I. Material Utama
1 Tiang Beton 7 M 100 DaN bh 2,020,950
2 Tiang Beton 7 M 100 DaN E bh 2,220,750
3 Tiang Beton 9 M 200 DaN bh 3,019,950
4 Tiang Beton 9 M 200 DaN E bh 3,287,250
5 Tiang Beton 11 M 200 DaN bh 4,356,450
6 Tiang Beton 11 M 350 DaN bh 5,231,250
7 Tiang Beton 12 M 200 DaN bh 5,263,650
8 Tiang Beton 12 M 350 DaN bh 5,714,550
9 Tiang Beton 13 M 350 DaN bh 7,114,500
10 Tiang Beton 13 M 350 DaN E bh 7,560,000
11 Pin Post Insulator 20 KV setara Twink , Veekers (Cilicone) bh 399,600
12 Strain Insulator 20 KV setara Twink, Veekers (Cilicone) bh 391,500
13 AAAC 70 mm mtr 18,090
14 AAAC-S 70 mm mtr 27,540
15 AAAC-S 150 mm mtr 45,500
16 Steel Wire 22 mm (Ground Wire) mtr 8,775
17 Twisted Cable 3 x 70 + 1 x 50 mm mtr 70,470
18 NYY 1 x 150 mm m 298,350
19 NYY 4 x 70 mm m 548,100
20 Lighting Arester 24 KV 10 KA lengkap (Polymer/Silicone) bh 1,336,500
21 Cut Out 100 A 24 KV + Fuse Link 100 A (Polymer/Silicone) set 1,485,000
22 Trafo Dist 25 KVA, 20 KV, 400V/231/3 Ph (D3) bh 59,400,000
23 Trafo Dist 50 KVA, 20 KV, 400V/231/3 Ph (D3) bh 76,950,000
24 Trafo Dist 100 KVA, 20 KV, 400V/231/3 Ph (D3) bh 101,250,000
III. Konstruksi
1 Singel Arm Band 8" & Nut M 16 + Washer set 74,200
2 Cross Arm UNP 100x50x4x2000 mm bh 399,300
3 Cros arm NP 10 - 600 mm.U/dudukan Pipa. bh 110,800
4 Cros arm NP 8 - 1000 mm.U/dudukan LV Panel. bh 231,000
5 Ball Clevis + Socket Eye bh 62,775
6 HV Band Strap / Cross Arm Clevis / Susp. Eye bh 47,500
7 Dead End Clamp (Strain Clamp) 70 - 150 mm set 56,250
NO NAMA MATERIAL SAT HARGA SATUAN
1 2 3 4
V. Sertifikasi
1 SLO SUTM (1,1 - 2,5 KMs) set 12,820,000
2 SLO SUTM (2,5 - 4,0 KMs) set 30,100,000
3 SLO SUTR (1,1 - 2,5 KMs) set 11,350,000
4 SLO SUTR (2,6 - 5 KMs) set 17,500,000
5 SLO GTT 50 KVA set 2,550,000
6 SLO GTT 100 KVA set 5,100,000
45,500.00 + 2,500.00
Jumlah = 48,000.00
9 1 M' Pasang Kabel Steel Wire 22 mm
Bahan :
1.00 m' Steel Wire 22 mm @ 8,775.00 8,775.00
Upah :
1.00 m' Ongkos Pasang @ 1,300.00 1,300.00
8,775.00 + 1,300.00
Jumlah = 10,075.00
10 1 M' Pasang Kabel Twisted 3 x 70 + 1 x 50 mm
Bahan :
1.00 m' Twisted 3 x 70 + 1 x 50 mm @ 70,470.00 70,470.00
Upah :
1.00 m' Ongkos Pasang @ 4,500.00 4,500.00
70,470.00 + 4,500.00
Jumlah = 74,970.00
11 1 Set Pasang Konstruksi TM 1
Bahan :
1.00 bh Cross Arm 2000 Type Tumpu @ 399,300.00 399,300.00
1.00 bh Arm Tie Type 750 - Pipe 3/4" @ 68,750.00 68,750.00
2.00 set Bolt & Nut M 16 x 400 (Double Arm) @ 54,000.00 108,000.00
1.00 set Bolt & Nut M 16 x 50/16x120+washer @ 34,375.00 34,375.00
3.00 bh Pin Post Insulator 20 KV @ 399,600.00 1,198,800.00
