Você está na página 1de 11

Stope Blast Vibration Analysis at

Dugald River Underground Mine


R Hassell1, E Villaescusa2, R de Vries3 and J Player4

ABSTRACT
Concerns regarding the uncertainty of stope dilution at MMG Dugald River Underground Mine
led to a trial stoping program to acquire full-scale comprehensive geotechnical information and to
test the validity of the geotechnical and mining parameters. Given that stope production drilling
and blasting is a key parameter that influences dilution a detailed stope blast vibration project was
implemented. The stoping trial consisted of 19 stopes, a combination of both sublevel open stoping
and longitudinal and transverse stopes, of which five were monitored for blast vibrations.
The blast vibration project utilised 20 triaxial geophones and five triaxial accelerometers installed
in the hanging wall of five monitored stopes. For each stope fired, full blast waveforms were
recorded along with detailed information of the blast design. Analysis of the blast vibrations used
the Holmberg-Persson approach, with potential damage determined by the relative (Holmberg-
Persson) K values.
The project identified the benefit of parallel, breakthrough slot holes in reducing blast vibration
damage. The results show that radial rings toeing or stabbing into the stope wall lead to higher
vibrational energy yield which contributed to increased overbreak. Hanging wall overbreak,
by comparison, with parallel, breakthrough blastholes with 1 m standoff, combined with lower
density explosive charging (0.8 EP) and increased delays limited blast vibration damage. A number
of ring burdens from 1.4 m to 2.5 m were monitored with no difference in terms of energy yield
being identified. Changes to the stope drill and blast design are suggested to better control the
large blast vibrations and recommendations from this project have been implemented into future
mine design and planning.

INTRODUCTION Geological conditions


The Dugald River Zn-Pb-Ag deposit is located 85 km north- The Dugald River deposit occurs within the eastern fold belt
west of Cloncurry, Queensland. The deposit was discovered of the Mt Isa Inlier and the Dugald Lode is hosted within a
pre-1880, with first systematic exploration not occurring until steeply dipping black slate sequence of low metamorphic
the 1950s. It is regarded as one of the largest and highest- grade. The deposit is a steep dipping tabular orebody,
grade known undeveloped deposits of zinc, lead and silver in
extending approximately 2 km along strike and to a depth
the world with a Total Mineral Resource (measured, indicated
of approximately 1 km. The orebody strikes approximately
and inferred) of 55 Mt at 13.4 percent zinc, 2.1 percent lead
and 36 g/t silver (MMG Limited, n/d). The deposit was northsouth (MGN), dips between 45 to 85 to the west, and
acquired by MMG Ltd in 2009, with mine development starting varies in true thickness from 2 to 35 m. The area of greatest ore
in February 2012. Exposure of the geological conditions thickness occurs in the central part of the orebody between
during development together with underground diamond the depths of 300 and 600 m, which coincides with the area
drilling highlighted a more complex and challenging mining of flattest dip.
environment than predicted in the feasibility study. A mining The hanging wall slates (HWSL) occur in the immediate
method review was completed in mid-2013, which concluded hanging wall of the Dugald Lode and typically vary in
that there was an unacceptable level of uncertainly in regards
thickness between 50 and 100 m. In the area where the Dugald
to stope dilution. It was recommended that a trial stoping
program be completed to address the main uncertainties Lode dip flattens to less than 50, the thickness can be as little
regarding this. Trial stoping commenced in early 2014. Given as 10 m. Muscovite schist, mafic porphyry and calc-silicates
stope production drilling and blasting are key parameters units are to the west of the hanging wall of the HWSL. The
that influence stope dilution (Villaescusa, 2014a), a detailed HWSL typically consist of massive, fine-grained dark grey
stope blast vibration project was implemented as part of the slate, spotted in places; to laminated, fine-grained dark grey
overall trial stoping study. to light grey slates, often with carbonate veining.

1. MAusIMM, Geotechnical Engineer, Dugald River Mine, MMG, PO Box 69, Cloncurry Qld 4841. Email: rhett.hassell@mmg.com
2. Professor and Industry Chair Mining Rock Mechanics, Western Australian School of Mines, Curtin University of Technology, Locked Bag 30, Kalgoorlie WA 6433. Email: e.villaescusa@curtin.edu.au
3. MAusIMM, Senior Geotechnical Engineer, Dugald River Mine, MMG, PO Box 69, Cloncurry Qld 4841. Email: rhett.devries@mmg.com
4. MAusIMM(CP), Principal Geotechnical Engineer, MineGeo Tech Pty Ltd, PO Box 8054, Kalgoorlie WA 6433. Email: johnplayer@minegeotech.com.au

