cast-brass P-trap; 0.045-inch thick tubular
brass waste to wall; and wall escutcheon.
Copy and edit paragraph and subparagraphs below for each type
kitchen sink required.
c. Sink Faucet: Deck mount, single lever, chrome plated, 8 inch swing spout, ABA
compliant faucet.
d. Supplies: NPS 1/2 chrome-plated copper with stops.
e. Drain Piping: NPS 1-1/2 chrome-plated, cast-brass P-trap; 0.045-inch thick tubular
brass waste to wall; and wall escutcheon(s).
Copy and edit paragraph and subparagraphs in this Article for each
type service basin required.
A. Service Sinks:
a. Size: 24 by 24 inches.
b. Height: 10 inches.
Copy and edit paragraph and subparagraphs in this Article for each
type Government-furnished fixture required.
1. Description: Self-contained, Dual, wall hung, electric refrigerated, Barrier free, stainless
steel basin, ABA compliant, with pre filter, and anti-microbial bubbler and electric
refrigerated cooler.
2. Manufacturers: Subject to compliance with requirements, provide products by one of the
following:
a. Elkay.
b. Haws.
c. Oasis.
d. Halsey Taylor.
PART 3 - EXECUTION
3.1 EXAMINATION
B. Verify that walls and floor finishes are prepared and ready for installation of fixtures.
D. Confirm that millwork is constructed with adequate provision for the installation of counter top
lavatories and sinks.
3.2 PREPARATION
A. Rough-in fixture piping connections in accordance with minimum sizes indicated in fixture
rough-in schedule for particular fixtures.
3.3 INSTALLATION
A. Install each fixture with trap, easily removable for servicing and cleaning.
B. Provide chrome plated rigid or flexible supplies to fixtures with loose key stops, reducers, and
escutcheons.
D. Install and secure fixtures in place with wall carriers and bolts.
E. Seal fixtures to wall and floor surfaces with sealant as specified in Division 07 Section Joint
Sealants, color to match fixture.
F. Solidly attach water closets to floor with lag screws. Lead flashing is not intended hold fixture
in place.
A. Review millwork Shop Drawings. Confirm location and size of fixtures and openings before
rough-in and installation.
B. Adjust stops or valves for intended water flow rate to fixtures without splashing, noise, or
overflow.
3.6 CLEANING
END OF SECTION
GENERAL
1.01 DeCA will provide the latest version of this Specification Section at the predesign conference.
1.02 DeCA maintains lists of existing equipment in commissaries at Ft. Lee. Obtain these lists and
include them in this Section.
END OF SECTION
June 2011 23 01 00 1
SECTION 23 01 00
MAINTENANCE AND REPAIR FOR HVAC AND REFRIGERATION
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Scope of Work:
A. Pre Performance Inspection: Within 10 days after Contract award, conduct a visual inspection
of the existing Commissary refrigeration and HVAC equipment to be maintained under this
Section. Within 7 days after the inspection, provide a letter to the Contracting Officer.
B. Mechanic Experience: The refrigeration mechanic shall have at least 5 years of journeyman
refrigeration experience in the field of commercial supermarket refrigeration and HVAC that is
equal to the type and complexity to the systems indicated in this contract. On every occasion
where the Contractor performs services at least one qualified mechanic shall be sent to the job
site.
1.4 DEFINITIONS
B. New Equipment: New equipment installed under the requirements of another Specification
Section of this Construction Contract. (Includes associated controls, piping, and power wiring
between system components and back to power distribution panels).
D. Emergency: Events which are emergencies and require an emergency response and repair:
1. When a refrigerated display case or a conditioned room is not within the temperature
limits shown in Technical Exhibit #2 for a period of 2 hours.
2. When electrical power outages occur, that upon restoration of the electrical power,
deficient temperatures occur as a result of equipment failing to re-start and commissary
personnel are unable to re-start the refrigeration equipment.
3. When the Refrigeration Alarm System (RMCS) becomes inoperable.
A. All parts, materials and equipment provided under this contract shall be new. Replacement
parts, furnished by others than the original manufacturer, may be used only if the parts are
equal to or better than the original and has been approved by the Contracting Officer or
Governments Designated Inspector. Remanufactured compressors may be used, provided the
compressors are furnished by a manufacturer that is authorized and approved by the original
refrigeration equipment manufacturer and the Contractor has obtained written approval from the
Contracting Officer.
A. Parts for replacement requiring special order due to non-availability locally relieves the
Contractor for the 24 hour requirements. The Contractor shall forward written justification for
approval by the Contracting Officer. The written justification shall include the non-available
parts that are required, the expected delivery date, the means of shipment, and the anticipated
completion date. The Contractor shall make every effort to expedite the purchase and delivery
of such parts by using special means of shipment.
PART 3 - EXECUTION
A. Pre Performance Inspection: Contractors shall perform inspection within 14 days of arriving on
site. Contractors will assume responsibilities for Emergency Response, Emergency Repairs
and Preventative Maintenance at the time the inspection report is submitted to the Contracting
Officer. Inspection shall include the following as a minimum:
B. Emergency Response: Provide emergency response to all emergency calls from the
Commissary requesting emergency repair of new or existing refrigeration or HVAC equipment.
(See definition of emergency, this Section.)
C. Emergency Repair: Provide Emergency Repair of existing HVAC and refrigeration equipment.
Where parts or refrigerant are required, see paragraph titled, "Contractor Furnished, Parts and
Labor and Refrigerant and Items."
1. Emergency Repair Time Limitation: Equipment shall be repaired within 24 hours after the
Contractor or their representative receives the request for emergency repairs.
a. Failure to Comply: If the Contractor does not repair the equipment to proper
operation within 24 hours of a request for emergency repairs, then the government
reserves the right to arrange for repairs by other means and to pay for these
repairs, by deduction from the contracted amount for this Construction Contract.
D. Preventative Maintenance (PM): Provide PM on existing and new HVAC and refrigeration
equipment. During PM conduct all tests and make coordinate repairs and adjustments
necessary to keep all systems operating properly. Where repairs and parts are required, see
paragraph titled, "Contractor Furnished, Parts and Labor and Refrigerant and Items."
1. Minimum PM Requirements for Initial PM, Periodic PM, and Final PM: Insure that the
following work is accomplished (where repairs and parts are required, see paragraph
titled, "Contractor furnished, Parts and Labor and Refrigerant and Items"):
a. Air Filter Change: Each time filters are changed; date each and every filter being
installed in ink, indicating the day, which the filter was installed.
b. Refrigerant receivers levels are brought to a minimum of 30 percent with heat
reclaim on.
c. All HVAC equipment including boilers are ran to verify automatic controls and
equipment operation.
d. Sales Area Dry bulb and RH sensor is calibrated and recorded for the PM report.
e. All compressor rooms cleaned.
f. All refrigerated display cases and walk-ins are adjusted to maintain Technical
Exhibit #2 temperatures and manufacturer specified defrosts.
g. All display case anti sweat heaters and their controllers are working.
h. All display case and storage/processing room lights are working.
i. All missing or loose display case trim or kick panels are installed.
j. All display case and refrigerated room door gaskets are repaired or replaced.
k. Parts and Labor and Refrigerant: Where repairs and parts or refrigerant are
required to complete PM, see breakout of responsibility in paragraph titled,
"Contractor Furnished, Parts and Labor and Refrigerant and Items."
l. Inspection Report: Within 10 days after PM is conducted, provide a PM inspection
report to the Contracting Officer. In the letter, specifically identify any item, which
was not in proper working condition upon completion of PM.
A. Existing Equipment: Provide items and services indicated below to accomplish PM and
Emergency Repair on existing equipment.
B. New Equipment: Provide items and services indicated below to accomplish PM and emergency
repair on new equipment.
C. Interconnected New and Existing Equipment: (Example: when an air conditioning condenser,
but not the compressor, is replaced under another Specification Section.) Provide items and
services indicated below to accomplish PM and emergency repair on interconnected new and
existing equipment.
A. Reimbursement for Parts/Equipment: The Government shall reimburse for individual parts or
equipment, which exceeds $500.00. The established cost of parts shall be at actual cost
invoiced to the Contractor including cash, trade discounts or rebates. The Contractor shall
obtain written approval from the Contracting Officer prior to replacing a part or piece of
refrigeration or HVAC equipment costing $500.00 or more. The Contractor shall provide written
request indicating the work to be done, the parts to be replaced and the estimated cost prior to
starting the work. Additionally, upon request of the Contracting Officer, the Contractor shall
provide three quotes for the equipment being replaced.
1. Crane Rental: If a crane is used to lift reimbursable parts, then the Government shall
reimburse the rental costs for the crane.
2. Excluded Items: Excluded from reimbursable items are:
a. Equipment/items that are new under other section of this Construction Contract.
b. Refrigerant, refrigerant oil.
c. Labor shall not be reimbursed unless the requirements for Reimbursement for
Labor and Overhead are met.
3.4 SECURITY
A. The Contractor shall be responsible for safeguarding government property which the Contractor
is given access. At the close of each work period, government facilities, equipment, and
materials shall be properly secured. Upon arrival at the Commissary, the Contractor shall
request that the Commissary personnel unlock the doors to the mechanical rooms, thus
allowing the Contractor or his representative access to the refrigeration or HVAC equipment.
The Contractor shall notify the commissary personnel to secure the unlocked doors prior to
departure.
3.6 STORAGE
A. No storage space is available in the Commissary mechanical rooms. The Government is not
responsible for theft or damage to Contractor's property that is stored in the mechanical rooms.
A. The Contractor shall provide a separate service statement upon completion of each Emergency
Service Work Call, and Periodic Preventive Maintenance Visit. The service statement shall list
all material (and amount of refrigerant, system charged, and the like for reimbursement
purposes) and man hours provided, reason for the call, description of work, serial number of
equipment, part repaired or provided, and the names of person(s) doing the work and shall be
signed by the AGP. A copy shall be left with the Commissary Officer or representative signing
the service statement.
A. Prior to the end of the Performance Period for Maintenance and Emergency Repair Service,
provide a letter to the Contracting Officer. Indicate in this letter:
The following listing includes, but not limited to, the major pieces of EXISTING equipment that shall be
maintained under this Contract. The Contractor shall also maintain associated controls, piping, wiring,
etc., associated with these major pieces of equipment.
***Sample list, A/E to obtain updated list for the installation from
DeCA Project Manager.
DISPLAY CASES
UNIT COOLERS
QTY LOCATION
(EA.) Room Name
6 Dairy Storage
8 Frozen Food
8 Carcass Storage
2 Meat Holding
3 Met Cutting
3 Meat Wrapping
3 PrePack Meat Storage
4 Produce Storage
1 Candy Storage
1 Deli Storage
2 Produce Processing
2 Behind Milk Roll-In
SYSTEM QTY.
NO. (EA.) HP (EACH COMPRESSOR)
1 3 7.5
2 3 5; 10; 25
3 3 5; 10; 25
4 3 2 at10; 15
5 3 2 at 10; 15
6 3 10
7 3 5; 10; 20
CONDENSERS
QTY.
(EA.) TYPE/DESCRIPTION
7 Remote air Cooled Condensers
QTY.
(EA.) TYPE/DESCRIPTION
2 Air (Mounted in Air Handling Unit)
QTY.
(EA.) TYPE/DESCRIPTION
1 RMCS
The contractors shall reference the Mechanical and Refrigeration drawings for all new HVAC and
Refrigeration Equipment that shall be maintained under this Contract. The Contractor shall also maintain
associated controls, piping, wiring, etc., associated with these major pieces of equipment.
HEATING
AREA COOLING
Sales and Checkout 72-75F, 52 deg. F. dew 68-71F, **52 deg. F. dew
point* point
*Set controls at 40 percent RH max. Environment is not deficient until 50 percent is reached.
**If the system has night setback, let temperature fall to a minimum of 60 deg F during hours that the
commissary is closed.
***Should the temperature rise above 72 deg F during the winter due to internal load, cooling should not
start until the temperature reaches the temperature requirements for summer.
****Excluding delivery, dry storage and mechanical equipment rooms
END OF SECTION
GENERAL
1.01 Related Sections. See Division 23 Sections 23 90 00 Product Refrigeration Systems and
23 09 16 Refrigeration Monitoring and Control Systems (RMCS).
1.02 New Store Concept:
A. Ensure mechanical systems incorporated into new store compliment and encompass current
marketing strategies resulting in a pleasing, efficient, and energy saving system. Identify
appropriate mechanical systems early in the design to achieve both the desired appearance
and energy savings. Coordinate design concept with CIED prior to commencing design.
B. Current marketing trend eliminates suspended ceiling in Sales Area and renders ceiling
structure visible. This impact on air conditioning systems and other mechanical systems is
immediate. The design Mechanical Engineer shall provide guidance to the design Architect
for appropriate visual appearance of the mechanical systems. Accomplish this by
incorporating spiral ductwork (insulation as required), protecting overhead exposed
refrigeration lines from excessive condensation by applying appropriate insulation (or other
means of catching condensate), and paralleling structural support runs with piping runs.
Also, recent trends to varying lighting levels require the design to properly account for heat
generated on carrying out of the new schemes into the different projects. Incorporate these
and other energy saving initiatives into the construction documents.
C. The sections comprising Division 23 address air conditioning of the various functional areas.
The design Mechanical Engineer shall work closely with CIED during the development of the
construction documents. Constant changes in marketing trends require flexibility in the
designs of the mechanical systems. The attached air conditioning Design Standards Plates,
230500 series provide guidance in the general layout of the air conditioning systems.
Anticipate variations of these layouts as new marketing trends are incorporated into the
different projects.
1.03 Remodel Concept:
A. Incorporate new store concepts during major remodeling of existing facilities. Many will not
apply. The design Mechanical Engineer shall coordinate with the design Architect on those
marketing concepts to include in the construction documents. The same requirements for
new store projects shall apply for remodel projects to the extent feasible. For example,
exposed structure will require spiral ductwork. Installation of a new suspended ceiling will
allow the use of rectangular sheet metal ductwork. Other remodel or addition/alteration
information is in other sections of Division 23. Ensure mechanical systems incorporated into
remodeled store result in an efficient and energy saving system. Identify and provide
appropriate mechanical systems calculations early in design to achieve desired energy
savings.
B. Phasing of work to accomplish the desired changes will be an important consideration to
incorporating the changes. Clearly discuss the effect of the work on the mechanical systems
in the design analysis. Discuss any conflicts or problems with attempting to incorporate the
new marketing concept application. (For example, removing the suspended ceiling will
require additional insulation at the roof deck. Incorporating the new concept of exposed
structure will require extensive roof work.) Clearly discuss the approach to replacing the
existing mechanical systems.
1.04 Applicable Codes:
A. The International Code Council family of codes, current editions, shall govern DeCA
construction. These codes include: International Building code (IBC), International
Mechanical (IMC), and International Energy Conservation Code (IECC), Federal Energy
Reduction Mandates including Executive Order 13423 and Guiding Principles, EISA 2007
June 2011 23 05 00 1
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
(Energy Independence and Security Act of 2007), EPACT 2005 (Energy Policy Act of 2005)
and 10 CFR Part 433.
A. Unified Facilities Criteria (UFC).
1.05 Design Analysis:
1. Provide HVAC load analysis and calculations with all design submittals.
2. Design calculations to verify the HVAC equipment selections.
3. Investigation results of the availability of heat source.
4. Include a computer energy analysis to verify compliance with codes and federal
guidelines.
1.06 System Design:
A. See Section 23 05 00 for general requirements. Comply with the requirements of the Design
Standard Plates as applicable. Provide building [EDIT OUT FOR TROPICS: heating and]
cooling load calculations, [EDIT OUT FOR TROPICS: heating and cooling equipment, duct
sizing calculations by a professional mechanical engineer licensed to practice that discipline
in any one of the states or possessions of the United States, Washington D.C., or Puerto
Rico.
B. Design Conditions:
1. Summer:
SPACE TYPICAL
Sales Area 75 deg F DB; 52 Deg F dew point
Summer and winter
Offices, CISIC Room, Alcove, Rest 15 deg F less than the 50% RH min +/- 10%
Rooms, Locker Rooms and Breakrooms 2-1/2% outside dry bulb
(DB) weather condition
not to exceed 78 deg F
DB or be less than 75
deg FDB
Delivery, dry storage, and Mechanical fan forced ventilation
equipment rooms
2. Winter: [NOT IN TROPICS]
SPACE TYPICAL
Sales Area, CISIC Room, Offices, Rest Rooms, Locker Rooms 70 deg F DB
and Breakrooms
Office, breakroom and administration areas 70 deg F DB
Delivery, Dry Storage and Mechanical Rooms 55 deg F DB
Entry/Exit, Cart Return Vestibules 155 deg F DB, unless
otherwise directed
3. Outside Design Temperatures for the Sales Area: Base on 1% of design temperatures.
Design other areas per applicable standards per Division 01. The number of people for
Sales Area calculations will be based on 55 ft2 per person of net area. Cooling and
heating load profiles shall be provided for the sales area by the Architect/Engineer.
4. Cooling and Heating Load Profiles for Sales Area: Provide.
5. Economizer Cycle: Do not use for Sales Area cooling.
6. No variable air volume systems without prior approval from DeCA CIED.
June 2011 23 05 00 2
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
7. Provide minimal outside make-up air to offset that amount exhausted from the Sales
Area and to provide a slight positive pressure.
8. Design air volumes for the Sales Area:
a. See Design Standard 230500-03 for general layout and diffuser preference.
b. Discharge Air and Return Air: Base on following:
1) 5 L/s/m2 (0.75 CFM/ft2) of Sales Area floor area.
9. Outside air volumes;
a. Sales/Checkout Area : In accord with ASHRAE Standard 62:
.30 cfm per SF x 70% of floor space occupiable x 18/30 = .126 cfm per square foot
assuming that peak occupancy is less than 3 hours duration and average occupancy
is 18 people per 1000 SF as stated above rather than the 30 people per square foot
assumed by ASHRAE. Verify that this is adequate to offset exhaust and create a
slight positive pressure within the building. Peak occupancy is rare and of short
duration.
b. Other areas comply with ASHRAE 62, latest edition.
c. Refrigerant: R410A shall be used in all HVAC systems.
C. Design Review:
1. Provide comprehensive HVAC control design review to insure that the RMCS and
conventional controls are properly integrated, complete, and coordinated.
2. Review to ensure that all Specification Sections and Construction Drawings clearly reflect
all control requirements and specifications.
3. Review to ensure that all Specification Sections and Construction Drawings are
consistent and cohesive in the control requirements that they indicate.
D. HVAC Design Analysis:
1. Provide HVAC load calculations at all design review submittals to include detailed
description of all systems [(new and existing)], proposed changes, and phasing work if
applicable.
2. Include following:
a. Copy of page from Engineering Weather Data showing design temperatures for the
installation.
b. Air Flow ductwork schematic for [new] air handling units.
c. For each AHU provide summary of loads on air conditioning load estimate form.
d. A single page recapitulation of all loads is recommended for evaluation.
e. Detailed psychometric analysis of each AHU system.
f. Psychometric chart of each system identifying air flow conditions.
g. Include AHU/DD schematic with points and conditions with reference to
psychrometric chart.
h. Include in design analysis summary table of all product type selections based on
Efficiency Recommendation Tables from DOE/FEMPs Buying Energy Efficient
Products.
June 2011 23 05 00 3
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
June 2011 23 05 00 4
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
(2) 1D02.
d) Ice Cream:
(1) 1B08.
(2) 1G12.
(3) 1G28 - Use if available for designs with underfloor return ducts.
e) Frozen juice: 1G13.
f) Frozen Food:
(1) 1G06.
(2) 1G07.
(3) 1G10.
(4) 1G27 - Use if available for designs with underfloor return ducts.
(5) 1M06 - Should verify with DeCA that they still want to use this case, I
deleted from specs due to it being open face, multi-deck frozen.
g) Produce:
(1) 1P02.
(2) 1P03.
(3) 1P07.
d. Return Air Volumes (See Design Standard 230500-01and 03):
1) 116 L/s/m (75 CFM/ft):
a) 1B08.
b) 1D01.
c) 1D02.
d) 1G02.
e) 1G10.
f) 1G12.
g) 1G13.
h) 1G27.
i) 1G28.
j) 1M02.
k) 1M04.
l) 1M06.
m) 1M07.
n) 1P02.
o) 1P03.
p) 1P07.
June 2011 23 05 00 5
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
with 2/3 of the total air flow. Provide a second sensible cooling only unit with
an indirect gas fired heating Section handling only return air to serve the
remaining Sales Area. [UNLESS CIEDM DETERMINES OTHERWISE]
3) Sales area cooling/heating and dehumidification (See Design Standard 23 07 83-
01):
a) The dual path DX dehumidification unit with gas fired heating shall be
configured and controlled as shown on Design Standard Plate 23 07 83-01.
b) Sources:
(1) Seasons 4.
(2) Aaon.
(3) Munters.
(4) Desert Aire.
c) Discuss extensive replacement of HVAC systems with CIEDM prior to
continuing with design.
d) Air Conditioning Refrigeration Machines:
(1) Split systems or packaged systems with integral condensing units having
multiple semi-hermetic reciprocating or scroll hermetic compressors and
air-cooled condensers.
(2) Do not exceed eight (8) compressors in any case. Consider requiring
unloaders where partial load conditions exist.
(3) Discuss with CIEDM the rationale for use of other than packaged air
conditioning units.
e) Sales Area Dehumidifier control:
(1) Utilize RMCS (Division 23 Section 23 09 16 Refrigeration Monitoring and
Control Systems (RMCS) for control. Sequence of control is indicated in
Division 23 Section 23 09 16 Refrigeration Monitoring and Control
Systems (RMCS).
(a) Use dual path control schematic on design standard 23 84 16-01.
f) Heat Reclaim System: See Design Standard 23 84 16-01.
(1) General: Heat reclaim in commissary facilities refers to the utilization of
the heat rejected by the display and perishable storage refrigeration to
supplement the Sales Area, Administration Area and Warehouse heating
and the heating of domestic hot water. It will not supplement the store
heating and dehumidification control system as a means of meeting the
overall building energy budget. Provide heat reclaim by equipping the
refrigeration system with a second condenser (heat recovery coil)
located in the facility AHU. Divert compressor discharge gas to heat
reclaim coil as required by the space thermostat. Connect heat reclaim
coil in series with remote condenser. Depending upon the geographic
location, reclaimed heat can provide from 45% to 100% of heating
requirements. Heat reclaim used in conjunction with air conditioning
provides economical reheat for dehumidification control. Heat available
for heat reclaim is proportional to refrigeration load. In cold weather,
refrigeration load can decrease and reduce heat of rejection to 50% of
summer design value.
June 2011 23 05 00 7
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
June 2011 23 05 00 8
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
June 2011 23 05 00 9
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
1) Provide a packaged rooftop HVAC unit or, where local regulations will not permit
or local conditions make outdoor equipment impractical, split system air
conditioning equipment. Provide gas fired or heat pump heating sections as fuel
cost economics or building constraints suggest.
2) Do not provide outside make-up air.
3) Consider following internal heat loads:
a) Equipment: 15,000 to 30,000 BTU/HR.
b) Lights: 2.5 Watts/ft2.
c) Four (4) 4 personnel.
4) Provide ceiling exhaust fan to discharge return air and aroma of baked goods
from bakery work room into the sales area for full size, bake off bakeries only.
5) Provide Type 1 hoods in accord with NFPA 96 (latest edition) and the IMC. All
hoods shall have fire suppression systems in accord with NFPA 96, IFC, and the
IMC. Provide hoods at:
a) Rotisserie oven.
b) Kombi oven.
c) Bakery oven (this hood may be integral. Verify that fire suppression is
provided.)
The Hoods shall be compensating or makeup air type when exhaust air quantity
exceeds 5% of the total circulated air quantity in the Sales Area. Stainless steel
splash panels, if required, shall be furnished under Division 05 Metals.
6) Provide a flue exhaust fan for the oven in accord with manufacturers
instructions.
1. Design to ensure adequate heating will be available to the facility. Clearly identify
operating sequence reset requirements for operation of the heating system when
ambient conditions are at or below 155 deg F with full heat available at 35 deg F.
Provide space heating equipment to heat all portions of the facility. In extreme climates
and only at the direction of DeCA, provide a boiler to supply hot water to all HVAC
equipment handling 800 cfm or more.
June 2011 23 05 00 11
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
June 2011 23 05 00 12
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
June 2011 23 05 00 13
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
c. Base control on separate thermostat for required number of exhaust fans and stage
thermostat set points on outside temperatures.
d. Make fans operate when under slab temperature exceeds 55 deg F.
e. Provide forced ventilation system to produce air movement in the space between the
suspended slab floor at a rate of 0.1 to 0.25 CFM/ft2.
6. Other Storage Room Ventilation (Sensitive Storage, damaged merchandise room, Janitor
Closet, Contractor Storage Room, Main Supply Room and Small Store Room):
a. Provide forced exhaust air ventilation at rate of 2 CFM/ft2 of floor area.
b. Introduce make-up air through vandal proof grilles and exhaust through roof. (See
Design Standard 23 05 00-13 for Sensitive Storage).
c. Control by conventional thermostat, where more than one room is served locate
thermostat in the largest room.
7. Restroom Exhaust (See Design Standards 23 05 00-5, 23 05 00-6 and 23 05 00-7):
a. Provide single exhaust fan to exhaust from both men's and women's restrooms at
rate of 125 CFM per stall.
b. Introduce Make-up air through door grille.
c. Control exhaust fan by room light switch/occupancy sensor except where more than
one room is served by a single fan, the fan shall run continuously.
8. Telephone Sub Hub Rooms:
a. Provide single forced exhaust air ventilation fan [200cfm].
b. Introduce Make-up air from air conditioned space through door grille.
9. Electrical Rooms:
a. Provide single forced exhaust air ventilation fan.
b. Introduce unconditioned make-up air though door grille from unairconditioned space
or outdoor air louver.
c. Control from conventional thermostat.
H. Control of HVAC Units:
1. Utilize RMCS (Division 23 Section 23 09 16 Refrigeration Monitoring and Control
Systems (RMCS) for control of the Sales area, units with cooling capacities greater than
30,000 BTUhr and unit heaters. Sequence of control is indicated in Division 23 Section
23 09 16 Refrigeration Monitoring and Control Systems (RMCS).
2. Utilize Standard programmable wall mounted thermostats with locking cover and night
setback for control of units with cooling capacities less than 30,000 BTU/hr.
a. Indicate sequence of control for these non-RMCS controlled units on construction
drawings or in specifications.
b. Make sequence provide for fan to run continuous during occupied and "demand only"
during unoccupied.
c. Emergency HVAC shut down must be incorporated with RMCS system to enable all
HVAC equipment to be shut down in the event a hazardous airborne substance is
released.
I. Wall Heaters, Vestibule Heaters, Radiant Heaters:
June 2011 23 05 00 14
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
EXECUTION
3.01 Environmental Compliance Responsibilities:
A. General:
1. Detail in specifications contractor's responsibility for compliance with environmental laws,
rules, procedures and guidelines as they apply to construction and maintenance of
commissary facility equipment.
2. Provide all relative EPA documents for compiling of environmental data by contractor to
support project and assure compliance.
3. Detail in specifications the following items:
a. Service Practice Requirements: Observe EPA required service practices that
minimize emissions of ozone-depleting refrigerants.
b. Equipment Certification: Compliance with certification program for recovery and
recycling equipment.
c. Refrigerant Handling Records: Compliance with recording procedures addressing
refrigerant releases during servicing and disposal of air-conditioning and refrigeration
equipment. Include in specifications requirement for recording and submitting to the
Contracting Officer quantity and type of refrigerant added or removed from any air-
June 2011 23 05 00 15
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
June 2011 23 05 00 16
DeCA DESIGN CRITERIA HANDBOOK
23 05 00 COMMON WORK RESULST FOR
HVAC
END OF SECTION
June 2011 23 05 00 17
SECTION 23 05 00
COMMON WORK RESULTS FOR HVAC
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1. Section includes general requirements for heating, ventilating, air conditioning, and
refrigeration.
A. The following publications form a part of this Specification to the extent they are applicable.
1. All work must be performed in accordance with the requirements of current editions of
local, county, state and national codes and regulations including the requirements of the
latest editions of the following:
1. All equipment, apparatus and systems shall be rated, tested, fabricated and/or installed in
accordance with the applicable industry standard mentioned. The following list will serve
to clarify abbreviations that appear in other Sections of this Specification:
A. Contractor shall apply and pay for all permits, inspections, reviews, etc. required by the
authorities having jurisdiction.
1.5 DEFINITIONS
A. Furnish: The term furnish means supply and deliver to the Project Site, ready for unloading,
unpacking, assembly, installation and similar operations.
B. Install: The term install describes operations at the Project Site including the actual unloading,
unpacking, assembly, erecting, placing, anchoring, applying, working to dimension, finishing,
curing, protecting, cleaning, and similar operations.
C. Provide: The term provides means to furnish and install, complete and ready for intended use.
A. See Division 01 Section Quality Control for requirements for Shop Drawings and product data.
C. See applicable Sections to this Division for items requiring Shop Drawings.
A. Materials, the style, make or quality of which is specifically designated, shall be as specified.
B. Contractor shall furnish necessary materials in ample quantities and as frequently as required to
avoid delay in the progress of the Work, and shall so store them as to prevent interference with
other work.
A. All materials or work found to be defective or not in strict conformity with the drawings or
different from requirements of the drawings and specifications or defaced or injured through
negligence of Contractor or his employees, or through action of fire or weather will be rejected
and shall be immediately removed from premises by Contractor and satisfactory materials and
work substituted without delay.
B. All defective work or imperfect work shall be corrected immediately on notice from
Governments Designated Inspector. No previous inspection or certificate on account shall be
held to relieve Contractor from their obligation to furnish sound materials and to perform good
and satisfactory work.
A. Contractor shall confer with other contractors at the site before installing their work to avoid
interferences so that maximum head room and clearances may be maintained. In event that
interferences develop between work of various contractors, Governments Designated
Inspector's decision will be final and no additional compensation will be allowed for changes
required.
B. Particular attention shall be paid to situations where recessed equipment, pipes and lights
occur, or where the work of several trades occurs together above suspended ceilings, in pipe
shafts or in areas where space is limited.
C. All fixtures, equipment, devices, switches, outlets, pumps, etc., shall be positioned to avoid all
interferences with and to assure proper coordination with work of all other trades, cases,
partitions, wall, floor and ceiling patterns, architectural features, etc. All recessed devices,
fixtures, etc., shall be coordinated with all wall, floor and ceiling patterns. Governments
Designated Inspector will reconcile conflicts and adjustments where such adjustments are
warranted.
D. Arrange for pipe spaces, chases, slots, and openings in building structure during progress of
construction, to allow for mechanical installations.
F. Coordinate requirements for access panels and doors for mechanical items requiring access
that are concealed behind finished surfaces. Access panels and doors are specified in Division
08 Section Access Doors and Frames.
A. Contractor shall keep all their respective pipe openings closed by means of plugs or caps to
prevent entrance of foreign matter during construction and cover all fixtures, equipment, and
apparatus as required to protect them against dirt, water, chemical or mechanical damage both
before and after installation. Any such fixtures, equipment or apparatus damaged prior to final
acceptance of the Work shall be restored to its original condition or replaced by Contractor at no
cost to Government.
A. Deliver products to project properly identified with names, model numbers, types, grades,
compliance labels, and similar information needed for distinct identifications; adequately
packaged and protected to prevent damage during shipment, storage and handling.
B. Store equipment and materials at the site, unless off-site storage is authorized in writing.
Protect stored equipment and materials from damage.
A. The layout shown on the Contract Drawings is necessarily diagrammatic but shall be followed
as closely as actual construction and as other work will allow. The dimensions of work as
shown on the Contract Drawings are not as-built dimensions. No measurements shall be
scaled from the drawings and used as definite dimensions for laying out or fitting work in place.
B. The layout of manufactured equipment as shown on the drawings shall be checked and the
exact location shall be determined from the dimensions of equipment shop drawings approved
by the Governments Designated Inspector.
A. Upon completion of the Work, Contractors shall provide the Governments Designated Inspector
with three copies of maintenance manual for all equipment furnished and installed under their
Work. Manuals shall be in substantial 3-ring binders with project name and number inscribed on
face and hinged back. Manual shall include roster of all Government training session
attendees. The manual shall, however, first be approved by the Governments Designated
Inspector.
B. The manual shall include manufacturer's lubricating and operating instructions and parts list and
serial numbers for all operating machinery, including drive information, and motor horsepower,
amperage, and voltage readings on all phases, valve chart, sequence of operation, index
following the order listed in the specifications, warranties in the name of the Installation, and a
list of manufacturers, service firms and subcontractors names and telephone numbers.
C. Training attendance rosters for each training session shall be included in manuals. Roster will
identify training subject, date, attendees name, job title, office symbol, grade/rank, and
telephone number.
D. All switches, controls, and safety devices shall be clearly and permanently marked with
embossed or printed plates as to purpose and operation and shall be tested in the presence of
the Governments Designated Inspector to ensure that he understands their function and
purpose.
E. Upon completion of the Work, Contractors shall put the systems into service. Contractors shall
be entirely responsible for the equipment during all testing operations including the lubricating
and turning on and off of such apparatus.
A. Refer to the Division 01 Section Closeout Procedures for requirements. The following
paragraphs supplement the requirements of Division 01.
B. Mark Drawings to indicate revisions to piping and ductwork, size and location both exterior and
interior; including locations of coils, dampers and other control devices, filters, boxes, and
similar units requiring periodic maintenance or repair; actual equipment locations, dimensioned
for column lines; actual inverts and locations of underground piping; concealed equipment,
dimensioned to column lines; mains and branches of piping systems, with valves and control
devices located and numbered, concealed unions located, and with items requiring
maintenance located (i.e., traps, strainers, expansion compensators, tanks, etc.); Change
Orders; concealed control system devices.
1.15 COMMISSIONING
A. All Mechanical, Plumbing, Controls (Division 23 Section Instrumentation and Control Devices for
HVAC and Division 23 Section Refrigeration Monitoring and Control Systems (RMCS), and TAB
Contractors shall comply with the requirements of Division 01 Section General Commissioning
Requirements and Division 23 Section Commissioning of HVAC.
PART 3 - EXECUTION
3.1 ACCESSIBILITY
A. Install equipment and materials to provide required access for servicing and maintenance.
Coordinate the final location of concealed equipment and devices requiring access with final
location of required access panels and doors. Allow ample space for removal of all parts that
require replacement or servicing.
B. Disconnect, demolish, and remove mechanical systems, equipment, and components indicated
to be removed.
3.3 ROUGH-IN
A. Verify final locations for rough-ins with field measurements and with the requirements of the
actual equipment to be connected.
A. General: sequence, coordinate, and integrate the various elements of mechanical systems,
materials, and equipment. Comply with the following requirements:
A. This Article specifies the cutting and patching of mechanical equipment, components, and
materials to include removal and legal disposal of selected materials, components, and
equipment.
B. Refer to Division 01 Section Quality Control for general requirements for cutting and patching.
C. Refer to Division 26 for requirements for cutting and patching electrical equipment, components,
and materials.
D. Do not endanger or damage installed Work through procedures and processes of cutting and
patching.
E. Arrange for repairs required to restore other work, because of damage caused as a result of
mechanical installations.
F. No additional compensation will be authorized for cutting and patching Work that is necessitated
by ill-timed, defective, or non-conforming installations.
G. Perform cuttings, fittings, and patching of mechanical equipment and materials required to:
H. Provide and maintain temporary partitions or dust barriers adequate to prevent the spread of
dust and dirt to adjacent areas.
A. Refer to the Division 01 Section Closeout Procedures for general requirements for final
cleaning.
B. Refer to Division 23 Section Testing, Adjusting, and Balancing for HVAC for requirements for
cleaning filters, strainers, and mechanical systems prior to final acceptance.
3.7 COMMISSIONING
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable.
1.3 SUBMITTALS
B. Shop Drawings for Field-Installed Motors: Dimensioned Plans, Elevations, Sections, and
Details, including required clearances and service space around equipment. Include the
following:
D. Operation and Maintenance Data: For field-installed motors to be included in operation and
maintenance manuals.
1.4 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacture of electric motors for the intended use, and
their accessories, with minimum three years documented product development, testing, and
manufacturing experience.
B. Protect motors stored on site from weather and moisture by maintaining factory covers and
suitable weather-proof covering. For extended outdoor storage, remove motors from equipment
and store separately.
PART 2 - PRODUCTS
A. Motors Less Than 250 Watts, for Intermittent Service: Equipment manufacturer's standard and
need not conform to these Specifications.
C. Type:
D. Explosion-Proof Motors: UL approved and labeled for hazard classification, with over
temperature protection.
F. Wiring Terminations:
1. Provide terminal lugs to match branch circuit conductor quantities, sizes, and materials
indicated. Enclose terminal lugs in terminal box sized to NFPA 70, threaded for conduit.
2. For fractional horsepower motors where connection is made directly, provide threaded
conduit connection in end frame.
H. All motors shall be designed for the operating conditions and service requirements of the
intended service.
D. Drip-proof Enclosure: Class A (122 deg F temperature rise) insulation, NEMA Service Factor,
prelubricated sleeve or ball bearings.
E. Enclosed Motors: Class A (122deg F temperature rise) insulation, 1.0 Service Factor,
prelubricated ball bearings.
D. Open Drip-proof or Enclosed Air Over Enclosure: Class A (122 deg F temperature rise)
insulation, minimum 1.0 Service Factor, prelubricated sleeve or ball bearings, automatic reset
overload protector.
F. Drip-proof Enclosure: Class A (122 deg F temperature rise) insulation, NEMA Service Factor,
prelubricated sleeve or ball bearings.
G. Enclosed Motors: Class A (122 deg F temperature rise) insulation, 1.0 Service Factor,
prelubricated ball bearings.
C. Power Output, Locked Rotor Torque, Breakdown or Pull Out Torque: NEMA Design B
characteristics.
D. Design, Construction, Testing, and Performance: Conform to NEMA MG 1 for Design B motors.
F. Testing Procedure: In accordance with IEEE 112. Load test motors to determine free from
electrical or mechanical defects in compliance with performance data.
G. Motor Frames: NEMA Standard T-Frames of steel, aluminum, or cast iron with end brackets of
cast iron or aluminum with steel inserts.
H. Thermistor System (Motor Frame Sizes 254T and Larger): Three PTC thermistors imbedded in
motor windings and epoxy encapsulated solid state control relay for wiring into motor starter;
refer to Division 26 Section Motor-Control Centers.
I. Bearings: Grease lubricated anti-friction ball bearings with housings equipped with plugged
provision for relubrication, rated for minimum AFBMA 9, L-10 life of 20,000 hours. Calculate
bearing load with NEMA minimum V-belt pulley with belt centre line at end of NEMA standard
shaft extension. Stamp bearing sizes on nameplate.
K. Part Winding Start: Where indicated, use part of winding to reduce locked rotor starting current
to approximately 60 percent of full winding locked rotor current while providing approximately 50
percent of full winding locked rotor torque.
L. Weatherproof Epoxy Sealed Motors: Epoxy seal windings using vacuum and pressure windings
with rotor and starter surfaces protected with epoxy enamel; bearings double shielded with
waterproof non-washing grease.
M. Nominal Efficiency: As scheduled at full load and rated voltage when tested in accordance with
IEEE 112.
A. Motors Used with Reduced-Inrush Controllers: Match wiring connection requirements for
controller with required motor leads. Provide terminals in motor terminal box, suited to control
method.
B. Motors Used with Variable Frequency Controllers: Ratings, characteristics, and features
coordinated with and approved by controller manufacturer.
1. Designed with critical vibration frequencies outside operating range of controller output.
2. Temperature Rise: Matched to rating for Class B insulation.
3. Insulation: Class H.
4. Thermal Protection: Comply with NEMA MG 1 requirements for thermally protected
motors.
C. Rugged-Duty Motors: Totally enclosed, with 1.25 minimum service factor, greased bearings,
integral condensate drains, and capped relief vents. Windings insulated with nonhygroscopic
material.
D. Source Quality Control: Perform the following tests on each motor according to NEMA MG 1:
PART 3 - EXECUTION
3.1 APPLICATION
A. Single Phase Motors for Shaft Mounted Fans Centrifugal Pumps: Split phase type.
B. Single Phase Motors for Shaft Mounted Fans or Blowers: Permanent split capacitor type.
C. Single Phase Motors for Fans, Pumps, Blowers, Air Compressors: Capacitor start type.
D. Single Phase Motors for Fans, Blowers, Pumps: Capacitor start, capacitor run type.
E. Motors Located in Exterior Locations, Wet Air Streams Downstream Draw Thru Cooling Coils,
Air Cooled Condensers: Totally enclosed type.
B. Install securely on firm foundation. Mount ball bearing motors with shaft in any position.
C. Check line voltage and phase and ensure agreement with nameplate.
Minimum
Minimum Percent
NEMA Percent Power
HP RPM(Syn) Frame Efficiency Factor
Minimum
Minimum Percent
NEMA Percent Power
HP RPM(Syn) Frame Efficiency Factor
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
1.3 SUBMITTALS
B. Product Data:
1. Flexible Pipe Connectors: Indicate maximum temperature and pressure rating, face-to-
face length, live length, hose wall thickness, hose convolutions per foot and per
assembly, fundamental frequency of assembly, braid structure, and total number of wires
in braid.
2. Dimensions and ratings.
3. Design data and selection calculations.
A. Protect equipment from exposure by leaving factory coverings, pipe end protection, and
packaging in place until installation.
PART 2 - PRODUCTS
1. Two piece welded steel with enamel paint, bolted, with spider to fit standard pipe, frame
with four mounting holes, clearance for minimum 1 inch thick insulation, minimum 3 inch
travel.
PART 3 - EXECUTION
3.1 INSTALLATION
C. Install flexible connectors at right angles to displacement. Install one end immediately adjacent
to isolated equipment and anchor other end. Install in horizontal plane unless indicated
otherwise.
D. Rigidly anchor pipe to building structure where necessary. Provide pipe guides so movement is
directed along axis of pipe only. Erect piping such that strain and weight is not on cast
connections or apparatus.
G. Provide victaulic piping with minimum one joint per inch pipe diameter instead of flexible
connector supported by vibration isolation.
A. Install anchors at locations to prevent stresses from exceeding those permitted by ASME B31.9
and to prevent transfer of loading and stresses to connected equipment.
B. Fabricate and install steel anchors by welding steel shapes, plates, and bars to piping and to
structure. Comply with ASME B31.9 and AWS D1.1.
E. Use grout to form flat bearing surfaces for expansion fittings, guides, and anchors installed on
or in concrete.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Flow meters.
2. Pressure gages and pressure gage taps.
3. Thermometers and thermometer wells.
4. Filter gages.
5. Temperature and Pressure (T&P) Stations.
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
1.3 SUBMITTALS
B. Do not install instruments when areas are under construction, except for required rough-in, taps,
supports and test plugs.
A. Do not install instrumentation when areas are under construction, except for required rough-in,
taps, supports and test plugs.
PART 2 - PRODUCTS
A. Calibrated venturi orifice plate or pitot and flanges with valved taps, chart for conversion of
differential pressure readings to flow rate, or annular element flow stations with meter set.
1. Measuring Station: Type 316 stainless steel pitot type flow element with safety shut-off
valves and quick coupling connections, and permanent metal tag indicating design flow
rate, reading for design flow rate, metered fluid, line size, station or location number.
2. Portable Meter Set: Dry single diaphragm type pressure gage with 6 inch dial pointer,
stainless steel wetted metal parts, variable pulsation damper, equalizing valve, two bleed
valves, and master chart for direct conversion of meter readings to flow rate, mounted in
A. Gage: ASME B40.100, UL 393 [UL 404] drawn steel case, phosphor bourdon tube, rotary
brass movement, brass socket, front recalibration adjustment, black scale on white background.
B. Case: Steel with brass bourdon tube or cast aluminum with phosphor bronze bourdon tube.
F. Scale: Psi.
A. Gage Cock:
B. Needle Valve:
1. Brass, 1/4 inch NPT for minimum [150 psig.] [300 psi.]
C. Ball Valve:
D. Pulsation Damper:
2.4 THERMOMETERS
A. Stem Thermometer: ASTM E1, ASME B40.200, adjustable angle, red appearing mercury, lens
front tube, cast aluminum case with enamel finish, cast aluminum adjustable joint with positive
locking device.
B. Dial Thermometer: ASTM E1, stainless steel case, bimetallic helix actuated with silicone fluid
damping, white with black markings and black pointer hermetically sealed lens, stainless steel
stem.
A. Socket: Brass separable sockets for thermometer stems with or without extensions as required,
and with cap and chain, to be mounted in piping systems.
B. Flange: 3 inch outside diameter reversible flange, designed to fasten to sheet metal air ducts,
with brass perforated stem.
1. Pete's Plugs.
C. Test Plug: 1/4 inch or 1/2 inch brass fitting and cap for receiving 1/8 inch outside diameter
pressure or temperature probe with neoprene core for temperatures up to 200 deg F.
D. Test Kit: Carrying case, internally padded and fitted containing one 3-1/2 inch diameter
pressure gage, one gage adapter with 1/8 inch probes, two 1-1/2 inch dial thermometers.
A. 3-1/2 inch diameter dial in metal case, diaphragm actuated, black figures on white background,
front recalibration adjustment, 2 percent of full scale accuracy.
B. Inclined manometer, red liquid on white background with black figures, front recalibration
adjustment, 3 percent of full scale accuracy.
C. Accessories: Static pressure tips with compression fittings for bulkhead mounting, 1/4 inch
diameter tubing.
PART 3 - EXECUTION
3.1 INSTALLATION
B. Install one pressure gage per pump, with taps before strainers and on suction and discharge of
pump; pipe to gage with isolating valves.
C. Install pressure gages with pulsation dampers. Provide gage cock, needle valve or ball valve to
isolate each gage. Extend nipples to allow clearance from insulation.
F. Install Temperature and Pressure Stations in piping adjacent to controls systems thermostat,
transmitter, or sensor sockets.
I. Provide instruments with scale ranges selected according to service with largest appropriate
scale.
J. Install gages and thermometers in locations where they are easily read from normal operating
level. Install vertical to 45 degrees off vertical.
K. Adjust gages and thermometers to final angle, clean windows and lenses, and calibrate to zero.
L. Locate duct mounted thermometers minimum 10 feet downstream of mixing dampers, coils, or
other devices causing air turbulence.
3.2 SCHEDULES
LOCATION
LOCATION
LOCATION
H. Install static pressure gages to measure across filters and filter banks, (inlet to outlet). On
multiple banks, provide manifold and single gage.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications for a part of this Specification to the extent they are applicable.
2.1 ACCESSORIES
A. Hanger Rods: Mild steel threaded both ends, threaded one end, or continuous threaded.
B. Beam clamps shall not be of the set screw type unless they also have a positive means of
securing the clamp against horizontal movement, i.e. horizontal j-bolt extending to the opposite
flange of the beam or joist or similar device.
C. Hanger loads of up to 300 pounds can be applied to the top or bottom chord of a bar joist using
a threaded rod between the chord angles with washer and double nuts above and below the
chord within 6 inches of a panel point. Heavier loads require coordination with the joist
manufacturer.
2.3 INSERTS
A. Inserts: Malleable iron case of galvanized steel shell and expander plug for threaded connection
with lateral adjustment, top slot for reinforcing rods, lugs for attaching to forms; size inserts to
suit threaded hanger rods.
B. Self drilling expansion anchors, powder driven anchors, or other similar devices shall be applied
in accord with their manufacturers published ratings and instructions.
A. Fabrication: Welded 18 gage galvanized steel shell and base, mitered 3 inch cant, variable step
to match roof insulation, 1-1/2 inch thick insulation, factory installed wood nailer, 14 inches
minimum height, higher where noted. Vary height of curbs and rails to compensate for roof
pitch and make top of curb level.
B. For piping penetration curbs, provide a curb cap with tapered neoprene pipe flashing sleeves
and stainless steel drawbands.
C. Construct to meet the wind loading criteria and local seismic design criteria on Structural
Drawings.
2.6 SLEEVES
A. Sleeves for Pipes Through Non-Fire Rated Floors: 18 gage galvanized steel.
B. Sleeves for Pipes Through Non-Fire Rated Beams, Walls, Footings, and Potentially Wet Floors:
Steel pipe or 18 gauge galvanized steel.
C. Sleeves for Pipes Through Fire Rated and Fire Resistive Floors and Walls, and Fire Proofing:
Prefabricated fire rated sleeves including seals, AWL listed.
D. Sleeves for pipes for ducts through foundation walls below grade.
H. Sealant: Acrylic.
A. Concrete housekeeping pads shall comply with Division 03. Concrete pads shall extend 6
inches beyond equipment and be 4 inches high indoors, 6 inches high out of doors on grade.
A. Description: Welded, shop- or field-fabricated equipment support made from structural carbon-
steel shapes.
A. Structural Steel: ASTM A 36/A 36M, carbon-steel plates, shapes, and bars; black and
galvanized.
B. Grout: ASTM C 1107, factory-mixed and -packaged, dry hydraulic-cement, nonshrink and non
metallic grout; suitable for interior and exterior applications.
PART 3 - EXECUTION
3.1 INSTALLATION
1. Support of all equipment, piping, etc. such that it will withstand a force of 5 times its
weight in any direction and 1.5 times its weight downward.
2. Do not attach to roof deck, connect to structural members and span between same with
structural members, Unistrut, etc.
3. Roof mounted equipment curbs and roof mounting rails shall be installed to withstand the
wind and seismic loading required by Division 01 Section Summary of Work.
3.2 INSERTS
B. Provide inserts for suspending hangers from reinforced concrete slabs and sides of reinforced
concrete beams.
C. Provide hooked rod to concrete reinforcement section for inserts carrying pipe over 4 inches.
D. Where concrete slabs form finished ceiling, locate inserts flush with slab surface.
E. Where inserts are omitted, drill through concrete slab from below and provide through-bolt with
recessed square steel plate and nut recessed into and grouted flush with slab.
B. Install hangers to provide minimum 1/2 inch space between finished covering and adjacent
work.
E. Support horizontal cast iron pipe adjacent to each hub, with 5 feet maximum spacing between
hangers.
F. Support vertical piping at every floor. Support vertical cast iron pipe at each floor at hub.
G. Where several pipes can be installed in parallel and at same elevation, provide multiple or
trapeze hangers unless seismic zone dictates individual clevis hangers. Verify seismic zone
with Division 23 Section Vibration and Seismic Controls for HVAC Piping and Equipment.
I. Provide [copper plated hangers and supports for copper piping] [sheet lead packing
between hanger or support and piping].
A. Provide housekeeping pads of concrete, minimum 4 inches thick and extending 6 inches
beyond supported equipment. Refer to Division 03 Section Cast-in-Place Concrete.
B. Provide templates, anchor bolts, and accessories for mounting and anchoring equipment.
C. Construct supports of steel members. Brace and fasten with flanges or plates bolted to
structure.
D. Provide rigid anchors for pipes after vibration isolation components are installed.
3.5 FLASHING
A. Provide flexible flashing and metal counterflashing where piping and ductwork penetrate
weather or waterproofed walls, floors, and roofs.
B. Provide curbs for mechanical roof installations 14 inches minimum high above roofing surface.
Flash and counterflash with sheet metal; seal watertight. Attach counterflashing and
mechanical equipment, and lap base flashing on roof curbs. Flatten and solder joints.
C. Adjust storm collars tight to pipe with bolts; calk around top edge. Use storm collars above roof
jacks. Screw vertical flange section to face of curb.
3.6 SLEEVES
B. Size sleeves large enough to allow for movement due to expansion and contraction. Provide for
continuous insulation wrapping.
D. Where piping or ductwork penetrates floor, ceiling, or wall, close off space between pipe or duct
and adjacent work with stuffing (fire stopping at fire walls) insulation and caulk air tight. Provide
close fitting metal collar or escutcheon covers at both sides of penetration.
A. Fasten curbs to structure and units to curb in such a way as to withstand design wind loading.
END OF SECTION
****See IBC para. 1621 and ASCE 7.02, para 9.6 for applicability of
this section and for exceptions based on seismic design category
and importance factor. The structural engineer shall determine
these values. Include, delete or edit this section as appropriate***
1.1 SUMMARY
A. Section Includes:
Air Conditioning Units Fans (All types) Tanks (All types) Compressor racks
Air Handling Units Comp. Room Units Heat Exchangers Unit Heaters
Condensers Condensing Units Var. Freq. Drives Piping
Water Heaters Cooling Towers Pumps (All types) Ductwork
Rooftop Units Boilers Water Chillers Kitchen Hoods
B. Related Sections:
1.2 INTENT
****See IBC para. 1621 and ASCE 7.02, para 9.6 for exceptions
based on seismic design category and importance factor. The
structural engineer shall determine these values. Include, delete or
edit this section as appropriate***
B. All such systems must be installed in strict accordance with seismic codes, component
manufacturer's and building construction standards. Whenever a conflict occurs between the
manufacturer's or construction standards, the most stringent shall apply.
D. Any variance or non-compliance with these specification requirements shall be corrected by the
Contractor in an approved manner.
E. Seismic restraints shall be designed in accordance with IBC 2009, Chapter 16 and ASCE-7.
E. OSHPD: Office of Statewide Health Planning and Development for the State of California.
A. Vibration Isolators:
1. Provide vibration isolation on motor driven equipment over 0.5 HP (0.35 kW) unless
internal isolation is specified.
2. Provide minimum static deflection of isolators for equipment as scheduled on the
Contract Drawings.
B. Seismic Restraints:
1. Provide seismic restraint for all equipment not listed in exclusions (3.2 below) and on
connected piping, conduit and ductwork.
2. All seismic restraints shall be designed to be adequate to keep mechanical and electrical
building components in place during a seismic or wind event described in Division 01
Section Summary of Work.
3. All floor and roof mounted equipment whether isolated or not shall be anchored, bolted or
welded to the structure. Bolt locations, diameter of inserts, embedment depth and weld
length as shown on the approved submittal Drawings shall be installed as approved.
4. All suspended equipment shall be two or four point independently braced with engineered
cable restraints, installed taut for non-isolated equipment. A minimum of four (4) cables
C. Wind-Restraint Loading:
1.5 SUBMITTALS
B. Shop Drawings: Indicate and locate vibration isolators, with static and dynamic load on each.
Indicate and locate seismic restraints, with load on each.
C. Product Data: Provide schedule of vibration isolator and seismic restraint type with location and
load on each. Provide manufacturers product data for each isolator and restraint.
E. Manufacturer's Certificate: Certify that seismic restraints have been selected and designed by a
licensed professional engineer, licensed to practice in the state where the restraints are being
installed, to meet or exceed specified requirements.
F. Where walls, floors, slabs or supplementary steel work are used for seismic restraint locations,
details of acceptable attachment methods for ducts, conduit and pipe must be included and
approved before the condition is accepted for installation. Restraint manufacturers' submittals
must include spacing, static loads and seismic loads at all attachment and support points.
G. Seismic restraint calculations must be provided for all connections of equipment to the structure.
Calculations must be stamped by a registered professional engineer with at least five years of
seismic design experience, licensed in the state of the job location.
H. Welding certificates.
PART 2 - PRODUCTS
A. Housekeeping pad reinforcement and monolithic pad attachment to the structure details and
design shall be prepared by the restraint vendor if not already indicated on the Drawings.
C. Housekeeping pad anchors shall consist of a ductile iron casting that is tapered and hexagonal,
smaller at its base than at its top. The upper portion shall have holes for rebar to pass through.
The anchor shall be continuously threaded from top to bottom for the attachment of soleplates.
Housekeeping pad anchors shall be attached to the structural slab using a stud wedge anchor.
Housekeeping pad anchors shall be type HPA and stud wedge anchor shall be equal to type
SAS both as manufactured by Mason Industries, Inc or equivalent.
A. Contractor shall supply supplementary support steel for all equipment, piping, ductwork, etc.
including roof mounted equipment, as required or specified. When supplementary support steel
structure is welded, the Contractor shall qualify procedures and personnel according to
AWS D1.1/D1.1M, "Structural Welding Code - Steel."
2.3 ATTACHMENTS
A. Contractor shall supply restraint attachment plates cast into housekeeping pads, concrete
inserts, double sided beam clamps, etc. in accordance with the requirements of the restraint
vendor's calculations.
A. Seismic Cable Restraints shall consist of galvanized steel aircraft cables sized to resist seismic
loads with a minimum safety factor of two and arranged to provide all-directional restraint.
Cables must be pre-stretched to achieve a certified minimum modulus of elasticity. Cable end
connections shall be steel assemblies that swivel to final installation angle and utilize two
clamping bolts to provide proper cable engagement. Cables must not be allowed to bend
across sharp edges. [Cable assemblies shall have an Anchorage Preapproval "R" Number
from OSHPD in the State of California verifying the maximum certified load ratings].
Cable assemblies shall be Type SCB at the ceiling and at the clevis bolt, SCBH between the
hanger rod nut and the clevis or SCBV if clamped to a beam all as manufactured by Mason
Industries, Inc or equivalent.
B. Seismic solid braces shall consist of steel angles or channels to resist seismic loads with a
minimum safety factor of 2 and arranged to provide all directional restraint. Seismic solid brace
end connectors shall be steel assemblies that swivel to the final installation angle and utilize two
through bolts to provide proper attachment. [Seismic solid brace assembly shall have
anchorage preapproval "R" number from OSHPD in the state of California verifying the
maximum certified load ratings]. Solid seismic brace assemblies shall be equal to type SSB
as manufactured by Mason Industries, Inc., or equivalent.
D. Pipe clevis cross bolt braces are required in all restraint locations. They shall be special
purpose preformed channels deep enough to be held in place by bolts passing over the cross
bolt. [Clevis cross braces shall have an Anchorage Preapproval "R" Number from
OSHPD in the State of California]. Clevis cross brace shall be equal to type CCB as
manufactured by Mason Industries, Inc., or equivalent.
E. All-directional seismic snubbers shall consist of interlocking steel members restrained by a one-
piece molded neoprene bushing of bridge bearing neoprene. Bushing shall be replaceable and
a minimum of 1/4 inch thick. Rated loadings shall not exceed 1000 psi. A minimum air gap of
1/8 inch shall be incorporated in the snubber design in all directions before contact is made
between the rigid and resilient surfaces. Snubber end caps shall be removable to allow
inspection of internal clearances. Neoprene bushings shall be rotated to insure no short circuits
exist before systems are activated. [Snubbers shall have an Anchorage Preapproval "R"
Number from OSHPD in the State of California verifying the maximum certified horizontal
and vertical load ratings]. Snubber shall be equal to type Z-1225 as manufactured by Mason
Industries, Inc., or equivalent.
F. All directional seismic snubbers shall consist of interlocking steel members restrained by shock
absorbent rubber materials compounded to bridge bearing specifications. Elastomeric materials
shall be replaceable and a minimum of 3/4 inch thick. Rated loadings shall not exceed 1000
psi. Snubbers shall be manufactured with an air gap between hard and resilient material of not
less than 1/8 inch nor more that 1/4 inch. Snubbers shall be installed with factory set
clearances. The capacity of the seismic snubber at 3/8 inch deflection shall be equal or greater
than the load assigned to the mounting grouping controlled by the snubber multiplied by the
applicable "G" force. Submittals shall include the load deflection curves up to 1/2 inch
deflection in the x, y and z planes. [Snubbers shall have an anchorage preapproval "R"
number from OSHPD in the state of California verifying the maximum certified horizontal
and vertical load ratings]. Snubbers shall be equal to series Z-1011 as manufactured by
Mason Industries, Inc., or equivalent.
G. Stud wedge anchors shall be manufactured from full diameter wire, not from undersized wire
that is "rolled up" to create the thread. The stud anchor shall also have a safety shoulder which
fully supports the wedge ring under load. The stud anchors shall have an evaluation report
number from the I.C.B.O Evaluation Service, Inc. verifying its allowable loads. Drill-in stud
wedge anchors shall be equal to type SAS as manufactured by Mason Industries, Inc., or
equivalent.
H. Female wedge anchors are preferred in floor locations so isolators or equipment can be slid into
place after the anchors are installed. Anchors shall be manufactured from full diameter wire,
and shall have a safety shoulder to fully support the wedge ring under load. Female wedge
anchors shall have an evaluation report number from the I.C.B.O Evaluation Service, Inc.
verifying to its allowable loads. Drill-in female wedge anchors shall be equal to type SAB as
manufactured by Mason Industries, Inc., or equivalent.
***Use this Spec only when required by Section a.6 of ASCE 7.02,
Section 1621 of the IBC, or when wind loading would cause
overturning. The structural engineer shall determine seismic
category and wind loading.
A. Curb mounted rooftop equipment over 150 pounds shall be mounted on spring isolation curbs.
The lower member shall consist of a sheet metal Z section containing adjustable and removable
steel springs that support the upper floating section. The upper frame must provide continuous
support for the equipment and must be captive so as to resiliently resist wind and seismic
forces. All directional neoprene snubber bushings shall be a minimum of 1/4 inch thick. Steel
springs shall be laterally stable and rest on 1/4 inch thick neoprene acoustical pads. Hardware
must be plated and the springs provided with a rust resistant finish. The curbs waterproofing
shall consist of a continuous galvanized flexible counter flashing nailed over the lower curbs
waterproofing and joined at the corners by EPDM bellows. All spring locations shall have
access ports with removable waterproof covers. Lower curbs shall have provision for 2 inches
of insulation. The roof curbs shall be built to seismically contain the rooftop unit and to
withstand local wind loading. See Division 01 Section Summary of Work. The unit must be
solidly fastened to the top floating rail, and the lower Z section anchored to the roof structure.