5.40 m' Aluminium Bending Wire 3,20 mm @ 5,200.00 28,080.00
3.30 bh Alluminium Tape 4,0 mm @ 6,900.00 22,770.00
1.00 set Perlengkapan @ 15,000.00 15,000.00
Upah :
1.00 set Ongkos Pasang @ 200,000.00 200,000.00
1,875,075.00 + 200,000.00
Jumlah = 2,075,075.00
12 1 Set Pasang Konstruksi TM 2
Bahan :
2.00 bh Cross Arm 2000 Type Tumpu @ 399,300.00 798,600.00
2.00 bh Arm Tie Type 750 - Pipe 3/4" @ 68,750.00 137,500.00
3.00 set Bolt & Nut M 16 x 400 (Double Arm) @ 54,000.00 162,000.00
6.00 bh Pin Post Insulator 20 KV @ 399,600.00 2,397,600.00
10.80 m' Aluminium Bending Wire 3,20 mm @ 5,200.00 56,160.00
6.60 m' Alluminium Tape 4,0 mm @ 6,900.00 45,540.00
1.00 set Perlengkapan @ 15,000.00 15,000.00
Upah :
1.00 set Ongkos Pasang @ 250,000.00 250,000.00
3,612,400.00 + 250,000.00
Jumlah = 3,862,400.00
13 1 Set Pasang Konstruksi TM 4
Bahan :
2.00 bh Cross Arm 2000 Type Tarik @ 399,300.00 798,600.00
2.00 bh Arm Tie Type 750 - Pipe 3/4" @ 68,750.00 137,500.00
4.00 set Bolt & Nut M 16 x 400 (Double Arm) @ 54,000.00 216,000.00
3.00 set Bolt & Nut M 16 x 140 mm + Washer @ 40,500.00 121,500.00
3.00 bh Strain Insulator 20 KV @ 391,500.00 1,174,500.00
3.00 bh Ball Clevis + Socket Eye @ 62,775.00 188,325.00
3.00 bh HV Band Strap / Cross Arm Clevis @ 47,500.00 142,500.00
3.00 bh Dead End Clamp (Strain Clamp) @ 56,250.00 168,750.00
2.00 bh U Strap @ 30,000.00 60,000.00
1.00 set Perlengkapan @ 15,000.00 15,000.00
Upah :
1.00 set Ongkos Pasang @ 250,000.00 250,000.00
3,022,675.00 + 250,000.00
Jumlah = 3,272,675.00
14 1 Set Pasang Konstruksi TM 4X
Bahan :
3.00 bh Dead End Clamp (Strain Clamp) @ 56,250.00 168,750.00
3.00 bh HV Band Strap / Cross Arm Clevis @ 47,500.00 142,500.00
3.00 bh Ball Clevis + Socket Eye @ 62,775.00 188,325.00
4.00 set Bolt & Nut M 16 x 400 (Double Arm) @ 54,000.00 216,000.00
3.00 bh Line Tap Connector 70 - 70 mm @ 23,125.00 69,375.00
1.80 m' Aluminium Bending Wire 3,20 mm @ 5,200.00 9,360.00
1.10 m' Alluminium Tape 4,0 mm @ 6,900.00 7,590.00
3.00 bh Strain Insulator 20 KV @ 391,500.00 1,174,500.00
1.00 bh Pin Post Insulator 20 KV @ 399,600.00 399,600.00
1.00 set Perlengkapan @ 15,000.00 15,000.00
Upah :
1.00 set Ongkos Pasang @ 250,000.00 250,000.00
2,391,000.00 + 250,000.00
Jumlah = 2,641,000.00
4.00 set Bolt & Nut M 16 x 400 (Double Arm) @ 54,000.00 216,000.00
6.00 set Bolt & Nut M 16 x 140 mm + Washer @ 40,500.00 243,000.00
1.00 set Double Arm Band 6" Bolt&Nut+Washer @ 81,000.00 81,000.00
3.60 m' Aluminium Bending Wire 3,20 mm @ 5,200.00 18,720.00
2.20 m' Alluminium Tape 4,0 mm @ 6,900.00 15,180.00