11TH INTERNATIONAL SYMPOSIUM ON ROCK FRAGMENTATION BY BLASTING / SYDNEY, NSW, 2426 AUGUST 2015 221
R HASSELL et al

The footwall slates and limestones are to the footwall of the TRIAL STOPING AND MINING METHODOLOGY
Dugald Lode. A narrow zone of footwall slates (FWSL) grade
The objective of the trial stoping was to acquire full-scale
to limestone (LMST) over a distance of up to 50 m. In some
comprehensive geotechnical information and learning
areas the footwall slates are absent and the limestone forms
through a cash flow neutral preproduction program, to test the
the footwall contact with the Dugald Lode. The footwall slates validity of current geotechnical and mining parameters. The
are almost identical in geological and geotechnical parameters selection of the trial stoping area, termed Zone 6, was based on
to the hanging wall slates. the drilling information available at the time. As such, it was
The orebody is hosted by slate and is dominated by sphalerite seen to be representative of the likely hanging wall rock mass
and pyrrhotite/pyrite with minor galena, arsenopyrite and conditions expected across the orebody in late 2013.
chalcopyrite. It ranges from massive sulfide breccias with Mining of the trial stopes was by sublevel open stoping
large angular clasts of slate to stringer veins hosted in slate. (SLOS) with cemented rock fill (CRF). Sublevel heights
The area selected for trial stoping at Dugald River is were 25m and stope strike lengths varied from 15 to 30m.
located at shallow depth (<250 m below the ground surface). A total of 19 stopes were taken during the trial. A long
The rock mass consists of a steeply west dipping, bedded section of the trial area is shown in Figure 2, with the five
rock intersected by large-scale, potentially weak, geological blast monitored stopes outlined. Due to the variability in
discontinuities. Some of these features are subparallel to the the lode width both longitudinal and transverse stopes were
orebody and sometimes located within the orebody or the designed with a value of 12 m being the critical dimension
immediate hanging wall of the designed stopes. A cross- between the transitions. In addition to the blast vibration
section showing the fault locations is shown in Figure 1. The project a significant geotechnical instrumentation program
structures show variability along strike and down dip, even was completed concurrently.
within a single stope geometry (ie 20 m along strike). The rock
mass outside the geological structures can be rated as fair to
good, as indicated by the low frequency of discontinuities
per metre and the high strength of the intact rock. Average
uniaxial compressive strength (UCS) of the massive/breccia
orebody is approximately 200MPa. The strength of the host
rock slates is about 150 MPa with both rock masses having a
high modulus.

FIG 2 Longitudinal section showing trial stopes sequence


with white outlined stopes being blast monitored.

Stope production drilling


Stope production drilling was completed using a Sandvic
DL42115C. A blasthole diameter of 89 mm was considered
suitable for the range of stope heights (floor to floor distances
of 25 m) being designed at Dugald River. This allows for
holes exceeding 30 m (if required) to be drilled at a nominal
2.52.8m burden (Villaescusa, 2014a). A range of ring burdens
from 1.4 m to 2.5 m were trialled. Spacing to burden ratios of
1.41.8 were maintained where possible.
Breakthrough holes were surveyed at the collar and toe
location to determine drill hole deviation. A collaring error of
less than 200 mm from the design location and a toe deviation
FIG 1 Cross-section through the trial stopes showing major fault orientations. of less than two percent of the borehole length was targeted.

222 11TH INTERNATIONAL SYMPOSIUM ON ROCK FRAGMENTATION BY BLASTING / SYDNEY, NSW, 2426 AUGUST 2015
STOPE BLAST VIBRATION ANALYSIS AT DUGALD RIVER UNDERGROUND MINE

For the five monitored stopes the average collaring error was
228mm and the average toe deviation was 2.17 percent. The A
level of drill hole accuracy was less than target and initiated an
improvement in operational factors such as survey markups,
rig positioning, calibration of the inclinometer and drilling
speed.
Drilling was undertaken from ore drive development
located in the hanging wall of the orebody with drive width
narrower than the orebody. Drilling was designed using
radial holes toeing into the stope footwall (FW) boundary but
parallel to the designed hanging wall (HW). For transverse
stopes, the slot was drilled in the cross-cut drive but not
parallel to the dip of the orebody. Typical drill plan sections
are shown in Figure3. Parallel HW holes were considered
beneficial for reducing blast damage to the stope hanging
walls and limiting dilution. A disadvantage of radial drilling
is that drilling and blasting becomes more difficult as a
uniform explosive distribution may not be achieved.

FIG 4 Plan views of designs for (A) a longhole


winze and (B) a raise bore-assisted winze.

