METHOD OF EXECUTION

Package: CONSTRUCTION OF SOLO - Kertosono TOLL ROAD


JOB HANDLING WEL
Job well handling are dealing with large amounts of water. That requires dewatering.

Step-by-step implementation are as follows:


1. Existing wells on the mark and the measured depth of the well and the depth of the channel
base

2. Land use excavator dug job until it reaches a specified elevation. Wellbore maintained.

3. Dewatering water in the channel, and the material is inserted into the well. Soil compaction
in the channel do his best.

4. The mouth of the well is capped with concrete construction to avoid a decrease in the area
of the well.

5. The dissemination of material and compaction layer by layer do..


the need for tools
Excavator 1 Unit
Stamper 1 Unit
Pump 1 Unit
Dump Truck 25 Unit

Manpower Requirement
Site Manager 1
Executing 1
Surveyor 1
Operator 4
Helper 2
Flagman 2
Driver 25

Material needs
Borrow Material Adjust the size of wells
Adjust the size of the concrete wells