Você está na página 1de 24

RENCANA ANGGARAN BIAYA

(RAB)

PROGRAM :
KEGIATAN :
PEKERJAAN :
LOKASI :
DANA :
TH. ANGGARAN :

HARGA
JUMLAH
NO JENIS PEKERJAAN SAT VOLUME ANALISA SATUAN
Rp. Rp.
1 2 3 4 5 6 7

A PENAMBAHAN KAMARMANDI R.DINAS DOKTER PUSKESMAS SANANWETAN


I PEKERJAAN TANAH
1 Galian tanah Pondasi M3 3.16 SNI II.1.6.1 27,620.00 87,348.25
2 Urugan pasir bawah pondasi M3 0.28 SNI II.11.6.11 96,850.00 26,633.75
JUMLAH II 113,982.00
II PEKERJAAN PONDASI
1 Anstampeng M3 0.55 SNI III.9.6.9 238,230.00 131,026.50
2 Pondasi batu kali 1 : 4 M3 0.81 SNI III.2.6.2 538,140.00 435,893.40
JUMLAH III 566,919.90
III PEKERJAAN PASANGAN DAN BETON
1 Pasangan Batu Merah 1/2 Bata, 1 pc : 2 ps (trasram) m2 1.05 SNI IV.3.6.7 86,800.00 91,140.00
2 Pasangan Batu Merah 1/2 Bata, 1 pc : 4 ps m2 7.20 SNI IV.5.6.9 76,090.00 547,848.00
3 Plesteran 1 pc : 2 pp, Tebal 15 mm (trasram) m2 2.10 SNI V.1.6.2 32,250.00 67,725.00
4 Plesteran 1 pc : 4 ps, Tebal 15 mm m2 14.40 SNI V.3.6.4 26,650.00 383,760.00
5 Keramik Lantai KM/WC 20 x 20 m2 1.88 SNI XIII.9.6.36 119,220.00 223,537.50
6 Keramik Dinding KM/WC 20 x 25 m2 3.00 SNI XIII.11.6.54 128,300.00 384,900.00
7 List Keramik Dinding 8 x 20 bh 11.00 Ls 18,000.00 198,000.00
10 List Plafon Gypsum m' 5.50 OL.VI.3 26,570.00 146,135.00
11 Pasang Kloset Jongkok bh 1.00 SNI X.2.6.2 266,230.00 266,230.00
12 Sloof 15 x 20
Mengecor K175 M3 0.08 SNI VII.2.6.5 761,000.00 62,782.50
Pembesian 122.765 KG 10.13 SNI VII.8.6.17.a 11,380.00 115,257.92
Begisting M2 0.46 OL.V.2 34,560.00 15,966.72
13 Kolom 11 X 11
Mengecor K175 M3 0.09 SNI VII.2.6.5 761,000.00 69,981.56
Pembesian 124.7567 KG 11.47 SNI VII.8.6.17.a 11,380.00 130,558.49
Begisting M2 0.51 OL.V.9 34,297.50 17,662.39
14 Ring Balok 15 x 20
Mengecor K175 M3 0.08 SNI VII.2.6.5 761,000.00 62,782.50
Pembesian 135.7567 KG 11.20 SNI VII.8.6.17.a 11,380.00 127,455.18
Begisting 6.67 M2 0.46 OL.V.10 54,450.00 25,155.90
15 Pasang instalasi lampu/ stop kontak Ttk 1.00 Harga Sat 150,000.00 150,000.00
16 Lampu Hemat Energi 18 watt ( Philips SL ) Inbow lengkap Holder Stanlee Bh 1.00 Harga Sat 120,000.00 120,000.00
17 Saklar Tunggal ( Broco ) Bh 1.00 Harga Sat 23,000.00 23,000.00
18 Pengecatan Dinding Bh 16.50 Harga Sat 30,000.00 495,000.00

JUMLAH III 3,724,878.65


XI PEKERJAAN PAVING, PLAT DUIKER
PINTU BESI, DAN ATAP POLYKARBONAT DAN PERESAPAN
1 Plat Duiker t=15 cm L=1.00m P=5.00m
Mengecor K175 M3 0.75 SNI VII.2.6.5 761,000.00 570,750.00
Pembesian 130.7567 KG 107.25 SNI VII.8.6.17.a 11,380.00 1,220,505.00
Begisting M2 5.00 OL.V.8 23,037.50 115,187.50
2 Galian tanah Pondasi M3 16.80 SNI II.1.6.1 27,620.00 464,016.00
3 Pondasi batu kali 1 : 4 Plat Duiker M3 10.05 SNI III.2.6.2 538,140.00 5,408,307.00
4 Plesteran 1 Pc : 4 Ps m2 9.00 SNI V.3.6.4 26,650.00 239,850.00
5 Pasang atap twinlight rangka pipa stainles 2m x 5m m2 10.00 Harga Sat 678,500.00 6,785,000.00
6 Pasang Pintu Besi R.dinas m2 1.60 Harga Sat 400,000.00 640,000.00
7 Pembuatan Sumur Peresapan dapur Gizi Puskesmas Kep kidul Unit 1.00 Harga Sat 1,000,000.00 1,000,000.00
8 Pasang Listrik Baru R.Dinas Dokter 900 Watt Unit 1.00 Harga Sat 2,500,000.00 2,500,000.00
Pasang Pompa air Unit 1.00 Harga Sat 600,000.00 600,000.00
9 Plat Penutup Sumur t=15 cm Dia. 1.05 m
Mengecor K175 M3 0.87 SNI VII.2.6.5 761,000.00 658,616.96
Pembesian 135.7567 KG 123.76 SNI VII.8.6.17.a 11,380.00 1,408,401.74
Begisting M2 5.00 OL.V.8 23,037.50 115,187.50
10 Pasang Pipa PVC dia 3/4" m' 8.00 SNI X.12.6.25 20,340.00 162,720.00
11 Pengecatan Dinding Lama m2 50.00 SNI XIV.6.6.15 8,310.00 415,500.00

JUMLAH XI 22,304,041.71

JUMLAH Rp 26,709,822.26
DIBULATKAN Rp 26,709,000.00

910,270,000.00
Mengetahui, Blitar, - - 2010
PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PERENCANA
(P P T K) CV. WIJAYA MANDIRI

SISWATI Ir. SARJONO


NIP.19630915 198412 2 007 Direktur
BACK UP
SKETSA GAMBAR

.0
7
2.0
.0

3.0
1

8.0
8.0

1 PEKERJAAN TANAH
# Galian Tanah Pondasi
76.00 X 0.80 x 1.00 = 60.80 m3
# Urugan Pasir Bawah Lantai
10.00 x 10.00 x 0.03 = 3.00
6.00 x 1.70 0 0.03 = 0.31
3.31 m3
2 PEKERJAAN PONDASI
# Aanstampeng
76.00 x 0.80 x 0.20 = 12.16 m3
# Pondasi Batu Kali
76.00 x 1.10 x 0.40 = 33.44 m3
# Pondasi Rolag
10.00 x 55.00 = 550 m2

3 PEKERJAAN PASANGAN
# Pas. Bata Merah
30.00 x 4.00 = 120.00 m2
# Pas. Gewel
6.00 1.50 9
10.00 x 2.00 = 20
2.00 = 49.00 m2
# Luasan Kusen
SKETSA GAMBAR

P1 D = 4.17 x 1.00 = 4.17


P1 T = 1.64 5.00 = 8.2
P1 K = 1.44 1.00 = 1.44
JI = 2.92 x 6.00 = 17.52
BV = 0.59 x 1.00 = 0.59
0.93 1.00 = 0.93
31.92 m2
# Luasan Pas. Bata Merah
120.00 + 49.00 - 31.92 = 137.08 m2

# Keramik Lantai
43.32 x 4.00 = 173.28
16.74 x 5.00 = 83.70
3.00 X 8.12 x 6.00 = 146.16
10.72 x 7.00 = 75.04
478.18 m2

4 PEKERJAAN KAYU ATAP DAN PLAFOND


# Kuda Kuda Bentang 10.00
SKETSA GAMBAR
Ruiter 2/20
Nok8/12
IkatanStripT= 4 mm
Sepatu 8/12
Tiang/Ander 8/12

Skoor 8/12
Kaki Kuda-Kuda8/12

Usuk 5/7
Kaki Kuda-Kuda8/12
Pengapit 2x6/12

Gording 8/12 Gording 8/12


Tupai - Tupai Tupai - Tupai

Balok Tarik8/12

Balok Tembok 8/12 Balok Tembok8/12

10.00 x 0.06 x 0.12 = 0.07


35.60 x 0.08 x 0.12 = 0.34
0.41 m3
# Pas. Gording Nok dan Balok Tembok 6/12
SKETSA GAMBAR

14.00 x 0.08 x 0.12 = 0.13


2.00 = 0.27
11.15 x 0.08 x 0.12 = 0.11
4.00 = 0.43
2.80 x 0.08 x 0.12 = 0.05
2.00 = 0.10
TOTAL = 0.80 m3
# Reng Usuk
15.23 x 11.15 = 169.81
10.07 x 1.95 = 19.64
= 189.45 m2
5 PEKERJAAN BETON
SKETSA GAMBAR

# Sloof
76.00 x 0.15 x 0.20 = 2.28 m3
# Kolom Praktis
0.15 x 0.15 x 4.00 = 0.09
24.00 = 2.16 m3
# Ring Balk
76.00 x 0.20 x 0.15 = 2.28 m3
# Rabat
0.05 43.32 x 4.00 = 8.66
0.05 16.74 x 5.00 = 4.19
0.05 X 8.12 x 6.00 = 2.44
0.05 10.72 x 7.00 = 3.75
19.04 m3
x 0.15 x 0.20 = - m3
8x = - m3
4.80 x 0.06 x 0.15 = 0.04
4.00 = 0.17 m3
Kusen P2
4.70 x 0.06 x 0.15 = 0.04
1.00 = 0.04 m3
# Kusen PJ1
13.50 x 0.06 x 0.12 = 0.10
1.00 = 0.19 m3
Kusen PJ2
13.30 x 0.06 x 0.12 = 0.10
1.00 = 0.10 m3
# Kusen BV1
5.37 x 0.06 x 0.12 = 0.04
1.00 = 0.04 m3
Kusen BV2
3.86 x 0.06 x 0.12 = 0.03
1.00 = 0.03 m3
TOTAL 0.57 m3