[Curb shall have anchorage preapproval "R" from OSHPD in the state of California
attesting to the maximum certified horizontal and vertical load ratings.] Curb shall be
equal to type RSC as manufactured by Mason Industries, Inc.
PART 3 - EXECUTION
3.1 INSTALLATION
B. Installation of vibration isolators and seismic restraints must not cause any change of position of
equipment, piping or duct work resulting in stresses or misalignment.
C. Coordinate work with other trades to avoid rigid contact with the building.
D. Overstressing of the building structure must not occur because of overhead support of
equipment. Contractor must submit loads to the structural engineer of record for approval.
Generally bracing may occur from:
E. Cable restraints shall be installed slightly slack to avoid short circuiting the isolated suspended
equipment, piping or conduit.
F. Cable assemblies are installed taut on non-isolated systems Seismic solid braces may be used
in place of cables on rigidly attached systems only.
G. At locations where cable restraints are located, the support rods must be braced when
necessary to accept compressive loads with braces.
I. Equipment 400 lbs. and less mounted 4 feet or less above floor level is excepted.
1. Seismically restrain all piping listed as a, b or c below. Use cables if isolated. Rigid
restraints may be used on unisolated piping.
a. Fuel oil piping, gas piping, medical gas piping, and compressed air piping that is 1
inch I.D or larger.
b. Piping located in boiler rooms, mechanical equipment rooms, and refrigeration
equipment rooms that is 1-1/4 inch I.D. and larger.
c. All other piping 1-1/2 inch diameter and larger.
2. Transverse piping restraints shall be at 40 foot maximum spacing for all pipe sizes,
except where lesser spacing is required to limit anchorage loads.
3. Longitudinal restraints shall be at 80 foot maximum spacing for all pipe sizes, except
where lesser spacing is required to limit anchorage loads.
4. Where thermal expansion is a consideration, guides and anchors may be used as
transverse and longitudinal restraints provided they have a capacity equal to or greater
than the restraint loads in addition to the loads induced by expansion or contraction.
5. For fuel oil and all gas piping transverse restraints must be at 20 foot maximum and
longitudinal restraints at 40 foot maximum spacing.
6. Transverse restraint for one pipe section may also act as a longitudinal restraint for a
pipe section of the same size connected perpendicular to it if the restraint is installed
within 24 inches of the elbow or TEE or combined stresses are within allowable limits at
longer distances.
7. Hold down clamps must be used to attach pipe to all trapeze members before applying
restraints in a manner similar to clevis supports.
8. Branch lines may not be used to restrain main lines.
9. Cast iron pipe of all types, glass pipe and any other pipes joined with a four band shield
and clamp assembly in Zones 2B, 3 and 4 shall be braced as in T. 2 and 3 above. For
Zones 0, 1 and 2A, 2 band clamps may be used with reduced spacings of 1/2 of those
listed in T.2 and 3.
1. Seismically restrain all duct work with specification 12 or 13 restraints as listed below:
2. Transverse restraints shall occur at 30 foot intervals or at both ends of the duct run if less
than the specified interval. Transverse restraints shall be installed at each duct turn and
at each end of a duct run.
3. Longitudinal restraints shall occur at 60 foot intervals with at least one restraint per duct
run. Transverse restraints for one duct section may also act as a longitudinal restraint for
1. All electrical conduit and wire 5 lbs/ft. and larger shall be restrained seismic cable
restraints or seismic solid brace restraints.
2. All electrical bus ducts, cable trays and ladder trays shall be restrained with seismic cable
restraints or seismic solid brace restraints.
3. Transverse restraints shall occur at 30 foot intervals or both ends if the electrical run is
less than the specified interval. Transverse restraints shall be installed at each electrical
services turn and at each end of the electric run.
4. Longitudinal restraints shall occur at 60 foot intervals with at least one restraint per
electric run. Transverse restraints for one electric section may also act as a longitudinal
restraint for a duct for an electric section connected perpendicular to it if the restraints are
installed within 4 feet of the intersection of the electric run and if the restraints are sized
for the larger electric run.
5. All rigid floor mounted equipment must have a resilient media between the equipment
mounting hole and the anchor bolt. Anchor bolts shall be designed for specified seismic
forces.
6. Wall mounted panels shall be mounted with resilient bushings and anchor bolts. Floor
mounted panels shall be mounted resilient bushings.
M. All mechanical equipment shall be vibration isolated and seismically restrained as per the
schedules on the Drawings.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Nameplates.
2. Tags.
3. Stencils.
4. Pipe Markers.
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
PART 2 - PRODUCTS
2.1 NAMEPLATES
A. Description: Laminated three-layer plastic with engraved black letters on light contrasting
background color, 4 inch by 1-1/2 inch or larger.
2.2 TAGS
A. Plastic Tags: Laminated three-layer plastic, brass, or aluminum with engraved black letters on
light contrasting background color. Tag size minimum 1-1/2 inch.
A. Plastic Pipe Markers: Factory fabricated, flexible, semi-rigid plastic, preformed to fit around pipe
or pipe covering; minimum information indicating flow direction arrow and identification of fluid
being conveyed.
B. Plastic Tape Pipe Markers: Flexible, vinyl film tape with pressure sensitive adhesive backing
and printed markings.
2.4 STENCILS
B. Stencil Paint: As specified in Division 09 Section Painting and Coating, semi-gloss enamel,
colors and lettering size conforming to ASME A13.1.
1. Factory fabricated, flexible, semi-rigid plastic, preformed to fit around pipe or pipe
covering. Larger sizes may have maximum sheet size with spring fastener.
1. Flexible, vinyl film tape with pressure sensitive adhesive backing and printed markings.
PART 3 - EXECUTION
3.1 PREPARATION
3.2 INSTALLATION
D. Apply stencil painting in accordance with Division 09 Section Painting and Coating.
F. Install plastic tape pipe markers complete around pipe in accordance with manufacturer's
instructions.
G. Identify air handling units, pumps, heat transfer equipment, tanks, and water treatment devices
with plastic nameplates. Small devices, such as in-line pumps, may be identified with tags.
H. Identify control panels and major control components outside panels with plastic nameplates.
K. Identify air terminal units and radiator valves with numbered tags.
M. Identify piping, concealed or exposed, with plastic pipe markers or plastic tape pipe markers.
Delete markers on piping 3/4 inch diameter and smaller. Identify service and flow direction.
Install in clear view and align with axis of piping. Locate identification not to exceed 50 feet on
straight runs including risers and drops, adjacent to each valve and Tee, at each side of
penetration of structure or enclosure, and at each obstruction.
N. Identify ductwork with stenciled painting. Identify with air handling unit identification number and
area served. Locate identification at air handling unit, at each side of penetration of structure or
enclosure, and at each obstruction.
O. Provide ceiling tacks to locate equipment, valves, or dampers above T-bar type panel ceilings.
Locate in corner of panel closest to equipment.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Work:
A. The following publications form a part of this specification to the extent they are applicable:
B. Procedures:
1. Perform total system balance in accordance with AABC National Standards for Field
Measurement and Instrumentation, Total System Balance.
2. Maintain one copy of document on site.
3. Provide certification of calibration of instruments indicating calibration not less than 6
months prior to date of use.
1.3 QUALIFICATIONS
A. Agency: Company specializing in the testing, adjusting, and balancing of systems specified in
this Section with minimum three experience certified by either AABC or NEBB.
1.4 SUBMITTALS
B. LEED Submittal:
C. Qualification Data: Submit, for approval within 30 days after award of Contract, the name of
adjusting and balancing agency and evidence that TAB firm and this Project's TAB team
members meet the qualifications specified.
D. Field Reports: Indicate deficiencies in systems that would prevent proper testing, adjusting, and
balancing of systems and equipment to achieve specified performance.
E. Prior to commencing work, submit report forms or outlines indicating adjusting, balancing, and
equipment data required.
F. Submit draft copies of report for review prior to final acceptance of Project. Provide final copies
for Government's Designated Representative and for inclusion in operating and maintenance
manuals.
1. Provide reports in soft cover, letter size, 3-ring binder manuals, complete with index page
and indexing tabs, with cover identification at front and side. Include set of reduced
Drawings with air outlets and equipment identified to correspond with data sheets, and
indicating thermostat locations.
2. Test Reports: Indicate data on AABC National Standards for Total System Balance
forms containing information indicated in Schedules.
3. Submit technician's field notes with the preliminary report.
A. Perform total system balance in accordance with AABC National Standards for Field
Measurement and Instrumentation, Total System Balance.
B. Certification of TAB Reports: Certify TAB field data reports. This certification includes the
following:
1. Review field data reports to validate accuracy of data and to prepare certified TAB
reports.
2. Certify that TAB team complied with approved TAB plan and the procedures specified
and referenced in this Specification.
C. TAB Report Forms: Use standard forms from NEBB's "Procedural Standards for Testing,
Adjusting, and Balancing of Environmental Systems." Or from SMACNA's "HVAC Systems -
Testing, Adjusting, and Balancing."
E. Provide certification of calibration of instruments indicating calibration not less than 6 months
prior to date of use.
1.6 QUALIFICATIONS
A. Agency: Company specializing in the testing, adjusting, and balancing of systems specified in
this Section with minimum three years documented experience certified by either AABC or
NEBB.
B. Perform Work under supervision of NEBB Certified Testing, Balancing and Adjusting
Supervisor.
1.7 SEQUENCING
A. Sequence work to commence after leakage and pressure tests on air and water distribution
systems have been satisfactorily completed and before Substantial Completion of Project.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that systems are complete and operable before commencing work. Ensure the following
conditions:
B. Submit field reports. Report defects and deficiencies noted during performance of services
which prevent system balance.
3.2 PREPARATION
A. Provide instruments required for testing, adjusting, and balancing operations. Make instruments
available to Quality Control Representative to facilitate spot checks during testing.
A. Air Handling Systems: Adjust to within plus or minus 5 percent of design for supply systems and
plus or minus 10 percent of design for return and exhaust systems.
B. Air Outlets and Inlets: Adjust total to within plus 10 percent and minus 5 percent of design to
space. Adjust outlets and inlets in space to within plus or minus 10 percent of design.
3.4 ADJUSTING
B. Permanently mark settings of valves, dampers, and other adjustment devices allowing settings
to be restored. Set and lock memory stops.
C. After adjustment, take measurements to verify balance has not been disrupted or that such
disruption has been rectified.
D. Leave systems in proper working order, replacing belt guards, closing access doors, closing
doors to electrical switch boxes, and restoring thermostats to specified settings.
E. At final inspection, recheck random selections of data recorded in report. Recheck points or
areas as selected and witnessed by the Government.
F. Check and adjust systems approximately six months after final acceptance and submit report.
A. Adjust air handling and distribution systems to provide required or design supply, return, and
exhaust air quantities at site altitude.
B. Make air quantity measurements in ducts by Pitot tube traverse of entire cross sectional area of
duct.
D. Adjust distribution system to obtain uniform space temperatures free from objectionable drafts
and noise.
E. Use volume control devices to regulate air quantities only to extend that adjustments do not
create objectionable air motion or sound levels. Effect volume control by duct internal devices
such as dampers and splitters.
F. Vary total system air quantities by adjustment of fan speeds. Provide drive changes required.
Vary branch air quantities by damper regulation.
G. Provide system schematic with required and actual air quantities recorded at each outlet or
inlet.
H. Measure static air pressure conditions on air supply units, including filter and coil pressure
drops, and total pressure across the fan. Make allowances for 50 percent loading of filters.
I. Adjust outside air automatic dampers, outside air, return air, and exhaust dampers for design
conditions.
J. Measure temperature conditions across outside air, return air, and exhaust dampers to check
leakage.
K. Where modulating dampers are provided, take measurements and balance at extreme
conditions. Balance variable volume systems at maximum air flow rate, full cooling, and at
minimum air flow rate, full heating.
L. Measure building static pressure and adjust supply, return, and exhaust air systems to provide
required relationship between each to maintain approximately 0.05 inches positive static
pressure near the building entries.
B. Use calibrated Venturi tubes, orifices, or other metered fittings and pressure gages to determine
flow rates for system balance. Where flow metering devices are not installed, base flow
balance on temperature difference across various heat transfer elements in the system.
C. Adjust systems to provide specified pressure drops and flows through heat transfer elements
prior to thermal testing. Perform balancing by measurement of temperature differential in
conjunction with air balancing.
D. Effect system balance with automatic control valves fully open to heat transfer elements.
E. Effect adjustment of water distribution systems by means of balancing cocks, valves, and
fittings. Do not use service or shut-off valves for balancing unless indexed for balance point.
F. Where available pump capacity is less than total flow requirements or individual system parts,
full flow in one part may be simulated by temporary restriction of flow to other parts.
A. Report Forms:
1. Title Page:
2. Summary Comments:
***CTA-Comment: If AABC forms are used, then the below will not
be needed:
3. Instrument List:
a. Instrument.
b. Manufacturer.
c. Model number.
d. Serial number.
e. Range.
f. Calibration date.
4. Electric Motors:
a. Manufacturer.
b. Model/frame.
c. HP/BHP.
d. Phase, voltage, amperage; nameplate, actual, no load.
e. RPM.
f. Service factor.
g. Starter size, rating, heater elements.
h. Sheave make/size/bore.
5. V-Belt Drive:
a. Identification/location.
b. Required driven RPM.
6. Pump Data:
a. Identification/Number.
b. Manufacturer.
c. Size/model.
d. Impeller.
e. Service.
f. Design flow rate, pressure drop, BHP.
g. Actual flow rate, pressure drop, BHP.
h. Discharge pressure.
i. Suction pressure.
j. Total operating heat pressure.
k. Shut off, discharge and suction pressure.
l. Shut off, total head pressure.
7. Combustion Test:
a. Boiler manufacturer.
b. Model number.
c. Serial number.
d. Firing rate.
e. Overfire draft.
f. Gas meter timing dial size.
g. Gas meter time per revolution.
h. Gas pressure at meter outlet.
i. Gas flow rate.
j. Heat input.
k. Burner manifold gas pressure.
l. Percent carbon monoxide (CO).
m. Percent carbon dioxide (CO2).
n. Percent oxygen (O2).
o. Percent excess air.
p. Flue gas temperature at outlet.
q. Ambient temperature.
r. Net stack temperature.
s. Percent stack loss.
t. Percent combustion efficiency.
u. Heat output.
a. Identification/number.
b. Location.
c. Manufacturer.
d. Model number.
e. Serial number.
f. Entering DB air temperature, design and actual.
g. Leaving DB air temperature, design and actual.
h. Number of compressors.
a. Identification/number.
b. Manufacturer.
c. Capacity.
d. Model number.
e. Serial number.
f. Evaporator entering water temperature, design and actual.
g. Evaporator leaving water temperature, design and actual.
h. Evaporator pressure drop, design and actual.
i. Evaporator water flow rate, design and actual.
j. Condenser entering water temperature, design and actual.
k. Condenser pressure drop, design and actual.
l. Condenser water flow rate, design and actual.
a. Identification/number.
b. Location.
c. Service.
d. Manufacturer.
e. Air flow, design and actual.
f. Entering air DB temperature, design and actual.
g. Entering air WB temperature, design and actual.
h. Leaving air DB temperature, design and actual.
i. Leaving air WB temperature, design and actual.
j. Water flow, design and actual.
k. Water pressure drop, design and actual.
l. Entering water temperature, design and actual.
m. Leaving water temperature, design and actual.
n. Saturated suction temperature, design and actual.
o. Air pressure drop, design and actual.
a. Identification/number.
b. Location.
c. Service.
d. Manufacturer.
e. Air flow, design and actual.
f. Water flow, design and actual.
g. Water pressure drop, design and actual.
h. Entering water temperature, design and actual.
i. Leaving water temperature, design and actual.
j. Entering air temperature, design and actual.
k. Leaving air temperature, design and actual.
l. Air pressure drop, design and actual.
a. Location.
b. Manufacturer.
c. Model number.
d. Serial number.
a. Identification/location.
b. Design air flow.
c. Actual air flow.
d. Design return air flow.
e. Actual return air flow.
f. Design outside air flow.
g. Actual outside air flow.
h. Return air temperature.
i. Outside air temperature.
j. Required mixed air temperature.
k. Actual mixed air temperature.
l. Design outside/return air ratio.
m. Actual outside/return air ratio.
a. Location.
b. Manufacturer.
c. Model number.
d. Serial number.
e. Air flow, specified and actual.
f. Total static pressure (total external), specified and actual.
g. Inlet pressure.
h. Discharge pressure.
i. Sheave Make/Size/Bore.
j. Number of Belts/Make/Size.
k. Fan RPM.
a. System zone/branch.
b. Duct size.
c. Area.
d. Design velocity.
e. Design air flow.
f. Test velocity.
g. Test air flow.
h. Duct static pressure.
i. Air temperature.
j. Air correction factor.
1) Blower.
2) Orifice, tube size.
3) Orifice size.
4) Calibrated.
3.8 DEMONSTRATION
A. Repeat up to 2.5 percent of measurements in the presence of the Division 01 Section General
Commissioning Requirements team.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Ductwork insulation.
2. Duct Liner.
3. Jackets.
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
1.3 SUBMITTALS
a. Product Data for Credit EQ 4.1: For adhesives and sealants, including printed
statement of VOC content.
B. Deliver materials to site in original factory packaging, labeled with manufacturer's identification,
including product density and thickness.
C. Store insulation in original wrapping and protect from weather and construction traffic.
1.5 QUALIFICATIONS
B. Applicator Qualifications: Company specializing in performing the work of this Section with
minimum 3 years experience approved by manufacturer.
PART 2 - PRODUCTS
1. Kraft paper with glass fiber yarn and bonded to aluminized film.
2. Moisture vapor transmission: ASTM E96; 0.02 perm.
3. Secure with pressure sensitive tape.
1. Kraft paper reinforced with glass fiber yarn and bonded to aluminized film, with pressure
sensitive rubber based adhesive, UL rated and 25/20 rated.
1. Kraft paper with glass fiber yarn and bonded to aluminized film.
2. Moisture vapor transmission: ASTM E96; 0.04 perm.
3. Secure with pressure sensitive tape.
1. Kraft paper reinforced with glass fiber yarn and bonded to aluminized film, with pressure
sensitive rubber based adhesive.
A. Insulation: ASTM C1071; flexible or rigid, noncombustible blanket with poly vinyl acetate
polymer or acrylic polymer meeting ASTM G21 impregnated surface and edge coat.
B. Adhesive:
C. Liner Fasteners: Galvanized steel, self-adhesive pad, impact applied or welded with integral
press-on head.
1. Kraft paper reinforced with glass fiber yarn and bonded to aluminized film, with pressure
sensitive rubber based adhesive.
2.4 CALCIUM SILICATE (CS) BLOCKS - FOR SURFACES 400 DEG. F. AND HIGHER.
A. Molded rigid sections of hydrous calcium silicate rated at 1200 deg F, 15 pcf, 0.6 Btu-in./hr.-sq.
ft - deg F at 500 deg F. (ASTM C177), ASTM C533, 160 psi compressive strength.
1. High density polyethylene with embossed aluminum outer layer and self-adhesive
rubberized asphalt film with release paper. Childers MFM Building Products corp.
Flexclad 400 or equal.
2. Moisture vapor transmission: ASTM E96; 0.02 perm.
C. Mastic:
1. Material: High temperature soluble fiber blanket encapsulated in scrim reinforced foil.
2. Type and Size: Roll 2 inches by 24 inches by 20 LF or 2 inches by 48 inches by 20 LF.
3. Color: Aluminum silver.
4. Weight: 1.33 lb/sq. ft.
5. Surface Burning Characteristics (ASTM E-84):
PART 3 - EXECUTION
3.1 EXAMINATION
B. Verify that ductwork has been tested before applying insulation materials.
C. Verify that surfaces are clean, foreign material removed, and dry.
3.2 INSTALLATION
A. General:
5. Exterior Applications: Provide duct liner in addition to insulation with vapor barrier jacket.
Cover with caulked aluminum jacket with seams located on bottom side of horizontal duct
section.
a. Secure insulation with vapor barrier with wires and seal jacket joints with vapor
barrier adhesive or tape to match jacket. Pin insulation on sides and bottom with
adhesive attached pins 18 inches o.c.
b. Secure insulation without vapor barrier with staples, tape, or wires.
c. Install without sag on underside of ductwork. Use adhesive or mechanical
fasteners where necessary to prevent sagging. Lift ductwork off trapeze hangers
and insert spacers.
d. Seal vapor barrier penetrations by mechanical fasteners with vapor barrier
adhesive.
e. Stop and point insulation around access doors and damper operators to allow
operation without disturbing wrapping.
DUCTWORK THICKNESS
Inch
Combustion Air Duct 1.5
Outside Air Intake Ducts 2
Mixed air Plenums 1.5
Ventilation Equipment Casings Factory Pre-insulated
Supply Ducts 1.5 covering on round, rectangular or flat oval
ducts.
Other Ducts and Plenums As noted on the Drawings.
Rooftop HVAC Units 8 inches - 3 lbs density rigid insulation inside the
roof curb as detailed on the Drawings.
1. Calcium silicate: Install in 2 layers, with joints tightly butted and staggered. Secure with
No. 16 gauge stainless steel wire on square or rectangular surfaces - 1/2-inch by 0.015
galvanized steel bands on 12 inches maximum centers on cylindrical areas. Where
required, provide studs, clips or angles as anchors for wire and bands. Secure insulation
with circumferential steel straps.
2. Finish: 1 in. wire mesh with 1/4-inch thick Keene Super-Powerhouse Finishing Cement
and fiberglass cloth jacket. Reinforce all corners with corner bead.
3. Taper insulation to nameplates, cleanouts, manholes, etc. Leave nameplates exposed.
4. Insulate kitchen hood exhaust ducts with 2 inches of calcium silicate.
1. [Secure insulation with full coverage of adhesive and seal "butter" insulation joints
with vapor barrier adhesive. Pin insulation on sides and bottom with adhesive
attached pins 18 inches oc. Trim pins flush with insulation before applying vapor
barrier jacket.]
2. Secure insulation without staples, tape, or wires.
3. Lift ductwork off trapeze hangers and install insulation and vapor barrier continuously
past hanger.
4. Stop and point insulation around access doors and damper operators to allow operation
without disturbing wrapping.
5. Apply self adhesive vapor barrier jacket continuously overlapping joints 3 inches. Lap
vapor barrier 3 inches minimum onto hangers, bare metal where reinforcing is to be
covered.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Piping insulation.
2. Jackets and accessories.
B. Related Sections:
A. Materials: Flame spread/smoke developed rating of 25/50 or less in accordance with NFPA 255
and UL 723.
B. All materials and insulating values shall comply with the International Energy Conservation
Code.
A. The following publications form a part of this specification to the extent they are applicable:
1.4 SUBMITTALS
a. Product Data for Credit EQ 4.1: For adhesives and sealants, documentation
including printed statement of VOC content and chemical components.
B. Deliver materials to site in original factory packaging, labeled with manufacturer's identification,
including product density and thickness.
C. Store insulation in original wrapping and protect from weather and construction traffic.
F. Maintain temperature during and after installation for minimum period of 24 hours.
1.6 QUALIFICATIONS
A. Applicator: Company specializing in performing the work of this section with minimum three
years experience.
PART 2 - PRODUCTS
A. Insulation:
1. ASTM C921, white kraft paper with glass fiber yarn, bonded to aluminized film.
2. Moisture Vapor Transmission: ASTM E96; 0.02 perm-inches.
C. Fitting Covers:
2. Jacket: ASTM D1784, One piece molded type fitting covers and sheet material, off-white
color.
D. Tie Wire:
1. 16-gauge soft annealed stainless steel with twisted ends on maximum 12 inch centers.
B. Jacket:
1. White all serviceable jacket with evaporation holes, cap seal joints and butt strips, no
staples.
2. Permeance: 0.4 perms maximum.
2.4 ADHESIVES
A. Aluminum Jacket: ASTM B 209, 3003 Alloy, H-14 temper, roll stock ready for shop or field
cutting and forming to indicated sizes.
1. Finish and Thickness: Smooth finish, 0.016-inchthick for interior applications and 0.020-
inch thick for exterior applications.
2. Moisture Barrier for Indoor Applications: 1 milthick, heat-bonded polyethylene and kraft
paper.
3. Moisture Barrier for Outdoor Applications: 3 mil thick, heat-bonded polyethylene and
kraft paper.
4. Elbows: Preformed 45-degree and 90-degree, short- and long-radius elbows, same
material, finish, and thickness as jacket.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that piping has been tested before applying insulation materials.
B. Verify that surfaces are clean, foreign material removed, and dry.
3.2 INSTALLATION
A. General:
B. Installation: Glass fiber insulated pipes conveying fluids below ambient temperature:
C. Installation: Hot piping conveying fluids 140 deg F or less, insulate flanges and unions at
equipment completely. Bevel and seal ends of insulation.
1. For hot piping conveying fluids over 140 deg F, insulate flanges and unions at equipment.
2. Glass fiber insulated pipes conveying fluids above ambient temperature:
1. All longitudinal and butt joints shall be fully glued and sealed.
1. Install in accordance with NAIMA National Insulation Standards and Knauf installation
instructions.
2. Where insulation is indicated to be replaced, remove existing insulation. Allow piping to
warm to above the dew point and to dry thoroughly before applying new insulation.
Coordinate with the Commissary Officer to schedule work for times when the
Commissary is closed.
3. Insulate fittings, joints, and valves with insulation of like material and thickness as
adjoining pipe. Finish with PVC fitting covers. Install wicking material as directed by
manufacturer.
4. Continue insulation through walls, sleeves, pipe hangers, and other pipe penetrations.
Finish at supports, protrusions, and interruptions. At fire separations, refer to Division 07
Section Firestopping.
5. Install jacket with evaporation holes aligned with wicking material at the bottom of the
pipe.
a. Shields: Galvanized steel between pipe hangers or pipe hanger rolls and inserts.
b. Insert location: Between support shield and piping and under the finish jacket.
c. Insert configuration: Minimum 6 inches long, of same thickness and contour as
adjoining insulation; may be factory fabricated.
3.3 TOLERANCE
A. Substituted insulation materials shall provide thermal resistance within 10 percent at normal
conditions, as materials indicated.
Above 140 deg F, below 200 deg F: 4 inch and larger 1.5 inch
Under 4 inch 1.0 inch
B. Heating System:
A. Insulation installed outdoors shall be provided with an aluminum jacket with lock seam
longitudinal joint and stainless steel "Bandit" straps for butted joints as required for a water-tight
installation.
END OF SECTION
***********************************************************
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 DEFINITIONS
1.3 DESCRIPTION
3. Warranty Period:
a. Putting all HVAC equipment and systems into operation and continuing the
operation during each working day of TAB and commissioning, as required.
b. Including cost of sheaves and belts that may be required by TAB.
c. Providing test holes in ducts and plenums where directed by TAB to allow air
measurements and air balancing. Providing an approved plug.
d. Providing temperature and pressure taps according to the Construction
Documents for TAB and commissioning testing.
6. Install a P/T plug at each water and steam sensor which is an input point to the control
system.
7. List and clearly identify on the As-built Drawings the locations of all air-flow stations.
8. Prepare a preliminary schedule for Division 23 pipe and duct system testing, flushing and
cleaning, equipment start-up and TAB start and completion for use by the CA. Update
the schedule as appropriate.
9. Notify the GC when pipe and duct system testing, flushing, cleaning, startup of each
piece of equipment and TAB will occur. Be responsible to notify the GC ahead of time,
when commissioning activities not yet performed or not yet scheduled will delay
construction. Be proactive in seeing that commissioning processes are executed and
that the GCR has the scheduling information needed to efficiently execute the
commissioning process.
10. Refer to Division 01 Section General Commissioning Requirements for specific details on
non-conformance issues relating to prefunctional checklists and tests and for issues
relating to functional performance tests.
11. The training shall consist of a review of the O&M manuals and hands-on training. Hands-
on training shall include start-up, operation in all modes possible, including manual, shut-
down and any emergency procedures and preventative maintenance for all pieces of
equipment. The Mechanical Contractor shall fully explain and demonstrate the operation,
function and overrides of any local packages controls, not controlled by the central
control system. Training shall occur after functional testing is complete, unless approved
otherwise by the Contracting Officer.
1) Controlled system.
2) Point abbreviation.
3) Point description.
4) Display unit.
5) Control point or setpoint (Yes / No).
6) Monitoring point (Yes / No).
3. An updated as-built version of the Control Drawings and sequences of operation shall be
included in the final controls O&M manual submittal.
4. Assist and cooperate with the TAB Contractor in the following manner:
a. Meet with the TAB Contractor prior to beginning TAB and review the TAB plan to
determine the capabilities of the control system toward completing TAB. Provide
the TAB Contractor any unique instruments needed for setting terminal unit boxes
and instruct TAB in their use (handheld control system interface for use around the
building during TAB, etc.).
b. For a given area, have all required prefunctional checklists, calibrations, startup
and selected functional tests of the system completed prior to TAB.
c. Provide a qualified technician to operate the controls to assist the TAB Contractor
in performing TAB, or provide sufficient training for TAB to operate the system
without assistance.
a. Using a skilled technician who is familiar with the installed systems in this building,
execute the functional testing of the controls system. Assist in the functional testing
of all equipment. Provide two-way radios during the testing.
b. Execute all control system trend logs.
6. The Controls Contractor shall prepare a written plan indicating in a step-by-step manner,
the procedures that will be followed to test, checkout and adjust the control system prior
to functional performance testing. At minimum, the plan shall include for each type of
equipment controlled by the automatic controls:
a. System name.
b. List of devices.
c. Step-by-step procedures for testing each controller after installation, including:
d. A copy of the log and field checkout sheets that will document the process. This
log must include a place for initial and final read values during calibration of each
point and clearly indicate when a sensor or controller has "passed" and is
operating within the contract parameters.
e. A description of the instrumentation required for testing.
f. Indicate what tests on what systems should be completed prior to TAB using the
control system for TAB work. Coordinate with the CA and TAB Contractor for this
determination.
7. Provide a signed and dated certification to the GC upon completion of the checkout of
each controlled device, equipment and system prior to functional testing for each piece of
equipment or system, that all system programming is complete as to all respects of the
Contract Documents, except functional testing requirements.
8. Beyond the control points necessary to execute all documented control sequences,
provide monitoring, control and virtual points.
9. List and clearly identify on the As-built duct and Piping Drawings the locations of all
monitoring and control sensors.
10. Provide all test equipment necessary to fulfill specified testing requirements.
D. TAB Contractor: The duties of the TAB Contractor, in addition to those listed in Paragraph A,
above, are:
1. Submit the outline of the TAB plan and approach for each system and component to the
CA, CO, GC and the Controls Contractor six weeks prior to starting the TAB. This plan
shall be developed after the TAB has met with the CC and become familiar with the
control system.
2. The submitted plan shall include:
a. Certification that the TAB Contractor has reviewed the Construction Documents
and the systems with the design engineers and contractors to sufficiently
understand the design intent for each system.
b. An explanation of the intended use of the building control system. The Controls
Contractor shall comment on feasibility of the plan.
c. All field checkout sheets and logs to be used that list each piece of equipment to
be tested, adjusted and balanced with the data cells to be gathered for each.
d. Discussion of what notations and markings will be made on the Duct and Piping
Drawings during the process.
e. Final test report forms to be used.
f. Detailed step-by-step procedures for TAB work for each system and issue:
terminal flow calibration (for each terminal type), diffuser proportioning, branch /
submain proportioning, total flow calculations, rechecking, diversity issues,
expected problems and solutions, etc. Criteria for using air flow straighteners or
relocating flow stations and sensors shall be discussed. Provide the analogous
explanations for the waterside.
g. List of all airflow, water flow, sound level, system capacity and efficiency
measurements to be performed and a description of specific test procedures,
parameters, formulas to be used.
3. The TAB field technicians shall keep a running log of events and issues. Submit hand-
written reports of discrepancies, deficient or uncompleted work by others, contract
interpretation requests and lists of completed tests to the CA, GC and CO at least twice a
week.
4. Communicate in writing to the Controls Contractor all setpoint and parameter changes
made or problems and discrepancies identified during TAB which affect the control
system setup and operation.
5. Provide a draft copy of the TAB report to the CA within two weeks of completion. The
report shall contain a full explanation of the methodology, assumptions and the results in
a clear format with designations of all uncommon abbreviations and column headings.
The report should follow the latest and most rigorous reporting recommendations by
AABC, NEBB or ASHRAE Standard 111.
6. Provide the CA with any updates as a result of A/E review.
7. Provide all test equipment necessary to fulfill specified testing requirements.
3.1 STARTUP
A. The Mechanical and Controls Contractors shall follow the start-up and initial checkout
procedures listed in the Responsibilities list in this Section and in Division 01 Section General
Commissioning Requirements. Division 23 Sections require start-up and complete systems and
sub-systems that are fully functional, meeting the design objectives of the Contract Documents.
The commissioning procedures and functional testing do not relieve or lessen this responsibility
or shift that responsibility partially to the commissioning agent, technical inspector or
Government.
B. Functional testing is intended to begin upon completion of a system. Functional testing may
proceed prior to the completion of systems or sub-systems at the discretion of the CO.
Beginning system testing before full completion does not relieve the Contractor from fully
completing the system, including all prefunctional checklists as soon as possible.
A. The following O&M manual requirements do not replace O&M manual documentation
requirements elsewhere in these Specifications.
B. Division 23 Contractors shall compile and prepare documentation for all commissioned systems
covered in Division 23 and deliver this documentation to the GC for inclusion in the O&M
manuals prior to the training of Government personnel.
C. Special Control System O&M Manual Requirements: In addition to documentation that may be
specified elsewhere, the Controls Contractor shall compile and organize at a minimum the
following data on the control system in labeled 3-ring binders with indexed tabs.
1. Three copies of the controls training manuals in a separate manual from the O&M
manuals.
2. Operation and Maintenance Manuals containing:
a. Specific instructions on how to perform and apply all functions, features, modes,
etc. mentioned in the controls training sections of this specification and other
features of this system. These instructions shall be step-by-step. Indexes and
clear tables of contents shall be included. The detailed technical manual for
programming and customizing control loops and algorithms shall be included.
b. Full as-built set of Control Drawings.
c. Full as-built sequence of operations for each piece of equipment.
d. Full points list: A listing of all rooms shall be provided with the following
information for each room:
1) Floor.
2) Room number.
3) Room name.
4) Air handler unit ID.
5) Reference Drawing number.
6) Air terminal unit tag ID.
7) Heating and/or cooling valve tag ID.
e. Full print out of all schedules and set points after testing and acceptance of the
system.
f. Full as-built print out of software program.
g. Electronic copy on disk of the entire program for this facility.
h. Marking of all system sensors and thermostats on the as-built floor plan and
Mechanical Drawings with their control system designations.
i. Maintenance instructions, including sensor calibration requirements and methods
by sensor type, etc.
j. Control equipment component submittals, parts lists, etc.
k. Warranty requirements.
l. Copies of all checkout tests, other than commissioning tests, and calibrations
performed by the Contractor.
3. The manual shall be organized and subdivided with permanently labeled tabs for each of
the following data in the given order:
a. Sequences of operation.
b. Control Drawings.
c. Points lists.
d. Controller / module data.
e. Thermostats and timers.
f. Sensors and DP switches.
g. Valves and valve actuators.
h. Dampers and damper actuators.
i. Program setups (software program printouts).
4. Field checkout sheets and trend logs should be provided to the GC for inclusion in the
on-site Commissioning filing system.
D. Special TAB Documentation Requirements: The TAB Contractor shall compile and submit the
following with other documentation that may be specified elsewhere in the Specifications.
1. The TAB Contractor shall mark on the Drawings where all traverse and other critical
measurements were taken and cross reference the location in the TAB report.
A. The GC shall be responsible for training coordination and scheduling and ultimately to ensure
that training is completed.
B. The QC shall be responsible for reviewing the content and adequacy of the training of
Government personnel for commissioned equipment or systems. TI will verify compliance.
C. Mechanical and: The Mechanical and Plumbing Contractors shall have the following training
responsibilities for their respective commissioned systems:
1. Provide the TI with a training plan four weeks before the planned training.
2. Provide designated Government personnel with comprehensive orientation and training
in the understanding of the systems and the operation and maintenance of each piece of
commissioned equipment.
9. Hands-on training shall include start-up, operation in all modes possible, including
manual, shut-down and any emergency procedures and preventative maintenance for all
pieces of equipment.
10. Fully explain and demonstrate the operation, function and overrides of any local
packaged controls, not controlled by the central control system.
11. Training shall occur after functional testing is complete, unless approved otherwise by the
Contracting Officer.
12. Minimum Duration of Training: In addition to training hours included in individual Division
23 Sections, provide training on each system according to the following schedule:
SYSTEM HOURS
8
24
Air Handling Supply and Exhaust Systems 24
D. Controls Contractor: The Controls Contractor shall have the following training responsibilities:
1. Provide the CA with a training plan four weeks before the planned training.
a. Training I: Control System. The first training shall consist of 8 hours of actual
training. This training may be held on-site or in the supplier's facility. If held off-
site, the training may occur prior to final completion of the system installation.
Upon completion, each student, using appropriate documentation, should be able
to perform elementary operations and describe general hardware architecture and
functionality of the system.
b. Training II: Building Systems. The second session shall be held on-site for a
period of 24 hours of actual hands-on training after the completion of system
commissioning. The session shall include instruction on:
c. Training III: The third training will be conducted on-site six months after occupancy
and consist of 16 hours of training. The session shall be structured to address
1. TAB shall meet for 8 hours with facility staff after completion of TAB and instruct them on
the following:
a. Go over the final TAB report, explaining the layout and meanings of each data
type.
b. Discuss any outstanding deficient items in control, ducting or design that may
affect the proper delivery of air or water.
c. Identify and discuss any terminal units, duct runs, diffusers, coils, fans and pumps
that are close to or are not meeting their design capacity.
d. Discuss any temporary settings and steps to finalize them for any areas that are
not finished.
e. Other salient information that may be useful for facility operations, relative to TAB.
END OF SECTION
PART 1 - GENERAL
A. Section Includes:
1. Thermostats.
2. Control valves.
3. Dampers.
4. Flow switch.
5. Miscellaneous accessories.
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
1.3 SUBMITTALS
1.4 QUALIFICATIONS
C. Attendees shall be Division 23 Section Refrigeration Monitoring and Control Systems (RMCS)
Sub-contractor, Division 23 Section Instrumentation and Control Devices for HVAC Sub-
contractor, Government's Designated Representative, and General Contractors
Representative.
B. Provide service and maintenance of control system for one year from date of Substantial
Completion.
C. Provide complete service of controls systems, including call backs. Make minimum of 4
complete normal inspections of approximately 42 hours duration in addition to normal service
calls to inspect, calibrate, and adjust controls, and submit written reports.
2.1 THERMOSTATS
B. Thermostats - Programmable:
1. Remote bulb or bimetal rod and tube type, proportioning action with adjustable throttling
range, adjustable setpoint.
2. Scale range: [-10 to 70 deg F] <insert range>.
F. Immersion Thermostat:
1. Remote bulb or bimetallic rod and tube type, proportional action with adjustable setpoint
and adjustable throttling range.
1. Remote bulb or bimetallic rod and tube type, proportional action with adjustable setpoint
in idle of range and adjustable throttling range.
2. Averaging service remote bulb element: [7.5 feet] [20 feet].
A. Globe Pattern:
1. Up to 2 inches: Bronze body, bronze trim, rising stem renewable composition disc,
screwed ends [with backseating capacity repackable under pressure].
2. Over 2 inches: Iron body, bronze trim, rising stem, plug-type disc, flanged ends,
renewable seat and disc.
3. Hydronic Systems:
B. Electronic Operators:
1. Two position valves shall spring return to normal position as indicated on freeze, fire, or
temperature protection.
2. Select operator for full shut off at maximum pump differential pressure.
2.3 DAMPERS
B. Damper Operators:
C. General: Provide smooth proportional control with sufficient power for air velocities 20 percent
greater than maximum design velocity and to provide tight seal against maximum system
pressures. Provide spring return for two position control and for fail safe operation.
D. Electric Operators:
1. Spring return, adjustable stroke motor having oil immersed gear train, with [auxiliary end
switch] [minimum position potentiometer] [and 24 V dc, 24 va transformer].
2. Number: Sufficient to achieve unrestricted movement throughout damper range.
[Provide one damper operator for maximum 36 sq. ft. damper section.]
3. Verify that operators are compatible with Division 23 Section Refrigeration Monitoring and
Control Systems (RMCS).
A. Control heating water supply temperature modulated from at 200 deg F to 140 deg F at 60 deg
F. in accordance with outdoor reset schedule by modulating boiler bypass control valve.
A. Fan [and makeup air fan] shall run when any appliance under hood runs. Provide relays,
wiring, etc. as required.
PART 3 - EXECUTION
A. On room temperatures above 85 deg F open intake damper (if shown) and start exhaust fan.
Obtain power for intake dampers from the circuit provided for the factory furnished motorized
damper in the fan intake. Furnish motorized dampers as specified in Division 23 Section Metal
Ducts. Provide all conduit, wiring, relays, etc. to complete the installation of the controls,
motors, and dampers.
A. Section 23 09 16 Refrigeration Monitoring and Control Systems (RMCS) shall furnish the
controls for these units. Provide wiring, relays, etc. to interface with Section 23 09 16
Refrigeration Monitoring and Control Systems (RMCS) Contact Closures.
A. Mount and wire the thermostat furnished with the unit. Provide control wiring between indoor
and outdoor units.
3.4 GAS FIRED UNIT HEATERS, RADIANT HEATERS, AND [ROOF MOUNTED] [DUCT]
FURNACE
1. D/N - Enable fan to run in Day mode of the air conditioning unit indicated- by Division 23
Section Refrigeration Monitoring and Control Systems (RMCS).
2. Stat - Start fan on temperature rise above 85 deg F - by Division 23 Section
Instrumentation and Control Devices for HVAC.
A. Single temperature electric room thermostat maintains constant space temperature of 68 deg F
by cycling control valve.
B. Single temperature thermostat on return heating water line [from floor mounted cabinet
heaters] de-energizes fan on temperature below 95 deg F.
END OF SECTION
GENERAL
1.01 SCOPE:
A. Non-RMCS controlled devices: On HVAC devices not controlled by the RMCS, provide as
necessary: control power, power wiring, valves, actuators, conduit, wiring, circuit boards,
thermostats, labor, etc, for a complete and operation system.
B. RMCS controlled devices: On HVAC devices controlled by the RMCS, provide all: control
power supply, [valves, boiler reset controls,] power wiring, actuators, conduit, wiring, HVAC
interface boards, etc, as necessary to connect to RMCS dry control contacts as shown on
Design Standard Plates 23 09 16-42 through 46. Make final connection to RMCS dry
contacts. Section 23 09 16 shall provide all temperature sensing probes and condition
monitor wiring and conduit. Section 23 90 00 shall provide heat reclaim valves.
1.02 Related Sections: 23 05 00, 23 09 16.
PRODUCTS
2.01 HVAC control parameters
A. Air conditioning equipment 30,000 BTU/hr capacity and larger shall be controlled by the
RMCS, Section 23 09 16. All other controlled equipment shall have controls as described
herein. These controls shall be specified in Section 23 09 13 or specified with the equipment
with installation and wiring specified in this Section.
B. DX cooling: On air handlers with more than 6 tons DX cooling capacity, provide control of two
stages of cooling and banked evaporator.
C. Chilled water cooling: On air handlers with more than 6 tons Chilled water cooling capacity,
provide control of two control valves in parallel.
D. Heat Reclaim: Heat reclaim valves shall be provided by 23 90 00 contractor.
E. Control parameters
1. Do not provide pneumatic controls.
2. Do not use DDC controls.
3. Use only two position, on-off, controls. Do not use modulating or proportional except in
the case of boiler or cooling tower/evaporative cooler bypass valves.
4. Do not use economizer cycles.
5. Do not use variable volume controls.
EXECUTION
3.01 Carefully coordinate the specification of this Section with Section 23 09 16.
3.02 Require a conference between the HVAC and RMCS subcontractors to coordinate the interface
of their work.
END OF SECTION
June 2011 23 09 13 1
DeCA DESIGN CRITERIA HANDBOOK
23 09 16 REFRIGERATION MONITORING AND CONTROL SYSTEMS (RMCS)
GENERAL
END OF SECTION
June 2011 23 09 16 1
SECTION 23 09 16
REFRIGERATION MONITORING AND CONTROL SYSTEMS (RMCS)
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
***** A/E shall edit section names and numbers as necessary for
design numerical and name consistency.
A. General:
1. Provide a monitoring and control system (RMCS) to monitor and control product
refrigeration and HVAC equipment designated for control by RMCS. Items which shall be
controlled by the RMCS include:
***** A/E shall edit by adding the words existing if control of existing
equipment is required on an ADD/ALTER PROJECT.
***** A/E shall edit and delete reference to items, which are not
indicated for control by RMCS. Also, A/E shall enter the appropriate
drawing numbers at the question marks.
1.3 SUBMITTAL
B. Contractor shall furnish a RMCS construction submittal for review and approval as herein
indicated.
1. Distribution:
B. Laptop Computer: Laptop shall be compatible to communicate with RMCS and shall have the
following minimum features: modem, read/write CD drive, 60MB hard disk.
C. Desktop Computer: Desktop Computer monitor and keyboard with the following minimum
features: R/W CD Drive, 100G Hard disk.
E. Refrigeration Alarm Annunciator: Shall have an audible alarm and reset button.
G. ICU'S: Individual control units (ICUs) shall have the following minimum features:
1. Independent Operation: Each ICU shall operate independent of the other ICUs. If one
ICU is taken out of operation, the other ICUs shall continue normal operation. The ICU
unit shall retain all setpoints during a "power down" or "power up" and shall automatically
reboot and commence normal operation.
2. Memory Storage: System programs shall be stored in EPROM or CMOS memory. If
CMOS memory is provided, the contents of memory shall be maintained for a minimum
of 1 year by battery. The system shall have battery back up for retention of system clock
of at least 1 year.
3. Voltage/Surge Protection: System shall operate from 100V AC to 130V AC 60 HZ power.
Power supply to ICU shall have surge protection which meets the following.
a. EMI/RFI filtering.
b. Meets Government and military specs for fire panel applications.
c. User replaceable fusing.
d. LEDs to indicate protection status, ground presence, ground fault indication, fuse
status.
e. Tested to meet UL 1449 approved.
f. 120 VAC, 20 amp continuous rating.
g. 10 year limited warranty.
h. DITEK Model 120SR or approved equal.
6. Communication: Shall be connected to the data collection unit (DCU) through an RS485
port.
7. Acceptable Manufacturers: Danfoss AK-SC255 (Baltimore, MD) or approved equal.
1. Analog Inputs:
1) The range for the compressor low pressure side shall be 0 psig to 200 psig
with plus or minus 1 psig.
2) The range for the compressor high pressure side shall be 0 psig to 500 psig
with accuracy of plus or minus 5 psig.
1) Shall measure 0 to 1000 parts per million of all refrigerants provided in this
project. Shall operate from 0 deg F to 120 deg F.
2) Shall not require maintenance more often than every 6 months in order to
operate properly.
I. Limit Switches: Provide rotary limit switches with mechanical arm to monitor walk-in freezer
doors.
J. Three (3) Phase KWHR Transducer/CT: Three (3) phase KWHR (pulse) transducer, with
current transformers on building main power. Provided and installed by Division 26 Contractor
(see paragraph 3.2.E). Hawkeye Series H-8050 or approved equal. Veris Industries Inc. 1-800-
354-8556.
A. General: System software shall be furnished, installed, tested, and debugged to provide;
control/functions described herein this Specification Section. Control Variables/Setpoints:
Setpoints shall be remote selectable by user via "laptop computer" on telephone line and
modem. This portion of the software shall be resident on site in the RMCS ICU's. This
software shall be protected from loss during power failure.
B. Software Configuration: System software shall allow user to add/remove: digital outputs/inputs,
analog inputs, schedules and programs. This software may be either transient or resident. If
software is transient, it shall be compatible with an IBM PC and shall allow user to re configure
C. Data Base Features: Data base features of system software shall provide the following
features:
1. Downloading Capability: This database software shall allow downloading of on-site data
base to an offside location via phone line and IBM PC. Data-base shall contain;
setpoints, names, tables, etc.
2. Unattended Phone Line Disconnect Feature: Master controller communication software
shall force the modem to hang up the phone line if no data is transferred for 5 minutes.
Also, when the modem on the RMCS cannot detect a carrier signal for a period of time (8
to 40 seconds), the RMCS software shall make the modem hang up the phone line.
3. Downloading Software: P.C. software on diskette shall be provided which shall allow the
data base to be edited off-site then reloaded via phone line to commissary. This software
shall be user friendly and shall have error checking features. This software shall take
care of all output data formatting and shall be formatted for 80 column output. A copy of
this software shall be provided to HQ DeCA/PMF Lackland AFB TX and HQ DeCA/DOR
Ft. Lee VA along with a letter granting the Government the right to use this software.
D. Phase Loss Protector Features: When a phase loss/unbalance occurs, all RMCS controlled 3
phase loads shall be shutdown until power is restored. Systems shall automatically restart upon
return of all three phases. Monitor power at panel "CP" on dedicated breaker.
E. Alarm Features:
1. Types Of Alarms: RMCS shall provide for the following types of alarms:
a. Alarm (A): When an alarm occurs, the audible buzzer in commissary sounds and
the alarm dial out begins.
b. Alarm Logs (L): These are events that are recorded in the system and do not
produce any dial out or buzzer.
2. Alarm Dial Out Sequence: The RMCS shall execute the following dial out actions upon
each Alarm (A) event:
3. User Selection/Configuration Of Alarm Dial Out Actions: The RMCS software shall
provide the user with the following alarm dial out configuration options:
F. History Logging Features: The RMCS software shall collect data from the ICUs and shall
provide the following features:
1. Alarm History: Log the last ten alerts and last ten alarms.
2. User Configuration: Allow user (via keyboard) to, select items to: log, select logging
interval (seconds or minutes), select number of samples. The items which shall be
logged in this manner shall be all; analog inputs (AI), analog outputs (AO), digital outputs
(DO), digital inputs (DI).
3. Compressor Runtime: The compressor cycles per day and total run time per day shall be
logged for a period of not less than 4 days.
4. Condenser Runtime: The condenser fan cycles per day and total run time per day shall
be logged for a period of not less than 4 days.
5. Refrigeration Runtime: The refrigeration circuits defrost cycles per day and total run time
per day; shall be logged for a period of not less than 4 days.
G. Security/Access Features: Software shall require a password(s) in order to access the system.
Password shall be for user identification and shall not be echoed on printer or terminal. The
system shall be capable of using a password of 4 or more characters. At least four levels of
access shall be provided. One level of access shall be provided to view data/setpoints. One
password will only permit lighting override and lighting schedule changes. The other two levels
shall provide access to change, setpoints and system programs.
H. Compressor Control Features: RMCS control of refrigeration compressors shall incorporate the
following features:
1. User Access: Software shall allow the user to select and adjust all setpoints.
2. Control Strategy: Software shall control the compressors on each multiplex compressor
system by the following method:
I. Subcooler Control Features: The RMCS shall control 2 normally closed liquid line solenoids,
one sized for 25 percent subcooler operation, one sized for 75 percent and both open for 100
percent operation. A temperature sensor shall be mounted on the subcooled liquid outlet to
maintain the subcooled liquid at a temperature of 50 degrees F.
J. Electronic Evaporative Pressure Regulator Valve Control Features. The RMCS shall control the
Electronic Evaporative Pressure Regulator (EEPR) via an interface board which will provide low
voltage power (24VDC) and control to the motor in the EEPR.
1. When all defrost termination Klixons Provided by Case OEM are closed or the RMCS
Coil Sensors reach the RMCS Defrost Termination setpoint, the RMCS shall terminate
defrost and return circuit to normal refrigeration.
a. One stage cooling and [one stage heating.] [2 stage heating for heat pump
units with electric heat.]
b. Night set back.
c. Fractional Horsepower AHU fans shall only operate during heating or cooling
demand. AHU fans (1) horsepower and greater, shall operate continuously during
daytime and on demand at night.
d. Shall have a schedule for user to select on/off hours.
e. Close outdoor air dampers in unoccupied mode.
1. The RMCS shall provide contact closures and wiring to the contactors for the following
lighting functions:
a. Sales Area Lighting: Control the second 1/2 Sales Area (first 1/2 Sales Area
contactor shall be controlled only by the RMCS schedule), and Checkout area.
b. Refrigerated Case lighting and the Sales Area Mass Display, Track, Dairy, and
Produce lighting.
c. All outside lighting.
d. Cancel override.
3. Division 23 Section Refrigeration Monitoring and Control Systems (RMCS) shall program
the system such that:
a. When any of the momentary contact switches is closed for 6 seconds, the
contactor controlled by that switch shall energize the lighting circuit controlled by
that switch for 240 minutes. One of the Sales Area contactors shall open after 235
minutes to provide an indication to the operators that the lights are about to be
turned off so that they may be reset.
b. When the "Cancel" switch is closed for 6 seconds, the contactors shall open and
the control shall revert to the original program.
c. Label all switches with the lighting control function, i.e. "Sales and Checkout
lighting On," "Case lights and supplementary Lighting On," "Outside Lighting On"
and "Cancel All Lighting Control Overrides."
d. Outdoor lighting shall be turned off when the light sensor senses daylight.
N. Condenser Control Features: The RMCS shall provide the following refrigeration condenser
control functions.
A. Guide Lines: The entire system shall be installed in accordance with RMCS manufacturers'
recommendations and the requirements of these specifications. Where the Contract
requirements are in conflict with those of the manufacturer, the more stringent requirement shall
be followed.
B. N.E.C. The entire system shall be installed in accordance with the current National Electric
Code and the requirements of these Specifications.
D. Inspection/Certification of Installation:
A. Individual Control Units (ICU's): ICU's shall be provided for the following equipment.
2. Installation/Testing: ICUs shall be installed and tested at the respective factory of the
compressor system manufacturer or air handler manufacturer.
B. Analog Temperature Sensors: Analog temperature sensors shall be furnished and installed at
the following locations:
C. Analog Pressure Sensors: Analog pressure sensors shall be furnished and installed at the
following locations:
D. Analog Receiver Level Sensors: Furnish and install one sensor in each product refrigeration
multiple compressor receiver.
E. Digital Sensors: Digital inputs shall be furnished and installed to monitor the following electrical
loads:
F. Refrigeration Alarm Annunciator and Computer Terminal: Furnish and install in the Store
Manager's office.
G. Wiring: All RMCS wiring shall as a minimum meet the following requirements.
1. Routing:
2. Wire Size: All field wiring shall be at a minimum #18 AWG stranded wire.
3. Connections: All splices/connections shall be made in junction boxes and shall utilize
either terminal strips or 3M scotch lock crimp connectors.
4. Labeling: Control cables shall be labeled at all junction boxes and at the origination and
termination of each cable. The Cable number/letter indicated on the submittal drawings
shall be specified on this label.
H. Commercial Phone Line: Before the refrigeration system is tested, the Contractor shall have a
commercial (voice grade) telephone line installed for use with the RMCS system. Coordination
for installation of the telephone line is as follows:
1. Installation: Through the Contracting Officer, the Contractor shall coordinate the
installation of the phone line with the base communication office.
2. Transfer of Billing: Upon final acceptance of this system, the Contractor shall notify the
Contracting Officer that the billing for the phone line needs to be transferred to the
Commissary effective 30 days after the date of final acceptance. The Contractor shall
pay all costs on the phone line up until 30 days after the date of final acceptance.
A. Initial Software Setpoints: Initially, the RMCS shall be set to maintain the following setpoints:
3. HVAC Setpoints: The HVAC setpoints controlled by RMCS shall be initially set as follows:
Deg F
Cooling Stage 1 75/73
Cooling Stage 2 76/74
Ht Rec Stage 1 69/70
Ht Rec Stage 2 68/69
Aux Ht Stage 1 66/67
Aux Ht Stage 2 65/66
b. Bakery/Deli Setpoints:
CUTIN/OUT
Deg F
Cooling 75/73 5/5
Heating 69/70 5/5
CUTIN/OUT
Deg F
Cooling 78/76 5/5
Heating 68/70 5/5
d. Exhaust Fans: The Compressor Room exhaust fans shall be set as follows:
***** A/E shall edit as necessary and enter the fan #s.
CUTIN/OUT
Deg F
Ventilation Stage 1 (EF [<#>]) 75/70
Ventilation Stage 2 (EF[<#>]) 80/75
Ventilation Stages 1 & 2 (EF[<#>])75/70
80/75
4. Alarm Setpoints: The RMCS alarm setpoints shall be initially set as follows with alarm
inhibited during defrost:
(ROOMS)
O O
BKBX 45 F/150 A 32 F/120 A 4/45
O O
BKFZ 10 F/150 A -25 F/120 L 3/45/50
O O
PRBX 45 F/150 A 32 F/120 A 3/40
O O
PRPR 70 F/150 A 32 F/120 A 1/70 "&"
DLBX 40OF/150 A 28OF/120 A 3/45
MTBX 40OF/150 A 25OF/120 A 3/45/50
POBX 40OF/150 A 25OF/120 A 3/45/50
HDBX 40OF/150 A 25OF/120 A 3/45/50
MTWR 55OF/120 A 40OF/120 L 1/60 "&"
MTPR 55OF/120 A 40OF/120 L 1/60 "&"
FRZV 40O F/120 A 25O F/120 L 1/60 "&"
FZBX 10OF/150 A -25OF/120 L 3/45/50
DYBX 38OF/120 A 32OF/120 A 4/45
O
CTBX 72 F/180 A 32OF/120 A 1/70 "&"
Sales Temp 78OF/180 L 32OF/120 A 1/70 "&"
Sales DP 55OD/180 L
FZDR OPEN/30 A
Liquid. Level. 10 percent/120 A
PHASE LOSS OFF/05 L
MON PROOF /05 L
MT Suct PR 60PSI/30 A 30PSI/90 A
LT Suct PR 25PSI/30 A OPSI/90 A
HIGH HEAD 270/03 A 125/120 L
Vapor Detectors Alarm on Sensing of Refrigerant vapor levels exceeding a preset value.
NOTES:
A=Alarm
L=Log (Record Only)
*= Per manufacturer's published data
"&"= Defrost between 10PM and 4AM
1. Names: The "Standard RMCS Point Names" shall be used/indicated in the system
software (see list, item #5).
2. Inputs: All analog inputs shall have an identification tag at input sensor/transducer to
identify input. Except for pressure transducers, tags shall be secured with fasteners
Refrigeration
Cases/WIB Abbreviations
Bakery Case BAKE
Dairy Case DYCS
Fish Case FISH
Deli Case DELI
Multi Deck Deli Case MDDI
Single Deck Frozen Food SDFF or FZCS
Frozen Food with Gl Dr FZGD
Ice Cream with Gl Dr ICGD
Meat Case MTCS
Produce Case PRCS
Dairy Box DYBX
Poultry Box POBX
Freezer Vestibule FRZV
Freezer Box FZBX
Bakery Box BKBX
Frozen Baked Box FZBX
Controlled Temp (Candy) CTBX
Meat Cutting Room MTCU
Meat Wrapping Room MTWR
Meat Holding Box HDBX
Produce Box PRBX
Produce Prep PRPR
Deli Box DLBX
Fish Box FIBX
Compressor Systems SYS##X (where ## is the system number and X is the
compressor letter.)
Defrost DEF## .XX (where ## is system numbered XX
designates refr circuit number.)
Air Cooled Condensers ACC##X (where ## is the condenser number and X is
the stage number on the condenser.)
Liquid Line Solenoid LLSV ## (where ## is the refr circuit number).
Names Abbreviations
Main Air Handler AHU ## (where ## is Air Handler 1, 2, etc. the AHU
number)
Cooling Stages Cool# (where # designates the stage number. When
more than one AHU is present, designate as COOL### where
## is for AHU and the 2nd # is for stage.)
Heat Reclaim Stages (HR) HR### (where ## is AHU number and # is the stag
number.)
Auxiliary Duct Heat (AH) AHEH### (electric) AHGH### (gas) AHOH###
(oil) AHSH### (steam) AHWH### (water) (where ##
is AHU number and # is stage number.)
Dehumidification DHUM.## (where ## is the desiccant sys#)
Humidity HUMD## (where ## is the AHU number.)
Dewpoint DEWPT## (where ## is the AHU number.)
Condensing Water Temp COND WTR
Mezzanine Room Temp MEZ TMP
Outside Air Temperature OTSD TMP
Pan Water Temperature PAN WTR
Stock Room Temperature STCK TMP
Store Temperature INSD TMP (when only one zone) INSIDE X (where X
=zone when more than one.)
Supply Air Temperature SP## AIR (where X is AHU number)
Compressor Suction / SYS##ST# or SYS##DT## (where ## is system number
and Discharge Temperature # is compressor letter.)
Oil Pressure Monitor OPMXXX (where ## is system number and # is
compressor letter.)
Refrigerant Level SYSXXLQD (where XX is the system number.)
Chill Water Supply CWSTMP
Chill Water Return CWRTMP
System Suction Pressure SYS##SP (where ## is the system number.)
System Discharge Press SYS##DP (where ## is the SYS number.)
