Você está na página 1de 9

ARTICLE IN PRESS

WAT E R R E S E A R C H 42 (2008) 338 346

Available at www.sciencedirect.com

journal homepage: www.elsevier.com/locate/watres

Biological nutrient removal in a small-scale MBR treating


household wastewater

Christian Abegglena,b,, Mario Ospelta,b, Hansruedi Siegrista,b


a
Eawag, Swiss Federal Institute of Aquatic Sciences and Technology, CH-8600 Dubendorf, Switzerland
b
ETH, Institute of Environmental Engineering, CH-8093 Zurich, Switzerland

ar t ic l e i n f o abs tra ct

Article history: The biological nutrient-removal potential of an on-site Membrane bioreactor (MBR) located
Received 27 January 2007 in the basement of a four-person house treating domestic wastewater was investigated.
Received in revised form The reactor consists of two tanks in series. This treatment plant differs from other
28 June 2007 conventional MBRs by a highly fluctuating influent water flow and a lack of pretreatment.
Accepted 18 July 2007 During the first period, the first reactor was operated as a primary clarifier, resulting in
Available online 25 July 2007 nitrogen and phosphorus removals of 50% and 25%, respectively. Primary sludge
production and bad odors in the basement were further disadvantages. When using the
Keywords:
first reactor as an anaerobic/anoxic reactor by recycling activated sludge and mixing the
On-site wastewater treatment
first reactor, nitrogen and phosphorus removals of over 90% and 70% were achieved,
Membrane bioreactor (MBR)
respectively. By applying a dynamic model of the plant, the return sludge ratio was
Decentralized
identified as the most important parameter. With a return sludge ratio of about 1.2, optimal
Biological nutrient removal
PAO growth and phosphorous removal up to 90% was reached. Since only activated sludge
Enhanced biological phosphorus
is produced with this operational mode, on-site sludge dewatering is possible. During
removal (EBPR)
vacation periods without loading, the Bio-P activity is kept constant if the aeration is
reduced to 520 min d1.
& 2007 Elsevier Ltd. All rights reserved.

1. Introduction wastewater, assuming that the plants are maintained and


operated properly. In reality, this value is expected to be much
The purification capacity of small-scale wastewater treat- higher.
ment plants (WWTPs) for the two nutrients nitrogen and Since decentralized wastewater treatment is seen as a possible
phosphorus is often limited. Nitrification and denitrification future technology allowing the sanitation requirements to be met
may occur to a certain degree in biological systems, depend- (Green and Ho, 2005; Wilderer, 2005), nutrient removal in small-
ing on the plant layout and the operating conditions. In scale plants should move into the focus of research interest.
contrast, phosphorus is only removed to a substantial extent The optimum technology and plant size will depend on the
with the aid of chemical precipitation. specific circumstances of each site. However, membrane bior-
Table 1 compares removal efficiencies of different treat- eactor (MBR) technology may be of interest for small-scale
ment systems with a central WWTP. These values were wastewater treatment (Fane and Fane, 2005). Thanks to their
estimated by Swiss experts based on measurements in small reactor size and good effluent quality, which makes the
several small-scale treatment plants (VSA, 2005). effluent available for reuse, MBRs are an attractive option for
Flasche (2002) estimates that the 10% of the population decentralized sites. Nutrient removal in (decentralized) MBRs has
connected to small-scale WWTPs in Lower Saxony (Germany) been studied by several researchers who showed that high levels
account for 20% of the organic and nitrogen loads in domestic of both nitrogen and phosphorus removal can be achieved by

Corresponding author. Eawag, Swiss Federal Institute of Aquatic Sciences and Technology, CH-8600 Dubendorf, Switzerland.
Tel.: +41 44 823 53 79.
E-mail address: christian.abegglen@eawag.ch (C. Abegglen).
0043-1354/$ - see front matter & 2007 Elsevier Ltd. All rights reserved.
doi:10.1016/j.watres.2007.07.020
ARTICLE IN PRESS
WAT E R R E S E A R C H 42 (2008) 338 346 339

Table 1 Removal efficiencies for several small-scale wastewater treatment plants, compared with the WWTP
Werdhoelzli, Zurich

COD removal (%) N removal (%) P removal (%) Source

Septic tank 2030 010 10 VSA (2005)


SBR 490 1070 1070 VSA (2005)
Trickling filter 490 1040 10 VSA (2005)
Reed bed 48090 1090 1060 VSA (2005)
Sand filter 48090 1020 10 VSA (2005)
WWTP 95 60 90 Plant data