7 PEKERJAAN CAT KUSEN


SKETSA GAMBAR

Kusen P1
4.80 x 27 = 129.60
4.00 = 518.40 m2
Kusen P2
4.70 x 27 = 126.90
1.00 = 126.90 m2
Kusen PJ1
13.50 x 27 = 364.50
1.00 = 364.50 m2
Kusen PJ2
13.30 x 27 = 359.10
1.00 = 359.10 m2
Kusen BV1
5.37 x 27 = 144.99
1.00 = 144.99 m2
Kusen BV2
3.86 x 27 = 104.22
1.00 = 104.22 m2
TOTAL = 1,618.11 m2

Pemasangan kaca 5mm


1.70 x 1.00 = 1.70
1.71 x 6.00 = 10.26
1.68 x 1.00 = 1.68
0.19 x 1.00 = 0.19
TOTAL = 13.83 m2
RENCANA ANGGARAN BIAYA
(RAB)

KEGIATAN : PEMBANGUNAN RUMAH PRIBADI


PEKERJAAN : PEMBANGUNAN RUMAH PRIBADI
LOKASI :PLANDIREJO RT2 RW3 KEC BAKUNG KAB.BLITAR
TH. ANGGARAN : 2013

Tgl : s/d .

HARGA SATUAN JUMLAH


NO JENIS PEKERJAAN SAT VOLUME ANALISA
Rp. Rp.
1 2 3 4 5 6 7

1 PEKERJAAN TANAH
1 Galian tanah Pondasi M3 60.80 SNI II.1.6.1 27,620.00 1,679,296.00
2 Urugan pasir bawah pondasi M3 3.31 SNI II.11.6.11 96,850.00 320,186.10
3 Urugan pasir bawah lantai 10 cm M3 3.31 SNI II.11.6.11 96,850.00 320,186.10

JUMLAH II 2,319,668.20
2 PEKERJAAN PONDASI
1 Anstampeng M3 12.16 SNI III.9.6.9 238,230.00 2,896,876.80
2 Pondasi batu kali 1 : 4 M3 33.44 SNI III.2.6.2 538,140.00 17,995,401.60
3 Pondasi Roolag M2 550.00 SNI IV.2.6.3 158,170.00 86,993,500.00

JUMLAH III 107,885,778.40


3 PEKERJAAN PASANGAN
1 Pasangan Batu Merah 1/2 Bata, 1 pc : 4 ps m2 120.00 SNI IV.5.6.9 76,090.00 9,130,800.00
2 Plesteran 1 pc : 4 ps, Tebal 15 mm m2 240.00 SNI V.3.6.4 26,650.00 6,396,000.00
3 Keramik lantai 40 x 40 Dalam dan kamar mandi 20 x 20 m2 478.18 SNI XIII.8.6.35 109,550.00 52,384,619.00
JUMLAH IV 67,911,419.00
4 PEKERJAAN KAYU, ATAP DAN PLAFOND
1 Pas. Kuda kuda Kayu Kruing 8/12 m3 0.41 SNI VI.6.6.13 9,212,250.00 3,811,660.56
2 Pas. Gording Kayu Kruing 6/12 m3 0.80 SNI VI.8.6.15 8,800,970.00 7,038,297.65
3 Pasang Reng Usuk Kayu Kruing m2 189.45 OL.IV.6 123,500.00 23,397,198.50
4 Genteng prentul ex trenggalek m2 189.45 SNI VIII.1.6.2 49,460.00 9,370,246.46
5 Bubungan Genteng prentul m' 11.95 SNI VIII.4.6.6 60,100.00 718,195.00
6 Pasang Listplank Kayu Kamper m' 15.53 OL.IV.8 77,500.00 1,203,730.00
7 Rangka plafond 5/7, 2/3 kayu meranti dan eternit M2 164.00 OL.VI.8 105,770.00 17,346,280.00
8 Pasang list tepi plafond chamfer M' 152.00 OL.VI.2 10,630.00 1,615,760.00
JUMLAH V 64,501,368.17
5 PEKERJAAN BETON
1 Sloof 15 x 20
Mengecor K.175 M3 2.28 SNI VII.2.6.5 761,000.00 1,735,080.00
Pembesian 134.7567 KG 307.25 SNI VII.8.6.17.a 11,380.00 3,496,451.24
Begisting M2 30.40 OL.V.2 34,560.00 1,042,644.00
2 Kolom 15 X 15
Mengecor K.175 M3 2.16 SNI VII.2.6.5 761,000.00 1,643,760.00
Pembesian 134.7567 KG 291.07 SNI VII.8.6.17.a 11,380.00 3,312,427.49
Begisting M2 28.80 OL.V.9 34,297.50 987,768.00
3 Ring Balk 15/20
Mengecor K.175 M3 2.28 SNI VII.2.6.5 761,000.00 1,735,080.00
Pembesian 134.7567 KG 307.25 SNI VII.8.6.17.a 11,380.00 3,496,451.24
Begisting M2 30.40 OL.V.2 34,560.00 1,042,644.00
3 Beton Rabat keliling ruangan
Mengecor M3 19.04 SNI VII.1.6.4 603,730.00 11,493,208.01
JUMLAH VI 29,985,513.98
6 PEKERJAAN KAYU
1 Kusen jendela dan Pintu kamfer 6/15 M3 0.57 SNI VI.1.6.1 12,002,500.00 6,862,021.29
2 Pasang daun pintu panil kamfer M2 13.44 SNI VI.3.6.5 592,750.00 7,966,560.00
3 Pasang daun jendela kaca M2 13.65 SNI VI.4.6.6 330,800.00 4,515,503.25
JUMLAH VII 19,344,084.54
7 PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Kaca Polos 5mm m2 13.83 SNI XII.17.6.17 81,270.00 1,123,964.10
2 Engsel Jendela Set 32.00 SNI XII.6.6.6 16,370.00 523,840.00
3 Engsel Pintu Set 16.00 SNI XII.5.6.5 27,860.00 445,760.00
4 Grendel Pintu Bh 7.00 Harga Sat 9,900.00 69,300.00
5 Grendel Jendela Bh 16.00 Harga Sat 5,500.00 88,000.00
6 Winhak kait jendela Bh 16.00 SNI XII.7.6.7 44,250.00 708,000.00
7 Kunci tanam 2X putaran Bh 6.00 SNI XII.2.6.2 108,320.00 649,920.00
JUMLAH VIII 3,608,784.10
8 PEKERJAAN PENGECATAN
1 CatTembok baru M2 240.00 SNI XIV.5.6.14 11,090.00 2,661,600.00
2 Cat Plafond/ Eternit M2 90.00 OL.IX.5 16,300.00 1,467,000.00
3 Cat Kayu baru M2 13.64 OL.IX.2 34,160.00 466,017.55
JUMLAH IX 4,594,617.55
9 PEKERJAAN INSTALASI LISTRIK
1 Pasang instalasi lampu/ stop kontak Ttk 21.00 Harga Sat 100,000.00 2,100,000.00
3 Lampu Hemat Energi 18 watt ( Philips SL ) Inbow lengkap Holder Stanlees Bh 16.00 Harga Sat 31,900.00 510,400.00
4 Saklar Tunggal ( Broco ) Bh 6.00 Harga Sat 25,300.00 151,800.00
5 Saklar ganda ( Broco ) Bh 2.00 Harga Sat 33,000.00 66,000.00
6 Stop kontak 200 Va ( Broco ) Bh 5.00 Harga Sat 25,300.00 126,500.00
JUMLAH X 2,954,700.00

JUMLAH Rp 303,105,933.95
DIBULATKAN Rp 303,105,000.00
REKAPITULASI
RENCANA ANGGARAN BIAYA

KEGIATAN : PEMBANGUNAN RUMAH PRIBADI


PEKERJAAN : PEMBANGUNAN RUMAH PRIBADI
LOKASI :PLANDIREJO RT2 RW3 KEC BAKUNG KAB.BLITAR
TH. ANGGARAN : 2013

NO JENIS PEKERJAAN JUMLAH


( Rp )
1 2 3

1 PEKERJAAN TANAH Rp 2,319,668.20


2 PEKERJAAN PONDASI Rp 107,885,778.40
3 PEKERJAAN PASANGAN Rp 67,911,419.00
4 PEKERJAAN KAYU, ATAP DAN PLAFOND Rp 64,501,368.17
5 PEKERJAAN BETON Rp 29,985,513.98
6 PEKERJAAN KAYU Rp 19,344,084.54
7 PEKERJAAN PENGGANTUNG DAN PENGUNCI Rp 3,608,784.10
8 PEKERJAAN PENGECATAN Rp 4,594,617.55
9 PEKERJAAN INSTALASI LISTRIK Rp 2,954,700.00
SUB TOTAL I Rp 303,105,933.95

JUMLAH Rp 303,105,933.95
DIBULATKAN Rp 303,105,000.00
SNI
STANDAR NASIONAL INDONESIA

DAFTAR ANALISA BAHAN DAN UPAH KERJA


PEMERINTAH KOTA BLITAR TAHUN ANGGARAN 2011
(SEMESTER I)

II.1.6.1 1 m3 Galian Tanah Biasa (Sedalam 1 m)