Sequence
FIG 3 Typical longitudinal (left) and transverse drill plans (right). Sublevel open stoping (SLOS) requires sequential blasting of
three areas: winzes, slots and rings. Winzes (3.0 m 3.0m)
create the initial void into which the slot (3.0 m width of
Two types of winze designs were trialled in the blast stope) is then fired. The remainder of the stope, termed ring
monitoring stopes, both of 3.0 m 3.0 m size: a conventional firings, is then fired into the slot. A combination of these
longhole winze (LHW) design incorporating four reamers areas can be fired in one blast, which provides productivity
(203mm diameter) and 13 blastholes and a raise bored efficiencies; however, this also increases the risk of misfires
(1000mm diameter) assisted winze with 12 blastholes and frozen ground. With the use of electronic detonators, the
(Figure4). risk can be greatly reduced. The limiting factor to the size of
many of the blasts is the available void. A minimum void
Explosives ratio of 30 percent was used. Stope 2 was sequenced with
Ammonium nitrate emulsion was used as the bulk explosive the slot fully extracted before charging and firing the rings.
and was loaded into blastholes using a Hypercharge Drive This created a working-at-heights exposure risk, which was
unit. The unit combines the non-explosive emulsion with eliminated in subsequent stope firing sequences by firing the
sensitiser to deliver the water resistant explosive to the winze and slot to a cap. With the use of raise-bore-assisted
blasthole (Orica, 2011). A nominal emulsion density of winzes the initial winze firing was included in the undercut
1.09g/cm3 was used for all holes other than hanging wall holes firing reducing the number of firings from three to two.
where a density of 0.87g/cm3 was used. The lower density
explosive in the hanging wall was used to aid in limiting Timing
blast damage. i-kon electronic detonators (Orica, 2014) were The fundamental objective of the blast timing is to provide each
utilised for all mass blasts due to their greater timing accuracy, charge column with as many free faces as possible to break
increased delay interval and reduced probability of cut-offs. into. The cut-off slot is the most important geometry in sublevel
Electronic detonators can be logged in delay increments of stoping as it provides a free face and void for the remainder of a
1ms from 0 to 15 000 ms. Non-electric detonators utilising stope to be blasted into. Slots are critical areas where significant
the shock tube initiation system were used only for winze rock mass damage can occur due to the high concentration of
firings. These detonators have considerably larger scatter in explosive energy utilised to ensure an initial free face or void.
their detonation time. Typically, 15002000 ms were used to fire the winze, followed

11TH INTERNATIONAL SYMPOSIUM ON ROCK FRAGMENTATION BY BLASTING / SYDNEY, NSW, 2426 AUGUST 2015 223
R HASSELL et al

immediately by the slot holes, which were fired 100 ms apart.


Between the slot and rings a delay of up to 1500 ms was used A
to ensure the slot material had moved from the void. The rings
were fired with an inter-ring timing of 23 ms/m of spacing and
between rings greater than 40 ms/m of burden. An additional
delay of 40 ms was used for the hanging wall holes to ensure as
many free faces as possible.

STOPE BLAST VIBRATION MONITORING


In general, the objectives of a blast vibration monitoring
program can focus on one of two areas, namely: a fundamental
timing analysis identifying the location and cause of any
misfired blastholes and also a detailed vibration analysis
assessing blast damage, which may ultimately aid stope
stability analysis. The approach includes several stages as
follows (Villaescusa, 2014b):
1. design and installation of sensors (geophones and
accelerometers) at locations appropriate for monitoring
the different blasting sequences within a stope and
meeting the program objectives
2. monitor the level of vibration from the various stages of a
stope extraction (rise, slot and production rings)
3. analysis of the data to determine a relationship between
vibration level, distance and explosive quantity for each
of the blasts B
4. identify a link between vibration level and overbreak or
damage around a stope perimeter
5. modelling of the blast patterns to identify expected zones
of poor fragmentation within the blast or damage around
the stope boundaries.
The key objective for the blast vibration monitoring was to
assess the extent of blast vibration damage and to provide
recommendations on drill hole orientation, ring burdens,
stand-off distances, sequencing and timing to reduce blast
damage.

Blast vibration monitoring system design


The monitoring system used at Dugald River comprised
an Instantel Minimate Plus unit and an interface box. Each
Instantel device has eight channels and allows two triaxial
sensor arrays to be used for, either two geophones, two
accelerometers or a combination of accelerometers and
geophones. The triaxial sensor has one element oriented
directly towards the stope (referred to as the radial), one
sensor orientated parallel to a stope hanging wall (referred to
as the transverse) and a third sensor oriented vertically. The
sensor arrays were constructed specifically for the available
hole diameter (NQ2 diamond) and orientation. FIG 5 Typical stope hanging wall blast monitoring
The research project utilised 24 triaxial geophones and six layout in (A) section and (B) plan views.
triaxial accelerometers installed over five trial stopes. Typically,
each stope had three vibration monitoring holes drilled from Accelerometers were positioned closest to the stope
a geotechnical monitoring hanging wall drive. The centre boundary because of their capability for recording the high
monitoring hole for each stope has an accelerometer 24 m frequencies that occur in close proximity to blasthole charges.
from the hanging wall blasthole, a geophone approximately The accelerometers used were the PCB 356A01, with ag range
3m further away and a second geophone a further 3 m. The with a nominal 5 mV/g sensitivity. Unlike the geophone
additional two vibration monitoring holes for each stope have elements, accelerometers require an excitation voltage, which
a single geophone in each hole 5 to 7 m from the blasthole.
is provided to the unit via the interface box within each
The coordinates for each sensor location are based upon the
of the units. Accounting for the maximum voltage input
distance along the monitoring hole. A typical monitoring set-
up used at Dugald River is shown in Figure 5, where different permissible with the Instantel units, the sensitivity is adjusted
monitoring holes being a geophone hole, an observation hole in the interface boxes to 0. 00182 V/g. The geophones used
and an extensometer hole are shown. Data can be collected were OYO MicroSeis 101 LT with a frequency response of
from closed walls (excavation not exposed), from exposed 142000 Hz and a range of 02000 mm/s. The 101 LT is a
walls, adjacent to the stope void or from a filled wall following versatile geophone with a suitable frequency and amplitude
stope extraction. range for blast monitoring (Villaescusa, 2014b).