Bath, Kitchen

Recycling Irrigation
Toilet

Sieve Infiltration
Storage
Q tank

QR
V1
V2

Excess
Hydrolysis MBR sludge

Fig. 1 Modified flow scheme with hydrolysis chamber. During operation with the primary clarifier, no sieve and return
sludge pump were in operation and the first reactor was neither mixed nor aerated.

biological means (e.g. Ahn et al., 2003; Lesjean et al., 2005; Monti produced within the building flows through the treatment
et al., 2006; Patel and Nakhla, 2006). However, all these reactor plant. The effluent is stored in a tank outside: 35% of it is
systems are adaptations of the conventional activated sludge recycled for toilet flushing and irrigation, while the rest is
system: they rely on continuous water flows and pretreatment percolated.
(e.g. screen), and they are designed for 1001000 PE. The plant consists of two reactors each with a volume of
Conventional reactor designs cannot be applied on a 1.5 m3 (Fig. 1). A flat-sheet membrane (4 m2, 0.04 mm pore size)
household scale for several reasons: water flows are subject with coarse bubble cross-flow aeration is installed in the
to high fluctuation, the reactor size needs to be designed for second reactor. Oxygen is supplied by fine bubble aeration.
buffering the water flow and it is difficult to implement The first tank was initially used as a primary clarifier and
clearly defined environmental conditions in every part of the subsequently as a biological reactor. During the second
plant. Operating stability, maintenance requirements and soft period, the sludge from the MBR was pumped to the first
factors such as noise and odors also need to be considered. tank by an airlift pump. Excess sludge is pumped to a filter
In this study, we investigated the operation of a two- bag outside the building at intervals of 12 weeks.
chamber MBR used to treat the domestic wastewater of a
four-person household. Two reactor configurations were 2.1.1. Operation with primary clarifier
compared with respect to their operational stability and The first reactor was initially used as a sedimentation tank.
nutrient removal. The configurations studied included a A baffle with an opening at the bottom was installed in the
primary clarifier in the first reactor followed by an MBR in middle of the reactor to prevent short circuits. The hydraulic
the second reactor for the first period, and an anaerobic/ retention time was approximately 3 d. This led to an equal-
anoxic reactor followed by an MBR for the second period. ization of the pollutant concentration. A stable, malodorous
sludge blanket formed within a short time. The primary
sludge was removed when the operational mode was
2. Material and methods changed.

2.1. Wastewater treatment plant 2.1.2. Operation with sludge recycling


The first reactor was retrofitted for several reasons: bad odors,
The treatment plant is located in the basement of a four- limited nutrient removal and primary sludge production. In
person household in Switzerland. All the wastewater order to overcome these disadvantages, mixing between the
ARTICLE IN PRESS
340 WA T E R R E S E A R C H 42 (2008) 338 346

