INFORMEDEAVANCEDEOBRA ING.

RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

INFORMEDEAVANCEDEOBRA
ANLSISCUANTITAIVO


1.DATOSGENERALESDELPROYECTO

CONTRATONo. GG0162017
OBJETODELCONTRATO: CONSTRUCCINDESOLUCIONES
HABITACIONALESENLOSTERRENOS
URBANIZADOSDELREASENTAMIENTONUEVA
CHAMANGA,CANTNMUISNE,PROVINCIADE
ESMERALDAS
CONTRATISTA: CONSTRUCTORACONALBAS.A.
MONTOCONTRATADO: $3200.000,00
PLAZODEEJECUCION: 120DIAS
ANTICIPO50%: $1600.000,00
FECHADEENTREGADELANTICIPO: 27DEMARZO2017
FECHADEACTADEINICIO: 13DEMARZO2017
FECHADETERMINACIN: 10DEJULIO2017
FISCALIZADOR: ING.RAFAELVILLAASTUDILLO

CONTRATONo. GG0172017
OBJETODELCONTRATO: EJECUCINDEOBRASDEURBANIZACINPARAEL
REASENTAMIENTONUEVACHAMANGA,CANTN
MUISNE,PROVINCIADEESMERALDAS
CONTRATISTA: CONSTRUCTORACONALBAS.A.
MONTOCONTRATADO: $3587.110,63
PLAZODEEJECUCION: 120DIAS
ANTICIPO50%: $1793.555,32
FECHADEENTREGADELANTICIPO: 27DEMARZO2017
FECHADEACTADEINICIO: 13DEMARZO2017
FECHADETERMINACIN: 10DEJULIO2017
FISCALIZADOR: ING.RAFAELVILLAASTUDILLO


1
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

2.ANTECEDENTES
LaEmpresaPblicadeDesarrolloEstratgicoEcuadorEstratgicoE.P.(EEEP),representadaporel
Ing. Pablo Ortiz Hidalgo, Gerente General Subrogante, es la encargada de ejecutar las polticas y
programas de desarrollo gubernamental para con la ejecucin de programas de construccin de
infraestructura de obra civil en zonas determinadas por los sectores estratgicos. EEEP contrat la
CONSTRUCCIN DE SOLUCIONES HABITACIONALES EN LOS TERRENOS URBANIZADOS DEL
REASENTAMIENTONUEVACHAMANGA,CANTNMUISNE,PROVINCIADEESMERALDASylaEJECUCIN
DE OBRAS DE URBANIZACIN PARA EL REASENTAMIENTO NUEVA CHAMANGA, CANTN MUISNE,
PROVINCIA DE ESMERALDAS a travs del Formulario de Requerimiento de contrataciones por
Emergencia,defecha13demarzode2017.
EEEP,seencargderealizarelprocesodeseleccindelcontratistaparalaejecucindelosproyectos
antesmencionados;signadosconcdigoNo.COEMEEEP0032017yCOEMEEEP0042017.
ElcontratistaseleccionadofuelaempresaCONSTRUCTORACONALBAS.A.,quiendeberejecutar
elproyecto(ejecucindelosdoscontratosensimultneo)enunplazode120dascontadosapartirdel
13demarzode2017,fechaenlacualsefirmaelFormularioDeRequerimientodeContratacionespor
Emergencia.

3.OBJETODELINFORME
Determinarelavancedeobrarealalafecha,deloscondominios.Sedeberesaltarquedada
lanaturalezadelcontratoelrubroprincipaldelpresupuestodeobraesCONDOMINIOFNIX
(4 DEPARTAMENTOS) y se lo contabiliza por unidades completamente acabadas. Por lo
tanto,parapoderdeterminarunavancerealyglobaldelproyectoserealizaunaponderacin
decadaunodeloscomponentesdeloscondominiosejecutadoshastaelmomento.
Determinarelavancedeobrarealalafecha,delaurbanizacin.
Determinar si el proyecto ser terminado dentro del tiempo establecido; tanto para el
proyectodecondominioscomodelaurbanizacin.

4.DESCRIPCINDELPROYECTO
ELproyectoconsisteenlaconstruccinde320viviendasenunterrenourbanizado,enlazonade
reasentamientodelaNuevaChamanga.Estasunidadesdeviviendasernparabeneficiodelasfamilias
quesufrieronlaprdidatotaldesuscasasarazdelterremotodel16deabrildel2016.Losbeneficiarios
sonseleccionadosmedianteunprocesodeseleccinacargodel MIDUVI.EEPesquien se encargade
ejecutar la construccin de las viviendas a travs del contratista y supervisada por la fiscalizacin
contratadaporEEP.
LasviviendasenconstruccinpasaronporunprocesodediseoquefueaprobadoporelMIDUVI,
quien adems es responsable de determinar las caractersticas tcnicas de cada tipo de vivienda. Es
tambin la entidad encargada de determinar la lista de los beneficiarios para cada vivienda; y de
entregarlademaneraoficialaEEP.
Las viviendas (4 departamentos por condominio) son ejecutadas sobre un terreno que debe ser
urbanizado;yasserfuncionales.Tantoloscondominioscomolaurbanizacinsedetallanacontinuacin:

URBANIZACIN
Obraspreliminares
o Oficinas
o Bodegas


2
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

Movimientodetierras
o Materialgranulargrueso
o Materialgranularfino
Vas
o Veredasybordillos
o Adoquinado
Reddeaguapotable
Pozosdeagua
Cisternadeagua
o Excavacinyrelleno
o Estructura
Reddealcantarillado
o Excavacinyrelleno
o Estructura
Plantadetratamientodeaguasnegras
Instalacioneselctricasytelefnicas
Parquecentralyjuegosdenios


3
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA



CONDOMINIOFNIX(4Departamentos)
Estructuradedosplantasenhormignarmadoycubiertametlica
Plantabajade80M2yplantaaltade80M2total160M2
Tantoenplantabajacomoenplantaaltahaydosdepartamentosde40M2cadauno
Ladistribucinarquitectnicapordepartamentoes:
o Cocina
o SalaComedor
o Baocompleto
o 2habitaciones
Losacabadosson:
o Acabadodepisosenlucidoypintado
o Acabado de paredes interiores resanado, empastado y pintado (pintura de
caucho)
o Acabadodeparedesexterioresresanado, impermeabilizado ypintado(pintura
elastomrica)
o Ventanasdealuminioyvidrio
o PuertastamboradasdeMDFconcerraduras
o Cermicaenbaoycocina(enzonashmedas)
o Aparatossanitarios(incluyepozodelavaplatos)ygrifera