224 11TH INTERNATIONAL SYMPOSIUM ON ROCK FRAGMENTATION BY BLASTING / SYDNEY, NSW, 2426 AUGUST 2015
STOPE BLAST VIBRATION ANALYSIS AT DUGALD RIVER UNDERGROUND MINE

Installation is 0.01 per cent of the delay time, which is considerably


less than the delays between charges. However, during
Correct installation of the geophones/accelerometers was
the analysis it was quickly noted that there was a standard
critical to the success of the monitoring program. The
drift with the Instantel units of approximately 5 ms, which
geophones and accelerometers were connected to slotted
needed to be accounted for. For winze firings, the long delay
PVC pipe and installed down 75.7 mm diameter diamond
times used (>200ms) meant that scatter with the non-electric
drill holes. The pipes were marked and connected to ensure
detonators did not affect the peak vibration selection. This
the instruments were installed in the correct orientation.
methodology allowed accurate identification of the peak
Following final positioning the holes were grouted with
velocity at the geophone for each charge, irrespective of the
a 0.35 ratio water cement mixture and allowed to cure a
orientation of the blasthole relative to the geophone location.
minimum of seven days before the first firing.
The peak velocity for each hole was plotted at the blasthole
toe location (Figure 7) which allowed the identification of the
Data collection holes which were responsible for the high vibration.
Prior to each blast four Instantel Minimate Plus units were
each connected to two geophones/accelerometers. All
instruments could not be connected for each blast so only
BLAST VIBRATION ANALYSIS
those instruments deemed the most relevant were used. To In open stoping, equations to estimate the level of vibration
ensure that the start of each blast was recorded a separate very close to a blasthole (where fracturing is occurring) must
break wire was run from each unit to the location of the be modified to account for the long, cylindrical shape of the
electric detonator where it was joined to the detonator cord. charges with respect to the monitoring locations. The typical
This ensured that the units started recording when the electric equations used for surface blasting, such as the USBM inverse
detonator was initiated, which subsequently initiated the distance law, can only be applied when the distance between
downhole detonators. For i-kon blasts, which do not use an the blasthole and the monitoring point exceeds three times
electric detonator, an electronic detonator timed at zero was the length of the charge length (Villaescusa, 2014b). Empirical
substituted to specifically perform the wire break. evidence has shown that near field peak particle velocity (PPV)
levels from blasting can be linked to rock mass disturbance and
A total of 12 out of the 14 blasts were successfully monitored.
damage. One of the most widely used engineering methods
For each blast, the detailed charging and timing information
to model the attenuation of blast waves in a rock mass is the
for each hole was recorded, including the ring number, the
Holmberg-Persson approach (Holmberg and Persson, 1980).
hole number, the explosive column length, the blasthole
The basic assumptions of this approach are:
diameter, the delay time, the explosive density and the design
coordinates (x,y,z) of collar and toe locations of the charge 1. a radiating blast wave obeys charge weight scaling laws
column. 2. the PPV due to each small element of charge within the
For each instrument, full waveforms were recorded and blasthole is numerically additive
peak levels corresponding to each of the given delays as per 3. the velocity of detonation (VOD) of the explosive charge
the nominal initiation sequence, were determined from the is accounted for in the estimated model attenuation
waveforms. This was achieved by calculating the vector sum constants
from the geophones triaxial measurements and assigning the 4. the effect of free face boundaries is neglected, that is, the
peak vector sum to the relevant delay. Figure 6 shows the analysis corresponds to fully confined blasting conditions.
vector sums from four sensors (VSG16, versus G17, versus Despite the above limitations, several studies have
G12 and versus G18) during the mass blast of Stope 9. Delay demonstrated that PPV as an engineering index can be
times as per the charge plan are also shown (blue diamonds). successfully applied to infer the extent of potential damage
Matching the delay to peak velocity is possible due to the and disturbed zones. From a practical point of view, this type
high accuracy of the electronic detonators; detonator error of analysis allows the engineer to evaluate and better define

FIG 6 Peak vector sum for four triaxial sensors with respect to an individual stope blasting sequence.