0.7500 Oh Pekerja Rp. 35,000.00 = Rp. 26,250.00
0.0250 Oh Mandor Rp. 55,000.00 = Rp. 1,375.00
Total = Rp. 27,625.00
Dibulatkan = Rp. 27,620.00
II.11.6.11 1 m3 Urugan Pasir
1.2000 m3 Pasir Urug Rp. 71,500.00 =Rp. 85,800.00
Sub Total = Rp. 85,800.00
0.3000 Oh Pekerja Rp. 35,000.00 =Rp. 10,500.00
0.0100 Oh Mandor Rp. 55,000.00 =Rp. 550.00
Sub Total = Rp. 11,050.00
Total = Rp. 96,850.00
Dibulatkan = Rp. 96,850.00
III.2.6.2 1 m3 Pasang Pondasi Batu Kali Belah 1 pc : 4 ps
1.2000 m3 Batu Kali Belah 15/20 Rp. 132,000.00 =Rp. 158,400.00
163.0000 kg Semen PC Rp. 1,500.00 =Rp. 244,500.00
0.5200 m3 Pasir Pasang Rp. 93,500.00 =Rp. 48,620.00
Sub total =Rp. 451,520.00

1.5000 Oh Pekerja Rp. 35,000.00 =Rp. 52,500.00


0.6000 Oh Tukang Batu Rp. 45,000.00 =Rp. 27,000.00
0.0600 Oh Kepala Tukang Batu Rp. 50,000.00 =Rp. 3,000.00
0.0750 Oh Mandor Rp. 55,000.00 =Rp. 4,125.00
Sub Total = Rp 86,625.00
Total = Rp. 538,145.00
Dibulatkan = Rp. 538,140.00
III.9.6.9 1 m3 Pasang Pondasi Batu Kosong (Aanstampeng)
1.2000 m3 Batu Kali Belah 15/20 Rp. 132,000.00 =Rp. 158,400.00
0.4320 m3 Pasir Urug Rp. 71,500.00 =Rp. 30,888.00
Sub total =Rp. 189,288.00

0.7800 Oh Pekerja Rp. 35,000.00 =Rp. 27,300.00


0.3900 Oh Tukang Batu Rp. 45,000.00 =Rp. 17,550.00
0.0390 Oh Kepala Tukang Batu Rp. 50,000.00 =Rp. 1,950.00
0.0390 Oh Mandor Rp. 55,000.00 =Rp. 2,145.00
Sub total =Rp. 48,945.00
Total = Rp. 238,233.00
Dibulatkan = Rp. 238,230.00
IV.2.6.3 1 m2 Pasangan Batu Merah Tebal 1 Bata, 1 pc : 4 pp
140.0000 bh Bata Merah Kelas I Rp. 550.00 =Rp. 77,000.00
26.5500 kg Semen PC Rp. 1,500.00 =Rp. 39,825.00
0.0930 m3 Pasir Pasang Rp. 93,500.00 =Rp. 8,695.50
Sub total =Rp. 125,520.50
0.6000 Oh Pekerja Rp. 35,000.00 =Rp. 21,000.00
0.2000 Oh Tukang Batu Rp. 45,000.00 =Rp. 9,000.00
0.0200 Oh Kepala Tukang Batu Rp. 50,000.00 =Rp. 1,000.00
0.0300 Oh Mandor Rp. 55,000.00 =Rp. 1,650.00
Sub Total = Rp 32,650.00
Total = Rp. 158,170.50
Dibulatkan = Rp. 158,170.00
IV.5.6.9 1 m2 Pasangan Batu Merah Tebal 1/2 Bata, 1 pc : 4 pp
70.0000 bh Bata Merah Kelas I Rp. 550.00 =Rp. 38,500.00
11.5000 kg Semen PC Rp. 1,500.00 =Rp. 17,250.00
0.0430 m3 Pasir Pasang Rp. 93,500.00 =Rp. 4,020.50
Sub total =Rp. 59,770.50
0.3000 Oh Pekerja Rp. 35,000.00 =Rp. 10,500.00
0.1000 Oh Tukang Batu Rp. 45,000.00 =Rp. 4,500.00
0.0100 Oh Kepala Tukang Batu Rp. 50,000.00 =Rp. 500.00
0.0150 Oh Mandor Rp. 55,000.00 =Rp. 825.00
Sub Total = Rp 16,325.00
Total = Rp. 76,095.50
Dibulatkan = Rp. 76,090.00
V.3.6.4 1 m2 Plesteran 1 pc : 4 pp (Tebal 15 mm)
6.2400 kg Semen PC Rp. 1,500.00 =Rp. 9,360.00
0.0240 m3 Pasir Pasang Rp. 93,500.00 =Rp. 2,244.00
Sub total =Rp. 11,604.00
0.2000 Oh Pekerja Rp. 35,000.00 =Rp. 7,000.00
0.1500 Oh Tukang Batu Rp. 45,000.00 =Rp. 6,750.00
0.0150 Oh Kepala Tukang Batu Rp. 50,000.00 =Rp. 750.00
0.0100 Oh Mandor Rp. 55,000.00 =Rp. 550.00
Sub Total = Rp 15,050.00
Total = Rp 26,654.00
Dibulatkan = Rp 26,650.00
V.16.6.27 1 m2 Acian Beton
3.2500 kg Semen PC Rp. 1,500.00 =Rp. 4,875.00
Sub Total =Rp. 4,875.00
0.1500 Oh Pekerja Rp. 35,000.00 =Rp. 5,250.00
0.1000 Oh Tukang Batu Rp. 45,000.00 =Rp. 4,500.00
0.0100 Oh Kepala Tukang Batu Rp. 50,000.00 =Rp. 500.00
0.0080 Oh Mandor Rp. 55,000.00 =Rp. 440.00
Sub Total =Rp. 10,690.00
Total =Rp. 15,565.00
Dibulatkan =Rp. 15,560.00
VI.1.6.1 1 m3 Pasang Kusen Pintu dan Jendela (Mutu Kayu Klas II)
1.1000 m3 Kayu kamper, balok (mutu kayu klas II) Rp. 9,737,500.00 =Rp. 10,711,250.00
1.2500 kg Paku 3" Rp. 19,800.00 =Rp. 24,750.00

198
1.0000 kg Lem Kayu Rajawali Rp. 40,000.00 =Rp. 40,000.00
Sub Total =Rp. 10,776,000.00
6.0000 Oh Pekerja Rp. 35,000.00 =Rp. 210,000.00
20.0000 Oh Tukang Kayu Rp. 45,000.00 =Rp. 900,000.00
2.0000 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 100,000.00
0.3000 Oh Mandor Rp. 55,000.00 =Rp. 16,500.00
Sub Total =Rp. 1,226,500.00
Total =Rp. 12,002,500.00
Dibulatkan =Rp. 12,002,500.00
VI.3.6.5 1 m2 Pasang Daun Pintu Panel (Mutu Kayu Klas I atau II)
0.0400 m3 Kayu kamper, papan (mutu kayu klas II) Rp. 10,250,000.00 =Rp. 410,000.00
0.5000 kg Lem Kayu Rajawali Rp. 40,000.00 =Rp. 20,000.00
Sub Total =Rp. 430,000.00
1.0000 Oh Pekerja Rp. 35,000.00 =Rp. 35,000.00
2.5000 Oh Tukang Kayu Rp. 45,000.00 =Rp. 112,500.00
0.2500 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 12,500.00
0.0500 Oh Mandor Rp. 55,000.00 =Rp. 2,750.00
Sub Total =Rp. 162,750.00
Total =Rp. 592,750.00
Dibulatkan =Rp. 592,750.00
VI.4.6.6 1 m2 Pasang Daun Pintu dan Jendela Kaca (Mutu Kayu Klas I atau II)
0.0184 m3 Kayu kamper, papan (mutu kayu klas II) Rp. 10,250,000.00 =Rp. 188,600.00
0.3000 kg Lem Kayu Rajawali Rp. 40,000.00 =Rp. 12,000.00
Sub Total =Rp. 200,600.00
0.8000 Oh Pekerja Rp. 35,000.00 =Rp. 28,000.00
2.0000 Oh Tukang Kayu Rp. 45,000.00 =Rp. 90,000.00
0.2000 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 10,000.00
0.0400 Oh Mandor Rp. 55,000.00 =Rp. 2,200.00
Sub Total =Rp. 130,200.00
Total =Rp. 330,800.00
Dibulatkan =Rp. 330,800.00
VI.6.6.13 1 m3 Pasang Konstruksi Kuda-kuda Konvensional (Mutu Kayu Klas I, II, dan III), Bentang 6 m
1.1000 m3 Kayu Klas III (Balok Kayu Kruing) Rp. 7,328,750.00 =Rp. 8,061,625.00
15.0000 kg Besi Plat Begel Rp. 19,250.00 =Rp. 288,750.00
5.6000 kg Paku 3" Rp. 19,800.00 =Rp. 110,880.00
Sub Total =Rp. 8,461,255.00
4.0000 Oh Pekerja Rp. 35,000.00 =Rp. 140,000.00
12.0000 Oh Tukang Kayu Rp. 45,000.00 =Rp. 540,000.00
1.2000 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 60,000.00
0.2000 Oh Mandor Rp. 55,000.00 =Rp. 11,000.00
Sub Total =Rp. 751,000.00
Total =Rp. 9,212,255.00
Dibulatkan =Rp. 9,212,250.00
VI.8.6.15 1 m3 Pasang Konstruksi Gording (Mutu Kayu Klas III)
1.1000 m3 Kayu Klas III (Balok Kayu Kruing) Rp. 7,328,750.00 =Rp. 8,061,625.00
15.0000 kg Baut/Mur Rp. 19,250.00 =Rp. 288,750.00
3.0000 kg Paku 4" Rp. - =Rp. -
Sub Total =Rp. 8,350,375.00