4
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

o Cielorasodevinyl
o Piedradelavarposterior
Laestructurasecomponede:
o Losadecimentacindehormign,conarmaduraderefuerzotantosuperiorcomo
inferior
o Murosportantesdehormign,condoblearmaduraderefuerzo
o Losadeentrepisodehormign,soportadaporlosmurosportantes,conarmadura
derefuerzotantosuperiorcomoinferior
o Cubiertametlicadeperfilesdeacero,contejadefibrocmentoprepintada
o Escalerasdehormignarmadoconpasamanosmetlicosdetubonegropintado
Instalaciones:
o Elctricasinterruptores,iluminacinytomacorrientesde110Vyunode220V
o SanitariastuberadeaguafraydeaguasnegrasenPVC


5
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA


Los condominios son construidos sobre la plataforma generada en el proceso constructivo de la
urbanizacin.
Para la disposicin de los desechos de aguas negras; los condominios se conectan a la red
alcantarillado de la urbanizacin. Las acometidas de agua potable y energa elctrica tambin estn
conectadasalasredesdelaurbanizacin.

5.AVANCEFSICODEOBRA
Elproyectodecondominiostieneunavancefsicodeobraalafechadel48.40%
EnelcuadrodelAnexo1sedetallaelavancefsicodelaobradecondominios.

PROYECTODECONDOMINIOS
No.DEVIVIENDASTOTALES 320
No.DEVIVIENDASCOMPLETASAL100% 40
PORCENTAJE 12.50%
No.DEVIVIENDASENEJECUCIN 240
PORCENTAJE 75.00%
No.DEVIVIENDASCOMPLETASAL70% 96
PORCENTAJE 40.00%
No.DEVIVIENDAS>20%y<50% 48
PORCENTAJE 20.00%
No.DEVIVIENDASAL20% 96
PORCENTAJE 40.00%
No.DEVIVIENDASPORINVERVENIR 40
PORCENTAJE 12.50%

Elproyectodecondominiostieneunavancefsicodeobraalafechadel41.62%
EnelcuadrodelAnexo2sedetallaelavancefsicodelaobradeurbanizacin.

Enconjuntolosdosproyectostienenunavancepromediodel45.01%


6
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

6.AVANCEECONMICO
Unavezrealizadoelanlisisdelavancefsicodelproyectosepuededeterminarelavanceeconmico
delmismo;elcualsedetallaacontinuacin.

PROYECTODECONDOMINIOS
MONTODELCONTRATO $3,200,000.00
MONTOEJECUTADO $1,548,700.00
ANTICIPO50% $1,600,000.00
ANTICIPOPORDEVENGAR $51,300.00
%AVANCEECONMICO(sobrepresupuestocontractual) 48.40%

PROYECTODEURBANIZACIN
MONTODELCONTRATO $3,587,110.63
MONTOEJECUTADO $1,493,095.52
ANTICIPO50% $1,793,555.32
ANTICIPOPORDEVENGAR $300,459.80
%AVANCEECONMICO(sobrepresupuestocontractual) 41.62%

PROYECTOENCONJUNTO
MONTOTOTAL $6,787,110.63
MONTOEJECUTADO $3,041,795.52
ANTICIPOTOTAL(50%) $3,393,555.32
ANTICIPOPORDEVENGAR $351,759.80
%AVANCEECONMICO(sobrepresupuestocontractual) 44.82%

7.ANLISISFINANCIEROYPROYECCINDECOSTOS
A continuacin, se presenta el anlisis financiero del proyecto para obtener el Valor Ganado del
mismohastalafecha.

ParalogrardeterminarelValorGanadodelproyectohastalafecha,secrearondeterminantres
parmetrosfundamentalesqueson:
ValorPlanificado(PV)
ValorEjecutado(EV)
CostoActual(AC)
Estosparmetrossonrelacionadosentresentrescortesdeejecucindelproyecto:
Corte1(Semana2)
Corte2(Semana4)
Corte3(Semana6)
DelasrelacionesestablecidasentrelosparmetrosseobtienenlasVariacionesdelproyectoen:
VariacindelCronograma(SV)
VariacindelCosto(CV)


7
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

As tambin de las relaciones establecidas entre los parmetros se obtienen los ndices de
DesempeodelaGestindelValorGanadoEVMquenospermitendeterminarlaeficienciadelproyecto
realconelproyectoplanificado.
ndicedelDesempeodelCronograma(SPI)
ndicedelDesempeodelCosto(CPI)

Nota.SedebetomarencuentaqueparaelpresenteanlisiselCostoActual(AC)noeselcosto
real que le representa al constructor ejecutar un rubro a travs de su APU (ya que esa
informacinesinternadelcontratistaynoestdisponible).ParaelpresenteanlisiselACselo
determina como el costo inicial de cada rubro afectado tanto por la variacin en tiempo de
ejecucindelrubrocomoenlavariacindecantidadesrealesejecutadas.

VALORPLANIFICADO
VALORPLANIFICADOPORCORTESPV
TOTAL CORTE1SEMANA2 CORTE2SEMANA4 CORTE3SEMANA6
COD. CONCEPTO
CONTRACTUAL CANTIDAD VALOR CANTIDAD VALOR CANTIDAD VALOR

