Ref.No.cHN/Poc.Tripping/C-42t QO OS 7g Date: 17 ffO.r^t?-


EVENT ANALYSIS REPORT v curu
UNIT NO : 5 ITPS: Chandrapur Super Thermal Power Station Unit Capacity: 500 MW
1. *HO Code: Station Code: CSTPS U5 Time- Date- No. of days from last
T15 2014-15 11 :01 Hrs 18/LUZAL4 sync.:- 89.40

Last Overhaul (AOH) synchronisation Date 3110812013 474.5 Days 1.30 Years
2. Operating conditions at the time of Event '-
Load MW Coal Cycles in service Oil Suppoft
36s A,B,D,G,H NiI
3. Nature of Event : Unit tripped on "Loss of Fuel" Indication (T&IC problem)

4. Name of First Up, Main Protections & protection on which GCB tripped:
Boiler tripped on "Loss of Fuel" protection, Turbine tripped on interlock, Generator lockout relay U,l32G operated.

5 A) Observations :-
Unit was running at 365 MW load with coal mill A,B,D,G & H in seruice. At 11:01 Hrs, Suddenly all running coal mills
tripped thereby tripping all the coal feeders and boiler tripped on "Loss of Fuel" Indication. PA header pressure was
normal.

5 B) Remedial Action/work done :-


FSSS supply & both power supply checked found healthy. No faulty indication found on processor card.
Communication poert found active. Power supply changeover trial taken and found healthy. Boiler lightup activities
started.
6. Root Cause Analysis :-
There might be malfunctioning of program in processor card.

7. Preventive action suggested (Shoft Term) :- Nil

8. Preventive action suggested (Long Term) :-


l)Throughout checking of all connections, processors and control cards will be carried out in available opportunity.
2) Program in processor card shall be reloaded.

9. Similar event occurred last time: - Nil u# -- Time: -- Date: ---

9A. Implementation Status of Long Term/Shod Term measures stated at Sr No 9:-


ShortTerm: Nil
Long Term: Nil

10. Boiler lighted up Time - 12:00 Hrs Date- LBlL2l20L4


11. T-A Set Synchronised Time - L4:02 Hrs Date- LBlLZlz}l4
L2. Remark :- Nil

)
chief ffi(o&M)
CSTPSXhandrapur.

13. Recomendations of Works Section:


1. Procurement/Replacement Plan:
2. Operational Error:
3. Delay in Maintenance:
4. Delay in bringing back the Unit:
5. Training of Staff:
6. Whether remedial action is completed satisfactory & point is ctosed :

cElDy C E (Works)