2.4000 Oh Pekerja Rp. 35,000.00 =Rp. 84,000.00


7.2000 Oh Tukang Kayu Rp. 45,000.00 =Rp. 324,000.00
0.7200 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 36,000.00
0.1200 Oh Mandor Rp. 55,000.00 =Rp. 6,600.00
Sub Total =Rp. 450,600.00
Total =Rp. 8,800,975.00
Dibulatkan =Rp. 8,800,970.00
VII.1.6.4 1 m3 Membuat Beton Lantai Kerja Mutu f'c = 7,4 MPa (K100), Slump (3-6 cm), w/c = 0,87
(Setara Beton Tumbuk/Beton Rabat 1 PC : 3 Ps : 5 Kr)
230.0000 kg Semen PC Rp. 1,500.00 =Rp. 345,000.00
0.6379 m3 Pasir Beton Rp. 99,000.00 =Rp. 63,147.86
0.7607 m3 Batu Kali Pecah 2/3 (Maksimum 30 mm) Rp. 187,000.00 =Rp. 142,258.52
200.0000 ltr Air Bersih Rp. 5.00 =Rp. 1,000.00
Sub Total = Rp 551,406.38
1.2000 Oh Pekerja Rp. 35,000.00 =Rp. 42,000.00
0.2000 Oh Tukang Batu Rp. 45,000.00 =Rp. 9,000.00
0.0200 Oh Kepala Tukang Batu Rp. 50,000.00 =Rp. 1,000.00
0.0060 Oh Mandor Rp. 55,000.00 =Rp. 330.00
Sub Total = Rp 52,330.00
Total = Rp 603,736.38
Dibulatkan = Rp 603,730.00
VII.2.6.5 1 m3 Membuat Beton Mutu f'c = 14,5 MPa (K175), Slump (12 2 cm), w/c = 0,66
(Setara Beton 1 PC : 2 Ps : 3 Kr)
326.0000 kg Semen PC Rp. 1,500.00 =Rp. 489,000.00
0.5429 m3 Pasir Beton Rp. 99,000.00 =Rp. 53,742.86
0.7622 m3 Batu Kali Pecah 2/3 (Maksimum 30 mm) Rp. 187,000.00 =Rp. 142,535.56
215.0000 ltr Air Bersih Rp. 5.00 =Rp. 1,075.00
Sub Total = Rp 686,353.41
1.6500 Oh Pekerja Rp. 35,000.00 =Rp. 57,750.00
0.2500 Oh Tukang Batu Rp. 45,000.00 =Rp. 11,250.00
0.0250 Oh Kepala Tukang Batu Rp. 50,000.00 =Rp. 1,250.00
0.0800 Oh Mandor Rp. 55,000.00 =Rp. 4,400.00
Sub Total =Rp. 74,650.00
Total = Rp 761,003.41
Dibulatkan = Rp 761,000.00
VII.8.6.17.a 1 kg Pembesian dengan Besi Polos
1.0500 kg Besi Beton Polos Rp. 10,000.00 =Rp. 10,500.00
0.0150 kg Kawat Beton Rp. 18,150.00 =Rp. 272.25
Sub Total =Rp. 10,772.25
0.0070 Oh Pekerja Rp. 35,000.00 =Rp. 245.00
0.0070 Oh Tukang Besi Rp. 45,000.00 =Rp. 315.00
0.0007 Oh Kepala Tukang Besi Rp. 50,000.00 =Rp. 35.00
0.0004 Oh Mandor Rp. 55,000.00 =Rp. 22.00
Sub Total =Rp. 617.00
Total = Rp 11,389.25
Dibulatkan = Rp 11,380.00
VIII.1.6.2 1 m2 Pasang Genteng Prentul Ex. Trenggalek
25.0000 Bh Genteng Prentul Ex. Trenggalek Rp. 1,600.00 =Rp. 40,000.00

199
Sub Total Rp. 40,000.00
0.1500 Oh Pekerja Rp. 35,000.00 =Rp. 5,250.00
0.0750 Oh Tukang Kayu Rp. 45,000.00 =Rp. 3,375.00
0.0080 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 400.00
0.0080 Oh Mandor Rp. 55,000.00 =Rp. 440.00
Sub Total = Rp 9,465.00
Total =Rp. 49,465.00
Dibulatkan =Rp. 49,460.00
VIII.4.6.6 1 m1 Pasang Bubungan Genteng Prentul Ex. Trenggalek
5.0000 Bh Bubungan Genteng Prentul Ex. Trenggalek Rp. 4,200.00 =Rp. 21,000.00
8.0000 kg Semen PC Rp. 1,500.00 =Rp. 12,000.00
0.0320 m3 Pasir Pasang Rp. 93,500.00 =Rp. 2,992.00
Sub Total =Rp. 35,992.00

0.4000 Oh Pekerja Rp. 35,000.00 =Rp. 14,000.00


0.2000 Oh Tukang Kayu Rp. 45,000.00 =Rp. 9,000.00
0.0200 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 1,000.00
0.0020 Oh Mandor Rp. 55,000.00 =Rp. 110.00
Sub Total =Rp. 24,110.00
Total =Rp. 60,102.00
Dibulatkan =Rp. 60,100.00
XII.2.6.2 1 buah Pasang Kunci Pintu
1.0000 bh Kunci Pintu "Cap Kuda 2x Putar" Rp. 84,700.00 =Rp. 84,700.00
Sub Total =Rp. 84,700.00
0.0100 Oh Pekerja Rp. 35,000.00 =Rp. 350.00
0.5000 Oh Tukang Kayu Rp. 45,000.00 =Rp. 22,500.00
0.0100 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 500.00
0.0050 Oh Mandor Rp. 55,000.00 =Rp. 275.00
Sub Total =Rp. 23,625.00
Total =Rp. 108,325.00
Dibulatkan =Rp. 108,320.00
XII.6.6.6 1 set Pasang Engsel Jendela Kupu-kupu
1.0000 set Engsel Jendela Kupu-kupu Rp. 11,000.00 =Rp. 11,000.00
Sub Total =Rp. 11,000.00
0.0100 Oh Pekerja Rp. 35,000.00 =Rp. 350.00
0.1000 Oh Tukang Kayu Rp. 45,000.00 =Rp. 4,500.00
0.0100 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 500.00
0.0005 Oh Mandor Rp. 55,000.00 =Rp. 27.50
Sub Total =Rp. 5,377.50
Total =Rp. 16,377.50
Dibulatkan =Rp. 16,370.00
XII.7.6.7 1 set Pasang Hak Angin Sikutan Biasa
1.0000 set Hak Angin Sikutan Biasa Rp. 33,000.00 =Rp. 33,000.00
Sub Total =Rp. 33,000.00
0.0200 Oh Pekerja Rp. 35,000.00 =Rp. 700.00
0.2000 Oh Tukang Kayu Rp. 45,000.00 =Rp. 9,000.00
0.0200 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 1,000.00
0.0100 Oh Mandor Rp. 55,000.00 =Rp. 550.00
Sub Total =Rp. 11,250.00
Total =Rp. 44,250.00
Dibulatkan =Rp. 44,250.00
XII.17.6.17 1 m2 Pasang Kaca Polos 5 mm
1.1000 m2 Kaca Polos 5 mm Rp. 66,550.00 =Rp. 73,205.00
Sub Total =Rp. 73,205.00
0.0150 Oh Pekerja Rp. 35,000.00 =Rp. 525.00
0.1500 Oh Tukang Kayu Rp. 45,000.00 =Rp. 6,750.00
0.0150 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 750.00
0.0008 Oh Mandor Rp. 55,000.00 =Rp. 41.25
Sub Total =Rp. 8,066.25
Total =Rp. 81,271.25
Dibulatkan =Rp. 81,270.00
XIII.8.6.35 1 m2 Pasang Lantai Keramik, Uk. 30 x 30 cm
1.0000 m2 Lantai Keramik Asia 30 x 30 cm Rp. 46,200.00 =Rp. 46,200.00
10.0000 kg Semen PC Rp. 1,500.00 =Rp. 15,000.00
1.5000 kg Semen Putih Rp. 2,200.00 =Rp. 3,300.00
0.0450 m3 Pasir Pasang Rp. 93,500.00 =Rp. 4,207.50
Sub total =Rp. 68,707.50
0.6200 Oh Pekerja Rp. 35,000.00 =Rp. 21,700.00
0.3500 Oh Tukang Batu Rp. 45,000.00 =Rp. 15,750.00
0.0350 Oh Kepala Tukang Batu Rp. 50,000.00 =Rp. 1,750.00
0.0300 Oh Mandor Rp. 55,000.00 =Rp. 1,650.00
Sub Total = Rp 40,850.00
Total =Rp. 109,557.50
Dibulatkan =Rp. 109,550.00
XIII.11.6.54 1 m2 Pasang Dinding Keramik, Uk. 20 x 25 cm
1.0000 m2 Dinding Keramik Asia 20 x 25 cm Rp. 63,250.00 =Rp. 63,250.00
9.3000 kg Semen PC Rp. 1,500.00 =Rp. 13,950.00
1.9400 kg Semen Putih Rp. 2,200.00 =Rp. 4,268.00
0.0180 m3 Pasir Pasang Rp. 93,500.00 =Rp. 1,683.00
Sub total =Rp. 83,151.00
0.6000 Oh Pekerja Rp. 35,000.00 =Rp. 21,000.00
0.4500 Oh Tukang Batu Rp. 45,000.00 =Rp. 20,250.00
0.0450 Oh Kepala Tukang Batu Rp. 50,000.00 =Rp. 2,250.00
0.0300 Oh Mandor Rp. 55,000.00 =Rp. 1,650.00
Sub Total = Rp 45,150.00
Total =Rp. 128,301.00
Dibulatkan =Rp. 128,300.00
XIV.5.6.14 1 m2 Mengecat Tembok Baru
0.1000 kg Plamir Tembok Rp. 9,900.00 =Rp. 990.00
0.3600 kg Cat Tembok "Decolith" Rp. 17,000.00 =Rp. 6,120.00
Sub Total =Rp. 7,110.00
0.0200 Oh Pekerja Rp. 35,000.00 =Rp. 700.00
0.0630 Oh Tukang Cat Rp. 45,000.00 =Rp. 2,835.00
0.0063 Oh Kepala Tukang Cat Rp. 50,000.00 =Rp. 315.00
0.0025 Oh Mandor Rp. 55,000.00 =Rp. 137.50
Sub Total =Rp. 3,987.50
Total =Rp. 11,097.50
Dibulatkan =Rp. 11,090.00