System Condenser Press SYS##CP (where ## is the SYS number.)
A. O & M MANUALS: Contractor shall furnish O&M manuals and information as herein indicated.
1. Distribution:
a. Provide one (1) copy and 3 CD ROM copies to DeCA/ DOFC, 2250 Foulois Ave,
Lackland AFB TX 78236-1039.
b. Provide one (1) copy to HQ DeCA/ENFS Ft. Lee Virginia.
c. Provide three (3) copies to the Contracting Officer (to be forwarded to
Commissary).
B. CADD Files: Provide CADD files (DWG and DXE format) on CD ROM indicating; analog probe
locations, and point to point electrical interface drawings between RMCS connections and other
equipment.
C. Control Task Manual: Provide a booklet attached by chain to each ICU and one attached to the
Desk Top Computer. Each manual shall contain the following:
1. Control Task Description: Provide a written description of each and every control task.
Description shall clearly describe at length, how each relay point is affected by changes
in the input.
2. Wiring Diagram: Provide a half sized As-Built drawing that folds into booklet, indicating
physical location in store of all relays, relay boards, and sensors. Provide one full sized
As-Built with same information and mount on equipment room wall with other As-Built
drawings.
D. Training: The startup technician give the following training sessions each of which shall be:
coordinated with the commissary, scheduled during week days, scheduled at a minimum of 14
days in advance, and coordinated through the Contracting Officer. During these sessions,
Commissary Store Personnel shall be instructed on accessing the RMCS temperatures and
alarms using the laptop computer. Additionally during these sessions, Commissary Personnel
shall be instructed on changing the lighting schedules by means of using the lighting password.
1. First Training Session: A four hour training session (to a minimum of four Commissary
Store Personnel) within 14 days after final acceptance and all RMCS final inspection
punch list items are resolved. This training session should be considered in conjunction
with 3 day commissioning start up visit.
2. Second Training Session: A second four hour training session (to a minimum of four
Commissary Store Personnel) at least 30 days after but no more than 45 days after the
final acceptance.
1. User Video: This video should be tailored to equipment installed on this project and will
explain to commissary management how to determine what causes a refrigeration alarm
1. CD ROM: CD ROM containing backup of all RMCS name, and setpoints for site.
2. Distribution: Mail to DeCA/PMF, Lackland AFB TX, 78236-1039.
H. Spare Parts: The following spare parts shall be provided at least 30 days prior to final
acceptance.
J. Alarm Monitoring and Notification: Manufacturer shall provide a 24 hour a day Alarm monitoring
and notification service during the first 90 days of the warranty after final acceptance. See 3.6
Warranty.
1. General: RMCS shall dial out alarms to a monitoring service using a toll free (1-800)
phone number. Monitoring company shall evaluate all alarms and shall notify designated
3.6 WARRANTY
1. The manufacturer of the RMCS shall guarantee that the RMCS equipment/software, shall
operate and provide specified control without failure for the periods indicated below
beginning on the date of final acceptance.
a. First 90 Days: During the first 90 days of the warranty, the Manufacturer shall
provide 24 hours a day, 7 days per week (including holidays), service to the
Commissary. A technician shall arrive at the Commissary within 2 hours of receipt
of a telephone call for warranty service. All parts and labor shall be provided by
the Manufacturer at no cost to the Government during this period. Additionally,
manufacturer shall provide a 24 hour a day Alarm Monitoring and Notification
service.
b. 91 To 365 Day: During the 91st day through the 365 day of the warranty, the
Manufacturer shall provide free exchange of parts within 24 hours of notification.
Shipping costs shall be paid by the Manufacturer. These parts will be installed by
a Maintenance Contractor whose services are provided for under a separate
Contract. No installation cost shall be paid by the RMCS Manufacturer for
replacement of these parts. Additionally, manufacturer shall provide a 24 hour a
day Alarm Monitoring and Notification service.
c. First Five Years: Additionally, during the 91st day through the first five years of the
warranty, the manufacturer of the RMCS shall provide assistance (via telecon at
no cost to the Government nor Government Contractor) in helping the Government
or Contractor personnel locate any problem with the RMCS system. During this
warranty period, the manufacture of the RMCS shall unconditionally provide
software maintenance at no cost to the Government or Government Contractor.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
2. Valves:
a. Gate valves.
b. Globe or angle valves.
c. Ball valves.
d. Plug valves.
e. Butterfly valves.
f. Check valves.
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
A. Where more than one piping system material is specified, ensure system components are
compatible and joined to ensure the integrity of the system is not jeopardized. Provide
necessary joining fittings. Ensure flanges, union, and couplings for servicing are consistently
provided.
C. Use unions, flanges, and couplings downstream of valves and at equipment or apparatus
connections. Do not use direct welded or threaded connections to valves, equipment or other
apparatus.
D. Use non-conducting dielectric connections whenever jointing dissimilar metals in open systems.
E. Provide pipe hangers and supports in accordance with MSS SP69 unless indicated otherwise.
F. Use gate, ball, or butterfly valves with drip tight rating for shut-off and to isolate equipment, part
of systems, or vertical risers.
G. Use ball or butterfly valves with memory stops for throttling, bypass, or manual flow control
services.
I. Use butterfly and ball valves in heating and chilled water systems interchangeably with gate
valves.
J. Use only butterfly, ball, or balancing valves in chilled and condenser water systems for throttling
and isolation service.
L. Use 3/4 inch ball valves with cap for drains at main shut-off valves, low points of piping, bases
of vertical risers, and at equipment.
Product Data: For each type of valve indicated. Include flow and
pressure drop curves based on manufacturer's testing Retain
paragraph below if procedures for welder certification are retained
in 'Quality Assurance' Article.
A. Field Test Reports: Written reports of tests specified in Part 3 of this Section. Include the
following:
B. LEED Submittal:
1. Product Data for Credit EQ 4.1: For solvent cements and adhesive primers, including
printed statement of VOC content.
1.5 QUALIFICATIONS
B. Provide temporary end caps and closures on piping and fittings. Maintain in place until
installation.
C. Protect piping systems from entry of foreign materials by temporary covers, completing sections
of the work, and isolating parts of completed system.
1. Fittings: ASTM B16.3, malleable iron or ASTM A234, forged steel welding type fittings.
2. Joints: Threaded, or AWS D1.1 welded.
1. Fittings: ASME B16.18, cast brass, or ASME B16.22, solder wrought copper.
2. Tee Connections: Mechanically extracted collars with notched and dimpled branch tube.
3. Joints: Solder, lead free, ASTM B32, 95-5 tin-antimony, or tin and silver, with melting
range 430 to 535 deg F. Braze, AWS A5.8 BCuP silver/phosphorus/copper alloy with
melting range 1190 to 1480 deg F.
1. Fittings: ASME B16.18, cast brass, or ASME B16.22 solder wrought copper.
2. Joints: Solder, lead free, ASTM B32, 95-5 tin-antimony, or tin and silver, with melting
range 430 to 535 deg F.
1. Bronze body, bronze trim, screwed union bonnet, handwheel, inside screw, solid wedge
disc, solder or threaded ends.
1. Iron body, bronze trim, bolted bonnet, rising stem, handwheel, outside screw and yoke,
solid wedge disc with bronze seat rings, flanged ends.
1. Bronze body, bronze trim, screwed bonnet, rising stem and handwheel, inside screw
renewable composition disc and bronze seat, solder or threaded ends.
B. Over 2 Inches:
1. Iron body, bronze trim, bolted bonnet, rising stem, handwheel, outside screw and yoke,
rotating plug-type disc with renewable seat ring and disc, flanged ends.
1. Bronze two piece body, chrome plated bronze ball, teflon seats and stuffing box ring,
lever handle, solder or threaded ends.
A. Body: Cast or ductile iron with resilient replaceable EPDM seat, wafer or lug ends, extended
neck.
1. Bronze body, bronze trim, bronze rotating swing disc, with composition disc, solder or
threaded ends.
B. Over 2 Inches:
1. Iron body, bronze trim, bronze or bronze faced rotating swing disc, renewable disc and
seat, flanged ends.
A. Iron body, bronze trim, split plate, hinged with stainless steel spring, resilient seal bonded to
body, wafer or threaded lug ends.
PART 3 - EXECUTION
3.1 PREPARATION
A. Ream pipe and tube ends. Remove burrs. Bevel plain end ferrous pipe.
D. Keep open ends of pipe free from scale and dirt. Protect open ends with temporary plugs or
caps.
E. After completion, fill, clean, and treat systems. Refer to Division 23 Section Water Treatment
for Closed-Loop Hydronic Systems.
3.2 INSTALLATION
C. Route piping in orderly manner, parallel to building structure, and maintain gradient.
D. Install piping to conserve building space, and not interfere with use of space.
H. Install piping to allow for expansion and contraction without stressing pipe, joints, or connected
equipment. Refer to Division 23 Section Expansion Fittings and Loops for HVAC Piping.
I. Inserts:
1. Install in accordance with Division 23 Section Hangers and Supports for HVAC Piping
and Equipment.
2. Support horizontal piping as scheduled.
3. Install hangers to provide minimum 1/2 inch space between finished covering and
adjacent work.
4. Place hangers within 12 inches of each horizontal elbow.
5. Use hangers with 1-1/2 inch minimum vertical adjustment. Design hangers for pipe
movement without disengagement of supported pipe.
6. Where several pipes can be installed in parallel and at same elevation, provide multiple
or trapeze hangers.
7. Provide copper plated hangers and supports for copper piping or sheet lead packing
between hanger or support and piping.
8. Prime coat exposed steel hangers and supports. Hangers and supports located in crawl
spaces, pipe shafts, and suspended ceiling spaces are not considered exposed.
K. Provide clearance in hangers and from structure and other equipment for installation of
insulation and access to valves and fittings. Refer to Division 23 Section HVAC Piping
Insulation.
M. Slope piping and arrange systems to drain at low points. Use eccentric reducers to maintain top
of pipe level.
N. Where pipe support members are welded to structural building framing, scrape, brush clean,
and apply one coat of zinc rich primer to welds.
O. Prepare unfinished pipe, fittings, supports, and accessories, ready for finish painting. Refer to
Division 09 Section Painting and Coating.
3.3 SCHEDULES
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Expansion tanks.
2. Air vents.
3. Air separators.
4. Strainers.
5. Balancing valves.
6. Flow indicators, controls, meters.
7. Relief valves.
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
1.3 SUBMITTALS
B. Product Data: Provide product data for manufactured products and assemblies required for this
project. Include component sizes, rough-in requirements, service sizes, and finishes. Include
product description, model.
C. Submit inspection certificates for pressure vessels from authority having jurisdiction.
A. Maintenance Data: Include installation instructions, assembly views, lubrication instructions, and
replacement parts list.
B. The Contractor shall submit all certifications and testing data as a supplement to previously
submitted O & M manuals at contract closeout.
1.5 QUALIFICATIONS
A. Accept valves on site in shipping containers with labeling in place. Inspect for damage.
C. Provide temporary end caps and closures on piping and fittings. Maintain in place until
installation.
D. Protect piping systems from entry of foreign materials by temporary covers, completing sections
of the work, and isolating parts of completed system.
PART 2 - PRODUCTS
A. Construction: Closed, welded steel, tested and stamped in accordance with ASME SEC 8-D;
cleaned, prime coated, and supplied with steel support saddles; with tappings for installation of
accessories.
B. Gage Glass Set: Brass compression stops, guard, and 3/4 inch red line glass, maximum 24
inches length, long enough to cover tank for 2 inches above bottom to 2 inches below top.
C. Automatic Cold Water Fill Assembly: Pressure reducing valve, strainer, and valved by-pass.
A. Manual Type: Short vertical sections of 2 inch diameter pipe to form air chamber, with 1/8 inch
brass needle valve at top of chamber.
B. Float Type:
C. Washer Type:
1. Brass with hydroscopic fiber discs, vent ports, adjustable cap for manual shut-off, and
integral spring loaded ball check valve.
1. Steel, tested and stamped in accordance with ASME SEC 8-D; for 125 psig operating
pressure, with integral bronze strainer, tangential inlet and outlet connections, and
internal stainless steel air collector tube.
2.4 STRAINERS
1. Screwed brass or iron body for 175 psig working pressure, Y pattern with 1/32 inch
stainless steel perforated screen.
1. Flanged iron body for 175 psig working pressure, Y pattern with 3/64 inch stainless steel
perforated screen.
A. Calibrated, plug type balance valve with precision machined orifice, readout valves equipped
with integral check valves and gasketed caps, calibrated nameplate and indicating pointer.
B. Cast iron or bronze, globe style, balance valve with handwheel with vernier type ring setting and
memory stop, readout valves equipped with integral check valves and gasketed caps.
C. Portable meter consisting of case containing one 3 percent accuracy pressure gage with 0-60
feet pressure range for 500 psig maximum working pressure, color coded hoses for low and
high pressure connections, and connectors suitable for connection to read-out valves.
A. Orifice principle by-pass circuit with direct reading gage, soldered or flanged piping connections
for 125 psig working pressure, with shut off valves, and drain and vent connections.
B. Direct reading with insert pitot tube, threaded coupling, for 150 psig working pressure, maximum
240 deg F, 5 percent accuracy.
C. Cast iron, wafer type, orifice insert flow meter for 250 psig working pressure, with read-out
valves equipped with integral check valves with gasketed caps.
D. Portable meter consisting of case containing one 3 percent accuracy pressure gage with 0-60
feet pressure range for 500 psig maximum working pressure, color coded hoses for low and
high pressure connections, and connectors suitable for connection to read-out valves.
A. Bronze body, teflon seat, stainless steel stem and springs, automatic, direct pressure actuated,
capacities ASME certified and labeled.
PART 3 - EXECUTION
3.1 INSTALLATION
B. Where large air quantities can accumulate, provide enlarged air collection standpipes.
D. For automatic air vents in ceiling spaces or other concealed locations, provide vent tubing to
nearest drain.
E. Provide air separator on suction side of system circulation pump and connect to expansion tank.
F. Provide valved drain and hose connection on strainer blow down connection.
G. Provide relief valves on pressure tanks, low pressure side of reducing valves, heat exchangers,
and expansion tanks.
H. Select system relief valve capacity so that it is greater than make-up pressure reducing valve
capacity. Select equipment relief valve capacity to exceed rating of connected equipment.
J. Where one line vents several relief valves, make cross sectional area equal to sum of individual
vent areas.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
A. Ensure pumps operate pumping specified fluids at specified system fluid temperatures without
vapor binding and cavitation, are non-overloading in parallel or individual operation, and operate
within 25 percent of midpoint of published maximum efficiency curve.
1.4 SUBMITTALS
B. Product Data: Provide pump curves showing performance characteristics with pump and
system operating point plotted applicable. Include electrical characteristics and connection
requirements.
A. Operation and Maintenance Data: Include installation instructions, assembly views, lubrication
instructions, and replacement parts list.
B. The Contractor shall submit all certifications and testing data as a supplement to previously
submitted O & M manuals at contract closeout.
1.6 QUALIFICATIONS
A. Listed and classified by UL as suitable for the purpose specified and indicated.
A. Provide one set of mechanical seals for each type of pump furnished.
PART 2 - PRODUCTS
A. Type: Vertical, single stage, close coupled, radially or horizontally split casing, for in-line
mounting, for 175 psig working pressure.
B. Casing: Cast iron, with suction and discharge gage port, casing wear ring, seal flush
connection, drain plug, flanged suction and discharge.
C. Impeller: Bronze, fully enclosed, keyed directly to motor shaft or extension, trim impeller to
match specified performance.
D. Shaft: Carbon steel with stainless steel impeller cap screw or nut and bronze sleeve.
E. Seal: Carbon rotating against a stationary ceramic seat, 250 deg F maximum continuous
operating temperature.
A. Acceptable Products:
1. Acceptable Manufacturers:
a. Hoffman.
b. Aurora.
c. Roth.
d. Weil.
A. System: Flow indicator, filter housing with cartridge filter, shut-off valves, and flow control valve.
C. Hot Water Filter Housing: Glass reinforced nylon plastic suitable for 220 deg F and 200 psig
operating conditions.
PART 3 - EXECUTION
3.1 PREPARATION
3.2 INSTALLATION
B. Provide access space around pumps for service. Provide no less than minimum as
recommended by manufacturer.
D. Provide line sized shut-off valve and strainer on pump suction, and line sized soft seat check
valve and balancing valve on pump discharge.
E. Provide air cock and drain connection on horizontal pump casings and gauge tapping on
suction and discharge flanges.
G. Provide side-stream filtration system for heating water system. Install across pump with flow
from pump discharge to pump suction from pump gauge tappings.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Piping.
2. Refrigerant.
3. Flexible connections.
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
1.3 SUBMITTALS
B. Indicate schematic layout of system, including equipment, critical dimensions, and sizes
developed by the Condensing Unit Manufacture Submittals At Project Closeout:
A. Deliver and store piping and specialties in shipping containers with labeling in place.
B. Protect piping and specialties from entry of contaminating material by leaving end caps and
plugs in place until installation.
C. Dehydrate and charge components such as piping and receivers, seal prior to shipment, until
connected into system.
1.5 QUALIFICATIONS
A. Installer: Company specializing in performing the work of this Section with minimum three years
documented experience.
B. Design piping system under direct supervision of a Professional Engineer experienced in design
of this work, licensed in one of the states of the United States of America, and employed or
approved by the manufacturer of the equipment.
B. Products Requiring Electrical Connection: Listed and classified by UL, as suitable for the
purpose indicated.
2.1 PIPING
1. See Division 23 Section Hangers and Supports for HVAC Piping and Equipment.
2.2 REFRIGERANT
1. R-410A.
A. 500 psig minimum operating pressure; seamless tin-bronze core, high-tensile bronze-braid
covering, and solder-joint end connections: dehydrated, pressure tested, minimum 7 inches
long.
PART 3 - EXECUTION
A. Where more than one piping system material is specified ensure system components are
compatible and joined to ensure the integrity of the system is not jeopardized. Provide
necessary joining fittings. Ensure flanges, union, and couplings for servicing are consistently
provided.
B. Provide pipe hangers and supports in accordance with MSS SP69 unless indicated otherwise.
1. Use in liquid line of systems operating with single pump-out or pump-down compressor
control.
2. Use in liquid line of single or multiple evaporator systems.
3. Use in oil bleeder lines from flooded evaporators to stop flow of oil and refrigerant into the
suction line when system shuts down.
A. Pressure test system with dry nitrogen to 200 psig. Perform final tests at 27 inches vacuum and
200 psig using electronic leak detector. Test to no leakage.
3.3 PREPARATION
3.4 INSTALLATION
B. Basic piping installation requirements are specified in Division 23 Section Common Work
Results for HVAC.
C. Install piping as short and direct as possible, with a minimum number of joints, elbows, and
fittings.
D. Arrange piping to allow inspection and service of compressor and other equipment. Install
valves and specialties in accessible locations to allow for service and inspection.
E. Install piping with adequate clearance between pipe and adjacent walls and hangers or between
pipes for insulation installation. Use sleeves through floors, walls, or ceilings, sized to permit
installation of full-thickness insulation.
F. Below ground, install copper tubing in protective PVC Pipe. Install copper tubing in rigid or
flexible conduit in locations where copper tubing will be exposed to mechanical injury.
1. Install horizontal hot-gas discharge piping with a uniform slope of 1 inch for every 20 feet
downward away from compressor.
2. Install horizontal suction lines with a uniform slope of 1 inch for every 20 feet downward
to compressor.
H. Install bypass around moisture-liquid indicators in lines larger than NPS 2 inch.
I. Install unions to allow removal of solenoid valves, pressure-regulating valves, and expansion
valves and at connections to compressors and evaporators.
J. When brazing, remove solenoid-valve coils and sight glasses; also remove valve stems, seats,
and packing, and accessible internal parts of refrigerant specialties. Do not apply heat near
expansion valve bulb.
K. Hanger, support, and anchor products are specified in Division 23 Section Hangers and
Supports for HVAC Piping and Equipment.
L. Install hangers for copper tubing with the following maximum spacing and minimum rod sizes:
A. Braze joints according to Division 23 Section Common Work Results for HVAC.
B. Fill pipe and fittings with an inert gas (nitrogen or carbon dioxide) during brazing to prevent
scale formation.
A. Test and inspect refrigerant piping according to ASME B31.5, Chapter VI.
2. Test high- and low-pressure side piping of each system with dry nitrogen to 200 psig.
Perform final tests at 27 inches vacuum and 200 psig using electronic leak detector. Test
to no leakage.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1. Division 23 Section Hydronic Piping: Placement of water coupon rack, by-pass (pot)
feeder.
A. The following publications form a part of this Specification to the extent they are applicable:
1.3 SUBMITTALS
B. Product Data: Provide chemical treatment materials, chemicals, and equipment including and
connection requirements.
D. Manufacturer's Field Reports: Indicate start-up of treatment systems when completed and
operating properly. Indicate analysis of system water after cleaning and after treatment.
A. Operation and Maintenance Data: Include data on chemical treatment programs. Include step
by step instructions on test procedures including target concentrations.
B. The Contractor shall submit all certifications and testing data as a supplement to previously
submitted O & M manuals at Contract Closeout.
1.5 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing the products specified in this Section with
minimum three years experience. Company shall have local representatives with water
analysis laboratories and full time service personnel.
B. Installer: Company specializing in performing the work of this Section with minimum three years
experience and approved by manufacturer.
A. Furnish service and maintenance of treatment systems for one year from Date of Substantial
Completion.
B. Provide technical service visits to perform field inspections and make water analysis on site six
months and eleven months after completion. Detail findings in writing on proper practices,
chemical treating requirements, and corrective actions needed. Submit two copies of field
service report after each visit.
C. Provide laboratory and technical assistance services during this maintenance period.
D. Include two hour training course for operating personnel, instructing them on installation, care,
maintenance, testing, and operation of water treatment systems. Arrange course at start up of
systems.
2.1 MATERIALS
A. System Cleaner:
1. Liquid alkaline compound with emulsifying agents and detergents to remove grease and
petroleum products; sodium tripoly phosphate and sodium molybdate.
A. 1.8 gal quick opening cap for working pressure of 175 psig.
A. Provide white enamel test cabinet with local and fluorescent light, capable of accommodating 4
- 10 ml zeroing titrating burettes and associated reagents.
A. Fill the circulating water systems with a solution of 30 percent inhibited ethylene glycol and 70
percent water.
PART 3 - EXECUTION
3.2 PREPARATION
A. Systems shall be operational, filled, started, and vented prior to cleaning. Use water meter to
record capacity in each system.
3.3 INSTALLATION
B. Piping installation requirements are specified in other related Sections. Drawings indicate
general arrangement of piping, fittings, and specialties.
E. Ground equipment.
1. Apply heat while circulating, slowly raising temperature to 160 deg F and maintain for 12
hours minimum.
2. Remove heat and circulate to 100 deg F or less; drain systems as quickly as possible
and refill with clean water.
3. Circulate for 6 hours at design temperatures, then drain.
4. Refill with clean water and repeat until system cleaner is removed.
D. Flush glycol filled closed systems with clean water for one hour minimum. Drain completely and
refill.
3.5 INSTALLATION
A. Provide one bypass feeder on each system. Install isolating and drain valves and necessary
piping. Install around balancing valve downstream of circulating pumps unless indicated
otherwise.
B. Introduce closed system treatment through bypass feeder when required or indicated by test.
C. Provide 3/4 inch water coupon rack around circulating pumps with space for 4 test specimens.
1. Do not enclose, cover, or put piping into operation until it is tested and satisfactory test
results are achieved.
2. Test for leaks and defects. If testing is performed in segments, submit separate report for
each test, complete with diagram of portion of piping tested.
3. Leave uncovered and unconcealed new, altered, extended, and replaced water piping
until it has been tested and approved. Expose work that has been covered or concealed
before it has been tested and approved.
4. Cap and subject piping to static water pressure of 50 psig above operating pressure,
without exceeding pressure rating of piping system materials. Isolate test source and
allow test pressure to stand for four hours. Leaks and loss in test pressure constitute
defects.
5. Repair leaks and defects with new materials and retest piping until satisfactory results are
obtained.
6. Prepare test reports, including required corrective action.
A. Sample boiler water at one-week intervals after boiler startup for a period of five weeks, and
prepare certified test report for each required water performance characteristic. Where
applicable, comply with ASTM D 3370 and the following standards:
3.9 DEMONSTRATION
1. Train Owner's maintenance personnel on procedures and schedules for starting and
stopping, troubleshooting, servicing, and maintaining equipment and schedules.
C. Review data in maintenance manuals, especially data on recommended parts inventory and
supply sources and on availability of parts and service. Refer to Division 01 Section Closeout
Procedures.
D. Review data in maintenance manuals, especially data on recommended parts inventory and
supply sources and on availability of parts and service. Refer to Division 01 Section Closeout
Procedures.
E. Schedule at least [four] hours of training with Owner, through Architect, with at least seven days
advance notice.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Metal ductwork.
2. Casing and plenums.
3. Duct cleaning.
4. Air turning devices.
5. Fire dampers.
6. Smoke dampers.
7. Duct access doors.
8. Duct test holes.
9. Flexible duct connections.
10. Volume control dampers.
11. Motorized dampers.
12. Damper motors.
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
A. No variation of duct configuration or sizes permitted except by written permission. Size round
ducts installed in place of rectangular ducts in accordance with ASHRAE table of equivalent
rectangular and round ducts.
1.4 SUBMITTALS
C. LEED Submittals:
1. Product Data for Prerequisite EQ 1: Documentation indicating that duct systems comply
with ASHRAE 62.1, Section 5 - "Systems and Equipment."
2. Product Data for Prerequisite EA 2: Documentation indicating that duct systems comply
with ASHRAE/IESNA 90.1, Section 6.4.4 - "HVAC System Construction and Insulation."
A. Perform Work in accordance with SMACNA - HVAC Duct Construction Standards - Metal and
Flexible [, and NAIMA Fibrous Glass Construction Standards].
A. Do not install duct sealants when temperatures are less than those recommended by sealant
manufacturers.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Galvanized Steel Ducts: ASTM A525 and ASTM A527 galvanized steel sheet, lock-forming
quality, having zinc coating of in conformance with ASTM A90.
1. Two ply vinyl film supported by helically wound spring steel wire; fiberglass insulation;
polyethylene vapor barrier film.
2. Pressure Rating: 4 inches WG positive and 1.0 inches WG negative.
3. Maximum Velocity: 4000 fpm.
4. Temperature Range: Minus 10 deg F to 160 deg F.
D. Sealant:
1. Non-hardening, water resistant, fire resistive, compatible with mating materials; liquid
used alone or with tape, or heavy mastic.
2. Low Volatile Organic Content (VOC).
E. Hanger Rod: ASTM A36; steel; threaded both ends, threaded one end, or continuously
threaded.
A. Fabricate and support in accordance with SMACNA HVAC Duct Construction Standards - Metal
and Flexible, and as indicated. Provide duct material, gages, reinforcing, and sealing for
operating pressures indicated.
B. Construct T's, bends, and elbows with radius of not less than 1-1/2 times width of duct on
centerline. Where not possible and where rectangular elbows are used, provide air foil turning
vanes. Where acoustical lining is indicated, provide turning vanes of perforated metal with
glass fiber insulation.
C. Increase duct sizes gradually, not exceeding 15 degrees divergence wherever possible;
maximum 30 degrees divergence upstream of equipment and 45 degrees convergence
downstream.
D. All [exposed] round duct shall be spiral lock seam, [double wall insulated with 1 inch
minimum of K=.25, 3lb/sq.ft fiber glass insulation with cleanable, noneroding,
antimicrobial coating, and galvaneal outer duct ready for painting. Fabricate round and
oval duct fittings two gages heavier than duct gages indicated in SMACNA Standard.
Joints shall be minimum 4 inch cemented slip joint, brazed or electric welded. Prime
coat welded joints. Package exposed duct so as to prevent shipping damage].
E. Provide standard 45 degree lateral wye takeoffs unless otherwise indicated where 90 degree
conical tee connections may be used.
A. Multi-blade device with blades aligned in short dimension; steel or aluminum construction; with
individually adjustable blades, mounting straps.
B. Ceiling Dampers: Galvanized steel, 22 gage frame and 16 gage flap, two layers 0.125 inch
ceramic fiber on top side, [and one layer on bottom side for round flaps,] with locking clip.
D. Curtain Type Dampers: Galvanized steel with interlocking blades. Provide stainless steel
closure springs and latches for [horizontal installations] [closure under air flow conditions].
Configure with blades out of air stream except for [1.0 inch] [ ] pressure class ducts
up to 12 inches in height.
E. Multiple Blade Dampers: 16 gage galvanized steel frame and blades, oil-impregnated bronze or
stainless steel sleeve bearings and plated steel axles, 1/8 by 1/2 inch plated steel concealed
linkage, stainless steel closure spring, blade stops and lock.
F. Fusible Links: UL 33, separate at [160] [212] [ ] degrees F with adjustable link straps
for combination fire/balancing dampers.
C. Multiple Blade Dampers: Fabricate with 16 gage galvanized steel frame and blades,
oil-impregnated bronze or stainless steel sleeve bearings and plated steel axles, stainless steel
jamb seals, 1/8 by 1/2 inch plated steel concealed linkage, stainless steel closure spring, blade
stops, and lock, and 1/2 inch actuator shaft.
A. Fabricate in accordance with SMACNA HVAC Duct Construction Standards - Metal and
Flexible, and as indicated.
B. Fabrication: Rigid and close-fitting of galvanized steel with sealing gaskets and quick fastening
locking devices. For insulated ductwork, install minimum 1 inch thick insulation with sheet metal
cover.
C. Access doors with sheet metal screw fasteners are not acceptable.
A. Temporary Test Holes: Cut or drill in ducts as required. Cap with neat patches, neoprene plugs,
threaded plugs, or threaded or twist-on metal caps.
A. Fabricate in accordance with SMACNA HVAC Duct Construction Standards - Metal and
Flexible, and as indicated.
1. Fabric: UL listed fire-retardant neoprene coated woven glass fiber fabric to NFPA 90A,
minimum density 30 oz per sq yd.
2. Net Fabric Width: Approximately 6 inches wide.
3. Metal: 3 inch wide, 24 gage galvanized steel.
1. Manufacturers:
5. Blades:
a. Oil-impregnated bronze.
b. Dampers in ducts with pressure classes of 3-inch wg or less shall have axles full
length of damper blades and bearings at both ends of operating shaft.
a. Stainless-steel sleeve.
b. Dampers in ducts with pressure classes of 3-inch wg or less shall have axles full
length of damper blades and bearings at both ends of operating shaft.
a. Hercules.
2. These take-offs have large 1 inch flanges with an adhesive coated gasket that holds the
fitting in position during installation and assures a tight seal.
3. All high Efficiency Take-offs have dampers with standard hardware. Provide damper
hardware with 2 inch standoffs (for insulated duct).
a. Jiffy Damper.
2. Blades: Stiffen damper blades for stability. Provide galvanized-steel, 24-gauge (0.024
thick.).
3. Blade axles to be galvanized-steel.
A. Fabricate in accordance with SMACNA HVAC Duct Construction Standards - Metal and
Flexible, and as indicated.
C. Multi-Blade Damper: Fabricate of opposed blade pattern with maximum blade sizes 8 by 72
inch. Assemble center and edge crimped blades in prime coated or galvanized channel frame
with suitable hardware.
D. End Bearings: Except in round ductwork 12 inches and smaller, provide end bearings. On
multiple blade dampers, provide oil-impregnated nylon or sintered bronze bearings.
E. Quadrants:
A. Dampers shall be as VOLUME CONTROL DAMPERS above except that parallel blade
dampers may be used for two position service and dampers shall have blade edge and jamb
gaskets.
A. Operators: UL listed and labeled spring return type electric type suitable for 120 volts, single
phase, 60 Hz. Locate damper operator on exterior of duct and link to damper operating shaft.
PART 3 - EXECUTION
3.1 INSTALLATION
B. Install and seal ducts in accordance with SMACNA HVAC Duct Construction Standards - Metal
and Flexible.
C. Duct Sizes are inside clear dimensions. For lined ducts, maintain sizes inside lining.
E. Locate ducts with sufficient space around equipment to allow normal operating and
maintenance activities.
F. Use crimp joints with or without bead for joining round duct sizes 8 inch and smaller with crimp
in direction of air flow.
H. Connect diffusers to low pressure ducts directly or with 10 feet maximum length of insulated
flexible duct held in place with strap or clamp.
I. Connect flexible ducts to metal ducts with draw bands and sheet metal screws.
L. Kitchen exhaust ducts shall have access doors accessible from a 10 or shorter step ladder in
accord with NFPA 96-(most current version).
M. Provide backdraft dampers on exhaust fans or exhaust ducts nearest to outside and where
indicated.
O. Provide duct test holes where indicated and required for testing and balancing purposes.
P. Provide fire dampers and smoke dampers at locations indicated. Install with required perimeter
mounting angles, sleeves, breakaway duct connections, corrosion resistant springs, bearings,
bushings and hinges.
Q. Install smoke dampers and combination smoke and fire dampers in accordance with NFPA 92A.
S. Provide flexible connections immediately adjacent to equipment in ducts associated with fans
and motorized equipment, and supported by vibration isolators.
T. Provide balancing dampers at points on supply, return, and exhaust systems where branches
are taken from larger ducts as required for air balancing. Install minimum 2 duct widths from
duct take-off.
V. Provide balancing dampers on high velocity systems where indicated. Refer to Division 23
Section Convection Heating and Cooling Units.
W. Provide balancing dampers on duct take-off to diffusers, grilles, and registers, regardless of
whether dampers are specified as part of the diffuser, grille, or register assembly.
3.2 TESTING
A. Test in accordance with procedure outlined in SMACNA HVAC Air Duct Leakage Test Manual.
Testing shall be required for all pressure classes unless waived by the Contracting officer.
3.3 CLEANING
A. Clean duct system and force air at high velocity through duct to remove accumulated dust. To
obtain sufficient air, clean half the system at a time. Protect equipment which may be harmed
by excessive dirt with temporary filters, or bypass during cleaning. Provide adequate access
into ductwork for cleaning purposes.
3.4 SCHEDULES
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
1.3 SUBMITTALS
PART 2 - PRODUCTS
A. Product Requirements:
1. Performance Ratings: Conform to AMCA 210 and bear the AMCA Certified Rating Seal.
2. Sound Ratings: AMCA 301, tested to AMCA 300, and bear AMCA Certified Sound Rating
Seal.
3. Fabrication: Conform to AMCA 99.
4. UL Compliance: UL listed and labeled, designed, manufactured, and tested in
accordance with UL 705.
B. Fan Unit: V-belt or direct driven as indicated, with spun aluminum housing; resilient mounted
motor; 1/2 inch mesh, 16 gage aluminum birdscreen; square base to suit roof curb with
continuous curb gaskets.
C. Roof Curb: See Division 23 Section Hangers and Supports for HVAC Piping and Equipment.
D. Disconnect Switch: Factory wired, non-fusible, in housing for thermal overload protected motor.
E. Backdraft Dampers: Gravity actuated with counterweight and interlocking aluminum blades with
felt edges in steel frame installed on fan discharge.
F. Sheaves: Cast iron or steel, dynamically balanced, bored to fit shafts and keyed; variable and
adjustable pitch motor sheave selected so required rpm is obtained with sheaves set at mid-
position; fan shaft with self aligning pre-lubricated ball bearings.
A. Centrifugal Fan Unit: V-belt or direct driven with galvanized steel housing , resilient mounted
motor, gravity backdraft damper in discharge.
C. Sheaves: Cast iron or steel, dynamically balanced, bored to fit shafts and keyed; variable and
adjustable pitch motor sheaves selected so required rpm is obtained with sheaves set at mid-
position; fan shaft with self-aligning pre-lubricated ball bearings.
A. Product Requirements:
1. Performance Ratings: Conform to AMCA 210 and bear the AMCA Certified Rating Seal.
2. Sound Ratings: AMCA 301, tested to AMCA 300, and bear AMCA Certified Sound
Rating Seal.
3. Fabrication: Conform to AMCA 99.
4. UL Compliance: UL listed and labeled, designed, manufactured, and tested and installed
in accordance with UL 705 and 96.
B. Fan Unit: V-belt or direct driven as indicated, with upblast spun aluminum housing with grease
tray, resilient mounted motor; 2 inch mesh, 0.62 inch thick aluminum wire birdscreen; square
base to suit roof curb with continuous curb gaskets.
C. Roof Curb: Ventilated double wall, hinged curb adapter, and factory installed nailer strip. See
3.1G below.
D. Disconnect Switch: Factory wired, non-fusible, in housing for thermal overload protected motor.
E. Sheaves: Cast iron or steel, dynamically balanced, bored to fit shafts and keyed; variable and
adjustable pitch motor sheave selected so required rpm is obtained with sheaves set at mid-
position; fan shaft with self-aligning pre-lubricated ball bearings.
A. Complete factory assembled prewired units consisting of casing, split housing fan scrolls for
easy access, centrifugal fans, inlet screen, discharge grille and motor specifically designed to
provide a uniform velocity across the entire width of unit.
D. Unit casings shall be a minimum of 14 gauge steel and finished in epoxy enamel.
E. Motors shall be 2-speed, permanently lubricated, totally enclosed, air over, equipped with heavy
duty thrust bearings and double extended shafts requiring no outboard bearings. Belt driven
units will not be acceptable.
G. Discharge grille shall be adjustable double deflection type with airfoil shaped extruded
aluminum vanes.
H. Furnish for outdoor weather exposed mounting, with water-proof junction boxes.
I. Factory mounted, factory wired control panels including disconnect, motor starters, transformer
for low voltage door switch and terminal strip for connection to power source. Mount and wire
door switch.
A. Unit shall consist of a filtered makeup air fan and indirect gas fired heater, in take duct, and turn
down cabinet all factory mounted and wired on a common roof curb.
B. The filtered makeup air unit shall have a resiliently mounted, belt driven, double width, double
inlet centrifugal fan, with a permanently lubricated ball bearing motor and adjustable speed
drive. The fan and turn down cabinets shall be constructed to be galvanized steel panels with 1
inch foil faced fiberglass insulation. The panels shall be removable for access to internal parts.
Filters shall be UL classified aluminum mesh.
C. Roof curb and roof mounting rails shall be in accord with Division 23 Section Hangers and
Supports for HVAC Piping and Equipment.
D. The indirect as fired heater shall have a stainless steel heat exchanger, aluminized steel
burners, gravity venting system, electric spark ignition pilot, gas pressure regulator, control
transformer, modulation has valve, safety pilot, high limit switch, discharge thermostat to start
and modulate the burner, and an enameled aluminized steel cabinet with 1 inch foil faced
insulation.
E. The prewired control panel shall include a disconnect switch, main fuse blocks and fuses, motor
starter switch thermal overloads, control transformer, all UL listed and mounted in a unified
control panel for single point electrical connection.
F. The inlet duct and hood shall extend 10 feet (or as required by code) from the exhaust fan
discharge and be constructed of galvaneal or aluminized steel and pointed to match the fan and
furnace cabinets.
A. Product Requirements:
1. Performance Ratings: Conform to AMCA 210 and bear the AMCA Certified Rating Seal.
2. Sound Ratings: AMCA 301, tested to AMCA 300, and bear AMCA Certified Sound Rating
Seal.
3. Fabrication: Conform to AMCA 99.
4. UL Compliance: UL listed and labeled, designed, manufactured, and tested in
accordance with UL 705.
C. Roof Curb: See Division 23 Section Hangers and Supports for HVAC Piping and Equipment.
D. Disconnect Switch: Factory wired, non-fusible, in housing for thermal overload protected motor.
E. Backdraft Dampers: Gravity actuated with counterweight and interlocking aluminum blades with
felt edges in steel frame installed on fan discharge.
F. Sheaves: Cast iron or steel, dynamically balanced, bored to fit shafts and keyed; variable and
adjustable pitch motor sheave selected so required rpm is obtained with sheaves set at mid-
position; fan shaft with self aligning pre-lubricated ball bearings.
PART 3 - EXECUTION
3.1 INSTALLATION
C. Secure roof-mounting fans to roof curbs with cadmium-plated hardware. Refer to Division 07
Section Roof Accessories for installation of roof curbs.
D. Ceiling Units: Suspend units from structure; use steel wire or metal straps.
Retain and edit first paragraph below for suspended units; delete if
vibration and seismic controls are specified in Part 2 "Capacities
and Characteristics" paragraphs or are indicated on Drawings. If
not scheduled, identify required vibration- and seismic-control
device by using the titles of devices described in Division 15
Section "Mechanical Vibration and Seismic Controls" and identify
its required static deflection.
E. Support suspended units from structure using threaded steel rods and [elastomeric hangers]
[spring hangers] [spring hangers with vertical-limit stops] <Insert device> having a static
deflection of 1 inch. Vibration-control devices are specified in Division 23 Section Vibration and
Seismic Controls for HVAC Piping and Equipment.
I. Do not operate fans for any purpose until ductwork is clean, filters in place, bearings lubricated,
and fan has been test run under observation.
J. Range hood exhaust fans shall discharge 40 inches or more above roof and 3 feet above
intakes within 10 feet horizontally.
K. Label units according to requirements specified in Division 23 Section Identification for HVAC
Piping and Equipment.
3.2 CONNECTIONS
A. Duct installation and connection requirements are specified in other related Sections. Drawings
indicate general arrangement of ducts and duct accessories. Make final duct connections with
flexible connectors. Flexible connectors are specified in Division 23 Section Metal Ducts and
Air Accessories.
C. Ground equipment according to Division 26 Section Grounding and Bonding for Electrical
Systems.
A. Perform the following field tests and inspections and prepare test reports:
3.4 CONTROL
A. NON-RMCS controlled units: Provide controls as indicated on drawings and Division 23 Section
Instrumentation And Control Devices For HVAC.
B. RMCS controlled units shall be controlled as indicated on drawings and Division 23Section
REFRIGERATION MONITORING AND CONTROL SYSTEMS (RMCS).
C. Bakery Oven exhaust shall be interlocked and operate when oven is operating.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Registers/grilles.
2. Louvers.
3. Roof hoods.
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
1.3 SUBMITTALS
A. Test and rate air outlet and inlet performance in accordance with ADC Equipment Test Code
1062 and ASHRAE 70.
1.5 QUALIFICATIONS
PART 2 - PRODUCTS
C. Accessories: Radial opposed blade damper as detailed on the Drawings with damper adjustable
from diffuser face.
A. Type: Lay in style with louvered face, fully adjustable pattern, and removable face.
C. Accessories: Radial opposed blade damper and microprocessor based volume controller for
variable volume heating and cooling with automatic changeover. Where multiple diffusers occur
in one space, provide master-drone controls. Provide one remote controller for each room and
one additional controller.
A. Type: Perforated face with fully adjustable pattern and removable face.
B. Fabrication: Steel with steel or aluminum frame and baked enamel finish.
C. Accessories: Radial opposed blade damper and multi-louvered equalizing grid with damper
adjustable from diffuser face.
A. Type: Streamlined and individually adjustable blades, 3/4 inch minimum depth, 3/4 inch
maximum spacing with spring or other device to set blades, horizontal face, double deflection.
C. Fabrication: Steel with 20 gage minimum frames and 22 gage minimum blades, steel and
aluminum with 20 gage minimum frame, or aluminum extrusions, with factory baked enamel,
color to be selected.
D. Damper: Integral, gang-operated opposed blade type with removable key operator, operable
from face.
A. Type: Streamlined blades, 3/4 inch minimum depth, 3/4 inch maximum spacing, with spring or
other device to set blades, horizontal face.
C. Fabrication: Steel with 20 gage minimum frames and 22 gage minimum blades, with factory
baked enamel finish, color to be selected.
D. Damper: Integral, gang-operated, opposed blade type with removable key operator, operable
from face.
A. Type: Continuous width and number of slots as scheduled with adjustable vanes for left, right,
or vertical discharge.
C. Frame: Margin as scheduled with countersunk screw, concealed mounting or support clips for
suspension system mounting and gasket, mitered end border.
***A/E to edit***
A. Type: Streamline blades with 90 degree [one-way] [two-way] deflection as scheduled sized
and space as scheduled.
C. Fabrication: Steel with 20 gage minimum frames and 22 gage minimum blades, steel and
aluminum with 20 gage minimum frame, or aluminum extrusions, with factory off-white enamel,
baked enamel finish.
D. Damper: Integral, gang-operated, opposed blade type with removable key operator, operable
from face.
A. Type: 4 inch deep with blades on 45 degree slope with center baffle and return bend, heavy
channel frame, birdscreen with 1/2 inch square mesh.
B. Fabrication: 12 gage thick extruded aluminum, welded assembly, with factory fluropolymer
spray finish color to be selected by the Contracting Officer.
A. Fabricate air inlet or exhaust hoods in accordance with SMACNA HVAC Duct Construction
Standards - Metal and Flexible.
B. Fabricate of galvanized steel, minimum 16 gage base and 20 gage hood, or aluminum,
minimum 16 gage base and 18 gage hood; suitably reinforced; with removable hood; birdscreen
with 1/2 inch mesh, and 1 inch internal neoprene faced insulation.
C. Mount unit on minimum 12 inch high curb base with insulation between duct and curb.
PART 3 - EXECUTION
3.1 INSTALLATION
B. Check location of outlets and inlets and make necessary adjustments in position to conform with
architectural features, symmetry, and lighting arrangement.
D. Provide balancing dampers on duct take-off to diffusers, and grilles and registers, despite
whether dampers are specified as part of the diffuser, or grille and register assembly.
E. Paint ductwork visible behind air outlets and inlets matte black. Refer to Division 09 Section
Painting and Coating.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Kitchen hoods.
2. Fire extinguishing equipment.
3. Fuel shutoff devices.
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
1.3 SUBMITTALS
1. Hoods.
2. Grease removal devices.
C. Shop Drawings:
1. Show plan view, elevation view, sections, roughing-in dimensions, service requirements,
duct connection sizes, and attachments to other work.
2. Show cooking equipment plan and elevation to confirm minimum code-required
overhang.
3. Indicate performance, exhaust and makeup air airflow and pressure loss, at actual
Project-site elevation.
4. Indicate method of attaching hangers to building structure.
5. Show exhaust and makeup air ducts, and fittings connecting to hoods.
6. Show water-supply and drain piping.
7. Show control cabinets.
8. Show fire-protection piping, actuation devices, and manual control devices.
9. Detail equipment assemblies and indicate dimensions, weights, loads, required
clearances, method of field assembly, components, and location and size of each field
connection.
10. Wiring Diagrams: Power, signal, and control wiring.
D. Piping Diagrams: Detail fire-suppression piping and components and differentiate between
manufacturer-installed and field-installed piping. Include roughing-in requirements for drain
connections. Show cooking equipment plan and elevation to illustrate fire-suppression nozzle
locations.
PART 2 - PRODUCTS
A. Kitchen hoods:
1. Greenheck.
2. Captive Air
3. Halton
4. Gaylord.
5. Econovent.
6. Duo-Air.
7. Greasmaster.
2.2 MATERIALS
1. The exhaust hood, entire exhaust duct system and all grease producing appliances under
the hood shall be protected against fire by the wet chemical fire suppression system.
2. The system shall be designed and installed by a factory authorized distributor in
accordance with Underwriter's Laboratories and Factory Mutual's listings and to conform
to all local authorities having jurisdiction including NFPA #96.
3. Provide automatic gas and electric fuel shutoff devices (manual reset) to the Plumbing
and Electrical Contractors for all cooking appliances wired to stop appliances upon the
actuation of the system.
4. Nozzles located in the plenum and exhaust duct shall be of the spring loaded, self-closing
type, capable of functioning with a heavy accumulation of grease.
5. Nozzles for deep fat fryer and other associated cooking equipment shall be either of the
self-closing type or shall be fitted with nozzle covers as supplied by the manufacturer.
6. Entire system shall be self-purging.
7. The installer shall have regularly available contract maintenance of this type system plus
24 hour emergency service for same. They shall furnish as a part of this work a
maintenance contract for one year from the date of Substantial Completion with
inspection at least once each 6 months and 24 hour emergency service when required.
8. All exposed piping and devices shall be chrome plated, chrome sleeved or stainless
steel.
9. Remote manual release at exit door (10 feet minimum from exhaust system, 4 feet 6
inches AFF).
10. Furnish all required wiring to connect fire extinguishing system to building fire alarm
system.
11. All wiring or cabling shall be concealed.
PART 3 - EXECUTION
3.1 PREPARATION
3.2 INSTALLATION
1. Make closed butt and contact joints that do not require filler.
C. Install hoods and associated services with clearances and access for maintaining, cleaning, and
servicing hoods, grease removal devices, and fire-suppression systems according to
manufacturer's written instructions and requirements of authorities having jurisdiction.
D. Make cutouts in hoods where required to run service lines and to make final connections.
E. Securely anchor and attach items and accessories to walls, floors, or bases with stainless-steel
fasteners, unless otherwise indicated.
G. Install trim strips and similar items requiring fasteners in a bed of sealant. Fasten with stainless-
steel fasteners at 48 inches o.c. maximum.
H. Install sealant in joints between equipment and abutting surfaces with continuous joint backing,
unless otherwise indicated. Provide airtight, watertight, vermin-proof, sanitary joints.
I. Install lamps, with maximum recommended wattage, in equipment with integral lighting.
J. Electrical contractor will provide all field wiring to do the following (upon fire extinguisher system
actuation):
K. Electrical contractor will provide power wiring to lights. He will also furnish and install wall
mounted light switch.
L. Division 23 Section Commercial-Kitchen Hoods contractor shall do all other electrical wiring
required, if any.
N. Fabricate in accord with Kitchen Equipment Fabrication Guidelines and "Duct Construction
Standards" unless specified in Division 05 Section Metal Fabrications.
O. Coordinate with Division 05 Metal Fabrications for stainless steel wall panels required behind
equipment item 1D09 chicken rotisserie.
R. Ground equipment.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
1.3 DEFINITIONS
D. Vent: That portion of a venting system designed to convey flue gases directly outdoors from a
vent connector or from an appliance when a vent connector is not used.
E. Vent Connector: That part of a venting system that conducts the flue gases from the flue collar
of an appliance to a chimney or vent, and may include a draft control device.
A. Factory built vents and chimneys used for venting natural draft appliances shall comply with
NFPA 211 and are UL listed and labeled.
B. Design chimneys and vents metal stacks for wind loading and seismic loads specified in
Division 01 Section Summary of Work.
1.5 SUBMITTALS
1.6 QUALIFICATIONS
A. Conform to IMC and NFPA 54 (ANSI Z223.1) code for installation of natural gas burning
appliances and equipment.
PART 2 - PRODUCTS
B. Fabrication: Inner pipe of sheet aluminum, and outer pipe of galvanized sheet steel, tested in
compliance with UL 441.
B. Provide double wall metal stacks, UL listed, for use with building heating equipment, in
compliance with NFPA 211.
C. Fabricate with 1 inch minimum air space between walls. Construct inner jacket of 20 gage
ASTM A167 stainless steel. Construct outer jacket of aluminum coated steel stainless steel 24
gage for sizes 10 inches to 24 inches and 20 gage for sizes 28 inches to 48 inches.
D. Accessories, UL labeled:
1. Ventilated Roof Thimble: Consists of roof penetration, vent flashing with spacers and
storm collar.
2. Exit Cone: Consists of inner cone, and outer jacket, to increase stack exit velocity 1.5
times.
3. Stack Cap: Consists of conical rainshield with inverted cone for partial rain protection
with low flow resistance.
A. 24 gage or heavier galvanized steel pipe with accessories provided by the appliance
manufacturer.
B. The assembly shall be constructed to maintain air tightness of both the flue and intake duct.
B. Fabrication: Double-wall metal vents, inner shell ASTM A 959, Type 29-4C stainless steel and
outer jacket aluminized steel. Inner shell and outer jacket separated by at least a 1/2-inch
airspace, tested according to UL 1738 and rated for 480 deg F continuously, with positive or
negative flue pressure complying with NFPA 211.
C. Provide Manufacturers standard rain cap, ventilated thimble, storm collar, flashing and other
accessories required for a complete installation.
Edit note: delete if not using pre-fabricated grease ducting for type
1 commercial kitchen exhaust hood grease duct.
PART 3 - EXECUTION
3.1 INSTALLATION
C. For Type B double wall gas vents, maintain UL listed minimum clearances from combustibles.
Assemble pipe and accessories as required for complete installation.
E. Clean chimneys and vents during installation, removing dust and debris.
H. Seal between sections of positive-pressure vents and grease exhaust ducts according to
manufacturer's written installation instructions, using sealants recommended by manufacturer.
I. Support vents at intervals recommended by manufacturer to support weight of vents and all
accessories, without exceeding appliance loading
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Boilers.
2. Controls and boiler trim.
3. Hot water connections.
4. Fuel connection.
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
C. Shop Drawings: Indicate capacity and dimensions of manufactured products and assemblies
required for this project. Indicate electrical service with electrical characteristics and connection
requirements, and duct connections.
A. Manufacturer's Field Reports: Indicate condition of equipment after start-up including control
settings and performance chart of control system.
C. The Contractor shall submit all certifications and testing data as a supplement to previously
submitted O & M manuals at contract closeout.
A. Conform to applicable code and NFPA 70 code for internal wiring of factory wired equipment.
B. Conform to ASME SEC 4 and SEC 8D and AGA Z21.13 and UL 726 for boiler construction.
A. Protect units before, during, and after installation from damage to casing by leaving factory
shipping packaging in place until immediately prior to final acceptance.
A. Acceptable Manufacturers:
1. Lochinvar.
2. Bryan.
B. Manufactured Units:
1. Hot water natural draft boiler with horizontal grid, finned tube heat exchanger, gas
burning system, refractory combustion chamber, controls, and boiler trim [including
circulator] [and fill system consisting of diaphragm type expansion tank, fill and
check valve, and automatic air vent].
C. Fabrication:
1. Assembly: Finned copper tube heat exchanger assembled within combustion chamber
conforming to ASME SEC 4 [and SEC 8D] requirements, and tested for maximum
working pressure of 160 psi.
2. Combustion Chamber: Line with interlocking refractory insulating panels of vermiculite,
high temperature cements, asbestos fiber and refractory clay for service temperatures to
2100 deg F.
3. Exchanger: Fabricate of finned copper tubing with stainless steel baffles and sealed into
bronze, steel, or cast iron headers with silicone O-ring gaskets.
4. Jacket: Galvanized steel with factory applied baked enamel, insulated with foil faced
fiberglass insulation.
E. Trim:
1. Operating Controls: Pre-wired, factory assembled electric control including pilot safety
and thermocouple transformer, 24-volt gas valve, manual main and pilot valves, and
junction box.
2. Operating temperature controller [with outdoor reset] to control burner operation to
maintain supply water temperature at 200 deg F at 0 deg F ambient and 140 deg F at 60
deg F ambient and above.
3. Building Management System Interface: Factory install hardware and software to enable
RMCS to monitor, control, and display boiler status and alarms. Refer to Div 23 Section
Refrigeration Monitoring And Control Systems (RMCS)
4. High limit temperature controller with automatic reset for burner to prevent boiler water
temperature from exceeding safe system temperature.
A. Acceptable Manufacturers:
1. Lochinvar.
2. Bryan.
B. Manufactured Units:
C. Fabrication:
a. Motors: Minimum size as indicated. If not indicated, large enough so driven load
will not require motor to operate in service factor range above 1.0.
3. Safety Controls: Energize ignition, limit time for establishment of flame, prevent opening
of gas valve until pilot flame is proven, stop gas flow on ignition failure, [energize blower
motor, and after air flow proven] [and] allow gas valve to open.
4. Flue Gas Collector and Draft Hood: [Integral with boiler casing.] [External] draft
diverter [with automatic motorized vent damper]. [Integral with boiler casing with
E. Trim:
F. Controls:
1. Operating Controls: Pre-wired, factory assembled electric control including pilot safety
and thermocouple transformer, 24-volt gas valve, manual main and pilot valves, and
junction box.
2. Operating temperature controller [with outdoor reset] to control burner operation to
maintain supply water temperature at 200 deg F at 0 deg F ambient and 140 deg F at 60
deg F ambient and above.
3. Building Management System Interface: Factory install hardware and software to enable
RMCS to monitor, control, and display boiler status and alarms. Refer to Div 23 Section
Refrigeration Monitoring And Control Systems (RMCS).
4. High limit temperature controller with automatic reset for burner to prevent boiler water
temperature from exceeding safe system temperature.
PART 3 - EXECUTION
3.1 INSTALLATION
C. Install boiler on concrete housekeeping base, sized minimum 4 inches larger than boiler base.
Refer to Division 03 Section Cast-In-Place Concrete.
D. Provide piping connections and accessories as indicated; refer to Division 23 Section Hydronic
Piping Specialties.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
1. ASHRAE 103 - Heating Seasonal Efficiency of Central Furnaces and Boilers, Methods of
Testing.
2. NEMA MG 1 - Motors and Generators.
3. NFPA 54 (AGA Z223.1) - National Fuel Gas Code.
4. NFPA 70 - National Electrical Code.
5. NFPA 90A - Installation of Air Conditioning and Ventilating Systems.
6. NFPA 90B - Installation of Warm Air Heating and Air Conditioning Systems.
7. NFPA 211 - Chimneys, Fireplaces, Vents, and Solid Fuel Burning Appliances.
1.3 SUBMITTALS
PART 2 - PRODUCTS
A. Acceptable Manufacturers:
1. Panelbloc.
2. Schwank Inc.
3. Reznor/Thomas & Betts Corporation.
D. Gas Burner:
F. Room Sensor: Provide a wall mounted sensor to cycle burner to maintain room temperature
setting utilizing the RMCS system.
A. Acceptable Manufacturers:
B. Units: Self-contained, packaged factory assembled, pre-wired unit consisting of cabinet, supply
fan, heat exchanger, burner, controls, and accessories. Provide separated combustion type
where scheduled.
C. Cabinet: Galvanized steel with baked enamel finish easily removed and secured access doors,
glass fiber insulation and reflective liner.
D. Supply Fan: Propeller or Centrifugal forward curved type as scheduled with direct or belt drive.
F. Gas Burner:
G. Operating Controls:
1. Room Sensort: Provide a wall mounted sensor to cycle burner to maintain room
temperature setting utilizing RMCS system.
2. Supply Fan Control: Energize from bonnet temperature independent of burner controls,
with adjustable timed off delay and fixed timed on delay, with manual switch for
continuous fan operation.
A. Acceptable Manufacturers:
1. Reznor.
2. Lennox Industries, Inc.
3. Modine.
B. Units: Self-contained, power vented, [indoor] [rooftop], packaged, factory assembled, pre-
wired unit consisting of cabinet and supply fan assembly, and duct furnaces each consisting of
heat exchanger, burner, and roof curb.
C. Cabinet: Galvanized steel with baked enamel finish, easily removed and secured access doors,
glass fiber insulation and reflective liner.
D. Supply Fan: Centrifugal type rubber mounted with belt drive, variable pitch motor pulley.
E. Filter: One inch (25 mm) thick glass fiber throw-away type, located to filter air before fan.
F. Gas Fired Duct Furnace Units: Self-contained, power vented, packaged, factory assembled,
pre-wired unit consisting of cabinet, heat exchanger, burner, controls, and accessories.
G. Operating Controls:
1. Room Sensort: Provide a wall mounted sensor to cycle burner to maintain room
temperature setting utilizing RMCS system.
2. Supply Fan Control: Energize from bonnet temperature independent of burner controls,
with adjustable timed off delay and fixed timed on delay, with manual switch for
continuous fan operation.
H. Disconnect Switch:
I. Roof Curb:
1. [Roof Mounting Curb: 14 inches (350 mm) high galvanized steel, channel frame
with gaskets, nailer strips, insulated, top to be level, designed in accord with
Division 23 Section Hangers and Supports for HVAC Piping and Equipment [and
A. Acceptable Manufacturers:
1. Carrier.
2. Trane.
3. Lennox.
B. Units: Self-contained, power vented, Indoor, packaged, factory assembled, pre-wired unit
consisting of cabinet and supply fan assembly, heat exchanger, and burner.
C. Cabinet: Galvanized steel with baked enamel finish, easily removed and secured access
doors, glass fiber insulation and reflective liner.
D. Supply Fan: Centrifugal type rubber mounted with direct or belt drive, variable pitch motor
pulley.
E. Filter: One inch thick glass fiber throw-away type, located to filter air before fan.
F. Gas Fired Furnace Units: Self-contained, separated combustion, power vented, packaged,
factory assembled, pre-wired unit consisting of cabinet, heat exchanger, burner, controls, and
accessories.
G. Operating Controls:
A. Acceptable Manufacturers:
B. Units: Packaged, partially factory assembled, pre-wired unit consisting of cabinet, burner, heat
exchanger, radiant tube, reflector, controls; for natural gas.
C. Heat Exchanger: Aluminized tubular steel combustion chamber with aluminized steel tube with
aluminum reflector.
D. Gas Burner:
1. Gas Burner: Forced Draft type with adjustable combustion air supply.
2. Gas valve provides 100 percent safety gas shut-off; 24 volt combining pressure
regulation, safety pilot, manual set (On-Off), pilot filtration, automatic electric valve.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Division 01 Section Quality Control: Verification of existing conditions before starting work.
B. Verify that space is ready for installation of units and openings are as indicated on Shop
Drawings.
3.2 INSTALLATION
C. Provide vent connections to NFPA 211. Refer to Division 23 Section Breechings, Chimneys,
and Stacks.
