Daily Report

Project Name: KBK Project


Project Code: 03 YG 00400 Report Date : 20-Jun-2017 Tuesday No. of Day 690 Report No. DPR-384
Project Start Date 2015-8-1 Contract Period 458 Calendar Day AM PM Fine
Weather
Estimate Completion Date 2016-10-31 Remain Period (232) Calendar Day 6~8 8~10 10 ~12 13~15 15~17 17~19 Rain
Work Force
M&E Site Surveyo Office Geotec General Crane Crane Steel
Trades PM PE SAE Site Engr QA/QC QS Admin Safety Security Welder
engineer Store r Staff h Workers Operator Helper Worker
Today 1 1 1 1 1 1 2 1 2 6 7
Operator Helper Manson Steel
Trades M&E Manson Carpenter Total
(ACP) (ACP) worker Supervisior
Today 1 2 27
Machine & Equipments onsite
Description previous Today Cum. Remarks Description previous Today Cum. Remarks Description previous Today Cum. Remarks
25 Ton Crane 1 1 1 1.5 Hp Submer; pump 4 4 4 19KW Welding Box 6 6 6
Sheet pile machine 0 0 0 1 Hp Motor pump 1 1 1 60 KVA generator 1 1 1
3"x3" Air Compressor 1 1 1 1.5 Hp Motor pump 1 1 1
165 KVA Generator 1 1 1 2Hp Pressure pump 0 0 0
Material Delivery On Site
Quantity Quantity Quantity
Description Unit Description Unit Description Unit Remarks
Today Total Today Total Today Total
TB-033,034,005,006 No 7 7
G-019,023 No 10 10

FO-OP-01 REV-00 Page: 1/2


Daily Report

Project Name: KBK Project


QC - Test Sampling
Item Remarks
Test
Sampl
e
Taken

LTI Free Day UA,UC Near Miss FAI MTC LTA Daily TBT
HSE Conducted By
Safety Officer
Works Carried out Details
Trades Of Work Location Remark
1 Dismantling of temporary platform and strutting At grid (A-C)
2 Welding work and tightening bolt & nuts At grid E and (A-C)
3 Tie beam installation work at 1st and 2nd floor At grid (B-C)
4 Column installation work at lift pit area At grid (B-C)
5 Housekeeping work
6 Moved wastage material form site

Special Event
Site
Visitors
Purpose Instructi
on site
on
Project Manager Project Engineer Prepare By: Site Engineer
Name U Khin Maung Myint Name Name Aye Wit Yee Soe
Signature Signature Signature

FO-OP-01 REV-00 Page: 2/2


KBK Project
Site Progress Photo
Date: 20.6.2017

Steel structue installation work at 1st and 2nd floor , grid B-C

Moved unnecessary materials from site