2.00 bh Pin Post Insulator 20 KV @ 399,600.00 799,200.00
6.00 bh Strain Insulator 20 KV @ 391,500.00 2,349,000.00
6.00 bh Ball Clevis + Socket Eye @ 62,775.00 376,650.00
6.00 bh HV Band Strap / Cross Arm Clevis @ 47,500.00 285,000.00
6.00 bh Dead End Clamp (Strain Clamp) @ 56,250.00 337,500.00
3.00 bh Line Tap Connector 70 - 70 mm @ 23,125.00 69,375.00
1.00 bh U Strap @ 30,000.00 30,000.00
1.00 set Perlengkapan @ 25,000.00 25,000.00
Upah :
1.00 set Ongkos Pasang @ 310,000.00 310,000.00
6,782,625.00 + 310,000.00
Jumlah = 7,092,625.00
19 1 Set Pasang Konstruksi TR 1
Bahan :
1.00 bh Suspension Clamp Bracket @ 29,700.00 29,700.00
1.00 bh Suspension Clamp @ 28,215.00 28,215.00
2.00 set Stailessteel Srtip 0.75 mtr @ 23,750.00 47,500.00
2.00 bh Stopping Buckle @ 5,500.00 11,000.00
3.00 bh Plastic Strip @ 3,105.00 9,315.00
2.00 bh Plastic Strap @ 3,105.00 6,210.00
Upah :
1.00 Ongkos Pasang @ 93,750.00 93,750.00
131,940.00 + 93,750.00
Jumlah = 225,690.00
20 1 Set Pasang Konstruksi TR 2
Bahan :
1.00 bh Tension Brackett @ 28,957.50 28,957.50
2.00 bh Strain Clamp @ 40,095.00 80,190.00
2.00 set Stailessteel Srtip 0.75 mtr @ 23,750.00 47,500.00
2.00 bh Stopping Buckle @ 5,500.00 11,000.00
3.00 bh Plastic Strip @ 3,105.00 9,315.00
2.00 bh Plastic Strap @ 3,105.00 6,210.00
Upah :
1.00 set Ongkos Pasang @ 125,000.00 125,000.00
183,172.50 + 125,000.00
Jumlah = 308,172.50
21 1 Set Pasang Konstruksi TR 3
Bahan :
1.00 bh Tension Brackett @ 28,957.50 28,957.50
1.00 bh Strain Clamp @ 40,095.00 40,095.00
4.00 set Stailessteel Srtip 0.75 mtr @ 23,750.00 95,000.00
4.00 bh Stopping Buckle @ 5,500.00 22,000.00
2.00 bh Plastic Strip @ 3,105.00 6,210.00
2.00 bh Link @ 4,125.00 8,250.00
2.00 bh Yokes @ 1,300.00 2,600.00
1.00 bh PCV 3/4" - 50 cm @ 30,000.00 30,000.00
4.00 bh Plastic Strap @ 3,105.00 12,420.00
Upah :
1.00 set Ongkos Pasang @ 125,000.00 125,000.00
245,532.50 + 125,000.00
Jumlah = 370,532.50
22 1 Set Pasang Konstruksi TR 4A
Bahan :
2.00 set Susp & Small Angle Assembly 35-70 mm @ 81,250.00 162,500.00
4.00 set Stailessteel Srtip 0.75 mtr @ 23,750.00 95,000.00
4.00 bh Stopping Buckle @ 5,500.00 22,000.00
6.00 bh Plastic Strip @ 3,105.00 18,630.00
6.00 bh Line Tap Connector 70 - 70 mm @ 23,125.00 138,750.00
2.00 bh Bimetal Connector 25 - 50 mm @ 71,280.00 142,560.00
1.00 set Perlengkapan @ 10,000.00 10,000.00
Upah :
1.00 set Ongkos Pasang @ 156,250.00 156,250.00
589,440.00 + 156,250.00
Jumlah = 745,690.00
23 1 Set Pasang Konstruksi TR 6
Bahan :
1.00 bh Suspension Clamp Bracket @ 29,700.00 29,700.00
23
HARGA JUMLAH