D. Install unit heaters and dust furnaces with vibration isolation. Refer to Division 23 Section
Vibration and Seismic Controls for HVAC Piping.
A. Install all controls and all electrical power control wiring and devices from the point of electrical
connection shown on the Electrical Drawings.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
1.3 SUBMITTALS
C. LEED Submittal:
A. Comply with manufacturer's installation instructions for rigging, unloading, and transporting
units.
PART 2 - PRODUCTS
2.1 REFRIGERANT
2.2 EFFICIENCY
A. Equipment shall meet or exceed the minimum efficiency requirements set forth in the
International Energy Conservation Code, edition adopted by authority having jurisdiction.
A. Units: Self-contained, packaged, factory assembled and pre-wired units suitable for outdoor
use consisting of cabinet, compressors, condensing coil and fans, integral sub-cooling coil,
controls, liquid receiver, and screen guards.
C. Performance Ratings: Energy Efficiency Rating (EER) and Coefficient of Performance (COP)
not less than prescribed by ASHRAE 90A.
2.4 CASING
A. House components in welded steel frame with galvanized steel panels with weather resistant,
baked enamel finish.
B. Mount starters, disconnects, and controls in weatherproof panel provided with full opening
access doors. Provide mechanical interlock to disconnect power when door is opened.
A. Coils: Aluminum fins [copper fins] mechanically bonded to seamless copper tubing with
corrosion resistant polyethylene coating and coastal filter. Provide sub-cooling circuits. Air test
under water to 425 psig, and vacuum dehydrate. Seal with holding charge of refrigerant.
B. Coil Guard: Expanded metal, Louvered, or PVC coat steel wire for hail damage prevention.
A. Vertical discharge direct belt driven propeller type condenser fans with fan guard on discharge.
Equip with roller or ball bearings with grease fittings extended to outside of casing.
B. Weatherproof motors suitable for outdoor use, single phase permanent split capacitor or 3
phase, with permanent lubricated ball bearings and built in thermal overload protection.
2.7 COMPRESSORS
B. Mounting: Statically and dynamically balance rotating parts and mount on vibration isolators.
D. Crankcase Heater: Evaporates refrigerant returning to crankcase during shut down. Energize
heater when compressor is not operating.
A. Provide each unit with one refrigerant circuit, factory supplied and piped. Refer to Division 23
Section Refrigerant Piping.
1. Filter dryer.
2. Thermal expansion device.
3. Insulated suction line.
4. Suction and liquid line service valves and gage ports.
5. Charging valve.
6. Compressor discharge service valve.
7. Condenser pressure relief device.
8. Moisture and liquid indicator.
2.9 CONTROLS
A. On unit, mount weatherproof steel control panel, NEMA 250, containing power and control
wiring, factory wired with single point power connection.
B. Provide compressor starter, control power transformer or terminal for controls power, and
condenser fan starter relay.
C. Provide safety controls arranged so any one will shut down machine:
D. Provide one of the following controls to permit operation down to 30 deg F ambient temperature:
1. Head pressure switch to cycle fan motors in response to refrigerant condensing pressure.
2. Solid state control to vary speed of one condenser fan motor in response to refrigerant
condensing pressure.
3. Electronic control consisting of mixing damper assembly, controlled to maintain constant
refrigerant condensing pressure.
E. Provide one of the following controls to permit operation below 30 deg F ambient temperature.
1. Low Ambient Controller: Cycles condenser fan to permit operation down to 0 deg F [with
time-delay relay to bypass low-pressure switch].
2. Low Ambient Controller: Controls condenser fan speed to permit operation down to
minus 20 deg F [with time-delay relay to bypass low-pressure switch].
F. For heat pump units, provide reversing valve, suction line accumulator, [discharge muffler,]
flow control check valve, and solid-state defrost control utilizing thermistors.
3.1 INSTALLATION
A. Install units level and plumb, firmly anchored in locations indicated; maintain manufacturer's
recommended clearances.
D. Vibration Isolation: Mount ground-mounted condensing units on rubber pads with a minimum
deflection of 1/4 inch.
E. Vibration Isolation: Mount ground-mounted condensing units on restrained spring isolators with
a minimum deflection of 1 inch. Anchor units to supports.
G. Loose Components: Install electrical components, devices, and accessories that are not factory
mounted.
J. Provide connection to refrigeration piping system and evaporators. Refer to Division 23 Section
Refrigerant Piping. Comply with ASHRAE 15.
L. Charge system with refrigerant and test entire system for leaks after completion of installation.
Repair leaks, put system into operation, and test equipment performance.
M. Securely fasten condensing units to housekeeping pads on roof mounting rails to withstand
wind and seismic loading specified in Division 01 Section Summary of Work.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Chiller package.
2. Charge of refrigerant and oil.
3. Controls and control connections.
4. Chilled water connections.
5. [Remote air cooled condenser.]
6. Refrigerant piping.
7. Starters.
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
C. Shop Drawings: Indicate components, assembly, dimensions, weights and loadings, required
clearances, and location and size of field connections. Indicate valves, strainers, and
thermostatic valves required for complete system.
A. Operation and Maintenance Data: Include start-up instructions, maintenance data, parts lists,
controls, and accessories. Include trouble-shooting guide.
B. The Contractor shall submit all certifications and testing data as a supplement to previously
submitted O & M manuals at Contract closeout.
A. Comply with manufacturer's installation instructions for rigging, unloading, and transporting
units.
B. Protect units from physical damage before, during and after installation.
A. Acceptable Manufacturers:
1. Trane.
2. Carrier.
B. Efficiency:
1. EER shall not be less than required by the International Energy Conservation Code,
version adopted by authority having jurisdiction.
C. Manufactured Units:
1. Provide factory assembled and tested indoor air cooled liquid chillers consisting of
compressors, remote air cooled condenser, evaporator, thermal expansion valve,
refrigeration piping and accessories, and control panel. Construction, testing, and ratings
shall be in accordance with ARI 590.
2. Conform to UL 465 code for construction of reciprocating water chillers and provide UL
label.
3. Conform to ASME SEC 8 Boiler and Pressure Vessel Code for construction and testing
of reciprocating water chillers.
4. Conform to ASHRAE 15 code for construction and operation of water chillers.
D. Semi-Hermetic Compressors:
1. Reciprocating Compressors:
1) Starter: Part winding, with manual reset current overload protection, starter
relay, control power transformer, terminal strip for connection to interface
equipment.
2) Safety Controls: Manually reset, adjustable high and low pressure cutouts,
low oil pressure cutout.
3) Panel Face: Compressor run light, start-stop switch, circuit breaker or
disconnect switch, demand limit switch, elapsed time meter, crankcase
heater start-stop switch and light.
1. Provide shell and tube type, ASME labeled, evaporator, seamless or welded steel
construction with removable cast iron or fabricated steel heads, seamless copper tubes
or red brass tubes with integral fins, rolled or silver brazed into tube sheets. [Provide
multiple refrigerant circuits on multiple compressor units.]
2. Design, test, and stamp refrigerant side for 225 psig working pressure and water side for
150 psig working pressure, in accordance with ASME SEC 8.
3. Insulate with 0.75 inch minimum thick flexible elastomeric thermal insulation complying
with ASTM C 534, Type II, with maximum K value of 0.28.
4. Provide water drain connection and thermometer wells for temperature controller and low
temperature cutout.
G. Enclosures:
1. House air cooled condenser components in welded steel frame with galvanized steel
panels with weather resistant, baked enamel finish.
2. Mount starters and disconnects in panel provided with full opening access doors.
Provide mechanical interlock to disconnect power when door is opened.
H. Refrigerant Circuit:
1. Provide refrigerant circuits, factory and field supplied and piped. Refer to Division 23
Section "Refrigerant Piping".
2. Provide for each refrigerant circuit:
1. On chiller, mount steel control panel, containing starters power and control wiring,
molded case disconnect switch, factory wired with single point power connection.
2. For each compressor, provide part winding starter, non-recycling compressor overload,
starter relay, and control power transformer or terminal for controls power. Provide
manual reset current overload protection.
3. Provide safety controls with indicating lights with terminations for connection to controls
system arranged so any one will shut down machine and require manual reset:
5. Building Management System Interface: Factory install hardware and software to enable
RMCS to monitor, control, and display chiller status and alarms. Refer to Div 23 Section
Refrigeration Monitoring And Control Systems (RMCS).
6. Provide pre-piped gage board with pressure gages for suction and discharge refrigerant
pressures, and oil pressures for each compressor.
A. Acceptable Manufacturers:
1. Trane.
2. Carrier.
B. Manufactured Units:
1. Provide factory assembled and tested outdoor air cooled liquid chillers consisting of
compressors, condenser, evaporator, thermal expansion valve, refrigeration accessories,
and control panel. Construction, testing, and ratings shall be in accordance with ARI 590.
C. Semi-Hermetic Compressors:
1. Reciprocating Compressors:
1) Starter: Part winding, with manual reset current overload protection, starter
relay, control power transformer, terminal strip for connection to interface
equipment.
2) Safety Controls: Manually reset, adjustable high and low pressure cutouts,
low oil pressure cutout.
3) Panel Face: Compressor run light, start-stop switch, circuit breaker,
demand limit switch, elapsed time meter, crankcase heater start-stop switch
and light.
[ -- OR -- ]
2. Screw Compressors:
a. Unit: direct drive, semi-hermetic 3600 rpm, fixed compression, rotary screw
compressor with control panel.
b. Features: Differential refrigerant pressure oil pump, oil heater, oil separator and
filter, oil charging valve.
c. Motor: Suction gas cooled hermetically sealed, squirrel cage induction.
d. Controls:
1. Provide shell and tube type evaporator, seamless or welded steel construction with cast
iron or fabricated steel heads, seamless copper tubes or red brass tubes with integral
fins, rolled or silver brazed into tube sheets. Provide multiple refrigerant circuits as
indicated.
2. Design, test, and stamp refrigerant side for 225 psig working pressure and water side for
150 psig working pressure, in accordance with ASME SEC 8.
3. Insulate with 0.75 inch minimum thick flexible elastomeric thermal insulation complying
with ASTM C 534, Type II, with maximum K value of 0.28.
4. Provide water drain connection and thermometer wells for temperature controller and low
temperature cutout.
E. Condensers:
F. Enclosures:
1. House components in welded steel frame with galvanized steel panels with weather
resistant, baked enamel finish.
2. Mount starters and disconnects in weather proof panel provided with full opening access
doors. Provide mechanical interlock to disconnect power when door is opened.
G. Refrigerant Circuit:
1. Provide refrigerant circuits, factory supplied and piped. Refer to Division 23 Section
Refrigerant Piping.
2. Provide for each refrigerant circuit:
H. Controls:
1. On chiller mount weather proof steel control panel, containing starters power and control
wiring, factory wired with single point power connection.
2. For each compressor, provide part winding starter, non-recycling compressor overload,
starter relay, and control power transformer or terminal for controls power. Provide
manual reset current overload protection.
5. Building Management System Interface: Factory install hardware and software to enable
RMCS to monitor, control, and display chiller status and alarms. Refer to Div 23 Section
Refrigeration Monitoring And Control Systems (RMCS).
6. Provide pre-piped gauge board with pressure gauges for suction and discharge
refrigerant pressures, and oil pressures for each compressor.
7. For multiple units, provide remote mounted sequence panel to allow operation in parallel
with lead-lag switching.
PART 3 - EXECUTION
3.1 INSTALLATION
C. Install units on vibration isolation. Refer to Division 23 Section Vibration and Seismic Controls
for HVAC Piping and Equipment.
D. Complete Refrigerant Piping from chiller to remote air cooled condenser. Pipe pressure relief
device full size to out of doors.
1. On outlet, provide:
G. Securely fasten units to housekeeping pads on roof mounting rails to withstand wind and
seismic loading specified in Division 01 Section Summary of Work.
B. Supply service of factory trained representative for a period of 2 days to supervise testing,
dehydration and charging of machine, start-up, and instruction on operation and maintenance to
Government.
B. Demonstrate system operation and verify specified performance. Refer to Division 23 Section
Testing, Adjusting, and Balancing for HVAC.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
1.3 SUBMITTALS
C. LEED Submittals:
A. Protect units from physical damage by storing off site until roof mounting curbs are in place,
ready for immediate installation of units.
1.7 WARRANTY
A. Provide a five year warranty to include coverage for refrigeration compressors and heat
exchangers.
2.1 REFRIGERANT
2.2 EFFICIENCY
A. EER shall not be less than 10.5 for units 10 tons of nominal capacity and above.
B. EER shall not be less than 12 for units 6 to 10 tons of nominal capacity.
A. General: Roof mounted units having [no heat], [or] [heat pump], [or] [gas burner], and
electric refrigeration, configured as scheduled on the Drawings.
2.4 FABRICATION
A. Cabinet: Galvanized steel with baked enamel finish, access doors or removable access panels
with quick fasteners screwdriver operated flush cam type or locking door handle type with piano
hinges. Structural members shall be minimum 18 gage, with access doors or removable panels
of minimum 20 gage.
B. Insulation: 1/2 inch thick with neoprene or resin coated glass fiber with edges protected from
erosion.
C. Supply Fan: Forward curved centrifugal type, resiliently mounted with V-belt drive and
adjustable variable pitch motor pulley, and rubber isolated hinge mounted high efficiency motor
or direct drive as indicated. Isolate complete fan assembly. Refer to Division 23 Section
Vibration and Seismic Controls for HVAC Piping and Equipment.
D. Air Filters: 2 inches thick pleated media 30 percent NBS, 1 inch thick for units 5 nominal tons
and less.
E. Roof Mounting Curb: 14 inches high galvanized steel, channel frame with gaskets, nailer strips,
insulated, top to be level, designed in accord with Division 23 Section Hangers and Supports for
HVAC Piping and Equipment [and Division 23 Section Vibration and Seismic Controls for
HVAC Piping and Equipment].
A. Provide copper tube aluminum fin coil assembly with galvanized drain pan and connection.
A. Finned tube heating elements or [Helical nickel-chrome resistance wire coil heating
elements with refractory ceramic support bushings] easily accessible with automatic reset
thermal cut-out, built-in magnetic contactors, galvanized steel frame, control circuit transformer
and fuse, manual reset thermal cut-out, airflow proving device, load fuses.
B. Controls: Start supply fan before electric elements are energized and continue operating until
air temperature reaches minimum setting, with switch for continuous fan operation.
2.7 FILTERS
A. Units shall be equipped with disposable roughing filters ahead of pleated disposable type filters
with nonwoven pleated media held in place by a welded wire support grid. All filters shall be
mounted such that air bypass is minimized. Pleated media filters shall be 30 percent minimum
efficiency per ASHRAE Test Standard 52.2-2007.
A. Gas Burner: Induced draft type minimum efficiency 80 percent. Burner with adjustable
combustion air supply, pressure regulator, gas valves, manual shut-off, intermittent spark or
glow coil ignition, flame sensing device, and automatic 100 percent shut-off pilot.
C. Gas Burner Safety Controls: Energize ignition, limit time for establishment of flame, prevent
opening of gas valve until pilot flame is proven, stop gas flow on ignition failure, energize blower
motor, and after air flow proven and slight delay, allow gas valve to open.
D. High Limit Control: Temperature sensor with fixed stop at maximum permissible setting, de-
energize burner on excessive bonnet temperature and energize burner when temperature drops
to lower safe value.
E. Supply Fan Control: Temperature sensor sensing bonnet temperatures and independent of
burner controls, with provisions for continuous fan operation.
2.9 COMPRESSOR
A. Provide hermetic scroll compressors, resiliently mounted with positive lubrication, crankcase
heater, high and low pressure safety controls, motor overload protection, suction and discharge
service valves and gage ports, and filter drier.
A. Provide copper tube [copper] [aluminum] fin coil assembly with subcooling rows and coil
guard.
B. Provide direct drive propeller fans, resiliently mounted with fan guard, motor overload
protection, wired to operate with compressor. Provide high efficiency fan motors.
C. Provide refrigerant pressure switches or outdoor thermostat to cycle condenser fans for
operation to 0 deg F.
A. Dampers: Provide motorized outside air dampers for minimum outside air quantity as well as
for the economizer cycle. Provide relief air fans where scheduled. Provide control of remote
relief air dampers and exhaust fans where scheduled.
B. Damper Operator: 24 volt with gear train sealed in oil with spring return on units 7.5 ton cooling
capacity and larger.
2.12 CONTROLS
A. On unit, mount weatherproof steel control panel, NEMA 250, containing power and control
wiring, factory wired with single point power connection.
B. Provide unit disconnect switch, compressor starter, control power transformer or terminal for
controls power, and condenser fan starter relay.
C. Provide safety controls arranged so any one will shut down machine:
D. Provide one of the following controls to permit operation down to 30 deg F ambient temperature:
1. Head pressure switch to cycle fan motors in response to refrigerant condensing pressure.
2. Solid state control to vary speed of one condenser fan motor in response to refrigerant
condensing pressure.
3. Electronic control consisting of mixing damper assembly, controlled to maintain constant
refrigerant condensing pressure.
4. For heat pump units, provide reversing valve, suction line accumulator, [discharge
muffler,] flow control check valve, and solid-state defrost control utilizing thermistors.
E. The RMCS, Division 23 Section Refrigeration Monitoring and Control Systems (RMCS), shall
control heating, cooling, fan operation, and the outdoor air motorized damper. Provide a
terminal strip for the Division 23 Section Refrigeration Monitoring and Control Systems (RMCS)
connection. Coordinate with the Division 23 Section Refrigeration Monitoring and Control
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that roof is ready to receive work and opening dimensions are as indicated on Shop
Drawings.
3.2 INSTALLATION
C. Mount units on factory built roof mounting curb providing watertight enclosure to protect
ductwork and utility services. Install roof mounting curb level. Secure to withstand wind and
seismic loading specified in Division 01 Section Summary of Work.
B. Provide initial factory-authorized service representative start-up and shut-down during first year
of operation.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this specification to the extent they are applicable:
1.3 SUBMITTALS
A. Comply with manufacturer's installation instructions for rigging, unloading, and transporting
units.
PART 2 - PRODUCTS
2.1 GENERAL
2.2 MANUFACTURERS
1. Carrier Corporation; Home Comfort and HVAC Building & Industrial Systems.
2. Lennox International Inc.
3. Trane; a business of American Standard companies.
4. YORK; a Johnson Controls company.
5. <Insert manufacturer's name>.
2.3 REFRIGERANT
A. R410A.
A. Units: Self-contained, packaged, factory assembled and pre-wired [cooling] [heat pump] units
suitable for outdoor use consisting of cabinet, compressors, outdoor coil and fans, integral sub-
cooling coil, controls, liquid receiver, and screen guards with separate indoor ductless fan and
coil.
B. Construction and Ratings: In accordance with ARI 210/240 and UL 207 and UL 303. Testing
shall be in accordance with ASHRAE 14.
C. Performance Ratings: Energy Efficiency Rating (EER) and Coefficient of Performance (COP)
not less than prescribed by ASHRAE 90A.
D. Casing:
1. House components in welded steel frame with galvanized steel panels with weather
resistant, baked enamel finish.
2. Mount starters, and controls in weatherproof panel provided with full opening access
doors.
3. Provide removable access doors or panels with quick fasteners.
E. Condenser Coils:
1. Direct driven propeller type condenser fans with fan guard on discharge.
2. Weatherproof motors suitable for outdoor use, single phase permanent split capacitor
with built in thermal overload protection.
G. Compressors:
A. [Four way discharge, ceiling recessed fan coil unit with condensate pump, [electric
heating coil] outdoor air intake provision (to draw air from the adjacent ceiling space),
and combination return air grille and adjustable supply air diffuser.]
C. [Horizontal ceiling surface mounted fan coil unit with condensate pump, [electric heating
coil] and adjustable supply air diffuser.]
D. The condensate pump shall have a minimum shut-off head of 15 feet or a separate condensate
pump with reservoir, float switch and check valve shall be furnished. (Little Giant VCL-24ULS
or equal.)
A. Provide each unit with one refrigerant circuit, factory supplied and piped.
1. Filter dryer.
2. Thermal expansion device.
3. Insulated suction line.
4. Suction and liquid line service valves and gage ports.
5. Charging valve.
6. Compressor discharge service valve.
7. Condenser pressure relief device.
8. Precharged refrigerant piping.
2.7 CONTROLS
A. On outdoor unit, mount weatherproof steel control panel, containing power and control wiring,
factory wired with single point power connection.
B. Provide compressor starter, control power transformer or terminal for controls power, and
condenser fan starter relay.
C. Provide safety controls arranged so any one will shut down machine:
D. Provide one of the following controls to permit operation down to 0 deg F ambient temperature:
1. Head pressure switch to cycle fan motors in response to refrigerant condensing pressure.
2. Solid state control to vary speed of one condenser fan motor in response to refrigerant
condensing pressure.
3. Electronic control consisting of mixing damper assembly, controlled to maintain constant
refrigerant condensing pressure.
E. Wall mounted, hard wired, programmable microprocessor controller with room sensors and self
diagnostic feature. Provide locking cover.
3.1 INSTALLATION
B. Install seismic restraints per Division 23 Section Vibration and Seismic Controls for HVAC
Piping and Equipment.
D. Provide connection to refrigeration piping system and evaporators. Comply with ASHRAE 15.
F. Charge system with refrigerant and test entire system for leaks after completion of installation.
Repair leaks, put system into operation, and test equipment performance.
H. Securely fasten condensing units to housekeeping pads on roof mounting rails to withstand
wind and seismic loading specified in Division 01 Section Summary of Work.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
1.3 SUBMITTALS
a. Indicate cross sections of cabinets, grilles, bracing and reinforcing, and typical
elevations.
b. Submit schedules of equipment and enclosures typically indicating length and
number of pieces of element and enclosure, corner pieces, end caps, cap strips,
PART 2 - PRODUCTS
A. Acceptable Manufacturers:
1. Trane.
2. Engineered Air.
3. Rosemex.
4. Slant/Fin.
B. Heating Elements: Copper or steel tube, mechanically expanded into evenly space aluminum
or steel fins.
C. Element Hangers: Quiet operating, ball bearing cradle type providing unrestricted longitudinal
movement, on enclosure brackets.
D. Enclosures: 0.0478 inch steel up to 18 inches in height, 0.0598 inch steel over 18 inches in
height, with easily jointed components for wall to wall installation. Support rigidly, on wall or
floor mounted brackets at least 3 feet on center maximum.
F. Access Doors: For otherwise inaccessible valves, provide factory-made permanently hinged
access doors, 6 by 7 inch minimum size, integral with cabinet.
G. Capacity: As scheduled, based on 65 deg F entering air temperature, 180 deg F average water
temperature.
A. Acceptable Manufacturers:
B. Coils: Seamless copper tubing, silver brazed to steel headers, and with evenly spaced
aluminum fins mechanically bonded to tubing.
C. Casing: 0.0478 inch steel with threaded pipe connections for hanger rods.
E. Fan: Direct drive propeller type, statically and dynamically balanced, with fan guard; horizontal
models with permanently lubricated sleeve bearings; vertical models with grease lubricated ball
bearings.
F. Air Outlet: Adjustable pattern diffuser on projection models and two way louvers on horizontal
throw models.
G. Motor: Permanently lubricated sleeve bearings on horizontal models, grease lubricated ball
bearings on vertical models. Refer to Division 23 Section Common Motor Requirements for
HVAC Equipment.
I. Capacity: As scheduled.
A. Acceptable Manufacturers:
1. Carrier Corporation.
2. Markel Products; a division of TPI Corporation.
3. McQuay International.
4. Rosemex.
5. Trane.
B. Coils: Evenly spaced aluminum fins mechanically bonded to copper tubes, designed for 100 psi
and 220 deg F.
D. Finish: Factory applied baked enamel of color as selected on visible surfaces of enclosure or
cabinet.
F. Motor: Tap wound multiple speed with sleeve bearings, resiliently mounted.
H. Filter: Easily removed 1 inch thick glass fiber throw-away type, located to filter air before coil.
A. Acceptable Manufacturers:
1. Carrier Corporation.
2. McQuay International.
3. Trane.
4. York International Corporation.
C. [Cooling] [Heat Pump Indoor] [Water] [Electric] Coils: Evenly spaced aluminum fins
mechanically bonded to copper tubes, designed for 200 psi and 220 degrees F. Provide drain
pan under cooling coil, easily removable for cleaning, with drain connection. [Separate heating
and cooling coils.]
D. Cabinet: 20 gage steel with glass fiber insulation and supply and return duct collars.
I. Filter: Easily removed 1 inch thick pleated media 30 percent ASHRAE 52-76 Dust Spot Test
efficiency located to filter air before coil.
K. Controls: Furnished under Division 23 Section Instrumentation and Control Devices for HVAC
and Division 23 Section Refrigeration Monitoring and Control Systems (RMCS).
3.1 INSTALLATION
B. Install equipment exposed to finished areas after walls and ceiling are finished and painted.
Avoid damage.
C. Protection: Provide finished cabinet units with protective covers during balance of construction.
F. Finned Tube Radiation: Locate on outside walls and run cover wall-to-wall unless otherwise
indicated. Install wall angles where units butt against walls.
G. Unit Heaters: Hang from building structure, with pipe hangers anchored to building, not from
piping. Mount as high as possible to maintain greatest headroom unless otherwise indicated.
H. Cabinet Unit Heaters: Install as indicated. Coordinate to assure correct recess size for
recessed units.
I. Hydronic Units: Provide with shut-off valve on supply and balancing valve on return piping. If
not easily accessible, extend vent to exterior surface of cabinet for easy servicing.
3.2 CLEANING
A. After construction is completed, including painting, clean exposed surfaces of units. Vacuum
clean coils and inside of cabinets.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
B. Product Data: Provide coil and frame configurations, dimensions, materials, rows, connections,
and rough-in dimensions.
C. Shop Drawings: Indicate coil and frame configurations, dimensions, capacities, materials, rows,
connections, and rough-in dimensions.
B. Comply with ARI 410, Standard for Forced-Circulation Air-Cooling and Air-Heating Coils, for
components, construction, and rating.
C. Comply with applicable requirements in ASHRAE 62.1, Section 5 Systems and Equipment and
Section 7 Construction and Startup.
A. Protect coil fins from crushing and bending by leaving in shipping cases until installation, and by
storing indoors.
B. Protect coils from entry of dirt and debris with pipe caps or plugs.
PART 2 - PRODUCTS
A. Tubes: Seamless copper, complying with ASTM-B-75, arranged in parallel or staggered pattern,
expanded into fins, silver brazed joints, compliant with ARI-410.
C. Casing: Die formed channel frame of 16 gage galvanized steel. Provide tube supports for coils
longer than 48 inches.
D. Headers: Cast iron with tubes expanded into header or Seamless copper tube with silver brazed
joints.
E. Testing: Air test under water to 200 psig for working pressure of 200 psig and 220 deg F.
F. Configuration: Drainable, with threaded plugs in headers for drain and vent.
A. Tubes: Seamless copper, complying with ASTM-B-75, arranged in parallel or staggered pattern,
expanded into fins, brazed joints, compliant with ARI-410.
B. Fins: [Aluminum] [Copper] continuous plate type with full fin collars.
C. Casing: Die formed channel frame of 16 gage galvanized steel. Provide tube supports for coils
longer than 36 inches.
E. Liquid Distributors: Brass or copper venturi type distributor with seamless copper distributor
tubes.
F. Testing: Air test under water at 300 psig for working pressure of 250 psig; clean, dehydrate, and
seal with dry nitrogen charge.
G. Fin Spacing: As required to meet capacity. No more than 14 fins per inch.
A. Assembly: ANSI/UL 1096 listed and labeled, with terminal control box and [hinged] cover,
splice box, coil, casing, and controls.
B. Coil: Enclosed copper tube, aluminum finned element of coiled nickel-chrome resistance wire
centered in tubes and embedded in refractory material or exposed helical coil of nickel-chrome
resistance wire with refractory ceramic support bushings as scheduled.
C. Casing: Die formed channel frame of 18 gagegalvanized steel. Provide tube supports for coils
longer than 36 inches.
D. Controls: Automatic reset thermal cut-out, built-in magnetic, control circuit transformer and
fuse, manual reset thermal cut-out, air flow proving device, unfused disconnect, load fuses.
PART 3 - EXECUTION
3.1 INSTALLATION
1. Install in ducts and casings in accordance with SMACNA HVAC Duct Construction
Standards, Metal and Flexible.
2. Support coil sections independent of piping on steel channel or double angle frames and
secure to casings.
3. Provide frames for maximum three coil sections.
4. Arrange supports to avoid piercing drain pans.
5. Provide airtight seal between coil and duct or casing.
6. Refer to Division 23 Section Metal Ducts and Air Accessories.
B. Protect coils to prevent damage to fins and flanges. Comb out bent fins.
E. Hydronic Coils:
1. Hydronic Coils: Connect water supply to leaving air side of coil (counterflow
arrangement).
2. Provide shut-off valve on supply line and balancing valve with memory stop on return
line.
3. Locate water supply at bottom of supply header and return water connection at top.
4. Provide manual air vents at high points complete with stop valve.
5. Ensure water coils are drainable and provide drain connection at low points.
6. Refer to Division 23 Section Hydronic Piping Specialties.
7. For cooling coils where air velocity exceeds 500 ft/min. provide [three break] [six break]
moisture eliminators of galvanized steel.
8. Provide drain pan and drain connection for cooling coils.
a. Fabricate drain pan from 20 gage galvanized steel with connection for drain;
insulated and complying with ASHRAE 62.1.
b. Extend 3 inches from face of coil entering air side 6 inches from face of coil leaving
air side[ and 4 inches from face of eliminators].
c. Pipe drain pans individually to floor drain[ with water seal trap].
G. Refrigerant Coils: Provide sight glass in liquid line within 12 inches of coil. Refer to Division 23
Section Refrigerant Piping.
H. Insulate headers located outside air flow as specified for piping. Refer to Division 23 Section
HVAC Piping Insulation.
END OF SECTION
***DESIGN NOTES***
TABLE OF CONTENTS
PART I GENERAL
1.3 REFERENCES
1.8 WARRANTY
2.2 DEHUMIDIFIERS
3.1 EXAMINATION
3.2 INSTALLATION
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
A. The following publications form a part of this Specification to the extent they are applicable:
1.3 SUBMITTALS
1.5 QUALIFICATIONS
A. Protect units from physical damage by storing off site until roof mounting curbs are in place,
ready for immediate installation of units.
A. Provide a five year warranty to include coverage for refrigeration compressors and heat
exchangers.
PART 2 - PRODUCTS
A. Seasons 4.
B. Munters.
C. AAON.
2.2 REFRIGERANT
2.3 EFFICIENCY
2.4 DEHUMIDIFIERS
***Edit as appropriate
A. General: [Packaged] [Indoor] [Mezzanine mounted] [with remote air cooled condensing
unit] [condenser] [rooftop] units having gas burner and electric refrigeration using non-ozone
depleting refrigerant.
***Edit as appropriate
2.5 CABINET
A. [Aluminum or galvanized steel double wall panels with baked enamel finish and rigid
internal channel frame, fully gasketed joints. Structural members shall be minimum 18
gage.] Drain pans shall be stainless steel.
B. [Aluminum or stainless steel double wall panels with rigid internal stainless steel or
aluminum channel frame, fully gasketed joints. Bottom of unit shall be panned with
aluminum. Drain pans shall be stainless steel. Filter frames shall be aluminum
extrusions. All internal and external surfaces, structural elements, and fasteners shall be
aluminum or stainless steel.]
C. Access doors with flush cam type or locking door handle type with piano hinges and gasketed
heads jambs and sills with knife edge meeting gasket for positive seal. Access doors frames
shall be a minimum 20 gage.
D. Exterior surface shall be cleaned and finished with an air dry enamel. All coils and controls
shall be removable thorough the access doors.
E. Cabinet Insulation shall be 2 inch thick (R-7) for with full inner galvanized steel or aluminum
panel.
F. [Roof Mounting Curb: 14 inches high galvanized steel, channel frame with gaskets, nailer
strips, insulated, top to be level, designed in accord with Division 23 Section Hangers
and Supports for HVAC Piping and Equipment[ and Division 23 Section Vibration and
Seismic Controls for HVAC Piping and Equipment].]
A. Provide mechanical unit manufacturer engineered galvanized metal brackets for anchorage of
Roof Top Mechanical Units to manufactured roof curbs.
B. Design and fabricate brackets to anchor mechanical units to resist forces due to design wind
pressure and seismic forces. Wind load design requirements are as indicated on Structural
Drawing.
A. Backward inclined airfoil centrifugal type, enameled steel construction, resiliently mounted with
V-belt drive and adjustable variable pitch motor pulley to be replaced with fixed pitch sheave
after balancing, and rubber isolated hinge mounted premium efficiency open drip proof motor or
direct drive as indicated.
D. All fans shall be vibration isolated and factory balanced such that maximum displacement in any
plane does not exceed 1.5 mils for fans operating at or below 2000 RPM or 1.0 mils above 2000
RPM. Fans shall operate at 80 percent or less of their first critical speed.
2.8 FILTERS
A. Outside air inlets and return air plenums shall be equipped with disposable roughing filters
ahead of pleated disposable type filters with nonwoven pleated media held in place by a welded
wire support grid. All filters shall be mounted such that air bypass is minimized. Pleated media
filters shall be MERV 8 per ASHRAE Test Standard 52.2-2007.
2.9 DAMPERS
A. Provide manual balancing dampers with position indicating quadrants and locking hardware for
balancing of the by pass air stream and motorized dampers for outdoor and return air service.
B. All dampers shall have heavy gauge [galvanized steel frames, galvanized steel blades with
oil impregnated or synthetic bushings] [aluminum blades and frames, plated steel axels
with synthetic bushings] and plated interconnecting linkage for smooth operation. Dampers
shall be opposed blade type equipped with blade edge and end seals to minimize leakage. All
motorized dampers shall be equipped with operators to provide automatic control operation.
A. Gas Burner: Two stage (NOT MODULATING) natural gas burner with adjustable combustion
air supply, pressure regulator, gas valves, manual shut-off, intermittent spark or glow coil
ignition, flame sensing device, and automatic 100 percent shut-off pilot. Burner shall have a
forced draft or combustion blower to provide positive venting.
B. Gas Burner Safety Controls: Energize ignition, limit time for establishment of flame, prevent
opening of gas valve until pilot flame is proven, stop gas flow on ignition failure, energize blower
motor, and after air flow proven and slight delay, allow gas valve to open.
C. High Limit Control: Temperature sensor with fixed stop at maximum permissible setting, de-
energize burner on excessive bonnet temperature and energize burner when temperature drops
to lower safe value.
D. Supply Fan Control: Temperature sensor sensing bonnet temperatures and independent of
burner controls, with provisions for continuous fan operation.
****NOTE: Select copper fin coil and stainless steel end plates for
outdoor air within 30 miles of the seacoast.
A. Provide copper tube aluminum fin coil assembly with stainless drain pan [and coil endplates]
and [maximum face velocity shall not exceed 350 fpm to reduce supply fan horsepower
requirement] connection for return air coil. Provide copper tube, [copper] [aluminum] fin coil
with stainless steel drain pan for outdoor air coil.
B. Coils shall be direct expansion type constructed with 1/2 inch or 5/8 inch OD seamless copper
tubes mechanically expanded for a compression bond to fins. All evaporator coils shall be
counter flow circuited and equipped with seamless copper tube pressure type distributors. DX
coil will be designed for a maximum working pressure of 400 PSIG. Coil assemblies shall
include 16 gage galvanized steel casings with a support mounting structure that permits coil
removal through side access. Assemblies shall include an insulated drain pan complete with
exterior trap.
C. All direct expansion coils shall be equipped with a thermostatic expansion valve with external
equalization and liquid line solenoid valve. Provide capillary tubes or thermostatic expansion
valves for units of 6 tons capacity and less, and thermostatic expansion valves and alternate
row circuiting for units 7.5 tons cooling capacity and larger.
2.12 COMPRESSOR
A. Provide hermetic scroll compressors, resiliently mounted with positive lubrication, crankcase
heater, high and low pressure safety controls, motor overload protection, suction and discharge
service valves and gage ports, and filter drier.
****Select copper fin coil and stainless steel end plates within 30
miles of the seacoast.
B. Provide copper tube [aluminum fin] [copper fin] coil assembly [with stainless steel end
plates] sub cooling rows and coil guard.
C. Provide direct drive propeller fans, resiliently mounted with fan guard, motor overload
protection, wired to operate with compressor. Provide high efficiency fan motors.
F. [Aluminum or galvanized steel panels with baked enamel finish and rigid internal channel
frame. Structural members shall be minimum 18 gage.]
G. [Aluminum or Stainless steel panels with rigid stainless steel or aluminum channel
frame. All internal and external surfaces, structural elements, and fasteners shall be
aluminum or stainless steel. Fan blades and venturis shall be aluminum or powder
coated steel.]
A. Dampers: Provide motorized outside air dampers for fixed outside air quantity. Damper
construction shall be specified in "DAMPERS" above.
B. Damper Operator: 24 volt with gear train sealed in oil with spring return on units 7.5 ton cooling
capacity and larger.
A. Shall be provided under Division 23 Section Product Refrigeration Systems. Under this Section,
provide a coil cabinet and mount the coil in the unit at the factory.
B. Coils shall be counterflow circuited. Face air flow velocities shall not exceed 550 FPM. Coils
shall be designed for a maximum working pressure of 400 PSIG.
C. The heat reclaim coils shall be provided by the product refrigeration manufacturer and installed
by the HVAC contractor or factory installed.
A. Provide terminal strip on unit for connection of operating controls to the Division 23 Section
Refrigeration Monitoring and Control Systems (RMCS). See Division 23 Section Refrigeration
Monitoring and Control Systems (RMCS) for control functions required. Install and wire the ICU
provided by Division 23 Section Refrigeration Monitoring and Control Systems (RMCS).
B. Interface controls with Division 23 Section Refrigeration Monitoring and Control Systems
(RMCS). Provide all controls or devices required to perform the control and monitoring
functions specified in Division 23 Section Refrigeration Monitoring and Control Systems
(RMCS), but not provided by Division 23 Section Refrigeration Monitoring and Control Systems
(RMCS).
A. Space temperature and humidity shall be controlled by a minimum of three individual cooling
stages utilizing two air paths. The outside air path will process all of the outside air (no bypass)
and provide most of the dehumidification required for the space. An outdoor air precooling coil
and dehumidification coils (6-row minimum) shall be used. The return air path will have a
cooling coil to cool the return air as required to provide the remaining cooling required for the
space. Some return air may be bypassed.
B. The air paths will then mix, heating will be accomplished by utilizing reclaimed refrigeration heat
through heat reclaim coils as the first stage of heating, with the second and third stages of
heating provided by a two stage gas fired power burner or electric heating coil (depending on
utility costs and availability). The reclaimed heat will be used when available and will provide
the first stage of heat. The gas or electric heating will only be used if additional capacity is
required.
C. Fan operation shall be continuous. Fan shall run at high speed (100 percent) in occupied mode
and for cooling dehumidification operation and at low speed (50 percent) at all other times.
D. Compressors shall be sized to match the cooling/dehumidification requirements of the two paths
with the evaporator coils.
E. Multiple Condenser fans shall be controlled from liquid temperature and shall be cycled to
maintain a target liquid temperature.
F. Heat reclaim will be used for reheat and for initial stages of heat.
G. Control the gas heating section from space temperature only after maximum utilization of heat
reclaim has been realized. Auxiliary heat shall not be used for reheat control.
H. The dehumidification coil in the outdoor air path is stage 1 and the outside air precooling coil is
stage 2. The return air cooling coil is stage 3. Stage 1, 2 and 3 coils shall be controlled from
space humidity in that order to maintain 52 deg F dewpoint. Precooling coil shall be locked out
below an ambient temperature of 72 deg F.
I. Outside air and return air motorized dampers shall be provided. The outside air (or night
setback) damper shall be open during the occupied cycle and closed in the unoccupied cycle.
The outside air (or night setback) damper shall be mechanically linked to the return air damper
so the return air damper shall open when the outdoor air (or night setback) damper closes,
allowing return air to follow both air paths.
J. To allow the specified air flow rates in the two paths, an array of static pressure probes shall be
positioned to monitoring internal air pressure drops through key elements of the dual path
system. Each air path shall have built-in balancing dampers for air volume adjustment.
K. Provide a differential pressure switch to monitor the operation of the main blower.
2.18 ELECTRICAL
A. Unit shall be factory prewired with all controls necessary for complete and satisfactory
operation.
B. Unit manufacturer shall mount and wire the ICU provided by the Division 23 Section
Refrigeration Monitoring and Control Systems (RMCS) manufacturer.
C. Disconnect Switch: Factory mount disconnect switch in control panels of indoor and outdoor
units.
D. Duplex Outlet: Provide a separately fused 120V duplex outlet at the air cooled condenser for
service use.
E. Motor starters for motors 20 hp and above shall be reduced voltage solid state type.
F. Lights [and ventilation fan in compressor module and] in each module of the unit with a
switch and pilot light on the exterior of the unit.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that roof is ready to receive work and opening dimensions are as indicated on Shop
Drawings.
3.2 INSTALLATION
A. Examine areas and conditions under which dehumidifier units are to be installed. Do not
proceed with work until satisfactory conditions have been corrected.
B. Install dehumidifier units where indicated, in accordance with equipment manufacturers written
instructions, and with recognized industry practices, to ensure that units comply with
requirements and serve intended purposes.
C. Coordinate with other work, including ductwork, floor construction, roof decking, and piping, as
necessary to interface installation of dehumidifier units with other work.
D. Upon completion of installation of dehumidifier units, the services of a factory technician shall be
provided to start-up and operate equipment to demonstrate capacity with requirements. Field
correct malfunctioning units, then retest to demonstrate compliance.
I. Mount units on factory built roof mounting curb providing watertight enclosure to protect
ductwork and utility services. Install roof mounting curb level. Secure to withstand wind and
seismic loading specified in Division 01 Section Work Covered by Contract Documents.
B. The manufacturer shall provide a factory field service technician for startup supervision and
instruction of operating personnel.
END OF SECTION
GENERAL
1.01 See Criteria Division 13 Section Cold Storage Rooms and Division 23 Section Refrigeration
Monitoring and Control Systems (RMCS) for additional information.
1.02 Summary. Product refrigeration includes all display cases, compressors, condensers, heat
recovery coils, evaporators (unit coolers for insulated cold storage rooms), refrigerant piping,
refrigerant controls, monitoring systems or Refrigeration Monitoring and Control System (RMCS),
associated controls, and all wiring including that not indicated on Drawings required for a
complete, functional and usable system. Refrigeration compressor units with all controls, heat
recovery coils, heat reclaim hot water heaters, diverting valves for heat recovery, condensers,
unit coolers, display cases and RMCS shall be furnished by a single display case or compressor
system manufacturer. The only exception to this is that the self-contained display cases can be a
different manufacturer than the other cases.
At pre-design conference, PMP will provide current Guide Specification. Division 23 Section
Product Refrigeration Systems.
1.03 Design, Furnishing and Installation. The Product System Refrigeration System Provider
(Provider) shall be either the primary compressor system manufacturer or the primary display
case manufacturer. The entire refrigeration system shall be furnished by the Provider who shall
be singly responsible for the design, furnishing, installation, testing, and satisfactory operation of
the total system, including both high and low side components. The installation shall be
supervised by a field engineer employed by the compressor system manufacturer or display case
manufacturer, as the case may be. The design shall use the most energy efficient combination
and arrangement of compressors for the compressor systems, consistent with operational
reliability. Prior to acceptance, the manufacturer shall submit a letter stating that the total
refrigeration system has been inspected and approved by the manufacturer and that it meets the
manufacturer's installation requirements. Provide registered engineering seal and signature on
each Drawing. All contractor design and installation not specifically addressed in this RFP shall
meet or exceed ASHRAE recommendations/guidelines and recommendations of the equipment
manufacturer(s).
1.04 Coordination. The Provider shall coordinate the installation of the total refrigeration systems as
delineated, and shall prepare complete shop Drawings, submittals, and design analysis of the
entire refrigeration system.
1.05 Warranty and Maintenance. Warrant all refrigeration systems and components for a period of
one year following completion and acceptance of the building by the Government. During the
first 90 days of this warranty period, provide monthly preventative maintenance of the systems to
include filter changes, lubrication, and adjustments per systems and component manufacturers'
operation and maintenance manuals. Respond to emergency service calls within 2 hours of
notification and render system(s) 100% repaired and operational within 24 hours.
PRODUCTS
2.01 Mechanical Centers.
A. Compressor systems shall be installed in mechanical center(s) which shall be installed either
at grade or on the roof. Air cooled condensers shall be installed on the roof of the
mechanical center when centers are at grade. When centers are on the roof, use horizontal
receivers and elevate condensers above roof sufficiently to drain to the receivers by gravity.
The centers shall also contain water heaters, electrical equipment and such other equipment
as required by Section Product Refrigeration Systems. The centers shall be located so as to
minimize the length of suction and liquid piping to the various cases and coolers as well as
the length of hot gas piping to the air handling unit coil.
2.02 Unit Coolers.
June 2011 23 90 00 1
DeCA DESIGN CRITERIA HANDBOOK
23 90 00 PRODUCT REFRIGERATION
SYSTEMS
A. General. Size unit coolers in the preparation areas to meet or exceed the load upon the
room at suction temperatures no greater than 20 deg F below room temperatures. Size unit
coolers in all other storage rooms to meet or exceed the load upon the room at suction
temperatures no greater than 10 deg F below room temperatures. Size unit coolers in frozen
food storage rooms to meet or exceed the load upon the room at a suction temperature no
greater than 8 deg F below room temperatures. Unit coolers operating in rooms at or below
28 deg F shall have maximum fin spacings of 4 fins per inch. Unit coolers operating in rooms
above 28 deg F shall have maximum fin spacings of 6-8 fins per inch. Condensate drain
lines in rooms operating at or below 32 deg F shall have 1" unicellular insulation and heat
tape. Run refrigerant piping to compressor units in located in mechanical centers.
B. Suspension. Suspend unit coolers located in insulated cold storage rooms through ceiling
via suspension system from roof structural members. Do not use ceiling support columns
within the cooler panels. Suspension system shall consist of all members, including
fasteners and attachments, required to support unit coolers from underside of roof structural
members. Suspension system shall be of steel materials. Design of suspension system shall
be in accordance with AISC Specifications for the Design, Fabrication and Erection of
Structural Steel for Buildings.
C. Provide unit cooler fans with premium efficiency motors.
D. Required product temperatures to be maintained in walk in boxes and freezers is:
B. Required product temperatures, corresponding suction temperatures, coil types and defrost
method for all types of display cases shall be as follows: [NOTE TO SPECIFIER: Check
against Commissary Equipment List in Appendix A and edit out any inapplicable pieces of
equipment:]
June 2011 23 90 00 2
DeCA DESIGN CRITERIA HANDBOOK
23 90 00 PRODUCT REFRIGERATION
SYSTEMS
OC = Off Cycle
1B06 38 42 25 - OC
1B32 38 42 25 - OC
1D00 36 20 - OC
1D01 33 - 25 OC
1D02 35 38 27 - OC
1D24 30 35 - 25 OC
1F00 28 32 20 - E
1F01 28 32 - 25 E
1G00 34 36 20 - OC
1G02 34 38 - 28 OC
1G09 0 -15 - E
1G10 0 -7 - E
June 2011 23 90 00 3
DeCA DESIGN CRITERIA HANDBOOK
23 90 00 PRODUCT REFRIGERATION
SYSTEMS
1G27 0 -7 - E
1G30 0 -7 - E
1M02 28 34 - -25 OC
1M04 30 36 - 28 OC
1M05 33 38 - 27 OC
1M07 28 34 - 25 E
1M07F 28 34 - 25 E
1M09 28 34 15 - E
1P02/3 34 38 30 OC
1P07 35 38 28 OC
C. Display case item descriptions. Refer to Equipment Descriptions for specific requirements.
D. Refrigerant line and return air duct layout:
1. In the case of island case configurations, to extent practical, consolidate return air duct
risers and refrigerant line risers into shafts at column where they can be run overhead,
above the sales area ceiling, to the mechanical center(s) and/or air handling unit.
2. Where refrigerant piping must be routed above sales area ceiling, where possible, route
above shopping aisles, and not above soffits. This will allow for easier access for
maintenance of the piping, electrical and condensate pans.
3. Consider placement of chases to avoid obtrusive views or interference with overall sales
area decor and appearance.
4. Condensate pans under refrigerant piping:
a. For piping routed above Sales Area ceiling: Provide condensate pans under piping
operation at 0 deg SST and lower if store is located where 2.5% design wet bulb
exceeds 74 deg F.
b. For piping routed above Walk-in Storage or Processing Rooms and overhead in
Warehouse: Provide condensate pans under piping operation at 0 deg SST and
lower if store is located where 2.5% design wet bulb exceeds 78 deg F.
c. Slope drain pans to drain fitting. Pipe drain fitting to floor drain.
June 2011 23 90 00 4
DeCA DESIGN CRITERIA HANDBOOK
23 90 00 PRODUCT REFRIGERATION
SYSTEMS
5. Under floor tunnels shall not be used without express direction from DeCA/END.
6. Conceal ductwork above the ceiling. [See Division 23 for general guidance if no
ceiling is proposed].
2.04 Product Refrigeration System.
A. Comply with requirements of refrigeration system Design Standards Plates.
B. The product refrigeration system includes compressors, condensers, recovery systems,
evaporators (unit coolers for insulated cold storage rooms), refrigerant piping, refrigerant
controls, head pressure controls, defrost systems, and a refrigeration monitoring and control
system (RMCS). Provide the product refrigeration with [three] [two] [one] [separate] low
temperature system[s] and [three] [two] [one] [separate] medium temperature system[s]
[SIZE SPECIFIC: on projects 80,000 sf or less in size, provide with two separate low
temperature systems and two separate medium temperature systems and on projects 30,000
sf or less in size, provide with one low temperature system and one medium temperature
systems.] Each system shall be a multiplex compressor system. Locate compressor
systems [on the mezzanine] [in mechanical centers] [at grade] [on the roof] with
refrigerant lines to cases, coolers, heat reclaim, and remote condensers. Remote
condensers shall be air cooled types. Locate remote condensers on the roof [of the
mechanical centers] above the compressor systems. Locate compressor racks as close as
practical to heat reclaim coils not to exceed 60'-0" piping run. Summer design ambient
temperature shall be the 1% dry bulb design temperature for the area. Condenser capacity
shall meet or exceed compressor heat of rejection at a condensing temperature 10 deg F
above design entering air temperature for low temperature systems and 15 deg F above the
design entering air temperature for medium temperature systems. Use refrigerant R-404A on
all systems. Provide each refrigerated display case with a temperature probe, or as required
in the corresponding equipment descriptions, and ensure that the temperature on the
refrigeration monitoring and control system is readable. Provide a factory installed
temperature probe connected to the RMCS system in each display case. Provide each
double-wide frozen food/ice cream case with two such temperature probes (i.e., one on each
side of the case). Mount all temperature probes in the discharge air stream not more than 6"
from the discharge air grille and at an easily accessible location.
C. Refrigeration Defrost Methods.
1. On display cases with operating SST at greater than 15 deg F, the defrost shall be off
cycle, or as required in the Equipment Descriptions.
2. On walk-in boxes with operating SST greater than 22 deg F, the defrost shall be off cycle.
3. Off cycle defrost shall be time-initiated and time-terminated.
4. All other refrigeration defrost shall be electric. Electric defrost shall be time-initiated and
temperature-terminated with time fail safe.
5. Defrost shall be controlled through the RMCS.
D. Compressor Systems. Locate multiplex compressor systems [in mezzanine] [or] [in
mechanical centers] with refrigerant lines to cases, coolers, heat reclaim, and remote
condensers. Install an evaporator pressure regulator at the compressor system for each
piping circuit to provide temperature control of fixtures and rooms. For each compressor
provide replaceable core suction filter/drier, crankcase heater, high pressure safety switch
with manual reset and low pressure cut in/out with automatic reset, braided steel lines to
controls, electronic oil pressure safety control, and compressor isolation valves.
Compressors shall be high efficiency, semi-hermetic, "Copeland discus" or approved equal.
Each compressor system shall have an oil separator, replaceable core liquid line filter drier,
and liquid receiver with visual and RMCS level indication. Compressors shall be staged on
and off through the RMCS.
June 2011 23 90 00 5
DeCA DESIGN CRITERIA HANDBOOK
23 90 00 PRODUCT REFRIGERATION
SYSTEMS
E. Condensers. Locate on roof [of the mechanical centers]. Condensers shall be air cooled
type with copper tubes and aluminum fins. Maximum fins per inch shall be 10. Fan motors
shall be direct drive type. Control shall be through the RMCS and shall provide for staging of
each parallel fan set to control condensing pressure. [SITE SPECIFIC: Include following
sentence if condensers will be installed within 30 miles of salt water:] [Provide Copper coil
and copper fin condensers.] If VFD control is specified for condenser, mount VFD panel in
[mezzanine] [mechanical center].
F. Refrigeration Piping. Type "L" hard drawn copper soldered with a brazing alloy containing
minimum 15% silver. Slope refrigeration suction lines minimum of 1" per 20'-0" toward the
compressor(s) and provide with a suction trap at the base of each vertical riser. Suction
piping shall maintain a minimum refrigerant velocity in horizontal lines of 700 fpm and 1500
fpm on vertical risers. Maximum suction line pressure drop shall be 2 psi and maximum
liquid line pressure drop shall be 5 psi. Route all refrigeration piping in a manner which
provides for easy access for repair of each solder connection without moving display cases,
concrete, or cooler panels. In each display case and unit cooler provide "sweat type" brass
liquid line ball valves, "sweat type" expansion valves and strainer, "sweat type" schrader
valve on the suction line, and a heat exchanger. Use only long radius elbows (45o elbows
are not permissible) in the refrigeration piping system. Cover refrigeration suction piping on
systems operating below 0 deg F SST with unicellular piping insulation having a minimum
thickness of [1"] [1-1/2"] [SITE SPECIFIC: Use second figure for insulation for suction
piping in regions where the 2.5% design wet bulb exceeds 78 deg F).]. Cover refrigeration
suction piping on systems operating above 0 deg F SST with unicellular piping insulation
having a minimum thickness of [3/4"] [1"] [SITE SPECIFIC: Use second figure for insulation
for suction piping in regions where the 2.5% design wet bulb exceeds 78 deg F.].
G. Refrigerant Suction Line Insulation.
1. Suction lines operating above 0 deg F saturated suction temperature (SST) shall be
insulated with elastomeric pipe insulation with wall thickness of 1". Where the 2.5%
design wet bulb temperature exceeds 78 deg F insulation wall thickness shall be 1".
2. Suction lines operating at a 0 deg F and lower shall be insulated with elastomeric pipe
insulation of 1" wall thickness. Where the 2.5% design wet bulb temperature exceeds 78
deg F insulation wall thickness shall be 1-3/4" and may be applied in two layers with only
the outer layer being of the factory split self adhesive type.
H. Specify aluminum jacket on all exterior insulation.
2.05 Heat Reclaim Water Heaters. Provide to heat domestic water for building with heat rejection of
product refrigeration system.
2.06 Prefabricated Walk-in Refrigerators and Freezers. Refer to Division 13 Section Cold Storage
Rooms.
2.07 Electrical.
A. Provide grounding conductors in all refrigeration electrical conduit runs.
B. Provide duplex receptacles in the kick plates 3' from the end of each side of each island case
lineup. See Design Standard Plate Product Refrigeration Systems-50.
EXECUTION
3.01 Refrigerant Handling and Recovery. Division 01 Section Environmental Procedures for
Refrigerants applies.
3.02 Display Cases:
June 2011 23 90 00 6
DeCA DESIGN CRITERIA HANDBOOK
23 90 00 PRODUCT REFRIGERATION
SYSTEMS
A. Seal as required to floor, walls and to each other with sheet metal parts and caulking per
Design Standards Division 23 Sections Common Work Results for HVAC and Product
Refrigeration Systems.
B. Include details of case sealing on construction Drawings.
3.03 Electrical:
A. Show on the Refrigeration Drawings:
1. Provide a weatherproof disconnect and enclosure for a permanent plug-in receptacle for
power to a temporary refrigeration trailer. The trailer provider will provide a receptacle to
match the NEMA configuration of the trailer plug. Provide conductors and circuit breaker
for 208V/3/70 ampere load.
2. Provide a duplex outlet at each end and each side of the island case runs. Locate the
receptacle in the toe/space of the cases 5' from each end of each case run except that
it shall not be below doors at glass door cases.
3.04 Compressor Systems Locations:
A. Mechanical Centers shall be used in lieu of constructing mechanical mezzanines.
B. In smaller stores Mechanical Centers may be located on Grade when line lengths exceed
practical limits (300'). Locate centers on the roof.
C. Locate Roof mounted Mechanical Centers above walk -in coolers to minimize noise in the
Sales Area.
3.05 Contract Documents Check List:
A. Layout unit cooler drain lines on Drawings, such that lines do not cross door openings.
B. In add / alter projects insure continuous availability of refrigerated cases and walk-ins by
providing a location for new equipment separated from the old equipment location so that
new and existing refrigerated cases and walk-ins can be operated simultaneously.
C. Verify that space and structural support are adequate for replacement equipment.
D. Show location of floor drains for all condensate producing equipment.
E. Gas fired equipment located in refrigeration equipment rooms, occupied spaces, or in
equipment spaces other than properly ventilated and protected boiler rooms shall be of the
separated combustion type with combustion air ducted from out of doors.
F. Work with the Structural Engineer to determine whether seismic restraint or wind restraint is
needed for items of mechanical equipment based on ASCE 7-02.
G. All unit heaters in machinery rooms and mechanical centers shall be sealed combustion type.
H. Show a vapor detector on the Drawings in the refrigeration machinery room(s) or mechanical
center(s).
END OF SECTION
June 2011 23 90 00 7
SECTION 23 90 00
PRODUCT REFRIGERATION SYSTEMS
(Edited from DeCA June 2011 Design Criteria)
PART 1 - GENERAL
1.1 SUMMARY
A. Related Sections:
1. Division 23 Section Product Refrigeration Systems Contractor shall be either the installer
of the refrigeration equipment or the manufacturer of the compressor systems or the
manufacturer of the display cases. Division 23 Section Product Refrigeration Systems
Contractor shall have total system responsibility for all material and work indicated in
Division 23 Section Product Refrigeration Systems and Division 23 Section Refrigeration
Monitoring and Control System (RMCS). This includes, refrigeration piping, refrigeration
electrical and wiring, refrigeration equipment, RMCS equipment, RMCS wiring.
Subcontracts for portions of Division 23 Section Product Refrigeration Systems or
Division 23 Section Refrigeration Monitoring and Control System (RMCS), shall be made
directly with, and shall be directly under the control of the Division 23 Section Product
Refrigeration Systems Contractor.
A. The product refrigeration includes the design, procurement, installation, and testing of all
products, equipment, and materials required for a complete, functional and usable system. This
includes, but is not limited to display cases, compressors, condensers, heat recovery coils,
evaporators, unit coolers, refrigerant piping, pipe insulation, Refrigeration Monitoring and
Control System (RMCS), associated controls, and electrical panels and wiring including that not
indicated on Drawings.
1.3 SUBMITTAL
A. Provide submittal of equipment and material to be used per submittal requirements indicated
below:
1. Submit within 30 days after receipt of Notice to Proceed, and before starting construction
or installation of materials.
2. Distribution: Two complete sets shall be provided to the following offices for approval.
One set shall be submitted to the PMAC Technical Inspector on site and one set shall be
submitted to DeCA Project Manager Each set shall be in a three ring binder with a hard
cover.
3. Contract Variances: If departures from the contract Drawings are deemed necessary,
details of such departures, including changes in related portions of the project and the
reasons therefore, shall be submitted with the drawings. Where such departures require
piping or equipment to be supported otherwise than as shown, the details submitted shall
include loading and type and kind of frames, brackets, stanchions, or other supports
necessary. Approved departures shall be made at no additional cost to the government.
4. Refrigeration Capacity Calculations: For each refrigeration system, capacity data (charts
or tabulated information) for evaporator-compressor and compressor-condenser
arrangements shall be submitted to assure properly balanced refrigeration equipment at
the design conditions.
5. Provide calculations on refrigeration piping pressure drops. (See Part 3 of this Section for
piping installation and manufacturer design requirements).
6. Provide completed refrigeration schedules in same format as on Contract Drawings.
7. Installation Drawings: The layout drawings shall include a plan of the proposed piping,
wiring, and equipment to establish that the equipment will fit the allocated spaces with
clearances for installation and maintenance, and that components of the total product
refrigeration system are fully coordinated. Interconnecting piping and wiring between
evaporators, unit coolers, heat recovery coils, and refrigerated display cases shall be
clearly shown and sizes indicated. The drawings shall include proposed details for
attachment, anchoring, and hanging to structural framing of the building; vibration
isolation units; and foundation and supports.
8. Electrical: (See Part 3 of this Section for electrical installation and manufacturer design
requirements).
a. Letter Acknowledging Their Submitted Design: The Contractor shall provide with
the refrigeration submittal a letter from the display case manufacturer stating that
the engineering department of the display case manufacturer has performed the
design for the refrigeration electrical power wiring.
b. Installation Drawings: Provide power layout drawings showing electrical runs with
wire sizes, conduit sizes, and connection points. Wiring diagrams shall identify
each component, and one diagram shall show interconnected or interlocked
components.