11TH INTERNATIONAL SYMPOSIUM ON ROCK FRAGMENTATION BY BLASTING / SYDNEY, NSW, 2426 AUGUST 2015 225
R HASSELL et al

FIG 7 Plan view of the maximum recorded vibration levels in mm/s with respect to toe of the holes (-1 values refer to holes not fired).

parameters such as stand-off distances, explosive charge


densities and overall charging configurations with the view
to minimise the extent of damage beyond the boundaries of
the excavation.
The assumptions allow the derivation of a non-linear
relationship to describe the peak particle velocity (PPV)
attenuation in the near field.

l H + xs - xo x -x a
PPV = K >d r nf arctan f p + arctan f o s p pH (1)
o ro ro
where:
l is the linear charge concentration (kg/m)
H, ro, xs, xo are geometric parameters (Figure 8)
This can be simplified to:

PPV = K 5 a?a (2)

where:
a  is defined as the Holmberg-Persson term (a term
which accounts for the explosive loading and
FIG 8 Terms of reference of the Holmberg-Persson
blasthole geometry)
equation (Holmberg and Persson, 1980).
K and a are the rock mass explosive specific attenuation levels were calculated and, according to the nominal initiation
constants time based on the blast plans and the recorded time of the
Site specific constants K and were determined in order to vibration pulse, a vibration level was assigned to a given
model peak particle velocity attenuation across the rock mass. blasthole. The data was then plotted as vibration levels versus
This is achieved by analysing near-field PPV measurements the Holmberg-Persson Term.
for different blasting configurations and explosive types. The data can be regressed to determine equations that relate
From the vibration waveforms, the peak vector sum vibration vibration level to distance and explosive loading. The data

226 11TH INTERNATIONAL SYMPOSIUM ON ROCK FRAGMENTATION BY BLASTING / SYDNEY, NSW, 2426 AUGUST 2015
STOPE BLAST VIBRATION ANALYSIS AT DUGALD RIVER UNDERGROUND MINE

is fitted using a constant defining the rate of attenuation (a) being fired together the blast vibration data was separated
and the assessment of the potential damage from the blast is into separate blast areas and K values determined.
determined by the relative K values. Higher values of K reflect Given that the values have been calculated for similar rock
greater vibrational energy yield and potentially a greater zone mass conditions, stope size and monitoring location and
of damage around a blasthole. A value of a equal to 0.75 was distances, they can be used as a relative comparison to assess
used for all the monitored blasts at Dugald River. A typical performance. Due to the large data set and subsequent time
analysis result is shown in Figure 9. In this example of the restraints, the same level of analysis was not completed for
final mass blast of Stope 9, the K value was calculated at 2200, each stope. The comparative results for the Dugald River
the largest K value calculated for the monitoring. Some of the stopes are shown in Table 1.
points do not fit this trend and the outlier high vibration points The values show that for comparable amounts of explosive
are discussed later. charges, most of the blast damage is occurring at the initial
After determining the site specific attenuation constants, stages of the void generation during the winze/slot creation
predictions of the extent of blast damage/preconditioning (and interaction between them). The process is complicated
into stope walls can be made by applying the Holmberg- by the stoping geometry with both parallel and radial drilling.
Persson model and by considering a site specific critical PPV For example, for longitudinal stoping, the drilling drives are
or damage threshold given by the following relationship not open across the full orebody width, thus requiring radial
(Persson, Holmberg and Lee, 1994): drilling for the slot instead of the parallel drilling. With ore
drives located on the orebody hanging wall, radial drilling will
TVp necessarily toe into the stope FW boundaries. To understand
PPVcrit = (3) the effect of different blasthole orientations further analysis
E
is required.
where:
T is the tensile strength of the rock (Pa) Blasthole orientation
E is the elastic Youngs modulus (Pa) To determine the source of the high vibration the results
Vp is the compressional wave velocity (m/s) from ring firings were divided into damage potential from
Intact rock property testing of the orebody and adjacent breakthrough holes (B/T), FW Stabbing and radial toeing into
slates provides tensile strength ranges from 10.0 to 18.5MPa the footwall (FW Toeing), as per Figure 10. The blast vibration
and a modulus from 55 to 73 GPa (Hogan and Thompson, data for ring firings for Stopes 5, 7 and 9 were separated
2014). Assuming a P-wave velocity of 5800 m/s this provides out based on this hole nomenclature and K values were
a PPVcrit range from 800 mm/s for massive breccia to determined. The results, shown in Table 2, suggest that most
1500 mm/s for unaltered slates. For this analysis, values of of the damage is occurring from the FW stabbing and radial
PPV exceeding 1000 mm/s are considered critical. toeing into the stope footwall. Damage leading to overbreak is
augmented when steep west-dipping faults daylight into the
Blast vibration analysis results footwall stope boundary. This provides a plane of weakness
The underlying assumption is that the assessment of the to which the rock fails back to.
potential damage from a particular blast is determined by The large vibrations (for the charge weight) emanating
the relative (Holmberg-Persson) K values. Higher values of from the footwall boundaries were being monitored within
K reflect greater vibrational energy yield and potentially a the instrumented stope hanging walls. That is, the large
greater zone of damage around the blastholes. K values were vibrations were being recorded even with the progressive
determined for each blast. However, given the complexity void being formed ahead of the detonation front at those
of the blasts with multiple blast areas (winze, slot, rings) all locations (ie centre of stope blasted first). The increase in

FIG 9 Vibration levels versus the Holmberg-Persson term for Stope 9, final mass blast (from Villaescusa, 2014b).