1 PRELIMINARES $318,020.60 13.39% $42,598.07 32.59% $103,649.68 57.59% $183,154.83


2 MOVIMIENTODETIERRA $1,103,290.63 32.76% $361,484.53 61.86% $682,492.75 87.29% $963,024.66
3 OBRACIVIL $583,262.54 0.00% $0.00 12.50% $72,907.82 37.50% $218,723.45
4 REDDEAGUAPOTABLE $161,873.06 34.11% $55,213.82 63.37% $102,583.81 87.79% $142,109.98
5 POZOSDEAGUA $126,726.72 0.00% $0.00 25.00% $31,681.68 75.00% $95,045.04
6 CISTERNA $117,464.55 0.00% $0.00 25.00% $29,366.14 75.00% $88,098.41
7 REDDEALCANTARILLADOSANITARIO $247,019.01 22.77% $56,240.76 50.61% $125,025.61 83.54% $206,354.54
8 PLANTADETRATAMIENTOAASS $196,454.56 0.00% $0.00 25.00% $49,113.64 75.00% $147,340.92
9 REDDEALCANTARILLADOPLUVIAL $69,168.59 0.00% $0.00 25.00% $17,292.15 75.00% $51,876.44
10 REDELECTRICADEMEDIATENSIONYBAJATENSION $485,581.80 0.00% $0.00 0.00% $0.00 0.00% $0.00
11 CANALIZACIONTELEFONICA $47,613.34 0.00% $0.00 0.00% $0.00 0.00% $0.00
12 VARIOS $71,981.97 0.00% $0.00 0.00% $0.00 0.00% $0.00
13 AMBIENTALES $58,653.26 10.88% $6,384.17 31.27% $18,340.01 61.15% $35,867.51

$3,587,110.63 $521,921.35 $1,232,453.28 $2,131,595.79



VALOREJECUTADO
VALOREJECUTADOPORCORTESEV
TOTAL CORTE1SEMANA2 CORTE2SEMANA4 CORTE3SEMANA6
COD. CONCEPTO
CONTRACTUAL CANTIDAD VALOR CANTIDAD VALOR CANTIDAD VALOR

1 PRELIMINARES $318,020.60 40.18% $127,780.68 40.18% $127,780.68 40.18% $127,780.68


2 MOVIMIENTODETIERRA $1,103,290.63 8.30% $91,583.27 42.28% $466,522.03 77.26% $852,372.68
3 OBRACIVIL $583,262.54 0.00% $0.00 0.86% $4,995.50 3.74% $21,827.20
4 REDDEAGUAPOTABLE $161,873.06 6.50% $10,521.75 24.29% $39,318.97 44.44% $71,936.99
5 POZOSDEAGUA $126,726.72 2.45% $3,104.80 14.70% $18,628.83 36.75% $46,572.07
6 CISTERNA $117,464.55 0.00% $0.00 22.11% $25,968.76 56.24% $66,062.06
7 REDDEALCANTARILLADOSANITARIO $247,019.01 1.14% $2,816.02 13.36% $33,001.74 44.44% $109,775.25
8 PLANTADETRATAMIENTOAASS $196,454.56 0.00% $0.00 2.14% $4,198.75 6.76% $13,272.62
9 REDDEALCANTARILLADOPLUVIAL $69,168.59 1.14% $788.52 13.36% $9,240.92 44.44% $30,738.52
10 REDELECTRICADEMEDIATENSIONYBAJATENSION $485,581.80 0.00% $0.00 6.58% $31,951.28 16.62% $80,703.70
11 CANALIZACIONTELEFONICA $47,613.34 0.00% $0.00 12.56% $5,980.24 28.32% $13,484.10
12 VARIOS $71,981.97 0.00% $0.00 0.00% $0.00 0.00% $0.00
13 AMBIENTALES $58,653.26 100.00% $58,653.26 100.00% $58,653.26 100.00% $58,653.26

$3,587,110.63 $295,248.30 $826,240.95 $1,493,179.13




8
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

COSTOACTUAL
COSTOACTUALPORCORTESAC
TOTAL CORTE1SEMANA2 CORTE2SEMANA4 CORTE3SEMANA6
COD. CONCEPTO
CONTRACTUAL CANTIDAD VALOR CANTIDAD VALOR CANTIDAD VALOR

1 PRELIMINARES $318,020.60 40.18% $127,780.68 40.18% $127,780.68 40.18% $127,780.68


2 MOVIMIENTODETIERRA $1,103,290.63 8.30% $89,751.61 42.28% $457,191.59 77.26% $835,325.23
3 OBRACIVIL $583,262.54 0.00% $0.00 0.86% $4,745.73 3.74% $20,735.84
4 REDDEAGUAPOTABLE $161,873.06 6.50% $9,995.66 24.29% $37,353.02 44.44% $68,340.14
5 POZOSDEAGUA $126,726.72 2.45% $3,415.29 14.70% $20,491.71 36.75% $51,229.28
6 CISTERNA $117,464.55 0.00% $0.00 22.11% $28,565.63 56.24% $72,668.27
7 REDDEALCANTARILLADOSANITARIO $247,019.01 1.14% $2,675.22 13.36% $31,351.65 44.44% $104,286.49
8 PLANTADETRATAMIENTOAASS $196,454.56 0.00% $0.00 2.14% $4,324.71 6.76% $13,670.80
9 REDDEALCANTARILLADOPLUVIAL $69,168.59 1.14% $709.67 13.36% $8,316.83 44.44% $27,664.67
10 REDELECTRICADEMEDIATENSIONYBAJATENSION $485,581.80 0.00% $0.00 6.58% $35,146.41 16.62% $88,774.06
11 CANALIZACIONTELEFONICA $47,613.34 0.00% $0.00 12.56% $6,578.26 28.32% $14,832.51
12 VARIOS $71,981.97 0.00% $0.00 0.00% $0.00 0.00% $0.00
13 AMBIENTALES $58,653.26 100.00% $52,787.93 100.00% $52,787.93 100.00% $52,787.93

$3,587,110.63 $287,116.05 $814,634.16 $1,478,095.90



VALORGANADOCORTE1(semana2)
VALORGANADO
TABLADESEGUIMIENTO

OBRA: URBANIZACINCHAMANGA MONTOPV: $521,921.35 CV: $8,132.25


UBICACIN: Chamanga,ProvinciadeEsmeraldas MONTOEV: $287,116.05 SV: $226,673.04
CONTRATISTA: CONALBAS.A. MONTOAC: $295,248.30
CORTENo. 1 FECHA: 27Mar17