two reactors was enhanced. This was done by pumping Several plant parameters are recorded and can be mon-
activated sludge from the MBR to the first reactor, where a itored online: water level (both reactors), drinking water
second airlift pump was installed for aeration, mixing and consumption, transmembrane pressure and permeate flow.
dosing wastewater to the MBR. A sieve had to be installed in The switch on and off times of the aeration pumps, airlift
the first reactor to prevent clogging of the membrane. The pumps, the permeate pump and the excess sludge pump are
presence of oxygen (from the airlift pump), nitrate and also recorded.
activated sludge (from the MBR) in the first reactor was
expected to reduce the production of bad odors and to 2.4. Model
enhance hydrolysis, denitrification and biological P-removal.
A plant model for dynamic simulations based on Fig. 1 and
2.1.3. Control system Table 2 was set up in Simba (ifak GmbH, Magdeburg,
All the pumps (aeration, airlift pumps) are operated inter- Germany). The biokinetic model used was the ASM3 (Henze
mittently. Aeration and permeate withdrawal are controlled et al., 2000) for organic matter and nitrogen with the
by the water level. Three operational modes can be differ- parameter set from Koch et al. (2000), extended by the Eawag
entiated: Bio-P module (Rieger et al., 2001) for the phosphorus
components. The influent water flow was modeled using
 Sleep mode: Due to noise emissions from the aeration, plant data from the water-level measurements.
which the residents perceived as disturbing, the plant had Data from September to November 2005 were used for the
to be switched off during 7.5 h at night (10 p.m.5.30 a.m.). operation with the primary clarifier, and from March to June
It would be switched on only in case of emergency, i.e. if 2006 for the simulations of the second period. This period
the water level were to rise beyond an alarm level. During covered three different load situations: vacation (no influent)
sleep mode, all the pumps are shut down. during the first 7 d, followed by normal load for 42 d and a
 Standby mode: This mode can be defined as the filling low-loading period of 14 d at the end.
phase. The aeration system is turned on, but is maintained
at a low level. During the second period, the airlift pumps 2.4.1. Model calibration for operation with primary clarifier
were also switched on. In the first period, the primary clarifier was not included in
 Pump mode: This mode is switched on as soon as the water the model. The primary effluent concentrations were quite
level in the MBR reaches a certain height. After a defined stable over the whole period and were assumed to be
pre-aeration time the permeate pump starts, the cross- constant. Measured COD, nitrogen and phosphorus concen-
flow aeration works all the time and the fine bubble trations were used as influent values (Table 2). COD was
aeration system operates at the defined aeration times. fractionated according to Table 3.
The permeate suction pump is switched off when a For the period with sludge recycling, the raw influent had to
minimum water level or sleep time is reached. be characterized. Its composition depends strongly on water
origin (showering, feces, urine, kitchen sink, etc.) and could
not be assessed directly within our system. As the hydraulic
2.2. Wastewater composition
retention time in the first reactor still remained around 2 d,
the influent concentrations were assumed to be constant over
The treatment plant is fed by domestic wastewater. In
the day.
contrast to most other investigations with small-scale
Nitrogen and phosphorus influent loads could be estimated
WWTPs, the wastewater does not originate from a sewer
from the period with primary clarifier; however, for COD this
system. Several difficulties must therefore be overcome: this
was not possible. The calibration aimed at obtaining a
wastewater is not diluted by rainwater or infiltrated ground-
suitable and realistic COD fragmentation, because this has a
water, it contains hair and particles, the water flow and
strong impact on the biological activity. The resulting influent
pollutant load to the plant fluctuates greatly and is not
controllable, and neither the wastewater composition nor the
concentrations in the raw influent can be measured. Further-
Table 2 Model inlet concentrations and plant conditions
more, around 30% of the influent is recycled permeate, which for the two periods
leads to an accumulation of non-degradable substances
(e.g. salts, organic matter, color).
1st period 2nd period

2.3. Measurements CODtot gCOD m3 560 1100


Ntot gN m3 100 105
Ptot gP m3 20 20
Grab samples were taken from the influent and effluent of the
Alkalinity mol m3 12 12
MBR, transported to the laboratory and analyzed within hours
Q m3 d1 0.36; 0.010.86 0.34; 0.040.76
by the cantonal laboratory of Solothurn according to standard QR m3 d1 0 0.250.6
Swiss methods (Clesceri et al., 1998). Online measurement V1 m3 1.3 (not modeled) 11.3 (fully
devices from WTW (Weilheim, Germany) of the 700 IQ series mixed)
were used for oxygen (Trioxmatic), ammonium (Ammolyt), V2 m3 0.81.3 (fully 11.3 (fully
nitrate (Varion), temperature, pH and redox potential mixed) mixed)

