Jobs in the rainy season dealing with large amounts of water. That requires a drainage channel edge to
land a job.
3. After reaching the elevation of the excavation plan. Compacted subgrade. If there was a
puddle of water, the water is pumped out until the machine can go in for a job
compacting subgrade and embankment.
4. Fill conducted layer by layer, until the planned elevation where the elevation is high
enough and safe from puddles.
5. The sides next to it, dug and dumped out. Using the access point side that has been in the
pile.
6. The next steps according to the stages of work.