200
HASIL
OBSERVASI
DAFTAR ANALISA BAHAN DAN UPAH KERJA
PEMERINTAH KOTA BLITAR TAHUN ANGGARAN 2011
(SEMESTER I)
OL.IV.6 1 m2 Pasang Rangka Atap Genteng Biasa/Prentul (Mutu Kayu Klas II)
0.0120 m3 Kayu kruing, usuk (mutu kayu klas III) Rp. 7,072,500.00 =Rp. 84,870.00
0.0036 m3 Kayu kruing, reng (mutu kayu klas III) Rp. 6,918,750.00 =Rp. 24,907.50
0.2500 kg Paku 2,5" dan Paku 4" Rp. 19,800.00 =Rp. 4,950.00
Sub Total =Rp. 114,727.50
0.1000 Oh Pekerja Rp. 35,000.00 =Rp. 3,500.00
0.1000 Oh Tukang Kayu Rp. 45,000.00 =Rp. 4,500.00
0.0100 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 500.00
0.0050 Oh Mandor Rp. 55,000.00 =Rp. 275.00
Sub Total =Rp. 8,775.00
Total =Rp. 123,502.50
Dibulatkan =Rp. 123,500.00
OL.IV.8 1 m1 Pasang Listplank Ukuran 3 x 20 cm (Mutu Kayu Klas I atau II)
0.0060 m3 Kayu Klas II (Papan Kayu Kamper 3/20) Rp. 10,250,000.00 =Rp. 61,500.00
0.1000 kg Paku 3" Rp. 19,800.00 =Rp. 1,980.00
Sub Total =Rp. 63,480.00
0.1000 Oh Pekerja Rp. 35,000.00 =Rp. 3,500.00
0.2000 Oh Tukang Kayu Rp. 45,000.00 =Rp. 9,000.00
0.0250 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 1,250.00
0.0050 Oh Mandor Rp. 55,000.00 =Rp. 275.00
Sub Total =Rp. 14,025.00

Total =Rp. 77,505.00


Dibulatkan =Rp. 77,500.00
Ukuran kompres 3/10 38,750.00
Dibulatkan =Rp. 38,750.00
OL.V.2 1 m2 Pasang Bekisting Untuk Sloof (Mutu Kayu Klas IV)
0.0400 m3 Kayu Klas IV (Papan Kayu Tahun 3/20) Rp. 2,480,500.00 =Rp. 99,220.00
0.1000 ltr Minyak Bekisting/Solar Rp. 4,500.00 =Rp. 450.00
0.3000 kg Paku 3" Rp. 19,800.00 =Rp. 5,940.00
Sub Total =Rp. 105,610.00
0.5200 Oh Pekerja Rp. 35,000.00 =Rp. 18,200.00
0.2600 Oh Tukang Kayu Rp. 45,000.00 =Rp. 11,700.00
0.0260 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 1,300.00
0.0260 Oh Mandor Rp. 55,000.00 =Rp. 1,430.00
Sub Total =Rp. 32,630.00
Total = Rp 138,240.00
Dibulatkan = Rp 138,240.00
1 m2 bekisting (dihitung 1x pakai) = Rp 138,240.00
1 m2 bekisting (dihitung 4x pakai) = Rp 34,560.00
OL.V.9 1 m2 Pasang Bekisting Kolom Praktis (Mutu Kayu Klas IV)
0.0400 m3 Kayu Klas IV (Papan Kayu Tahun 3/20) Rp. 2,480,500.00 =Rp. 99,220.00
0.4000 kg Paku 3" Rp. 19,800.00 =Rp. 7,920.00
0.1500 kg Bendrat Rp. 18,150.00 =Rp. 2,722.50
Sub Total =Rp. 109,862.50
0.3000 Oh Pekerja Rp. 35,000.00 =Rp. 10,500.00
0.3300 Oh Tukang Kayu Rp. 45,000.00 =Rp. 14,850.00
0.0330 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 1,650.00
0.0060 Oh Mandor Rp. 55,000.00 =Rp. 330.00
Sub Total = Rp 27,330.00
Total = Rp 137,192.50
Dibulatkan = Rp 137,190.00
1 m2 bekisting (dihitung 1x pakai) = Rp 137,190.00
1 m2 bekisting (dihitung 4x pakai) = Rp 34,297.50
OL.V.10 1 m2 Pasang Bekisting Balok Anak (Mutu Kayu Klas IV)
0.3500 lbr Tripleks 3 mm Rp. 60,500.00 =Rp. 21,175.00
0.0180 m3 Kayu Klas IV (Usuk Kayu Tahun 4/6) Rp. 1,947,500.00 =Rp. 35,055.00
0.0400 m3 Kayu Klas IV (Papan Kayu Tahun 3/20) Rp. 2,480,500.00 =Rp. 99,220.00
0.4000 kg Paku 3" Rp. 19,800.00 =Rp. 7,920.00
2.0000 btg Bambu Apus 6-10 x 600cm Rp. 13,200.00 =Rp. 26,400.00
Sub Total =Rp. 189,770.00

0.3200 Oh Pekerja Rp. 35,000.00 =Rp. 11,200.00


0.3300 Oh Tukang Kayu Rp. 45,000.00 =Rp. 14,850.00
0.0330 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 1,650.00
0.0060 Oh Mandor Rp. 55,000.00 =Rp. 330.00
Sub Total = Rp 28,030.00
Total = Rp 217,800.00
Dibulatkan = Rp 217,800.00
1 m2 bekisting (dihitung 1x pakai) = Rp 217,800.00
1 m2 bekisting (dihitung 4x pakai) = Rp 54,450.00
OL.VI.2 1 m1 Pasang List Eternit
1.0500 m1 List Kayu Tahun 1/4 Rp. 6,050.00 =Rp. 6,352.50
0.0900 kg Paku 1" Rp. 19,800.00 =Rp. 1,782.00
Sub Total =Rp. 8,134.50
0.0200 Oh Pekerja Rp. 35,000.00 =Rp. 700.00
0.0400 Oh Tukang kayu Rp. 45,000.00 =Rp. 1,800.00
Sub Total =Rp. 2,500.00
Total =Rp. 10,634.50
Dibulatkan =Rp. 10,630.00
OL.VI.8 1 m2 Pasang Langit-langit Eternit (1,00 x 1,00) m, Rangka Mutu Kayu Klas III
0.0120 m3 Kayu Klas III (Usuk Kayu Meranti 4/6) Rp. 5,945,000.00 =Rp. 71,340.00
0.0600 kg Paku 3" Rp. 19,800.00 =Rp. 1,188.00
1.1000 lbr Eternit Lokal Rp. 9,100.00 =Rp. 10,010.00
0.0200 kg Paku Eternit Rp. 22,000.00 =Rp. 440.00
Sub Total =Rp. 82,978.00
0.1800 Oh Pekerja Rp. 35,000.00 =Rp. 6,300.00
0.3200 Oh Tukang Kayu Rp. 45,000.00 =Rp. 14,400.00
0.0320 Oh Kepala Tukang Kayu Rp. 50,000.00 =Rp. 1,600.00
0.0090 Oh Mandor Rp. 55,000.00 =Rp. 495.00
Sub Total =Rp. 22,795.00
Total =Rp. 105,773.00
Dibulatkan =Rp. 105,770.00
OL.IX.5 1 m2 Mengecat Eternit
0.2700 kg Cat Decolith Rp. 17,000.00 =Rp. 4,590.00
Sub Total =Rp. 4,590.00
0.2250 Oh Tukang Cat Rp. 45,000.00 =Rp. 10,125.00
0.0230 Oh Kepala Tukang Cat Rp. 50,000.00 =Rp. 1,150.00
0.0080 Oh Mandor Rp. 55,000.00 =Rp. 440.00
=Rp. =Rp. 11,715.00
Total =Rp. 16,305.00
Dibulatkan =Rp. 16,300.00

224
BOW
DAFTAR ANALISA BAHAN DAN UPAH KERJA
PEMERINTAH KOTA BLITAR TAHUN ANGGARAN 2011
(SEMESTER I)
III. PEKERJAAN BONGKARAN

III.2.L.4 10 m2 Membongkar dinding tembok yang tipis, terhitung dengan membersihkan bata-batanya
2.000 Oh Pekerja Rp. 35,000.00 =Rp. 70,000.00
0.100 Oh Mandor Rp. 55,000.00 = Rp 5,500.00
Total =Rp. 75,500.00
Dibulatkan =Rp. 75,500.00
(Jikalau tidak dengan membersihkan dihitung setengahnya)
1.000 Oh Pekerja Rp. 35,000.00 =Rp. 35,000.00
0.050 Oh Mandor Rp. 55,000.00 = Rp 2,750.00
Total =Rp. 37,750.00
sehingga 1 m3 menurunkan rangka atap dari kayu menjadi =Rp. 3,775.00
Dibulatkan =Rp. 3,770.00

III.4.L.7 10 m2 Menurunkan Atap Genteng atau Sirap, Jikalau Genteng atau Sirap itu Hendak Dipakai Lagi
2.000 Oh Pekerja Rp. 35,000.00 =Rp. 70,000.00
0.100 Oh Mandor Rp. 55,000.00 = Rp 5,500.00
Total =Rp. 75,500.00
1 m2 menurunkan atap genteng / sirap =Rp. 7,550.00
Dibulatkan =Rp. 7,550.00
(Jikalau genteng atau sirap tidak dipakai lagi, dihitung 1/2 dari analis ini)
1.000 Oh Pekerja Rp. 35,000.00 =Rp. 35,000.00
0.050 Oh Mandor Rp. 55,000.00 = Rp 2,750.00
Total =Rp. 37,750.00
sehingga 1 m2 menurunkan genteng atau sirap menjadi =Rp. 3,775.00
Dibulatkan =Rp. 3,770.00