PV AC EV
COD. RUBRO CV SV CPI SPI
USD USD USD
1 PRELIMINARES $42,598.07 $127,780.68 $127,780.68 $0.00 $85,182.61 1.000 3.000
2 MOVIMIENTODETIERRA $361,484.53 $89,751.61 $91,583.27 $1,831.67 $269,901.25 1.020 0.253
3 OBRACIVIL $ $ $ $0.00 $0.00 NOAC NOPV
4 REDDEAGUAPOTABLE $55,213.82 $9,995.66 $10,521.75
5 POZOSDEAGUA $ $3,415.29 $3,104.80 $310.48 $3,104.80 0.909 NOPV
6 CISTERNA $ $ $ $0.00 $0.00 NOAC NOPV
7 REDDEALCANTARILLADOSANITARIO $56,240.76 $2,675.22 $2,816.02 $140.80 $53,424.74 1.053 0.050
8 PLANTADETRATAMIENTOAASS $ $ $ $0.00 $0.00 NOAC NOPV
9 REDDEALCANTARILLADOPLUVIAL $ $709.67 $788.52 $78.85 $788.52 1.111 NOPV
10 REDELECTRICADEMEDIATENSIONYBAJATENSION $ $ $ $0.00 $0.00 NOAC NOPV
11 CANALIZACIONTELEFONICA $ $ $ $0.00 $0.00 NOAC NOPV
12 VARIOS $ $ $ $0.00 $0.00 NOAC NOPV
13 AMBIENTALES $6,384.17 $52,787.93 $58,653.26 $5,865.33 $52,269.09 1.111 9.187
TOTALES $521,921.35 $287,116.05 $295,248.30 $8,132.25 $226,673.04 1.028 0.566

VALORGANADO CORTE1
$1,600,000
$1,400,000
$1,200,000
$1,000,000
MONTO

$800,000 $521,921.35

$600,000
$400,000 $295,248.30

$200,000 $287,116.05
$0
0 1 2 3 4
TIEMPO (SEMANAS)

LNEABASE EV AC PV



9
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

VALORGANADOCORTE2(semana4)
VALORGANADO
TABLADESEGUIMIENTO

OBRA: URBANIZACINCHAMANGA MONTOPV: $1,232,453.28 CV: $11,606.80


UBICACIN: Chamanga,ProvinciadeEsmeraldas MONTOEV: $814,634.16 SV: $406,212.32
CONTRATISTA: CONALBAS.A. MONTOAC: $826,240.95
CORTENo. 2 FECHA: 10Apr17

PV AC EV
COD. RUBRO CV SV CPI SPI
USD USD USD
1 PRELIMINARES $103,649.68 $127,780.68 $127,780.68 $0.00 $24,131.00 1.000 1.233
2 MOVIMIENTODETIERRA $682,492.75 $457,191.59 $466,522.03 $9,330.44 $215,970.72 1.020 0.684
3 OBRACIVIL $72,907.82 $4,745.73 $4,995.50 $249.78 $67,912.31 1.053 0.069
4 REDDEAGUAPOTABLE $102,583.81 $37,353.02 $39,318.97
5 POZOSDEAGUA $31,681.68 $20,491.71 $18,628.83 $1,862.88 $13,052.85 0.909 0.588
6 CISTERNA $29,366.14 $28,565.63 $25,968.76 $2,596.88 $3,397.38 0.909 0.884
7 REDDEALCANTARILLADOSANITARIO $125,025.61 $31,351.65 $33,001.74 $1,650.09 $92,023.87 1.053 0.264
8 PLANTADETRATAMIENTOAASS $49,113.64 $4,324.71 $4,198.75 $125.96 $44,914.89 0.971 0.085
9 REDDEALCANTARILLADOPLUVIAL $17,292.15 $8,316.83 $9,240.92 $924.09 $8,051.22 1.111 0.534
10 REDELECTRICADEMEDIATENSIONYBAJATENSION $ $35,146.41 $31,951.28 $3,195.13 $31,951.28 0.909 NOPV
11 CANALIZACIONTELEFONICA $ $6,578.26 $5,980.24 $598.02 $5,980.24 0.909 NOPV
12 VARIOS $ $ $ $0.00 $0.00 NOAC NOPV
13 AMBIENTALES $18,340.01 $52,787.93 $58,653.26 $5,865.33 $40,313.25 1.111 3.198
TOTALES $1,232,453.28 $814,634.16 $826,240.95 $11,606.80 $406,212.32 1.014 0.670

VALORGANADO CORTE2
$2,000,000
$1,800,000
$1,600,000 $1,232,453.28
$1,400,000
$1,200,000
MONTO

$1,000,000 $814,634.16
$800,000
$600,000
$400,000 $826,240.95

$200,000
$0
0 1 2 3 4 5
TIEMPO (SEMANAS)

LNEABASE EV AC PV



VALORGANADOCORTE3(semana6)
VALORGANADO
TABLADESEGUIMIENTO

OBRA: URBANIZACINCHAMANGA MONTOPV: $2,131,595.79 CV: $15,083.23


UBICACIN: Chamanga,ProvinciadeEsmeraldas MONTOEV: $1,478,095.90 SV: $638,416.65
CONTRATISTA: CONALBAS.A. MONTOAC: $1,493,179.13
CORTENo. 3 FECHA: 24Apr17

PV AC EV
COD. RUBRO CV SV CPI SPI
USD USD USD
1 PRELIMINARES $183,154.83 $127,780.68 $127,780.68 $0.00 $55,374.15 1.000 0.698
2 MOVIMIENTODETIERRA $963,024.66 $835,325.23 $852,372.68 $17,047.45 $110,651.98 1.020 0.885
3 OBRACIVIL $218,723.45 $20,735.84 $21,827.20 $1,091.36 $196,896.25 1.053 0.100
4 REDDEAGUAPOTABLE $142,109.98 $68,340.14 $71,936.99
5 POZOSDEAGUA $95,045.04 $51,229.28 $46,572.07 $4,657.21 $48,472.97 0.909 0.490
6 CISTERNA $88,098.41 $72,668.27 $66,062.06 $6,606.21 $22,036.35 0.909 0.750
7 REDDEALCANTARILLADOSANITARIO $206,354.54 $104,286.49 $109,775.25 $5,488.76 $96,579.29 1.053 0.532
8 PLANTADETRATAMIENTOAASS $147,340.92 $13,670.80 $13,272.62 $398.18 $134,068.30 0.971 0.090
9 REDDEALCANTARILLADOPLUVIAL $51,876.44 $27,664.67 $30,738.52 $3,073.85 $21,137.92 1.111 0.593
10 REDELECTRICADEMEDIATENSIONYBAJATENSION $ $88,774.06 $80,703.70 $8,070.37 $80,703.70 0.909 NOPV
11 CANALIZACIONTELEFONICA $ $14,832.51 $13,484.10 $1,348.41 $13,484.10 0.909 NOPV
12 VARIOS $ $ $ $0.00 $0.00 NOAC NOPV
13 AMBIENTALES $35,867.51 $52,787.93 $58,653.26 $5,865.33 $22,785.75 1.111 1.635
TOTALES $2,131,595.79 $1,478,095.90 $1,493,179.13 $15,083.23 $638,416.65 1.010 0.700