(Sensolyt).
ARTICLE IN PRESS
WAT E R R E S E A R C H 42 (2008) 338 346 341

Table 3 Resulting COD fractionation for the two operating conditions (aeration times), no significant improve-
modeled periods ment of denitrification could be obtained without impairing
nitrification.
Fraction SS SI XI XH XA XS
3.1.3. Phosphorus removal
Koch et al. 0.1 0.06 0.2 0.09 0 0.55 The only phosphorus-removing process expected was incor-
(2000)
poration into the biomass. With an average sludge production
1st period 0.1 0.06 0.2 0.05 0.004 0.586
2nd period 0.1 0.03 0.2 0.05 0.004 0.616
of 60 gCOD d1, a phosphorus-removal potential of 0.9 gP d1 or
10% is calculated (iP 0.015 gP g1
COD). However, the observed
phosphorus-removal was 2 gP d1 (Table 4), corresponding to
25% and a phosphorus content of the excess sludge of 3.5%,
which indicates that other processes were involved. As the
composition and plant conditions are shown in Table 2 and sludge is not exposed to anaerobic conditions, enhanced
the COD characterization with the model in Table 3. The biological phosphorus removal (EBPR) was excluded (no
activated sludge concentration was successfully reproduced activity could be detected in batch tests either). Recycling of
on the basis of this inlet characterization. Excess sludge the wastewater means that potassium, magnesium and
removal was implemented according to real plant data. calcium ions accumulate in the system, leading to higher
The influent phosphorus concentration was set to 80% of concentrations than in the drinking water. With this higher
the estimated influent concentrations due to precipitation ion concentration and the relatively high pH value (7.87.9),
processes in the MBR (precipitation processes were not precipitation of phosphates (apatite, struvite) may account for
included in the model, see Section 3.1.3). the higher phosphorus-removal efficiency (Maurer and Boller,
1996). Additional phosphorus removal could originate from
2.4.2. Biokinetic model calibration the presence of additives in laundry detergents (zeolithes):
When the model was applied, the organic and nitrogen these release free aluminum ions which precipitate with the
components were reproduced adequately, but the phosphate phosphate (Wild et al., 1996).
effluent values were too high. One correction to the Eawag
Bio-P module (Rieger et al., 2001) had to be implemented: the 3.2. Operation with sludge recycling
decay rate of the PAOs was corrected from 0.2 to 0.15 d1 for
201, which is within the possible range mentioned by Lopez 3.2.1. Sludge production
et al. (2006). As expected, sludge production was strongly increased when
the primary clarifier was used as a biological reactor, reaching
1757100 gCOD d1, including toilet paper and feces, which are
3. Results normally kept back in the screen in conventional WWTP. This
corresponds to a total sludge production of 50 g d1 PE1 and
3.1. Operation with primary clarifier 34 people living in the house, which is about the same as
total sludge production in a conventional WWTP. The sludge
3.1.1. Sludge production age was between 50 and 200 d, and the F/M ratio could not be
The F/M ratio was in the range of 0.060.11 gCOD g1 1
VSS d , with determined.
a sludge age of 3050 d. Activated sludge production in the
MBR during this period was 60 gCOD d1 (720 gCOD d1). Sludge 3.2.2. Nitrogen removal
removal occurred on a weekly basis and was stopped Nitrogen removal was strongly improved with recycling,
temporarily. With this operation mode, approximately 56 compared with the first period. Nitrification was still stable,
filter bags with a volume of 40 l would be filled per year. but without the distinct morning peaks observed during
No measurements of the primary sludge production primary clarifier operation (Figs. 2 and 3).
were made. The most remarkable difference was seen in the denitrifi-
cation. The nitrate effluent concentrations decreased from 45
3.1.2. Nitrogen removal to 510 g m3 (Fig. 4), so that a total nitrogen removal of over
Due to the high sludge age, nitrification was very stable. In the 90% was achieved. This happened immediately after the
mornings, an ammonium peak with values of 510 gN m3 operating mode was changed.
could be observed (Fig. 2), which was minimized by introdu-
cing a pre-aeration step before starting the permeate with- 3.2.3. Phosphorus removal
drawal. The peak stemmed from the high water consumption Only a slight increase in phosphorus removal was observed at
in the morning, when people took a shower, and the the beginning of the new operating mode with QR/Q 0.1,
ammonium-rich water from the primary clarifier flowed to which could be attributed to higher sludge production. After
the MBR. The maximum ammonium concentration in the adjusting the operating conditions on March 15 (return sludge
MBR reached 20% of the influent concentration (Fig. 2). ratio increased to 1.5 70.5, slight decrease of the aeration
Total nitrogen elimination was 50%, including incorpora- intensity), the environmental conditions were suitable for
tion and denitrification. Incorporation was limited by sludge Bio-P organisms. After 1 month, Bio-P activity was clearly
production and denitrification by a lack of organic substrate. detectable with a phosphate reduction of about 5 g m3 and
When applying the dynamic model and changing the PAO activity measured in batch tests. Due to operating
ARTICLE IN PRESS
342 WA T E R R E S E A R C H 42 (2008) 338 346

ammonium phosphate nitrate


25 50

NH4-N and PO4-P (g m-3)


20 40

NO3-N (g m-3)
15 30

10 20

5 10

0 0
0 0.5 1 1.5 2 2.5 3
time (days)

Fig. 2 Modeled ammonium, phosphate and nitrate MBR concentrations with primary clarifier operation. The periods
marked in gray indicate permeate withdrawal times. The average modeled concentrations are similar to the measured
effluent concentrations. Phosphate is too high because no precipitation processes were implemented.