9. Subcontract Plan: Provide flow chart indicating General Contractor, Section Product
Refrigeration Systems contractor, and each and every subcontract related to work in
Division 23 Section Product Refrigeration Systems and Division 23 Section Refrigeration
Monitoring and Control System (RMCS). All subcontracts for work in Division 23 Section
Product Refrigeration Systems or Section Refrigeration Monitoring and Control System
(RMCS) shall be made with and report to Division 23 Section Product Refrigeration
Systems Contractor.
10. Manufacturer Data Sheets: The list of materials and equipment shall be supported by
sufficient descriptive materials, such as catalog cuts, diagrams, and other data published
by the manufacturer, to demonstrate conformance to the Specification requirements.
Model numbers alone will not be acceptable. Submit data concerning the following items
for approval. Manufacturers catalog not acceptable, specific cut sheets or equipment data
shall be provided for each piece of equipment:
11. Manufacturer Approval of Installer: As part of the submittal, the display case
manufacturer shall submit a letter acknowledging their responsibility to inspect and certify
the system installation with an employee of the manufacturing company and their
approval of the contractor or sub contractor installing the equipment (see paragraph 1.3).
No installation work on refrigeration systems shall start until this information is provided to
the contracting officer.
12. Installer Resume: As part of the submittal, the installing contractor shall furnish resumes
and EPA certification of the key refrigeration mechanics and field superintendent
responsible for installation of the refrigeration piping and components (see paragraph
1.3). No installation work on refrigeration systems shall start until this information is
provided to the contracting officer.
B. Type Compressors: Compressors 2 KW (2 hp) and less may be welded hermetic type.
Compressors above 2 KW (2 hp) shall be the accessible, semi-hermetic. Compressors shall be
integrally cast housings of close-grained iron with oil- level bull's eye, cast cylinder heads, cast-
aluminum or forged steel connecting rods, and cast iron or forged-steel crankshafts. The
lubrication system on compressors 5 KW (5 hp) or larger shall be the forced-feed, positive-
displacement type with oil strainer. The oil pump shall be reversible. Suction and discharge
valves shall be flange connected, wrench-operated, rising stem with cap. Rotating parts shall
be statically and dynamically balanced at the factory to eliminate vibration.
C. Compressor Accessories:
3. Liquid line filter driers: Filter-driers shall be installed in main liquid lines leaving the
receiver. Filter-driers Sizes 1/2 inch and larger shall be the full flow, replaceable core
type. Sizes smaller than 1/2 inch shall be the sealed type. Cores shall be of suitable
desiccant that will not plug, cake, dust, channel, or break down. The desiccant shall
remove water, acid, and foreign material from the refrigerant. The filter-drier shall be
constructed so that none of the desiccant will pass into the refrigerant lines. The
minimum bursting pressure shall be 1,500 psi. Filter-driers shall be provided where
recommended by manufacturer of display cases. Liquid line filter-driers shall be wax
removal desiccant or approved equivalent.
4. Sight Glass: A moisture indicator sight-glass shall be provided in the liquid line preceding
the liquid manifold. The moisture indicating elements shall be removable. Moisture
indicators shall have a reversible color indicator which has an easily distinguished color
change. Sight glasses shall be provided with a protective cover and shall have solder-
type connections.
5. Oil Separator: A 99 percent or higher efficiency discharge line oil separator, shall be
provided in the discharge line from each multiplex compressor system. Oil separator
shall have removable flanged head for ease in removing float assembly and removable
screen cartridge assembly. Provide a line size shutoff valve and sight glass in the oil
return line leaving the oil separator. Insure that oil separator is installed such that float
removal is easily accomplished. Pipe oil return to oil reservoir.
6. Oil Reservoir: An oil reservoir adequately sized for the system with two sight glass ports
shall be installed above the compressor system. Provide 3/8 inch angle service valves
on top and bottom of reservoir. Install Reservoir Pressure Valve on top of reservoir and
pipe to suction header. Provide manufacturer's standard filter on oil return line to oil level
regulators.
7. Separator/Reservoir: As an alternate to paragraphs above, an oil separator-reservoir
assembly similar to the Hussmann "TurboShed" system is acceptable. This type of
system shall consist of a combination separator-reservoir assembly and oil pressure
regulation valve.
8. Oil Regulators: On each compressor, provide an adjustable oil level regulator with shut-
off valve on each inlet. This will allow removal of individual compressors without shutting
down the whole system.
9. Manifolds: Liquid and suction manifolds shall be provided on each multiplex system.
Each manifold shall have the required number of service valves to permit servicing unit
coolers and display cases. Each manifold shall have one spare 5/8 inch liquid stub and
1-3/8 inch suction stub. Each service valve shall have a full ported gauge port which can
be closed by back-seating the valve and a front seat which can close-off the line
connected to the manifold. Service valves shall have a removable cap over the valve
stem. Insulate suction header-manifolds with 3/4 inch thick unicellular plastic insulation.
10. Subcoolers: One subcooler will be provided on each low temperature multiplex system.
They will be piped on site to the medium temperature multiplex system with the highest
design suction temperature, as indicated on contract drawings <insert sheet number>
through <insert sheet number>. Subcoolers shall be plate type heat exchangers.
11. Electronic Evaporator Pressure Regulators (EEPR): EEPR valves shall be installed when
indicated on refrigeration schedules. Unless otherwise noted on the refrigeration
schedule, the EEPR valve shall be installed at the compressor systems. Provide on each
EEPR valve a Schrader type valve so upstream pressure can be measured with a gauge.
Wiring from the EEPR shall be run to the RMCS for control. See Division 23 Section
Refrigeration Monitoring and Control System (RMCS).
***Use horizontal receiver where it is desirable to reduce the height of the condensers as
when mechanical centers are roof mounted***
12. Receiver: Liquid receivers shall be [vertical or] horizontal-type, designed, and rated in
accordance with the recommendations of ANSI/AHRI Standard 495-2005, except as
modified herein. The receiver shall be constructed and tested in accordance with
requirements of Section VIII of the ASME Boiler and Pressure Vessel Code. Each
receiver shall be equipped with inlet, outlet drop pipe, service ports on inlet and outlet,
purging valve, relief valves of capacity and setting required by ANSI/ASHRAE Standard
15-2010. Provide calculations on receiver capacity sizing. On multiplex systems, provide
liquid level gauge or liquid level indicators on receivers. Each receiver should have a
storage capacity not less than 500 lbs at 80 percent capacity. Each receiver shall have
an analog liquid level sensor connected to the RMCS. See Division 23 Section
Refrigeration Monitoring and Control System (RMCS).
13. Suction Accumulator: On multiplex systems, suction accumulators shall be installed and
shall be designed within the suction header to provide a positive trap for liquid carry-over
and to assure oil return to compressor. The accumulator internal liquid holding volume
shall be at least 0.4 cubic feet. Design shall insure that oil is not trapped in the
accumulator.
14. Pressure Tap: Provide on discharge line, receiver inlet, and suction manifolds a 1/8 inch
FPT with shut-off valve for installation of pressure transducers.
***Edit this section when Distributed parallel system is used for remote bakery/Deli, etc.
Delete if not used
A. Location:
1. Indoor applications shall have vertical frame and housing to maximize floor space and be
located per Drawing.
2. Outdoor and warehouse applications shall have either vertical or horizontal frame and
housing and be located per Drawing.
C. Compressor Accessories:
A. Performance Standard: Condensing units shall be as described herein and in the schedule.
Each unit shall conform to and shall consist of the equipment and accessories as listed in
ANSI/AHRI Standard 520-2004, Performance Rating of Positive Displacement Condensing
Units. The units shall be tested and rated in accordance with ANSI/ASHRAE Standard 23-2005
(Methods of Testing for Rating Positive Displacement Refrigerant Compressors and
Condensing Units).
B. Capacity Selection: Air-cooled condensing unit shall be sized for a maximum condensing
temperature of 15 deg F above ambient temperature. Condensers shall have a maximum of 12
fins per inch.
D. Condenser: Condenser tubes shall be copper with [copper] [aluminum] fins. Where
condensing units are to be installed within 30 miles of a salt water body of water, condensers
are to have copper fins.
E. Head Pressure Control: Provide head pressure controls. Condensing pressure controls shall
enable condensing temperature to drop from that indicated on Drawings to 90 deg F, shall
maintain proper condensing temperatures at outdoor temperatures down to 0 deg F, and shall
be automatic in operation without daily or seasonal adjustment. To maintain desired
condensing temperatures, variable speed or standard condenser fan controls shall be provided
along with a receiver heater Suction Accumulator: Suction accumulator shall be installed on
condensing units serving unit coolers with electric defrost.
F. Receivers: Receivers shall have a storage capacity not less than 20 percent in excess of the
following: refrigerant (liquid) in liquid line(s); refrigerant (vapor) in evaporator and discharge
line; refrigerant (liquid) in condenser drain line; refrigerant (liquid) in condenser circuit (100
percent flooded); and sufficient liquid seal of at least 20 percent in receiver with the above
conditions.
2.4 CONTROLS
A. Scope: Controls shall include those required for automatic operation of each compressor, air-
cooled condenser, and defrost cycle as specified herein, as indicated under Division 23 Section
Refrigeration Monitoring and Control System (RMCS), as indicated on the Drawings, and as
recommended by the manufacturer of the insulated cold storage room unit coolers and
refrigerated display cases.
B. Factory Controls Installation: The compressor system manufacturer shall factory mount, install,
and test each ICU installed on each compressor system. See Division 23 Section Refrigeration
Monitoring and Control System (RMCS).
C. Voltage/Interface: Control voltage for compressor control circuits, condenser control circuits,
heat reclaim control valves, and liquid line solenoid valves shall be 208 volts 60 Hz. The RMCS
shall be interfaced to these control circuits using relays.
D. Back-up Controls: Each compressor on the system shall have a conventional low pressure
control wired in series with controls provided under the Refrigeration Monitor and Control
System. Low-pressure control shall have automatic reset and micro adjustable cut-in and cut-
out range. Use ultra cap super hose or approved equal.
E. High Pressure Control: Each compressor shall have a single high-pressure control with manual
reset, adjustable set-point, and auxiliary alarm contact. Use ultra cap super hose or approved
equal.
F. Heat Reclaim: Heat recovery coil circuits shall be "pumped out" when circuit is not in heat
reclaim. RMCS controls on compressor system shall have adjustable lockout set points.
G. Head Pressure Control. Automatic condensing pressure controls shall be provided to enable
the condensing temperature to drop from that indicated on Drawings to 75 deg F. They will
maintain proper condensing temperatures at outdoor temperatures down to 0 deg F and shall
be automatic in operation without daily or seasonal adjustment. Head pressure controls,
consisting of modulating valves and bypass check valves, shall be provided to control head
pressure by flooding the condenser coil with liquid refrigerant to maintain desired condensing
temperatures. On upstream pressure regulating valves, provide a schrader type of valve to
measure upstream pressure on regulating valve.
J. Fixture and Unit Cooler Suction Pressure Control: Suction pressure control shall be by the
RMCS via an EEPR valve for each system. EEPR valves are installed on the compressor
system, unless otherwise noted on Drawings, and wired through an interface board to the
RMCS.
***A-E shall edit to provide copper finned coil with stainless steel end plates within 30 miles
of saltwater
C. Coils: The condenser coil shall be of the extended-surface fin-and-tube type and constructed of
seamless copper tubes with [aluminum] [copper] fins [and stainless steel end plates]. The
fins shall be soldered or mechanically bonded to the tubes and installed in a metal casing.
Condenser coil shall have a maximum of 10 fins per inch. The coil shall be dried to remove free
moisture and capped to prevent entrance of foreign matter. A purging valve shall be installed
on top of the inverted trap of the refrigerant inlet to condenser.
D. Fans: Fans shall be the propeller-type, directly connected to the motor shaft and statically and
dynamically balanced.
E. Cabinets and Structures: [Aluminum or galvanized steel panels with baked enamel finish
and rigid internal channel frame fully gasketed joints. Structural members shall be
minimum 18 gage].
F. Cabinets and Structures: [Aluminum or stainless steel panels with rigid internal stainless
steel or aluminum channel frame, fully gasketed joints. All internal and external
surfaces, structural elements, and fasteners shall be aluminum or stainless steel. Fans
shall be aluminum or epoxy coated steel].
G. Motors: Provide premium efficiency 850 rpm electric motors not to exceed 1.0 hp per 30 inch
diameter fan. Motors shall be totally enclosed or open drip-proof type so located within an
enclosure as to be fully protected from the weather. Motor starters shall be magnetic, across-
the-line type with a general-purpose enclosure. Motors shall have built-in overload protection
and breaker protection. Control circuit on 480 VAC condenser motors shall be 208 VAC
maximum. Provide transformer at condenser for 208 VAC control.
H. Capacity: Sizing of the condensers for full capacity at design conditions shall be based on the
following:
I. Fan Control: On multiplex compressor systems, condenser fans shall be located so that each
refrigerant circuit of a compressor system is under a set of fans which, when cycled, shall not
affect another compressor system. The first fan at the header end of the condenser shall be first
"ON" and last "OFF". Other fans shall be controlled by the RMCS (see Division 23 Section
Refrigeration Monitoring and Control System (RMCS)). Provide motor starters for each fan.
J. Low Ambient Capacity Control: In climates with the winter design temperature lower than 30
deg F. Condensers with a heat of rejection capacity greater than 23 MBH at 1 inch TD shall
have a 50 percent /50 percent split header to circuit OFF 50 percent of the condenser at the
RMCS programmed low outdoor ambient setpoint.
K. Receiver for Distributed Parallel Systems: Liquid receivers shall be horizontal-type, designed,
and rated in accordance with the recommendations of ANSI/AHRI Standard 495-2005, except
as modified herein. The receiver shall be constructed and tested in accordance with
requirements of Section VIII of the ASME Boiler and Pressure Vessel Code. Each receiver
shall be equipped with inlet, outlet drop pipe, service ports on inlet and outlet, purging valve,
relief valves of capacity and setting required by ANSI/ASHRAE 15-2010, provide liquid level
gauge or liquid level indicators on receivers. All receivers shall be insulated and shall have
white Armaflex paint, or equivalent, to protect from UV rays. For distributed systems containing
6 compressors or less, maximum receiver capacity at 80 percent full shall be 174 lbs. Systems
up to 8 compressors shall have receiver maximum capacity ratings at 80 percent full of 261 lbs.
or less. Ratings are based on R-404A refrigerant.
A. Heat recovery coils shall be furnished as an integral part of the product refrigeration system and
shall be approved by the display case manufacturer who shall coordinate the installation of heat
recovery coils with the HVAC.
B. Circuiting: Coils shall be single or multi-circuited as required and shall comply with the
requirements outlined under condensers above. Coils shall be mounted for counter-flow
service.
C. Valves: Diverting valves for heat recovery shall be furnished by display case manufacturer.
D. Controls: Other controls for the heat recovery are specified in Division 23 Section Refrigeration
Monitoring and Control System (RMCS).
E. Capacity: Heat recovery coils shall be sized for the capacity of circuits as indicated on Drawings
and rated at 27 F degrees temperature difference. Required refrigerant pressure drop across
the coil shall not exceed 9 psi between the inlet and outlet header. Static air pressure drop
across the coil shall not exceed .4 inch of water. Coils shall have a maximum of 12 fins per inch.
Tubing joints shall be brazed with silver brazing alloy. Performance of heat recovery coils shall
be as scheduled on Drawings.
***Do not use this type of heat reclaim water heater where there is limited space available.
A. As indicated on Contract Drawings, provide heat reclaim water heater(s). The units shall be
integrated into the product refrigeration system for maximum utilization. The refrigerant circuit
shall be rated for 400 psi. The unit shall be equivalent to "Therma-Stor" II-1.
B. Heat exchanger shall be glass lined 119 gallon storage tanks with heat exchanger wrapped
around the tank with double wall construction. Insulate tank with 2 inch foam insulation.
C. Controls as necessary to maintain water temperature in storage tank and heat pressure, shall
be provided by display case manufacturer.
D. The heat reclaim water heaters shall be furnished as an integral part of the product refrigeration
system and approved by the display case manufacturer.
A. Fabrication: Unit coolers shall be the suspended type. Each unit cooler shall be self-contained,
enclosed in a suitable metallic casing which is the manufacturer's standard. Unit coolers shall
be quiet in operation. Fans shall be of the propeller type directly connected to the motor shaft.
Evaporator coils shall have copper tubes and aluminum fins.
B. Heat Exchangers: Heat exchangers shall be provided on unit coolers to sub-cool liquid
refrigerant and shall be sized for each unit cooler at the operating conditions.
C. Capacity: Capacities of unit coolers after derating for motor heat shall be not less than required
to meet or exceed the refrigerated room loads indicated on the Drawings and based on the
operating conditions specified. The quantity of unit cooler(s) required, temperature difference,
fins per inch, capacities and the type of airflow (Type I or II), and type of defrost shall be as
indicated on Drawings.
D. Valves: Unit coolers shall have a liquid line shut-off valve (soldered type). Provide Schrader
type valve with cap on suction outlet of unit cooler. Provide balanced port thermal expansion
valve (sweat fitting) with removable screen for each unit cooler, properly sized and designed for
use with the type of refrigerant indicated.
E. Motors: Provide premium efficiency 208/230V ECM (electrically commutated motors) fan
motors. Shaded pole motors are not acceptable.
F. Filter Drier: Provide a (sweat type) filter drier at inlet of each expansion valve. Filter drier shall
filter contaminants down to 20 microns. Flow capacity shall meet coil requirements.
A. Install all compressor systems, supporting electrical panels and transformers as well as other
supporting equipment, heat recovery water heaters, [gas fired water heaters] and related
equipment in [grade] [roof] mounted mechanical center[s]. These mechanical centers shall be
factory prefabricated, prepiped and prewired ready to set in place, and requiring only single
point electrical and piping connection. All RMCS wiring is to be installed in electrical metallic
tubing (EMT) conduit.
1. [Roof curb] [Grade mounting frame] and structural attachment points coordinated with
the building structure to assure adequate wind and seismic resistance. See Division 01
Section Summary of Work.
2. Adequate service lighting (30 foot candles at the compressors) and battery backed
emergency lighting.
3. Ventilation designed for 100 cfm per compressor horsepower. Inlet louvers (rain proof)
[with motorized dampers] shall be located on one side of the center with sidewall
exhaust fans with motorized dampers on the opposite side and offset lengthwise to draw
air over the compressor racks, all in accord with Division 23.
4. [Structural steel for locating air cooled condensers on the roof of the center and
OSHA compliant catwalks a minimum of 24 inch wide, 12 gauge, grip strut,
diamond plank with ladders and 1-1/2 inch diameter hand rails and intermediate
rails.]
5. All necessary electrical panels, transformers, wiring, etc. required to support the Product
Refrigeration system.
6. Heat recovery water heaters, [gas fired water heaters, circulating pumps,] piped to
the point of connection to the building. All plumbing equipment, piping, insulation, etc.
shall be in accord with Division 22.
7. Doors sized and located to facilitate replacement of equipment.
8. Trolley and track the length of the center with hoist to handle compressors.
9. R-6 insulated corrugated galvanized steel wall and roof panels with factory baked enamel
finish in color as selected by the contracting officer. Flame spread/smoke developed
shall not exceed 25/50 by ASTM E84.
10. 3/16 inch steel plate floor [with the curb below the floor filled with 6 pound density
board insulation for noise control].
A. General:
1. Scope: The Work includes the furnishing, installing, and adjusting of the display cases
and accessories indicated, specified, or necessary for operation. The material,
equipment, and appurtenances specified herein shall be the standard products of an
established manufacturer and shall have a history of satisfactory commercial operating
service.
2. Basis-of-Design Products: To establish the significant qualities related to type, function,
dimension, in-service performance, physical properties, appearance, and other
characteristics for purposes of evaluating comparable products of other manufacturers, a
specific manufacturers product is named and accompanied by the words "basis-of-
design", including make or model number or other designation. Subject to compliance
with requirements, provide either the named products or equal products.
3. Standards: Case ratings shall be based on ANSI/AHRI 1200-2010, "Performance Rating
of Commercial Refrigerated Display Merchandisers and Storage Cabinets." Or
ANSI/ASHRAE Standard 72-2005, "Method of Testing Commercial Refrigerators and
Freezers." The ratings which shall be employed are for a store environment of 75 deg F
dry bulb and 55 percent relative humidity.
4. Temperature performance shall be based on the product temperatures maintained by the
display cases. The intended result is preservation of the foods in such a fashion as is
generally considered acceptable for displayed retail foods.
5. Color: Color of display cases interior and exterior, end panels and toe panels (kicks) shall
be as specified in the Contract Drawings and approved by the Contracting Officer. See
Architectural finish schedule for colors.
6. Accessibility: Cooling coils, thermal expansion valves, air circulators, and drains shall be
accessible for ease of maintenance, removal, and replacement.
7. Insulation: Spaces between inner and outer walls of basic case shall be completely filled
with not less than 2 inch of polyurethane insulation foamed in place throughout, including
end panels. Insulation "K" factor shall be equivalent to 0.13 BTU deg F, per inch of
thickness. Insulation shall be enclosed and waterproofed to prevent moisture
penetration, and allow high pressure spray cleaning without damage to insulation.
8. All sheet metal and framing to be galvanized steel, stainless steel or anodized aluminum.
9. Floor Air Gap: Where return air for HVAC is drawn from under a refrigerated display
case, that case shall be equipped for return air with a 1 inch opening the full length of the
case.
10. End Panels: Cases located adjacent to solid walls shall have boxed end panels. Cases
with exposed ends shall have contour end panels coordinated with case profile See
Architectural finish schedule for colors.
11. Mirrored Panels: End panels on produce cases shall have a mirror on panel side towards
the product.
12. Local Thermometers: Provide and install a solar powered digital thermometer with a
minimum 3/8 inch high display to read entering air temperature on each display case.
Provide one digital thermometer for each side of the 1G07 display cases.
13. Descriptive dimensions of display cases are only approximate. Some variation is
permissible. However, minimum product capacity requirements shall be met or
exceeded.
14. Controls: For controls, see Refrigeration Drawings, and Division 23 Section Refrigeration
Monitoring and Control System (RMCS). Provide a sensor in each refrigerated case, pre-
wired at the factory.
15. Exterior Material: The exterior of the display case shall not be less than 20 gauge steel
finished in baked porcelain enamel, baked refrigerator synthetic enamel, baked acrylic
29. Transparent reach-in doors shall be of triple-pane glass with either heat-reflective treated
glass or gas fill requiring no anti-sweat heaters to prevent external condensation in stores
with less than 60 percent relative humidity. The door frames shall be constructed of non
conductive composite material (Hussmann Innovator II) or insulated aluminum with
thermal break (Anthony Innovator II) or similar construction requiring heat only to prevent
freezing of the door gasket seal.
30. Night curtains shall be provided on all multideck cases except 1P07. Standard is Super
Market Energy Technologies "Night Shield Night Covers" magnetically mounted,
manually operated, spring loaded, retractable, anti-bacterial treated, aluminized fabric
screen. The screens shall be integrated into the design of the case so that they are
concealed form view when retracted.
NOTE: The Contract Documents reflect dimensions based on a single manufacturers fixture
sizes and required clearances as "Basis-of-Design". If display cases from another
manufacturer are provided, it will be necessary to adjust contract document dimensions
accordingly. This will include, but is not limited to length, width, and height of display case
openings and adjacent spaces/fixtures. Shop drawings shall accurately reflect all required
changes for coordination with affected construction trades (i.e. plumbing, electrical, HVAC,
etc.).
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
2) Height: 49 inches.
3) Depth: 39-1/2 inches.
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
2) Height: 49 inches.
3) Depth: 39-1/2 inches.
a. Nominal Dimensions:
1) Length:
***DESIGN NOTE***
Self-contained case shall be Hussmann HGL which has a totally different profile and
appearance. Substitute the following paragraphs for (2) above:
1) Length:
3. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
2) Height: 49 inches.
3) Depth: 39-1/2 inches.
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
b. Lights: Two rows of fluorescent lights in top of case and one row beneath each
shelf the length of case.
c. Shelving: Two 12 inch or one 12 inch and one 10 inch stainless steel or epoxy
coated mezzanine shelves full length of case.
d. Glass Front: Curved, lift up design, lockable, with fully gasketed perimeter.
e. Sliding glass rear doors, lockable.
f. Wrapping Board: Full length at rear of case.
g. 9 inch deep package ledge continuous on front of case.
h. Mirrored inside end panels.
i. Convenience Outlet: 120V duplex receptacle for scales.
j. Designed to maintain average product temperature of 36 deg F.
k. Maximum refrigeration load for parallel system 375 B/hr/lf.
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
***DESIGN NOTE***
Self-contained case shall be Hussmann HGM which has a totally different profile and
appearance. Substitute the following paragraphs for (2) above:
a. Bottom mounted air cooled condensing unit, designed to slide out for ease of
maintenance, electronic temperature control, defrost controls, and anti-
condensation heaters and condensate pan.
b. Electrical requirement 208V, single phase.
c. Self-contained refrigeration designed to maintain a product temperature of 30 to 36
deg F with Case to be provided without requirement for floor drain to allow mobility
for relocation. Seamless, non-corrosive electric condensate dissipater pan shall
be included.
1) Length:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
a) 1D07-A: 48 inches.
b) 1D07-B: 72 inches.
c) 1D07-C: 96 inches.
2) Height: 44 inches.
3) Width: 60 inches.
b. Case to be provided with refrigerated rear storage compartment, rear work table,
and swivel castors.
c. Self-contained refrigeration designed to maintain a product temperature of 33 to 38
deg F for specialty sandwiches or sushi. With bottom mounted air cooled
condensing unit, designed to slide out for ease of maintenance, electric
temperature control, defrost controls, and anti-condensation heaters and
condensate pan.
d. Electrical requirement 120V, 60 Hertz, single phase.
e. Case does not require a floor drain, uses an electric condensate dissipator pan.
f. Place a label in the bottom of the case every 3 feet behind the front sill stating "Do
not flush with water. There is no direct drain connection and the floor will be
flooded."
g. Provide power cord.
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
a) 1D22-8: 96 inches.
b) 1D22-12: 144 inches.
b. Product display depth to be a minimum of 5 inch with adjustable angle wire racks.
c. Case to be provided with one adjustable wire rack and one non-refrigerated top
display area.
d. Curved 9-7/8 inch high Plexiglas perimeter.
e. Color shall be as indicated on Architectural Drawings.
f. Self-contained refrigeration designed to maintain a product temperature of 28 to 34
deg F for fresh meat, 34 to 38 deg F for prepak meat or deli foods. With bottom
mounted air cooled condensing unit, designed to slide out for ease of
maintenance, electric temperature control, defrost controls, and anti-condensation
heaters and condensate pan.
g. Electrical requirement 208V, single phase.
h. Case to be provided without requirement for floor drain to allow mobility for
relocation. Seamless, non-corrosive electric condensate dissipater pan shall be
included.
i. Place a label in the bottom of the case every 3 feet behind the front sill stating "Do
not flush with water. There is no direct drain connection and the floor will be
flooded."
j. Provide power cord with suitable twist lock plug and receptacle.
J. 1D24 Case, Low Profile, Prepackaged Deli, Multi-Deck, 8 Foot Medium Temperature, Open
Type:
1. Salient Characteristics:
a. Nominal Dimensions:
K. 1F00-8,-12, Case, Fresh Fish, Refrigerated, Medium Temperature, Clerk Service, 8 or 12 Foot:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
2) Height: 52 inches.
3) Depth: 44-5/8 inches.
4) Sill height: 22-1/2 inches.
b. Two rows of fluorescent light on top of case for the length of the case.
c. Lift up, curved tempered front glass. Glass must be lockable.
d. 4 or 6 rear service removable glass sliding doors. Lockable doors must be
furnished.
e. A 7 inch to 10 inch deep high density polyethylene food wrapping shelf that is the
full length rear of the case, duplex receptacles (120 volts) required on rear mullions
for display scales and printer.
f. Stainless steel interior, stainless steel adjustable ice trays, bottom rack and drain
pan; bottom flushing system with a timer clock; perimeter heater and ice guard for
front glass.
g. Designed to maintain a product temperature of 28 to 32 deg F. Blower coil type.
Top gravity coil and bottom serpentine coil.
h. Maximum refrigeration load for parallel system 380 B/hr/lf.
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
M. 1G00B-8, -12 Case, Cheese, Island, Medium Temperature, 8 or 12 Foot, Open Type:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
a) 1G00B-8: 96 inches.
b) 1G00B-12: 144 inches.
b. Case to be a unitized island case with refrigerated ends and glass front. Case to
have rounded outside corners.
c. Adjustable epoxy coated wire racks capable of permitting shallow displays in at
least three positions.
d. Front edges of deck equipped with price tag molding to hold standard size price
tags/labels.
e. Designed to maintain a product temperature of 34 to 36 deg F.
f. [Case to be provided with superstructure for multilevel display shelving.]
g. Maximum refrigeration load for parallel system 780 B/hr/lf.
N. 1G02-8, 12 Case, Dairy, Multi-Deck, Front Load, Medium Temperature, Open Type, 8 or 12
Foot:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
O. 1G02-8, 12 Case, Dairy, Multi-Deck, Rear Load, Medium Temperature, Open Type:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
P. 1G03-6, -8, -10, -12 Case, Cheese, Island, Self-Contained, Medium Temperature, Open Type,
6, 8, 10, or 12:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
a) 1G03-6: 72 inches.
b) 1G03-8: 96 inches.
c) 1G03-10: 120 inches.
d) 1G03-12: 147 inches.
Q. 1G06 Case, Frozen Food, End Cap for Wide Island, Low Temperature:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
b. End caps shall be designed for compatibility and for wraparound appearance when
joined to the wide island frozen island food case described at CED 1G07-A and
1G07-B. Dimensions, materials, accessories, trim and finish shall match adjoining
cases.
c. Shelves: Epoxy coated bottom wire shelves: adjustable to at least three positions.
d. Designed to maintain a product temperature of -10 to 0 deg F.
e. Maximum refrigeration load for parallel system 1650 B/hr/case.
f. Each case shall be furnished with modular sliding glass covers as follows:
R. 1G07 Case, Frozen Food, Wide Island, Low Temperature, Open Type, 8 or 12 Foot:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
b. Shelves: Epoxy coated bottom wire shelves; adjustable to at least three positions.
c. Designed to maintain a product temperature of -10 to 0 deg F.
d. Maximum refrigeration load for parallel system 640 B/hr/lf.
e. Each case shall be furnished with modular sliding glass covers as follows:
S. 1G09-8, -12 Case, Frozen Food, Intermediate Island, Low Temperature, Open Type, 8 or 12
Foot:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
b. Shelves: Epoxy coated bottom wire shelves; adjustable to at least three positions.
c. Front edges of deck equipped with price tag molding to hold standard size price
tags/labels.
d. Designed to maintain a product temperature of 0 deg F.
e. Maximum refrigeration load for parallel system 380 B/hr/lf.
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
b. Lights: Vertical LED lighting assembly, one at each end and one between all
doors.
c. Shelves: Five solid adjustable upper shelves per door section with price tag
molding. One bottom epoxy coated wire rack per door section with price tag
molding.
d. Doors: constructed per paragraph 2.10.A.29, 67 inches high with magnetic
gaskets, automatic door closures, doors hinged on left side.
e. Designed to maintain a product temperature of 0 deg F.
f. Maximum refrigeration load for parallel system 1250 B/hr/door.
U. 1G12-2, 3, 4, 5 Case, Ice-Cream, Frozen Foods, Frozen Juice, 2, 3, 4, Or 5 Glass Doors, Low
Temperature, Upright:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
b. Lights: Vertical LED lighting assembly, one at each end and one between all
doors.
c. Shelves: Five solid adjustable upper shelves per door section with price tag
molding. One bottom epoxy coated wire rack per door section with price tag
molding.
d. Doors: constructed per paragraph 2.10.A.29, 67 inches high with magnetic
gaskets, automatic door closures, doors hinged on left side.
e. Designed to maintain a product temperature of -10 deg F.
f. Maximum refrigeration load for parallel system 1350 B/hr/door.
1. The 1G13-2, 3, 4, and 5 are the same as 1G12-2, 3, 4, and 5 respectively except that the
adjustable shelves shall be five tiers of solid shelves with 3 inch product lip designed to
display frozen juice.
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
a) 1G15-6: 74 inches.
b) 1G15-8: 96 inches.
c) 1G15-12: (2 - 72 inch cases).
2. Basis-of-Design Product:
1. Salient Characteristics:
a. Nominal Dimensions:
1. Salient Characteristics:
1) Length:
Z. 1G27-3,-4,-5 Case, Frozen Food, Back To Back, 3, 4, Or 5 Glass Doors Per Side:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
2) Height: 83 inches.
3) Depth: 72-3/8 inches.
4) Sill Height: 13-3/8 inches.
b. Lights: Vertical LED lighting assembly, one at each end and one between all
doors.
c. Shelves: Minimum of five 22-inch deep adjustable solid shelves per door section
with and price tag molding to hold standard price and UPC tags and labels. One
bottom wire rack per door section with price tag molding.
d. Doors: Constructed per paragraph 2.10.A.29, 67 inches high with magnetic
gaskets, automatic door closures, doors hinged on left side.
e. Designed to maintain a product temperature of 0 deg F.
f. Maximum refrigeration load for parallel system 1045 B/hr/door including both
sides.
AA. 1G28-3, 4, 5 Case, Ice-Cream, Frozen Foods, Frozen Juice, Back To Back, 3, 4, or 5 Glass
Doors Per Side, Low Temperature, Upright:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
2) Height: 83 inches.
3) Depth: 72-3/8 inches.
4) Sill Height: 13-3/8 inches.
b. Lights: Vertical LED lighting assembly, one at each end and one between all
doors.
BB. 1G30 -3,-4,-5 Case, Frozen Food, Back To Back, 3, 4, Or 5 Glass Doors Per Side, End Cap:
CC. 1G31 -3,-4,-5 Case, Ice Cream, Frozen Foods, Frozen Juice, Back To Back, 3, 4, or 5 Glass
Doors Per Side, Low Temperature, Upright, End Cap:
DD. 1M02-8, 12 Case, Fresh Meat, Single Deck, Medium Temperature, Open Type, 8 or 12 Foot:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
Note: Case shall match Fresh Meat line-up type including exterior dimensions. Case shall
be located in Fresh Meat line-up.
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
FF. 1M04-A Case, Meat Or Prepackaged Deli, Multi-Deck 6, 8, or 12 Foot, Remote, Medium
Temperature, Open Type:
1. Same as 1M04 except furnish with peg bar assembly and rear close-off/baffles. Include
six 15 inch pegs per each peg bar assembly.
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
HH. 1M07 Case, Meat, Multi-Deck, Medium Temperature, Open Type, 8 or 12 Foot:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
II. 1M07-F Case, Fresh Meat or Deli, Multi-Deck, Low Profile, Medium Temperature, With Shelves:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
b. Shelves: Two shelves, 14 inches top and 16 inches lower adjustable shelves
extending full length of case.
c. One or two full-length rows of fluorescent lighting at canopy.
d. Designed to maintain a product temperature of 28 to 34 deg F.
e. Front edges of shelves and deck equipped with price tag molding to hold standard
size price tags/labels.
f. Curved front panels.
JJ. 1M09-6, -8, -12 Case, Fresh Meat or Deli, Multi-Deck, Low Profile, 6, 8 Or 12 Foot, Remote,
Medium Temperature, with Two Shelves:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
b. Shelves: Two shelves, 14 inches top and 16 inches lower adjustable shelves
extending full length of case.
c. Two full-length row of fluorescent lighting at canopy.
d. Designed to maintain a product temperature of 28 to 34 deg F.
e. Front edges of shelves and deck equipped with price tag molding to hold standard
size price tags/labels.
f. Curved front panels.
g. Plexiglas shelf stops on each shelf.
h. Provide night curtains (2.10.A.30.).
i. Maximum refrigeration load for parallel system 1100 B/hr/lf.
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
2) Height: 44 inches.
3) Depth: 74 inches.
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
MM. 1P02-8, -12 Case, Produce, Medium Temperature, Open Type, One Shelf, 8 or 12 Foot:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
NN. 1P03-8, -12 Case, Produce, Single deck, Medium Temperature, 8 or 12 Foot:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
OO. 1P06 Case, Floral Merchandiser, 3 Glass Doors, Medium Temperature, Upright:
1. Salient Characteristics:
a. Nominal Dimensions:
PP. 1P07-8, -12 Case, Produce, Pre-cut Packaged Vegetables and Juices, Upright, Refrigerated, 5
Adjustable Upper Shelves, 8 or 12 Foot:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
1) Three clear or black color acrylic product dividers per four foot section of
shelf.
2) Three inch high wire or acrylic front product stop, the entire length of each
shelf.
3) Price Tag Molding: On front of each shelf.
QQ. 1P09-6, -8, -12 Case, Produce, Multi-Deck, Self-Contained, Medium Temperature, Open Type,
6, 8 or 12 Foot:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
a) 1P09-6: 72 inches.
2) Height: 79 inches.
3) Depth: 43 inches.
4) Height of front shall be 26 to 30 inches.
b. Shelves: Four levels of display with 3 rows upper adjustable shelves extending full
length of case.
c. One full-length row of fluorescent lighting at canopy as well as individual shelves.
d. Self-contained refrigeration sized to maintain a product temperature of 34 to 38
deg F with bottom mounted air cooled condensing unit, designed to slide out for
ease of maintenance, electronic temperature control, defrost controls, and anti-
condensation heaters and condensate pan.
e. Electrical Requirements (default) are 208-230V, 60HZ, 1 phase, with (30 amp)
NEMA L14-30 plug.
f. Front edges of shelves and deck equipped with price tag molding to hold standard
size price tags/labels.
g. Quick disconnect fitting for water hose. Furnish one 24 foot water hose with shutoff
spray nozzle for each 6 cases.
RR. 1P11-6, -8, -12 Case, Produce, Single-Deck, Low Profile, Refrigeration Medium Temperature,
Open Type, 6, 8 or 12 Foot:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
2. Basis-of-Design Product:
1. Salient Characteristics:
a. Nominal Dimensions:
1) Length:
2) Height: 98 inches.
3) Depth: 40 inches.
1. Salient Characteristics:
a. Controller designed to control water flow upon direction from the timer mechanism.
b. Controller designed to be mounted separately from the timer by as much as fifty
feet apart.
c. Water shut off valve for service.
d. Controller to operate concurrently with the reverse osmosis unit.
e. Timer:
f. Tunes:
g. Mist Bars:
1) Reverse osmosis (RO) system with a minimum capacity of 600 GPD (gallon
per day), expandable to 900 GPD.
2) Compact unit in an enclosed powder coated metal box for easy mounting in
a produce prep room.
3) Provided with quick connect water fittings.
4) Four pre-filters: one 50-micron sediment filter, two 5-micron wrapped carbon
filters, and one 5-micron sediment filter.
5) Self-diagnostic filter replacement notification system with a "call for service"
light and a reset button.
A. Scope: The refrigeration piping system shall consist of HVAC and product piping systems and
heat reclaim piping systems handling fluorocarbon refrigerants.
C. Quality Assurance: Tubing delivered to the job site or found on the job site without capped ends
shall be tagged and rejected from installation on this project.
D. Accessories:
1. Product Standards: Refrigerant piping, valves, fittings, and accessories shall conform to
the requirements of ANSI/ASHRAE Standard 15-2010, and ANSI B31.5unless otherwise
specified.
2. Fittings: Fittings for brazed joints shall be wrought copper or forged-brass sweat fittings.
Cast sweat-type fittings shall not be allowed for brazed joints. Ells shall be of long radius
type. No 45 degree elbows shall be used.
3. Hand Valves: Refrigerant shut-off valves shall be designed for use with the refrigerant
used and shall have pressure ratings compatible with system pressures encountered.
Gate valves shall not be acceptable. Valves shall be all brass, handwheel-operated,
diaphragm, packless-type, globe or angle valves in sizes up to and including 5/8 inch.
For valves 5/8 inch and larger, ball valves designed specifically for refrigerant service
shall be used.
4. Check Valves: Check valves shall be steel or brass body, lift or swing type suitable for
refrigerant liquid or gas service.
5. Solenoid Vales: Solenoid valves shall be bronze, brass or steel body, packless type, with
stainless-steel trim, rated for continuous-duty service, direct or pilot operated, provided
with manual lift stem and designed for or use with the type of refrigerant used. Valves
shall have a safe working pressure of 400 psi and a maximum operating pressure
differential of at least 200 psi at 85 percent of rated voltage. Valves shall have an
operating pressure differential suitable for the refrigerant used. Valves shall have
adequate capacity for the installation at a pressure drop suitable for the refrigerant used.
Solenoids shall have moisture proof insulation and shall be UL approved.
6. Expansion valves (sweat fitting) shall be designed for use with the type of refrigerant
used and with a pressure rating suitable for the pressure encountered. The valves shall
be of the thermostatic type, diaphragm or bellows operated, with removable screens and
external super heat adjustment set at the factory for 10 deg F super heat. Power
elements and valve size shall be as recommended by the manufacturer for the service
intended. Multi range expansion valves are not acceptable.
1. Suction lines operating above 0 deg F saturated suction temperature (SST) shall be
insulated with elastomeric pipe insulation with wall thickness of 1 inch. Where the 2.5
percent design wet bulb temperature exceeds 78 deg F insulation wall thickness shall be
1.5 inch.
2. Suction lines operating at a 0 deg F and lower shall be insulated with elastomeric pipe
insulation of 1 inch wall thickness.
B. Refrigerant Liquid Lines: Liquid lines shall be insulated with elastomeric pipe insulation with 1/2
inch wall thickness. Liquid lines in return air tunnels, ducts, refrigerated cases, and walk-in
boxes do not require insulation.
C. Drains on Unit Coolers in Refrigerated Rooms: In refrigerated rooms that operate at less than
32 deg F, drains shall be insulated with elastomeric pipe insulation with 1/2 inch wall thickness.
D. Elastomeric Pipe Insulation Standard: Elastomeric flexible pipe insulation. Flame-spread rating
not greater than 25 and a smoke-developed rating not greater than 50. Insulation shall have a
K factor of .28 or less at 75 deg F mean temperature. Insulation shall have a water vapor
permeability of .10 or less and a water absorption by volume of 1 percent or less. Insulation
shall be assembled with all-temperature adhesive (Armstrong 520 or equivalent). Splitting of
joints of insulation is not allowed except for the outer layer of two layer pipe insulation where the
total thickness exceeds 1 inch. Butt joints of insulation shall not be sealed until pressure tests
and leak tests are completed. Insulation installed outdoors and subject to water damage shall
be provided with an additional (0.016 inch aluminum jacket with lock seam longitudinal joint and
stainless steel "Bandit" straps for butted joints as required for a water-tight installation.
E. Refrigerant Hot Gas Lines: Hot gas lines from the compressor systems to heat recovery coils
shall be insulated with 1 inch of fiberglass. Outlet lines on heat recovery coils do not require
insulation. Fiberglass insulation shall be installed after pressure and leak tests are completed.
Refrigerant line leaving heat reclaim coil does not require insulation.
F. Fiberglass Insulation Standard: Fiberglass insulation shall have composite (insulation, jacket or
facing, and adhesive used to adhere the facing or jacket to the insulation) fire rating of 25 and
smoke hazard rating of 50 as tested by procedure ASTM E-84, NFPA 225 or UL 723. Insulation
material should have a maximum K factor of 0.28 or less at 75 deg F mean temperature with
factory-applied fire retardant vapor barrier jacket. Jacking materials installed in exposed
locations (mechanical equipment rooms, exposed in finished areas, etc.) shall be Owens-
Corning ASJ or pre-sized glass cloth, neither requiring painting but suitable or direct application
of finish without surface preparation. Jackets furnished for installation in concealed locations (in
chases, above ceiling, etc. may be ASJ or FRJ. ASJ and FRJ jackets shall have self-sealing
joints. Insulation shall be provided with a vapor barrier having vapor permeability rating suitable
for the service intended, and joints shall be properly sealed.
G. Insulation installed outdoors shall be provided with an additional 0.016 inch aluminum jacket
with lock seam longitudinal joint and stainless steel "Bandit" straps for butted joints as required
for a water-tight installation.
1. Furnish the refrigeration compressor units, condensers, heat recovery coils, heat reclaim
hot water heaters, diverting valves for heat recovery, unit coolers, display cases and
RMCS.
2. Coordination: Coordinate the installation of the total refrigeration system.
3. Submittal: Shall review the construction project Electrical Drawings and Specifications
and provide electrical power and control wiring and refrigeration piping not specifically
provided for in the Drawings and Specifications.
4. Factory Testing: Shall factory mount, install, and test the control system for each
compressor system.
5. Interim Inspections/Reports: An Employee of the Display Case Manufacturer, not of the
dealer or installing contractor, shall conduct inspections of the installation of the product
refrigeration systems every 60 days beginning upon delivery of the first piece of
refrigeration equipment. Within 5 days after each inspection by the manufacturer, an
inspection report shall be submitted to the Contracting Officer. The inspection report
shall detail whether or not the product refrigeration equipment is being installed in
accordance with the Manufacturer's recommendations. All items of non-compliance
shall be noted on this report. failure to provide these reports in a timely manner may
result in the Contracting Officer's attainment of a manufacturer inspection visit and
subsequent deduction of payment from the Contractor. The representative shall have
been employed by the same manufacturer's which furnished the display cases, for a
minimum of two years and shall have a minimum of 5 years journeyman refrigeration
"hands on" experience.
6. Piping Certifications: A letter signed by the manufacturer of the display cases certifying
the piping is installed in accordance with the manufacturer's requirements shall be
submitted to the contracting officer prior to charging the systems with refrigerant. All
items of non-compliance shall be noted in this report.
7. Startup: Display case manufacturer's technical representative, not of the dealer or
installing contractor, shall be provided to "fine tune" and commission the system prior to
conducting the five day performance test. For projects where the equipment is installed
in phases, the manufacturers representative shall inspect each major phase of
refrigeration work.
8. Final Certification: A letter signed by the manufacturer of the display cases certifying the
systems are installed in accordance with the manufacturer's requirements shall be
submitted to the contracting officer prior to final acceptance of the systems. All items of
non-compliance shall be noted in this letter.
9. The contractor installing the equipment must be an installer who is approved by the
display case manufacturer.
B. Contractor Experience: The installer shall have successfully completed not less than three
installations of equal or greater size and complexity within the past three years.
C. Mechanic's Experience: The installing contractor or subcontractor shall employ EPA certified
refrigeration mechanics to install the system. The mechanics installing the system shall have a
minimum of three years experience installing supermarket refrigeration systems. As part of the
submittal, the installing contractor shall furnish resumes and EPA certification of the key
D. Testing: Provide water tightness test(s) and pressure test(s) and performance test(s) per
paragraph 3.2, prior to stocking fixtures.
A. Product Delivery/Storage: The Contractor shall coordinate delivery of materials and equipment
with the construction schedule. Materials and equipment stored on site must be protected from
damage. Display cases, unit coolers, and compressor racks must be stored in a covered
storage area and be kept clean and dry until installed in the commissary.
B. System Identification: Compressor systems, unit coolers, condensers, heat reclaim coils, and
refrigerated display cases shall have a permanent metal or laminated plastic identification tag to
identify compressor system, refrigerant circuit numbers, and alarm probe. The identification
scheme must be coordinated with and match the RMCS system identification scheme. Letters
on tag shall be 1/4 inch to 3/8 inch in height. Mechanically fasten the tag.
D. Filter and Oil Change: Upon completion of the performance test, the Contractor shall perform
the following on each refrigeration system and show the removed filter-drier to the
Governments Designated Inspector:
E. Refrigerant Charge: Provide refrigerant charge to maintain not less than 30 percent receiver
level with heat reclaim "ON".
A. Comply with Division 26, especially Section Raceways and Boxes which limits the number of
conductors per conduit.
B. Scope: Provide all wiring for product refrigeration system including wiring necessary for
operation of system which is not specifically shown on drawings. All equipment shall have
disconnect switches.
C. Design Scope: In accordance with the Drawings and this Section of the Specification, the
Contractor shall have the electrical power wiring for the refrigeration system designed by the
engineering department of the display case manufacturer.
E. Grounding: Provide a grounding conductor in all branch circuit conduits. Do not use conduit as
the only means of grounding for the refrigeration electrical system.
G. Conductor Temperature Design Standard: All power wiring in the refrigeration compressor
rooms shall be designed for 9 deg F higher than the 1 percent ambient summer design
temperature.
H. Transformer Temperature Design Standard: All transformers provided for the refrigeration shall
have copper windings and shall be rated for 144 deg F temperature rise.
I. Breaker Ir Standard: Minimum interrupting rating (Ir, RMS) for refrigeration electrical feeders
and branch circuits circuit breakers shall be as follows:
J. Circuit Breaker:
K. Defrost Feeder Design Loading: The minimum size of feeder for 208V defrost panels shall be
as follows:
1. On multiplex compressor systems with 5 or less refrigeration circuits the feeder shall be
sized for the following combined loads: largest defrost load, control circuit on compressor
system, and unit cooler fan motor loads.
2. On multiplex compressor systems with more than 5 refrigeration circuits the feeder shall
be sized for the following combined loads: largest defrost load plus one other defrost
load, control circuit on compressor system, and unit cooler fan motor loads.
L. Penetrations: Seal electrical penetrations in walk-in boxes and display cases with silicon sealant
inside and outside of conduits. See Division 13 Section Cold Storage Rooms and Electrical
details.
A. Brazing Material: Copper joints shall be brazed with AWS BCUP5 (14.5-15.5 percent Silver)
Silver Braze and copper to brass or steel shall be brazed with AWS BAG4 (40 percent Silver).
B. Purging: During brazing operations, the tubing and fitting being brazed shall have a continuous
purge of dry nitrogen at a rate which will preclude oxidation of the tubing and fitting. Tubing and
fittings shall be properly cleaned prior to brazing. Copper tubing joints that are assembled on
the job site shall be assembled with fittings.
C. Cutting: Joints in copper tubing shall be cut square with tubing cutter, ends shall be reamed,
and fillings and dust removed from interior of pipe
D. Piping Design: Refrigeration piping shall be sized by the refrigeration equipment manufacturer
and shall be based on the following:
1. Pressure Drop Liquid and Discharge: Pressure drop in the liquid and discharge line shall
not be greater than 3 psi.
2. Pressure Drop Suction Line: Pressure drop in the suction line shall not be greater than 2
psi.
3. Velocity Suction line: Minimum gas velocity for horizontal suction line shall be 700 FPM
and 1500 FPM for vertical suction line.
4. Maximum velocity for liquid line from condenser to receiver line shall be 100 FPM.
5. Traps/Risers: Every suction riser shall have an oil trap sized the same as the horizontal
suction line. The oil trap shall be long radius wrought copper manufactured for use as a
trap. Traps constructed of several 90 degree elbows are not permitted. For risers
exceeding 16 feet a second trap shall be installed at the mid-point of the riser. Suction
and discharge horizontal lines shall be continuously pitched a minimum of 1/2 inch per 10
feet in the direction of flow.
6. The first three support points from the compressor racks of each piping circuit shall have
hydrazorb or equal clamps securing both suction and liquid lines to trapeze hangers with
other circuits. See DeCA detail "clamp assembly for uninsulated refrigeration line or
electrical conduit".
7. Condenser Piping: 50 percent/ 50 percent split:
a. Hot Gas Lines: Parallel and equivalent, hot gas lines shall be installed to
accommodate condensers which are indicated for 50 percent / 50 percent
condenser split. See this Section and or contract drawings.
b. Liquid Lines: Parallel and equivalent, liquid lines shall be installed to accommodate
condensers which are indicated for 50 percent / 50 percent condenser split. See
this Section and or contact drawings.
8. Provide risers, traps, offsets, and drops as required to coordinate with the building
structure and the work of other trades.
E. System Cleanliness: Pipes, strainers, and valves shall be cleaned free of scale and thoroughly
flushed of foreign matter. Strainers and valves shall be thoroughly cleaned. The interior and
exterior (tubes and fins) of air-cooled condensers, evaporative condensers, unit coolers, and
display cases shall be thoroughly cleaned of debris and blown free of small particles of rubbish
and dust. Equipment shall be wiped clean, with oil, dust, dirt, and-or paint spots removed. It
shall be the responsibility of the Contractor to maintain the system in this clean condition until
final acceptance.
G. Fitting: Pipes shall be cut accurately to measurements established at the job site and worked
into place without springing or forcing, and properly clearing windows, doors, and other
openings. Pipes shall be installed to permit free expansions and contraction without damage to
joints or hangers. Changes in direction shall be made with fittings. Bent pipe showing kinks,
wrinkles, flattening or other malformations will not be accepted. Open ends of pipes or
equipment shall be properly capped or plugged during installation to keep dirt and other foreign
material out of the system.
H. Isolation Valves: Hand valves shall be installed on each side of each piece of equipment such
as compressors, heat recovery coils, hot water heater, heat exchanges, condensers, receivers,
and other similar items, and at other points indicated or required for maintenance, isolation,
charging, or sectionalizing purposes. Additional valves necessary for safe and proper operation
of the refrigeration system shall be included in the installation. Valves are not required on the
outlet of evaporators in cases and unit coolers.
I. Hangers: Pipe supports and hangers shall conform to the requirements of the Specifications.
Hangers shall be located within 3 feet of the ends of each run out, not over 1 foot from each
change of direction, and at intervals indicated on the Drawings in the table entitled "Pipe
Support Spacing for Refrigerant Piping."
A. Drains:
1. Union: Unit cooler drains shall be piped to be easily disconnected and to allow the drain
pan to be easily dropped for service.
2. Piping material shall be type L or M hard-drawn copper.
3. Traps: Traps are required on unit cooler condensate drains where the drains are
extended to a floor drain outside the room. Drains for unit coolers in frozen food and
carcass rooms storage shall be trapped outside of the room.
4. Heat tape: Heat tape and 1/2 inch unicellular plastic insulation is required on condensate
drains in rooms where temperature is maintained at 32 deg F or lower. Heat tape shall
be the type that regulates its own heat output as its temperature changes (FreezGard or
equivalent). Avoid piping drain lines above doorways. Maximum length of a drain line
shall be 50 feet.
5. Heat Exchanger: Provide a heat exchanger for each unit cooler.
6. Valves: Unit coolers shall have a liquid line shutoff valve (sweat type). Provide Schrader
type valve with cap on suction outlet of unit cooler. Provide balanced port thermal
expansion valve (sweat fitting) for each unit cooler, properly sized and designed for use
with the type of refrigerant indicated.
7. See unit cooler mounting detail.
B. Valves: Each refrigerated case having a remote compressor system shall have a liquid line
hand shutoff valve (solder type). Balanced port thermostatic expansion valve (sweat fitting). At
each TX valve bulb location, provide a Schrader type valve with cap.
E. Sensors: Probes for the alarm and monitoring system shall be pre-wired at the factory. Mount
probes in the discharge air at the center of the cases.
F. Each refrigerated display case shall have a decal or metal tag marking the location of the
thermal expansion valve, thermostat, and solenoid valve. The decal or metal tag shall be
placed on the lower part of the case or on the kick plate.
G. Close-off Panels: Provide close-off panels as necessary to ensure return air is only drawn from
the front of the display cases. Back to back display cases must be sealed with closure panels
at the top and sides of the display cases. Use stainless steel or other visually appealing
material for closure panels in visible locations.
H. Condensate Piping: Case drain piping shall be sized as recommended by the case
manufacturer. Drains shall be accessible for ease of maintenance. Except for seafood and rear
roll-in dairy case(s), drain pipe may be schedule 40 PVC or type M hard-drawn copper. On
seafood and roll-in dairy cases, use type M or L hard-drawn copper.
I. Condensate Drain Strainer: Provide a 1/4 inch mesh stainless steel strainer inside the case at
each drain. Secure strainer to drain.
J. Stat Location: When display case thermostats are required, install so that set-point adjustments
can be made without unloading or removing panels from the cases.
K. Partitions: Provide and install a plexiglass partition between display cases with electric defrost
which are connected to different refrigeration circuits. Partitions are to match interior of case.
Seal the edge joints.
M. Anti Condensate Fans: Where back to back display cases occur without floor level return air
pulled from under the cases; provide ventilation fans to circulate store air through this area.
N. Light Tube Covers: All lights in display cases require protective shields.
O. Produce Water Connection: Provide quick connect domestic cold water connection: Provide
and install quick connections for spraying water on the produce. Provide connection in every
1P02 produce case.
3.7 TESTING
A. Entire System: Upon completion of each refrigeration system, and at a time designated by the
Contracting Officer, refrigerant piping fabricated at the job site shall be pressure-tested for leaks
and the entire system shall be tested as hereinafter specified. The tests shall be conducted in
the presence of the Governments Designated Inspector. The Contractor shall furnish
instruments, test equipment, and personnel who are required for the tests.
1. Pressure Test: After components of the refrigerant system have been installed and the
piping connected, the total product refrigeration system shall be subjected to a pneumatic
test. The pneumatic testing shall be done by charging system with a sufficient amount of
anhydrous carbon dioxide or dry nitrogen to bring the pressure to 300 psi for high side
and 150 psi for low side. The system shall be proven tight and free of leaks by testing
joints with a halide or electronic leak detector and by allowing the leak test pressure to
remain on the system for 12 hours with no drop in pressure. Correction of .3 psi will be
allowed for each degree change in the initial and final temperature of the surrounding air,
plus for an increase and minus for a decrease.
2. Evacuation Test: After the foregoing tests have been satisfactorily completed and the
pressure relieved, the system shall be evacuated to an absolute pressure of 500 microns.
During evacuation of the system the ambient temperature shall be higher than 34 deg F.
No more than one system shall be evacuated at one time by one vacuum pump. When a
vacuum of 500 microns is obtained, close off vacuum pump for 30 minutes and observe
the magnitude and rate of pressure rise. If pressure continues to rise, check the system
for leaks, repair them, and repeat the evacuation procedure. If pressure rises to a point
and holds, but rises above 1000 microns, repeat the evacuation and close off procedure
until the rise is small enough to indicate that the system is dry. The Contractor shall
maintain records of test pressures and vacuum reading on each system and shall
indicate length of time test pressures and vacuums were maintained. This record shall
be submitted to the Contracting Officer at the completion of the pressure and leak tests.
3. Electronic Leak Test: Upon completion of the evacuation test, the vacuum shall be
broken by completely charging with dry refrigerant for which the system is designed and
shall be subjected to the performance tests and halide torch or electronic leak-detector
tests herein specified. Upon satisfactory completion of the tests, charge the systems with
adequate refrigerant to maintain a minimum of 20 percent receiver capacity reserve
during all operating conditions including simultaneous heat reclaim and condenser flood
back during cold weather operation. Loss of refrigerant during the warranty period shall
be guaranteed and refrigerant required shall be Contractor-furnished.
C. Case Water Tightness Test: Test the water tightness of all display cases joints and refrigeration
line penetrations with a hose stream of water. Conduct this test prior to cases start up and in
the presence of the Governments Designated Inspector. Provide written copy of test witnessed
by Governments Designated Inspector prior to turning cases over to government.
D. Performance Test: After the pressure tests have been completed, systems are operational, and
before the total product refrigeration system is accepted, performance tests to demonstrate the
capacity specified and general operating characteristics of equipment shall be conducted in the
presence of the Governments Designated Inspector, by a competent, experienced engineer
from the display case manufacturer who will attest the reliability of the results. The operational
test shall cover a period of not less than 5 days for each system and shall demonstrate that the
entire system is functioning in accordance with the Drawings and Specifications. Corrections
and adjustments shall be made as necessary to produce specified conditions. The Contractor
shall assure full responsibility for satisfactory operation of the integrated system. Typed,
tabulated data taken during the performance tests that indicate that the system will produce the
required capacity, shall be provided. Performance tests shall include the following specific
information in the report and conclusions regarding the adequacy of the system:
A. Prior to phase completion and government usage of any piece of new refrigeration equipment,
the following shall be accomplished:
A. Distribution:
1. Provide one (1) copy to DeCA/PMF 2250 Foulois St. Suite 2, Lackland AFB TX 78236-
1039.
2. Provide one (1) copy to HQ DeCA/ENFS Ft. Lee, VA. 2301-1800.
3. Provide two (2) copies to the Contracting Officer (to be forwarded to commissary).
1. Cover: The following identification shall be inscribed on the covers: "OPERATING AND
MAINTENANCE INSTRUCTIONS," the location of the building, the name of the installer,
and the contract number. A fly sheet shall be placed before instructions covering each
subject. The instruction sheets shall be approximately 8-1/2 inch by 11 inch, with large
sheets of drawings folded in. The instructions shall include, but shall not be limited to,
the following:
A. The manufacturer shall guarantee that the equipment furnished shall operate without excessive
noise or vibration; deliver the specified capacities indicated in the schedule and nameplate
ratings without overloading; and shall satisfactorily operate for a period of 1 year from the date
of final acceptance of the units by the Contracting Officer.
B. Work and equipment shall be guaranteed by the installing contractor to be free from defects in
the materials or workmanship for a period of one year from date of final acceptance of the total
construction project by the Contracting Officer. The refrigeration systems shall be guaranteed
to perform satisfactorily for 1 year from date of final acceptance of the total construction project
by the Contracting Officer. Satisfactory performance shall mean that the refrigerated cases and
insulated cold storage rooms shall maintain the design discharge air temperature while
operating at design conditions. Design conditions and temperatures shall be based on
ASHRAE Standard No. 72-83.