222
XV. KELOMPOK BAHAN BANGUNAN, KELISTRIKAN, ANALISA BAHAN DAN UPAH KERJA

A. DAFTAR HARGA SATUAN BAHAN BANGUNAN

HARGA TRIWULAN I
NO. JENIS BAHAN UKURAN SATUAN
(Rp)
1 2 3 4 5

I BAHAN PASANGAN DAN


CAMPURAN BETON
1 Batu kali belah 10/ 15, 15/20 m3 132,000.00
2 Batu kali pecah 5/7 m3 145,200.00
3 Batu kali pecah 4/6 m3 148,500.00
4 Batu kali pecah 3/5 m3 177,100.00
5 Batu kali pecah 2/3 m3 187,000.00
6 Batu kali pecah Crusher 1/2 m3 192,500.00
7 Batu kali pecah Crusher 1/1 m3 203,500.00
8 Batu kali pecah Crusher 0,5/1 m3 211,200.00
9 Pasir beton/cor - m3 99,000.00
10 Pasir pasang - m3 93,500.00
11 Pasir urug - m3 71,500.00
12 Tanah urug biasa - m3 66,000.00
13 Batu merah klas I - bh 550.00
14 Batu merah klas II - bh 500.00
15 Semen Gresik (PC Gresik) 50 kg zak 75,000.00
16 Semen Gresik (PC Gresik) 40 kg zak 60,500.00
17 Semen Tiga Roda 50 kg zak 74,000.00
18 Semen Tiga Roda 40 kg zak 59,400.00
19 Semen putih 40 kg zak 88,000.00
20 PC super nut - kg 12,100.00
21 Glass block bening 20 x 20 bh 22,000.00
22 Glass block buram 20 x 20 bh 22,000.00

II BAHAN KUZEN KAYU DAN


KERANGKA ATAP
1 Kayu kamper, balok (mutu kayu klas II) 6/12, 6/15, 8/12 m3 9,737,500.00
2 Kayu kamper, papan (mutu kayu klas II) 2/20, 3/20, 3/25 m3 10,250,000.00
3 Kayu kamper, usuk (mutu kayu klas II) 4/6, 5/7 m3 9,430,000.00
4 Kayu kamper, reng (mutu kayu klas II) 2/3, 3/5 m3 9,225,000.00
5 Kayu meranti, balok (mutu kayu klas III) 6/12, 6/15, 8/12 m3 5,945,000.00
6 Kayu meranti, papan (mutu kayu klas III) 2/20, 3/20, 3/25 m3 6,355,000.00
7 Kayu meranti, usuk (mutu kayu klas III) 3/5,4/6,5/7 m3 5,945,000.00
8 Kayu meranti, reng (mutu kayu klas III) 2/3, 3/5 m3 5,330,000.00
9 Kayu bekisting, papan (mutu kayu klas IV) 3/20-200 m3 1,400,000.00
10 Kayu bekisting, usuk (mutu kayu klas IV) 4/6-200 m3 1,004,500.00
11 Kayu tahun, papan (mutu kayu klas IV) 2/20, 3/20, 3/25 m3 2,480,500.00
12 Kayu tahun, usuk (mutu kayu klas IV) 3/5, 4/6, 5/7 m3 1,947,500.00
13 Kayu gelam (mutu kayu klas IV) 10-12 x 300 cm btg 20,500.00

192
HARGA TRIWULAN I
NO. JENIS BAHAN UKURAN SATUAN
(Rp)
1 2 3 4 5
14 Kayu kruing, balok (mutu kayu klas III) 6/12, 6/15, 8/12 m3 7,328,750.00
15 Kayu kruing, papan (mutu kayu klas III) 2/20, 3/20, 3/25 m3 8,251,250.00
16 Kayu kruing, usuk (mutu kayu klas III) 4/6, 5/7 m3 7,072,500.00
17 Kayu kruing, reng (mutu kayu klas III) 2/3 m3 6,918,750.00
18 List kayu tahun 1/4 m1 6,050.00
19 List kayu profil 4/4 m1 8,250.00
20 List kayu profil 5/5 m1 8,800.00
21 Bambu Jawa bongkotan 10-12 x 300cm btg 17,600.00
22 Bambu ori 10-12 x 600cm btg 24,200.00
23 Bambu apus 6-10 x 600cm btg 13,200.00
24 Gedek guling - m2 7,150.00

193
HARGA TRIWULAN I
NO. JENIS BAHAN UKURAN SATUAN
(Rp)
1 2 3 4 5
III BAHAN PENUTUP ATAP DAN PLAFON
1 Harflek 4 mm 40 x 200 cm lbr 16,940.00
2 Harflek 4 mm 50 x 200 cm lbr 19,250.00
3 Harflek 4 mm 60 x 200 cm lbr 23,100.00
4 Woodplek tebal 9 mm 30x400 lbr 111,100.00
5 Woodplek tebal 9mm 20x300 lbr 53,350.00
6 Eternit (lokal) - lbr 9,100.00
7 Eternit (kerang) - lbr 13,200.00
8 Eternit (Gresik) - lbr 16,500.00
9 Gypsum tebal 9 mm 122 x 244 lbr 84,700.00
10 Gypsum tebal 12 mm 122 x 244 lbr 93,500.00
11 List Gypsum 15 x 200 cm btg 26,400.00
12 List Gypsum 10 x 200 cm btg 18,150.00
13 Genteng flam press Jawa/lokal - bh 1,400.00
14 Genteng kaca (model karang pilang) - bh 10,450.00
15 Genteng karang pilang/wisma - bh 4,800.00
16 Genteng bubung karang pilang/wisma - bh 9,600.00
17 Genteng bubung Jawa/lokal - bh 4,400.00
18 Genteng Bambe - bh 5,500.00
19 Genteng bubungan Bambe - bh 9,900.00
20 Genteng prentul ex.Trenggalek - bh 1,600.00
21 Genteng bubungan prentul ex. Trenggalek - bh 4,200.00
13 Genteng Mantili ex Trenggalek - bh 2,000.00
14 Genteng Bubung Mantili ex. Trenggalek - bh 4,500.00
15 Genteng Beton - bh 2,400.00
16 Genteng Bubung Beton - bh 4,800.00
17 Genteng Kanmuri Glasur - bh 7,700.00
18 Genteng Kanmuri Bubung Glasur - bh 20,350.00
19 Genteng KIA Glasur - bh 7,700.00
20 Genteng KIA Bubung Glasur - bh 20,350.00
21 Genteng Impresso Glasur - bh 7,150.00
22 Genteng Bubung Impresso Glasur - bh 19,250.00
15 Seng Talang BJLS 30 l = 90 cm m1 51,400.00
16 Seng Talang BJLS 27 l = 90 cm m1 36,300.00
17 Seng Talang BJLS 27 l = 60 cm m1 32,670.00
18 Seng Talang BJLS 30 l = 45 cm m1 26,400.00
19 Seng Datar BJLS 30 80 x 180 cm lbr 88,000.00
20 Seng Gelombang BJLS 40 80 x 180 cm lbr 112,000.00
21 Seng Gelombang BJLS 30 80 x 180 cm lbr 88,500.00
22 Seng Gelombang BJLS 30 80 x 300 cm lbr 145,200.00
23 Seng Gelombang BJLS 30 80 x 150 cm lbr 75,000.00
20 Seng Datar BJLS 27 80 x 180 cm lbr 73,700.00
21 Karet Talang l = 60 cm m1 12,100.00
22 Karet Talang l = 90 cm m1 15,200.00
23 Fiberglass "Kano Flash" l = 92 cm. m1 67,650.00

194
HARGA TRIWULAN I
NO. JENIS BAHAN UKURAN SATUAN
(Rp)
1 2 3 4 5
21 Teakwood tebal 3 mm ( 4' x 8' ) lbr 127,000.00
22 Teakwood tebal 3 mm 90 x 210 cm lbr 90,750.00
23 Tripleks tebal 9 mm ( 4' x 8' ) lbr 163,350.00
24 Tripleks tebal 3 mm ( 4' x 8' ) lbr 60,500.00
25 Plywood tebal 6 mm ( 4' x 8' ) lbr 108,900.00
26 Plywood tebal 4 mm 90 x 210 cm lbr 75,350.00
27 Plywood tebal 4 mm ( 4' x 8' ) lbr 90,750.00
28 Plywood tebal 2 mm ( 4' x 8' ) lbr 84,700.00

IV BAHAN BESI/LOGAM
1 Besi begel/baut - kg 19,250.00
2 Besi beton polos - kg 10,000.00
4 Besi plat aluminium tebal 2 mm 4' x 8' lbr 726,000.00
5 Besi plat bordes tebal 3 mm 4' x 8' lbr 1,331,000.00
6 Besi plat strip panjang tebal 3 mm (30x6000)mm m1 42,350.00
7 Kawat ikat beton (bendrat) - kg 18,150.00
10 Pintu Alumunium (kualitas II) 70 x 200 cm lbr 299,750.00
13 Slimar alumunium - m1 125,000.00
14 Sunscreen Alumunium - m1 85,000.00
15 Pagar besi ulir komplit dengan mainan - m2 632,500.00
16 Pintu pagar besi ulir komplit dengan mainan - m2 737,000.00
17 Rolling door aluminium - m2 709,500.00
18 Pintu plat harmonika - m2 1,265,000.00
19 Atap twin lite rangka pipa stainlis steel - m2 740,000.00
20 Atap twin lite rangka pipa besi - m2 605,000.00
21 Teralis besi - m2 498,300.00
22 Teralis aluminium - m2 623,150.00
23 Railling stainless steel 2" m2 898,260.00
24 Kusen Pintu Aluminium Silver "HC" 4 / 12 m1 106,400.00
25 Kusen Pintu Aluminium Coklat "YKK" 5 / 10 m1 126,700.00
26 Kusen Jendela Aluminium Silver "HC" 4 / 12 m1 99,800.00
27 Kusen Jendela Aluminium Coklat "YKK" 5 / 10 m1 126,700.00
28 Waterstop "Maspion" 250 mm m1 206,800.00
29 Sealent - tube 41,250.00