11TH INTERNATIONAL SYMPOSIUM ON ROCK FRAGMENTATION BY BLASTING / SYDNEY, NSW, 2426 AUGUST 2015 227
R HASSELL et al

TABLE 1
A comparison of K values at the Dugald River Mine (from Villaescusa, 2014b).

Stope Stope type Firing type Ring burdens K value


(m) Winze Slot Rings
2 Transverse LHW winze 1 a 567 a a
LHW winze 2 a 1200 a a
LHW winze 3, full slot a b b a
Rings 2.0 a a 2000
5 Transverse LHW winze 1 a 497 a a
LHW winze 2, slot undercut a 300 1000 a
LHW winze 3, slot, rings 2.0 850 1600 2200
7 Longitudinal LHW winze 1 a b b b
LHW winze 2, slot undercut a 1131 650 a
LHW winze 3, slot, rings 1.4 and 2.4 c c 2200
9 Transverse Raise bore winze 1, slot undercut a 350800 2000 a
Raise bore winze 2, slot, rings 2.0 and 2.5 c c 2200
10 Longitudinal Raise bore winze 1, slot undercut a 10002200 1000 a
Raise bore winze 2, slot, rings 1.9 and 2.0 350 500 800
a. Not part of firing; b. firing occurred but no vibration data recorded; c. firing occurred, data recorded, detailed analysis not completed.

FIG 10 Sections showing design and cavity monitoring system shapes with locations for breakthrough holes
(B/T), footwall (FW) stabbing holes and FW toeing holes. Fault locations are also shown.

TABLE 2
K values for ring firings by hole location (Villaescusa, 2014b).

Stope Firing number Ring burdens (m) K value


All rings Breakthrough Footwall stabbing Footwall toeing
5 5.3 2.0 2200 1600 1600 2200
7 7.3 1.4 1000 200 1200 1000
7 7.3 2.4 2600 180 600 2600
9 9.1 2.5 2200 2200 1100 2200

228 11TH INTERNATIONAL SYMPOSIUM ON ROCK FRAGMENTATION BY BLASTING / SYDNEY, NSW, 2426 AUGUST 2015
STOPE BLAST VIBRATION ANALYSIS AT DUGALD RIVER UNDERGROUND MINE

blast vibration damage due to confinement of the blastholes the 89 mm holes with the drilling practices and the rock mass
in the footwall is considerable. Cavity monitoring system strength at Dugald River.
(CMS) surveys at those stope locations indicate damage such
as overbreak. The benefit of parallel, breakthrough holes in Firing sequence
reducing blast vibration damage is clear. The relatively tight mass blasting sequence (ie only two firings
An exception to this was Stope 9 where high vibration per stope), used for some stopes did not seem to increase
was observed in the hanging wall holes. This stope had a damage to the rock mass compared to those stopes with a
large amount of underbreak on both the hanging wall and greater number of firings. Stope 2 was extracted with four
footwall from the ring firing due to poor ground conditions firings and by firing out the slot completely before the ring
with collapsing holes leading to some holes being uncharged. firings. This compares with Stopes 5 and 7 with three firings
It is presumed the additional confinement provided by the and Stopes 9 and 10 with two firings. The later stopes had an
unfired holes created the high vibration results shown in 810 m cap over the slot that was fired with the rings during
Figure 9. the final mass firing. The results did not show a discernible
difference between the two methods. Later stope firings
Hanging wall blasthole stand-off distance during the trial that were not blast monitored successfully
fired out entire lifts (winze, slot and rings) in the one firing.
All stopes were designed with a 1 m blasthole stand-off from
It is generally considered that a more sequential enlargement
the stope hanging wall boundary. The aim of the stand-
of the winze and slot reduces blast damage prior to the mass
off was to limit rock breakage beyond the stope design.
blasting. More data for an increased number of firings would
Reconciliations of hanging wall overbreak following mining
have been preferred, but given the current information, tight
compared favourably with the stand-off distance with
mass blasting sequences perform well and with considerable
overbreak in good ground conditions limited to less than 1 m.
productivity benefits.
Hanging wall failure of Stope 2 in poor ground conditions
nearly reached the adjacent accelerometer position, where very Winzes
high levels of vibration (5000 mm/s) were measured at about Two types of winzes were used: a conventional longhole
5.58.5 m distances from the hanging wall holes. This level of winze (LHW) and a raise bore assisted winze (Figure 4).
vibration probably represents the limit of breakage for this rock Both winzes were 3.0 m 3.0 m, with the LHW containing
mass and stoping geometry as indicated by the CMS survey. 13 blastholes and 4 203 mm diameter reamers and the raise
The results agree well with the notion that PPVbreakage is about bore assisted winze containing 12 blastholes and a 1000 mm
four times PPVcritical (Villaescusa, 2014b). Stope 7 accelerometer diameter raise bore. K values for LHW ranged from 3001200
was located about 3 m away from the hanging wall hole. (Stopes 2, 5 and 7; Table 1) and raise-bore-assisted from
Back analysis of overbreak showed similar levels of PPVcritical 3502200 (Stopes9 and 10; Table 1). Both winze methods had
and PPVbreakage. Based on the accelerometer results, a stand-off comparable blast vibrations with the exception of the winze
distance of at least a metre is required for the hanging wall holes and slot undercut firing of Stope 10.
in order to minimise breakage beyond the stope boundary.
The very high vibration levels for the raise-bore-assisted
winze during the first firing of Stope 10 were for the first eight
Ring burdens
holes near the raise bored relief hole. The results suggest that
Ring burdens ranging from 1.4 m to 2.5 m were monitored. the use of a raise bore does not necessarily lower the stope
Observations on the quality of the ore walls following firing blast damage and that more holes may be required near the
generally showed relatively smooth, clean walls that have raise bore hole to break its circularity very early on in the
broken back to the ring location (Figure 11). Some cratering detonation sequence. However, the raise bore-assisted winzes
occurred at the collar. The monitoring data indicates a similar tended to be fired over a greater length so alternatively,
level of vibration over several mass blasts (Table 2). The 1.4m shorter raise heights ahead of the slot creation could be
ring burden displayed the lowest vibration but its design was blasted to reduce the confinement.
the result of wall overbreak in the adjacent stope and is not
considered an economically viable option. The analysis could The effect of backfill in limiting further damage in
not distinguish a significant difference between 2.0 m to 2.5m
ring spacings. Therefore, a 2.5 m burden is recommended for adjacent stopes
The effectiveness of the fill mass was investigated by
monitoring Accelerometer A3 in the hanging wall of Stope2.
Figure 12 shows the response of A3 with the three blast events
on Stope 5 with K values from 549 to 850. This compares to
closed wall (before extraction) K values of 550, which were
recorded for other stopes. The accelerometer data suggest
that the cemented rock fill support is effectively stabilising the
filled voids. Hence, the data from filled stopes is similar to the
data obtained when the stope wall is not yet open.