10
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

VALORGANADO CORTE3
$3,000,000
$2,131,595.79
$2,500,000

$2,000,000
$1,493,179.13
MONTO

$1,500,000

$1,000,000
$1,478,095.90
$500,000

$0
0 1 2 3 4 5 6 7
TIEMPO (SEMANAS)

LNEABASE EV AC PV

15.CONCLUSIONESYRECOMENDACIONES
ParalafechaactualelCPIreflejaunvalorde1.01loqueindicaqueelcostodelproyectoactual
esmenorqueelcostoplanificado.
ParalafechaactualelSPIreflejaunvalorde0.70loqueindicaqueelcronogramadelproyecto
actualestretrasadocomparadoconelcronogramaplanificado.
Sibienesciertoqueexisteunretrasofrentealcronogramaplanificado,estonoquieredecirque
elproyectosevayaaalargarmsalldeltiempocontractual,yaqueelcronogramaplanificado
esmuyambiciosoypretendeterminarlaobraenuntiempode78das(65%deltiempototal).
EsnecesariogestionareltemadelaelectrificacindelaurbanizacinconpersonaldeCENELpara
notenerretrasoseneserubroenunfuturocercano,yastenerlasviviendascompletamente
habilitadas.

Chamanga,25deabril2017

__________________________
Ing.RafaelVillaAstudillo,MDI
Fiscalizador


11
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

PROYECTO:CONSTRUCCINDEVIVIENDASOCIALENSANJOSDECHAMANGA
ANEXO1CUADRODETALLADODEAVANCEDEOBRA
CONTRATO:CONDOMINIOS
FECHA: 24deabril2017 ELABORADOPOR: ING.RAFAELVILLAASTUDILLO
MONTO: $3,200,000.00 REVISADOPOR: ARQ.JUANFRANSICOESTVEZ

AVANCEDEOBRA
CIMENTACIN Estructura Acabados Instalaciones
UBICACIN CANTIDAD
20% 50% 25.00% 5.00%
TOTAL OBSERVACIONES
5.00% 15.00% 11.25% 11.25% 11.25% 11.25% 5.00% 4.50% 4.50% 1.25% 1.25% 4.50% 4.50% 4.50% 2.50% 2.50% CONDOMINIO
Pintura Pintura Inst. Inst.
MANZANA ID Usuario PlantaBaja PlantaAlta Replanteo Cimentacin ArmaduraPB ArmaduraPA HormignPB HormignPA Cubierta Puertas Ventanas Cermica Pasamanos CieloRaso
Exterior Interior Elctricas Sanitarias

C1 CONDOMINIO1 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 100.00%
C2 CONDOMINIO2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 100.00%
C3 CONDOMINIO3 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 100.00%
C4 CONDOMINIO4 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 100.00%
C5 CONDOMINIO5 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 100.00%
MANZANA
C6 CONDOMINIO6 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 100.00%
1
C7 CONDOMINIO7 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 100.00%
C8 CONDOMINIO8 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 100.00%
C9 CONDOMINIO9 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 100.00%
C10 CONDOMINIO10 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 100.00%
C80 CONDOMINIO11 2 2 0.00%

SUBTOTAL 22 22 0.6250% 1.8750% 1.4063% 1.4063% 1.4063% 1.4063% 0.6250% 0.5625% 0.5625% 0.1563% 0.1563% 0.5625% 0.5625% 0.5625% 0.3125% 0.3125% 90.91%

AVANCEDEOBRA
CIMENTACIN Estructura Acabados Instalaciones
UBICACIN CANTIDAD
20% 50% 25.00% 5.00%
TOTAL OBSERVACIONES
5.00% 15.00% 11.25% 11.25% 11.25% 11.25% 5.00% 4.50% 4.50% 1.25% 1.25% 4.50% 4.50% 4.50% 2.50% 2.50%
CONDOMINIO
Pintura Pintura Inst. Inst.
MANZANA ID Usuario PlantaBaja PlantaAlta Replanteo Cimentacin ArmaduraPB ArmaduraPA HormignPB HormignPA Cubierta Puertas Ventanas Cermica Pasamanos CieloRaso
Exterior Interior Elctricas Sanitarias

C11 CONDOMINIO1 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 91.00%


C12 CONDOMINIO2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 91.00%
C13 CONDOMINIO3 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 91.00%
C14 CONDOMINIO4 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 91.00%
C15 CONDOMINIO5 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 91.00%
MANZANA C16 CONDOMINIO6 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 91.00%
2 C17 CONDOMINIO7 2 2 1 1 1 1 1 1 1 1 1 1 1 1 85.25%
C18 CONDOMINIO8 2 2 1 1 1 1 1 1 1 1 1 1 1 1 85.25%
C19 CONDOMINIO9 2 2 1 1 1 1 1 1 1 1 1 1 1 1 85.25%
C20 CONDOMINIO10 2 2 1 1 1 1 1 1 1 1 1 1 1 77.50%
C21 CONDOMINIO11 2 2 1 1 1 1 1 1 1 1 1 1 1 77.50%
C22 CONDOMINIO12 2 2 1 1 1 1 1 1 1 1 1 1 1 77.50%