C. Emergency Repair Warranty: In addition to the warranty of construction, the following repair
service is a part of the specifications and shall be binding on the installing contractor:
1. The manufacturer of the equipment shall guarantee that the equipment shall operate
without failure for the periods indicated below beginning on the date of final acceptance
of the total construction contract by the contracting officer.
2. First 90 Days: During the first 90 days of the warranty, the Manufacturer shall provide 24
hours a day, 7 days per week (including holidays), service to the Commissary. A
technician shall arrive at the Commissary within 2 hours of receipt of a telephone call for
warranty service. All parts and labor shall be provided by the Manufacturer at no cost to
the government during this period.
3. 91 to 365 Day: During the 91st day through the 365 day of the warranty, the
Manufacturer shall provide free exchange of parts within 24 hours of notification.
Shipping costs shall be paid by the Manufacturer. These parts will be installed by the
installing contractor and billed to the manufacturer.
A. General: All Work shall be accomplished in accordance with current regulatory requirements
established by the Environmental Protection Agency, including final regulations to implement
the Clean Air Act.
B. Recover all refrigerant in accord with all State, Local, and Federal regulations regarding the
recover, handling, and storage of refrigerants.
END OF SECTION
BOTTOM OF
SOFFITT AIRTIGHT
RETURN AIR DUCT
IN SOFFITT
GASKET PER
ARCHITECTURAL
DETAILS
CLOSURE PANEL TO
SEAL BETWEEN
TOPS AND ENDS OF
CASES
BOTTOM OF
SOFFITT AIRTIGHT
RETURN AIR DUCT
IN SOFFITT
GASKET PER
ARCHITECTURAL
DETAILS
CLOSURE PANEL TO
SEAL BETWEEN
TOPS AND ENDS OF
CASES
DESIGN CRITERIA
1. Related Sections: Division 01 and Sections 08 42 29.23, 11 13 00, 23 90 00, 28 16 00, 28 23 00,
28 31 00, and 28 39 00.
2. Reference Standards: Basic requirements for design are set forth in NFPA-101 Life Safety Code,
NFPA-70 National Electrical Code, ANSI C2 National Electrical Safety Code, and in OSHA
Regulations.
3. Electrical Systems: Electrical systems for large motors, compressors, and lighting for new
commissaries: 277/480 volt, 3-phase. Receptacles, small motors, equipment loads and lighting not
suitable for 277v: connect to 120/208V, 3-phase system.
4. One Line Electrical Diagram: Include detailed One Line Electrical diagram in the project drawings; not
a Riser diagram. As a minimum, ensure the one line electrical diagram includes sizing information for
the following:
A. Panelboards/switchboards.
B. Overcurrent protection.
C. Feeders/conductors.
D. Conduit.
E. Transformers.
F. Disconnects.
G. Transfer switches.
H. Generators.
I. Type of transformer winding.
5. Wire Sizes: Show in American Wire Gauge (AWG). Show conduit sizes in inches.
6. Refrigeration System: Provide with separate electrical feeder through a manual transfer switch.
Provide fused disconnect switch mounted on exterior of commissary as a connection point for a
Government furnished portable generator as alternate source to manual transfer switch. Design and
show system up to load side of manual transfer switch in the electrical plans. Refer to Section
23 90 00 and Design Plate 23 90 00-14/14A; see also Section 26 36 00.
7. Project Refrigeration System Electrical Circuits: The Contractor and its display case manufacturer
shall design and provide electrical circuits for the project refrigeration system (feeder from the load
side of the manual transfer switch, refrigeration panelboards, case-to-case wiring for fans, lights,
defrost control and power, Refrigeration Monitoring Control System, etc.). Electrical defrost for the
product refrigeration system shall be rated for 208 Volt operation. Refer to Section 23 90 00 and
Design Plate 23 90 00-14/14A.
8. Electrical Metering: Provide as described in Section 26 51 00 Interior Lighting and 26 56 00 Exterior
Lighting.
9. Electrical and communications distribution should be run overhead rather than under the floor for
loads in the sales and checkout areas and in the processing rooms. Items impractical to feed
overhead, such as wide island display cases that have no suitable place to attach overhead conduits,
may be fed via the shortest underfloor conduit route available. Other exceptions may be approved by
DeCA in special circumstances.
10. Electrical feeders and branch circuits in conduit should not exceed 9 current-carrying conductors in a
conduit, except for conduit nipples 24 inches or less in length.
11. Fire Alarm, Security Alarm, Video Surveillance, and Mass Notification Systems design criteria are
found in Division 28.
June 2011 26 05 00 1
DeCA DESIGN CRITERIA HANDBOOK
26 05 00 COMMON WORK RESULTS FOR ELECTRICAL
12. Electrical Wiring for Point of Sale and LAN Equipment: Special isolated-ground feeders, panels,
circuits and wiring devices and standby engine-generator are required. These requirements are
detailed in Section 26 05 00.
13. Commissary Operational Equipment Electrical Circuits: Provide electrical circuits for the commissary
operational equipment, other than refrigeration electrical provided under Division 23, including balers,
battery chargers for the material handling equipment (MHE) (walkie-stackers, pallet jacks, etc).
Space battery chargers 48 inches apart horizontally to permit simultaneous recharging of MHE.
Provide circuits for CFCI, GFCI, and GFGI equipment shown in the Equipment List or Equipment
Descriptions for the individual project, and for any relocated or reused existing equipment.
14. Electrical Circuit Breaker Panels: Do not install electrical circuit breaker panels in any refrigerated
storage or processing room due to requirements for wash-down cleaning. Do not attach panelboards
to either side of any insulated cooler panel wall.
15. Interlocking Controls:
A. Provide on all overhead doors that have electrically operated door openers. Controls shall
prevent door opener from operating when door is locked. Refer to Sections 08 42 29.23.
B. Provide on all electrically operated dock levelers to prevent raising the dock leveler against a
closed overhead door. Refer to Sections 08 36 13 and 11 13 00.
16. Grounding Wire: Provide feeders and branch circuits with separate grounding wire sized in
accordance with National Electric Code. Provide grounding conductor with green colored insulation
for convenience outlets.
17. Rebates: Research power company rebate opportunities and incorporate design features when
practicable that will avail DeCA of such monetary and financing incentives. Initiate rebate/incentive
agreements with power company and host installation serving the project location and following
through to assure a signed rebate agreement is made part of the final 100 percent design submittal
or a waiver of rebate is signed by the DeCA Director of Facilities. The A-E shall include as a part of
the construction specifications and bid schedule the requirement that the Contractor complete the
power company request for payment in order that payment be made to DeCA or the host installation
as applicable. Typical power company rebate opportunities are as follows:
A. High Efficiency Lighting Systems.
B. High Performance Building Envelopes.
C. High Efficiency Packaged Air-Conditioners and Heat Pumps.
D. High Efficiency Chillers.
E. High Efficiency Motors.
F. HVAC Controls.
G. High Efficiency Water Heating.
H. High Efficiency Refrigeration.
I. Day Lighting Measures.
J. Electric Cooking.
K. Cogeneration.
L. Power Conditioning.
18. Electric Motors: One horsepower and larger, polyphase induction motors: NEMA MG1 Premium
Efficiency (current edition), energy-saver design type and power factor corrected to a nominal 95
percent, where possible. Locate capacitors near and switched with motor. Other motors not covered
under MG1 Premium Efficiency standards shall be of the highest efficiency rating available for the
application.
19. Corrosion Resistance: All exterior electrical equipment shall be corrosion resistant designs adequate
for tropical marine, coastal, or wet atmospheres, as applicable to the project location.
20. Exposed Electrical: Paint electrical devices (raceways, boxes, etc.) exposed to view in the Sales
Area of the Commissary. Install conduits and other devices in a neat and orderly fashion.
June 2011 26 05 00 2
DeCA DESIGN CRITERIA HANDBOOK
26 05 00 COMMON WORK RESULTS FOR ELECTRICAL
21. Construction Phasing: For renovation projects, analyze phasing requirements and provide adequate
phasing notes in the construction documents to assure appropriate electrical support and timely
incremental work completion during demolition and construction phases. Require timely coordination
conferences between Contractor, Store Operator, Construction Inspector, Authorities Having
Jurisdiction, and Suppliers of critical equipment. Require timely investigation by the Contractor of the
phase site before construction starts, to insure that critical clearances are correct (example:
clearance above ceiling height for recessed light fixtures), and to determine and document existing
conditions (example: existing inoperative or damaged electrical outlets, or items that will require
temporary electrical service).
22. Design Analysis:
A. Provide a Design Analysis that illustrates by narrative, calculations and cut sheets the basis of
the electrical design. Provide calculations to support design decisions on sizes and ratings of
electrical distribution elements; i.e., NEC load, ampacity, voltage drop, fault currents, and
illumination intensity. On Add/Alter projects, illustrate selective tripping coordination of new
overcurrent protective devices with existing upstream protective devices and all load side
protective devices, down to the branch panel feeder breaker level, using time/current graphs for
the existing and proposed new breakers. On New Facility projects, include in the electrical
narrative a discussion of protective devices selected to assure the possibility of selective tripping
coordination. In the project documents, require the New Facility Construction Contractor to
submit a complete coordination study including time/current graphs. Edit and use Guide
Specification 26 28 01 for New Facility Projects, and for major Remodel projects that significantly
change overcurrent protective devices above the small branch circuit level.
B. Include in the design analysis a summary table of all product type selections based on Efficiency
Recommendation Tables from DOE/FEMPs Buying Energy Efficient Products.
23. Design Plates: Edit any Design Plates incorporated in the project drawings to coordinate
appropriately with individual project conditions. Do not include Design Plates that are not applicable
to the project. Remove from these details any notes and instructions intended only for the designers.
24. Guide Specifications: Use DeCA guide specifications where available. Where DeCA guide
specifications are not available for a needed item, use appropriate MasterSpecs or other commercial
specs. Edit any guide specifications used to conform to individual project guidance and conditions,
and to these design criteria. Edit each section used to remove any superfluous requirements; for
example, delete seismic bracing, testing, and qualification requirements if the site zone does not
require seismic considerations. Editing notes and suggestions are included in the Guide
Specifications as "Hidden Text". Edit any text from these Design Criteria incorporated by the A-E into
the design or construction specifications, to coordinate appropriately with individual project conditions
and requirements and to remove instructions and notes intended only for designers. Do not include
sections that are not applicable to the project in the Project Specifications.
END OF SECTION
June 2011 26 05 00 3
SECTION 26 05 00
COMMON WORK RESULTS FOR ELECTRICAL
(Edited from DeCA June 2011 Design Criteria)
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
C. Field Test Reports: Indicate and interpret test results for compliance with performance
requirements.
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
1.4 COORDINATION
A. Coordinate chases, slots, inserts, sleeves, and openings with general construction work and
arrange in building structure during progress of construction to facilitate the electrical
installations that follow.
1. Set inserts and sleeves in poured-in-place concrete, masonry work, and other structural
components as they are constructed.
B. Sequence, coordinate, and integrate installing electrical materials and equipment for efficient
flow of the Work. Coordinate installing large equipment requiring positioning before closing in
the building.
1. Coordinate installation and connection of exterior underground and overhead utilities and
services, including provision for electricity-metering components.
2. Comply with requirements of authorities having jurisdiction and of utility company
providing electrical power and other services.
D. Coordinate location of access panels and doors for electrical items that are concealed by
finished surfaces. Access doors and panels are specified in Division 08 Section Access Doors
and Frames.
PART 2 - PRODUCTS
B. Metal Items for Use Outdoors or in Damp Locations: Hot-dip galvanized steel.
C. Slotted-Steel Channel Supports: Flange edges turned toward web, and 9/16 inch diameter
slotted holes at a maximum of 2 inches o.c., in webs.
D. Slotted-Steel Channel Supports: Comply with Division 05 Section Metal Fabrications for slotted
channel framing.
1. Fittings and Accessories: Products of the same manufacturer as channels and angles.
2. Fittings and Accessory Materials: Same as channels and angles, except metal items
may be stainless steel.
F. Raceway and Cable Supports: Manufactured clevis hangers, riser clamps, straps, threaded C-
clamps with retainers, ceiling trapeze hangers, wall brackets, and spring-steel clamps or click-
type hangers.
G. Pipe Sleeves: ASTM A 53, Type E, Grade A, Schedule 40, galvanized steel, plain ends.
A. Meter: Electronic kilowatt-hour/demand measuring to record electricity used and highest peak
demand over a time period according to electric utility. Meter is designed for use on the type
and rating of circuit indicated for its application.
1. E-MON Corporation.
2. National Meter Industries, Inc.
3. Osaki Meter Sales, Inc.
4. Power Measurement.
5. Square D; Schneider Electric.
A. For Equipment: Equipment manufacturer's paint selected to match installed equipment finish.
PART 3 - EXECUTION
A. Headroom Maintenance: If mounting heights or other location criteria are not indicated, arrange
and install components and equipment to provide the maximum possible headroom.
B. Materials and Components: Install level, plumb, and parallel and perpendicular to other building
systems and components, unless otherwise indicated.
D. Right of Way: Give to raceways and piping systems installed at a required slope.
A. Damp Locations and Outdoors: Hot-dip galvanized materials or nonmetallic, U-channel system
components.
E. Strength of Supports: Adequate to carry present and future loads, times a safety factor of at
least four; minimum of 200 pound design load.
A. Install support devices to securely and permanently fasten and support electrical components.
B. Install individual and multiple raceway hangers and riser clamps to support raceways. Provide
U-bolts, clamps, attachments, and other hardware necessary for hanger assemblies and for
securing hanger rods and conduits.
D. Size supports for multiple raceway installations so capacity can be increased by a 25 percent
minimum in the future.
E. Support individual horizontal raceways with separate, malleable-iron pipe hangers or clamps.
F. Install 1/4 inch diameter or larger threaded steel hanger rods, unless otherwise indicated.
G. Arrange supports in vertical runs so the weight of raceways and enclosed conductors is carried
entirely by raceway supports, with no weight load on raceway terminals.
I. Separately support cast boxes that are threaded to raceways and used for fixture support.
Support sheet-metal boxes directly from the building structure or by bar hangers. If bar hangers
are used, attach bar to raceways on opposite sides of the box and support the raceway with an
approved fastener not more than 24 inches from the box.
J. Install metal channel racks for mounting cabinets, panelboards, disconnect switches, control
enclosures, pull and junction boxes, transformers, and other devices unless components are
mounted directly to structural elements of adequate strength.
K. Install sleeves for cable and raceway penetrations of concrete slabs and walls unless core-
drilled holes are used. Install sleeves for cable and raceway penetrations of masonry and fire-
rated gypsum walls and of all other fire-rated floor and wall assemblies. Install sleeves during
erection of concrete and masonry walls.
7. Welding to steel structure may be used only for threaded studs, not for conduits, pipe
straps, or other items.
8. Light Steel: Sheet-metal screws.
9. Fasteners: Select so the load applied to each fastener does not exceed 25 percent of its
proof-test load.
A. Install equipment according to utility company's written requirements. Provide grounding and
empty conduits as required by utility company.
3.5 FIRESTOPPING
A. Apply firestopping to cable and raceway penetrations of fire-rated floor and wall assemblies to
achieve fire-resistance rating of the assembly. Firestopping materials and installation
requirements are specified in Division 07 Section Firestopping.
A. Construct concrete bases of dimensions indicated, but not less than 4 inches larger, in both
directions, than supported unit. Follow supported equipment manufacturer's anchorage
recommendations and setting templates for anchor-bolt and tie locations, unless otherwise
indicated. Use 3000-psi, 28-day compressive-strength concrete and reinforcement as specified
in Division 03 Section Cast-in-Place Concrete.
C. Abandoned Work: Cut and remove buried raceway and wiring, indicated to be abandoned in
place, 2 inches below the surface of adjacent construction. Cap raceways and patch surface to
match existing finish.
E. Remove, store, clean, reinstall, reconnect, and make operational components indicated for
relocation.
A. Cut, channel, chase, and drill floors, walls, partitions, ceilings, and other surfaces required to
permit electrical installations. Perform cutting by skilled mechanics of trades involved.
B. Repair and refinish disturbed finish materials and other surfaces to match adjacent undisturbed
surfaces. Install new fireproofing where existing firestopping has been disturbed. Repair and
refinish materials and other surfaces by skilled mechanics of trades involved.
A. Inspect installed components for damage and faulty work, including the following:
B. Test Owner's electricity-metering installation for proper operation, accuracy, and usability of
output data.
1. Connect a load of known kW rating, 1.5 kW minimum, to a circuit supplied by the metered
feeder.
2. Turn off circuits supplied by the metered feeder and secure them in the "off" condition.
3. Run the test load continuously for eight hours, minimum, or longer to obtain a
measurable meter indication. Use a test load placement and setting that ensure
continuous, safe operation.
A. Refinish and touch up paint. Paint materials and application requirements are specified in
Division 09 Section Painting and Coating.
1. Clean damaged and disturbed areas and apply primer, intermediate, and finish coats to
suit the degree of damage at each location.
2. Follow paint manufacturer's written instructions for surface preparation and for timing and
application of successive coats.
3. Repair damage to galvanized finishes with zinc-rich paint recommended by
manufacturer.
4. Repair damage to PVC or paint finishes with matching touchup coating recommended by
manufacturer.
A. On completion of installation, including outlets, fittings, and devices, inspect exposed finish.
Remove burrs, dirt, paint spots, and construction debris.
B. Protect equipment and installations and maintain conditions to ensure that coatings, finishes,
and cabinets are without damage or deterioration at time of Substantial Completion.
END OF SECTION
1.1 SUMMARY
A. Section Includes:
1. Cables and related splices, terminations, and accessories for medium-voltage electrical
distribution systems.
1.2 SUBMITTALS
A. Product Data: For each type of cable indicated. Include splices and terminations for cables and
cable accessories.
C. Qualification Data: For testing agency, and for cable splicing technician.
A. Installer: Engage a cable splicer, trained and certified by splice material manufacturer, with not
less than three years experience, to install, splice, and terminate medium-voltage cable.
C. Source Limitations: Obtain cables and accessories through one source from a single
manufacturer.
D. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
A. Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless
permitted under the following conditions and then only after arranging to provide temporary
utility services according to requirements indicated:
1. Notify Contracting Officer at least seven days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Governments Designated
Representatives written permission.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Cables:
2.2 CABLES
B. Conductor: Copper.
E. Conductor Insulation: Cross linked polyethylene (XLP) complying with NEMA WC 74.
G. Shielding: Solid copper wires, helically applied over semiconducting insulation shield.
H. Shielding and Jacket: Corrugated copper drain wires embedded in extruded, chlorinated,
polyethylene jacket.
1. Circuit Identification: Color-coded tape (black, red, blue) under the metallic shielding.
A. Connectors and Splice Kits: Comply with IEEE 404; type as recommended by cable or splicing
kit manufacturer for the application.
B. Splicing Products: As recommended, in writing, by splicing kit manufacturer for specific sizes,
ratings, and configurations of cable conductors. Include all components required for complete
splice, with detailed instructions.
1. Compound-filled, cast-metal body, metal-clad cable terminator for metal-clad cable with
external plastic jacket.
B. Shielded-Cable Terminations: Comply with the following classes of IEEE 48. Insulation class is
equivalent to that of cable. Include shield ground strap for shielded cable terminations.
1. Class 1 Terminations: Modular type, furnished as a kit, with stress-relief tube; multiple,
molded-silicone rubber, insulator modules; shield ground strap; and compression-type
connector.
2. Class 1 Terminations: Heat-shrink type with heat-shrink inner stress control and outer
nontracking tubes; multiple, molded, nontracking skirt modules; and compression-type
connector.
3. Class 1 Terminations: Modular type, furnished as a kit, with stress-relief shield
terminator; multiple-wet-process, porcelain, insulator modules; shield ground strap; and
compression-type connector.
A. Description: Modular system, complying with IEEE 386, with disconnecting, single-pole, cable
terminators and with matching, stationary, plug-in, dead-front terminals designed for cable
voltage and for sealing against moisture.
C. Load-Break Cable Terminators: Elbow-type units with 200-A load make/break and continuous-
current rating; coordinated with insulation diameter, conductor size, and material of cable being
terminated. Include test point on terminator body that is capacitance coupled.
D. Dead-Break Cable Terminators: Elbow-type unit with 600-A continuous-current rating; designed
for de-energized disconnecting and connecting; coordinated with insulation diameter, conductor
size, and material of cable being terminated. Include test point on terminator body that is
capacitance coupled.
F. Test-Point Fault Indicators: Applicable current-trip ratings and arranged for installation in test
points of load-break separable connectors, and complete with self-resetting indicators capable
of being installed with shotgun hot stick and tested with test tool.
G. Tool Set: Shotgun hot stick with energized terminal indicator, fault-indicator test tool, and
carrying case.
A. Tape for First Course on Metal Objects: 0.01 inch thick, corrosion-protective, moisture-
resistant, PVC pipe-wrapping tape.
B. Arc-Proofing Tape: Fireproof tape, flexible, conformable, intumescent to 0.3 inch thick,
compatible with cable jacket.
A. Indicators: Manual-reset fault indicator, arranged to clamp to cable sheath and provide a
display after a fault has occurred in cable. Instrument shall not be affected by heat, moisture,
and corrosive conditions and shall be recommended by manufacturer for installation conditions.
B. Resetting Tool: Designed for use with fault indicators, with moisture-resistant storage and
carrying case.
B. Test strand-filled cables for water-penetration resistance according to ICEA T-31-610, using a
test pressure of 5 psig.
PART 3 - EXECUTION
3.1 INSTALLATION
B. Pull Conductors: Do not exceed manufacturer's recommended maximum pulling tensions and
sidewall pressure values.
1. Where necessary, use manufacturer-approved pulling compound or lubricant that will not
deteriorate conductor or insulation.
2. Use pulling means, including fish tape, cable, rope, and basket-weave cable grips that
will not damage cables and raceways. Do not use rope hitches for pulling attachment to
cable.
C. Install exposed cables parallel and perpendicular to surfaces of exposed structural members
and follow surface contours where possible.
D. Support cables according to Division 26 Section Common Work Results for Electrical.
E. In manholes, handholes, pull boxes, junction boxes, and cable vaults, train cables around walls
by the longest route from entry to exit and support cables at intervals adequate to prevent sag.
F. Install cable splices at pull points and elsewhere as indicated; use standard kits.
1. Protective Cap: At each terminal junction, with one on each terminal to which no feeder
is indicated to be connected.
2. Portable Feed-Through Accessory: Three.
3. Standoff Insulator: Three.
H. Arc Proofing: Unless otherwise indicated, arc proof medium-voltage cable at locations not
protected by conduit, cable tray, direct burial, or termination materials. In addition to arc-
proofing tape manufacturer's written instructions, apply arc proofing as follows:
I. Seal around cables passing through fire-rated elements according to Division 07 Section
Firestopping.
K. Ground shields of shielded cable at terminations, splices, and separable insulated connectors.
Ground metal bodies of terminators, splices, cable and separable insulated-connector fittings,
and hardware.
A. Testing: Engage a qualified testing agency to perform the following field quality-control testing:
1. After installing medium-voltage cables and before electrical circuitry has been energized,
test for compliance with requirements.
2. Perform each electrical test and visual and mechanical inspection stated in NETA ATS,
Section 7.3.2. Certify compliance with test parameters.
C. Remove malfunctioning units, replace with new units, and retest as specified above.
END OF SECTION
DESIGN CRITERIA
June 2011 26 05 19 1
SECTION 26 05 19
LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes:
1. Building wires and cables and associated connectors, splices, and terminations for wiring
systems rated 600 V and less.
B. Related Sections:
1. Division 27 Section Communications Horizontal Cabling for transmission media used for
control and signal circuits.
2. Division 26 Section Medium-Voltage Cables for single-conductor and multiconductor
cables, cable splices, and terminations for electrical distribution systems with 2001 to
35,000 V.
1.2 SUBMITTALS
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. In other Part 2 articles where subparagraph titles below introduce lists, the following
requirements apply for product selection:
A. Available Manufacturers:
B. Refer to Part 3 "Conductor and Insulation Applications" Article for insulation type, cable
construction, and ratings.
C. Conductor Material: Copper complying with NEMA WC 70; solid conductor for No. 10 AWG and
smaller, stranded for No. 8 AWG and larger.
D. Conductor Insulation Types: Type THW, THHN-THWN XHHW, USE, and SO complying
with NEMA WC 70.
E. Multiconductor Cable: Power and Control Tray Cable, Type TC; Metal-clad cable, Type MC;
and Type SO with ground wire.
A. Available Manufacturers:
B. Description: Factory-fabricated connectors and splices of size, ampacity rating, material, type,
and class for application and service indicated.
C. Feeders Concealed in Ceilings, Walls, and Partitions: Type THHN-THWN, single conductors in
raceway.
F. Branch Circuits Concealed in Ceilings, Walls, and Partitions: Type THHN-THWN, single
conductors in raceway.
G. Branch Circuits Concealed in Concrete and below Slabs-on-Grade: Type THHN-THWN, single
conductors in raceway. MC cable is allowable to be used in spaces that are difficult to access;
lengths shall not exceed 50 feet. All homerun circuits shall be contained in conduit.
H. Cord Drops and Portable Appliance Connections: Type SO, hard service cord.
L. Unless otherwise noted, conductor sizes given on the drawings are for Type THWN 167 deg F
copper conductors, not more than 3 conductors in a raceway, in ambient temperature not
exceeding 86 deg F. If other insulation types or conditions are proposed, conductor size shall
be adjusted in accordance with requirements of the N.E.C. at no increase of cost to the
3.2 INSTALLATION
A. Conceal cables in finished walls, ceilings, and floors, unless otherwise indicated.
C. Use pulling means, including fish tape, cable, rope, and basket-weave wire/cable grips, that will
not damage cables or raceway.
D. Install exposed cables parallel and perpendicular to surfaces of exposed structural members,
and follow surface contours where possible.
E. Support cables according to Division 26 Section Common Work Results for Electrical.
G. Identify and color-code conductors and cables according to Division 26 Section Identification for
Electrical Systems.
3.3 CONNECTIONS
B. Make splices and taps that are compatible with conductor material and that possess equivalent
or better mechanical strength and insulation ratings than unspliced conductors.
C. Wiring at Outlets: Install conductor at each outlet, with at least 6 inches of slack.
1. After installing conductors and cables and before electrical circuitry has been energized,
test for compliance with requirements.
END OF SECTION
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 SUBMITTALS
1. Ground rods.
2. Chemical rods.
1.3 Qualification Data: For firms and persons specified in "Quality Assurance" Article.
1.4 Field Test Reports: Submit written test reports to include the following:
C. Results of failed tests and corrective action taken to achieve test results that comply with
requirements.
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
C. Comply with NFPA 70; for overhead-line construction and medium-voltage underground
construction, comply with IEEE C2.
D. Comply with NFPA 780 and UL 96 when interconnecting with lightning protection system.
PART 2 - PRODUCTS
A. For insulated conductors, comply with Division 26 Section Low-Voltage Electrical Power
Conductors and Cables.
B. Material: Copper.
D. Isolated Ground Conductors: Insulated with green-colored insulation with yellow stripe. On
feeders with isolated ground, use colored tape, alternating bands of green and yellow tape to
provide a minimum of three bands of green and two bands of yellow.
1. Bonding Cable: 28 kcmil, 14 strands of No. 17 AWG copper conductor, 1/4 inch in
diameter.
2. Bonding Conductor: No. 4 or No. 6 AWG, stranded copper conductor.
3. Bonding Jumper: Bare copper tape, braided bare copper conductors, terminated with
copper ferrules; 1-5/8 inches wide and 1/16-inch thick.
4. Tinned Bonding Jumper: Tinned-copper tape, braided copper conductors, terminated
with copper ferrules; 1-5/8 inches wide and 1/16-inch thick.
J. Grounding Bus: Bare, annealed copper bars of rectangular cross section, with insulators.
A. Comply with IEEE 837 and UL 467; listed for use for specific types, sizes, and combinations of
conductors and connected items.
C. Welded Connectors: Exothermic-welded type, in kit form, and selected per manufacturer's
written instructions.
C. Chemical Electrodes: Copper tube, straight or L-shaped, filled with nonhazardous chemical
salts, terminated with a 4/0 bare conductor. Provide backfill material recommended by
manufacturer.
3.1 APPLICATION
B. Exothermic-Welded Connections: Use for connections to structural steel and for underground
connections, except those at test wells.
D. Ground Rod Clamps at Test Wells: Use bolted pressure clamps with at least two bolts.
E. Grounding Bus: Install in electrical and telephone equipment rooms, in rooms housing service
equipment, and elsewhere as indicated.
1. Use insulated spacer; space 1 inch from wall and support from wall 6 inches above
finished floor, unless otherwise indicated.
2. At doors, route the bus up to the top of the door frame, across the top of the doorway,
and down to the specified height above the floor.
F. Underground Grounding Conductors: Use copper conductor, No. 2/0 AWG minimum. Bury at
least 24 inches below grade or bury 12 inches above duct bank when installed as part of the
duct bank.
A. Comply with NFPA 70, Article 250, for types, sizes, and quantities of equipment grounding
conductors, unless specific types, larger sizes, or more conductors than required by NFPA 70
are indicated.
C. Busway Supply Circuits: Install insulated equipment grounding conductor from the grounding
bus in the switchgear, switchboard, or distribution panel to equipment grounding bar terminal on
busway.
H. Water Heater, Heat-Tracing, and Antifrost Heating Cables: Install a separate equipment
grounding conductor to each electric water heater, heat-tracing, and antifrost heating cable.
Bond conductor to heater units, piping, connected equipment, and components.
I. Signal and Communication Systems: For telephone, alarm, voice and data, and other
communication systems, provide No. 6 AWG minimum insulated grounding conductor in
raceway from grounding electrode system to each service location, terminal cabinet, wiring
closet, and central equipment location.
1. Service and Central Equipment Locations and Wiring Closets: Terminate grounding
conductor on a 1/4 by 2 by 12 inch grounding bus.
2. Terminal Cabinets: Terminate grounding conductor on cabinet grounding terminal.
3.3 COUNTERPOISE
A. Ground the steel framework of the building with a driven ground rod at the base of every corner
column and at intermediate exterior columns at distances not more than 60 feet apart. Provide
a grounding conductor (counterpoise), electrically connected to each ground rod and to each
steel column, extending around the perimeter of the building. Use tinned-copper conductor not
less than No. 2/0 AWG for counterpoise and for tap to building steel. Bury counterpoise not
less than 18 inches below grade and 24 inches from building foundation.
3.4 INSTALLATION
A. Ground Rods: Install at least three rods spaced at least one-rod length from each other and
located at least the same distance from other grounding electrodes.
1. Drive ground rods until tops are 2 inches below finished floor or final grade, unless
otherwise indicated.
2. Interconnect ground rods with grounding electrode conductors. Use exothermic welds,
except at test wells and as otherwise indicated. Make connections without exposing steel
or damaging copper coating.
C. Bonding Straps and Jumpers: Install so vibration by equipment mounted on vibration isolation
hangers and supports is not transmitted to rigidly mounted equipment. Use exothermic-welded
connectors for outdoor locations, unless a disconnect-type connection is required; then, use a
bolted clamp. Bond straps directly to the basic structure taking care not to penetrate any
adjacent parts. Install straps only in locations accessible for maintenance.
D. Metal Water Service Pipe: Provide insulated copper grounding conductors, in conduit, from
building's main service equipment, or grounding bus, to main metal water service entrances to
building. Connect grounding conductors to main metal water service pipes by grounding clamp
connectors. Where a dielectric main water fitting is installed, connect grounding conductor to
street side of fitting. Bond metal grounding conductor conduit or sleeve to conductor at each
end.
E. Water Meter Piping: Use braided-type bonding jumpers to electrically bypass water meters.
Connect to pipe with grounding clamp connectors.
F. Bond each aboveground portion of gas piping system upstream from equipment shutoff valve.
G. Install one test well for each service at the ground rod electrically closest to the service
entrance. Set top of well flush with finished grade or floor.
H. Ufer Ground (Concrete-Encased Grounding Electrode): Fabricate according to NFPA 70, using
a minimum of 20 feet of bare copper conductor not smaller than No. 4 AWG.
1. If concrete foundation is less than 20 feet long, coil excess conductor within base of
foundation.
2. Bond grounding conductor to reinforcing steel in at least four locations and to anchor
bolts. Extend grounding conductor below grade and connect to building grounding grid or
to grounding electrode external to concrete.
3.5 CONNECTIONS
C. Equipment Grounding Conductor Terminations: For No. 8 AWG and larger, use pressure-type
grounding lugs. No. 10 AWG and smaller grounding conductors may be terminated with winged
pressure-type connectors.
E. Connections at Test Wells: Use compression-type connectors on conductors and make bolted-
and clamped-type connections between conductors and ground rods.
F. Tighten screws and bolts for grounding and bonding connectors and terminals according to
manufacturer's published torque-tightening values. If manufacturer's torque values are not
indicated, use those specified in UL 486A.
A. Comply with IEEE C2 requirements. Use 2 or more parallel ground rods if a single ground rod
electrode resistance to ground exceeds 25 ohms.
B. Drive ground rods to a depth of 12 inches below finished grade in undisturbed earth.
C. Ground Rod Connections: Use clamp-type connectors listed for the purpose for underground
connections and connections to rods.
E. Secondary Neutral and Tank of Transformer: Interconnect and connect to grounding conductor.
F. Protect grounding conductors running on surface of wood poles with molding extended from
grade level up to and through communication service and transformer spaces.
A. Manholes and Handholes: Install a driven ground rod close to wall and set rod depth so
4 inches will extend above finished floor. If necessary, install ground rod before manhole is
placed and provide a No. 1/0 AWG bare, tinned-copper conductor from ground rod into manhole
through a waterproof sleeve in manhole wall. Protect ground rods passing through concrete
floor with a double wrapping of pressure-sensitive tape or heat-shrunk insulating sleeve from 2
inches above to 6 inches below concrete. Seal floor opening with waterproof, nonshrink grout.
C. Pad-Mounted Transformers and Switches: Install two ground rods and counterpoise circling
pad. Ground pad-mounted equipment and noncurrent-carrying metal items associated with
substations by connecting them to underground cable and grounding electrodes. Use tinned-
copper conductor not less than No. 2 AWG for counterpoise and for taps to equipment ground
pad. Bury counterpoise not less than 18 inches below grade and 6 inches from the foundation.
1. After installing grounding system but before permanent electrical circuitry has been
energized, test for compliance with requirements.
2. Test completed grounding system at each location where a maximum ground-resistance
level is specified, at service disconnect enclosure grounding terminal, and at ground test
wells. Measure ground resistance not less than two full days after the last trace of
precipitation, and without the soil being moistened by any means other than natural
drainage or seepage and without chemical treatment or other artificial means of reducing
natural ground resistance. Perform tests, by the fall-of-potential method according to
IEEE 81.
3. Provide drawings locating each ground rod and ground rod assembly and other
grounding electrodes, identify each by letter in alphabetical order, and key to the record
of tests and observations. Include the number of rods driven and their depth at each
location and include observations of weather and other phenomena that may affect test
results. Describe measures taken to improve test results.
A. Restore surface features, including vegetation, at areas disturbed by Work of this Section.
Reestablish original grades, unless otherwise indicated. If sod has been removed, replace it as
soon as possible after backfilling is completed. Restore areas disturbed by trenching, storing of
dirt, cable laying, and other activities to their original condition. Include application of topsoil,
fertilizer, lime, seed, sod, sprig, and mulch. Comply with Division 32 Section Planting. Maintain
restored surfaces. Restore disturbed paving as indicated.
END OF SECTION
DESIGN CRITERIA
June 2011 26 05 33 1
SECTION 26 05 33
RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
(Edited from DeCA June 2011 Design Criteria)
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes: Raceways, fittings, boxes, enclosures, and cabinets for electrical wiring.
B. Related Sections:
List below only products and equipment that the reader might
expect to find in this Section but are specified elsewhere.
2. Division 26 Section Vibration and Seismic Controls for Electrical Systems for seismic
restraints and bracing of raceways, boxes, enclosures, and cabinets.
3. Division 26 Section Wiring Devices for devices installed in boxes and for floor-box service
fittings.
1.2 DEFINITIONS
Retain abbreviations that remain after this Section has been edited.
1.3 SUBMITTALS
A. Product Data: For raceways, wireways and fittings, outlet boxes, floor boxes, hinged-cover
enclosures, and cabinets.
B. Shop Drawings: Show fabrication and installation details of components for custom raceways,
fittings, boxes, enclosures, and cabinets not completely described by published Product Data.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
a. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified."
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
1.5 COORDINATION
A. Coordinate layout and installation of raceways, boxes, enclosures, cabinets, and suspension
system with other construction that penetrates ceilings or is supported by them, including light
fixtures, loudspeakers, HVAC equipment, fire-suppression system, and partition assemblies.
2.1 MANUFACTURERS
A. In other Part 2 articles where subparagraph titles below introduce lists, the following
requirements apply for product selection:
A. Available Manufacturers:
A. Available Manufacturers:
1. American International.
2. Anamet Electrical, Inc.; Anaconda Metal Hose.
3. Arnco Corp.
4. Cantex Inc.
5. Certainteed Corp.; Pipe & Plastics Group.
6. Condux International.
7. ElecSYS, Inc.
8. Electri-Flex Co.
9. Lamson & Sessions; Carlon Electrical Products.
10. Manhattan/CDT/Cole-Flex.
11. RACO; Division of Hubbell, Inc.
12. Spiralduct, Inc./AFC Cable Systems, Inc.
13. Thomas & Betts Corporation.
D. LFNC: UL 1660.
A. Available Manufacturers:
1. Hoffman.
2. Square D.
B. Material and Construction: Sheet metal sized and shaped as indicated, NEMA 1 or 3R as
appropriate for location.
C. Fittings and Accessories: Include couplings, offsets, elbows, expansion joints, adapters, hold-
down straps, end caps, and other fittings to match and mate with wireways as required for
complete system.
D. Select features, unless otherwise indicated, as required to complete wiring system and to
comply with NFPA 70.
A. Available Manufacturers:
1. Hoffman.
2. Lamson & Sessions; Carlon Electrical Products.
C. Fittings and Accessories: Include couplings, offsets, elbows, expansion joints, adapters, hold-
down straps, end caps, and other fittings to match and mate with wireways as required for
complete system.
D. Select features, unless otherwise indicated, as required to complete wiring system and to
comply with NFPA 70.
A. Surface Metal Raceways: Galvanized steel with snap-on covers. Furnish with manufacturer's
standard prime coating. Paint to match surrounding wall finish.
1. Available Manufacturers:
B. Types, sizes, and channels as indicated and required for each application, with fittings that
match and mate with raceways.
A. Available Manufacturers:
C. Cast-Metal Outlet and Device Boxes: NEMA FB 1, Type FD, with gasketed cover.
G. Cast-Metal Pull and Junction Boxes: NEMA FB 1, galvanized cast iron or cast aluminum with
gasketed cover.
H. Hinged-Cover Enclosures: NEMA 250, Type 1, with continuous hinge cover and flush latch.
1. Metal Enclosures: Steel, finished inside and out with manufacturer's standard enamel.
I. Cabinets: NEMA 250, Type 1, galvanized steel box with removable interior panel and
removable front, finished inside and out with manufacturer's standard enamel. Hinged door in
front cover with flush latch and concealed hinge. Key latch to match panelboards. Include
metal barriers to separate wiring of different systems and voltage and include accessory feet
where required for freestanding equipment.
A. Finish: For raceway, enclosure, or cabinet components exposed in finished spaces, provide
manufacturer's standard prime-coat finish ready for field painting.
B. Finish: For raceway, enclosure, or cabinet components in other than finished spaces, provide
manufacturer's standard gray paint applied to factory-assembled surface raceways, enclosures,
and cabinets before shipping.
PART 3 - EXECUTION
A. Outdoors:
B. Indoors:
1. Exposed: EMT; RMC where likely to be physically damaged; Schedule 40 PVC only in
refrigerated cooler boxes, above 48 inches AFF.
2. Concealed: EMT or RMC.
3. Connection to Vibrating Equipment (Including Transformers and Hydraulic, Pneumatic,
Electric Solenoid, or Motor-Driven Equipment): FMC; except use LFMC in damp or wet
locations.
4. Damp or Wet Locations: Schedule 40 PVC.
5. Boxes and Enclosures: NEMA 250, Type 1, except as follows:
a. Damp or Wet Locations: NEMA 250, Type 4, stainless steel in food prep or display
areas,
D. Raceway Fittings: Compatible with raceways and suitable for use and location.
1. Intermediate Steel Conduit: Use threaded rigid steel conduit fittings, unless otherwise
indicated.
2. PVC Externally Coated, Rigid Steel Conduits: Use only fittings approved for use with that
material. Patch all nicks and scrapes in PVC coating after installing conduits.
3.2 INSTALLATION
A. Keep raceways at least 6 inchesaway from parallel runs of flues and steam or hot-water pipes.
Install horizontal raceway runs above water and steam piping.
B. Complete raceway installation before starting conductor installation. Plan raceways so that no
more than 9 current-carrying conductors (including neutrals) will be enclosed in any single
conduit more than 24 inches in length.
C. Support raceways as specified in Division 26 Section Common Work Results for Electrical.
F. Protect stub-ups from damage where conduits rise through floor slabs. Arrange so curved
portions of bends are not visible above the finished slab.
G. Make bends and offsets so ID is not reduced. Keep legs of bends in the same plane and keep
straight legs of offsets parallel, unless otherwise indicated.
1. Install concealed raceways with a minimum of bends in the shortest practical distance,
considering type of building construction and obstructions, unless otherwise indicated.
J. Install exposed raceways parallel or at right angles to nearby surfaces or structural members
and follow surface contours as much as possible.
K. Join raceways with fittings designed and approved for that purpose and make joints tight.
M. Terminations:
1. Where raceways are terminated with locknuts and bushings, align raceways to enter
squarely and install locknuts with dished part against box. Use two locknuts, one inside
and one outside box.
2. Where raceways are terminated with threaded hubs, screw raceways or fittings tightly
into hub so end bears against wire protection shoulder. Where chase nipples are used,
align raceways so coupling is square to box; tighten chase nipple so no threads are
exposed.
N. Install pull wires in empty raceways. Use polypropylene or monofilament plastic line with not
less than 200 pound tensile strength. Leave at least 12 inches of slack at each end of pull wire.
O. Telephone and Signal System Raceways, 2-Inch Trade Size and Smaller: In addition to above
requirements, install raceways in maximum lengths of 150 feetand with a maximum of two 90-
degree bends or equivalent. Separate lengths with pull or junction boxes where necessary to
comply with these requirements.
P. Install raceway sealing fittings at suitable, approved, and accessible locations and fill them with
UL-listed sealing compound. For concealed raceways, install each fitting in a flush steel box
with a blank cover plate having a finish similar to that of adjacent plates or surfaces. Install
raceway sealing fittings at the following points:
1. Where conduits pass from warm to cold locations, such as boundaries of refrigerated
spaces.
2. Where otherwise required by NFPA 70.
Q. Stub-up Connections: Where specifically shown on drawings, extend conduits through concrete
floor for connection to freestanding equipment. Install with an adjustable top or coupling
threaded inside for plugs set flush with finished floor. Extend conductors to equipment with rigid
R. Flexible Connections: Use maximum of 72 inchesof flexible conduit for recessed and
semirecessed lighting fixtures; for equipment subject to vibration, noise transmission, or
movement; and for all motors. Use LFMC in damp or wet locations. Install separate ground
conductor across flexible connections.
S. Surface Raceways: Install a separate, green, ground conductor in raceways from junction box
supplying raceways to receptacle or fixture ground terminals.
T. Set floor boxes level and flush with finished floor surface.
3.3 PAINTING
A. Exposed conduits and boxes in the Sales Area shall be painted to match the surrounding
surfaces. Coordinate colors and painting with other related trades.
3.4 PROTECTION
A. Provide final protection and maintain conditions that ensure coatings, finishes, and cabinets are
without damage or deterioration at time of Substantial Completion.
3.5 CLEANING
A. After completing installation of exposed, factory-finished raceways and boxes, inspect exposed
finishes and repair damaged finishes.
END OF SECTION
DESIGN CRITERIA
1. Applicable Sections. Section 26 05 00 applies. Refer to Design Standard 26 05 00-05.
2. Provide Tele-Power Poles:
A. Rough-in cables for overhead power and communications wiring from cable trays to checkout
stands. (Using Tele-Power poles to be furnished, installed and wired by the government via
contract with IBM.)
B. For connecting to overhead cable trays where used for flexible overhead interior power and
communications wiring, as an alternative to wiring in conduit or under floors. Consider this method
for connecting free-standing equipment or modular office furniture located away from walls.
3. Size and Type.
A. Select tele-power pole size in accordance with NEC for the conductors required. Include all size
information on the construction documents.
B. Type: Steel or aluminum, single- or double-compartment, with required communications and/or
electrical receptacle outlets or other fittings. Select or specify painting a color that is complimentary
to the surroundings.
C. Fittings: Provide ceiling trim, end J-boxes, scuff boots, cable tray connectors, flexible conduit
connectors, etc., as required for a complete power and/or communications drop.
D. Provide products that are U.L. listed, with housing approved as a grounding conductor.
E. Typical Product for use at commissary check stands: Wiremold 25DTP-4 Series, length as
required (10', 12', or 15'), or equal.
4. Install tele-power poles in accordance with the NEC, NECA, and manufacturers instructions.
Support and anchor the equipment solidly. Maintain separation of power and communication cables
throughout the system.
5. Specifications: Guide Spec Section 26 27 26, Wiring Devices, covers this equipment under "service
poles". Edit to suit project conditions.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: Section 26 05 00 applies.
2. Provide cable tray systems:
A. For overhead power and communications wiring between checkout stands and sources of supply.
Reference Design Standards 26 05 00-05, 26 05 00-06, 26 05 00-11, 26 05 00-12, 26 05 00-13,
26 05 00-14.
B. For flexible overhead interior power and communications wiring, where appropriate and
economical, as an alternative to wiring in conduit or under floors. Consider cable trays for wiring to
moveable fixtures such as gondola shelving.
3. Size and Location:
A. Select cable tray size in accordance with NEC 392, based on ultimate anticipated conductor fill
(e.g., considering future checkout stands) plus 25%. Minimum width of the cable tray must allow
for a minimum-bending-radius 180 degree bend in any cable, so that cable slack may be looped
back within the tray. Use dimensions for NEC approved multi-conductor power tray cables and
data cables. Where divided cable tray is used to provide separate channels for communication
and power wiring, determine the required size of each channel for proper placement of the
longitudinal tray barrier. Include all tray size information on the construction documents.
B. Locate cable trays as inconspicuously as possible, no lower than the bottom of lighting luminaires.
Cable trays must be accessible for their entire length. If there is no possible cable tray route that
maintains accessibility over the entire length, it is permissible to transition to electrical conduit
raceways for the inaccessible portion of the run. The raceways in this portion should maintain
separation of power and communications cables, and include one spare 2" conduit with pull cord
for each class of service. Where cable trays are visible in customer areas or office environments,
paint to match surroundings. Mounting height at checkout stands: If a layin ceiling is available,
locate the cable tray above the ceiling; if the ceiling is an open type, locate the cable tray high
as possible while avoiding conflicts with HVAC ductwork.
4. Drop Take-Off Arrangement:
A. Since drops are used to connect with relocatable equipment and fixtures, provide take-off points
on the cable tray that can be changed or abandoned and sealed without losing the integrity or
appearance of the tray.
B. Drops may consist of tele-power poles, conduits, vertical cable tray sections, or other approved
electrical raceways, as appropriate for the use and location, or as directed.
5. Provide cable tray meeting NEMA Standard VE-1, U.L. listed, and approved as a grounding
conductor.
A. (Types above check stands): Solid bottom, ventilated, steel; with hinged latching cover,
ventilated, steel. Divider barriers shall be steel.
B. (Types other than above check stands): Basket type cable tray.
C. Fittings: Provide all fittings required for a complete cable tray installation. Provide vertical and
horizontal bends, tees, wyes, reducers, end blanks, cabinet connectors, splice plates, hangers,
etc., as required. Bend radii shall support the minimum bending radii of cables installed. Provide
C-shape cable tray support hangers to facilitate lay-in placement of wiring in the cable trays.
6. Install cable trays in accordance with the NEC, NECA, Cable Tray Institute Installation Guidelines,
and manufacturers instructions. Configure the cable trays to afford accessibility for adding,
removing, or replacing cables. Maintain separation of power and communication cables throughout
the system, including at take-off points.
END OF SECTION
June 2011 26 05 36 1
SECTION 26 05 36
CABLE TRAYS FOR ELECTRICAL SYSTEMS
(Edited from DeCA June 2011 Design Criteria)
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
List below only products and equipment that the reader might
expect to find in this Section but are specified elsewhere.
2. Division 26 Section Vibration and Seismic Controls for Electrical Systems for mounting
and anchoring cable trays.
1.2 SUBMITTALS
A. Product Data: Include data indicating dimensions and finishes for each type of cable tray
indicated.
1. Show fabrication and installation details of cable tray, including plans, elevations, and
sections of components and attachments to other construction elements. Designate
components and accessories, including clamps, brackets, hanger rods, splice-plate
connectors, expansion-joint assemblies, straight lengths, and fittings.
C. Coordination Drawings: Floor plans and sections drawn to scale. Include scaled cable tray
layout and relationships between components and adjacent structural and mechanical
elements. Show the following:
D. Product Certificates: For each type of cable tray, signed by product manufacturer.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
a. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified."
2. Dimensioned Outline Drawings of Cable Tray Units: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
G. Operation and Maintenance Data: For cable trays to include in emergency, operation, and
maintenance manuals.
A. Source Limitations: Obtain cable tray components through one source from a single
manufacturer.
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
C. Comply with NEMA VE 1, "Metal Cable Tray Systems," if cable tray types specified are defined
in the standard.
1.4 COORDINATION
A. Coordinate layout and installation of cable trays and suspension system with other construction
that penetrates ceilings or is supported by them, including light fixtures, loudspeakers, HVAC
equipment, fire-suppression system, and partition assemblies.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Cable Trays, Fittings, and Accessories (Above Checkout Stands): Steel, solid ventilated bottom
with the following finish:
C. Sizes and Configurations: Refer to the Drawings for specific requirements for types, materials,
sizes, and configurations.
A. Fittings: Tees, crosses, risers, elbows, and other fittings as indicated, of same materials and
finishes as cable tray.
B. Covers (Solid type only): Solid, ventilated type of same materials and finishes as cable tray.
Provide hinged latching covers on all cable trays.
D. Cable tray supports and connectors, including bonding jumpers, as recommended by cable tray
manufacturer.
A. Lettering: 1-1/2 inch high, black letters on yellow background with legend "WARNING! NOT
TO BE USED AS WALKWAY, LADDER, OR SUPPORT FOR LADDERS OR PERSONNEL."
B. Materials and fastening are specified in Division 26 Section Identification for Electrical Systems.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions for compliance with requirements for installation
tolerances and other conditions affecting performance.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
C. Install expansion connectors where cable tray crosses building expansion joint and in cable tray
runs that exceed 90 feet. Space connectors and set gaps according to NEMA VE 1.
F. Locate cable tray above piping unless accessibility to cable tray is required or unless otherwise
indicated.
G. Seal penetrations through fire and smoke barriers according to Division 07 Section
Firestopping.
H. Sleeves for Future Cables: Install capped sleeves for future cables through firestop-sealed
cable tray penetrations of fire and smoke barriers.
I. Workspace: Install cable trays with sufficient space to permit access for installing cables.
J. Install barriers to separate cables of different systems, such as power, communications, and
data processing; or of different insulation levels, such as 600, 5000, and 15 000 V.
L. After installation of cable trays is completed, install warning signs in visible locations on or near
cable trays.
3.3 CONNECTIONS
1. After installing cable trays and after electrical circuitry has been energized, test for
compliance with requirements.
2. Perform the following electrical test and visual and mechanical inspections:
a. Visually inspect each cable tray joint and each ground connection for mechanical
continuity.
3.5 PROTECTION
A. Provide final protection and maintain conditions, in a manner acceptable to manufacturer and
Installer, that ensure cable tray is without damage or deterioration at time of Substantial
Completion.
1. Repair damage to galvanized finishes with zinc-rich paint recommended by cable tray
manufacturer.
2. Repair damage to PVC or paint finishes with matching touchup coating recommended by
cable tray manufacturer.
END OF SECTION
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
1.2 DEFINITIONS
Retain acronym and abbreviations that remain after this Section has
been edited.
C. Seismic Restraint: A fixed device (a seismic brace, an anchor bolt or stud, or a fastening
assembly) used to prevent vertical or horizontal movement, or both vertical and horizontal
movement, of an electrical system component during an earthquake.
D. Mobile Structural Element: A part of the building structure such as a slab, floor structure, roof
structure, or wall that may move independent of other mobile structural elements during an
earthquake.
1.3 SUBMITTALS
A. Product Data: Illustrate and indicate types, styles, materials, strength, fastening provisions, and
finish for each type and size of seismic restraint component used.
1. Anchor Bolts and Studs: Tabulate types and sizes, complete with report numbers and
rated strength in tension and shear as evaluated by an agency approved by authorities
having jurisdiction.
B. Shop Drawings: For anchorage and bracing not defined by details and charts on Drawings.
Indicate materials, and show designs and calculations signed and sealed by a professional
engineer.
C. Coordination Drawings: Plans and sections drawn to scale and coordinating seismic bracing for
electrical components with other systems and equipment, including other seismic restraints, in
the vicinity.
E. Qualification Data: For firms and persons specified in "Quality Assurance" Article.
F. Material Test Reports: From a qualified testing agency indicating and interpreting test results of
seismic control devices for compliance with requirements indicated.
A. Comply with seismic restraint requirements in UFC 3-310-04 Seismic Design for Building, and
IBC, unless requirements in this Section are more stringent.
A. Project site class as defined in UFC: [A] [B] [C] [D] [E] [F].
B. Seismic Risk Occupancy Category as defined in UFC: [I] [II] [III] [IV].
D. Design spectral response acceleration as short periods, SDS, as defined in UFC: <Insert
Value>
1.6 COORDINATION
A. Coordinate layout and installation of seismic bracing with building structural system and
architectural features, and with mechanical, fire-protection, electrical, and other building
features in the vicinity.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Structural Safety Factor: Strength in tension and shear of components used shall be at
least two times the maximum seismic forces to which they will be subjected.
B. Concrete and Masonry Anchor Bolts and Studs: Steel-expansion wedge type.
D. Through Bolts: Structural type, hex head, high strength. Comply with ASTM A 325.
F. Beam Clamps for Steel Beams and Joists: Double sided. Single-sided type is not acceptable.
G. Bushings for Floor-Mounted Equipment Anchors: Neoprene units designed for seismically rated
rigid equipment mountings, and matched to the type and size of anchor bolts and studs used.
B. Channel-Type Bracing Assemblies: Slotted steel channel, with adjustable hinged steel brackets
and bolts.
C. Cable-Type Bracing Assemblies: Zinc-coated, high-strength steel wire rope cable attached to
steel thimbles, brackets, and bolts designed for cable service.
1. Arrange units for attachment to the braced component at one end and to the structure at
the other end.
2. Wire Rope Cable: Comply with ASTM 603. Use 49- or 133-strand cable with a minimum
strength of 2 times the calculated maximum seismic force to be resisted.
D. Hanger Rod Stiffeners: Slotted steel channels with internally bolted connections to hanger rod.
PART 3 - EXECUTION
3.1 APPLICATION
A. Generator Sets: Comply with Division 23 Section Vibration and Seismic Controls for HVAC
Piping and Equipment.
3.2 INSTALLATION
A. Install seismic restraints according to applicable codes and regulations and as approved by
authorities having jurisdiction, unless more stringent requirements are indicated.
B. Attachments to New Concrete: Bolt to channel-type concrete inserts or use expansion anchors.
D. Holes for Expansion Anchors in Concrete: Drill at locations and to depths that avoid reinforcing
bars.
F. Attachments to Hollow Walls: Bolt to slotted steel channels fastened to wall with expansion
anchors.
H. Attachments to Steel: Bolt to clamps on flanges of beams or on upper truss chords of bar joists.
A. Anchor rigidly to a single mobile structural element or to a concrete base that is structurally tied
to a single mobile structural element.
1. Size concrete bases so expansion anchors will be a minimum of 10 bolt diameters from
the edge of the concrete base.
B. Expansion and Contraction: Install to allow for thermal movement of braced components.
D. Attachment to Structure: If specific attachment is not indicated, anchor bracing to the structure
at flanges of beams, upper truss chords of bar joists, or at concrete members.
A. Make flexible connections in raceways, cables, wireways, cable trays, and busways where they
cross expansion and seismic control joints, where adjacent sections or branches are supported
by different structural elements, and where they terminate at electrical equipment anchored to a
different mobile structural element from the one supporting them.
A. Testing Agency: Engage a qualified testing agency to perform the following field quality-control
testing:
END OF SECTION
DESIGN CRITERIA
June 2011 26 05 53 1
SECTION 26 05 53
IDENTIFICATION FOR ELECTRICAL SYSTEMS
(Edited from DeCA June 2011 Design Criteria)
1.1 SUMMARY
A. Section Includes: Electrical identification materials and devices required to comply with
ANSI C2, NFPA 70, OSHA standards, and Authorities Having Jurisdiction.
1.2 SUBMITTALS
PART 2 - PRODUCTS
A. Comply with ANSI A13.1, Table 3, for minimum size of letters for legend and for minimum
length of color field for each raceway and cable size.
B. Adhesive Labels: Preprinted, flexible, self-adhesive vinyl with legend overlaminated with a
clear, weather- and chemical-resistant coating.
D. Colored Adhesive Tape: Self-adhesive vinyl tape not less than 3 mils thick by 1 to 2 inches
wide.
F. Tape Markers: Vinyl or vinyl-cloth, self-adhesive, wraparound type with preprinted numbers and
letters.
G. Aluminum, Wraparound Marker Bands: Bands cut from 0.014-inch-thick aluminum sheet, with
stamped or embossed legend, and fitted with slots or ears for permanently securing around wire
or cable jacket or around groups of conductors.
H. Plasticized Card-Stock Tags: Vinyl cloth with preprinted and field-printed legends. Orange
background, unless otherwise indicated, with eyelet for fastener.
J. Brass or Aluminum Tags: 2 by 2 by 0.05-inchmetal tags with stamped legend, punched for
fastener.
B. Engraved Plastic Nameplates and Signs: Engraving stock, melamine plastic laminate, minimum
1/16 inchthick for signs up to 20 sq. in.and 1/8 inchthick for larger sizes.
C. Baked-Enamel Signs for Interior Use: Preprinted aluminum signs, punched or drilled for
fasteners, with colors, legend, and size required for the application. 1/4 inchgrommets in
corners for mounting.
E. Fasteners for Nameplates and Signs: Self-tapping, stainless-steel screws or No. 10/32,
stainless-steel machine screws with nuts and flat and lock washers.
A. Cable Ties: Fungus-inert, self-extinguishing, one-piece, self-locking, Type 6/6 nylon cable ties.
1. Primer for Galvanized Metal: Single-component acrylic vehicle formulated for galvanized
surfaces.
2. Primer for Concrete Masonry Units: Heavy-duty-resin block filler.
3. Primer for Concrete: Clear, alkali-resistant, binder-type sealer.
4. Enamel: Silicone-alkyd or alkyd urethane as recommended by primer manufacturer.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Identification Materials and Devices: Install at locations for most convenient viewing without
interference with operation and maintenance of equipment.
B. Lettering, Colors, and Graphics: Coordinate names, abbreviations, colors, and other
designations with corresponding designations in the Contract Documents or with those required
by codes and standards. Use consistent designations throughout Project.
C. Sequence of Work: If identification is applied to surfaces that require finish, install identification
after completing finish work.
1. Entire floor area directly above conduits running beneath and within 12 inchesof a
basement or ground floor that is in contact with earth or is framed above unexcavated
space.
2. Wall surfaces directly external to conduits concealed within wall.
3. All accessible surfaces of concrete envelope around conduits in vertical shafts, exposed
in the building, or concealed above suspended ceilings.
4. Entire surface of exposed conduits.
1. Clean surfaces of dust, loose material, and oily films before painting.
2. Prime surfaces using type of primer specified for surface.
3. Apply one intermediate and one finish coat of enamel.
G. Caution Labels for Indoor Boxes and Enclosures for Power and Lighting: Install pressure-
sensitive, self-adhesive labels identifying system voltage with black letters on orange
background. Install on exterior of door or cover.
H. Paths of Underground Electrical Lines: During trench backfilling, for exterior underground
power, control, signal, and communication lines, install continuous underground plastic line
marker located directly above line at 6 to 8 inchesbelow finished grade. Where width of multiple
lines installed in a common trench or concrete envelope does not exceed 16 inchesoverall, use
a single line marker. Install line marker for underground wiring, both direct-buried cables and
cables in raceway.
I. Color-Coding of Secondary Phase Conductors: Use the following colors for service, feeder and
branch-circuit phase conductors:
1. 208/120-V Conductors:
a. Phase A: Black.
b. Phase B: Red.
c. Phase C: Blue.
a. Phase A: Yellow.
b. Phase B: Brown.
c. Phase C: Orange.