Table 4 Measured influent and effluent values of the


MBR for operation with primary clarifier ratios of 0.61.7, which resulted in PAO concentrations in the
MBR of 3001500 g m3, respectively (Fig. 5). Increasing the
Influent Effluent return sludge ratio over 1.2 did not affect the PAO concentra-
(MBR) (MBR) tions. Fig. 6 shows the corresponding phosphate concentra-
tions in the effluent (a) and the degradable substrate
COD gCOD m3 562 (7120) 38.1 (76.8) concentrations in the first reactor (b) for three return sludge
NH4-N gN m3 84.3 (712.9) 1.04 (71.08)
ratios (1.7, 1.06, calibration period (0.51.8)). The results show
NO3-N gN m3 45 (76.7)
that Bio-P is substrate-limited with a return sludge ratio
Ptot (in), PO4-P gP m3 23.9 (72.0) 17 (72.8)
(eff) greater than 1.2.
By optimizing the return sludge ratio, an average phos-
The samples were taken in the morning, which leads to elevated phorus removal of 70% was achieved (compared with 25%
ammonium values. during the calibration period). As Figs. 5 and 6 show, there is a
risk of significant phosphorus loss during and after zero or
low-loading periods. By reducing the aeration intensity
during such periods, PAO decay and phosphorus loss could
problems, the return sludge ratio was reduced to 0.51 be reduced. However, this requires an adapted aeration
between April 12 and June 14. Q/QR was increased to 1.5 control strategy.
again afterwards, which resulted in better phosphorus
removal of up to 85% in December 2006 (Fig. 4). 3.2.4.2. Permeate withdrawal. Sleep mode is one of the
operational constraints. It should be overcome in the design
3.2.4. Optimization of nutrient removal of a new system, as ammonium, nitrate and phosphate
Several parameters in the existing system were subject to values reach their minimum between midnight and 6 oclock
optimization: aeration times, dosing interval from the hydro- in their diurnal variation (Fig. 3). Implementation of a
lysis reactor to the MBR, return sludge ratio and permeate different process control that withdraws the permeate during
withdrawal times. The influent values of the calibration the night unless the water level reaches a maximum
period according to Tables 2 and 3 were used for the modeling level enhances phosphorus removal by another 10% to a total
of the optimization steps (15.4.13.6.2006). The results were of 80%.
always compared with those of the calibration period.

3.2.4.1. Return sludge ratio and aeration control. In the first 4 4. Discussion
weeks of the calibration period with a return sludge ratio of
1.570.5, the PAOs accumulated, but remained stable after 4.1. Operation with a primary clarifier
reducing that ratio to 0.5 (Fig. 5). This indicates the
importance of the return sludge ratio. As the airlift pumps The disadvantages of primary clarifier are the primary sludge
were operated with fixed time intervals, the return sludge production and formation of a malodorous sludge blanket.
ratio depended strongly on the influent water flow and could The activated sludge is preferentially pumped to the primary
not be regulated exactly. clarifier and removed together with the primary sludge,
During the calibration period no real steady state was which has to be disposed in a central WWTP.
reached. For the optimization of nutrient removal, the system The nitrification capacity is adapted to the average ammo-
was therefore dynamically modeled for about 200 d, to nium load, which leads to ammonium peaks during ammo-
achieve stable conditions. Subsequently, a period of 9 weeks nium shock loading. Denitrification is limited because
was studied in detail. The model was run with return sludge not enough substrate is available during anoxic periods.
ARTICLE IN PRESS
WAT E R R E S E A R C H 42 (2008) 338 346 343

ammonium nitrate phosphate


20

15

gN m-3; gP m-3
10

0
0 0.5 1 1.5 2 2.5 3
time (days)

Fig. 3 Modeled ammonium, nitrate and phosphate concentrations in the MBR with an optimized return sludge ratio. The
periods marked in gray indicate permeate withdrawal times.