SUBTOTAL 24 24 0.75% 2.25% 1.69% 1.69% 1.69% 1.69% 0.75% 0.51% 0.51% 0.19% 0.14% 0.34% 0.00% 0.00% 0.38% 0.38% 86.19%

AVANCEDEOBRA
CIMENTACIN Estructura Acabados Instalaciones
UBICACIN CANTIDAD
20% 50% 25.00% 5.00%
TOTAL OBSERVACIONES
5.00% 15.00% 11.25% 11.25% 11.25% 11.25% 5.00% 4.50% 4.50% 1.25% 1.25% 4.50% 4.50% 4.50% 2.50% 2.50%
CONDOMINIO
Pintura Pintura Inst. Inst.
MANZANA ID Usuario PlantaBaja PlantaAlta Replanteo Cimentacin ArmaduraPB ArmaduraPA HormignPB HormignPA Cubierta Puertas Ventanas Cermica Pasamanos CieloRaso
Exterior Interior Elctricas Sanitarias

C23 CONDOMINIO1 2 2 1 1 1 1 1 1 1 70.00%


C24 CONDOMINIO2 2 2 1 1 1 1 1 1 1 70.00%
C25 CONDOMINIO3 2 2 1 1 1 1 1 1 65.00%
C26 CONDOMINIO4 2 2 1 1 1 1 1 1 65.00%
C27 CONDOMINIO5 2 2 1 1 1 1 1 1 65.00%
MANZANA C28 CONDOMINIO6 2 2 1 1 1 1 1 1 1 70.00%
3 C29 CONDOMINIO7 2 2 1 1 1 1 1 1 1 70.00%
C30 CONDOMINIO8 2 2 1 1 1 1 1 1 1 70.00%
C31 CONDOMINIO9 2 2 1 1 1 1 1 1 1 70.00%
C32 CONDOMINIO10 2 2 1 1 1 1 1 1 1 70.00%
C33 CONDOMINIO11 2 2 1 1 1 1 1 1 1 70.00%
C34 CONDOMINIO12 2 2 1 1 1 1 1 1 1 70.00%

SUBTOTAL 24 24 0.75% 2.25% 1.69% 1.69% 1.69% 1.69% 0.56% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 68.75%

A1|1de3
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

PROYECTO:CONSTRUCCINDEVIVIENDASOCIALENSANJOSDECHAMANGA
ANEXO1CUADRODETALLADODEAVANCEDEOBRA
CONTRATO:CONDOMINIOS
FECHA: 24deabril2017 ELABORADOPOR: ING.RAFAELVILLAASTUDILLO
MONTO: $3,200,000.00 REVISADOPOR: ARQ.JUANFRANSICOESTVEZ

AVANCEDEOBRA
CIMENTACIN Estructura Acabados Instalaciones
UBICACIN CANTIDAD
20% 50% 25.00% 5.00%
TOTAL OBSERVACIONES
5.00% 15.00% 11.25% 11.25% 11.25% 11.25% 5.00% 4.50% 4.50% 1.25% 1.25% 4.50% 4.50% 4.50% 2.50% 2.50%
CONDOMINIO
Pintura Pintura Inst. Inst.
MANZANA ID Usuario PlantaBaja PlantaAlta Replanteo Cimentacin ArmaduraPB ArmaduraPA HormignPB HormignPA Cubierta Puertas Ventanas Cermica Pasamanos CieloRaso
Exterior Interior Elctricas Sanitarias

C35 CONDOMINIO1 2 2 1 1 1 1 1 1 65.00%


C36 CONDOMINIO2 2 2 1 1 1 1 1 1 65.00%
C37 CONDOMINIO3 2 2 1 1 1 1 1 1 65.00%
C38 CONDOMINIO4 2 2 1 1 1 1 1 1 65.00%
C39 CONDOMINIO5 2 2 1 1 1 1 42.50%
MANZANA C40 CONDOMINIO6 2 2 1 1 1 1 1 1 65.00%
4 C41 CONDOMINIO7 2 2 1 1 1 1 1 1 65.00%
C42 CONDOMINIO8 2 2 1 1 1 1 1 53.75%
C43 CONDOMINIO9 2 2 1 1 1 1 42.50%
C44 CONDOMINIO10 2 2 1 1 1 31.25%
C45 CONDOMINIO11 2 2 1 1 1 31.25%
C46 CONDOMINIO12 2 2 1 1 1 31.25%

SUBTOTAL 24 24 0.75% 2.25% 1.69% 1.13% 1.13% 0.84% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 51.88%

AVANCEDEOBRA
CIMENTACIN Estructura Acabados Instalaciones
UBICACIN CANTIDAD
20% 50% 25.00% 5.00%
TOTAL OBSERVACIONES
5.00% 15.00% 11.25% 11.25% 11.25% 11.25% 5.00% 4.50% 4.50% 1.25% 1.25% 4.50% 4.50% 4.50% 2.50% 2.50%
CONDOMINIO
Pintura Pintura Inst. Inst.
MANZANA ID Usuario PlantaBaja PlantaAlta Replanteo Cimentacin ArmaduraPB ArmaduraPA HormignPB HormignPA Cubierta Puertas Ventanas Cermica Pasamanos CieloRaso
Exterior Interior Elctricas Sanitarias

C47 CONDOMINIO1 2 2 1 1 20.00%


C48 CONDOMINIO2 2 2 1 1 20.00%
C49 CONDOMINIO3 2 2 1 1 20.00%
C50 CONDOMINIO4 2 2 1 1 20.00%
C51 CONDOMINIO5 2 2 1 1 20.00%
MANZANA C52 CONDOMINIO6 2 2 1 1 20.00%
5 C53 CONDOMINIO7 2 2 1 1 20.00%
C54 CONDOMINIO8 2 2 1 1 20.00%
C55 CONDOMINIO9 2 2 1 1 20.00%
C56 CONDOMINIO10 2 2 1 1 20.00%
C57 CONDOMINIO11 2 2 1 1 20.00%
C58 CONDOMINIO12 2 2 1 1 20.00%

SUBTOTAL 24 24 0.75% 2.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 20.00%

AVANCEDEOBRA
CIMENTACIN Estructura Acabados Instalaciones
UBICACIN CANTIDAD
20% 50% 25.00% 5.00%
TOTAL OBSERVACIONES
5.00% 15.00% 11.25% 11.25% 11.25% 11.25% 5.00% 4.50% 4.50% 1.25% 1.25% 4.50% 4.50% 4.50% 2.50% 2.50%
CONDOMINIO
Pintura Pintura Inst. Inst.
MANZANA ID Usuario PlantaBaja PlantaAlta Replanteo Cimentacin ArmaduraPB ArmaduraPA HormignPB HormignPA Cubierta Puertas Ventanas Cermica Pasamanos CieloRaso
Exterior Interior Elctricas Sanitarias