NO NAMA MATERIAL VOLUME SAT TOTAL
SATUAN HARGA
1 2 4 3 4 5 6
SUTM 1,362 Ms
I. MATERIAL UTAMA
1 Tiang Beton 13 M 350 DaN 1 bh 9,889,500 9,889,500
2 Tiang Beton 11 M 200 DaN (untuk SP dan HGW) 2 bh 6,242,450 12,484,900
3 Tiang Beton 9 M 200 DaN (untuk SP di TM8XC) 1 bh 4,577,250 4,577,250
4 AAAC-S 150 mm 4,168 mtr 48,000 200,050,560
5 Steel Wire 22 mm (Ground Wire) 1,389 mtr 10,075 13,996,593
240,998,803
II. MATERIAL NON UTAMA
1 Ground Wire End Clamp 30 bh 45,625 1,368,750
1,368,750
III. KONSTRUKSI
1 Pemasangan Konstruksi TM1 14 set 2,075,075 29,051,050
2 Pemasangan Konstruksi TM2 1 set 3,862,400 3,862,400
3 Pemasangan Konstruksi TM8XC 1 set 8,992,400 8,992,400
4 Pemasangan Konstruksi TM4 1 set 3,272,675 3,272,675
5 Pemasangan Konstruksi TM10 12 set 7,092,625 85,111,500
6 Pemasangan Arde (Dalam) 5 set 671,280 3,356,400
7 Pemasangan Treckschoore ( GW ) 24 set 1,371,300 32,911,200
8 Pemasangan Druckschoore ( SP ) 2 set 905,825 1,811,650
9 Pemasangan Horizontal Guy Wire (HGW) 1 set 1,750,675 1,750,675
170,119,950
IV. JASA
1 Langsiran 1 ls 4,500,000 4,500,000
4,500,000
V. SERTIFIKASI
1 SLO 1 set 12,820,000 12,820,000
12,820,000
SUTR 1,327 Ms
I. MATERIAL UTAMA
1 Tiang Beton 9 M 200 DaN 2 bh 4,309,950 8,619,900
2 Tiang Beton 7 M 200 DaN 1 bh 2,973,950 2,973,950
3 Twisted Cable 3 x 70 + 1 x 50 mm 1,354 mtr 74,970 101,474,894
113,068,744
II. KONSTRUKSI
1 Pemasangan Konstruksi TR 1 12 set 225,690 2,708,280
2 Pemasangan Konstruksi TR 2 15 set 308,173 4,622,588
3 Pemasangan Konstruksi TR 3 2 set 370,533 741,065
4 Pemasangan Arde (Luar) 2 set 1,122,630 2,245,260
5 Memasang Treckschoore (GW) 5 set 848,275 4,241,375
6 Pemasangan Druckschoore ( SP ) 1 set 905,825 905,825
15,464,393
III. JASA
1 Langsiran 1 ls 2,105,000 2,105,000
2,105,000
IV. SERTIFIKASI
1 SLO 1 set 11,350,000 11,350,000
11,350,000
J UM LAH 743,978,697
REKAPITULASI
RENCANA ANGGARAN BIAYA
ENGINEER ESTIMATE (EE)
JUMLAH
NO JENIS PEKERJAAN (Rp)
1 2 3
A. SUTM
I. MATERIAL UTAMA 240,998,803
II. MATERIAL NON UTAMA 1,368,750
III. KONSTRUKSI 170,119,950
IV. JASA 4,500,000
V. SLO 12,820,000
SUB PEKERJAAN A 429,807,503
B. SUTR
I. MATERIAL UTAMA 113,068,744
II. KONSTRUKSI 15,464,393
III. JASA 2,105,000
IV. SLO 11,350,000
SUB PEKERJAAN B 141,988,136
C. GTT
I. MATERIAL UTAMA 128,682,000
II. MATERIAL NON UTAMA 13,407,375
III. KONSTRUKSI 21,756,695
IV. UPAH / JASA 3,236,987
V. SLO 5,100,000
SUB PEKERJAAN C 172,183,057
J U M LAH 743,978,697
PPN 10% 74,397,870
TOTAL 818,376,566
DIBULATKAN 818,376,000
Terbilang : DELAPAN RATUS DELAPAN BELAS JUTA TIGA RATUS TUJUH PULUH ENAM RIBU RUPIAH