QR/Q 0.1 1.5 0.5 1.5


25 50
calibration period Phosphate Nitrate
20 40

15 30

gN m-3
gP m-3

10 20

5 10

0 0
5.09.05 25.10.05 14.12.05 2.02.06 24.03.06 13.05.06 2.07.06 21.08.06 10.10.06 29.11.06
time

Fig. 4 Measured grab sample values of nitrate and phosphate in the permeate. With the beginning of the sludge recycling on
December 14, the nitrate values decreased substantially and Bio-P bacteria started to grow in. In March, the return sludge
ratio was increased to 12, which resulted in an improved biological P-removal. QR/Q was reduced to 0.5 between April 12 and
June 7 due to operation problems.

vacation normal load low load


2000
R = 1.7, optimized aeration
R = 1.7
1500
gCOD m-3

R = 1.26
1000
R = 1.06

500
R = 0.64
calibration
0
0 10 20 30 40 50 60
time [days]

Fig. 5 Modeled PAO concentrations for the calibration period and different ratios of QR/Q (1.7, 1.26, 1.06 and 0.64). During the
calibration period, the return sludge ratio varied between 0.5 and 1.8. For the runs with different ratios, the activated sludge
composition was brought to a steady state before modeling this period. When minimizing the aeration intensity during low-
loading periods, decay of PAO is reduced.

Optimization of the aeration times in the model showed no post-treatment step (Westholm, 2006) or urine separation
relevant improvement of nutrient removal. with separate treatment needs to be introduced.
Phosphorus removal is relatively low (25%) with this The data indicate that a primary clarifier may be advanta-
operating mode. If phosphorus removal is required, then geous for membrane permeability (Fig. 7). This could be
simultaneous precipitation with flocculants, sorption in a explained by the fact that the membrane chamber receives
ARTICLE IN PRESS
344 WA T E R R E S E A R C H 42 (2008) 338 346

vacation normal load low load


80
R = 1.7
R = 1.06
60
R = 0.64

gP m-3
R = 1.7, optimized
40

20

0
0 10 20 30 40 50 60

600 R = 1.7
R = 1.06
R = 0.64
400
gCOD m-3

200

0
030 10
40 50 20 60
time [days]
Fig. 6 (a) Modeled effluent phosphate concentration for different recycling ratios. (b) Modeled substrate concentrations in the
first reactor for different recycling ratios.

without with sludge recycling


Maximum suction pressure [bar]

0.0 250

Permeability [l m-2 bar-1 d-1]


max. suction pressure
-0.1 200
permeability

-0.2 150

-0.3 100

-0.4 50

-0.5 0
05.09.2005 25.10.2005 14.12.2005 02.02.2006 24.03.2006 13.05.2006 02.07.2006 21.08.2006

Fig. 7 Development of membrane permeability and maximum daily suction pressure (corresponding to the pressure
difference over the membrane) during the observed period.

less suspended solids and organic material, which cause results. This is mainly due to high water and load fluctua-
blockages and increased membrane fouling, respectively. tions, which temporarily lead to an overloading of the plant or
increased decay of PAOs due to minimal aeration. Under
optimum conditions, daily phosphorus removal of around
4.2. Operation with sludge recycling 90% can be achieved, which was also shown in reality, when
measured effluent phosphorus concentrations went down to
With sludge recycling between the MBR and the first tank, 1 gP m3 in November 2006 (Fig. 4).
only activated sludge is produced that can be treated locally.
In our system, the sludge is pumped into a filter bag where it
is dewatered to 10% dry matter. This sludge may be mixed 4.3. Operational constraints
with kitchen waste and composted. If the filter bag is placed
in a dry room, a dry matter content of 8090% is reached 4.3.1. Membrane permeability
without causing any odor problems. The model results are very positive and promising. Not all the
Odor problems in the basement disappeared thanks to proposed changes could be implemented on the plant
activated sludge recycling and intermittent aeration. In view because further experiments are still going on (e.g. urine
of the better nutrient removal and easier sludge handling separation). Moreover, the goals of a decentralized MBR may
(no malodorous primary sludge), this operation mode should differ under various conditions (legal requirements for
be favored in the future. effluent quality, water reuse). Safe and straightforward
Despite a very favorable COD:P ratio of 75 gCOD/gP, phos- operation of the plant is crucial, and one of the cost drivers
phorus removal is limited to 7080% according to the model is its servicing (e.g. membrane replacement or cleaning,
ARTICLE IN PRESS
WAT E R R E S E A R C H 42 (2008) 338 346 345

35 35
day 0
30 30
day 9
day 17
25 25

PO4-P (g m-3)
PO4-P (g m-3)

20 20

15 15

10 10

5 5

0 0
0 5 10 15 20 0 2 4 6 8 10
Time (days) Time (hours)