PRACTICAL APPLICATIONS OF THE BLAST


MONITORING RESULTS
The key outcome of the blast monitoring trial was to confirm
the benefit of parallel, breakthrough holes in reducing blast
vibration damage. Confining of blastholes by drilling of radial
rings toeing or stabbing into the rock mass leads to higher
FIG 11 View towards Stope 2 hanging wall showing vibrational energy yield which contributes to increased
the condition of the ore walls after slot firing. overbreak. Comparison of overbreak volumes in Table 3

11TH INTERNATIONAL SYMPOSIUM ON ROCK FRAGMENTATION BY BLASTING / SYDNEY, NSW, 2426 AUGUST 2015 229
R HASSELL et al

FIG 12 Vibration levels versus the Holmberg-Persson term for mass blast for Stope 5 as monitored from
accelerometers A3 located in adjacent filled Stope 2 (from Villaescusa, 2014b).

TABLE 3 vibration results and back analysing stope overbreak where


Overbreak volumes in the hanging wall and footwall non-structural-related overbreak was limited to less than 1m.
Where faulting influenced the hanging wall, the depth and
of the stopes that were blast monitored.
extent of failure was less than seen in the footwall. This system
Stope Hanging wall overbreak Footwall overbreak should be incorporated into future stoping at Dugald River.
volume (m3) volume (m3) Faulting of the rock mass surrounding stoping and the
subsequent reduction in rock mass quality is a reality of the
2 364.5 243.5
Dugald River orebody. Reducing the damage from stope
5 24.5 293.2 blast vibrations is considered a central control for reducing
7 420.8 98.8 fault related and non-fault related overbreak. To reduce the
level of footwall blast damage, a solution is to drill parallel
9 203.3 198.3
footwall holes particularly within the slot. However, there
10 30.7 343.6 are some practical considerations to these recommendations.
Total 1043.8 1177.4 For transverse stopes with a cross-cut drive, the winze and
slot can be drilled parallel without any changes to the mine
provides additional confirmation. The footwall had a greater design. Where the orebody dip is less than 70, there will need
amount of overbreak volume than the hanging wall. This to be some consideration on the drilling of the fired ore and
compares well to the overbreak volume of all 19 stopes, with potential confinement of the footwall holes.
4882 m3 in the hanging wall and 5655 m3 in the footwall. To achieve parallel drilling with the rings, additional footwall
Typical sections showing overbreak and underbreak have ore drive development is required. This adds a significant
been shown previously in Figure 10. additional cost for each stope, with negative mine scheduling
Both the hanging wall and footwall exposed similar ground implications. However, a large enough orebody width is
conditions, with an average hanging wall Q of 10.1 and an required to achieve this which is not common for Dugald River.
average footwall Q of 9.3. Q values are for the first 5 m of For longitudinal stopes, the ore drill drive will be required
the hanging wall or footwall. The footwall can be regarded as to be opened to the full orebody width. Current ore drives are
kinematically more stable with failure by sliding as opposed 5.5m wide, which allow for parallel drilling of the footwall and
to slabbing and gravity fall. Both surfaces were intersected hanging wall for orebody widths less than 3.5 m. Increased
by faults, which often influenced the location and depth of development and ground support costs, variable orebody
overbreak. Where faults daylighted into the stope, as shown widths and decreased stability from larger excavations all
in Figure 10, the overbreak profile followed the fault plane. need to be considered. Beyond a 7 m orebody width this will
The hanging wall did have the benefit of cable bolting from not be practical and a cross-cut drive is required to ensure
the ore drive which controlled overbreak. However, the parallel slot holes as a minimum.
evidence strongly suggests that the high vibrations created in Two types of winze were trialled, conventional longhole
the footwall of the stopes are a major control on overbreak. winzes and raise bore-assisted winzes. Results show that the
Hanging wall overbreak, by comparison, with parallel, introduction of the raise bore does not directly result in an
1m stand-off breakthrough blastholes combined with lower- automatic reduction in blast damage. Winzes that are not
density explosive charging (0.8 EP) and increased delays parallel to the hanging wall (and particularly when vertical)
limited blast vibration damage. This was shown in the blast result in high vibration due to radial drilling within the