195
HARGA TRIWULAN I
NO. JENIS BAHAN UKURAN SATUAN
(Rp)
1 2 3 4 5
V BAHAN LANTAI
1 Paving stone per segi abu-abu, cetak kering t = 6 cm m2 44,550.00
2 Paving stone per segi abu-abu, cetak basah t = 6 cm m2 63,800.00
5 Paving stone segi 6 abu-abu, cetak kering t = 6 cm m2 45,100.00
6 Paving stone segi 6 merah, cetak basah t = 6cm m2 61,600.00
7 Tegel keramik 10 x 20 m2 58,300.00
8 Tegel keramik polos 15 x 15 m2 46,200.00
10 Tegel keramik, Asia 20 x 25 m2 63,250.00
11 Tegel keramik, berserat 30 x 30 m2 59,400.00
12 Tegel keramik putih, Asia 30 x 30 m2 46,200.00
13 Tegel keramik, kasar 20 x 20 m2 55,000.00
14 Tegel keramik, Super Milan 40 x 40 m2 73,700.00
16 Tegel keramik, Mulia 30 x 30 m2 45,100.00
18 Tegel keramik, Arwana 30 x 30 m2 49,500.00
19 Tegel keramik, Asia 30 x 30 m2 45,100.00
20 Tegel keramik, Classic 30 x 30 m2 60,500.00
23 Tegel keramik, Granito 30 x 30 m2 209,000.00
24 Tegel keramik, Granito 40 x 40 m2 280,500.00
25 Tegel keramik Granite Black 40 x 40 m2 292,600.00
26 Tegel keramik Granite Polish 40 x 40 m2 257,000.00
27 Tegel keramik Model Granito Hitam 60 x 60 m2 140,000.00
28 Ubin keramik artistik 5 x 20 bh 11,550.00
29 Ubin keramik artistik 10 x 20 bh 20,900.00
30 Ubin keramik artistik 15 x 15 m2 49,500.00
31 Ubin keramik artistik 20 x 20 m2 56,650.00
32 List Keramik/Border 10 x 20 bh 11,000.00
33 Stepnoiseng 10x 40 bh 20,000.00
34 Stepnoiseng 7 x 30 bh 15,000.00

VI BAHAN PENGECATAN
1 Cat besi Emco tanda Bintang - kg 72,000.00
2 Cat kayu Emco tanda Bintang - kg 72,000.00
3 Meni besi/kayu, cap Pedang - kg 21,000.00
4 Thinner A spesial "Altech" - ltr 28,000.00
5 Thinner A biasa "Power" - ltr 22,000.00
6 Thinner B spesial - ltr 11,000.00
7 Minyak cat/afduner - ltr 11,000.00
8 Cat tembok eksterior Mowilex - ltr 92,400.00
9 Cat tembok Alcabond - kg 27,500.00
10 Cat tembok Alcaplast - kg 8,800.00
11 Cat tembok Wallsealer - kg 19,800.00
12 Cat tembok Vinylex - kg 20,350.00
13 Cat tembok Decolith - kg 17,000.00
14 Cat tembok Metrolith - kg 19,800.00
15 Cat tembok Cathylac - kg 19,800.00

196
HARGA TRIWULAN I
NO. JENIS BAHAN UKURAN SATUAN
(Rp)
1 2 3 4 5
16 Cat tembok Cendana - kg 17,600.00
17 Cat genteng Matex - kg 48,400.00
18 Kertas gosok - lbr 5,000.00
19 Plamur tembok - kg 9,900.00
20 Plamur kayu - kg 20,900.00
21 Plamur besi - kg 35,200.00
22 Lem Rajawali untuk Kayu - kg 40,000.00
23 Lem Rajawali untuk Tembok - kg 18,100.00
24 Lem kayu khusus (Vinyl) - kg 15,800.00
25 Soda Api - kg 16,500.00
26 Teak Oil - ltr 29,700.00
27 Residu - ltr
27 Kuas Eterna 3" bh 11,000.00
28 Kuas Eterna 4" bh 16,500.00
29 Kuas Eterna 5" bh 20,900.00
30 Kalsium - kg 1,300.00
31 Coating - kg 44,000.00

VII BAHAN PENGGANTUNG DAN PENGUNCI


1 Engsel H "Stayer" 4" set 12,100.00
2 Engsel Kuningan arch asli "Elitech" 4" set 18,700.00
3 Engsel jendela (kupu - kupu) 3" set 11,000.00
4 Engsel pintu "UNION" 4" bh 19,800.00
5 Engsel jendela "UNION" 3" bh 16,500.00
6 Espanyolet kualitas I - set 48,400.00
7 Grendel AEG "ELT" - bh 31,900.00
8 Grendel biasa (besar) 8" bh 9,900.00
9 Grendel biasa (kecil) 3" bh 5,500.00
10 Grendel kuningan/krom kecil "Belucci" 4" bh 23,100.00
11 Grendel tanam kuningan besar "Cavel" 60 cm set 246,400.00
12 Kunci gembok besar, Globe 40 mm bh 31,350.00
13 Kunci gembok sedang, Globe 30 mm bh 20,900.00
14 Kunci tanam (808) - bh 9,350.00
15 Kunci tanam cap KUDA (2x putar) besar - bh 84,700.00
16 Kunci tanam "SES" besar (tanpa handel) - bh 159,500.00
17 Kunci tanam antik "Miller" (dengan handel) - bh 245,300.00
18 Kunci tanam KM/WC "Miller" - bh 85,800.00
19 Kunci silinder "SES" - bh 199,650.00
20 Kunci slot merk "SES" (dengan handel) - bh 425,700.00
21 Kunci slot 2 putaran "YALE" (dengan handel) - bh 139,700.00
22 Kunci slot 2 putaran "CAVEL" (dengan handel) - bh 302,500.00
23 Kunci lemari, Wing - bh 7,700.00
24 Hak angin biasa 8" set 7,200.00
25 Hak angin 4 mm (lurus) - set 14,300.00
26 Hak angin (sikutan) "SES" - set 33,000.00

197
HARGA TRIWULAN I
NO. JENIS BAHAN UKURAN SATUAN
(Rp)
1 2 3 4 5
27 Hak angin lurus (bisa disetel maju/mundur) "SES" - set 82,500.00
28 Pegangan pintu (model standar) p = 20 cm bh 74,800.00
29 Spring knip "Picasso" - bh 19,800.00
30 Door closer "Belucci" - bh 233,200.00
31 Door stopper "Belucci" - bh 49,500.00
32 Rel pintu dorong, biasa - btg 116,600.00
33 Rel pintu dorong, J4 SES - btg 225,500.00

VIII BAHAN SANITASI


1 Slang spiral saluran kran wastafel - set 46,200.00
2 Kloset duduk porselin komplit (INA) - bh 1,210,000.00
3 Kloset duduk porselin komplit (KIA) - bh 1,320,000.00
4 Kloset duduk porselin komplit (TOTO) - bh 1,870,000.00
5 Kloset jongkok porselin (INA) - bh 137,500.00
6 Kloset jongkok porselin (TOTO) - bh 211,200.00
7 Kloset jongkok teraso - bh 33,000.00
8 Kran air stainless steel 1/2" bh 48,400.00
9 Kran air stainless steel 3/4" bh 52,800.00
10 Kran air (DUPONT) 1/2" bh 188,650.00
11 Kran air kuningan 1/2" bh 30,250.00
12 Kran shower "Toto" 3/4" set 484,000.00
13 Septic Tank (10 pemakai) dan Sumur - bh 5,250,000.00
Peresapan (dalam 3,00 m)
14 Watermur besi 3/4" bh 9,350.00
15 Wastafel warna muda "ITO" - bh 316,800.00
16 Wastafel warna tua "ITO" - bh 378,400.00
17 Rol TBA (seal tape) Jumbo - rol 12,100.00
18 Siphon Washer, kelas sedang plastik - set 46,200.00
19 Water drain dan assesories - set 36,300.00
20 Bak mandi fiberglass 0,5 m3 bh 264,000.00
21 Bak cuci piring stainless steel, besar (double) - bh 550,000.00
22 Bak cuci teraso - bh 147,400.00
23 Tempat sabun keramik "Sotento" - bh 30,250.00
24 Urinoir "INA" (komplit) - set 1,089,000.00
25 Floor drain stainless steel "Onde" - bh 70,400.00
26 Kurasan (putih) stainless steel - bh 45,650.00
27 Bak mandi porselin 60 x 60 cm bh 466,400.00
28 Tandon air fiberglass "Penyu" 550 ltr bh 943,800.00
29 Pompa tangan "Dragon" - bh 305,800.00
30 Hand shower plastik (termasuk slang) - set 201,300.00
31 Wall shower "Toto" - set 335,500.00
32 Pompa air "Shimizu 125 W" - bh 431,200.00
33 Pompa air "Sanyo 125 W" - bh 550,000.00

IX BAHAN JENIS KACA

198
HARGA TRIWULAN I
NO. JENIS BAHAN UKURAN SATUAN
(Rp)
1 2 3 4 5
1 Kaca polos t = 3 mm m2 54,450.00
2 Kaca polos t = 5 mm m2 66,550.00
3 Kaca polos t = 9 mm m2 133,100.00
4 Kaca rayban t = 5 mm m2 78,650.00
5 Kaca es/buram t = 5 mm m2 121,000.00
6 Krepyak kaca nako 15 x 70 cm (includ kerangka) t = 5 mm daun 30,250.00
7 Kaca buram t = 3 mm m2 90,750.00
8 Kaca cermin t = 3 mm m2 162,200.00

