Escolar Documentos
Profissional Documentos
Cultura Documentos
Design cost estimation is the monetary description of the costs associated to the plant that is
based on fixed and working capital. Fixed Capital is the total cost required to erect a full
functional plant ready to start up. This is the cost paid to install the plant with its equipment
and eventually this will end up as the scrap value after the end of the project life span.
Working Capital is the additional funds required for the process continuation once it is started
up to the point of income generation. Total investment required for the plant design is the
sum of fixed and working capital.
At the initial stages of the designing, a rough but adequate financial proposal is required. Due
to the existence of several unknown factors a well-defined and perfectly accurate estimation
could not be practically done. According to sources available, it was found that at the early
stages of the design, in other words during the flow sheet stage, capital cost calculations is
done preliminary with an accuracy of around 30% (Sinnott, Coulson & Richardson's
Chemical Engineering Volume 6 (Chemical Engineering Design), 1999).
The estimation of capital cost in the section that follows is based on rapid capital cost
estimation methods such as historical cost analysis and factorial method of cost calculations.
Accuracy of these estimations is highly dependent on the stage of the plant design and
available data of the same. The estimation has been done based on data available at this stage
and approximations have been made to approximate unknowns based on certain sources.
Note: It should be pointed out that cost calculations have been rounded up to the nearest whole
number (or nearest Indian Rupees ). What is presented in this chapter is for the most part, a
summarized version of the calculations along with the approach taken in calculation along
with justifications and assumptions made. Appendix I should be referred for MS Excel
calculation sheets.
2.1.2 Estimation of total initial investment
1 =2 (2 ) (1.1)
1
While the above relation is regarded as being a rough guide for most chemical manufacturing
plants, a chart was obtained that was specifically applicable for Sulfuric acid which had
indicated the relationship of plant fixed capital cost with capacity that is extracted and
provided below (Sinnott, Coulson & Richardson's Chemical Engineering Volume 6 (Chemical
Engineering Design), 1999).
Capital cost vs capacity relationship for Sulfuric acid plants (Garrett (1989))
Plant capacity: As established form above calculations that 120MTPD of raw sulphur is
required to produce 330MTPD of sulphuric acid at (98.8% concentration)
Since the graph in Figure 2.1 that is used to estimate the plant cost is based on tons (US)
where 1 MT = 1.10231 tons, the above capacity is equivalent to 363.76tons/day
CEPCI for 1989 was approximated as 350.0 while 2015 index was obtained as 556.0
(Chemical Engineering Plant Cost Index (averaged over year)).
2015
Now, Cost in year 2015 = cost 1989 ( )
1989
556
= 5106 (350) = 7.95106 USD
Based on the indications in the graph the correlation seems to be based on plants in the
India. Then, the capital cost for 2017 should be calculated according to the average
inflation rates of the India.
Effective interest rate ( ) for the year 2017 from the data given till May was found to
be1.52%.
Interest rate (r) till June 2017,
= (1 + ) , n= 2 (till June, for the first half of the year 2017)
= 0.0152= (1+r) 2
F = P(1 + )
The total investment required initially can be estimated based on the approximations made
above:
Note: It was assumed throughout this section that the number of working days per year was
300 (i.e. 25 days a month).