3. Factory apply color the entire length of conductors, except the following field-applied,
color-coding methods may be used instead of factory-coded wire for sizes larger than
No. 10 AWG:
J. Power-Circuit Identification: Metal tags or aluminum, wraparound marker bands for cables,
feeders, and power circuits in vaults, pull and junction boxes, manholes, and switchboard
rooms.
1. Legend: 1/4 inchsteel letter and number stamping or embossing with legend
corresponding to indicated circuit designations.
2. Tag Fasteners: Nylon cable ties.
3. Band Fasteners: Integral ears.
1. Warnings, Cautions, and Instructions: Install to ensure safe operation and maintenance
of electrical systems and of items to which they connect. Install engraved plastic-
laminated instruction signs with approved legend where instructions are needed for
system or equipment operation. Install metal-backed butyrate signs for outdoor items.
2. Emergency Operation: Install engraved laminated signs with white legend on red
background with minimum 3/8 inch high lettering for emergency instructions on power
transfer, load shedding, and other emergency operations.
END OF SECTION
***********************************************************
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
1.2 DEFINITIONS
1.3 DESCRIPTION
1.4 RESPONSIBILITIES
C. Warranty Period:
1.5 SUBMITTALS
PART 3 - EXECUTION
3.1 STARTUP
A. The Electrical Contractors shall follow the start-up and initial checkout procedures listed in the
Responsibilities list in this Section and in Division 01 Section General Commissioning
Requirements. Division 26 has start-up responsibility and is required to complete systems and
sub-systems so they are fully functional, meeting the design objectives of the Contract
Documents. The commissioning procedures and functional testing do not relieve or lessen this
responsibility or shift that responsibility partially to the Commissioning Agent, Technical
Inspector, or Government.
B. Functional testing is intended to begin upon completion of a system. Functional testing may
proceed prior to the completion of systems, or sub-systems at the discretion of the PM and GC.
Beginning system testing before full completion, does not relieve the Contractor from fully
completing the system, including all prefunctional checklists as soon as possible.
A. The following O&M manual requirements do not replace O&M manual documentation
requirements elsewhere in these specifications.
B. Division 26 shall compile and prepare documentation for all commissioned systems covered in
Division 26 and deliver this documentation to the GC for inclusion in the O&M manuals prior to
the training of Government personnel.
A. The GC shall be responsible for training coordination and scheduling and ultimately to ensure
that training is completed.
C. Electrical Contractor: The Electrical Contractor shall have the following training responsibilities:
1. Provide the TI with a training plan four weeks before the planned training.
2. Provide designated Government personnel with comprehensive orientation and training
in the understanding of the systems and the operation and maintenance of each major
piece of commissioned electrical equipment or system.
3. Training shall start with classroom sessions, if necessary, followed by hands on training
on each piece of equipment, which shall illustrate the various modes of operation,
including startup, shutdown, fire/smoke alarm, power failure, etc.
4. During any demonstration, should the system fail to perform in accordance with the
requirements of the O&M manual or sequence of operations, the system will be repaired
or adjusted as necessary and the demonstration repeated.
5. The appropriate trade or manufacturer's representative shall provide the instructions on
each major piece of equipment. This person may be the start-up technician for the piece
of equipment, the installing contractor or manufacturers representative. Practical
building operating expertise as well as in-depth knowledge of all modes of operation of
the specific piece of equipment are required. More than one party may be required to
execute the training.
6. The training sessions shall follow the outline in the Table of Contents of the operation and
maintenance manual and illustrate whenever possible the use of the O&M manuals for
reference.
7. Training shall include:
8. Hands-on training shall include start-up, operation in all modes possible, including
manual, shut-down and any emergency procedures and maintenance of all pieces of
equipment.
9. Fully explain and demonstrate the operation, function and overrides of any local
packaged controls, not controlled by the central control system.
10. Training shall occur after functional testing is complete, unless approved otherwise by the
Project Manager.
11. Minimum Duration of Training: The electrical contractor shall provide training on each
piece of equipment according to the periods indicated in the individual Division 26
Sections.
END OF SECTION
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
B. Related Sections:
List below only products that the reader might expect to find in this
Section but are specified elsewhere.
Retain abbreviations that remain after this Section has been edited.
1.2 SUBMITTALS
B. Shop Drawings: Show installation details for occupancy and light-level sensors.
1. Lighting plan showing location, orientation, and coverage area of each sensor.
2. Interconnection diagrams showing field-installed wiring.
D. Operation and Maintenance Data: For each type of product to include in emergency, operation,
and maintenance manuals.
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
1.4 COORDINATION
A. Coordinate layout and installation of ceiling-mounted devices with other construction that
penetrates ceilings or is supported by them, including light fixtures, HVAC equipment, fire-
suppression system, and partition assemblies.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. In other Part 2 articles where titles below introduce lists, the following requirements apply to
product selection:
A. Line-Voltage Surge Protection: An integral part of the devices for 120- and 277-V solid-state
equipment. For devices without integral line-voltage surge protection, field-mounting surge
protection shall comply with IEEE C62.41 and with UL 1449.
A. Available Manufacturers:
A. Available Manufacturers:
B. Description: Solid state, with [SPST] [DPST] dry contacts rated for [1800-VA tungsten or
1000-VA inductive] <Insert value>, to operate connected relay, contactor
coils, microprocessor input, and complying with UL 773A.
1. Light-Level Monitoring Range: 1.5 to 10 fc, with an adjustment for turn-on and turn-off
levels within that range.
2. Time Delay: 15-second minimum, to prevent false operation.
3. Surge Protection: Metal-oxide varistor type, complying with IEEE C62.41 for
Category A1 locations.
4. Mounting: Twist lock complying with IEEE C136.10, with base-and-stem mounting or
stem-and-swivel mounting accessories as required to direct sensor to the North sky
exposure.
A. Available Manufacturers:
1. Allen-Bradley/Rockwell Automation.
2. Area Lighting Research, Inc.
3. Cutler-Hammer; Eaton Corporation.
4. Fisher Pierce.
5. Grasslin Controls Corporation.
6. Intermatic, Inc.
7. Lithonia Lighting.
8. MicroLite Corporation.
9. Novitas, Inc.
10. Paragon Electric Co.
11. Square D.
B. Ceiling-Mounting Photoelectric Switch: Solid-state, light-level sensor unit, with separate relay
unit mounted on luminaire, to detect changes in lighting levels that are perceived by the eye.
Cadmium sulfide photoresistors are not acceptable.
1. Sensor Output: Contacts rated to operate the associated relay, complying with UL 773A.
Sensor shall be powered from the relay unit.
2. Relay Unit: Dry contacts rated for 20-A ballast load at 120- and 277-V ac, for 13-A
tungsten at 120-V ac, and for 1 hp at 120-V ac. Power supply to sensor shall be 24-V dc,
150-mA, Class 2 power source as defined by NFPA 70.
1. Sensor Output: Contacts rated to operate the associated relay, complying with UL 773A.
Sensor shall be powered from the relay unit.
2. Relay Unit: Dry contacts rated for 20-A ballast load at 120- and 277-V ac, for 13-A
tungsten at 120-V ac, and for 1 hp at 120-V ac. Power supply to sensor shall be 24-V dc,
150-mA, Class 2 power source as defined by NFPA 70.
3. Light-Level Monitoring Range: 1000 to 10,000 fc, with an adjustment for turn-on and
turn-off levels within that range.
4. Time Delay: Adjustable from 5 to 300 seconds to prevent cycling, with deadband
adjustment.
5. Indicator: Two LEDs to indicate the beginning of on and off cycles.
A. Available Manufacturers:
1. Hubbell Lighting Inc.
2. Leviton Mfg. Company Inc.
3. Sensor Switch, Inc.
4. Watt Stopper (The).
A. Available Manufacturers:
B. General Description: Wall- or ceiling-mounting, solid-state units with a separate relay unit.
1. Operation: Unless otherwise indicated, turn lights on when covered area is occupied and
off when unoccupied; with a time delay for turning lights off, adjustable over a minimum
range of 1 to 15 minutes.
2. Sensor Output: Contacts rated to operate the connected relay, complying with UL 773A.
Sensor shall be powered from the relay unit.
3. Relay Unit: Dry contacts rated for 20-A ballast load at 120- and 277-V ac, for 13-A
tungsten at 120-V ac, and for 1 hp at 120-V ac. Power supply to sensor shall be 24-V dc,
150-mA, Class 2 power source as defined by NFPA 70.
4. Mounting:
C. PIR Type: Ceiling mounting; detect occupancy by sensing a combination of heat and
movement in area of coverage.
1. Detector Sensitivity: Detect a person of average size and weight moving at least 12
inchesin either a horizontal or a vertical manner at an approximate speed of 12 inches/s.
E. Dual-Technology Type: Ceiling mounting; detect occupancy by using a combination of PIR and
ultrasonic detection methods in area of coverage. Particular technology or combination of
technologies that controls on and off functions shall be selectable in the field by operating
controls on unit.
A. Available Manufacturers:
1. Allen-Bradley/Rockwell Automation.
2. Cutler-Hammer; Eaton Corporation.
3. GE Industrial Systems; Total Lighting Control.
4. Square D.
5. Siemens.
B. Description: Electrically operated and electrically held, complying with NEMA ICS 2 and
UL 508.
1. Current Rating for Switching: Listing or rating consistent with type of load served,
including tungsten filament, inductive, and high-inrush ballast (ballast with 15 percent or
less total harmonic distortion of normal load current).
2. Control-Coil Voltage: Match control power source.
A. Power Wiring to Supply Side of Remote-Control Power Sources: Not smaller than No. 12 AWG,
complying with Division 26 Section Low-Voltage Electrical Power Conductors and Cables.
B. Classes 2 and 3 Control Cable: Multiconductor cable with stranded copper conductors not
smaller than No. [18] [22] [24] AWG, complying with Division 26 Section Low-Voltage Electrical
Power Conductors and Cables.
C. Class 1 Control Cable: Multiconductor cable with stranded copper conductors not smaller than
No. [14] [16] [18] AWG, complying with Division 26 Section Low-Voltage Electrical Power
Conductors and Cables.
D. Install unshielded, twisted-pair cable for control and signal transmission conductors, complying
with Division 27 Section Voice and Data Communication Cabling.
PART 3 - EXECUTION
A. Install and aim sensors in locations to achieve at least 90 percent coverage of areas indicated.
Do not exceed coverage limits specified in manufacturer's written instructions.
A. Wiring Method: Comply with Division 26 Section Low-Voltage Electrical Power Conductors and
Cables. Minimum conduit size shall be 1/2 inch.
B. Wiring within Enclosures: Bundle, lace, and train conductors to terminal points. Separate
power-limited and nonpower-limited conductors according to conductor manufacturer's written
instructions.
C. Install field-mounting transient voltage suppressors for lighting control devices in Category A
locations that do not have integral line-voltage surge protection.
D. Size conductors according to lighting control device manufacturer's written instructions, unless
otherwise indicated.
E. Splices, Taps, and Terminations: Make connections only on numbered terminal strips in
junction, pull, and outlet boxes; terminal cabinets; and equipment enclosures.
3.3 IDENTIFICATION
A. Identify components and power and control wiring according to Division 26 Section Identification
for Electrical Systems.
A. Perform the following field tests and inspections and prepare test reports:
1. After installing time switches and sensors, and after electrical circuitry has been
energized, adjust and test for compliance with requirements.
2. Operational Test: Verify actuation of each sensor and adjust time delays.
B. Remove and replace lighting control devices where test results indicate that they do not comply
with specified requirements.
3.5 ADJUSTING
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data: Include rated nameplate data, capacities, weights, dimensions, minimum
clearances, installed devices and features, location of each field connection, and performance
for each type and size of transformer indicated.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
a. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified."
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
G. Operation and Maintenance Data: For transformer and accessories to include in emergency,
operation, and maintenance manuals.
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
C. Comply with ANSI C57.12.28, IEEE C57.12.10, IEEE C57.12.70, and IEEE C57.12.80.
A. Service Conditions: IEEE C37.121, usual service conditions except for the following:
1.5 COORDINATION
A. Coordinate installation of area drainage, downspouts, maintenance access, louvers, doors, spill
retention areas, and sumps. Coordinate installation so no piping or conduits are installed in
space allocated for medium-voltage transformers except those directly associated with
transformers.
2.1 MANUFACTURERS
In first paragraph below, retain stainless steel cabinet and sills for
coastal installations.
B. Insulating Liquid: Mineral oil, complying with ASTM D 3487, Type II, and tested according to
ASTM D 117.
D. Full-Capacity Voltage Taps: Four 2.5 percent taps, 2 above and 2 below rated high voltage;
with externally operable tap changer for de-energized use and with position indicator and
padlock hasp.
E. High-Voltage Switch: [200] [300] [400] A, make-and-latch rating of 10-kA RMS, symmetrical,
arranged for loop feed with 3-phase, 4-position, gang-operated, load-break switch that is oil
immersed in transformer tank with hook-stick operating handle in primary compartment.
F. Primary Fuses: 15.0-kV fuse assembly with fuses complying with IEEE C37.47. [Interrupting
Rating of current-limiting fuses shall be 50-kA RMS at specified system voltage.]
G. High-Voltage Terminations and Equipment: Dead front with universal-type bushing wells for
dead-front bushing-well inserts, complying with IEEE 386 and including the following:
H. Accessories:
A. Design and fabricate transformers, and anchorage devices for them, to withstand static and
seismic forces in any direction.
A. Factory Tests: Perform design and routine tests according to standards specified for
components. Conduct transformer tests according to IEEE C57.12.90.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and conditions for compliance with requirements for medium-voltage
transformers.
C. Examine walls, floors, roofs, and concrete bases for suitable mounting conditions where
transformers will be installed.
D. Verify that ground connections are in place and that requirements in Division 26 Section
Grounding and Bonding for Electrical Systems have been met. Maximum ground resistance
shall be 5 ohms at location of transformer.
E. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
3.3 IDENTIFICATION
A. Identify field-installed wiring and components and provide warning signs as specified in
Division 26 Section Identification for Electrical Systems.
3.4 CONNECTIONS
A. Ground equipment according to Division 26 Section Grounding and Bonding for Electrical
Systems.
B. Connect wiring according to Division 26 Section Low-Voltage Electrical Power Conductors and
Cables.
B. Perform the following field tests and inspections and prepare test reports:
1. After installing transformers but before primary is energized, verify that grounding system
at substation is tested at specified value or less.
2. After installing transformers and after electrical circuitry has been energized, test for
compliance with requirements.
3. Perform electrical test and visual and mechanical inspection stated in NETA ATS,
Section 7.2. Certify compliance with test parameters.
4. Test and adjust controls and safeties. Replace damaged and malfunctioning controls
and equipment.
C. Remove malfunctioning units, replace with new units, and retest as specified above.
A. Voltage Monitoring and Adjusting: If requested by Government, perform the following voltage
monitoring after Substantial Completion but not more than six months after Final Acceptance:
1. During a period of normal load cycles as evaluated by Government, perform seven days
of three-phase voltage recording at secondary terminals of each transformer. Use
voltmeters with calibration traceable to National Institute of Science and Technology
standards and with a chart speed of not less than 1 inch per hour. Voltage unbalance
greater than 1 percent between phases, or deviation of any phase voltage from nominal
value by more than plus or minus 5 percent during test period, is unacceptable.
2. Corrective Actions: If test results are unacceptable, perform the following corrective
actions, as appropriate:
3. Retests: After corrective actions have been performed, repeat monitoring until
satisfactory results are obtained.
4. Report: Prepare written report covering monitoring and corrective actions performed.
B. Infrared Scanning: After Substantial Completion, but not more than 60 days after Final
Acceptance, perform infrared scan of each transformer. Open primary and secondary front rear
panels so joints and connections are accessible to portable scanner.
END OF SECTION
DESIGN CRITERIA
1. Related Sections: Section 26 05 00 applies.
2. Location: Install in accessible utility locations near to the load served. If suspended above ceiling,
provide access panels. Provide bollards to protect from forklift / pallet jack traffic as needed. Provide
for proper ventilation.
3. Dry-type transformers: Dry-type transformers shall have 220 deg C (Class "H") insulation, 80 deg C
rise and four 2-1/2 percent taps (2 above and 2 below normal). Delta-Wye connection unless
otherwise noted.
4. Provide shielded and/or power conditioning type transformers for sensitive loads (e.g., POS) where
directed in individual project requirements, or where required by existing power supply conditions.
END OF SECTION
June 2011 26 22 00 1
SECTION 26 22 00
LOW-VOLTAGE TRANSFORMERS
(Edited from DeCA June 2011 Design Criteria)
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1. The following types of dry-type transformers rated 600 V and less, with capacities up to
1000 kVA:
1.2 SUBMITTALS
A. Product Data Include rated nameplate data, capacities, weights, dimensions, minimum
clearances, installed devices and features, and performance for each type and size of
transformer indicated.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
a. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified."
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
1.5 COORDINATION
A. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases. Concrete,
reinforcement, and formwork requirements are specified in Division 03.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Comply with NEMA ST 20, and list and label as complying with UL 1561.
B. Provide transformers that are internally braced to withstand seismic forces specified in
Division 26 Section Vibration and Seismic Controls for Electrical Systems.
F. Enclosure: Ventilated, raintight, NEMA 250, Type [3R] [3R, stainless steel]. Outdoor, where
scheduled.
G. Enclosure: Totally enclosed, nonventilated, with lifting eyes, NEMA 250, Type [3R] [3] [4X,
stainless steel]. Outdoor, where scheduled.
1. Core and coil shall be encapsulated within resin compound, sealing out moisture and air.
J. Taps for Transformers Smaller Than 3 kVA: One 5 percent tap above normal full capacity.
K. Taps for Transformers 7.5 to 24 kVA: One 5 percent tap above and one 5 percent tap below
normal full capacity.
L. Taps for Transformers 25 kVA and Larger: Two 2.5 percent taps above and four 2.5 percent
taps below normal full capacity.
M. K-Factor Rating: Transformers indicated to be K-factor rated shall comply with UL 1561
requirements for nonsinusoidal load current-handling capability to the degree defined by
designated K-factor.
1. Unit shall not overheat when carrying full-load current with harmonic distortion
corresponding to designated K-factor.
2. Indicate value of K-factor on transformer nameplate.
N. Electrostatic Shielding: Each winding shall have an independent, single, full-width copper
electrostatic shield arranged to minimize interwinding capacitance.
1. Arrange coil leads and terminal strips to minimize capacitive coupling between input and
output terminals.
2. Include special terminal for grounding the shield.
3. Shield Effectiveness:
A. Description: Self-cooled, two-winding dry type, rated for continuous duty and with wiring
terminals suitable for connection as autotransformer. Transformers shall comply with
NEMA ST 1 and shall be listed and labeled as complying with UL 506 or UL 1561.
A. Description: Self-cooled, two-winding dry type, rated for continuous duty, complying with
NEMA ST 1, and listed and labeled as complying with UL 506.
B. Ratings: Continuous duty. If rating is not indicated, provide at least 50 percent spare capacity
above connected peak load.
B. Factory Sound-Level Tests: Conduct sound-level tests on equipment for this Project.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine conditions for compliance with enclosure- and ambient-temperature requirements for
each transformer.
C. Examine walls and floors for suitable mounting conditions where transformers will be installed.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Install wall-mounting transformers level and plumb with wall brackets fabricated by transformer
manufacturer.
C. Install suspended transformers on trapeze brackets suspended from the building structure as
shown on the Drawings.
3.3 CONNECTIONS
A. Ground equipment according to Division 26 Section Grounding and Bonding for Electrical
Systems.
B. Connect wiring according to Division 26 Section Low-Voltage Electrical Power Conductors and
Cables.
3.4 ADJUSTING
A. Record transformer secondary voltage at each unit for at least 48 hours of typical occupancy
period. Adjust transformer taps to provide optimum voltage conditions at secondary terminals.
B. Adjust buck-boost transformers to provide nameplate voltage of equipment being served, plus
or minus 5 percent, at secondary terminals.
C. Output Settings Report: Prepare a written report recording output voltages and tap settings.
END OF SECTION
DESIGN CRITERIA
END OF SECTION
June 2011 26 23 00 1
SECTION 26 23 00
SWITCHBOARDS
(Edited from DeCA June 2011 Design Criteria)
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1.2 DEFINITIONS
Retain abbreviations that remain after this Section has been edited.
1.3 SUBMITTALS
A. Product Data: For each type of switchboard, overcurrent protective device, transient voltage
suppression device, ground-fault protector, accessory, and component indicated. Include
dimensions and manufacturers' technical data on features, performance, electrical
characteristics, ratings, and finishes.
1. Dimensioned plans, elevations, sections, and details, including required clearances and
service space around equipment. Show tabulations of installed devices, equipment
features, and ratings. Include the following:
a. Enclosure types and details for types other than NEMA 250, Type 1.
b. Bus configuration, current, and voltage ratings.
c. Short-circuit current rating of switchboards and overcurrent protective devices.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
a. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified."
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
E. Operation and Maintenance Data: For switchboards and components to include in emergency,
operation, and maintenance manuals. In addition to items specified in Division 01 Section
Closeout Procedures, include the following:
A. Source Limitations: Obtain switchboards through one source from a single manufacturer.
B. Product Selection for Restricted Space: Drawings indicate maximum dimensions for
switchboards including clearances between switchboards and adjacent surfaces and other
items. Comply with indicated maximum dimensions.
C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
A. Deliver in sections or lengths that can be moved past obstructions in delivery path.
B. Store indoors in clean dry space with uniform temperature to prevent condensation. Protect
from exposure to dirt, fumes, water, corrosive substances, and physical damage.
A. Installation Pathway: Remove and replace access fencing, doors, lift-out panels, and structures
to provide pathway for moving switchboards into place, if necessary.
B. Environmental Limitations: Rate equipment for continuous operation under the following
conditions, unless otherwise indicated:
D. Interruption of Existing Electric Service: Do not interrupt electric service to facilities occupied by
Government or others unless permitted under the following conditions and then only after
arranging to provide temporary electric service according to requirements indicated:
1. Notify Contracting Officer no fewer than ten days in advance of proposed interruption of
electric service.
2. Indicate method of providing temporary electric service.
3. Do not proceed with interruption of electric service without Contracting Officer's written
permission.
1.7 COORDINATION
A. Coordinate layout and installation of switchboards and components with other construction
including conduit, piping, equipment, and adjacent surfaces. Maintain required workspace
clearances and required clearances for equipment access doors and panels.
B. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases. Concrete,
reinforcement, and formwork requirements are specified in Division 03.
A. Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents.
1. Potential Transformer Fuses: Equal to 10 percent of amount installed for each size and
type, but no fewer than 2 of each size and type.
2. Control-Power Fuses: Equal to 10 percent of amount installed for each size and type, but
no fewer than 2 of each size and type.
3. Fuses and Fusible Devices for Fused Circuit Breakers: Equal to 10 percent of amount
installed for each size and type, but no fewer than 3 of each size and type.
4. Fuses for Fused Switches: Equal to 10 percent of amount installed for each size and
type, but no fewer than 3 of each size and type.
5. Fuses for Fused Power-Circuit Devices: Equal to 10 percent of amount installed for each
size and type, but no fewer than 3 of each size and type.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. In other Part 2 articles where titles below introduce lists, the following requirements apply to
product selection:
A. Available Manufacturers:
D. Main-Bus Continuous: [4000] [3000] [2500] [2000] [1600] [1200] <Insert ampere rating> A.
F. Enclosure: Steel, NEMA 250, Type [1] [3R] [3R, with interior-lighted walk-in aisle].
G. Enclosure Finish for Outdoor Units: Factory-applied finish in manufacturer's standard color,
undersurfaces treated with corrosion-resistant undercoating.
H. Enclosure Finish for Indoor Units: Factory-applied finish in manufacturer's standard gray finish
over a rust-inhibiting primer on treated metal surface.
J. Insulation and isolation for main bus of main section and main and vertical buses of feeder
sections.
K. Space Heaters: Factory-installed electric space heaters of sufficient wattage in each vertical
section to maintain enclosure temperature above expected dew point.
M. Bus Transition and Incoming Pull Sections: Matched and aligned with basic switchboard.
N. Hinged Front Panels: Allow access to circuit breaker, metering, accessory, and blank
compartments.
2. Load Terminals: Insulated, rigidly braced, silver-plated, copper runback bus extensions
equipped with pressure connectors for outgoing circuit conductors. Provide load
terminals for future circuit-breaker positions at full ampere rating of circuit-breaker
position.
3. Ground Bus: 1/4-by-2-inch-minimum-size, hard-drawn copper of 98 percent conductivity,
equipped with pressure connectors for feeder and branch-circuit ground conductors. For
busway feeders, extend insulated equipment grounding cable to busway ground
connection and support cable at intervals in vertical run.
4. Contact Surfaces of Buses: Silver plated.
5. Main Phase Buses, Neutral Buses, and Equipment Ground Buses: Uniform capacity for
entire length of switchboard's main and distribution sections. Provide for future
extensions from both ends.
6. Neutral Buses: 100 percent of the ampacity of phase buses, unless otherwise indicated,
equipped with pressure connectors for outgoing circuit neutral cables. Bus extensions for
busway feeder neutral bus are braced.
Q. Future Devices: Equip compartments with mounting brackets, supports, bus connections, and
appurtenances at full rating of circuit-breaker compartment.
1. Line to neutral.
2. Line to ground.
3. Neutral to ground.
D. EMI/RFI Noise Attenuation Using 50-ohm Insertion Loss Test: 55 dB at 100 kHz.
F. Maximum UL 1449 clamping levels shall not exceed 400 V, line to neutral and line to ground on
120/208 V; and 800 V, line to neutral and line to ground on 277/480 V systems.
G. Withstand Capabilities: 3000 Category C surges with less than 5 percent change in clamping
voltage.
H. Accessories:
1. Form-C contacts, one normally open and one normally closed, for remote monitoring of
system operation. Contacts to reverse position on failure of any surge diversion module.
2. Audible alarm activated on failure of any surge diversion module.
3. Six-digit transient-counter set to total transient surges that deviate from the sine-wave
envelope by more than 125 V.
A. Molded-Case Circuit Breaker: NEMA AB 3, with interrupting capacity to meet available fault
currents.
a. Instantaneous trip.
b. Long- and short-time pickup levels.
c. Long- and short-time time adjustments.
2
d. Ground-fault pickup level, time delay, and I t response.
4. GFCI Circuit Breakers: Single- and two-pole configurations with [5] [30] mA trip
sensitivity.
B. Molded-Case Circuit-Breaker Features and Accessories: Standard frame sizes, trip ratings, and
number of poles.
1. Lugs: [Mechanical] style, suitable for number, size, trip ratings, and conductor material.
2. Application Listing: Appropriate for application; Type SWD for switching fluorescent
lighting loads; Type HACR for heating, air-conditioning, and refrigerating equipment.
3. Ground-Fault Protection: [Integrally mounted] [Remote-mounted] relay and trip unit
with adjustable pickup and time-delay settings, push-to-test feature, and ground-fault
indicator.
C. Enclosed, Insulated-Case Circuit Breaker: Fully rated, encased-power circuit breaker with
interrupting capacity rating to meet available fault current.
a. Instantaneous trip.
b. Long- and short-time pickup levels.
c. Long- and short-time time adjustments with I2t response.
d. Ground-fault pickup level, time delay, and I2t response.
1. Available Manufacturers:
a. Boltswitch, Inc.
b. Cutler-Hammer Products; Eaton Corporation.
c. Pringle Electrical Mfg. Co.
d. Siemens Energy & Automation, Inc.
e. Square D.
f. <Insert manufacturer's name.>
2. Main Contact Interrupting Capability: 12 times the switch current rating, minimum.
3. Operating Mechanism: Manual handle operation to close switch; stores energy in
mechanism for closing and opening.
a. Electrical Trip: Operation of lever or push-button trip switch, or trip signal from
ground-fault relay or remote-control device, causes switch to open.
4. Auxiliary Switches: Factory installed, single pole, double throw, with leads connected to
terminal block, and including one set more than quantity required for functional
performance indicated.
7. Open-Fuse Trip Device: Arranged to trip switch open if a phase fuse opens.
E. Fused Switch: NEMA KS 1, Type HD; clips to accommodate specified fuses; lockable handle.
1. Potential Transformers: Secondary voltage rating of 120 V and NEMA accuracy class of
0.3 with burdens of W, X, and Y.
2. Include provisions for continuous monitoring of power and phase currents by the
Refrigeration Monitoring and Control System (RMCS). Coordinate with the RMCS
supplier.Mounting: Display and control unit flush or semiflush mounted in instrument
compartment door.
A. Control Circuits: 120 V, supplied through secondary disconnecting devices from control-power
transformer.
B. Control-Power Fuses: Primary and secondary fuses for current-limiting and overload protection
of transformer and fuses for protection of control circuits.
B. Fungus Proofing: Permanent fungicidal treatment for switchboard interior, including instruments
and instrument transformers.
2.8 IDENTIFICATION
PART 3 - EXECUTION
3.1 PROTECTION
3.2 EXAMINATION
A. Examine elements and surfaces to receive switchboards for compliance with installation
tolerances and other conditions affecting performance.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.3 INSTALLATION
A. Install switchboards and accessories according to NEMA PB 2.1 and NECA 400.
B. Install and anchor switchboards level on concrete bases, 4-inch nominal thickness. Concrete
base is specified in Division 26 Section Common Work Results for Electrical, and concrete
materials and installation requirements are specified in Division 03.
1. Install dowel rods to connect concrete base to concrete floor. Unless otherwise
indicated, install dowel rods on 18-inch centers around full perimeter of base.
2. For switchboards, install epoxy-coated anchor bolts that extend through concrete base
and anchor into structural concrete floor.
C. Comply with mounting and anchoring requirements specified in Division 26 Section Vibration
and Seismic Controls for Electrical Systems.
D. Temporary Lifting Provisions: Remove temporary lifting eyes, channels, and brackets and
temporary blocking of moving parts from switchboard units and components.
E. Operating Instructions: Frame and mount the printed basic operating instructions for
switchboards, including control and key interlocking sequences and emergency procedures.
Fabricate frame of finished wood or metal and cover instructions with clear acrylic plastic.
Mount on front of switchboards.
3.4 IDENTIFICATION
1. Test insulation resistance for each switchboard bus, component, connecting supply,
feeder, and control circuit.
2. Test continuity of each circuit.
B. Perform the following field tests and inspections and prepare test reports:
1. Perform each electrical test and visual and mechanical inspection stated in NETA ATS,
Sections 7.1, 7.5, 7.6, 7.9, 7.10, 7.11, and 7.14 as appropriate. Certify compliance with
test parameters.
2. Correct malfunctioning units on-site, where possible, and retest to demonstrate
compliance; otherwise, replace with new units and retest.
a. Initial Infrared Scanning: After Substantial Completion, but not more than 60 days
after Final Acceptance, perform an infrared scan of each switchboard. Remove
front panels so joints and connections are accessible to portable scanner.
b. Follow-up Infrared Scanning: Perform an additional follow-up infrared scan of
each switchboard 11 months after date of Substantial Completion.
c. Instruments, Equipment, and Reports:
3.6 CLEANING
3.7 DEMONSTRATION
END OF SECTION
DESIGN CRITERIA
1. Related Sections: Division 01 and Sections 26 05 00, 26 05 33, and 11 40 00.23 apply.
2. Circuit Breaker Panelboards: Provide full size bolted-connection panels as required to serve all branch
circuits and provide 20 percent spares. Load centers are not acceptable. Install in utility spaces near to
the loads served, to the extent practicable. When installed in occupied, finished spaces, make the
panelboards as inconspicuous as possible by selecting location thoughtfully and providing enamel paint
finish of exposed panel fronts to match color of surrounding surfaces. Do not place electrical panels in
any areas potentially exposed to moisture and wash down operations such as processing areas,
janitor's closets etc.
3. Refrigeration Equipment Loads: Provide a separate power panel under Division 23 to serve
refrigeration equipment loads.
4. Bus Bars: Provide copper bus bars in all panelboards.
5. Required Features:
A. Dead front construction, flush- or surface- type as required. Flush trims with no exposed screws or
hinges. Latch with lock (all keyed alike). Circuit directory under plastic inside door, neatly typed with
final circuit designations. Directory shall be specific as to load served; e.g., "Lights Sales Row 5"
rather than "Lights"; use room names, not numbers.
B. Plated copper bussing fully rated with sequentially phased branch distribution. Fully-rated neutral
bar in mains compartment. Equipment ground bar in each panelboard. Additional isolated ground
bar where specified. Provide all bus links and accessories required for ultimate full utilization of
spaces for future breakers.
C. Breakers: Thermal-magnetic trip calibrated at 40 deg C, in each pole of multi-pole breakers, fully
common-trip. Thermal trip elements to be ambient-compensating above 40 deg C. Breaker trip
ratings to be visible without removing panel cover. Breakers to have single trip-free operating handle
with clearly distinct "closed", "open" and "tripped" positions.
6. Ensure that walls have sufficient depth to conceal the panelboard tub where flush mounted panels are
intended. Provide full NEC "working space" clearance at panelboards.
7. Provide spare conduits to an accessible space for spares at all flush panelboards.
END OF SECTION
June 2011 26 14 16 1
SECTION 26 24 16
PANELBOARDS
(Edited from DeCA June 2011 Design Criteria)
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1.2 DEFINITIONS
Retain abbreviations that remain after this Section has been edited.
1.3 SUBMITTALS
A. Product Data: For each type of panelboard, overcurrent protective device, transient voltage
suppression device, accessory, and component indicated. Include dimensions and
manufacturers' technical data on features, performance, electrical characteristics, ratings, and
finishes.
a. Enclosure types and details for types other than NEMA 250, Type 1.
b. Bus configuration, current, and voltage ratings.
c. Short-circuit current rating of panelboards and overcurrent protective devices.
a. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified."
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
F. Panelboard Schedules: For installation in panelboards. Submit final versions after load
balancing.
G. Operation and Maintenance Data: For panelboards and components to include in emergency,
operation, and maintenance manuals. In addition to items specified in Division 01 Section
Closeout Procedures, include the following:
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
A. Environmental Limitations: Rate equipment for continuous operation under the following
conditions, unless otherwise indicated:
B. Interruption of Existing Electric Service: Do not interrupt electric service to facilities occupied by
Government or others unless permitted under the following conditions and then only after
arranging to provide temporary electric service according to requirements indicated:
1. Notify Contracting Officer no fewer than ten days in advance of proposed interruption of
electrical service.
2. Do not proceed with interruption of electrical service without Contracting Officer's written
permission.
1.6 COORDINATION
A. Coordinate layout and installation of panelboards and components with other construction that
penetrates walls or is supported by them, including electrical and other types of equipment,
raceways, piping, and encumbrances to workspace clearance requirements.
A. Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
a. Current Technology.
b. Liebert Corporation.
A. Fabricate and test panelboards according to IEEE 344 to withstand seismic forces defined in
Division 26 Section Vibration and Seismic Controls for Electrical Systems.
E. Service Equipment Label: UL labeled for use as service equipment for panelboards with main
service disconnect switches.
F. Future Devices: Mounting brackets, bus connections, and necessary appurtenances required
for future installation of devices. Provide where spaces are scheduled.
A. Doors: Secured with vault-type latch with tumbler lock; keyed alike. Omit for fused-switch
panelboards.
1. For Circuit-Breaker Frame Sizes 125 A and Smaller: Bolt-on circuit breakers.
2. For Circuit-Breaker Frame Sizes Larger Than 125 A: Bolt-on circuit breakers.
A. Branch Overcurrent Protective Devices: Bolt-on circuit breakers, replaceable without disturbing
adjacent units.
B. Doors: Concealed hinges; secured with flush latch with tumbler lock; keyed alike.
A. Do not use.
A. Doors: Secured with vault-type latch with tumbler lock; keyed alike.
D. Bus: Copper phase and neutral buses; 200 percent capacity neutral bus and lugs.
E. Transient Voltage Suppression Device: IEEE C62.41, integrally mounted, plug-in-style, solid-
state, parallel-connected, sine-wave tracking suppression and filtering modules.
a. Line to neutral.
b. Line to ground.
c. Neutral to ground.
3. EMI/RFI Noise Attenuation Using 50-ohm Insertion Loss Test: 55 dB at 100 kHz.
a. Form-C contacts, one normally open and one normally closed, for remote
monitoring of system operation. Contacts to reverse position on failure of any
surge diversion module.
b. Audible alarm activated on failure of any surge diversion module.
c. Six-digit transient-counter set to total transient surges that deviate from the sine-
wave envelope by more than 125 V.
A. Molded-Case Circuit Breaker: UL 489, with interrupting capacity to meet available fault
currents. Multipole units enclosed in a single housing, all poles common trip, with a single
handle to operate as a single unit.
a. Instantaneous trip.
b. Long- and short-time pickup levels.
c. Long- and short-time time adjustments.
d. Ground-fault pickup level, time delay, and I2t response.
B. Molded-Case Circuit-Breaker Features and Accessories: Standard frame sizes, trip ratings, and
number of poles.
1. Lugs: Compression style, suitable for number, size, trip ratings, and conductor materials.
2. Application Listing: Appropriate for application; Type SWD for switching fluorescent
lighting loads; Type HACR for heating, air-conditioning, and refrigerating equipment.
3. Ground-Fault Protection: Integrally mounted relay and trip unit with adjustable pickup
and time-delay settings, push-to-test feature, and ground-fault indicator.
4. Shunt Trip: 120-V trip coil energized from separate circuit, set to trip at [55] [75] percent
of rated voltage.
5. Auxiliary Contacts: [One SPDT switch] [Two SPDT switches] with "a" and "b" contacts;
"a" contacts mimic circuit-breaker contacts, "b" contacts operate in reverse of circuit-
breaker contacts.
6. Key Interlock Kit: Externally mounted to prohibit circuit-breaker operation; key shall be
removable only when circuit breaker is in off position.
7. Zone-Selective Interlocking: Integral with electronic trip unit; for interlocking ground-fault
protection function.
A. Fungus Proofing: Permanent fungicidal treatment for panelboard interior, including overcurrent
protective devices and other components.
PART 3 - EXECUTION
3.1 INSTALLATION
B. Comply with mounting and anchoring requirements specified in Division 26 Section Vibration
and Seismic Controls for Electrical Systems.
C. Mount top of trim 74 inches above finished floor, unless otherwise indicated.
D. Mount plumb and rigid without distortion of box. Mount recessed panelboards with fronts
uniformly flush with wall finish.
G. Stub four 1-inchempty conduits from panelboard into accessible ceiling space or space
designated to be ceiling space in the future. Stub four 1-inchempty conduits into raised floor
space or below slab not on grade, with caps.
H. Arrange conductors in gutters into groups and bundle and wrap with wire ties after completing
load balancing.
3.2 IDENTIFICATION
B. Create a directory to indicate installed circuit loads after balancing panelboard loads. Obtain
approval before installing. Use a computer or typewriter to create directory; handwritten
directories are not acceptable.
3.3 CONNECTIONS
A. Ground equipment according to Division 26 Section Grounding and Bonding for Electrical
Systems.
B. Connect wiring according to Division 26 Section Low-Voltage Electrical Power Conductors and
Cables.
1. Test insulation resistance for each panelboard bus, component, connecting supply,
feeder, and control circuit.
2. Test continuity of each circuit.
B. Perform the following field tests and inspections and prepare test reports:
1. Perform each electrical test and visual and mechanical inspection stated in NETA ATS,
Section 7.5 for switches and Section 7.6 for molded-case circuit breakers. Certify
compliance with test parameters.
2. Correct malfunctioning units on-site, where possible, and retest to demonstrate
compliance; otherwise, replace with new units and retest.
C. Load Balancing: After Substantial Completion, but not more than 60 days after Final
Acceptance, measure load balancing and make circuit changes.
D. Infrared Scanning: After Substantial Completion, but not more than 60 days after Final
Acceptance, perform an infrared scanning of each panelboard. Remove panel fronts so joints
and connections are accessible to portable scanner. Perform remedial action for any
deficiencies detected.
3.5 CLEANING
END OF SECTION
DESIGN CRITERIA
END OF SECTION
June 2011 26 24 19 1
SECTION 26 24 19
MOTOR-CONTROL CENTERS
(Edited from DeCA June 2011 Design Criteria)
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1. AC, enclosed controllers rated 600 V and less, of the following types:
B. Related Sections:
1.2 SUBMITTALS
A. Product Data: For each type of enclosed controller. Include dimensions and manufacturer's
technical data on features, performance, electrical characteristics, ratings, and finishes.
B. LEED Submittals:
1. Product Data for Credit EA 5: For continuous metering equipment for energy
consumption.
D. Coordination Drawings: Floor plans, drawn to scale, showing dimensioned layout, required
working clearances, and required area above and around enclosed controllers where pipe and
ducts are prohibited. Show enclosed controller layout and relationships between electrical
components and adjacent structural and mechanical elements. Show support locations, type of
support, and weight on each support. Indicate field measurements.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
a. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified."
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
H. Operation and Maintenance Data: For enclosed controllers to include in emergency, operation,
and maintenance manuals. In addition to items specified in Division 01 Section Closeout
Procedures, include the following:
1. Routine maintenance requirements for enclosed controllers and all installed components.
I. Load-Current and Overload-Relay Heater List: Compile after motors have been installed and
arrange to demonstrate that selection of heaters suits actual motor nameplate full-load currents.
A. Manufacturer Qualifications: A qualified manufacturer. Maintain, within 100 milesof Project site,
a service center capable of providing training, parts, and emergency maintenance and repairs.
B. Source Limitations: Obtain enclosed controllers of a single type through one source from a
single manufacturer.
C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
A. Store enclosed controllers indoors in clean, dry space with uniform temperature to prevent
condensation. Protect enclosed controllers from exposure to dirt, fumes, water, corrosive
substances, and physical damage.
1. Notify Contracting Officer no fewer than ten days in advance of proposed interruption of
electrical service.
2. Indicate method of providing temporary utilities.
3. Do not proceed with interruption of electrical service without Contracting Officer's written
permission.
A. Coordinate layout and installation of enclosed controllers with other construction including
conduit, piping, equipment, and adjacent surfaces. Maintain required workspace clearances
and required clearances for equipment access doors and panels.
B. Coordinate size and location of concrete bases, if required. Cast anchor-bolt inserts into bases.
Concrete, reinforcement, and formwork requirements are specified in Division 03 Section Cast-
in-Place Concrete.
C. Coordinate installation of roof curbs, equipment supports, and roof penetrations. These items
are specified in Division 07 Section Roof Hatches.
D. Coordinate features of enclosed controllers and accessory devices with pilot devices and
control circuits to which they connect.
E. Coordinate features, accessories, and functions of each enclosed controller with ratings and
characteristics of supply circuit, motor, required control sequence, and duty cycle of motor and
load.
A. Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents.
1. Spare Fuses: Furnish one spare for every ten installed, but no fewer than one set of
three of each type and rating.
2. Indicating Lights: Two of each type installed.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manual Controller: NEMA ICS 2, general purpose, Class A, with toggle action and overload
element.
B. Magnetic Controller: NEMA ICS 2, Class A, full voltage, nonreversing, across the line, unless
otherwise indicated.
1. Control Circuit: 120 V; obtained from [integral control power transformer] <Insert
source of control power> with a control power [transformer] [source] of sufficient
capacity to operate connected pilot, indicating and control devices, plus 100 percent
spare capacity.
A. Star-Delta Controller: NEMA ICS 2, closed transition with adjustable time delay.
B. Part-Winding Controller: NEMA ICS 2, closed transition with separate overload relays for
starting and running sequences.
D. Solid-State, Reduced-Voltage Controller: NEMA ICS 2, suitable for use with NEMA MG 1,
Design B, polyphase, medium induction motors.
A. Multispeed Enclosed Controller: Match controller to motor type, application, and number of
speeds; include the following accessories:
1. Compelling relay to ensure that motor will start only at low speed.
2. Accelerating relay to ensure properly timed acceleration through speeds lower than that
selected.
3. Decelerating relay to ensure automatically timed deceleration through each speed.
2.5 ENCLOSURES
2.6 ACCESSORIES
C. Stop and Lockout Push-Button Station: Momentary-break, push-button station with a factory-
applied hasp arranged so padlock can be used to lock push button in depressed position with
control circuit open.
F. Meters: Panel type, 2-1/2-inchminimum size with 90- or 120-degree scale and plus or minus 2
percent accuracy. Where indicated, provide transfer device with an off position. Meters shall
indicate the following:
1. Inputs from sensors or 5-A current-transformer secondaries, and potential terminals rated
to 600 V.
2. Switch-selectable digital display of the following:
H. Phase-Failure and Undervoltage Relays: Solid-state sensing circuit with isolated output
contacts for hard-wired connection. Provide adjustable undervoltage setting.
I. Current-Sensing, Phase-Failure Relays for Bypass Controllers: Solid-state sensing circuit with
isolated output contacts for hard-wired connection; arranged to operate on phase failure, phase
A. Finish: Manufacturer's standard gray paint applied to factory-assembled and -tested enclosed
controllers before shipping.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and surfaces to receive enclosed controllers for compliance with requirements,
installation tolerances, <Insert Project-specific conditions>, and other conditions affecting
performance.
1. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. See Division 26 Section Common Work Results for Electrical for general installation
requirements.
B. For control equipment at walls, bolt units to wall or mount on lightweight structural-steel
channels bolted to wall. For controllers not at walls, provide freestanding racks complying with
Division 26 Section Common Work Results for Electrical.
D. Comply with mounting and anchoring requirements specified in Division 26 Section Vibration
and Seismic Controls for Electrical Systems.
E. Enclosed Controller Fuses: Install fuses in each fusible switch. Comply with requirements in
Division 26 Section Fuses.
B. Concrete base is specified in Division 26 Section Common Work Results for Electrical, and
concrete materials and installation requirements are specified in Division 03.
3.4 IDENTIFICATION
A. Identify enclosed controller, components, and control wiring according to Division 26 Section
Identification for Electrical Systems.
1. Connect selector switches to bypass only manual- and automatic-control devices that
have no safety functions when switch is in hand position.
2. Connect selector switches with enclosed controller circuit in both hand and automatic
positions for safety-type control devices such as low- and high-pressure cutouts, high-
temperature cutouts, and motor overload protectors.
3.6 CONNECTIONS
A. Conduit installation requirements are specified in other Division 26 Sections. Drawings indicate
general arrangement of conduit, fittings, and specialties.
B. Ground equipment according to Division 26 Section Grounding and Bonding for Electrical
Systems.
1. Test insulation resistance for each enclosed controller element, bus, component,
connecting supply, feeder, and control circuit.
2. Test continuity of each circuit.
C. Perform the following field tests and inspections and prepare test reports:
1. Perform each electrical test and visual and mechanical inspection, except optional tests,
stated in NETA ATS, "Motor Control - Motor Starters." Certify compliance with test
parameters.
2. Correct malfunctioning units on-site, where possible, and retest to demonstrate
compliance; otherwise, replace with new units and retest.
3.8 ADJUSTING
3.9 DEMONSTRATION
END OF SECTION
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1.2 DEFINITIONS
Retain abbreviation below that remains after this Section has been
edited.
1.3 SUBMITTALS
A. Product Data: Include technical descriptions, dimensions, rated capacities, weights, finishes,
and accessories for the following:
1. Feeder-bus assemblies.
2. Plug-in bus assemblies.
3. Bus plug-in devices.
B. Shop Drawings: For each type of bus assembly and plug-in device.
1. Show fabrication and installation details for enclosed bus assemblies. Include plans,
elevations, and sections of components. Designate components and accessories,
including clamps, brackets, hanger rods, connectors, fire stops, weather stops, straight
lengths, and fittings.
2. Indicate required clearances, method of field assembly, and location and size of each
field connection.
3. Detail connections to switchgear, switchboards, transformers, and panelboards.
C. Product Certificates: For each type of enclosed bus assembly, signed by product manufacturer.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
a. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified."
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
F. Operation and Maintenance Data: For enclosed bus assemblies to include in emergency,
operation, and maintenance manuals.
A. Source Limitations: Obtain enclosed bus assemblies and plug-in devices through one source
from a single manufacturer.
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
A. Deliver, store, and handle enclosed bus assemblies according to NEMA BU 1.1, "General
Instructions for Proper Handling, Installation, Operation and Maintenance of Busway Rated 600
Volts or Less."
A. Derate enclosed bus assemblies for continuous operation at indicated ampere ratings for
ambient temperature not exceeding 122 deg F [140 deg F] <Insert ambient temperature>.
1.7 COORDINATION
A. Coordinate layout and installation of enclosed bus assemblies and suspension system with
other construction that penetrates ceilings or floors or is supported by them, including light
fixtures, HVAC equipment, fire-suppression system, and partition assemblies.
B. Coordinate size and location of concrete curbs around openings for vertical bus. Concrete,
reinforcement, and formwork requirements are specified in Division 03.
A. Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents.
1. Plug-in Units: [10] <Insert number> percent of amount installed [for each size
indicated], but no fewer than <Insert number> unit(s).
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Voltage: [120/208] [240] [480] [277/480] V; 3 phase; [100] [200] [percent neutral
capacity].
2. Temperature Rise: 55 deg C above 40 deg C ambient maximum for continuous rated
current.
3. Bus Materials: Current-carrying [copper] [aluminum] conductors, fully insulated with
Class 130C insulation except at joints; plated surface at joints.
1. Voltage: [120/208] [240] [480] [277/480] V; 3 phase; [100] [200] [percent neutral
capacity].
2. Temperature Rise: 55 deg C above 40 deg C ambient maximum for continuous rated
current.
3. Bus Materials: Current-carrying [copper] [aluminum] conductors, fully insulated with
Class 130C insulation except at stabs and joints; plated surface at stabs and joints.
A. Fusible Switches: NEMA KS 1, heavy duty; with rejection-type fuse clips to accommodate
specified fuses; hookstick-operated handle, lockable with two padlocks, and interlocked with
cover in closed position. See Division 26 Section Fuses for fuses and fuse installation
requirements.
C. TVSS: NEMA 250, Type 1 enclosure with NEMA KS 1, fusible, disconnect switch and external
handle to isolate TVSS from busway. TVSS product and installation requirements are specified
in Division 26 Section Transient Voltage Suppression.
D. Motor Controllers: NEMA ICS 2, Class A, full voltage, nonreversing, across the line, unless
otherwise indicated.
1. Control Circuit: 120 V; obtained from [integral control power transformer] <Insert
source of control power> with a control power [transformer] [source] of enough
capacity to operate connected pilot, indicating and control devices, plus 100 percent
spare capacity.
2. Combination Controller: Factory-assembled, combination controller and disconnect
switch with or without overcurrent protection as indicated.
E. Multispeed Motor Controllers: Match controller to motor type, application, and number of
speeds; include the following accessories:
3.1 INSTALLATION
A. Support bus assemblies independent of supports for other elements such as equipment
enclosures at connections to panelboards and switchboards, pipes, conduits, ceilings, and
ducts.
1. Design each fastener and support to carry load indicated by seismic requirements and to
comply with seismic-restraint details according to Division 26 Section Vibration and
Seismic Controls for Electrical Systems.
B. Install expansion fittings at locations where bus assemblies cross building expansion joints.
Install at other locations so distance between expansion fittings does not exceed 90 percent of
manufacturer's recommended distance between fittings.
C. Install firestop fittings where bus assemblies penetrate fire-rated elements such as walls, floors,
and ceilings. Seal around penetrations according to Division 07 Section Firestopping, and as
directed by authorities having jurisdiction.
D. Install appropriate weatherseal fittings and flanges where bus assemblies penetrate exterior
elements such as walls or roofs. Seal around openings to make weathertight. See Division 07
Section Joint Sealants for materials and application.
E. Install a concrete curb at least 3 inches high around bus-assembly floor penetrations.
G. Tighten bus-assembly joints with torque wrench or similar tool recommended by bus-assembly
manufacturer. Tighten joints again after bus assemblies have been energized for 30 days.
H. Install bus-assembly plug-in units. Support connecting conduit independent of plug-in unit.
A. Ground equipment according to Division 26 Section Grounding and Bonding for Electrical
Systems.
B. Connect wiring according to Division 26 Section Low-Voltage Electrical Power Conductors and
Cables.
A. Perform the following field tests and inspections and prepare test reports:
1. After installing enclosed bus assemblies and after electrical circuitry has been energized,
test for compliance with requirements.
2. Perform each electrical test and visual and mechanical inspection stated in NETA ATS,
Section 7.4. Certify compliance with test parameters.
B. Remove and replace units that do not pass tests or inspections and retest as specified above.
C. Infrared Scanning: Two months after Substantial Completion, perform an infrared scan of bus
assembly including joints and plug-in units.
3.4 ADJUSTING
A. Set field-adjustable, circuit-breaker trip ranges and overload relay trip settings as indicated.
3.5 CLEANING
A. After completing system installation, clean enclosed bus assemblies, supports, and
accessories. Inspect exposed finishes and repair damaged finishes. Remove scratches, burrs,
and surface defects.
A. Provide final protection to ensure that moisture does not enter bus assembly.
END OF SECTION
DESIGN CRITERIA
June 2011 26 27 26 1
DeCA DESIGN CRITERIA HANDBOOK
26 27 26 WIRING DEVICES
11. Ground-type Duplex Receptacle at Commissary Ice Merchandiser: Provide at each Ice Merchandiser
location at front of Commissary. Verify quantity with Store Director.
12. Fax and Photocopy Machines: Provide dedicated electrical duplex receptacles for photocopy and fax
machines located within the admin area.
13. Offices and Administrative Areas: Provide at least four general-purpose duplex receptacles in the
wiring channel at each work station where modular work stations are provided. [Provide filtered
power at two receptacles should conditions warrant, i.e. in geographical areas where power
quality is very poor.] Where work stations are not next to a permanent wall, provide power poles to
connect electrical. Provide wall-mounted receptacles not more than 10' apart nor more than 5' along
the floor line from any accessible wall area more than 2' wide. Provide not less than one duplex
receptacle on each wall of any office. Do not count dedicated receptacles in satisfying the
requirements of this paragraph.
14. Mechanical Rooms and Utility Areas: Provide duplex receptacles sufficient for maintenance
operations, such that any point can be reached with a 25' extension cord.
15. Break Rooms: Provide dedicated GFCI receptacles for vending machines and for microwave,
refrigerator, and coffee service in addition to minimum general purpose receptacles.
16. Training Room: Provide receptacles for audiovisual device connections (overhead projectors,
videotape machines/TV, slide projectors, etc.), in addition to minimum general purpose receptacles.
Where a central table is provided, provide one or two drop cord receptacles at 7' AFF over the table
(depending on table dimensions).
17. Light Switches: Provide local control of lighting in each room. Provide light switches to control lights
at each entry to the room inside the room and opposite the hinge side of the door, except as
otherwise indicated for refrigerated processing rooms. Provide 3-way and 4-way switches, as
appropriate, for spaces with more than one entry. Where multiple entrances would require a large
number of 3- and 4-way switches, consider pilot control using relays. Provide multi-level control of
lighting in the Training Room and Conference Room to facilitate use of audio-visual presentations;
use separate switching of lamps or fixtures, or use dimmer controls for multi-level control. Use
occupancy sensors in offices, breakrooms, training rooms, rest rooms. Refer to Section 26 51 00 for
further details.
18. Loading Docks: Provide exterior receptacle at each loading dock for refrigerated trailers where
directed by DeCA. [note: This item is not generally needed at most stores. Trailers dont sit at the
dock very long. Exceptions: where deliveries are infrequequent and trailers may sit a long time.]
19. General Purpose Receptacles: 20-amp, 125 volt, single-phase, 3-wire, duplex Specification Grade
grounded type. Grey color to match stainless steel device plates unless otherwise indicated.
20. Waterproof Electrical Receptacles and Switches: Electrical receptacles and switches outdoors and in
the preparation areas shall be waterproof. Protect receptacle circuits by GFI breakers located in the
panel or with individual GFCI type receptacles (feed-through type not permitted). Surface mounted
junction boxes located in processing areas subject to hot water wash down shall be a sealed type
conforming to the NFPA classification for wet areas.
21. Light Switches: Specification grade, 20-Amp, A.C. only, voltage rating and pole configuration per
application. Grey color to match stainless steel device plates unless otherwise indicated.
22. Isolated Ground Receptacles: Provide orange faced isolated ground duplex receptacles for all POS
system equipment and other outlets served from the POS system isolated ground panelboard.
Receptacles to be rated 20 Amp, 125 volt, single phase, 3 wire.
23. Special Purpose Receptacles: Provide appropriate specification grade receptacles for equipment
requiring ratings or pole configurations other than those addressed above. Grey color to match
device plates unless otherwise indicated.
24. Multi-Outlet Assemblies (Plugmold): Provide where indicated. Aluminum or steel body with
receptacle outlets as indicated in the drawings or in other sections of this Handbook. Unless
otherwise indicated, receptacles shall be duplex grounding type 125V 15A receptacles, spaced on
12" centers.
June 2011 26 27 26 2
DeCA DESIGN CRITERIA HANDBOOK
26 27 26 WIRING DEVICES
25. Device Plates: Stainless Steel, brushed finish, in finished areas. Galvanized steel, for flush or
surface mount as appropriate, in unfinished areas. Where cast metal boxes are used, plates to
match box. Weatherproof covers in wet locations. Screws to match in all cases.
26. Mounting height of devices: Unless otherwise noted or required for special purposes, mount all
devices of like kind at the same height throughout the facility, and with sensitivity to ABA
requirements.
A. Light Switches: 48" AFF
B. Duplex Receptacles
1). Above Countertops 8" Above Counter - but coordinate with architectural
features
2). For Refrigerators 8" higher than adjacent countertop, or 48" AFF if no countertop
3). In Processing Coolers 48" AFF
4). Other Locations 12" to 16" AFF; coordinate with adjacent
communications
END OF SECTION
June 2011 26 27 26 3
SECTION 26 27 26
WIRING DEVICES
(Edited from DeCA June 2011 Design Criteria)
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1.2 DEFINITIONS
Retain abbreviations that remain after this Section has been edited.
1.3 SUBMITTALS
B. Shop Drawings: List of legends and description of materials and process used for premarking
wall plates.
A. Source Limitations: Obtain each type of wiring device through one source from a single
manufacturer.
1.5 COORDINATION
PART 2 - PRODUCTS
2.1 MANUFACTURERS
1. Wiring Devices:
2. Multioutlet Assemblies:
3. Telephone/Power Poles:
2.2 RECEPTACLES
C. GFCI Receptacles: Straight blade, non-feed-through type, Heavy-Duty grade, with integral
NEMA WD 6, Configuration 5-20R duplex receptacle; complying with UL 498 and UL 943.
Design units for installation in a 2-3/4-inch- deep outlet box without an adapter.
E. TVSS Receptacles: Straight blade, NEMA WD 6, Configuration 5-20R, with integral TVSS in
line to ground, line to neutral, and neutral to ground.
1. TVSS Components: Multiple metal-oxide varistors; with a nominal clamp level rating of
500 volts and minimum single transient pulse energy dissipation of 140 J line to neutral,
and 70 J line to ground and neutral to ground.
2. Active TVSS Indication: Visual only with light visible in face of device to indicate device is
"active" or "no longer in service."
F. Industrial Heavy-Duty Pin and Sleeve Devices: Comply with IEC 309-1.
1. Body: Nylon with screw-open cable-gripping jaws and provision for attaching external
cable grip.
2. External Cable Grip: Woven wire-mesh type made of high-strength galvanized-steel wire
strand, matched to cable diameter, and with attachment provision designed for
corresponding connector.
Delete this Article unless required cord and plug sets for equipment
are furnished by Government or specified in other Sections.
Coordinate with other Sections and with Part 3.
A. Description: Match voltage and current ratings and number of conductors to requirements of
equipment being connected.
2.5 SWITCHES
A. Single- and Double-Pole Switches: Comply with DSCC W-C-896F and UL 20.
C. Dimmer Switches: Modular, full-wave, solid-state units with integral, quiet on/off switches and
audible frequency and EMI/RFI filters.
D. Receptacles: 20A 125V grounding duplex on 12 inch centers, or 20A 125V grounding single on
6 inch centers where indicated on Drawings.
A. Description: Factory-assembled and -wired units to extend power and voice and data
communication from distribution wiring concealed in ceiling to devices or outlets in pole near
floor.
1. Poles: Nominal 2.5-inch- square cross section, with height adequate to extend from floor
to at least 6 inches above ceiling (or other height indicated on Drawings), and with
separate channels for power wiring and voice and data communication cabling.
2. Mounting: Ceiling trim flange with concealed bracing arranged for positive connection to
ceiling supports; with pole foot and carpet pad attachment.
2.9 FINISHES
1. Wiring Devices Connected to Normal Power System: Gray, unless otherwise indicated or
required by NFPA 70.
2. Wiring Devices Connected to Emergency Power System: Red.
3. TVSS Devices: Blue.
4. Isolated-Ground Receptacles: Orange; or as specified above, with orange triangle on
face.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install devices and assemblies level, plumb, and square with building lines.
B. Install wall dimmers to achieve indicated rating after derating for ganging according to
manufacturer's written instructions.
C. Install unshared neutral conductors on line and load side of dimmers according to
manufacturers' written instructions.
D. Arrangement of Devices: Unless otherwise indicated, mount flush, with long dimension vertical,
and with grounding terminal of receptacles on bottom. Group adjacent switches under single,
multigang wall plates. Group adjacent voice or data outlets under single, multigang wall plates.
E. Remove wall plates and protect devices and assemblies during painting.
F. Adjust locations of floor service outlets and service poles to suit arrangement of partitions and
furnishings.
