1.1 Solar PV Plant: PR : 0.80 & CUF : 18% Solar PV Plant: PR : 0.80 & CUF : 18%
Section
2 Location (against installed DC capacity at STC) (against installed DC capacity at STC)
V: TS
Details
Wind Farm: CUF: 28% Wind Farm: Contractor shall demonstrate efficiency/power at
the observed wind speeds (measured with the wind
monitoring mast which is to be installed by the contractor) as
per certified Power Curve of WEG supplied by the
manufacturer and maintain minimum 95% annual Availability
during the O&M Period.
Energy Storage System: 95% Availability,
85% AC to AC Round Trip Efficiency (FR Use Case ) and Energy Storage System: 95% Availability,
90% for Peak Management Use Case 85% AC to AC Round Trip Efficiency (FR Use Case ) and
90% for Peak Management Use Case
(Committed CUF Actual CUF) x 8760 x Rs. 6.5; (Committed CUF Actual CUF) x 8760 x Rs. 6.5;
for period after commissioning till the O&M contract for period after commissioning till the O&M contract closure.
closure. The CUF shall be evaluated as per the formula The CUF shall be evaluated as per the formula mentioned at
mentioned at Clause Clause 7 of TS of this NIT.
7 of TS of this NIT.
Part-02 of Plant Facilities: Part-02 of Plant Facilities:
Failure to meet the Functional Guarantee tests as Failure to meet the Functional Guarantee tests as specified
specified in Clause 17.8 in the trial run period for in Clause 17.8 in the trial run period for Operational
Operational Acceptance shall attract the imposition of Acceptance shall attract the imposition of Liquidated
Liquidated Damages, as follows: Damages, as follows:
Failure to meet the 96 Hours Short Time Test Run: LD @ Failure to meet the 96 Hours Short Time Test Run: LD @ 1%
1% of the total Contract Price. Failure to meet the Power of the total Contract Price. Failure to meet the Power Curve
Curve Performance Test: a LD of 1% of the total Contract Performance Test: a LD of 1% of the total Contract Price.
Price. During the O&M Period, for shortfall in availability below 95%,
Liquidity Damages during O&M period, imposed annually,
shall be charged at a rate of: (Committed Annual Net Liquidity Damages during O&M period shall be imposed
Expected Energy Generation (NEEG) Actual Annual annually as follows, if availability is less than 95%:
Energy Generation) x Rs. 6.5; for period after 1 (.95 - Actual annual Availability) x 8760 x
commissioning till the O&M contract closure. Actual Annual CUF x Installed Capacity (kWs)
x Rs. 6.5
Eg. Actual annual availability : 92% i.e. 0.92
3 Site Development Work D+120 landslide etc which could affect movement of material/
Section
including levelling, micro- equipment leading to disruption of work schedule. In
5 IV: 6
siting etc. general, Himachal Pradesh Public Works Department and
SCC
4 Completion of supply of D+200 Border Road Organization promptly clear such roadblocks
major equipment for Part- and damages. In addition working conditions at site may
01, Part-02 and Part-03 not be conducive on account of snowfall or extreme cold
5 Installation of all major D+280 during winter months. The bidder shall take into
The above timelines are indicative only. The bidders shall No. from D
provide their detailed schedule in view of the Supply 1 Notification of Award (Issue Zero Date
Schedules and prevailing weather conditions at Site for of LOI ) (D)
ease of transportation and installation. 2 Approval of Designs, D+60
The Contractor shall inform the Employer through Scheme and Technology
notice, and a final notice 7 days in advance to enable the 3 Site Development Work D+120
Employer inform the commissioning committee of the date including levelling, micro-
on which it intends to synchronize the Power Project (Part- siting etc. and establishment
01, Part-02, and Part-03) to the Grid System. of Wind Monitoring Mast for
gathering wind data
The Contractor shall prepare the completion schedule
accordingly and in conformity with provisions of technical 4 Completion of supply of D+200
major equipment for Part-01,
specifications and carry out the work as per this schedule
Part-02 and Part-03
subject to Force Majeure conditions. The Contractor
shall mobilize resources keeping in view, the above 5 Installation of all major D+280
Section
7 15.1
V: TS Rated Power: in the range of 50-100kW Rated Power: in the range of 30-500kW
CUF = CUF =
8760 8760
16
Where, Where,
EN is number of units recorded at the ABT metre at 22 EN is number of units recorded at the ABT metre at 22 kV
kV local bus bar in Plant Facilities after excluding local bus bar in Plant Facilities after excluding auxiliary
auxiliary consumption. consumption.