C59 CONDOMINIO1 2 2 1 1 20.00%


C60 CONDOMINIO2 2 2 1 1 20.00%
C61 CONDOMINIO3 2 2 1 1 20.00%
C62 CONDOMINIO4 2 2 1 1 20.00%
C63 CONDOMINIO5 2 2 1 1 20.00%
MANZANA C64 CONDOMINIO6 2 2 1 1 20.00%
6 C65 CONDOMINIO7 2 2 1 5.00%
C66 CONDOMINIO8 2 2 1 5.00%
C67 CONDOMINIO9 2 2 1 5.00%
C68 CONDOMINIO10 2 2 1 5.00%
C69 CONDOMINIO11 2 2 1 5.00%
C70 CONDOMINIO12 2 2 1 5.00%

SUBTOTAL 24 24 0.75% 1.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.50%

A1|2de3
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

PROYECTO:CONSTRUCCINDEVIVIENDASOCIALENSANJOSDECHAMANGA
ANEXO1CUADRODETALLADODEAVANCEDEOBRA
CONTRATO:CONDOMINIOS
FECHA: 24deabril2017 ELABORADOPOR: ING.RAFAELVILLAASTUDILLO
MONTO: $3,200,000.00 REVISADOPOR: ARQ.JUANFRANSICOESTVEZ

AVANCEDEOBRA
CIMENTACIN Estructura Acabados Instalaciones
UBICACIN CANTIDAD
20% 50% 25.00% 5.00%
TOTAL OBSERVACIONES
5.00% 15.00% 11.25% 11.25% 11.25% 11.25% 5.00% 4.50% 4.50% 1.25% 1.25% 4.50% 4.50% 4.50% 2.50% 2.50%
CONDOMINIO
Pintura Pintura Inst. Inst.
MANZANA ID Usuario PlantaBaja PlantaAlta Replanteo Cimentacin ArmaduraPB ArmaduraPA HormignPB HormignPA Cubierta Puertas Ventanas Cermica Pasamanos CieloRaso
Exterior Interior Elctricas Sanitarias

C71 CONDOMINIO1 2 2 0.00%


C72 CONDOMINIO2 2 2 0.00%
MANZANA C73 CONDOMINIO3 2 2 0.00%
7 C74 CONDOMINIO4 2 2 0.00%
C75 CONDOMINIO5 2 2 0.00%
C76 CONDOMINIO6 2 2 0.00%

SUBTOTAL 12 12 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

AVANCEDEOBRA
CIMENTACIN Estructura Acabados Instalaciones
UBICACIN CANTIDAD
20% 50% 25.00% 5.00%
TOTAL OBSERVACIONES
5.00% 15.00% 11.25% 11.25% 11.25% 11.25% 5.00% 4.50% 4.50% 1.25% 1.25% 4.50% 4.50% 4.50% 2.50% 2.50%
CONDOMINIO
Pintura Pintura Inst. Inst.
MANZANA ID Usuario PlantaBaja PlantaAlta Replanteo Cimentacin ArmaduraPB ArmaduraPA HormignPB HormignPA Cubierta Puertas Ventanas Cermica Pasamanos CieloRaso
Exterior Interior Elctricas Sanitarias

C77 CONDOMINIO1 2 2 0.00%


MANZANA
C78 CONDOMINIO2 2 2 0.00%
8
C79 CONDOMINIO3 2 2 0.00%

SUBTOTAL 6 6 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

AVANCEGLOBAL 160 160 4.38% 12.00% 6.47% 5.91% 5.91% 5.63% 1.94% 1.07% 1.07% 0.34% 0.30% 0.90% 0.56% 0.56% 0.69% 0.69% 48.40%
TOTALVIVIENDAS 320 16.38% 25.84% 4.80% 1.38% OK

A1|3de3
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

PROYECTO:CONSTRUCCINDEVIVIENDASOCIALENSANJOSDECHAMANGA
ANEXO2CUADRODETALLADODEAVANCEDEOBRA
CONTRATO:URBANIZACIN

MONTOCONTRATO: ########### FECHA: 24deabril2017 ELABORADOPOR: ING.RAFAELVILLAASTUDILLO REVISADOPOR: ARQ.JUANFRANSICOESTVEZ

AVANCEDEOBRA
DESCRIPCION PRELIMINAR MOVIMIENTODETIERRA OBRACIVIL REDAGUAPOTABLE POZODEAGUA CISTERNA ALCANTARILLADO PLANTADETRATAMIENTO INST.ELECT.YTELEF. VARIOS
8.87% 30.76% 16.26% 4.51% 3.53% 3.27% 8.81% 5.48% 14.87% 3.64% OBSERVACIONES
RELLENO ESTUDIOY BOMBASY EQUIPOSDE TOTALAVANCE
SEMANA CAMPAMENTO CERRAMIENTO RELLENOPIEDRA BORDILLOS ACERAS BASE ADOQUIN CANCHA EXCAVACIN RELLENO TUBERIA HORMIGON ACERO PLUVIAL SANITARIO HORMIGON ACERO ELECTRICAS TELEFONICAS JARDINES KITSEGURIDAD
AO MES MEJORAMIENTO PERFORACION TUBERIA BOMBEO
DESDE HASTA 40.18% 59.82% 55.76% 44.24% 13.67% 12.05% 26.55% 35.83% 11.90% 7.85% 9.36% 82.79% 49.00% 51.00% 34.53% 21.71% 43.76% 21.88% 78.12% 60.78% 39.22% 91.07% 8.93% 55.10% 44.90%

