JICAs Current Projects in the Transport Sector
(Roads)

Poipet
TCP
Loan Transport Policy Advisor
NR5 Improvement (End)
(2015-2020) Strengthening Capacity for
Road Bridge Maintenance
Loan (2015-2018)
NR5 Improvement (North)
(2014-2019)
Loan
NR5 Improvement (Middle) P/S
(2015-2020) Rehabilitation of Chroy
Chongwa Bridge

Loan
NR5 Improvement (South) F/S
(2015-2020) Phnom Penh Bavet
Expressway

Grant
Image of future NR5 NR1 rehabilitation (Phase
IV and Urban section)
(2014-2017)
Grant
Neak Loeung (Tsubasa)
Bridge Construction
(2010-2015)

-2-
JICAs Current Projects in the Transport Sector
(Ports : Sihanoukville Port)
Loan
Multi-Purpose
Terminal Development Project
(2009-2017)
Facilities : Quay wall and Yard
for bulk cargo, Access Cannel
and Basin, Tug boat.

TCP
Capacity Development on Container
Terminal Management and
Operation in SHV Port
(2013-2016)

SHV Port SEZ 70ha


Productions of Integrated Digital
(2009-2012)
Terrain Model and Electronic
Navigational Chart Container Terminal 400m
(2013-2016) (2002-2007)

New Quay 350m


(1967-1970)

Old Port 290m


(1956-1959)

-3-
JICAs Current Projects in the Transport Sector
(Urban Transport)

F/S (planned)
Rail Transit
System in PP

Grant 100 Traffic Signals and


TCP
Traffic Control Center
Traffic Management Suggestions from PP
System in PP Master Plan in 2035
(2015-2017)

-4-
JICAs Strategies for Future Assistance

Logistics and connectivity


reinforcement through corridor
development
- Southern Economic Corridor
- High-standard infrastructure
- Flood mitigation
- SHV port expansion
- O&M of SHV port
- Inland waterway

-5-
JICAs Strategies for Future Assistance

Environmental Urban Transport


& Social
Considerations Sustainable and
continuous
development
through
addressing

Maintenance/ Traffic Safety


Asset and Security
Management
-6-
New TCP for Environmental & Social
Considerations
EIA: Environmental Impact
Environmental and Social Assessment
Considerations (ESC) EMP: Environmental
Management Plan
ROW: Right of Way

Environmental Social
Considerations Considerations

Implementing ROW
EIA/EMP Resettlement
EMP management
Climate Indigenous
Monitoring Monitoring
Change Peoples
Stakeholder
Safety .... ....
Consultation

Project purpose: capacity enhancement of MPWT officials on ESC


through applying Road Environmental Guidelines and ROW
Management System
-7-
New TCP for improving traffic safety

Improvement of
traffic safety

Stricter control Improvement of Awareness raising Facility


of violation vehicle control for road users improvement
Capacity enhancement Proper vehicle registration Improvement of User friendly design
for police and data management. Driving License system such as sidewalks and
traffic signals.
Improvement of vehicle Law enforcement such
safety(restriction of illegal as helmet wearing.
imported vehicle,
modernization of vehicle Campaign for traffic
inspection) safety

Project purpose: improvement of traffic safety through capacity


development of MPWT s vehicle control(registration and inspection)