Escolar Documentos
Profissional Documentos
Cultura Documentos
2004 - 9
2005 June
Items to be considered -
Example 1:
Schedule of Finishes
Location Ceiling Walls Floor
Entrance 10 mm Render in 3 mm
Passage plasterboard cement and sand thermoplastic
skimmed with 3 (1:3) 10 mm tiles on 52 mm
mm coat of hard thick and set cement and sand
wall plaster and with 3 mm hard screed.
twice emulsion wall plaster and
painted. finished with 2
undercoats and
1 coat of hard
gloss paint.
Waiting room --- Ditto --- Render and set 30 mm thick oak
as before; 450 black flooring
mm frieze twice laid herring
emulsion bone, with two
painted, black plain
remainder borders on 25
papered with mm cement and
pattern paper, sand screed.
P.C. $ 5.00 cents
per piece and
frieze border P.C.
$ 4.00 cents per
meter.
Office --- Ditto --- Render and set --- Ditto ---
as before and
twice emulsion
painted.
Note: All rooms are 2.400 m high (20 mm coved internal angles)
Example2:
Manhol Ground Invert Type of Sewer Type of Location
e level Level manhole size channel
nr cover
1 240.000 236.00 Medium 2 / 225 Field
0 225 straight
2 238.800 236.30 Medium 2 / 225 Field
0 225 curved
3 238.500 236.54 Medium 1 / 225 Field
0 225 straight
4 238.650 236.75 Heavy 3 / 150 Road
5 150 curved
5 239.000 237.05 Heavy 2 / 150 Road
5 150 curved
6 239.000 237.05 Heavy 2 / 150 Road
5 150 curved
Total 3 5 /225
Medium 7 /
3 Heavy
1
5
0
Operational Bill:
The description of the billed work followed the actual building process,
with materials shown separately from labour, all described in terms of the
operations necessary for the construction of the building. (An operation –
work performed by a man or a gang between definite breaks in the work
pattern. Ex. Brick laying from DPC to 1st floor).
Activity Bill:
The activity bill is a development of the operational form but without the
separation of labour and materials. It is sub divided in to sections based
on activities or operations described from a network analysis.
Elemental Bill:
Items were arranged (not in work section order main headings of the
separate work sections) and grouped according to their position in the
building (element). Ex. External wall, Roof, Floor, etc.
Within each element, the items could be billed in work section order or
grouped in building sequence.
Annotated Bill:
It is possible for the bill of quantities to give the contractor full details of
the quantity, type and quality of materials and labour, and for an accurate
and complete set of drawings to show him precisely where and how the
work is to be executed. Nevertheless, there are always some billed items
whose locations in the work is not readily identifiable, and it is most useful
to have a note against them in the bill giving their locations.