2017 MAR. 13 19 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0500 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 1.0000 5.28%
2017 MAR. 20 26 1.0000 0.0000 0.0850 0.0805 0.0000 0.0000 0.0000 0.0000 0.0000 0.0650 0.0650 0.0650 0.0500 0.0000 0.0000 0.0000 0.0000 0.0114 0.0114 0.0000 0.0000 0.0000 0.0000 0.0000 1.0000 8.23%
2017 MAR./ABR. 27 2 1.0000 0.0000 0.2589 0.2454 0.0000 0.0000 0.0000 0.0000 0.0000 0.1540 0.1540 0.1540 0.1000 0.0000 0.0836 0.0836 0.0000 0.0930 0.0930 0.0000 0.0000 0.0258 0.0100 0.0000 1.0000 15.18%
2017 ABR. 3 9 1.0000 0.0000 0.4328 0.4103 0.0333 0.0333 0.0000 0.0000 0.0000 0.2429 0.2429 0.2429 0.3000 0.0000 0.4510 0.3010 0.0000 0.1336 0.1336 0.0029 0.0500 0.0658 0.1256 0.0000 1.0000 23.03%
2017 ABR. 10 16 1.0000 0.0000 0.6067 0.5751 0.0670 0.0670 0.0000 0.0000 0.0000 0.3318 0.3318 0.3318 0.5000 0.0000 0.7615 0.6540 0.0000 0.2672 0.2672 0.0338 0.0550 0.0981 0.0178 0.0000 1.0000 31.33%
2017 ABR. 17 23 1.0000 0.0000 0.7908 0.7496 0.1455 0.1455 0.0000 0.0000 0.0000 0.4444 0.4444 0.4444 0.7500 0.0000 1.0000 1.0000 0.0000 0.4444 0.4444 0.0676 0.0675 0.1662 0.2832 0.0000 1.0000 41.62%
2017 ABR. 24 30 0.00%
2017 MAY. 1 7 0.00%
2017 MAY. 8 14 0.00%
2017 MAY. 15 21 0.00%
2017 MAY. 22 28 0.00%
2017 MAY./JUN. 29 4 0.00%

A2|1de1
INFORMEDEAVANCEDEOBRA ING.RAFAELVILLAASTUDILLO
PROYECTOCHAMANGA

VALORPLANIFICADOPV
CRONOGRAMAVALORADOPORCAPTULOS

COD. DESCRIPCIONDERUBROS TOTAL(USD) MARZO ABRIL MAYO JUNIO JULIO


SEMANA1 SEMANA2 SEMANA3 SEMANA4 SEMANA5 SEMANA6 SEMANA7 SEMANA8 SEMANA9 SEMANA10 SEMANA11 SEMANA12 SEMANA13 SEMANA14 SEMANA15 SEMANA16 SEMANA17

1 PRELIMINARES $318,020.60 $21,299.03 $21,299.03 $21,299.03 $39,752.58 $39,752.58 $39,752.58 $39,752.58 $19,022.64 $19,022.64 $19,022.64 $19,022.64 $19,022.64 $0.00 $0.00 $0.00 $0.00 $0.00
2 MOVIMIENTODETIERRA $1,103,290.63 $180,742.26 $180,742.26 $180,742.26 $140,265.96 $140,265.96 $140,265.96 $140,265.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
3 OBRACIVIL $583,262.54 $0.00 $0.00 $0.00 $72,907.82 $72,907.82 $72,907.82 $72,907.82 $58,326.25 $58,326.25 $58,326.25 $58,326.25 $58,326.25 $0.00 $0.00 $0.00 $0.00 $0.00
4 REDDEAGUAPOTABLE $161,873.06 $27,606.91 $27,606.91 $27,606.91 $19,763.08 $19,763.08 $19,763.08 $19,763.08 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
5 POZOSDEAGUA $126,726.72 $0.00 $0.00 $0.00 $31,681.68 $31,681.68 $31,681.68 $31,681.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6 CISTERNA $117,464.55 $0.00 $0.00 $0.00 $29,366.14 $29,366.14 $29,366.14 $29,366.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7 REDDEALCANTARILLADOSANITARIO $247,019.01 $28,120.38 $28,120.38 $28,120.38 $40,664.47 $40,664.47 $40,664.47 $40,664.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
8 PLANTADETRATAMIENTOAASS $196,454.56 $0.00 $0.00 $0.00 $49,113.64 $49,113.64 $49,113.64 $49,113.64 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
9 REDDEALCANTARILLADOPLUVIAL $69,168.59 $0.00 $0.00 $0.00 $17,292.15 $17,292.15 $17,292.15 $17,292.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
10 REDELECTRICADEMEDIATENSIONYBAJATENSION $485,581.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $97,116.36 $97,116.36 $97,116.36 $97,116.36 $97,116.36 $0.00 $0.00 $0.00 $0.00 $0.00
11 CANALIZACIONTELEFONICA $47,613.34 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $5,099.89 $5,099.89 $5,099.89 $5,099.89 $5,099.89 $5,528.48 $5,528.48 $5,528.48 $5,528.48 $0.00
12 VARIOS $71,981.97 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $8,997.75 $8,997.75 $8,997.75 $8,997.75 $35,990.99
13 AMBIENTALES $58,653.26 $3,192.09 $3,192.09 $3,192.09 $8,763.75 $8,763.75 $8,763.75 $8,763.75 $2,804.40 $2,804.40 $2,804.40 $2,804.40 $2,804.40 $0.00 $0.00 $0.00 $0.00 $0.00

INVERSIONMENSUAL $260,960.67 $260,960.67 $260,960.67 $449,571.26 $449,571.26 $449,571.26 $449,571.26 $182,369.54 $182,369.54 $182,369.54 $182,369.54 $182,369.54 $14,526.22 $14,526.22 $14,526.22 $14,526.22 $35,990.99
%AVANCEPARCIAL 7.27% 7.27% 7.27% 12.53% 12.53% 12.53% 12.53% 5.08% 5.08% 5.08% 5.08% 5.08% 0.40% 0.40% 0.40% 0.40% 1.00%
INVERSIONACUMULADA $260,960.67 $521,921.35 $782,882.02 $1,232,453.28 $1,682,024.53 $2,131,595.79 $2,581,167.04 $2,763,536.58 $2,945,906.12 $3,128,275.67 $3,310,645.21 $3,493,014.75 $3,507,540.97 $3,522,067.20 $3,536,593.42 $3,551,119.64 $3,587,110.63
%AVANCEACUMULADO 7.27% 14.55% 21.82% 34.36% 46.89% 59.42% 71.96% 77.04% 82.12% 87.21% 92.29% 97.38% 97.78% 98.19% 98.59% 99.00% 100.00%