X BAHAN BETON CETAKAN


1 Beton roster klingker warna merah 10 x 20 cm bh 8,800.00
2 Buis beton (p = 100 cm) 15 cm bh 44,550.00
3 Buis beton (p = 100 cm) 20 cm bh 55,000.00
4 Buis beton (p = 100 cm) 30 cm bh 74,800.00
5 Buis beton (p = 100 cm) 40 cm bh 83,600.00
6 Buis beton (p = 50 cm) 50 cm bh 85,800.00
7 Buis beton (p = 50 cm) 60 cm bh 73,700.00
8 Buis beton (p = 50 cm) 80 cm bh 94,600.00
9 Buis beton (p = 50 cm) 100 cm bh 114,400.00
10 Buis Beton U (p = 100 cm) 15 cm bh 38,500.00
11 Buis Beton U (p = 100 cm) 20 cm bh 43,450.00
12 Buis Beton U (p = 100 cm) 30 cm bh 53,900.00
13 Got talang R 15 (segmen) - bh 30,800.00
14 Got talang R 25 (segmen) - bh 52,800.00

XI BAHAN PIPA PVC


1 Pipa PVC tipe AW "Maspion" 1/2" - 400 btg 24,200.00
2 Pipa PVC tipe AW "Maspion" 5/8" - 400 btg 28,600.00
3 Pipa PVC tipe AW "Maspion" 3/4" - 400 btg 31,350.00
4 Pipa PVC tipe AW "Maspion" 1" - 400 btg 41,250.00
5 Pipa PVC tipe AW "Maspion" 2" - 400 btg 105,600.00
6 Pipa PVC tipe AW "Maspion" 3" - 400 btg 181,500.00
7 Pipa PVC tipe AW "Maspion" 4" - 400 btg 272,800.00
8 Pipa PVC tipe AW "Maspion" 5" - 400 btg 423,500.00
9 Pipa PVC "Maspion" tipe D 2" - 400 btg 51,700.00
10 Pipa PVC "Maspion" tipe D 3" - 400 btg 105,600.00

199
HARGA TRIWULAN I
NO. JENIS BAHAN UKURAN SATUAN
(Rp)
1 2 3 4 5
11 Pipa PVC "Maspion" tipe D 4" - 400 btg 148,500.00
12 Pipa PVC "Maspion" tipe D 5" - 400 btg 234,300.00
13 Lem PVC "Wavin" - tube 8,800.00
14 Keni PVC tipe AW 1/2" bh 1,500.00
15 Keni PVC tipe AW 3/4" bh 2,200.00
16 Keni PVC tipe AW 2" bh 9,900.00
17 Keni PVC tipe AW 3" bh 14,850.00
18 Keni PVC tipe AW 4" bh 22,000.00
19 Keni PVC tipe AW 5" bh 28,600.00
20 Klem PVC - bh 4,950.00
21 Talang PVC U "Maspion" 400 cm bh 96,800.00
22 Talang PVC U 400 cm bh 78,650.00
23 Clam Talang PVC U - bh 6,600.00
24 Shock Talang PVC U - bh 6,600.00
25 Tutup Talang PVC U - bh 6,600.00
26 Corong Talang PVC U - bh 18,150.00

XII BAHAN JENIS PAKU


1 Paku asbes gelombang (paku pancing) - bh 2,750.00
2 Paku kayu 1" kg 19,800.00
3 Paku kayu 1,5" - 2" kg 19,800.00
4 Paku kayu 2,5" - 3" kg 19,800.00
5 Paku kayu 4" kg 17,000.00
6 Paku payung (paku seng gelombang) - kg 25,000.00
7 Paku sekrup 1" dos 12,100.00
8 Paku sumbat - dos 22,000.00
9 Paku triplek/eternit - kg 22,000.00
10 Paku beton 5 cm bh 550.00
11 Paku kalsiboard - kg 30,250.00

XIII BAHAN PERALATAN LISTRIK


1 Fiting plafon - set 9,900.00
2 T doos PVC - bh 1,650.00
3 Isolator kecil - bh 1,450.00
4 Stop kontak (Broco) - bh 25,300.00
5 Skakelar tunggal (Broco) - bh 25,300.00
6 Skakelar ganda (Broco) - bh 33,000.00
7 Stop kontak dan skakelar (Broco) - bh 33,000.00
8 Skakelar / hendel pemindah arus - bh 9,900.00
9 Zekring lengkap dengan box - bh 80,000.00
10 Las doof - bh 25,300.00
11 Panel box - bh 25,300.00
12 Meinswitch - bh 33,000.00
13 Zekring MCB thermis 10 - 16 Amp. - bh 38,500.00
14 Zekring MCB thermis 10 Amp. - bh 45,000.00

200
HARGA TRIWULAN I
NO. JENIS BAHAN UKURAN SATUAN
(Rp)
1 2 3 4 5
15Stater lampu TL - bh 88,000.00
16Lampu pijar 25,40,75 / 220 V "Philips" - bh 6,600.00
17Bola lampu Armateur "Philips" 250 watt bh 66,000.00
18Lampu hemat energi 18 W / 220 V (Philips) - bh 38,500.00
19Lampu hemat energi 18 W / 220 V (Osram) - bh 31,900.00
20Lampu TL 20 W / 220 V, komplit balast - bh 92,400.00
(Philips)
21 Lampu TL 40 W / 220 V, komplit balast - bh 165,000.00
(Philips)
22 Kabel NYM. 2 x 2,5 - m1 11,000.00
23 Kabel NYY. 1 x 2,5 - m1 7,700.00
24 Kabel twisted Indonesia 3 x 70 x 50 mm2 m1 7,150.00
25 Kabel twisted multi kabel m1 7,150.00
26 Instalasi listrik - titik 150,000.00
27 Penangkal Petir Lengkap (2 Spit), tinggi 10 m - unit 2,420,000.00
(Tidak termasuk izin dari Depnaker)
XIV TANAMAN UNTUK TAMAN
1 Tanaman Pucuk Merah - bh 90,000.00
2 Tanaman Palem Ekor Tupai - bh 312,500.00
3 Tanaman Dadap Merah - bh 62,500.00
4 Tanaman Kana jepang - bh 16,500.00
5 Rumput gajah - bh 11,000.00
XV BAHAN BBM DAN ALAT BERAT
1 Bensin - ltr 4,500.00
2 Solar - ltr 4,500.00
3 Minyak tanah - ltr 5,500.00
4 Oli mesin Mesran - ltr 33,000.00
5 Minyak pelumas - ltr 37,400.00
Sumber data : Hasil Survey Dinas Pekerjaan Umum Daerah Kota Blitar, Asosiasi Profesi Kota Blitar, dan Badan
Pusat Statistik (BPS) Kota Blitar
Catatan :
1. Harga diatas berlaku di Kota Blitar
2. Harga diatas sudah termasuk pajak (PPN 10%) serta biaya umum dan keuntungan yang wajar (15%)

201
XV. KELOMPOK BAHAN BANGUNAN, KELISTRIKAN, ANALISA BAHAN DAN UPAH KERJA

B. DAFTAR UPAH KERJA HARIAN

HARGA TRIWULAN I
NO. JENIS BAHAN UKURAN SAT.
(Rp)
1 2 3 4 5

1 MANDOR 8 jam/hari Org/hr 55,000.00


2 KEPALA TK. BATU 8 jam/hari Org/hr 50,000.00
3 KEPALA TK. KAYU 8 jam/hari Org/hr 50,000.00
4 KEPALA TK. BESI 8 jam/hari Org/hr 50,000.00
5 KEPALA TK. CAT 8 jam/hari Org/hr 50,000.00
6 KEPALA TK. LISTRIK 8 jam/hari Org/hr 52,000.00
7 KEPALA TK. PIPA 8 jam/hari Org/hr 50,000.00
8 TUKANG BATU 8 jam/hari Org/hr 45,000.00
9 TUKANG KAYU 8 jam/hari Org/hr 45,000.00
10 TUKANG BESI 8 jam/hari Org/hr 45,000.00
11 TUKANG CAT 8 jam/hari Org/hr 45,000.00
12 TUKANG PLITUR 8 jam/hari Org/hr 45,000.00
13 TUKANG ASPAL 8 jam/hari Org/hr 45,000.00
14 TUKANG PIPA 8 jam/hari Org/hr 45,000.00
15 TUKANG LISTRIK 8 jam/hari Org/hr 47,000.00
16 TUKANG GALI TANAH 8 jam/hari Org/hr 40,000.00
17 PENJAGA MALAM 8 jam/hari Org/hr 40,000.00
18 MASINIS 8 jam/hari Org/hr 40,000.00
19 PEMBANTU MASINIS 8 jam/hari Org/hr 35,000.00
20 MEKANIK 8 jam/hari Org/hr 45,000.00
21 PEMBANTU MEKANIK 8 jam/hari Org/hr 40,000.00
22 OPERATOR 8 jam/hari Org/hr 45,000.00
23 PENGEMUDI/SOPIR 8 jam/hari Org/hr 45,000.00
24 PENJAGA API 8 jam/hari Org/hr 40,000.00
25 PEMBANTU TUKANG / PEKERJA 8 jam/hari Org/hr 35,000.00
26 PEKERJA TAK TERLATIH 8 jam/hari Org/hr 32,000.00

Sumber data : Hasil Survey Dinas Pekerjaan Umum Daerah Kota Blitar, Asosiasi Profesi Kota Blitar, dan Badan
Pusat Statistik (BPS) Kota Blitar
Catatan :
1. Upah kerja diatas berlaku di Kota Blitar
2. Upah kerja diatas sudah termasuk pajak (PPh maks. 3,0%)

Blitar, Agustus 2009

Mengetahui, Dibuat oleh,


KEPALA DINAS PEKERJAAN UMUM TIM PENYUSUN HSBU
DAERAH KOTA BLITAR DINAS PEKERJAAN UMUM
DAERAH KOTA BLITAR
Koordinator,

196
EKOSAPTO SOFIASUSENO, ST Ir. ERNA SANTI, MT
Pembina Penata Tingkat I
NIP. 19540629 198212 1 001 NIP. 19670516 199803 2 005

197

Você também pode gostar