Fig. 8 Development of phosphate concentration during periods without influent (left) and after switching on the aeration
(days 0, 9 and 17). When the residents return from their vacation, the aeration should be switched on for a couple of hours to
enable the PAOs to take up the released phosphate before starting permeate withdrawal.

sludge removal, etc. (Trussell et al., 2006)). The servicing strongly equalized by the buffer volume of the first tank.
interval depends mainly on the membrane permeability and The weekly variation with higher water consumption on
is necessary every 612 months. weekends leads to longer pumping times, but there are also
Fig. 7 shows the development of the maximum suction periods without any influent. During such vacation periods,
pressure and the permeability of a new membrane module the aeration should be switched off to minimize decay rates,
during 1 year of operation. The membrane was replaced at the as was shown by Siegrist et al. (1999). When the aeration is
beginning of September 2006. It had never been cleaned switched off, however, anaerobic and putrescent conditions
during operation. There is no obvious change in the decreas- will become established, leading to the production of
ing gradient of the permeability profile after starting sludge methane as well as malodorous and toxic substances, which
recycling and intermittent aeration of the first reactor. The impair the activity of the microorganisms. Loss of phosphate
permeate flow (see equation) remains constant until a must also be prevented: under anaerobic conditions, PAOs
permeability of about 50 l m2 h1 bar1 is reached. release the stored polyphosphate as phosphate, which might
be lost after switching to normal operation again.
Q membrane Fmembrane Dpmembrane xmembrane ,
The behavior of the Bio-P organisms during vacation
with Fmembrane 4 m2, Dpmembrane max. suction pressure periods was determined with lab experiments. When kept
(bar) and xmembrane permeability (l m2 bar1 h1). in an anaerobic state with short daily aeration times
In the last month with a permeability of under (520 min d1), the phosphate is released within a week.
50 l m2 h1 bar1, the flow declined to 2530 l h1. This led to Although the activity remains stable for at least 3 weeks
a doubling of the pumping time and capacity problems. (Fig. 8), 24 h of aeration are required for the phosphorus
The space between the membrane plates, and the hole uptake to be completed before starting the permeate pump.
diameter of the sieve in the first reactor were both 6 mm. Hair,
seeds and other suspended solids partially passed through
the sieve and accumulated between the membrane plates, 5. Conclusions
leading to physical blockage of the plates and impaired
efficiency of cross-flow aeration. This effect was temporarily
 When operating an MBR with primary clarifier, good BOD
reduced by increasing the cross-flow aeration time during
removal, stable nitrification and nitrogen removal of
standby mode at the end of May 2006.
around 50% are easy to attain. Phosphorus removal was
The effect of this blocking on the permeability is not quite
around 30% by incorporation and natural precipitation.
clear because no significant permeability increase could be
When installed indoors, such a reactor needs to be airtight
observed after the membrane had been cleaned with high-
and equipped with off-gas treatment. The activated sludge
pressure water flows, active chlorine and acids. The removal
is best pumped to the primary clarifier, removed with the
of the physical blockage without associated improvement of
primary sludge and disposed in a central WWTP.
the permeability indicates that the decrease in the latter must
 The operation of the first reactor with mixing, aeration,
be attributed to membrane fouling.
sieving of the inlet to the MBR and sludge recycling results
in fewer odor problems, a higher denitrification rate
4.3.2. Vacation (490%) and partially enhanced biological phosphorus
As this treatment plant is operated in a one-family house, the removal of about 7090%. This operation has the advan-
loading is very dynamic but the diurnal variations are tage that a single, stabilized sludge is produced, which can
ARTICLE IN PRESS
346 WA T E R R E S E A R C H 42 (2008) 338 346