230 11TH INTERNATIONAL SYMPOSIUM ON ROCK FRAGMENTATION BY BLASTING / SYDNEY, NSW, 2426 AUGUST 2015
STOPE BLAST VIBRATION ANALYSIS AT DUGALD RIVER UNDERGROUND MINE

slot. Preferences for either winze type should be based on ACKNOWLEDGEMENTS


scheduling and operational constraints to achieve parallel
The authors would like to acknowledge the help of Tom
holes within the slot.
Williams, Jack Carswell and Andrew Rajapakse, Geotechnical
The results showed that larger ring burdens and reduced Engineers at Dugald River, John Heilig from Heilig and
number but larger stope firing sequences do not appear to Partners and Italo Onederra from JKMRC for aiding in the
increase the overall damage to the rock mass when compared completion of the project. The authors would also like to
to smaller ring burdens and an additional staged firing thank MMG for permission to publish this paper.
sequence. Both outcomes improve the productivity of the
stope cycle and confirm their low influence on blast damage.
REFERENCES
Hogan, P and Thompson, A, 2014. Report on intact rock properties
CONCLUSIONS testing for Dugald River, Western Australian School of Mines,
A highly successful blast vibration monitoring program Curtin University of Technology.
was completed at Dugald River, which greatly enhanced Holmberg, R and Persson, P A, 1980. Design of tunnel perimeter blast
the understanding of the main controls on blast damage. hole patterns to prevent rock damage, Transactions of the Institute
The effectiveness of the program relied on clear objectives, of Mining and Metallurgy, 89:A37-A40.
strong management support, good instrument design, a MMG Limited, n/d. Dugald River fact sheet [online]. Available from:
high level of oversight during instrument installation and <http://www.mmg.com/en/Our-Operations/Development-
data collection, together with detailed analysis techniques projects/Dugald-River.aspx> [Accessed: March 2015].
to understand what the data is saying. Such programs are Orica, 2011. Subtek Eclipse [online], 6 October. Available from: <http://
difficult to implement at an operating underground mine but www.oricaminingservices.com/au/en/page/products_and_
the benefit of actual data over opinions and rules of thumb services/bulk_systems/bulk_systems> [Accessed: March 2015].
cannot be overstated. Orica, 2014. i-kon II detonator [online], April. Available from:
The main parameters that cause high blast vibrations leading <http://www.oricaminingservices.com/au/en/page/
to stope wall damage were identified with the advantage of products_and_services/electronic_blasting_systems/i-kon_ii/i-
parallel breakthrough holes being clearly proven. Changes to kon_ii_-_the_next_generation> [Accessed: March 2015]
the stope drill and blast design are suggested to better control Persson, P, Holmberg, R and Lee, J, 1994. Rock Blasting and Explosives
blast vibrations. These controls have impacts beyond simple Engineering (CRC Press: London).
ring design and timing. A cost benefit analysis of the options Villaescusa, E, 2014a. Geotechnical Design for Sublevel Open Stoping
was not part of the scope of the project but would greatly aid (CRC Press: London).
in determining the balance between cost, productivity and Villaescusa, E, 2014b. Blast monitoring of sublevel open stoping
managing overbreak from blast vibrations. production blasting, Research project for MMG Dugald River,
Western Australian School of Mines, Curtin University of
Technology.

11TH INTERNATIONAL SYMPOSIUM ON ROCK FRAGMENTATION BY BLASTING / SYDNEY, NSW, 2426 AUGUST 2015 231

Você também pode gostar