G. Devices installed within gondola shelving are to be wired with Type MC metal-clad cable run in
the protected spaces behind back panels and under the base shelf, supported above the floor
by the holes in the base shelf supports. Coordinate the final exact locations with store
operations personnel through the Governments Designated Inspector. Receptacles mounted in
the toe space below the base shelf are to be aligned with the long dimension horizontal.
3.2 IDENTIFICATION
1. Receptacles: Identify panelboard and circuit number from which served. Use engraved
machine printing with black-filled lettering on face of plate, and durable wire markers or
tags inside outlet boxes.
3.3 CONNECTIONS
A. Ground equipment according to Division 26 Section Grounding and Bonding for Electrical
Systems.
A. Perform the following field tests and inspections and prepare test reports:
1. After installing wiring devices and after electrical circuitry has been energized, test for
proper polarity, ground continuity, and compliance with requirements.
B. Remove malfunctioning units, replace with new units, and retest as specified above.
END OF SECTION
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
D. Other Action Submittals (Due before final setting of overcurrent devices prior to energizing the
service):
1. Coordination-study input data, including completed computer program input data sheets.
2. Coordination-study report.
3. Equipment evaluation report.
4. Setting report.
A. Studies shall use computer programs that are distributed nationally and are in wide use.
Software algorithms shall comply with requirements of standards and guides specified in this
Section. Manual calculations are not acceptable.
E. Comply with IEEE 242 for short-circuit currents and coordination time intervals.
PART 2 - PRODUCTS
D. Optional Features:
1. Arcing faults.
2. Simultaneous faults.
3. Explicit negative sequence.
4. Mutual coupling in zero sequence.
3.1 EXAMINATION
A. Examine Project overcurrent protective device submittals for compliance with electrical
distribution system coordination requirements and other conditions affecting performance.
Devices to be coordinated are indicated on Drawings.
B. Proceed with coordination study only after relevant equipment submittals have been assembled.
Overcurrent protective devices not submitted for approval with coordination study may not be
used in study.
B. Study electrical distribution system from normal and alternate power sources throughout
electrical distribution system for Project and use approved computer software program to
calculate values. Include studies of system-switching configurations and alternate operations
that could result in maximum fault conditions.
C. Calculate momentary and interrupting duties on the basis of maximum available fault current.
D. Calculations to verify interrupting ratings of overcurrent protective devices shall comply with the
following:
E. Study Report: Enter calculated X/R ratios and interrupting (5-cycle) fault currents on electrical
distribution system diagram of the report. List other output values from computer analysis,
including momentary (1/2-cycle), interrupting (5-cycle), and 30-cycle fault-current values for 3-
phase, 2-phase, and phase-to-ground faults.
A. Gather and tabulate the following input data to support coordination study:
1. Product Data for overcurrent protective devices specified in other Division 26 Sections
and involved in overcurrent protective device coordination studies. Use equipment
designation tags that are consistent with electrical distribution system diagrams,
overcurrent protective device submittals, input and output data, and recommended
device settings.
2. Impedance of utility service entrance.
a. Load current that is the basis for sizing continuous ratings of circuits for cables and
equipment.
b. Circuit-breaker and fuse-current ratings and types.
c. Relays and associated power and current transformer ratings and ratios.
d. Transformer kilovolt amperes, primary and secondary voltages, connection type,
impedance, and X/R ratios.
e. Generator kilovolt amperes, size, voltage, and source impedance.
f. Cables. Indicate conduit material, sizes of conductors, conductor insulation, and
length.
g. Busway ampacity and impedance.
h. Motor horsepower and code letter designation according to NEMA MG 1.
a. Special load considerations, including starting inrush currents and frequent starting
and stopping.
b. Magnetic inrush current overload capabilities of transformers.
c. Motor full-load current, locked rotor current, service factor, starting time, type of
start, and thermal-damage curve.
d. Ratings, types, and settings of utility company's overcurrent protective devices.
e. Special overcurrent protective device settings or types stipulated by utility
company.
f. Time-current-characteristic curves of devices indicated to be coordinated.
g. Manufacturer, frame size, interrupting rating in amperes rms symmetrical, ampere
or current sensor rating, long-time adjustment range, short-time adjustment range,
and instantaneous adjustment range for circuit breakers.
h. Manufacturer and type, ampere-tap adjustment range, time-delay adjustment
range, instantaneous attachment adjustment range, and current transformer ratio
for overcurrent relays.
i. Panelboards, switchboards, motor-control center ampacity, and interrupting rating
in amperes rms symmetrical.
B. Perform coordination study and prepare a written report using the results of fault-current study
and approved computer software program. Comply with IEEE 399.
1. Comply with NFPA 70 for overcurrent protection of circuit elements and devices.
2. See Editing Instruction No. 4 in the Evaluations for discussion of two publications listed in
first paragraph below.
3. Comply with [IEEE 141] [IEEE 242] recommendations for fault currents and time
intervals.
C. Motors served by voltages more than 600 V shall be protected according to IEEE 620.
A. Protect cables against damage from fault currents according to ICEA P-32-382, ICEA P-45-482,
and conductor melting curves in IEEE 242.
B. Verify adequacy of phase conductors at maximum three-phase bolted fault currents, equipment
grounding conductors, and grounding electrode conductors at maximum ground-fault currents.
a. Device tag.
b. Relay-current transformer ratios; and tap, time-dial, and instantaneous-pickup
values.
c. Circuit-breaker sensor rating; and long-time, short-time, and instantaneous
settings.
d. Fuse-current rating and type.
e. Ground-fault relay-pickup and time-delay settings.
a. Device tag.
b. Voltage and current ratio for curves.
c. Three-phase and single-phase damage points for each transformer.
d. No damage, melting, and clearing curves for fuses.
e. Transformer inrush points.
f. Maximum fault-current cutoff point.
B. Testing: Engage a qualified testing agency to perform the following device setting and to
prepare test reports.
1. After installing overcurrent protective devices and during energizing process of electrical
distribution system, perform the following:
END OF SECTION
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data: Include the following for each fuse type indicated:
1. For each fuse having adjusted ratings, include location of fuse, original fuse rating, local
ambient temperature, and adjusted fuse rating.
2. Provide manufacturer's technical data on which ambient temperature adjustment
calculations are based.
C. Operation and Maintenance Data: For fuses to include in emergency, operation, and
maintenance manuals.
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
A. Where ambient temperature to which fuses are directly exposed is less than 40 deg F or more
than 100 deg F, apply manufacturer's ambient temperature adjustment factors to fuse ratings.
1.5 COORDINATION
A. Coordinate fuse ratings with utilization equipment nameplate limitations of maximum fuse size.
A. Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents.
1. Fuses: Quantity equal to ten percent of each fuse type and size, but no fewer than 3 of
each type and size.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Characteristics: NEMA FU 1, nonrenewable cartridge fuse; class and current rating indicated;
voltage rating consistent with circuit voltage.
A. Cabinet: Wall-mounted, 0.05-inch- thick steel unit with full-length, recessed piano-hinged door
and key-coded cam lock and pull.
1. Size: Adequate for storage of spare fuses specified with 15 percent spare capacity
minimum.
2. Finish: Gray, baked enamel.
3. Identification: "SPARE FUSES" in 1-1/2-inch- high letters on exterior of door.
4. Fuse Pullers: For each size of fuse.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine utilization equipment nameplates and installation instructions. Install fuses of sizes
and with characteristics appropriate for each piece of equipment.
B. Evaluate ambient temperatures to determine if fuse rating adjustment factors must be applied to
fuse ratings.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
A. Service Entrance: Class [L, fast acting] [L, time delay] [RK1, fast acting] [RK1, time delay]
[J, fast acting] [J, time delay] [T, fast acting].
B. Feeders: Class [L, fast acting] [L, time delay] [RK1, fast acting] [RK1, time delay] [J, fast
acting] [J, time delay] [RK5, time delay].
D. Other Branch Circuits: Class [RK1, time delay] [RK5, time delay] [J, fast acting] [J, time
delay].
3.3 INSTALLATION
A. Install fuses in fusible devices. Arrange fuses so rating information is readable without
removing fuse.
3.4 IDENTIFICATION
A. Install labels indicating fuse replacement information on inside door of each fused switch or
other fusible device.
END OF SECTION
DESIGN CRITERIA
END OF SECTION
June 2011 26 28 16 1
SECTION 26 28 16
ENCLOSED SWITCHES AND CIRCUIT BREAKERS
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1.2 DEFINITIONS
Retain abbreviations that remain after this Section has been edited.
1.3 SUBMITTALS
A. Product Data: For each type of enclosed switch, circuit breaker, accessory, and component
indicated. Include dimensioned elevations, sections, weights, and manufacturers' technical
data on features, performance, electrical characteristics, ratings, and finishes.
1. Enclosure types and details for types other than NEMA 250, Type 1.
2. Current and voltage ratings.
3. Short-circuit current rating.
a. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified."
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
F. Operation and Maintenance Data: For enclosed switches and circuit breakers to include in
emergency, operation, and maintenance manuals. In addition to items specified in Division 01
Section Closeout Procedures, include the following:
1. Manufacturer's written instructions for testing and adjusting enclosed switches and circuit
breakers.
2. Time-current curves, including selectable ranges for each type of circuit breaker.
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
C. Product Selection for Restricted Space: Drawings indicate maximum dimensions for enclosed
switches and circuit breakers, including clearances between enclosures, and adjacent surfaces
and other items. Comply with indicated maximum dimensions.
A. Environmental Limitations: Rate equipment for continuous operation under the following
conditions, unless otherwise indicated:
1. Ambient Temperature: Not less than minus 22 deg F and not exceeding 104 deg F.
2. Altitude: Not exceeding 6600 feet.
1.6 COORDINATION
A. Coordinate layout and installation of switches, circuit breakers, and components with other
construction, including conduit, piping, equipment, and adjacent surfaces. Maintain required
workspace clearances and required clearances for equipment access doors and panels.
A. Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents.
a. Potential Transformer Fuses: One set of each size and type used.
b. Control-Power Fuses: One set of each size and type used.
c. Fuses for Fusible Switches: One set of each size and type used.
d. Fuses for Fused Power Circuit Devices: One set of each size and type used.
2. Spare Indicating Lights: [Six sets] [One set] of each type installed.
2.1 MANUFACTURERS
A. In other Part 2 articles where titles below introduce lists, the following requirements apply to
product selection:
A. Available Manufacturers:
B. Fusible Switch, 1200 A and Smaller: NEMA KS 1, Type HD, with clips or bolt pads to
accommodate specified fuses, lockable handle with capability to accept two padlocks, and
interlocked with cover in closed position.
C. Nonfusible Switch, 1200 A and Smaller: NEMA KS 1, Type HD, lockable handle with capability
to accept two padlocks, and interlocked with cover in closed position.
D. Accessories:
1. Equipment Ground Kit: Internally mounted and labeled for copper and aluminum ground
conductors.
2. Neutral Kit: Internally mounted; insulated, capable of being grounded, and bonded; and
labeled for copper and aluminum neutral conductors.
3. Auxiliary Contact Kit: Auxiliary set of contacts arranged to open before switch blades
open.
A. Available Manufacturers:
a. Instantaneous trip.
b. Long- and short-time pickup levels.
c. Long- and short-time time adjustments.
d. Ground-fault pickup level, time delay, and I2t response.
4. Current-Limiting Circuit Breakers: Frame sizes 400 A and smaller and let-through ratings
less than NEMA FU 1, RK-5.
5. GFCI Circuit Breakers: Single- and two-pole configurations with [5] [30]-mA trip
sensitivity.
D. Molded-Case Switches: Molded-case circuit breaker with fixed, high-set instantaneous trip only,
and short-circuit withstand rating equal to equivalent breaker frame size interrupting rating.
2.4 ENCLOSURES
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine elements and surfaces to receive enclosed switches and circuit breakers for
compliance with installation tolerances and other conditions affecting performance.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
A. Coordinate size and location of concrete bases. Verify structural requirements with structural
engineer.
B. Concrete base is specified in Division 26 Section Common Work Results for Electrical, and
concrete materials and installation requirements are specified in Division 03.
3.3 INSTALLATION
A. Comply with applicable portions of NECA 1, NEMA PB 1.1, and NEMA PB 2.1 for installation of
enclosed switches and circuit breakers.
C. Comply with mounting and anchoring requirements specified in Division 26 Section Vibration
and Seismic Controls for Electrical Systems.
D. Temporary Lifting Provisions: Remove temporary lifting eyes, channels, and brackets and
temporary blocking of moving parts from enclosures and components.
3.4 IDENTIFICATION
A. Manufacturer's Field Service: For the equipment listed below, engage a factory-authorized
service representative to inspect, test, and adjust field-assembled components and equipment
installation, including connections, and to assist in field testing. Report results in writing.
1. <Insert Equipment(s)>
C. Perform the following field tests and inspections and prepare test reports:
a. Initial Infrared Scanning: After Substantial Completion, but not more than 60 days
after Final Acceptance, perform an infrared scan of each enclosed switch and
circuit breaker. Open or remove doors or panels so connections are accessible to
portable scanner.
b. Instruments, Equipment and Reports:
3.6 ADJUSTING
3.7 CLEANING
A. On completion of installation, vacuum dirt and debris from interiors; do not use compressed air
to assist in cleaning.
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1. Packaged diesel-engine generator sets with the following features and accessories:
B. Related Sections:
1.2 DEFINITIONS
Retain abbreviation and terms that remain after this Section has
been edited.
A. Operational Bandwidth: The total variation from the lowest to highest value of a parameter over
the range of conditions indicated, expressed as a percentage of the nominal value of the
parameter.
B. Steady-State Voltage Modulation: The uniform cyclical variation of voltage within the
operational bandwidth, expressed in Hertz or cycles per second.
1.3 SUBMITTALS
B. Shop Drawings: Detail equipment assemblies and indicate dimensions, weights, loads,
required clearances, method of field assembly, components, and location and size of each field
connection.
1. Dimensioned outline plan and elevation drawings of engine-generator set and other
components specified.
2. Design Calculations: Signed and sealed by a qualified professional engineer. Calculate
requirements for selecting vibration isolators and seismic restraints and for designing
vibration isolation bases.
3. Vibration Isolation Base Details: Signed and sealed by a qualified professional engineer.
Detail fabrication, including anchorages and attachments to structure and to supported
equipment. Include base weights.
4. Wiring Diagrams: Power, signal, and control wiring.
C. Welding certificates.
D. Manufacturer Seismic Qualification Certification: Submit certification that day tank, engine-
generator set, batteries, battery racks, accessories, and components will withstand seismic
forces defined in Division 26 Section Vibration and Seismic Controls for Electrical Systems.
Include the following:
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
a. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified."
b. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified and the unit
will be fully operational after the seismic event."
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
G. Certified Test Reports: For components and accessories that are equivalent, but not identical,
to those tested on prototype unit.
I. Test Reports:
1. Report of factory test on units to be shipped for this Project, showing evidence of
compliance with specified requirements.
2. Report of sound generation.
K. Operation and Maintenance Data: For packaged engine generators to include in emergency,
operation, and maintenance manuals. In addition to items specified in Division 01 Section
Closeout Procedures, include the following:
1. List of tools and replacement items recommended to be stored at the Project for ready
access. Include part and drawing numbers, current unit prices, and source of supply.
1. Maintenance Proximity: Not more than four hours' normal travel time from Installer's
place of business to Project site.
C. Source Limitations: Obtain packaged generator sets and auxiliary components through one
source from a single manufacturer.
D. Product Options: Drawings indicate size, profiles, and dimensional requirements of packaged
generator sets and are based on the specific system indicated.
E. Welding: Qualify procedures and personnel according to ASME Boiler and Pressure Vessel
Code: Section IX for welding exhaust-system piping.
F. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
I. Comply with NFPA 110 requirements for Level [1] [2] emergency power supply system.
J. Engine Exhaust Emissions: Comply with applicable state and local government requirements.
1.5 COORDINATION
A. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases. Concrete,
reinforcement, and formwork requirements are specified in Division 03.
1.6 WARRANTY
A. Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents.
1. Fuses: One for every 10 of each type and rating, but not less than one of each.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
B. Power Output Ratings: Nominal ratings as indicated, with capacity as required to operate as a
unit as evidenced by records of prototype testing.
E. Nameplates: Each major system component shall be equipped with a nameplate to identify
manufacturer's name and address, and model and serial number of component.
G. Mounting Frame: Adequate strength and rigidity to maintain alignment of mounted components
without depending on concrete foundation. Mounting frame shall be free from sharp edges and
corners and shall have lifting attachments arranged for lifting with slings without damaging
components.
A. Meet ISO 8528-5 G3 requirements. Oversizing generator compared with the rated power
output of the engine is permissible to meet specified performance.
1. Nameplate Data for Oversized Generator: Show ratings required by the Contract
Documents rather than ratings that would normally be applied to generator size installed.
B. Steady-State Voltage Operational Bandwidth: +/- 2 percent of rated output voltage from no load
to full load.
D. Transient Voltage Performance: Not more than 10 percent variation for 50 percent step-load
increase or decrease. Voltage shall recover and remain within the steady-state operating band
within 0.5 second.
E. Steady-State Frequency Operational Bandwidth: Plus or minus 0.25 percent of rated frequency
from no load to full load.
F. Steady-State Frequency Stability: When system is operating at any constant load within the
rated load, there shall be no random speed variations outside the steady-state operational band
and no hunting or surging of speed.
G. Transient Frequency Performance: Less than 5.0 percent variation for a 50 percent step-load
increase or decrease. Frequency shall recover and remain within the steady-state operating
band within three seconds.
H. Output Waveform: At no load, harmonic content measured line to neutral shall not exceed 2
percent total with no slot ripple. The telephone influence factor, determined according to
NEMA MG 1, shall not exceed 50 percent.
I. Sustained Short-Circuit Current: For a 3-phase, bolted short circuit at system output terminals,
the system shall supply a minimum of 300 percent of rated full-load current for not less than 10
seconds and then clear the fault automatically, without damage to winding insulation or other
generator system components.
K. Start Time: Comply with NFPA 110, Type 10, system requirements.
1. Ambient Temperature: [41 to 104 deg F] [5 to 104 deg F] [-40 to 158 deg F].
1. [High salt-dust content in the air due to sea-spray evaporation] <Insert unusual
condition>.
2.5 ENGINE
1. Filter and Strainer: Rated to remove 90 percent of particles 5 micrometers and smaller
while passing full flow.
2. Thermostatic Control Valve: Control flow in system to maintain optimum oil temperature.
Unit shall be capable of full flow and is designed to be fail-safe.
3. Crankcase Drain: Arranged for complete gravity drainage to an easily removable
container with no disassembly and without use of pumps, siphons, special tools, or
appliances.
1. Main Fuel Pump: Mounted on engine. Pump ensures adequate primary fuel flow under
starting and load conditions.
2. Relief-Bypass Valve: Automatically regulates pressure in fuel line and returns excess
fuel to source.
F. Coolant Jacket Heater: Electric-immersion type, factory installed in coolant jacket system.
Comply with NFPA 110 requirements for Level 1 equipment for heater capacity.
C. Expansion Tank: Constructed of welded steel plate and rated to withstand maximum closed-
loop coolant system pressure for engine used. Equip with gage glass and petcock.
1. Rating: 50-psig maximum working pressure with coolant at 180 deg F, and
noncollapsible under vacuum.
2. End Fittings: Flanges or steel pipe nipples with clamps to suit piping and equipment
connections.
B. Base-Mounted Fuel Oil Tank: Factory installed and piped, complying with UL 142 fuel oil tank.
Features include the following:
A. Muffler: Industrial type, sized as recommended by engine manufacturer; sound level in the 20-
to 75-Hz frequency band measured at a distance of 25 feet from exhaust discharge shall be
87 dBA or less.
B. Condensate Drain for Muffler: Schedule 40, black steel pipe connected to muffler drain outlet
through a petcock.
C. Connection from Engine to Exhaust System: Flexible section of corrugated stainless-steel pipe.
D. Connection from Exhaust Pipe to Muffler: Stainless-steel expansion joint with liner.
A. Description: Heavy-duty, engine-mounted air cleaner with replaceable dry-filter element and
"blocked filter" indicator.
A. Description: [12] [24]-V electric, with negative ground and including the following items:
1. Components: Sized so they will not be damaged during a full engine-cranking cycle with
ambient temperature at maximum specified in "Environmental Conditions" Paragraph in
"Service Conditions" Article.
2. Cranking Motor: Heavy-duty unit that automatically engages and releases from engine
flywheel without binding.
A. Functional Description: When mode-selector switch on the control and monitoring panel is in
the automatic position, remote-control contacts in one or more separate automatic transfer
switches initiate starting and stopping of the generator set. When mode-selector switch is
switched to the on position, the generator set starts. The off position of the same switch
initiates generator-set shutdown. When generator set is running, specified system or equipment
failures or derangements automatically shut down the generator set and initiate alarms.
Operation of a remote emergency-stop switch also shuts down the generator set.
B. Configuration: Operating and safety indications, protective devices, basic system controls, and
engine gages shall be grouped in a common control and monitoring panel mounted on the
generator set. Mounting method shall isolate the control panel from generator-set vibration.
C. Indicating and protective devices and controls shall include those required by NFPA 110 for a
Level 1 system, and the following:
1. AC voltmeter.
2. AC ammeter.
3. AC frequency meter.
4. DC voltmeter (alternator battery charging).
5. Engine-coolant temperature gage.
6. Engine lubricating-oil pressure gage.
D. Supporting Items: Include sensors, transducers, terminals, relays, and other devices and
include wiring required to support specified items. Locate sensors and other supporting items
on engine or generator, unless otherwise indicated.
E. Common Remote Audible Alarm: Comply with NFPA 110 requirements for Level 1 systems.
Include necessary contacts and terminals in control and monitoring panel.
1. Overcrank shutdown.
2. Coolant low-temperature alarm.
3. Control switch not in auto position.
4. Battery-charger malfunction alarm.
5. Battery low-voltage alarm.
F. Remote Alarm Annunciator: Comply with NFPA 99. Labeled LED shall identify each alarm
event. Common audible signal shall sound for alarm conditions. Silencing switch in face of
panel shall silence signal without altering visual indication. Connect so that after an alarm is
silenced, clearing of initiating condition will reactivate alarm until silencing switch is reset.
Cabinet and faceplate are surface- or flush-mounting type to suit mounting conditions indicated.
G. Remote Emergency-Stop Switch: Flush; wall mounted, unless otherwise indicated; and labeled.
Push button shall be protected from accidental operation.
A. Generator Circuit Breaker: Molded-case, electronic full function- type; 100 percent rated;
complying with NEMA AB 1 and UL 489.
B. Drive: Generator shaft shall be directly connected to engine shaft. Exciter shall be rotated
integrally with generator rotor.
D. Stator-Winding Leads: Brought out to terminal box to permit future reconnection for other
voltages if required.
E. Construction shall prevent mechanical, electrical, and thermal damage due to vibration,
overspeed up to 125 percent of rating, and heat during operation at 110 percent of rated
capacity.
F. Excitation shall use no slip or collector rings, or brushes, and shall be arranged to sustain
generator output under short-circuit conditions as specified.
G. Enclosure: Dripproof.
1. Adjusting rheostat on control and monitoring panel shall provide plus or minus 5 percent
adjustment of output-voltage operating band.
2. Provide automatic compensation for feeder voltage drop between the generator output
terminals and the distribution panel, to maintain stable voltage at the panel.
J. Strip Heater: Thermostatically controlled unit arranged to maintain stator windings above dew
point.
K. Windings: Two-thirds pitch stator winding and fully linked amortisseur winding.
2.15 FINISHES
A. Indoor and Outdoor Enclosures and Components: Manufacturer's standard enamel over
corrosion-resistant pretreatment and compatible standard primer.
A. Prototype Testing: Factory test engine-generator set using same engine model, constructed of
identical or equivalent components and equipped with identical or equivalent accessories.
1. Tests: Comply with NFPA 110, Level 1 energy converters in Paragraphs 3.2.1, 3.2.1.1,
and 3.2.1.2.
2. Generator Tests: Comply with IEEE 115.
B. Project-Specific Equipment Tests: Before shipment, factory test engine-generator set and other
system components and accessories manufactured specifically for this Project. Perform tests at
rated load and power factor. Include the following tests:
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas, equipment bases, and conditions, with Installer present, for compliance with
requirements for installation and other conditions affecting packaged engine-generator
performance.
B. Examine roughing-in of piping systems and electrical connections. Verify actual locations of
connections before packaged engine-generator installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
A. Coordinate size and location of concrete bases. Verify structural requirements with structural
engineer.
B. Concrete base is specified in Division 26 Section Common Work Results for Electrical, and
concrete materials and installation requirements are specified in Division 03.
3.3 INSTALLATION
C. Vibration Isolation: Mount packaged engine generators on vibration isolation equipment base
as specified in Division 21 Section Fire-Suppression Sprinkler Systems, Division 22 Section
Vibration and Seismic Controls for Plumbing Piping and Equipment, Division 23 Section
Vibration and Seismic Controls for HVAC Piping and Equipment.
E. Install exhaust-system piping. Extend to point of termination outside structure. Size piping
according to manufacturer's written instructions.
1. Install condensate drain piping for engine exhaust system. Extend drain piping from low
points of exhaust system and from muffler to condensate traps and to point of disposition.
2. Support exhaust piping and muffler with pipe hangers spaced a maximum of 20 feet
horizontally and at each floor vertically. Pipe hangers are specified in Division 21 Fire-
Suppression Sprinkler Systems, Division 22 Section Common Work Results for
Plumbing, and Division 23 Section Hangers and Supports for HVAC Piping and
Equipment.
3. Restrain exhaust piping and mufflers with cable-type bracing assemblies. Cable-type
bracing assemblies are specified in Division 26 Section Vibration and Seismic Controls
for Electrical Systems.
F. Electrical Wiring: Install electrical devices furnished by equipment manufacturers but not
specified to be factory mounted.
3.4 CONNECTIONS
a. Diesel storage tanks, tank accessories, piping, valves, and specialties for fuel
systems outside the building are specified in Division 23 Section Fuel Oil
Distribution.
b. Diesel fuel piping, valves, and specialties inside the building are specified in
Division 23 Section Fuel Oil Piping.
B. Ground equipment according to Division 26 Section Grounding and Bonding for Electrical
Systems.
C. Connect wiring according to Division 26 Section Low-Voltage Electrical Power Conductors and
Cables.
3.5 IDENTIFICATION
1. Perform each electrical test and visual and mechanical inspection stated in NETA ATS,
Sections 7.15.2.1 and 7.22.1 (except for vibration baseline test). Certify compliance with
test parameters.
2. Perform tests recommended by manufacturer.
3. NFPA 110 Acceptance Tests: Perform tests required by NFPA 110 that are additional to
those specified here including, but not limited to, the following:
a. Measure charging voltage and voltages between available battery terminals for
full-charging and float-charging conditions. Check electrolyte level and specific
gravity under both conditions.
b. Test for contact integrity of all connectors. Perform an integrity load test and a
capacity load test for the battery.
c. Verify acceptance of charge for each element of the battery after discharge.
d. Verify that measurements are within manufacturer's specifications.
5. Battery-Charger Tests: Verify specified rates of charge for both equalizing and float-
charging conditions.
6. System Integrity Tests: Methodically verify proper installation, connection, and integrity
of each element of engine-generator system before and during system operation. Check
for air, exhaust, and fluid leaks.
C. Coordinate tests with tests for transfer switches and run them concurrently.
D. Test instruments shall have been calibrated within the last 12 months, traceable to standards of
the National Institute for Standards and Technology, and adequate for making positive
observation of test results. Make calibration records available for examination on request.
E. Leak Test: After installation, charge system and test for leaks. Repair leaks and retest until no
leaks exist.
F. Operational Test: After electrical circuitry has been energized, start units to confirm proper
motor rotation and unit operation.
G. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and
equipment.
I. Retest: Correct deficiencies identified by tests and observations and retest until specified
requirements are met.
J. Report results of tests and inspections in writing. Record adjustable relay settings and
measured insulation resistances, time delays, and other values and observations. Attach a
label or tag to each tested component indicating satisfactory completion of tests.
B. Inspect field-assembled components and equipment installation, including piping and electrical
connections. Report results in writing.
3.8 DEMONSTRATION
END OF SECTION
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1.2 SUBMITTALS
A. Product Data: For each type of product indicated. Include dimensions; shipping, installed, and
operating weights of multiple capacitor cells or elements; and data on features, ratings, and
performance.
C. Field Test Reports: Indicate and interpret test results for compliance with performance
requirements.
D. Maintenance Data: For equipment to include in maintenance manuals specified in Division 01.
Include the following:
1. Lists of spare parts and replacement components recommended for storage at Project
site.
2. Detailed instructions covering operation under both normal and abnormal conditions.
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Capacitor Cells: Dry, metallized-dielectric, self-healing type. Each cell shall be encapsulated in
thermosetting resin inside plastic container.
NFPA 70, Article 460, requires that capacitors have a way to reduce
residual voltage to 50 V or less within 60 seconds of disconnection
from supply source. If capacitor is directly connected to a motor or
other equipment terminals, windings of connected unit may serve
the above function. Paragraph below applies if resistors are to
provide or back up capacitor discharge function.
D. Discharge Resistors: Factory installed and wired. Resistors may be omitted if permitted by
NFPA 70.
E. Enclosure: NEMA 250, steel or aluminum, arranged to contain the fluid leakage from capacitor
cells; factory equipped with mounting brackets suitable for type of mounting indicated.
B. Internal Wiring: Factory wired, ready for field connection to external circuits at a single set of
pressure terminals.
A. Factory test power factor correction equipment before shipment. Comply with NEMA CP 1.
Include the following:
PART 3 - EXECUTION
3.1 INSTALLATION
B. Comply with mounting and anchoring requirements specified in Division 26 Section Vibration
and Seismic Controls for Electrical Systems.
3.2 IDENTIFICATION
1. Operational Test: After electrical circuits have been energized, connect and observe
units to confirm proper operation.
B. Inspection: Perform external and internal inspections of capacitor equipment for damage and
for compliance with the Contract Documents and manufacturer's documentation. Check
electrical and mechanical bolted connections for required torquing.
C. Inspection of Seismic Controls: Check type, size, quantity, arrangement, and installation of
equipment mounting and anchorage devices against requirements indicated in manufacturer's
certification.
D. Testing: Perform the following and certify compliance with test parameters:
1. Test insulation resistance between capacitor terminals and case. Follow manufacturer's
written instructions or those below:
E. Correct deficiencies shown by inspections and tests on site where possible, and retest;
otherwise, remove and replace with new units and retest.
3.4 CLEANING
A. After completing equipment installation, inspect unit components. Remove paint splatters and
other spots, dirt, and debris. Repair damaged finish to match original finish.
END OF SECTION
DESIGN CRITERIA
END OF SECTION
June 2011 26 36 00 1
SECTION 26 36 00
TRANSFER SWITCHES
(Edited from DeCA June 2011 Design Criteria)
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
List below only products that the reader might expect to find in this
Section but are specified elsewhere.
A. Product Data: Include rated capacities, operating characteristics, furnished specialties, and
accessories.
B. Shop Drawings: Dimensioned plans, sections, and elevations showing minimum clearances,
conductor entry provisions, gutter space, installed features and devices, and material lists for
each switch specified.
1. Basis for Certification: Indicate whether withstand certification is based on actual test of
assembled components or on calculation.
a. The term "withstand" means "the unit will remain in place without separation of any
parts from the device when subjected to the seismic forces specified."
2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate
and describe mounting and anchorage provisions.
3. Detailed description of equipment anchorage devices on which the certification is based
and their installation requirements.
F. Operation and Maintenance Data: For each type of product to include in emergency, operation,
and maintenance manuals. In addition to items specified in Division 01 Section Closeout
Procedures include the following:
A. Manufacturer Qualifications: Maintain a service center capable of providing training, parts, and
emergency maintenance repairs within a response period of less than eight hours from time of
notification.
B. Source Limitations: Obtain automatic transfer switches and nonautomatic transfer switches
through one source from a single manufacturer.
C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, for emergency service under UL 1008, by a testing agency acceptable to authorities
having jurisdiction, and marked for intended use.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Indicated Current Ratings: Apply as defined in UL 1008 for continuous loading and total system
transfer, including tungsten filament lamp loads not exceeding 30 percent of switch ampere
rating, unless otherwise indicated.
B. Tested Fault-Current Closing and Withstand Ratings: Adequate for duty imposed by protective
devices at installation locations in Project under the fault conditions indicated, based on testing
according to UL 1008.
C. Solid-State Controls: Repetitive accuracy of all settings is plus or minus 2 percent or better over
an operating temperature range of minus 4 to plus 158 deg F.
G. Oversize Neutral: Ampacity and switch rating of neutral path through units indicated for
oversize neutral shall be double the nominal rating of circuit in which switch is installed.
H. Enclosures: General-purpose NEMA 250, Type 1, 3R, or 12, as appropriate to the location,
complying with NEMA ICS 6 and UL 508, unless otherwise indicated.
J. Factory Wiring: Train and bundle factory wiring and label, consistent with Shop Drawings,
either by color code or by numbered or lettered wire and cable tape markers at terminations.
1. Designated Terminals: Pressure type suitable for types and sizes of field wiring
indicated.
2. Power-Terminal Arrangement and Field-Wiring Space: Suitable for top, side, or bottom
entrance of feeder conductors as indicated.
3. Control Wiring: Equipped with lugs suitable for connection to terminal strips.
C. Manual Switch Operation: Under load, with door closed and with either or both sources
energized. Transfer time is same as for electrical operation. Control circuit automatically
disconnects from electrical operator during manual operation.
A. Undervoltage Sensing for Each Phase of Normal Source: Senses low phase-to-ground voltage
on each phase. Pickup voltage is adjustable from 85 to 100 percent of nominal, and dropout
B. Time delay for override of normal-source voltage sensing delays transfer and engine start
signals. Adjustable from zero to six seconds, and factory set for one second.
D. Time Delay for Retransfer to Normal Source: Adjustable from 0 to 30 minutes, and factory set
for 10 minutes. Provides automatic defeat of delay on loss of voltage or sustained undervoltage
of emergency source, provided normal supply has been restored.
1. Normal Power Supervision: Green light with nameplate engraved "Normal Source
Available."
2. Emergency Power Supervision: Red light with nameplate engraved "Emergency Source
Available."
H. Unassigned Auxiliary Contacts: Two normally open, single-pole, double-throw contacts for each
switch position, rated 10 A at 240-V ac.
I. Transfer Override Switch: Overrides automatic retransfer control so automatic transfer switch
will remain connected to emergency power source regardless of condition of normal source.
Pilot light indicates override status.
J. Engine Starting Contacts: One isolated and normally closed, and one isolated and normally
open; rated 10 A at 32-V dc minimum.
K. Engine Shutdown Contacts: Time delay adjustable from zero to five minutes, and factory set for
five minutes. Contacts shall initiate shutdown at remote engine-generator controls after
retransfer of load to normal source.
1. Exerciser Transfer Selector Switch: Permits selection of exercise with and without load
transfer.
2. Push-button programming control with digital display of settings.
A. Operation: Electrically actuated by push buttons designated "Normal Source" and "Alternate
Source." In addition, removable manual handle provides quick-make, quick-break manual-
switching action. Switch is capable of electrically or manually transferring load in either
direction with either or both sources energized. Control circuit disconnects from electrical
operator during manual operation.
1. Normal Power Supervision: Green light with nameplate engraved "Normal Source
Available."
2. Emergency Power Supervision: Red light with nameplate engraved "Alternate Source
Available."
C. Unassigned Auxiliary Contacts: One set of normally closed contacts for each switch position,
rated 10 A at 240-V ac.
2.7 FINISHES
A. Factory test and inspect components, assembled switches, and associated equipment. Ensure
proper operation. Check transfer time and voltage, frequency, and time-delay settings for
compliance with specified requirements. Perform dielectric strength test complying with
NEMA ICS 1.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Comply with mounting and anchoring requirements specified in Division 26 Section Vibration
and Seismic Controls for Electrical Systems.
1. Concrete Bases: 4 inches high, reinforced, with chamfered edges. Extend base no more
than 2 inches in all directions beyond the maximum dimensions of switch, unless
otherwise indicated. Cast anchor-bolt inserts into bases. Comply with Division 03
Section Cast-in-Place Concrete.
3.2 CONNECTIONS
A. Ground equipment according to Division 26 Section Grounding and Bonding for Electrical
Systems.
B. Connect wiring according to Division 26 Section Low-Voltage Electrical Power Conductors and
Cables.
B. Perform the following field tests and inspections and prepare test reports:
1. After installing equipment and after electrical circuitry has been energized, test for
compliance with requirements.
4. After energizing circuits, demonstrate interlocking sequence and operational function for
each switch at least three times.
5. Ground-Fault Tests: Coordinate with testing of ground-fault protective devices for power
delivery from both sources.
D. Report results of tests and inspections in writing. Record adjustable relay settings and
measured insulation and contact resistances and time delays. Attach a label or tag to each
tested component indicating satisfactory completion of tests.
END OF SECTION
DESIGN CRITERIA
END OF SECTION
June 2011 26 42 13 1
SECTION 26 42 13
PASSIVE CATHODIC PROTECTION FOR UNDERGROUND AND SUBMERGED
PIPING
(Edited from DeCA June 2011 Design Criteria)
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
Adjust list below to suit Project; delete all that are not applicable.
b. Valves or fittings of ferrous metal on buried nonmetallic pipelines for [natural gas]
[water] <insert other> service.
A. Qualified Individual: Design, construction supervision, and testing of the cathodic protection
and associated bonding, isolation, and coating of the structures shall be accomplished by an
individual qualified under one of the following:
B. Design appropriate and economical cathodic protection for each structure in accordance with
the NACE Recommended Practice for Control of Pipeline Corrosion. Include all bonding and
isolation, and appropriate test stations. Design for not less than 20 years anode life expectancy.
1. Investigate existing conditions on site that affect cathodic protection, and research utility
records of the Host Military Installation to determine the existence of other utilities and
cathodic protection systems in the area that may influence, or be influenced by, the new
protected structure(s).
2. Conduct any tests that may be required in the design of the cathodic protection,
furnishing all equipment, supplies, and labor for the tests. (Examples of tests that might
be required are soil resistivity, current requirements tests, structure continuity tests, stray
current tests.)
E. Test the protected structure for "hot spots," unprotected areas of structure, or interference from
stray currents.
F. Check for cathodic interference on other structures in the vicinity, if deemed necessary by the
Qualified Individual.
G. Make any adjustments or corrections that may be required to bring the protected structure to
acceptable protection, or to eliminate interferences, and retest.
H. Furnish full reports of all tests, prepared and signed by the Qualified Individual.
I. Submittals:
A. General: Provide galvanic anode cathodic protection for the structures indicated on the
Drawings to receive cathodic protection. Apply anodes to each separate continuous structure in
accordance with the table below.
C. Anodes: Anodes shall be standard H-1 alloy magnesium anodes prepackaged in standard
gypsum-bentonite-sodium sulfate formula prepared backfill bags for cathodic protection service,
of the (magnesium) weights indicated in the Table. Anodes shall have 10-foot insulated #12
AWG copper lead wires.
D. Wire Connections to Structure: Wire connections to the protected structure shall be made by an
exothermic welding process, such as Cadweld or Thermoweld. Use the tools, molds,
accessories, and weld charges recommended by the manufacturer for the specific wire and
structure type. Follow all instructions of the manufacturer precisely in making the welds.
E. Test Stations: Provide at least one flush-mounted cathodic protection test station for each
separate structure protected, other than isolated valves or fittings on nonmetallic pipelines. For
pipeline structures exceeding 200 feet length, provide two test stations. One or more test
stations should be installed at anode connection points, with the anode wire as well as two
structure contact wires brought into the test station terminals. Provide a separable link to
connect the anode lead wire to one of the structure contact wires. Provide additional test
stations where indicated on the Drawings.
F. Acceptance Tests: Perform tests listed below on each protected structure, in the presence of
the authorized Governments Designated Inspector and any other government technical
personnel responsible for cathodic protection. Provide all equipment, wiring and labor for the
tests. The test should be performed not less than two days after the anodes are connected to
the structure, to allow time for polarization to stabilize.
1. Using a high impedance voltmeter (50,000 ohms per volt or higher), measure the
structure-to-soil potential at the soil surface above the protected structure every 10 feet
along its length. Soil contact shall be made with a standard copper to copper sulfate
reference electrode designed for soil potential measurements, placed firmly upon slightly
moistened soil for good contact. Structure contact shall be made at a cathodic protection
test station; or, in the case of isolated valves with no test station, the contact may be
made directly to the exposed valve stem or body.
2. Protection is considered to be adequate if the structure-to-soil potential is negative 0.85
volt or greater. Protective potentials exceeding negative 2.0 volts may cause disbonding
of coatings, and should be reduced by introducing resistance into the anode connection.
3. Using a sensitive milliammeter, measure the current flow between the anode and the
protected structure. Higher current indicates more rapid consumption of the anode
material.
a. For Magnesium Anodes: For the desired rated life expectancy of 20 years, this
current should not exceed the current shown in the table below corresponding to
the anode weight.
4. If tests show the protection to be inadequate, or the anode current too high, remedial
measures may be required. It may be necessary to introduce resistance into the anode
lead connection; or the structure may be electrically shorted to another structure causing
a drain on the protective current. Consult with the Governments Designated Inspector for
guidance in correcting the problems. Retest after taking corrective measures.
5. Prepare a clear, typewritten report of final tests showing all structure-to-soil potentials
and anode currents. Record location and ohmic value of any resistances that were
added.
1.4 SUBMITTALS
A. Submit catalog data on all equipment and materials to be provided for the cathodic protection
installation, showing conformance to these specification requirements. For Approval.
B. Submit test reports of all tests conducted on the cathodic protection systems. For Approval and
permanent facility records.
D. Submit Record Drawings: Record locations and sizes of anodes, test stations, insulators and
the like on the record Drawings as required in Division 01 Section Closeout Procedures.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. In other Part 2 articles where titles below introduce lists, the following requirements apply to
product selection:
A. Available Manufacturers:
1. HARCO.
2. Mesa Products.
3. Brance-Krachy.
1. Cast magnesium anodes of H-1 alloy, Grade A, in accordance with ASTM Standard
B843, Alloy AZ63. Open Circuit Potential not less than 1.53 volts, and Current Efficiency
not less than 45 percent, when tested in accordance with ASTM-G97 procedures.
a. H-1 Magnesium Alloy, Grade A: Aluminum 5.3-6.7 percent; Zinc 2.5-3.5 percent;
Manganese 0.15-0.7 percent; Silicon 0.10 percent max.; Copper 0.02 percent
max.; Nickel 0.002 percent max.; Iron 0.003 percent max.; Other Impurities 0.30
percent max.; Magnesium - remainder to 100 percent.
2. Lead wire of #12 AWG copper wire, insulated with type TW insulation or HMWPE
insulation, 10 feet long, silver-soldered (45 percent silver) to the galvanized steel core of
the magnesium anode, and sealed against moisture.
3. Anode centered in a cloth bag containing a backfill mixture of 75 percent hydrated
gypsum, 20 percent bentonite, and 5 percent sodium sulfate.
4. Packaged for shipping and storage in a multiwall paper sack; palletized, and film-
wrapped.
A. Available Manufacturers:
B. Test stations shall be flush-to-grade design with sturdy plastic outer tube and well-sealing top
cover, similar to "Fink" test stations by Cott Manufacturing. Terminals and connecting links shall
be of nickel plated brass. Provide each test station with a minimum of 3 terminals and one link.
Station shall include a locator magnet.
C. Provide three each of any special tools required for operation and maintenance of the test
stations.
PART 3 - EXECUTION
A. Handling: Keep packaged magnesium anodes dry and protect from physical damage until
ready to install. Remove protective packaging carefully just before installation to avoid damage
to the cloth backfill sack or lead wire. Never handle the anode by its lead wire. When lowering
the anode into the earth, support its weight with a "sling" of rope or fabric until it is resting on the
bottom of the hole.
B. Location: Space anodes evenly over the extent of the protected structure; if one anode is
required, it should be near the midpoint of the structure.
C. Bell Hole: Provide a bell hole for the anode that is to one side of the structure to be protected,
deep enough that the entire anode will be lower than the lowest part of the structure. Minimum
D. Wiring: Anode lead wires and wires for contact to the structure shall be installed with sufficient
slack that tamping the backfill will not place strain upon the wires or the wire connections. Place
wires in the trench in such a way that they are not likely to be damaged if the structure has to be
dug up in the future.
E. Backfilling: When backfilling the anode, after about 12 inches of backfill cover has been placed,
activate the anode by pouring 5 gallons of clean water slowly over the anode site to moisten the
anode, the prepared backfill inside the cloth bag, and the earth around the anode.
A. Avoid placing test stations directly above anodes or directly above the protected structure.
Place test stations 18 to 24 inches off the centerline of the protected structure, and at least 5
feet horizontally from the anode. Place the top of the station flush with pavements, or 1/2 inch
above grade if unpaved. The earth directly underneath a test station should be native backfill,
so it can be used for earth contact for testing purposes in case the surrounding area is paved or
covered.
3.3 TESTING
1. Be sure your test lead connection to the structure makes good contact to metal. Use
abrasive paper or a file to clean tarnish or soil from any connection point. Do not use the
anode wire as a structure contact; use an independent structure contact wire at the test
station.
2. To insure good soil contact at the tip of the copper/copper sulfate reference electrode,
moisten the soil slightly (about 1/2 cup of clean water) at the point of contact. Place the
reference electrode on the soil as close to the vertical centerline of the structure as
possible.
3. Record the negative potential of the pipe to the soil, to 3 significant figures.
1. Positive current flow in the anode lead is from the structure to the anode.
2. Record current to 3 significant figures. Record a sample structure-to-soil potential reading
taken simultaneously with the current reading, to ensure that the insertion of the ammeter
has not altered the protective current level.
D. Test Reports:
1. Record all tests and corrective actions. Provide a test report, clearly typed, showing all
tests and numerical results, identifying the protected structures tested, persons involved
in the tests, equipment used, and the date the tests and corrective actions were
accomplished.
END OF SECTION
Verify that Section titles referenced in this Section are correct for
this Project's Specifications; Section titles may have changed.
1.1 SUMMARY
A. Section Includes:
1. Transient voltage surge suppressors for low-voltage power, control, and communication
equipment.
B. Related Sections:
List below only products and equipment that the reader might
expect to find in this Section but are specified elsewhere.
2. Division 26 Section Panelboards for factory-installed transient voltage surge suppressors.
3. Division 26 Section Switchboards for factory-installed transient voltage surge
suppressors.
1.2 SUBMITTALS
A. Product Data: For each type of product indicated. Include rated capacities; shipping, installed,
and operating weights; furnished specialties; and accessories.
1. UL 1283 certification.
2. UL 1449 listing and classification.
C. Field Test Reports: Written reports of tests specified in Part 3 of this Section. Include the
following:
A. Source Limitations: Obtain suppression devices and accessories through one source from a
single manufacturer providing field representation in the project area.
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
C. IEEE Compliance: Comply with IEEE C62.41, "IEEE Guide for Surge Voltages in Low Voltage
AC Power Circuits," and test devices according to IEEE C62.45, "IEEE Guide for Surge
Suppressor Testing."
D. NEMA Compliance: Comply with NEMA LS 1, "Low Voltage Surge Protective Devices."
A. Placing into Service: Do not energize or connect data terminals to their sources until the surge
protective devices are installed and connected.
B. Existing Utilities: Do not interrupt utilities serving facilities occupied by Government or others
unless permitted under the following conditions and then only after arranging to provide
temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than ten days in advance of proposed utility
interruptions.
2. Do not proceed with utility interruptions without Contracting Officer's written permission.
C. Service Conditions: Rate surge protective devices for continuous operation under the following
conditions, unless otherwise indicated:
1. Maximum Continuous Operating Voltage: Not less than 115 percent of nominal system
operating voltage.
2. Operating Temperature: 30 to 120 deg F.
3. Humidity: 0 to 85 percent, noncondensing.
4. Altitude: Less than 20,000 feet above sea level.
1.6 WARRANTY
A. General Warranty: Special warranties specified in this Article shall not deprive Government of
other rights Government may have under other provisions of the Contract Documents and shall
be in addition to, and run concurrent with, other warranties made by Contractor under
requirements of the Contract Documents.
C. Special Warranty for Plug-in Cord-Connected Surge Suppressors: Written warranty, executed
by manufacturer agreeing to repair or replace electronic equipment connected to circuits
protected by surge suppressors.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Surge Protective Device Description: Modular design with field-replaceable modules and the
following features and accessories:
B. Peak Single-Impulse Surge Current Rating: [320] [240] [160] kA per phase.
D. Protection modes and UL 1449 clamping voltage for grounded wye circuits with voltages of
480Y/277 and 208Y/120; 3-phase, 4-wire circuits, shall be as follows:
A. Surge Protective Device Description: Modular design with field-replaceable modules and the
following features and accessories:
B. Peak Single-Impulse Surge Current Rating: [160] [120] [80] kA per phase.
A. Description: Non-modular, plug-in suppressors with at least four 15-A, 120-V ac, NEMA WD 6,
Configuration 15-15R receptacles, suitable to plug into a NEMA WD 6, Configuration 15-15R
receptacle; with the following features and accessories:
A. Protectors for copper data, antenna, and telephone conductors entering the building from the
outside shall be as recommended by the manufacturer for the type of line being protected.
2.6 ENCLOSURES
A. NEMA 250, with type matching the enclosure of panel or device being protected.
PART 3 - EXECUTION
A. Install devices at service entrance on load side, with ground lead bonded to service entrance
ground.
1. Provide multipole, 15-A circuit breaker as a dedicated disconnect for the suppressor,
unless otherwise indicated.
3.2 CONNECTIONS
Retain one of three paragraphs below, or delete all three and retain
"Manufacturer's Field Service" Paragraph if field quality-control
testing is performed by manufacturer's service representative.
3.4 DEMONSTRATION
END OF SECTION
DESIGN CRITERIA
1. Reference Standards: Basic requirements for design are set forth in NFPA-101 Life Safety Code,
NFPA-70 National Electrical Code, National Electrical Safety Code, and in OSHA Regulations.
2. Related Sections: Sections 26 51 00, and Design Standard Plates 26 51 00-01, -02 and -03, apply.
3. Lighting Intensities: Maintained average lighting intensities shall comply with foot-candle levels
stipulated by the Minimum Commissary Illumination Standards (attached). Design to the FC shown,
within +10 percent / -5 percent. If any spaces are not covered by the Minimum Commissary
Illumination Standards, provide illumination in accordance with the Handbook of the IES (Illuminating
Engineering Society). Use point-to-point method of analysis in the sales area and for parking lot
lighting. In calculating the sales area illumination, take into consideration the effect of gondola
shelving. Evaluate lighting intensity on the vertical gondola facings as well as the horizontal plane;
vertical illumination on the gondola facing at 30" AFF shall be not less than 50 percent of the
specified horizontal illumination. Use the zonal cavity method of analysis in all other spaces.
A. Provide minimum illumination levels for each room and area as indicated.
B. Illumination levels, expressed in footcandles (FC), are based on a horizontal work plane 30" above
the floor surface, unless otherwise noted. Additional specific requirements are annotated in the
Remarks column. Notes referenced in the Remarks column refer to additional specific requirements
detailed in LIGHTING DESIGN REQUIREMENTS NOTES following the table.
4. The designer may recommend other than the type of lamps indicated, provided a cost study addressing
initial and twenty year life-cycle costs shows the selected lamps to be substantially more cost-effective.
Alternative light sources shall provide equal quality of illumination and color rendering.
5. Electrical power: 277 volts where practicable for interior lighting.
6. Lighting Power Monitoring: Install current transformers and transducers associated with the
Refrigeration Monitoring and Control System (RMCS) in lighting power wiring to monitor interior lighting
power consumption and demand. For remodel projects or where total lighting monitoring is impractical,
monitor major general lighting in the sales and staging areas as a minimum.
7. Fluorescent Lighting: Use Fluorescent lighting as the primary interior lighting system except where
the Minimum Commissary Illumination Standards indicate otherwise. Use fluorescent lighting with a
minimum Color Rendering Index (CRI) of 82, and low mercury content ("green" lamps).
A. 8' 0" lamps: minimum efficacy of 86 lumens per watt.
B. 4' 0" lamps: minimum efficacy of 82 lumens per watt.
C. Highly efficient T8 or T5
D. Lamps: use throughout all areas where fluorescent lamps are indicated.
E. Minimize the number of different types of lamps used throughout the commissary, thus reducing
maintenance requirements.
F. Preferred color temperature for sales area general lighting, offices and utility areas: 3500 Kelvin
(e.g., SP35 lamps)
G. Fluorescent lamps over red meat displays: 3000 Kelvin color temperature, e.g. SP30 lamps.
H. Design lighting in larger interior areas (Sales, Staging/Receiving) for specific lamp/ballast
combinations providing optimum lumens-per-watt efficacy in the range of 95 to 105, with a system
ballast factor range of 0.95 to 1.15. Call out the specific design system efficacy and ballast factor as
a requirement in the Fixture Schedule. Specific lamp and ballast products also may be cited in the
schedule as "basis of design" products.
8. Metal Halide Interior Lighting: Use is limited as noted elsewhere in this criteria section. Interior metal
halide light fixtures must comply with Engineering Technical Letter (ETL) 05-1, "Use of Acrylic Diffusers
June 2011 26 51 00 1
DeCA DESIGN CRITERIA HANDBOOK
26 51 00 INTERIOR LIGHTING
with Metal Halide Fixtures", dated 05 Feb 05. Fixtures should: a) use "O-rated" lamps suitable for open
luminaires; or b) have a tempered glass diffuser; or c) provide a tempered glass overlay between the
lamp and the acrylic diffuser. All fixtures must be U.L. listed.
9. Exposed Overhead Structure: In sales area designs featuring overhead space open to structure use
fluorescent as primary general illumination.
10. LED Fixtures: Use LED fixtures for specialty lighting of displays and highlighting wall graphics.
11. Incandescent and High Pressure Sodium (HPS) lighting: Do not use incandescent or high pressure
sodium (HPS) light fixtures for general interior lighting, except where specifically authorized in this
section or requested by DeCA.
12. Energy Saving Devices: Use energy saving devices in the design (e.g. providing RMCS based
controls to enable the store manager to reduce the lighting intensity in the sales area to 50 percent
during stocking and cleaning). Provide only state-of-the-art energy efficient lighting fixtures, electronic
ballasts, and energy saving lamps and controls. Where specifically approved by DeCA, daylight
harvesting methods may be considered, with economic justification. Ensure that local switching is
provided in all offices and areas; utilize occupancy sensors where appropriate. Illumination quality is not
to be reduced for energy / cost benefits.
A. RMCS Control: Refer to Design Standards 26 51 00-01, 26 51 00-02, and 26 51 00-03. The
RMCS presents a closing maintained contact for "on" control of lighting. The number of control
circuits required for the Sales Area is five two for general lighting subject to 50 percent
reduction for all Sales Areas and the Checkout Area; and one for all Accent and Dcor lighting.
B. Occupancy Sensors: Provide occupancy sensors for control of the lighting in all offices,
breakrooms, restrooms, training rooms, and other areas subject to intermittent use.
13. Safety Features: Include proper safety features for all lighting fixtures to prevent food contamination
and injury to personnel, e.g. shielded, shatter-proof light fixtures or tube guards beside or above areas
where unprotected, un-packaged, or uncovered foods are stored, prepared, or served, and where
utensils and equipment are cleaned and stored, so that broken glass cannot contaminate food. This
includes 1P01, 2P02 produce cases, 1D00 deli cases, 1B04 bakery cases, and clerk service fish cases
1F00. Provide appropriate emergency lights in public areas, processing rooms, restrooms and
mechanical rooms.
14. Emergency Lighting: Provide as necessary to permit safe egress from all offices and areas during power
outages, in accordance with NFPA-101 Life Safety Code, and in other areas as specified herein. All
life-safety required emergency lights shall have automatic battery backup or connected to generator
power. Other emergency lighting for occupant convenience and comfort may utilize generator power
alone. Provide battery-operated emergency light fixtures in Meat Cutting, Meat Wrap, stairwells and
electrical rooms also for safety and egress. Batteries shall be remotely located outside of refrigerated
areas. Where emergency lighting fixtures also function as normal illumination in a space, switch the
fixtures with the other lights in the space.
15. Night Lighting: Provide a very limited amount of unswitched 24-hour night lighting only in the sales
area, receiving-staging, and offices having exterior windows. The intent is to enhance security by
permitting observation from outside the store, and also to provide minimal entry illumination for
personnel opening the store. These fixtures may also be part of the emergency lighting where
appropriate.
16. Staging and Receiving Areas: Provide fluorescent lighting in Staging and Receiving where free-
standing pallet racks are included. Place light fixtures in the Staging and Receiving areas in such a
manner that there shall be a sufficient clear height 17' 0" minimum from the finished floor. Determine
the exact arrangement of light fixtures based on the pallet rack storage layout. Control receiving,
staging, and MHE charging area lights by toggle switches (no panel control) on wall outside receiving
manager's office. If control from several locations is contemplated, consider using contactor control with
a switched pilot circuit. Where daylighting is used, provide for RMCS control to dim or turn off lights
June 2011 26 51 00 2
DeCA DESIGN CRITERIA HANDBOOK
26 51 00 INTERIOR LIGHTING
when natural lighting is sufficient. Coordinate placement of light fixtures with overhead doors, unit
heaters, pallet racks and refrigeration piping.
17. Refrigerated Areas: Furnish areas refrigerated below 40 deg F with LED lighting units in moisture
resistant fixtures.
18. Accent Lighting: Provide overhead energy efficient accent lighting over island produce cases, island
dairy cases, coffin meat cases, and mass display areas. Provide accent intensity as required in the
Minimum Commissary Illumination Standards. Control by the accent lighting circuit on the RMCS
(timer with manual override). Refer to Note 4, attached, for details.
19. Exterior Lighting: Provide lighting powered from the commissary. Provide lighting in the employee
and customer parking lots, access roads, service yard and general security lighting around the
building perimeter. Fixtures shall be dark sky compliant and provide cutoff angle to prevent spill light
into adjacent areas.
A. General:
1). Control Diagram: See Design Standard Plate 26 56 00-02, "Exterior Lighting Controls
Details".
2). Photoelectric Control: Provided by RMCS.
3). Timer: Timing functions provided through RMCS.
20. Receiving Door Lights: retractable loading lights at all receiving doors equipped with dock levelers and
dock seals for direct unloading of trailers. Mount lights on opposite sides from door lift chain. Lights
shall be Model LL with LED lamps as manufactured by Overhead door Company or approved equal.
21. Illuminated Exit Signs and Emergency Lights: Provide illuminated exit signs (color red or green as
appropriate, LED type) and emergency lights (preferably battery type) for all emergency exits and
passageways as required by the NFPA Life Safety Code No. 101 and local Ordinance. Give attention
to the type and location of fixtures selected so that they shall be firmly anchored. Connect all
emergency lighting to the emergency generator. Provide battery packs for the emergency lighting in
the processing rooms, mechanical mezzanine, and all stairwells. Self-Luminous non-powered fixtures
are permitted when listed by NFPA, UL924, OSHA, NRC and applicable Codes and ordinances.
22. Supplementary Lighting: Use supplementary lighting to provide the illuminating levels required for
specific work areas. Do not direct heat producing accent spot lighting in sales areas at refrigerated
display cases. Provide receiving door lighting for illuminating delivery vehicle interiors.
23. Spare Lamps: Spare lamps are not required. At completion, provide a list of lamps required for each
fixture..
END OF SECTION
Attachments:
June 2011 26 51 00 3
DeCA DH 20-1 DeCA DESIGN CRITERIA HANDBOOK
265100 INTERIOR LIGHTING
June 2011 26 51 00 1
DeCA DH 20-1 DeCA DESIGN CRITERIA HANDBOOK
265100 INTERIOR LIGHTING
June 2011 26 51 00 2
DeCA DH 20-1 DeCA DESIGN CRITERIA HANDBOOK
265100 INTERIOR LIGHTING
June 2011 26 51 00 3
DeCA DH 20-1 DeCA DESIGN CRITERIA HANDBOOK
265100 INTERIOR LIGHTING
END OF TABLE
June 2011 26 51 00 4
DeCA DESIGN CRITERIA HANDBOOK
26 51 00 INTERIOR LIGHTING
2. Use fluorescent lighting for sales area illumination.. Except as specified by Note 20, 22, or 23, design
Sales area and check out area general lighting so that it is controlled in two circuits by the RMCS
controller, with RMCS manual switching on wall at customer service desk to over-ride the RMCS timer
function (Refer to Design Standard Plate 26 51 00-02). Provide approximately half the required FC
lighting level for night stocking on each lighting circuit. These two circuits are to be alternated nightly so
that both groups of lamps will have approximately the same life expectancy. Display case lights and
accent lights shall be controlled by the RMCS. Design sales area fluorescent lighting perpendicular to
runs of gondola display shelving. Overall design shall provide for uniformity of illumination at both high
and low-lighting levels. Both checkout and sales area shall have some lights that remain on at all times
for night lighting (Refer to 14).
3. Design lighting above display cases to specifically enhance the product appearance and provide identity
and personality to the department. Soft white fluorescent lighting (3000K) is recommended for red
meat displays.
4. Special accent highlighting of 100 FC is required over the island produce cases, island dairy cases,
plant display, and mass dis