be dewatered and air-dried onsite. The influence of the Henze, M., Gujer, W., Mino, T., van Loosdrecht, M.C.M., 2000.
higher organic and suspended solids load on membrane Activated Sludge Model No. 3. Scientific and Technical Report
permeability will be further investigated during longer No. 9: Activated Sludge Models ASM1, ASM2, ASM2d and
ASM3. IWA Task Group on Mathematical Modeling for Design
operation periods.
and Operation of Biological Wastewater Treatment. IWA
 According to the simulation results, stable EBPR can be Publishing, London.
achieved in small-scale membrane systems with sludge Koch, G., Kuehni, M., Gujer, W., Siegrist, H., 2000. Calibration and
recycling under highly dynamic influent conditions and validation of Activated Sludge Model No. 3 for Swiss municipal
irregular excess sludge removal. Due to the high phos- wastewater. Water Res. 34 (14), 35803590.
phorus storage in the sludge, decay of PAO during low- Lesjean, B., Gnirss, R., Buisson, H., Keller, S., Tazi-Pain, A., Luck, F.,
loading periods needs to be minimized by reducing the 2005. Outcomes of a 2-year investigation on enhanced
biological P-removal and trace organics in membrane bior-
aeration times to prevent phosphorus loss. The essential
eactor (MBR). Water Sci. Technol. 52 (1011), 453460.
parameter for stable operation is the return sludge ratio. Lopez, C., Pons, M.N., Morgenroth, E., 2006. Endogenous processes
 To prevent a substantial loss of biological activity of the during long-term starvation in activated sludge performing
activated sludge during long zero load (vacation) periods, enhanced biological phosphorus removal. Water Res. 40 (8),
the sludge has to be kept under anaerobic conditions with 15191530.
short daily aeration periods. Bio-P sludge releases the Maurer, M., Boller, M., 1996. Modelling of phosphorus precipita-
tion in wastewater treatment plants with enhanced biological
phosphate anaerobically within 7 d but takes it up again
phosphorus removal. Water Sci. Technol. 39 (1), 147163.
after 24 h of aeration.
Monti, A., Hall, E.R., Dawson, R.N., Husain, H., Kelly, H.G., 2006.
 Distant controlling by Internet and regular servicing of the Comparative study of biological nutrient removal (BNR)
plant by a licensed plant supplier might be the only processes with sedimentation and membrane-based separa-
solution to prevent malfunctioning and low nutrient- tion. Biotechnol. Bioeng. 94 (4), 740752.
removal efficiency of such a small plant. Patel, J., Nakhla, G., 2006. Simultaneous nitrification and deni-
trification with anoxic phosphorus uptake in a membrane
bioreactor system. Water Environ. Res. 78 (11), 21932202.
Rieger, L., Koch, G., Kuehni, M., Gujer, W., Siegrist, H., 2001. The
R E F E R E N C E S
Eawag Bio-P module for activated sludge model no. 3. Water
Res. 35 (16), 38873903.
Siegrist, H., Brunner, I., Koch, G., Phan, L.C., Le, V.C., 1999.
Ahn, K.H., Song, K.G., Cho, E., Cho, J., Yun, H., Lee, S., Kim, J., 2003. Reduction of biomass decay rate under anoxic and anaerobic
Enhanced biological phosphorus and nitrogen removal using a conditions. Water Sci. Technol. 39 (1), 129137.
sequencing anoxic/anaerobic membrane bioreactor (SAM) Trussell, R.S., Merlo, R.P., Hermanowicz, S.W., Jenkins, D., 2006.
process. Desalination 157, 345352. The effect of organic loading on process performance and
Clesceri, L.S., Greenberg, A.E., Eaton, A.D., 1998. Standard membrane fouling in a submerged membrane bioreactor
Methods for the Examination of Water and Wastewater, 20th treating municipal wastewater. Water Res. 40 (14), 26752683.
ed. American Public Health Association/American Water VSA, 2005. Leitfaden Abwasser im landlichen Raum (Wastewater
Works Association/Water Environment Federation, in the Rural Environment). Swiss Water Pollutant Control
Washington, DC, USA. Association, Zurich, Switzerland (in German).
Fane, A.G., Fane, S.A., 2005. The role of membrane technology in Westholm, L.J., 2006. Substrates for phosphorus removalpoten-
sustainable decentralized wastewater systems. Water Sci. tial benefits for on-site wastewater treatment? Water Res. 40
Technol. 51 (10), 317325. (1), 2336.
Flasche, K., 2002. Possible applications and performance of small- Wild, D., Kisliakova, A., Siegrist, H., 1996. P-fixation by Mg, Ca and
scale wastewater treatment plants. Dissertation of the In- zeolite A during stabilization of excess sludge from enhanced
stitute for Urban Water Management and Waste Technology, biological P-removal. Water Sci. Technol. 34 (12), 391398.
University of Hanover (in German). Wilderer, P.A., 2005. UN water action decade: a unique challenge
Green, W., Ho, G., 2005. Small scale sanitation technologies. Water and chance for water engineers. Water Sci. Technol. 51 (8),
Sci. Technol. 51 (10), 2938. 99107.

Você também pode gostar