CF=
CF= *(1-Module
*
Degradation Factor*No. of Years)
1
Reference radiation is 1862 kWh/m2 as per NASA
(1Module Degradation FactorNo.of Years)
database.
Reference radiation is 1862 kWh/m2
Certificate of Compliance
17 Resources with Electric Power Systems). Such The Contractors equipment shall be compliant with IEEE
compliance shall be certified by an independent testing IEEE1547/ UL1741/ IEC 62116 or equivalent. Such
agency. Compliance shall be certified in writing and compliance shall be certified by an independent testing
submitted to the Owner at least 30 days before shipment. agency. Compliance shall be certified in writing and submitted
Sectio Certification of compliance shall be at Contractors to the Owner at least 30 days before shipment. Certification
n V: TS 22.6 expense. of compliance shall be at Contractors expense.
Insulation: Insulation:
18 Section 6.13.3 The dielectric strength of the winding, given insulation and The dielectric strength of the winding, given insulation and the
V: TS the bushings shall conform to the values given in IS: 2026 bushings shall conform to the values given in IS: 2026 (Part
(Part III)/1981 (or its latest amendment) for highest system III)/1981 (or its latest amendment) for highest system voltage
voltage of 36 kV, of 24 kV,
Frequency and System Voltage: Frequency and System Voltage:
The transformer shall be suitable for continuous operation The transformer shall be suitable for continuous operation
19 6.13.11 with a frequency variation of 2.5% from normal of 50Hz with a frequency variation of 2.5% from normal of 50Hz
Section without exceeding the specified temperature rise. The without exceeding the specified temperature rise. The highest
V: TS highest system rated voltage shall be 36 kV. system rated voltage shall be 24 kV.
CCTV Cameras must be installed to have complete coverage
CCTV cameras must be installed minimum at main entry
of following areas;
gate and control room. Bidder may propose other locations
1. Main entry: Covering all the entry/exit 24 hrs.
as required to provide security for the entire plant. Bidder
20 6.45.1 2. Along the Plant Perimeter: Covering complete perimeter of
has to propose the locations and number of cameras
Plant Area to capture all possible intrusion.
required for the plant during bidding. However, Employer
Section 3. Control Rooms: Covering Entry/Exit and activities within
will decision on number of cameras shall be final.
V: TS Control Rooms.
Bidder shall also provide required set of onsite testing
Bidder shall also provide required set of onsite testing instruments/equipment viz:
instruments/equipment viz. earth resistance tester, (i) Earth resistance tester:
rheostats, insulation tester, millimetres, clamp meters, Sl. Parameters Specification
CRO, Function Generator, Transformer oil BDV kit, Relay No
21 6.46.1 1 Display LCD Digital Display with
testing kit, infra-red thermal imaging hand held backlight
temperature meter, inverter testing kit etc. All testing 2 Range Earth Resistance: up to
2000
equipment shall possess valid calibration certificate issued Earth Voltage : 200 V
Section from approved NABL labs. 3 Safety Ratings IP 56
4 Programmable Enabled
V: TS
Limits setting
Accessories
1 Earth Ground Stakes (4 Nos)
2 Three cable reels with cable length up to 20 m
3 Carry Case-1 (capable of handling tester along
with accessories)
4 1 set of spare battery
(iv) Multi-metres:
Note:
a) All testing equipment shall possess valid
calibration certificate issued from approved NABL
labs.
b) Instruments of superior rating is allowed after
seeking consent of the Employer
c) Maintenance, calibration, up keeping, repair &
replacement of these tools will be in the scope of
Contractor during O&M.
d) It is Contractors responsibility to arrange for
tools, tackles, logistics, test kits, manpower, experts
etc. required for trouble free operation of Plant